underground ducting for electrical/data · pdf filenwksrtc - north west karnataka state road...
TRANSCRIPT
Feasibility Report
31st August 2017
Hubballi-Dharwad Smart City –Underground Ducting forElectrical/Data distribution.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 2 of 67
This document has been prepared solely for HDSCL, being the express addressee to this document. PwC and
TCE does not accept or assume any liability, responsibility or duty of care for any use of or reliance on this
document by anyone, other than (i) HDSCL, to the extent agreed in the relevant contract for the matter to
which this document relates (if any), or (ii) as expressly agreed by PwC and TCE in writing in advance.
This publication (and any extract from it) may not be copied, paraphrased, reproduced, or distributed in any
manner or form, whether by photocopying, electronically, by internet, within another document or otherwise,
without the prior written permission of PwC and TCE. Further, any quotation, citation, or attribution of this
publication, or any extract from it, is strictly prohibited without PwC’s and TCE’s prior written permission.
PricewaterhouseCoopers Tata Consulting Engineers Limited Aminbhavi & Hegde Engineering
Consultants Pvt. Ltd.
© 2016 PricewaterhouseCoopers Private Limited, Tata Consulting Engineers Limited, Aminbhavi & Hegde
Engineering Consultants Pvt. Ltd.. All rights reserved.
In this document, PwC refers to PricewaterhouseCoopers Private Limited (a limited liability company in
India) an India member firm and may sometimes refer to the PwC network.
Each member firm is a separate legal entity.
Please see www.pwc.com/structure for further details.
TCE refers to Tata Consulting Engineers Limited
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 3 of 67
REVISION STATUS
Sl.No.
RevisionNo
PreparedBy
CheckedBy
PassedBy
SubmittedOn
Purpose
1 RO DB SH DG 31-08-2017 Submission
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 4 of 67
Table of Contents1. Executive Summary 11
2. Project Introduction 13
2.1 Background 13
2.2 City Overview 13
2.3 Smart City Mission 14
2.4 Project Idea and Scope 15
2.5 Necessity of the project 16
2.6 Project Description 17
2.7 Site Description 18
2.8 Site topography 18
2.9 Site Reconnaissance 18
2.10 Industry Overview 19
2.11 Regional Profile 20
2.12 City Connectivity 21
2.13 Climatic Conditions 22
2.14 Land Use Pattern of the city 22
3. Existing System and its Analysis 24
3.1 Introduction 24
3.2 Existing System 24
3.3 Past/Ongoing Projects and Proposals 24
3.3.1 Work involved details (By HESCOM) 25
3.4 Existing System Analysis 28
3.5 Conclusion 28
4. Project 29
4.1 Project Components 29
4.1.1 Under Ground System-Type-1 30
4.1.2 Under Ground System-Type-2 31
4.1.3 Under Ground System-Type-3: 32
4.1.4 Underground System- Type-4 33
4.1.5 Underground System-Type-5: 33
4.1.6 Cost implication of different underground components is indicated in table 5 34
4.2 Proposed Underground System In Various Widths Of Roads: 35
4.2.1 FOR ROAD WIDTH OF 14M TO 30M: 38
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 5 of 67
4.2.2 For Road Width Of 9m to 12m 41
4.2.3 For Road Width Of 6m-8m 44
4.2.4 For Road Width Of 3m To 5m: 46
4.3 Proposed HDPE Ducts for Underground Ducting: 47
4.3.1 HDPE Ducts For Fibre Optics And Communication Cable 48
4.3.2 Comparative Analysis Of Different Types Of Pipes: 48
4.4 Recommendations: 49
4.5 Approach & Methodology, Studies, Surveys Including Data Collection, Analysis 50
4.6 Best Case Studies for similar projects in India/World 52
4.7 Referenced Studies and Surveys 53
4.8 SWOT Analysis 54
5. Project Financials 55
5.1 Project Design 55
6. Statutory and Legal Framework 57
6.1 Legal And Regulatory Framework: 57
6.2 L0cal Regulatory Framework 57
7. Indicative Environmental & Social Impacts 58
7.1 Introduction: 58
7.2 Air quality: 58
7.2.1 Impacts during Construction for proposed project: 58
7.2.2 Impacts during Operation 58
7.2.3 Mitigation Measures: 59
7.3 NOISE QUALITY 59
7.3.1 Impacts during Construction 59
7.3.2 Impacts during Operation 59
7.3.3 Mitigation Measures 60
7.4 WATER QUALITY 60
7.4.1 Mitigation Measures 60
7.5 LAND ENVIRONMENT 60
7.5.1 Impacts of Construction Wastes 60
7.5.2 Mitigation Measures 61
7.6 SOCIO ECONOMIC IMPACTS FOR PROPOSED PROJECT 61
7.7 POTENTIAL ENVIRONMENTAL IMPACT MATRIX 61
7.8 CONCLUSION 64
8. Operating Framework 65
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 6 of 67
8.1 INDICATIVE PROJECT STRUCTURING 65
8.1.1 Milestones 65
8.1.2 Operation and Maintenance 66
8.2 RISKS AND MITIGATION 66
8.2.1 Risks 66
8.2.2 Mitigation 66
9. WAY FORWARD AND CONCLUSIONS 67
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 7 of 67
List of Tables
Table 1 : Benefits of underground ducting and its limitations 17
Table 2 : Details of Industrial Estate on Gokul Road 20
Table 3 Land Use of Hubballi- Dharwad (2000) 23
Table 4: Land Use of Hubballi Dharwad -2021 (proposed) 23
Table 5 : Cost comparison of different type of ducting 34
Table 6 : ROW of roads in Hubballi ABD area 36
Table 7 : Comparative analysis of different types of pipe 48
Table 8 : Approach adopted for project 50
Table 9: Methodology 51
Table 10: SWOT Analysis 54
Table 11 : Capital cost of under grounding 55
Table 12 : Potentiail environmental impact matrix for Hubbali town 63
Table 13 : Summary of environmental management plan 63
Table 14: Major Milestones and Time Allocated 65
Table 15 Tentative planning for next deliverables 67
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 8 of 67
List of Figures
Figure -1: Look of a city with and without overhead lines .......................................................................16
Figure -2: ABD Area & Surroundings .............................................................................................................18
Figure -3: Existing 11kV transmission line map......................................................................................... 26
Figure -4: Existing 415V power transmission lines of Hubbali town .................................................. 27
Figure -5: Existing man holes for OFC .......................................................................................................... 27
Figure -6: Utility Tunnel (Typ) ........................................................................................................................ 30
Figure -7: Utility duct(Typ) ................................................................................................................................31
Figure -8: Electrical & ICT trench (Typ) ....................................................................................................... 32
Figure -9: Pipe ducting(typ) ............................................................................................................................. 33
Figure -10: C-pipe ducting (Typ) ..................................................................................................................... 34
Figure -11: Road map of Hubbali town.......................................................................................................... 37
Figure -12: Percentage road length of Hubbali town ................................................................................ 38
Figure -13: Layout sec. of Gokul Road (Typ)-Industrial estate junction to Airport ........................ 39
Figure -14: Layout section of Gokul Road- Hosur circle to industrial estate .................................... 39
Figure -15: Layout section of Siddappa Kambli Road- Hosur circle to Railway station ................40
Figure -16: Layout sec. of 9M TO 12M wide Road (Typ)........................................................................... 42
Figure -17: Road crossing Figure -18: Feeder pillar Figure -19: Man hole ............................. 43
Figure -20: Layout sec. of 8M wide road (Typ)........................................................................................... 45
Figure -21: Layout sec. of 3M TO 5M wide Road (Typ)............................................................................. 46
Figure -22: De-merits of RCC pipe.................................................................................................................. 47
Figure -23: Merits of HDPE pipe..................................................................................................................... 47
Figure -24: Multiple bundled ICT duct.......................................................................................................... 48
Figure -25: Bangalore smart roads under tender S.U.R.E...................................................................... 53
Figure -26: Utility tunnel, Gift city, Gujarat ................................................................................................ 53
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 9 of 67
Abbreviations
ABD - Area Based Development
AWCS - Automatic Waste Collection System
BRTS - Bus Rapid Transport System
CBD - Central Business District
CBT - Central Bus Terminal
CCTV - Closed-circuit television
dB - Decibel
DPR - Detailed Project Report
EPC - Engineering Procurement Construction
FY - Financial Year
GHMC - Greater Hyderabad Municipal Corporation
GoI - Government of India
GoK - Government of Karnataka
GPS - Global Positioning System
Ha - Hectare
HDMC - Hubballi Dharwad Municipal Corporation
HDSCL - Hubballi-Dharwad Smart City Limited
HDUDA - Hubballi-Dharwad Urban Development Authority
IT - Information Technology
Km - Kilometres
KSIIDC - Karnataka State Industrial and Infrastructure Development Corporation
KSRTC - Karnataka State Road Transport Corporation
MD - Managing Director
MoEF - Ministry of Environment and Forests
MoUD - Ministry of Urban Development
MSME - Micro, Small & Medium Enterprises
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 10 of 67
NBP - Non Biophysical Components
NGO - Non-Governmental Organisation
NH - National Highway
NWKSRTC - North West Karnataka State Road Transport Corporation
O&M - Operation and Maintenance
PCB - Pollution Control Board
PK - Pourkarmikas
PMC - Project Management Consultant
PwC - PricewaterhouseCoopers Pvt. Ltd.
