transmission development plan 2013-2022
DESCRIPTION
Transmission Development Plan 2013-2022TRANSCRIPT
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 1 of 138
Office: Long-term Planning and Development
TRANSMISSION DEVELOPMENT PLAN
2013-2022
January 2013
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 2 of 138
Office: Long-term Planning and Development
1. INTRODUCTION ................................................................................................ 5
1.1. Role of the Transmission System and Market Operator ............................................ 7
1.2. Transmission network ............................................................................................... 8
1.3. Access to Planning .................................................................................................. 10
1.4. Content of the Plan ................................................................................................. 12 2. GRID CODE TECHNICAL REQUIREMENTS .............................................. 13
2.1. Introduction ............................................................................................................ 13
2.2. Relevant data for planning –requirements for the transmission system users ........... 14
2.3. Data Attributes ....................................................................................................... 14
2.4. Standards and criteria for transmission network planning ........................................ 15
2.5. 400 kV, 220 kV and 110 kV Network Planning Criteria .......................................... 16
2.6. Long-term planning criteria for the revitalizing of the transmission network ........... 19
2.7. Planning methodology ............................................................................................ 21
2.8. Substation configuration planning ........................................................................... 22
3. ELECTRICITY LOAD FORECAST ..................................................................... 26
3.1. Introduction ............................................................................................................ 26
3.2. Background history of the load, and current situation ............................................. 26
3.3. Demand profile ....................................................................................................... 27
3.4. Long term forecasts of demand 2013-2022 ............................................................. 31 4. GENERATION CAPACITIES OF KOSOVO POWER SYSTEM .................... 32
4.1. Introduction ............................................................................................................ 32
4.2. Planning of the new generating units ....................................................................... 34
4.3. Renewable sources .................................................................................................. 35
4.4. Application for connection of the HPP “Lumi Deçani” with the transmission grid . 36 5. KOSOVO TRANSMISSION NETWORK DEVELOPMENT PROJECTS ..... 37
5.1. History of the transmission network ....................................................................... 37
5.2. Implemented projects 2007-2012 ............................................................................ 39
5.3. Transmission network infrastructure development; 2013-2022 ................................ 41
5.3.1. Introduction ............................................................................................................ 41
5.3.2. Ongoing development projects ............................................................................... 42
5.3.3. List of new development projects planned for the period 2013-2022 ...................... 43
5.3.3.1.The list of new projects in the category of transmission network reinforcement...... 43
5.3.3.2. List of new projects, to support the load ................................................................ 46
5.3.3.3. Projects planned for the category of revitalization of KOSTT substations ............. 47
5.3.3.4. Projects planned in the category of supporting transmission system operation ....... 48
5.4. Technical description of projects planned in transmission ....................................... 49
5.4.2. Transmission grid strengthening projects ................................................................ 50
5.4.3. 110 kV line revitalization projects ............................................................................ 63
5.4.4. Load support projects ............................................................................................. 69
5.4.5. Substation Revitalization Projects ............................................................................ 79
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 3 of 138
Office: Long-term Planning and Development
5.4.6. Projects to enhance monitoring, control and measurement systems in the
Transmission System .......................................................................................................... 84 5.5. Rationale for changes in projects of the TDP 2013-2022 in comparison to the TDP
2012-2021 .......................................................................................................................... 88
6. TRANSMISSION NETWORK PERFORMANCE ANALYSIS ..................... 91
6.1. Description of the network model. .......................................................................... 91
6.1.1. Transformation capacities; Q4-2012 ........................................................................ 92
6.1.2. The current load exchange capacity with neighboring countries .............................. 93
6.2. Analysis of the transmission network condition as per topology Q4-2012 ............... 96
6.2.1. N-security criterion analysis ..................................................................................... 96
6.2.2. N – 1 security criteria analysis ................................................................................. 97
6.2.3. Voltage profile and losses ........................................................................................ 99
6.3. Analysis of the transmission network condition by topology- 2018 ....................... 104
6.3.1. N-security criterion analysis ................................................................................... 104
6.3.2. N-1 security criterion analysis ................................................................................ 105
6.3.3. Voltage profile and losses ...................................................................................... 106
6.4. Analysis of the transmission network condition, topology - 2022 .......................... 112
6.4.1. N security criterion analysis ................................................................................... 112
6.4.2. N-1 security criterion analysis ................................................................................ 113
6.4.3. Voltage profile and losses ...................................................................................... 114
6.5. General conclusion ............................................................................................... 120
6.5.1. Network capacity development ............................................................................. 121
6.5.2. N-1 security criterion ............................................................................................ 122
6.5.3. Quality of supply and efficiency ............................................................................ 123
7. FAULT CURRENTS IN THE TRANSMISSION NETWORK................... 124
7.1. Introduction .......................................................................................................... 124
7.2. Calculation of fault currents level .......................................................................... 124
7.2.1. Mathematical model, calculation methodology and applied software ..................... 124
7.2.2. Features of the power circuits of the transmission network ................................... 126
7.2.3. Results of the calculated fault currents .................................................................. 126 7.2.4. Assessments of the calculated fault currents in busbars 400 kV, 220 kV and 110 kV
(2012) ...............................................................................................................................127
7.2.5. Assessments of the calculated fault currents in busbars 35 kV and 10 kV .............. 128
7.2.6. Assessments of the calculated fault currents (2018) ............................................... 130
7.2.7. Assessments of the calculated fault currents (2022) ............................................... 131
8. ENVIRONMENTAL IMPACTS ..................................................................... 132
8.1. Environmental protection ..................................................................................... 132
8.2. Environmental problems in the transmission system ............................................. 133
8.2.1. Environmental problems caused by the lines ......................................................... 133
8.2.2. Environmental problems caused by the substations .............................................. 134
8.2.3. Caution on the other environmental impacts ......................................................... 135
8.3. Environmental plans ............................................................................................. 136 REFERENCES .......................................................................................................... 137
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 4 of 138
Office: Long-term Planning and Development
Abbreviations
ENTSO/E – (European Network of Transmission System Operators for Electricity)
ESTAP I &II - (Energy Sector Technical Assistance Project)
IPA ( Instrument for Pre-Accession)
KOSTT – System, transmission and market operator JSC
KEK – Kosovo Energy Corporation J. S. C.
MZHE – Ministry of Economic Development
MTI – Ministry of Trade and Industry
OPGW – Optical Ground Wire
TSO – Transmission system operator
PSS/E- Power System Simulator/Engineering
TDP – Transmission Development Plan
EES –Power system
SCADA/EMS – Supervisory Control and Data Acquisition/Energy Management System
SECI – South East Cooperative Initiative (Regional transmission planning project)
EMS – Environment management system
TACSR/ACS – (Special conductor with high level of thermal resistance, Al-Çe)
IT – Information technology
ERO – Energy Regulatory Office
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 5 of 138
Office: Long-term Planning and Development
1. INTRODUCTION
Electricity sector as one of the most important industrial sectors in the economy of Kosovo
should be developed and planned appropriately. Transmission network, which is operated by
KOSTT, plays an important role in the energy and electricity system enabling the
transmission of power from generators to large customers and distribution nodes.
The vision of KOSTT is to “to provide safe and reliable service to users of the transmission
system, responsive to social and environmental aspects, integrated to European transmission
mechanisms, while also being financially stable and profitable”.
KOSTT mission is to provide:
- Quality services by implementing technical and technological achievements in the
development of the transmission system;
- Transparency and non-discrimination for transmission system users in competitive
electricity market;
Advancement of the company’s position on the international level through
increased activities in this way.
Related to the above-mentioned responsibilities on the transmission system development
and legal obligations, KOSTT hereby drafts the Transmission Development Plan (TDP),
which represents one of the main foundations of development planning of KOSTT. The
importance of preparing and implementing such document is faced also in the legislative
requirements related to the preparation and treatment of this document and as such belong
to the primary and secondary level legislation.
Legal Requirements: Law on Energy:
- TSO and DSO prepare and publish development plans, in accordance with the requirements of the
Law on Energy Regulator. These plans must be compatible with license requirements and the
Energy Strategy, Strategy Implementation Plan, and Energy Balances.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 6 of 138
Office: Long-term Planning and Development
Law on Electricity:
- TSO shall be responsible for fulfilling requirements related to the ten (10) year system development
plan, as per sub-paragraph 5. 6 of paragraph 5 and paragraph 6 of Article 14, Law on Energy
Regulator.
Law on Energy Regulator:
- The Energy Regulatory Office shall examine whether the ten-year development plan submitted by the
transmission system operator covers all investment needs identified in the consultation process, and
may require the transmission system operator to amend the ten-year system development plan as
appropriate.
Licenses for the Transmission System Operator:
- In accordance with Article 7 of the Law on Energy and article 12 of the Law on Electricity, and
Article 14 of the Law on the Energy Regulator, the Licensee shall develop and publish a medium
(3-5 years) investment development plan that shall derive from long-term transmission system
development plan (10 years). Such a development plan shall be made in conformity with the
applicable legislation by consulting current and potential system users. Before its, publication, the
plan shall be submitted to ERO for approval
Grid Code:
- Each year TSO will prepare and issue a detailed plan on Transmission Development Plan
(TDP) for the next 10 years.
Rule on licensing energy activities in Kosovo:
- Transmission System Operator license applicant, in addition to the requirements of Article 9 and
10 of this rule, shall submit to ERO the system development plan, as defined in Article 12,
paragraph 1 (1. 20) of the Law on Electricity, and Article 7 of the Law on Energy, including the
system development’s impact in the tariffs approved by ERO.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 7 of 138
Office: Long-term Planning and Development
ENTSO-E Requirements: According to the article of the (EC) Regulation No. 714/2009 of the 3rd package that
defines the coordination of the operation and development of the transmission system "an
extensive network plan for the community-wide should include modeling of integrated
network, scenario development, an adequacy concept generation and an assessment of the
resilience of the system”. Furthermore, TDP (Transmission Development Plan) should
“build on national investment plans and, if appropriate under the guidelines for energy
networks”.
Pursuant on the above mentioned legal obligations, KOSTT is obliged to draft and after
approval from Energy Regulatory Office, to publish and implement such document,
which is drafted in full compliance with Energy Strategy of Kosovo.
1.1. Role of the Transmission System and Market Operator
KOSTT mandate is defined by the Law on Electricity, secondary legislation and licenses
issued by the Energy Regulatory Office (ERO). KOSTT as an independent operator of
transmission system and market is responsible for operating and developing the transmission
system, including network transmission and operation of electricity market.
KOSTT responsibilities related to the transmission network development are:
- Organization of preliminary studies for possibilities for new constructions of transmission capacities,
facilities and equipment, supported by technical, economic and financial studies
- Compilation and publication of short and long term plans for expansion and modernization of the
transmission network.
- The development of transmission network and interconnection with neighboring networks in order to
guarantee the security of supply,
- Provision of sufficient information on any other system operator to which the system is connected to
ensure that it is a matter related to their development requirements
- Coordination on the planning and development of transmission network with counterpart companies
in the region and drafting of the ten-years plan at the ENTSO-E level
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 8 of 138
Office: Long-term Planning and Development
Under the granted license, KOSTT shall prepare and publish the mid-term (3-5 years)
transmission development plan as part of the ten-year development plan. After its
approval by the Energy Regulatory Office, TDP should be published by KOSTT.
Network users can use this Plan to plan their future activities, for new connections or
strengthening the existing ones.
1.2. Transmission network
Kosovo Power System, is interconnected through cross border lines with the neighboring
countries: Serbia, Macedonia, Montenegro and Albania through high carrying capacity lines
400 kV, 220 kV and three 110 kV lines. Kosovo Power System is characterized by strong
network interconnection voltage of 400 kV, which is strongly interconnected in the regional
network. Powerful interconnection of the transmission network with the surrounding
networks the ranks the Power System of Kosovo, as one of the important nodes of Power
in the region and beyond. The continuous increase of electricity consumption in the country
and the region, increase power flows in the internal lines and those of interconnection. This
increase of power flows continuously narrows safety margins of the stability of Kosovo’s
Power System, and other systems interrelated with our system. Necessary reinforcements in
the transmission network in the country and in the region are vital in maintaining the
stability and reliability of the system in the near future.
After the decision of the Government of the Republic of Kosovo (no. 10/29 2011) on the
transfer of a part of the 110/35 kV grid and 110/10(20) kV grid from the DSO to the
KOSTT, the transmission system is operating at five voltage levels, 400 kV, 220 kV, 110 kV,
35 kV and 10(20) kV. The boundary of assets with generation and eligible consumers has
remained the same, while the boundary with the Distribution grid has been displaced from
the borns 110 kV of load transformers in connection points at busbars 35 kV and 10 kV at
the bottom of transformer fields 35 kV and 10 kV. This includes the system of auxiliary
supplies, together with the transformer fields for own-consumption at substations 110/35
kV, 110/35/10(20) kV and 110/10(20) kV, and the command facility and the areas around
the location. The figure 1-1 shows the technical boundaries after the Government decision.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 9 of 138
Office: Long-term Planning and Development
Figure 1-1. Technical boundary between KOSTT and parties connected to the transmission grid
The main problems identified in the assets transferred are mainly related to the transformer
fields 35 kV, with an outdoor construction, built in the 70es and 80es. Also, we have
identified equipment which are not dimensioned according to the short connection load of
the substation in which they were built in. Four 110/10 kV substations have only one
transformer each, the operations of which do not ensure required reliability in consumer
supply, and render the maintenance process rather difficult, due to the lack of alternative
supply lines.
In this TDP, the list of projects from the previous plan was updated in terms of temporal
implementation, and detailed analysis were undertaken, based on the asset transfer from the
KEK-DSO to KOSTT, and emergency and long-term consolidation requirements were
identified, for the part of the grid transferred to the KOSTT management. Preliminarily, a
Transmission network
400kV, 220kV dhe 110kV
KOSTT
G
220kV,110kV
10(20)kV
400kV,220kV,110kV
Generation
10(20)kV
35kV
DSO
220kV, 110kV
6.3kV,10kV,35kV
Industrial consumers
AC/DC
AC/DC
10(20)kV
35kV
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 10 of 138
Office: Long-term Planning and Development
detailed survey of transferred equipment was undertaken by the Planning and Maintenance
Engineers, with a view of identifying the technical condition of load transformers, their
fields, and other auxiliary equipment (protection, control).
1.3. Access to Planning
The process of planning and development of transmission network is a long and complex
process. The process involves a number of activities, such as network development in
relation to energy demand prediction, generation prediction, enabling the identification of
necessary reinforcements and extensions needed to achieve network operating within the
parameters of reliability and environmental impact. Although TDP takes as a reference the
prediction for a certain period based on the Long-Term Energy Balance, the plan must also
convey the strategic development of the transmission system over the long term timeframe.
The planning process is a result of the process of restructuring the energy market. The
planning process has changed in some respects, compared to the previous process in the
vertically integrated companies:
- Uncertainties coming from the market environment and input data.
- Objectives of different network users (generators, traders, suppliers, customers and network
operators)
- Incompliance and disproportion between the technical, economic, environmental and social
requirements.
- Uncertainties coming from the level of integration of energy from the renewable sources
In addition, the need for regional market integration requires increasing and strengthening of
the interconnection capacity, which affects the planning process at national level. Network
development options based on the Planning Code and on the general planning rules
recommended by the ENTSO/E. Determinative methodology (defining), which is based
on the security criteria N-1, presents the basic methodology applied in this plan, the purpose
of identifying and determining the list of projects necessary for development of the
transmission network.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 11 of 138
Office: Long-term Planning and Development
This plan contains information on the development and reinforcement expected to occur in
the transmission network in Kosovo for 10 years in the following:
- Building of new transformation and transmission capacities,
- Strengthening of existing transmission and transformation capacities,
- Construction of the interconnection lines with the neighboring countries,
- Revitalizing of the existing equipments of the high voltage (lines and substations)
- Development of supporting systems of transmission system.
It also contains information on the possibilities of connecting new generating units and new
loads in the transmission system.
The main objective of the ten-year plan is to identify projects which will increase capacity,
reliability and efficiency of the operation of the transmission network. This plan will enable
consumers, energy market participants, energy producers, prospective investors to familiarize
with the transmission development plan for the next ten years.
This document presents development plan drafted in KOSTT, covering a ten year period,
from 2013 until 2022, in compliance with the ENTSO/E requirements, where the year
2012 represents the reference year, or the so-called year zero. All information in the
development plan, such as project details, the expected starting date of the project
implementation, network transmission connection applications in in 2011, and those
ongoing until end 2012, are all taken into consideration in developing this document.
For the preparation of development plan appropriate calculations were made with the
relevant software PSS/E 33, simulating computer models of the system based on data
provided by KOSTT and network users, and based as well on the load prediction for the
next 10 years. Load forecast is based on historical data (consumption, maximum load, the
load duration curve, etc.), as well as the expected demand from industrial and commercial
consumption and new connections expected to occur. Generation data are provided by
KEK - Generation and other generators. Data for interconnections expected to be built in
the region, were provided by studies made in the Planning Group for Regional Transmission
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 12 of 138
Office: Long-term Planning and Development
Network Planning - SECI, in which group KOSTT contributes as well through its
representatives
For each year of development, studies were conducted for the power flows, simultaneously
following the increase of the demand for maximum load. Calculations were also made for
breakdowns in different periods. Based on results of calculations, it is possible to provide
estimates on how the network will operate for the estimated next years. Bottlenecks have
been identified and possible solutions were presented by analyzing their impact on
improving the operating performance of the transmission network. The transmission
network was analyzed also for minimal loads, thereby identifying eventual problems in
overloads in 400 kV, 220 kV, 110 kV, 35 kV and 10 kV, which may appear in summer
minimal load regimes.
KOSTT has been carefully evaluating the accuracy of information, which does not fall under
KOSTT responsibility, making clear that KOSTT is not responsible for information or
incorrect data received from other parties.
1.4. Content of the Plan
TDP is structured in 8 chapters including the introduction:
Chapter 1– Introduction
Chapter 2 - Technical requirements of the Grid Code - presents the process of data
collection, planning criteria and standards, and configuration of substations by voltage level
400 kV, 220 kV and 110 kV.
Chapter 3 - Presents the electricity demand forecast, broken down in the consumption of
the past three years and forecasted consumption for the next 10 years.
Chapter 4 - List of existing generators and planned ones. It is also presents the renewable
generation and KOSTT policies in support of this technology.
Chapter 5 - Describes the KOSTT network transmission, and interconnection with its
neighbors. A part of this chapter describes in details the future developments of the
network.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 13 of 138
Office: Long-term Planning and Development
Chapter 6 - System performance is presented for different network conditions for certain
periods of development plan.
Chapter 7 – Contains the results of the short circuit currents for certain periods of time, in
order to assess the disconnection ability of existing circuit breakers and the dynamic stability
of high voltage equipment in case of occurrence of failures in the transmission network.
Chapter 8 - Includes access to environmental planning policy in relation to the
Transmission Development Plan
Chapter 9 - Contains a list of references.
2. GRID CODE TECHNICAL REQUIREMENTS
2.1. Introduction
One of the main KOSTT objectives is development of the transmission system with the
purpose of safe, efficient and reliable operation in order to enable electricity operation,
fulfilling the demand in compliance with the legal requirements. Transmission System
Operator has planned developments of the network based on long-term electricity needs.
Demand for electricity transmission depends on many factors: increased consumption,
installation of new generating units, new cross-border lines, development of heavy industry,
etc.
The need for reinforcements in the transmission network is determined based on the study
of network performance against the planned technical standards outlined in the Grid Code
respectively Planning Code.
The Grid Code covers the operational procedures and provisions governing the interaction
between KOSTT and users of the Transmission System in Kosovo. This code also includes
the processes of planning, connection, operation and balances system in normal and
emergency situations. Processes include different periods based on the situations in the past,
current situation and long-term domain.
The Planning Code specifies technical criteria and procedures to be applied by KOSTT in
planning and development of the Transmission System of Kosovo. Even users of the
Transmission System during the planning and development of their systems should consider
the Planning Code. This code also sets requirements for the collection of reliable
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 14 of 138
Office: Long-term Planning and Development
information from users, so that KOSTT can make planning and development of
transmission system in Kosovo.
Based on Article 15 of the 'License of the Transmission System Operator' Transmission
System Operator also has developed the basic planning criteria which are detailed in the
document approved by the ERO, "Transmission System Security and Planning Standards ”.
This document defines a range of criteria and methodologies that KOSTT should adopt
(enforce) in the planning process of developing the transmission network in Kosovo
2.2. Relevant data for planning –requirements for the transmission system users
In order for KOSTT to implement its Transmission Network development plan, all network
users are required to submit relevant data affecting the determination of the plan. This
section will briefly describe the process of collecting data needed for long-term planning,
since more detailed ones can be found in Planning Code - Grid Code, which can be
downloaded from the official site of KOSTT: www. kostt. com
During the process of applying for new connections to the transmission network, to enable
the completion of each connection offer - each user must submit to KOSTT the standard
data of planning and preliminary project planning, attached to the application for connection
application, and within two months from the date of the receiving the bid, the detailed
planning data should be submitted. Any change from the previous data network users, the
party is obliged to inform KOSTT in order to revise data.
KOSTT is also required to present users with the system data to enable users to model their
network related to the contribution of the fault currents.
2.3. Data Attributes
The data, which transmission system users are obliged to send to KOSTT, are characterized
depending on the type of system users. They usually fall into two main categories:
- Generator, and
- Load.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 15 of 138
Office: Long-term Planning and Development
Existing and new generators are required to submit data for generating units’ plants, which
are required by KOSTT, and all data changes that occur for different reasons. Each
generation in the application for connection to KOSTT for getting a new connection or
modification of an existing connection, must provide the necessary information as required
by Planning Code.
The data which are filled must contain the information such as plant location, name and type
of facility, estimated date of commission etc. , and information of the technical nature such
as expected monthly production of power, features of the power generator, the technical
characteristics of synchronous machine, turbine, adjustment equipment (speed regulator,
exciter, fluctuations stabilizers), the data of step-up transformer, the connection
configuration, data allocation and the type of relay protection, data for the own consumption
needs of the plant, etc. .
The load has the character of distribution points that use the transmission network. They
represent all the substations and distribution network, the network included 220 kV and 110
kV , and industrial customers connected to the transmission network.
Each user with the loading application for connection submitted to KOSTT for a new
connection or modification of an existing connection must provide the necessary
information as required by Planning Code. This information should contain information
about the substation location, time of becoming operational, load forecasting for the next 10
years, etc, and technical data such as configuration of the substation, voltage level,
transformers data, data on high voltage equipment, nature of the load, type of obstacles in
low voltage level, etc.
Detailed description about the user data at this point is made so that the reader could have a
clear perception that any inconsistence in this document is subject to the user if they follow
the criteria listed above.
2.4. Standards and criteria for transmission network planning
Transmission network planning is based on the criteria set out in Planning Code, which are
described in detail in the document “Transmission System Security and Planning Standards”.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 16 of 138
Office: Long-term Planning and Development
Standard method of planning or determinative methods of transmission network planning,
which presents the classical method used in many countries, which also applies to KOSTT.
