http://nodal.ercot.com 1 TSP Nodal Engagement Market Participant Call ERCOT August 04, 2010

Upload: yuki

Post on 07-Jan-2016

33 views

Category:

Documents


2 download

DESCRIPTION

TSP Nodal Engagement Market Participant Call. ERCOT August 04, 2010. Agenda. General Reminders / Updates SSWG update NDSWG Update – None this week. Market Trials 2010 Roadmap. Full System Market and Reliability Testing Update. LFC Update. Next Full System Test 24-Hours in duration - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: TSP Nodal Engagement  Market Participant Call

http://nodal.ercot.com 1

TSP Nodal Engagement Market Participant Call

ERCOT

August 04, 2010

Page 2: TSP Nodal Engagement  Market Participant Call

• General Reminders / Updates

• SSWG update

• NDSWG Update – None this week

Agenda

http://nodal.ercot.com 2

Page 3: TSP Nodal Engagement  Market Participant Call

Market Trials 2010 Roadmap

http://nodal.ercot.com 3

Page 4: TSP Nodal Engagement  Market Participant Call

http://nodal.ercot.com 4

Full System Market and Reliability Testing Update

Page 5: TSP Nodal Engagement  Market Participant Call

http://nodal.ercot.com 5

LFC Update

– Next Full System Test• 24-Hours in duration• To start on Thursday 8/19/2010 12:00 PM and complete on 8/20/2010 12:00 PM• Operational scenarios will be discussed on the Friday Real Time Market call

– 168-Hour update• Additional discussions on the format and objectives were discussed at the

NATF session on 8/9/2010• It was agreed that a revised Handbook would be published and discussed at a

Special TAC session• The special TAC session will occur on 8/12/2010

Page 6: TSP Nodal Engagement  Market Participant Call

http://nodal.ercot.com 6

General Reminders

Page 7: TSP Nodal Engagement  Market Participant Call

http://nodal.ercot.com 7

General Reminders

– Joint NDSQG and NATF session to occur on Tuesday 8/17/2010• Session will be dedicated locking in modeling expectations• Details are posted at: http://www.ercot.com/calendar/2010/08/20100817-NATFNDSWG

• Reminder: Outage Scheduler with Zonal Outage Transfer• Delete all Outages and run Zonal to Nodal Transfer Tool Friday, 8/13 (Note that 80% to 85% of the

outages are transferred)

• Resource Outages will not be transferred by the Transfer tool

• The target is to make available for outage transfer validation and outage submissions Monday 8/16, 7:00 am, for the upcoming tests, optional months of October & November and for December and beyond

• A Market Notice will be sent out once ERCOT has completed this work. It is important that MPs do not start validation prior to receiving this Market Notice.

• Request list of Outages not transferred from [email protected]

• Send email to Market [email protected] confirming outages have been validated by 9/17 for all Outages December and beyond

• First production pull of OS data is scheduled for 10/2 for the first CRR Auction

• TSPs and QSEs are responsible to ensure that the outages in the Nodal Outage Scheduler are correct

• Outages previously approved in zonal will be automatically approved in Nodal

Page 8: TSP Nodal Engagement  Market Participant Call

ERCOT TAC Meeting - ROS Report03/04/2010 Ken Donohoo

8

Nodal Model Effort Activity

OperationsModel

(NMMS)

CRRModel

TopologyProcessor(Software)

Long TermPlanning

Model

NDSWGSupport

SSWGSupport

SSWGSupport

SSWG& ERCOT

Development

Page 9: TSP Nodal Engagement  Market Participant Call

SSWG Planning Model Activities

• Correcting Connectivity Node Groups– Aug 6 TP output: 87 CNGs needing correction

• Phase II Corrections: Area #, Zone #, Load ID, Branch ID, Generator ID, mileage

– ERCOT sent correction spreadsheet July 9– Due July 30

• August 15 Deadline for submitting NOMCRs to correct planning data

Page 10: TSP Nodal Engagement  Market Participant Call

SSWG Planning Model Activities

• New Topology Processor update delivered to ERCOT– Being tested by ERCOT and SSWG– SSWG has submitted a System Change Request (SCR759) related to the

Topology Processor changes• ROS approved with “High” priority at July 15 meeting• ROS to formally approve and place in Priority List at Aug 13 meeting

• Identifying important modeling issues– Categorize these and determine if additional SCRs are necessary– SSWG to work on drafting next SCR

• MOD/PMCR Training complete– MOD Sandbox to be opened for TSP access until Sept 1

• Aug 18 meeting – Plan 2010 Test Case procedure– First test of creating case with new method– Many unknowns to be discussed

Page 11: TSP Nodal Engagement  Market Participant Call

SSWG Modeling Issues

Annual Planning Model related issues:• SPS: Additional equipment modeled in IMM• Off-nominal transformers: TP not calculating impedances

correctly• Transformer modeling: 2 winding vs 3 winding• No ratings on zero impedance line segments• Ownership• Loads and cap banks being collapsed to the correct CNGs• Cap banks connected to distribution voltage• FACTS devices• Future versions of PSSE• MOD issues: submission process, access, project types, user-

defined fields, PMCR to NOMCR transition• TSPs without PSSE or MOD File Builder

Page 12: TSP Nodal Engagement  Market Participant Call

SSWG Nodal Schedule

June – August Make remaining changes to IMM prior to Planning Go-Live

July TSPs Complete changes based on TP enhancements

Aug 15 Deadline for submitting NOMCRs with planning changes

Aug 18 SSWG 2010 test case meeting

Aug Compare TP output to SSWG 2010 summer peak case

Nov Create 2012 summer peak case using TP and MOD

Dec – Feb 2011 Review, update, and modify TP/MOD process for case creation

Dec 1 Nodal Go-Live

Mar – April 2011 Assuming Nov test meets SSWG approval, begin work to create 12DSA using Nodal

method

Page 13: TSP Nodal Engagement  Market Participant Call

Telemetry Quality Update

• July SE Telemetry Standards Report Posted on MIS Secure

– Monthly and Quarterly Telemetry Point Availability Statistics Report (June and July 2010)

– Quarterly Point Availability Statistics Report (Q2 2010)

– Reports => Reports and Extracts Index

• TSPs

– 11 out of 20 TSPs above 98% for June, No TSPs below 90%

– 18 out of 20 TSPs above 98% for July, No TSPs below 96%

• QSEs

– 58 out of 79 QSEs above 98% for July. 95.66% average for the 21 QSEs below 98%

http://nodal.ercot.com 13

Page 14: TSP Nodal Engagement  Market Participant Call

Telemetry Quality Update

• MP23 Telemetry Quality Metric– Needed for Nodal Readiness. Scheduled to light up 8/25 (using July 2010 statistics)– ERCOT will use the 98% threshold. If the Telemetry Standards are modified and

approved by TAC, ERCOT will adopt the new threshold in the metric.– Will be updated monthly until Nodal Go-Live (based on monthly statistics)– From 8/25 to 9/30

• Green >= 98%, Amber >= 90% and < 98%, Red < 90%– From 10/1 – Nodal Go-Live

• Green >= 98%• Red < 90%

– For new equipment and outages, TSPs and QSEs can manually override telemetry to ensure that availability statistics are as accurate as possible

• Communication– For any concerns over reports, contact [email protected]– For resolution to telemetry issues, contact [email protected]