RCC - Reinforced Cement Concrete
SCC - Special Contract Clause
SCP - Smart City Proposal
SH - State Highway
SPCB - State Pollution Control Board
SPV - Special Purpose Vehicle
SWOT - Strengths, Weaknesses, Opportunities, and Threats
TCE - TATA Consulting Engineers Limited
ULB - Urban Local Body
UNEP - United Nation Environment Programme
USEPA - United States Environment Protection Agency
HESCOM Hubli Electricity Supply Company Limited
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 11 of 67
1. Executive Summary
Hubballi-Dharwad, an administrative node in North Karnataka is also a well-known commercial hub of
the region. The population of the city is 9.43lakhs as per 2011 census. Hubballi Dharwad under
Government of India’s Smart Cities Mission is being developed as one of the 100 Smart Cities in the
country.
Just like other city services, electricity is a vital resource for day to day living and overall development of
a city. An efficient, reliable and well organized power sector capable of delivering quality power along
with quality service is a necessity for any progressive community. As suggested under smart city features
in the Smart Cities Guidelines, cities have to focus on energy efficiency and promote underground electric
wiring to ensure continuous electricity supply. In Hubballi-Dharwad, Hubballi Electricity Supply
Company Limited (HESCOM) has been vested with the responsibility of distribution of power to the
households. Power supply in Hubballi-Dharwad is partially through overhead transmission lines &
partially underground. 80% of the overhead HT lines have been laid underground and process for
putting remaining 20% HT lines underground is under process. As of now, all LT lines are overhead
transmission lines.
Underground ducting is the replacement of existing overhead power supply
system and/or telecommunication line and/or similar services with underground cables. This is not
only performed for aesthetic, but also serves as the additional significant purpose of making the
power lines less susceptible to outages during high wind thunderstorms and other natural
calamities.
As electrical lines are often buried along existing public streets and right-of-way, provision of
underground services projects is best incorporated into plans for street improvement to reduce
unforeseen interruptions, rliability of power supply, public safety and reduction of maintenance
cost.
Based on the site survey conducted and also discussions with the KPTCL / HESCOM authorities, the
underground ducting project shall be carried out along the public streets.
In this feasibility study, separate directly and completely grounded High density polyethylene pipe
ducts for carrying power, fibre optic or any other utility cables or wires are recommended.
Smart metering is not considered in this feasibility report since for application of smart metering,
the entire power supply distribution system has to be studied separately. Integration of smart
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 12 of 67
metering for 24x7 electricity supply has been discussed with HESCOM, and this is envisaged to be
taken up by HESCOM and HDMC in later phases. For now, implementation and cost of smart
metering hasn’t been considered. The cost for underground ducting has been estimated to be
around Rs.108 Crore and is expected to be executed on EPC contract. The construction
cost will be borne by HDSCL and the O&M shall be done by service providers.
The social and environmental studies have also been carried out and it has been inferred from these
studies that the proposed project would be beneficial to the community as this can make the power
line less susceptible to outages during high wind thunderstorms and also contribute in the aesthetics
look of the city.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 13 of 67
2. Project Introduction
2.1 Background
Government of India intends to transform 100 Indian Cities to Smart Cities. The twin city of Hubballi-
Dharwad has been selected to be developed as a smart city under the Smart Cities Mission launched by
the Ministry of Urban Development (MoUD). In September 2016, Hubballi-Dharwad was selected
amongst the 27 winners of the "2nd Round Competition of SCM” based on the Smart City Plan (SCP).. As
mandated in the mission guidelines, Hubballi-Dharwad has incorporated a Special Purpose Vehicle
(SPV) – Hubballi-Dharwad Smart City Limited (HDSCL) (the “Authority”) to plan, design, implement,
coordinate and monitor the smart city projects in Hubballi-Dharwad.
Further, HDSCL has received funds from Government of India (GoI) and Government of Karnataka
(GoK) for developing Hubbali-Dharwad as Smart City and implementation of projects proposed by city
under the mission. Project implementation will include carrying out the feasibility study, preparation of
project reports, detailing out the plans, and monitoring and management of the projects. Pursuant to
above, PricewaterhouseCoopers Pvt. Ltd. (PwC) in association with TATA Consulting Engineers Limited
(TCE) and Aminbhavi and Hegde (AH) have been appointed as Project Management Consultant (PMC)
for providing consultancy services for detailing out the ABD and Pan-City plans; preparation of detailed
project reports for the envisaged project packages and project management consultancy support for the
same.
The ABD area is mainly characterized by two kind of land use- commercial and administrative.
2.2 City Overview
Hubballi- Dharwad as a city is an agglomeration of two towns in the northern part of state of Karnataka..
Hubballi-Dharwad is one of the oldest city in Karnataka state with strong cultural and historical
importance, and is also the second-largest urban settlement in Karnataka after Bengaluru. The twin cities
of Hubballi and Dharwad are located at a distance of about 20 km from each other and are municipally
administered by a single Municipal Corporation. Hubballi was identified as an important commercial
and trade centre for the entire northern Karnataka region by the British. Hubballi and Dharwad were
separate municipal entities, but due to functional and administrative interdependency, a common
municipal borough was constituted in the year 1925 for the combined population of 69,940. Further,
Hubballi-Dharwad municipality was upgraded to corporation in the year 1962. Hubballi is the
commercial centre and business hub of North Karnataka region. Crops including cotton, chilli pepper
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 14 of 67
and peanuts are grown aplenty in the surrounding rural agricultural areas, and Hubballi is a major
trading centre for these commodities. It is also an important city for the Indian Railways, as it is the
headquarters for South Western Railway zone and the Hubballi Railway Division. Hubballi is a major
railway junction in North Karnataka. It is also the headquarters of North Western Karnataka Road
Transport Corporation. Hubballi also houses the largest number of government offices outside
Bangalore. . It has more than 3,000 small and medium industries. Approximately 55% of the city‘s
population is involved in the tertiary sector. The demographic indicators namely sex ratio and literacy
rates are favourable and higher than that of Karnataka and India. The existing population of the
Hubballi- Dharwad Municipal Corporation area as per Census 2011 is about 9.43 lakhs.
2.3 Smart City Mission
Smart Cities Mission is an urban renewal and retrofitting program by the Government of India with a
mission to develop 100 cities (the target has been revised to 109 cities) all over the country making them
citizen friendly and sustainable. The Union Ministry of Urban Development is the key role player in
designing, implementing and monitoring the mission in collaboration with the state governments and
urban local bodies of the respective cities.
Round-1 Cities Round-2 Cities Round-3 Cities
The objective of Smart City Mission is to promote cities to provide core infrastructure and give a decent
quality of life to its citizens, a clean and sustainable environment with application of ‘Smart’ Solutions.
The focus is on sustainable and inclusive development and the idea is to look at compact areas, create a
replicable model which will act like a light house to other aspiring cities. The mission is meant to set
examples that can be replicated both within and outside the Smart City, catalysing creation of similar
Smart Cities in various regions and other parts of the country.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 15 of 67
Accordingly, the purpose of Smart Cities Mission is to drive economic growth and improve quality of life of
people by enabling local area development and harnessing technology especially that leads to Smart
outcomes. Area-based development (retrofit and redevelop) will transform existing areas including slums
into better planned ones thereby improving liveability of the whole City. Application of Smart Solutions
will enable cities to use technology, information and data to improve infrastructure and services.
Comprehensive development in this way will improve quality of life, create employment and enhance
income for all, especially the poor and the disadvantaged, leading to creation of inclusive Cities.
2.4 Project Idea and Scope
The purpose of Smart Cities Mission is to drive economic growth and improve quality of life of people by
enabling local area development and harnessing technology, especially technology that leads to Smart
outcomes. Area-based development will transform existing areas (retrofit and redevelop); including
slums, into better planned ones, thereby improving livability of the whole City. 24 X 7 power supply is an
integral component of smart city development.
Electrical power is transmitted through either overhead power lines or underground cables. Each of the
two types has its benefits as well as pitfalls as well as places where it is commonly used. The choice of
which method to use, is influenced by voltage, cost, safety, type of application, and other factors. Whereas,
the overhead lines are cheap, easy to install, troubleshoot and upgrade, the same cannot be said about the
underground cables. Underground cables have their place too, and despite being expensive, they have
several advantages. These are mostly used where it is dangerous to have overhead lines such as densely
populated areas as well as in providing the missing link in areas where overhead lines cannot be used.
Electrical lines along with Information and communication technology (ICT) lines can be taken under
ground in various forms for eg: Utility Tunnel / Ducting / Electrical Trench/ Piping ducting/ Cables
buried directly in ground. All these are possible subjected to availability of space.
“Undergroundducting” is one of the projects taken under smart city proposal for Hubballi-Dharwad.
This project aims towards underground ducting of overhead LT transmission lines (415V) and ICT lines
across the city for 24 X 7 power supply. The aim of the project is to provide assured power supply in the
city. Separate strategies need to be planned for residential and non- residential areas in the ABD area.
The scope of the Feasibility Report for underground ducting in ABD area of Hubballi-Dharwad Smart City
Limited has been finalised after carrying out the following studies:
• Reconnaissance Survey
• Stakeholder consultation and surveys
• Case studies of best practices around the world
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 16 of 67
• SWOT analysis
• Indicative Environmental & Social Impacts
• Project Financials
• Statutory and Legal Framework
2.5 Necessity of the project
The purpose of Smart Cities Mission is to drive economic growth and improve quality of life of people by
enabling local area development. By doing so, sustainability and environmental balance should be
maintained. The residents and other stake holders of the city should be ensured with all basic amenities.
