transmission / distribution projects company:eli-n … · 2008. 7. 24. · add 4th auto)..... 33...

91
TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N CUSTOMER: ENTERGY SERVICES (EMO) FACILITIES STUDY EJO # F4PPGS0396 ICTT-2007-104 TRANSMISSION SERVICE REQUEST OASIS 1478781- ALTERNATIVE OPTIONS 2 & 3 Revision: 3 Rev Issue Date Description of Revision Revised By Project Manager 1 11/13/07 ICT Determine Status of Upgrades James Lyle Jody Holland A 06/05/08 Edited and submitted to team members for their input Ibrahim Khan Charles Newell B 07/07/08 Edited and submitted to team members for their input Ibrahim Khan Charles Newell C 07/08/08 Formatted and submitted to Ed Brawner for review Gwen Hymel Charles Newell 2 07/16/08 ICT Determines Upgrade Classification James Lyle Jody Holland 3 7/23/08 Wrong Version of FS submitted to ICT James Lyle Jody Holland

Upload: others

Post on 20-Aug-2020

3 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

TRANSMISSION / DISTRIBUTION PROJECTS

COMPANY:ELI-N

CUSTOMER: ENTERGY SERVICES (EMO)

FACILITIES STUDY

EJO # F4PPGS0396

ICTT-2007-104

TRANSMISSION SERVICE REQUEST

OASIS 1478781- ALTERNATIVE OPTIONS 2 & 3

Revision: 3

Rev Issue Date Description of Revision Revised By Project

Manager

1 11/13/07 ICT Determine Status of Upgrades James Lyle Jody Holland

A 06/05/08 Edited and submitted to team members for their input Ibrahim Khan Charles Newell

B 07/07/08 Edited and submitted to team members for their input Ibrahim Khan Charles Newell

C 07/08/08 Formatted and submitted to Ed Brawner for review Gwen Hymel Charles Newell

2 07/16/08 ICT Determines Upgrade Classification James Lyle Jody Holland

3 7/23/08 Wrong Version of FS submitted to ICT James Lyle Jody Holland

Page 2: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

1. EXECUTIVE SUMMARY..................................................................................................5

2. SAFETY AWARENESS .....................................................................................................5

3. SCOPE SUMMARY............................................................................................................5

3.1 Split Sterlington 115kV bus and replace 500/115kV autotransformer #2 with a unit rated 750 MVA ................................................................................. 5 3.2 Line/transformer upgrades required for the loss of the single 500/115kV autotransformer on Sterlington 115kV split bus #2............................................ 6 3.3 Install a 43.2 MVAR capacitor bank at Walnut Grove 115kV and 43.2 MVAR capacitor bank at Riser 115kV ............................................................... 6 3.4 Upgrade Walnut Grove-Swartz 115kV transmission line............................. 7 3.5 Move the 600MVA 500/115kV autotransformer at Sterlington to Baxter Wilson ............................................................................................................... 7 3.6 North Bastrop Reliability Project. ............................................................ 7 3.7 Delist Sterlington Unit #6. ....................................................................... 8 3.8 Split Sterlington 115kV bus and install new 4th 600MVA, 500/115kV autotransformer at Sterlington........................................................................... 8 3.9 Walnut Grove-Swartz 115kV transmission line ........................................... 8 3.10 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer ... 8 3.11 North Bastrop Reliability Project............................................................... 9 3.12 Delist Sterlington Unit #6.......................................................................... 9

4. SCOPE DETAILS................................................................................................................9

4.1 Sterlington 115 kV Substation – Split Bus & Relocate Walnut Grove.......... 9 4.2 Sterlington 500 kV Substation –Upgrade Autotransformer#2 to 750MVA . 12 4.3 Baxter Wilson 500 kV Substation – Install 2nd Autotransformer relocated from Sterlington............................................................................................... 13 4.4 Riser 115kV Substation............................................................................. 18 4.5 Walnut Grove 115kV Substation .............................................................. 19 4.6 Swartz 115kV Substation ......................................................................... 21 4.7 Rilla 115kV Substation ............................................................................. 22 4.8 Selman Field 115kV Substation ............................................................... 23 4.9 Bastrop 115kV Substation........................................................................ 24 4.10 Walnut Grove to Swartz 115 kV line....................................................... 24 4.11 Sterlington 115 kV tie from Autotransformer#2 to 115 kV bus rated-750MVA .......................................................................................................... 25 4.12 Relocate Tallulah dead-end in the area of transformer at Baxter Wilson 26 4.13 Sterlington IPCO Upgrade...................................................................... 26 4.14 IPCO – Bastrop Upgrade ....................................................................... 27 4.15 Bastrop - N. Bastrop Tap - Log Cabin Upgrade ..................................... 28 4.16 N. Bastrop Tap – N. Bastrop Upgrade.................................................... 29 4.17 Frostkraft - Rilla Upgrade ....................................................................... 29 4.18 Relocate Walnut Grove (Lamkin) to new bay on the 115kV Sterlington bus split # 2 ..................................................................................................... 30 4.19 Sterlington 500 kV Substation – 4th Autotransformer ............................ 31

Entergy Transmission Business Page 2 of 52

Page 3: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 3 of 52

4.20 Sterlington 115 kV – (Split Bus, Relocate Walnut Grove (Lamkin) Lines, & Add 4th Auto) .................................................................................................. 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington 115 kv Tie Line from auto transformer #4 to 115kv bus rated for 600 MVA .................................................................................................... 41 4.23 North Bastrop Reliability Project.............................................................. 41

5. COSTS................................................................................................................................42

6. SCHEDULE .......................................................................................................................44

Project Definition ............................................................................................. 44 Transmission Lines ......................................................................................... 44 Substations ..................................................................................................... 44

7. CONFIRMED RESERVATIONS .....................................................................................45

8. STUDY QUEUE ................................................................................................................52

9. ATTACHMENTS ..............................................................................................................52

A. One Line Drawings.......................................................................................... 52

Page 4: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 4 of 52

Table of Acronyms

ACSR Aluminum Conductor Steel Reinforced ACSS Aluminum Conductor Steel Supported ADEQ Arkansas Department of Environmental Quality AEPW American Electric Power West AFUDC Allowance for Funds Used During Construction ANO Arkansas Nuclear One ATC Available Transfer Capability CLECO Central Louisiana Electric Company CSWS Central & Southwest Control Area EES Entergy Control Area EHV Extra-High Voltage ICT Independent Coordinator of Transmission kV Kilo-Volt MCM (M) Thousand Circular Mils MDEA Mississippi Delta Energy Agency MEP Mississippi Electric Power MPS Missouri Public Service MVA Mega-Volt Amp MW Mega-Watt NPDES National Pollution Discharge Elimination System NOI Notice of Intent OASIS Online Access and Same-time Information System OATT Open Access Transmission Tariff OG&E Oklahoma Gas & Electric POD Point of Delivery POR Point of Receipt SOC System Operations Center SHPO Arkansas State Historic Preservation Office SHV Super High Voltage SW Switch Station SWEPCO Southwest Electric Power Company TOC Transmission Operations Center

Page 5: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 5 of 52

1. EXECUTIVE SUMMARY

Entergy Services (EMO) has submitted a Transmission Service Request for 804 MW of firm network transmission service. The time period for this transfer is from 1/1/2008 until 1/1/2058. The direction of the transaction is from Entergy (EES) to Entergy (EES). The planning study identifies various substation and line equipment upgrades and rebuilds in order to mitigate undesirable system conditions.

Customer requested a facility study to provide an estimated cost of necessary transmission upgrades. The estimated cost of these transmission facilities does not include a grossed-up cost of Entergy’s income tax burden. However these tax gross-ups may apply. Under Entergy’s Independent Coordinator of Transmission which became effective on November 17, 2006, Entergy will recover these costs based on the Attachment T to Entergy’s OATT. In this Attachment T, the ICT has determined these costs to be classified as Supplemental and Base Plan Upgrades.

2. SAFETY AWARENESS

Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety for personnel in mind for construction, operation, and maintenance of the equipment. Specific to the job a safety plan can be developed after site visits and construction plan and outages that are prepared based on an execution plan. This facility study did not afford the foresaid and therefore the safety aspects are described in general. Should the work contained within this Facility Study be approved, a detailed Safety Plan will be formulated and incorporated within the project plan. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and Contract employees must follow all applicable safe work procedures.

3. SCOPE SUMMARY

The Planning Study has identified the following transmission constraints under options 2 and 3 as identified in Entergy’s Planning solution set revision 7 dated 2 June 2008.

Option 2: Large autotransformer on Sterlington 115kV split bus #2 with Sterlington Unit #6 de-list

3.1 Split Sterlington 115kV bus and replace 500/115kV autotransformer #2 with a unit rated 750 MVA

The Sterlington 500/115kV autotransformer #1 or #2 overloads for the loss of the Sterlington 500/115kV autotransformer #2 or #1. A third autotransformer cannot be placed in service because there is a short circuit limitation restricting the use of three autotransformers at Sterlington. It is required that the Sterlington 115kV bus be split in order to place a 3rd Sterlington autotransformer in-service. The split bus #1 contains the transmission lines to Walnut Grove (Swartz), Oak Ridge, IPCO, Selman, and Drew. The split bus #2 contains the transmission lines to Downsville, Marion, Meridian, N. Crossett, and Walnut Grove (Lamkin). The Sterlington 600MVA, 500/115kV autotransformers #3 and #1 are placed on split bus #1. The Sterlington 600MVA, 500/115kV autotransformer #2 is replaced with a new 500/115kV autotransformer having a capacity of at least 750MVA. The existing 600MVA, 500/115kV autotransformer #2 overloads for the loss of either the Sterlington 500/115kV autotransformer #3 or #1. The existing 600MVA, 500/115kV autotransformer #2 will be moved to Baxter Wilson.

Page 6: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 6 of 52

The following sections describe the scope details required for the above work: • 4.1 Sterlington 115kV Substation – Split Bus & Relocate Walnut Grove • 4.2 Sterlington 500kV Substation – Upgrade Autotransformer #2 to 750MVA • 4.11 Sterlington 115kV tie from Autotransformer#2 to 115kV bus rated 750MVA • 4.18 Relocate Walnut Grove (Lamkin) to new bay on the 115kV Sterlington bus split # 2

3.2 Line/transformer upgrades required for the loss of the single 500/115kV autotransformer on Sterlington 115kV split bus #2

The following transmission lines overload for the loss of the single 500/115kV autotransformer on the Sterlington 115kV split bus #2 is:

• Sterlington-IPCO 115kV must be upgraded from 186MVA to at least 278MVA. • IPCO-Bastrop 115kV from 186MVA must be upgraded from 186MVA to at least 255MVA. • Bastrop breaker R3923 and associated switches must be upgraded to 2000A due to the IPCO-

Bastrop 115kV line upgrade to 255MVA. • Bastrop-N. Bastrop Tap – Log Cabin 115kV must be upgraded from 174MVA to at least

197MVA. • North Bastrop Tap-North Bastrop 115kV must be upgraded from 174MVA to at least 178MVA. • Frostkraft-Rilla 115kV must be upgraded from 175MVA to at least 191MVA. • Rilla switch # R1896 must be upgraded from 600A to 2000A due to the Frostkraft-Rilla 115kV

line upgrade to 191MVA • Selman Field 115/69kV autotransformer must be upgraded from 180MVA to at least 193MVA.

The following sections describe the scope details required for the above work: • 4.7 Rilla 115kV Substation (due to Frostkraft – Rilla Upgrade) • 4.8 Selman Field 115kV Substation • 4.9 Bastrop 115kV Substation • 4.13 Sterlington-IPCO Upgrade • 4.14 IPCO – Bastrop Upgrade • 4.15 Bastrop – N. Bastrop Tap – Log Cabin Upgrade to 197MVA • 4.16 N. Bastrop Tap – N. Bastrop Upgrade to 178MVA • 4.17 Frostkraft – Rilla Upgrade

The upgrade of the Sterlington-IPCO 115kV transmission line also eliminates the overload for the loss of the Gerald Andrus-Lake Village Bagby 230kV transmission line and the Lake Village Bagby 230/115kV autotransformer.

3.3 Install a 43.2 MVAR capacitor bank at Walnut Grove 115kV and 43.2 MVAR capacitor bank at Riser 115kV

Under-voltage situations are identified at the following substations for the loss of the single 500/115kV autotransformer on the Sterlington 115kV split bus #2:

• Monroe 115kV • West Monroe 115kV • Frostkraft 115kV • Riser 115kV • Lamkin 115kV • Chenere 115kV • Drew 115kV • Huttig 115kV • Walnut Grove (Lamkin) 115kV • Sterlington 115kV split bus #2 • Crossett Paper Mill 115kV • Meridian AECC 115kV

Page 7: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 7 of 52

For voltage support, a 43.2 MVAR capacitor bank at Walnut Grove and a 43.2 MVAR capacitor bank at Riser 115kV are required. The following sections describe the scope details required for the above work:

• 4.4 Riser 115kV Substation • 4.5 Walnut Grove 115kV Substation

3.4 Upgrade Walnut Grove-Swartz 115kV transmission line

The Walnut Grove-Swartz 115kV transmission line overloads for the loss of following elements:

• Large Sterlington 500/115kV autotransformer #3 • Sterlington-El Dorado 500kV • Sterlington-IPCO 115kV • Sterlington-Selman Field 115kV • Selman Field-Rilla 115kV • Sterlington-Walnut Grove (Lamkin) 115kV • Monroe-West Monroe 115kV • Baxter Wilson-South Vicksburg-Port Gibson 115kV • Plantation-Murray Hydro 115kV • Franklin-Meadville-Roxie 115kV

It is required that the Walnut Grove-Swartz 115kV transmission line be upgraded from a capacity of 228MVA to at least 276MVA. The following sections describe the scope details required for the above work:

• 4.6 Swartz 115kV Substation (due to Walnut Grove – Swartz line upgrade) • 4.10 Walnut Grove to Swartz 115 kV line

3.5 Move the 600MVA 500/115kV autotransformer at Sterlington to Baxter Wilson

The 600MVA 500/115kV autotransformer at Sterlington is moved to Baxter Wilson to eliminate the following overloads for the loss of the Baxter Wilson 500/115kV autotransformer:

• Sterlington-Oak Ridge 115kV • Ray Braswell-Bolton 115kV • Greenville-Southeast Greenville 115kV

The following sections describe the scope details required for the above work:

• 4.3 Baxter Wilson 500kV Substation – Install 2nd Autotransformer relocated from Sterlington • 4.12 Relocate Tallulah dead-end in the area of transformer at Baxter Wilson

3.6 North Bastrop Reliability Project.

The loss of Sterlington-IPCO 115kV transmission line results in low voltage levels from Bastrop to Oak Grove. In the North Bastrop Reliability Project, the Sterlington-Crossett North 115kV line is tapped by constructing about 7 miles of double circuit 115kV line into North Bastrop. Three breakers are to be installed at North Bastrop substation with each breaker connected to lines from Sterlington, North Crossett, and Oak Grove/Log Cabin/Bastrop. The North Bastrop Reliability Project is proposed in the ICT Base Plan for 2012. If this project is approved, the customer may only be required to pay acceleration costs.

See the attached Project Execution plan.

Page 8: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 8 of 52

3.7 Delist Sterlington Unit #6. The Ray Braswell-Baxter Wilson 500kV transmission line overloads for the loss of the Franklin-Grand Gulf 500kV transmission line. This constraint is eliminated by delisting Sterlington unit #6.

OPTION 3: Four 600MVA, 500/115kV autotransformers at Sterlington with Sterlington Unit #6 delist.

3.8 Split Sterlington 115kV bus and install new 4th 600MVA, 500/115kV autotransformer at Sterlington.

The Sterlington 500/115kV autotransformer #1 or #2 overloads for the loss of the Sterlington 500/115kV autotransformer #2 or #1. A third autotransformer cannot be placed in service because there is a short circuit limitation restricting the use of three autotransformers at Sterlington. It is required that the Sterlington 115kV bus be split in order to place a 3rd Sterlington autotransformer in-service. The split bus #1 contains the transmission lines to Walnut Grove (Swartz), Oak Ridge, IPCO, and Selman. The split bus #2 contains the transmission lines to Drew, Downsville, Marion, Meridian, N. Crossett, and Walnut Grove (Lamkin). The Sterlington 600MVA, 500/115kV autotransformers #3 and #1 are placed on split bus #1. The Sterlington 600MVA, 500/115kV autotransformer #2 and the new 600MVA, 500/115kV autotransformer #4 are placed on split bus #2. The 4th 500/115kV autotransformer is required to eliminate the overload on the Sterlington autotransformer #2 for the loss of the Sterlington-El Dorado 500kV transmission line or the Sterlington 500/115kV autotransformer #1 or #3. The following sections describe the scope details required for the above work:

• 4.18 Relocate Walnut Grove(Lamkin) to new bay on the 115kV Sterlington bus split# 2 • 4.19 Sterlington 500kV Substation – 4th Autotransformer • 4.20 Sterlington 115kV Substation – (Split Bus, Relocate Walnut Grove (Lamkin) Line, & Add

4th Auto)

The following transmission line overloads for the specified contingencies.

3.9 Walnut Grove-Swartz 115kV transmission line

Line must be upgraded from 228MVA to at least 256MVA. The Walnut Grove-Swartz 115kV transmission line overloads for the loss of the Sterlington-Selman Field 115kV line, Baxter Wilson-Vicksburg South 115kV line, or Plantation-Murray 115kV line. The following sections describe the scope details required for the above work:

• 4.6 Swartz 115kV Substation (due to Walnut Grove – Swartz line upgrade) • 4.10 Walnut Grove to Swartz 115 kV line

3.10 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer

The 2nd 600MVA, 500/115kV autotransformer is installed at Baxter Wilson to eliminate the following overloads for the loss of the Baxter Wilson 500/115kV autotransformer:

• Sterlington-Oak Ridge 115kV • Ray Braswell-Bolton 115kV • Greenville-Southeast Greenville 115kV

The following sections describe the scope details required for the above work:

• 4.12 Relocate Tallulah dead-end in the area of transformer at Baxter Wilson • 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer

Page 9: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 9 of 52

3.11 North Bastrop Reliability Project. The loss of Sterlington-IPCO 115kV transmission line results in low voltage levels from Bastrop to Oak Grove. In the North Bastrop Reliability Project, the Sterlington-Crossett North 115kV line is tapped by constructing about 7 miles of double circuit 115kV line into North Bastrop. Three breakers are to be installed at North Bastrop substation with each breaker connected to lines from Sterlington, North Crossett, and Oak Grove/Log Cabin/Bastrop. The North Bastrop Reliability Project is proposed in the ICT Base Plan for 2010. If this project is approved, the customer may only be required to pay acceleration costs. See the attached Project Execution plan.

3.12 Delist Sterlington Unit #6. The Ray Braswell-Baxter Wilson 500kV transmission line overloads for the loss of the Franklin-Grand Gulf 500kV transmission line. This constraint is eliminated by delisting Sterlington unit #6.

4. SCOPE DETAILS Option 2:

4.1 Sterlington 115 kV Substation – Split Bus & Relocate Walnut Grove Electrical It is required that the Sterlington 115kV bus be split in order to place the existing 3rd Sterlington autotransformer in-service. Split bus #1 contains transmission lines to Walnut Grove (Swartz), Oak Ridge, IPCO, Selman, and Drew, and ties to 500/115kV autotransformers #1 and #3 as shown on drawing L0090SO5 and L0099SO6. Split bus #2 contains transmission lines to Downsville, Marion, Meridian, N. Crossett, and Walnut Grove (Lamkin) and ties to autotransformer bank #2. The bus needs to be physically cut west of the bay terminating Drew and the tie to autotransformer # 1 (four single phase units). This split will be between bay 4 and bay 5 as shown on drawing L0090SO5. A tie breaker between bus split 1 and bus split 2 is not required. The Walnut Grove (Lamkin) Transmission Line will be relocated from bay 13 to bay 4 by building bus from the transmission dead-end structure to a new dead-end located in front of bay 4. Work in Bay 4 includes new equipment and structures to tie the line to both north and south buses. The substation WO will allocate the bus work required for the line relocation and the transmission line WO will cover removal from existing bay, termination of line on to bus using a flying tap and termination from dead-end to the new bay. Autotransformer #2 will be replaced with a new 3 phase 750MVA unit. This will require upgrading all bus and equipment in Bay 2 to 4000A and switches R8187 and R5307 in Bay 1 upgraded to 2000A. The relay room will be expanded to accommodate additional panels. Remove two breakers and six switches including 2 with ground blades. Install the following electrical equipment:

(2) 115kV breakers 2000A 63kA (2) 115kV breakers 4000A 63kA (6) Switches 115kV 2000A (4) Switches 115kV 4000A (2) Ground Switches 115kV (6) Surge arresters (3) AX2E DE structure (8) CE Switch support (69) 115kV low bus supports

Page 10: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 10 of 52

(12) 115kV high bus supports (8) CCVT pedestals (6) Arrester pedestals (1) Dead-end structure two-level (165) 115kV post insulators 2500 ft of rigid bus 1000 square ft control house extension

Site The area required for the expansion of the 115kV yard is approximately 1 acre. Due to the poor soil conditions, geotextile fabric is required across the entire site. In addition approximately 3-5 ft of fill will be required to bring the new portion of the site up to the elevation of the existing 115kV substation. Approximately 1,900 tons of limestone and 7,500 cu.yards of fill will be required for site prep. Foundations The following foundation work is required: Install 1000ft of 2” PVC conduit Install 3500ft of grounding conductor Foundations for the 2-level dead end will be a new design; all others will be similar to existing foundations already installed:

(4) Circuit breaker dead-tank (8) CCVT pedestals (6) Arrester pedestals (12) High bus support (69) Low bus support (4) CE switch support (1) Full tension two-level Dead-end structure (3) Reduced tension Dead-end structure

Relay Design: 500/115kV Autotransformer #2 Low side Protection

• Primary protection will be a SEL-311L line current differential relay. • Backup protection will be a SEL-421 line distance relay. The supervisory control switches

(43SUPV) for these breakers are not needed on the relay panel, since this function is handled centrally near the RTU.

