tyli program, corridor and construction management qualifications_2015

34
T.Y. Lin International A GLOBAL INFRASTRUCTURE FIRM PROGRAM, CONSTRUCTION, AND CORRIDOR MANAGEMENT CAPABILITIES & EXPERIENCE

Upload: chandra-revuru-mba-csi-cdt-ccca-ccm

Post on 08-Aug-2015

143 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TYLI Program, Corridor and Construction Management Qualifications_2015

T.Y. Lin InternationalA G L O B A L I N F R A S T R U C T U R E F I R M

P R O G R A M , C O N S T R U C T I O N , A N D C O R R I D O R M A N AG E M E N T

CAPABILITIES & EXPERIENCE

Page 2: TYLI Program, Corridor and Construction Management Qualifications_2015

1

A GLOBAL INFR ASTRUCTURE GROUPT.Y. Lin International (TYLI) is a member of the Dar Group, a global partnership

comprised of over 16,000 professional engineers, planners, architects, economists,

and scientists who share a common goal – the advancement of infrastructure around

the world for the betterment of local communities. The Dar Group has consistently

been ranked among the top international design firms in the world by Engineering

News-Record.

Having grown over the past 60 years into an internationally recognized, award-winning,

multi-disciplined, full service infrastructure consultancy, the Dar Group’s presence

and project experience span multiple continents around the globe. Our organization

specializes in providing technical leadership and expertise on all types of infrastructure

and facilities projects, in any locale worldwide.

San FranciscoGlobal Bridge TYLI China

TYLI Taiwan

TYLI MalaysiaTYLI Singapore

Coral GablesGlobal Aviation

M A R K E T S E C T O R S

Aviation

Bridges

Facilities

Ports and Marine

Power and Energy

Rail & Transit

Surface Transportation

Water and Wastewater

E N R T O P D E S I G N F I R M S ( 2 0 1 4 ) D A R A L H A N D A S A H

#8 - Top International Design Firms

#1 - Airports

#2 - General Building

#2 - Bridges

#2 - Transportation

#3 - Highways

#6 - Mass Transit and Rail

Page 3: TYLI Program, Corridor and Construction Management Qualifications_2015

2

Geographic Presence and Project Locations

Project Locations

WO R LDWI D E R ESO U RCESThe Dar Group’s geographic office presence and project

locations are depicted on the map below. The firms’ offices

provide local engineers, planners, architects, economists,

and scientists as an international network of professionals.

The Dar Group is dedicated to planning, designing and

managing infrastructure and facilities projects that contribute

to the sustainable advancement of local communities

worldwide.

The Dar Group operates from over 100 offices in 45

countries. As a member of the Dar Group, T.Y. Lin

International can draw upon the collective resources and

expertise of the entire consultancy, which includes the

member firms listed below:

• Dar Al-Handasah (Shair and Partners)

• Perkins + Will

• Penspen

• Landrum & Brown

• Pierre Yves Rochon

• R&H Railway Consultants Group

• IPA Advisory

• D2 Consult International

• Ross & Baruzzini

• Currie & Brown

• Maffeis

• Integral Group

Page 4: TYLI Program, Corridor and Construction Management Qualifications_2015

3

T.Y. L I N I NT ER N ATI O N A L FI R M OV ERVI E WWhat began in 1954 as a two-person firm created by our founder, Professor T.Y. Lin,

has since grown into an internationally renowned network of the best engineering talent

with the ability to draw upon the worldwide resources and expertise of the Dar Group.

Headquartered in San Francisco, California, T.Y. Lin International is ranked among

the Top 50 Designers (No. 44) in International Markets by Engineering News-Record.

With industry leaders in offices across the globe, each of our clients benefit from the

personal attention of our organization’s local professionals and worldwide experts,

delivering quality services and state-of-the-art technical solutions on a variety of local

infrastructure and facilities projects led by respected and world-renowned experts.

Page 5: TYLI Program, Corridor and Construction Management Qualifications_2015

4

PROGRAM MANAGEMENTWhat We DoStrong capabilities in all aspects of project and program management enable us to successfully provide oversight and project management services for billions of dollars in local, national, and international transportation construction improvements around the world, ranging from streets to freeways and interchanges, transit systems, airports, facilities, and transportation projects of all sizes in between.

Areas of ExpertiseOur staff includes program managers, project managers, project control specialists, schedulers, planners, engineers and scientists with proven experience in the project management and project delivery process. We take large transportation projects from inception through to completion.

Representative Clients• Regional Transportation Authorities & Transit

Agencies• State Departments of Transportation and Local

Municipalities• Airport Authorities• Transportation Agencies and Authorities• Public-Private Partnership Concessionaires

CORRIDOR MANAGEMENTWe bring our depth of expertise in Program Management and Construction Management to our clients’ most complex transportation corridors. TYLI is experienced in Corridor Management of new facilities, expanding new technology on existing corridors and complex reconstruction of high volume transportation facilities.

CONSTRUCTION MANAGEMENTWhat We DoTYLI recognizes to successfully complete a project depends on the ability, experience, and qualifications of our construction management team to identify a project’s relevant issues, and manage these issues with the appropriate actions. This is accomplished by continuously focusing on the construction underway, and by anticipating and identifying any future potential issues, and resolving them before they become challenges. Having an eye for detail and an understanding of construction practices, as well as the ability to focus on the broader picture, allows us to exceed client expectations.

Areas of ExpertiseThe TYLI Team is comprised of experts in all areas of engineering and transportation specialists in architecture, landscape architecture and environmental. Our team understands our clients have stringent practices in order to meet funding requirements and we focus not only on building the infrastructure right but preparing the construction documents to meet audits and allow for a seamless close out. Our team of experts are experienced in the following areas:

• Constructability Review of Plans

• Construction Layout/Verification

• Key Stakeholder & Community Coordination

• Traffic Control Coordination

• Utility Coordination

• Inspection and Documentation

• Material Testing

• Shop Drawing and Product Submittal Reviews

• Schedule Monitoring

• Progress Meetings

• Project Close-out

Representative Clients• Class I Railroads• Cities and Counties/ Local Municipalities• Highway Toll Authorities• Regional Transportation Authorities & Transit Agencies• State Departments of Transportation• Airport Authorities

Page 6: TYLI Program, Corridor and Construction Management Qualifications_2015

5

For TYLI, understanding the complexities of the design and construction process is

invaluable in guiding clients through the most critical phases of project development.

Following time-tested and proven engineering and construction practices, we’ve been

involved in safely bringing many of the world’s most challenging infrastructure projects

to fruition. We maintain and document communication, manage budget and schedules,

and ensure the quality of materials and the final product. To do this, we utilize the most

current programs and software for implementation including Primavera, GIS Tracking,

Project Wise - Bentley, custom-written MS Access, e-Builder, and a variety of tablet and

smartphone applications.

Our staff takes pride in solving some of the world’s most complex infrastructure

projects and working with our clients to successfully deliver them.

IT’S ALL IN THE DETAILS...

