transporting, deposition, curing and finishing of concrete

Upload: sathish-selva

Post on 04-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    1/29

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    2/29

    102

    Concrete Technology appreciate the importance of placing of concrete, explain the steps taken for preparation of surface before placing

    concrete,

    discuss the different types of vibrators, appreciate the importance and objectives of curing, describe the methods of curing, duration of curing and effects of

    delayed curing,

    explain the finishing operations, and explain the purpose of providing the joints in concrete construction.

    6.2 TRANSPORTATION OF CONCRETE

    The process of carrying the concrete mix from the place of its mixing to final

    position of deposition is called as transportation of concrete.

    The time factor is very important in case of transportation of concrete. Theconcrete mix should be transported as quickly as possible.

    6.2.1 Importance of Transportation

    The concrete mix should carry from its mixing place to final position of

    placement in a very short time. It will minimize the loss of water by evaporation.

    It will also not allow the concrete to become stiff. The mix can be transported

    either manually or mechanically. In case of manual labour, the concrete is

    transported in iron-pans, wheel barrows, etc. Pumps or trucks or belt conveyors

    are used to transport the concrete mechanically. The concrete mix required at

    lower levels is transported by chutes and at upper levels is hoisted by means of

    barrow lifts attached to the scaffolding.

    6.2.2 Precautions in Transporting of Concrete

    The following precautions should be observed during transporting of concrete

    from the mixing place.

    (a) When water is added to cement, the process of hydration starts andwith the passage of time, the cement-water paste starts solidifying

    thus making concrete stiffer. Concrete should be transported as

    quickly as possible to the formwork within the initial setting time of

    cement.

    (b) The process of mixing, transporting, placing and compacting concreteshould not take more than 90 minutes in any case.

    (c) No water should be lost from the mix during transportation.(d) The concrete mix should be protected from drying in hot weather and

    from rain during transport from the place of mixing to the position of

    placing.

    (e) The cost of transportation should be as low as possible.(f) Segregation of concrete should be prevented under all circumstances.

    Ready Mixed Concrete in which the segregation is observed, should

    not be placed in any case.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    3/29

    103

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    (g) The concrete should be kept agitated in truck mixer in order toprevent it from becoming stiff if more time is likely to be spent during

    transportation.

    (h) The permissible duration of transport of concrete should bedetermined in the laboratory.

    6.2.3 Transporting OperationsThe following are the transporting operations used for concrete in order to

    discharge it directly into the position where it is required.

    (a) Transport of concrete by pans,(b) Transport of concrete by wheel barrows,(c) Transport of concrete by tipping lorries,(d) Transport of concrete in containers,(e) Transport of concrete by belt conveyors, and(f)

    Transport of concrete by pumps.

    Transport of Concrete by Pans

    Iron pans are used for transportation of concrete. This method is adopted

    where the quantity of mix is small and access to the point of placing is

    restricted. This method is slow as well as costly.

    Transport of Concrete by Wheelbarrows

    The capacity of wheelbarrows varies from 70 liters to 80 liters. Steel

    wheelbarrows with pneumatic tyres are used for moderate distances.

    Transport of Concrete by Tipping Lorries

    This method is widely used for the transport of concrete mix and

    discharging it directly at the position of concreting such as in the

    construction of air field pavements, dams, concrete floors, canal lining and

    roads, etc. Tipping lorries are used for transporting ready mixed concrete

    and for arrangements for receiving, loading and reloading it. The height of

    mix in the lorries should not be less than 40 cm in order to avoid

    segregation. The mix delivered in tipping lorries is discharged directly into

    the structure. If it becomes difficult, then the mix is discharged into skips or

    tubs, which are then moved to the position of placing by crane.

    Transport of Concrete in Containers

    This method exclude the loss of mortar and cement slurry during

    transportation and also ensure the gradual emptying which is necessary for

    concreting reinforced structures. This is one of the main methods of

    delivering ready-mixed concrete from the mixing place to the point of

    placing without the need for unloading and reloading. For this purpose

    hoppers, skips and wagon bodies are used. Lorries transport hoppers and

    skips. Containers are delivered from the transport vehicle to the position of

    placing the concrete mix by cranes of different types and desired lifting

    capacity. This method reduces the risk of segregation of concrete and also

    protects it from atmospheric effects.

    Transport of Concrete by Belt Conveyors

    In this method, the belt used has a covering of rubber of width 60 cm and

    speed not exceeding 1 m/s. The slump of concrete mix should not be more

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    4/29

    104

    Concrete Technology than 6 cm in any case. The line of the conveyors should not have any

    marked breaks in plan. The angle of inclination of the conveyor must not

    exceed 18for 4 cm slump and 15for 4 to 6 cm slump. Flat belts are used

    only for a distance of 20 m and if the distance is large, the working part of

    the belt should be trough shaped. When the concrete is unloaded from the

    conveyor or when it is transferred from one part of the conveyor to another,

    guide boards should be used to prevent segregation of concrete. Boards

    should be arranged properly so as to avoid segregation (Figure 6.1). Free

    falling of concrete from the roller of the conveyor is also not allowed.

    For getting continuous supply of concrete this method is used. This method

    is most suitable under summer conditions for concreting structures at a

    distance of 250 to 500 m from the place of mixing and also in those cases

    where it is difficult for lorries and other types of transport to reach the

    structure.

    Figure 6.1 : Methods of Discharging Concrete from Belt

    Transport of Concrete by Pumps

    Concrete pumps are used to deliver concrete for concreting densely

    reinforced structures, internal structural elements of buildings and large

    mass concrete structures. These are also used for concreting of tunnel

    linings. Such pumps cover a horizontal distance of 300 to 400 m and a

    vertical distance of 40 to 50 m. Pumping is a process of transporting

    concrete without unloading and reloading in a vertical or horizontal

    direction and without a harmful effect on its quality.

    Figure 6.2 : Transportation of Concrete by Pumps

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    5/29

    105

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    In this method, the concrete is charged into the receiving hopper and kept

    mixed continuously by the paddles in order to retain uniformity of mix and

    to prevent segregation. The impeller blades through the open suction valve

    push the concrete into the barrel of the pump. The suction valve closes

    when the plunger moves to the left. The pressure valve opens which moves

    the concrete from the barrel into the pipeline. The diameter of the pipeline

    depends upon the size of the aggregate used but it does not exceed 30 cm in

    any case. The slump should not be less than 5 cm and more than 8 cm. The

    water-cement ratio should remain between 0.5 to 0.65. Stiff mixes are not

    suitable to be delivered by pumps because their pumping properties are not

    good. Sharp turns and bends should be avoided in the pipeline. The number

    of bends in a pipeline should be as small as possible.