• Install one (1) CVT on the with junction Box Bus 115kv Split Control:

• Install one (1) Bus Potential transfer panel • Install Bus Differential Protection for the both North Bus #2 & South Bus #2 utilizing the SEL-

487 • Install three (3) CVT on the North Bus#2 with junction Box • Install three (3) CVT on the South Bus #2 with junction Box • Existing North Bus #1 & South Bus #1 bus differential scheme rework.

Breaker Control: • Install five (5) Breaker Control Panel The panel will use an SEL 351 for sync, re-close, and

breaker failure. Breaker failure, reclosing, and synch will be handled by a SEL-351 relay. Walnut Grove (Lamkin) to (bay 4) 115 kV at Sterlington

• Install one (1) Line panel. The panel will use an SEL421 for primary digital and an SEL311-C for digital backup step distance protection.

• Install one (1) CVT on the with junction Box Walnut Grove (Swartz) (bay 9) 115 kV at Sterlington

• Upgrade Line panel. Replace primary relaying with SEL421. Remove carrier relaying equipment

• Install one (1) F/O Junction Box of D.E. tower

Page 11: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 11 of 52

• Remove one (1) Trap & tuner Relay Communications

• Install one (1) Orion Com Processor to support communications • Install one (1) SEL2032 for RTU IED • Install three (3) Fiber Optic ADSS, 24-Fiber • One Lot of Control Cable

Relay Settings New relaying to set Existing relaying to set A study must be done to determine what relaying at remote stations will be affected SCADA A configuration for the RTU will be required. There will also be a configuration required for the SEL2032 being installed at this station. Long Delivery items with lead times: Equipment Quantity Lead

115KV CIRCUIT BREAKER 4 20 weeks

115KV DISCONNECT SWITCH 8 20 weeks

115KV INSULATORS 165 14 weeks

STEEL STRUCTURES 1 lot 20 weeks

115 KV Breaker Control Panel 4 16 weeks

115 kV CCVT’s 8 30 weeks

Bus differential panel 1 16 weeks

Potential transfer panel 1 16 weeks Lead times are as of June 2008

Construction Methodology, duration of construction and outages required: A small amount of grading work and fence relocation will be required to relocate Walnut Grove/Monroe 115 kV line. Outages will likely be required on South Bus No. 1 & No. 2 and North Bus No. 1 & No. 2 in order to perform foundation work. Control house is expected to be enlarged and should not require any outages. Electrical and relay work will require some non outage construction work followed by an outage on the North & South Busses to install new PT’s needed to split the bus. Also outages will be required on each of the busses to connect in new construction. An outage will be required to tie in the relocated bus work on the Walnut Grove/Monroe 115 kV line. Relay testing and checkout will be required on the new Walnut Grove/Monroe line terminal, new bus differentials, new autotransformer connection and all other associated breakers, equipment, etc. All work will be coordinated with work in the 500 kV yards which will drive the duration of this project. Work will likely take approximately one year to complete from grading work to commissioning of new facilities. Assumptions made in scoping and estimates: Existing foundation of 115kV oil circuit breakers R4538 and R2162 will accommodated the new 4000A 115kV gas circuit breakers

Page 12: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 12 of 52

4.2 Sterlington 500 kV Substation –Upgrade Autotransformer#2 to 750MVA

Electrical Remove Autotransformer # 2 - a three phase 616 MVA, 500/115kV unit. It will be transported to Baxter Wilson. The unit will be replaced with a three phase 750MVA autotransformer as shown L0091SO5. The new autotransformer will be bigger than the existing unit and will require a new transformer deadend, arresters and bus work connections. The following electrical equipment will be installed:

(1) 500/115kV autotransformer 750MVA with 115kV arresters (3) 500kV arresters (3) Arrester support structures (1) Autotransformer dead-end structure (1) Lot of bus work and insulators (1) Yard lights (1) Auxiliary transformer

Site The site will not require any expansion since the new transformer will be replacing an existing transformer. However, due to the poor soil conditions, geotextile fabric is required in any of the areas disturbed or excavated by new construction. Approximately 300 tons of limestone and 50cu. yards of fill will be required for site prep. Foundations The new transformer will be larger than the existing unit. The existing transformer foundation will be demolished. A new foundation with oil containment will be installed for the bigger unit. The existing transformer deadend will be replaced to accommodate the larger unit. The following foundation materials will be installed:

300’ Cable trough – poured in place 500’ 2” PVC Conduit 2,000ft of grounding Foundations for the following equipment will use similar to existing designs.

(1) auto-transformer w/oil containment (3) Arrester Pedestal Support foundations (1) Transformer deadend foundation (1) Yard light foundation (1) Aux Transformer foundation

1000ft of pile driving for autotransformer foundation

Relay Design: 500/115kV Autotransformer #2 Protection

• Dual SEL-387 transformer Differential relays with CT inputs from the high-side breakers and the autotransformer low side will be used for Auto #2 Differential protection. A SEL 311L will be used to protect the low side of Auto #2.

• The existing Bus Differential scheme will not need revision. 500kV Instrument Transformers

• Install one (1) CCVT Relay Communications • Two (2) fiber-optic ADSS cables, enclosed in inner-duct, routed in existing cable Trenches are

required between Sterlington 500kV and 115kV switchyard control houses.

Page 13: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 13 of 52

• Two (2) SEL-2506 fiber-optic remote I/O modules are required to dually transmit/receive trip, breaker failure initiate, and lockout for the breakers associated with the 500/115kV Autotransformer #4.

• One (1) Orion Communication Processor for the new relays

Relay Settings

• New Relaying to set SEL-387 Transformer Protection (2) SEL-311L Low side of Auto #2 (1) SEL-351 Breaker Control (2)

• Existing Relaying to set A study must be done to determine what relaying at remote stations will be affected SCADA An RTU configuration will be required at this station. There is also a configuration required for the SEL2032 being installed at this station. Long Delivery items with lead times: Equipment Quantity Lead

500/115kVAutotransformer 1 100 weeks

Steel Structures 1 lot 24 weeks

Insulators 1 lot 14 weeks

500kV Bus 1 lot 14 weeks

500 kV CCVT 1 30 weeks

Auto diff panel 2 16 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

The existing autotransformer will be de-energized for several months while the new autotransformer is installed. Existing foundations will have to be demolished and then new foundations installed. Most likely foundation installation will require “slurry” work to install. Electrical and relay work will be required to install the autotransformer and new bus connections. New control cable will be installed as well as a new relay panel. Outages to other equipment in the substation should not be required.

Assumptions made in scoping and estimates: None documented by the team

4.3 Baxter Wilson 500 kV Substation – Install 2nd Autotransformer relocated from Sterlington

Electrical:

Page 14: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 14 of 52

Transformer Yard Install 600 MVA transformer moved from Sterlington. It is assumed that it is capable of operating in parallel with the existing unit as show on drawings M3020S05 and M3020EA2 (electrical arrangement). See assumption section. 500kV Yard The 500kv yard will include the addition of one folded bay connected to the existing West and East 500kVbus. The new bay will consisting of two breakers, their associated 4 isolating switches and one A phase CVT. The node connection to the transformer will include one disconnect switch with ground switch and surge arresters. All switches shall be motor operated. Associated EHV bus work, support structures and insulators shall be installed. 115kV Connection The connection from the transformer to the 115kV yard shall include four structures with 42 ft pull off for strung bus. The existing Tallulah line must be relocate with three prop structure as part of the T-line asset. Rigid bus will be installed from the transformer pull off, under the Tallulah 115kV line, to a structure pull off for strung bus to the 115kV yard. Two structures shall be installed to support the strung bus to the 115kV yard. A separate WO for line work will be established. However for the purposes of this scope the estimates ($162,000 full financial) are included in the substation cost. 115kV Yard The 115kV yard additions will include the installation of one bay including two breakers, 4 associated isolating switch, one ground switch, three arresters, and three CVT’s. Associated bus work, support structures and insulators shall be installed as well. Due to the paralleling of two transformers, the 115 kV fault level will exceed the existing breaker ratings. Therefore, all breakers will be replaced by 63 kA rating breakers. Breakers must be removed and disposed properly and these include 11 oil circuit breakers. Substation upgrades Shielding shall be installed for the 500kV yard and the 115kV stung bus.

Station service to be reviewed and added if required through tertiary or other sources The existing control house shall be expanded. Site: The area required for the expansion of the 500kV yard is approximately 2 acre. Due to the poor soil conditions, approximately 2’ of excavation is required across the entire site. In addition approximately 6 ft of fill will be required to bring the new portion of the site up to the elevation of the existing 500kV substation. Approximately 3,600 tons of limestone and 30,000 cu. yards of fill will be required for site prep. Foundations: Foundations used will be similar to existing foundation at the Baxter Wilson 500kV and 115kV yards respectively. Foundations required:

- (2) 115kV Breaker support slab - (14) 115kV High elevation bus support - (19) 115kV Low elevation bus support - (5) 115kV High elevation switch support - (1) 115kV Low elevation switch support - (7) 115kV Arrester & CVT support - (3) 115kV Deadend pull off - (1) 500kV Transformer slab - (1) 500kVTransformer oil containment - (2) 500kV Breaker support slab - (58) 500kV High elevation bus support3 - (21) 500kV Low elevation bus support - (6) 500kV High elevation switch support - (24) 500kV Low elevation switch support - (4) 500kV CCVT & Arrester support

Page 15: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 15 of 52

- (4) Shield Pole

Cable trench shall extend from the control house expansion to the new transformer and additional conduit shall be installed to the new equipment. The grounding system shall be upgraded for the system changes and the ground grid shall be expanded for the new equipment. Relay Design:

• Provide and install primary and back-up protection for new autotransformer tied to the 500kV new two (2) breakers of the existing folded ring bus arrangement and to the new two (2) breakers of the 115kV breaker and half station. Replacement required of the existing (13) 115Kv breakers so to accommodate new fault current. Modification required for existing 500kV protection scheme, to operate together with new scheme. Modification required for existing 115kV protection scheme, to operate new breaker replacements/additions and new autotransformer tie to 500kV system.

• Design, purchase, and install a primary/backup autotransformer panel, which includes Nxphase T-pro relay, SEL 387 and SEL 351A relays. The Nxphase T-pro is the autotransformer primary 500/115kV differential protection zone and metering, which wraps from the high side bushing and low side bushing. The first SEL 387 is for the autotransformer backup 500/115kV differential protection and the backup high side bus differential protection, which wraps from the high side breaker J22BX and breaker J22CX and the new 500kV Autotransformer low side bushing. The second SEL 387 is the autotransformer backup 500/115kV differential protection and the backup low side bus differential protection, which wraps from the low side breaker J15BX and breaker J15CX and the new 500kV Autotransformer low side bushing creating a low side bus autotransformer zone of protection. The SEL 351A will monitor the tertiary winding and this relay will be used for alarm purposes only. Furthermore, sudden pressure protection is located in this panel.

• Design, purchase, and install a primary autotransformer high side bus differential panel, which includes the SEL 587Z relay is the 500kV bus differential zone of protection from the high side breaker J22BX and breaker J22CX to the high side bushing of the autotransformer.

• Design, purchase, and install a primary autotransformer high side bus differential panel, which includes the Nxphase B-Pro relay is the 115kV bus differential zone of protection from the low side breaker J15BX and breaker J15CX to the low side bushing of the autotransformer. Verify during design phase if an impedance relay protecting from the low side breakers looking past the autotransformer is necessary.

• Design, purchase, and install two (2) breaker control panels for the two new 500kV circuit breakers installed. Use the breaker control panel drawings done at typical 500kV Project as a reference. These drawings are slightly different from the standard because the breakers disconnect control switches have been added to the breaker control panel.

• Design, purchase, and install two (2) breaker control panels for the new 115kV circuit breakers being installed. The new 115kV breakers will give a double breaker configuration for the 115kV section.

• Modifications to the existing 115kV bus differential panel will be necessary to include the addition of the 115kV breakers.

• Modifications to the existing D20 RTU with a GE Harris D20-ME board to work with new SEL2032, Orion unit and four new status cards.

• Design, purchase, and install junction boxes and indoor distribution junction box as per Entergy Standard Bus Potential Junction Box for High Voltage Metering and Relaying #PM2402, latest revision.

• Install two (2) breaker control panels (2-500kVbreakers) • Install two (2) breaker control panels (2-115kVbreakers) • Install one gang MOS control panel. (5 switches) • Modify existing Bus Differential Panels (Primary East / West Bus & Backup East / West Bus) • Install one (1) 500kV primary XFMR bus diff panels • Install one (1) 500/115kV dual primary/backup XFMR diff panels with Tertiary winding

protection. • Install one (1) 115kV backup bus diff panels XFMR bus diff panels • Install one (1) SEL2032 with associated connections

Page 16: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 16 of 52

• Install one (1) Orion Unit with associated connections • Install one (1) 500kV CVT’s • Install three (3) 115kV CVT’s • Install four (4) Differential CT junction boxes • Install one (1) marshalling junction boxes • Install two (2) XFMR interface monitoring junction box • Install one (1) CVT junction boxes (500kV – CVT) • Install one (1) CVT junction boxes (115kV – CVT) • Install one (1) lot of Shielded Control Cable, Control Cable and fiber optic cable • Autotransformer and Breaker Control, indication, alarms, and analog will have to be wired up,

configured, and programmed for the RTU. • The RTU is a Harris D20 unit that will have to be upgraded with the latest software and

expanded with S status cards and K control cards. • Upgrade existing DFR panel to accommodate new autotransformer

Revenue, interstate or inter-utility metering

• Not Applicable

Relay Settings including DFRs: Transformer and Bus Differential Work Associated with New Equipment Calculate and Develop Relay Settings for new Autotransformer Diff Relays at Baxter Wilson Calculate and Develop Relay Settings for new Breaker Control Relays at Baxter Wilson Calculate and Develop Relay Settings for new Bus Differential Relays at Baxter Wilson Transformer and Bus Differential Work Associated with Existing Equipment Review/Update Relay settings for Existing 500/115 kV Autotransformer Diff Relays at Baxter Wilson Review/Update Relay settings for Existing 500/115 kV Autotransformer Diff Relays at Baxter Wilson Review/Update Relay Settings for Existing 500 kV, and 115 kV Bus Differential Relays at Baxter Wilson Review/Update Relay Settings for Existing 500 kV and 115 kV Breaker Control Relays at Baxter Wilson Line Work Associated with Existing Equipment (500 kV) Review/Update Relay Settings for the incoming lines to Baxter Wilson Line Work Associated with Existing Equipment (115 kV) Review/Update Relay Settings for the incoming lines to Baxter Local RTU and TOC work

Function description (Control/Status/Alarm/Analogue)

Number of functions to be added

Number of functions to be deleted

Comment

5 Analogue, 150 Alarms, 18 Control TBD TBD TBD

Long Delivery items with lead times: Equipment Quantity Lead

500 KV Breaker Control Panel 2 16 weeks

MOS Panel 2 10 weeks

Auto transformer panel 2 16 weeks

Bus Differential panel 3 16 weeks

Page 17: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 17 of 52

115 KV Breaker Control Panel 2 16 weeks

115 kV CCVT’s 3 30 weeks

500 kV CCVT 1 30 weeks

500kV Breakers 2 26 weeks

115kV Breakers 15 22 weeks

500kV Auto- transformer 1 28 months

500kV Switches 5 26 weeks

115kV Switches 4 18 weeks

Arresters 12 18 weeks

Structures 1 lot 26 weeks

Shieldwire/Conductor 1 lot 24 weeks

Insulators 247 16 weeks

Rigid Bus 5000 ft 20 weeks

Station service Xfmr 1 40 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

The substation will have to be expanded on the north side of the 500 kV yard. This will require

considerable fill materials and will probably require the removal of up to two feet of existing silt type materials. The foundations are near a river bottom and could require some concrete to be poured utilizing slurry materials. This will most likely be limited to the deeper piers used for shield wire and dead end structures. Oil containment will be provided underneath the autotransformer. Outages will be required for foundation work including outages on the 115 kV Bus No. 1, 115 kV Bus No. 2,500 kV West Bus and 500 kV East Bus. Foundation work for replacing the 115 kV breakers may be required. If so this work will have to be done while each breaker is out of service.

Much of the Electrical and Relay construction work in the 500 kV yard can be completed without outages

but will require separate outages to the 500 kV West Bus and 500 kV East bus to connect the new construction to the existing facilities. Also outages on the 115 kV Bus No. 1 and 115 kV Bus No. 2 will be required to connect new construction to the existing bus. Outages will be required on each 115 kV breaker while they are being replaced however since it is a breaker and half scheme, the line or transformer can remain in service while the work is being performed.

The autotransformer relocated from Sterlington will have to be re-dressed out and re-oil filled. Also any

necessary maintenance work required will be performed at this time. The work to replace the 115 kV breakers will most likely have to be done “one breaker at a time” and

depending on whether or foundations have to be replaced, it could take anywhere from 2 to 4 weeks per breaker to complete. This will be looked at closer after breaker manufacturer is determined and design work progresses.

The Tallulah 115 kV line will have to be relocated to assure proper safe working and electrical clearances between new 500 kV bus and the 115 kV line. A new dead end tower will have to be installed and an outage will be required when the conductor is relocated. Work will likely take a minimum of one and a half years to construct from grading work to commissioning of new facilities if all materials and design is available.

Page 18: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 18 of 52

Assumptions made in scoping and estimates: - Autotransformer will not require refurbishment - No obstructions such as pipelines, etc

- The bridges and roads in the neighborhood of Baxter Wilson are capable of handling weight of a 3 phase transformer. Should this not be possible, we would have to resort to 3 single phase units with a considerable impact on cost. A decision during design phase will be made.

4.4 Riser 115kV Substation Add 43.2 MVAR capacitor bank as show on station oneline drawing L0679S06 and electrical arrangement drawing L0679EA2. Electrical:

Extend the bus on the east side of the 115kv yard to install the following for a capacitor banks

• Install one (1) 115kv 43.2MVAR capacitor bank • Install one (1) 115kv cap switcher and support structure • Install one (1) 115kv 2000a disconnect switch, manually operated • Install one (1) 115kv switch support structure, type CE • Install three (3) CVT support structures for the bus CVT’s • Install nine (9) 115kv bus supports • Install eighteen (18) insulators • Install one (1) yard light • Install approximately 300ft of rigid bus work and 150ft of strung bus work

Site:

The site work will require the following materials: • 200 cu yds of fill dirt • 100 cu yds of stripping topsoil • 200 tons of limestone • 200 ft of new fence • 160 ft of removal of existing fence

Foundations:

The following foundations will need to be installed totaling 33 cu yds of concrete:

• Install one (1) 3 phase capacitor bank foundation • Install one (1) 115kv cap switcher foundation • Install nine (9) 115kv low elevation bus support foundations • Install one (1) 115kv low elevation switch support foundation • Install three (3) 115kv tubular CVT support foundations • Install approximately 1000 ft of grounding to expand the station • Install approximately 400 ft of conduit and one pull box.

