Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision # RTC Review BOD Approval Date Public Review & Comment 19-1 August 21, 2019 October 14, 2019 August 23, 2019 – October 14, 2019

Upload: others

Post on 03-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 1 of 47

Waccamaw Regional Council of Government

RURAL TRANSPORTATION IMPROVEMENT PROGRAM

TIP PERIOD:

OCTOBER 1, 2019-SEPTEMBER 30, 2022

Revision # RTC Review BOD Approval Date Public Review & Comment 19-1 August 21, 2019 October 14, 2019 August 23, 2019 – October 14, 2019

Page 2: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 2 of 47

REVISION SUMMARIES Revision 1 – Approved by the Board of Directors on October 14, 2019 The minor amendments are necessary to reflect revised funding amounts, funding sources, and timelines as allocated on the TIP as noted below:

o Intersection Improvements that are now funded by non-guideshare money- 3A – US 701 & Jeanette (City of Conway) RIDE III 3H – US 701 & Industrial Park (Horry County) RIDE III 3I – US 701 & Harris Short Cut (Horry County) RIDE III 3J – US 378 & SC-134 (Horry County) SAFETY 3K – SC 9 & Heritage (Town of Loris) RIDE III 3M – US 701 & Fox Bay (Town of Loris) RIDE III

o Incorporate new method for showing projects of the TIP. The method will be implemented with unfunded and newly funded projects. The following projects are also the first to be subject to the new review process (SCDOT Feasibility Study)

Priority Project Description 2020 2021 2022 Future Funding 3L Big Dam Swamp $100 $2,300 3N Main & MLK $60 $640 3O Easler & Holliman & OGR $140 $2,660

o Support the Horry County CTC project with a commitment of $400,000 towards the completion of the intersection project at 501 and Enoch Road.

Page 3: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 3 of 47

Table of Contents

LIST OF ACROMYMS AND TERMS……………………………………….……………….5 RURAL TIP LEGEND………………………………………………………………………….6

WACCAMAW REGIONAL COUNTIL OF GOVERNMENTS ................................................ 7

RURAL PLANNING STRUCTURE ........................................................................................ 8 RURALTIP AMENDMENT PROCESS AND PROCEDURES ................................................. 9

PROJECTS ........................................................................................................................................ 12

ANDREWS BYPASS PHASE 1 ............................................................................................. 13 ANDREWS BYPASS PHASE 2 .................................................................................................. 14

INTERSECTION PROJECTS ....................................................................................................... 15 US 701 & JANETTE .................................................................................................................... 16 US 17A & POWELL .................................................................................................................... 17 SC905 & OLD REAVES FERRY ............................................................................................... 18 SC 9 & SC 905 .............................................................................................................................. 19 SC 41/51 & BROWNS FERRY ................................................................................................... 20 COUNTY LINE & S-16 ............................................................................................................... 21 LONGSTREET & MAIN............................................................................................................. 22 US 701 & INDUSTRIAL PARK ................................................................................................. 23 US 701 & HARRIS SHORT CUT .......................................................................................... 24 US 378 & S-134 ...................................................................................................................... 25 SC 9 & HERITAGE ...................................................................................................................... 26 BIG DAM SWAMP ...................................................................................................................... 27 US 701 & FOX BAY .................................................................................................................... 28 MAIN & MLK .............................................................................................................................. 29 EASLER & HOLLIMAN ............................................................................................................. 30

NON GUIDESHARE PROJECTS ................................................................................................. 31 WIDENING PROJECTS SC HIGHWAY 9 EAST WIDENING ......................................................................................... 32 US HIGHWAY 701 WIDENING ................................................................................................ 33 PAVEMENT GEORGETOWN COUNTY PAVEMENT PRES & RESURF .............................................. 34 HORRY COUNTY PAVEMENT PRES & RESURF ................................................................ 34 WILLIAMSBURG COUNTY PRES & RESURF ...................................................................... 34 FTA/SCDOT GRANTS SECTION 5310 WILLIAMSBURG CO. DSN ........................................................................... 35 SECTION 5316 WILLIAMSBURG CO. DSN ....................................................................... 36 SECTION 5316 WILLIAMSBURG CO. TRANSIT ................................................................... 36 SECTION 5311 WILLIAMSBURG CO. TRANSIT .................................................................. 37

Page 4: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 4 of 47

SECTION 5339 WILLIAMSBURG CO. TRANSIT .................................................................. 38 SECTION 5310 GRACE MINISTRIES (NEIGHBOR 2 NEIGHBOR) .................................... 35 SECTION 5310 GEORGETOWN COUNTY GOV ............................................................... 35 SECTION 5310 GEORGETOWN CO. DSN .......................................................................... 35 SCDPT BRIDGE AND INTERSECTION GREENHOUSE RD & TODD RD .............................................................................................. 39 PALMETTO SWAMP BRIDGE ............................................................................................ 40 US ALT 17 OVER SAMPIT RIVER ........................................................................................... 41 SC HIGHWAY 9 & SC 410 GREEN SEA HIGHWAY ............................................................ 42

HORRY COUNTY CTC PROJECT ............................................................................................. 43 US 501 & ENOCH RD

