training repor1
TRANSCRIPT
-
8/6/2019 Training Repor1
1/36
TRAINING REPORT
ON
GENERATION OF ELECTRICAL
ENERGY
AT
KANTI BIJLEE UTPADAN NIGAM LIMITED
(A joint venture of NTPC Ltd. &BSEB)
MUZAFFARPUR THERMAL POWER STATION, KANTI, MUZAFFARPUR,
BIHAR
Submitted for the partial fulfilment of the Requirement of
BACHELOR IN ELECTRICAL ENGINEERING
DURATION : 30.05.2011 to 26.06.2011
Under the guidance of :-
1. Mr. J. Bhattacharya
DGM
2. Mr. A. K. Jena
3. Mr. N. D. Nayak
SUBMITTED BY:-
Md.
SHARIQUE AFZAL
COLLEGE: AL INSTITUTE OF TECHNOLOGY, ICHCHHANATH, SURAT-
395007(GUJARAT), INDIA
COURSE : B. TECH. (ELECTRICAL ENGG.)
YEAR : 3nd year (6th Sem. )
-
8/6/2019 Training Repor1
2/36
ADMISSION NUMBER : U09EE567
ACKNOWLEDGMENT
This report pertains to take vocational training which was undertaken
under KANTI BIJLEE UTPADAN NIGAM LIMITED, KANTI,
MUZAFFARPUR, BIHAR ( A joint venture of NTPC & BSEB ) in
partial fulfilment of the requirement for the BACHELOR IN
ELECTRICAL ENGINEERING from SARDAR VALLABHBHAI
NATIONAL INTITUTE OF TECHNOLOGY, ICHCHHANATH, SURAT-
395007,GUJARAT. The main purpose of the training was to acquaint
myself with practical experience of actual work condition in which we
are required to work in future. I learnt a lot from the practical
experience of the engineering & other personals under whom I was
placed for training. This helped me to develop the habit of analysis
critically various aspects of problem at the time of decision making.
I would like to acknowledge to Mr. J. Bhattacharya, Mr.
A.K.Jena, Mr.N. D. Nayak, during training period whogive me clear details & guidelines for the power station .
Finally; I would like to express my thanks to all of the technical & non
technical persons for the co- operation & valuable guidance duringmy training period.
-
8/6/2019 Training Repor1
3/36
INTRODUCTION ABOUT THE
PLANT
KBUNL (Kanti Bijlee Utpadan Nigam Limited) which was formerly
known as Vaishali Power Generating Company Ltd(VPGCL) is situated
in kanti which is 12 km away from main town muzaffarpur.
It is totally coal fired Thermal power station.
There are two units of each 110MW installed capacity.
RECENT DEVELOPMENT
NTPC has opted for joint venture(jv) with BSEB. The main feature of
this jv is as follows:
KANTI BIJLEE UTPADAN NIGAM LIMITEDThis jv was incorporated on with Bihar State Electricity Board, a State run
Electricity Board in the State of Bihar with NTPC, engaged in generation,transmission and distribution of electricity.
OBJECTIVE: To take over Muzaffarpur Thermal Power station(2*110MW),a coal based power station at kanti , for carrying ourrestoration ,R&M and supplying power mainly to state ofBihar.
PROMOTERS EQUITY
NTPC: 51-74%BSEB: 49-26%
-
8/6/2019 Training Repor1
4/36
ABSTRACT
Any thermal power plant is converting the chemical energy of fossil
fuel (coal) into electrical energy. The process involved for this
conversion is based upon the modified Rankin cycle. The major
components that are used to accomplish the modified Rankin cycle
are:
Boiler feed pump,
The steam generator water walls (evaporator),
Steam generator super heaters,
Steam turbine,
Reheater,
Condenser,
Regenerative feed heaters etc.
All components of a power generating cycle are vital and critical in
operation. In Modified Rankin cycle, the two most important aspects
that is added are reheating & regenerative heating. By reheating we
used to send the steam coming from exhaust of the turbine back to
the reheater of the boiler so that its enthalpy increases and more
work can be done by this steam the other purpose is to make steam
dry so that no harm will be done to the blades of turbine.
-
8/6/2019 Training Repor1
5/36
In MTPS Kanti, we have three turbines in Tandem coupling namely
one H.P Turbine, one I.P Turbine & one L.P Turbine coupled with the
generator to which is synchronized with the grid to produce
electricity at 50Hz.
In all my modesty, i wish to record here that a sincere attempt has
been made for the presentation of this project report. I also trust that
this study will not only prove to be of academic interest but also will
be able to insight into the area of technical management.
CONTENT
SINO.