Relay Design: Capacitor Bank Control:

• Install one (1) Capacitor Bank Control Panel The panel will use a SEL-451 • Install one (1) Neutral PT • Install one (1) Neutral PT Junction Box, Termination, Cable • Install one (3) CVTs on transfer bus

Page 19: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 19 of 52

• Install one (1) CVT Junction Box, Termination, Cable • Settings will need to be derived for one capacitor bank control panel consisting of one SEL 451

relay. Long Delivery items with lead times: Equipment Quantity Lead

Capacitor Bank 1 24 weeks

Cap Switcher 1 22 weeks

115kV Switch 1 18 weeks

Steel Structures 1 lot 20 weeks

Insulators 18 14 weeks

Buswork 1 lot 14 weeks

Cap Bank Control Panel 1 16 weeks

115 kV CCVT’s 3 30 weeks

69 kV PT 1 30 weeks

Conductor 1 lot 24 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: This project may require expansion of the substation yard requiring some minor grading work and fence expansion. Foundation work should not require any outages as the new facilities are being installed on the end of the existing bus. Electrical construction will not require any outages as the plan will be to install all new construction and then tie to the existing energized bus with 4’ bus splices. If crews decide to not install the 4’ bus splices, then the operating bus will have to be de-energized in order to tie-in the new construction. This would require the installation of the mobile transformer or if possible, all load in the station would have to be moved to other sources and the two lines would have to be de-energized. As this project develops and schedules are derived, bus outages will be looked at closer. Relay work will be required to install and checkout and then make ready for service the new capacitor bank. Assumptions made in scoping and estimates: None provided by the team

4.5 Walnut Grove 115kV Substation

Add 43.2 MVAR capacitor bank as shown on station oneline L0469S05 and electrical arrangement L0469EA2 Electrical:

Extend the bus north on the west side of the 115kv yard to install the following for a capacitor banks • Install one (1) 115kv 43.2MVAR capacitor bank • Install one (1) 115kv cap switcher and support structure • Install one (1) 115kv 2000A disconnect switch, manually operated • Install one (1) 115kv switch support structure, type CE • Install three (3) CVT support structures for the bus CVT’s • Install nine (9) 115kv low bus supports • Install six (6) 115kv high bus supports

Page 20: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 20 of 52

• Install twenty-four (24) insulators • Install one (1) yard light • Install approximately 450ft of rigid bus work and 150ft of strung bus work.

Site: The site work will require the following materials:

• 200 cu yds of fill dirt • 100 cu yds of stripping topsoil • 300 tons of limestone • 500 ft of new fence • 50 ft of removal of existing fence

Foundations:

The following foundations will need to be installed totaling 33 cu yds of concrete:

• Install one (1) 3 phase capacitor bank foundation • Install one (1) 115kV cap switcher foundation • Install nine (9) 115kV low elevation bus support foundations • Install six (6) 115kV high elevation bus support foundations • Install one (1) 115kV low elevation switch support foundation • Install three (3) 115kV tubular CVT support foundations • Install approximately 1000 ft of grounding to expand the station • Install approximately 400 ft of conduit and one pull box.

Relay Design: Capacitor Bank Control:

• Install one (1) Capacitor Bank Control Panel The panel will use a SEL-451 • Install one (1) Neutral PT • Install one (1) Neutral PT Junction Box, Termination, Cable • Install one (3) CVTs on bus • Install one (1) CVT Junction Box, Termination, Cable • Settings will need to be derived for one capacitor bank control panel consisting of one SEL 451

relay. Control House Equipment: • Upgrade RTU - Status cards & Control cards • Install a free standing Split AC/DC panel. • One Lot of Control Cable

Long Delivery items with lead times: Equipment Quantity Lead

Capacitor Bank 1 24 weeks

Cap Switcher 1 22 weeks

115kV Switch 1 18 weeks

Steel Structures 1 lot 20 weeks

Insulators 24 14 weeks

Buswork 1 lot 14 weeks

Cap Bank Control Panel 1 16 weeks

AC/DC panel 3 16 weeks

115 kV CCVT’s 3 30 weeks

69 kV PT 1 30 weeks

Page 21: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 21 of 52

Conductor 1 lot 24 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: This project will require expansion of the substation yard requiring some grading work and fence expansion. Foundation work should not require any outages as the new facilities are being installed on the end of the existing bus. Electrical construction will not require any outages as the plan will be to install all new construction and then tie to the existing energized bus with 4’ bus splices. If crews decide to not install the 4’ bus splices, then the operating bus will have to be de-energized in order to tie-in the new construction. This would require the installation of the mobile transformer or if possible, all load in the station would have to be moved to other sources and all line sources would have to be de-energized. As this project develops and schedules are derived, bus outages will be looked at closer. Relay work will be required to install and checkout and then make ready for service the new capacitor bank. Assumptions made in scoping and estimates: None provided by the team

4.6 Swartz 115kV Substation Walnut Grove-Swartz 115kV transmission line to be upgraded. As a result the following relay communication upgrades are required. Electrical: Remove Trap and replace with strung bus Attachment for F.O. Junction Box on dead end tower Install conduit from D.E. tower to control house Site: None Foundations: None Relay Design: Sterlington (Walnut Grove) 115 kV at Swartz

• Upgrade Line panel. Replace primary relaying with SEL421. Remove carrier relaying equipment

• Install F.O. Junction Box , Splice tray , Comm. Rack • Remove one (1) trap & tuner

Long Delivery items with lead times: Equipment Quantity Lead

Buswork 1 lot 14 weeks Lead time as of June 2008

Page 22: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 22 of 52

Construction Methodology, duration of construction and outages required: No grading or foundation work should be required. Some conduit work will be required for new fiber optic cable. Electrical construction will require the line to be de-energized. Relay work will be performed concurrently with the electrical construction. Assumptions made in scoping and estimates: None provided by the team

4.7 Rilla 115kV Substation

Replace the existing 600A switch # R1896 with a 2000A switch due to an upgrade of the Frostkraft - Rilla 115kV line to 191MVA. See station oneline L0041S05 Electrical: Remove the existing 600A switch in position # R1896 and install a 2000A switch. The following material is required. One (1) 115kV 2000A disconnect switch Nine (9) insulators One lot of buswork, about 100ft Site: None Foundations: None Relay Design: None Long Delivery items with lead times: Equipment Quantity Lead

115kV Switch 1 18 weeks

Insulators 9 14 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

No grading or foundation work will be required. Electrical construction will require the Frostkraft line to be de-energized and will require an outage to the 115 kV Transfer Bus. No relay work should be required. Assumptions made in scoping and estimates: None provided by the team

Page 23: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 23 of 52

4.8 Selman Field 115kV Substation Selman Field 115/69kV autotransformer must be upgraded from 180MVA to at least 193MVA due to the loss of the single 500/115kV autotransformer on the Sterlington 115kV split bus #2. See station oneline L0479S05. Electrical: Replace autotransformer with new 115/69 kV 200MVA unit with high voltage and low voltage arresters. Site: The following materials will be required to remove the existing transformer foundation and replace it with a new one.

- 50 cubic yards of fill - 100 tons of limestone

Foundations: The existing transformer foundation will be demolished to accommodate the larger autotransformer. The following foundation work will need to be installed:

- (1) Transformer foundation - (1) Transformer oil containment - (1) Removal of existing transformer foundation - 1 lot of conduit to the new unit - 1 lot of grounding -

Relay Design: Sterlington (Walnut Grove) 115 kV at Swartz

• Upgrade Line panel. Replace primary relaying with SEL421. Remove carrier relaying equipment

• Install F.O. Junction Box , Splice tray , Comm. Rack • Remove one (1) trap & tuner

Long Delivery items with lead times: Equipment Quantity Lead

Buswork 1 lot 14 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

An extended outage lasting for several months will be required on the autotransformer in order to replace it. The existing autotransformer will be removed. Minor grading work will be required. Existing foundations for the autotransformer will be demolished. New foundations and oil containment will be installed. Electrical and relay will then be performed after the new autotransformer is installed and dressed out. Electrical and Relay work will also be required on the Sterlington line to remove the line trap equipment, install fiber optic equipment and replace the line panel. Assumptions made in scoping and estimates: None provided by the team

Page 24: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 24 of 52

4.9 Bastrop 115kV Substation Upgrade Breaker R3923 and associated switches to 2000A due to the IPCO-Bastrop 115kV line upgrade to 255MVA. See drawing L0402S05. Electrical: Remove one breaker and two switches. Install one 115kV 2000 Breaker, two 115kV 2000A disconnect switches including one with ground, three surge arresters, and three equipment support structures. Site: None Foundations: Install three equipment support structures for arresters. Relay Design: Remove one 1200 amp Line Trap Install one 2000 amp Line Trap, and supports. Long Delivery items with lead times: Equipment Quantity Lead

Buswork 1 lot 14 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: Unsure at this time if foundation work will be required for the new breaker. This will depend upon final foundation design. During electrical and relay work, an outage to the IPCO-Perryville 115 kV line will be required. The outage duration will have to be kept to a minimum and be performed during the low-load time of the year. Also this line outage may have to be coordinated with off-peak industrial customer loads. Also an outage to the 115 kV operating bus will be required.

Assumptions made in scoping and estimates: None provided by the team

4.10 Walnut Grove to Swartz 115 kV line

Requirement is to increase capacity from 228 MVA to 276 MVA or greater. The line length is 11.4 miles and will be rebuilt because the original construction was performed in 1965 and does not meet existing loading and clearance standards.

Scope of Line Design - Remove 11.4 miles of wood H-frame transmission line including poles, insulators, conductors, shield

wire, guy wire, etc. - Install 11.4 miles of single pole, single circuit transmission line using 1590 ACSR Lapwing conductor,

polymer insulators, 24 fiber 0.528” dia. OPGW shield wire, and vibratory pile foundations where required.

Page 25: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 25 of 52

ROW or Permit issue known at this time: Not known at the time of developing this scope

Long Delivery items with lead times: Equipment Quantity Lead

Poles 105 ea 16 weeks

Foundations 80 ea 16 weeks

1590 ACSR Lapwing 360000 lbs 12 weeks

0.528 OPGW 68000 ft 14 weeks

Polymer insulators 350 ea 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

• Mobilize line contractor and receive materials. • Take a 20 week outage on Walnut Grove-Swartz line section. • Rebuild line with new structures, insulators, conductor and OPGW shield wire. • Total construction duration – approximately 22 weeks.

Assumptions made in scoping and estimates:

- No Distribution underbuild - Foundations will be needed on approximately 75% of the structures

4.11 Sterlington 115 kV tie from Autotransformer#2 to 115 kV bus rated-750MVA

Construct 0.3 mile of overhead line to connect new transformer 115 kV side to the 115 kV bus rated for 750MVA. Scope of Line Design

- Remove 0.15 mile of double bundled 1780 ACSR conductor and insulators. - Existing 3 pole steel structures remain. - Install 0.15 mile of new double bundled 1590 ACSS conductor and insulators on existing 3 pole

steel structures - Existing SW remains in place

Long Delivery items with lead times Equipment Quantity Lead

1590 ACSS Lapwing 9000 lbs 18 weeks

Polymer Insulators 33 ea 14 weeks Lead time as of June 2008

Page 26: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 26 of 52

Construction Methodology, duration of construction and outages required: An outage will be required on the #2 Auto tie line. Outages may be required on substation bus. Construction methodology will involve removing existing conductor and insulators, and installing new insulators and conductor as described in above scope. Construction duration will be approximately 2 weeks.

Assumptions made in scoping and estimates:

- Foundations will be needed on approximately 100% of the structures - Necessary line outages and substation bus outages to perform work are obtainable

4.12 Relocate Tallulah dead-end in the area of transformer at Baxter Wilson

Line removal and reconstruction work equal to that of constructing a 0.1 mile length of line is required to provide space for proposed transformer tie line. Scope of Line Design

- Remove 0.1 mile of transmission line including poles, insulators, conductors, shield wire, guy wire, etc.

- Install 0.1 mile of single pole, single circuit transmission line using 954 ACSR Cardinal conductor, polymer insulators, 7 no. 7 shield wire, and vibratory pile foundations where required.

Long Delivery items with lead times: Equipment Quantity Lead

Poles 2 ea 16 weeks

Foundations 1 ea 16 weeks

954 ACSR Cardinal 2800 lbs 12 weeks

7 no 7 Alumoweld 1000 ft 12 weeks

Polymer insulators 12 ea 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: An outage will be required on the Baxter Wilson-Tallulah 115kV line. Construction methodology will be determined during detailed design.

Assumptions made in scoping and estimates:

- 1 foundation will be required - Necessary line outages to perform work are obtainable

4.13 Sterlington IPCO Upgrade

Scope of Line Design

Page 27: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 27 of 52

Upgrade line to 278 MVA (1396 amps) In order to meet the required rating of 278 MVA, the following sections of the Sterlington – IPCO line will require upgrading: Structures 3 thru 6 (distance ~956’ 0.181 mi), structures 17 thru 67 (distance ~28230’ – 5.346 mi) and the one span between structure #67 and the IPCO substation deadend (distance ~90’). The existing double bundled 336 ACSR in the first two segments and the 1027.4 ACSR in the span between structure 67 and the substation deadend will be replaced with 1590 ACSR “Lapwing”. Wood structures 3, 4, 5 and 18 – 67 will be replaced with single pole direct embedded structures. New braced post or deadend insulators will be installed on all new structures. Long Delivery items with lead times: Equipment Quantity Lead

Poles 53 16 weeks

Foundations 8 16 weeks

1590 ACSR Lapwing 165,117 lbs 12 weeks

Polymer insulators 186 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: Typical line construction practices will be utilized for this project. Tracked equipment will be used where necessary especially for handling and setting the concrete poles. Specialized equipment will be required for the installation of the vibratory caissons. Construction sequencing is anticipated to occur as follows: (1) Receive material, spot and frame poles. (2) Take crippling outage to set new structures and remove old structures. Existing conductor and shield wire will be transferred to new structures and temporarily placed in blocks. (3) The existing conductor and shield wire will be used to pull in new conductor and shield wire. (4) Complete all wire terminations, jumpers, grounding, ROW clean up, etc. and re-energize line section. The total line construction duration will be approximately 16 weeks with a line outage duration window of approximately 12 weeks. Assumptions made in scoping and estimates:

• 8 Vibratory piles will be required • A crippling outage can be taken on this line section • No ROW access issues for construction equipment and for hauling, spotting concrete poles • All necessary crossing permits are obtainable (Hwy., Railroad, etc.)

4.14 IPCO – Bastrop Upgrade

Scope of Line Design Upgrade line to 255 MVA (1280 amps) In order to meet the required capacity of 255 MVA, the existing line between IPCO and Bastrop will need to be rebuilt. The existing double bundled 336 ACSR conductor will be replaced with 1272 ACSR “Bittern” conductor. The existing wood H-frames and three pole angle and deadend structures will be replaced with new single pole direct embedded structures. Angle and deadend structures will be guyed.

Page 28: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 28 of 52

Long Delivery items with lead times: Equipment Quantity Lead

Poles 42 16 weeks

Foundations 5 16 weeks

1272 ACSR Bittern 99,885 lbs 12 weeks

Polymer insulators 168 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: Typical line construction practices will be utilized for this project. Tracked equipment will be used where necessary especially for handling and setting the concrete poles. Specialized equipment will be required for the installation of the vibratory caissons. Construction sequencing is anticipated to occur as follows: (1) Receive material, spot and frame poles. (2) Take crippling outage to set new structures and remove old structures. Existing conductor and shield wire will be transferred to new structures and temporarily placed in blocks. (3) The existing conductor and shield wire will be used to pull in new conductor and shield wire. (4) Complete all wire terminations, jumpers, grounding, ROW clean up, etc. and re-energize line section. The total line construction duration will be approximately 13 weeks with a line outage duration window of approximately 10 weeks.

Assumptions made in scoping and estimates:

• 5 Vibratory piles will be required • A crippling outage can be taken on this line section • No ROW access issues for construction equipment and for hauling, spotting concrete poles • All necessary crossing permits are obtainable (Hwy., Railroad, etc.)

4.15 Bastrop - N. Bastrop Tap - Log Cabin Upgrade

Upgrade line to 197 MVA (989 amps) Scope of Line Design Rebuild line using single steel pole construction and 954 ACSR “Cardinal” conductor. Long Delivery items with lead times: Equipment Quantity Lead

Poles 101 16 weeks

Foundations 5 16 weeks

954 ACSR Cardinal 115,373 lbs 12 weeks

Polymer insulators 336 10 weeks Lead time as of June 2008

Page 29: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 29 of 52

Construction Methodology, duration of construction and outages required: Typical line construction practices will be utilized for this project. Tracked equipment will be used where necessary. Specialized equipment will be required for the installation of the vibratory caissons and for the drilled pier foundations. Construction sequencing is anticipated to occur as follows: (1) Receive material, spot and frame poles. (2) Take crippling outage to install drilled pier foundations, set new structures and remove old structures. Existing conductor and shield wire will be transferred to new structures and temporarily placed in blocks. (3) The existing conductor and shield wire will be used to pull in new conductor and shield wire. (4) Complete all wire terminations, jumpers, grounding, ROW clean up, etc. and re-energize line section. The total line construction duration will be approximately 23 weeks with a line outage duration window of approximately 18 weeks. Assumptions made in scoping and estimates:

• 6 Vibratory piles will be required • 5 concrete drilled pier foundations will be required • A crippling outage can be taken on this line section • No ROW access issues for construction equipment • All necessary crossing permits are obtainable (Hwy., Railroad, etc.) • Steel poles being installed in lieu of heavy concrete poles

4.16 N. Bastrop Tap – N. Bastrop Upgrade

Scope of Line Design Upgrade line to 178 MVA (894 amps) Existing conductor is 1027.4 ACSR which should provide the required load capacity. Construction Methodology, duration of construction and outages required: Not Applicable – depending on field verification to uprate ampacity of existing conductor to achieve requested load capacity. Assumptions made in scoping and estimates: Surveying will be required to verify existing conductor has adequate clearance when operating at temperatures required meeting the 178 MVA requirement. Structures may have to be replaced if adequate clearance is not available.

4.17 Frostkraft - Rilla Upgrade

Scope of Line Design Upgrade line to 191 MVA (959 amps) The majority of the line is constructed with double bundled 336.4 26/7 ACSR conductor and requires no upgrade. However several sections of the line have 666 24/7 ACSR conductor and will require reconductoring to meet the required ampacity of 191 MVA. The sections requiring re-conductoring are as follows: Frostkraft Sub – Str #28 (1 span - 265’); Str.#72 – Str.#91 (19 spans – 10,650’); Str. #102 – Rilla Sub. (3 spans – 1215’). The under rated line sections will re-conductored with 954 ACSR “Cardinal”

Page 30: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 30 of 52

conductor. Total length of wire to be replaced is 12,130 feet (2.3 miles). Wood structures #28, 72, 76 thru 91, 103, and 104 will be replaced with new single pole structures. The total quantity of structures to be replaced is 20. Six (6) vibratory piles are assumed to be required in areas near the river. New fiber optic shield will be installed on the sections requiring reconductoring. Long Delivery items with lead times: Equipment Quantity Lead

Poles 20 16 weeks

Foundations 6 16 weeks

954 ACSR Cardinal 47,000 lbs 12 weeks

Polymer insulators 81 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: Typical line construction practices will be utilized for this project. Tracked equipment will be used where necessary especially for handling and setting the concrete poles. Specialized equipment will be required for the installation of the vibratory caissons. Construction sequencing is anticipated to occur as follows: (1) Receive material, spot and frame poles. (2) Take crippling outage to set new structures and remove old structures. Existing conductor and shield wire will be transferred to new structures and temporarily placed in blocks. (3) The existing conductor and shield wire will be used to pull in new conductor and shield wire. (4) Complete all wire terminations, jumpers, grounding, ROW clean up, etc. and re-energize line section. The total line construction duration will be approximately 11 weeks with a line outage duration window of approximately 9 weeks. Assumptions made in scoping and estimates:

• 6 Vibratory piles will be required • A crippling outage can be taken on this line section • No ROW access issues for construction equipment and for hauling, spotting concrete poles • All necessary crossing permits are obtainable (Hwy., Levee, Railroad, etc.) • A flagman will be required while working along side of the railroad tracks

4.18 Relocate Walnut Grove (Lamkin) to new bay on the 115kV Sterlington bus split # 2

Remove line from existing dead-end structure, terminate line on new rigid bus with a flying pass and make connection to structure on the new bay. A low profile rigid bus will be built by Substations by extending the fence and grounding. Scope of Line Design Remove 2 existing terminal structures and associated conductors, insulators, shield wire, etc. Install 2 new terminal structures and associated hardware to connect with proposed rigid bus and substation line bay dead end structures.

