two construction supervision & quality control

Upload: bolinag

Post on 04-Apr-2018

233 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/30/2019 Two Construction Supervision & Quality Control

    1/52

    1

    Ministry of Works and Urban Development

    Training Manual for Construction

    Supervision and Quality Control

  • 7/30/2019 Two Construction Supervision & Quality Control

    2/52

    2

    I. Construction Project

    1. Stages Involved in Construction Project

    1.1 Conception: - During this period of the project thefollowing are formulated and prepared.

    The necessity and objective of the project

    Feasibility.

    The function it will serve

    The resources (land, finance, input) required forthe implementation

  • 7/30/2019 Two Construction Supervision & Quality Control

    3/52

    3

    1.2 Design: - At this stage of the project AnEngineer/architect is consulted. TheEngineer or the consultant shallinvestigate the land and prepare DesignDocument. The following are consideredat design stage.

    Preliminary Design

    Ownership

    Master Plan

    Programme

    Soil Test

    Topographic Survey

  • 7/30/2019 Two Construction Supervision & Quality Control

    4/52

    4

    Building Permit

    (Final Design) Complete Working Drawings,Architectural, Structural, Sanitary, Electrical,Specification and Bill of quantities, necessarydetail drawings.

    Preparation of contract documents.

    1.2. Design Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    5/52

    5

    1.3 Realization: -At this stage. Contract issigned between Client and Contractor. Theactual execution of the project

    (Construction) is started.

  • 7/30/2019 Two Construction Supervision & Quality Control

    6/52

    6

    2. Partners in a Construction Project: -

    A construction project is realized under thepartnership of three parties;

    The Client: (Owner Regional Governments shallprovide the money for the realization of the project,Evaluate and monitor the project.

    The Consultant or Engineer: HDPO (prepareDrawings and supervise the project.)

    The Contractor: Contractors and subcontractors. Execute the actual construction as perDrawings and specifications provide for the

    engineer.

  • 7/30/2019 Two Construction Supervision & Quality Control

    7/52

    7

    These being partners in ordinary constructionproject, HDP include more partners like MSE inproduction and Construction works. In

    construction works MSEs are considered asSub contractors.

    2. Partners in a construction project Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    8/52

    8

    3. Planning: - planning is thinking ahead ofthe operation or activities to be performed.

    It is a careful consideration of allpossibilities in order to complete the projectwith the estimated cost, within the

    estimated period and with an acceptablequality.

  • 7/30/2019 Two Construction Supervision & Quality Control

    9/52

    9

    3.1 Objectives of Planning

    (Planning in general is Managing Resources) The time for delivering of material

    The type, quantities and duration of equipmentneeded.

    Classification and number of labourers neededand the time when they are needed.

    The amount of money required and when itsrequired

    The time allocation to accomplish everycomponent of the work.

    Quality Assurance.

  • 7/30/2019 Two Construction Supervision & Quality Control

    10/52

    10

    More than 100 commercial project

    management software packages are

    available.

    Most of them are considered as

    administrative overhead.

    They yielded only marginal Benefit.

    Have largely been neglected by

    managers.

  • 7/30/2019 Two Construction Supervision & Quality Control

    11/52

    11

    3.2 Methods of Planning:-

    Many techniques have been established in thepast 50 yrs.

    Gantt or bar chart

    Critical path method (CPM)

    Program Evaluation and Review Technique(PERT)

  • 7/30/2019 Two Construction Supervision & Quality Control

    12/52

    12

    Gantt Chart (Bar Chart) Methods.

    Activities are listed

    The time required for completion is

    estimated.

    Beginning of the project is set.

    Parallel and sequential activities are

    identified.

    The chart is prepared.

  • 7/30/2019 Two Construction Supervision & Quality Control

    13/52

    13

    3.3 Critical Path Method (CPM) AndProgram Evaluation & ReviewTechnique (PERT)

    The method has been developed since 1950s

    Rarely used in real projects.

    When used, are used for month end project

    rather than for proactive decision-making.

    These are recent developments in planning and

    scheduling upon chart methods. In both methods

    entire planning and scheduling is representedgraphically in the form of a network of the various

    operations involved in to.

  • 7/30/2019 Two Construction Supervision & Quality Control

    14/52

    14

    In the CPM scheduling the project is carried

    out in using the following steps:

    a. The project should be divided into variousactivities.

    b. The time required for each activity should beestimated.

    c. The sequence depending upon the importanceof the activity should be determined.

    d. By inter-connecting properly the activities andevents to the network should be drawn.