S E R V I C E S

Construction Administration

Document Control

Budget & Schedule Management

Quality Oversight

Plan & Coordinate Design Tasks

Construction Management & Inspection

Financial Reporting & Controls

Claim Management

Page 7: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S :

P R O G R A M M A N A G E M E N T

Page 8: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

7

a member of the Dar Group Companies

T.Y. Lin International is part of the Team selected to provide Program Management services for the new South Runway and Terminal 4 Expansion for Fort Lauderdale-Hollywood International Airport, this includes; the construction of the new South Runway, adjacent taxiways, high speed exits, north/south runway connector and holding pad; and enabling projects that will precede the new Runway. The Program also includes extensive remodeling and expansion Terminal 4, and coordination of construction within rights-of-way of the Florida Department of Transportation and Florida East Coast Railroad at Fort Lauderdale–Hollywood International Airport. The services provided by the Program Management Team include:

Program Management and Controls• Plan and coordinate all design and construction tasks • Manage and oversee the activities of one or more Construction Project Management firms assigned to the program• Prepare monthly Project Management Information System reports• RLI development and administration through to award stage• Coordinate/Record Sunshine negotiation meetings • Track project costs and schedules • Insure compliance with SDBE policies • Financial reporting and controls• Prepare Agenda Reports for the Board

Contract Administration • Review and approve payment applications from contractors and consultants • Review and approve change orders, claims, and contract price adjustments.• Prepare responses to RFI’s• Assist with negotiations on change management with contractors and consultants• Insure that permits, schedules, schedule of values, NTP’s, submittals, shop drawings and necessary approvals are submitted

and achieved in a timely manner• Insure that all warranties are in place and that punch lists have been completed

General Administration• Prepare, research and respond to BCAD with public record requests• Perform procurement functions with strict adherence to County Policy• Prepare monthly operations reports • Maintain close coordination and communication with all stakeholders

PROGRAM MANAGEMENT SERVICES FOR NEW SOUTH RUNWAY AND TERMINAL 4 EXPANSION OWNER’S REPRESENTATIVE SERVICESF O R T L A U D E R D A L E - H O L L Y W O O D I N T E R N A T I O N A L A I R P O R T , F L O R I D A

Page 9: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

8

a member of the Dar Group Companies

The Port of Miami is home to one of the world’s largest cruise ports and is a major cargo port in the United States. The port is located on Dodge Island, just off the coast of downtown Miami. The Port Boulevard Bridge, currently the sole access point to the port, has experienced significant vehicle traffic in recent years due to the growth of Miami’s cargo and tourism trades. The Port of Miami Tunnel Project was the culmination of a study performed by the Florida Department of Transportation, determining that a second point of entry to the port was necessary to help alleviate congestion on the Port Boulevard Bridge. The Tunnel project links the Port of Miami with the adjacent Interstate system, improving the passenger and cargo movement to and from the Port.

The Port of Miami Tunnel Project consists of three components: a Tunnel connection between Watson Island and Port of Miami; connections to the Port of Miami roadway system; and widening of the MacArthur Causeway bridge.

The tunnel structure is 3,900 feet in length and is composed of two tunnels, each containing two traffic lanes, curbs, walkways, ventilation fans and additional safety features. Each will be 36 feet in diameter and will connect Watson Island and the Port of Miami beneath the main shipping channel in the Biscayne Bay Aquatic Preserve, moving traffic to and from the Port. The bottom of the tunnels will be approximately 100 feet below the surface at their deepest point and will be constructed utilizing a Tunnel Boring Machine (TBM). For both travel directions, the roadway ramp connector alignments will descend into a depressed U-wall section and will continue to cut-and-cover sections at the tunnel entry portals and progress into separate tunnel bores beneath the main shipping channel.

The firm served the Florida Department of Transportation as a member of a technical advisory team that supported the agency in its efforts to procure a Concession Agreement with a concessionaire to design, construct, finance, and operate and maintain the facility over an extended period of time.

Some of the firm’s responsibilities included analysis and compliance with structural engineering, life safety requirements and environmental review/compliance.

PORT OF MIAMI TUNNELM I A M I - D A D E C O U N T Y , F L O R I D A

PROJECT HIGHLIGHTS• Twin-Bored Tunnel System• Cut-and-Cover Design• Public-Private partnership• Sub-aqueous Crossing• U-wall Structures• Environmental Review• Life Safety System Compliance• Technical Advisement and Procurement of

Concessionaire• Owner’s Representative Services

Page 10: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

9

a member of the Dar Group Companies

PROJECT HIGHLIGHTS• Program Management Oversight• Budget & Schedule Maintenance• Multi-agency Coordination

CALIFORNIA HIGH-SPEED RAIL PROGRAM MANAGEMENT OVERSIGHTS A C R A M E N T O , C A L I F O R N I A

T.Y. Lin International (TYLI) was selected by the California High-Speed Rail Authority (Authority) for the Program Management Oversight (PMO) of the statewide intercity High-Speed Rail System. High-speed trains will run from San Francisco to Los Angeles/Anaheim, with extensions to Sacramento and San Diego at speeds of up to 220 mph, and will interconnect with other transportation alternatives to provide a comprehensive, multifaceted rail network throughout California.

The planning, engineering and environmental work on the system is managed through a Program Management Consultant (PMC) and individual project delivery teams for each of the eight (8) segments of the 800-mile corridor. As the Authority’s PMO, TYLI performs direct oversight of the PMC through a comprehensive, multi-disciplined oversight team, and coordinates PMO activities with both the Authority staff and the PMC. Specifically, the PMO identifies and tracks ongoing project tasks, work progress, possible problem areas, and works with the PMC to make any needed adjustments and corrections to keep the program on schedule, within budget, and according to specifications.

The PMO supports the Authority in achieving its objectives with interagency work and also supports the Authority in its dealings with key federal regulatory agencies such as the US Army Corps of Engineers, as well as with the Federal Railroad Administration (FRA). Additionally, the PMO is responsible for advising the Authority on how to best manage and utilize various procurement and delivery options.

Page 11: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

10

a member of the Dar Group Companies

PROGRAM MANAGEMENT SERVICES FOR THE 2005-PRESENT CITYWIDE CONSTRUCTION ENGINEERING SERVICESC H I C A G O , I L L I N O I S

T.Y. Lin International (TYLI) was selected by the City of Chicago Department of Transportation (CDOT) to be one of three firms to lead the Citywide Construction Engineering Services contract. This contract required program and construction management for work consisting of various street and alley resurfacing, speed hump installation, sidewalk replacement, and curb and gutter replacement projects that were constructed by City labor forces called In-House Construction. One primary program that was serviced under this contract was the City of Chicago Aldermanic Menu Program, which allocates a budget to Alderman for infrastructure priorities within their respective wards. Other City work that has been serviced under this contract, for which TYLI provided construction expertise, includes ADA compliance, 311 repairs, vault reconstruction, speed hump installation, and pot hole patching, as requested by CDOT engineering.

The group was tasked to coordinate the overall program with CDOT engineering and In-House Construction. Pre-construction services included: providing the required survey; engineering and constructability reviews; developing the associated quantities; identification of private utility issues that impact construction; and field marking of approved project limits. Construction phase services included: construction schedule development and support coordination of public and private utility work within project limits; construction support to In-House Construction crews, as requested, to evaluate unforeseen conditions; development of as-built documentation for delivery to CDOT, and provision of QC checking by inspecting all completed ADA ramps to determine any necessary remedial work prior to submittal to the QA program for approval.

The bituminous alley and street resurfacing portion of the Menu program involved resurfacing of residential streets and alleys throughout the 50 city wards. TYLI provided Lead Survey Engineers and Field Engineers to review project sites, prepare menu surveys, assist with utility coordination services and calculate individual project quantities for the purpose of determining project costs.

PROJECT HIGHLIGHTS• Construction Management to lead

Citywide contracts• Coordinated City in-house teams• Scheduling support• $65M annual program

Page 12: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

11

a member of the Dar Group Companies

PROGRAM MANAGEMENT SERVICES FOR THE 2005-PRESENT CITYWIDE CONSTRUCTION ENGINEERING SERVICES CONTINUEDC H I C A G O , I L L I N O I S

The concrete portion Menu program included reconstruction of curb and gutter, and sidewalks throughout the city’s wards. TYLI provided the Concrete Coordinator who managed the over-all Concrete Program. TYLI was responsible for assigning Field Engineers to projects, reviewing daily work schedules, conducting meetings, identifying scope changes, forwarding recommended changes to CDOT for consideration and closeout of completed projects. To comply with the City’s updated ADA sidewalk ramp program requirements, TYLI also provided an ADA Coordinator who was responsible for the quality control verification of compliance on all sidewalk ramps constructed by the City’s In-House Construction division. TYLI reported findings to the City for quality assurance review.

Construction Scheduling Support

TYLI provides support services to develop the annual schedules for the CDOT’s street resurfacing and concrete sidewalk rehabilitation programs. These services utilize GIS mapping, Microsoft Project, and several of the City’s internal database and tracking software packages to schedule the City’s in-house labor forces. TYLI assists in promoting operational efficiency for CDOT’s construction operations while providing capital improvements equitably throughout the entire City limits. The City operates up to five paving operations and 25 concrete crews working throughout the City of Chicago all assisted by TYLI’s scheduling services.