24 x 7 power supply is one of these basic amenities. In an effort to raise the standard of living in Hubballi
and to make the city a true smart city, the HDSCL intends to introduce provisions for assured electricity
supply in the city.
As per smart city proposal, for assured 24 x 7 hours electricity supply with minimum outages, the power
supply in the city shall be through underground cabling system instead of overhead transmission line. In
some of the best cities in the world (e.g. London or Sydney) we find no overhanging wires or cables across
buildings, promenades, streets etc. All cabling is underground, whether it is power, internet, cable TV,
fibre optic or any other utility cables or wires. Underground ducting provisions not only reduce power
outages but at the same time improve the aesthetics of the city. Also they are relatively easy to maintain
and remain less vulnerable during strong winds and inclement weather. Table 1 provide the advantages
and limitations of the underground ducting
Photographs below depict the improvements in aesthetics observed from the underground ducting when
compared to that of the above ground installations.
Figure -1: Look of a city with and without overhead lines
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 17 of 67
Table 1 : Benefits of underground ducting and its limitations
Benefits from Undergrounding Limitations to Undergrounding
Improved reliability in wind and
winter weather events.
Increased cost of materials and labour
Aesthetics Increased duration of outages because failures
are difficult to locate and access
Can be paired with undergrounding
cable and telecommunication lines
Shortened line life as compared to overhead lines
Can reduce cost of conversion through
salvage
Exposure to road salt and corrosive chemicals.
Increase in property values with
underground utility connections.
Higher maintenance costs.
Can shorten outages duration after
major storm damage
More complex and costly maintenance and repair
Reduction in public safety risks from
downed wires
Susceptible to safety risk during storm surges
and flooding
2.6 Project Description
As per smart city proposal, for assured 24 x 7 hours electricity supply with minimum outages, the power
supply in the city shall be through underground ducting instead of overhead transmission lines.
Underground ducting are planned to be implemented along existing public streets along the right-of-way
after reconnaissance survey and land use pattern study and according to existing condition in the area to
ensure roads are free from overhead cables and electricity lines.
Refined methodology is followed in submitting the project deliverables in accordance with thefollowing stages:
Deliverable 1: Feasibility Report
Deliverable 2: Draft DPR
Deliverable 3: Final DPR
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 18 of 67
2.7 Site Description
The Project area for which the Underground Ducting for Electrical/Data distribution plan of action is to be
prepared is located in 992 acres encompassing the city centre and growth corridor of Hubballi- from
Airport to Railway, linking BRTS. The site is near to Commissioners office and other government offices.
Major commercial area and old markets of Hubballi - Dharwad city are part of ABD area. It links airport to
the railway station connecting major traffic junctions like Rani-Chennama Circle, Court Circle, Hosur
Circle etc. The ABD area also includes BRTS Depot, NWKRTC Depot, old and new bus stands along Gokul
Road. There is also green cover from MG Market and other open spaces like Nehru Stadium, Tolenkere
Lake etc. A 120 acre of Industrial Cluster also exists near Gokul Road Police station.
Figure -2: ABD Area & Surroundings
2.8 Site topography
The site topography is in such a way that Gokul road forms a ridge line and the site slopes on both
directions of the Gokul Road. The entire area drains towards two areas – Tolankere Lake as well as Main
Nala passing near the Clarks hotel which leads from Unkar lake. The elevation varies from 647 to 620 m.
2.9 Site Reconnaissance
The consultant team has carried out reconnaissance survey in the ABD area and marked the existing areas
where power supply is through overhead transmission lines. The complete information on the existing
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 19 of 67
system has been provided in the existing system chapter. The efficiency in the existing system has been
suitably analysed and accordingly necessary planning has been done to make this project more viable in
social, economic and administrative terms.
2.10 Industry Overview
Hubballi-Dharwad is the most urbanized area in north Karnataka. It is also known as the commercial hub
of north Karnataka region. The major contributors to economy of Hubballi-Dharwad city are tertiary-
based activities, namely, trade and commerce including agro-based activities, transport and Education
sector. Hubballi is the commercial hub and major economic activities include industries, trade and
commerce. It has more than 3,000 small and medium industries. Approximately 55% of the city‘s
population is involved in the tertiary sector.
The railway workshop and Karnataka Central Co-operative Textile Mill were established in the city during
the British regime. A number of ginning and pressing units were established during the early 20th century
in the cotton belt region around it; the activity has gradually declined due to export of cotton to Mumbai
and other areas. There were 6 textile industries in Hubballi including the Maratha Spinning and Weaving
Mill. About 2,000 people were employed in these textile units. The railway workshop in Hubballi
manufactures passenger coaches and goods wagons. Karnataka State Road Transport Corporation
(KSRTC) also established its workshop in Hubballi and is engaged in bodybuilding for buses belonging to
the corporation.
The other modern industries in the area includes food processing, woodworking, steel furniture, printing,
domestic utensils, service industries, and miscellaneous units. The Hubballi region is also known for its
rich mineral deposits like manganese, iron, and copper, but not in sufficient quantity for economic
exploitation. Industries are located along national highway, station road, Koppikar Road, Neeligin Road,
and Dajibanpeth area of Hubballi . There are around 9800 industries in Hubballi with 10 major
industries.
There are 20 Medium & Large Scale Industries in and around municipal limits with an investment of
Rs.744.66 Crores providing employment to 7325 persons, Tata Marcopolo, Tata Motors & Telcon, Bharath
NRE Coke Ltd, ADM Agro Industries Ltd, Micro Finish Valves Ltd, Mevin Mifrom Pvt Ltd, NGEF, Wier
BDK, RSB Transmission Ltd, VRL Logistics Pvt Ltd, Bellad Group of Industries, are key industrial giants
in the area. The Large & Medium scale industries are engaged in production of Buses, Electrical Motors &
Centrifugal Pumps, Spinning Yarn Ceramic Tiles, M.S.Ignots and Castings, Automobile Spares,
Excavators, Machine Tools, Liquid Petroleum Gas Bottling Plant, Draw Shaft Components etc, Industrial
Valves and Machinery Components, Food Products like, Mango Pulp & Juice are the major exportable
items from Hubballi-Dharwad . A Software Technology Park is functional in Hubballi, which has added to
the district`s ability to cater to the requirements of Information Technology and IT-enabled projects.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 20 of 67
The ABD area has 120 acre MSME cluster on Gokul Road near Basaveshwar Nagar. The details of the
industrial estate are given in the table below.
Table 2 : Details of Industrial Estate on Gokul Road
No IndustrialEstate
Year Landacquired (inAcres)
No. ofsheds
No. ofsheds
allotted
Vacantsheds
No. ofsites
developed (inAcres)
No.of
sitesallott
ed
No.of
vacant
sites
No.of
unitswork
ing
1 Gokul and
M.T.SagarHubballi
1958-1994
Ist Stage
IInd Stage
123.00Acres
502 502 0 310 310 310 812
2.11 Regional Profile
Hubballi is located between 15° 11' - 15° 31' North Latitude and 75° 01' - 75° 28' East Longitude at an
altitude of 627.97m above sea level. Located at about 425 km north of Bangalore and separated by a
distance of 20 km, both the cities are connected to Pune and Bangalore by rail network; other rail links
connect the city with Hotgi, Sholapur, Marmagoa and Bellary. The twin cities are also connected to
Mumbai and Bangalore by Air. The city attracts floating population from neighbouring urban centres such
as Karwar and other towns from north Karnataka as well as Dharwad district, for the purpose of trade and
commerce, health, and education. It also attracts population from across the district to avail the
administrative services provided at various district offices both in Hubballi and Dharwad. Hubballi is the
educational hub of north Karnataka and attracts population from the north Karnataka region for
educational purpose.
The ABD area of 992 acres is located at the heart of Hubballi city and is very well connected with all the
surrounding areas by road. The ABD area is mainly planned based on a transit-oriented development. Two
bus stations- old as well as new NWKSRTC station and Central Bus Terminal (CBT) fall inside the limits of
ABD area. The Hubballi Junction Railway station, which is the headquarters of South western Railway
marks the eastern boundary of ABD area. Also, there is also an airport in ABD area near Gandhi Nagar,
which has daily flight to Bangalore.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 21 of 67
2.12 City Connectivity
Hubballi – Dharwad is well connected to the major cities by road network and rail network. It has air
connectivity with Bangalore and Mumbai. The city is also the head quarter of divisional railways.
National highway, NH4, is the major corridor of Hubballi Dharwad passing through the central city core
and connects Pune and Bangalore. Dharwad is predominantly set to the west of NH4. The major roads in
both cities follow a radial pattern, originating from the centre of Hubballi city and connecting other
major towns like Bijapur, Karwar, Marmagoa and Sholapur. The National highway NH-4 built to bypass
traffic from PB road connects the twin cities with Bangalore and Pune. Other highways passing
through/connecting the city are NH-218 (to Solapur), NH- 63 (to Haliyal and Gadag), SH- 73 and SH- 28
(to Goa). The major district roads connect Kalghatai, Soundhatti and Halyal etc.
