training report at pgcil hvdc ss

Upload: kunik-swaroop

Post on 03-Jun-2018

264 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    1/49

    SUMMER TRAINING

    1

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    2/49

    ACKNOWLEDGEMENT

    2

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    3/49

    EXECUTIVE SUMMARY

    Electric power transmission was originally developed with direct current. The availability

    of transformers and the development and improvement of induction motors at the

    beginning of the 20thCentury, led to greater appeal and use of a.c. transmission. But, later

    realized .c. transmission is more practical when long distances were to be covered or where

    cables were re!uired.

    The purpose of this study is to e"amine the #$C systems % understand the transmission

    system for transmitting huge chun& of power to various remote locations where generation is

    not feasible. This study also provides various theories regarding #$C systems and it also

    covers the pivotal role played by PGCIL in handling #$C systems in 'ndia.

    (ther )spects such as Transmission *lanning Criteria is also included which is basic

    re!uirement of any #$C *ro+ect carried out by *C'- in 'ndia. 't covers various factors such

    as *ower e!uirement, Type of Conductor, -ine -imit, Tariff, % etc. which are necessary to

    understand beforehand installing any #$C system. #$C system/s protection e.g. lightning

    stri&e1 % human safety measure are briefly discussed .

    3

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    4/49

    Table of ContentsABOUT PGCIL.........................................................................................................5

    'ntroduction.................................................................................................................(b+ectives....................................................................................................................

    Establishment of Transmission 3ystem.......................................................................41 ABOUT HVDC..............................................................................9

    'ntroduction: ..95.5 )$)6T)E3 ($E )C ................................................................................50

    5.2. -'7'T)T'(63888........................................................................................55

    2A HVDC BIPOLE CONVERTER............................................................................122.5. C(7*(6E6T3.........................................................................................................52

    9THE THEORY OF CONVERTERS HVDC............................................... 88..........5

    9.5 C(6$ET( C(6T(-..................................................................................................5

    9.2 C(77:T)T'(6 *(CE33.............................................................................................549.9 #$C C(6;':)T'(63..............................................................................................549.< C(6$ET(3 )**-'C)T'(63......................................................................................20

    ! TRANSMISSION PLANNING CRITERIA..............................................................................25

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    5/49

    POWER GRID CORPORATION OF INDIA LIMITED "HISTORY#:$

    I%&'()*+&,(%:

    P(-' G',) C('/('0&,(% ( I%),0 L,,&)POWERGRID3Founded 23 October 19921 is a

    6avratna state?owned electric utility company head!uartered in urgaon, 'ndia. *owerrid was

    incorporated on (ctober 29, 5A@A under the companies )ct, 5A> as the 6ational *ower

    Transmission Corporation -imited, with the responsibility of planning, e"ecuting, owning

    operating and maintaining the high voltage transmission systems in the country. The total

    revenue of company is 4,09.@ crore 200A1 with net income 2,0

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    6/49

    ischarge all functions of planning and coordination relating to 'nter?3tate Transmission

    3ystem with?

    o 3tate Transmission :tilities

    o Central overnment

    o 3tate overnment

    o enerating Companies

    o egional Electricity Boards

    o )uthority

    o -icensees

    o Transmission -icensees

    o )ny other person notified by the Central overnment on this behalf.

    E"ercise supervision and control over the 'nter?3tate Transmission 3ystem.

    Efficient (peration and 7aintenance of Transmission 3ystems.

    EstablishFaugment and operate all egional -oad ispatch Centers and Communication

    facilities.

    To facilitate private sector participation on Transmission system through 'ndependent

    *rivate Transmission Company, Goint $entures.

    To assist various 3EBs and other utilities in up gradation of s&ills % sharing of e"pertise

    by organizing regular conferences, tailor?made training wor&shops directed towards

    specific technological and (%7 areas and e"tending laboratory facilities for testing

    purposes etc.

    6

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    7/49

    estoring power in !uic&est possible time in the event of any natural disasters li&e super?

    cyclone, flood etc. through deployment of Emergency estoration 3ystems.

    D4(/%&04 S&0;:

    The phased development of *(HE' at the time of its formation was foreseen as followsI

    *hase?'I Transfer of Transmission facilities along with related manpower from Central F

    CentreJ3tate Goint $enture (rganizations.

    *hase?''I Transfer of e"isting egional Electricity Boards and egional -oad ispatch

    Centers together with associated communication facilities.

    *hase?'''I Establish *ower *ool to facilitate e"change of power between 3tatesFegionsleading to formation of 6ational *ower rid.

    E&074,,000 &m now.

    There are regional gridsI

    6orthern egionI

    7

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    8/49

    elhi, #aryana, #imachal *radesh, Gammu )nd Kashmir, *un+ab, a+asthan

    :ttaranchal and :ttar *radesh

    Eastern egionI

    Bihar, Ghar&hand, (rissa 3i&&im and Hest Bengal.

    Hestern egionI

    adra and 6agar #aveli, aman and iu, Chhattisgarh, oa u+arat, 7adhya *radesh

    and 7aharashtra.

    3outhern egionI

    )ndhra *radesh, Karnata&a, Kerala, *ondicherry and Tamil 6adu.

    6orth?Eastern egionI

    )runachal *radesh, )ssam, 7anipur, 7eghalaya, 7izoram, 6agaland and Tripura

    *(HE'/s networ&, as at 3eptember, 200@, comprises of over >A,000 circuit &m of high

    voltage transmission lines and 55> sub?stations spread across the country. The inter?regional

    power transfer capacity of 6ational rid has been enhanced to about 54,000 7H from 5

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    9/49

    H,;< V(4&0; D,'+& C*''%& "HVDC#

    I%&'()*+&,(%

    ) 2==? 2==@

    T'0%,,(% %&-(' "+& # 0,4>,@00

    S*7&0&,(% "%*7'# @ A9 50< 552

    T'0%('0&,(% C0/0+,&6 "MVA#

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    10/49

    proportional to the s!uare of the current. #owever, power is also proportional to voltage, so for

    a given power level, higher voltage can be traded off for lower current. Thus, the higher the

    voltage, the lower the power loss. *ower loss can also be reduced by reducing resistance,

    commonly achieved by increasing the diameter of the conductor but larger conductors are

    heavier and more e"pensive.