Page 13: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

12

a member of the Dar Group Companies

Since 1997, T.Y. Lin International (TYLI) has provided planning and engineering services and in-house staff to the Chicago Department of Transportation (CDOT) to assist in creating the most bicycle friendly big city in America. TYLI develops Phase I planning studies, Phase II engineering design drawings and Phase III construction services for the installation of innovative bikeways designs, which include barrier and buffer protected bike lanes, and neighborhood greenways.

Under this task order, the TYLI’s primary objectives are to fulfill Mayor Rahm Emanuel’s commitment to install 100 miles of protected bicycle lanes in Chicago by 2015 and to provide bicycle program management services at the CDOT offices.

Program management activities include supervising other consultants designing bikeways in Chicago and working with other City departments to secure funding and project approvals.

Planning work includes project selection, data collection on roadway, traffic and land use conditions, stakeholder and public coordination, obtaining aldermanic approvals, coordinating with outside agencies and receiving internal city approvals.

Engineering work consists of collecting roadway geometric data, traffic counts, conducting traffic studies, preparing engineering design plans and providing construction inspection services. TYLI also assists CDOT in obtaining Illinois Department of Transportation (IDOT) approval on engineering designs plans, specifications and cost estimates for projects that are federally funded or on roadways under state jurisdiction.

Since the start of this Task Order, TYLI has been responsible for planning, designing and overseeing the installation of 55 miles of protected bike lanes in Chicago.

Bicycle Program AdministrationTYLI staff managed CDOT funding for consulting and construction services. TYLI developed the budget for internal and external (consultants) staff and proposed bikeways projects, identified funding opportunities, worked with elected officials on project approval and wrote successful grant applications for federal funding.

Currently, the TYLI team includes six planners and engineers that provide bicycle program management services at the CDOT offices. This program management team is responsible for planning, designing and implementing Mayor Rahm Emanuel’s objective of adding 100 miles of protected bicycle lanes in Chicago by 2015.

Program management activities include addressing internal CDOT administrative issues and procedures, preparing program budgets, and supervising other consultants that are involved in the planning, design, and implementation of the City’s bicycle system.

TYLI works on behalf of CDOT to obtain Illinois Department of Transportation (IDOT) approval on engineering designs plans,specifications, and cost estimates.

CHICAGO DEPARTMENT OF TRANSPORTATION BICYCLE PROGRAM MANAGEMENT (2011 – 2015)C H I C A G O , I L L I N O I S

PROJECT HIGHLIGHTS• Coordinate City in-house teams + consultants• Program Management

Page 14: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

13

a member of the Dar Group Companies

CITY OF ROCHESTER PARKING GARAGE EVALUATION AND MAINTENANCE PROGRAMR O C H E S T E R , N E W Y O R K

T.Y. Lin International (TYLI) was awarded a 5-year contract with the City of Rochester to evaluate and develop maintenance programs for eight City-owned parking structures. All of the structures are between 15 and 40 years old and most are cast-in-place, post-tensioned structures.

The scope of work for this project focused on annual inspections, development of a base-line rating system, condition reports, and preparation of an annual repair contract. A special emphasis was placed on structural and waterproofing systems. All of the building systems within each garage were visually inspected, including building envelope, elevator shafts, electrical, mechanical, plumbing, security, and revenue control systems. TYLI also proceeded with a strategic deck evaluation program, consisting of a chloride ion content analysis to determine the locations that would benefit most from a sealer or waterproofing membrane.

TYLI utilized the inspection and chloride content data along with life-cycle analyses to develop maintenance plans for each structure, separating immediate needs and preventative maintenance from long-term capital improvements. A prime example of this program’s success was the development of a creative and unique solution to the ongoing deterioration of the deck post-tensioning at the South Avenue Garage. TYLI developed an approach of installing supplemental post-tensioning and deck protection with the goal of providing a long-term solution that is easily constructible, minimally disruptive, and extends the useful life of the garage through the introduction of a redundant system.

In the final year of the contract, TYLI also designed elevator modernizations and replacements at four of the garages.

Work orders were developed as part of the program, for those items that could be addressed by City Building Services, Municipal Parking, or the garage operators. TYLI also assisted the City in preparing capital improvement budget requests and developing a yearly maintenance repair contract with a value in the $800,000 to $2,400,000 range. TYLI also provided construction administration and inspections for annual maintenance contract.

PROJECT HIGHLIGHTS• Term contract• Developed maintenance programs• Visual inspections

Page 15: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S :

C O R R I D O RM A N A G E M E N T

Page 16: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

15

a member of the Dar Group Companies

T.Y. Lin International (TYLI) was selected to provide Phase I Preliminary Design and Phase II Final Design Engineering Services for the Wacker Drive Viaduct and ramps from the Congress Parkway Interchange to the Adams Street Intersection. The Wacker Drive Viaduct from Michigan Avenue to the Congress Parkway is a multiple-span reinforced concrete structure that carries six lanes of traffic over a lower level four-lane mainline roadway and adjacent service drives. These upper and lower level roadways serve as the main Loop Area distribution and collector roadways to and from the Eisenhower Expressway, North Michigan Avenue business district and Lake Shore Drive.The structure is owned and maintained jointly by the City of Chicago and the Illinois Department of Transportation. The Michigan/Lake leg of the structure was constructed in the 1920’s and rehabilitated in the 1970’s. The Lake/Congress leg was constructed in the 1950’s. The overall condition of this structure was fair to poor. The existing roadway geometrics did not meet current design standards. Complete reconstruction was necessary to address the deteriorated condition and incorporate safety and capacity improvements.The section of Wacker Drive from Adams Street through the Congress Interchange includes two distinct structure areas. The viaduct portion, a two-level structure from Adams Street to Van Buren Street, is a cast-in-place reinforced concrete two-way slab structure supported by reinforced concrete columns and drop panels. The Congress Parkway interchange connects the Wacker Drive Viaduct to the Congress Parkway and several adjacent local roads. The interchange consists of a nineteen-span double deck reinforced concrete frame structure, three reinforced concrete box tunnel structures, a reinforced concrete retained earth structure and several reinforced concrete retaining walls. The Phase I services included:• Addendum to the Project Development Report• Intersection Design Studies• Bridge Inspections and Bridge Condition Reports• Utility Impact Assessment and Concept Design• Preliminary design of a ventilation system• Location Drainage Study

• Staging concepts, Preliminary Maintenance of Traffic (MOT) design, and Phasing Plan

• Pump station hydraulic report• Development of a preliminary streetscape design• Phase I special waste assessment• Type, size, and location drawings (TS&L’s)

The Phase II services included:• Complete contract documents for three bid packages:

Congress interchange, south viaduct, and advanced utility contracts

• Relocation design for watermains, storm sewer, sanitary sewer, gas and electrical facilities.

• Permitting• Final staging and MOT• Right-of-way documents• Financial plan to meet FHWA requirements

In order to minimize disruptions to vehicular and pedestrian traffic, adjacent building operations, and local businesses an extremely aggressive design and construction schedule was established. Working closely with CDOT, adjacent construction projects, and local building owners, TYLI was able to deliver this project on schedule and on budget.

PHASE I & II DESIGN ENGINEERING SERVICES, WACKER DRIVE VIADUCT FROM CONGRESS PARKWAY TO ADAMS STREETC H I C A G O , I L L I N O I S

PROJECT HIGHLIGHTS• Civil oversight responsibility for corridor during design

phase• Overall traffic analysis for final design and during various

construction phases• Continuity and standardization of details and specifications

for all parts of corridor• Lead responsibility for coordination associated with the

extensive and complicated utility relocation• Overall lead for the Maintenance of Traffic/Phasing

Development

Page 17: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

16

a member of the Dar Group Companies

T.Y. Lin International (TYLI) was selected to provide technical oversight and coordination of professional services for the survey, preliminary design and final design improvements between the South Subway Portal near 16th/Clark to 98th Street, an approximately 10.5 mile corridor. The Segment A project scope included analysis of existing conditions including bridge condition inspection and design and preparation of contract documents for renewal of approximately 14,700 lineal feet of double track on CTA’s Dan Ryan rail services. This section included four bridges and the tunnel and incline structures at 29th. Project OversightAs Lead Designer for the Dan Ryan Track Renewal Project, TYLI was responsible for developing and implementing the overall design approach, and coordinating the production of deliverable documents by the design firms and its subconsultants, as well as the field survey consultants.TYLI was also responsible for developing a complete and comprehensive set of contract specifications and drawings for common technical specifications and drawings to be used by the Consultants as part of their design of the reconstruction elements. Specific scope elements included:

• Working with data provided by the survey consultant, developing baseline plan and profile geometry depicting existing centerline of right of way, centerline of track, top of rail, curve data and superelevation of the existing track.