    6.2.4 Safety during Transportation of Concrete

    The following safety measures must be observed during transport of concrete.

    (a) The distance between wagons being moved by hand simultaneouslyin one direction should not exceed 20 m in any case and 30 m on

    slopes.

    (b) The distance from the bottom of the skip to the surface on which it isdischarged should not exceed 1 m in any case if concrete is

    discharged from the skips.

    (c) Places where lorries are discharged should be equipped with strongsupports for tipping lorries.

    (d) No person should be present on the structure being concreted at theposition of discharge of the tipping lorry.

    (e) The whole system of the pipe line should be checked up by usinghydraulic pressure 1.5 times the operating pressure before pumping

    concrete. Generally, water is used for this purpose.

    (f) The driver of the hoist should be able to see the positions of chargingand discharging the hoist when the mix is to be raised by shaft hoists.

    (g) The barrow run should be cleaned for the removal of dirt and concretewhen concrete is transported by wheelbarrow. If the barrow run is

    located at a height of more than 1 m, the boarded surface should not

    be less than 1.2 m wide and fencing must be 1 m high. The thickness

    of the board for fencing should not be less than 15 cm.

    SAQ 1

    (a) What do you mean by transportation of concrete?(b) What precautions should be taken during transportation of concrete?(c) Enlist the methods of transportation and explain any one.(d) State the safety measures to be taken during transportation of

    concrete.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    6/29

    106

    Concrete Technology6.3 PLACEMENT OR DEPOSITION OF CONCRETE

    The process of depositing the concrete in its required position is called placement

    of concrete.

    It is very essential to place concrete properly and carefully in order to obtain good

    quality of surface. Areas which will be in contact with concrete must be prepared

    carefully before placing concrete.

    6.3.1 Importance of Placing of Concrete

    The quality of concrete depends on the method of placing it during concreting. If

    it is not placed properly, segregation will result. The formation of irregular and

    unsightly lines will also take place. Therefore, in order to remove the possibility

    of occurrence of segregation and irregular lines, it is very important to place

    concrete uniformly and properly.

    6.3.2 Precautions while Placing Concrete

    The following precautions must be observed during placing of concrete in orderto get required strength of the concrete.

    (a) The concrete should not be thrown from a height of more than 1 m toprevent segregation.

    (b) The concrete should be deposited in horizontal layers of uniformthickness not exceeding 45 cm for mass concrete and 30 cm for

    reinforced concrete.

    (c) No person should be allowed to walk over freshly laid concrete.(d) The old surface should be made rough, cleaned and cement grouted

    before placing any new layer of concrete.(e) The alignment of reinforcement and formwork should not be

    disturbed in any case when concrete is placed in RCC members.

    (f) Placement of concrete should be discontinued during rainy periods.(g) The laitance should be removed, i.e. squeezed out, before placing new

    concrete.

    (h) Concrete should be laid continuously in order to prevent theformation of irregular and unsightly lines.

    (i) The internal surfaces of the formwork should be oiled in order toprevent concrete from sticking to sides.

    (j) The placing of concrete should start widthwise in reinforced cementconcrete slabs.

    6.3.3 Preparation of Surface before Placing Concrete

    It is very essential to prepare a proper base or place before placing the concrete

    mix in order to develop proper bond between the base and fresh concrete. Before

    placing concrete, the different types of bases should be prepared as below.

    In the Case of Hardened Concrete Base

    The coarse aggregates should be exposed by making the base rough. It ismade rough by striking sand under high pressure (i.e. hand blasting). After

    this the surface should be washed with water under pressure in order to

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    7/29

    107

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    remove the dust particles from it. After the surface is cleaned, a thin coat of

    cement paste is applied before placing concrete over the hard surface.

    In the Case of Specially Prepared Sub-bases

    In case of brick soling and water bound macadam, base should be made

    rough with the help of steel brush. Dust and loose particles should be

    removed from the sub-base before placing the concrete over it. Before

    placing concrete the water should be sprinkled over the surface.

    In the Case of Natural Soil

    Before placing any layer of concrete over natural soil, the soil should be

    compacted uniformly and its moisture deficiency should be removed

    initially in order to prevent it from absorbing moisture from beneath the

    concrete layer.

    In the Case of Rocky Base

    In the case of rocky base the sides should be cut in vertical direction and not

    in sloping direction. All the loose particles should be removed off the rocky

    base. Before placing concrete the water should be sprinkled over thesurface.

    SAQ 2

    (a) What is meant by placement of concrete?(b) What are the precautions to be taken while placing the concrete?(c) How surface should be prepared before placing of the concrete?

    6.4 COMPACTION OF CONCRETE

    The process of consolidating concrete mix after placing it in position is called as

    compaction of concrete.

    The object of compaction is to remove air from the concrete and to give

    maximum density to the concrete. Presence of more air voids will reduce thestrength. It also ensures an intimate contact between the concrete and the surfaces

    of reinforcing steel and other embedded parts of the structure. During the process

    of compaction it is important to note that the reinforcement should not be

    disturbed and the forms should not be damaged or displaced. If the compaction is

    not uniform, the concrete becomes porous, non-homogeneous and attains less

    strength. The mix to be used should have adequate workability for placing

    without any difficulty and in order to obtain maximum density. The mix should

    also not be too wet, as it would otherwise cause segregation, lower density, and

    excessive laitance at the top.

    6.4.1 Importance of CompactionA considerable amount of air is entrapped in concrete along with the partial

    segregation of aggregates during the manufacture of concrete. It lowers the

    quality of concrete by making it porous and non-homogeneous. The importance

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    8/29

    108

    of compacting operations is to remove the entrapped air and arrange the

    ingredients uniformly to obtain better quality of concrete. The strength of

    concrete may reduce by 30% by the presence of only 5% voids. The density,

    durability and strength of concrete are the factors, which affect the quality of

    compaction.

    Concrete Technology

    6.4.2 Compaction Methods

    It is very important to decide whether to use a workable mix with hand or a stiffermix with vibration before considering the method of compaction. It has been

    determined that a better surface with less blow holes is obtained for workable

    concrete.