Hubballi is well connected by the rail network to Bengaluru and other major cities such as Mumbai in the
north-west and Thiruvananthapuram in the south. Being an important railway junction, there are daily
trains to Bijapur, Solapur, Bellary, Pune, Ajmer, New Delhi, Hyderabad, Ahmedabad, Vasco, Vijayawada,
Mysore, Tirupati, Chennai, and Howrah. There is an operational airport in Hubballi.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 22 of 67
2.13 Climatic Conditions
Hubballi-Dharwad experiences a tropical climate with distinct wet and dry seasons. However, Dharwad
enjoys a better climate than Hubballi in view of its higher altitude. Owing to the location, Dharwad enjoys
a pleasant weather with moderate climate throughout the year. The coolest month is December with an
average low temperature of 15.4 °C and the hottest month is April with an average high temperature of
32.8 °C. The region receives rainfall from both northeast and southwest monsoons, and the wettest
months are September and October. The average annual rainfall is around 675 mm for Hubballi and 812
mm for Dharwad.
2.14 Land Use Pattern of the cityAs per the comprehensive development plan, the percentage of land under residential use has gone up
from 25% to 31% between 1986 and 2000. However, this is still low compared to the prevalent norm of
35% to 40% of land under residential use, indicating the availability of potential land for residential
development. Growth in commercial land use is slow compared to what has been envisaged in the
comprehensive development plan. Overcrowding of the existing CBD at Hubballi and lack of demand for
commercial space in CBD at Navanagar are one of the major reasons for the slow pace of growth in
commercial land use. The table 2 below shows land use of 2000 and table 3 shows proposed land use.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 23 of 67
Table 3 Land Use of Hubballi- Dharwad (2000)
Sl.No Land Use Area(Ha) Area(%)
1 Residential 3,196 31%
2 Commercial 336 3%
3 Industrial 528 5%
4 Public and Semi-Public 1,750 17%
5 Recreational 663 6%
6 Transportation and Communication 2,269 22%
7 Water Bodies, Agricultural & Others 1,632 16%
Total 10,374 100%
Source : Comprehensive Development Plan (2003), HDUDA
As per the population projections carried out in the demography section, the city would have a population of
11.6 lakhs by 2021. The proposed land use plan is as shown in table below:
Table 4: Land Use of Hubballi Dharwad -2021 (proposed)
Sl.No Land Use Area(Ha) Area(%)
1 Residential 5,717 42%
2 Commercial 835 6%
3 Industrial 738 5%
4 Public and Semi-Public 2,021 15%
5 Recreational 1,431 10%
6 Transportation and Communication 3,005 22%
7 Water Bodies, Agricultural & Others -- --
Total 13,747 100%
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 24 of 67
3. Existing System and itsAnalysis
3.1 Introduction
As suggested under smart city features in the Smart Cities Guidelines, cities have to focus on energy
efficiency and promote underground electric wiring to ensure continuous electricity supply. City of
hubballi is fed from 1 no. of 220kV sub-station, 7 nos. of 110kV sub station and 2 nos. of 33kV substation,
which are located at different places in the city. Considering the human safety, aesthetic look, overall
traffic and uninterrupted supply requirements, HDMC intends to go for underground ducting system as
part of smart city project.
80% of the 11kV HT overhead transmission lines are underground and commissioned. Remaining 20%
work is under execution. Existing 11kV transmission lines map is shown in Fig. 3.
The low voltage(415V) overhead transmission lines which are running parallel with 11kV HT overhead
lines has to be removed/put into underground system. .
3.2 Existing System
At present HESCOM is converting all 11kV HT overhead lines to underground cabling under IPDS
(Integrated power distribution scheme).
Out of entire Hubbali city:
1/3 area has been covered in the year 2006 and has been commissioned.
Of the remaining 2/3 area- 50% has been executed and ready for commissioning. Remaining
50% is under execution.
OFC cables are being laid by government (BSNL) as well as private vendors along with HT cables.
All 415V power lines in the city are overhead transmission lines and need to be converted to
underground. Existing 415V transmission lines of Hubballi town is indicated in fig. 4.
3.3 Past/Ongoing Projects and Proposals
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 25 of 67
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED (HESCOM) mission is to ensure reliable quality
power to its customers at competitive prices. HESCOM is committed to achieve this. As a part of this,
HESCOM has started “Conversion of existing 11kV Over Head Feeders to 11kV Under Ground cable
system in Hubli City”.
3.3.1 Work involved details (By HESCOM)
27 Nos. of feeders are proposed, By Laying of 3cx400sq.mm UG Cable Trunk Line: 123.23km.
For Looping the Distribution Transformer Centers (DTC’s) 117 Loops are proposed using
3cx95/240sq.mm UG Cable: 340.51km
No. of Ring Main Unit (RMU’s) to be provided for 27 nos of proposed feeders
(OD+3VL,2OD+2VL,2OD+1VL) : 92 nos.
Providing additional RMU panels to existing RMU’s : 12 nos.
Providing 3rd pole by looping Distribution Transformer Centers (DTC’s) no. of Transformers to
be covered.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 26 of 67
Figure -3: Existing 11kV transmission line map
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 27 of 67
Figure -4: Existing 415V power transmission lines of Hubbali town
Figure -5: Existing man holes for OFC
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 28 of 67
3.4 Existing System Analysis
In Hubballi 80% of the overhead HT lines have been laid underground and process for putting remaining
20% HT lines underground is under process. All LT lines in the city are overhead transmission lines. It
has been found essential to convert all overhead transmission lines & cables to underground, whether it
is power, internet, cable TV, fibre optic or any other utility cables or wires. This not only reduces the
outages during strong winds and inclement weather but also improves the aesthetics of the city.
As part of the survey, existing overhead transmission lines along with poles and transformer locations
were identified. Also, right of way of the roads along with the space available alongside the road were
identified for proposing the underground ducts suitably.
Apart from the above, there are many ICT cables laid underground already by the following agencies:
Airtel
Jio and Reliance
BSNL
Vodaphone
Idea
Docomo
3.5 Conclusion
In Hubballi 80% of the overhead HT lines have been laid underground and process for putting remaining
20% HT lines underground is under process. All LT lines in the city are over-head transmission lines.
Power reliability may be at stake with the existing 415V overhead transmission lines in the ABD area.
Hence for implementation of 24x7 power supply in ABD area, it is felt necessary and appropriate to
undertake the project of underground ducting of all electrical cables for assured power supply to the
residents of Hubballi.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 29 of 67
4. Project
4.1 Project Components
Underground ducting is the replacement of existing overhead systems of power transmission
system or telecommunications, with underground cables. This not only improves the aesthetics, but also
serves the additional significant purpose of making the power lines less susceptible to outages during
high wind, thunderstorms or heavy snow or ice storms. Undergrounding may require the initial high
costs of electric power transmission and distribution but will decrease operational costs over the lifetime
of the cables.
Considering the human safety, aesthetic look, overall traffic and uninterrupted supply requirements,
smart cities should be laid with underground ducting system. The aerial cables that carry high-
voltage electricity supported by large pylons are generally considered as non-attractive feature of the
countryside. Underground cables can transmit power across densely populated or areas where land is
costly or environmentally or aesthetically sensitive. Underground and underwater crossings may be a
practical alternative for crossing rivers.
In normal Indian context all underground utilities are being laid as and when required where ever space
is available, fulfilling basic technical norms. In dense areas or say highly populated areas various utilities
are laid in mesh form without keeping allowances for other utilities and its technical norms. Particularly
at the time of operation and maintenance, this will become most difficult and disturbing road or footpath
while digging / excavating to open the underground utility and also damage other congruent utilities.
This is the normal situation in urban areas.
Underground ducting can be done in two different ways by making utility ducts and directly buried
through pipes. Utility tunnels are common in very cold climates where direct burial below the frost line is
not feasible (such as in Alaska, where the frost line is often more than 18 ft (5.5 m) below the surface,
which is frozen year round). They are also built in places where the water table is too high to bury water
and sewer mains and where utility poles would be too unsightly or pose danger (like
in earthquake prone Tokyo). Tunnels are also built to avoid the disruption caused by recurring
construction, repair and upgrading of cables and pipes in direct burial trenches.
Utility tunnels are also often common at large industrial, institutional, or commercial sites, where
multiple large-scale services infrastructure (gas, water, power, heat, steam, compressed air,
telecommunications cable, etc.) are distributed around the site to multiple buildings, without impeding
vehicular or pedestrian traffic above ground. Due to the nature of these services, these services may
require regular inspection, repair, maintenance, or replacement, and therefore accessible utility tunnels
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 30 of 67
are preferred instead of direct burying of the services in the ground. Utility tunnels range in size from just
large enough to accommodate the utility being carried, to very large tunnels that can also accommodate
human and even vehicular traffic.
Underground ducting for utilities can be done in the following ways:
• Utility tunnel for road width ≥ 12 meters
• Utility Duct for road width ≥ 9 meters
• Electrical & ICT duct
• Pipe ducting
• C Pipe ducting
4.1.1 Under Ground System-Type-1
Utility Tunnel
Utility Tunnel can carry all the utility services such as electricity, water, solid waste, district cooling
supply pipes, etc to the various areas across the city. Utility tunnel is considered an optimal solution to
avoid underground crowding of service lines in narrow right of way.
It is built to avoid the disruption caused by recurring construction, repair and upgrading of cables and
pipes in direct burial trenches.
A typical layout diagram and snapshot of a utility tunnel are indicated in Fig.6.
Figure -6: Utility Tunnel (Typ)
Advantages of Utility Tunnels:
Easier accessibility to utilities for maintenance and Upgrading.
