Monthly report March 2019 Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv Building of the multifunctional complex on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv. Section B Monthly report march 2019 "29 th» March 2019 Director LLC "DNA VIP __________ David Maor Monthly report March 2019 p. 1 of 19

Upload: others

Post on 26-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Building of the multifunctional complex on 100-A Vasylkivska street, in the

Holosiivskyi district of Kyiv.

Section BMonthly report march 2019

"29 th» March 2019

Director LLC "DNA VIP __________ David Maor

Ukraine01034. Kyiv1-D Skovoroda st.LLC "DNA VIP"Tel: +38 (044) 257-30-59Fax: +38 (044) 257-30-27e-mail: [email protected]

Monthly report March 2019p. 1 of 15

Page 2: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Contents

1 Introduction Рage 32 Provided service Page 33 P. 2.1.1 and 2.1.5. Control over violation of the requirements of the agreed and

approved project documentation. Technical supervision of a construction.Page 4-10

4 P.2.1.7. Verification of the presence of documents which confirm qualitative characteristics of a structure, products, materials and equipment.

Page 7

5 P.2.1.10. Control over the maintenance of the general log of the construction works

Page 7

6 P.2.1.4. Control over the compliance of safety regulations during the construction. Page 87 P.2.1.2. The degree of the construction's facility readiness. Page 8-12

Monthly report March 2019p. 2 of 15

Page 3: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

1. Introduction

Services of the technical supervision of the construction of a residential complex with built-in

trading and office premises, situated on the 100-A Vasylkivska street, in the Holosiyivsky district of

Kyiv according to the contract "About the provision of technical supervision services, respectively" to

the requirements of the current legislation of Ukraine.

2. Provided service

The process of execution of work on the construction site was planned on the basis of the schedule of

execution of works (Appendix No. 1 to the contract of the general contract, developed in аugust 2017).

2.1.1. Control of quality. Control over violation of the requirements of the agreed and approved

project documentation, construction norms, rules, standards and specifications, approved project, the use

of substandard building materials, structures, products.

2.1.2. The Construction readiness degree and determination of degree of backlog of the planned deadlines

for the completion of the relevant construction stage specified in the project documentation and

construction schedule, by providing the Customer with conclusions.

2.1.4. Control over the compliance of safety regulations during the construction, provided by the State

construction regulations and rules of Ukraine.

2.1.5. Technical supervision of the construction in accordance with the requirements of the approved

design documentation;

2.1.7. Verification of the availability of documents which confirm qualitative characteristics of structures,

products, materials and equipment used during the construction - technical passports, certificates,

documents that reflect the results of laboratory tests, devices and technologies in accordance with the

design documentation, legislation and boundary indicators of works cost.

2.1.9. Controlling measurements, carried out at the time of inspection by the state supervisory bodies and

departmental inspections, as well as the independent conduct of control measurements of performed

work;

2.1.10. Control over the maintenance of the general log of the construction works of the standard sample

Monthly report March 2019p. 3 of 15

Page 4: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

P. 2.1.1. and 2.1.5. Control of quality. Control over violation of the requirements of the agreed and

approved project documentation, construction norms, rules, standards and specifications,

approved project, the use of substandard building materials, structures, products. Technical

supervision of the construction in accordance with the requirements of the approved project

documentation.

Ventilation and heating networks.

According to sections WS and HW from 03.01.1 9 till 03.28.1 9 .

1. Quality control of air conditioner and boiler drainage networks in bathrooms on 3rd, 17th, 20th,

21st and 22ndfloors of block “B”.

Works are completed according to the project.No remarks.

2. Quality control bathroom floors base hydro isolation on 17th, 20th, 21st and 22nd floors of block

“B”.

Works are completed according to the project.No remarks.

3. Quality control of water supply networks in bathroomson3rd, 12th, 17th, 20thand 21st floors of

block “B”.

Works are completed according to the project.No remarks.

4. Quality control of air conditioners drainage networks in apartments on 3rd, 4th, 11th, 14th, 15th

and 23rd floors of block “B”.

Works are completed according to the project.No remarks.

5. Quality control of air conditioners drainage networks connection to sewage in apartments on

8th, 9th, 11th, 13th, 14th, 15th, 16th, 18th and 29th floors of block “B”.

Works are completed according to the project.No remarks.

Monthly report March 2019p. 4 of 15

Page 5: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Finishing work.

Quality control of floor creed.

Work is completed at marks:

+12.050; +15.050; +21.050; +24.050; +30.050; +33.050; +36.050; +39.050; +42.050; +45.050; +48.050;

+51.050; +54.050; +57.050; +60.050; +63.050; +66.050; +69.050; +72.050

Works are completed according to the project.

No remarks.

