turbines on - ararat wind farm€¦ · the area,” beon energy solutions project manager michael...
TRANSCRIPT
“The local community has been
overwhelmingly supportive of the Ararat
Wind Farm and recognise the significant
benefits associated with a project of this
scale,” RES Australia's Tanya Jackson said.
“Without this community support the
project would have faced many more
challenges throughout development
and construction.
turbines onhe Ararat Wind Farm is located
180km north-west of Melbourne
and between 9-17km north-east
of Ararat on 5000 ha of land owned by
17 separate landholders. The project
is a joint venture between Downer and
GE and also benefits from a power
purchase agreement with the ACT
Government, guaranteeing the purchase
of approximately 40 per cent of the energy
produced at the site.
Project developer RES Australia identified
the high ground around Ararat as a
suitable location for a wind farm and began
initial site feasibility investigations in 2007.
A decade later, power is flowing to the
grid, with 55 of the Ararat Wind Farm’s
75 turbines erected – 40 of those
commissioned and generating electricity.
The project is on track to reach
completion by May, with all of the 75
turbines’ components delivered to site.
The Ararat Wind Farm was the first
major wind farm contract to be signed
following restored bipartisan support for
the Renewable Energy Target (RET) in
June 2015.
The power is transmitted across 21.5km
of transmission line and connection
works, including 106 poles, to the grid
via the 132/220kV transformer installed
at Elmhurst by Beon Energy Solutions
(initially launched as Citipower and
Powercor Energy Solutions).
Beon designed and constructed the
$38 million terminal station housing the
transformer, 22 days ahead of schedule.
Less than a year since construction began on the Ararat Wind Farm, the turbines are turning. The 240MW, 75-turbine facility will be the country’s third-largest wind farm and once completed, it will generate enough electricity to power around 120,000 homes in Victoria.
In April, a 128-tonne transformer required
to convert power generated from the wind
farm to the main electricity grid rolled
through the sleepy town of Elmhurst,
after travelling more than 6000 nautical
miles from Shanghai to the Port of
Melbourne. Transport of the transformer,
the biggest single component of the
project’s construction, required a convoy
of escorts and two prime movers to carry
the 4.2m wide and 50m long trailer along
the Pyrenees Highway through Ararat
and into Elmhurst.
The terminal station and the connection
assets of 106 poles and 21.5km of
transmission line was completed and fully
energised by the end of June 2016.
To convert the 33kV wind farm electrical
collector network to 132kV for transmission
to the electricity grid via the Elmhurst
transformer, two purpose-built
transformers were installed on site.
The transformers, procured via a
$4 million contract with Victorian-
based Wilson Transformer
Company, are more than 8m in
length, 4.5m wide and 7m high
when fully assembled.
The transformers were
manufactured and tested in
Glen Waverley, Victoria, and
represent the completion of a
substantial contract for Wilson
Transformer Company.
GE Downer has completed
the 52km internal access track
across the site.
TAnother major milestone for the Ararat
Wind Farm was the installation by Beon
Energy of the innovative Enchanced
Silicon Polymer (ESP) insulators on the
132kV powerline.
The Ararat Wind Farm was the first to
have the ESP insulators installed.
Previously, porcelain insulators have been
used for this type of construction,
however, the ESP insulator provides
a lighter, quicker and environmentally
safer alternative.
The ESP insulator provides a braced
arrangement, which is stronger and
can withstand higher loads than the
porcelain equivalent. This allows for
longer spans, which lead to a reduced
number of structures for the project.
The ESP insulator is substantially lighter
than porcelain, which saved significant time
in construction. The ESP insulator is also
bird resistant which is critical as the power
line is located in a high bird strike zone.
“We are very happy with the ESP
Insulator, they are lighter to use which
decreases our manual handling risk,
quicker to construct and we never had
any evidence of bird damage as there
was a significant amount of cockatoos in
the area,” Beon Energy Solutions project
manager Michael Kennedy said.
The need for polymer insulators
occurred as transmission voltages rose
through 500kV to 750kV and beyond,
as the loading from porcelain and glass
insulators became extreme.
“Ohio Brass/Hubbell Power Systems
sold the first EPDM alloy polymer
tension insulator in 1976 for a 750kV
transmission line application, and
this early generation was installed in
Australia by 1980,” Bri-Tech’s Cameron
Galbraith said.
“All of these early generation insulators
are still performing, other than where they
have been replaced with upgrades or
route changes.
“Through Hubbell’s process
of continuous improvement, the
polymer was improved to become ESP,
and since 1986, has remained essentially
the same with a unique blend of durability,
mechanical strength, tracking resistance,
hydrophobicity and longevity in the
environment.”
With more than 1.6 million ESP insulators
and arresters in service in Australia alone
and more than 40 years of field installation
experience, there has been only one
insulator reported with serious bird
damage and even that instance did not
result in a field failure.
Polymer insulators provide exceptional
capacity to resist conductor failure and
share load between insulators. ESP has
a proven ability to not attract birds and
resist damage by them.
“Transmission and distribution engineers
now have a major resource to help ensure
optimum value and long-term service
when building lines,” Mr Galbraith said.
“In today’s environment, a utility can’t
afford to build a line and then return
within a year to replace damaged
insulators or even worse deal with
an outage condition or dropped line
generated by a failed insulator.”
“We have made a concerted effort to keep
the community informed of construction
progress and where possible invited them
to share in significant project milestones,
such as the arrival of the first turbine
blade in June.”
INDUSTRY UPDATE
2017 JAN|FEB38
INDUSTRY UPDATE
JAN|FEB 2017 39