Page 1: UBS Australian Utilities Conference

UBS – Australian Utilities Conference

29 April 2010

AGL External

AGL Energy Limited

Regulatory reform: Blowing in the right direction

Jeff DimeryGroup General Manager Merchant Energy

Page 2: UBS Australian Utilities Conference

2

Disclaimer

The information in this presentation:

› Is not an offer or recommendation to purchase or subscribe for securities in AGL Energy Limited or to retain any securities currently held.

› Does not take into account the potential and current individual investment objectives or the financial situation of investors.

› Was prepared with due care and attention and is current at the date of the presentation.

› Actual results may materially vary from any forecasts (where applicable) in this presentation.

› Before making or varying any investment in securities in AGL Energy Limited, all investors should consider the appropriateness of that investment in light of their individual investment objectives and financial situation and should seek their own independent professional advice.

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 3: UBS Australian Utilities Conference

3Investment in renewable technologies

Wind is the global technology of choice among renewable technologies- 63% of investment in 2009 (US$60bn)

Source: PEW Centre (2010)

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 4: UBS Australian Utilities Conference

4

Technology cost curve

» Source: ACIL Tasman, AGL, Roam, MMA

Renewable technologies

UBS – Australian Utilities Conference

29 April 2010

AGL External

Wind currently has a substantial cost advantage

Page 5: UBS Australian Utilities Conference

5

Policies globally driving renewable investment

Since mid-2009, a number of new policies have been announced that will drive renewable investment

Country/State Renewable Mandate

Spain 22.5% renewable by 2020

US – Colorado 30% renewable by 2020

US - Alaska 50% renewable by 2025

Israel 10% renewable by 2020

Kuwait 5% renewable by 2020

» Source: DB Climate Change Advisors

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 6: UBS Australian Utilities Conference

6

Expanded Renewable Energy Target…

Source: Roam, AGL

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 7: UBS Australian Utilities Conference

7

$0

$10

$20

$30

$40

$50

$60

$70

$80

$90

$100

Sep-03 Mar-04 Sep-04 Mar-05 Sep-05 Mar-06 Sep-06 Mar-07 Sep-07 Mar-08 Sep-08 Mar-09 Sep-09

$/R

EC

Expanded MRET Passed

Expanded MRET Announced

Drought Impacting Hydros

SHW & PV Increases REC Bank

Renewable Energy Certificates: Prices start to rise

Penalty effectively raised to $93 per MWh.

› Responsibility resides with retailer

› Increased penalty recognises need to incentivise development of higher cost renewable sites

› Anticipate rapid rise in REC prices following development of low cost sites and ramp up of target

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 8: UBS Australian Utilities Conference

8

Impact of Renewable Policy Setting

Source: AGL Greenhouse modeling

Fundamental changes required to generation mix.

New Build Generation MixYears of Forecast - 2010 to 2020

2,800MW

5,500MW

5,500MW

4,500MW

9,500MW

1,200MW

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

Original 2006 forecast(ETS, 2% MRET)

Current 2010 forecast(ETS, 20% Expanded RET)

Cap

acit

y r

eq

uir

ed

(M

W)

Coal Plant CCGT Base Plant OCGT Peak Plant Renewable Plant

Renewables dominate

OCGT peaking plant displaces CCGT base plant

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 9: UBS Australian Utilities Conference

9

Renewable Energy Certificate (REC) obligations

› Macarthur (365MW) conditional commitment

› Federal legislation requires AGL to surrender approximately 9 million RECs per annum by 2020

› Strong pipeline of development opportunities

› Proven capability in site selection, project development and performance

› Development pipeline delayed until improved MRET policy framework

Appropriate regulatory settings required to facilitate investment.