    #igh voltages cannot be easily used in lighting and motors, and so transmission?level voltage

    must be reduced to values compatible with end?use e!uipment. The transformer, which only

    wor&s with alternating current, is an efficient way to change voltages. *ractical manipulation of

    C voltages only became possible with the development of high power electronic devices such

    as mercury arc valves and later semiconductor devices, such as thyristors, insulated?gate bipolar

    transistors 'BTs1, high power capable 7(3;ETs power metalJo"ideJsemiconductor field?

    effect transistors1 and gate turn?off thyristors T(s1

    A)0%&0; 0%) L,,&0&,(% ( 04&'%0&,%; +*''%& &'0%,,(%

    The advantage of #$C is the ability to transmit large amounts of power over long distances

    with lower capital costs and with lower losses than )C. epending on voltage level and

    construction details, losses are !uoted as about 9 per 5,000 &m. #igh?voltage direct currenttransmission allows efficient use of energy sources remote from load centers.

    'n a number of applications #$C is more effective than )C transmission. E"amples includeI

    :ndersea cables, where high capacitance causes additional )C losses.

    Endpoint?to?endpoint long?haul bul& power transmission without intermediate LtapsL, for

    e"ample, in remote areas

    'ncreasing the capacity of an e"isting power grid in situations where additional wires are

    difficult or e"pensive to install *ower transmission and stabilization between unsynchronised )C distribution systems

    Connecting a remote generating plant to the distribution grid

    3tabilizing a predominantly )C power?grid, without increasing prospective short circuit

    current

    10

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    11/49

    educing line cost. #$C needs fewer conductors as there is no need to support multiple

    phases. )lso, thinner conductors can be used since #$C does not suffer from the s&in

    effect

    ;acilitate power transmission between different countries that use )C at differing

    voltages andFor fre!uencies 3ynchronize )C produced by renewable energy sources

    -ong undersea cables have a high capacitance. Hhile this has minimal effect for C

    transmission, the current re!uired to charge and discharge the capacitance of the cable causes

    additional '2 power losses when the cable is carrying )C. 'n addition, )C power is lost

    to dielectric losses.

    #$C can carry more power per conductor, because for a given power rating the constant

    voltage in a C line is lower than the pea& voltage in an )C line. 'n )C power, the root means!uare 731 voltage measurement is considered the standard, but 73 is only about 45 of

    the pea& voltage. The pea& voltage of )C determines the actual insulation thic&ness and

    conductor spacing. Because C operates at a constant ma"imum voltage without 73, this

    allows e"isting transmission line corridors with e!ually sized conductors and insulation to carry

    2A more power into an area of high power consumption than )C, which can lower costs.

    Because #$C allows power transmission between unsynchronised )C distribution systems, it

    can help increase system stability, by preventing cascading failure from propagating from one

    part of a wider power transmission grid to another. Changes in load that would cause portions of

    an )C networ& to become unsynchronized and separate would not similarly affect a C lin&,

    and the power flow through the C lin& would tend to stabilize the )C networ&. The magnitude

    and direction of power flow through a C lin& can be directly commanded, and changed as

    needed to support the )C networ&s at either end of the C lin&. This has caused many power

    system operators to contemplate wider use of #$C technology for its stability benefits alone

    D,0)0%&0;

    The disadvantages of #$C are in conversion, switching and control. ;urther operating an#$C scheme re!uires &eeping many spare parts, which may be used e"clusively in one

    system as #$C systems are less standardized than )C systems and the used technology

    changes fast.

    The re!uired static inverter are e"pensive and have limited overload capacity. )t smaller

    transmission distances the losses in the static inverters may be bigger than in an )C

    11

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    12/49

    transmission line. The cost of the inverters may not be offset by reductions in line construction

    cost and lower line loss.

    'n contrast to )C systems, realizing multiterminal systems is comple", as is e"panding e"isting

    schemes to multiterminal systems. Controlling power flow in a multiterminal C system

    re!uires good communication between all the terminals power flow must be actively regulated

    by the control system instead of by the inherent properties of the transmission line. #igh

    voltage C circuit brea&ers are difficult to build because some mechanism must be included in

    the circuit brea&er to force current to zero, otherwise arcing and contact wear would be too great

    to allow reliable switching. 7ulti?terminal lines are rare

    C(& (

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    13/49

    in order to provide the necessary bloc&ing voltage capability.Thyristors used for #$C valves

    are amongst the largest semiconductors of any type produced for

    any industry. ;igure shows an @. &$ thyristor with an active silicon diameter of 55 mm

    whichstarts life as a silicon ingot of 52 mm diameter, hence such thyristors are often referred

    to as52 mmD thyristors1.

    3uch components are e"pensive and there may be many thousand such components in a #$Cstation. 7oreover, they are !uite delicate and re!uire a great many additional components to

    control.

    2. Convertor Transforer: The converter transformer is the interface betweenthe )C system and the thyristor valves. Typically the #$C converter transformer issub+ected to a C voltage insulation stress as well as the )C voltage stress normally

    e"periencedby a power transformer. it is important that the converter transformer be

    thermally designed to ta&e into consideration both the fundamental fre!uency load and

    the )C harmonic currents that will flow from the converter through the converter

    transformer to the )C harmonic filters.