Long Delivery items with lead times: Equipment Quantity Lead

Poles 6 16 weeks

Page 31: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 31 of 52

Foundations 6 16 weeks

1780 ACSR Chukar 1000 lbs 12 weeks

Polymer insulators 20 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: Construction methodology will be made during detail design of the project. At a minimum, an outage will be required on the Sterlington-Walnut Grove line section to allow for necessary structure work and line relocation. Additional line outages may also be required but cannot be determined at this time based on this preliminary study.

Assumptions made in scoping and estimates:

- Existing deadend structures will need to be relocated - Foundations will be needed on all of the structures

Option 3:

4.19 Sterlington 500 kV Substation – 4th Autotransformer

Site The area required for the expansion of the 500kV yard is approximately 5.4 acre. Due to the poor soil conditions, geotextile fabric is required across the entire site. In addition approximately 3-5 ft of fill will be required to bring the new portion of the site up to the elevation of the existing 500kV substation. It is assumed that the site is heavily wooded and approximately 2’ of soil will need to be excavated to ensure the removal of all tree stumps and roots. Approximately 10,000 tons of limestone and 50,000 cu. yards of fill will be required for site prep. Foundation

1000’ Cable trough – poured in place 1000’ 2” PVC Conduit 15,000ft of grounding Foundations for the following equipment will use similar to existing designs. (1) auto-transformer w/oil containment (2) dead-tank breakers (1) Full tension dead-end structure (1) Autotransformer dead-end structure (53) Low bus support (42) High bus support (24) Low switch support (27) High switch support (12) Equipment pedestals (CCVT or surge arrester) (4) Shield wire structures (14) Yard lights 1320ft of pile driving for autotransformer foundation

Electrical Add a second 500/115kV, 396/492/616 MVA, 7.92% impedance autotransformer with buried tertiary in the new 500 kV outdoor 500 kV substation for paralleling with the existing unit.

Page 32: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 32 of 52

To add the new autotransformer it is necessary to expand the ring bus towards Old Sterlington Road to add one more node and relocate Perryville line 2 to prevent autotransformer #3 & #4 from sharing a breaker The 115 kV will tie via overhead line to the 115kV yard. A separate line WO will be used.

Electrical Equipment: (1) 500/115kV autotransformer (2) 500kV breakers (6) 500kV Switches 3000A with motor operator (2) 500kV Ground Switches (1) Full tension dead-end structure (1) Autotransformer dead-end structure (53) Low bus support (42) High bus support (24) Low switch supports (27) High switch supports (12) Equipment Pedestals (CCVT or Surge Arrester) (4) Shield wire structures 165 Post insulators 6200ft 500kV aluminum bus with damper conductor 3000ft Shield wire (12) Yard lights

Relay 500/115kV Autotransformer #4 Protection

• Dual SEL-387 transformer Differential relays with CT inputs from the high-side breakers and the autotransformer low side will be used for Auto #4 Differential protection. A SEL 311L will be used to protect the low side of Auto #4.

• 500/115kV Perryville #2 Line Protection; CT inputs from the new breakers will need to be wired to the existing Perryville 2 line panel.

• The existing bus Differential scheme will not need revision. • 500kV Breaker Control & Protection (Qty =2) Breaker failure, reclosing, and sync will be handled a by SEL-351relay. • The supervisory control switches (43SUPV) are not needed on the relay panels, since this

function is handled centrally near the RTU. • 500kV Motor Operated Switch Control (Qty=5) Interlocks (52b contacts) from associated

breakers are required. • The supervisory control switch (43SUPV) is not needed on the relay panels, since this function

is handled centrally near the RTU. These controls will be centrally located on a single panel. • 500kV Instrument Transformers - Three (3) Perryville 2 line CCVTs will be relocated to reflect

the line movement. The Auto #4 CCVT will be installed.

Relay Communications • Two (2) fiber-optic ADSS cables, enclosed in inner-duct, routed in existing cable Trenches are

required between Sterlington 500kV and 115kV switchyard control houses. • Two (2) SEL-2506 fiber-optic remote I/O modules are required to dually transmit/receive trip,

breaker failure initiate, and lockout for the breakers associated with the 500/115kV Autotransformer #4.

• One (1) SEL-2032 will be required to support Communications (dialup, SCADA, etc.) with the new relays.

Relay Settings

• New Relaying to set SEL-387 Transformer Protection (2)

Page 33: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 33 of 52

SEL-311L Low side of Auto #4 (1) SEL-351 Breaker Control (2)

• Existing Relaying to set

A study must be done to determine what relaying at remote stations will be affected SCADA An RTU configuration will be required at this station. There is also a configuration required for the SEL2032 being installed at this station. Construction Strategy and timing of outages: The substation will have to be expanded on the south end. The substation addition that was installed two years ago required extensive work on the substation pad requiring the installation of two types of filter fabric to help stabilize the soil. Also an iron ore type fill was used to help strengthen the fill materials. This will require a little more time on the site grading work but should not cause any unforeseen problems. The foundation work may require some concrete to be poured utilizing slurry materials. This will most likely be limited to the deeper piers used for shield wire and dead end structures. Oil containment will be provided underneath the autotransformer. Outages will be required on two points on the ring bus during foundation construction. Electrical and relay work will require some non outage construction work followed by outages on the ring bus. The Perryville No. 2 line will be relocated to a different node on the ring bus and will require an outage. Also an outage on Autotransformer No. 3 will be required to tie in the new construction. All work will be coordinated with work in the 115 kV yard. Substation long delivery items:

Quantity Material Description Lead Time (weeks) 1 500/115kV Autotransformer 104 - 116 2 500kV Breaker 26 6 500kV Switch 26 3 surge arresters 18

1 lot 500kV Steel Structures 20 1 lot 500kV insulators 20 1 lot EHV buswork 20

2 500 KV BREAKER CONTROL PANEL 16 1 500 kV CCVT 16 2 MOS Panel 10 2 Auto Differential panel 16

Lead time as of June 2008

ASSUMPTIONS: None provided by the team

4.20 Sterlington 115 kV – (Split Bus, Relocate Walnut Grove (Lamkin) Lines, & Add 4th Auto)

Site The area required for the expansion of the 115kV yard is approximately 1 acre. Due to the poor soil conditions, geotextile fabric is required across the entire site. In addition approximately 3-5 ft of fill will be

Page 34: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 34 of 52

required to bring the new portion of the site up to the elevation of the existing 115kV substation. Approximately 1,900 tons of limestone and 7,500 cu. yards of fill will be required for site prep. Foundation

1000ft of 2” PVC conduit 3500ft of grounding conductor Foundations for the 2-level dead end will be a new design; all others will be similar to existing foundations already installed: (4) Circuit breaker dead-tank (2 in the new auto#4 bay and 2 in new Walnut Grove bay) (9) CCVT pedestal (12) High bus support (69) Low bus support (4) CE switch support (1) Full tension two-level Dead-end structure (3) Reduced tension Dead-end structure

Electrical BUS SPLIT It is required that the Sterlington 115kV bus be split in order to place the existing 4th Sterlington autotransformer in-service. The bus needs to be physically cut between bays 5 and 6 (bay numbering per drawing L0090EA2). The bus needs to be physically cut east of the bay terminating Drew and the tie to autotransformer # 1 (four single phase units). A tie breaker between bus split 1 & 2 is not required. See table below for final configuration.

SPLIT BUS #1 SPLIT BUS #2 Walnut Grove (Swartz) Drew (Frostkraft)

Oak Ridge Downsville

IPCO Marion

Selman Meridian

N. Crossett

500/115kV Autotransformer #3 Walnut Grove (Lamkin)

500/115kV Autotransformer #4 500/115kV Autotransformer #1

500/115kV Autotransformer #2 RELOCATE WALNUT GROVE (MONROE) T-LINE Relocate this line from bay 13 to bay 4 by building bus from the transmission dead-end structure to a new dead-end located in front of bay 4. The existing T-line dead end will remain in place and taps will connect line conductor to bus below. Work in Bay 4 includes new equipment and structures to tie the line to both north and south buses. The substation WO will allocate the bus work required for the line relocation and the transmission line WO will cover removal from existing bay, termination of line on to bus using a flying tap and termination from dead-end to the new bay.

Page 35: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 35 of 52

AUTOTRANSFORMER #4 TIE BAY Bay 7 will tie the new 500/115kV autotransformer with a new 2-level dead-end structure to terminate the Bastrop line on top and transformer tie on bottom. Work includes new equipment and structures to tie the autotransformer to both north and south buses. The relay room will be expanded to accommodate additional panels.

Electrical Equipment: (4) 115kV breakers 3000A 63kA (4) Switches 115kV 2000A (4) Switches 115kV 3000A (2) Ground Switches 115kV (3) AX2E DE structure (8) CE Switch support (69) 115kV low bus supports (12) 115kV high bus supports (8) E pedestals (1) Dead-end structure two-level (165) 115kV post insulators 2500 ft of rigid bus 1000 square ft control house extension

Relay 500/115kV Autotransformer #4 Low side Protection

• Primary protection will be a SEL-311L line current differential relay. • Backup protection will be a SEL-421 line distance relay. The supervisory control switches

(43SUPV) for these breakers are not needed on the relay panel, since this function is handled centrally near the RTU.

• Install one (1) CVT on the with junction Box Bus 115kv Split Control:

• Install one (1) Bus Potential transfer panel • Install Bus Differential Protection for the both North Bus #2 & South Bus #2 utilizing the SEL-

487 • Install three (3) CVT on the North Bus#2 with junction Box • Install three (3) CVT on the South Bus #2 with junction Box • Existing North Bus #1 & South Bus #1 bus differential scheme rework.

Breaker Control: • Install four (4) Breaker Control Panel The panel will use an SEL 351 for sync, re-close, and

breaker failure. Breaker failure, re-closing, and synch will be handled by a SEL-351 relay. Walnut Grove to new bay – 115 kV at Sterlington

• Install one (1) Line Relay Panel 28”. The panel will use an SEL421 for primary digital and an SEL311-C for digital backup step distance protection.

• Install one (1) CVT on the with junction Box Frostkraft line to bus #1 (bay 13)

• Rework existing Monroe “Walnut Grove” Line panel. The panel uses an SEL421 for primary and an SEL311-C for backup step distance protection. Install Pulars to for PLC.

• Install one (1) CVT on the with junction Box • Install one (1) Line Trap the with Tuner • Install one (1) Orion Com Processor to support communications • Install one (1) SEL2032 for RTU IED • Install two (2) Fiber Optic ADSS, 24-Fiber • One Lot of Control Cable

Page 36: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 36 of 52

Long Delivery items with lead times: Equipment Quantity Lead

115KV Breaker Control Panel 4 16 weeks

115KV Bus Diff panel 2 16 weeks

Potential Transfer Panel 2 10 weeks

115KV Line panel 1 16 weeks Lead time as of June 2008

Relay Communications Two (2) fiber-optic ADSS cables enclosed inner duct routed in existing cable trench are required between Sterlington 500kV and 115kV switchyard control houses Two (2) SEL-2506 fiber-optic remote I/O modules are required to dually transmit/receive trip, breaker failure initiate, and lockout Commands for the breakers associated with the 500/115kV Autotransformer #4. Relay Settings New relaying to set Existing relaying to set A study must be done to determine what relaying at remote stations will be affected SCADA A configuration for the RTU will be required. There will also be a configuration required for the SEL2032 being installed at this station. Construction Strategy and timing of outages: A small amount of grading work and fence relocation will be required to relocate Walnut Grove/Monroe 115 kV line. Outages will likely be required on South Bus No. 1 & No. 2 and North Bus No. 1 & No. 2 in order to perform foundation work. Control house is expected to be enlarged and should not require any outages. Electrical and relay work will require some non outage construction work followed by an outage on the North & South Busses to install new PT’s needed to split the bus. Also outages will be required on each of the busses to connect in new construction. An outage will be required to tie in the relocated bus work on the Walnut Grove/Monroe 115 kV line. Relay testing and checkout will be required on the new Walnut Grove/Monroe line terminal, new bus differential, new autotransformer connection and all other associated breakers, equipment, etc. All work will be coordinated with work in the 500 kV yard which will drive the duration of this project. Substation long delivery items:

Quantity Material Description Lead 4 115kV circuit breaker 22 weeks 8 115kV disconnect switch 18 weeks 165 115kV insulators 14 weeks 1 lot Steel structures 20 weeks 1 lot 115kV buswork 14 weeks 2 115 KV Beaker control panel 16 weeks 2 Bus Differential panel 16 weeks 1 Potential transfer panel 16 weeks

Lead time as of June 2008

Page 37: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 37 of 52

Assumptions: None provided by the team

4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer

Electrical: Transformer Yard Install second new 600 MVA transformer. It is assumed that it is capable of operating in parallel with the existing unit. See assumption section. Additional tertiary equipment will include station service capability of 500KVA, adequate grounding protection including transformers and limiting reactors, etc. 500kV Yard The 500kv yard will include the addition of one folded bay connected to the existing West and East 500kVbus. The new bay will consisting of two breakers, their associated 4 isolating switches and one A phase CVT. The node connection to the transformer will include one disconnect switch with ground switch and surge arresters. All switches shall be motor operated. Associated EHV bus work, support structures and insulators shall be installed. 115kV Connection The connection from the transformer to the 115kV yard shall include four structures with 42 ft pull off for strung bus. The existing Tallulah line must be relocate with three prop structure as part of the T-line asset. Rigid bus will be installed from the transformer pull off, under the Tallulah 115kV line, to a structure pull off for strung bus to the 115kV yard. Two structures shall be installed to support the strung bus to the 115kV yard. A separate WO for line work will be established. However for the purposes of this scope the estimates ($162,000 full financial) are included in the substation cost. 115kV Yard The 115kV yard additions will include the installation of one bay including two breakers, 4 associated isolating switch, one ground switch, three arresters, and three CVT’s. Associated bus work, support structures and insulators shall be installed as well. Due to the paralleling of two transformers, the 115 kV fault level will exceed the existing breaker ratings. Therefore, all breakers will be replaced by 63 kA rating breakers. Breakers must be removed and disposed properly and these include 11 oil circuit breakers. Substation upgrades Shielding shall be installed for the 500kV yard and the 115kV stung bus.

Station service to be reviewed and added if required through tertiary or other sources The existing control house shall be expanded. Site: The area required for the expansion of the 500kV yard is approximately 2 acre. Due to the poor soil conditions, approximately 2’ of excavation is required across the entire site. In addition approximately 6 ft of fill will be required to bring the new portion of the site up to the elevation of the existing 500kV substation. Approximately 3,600 tons of limestone and 30,000 cu. yards of fill will be required for site prep. Foundations: Foundations used will be similar to existing foundation at the Baxter Wilson 500kV and 115kV yards respectively. Foundations required:

- 115kV Breaker support slab - 115kV High elevation bus support - 115kV Low elevation bus support

Page 38: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 38 of 52

- 115kV High elevation switch support - 115kV Low elevation switch support - 115kV Arrester & CVT support - 115kV Deadend pull off - 500kV Transformer slab - 500kVTransformer oil containment - 500kV Breaker support slab - 500kV High elevation bus support - 500kV Low elevation bus support - 500kV High elevation switch support - 500kV Low elevation switch support - 500kV CCVT & Arrester support - Shield Pole

Cable trench shall extend from the control house expansion to the new transformer and additional conduit shall be installed to the new equipment. The grounding system shall be upgraded for the system changes and the ground grid shall be expanded for the new equipment. Relay Design:

• Provide and install primary and back-up protection for new autotransformer tied to the 500kV new two (2) breakers of the existing folded ring bus arrangement and to the new two (2) breakers of the 115kV breaker and half station. Replacement required of the existing (13) 115Kv breakers so to accommodate new fault current. Modification required for existing 500kV protection scheme, to operate together with new scheme. Modification required for existing 115kV protection scheme, to operate new breaker replacements/additions and new autotransformer tie to 500kV system.

• Design, purchase, and install a primary/backup autotransformer panel, which includes Nxphase T-pro relay, SEL 387 and SEL 351A relays. The Nxphase T-pro is the autotransformer primary 500/115kV differential protection zone and metering, which wraps from the high side bushing and low side bushing. The first SEL 387 is for the autotransformer backup 500/115kV differential protection and the backup high side bus differential protection, which wraps from the high side breaker J22BX and breaker J22CX and the new 500kV Autotransformer low side bushing. The second SEL 387 is the autotransformer backup 500/115kV differential protection and the backup low side bus differential protection, which wraps from the low side breaker J15BX and breaker J15CX and the new 500kV Autotransformer low side bushing creating a low side bus autotransformer zone of protection. The SEL 351A will monitor the tertiary winding and this relay will be used for alarm purposes only. Furthermore, sudden pressure protection is located in this panel.

• Design, purchase, and install a primary autotransformer high side bus differential panel, which includes the SEL 587Z relay is the 500kV bus differential zone of protection from the high side breaker J22BX and breaker J22CX to the high side bushing of the autotransformer.

• Design, purchase, and install a primary autotransformer high side bus differential panel, which includes the Nxphase B-Pro relay is the 115kV bus differential zone of protection from the low side breaker J15BX and breaker J15CX to the low side bushing of the autotransformer. Verify during design phase if an impedance relay protecting from the low side breakers looking past the autotransformer is necessary.

• Design, purchase, and install two (2) breaker control panels for the two new 500kV circuit breakers installed. Use the breaker control panel drawings done at typical 500kV Project as a reference. These drawings are slightly different from the standard because the breakers disconnect control switches have been added to the breaker control panel. Design, purchase, and install two (2) breaker control panels for the new 115kV circuit breakers being installed. The new 115kV breakers will give a double breaker configuration for the 115kV section.

• Modifications to the existing 115kV bus differential panel will be necessary to include the addition of the 115kV breakers.

• Modifications to the existing D20 RTU with a GE Harris D20-ME board to work with new SEL2032, Orion unit and four new status cards.

Page 39: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 39 of 52

• Design, purchase, and install junction boxes and indoor distribution junction box as per Entergy Standard Bus Potential Junction Box for High Voltage Metering and Relaying #PM2402, latest revision.

• Install two (2) breaker control panels (2-500kVbreakers) • Install two (2) breaker control panels (2-115kVbreakers) • Install one gang MOS control panel. (5 switches) • Modify existing Bus Differential Panels (Primary East / West Bus & Backup East / West Bus) • Install one (1) 500kV primary XFMR bus diff panels • Install one (1) 500/115kV dual primary/backup XFMR diff panels with Tertiary winding

protection. • Install one (1) 115kV backup bus diff panels XFMR bus diff panels • Install one (1) SEL2032 with associated connections • Install one (1) Orion Unit with associated connections • Install one (1) 500kV CVT’s • Install three (3) 115kV CVT’s • Install four (4) Differential CT junction boxes • Install one (1) marshalling junction boxes • Install two (2) XFMR interface monitoring junction box • Install one (1) CVT junction boxes (500kV – CVT) • Install one (1) CVT junction boxes (115kV – CVT) • Install one (1) lot of Shielded Control Cable, Control Cable and fiber optic cable • Autotransformer and Breaker Control, indication, alarms, and analog will have to be wired up,

configured, and programmed for the RTU. • The RTU is a Harris D20 unit that will have to be upgraded with the latest software and

expanded with S status cards and K control cards. • Upgrade existing DFR panel to accommodate new autotransformer

Revenue, interstate or inter-utility metering

• Not Applicable

Relay Settings including DFRs: Transformer and Bus Differential Work Associated with New Equipment Calculate and Develop Relay Settings for new Autotransformer Diff Relays at Baxter Wilson Calculate and Develop Relay Settings for new Breaker Control Relays at Baxter Wilson Calculate and Develop Relay Settings for new Bus Differential Relays at Baxter Wilson Transformer and Bus Differential Work Associated with Existing Equipment Review/Update Relay settings for Existing 500/115 kV Autotransformer Diff Relays at Baxter Wilson Review/Update Relay settings for Existing 500/115 kV Autotransformer Diff Relays at Baxter Wilson Review/Update Relay Settings for Existing 500 kV, and 115 kV Bus Differential Relays at Baxter Wilson Review/Update Relay Settings for Existing 500 kV and 115 kV Breaker Control Relays at Baxter Wilson Line Work Associated with Existing Equipment (500 kV) Review/Update Relay Settings for the incoming lines to Baxter Wilson Line Work Associated with Existing Equipment (115 kV) Review/Update Relay Settings for the incoming lines to Baxter Local RTU and TOC work

Function description (Control/Status/Alarm/Analogue)

Number of functions to be added

Number of functions to be deleted

Comment

5 Analogue, 150 Alarms, 18 Control TBD TBD TBD

Page 40: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 40 of 52

Long Delivery items with lead times: Equipment Quantity Lead

Auto Transformer 1 80 weeks

500 KV Breaker Control Panel 2 16 weeks

MOS Panel 2 10 weeks

Auto transformer panel 2 16 weeks

Bus Differential panel 3 16 weeks

115 kV Break Control Panels 2 16 weeks

115 kV CCVT’s 3 30 weeks

500 kV CCVT 1 30 weeks

500kV Breakers 2 26 weeks

115kV Breakers 15 22 weeks

500kV Auto transformer 1 28 months

500kV Switches 5 26 weeks

115kV Switches 4 18 weeks

Arresters 12 18 weeks

Structures 1 lot 26 weeks

Shieldwire/Conductor 1 lot 24 weeks

Insulators 247 16 weeks

Rigid Bus 5000 ft 20 weeks

Station service Xfmr 1 40 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required:

The substation will have to be expanded on the north side of the 500 kV yard. This will require

considerable fill materials and will probably require the removal of up to two feet of existing silt type materials. The foundations are near a river bottom and could require some concrete to be poured utilizing slurry materials. This will most likely be limited to the deeper piers used for shield wire and dead end structures. Oil containment will be provided underneath the autotransformer. Outages will be required for foundation work including outages on the 115 kV Bus No. 1, 115 kV Bus No. 2,500 kV West Bus and 500 kV East Bus. Foundation work for replacing the 115 kV breakers may be required. If so this work will have to be done while each breaker is out of service.

