transmission coordination and planning committee 2014 q1 stakeholder meeting

18
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Upload: howe

Post on 23-Jan-2016

47 views

Category:

Documents


0 download

DESCRIPTION

Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting. March 26, 2014. Agenda. Introductions Background Transmission Planning Process 2014 TCPC Study Scope Stakeholder Input and Questions. Energy Delivery 101. Meeting Objectives. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

March 26, 2014

Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Page 2: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

• Introductions• Background• Transmission Planning Process• 2014 TCPC Study Scope• Stakeholder Input and Questions

Agenda

3/26/2014 2

Page 3: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Energy Delivery 101

33/26/2014

Page 4: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Meeting Objectives• Plan the expansion of the transmission system to ensure

reliable, efficient delivery of energy to customers at a reasonable cost.

• Develop and coordinate plans with interested stakeholders at the local, state, and regional level to identify and address concerns in the early stages of project development.

• Ensure openness and transparency while addressing applicable regulatory requirements.

43/26/2014

Page 5: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Transmission Planning

53/26/2014

Page 6: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

What is Transmission Planning?

The process of evaluating the transmission system to identify transmission facilities required to deliver existing and future generating resources to existing and future customer loads while balancing reliability, societal impact and cost.

3/26/2014 6

Page 7: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Types of Planning Studies

• System Interconnection Requestso Generator, Load or Transmission Interconnection

• Feasibility Study• System Impact Study• Facilities Study

• Transmission Service Study

• Reliability Study

• Economic Study

73/26/2014

Page 8: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Transmission Planning Process

Major factors in the process:• Future planning periods (5, 10, 20+ years)• Load forecasts (existing + future growth scenarios)• Generation output (serve local load vs. off-system sales)• Generation types (thermal, hydro, wind, solar, etc.)• Planned projects (local and regional)• System disturbances (consider all relevant outages)• Reliability criteria (the measuring stick for adequate

transmission system performance)• Transmission system commitments (capacity

availability)• Local, state, and federal regulatory requirements

83/26/2014

Page 9: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

9

Transmission Planning Groups

Transmission Coordination & Planning Committee (local)ohttp://www.oasis.oati.com/CLPT/index.html

oSelect “Transmission Planning” folder

Colorado Coordinated Planning Group (sub-regional)owww.westconnect.com/planning_ccpg.php

WestConnect (regional)owww.westconnect.com/planning.php

3/26/2014

Page 10: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Transmission Planning Process

103/26/2014

Page 11: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Multi-Year Transmission PlanPROJECT ESTIMATE

D ISDSTATUS

South Cheyenne 115 kV Substation 2014 Planned

North Range 115 kV Substation 2013 In-Service

North Range 115 kV Transmission Line 2013 In-Service

Corlett-South Cheyenne 115 kV Line 2014 Planned

Swan Ranch 115 kV Substation 2014 Planned

North Range-Swan Ranch-South Cheyenne 115 kV Circuit

2014 Planned

Cheyenne Prairie Generation Interconnection 2014 Planned

Data Center 115 kV Substation and Transmission

2015 Planned

Second South Cheyenne 230/115 kV Transformer

2015 Planned

113/26/2014

Page 12: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

CLFP Transmission Plan

123/26/2014

Page 13: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

2014 Study Scope: 5 and 10-Year

Scenarios• 2019 Heavy Winter Load

o Power flow, transient stability, voltage stability

• 2019 Light Winter Loado High Renewable Generation Outputo Power flow, transient stability, voltage stability

• 2025 Heavy Summer Loado Power flow (transient stability as needed)

• 10-year off-peak case undecided at this time

133/26/2014

Page 14: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Data Collection

• Requested data due: Friday April 11, 2014

• Peak and Off-Peak Load Data by PODo Monthly demand data for study years is criticalo Monthly demand for 10 year planning horizon is

preferred

• Resource Datao Demand requirement + reserves

• Reservation Datao Forecasted monthly transfer values on a per path

basis, including rollover rights

143/26/2014

Page 15: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Requesting Scenarios and Alternatives

• Use CCPG Request Form at any time

• Ensures all stakeholder suggestions are

considered

• Form will be submitted to CCPG and directed to the appropriate group

• All requests will be acknowledged and responded

to

• www.westconnect.com/filestorage/ccpg_request_form.xls

153/26/2014

Page 16: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Next Meetings• Q2 Meeting: May 15, 2014 2:30-3:30 p.m.

o Review stakeholder comments following Q1 meeting, submitted data, planned project status, other regional planning updates

• Q3 Meeting: August 21, 2014 9:30-11:00 a.m.o Review stakeholder comments following Q2 meeting, study

results, identified solutions and alternatives, planned project status, other regional planning updates

• Q4 Meeting: November 20, 2014 9:30-11:00 a.m.o Review final comments to draft LTP report, preferred project

alternatives, planned project status, other regional planning updates

• Additional stakeholder discussions may be held as necessary

163/26/2014

Page 17: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

Wes Wingen, PE

Manager of Transmission Planning

[email protected]

(605) 721-2268

Dan Baye

Transmission Planning Engineer

[email protected]

(605) 721-2471

Questions?

3/26/2014 17

Page 18: Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting

List of Acronyms• CCPG = Colorado Coordinated Planning Group• CPCN= Certificate of Public Convenience and Necessity• FERC = Federal Energy Regulatory Commission• KV = Kilovolt (1,000 volts)• LTP = Local Transmission Plan• MW = Megawatts (millions of watts)• NERC = North American Electric Regulatory Corporation• OASIS = Open Access Same-time Information System• POD = Point of Delivery• TCPC = Transmission Coordination & Planning

Committee• WECC = Western Electricity Coordinating Council

183/26/2014