    !.AC ,4&': The )C harmonic filters are typically composed of a high voltageconnected capacitor ban& in series with a medium voltage circuit comprizing air?cored

    air?insulated reactors, resistors and capacitor ban&s. These filters are used to limit theimpact of )C harmonics and reactive power generated by Convertors .

    ".S((&

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    14/49

    a. Po%er Contro&: If the power demand is chaned then the power order wi!! ramp to the new

    power transfer !e"e! at a rate of chane #$nown as the %ramp rate&' pre(se!ected b) the operator* +)pica!!)

    the ma,imum power !imit is defined b) an o"er!oad contro!!er which is continuous!) ca!cu!atin the

    therma! capabi!it) of the con"erter station e-uipment*

    b. 're()en*y Contro&: . / scheme can contro! the . fre-uenc) of an . s)stem b)

    automatica!!) adustin the power bein de!i"ered into that . s)stem in order to ba!ance the !oad with the

    supp!)* +he fast power contro! b) the / reduces the under(fre-uenc) or o"er(fre-uenc) which can

    resu!t from a chanin !oad in a sma!! power s)stem such as an is!and !oad*

    c. Prote*tion: a #$C converter station the types of protection utilized fall into

    two categories

    M Conventional )C1 substation protection

    M C protection

    )C connected e!uipment such as converter transformers and )C harmonic filter

    components, along with feeders and busbars, are protected using conventional )C protection

    relays. The converter, along with the C circuit, is protected using hardware and software.

    14

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    15/49

    +.DC fi&ters: Converter operation results in voltage harmonics being generated at theC

    terminals of the converter, that is, there are sinusoidal )C harmonic components superimposed

    on the C terminal voltage. This )C harmonic component of voltage will result in )C

    harmonic current flow in the C circuit and the field generated by this )C harmonic current

    flow can lin& with ad+acent conductors,such as open?wire telecommunication systems, and

    induce harmonic current flow in these other circuits. 'n a bac&?to?bac& scheme, these harmonics

    are contained within the valve hall with ade!uate shielding and, with a cable scheme,

    the cable screen typically provides ade!uate shielding. #owever, with open?wire C

    transmission it may be necessary to provide C filters to limit the amount of harmonic current

    flowing in the C line. The C filter is physically similar to an )C filter in that it is connected

    to the high voltage potential via a capacitor ban& other capacitors along with reactors and

    resistors are then connected to the high voltage capacitor ban& in order to provide the desired

    tuning and

    T

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    16/49

    T

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    17/49

    as the driving voltage. The lea&age inductances of phases 5 and 9 will be the reactances which

    determine the current. This is simply a phase to phase short circuit of the transformer. The short

    circuit current flows through valve 9 in the forward direction and through valve 5 counter to the

    forward direct current. )s soon as the short circuit current has achieved the amplitude of the

    direct current the composite current is zero1, valve 5 e"tinguishes. )t this point, thecommutation process has ended and valve 9 is carrying the entire direct current. Curve of the

    direct voltage during commutation is along the average value of the voltages of valves 5 and 9.

    C*''%& +(%&'(4

    Current control mainly determines

    3teady state transmission power

    Changes in transmission power according to size and rate of change

    The dynamic behavior of the system including temporary overload

    -imitation of transient overcurrents determined by amplitude and duration

    The loading of all essential components of an #$C system, with the e"ception of filter

    circuits, is determined by the direct current or an alternating current proportional to the direct

    current. Therefore current control is also a very essential protective function.

    'n #$C two point systems, the rectifier generally assumes the tas& of the current control. 't

    is occasionally advantageous to assign the current control function to the inverter. #owever,

    since the current control of the rectifier is needed as a proactive function, it is advantageous

    to also use it for this purpose during normal operation. Then it is always active and monitors

    itself.

    17

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    18/49

    HVDC C(%,;*'0&,(%

    M(%(/(4 0%) 0'&< '&*'%

    'n a common configuration, called monopole, one of the terminals of the rectifier is connected

    to earth ground. The other terminal, at a potential high above, or below, ground, is connected to

    a transmission line. The earthed terminal may or may not be connected to the corresponding

    connection at the inverting station by means of a second conductor.

    'f no metallic conductor is installed, current flows in the earth between the earth electrodes at

    the two stations. Therefore it is a type of single wire earth return. The issues surrounding earth?

    return current include

    Electrochemical corrosionof long buried metal ob+ects such as pipelines :nderwater earth?return electrodes in seawater may produce chlorine or otherwise affect

    water chemistry.

    )n unbalanced current path may result in a net magnetic field, which can affect magnetic

    navigational compasses for ships passing over an underwater cable.

    These effects can be eliminated with installation of a metallic return conductor between the two

    ends of the monopolar transmission line. 3ince one terminal of the converters is connected to

    earth, the return conductor need not be insulated for the full transmission voltage which ma&es

    it less costly than the high?voltage conductor.

    BIPOLAR

    'n bipolar transmission a pair of conductors is used, each at a high potential with respect to

    ground, in opposite polarity. 3ince these conductors must be insulated for the full voltage,

    18

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    19/49

    transmission line cost is higher than a monopole with a return conductor. #owever, there are a

    number of advantages to bipolar transmission which can ma&e it the attractive option.

    :nder normal load, negligible earth?current flows, as in the case of monopolar

    transmission with a metallic earth?return. This reduces earth return loss and environmentaleffects.

    Hhen a fault develops in a line, with earth return electrodes installed at each end of the

    line, appro"imately half the rated power can continue to flow using the earth as a return path

    operating in monopolar mode.

    3ince for a given total power rating each conductor of a bipolar line carries only half the

    current of monopolar lines, the cost of the second conductor is reduced compared to a

    monopolar line of the same rating.

    'n very adverse terrain, the second conductor may be carried on an independent set of

    transmission towers, so that some power may continue to be transmitted even if one line is

    damaged.