SOUTH CAROLINA FINANCIAL SUMMARY ........................................................................... 44

Page 5: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 5 of 47

LIST OF ACRONYMS and TERMS

ARRA American Reinvestment and Recovery Act CAP Capital CONST Construction FAST Act Fixing America’s Surface Transportation Act FTA Federal Transit Administration GSATS Grand Strand Area Transportation Study NHS National Highway System OP Operating PE Preliminary Engineering PPP Public Participation Plan RIDE Road Improvement Development Effort RLRTP Rural Long Range Transportation Plan ROW Right – of – Way RPO Rural Planning Organization RTC Rural Technical Committee SAFETEA – LU Safe Accountable Flexible Efficient Transportation Equity Act: Legacy for Users SCDOT South Carolina Department of Transportation STIP Statewide Transportation Improvement Plan STP Surface Transportation Program TIP Transportation Improvement Program UW Underway

Page 6: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 6 of 47

WRCOG Waccamaw Regional Council of Governments

RURAL TIP LEGEND

Unidentified Funding Source

Multiple Funding Sources

Federal Transit Administration

Federal Highway Administration

Page 7: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 7 of 47

WACCAMAW REGIONAL COUNCIL OF GOVERNMENTS RURAL TRANSPORTATION IMPROVEMENT PROGRAM

Waccamaw Regional Council of Governments (WRCOG) is the designated Rural Planning Organization (RPO) responsible for carrying out the rural transportation planning process for the Waccamaw region. The WRCOG rural study area boundary includes the western portions of Horry and Georgetown counties, and the entirety of Williamsburg County. More specifically, the rural area includes all portions of the three counties that are not included in the MPO region (See map below). Several municipalities lay within the boundaries, including: Andrews, Aynor, Conway (partially), Greeleyville, Hemingway, Kingstree, Lane, Loris, and Stuckey.

The primary responsibilities concerning rural area planning are to:

• Develop a Rural Long Range Transportation Plan (LRTP), which is the 25 year transportation vision for the rural area;

• Develop a Rural Transportation Improvement Plan (TIP), which is the list of specific projects for which federal and state funds are anticipated; and

• Develop a Rural Planning Work Program (RPWP), which identifies the annual transportation planning activities that are to be undertaken in support of the goals and objectives established in the Long Range Transportation Plan.

As the RPO, WRCOG provides the forum for cooperative decision making regional transportation plans and programs to meet the changing needs. It is composed of elected and appointed officials representing local, state, and federal governments or agencies having interest or responsibility in comprehensive transportation planning.

Page 8: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 8 of 47

RURAL PLANNING STRUCTURE

To facilitate and encourage maximum interaction among these groups and the local community, WRCOG has an adopted committee structure. The Policy Committee (WRCOG Board of Directors), as the official decision making body, establishes the policies for the overall conduct of WRCOG and is responsible for the adoption of plans and programs and reviews the rural technical committees’ recommendations.

The Technical Committee, which was established by the Policy Committee, is composed of the professional/technical representatives of the municipalities and agencies that lie within the region. These member governments and public agencies often have direct or indirect responsibilities for transportation planning and/or implementation procedures. Their primary responsibility is to monitor all technical activities including the annual development of a draft RPWP and biennial development of a draft TIP. They also provide recommendations to the Policy Committee for final endorsement of all major studies and planning activities affecting the rural areas.

Rural Long Range Transportation Plan

The Rural Long Range Transportation Plan was adopted by the Rural Policy Committee (WRCOG Board of Directors) in 2016 and must be updated every five years to reflect changing conditions and new planning principles. The Rural LRTP document established goals and objectives, which form the basis for the initial evaluation of projects submitted for the Rural TIP. The process of undertaking major transportation studies, identifying short and long-range needs, and targeting major growth areas in the rural region for intensive study has strengthened programming methods and procedures for the Rural TIP. The entire planning/programming/implementation process involves input by federal, state and local governments and the public in the early planning stages. This support carries through into TIP programming. The Rural LRTP will be updated in 2021.

Rural Transportation Improvement Program (TIP)

This Rural TIP is a three-year program of transportation capital projects together with a three-year estimate of transit capital and maintenance requirements. While the Rural TIP is usually approved biennially, the document may be amended throughout the year. The Fast Act mandates that a TIP include the following:

• Identify transportation improvement projects recommended for advancement during the program years. The projects required are those located within the study area and receiving Federal Highway Administration (FHWA) or Federal Transit Administration (FTA) funds;

• Identify the criteria and process for prioritization for inclusion of projects in the TIP and any changes from past TIPs;

• Group improvements of similar urgency and anticipated staging into appropriate staging periods;

• Include realistic estimates of total costs and revenue for the program period;

• Include a discussion of how improvements recommended from the LRTP were merged into the TIP; and

Page 9: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 9 of 47

• List major projects from the previous TIPs that were implemented and identify major delays in planned implementation.

The TIP may also include regional highway projects that are being implemented by the state, city and county for which federal funding is requested.