Much of the Electrical and Relay construction work in the 500 kV yard can be completed without outages

but will require separate outages to the 500 kV West Bus and 500 kV East bus to connect the new construction to the existing facilities. Also outages on the 115 kV Bus No. 1 and 115 kV Bus No. 2 will be required to connect new construction to the existing bus. Outages will be required on each 115 kV breaker while they are being replaced however since it is a breaker and half scheme, the line or transformer can remain in service while the work is being performed.

The work to replace the 115 kV breakers will most likely have to be done “one breaker at a time” and

depending on whether or foundations have to be replaced, it could take anywhere from 2 to 4 weeks per breaker to complete. This will be looked at closer after breaker manufacturer is determined and design work progresses.

Page 41: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 41 of 52

The Tallulah 115 kV line will have to be relocated to assure proper safe working and electrical clearances between new 500 kV bus and the 115 kV line. A new dead end tower will have to be installed and an outage will be required when the conductor is relocated. Work will likely take a minimum of one and a half years to construct from grading work to commissioning of new facilities if all materials and design is available.

Assumptions made in scoping and estimates:

- No obstructions such as pipelines, etc - The bridges and roads in the neighborhood of Baxter Wilson are capable of handling weight of a 3

phase transformer. Should this not be possible, we would have to resort to 3 single phase units with a considerable impact on cost. A decision during design phase will be made.

4.22 Sterlington 115 kv Tie Line from auto transformer #4 to 115kv bus rated for 600 MVA

Scope of work

- Remove 0.3 mile of transmission line including poles, insulators, conductors, shield wire, guy wire, etc.

- Install 0.3 mile of single pole, double circuit transmission line using 2x1780 ACSR Chukar conductor, polymer insulators, 24 fiber 0.528” dia. OPGW shield wire, and vibratory pile foundations where required.

- Install 0.3 mile of single pole, single circuit transmission line using 2x1780 ACSR Chukar conductor, polymer insulators, 24 fiber 0.528” dia. OPGW shield wire, and vibratory pile foundations where required.

Long Delivery items with lead times: Equipment Quantity Lead

Poles 8 16 weeks

Foundations 6 16 weeks

1780 ACSR Chukar 25000 lbs 12 weeks

0.528 OPGW 2000 ft 14 weeks

Polymer insulators 33 10 weeks Lead time as of June 2008

Construction Methodology, duration of construction and outages required: An outage will be required on the #3 Auto tie line. Outages may be required on sections of substation bus. Construction methodology will be determined during detailed design.

Assumptions made in scoping and estimates:

- Foundations will be needed on approximately 75% of the structures - Necessary line outages and substation bus outages to perform work are obtainable.

4.23 North Bastrop Reliability Project

See the attached Project Execution plan.

Page 42: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 42 of 52

Entergy has currently deferred this project beyond 2013 and should this project be not completed by the time customer commences work on this OASIS, cost associated with this project will be borne by the customer. 5. COSTS The ICT has reviewed and determined whether each required upgrade is considered a Base Plan Upgrade or a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT. The costs shown in the table include indirect cost (45%), but do not include tax gross up. The estimated tax gross-up rate is 30.948%. The costs shown are considered to be accurate to within +/-25%.

Projected Costs in 2008 dollars w/o escalation and tax gross up

Description Option 2 Cost including 45% indirect

Option 3 Cost including 45% indirect

Substations:

4.1 Sterlington 115 kV bus split & relocate Walnut Grove $4,800,256

4.2 Sterlington 500 kV, XFMR # 2 to 750 MVA $15,095,141

4.3 Baxter Wilson – add 500 kV XFMR from Sterlington $12,391,140

4.4 Riser 115 kV – add 43.2 MVAR Capacitor bank $823,523

4.5 Walnut Grove 115 kV – add 43.2 MVAR Capacitor bank $955,442

4.6 Swartz 115 kV – Communication upgrade $168,670

4.7 Rilla 115 kV – Upgrade switches $111,392

4.8 Selman Field 115 kV – Upgrade Transformer $4,540,847

4.9 Bastrop 115 kV – Replace breaker & switches $402,281

4.19 Sterlington 500 kV 4th transformer 600 MVA $17,788,932 4.20Sterlington 115kV(Split bus, relocate Walnut Grove (Lamkin) line &add 4thtrans) $3,568,159

4.21 Install 2nd 500 kV transformer at Baxter Wilson $21,455,436

Lines:

4.10 Walnut Grove – Swartz 115 kV line upgrade $7,696,600

4.11 Sterlington 115 kV tie-line – for 750 MVA transformer $276,325

4.12 Relocate Tallulah dead-end Tower – Baxter Wilson S/S $229,100

4.13 Sterlington IPCO 115 kV line upgrade $4,296,071

4.14 IPCO - Bastrop 115 kV line upgrade $3,537,798

4.15 Bastrop – N Bastrop – Log Cabin 115 kV line upgrade $6,643,193

4.16 N Bastrop Tap – N Bastrop 115 kV upgrade $0

4.17 Frostkraft - Rilla 115 kV line upgrade $2,407,627

4.18 Relocate Walnut Grove (Lamkin) to new bay on the 115kV Sterlington bus # 2 $229,100 4.22 Sterlington - 115 kV tie-line for new 600 MVA 4th transformer $459,650

4.23 North Bastrop Reliability Project* $17,982,408 $17,982,408

Total with OH and excluding TGU $82,357,814 $61,483,685

Note: The indirect cost could vary from those existing used at the time of this study

The cost of purchasing expensive energy during line or substation element outages is not included in the above cost. * North Bastrop reliability project estimates developed in 2007 have been adjusted by 6% to accommodate price increase and make it equivalent to 2008 dollars

Page 43: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 43 of 52

ICT Cost Allocation

Option 2 Option 3

Description Base Plan Upgrade

Supplemental Upgrade

Base Plan Upgrade

Supplemental Upgrade

Substations:

4.1 Sterlington 115 kV bus split & relocate Walnut Grove

$4,800,256

4.2 Sterlington 500 kV, XFMR # 2 to 750 MVA $15,095,141

4.3 Baxter Wilson – add 500 kV XFMR from Sterlington

$12,391,140

4.4 Riser 115 kV – add 43.2 MVAR Capacitor bank $823,523

4.5 Walnut Grove 115 kV – add 43.2 MVAR Capacitor bank $955,442

4.6 Swartz 115 kV – Communication upgrade $168,670 $168,670

4.7 Rilla 115 kV – Upgrade switches $111,392 4.8 Selman Field 115 kV – Upgrade Transformer $4,540,847 4.9 Bastrop 115 kV – Replace breaker & switches $402,281 4.19 Sterlington 500 kV 4th transformer 600 MVA $17,788,932

4.20Sterlington 115kV(Split bus, relocate Walnut Grove (Lamkin) line &add 4thtrans) $3,568,159

4.21 Install 2nd 500 kV transformer at Baxter Wilson $21,455,436

Lines: 4.10 Walnut Grove – Swartz 115 kV line upgrade $7,696,600 $7,696,600

4.11 Sterlington 115 kV tie-line – for 750 MVA transformer $276,325 4.12 Relocate Tallulah dead-end Tower – Baxter Wilson S/S $229,100 $229,100

4.13 Sterlington IPCO 115 kV line upgrade $4,296,071

4.14 IPCO - Bastrop 115 kV line upgrade $3,537,798 4.15 Bastrop – N Bastrop – Log Cabin 115 kV line upgrade $6,643,193 4.16 N Bastrop Tap – N Bastrop 115 kV upgrade $0

4.17 Frostkraft - Rilla 115 kV line upgrade $2,407,627 4.18 Relocate Walnut Grove (Lamkin) to new bay on the 115kV Sterlington bus # 2 $229,100

4.22 Sterlington - 115 kV tie-line for new 600 MVA 4th transformer $459,650

4.23 North Bastrop Reliability Project* $17,982,408 $17,982,408

Total Cost (2008 dollars) $17,982,408 $64,375,406 $17,982,408 $51,595,647 Note: The indirect cost could vary from those existing used at the time of this study

Page 44: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 44 of 52

The cost of purchasing energy during line or substation element outages is not included in the above cost. * North Bastrop reliability project estimates developed in 2007 have been adjusted by 6% to accommodate price increases and make it equivalent to 2008 dollars.

6. SCHEDULE Purpose of this section is to determine if the longest duration for an activity would exceed the start date of the requirement for power delivery identified in section 1. A detailed schedule will be prepared subsequent to customer approval. If outage cannot be obtained or must be sequenced due to seasonal requirements, additional time will be required to complete the upgrades. The following are rough durations

Project Definition

Includes surveys, soil borings, and Project Execution Plan - 24 Weeks

Transmission Lines Includes design, ROW acquisition, permits, material procurement, and construction - 52 weeks

Substations Includes design, material procurement (transformer the longest delivery item), and construction - 116 weeks Notes to Duration Schedules:

• Most of the construction work requiring outages will be performed during off-peak load season. Line outages will be discussed with the SOC and TOC and the assumption is made that line outages will be executed as planned. However, last minute denial of outages by the SOC/TOC along with resulting schedule delay is possible.

• Transmission Line and Substation projects will begin subsequent to Definition phase Project Execution Plan

• Schedule durations are high level estimates at this time. Upon project approval, a detailed schedule will be produced.

• Based on the project duration schedule, the upgrades necessary to facilitate granting of this service will not be completed prior to the requested start of service. Should approval to proceed be given in August 2008, construction will not be completed until August 2011. Should the transformer be ordered in August 2008, we could save 5 months and in-service could be achieved by March 2011.

Page 45: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 45 of 52

7. CONFIRMED RESERVATIONS OASIS# PSE MW Begin End 140912 NRG Power Marketing 103 01/01/98 01/01/08 250778 (delisting) Entergy Services, Inc. (EMO) 1 07/02/98 07/01/11 392740 Ameren Energy Inc. 165 04/12/99 01/01/09 569011 Entergy Services, Inc. (EMO) 242 03/01/00 01/01/14 731017 South Mississippi Electric Power

Assoc. 75 01/01/01 06/01/09

759196 Entergy Services (EMO) 143 01/01/01 01/01/21 759294 East Texas Electric Cooperative 31 01/01/01 01/01/18 810207 South Mississippi Electric Power

Assoc. 300 01/01/02 01/01/20

810234 South Mississippi Electric Power Assoc.

300 01/01/02 01/01/20

850239 Municipal Energy Agency of Mississippi

19 05/01/01 01/01/10

850304 Municipal Energy Agency of Mississippi

13 05/01/01 06/01/10

851493 Municipal Energy Agency of Mississippi

13 05/01/01 06/01/10

1019492 South Mississippi Electric Power Assoc.

51 01/01/02 01/01/18

1024194 City Water & Light, Jonesboro 83 01/01/03 01/01/10 1024198 City Water & Light, Jonesboro 168 01/01/03 01/01/10 1035455 South Mississippi Electric Power

Assoc. 280 01/01/03 01/01/08

1036858 South Mississippi Electric Power Assoc.

280 01/01/08 01/01/21

1084342 East Texas Electric Cooperative 50 01/01/05 01/01/09 1084344 East Texas Electric Cooperative 50 01/01/05 01/01/09 1084345 East Texas Electric Cooperative 75 01/01/05 01/01/09 1096986 Tennessee Valley Auth BPT 73 09/01/03 09/01/13 1099991 City Water & Light Jonesboro 83 01/01/10 01/01/16 1099997 City Water & Light, Jonesboro 168 01/01/10 01/01/16 1105665 Entergy Services, Inc. (EMO) 185 02/01/03 02/01/16 1105666 Entergy Services, Inc. (EMO) 91 02/01/03 02/01/27 1105668 Entergy Services, Inc. (EMO) 206 02/01/03 02/01/27

Page 46: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 46 of 52

OASIS# PSE MW Begin End 1126821 Entergy Services, Inc. (EMO) 101 05/01/04 05/01/29 1139973 South Mississippi Electric Power

Assoc. 95 05/01/03 12/30/28

1139975 South Mississippi Electric Power Assoc.

95 05/01/04 12/31/29

1139977 South Mississippi Electric Power Assoc.

95 05/01/05 12/31/29

1139982 South Mississippi Electric Power Assoc.

130 01/01/03 01/01/20

1151106 Entergy Services, Inc. (EMO) 20 06/01/10 06/01/29 1161925 Cleco Power LLC (Gen) 12 08/01/03 01/01/10 1161927 Cleco Power LLC (Gen) 7 08/01/03 01/01/10 1161928 Cleco Power LLC (Gen) 7 08/01/03 01/01/10 1168061 Entergy Services, Inc. (EMO) 80 08/01/04 02/01/28 1168408 Entergy Services, Inc. (EMO) 247 08/01/04 02/01/28 1192287 (1140407) Entergy Services, Inc. (EMO) 725 01/01/05 09/01/33 1202470 NRG Power Marketing 91 04/01/04 04/01/09 1210356 Entergy Services, Inc. (EMO) 290 07/01/05 07/01/07 1210357 Entergy Services, Inc. (EMO) 100 07/01/05 07/01/07 1272606 (renewal) Entergy Services, Inc. (EMO) 150 05/01/05 05/01/07 1286481 Merrill Lynch Commodities 11 01/01/00 01/01/10 1289686 (delisting) Entergy Services Inc. (EMO) 1 06/01/07 06/01/30 1294132 Entergy Services, Inc. (EMO) 526 01/01/06 01/01/35 1309874 East Texas Electric Cooperative 75 01/01/09 01/01/17 1309875 East Texas Electric Cooperative 50 01/01/09 01/01/17 1309876 East Texas Electric Cooperative 50 01/01/09 01/01/17 1310448 (1284799)

(delisting) Entergy Services Inc. (EMO) 1 06/01/07 06/01/30

1321868 (renewal) NRG Power Marketing 320 01/01/06 01/01/07 1328125 CLECO Power Marketing 35 01/01/06 01/01/11 1338849 Louisiana Energy & Power

Authority 45 9/1/2005 9/1/2010

1340017 Plum Point Energy Associates 40 03/01/10 03/01/40 1340019 Plum Point Energy Associates 35 03/01/10 03/01/40 1340028 Plum Point Energy Associates 50 03/01/10 03/01/30

Page 47: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 47 of 52

OASIS# PSE MW Begin End 1340029 Plum Point Energy Associates 50 03/01/10 03/01/30 1340665 Entergy Services, Inc. (EMO) 200 01/01/06 01/01/09 1340673 Entergy Services, Inc. (EMO) 50 06/01/07 06/01/08 1340674 Entergy Services, Inc. (EMO) 50 06/01/08 06/01/09 1346435 Entergy Services, Inc. (EMO) 100 06/01/07 06/01/08 1346437 Entergy Services, Inc. (EMO) 100 06/01/08 06/01/09 1346440 Entergy Services, Inc. (EMO) 200 06/01/07 06/01/08 1346441 Entergy Services, Inc. (EMO) 200 06/01/08 06/01/09 1346444 Entergy Services, Inc. (EMO) 179 02/01/07 02/01/08 1348508 CLECO Power Marketing 10 01/01/06 01/01/10 1352704 (1340032) Plum Point Energy Associates 5 03/01/10 03/01/40 1353140 Constellation Energy Group 10 01/01/06 01/01/07 1353141 Constellation Energy Group 5 01/01/06 01/01/07 1353344 (renewal) Merrill Lynch Commodities 85 10/01/05 10/01/06 1353393 (renewal) Merrill Lynch Commodities 4 11/01/05 11/01/06 1356328 Municipal Energy Agency of

Mississippi 40 06/01/10 06/01/40

1366979 MidAmerican Energy 50 01/01/06 01/01/07 1366980 MidAmerican Energy 50 01/01/06 01/01/07 1366981 MidAmerican Energy 50 01/01/06 01/01/07 1366982 MidAmerican Energy 50 01/01/06 01/01/07 1371416 NRG Power Marketing 100 03/01/06 03/01/07 1371481 (delisting) Entergy Services, Inc. (EMO) 1 01/01/06 01/01/07 1372645 Morgan Stanley Commodities

Group 102 01/01/07 01/01/08

1372646 Morgan Stanley Commodities Group

102 01/01/07 01/01/08

1373112 Louisiana Energy & Power Authority

61 01/01/06 01/01/07

1373643 City of Conway 25 03/01/10 03/01/40 1373714 East Texas Electric Cooperative 63 01/01/10 01/01/30 1375001 NRG Power Marketing 3 07/01/06 07/01/07 1375299 Louisiana Generating LLC 11 03/01/06 03/01/11 1375300 Louisiana Generating LLC 8 03/01/06 03/01/11 1375301 Louisiana Generating LLC 5 03/01/06 03/01/11 1375559 CLECO Power LLC 675 12/01/06 12/01/16

Page 48: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 48 of 52

OASIS# PSE MW Begin End 1376208 Louisiana Energy & Power

Authority 6 02/01/06 02/01/07

1380484 Osceola Light & Power 9 09/01/09 09/01/39 1381068 Plum Point Energy Associates 100 06/01/10 06/01/11 1381247 Constellation Energy Group 140 01/01/06 01/01/07 1381248 (1349801) City of West Memphis 70 01/01/06 01/01/07 1381312 Constellation Energy Group 240 01/01/06 07/01/07 1381317 Constellation Energy Group 70 01/01/06 01/01/07 1381318 Constellation Energy Commodities

Group 70 01/01/06 01/01/07

1381322 Constellation Energy Commodities Group

6 01/01/06 06/01/07

1381398 Constellation Energy Group 34 01/01/06 01/01/36 1381400 Constellation Energy Group 34 01/01/06 01/01/36 1381404 Constellation Energy Group 17 01/01/06 01/01/36 1381406 (1325187) Constellation Energy Group 17 01/01/06 01/01/36 1382543 Mid American Energy Company 100 03/01/06 03/01/07 1382544 Mid American Energy Company 100 03/01/06 03/01/07 1383852 AECC 550 01/01/07 01/01/17 1385131 Ameren 12 06/01/06 06/01/07 1385835 (1363730) City of Prescott 22 04/01/06 04/01/09 1385842 South Mississippi Electric Power

Assoc. 100 38

01/01/09 01/01/10

01/01/10 01/01/11

1387272 CLECO Power 11 04/01/06 04/01/16 1387274 CLECO Power 16 04/01/06 04/01/07 1387275 CLECO Power 16 04/01/07 04/01/08 1389008 NRG Power Marketing 270 06/01/07 06/01/08 1389848 Louisiana Energy & Power

Authority 6 02/01/07 02/01/08

1389848 Louisiana Energy & Power Authority

6 02/01/07 02/01/08

1393874 NRG Power Marketing 5 09/01/06 09/01/07 1394479 Louisiana Generating LLC 2 06/01/06 06/01/07 1396788 Constellation Energy Commodities 70 06/01/06 06/01/07 1401985 Constellation Commodities Group 42 08/01/06 08/01/36 1403756 Constellation Commodities Group 100 01/01/07 01/01/08

Page 49: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 49 of 52

OASIS# PSE MW Begin End 1403757 Constellation Commodities Group 100 01/01/07 01/01/08 1406786 South Mississippi Electric Power