    The compaction methods are classified as follows :

    Hand Compaction

    Hand compaction method is adopted for pavements, narrow and deep

    members. Compaction must be uniform and concrete must reach to the

    corners of the formwork. Excessive compaction is not good because it will

    try to push the aggregates at the bottom thus bringing the mortar at the

    surface. Iron rods and rammers are used for the hand compaction. Mass

    concrete is compacted in successive layers of thickness not exceeding 30

    cm by tamping with light rammers or templates. Iron rods are used for

    compacting reinforced concrete work in layers not exceeding 15 cm in

    thickness.

    Hand compaction is further classified as follows :

    Rodding

    Rodding is adopted in case of unimportant concrete work of small

    magnitude. When rodding is used, the consistency of concrete is

    maintained at a higher level. The thickness of the layer is limited

    about 15 to 20 cm. Rodding is nothing but poking the concrete with

    about 2 m long, 16mm diameter rod to pack the concrete between the

    reinforcement and sharp corners and edges. Rodding is done

    continuously over the complete area to effectively pack the concrete

    and drive away the entrapped air.

    Instead of iron rod, bamboos or cane may also be used for rodding

    purpose.

    Ramming

    Ramming should be done with care as it may disturb the position of

    reinforcement or the formwork may fail if steel rammer is used. Lightramming can be permitted in un-reinforced foundation concrete or in

    ground floor construction. It should not be permitted in case of

    reinforced concrete or in the upper floor construction, where concrete

    is placed in the formwork supported on struts.

    Tamping

    Tamping is one of the usual methods adopted in compacting roof or

    floor slab or road pavements where the thickness of concrete is

    comparatively less and the surface to be finished smooth and level.

    Tamping consists of beating the top surface by wooden crossbeam of

    section about 10

    10 cm.Mechanical Compaction

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    9/29

    109

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    In case of mechanical compaction concrete is compacted by vibration

    during which the vibrator communicates rapid vibrations to the particles

    thus increasing the mobility of concrete. The particles occupy a more stable

    position under the force of gravity. The concrete mix fills all the spaces thus

    forcing air to the surface and making concrete denser. The frequency and

    duration of vibration, its amplitude depends on the conditions of vibration

    for compacting the mix. The maximum frequency of vibration depends on

    the size of the particles and on the mobility of concrete. Following are the

    advantages of vibratory compaction.

    (a) A better finish and better quality of concrete is obtained ascompared to hand compaction.

    (b) The concrete produced is more dense and impermeable.(c) Bond between steel and concrete is improved.(d) Laitance is partially reduced.(e) Speed of placing concrete is increased by the ready flow of

    vibrated concrete into difficult positions.

    (f) Creep and shrinkage are also reduced due to the possibility ofhigher aggregate-cement ratio.

    (g) Concrete with even lower w/c ratio and with lower cement canbe compacted effectively.

    (h) Better compaction can be achieved in heavily reinforcedconcrete members.

    The following difficulties are encountered in vibratory compaction.

    (a) Finishing of horizontal surface.(b) Discharging very stiff concrete from mixers.(c) The lack of sufficient vibration at points not immediately in

    contact with the vibrating equipment thus resulting in

    segregation.

    (d) Discharging stiff concrete from lorries and other means oftransport.

    Compaction by Pressure and Jolting

    This is one of the effective methods of compacting very dry concrete. This

    method is used for compacting hollow blocks, cavity blocks and solid

    concrete blocks. The stiff concrete is vibrated, pressed and also given joltsand due to this the stiff concrete gets compacted to dense form to give good

    strength. By applying great pressure, a concrete of very low water cement

    ratio could be compacted to yield very high strength. Generally this method

    is used in the laboratory.

    Compaction by Spinning

    Spinning is one of the recent methods of compaction of concrete and is used

    for the fabrication of concrete pipes. The plastic concrete when spun at a

    very high speed, gets well compacted by centrifugal force.

    6.4.3 Types of VibratorsThe vibrators commonly used are classified as follows :

    (a) Internal vibrator

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    10/29

    110

    Concrete Technology (b) Screed vibrator(c) Form vibrator(d) Table vibrator(e) Platform vibrator

    Internal Vibrator

    Internal vibrator is also known as needle or immersion or poker vibrator. Itconsists of a power unit and a long flexible tube at the end of which fitted a

    vibrating head. These vibrators have higher efficiency since all the energy

    is directly transmitted to the concrete. As they are portable, therefore, can

    be readily used in difficult positions. The vibrating element is immersed in

    the fresh concrete, which transmits vibrations through the vibrator body. It

    is very important to keep the vibrating head in the concrete while running in

    order to keep the bearings cool and avoid breakdowns. It should be inserted

    vertically or nearly so at points 45 cm to 75 cm apart and should be

    withdrawn slowly at the rate of 7.5 cm/sec. These should not be used for

    pushing concrete laterally in the formworks because it will cause

    segregation. The frequency of vibration is about 7000 cycles/mt. Suchvibrators are used for compacting large sections of mass concrete in

    structures, for concrete of beams, columns, foundations, etc.

    Figure 6.3 : Internal Vibrator

    Screed Vibrator

    Screed vibrator is also known as surface vibrator. These vibrators are used

    for compacting plain concrete or one-way reinforced concrete floors, road

    surfaces, the thickness of which does not exceed 20 cm. This vibrator is setup on the concrete surface after placing the concrete and vibrations are

    transmitted to concrete through a working platform.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    11/29

    111

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    Figure 6.4 : Section of a Typical Metal Form for Road Slab Construction

    Figure 6.5 : Compaction of Cement Concrete Road Slab by a Screed Vibrator

    Form Vibrator

    Form vibrators are also known as external vibrator. It is fastened to the

    formwork by a clamping device and transmits vibrations to the concrete.

    External vibrator is clamped at a distance up to 25 cm in depth from the

    formwork. The vibrator must be firmly clamped to the form as otherwise its

    efficiency will be reduced. The formwork should be sufficiently strong and

    rigid to resist the oscillatory action. The time of vibration is from 45 to

    90 seconds. The vibrator is switched off for 5 minutes after its continuous

    working for half an hour in order to allow cooling of motor. If the motor of

    the vibrator heats up more rapidly, the work should be immediately

    stopped. The electrician should be called in order to check the motor

    winding. In this case, more power is required in comparison to internal

    vibrators. Therefore, emergency vibrators must be kept near the concreting

    work as replacement for vibrators, which go out of order. Form vibrators

    are used in concreting of thin components of monolithic structures, heavily

    reinforced arches and tunnel and tunnel lining, etc. They are also used in the

    production of different pre-cast reinforced concrete components.