The main principle according to which the transmission network is dimensioned, is the
necessity of fulfilling all technical requirements in accordance with Grid Code, and that the
N-1 elements at work facing the most difficult conditions for operation. So basically this
method of planning is mainly based on critical conditions of operation of the transmission
network. In principle, planning the transmission system in Kosovo is conduct is such a
manner that the operation of the system meets the criteria 'N-1'. However, in some
situations where it is not efficient to fulfill the 'N-1' criteria there will be applied exemptions
for a period of time.
In relation to substations 110/35 kV and 110/10(20) kV, and those combined
110/35/10(20) kV, fulfillment of the N-1 criterion is a complex process, depending on the
medium-voltage network infrastructure, which is managed by the DSO. The N-1 criterion is
not met in a large number of substations, in terms of transformation, but in substations with
two or more transformers installed, even despite the failure to fulfill the N-1 criterion, in
coordination with the DSO, this criterion may be achieved, if the connection reserves of
medium voltage grid are used. This implies the transfer of lost load from the failure of one
transformer to the other transformer, or to the other substation, by connecting switches,
which are mainly open and enter into operation in such cases. One of the most complex and
costly cases in fulfilling the N-1 criterion is when the substation has two medium-voltage
levels, 35 kV and 10(20) kV. The N-1 criterion can be accomplished at a much lower cost if
in the side of the distribution system, reserve modular substations 35/10 (kV) are installed,
which would serve only in cases for load transfer from 35 kV to 10 kV, or vice-versa. This
can be achieved by harmonizing the two development plans of the KOSTT and DSO,
thereby minimizing the investment cost.
2.5. 400 kV, 220 kV and 110 kV Network Planning Criteria
Kosovo's transmission system in the 400 kV and 220 kV levels has technical and economic
characteristics which differ from the 110 kV systems. Investment cost and their
dimensioning criteria are much higher than at 110 kV. Transmission system is
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 17 of 138
Office: Long-term Planning and Development
interconnected with regional transmission systems through the network of 400 kV and 220
kV, so the effects of investment in network voltage 400 kV and 220 kV are not isolated but
have a regional character. KOSTT has defined the strategy for developing the transmission
network which is oriented in strengthening/development of the network 400 kV and 110
kV, whilst network 220 kV will not be develop further, except for specific cases where no
other solution could be found.
Transmission System Planning is made according to the criteria defined by the Grid Code,
considering the fulfillment of the N-1 criteria, meaning that the system must be capable of
normal operation in case of occurrence of the fault in the network (in Kosovo or in other
systems) and the loss of one of the following elements:
- airline or cable lines
- transformer,
- compensator, and
- generator (this criterion cannot be seen in the plan, but it is a requirement for the developers of
generation capacity)
In case of loss of one of the above elements as a result of failures or maintenance,
transmission system must fulfill the following operation conditions:
- transmission lines should not be loaded above their thermal limits,
- reduction of the supply capacity is not allowed
- level of voltage tension and speed change cannot exceed allowed limits,
- transient and dynamic stability of the Power System should not be endangered, and
- power transformers should not be over-loaded.
The 110 kV network, which development is done in accordance with the Transmission
Connection Tariff Methodology of KOSTT, includes all equipment, voltage 110 kV (lines
and facilities) in addition to the distribution transformers 110/10 (20) kV and 110/35 kV
and relevant transformation fields, now transferred from KEK DSO to KOSTT.
In normal operating conditions the performance of the transmission system should be
operating in accordance with criteria outlined in the Grid Code.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 18 of 138
Office: Long-term Planning and Development
Grid Code defines the allowed voltage limits in the transmission system as in Table 2. 1
Table 2-1 Allowed voltage limits
*Allowed limits of medium voltage are referenced in the Distribution Code
Loading the transmission lines above the designed thermal limits of the conductors, will be
perceived as overload of the line. Also, each load of the transformer above their nominal
power will be considered as their overloading.
The following table shows thermal margins for conductor of the cross sections, which
standards are applied in KOSTT.
Table 2-2 Standard electrical parameters for air lines and cables
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 19 of 138
Office: Long-term Planning and Development
High voltage facilities operating in the transmission network should be durable and
sufficiently safe in case of failures of the system. The Electrical Equipment Code defines
maximal nominal currents, maximal fault currents and allowed duration of faults. Table 2-3
shows nominal currents for high and medium voltage equipment.
Table 2-3 Standard electrical parameters for disconnection equipment
2.6. Long-term planning criteria for the revitalizing of the transmission network
The revitalizing plan for the electro-energetic elements as overhead lines, transformers,
cables and substations, generally depends on the technical situation, their age and intensity of
use of these elements in retrospect. The revitalization plan of the transmission network
equipment is done as follows:
- Overhead lines: their revitalization depends on two factors: their age and level of losses
incurred in the line during a long – term period. For phase conductor and earth wire,
insulator, connection bridges, the time of 40 years represents a condition for adding them
into the revitalization list. Frequency of breakdowns in lines is an additional indicator to
select the revitalization list.
Nominal Voltage
Maximal
operation
current
Fault
current
Fault
dynamic current
Fault
permitted
current
400 kV 2500* A 40 kA 100 kA 1 s **
220 kV 2500 A 40 kA 100 kA 1 s **
110 kV 2000 A 40 kA 100 kA 1 s **
35 kV 1600 A 25 kA 63 kA 1 s **
10 (20) kV 2500 A 25 kA 63 kA 1 s **
10 kV*** 3150 A 40 kA 100 kA 1 s **
6. 3 kV 3150 A 40 kA 100 kA 1 s **
* In specific cases and conditions, the 3150 A current may be adapted ** In specific cases and conditions, the 3s time current may be adapted ***In specific cases when used for 63 MVA transformers, 110/10 kV and when Parallel works of the transformers in the 10 kV side is envisaged
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 20 of 138
Office: Long-term Planning and Development
In terms of losses in the list for revitalization are included the lines of cross section of
150mm2, which are also associated with the first factor, since the initial development phase
of the transmission network (1950-1970) 110 kV lines are built with the cross section
conductor of 150mm2. This development concept is now being applied in all ENTSO/E
transmission systems. 220 kV lines are considered to be older lines (>50-60 years), since
their development took place mainly during the 60-ies and 70-ies. The European concept
consists on the point that 220 kV lines are gradually re-raised to 400 kV level, mainly using
only their routes. The difficulties faced in expropriation of private properties for
development of new lines are distinct in all countries in Europe.
- Power transformers: plan of replacing the power transformers of the transmission
network is based on their expected lifetime, which is estimated at 50 years. Another
important factor which affects that the transformers will be included in the list for the
replacement is their factual situation, which is monitored by maintenance teams through
their periodic testing. Historical statistical data of events in specific transformers (load level,
number and frequency of measures in protecting transformers, gas analysis, etc. ) are an
important factor in selecting new transformers to replace the old ones.
Selection of nominal power of transformers will be standardized: For the level of 400/220
kV voltages 400MVA automatic transformers are recommended, for the level 400/110 kV
300 MVA automatic transformers are recommended, for the 220/110 kV voltage level,
150MVA automatic transformers, while for 220/35/10(20) kV, 110/35/10(20) kV levels, it
is transformers with 40 MVA and 31. 5 MVA power. For specific cases, such as large
industrial consumption, transformers with a higher power than 40 MVA can be adapted.
- Substations (overhead line bay and transformers): the revitalizing plan of the
substations areas, which are included in the defined boundaries of the transmission network,
is also based on age of the equipment and their factual situation. Priority for revitalizing have
substations with high impact on transmission systems, but also all the substations that their
age has passed 40 years. Systematic transition from oil-containing disconnection equipment
to gas equipment SF6 is an objective of KOSTT, provided by development and investment
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 21 of 138
Office: Long-term Planning and Development
plans. After the relocation of the boundary between KOSTT and DSO in the medium
voltage level, priorities in Revitalization projects have been revised, resulting with a change
of priorities in some projects presented in the previous year’s plan.
2.7. Planning methodology
The approach of the transmission network planning methodology consists of the following
steps:
- Collection of input data (creation of data base for computer modeling of the network).
- Definition of different scenarios taking into account factors strengthening the development of
generation, load, applications for connection, balance of power system, exchanges etc.
- The creation of computer models of the network transmission format to PSS/E.
- Determine the plan for revitalizing the existing electrical equipment on the basis of their life cycle.
- Identification of network constraints (N-1 tests).
- Definition of the possibilities of strengthening the network on the basis of N-1 tests.
- Analysis of the voltage profiles and losses in the system.
- The final definition of the reinforcement plan and plan for revitalizing transmission network
Figure 2-1shows the transmission network planning methodology
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 22 of 138
Office: Long-term Planning and Development
Figure 2-1 Transmission network process development and revitalization planning
2.8. Substation configuration planning
KOSTT has prepared a document on the Transmission System Security and Planning
Standards, which sets forth planning standards for substations 400/220 kV, 400/110 kV,
220/110 kV and 110/10 (20) kV, a document which is approved by ERO.
All 400/110 kV substations planned will be configured with double bus bars with coupler
and open system. Dimensioning of electrical equipment shall be based on the Electrical
Equipment Code, always being supported by computer analysis of power that define the
power flows and short circuit level to the respective substations. These criteria may
exempt those substations to which power generators and consumers of such importance
Gathering of input data and Creation of system model in PSS/E
Creation of models with current and Planned conditions
Technical analysis of the performance of
system ( Power flows , criteria N -1 with PSS/E
Identification of needs for system reinforcement
Creation of different scenarios of system reinforcement
Selection of most optimal scenarios and
Creation of final list of development
Projects and revitalization of the TN
Technical analysis of the performance of system (power flows, criteria N-1)
with PSS/E
Evaluation of applications for connection to TN
Connection approved
Revitalization plan of transmission network
Data on the state and ageing of equipments
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 23 of 138
Office: Long-term Planning and Development
can be connected, so as to require a higher operational security level in a link. In these
cases the design of bus bars can take into account additional specifications.
Figure 2-2 presents a standard configuration for substations of 400/110 kV voltage level.
Double bus bars system for 400 kV voltage level shown in figure 2-2 can be advanced
with the additional system of the auxiliary bus bars in substations that are connected to
more than three 400 kV lines.
Figure 2-2 Standard planning of the bus bars configuration of new substations in the transmission
network
220/110 kV substations’ configuration will be similar to the 400/110 kV substations.
Configuration of substations 110/10 (20) kV is designed based on two criteria regarding
system bus bars of 110 kV. Determining criteria in determination the busbar system
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 24 of 138
Office: Long-term Planning and Development
configuration will be number of lines planned to be connected in the 110 kV substations.
For substations that will be connected in the long term only with two lines, “H” type bus bar
system applies, as shown in figure 2-3. Medium voltage busbar system 35 kV and 10(20) kV
are also designed with the dual busbar system with a connecting field. Technical concept of
the construction of 35 kV transformer fields could be with outer construction (AIS), or with
internal modular construction installed within the commanding facility. The latter is more
preferred given the savings in space. 10(20) kV transformer fields are planned to be modular,
installed within the commanding facility. In addition, own consumption field, which after
displacement of the technical boundary with DSO belongs to KOSTT, should of the same
type.
Figure 2-3
Substations that will be connected with more than two lines, the double bus bar system with
couplers applies, as shown in the figure 2-4.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 25 of 138
Office: Long-term Planning and Development
Figure 2-4
Nominal power of the substation shall be projected based on long-term projections of the
relevant substation load. 110/10(20) kV transformers with nominal power of 2x31. 5 MVA
and 2x40 MVA shall be standardized during the projection of 110/10(20) kV substations,
whereby the space for the third transformer field shall be available to hold the
transformation reserves in case of unplanned load increase.
The dimensions of the phase and protective conductors for transmission lines are also
standardized as follows:
For 110 kV lines: conductor 1x240/40mm2 of ASCR, earth wire C 1x50 mm2;
For 220 kV lines: conductor 1x360/65mm2 of ASCR, earth wire C 2x50 mm2 or
1x490/65 mm2 of ASCR earth wire C 2x70 mm2.
For 400 kV lines: conductor mm2 of ASCR 2x490/65, earth wire Al 2x126 mm2.
There is also another technology and conductors that have been applied in KOSTT. These
conductors called "Hot wire" are the work of special alloy TACSR/ACS, which has the
ability to work at higher temperatures. Usually used for short length of lines and where there
is no possibility of strengthening the pillars. Their transmission capacity, e. g. a conductor of
TACSR/ACS of 150/25mm2 / is the same with the transmission capacity of a conventional
conductor 240/40mm2, while the weight is almost the same as conventional 150/25mm2
conductor. Their handicap is that such replacement of conductors does not help reduce
power losses, and therefore they are preferred only in short circuit lines and those cases
T 1 T 2 Reserve
Tr. Bay
Bus coupler
Line 110 kV
Line 110 kV
Line 110 kV Reserve bay Reserve bay
B 1 B 2
110 kV
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 26 of 138
Office: Long-term Planning and Development
where there is no possibility of reinforcement of the towers, which is not possible to install
because of the weight of the conventional conductor of 240/40mm2.
All the new (and enforced) lines will be equipped with at least 48 OPGW fibers in protective
conductor to support the planned telecommunications network SCADA/ EMS.
3. ELECTRICITY LOAD FORECAST
3.1. Introduction
One of the basic data determining future transmission capacity development is to forecast
electricity load or power. The load forecast represents an integral part of network, generation
and and transmission and distribution system operation planning. The main source of data
for development of load forecast in the next 10 years is the demand forecast model
developed by KOSTT, used by the document: Long-Term Energy Balance 2011 to 2020[2].
This model provides a 10 year forecast, hourly electricity demand. As such, this model allows
forecasting of load for each hour in the next 10 years, including seasonal peak loads (winter
and summer).
3.2. Background history of the load, and current situation
For several years the electricity sector in Kosovo has faced electricity supply problems. Daily
shedding, planned or unplanned are still present. This means that the recorded consumption
is not the same as demand which would exist if there was a safe and quality supply of
electricity. Planned reductions (scheduled) are mainly done in the hours when required
consumption cannot be covered by local generation capacity and lack of imports, or because
of capacity limitation of the DSO. The unplanned reductions happen due to unexpected and
unforeseeable faults, and because of interruptions in generation units, in the transmission
and distribution and network infrastructure.
Figure 3-1 shows a historical chart of development of maximum load for our country. The
unusual nature of the load curve in years reflects the political and economic situation in
Kosovo. After the end of the war in Kosovo (1999) and to date, the maximum load has
marked an average annual growth of 6%.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 27 of 138
Office: Long-term Planning and Development
Fig. 3-1Peak history over years in Kosovo
The figure 3-1 shows maximum loads registered for years 2002-2011, for winter and summer
seasons. The maximum load for 2011 increased for 0. 5 % compared to the previous year.
Tab. 3-1Maximum active loads, summer and winter, for the period 2002-2011
3.3. Demand profile
Characteristics of the load duration curve of the Power System of Kosovo has undergone
constant changes, both in terms of growth but also proportional to the change of load
factor. In figure 3-2 we can see the load duration curve for the previous year in 2011.
Summer consumption growth has led to increased load factor by 0. 57, while other
characteristics of the load duration curve are as follows
1. 54% of the annual period the load was above 1000 MW, 22% of the year, the load was in
the range between 800MW until 1000 MW.
Pe
ak [M
W]
Year 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Winter peak [MW] 723 759 811 898 916 933 967 1072 1156 1150
Summer peak [MW] 560 597 569 617 637 690 764 795 810 804
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 28 of 138
Office: Long-term Planning and Development
Fig. 3-2Curve of the duration of the load for 2011
The electricity demand in Kosovo marks a curve which in a considerable time of the year
(winter season), is not constant as a result of reduced consumption in times of peak loads.
Such a curve may be seen in the figure 3-3, which provides a weekly chart in the winter
season, for a typical week of January 2011. Latent consumption provides the real
consumption, if there would not be any consumption reduction. Load shedding causes
deformation of the consumption curves, and as such it differs them from no-shedding
curves, which do not display any obvious surge. Peak loads are marked between 19 and 21
hrs, while the minimum loads between 4 and 6 hrs in the morning.
LOAD DURATION CURVE FOR YEAR 2011
Peak Pmax=1150 MW Load factor LF=0.57
Average Power Paver=642 MW
1.54% of the year, P>1000 MW
22% of the year 800 MW<P<1000 MW
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 29 of 138
Office: Long-term Planning and Development
Fig. 3-3 Typical winter chart in January 2011
Figure 3-4 provides a daily diagram for a characteristic day of January 2011, which
corresponds to one of the reference points as per ENTSO/E. This diagram provides two
curves, from which the first shows consumption made, the second shows the latent
consumption, based on data registered in the dispatch diary of KOSTT. Load shedding in
normal working conditions of the electro-energy system usually occurs in two consumption
ranges: 9:00 – 12:00 and 17:00 – 23:00 hrs. The difference between maximum and minimum
values in winter loads for 2011 is around 450MW or 35% of the peak value.
400
500
600
700
800
900
1000
1100
1200
1300
1 9 17 25 33 41 49 57 65 73 81 89 97 105 113 121 129 137 145 153 161
[MW
]
7 days
Latent consumption Consumption
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 30 of 138
Office: Long-term Planning and Development
Fig. 3-4 Daily load diagram for one selected day in January 2011
Figure 3-5 provides a daily chart for a typical day in July 2011. There is no load shedding in
this chart, and the difference between maximum and minimum values of daily loads is
around 51%. In this time period, this difference in loads makes it very difficult to balance the
system, especially after midnight, when loads are minimal, and fall under the boundaries of
technical minimums of existing plants.
955
10451065
630
915
1015
1035
500
600
700
800
900
1000
1100
1200
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Daily Load: Wednesday 3-rd January 2011
Latent consumption realized consumption
Load shedding
MW
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 31 of 138
Office: Long-term Planning and Development
Fig. 3-5 Daily load chart for a typical day in July 2011
3.4. Long term forecasts of demand 2013-2022
The power and load forecast is based on the forecast provided by the document: “Long-
Term electricity Demand 2013-2022”.
For forecasting power and load demands in Kosovo, a complex mathematic model was
created in Excel, which links the influence of four variables (correction factors) in calculating
power and electricity demands. The above-mentioned factors are presented in the following:
- Factor 1: Implementation of the Government program for efficient electricity use;
- Factor 2: Reduction of consumption due to a more efficient billing, and more effective metering and
checking procedures (reduction of commercial losses);
- Factor 3: Influence of GDP forecast in consumption development;
- Factor 4: Forecasting technical losses in transmission and distribution networks
The forecast of demand development for power in the period 2013-2022 according to three
scenarios of growth is presented by figure 3-6, while numerical data corresponding with
figure 3-6 are presented in the table 3-2.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 32 of 138
Office: Long-term Planning and Development
The basic scenario of load development is characterized by an average annual growth of 2.
41%. This load development scenario shall be the main input in assessing operational
performance of the transmission network.
Figure 3-6 . Low, basic (average) and high growth scenarios for peak loads (maximum load)
Table. 3-2. Respective data of peak forecast, related to Figure 3-6
4. GENERATION CAPACITIES OF KOSOVO POWER SYSTEM
4.1. Introduction
Electricity in Kosovo is produced by two relatively large power plants: PP Kosovo A and
Kosovo B. Both power plants use coal - lignite as fuel. Pursuant to the Government Energy
Program, it has been foreseen that in the period between 2016-2017, capital overhauls will be
1584
1072
1158 11501170
12201250
12831310
13401365
13901410
1452 1494
1404
1000
1050
1100
1150
1200
1250
1300
1350
1400
1450
1500
1550
1600
1650
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
High scenario Base scenario Low scenarioMW
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 33 of 138
Office: Long-term Planning and Development
performed on B1 and B2 units, which is to reflect on reliability of operation of these two
units. Units A3, A4 and A5 of the TPP Kosova A according to the Energy Strategy 2009-
2018, shall be operating until the end of 2017, until they are ultimately decommissioned.
Table 4-1. Main features of Kosovo A and Kosovo B generation units
Apart from Kosovo A and B power plants, managed by KEK, there is also a hydro-power plant Ujmani (2x17. 5MW), managed by the POE Ibër-Lepenci. There are also low capacity hydro-power plants in operation. The table 4-2 provides the key data on small HPP-s connected to the distribution network.
Table 4-2. Main features of existing hydro-power plants of Kosovo
Unit Starting Time Action Lifetime
Kosova A
A3 1970 Regular overhauls 2017
Existing TPP A4 1971 Regular overhauls 2017
A5 1975 Regular overhauls 2017
Kosova B
B1 1983 Capital Revitalization(2016) 2030
B2 1984 Capital Revitalization(2017) 2030
Ujmani
Existing HPP U1+U2 1983 Regular overhauls >2030
Lumbardhi
G1+G2 1983 Planning increasing capacity 2030
EXISTING GENERATION UNITS
*During 2012 and 2013 is expected to install new filters in A3,A4 and A5
Installed Net Disposal HPP UJMANI G1 17.5 16 16 1983 G2 17.5 16 16 1983 HPP LUMBARDHI* G1 4.04 4.00 4.00 1957 (2005) G2 4.04 4.00 4.00 1957 (2005) HPP BURIMI G1 0.34 0.34 0.34 1948(2010) G2 0.136 0.13 0.13 1948(2010) HPP DIKANCE* G1 0.67 0.66 0.66 1957(2010) G2 0.67 0.66 0.66 1957(2010) HPP RADAVC 0.00 G1 0.14 0.14 0.14 1934 G2 0.14 0.14 0.14 1934
* HPP Lumbardhi and HC Dikance are given in private investment concession
GENERATING UNIT Capacity units of HPP [MW] Put on operation
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 34 of 138
Office: Long-term Planning and Development
4.2. Planning of the new generating units
Estimates of new generating units for the period 2013-2022 is designed based on the
expected generation from existing generating units, including the continued operation of
some units of PP Kosovo A until 2017, existing hydro plants and new ones planned to be
built, as well as production from PP "New Kosovo" and HP Zhuri
The new generation capacity development concept is focused on primary energy resources in
Kosovo. This concept presented by the Energy Strategy 2009-2018, and updated in the most
recent data of the MED, forecasts during the 2013-2022 period:
Development of the Kosova e Re Power Plant
Development of the Zhur Hydro-Power Plant
Development of renewable energy generation capacities (small HPPs, wind turbines, biomass-
fueled plants, and solar panels)
The Kosova e Re Power Plant project shall consist of two units at an installed capacity of
2x300MW. The first unit (300MW) is expected to be commissioned by the early 2018, while
the second unit in 2019. The development of the Kosova e Re Power Plant will be necessary
for the security of supply of electricity consumption increasing in Kosovo. The Power Plant
is expected to abide by all environmental requirements as set and mandated by the European
Union, by using advanced technology which is already proven in commercial use. These
technologies should apply modern coal combustion processes, with a view of achieving a
general efficiency rate of 37%-40%. The development of the Kosova e Re Power plant
project was expected to be coordinated in time with the TPP Kosovo A decommissioning
process (2016-2017), and the capital overhaul of the two TPP Kosovo B units (2016-2017),
but due to current delays, such coordination seems unlikely.