Quality control of plastering works (apartments + places for common use).

Work is completed at marks:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks.

Quality control overlaying plates, putty.

The work is carried out by the marks:

+15.150; +18.150; +21.150;+24.150; +27.150;+30.150; +33.150; +36.150; +39.150; +42.150;

+45.150+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks.

Works on the device of warming and decorative finishing of a facade are carried out.

Quality control. Works are carried out at the following markings:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Installation of entrance doors to the apartments.

Quality control. Work is completed at marks:

+15.150; +18.150; +21.150;+24.150; +27.150;+30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69,050; +72,050.

Works are completed according to the project.

Monthly report March 2019p. 5 of 15

Page 6: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

No remarks.

Installation of doors at the exits to the balcony cold transition

Quality control. Work is completed at marks:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks

Works on the installation of fencing balconies

Quality control. Work is completed at marks:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks.

Installation work on low-voltage systems.

Quality control. Work is completed at marks:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks.

Electric networks and lightning protection

Quality control. Work is completed at marks:

+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;

+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;

Works are completed according to the project.

No remarks.

Installation of elevators

Quality control

Completed installation of all elevators (two KONE elevators and one Doppler elevator). Preparation of

elevators for commissioning, experimental operation.

Works are completed according to the project.

No remarks.

Monthly report March 2019p. 6 of 15

Page 7: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Apartments are completed with furniture, interior items, lamps, washbasins, toilet bowls, mixers

tap /

Monthly report March 2019p. 7 of 15

Page 8: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Monthly report March 2019p. 8 of 15

Page 9: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Finishing works and furnishing of the lobby are carrier out.

Monthly report March 2019p. 9 of 15

Page 10: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

P.2.1.7. Verification of the presence of documents which confirm qualitative characteristics of a

structure, products, materials and equipment, which are used during building of the facility, such

as technical passports, certificates, documents that reflect the results of laboratory tests, devices

and technologies in accordance with the design documentation, legislation and boundary indicators

of works cost. The quality of reinforcing products and concrete mix is controlled constantly as well as

laboratory analyses of materials. The quality of materials and products meets all necessary regulatory

acts, state standards passports, certificates.

P.2.1.10. Control over the maintenance of the general log of the construction works of the standard

sample. Verification of the necessary records in works logs, author's supervision monitoring ,

availability of necessary licenses;

The logs of author's supervision,production works, concrete, welding and joint works are being

conducted, there are no remarks.

P.2.1.4. Control over the compliance of safety regulations during the construction, provided by the

State construction regulations and rules of Ukraine.

The perimeter of the building's site, the area of production (floors), the work of the tower crane and

the assembly area of the reinforcement frame are fenced. The passages of the elevator's shafts are closed,

the overlap is installed in the mines.

Monthly report March 2019p. 10 of 15

Page 11: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

All builders work in protective helmets, vests, belts and overalls. All floors are cleaned, staircases

are fenced, the construction site is in good condition. Toilets are installed in the construction camp and on

the upper floors of building; containers for household and solid construction waste are provided as well as

their regular export.

Logs of operational control over the state of occupational safety, registration of instructions on the

safety of work in the workplace, instructions for the right of movement of goods by a base and a screw

crane, the issuance of safety devices and personal protective equipment, periodic inspection of removable

load grip devices and containers, are kept. Logs of operational control over the state of occupational

safety, registration of instructions on the safety of work in the workplace, instructions for the right of

movement of goods by a tower crane, the issuance of safety devices and personal protective equipment,

periodic inspection of removable devices and containers

are conducted. There is no remarks.

Fire safety of the construction camp. The register of instructions about fire safety is conducted.

Warehouses are equipped with extinguishers, fire-prevention shields are completed, "Instructions about

fire safety in office and household premises" are present. The condition of electrical networks in premises

which were mentioned earlier is normal. All house hold premises are grounded.

Conclusions of the section: In general, the quality of performed works corresponds to the

working project and operating norms, measures for the protection of labor and industrial

sanitation on the construction site in proper condition.

P.2.1.2. The construction readiness degree and determination of degree of back log of the

planned deadlines for the completion of the relevant construction stage, specified in the project

documentation and constructions chedule, providing the customer with conclusions.

