Twinning Project TR 08 IB EN 03. Industrial Emissions Directive 2010/75/EU. Integrated Permitting and Inspection in Turkey. Ece Tok – Resident Twinning Advisor Counterpart. Cesar Seoanez – Resident Twinning Advisor. Outline. IED 2010/75/EU & Integrated Permitting. Further info. - PowerPoint PPT PresentationTRANSCRIPT
Twinning Project TR 08 IB EN 03
Integrated Permitting and Inspection in Turkey
Cesar Seoanez – Resident Twinning Advisor
Industrial Emissions Directive 2010/75/EU
Ece Tok – Resident Twinning Advisor Counterpart
Outline
Next steps: input & cooperation
IED 2010/75/EU & Integrated Permitting
Twinning project - TR/2008/IB/EN/03
IED permit procedure
Twinning Project & activities
Further info
Draft By-Law
IED & Integrated Permitting
EIA: 97/11/EC
• Directive 96/61/EC 08/1/EC Industrial Emissions 10/75/EU
Industries: 01/80/EC, 99/13/EC, 00/76/EC…
EU Integrated approach to protect environment:
Turkey to become EU Member Closing benchmarks: alignment
EU Policy: for all Member States
Twinning project - TR/2008/IB/EN/03
IED & Integrated Permitting
New integrated permit procedure: Annex I
We focus on Chapters I & II of new Directive (“IPPC” Chapters)
IED 2010/75/EU : main features
Replaces & updates 7 Directives: IPPC + 6 “sector”:
Twinning project - TR/2008/IB/EN/03
LCP , VOC , Waste Co/Incineration , TiO2
Entegre Kirlilik Önleme ve Kontrol Direktifi (IPPC) - Endüstriyel Emisyonlar Direktifi (EED)
• Tüm alıcı ortamları birlikte değerlendirdiği ve çevreyi bir bütün olarak yüksek seviyede koruması,
• Hava, su, atık ve toprağa olan etkilerin en aza indirilmesi, • enerji verimliliği, • ham maddenin etkin kullanılması, • atık minimizasyonu• işletmelerden kaynaklanan emisyonların kaydı ve raporlanması
(E-PRTR/PRTR)• İzin sürecine halkın katılımı/ bilgiye ve yargıya erişimi • izin, denetim ve izleme koşullarını kapsayan
yatay bir mevzuattır.
Entegre Kirlilik Önleme Kontrol (EKÖK) &Endüstriyel Emisyonlar Direktifi (EED)
Entegre Kirlilik Önleme Kontrol (EKÖK) &Endüstriyel Emisyonlar Direktifi (EED)
Entegre Çevre İzin
MEİT
Demontaj
Al. Ort. St.
• Kapasite Oluşturulması Ocak 2003 Aralık 2004
• Uyumlaştırma,Uygulama,Stratejisi Hazırlanması
Ocak 2006 Şubat 2008
ENTEGRE KİRLİLİK ÖNLEME,KONTROL DİREKTİFİNİN İÇ MEVZUATA KAZANDIRILMASI ÇALIŞMALARI
Entegre/tek izin konusunda ortak bir anlayış benimsendi,
Direktifin amaç kapsam ve (BAT-BREFs) uygulamaları ile ilgili eğitim verebilecek 14 kişilik bir ekip oluşturuldu
Direktifin uyumlaştırılması ve uygulanması için politika ve strateji oluşturacak koordinatör / yetkili tek bir merkezi otoritenin olması benimsendi,
KAPASİTE OLUŞTURULMASI PROJESİ SONUÇLARI 2004Gelecekte sağlıklı, etkin bilgi akışı
sağlanarak, izinlerin taşra teşkilatınca verilmesine ilişkin kurumsal yaklaşım oluşturulması benimsendi,
Edinilen bilgiler ilgili tüm taraflarla paylaşıldı, bilgi birikimi oluşturuldu
IPPC direktifinin etkin uygulanabilmesi için bundan sonra izlenmesi gereken stratejinin ana hatları ortaya kondu.
TASLAK UYGULAMA STRATEJİSİNDE• IPPC tesisleri için çevre izinlerinin ÇOB içerisinde
entegre edilmesi, diğer otoriteler ile koordine edilerek tek bir izin olarak verilmesi;
• IPPC-olmayan tesisler için ise sadece ÇOB tarafından verilen çevre izinlerinin koordinasyon ile tek bir çevre izni haline getirilmesi ve bunun diğer otoritelerin izinleri ile koordinasyonu.