With a view of securing uninterrupted supply of sufficient lignite for the new and existing
plants, a new lignite mining area “Sibovc South” has been opened, with reserves estimated at
830 M tonnes, which is sufficient to supply power plants for a long-term period of over 40
years. The mine is already fully operational, with full generation capacities.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 35 of 138
Office: Long-term Planning and Development
The base scenario forecasts the development of the known project of the accumulation HPP
“Zhuri”, at a capacity of 305MW, and estimated annual energy generation capacity of 398
GWh. This HPP is planned to be commissioned for operation in the early 2017. Completion
of this project is considered to be of high importance for the optimization of the electro-
energy system, thereby influencing the stability and flexibility, and regulatory reserves for the
system.
4.3. Renewable sources
According to the objectives of the European Strategy 20-20-20 Renewable Energy Directive,
by 2020, 20% of the total energy generated shall be by renewable sources, such as wind
plants, hydro-power plants, etc. Kosovo has also set long-term indicative targets related to
the development of renewable sources agreed with the Energy Community. Renewable
energy source potentials in Kosovo are not as large, both in terms of water potential and
wind. Nevertheless, there are certain regions endowed in such potential, and they must be
exploited. The plans for development of renewable energy generation capacities are also
supported and promoted by the MED, namely through the Government Program for Clean
and Efficient Energy. This program sets the indicative goals for amounts of energy to be
generated from renewable sources. The base scenario of development of renewable sources
requires the development of a large number of small HPPs (>16), totaling a capacity of 128.
2 MW, by 2022.
A considerable contribution in the renewable energy generation is left to the wind turbines,
in which case the plan is to install up to 154 MW of wind generation capacity by 2022, at an
estimated average capacity factor of 0. 22. KOSTT has so far received applications by several
private investors for connecting wind energy generation plans to the transmission network
but still no significant developments regard this.
Development of generation plants which would use biomass and urban waste as fuel is
forecasted to happen by 2014, with a progressive development of capacities of up to 10 MW
by 2022. Meanwhile, a slower development is forecasted for solar panel generated electricity,
as a result of the costly technology.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 36 of 138
Office: Long-term Planning and Development
4.4. Application for connection of the HPP “Lumi Deçani” with the transmission
grid
Based on the application of 19. 09. 2012, received by the company “KELKOS ENERGY”,
in relation to the possibility of connecting the Hydro-Power Plant with a generation capacity
of 35. 5MW to the transmission network, the KOSTT has undertaken a technical analysis, by
determining the optimal configuration of the connection with the transmission network. The
HPP proposed consists of an expansion of capacities of the existing HPP Lumbardhi (8.
3MW, 22GWh annual generation), by creating a series of small HPP-s on the Deçani river.
The applicant is planning the development of three additional HPPs with the following
specifications:
- HPP Deçani, available capacity PA=14. 3 MW, and planned annual generation of 41. 9 GWh.
- HPP Belaja, available capacity PA=8. 1 MW, and planned annual generation of 24. 8 GWh
- HPP Lumbardhi, available capacity PA=4. 8 MW, and planned annual generation of 17 GWh
In due consideration of the existing HPP Lumbardhi, the applicant has requested the
connection of a total hydro-generation capacity of Pg=35. 5 MW (Wg=105. 7 GWh) with
the transmission network. Upon a detailed technical analysis, the connection is to be made
with the 110 kV busbars of the Deçani substation, through a 35 kV line and uploading
transformer 35/110 kV , at a 40 MVA power.
Figure 4- 1 shows the basic configuration of the interconnection of HPP generators
with the connection point at SS Deçani.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 37 of 138
Office: Long-term Planning and Development
Fig. 4-1 Optimal connection point of the 35. 5MW HPP to the transmission grid
5. KOSOVO TRANSMISSION NETWORK DEVELOPMENT
PROJECTS
5.1. History of the transmission network
Kosovo Transmission Network during the years has been developed in several stages of
expansion, reinforcement and consolidation.
Between 1953 and 1958, the first line of 110 kV was built in Kosovo, Novi Pazar (Serbia)
until Butel (Macedonia), by interconnecting the substations (SS): SS Vallaç, Trepca SS, SS
Vucitrn, SS Kosovo A, SS Prishtina 1 and SS Prishtina 4, SS Ferizaj 1 and SS Sharri. 110 kV
conductor built in the initial development of the network were 110 kV cross section
conductors of 150mm2.
In 1960 the first line of 220 kV was built in Kosovo, SS Krushevci (Serbia) to SS Kosovo A,
which was at that time in the construction phase. From 1962 to 1975 it was constructed (PP)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 38 of 138
Office: Long-term Planning and Development
Kosovo A with its five units. In 1978 was built the first line of 400 kV in Kosovo connecting
to the SS Nish (Serbia) with SS Skopje (Macedonia) through SS Kosovo B.
In 1981 was built the HP Ujmani connected through 110 kV line with SS Vallaçi.
The second 400 kV line of the interconnection Ribarevina (Montenegro) to SS Kosovo B
was built in 1983, as well as two 400 kV lines connecting TP Kosovo B (1983) with SS
Kosovo B. In the same year it was built the 220 kV lines from SS Kosova B to SS Prizren 2,
through the switch gear Drenas. In the same year was also built the second 220 kV line to
Drenas followed by the double line for the supply of industrial facilities of Feronikeli.
The 220 kV interconnection line from SS Prizren 2 to Hydro power plant (HPP) Fierza
(Albania) was build in 1988; in the same year, the 220 kV double lines from the SS Kosovo B
to SS Prishtina 4 were also build. Also in the mid 70s and 80s the network of 110 kV
undertook visible development, using conductors of the large section of 240mm2. The year
1990 represents the end of investments in transmission network for a period of 10 years
until 2000, which represents a break of 10 years without investing in the development of the
transmission network. This can be seen in figures 5-1 and figure 5-2.
Fig. 5-1 Intensity of investments in lines1980-2012
km 100
1980 1990 2000
400 kV 220 kV 110 kV
2010
20 40 60 80
Year
km 100
1980 1990 2000
400 kV 220 kV 110 kV
Line investments
2010
20 40 60 80
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 39 of 138
Office: Long-term Planning and Development
Fig. 5-2 Intensity of investments in substations 1980-2012
After the war in Kosovo, the condition of the SEE in Kosovo was dire, including in
generation, transmission and distribution. Emergency investments in the SEE begun at this
time, supported by the Kosovo Budget and international donors. Due to great demand, the
transmission network did not follow the rapid consumption growth trend after 2000.
5.2. Implemented projects 2007-2012
After the establishment of KOSTT and to this date, intensive capital investments have been
done in the transmission network to develop and strengthen the transmission network.
Transmission network reinforcements, modernization of supporting systems for System
Operation, have resulted with a notable increase of reliability and security of supply. Table 5-
1 lists projects implemented thus far. The process, from planning until implementation, was
rather challenging, considering the high development dynamics and implementation of such
a high number of projects. The most challenging process was the implementation of projects
in the same time period, taking into account the minimization of undelivered energy as a
result of load shedding to carry out works during the project implementation. This challenge
was successfully realized thanks to the commitment of KOSTT engineers in optimizing the
project implementation process.
Years
Nr SS/ vit
3
1980 1990 2000 2010
2
1
Nr SS/ vit
3
1980 1990 2000
Investments in substations
2010
2
1
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 40 of 138
Office: Long-term Planning and Development
Table 5-1. List of realized projects in KOSTT from 2007 until 2012.
Nr Project name Year
1 Replacement the line conductor 110 kV, L 125, SS Kosova A-SS Vushtrri 1&2 2007
2 Replacement the line conductor 110 kV, L164/3, SS Prizreni 1-SS Prizreni 2 2007
3 Replacement circuit breaker 110 kV, SS Prishtina1 & SS Prishtina2 2008
4 New line 110 kV, SS Prizren 2- SS Rahoveci 2008
5 Replacement the line conductor 110 kV, L126/1 SS Deçan- SS Gjakova 1 2009
6 AT1 at SS Kosova A, 220/110 kV 2009
7 Rehabilitation of SS Kosova A 2009
8 Rehabilitation of SS Prishtina 1 2009
9 Package Project PEJA 3 2009
10 Replacement of relay protection at SS Kosova B & SS Prishtina 4 2009
11 ITSMO Meters (to the borders) 2010
12 Line 212 adaptation as 110kV,SS Kosova A-SS Ferizaj 1 2010
13 New line 110 kV, SS Peja 3-SS Klina,within the package project Peja 3 2010
14 Connection of SS Skenderaj 110/10 kV, with double circuit line 110kV, in connection point Line SS Vallaq -SSPeja 3
2010
15 AT3 at SS Prishtina 4, 220/110 kV 2010
16 Replacement the line conductor 110 kV, L 126/5, SS Peja 1- SS Peja 2 2010
17 Rehabilitation of SS Kosova B 2011
18 Package Project FERIZAJ 2 2011
19 SCADA/EMS 2011
20 Rehabilitation of SS PRIZRENI 2, 220/110kV & AT3=150MVA 2012
21 IT system to support market operation 2012
22 Replacement of relay protection at SS Prishtina 2 & SS Prishtina 3 2012
23 Circuit breaker 400 kV for generation bay at SS Kosova B 2012
24 Busbar seperation into two sections at SS Gjilani 1 & SS Theranda 2012
25 Rehabilitation of equipment for own supply at SS Kosova B 2012
26 General rehabilitation equipment 110 kV at SS Prishtina 3 (system GIS) 2012
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 41 of 138
Office: Long-term Planning and Development
5.3. Transmission network infrastructure development 2013-2022
5.3.1. Introduction
This chapter presents and examines the development projects of the transmission network
in the period 2013-2022. Considering the planning process of the transmission network as an
extremely complex process, with greater dependence on many factors, the ten-year domain
that defines this document is divided into two periods: first five years 2013-2017 and the
second period of five years, 2018– 2022.
The first period of five years is considered relevant and influential in the long term
development of the network and with high probability of implementation and as such the
projects that are included in this period of time are analyzed in detail. Second period of
2018-2022 includes optional projects in a comprehensive manner that have internal or
regional character for which KOSTT considers their importance and their contribution in
achieving the technical standards for operation of the transmission system in order to
support the electricity market.
Transmission network development projects are divided into four categories:
- Transmission network reinforcements
- New 110/10(20) kV nodes
- Rehabilitation of the transmission network
- Supporting projects of the transmission system (management, monitoring, measurement and control).
Because of considerable complex dependence on the various factors for the implementation
of the projects, the time and manner of such implementation can be considered as subject to
possible changes and as such the next document will revise the data and update them.
Tables contain the project identification codes (ID), a general description of the project, the
expected completion time and reasons and effects of project implementation.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 42 of 138
Office: Long-term Planning and Development
5.3.2. Ongoing development projects
The investment intensity in the transmission system infrastructure continued throughout
2011-2012, pursuing objectives and aims deriving from the long-term development plan of
KOSTT. Table 5-2 shows projects in implementation during 2012, or which are in the
tendering process.
Tab. 5-2 Projects in implementation, and projects being procured
Nr Project name Technical description Year
1 Transformer 40 MVA,110/10(20) MVA
New power transformer 40 MVA, 110/10(20) kV, in case of emergency
2012
2 Rehabilitation of equipment for own supply at SS Kosova B
Modernisation of AC/DC supply 2012
3
Replacement the line conductor 110 kV, L125/2 & L125/3 , (SSVushtrri 1-SSTrepçë-SS Vallaq)
Replacement the line conductor 150/25mm2 into 240/40mm2 , length 9.6km from SS Trepça up toSNS Vushtrria 1, and 11.4 km from SS Trepça up to SS Vallaqi
2012-2013
4 Rehabilitation of HV facilities at SS Ferizaji 1 & SS Gjilani 1
110 kV circuit breakers and disconnectors replacement 2013
5 Connection point of SS Lipjani at line 110 kV, L112
New double circuit line 110 kV, from SS Lipjani up to connection point at line L112. Connection with double circuit line 110 kV at the exsisting line L 112 SS Kosova A –SNS Ferizaj 1
2013
6 Allocation of L1806 line from SS Gjakova 2 up to SS Gjakova 1
Construction of double circuit line 110kV, 4km from the connection point line L1806 (SS Klinë-SS Gjakova 2) up to SS Gjakova 1 Total rehabilitation of SS Gjakova1 ( 110kV equipment). Transfer on double busbar.
2013
7 Rehabilitation of HV equipment at SS Prizreni 3
Replacement of three line fields 110 kV, of two transformer fields 110 kV and one coupling bay 110 kV. Replacement of protection equipment for three line fields.
2014
8
Rehabilitation of HV equipment at SS Gjakova 2
Replacement of three line fields 110 kV, of two transformer fields 110 kV and one coupling bay 110 kV. Replacement of protection equipment for three line fields.
2014
9 LFC- Secondary regulation
Project contains telecommunication routes, hardware and software equipment, which will enable the optimal implementation of the secondary regulation of both systems.
2014
10 New interconnection line 400 kV SS Kosova B - SS Kashar(AL)
New line 400 kV, 2x490mm2, length 239km of which 85.5km in the territory of Kosova. HV equipment, control protection and metering system
2015
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 43 of 138
Office: Long-term Planning and Development
Four projects from the list 4, 6, 7 and 11) pertain to projects of enforcement of transmission
capacities. The major interconnection project 400 kV SS Kosovo B – SS Kashar is in the
process of selecting the bidders and is expected to enter into operation by 2015.
5.3.3. List of new development projects planned for the period 2013 -
2022
The following is a list of projects planned broken down by categories, as an outcome of an
optimal selection of various scenarios of network reinforcement during the planning process.
These projects span through the period 2013-2022. The projects are presented in tables
categorized as per respective specifics. A large number of these projects is part of the
Development Plan 2012-2021, as approved by the ERO, while there are some new projects,
resulting from a detailed analysis of the network during the planning process. Factors
considered influential in redesigning some earlier projects, in changing their implementation
period, and selection of some new projects, are processes which are not dependent on
KOSTT, such as: applications for new power or generation connections, funding security
aspects, property expropriations, etc. For the reasons mentioned above, the planning process
and projects selected are adapted to the changes which pursued in the meantime.
In addition, relevant impact in the review of priorities in planned investments is the
displacement of the technical boundary from the 110 kV level to the medium voltage level.
On this occasion, after analyzing and reviewing the technical situation of assets transferred
from KEK-DSO in KOSTT, projects are identified which are qualified with a high priority,
always calling in maintenance of the security of supply.
5.3.3.1. The list of new projects in the category of transmission network
reinforcement
The table 5-3 provides a list of projects planned for the next 10 years, which are considered
to be influential in establishing network capacities, pursuant to requirements of the Grid
Code. Projects are ranked according to their planned implementation period. Some of the
projects should be funded or co-funded by donors such as the IPA 2011 program, KfW etc.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 44 of 138
Office: Long-term Planning and Development
The commissioning date of the projects will depend on procedures implemented by donors.
Network performance analysis has shown that projects such as second transformer at SS
Peja 3 are necessary much earlier (2012-2013), but due to their incorporation with the IPA
2011 program, cannot be implemented earlier. For the IPA 2012 program, a certain number
of projects have been proposed, as shown in table 5-4. The vast majority of investments is to
be made by KOSTT with soft loans offered by the German Bank for Reconstruction
(KfW), while the remaining part shall be a donation of the European Union and investments
of the Kosovo Budget.
Table 5-3 List of projects planned for reinforcement of transmission network 2013-2022
PROJECTS OF CATEGORY: REINFORCEMENT OF TRANSMISSION NETWORK (2013-2022)
No
ID
Title of Project Technical Description Rationale
Year
1
T&
D T
R_
SK
EN
Second transformer 40 MVA in SS Skenderaj
a) Transformer TR2 110/10(20) kV , 40MVA b) 1 transformer field 110 kV and 10(20) kV completed
Increasing security and reliability of supply in Skenderaj. Optimization of the maintenance process of Substation. Creation of transformation reserves.
Q2-2
014
2
T-A
TR
/P
EJA
3
AT2-300 MVA in SS PEJA3 and SS FERIZAJ 2
(a) Auto-transformer 300 MVA, 400/110 kV ; (b) Installation of high voltage equipment for 400 kV and 110 kV transformer fields
Increase of transformation capacities and fulfillment of the N-1 security criterion. Q
4-2
015
3
T-L
PE
JA3-P
EJA
1
New line 110 kV SS Peja 3- SS Peja 1 and revitalization of SS Peja 1
a) 28 km, Al. Çe240 mm2; b) Line field in SS Peja 3; c) Revitalization of SS Peja 1 of equipment and busbar system in the level 110 kV , moving to dual busbar system and GIS system for 110 kV equipment.
Construction of the line enables the fulfillment of the N-1 criterion. In addition, Revitalization of SS Peja 1 affects the increase of security and reliability of system operation.
Q4-2
015
4
T-R
IV/
L12
6/
5
Revitalization of the line 110 kV : L126/2 SS Peja 2- SS Deçan
(a) Replacement of conductor from 150/25 mm2 to 240/40 mm2 in a distance of 14. 57 km from SS Peja 2 until SS Deçan (b) Reinforcement of concrete towers and replacement of existing insulators with composite insulation
Increase of transmission capacity of the line from 83 MVA to 114 MVA with the aim of reducing power losses, improving the N-1 security criterion for the substation ring110 kV Peja3-Peja1-Peja2-Deçan –Gjakova1.
Q4-
2015
5
T&
D T
R_
KL
INA
Second transformer 40MVA in SS Klinë
a) Transformer TR2 110/10(20) kV , 40MVA b) 1 transformer field 110 kV and 10(20) kV completed
Increase security and reliability of Klina supply. Optimization of the maintenance process of Substation. Creation of transformation reserves.
Q2-2
018
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 45 of 138
Office: Long-term Planning and Development
6
T-R
IV/
L16
3/
1
Revitalization of the line 110 kV : L163/1
(a) Replacement of conductor from 150/25mm2 to 240/40mm2 with a length of 32km from SS Kosova A until SS Vallaqi; (b) Reinforcement of concrete towers and replacement of existing insulators with composite insulation.
Increase of transmission capacity of the line from 83 MVA në 114 MVA with the aim of reducing power losses, improving the N-1 security criterion for the substation ring 110 kV Kosova A-Bardhi-Vaganica-Vallaq.
Q4-
2019
7
T&
D
TR
_B
UR
IMI
Second transformer 40MVA in SS Burim
a) Transformer TR2 110/10(20) kV , 40MVA b) 1 transformer field 110 kV and 10(20) kV completed
Increase security and reliability of Burimi supply. Optimization of the maintenance process of Substation. Creation of transformation reserves.
Q2-2
020
8
T-R
IV/
L11
8/
3
Revitalization of the line 110 kV : L179/1 SS Prizren 1 – SS Prizren 3-
a) Replacement of conductor from 150/25mm2 to 240/40 mm2with a length of 4. 69 km from SS Prizren 1 to SS Prizren 3
Increase of transmission capacity of the line from 83 MVA në 114 MVA with the aim of reducing power losses, improving the N-1 security criterion.
Q3-2
020
9
TR
IV/
L15
5/
2
Revitalization of the line 110 kV : L155/2 in coordination with construction of SS Leposaviq 110/10 kV
a) Replacement of phased and protection conductors until (14km) b) Reinforcement of towers and replacement of insulators.
Strengthening transmission capacities and supporting the load in the northern part of Kosovo Q
4-2
020
10
T-L
2 P
Z1-
PZ
2
New line 110 kV SS Prizren 1- SS Prizren 2
a) 3. 5km, Al. Çe240mm2, b) Line field 110 kV in SS Prizren 2, c) Line field 110 kV in SS Prizren 1
Continuous growth of consumption in the region of Prizren risks the security of supply of substation ring Prizren 1, Prizren 3, Therandë. Ndërtimi i linjës se re transmetuese mundëson plotësimin e kriterit N-1.
Q4-2
021
11
T&
D T
R_
Beri
v
Second transformer 40MVA in SS Berivojcë
a) Transformer TR2 110/10(20) kV , 40MVA b) 1 transformer field 110 kV and 10(20) kV completed
Increasing security and reliability of supply in Kamenica. Optimization of the maintenance process of Substation. Creation of transformation reserves.
Q2-2
021
12
T-L
2 P
EJA
3-U
JMA
N
New line 110 kV Peja 3- HC Ujmani
a) 25km, Al. Çe240mm2 b) Line field 110 kV in SS Peja 3 c) Line field 110 kV në HC Ujmani
Creation of new ring 110 kV Peja 3-Ujman-Vallaq and fulfillment of the N-1 criterion Q
3-2
022
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 46 of 138
Office: Long-term Planning and Development
13
T/
RIN
G_
400 k
V
Package Project RING 400 kV GJAKOVË-PRIZREN-FERIZAJ
(a) Construction of the distribution system 400 kV SSH Gjakova 3 which includes 3 line fields and a connection field (b) Construction of SS Prizren 4, 400/110 kV, 1x300MVA in follow up of SS Prizren 2 which includes two 400 Kv line fields and one connection field 400 kV c) Construction of the 400 kV line, 31.5 km from SSH Gjakova 33 to SS Prizren 4 d) Construction of the line 400 kV, 56.5 km SS Prizren 4 - SS Ferizaj 2
Ring road configuration of the 400 kV network, with a view of optimizing load flows, support of new generation and load. Q
4-2
022
5.3.3.2. List of new projects, to support the load
After the transfer of 110 kV assets from the KEK-DSO to the KOSTT, the approach of
planning new 110 kV nodes pertaining to the category of load support has been revised.
Based on the applicable connection fee methodology in the transmission network, these
projects have been categorized as optional, and they appear in the plan only when an
application is submitted by the DSO, and received by the KOSTT, for their connection.
Currently, activities are ongoing in amending the connection fee methodology, thereby
reviewing more optimal approaches in the process of 110/x kV node planning. This
development plan, in a difference from the last year’s plan, four other projects of the load
support category are presented, harmonized with the priorities recommended by the KEK-
DSO development plan, approved by the ERO. The following table presents the load
support projects for the next 10 years:
Table 5-4 List of projects planned for reinforcement of transmission network 2013-2022
PROJECTS AIMED AT SUPPORTING THE LOAD (2013-2022)
Nr
ID
Title of Project Technical Description Rationale
Vit
i
1
T&
D-L
2/
MIT
2
SS Mitrovica 2 with 110 kV transmission lines
a) Dual line 0. 5km,110 kV connection in the line Vallaq-Palaj and dual line 0. 6km connection in the line Trepça-Vallaq. b) SS Mitrovica 2, 110/10(20) kV , 2x40MVA c) 2 transformer fields in 110 kV and 10(20) kV , 4 line fields 110 kV and connection fields 110 kV . c) command facility with ancillary equipment
Increase of security and quality of supply for the region of Mitrovica Q
4-
2017
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 47 of 138
Office: Long-term Planning and Development
2
T&
D-L
2/
DR
AG
ASH
SS Dragashi and line 110 kV SS Kuks-SS Dragash- SS Prizren 21
(a) SS Dragashi, 2 transformation fields, 2 line fields and one connection field. b) Single line, 8km, Al. Çe240mm2 from SSPrizren 2 to Zhur (dual towers). c) Dual line 13km, Al. Çe2x240mm2 from Zhuri until SS Dragashi d) Single line 26km, Al. Çe240mm2 from Zhur until Kukës (from the border to Kukës 17km)
Optimization of operation of both systems of Kosovo and Albania. Quality and reliable supply for Dragash. Reduction of load flows at SS Prizren 1.