• Identifying factors influencing alignments, limits of geometry improvements and corresponding operating speed for CTA review. Submitting potential exceptions to CTA Design Criteria for CTA consideration.

• Reviewing CTA standard drawings for typical ballasted track construction. Submitting recommended modifications for CTA review. Incorporating these in contract documents accordingly.

• Investigating alternative types of track construction, i.e. direct fixation/slab track, through CTA transit station platforms. Submitting recommendation(s) for CTA review. Developing preliminary design for approved alternative.

Civil/TrackThe project included analysis of existing conditions, reports and drawings, and design and preparation of contract documents for renewal of approximately 10,400 lineal feet of double track on CTA’s Dan Ryan rail service. Approximately 1400 lineal feet of double track associated with the 23rd Street and 33rd Street Interlockings had been reconstructed recently and was excluded from this Segment except for incidental connections and/or minor modifications.

SEGMENT A OF THE DAN RYAN RED LINE TRACK RENEWAL PROJECTC H I C A G O , I L L I N O I S

PROJECT HIGHLIGHTS• Oversight for 10-mile corridor• Consistency of complicated details and approach in

Construction Documents• Standardized details and specifications for all parts of

project• All segments of project had continuity & consistency• TYLI’s project oversight role included the following:

» Developing and implementing the overall design approach to accommodate a 154 day construction duration and coordinating the production of deliverable documents by the design firms and their sub-consultants, as well as the field survey consultants.

» Coordinating all signal, traction power and communications design work to ensure all design components were implemented into a cohesive and comprehensive set of contract documents.

» Generating a comprehensive set of contract specifications and drawings to be used by all DORs to ensure consistency of design.

Page 18: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

17

a member of the Dar Group Companies

Track renewal generally included replacement of deteriorated track components with new continuous welded rail (CWR), ties, fasteners, ballast, sub-ballast, geotech fabric, subgrade and drainage improvements, as well as traction power distribution system improvement.Design and contract documents required detailed attention to preserving the integrity of currently functional signal, communication and traction power system cables, ducts and related components.The design included drawings and supporting specifications for use by the Contractor to aid and identify the necessary Construction staging, as directed by CTA.Structures/TunnelTYLI prepared Bridge Condition Reports (BCRs) to document the physical condition and functionality of the existing tunnel and ballasted deck structures. Field inspections were performed to document the existing condition of the structures and were used as a basis for evaluating rehabilitation and potential improvements. TYLI submitted a detailed, site specific, inspection plan that is prepared by and includes inspection supervision by a licensed Structural Engineer - for CTA review.The field investigation consisted of a detailed inspection using up-close, hands-on access to all exposed elements. The Bridge Condition Report summarized the results of the field inspection and provided recommendations for rehabilitation and/or improvements for each structure. Finally, this report summarized recommendations and provided a cost estimate for the proposed rehabilitation and improvement work.Large Team Schedule• Careful planning and organization of the design approach was a critical factor in meeting the aggressive nine month design

schedule• Strong design oversight mechanism to maintain design consistency between multiple disciplines and two independent design

teams• Production of one comprehensive set of construction documents conforming to the common design approach, details and

specifications, permitting the various DORs to work independently and efficiently within an established set of design criteria, drawing templates and common specifications

SEGMENT A OF THE DAN RYAN RED LINE TRACK RENEWAL PROJECT CONTINUED...C H I C A G O , I L L I N O I S

Page 19: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

18

a member of the Dar Group Companies

T.Y. Lin International (TYLI) has been selected to serve as Project Management (PM) Consultant to assist the Illinois Department of Transportation Division of Public & Intermodal Transportation, Bureau of Capital Transit (IDOT) in overseeing the design and construction of a Multi-Modal Regional Transportation Center (MRTC) in Joliet, Illinois. The new Joliet MRTC facility presents an opportunity to create a transportation improvement that benefits local and regional travelers. Bringing together Amtrak, High Speed Rail, Metra, Pace and intercity busses in a common facility will vastly improve access and create a positive effect on the local and Will County economies, as well as the regional transportation network.

TYLI is providing both design oversight and construction engineering services for the Joliet MRTC project. Design oversight activities include: master schedule and budget monitoring; establishing and maintaining a web-based document control system; reviewing all design submittals,coordinating environmental and utility relocation activities; constructability and staging reviews, including contractor site access and storage and maintenance of traffic; conducting Quality Management Plan compliance reviews; and coordinating with the key stakeholders, including IDOT, City of Joliet and their project consultants, Union Pacific Railroad, Burlington Northern Santa Fe Railroad, Metra, Amtrak and Pace.

During construction, TYLI will provide resident engineering services, including field inspection, quality assurance, material testing, survey support, submittal and shop drawing coordination and engineering support. Project controls and documentation will include progress meetings, budget and schedule controls, pay estimate review and contract modification preparation, responses to contractor requests for information and project closeout.

This project will require an extensive amount of coordination and communications among railroad operations and engineering, transit agencies and intercity carriers, governmental agencies, utilities, local residents and businesses and local elected officials. TYLI is focused on the maintenance of passenger and freight operations during construction. The construction of the MRTC may require partial or total closures of Metra and Amtrak station and parking facilities, use of temporary facilities and shortened platform boarding areas, all of which could have significant impacts on rider’s convenience and safety if not properly designed and staged. Likewise, Metra, BNSF and UPRR track and signal relocations must be carefully planned, staged and coordinated with freight and passenger operations to minimize delays while providing access to complete the necessary construction work.

TYLI has worked with all project stakeholders, Joliet, UP, BNSF, Metra and Pace to establish and monitor overall project scope, master budget and schedule controls for the project. TYLI has managed its own budget to allow for additional project activities and time coverage within the original estimated cost.

DESIGN OVERSIGHT AND CONSTRUCTION MANAGEMENT FOR THE JOLIET MULTIMODAL TRANSPORTATION CENTERJ O L I E T , I L L I N O I S

PROJECT HIGHLIGHTS• Program Management• Coordinating Multiple Stakeholders• Maintenance of Traffic• Establish/Monitor Master Budget and Schedule Controls

Page 20: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

19

a member of the Dar Group Companies

T.Y. Lin International (TYLI) was selected by the Illinois Department of Transportation (IDOT) to provide Phase I and II engineering services for the construction of a new I-57 Interchange at I-294 (Tri-State Tollway) in Cook County, Illinois, one of two places in the United States where Interstate highways crossed with no interchange. The Phase I work was processed utilizing an accelerated schedule with design approval received one year after notice-to-proceed.Phase I work was also required along 147th Street to address potential capacity issues from proposed interchanges, correct existing roadway deficiencies and other safety issues. The intent of the Phase I work was to investigate the project area, conduct studies and make recommendations to enable preparation of a summarizing Combined Design Report with Structure Type, Size and Location drawings to enable approval by the reviewing agencies. Documentation of additional Environmental Assessment (EA) factors not identified in previous studies was also provided. The Phase I work included appropriate studies and definition of the following items to be designed in Phase II:

• Geometry of multiple new ramp and flyover bridges at the I-57/I-294 Interchange

• Replacement of bridges at the I-57/147th Street and I-294/147th Street Interchanges

• Bridge inspection and condition reports for structures to be rehabilitated and modified to accommodate new/revised geometrics

• Work on numerous other bridges including their removal and replacement, rehabilitation, and widening to be defined