Description Page-No
01 An over view (NTPC) 0302 Plant introduction 04-0503 Schematic diagram of thermal power plant 0604 Working principle 0705 Process of generation of electricity 0806 Coal to steam 0907 Steam to mechanical 10-1108 Power Generation, Transmission &
Distribution12-13
09 Single line diagram of grid 1410 Transmission 15-1811 Light up process 1912 Main boiler components 19-2113 Cooling water circuit 2214 Types of fan 22-2315 Types of pump 23-24
16 Types of turbine 24-2517 Types of heater 25
-
8/6/2019 Training Repor1
6/36
18 Unit control desk and panels 2519 References 26
An Overview
NTPC
NTPC was set up in 7th November 1975, the NAVRATNA power giant
today generates more than one fourth of the total power in the
country, ranked 5th largest power generating utility in the world, NTPC
is the second most efficient in capacity utilization among the top ten
thermal generating companies according to a survey conducted byData monitor, United Kingdom. In a short span of two decades, NTPC
has earn its prime status by setting up a total generating capacity of
22,249MW, with 19.14% of Indias operating capacity, the company
generates 26.7% of country electricity through its 13 coal & 7 gas
based power plants spread all over the country.
Today, country needs a 10% sustained growth in power generation to
ensure the momentum for a 7% overall growth in the economy.
Recognizing this, NTPC has committed itself to achieving the status of
a 30,000MW plus company by the year 2007 and 40,000MW pluscompany by the year 2012 and power generating capacity addition
programme of 51,000MW (including nuclear energy and non-
conventional sources of energy) for the tenth plan.
NEW TECHNOLOGY
Super critical technology at NTPC Sipat project (3*600MW) to
increase the efficiency of the cycle and to decrease the green house
gas emission,
-
8/6/2019 Training Repor1
7/36
Closed cycle seawater cooling at Simhadri project for first time
in India
Introduction of IGCC (Integrated gasified combined cycle) for
clean and efficient utilization of coal.
ENVIROMENT MANAGEMENT
Liquid water treatment plants at Farakka and
Kahalgaon.
Ash water recycling system at Kahalgaon and korba to
reduce water requirement for ash disposal at these
stations.
PLANT INTRODUCTION
Salient Features Of Boiler Plant
1. General
Type of boiler Single drum tangential firing &reheat type (water tube)
Type of fuel used Pulverized coal (Main fuel), Heavy oil & L.D.O (for light up & flamestabilization)
No. Of Mills 06Type of Mills Pressurized type Bowl MillFurnace Balanced draught P.A Fans 02 (each 60% capacity)F.D Fans 02 (each 60% capacity)I.D Fans 03 (each 60% capacity, one
standby)Air heater 02Types of Air Heater Trisector regenerative
Electrostatic Precipitator 01
-
8/6/2019 Training Repor1
8/36
2. M.C.R Parameter
M.C.R. Value
S.H. Outlet steam flow 375 T/HrR.H. stem flow 331 T/Hr Pressure at S.H. Outlet 141.5 AtaTemp. at S.H. Outlet 540cPressure at R.H. Inlet 37 AtaPressure at R.H Outlet 32.9 AtaTemp. at R.H. Inlet 369cTemp. at R.H Outlet 540cPressure in drum 148.69 Ata
Design pressure 158.0 kg/cmFlue gas temp. leavingEconomiser
350c
Flue gas temp. leaving AirHeater
142c
Feed Water Temp. beforeEconomizer
235c
Salient Features Of Turbine
1. General
Type Of Turbine Reheat No. Of Cylinders 3(HP,IP &LP)No. Of LP Heater 05No. Of HP Heater 02Deaerator 01(Variable pressure type)No. Of Extraction pump 03(one standby)No. Of BFP 02(one standby)
M.C.R. Parameter
M.C.R. Value
Rated output 110MW M.S. Pressure at H.P.turbine inlet
130 Ata
M.s. temp. at H.P. turbine
inlet
535c
-
8/6/2019 Training Repor1
9/36
H.R.H. temp. at I.P.turbine inlet
535c
Turbine speed 3000 rpmCondenser Vacuum 0.1 kg/cm(abs)
No. Of Extraction 07Quality of cooling water 15,400 m/hrSalient Features Of Generator
Rating ContinuousActive Output 110 MW Rated Voltage 11000+/-5%V Rated Current 7220 APower Factor 0.8 lagging
Frequency 50 Hz Excitation System Static typeField current at ratedoutput
1335 A
Type of cooling system Hydrogen CooledHydrogen Pressure 2 AtaNo. Of H cooled elements
06
Cooling medium for H Soft water
WORKING PRINCIPLE
The working principle of thermal power plant is based on Rankin
cycle. A central steam station basically works on the Rankin cycle.
Steam is produced in the boiler , is expanded in the prime mover
(Turbine) and is condensed in a condenser to be fed into the boiIer.
