OPTIMIZING THE ROI ON ENERGY EFF IC IENCY
Save On Energy Symposium Date: June 22nd, 2017
Presenter: Mark Glasier
U N I O N G A S I N C E N T I V E P R O G R A M
NATURAL GAS S T O R A G E ,
T R A N S M I S S I O N A N D D I S T R I B U T I O N
$8.2 B I L L I O N
I N A S S E T S
D A W N
HUB
C A N A D A ’ S
TOP 100 E M P L O Y E R S
E N B R I D G E I N C .
NYSE: ENB
100+ Y E A R S
Who we are
Whom we serve
Over
400
Ontario communities
1.4 million
customers
Ontario based
Natural Gas Advantage
We’re committed to conservation
• To help you use energy effectively, responsibly
• To help to keep industry and jobs in Ontario
• To keep you competitive
U N I O N G A S E N E R G Y E F F I C I E N C Y P R O G R A M
YOUR SUCCESS IS OUR SUCCESS.
U N I O N G A S E N E R G Y E F F I C I E N C Y P R O G R A M
Lower your cap-and-trade costs by improving your energy efficiency
W O R K I N G I N A L O W - C A R B O N E C O N O M Y
U N I O N G A S E N E R G Y E F F I C I E N C Y P R O G R A M
The ROI on eff iciency
CASH INCENTIVES R E D U C E U P F R O N T I N V E S T M E N T REDUCED USAGE
L E S S E N S I M PA C T O F C A P A N D T R A D E
EQUIPMENT UPGRADES R E D U C E O P E R AT I N G C O S T S
ROI O P T I M I Z E PAY B A C K A N D O N G O I N G S AV I N G S
Save money and energy • Specific incentives for equipment
with set capacities or outputs
• Space heating
• Water heating
• Cooking
U N I O N G A S C U S T O M E R I N C E N T I V E S
$6,000 / unit
CONDENSING BOILER INFRARED HEATER CONDENSING UNIT HEATER
CONDENSING FURNACE
$400 / unit $750 / unit
$200 / unit
Commercial Space Heating Programs
$0.40 / CFM
CONDENSING MAKE-UP AIR UNIT
$3,000 / building
BOILER LOAD CONTROL
UP TO UP TO
UP TO UP TO
Commercial Space Heating Programs
ENERGY RECOVERY VENTILATOR
UP TO
$1.15 / CFM
HEAT RECOVERY VENTILATOR
UP TO
$0.75 / CFM
AIR CURTAIN PEDESTRIAN DOOR
UP TO
$1,000 / unit
AIR CURTAIN SHIPPING DOOR
UP TO $1,800 / unit
DEMAND CONTROL VENTILATION SYSTEM
WITH CO2 SENSOR
$500 / unit
Commercial Water Heating Programs
$8,000 / unit
OZONE LAUNDRY EQUIPMENT
UP TO $6,000 / unit
CONDENSING BOILER
$200 / unit
FRONT-LOADING CLOTHES WASHER
– CEE TIER 2
$450 / unit
CONDENSING TANKLESS WATER HEATER
UP TO
Commercial Foodservice Programs
ENERGY STAR®
STEAM COOKER
$450 / unit
HIGH EFFICIENCY UNDER-FIRED BROILER
$500 / unit
DEMAND CONTROL KITCHEN VENTILATION
UP TO
$4,600 / unit
ENERGY STAR®
DISHWASHER
UP TO $450 / unit
UP TO
ENERGY STAR®
FRYER
$700 / VAT
CHALLENGE
PAYING FOR
CLIMATE-CONTROLLED AIR 24/7
THOUGH STORE OPERATES 12 HOURS/DAY
SOLUTION
FIVE NEW DEMAND CONTROL VENTILATION
UNITS WORK ONLY AS NEEDED BY
MEASURING CO2 LEVELS
TWO NEW PEDESTRIAN AIR CURTAINS
PREVENT FURTHER LOSS OF HEATED
AIR AT DOORS
Giant Tiger: 30% Savings, Great ROI
SAVINGS
30% REDUCTION IN ANNUAL GAS USAGE
$1,500 IN ANNUAL ENERGY SAVINGS
INITIAL INVESTMENT
RECOUPED IN LESS THAN 3 YEARS
ONGOING
SAVINGS YEAR AFTER YEAR
Giant Tiger: 30% Savings, Great ROI
COST
PROJECT COST
INCENTIVES
TOTAL
$6,600 $2,050 $4,550
-
Custom Engineering Projects Analyze, design
and optimize your energy
efficiency returns
Engineering feasibility
studies
Process improvement
studies
Study top-up
Energy saving measures
New and retrofit equipment
Meters
•
•
•
•
•
•
C O M M E R C I A L A N D I N D U S T R I A L C U S T O M E R I N C E N T I V E S
Custom Engineering Projects
PROJECT INCENTIVE - COMMERCIAL INCENTIVE - INDUSTRIAL
ENGINEERING FEASIBILITY STUDY 50% up to $4,000 50% up to $10,000
PROCESS IMPROVEMENT STUDY 66% up to $20,000
STUDY TOP-UP Feasibility Study Top-up 50% up to $10,000
Process Improvement Top-up 34% up to $20,000
NEW AND RETROFIT EQUIPMENT
Contract Service Rates $0.10/m3 up to $100,000
General Service Rates $0.20/m3 up to $40,000
Total incentive cannot exceed 50% of project cost
METERS 50% of installed cost
Limit: 5 meters/year per site
C O M M E R C I A L A N D I N D U S T R I A L C U S T O M E R I N C E N T I V E S
Boiler upgrade HIGHER EFFICIENCY BOILERS SAVE YOU MORE
Replaced 40% boiler (82% efficiency) with
new boiler (91.75% efficiency)
New boiler has energy efficient measures
like linkageless controls and an economizer
•
•
Project Cost $245,000 (incremental $53,000)
Incentive $11,011 ($0.10/m3)
Savings m3/yr 110,114
Cost Avoidance $27, 528
Simple Payback
1.9 years with Union Gas incentive
(2.4 years without)
CO2 Reduction 206.8
C A S E S T U D Y:
Optimizing your building’s energy use GET PAID TO
IMPLEMENT LOW-COST OR NO-COST
IMPROVEMENTS
R U N S M A R T P R O G R A M
Exceeding standards and saving money
Above and beyond
building codes
Buildings that work for
everyone
Getting help designing
more energy
efficient buildings
Commit your time, not
your capital
•
•
•
•
C O M M E R C I A L S AV I N G S B Y D E S I G N
Q&A
U N I O N G A S E N E R G Y E F F I C I E N C Y P R O G R A M
uniongas.com/savemoneyandenergy
For a full list of Union Gas Incentive Programs, please visit
TO APPLY FOR YOUR UNION GAS INCENTIVES OR LEARN MORE,
CONTACT YOUR UNION GAS
ACCOUNT MANAGER.
U N I O N G A S E N E R G Y E F F I C I E N C Y P R O G R A M
Start Saving Now