• Multiple retaining walls• Extensions and/or replacements of existing box culverts and

new box culverts

• Conceptual signage • Pavement marking types• Traffic signals as part of the Intersection Design Studies• Determination of lighting type/concept• Detention pond analysis and locations• Floodway and floodway impacts and analysis• Project phasing, staged construction, and financial

constraints and implications• Safety improvements identified as part of the overall project

crash analysis

Subsequent to the receipt of Design Approval, an initial Value Engineering Study was performed by an outside firm. Additional detailed geometric analysis resulted in changes to the ramp configuration, a reduction in overall ROW requirements and a $20 million savings in construction. Phase II consisted of preparing construction documents including plans, specifications, cost estimates and related contract materials. It was anticipated the full build-out of the defined interchange improvements would take place over an extended time frame based on available IDOT, Illinois Tollway and/or Federal funds and on the ability to acquire the necessary right-of-way. Multiple sets of staged construction plans were prepared, providing for the logical, sequential construction of roadway segments as defined in Phase I. Multiple Stakeholder CollaborationThe design portion of the project presented a large amount of complex design issues along with coordination with the local agencies. Roadways within the project limits were under the jurisdiction of several agencies, including Illinois Department of Transportation, Illinois Tollway, Cook County Highway Department, and various local municipalities with oversight by the Federal Highway Administration.ComplexitiesEach plan set needed to be designed as a ‘stand alone’ set that could be won by a separate contractor while also allowing enough flexibility for multiple contractors to work on adjacent segments. The design components were planned so that they could be sequentially placed in operation, including overlapping Maintenance of Traffic on two major interstate highways.

PROJECT HIGHLIGHTS• Collaborative effort with Tollway and IDOT • Met both agencies’ requirements for bid packaging/phasing• Met all schedules, despite their fast-tracked nature• Phasing Plan, Financial Plan, Project Management Plan

I-57/I-294 INTERCHANGE PROJECT - PART ONE S O U T H E R N C O O K C O U N T Y , I L L I N O I S

Page 21: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

20

a member of the Dar Group Companies

The I-15 Express/Bus Rapid Transit (BRT) Lanes Improvement project was completed as part of SANDAG’s Early Action Program. The project included the widening of the 20-mile freeway, from California State Route (SR) 78 in Escondido to SR 163 in San Diego to accommodate the addition of reversible High Occupancy Toll (HOT) lanes in the median of the freeway. The express lanes provide connectivity to four adjacent transit centers with park-and-ride facilities via direct access ramps (DAR). The DARs allow buses, carpoolers, vanpoolers, and FasTrak (California’s electronic collection system) users to access the express lanes, bypassing general congestion on the on-ramps. In mid-2014, new BRT began operations along I-15 using the express lanes and DARs. New BRT services include all-day, all-stops, bi-directional freeway service; an all-day, limited stop, bi-directional service; and two peak periods, peak-direction-only Commuter Express services.

The San Diego-bound services allow passengers to connect to the local BRT services. The entire system is controlled by a sophisticated Intelligent Transportation Systems (ITS) infrastructure that includes variable pricing to help control congestion. The project required existing bridges (undercrossings and overcrossings) to be widened or replaced with special retaining walls and drainage design in order to accommodate the new DARs and express lanes. TYLI worked on an accelerated schedule for all segments of the project providing design and other support services as the prime consultant to Caltrans District 11, Caltrans Office of Special Funded Projects, and Caltrans Structures Design.

TYLI was also a subconsultant on other teams, leading to the completion of plans, specification, and estimates (PS&E) for construction bids. TYLI’s work was performed at Hale Avenue Undercrossing, W. Mission Avenue Undercrossing, Mercy Road Undercrossing, Los Peñasquitos Creek Bridge, Pomerado Tieback Retaining Wall, and Pomerado Road Overcrossing. TYLI staff served as the overall Project Manager for the consultant teams on the South Segment and as the Structures Lead for several Units within the North and South Segments.

I-15 EXPRESS/BUS RAPID TRANSIT LANES IMPROVEMENTS A N D I E G O , C A L I F O R N I A

PROJECT HIGHLIGHTS• Completion of specifications and plans for construction

bids• Corridor Management• Project Management for consultants

Page 22: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

21

a member of the Dar Group Companies

Through task orders on its $25M on-call contract with the San Diego Association of Governments (SANDAG), T.Y. Lin International (TYLI) is providing Project Management Consultant (PMC) services and design reviews for the Mid-Coast Corridor Transit Project, a SANDAG TransNet Early Action Project. TYLI is also serving as Procurement Advisor for the CM/GC which includes preparation of the procurement documents.

With this project, the San Diego Trolley system service would be extended approximately 11 miles, adding eight stations (with an option for a ninth station). The project includes over six miles of on-grade alignment and four miles of elevated guideway with significant structures (walls, bridges and a cut and over tunnel). Several new traction power substations (TPSS’s) will be needed along the new double track alignment as well as systems and TPSS upgrades or replacements along 3.5 miles of existing double track which is also part of this project. The alignment crosses over Interstate 8, Interstate 5 (twice), under State Route 52, as well as crossing several local streets, the San Diego River, Tecolote Creek, and Rose Creek.

For much of its length, the new LRT alignment (on exclusive new double track) would share the busy San Diego Northern Railway (SDNR) railroad corridor right-of-way (ROW) owned by MTS which is also occupied by the COASTER commuter rail, Amtrak Intercity Rail, and Burlington Northern Santa Fe (BNSF) freight rail.

Challenges include significant utilities throughout the corridor; ROW sharing amongst railroad, highway, and city streets; coordinating with major capital projects planned or underway along the corridor including the I-5 North Coast freeway improvements; and issues associated with sensitive areas, such as the San Diego River and Tecolote and Rose Creeks.

TYLI, along with its subconsultant, InfraConsult, LLC, is providing PMC support services to assist SANDAG during the Preliminary Engineering and Environmental Review/Clearance Phase of the Mid-Coast Corridor Transit Project serving as an extension of SANDAG staff. These services include, but are not limited to, project administration and control, review of advanced conceptual engineering submittals in support of the environmental document and cost estimates, review of environmental submittals, project management and technical assistance, coordination of activities, third party agreements, analyses of alternative delivery methods for the project, and assisting with New Start submittals and other submittals with the Federal Transit Authority (FTA) and FTA’s Program Management Oversight Consultant (PMOC).

MID-COAST CORRIDOR TRANSIT PROJECTS A N D I E G O , C A L I F O R N I A

PROJECT HIGHLIGHTS• Project Management• Procurement Advisor

• Cost Estimates• Extensive Coordination

Page 23: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

22

a member of the Dar Group Companies

The Contra Costa Transportation Authority (CCTA), in cooperation with Caltrans District 4, the City of Pittsburg, and the City of Antioch, is the lead agency conducting this project that proposes to widen 6 miles of State Route 4 (SR4) from four lanes to eight lanes beginning at Loveridge Road and terminating at SR160. The eight lanes will consist of one high occupancy vehicle (HOV) lane and three mixed flow lanes in each direction. Auxiliary lanes will also be added between interchanges. Multi-modal options such as the addition of mass transit in the median are included as well. TYLI is the Prime Consultant for Segment 3 which accounts for $150 million of this $340 million corridor improvement project. TYLI is responsible for project management, environmental coordination, community outreach, design development, agency coordination and interface, utility coordination and relocation, and ROW engineering and acquisition support. Significant coordination has taken place with the various agencies and the other consulting firms preparing the improvement plan packages for prior segments. Segment 3 is funded by the Contra Costa County half-cent transportation sales tax (Measure J) funds, Bridge Toll funds, and BART (RM2) funds. Segment 3 is divided into two separate projects (3A and 3B) that consist of 3 miles of improvements from 0.3 mile west of the “A” Street Undercrossing to 1.8 miles east of the Hillcrest Avenue Overcrossing. Segment 3A includes mainline and interchange work from the western project limit to just west of Hillcrest Avenue. Local street and utility (sewer and water) improvements are also included. Construction is scheduled to commence in the summer of 2012 for an estimate of 660 working days. Segment 3B is currently in final design and begins just west of the Hillcrest Avenue Interchange and extends to the eastern project limit terminating at the SR4/SR160 Junction. Construction for Segment 3B is scheduled to commence in the winter of 2012 for an estimate of 675 working days.The project consists of developing the final PS&E. As part of the project, the design will provide for the widening of the overcrossing at Hillcrest Avenue and the replacement of SR4 undercrossings at “A” Street and Cavallo Road, and the Roosevelt Lane pedestrian undercrossing. The underpasses for eBART will also be designed at “A” Street and Cavallo Road. Twenty-two retaining walls and 15 sound walls are being designed for this project. The mainline vertical alignment will generally follow the existing profile, except near the eBART station area where the profile rises to a maximum of 9 feet. Stage construction challenges for the construction of these structures include:• Constructing the Hillcrest Avenue OC widenings by temporarily lowering SR4 by 15-inches to avoid nonstandard falsework vertical

