training report at pgcil hvdc ss
TRANSCRIPT
-
8/12/2019 Training Report at PGCIL HVDC Ss
1/49
SUMMER TRAINING
1
-
8/12/2019 Training Report at PGCIL HVDC Ss
2/49
ACKNOWLEDGEMENT
2
-
8/12/2019 Training Report at PGCIL HVDC Ss
3/49
EXECUTIVE SUMMARY
Electric power transmission was originally developed with direct current. The availability
of transformers and the development and improvement of induction motors at the
beginning of the 20thCentury, led to greater appeal and use of a.c. transmission. But, later
realized .c. transmission is more practical when long distances were to be covered or where
cables were re!uired.
The purpose of this study is to e"amine the #$C systems % understand the transmission
system for transmitting huge chun& of power to various remote locations where generation is
not feasible. This study also provides various theories regarding #$C systems and it also
covers the pivotal role played by PGCIL in handling #$C systems in 'ndia.
(ther )spects such as Transmission *lanning Criteria is also included which is basic
re!uirement of any #$C *ro+ect carried out by *C'- in 'ndia. 't covers various factors such
as *ower e!uirement, Type of Conductor, -ine -imit, Tariff, % etc. which are necessary to
understand beforehand installing any #$C system. #$C system/s protection e.g. lightning
stri&e1 % human safety measure are briefly discussed .
3
-
8/12/2019 Training Report at PGCIL HVDC Ss
4/49
Table of ContentsABOUT PGCIL.........................................................................................................5
'ntroduction.................................................................................................................(b+ectives....................................................................................................................
Establishment of Transmission 3ystem.......................................................................41 ABOUT HVDC..............................................................................9
'ntroduction: ..95.5 )$)6T)E3 ($E )C ................................................................................50
5.2. -'7'T)T'(63888........................................................................................55
2A HVDC BIPOLE CONVERTER............................................................................122.5. C(7*(6E6T3.........................................................................................................52
9THE THEORY OF CONVERTERS HVDC............................................... 88..........5
9.5 C(6$ET( C(6T(-..................................................................................................5
9.2 C(77:T)T'(6 *(CE33.............................................................................................549.9 #$C C(6;':)T'(63..............................................................................................549.< C(6$ET(3 )**-'C)T'(63......................................................................................20
! TRANSMISSION PLANNING CRITERIA..............................................................................25
-
8/12/2019 Training Report at PGCIL HVDC Ss
5/49
POWER GRID CORPORATION OF INDIA LIMITED "HISTORY#:$
I%&'()*+&,(%:
P(-' G',) C('/('0&,(% ( I%),0 L,,&)POWERGRID3Founded 23 October 19921 is a
6avratna state?owned electric utility company head!uartered in urgaon, 'ndia. *owerrid was
incorporated on (ctober 29, 5A@A under the companies )ct, 5A> as the 6ational *ower
Transmission Corporation -imited, with the responsibility of planning, e"ecuting, owning
operating and maintaining the high voltage transmission systems in the country. The total
revenue of company is 4,09.@ crore 200A1 with net income 2,0
-
8/12/2019 Training Report at PGCIL HVDC Ss
6/49
ischarge all functions of planning and coordination relating to 'nter?3tate Transmission
3ystem with?
o 3tate Transmission :tilities
o Central overnment
o 3tate overnment
o enerating Companies
o egional Electricity Boards
o )uthority
o -icensees
o Transmission -icensees
o )ny other person notified by the Central overnment on this behalf.
E"ercise supervision and control over the 'nter?3tate Transmission 3ystem.
Efficient (peration and 7aintenance of Transmission 3ystems.
EstablishFaugment and operate all egional -oad ispatch Centers and Communication
facilities.
To facilitate private sector participation on Transmission system through 'ndependent
*rivate Transmission Company, Goint $entures.
To assist various 3EBs and other utilities in up gradation of s&ills % sharing of e"pertise
by organizing regular conferences, tailor?made training wor&shops directed towards
specific technological and (%7 areas and e"tending laboratory facilities for testing
purposes etc.
6
-
8/12/2019 Training Report at PGCIL HVDC Ss
7/49
estoring power in !uic&est possible time in the event of any natural disasters li&e super?
cyclone, flood etc. through deployment of Emergency estoration 3ystems.
D4(/%&04 S&0;:
The phased development of *(HE' at the time of its formation was foreseen as followsI
*hase?'I Transfer of Transmission facilities along with related manpower from Central F
CentreJ3tate Goint $enture (rganizations.
*hase?''I Transfer of e"isting egional Electricity Boards and egional -oad ispatch
Centers together with associated communication facilities.
*hase?'''I Establish *ower *ool to facilitate e"change of power between 3tatesFegionsleading to formation of 6ational *ower rid.
E&074,,000 &m now.
There are regional gridsI
6orthern egionI
7
-
8/12/2019 Training Report at PGCIL HVDC Ss
8/49
elhi, #aryana, #imachal *radesh, Gammu )nd Kashmir, *un+ab, a+asthan
:ttaranchal and :ttar *radesh
Eastern egionI
Bihar, Ghar&hand, (rissa 3i&&im and Hest Bengal.
Hestern egionI
adra and 6agar #aveli, aman and iu, Chhattisgarh, oa u+arat, 7adhya *radesh
and 7aharashtra.
3outhern egionI
)ndhra *radesh, Karnata&a, Kerala, *ondicherry and Tamil 6adu.