Assoc. 100 04/01/10 04/01/40

1407894 Morgan Stanley Commodities Group

102 01/01/08 01/01/09

1407895 Morgan Stanley Commodities Group

102 01/01/08 01/01/09

1408199 South Mississippi Electric Power Assoc.

100 04/01/10 04/01/40

1408981 NRG 92 01/01/07 01/01/10 1410022 (1340037) City of North Little Rock 60 03/01/10 03/01/40 1412068 NRG 103 01/01/07 01/01/08 1413110 NRG Power Marketing 100 01/01/07 01/01/09 1413255 American Electric Power Service

Corp 225 01/01/07 01/01/09

1414925 Constellation Commodities Group 22 01/01/07 01/01/08 1414927 Constellation Commodities Group 50 01/01/07 01/01/08 1416650 NRG Power Marketing 100 01/01/07 01/01/08 1422496 Constellation Commodities Group 57 01/01/07 01/01/08 1422498 Constellation Commodities Group 9 01/01/07 01/01/08 1425495 East Texas Electric Cooperative 50 03/01/10 03/01/45 1431621 South Mississippi Electric Power

Assn. 200 01/01/07 01/01/08

1432487 Arkansas Electric Cooperative Corp.

50 12/01/07 12/01/19

1443976 (1424383) Constellation Commodities Group 9 01/01/07 01/01/08 1435972 Entergy Services, Inc. (EMO) 150 05/01/07 05/01/10 1435973 Entergy Services, Inc. (EMO) 135 05/01/08 05/01/10 1436590 MidAmerican Energy 50 01/01/07 01/01/08 1436591 MidAmerican Energy 50 01/01/07 01/01/08 1436592 MidAmerican Energy 50 01/01/07 01/01/08 1436593 MidAmerican Energy 50 01/01/07 01/01/08 1440358 NRG Power Marketing 100 03/01/07 03/01/08 1442295 NRG Power Marketing 3 07/01/07 07/01/09 1442453 NRG Power Marketing 320 06/01/07 06/01/26 1448054 NRG Power Marketing 103 01/01/08 01/01/09

Page 50: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 50 of 52

OASIS# PSE MW Begin End 1448057 NRG Power Marketing 103 01/01/08 01/01/09 1449494 Entergy Services, Inc. (EMO) 154 06/01/07 06/01/09 1449495 Entergy Services, Inc. (EMO) 322 06/01/09 06/01/59 1449881 Cargill Power 103 01/01/08 01/01/09 1452308 NRG Power Marketing 100 01/01/08 01/01/09 1452603 NRG Power Marketing 100 09/01/07 09/01/08 1435303 East Texas Electric Coop 150 01/01/07 01/01/40 1453402 NRG Power Marketing 103 01/01/09 01/01/10 1456636 CLECO Power LLC 10 10/01/07 10/01/12 1458787 Louisiana Energy & Power

Authority 2 03/31/07 03/31/08

1464028 East Texas Electric Coop 168 01/01/10 01/01/40 1466197 NRG Power Marketing 206 01/01/09 01/01/10 1466561 Constellation Energy 50 01/01/08 01/01/09 1466562 Constellation Energy 25 01/01/08 01/01/09 1470811 East Texas Electric Coop 186 01/01/10 01/01/40 1477069 Entergy Services 10 11/01/07 11/01/37 1477256 NRG Power Marketing 103 01/01/08 01/01/09 Pre-888 Transactions

OASIS # PSE MW Begin End 1219160 NRG Power Marketing 91 04/01/09 04/01/141306068 Entergy Services, Inc. (EMO) 1718 02/01/05 01/01/071306069 Entergy Services, Inc. (EMO) 741 02/01/05 01/01/071306070 Entergy Services, Inc. (EMO) 1867 02/01/05 01/01/071306071 Entergy Services, Inc. (EMO) 1142 02/01/05 01/01/071306072 Entergy Services, Inc. (EMO) 59 02/01/05 01/01/071306073 Entergy Services, Inc. (EMO) 148 02/01/05 01/01/071306074 Entergy Services, Inc. (EMO) 194 02/01/05 01/01/071306075 Entergy Services, Inc. (EMO) 1157 02/01/05 01/01/071306076 Entergy Services, Inc. (EMO) 1219 02/01/05 01/01/071306077 Entergy Services, Inc. (EMO) 683 02/01/05 01/01/071306078 Entergy Services, Inc. (EMO) 140 02/01/05 01/01/071306079 Entergy Services, Inc. (EMO) 456 02/01/05 01/01/071306080 Entergy Services, Inc. (EMO) 739 02/01/05 01/01/071306081 Entergy Services, Inc. (EMO) 183 02/01/05 01/01/071306082 Entergy Services, Inc. (EMO) 64 02/01/05 01/01/071306083 Entergy Services, Inc. (EMO) 870 02/01/05 01/01/071306084 Entergy Services, Inc. (EMO) 129 02/01/05 01/01/071306085 Entergy Services, Inc. (EMO) 140 02/01/05 01/01/071306086 Entergy Services, Inc. (EMO) 130 02/01/05 01/01/07

Page 51: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 51 of 52

OASIS # PSE MW Begin End 1306087 Entergy Services, Inc. (EMO) 65 02/01/05 01/01/071306088 Entergy Services, Inc. (EMO) 947 02/01/05 01/01/071306089 Entergy Services, Inc. (EMO) 61 02/01/05 01/01/071306090 Entergy Services, Inc. (EMO) 304 02/01/05 01/01/071306092 Entergy Services, Inc. (EMO) 351 02/01/05 01/01/071306094 Entergy Services, Inc. (EMO) 692 02/01/05 01/01/071306095 Entergy Services, Inc. (EMO) 1641 02/01/05 01/01/071306096 Entergy Services, Inc. (EMO) 433 02/01/05 01/01/071306097 Entergy Services, Inc. (EMO) 1926 02/01/05 01/01/071306098 Entergy Services, Inc. (EMO) 946 02/01/05 01/01/071306099 Entergy Services, Inc. (EMO) 1233 02/01/05 01/01/071332606 East Texas Electric Cooperative 55 01/01/06 01/01/171412155 Entergy Services, Inc. (EMO) 1718 01/01/07 01/01/381412156 Entergy Services, Inc. (EMO) 741 01/01/07 01/01/381412158 Entergy Services, Inc. (EMO) 1867 01/01/07 01/01/381412160 Entergy Services, Inc. (EMO) 1142 01/01/07 01/01/381412161 Entergy Services, Inc. (EMO) 59 01/01/07 01/01/381412162 Entergy Services, Inc. (EMO) 148 01/01/07 01/01/381412163 Entergy Services, Inc. (EMO) 194 01/01/07 01/01/381412164 Entergy Services, Inc. (EMO) 1157 01/01/07 01/01/381412165 Entergy Services, Inc. (EMO) 1219 01/01/07 01/01/381412166 Entergy Services, Inc. (EMO) 683 01/01/07 01/01/381412167 Entergy Services, Inc. (EMO) 140 01/01/07 01/01/381412168 Entergy Services, Inc. (EMO) 456 01/01/07 01/01/381412169 Entergy Services, Inc. (EMO) 739 01/01/07 01/01/381412170 Entergy Services, Inc. (EMO) 183 01/01/07 01/01/381412171 Entergy Services, Inc. (EMO) 64 01/01/07 01/01/381412172 Entergy Services, Inc. (EMO) 870 01/01/07 01/01/381412173 Entergy Services, Inc. (EMO) 129 01/01/07 01/01/381412174 Entergy Services, Inc. (EMO) 140 01/01/07 01/01/381412175 Entergy Services, Inc. (EMO) 130 01/01/07 01/01/381412176 Entergy Services, Inc. (EMO) 65 01/01/07 01/01/381412177 Entergy Services, Inc. (EMO) 947 01/01/07 01/01/381412178 Entergy Services, Inc. (EMO) 61 01/01/07 01/01/381412179 Entergy Services, Inc. (EMO) 304 01/01/07 01/01/381412180 Entergy Services, Inc. (EMO) 351 01/01/07 01/01/381412181 Entergy Services, Inc. (EMO) 692 01/01/07 01/01/381412182 Entergy Services, Inc. (EMO) 1641 01/01/07 01/01/381412183 Entergy Services, Inc. (EMO) 433 01/01/07 01/01/381412184 Entergy Services, Inc. (EMO) 1926 01/01/07 01/01/381412185 Entergy Services, Inc. (EMO) 946 01/01/07 01/01/381412186 Entergy Services, Inc. (EMO) 1233 01/01/07 01/01/38

Page 52: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

EMO OUACHITA OASIS 1478781- Options 2&3 Facilities Study

Entergy Transmission Business Page 52 of 52

8. STUDY QUEUE

OASIS PSE MW Begin End 1460876 Aquila Networks – MPS 75 03/01/09 03/01/291460878 Aquila Networks – MPS 75 03/01/09 03/01/291460879 Aquila Networks – MPS 75 03/01/09 03/01/291460881 Aquila Networks – MPS 75 03/01/09 03/01/291460900 Louisiana Energy & Power Auth 116 01/01/09 01/01/301468113 Muni energy Agcy of Miss 20 06/01/11 06/01/411468285 Mid American Energy 103 09/01/07 09/01/081468286 Mid American Energy 103 09/01/07 09/01/081470484 City of W. Memphis 20 01/01/11 01/01/411471303 Cargill Power Markets, LLC 103 01/01/08 01/01/091475343 Constellation Energy 25 01/01/08 01/01/091477639 Westar Energy Generation & Mktg 27 06/01/10 06/01/401477639 Westar Energy Generation & Mktg 15 06/01/10 06/01/11 9. Attachments

A. One Line Drawings

Description Page Baxter Wilson M3020SO5 Sterlington 115kV A Sterlington B Sterlington 500kV C Sterlington to Bastrop – PEP Rev. 3 D

Page 53: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

C:\T

EM

P\A

M-W

ork\

mro

uss1

\M-C

ctap

etsp

047,

D-T

Doc

s,S-

Tem

plat

e\E

MI\S

ubst

atio

n\St

atio

n O

nelin

es\M

3020

SO5.

DW

G, 1

1/5/

2007

8:2

9:28

AM

, mro

uss1

Page 54: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington
jdl0107
Typewritten Text
A
Page 55: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington
jdl0107
Typewritten Text
B
Page 56: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington
jdl0107
Typewritten Text
C
Page 57: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Transmission / Substation ProjectsCompany: Entergy Transmission

Customer: N.LA

Work Order Numbers: TL9575 – Sterlington to North Crossett Line cut-in; TL9582 – Log Cabin S/S to

North Bastrop fiber optic installation; TS9575 – North Bastrop; TSXXXX – Sterlington; TSXXXX –

Bastrop; TSXXXX – Oak Grove; TSXXXX – North Crossett; TSxxxx – Log Cabin

Funding Project Number: F1PCU75170

Sterlington to Bastrop Project Cut-in line between Sterlington to North Crossett and bring new 7.0 mile of double circuit 1272 ACSR into North

Bastrop; Replace shield wire by 24 pair OPGW between North Bastrop and Log Cabin substation

(approximately 3.9m), replace splice box for OPGW outside Log Cabin by a 4 port box, extend OPGW from

splice box to Log Cabin S/S and install ADSS into relay room , replace power line carrier in Log Cabin relay

room by communication equipment for fiber optics for transmitting blocking signals for relay protection to Oak

Grove, Bastrop and N Bastrop, Convert North Bastrop to a 3-Breaker Substation; modify relaying at Sterlington,

North Crossett, Bastrop, Oak Grove

Revision: 3

Project Team:

Name Position Location Tel. E-Mail

Charles Newell Program Manager L-ATT-1B 504-463-2482 [email protected]

Will Hobdy Construction

Engineer M-MAYS-52 601-368-1625 [email protected]

Charlie Gambrell Construction M-MAYS-52 601-368-2000 [email protected]

Blake Henessey Communications M-TOMB-01 8-430-4431 [email protected]

John Sistrunk Asset Management L-WMO-ONT 318-651-6280 [email protected]

Jared Powell T-Line Design L-ATT-1D 504-463-7308 [email protected]

Hong-To Lam T-Line Design L-ATT-1D 504-463-1204 [email protected]

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 1 of 35

jdl0107
Typewritten Text
D
Page 58: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 2 of 35

Marnie Roussell Substation Engineer L-ATT-1C 504-463-7316 [email protected]

Greg Buisson Sr. Relay Engineer L-ATT-1B 504-463-7314 [email protected]

Tim Kern Relay Engineer L-AT&T-1B 504-463-2942 [email protected]

Tim Hall Settings Engineer L-ENT-17B 504-576-4775 [email protected]

Jerry Highstreet SCADA Engineer L-ENT-17B 504-576-4584 [email protected]

Paul Legrand T-Line Lead L-AT&T-1D 504-463-7062 [email protected]

Tammy Adams ROW / Vegetation L-WMO-ONT 318-651-6267 [email protected]

Jeff Spilyards Environmental A-TCBY-25E 501-371-3951 [email protected]

John Massey ROW L-WMO-ONT 318-651-6267 [email protected]

Ibrahim Khan Contract Project

Manager 504-812-2939 [email protected]

Page 59: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 3 of 35

P.E.P Revision History

Rev Issue Date Description of Revision Revised By Program Manager

A 5/7/04

Revised for Design Comments and

Issued to Construction, ROW,

Regulatory, Asset Management,

D-Lines, SCADA for Review and

Approval

Paul Legrand, Carlos

Cruz Montano,

Fernando Coye, Tim

Kern, Joe Bui, Jerry

Highstreet and Mark

Able

Charles Newell

B 5/24/04

Revised for Construction, ROW,

Regulatory, Asset Management,

D-Lines and SCADA Comments

and Issued to JET / Supervisors

for Review and Approval

Will Hobdy, Tammy

Adams, Murry

Witcher John

Sistrunk, Doug

Dollar, Paul Legrand,

Carlos Cruz

Montano, Fernando

Coye, Tim Kern, Joe

Bui, Jerry Highstreet

and Mark Able

Charles Newell

C 6/10/04

Revised for JET / Supervisor

Approval Comments and Issued

for Manager / Peer Group Review

and Approval

Paul Legrand, Steve

Parrish, Carlos Cruz

Montano, Brian Story,

Tim Kern, Terry

Clement, Milton

Bostic, Joe Bui, Dan

Glaser, Paul Leist

Charles Newell

0 7/19/04

Revised for Manager and Peer

Review Comments and Issued as

Revision 0 for Budget Approval

and Project Execution

Mark Able Charles Newell

Page 60: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 4 of 35

1 8/26/04

Revised for Changes to the Scope

of Work: 1) Add Conversion of Log

Cabin to a 3-Breaker Substation,

2) Revise North Bastrop to a 3-

Breaker Substation from a 4-

Breaker Substation, and 3) Revise

the 3.7 Mile North Bastrop Tap to

North Bastrop Rebuild to 0.2 Mile

North Bastrop Tap to Log Cabin

Rebuild

Carlos Cruz

Montano, Fernando

Coye, Paul Legrand,

Paul Leist, Will

Hobdy, Mark Able

Charles Newell

1A 3/26/07 Revised for team input Ibrahim Khan Charles Newell

1B 5/06/07

Revised deleting Log Cabin and

adding D/C to north Bastrop from

Log Cabin tap

Ibrahim Khan Charles Newell

1C 5/29/07 WH’s revised outage table and

sequence of construction Ibrahim Khan Charles Newell

1D 6/03/07 Edited including adding team

information Ibrahim Khan Charles Newell

2 06/07/07

Incorporated Marnie, Tim Kern,

Will Hobdy and Charlies comments

and submitted to PGM for

approvals

Ibrahim Khan Charles Newell

2A 7/12/07

Modified PEP - establishing 4

terminal network and for team

input

Ibrahim Khan Charles Newell

2B 8/7/07 Revised including revisions for

OPGW into Log Cabin Ibrahim Khan Charles Newell

3 8/14/07 Submitted to PGM for approval Ibrahim Khan Charles Newell

Page 61: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

TABLE OF CONTENTS PROJECT EXECUTION PLAN (P.E.P.)

TABLE OF CONTENTS ..............................................................................................................................................5

1. EXECUTIVE SUMMARY:................................................................................................................................7

2. PROJECT STRATEGIC PLANNING – Key Execution Strategies ...............................................................7

3. SCOPE: ................................................................................................................................................................8

3.1. DETAILED SCOPE STATEMENT........................................................................................................................8 3.2. SCOPE DETAILS ..............................................................................................................................................9 3.2.1. SUBSTATION(S)...........................................................................................................................................9 3.2.1.1. NORTH BASTROP TS9575:......................................................................................................................9 3.2.1.2. STERLINGTON TSXXXX:.....................................................................................................................16 3.2.1.3. OAK GROVE TSXXXX: .......................................................................................................................17 3.2.1.4. NORTH CROSSETT TSXXXX: ..............................................................................................................18 3.2.1.5. BASTROP TSXXXX: ............................................................................................................................20

3.2.1.6. Log Cabin TSXXXX:.......................................................................................................................21

3.2.2 SCADA:............................................................................................................................................22

3.2.3. TRANSMISSION LINES WORK....................................................................................................................22 3.2.3.1. STERLINGTON TO N. CROSSETT – NEW 7 MILE IN AND OUT TO NORTH BASTROP, TL9575: ................22 3.2.3.2. N. BASTROP TO LOG CABIN FIBER OPTIC - TL9582: ..............................................................................23

3.2.3.3. Distribution Wires Scope.............................................................................................................23

4. MATERIALS MANAGEMENT PLAN ..........................................................................................................23

5. PROJECT CONTROLS PLAN: ......................................................................................................................24

5.1. SCOPING ESTIMATE ......................................................................................................................................25

5.2. CASHFLOW....................................................................................................................................................25

5.3. BASELINE ESTIMATE ....................................................................................................................................26 5.4. BASELINE SCHEDULE ...................................................................................................................................26 5.5. CONTINGENCIES ...........................................................................................................................................26 5.6. OUTAGE PLAN..............................................................................................................................................28 5.6. GATE REVIEWS.............................................................................................................................................28

6. RESOURCE PLAN ...........................................................................................................................................28

7. QUALITY PLAN...........................................................................................................................................28

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 5 of 35

Page 62: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

8. CONSTRUCTION MANAGEMENT PLAN..............................................................................................29

9. RISK MANAGEMENT PLAN.....................................................................................................................31

10. REGULATORY, ROW, LEGAL AND ENVIRONMENTAL COMPLIANCE PLAN(S):....................32

11. PROJECT CLOSURE: .................................................................................................................................33

12. COMMUNICATIONS PLAN: .....................................................................................................................33

ATTACHMENTS:.............................................................................................................................................34

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 6 of 35

Page 63: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

1. EXECUTIVE SUMMARY:

The 115kV line from Sterlington to Bastrop in North Louisiana is 11 miles long. Loss of the

Sterlington to Bastrop 115kV line will result in 82% to 89% voltage levels from Bastrop to

Oak Grove to Darnel. The 115kV line from Sterlington to IPPCO cannot be opened most of

the year. The objective of this project is to build a transmission loop from Sterlington to

North Bastrop to Bastrop to relieve low voltages caused by single contingencies.

The benefits provided by this project will be to alleviate the anticipated violation of NERC

Planning Standard I.A.S2.M2 performance criteria associated with Category 'B'

contingencies.

Rejection of this project will prolong the transmission system's exposure to outages and

possible equipment damage and will result in violation of NERC Planning Standard

I.A.S2.M2.

The total estimated cost is $16,964,536 including $5,278,512 in indirect cost. See section 5,

page 26 for estimates, page 27 for cash flow by jurisdiction, and page 28 for list of

contingencies.

The target date for completion of the project is 03/31/09. Work at North Bastrop, lines and

remote stations will be completed in a sequential order starting in September 2008.

2. PROJECT STRATEGIC PLANNING – Key Execution Strategies

2.1. Assumptions and Their Potential Effects

− ROW for the 7m new transmission line has all been acquired in previous phase

except for one track.

− The wood pecker bird issue would amicably be resolved – otherwise diversion of line

and uncertainties including delay and escalation is cost would occur. (by the time of

revision 3 of this document, this issue has been resolved)

2.1.1. Availability of funds:

Funding approval (FP) should be completed by the end of September 2007 enabling

commencement of design and start of construction in February 2008.

2.1.2. Outage Assumptions:

Crippling outages will be available during the entire construction phase.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 7 of 35

Page 64: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

2.2. Entergy Safety Procedures and Guidelines

General safety policy and guidelines are provided in the “Entergy Transmission Safety

Manual”, which can be accessed via link:

http://lr_web.ar.entergy.com/op_supp/safety/manual/manual.htm

3. SCOPE:

3.1. Detailed Scope Statement

The 115kV line from Sterlington to Bastrop in North Louisiana is 11 miles long. Loss of the

Sterlington to Bastrop 115kV line will result in 82% to 89% voltage levels from Bastrop to

Oak Grove to Darnel. The 115kV line from Sterlington to IPPCO cannot be opened most of

the year. The objective of this project is to build a transmission loop to relieve low voltages

caused by single contingencies.