PROCESS OF GENERATION OF
ELECTRICITY
MTPS Kanti is a Thermal Power Plant. The functioning of every
Thermal power plant is based on following process:-
1. Coal To Steam
2. Steam To Mechanical power
-
8/6/2019 Training Repor1
10/36
3. Power Generation, Transmission & Distribution.
Coal To Steam
Coal and water are the primary inputs to a thermal power plant.This
process of conversion of water to steam by using heat energy
produced by burning of coal by producing heat takes place in boiler
and its auxiliaries. Coal burns in a furnace located at the bottom part
of the boiler. Feed water is supplied to the boiler drum by boiler feed
pumps, where water is heated and converted into saturated steam.
This is further superheated in the super heaters.
Steam To Mechanical Power
This is the most important process of a power plant. The superheated
steam produced in the boiler at high pressure and temperature is
feed to the turbine giving up heat energy, which is transformed into
mechanical energy on turbine shaft. Thus, mechanical power is
obtained from the turbine shaft.
Power Generation, Transmission & Distribution
Mechanical power produced at the shaft of the turbine is used to
rotate the rotor of an electrical generator that produces electricalpower. The electric power produced by the generator is boosted to a
high voltage by a generator transformer to reduce transmission
losses. This power at EHV i.e. 400 KV is transmitted and distributed
by EHV transmission lines.
Coal To Steam
We are taking coal from coal-yard as Wagon tippler load with the help
of motor on which the conveyer belt is mounted. As Wagon tippler
consist of rotor & pinion. The pinion use to rotate rotor. If in case
Wagon tippler not working then mechanically coal is transfer into
hopper to the belt. We supply coal in coal bunker watching the load
on control room connected Ammeter & Voltmeter. Feeder is used to
put coal on belt. Small motors are connected to belt for support. Coal
being passed through metal detector after passing through metal
detector it is passed through vibrating screen where coal of 5mm
-
8/6/2019 Training Repor1
11/36
seperated from large coal ane fed to crusher then magnetic separator
to remove iron particle from coal. Then fed to crusher to coal bunker.
Metal detector placed over conveyer belt
From coal bunker coal is supplied, to pulverising mill. There are six
coal bunkers supplying coal to each mill and are located at top of the
mills to add in gravity feeding of coal. Each bunker store coal whichcan be used for 12 hrs. Coal is supplied to the mill by the four
barriers. With the help of primary air fan we feed coal to pulveriser
mill with high pressure of air. There are five pipes connected to mill
from on we feed coal to mill and from other four pipes coal dust
comes out from mill after pulverising. The coal is converted into
powered form in the mill. The mill is ball mill of MTPS power station.
With the help of primary air coal dust is feed into ignited boiler. The
coal which we are using for thermal power plant is of class c. In boiler
heat of coal is used to convert water into steam. Coal produces heat
of 330c and that of super heated stem is 535 c.
Steam To mechanical power
The steam which being produced in the boiler are collected in boiler
drum. This boiler drum is mounted on top of the boiler. From boiler
drum steam is passed through super heater. There are three super
heaters between boiler drum and high pressure turbine. Super
-
8/6/2019 Training Repor1
12/36
heaters are used to remove moisture or water droplets from steam
which can decrease efficiency of turbine.
The stem passing through high pressure turbine again given to
reheater where steam is reheated and then used on intermediate
turbine from intermediate turbine steam is directly used on low
pressure turbine. The steam which is being used on low pressure
goes to condenser where it cools. The steam heated in reheater at
535c and fed to intermediate turbine of 20 kg/cm and then fed to
low pressure. And this produces mechanical power on shaft on
turbine. Where the turbine shaft is directly coupled with the
alternator rotor.
Turbine
Types of turbine
1. HP Turbine:-
-
8/6/2019 Training Repor1
13/36
HP turbine is a single flow design with eight stages of blading. Each
stages compromises stationary and moving blades which are
positioned into the rotor mounted on the diaphragms, directs steam
into the rotor mounted on the moving blades. HP turbine is double
shell construction comprising inner and outer casing.
H.P steam enters the H.P turbine inner casing through inlet
connection are mounted on the top and bottom outer casing. The
steam exhausts through the two branches in the bottom half casing
and returns to the boiler to be reheated to increase the temperature
of the steam to 535c so that the efficiency increases.
2. I.P Turbine: -
Intermediate pressure turbine is a double flow design with seven
stages on blading on either side of central steam inlet. Each stage
comprises stationary and moving blades which are positioned so that
the stationary blades mounted on diaphragm, directs the steam into
rotor mounted moving blades. The inner casing , diaphragm carrier
ring and outer casing are made in halves bolted together in the
horizontal centre.
3. L.P Turbine:-L.P Turbine is a double flow design with six stages in each of its front
and rear flow paths. Each stage consists of number of stationary
blades incorporating in the diaphragm located in the casing and a set
of rotating blades mounted on the rotor disc.