Environmental impacts are minimized: such as traffic disruption
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 31 of 67
Location information is made more accessible.
An adequate airflow in ducts allows better heat transmission from electricity cables than in direct
trenched/ buried situations.
Utility tunnels range in size from just large enough to accommodate the utility being carried, to very
large tunnels that can also accommodate human and even vehicular traffic.
Dis-advantages of Utility Tunnels:
High initial construction cost as compared to traditional open excavation methods.
Space required for utility tunnel is more compared to other underground services. Only suitable for
green field projects having more wider roads.
4.1.2 Under Ground System-Type-2
Utility Duct:
In Utility Duct all the services will be located along with Electrical cables which will be placed in
separate electrical trench.
Typical layout diagram of a utility duct is shown in fig 7.
Figure -7: Utility duct(Typ)
Advantages:
This type of arrangement carries all the utility supplies in a well structured manner. It allows space for
operation, maintenance etc.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 32 of 67
Disadvantages:
It consumes about 5 metres of space. It is more costly. So this type is more preferable for roads having
more ROW.
4.1.3 Under Ground System-Type-3:
Electrical & ICT Trench:
In this type of underground system, cables are laid in cable trays, either perforated or ladder type in
closed ducts. Cable trays are mounted in the concrete duct with the help of angles and channel. In this
type dedicated trays are provided for HT,LT & ICT cables.
A typical layout diagram and snapshot of a electrical & ICT trench are indicated in Fig8.
Figure -8: Electrical & ICT trench (Typ)
Advantages:
This can be best suited for narrow roads. The overall width of this duct is less than 2m and it is
cheaper compared to other type of ducts. Since manhole provision is there, this is far better than
directly buried in terms of maintenance. Road cutting and hence the traffic disruption can be avoided
in this system.
Disadvantages:
It consumes about 2 meters of space. Also construction of concrete ducts for installation of trays
makes it costly.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 33 of 67
4.1.4 Underground System- Type-4
Pipe Ducting:
Electrical and ICT cables are directly carried through pipes of various diameters which are directly
buried into the ground. This can carry utilities such as power cables, ICT cables but cannot be used as
multipurpose for water supply, gas supply etc. Cable pull chamber is provided at every 100m interval
of length which helps in maintenance and fault clearance.
• A typical layout diagram and snapshot of a pipe ducting with pull chamber are indicated in fig 9.
Figure -9: Pipe ducting(typ)
Advantages:
Less cost, easy construction and less space consumption.
Disadvantages:
Maintenance provision is less compared to ducts & C-pipe.
Pipe cutting, road cutting & excavation is required in case of cable fault.
Pulling of cable would be laborious task.
4.1.5 Underground System-Type-5:
C-Pipe Ducting:
Electrical Pipe ducting consist of C shape RCC pipe of 300/ 150 mm diameter.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 34 of 67
2 nos of C shaped pipe shall be placed one above the other to form pipe and laid in ground at the
depth of 1000/ 750 mm from ground level.
A typical layout diagram of C pipe ducting are indicated in Fig.10`.
Figure -10: C-pipe ducting (Typ)
Advantages:
Advantage of using C shaped pipe helps in easy laying of cables and also maintaining of cables during
fault.
Disadvantages:
Digging of road is required during maintenance/ laying of cable.
Soil settlement and undulation of level due to rain etc. Hence frequent maintenance is required.
4.1.6 Cost implication of different undergroundcomponents is indicated in table 5
Table 5 : Cost comparison of different type of ducting
Sl.No
Undergroundcomponent
Costimplication
Remarks
1 Utility Tunnel 50Crores/KM
High initial construction cost as
compared to traditional open excavation
methods.
Space required for utility tunnel is more
compared to other underground services.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 35 of 67
Sl.No
Undergroundcomponent
Costimplication
Remarks
2 Utility Duct 6Crores/KM
It consumes about 5 metres of space.
So this type is more preferable for roads
having more ROW.
Maintenance costs are higher.
3 Electrical &ICT Trench
2Crores/KM
Road surfaces can be avoided from
damages.
Maintenance costs are higher.
4 Pipe Ducting 1 crore/KM Installation and maintenance costs are
less compared to other underground
components.
5 C-Pipe ducting 1.3crore/KM
Installation and maintenance costs of C-
Pipe ducting are less than other
components except pipe ducting.
Also during fault rectification, the whole
length of cable needs not to be pulled out.
Instead the top of the c-pipe duct can be
removed and the portion of the faulty
cable can be replaced.
This type of ducting is applicable for
roads with narrow ROW.
Digging of road is required for
maintenance & repair. Hence concrete
paver blocks can be used for road
restoration work. The concrete paver
block does not provide smooth riding
comfort and is subjected to yield in the
long run.
4.2 Proposed Underground System In Various WidthsOf Roads:
Based on the site survey conducted, ABD area consists of approximately 64KM of roads between 30M to 3Mwidth that need retrofitting to enhance the overall appearance of ABD area. Summary of the existing ROWwidth of roads are as under:
6% of the roads (4KM) are in the range of 3m to 5m
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 36 of 67
29% of the roads (19KM) are in the range of 6m to 8m
31% of the roads (20km) are in the range of 9m to 12m
34% of the roads (22km) are in the range of 14m to 30m.
Existing road map of ABD area is indicated in fig 11.Based on survey road map drawing, the road width ofHubballi town within the ABD area are indicated in table 6 & in fig. 12
Table 6 : ROW of roads in Hubballi ABD area
Sl. No. Road width in (m) Road length in (m) Road length in (KM)
1 3 366 0.366
2 4 1587 1.587
3 5 1888 1.888
4 6 10449 10.449
5 7 1266 1.266
6 8 6800 6.8
7 9 3534 3.534
8 10 9970 9.97
9 11 862 0.862
10 12 5937 5.937
11 14 4939 4.939
12 15 2202 2.202
13 16 2810 2.81
14 18 2643 2.643
15 22 2019 2.019
16 26 1606 1.606
17 30 5511 5.511
TOTAL 64389 65
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 37 of 67
Figure -11: Road map of Hubbali town
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart CityLimited
Prepared for Hubballi Dharwad Smart City Limited Page 38 of 67
Figure -12: Percentage road length of Hubbali town
Hence based on the road width available, the following sections are recommended for utility laying.
4.2.1 FOR ROAD WIDTH OF 14M TO 30M: Underground Pipe ducting for electrical & ICT cables on both side of the road are
recommended. A typical laying arrangement in Gokul Road is indicated in the cross-section
drawing below. Pipes are laid in trefoil formation.
150MM dia HDPE pipe are used for LT cables. For street lighting along the foot paths, HDPE
pipe of 100MM dia are used.
In 6 lane divided carriage way, two nos of 100mm dia HDPE pipe for ICT & street light cables
are proposed in the median.
Feeder pillar panels will be provided to connect each Commercial outlets/ Individual Houses.
From feeder pillar, connection to individual houses shall be through UG cables which will be
taken in 50mm dia HDPE pipe as indicated in the road sectional drawing.
For street lighting cable, underground pipe ducting on both side of the road and along the
median are recommended. Typical Laying arrangements are indicated in diagram 13.
At every 100 M, road crossings shall be provided with 3 x150MM dia RCC hume pipes for HT,
LT & ICT cables & 1 x100MM dia RCC hume pipes for street light.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 39 of 67
Figure -13: Layout sec. of Gokul Road (Typ)-Industrial estate junction to Airport
Figure -14: Layout section of Gokul Road- Hosur circle to industrial estate
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 40 of 67
Figure -15: Layout section of Siddappa Kambli Road- Hosur circle to Railway station
.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 41 of 67
4.2.2 For Road Width Of 9m to 12m Underground Pipe ducting for electrical & ICT cables on both side of the road are preferred. Laying
arrangement is indicated below.
Access chamber at every 50 metre for LT cables shall be provided.
Feeder Pillar Panels will be provided to connect each Commercial outlets/ Individual Houses.
Feeder pillar panel will be mounted on a panel stand over the storm water drain. Photographs of
feeder pillar, road crossing and man holes are indicated in fig.15, 16,17.
Cut out shall be provided on both side of the storm water drain so that half cut pipe of 50mm dia
can be placed for incoming LT cables to feeder pillar and for outging cables of feeder pillar to
individual house hold connections.
From feeder pillar, connection to individual houses shall be through UG cables which will be taken
in 50mm dia HDPE pipe as indicated in the road sectional drawing.
Power supply to household/ commercials on other side of the road shall be from the same feeder
pillars thro 150mm dia. HDPE pipe. Road crossings with pavered blocks shall be provided as
provisions for laying of the cables across the road. Typical Laying arrangements are indicated in
diagram 14.
At every 100 M, road crossings shall be provided with 3 x150MM dia RCC hume pipes for HT, LT &
ICT cables & 1 x100MM dia RCC hume pipes for street light.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 42 of 67
Figure -16: Layout sec. of 9M TO 12M wide Road (Typ)
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 43 of 67
Figure -17: Road crossing Figure -18: Feeder pillar Figure -19: Man hole
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 44 of 67
4.2.3 For Road Width Of 6m-8m Underground Pipe ducting for electrical & ICT cables on both side of the road are preferred. Laying
arrangement is indicated below.
Access chamber at every 50 metre for LT cables shall be provided.
Feeder pillar panels will be provided to connect each commercial outlets/ individual houses. Feeder
pillar panel will be mounted on a panel stand over the storm water drain.