    3.3 CPM & PERT Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    15/52

    15

    3.3 CPM & PERT Continued

    e. The number should now be assigned to eachevent, being sure that the number at the head ofthe arrow should be greater than the number at

    the tail of the arrow.f. The chart should be then prepared consisting of

    horizontal and vertical columns on which activitywith an appropriate designation be written.

    g. The activity laying on the critical path should bedetermined.

  • 7/30/2019 Two Construction Supervision & Quality Control

    16/52

    16

    3.4 Properties of CPM Network

    1. The CPM essentially is a chart consisting of a'Network' of arrows and nodes.

    2. Each arrow represents a step or activity or task fora particular work.

    3. The tail of the arrow indicates the start of theactivity while the head of the arrow represents the

    completion of the activity.4. It is designated by two numbers, the number at the

    head being always greater than the number at thetail.

    5. The length and shape of line and arrow do not giveany significant information of the activity. Each'Node' is given a certain number, and representsthe completion of the activity indicated by theleading to it.

  • 7/30/2019 Two Construction Supervision & Quality Control

    17/52

    17

    How to use the CPM?

    Task ID Duration Dependency

    A 7B 3C 6 AD 3 B

    E 3 D,FF 2 BG 3 CH 2 E,G

  • 7/30/2019 Two Construction Supervision & Quality Control

    18/52

    18

    3

  • 7/30/2019 Two Construction Supervision & Quality Control

    19/52

    19

    3.5 Importance of critical path network

    1. It helps the top management to concentrate their

    attention on critical activities and their completion intime.

    2. If any activity on the critical path is delayed it willdelay the project completion.

    3. Knowledge of critical and non critical activities helpsthe management divert the resources from non-critical activates which are in advance to criticalactivities for achieving economy.

  • 7/30/2019 Two Construction Supervision & Quality Control

    20/52

    20

    Advanced Project and ResourceScheduling

    Important Points in Planning

    The Cascade Effect

    Project work is Characterized by highuncertainty.

    Non-linear dependency.

    Delay multiply. Gains not adding up.

  • 7/30/2019 Two Construction Supervision & Quality Control

    21/52

    21

    1. Integration Dependency

    A

    B

    E

    C

    D

  • 7/30/2019 Two Construction Supervision & Quality Control

    22/52

    22

    Advantage When task finishes early, subsequent tasks

    can be begun immediately.

    Disadvantages Delays multiply very fast.

    With delays engineers are forced to

    multitask.

    As multi tasking goes up, production of

    goes down.

    Aggressive Schedule

  • 7/30/2019 Two Construction Supervision & Quality Control

    23/52

    23

    3. Relaxed Scheduling

    Advantage

    Delays do not multiply

    Disadvantage The work expands to fill the time

    (Parkinson's law)

    Gains do not add up, but delays stillpropagate.

  • 7/30/2019 Two Construction Supervision & Quality Control

    24/52

    24

    Advanced Project and ResourceScheduling

    Prevents delay from multiplying

    Gains add up

    Provides clear priorities to contain

    multitasking

    Creates pool system so that work

    doesnt expand unnecessarily.

  • 7/30/2019 Two Construction Supervision & Quality Control

    25/52

    25

    The Method is based on Dr. Goldratts theory

    of constraints and has three components.

    1. Critical Chain Buffering. Critical chain is the resource-leveled critical

    Data in a project. Since critical chain is thebest possible cycle time for a project, itshall be scheduled aggressively whileprotecting is from delays on Non-criticalchain.

    . Buffers are blocks of unscheduled timeplaced at the end of a series of tasks to aabsorber cumulative delays on thosetasks.

  • 7/30/2019 Two Construction Supervision & Quality Control

    26/52

    26

    Feeding Buffers- Placed at the end of Non-

    critical chains to preventdelays on Non-critical

    chains from impeding

    progress on critical chain.

    Project Buffer placed at the end of critical

    chain to absorb delays oncritical chain.

  • 7/30/2019 Two Construction Supervision & Quality Control

    27/52

    27

    1. Constraints Based Pipelining

    Constraints are the most heavily loaded &resourced.

    Since constraints restrict the number ofprojects that can be undertaken

    simultaneously, the objective is to maximizetheir utilization.

    Pipelining is the process of schedulingmultiple projects simultaneously.

    Constraints based pipe ling schedules theconstraints first, and then checks forcapacity of non-constraints.