The current proposal is to tap the existing line from Sterlington to North Crossett and build

7.0 miles of double-circuit 1272 ACSR In-and-Out line to the North Bastrop substation.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 8 of 35

Page 65: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Crossett North (Replace relaying)

An existing 115kV line from North Bastrop to Log Cabin S/S will be terminated into a new

breaker at North Bastrop. The existing 3.7 mile of shield wire between North Bastrop &

Basrtop tap will be replaced by OPGW (24 fibers). Existing splice box outside Log Cabin will

be replaced by a 4 port box. It will house OPGW from Bastrop, N Bastrop, Oak Grove and

OPGW going to Log Cabin and connections will be made to communicate between all 4

ends. Existing shield wire between pole outside Log Cabin and Log Cabin will be replaced

by OPGW from the splice box. One splice box will be installed inside Log Cabin on A frame

for termination of OPGW and from the splice box ADSS cable will be installed inside a

buried conduit leading into the relay room for termination into fiber optic SEL-2510

communication equipment.

Blocking scheme at Log Cabin will be modified removing power line carrier keying. Instead,

the fiber optic communication will be used for this purpose. All work will be done at Entergy

expense but equipment ownership and maintenance will be by LAGen.

The T-line spans inside the North Bastrop substation will be relocated from over the new

expansion to an adjacent area.

The North Bastrop substation will be upgraded to a two-bus substation consisting of three

(3) line bays with breakers and two (2) transformer bays.

Exisiting OPGW as shield

Sterlington (Modify Communication & relaying)

IPCO

Bastrop (Modify Communication & relaying)

Oak Grove (Modify communication & relaying)

Gallion Log Cabin (Replace existing PLC communication with digital)

North Bastrop (Convert to 3 breakers, install

communication & relaying)

Build new 7.0 mile double circuit

Replace 3.7 mile shield wire with OPGW shield wire

Old North Bastrop tap

Exisiting OPGW as shield

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 9 of 35

Page 66: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Modifications will also be made to line relaying at Sterlington, North Crossett, Bastrop and

Oak Grove.

New Multiplexing communication equipment will be installed at North Bastrop, Bastrop

Sterlington and Oak Grove. This will increase the capacity of the eight fiber backbone

system, allowing digital protection, SCADA, intranet and voice communication at North

Bastrop Substation /Service center, Bastrop, Sterlington, and Oak Grove. The existing West

Monroe/Greenville fiber optic backbone will need to be severed at Log Cabin, breaking out

four of the eight existing fibers (backbone) between Bastrop and Oak Grove and connecting

the four fiber pairs to the new fibers going into to North Bastrop.

3.2. Scope Details

3.2.1. Substation(s)

3.2.1.1. North Bastrop TS9575:

The North Bastrop substation will be upgraded to a two bus station with three (3) line

bays with breakers.

3.2.1.1.1. Site Work

Significant site work needs to be performed at North Bastrop Substation to address

drainage problems while this major expansion project takes place. This plan provides for

the following:

- The site survey was performed in 2004

- Soil borings were ordered in April 2007

- Strip grass and sterilize topsoil.

- Grade new area of substation.

- Install new drainage.

- Add a 6” layer of crushed rock.

- Extend fence to allow installation of new operating bus and addition of new

transmission line bays for Sterlington and Crossett North lines. This work includes

removal of southeast section of existing fence (approximately 270’) and

installation of new access gates.

- Modify and extend access road to allow maintenance vehicles to access breakers.

3.2.1.1.2. Foundation Work

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 10 of 35

Page 67: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

A special consideration will be addressed during detailed design for the new control

house. Substation drainage problems will be addressed in the site portion of the scope.

Also, the substation has experienced occasional flooding over the past years due to a

nearby creek. Consequently, the foundation for the new control house will be set at least

24” higher than other foundations to eliminate flood possibility. The foundation scope for

this project is as follows:

- Remove one slab foundation 1.5 cyds (storage building) to accommodate the new

control house:

- Install new foundations for the following structures and equipment:

- one (1) AX tower

- two (2) AM towers

- five (5) “CE” towers

- forty-five (45) bus support columns – (39) low bus and (6) high

- three (3) 115kV breakers

- eight (8) E towers

- one (1) outdoor alarm junction box

- two (2) 115kV circuit switchers

- two (2) junction box foundations near transformer for slip over CT’s

- one (1) 16’x 36’ control building

- Install new perimeter grounding and connect to fence, access gates, and existing

ground grid as per Entergy standards. Tie all new foundations to ground grid.

- Install new section of cable trough for new breakers and tie to new control building

and existing trough.

- Install conduit as required

3.2.1.1.3. Electrical Work

Crossett North Line Bay: Install new transmission line bay for consisting of the following equipment:

- One(1) AX tower with shield extension as a lead in structure with one A phase line

trap hung in suspension to bus below supported by detail ”Y” bus support brackets

- Four (4) “E” tower for one CVT with associated junction box and three (3)

metering CT’s with one junction box

- One (1) AM tower with steel for switch operating mechanisms and CVT mounting

shelf to accommodate arresters

- one (1) “CE” tower,

- one (1) 115kV 2000A vertical break disconnect switch with ground

- two (2) 115kV 2000A vertical break disconnect switches,

- one (1) 115kV 2000A 40kA breaker

- three (3) arresters

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 11 of 35

Page 68: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

- Bus, insulators and fittings.

Sterlington Line Bay: Install new transmission line bays consisting of the following equipment:

- One (1) AM tower with steel for switch operating mechanisms

- one (1) “CE” tower

- one (1) “E” Tower

- one (1) 115kV 2000A vertical break disconnect switch with ground

- two (2) 115kV 2000A vertical break disconnect switches

- one (1) 115kV 2000A 40kA breaker

- three (3) arresters mounted per drawing L0070E50

- mount A phase CVT with junction box per drawing L0070E50

- Bus, insulators and fittings.

Log Cabin Line Bay: Remove the following equipment

- One (1) coupling capacitor unit

- One (1) line tuning unit

Replace the motor operator on switch R4335 with a swing handle manual operator

Complete existing line bay for new bus arrangement:

- one (1) “CE” tower,

- two (2) 115kV 2000A vertical break disconnect switches,

- one (1) 115kV 2000A 40kA breaker

- three (3) arresters mounted on per drawing L0070E50

- install A phase CVT with junction box on existing E tower

- Bus, insulators and fittings.

Transformer #X168 Bay: Remove spring-operated ground switch

Replace the motor operator on switch R3543 with a swing handle manual operator

Connect the existing transformer #X168 bay to the new operating bus with the

following new equipment and structures:

- One (1) “CE” tower

- one (1) 115kV 2000A vertical break disconnect switch

- one (1) 115kV 1200A circuit switcher mounted on 16’ structure.

- Three (3) high single phase bus supports columns

- bus, insulators and fittings.

Replace three (3) existing HV arresters and install three (3) LV arresters. Mounting

brackets may be required.

Install slip over CT’s on high voltage bushings of transformer and associated conduit

and junction box near transformer #168.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 12 of 35

Page 69: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Transformer #X185 Bay:

Remove Mark V circuit switcher R7160. This will be replaced by a switch.

Connect the existing transformer #X185 bay to the new operating bus with the

following new equipment and structures:

- one (1) “CE” tower

- two (2) 115kV 2000A vertical break disconnect switch (one replaces circuit

switcher R7160

- one (1) 115kV 1200A circuit switcher mounted on 16’ structure.

- three (3) high single phase bus supports columns

- bus connections, insulators and fittings.

Replace three (3) existing HV arresters and install three (3) LV arresters. Mounting

brackets may be required.

Install slip over CT’s on high voltage bushings of transformer and associated conduit

and junction box near transformer #185.

General/Common Equipment:

- Extend existing operating bus (designer to match elevation of existing bus): twelve

(12) single phase low bus support columns, insulators and aluminum tubing. This

will become the transfer bus.

- Install new operating bus: thirty-three (33) single phase low bus support columns,

insulators and aluminum tubing.

- Three (3) E towers for operating bus CVT’s with one junction box

- Install steel to mount one outdoor alarm junction box, 36” x 42”

- Install six (6) lighting fixtures (one per bay).

- Install one (1) new pre-fabricated control building (16’ x 36’).

- Remove one (1) small storage building to accommodate the new control house

- Designer to perform lightning protection analysis and provide lightning protection

as required (cost to provide lightning protection, if needed, is not included in the

cost estimate).

3.2.1.1.4. Relay/Configuration

North Crossett Line Bay:

- Install one (1) standard line/breaker control panel with unblocking carrier scheme,

using the Pulsar UPLC carrier.

- Install one (1) 2000A line trap relocated from Sterlington.

- Install one (1) 115kV CCVT with carrier accessories for indication, synch check

and carrier transmission.

- Install one (1) line tuner.

- Install one (1) CCVT line potential junction box.

- Install three (3) metering CT’s for company inter-tie.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 13 of 35

Page 70: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Sterlington Line Bay:

- Install one (1) standard line/breaker control panel with fiber connection.

- Install one (1) 115kV CCVT for indication and synch check.

- Install one (1) CCVT line potential junction box.

Log Cabin/Oak Gove/Bastrop Line Bay:

- Install one (1) standard line/breaker control panel with fiber connection.

- Install one (1) 115kV CCVT for indication and synch check.

- Install one (1) CCVT line potential junction box.

General/Common Equipment:

- Install one (1) bus differential panel (microprocessor based).

- Install one (1) outdoor alarm junction box.

- Install one (1) metering CT junction box (mounted outside).

- Install one (1) bus potential distribution junction box (mounted inside).

- Install three (3) CCVTs for bus potentials.

- Install one (1) bus potential junction box.

AC transfer switch exists in metal-clad switchgear.

- Move one (1) transformer differential panels.

- SEL-2032 communication processor w/ cable, SEL Starcom modem, & Teltone

line-sharing switch are all existing and will be reused.

- Install new battery, charger and test switch in new relay building

- Install one (1) G.E. Telenetics modem.

- Install one (1) 200A battery test switch.

- Install one (1) D20 RTU consisting of:

* One (1) ME motherboard kit.

* One (1) 125VDC power supply.

* One (1) telenetics modem.

* One (1) RTU termination cabinet.

* Four (4) D20 S card kits.

* One (1) D20 A card kit.

* One (1) D20 K card kit with 4 KI cards.

- Install one (1) stand-alone DC panel.

- Install one (1) stand-alone AC panel.

- Install one (1) DC inverter on 19” rack.

- Install one (1) DC transducer

- Install voice and data circuits (ADSS Cable & Hardware, Misc. Fiber Components,

Patch Panel, Fiber Jumpers , DC-DC converter, Relay Rack, Fiber Optic Mux,

Channel Bank/DACS, Misc. Components coordinated by telecom)

- Install one (1) indoor alarm junction box.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 14 of 35

Page 71: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

- Install six (6) 2000:5A slip-over CTs (three on each transformer for bus differential

protection).

- Install two (2) CT junction boxes for transformer slip-over CT’s.

- Install new single meter panel for Crossett North #2. Meter panel at Sterlington is

a dual panel and cannot be moved. We will leave the existing transformer

metering panel in service in the old building.

- Install one 12 point local control panel.

- Install two (2) breaker enclosures with receptacles for gas handling equipment.

- Install one (1) Lot of control cable, approx. 25,000 ft.

- A conduit and fiber will be run to the North Bastrop office

- Remove one (1) MOS panel

- Remove one (1) Tejas RTU.

. At North Bastrop, the existing equipment that is wired to the Tejas RTU shall be moved

over to the new D20 RTU.

Settings:

A System Impact Study has been conducted. During design, the system will be modeled

and settings provided for the following relays at North Bastrop:

- North Bastrop to Oak Grove/Bastrop/Log Cabin 4 terminal Line: new SEL-421 and

SEL-311C

- North Bastrop to Sterlington Line: new SEL-421 and SEL-311C

- North Bastrop to Crossett North Line: new SEL-421 and SEL-311C

- New bus differential panel

- New transformer differential panels

RTU Configuration:

An RTU configuration will be developed and provided to Asset Management for

installation.

ITEM DESCRIPTION OF ASSUMPTION, NOTES/COMMENTS

1

Fiber optic communication equipment will be needed. This equipment

shall be bought and installed by the Communication Group. Also the

phone line needs to be transferred to the new house.

2 The existing 200Ah battery set, battery rack, and 25A battery charger

needs to be transferred from the old house to the new house.

3 All existing devices need to be wired to the new D20 RTU.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 15 of 35

Page 72: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

3.2.1.2. Sterlington TSXXXX:

3.2.1.2.1. Site Work

- None.

3.2.1.2.2. Foundation Work

- Install (2) 2” runs of conduit from new CCVT to cable trough.

- Install (1) 2” conduit for fiber optic.

3.2.1.2.3. Electrical Work

Existing line from Sterlington to Crossett North will now terminate at North Bastrop

Substation; relay communication on this line will be through fiber optic.

- Remove existing line trap.

- Remove existing CCVT.

- Install new CCVT on existing structure.

- Install junction box on existing structure.

3.2.1.2.4. Relay / Configurations Work

The Sterlington to North Bastrop line section will utilize a POTT scheme via fiber.

This calls for the existing blocking line/breaker panel at Sterlington to be replaced

with the new standard fiber line/breaker panel.

- Install one (1) standard line/breaker control panel with fiber connection for breaker

R7265. Breaker R2199 is being controlled by the Vienna dual line/breaker control

panel.

- Install one (1) CVT (existing CVT is old and needs to be replaced).

- Install one (1) CCVT junction box.

- Install one (1) Lot of control cable (approx. 5000 ft.).

- Upgrade telecomm equipment (Misc. Fiber Components, Fiber Jumpers, Fiber

Optic Mux, Channel Bank/DACS, Misc. Components coordinated by telecom)

- G.E. Telenetics modem. EXISTING

- ME motherboard kit. EXISTING

- The RTU has plenty of spare status points and the existing control points will be

reused. Two more control points for the LSR will be needed and we will use old

generator breaker points.

- The station has a SEL 2032 with associated modem and teltone. The SEL 2032

has 9 spare ports to accommodate the new relays.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 16 of 35

Page 73: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

- Remove one (1) line/breaker control panel with blocking carrier scheme this panel

utilizes KD4, KD41, KRP relays and TC blocking carrier set.

- Remove one (1) ground relay panel.

- Remove one (1) line trap.

- Remove one (1) CVT.

- Remove one (1) line tuner.

- Disable Crossett North #2 meter panel.

Settings:

A System Impact Study has been conducted. During design, the system will be modeled

and settings provided for the following relays at Sterlington:

- Sterlington to North Bastrop Line: new SEL-421 and SEL-311C

- Sterlington to Bastrop Line: update CEY52A and GCXG (Zone 2 and 3)

- Sterlington to Crossett North Line: update KD-10 and SDG-4T (Zone 2 and 3)

RTU Configuration:

An RTU configuration will be developed and provided to Asset Management for

installation.

ITEM DESCRIPTION OF ASSUMPTION, NOTES/COMMENTS 1 This station has two battery sets. The DC supply for the primary and

backup relaying should be separated.

2 Fiber optic communication equipment will be needed. This equipment

shall be bought and installed by the Communication Group.

3.2.1.3. Oak Grove TSXXXX:

3.2.1.3.1. Site Work

- None.

3.2.1.3.2. Foundation Work

- Install (2) 2” conduits for bus potential devices.

- Install (1) 2” conduit for fiber optic.

3.2.1.3.3. Electrical Work

Existing line from Oak Grove to Gallion, to Log Cabin terminating at Bastrop will now

terminate at North Bastrop. Relay communication on this line will be through fiber

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 17 of 35

Page 74: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

optic. In addition, new bus potential devices will be required on the operating bus.

- Remove existing line trap.

- Install bus potential junction box on existing structure.

- Remove existing (3) CCVTs and replace them by new ones on the existing

supports

3.2.1.3.4. Relay / Configurations Work

- Install one (1) standard line/breaker control panel with fiber connection.

- Install three (3) CCVTs for bus potentials (the outer phase CCVTs are old and

need to be replaced).

- Install one (1) CCVT junction boxes to bring in all 3 CCVT’s. Indoor bus

distribution box will be reused.

- Line sensing CCVT is new and will not be replaced.

- DC panel has three (3) spare 30A DC breakers (Heinmann).

- Teltone substation line-sharing switch. EXISTING

- Install one (1) SEL 2032 w/ cable.

- Install one (1) G.E. modem (To connect Teltone to RTU).

- Install one (1) Starcom modem.

- Install one (1) Lot of cable (approx. 5000 ft.).

- Install one (1) ME motherboard kit. M motherboard is existing.

- Upgrade telecomm equipment (Misc. Fiber Components, Fiber Jumpers, Fiber

Optic Mux, Channel Bank/DACS, Misc. Components coordinated by telecom)

- Remove one (1) line/breaker control panel with blocking carrier scheme this panel

utilizes KD4, KD41, KRP relays and TC blocking carrier set.

- Remove Bastrop ground distance panel.

- Remove one (1) line trap.

- Remove one (1) line tuner.

- Remove three (3) CCVTs on bus.

Settings:

A System Impact Study has been conducted. During design, the system will be modeled

and settings provided for the following relays at Oak Grove:

- Oak Grove – North Bastrop Line: new SEL-421 and SEL-311C with special

emphasis on reclosing for testing fault on feeder at Log Cabin and restoring load

- Oak Grove to L.V. Bagby Line: update KD and SEL-311C (Z1,Z2,Z3)

- L.V. Bay to Oak Grove Line: update GOC JBCG-53

RTU Configuration:

An RTU configuration will be developed and provided to Asset Management for

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 18 of 35

Page 75: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

installation.

ITEM DESCRIPTION OF ASSUMPTION, NOTES/COMMENTS 1 Fiber optic communication equipment will be needed. This equipment

shall be bought and installed by the Communication Group.

3.2.1.4. North Crossett TSXXXX:

3.2.1.4.1. Site Work

- None.

3.2.1.4.2. Foundation Work

- None.

3.2.1.4.3. Electrical Work

Existing line from North Crossett to Sterlington will now terminate at North Bastrop

Substation; existing CVT on A phase to be removed and existing CVT on C phase to

be moved to A phase.

3.2.1.4.4. Relay / Configurations Work

The North Crossett to North Bastrop will utilize the unblocking scheme. This calls for

the existing blocking line/breaker panel at North Crossett to be replaced with the new

standard unblocking line/breaker panel.

- Install one (1) standard line/breaker control panel with unblocking carrier scheme

using a Pulsar UPLC Carrier.

- Install six (6) 30A DC breakers (Siemens ED2 breakers)

- Install one (1) Lot of control cable (approx. 5000ft.)

- Install one (1) CCVT on A phase.

- Install one (1) CCVT junction box.

- Install one (1) Orion 5R communications processor.

- Install one Line Tuning pack.

- Remove one (1) line/breaker control panel with blocking carrier scheme this panel

utilizes KD4, KD41, KRP relays and TC blocking carrier set

Settings:

A System Impact Study has been conducted. During design, the system will be modeled

and settings provided for the following relays at Crossett North:

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 19 of 35

Page 76: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

- Crossett North to North Bastrop Line: new SEL-421 and SEL-311C

- Crossett North to Sterlington Line: update KD-41 (Z3) and IRP-9

Settings will also be provided for other Arkansas Substations, Monticello East and Lake

Village Bagby, as follows:

- Monticello East to Crossett North Line: update JBCG-53

- Lake Village to Crossett North Line: update JBCG-53

RTU Configuration:

An RTU configuration will be developed and provided to Asset Management for

installation.

ITEM DESCRIPTION OF ASSUMPTION, NOTES/COMMENTS 1 The existing relaying utilizes a blocking scheme; however, the new

panel will utilize an unblocking scheme. Relay Settings may need to

assign a new frequency.

2 The C phase CCVT can be used to replace the A phase CCVT. The C

phase CCVT has carrier accessories on it.

3.2.1.5. Bastrop TSXXXX:

3.2.1.5.1. Site Work

- None.

3.2.1.5.2. Foundation Work

- Install (1) 2” conduit for fiber optic.

3.2.1.5.3. Electrical Work

Existing line from Bastrop to Oak Grove will now terminate at North Bastrop

Substation. Relay communications on this line will be through fiber optic.

- Remove existing line trap.