    ) bipolar system may also be installed with a metallic earth return conductor.

    Bipolar systems may carry as much as 9,200 7H at voltages of NF?>00 &$. 3ubmarine cable

    installations initially commissioned as a monopole may be upgraded with additional cables and

    operated as a Bipole.

    C('(%0 D,+

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    20/49

    considerable power loss, create audible and radio?fre!uency interference, generate to"ic

    compounds such as o"ides of nitrogen and ozone, and bring forth arcing.

    Both )C and C transmission lines can generate coronas, in the former case in the form of

    oscillating particles, in the latter a constant wind. ue to the space charge formed around the

    conductors, an #$C system may have about half the loss per unit length of a high voltage )C

    system carrying the same amount of power. Hith monopolar transmission the choice of polarity

    of the energised conductor leads to a degree of control over the corona discharge. 'n particular,

    the polarity of the ions emitted can be controlled, which may have an environmental impact

    on particulate condensation. *articles of different polarities have a different mean?free

    path.1 6egative coronas generate considerably more ozone than positive coronas, and generate it

    further downwind of the power line, creating the potential for health effects. The use of

    a positive voltage will reduce the ozone impacts of monopole #$C power lines.

    A//4,+0&,(%

    O',-

    The controllability of current?flow through #$C rectifiers and inverters, their application in

    connecting unsynchronized networ&s, and their applications in efficient submarine cables mean

    that #$C cables are often used at national boundaries for the e"change of power. (ffshore

    windfarms also re!uire undersea cables, and their turbines are unsynchronized.

    AC %&-(' ,%&'+(%%+&,(%

    )C transmission lines can only interconnect synchronized )C networ&s that oscillate at the

    same fre!uency and in phase. 7any areas that wish to share power have unsynchronized

    networ&s. #owever, #$C systems ma&e it possible to interconnect unsynchronized )C

    networ&s, and also add the possibility of controlling )C voltage and reactive power flow.

    ) generator connected to a long )C transmission line may become unstable and fall out of

    synchronization with a distant )C power system. )n #$C transmission lin& may ma&e it

    economically feasible to use remote generation sites. Hind farms located off?shore may use

    #$C systems to collect power from multiple unsynchronized generators for transmission to

    the shore by an underwater cable.

    20

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    21/49

    'n general, however, an #$C power line will interconnect two )C regions of the power?

    distribution grid. 7achinery to convert between )C and C power adds a considerable cost in

    power transmission. The conversion from )C to C is &nown as rectification and from C to

    )C as inversion. )bove a certain brea&?even distance about 0 &m for submarine cables, and

    perhaps >00J@00 &m for overhead cables1, the lower cost of the #$C electrical conductorsoutweighs the cost of the electronics.

    T'0%,,(% P40%%,%; C',&',0I%&'()*+&,(%

    The ob+ective of system planning is to evolve a power system with a level of performance

    characterised by an acceptable degree of ade!uacy and security based on a trade?off between

    costs and ris&s involved. 'nsofar as power transmission systems are concerned , there are nowidely adopted uniform guidelines which determine the criteria for transmission planning vis?s?

    vis acceptable degree of ade!uacy and security. The criteria generally depends on the factors

    such as availability of generation vis?O?vis demand, voltage levels, and configuration of the

    system, control and communication facilities and resource constraints. *ractices in this regard

    vary from country to country. The common theme in the various approaches is the acceptable

    system performanceD. Even though the factors affecting system performance are probabilistic in

    nature, deterministic approach has been used most commonly, being rather easy to apply. ;or

    adopting probabilistic approach, long operating e"perience and availability of reliable statistical

    data regarding performance of system components, namely e!uipment failure rate, outage

    duration, etc, are essential. 3uch data are presently being compiled by a few utilities but these

    are still inade!uate to go in for a totally probabilistic approach. #ence it is considered prudent

    to adopt a deterministic approach for the present with a committed thrust towards progressive

    adoption of probabilistic approach.

    21

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    22/49

    P40%%,%; P

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    23/49

    The choice shall be based on cost, reliability, right?of?way re!uirements, energy losses,

    down time in case of upgradation and reconductoring options1

    'n case of generating station close to a ma+or load centre, sensitivity of its complete

    closure with loads to be metto the e"tent possible1from other generating stations is also

    studied.

    'n case of transmission system associated with 6uclear *ower 3tations there shall be two

    independent sources of power supply for the purpose of providing start?up power

    facilities. ;urther the angle between start?up power source and the 6** switchyard

    should be, as far as possible, maintained within 50 degrees.

    The evacuation system for sensitive power stations viz., 6uclear power stations shall

    generally be planned so as to terminate it at large load centres to facilitate islanding of the

    power station in case of contingency.

    Contingency is the temporary removal of one or more system elements from service. The

    cause or reason for such removal may be a fault , planned maintenanceFrepair etc.

    5. 3ingle Contingency J The contingency arising out of removal of one system element

    from service.

    2. ouble Contingency J The contingency arising out of removal of two system elements

    from service. 't includes a FC line, two 3FC lines in same corridor or different corridors,

    a 3FC line and a transformer etc.

    9. are Contingency J Temporary removal of complete generating station or complete sub?

    station including all the incoming % outgoing feeders and transformers 1 from service,

    #$C bipole and stuc& brea&er condition.

    Hhere only two circuits are planned for evacuation of power from a generating station,

    these should be two single lines instead of a double circuit line.

    eactive power flow through 'CTs shall be minimal. 6ormally it shall not e"ceed 50 of

    the rating of the 'CTs. Hhenever voltage on #$ side of 'CT is less than 0.A4 pu, no

    reactive power shall flow through 'CT.

    23

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    24/49

    ThermalF6uclear enerating units shall normally not run at leading power factor.

    #owever, for the purpose of charging, generating unit may be allowed to operate at

    leading power factor as per the respective capability curve.