Power Generation, Transmission &
Distribution
Mechanical power produced at the shaft of the turbine is used torotate rotor. where magnetic flux produced inside the stator
conductor cuts by rotor conductor an electro motive force will be
induced due to Faradays law of Electromagnetic induction and
produces electricity with the speed of 3000rpm and frequency of
50Hz. As generator consists of stator which consist of stator winding
and rotor consisting of rotor winding. And we have three phase
supply. For cooling purpose of generator we are using hydrogen
which is shielded with oil.
-
8/6/2019 Training Repor1
14/36
GENERATOR
A generator consists of rotor which consists of carbon brushes. The
rotor rotates at 3000rpm in case of any fault if production of plants
stops then we have bearing motor which rotates shaft of turbine
continuously and rotor at 65rpm. This is because if shaft doesntrotates then due to load it may bend.
As generator produces 110MW or generates 11kv output. The output
of generator is step up to 220kv by using step up transformer or
generating transformer. Three phase is fed to station transformer.
There are two station transformer1 and 2 which is step down
transformer. Here 220kv is step down to 6.6kv for internal purpose.
This 6.6kv is step down to 415v for low rating motors. At generating
transformer we are using lighting arrestor which protects G.T from
lighting. This 220kv is given to grid substation. In grid substation we
are using some protective system before distribution we have Bus
isolator, SF6 breaker, Line isolator, CT, lightning arrestor. Similarly we
have two unit auxiliary transformer UAT-1 and UAT-2, which will step
down voltage from 11kv to 6.6kv and it will supply to unit auxiliary
board 1BA, 1BB.
Similarly station transformer will supply to station board 9BA, 9BB.
One unit is tie with other unit because during the failure of any one of
the unit other unit will able to supply.
-
8/6/2019 Training Repor1
15/36
We are using web trap which changes the frequency 50Hz to 500Hz
can be used for communicate in power plant. As three phase fed to
station transformer (Auto transformer) by step up we fed to
switchyard where circuit breaker is closed, when terminal voltage and
frequency matched with the busbar conductor.
Transmission
The KBUNL has capacity to generate 220MW of electricity but only
one unit is working and the second unit is under R&M process. We are
generating 90Mw out of 110MW and giving to the substation. The
transmission is done through three phase, double circuit system. with
the help of transformer, we are converting 11kv to 220kv and fed to
substation. It is then step down to 132kv and feeded to BSEB and
local areas.
Equipments used in transmission of power:-
1. Sub- Station
A. Control Room
B. switchyard
Sub-Station:-
It is the place where power is changed, step down or step up and
transmitted to other places. It consists of various protection
equipments, switching circuits etc.
A substation consists of
a) Bus isolators
b) circuit breaker
c) Line isolator
d) Current transformer
e) CVT
f) Lightning arrestor
g) Wave trap
-
8/6/2019 Training Repor1
16/36
A. Control Room:-
It is the brain of any sub-station. All the necessary steps about the
transmission, protection, charging etc. are carried out in the control
room.
Measuring instruments of the control room:-
a) Relay circuit
b) Fault locator
c) Switch gears
d) Voltmeters
e) Ammeters
f) Power meter
g) CRT screen
h) Battery room
a) Relay circuit:- A relay is a protective device that operates
during faulty condition and gives command to circuit breaker to tripcircuit.
Operating principle:-
1. Electromagnetic attraction
2. Electromagnetic induction
Components of electromagnetic relay:-
1. Shaded pole
2. Watt-hour meter
3. Induction cup
4. Single and double induction loop
b) Fault locator:- A simple beam relay would measure thecurrent seen by the relay with the voltage at the relaying point. By
-
8/6/2019 Training Repor1
17/36
comparing these two quantities the relay measure the line
impedence (z=v/i) up to the point of fault.
c) Switch gear:- Switches are used in sub-station as a devicefor making or breaking the electric circuit in convenient way i.e just
by the simple motion of a knob or a handle to connect together or
disconnect two terminals to which cables are connected. There are
two types of switch gears Air switch and Oil switch.
d) Voltmeter:- It is an instrument, which measures the voltagealong the phase. It actually measures the potential difference
between the two points of the conductors.
e) Ammeter:- It is an instrument, which measures the currentacross the conductor. It is mounted on the panel board. Where staff
on duty can easily watch the readings.
f) Power meter:- These instruments are used to measure thepower in standard units i.e in MW. This instrument is also mounted on
the panel board for easy watch for the operating staff.
g) CRT screen:- It is a computer arrangement in which current
information about the transmission line is seen. The circuit diagramof switchyard and control room is stored in hard disk. It also displays
the current status of the transmission line.
h) Battery room:- This room consists of 3 units of batteriesand charged for emergency purpose. In each unit there are 110
batteries. When power failure is there, then power is supplied by the
battery to keep all the instrument or devices in on status. There are
two types of charger for charging battery 1)Float charger 2)Boost
charger. Float charger is mainly used for charging purpose.