6orth?Eastern egionI
)runachal *radesh, )ssam, 7anipur, 7eghalaya, 7izoram, 6agaland and Tripura
*(HE'/s networ&, as at 3eptember, 200@, comprises of over >A,000 circuit &m of high
voltage transmission lines and 55> sub?stations spread across the country. The inter?regional
power transfer capacity of 6ational rid has been enhanced to about 54,000 7H from 5
-
8/12/2019 Training Report at PGCIL HVDC Ss
9/49
H,;< V(4&0; D,'+& C*''%& "HVDC#
I%&'()*+&,(%
) 2==? 2==@
T'0%,,(% %&-(' "+& # 0,4>,@00
S*7&0&,(% "%*7'# @ A9 50< 552
T'0%('0&,(% C0/0+,&6 "MVA#
-
8/12/2019 Training Report at PGCIL HVDC Ss
10/49
proportional to the s!uare of the current. #owever, power is also proportional to voltage, so for
a given power level, higher voltage can be traded off for lower current. Thus, the higher the
voltage, the lower the power loss. *ower loss can also be reduced by reducing resistance,
commonly achieved by increasing the diameter of the conductor but larger conductors are
heavier and more e"pensive.
#igh voltages cannot be easily used in lighting and motors, and so transmission?level voltage
must be reduced to values compatible with end?use e!uipment. The transformer, which only
wor&s with alternating current, is an efficient way to change voltages. *ractical manipulation of
C voltages only became possible with the development of high power electronic devices such
as mercury arc valves and later semiconductor devices, such as thyristors, insulated?gate bipolar
transistors 'BTs1, high power capable 7(3;ETs power metalJo"ideJsemiconductor field?
effect transistors1 and gate turn?off thyristors T(s1
A)0%&0; 0%) L,,&0&,(% ( 04&'%0&,%; +*''%& &'0%,,(%
The advantage of #$C is the ability to transmit large amounts of power over long distances
with lower capital costs and with lower losses than )C. epending on voltage level and
construction details, losses are !uoted as about 9 per 5,000 &m. #igh?voltage direct currenttransmission allows efficient use of energy sources remote from load centers.
'n a number of applications #$C is more effective than )C transmission. E"amples includeI
:ndersea cables, where high capacitance causes additional )C losses.
Endpoint?to?endpoint long?haul bul& power transmission without intermediate LtapsL, for
e"ample, in remote areas
'ncreasing the capacity of an e"isting power grid in situations where additional wires are
difficult or e"pensive to install *ower transmission and stabilization between unsynchronised )C distribution systems
Connecting a remote generating plant to the distribution grid
3tabilizing a predominantly )C power?grid, without increasing prospective short circuit
current
10
-
8/12/2019 Training Report at PGCIL HVDC Ss
11/49
educing line cost. #$C needs fewer conductors as there is no need to support multiple
phases. )lso, thinner conductors can be used since #$C does not suffer from the s&in
effect
;acilitate power transmission between different countries that use )C at differing
voltages andFor fre!uencies 3ynchronize )C produced by renewable energy sources
-ong undersea cables have a high capacitance. Hhile this has minimal effect for C
transmission, the current re!uired to charge and discharge the capacitance of the cable causes
additional '2 power losses when the cable is carrying )C. 'n addition, )C power is lost
to dielectric losses.
#$C can carry more power per conductor, because for a given power rating the constant
voltage in a C line is lower than the pea& voltage in an )C line. 'n )C power, the root means!uare 731 voltage measurement is considered the standard, but 73 is only about 45 of
the pea& voltage. The pea& voltage of )C determines the actual insulation thic&ness and
conductor spacing. Because C operates at a constant ma"imum voltage without 73, this
allows e"isting transmission line corridors with e!ually sized conductors and insulation to carry
2A more power into an area of high power consumption than )C, which can lower costs.
Because #$C allows power transmission between unsynchronised )C distribution systems, it
can help increase system stability, by preventing cascading failure from propagating from one
part of a wider power transmission grid to another. Changes in load that would cause portions of
an )C networ& to become unsynchronized and separate would not similarly affect a C lin&,
and the power flow through the C lin& would tend to stabilize the )C networ&. The magnitude
and direction of power flow through a C lin& can be directly commanded, and changed as
needed to support the )C networ&s at either end of the C lin&. This has caused many power
system operators to contemplate wider use of #$C technology for its stability benefits alone
D,0)0%&0;
The disadvantages of #$C are in conversion, switching and control. ;urther operating an#$C scheme re!uires &eeping many spare parts, which may be used e"clusively in one
system as #$C systems are less standardized than )C systems and the used technology
changes fast.
The re!uired static inverter are e"pensive and have limited overload capacity. )t smaller
transmission distances the losses in the static inverters may be bigger than in an )C
11
-
8/12/2019 Training Report at PGCIL HVDC Ss
12/49
transmission line. The cost of the inverters may not be offset by reductions in line construction
cost and lower line loss.
'n contrast to )C systems, realizing multiterminal systems is comple", as is e"panding e"isting
schemes to multiterminal systems. Controlling power flow in a multiterminal C system
re!uires good communication between all the terminals power flow must be actively regulated
by the control system instead of by the inherent properties of the transmission line. #igh
voltage C circuit brea&ers are difficult to build because some mechanism must be included in
the circuit brea&er to force current to zero, otherwise arcing and contact wear would be too great
to allow reliable switching. 7ulti?terminal lines are rare
C(& (
-
8/12/2019 Training Report at PGCIL HVDC Ss
13/49
in order to provide the necessary bloc&ing voltage capability.Thyristors used for #$C valves
are amongst the largest semiconductors of any type produced for
any industry. ;igure shows an @. &$ thyristor with an active silicon diameter of 55 mm
whichstarts life as a silicon ingot of 52 mm diameter, hence such thyristors are often referred
to as52 mmD thyristors1.
3uch components are e"pensive and there may be many thousand such components in a #$Cstation. 7oreover, they are !uite delicate and re!uire a great many additional components to
control.
2. Convertor Transforer: The converter transformer is the interface betweenthe )C system and the thyristor valves. Typically the #$C converter transformer issub+ected to a C voltage insulation stress as well as the )C voltage stress normally
e"periencedby a power transformer. it is important that the converter transformer be
thermally designed to ta&e into consideration both the fundamental fre!uency load and
the )C harmonic currents that will flow from the converter through the converter
transformer to the )C harmonic filters.