Q4-2
017
3
T-L
/M
AL
ISH
EV
A
Project Package SS Malisheva with 110 kV transmission lines
a) 110kV line Malishevë _Rahovec 16km, and line Malishevë -Therandë 16. 5km, Al. Çe240mm2 b) 2 transformers 31. 5MVA, 110/10(20) kV c) 2 transformation fields 110 kV and 10(20) kV , 2 line fields 110 kV , 1 connection field 110 kV . d) Command facility with ancillary equipment
Increase of security and quality of supply in the region of Malishevë, and fulfillment of the N-1 criterion for SS Rahoveci Q
4-2
018
4
T-L
/P
RIS
HT
INA
6
Package Project Prishtina 6 me dual underground cable 110 kV
a) GIS type substation, 110/10(20) kV , 2x40MVA b) two cable fields 110 kV b) two cables 110 kV , 1000mm2, with a length of 5. 5km c) 2 transformer fields in 110 kV and ne 10(20) kV , 1 connection field 110 kV . d) Command facility with ancillary equipment
Increase of security and quality of supply in the Prishtina center, Fulfillment of the N-1 criterion, reduction of technical losses and discharge of the capital’s 110 kV substations.
Q4-2
018
5
T-L
/F
_K
OS
OV
A
Project SS Fushe Kosova
a) Dual line connection 110 kV ,1. 5kM in the 110 kV line Kosova A- Lipjan (L112a) b) Substation 110/10(20) kV 2x40MVA me 2 transformation fields 110 kV and 10(20) kV , me 2 line fields 110 kV , me 1 connection field 110 kV c) command facility with ancillary equipment
Increase of security and quality of supply in the region of Fushë Kosove, si and fulfillment of the N-1 criterion. Q
4-2
019
5.3.3.3. Projects planned for the category of revitalization of KOSTT
substations
The following table contains a list of projects related to the process of revitalization of
substations managed by KOSTT.
Tab. 5-5. List of projects of the category of revitalization of substations
PROJECTS OF CATEGORY: REVITALIZATION OF SS (KOSTT) - (2013-2022)
Nr
ID Title of Project Technical Description Rationale Viti
1
TD
/R
IV_
GJ1
Revitalization of equipment of TM (35 kV ) in SS Gjakova 1
a)Replacement of 2 transformation fields 35kV , replacement of 1 Petersen reactance, replacement of connection equipment of the neutral of both transformers andb) replacement of dy mbrojtjeve rele te transformatorëve
To increase the security and reliability of substation’s operations Q
4-
2013
1Project SS Dragash with interconnection line 110kV in Kukes is presented in TDP 2012-2021
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 48 of 138
Office: Long-term Planning and Development
2
TD
/R
IVG
JL1
Revitalization of equipment of TM(35 kV ) in SS Gjilani 1
a)Replacement of 2 transformation fields 35kV , replacement of 1 Petersen reactance, replacement of connection equipment of the neutral of both transformers and b) replacement of two transformer relay protections
To increase the security and reliability of substation’s operations Q
4-
2014
3
T/
CB
_P
R4
Replacement of breakers in SS Prishtina 4
a)Replacement of breakers of 110 kV and 220 kV power, except two ATR3 fields
To increase the security and reliability of substation’s operations Q
4-2
015
4
TD
/R
IVF
Z1
Revitalization of equipment of TM(35 kV ) in SS Ferizaj 1
a)Replacement of 2 transformation fields 35kV , replacement of 1 Petersen reactance and b) replacement of connection equipment of the neutral of both transformers .
To increase the security and reliability of substation’s operations Q
4-
2015
5
TD
/R
IVP
2&
LP
Revitalization of equipment of TM(35 kV ,10 kV ) in SS Prishtina 2 andSS Lipjani
a)Replacement of 2 transformation fields 10 kV , replacement of 1 transformation field 35 kV ,replacement of 2 Petersen reactance and b) replacement of connection equipment of the neutral of both transformers in SS Lipjani .
To increase the security and reliability of substations’ operations Q
4-
2017
6
TD
/R
IV_
TH
ER
Revitalization of equipment of TLin SS Theranda
a)Replacement of two line fields 110kV , replacement of two transformation fields 110 kV and one connection field 110 kV. Move to dual busbar system. b) Replacement of two transformation fields 10 kV and one 35 kV . c) Replacement of field for own consumption
To increase the security and reliability of this important substation’s operations for supply for Theranda
Q2-2
018
7
TD
/R
_V
AL
L
Revitalization of equipment of TLin SS Vallaqi
a)Replacement of 5 fields of lines 110kV , replacement of two (2) transformation fields 110 kV . b) Replacement of 110 kV busbar systems and portals and replacement of a connection field 110 kV.
To increase the security and reliability of this important substation’s operations to supply a part of Mitrovica Q
4-2
019
8
TD
/R
IV_
VIT
Revitalization of HV equipment at SS Vitia
(a) Replacement of 2 110 kV line fields, replacement of (2) transformer fields 110 kV For own consumption 35 kV. b) Modernization of transformer protections.
To increase the security and reliability of this important substation’s operations for supply for Vitia
Q2-2
021
5.3.3.4. Projects planned in the category of supporting transmission system
operation
The following table provides the projects planned in the category of supporting transmission
system operation. This list was selected through an identification of transmission system in
complying to technical requirements as per Grid Code and those recommended by
ENTSO/E.
Tab. 5-6. List of projects in the category of support to system operation 2013-2022
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 49 of 138
Office: Long-term Planning and Development
PROJECTS IN CATEGORY: SUPPORT SYSTEM - (2013-2022)
Nr
ID Title of Project Technical Description Rationale Viti
1
TD
_M
AT
JE Installation of metering
groups in the new boundary between KOSTT and KEK/DSO
a)Metering transformer of power in 35 kV and 10(20) kV levels in line with the metering code and associated works
Accurate metering in line with the metering code after the change of the technical boundary, namely the commercial border from 110 kV to 35 kV and 10(20) kV
Q3-2
014
2
T/
TE
LE
K_
OP
GW
OPGW installation at interconnection lines 400 kV - Installation of telecommunication routes by optical fiber, in 400 and 220 kV interconnection lines up to the borders.
(a) Existing protective conductor 65mm2 at 400 kV to the borders with neighboring countries will be replaced with another conductor of same dimension, containing 96 optical fibers.
Fulfilling technical requirements of the ENTSO/E Manual Q
3-2
015
T/
SC
AD
A_
Int
Implementation of changes and their incorporation in SCADA/EMS2
a) Inclusion of all changes in existing substations, and b) incorporation of new substations in SCADA/EMS in the Dispatch Center and Emergency Dispatch Center
Optimal use of the SCADA/EMS system
Q4-2
015
3
T/
MA
T_
NJE
HS
OR
E
INTER-OST Meters - Installation of metering points at cross border lines, in compliance with the Metering Code
(a) Installation of two-core metering transformers for commercial metering, same characteristics in 400, 220 and 110 kV interconnection lines (b) Replacement of existing meters with meters compliant to the Metering Code
The project allows for completion of installation of border meters, in accordance with the Metering Code. Q
4-
2015
4
T/
GIS
-SY
ST
EM
GIS System supporting the Transmission System
(a) Full set of remote controlled equipment: laser locator, thermal camera, digital area photo camera, GPS equipped, internal navigation system (b) Respective software for data integration and processing from equipment, and CAD and GIS data presentation
Improvement of maintenance of lines and substations. Data processing on pillars, line routes, identification of properties affected by lines, etc.
Q2-2
018
5.4. Technical description of projects planned in transmission
5.4.1. Introduction
The first stage of transmission network consolidation was completed with the completion of
the projects: SS Peja 3, L112 line, AT 150 MVA at SS Kosovo A. The second stage of
transmission network reinforcement, which enabled the enhancement of network reliability
security, in terms of N-1 criterion, was completed after the implementation of the SS Ferizaj
2Project with start in 2013 and is in process conform changes in network topology.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 50 of 138
Office: Long-term Planning and Development
Project and the connection of SS Gjilani 5. The transmission network planning process,
based on high voltage line planning criteria, is a dynamic one, and as such, it aims for
fulfillment of technical criteria which in the long term secure a safe prospect of load and
generation development.
The following is a description of development projects from the list of projects planned for
the period 2013-2022. A series of projects planned to complete by the end of 2022 will bring
the transmission network to a condition which guarantees security and high reliability in
operation, in full accordance with the Grid Code. This period includes projects which
influence directly the reinforcement of the transmission network, substation revitalization
projects and load support projects, for which the parties have applied to KOSTT for
connection to the transmission network.
5.4.2. Transmission grid strengthening projects
The following are detailed descriptions of planned projects pertaining the category of
strengthening or capacity increase of transmission grid, for the planning period 2013-2022.
Project: Second 40 MVA Transformer, 110/10(20) kV at SS Skenderaj
Within the Peja 3 Project Package, the first 110 kV substation was built in Skenderaj, but in
the absence of funding, the substation was only fitted with a single and used transformer
(1988) at power 31. 5 MVA. After the operationalization of substation, the performance of
transformer had serious difficulties with the transformer core, thereby resulting in frequent
failures of the substation, and full loss of supply for the consumers in the Skenderaj region.
The previous transformer capacities 35/10 kV were dismantled by KEK-DSO for use in
other parts of the Kosovo grid. The lack of alternative supply and technical problems in the
existing transformer have emphasized the urgent need to install a second 40MVA
transformer at SS Skenderaj. Also, operating with a single transformer is a major difficulty in
realizing maintenance works, when there are no other alternatives to supply consumption.
The project is given high priority, since the benefits of the project are:
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 51 of 138
Office: Long-term Planning and Development
- Reduction of undelivered power to consumers,
- Increased safety and reliability of supply to Skenderaj and surroundings
- Increased transformation capacities
The project is planned for completion in the second quarter of 2014.
Project: AT2-300 MVA in SS PEJA3 and SS FERIZAJ 2
- Second AT 300MVA at SS PEJA 3,400/110 kV
The consistent increase of the load in the Dukagjini Plain region directly influences the
increased load in the single AT 300MVA at SS Peja 3. Computer analysis have shown that
during winter peak 2012-2013, around 3% (260 hours) of the year, the substation Peja 3
operates at risk as per security criterion N-1. The percentage of hours at risk will continue to
grow for 5% for the winter peak 2013-2014, and 7% for the winter peak in 2014-2015.
Figure 5-3 shows the power flows in PSS/E according to the forecasted load for the year
when the second transformer enters into operation. Based on planning criteria, the need for
a second transformer at SS Peja is rather pressing, but due to financial limitations, this
project was proposed for support from the IPA 2011 program. European Union procedures
for funding and implementing projects to be supported by the IPA program determine the
time of project commissioning, and this time is expected to be the fourth quarter of 2015.
Expected benefits from the project are:
- Enhancement of transformation capacities and fulfillment of the N-1 criterion of the
important 400/110 kV node
- Increasing the reliability and security of supply for 20% of the national consumption
- Reduction of the undelivered energy to the consumers.
- Optimization of the transformer maintenance process and their relevant fields.
- Creation of the conditions for 400 kV and 110 kV network reconfiguration (400 kV ring
and regrouping of 110 kV loads)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 52 of 138
Office: Long-term Planning and Development
Figure 5-3 . Power flows in two automatic transformers of SS Peja 3 after commissioning in the Q4
of 2015
- Second AT 300MVA at SS FERIZAJ 2, 400/110 kV
A consistent increase of load in southeast Kosovo (Ferizaj, Viti, Sharr, Gjilan, Theranda)
influences directly in the increased load on the single AT 300MVA at SS Ferizaj 2. The
second AT will influence the increased load flows from 400 kV to the 110 kV level at SS
Ferizaj 2, thereby relieving sensibly the load on AT-s SS Kosova A and SS Prishtina 4. With
the installation of the second auto-transformer, the substation Ferizaj 2, will comply to the
N-1 criterion for a long term, thereby increasing transformation capacities of the
transmission system for 300MVA. A project similar to the SS Peja 3 auto-transformer
project will be funded by the IPA 2011 program, the commissioning of which is expected in
the fourth quarter of 2015. The project envisages the financing of the installation of
AT2/300MVA/400/110 kV, from a transformer field 400 kV and 110 kV.
Figure 5-4 shows the power flows in PSS/E according to the forecasted load, for the year
when the second automatic transformer enters into operation.
Expected benefits from the project are:
Two lines 110 kV Up to SS PEJA 1
lines 110 kV Up to NS Burimi Line 110 kV
Up to Klina
Line 110 kV Up to SS Skenderaj
SS PEJA 3 400 / 110 kV
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 53 of 138
Office: Long-term Planning and Development
- Enhancement of transformation capacities and fulfillment of the N-1 criterion of the
important 400/110 kV node
- Increasing the reliability and security of supply for 22% of the national consumption
- Reduction of the undelivered energy to the consumers.
- Optimization of the transformer maintenance process and their relevant fields.
- Creation of the conditions for 400 kV and 110 kV network reconfiguration (400 kV ring
and regrouping of 110 kV loads)
Figure 5-4. Power flows in two automatic transformers of SS Ferizaj 2 after commissioning in Q4-
2015
New 110 kV line SS Peja 3- SS Peja 1, and revitalization of SS Peja 1
Following completion of the L1806 line allocation project from SS Gjakova 2 to SS Gjakova
1, the Dukagjini Plain area will comply fully to the criterion N-1. Based on a long term load
forecast, and based on computer simulations, the security criterion N-1 will not be complied
with until after 2015. A critical outage would be the outage of 110 kV line SS Peja 3-SS Peja
1, in which case there would be an overload in the line SS Gjakova 1- SS Deçan and SS Peja
3 - SS Klina. For this reason, to eliminate this problem, it is necessary to build a second 110
kV supply line, 240mm2, at a length of 28km, from SS Peja 3 to SS Peja 1. The project
should be coordinated with the SS Peja 1 revitalization project, which provides for a full
rehabilitation of 110 kV equipment, and transition to the double bus bar system in the
compact GIS system including 35 kV transformer fields. This project is proposed for
DY LINJAT 110kV
deri NSFerizaj 1
Linja 110kV
deri NS Gjilani 5 Linja 110kV
deri NSLipjani
Linja 110kV
deri NS Sharri
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 54 of 138
Office: Long-term Planning and Development
funding from the IPA 2012 program, while the commissioning of the project is expected in
the fourth quarter of 2016. Due to an over-urbanized area close to the Peja 1 substation, the
five pylons close to the substation must be constructed instead of existing pillars, and they
must be dual. If there are problems in property expropriation, an optional solution will be to
dismantle the existing line, and construction of a new doubled line, thereby avoiding a new
route. The figure 5-5 shows a geographical position of the project.
Expected benefits from the project are:
- Transmission network capacity enhancement and fulfillment of the N-1 criterion for a
long-term period for the network sections of the region of Dukagjini
- Reduction of active and reactive power losses in the transmission network.
- Reduction of undelivered energy to consumers
- Enhancing operational security and reliability of SS Peja 1 (substation built in 1961)
- Support for the integration of small hydropower plants in the energy system
Figure 5-5. Second line SS Peja 3- SS Peja 1
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 55 of 138
Office: Long-term Planning and Development
Project: Second 40 MVA transformer, 110/10(20) kV at SS Klina
The substation 110/10 kV in Klina has had a single transformer in operation since its
construction in 1988. Operating with a single transformer poses a great risk in case of
unplanned failure of transformer, thereby leaving Klina without supply until repair. On the
other hand, consumption supply must have a transforming reserve, which responds to
continuous increase of load. For the reasons mentioned above, there is a need to install a
second transformer at SS Klina. Selection of substations with a single transformer for
installation of the second transformer took into account the age of transformer and technical
condition as recorded by maintenance teams.
The expected benefits of the project are:
- Reduction of undelivered power to consumers,
- Increased safety and reliability of supply to Klina and surroundings
- Increased transformation capacities
- Optimization of maintenance processes
The project is planned for completion in the second quarter of 2018.
Project: Second 40 MVA transformer, 110/10(20) kV at SS Burimi
Substation 110/10 kV in Burimi has only one transformer in operation since its construction
in 1989. Operating with a single transformer poses a great risk in case of unplanned failure
of transformer, thereby leaving Burimi without supply until repair. Also, there are serious
problems in performing maintenance of transformer and its plates, since this process also
requires full interruption of consumption supply. On the other hand, consumption supply
must have a transforming reserve, which responds to continuous increase of load. For the
reasons mentioned above, there is a need to install a second transformer at SS Burimi.
Selection of substations with a single transformer for installation of the second transformer
took into account the age of transformer and technical condition as recorded by
maintenance teams.
The expected benefits of the project are:
- Reduction of undelivered power to consumers,
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 56 of 138
Office: Long-term Planning and Development
- Increased safety and reliability of supply to Burimi and surroundings
- Increased transformation capacities
- Optimization of maintenance processes
The project is planned for completion in the second quarter of 2020.
Project: New line 110 kV SS Prizren 1- SS Prizren 2
The consistent growth of load in the Prizren region shall put at risk the N-1 criterion for that
area of the transmission network. This risk will be present after 2017, when the peak load in
Kosovo is foreseen to be 1340MW. The second 110 kV line from SS Prizren 1 to SS Prizren
2 is necessary since with the current network configuration, an outage of the line SS Prizren
2- SS Prizren 3 would cause an overload on the L164/3 line. The project plans for the
construction of a new 110 kV line, 240mm2 (114MVA/605A) 3. 5 km long, as shown in the
figure 5-6. In this case, there are two other options of implementation, depending on
difficulty of expropriation and urban obstacles:
- Transformation of the existing L164/3 line to a double line
- Underground 110 kV cable
The project is due to be completed by 2018. This project is important for the realization of
110 kV consumption grouping concept as per main substations. The same project is also
considered by the Fichner study on redesign of the configuration of the transmission
network 400 kV and 110 kV.
Expected benefits from the project are:
- Fulfillment of the N-1 criterion
- Reduction of undelivered energy to consumers
- Enhancement of transmission network capacities
- Optimization of power flows and enabling the grouping of 110 kV loads
according to independent supply from main transmission system nodes (in this
case from SS Prizren 2)
The Project is planned to be completed in the fourth quarter of 2021
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 57 of 138
Office: Long-term Planning and Development
Figure 5-6. Second 110 kV line SS Prizren 1- SS Prizren 2
Project: Second 40 MVA transformer, 110/10(20) kV at SS Berivojce
Substation 110/10 kV in Berivojce has only one transformer in operation since its
construction in 2002. Operating with a single transformer poses a great risk in case of
unplanned failure of transformer, thereby leaving Kamenica without supply until repair.
Also, there are serious problems in performing maintenance of transformer and its plates,
since this process also requires full interruption of consumption supply. On the other hand,
consumption supply must have a transforming reserve, which responds to continuous
increase of load. For the reasons mentioned above, there is a need to install a second
transformer at SS Berivojce. This substation is the last one in the list of four substations
currently operation with a single transformer.
The expected benefits of the project are:
- Reduction of undelivered power to consumers,
- Increased safety and reliability of supply to Kamenica and surroundings
- Increased transformation capacities
- Optimization of maintenance processes
The project is planned to be completed in the second quarter of 2021.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 58 of 138
Office: Long-term Planning and Development
Project: New 110 kV line SS Peja 3- HPP Ujmani
A consistent growth of consumption in the Mitrovica region, and a single 110 kV line
connecting HPP Ujman with the transmission network, are factors necessitating
construction of a new 110 kV line to connect the plant with the strong network node SS
Peja 3. The figure 5-7 shows the geographical location of the 25 km long line. This project
allows for development of a new 110 kV ring road, which is important for the optimization
of the transmission network for the Mitrovica region. The expected consumption growth in
the region, especially due to the Trepca mine, will be more secure in terms of electricity
supply, in due consideration of increased transmission capacities. The new line will enable a
relief of supply lines for the 110 kV ring SS Kosova A – SS Bardhi – SS Vushtrria 1&2 – SS
Trepça.
Expected benefits from the project are:
- Fulfillment of the N-1 criterion for HC Ujmani
- Optimization of power flows in 110 kV lines, particularly discharging of supply lines of
SS Vallaqi
- Creation of necessary disconnection reserves during the maintenance process or during
unplanned breakdowns of the transmission system
- Valorization of transmigration capacities of Peja 3
The project is planned to be completed in 2022.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 59 of 138
Office: Long-term Planning and Development
Figure 5-7. Line SS Peja 3- HC Ujmani
Project Pack RING 400 kV GJAKOVA-PRIZREN-FERIZAJ
The current 400 kV network configuration is characterized as a star network, where the
centre of the star is the SS Kosova B. The optimal configuration of high voltage electricity
networks is the ring configuration, which ensures a higher operational flexibility and security
in the power system.
The expected development in terms of new generation capacities and load forecast, the
forecast of increasing flux of loads in regional exchanges, determine the need for
reconfiguration of the 400 kV network. Earlier studies, such as ESTAP I, have
recommended the reconfiguration of the 400 kV network in a ring form, thereby avoiding
220 kV network development.
Computer simulations undertaken in complex models, which incorporate regional systems,
in consideration of new generation capacity development scenarios in the country and the
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 60 of 138
Office: Long-term Planning and Development
region, and the forecasted load development also in the country and the region, reflect the
need for creation of the 400 kV ring in the territory of Kosovo.
This configuration is presented as an optional long-term project also in the earlier
developments of KOSTT. A detailed study on redesigning of the 400 kV network, and its
impact on the Kosovo power system, was undertaken by a German consultancy “Fichner”.
The study’s concept recommends the establishment of powerful 400/110 kV nodes, which
are to supply load groups, and by establishing capacity reserves in 110 kV lines, with a view
of optimization of load flows. Computer simulations in complex models undertaken by
KOSTT have shown that the network area of the Prizren region will not be compliant to the
N-1 criterion after 2020, due to high impedance of two 220 kV supply lines of SS Prizren 2.
A larger problem would occur if the 220 kV interconnection line Fierzë-Prizren 2 would fail.
In this case, voltage collapse may occur, coupled with the disconnection of the load at SS
Prizren 2. If one would view the transmission network before the construction of the 400
kV ring, one would be able to spot the existence of four powerful and sufficient nodes of
transformation to 110 kV: SS Peja 3 supplying Dukagjini consumption, SS Ferizaj 2
supplying southeastern part and SS Kosovo A, together with SS Prishtina 4, which mainly
supply Prishtina consumption. All these nodes are connected to a powerful horizontal
network, while SS Prizren 2 remains connected also to a horizontal 220 kV network, which
is relatively poor.