Relationship of the TIP to Other Federal and State Transportation Programs

Just as federal regulations require each rural planning organization to develop a Rural TIP, each state is required to develop a Statewide Transportation Improvement Program (STIP). The STIP includes all federally funded transportation projects throughout the state. In South Carolina, TIPs are included in the STIP without modification once approved by the relevant rural planning organization. Projects must be in the STIP before funding authorities such as FTA, FHWA, or the SCDOT can obligate funds.

RURAL TIP AMENDMENT PROCESS AND PROCEDURES

Occasionally circumstances dictate that changes are made to the Rural TIP following its biennial adoption. Federal regulations permit changes to the Rural TIP if the procedures are consistent with federal requirements for TIP development and approval. These changes, or amendments, are not routine. WRCOG will consider such amendments when the circumstances prompting such changes are compelling.

Proposed changes will be reviewed by WRCOG staff before any actions are considered. All changes must follow WRCOG policies on the Public Involvement Process. Changes must be consistent with the Rural LRTP, must maintain the financial constraint of the Rural TIP, and must be consistent with federal Title VI requirements. Proposed additions or changes to projects must also be consistent with the rules of the particular funding program involved.

Once new projects proposed for funding are identified, and the funding is committed, staff initiates the process to amend the projects and project funding in the Rural TIP. All rules for amending the new projects in the Rural TIP are followed (Public Participation Process, Title VI requirements, LRTP consistency, financial constraints, etc.).

When WRCOG is not involved in the programming decision associated with a project, staff relies on project sponsors to initiate a TIP amendment. If WRCOG is aware of new funding (i.e. federal earmarks, one-time state funding programs, etc.), staff may alert sponsors of the funding opportunities and request that an amendment be initiated that more fully documents the project scope and funding commitment. Generally, however, it is up to the project sponsor to initiate an amendment request or add new funding, or make necessary adjustments to the project scope, cost, and/or schedule.

All regionally significant transportation projects and all transportation projects requiring a federal action must be included in the Rural TIP. These projects may be added to the Rural TIP at any time, as long as procedures for doing so are consistent with federal requirements for Rural TIP development and approval.

Page 10: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 10 of 47

Types of TIP Amendments

Federal and State policies distinguish between two types of TIP amendments: minor amendments and major amendments. These types of amendments differ based on the magnitude of the proposed change and the level of review required by various federal, state and local agencies. As a general rule, significant changes to the cost, scope, and schedule of a project listing requires a major amendment, whereas minor changes such as fluid sources, description, lead agency, project limits, may be processed through minor amendments. Major Amendments must be approved by the Policy Committee, the SCDOT, FHWA, and FTA. Approval of minor amendments has been delegated to WRCOG Transportation Planning and the SCDOT Office of Planning. Regardless of the type of change, all modifications must be consistent with the LRTP, must maintain the financial constraint of the Rural TIP, and must be consistent with federal requirements.

Minor Amendments

Minor amendments are changes that revise project descriptions and funding sources. Other types of changes that can be made through a minor amendment are changes to a project’s lead agency, changes that split or combine more than one project, and changes to require information for grouped project listings. They take about 30 days to process and need to be approved by the WRCOG Transportation Planning Director and the SCDOT Office of Statewide Planning.

The following changes may be made through a minor amendment, as long as the change occurs within the approved timeframe of the TIP:

• Change in project sponsor or implementing agency; • Splitting or combining projects; • Change or clarification of project description- as long as the change does not significantly alter

the original project intent as identified through the environmental process. Changes in project limits must be within 10% of the total project length, not to exceed a total of two miles;

• Redirection of funds between existing phases, as long as a phase is not added or deleted; and • Federal public involvement procedures are not necessary for a minor change.

Federal public participation procedures required by 23 CFR 450.316 are not necessary for minor changes.

Major Amendment

Major amendments are changes other than minor amendments as described. Major amendments usually take about 90 days to process and need to be approved by the WRCOG Board of Directors, SCDOT, FHWA, and FTA. Adding or deleting a project or a change in funding is considered a major amendment.

Proposed amendments to the Rural TIP, other than minor amendments, must be developed pursuant to all federal guidelines. In general terms, these regulations state the Rural TIP may be modified at any time consistent with the procedures agreed to by the cooperating parties for developing the Rural TIP and all

Page 11: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 11 of 47

other federal requirements concerning the development, public involvement, and federal agencies approval of the Rural TIP.

The interagency consultation or coordination requirements will be followed for all major amendments to the Rural TIP. In some instances, it may be necessary to perform the air quality conformity analysis to evaluate impacts to the Rural TIP prior to approval of an amendment.

All changes that do not fall within the category of a minor amendment are processed as major amendments. The following changes are examples of changes made through a major amendment:

• Adding or deleting project(s); • Funding changes; • Adding or deleting a project phase; and • Significant changes in project scope, so as to alter the original intent of the project.

These amendment classifications and procedures are consistent with the statewide Rural TIP Guidelines SCDOT, FHWA, FTA. It is intended that WRCOG Rural TIP Amendment Process and Procedures adhere to the provisions of the Statewide Rural TIP Guidelines.

Rural TIP Amendment Request Submittal

To request a Rural TIP amendment, a project sponsor must submit an amendment proposal, requesting to amend the Rural TIP. WRCOG programming staff will review the submitted request for compliance with federal regulations, state statues and regional policies, including funding completeness, impacts to air quality, financial constraint, and compliance with other federal, state, and regional requirements before approving the submitted application or amendment. If the proposal is found not to conform to the funding program guidelines or is inconsistent with the financial constraint of the Rural TIP, the proposal may not be processed.