    'nter?regional lin&s shall, in the present conte"t, be planned as asynchronous ties unless

    otherwise permitted from operational consideration.

    L(0) G%'0&,(% S+%0',(

    The load?generation scenarios shall be wor&ed out so as to reflect in a pragmatic manner the

    daily and seasonal variations in the load demand and generation availability.

    L(0) )0%)

    The profile of annual and daily demands will be determined from past data. These data willusually give the demand at grid supply points and for the whole system identifying the

    annual and daily pea& demand.

    A+&, /(-'

    The system pea& demands shall be based on the latest reports of Electric *ower 3urvey

    E*31 Committee. 'n case these pea& load figures are more than the pea&ing availability, theloads will be suitably ad+usted substation wise to match with the availability.

    The load demands at other periods seasonal variations and minimum loads1shall be derived

    based on the annual pea& demand and past pattern of load variations.

    ;rom practical considerations the load variations over the year shall be considered as underI?

    5. )nnual *ea& -oad J 't is the simultaneous ma"imum demand of the system being

    studied. 't is based on latest Electric *ower 3urvey E*31 or total pea&ing power

    availability, whichever is less.

    2. 3easonal variation in *ea& loadscorresponding to high thermal and high hydro

    generation1

    24

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    25/49

    9. 7inimal load J 't is the e"pected minimum system demand and is determined from

    average ration of annual pea& load and minimum load observed in the system for the last

    years.

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    26/49

    units. 'n case of nuclear units the minimum level of output shall be ta&en as not less than 40

    of the rated capacity.

    eneration dispatches corresponding to the following operating conditions shall be considered

    depending on the nature and characteristics of the system.

    )nnual *ea& -oad

    7a"imum Thermal generation J 't is the condition when hydro generation is lownot

    necessarily minimum1and thermal generation is &ept ma"imum to meet seasonal pea&

    loadsnot necessarily annual pea& load1.'n other words it is the condition when the gap

    between monthly pea& demand and hydro power availability is ma"imum.

    7a"imum #ydro generation J 't is the condition when hydro power availability is

    ma"imum during the year. 't is also &nown as #igh #ydro condition.

    )nnual 7inimum -oad

    3pecial area dispatches J 't is the condition when power output from all the generating

    stations located in an area in close pro"imity1 is &ept at the ma"imum feasible level.

    7a"imum ;easible level of a generating station is the ma"imum power output when all

    the units in a power station are in service, assuming no planned or forced outages.

    #owever, in case of power stationFcomple" where si" or more units e"ist, for every si"

    units one unit Jsecond largest?is assumed to be under annual planned maintenance.

    3pecial dispatches corresponding to high agricultural load with low power factor,

    wherever applicable.

    (ff pea& conditions with ma"imum pumping load where *umped 3torage stations e"ist

    and also with the inter?regional e"changes, if envisaged.

    Complete closure of a generating station close to a ma+or load centre.

    The generation dispatch for purpose of carrying out sensitivity studies corresponding to

    complete closure of generating station close to a ma+or load centre shall be wor&ed out by

    increasing generation at other stations to the e"tent possible &eeping in view the

    ma"imum li&ely availability at these stations, ownership pattern, shares etc.

    26

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    27/49

    P',,74 L,% L(0),%; L,,&

    *ermissible line loading limit depend on many factors such as voltage regulation, stabilityand thermal capacity etc. Thermal capacity of a line refers to the amount of current that

    can be carried by a line conductor without e"ceeding its design operating temperature.

    3urge 'mpedance -oading 3'-1 means a unit power factor load over a resistance line

    such that series reactive loss 'P2Q1 along the line is e!ual to shunt capacitive gain

    $P2Q=1. :nder these conditions the sending end and receiving end voltages and current

    are e!ual in magnitude but different in phase position. Hhile 3'- gives a general idea of

    the loading capability of the line , it is usual to load the short lines above 3'- and long

    lines lower than 3'- because of the stability limitations1.line loading can also be shown

    in terms of surge impedance loading of uncompensated line1as a function of line length

    assuming a voltage regulation of and phase angular difference of 90 degrees between

    the two ends of the line. 'n case of shunt compensated lines, the 3'- will get reduced by a

    factor &, where

    & R s!rt 5?degree of compensation1

    ;or lines whose permissible line loading as determined from the curve is higher than the

    thermal loading limit, permissible loading limit shall be restricted to thermal loading

    limit.

    Thermal loading limits are generally decided by design practice on the basis of ambient

    temperature, ma"imum permissible conductor temperature, wind velocity, etc. 'n 'ndia,

    the ambient temperatures obtaining in the various parts of the country are different and

    vary considerably during the various seasons of the year. esigns of transmission line

    with )3C conductors in E#$ systems will normally be based on a conductortemperature limit of 4 deg Celsius. #owever, for some of the e"isting lines which have

    been designed for a conductor temperature of > deg Celsius the loading shall be

    correspondingly reduced. 'n the case of )))C conductors, ma"imum conductor

    temperature limit will be ta&en as @ deg Celsius.

    27

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    28/49

    T/('0'6 O'(4&0;

    These are power fre!uency overvoltages produced in a power system due to sudden load

    re+ection, single?phase?to?ground faults etc.

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    29/49

    be such that under steady state condition, switching on and off of the reactors shall not

    cause a voltage change e"ceeding . The standard sizes7$)1 of reactors areI?

    9 % @0 at &v 5?ph units1 0, >9 % 550 at @00 &$

    ;i"ed line reactors may be provided to control Temporary *ower ;re!uency overvoltage

    Safter all voltage regulation has ta&en place within the limits defined, under all probable

    operating conditions.