All these nodes are connected to the powerful horizontal network, while SS Prizren remains
connected in the network also in the horizontal, but relatively weak 220 kV.
The 400 kV network reconfiguration from the star shape to the ring shape configuration
brings about the following benefits:
- Enables the support for new generation capacities
- Increases the 400 kV network’s reliability and security.
- Facilitates the security of power exchange between Kosovo and countries in the region,
or transits going through our network.
- Enables the reconfiguration of the 110 kV network with the aim of optimizing
operational conditions of the transmission system
- Enhances the quality of consumption supply in the region of Prizren.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 61 of 138
Office: Long-term Planning and Development
- Facilitates the 400 kV line maintenance process.
The ring project is expected to be completed in two phases:
First stage: Includes construction of the 400 kV distribution station Gjakova 3, which will
be positioned very closely to the 400 kV interconnection line SS Kosova B – SS Tirana 2,
where it should be connected at a length of 51 km from SS Kosovo B, as shown in the
figure 5-8. SS Gjakova 3 is expected to perform the function of the new interconnection
point in a 400 kV ring. It should include three 400 kV line fields, with a possibility of
expansion, and one 400 kV connection field. Simultaneously, the SS Prizreni 4 400/110 kV
will be developed, which initially will have an installed 300MVA auto-transformer. The
substation will be positioned in a sequence to SS Prizreni 2, to use the existing 100 kV bus
bars, with a difference in placing a 110 kV sectional bus bar divider. The substation provides
also for the development of double 400 kV bus bars, to contain two 400 kV line fields, and
sufficient space for reserve line and transformer fields. The figure 5-9 shows the
configuration of SS Prizren 4. Both substations would operate in parallel at the 110 kV level,
which means the use of existing 3x150MVA auto-transformers at SS Prizren 2. Existing
220/110 kV auto-transformers will be used to the end of their life cycle, to be replaced with
additional AT-s 400/110 kV to be installed at SS Prizreni 4. The distribution substation
Gjakova 3, 400 kV will be connected by a 400 kV line, 2x490mm2(1316MVA/1900A), at a
length of 31.5km with SS Prizren 4, 400/110 kV. The first stage is planned to be completed
in 2022.
Second stage: Includes the stage of ring completion, with the development of a 400 kV
line, 56. 5 km line from SS Prizren 4 to SS Ferizaj 2, as presented by figure 5-8. The
construction of this line may be completed in the period between 2022-2025, and must be in
timely coordination with generation capacity development projects.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 62 of 138
Office: Long-term Planning and Development
Fig. 5-8 Geographical positioning of the 400 kV ring SS Gjakova 3-SS Prizren 4- SS Ferizaj 2
TC
PR4
A
B
DR
NS Ferizaj 2
NS Peja 3
SSH Gjakova 3
NS Prizreni 4
Prz. 2
NISH
Krushevc
RIBAREVINË
TIRANA 2
Fierzë
SHKUPI 5
31.5km
56.5km
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 63 of 138
Office: Long-term Planning and Development
Figure 5-9. Single pole scheme of modified substation SS Prizren 2, 220/110 kV to SS Prizreni 4,
400/110 kV
5.4.3. 110 kV line revitalization projects
The important factors that are taken into account for determining the list of lines which will
have the conductors replaced with larger transmission capacity are:
- The age of the lines,
- Line overload frequency (N-1)
- The level of power losses in the line
The first factor is clearly defined; while the second and third factors are identified by
computer analysis, thereby simulating load flows for different transmission system operation
conditions, in due consideration of perspective development of projects, which would
considerably impact the change of load flows in the transmission network. All 110 kV lines
with 150mm2 section, in the transmission network, have been analyzed in terms of load
losses, thereby pursuing reinforcement at the long term.
300 MVA
SY GJAKOVA 3 SS FERIZAJ 2
Reserve .
Reserve
3 x 150 MVA
400 kV 220 kV
110 kV 110 kV
coupling bay
coupling bay
coupling bay
Lines 110 kV Lines 110 kV Lines 110 kV
disconnetor
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 64 of 138
Office: Long-term Planning and Development
Lines that are 40 years old and lines with larger overload frequency and, understandably,
higher losses, are listed in the first place.
The main objective of this category of projects is to increase the capacity of 110 kV lines
with section conductors of 150mm2 (83 MVA), in conductor 240mm2 (114 MVA). Some
very old lines mainly have concrete towers and replacement of the existing conductors with
conductor on greater weight in mechanical and statically terms require reinforcement of
towers, with special emphasis on angular towers. Also portal towers require reinforcement
and eventual addition of the towers in order to increase the mechanical stability of the whole
line. The following 110 kV lines are selected for reinforcement for period 2013-2022:
Revitalization of the 110 kV line: SS Peja 2-SS Deçan, L126/2
Line of 14. 57 km connecting SS Peja 2 with SS Deçan, presented in figure 5-10, is a line
built in 1967, which contains 52 towers of portal type and conductor of 150mm2. Line
L126/2, is an important line, segment of the substations ring of 110 kV Peja 3 – Peja 1, -
Peja 2 - Deçan-Gjakova 1.
The project for the revitalizing of this line includes strengthening of the angular towers of
the portal form, installing new insulators and changing phase conductors. Protective
conductor will be replaced with the project SCADA/EMS. The project will assist in the
increase of the transmitting capacities and will assist in improvement of the N-1 security
criteria.
Expected benefits from the project are:
- Enhancing the transmission capacity of the line from 83 MVA to 114 MVA
- Reduction of active and reactive power losses
- Fulfillment of the N-1 criterion for the section of the network connecting 110 kV
substations of the Dukagjini region
The project is planned to be finalized in the fourth quarter of 2015.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 65 of 138
Office: Long-term Planning and Development
Fig. 5-10 Line 110 kV SS Peja 2 – SS Deçan with a length of 14. 57km
Project: Revitalization of the 110 kV line SS Kosova A- SS Bardhi – SS Vallaqi
From all results obtained from computer simulations, the current line L163 from Kosovo A
to SS Vallaq at the capacity of 83MVA (150mm2) seems to be more problematic in
comparison to other lines (150mm2) which are in the list for replacing conductors. After the
completion of the project of reinforcement of SS Bardh supply, whereby connection of SS
Kosovo A – SS Vallaq was completed, a part of the line remained with the section 150mm2,
therefore the project as a whole includes the revitalization of this section. Improvement of
capacity of this line should relief its overload, in the case of disconnection of supply line SS
Kosova A – SS Vushtrri 2. The same line with connect SS Mitrovica 2 as well, allowing for
an improvement of security and reliability of supply for the load in the Mitrovica region. The
figure 5-11 presents the part of the line planned for revitalization. The Project includes
replacement of conductors 150mm2 (83MVA/440A) with 240mm2(114MVA/605A)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 66 of 138
Office: Long-term Planning and Development
conductors, and necessary reinforcement in portal pillars, due to the added load on the
conductor.
Expected benefits from the project are:
- Enhancement of line transmission capacity from 83 MVA to 114 MVA
- Reduction of active and reactive power losses
- Fulfillment of the N-1 criterion for the section of the network connecting the ring:
Kosova A-Bardhi-Vushtrria 1&2-Trepça-Mitrovica 2-Vallaq
The project is planned to complete by the fourth quarter of 2019.
Fig. 5-11 Line 110 kV SS Kosova A – SS Bardhi – SS Vallaq with a length of 38. 5km
Project: Revitalization of 110 kV line, SS Prizren 1 – SSPrizren 3
The project provides for replacement of conductors, from 150/25mm2 to 240/40mm2 at a
length of 4. 69km, from SS Prizren 1 to SS Prizreni 3, as presented by figure 5-12. The
project also provides on static reinforcement of existing pillars, placement of new composite
insulators, and replacement of phase conductors.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 67 of 138
Office: Long-term Planning and Development
The line is an interconnecting segment for the supply of SS Prizren 3. Revitalization of this
line shall substantially impact the increase of security and operating reliability of that part of
the 110 kV network.
Expected benefits from the project are:
- Fulfillment of the N-1 criterion for the section of the 110 kV network connecting 110
kV substations in the region of Prizren
- Enhancement of line transmission capacity from 83 MVA to 114 MVA
- Reduction of active and reactive power losses
The project is planned to be completed by third quarter of 2020.
Fig. 5-12 110 kV line SS Prizren 1 – SS Prizren 3 with a length of 4. 69 km
Project: Revitalization of the 155/2 line, in coordination with development of the SS
Leposaviq 110/10 kV
The new SS Leposaviq 110/10(20) kV is planned to he supplied by the existing cross border
line SS Vallaq - SS N. Pazar, which shall be realized by a section close to the SS Leposaviq
35/10 kV . The line currently does not have sufficient capacity due to its sectional width
(150mm2). On the other hand, this line is one of the oldest lines of the transmission system
of Kosovo, therefore its reinforcement is necessary. Replacement of the conductor is
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 68 of 138
Office: Long-term Planning and Development
planned for 15km of the line, starting from SS Vallaqi to the point where the section is
planned to occur in the line L155/2. The figure 5-13 shows the geographical position of the
project.
Expected benefits from the project are:
- Enhancement of the line transmission capacity from 83 MVA to 114 MVA
- Reduction of active and reactive power losses
- Enabling the realization of SS Leposaviq 110/10(20) kV
The project is due to complete by the fourth quarter of 2020
Fig. 5-13 Revitalization project for the line L155/2 in coordination with construction of SS Leposaviq 110/10(20) kV .
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 69 of 138
Office: Long-term Planning and Development
5.4.4. Load support projects
The following are technical descriptions of projects supporting the load and expected
benefits from them
Project No. 5: SS Mitrovica 2, 110/10(20) kV
The continuous increase in electricity demand in the area of Mitrovica raise the need
for creating a new distribution facility in the area. The southern part of Mitrovica is currently
being supplied by the substation in the Industrial Complex of Trepça. The current capacities
of the distribution grid are limited, and during peak loads, 35 and 10 kV lines and cables are
overloaded. On the other hand, the mining and metallurgic industrial development requires
special, safe and independent supply. These are the factors necessitating the construction of
an SS Mitrovica 2, 110/10(20) kV, transforming capacity 2x40MVA, close to the existing
distribution substation 35/10 kV.
The optimal position of the new substation is in the proximity of the existing 35/10 kV
substation next to the sports stadium “Trepça”, in lieu to which the Municipality of
Mitrovica has already allocated the plot for the substations and line routes.
Based on the principle of security of operation of Transmission System, Mitrovica 2
should be built close to the existing lines L125/3 Trepça-Vallaq and L163/2 Palaj-
Vallaq. Apart from the short double line 300m, the connection will be made with the
110 kV line Palaj-Vallaq, while a second connection will be made by double line
400m with the 110 kV line Trepça – Vallaq. Figure 1-1 shows the connection to the
substation Transmission Grid. By this topology, this substation shall provide good
security in terms of N-1 security criteria, and as such, it will be an important 110 kV
node for the energy system of Kosovo. The expected benefits of the project are:
- Reliable and qualitative supply of consumption in Mitrovica
- Reduction of large amounts of undelivered power, as a result of elimination of
bottlenecks in the distribution grid
- Reduction of technical losses in the distribution network
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 70 of 138
Office: Long-term Planning and Development
- Support to economic development of Mitrovica
The project is planned for completion in the fourth quarter of 2017.
Fig. 5-14 Connection of SS Mitrovica 2 in the Transmission Network
Project: SS Dragash and 110 kV line SS Kukës-SS Dragash- SS Prizren 2
The project includes the development of SS Dragash 110/10(20) kV to be supplied with two
lines: SS Dragashi – SS Prizreni 2 (21km) and SS Dragashi - SS Kukës (39km). From Zhur to
Dragash, the line shall be double, while from Prizren 2 to Zhur, the line will be single, but
with doubled pillars, so that the other pillar line is used for the HPP Zhur project. The
Figure 5-15 presents the geographical location of the project, with relevant data. The project
coordinated between KOSTT and KEK-DSO is considered to be of importance for both
parties. For KEK_DSO the project allows for a better supply for the southern area of
Kosovo (Dragash and surroundings), reduction of technical losses at distribution, and relief
of 110/35 kV transformers at SS Prizreni 1.
In terms of benefits created by the transmission system project, we can underline a
few:
- Optimization of load flows between two systems KOSTT (Kosovo) and OST (Albania),
and minimization of electricity generation costs for both system generators.
SS MITROVICA 2 110 / 10 ( 20 ) kV
SS Trepça
SS PALAJ
SS Vushtrria 1
SS VALLAQ
HPP Ujmani SS N . Pazar
6 km
28 . 9 km
8 . 89 km
9 . 1 km
10 ( 20 kV )
40 MVA 40 MVA
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 71 of 138
Office: Long-term Planning and Development
- Relief of load from 110 kV lines SS Prizren 1-SS Prizren 2 and SS Prizren 1-SS Prizren 3,
equivalent to the Dragash load.
- Exchange of electricity surpluses between systems, which can be facilitated by radial
operation.
- Secure supply for SS Dragash and SS Kukës, thereby fulfilling the N-1 criterion (outage of
a line does not interrupt supply for SS Dragash or SS Kukës, due to doubled supply)
The project is expected to be operational by the fourth quarter of 2017.
Figure 5-15. Project of SS Dragash and line 110 kV with SS Kukës.
HPP Dikance
SS Zhuri 35 kV
SS PRIZRENI 2 220 / 110 kV
SS PRIZRENI 1 110 / 35 kV
8 . 4 km
SS Kuksi
SS Dragashi 35 kV
Line 35 kV
SS DRAGASHI 110 / 10 ( 20 ) kV
Double circuit line 110 kV Dragash - Zhur , 13 km
Zhuri
One circuit line ** 110 kV Prizren 2 - Zhur , 8 km
** Double towers for HPP Zhuri
One circuit line
110 kV Zhur - Kukes 26 km Zhur - -border 17 km
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 72 of 138
Office: Long-term Planning and Development
Project: Project Package Malisheva 110/10(20) kV
Following the transfer of 110 kV assets from KEK-DSO to the KOSTT, the process of
planning 110/10(20) kV substations for load support was taken by KOSTT, in due
harmonization with plans and priorities, and in connection to load support. The project
package Malisheva was included with the list of capital projects for load support and
strengthening transmission capacities of the network for the following reasons:
a) The condition of supply for the Malisheva is unsatisfactory, since this region is currently
supplied by a 35 kV line from SS Rahoveci. The length of this line causes large losses of
active and reactive power, thereby adversely influencing the quality of electricity
delivered to consumers. The 35 kV voltage level and other distribution levels during the
winter load are below minimum allowed values according to the distribution code. To
be able to provide for sustainable and long-term supply of electricity for the Malisheva
region, it is necessary to construct a 110/10(20) kV substation, with transformation
capacities of 2x31. 5 MVA.
b) The implementation at SS Malisheva shall be made in a way of creating a 110 kV ring,
which would connect SS Malisheva with SS Rahovec with a 17 km line, and SS
Malisheva with SS Theranda with a 19 km line. In this case, the radial supply of SS
Rahoveci will be eliminated, transformers at SS Rahovec are relieved, and a load group
Rahovec, Malishevë, Therandë will be created, supplied in turn by the strong node of SS
Prizren 2. This shall optimize the load flows, it will increase disconnection reserves,
while the line Therandë-Ferizaj 1 may operate remaining open or closed, depending on
the load flows and the system security assessment.
The two 110 kV lines shall be of 240 mm2 in dimension. This project is to be coordinated
with the equipment revitalization project at SS Theranda, which envisages the replacement
of 110 kV equipment, and migration to the double busbar system. At SS Rahovec, there is an
existing 110 kV line field, while at SS Theranda, a new line field must be constructed. Figure
1-2 shows the geographical coverage of the project package.
The expected benefits of the project are:
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 73 of 138
Office: Long-term Planning and Development
- Reliable and quality supply of consumption in Malisheva
- Development of a new flexible 110 kV ring Rahovec - Malisheva - Theranda
- Elimination of radial supply for SS Rahoveci (N-1 Criterion)
- Optimization of load flows and discharge of transformers at SS Rahovec
- Reduction of large amounts of undelivered power to the consumers, as a result of
elimination of bottlenecks in the distribution network
- Reduction of technical losses in the distribution grid
- Support to economic development of Malisheva
The project is planned for completion by the third quarter of 2018.
Figure 5-16 Geographic position of the project package SS Malisheva
SS RAHOVECI SS THERANDA
SS MALISHEVA 110 / 10 ( 20 ) kV 2 x 31 . 5 MVA
SS Malisheva 35 / 10 kV
Existing line 35 kV
Line 110 kV , 240 mm 2 , 15 km
Line 110 kV , 240 mm 2 , 17 km
Line 220 kV SY Drenas - SS Prizreni 2
In SS Ferizaj 1
In SS Priz . 1
In SS Prizreni 2
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 74 of 138
Office: Long-term Planning and Development
Project: SS Prishtina 6, 110/10(20) kV
In terms of security of supply for distribution consumers, the construction of the
new Prishtina 6 substation in the center of Prishtina is necessary, due to the fact that the
current capacities of distribution substations SS Prishtina 1, SS Prishtina 2 and SS Prishtina 3
will not be sufficient for a middle-term period. The consumption in Prishtina and its
surroundings is the highest in Kosovo, making around 25% of the national consumption.
The problems in distribution capacities increase during winter consumption, and specifically
exacerbating when the District Heating Company has difficulties, thereby increasing the
demand for electricity. The position proposed for the new substation is in or close to the
closed building of SS Prishtina III 35/10 kV, which is located close to the main offices of
KEK and KOSTT. The geographical position of the substation, in the urban area, clearly
determines the options of supplying the substation, therefore underground cable. Also, the
type of high voltage equipment should be modular/compact, or so-called “GIS” technology,
which requires smaller space for construction. The figure 1-3 shows the proposed site for
the substation.
Figure5-17. Geographical position of the two substations Prishtina 4 and Prishtina 6.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 75 of 138
Office: Long-term Planning and Development
Based on the satellite images, one may see that the pipelines must be laid in rather
urban areas, especially in the proximity of SS Prishtina 6. The connections mentioned above
are also presented with the earlier development plans for the Transmission grid. Figure 1-4
shows the projected configuration of connection of the SS Prishtina 6 to the Transmission
grid. According to information from the Department for Project Implementation, earlier
plans of the KOSTT had defined the cable line routes, and the urban consent had also been
given for the route, issued by the Municipality of Prishtina. The route was 5. 3 km long,
while due to the stalling of the project, numerous constructions have taken place on and
along the route, which necessitate the deviation of such a route. Joint KOSTT-DSO teams
have intensified their visits to the Municipality of Prishtina, with a view of defining clearly
the new route for 110 kV lines.
The expected benefits of the project are:
- Reliable and quality supply for the consumption of the centre of the Capital
- Relieved transformers at SS Prishtina 1, 2 and 3
- Reduction of technical losses in the distribution network
- Optimization of load flows in 110 kV lines, as a result of discharging transformers
at SS Prishtina 1, 2 and 3
- Reduction of large amounts of undelivered power to the consumer, as a result of
eliminating bottlenecks in the distribution network
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 76 of 138
Office: Long-term Planning and Development
Fig. 5-18 Configuration of connection of SS Prishtina 6, 2x40 MVA, 110/10(20) kV to the
transmission grid
Project: SS Fushë Kosova 110/10(20) kV
The list of priority projects of the KEK-DSO includes the construction of the substation
Fushë Kosova 110/10(20) kV, close to the existing substation 35/10 kV. This substation is
supplied by two 35 kV lines, 95 mm2 from SS Kosova A and SS Prishtina 1. Based on the
information from the KEK-DSO, 35/10 kV transformer capacities are close to the critical
limit, while on the other hand, the load in the region of Fushe-Kosove shows a tendency of
continuous growth. For this reason, there is a necessity of creating a new 110/10(20) kV
node in Fushë Kosovë, which should have sufficient long-term transforming capacities in
2x40MVA, which would be able to respond to the continuous load growth, in accordance
with technical criteria of transformation reserve. The construction of the substation should
allow for the relief of transformers at SS Prishtina 1 and SS Kosova A, and reduction of load
flows in supply lines of the SS Prishtina 1. In the technical aspect of connections, based on
the geographical position of the substation, the optimal position of connection with the
transmission grid would be the 110 kV L112 line SS Kosova A- SS Lipjan, which passes
close to the position proposed. The geographical position of the connection of SS Fushë
Kosova is presented in the figure 1-5. A double line of around 1 km in length, standard
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 77 of 138
Office: Long-term Planning and Development
dimensions of 240mm2, will be connected to the 110 kV Kosova A- Lipjan line point at a
distance of 4. 3 km from Kosova A. In this way, an optimal use of the line earlier converted
from 220 kV to 110 kV is achieved, by supplying two substations SS Lipjan and SS F.
Kosova.
The expected benefits of the project are:
- Reliable and quality supply of consumption in Fushe-Kosova
- Relieved transformers at SS Prishtina 1 and SS Kosova A
- Reduction of technical losses in the distribution network
- Optimal usage of converted L112 line (Kosova A-Lipjan – Ferizaj 2)
- Optimization of load flows at 110 kV lines, which supply substations of Prishtina, as a
result of relieving transformers at SS Prishtina 1 and Kosova A
- Reduction of large amounts of undelivered power to the consumer, as a result of
elimination of bottlenecks in the distribution network
The project is scheduled for completion by the fourth quarter of 2019
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 78 of 138
Office: Long-term Planning and Development
Figure 5-19. Configuration of connection of SS Fushë Kosova to the transmission network.
Existing 110 kV line SS Kosova A-SS Lipjan
SS F.Kosova
SS KOSOVA A
Connection point
4.3 km far from SS
Kosova A
Double 110 kV line 1 km, 240mm2
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 79 of 138
Office: Long-term Planning and Development
5.4.5. Substation Revitalization Projects
In determining the list of substations that required revitalization the following factors were
taken into consideration:
- Impact of the failure of the substations in the transmission system
- The age of the substation
- Frequency of the failures and damages in the equipments of the high voltage
- The level of the fault currents in the substations
Probability of failures in high voltage equipment begins to rise with age of equipment,
especially equipments that are greatly used. Also the substations which are characterized by
large currents failures considerably influenced in the accelerating the loss of their credibility.
Based on data archived in KOSTT related to the above mentioned factors a list was drafted
of substations requiring revitalization in the first five years of the development plan.