Proposed additions or changes to projects contained in the Rural TIP must also conform to the amendment rules of the funding program involved (i.e. if the project is funded with guideshare funds, it must also conform to the federal and state amendment guidelines before it can be processed).

Page 12: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 12 of 47

PROJECTS

1 ANDREWS BYPASS PHASE I 2 ANDREWS BYPASS PHASE II

Page 13: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 13 of 47

Project Name Andrews Bypass Phase I

Priority# 1 Funding Legend Route or State Road# US Hwy 521

Length (mi/km) 1.1mi Unidentified Funding Source Jurisdiction Georgetown Co. Multiple Funding Source Functional Class Principal Arterial Federal Transit Administration Total Cost $8,944,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Bonded Amount Remaining $3,171,000 $681,000 $597,000 $597,000 $439,000 $439,000

Programmed and Planned Improvements

TIP Project Description

US Highway 521 Andrews Bypass Phase I is complete. The project opened to traffic in late 2005. The remaining bond will be paid through FY 2023.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 14: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 14 of 47

Project Name

Andrews Bypass Phase 2

Priority# 2 Funding Legend Route or State Road# US Hwy 521

Length (mi/km) 2.5 mi Unidentified Funding Source Jurisdiction Georgetown Co. Multiple Funding Source Functional Class Principal Arterial Federal Transit Administration Total Cost $44,276,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Bonded Amount Remaining $2,000,000 $1,000,000 $10,900,000 $12,000,000

Programmed and Planned Improvements

TIP Project Description

US Highway 521 Andrews Bypass Phase 2 is currently in environmental review. The remaining bond will be paid through FY 2027.

Program Type

SYSTEM UPGRADE

Remarks This project is funded under the WRCOG’s guideshare program. The remaining bond will be paid through 2027 as follows: FY2024 ($12,000,000) FY2025 ($24,000,000) FY2026 ($3,188,000), FY2027 ($3,188,000)

Page 15: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 15 of 47

INTERSECTION IMPROVEMENT PROJECTS

3A US 701 & JANETTE - CONWAY 3B US 17A & POWELL – GEORGETOWN COUNTY 3C SC 905 & OLD REAVES FERRY - CONWAY 3D SC 9 & SC 905 – HORRY COUNTY 3E SC 41/51 & BROWNS FERRY – GEORGETOWN/WILLIAMSBURG COUNTIES 3F COUNTY LINE & S-16 - ANDREWS 3G LONGSTREET & MAIN - KINGSTREE 3H US 701 & INDUSTRIAL PARK – HORRY COUNTY 3I US 701 & HARRIS SHORT CUT – HORRY COUNTY 3J US 378 & S-134 – HORRY COUNTY 3K SC 9 & HERITAGE - LORIS 3L BIG DAM SWAMP – GEORGETOWN COUNTY 3M US 701 & FOX BAY - LORIS 3N MAIN & MLK - KINGSTREE 3O EASLER & HOLLIMAN & OGR - GREELEYVILLE

Page 16: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 16 of 47

Project Name US 701 & Janette St.

Priority# 3A Funding Legend Route or State Road# US Hwy 701

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Conway. Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $150,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $100,000 ROW $50,000 Construction Total $100,000 $50,000 0

Programmed and Planned Improvements

TIP Project Description

New signal addition, add right turn lane on Janette St, planted median, raised planted median on US Hwy 701.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program. The remaining balance will be funded by RIDE III.

Page 17: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 17 of 47

Project Name US 17A & Powell Rd.

Priority# 3B Funding Legend Route or State Road# US Hwy 17Alt

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Georgetown Co. Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $1,700,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $150,000 ROW $300,000 Construction $1,250,000 Total $150,000 $300,000 $1,250,000

Programmed and Planned Improvements

TIP Project Description

Realign Powell Rd. with US 17 Alt and provide left turn lane on US 17 Alt.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 18: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 18 of 47

Project Name SC 905 & Old Reeves Ferry

Priority# 3C Funding Legend Route or State Road# SC Hwy 905

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Conway Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $1,692,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $100,000 ROW $342,000 $1,250,000 Construction Total $100,000 $342,000 $1,250,000

Programmed and Planned Improvements

TIP Project Description

Realign Old Reaves highway with SC 905 and provide left turn lane on SC 905 and improve geometry.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 19: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 19 of 47

Project Name SC 9 & SC 905

Priority# 3D Funding Legend Route or State Road# SC Hwy 9 & 905

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry Co. Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $1,517,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $100,000 ROW $217,000 Construction $1,200,000 Total $100,000 $217,000 $1,200,000

Programmed and Planned Improvements

TIP Project Description

Construct offset left turn lanes on SC 9. Construct left turn lanes on SC 905.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 20: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 20 of 47

Project Name SC 41/51 & Browns Ferry

Priority# 3E Funding Legend Route or State Road# SC Hwy 41/51

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Gtown/Wburg Co. Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $2,861,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $150,000 ROW $200,000 Construction $2,511,000 Total $150,000 $200,000 $2,511,000

Programmed and Planned Improvements

TIP Project Description

Install left turn lane on US 41/51 and realign S-45-24 if necessary.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 21: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 21 of 47

Project Name County Line & S-16

Priority# 3F Funding Legend Route or State Road# SC Hwy 41

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Andrews Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $150,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $150,000 ROW Construction Total $150,000

Programmed and Planned Improvements

TIP Project Description

This project was removed. The project was not justifiable due to low traffic counts.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program.