    -ine reactors switchableFcontrolledFfi"ed1 may be provided if it is not possible to chargeE#$ line without e"ceeding the voltage limits defined. The possibility of reducing pre?

    charging voltage of the charging end shall also be considered in the conte"t of

    establishing the need for reactors.

    S&0&,+ VAR C(/%0&,(% "SVC#

    3tatic $) compensation shall be provided where found necessary to damp the powerswings and provide the system stability under conditions defined. The dynamic range of

    static compensators shall not be utilised under steady state operating conditions as far as

    possible.

    S*7$S&0&,(% P40%%,%; C',&',0 The re!uirements in respect of E#$ sub?stations in a system such as the total load to be

    catered by the sub?station of a particular voltage level, its 7$) capacity, number of

    feeders permissible etc. are important to the planners so as to provide an idea to them

    about the time for going in for the adoption of ne"t higher voltage level sub?station and

    also the number of substations re!uired for meeting a particular !uantum of load.

    29

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    30/49

    Keeping these in view the following criteria have been laid down for planning an E#$

    substationI

    The ma"imum fault level on any new substation bus should not e"ceed @0 of the rated

    rupturing capacity of the circuit brea&er. The 20 margin is intended to ta&e care of the

    increase in short?circuit levels as the system grows. The rated brea&ing current capability

    of switchgear at different voltage levels may be ta&en asI?

    592 &$ ?? 2F95 &)

    220 &$ ?? 95.F

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    31/49

    ) stuc& brea&er condition shall not cause disruption of more than four feeders for 220

    &$ system and two feeders for &$ systems.

    T'0%,,(% E%;,%',%;

    M08(' C(/(%%& ( T'0%,,(% L,%

    Conductor

    Tower esign and foundation

    Earth wire

    'nsulators

    31

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    32/49

    #ardware ;ittings

    )ccessories

    CONDUCTORS

    BUNDLE CONDUCTOR SELECTION AND OPTIMIATION

    3ize, Type and Configuration of conductor influencesI?

    Tower and its geometry

    ;oundations

    (ptimum spans

    ating and configuration of 'nsulator string

    'nsulator 3wings

    round clearance

    -ine interferences li&e electric field at ground, corona, radio % T$ interference, audible

    noise etc.

    CONDUCTOR SELECTION SCENARIO

    32

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    33/49

    SCENARIO A

    3election of character for a transmission line of identified voltage level and specified

    minimum power flow but power flow capacity becomes ruling factor in selection ofconductor size low voltage lines1.

    SCENARIO B

    3election of conductor for a transmission line with identified voltage level and a specified

    minimum power flow but voltage level become ruling factor in selection of

    conductorFconductor bundle size E#$F:#$ lines1.

    SCENARIO C

    3election of conductor for high power capacity long distances transmission lines where

    selection of voltage level and conductorFconductor bundle size are to be done together to

    obtain most optimum solution #$C Bipole1

    CONDUCTOR BUNDLE SELECTION METHODOLOGY

    *rimary set of conductor bundleFsizes identified to start optimization

    *arameters li&e insulation re!uirement, limits for corona, '$, )6, thermal ratings, line

    losses and statutory clearances identified

    33

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    34/49

    etailed analysis of various alternatives in respect of following to be carried out to select

    the configuration

    ( Basic insulation design and insulator selection

    ( Tower configuration analysis

    ( Tower weight and foundation analysis

    ( Capital line cost analysis and span optimization

    ( -ine loss calculation

    ( Economic evaluations*H1 of alternatives

    ( Comparison of interference performance( Cost sensitivity analysis

    CONDUCTOR OPTMIATION PROCEDURE

    *'7)= 3E-ECT'(6

    Thermal rating of the conductorFconductors

    7anufacturing facilities

    E"pense of other utilities

    3ystem voltage alternatives

    Construction convenience

    -ine loss considerations

    Terrain conditions and ground profile

    3pan length re!uirements

    34

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    35/49

    ight (f Hay limitations

    CONDUCTOR SELECTION DESIGN CONSIDERATIONS

    B)3'C C(63'E)T'(63 6(6 $)')B-E1

    51 -oading condition and reliability level for the transmission line.

    21 'nsulator co?ordination

    91 -imit load condition for structure, conductor, insulator, and hardware as well as limit

    conditions for swing of conductor and insulator strings.

    1 *arameters for economic evaluation

    CONDUCTOR SELECTION FOR SPECIAL TRANSMISSION SYSTEM

    35

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    36/49

    :*)T'6 (; -'6E3

    ( 3ag of the selected conductor at ma"imum operating temperature should not e"ceed

    the sag of the original conductor

    ( 6o e"tra loadings on the structure at various design considerations

    :*)'6 (; -'6E3

    ( -ine interference in respect of '$, T$', )6, E;, 7; etc. 3hould be within

    acceptable limits

    ( Conductor surface gradient within acceptable limits

    ( )symmetric bundle

    C(7*)CT -'6E3

    ( -owest possible sag and swing for re!uired !uantum of power

    ( Considerations involved in upgradingFup rating

    CONDUCTOR BUNDLE SELECTION: ESTIMATION OF TOWER

    WEIGHTS AND FOUNDATION VOLUMES

    ;or each alternative of conductor and insulator configuration

    T(HE HE'#T E3T'7)T'(6

    *reliminary tower design studies conducted

    36

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    37/49

    Estimation based on regression analysis and empirical formulae

    ;(:6)T'(6 $(-:7E E3T'7)T'(6

    *reliminary foundation design studies conducted

    C(6:CT( B:6-E (T'7'U)T'(6I TEC#6(?EC(6(7'C )6)-=3'3

    51 Capital cost of line

    Cost of each item, construction cost

    21 Cost of line losses

    )nnual loss cost R )nnual demand cost N )nnual energy -oss Cost

    91 esults of economic evaluation*H or )nnual Cost basis1

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    38/49

    )-- )-:7'6':7 )--(= C(6:CT( )))C

    ood Conductivity

    #igh Tensile 3trength

    3uperior Corrosion resistance compared to )C3

    'mproved strength to weight ratio resulting in lower sag

    -ower electrical losses

    )luminium Conductor 3teel 3upported )C33 Conductor1

    3imilar to )C3 e"cept )luminium

    3teel Core #igh 3trength1 carries most of the load and hence less sag compared to

    conventional )C3 conductor under emergency loadings.