Project: Revitalization of equipment in TM at SS Gjakova 1, SS Gjilani 1 , SS Ferizaji
1 and SS Lipjani
Within the activities after the transfer of assets from the KEK-DSO to the KOSTT,
pursuant to the decision of the Government, the assessment of the technical condition of
equipment in terms of their impact on reliability and security of operation of the
Transmission System is essential and necessary, for development planning within the
Transmission Development Plan to be adequate and optimal. In the process of initiating and
completing activities for asset transfer, technical working groups and sub-groups have
collected important data, which were helpful in enabling a proper and real assessment of the
technical asset condition. In having a more detailed overview of technical equipment,
additional visits were arranged to the 110/x kV substations, specially focusing on substations
constructed before 2000. During the process, detailed monitoring was made on the
following components:
- Transformers 110/x (technical parameters, age, physical condition)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 80 of 138
Office: Long-term Planning and Development
- Transformer neuters and connection equipment
- Transformer plates 35 kV and 10 kV
- Own-consumption fields 35/04 kV or 10/04 kV
- AC/DC system
- Transformer overvoltage dischargers
Based on the current condition of the Kosovo Energy System, the process of asset transfer,
after the displacement of the technical limit from the high voltage to medium voltage levels,
incorporates the following:
- 1 SS 220/35/10 kV
- 6 SS 110/35 kV
- 7 SS 110/35/10 kV
- 14 SS 110/10(20) kV (together with two new SSs in the process, SS Gjilani 5 and SS
Prishtina 7)
As part of the 54 transferred transformers, there are 5 triple-reel transformers with
transformer fields of 35 kV and 10(20) kV.
Total transferred:
- 59 transformer fields (35 kV and 10 kV )
- 28 fields of own consumption
- 28 AC/DC systems
The equipment is divided into age groups, those built before 2000, and those after:
Built before 2000 (old system):
- 13 transformer fields 10 kV and
- 17 transformer fields 35 kV
after 2000 (new system):
- 23 transformer fields 10 kV and
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 81 of 138
Office: Long-term Planning and Development
- 6 transformer fields 35 kV
In total, closely 50% of transformer fields may be considered to be relatively new, and up to
new. The other half may be categorized in various ages, from 26 to 46 years in age.
Within a detailed analysis of the technical condition, and age of equipment transferred, a
certain number of projects is ranked according to priorities in the development plan. This list
of projects, which did not take place in the TDP 2012-2021, includes revitalization of
medium voltage equipment, managed by KOSTT, at substations:
SS Gjakova 1, SS Gjilani 1, SS Ferizaji 1 and SS Lipjani
The project shall be implemented in the next 5 years, according to the priorities listed in
Table 5-5.
This package envisages the replacement of transformer fields 35 kV, internal and external
construction, connection equipment of transformer neuters, and modernization of
transformer relays.
Expected benefits of the Project:
- increased security and reliability of substation operations
- reduction of undelivered power, as a result of interruptions caused by failures
- improved safety of personnel working at the substation, and maintenance personnel
The project shall be implemented in the period 2013-2017
Project: Revitalization of SS Theranda:
This project is of special importance, since it is related to the construction of SS Malisheva
where a new 110 kV line SS Rahoveci- SS Theranda will be connected in this substation. The
current bus bar (H system) configuration of the SS Theranda does not allow for an
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 82 of 138
Office: Long-term Planning and Development
optimization of system operation, while representing a difficulty in the process of
maintenance. Based on planning standards, substations that have three or more lines must be
configured in double bus bar systems and connection fields. This project envisages the
replacement of existing 110 kV high voltage equipment, development of a double bus bar
system (360mm2), installation of a 110 kV connection field, and the replacement of medium
voltage transformer fields. The existing relay protection system in line fields is planned to be
replaced with modern numeric relays. The project package SS Malisheva with the 110 kV
lines, and the substation revitalization project must be integrated in a joint project.
Benefits from the project are:
- Enhancement of the substation operation reliability and security
- Optimization of the substation operation after the transfer to dual busbar system
- Reduction of undelivered energy to consumers
- Increase of the safety of staff members working in the substation and maintenance
teams
Project: Replacement of the switchgear in SS Prishtina 4:
SS Prishtina 4, 220/110 kV , 3x150MVA, is a very important transformation node in
Kosovo’s transmission system. Substation Prishtina 4, due to its proximity with the existing
and planned generation capacities, with the high level of flows, may risk the dynamic system
stability. Historical data of incidents recorded as a result of failures in switchgear show their
importance. This project is selected to apply for funding by the IPA 2012 program, and as
such, it is planned for implementation by the fourth quarter of 2015.
Benefits from the project are:
- Enhancement of the substation and transmission system operation reliability and security
in general
- Reduction of undelivered energy to consumers as a result of reduction of frequency of
breakdowns in switchgear, after their replacement.
- Adequate dimensioning of switchgear in line with the code of electrical equipment
- Increase of the safety of staff members working in the substation and maintenance
teams
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 83 of 138
Office: Long-term Planning and Development
Project: Revitalization of SS Vallaqi Substation:
SS Vallaqi was one of the first substations to be built in Kosovo. Revitalization of this
substation is necessary, due to the fact that 5 110 kV lines are connected to its 110 kV bus
bars, one of which conveys the load generated by the HPP Ujmani. The technical condition
of the substation is not satisfactory, and as such, it hampers the security and reliability of
consumer supply. Revitalization of the substation includes replacement of 110 kV high
voltage equipment, replacement of busbars and portal systems with double busbars and
connection lines. The project is due to finish by the fourth quarter of 2019.
Expected benefits from the project are:
- Enhancement of the substation operation reliability and security
- Optimization of the substation operation after the transfer to dual busbar system
- Reduction of undelivered energy to consumers
- Increase of the safety of staff members working in the substation and maintenance
teams
Project: Revitalization of Substation SS Vitia:
Exploitation of high voltage equipment for the substations in question, built in 1984, until
the planned time period for revitalization is economically feasible. If one refers to the age of
substations, frequency of outages and the technical state of equipment, their operation is
considered feasible for another 5-9 years.
Substation of Vitia represents a node which belongs to an important ring 110 kV : Sharr-
Viti –Gjilan 5 –Gjilan 1. Modernization of high voltage equipment, medium voltage
equipment which belong to KOSTT, and protection equipment, will have an effect in
increasing the operational security and reliability of this section of the transmission network.
Revitalization of 110 kV high voltage equipment at SS Vitia, 110/35 kV is planned to be
completed by 2021.
Expected benefits are:
- Enhancement of the substation operation reliability and security
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 84 of 138
Office: Long-term Planning and Development
- Reduction of undelivered energy to consumers
- Increase of the safety of staff members working in the substation and maintenance
teams
5.4.6. Projects to enhance monitoring, control and measurement
systems in the Transmission System
The following are TDP projects considered necessary to fulfill the requirements of the Grid
Code and ENTSO/E manual.
Project: Installation of metering groups in the new boundary between KOSTT and KEK/OSSH
The project of installing metering groups in the new commercial boundary with KEK-DSO,
after the displacement of such boundary, is considered to be a project of high priority. The
project envisages for the installation of current and voltage metering transformers in all
transformer fields in 35 kV and 10(20) kV levels, in transformers transferred from KEK-
DSO to the KOSTT. Metering transformers must have technical features in compliance with
metering code. Meters from the earlier metering points will be used, only replacing entry
sizes, which were earlier taken from the 110 kV metering transformers, while now from the
35 kV and 10(20) kV transformers. The project is scheduled to be completed by the third
quarter of 2013.
The expected benefits from the project are:
- Electricity metering transferred from KOSTT to the KEK-DSO pursuant to the
metering code
- Accurate metering of losses in the transmission network, including the 110/x kV
transformers
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 85 of 138
Office: Long-term Planning and Development
Project: OPGW in the interconnection lines
Currently there are no telecommunications routes OPGW at the boundary lines.
Requirements of Policy 6 of the Manual of ENTSO/E (UCTE) require that an OST must
have at least two lines of communication with neighboring systems. Therefore, the project of
establishment of OPGW in the interconnection lines up to the border point is considered
important for KOSTT and regional system as a whole. In order for the project to be
operational there should be an Agreement between TSO’s so the OPGW will be installed in
the entire length of the line on both sides of the border.
The main objective of this project is installation of protective conductor with OPGW (up to
the border with neighboring TSO) and telecommunications equipment in the existing
interconnection lines of 400 kV:
- L 407, SS Kosova B – SS Nish, with a length of 41 km
- L 437/2 SS Peja 3 – SS Ribarevina , with a length of 28. 8. km
- L 420 SS Ferizaj 2 – SS Shkupi 5, with a length of30. 6km
Total length of the OPGW installment is 100. 4km
The project was presented in IPA 2011 and is planned to be implemented in the third
quarter of 2015.
Expected benefits from the project are:
- Fulfilling the technical criteria from the ENTSO/E manual
- Exchange of data with neighboring systems
- Increasing operational safety of regional transmission systems
Project: Implementation of changes and their incorporation in the SCADA/EMS
Continuous development and change in the transmission network, namely construction of
new substations, require integration with the existing SCADA/EMS system. This is
necessary after any changes in configuration, with a view of achieving optimal usage of the
SCADA/EMS system. This project is also connected to the projects undertaken by KEK-
DSO, which are not integrated with SCADA/EMS, such as SS Prishtina 7, SS Gjilani 5 etc.
The project is continuous and permanent, in terms of time period, and as such it is planned
to conclude by the end of 2015. The expected benefits of the project are:
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 86 of 138
Office: Long-term Planning and Development
- Increased security and reliability of transmission system operation
- Correct usage of SCADA/EMS applications in the analysis of transmission system
performance
- Monitoring and command of the whole transmission system
- Fulfillment of technical criteria provided upon by the ENTSO/E Manual
Project: INTER-TSO Meters
Currently there are measuring points in all interconnection lines; however, they are not
completely in compliance with the Metering Code and the technical requirements of
ENTSO/E. The problems fall in two aspects:
- Current and voltage metering transformers have only one core for measuring, while the
Metering Code requires to have two commercial cores with identical characteristics.
- Meters should be of multiple tariffs
Project foresees replacement of the measuring points in the interconnection lines:
- Line 400 kV: SS Kosova B – SS Nish
- Line 220 kV: SS Podujeva – SS Krushevc, SS Prizreni 2 – SS Fierza
- Line 110 kV: SS Vallaqi – SS N. Pazari, SS Berivojca – SS Bujanovci
Also the project will include three other measuring points in SS Kosovo B in the border with
PP Kosova B:
- Line 220 kV, SS Kosovo B – PP Kosovo B
- Two generation fields B1 and B2 in SS Kosovo B.
This project will complete the measuring points in all border of the transmission system with
others.
This project was also presented in IPA 2011 and is expected to be implemented in the
fourth quarter of 2015.
- Metering electricity between KOSTT and neighboring systems in line with the
metering code.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 87 of 138
Office: Long-term Planning and Development
Project: GIS System in support of Transmission System
The geographical information system (GIS) is to be used for organizing and processing of
transmission data for the whole territory of the Republic of Kosovo. The main feature of the
GIS system is the possibility of spatial/geographical data inter-relation, classification of all
technical details of transmission assets in correlation with the surrounding areas. The GIS
system also allows for communication with other IT systems.
The application of a GIS system in the Transmission System would enable:
- Accurate geographical positioning of line (pillars) and substations, information on properties in
and around installation positions.
- Detailed Technical information on each line (pillar), substation, telecommunication antenna, etc
- Information on property structure and construction in routes planned for new lines.
- Remote communication by equipment such as: thermal vision cameras, laser height meters, GPS
photo cameras, logistical means of GPS equipped maintenance teams.
- Data collection and processing inside a single collection centre.
- Communication with other IT systems
Benefits from the GIS system are rather large, both in terms of savings in the maintenance
process, and in the process of operational and long term planning. This system shall also
integrate a system for identification of intensity and positioning of lightning discharges,
which would contribute in further enhancement of preventive maintenance. The project is
due to be completed by 2018.
Expected benefits from the project are:
- Minimization of transmission network maintenance costs
- Optimization of the planning and maintenance process, reduction of action time
- Systematization of technical data
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 88 of 138
Office: Long-term Planning and Development
5.5. Rationale for changes in projects of the TDP 2013-2022 in comparison to the
TDP 2012-2021
The current development plan has differences in the project list and their implementation
periods, in comparison to the TDP 2012-2021. Main reasons for such changes are:
- Displacement of technical and commercial boundaries between KOSTT and
KEK-DSO
- Applications for connection to the transmission network unforeseen with the past
plan
- Optimization of distribution of capital costs in years.
In many transmission systems in European countries and wider, planning criteria are similar
to criteria applied by KOSTT in long-term planning processes of the transmission system.
The fulfilment of the N-1 security security is rather challenging even for the most developed
countries, due to the high investment costs in such realization. For this reason, KOSTT also
takes into consideration the costs of reaching system operation security criteria in its
planning processes. The main objective is to fulfill such criteria within the shortest period
possible. The technical criteria of operation security require time to be met, while additional
information is provided to the ERO. The selection of projects to be postponed in periods
derives from a technical analysis of all projects, their degree of influence in the system
reliability and security, and priority setting based on benefits provided by these projects.
The displacement of the boundary from 110 kV to the medium voltage level between
KOSTT and KEK-DSO is the main factor necessitating the inclusion of new projects, and
postponement of projects in time. The assessment of the technical condition of transferred
assets has brought the emergency and additional investment needs to surface. Also, the
approach taken in planning 110/x kV substations has changed to some extent, thereby
causing additional responsibilities for KOSTT in planning, and in coordinating with KEK-
DSO plans. The ultimate approach in planning substations to support the load shall be
described in the revised methodology of connection fees, to be decided by the ERO.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 89 of 138
Office: Long-term Planning and Development
Some of the projects which the TDP 2012-2021 had scheduled for the northern part of the
transmission network have been postponed in time, due to the current situation of that part
of the Republic of Kosovo.
The following are projects which were added as new projects, which were not part of the
TDP 2012-2021, as a result of displacing technical and commercial boundaries between
KOSTT and KEK-DSO:
- Second transformers at SS Skenderaj, SS Klina, SS Burimi and SS Berivojce
- Revitalization of 35 kV voltage equipment at SS Gjakova 1, SS Gjilani 1, SS Ferizaj 1, SS
Prishtina 2 and SS Lipjani
- Reserve transformer 40MVA, 110/10(20) kV
Projects of load support, which are not related to the transfer of fees and connection fee
methodology, and are not part of the TDP 2012-2021:
- SS Mitrovica 2
- Project Package SS Malisheva
- SS Prishtina 6 and
- SS Fushë Kosova
The rationale for projects presented and expected benefits from their implementation is
provided with technical descriptions of each project presented above.
The projects which are not part of the TDP 2013-2022, while being earlier listed in the TDP
2012-2021, are:
- New 110 kV line Rahovec-Theranda
- New 110 kV line: Peja 1- Deçan
- New 110 kV line: Peja 3- Mitrovica 2
- Revitalization of L 118/1 SS Prishtina 1- SS Kosova A Line
- Revitalization of SS Klina and SS Lipjani (110 kV level)
The first project, the 110 kV line Rahovec -Theranda is incorporated with the SS Malisheva
Project Package. In this case, KOSTT shall require a derogation from the ERO, in terms of
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 90 of 138
Office: Long-term Planning and Development
N-1 criterion for supply of Rahovec, which is to operate in a radial manner, until the
Malisheva project goes into function.
The second project, the 110 kV line Peja 1- Deçan, is not in the list as a result of connection
of 35 MW HPP “Deçani” with the 110 kV busbars at SS Deçan. This injected power reduces
the load flows in that part of the network, and for this reason, the project is rescheduled for
after 2022.
The project New 110 kV Line Peja 3- Mitrovica 2 is postponed beyond the 2013-2022
period, and it remains optional, the initiation of which shall depend on development of
industrial demand in Mitrovicë.
The project of revitalization of 110 kV Line SS Prishtina 1- SS Kosova A, is eliminated as a
result of influence of SS Prishtina 6, SS Prishtina 7 and SS Fushë Kosova in reducing load
flows in 110 kV lines supplying substations SS Prishtina 1, 2 and 3.
The SS Klina and SS Lipjan revitalization projects have been postponed for after 2013-2022,
due to a reduction in investment costs, thereby considering that their operations until <40
years of age may be economically reasonable, but always in due account of the level of
security of supply.
Also, the project of implementing changes to the SCADA/EMS is a new project, which
appears as necessary after the implementation of changes in the network configuration.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 91 of 138
Office: Long-term Planning and Development
6. TRANSMISSION NETWORK PERFORMANCE ANALYSIS
6.1. Description of the network model
Transmission network planning begins with creating basic mathematical model which
corresponds to network situation at the end of 2012 using technical data elements that
comprise the Power System. The parameters necessary for creating basic mathematical
model include:
- Electrical parameters of existing generators
- Electrical parameters of 400 kV , 220 kV and 110 kV lines
- Electrical transformer parameters, without including the 110/35/10 kV and 110/10 kV
transformers
- The maximum active and reactive power during winter and summer season in the points of distribution
and other expendable points.
- Common power flow in border lines
- Normal configuration of the transmission network.
Simulations and technical analysis of system performance in different periods have been
conducted with the help of software package PSS/E 32. This applicable software for the
planning processes of transmission networks is used in most countries of South-East
Europe, but also in many European countries and the world.
Iterative method (recurring), "Full Newton Raphson” is used to calculate the power flows,
while in calculating the security network criteria is used the module ACA " AC Contingency
Solution "which is integrated into the PSS/E.
For the purpose of calculating the analysis of short circuits to the system nodes, and
disconnection ability of the breakers for voltage level: 400 kV , 220 kV and 110 kV a more
complex model was used, which includes the entire region of South-East Europe, model
which contains the order parameters of positive, negative and nular elements of the network.
To calculate the short circuit currents in the transmission network are implemented the
method of calculation according to the IEC 60909 standard.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 92 of 138
Office: Long-term Planning and Development
Power System is analyzed for the most unfavorable conditions during the maximum load
on the network. Operating conditions and system performance depends on network
configuration, interconnection flows and connection of existing generators.
The analyzed performance of the current network has identified the network sections which
do not comply with technical requirements and the needs for reinforcement in appropriate
time sequences, in correlation with the planned development of the system load.
6.1.1. Transformation capacities; Q4-2012
Transformation capacities of the transmission network, managed by KOSTT, are installed at
substations 400/220 kV , 400/110 kV and 220/110 kV , 220/X kV and 110/X kV.
The largest transformation capacity is installed at SS Kosova B 400/220 kV. At this
substation, there are three auto-transformers installed with a nominal load of 400MVA. The
total transformation capacity of this substation is 3*400 = 1200MVA.
- At SS Peja 3, 400/110 kV, only one auto-transformer of nominal load of 300MVA is
installed. In SS Ferizaj 2 400/110 kV also, an automatic transformer with nominal
power of 300 MVA was installed.
- At SS Kosova A, 220/110 kV, three AT-s of nominal load of 150 MVA are installed,
with a total transformation capacity of 450MVA.
- At SS Prishtina 4, 220/110 kV, three AT-s of nominal load of 150 MVA are
installed, with a total transformation capacity of 450MVA.
- At SS Prizreni 2, 220/110 kV, there are three automatic transformers with nominal
power 150 MVA, with a total capacity of 450MVA.
- Whereas, substations 110/x kV and 220/x kV have an installed capacity of 1788. 5
MVA (without Trepça, Sharri and Ujmani).
Table 6-2 shows transformation capacities of the transmission network in Kosovo, as per
network configuration Q4-2011.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 93 of 138
Office: Long-term Planning and Development
Tab. 6-1 Transformation capacities at transmission network; Q4-2012
Total transformation capacities for the current year 2012 are 4938. 5 MVA. This increase of
the transformation capacity comes as a result of KOSTT’s ownership of all 110/35/10(20)
kV and 220/35/10 kV substations.
Distribution transformers do not include transformers in Trepça, Ferronikeli, Ujmani dhe
Sharri, which are not part of KOSTT assets.
Direct load supply at 35 kV and 10 kV levels is realized with transformation capacities with
400/110 kV, 220/110 kV, 220/35/10 kV and 110/35/10(20) kV, with a total capacity of
3738. 5 MVA.
6.1.2. The current load exchange capacity with neighboring countries
The maximum capacity of load exchange with neighbors (at natural line power) with high
voltage transmission lines is 1740 MW. At 400 kV lines, the existing cross border
transmission capacity is around 1500 MW (3x500 MW), while at the 220 kV level, some
other 240 MW are added (120 MW line with Albania, and 120 MW line with Krusevac,
Serbia).
ATR- Q4 2012 Number Total Transforming Capacity (MVA)
400/220 kV 3 1200 SS KOSOVA B
400/110 kV 1 300 SS PEJA 3 1 300 SS FERIZAJ 2
220/100 kV SS KOSOVA A 3 450 SS PRIZRENI 2 3 450 SS PRISHTINA 4 3 450
110/10 kV & 110/35 kV
49 1708.5
220/10/35 kV & 220/10kV
2 80
Total 65 4938.5
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 94 of 138
Office: Long-term Planning and Development
NTC3 (Net transfer capacity) of interconnection lines in Kosovo is smaller than their natural
power, and it largely depends on the regional electricity balance in neighboring countries,
and from limitations to the regional horizontal network, which may appear in various
operational regimes. The table 6-2 shows the current capacities of interconnection lines as
per their natural power (P), average NTC and nominal thermal power (Sterm) [10]
Table 6-2. Current interconnection line capacities
The simultaneous interconnection transmission capacity (KNTI) is different from NTC, and
is calculated for two cases:
- When the electro-energy system simultaneously imports through all interconnections (at different time
periods), until a first limitation at the horizontal network appears for the importing country and
exporting countries (for the N-1 criterion).
3 NTC – means max total electricity power exchange between two control areas, compatible to security
standards applicable in all regulatory areas, and in due consideration of technical uncertainties of the network
condition (definition from the ENTSO-E guideline).
Niveli Fuqia natyrore Termike NTC
[kV] [MW] [MVA] [MW]
Kosovë - Serbi 600
NS Kosova B- NS Nish 400 500 1317
NS Podujeva - NS Krushevc 220 120 300
Kosovë - Maqedoni 400*
NS Ferizaj 2 - NS Shkupi 5 400 500 1317
Kosovë - Mali I Zi 400
NS Peja 2 - NS Ribarevinë 400 500 1317
Kosovë - Shqiperi 210*
NS Prizreni 2 - Fierza 220 120 300
* Nga https://www.entsoe.eu/fileadmin/user_upload/_library/ntc/archive/NTC-Values-Winter-2010-2011.pdf
SISTEMET DHE LINJAT
INTERKONEKTIVE
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 95 of 138
Office: Long-term Planning and Development
- When the power system simultaneously imports through all interconnections (at different time
periods), until a first limitation at the horizontal network appears for the importing country and
exporting countries (for the N-1 criterion).
Calculation is rendered by the PSS/E software, based on long term demand and generation
forecasts for the regional countries, correlated with regional transmission system
development plans [8]. Natural flows at interconnection lines are flows defined by system
impedance, generation location and loads in case when individual systems are balanced (no
exchange). Natural flows are amongst key factors affecting various capacities of
interconnection for imports and exports.
The Simultaneous Interconnection Transmission Capacity is not calculated as an amount of
Net Transfer Capacity (NTC), and as such, it is much smaller4.
Currently, the KNTI of the transmission system in Kosovo is approximately 900MW for
power imports, and 1000MW for power exports. Considering the electricity balance, it may
be considered that current interconnection capacities are rather large, and allow for any
exchange program for the needs of the power system in Kosovo.