!.AC ,4&': The )C harmonic filters are typically composed of a high voltageconnected capacitor ban& in series with a medium voltage circuit comprizing air?cored
air?insulated reactors, resistors and capacitor ban&s. These filters are used to limit theimpact of )C harmonics and reactive power generated by Convertors .
".S((&
-
8/12/2019 Training Report at PGCIL HVDC Ss
14/49
a. Po%er Contro&: If the power demand is chaned then the power order wi!! ramp to the new
power transfer !e"e! at a rate of chane #$nown as the %ramp rate&' pre(se!ected b) the operator* +)pica!!)
the ma,imum power !imit is defined b) an o"er!oad contro!!er which is continuous!) ca!cu!atin the
therma! capabi!it) of the con"erter station e-uipment*
b. 're()en*y Contro&: . / scheme can contro! the . fre-uenc) of an . s)stem b)
automatica!!) adustin the power bein de!i"ered into that . s)stem in order to ba!ance the !oad with the
supp!)* +he fast power contro! b) the / reduces the under(fre-uenc) or o"er(fre-uenc) which can
resu!t from a chanin !oad in a sma!! power s)stem such as an is!and !oad*
c. Prote*tion: a #$C converter station the types of protection utilized fall into
two categories
M Conventional )C1 substation protection
M C protection
)C connected e!uipment such as converter transformers and )C harmonic filter
components, along with feeders and busbars, are protected using conventional )C protection
relays. The converter, along with the C circuit, is protected using hardware and software.
14
-
8/12/2019 Training Report at PGCIL HVDC Ss
15/49
+.DC fi&ters: Converter operation results in voltage harmonics being generated at theC
terminals of the converter, that is, there are sinusoidal )C harmonic components superimposed
on the C terminal voltage. This )C harmonic component of voltage will result in )C
harmonic current flow in the C circuit and the field generated by this )C harmonic current
flow can lin& with ad+acent conductors,such as open?wire telecommunication systems, and
induce harmonic current flow in these other circuits. 'n a bac&?to?bac& scheme, these harmonics
are contained within the valve hall with ade!uate shielding and, with a cable scheme,
the cable screen typically provides ade!uate shielding. #owever, with open?wire C
transmission it may be necessary to provide C filters to limit the amount of harmonic current
flowing in the C line. The C filter is physically similar to an )C filter in that it is connected
to the high voltage potential via a capacitor ban& other capacitors along with reactors and
resistors are then connected to the high voltage capacitor ban& in order to provide the desired
tuning and
T
-
8/12/2019 Training Report at PGCIL HVDC Ss
16/49
T
-
8/12/2019 Training Report at PGCIL HVDC Ss
17/49
as the driving voltage. The lea&age inductances of phases 5 and 9 will be the reactances which
determine the current. This is simply a phase to phase short circuit of the transformer. The short
circuit current flows through valve 9 in the forward direction and through valve 5 counter to the
forward direct current. )s soon as the short circuit current has achieved the amplitude of the
direct current the composite current is zero1, valve 5 e"tinguishes. )t this point, thecommutation process has ended and valve 9 is carrying the entire direct current. Curve of the
direct voltage during commutation is along the average value of the voltages of valves 5 and 9.
C*''%& +(%&'(4
Current control mainly determines
3teady state transmission power
Changes in transmission power according to size and rate of change
The dynamic behavior of the system including temporary overload
-imitation of transient overcurrents determined by amplitude and duration
The loading of all essential components of an #$C system, with the e"ception of filter
circuits, is determined by the direct current or an alternating current proportional to the direct
current. Therefore current control is also a very essential protective function.
'n #$C two point systems, the rectifier generally assumes the tas& of the current control. 't
is occasionally advantageous to assign the current control function to the inverter. #owever,
since the current control of the rectifier is needed as a proactive function, it is advantageous
to also use it for this purpose during normal operation. Then it is always active and monitors
itself.
17
-
8/12/2019 Training Report at PGCIL HVDC Ss
18/49
HVDC C(%,;*'0&,(%
M(%(/(4 0%) 0'&< '&*'%
'n a common configuration, called monopole, one of the terminals of the rectifier is connected
to earth ground. The other terminal, at a potential high above, or below, ground, is connected to
a transmission line. The earthed terminal may or may not be connected to the corresponding
connection at the inverting station by means of a second conductor.
'f no metallic conductor is installed, current flows in the earth between the earth electrodes at
the two stations. Therefore it is a type of single wire earth return. The issues surrounding earth?
return current include
Electrochemical corrosionof long buried metal ob+ects such as pipelines :nderwater earth?return electrodes in seawater may produce chlorine or otherwise affect
water chemistry.
)n unbalanced current path may result in a net magnetic field, which can affect magnetic
navigational compasses for ships passing over an underwater cable.
These effects can be eliminated with installation of a metallic return conductor between the two
ends of the monopolar transmission line. 3ince one terminal of the converters is connected to
earth, the return conductor need not be insulated for the full transmission voltage which ma&es
it less costly than the high?voltage conductor.
BIPOLAR
'n bipolar transmission a pair of conductors is used, each at a high potential with respect to
ground, in opposite polarity. 3ince these conductors must be insulated for the full voltage,
18
-
8/12/2019 Training Report at PGCIL HVDC Ss
19/49
transmission line cost is higher than a monopole with a return conductor. #owever, there are a
number of advantages to bipolar transmission which can ma&e it the attractive option.
:nder normal load, negligible earth?current flows, as in the case of monopolar
transmission with a metallic earth?return. This reduces earth return loss and environmentaleffects.
Hhen a fault develops in a line, with earth return electrodes installed at each end of the
line, appro"imately half the rated power can continue to flow using the earth as a return path
operating in monopolar mode.
3ince for a given total power rating each conductor of a bipolar line carries only half the
current of monopolar lines, the cost of the second conductor is reduced compared to a
monopolar line of the same rating.