clearance on SR4 during construction.• Constructing a median crossover and a portion of the eastbound “A” Street UC to allow westbound traffic to be shifted to newly

constructed eastbound lanes to permit westbound lanes and westbound “A” Street UC to be constructed without interruption.• Constructing a median crossover and a portion of the westbound Cavallo Road UC to allow eastbound traffic to be shifted to newly

constructed westbound lanes to permit eastbound lanes and eastbound “A” Street UC to be constructed without interruption• Using cut and cover method to construct the Roosevelt Lane PUC while maintaining four lanes of traffic on the mainline at all timesTYLI’s work also included planning and design for new traffic signals, signal modifications, temporary signals, emergency vehicle preemption, portable changeable message signs, traffic operation system (including traffic management stations, closed circuit television cameras, ramp metering, wireless magnetometer vehicle detection systems, extinguishable message sign, fiber-optic conduit, vehicle detection systems), street and safety lighting, and pedestrian undercrossing lighting. The signals at the two ramp intersections for the diamond interchange at the “A” Street Undercrossing were designed to Caltrans specifications to replace the two existing signals due to the widening of “A” Street and the ramps. Two new Model 2070 L NEMA Controllers replaced the single Model 170 E Controller. The design of temporary spanwire signals for six construction stages presented a challenging task. The temporary spanwire signals for Stage 1 had to be designed in a way that modifications for the later stages could be minimized.

SR 4 (EAST) WIDENING AND INTERCHANGE IMPROVEMENTS – SEGMENT 3, A STREET TO SR 160C O N T R A C O S T A C O U N T Y ( A N T I O C H ) , C A L I F O R N I A

PROJECT HIGHLIGHTS• Environmental Coordination• Extensive Agency Coordination &

Interface• Utility Coordination & Relocation

• Corridor Management • Maintain consistency across mutli-

agency requirements• Budget & Schedule Controls

Page 24: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

23

a member of the Dar Group Companies

The remaining locations came under the City of Antioch review process. North of the “A” Street UC, a new signal was designed for the “A” Street / Rossi Avenue intersection to replace the 2-way stop signs. Due to the widening and improvements on Lone Tree Way south of the “A” Street UC, signal modifications were designed for the East Tregallas Road and West Tregallas Road intersections. The impact at the East Tregallas Road intersection was significantly more than at the West Tregallas Road intersection and was reflected in the signal modifications that were required.

The ability to maintain user requirements while responding to unique project conditions or community needs The project needed to effectively blend Caltrans and the affected cities requirements and design standards since the project crosses three jurisdictional boundaries. TYLI was successful in preparing a PS&E package that incorporated both Caltrans and the affected cities standards to their satisfaction while maintaining the project schedule, scope, and budget.TYLI developed stage construction plans that maintained pedestrian safety ensuring that the construction of sidewalks on both sides of the street was not done simultaneously. Mainline stage construction was developed to ensure that two lanes of traffic remained opened at all times during construction to minimize traffic interruptions.

Working with public and regulatory agencies The project involved extensive coordination and interface with public agencies. TYLI worked closely with CCTA, Caltrans District 4, Caltrans Headquarters, Caltrans District 59, City of Antioch (COA), and the Delta Diablo Sanitary District (DDSD) to deliver various components of the project. TYLI coordinated with Caltrans Districts 4 and 59 to obtain project approvals (i.e., Project Report, Environmental Clearance, Geometric Approval, Design Exceptions, Life Cycle Cost Analysis, Right- of-Way Certification). Additionally, coordination with Caltrans Headquarters successfully resulted in the project Ready To List (RTL) on February 27. TYLI coordinated with COA and DDSD to obtain design approval of various water and sewer facilities affected by the proposed project.

Success in keeping to budget and controlling costs, and success in meeting time schedule and scope • TYLI successfully controlled the budget and cost and met schedule and scope requirements through an accelerated design schedule,

value engineering strategies, and risk identification and management. • TYLI accelerated CCTA’s design schedule to meet anticipated funding through the CMIA Proposition 1B bond sales and expedited

design milestones through Caltrans District 4 and the local agencies. • TYLI staff used value engineering strategies to significantly reduce construction cost estimates at each design milestone; i.e., 35%,

65%. These “cost containment” efforts and TYLI’s experience in containing utility relocation costs underscore our capabilities in developing realistic project cost estimates and identifying cost-savings measures.

• TYLI staff provided strategic decision-making assistance to the CCTA for risk identification and management for all phases of the Caltrans project development process allowing us to meet all schedule and process milestones.

• TYLI identified project design challenges along with solutions that were beyond the original scope and budget in order to manage the control of “scope creep,” cost overruns, and schedule delays.

Approach to project management TYLI’s approach to project management on the SR4 project included leading the project development team to ensure timely resolution of issues. Specific project management components were continuous and early engagement of all project stakeholders ensuring consensus; reaching agreement on decisions in order to maintain the project schedule; project controls such as quality assurance and quality control (QA/QC); project invoicing; monthly project summary reports and schedule updates; and development and implementation of a QA/QC Plan, Risk Management Plan and Communication Plan. TYLI’s approach emphasized proactive client communication, team management for resource allocation and task progress, and coordination with involved agencies and other subconsultants.Approach to QA/QC TYLI prepared and is implementing detailed QA/QC plans specific to each of the two segments. TYLI’s QA/QC plans for the SR 4 widening project includes established independent design checks at 35%, 65%, 100% and Final PS&E milestones. TYLI has also conducted internal constructability reviews, with additional staff specifically assigned to this task, as well as coordinated constructability reviews with Caltrans, CCTA, and the adjacent two segments on SR 4 ensuring uniformity among all design teams. The TYLI Project Manager and QA Manager were responsible for assuring that quality control measures and quality assurance measures were

SR 4 (EAST) WIDENING AND INTERCHANGE IMPROVEMENTS – SEGMENT 3, A STREET TO SR 160 CONTINUED....C O N T R A C O S T A C O U N T Y ( A N T I O C H ) , C A L I F O R N I A

Page 25: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

24

a member of the Dar Group Companies

PLANNING & PROCUREMENT AND CONSTRUCTION MANAGEMENT (PCM) FOR TAICHUNG BUS RAPID TRANSIT (BRT) SYSTEMT A I C H U N G , T A I W A N

Taichung is the third largest city in Taiwan with a population of 2.6 million. The Taichung Metro (Taichung Mass Rail Transit System) is a rapid transit system featuring a combined of 16.7 km (10.4 miles) of elevated metro rail transit (MRT), 21 km (13 miles) of conventional rail, and 316 km (196.4 miles) of bus rapid transit system (BRT). The Blue Line has been designated as a prototype BRT corridor for the City. The Blue Line includes 17.2 km (10.7 miles) of mainline providing services between the Taichung Train station and Providence University at an estimated construction cost of $83 million. It also includes 28 km (17.4 miles) of rapid service extension at an estimated construction cost of $78 million. The Blue Line will include the following features:

• Partial or fully dedicated lanes;

• Separated and protected bus stations;

• Off-board fare collection systems;

• Real-time next bus information signs;

• Low floors and multiple-door buses with level boarding;

• Video security surveillance system; and

• Transit signal priority at intersections.