• Küçük kuruluşlar içinse genel bağlayıcı kurallar kapsamında değerlendirme yapılması önerilmektedir
UYUMLAŞTIRMA, UYGULAMA STRATEJİSİ HAZIRLANMASIPROJESİ SONUÇLARI 2008
IPPC TESİSLERİ
1-A TESİSLERİ
BAT zorunlu
IPPC DIŞI TESİSLER
1-B TESİSLERİ
BAT zorunlu
2-A TESİSLERİBAT zorunlu değil
2-BTESİSLERİ
İzne tabi olmayıp, Genel Bağlayıcı Kurallar uygulanır
TASLAK İZNE TABİ TESİSLER LİSTESİ VE GRUPLAR
Endüstriyel Kirlilik Önleme Kontrol (EKÖK) &Endüstriyel Emisyonlar Direktifi (EED)
Öngörülen Entegre Çevre İzninde • Alıcı ortamlar arası etkileşim, • Proseste yapılabilecek değişiklikler ile emisyonların oluşumunun önlenmesi/
sağlanamıyorsa kontrolü, • Mevcut en iyi tekniklerin uygulanması, • Enerji verimliliği,• Demontaj sonrası etkiler• Raporlama esasları değerlendirilecektir.
Entegre Çevre İzni ile;
• Tüm çevresel işlemler için tek bir izin, bu olmuyorsa izinlerin koordine edilmesi, Koordinasyon durumunda izin vermekle yetkili tek makam olması,
• Tesis kurulmadan önce izin verilmesi nedeniyle, ÇED süreciyle entegre izin sürecinin birleştirilerek bürokrasinin azaltılması,
• Mevcut en iyi tekniklerin kullanılmasının zorunlu hale getirilmesiyle çevrenin bir bütün olarak korunması,
• Halkın izin sürecine katılımı/bilgiye ve yargıya erişiminin• Pazarda rekabet gücünün artırılmasının sağlanması hedeflenmektedir.
12
MÜZAKERE SÜRECİ VE UYGULAMA TAKVİMİ
Uyumlaştırma 2012
Entegre izne geçiş 2015
Türkiye’de IPPC tam uygulama 2018
Further info
Twinning project - TR/2008/IB/EN/03
Turkish version of IED:
Small guide (info & links)
Website: http://ippc.cevreorman.gov.tr
email addresses in the brochure
In the website
http://www.cedgm.gov.tr Tüm Duyurular
Twinning Project
4 objectives:
4. Capacity building: supporting materials & training in 4 sectors
1. Public Administration capable of implementing integrated permitting & inspection
2. Alignment with EU acquis on this field: new by-law
3. Estimate of technical, institutional & financial resources needed
Partners: Turkey, Spain, Poland
2 years, 2011 & 2012, 1.425 million €
Açılış
İspanya& Polonya sistemlerinin kıyaslanması
+Güncellemek IPPC Eylem Planı
Yeni idari yapının tanımlanması
+Koordinasyon mekanziması
Yönetmeliğin 1. taslağı
+İdari prosedür
BAT değerlendirme opsiyonu , IPPC –
PRTR linkleri
Sanayi ve ÇOB için genel kılavuz
4 sektör için eğitimlerYönetmeliğin 2. Taslağı
4 sektör kılavuzu
Kaynakların belirlenmesi
+İlk izin verme
işlemi için strateji
Değerlendirme& diğer adımlar
+Proje’nin kapanışı
Proje ayıOCAK ARA
LIK2012
OCAK
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
Açılış
İspanya& Polonya sistemlerinin kıyaslanması
+Güncellemek IPPC Eylem Planı
Yeni idari yapının tanımlanması
+Koordinasyon mekanziması
Yönetmeliğin 1. taslağı
+İdari prosedür
BAT değerlendirme opsiyonu , IPPC –
PRTR linkleri
Sanayi ve ÇOB için genel kılavuz
4 sektör için eğitimlerYönetmeliğin 2. Taslağı
4 sektör kılavuzu
Kaynakların belirlenmesi
+İlk izin verme
işlemi için strateji
Değerlendirme& diğer adımlar
+Proje’nin kapanışı
Proje ayıOCAK ARA
LIK2012
OCAK
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
1. Entegre izin & denetimi uygulayabilecek kamu kurumu
Açılış
İspanya& Polonya sistemlerinin kıyaslanması
+Güncellemek IPPC Eylem Planı
Yeni idari yapının tanımlanması
+Koordinasyon mekanziması
Yönetmeliğin 1. taslağı
+İdari prosedür
BAT değerlendirme opsiyonu , IPPC –
PRTR linkleri
Sanayi ve ÇOB için genel kılavuz
4 sektör için eğitimlerYönetmeliğin 2. Taslağı
4 sektör kılavuzu
Kaynakların belirlenmesi
+İlk izin verme
işlemi için strateji
Değerlendirme& diğer adımlar
+Proje’nin kapanışı
Proje ayıOCAK ARA
LIK2012
OCAK