'n very adverse terrain, the second conductor may be carried on an independent set of
transmission towers, so that some power may continue to be transmitted even if one line is
damaged.
) bipolar system may also be installed with a metallic earth return conductor.
Bipolar systems may carry as much as 9,200 7H at voltages of NF?>00 &$. 3ubmarine cable
installations initially commissioned as a monopole may be upgraded with additional cables and
operated as a Bipole.
C('(%0 D,+
-
8/12/2019 Training Report at PGCIL HVDC Ss
20/49
considerable power loss, create audible and radio?fre!uency interference, generate to"ic
compounds such as o"ides of nitrogen and ozone, and bring forth arcing.
Both )C and C transmission lines can generate coronas, in the former case in the form of
oscillating particles, in the latter a constant wind. ue to the space charge formed around the
conductors, an #$C system may have about half the loss per unit length of a high voltage )C
system carrying the same amount of power. Hith monopolar transmission the choice of polarity
of the energised conductor leads to a degree of control over the corona discharge. 'n particular,
the polarity of the ions emitted can be controlled, which may have an environmental impact
on particulate condensation. *articles of different polarities have a different mean?free
path.1 6egative coronas generate considerably more ozone than positive coronas, and generate it
further downwind of the power line, creating the potential for health effects. The use of
a positive voltage will reduce the ozone impacts of monopole #$C power lines.
A//4,+0&,(%
O',-
The controllability of current?flow through #$C rectifiers and inverters, their application in
connecting unsynchronized networ&s, and their applications in efficient submarine cables mean
that #$C cables are often used at national boundaries for the e"change of power. (ffshore
windfarms also re!uire undersea cables, and their turbines are unsynchronized.
AC %&-(' ,%&'+(%%+&,(%
)C transmission lines can only interconnect synchronized )C networ&s that oscillate at the
same fre!uency and in phase. 7any areas that wish to share power have unsynchronized
networ&s. #owever, #$C systems ma&e it possible to interconnect unsynchronized )C
networ&s, and also add the possibility of controlling )C voltage and reactive power flow.
) generator connected to a long )C transmission line may become unstable and fall out of
synchronization with a distant )C power system. )n #$C transmission lin& may ma&e it
economically feasible to use remote generation sites. Hind farms located off?shore may use
#$C systems to collect power from multiple unsynchronized generators for transmission to
the shore by an underwater cable.
20
-
8/12/2019 Training Report at PGCIL HVDC Ss
21/49
'n general, however, an #$C power line will interconnect two )C regions of the power?
distribution grid. 7achinery to convert between )C and C power adds a considerable cost in
power transmission. The conversion from )C to C is &nown as rectification and from C to
)C as inversion. )bove a certain brea&?even distance about 0 &m for submarine cables, and
perhaps >00J@00 &m for overhead cables1, the lower cost of the #$C electrical conductorsoutweighs the cost of the electronics.
T'0%,,(% P40%%,%; C',&',0I%&'()*+&,(%
The ob+ective of system planning is to evolve a power system with a level of performance
characterised by an acceptable degree of ade!uacy and security based on a trade?off between
costs and ris&s involved. 'nsofar as power transmission systems are concerned , there are nowidely adopted uniform guidelines which determine the criteria for transmission planning vis?s?
vis acceptable degree of ade!uacy and security. The criteria generally depends on the factors
such as availability of generation vis?O?vis demand, voltage levels, and configuration of the
system, control and communication facilities and resource constraints. *ractices in this regard
vary from country to country. The common theme in the various approaches is the acceptable
system performanceD. Even though the factors affecting system performance are probabilistic in
nature, deterministic approach has been used most commonly, being rather easy to apply. ;or
adopting probabilistic approach, long operating e"perience and availability of reliable statistical
data regarding performance of system components, namely e!uipment failure rate, outage
duration, etc, are essential. 3uch data are presently being compiled by a few utilities but these
are still inade!uate to go in for a totally probabilistic approach. #ence it is considered prudent
to adopt a deterministic approach for the present with a committed thrust towards progressive
adoption of probabilistic approach.
21
-
8/12/2019 Training Report at PGCIL HVDC Ss
22/49
P40%%,%; P
-
8/12/2019 Training Report at PGCIL HVDC Ss
23/49
The choice shall be based on cost, reliability, right?of?way re!uirements, energy losses,
down time in case of upgradation and reconductoring options1
'n case of generating station close to a ma+or load centre, sensitivity of its complete
closure with loads to be metto the e"tent possible1from other generating stations is also
studied.
'n case of transmission system associated with 6uclear *ower 3tations there shall be two
independent sources of power supply for the purpose of providing start?up power
facilities. ;urther the angle between start?up power source and the 6** switchyard
should be, as far as possible, maintained within 50 degrees.
The evacuation system for sensitive power stations viz., 6uclear power stations shall
generally be planned so as to terminate it at large load centres to facilitate islanding of the
power station in case of contingency.
Contingency is the temporary removal of one or more system elements from service. The
cause or reason for such removal may be a fault , planned maintenanceFrepair etc.
5. 3ingle Contingency J The contingency arising out of removal of one system element
from service.
2. ouble Contingency J The contingency arising out of removal of two system elements
from service. 't includes a FC line, two 3FC lines in same corridor or different corridors,
a 3FC line and a transformer etc.
9. are Contingency J Temporary removal of complete generating station or complete sub?
station including all the incoming % outgoing feeders and transformers 1 from service,
#$C bipole and stuc& brea&er condition.
Hhere only two circuits are planned for evacuation of power from a generating station,
these should be two single lines instead of a double circuit line.
eactive power flow through 'CTs shall be minimal. 6ormally it shall not e"ceed 50 of
the rating of the 'CTs. Hhenever voltage on #$ side of 'CT is less than 0.A4 pu, no
reactive power shall flow through 'CT.
23
-
8/12/2019 Training Report at PGCIL HVDC Ss
24/49
ThermalF6uclear enerating units shall normally not run at leading power factor.
