underground utility location & sue...cardno, inc. director of utility market & practice...
TRANSCRIPT
Underground Utility Location & SUE
Jim Anspach, P.G. F.ASCE
Cardno, Inc.Director of Utility Market & Practice Development
35+ Million Miles of Underground Utilities in the US and Counting
US MAJOR OIL & GAS TRANSMISSION PIPELINE NETWORK
Records for legacy utilities are not comprehensive nor detailed/accurate
enough for project engineering purposes
Since Time Immortal, Surveyors have been recording visible utility features
on project maps• Some utility record
investigation?
• Connect the dots?
• More recently, call One-Call?
But, we don’t want to take responsibility for things we can’t see or measure
PLAN NOTES
1. Engineer and Surveyor take no responsibility for the accuracy and completeness of the utility information shown on these plans.
2. Utilities are depicted on these plans from records and visual observation. It is the responsibility of the contractor to verify all utilities before construction.
Incomplete and inaccurate maps of underground utilities between the structures lead to:
• Project construction surprises
• Delays
• Re-Design costs
• Damages
• Claims
• Change Orders
Pre 1980• One-Call just starting• Few devices for finding utilities• Few firms were mapping utilities• Utility Owners did “locating” for their own maintenance/repair
purposes• Finding Utilities was considered an “Art” or WITCHCRAFT
1979How Deep is that Utility?
• WGL Lawyer told employees they could only say “It’s So Deep”
• Ford Bacon Davis used Vacuum Trucks for anode installation
• Where is that utility in the 8” X 8” hole?
1983 Media General Contract
• Find and mark all utilities
• Expose all utilities in road crossings
1984 VDOT Project
• $1M in savings reported to FHWA
• $7M in savings reported “off-the-record”
• Markings surveyed by VDOT survey crews
Significant Advances in SUE
• Integrated Survey (1985)• WGL Union Stoppage (1986)• MD WSSC “Seal” requirement (1987)• CNA PL Insurance (1988)• VDOT Court Case (1989)• OR – 1st Design Ticket (in lieu of records)• FHWA Road Trip and Trials (1991)• “SUE” Association Talks Begin (1995)• ASCE 38 started (1996)
Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data
C-I /ASCE 38-02
“Engineer shall show utilities…”
Utility Investigations Vary:
> Records
> Visual Correlations
> Surface Geophysics
> Exposures and
Certified Record
Drawings
> Best Guess
But Depictions May Not:
> Utilities all shown on
the design plans the
same regardless of
method of
investigation.
Purpose of the Standard
– To assist owners and engineers in developingan unambiguous comprehensive scope ofwork concerning collecting and depictingutility information on documents.
– To standardize how utilities are portrayed ondocuments.
– And most importantly, to standardize anattribute for utility information that indicatesits reliability and quality (utility quality levelattribute).
These utility quality levels are used
– By Engineers – to make decisions on designing around existing utilities versus relocating them and to avoid redesign
– By Contractors – to determine construction bids and excavation methods
– By Project Owners – to retain a reliable map for future maintenance, security, or other needs
– By Courts – to allocate responsibility for errors and omissions and damages
“Quality Level D” (the least reliable data)
– Plotted on plans from records.
– Sometimes a field visit - to look for utility indications on the site - is made.
– Sometimes “verbal recollections” are plotted.
This level of effort is great for project planning purposes, utility “inventories,” and very preliminary utility relocation cost estimates.
Curb / EOP
Curb / EOP
Water Record says 4”
pipe is two feet off of
curb
“Quality Level C” (the “traditional” utility depiction)
– Surface Appurtenances are surveyed andaccurately plotted on a current site plan
– Utility data from records (QL D) are correlated tothe appurtenances
Problems with records interpretations still exist: e.g.schematics, no appurtenances depicted, utilities notstraight between appurtenances, no records exist, andso on.
Curb / EOP
Curb / EOP
Water Record says 4”
pipe is two feet off of
curb
Curb / EOP
Water Record says
pipe is two feet off of
curb, but…
Valves are six feet off
curbSurveyed &
Plotted Water
Valves
Curb / EOP
Water Record says
pipe is two feet off of
curb.
Engineer makes
judgment that water
line depiction should
be moved.
Surveyed &
Plotted Water
Valves
Curb / EOP
Water Record says
pipe is two feet off of
curb.
Engineer makes
judgment that water
line depiction should
be moved.
Surveyed &
Plotted Water
Valves
Curb / EOP
Water Record says
pipe is two feet off of
curb.
Engineer makes
judgment that water
line depiction should
be moved. OR
RECONFIGURED
Surveyed &
Plotted Water
Valves
“Quality Level B” (a significant upgrade in quality)
– Surface Geophysical Methods used to search forand trace existing utilities.
– Designated utilities are then surveyed and plottedon site plan.
Non-recorded utilities found. Utilities’ routes betweenappurtenances are imaged.
Typically used in early preliminary design forconstruction footprint decisions.