Page 22: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 22 of 47

Project Name Longstreet & Main St.

Priority# 3G Funding Legend Route or State Road# SC Hwy 527/261

Length (mi/km) Unidentified Funding Source Jurisdiction Kingstree Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $393,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 PE $100,000 ROW $30,000 Construction $263,000 Total $100,000 $30,000 $263,000

Programmed and Planned Improvements

TIP Project Description

Expand turning radius, install pedestrian refuge islands, textured crosswalks and pedestrian countdown signals.

Program Type

SYSTEM UPGRADE

Remarks This project was funded under the WRCOG’s guideshare program. Construction of the project is complete pending SCDOT Release.

Page 23: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 23 of 47

Project Name US 701 & Industrial Park

Priority# 3H Funding Legend Route or State Road# US Hwy 701

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry Co. Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $0 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 PE $150,000 ROW $50,000 Construction $550,000 Total $150,000 $50,000 $550,000

Programmed and Planned Improvements

TIP Project Description

Construct left turn lane on US 701.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED BY RIDE III. NO GUIDESHARE MONEY WILL BE USED FOR THIS PROJECT.

Page 24: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 24 of 47

Project Name US 701 & Harris Short Cut

Priority# 3I Funding Legend Route or State Road# US Hwy 701

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry Co. Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $0 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 PE $150,000 ROW $50,000 Construction $530,000 Total $150,000 $50,000 $530,000

Programmed and Planned Improvements

TIP Project Description

Construct left turn on US 701.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED BY RIDE III. NO GUIDESHARE MONEY WILL BE USED FOR THIS PROJECT.

Page 25: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 25 of 47

Project Name US 378 & S-134

Priority# 3J Funding Legend Route or State Road# US Hwy 378

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry Co. Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $0 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 PE $100,000 ROW $50,000 Construction $420,000 Total $100,000 $50,000 $420,000

Programmed and Planned Improvements

TIP Project Description

Install left turn lanes on US 378 and on S-134.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT IS AN SCDOT A SAFETY PROJECT. NO GUIDESHARE MONEY WILL BE USED FOR THIS PROJECT.

Page 26: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 26 of 47

Project Name SC 9 Business & Heritage Rd.

Priority# 3K Funding Legend Route or State Road# SC Hwy 9

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Loris Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $0 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 PE $100,000 ROW $75,000 Construction $200,000 Total $100,000 $75,000 $200,000

Programmed and Planned Improvements

TIP Project Description

Install left turn extension on SC 9 Business onto Perrin Road. Fix offset of roadway on Heritage Road.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED BY RIDE III. NO GUIDESHARE MONEY WILL BE USED FOR THIS PROJECT.

Page 27: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 27 of 47

Project Name SC 41 & Big Dam Swamp Dr.

Priority# 3L Funding Legend Route or State Road# SC Hwy 41

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Georgetown Co. Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $2,400,000 Federal Highway Administration

Estimated Unobligated Cost

FY 2019 FY 2020 FY 2021 FY 2022 FUTURE PLANNING $100,000 ROW Construction Total $100,000 $2,300,000

Programmed and Planned Improvements

TIP Project Description

Replacement project by Georgetown County for US 701 & Pringle Ferry. Realign the intersection.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED UNDER THE WRCOG’S GUIDESHARE PROGRAM..

Page 28: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 28 of 47

Project Name US 701 & Fox Bay

Priority# 3M Funding Legend Route or State Road# US Hwy 701

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Loris Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $0 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 PE $100,000 ROW $50,000 Construction $500,000 Total $100,000 $50,000 $500,000

Programmed and Planned Improvements

TIP Project Description

Install left turn lanes on Fox Bay Road and US 701.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED BY RIDE III. NO GUIDESHARE MONEY WILL BE USED FOR THIS PROJECT.

Page 29: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 29 of 47

Project Name Main St. & MLK

Priority# 3N Funding Legend Route or State Road# SC Hwy 261/377

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Kingstree Multiple Funding Source Functional Class Major Collector Federal Transit Administration Total Cost $700,00 Federal Highway Administration

Estimated Unobligated Cost

FY 2019 FY 2020 FY 2021 FY 2022 FUTURE PLANNING $60,000 ROW Construction Total $60,000 $640,000

Programmed and Planned Improvements

TIP Project Description

Expand turning radius, pedestrian refuge islands, textured crosswalks and pedestrian countdown signals.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED UNDER THE WRCOG’S GUIDESHARE PROGRAM..

Page 30: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 30 of 47

Project Name Easler Rd. & Holliman Rd & Old

Greeleyville Rd.