#owever, for the purpose of charging, generating unit may be allowed to operate at
leading power factor as per the respective capability curve.
'nter?regional lin&s shall, in the present conte"t, be planned as asynchronous ties unless
otherwise permitted from operational consideration.
L(0) G%'0&,(% S+%0',(
The load?generation scenarios shall be wor&ed out so as to reflect in a pragmatic manner the
daily and seasonal variations in the load demand and generation availability.
L(0) )0%)
The profile of annual and daily demands will be determined from past data. These data willusually give the demand at grid supply points and for the whole system identifying the
annual and daily pea& demand.
A+&, /(-'
The system pea& demands shall be based on the latest reports of Electric *ower 3urvey
E*31 Committee. 'n case these pea& load figures are more than the pea&ing availability, theloads will be suitably ad+usted substation wise to match with the availability.
The load demands at other periods seasonal variations and minimum loads1shall be derived
based on the annual pea& demand and past pattern of load variations.
;rom practical considerations the load variations over the year shall be considered as underI?
5. )nnual *ea& -oad J 't is the simultaneous ma"imum demand of the system being
studied. 't is based on latest Electric *ower 3urvey E*31 or total pea&ing power
availability, whichever is less.
2. 3easonal variation in *ea& loadscorresponding to high thermal and high hydro
generation1
24
-
8/12/2019 Training Report at PGCIL HVDC Ss
25/49
9. 7inimal load J 't is the e"pected minimum system demand and is determined from
average ration of annual pea& load and minimum load observed in the system for the last
years.
-
8/12/2019 Training Report at PGCIL HVDC Ss
26/49
units. 'n case of nuclear units the minimum level of output shall be ta&en as not less than 40
of the rated capacity.
eneration dispatches corresponding to the following operating conditions shall be considered
depending on the nature and characteristics of the system.
)nnual *ea& -oad
7a"imum Thermal generation J 't is the condition when hydro generation is lownot
necessarily minimum1and thermal generation is &ept ma"imum to meet seasonal pea&
loadsnot necessarily annual pea& load1.'n other words it is the condition when the gap
between monthly pea& demand and hydro power availability is ma"imum.
7a"imum #ydro generation J 't is the condition when hydro power availability is
ma"imum during the year. 't is also &nown as #igh #ydro condition.
)nnual 7inimum -oad
3pecial area dispatches J 't is the condition when power output from all the generating
stations located in an area in close pro"imity1 is &ept at the ma"imum feasible level.
7a"imum ;easible level of a generating station is the ma"imum power output when all
the units in a power station are in service, assuming no planned or forced outages.
#owever, in case of power stationFcomple" where si" or more units e"ist, for every si"
units one unit Jsecond largest?is assumed to be under annual planned maintenance.
3pecial dispatches corresponding to high agricultural load with low power factor,
wherever applicable.
(ff pea& conditions with ma"imum pumping load where *umped 3torage stations e"ist
and also with the inter?regional e"changes, if envisaged.
Complete closure of a generating station close to a ma+or load centre.
The generation dispatch for purpose of carrying out sensitivity studies corresponding to
complete closure of generating station close to a ma+or load centre shall be wor&ed out by
increasing generation at other stations to the e"tent possible &eeping in view the
ma"imum li&ely availability at these stations, ownership pattern, shares etc.
26
-
8/12/2019 Training Report at PGCIL HVDC Ss
27/49
P',,74 L,% L(0),%; L,,&
*ermissible line loading limit depend on many factors such as voltage regulation, stabilityand thermal capacity etc. Thermal capacity of a line refers to the amount of current that
can be carried by a line conductor without e"ceeding its design operating temperature.
3urge 'mpedance -oading 3'-1 means a unit power factor load over a resistance line
such that series reactive loss 'P2Q1 along the line is e!ual to shunt capacitive gain
$P2Q=1. :nder these conditions the sending end and receiving end voltages and current
are e!ual in magnitude but different in phase position. Hhile 3'- gives a general idea of
the loading capability of the line , it is usual to load the short lines above 3'- and long
lines lower than 3'- because of the stability limitations1.line loading can also be shown
in terms of surge impedance loading of uncompensated line1as a function of line length
assuming a voltage regulation of and phase angular difference of 90 degrees between
the two ends of the line. 'n case of shunt compensated lines, the 3'- will get reduced by a
factor &, where
& R s!rt 5?degree of compensation1
;or lines whose permissible line loading as determined from the curve is higher than the
thermal loading limit, permissible loading limit shall be restricted to thermal loading
limit.
Thermal loading limits are generally decided by design practice on the basis of ambient
temperature, ma"imum permissible conductor temperature, wind velocity, etc. 'n 'ndia,
the ambient temperatures obtaining in the various parts of the country are different and
vary considerably during the various seasons of the year. esigns of transmission line
with )3C conductors in E#$ systems will normally be based on a conductortemperature limit of 4 deg Celsius. #owever, for some of the e"isting lines which have
been designed for a conductor temperature of > deg Celsius the loading shall be
correspondingly reduced. 'n the case of )))C conductors, ma"imum conductor
temperature limit will be ta&en as @ deg Celsius.
27
-
8/12/2019 Training Report at PGCIL HVDC Ss
28/49
T/('0'6 O'(4&0;
These are power fre!uency overvoltages produced in a power system due to sudden load
re+ection, single?phase?to?ground faults etc.
-
8/12/2019 Training Report at PGCIL HVDC Ss
29/49
be such that under steady state condition, switching on and off of the reactors shall not
cause a voltage change e"ceeding . The standard sizes7$)1 of reactors areI?
9 % @0 at &v 5?ph units1 0, >9 % 550 at @00 &$
;i"ed line reactors may be provided to control Temporary *ower ;re!uency overvoltage
Safter all voltage regulation has ta&en place within the limits defined, under all probable
operating conditions.