Cut out shall be provided on both side of the storm water drain so that half cut pipe of 50mm dia
can be placed for incoming LT cables to feeder pillar and for outging cables of feeder pillar to
individual house hold connections.
From feeder pillar, connection to individual houses shall be through UG cables which will be taken
in 50mm dia HDPE pipe as indicated in the road sectional drawing.
Power supply to household/ commercials on other side of the road shall be from the same feeder
pillars thro 150mm dia. HDPE pipe. Road crossings with pavered blocks shall be provided as
provisions for laying of the cables across the road. Typical Laying arrangements are indicated in
diagram 18.
At every 100 M, road crossings shall be provided with 3 x150MM dia RCC hume pipes for HT, LT &
ICT cables & 1 x100MM dia RCC hume pipes for street light.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 45 of 67
Figure -20: Layout sec. of 8M wide road (Typ)
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 46 of 67
4.2.4 For Road Width Of 3m To 5m:
For roads under 3m to 8m, underground Pipe ducting for electrical & ICT cables on one side of the
road are preferred. Laying arrangement is indicated below. Access chamber at every 100 metre for
LT cables shall be provided.
Feeder pillar panels will be provided to connect each commercial outlets/ individual houses.
From feeder pillar, connection to individual houses shall be through UG cables which will be
taken in 50mm dia HDPE pipe as indicated in the road sectional drawing.
Power supply to household/ commercials on other side of the road shall be from the same feeder
pillars through 50mm dia HDPE pipe. Road crossings with pavered blocks shall be provided as
provisions for laying of the cables across the road. Typical laying arrangements of pipes in 3M to
5M width road are indicated in diagram.
Figure -21: Layout sec. of 3M TO 5M wide Road (Typ)
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 47 of 67
4.3 Proposed HDPE Ducts for Underground Ducting: HDPE ducts are preferred for underground ducting instead of RCC ducts. Cost efficiency,
installation flexibility and other properties of HDPE ducts make them frontrunner than RCC
ducts.
Comparative study of HDPE & RCC ducts are indicated in fig 20 & 21
Figure -22: De-merits of RCC pipe
Figure -23: Merits of HDPE pipe
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 48 of 67
4.3.1 HDPE Ducts For Fibre Optics And CommunicationCable
Multiple Bundled PLB (Permanent solidly Lubricated Silicore) HDPE ducts provides pathways & the
ability to install fiber optic cables and communication cables for the Fiber optic network, all within the
same multichannel construction. The multiple channel enables to install OF cables for present needs
and a provision for futuristic use as when demand grows. Fig. 22 shows the view of multiple bundled
HDPE ducts.
Figure -24: Multiple bundled ICT duct
4.3.2 Comparative Analysis Of Different Types Of Pipes:Comparative analysis of HDPE, RCC,GI & PVC pipes are indicated in table 7
Property RCC Pipe Conventional HDPEPipe
HDPE power duct
ChemicalResistance
No resistance to mostalkalis & acids.
Good resistance toacids & alkalis
Good resistance toacids & alkalis
Soil Settlement Does not adjust itselfto soil settlement andcracks.
Flexible, Does notcrack
Flexible, Does notcrack
Transportation &Handling
Very heavy & brittle.Difficult to handle,chances of breakagesduring handling andtransportation. Costof transportation is
Easy handling. Costof transportation islow
Easy handling. Cost oftransportation is low
Suitable both for direct buried and direct
install applications.
Duct sizes 20MM to 50MM OD ; in 2 way,
3 way, 4 way, 5 way & 7 way.
Reduces consumption of man holes,
fittings and saves project management
cost.
Table 7 : Comparative analysis of different types of pipe
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 49 of 67
4.4 Recommendations: Based on above feasibility study, for underground ducting of overhead transmission line, directly
buried HDPE pipe ducting for LT transmission lines(415V), fibre optic or any other utility cables or
wires are recommended.
high.
Flexibility Rigid, cannot be bent. Flexible Flexible
Inner wall andLaying of Cable
Internal surface ofthe pipes are notsmooth. Hencechances of cabledamage duringpulling.
The internal &external surface ofthe pipes are smoothand free fromgrooving & otherdefects.
Smooth Silicore innerlayer or Ribbed forreduced PullingForce.
HDD Technique Not Possible. Cable installation byHDD MethodPossible.
Not Possible.
Salient Features Heat generated incable plus Dynamicload does notdeform or melt theRCC pipe.
Heat generated incable plus Dynamicload makes theHDPE pipe to deformor melt and makes itunsustainable forlonger product cyclelife.
The power ductshave three concentriclayers viz. outerlayer, middle layerand inner layer withribs.The unique design ofRibbed duct allowsfor a lower coefficientof friction for poweror copper cableduring laying . Hence,heat generated incable plus Dynamicload does not makethe HDPE power ductto deform or melt andmakes it sustainablefor longer productcycle life.
Method of laying HDD not Possible.Suitable for open cutmethod.
Suitable for open cutand HDD method.
Suitable for open cutand HDD method.
Cost per metre Rs.410/meter (as perDHARWAD PWDS.O.R 2016-2017)
Rs.620/meter (asper BWSSB S.O.R2016-2017)
Rs.1350/meter (asper price list ofDURA-LINE)
Service life The expected servicelife of RCC pipe is lessthan 10 years.
The expected servicelife of HDPE pipe is25 years.
The expected servicelife of HDPE powerducts not less than 50years.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 50 of 67
Based on above cost implication chart and advantage and disadvantages of different underground
system, we recommend underground HDPE pipe ducting for LT cabling, ICT & telecommunication
cables, HT cables are directly buried in RCC C-pipe.
For maintenance purpose, access chamber at every 100m interval shall be provided.
Concrete paver blocks shall be used on footpaths and on-street parking areas on every roads. It will
give a good aesthetic view as compare to cast in situ concrete roads. With regards to maintenance, the
damaged blocks can be easily replaced where as in case of concrete roads the replacement of damaged
concrete is difficult.
Smart metering is not considered in this feasibility report since for application of smart metering, the
entire power supply distribution system has to be studied separately. Also, the same was discussed
with HESCOM. Since the implementation plan lacks the clarity, HDMC along with consultant team
should discuss with stake holders and line departments to close this.
4.5 Approach & Methodology, Studies, SurveysIncluding Data Collection, Analysis
Approach can be briefed as per the table below:
Table 8 : Approach adopted for project
Step Activity Detail
1 Base line study Overview of power demand.
Sources of power supply.
Collection of available data.
Review of existing DPRs and reports.
2 Data Analysis Type of underground system & type of pipe used forunderground 11kV overhead transmission line from reports ofHESCOM.
3 TechnologyEvaluation &
Feasibility ReportPreparation
Screening and Identification of type of ducting forunderground 415V power supply line based on techno-economic feasibility
Screening of technology on the basis of Modularity, scalability,Flexibility.
4 Policy finalization. Finalization of type of ducting based on feasibility as well asdiscussions with HDMC officials
Willingness survey to adapt to these new policies.
5 Preparation ofLayout, cost, and
Cost preparation for proposed underground ducting.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 51 of 67
DPR Preparation of DPR.
6 Preparation ofTender
Preparation of request for proposal and tender documentsinviting quotations from vendors
7 Tender Finalisationand Award of
Contract
Award of contract after techno-economic analysis of thequotations
The methodology adopted is tabulated as below:
Table 9: Methodology
Sl.No Scope Methodology Remarks
Task 1: Kick off Meeting with Commissioner and stake holders Hubballi- Dharwad Smart City Limited.
Task 2: Reconnaissance Site Visit to the ABD area
1 Study of existing
overhead transmission
lines in the city
Assessment of data collected
General Reconnaissance Survey
Task 3: Analysis and evaluation of existing situation of power supply in the city and identification of relevant key
weaknesses and gaps
2 Study the current
scenario of power
outages, power demand,
existing overhead
transmission line based
on data available with
the HDMC, electricity
department as well as
from the report of
HESCOM.
Consultation with HDMC electricity
department and collection of all the relevant
data related to power supply in the city and
existing scenario.
Site visit and data collection
The data collection would be carried out in
terms of:
Present scenario of overhead transmission
lines- Already undergrounded or under
execution.
Existing R.O.W available in public streets.
Analysing gaps in the existing
system as well as the newly
framed plan.
Underground ducting are
planned to be implemented
along existing public streets
in the right-of-way after
survey and land use pattern
study.
Strengthen thetransmission anddistribution network tocater to the expectedgrowth in demand ofexisting as well as futureconsumers.
Task-4: Preparation of feasibility report
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 52 of 67
3 Studying the various
options for conversion of
415V overhead
transmission line to
underground in ABD
area.
Consultation with Special Officer and
electricity department as well as the
Commissioner, HDMC to freeze
concept plans before proceeding to
feasibility.
Feasibility options were outlined after
studying the existing scenario of
underground system in the city.
Focus on technical,
economical as well as
social feasibility.
Task-4: Preparation of Detailed Project Report
4 While structuring the
project, consultant shall
take into account factors
influencing techno-
commercial viability,
existing regulatory
scenario, awareness as
well as potential support
mechanisms for making
projects financially
viable.
The project viability model would be
formulated considering the long term
sustainability of effective underground
system.
The conceptual plan would be developed
based on the available data and study.
Approval would be taken on the conceptual
plan from Municipal Corporation
Task-5: Preparation of Tenders and selection of a competent bidder according to technical, economic
criteria as well as HDMC norms.