Priority# 3O Funding Legend Route or State Road# S-45-593

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Greeleyville Multiple Funding Source Functional Class Minor Collector Federal Transit Administration Total Cost $2,800,000 Federal Highway Administration

Estimated Unobligated Cost

FY 2019 FY 2020 FY 2021 FY 2022 FUTURE PLANNING $140,000 ROW Construction Total $140,000 $2,660,000

Programmed and Planned Improvements

TIP Project Description

Realignment of intersection or roundabout.

Program Type

SYSTEM UPGRADE

Remarks THIS PROJECT WILL BE FUNDED UNDER THE WRCOG’S GUIDESHARE PROGRAM.

Page 31: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 31 of 47

NON GUIDESHARE FUNDED PROJECTS Widening Projects 4 SC HIGHWAY 9 EAST WIDENING 5 US HIGHWAY 701 WIDENING – NORTH OF LORIS SCDOT Pavement Pres & Resurf Projects 6 GEORGETOWN COUNTY 7 HORRY COUNTY 8 WILLIAMSBURG FTA Grants 9 SECTION 5310 WILLIAMSBURG CO. 10 SECTION 5316 WILLIAMSBURG CO. 11 SECTION 5316 WILLIAMSBURG CO. 12 SECTION 5311 WILLIAMSBURG CO. 13 SECTION 5339 WILLIAMSBURG CO. 14 SECTION 5310 GRACE MINISTRIES (NEIGHBOR 2 NEIGHBOR) 15 SECTION 5310 GEORGETOWN CO. GOV. 16 SECTION 5310 GEORGETOWN CO. DSN SCDOT Bridge and Intersection Projects 17 GREENHOUSE RD. & TOADD RD. 18 PALMETTO SWAMP BRIDGE 19 US 17 ALT OVER SAMPIT RIVER 20 SC HIGHWAY 9 & SC 410 GREEN SEA HIGHWAY

HORRY COUTY CTC PROJECT

21 US 501 & ENOCH RD.

Page 32: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 32 of 47

Project Name SC 9 East Widening

Priority# 4 Funding Legend Route or State Road# SC Highway 9

Length (mi/km) 1.2 Miles Unidentified Funding Source Jurisdiction Horry County Multiple Funding Source Functional Class Federal Transit Administration Total Cost $21,700,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE $1,500,000 ROW $4,000,000 Construction $16,200,000 Total $1,500,000 $4,000,000 $16,200,000

Programmed and Planned Improvements

TIP Project Description

Road widening project on SC 9 in Loris.

Program Type

SYSTEM UPGRADE

Remarks This project is funded by Horry Sales Tax

Page 33: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 33 of 47

Project Name US Highway 701 –North of Loris

Priority# 5 Funding Legend Route or State Road# US HWY 701

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry County Multiple Funding Source Functional Class Federal Transit Administration Total Cost $7,500,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE $1,000,000 ROW $1,500,000 Construction $5,000,000 Total $1,000,000 $1,500,000 $5,000,000

Programmed and Planned Improvements

TIP Project Description

Road widening project on US Highway 701, north of the Town of Loris

Program Type

SYSTEM UPGRADE

Remarks This project is funded by Horry Sales Tax

Page 34: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 34 of 47

Project Name Pavement Pres & Resurfacing

Priority# 6,7,8 Funding Legend Route or State Road# n/a

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Rural Multiple Funding Source Functional Class n/a Federal Transit Administration Total Cost $19,602,000 Federal Highway Administration

Estimated Unobligated Cost

Agency FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Georgetown County $1,885,000 $1,885,000 Horry County $6,389,000 $6,389,000 Williamsburg County $1,527,000 $1,527,000 Total $9,801,000 $9,801,000

Programmed and Planned Improvements

TIP Project Description

SCDOT Paving projects

Program Type Pavement Resurfacing

Remarks These projects are funded by non guideshare funds

Page 35: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 35 of 47

Project Name 5310

Priority# 9,14,15,16 Funding Legend Route or State Road# n/a

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Rural Multiple Funding Source Functional Class n/a Federal Transit Administration Total Cost $348,000 Federal Highway Administration

Estimated Unobligated Cost

Agency TYPE FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Williamsburg Co. DSN Capital (V) $63,000 $75,000 Grace Ministries Capital (M) $50,000 Georgetown Co. Gov $60,000 Georgetown Co. DSN Capital (V) $44,000 $56,000 Total $157,000 $191,000

Programmed and Planned Improvements

TIP Project Description

SCDOT OPT apportions funds for Elderly Individuals and Individuals with Disabilities to designated recipients in the rural areas. Public transportation capital projects are planned, designed, and carried out to meet the special needs of seniors and individuals with disabilities when public transportation is insufficient or unavailable. (E)=Service Expansion, (V)= Vehicle Purchase (C)=Capital Cost of Contracting, and (M)=Mobility Management

Program Type SCDOT Elderly Individuals and Individuals with Disabilities Program (5310).

Remarks This Policy Committee (WRCOG Board) recommends a prioritized list of ranked applications reviewed by Rural Transportation staff.