-ine reactors switchableFcontrolledFfi"ed1 may be provided if it is not possible to chargeE#$ line without e"ceeding the voltage limits defined. The possibility of reducing pre?
charging voltage of the charging end shall also be considered in the conte"t of
establishing the need for reactors.
S&0&,+ VAR C(/%0&,(% "SVC#
3tatic $) compensation shall be provided where found necessary to damp the powerswings and provide the system stability under conditions defined. The dynamic range of
static compensators shall not be utilised under steady state operating conditions as far as
possible.
S*7$S&0&,(% P40%%,%; C',&',0 The re!uirements in respect of E#$ sub?stations in a system such as the total load to be
catered by the sub?station of a particular voltage level, its 7$) capacity, number of
feeders permissible etc. are important to the planners so as to provide an idea to them
about the time for going in for the adoption of ne"t higher voltage level sub?station and
also the number of substations re!uired for meeting a particular !uantum of load.
29
-
8/12/2019 Training Report at PGCIL HVDC Ss
30/49
Keeping these in view the following criteria have been laid down for planning an E#$
substationI
The ma"imum fault level on any new substation bus should not e"ceed @0 of the rated
rupturing capacity of the circuit brea&er. The 20 margin is intended to ta&e care of the
increase in short?circuit levels as the system grows. The rated brea&ing current capability
of switchgear at different voltage levels may be ta&en asI?
592 &$ ?? 2F95 &)
220 &$ ?? 95.F
-
8/12/2019 Training Report at PGCIL HVDC Ss
31/49
) stuc& brea&er condition shall not cause disruption of more than four feeders for 220
&$ system and two feeders for &$ systems.
T'0%,,(% E%;,%',%;
M08(' C(/(%%& ( T'0%,,(% L,%
Conductor
Tower esign and foundation
Earth wire
'nsulators
31
-
8/12/2019 Training Report at PGCIL HVDC Ss
32/49
#ardware ;ittings
)ccessories
CONDUCTORS
BUNDLE CONDUCTOR SELECTION AND OPTIMIATION
3ize, Type and Configuration of conductor influencesI?
Tower and its geometry
;oundations
(ptimum spans
ating and configuration of 'nsulator string
'nsulator 3wings
round clearance
-ine interferences li&e electric field at ground, corona, radio % T$ interference, audible
noise etc.
CONDUCTOR SELECTION SCENARIO
32
-
8/12/2019 Training Report at PGCIL HVDC Ss
33/49
SCENARIO A
3election of character for a transmission line of identified voltage level and specified
minimum power flow but power flow capacity becomes ruling factor in selection ofconductor size low voltage lines1.
SCENARIO B
3election of conductor for a transmission line with identified voltage level and a specified
minimum power flow but voltage level become ruling factor in selection of
conductorFconductor bundle size E#$F:#$ lines1.
SCENARIO C
3election of conductor for high power capacity long distances transmission lines where
selection of voltage level and conductorFconductor bundle size are to be done together to
obtain most optimum solution #$C Bipole1
CONDUCTOR BUNDLE SELECTION METHODOLOGY
*rimary set of conductor bundleFsizes identified to start optimization
*arameters li&e insulation re!uirement, limits for corona, '$, )6, thermal ratings, line
losses and statutory clearances identified
33
-
8/12/2019 Training Report at PGCIL HVDC Ss
34/49
etailed analysis of various alternatives in respect of following to be carried out to select
the configuration
( Basic insulation design and insulator selection
( Tower configuration analysis
( Tower weight and foundation analysis
( Capital line cost analysis and span optimization
( -ine loss calculation
( Economic evaluations*H1 of alternatives
( Comparison of interference performance( Cost sensitivity analysis
CONDUCTOR OPTMIATION PROCEDURE
*'7)= 3E-ECT'(6
Thermal rating of the conductorFconductors
7anufacturing facilities
E"pense of other utilities
3ystem voltage alternatives
Construction convenience
-ine loss considerations
Terrain conditions and ground profile
3pan length re!uirements
34
-
8/12/2019 Training Report at PGCIL HVDC Ss
35/49
ight (f Hay limitations
CONDUCTOR SELECTION DESIGN CONSIDERATIONS
B)3'C C(63'E)T'(63 6(6 $)')B-E1
51 -oading condition and reliability level for the transmission line.
21 'nsulator co?ordination
91 -imit load condition for structure, conductor, insulator, and hardware as well as limit
conditions for swing of conductor and insulator strings.
1 *arameters for economic evaluation
CONDUCTOR SELECTION FOR SPECIAL TRANSMISSION SYSTEM
35
-
8/12/2019 Training Report at PGCIL HVDC Ss
36/49
:*)T'6 (; -'6E3
( 3ag of the selected conductor at ma"imum operating temperature should not e"ceed
the sag of the original conductor
( 6o e"tra loadings on the structure at various design considerations
:*)'6 (; -'6E3
( -ine interference in respect of '$, T$', )6, E;, 7; etc. 3hould be within
acceptable limits
( Conductor surface gradient within acceptable limits
( )symmetric bundle
C(7*)CT -'6E3
( -owest possible sag and swing for re!uired !uantum of power
( Considerations involved in upgradingFup rating
CONDUCTOR BUNDLE SELECTION: ESTIMATION OF TOWER
WEIGHTS AND FOUNDATION VOLUMES
;or each alternative of conductor and insulator configuration
T(HE HE'#T E3T'7)T'(6
*reliminary tower design studies conducted
36
-
8/12/2019 Training Report at PGCIL HVDC Ss
37/49
Estimation based on regression analysis and empirical formulae
;(:6)T'(6 $(-:7E E3T'7)T'(6
*reliminary foundation design studies conducted
C(6:CT( B:6-E (T'7'U)T'(6I TEC#6(?EC(6(7'C )6)-=3'3
51 Capital cost of line
Cost of each item, construction cost
21 Cost of line losses
)nnual loss cost R )nnual demand cost N )nnual energy -oss Cost
91 esults of economic evaluation*H or )nnual Cost basis1
-
8/12/2019 Training Report at PGCIL HVDC Ss
38/49
)-- )-:7'6':7 )--(= C(6:CT( )))C
ood Conductivity
#igh Tensile 3trength
3uperior Corrosion resistance compared to )C3
'mproved strength to weight ratio resulting in lower sag
-ower electrical losses
)luminium Conductor 3teel 3upported )C33 Conductor1
3imilar to )C3 e"cept )luminium
3teel Core #igh 3trength1 carries most of the load and hence less sag compared to
conventional )C3 conductor under emergency loadings.