  • 7/30/2019 Two Construction Supervision & Quality Control

    28/52

    28

    3. Buffer Management

    Monitoring the process of monitoringconsumption of buffer during execution

    Buffer Burn Rate (ratio of buffer

    consumed to work completed in achain)

    Priority is given to chains with the

    highest rate of Butter consumption. When BGR exceeds a specified level,

    it triggers a warning.

  • 7/30/2019 Two Construction Supervision & Quality Control

    29/52

    29

    4. Planning, General Out line, the Context

    of NIHDP

    In the context of NIHDP planning is working out the

    time allocation for the different components of theprogram. E.g. Land preparation, Logistics,Construction, MSE development, Financing.

    At the Planning stage different components of the

    work should be properly planned with the directinvolvement of the concerned sections.

    There should be proper coordination among differentdepartments at planning stage, for the planning ofone department directly affects the other.

    The General guide and the central focal point for theplanning of all other departments is the plan of theconstruction & supervision department.

  • 7/30/2019 Two Construction Supervision & Quality Control

    30/52

    30

    The construction supervision department works outthe time frame for the execution and completion of

    the construction based on (MPMWP) the desire of theclient which is the regional government.

    Based on the general time frame of the constructionschedule prepared by the Construction & supervision

    department head which includes all the projects, theremaining departments plan the execution andcompletion time of the tasks they undertake.

    In their planning formats methods and means

    through which to achieve the planned goals should bestated.

    Possible difficulties and obstacles should be sortedout with the means to address them.

    4. Planning General outline Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    31/52

    31

    4.1 Planning Construction and Supervision,

    General

    In planning Construction & supervision thefollowing are determined

    Type and quantity of Materials required for the

    construction. Quantity and duration of operation.

    Labour required for the work; (Skilled andUnskilled)

    Money required at different stages of the project.

    Total time to complete the project.

    4 1 Pl i t ti & i i G l C ti d

  • 7/30/2019 Two Construction Supervision & Quality Control

    32/52

    32

    Therefore the following schedules are prepared

    in advance based on the requirements onconstruction site.

    Construction schedule. Material schedule

    Labour schedule

    Equipment schedule (where necessary)

    Financial schedule.

    4.1 Planning construction & supervision, General Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    33/52

    33

    4.2 Construction schedule: - This is aRoaster for the execution of different

    operations.

    Before preparing the schedule the following are

    determined in advance: Break down of Various operations,

    Amount of work

    Rate of completing the works.

    Sequence of operation and their interrelationships

    4 2 C t ti S h d l C ti d

  • 7/30/2019 Two Construction Supervision & Quality Control

    34/52

    34

    After the break down of works the works areput in a compact form which could becommunicated with ease and accuracy. This

    form is what we call construction schedule. Allthe other schedules are prepared in the samemanner.

    4.2 Construction Schedule Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    35/52

    35

    4.3 Planning Construction and Supervisionthe Context of NIHDP

    Multi Projects Master work program

    is an overall annual plan

    identifies projects project start and finishing dates

    estimated costs

    4 3 Pl i C t ti t t f NIHDP C ti d

  • 7/30/2019 Two Construction Supervision & Quality Control

    36/52

    36

    This is based up on the regional

    governments

    Five year plan

    Approved annual plan and budget Estimated completion period and cost per square

    meter

    Status of on going projects

    Available capacity (contractors, MSE, Productionfirms)

    4.3 Planning Constructioncontext of NIHDP Continued

    4 3 Planning Constr ction conte t of NIHDP Contin ed

  • 7/30/2019 Two Construction Supervision & Quality Control

    37/52

    37

    MPMWP is prepared once in a year.Contractors Master work Program(Contractors Schedule) should consistof:-

    Activity bar chart and showing date of start andfinish and sequence of activities.

    Amount of work to be executed in each month Cash flow

    4.3 Planning Constructioncontext of NIHDP Continued

    4 3 Planning Construction context of NIHDP Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    38/52

    38

    Resource mobilization delivery schedule

    Manpower

    Equipment

    Material

    Quantity of work assigned crew and rate of

    output Work methodology

    4.3 Planning Constructioncontext of NIHDP Continued

    4 3 Planning Construction context of NIHDP Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    39/52

    39

    Project Master Work Program

    This is based on MPMWP + CMWP

    It includes the work plans of all contractors on a

    project site

    This is developed by the project engineer

    This should not take more than a week periodafter receiving contractors Master work Program(CMWP)

    4.3 Planning Constructioncontext of NIHDP Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    40/52

    40

    4.4 Project Work Schedule

    This is developed based on the contractorswork schedule

    It should be prepared once in a week at sitelevel

    Every quarter at zone or city Project officeslevel

  • 7/30/2019 Two Construction Supervision & Quality Control

    41/52

    41

    4.5 Master Project Schedule

    In case of More than one project Engineer theConstruction & supervision Department shouldprepare or compile one final Master Project

    schedule which includes the Project schedulesoff the entire project Engineers.

