tugas04 - 15512029 - deded permana
TRANSCRIPT
![Page 1: Tugas04 - 15512029 - Deded Permana](https://reader030.vdocuments.site/reader030/viewer/2022021112/5695d4731a28ab9b02a17c9e/html5/thumbnails/1.jpg)
7/24/2019 Tugas04 - 15512029 - Deded Permana
http://slidepdf.com/reader/full/tugas04-15512029-deded-permana 1/4
TUGAS 4
KL 4110
PERENCAAN DAN PRASARANA PELABUHAN
Dosen :AndojoWurjanto, Ph.D
Deded Permana
15512029
PROGRAM STUDI TEKNIK KELAUTAN
FAKULTAS TEKNIK SIPIL DAN LINGKUNGAN
INSTITUT TEKNOLOGI BANDUNG
2015
![Page 2: Tugas04 - 15512029 - Deded Permana](https://reader030.vdocuments.site/reader030/viewer/2022021112/5695d4731a28ab9b02a17c9e/html5/thumbnails/2.jpg)
7/24/2019 Tugas04 - 15512029 - Deded Permana
http://slidepdf.com/reader/full/tugas04-15512029-deded-permana 2/4
1.
Kapal rencana yang dipilih adalah general cargo ship (ambil ukuran terbesar pada
tabel).
Sumber : Fentek – Catalogue
Ilustrasi ukuran kapal :
![Page 3: Tugas04 - 15512029 - Deded Permana](https://reader030.vdocuments.site/reader030/viewer/2022021112/5695d4731a28ab9b02a17c9e/html5/thumbnails/3.jpg)
7/24/2019 Tugas04 - 15512029 - Deded Permana
http://slidepdf.com/reader/full/tugas04-15512029-deded-permana 3/4
2.
Rencana Dermaga
Perhitungan
Panjang dermaga : =1 , + (2 .40) 209 + 80 289
Lebar dermaga : Lebar = Gantry span + Diameter putar truk + 3m (jarak crane dari pinggir
dermaga )
: Lebar = 15m + 30m + 3m = 48m
Elevasi : HWS + 0.5H + freeboard
Asumsi, HWS = 1,62m ; H = 3m ; freeboard = 0,5m
Elevasi dermaga : 1,62 + 1,5 + 0,5 = 3,62 m (dari MSL)
Denah : (satuan dalam meter)
A
A
B B
![Page 4: Tugas04 - 15512029 - Deded Permana](https://reader030.vdocuments.site/reader030/viewer/2022021112/5695d4731a28ab9b02a17c9e/html5/thumbnails/4.jpg)
7/24/2019 Tugas04 - 15512029 - Deded Permana
http://slidepdf.com/reader/full/tugas04-15512029-deded-permana 4/4
Potongan A-A (satuan dalam meter)
Potongan B-B (satuan dalam meter)