    Weekly Site Progress Report Property Services

    Progress Report No: PS-005

    Date: 10 May 2011

    Progress Report for the Design Co-ordination Workshop

    Date: 11 May 2011 ( Day 1 )

    Day 1 : 09:30 to 18:00

    Issues have been discussed.

    A) Lift and escalatorSubcontractor: MELCO

    The first lot of lift equipment arrived on site on 6 May, 2011. This shipment includes Rail, Car

    Frame.

    Next shipment will include Lift Motor, Car Panel and Car Cable Roles. Time: TBA

    As main construction work still in progress and Melco will split the lift shaft installation work

    into 2 phases; first phase is start from 13 May 2011 and at 32/F and below. On 30 June 2011,

    main contractor will handover the 32/F and above and Melco will continue the rest of

    installation.

    B) Faade LightingSubcontractor: YKK

    Coordination work for 3 nos. of Faade lighting panel had completed. YKK agreed the

    locations for the switches board.

    WMC reminded YKK all connection for IBMS must be open circuit ( eg: Bacnet or eqv. ) and

    YKK agreed for this.

    WMC urged YKK to submit the electrical main switch board for approval as it was outstanding

    for long time. YKK agreed and submission will be done before 19 May 2011.

  • 8/6/2019 TS Site Progress Report 5

    2/2

    PS Form SPR.Rev0 Page 2/2 Revised date: 5/11/2011

    HVAC

    DN600 Condensing Pipe Riser: The riser installation can be started and the pipe support detail

    will be finalized by Engineer with subcontractor. Target to start the installation is 16 May 2011.

    Drawing / site installation Co-ordination Workshop

    B1 to B3 all plant rooms set up cleared for installation.

    The current Carpark ceiling design is 1.9m. Owners requirement for 2.2m can be achieved by

    using the original duct work design. Arup will issue the EI and follow on the access issue due tothe changes.

    At B3, the Domestics Transfer Pump Room is found too small for proper operation and

    maintenance work cannot be carried out. Engineer is requested to access any possible

    alternatives to enlarge the room

    For 5/F to 8/F, Arup will bring the cooling load design calculation on site so that we can prepare

    the single line design drawings on site.

    Close type Feed and Expansion tanks ( HVAC & PD )

    The existing design is not workable; Arup will revise the design of feed and expansion tank for

    both HVAC and PD system. Engineer will then issue EI for cost deduction. Contractor was

    instructed not to purchase the unnecessary parts and negative VO will be prepared.

    Other Issues:

    - Tomorrow will be continue for Day 2 workshop ( Level 1 to Level 8 )Next Meeting:

    - Next Meeting is on 12th

    May 2011

    Reported by: Danny Chan