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
2. Bu alanda AB mevzuatı ile uyumlaştırma: yeni yönetmelik
Açılış
İspanya& Polonya sistemlerinin kıyaslanması
+Güncellemek IPPC Eylem Planı
Yeni idari yapının tanımlanması
+Koordinasyon mekanziması
Yönetmeliğin 1. taslağı
+İdari prosedür
BAT değerlendirme opsiyonu , IPPC –
PRTR linkleri
Sanayi ve ÇOB için genel kılavuz
4 sektör için eğitimlerYönetmeliğin 2. Taslağı
4 sektör kılavuzu
Kaynakların belirlenmesi
+İlk izin verme
işlemi için strateji
Değerlendirme& diğer adımlar
+Proje’nin kapanışı
Proje ayıOCAK ARA
LIK2012
OCAK
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
3. Gerekli olan teknik, kurumsal & finansal kaynakların belirlenmesi
Açılış
İspanya& Polonya sistemlerinin kıyaslanması
+Güncellemek IPPC Eylem Planı
Yeni idari yapının tanımlanması
+Koordinasyon mekanziması
Yönetmeliğin 1. taslağı
+İdari prosedür
BAT değerlendirme opsiyonu , IPPC –
PRTR linkleri
Sanayi ve ÇOB için genel kılavuz
4 sektör için eğitimlerYönetmeliğin 2. Taslağı
4 sektör kılavuzu
Kaynakların belirlenmesi
+İlk izin verme
işlemi için strateji
Değerlendirme& diğer adımlar
+Proje’nin kapanışı
Proje ayıOCAK ARA
LIK2012
OCAK
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
4. Kapasite geliştirme: destek materyaller & 4 sektörde eğitim
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
Outputs until now:
1st Draft of the new Turkish By-Law transposing Chapters I & II of IED 2010/75/EU
IPPC-IED Action Plan
Suggestions MoEU structure, coordination, next steps
o For Annex I installations
o New permit procedure
Draft permit procedure
Twinning project - TR/2008/IB/EN/03
Faaliyetler & Takvim
Remaining outputs:
Estimate of resources for Public Administration (TA for industries)
Final version By-Law
4 Sector Guides (practical versions of BREFs): o Refineries, Steel Arc Furnace, Textile, Coal LCPs
2 Basic Guides: industries , permit writers
Training for application & permit, in the 4 sectors (4 pilots)
IPPC installations’ inventory from TA
Integrated Permit Procedure
Twinning project - TR/2008/IB/EN/03
Duration: 10 months
Permit application: comprehensive guide/s
New installations: before construction
Existing installations:
o Calendar of implementation
o Investments needed: New permit procedure
Twinning project - TR/2008/IB/EN/03
Başvuru formu(ÇED raporu + EED/IPPC + Seveso
belgeleri + şehir planlaması uygunluk raporu)
Rapor (Şehir planlaması)
Yetkili otorite
1 halkın katılımı toplantısını da içeren
halkın bilgilendirilmesi süreci
120 iş günü
Bilgi eksikliğinin giderilmesi10 iş günü
- Belediyeden raporlar- Şu konularda raporlar:
• farklı atık su deşarjları• atıklar• gürültü kontrolü• havaya emisyonlar• yeraltı suları ve toprak• ÇED
Sağlık koruma bandı Atık su arıtma tesisi dizaynı onayı Yeraltı suyu arama ve kullanım izni Kurulum izni
Tüm
sür
eç b
oyun
ca h
alk
gör
üş /
itira
z bi
ldire
bilir
Entegre Çevre İzni kararı taslağı
İşletmeci
Belediye otoritesi
Paydaşlar / halk
ÇŞB
YENİ TESİSLER İÇİN ENTEGRE ÇEVRE İZNİ PLANLAMA AŞAMASI
Farklı yetkili otorite veya daireler tarafından verilen raporların temin edilmesi
Projenin bir bütün olarak değerlendirilmesi ÇED + IPPC
Görüş/itirazların yetkili otorite tarafından değerlendirilmesi
Yetkili otorite tarafından EED/IPPC İzni (uygunluğun kontrolü sonrasında geçerliliğin korunabilmesi için yerine getirilmesi gereken koşulları içeren)
Pros
edür
ün b
u kı
smı 2
05 iş
gün
ü
Iptal (işletmecinin izin koşullarını yerine getiremeyeceğini
belirtmesi durumunda)İşletmeciye bildirim Yayımlanır
ÇED raporunun alınması için ilk basamaklar (ÇED
yönetmeliğinin 11. maddesine karşılık gelir)