General condition of the construction works of a residential complex with built-in trading-office premises on the 100-A Vasylkivska street, in the Holosiivskyi district of

Kyiv, Section B.01.04.2019

№ п.п Stage Maximum Cost

of a stage

Execution for reporting

period:

Execution of a stage on:

Percentage of execution on:

Marh 2019 01.04.2019 01.04.2019

1Preparatory work, temporary

buildings, permits, risk insurance. Gas boiler,

77 944 079,66 0,00 77 944 079,65 100,00

Monthly report March 2019p. 11 of 15

Page 12: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

technical conditions.2 Soil development 250 000,00 0,00 250 000,00 100,00

3 Arrangement of the pile foundation of the house 6 310 500,00 0,00 6 310 500,00 100,00

4 Concrete pile caps and force plate of the building 6 065 280,00 0,00 6 065 280,00 100,00

5 Damp proofing of walls 92 400,00 0,00 92 080,56 99,656 Monolithic frame 33 761 812,50 0,00 33 795 045,25 100,10

7Installation of reinforced

concrete structures (ventilation channels)

3 199 200,00 0,00 3 199 200,00 100,00

8Installation of reinforced

concrete structures (passages of staircases)

550 000,00 0,00 550 000,00 100,00

9 Brick masonry (internal) 5 086 800,00 0,00 5 086 800,00 100,0010 Facade masonry 5 878 125,00 0,00 5 878 125,00 100,0011 Brick masonry of partitions 2 205 000,00 0,00 2 205 000,00 100,00

12 Installation of windows and balcony doors 4 411 875,00 0,00 4 411 875,00 100,00

13 Installation of aluminum stained glass windows 3 630 000,00 0,00 3 630 000,00 100,00

14Plaster works

(apartments+places for common use)

7 361 280,00 0,00 7 361 280,00 100,00

15 The arrangement of a wet facade 5 362 500,00 0,00 4 826 250,00 90,00

16 Arrangement of balcony partitions 1 959 750,00 0,00 1 371 825,00 70,00

17 Networks of heating and ventilation of the house 11 000 000,00 0,00 11 000 000,00 100,00

18Networks of the water supply and sewerage system of the

house10 500 000,00 0,00 9 850 000,00 93,81

19 Floors 3 384 850,00 0,00 3 384 850,00 100,0020 Installation of apartment doors 2 345 000,00 0,00 2 345 000,00 100,00

21 Installation of fire-prevention doors 275 000,00 0,00 275 000,00 100,00

22 Decorating works (apartments) 54 530 712,50 650 000,00 37 594 962,64 68,94

23Decorating works (places for

common using technical buildings elevator halls)

3 818 880,00 572 832,00 1 908 496,00 49,98

24 Roof 831 060,00 0,00 831 060,00 100,0025 Fire alarm system 1 700 000,00 0,00 1 445 000,00 85,0026 Fire alert system 450 000,00 0,00 382 500,00 85,0027 Smoke protection system 3 000 000,00 0,00 3 000 000,00 100,0028 Gas fire extinguishing system 180 000,00 0,00 144 000,00 80,0029 Water fire extinguishing 600 000,00 84 000,00 599 000,00 99,8330 Pump station 1 200 000,00 0,00 1 200 000,00 100,00

Monthly report March 2019p. 12 of 15

Page 13: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

31 Low current networks 3 750 000,00 0,00 2 625 000,00 70,00

32 Electric networks and lightning protection 5 500 000,00 550 000,00 5 225 000,00 95,00

33 Individual heating point 1 and 2 5 000 000,00 0,00 5 000 000,00 100,00

34 Installation of elevator equipment 4 068 414,00 65 000,00 4 064 993,30 99,92

35 Illumination of facades and territory 600 000,00 0,00 0,00 0,00

36 Video monitoring, access, control 1 500 000,00 0,00 0,00 0,00

37 Dispatcher system 250 000,00 0,00 0,00 0,0038 Entrance groups and lobby 4 500 000,00 225 000,00 4 050 000,00 90,00

39 Premises for bicycles and carriages 153 360,00 0,00 0,00 0,00

40 Planting 315 000,00 0,00 0,00 0,0041 Sport ground 121 600,00 0,00 0,00 0,0042 Playground 305 220,00 0,00 0,00 0,0043 Paving shaped elements  530 750,00 0,00 0,00 0,0044 Asphalt 1 155 000,00 0,00 0,00 0,0045 Total 285 633 448,66 2 146 832,00 257 902 202,40 90,29

Conclusions on the section: on the 01 of April 2019, the degree of readiness of the Construction

Facility is 90,29 %, there is no lagging behind the planned deadlines for the completion of the relevant

construction stage specified in the project documentation and construction schedule.

Composed by: _____________ S.Zholtikov

Permit documentation

Monthly report March 2019p. 13 of 15

Page 14: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Permit for construction work

License for construction work of the contracting entity LLC KDD ENGINEERING http://kdd.ua/uk/#company

Monthly report March 2019p. 14 of 15

Page 15: ukraine-israel.comukraine-israel.com/.../uploads/2019/04/DNA-march-2019.docx · Web viewServices of the technical supervision of the construction of a residential complex with built-in

Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv

Expert opinion