B. Switch yard:-
It is systematic arrangement of various components, where all the
machines or equipments are connected with each other, looping, step
down, step up of transmission line are done here only.
A switchyard consists of following
equipments:-
-
8/6/2019 Training Repor1
18/36
a) Transformer
b) Tower
c) Conductor
d) Insulator
e) Circuit breaker
a) Transformer:-A transformer is an electrical device whichworks on the principle of mutual induction. The
autotransformer used in power station. It has three windings
primary, secondary and tertiary. The 220kv voltage is fed as
input to primary by step down132kv fed MTPS as input.
b) Tower:- Tower is the an important part of transmission line. Astower consists of guard ring. it is located at the bottom of the tower
so that any unauthorised person or animal cannot climb upto the
tower.
We have suspension type tower called as A type tower. The peak
point angle is 0 to 2. In this type conductor is suspended with an
insulator.
B-type : angle lies between (2-15)
C-type : angle lies between (15-30)
D-type: angle lies between (30-60)
-
8/6/2019 Training Repor1
19/36
C) Conductor:- A conductor is very essential equipment which isused for transmission of power. It is generally made of aluminium. It
is hanged on the tower with the help of insulators. Aluminium cost is
cheap and has good conductivity.
D) Insulator:- It is made up of porcelain material which is badconductor of electricity. For transmission purpose generally PIN-TYPE
insulators are used. The capacity of each disk is 20kv.
E) Circuit breaker:- These are mechanical devices designed toclose or open contact members thus closing or opening an electrical
circuit under normal or abnormal conditions. These circuit breakers
are equipped with trip coil connected to relay, design to open breaker
automatically.
Connection with grid to synchronisation:-
1. The terminal voltage of alternator must be equal to the bus-barvoltage.
2. The running speed frequency must be equal to the bus-bar
frequency.
(Ns=120f/P) => (f=PN/120)
Where, f= frequency
P= no. Of poles
N= speed of alternator
3. The terminal voltage of two conductors must be equal to the
two bus- bar terminal to place the external resistance to reduce the
voltage drop.
Light up process
-
8/6/2019 Training Repor1
20/36
MTPS Kanti has direct firing system. In this system, a controlled
quantity of crushed coal is fed to each bowl mill (pulveriser) by its
respective feeders and primary air is supplied from the primary air
fans which drives the coal as it is being pulverized and transports the
pulverized coal through the coal piping system to the coal burners.
There are six pulverisers out of which four are used and two remains
in standby. The raw coal feeders supply 74TPH of coal to each mill.
The pulverized coal and air discharge from the coal burners is
directed towards the centre of furnace to form fire ball. There are 24
tilting, tangentially fired coal burners fitted at the four corners of the
boiler at elevations.
The secondary air heating system supplies secondary air for
combustion in the furnace around the pulverized coal burners and
through auxiliary air compartments directly adjacent to the coal
burner compartments. There are 12 air-atomizing ignitors per boiler,
which initially ignite the coal and air mixture.
Above a predictable minimum loading condition, the ignition becomes
self-sustaining. Combustion is completed as the gases spiral up in the
furnace.
MAIN BOILER COMPONENTS
Boiler is a closed vessel in which water is converted into steam.
There are two types of boilers
a) Fire tube boiler
b) Water tube boiler
The major accessories of a steam-generating unitare listed as follows:-
Furnace
Economiser
Boiler drum
Down comers
Water walls
-
8/6/2019 Training Repor1
21/36
Riser tubes
Superheaters
Reheaters
De superheaters
Furnace:- A boiler furnace is the first pass of the boiler in whichfuel is burned and from which the combustion products pass to the
super heater and second pass of boiler. The combustion process is a
continuous process, which takes place in first pass of boiler and
controlled by fuel input through coal feeders. It is a radiant type and
water-cooled furnace and inclosure is made up of water walls.
The furnace is open at the bottom to allow ash/clinkers to fall freelyinto the furnace bottom ash hopper.
Economiser :- The function of an economiser in a steamgenerating plant is to absorb heat from flue gases and add this as
sensible heat to the feed water before the feed water enters the
evaporative circuit of boiler. This increases the efficiency of the
boiler.
The economiser is placed in the path of the flue gases leaving the
boiler rear gas pass below the rear super heater. The economiser is
continuous unfinned loop type and water flows in upward direction
and gas flows in downward directions.
Boiler drum:- It is a cylindrical pressure vessel withhemispherical ends. It contains two rows of cyclone separators, four
rows of driver boxes, a perforated feed water distribution pipe, and achemical dosing pipe.