In order to ensure effective access to the transmission network and implicitly market
infrastructure for cross-border transactions, is developed regulations 1228/2003/EC which
sets out the principles for congestions managing. In this case, it has become clear that
interconnection lines congestions should be selected on the basis of market orientation and
non-discriminatory methodology. The allocation of capacity currently based on the
calculation of NTC, on the interconnection lines between TSOs. The experience of recent
years has shown that cross-border capacity allocation method based on the market can lead
to inefficient use of interconnection capacity, if not taken into account the real power flows
properly. Allocation based on power flows, now is used by several TSO in Europe.
In general, capacity allocation based on power flows presents a method which applies to
large group of TSOs. This means that bids for energy and relevant cross-border capacities
are optimized by a centralized entity that takes care of the actual allocation "Coordinating
allocation Office." In capacity allocation mechanism based on power flows, commercial
4ENTSO/E Raport: System Adekuacy Forecast 2009-2020
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 96 of 138
Office: Long-term Planning and Development
transactions are not limited to interconnections where they have been reported, but they are
converted into the physical flow of power using simplified models in order to assess the
impact of flows in other interconnections, and to assess the overall safety of the
transmission system which includes the entire TSO-s group.
The expected advantages from the establishment of the "Office for coordinating allocation"
using coordinated sales based on the power flow are:
optimal use of existing interconnection
high level of system security
Facilitate regional market activities due to the efficient use of the transmission
network and the establishment of cross-border transactions
Increasing transparency between the parties involved.
Promote investment in infrastructure.
6.2. Analysis of the transmission network condition as per topology Q4-2012
Investments made in the transmission network during 2009-2012 have had an effect in
improving the operational performance of the transmission system. Current ongoing
projects, and those expected to be completed by the end of 2012, will enhance the network
even further towards compliance with the technical requirements as per Grid Code. Figures
6-3, 6-4 and 6-5 show Kosovo’s power system, as per network topology Q4-2012. Figure 6-4
shows power flows and voltage levels in the Power System in PSS/E.
6.2.1. N-security criterion analysis
The system was analyzed for a gross max load of 1170 MW, with all elements (lines,
transformers, load) at operation. In this case, power flows were monitored, together with the
level of voltage at bus bars, and level of load on 400 kV, 220 kV and 110 kV lines; and in
auto-transformers 400/220 kV, 400/110 kV and 220/110 kV, and after the transfer of 110
kV assets from KEK-DSO to KOSTT also in the 110/35 kV and 110/10(20) kV
transformers. Simulation results have not identified any overloaded elements. The maximum
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 97 of 138
Office: Long-term Planning and Development
capacity of internal transmission network, as per technical security criterion N for the end of
2012 is around 1480MW. This means that the transmission system can supply a gross load of
1480MW, while fulfilling the N-security criterion. If one refers to the forecasted maximum
load, there is a sufficient security margin, approx. 26. 5% (310 MW).
6.2.2. N – 1 security criteria analysis
The system performance was analyzed in terms of the N-1 security criterion, thereby
monitoring line and transformation loads, and the level of voltage at bus bars when a critical
element (transformer, line, cable) fails. Table 6-3 presents the lines which do not fulfill the
N-1 criterion, the outage of which causes deviation of load or voltage, beyond the limits
allowed by the Grid Code.
Table 6-3. Lines falling out of N-1 criterion, as per network configurationQ4:2012
In addition, critical outages are also associated with the line SS Drenas –SS Prizren 2, but
this is only eliminated if we import 100 MW or more from Fierza.
Critical failures numbered 1 and 2 will be eliminated if the line 110 kV SS Prizren 2-SS
Prizren 1 with a length of 3. 2 km, is converted into a dual line.
Critical failures 3 and 4 will be eliminated with the completion of the project of line
allocation L1806 from Gjakova 2 to Gjakova 1.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 98 of 138
Office: Long-term Planning and Development
In terms of transformation, there are further restrictions to the fulfillment of N-1 criterion.
Table 6-4 shows substations which do not fulfill the N-1 criterion.
Table 6-4. Auto-transformers falling out of N-1 criterion (Q4:2012)
Computer analysis (simulations in PSS/E in the system model) have shown that currently
the transmission network can fulfill the N-1 criterion for loads smaller than 1080 MW.
Figure 6-1 presents development of N and N-1 capacities of the (internal) network, in
relation to the seasonal load for the period Q1/2011-Q4/2012.
Figure 6-1 Development of internal transmission network capacities from Q1-2011 to Q4-2012.
Capacity /N (MW) Capacity /N-1 (MW)Peak load (MW)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 99 of 138
Office: Long-term Planning and Development
6.2.3. Voltage profile and losses
Creation of powerful nodes at SS Peja 3 and SS Ferizaj 2, and construction of 110 kV lines
and their reinforcement has made possible the situation that in normal operation conditions
of the transmission system (at maximum load), the level of voltage as per configuration Q4-
2012 is within allowed limits as per Grid Code. Figure 6-2 shows voltage profiles for two
different network topologies in 2011 and 2012. The chart presents that the voltage levels at
all nodes are within limits allowed by the Grid Code. One may observe the impact of entry
into operation of 100 kV line SS Ferizaj 2 – SS Gjilan 5, which reflects in a considerable
increase of voltage level at 110 kV nodes of some substations in the region of Gjilan
connected to the substation. In terms of fulfillment of the N-1 security criterion in terms of
voltage, tables 6-3 and 6-4 present the critical failures which cause a decline of voltage levels
under the limit allowed by Grid Code.
Fig 6-2. Comparison of voltage profile at 110 by two network topologies,2011 and 2012
The system was analyzed also in terms of load loss in maximum load, while the computer
calculation results are presented with the table 6-5. Losses were calculated specifically in lines
and transformers, as per level of voltage. Calculated load losses in peak load are based on
ideal resistance and inductivity of elements modeled at PSS/E, and do not reflect real losses,
which are dependent on other factors which cannot be modeled, such as: resistance of
contact of high voltage equipment, resistance of connection bridges in line conductors,
98
100
102
104
106
108
110
112
114
116
118
120
122
124
U(k
V)
Topology_2012_P=1170 MW Topology_2011_P=1150 MW
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 100 of 138
Office: Long-term Planning and Development
crown effect, impact of temperature change at Ohm resistance, etc. Nevertheless, the results
gained provide important comparisons showing the trend of loss development at the
function of load changes and network capacity. Grid load losses for various years do not
match with energy losses during a year, since in the majority of cases, grid reinforcements
take place in the fourth quarter of a year, while the effects at the volume of energy losses in
the network can only be recorded in the next year, after relevant reinforcements are made.
Tab. 6-5. Active and reactive power losses at maximum load (Q4-2012)
In terms of active power, the largest losses are caused at transmission lines (76%), where
losses at 110 kV lines dominate with a percentage of 66. 7% in comparison to total loss. In
comparison to peak losses in the previous year 2011 (29MW), current year losses have
marked an increase, 15% higher, which can be justified by the fact that 10/35/10(20) kV/
kV and 220/35/10(20) kV/kV distribution transformers have also been added in the
transmission network, and the peak load increased simultaneously with the network capacity
improvement. Reactive power losses are caused mainly at power transformers, while total
lines are rather close to reactive compensation. Losses of reactive power are greater than the
distribution transformers (74. 8 MVAr).
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 101 of 138
Office: Long-term Planning and Development
KOSOVO POWER SYSTEM 400/220/110 kV
Fig. 6-3 Single pole scheme, Kosovo power system, network topology Q4-2012
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 102 of 138
Office: Long-term Planning and Development
Fig. 6-4 Modell of the PSS/E of the Kosovo Power System by network topology Q4-2012
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 103 of 138
Office: Long-term Planning and Development
Fig. 6-5 Kosovo Power System by network topology Q4-2012
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 104 of 138
Office: Long-term Planning and Development
6.3. Analysis of the transmission network condition by topology- 2018
During 2018, rather important projects are due to complete, thereby influencing directly the
improvement of the operational performance of the transmission system. In the period
2013-2018, we expect to have operational the following projects
- SS Prishtina 7 110/10(20) kV
- SS Mitrovica 110/10(20) kV
- Interconnection line 400 kV SS Kosova B – SS Tirana 2
- Hydropower Plant “Lumi Deçani” 35 MW
- Second Auto-Transfomer 300MVA, in SS Peja 3, 400/110 kV
- Second Auto-Transfomer 300MVA, in SS Ferizaj 2, 400/110 kV
- New 110 kV line SS Peja 3- SS Peja 1
- Revitalization of the line L155/2 and L163
- SS Dragashi and line 110 kV SS Kukës-SS Dragash- SS Prizren 2
- SS Malisheva and line 110 kV SS Rahovec -SS Malisheva– SS Theranda
- SS Prishtina 6 110/10(20) kV
- SS Fushë Kosova 110/10(20) kV
- Revitalization of the line110 kV: L126/2 SS Peja 2- SS Deçan
Gross maximal load in 2018 is forecasted to be 1365MW. Figure 6-9, 6-10 and 6-11is shown
in Kosovo’s Power System, by network topology Q4-2018. Figure 6-10 shows the power
flows and voltages in the Power System in PSS/E.
6.3.1. N-security criterion analysis
The system was analyzed for the maximum estimated gross load of 1365 MW, for the
network topology Q4-2018, with all elements (lines, transformers, load) in operation.
The simulation results have not identified any lines or transformers overloaded. The
maximal capacity of the internal transmission network, as per N-security criterion for the
end of 2018 will increase considerably compared to 2012, as a result of planned
reinforcements in the transmission network. Maximal capacity of the internal transmission
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 105 of 138
Office: Long-term Planning and Development
network would revolve around the amount of 1850MW. This means that the transmission
system can supply a gross power of 1850 MW by the end of 2018, without any network
bottlenecks and under the allowed voltage level limits. Referring to the maximum estimated
load for 2018, there is a sufficient security margin, which circles around 34% (465 MW).
6.3.2. N-1 security criterion analysis
Implementation of planned projects until 2018 will result with a transmission system which
for the first time will fully meet the technical criteria required by the Grid Code, in terms of
security and quality of supply. From the fourth quarter of 2018, the transmission system will
fulfill the N-1 security criterion for lines (cables) and transformers, always referring to the
values outlined for the load in the next ten years. If the load forecast goes according to the
low scenario, the N-1 criterion will be fulfilled earlier.
Figure 6-6 shows N and N-1 capacity development of the (internal) network, in relation with
the seasonal load for the time period Q1:2013-Q4:2018
Capacity /N (MW) Peak load (MW) Capacity /N-1 (MW)
Figure 6-6 Internal transmission network capacity development, from Q1-2012 to Q4-2018.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 106 of 138
Office: Long-term Planning and Development
6.3.3. Voltage profile and losses
The voltage profile at all 110 kV voltage levels in the 2018 network topology should remain
within optimal limits in maximum load, as shown in the figure 6-7.
Fig. 6-7Voltage profile in 110 kV bus bars as per 2018 network topology
In operational regimes at summer loads in the system, higher voltage levels are recorded,
especially at 400 and 220 kV horizontal grids, as shown in the figure 6-9. The reason for
such an increase in voltage is development of the 400 kV network capacities in the region
influencing our system; construction of a 239km long line SS Kosova B- SS Tirana 2, which
in minimum load regimes should inject around 75MVAr of capacitative reactive power in SS
Kosovo B bus bars. In this case, the installation of an inductive reactor 120MVAr at SS
Tirana 2 (220kV bus bars) is considered.
The control of voltage level at 400kV bus bars is almost negligible, by undertaking
operational measures within the relatively small power system of Kosovo, while the voltage
level at 220 kV bus bars is partially controllable, by making limited modifications of the
network topology (opening of the SS Fierza – SS Prizren 2 line, disconnection of a
transformer at SS Kosova B etc). Over-voltage levels at 110kV level can be managed easily,
since the 110 kV network topology can be modified as per certain modes, with a view of
avoiding line overcompensation. The only technical possibility of controlling overloads on
transmission grids is installation of an inductive static reactor 100MVAr at SS Kosova B (at
98
100
102
104
106
108
110
112
114
116
118
120
122
124
126
U(k
V)
substations 110 kV
Profile UUmax,UminUnominal
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 107 of 138
Office: Long-term Planning and Development
220 kV bus bars). Due to high uncertainty of network developments in the region, the
voltage level at the horizontal network (inside and outside the system) will be monitored
carefully, so as to ensure a timely decision on planning installation of a 100 MVAr reactor at
SS Kosova B.
Fig. 6-8 Voltage level at 400kV and 220kV bus bars in summer minimum load regimes.
Active power losses will be reduced at 110 kV lines, while at 400 kV lines there will be an
increase of losses, as a result of construction of the 400 kV line SS Kosova B – SS Tirana 2,
and the increased transit flux in the transmission network. The active power losses will
increase in comparison to 2012, while reactive power losses will decrease in comparison to
2012. The following table shows total losses at transmission network, and loss percentages as
per voltage level and type of element.
234.5kV
412.8kV 411.6kV 412kV
234.3kV 233.4kV
230.3kV
233.4kV 233.8kV
0.98
1
1.02
1.04
1.06
1.08
1.1
1.12
(P.U
)
Voltage profile Unominal Umax Uextrem
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 108 of 138
Office: Long-term Planning and Development
Tab. 6-6. Active and reactive power losses in maximum load (2018)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 109 of 138
Office: Long-term Planning and Development
KOSOVO POWER SYSTEM 400/220/110 kV
Fig. 6-9 Single pole scheme of Kosovo power system, network topology 2018
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 110 of 138
Office: Long-term Planning and Development
Fig. 6-10 Model of the Kosovo Power System in PSS/E according to network topology 2018
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 111 of 138
Office: Long-term Planning and Development
Figure 6-11. Kosovo Power system according to network topology 2018
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 112 of 138
Office: Long-term Planning and Development
6.4. Analysis of the transmission network condition, topology - 2022
The operational performance of the transmission system was analyzed for 2022, modeled in
PSS/E by integrating all planned projects for the next 10 years. As per a list of projects
selected by a computer analysis determination, a considerable number of important projects
of transmission network reinforcement is planned for implementation for the time period
2019-2022 such as the following:
- Revitalization of the line SS Prizren 1 – SS Prizren 3
- New line 110 kV SS Prizren 1- SS Prizren 2
- Revitalization of the line L163 SS Kosova A- SS Bardhi - SS Mitrovica 2- SS Vallaq
- New line 110 kV SS Peja 3- HC Ujmani
- Revitalization of the line110 kV , L115/2
- Project Package 400 kV ring Gjakova - Prizren - Ferizaj (phase I)
Figures 6-15, 6-16and 6-17show Kosovo’s Power System according to network topology of
Q4-2022. Figure 6-16shows the power flows and voltages of the Power System in PSS/E.
6.4.1. N security criterion analysis
The system was analyzed with 1000 MW of new generation capacity connected to SS
Kosova B and decommissioning of the TPP Kosovo A, referring to the conservative
generation development scenario as per document “Generation Adequacy 2013-2022”.
The system was modeled to a gross load of 1494 MW as forecasted for 2022. The
construction of SS Prizren 4, 400/110kV and creation of a 400kV ring, should ultimately
bring the transmission network to a condition conducive to further support for the load and
development of large generation capacities, both conventional and renewable. As presented
by the Fichner study, the new 400 kV network topology will enable the sectioning of load
groups connected at 110 kV network, and enhancement of operational security of the
transmission network, by establishing reserve disconnection capacities. The internal network
capacity will have attained the amount of 2100MW with a 40. 5% (606MW) security margin
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 113 of 138
Office: Long-term Planning and Development
in relation to the maximum load for 2022. The figure 6-11 presents a horizontal scheme of
the transmission network, modeled after the regional network (SECI_2020_PSS/E). The
model shows the load flows for certain regimes of regional exchange. The ring configuration
allows for the creation of four consumption groups to be supplied by main transmission
substations.
Fig. 6-12 Horizontal network of transmission system, after development of 400 kV ring - topology
2022
6.4.2. N-1 security criterion analysis
The 2022 network topology transmission system does not identify any lines or transformers,
the outage of which would create any overload or underload in other parts of the network.
Such a network topology allows for a full compliance with the N-1 security criterion up to
the consumption rate of 1500MW. The creation of a 400 kV ring, and creation of four
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 114 of 138
Office: Long-term Planning and Development
consumption supply groups, all create higher flexibility and operation security of the system.
The failure of any single 400 kV line would not influence the security of supply for
consumption and regional exchange. The N-1 criterion is fulfilled both for interconnection
lines and internal lines.
Development of internal network capacities for the period 2018-2022 is presented with the
figure 6-13.
Capacity /N (MW) Peak load (MW) Capacity /N-1 (MW)
Fig. 6-13 Internal transmission network capacity of transmission 2018-2022.
6.4.3. Voltage profile and losses
The reconfiguration of the 110 kV network, by creation of four supply groups I- Peja 3, II-
Kosova A & Prishtina 4, III- Ferizaj 2 and IV-Prizreni 2&4, creates an almost maximal
optimization conditions for load flows, reflected into an ideal voltage profile at all bus bars
400, 220 and 110kV during the winter consumption.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 115 of 138
Office: Long-term Planning and Development
Figure 6-14 shows the voltage profile for 110kV bus bars.
Fig. 6-14 Voltage profile in 110 kV bus bars as per network topology for 2022
MW-expressed network active power losses will be higher than 2018, as a result of growing
consumption. As per computer calculations (Table 6-7), losses of active power in peak load
1494MW will be 40. 5 MW, from which 77. 8% are caused by lines, where line losses
dominate 110kV (54. 3%).
In terms of reactive power in the transmission system, the influence of 400 kV ring is rather
present. Lines inject a total reactive power of 161 MVAr (capacitative) into the network,
while on the other hand transformers can absorb a reactive power rate or approx 225.5
MVAr (inductive), which means that only 73. 5 MVAr are counted as reactive power losses
caused by the transmission network. The reactive side of consumption is to be covered by
domestic generation sources.
80
85
90
95
100
105
110
115
120
125
130
Fer
2
Fer
1
Ber
iv
Vush
i 2
Bar
dh
Deç
Dra
Gja
1
Sh
arri
Gjil
ani 5
Ujm
ani
Buri
mi
Sken
i K
lina
Vit
ia
Lip
j P
eja
3
Pej
a 1
Pr
6
Pr
5
Pr
1
Pr
2
Pr
3
Pr
4
Pz
1
Pz
2
Pz
3
Rah
z T
hez
Tre
pz
Ko
s A
Val
l
Substations 110kV
Vo
ltag
e [
kV
]
Voltage profile Unominal Umax Umin
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 116 of 138
Office: Long-term Planning and Development
Tab. 6-7. Active and reactive power losses in maximum load (2022)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 117 of 138
Office: Long-term Planning and Development
Fig. 6-15 Single-pole scheme of the Kosovo power system, network topology 2022
KOSOVO POWER SYSTEM 400/220/110 kV
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 118 of 138
Office: Long-term Planning and Development
Fig. 6-16 Model of the Kosovo Power System in PSS/E according to network topology 2022
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 4 page 119 of 138
Office: Long-term Planning and Development
Figure 6-17 Kosovo Power System by network topology 2022
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 120 of 138
Office: Long-term Planning and Development
6.5. General conclusion
The Kosovo transmission system must develop in a manner of allowing for a secure, reliable
and qualitative supply of consumption, pursuant to technical requirements of the Grid Code
and the operation manual of ENTSO/E. An adequate and sustainable development of the
transmission system provides for favorable conditions of development of conventional and
renewable generation capacities. Appropriate long term planning for transmission system
development is essential to meeting above-mentioned requirements. The Transmission
Development Plan 2013-2022 has identified medium and long term needs for infrastructure
projects necessary for the enhancement and maintenance of the operational performance of the
system, in relation to development in consumption, generation and regional markets of energy.
The TDP 2013-2022 sets forth the development priorities broken down by category and
implementation timelines. The full realization of transmission development plans is challenging
to the most developed countries. Difficulties in accessing property, global economic crisis, lack
of financial resources, social implications, are some of the factors which may slow or prevent
the realization of projects which are necessary to be taken into account by planning engineers.
If one would refer to development of KOSTT in the last 5 years, it may be considered that
development objectives have largely been realized thanks to financial support of the Kosovo
Budget and international donors. Positive impacts of projects completed and those ongoing
have been analyzed in the previous development plan, while the following are general
comments on new development projects presented in the TDP 2013-2022.
Developments in the last 5 years of the transmission system have created conditions for
KOSTT membership to ENTSO/E. Regarding policies arising from ENTSO/E Operation
Handbook which relates with technical requirements to be fulfilled each TSO, KOSTT with
recent investments, increasing the transmission capacity, security and reliability of the system as
well as development modern systems for measurement, monitoring and control, is in the same
position or better than some of the TSO-s in the region which are already members of the
ENTSO/E. With development of the secondary control project which represents one of the
main technical requirements for membership in the ENTSO/E, KOSTT will be fully ready for
membership.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 121 of 138
Office: Long-term Planning and Development
6.5.1. Network capacity development
The implementation of projects identified by the TDP 2013-2022 will enable a consistent
enhancement of internal network capacities, which in turn would render conducive to supply
consumption. Reinforcement at key nodes at SS Peja 3, SS Ferizaj 2 and SS Prizren 4, 400 kV
and 110 kV network reconfiguration with the development of new 110 kV lines, are the key
factors to foster development of transmission network capacities. The figure 6-18 shows a chart
of development of internal network capacities in relation to load development for the next 10
years, in two scenarios of peak development.
Fig. 6-18. Development of internal network capacities in relation to load development for the next 10
years
In the next ten year period, the horizontal network will also be subject to capacity
enhancement, as a result of development of the new 400 kV interconnection line SS Kosova B
– SS Tirana 2, and construction of the 400 kV ring in Kosovo. The capacity of transmission
network interconnection lines in Kosovo will be much higher than the import margin, or
possibilities of electricity export available to our country for the next 10 years, even in due
consideration of a considerable volume of transit flows (through our network) for the regional
countries. However, on the other hand, restrictions are announced in the regional network,
which could limit high imports. In most cases, capacities presented by TSO-s of the region,
particularly by EMS, are considerably lower than the reality. Figure 6-16 provides indicative
Capacity /N (MW) Peak load (MW) High peak load (MW)
Security margin
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 122 of 138
Office: Long-term Planning and Development
values of simultaneous interconnection capacity for export and import, calculated in a regional
model. The estimated capacities take into consideration the N-1 criterion for the whole
horizontal network of regional transmission systems.
When referring to planned generation development in Kosovo, the horizontal network will be
able to accommodate considerable generation capacities in full compliance with technical
requirements of ENTSO/E. In case of construction of a second 400 kV line SS Kosova B –
SS Skopje, interconnection capacities would be considerably higher. This project remains
optional, and its advancement will largely depend on the changes of transit flows to
Southeastern European countries, and the size of generation capacities to be installed in
Kosovo.