    4 5 Master Project Schedule Continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    42/52

    42

    4.5 Master Project Schedule Continued

    After this each schedule is provided for theconcerned department to base its plan up on it.

  • 7/30/2019 Two Construction Supervision & Quality Control

    43/52

    43

    4.6 Planning the Delivery of materials in thecontext of NIHDP

    This shows how and when to deliver thematerials requested by construction andsupervision department. Time of Tendering and

    Bulk purchase, Capacity of MSE and Amount ofmaterials like HCB, Precast beam to beproduced and delivered by each MSE is planedand communicated to the MSE's and othersuppliers. Generally on this plan the following islay out is expected.

    4.6 Planning the Delivery of materials in the context of NIHDPcontinued

  • 7/30/2019 Two Construction Supervision & Quality Control

    44/52

    44

    The time for delivering of materials, the time required forthe imported materials like steel Reinforcement Bar,Cement, Electrical and sanitary installation materials etc;

    The time required to produce materials By MSE.

    Those items imported form foreign suppliers are plannedat regional and Federal level, while the items producedlocally are planned at the Zonal and Regional level.

    The time required for the provision of materials in caseof locally produced materials include the time required tomobilize, organize and Deploy MSE, and equip them withthe necessary machinery, working space, and workingcapital.

    4.6 Planning the Delivery of materials in the context of NIHDPcontinued

    4.6 Planning the Delivery of materials in the context of NIHDPcontinued

  • 7/30/2019 Two Construction Supervision & Quality Control

    45/52

    45

    4.6 Planning the Delivery of materials in the context ofNIHDPcontinued

  • 7/30/2019 Two Construction Supervision & Quality Control

    46/52

    46

    5 Communications, the Context of NIHDPO

    Construction department should conveymaterial requests from every site to Logistics

    Logistics Department should give information

    to MSE department as material requirement atevery site.

    Logistic department should give information

    about material in store and at production site,materials ordered from suppliers and onshipment.

    5. Communications, the Context of NIHDPO continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    47/52

    47

    5. Communications, the Context of NIHDPOcontinued

    All departments should give information about

    their activities and problems encountered to theproject manager. One o the ways through whichthe responsible bodies at all level could beinformed about the progress of the project is

    Reporting. All Departments should at least writemonthly and quarterly report. In case ofconstruction& supervision Department thereporting procedure follows the upcoming

    pattern.

    Reports should be written at regular frequency;weekly, monthly, quarterly and annually.

    5. Communications, the Context of NIHDPO continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    48/52

    48

    5 Co u cat o s, t e Co te t o O

    Should provide timely, complete and accuratestatus information.

    Should warn of pending problem is in to take

    action. Should be easily understandable

    Report is submitted from site engineer toconstruction supervisor and supervision

    department head,

    A good report should have the followingcharacteristics

    5. Communications, the Context of NIHDPO continued

  • 7/30/2019 Two Construction Supervision & Quality Control

    49/52

    49

    ,

    The C&S Department head reports to projectmanagers city level

    Project manager at city level reports to the Mayoror City manager who ever Is In charge of heproject and project manager at regional level

    The manager at Regional level reports to thecabinet of the region (or person responsible forthe follow up of the project from the Cabinet.)

  • 7/30/2019 Two Construction Supervision & Quality Control

    50/52

    50

    6. Monitoring

    A continuous process of gathering, analyzing,interpreting of information of activities of theproject, in order to enable timely adjustment of

    the project when necessary.

    Its a basic part of implementation management.

  • 7/30/2019 Two Construction Supervision & Quality Control

    51/52

    51

    7. Evaluation

    Systematic and periodical analyzing of theactivities of the project.

    To make adjustment of the process whennecessary.

    This could be done in a quarterly or biannually orannually or at end of the project.

  • 7/30/2019 Two Construction Supervision & Quality Control

    52/52

    52