Belediye 20 iş günü içerisinde cevap vermeli
Seveso kategorisini gösteren Seveso belgesi
10 iş günü
20 iş günü
20 iş günü
Dosya 15 iş günü boyunca erişilebilir durumda
10 iş günü
Görüş/itiraz süreci10 iş günü
Yetkili İdareler & Halk
Twinning project - TR/2008/IB/EN/03
Tesisin inşasından önce gerekli diğer yapı izinleri
Faaliyetin başlayabilmesi için yapı kullanım izni & diğer çevre-dışı konulara ilişkin izinler
EED/IPPC Izni ile uygunluğun kontrolü
Olumlu (uygun)Olumsuz (uygun değil)
Gerekli değişiklikler için 1 ay
30 iş
gün
ü
Olumlu Olumsuz
Uygunluk Belgesi
İşletmeciye bildirim
Tesisin inşasıDenetim konusundaki
yetkili otoriteye bildirim
FAALİYET BAŞLAR
5 iş günü
Twinning project - TR/2008/IB/EN/03
Başvuru formu(ÇED raporu + EED/IPPC + Seveso
belgeleri + şehir planlaması uygunluk raporu)
Rapor (Şehir planlaması) – GEREKLİ İSE
Yetkili otorite
Halkın bilgilendirilmesi
süreci
120 iş günü
Bilgi eksikliğinin giderilmesi10 iş günü
Görüş/itiraz süreci10 iş günü
Yetkili İdareler & Halk
- Belediyeden raporlar- Şu konularda raporlar:
• farklı atık su deşarjları• atıklar• gürültü kontrolü• havaya emisyonlar• yeraltı suları ve toprak• ÇED (GEREKLİ İSE)
Sağlık koruma bandı (GEREKLİ İSE) Atık su arıtma tesisi dizaynı onayı Yeraltı suyu arama ve kullanım izni
Tüm
sür
eç b
oyun
ca h
alk
gör
üş /
itira
z bi
ldire
bilir
Entegre Çevre İzni kararı taslağı
İşletmeci
Belediye otoritesi
MEVCUT TESİSLER İÇİN ENTEGRE ÇEVRE İZNİ PLANLAMA AŞAMASI
Farklı yetkili otorite veya daireler tarafından verilen raporların temin edilmesi
Başvurunun bir bütün olarak değerlendirilmesi ÇED + IPPC
Görüş/itirazların yetkili otorite tarafından değerlendirilmesi
Yetkili otorite tarafından EED/IPPC İzni (uygunluğun kontrolü sonrasında geçerliliğin korunabilmesi için yerine getirilmesi gereken koşulları içeren)
Pros
edür
ün b
u kı
smı 2
05 iş
gün
ü
Iptal (işletmecinin izin koşullarını yerine getiremeyeceğini
belirtmesi durumundaİşletmeciye bildirim Yayımlanır
GEREKLİ İSE- ÇED raporunun alınması için ilk basamaklar
Belediye 20 iş günü içerisinde cevap vermeli
Seveso kategorisini gösteren Seveso belgesi – GEREKLİ İSE
10 iş günü
20 iş günü
20 iş günü
Dosya 15 iş günü boyunca erişilebilir durumda
Paydaşlar / halk
ÇŞB
Twinning project - TR/2008/IB/EN/03
Tesisin inşasından önce gerekli diğer yapı izinleri
Faaliyetin başlayabilmesi için yapı kullanım izni & diğer çevre-dışı konulara ilişkin izinler
EED/IPPC Izni ile uygunluğun kontrolü
Olumlu (uygun)Olumsuz (uygun değil)
Gerekli değişiklikler için 1 ay
30 iş
gün
ü
Olumlu Olumsuz
Uygunluk Belgesi
İşletmeciye bildirim
Tesisin inşasıDenetim konusundaki
yetkili otoriteye bildirim
FAALİYET BAŞLAR
5 iş günü
Twinning project - TR/2008/IB/EN/03
Draft By-Law
ANNEX IV: Public participation in decision-making
Structure:
TITLE I: Purpose, Scope, Basis, Definitions
TITLE II: Emission Limit Values and Best Available Techniques
TITLE III: Legal procedure for the Integrated Environmental Permit
TITLE IV: Inspections, infringements, non compliances and penalties
ANNEX I: Categories of activities under the scope of this By-Law
ANNEX II: List of polluting substances
ANNEX III: Criteria for determining best available techniques
Twinning project - TR/2008/IB/EN/03
Draft By-Law
ANNEX IV: Public participation in decision-making
Structure:
TITLE III: Legal procedure for the Integrated Environmental Permit
Article 16. Application for permit
Article 18. Public information and public participation meetingArticle 19. Collection of different Reports regarding the procedureArticle 20. Assessment as a whole and Draft of Integrated Environmental Permit Article 21. Plea of allegations for Public concerned and Competent Administration