Fig. 6-19 Simultaneous interconnection capacity development 2013-2022
6.5.2. N-1 security criterion
If one was to review the situation in the network before 2009, the N-1 security criterion would
not be compliant even in summer consumption, while in normal operation conditions, the
network would be subject to overloads which were managed by reducing load. In reference to
the current situation (2012), the network condition has changed largely for the better, in which
case the network does not display any bottleneck, while the N-1 security criterion is not
complied with only at 5% of the annual time, excluding radial supplies of Rahovec and Lipjan.
1000
1500 1500
-900
-1400 -1400-1600
-1400
-1200
-1000
-800
-600
-400
-200
0
200
400
600
800
1000
1200
1400
1600
1800
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
KNTI Export [MW] KNTI Import [MW]MW
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 123 of 138
Office: Long-term Planning and Development
Full implementation of the N-1 security criterion requires considerable investment. If we refer
to development processes planned for the next 10 years, the security criterion will be fully
complied with only after 2018, while until then, the criterion will be very close to completion.
The figure 6-20 shows the ability of the network to fulfill the N-1 security criterion, in a relation
with the maximum load for the next 10 years, for two load scenarios. It is clear from the Figure
that the N-1 criterion will not be fulfilled even after 2018 if we take as reference the high load
increase scenario.
Capacity /N -1(MW) Peak load (MW) High peak load (MW)
Fig. 6-20. N-1 capacity development of the transmission network 2013-2022
6.5.3. Quality of supply and efficiency
Not long ago, a considerable part of the transmission network could not provide quality supply
in winter peaks due to the poor network, large active and reactive power losses. All this resulted
in rather low voltage levels at the 110 kV level, especially in areas remote to generation sources.
On the other hand, the amount of energy undelivered to consumption, as a result of restrictions
in the transmission network, was rather high. Reinforcements to the network, especially after
2008, have created the conditions for a quality supply of consumption and an extraordinary
reduction of power losses in the grid. The voltage level was stabilized after the commissioning
of the Peja 3 project, while with further investments, the operational efficiency of the network
and quality of supply were enhanced to a satisfactory level. The planned reinforcement in the
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 124 of 138
Office: Long-term Planning and Development
next 10 years will allow for a further enhancement of quality of supply and efficiency, but also
maintenance, pursuant to technical requirements of the Grid Code.
7. FAULT CURRENTS IN THE TRANSMISSION NETWORK
7.1. Introduction
This chapter examines the problem level of fault currents in all bus bars of 400 kV, 220 kV and
110 kV voltage level. Review of fault currents or three phases and one phase to ground short
circuit level was made for periods in relation to the planned developments in transmission
network and the overall Kosovo Power System.
7.2. Calculation of fault currents level
Kosovo Power System is strongly interconnected to regional transmission network 400 kV and
220 kV . Relevant supplies of fault currents which are characterized by serious impact on
system security are concentrated in two main substations of the system: SS Kosovo B and SS
Kosovo A. All existing TP plants are connected in the two substations. The objective of the
study of short circuits is assessment of the impact of fault currents in the security of the system.
Fault currents in 400 kV, 220 kV and 110 kV bus bars will be calculated in accordance with
Policy 3 of the Operation Handbook of ENTSO-E.
The essential objective of this study is to identify the bus bars in which the level of fault
currents exceeds breaking capacities of the existing breaker and determination of security
margin of all installed breakers or those that will be installed in the transmission system in
Kosovo.
7.2.1. Mathematical model, calculation methodology and applied software
In order to determine the maximum fault currents in transmission system of Kosovo and the
impact of neighboring systems in these currents, in study was used regional model which
include 13 models of integrated Power System of the countries of South-Eastern Europe. For
this analysis is also used software PSS/E 32. Part of the network which is interconnected with
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 125 of 138
Office: Long-term Planning and Development
this model it’s equal to the Teveneni network (method for simulations of models in the case of
large networks).
Calculation methodology is based on the IEC 90609 standard. Maximum effective value of the
sub-transient component of the total fault currents three-phase and one-phase with ground, is
applied to every bus bars of level 400 kV, 220 kV and 110 kV. Different from the previous
plan, after the transfer of 110 kV assets, two and tri layer 110/x kV transformers were
incorporated in computer models in PSS/E. In this case the generators are equaled to their sub-
transient reactance X "d. The time of 100ms is considered as the time of fault elimination.
Based on IEC 90609 standard, calculations are made for no load operation, while the initial
conditions of the equaled network voltage of the Tevenen is taken as 1.1Un.
Idc Dc component of fault current
Higher limit
Lower limit
Current
Time
Ik” = Effective value of the fault currents
ip = The initial amplitude of the fault currents
Ik= Continual fault currents
idc = Dc component of the fault currents
A = Initial value of the dc component of idc
Fig 7-1 Form of the fault currents and its components
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 126 of 138
Office: Long-term Planning and Development
7.2.2. Features of the power circuits of the transmission network
In the transmission system currently in the existing substations of KOSTT are installed
different types of circuit breakers in terms of producers. While in terms of types of dielectrical
medium for extinguish electric arch are installed two types of breakers:
- Oil circuits and
- Gas circuits SF6
The old generation of the breakers have usually used oil as a dielectric medium for extinguish
the arch, while new generations of breakers use SF6 gas with a dielectric characteristic and
much better durability.
Breakers with SF6 medium for arch extinguish represent necessary standard of breakers for
installation in transmission network. Also this kind of breaker has general features significantly
better than oil breakers, as in electro-mechanical stability during the process of normal
connections and disconnection, or the occurrence of fault currents.
KOSTT systematically is replacing the oil breakers with the new breakers within the re-
vitalizing projects of the existing substations. Disconnection capacity of circuit breakers is
different starting from 16. 5 kA, 18. 3 kA, 23 kA, 31. 5 kA and 40 kA. The safety margin of the
breakers and other high voltage equipments is estimated by recognizing the level of faults
currents failures in a long-term domain that can occur in all substations and compared with the
level of disconnection capacities of the breakers.
7.2.3. Results of the calculated fault currents
Based on IEC 60909 standard, are calculated three-phase and one-phase to ground short circuit
for voltage levels 400 kV, 220 kV and 110 kV of the transmission network. Calculation of
currents is made in computer models in relation to the project development under the network
configuration: 2012, 2018 and 2022.
In Chapter 8, in a more general manner, we have presented the effects of installing new
generators to increase the value of fault currents in the domain of the second five year planning
period, starting from the lowest scenario development of generating units of PP New Kosovo,
HPP Zhuri, and the HPP “Deçan River” connected in SS Deçan.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 127 of 138
Office: Long-term Planning and Development
7.2.4. Assessments of the calculated fault currents in busbars 400 kV, 220 kV
and 110 kV (2012)
Results of simulation of three-phase and one-phase fault currents with ground for network
configuration according to the latest situation in 2012 based on the IEC 60909 standards is
presented in Figure 7. 2.
The results of computer calculations in PSS/E show greater level of short circuit power in two
main substations, SS Kosovo A and SS Kosovo B, which are very close to generating resources
and supplies from the powerful interconnection of 400 kV .
At 220 kV busbars at SS Kosovo A the one phase to ground short circuit at a value of 27 kA
represents the largest electricity transmission network. Also in the SS Kosovo B at the both
levels of voltage the one phase to ground short circuit are relatively large at 20. 9kA (at 400 kV)
and 26 kA (220 kV). In all other parts of the network, distancing from generator sources, three-
phase short circuit current dominates over the single-phase. All 110 kV substations near SS
Kosovo A (Prishtina area), are characterized with large fault currents. Results of calculating the
level of fault currents lead to the following conclusions:
- 400kV , 220kV and 110kV breakers installed in the transmission network have e sufficient security
margin (>20%). Their disconnection capacity towards fault currents level is within the limits allowed
under the IEC standards for the high voltage disconnection equipments.
Plans for re-vitalizing of substations SS Peja 1, SS Gjakova 1 etc will help increase the safety
margin of these substations, which have very old breakers installed that do not guarantee the
stated nominal stability.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 128 of 138
Office: Long-term Planning and Development
Ik3-three phase fault Ik1-one phase to earth faultFa
ult
cu
rren
t [k
A]
Fig. 7-2 Chart of three and single phase earthed fault currents, for the current network topology
7.2.5. Assessments of the calculated fault currents in busbars 35 kV and 10 kV
After the transfer of distribution transformers 110/X kV from KEK-DSO in KOSTT, two and
three-layer transformer models were transferred to calculate short circuits in the computer
model, for the busbars 10 kV and 35 kV . Transformer fields and owner consumption fields are
now part of the KOSTT infrastructure. Calculation of fault currents have identified breakers
which have no security margin and their operation may risk the security of supply. Table 8-
1shows values of three-phased short circuit current values for busbars 10 kV and35 kV for the
case when transformers are not working in parallel in the medium voltage side, as it is the
practice.
Single-phase short circuit currents with grounding in distribution systems are usually limited
through Xg reactance or Omic resistance Rg. According to the Distribution Code, transformers
110/35 kV must ground their neutrals through the so-called Petersen reactance, which
represents and resonant impedance and are applied when there are long and numerous 35 kV
cables. In this case, single-phase short circuits with grounding are limited in the range 300-
400A.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 129 of 138
Office: Long-term Planning and Development
Transformer neutrals 110/10(20)kV are grounded through omic resistor of various resistances,
depending on the transformer power and desired value of single-phase short circuit limitation
with grounding. Usually single-phase fault currents with grounding are limited in the range 150-
300A.
The breakers’ security margin was determined from the calculations of three-phased fault
currents comparing with the disconnection breakers installed capacity in existing substations.
The data presented in Table 8-1identify three substations with inadequate dimensioning of
currents breakers.
Calculation results of the level of fault currents lead to the following conclusions:
- In SS Prishtina 1 and SS Prishtina 3, existing breakers of 10 kV level risk the security of supply, as
they have a negative security margin
- In SS Klina, the 10 kV transformer field breaker has the best dimensioning (25kA), but other
outgoing breakers 10 kV have a highly reduced margin. Breakdowns during nighttime when voltage
level may exceed 1. 1Un,may be a risk for the substation.
- Other substations have a sufficient security margin
- Installation of transformers 63MVA of voltage level 110/10 kV must be avoided due to high fault
currents in busbars 10 kV
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 130 of 138
Office: Long-term Planning and Development
Table8-1 Calculations of three-phased short circuit current in busbars 35 kV and 10 kV
7.2.6. Assessments of the calculated fault currents (2018)
The development of the network and change of the configuration change affects the values of
fault currents. An input in raising fault currents should be given by the new interconnection line
400 kV SS Kosovo B – SS Tirana 2, which is expected to enter operation in 2015. Also
Substation Ik3
[kA] CB
[kA] Margin
Besiana 35kV 9.9 20 50.5% Besiana 10kV 24.2 31.5 23.2% Prishtina 1 35kV 9.5 16 40.6% Prishtina 1 10kV* 34.7 25 - 38.8% Prishtina 2 10kV 30 40 25.0% Prishtina 3 10kV* 23.1 20 - 15.5% Prishtina 5 23.1 31.5 26.7% Bardhi 35kV 14 25 44.0% Vushtrria 1 35kV 4.5 12 62.5% Vushtrria 2 10kV 16.4 25 34.4% Skenderaj 10kV 15.3 25 38.8% Vallaq 35kV 8 12 33.3% Burim 10kV 16.6 25 33.6% Peja 1 35kV 5.9 25 76.4% Peja 2 10kV 16 25 36.0% Deçan 10kV 15.3 20 23.5% Klinë 10kV 15.6 16 2.5% Gjakova 1 35kV 3.8 16 76.3% Gjakova 2 10kV 16.7 25 33.2% Rahovec 35 kV 4.6 20 77.0% Rahov ec 10kV 10.6 25 57.6% Prizren 1 35kV 4.6 16 71.3% Prizren 1 10kV 16.7 20 16.5% Prizren 3 10kV 17.2 20 14.0% Therandë 35kV 6.4 16 60.0% Therandë 10kV 16.4 25 34.4% Lipjan 35kV 4.9 25 80.4% Lipjan 10kV 17 25 32.0% Ferizaj 1 35 kV 4.8 15 68.0% Ferizaj 1 10kV 23.3 31.5 26.0% Viti 35kV 3.7 25 85.2% Gjilani 1 35kV 4.3 12 64.2% Gjilani 5 10kV 15.6 25 37.6% Berivojce 13.3 25 46.8%
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 131 of 138
Office: Long-term Planning and Development
impedance reduction of 110 kV lines due to their reinforcement impacts the growth of fault
currents. Figure 7-3 shows the values of short circuit currents, three and single-phased earthed
connections in main substations.
Based on the plan for re-vitalization of substations in relation to the disconnection capacity of
high voltage equipment and values calculated for the fault currents in the system for
configuration 2018 can be concluded that:
- All circuit breakers installed in the transmission network and all high voltage equipment have
sufficient margins of safety(>20%).
Plans for re-vitalizing of substations SS Peja 1, SS Gjakova 1 etc will help increase the safety
margin of these substations, which have very old breakers installed that does not guarantee the
stated nominal stability.
Fig. 7-3 Chart of three and single phase earthed fault currents, for the 2018 network topology.
7.2.7. Assessments of the calculated fault currents (2022)
The 2022 model takes into account the development of new generation units based on the
conservation scenario of the Generation Adequacy Plan 2011-2020. In this model TPP Kosova
A is disconnected, and three units 3x300MW are modeled as shown in Figure 6-11. From
results presented in Figure 7-4, a notable increase is noticed in the level of fault currents as a
result of the construction of new generation capacities, and the construction of the ring 400 kV.
Ik3-three phase fault Ik1-one phase to earth fault
Fau
lt c
urr
ent
[kA
]
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 132 of 138
Office: Long-term Planning and Development
At 220 kV bus bars at SS Kosovo B the one phase to ground short circuit at a value of 29. 3 kA
represents the largest electricity transmission network. In 220 kV busbars, there is a domination
of single-phased short circuit current with grounding with a 26. 8kA value. Because of the
decommissioning of TPP Kosovo A, the level of fault currents will be lowered if compared
with the calculated values from 2012 and 2018 models, the effects of construction of SS Prizren
4, 400/110 kV connected with the 400 kV ring, are also noticed in the region of Dukagjini.
Fault currents are notably higher in substations near SS Prizren than before construction.
If we compare the disconnection ability of fault breakers with the level of fault current level, we
reach the following conclusions
- All installed power breakers in the transmission network have a sufficient security margin. (20%).
- Installed power breakers in SS Kosova B and SS Kosova A and all high voltage equipment are not
risked by the construction of TPP New Kosova, 3x300MW. Their disconnection capacity 40kA allows
sufficient security margin.
Fig. 7-4 Chart of three and single phase earthed fault currents, for the current network topology2022.
8. ENVIRONMENTAL IMPACTS
8.1. Environmental protection
Continuous caution for environment will be part of the overall KOSTT Policy and engagement
of this police is addressed in the certification of KOSTT with ISO 14001:2004 Standard.
KOSTT Development Plan will take measures to prevent and correct any mistake that is
Ik3-three phase fault Ik1-one phase to earth fault
Fau
lt c
urr
ent
[kA
]
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 133 of 138
Office: Long-term Planning and Development
referred to the environmental protection in accordance with the internal and external legal
bases. Negative impacts mainly include terms of the impact of electromagnetic fields (EMF),
noise and visual impact on the environment (more important effects).
It is a primary objective for KOSTT for the future to put particular attention to gaps, which can
directly or indirectly affect the health and wellbeing of the KOSTT staff, and certainly the
health and wellbeing of parties outside of KOSTT.
8.2. Environmental problems in the transmission system
One can say that the Environmental problems in the transmission system are divided into following:
- Environmental problems caused by the lines, and - Environmental problems caused by the substations
8.2.1. Environmental problems caused by the lines
Today when needed energy necessary for the development of our country, appeared in the
Development Plan, we need to adjust the priority of claims being aware of their impact on the
environment. Therefore we can say that the priority is set towards a necessary development of
electricity transmission of high voltage (during the above elaboration this need is reflected and
justified), not to eliminate the need to minimize the possible impacts on the environment.
Most of the lines pass through the agricultural areas, while a little less of those lines that pass on
the mountain ecosystems where their impact is not so expressed.
From the aspect of electromagnetic radiation, greater influence has the industrial frequency
electromagnetic fields. The research of harmful effects of this type of non-ionizing radiation on
man have not yet given the final answer, but it should be noted that nowadays there is a special
interest for the possible effects of electromagnetic fields on electrical equipment as well as on
the living creatures, especially on people. On the moment of the legal sanction of
electromagnetic impact this plan will take into consideration and will be subject to TDP's
implementation.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 134 of 138
Office: Long-term Planning and Development
We are in the phase of adequate recordings for most sensitive aspects of environment impact,
aiming to adapt to the requirements recommended by the WHO. We also have to monitor the
causes of faulty automatics actions, reduction of the signal-noise ratio in communication and
transmission equipment, and other important impacts, summarizing the necessary and required
data.
8.2.2. Environmental problems caused by the substations
Besides occupying the surfaces substations carry the biggest visual changes in their
surroundings, but in aesthetic terms do not affect significantly, since under the rules they
should be located outside residential areas. The continuous noise caused (transformers work) or
the non-continuous work (disconnection equipment/circuits), the most direct impact on the
environment of substations, and due to vegetation relief is rarely transferred to the residential
areas, but in the substations location is likely to have greater value than those allowed. This will
be determined soon, and adequate measures are likely planned and undertaken.
In modern equipment, breakers/disconnections include inert gas, hazardous for human health
of not used properly and sufficiently (timelines are specified and gas releases must be
sporadically measured), but have a undesirable impact in the ozone layer and with toxic
products in small concentrations, which are caused during the working process in equipment.
Having in mind that there are strict procedures in accordance with international rules, in the use
and maintenance of SF6 circuits, it is proposed that the implementation of SF6 technology, is
ensured after a period of time, when we consider the need to add gas, detectors issuing leaking
warning near the switch, followed by measurements of compensated amounts, and also through
adequate measurements, so that the risk index will be brought to minimum.
Large quantities of synthetic oils found in power transformers, while a little less in the high
voltage equipment. Having in mind that oils possess a high potential for environmental
pollution, adequate measures are taken, such as the construction of collecting pool and
protection for collections of any oil leakage. These pools at the same time are a kind of
prevention in cases of large failures likely to occur.
In the second half of 2012, we have received 28 facilities of SS 110 kV , for which we have
undertaken GAP analysis, which, with ToR, should be oriented towards appropriate
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 135 of 138
Office: Long-term Planning and Development
improvements and, as we have acted in previous KOSTT SS, this is a perspective of objectives
in developments in environmental aspects in KOSTT, in terms of SS. Draft Pilot Project for an
Echo-analysis of the largest SS in KOSTT, “Kosova B” 400/220 kV will start its
implementation in 2013. With this Project we will also create an adequate and effective
assessment plan, in the perspective of other environmental assessments.
8.2.3. Caution on the other environmental impacts
At a time when the need for more and more energy is growing, the real impact on the
environment and aims for qualitative protection of this segment including this TDP that
supports the following:
- Reduction of emissions in water, air and land
- Increase of energy efficiency
- Enforcing preventive measures in order to reduce the number of accidents
- Addressing remains, particularly hazardous ones
- Possibility for recycling in many functional forms, including in indirect ways
- Development of systems for data collection and database (electronic forms)
- Reduction of parts and equipment that are outdated
- Follow-up of gaps in the Line system
- Drafting documentation for this Transmission segment
- Construction of dual lines, where there are possibilities to rationalize the use of surfaces and corridors
- In general, the improvement of corridor occupation for Transmission, where possible
All these are implemented in preliminarily planned time frames, such as:
- Reducing the damage done in the past
- Reduce the impact of ongoing activity in the relevant sector, and
- Prevention of pollution from activities in the future (e. g. EIA - Environmental Impact Assessment
and preventive measures in proper reduction)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 136 of 138
Office: Long-term Planning and Development
8.3. Environmental plans
In favor of the implementation of the requirements for environmental protection is the well
supported initiative in setting environmental policy in KOSTT which is under the procedure to
be adopted. Clear definition of environmental issues in KOSTT and orientation on what will be
done to control the environment, means planning. Planning is accomplished through new
projects, which are followed by the Environmental Impact Assessment. The implementation is
started by established the organizational structure, staff responsibilities, competencies and
training. Communication practices, control of documents and procedures, operational control
and emergency preparation, define the operational part of the program. These points are also
included in the EMS Manual (Environmental Management System) which will document a
program that has determined objectives and targets to be achieved. This Manual was developed
and has 18 procedures included which will be complemented with the Operational part, based
in practical requirements of the Transmission Operator and its operational plans. These, along
with routine monitoring conducted in the period 2013 – 202, reporting the situation recorded
along with appropriate recommendations, constitute a program of controlling acts and
corrective ones in EMS. Finally, a review of routine management activities is lowed by the
highest level in KOSTT the aim of which is to ensure future Environment protection and
sustainable development.
The long term environmental planning will support the benefit and KOSTT development plan,
by aiming:
- Proper financial management, which directs a better environmental control
Therefore all operational parts that have impact in environment will be included in KOSTT,
controlling the costs and its impact in the overall budget.
In addition to this, the following elements shall be respected:
- Domestic legislation (environment, energy)
- EU Legislation (environment, energy)
- Technical codes in KOSTT
- International standards and norms etc.
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 137 of 138
Office: Long-term Planning and Development
More needs to be done to improve and update of the new technologies and in improvement of
the infrastructure of the operation system (SCADA) and transmission system (construction of
the double and triple lines. The world has advanced much in terms of environment, and we
have to progress in achieving the required and targeted goals.
REFERENCES
The following are references made on published studies and reports:
[1]Transmission Development Plan 2012-2021 /KOSTT
[2] Long term energy balance 2013-2020/KOSTT (proposed)
[3] Generation Adequacy Plan 2013-2020/KOSTT (proposed)
[4] List of new Transmission Capacities 2011-2020/KOSTT
[5] Grid Code – second edition /KOSTT
[6] Electrical Equipment Code/KOSTT
[7] Transmission Connection Charging Methodology /KOSTT
[8] Transmission System Security and Planning Standards/KOSTT
[9] Operating Security Standards/KOSTT
[10] Electrical Standard Code/KOSTT
[11]. Distribution Code/KOSTT-KEK
[12] ESTAP II: Feasibility Study for the Kosova – Albania 400 kV Transmission
Interconnection Project (CESI, September 2005), World Bank Grant #H048
[13] ENTSO-E (UCTE) Operation Handbook, Last Edition
[14]Energy strategy of Kosovo 2009-2018
[15] “Transmission Network Expansion Project” FICHNER
[16] International Standard ISO 14001: 2004
[17] Many domestic and EU environmental laws
(The end of document)
TRANSMISSION DEVELOPMENT PLAN
DT-PA-001
ver. 0. 2 page 138 of 138
Office: Long-term Planning and Development
Prepared Controled ISO 9001
Approved
Name and surname
Gazmend Kabashi Safete Orana Kadri Kadriu
subscription
Data 31. 10. 2012