Can be operated at 200 degree C without loss of strength
'mproved Conductivity
Better self damping characteristics
Compact Conductors
)luminium wiresFstrands shaped trapezoidal
'ncreased )luminium area and hence higher current carrying capacity
38
-
8/12/2019 Training Report at PGCIL HVDC Ss
39/49
'6$) Conductors
Core made of alloy of 'ron. 6ic&el having low thermal coefficient of e"pansion5F9rdthat
of steel1
)fter certain transition temperature all load transferred to the core and hence lower sagcompared to )C3 after transition temperature
Can be operated up to 2000C
DESIGN OF TOWERS
SALIENT DESIGN CONDITIONS
The reliability of transmission line towers depends on the appropriate selection of design
criteriaFparameters.
Climatic conditions play an important role in determining the reliability of transmission
line tower.
) significant number of transmission line failures can be the result of wind speed
e"ceeding design limits due to deficiencies in selection of design parametersFcriteria.
EARTHWIRE
;unctions of Earth wire
To protect conductor against lighting flashovers
To provide a path for fault current
39
-
8/12/2019 Training Report at PGCIL HVDC Ss
40/49
-ighting ;lashovers
irect ;lashover
(ccurs due to shielding failure with lighting on the conductor, flashover ta&ing place
across the insulator string from conductor to ground.
Bac& ;lashover
(ccurs due to high towering resistance with a high voltage at the grounded tower cross
arm compared to conductor, resulting in a flashover across the insulator string from
ground to conductor.
7a"imum allowable fault current '1 through earthwire mainly depends upon
)rea of Earth wire)1
7a"imum permissible temperature
Time of short circuitt1
' varies proportional to ) and inversely proportional to s!rt t1
HARDWARE FITTINGS AND ACCESSORIES FOR CONDUCTOR
EARTHWIRE
#)H)E ;'TT'63
;or attachment of insulator string to tower
?shac&les, Ball clevis, =o&e *late, Chain lin&
;or attachment of insulator string to the conductor
40
-
8/12/2019 Training Report at PGCIL HVDC Ss
41/49
3uspension % tension assembly
;ittings li&e ?3hac&les, soc&et clevis, chain lin&
;or protection of insulator string from power follow current
)rcing horn
;or ma&ing electric field uniform and to limit the electric field at live end
Corona control ringFrading ring
;or fine ad+ustment of conductor sag ?3ag )d+ustment plate, Turn Buc&le
#)H)E ;'TT'63? esign
)rcing #orn
The air gap is maintained for satisfactory performance under actual field conditions.
;or power follow current
=o&e *late
To withstand mechanical loads?Thic&ness % shear edge maintained
To maintain sub conductor spacing
Corona Control ingFrading #orn
To cover at least one live and insulator disc
To cover hardware fittings susceptible for CoronaF'$
3uspension )ssembly
? 3haped to prevent hammering between clamp % conductor
? To minimize static % dynamic stress in conductor under various
loading conditions
? 7inimum level of coronaF'$ performance
41
-
8/12/2019 Training Report at PGCIL HVDC Ss
42/49
? ;or slipping of conductor under prescribed unbalanced conditions
between ad+acent conductor spans
Tension )ssembly
( To withstand loads of atleast A of conductor :T3
( To have conductivity more than that of conductor
3ag )d+ustment *lateFTurn Buc&le
( To ad+ust sag upto 50mm in steps of >mm.
C(& E%;,%',%;
W
-
8/12/2019 Training Report at PGCIL HVDC Ss
43/49
:ndergrounding is more e"pensive, since the cost of burying cables at transmission voltages is
several times greater than overhead power lines, and the life?cycle cost of an underground
power cable is two to four times the cost of an overhead power line.
A7&'0+& +(& &,0&
51 *reliminary 3urvey % 3oil 'nvestigation
21 -and )c!uisition for 3ubstation and % Compensation
91 Cost of compensation for transmission lines
Compensation towards trees, crops % *TCC
Compensation towards forest
-
8/12/2019 Training Report at PGCIL HVDC Ss
44/49
551 Custom uty
521 'nterest uring Construction 'C1
S*7&0&,(% E*,/%&
51 '3 3ubstation E!uipment.
21 Circuit Brea&ers
91 'solators
1 3urge )rrestersI They should be provided near line entrances, transformers so as to achieve
proper insulation coordination. These shall be fitted with pressure relief devices and
diverting ports suitable for shattering of porcelain housing providing path for the flow of
rated currents in the event of arresters failure.
S*7&0&,(% S*//('& 0+,4,&,
51 )C % C *ower supplies
21 ;ire ;ighting 3ystemI ;ire fighting system in general conforms to fire insurance regulations
of 'ndia. The fire fighting system is proposed with both )C motor % diesel engine drivenpumps. )utomatic heat actuated emulsifying system is proposed for transformers and
reactors.
91 (il evacuating, filtering, testing, % filling apparatusI To monitor the !uality of oil for the
satisfactory performance of transformers, shunt reactors and for periodical maintenance
44
-
8/12/2019 Training Report at PGCIL HVDC Ss
45/49
necessary oil evacuating, filtering, testing and filling apparatus would be provided at new
substations.
-
8/12/2019 Training Report at PGCIL HVDC Ss
46/49
wider geographic area. emote and low?cost sources of energy, such as hydroelectric power or
mine?mouth coal, could be e"ploited to lower energy production cost.