1. Excludes long-term supply agreements and Voluntary REC demands.

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 10: UBS Australian Utilities Conference

10

Australia has a world class wind resource

› Wind resource is best in Tasmania and areas in Western Australia, South Australia and Victoria

› NSW, Queensland and the Northern Territory have limited large scale wind potential

› The best wind sites are already being taken in Tasmania, South Australia and Western Australia

Average wind speeds (metres per second)

> 8

6-8

4-6

<4

Source: CSIRO

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 11: UBS Australian Utilities Conference

11

Wind farms: Success factors

A number of critical issues can mean success or failure of a wind farm development:

› Wind resource

› Land access (support by landowners)

› Capital cost

› Connection access: (cost, loss factor, grid capacity)

› Wind farm scale (to absorb certain fixed cost)

› O&M costs (typically only around 2% of capital cost per year)

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 12: UBS Australian Utilities Conference

12

Wind farms: Cost profile

1

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 13: UBS Australian Utilities Conference

13

Wind resource drives turbine selection

› Wind speed generally increases with height

› Wake effects reduce yield and drives turbine spacing

› Hallett Wind Farm stages 1, 2 and 4 are classic wind farm sites with prevailing winds perpendicular to ridge

Location of Hallett 1 turbines & wind speeds

N

Wind Rose for Hallett 1

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 14: UBS Australian Utilities Conference

14

Wind project diversity improves reliability

Geographical diversity enhances the level of ’firm’ generation.

0

10

20

30

40

50

60

70

80

90

100

Sun 06 Mon 07 Tue 08 Wed 09 Thu 10 Fri 11

Half hour time increments (6-12 April 2008)

Win

d g

enera

tion (

MW

)

$1

$10

$100

$1,000

$10,000

Regio

nal pool pri

ce (

$/M

Wh)

Wattle Point Hallett 1 Pool Price

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 15: UBS Australian Utilities Conference

15

Delivering high capacity factorsOperational performance exceeds investment assumptions.

1

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 16: UBS Australian Utilities Conference

16

Strong growth pipeline

Market leading portfolio provides strategic depth and optionality.

Project Nominal Capacity (MW) Location Type Project Status Definition

Bogong 140 Victorian Alps Hydro Commissioning Committed

McKay Creek Up Rate 10 Victorian Alps Hydro Commissioning Committed

Hallett 2 71 SA - Hallett Wind Commissioning Committed

Hallett 4 132 SA - Hallett Wind Under Construction Committed

Werribee Expansion 2 VIC - Werribee Biogas Under Construction Committed

Oaklands Hill 67 VIC - West Wind Under Construction Committed

Hallett 5 52 SA – Hallett Wind Under Construction Committed

Macarthur 365 VIC - West WindIn Development, JV with

MeridianConditional

Commitment

Barn Hill 130 SA - Redhill Wind DA Approved Probable

Hallett 3 80 SA - Hallett Wind In Development Possible

Crows Nest 150 QLD - Toowoomba Wind Permitted Possible

Ben Lomond 150 NSW - Armidale WindLandowner Agreements in

PlacePossible

Coopers Gap 300 QLD - Kingaroy WindLandowner Agreements in

PlacePossible

Other 3 Projects totalling up to 600 Various Various Under Review Possible

REN

EW

ABLE G

EN

ERATIO

N

UBS – Australian Utilities Conference

29 April 2010

AGL External

Page 17: UBS Australian Utilities Conference

17

Summary

UBS – Australian Utilities Conference

29 April 2010

AGL External

› Significant progress with renewable policies

› Critical that legislation is passed in May/June 2010

› Requires ~ $30 billion of investment in renewable generation

› Delay to CPRS is disappointing

› Uncertainty adversely impacts investment decisions

› Wind will be the dominant renewable technology over next decade

› AGL’s renewable portfolio performing well

› First-mover advantage

› Considerable development and operational experience

› Well-positioned portfolio of sites

Page 18: UBS Australian Utilities Conference

18

A range of information on AGL Energy Limited including ASX & Media Releases, Presentations, Financial Results, Annual Reports and Sustainability Reports is available from our website: www.agl.com.au

Alternatively, contact:

INSTITUTIONAL INVESTORS & ANALYSTS

John Hobson

Head of Investor Relations

AGL Energy Limited

phone: +61 2 9921 2789

Mobile: +61 (0) 488 002 460

e-mail: [email protected]

Further Information / Contacts

RETAIL INVESTORS & MEDIA

Nathan Vass

Investor Relations & Media

AGL Energy Limited

phone: +61 2 9921 2264

mobile: +61 (0) 405 040 133

e-mail: [email protected]

UBS – Australian Utilities Conference

29 April 2010

AGL External