    Table Vibrator

    This method is mostly adopted in the laboratories. This is the special case

    of a formwork vibrator, where the vibrator is clamped to the table. This

    method is used in making small but precise prefabricated reinforced cement

    concrete members. In this method, any member kept on the table gets

    vibrated.

    Platform Vibrator

    It is nothing but a table vibrator larger in size. Sometimes, the platform

    vibrator is also coupled with jerking or shock giving arrangements so that a

    thorough compaction is given to the concrete. Platform vibrator is used in

    the manufacture of large prefabricated concrete elements such as railway

    sleepers, prefabricated roofing elements, electric poles, etc.

    6.4.4 Handling of Vibrators

    Needle vibrators should be penetrated in vertical direction and vibrations should

    be transmitted till the concrete flattens and no entrapped air appears on the

    surface. The vibrator should be taken out of concrete slowly and carefully. Skilled

    workmen are essentially required for producing a uniform and well-compacted

    concrete. The correct placing and tamping of concrete mainly depends on the skill

    of the workmen and their experience. Vibration by unskilled persons is probably

    more dangerous than hand tamping, as there is always a risk of either under-compaction or over-compaction of concrete. The equipment to be used for

    vibration must be kept clean and free from coatings of set concrete. Thus, the

    vibrators should be used very carefully in order to compact the concrete layer

    uniformly.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    12/29

    112

    Concrete Technology The following steps should be observed in order to obtain good results by

    compacting concrete with vibrators.

    (a) Vibrators should be controlled carefully by immersing the internalvibrator for 5 to 15 seconds at points 45 to 75 cm apart.

    (b) The formworks should be as tight as possible in order to prevent anyleakage of mortar.

    (c) The vibrator should be inserted vertically otherwise it will not bepossible to regulate the degree of compaction in all portions of

    concrete.

    (d) The lift should not be less than 15 cm in order to avoid air beingtrapped.

    (e) The vibrator should be immersed through the full depth of the freshlylaid concrete. It should also be immersed into the lower layer if the

    concrete in that layer is still plastic.

    (f) The vibrator should be withdrawn very slowly and should be allowedto penetrate of its own accord.

    (g) The vibrator should not touch the form surface otherwise a sandstreak is likely to occur. The surface of the formwork can also be

    damaged.

    (h) The vibrator should only be used for compaction purposes. It shouldnot be used for pushing the concrete laterally in the formworks, which

    would otherwise cause segregation.

    6.4.5 Suitability of Mix for Compaction with Vibrator

    The consistency of concrete depends upon the placing conditions, type of mix and

    the efficiency of the vibrator. The slump should not exceed 5 cm when

    compacting concrete with vibrators. If the slump of the concrete mix is more, the

    segregation will take place. Segregation should be prevented under all

    circumstances.

    6.4.6 Selection of Vibrators for Various Situations

    Following table indicates the use of various vibrators depending upon the

    situation.

    Table 6.1 : Selection of Vibrators

    Sl. No. Type of Vibrator Places where Used

    1. Internal For large sections of mass concrete in

    structures, for concrete of foundations,

    columns, beams, etc.

    2. Screed For plain concrete or one-way

    reinforced concrete floors, road

    surfaces.

    3. Form For concreting thin components ofmonolithic structures, arches and

    tunnel lining, etc; for production of

    pre-cast reinforced concrete

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    13/29

    113

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    components.

    SAQ 3

    (a) Why concrete is required to be compacted?(b) State the methods of compaction and explain in brief.(c) How you will judge that compaction is proper or not?(d) What should be the duration of compaction? State the factors

    affecting it.

    (e) State the different types of vibrator and their usefulness. Explain anyone of them in brief.

    SAQ 4

    (a) What is vibrator? What is the objective of using vibrators inconcreting operation?

    (b) State the places where different types of vibrator are used.(c) State the precautions to be taken during the use of vibrators.(d)

    Tick the correct answer.(i) Vibrators should be penetrated in (horizontal/vertical) direction.

    (ii) Which type of vibrator is generally used for compaction of

    concrete?

    (1) Needle vibrator

    (2) Form vibrator

    (iii) For compacting thin reinforced concrete slabs following

    vibrator is recommended.

    (1) Immersion vibrator

    (2) Surface vibrator

    (iv) Surface vibrator is effective only when thickness of concrete

    member does not exceed

    (1) 200 mm

    (2) 500 mm

    (v) A surface vibrator for compaction of concrete is preferred for

    (1) Raft footings

    (2) Columns

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    14/29

    114

    Concrete Technology

    6.5 CURING OF CONCRETE

    The process of hardening the concrete mixes by keeping its surface moist for a

    certain period after compaction and finishing is called curing of concrete.

    Curing is one of the important factors for obtaining better strength. The concrete

    hardens because of the chemical reaction between water and cement, i.e.

    hydration. The chemical action that accompanies the setting of concrete is

    dependent on the presence of water. Although there is sufficient water at the time

    of mixing yet it is necessary to ensure that the water is retained to enable the

    chemical action to continue till the concrete is fully hardened. Properties of

    concrete such as strength, durability, wear resistance, water-tightness and volume

    stability improve with the passage of time. Three gallons of water are required

    approximately to hydrate one bag of cement. If the loss due to evaporation is

    more from newly placed concrete, the hydration process will stop and concrete

    will shrink thus creating tensile stresses at the drying surface. The development ofthese stresses will result into the formation of plastic shrinkage cracks.

    6.5.1 Importance of Curing

    The importance of curing of concrete is to improve its properties such as water-

    tightness, wear resistance, strength, volume stability and durability.

    6.5.2 Objects of CuringFollowing are the objects of curing.

    (a) Maintaining the process of hydration by preventing the loss of waterby evaporation.

    (b) To reduce the shrinkage of concrete.(c) To preserve the properties of concrete.

    6.5.3 Methods of CuringDifferent methods of curing are used for maintaining the concrete in a moist

    condition over a period of several days till it hardens and attains full strength. The

    method of curing depends upon the nature of work and atmospheric conditions.

    Following methods are generally used for curing.

    (a) Sprinkling water,(b) Ponding method,(c) Membrane curing,(d) Covering concrete surfaces with gunny bags,(e) Shading concrete works,(f) Chemical curing,(g) Steam curing,(h) Curing of concrete by infrared radiation, and(i) Electrical curing of concrete.