The capital cost of electric power stations is so high, and electric demand is so variable, that it is
often cheaper to import some portion of the needed power than to generate it locally. Because
nearby loads are often correlated, electricity must often come from distant sources. Because of
the economics of load balancing, wide area transmission grids now span across countries and
even large portions of continents. The web of interconnections between power producers and
consumers ensures that power can flow, even if a few lin&s are inoperative.
The unvarying or slowly varying over many hours1 portion of the electric demand is &nown as
the Vbase loadV, and is generally served best by large facilities and therefore efficient due to
economies of scale1 with low variable costs for fuel and operations, i.e. nuclear, coal, hydro.
enewable sources such as solar, wind, oceanFtidal, etc. are not considered Vbase loadV but canstill add power to the grid. 3maller and higher cost sources, such as combined cycle or
combustion turbine plants fueled by natural gas are then added as needed.
-ong distance transmission allows remote renewable energy resources to be used to displace
fossil fuel consumption. #ydro and wind sources canLt be moved closer to populous cities, and
solar costs are lowest in remote areas where local power needs are minimal. Connection costs
alone can determine whether any particular renewable alternative is economically sensible.
Costs can be prohibitive for transmission lines, but various proposals for massive infrastructure
investment in high capacity, very long distance super grid transmission networ&s could berecovered with modest usage fees.
#igh voltage direct current #$C1 is used to transmit large amounts of power over long
distances or for interconnections between asynchronous grids. Hhen electrical energy is
re!uired to be transmitted over very long distances, it is more economical to transmit using
direct current instead of alternating current. ;or a long transmission line, the lower losses and
reduced construction cost of a C line can offset the additional cost of converter stations at each
end. )lso, at high )C voltages, significant although economically acceptable1 amounts of
energy are lost due to corona discharge, the capacitance between phases or, in the case of buried
cables, between phases and the soil or water in which the cable is buried.
46
-
8/12/2019 Training Report at PGCIL HVDC Ss
47/49
E%,'(%%&04 0%) S(+,04 A/+&
F('& I%(4%& C40'0%+
)s per the practice, preliminary route selection is done by *(HE' based on such
documents as ;orest )tlas and the survey of 'ndia maps using beeD line method, followed
by field verification through wal& over survey. )ll possible steps are ta&en to avoid the route
alignment through the forests. 'n case where it becomes unavoidable due the geography of
the terrain, the alignment is made in such a way that the route through forests is barest
minimum.
;or the selection of optimum route, following points are to be ta&en into considerationI
The route of the proposed transmission line does not involve any human rehabilitation
)ny monument of cultural or historical importance is not generally affected.
The route does not create any threat to the survival of the community.
't does not affect any public utility services li&e playground , school, other
establishments, etc
't does not pass through any sanctuaries, national par&, etc.
't does not infringe with the areas of natural resources.
47
-
8/12/2019 Training Report at PGCIL HVDC Ss
48/49
S(+,04 I* RR 0*'
)s per the prevailing law, land below transmission line is not re!uired to be ac!uired and
only land for substation is ac!uired. *(HE' is following the practice of land
management to minimize the land re!uirement to the barest minimum. enerally 20 to 90
hectares of land is re!uired for constructing a substation depending upon the type of the
voltage level. Even for this 20 to 90 hectare land, *(HE' try to locate the substation
on government land as far as possible and in the absence of govt. land private land is
ac!uired. 'n order to insure the indigenous Tribal1 people do not suffer adverse affects,
utmost care is ta&en to avoid ac!uisition of land belonging to tribal community. 'n spite of
that, *(HE' has developed an indigenous people Tribal1 evelopment *lan '**1
which ensure that they receive culturally compatible social and economic benefits for any
adverse affects.
R, A%046,
R%* R,
The capital cost of the transmission system comprises of
i1 )n e!uity component
ii1 ) loan component
This is recovered through the annual transmission charges consisting of return re!uired for
the e!uity, an interest for the loan component together with the depreciation charges, the (
% 7 charges and interest on wor&ing capital from the beneficiaries as per 6otification in
proportion to the benefits derived by them. These are recovered in monthly fi"ed charges
from the beneficiaries. 'n addition to annual charges 'ncome Ta", ;E$ and incentives, etc.
as per notification would also be payable.
The Bul& *ower Transmission )greement B*T)1 which cover the payments for
transmission charges for all the e"isting pro+ects as well as those that may be included in
future after approval by CE) already e"ists.
48
-
8/12/2019 Training Report at PGCIL HVDC Ss
49/49
R;*40&('6 R,
B*T)s have the provision that the transmission tariff for new F e"isting transmission assets
commissioned as well as the additional tariff payable due to additional capitalization fromyear to year, etc. shall be computed by *(HE' based on norms F methodology
followed in the (' notification dated 5>.52.A4 in accordance with norms to be specified by
the Central Electricity egulatory Commission CEC1 as amended from time to time.
T0',
The cost of electric power is normally given by the e"pression a N bQ&H N cQ&Hh1 per
annum, where a is a fi"ed charge for the utility, independent of the power output b depends on
the ma"imum demand of the system and hence on the interest and depreciation on the installed
power station and c depends on the units produced and therefore on the fuel charges and the
wages of the station staff.
Tariff structure may be such as to influence the load curve and to improve the load factor.
Tariff should consider the pf power factor1 of the load of the consumer. if it is low, it ta&es
more current for the same &Hs and hence T and Transmission and istribution1 losses are
correspondingly increased. The power has to install either pf correcting improvement1 devices
such as synchronous condensors, 3$C 3tatic $ar Compensator1 or voltage regulating
e!uipment to maintain the voltages within allowed limits and thus the total cost increases. (ne
of the following alternatives may be used to avoid the low pf I
5. To charge the consumer based on K$) rather than KH.
2. ) pf penalty clause may be imposed on the consumer.