Curb / EOP
Curb / EOP
Water Record says 4”
pipe is two feet off of
curb
Curb / EOP
Water Record says
pipe is two feet off of
curb, but…
Valves are six feet off
curbSurveyed &
Plotted Water
Valves
Curb / EOP
Water Record says
pipe is two feet off of
curb
Designating indicates
otherwiseSurveyed &
Plotted Water
Valves
QL D and QL C
interpretations by
engineer were in error
“Quality Level A” (a guarantee in 3-D)
– Utilities exposed via non-destructive air-vacuummeans
– Exposed utilities are then surveyed and plotted onsite plan Elevations, Size, Condition, Materials,Precise Horizontal Positions are measured anddocumented
Typically used in final design stages. Allows smalladjustments in design for big savings in construction.
Ground
surface
Water line found at CL
Station 23+40, L10 to be
6 3/4” in diameter and
5.56 feet deep, slightly
corroded and cast iron
rather than ductile
The end result!
A map suitable for
current needs and
retrievable for future
needs with reliability of
the utilities clearly
indicated.
PLAN NOTES
1. Utilities are depicted on these plans in accordance with their achieved “Utility Quality Levels” as defined in the latest version of ASCE 38 (Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data).
2. Reliance upon these data for risk management purposes during bidding does not relieve the excavator or utility owner from following all applicable utility damage prevention statutes, policies, and/or procedures during construction.
3. It is important that the constructor investigates and understands the utility mapping scope of work between the project owner and their engineer regarding the types of utilities to be depicted and the project limits leading to these utility depictions.
DESIGN
ENGINEER
Without SUE With SUE
TOTAL RISK
RISK ELIMINATED
SUE
ENGINEER
D C B A
DEFINED QUALITY LEVELUNDEFINED QUALITY LEVEL
TOTAL ENGINEERING RISK POOL ALLOCATION OF RISK WITHIN ENGINEERING POOL
The total risk for the engineering pool decreases
as quality level increases, While within the
engineering pool, the risks shift towards the
subsurface utility engineer as quality levels trend
towards Quality Level A data.
How do you achieve a utility quality level ?
Quality Level D: Plotting from record
information
> Records research. How much?
> Is calling the One-Call adequate?
> Is a site visit necessary to look for utility
signs or appurtenances?
> Do I need to plot everything for which
there is a record? (e.g. individual
services, traffic control sensors?)
> What if there is an indication of a utility,
but no record?
How do you achieve a utility quality level ?Quality Level C: Correlation of records to surveyed
features / utility appurtenances
> Is using someone else’s survey of utility features
OK?
> How many surveyed features are required to call a
long run of utility Quality Level C?
> When does a Quality Level C line need to revert to
Quality Level D?
> Do I need to plot everything for which there is a
record? (e.g. individual services, traffic control
sensors)
> What if there is an surveyed utility feature, but no
record?
How do you achieve a utility quality level ?Quality Level B: Geophysics + Survey
> Is using someone else’s survey of utility marks
OK?
> What geophysics should I use?
> Do I search for a specific utility, or for
everything?
> How do I handle signals that are unknowns?
> How do I handle gaps in geophysical signals?
> What level of effort do I need to go to if I can’t
find a utility of record?
> Do I need to get into all the manholes and
vaults?
> To what Accuracy am I held responsible?
How do you achieve a utility quality level ?
Quality Level A: Exposure + Survey
> Does it matter what I use to excavate?
> What if I don’t find anything?
> How deep should I go?
> What if I find something different than I
thought was there?
> Can I trust someone else to survey my
patch and record the data?
> Do I need to convert to an elevation?
> To what accuracy am I held responsible?
> Water vs. Air vacuum?
ASCEACECNSPECSINUCAABAAWWAAIACMAAACSMWWEMAIMLAUSDAXLVOSCO
Engineering Series Contracts
Owner-EngineerEngineer – Sub-ConsultantEngineer – Geotechnical FirmEngineer - Surveyor
3D Model of Existing Facilities
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery
Utility Line Profile View
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery85
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery86
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery87
Locations with QLA Data
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery88
Test hole Test holeValve
Manhole
Assumed Curved Pipe Alignment
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery89
Test hole Test holeValve
Manhole
Assumed Straight Pipe Alignment
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery90
Test hole Test holeValve
Manhole
Assumed Horizontal Interpolation
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery91
Test hole Test holeValve
Manhole
3D Model Including Utilities
92
ATTRIBUTESQuality LevelMethod of “z” valueStarting elevationEnding elevationSizeMaterialOwnerConditionAgePressure
3D Utility Visualization – Ireland
3D Mapping and Marking of Underground Utilities during Project Development and
Delivery93
New Adventures Coming
• ASCE Utility “As-Built” Standard
• New SHRP Tools
• Utility Engineering and Surveying Institute
– SUE Training and Certifications
– “Utility Engineer” Education
– Utility Risk Envelopes
Senate Bill No. 481–Committee on Government AffairsCHAPTER..........
AN ACT relating to local governments; prohibiting a county,incorporated city or regional transportation commission fromcreating, maintaining or displaying a comprehensive modelor map of the physical location of all or a substantial portionof the facilities of a public utility, public water system orvideo service provider; providing that the prohibition doesnot limit the authority of a county, city or regionaltransportation commission to require a public utility, publicwater system or video service provider to discloseinformation relating to the physical location of the facilitiesof the public utility, public water system or video serviceprovider to facilitate certain public projects; revisingprovisions relating to municipal utilities; and providing othermatters properly relating thereto.
Lessons learned from Las Vegas RTC
Q & A