    Sprinkling Water

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    15/29

    115

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    Excellent method of curing is the continuous sprinkling of water. The

    quantity of water required by this method to cure concrete is much more

    than other methods. If water is sprinkled in intervals, then the concrete must

    not be allowed to dry between applications of water. A constant supply of

    water helps in preventing the formation of cracks caused by alternate

    wetting and drying.

    Ponding MethodsPonding method is mainly adopted for surfaces members such as

    pavements, floors, roofs, slabs and sidewalks, etc. In this method, a small

    dam of earth or water retaining material is placed around the perimeter of

    the surface. The surface is firstly covered for 24 hours after placing and

    compacting concrete. The enclosed area is further divided into a number of

    rectangles and is kept flooded with water. Water is filled in the rectangles

    two to three times per day depending upon the climatic conditions.

    Membrane Curing

    Membrane curing is used at the places where there is acute shortage of

    water. In membrane curing a newly laid concrete surface is covered byusing chemical or liquid membranes in order to prevent evaporation of

    moisture from concrete. This method has been found good in maintaining a

    satisfactory state of wetness in the body of concrete to promote continuous

    hydration when original w/c ratio used is not less than 0.5. The membranes

    should be applied immediately after the concrete has been finished. The

    concrete surface should be kept moist till the membrane is applied. Such

    compounds should neither be applied when there is free water on the

    concrete surface nor after the concrete has dried out. The correct time of

    applying membranes that when water film disappears from the surface of

    the finished concrete. Curing membranes are plastic films, bitumen

    emulsions, wax emulsions and waterproof papers, etc. Curing compounds

    should not be applied in between two courses in order to obtain perfect

    bonding. The disadvantage of this method is that concrete loses its strength

    due to less rate of hydration. No supervision is required in this method.

    Covering Concrete Surfaces with Gunny Bags

    The exposed surface of concrete is covered with old empty cement bags or

    hessian, which are kept moist by spraying water frequently. This method is

    widely used for structural concrete. This method can also be applied for

    horizontal and vertical members. The surface should not be allowed to dry

    even for small duration during the period of curing.Shading Concrete Works

    The object of shading is to avoid the evaporation of water from the surface

    of concrete after it is placed and compacted. This method is used to protect

    the newly laid concrete from wind, heat and direct sunrays. In cold weather,

    it prevents the freezing of concrete under frost condition. This process is

    mainly suitable for large surfaces such as road slabs. Using canvas and

    starching them on frames achieve shading over the newly laid concrete.

    Chemical Curing

    Chemical curing is accomplished by spraying the sodium silicate solution.

    About 500 gm sodium silicate mixed with water can cover 1 m2of surface

    and forms a hard and insoluble calcium silicate film. It actually acts as case

    hardener and curing agent. The application of sodium silicate results in a

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    16/29

    116

    Concrete Technology thin varnish like film, which also fill pores and surface voids, thus sealing

    the surface and preventing the evaporation of water.

    Steam Curing

    The hydration of cement accelerates with increase in temperature, which

    leads to faster development and strength.

    To steam curing, the concrete is subjected to higher temperature bymaintaining the required wetness.

    For concrete mixes with water-cement ratio ranging from 0.3 to 0.7, the

    increased rate of strength development can be achieved by resorting to

    steam curing. The mixes with low water-cement ratio respond more

    favorably to steam curing than mixes with higher water-cement ratio. In

    steam curing, the heating of the concrete products is caused by steam either

    at low pressure or high pressure. Steam curing is preferred for precast

    concrete products. These precast members are passed through the steam

    chambers. It is also used, when early removal of formwork is required to

    put the structure in sense without delay.

    Curing of Concrete by Infrared Radiation

    It is claimed that a much more rapid gain of strength can be obtained in this

    method than even with steam curing. The rapid initial rise of temperature

    does not result in a decrease in the ultimate strength as it does in the case of

    steam curing. The system is described as particularly applicable to the

    manufacture of hollow concrete products in which case the heaters are

    placed in the hollow spaces of the product. The normal operating

    temperature is 90C. The curing of concrete by infrared radiation has been

    used in Russia.

    Electrical Curing of Concrete

    This method is not used in India. It is more expensive. It is mostly used in

    very cold climatic regions. Passing alternating current of low voltage can

    cure concrete products and high amperage through electrodes in the form of

    plates covering the entire area of two opposite faces of concrete. The

    potential difference generally adopted is between 30 and 60 V. Evaporation

    is prevented by using an impermeable rubber membrane on the top surface

    of the concrete. Initially up to 3 hours, the resistance of concrete to flow of

    current decreases due to rise in temperature. There is rise in resistance

    afterwards, due to decrease in the quantity of free water available in the

    concrete due to hydration and evaporation. This period of rise intemperature should be about 12 hours. The duration of electrical-curing

    should be about 48 hours at the temperature of 50C or 36 hours at the

    temperature of 70C. The concrete products are cooled gradually in heat-

    insulated chambers for a minimum period of 24 hours. By electrical-curing

    concrete can attain the normal 28 days strength in a period of 3 days.

    6.5.4 Effects of Delayed Curing

    The concrete specimens placed in laboratory air for varying periods after casting,

    before being moist-cured, have indicated that the strength at 7 to 28 days

    decreases progressively as the period of air curing is increased. An exposure for

    3 days to air at a temperature of 23C and having a relative humidity of

    approximately 60% before being moist-cured at 23C has been found to reduce

    the 7 days strength by 12% and the 28 days strength by about 10%. The

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    17/29

    117

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    specimens left in air at 23C for the entire curing period have shown a reduction

    of 25% in the strength at 7 and 28 days as compared with standard moist-curing.

    The reduction under field conditions would probably have been greater. Similar

    adverse curing causes greater relative reduction in strength when Portland blast

    furnace slag cement and the cements blended with fly ash are used.

    6.5.5 Duration for Curing

    As per IS 456 : 1964, the concrete should be cured for at least seven days. The

    strength of concrete increases by 50% than that which is exposed to dry air for the

    entire period. The duration for which concrete should be protected against loss of

    water depends upon cement mass, weather and future exposure conditions. The

    period of curing may be a month or even more for lean concrete mixtures used in

    massive structures such as dams. The curing may extend for few days for richer

    mixes. As all the properties of concrete are improved by curing, therefore, it must

    be as long as practicable in all cases. Concrete must be kept at a temperature that

    is favorable for hydration.