The boiler drum is located on the upper front of the boiler, it is
suspended from roof steel work by two u-shaped slings.
It forms a part of the water circulating system of the boiler. The drum
serves mainly two functions.
The first and primary one is that it separates steam from the
mixture of the water and steam discharged into it and to reduce the
dissolved solid contents of the steam to below the prescribed limit of
1 ppm.
-
8/6/2019 Training Repor1
22/36
Secondly, the drum houses all equipments used for purification
of steam after being separated from the water. These equipments are
known as drum internals.
Down comers:- Down comer provide a passage for water fromthe boiler drum to bottom ring header. From bottom ring header
water goes to water walls for heat absorption and conversion into
steam heating. To achive the circulation of water into water walls
boiler circulation pumps are provided in down comers.
Riser tubes:- A riser is a tube through which the mixture of waterand steam pass from an upper water wall header to the steam drum.
Cooling water circuit
A large quantity of cooling water is required to condense the steam in
condenser and in maintaining a low pressure in it. Cooling water may
be taken from the upper side of the river and after passing through
condenser ( where it is heated ).
Where adequate quantity is not available water coming out from the
condenser may be cooled either in cooling pound or cooling tower.
The cooling tower having fans which is rotated with the help of
motors. The blades of fen are set at an angle of 13 to 15. More
angle of blade cause more cooling and more current drop. The motorrotates at 1400rpm.
Cooling tower
-
8/6/2019 Training Repor1
23/36
Types of fan :-
A fan is a device by which the air is made to flow at required velocity
and pressure in a defined path imparting K.E of its impellers to
air/flue gases. This pressure boost is used to create a draught in theair and flue gases system. Fans mainly perform two functions:
1. They supply air required for combustion in the furnace with
required pressure and flow.
2. They evacuate the product of combustion i.e. flue gases into
the atmosphere via chimney.
P.A fan:-
The primary air fan supplies heated air to the coal mills known as
primary air, to give dry and pulverized coal to the furnace for efficient
combustion. There are two P.A fans per boiler. The fan impeller is a
double inlet, centrifugal wheel with backward curved plate blades.
F.D fan:-
The forced draught fan system is provided to supply secondary air
required for pulverized coal combustion in the furnace, air for fuel oil
combustion and over fire air to minimize NOX production.
The F.D fan system comprises of two single stage axial flow, constant
speed, and auto variable pitch fans per boiler. These fans provide
pressurized atomospheric air to the boiler for combustion.
I.D fan:-
The induced draught fan system comprises of three centrifugal
double inlet fans per boiler, two operating and one standby. Each fan
unit consist of a backward curved plate bladed impeller, which is
driven by an electric motor through a variable speed hydraulic
coupling. The I.D fan serves the purpose of evacuating the products
of combustion or the flue gases in the atmosphere via chimney.
Types of pump :-
1.Condensate Extraction pump (CEP):-
The function of condensate extraction pumps is to pump out the
condensate to the deaerator through, L.P heaters. The steam fromthe L.P cylinders exhausts into the condenser shells where it is
-
8/6/2019 Training Repor1
24/36
constrained to flow across the water tubes, through which cooling
water is circulated.
2.Air extraction pump (AEP):-
The function of air extraction pump is to raise and maintain the
vacuum conditions in the turbine main condensers, and to remove air
and other non-condensable gases vented to the condensers from the
various parts of the turbine and feedweater heating system.
3.Boiler feed pump (BFP):-
Boiler feed pump is the most critical component of a power plant. It is
a rotary machine, which is coupled to a motor through variable speed
coupling or turbo coupling. Under normal conditions two 50% boiler
feed water pump sets are run in parallel to undertake the complete
load of feeding the boiler, while the third 50% pump set is on standby
duty.
Types of turbine1. HP Turbine:-
HP turbine is a single flow design with eight stages of blading. Each
stages compromises stationary and moving blades which are
positioned into the rotor mounted on the diaphragms, directs steam
into the rotor mounted on the moving blades. HP turbine is double
shell construction comprising inner and outer casing. H.P steam
enters the H.P turbine inner casing through inlet connection are
mounted on the top and bottom outer casing. The steam exhausts
through the two branches in the bottom half casing and returns to
the boiler to be reheated to increase the temperature of the steam to
535c so that the efficiency increases.
I.P Turbine:-
Intermediate pressure turbine is a double flow design with seven
stages on blading on either side of central steam inlet. Each stage
-
8/6/2019 Training Repor1
25/36
comprises stationary and moving blades which are positioned so that
the stationary blades mounted on diaphragm, directs the steam into
rotor mounted moving blades. The inner casing , diaphragm carrier
ring and outer casing are made in halves bolted together in the
horizontal centre.
