transmission arrangements for distributed generation dcmf 9 april 2008 pre consultation document
DESCRIPTION
Pre-consultation document Transmission charging Current arrangements do not reflect the transmission investment costs incurred as a result of generation connecting to the distribution networks ‘Embedded benefit’ of ~£18/kW provides additional incentives for generation to embed ‘Actual’ embedded benefit estimated to be ~£7.50/kW Demand savings ~£5.75/kW Generation connection savings ~£1.50/kW Commoditisation of the residual element would not reduce the embedded benefit for average load plantTRANSCRIPT
Transmission arrangements for distributed generation
DCMF9 April 2008
Pre consultation document
Pre-consultation documentIssues associated with DG
Transmission charging arrangements do not provide a level playing field for transmission and distribution connected generation in terms of cost-reflectivity
Access arrangements do not provide a level playing field in terms of access allocation as DG “jumps the queue”
No contractual framework for exporting GSP’s
DG not directly visible to NGET causing difficulties in Investment planning Demand forecasting Outage and fault level planning
Pre-consultation documentTransmission charging
Current arrangements do not reflect the transmission investment costs incurred as a result of generation connecting to the distribution networks
‘Embedded benefit’ of ~£18/kW provides additional incentives for generation to embed
‘Actual’ embedded benefit estimated to be ~£7.50/kW Demand savings ~£5.75/kW Generation connection savings ~£1.50/kW
Commoditisation of the residual element would not reduce the embedded benefit for average load plant
Pre-consultation documentProposals
CUSC modification regarding thresholds associated with a request for a Statement of Works by the DNO (CAP097) shortly
Inviting views regarding second CUSC modification to introduce a new entry product for exporting GSP’s
Presenting two competing potential enduring solutions for industry comment
GNSAM strawman Net DNO Agency Model strawman
Pre-consultation documentGNSAM (1)
GBSO
CVA Registered Embedded Generator
Pays TNUoS generation tariff directly to National Grid, minus
a cost reflective discount for explicit access rights
SVA Registered Embedded Generator
Distribution Network
Operators
Contract with the DNO for connection
Contract with the DNO for connection
Supplier
Pays supplier TNUoS generation tariff minus cost reflective discount for implicit access rights
Responsible for SVA generator output and pays
TNUoS generation tariff minus discount on behalf of SVA registered generator
Pre-consultation documentNet DNO Agency Model (1)
Transmission
Generator
Books and pays for TEC + short-term products
Directly connected
demand
Books and pays for TOC + short-term
access products via supplier
Distribution Network
OperatorsSupplier
Embedded Generator
Books and pays for TEC/TOC + short-term products
(overrun, sharing. Non-obligated release, short-term
demand product)
Notify demand requirement and
pay for TOC
Notify requirement and pay for TEC
Supplier
Pre-consultation documentNext steps
Pre-consultation expected to be published mid-April for a six weeks consultation period
Proposing modification to existing CAP097 thresholds Inviting views on:
GNSAM and Net DNO Agency Models presented as potential enduring solutions, in consideration of TAR
Appropriateness of developing an entry product for exporting GSPs at this time, given that this is a step in the direction of a Net DNO Agency model