    Table 6.2 : Strength of Cement Concrete with Different Periods of Curing

    Sl. No. Period of Curing Strength in Percentage

    1 1 day 16

    2 3 days 40

    3 7 days 67

    4 28 days 100

    5 3 months 122

    6 year 146

    7 1 year 155

    SAQ 5SAQ 5

    (a) What is curing? State its importance.(b) What are the objectives of curing?(c) Enlist different methods of curing.(d) Write short note on water curing.(e) What is membrane curing?

    SAQ 6

    (a) What is steam curing?(b) How are the following structural elements cured?

    (i) Test block

    (ii) Columns

    (iii) Hume pipe

    (iv) Bridge slab

    (v) Pre-cast products

    (vi) Wall

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    18/29

    118

    Concrete Technology (c) State the effects of delayed curing.(d) Tick the correct answer.

    (i) The following method may be used for the curing of concrete

    (1) Electrical curing

    (2) Mechanical curing

    (ii) The following sealing compounds can be used for the

    membrane curing

    (1) Rubber latex emulsions

    (2) Sodium silicate solution

    6.6 FINISHING OF CONCRETE

    The operations adopted for obtaining a true, uniform concrete surface are called

    as finishing operations.

    Concrete mix should be spread in such a way that no segregation takes place.

    Only designing the mix properly can ensure this. The results of finishing are good

    if the slump is about 5 cm. The choice of concrete finish depends upon the

    ultimate use of the completed job and the desired effect.

    6.6.1 Importance of Finishing

    Finishing is very important from engineering point of view. The importance of

    finishing is to keep the concrete surfaces free from undulations. Many concrete

    structures have an unsatisfactory appearance after exposure for some time. Some

    of the surfaces, which were quite pleasing when new, have weathered badly. The

    surface of concrete cannot be made pleasing to the eye as many unsightly features

    result from cracks, carelessly constructed and badly placed construction joints,

    patching or honey-combed or damaged areas, poor formwork and lack of

    sufficient cover to reinforcement.

    6.6.2 Finishing OperationsFollowing are the operations adopted for finishing of concrete surface.

    (a) Screeding,(b) Floating, and(c) Trowelling.

    Screeding

    The leveling operation that removes humps and hollows and gives a true,

    uniform concrete surface is called screeding.

    The process of screeding is also known as striking off. Straight edge is used

    for screeding. Straight edge is specially prepared and is slightly longer thanthe section being finished. The surface is struck off by moving the straight

    edge back and forth with a saw like motion across the top of the forms.

    The straight edge is advanced forward a short distance with each

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    19/29

    119

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    movement. A small quantity of concrete mix should always be kept ahead

    of the straight edge to fill the voids and maintain a plane surface. Screeds

    may be of vibrator type or roller type. Vibrators can also be fitted on

    screeds.

    Figure 6.6 : Screeding

    Floating

    The process of removing the irregularities from the surface of concrete left

    after screeding is called floating.

    The process of floating is done with the help of wooden float. Floating

    helps in leveling the surface and compacting concrete. The wooden float is

    1.5 m long and 20 cm wide. A handle is fixed in the center. Moving the

    wooden float backward and forward performs finishing. Bull float is used if

    the area of concrete surface is large. It is moved with the help of a handle

    without the operations getting on the concrete surface.

    Figure 6.7 : Floating

    TrowellingThe final operation of finishing is called trowelling.

    Trowelling is performed where a smooth and dense surface is desired.

    Trowelling should be delayed as far as possible. In most of the cases,

    trowelling is performed while the concrete is too soft and plastic. At this

    stage, excessive trowelling will cause crazing and result in a surface having

    less wear resistance. The important point is the period at which the

    trowelling is done and the pressure used by person responsible for the final

    operation of finishing. Finishing is always carried out with the trowel and

    the float. After floating surface should be allowed to dry and stiffen till all

    the excess water has disappeared.

    Trowelling should be done after water has evaporated from the concrete

    surface. Spreading dry cement on a wet concrete surface to absorb excess

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    20/29

    120

    water is not a good practice. The occurrence of such wet surfaces should be

    avoided. The finishing process should be delayed if such spots occur.

    Concrete Technology

    A gap of some time should be left between successive trowellings in order

    to permit concrete to increase its set. Initially, an older trowel is preferred to

    a new trowel. Trowel blade should be kept as flat against the surface as

    possible.

    Power float or power trowels are generally used in finishing large surfacearea such as aircraft hangars or factory floors and is not economical for

    small areas such as flats or dwelling houses. During trowelling, cement

    should not be spread, as it is dangerous and liable to produce a neat cement

    skin, which peels off after some time. Trowelling with power trowels

    should be delayed till the concrete becomes firm.

    Trowelling should be finished on the same day as the laying operation.

    Artificial drying can be very effective by laying cotton sheets on the floor

    and covering them with 2.5 cm to 5 cm of dry cement. The water is

    absorbed by the sheets which can be lifted afterwards say 10 or 15 minutes

    and after this trowelling can proceed for finishing the concrete surface.

    SAQ 7

    (a) What is finishing? How a good finish can be obtained?(b) Explain the necessity of finishing.(c) State the different methods of finishing of concrete.(d) Explain screeding in brief.(e) What is floating? Explain in brief.(f) What is trowelling? What are the precautions to be taken while

    trowelling?

    (g) Tick the correct answer.The final operation of finishing is called ___________________

    (floating/screeding/trowelling ).

    6.7 JOINTS IN CONCRETE CONSTRUCTIONWhen the large concrete members such as factory floors, workshop floors, long

    columns, residential floors, road pavements, air-field pavements, etc. are

    constructed, it is not practicable and advisable to place the concrete continuously

    in one stretch. A joint is left between subsequent concreting stretches and it iscalled as construction joint. Concrete may undergo expansion and contraction due

    to thermal changes, moisture movement, drying shrinkage and due to structural

    reasons. Therefore to make up for the impending expansion or contraction of

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    21/29

    121

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    concrete a proper provision is made in the form of a joint. Such joints are called

    contraction or expansion joints.

    The concrete joints can be classified as follows :

    (a) Construction joints,(b) Expansion joints, and(c) Contraction joints.

    6.7.1 Construction Joints

    Construction joints are the temporary joints provided between subsequent

    concreting operations. The positions of construction joints should be

    predetermined before starting of concreting operations. The joint should be

    horizontal in walls and columns and should be arranged at such a level to

    coincide with the general architectural features so that it does not look odd. In

    columns, the concrete should be filled up to a few inches below the junction of

    beams. The joint should be made at the point of minimum shear in beams and

    slabs. Concrete should be poured in one stretch till construction joint is reached.