Page 36: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 36 of 47

Project Name 5316

Priority# 10,11 Funding Legend Route or State Road# n/a

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Rural Multiple Funding Source Functional Class n/a Federal Transit Administration Total Cost $358,000 Federal Highway Administration

Estimated Unobligated Cost

Agency FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Williamsburg Co. DSN $38,000 Williamsburg Co. Transit $320,000 Total $358,000

Programmed and Planned Improvements

TIP Project Description

Job Access and Reverse Commute (JARC) program was established to address the unique transportation challenges faced by welfare recipients and low-income persons seeking to obtain and maintain employment. Many new entry-level jobs are located in suburban areas, and low-income individuals have difficulty accessing these jobs from their inner city, urban, or rural neighborhoods.

Program Type Capital, planning and operating

Remarks

This program is repealed. Job Access and Reverse Commute activities are eligible for funding under FTA's Urbanized Area Formula Grants (Section 5307) and the Formula Grants for Rural Areas (Section 5311) programs.

Page 37: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 37 of 47

Project Name 5311

Priority# 12 Funding Legend Route or State Road# n/a

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Rural Multiple Funding Source Functional Class n/a Federal Transit Administration Total Cost $9,699,000 Federal Highway Administration

Estimated Unobligated Cost

Agency FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Williamsburg Co. Transit $2,096,000 $1,309,000 $2,097,000 $2,098,000 $2,099,000

Programmed and Planned Improvements

TIP Project Description

The 5311 Formula Grants for Rural Areas program provides capital, planning, and operating assistance to states to support public transportation in rural areas with populations of less than 50,000, where many residents often rely on public transit to reach their destinations. The program also provides funding for state and national training and technical assistance through the Rural Transportation Assistance Program.

Program Type Planning, capital, operating, job access and reverse commute projects, and the acquisition of public transportation services.

Remarks This Policy Committee (WRCOG Board) recommends a prioritized list of ranked applications reviewed by Rural Transportation staff.

Page 38: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 38 of 47

Project Name 5339

Priority# 13 Funding Legend Route or State Road# n/a

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Rural Multiple Funding Source Functional Class n/a Federal Transit Administration Total Cost $514,000 Federal Highway Administration

Estimated Unobligated Cost

Agency FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Williamsburg Co. Transit $514,000

Programmed and Planned Improvements

TIP Project Description

Section 5339 Provides funding to states and transit agencies through a statutory formula to replace, rehabilitate and purchase buses and related equipment and to construct bus-related facilities.

Program Type

Capital projects to replace, rehabilitate and purchase buses, vans, and related equipment, and to construct bus-related facilities, including technological changes or innovations to modify low or no emission vehicles or facilities.

Remarks Subrecipients may be awarded through a designated recipient

Page 39: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 39 of 47

Project Name Greenhouse Rd/Todd Rd

Priority# 17 Funding Legend Route or State Road# Greenhouse Rd

Length (mi/km) n/a Unidentified Funding Source Jurisdiction County Multiple Funding Source Functional Class Federal Transit Administration Total Cost $605,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE ROW Construction Total $605,000

Programmed and Planned Improvements

TIP Project Description

The Corridor improvement project on Greenhouse Road/Todd Road in Kingstree

Program Type

SYSTEM UPGRADE

Remarks This project is an SCDOT Safety Improvement Project

Page 40: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 40 of 47

Project Name Palmetto Swamp Bridge

Priority# 18 Funding Legend Route or State Road# Brunson Spring Road

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry County Multiple Funding Source Functional Class Bridge Federal Transit Administration Total Cost $3,167,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE $700,000 ROW $50,000 Construction $2,417,000 Total $700,000 $50,000 $2,417,000

Programmed and Planned Improvements

TIP Project Description

Bridge replacement of bridge on S-97 (Brunson Spring Road) over Palmetto Swamp

Program Type

SYSTEM UPGRADE

Remarks This project is funded by State Gas Tax

Page 41: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 41 of 47

Project Name US 17 ALT over Sampit River

Priority# 19 Funding Legend Route or State Road# US 17 ALT

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Georgetown County Multiple Funding Source Functional Class Bridge Federal Transit Administration Total Cost $6,126,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE $700,000

(FY15) ROW $100,000

(FY17) Construction $5,325,000 Total $800,000 $5,326,000

Programmed and Planned Improvements

TIP Project Description

Bridge replacement of bridge on ALT 17 over Sampit River

Program Type

SYSTEM UPGRADE

Remarks This project is funded by FAST Act Non-National Highway System/Surface Transportation Block Grant Program (STBGP)

Page 42: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 42 of 47

Project Name SC 9 & SC 410 (Green Sea Hwy)

Priority# 20 Funding Legend Route or State Road# SC 9 & SC 410

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry County Multiple Funding Source Functional Class Intersection Federal Transit Administration Total Cost $1,450,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE $200,000 ROW $50,000 Construction $1,200,000 Total $200,000 $50,000 $1,200,000

Programmed and Planned Improvements

TIP Project Description

Intersection project at SC 9 & SC 410 (Green Sea Hwy)

Program Type

SYSTEM UPGRADE

Remarks This project is funded by SCDOT Safety Improvement

Page 43: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 43 of 47

Project Name US 501 & Enoch Rd. Horry County CTC

Priority# 21 Funding Legend Route or State Road# US 501

Length (mi/km) n/a Unidentified Funding Source Jurisdiction Horry County Multiple Funding Source Functional Class Intersection Federal Transit Administration Total Cost $400,000 Federal Highway Administration

Estimated Unobligated Cost

Prior Yrs FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 PE ROW Construction Total $400,000

Programmed and Planned Improvements

TIP Project Description

Horry County CTC project identified at US 501 & Enoch Rd.