    Can be operated at 200 degree C without loss of strength

    'mproved Conductivity

    Better self damping characteristics

    Compact Conductors

    )luminium wiresFstrands shaped trapezoidal

    'ncreased )luminium area and hence higher current carrying capacity

    38

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    39/49

    '6$) Conductors

    Core made of alloy of 'ron. 6ic&el having low thermal coefficient of e"pansion5F9rdthat

    of steel1

    )fter certain transition temperature all load transferred to the core and hence lower sagcompared to )C3 after transition temperature

    Can be operated up to 2000C

    DESIGN OF TOWERS

    SALIENT DESIGN CONDITIONS

    The reliability of transmission line towers depends on the appropriate selection of design

    criteriaFparameters.

    Climatic conditions play an important role in determining the reliability of transmission

    line tower.

    ) significant number of transmission line failures can be the result of wind speed

    e"ceeding design limits due to deficiencies in selection of design parametersFcriteria.

    EARTHWIRE

    ;unctions of Earth wire

    To protect conductor against lighting flashovers

    To provide a path for fault current

    39

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    40/49

    -ighting ;lashovers

    irect ;lashover

    (ccurs due to shielding failure with lighting on the conductor, flashover ta&ing place

    across the insulator string from conductor to ground.

    Bac& ;lashover

    (ccurs due to high towering resistance with a high voltage at the grounded tower cross

    arm compared to conductor, resulting in a flashover across the insulator string from

    ground to conductor.

    7a"imum allowable fault current '1 through earthwire mainly depends upon

    )rea of Earth wire)1

    7a"imum permissible temperature

    Time of short circuitt1

    ' varies proportional to ) and inversely proportional to s!rt t1

    HARDWARE FITTINGS AND ACCESSORIES FOR CONDUCTOR

    EARTHWIRE

    #)H)E ;'TT'63

    ;or attachment of insulator string to tower

    ?shac&les, Ball clevis, =o&e *late, Chain lin&

    ;or attachment of insulator string to the conductor

    40

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    41/49

    3uspension % tension assembly

    ;ittings li&e ?3hac&les, soc&et clevis, chain lin&

    ;or protection of insulator string from power follow current

    )rcing horn

    ;or ma&ing electric field uniform and to limit the electric field at live end

    Corona control ringFrading ring

    ;or fine ad+ustment of conductor sag ?3ag )d+ustment plate, Turn Buc&le

    #)H)E ;'TT'63? esign

    )rcing #orn

    The air gap is maintained for satisfactory performance under actual field conditions.

    ;or power follow current

    =o&e *late

    To withstand mechanical loads?Thic&ness % shear edge maintained

    To maintain sub conductor spacing

    Corona Control ingFrading #orn

    To cover at least one live and insulator disc

    To cover hardware fittings susceptible for CoronaF'$

    3uspension )ssembly

    ? 3haped to prevent hammering between clamp % conductor

    ? To minimize static % dynamic stress in conductor under various

    loading conditions

    ? 7inimum level of coronaF'$ performance

    41

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    42/49

    ? ;or slipping of conductor under prescribed unbalanced conditions

    between ad+acent conductor spans

    Tension )ssembly

    ( To withstand loads of atleast A of conductor :T3

    ( To have conductivity more than that of conductor

    3ag )d+ustment *lateFTurn Buc&le

    ( To ad+ust sag upto 50mm in steps of >mm.

    C(& E%;,%',%;

    W

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    43/49

    :ndergrounding is more e"pensive, since the cost of burying cables at transmission voltages is

    several times greater than overhead power lines, and the life?cycle cost of an underground

    power cable is two to four times the cost of an overhead power line.

    A7&'0+& +(& &,0&

    51 *reliminary 3urvey % 3oil 'nvestigation

    21 -and )c!uisition for 3ubstation and % Compensation

    91 Cost of compensation for transmission lines

    Compensation towards trees, crops % *TCC

    Compensation towards forest

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    44/49

    551 Custom uty

    521 'nterest uring Construction 'C1

    S*7&0&,(% E*,/%&

    51 '3 3ubstation E!uipment.

    21 Circuit Brea&ers

    91 'solators

    1 3urge )rrestersI They should be provided near line entrances, transformers so as to achieve

    proper insulation coordination. These shall be fitted with pressure relief devices and

    diverting ports suitable for shattering of porcelain housing providing path for the flow of

    rated currents in the event of arresters failure.

    S*7&0&,(% S*//('& 0+,4,&,

    51 )C % C *ower supplies

    21 ;ire ;ighting 3ystemI ;ire fighting system in general conforms to fire insurance regulations

    of 'ndia. The fire fighting system is proposed with both )C motor % diesel engine drivenpumps. )utomatic heat actuated emulsifying system is proposed for transformers and

    reactors.

    91 (il evacuating, filtering, testing, % filling apparatusI To monitor the !uality of oil for the

    satisfactory performance of transformers, shunt reactors and for periodical maintenance

    44

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    45/49

    necessary oil evacuating, filtering, testing and filling apparatus would be provided at new

    substations.

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    46/49

    wider geographic area. emote and low?cost sources of energy, such as hydroelectric power or

    mine?mouth coal, could be e"ploited to lower energy production cost.