    The construction joint must not be provided at the point of maximum bending

    moment in any case. Badly made and poorly finished construction joint will give

    an ugly appearance to the construction therefore it must be properly finished. The

    joints must be made at such places that the concrete comes under least maximum

    bending moment and shear force.

    6.7.2 Expansion Joints

    Concrete is subjected to volume change due to temperature variations, shrinkage,

    etc. Therefore, the provision must be made to cater for the volume change by way

    of joint to relieve the stresses produced. In small buildings, no expansion joint is

    needed in the floor or in the roof because expansion is very small as it is afunction of length. A long building undergoes large expansion. It is estimated that

    for the worst conditions, a long building may undergo an expansion of as much as

    2.5 cm. Therefore, buildings longer than 45 m are generally provided with one or

    more expansion joints. Roof of a long building is affected by maximum

    temperature variations. The roof is subjected to expansion and contraction during

    day and night and causes pushing or pulling to the load bearing walls. Serious

    cracks have been found in the masonry wall supporting the slab. Hence, attempts

    have been made to create a condition for a slab to slide over the wall when it is

    under expansion or contraction. The details such as the length of structure where

    expansion joint is to be provided can be determined after taking into

    consideration many factors such as temperature, exposure to weather, time andseason of the laying of the concrete, etc. Under no circumstances shall a structure

    of 45 m or more be without an expansion joint.

    In the past, expansion joints were provided at closer intervals in the floors and

    pavements. These days from experience, it is seen that concrete does not actually

    expand to the extent indicated by the simple analytical calculations, because of

    the frictional resistance offered by the sub grade. It is, therefore, possible to

    provide expansion joint at a much farther interval than in the past. IS 456 : 1978

    recommends as under.

    In view of the large number of factors involved in deciding the location, spacing

    and nature of expansion joints, the provision of expansion joint in reinforced

    cement concrete structures should be left to the discretion of the reinforced

    cement concrete designer. For purposes of general guidance, however, it is

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    22/29

    122

    recommended that structures exceeding 45 m in length shall be divided by one or

    more expansion joints.

    Concrete Technology

    6.7.3 Contraction Joints

    Concrete is subjected to plastic shrinkage and drying shrinkage due to which

    concrete shrinks. Stresses are developed and cracks are formed when shrinkage is

    restrained. Contraction joints are provided to avoid these cracks. Normally these

    joints are provided at 5 m to 10 m interval. Contraction joints are also called

    dummy joints or control joints. These joints will not be required if a provision is

    made to take up the shrinkage stresses by reinforcement. Hence, contraction

    joints are provided in un-reinforced floors and pavements. Contraction joints are

    made at the time of laying concrete by imbedding a timber plank or batten of

    sufficient depth and required thickness. This is afterwards removed when the

    concrete is hardened. Sometimes, steel plates of required thickness and width are

    forced down into the fresh concrete and then removed when the concrete is

    hardened. Sometimes contraction joints of required width and depth are cut by

    using a joint sawing machine. It is necessary that groove cut should be filled up

    with some joint sealing compound to protect the edges of concrete and also toprevent water from being held. The depth of joint should be about 2 cm. In

    residential flooring, the conventional contraction joint is omitted by casting the

    slab in alternate bays, to allow for the complete plastic shrinkage and also for

    maximum extent of drying shrinkage. It is usual practice to place glass-strip or

    aluminium strip in between the bays to create discontinuity between adjacent

    bays to prevent the development of continuous cracks.

    SAQ 8

    (a) Why joints are essential in concrete construction?(b) What are types of joints in concrete?(c) What is construction joint? Explain in brief.(d) Explain the expansion joint in brief.(e) Explain the purposes of providing contraction joint.(f) What is the method of joining the old concrete to new concrete?

    (Hint :Answer is in Sub-section 6.3.3.)

    6.8 FORMWORK

    The temporary construction used as a mould for the structure, in which the

    concrete is placed and in which it hardens is called as formwork.

    Formwork must be strong enough to withstand the hydrostatic pressure of wet

    concrete. The method of compaction, size and shape of the formwork also affects

    the shutter pressure. Formwork should be tight in order to prevent concrete from

    leaking out. Formwork should be easy to handle so that no time is wasted inassembling and disassembling. Formworks vary both in type and in the method of

    construction. Another type is the sliding type. In this type, an arrangement is

    more to rise the form with the placement of concrete. It is generally used where a

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    23/29

    123

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    good surface finish is required. It has two advantages. Firstly, it enables a high

    speed of construction and secondly, it eliminates the horizontal construction joint.

    6.8.1 Requirements for Formwork

    The following are the requirements for formwork :

    (a) The forms should have sufficient strength to support the loads.(b) The sheeting should be durable and rigid.(c) The sheeting should be thick enough to withstand the pressures of wet

    concrete.

    (d) The components of forms should be large enough to carry the loadsand forces without buckling.

    (e) The formwork should be of reasonable size and weight for easyhandling, transportation and erection.

    (f) The formwork should be easily and speedily erected.(g) The form surface should give a smooth finishing.(h) The joints of the form should be tight enough to prevent any material

    leakage.

    6.8.2 Checking of FormworkThe following points must be checked before placing concrete in the formwork :

    (a) The geometric dimensions of the formwork should be checked.(b) The accuracy of the horizontal surfaces should be controlled by levels

    and vertical surfaces by plum-bobs.

    (c) The sawdust, nails, mud particles, etc. should be removed beforeplacing concrete.

    (d) The alignment of the formwork should not be disturbed duringconcreting operations.

    (e) Oiling should be done in order to prevent sticking of concrete withformwork and to ensure smooth surface of concrete.

    (f) The joints in the formwork should be checked to avoid the leakage ofmaterial.

    (g) The old surface should be wetted before placing the concrete.6.8.3 Materials for FormworkThe following are the materials used for formwork :

    Timber

    The partially seasoned timber is most satisfactory for use of formwork.

    Green timber dries out and shrinks. It causes fins and ridges on the

    concrete. Kiln-dried timber has a tendency to swell when soaked with water

    from concrete. It causes bulging and distortion if the boards are tightly

    joined. Provision for slight swelling should always be made in case of

    seasoned timber.

    SheetingBy using boards 12.5 cm, 15 cm, 17.5 cm, 20 cm, 22.5 cm and 25 cm

    wide, various heights of centering can usually be obtained without

    excessive sawing. Thin sheeting (2.5 cm) is used for the sides of the

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    24/29

    124

    Concrete Technology beams and column boxes. The sheetings of 3.75 cm to 5 cm are used

    for the soffits of beams.