T.Y. Lin International (TYLI) serves as the Planning and PCM consultant for the Blue Line project (both the mainline and extensions) during the design, tendering, construction, and performance phases of the project. Additionally, TYLI is conducting a feasibility evaluation and finalization of the remaining 270 km (168 mile) BRT network plan including 29 km (18 miles) of elevated structures carrying six additional service lines. The total construction cost for the six planned service lines has been estimated at $911 million. As funding becomes available, the BRT network will be replaced with a metro rail system.

PROJECT HIGHLIGHTS• Planning & Procurement Management• Construction Management

Page 26: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S :

C O N S T R U C T I O N M A N A G E M E N T

Page 27: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

26

a member of the Dar Group Companies

ILLINOIS HIGH SPEED RAIL ENGINEERINGS P R I N G F I E L D , I L L I N O I S

T.Y. Lin International (TYLI) was selected by the Union Pacific Railroad (UPRR) to provide field verification services for the improvement of track between Godfrey and Lincoln, Illinois to accommodate high speed rail service. This project is administered through the Illinois Department of Transportation (IDOT) High Speed Rail Program. The Class of Track was improved from its current condition to a FRA Class 6 standard (110 mph Freight & Passenger). To accomplish this, the Union Pacific utilized its Track Renewal Group working with a Track Renewal Train (TRT) to reconstruct 240 miles of track on its Springfield & Joliet Subdivisions from MP 281.00 (St. Louis, IL) to MP 36.70 (Joliet, IL). Daily production included over 18,000 feet of rail and 4600 ties installed. The track renewal operation involved a total length of nearly 10 miles, including the TRT, and follow–on Union Pacific production equipment. Since the fall of 2010, TYLI’s contract has been budgeted annually and each annual phase of work has been completed under the budget allocated for the phase.

TYLI, as the Oversight Contractor, provides verification and documentation of all project activities, including all materials placed and labor utilized for the benefit of the project on a daily basis, project schedule, budget status, project expense verification, and review of invoice accuracy. The goal of the assignment was to ensure that all work progressed in compliance with the requirements of all State and Federal funding agencies. The Illinois High Speed Rail project was the first of the American Recovery and Reinvestment Act rail corridors to initiate actual construction. TYLI served as an extension of railroad staff and assisted UPRR with project management activities to deal with many implementation challenges. These included:

• Monitoring construction work activities, schedule compliance and real time cost estimating for UPRR forces and over 15 contractors /vendors

• Developing work progress and funding compliance reports for ever-evolving Federal reporting requirements

• Developing project quality management plan, quality assurance procedures and quality document record keeping

• Developing various work processes to identify necessary activities for compliance.

• Providing QA Testing by TY Lin subcontracted Independent Testing Labs of Contractor installed work on various Tier Contracts

• Conducting compliance audits in accordance with the IL HSR UPRR Quality Management Plan of UPRR Departments and General Contractors awarded the Tier work

• Providing project oversight / review of the UPRR contracted Construction Management engineering firms documentation uploaded to the Quickr database

• Maintaining quality document files on the UPRR Quickr database and hard copies of Quality Document in binders at the UPRR field office

• Participation in the potential Contractor Pre-Qualification evaluations

• Providing compliance review of individual Contractor invoices submitted in the UPRR Contract Audit System and the UPRR prepared monthly Pay Applications to IDOT for reimbursement

PROJECT HIGHLIGHTS• Program

Management• Oversight

Contractor

• Schedule Compliance

Page 28: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

27

a member of the Dar Group Companies

The Illinois State Toll Highway Authority selected T.Y. Lin International (TYLI) as part of a Joint Venture with V3 Companies of Illinois to perform the Overall Corridor Construction Management for the New Elgin-O’Hare Western Access Toll Highway, a ten mile corridor along the Elgin O’Hare Expressway and a six mile corridor for the new O’Hare Western Access. In addition to the corridor management role, TYLI and V3 are providing construction inspection services for the new interchange with I-290, which includes construction of two tri-level flyover ramps. The construction work is expected to include pavement and bridge construction, new frontage roads, storm sewer installation, barrier wall construction, toll collection facilities, striping and landscaping. The project duration of Spring 2013 to Spring 2018 will involve a demanding schedule with multiple concurrent activities.

OVERALL CORRIDOR CONSTRUCTION MANAGEMENT, TOLLWAY ELGIN O’HARE WESTERN ACCESS (EOWA) AND 290/53 RAMPSD U P A G E & C O O K C O U N T I E S , I L L I N O I S

PROJECT HIGHLIGHTS• Extensive knowledge of Tollway practices and requirements• Overall Corridor Construction Management for 16-miles• Concurrent Activities to Schedule/Manage

Page 29: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

28

a member of the Dar Group Companies

TYLI was selected to supervise the 2015-16 Sewer Lining Program for the City of Chicago’s Department of Water Management. The Program consists of the Sewer Main Lining Program and the Sewer Structure Rehabilitation Program. The Sewer Main Lining (SML) Program consists of lining approximately 50-60 miles of sewer mains and catch basin outlets per year and also lining 2,000-3,000 sewer structures per year. Some point repairs of the sewer mains before lining are also done under this program.

The Sewer Structure Rehabilitation (SSR) Program consists of lining 11,000-12,000 sewer structures (manholes, catch basins, and inlets) per year. As part of the program all sewer structures are cleaned and repairs or replacements are performed under this program prior to lining.

The full-time TYLI Program Manager will supervise a team of three full-time Resident Engineers and three full-time documentation engineers. This team will supervise 10-15 inspectors.

CHICAGO DEPARTMENT OF WATER MANAGEMENT TASK ORDER #90: SEWER LINING PROGRAM MANAGERC H I C A G O , I L L I N O I S

PROJECT HIGHLIGHTS• Management of large task order

including in-house team

Page 30: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

29

a member of the Dar Group Companies

TYLI’s Oregon operations Scheduling Group was selected to serve as a consultant to the Oregon Department of Transportation (ODOT) for the OR 43: Willamette River Bridge project. This complex bridge rehabilitation was experiencing numerous changes resulting from unforeseen field conditions. With eight months remaining before the opening to traffic date of October 15, 2012, T.Y. Lin International (TYLI) was added to the project team as scheduling specialists.

TYLI expanded upon Wildish Standard Paving Co.’s (WSTP) detailed construction schedule to include upcoming changes to the scope of work and provide continuous assessment of progress. To complete these tasks, TYLI converted the project schedule from MS Project to Primavera P6 in order to utilize the software’s advanced capabilities. Further, TYLI and ODOT set up protocols to capture tasks’ start/finish dates, percent completes and other relevant data in order to provide weekly schedule status updates.

When the scheduling team came on board the CPM had not been adequately maintained an over 30 Change Orders had not been accounted for in routine updates. TYLI performed a forensic CPM Schedule evaluation, incorporated Change Orders, and provided recommendations to the client and their construction contractor to meet established contract completion dates. TYLI worked closely with ODOT, the engineer of record, and the contractor to develop “what-if” schedule scenarios and recommended action plans to keep the project on schedule.

The project schedule began to show significant delays of up to 6 months with respect to a critical opening date. TYLI’s schedule team worked with the construction contractor and ODOT to evaluate the current status of the project and identify key activities that, once completed, would get the project on track to meet the critical opening date. Our scheduling team’s effort, along with the construction contractor dedication to the successful delivery of the project, and ODOT’s cooperation, resulted in opening the project six days ahead of schedule. TYLI facilitated a collaborative effort with ODOT and WSTP to augment the existing project schedule in identifying the critical remaining activities impacting the bridge opening. The team approach was crucial as it relied heavily on WSTP’s expertise in planning and construction techniques. WSTP’s involvement allowed ODOT to provide critical feedback, thereby allowing TYLI to develop frequent schedule modifications. The collaborative effort allowed the combined management team to uncover enhanced timeframes, logic ties, and establish resource loading needed to meet the milestones. TYLI utilized live work sessions with Primavera P6 to make changes on the fly and review the results in real-time.