- Install junction box.

3.2.1.5.4. Relay / Configurations Work

The Bastrop to North Bastrop line section will utilize a POTT scheme via fiber. This

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 20 of 35

Page 77: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

calls for the existing blocking line/breaker panel at Bastrop to be replaced with the

new standard fiber line/breaker panel.

- Install one (1) standard line/breaker control panel with fiber connection.

- Upgrade telecomm equipment (Misc. Fiber Components, Fiber Jumpers, Fiber

Optic Mux, Channel Bank/DACS, Misc. Components coordinated by telecom)

- Teltone substation line sharing switch. EXISTING

- SEL 2032. EXISTING

- SEL Starcom modem. EXISTING

- G.E. Telenetics modem. EXISTING

- RTU motherboard is a D20ME. EXISTING - Spare alarm and control points exist.

- Install one (1) Lot of control cable (approx. 1,500 ft.)

- Replace three (3) bus CCVT’s.

- Install one (1) bus potential junction box.

- Remove one (1) line/breaker control panel with blocking carrier scheme this panel

utilizes KD4, KD41, KRP relays and TC blocking carrier set.

- Remove one (1) line trap.

- Remove one (1) line tuner.

Settings:

A System Impact Study has been conducted. During design, the system will be modeled

and settings provided for the following relays at Bastrop:

- Bastrop to North Bastrop Line: new SEL-421 and SEL-311C

- Bastrop to Sterlington Line: update KD (Z1,Z2,Z3) and IRP-8

RTU Configuration:

An RTU configuration will be developed and provided to Asset Management for

installation.

ITEM DESCRIPTION OF ASSUMPTION, NOTES/COMMENTS 1 R3923 has two sets of slip-over CTs, one set on each side of the

breaker. The set on the 2, 4, 6 side has reversed polarity.

2 Fiber optic communication equipment will be needed. This equipment

shall be bought and installed by the Communication Group.

3.2.1.6. Log Cabin TSXXXX:

Since Entergy does not own any equipment in Log Cabin, LAGen has agreed to

procure ADSS, conduit, SEL2510, revise logic removing power line carrier blocking

and replacing it by ADSS communication at their cost. Entergy will provide

supervision as required. OJ Bruilette of LAGen has agreed to secure approval from

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 21 of 35

Page 78: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Will Day – VP, allocate $25k in 2008 budget and let CPM know (phone call 08-14-07)

3.2.1.6.1. Site Work

- None.

3.2.1.6.2. Foundation Work

- Install (1) 2” conduit for fiber optic.

3.2.1.6.3. Electrical Work

Install 2 splice boxes on line dead-end structures (line from N Bastrop and line to Oak

Grove) and provide hardware to attach the OPGW routed to the splice boxes. Route

ADSS cables from splice boxes in conduits to the relay room

3.2.1.6.4. Relay / Configurations Work

LAGen will disable the power line carrier blocking scheme and instead utilize new

fiber optic based communication equipment SEL2510 to send blocking signals to

Oak Grove, N Bastrop and Bastrop ends.

3.2.2. SCADA

Item / Description Add Remove

RTU Type (new/existing) 1 1

High Voltage Breakers 3 0

Motor Operated Switches 2 0

Fault Interrupter Switches 2 0

Line/Breaker Panels 7 5

Xfmr. Diff. Panels 2 2

Bus Diff. Panel 2 0

CCVTs for Bus Potentials 11 0

Meter Panel 1 1

* All other existing equipment at North Bastrop Lot 0

3.2.3. Transmission Lines Work

3.2.3.1. Sterlington to N. Crossett – New 7.0 Mile In and Out to North Bastrop,

TL9575:

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 22 of 35

Page 79: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

A new 115kV 7.0 mile long double circuit transmission line consisting of 1272 Bittern

conductor on single-pole and two pole structures will be constructed as part of this work.

One 7#7 Alumoweld shield wire and one 24 fiber OPGW will be provided. The OPGW

will deadend into a splice box at the tap point for a future connection to a fiber line from

Sterlington.

This Project Execution Plan to construct the new line provides for the following:

- Obtain surveys to facilitate ROW acquisition, transmission line design and

construction.

- Acquire a 100 feet wide ROW approximately 7.0 miles long (8 landowners).

- Obtain soil borings to facilitate transmission line design.

- Provide a ROW clearing specification.

- Perform detail design and provide a transmission line construction specification.

- Obtain environmental delineation to facilitate construction.

- Obtain a Storm Water Pollution Prevention Plan and implement / maintain related

mitigation measures.

- Obtain necessary permits (railroad crossing, river crossing, road crossing, etc.).

- Clear 100 feet wide ROW approximately 7 miles long (approximately 3.5 miles is

wooded, 2.5 miles is open farmland and 1 mile is adjacent to railroad ROW).

- Provide access roads adjacent to and along the new ROW as required for

construction.

- Design, procure and install approximately forty five (45) single pole steel or

concrete structures with necessary hardware.

- Design, procure and install approximately seventeen (17) free-standing or guyed 2

pole dead- end and angle structures with necessary hardware.

- Design, procure and install 1272 Bittern conductor.

- Design, procure and install one (1) 7#7 Alumoweld shield wire. (7 miles)

- Design, procure and install one (1) 24 fiber OPGW and hardware. (7 miles)

- Design, procure and install approximately four-hundred thirty-five (435) dead-end

and braced post insulators.

3.2.3.2. North Bastrop to Log Cabin line TL9582:

- Replace existing shield wire on line between North Bastrop and Log Cabin S/S by

a 24 pair OPGW and terminate the line on to a dead-end structure at North

Bastrop. Terminate OPGW in splice boxes at N Bastrop and Log Cabin.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 23 of 35

Page 80: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

- Outside Log Cabin S/S on line poles, replace existing OPGW splice box by 4 port

box. Replace existing shield wire by 24 strands OPGW on line between Log Cabin

S/S and transmission poles outside Log Cabin substation (relating to N

Bastrop/Bastrop line). Replace Terminate the OPGW in splice box in Log Cabin and

existing splice box at the tap and make connections with fibers on 8 pair existing

OPGW enabling communication between Oak Grove, Log Cabin, Bastrop and N

Bastrop.

3.2.3.3 Distribution Wire Scope

3.2.3.3.1 None

4. MATERIALS MANAGEMENT PLAN

4.1 Long Lead Time Equipment

Substation Long Lead Materials

Quantity Material Description Duration

(Weeks)

13 115kV CVTs 36

1 Control House (16’ x 36’) 28

2 2030 115kV Circuit Switchers 22

1 Lot – Insulators 22

11 115kV 2000A Switches, 3 with ground 20

3 115kV, 2000A, 40kA Breakers 20

3 Dead-end Structures 20

1 Lot – Substation Steel 20

7 Line / Breaker Control Panels 12

2 Transformer Differential Panels 12

2 Bus Differential Panel 12

21 Arresters 16

1 Lot – Bus 14

6 2000:5 Slipover CTs 12

T-Lines Long Lead Materials

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 24 of 35

Page 81: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Quantity Material Description Duration

(Weeks)

86 Concrete or Steel Poles 14 to 24

490,000 lbs Conductor – 1272 ACSR 24

10.7 miles 24 Fiber OPGW 24

475 Insulators 16

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 25 of 35

Page 82: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

5. PROJECT CONTROLS PLAN:

5.1 Scoping Estimate

Description

Direct

Responsibility

TL9575 – Sterlington to North Crossett #2: In and

Out to North Bastrop (ELI)

$7,328,980

TL9582 – North Bastrop to Log Cabin - 24 fiber

OPGW

$479,170

TSxxxx – Log Cabin S/S (EL $47,038

TS9575 – N Bastrop: Convert to 3-Breakers

$2,930,398

TSXXXX – North Crossett: Line Relay

Modifications (EAI)

$187,983

TSXXXX – Bastrop: Line Relay Modifications

$234,014

TSXXXX – Oak Grove: Line Relay Modifications

$260,992

TSXXXX – Sterlington ELI $217,450

Direct total $11,686,024

FVET based indirect + 3% contingency for ELI $5,278,512

Total $16,964,536

5.2 CASHFLOW:

Description

2007

2008

2009 Total

Direct Responsibility – ELI $554,000 $10,700,523 $243,518 $11,498,041

Indirect Responsibility – ELI $271,318 $4,762,079 $148,115 $5,181,513 Total ELI

$825,318 $15,462,603 $391,633 $16,679,554

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 26 of 35

Page 83: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Direct Responsibility – EAI $ 6,465 $ 175,032 $ 6,486 $ 187,983

Indirect Responsibility - EAI $ 3,336 $ 90,317 $ 3,347 $ 96,999 Total EAI $ 9,801 $ 265,349 $ 9,832 $ 284,982 Total Direct $ 560,465 $ 10,875,555 $ 250,004 $11,686,024 Total Indirect $ 274,654 $ 4,852,396 $ 151,462 $ 5,278,512 TOTAL $ 835,119 $ 15,727,951 $ 401,465 $16,964,536

5.3 Baseline Estimate

Due to large number and memory requirement, the base-lined Cost Estimate is stored in eroom.

See address in attachment section on last page.

5.4 Baselined Schedule: A schedule is prepared based on FP and RCRC approval by 01 October 2007.

5.5 Contingencies

Certain types of estimated cost areas are subject to a greater risk of changing than others due to

many factors such as market conditions, weather, productivity, estimate accuracy, etc.

Typically, contingency funds are established to address the possible occurrence of these risks.

The Change Management Process is used to control the use of these contingency funds. For

this project, the following cost risks and associated contingencies are proposed.

• Material 0% to 5% Say 3% contingency

• Construction Labor 3% to 9% Say 9%

• Other Labor 3% to 8% Say 6% contingency

Activity Contingency/Risk Reason for

contingency Amount $ Date risk is averted

and dollars could be

removed Electrical

material 6% Increase in

material cost and

steel cost

$23,830 After all material has

been ordered

Relay material 3% Increase in raw $20,076 After all material has

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 27 of 35

Page 84: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

material cost and

cable amount been ordered

7m Line material 3% Increase in

material cost or

change in design

$83,042 After all material has

been ordered

7m Line labor 6% Incidental due to

change in

priorities, etc

$14,280 After 60% design

completion

7m Line contract,

etc

9% Change in

weather, labor

situation, line

design changes,

route issues, etc

$349,900 After 70% completion

3.7m Line 5% Increase in

material and

contract cost or

change in design

$22,818 After all material has

been ordered and

contract is awarded

OH 3% of 44% for ELI

and 0% of 51.6%

for EAI

Unpredictability

and lack of ability

to control

$150,918 End of every quarter

after doing FVET

calculations and on the

basis of last 3 month

average

Total in

contingencies

$620,958

5.6 Outage Plan

Outage Number

Reason

Duration

1 De-Energize Sterlington to Crossett North #2 Transmission Line

Cut-In North Bastrop

Modify Sterlington Relaying

Modify North Crossett Relaying

5 days

2 De-Energize N. Bastrop to Log Cabin Tap (N. Bastrop tap line)

to replace shield wire by OPGW

96 days

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 28 of 35

Page 85: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

3 8 pair backbone communication Fiber between Bastrop and

Oak Grove need to be broken and spliced with 4 pairs from N

Bastrop. Careful Planning to keep the outage to a minimum

will be required

5.7 Gate Reviews

A gate review will be performed at the end of each phase to verify requirements are met before

entering into the next phase. However, if all requirements are not met and Project Manger

approves the project can move on into the next phase.

6.0 RESOURCE PLAN

Resources and Contracting Strategy

• ROW Acquisition Labor – ROW acquisition labor shall be provided by contract and

in-house labor.

• Design Labor – Design labor (all disciplines) shall be provided by in-house

resources.

• Materials – All materials shall be ordered by Design and procured via Purchase

Order or Stores.

• Construction – All construction-related labor (except relay installation and checkout)

shall be contract labor. Asset Management shall provide in-house labor for all relay

installation and checkout. Construction contracts shall be competitively bid to pre-

qualified contractors. Each contract shall be awarded on a lump-sum basis with

provisions for extras.

• Other Labor – Project Management, Construction Management and other support

labor shall be provided by in-house resources.

7.0 QUALITY PLAN

• Definition Phase – The Project Team shall develop the scope of work based upon

safety, constructability, operability, maintainability, specific Transmission System

Planning requirements, specific Asset Planning requirements, specific Asset

Management requirements, field verification and other established requirements as

applicable.

• Design Phase – Per established processes, designs shall be reviewed for

constructability and shall undergo quality reviews by JET / supervisors before the

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 29 of 35

Page 86: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

completed specifications are issued to Construction.

• Materials – Where possible, materials shall be standard and obtained from

established vendors. Where appropriate, vendor data reviews shall be performed by

Design with support from the Project Team as required. Certain materials may

require pre-acceptance checks as required by the specifications.

• Construction – Construction activities shall be coordinated and supervised by the

on-site Construction Representative. Special testing requirements (i.e. concrete

testing) shall be performed in accordance with specifications.

8.0 CONSTRUCTION MANAGEMENT PLAN

8.1 Project Execution

8.1.1 Constructability Reviews

- Constructability reviews will be performed at specified percent complete for

Transmission line, Substation and relay design. This interval is to be

determined by the project team.

8.1.2 Sequenced Construction Plan

1) At North Bastrop, construct a new Operating Bus and install four breakers

and other equipment during non-outage construction.

2) Construct a new 7.0 mile In and Out from the existing Sterlington to North

Crossett transmission line to North Bastrop Substation in the new ROW

during non-outage construction.

3) De-energize the Sterlington to North Crossett transmission line and cut in the

new double-circuit transmission line to North Bastrop during outage

construction. Complete relay modifications at Sterlington and North Crossett

during outage construction.

4) Energize the new transmission lines from North Bastrop to Sterlington and to

North Crossett. Commission all related equipment at North Bastrop,

Sterlington and North Crossett.

5) After the North Bastrop load has been shifted from the existing radial line to

the new double-circuit line, de-energize the North Bastrop tap and replace

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 30 of 35

Page 87: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

shield wire by 24 fiber OPGW.

6) De-Energize the Bastrop to Log Cabin line section, replace splice box on

pole, replace shield wire into Log Cabin by OPGW, replace power line carrier

logic equipment by SEL device, and replace shield wire into the S/S by

OPGW and terminate it in the splice box in the substation yard.

7) De-energize the Log Cabin to Oak Grove transmission line and complete

relay modifications at Oak Grove and Log Cabin for fiber optic.

8) Install Circuit Switchers to existing transformer banks at N. Bastrop.

9) Energize the transmission line from North Bastrop to Oak Grove with tap to

Log Cabin. Commission all related equipment at Oak Grove, Log Cabin and

N Bastrop.

8.1.3 Lay-Down Areas

1) Areas within or adjacent to existing substations will be used to stage

substation material and equipment.

2) Areas along the ROW or nearby secure substations will be used to stage

transmission line material and equipment.

8.2 Safety - Special Considerations for Construction

There are no special considerations for construction. This will be further reviewed prior to

construction.

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 31 of 35

Page 88: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

9.0 RISK MANAGEMENT PLAN

9.1 Risk Identification

Risk Assessment

The following are identified risks and how the Project Team will mitigate:

Identified Risk Quantified Value(Cost or

Schedule) Response Development

Ability to acquire ROW to meet

the schedule

Will impact schedule day per day Acquire easement as early as

possible

Survey not completed in a

timeframe that supports the

overall transmission line

schedule

Will impact schedule on a day

per day basis.

Obtain survey as soon as

possible.

Soil borings not completed in a

timeframe that supports the

overall transmission line

schedule

Will impact schedule on a day

per day basis.

Work has already

commenced

Wellheads and numerous

gathering system flow-lines in

vicinity of new transmission line

ROW

Will impact schedule day per day Identify wellhead and flow-

line locations early in design

and confirm before

excavating.

New equipment vendor data

received in a manner that

supports the design schedule

Will impact schedule on a day

per day basis.

Clearly define vendor data

schedule in purchase orders

and expedite vendor data.

Ability to get transmission line

outage

Will impact schedule day per day Schedule in TAORS 6

months in advance of

construction

Single line feed exposure Not quantified Coordinate with Customers

and execute construction as

efficiently as possible

Environmental Delineation

including wood pecker issue

Significant impact to schedule

and costs depending on findings

Acquire delineation as early

as possible

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 32 of 35

Page 89: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Wetland permit Significant impact to schedule

and costs if required

Acquire permit as early as

possible

10.0 REGULATORY, ROW, LEGAL AND ENVIRONMENTAL COMPLIANCE PLAN(S): Potential major environmental issues associated with the N. Bastrop/Log Cabin project include

regulations pertaining to:

§ National Pollutant Discharge Elimination System storm water discharges associated with

construction activities--storm water pollution prevention plan, siltation/erosion control

BMP’s, siltation/erosion control BMP inspections and NOI/NOT submittal,

§ Clean Water Act Section 404 dredge and fill--wetland permit, conditions of issuance

compliance and impact mitigation,

§ Endangered Species Act--threatened and endangered species incidental take, habitat

impacts and mitigation,

§ Historic Preservation Section 106--SHPO historic/cultural resource impact,

§ River and Harbors Act Section 10--navigable in-fact stream line crossing and

§ Potential CERCLA issues—if substation areas are contaminated.

Regarding, the latter issue, Jerry Roberts has provided Jeff with a Phase I environmental site

assessment report for the Log Cabin substation site that was conducted in November 2004. The

consultant recommendation in that report was that a subsurface investigation for PCB

contamination be conducted on the site prior to acquisition or commencement of construction

activities on the site.

Given this, the reported presence of red-cockaded woodpecker nest habitat and the likely

presence of jurisdictional wetlands along the line route; a project environmental impact analysis

should be conducted on the substation sites and proposed line route to better define the permit

requirements and risks. $50,000 should be adequate to define these issues, and proceed with

development of a storm water pollution prevention plan and preliminary CWA 404 jurisdictional

determination. The analysis will only define potential problems. Definition of expenses for

mitigating wetland or T&E species impacts, as well as siltation/erosion control best management

practice installation and maintenance, or remediation of any PCB contamination at the Log Cabin

site will be more complete after the initial assessment is completed. An additional potential

budget issue will be costs associated with installation of oil spill diversionary structures at the

substation sites. Environmental Management will need to evaluate the risk of oil discharge to

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 33 of 35

Page 90: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

surface water.

In order to proceed with securing a consultant to perform the study, preliminary plan and profile

drawings, preliminary construction scopes defining ROW clearing practices, line support structure

details and substation grading/excavation requirements; and line route maps are required.

ROW permits include:

- Highway / Creek crossing permits

- Permits for entire project

11.0 PROJECT CLOSURE:

11.1 Lessons Learned

Refer to corresponding Section of the P.E.P. “Guide” for additional guidance. A typical “Lessons

Learned” process and suggested checklist are available in the hyperlinked document below (also

available in “stand-alone” format in PMO e-room):

A suggested letter and questionnaire (see hyperlinked template document, below, also available in

“stand-alone” format in PMO eRoom) should be provided to each attendee, along with an agenda,

prior to the “Lessons Learned” meeting in order that everyone understand the process and comes

prepared.

12.0 COMMUNICATIONS PLAN:

12.1 Reoccurring Reports

• Project Schedule – To be updated by all and provided weekly by Scheduler

• Project Cost Reports – To be provided monthly by Cost Analyst to Project Team for input

• Construction Cost Data Sheets – To be provided by Construction

• Material Status Reports – To be maintained on-line by Project Support Services

• Monthly Status Reports – To be provided by Project Manager

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 34 of 35

Page 91: TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:ELI-N … · 2008. 7. 24. · Add 4th Auto)..... 33 4.21 Baxter Wilson -Install a new 2nd 600MVA, 500/115kV autotransformer 37 4.22 Sterlington

Sterlington to Bastrop Project – PEP Rev 3 (8-14-07)

Page 35 of 35

List of Attachments to the Project Execution Plan

Item Method Location

A Cost Estimates e-room, files not being

inserted here due to

their large number and

size

https://eroom.entergy.com/eRoom/Proje

ctsII/ENOI-ELI2/0_a1804

B Switching one-line diagrams,

operational one-line diagram and other

drawings

e-room, files not being

inserted here due to

their large number and

size

The elaborated path for above address

is:

my erooms/ELI North/Active

Projects/North Bastrop/Definition

C Schedule e-room, files not being

inserted here due to

their large number and

size

The elaborated path for above address

is:

my erooms/ELI North/Active

Projects/North Bastrop/Definition

D FVET e-room, files not being

inserted here due to

their large number and

size

The elaborated path for above address

is:

my erooms/ELI North/Active

Projects/North Bastrop/Definition