    The capital cost of electric power stations is so high, and electric demand is so variable, that it is

    often cheaper to import some portion of the needed power than to generate it locally. Because

    nearby loads are often correlated, electricity must often come from distant sources. Because of

    the economics of load balancing, wide area transmission grids now span across countries and

    even large portions of continents. The web of interconnections between power producers and

    consumers ensures that power can flow, even if a few lin&s are inoperative.

    The unvarying or slowly varying over many hours1 portion of the electric demand is &nown as

    the Vbase loadV, and is generally served best by large facilities and therefore efficient due to

    economies of scale1 with low variable costs for fuel and operations, i.e. nuclear, coal, hydro.

    enewable sources such as solar, wind, oceanFtidal, etc. are not considered Vbase loadV but canstill add power to the grid. 3maller and higher cost sources, such as combined cycle or

    combustion turbine plants fueled by natural gas are then added as needed.

    -ong distance transmission allows remote renewable energy resources to be used to displace

    fossil fuel consumption. #ydro and wind sources canLt be moved closer to populous cities, and

    solar costs are lowest in remote areas where local power needs are minimal. Connection costs

    alone can determine whether any particular renewable alternative is economically sensible.

    Costs can be prohibitive for transmission lines, but various proposals for massive infrastructure

    investment in high capacity, very long distance super grid transmission networ&s could berecovered with modest usage fees.

    #igh voltage direct current #$C1 is used to transmit large amounts of power over long

    distances or for interconnections between asynchronous grids. Hhen electrical energy is

    re!uired to be transmitted over very long distances, it is more economical to transmit using

    direct current instead of alternating current. ;or a long transmission line, the lower losses and

    reduced construction cost of a C line can offset the additional cost of converter stations at each

    end. )lso, at high )C voltages, significant although economically acceptable1 amounts of

    energy are lost due to corona discharge, the capacitance between phases or, in the case of buried

    cables, between phases and the soil or water in which the cable is buried.

    46

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    47/49

    E%,'(%%&04 0%) S(+,04 A/+&

    F('& I%(4%& C40'0%+

    )s per the practice, preliminary route selection is done by *(HE' based on such

    documents as ;orest )tlas and the survey of 'ndia maps using beeD line method, followed

    by field verification through wal& over survey. )ll possible steps are ta&en to avoid the route

    alignment through the forests. 'n case where it becomes unavoidable due the geography of

    the terrain, the alignment is made in such a way that the route through forests is barest

    minimum.

    ;or the selection of optimum route, following points are to be ta&en into considerationI

    The route of the proposed transmission line does not involve any human rehabilitation

    )ny monument of cultural or historical importance is not generally affected.

    The route does not create any threat to the survival of the community.

    't does not affect any public utility services li&e playground , school, other

    establishments, etc

    't does not pass through any sanctuaries, national par&, etc.

    't does not infringe with the areas of natural resources.

    47

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    48/49

    S(+,04 I* RR 0*'

    )s per the prevailing law, land below transmission line is not re!uired to be ac!uired and

    only land for substation is ac!uired. *(HE' is following the practice of land

    management to minimize the land re!uirement to the barest minimum. enerally 20 to 90

    hectares of land is re!uired for constructing a substation depending upon the type of the

    voltage level. Even for this 20 to 90 hectare land, *(HE' try to locate the substation

    on government land as far as possible and in the absence of govt. land private land is

    ac!uired. 'n order to insure the indigenous Tribal1 people do not suffer adverse affects,

    utmost care is ta&en to avoid ac!uisition of land belonging to tribal community. 'n spite of

    that, *(HE' has developed an indigenous people Tribal1 evelopment *lan '**1

    which ensure that they receive culturally compatible social and economic benefits for any

    adverse affects.

    R, A%046,

    R%* R,

    The capital cost of the transmission system comprises of

    i1 )n e!uity component

    ii1 ) loan component

    This is recovered through the annual transmission charges consisting of return re!uired for

    the e!uity, an interest for the loan component together with the depreciation charges, the (

    % 7 charges and interest on wor&ing capital from the beneficiaries as per 6otification in

    proportion to the benefits derived by them. These are recovered in monthly fi"ed charges

    from the beneficiaries. 'n addition to annual charges 'ncome Ta", ;E$ and incentives, etc.

    as per notification would also be payable.

    The Bul& *ower Transmission )greement B*T)1 which cover the payments for

    transmission charges for all the e"isting pro+ects as well as those that may be included in

    future after approval by CE) already e"ists.

    48

  • 8/12/2019 Training Report at PGCIL HVDC Ss

    49/49

    R;*40&('6 R,

    B*T)s have the provision that the transmission tariff for new F e"isting transmission assets

    commissioned as well as the additional tariff payable due to additional capitalization fromyear to year, etc. shall be computed by *(HE' based on norms F methodology

    followed in the (' notification dated 5>.52.A4 in accordance with norms to be specified by

    the Central Electricity egulatory Commission CEC1 as amended from time to time.

    T0',

    The cost of electric power is normally given by the e"pression a N bQ&H N cQ&Hh1 per

    annum, where a is a fi"ed charge for the utility, independent of the power output b depends on

    the ma"imum demand of the system and hence on the interest and depreciation on the installed

    power station and c depends on the units produced and therefore on the fuel charges and the

    wages of the station staff.

    Tariff structure may be such as to influence the load curve and to improve the load factor.

    Tariff should consider the pf power factor1 of the load of the consumer. if it is low, it ta&es

    more current for the same &Hs and hence T and Transmission and istribution1 losses are

    correspondingly increased. The power has to install either pf correcting improvement1 devices

    such as synchronous condensors, 3$C 3tatic $ar Compensator1 or voltage regulating

    e!uipment to maintain the voltages within allowed limits and thus the total cost increases. (ne

    of the following alternatives may be used to avoid the low pf I

    5. To charge the consumer based on K$) rather than KH.

    2. ) pf penalty clause may be imposed on the consumer.