Twinning project - TR/2008/IB/EN/03
Cooperation & next steps
Participation in Twinning activities (training & others)
Comments to 1st Draft By-Law
Update of Annexes in By-Laws for Permits (27214) & EIA (26939)
Final comments
Teşekkürler!
Your collaboration & comments are very important
[email protected]@gmail.com
Twinning project - TR/2008/IB/EN/03
http://ippc.cevreorman.gov.tr
Twinning project - TR/2008/IB/EN/03
Draft By-Law: Detailed structure
TITLE I. Purpose, Scope, Basis, DefinitionsArticle 1. Purpose and ScopeArticle 2. BasisArticle 3. DefinitionsArticle 4. Plants/installations/activities subject to integrated environmental permitArticle 5. Principles and basic obligations of the operator to be observed in construction, operation and dismantling of plants/installations/activities subject to integrated environmental permit.Article 6. General Binding RulesArticle 7. Coordination between the different Administrations involved in this procedureTITLE II. Emission limit values and best available techniques Article 8. Emission limit values, equivalent parameters and technical measuresArticle 9. Monitoring requirementsArticle 10. Environmental quality standardsArticle 11. Access to information and public participation in the permit procedureTITLE III. Legal procedure of the Integrated Environmental PermitCHAPTER I. Aim and enforcementArticle 12. Provisions for activities under the scope of the Integrated Environmental PermitArticle 13. Changes by operators to installationsArticle 14. Aim of the Integrated Environmental PermitCHAPTER II. Applications for and issuance of the Integrated Environmental PermitArticle 15. Urban plan certificateArticle 16. Application for permitArticle 17. Submitting of the application for permit Article 18. Public information and public participation meetingArticle 19. Collection of different Reports regarding the procedureArticle 20. Assessment as a whole and Draft of Integrated Environmental Permit Article 21. Plea of allegations for Public concerned and Competent AdministrationArticle 22. Integrated Environmental Permit
Twinning project - TR/2008/IB/EN/03
Draft By-Law: Detailed structure
Article 23. Integrated Environmental Permit conditionsArticle 24. Notification and publicity of the Integrated Environmental PermitArticle 25. Verification of compatibility with the Integrated Environmental PermitArticle 26. Start-up of the installationArticle 27. Sample taking and emission calculations after start-upArticle 28. Appeals and access to justiceArticle 29. Review and updating of permit conditions by the Competent AuthorityArticle 30. Site closureArticle 31. Activities with interprovincial and transboundary effectsArticle 32. Cost of the certificate for environmental permit and/or licenseTITLE IV. Inspections, infringements, non compliances and penaltiesCHAPTER I. Authorization and Liabilities of Environmental Consulting FirmsArticle 33. Authorization and Qualifications of Environmental Consulting FirmsArticle 34. Liabilities of the authorized environmental consulting firmsCHAPTER II. Infringements and penaltiesArticle 35. Infringements and penaltiesArticle 36. Control and inspectionProvisional Article 1. Temporary regime for existing installationProvisional Article 2. Procedures in forceArticle 37. RepealsArticle 38. EnforcementArticle 39. ExecutionANNEX I. Categories of activities under the scope of this By-Law ANNEX II. List of polluting substancesANNEX III. Criteria for determining best available techniquesANNEX IV. Public participation in decision-making