4.6 Best Case Studies for similar projects inIndia/World
Smart roads in Bangalore
Every urban road in Bangalore is an example of the chaos of traffic, broken footpaths, hanging cables,
clogged drains, overflowing sewage & haphazard street lights, transformers & telecom fixtures.
Temporary fixes with poor design & construction result in repeated digging & fixing of the same road
over & over again. In order to ensure good infrastructure and pedestrian safety in the city, the Tender
S.U.R.E(Specification for urban road execution) project was taken up to enable free flow of traffic. The
St Mark’s Road, residency road & Vittal Mallya Hospital Road, developed under the Phase 1 of
TenderSURE, were thrown open to the public for use. Now, water pipeline, sanitary line, electricity,
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 53 of 67
storm water drains and all other essential utilities have come under the footpath. Henceforth, agencies
should not find reasons to dig roads. Snapshot of a smart road is indicated in fig.23
Figure -25: Bangalore smart roads under tender S.U.R.E
Gift city, Gujarat
GIFTCL has proposed the Utility Tunnel to carry all the MEP Utility services such as electricity, water,
solid waste, district cooling supply pipes, etc to various blocks all over the city. It is built to avoid the
disruption caused by recurring construction, repair and upgrading of cables and pipes in direct burial
trenches. One of the greatest advantages is public safety. Tunnels also allow rapid access to all utilities
without having to dig access trenches or resort to confused and often inaccurate utility maps.
Snapshot of a utility tunnel is indicated in fig.24
Figure -26: Utility tunnel, Gift city, Gujarat
4.7 Referenced Studies and Surveys
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 54 of 67
The consultant team has collected existing data from site visits as well as consultation with residents,
HDMC officials etc.
4.8 SWOT Analysis
The SWOT analysis carried out for the city for the implementation of underground system in the Hubballi
ABD area is provided in the table below:
Table 10: SWOT Analysis
Strengths
Low AT &C losses within 18% in financialyear FY2017.
Launched 24 x 7 helpline for lodgingcustomer complaints and rectifying thesame within stipulated time.
Weaknesses
Reluctance of people and improper
infrastructure availability in terms of ROW
of roads.
Opportunities
City is under rapid development ofinfrastructure developments with SmartCity, BRTS and SBM schemes.
Proposed on going smart city initiatives.
Threats
Ignorance and long term behavioural
attitude of people.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 55 of 67
5. Project Financials
5.1 Project Design
Depending on the features that need to be provided for underground ducting, the capital cost has beentabulated in Table-11
Table 11 : Capital cost of under grounding
Sl No Features Cost (Crores)
1
Road width of 3M-5M for 4KM
2.00Supply of HDPE pipe –415V, ICT & street light.
Pull chambers- 415V & ICT cables
Earth excavations on both side of road
Back filling on both side of road
2 Road width of 6M-8M for 19KM 14.00
Supply of HDPE pipe –415V, ICT & street light.
Pull chambers- 415V & ICT cables
Earth excavations on both side of road
Back filling on both side of road
Supply of 150mm dia. Hume pipe-Road crossing
3
Road width of 9M-12M for 20KM
16.00
Supply of HDPE pipe –415V, ICT & street light.
Pull chambers- 415V & ICT cables
Earth excavations on both side of road
Back filling on both side of road
Supply of 150mm dia. Hume pipe-Road crossing
4 Road width of 14M-30M for 22KM 20.00
Supply of HDPE pipe –415V, ICT & street light.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 56 of 67
Pull chambers-11kV,415V & ICT cables
Earth excavations on both side of road & in median
Back filling on both side of road & in median
Supply of 150mm dia. Hume pipe-Road crossing
Road cutting and reinstatement 60.00
Total capital cost 112.00
O&M cost 6.00
Total Cost 118.00
Laying of cables for LT and ICT not included in price list. It would be ideal if the works are carried outin one go.
Shifting of the utility cables shall be done by utility provider. Hence, cost is not considered.
Cost of feeder pillars (connecting individual consumers) not considered.
Cost of cables connecting individual consumers from feeder pillars not considered.
Cost of pipes from feeder pillar to individual consumer not considered.
Regarding smart metering, the same was discussed with HESCOM. Since the implementation plan is
not clear, HDMC has to discuss with stake holders. Hence implementation and cost of smart metering
is not considered.
As the city is undergoing for 24x7 up-scaling and NMT, it is admissible, if the works of underground
ducting and up scaling projects are taken up at the same time. This not only synchronizes the works,
but will also reduce the additional burden of road reinstatement again and again along with lesser
disruption to traffic and local residents.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 57 of 67
6. Statutory and LegalFramework
6.1 Legal And Regulatory Framework:
As the land belongs to corporation, no major legal aspects are noticed for the proposed underground
ducting in the ABD area. The construction activity can be on open bid system under the overall
supervision of SPV/PMC.
The following aspects may be considered:
Shifting of existing utility lines and its implication on the service delivery for the existing customers.
There is an ongoing project on 24X 7 water supply system for entire Hubbali municipal corporation
area & synchronizing the proposed 24X 7 up scaling work and this underground ducting work can
provide substantial savings in the capital cost in terms of road reinstatement works.
As underground ducting for low voltage is carried out only for ABD area, non ABD area service
implications may have to be addressed by the utility service providers.
It is also advisable if the underground ducting project are implemented along with the 24X7 water
supply upscaling project.
6.2 L0cal Regulatory Framework
As per the Environmental regulations in India, no Environmental clearance is not required for these
types of works.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 58 of 67
7. Indicative Environmental &Social Impacts
7.1 Introduction:
In this Chapter potential impact on the environment from the proposed Underground ducting in the ABD
area are identified based on the nature and extent of various activities associated during construction and
after completion of the project. The proposed expansion activities will have impact of varying magnitude
on environmental components both beneficial (positive) and adverse (negative) impacts. Both these
(positive and negative) impacts are considered for the impact prediction studies.
7.2 Air quality:
7.2.1 Impacts during Construction for proposedproject:
The potential ambient air quality impacts arising from the proposed project would occur mainly during
construction phase. During construction, the project would have two major impacts on ambient air
quality due to increase in gaseous emissions by construction equipment’s and vehicles, and an increase
in dust by construction activities. Earth excavation work, foundation work, superstructure work, material
storage, transportation and handling of construction materials, and wind erosion are the major factors
that would produce a temporary, localized increase in SPM and RPM levels. The increased movement of
heavy vehicles carrying construction materials, operation of DG sets as standby power back up system
would generate gaseous emissions. However as DG sets are used as standby, the impacts are
insignificant. The degree of dust generated would depend on the soil compaction and moisture content of
the ground surface during construction. Dust and exhaust particulate emissions from equipment
operations would temporarily degrade air quality in the immediate construction zone. The increase in air
particulates would be minimized by the performance of the work. The construction contractor shall
visually monitor dust levels on the site during construction. Dust suppression needs to be instituted,
using water tankers mounted on tractors, sprinklers and other means as necessary.
7.2.2 Impacts during Operation
The Structures at the project site would be expected to have no impact on air quality during their normaloperation Impacts during Construction.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 59 of 67
7.2.3 Mitigation Measures:The impact on the air quality due to the operation of construction machineries in the site is found to be
insignificant. However, the negative impacts created as a result of movement of construction vehicles
needs critical attention. For mitigation of these impacts, following measures are suggested:
Vehicles transporting construction materials prone to fugitive dust emissions should be covered.
Trucks carrying sand should be provided with tarpaulin sheets to cover the bed and sides of the trucks.
Idling of delivery trucks or other equipment should not be permitted during loading and unloading
All construction vehicles should comply with air emission standards and be maintained properly.
Dust suppression measures in addition to the traffic management should be followed on these roads
7.3 NOISE QUALITY
The potential source of noise associated in the construction includes the excavation, utility shifting,
movement of dumpers, transporting construction material, etc. Pumping of water seeping during
construction and transportation of muck material could also be the potential source for noise pollution.
Therefore, properly maintained machines and equipment’s should be used to minimize the impact of
noise on the surrounding environment. Trucks used for transportation of muck material shall be lined
with rubber or equivalent material that will minimize the noise generated during the loading and
unloading operation of muck materials.
7.3.1 Impacts during Construction
Construction activities normally result in temporary and short duration increase in noise level. The main
sources of noise during construction period include movement of vehicles for loading and unloading of
construction materials, fabrication, handling of equipment and materials, operation of concrete mixing
plants, generators, welding machines etc. The areas affected are those close to the site. Under the worst
case scenario, considered for prediction of noise levels during construction phase, it has been assumed
that all these equipment’s generate noise from a common point at an average noise level of 85 dB (A).
7.3.2 Impacts during OperationThe proposed structure at the project site is not expected to have any impact on Noise during their
normal operation.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 60 of 67
7.3.3 Mitigation Measures Restriction on the usage of noise generating activities and traffic movement in the Residential
areas to day light hours to avoid high noise and sleep disturbance to residents during
construction phase.
Generator sets should be provided with noise shields around them.
Vehicles used for transportation of construction material should be well maintained.
7.4 WATER QUALITYThe proposed project will cause minimal effect on the water quality. As the workers employed in the
construction phase will be housed locally and will be few in number, there will not be substantial quantity
of waste water generated by them.