“The project is complex both in the nature of the work and in the inter-relationships of the parties needed to accomplish it. TYLI has provided skilled and experienced scheduling personnel…have been cooperative in working with all of the parties involved…has made a significant contribution to what is going to be a successful project.” - Wayne Statler, PE, PMP, ODOT, OR 43: Willamette River Bridge (Oregon City) PM

OR 43: WILLAMETTE RIVER BRIDGE CONSTRUCTION SCHEDULING O R E G O N C I T Y , O R E G O N

PROJECT HIGHLIGHTS• Complex Schedule Management

Page 31: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

30

a member of the Dar Group Companies

T.Y. Lin International was retained by the Delaware Department of Transportation (DelDOT) to provide Technical Review Services for the procurement, design and construction of a replacement bridge to cross the Indian River Inlet.

The current Indian River Inlet Bridge on SR 1 provides a critical link on the Eastern seaboard between Bethany Beach and Dewey Beach, Sussex County, Delaware. Due to severe scour experienced in the area, the bridge was scheduled for replacement with a new structure that will have an overall bridge length of 2,600 feet and a main span of 950 feet. The segmental, cable-stayed main span will allow the bridge to cross the inlet without any piers in the water and provides for the future potential widening of the inlet. The approaches consist of precast bulb-tee girders. The new bridge will have two 12-foot lanes for travel in each direction, a 10-foot wide outside shoulder, and a 4-foot wide inside shoulder in each direction. The minimum vertical clearance over the navigational channel will be 45 feet.

As Technical Review Consultant, T.Y. Lin International was the owner representative for this Design-Build Project. The scope of services during the Procurement Phase included reviewing the RFP, the contract documents, the performance specifications and the special provisions. T.Y. Lin International also evaluated the technical proposals prepared by the shortlisted teams and assisted DelDOT’s Selection Panel scoring the technical proposals.

During the Design Phase T.Y. Lin International provided general technical support to DelDOT and reviewed design submittals, issue papers and value engineering proposals. During the Construction Phase, T.Y. Lin International reviewed construction submittals, RFI’s and non-conformance reports. TYLI on-site engineers also provided support to DelDOT for construction engineering and inspection.

INDIAN RIVER INLET BRIDGES U S S E X C O U N T Y , D E L A W A R E

PROJECT HIGHLIGHTS• TYLI provided a full range of services, including owner’s

representative, program management, planning, preliminary engineering, construction, and operations oversight for this $150 million design-build project.

• The largest single contract DelDOT has ever awarded in its 90+ year history.

Page 32: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

31

a member of the Dar Group Companies

The firm is responsible for the construction management (including schedule and cost control analysis) of various sections/areas requiring storm water improvements as part of SFWMD’s ACCELER8 Program. After review and approval by the construction management team, each individual construction schedule then becomes a part of a master schedule that is coordinated with other on-going projects and future projects. This is a P3e/c schedule created, revised, and monitored by the district’s internal scheduling team. This schedule is cost loaded with design, land acquisition, permitting, and construction budgets. The schedule is updated monthly, reviewed, and reported on by our staff to ensure the overall program timeline is still on course.

The ACCELER8 program is an Everglades Restoration effort committed by a federal/state/local partnership to expedite the progress of eight restoration projects that will revitalize the Florida ecosystem. The projects consist of labor, equipment & materials to construct additional storm water treatment flow way for various areas identified by the program. The work will include the construction of canals, levees, flow control structures, the restoration of 55,000 acres of failed development, degrading of existing roads and beams, and filling of existing ditches and canals.

The firm is also responsible for a number of scheduling related activities. To date, there have been no cost overruns, no claims and no delays to the schedule. Our teams schedule related tasks run parallel with the tasks of the Construction Management (CM)/Construction Inspection Service (CIS) team. The procedure occurs as follows: After receiving the Notice to Proceed, the Contractor has ten (10) working days to submit the original base line schedule; it must be “cost loaded”. This schedule is presented in P3e or in Primavera Contractor. At this time, our staff has another ten (10) calendar days to review and compare our comments with the CM/CIS. This review is made by running Integrity Check to detect activities that do not have relationships and to follow the logic and duration of the project. After the review is completed the CM/CIS team will present the Owner with their recommendations for acceptance. Most of our projects have several substantial completion dates that must be met. This first review process must be completed before the first pay request is submitted by the Contractor since the Schedule is part of the submittal. After the Base line is accepted by the Owner for duration and logic, the Contractor will submit with each pay application an updated version of the schedule. This review is conducted by running the updated schedule through CLAIM DIGGER; this tool of P3e or Primavera Contractor will allow our staff to compare all changes made to the updated schedule to the latest accepted base line schedule on file. Next, our staff will run the INTEGRITY CHECK; this tool detects the relationship of the activities of the program and flags any that have been changed as a result of readjustment of the data input made every month.

Finally, our staff filters the schedule to print and review it to show Critical Path on each Substantial Completion mile stone and final project.

ACCELER8 PROGRAM – EVERGLADES RESTORATIONH E N D R Y C O U N T Y , F L O R I D A

Page 33: TYLI Program, Corridor and Construction Management Qualifications_2015

P R O J E C T P R O F I L E S

32

a member of the Dar Group Companies

Opened in 2007 the South Terminal at Miami International Airport (MIA) does more than just help transport one fourth of MIA’s passengers from one destination to another. The 1.7-million-square-foot facility amazes the senses of passengers with its architectural design as it meets their travel needs. South Terminal encompasses a new Concourse J with 15 gates and a renovated Concourse H with 13 gates, serving 20 domestic and international carriers.

T.Y. Lin International provided mechanical (plumbing and fire protection systems) and civil (airside/landside) engineering design and construction phase services for the South Terminal Expansion Program at MIA. The new multi-level $360M terminal is equivalent to a new midsize airport and represents the first major terminal expansion at MIA since the airport was built in the 1950s. The firm was also the engineer-of-record for the landside roadways adjacent to the South Terminal facility.

The facility included the design curbside roadways, the new South Bus Station; an 18-position bus station facility to serve the buses from the Port of Miami. The firm analyzed the civil design criteria and utilized computer-generated bus movements to ensure adequate pavement area was available for bus maneuvering. The design included the preparation of an early package for an interim bus station which was utilized during the terminal building construction. The design also included removal and rerouting of existing utilities beneath the proposed terminal. The civil work involved planning and design of landside roadways including a traffic calming circle for vehicular traffic exiting the airport from the terminal area and adjacent parking structure.

The airside civil scope of services of the work involved new aircraft parking aprons, full utility design to service the terminal building and a unique grading condition for a depressed lower level of in the baggage make-up area. The utility work involved demolition of existing service lines and creation of two replacement drainage lines that had to continue beneath the building between massive foundations. All site work was coordinated with three adjacent projects (terminal, airside, landside roadways) that were part of the overall South Terminal Program at MIA.

MIA NEW SOUTH TERMINAL EXPANSIONM I A M I , F L O R I D A

PROJECT HIGHLIGHTS• New Multi-level Airport Terminal• 1,700,000 sf.• Mechanical Engineering (Fire Protection and Plumbing)• Civil Engineering (Airside/Landside)• Coordination with On-going Projects• Coordination with Airlines

Page 34: TYLI Program, Corridor and Construction Management Qualifications_2015

Founded in the United States in San Francisco, California, T.Y. Lin International (www.tylin.com) is a full-service multi-disciplined infrastructure planning and engineering firm that has provided innovative, cost-effective, and constructible designs for more than 55 years. As a part of the DAR Group, our global partnerships extend to over 12,000 professionals worldwide, providing leadership and support on projects of varying size and complexity. Each client benefits from the organization’s global expertise while receiving personal attention to local needs. Trade publication Engineering News-Record has included T.Y. Lin International in its annual lists of top bridge design, transportation design, and design firms in both domestic and international markets. T.Y. Lin International, in association with the DAR Group partners, servies the sectors listed below.

MARKET SECTORS

Aviation Bridges Facilities Ports and Marine

For more information about T.Y. Lin International projects or to contact us, please visit our website at www.tylin.com or email us at [email protected].

Power and Energy Rail & Transit Surface Transportation

Water and Wastewater