3. L.P Turbine:-
L.P Turbine is a double flow design with six stages in each of its front
and rear flow paths. Each stage consists of number of stationary
blades incorporating in the diaphragm located in the casing and a set
of rotating blades mounted on the rotor disc.
Types of heater
1. High pressure heater (HPH):-In the water cycletemperature of feed water from BFP is increased to approx, 130c by
heating it in HP heater. As the heating of feed water in HP heater is
done by the extra steam coming out of the High Pressure Turbine(HPT) hence, it is named as High Pressure Heater (HPH).
2. Low pressure heater(LPH):-In the water cycle,temperature of condensate from CEP is raised to approx. 80c by
heating it in LP heater is done by the extra steam coming out of the
low pressure turbine(LPT) hence, it is known as low pressure heater.
Unit control desk and panel
The operation of each unit is envisaged from the central unit controlroom. It is located in the control bay at 9.0m TG floor. It is adequately
illuminated and is centrally air conditioned. For operation
convenience, the control room front wall has complete glass
panelling for TG hall view and the two double doors for entry from TG
hall.
The control board has a special profile with three sloping surfaces for
mounting a large facias, instruments and controls. The automatic
control station and drive control switches and indications are located
on the first sloping surface. The process indicators/recorders and
-
8/6/2019 Training Repor1
26/36
ammeters are mounted on the second sloping surface and the alarm
annunciation window facias are mounted on the top i.e. third sloping
surface. The unit control board are arranged in logical operating
sequence from the left to right starting with a) air and flue gas, b)
fuel oil, c) ball mills, d) steam & feed water, e) regenerative system,f) turbine and g) generator
Power distribution in KBUNL for
main plant and off-site area
There are two types of power distribution in KBUNL for plant
and its auxiliaries
1. HT System(6.6kv)
2. LT system (415v)
3. DC system(220 V)
-
8/6/2019 Training Repor1
27/36
HT System (6.6kv)
HT power used is of 6.6 kV .there are 2 no. Unit board per unit and 2
no. Station board per unit.
As given in the network drawing .these boards are
Unit-1
1. Unit board 1BA -6.6kv,1250 A.
2. Unit board 1BB-6.6kv, 1250 A
3. Station board9BA-6.6 kv , 1600 A
4. Station board9BB-6.6 kv , 1600 A
Unit-2
1. Unit board 2BA -6.6kv,1250 A
2. Unit board 2BB-6.6kv,1250 A
3. Station board 9BC-6.6 kv , 1600 A
4. Station board 9BD-6.6 kv , 1600 A
Station board
The purpose of this board are to import power to the powerhouse for
its auxiliary supply.Intially power taken from grid 220 kv bus through
station transformer -1 and charged station board 9BA and
9BB.Similarly power taken from grid through station transformer -2
and charged station board 9BC and 9BD
There is provision for coupling of station board 9BA to 9BC and 9BB
to 9BD through Tie breakers at both ends. These board supply power
-
8/6/2019 Training Repor1
28/36
initially to Unit board as well as the areas which are common to both
the units &Off-site areas .
Important feeders are:
1. Station service transformer
2. Cooling tower transformer
3. DM plant transformer
4. ASH handling transformer
5. CHP -6.6kV board through cables
6. FIRE hydrant pump
7. Mulisifyer pump
8. CW pump -3
9. HP Ash water pump A,B,C
Unit Boards
Before running the unit auxiliary power is required for different
activity in power plant so respective unit are charged through bus
coupler as per the drawing
1. 1BA charged through 9BA
2. 1BB charged through 9BB
3. 2BA charged through 9BC
4. 2BB charged through 9BD
After synchronisation of unit Normal Incomer from AUT taken into
service and station bus coupler taken out. Every board has I/C Bkr. ,
Bus PT and outgoing feeders for HT drive and transformers
Important feeders in units board of respective unit
1. BFP
-
8/6/2019 Training Repor1
29/36
2. PA FAN
3. ID FAN
4. FD FAN
5. COAL MILLS
6. CEP
7. Unit service transformer
8. ESP transformer
Breaker used in KBUNL6.6 kv system
BHEL- Make
MOCB - Breaker
LT system (415v)
Main plant
There are two types of LT supply system. One is station service whichis common for both the unit and other is for respective units service.
Station service switchgear(415v)
It has two section charged through station service transformer having
with LT breakers in each section.
Bus coupler provision is there.
Important feeders are:
1. ACW pump-1 and 2
2. Outgoing feeder to compressor MCC
3. Outgoing feeder to station emergency board
4. Station lightning
-
8/6/2019 Training Repor1
30/36
Unit service switch gear(415v)
It has two section each section charged through unit service
transformer having with LT breaker in and bus coupler.