7.4.1 Mitigation Measures High pressure hose should be used for cleaning and dust suppression purposes.
Discharge of construction wastes to surface water bodies or ground water should not be
allowed during construction. It shall be diverted to nearest sewer.
During Construction period in rainy season, the water quality is likely to be affected due to the
construction work and loosening of topsoil. This is likely to increase the suspended solids in
the run – off during heavy precipitation. It is envisaged that the monsoon period will be
avoided for cutting and filling of earthwork.
7.5 LAND ENVIRONMENTThe environmental impacts on land environment have been classified primarily into two aspects namely
i.e., direct impact on soil and land in the area. Land environment in the area has potential for
contamination if there are waste water discharges directly on to the land and from impacts arising out of
solid waste discharge on to the land. The proposed project is of very small scale and the discharges on
land from construction activity are minimal.
The Project Management Consultants (PMC) will adopt good construction practices that will ensure the
environmental impacts of waste effluents generated on-site during construction will be minimized.
7.5.1 Impacts of Construction WastesThe generation of waste material is inevitable during the construction phase of the development. Waste is
generated at different stages of construction process. Waste during construction activity relates to
excessive cement mix or concrete left after work is over, rejection caused due to change in design or
wrong workmanship etc. Excavation of earth and rock generates muck. Other wastes include top soil,
clay, sand, and gravel. These are normally re-used as filler at the same site after completion of excavation
work. Construction waste is bulky and heavy and is mostly unsuitable for disposal by incineration or
composting.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 61 of 67
7.5.2 Mitigation MeasuresThe solid waste generated during the construction phase is usually excavated earth material and
construction debris. Excavated earth material will be reused for backfilling; to fill up the low-lying areas
and whereas, topsoil will be reused for Landscaping / Greenbelt development purpose.
7.6 SOCIO ECONOMIC IMPACTS FOR PROPOSEDPROJECT
The project can improve the service of the Power supply system in the area. The positive impact of the
proposed activity is expected during the start-up of construction activities as well as through its life.
Besides the local population would be benefited from the 24x7 power supply, local dealers would be
benefited from contracts and supply of construction materials. The project will lead to better life styles.
This will lead to economic and social upliftment of the area.
7.7 POTENTIAL ENVIRONMENTAL IMPACT MATRIXThis methodology incorporates a list of project activities with a checklist of environmental components
that might be affected. Matrix method incorporates environmental conditions on one axis and proposed
actions on the other.
The impacts of each action on various environmental components are marked in a tabular format to
estimate the impacts which may be either qualitative, insignificant, high, adverse, beneficial or
quantitative by assessing a numerical score, but in the end there should be a grand total to signify the
magnitude of the impact. The activities discussed above are likely to affect the environment in varying
degrees. Relevant components of environment, which are likely to experience some impacts due to the
proposed project activities, have been identified.
Environmental parameters are broadly classified under three following groups considering the cause -
effect relationship:
Physical Environment
Biological Environment
Non Biophysical Components (NBP)
The parameters selected for impact identification are site activities and project specific. Differentparameters considered under the said groups are as follows:
Ambient Air Quality
Noise
Soil stability / erosion
Vegetation
Resource use
Health
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 62 of 67
Socio economic
The interaction between project activities and environmental parameters described above are shown in
the impact matrix in , the matrix points out each activity and its impact on specific environmental
parameters. This is a qualitative work and does not indicate quantitative impact. Some of the impacts are
temporary and localized and some impacts are short term and long term in the matrix.
The predicted impacts of the proposed project have been discussed - The environmental management
measures to reduce the adverse impacts are detailed in this Section.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 63 of 67
Table 12 : Potentiail environmental impact matrix for Hubbali town
Project Activities Physical Biological Non Biophysical Components (NBP)
Air Quality NoiseSoilstability/ erosion
WaterQuality
Vegetation
Health(Individual/Community,Occupational)
Socio-economic(Population,CommunityInfrastructure,Employment)
City - Implementation Phase
Construction of underground ducting- Excavation,Erection, Fabrication, Finishing
ST, -ve ST, -ve Nil ST, -ve Nil Nil LT, +ve
Operation of undergroundducting
Nil Nil Nil Nil Nil LT, +ve LT, +ve
Note: ST – Short Term, LT – Long Term, +ve – Potential Positive Impact, -ve – Potential Negative Impact (requires mitigation measures)
Table 13 : Summary of environmental management plan
Parameters Potential AdverseEnvironmental Impacts
Proposed Mitigation Measures ResidualImpacts
Implementation Issues
Responsibilities Monitoring
Under- groundducting
Gaseous emissions byconstruction equipment’s andvehicles, and increase in dust byconstruction activities
Vehicles transporting construction
materials prone to fugitive dust
emissions should be covered.
All construction vehicles should comply
with air emission standards
Dust suppression measures in addition
to the traffic management should be
followed on these roads.
NotSignificant.
Contractor HDSCL / PMC
Noise pollution from movementof vehicles for loading andunloading of constructionmaterials, fabrication, handlingof equipment and materials,operation of concrete mixingplants, generators etc.
Restriction on the usage of noise
generating activities in the Residential
areas to day light hours.
Generator sets should be provided with
noise shields around them.
Vehicles used for transportation of
construction material should be well
maintained.
NotSignificant.
Contractor HDSCL / PMC
Ground water pollution frompercolation of constructionwaste water.
High pressure hose should be used for
cleaning and dust suppression purposes.
Discharge of construction wastes to
nearest sewer.
Avoid earthwork during monsoon
season
NotSignificant.
Contractor HDSCL / PMC
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 64 of 67
7.8 CONCLUSION Envisaged benefits proposed underground ducting in city of hubballi-dharwad are as below.
Mitigation measures for adverse impacts have also been attributed below. The proposed
project will have positive impacts on the socio-economic environment of the study area. The
project will provide direct and indirect employment for Skilled, and unskilled personnel,
hence providing a boost to the local economy.
24 x 7 power supply in the city along with minimum outages. When underground ducting
system are well mapped, they also allow rapid access to all utilities without having to dig
access trenches or resort to confused and often inaccurate utility maps.
One of the greatest benefit is public safety. Underground power lines, wheather in common or
in separate channel, prevent downed utility cables from blocking roads, thus speeding
emergency access after natural disasters.
Dust suppression measures in addition to the traffic management should be followed.
Waste water discharged from the construction activities shall be diverted to the nearest sewer.
Noise produced from vehicular movement and construction activities can be curbed to
minimal by making use of noise shields for machinery, carrying out maintenance of vehicles,
and by restricting construction activity to day time.
Regular monitoring of air, water and noise parameters shall be carried out to keep a check on
routine compliance of statutory requirements.
The proponent strongly believes in the concept of sustainable development and understands the impacts
as identified above from the proposed project and will take all measures to mitigate such negative
impacts and also lay emphasis on the implementation of the recommendations of the Environmental
Management Plan in true spirits.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 65 of 67
8. Operating Framework
8.1 INDICATIVE PROJECT STRUCTURING
The project is headed by the Managing Director (MD) - Special Purpose Vehicle (SPV). The Project
Management Consultant (PMC) will manage the project in coordination with SPV and Hubballi-
Dharwad Municipal Corporation (HDMC). The technical aspects of the project will be handled by the
PMC. The project will be executed by the Contractor, who will be selected through the open tendering
process. Operation and Maintenance of the project will be carried out by HDMC/ private operator who
can carry out routine maintenance.
8.1.1 MilestonesThe major milestones and time allocated for the completion of each milestone is tabulated in Table 14below:
Table 14: Major Milestones and Time Allocated
Sl. No. Milestone Time Required(Months)
Cumulative Period( months)
1 Mobilisation 0.50 0.50
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 66 of 67
Sl. No. Milestone Time Required(Months)
Cumulative Period( months)
2 Site Visit 0.50 1.00
3 Design 2.00 3.00
4 Implementation 57.00 60.00
The capital costs and financial aspects of the project have been detailed in Chapter 6.
8.1.2 Operation and Maintenance
O&M has to be taken care of by the service providers; who will maintain the system as per the
required standards. As this is a major project impacting the aesthetics of the city, a fully dedicated
O&M strategy with dedicated staff committed to the implementation of the project is required. As
this project to be constructed under smart city funds; HDSCL will supervise the O&M.
8.2 RISKS AND MITIGATION
8.2.1 Risks Since a large capital will be invested on the construction and maintenance of the underground
ducting system, it is important to check that these are used properly
The ignorance among people may lead to non-usage of all these features.
Possibility of theft of man hole covers in economically backward areas.
8.2.2 Mitigation
Service provider should ensure proper operation and maintenance of the system.
Bringing awareness among citizens and educating them through social media, newspapers
and notices. This will prevent misuse.
Feasibility Report – Underground Ducting for Electrical/Data distribution - Hubballi Dharwad Smart City Limited
Prepared for Hubballi Dharwad Smart City Limited Page 67 of 67
9. WAY FORWARD ANDCONCLUSIONSBased on the above feasibility report, it is expected that, HDSCL accords their approval for
construction of underground ducting in the ABD area along with the conformation for all stake
holders associated with the project. This will also help the project to be implemented without any
land issues and the project can be expected to be completed as per the schedule provided in table 15.
Table 15 Tentative planning for next deliverables
Description Owner Tentative Timing
Approval of feasibility report HDSCL 31-08-2017
Submission of DPR PMC 16-10-2017
Approval of DPR HDSCL 8-11-2017
Submission of tenderdocuments
PMC 31-12-2017