Program Type

SYSTEM UPGRADE

Remarks Horry County CTC has submitted a request to the RTC in the amount of $400,000 to help fund this project. The request will be funded under the WRCOG’s guideshare program.

Page 44: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 44 of 47

FINANCIAL SUMMARY

Page 45: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

Page 45 of 47

PRIORITY PROJECT DESCRIPTION 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031FUTUR

E $TOTAL 10 - 31

1 ANDREWS BYPASS PHASE 1 * 681 731 384 690 685 681 597 597 439 439 8,9442 ANDREWS BYPASS PHASE 2 2,000 1,000 >>>>>> >>>>>> 10,900 12,000 12,000 24,000 3,188 3,188 44,2763 INTERSECTION IMPROVEMENTS 850 247 905 2,650 3,811 0 700 0 0 9,163

3A US 701& Janette - Conway® 100 >>>>>> >>>>>> 0 50 0 150 1503B US 17A & Powell - Georgetown Co. 150 >>>>>> 300 >>>>>> 1,250 1,700 1,8503C SC 905 & Old Reaves Ferry - Conway 100 0 342 1,250 1,692 3,5423D SC 9 & SC 905 - Horry Co. 100 217 >>>>>> 1,200 1,517 5,0593E SC 41/51 & Browns Ferry - Gtown/Wmb 150 >>>>>> >>>>>> 200 2,511 2,861 7,9203F County Line & S-16 - Andrews 150 >>>>>> 150 8,0703G Longstreet & Main - Kingstree 100 30 263 393 8,4633H US 701 & Industrial Park - Horry Co. ® 0 8,4633I US 701 & Harris Short Cut _ Horry Co. ® 0 8,4633J US 378 & S-134 - Horry Co. (S) 0 8,4633K SC 9 & Heritage - Loris® 0 8,4633L Big Dam Swamp - Georgetown Co. 0 100 0 0 2,300 2,400 10,863

3M US 701 & Fox Bay - Loris® 270 115 695 200 1,500 0 10,8633N Main & MLK - Kingstree 0 60 0 0 640 700 11,5633O Easler & Holliman & OGR - Greeleyville 0 140 0 0 2,660 2,800 14,363

4 SC Highway 9 East Widening 1,500 >>>>>> 4,000 16,200 21,7005 US Highway 701 Widening-North of Loris 1,000 1,500 >>>>>> 5,000 7,5006 G'TWN PAVEMENT PRES & RESURF 1,885 1,885 3,7707 HORRY PAVEMENT PRES & RESURF 6,389 6,389 12,7788 WIL'BURG PAVEMENT PRES & RESURF 1,527 1,527 3,0549 WIL'BURG CO. DSN 5310 63 75 13810 WIL'BURG CO. DSN 5316 38 3811 WIL'BURG CO. TRANSIT 5316 320 32012 WIL'BURG CO. TRANSIT 5311 2,096 1,309 2,097 2,098 2,099 9,69913 WIL'BURG CO. TRANSIT 5339 514 51414 GRACE MINISTRIES 5310 50 5015 GEORGETOWN CO. GOVERNMENT 5310 60 6016 GEORGETOWN CO. DSN 5310 44 56 10017 Greenhouse Rd/Todd Rd. 60518 Palmetto Swamp Bridge (Brunson Spring Rd) 700 50 2,41719 US 17ALT over Sampit River 700 100 5,32520 SC Highway 9 & SC 410 Green Sea Highway 200 50 1,20021 Horry Co. CTC US 501 & Enoch Rd. 400

SUB TOTAL 1,531 978 3,289 3,340 4,496 1,681 1,697 597 11,339 12,439 12,000 24,000 3,188 3,188 0 0 0 0 5,600 76,746CARRY OVER 13,038 17,863 18,895 18,743 17,435 18,942 20,433 23,024 14,873 17,622 20,810 -2 -2 -2 3,186 6,374 9,562 12,750

CHANGES FROM PREVIOUS TIPALL FIGURES IN $1,000

CURRENT TIP FISCAL YEARSSAFETY(S)RIDE III®INTERSECTION PROJECTS

ADVANCE GUIDESHARE PAYBACKADVANCE GUIDSHARE AMOUNTNON GUIDESHARE FUNDED PROJECTS

Page 46: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

2015-2022 Transportation Improvement Program Grand Strand Area Transportation Study

Page 46 of 47

AMENDMENTS (MINOR)

75

Page 47: TRANSPORTATION IMPROVEMENT PROGRAM...Page 1 of 47 Waccamaw Regional Council of Government RURAL TRANSPORTATION IMPROVEMENT PROGRAM TIP PERIOD: OCTOBER 1, 2019-SEPTEMBER 30, 2022 Revision

2015-2022 Transportation Improvement Program Grand Strand Area Transportation Study

Page 47 of 47