1. Important feeder
2. Outgoing feeder to boiler MCC section a and b
3. Outgoing feeder to turbine MCC section a and b
4. Unit lightning
Boiler MCC
It has two section A and B having with bus coupler mainly it provides
power control to all the LT drive in boiler area.
Important drives are:
1. Mill seal air fan A and B
2. Air preheater lub oil A and B
3. Hydrazine dosing pump A and B
4. Ammonia dosing pump A and B
5. Phosphate dosing pump A and B
Turbine MCC
It has two section having with bus coupler mainly it provides power
control to turbine aux.
Important drives are:
1. BCW pump A,B,C
2. Starting oil pump A and B
3. Drip pump A and B
4. Oil centrifuge
5. Chimney exhaust fan-A and B
Station emergency board
-
8/6/2019 Training Repor1
31/36
It has two sections A and B having with bus coupler. Each section
having with one normal I/C from Stn. Service PCC and one DG set.
Normally the board is charged through the normal I/C in case of
power failure in station DG set started and the board charged
through DG I/C breaker.
Important feeders are:
1. Outgoing feeder to respective unit emergency board
2. Battery charger
3. Inst. Compressor-4
Unit emergency board
It has two I/C one from Unit PCC and other from Stn. Emergency
board. Initially it charged through Unit PCC, in case of power failure
automatically it changes over to emergency supply system.
Important drives are:
1. AC seal oil pump
2. AC EOP
3. AC JOP
4. Turbine barring gear
5. AC scanner fan
6. Unit emergency lighting
Turbine v/v and damper MCC
It has two source one from Turbine MCC and other from Unit
Emergency board having with auto change over ckt. Mainly supply
power to all the valve control in turbine areas.
Boiler v/v and damper MCC
-
8/6/2019 Training Repor1
32/36
It has two source one from Boiler MCC and other from Unit
Emergency board having with auto change over ckt. Mainly supply
power to all the valve and damper control in boiler areas.
DC system
There are common DCDB of 220V dc system having with two set of
unit batteries and two charger one main and other standby.
Important drives are:
1. DC seal oil pump
2. DC JOP
3. DC EOP
4. DC scanner fan
5. DC lighting
6. DC supply to all HT /LT sw.gr for controlled and protection
system .
Like main plant in all the offsite area there are LT SG. Gear .They are
charged through their respective transformer to provide power toelectric drives of that area
Offsite areas are:
1. DM PLANT
2. RAW WATER
3. COOLING TOWER
4. ASH HANDLING PLANT
5. FUEL OIL PUMP HOUSE
6. COMPRESSOR
7. COAL HANDLING PLANT
-
8/6/2019 Training Repor1
33/36
GENERATOR
125MVA, 110KW, 11KV, 6050A, 0.88PF ,3000RPM,50HZ
Hydrogen cooled, with static excitation used in KBUNL
BHEL Make.
Initially power taken from grid for unit light-up process started. After
parameter of steam like pr. and temp. reached turbine rolling started
.After attaining 3000 RPM. Exitation field breaker made on when
generate output voltage attain then generator synchronised with
grid. the AVR system controlled the generator o/p voltage as per the
load. The generating power at 11kv is step-up by G.T. to220kv with
same power and export to the grid through 220kv bus in switchyard.
Switchyard
There are two 220kv and 132kv bus system in switch yard they are
coupled with 02 nos. IBT. KBUNL takes power from grid through
220kv line and export power through both 220kv and 132kv line
Details of MOCB at KBUNL:
For station incomer / Tie breaker
Voltage 7.2kv
-
8/6/2019 Training Repor1
34/36
Frequency 50hz
Normal current 1600A
RVM Breaking capacity 40kA
Short time current 40KA
Duration 3sec
Making capacity 102KAP
RF withstand 35kv
Impulse 75kvp
Shunt trip coil 220VDC
Spring release coil 220VDC
Type LM12/16J
SR.NO. 9026558
Division BHOPAL
Year 1983
For station feeder/station transformer
Voltage 7.2kv
Frequency 50hz
Normal current 630A
RVM Breaking capacity 40kA
Short time current 40KA
Duration 3sec
Making capacity 102KAP
RF withstand 35kv
-
8/6/2019 Training Repor1
35/36
Impulse 75kvp
Shunt trip coil 220VDC
Spring release coil 220VDC
Type LM12/6J
SR.NO. 9026564
Division BHOPAL
Year 1983
For unit incomer/ Bus coupler breaker
Voltage 7.2kv
Frequency 50 hz
Normal current 1250A
RVM Breaking capacity 40kA
Short time current 40KA
Duration 3sec
Making capacity 102KAP
RF withstand 35kv
Impulse 75kvp
Shunt trip coil 220VDC
Spring release coil 220VDC
Type LM12/12J
SR.NO. 9026598
Division BHOPAL
Year 1983
-
8/6/2019 Training Repor1
36/36