    Joists

    Joists are commonly 15 cm 5 cm but may vary from 10 cm 5 cm

    to 22.5 cm 10 cm according to type of work.

    PostsPosts may be 7.5 cm 10 cm to 12.5 cm 12.5 cm.

    Studs, Wales, Headtrees, Subsidiary Bearer and Transoms

    These may vary from 10 cm 5 cm to about 12.5 cm 12.5 cm.

    Sections about 7.5 cm 5 cm are useful for general bracing and light

    shuttering.

    Steel

    Steel forms can be used for as many number of times as desired and as such

    are economical. Better finish can be achieved by the use of steel forms, as

    they are factory made and fit exactly. Steel forms have the followingadvantages over other types of forms :

    (a) Quality of work is assured.(b) The wastage of material is eliminated.(c) Handling and transportation costs are reduced.(d) It reduces finishing costs.(e) It reduces friction losses.(f) Smaller number of tie rods is required.(g) These are safer than other material.(h) In order to obtain additional usage of the steel forms,

    adjustment of various sizes can easily be incorporated in the

    design of steel forms.

    (i) Collapsing and stripping is a smooth and gradual operationbecause it is usually controlled by jacks, etc.

    6.8.4 Formwork for Walls

    A common arrangement for wall formwork is shown in Figure 6.8. It is held

    together with bolts fitted with sleeve pieces. In this case, the sheathing is placed

    horizontally. It spans between vertical studs under the horizontal pressure due to

    wet concrete. The pressure on either side of the form is self-balanced.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    25/29

    125

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    Figure 6.8 : Formwork for Walls

    6.8.5 Formwork for Columns

    A common arrangement for column formwork is shown in Figure 6.9. The two

    sides are held together by bolts and the two opposite sides by hardwood wedges

    between the bolt and the form. The sheeting runs in vertical direction. It is madeup into panel units. At the head, provision is made for linking with the formwork

    for horizontal beam.

    Figure 6.9 : Formworks for Columns

    6.8.6 Formwork for Beams and Slabs

    The formwork in case of beams is constructed in such a way that the sides may be

    stripped before the soffit. It is so because the soffit must be left in place till the

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    26/29

    126

    Concrete Technology beam can safely support its own weight. The slab formwork is supported by the

    centering to the beam.

    Figure 6.10 : Formwork Supporting a Heavy Beam and Slab

    Figure 6.11 : Posts for Beam Centering

    Figure 6.12 : Beam Centering with Slab Centering

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    27/29

    127

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    Figure 6.13 : Centering for Heavy Beams

    Figure 6.14 : Beam Centering (Alternative Method)

    6.8.7 Faults in Erection of Formwork

    The following are the faults in the erection of the formwork :

    (a) Sheeting is too thin.(b) Bad sheeting joints, which will lead to leakage of concrete.(c) No distance piece is provided.(d) Strut is small and buckles.(e) No wailings are provided.(f) Warped sheeting is used.(g) Cleat is too small. It is cut wrongly.(h) Sole plate is not provided which will cause uneven distribution of

    load to ground.

    (i) Stake section is small and driven to insufficient depth.(j) No strutting at the base of the shutters is provided.

    6.8.8 Removal of FormworkThe suitability of the materials of the formwork for re-use depends in many

    respects on the way removal is done. The shuttering boards, frameworks are

    broken, the smooth surface is damaged and the bracing is bent, if the forms are

    not removed carefully. Therefore, removal of formworks should be carried out ina careful and orderly way. Formwork should not be removed without specific

    instructions from the engineer-in-charge. The engineer-in-charge before issuing

    instructions should make sure that the concrete has attained sufficient strength to

    carry its own load and any other load, which it carries at the top. The sides of the

    formworks, which are not loaded by weight of concrete member, should not be

    removed before the concrete gains strength. The lateral shuttering is usually

    removed in summer within 2 to 3 days. Posts supporting the formworks of load

    bearing structures should be removed only after stripping the sides of the form.

    Load bearing formworks should be removed only after concrete has gained

    strength.The following are the steps for striking the formworks :

    (a) Loosening of the tie wires.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    28/29

    128

    (b) Removing the supports, which support the formworks.Concrete Technology(c) Removing the shuttering boards or panels.

    Under normal circumstances when the temperature is 20oC and the cement used is

    ordinary, the formwork may be stripped after the expiry to the following periods :

    (a) Vertical sides of columns, walls, beams and slabs 1 to 2 days(b) Beam soffits 7 days(c) Bottom of slabs

    (i) Span of 4.5 m 7 days

    (ii) Span of 4.6 m and above, bottom of beams up to

    span of 6 m, bottom of arch ribs up to a span of 6 m. 14 days

    (d) Bottom of beams and arch ribs over 6 m spans 21days

    SAQ 9

    (a) Fill in the blanks

    (i) __________________ are used in heavy wall construction.

    (ii) __________________ dries out and shrinks.

    (iii) ___________________ should be done in order to make the

    surface of formwork smooth.

    (iv) Forms require ___________________ study as they account for

    reasonable percentage of the final cost of concrete.

    (v) In case of sliding type of formwork, it ____________________

    as the concrete is placed.

    (b) State True or False

    (i) Steel supports minimize the finishing costs.

    (ii) Hard woods are difficult and costly to work.(iii) Partially seasoned timber is most satisfactory to use for

    formworks.

    (iv) Sliding type of formwork enables high speed of construction.(v) The forms should be adequately braced.

    (c) What is formwork?

    (d) What are the requirements of formwork?(e) What are the precautions to be taken before placing concrete in

    formwork?

    (f) Enlist the faults in erection of formwork.(g) Discuss the procedure of removal of formwork.(h) Enlist the advantages of steel formwork.

  • 8/13/2019 Transporting, Deposition, Curing and Finishing of Concrete

    29/29

    Transporting,

    Deposition, Curing and

    Finishing of Concrete

    6.9 SUMMARY

    In this unit, you have studied concreting operations like transportation, placement

    or deposition, compaction, curing and finishing of concrete. You also studied

    different joints in concrete construction and formwork. In the next unit, you willstudy special types of concrete and concreting methods under extreme

    environmental conditions.

    6.10 ANSWERS TO SAQs

    Refer the relevant preceding text in the unit or other useful books on the topic

    listed in the section Further Reading given at the end of the booklet to get the

    answers of SAQs.