Tower Smoke Management - System Planning, Design & Testing
Kirk Rosenbaum, CCP, PQP Senior Commissioning Manager KEO International Consultants
INTRODUCTION Kirk Rosenbaum, CCP, PQP
Senior Commissioning Manager
• 30 + Years Experience in Design,
Construction Industry
• 12 + Years Experience Exclusively
in the Area of Commissioning
• 10 + Years Experience in Fire Life
Safety Review and Inspection
• Managed the Commissioning of
Over 2,500,000 m2 of new buildings
and 250,000 m2 of existing
buildings
• Former Director and Treasurer of
the Building Commissioning
Association
Need for Tower Smoke Management
Sample GCC Tower Fire Events 2012
Code & Standard Design Requirements
NFPA 92 – 2012;
Standard for Smoke Control Systems
5.2.1 – Pressure differential across smoke barriers shall be 12.5 Pa for fully sprinklered buildings. 5.2.2 – Pressure differential across doors shall not cause the force required to open the doors to exceed 133 N. 5.3 – Stairways are to be pressurized to a minimum of 12.5 Pa and a maximum level that causes door opening forces to be less than 133 N. 5.4 – Elevators shall be considered a separate smoke zone when smoke control is required. 5.3.5.1 – Vestibules shall not be required, but shall be permitted as part of a building smoke management system.
Code & Standard Design Requirements
Qatar Civil Defense
Fire Safety Standards
FSS 2.2.13 – Smoke Stop or Fire Fighting Lobby required when: (i) Stairway has no natural light or ventilation, or (ii) Stairway traverses more than 4 stories (incl. basements), or (iii) Has a habitable height more than 28 meters above Ground. All Fire Fighting Lifts shall be provided with a Fire Fighting Lobby. Mechanical Ventilation/Pressurization to be provided at 10 Air Changes per Hour (ACH). Mechanical equipment is to be provided with 100% stand-by power. Smoke Stop Lobbies shall be no less than 3 square meters in area. Fire Fighting Lobbies shall be no less than 6 square meters in area with no dimension less than 2 meters.
Code & Standard Design Requirements
Qatar Civil Defense
Fire Safety Standards
FSS 2.2.13 – Basements exceeding one story in depth require a Smoke Stop Lobby adjacent to the Fire Fighting Lift and its adjacent stairway only. Other basement stairways do not require Smoke Stop Lobbies. FSS 6.6.3 – Fire Lift required when building habitable height exceeds 23 meters above ground level or 9 meters below ground level. FSS 1.5 – A high-rise building exceeding 30 storeys shall be provided with refuge floors at an interval not exceeding 20 storeys. A high-rise building exceeding 30 storeys shall be provided with refuge floors at an interval not exceeding 20 storeys. A minimum of 50% of the gross floor area of the Refuge Floor must be a protected Holding Area.
Code & Standard Design Requirements
Qatar Civil Defense
Fire Safety Standards
FSS 1.5 – The Holding Area is to be ventilated: (ii) Naturally ventilation requires the total area of the ventilation openings to not
be less than 25% of the gross floor area of the Holding Area. (iii) Mechanical ventilation is also acceptable as long as the equipment is powered
via 2-hour fire rated cables and 100% stand-by power is available.
Low-Rise Building
• < 23 meters above ground
• < 9 meters below ground
• No smoke mgmt system required
Low-Rise Bldg w/ Deep Basement
• < 23 meters above ground
• > 9 meters below ground
• Fire Lift Required
• Bsmt Stair Pressurization Required
Mid-Rise Building
• > 23 meters above ground
• > 9 meters below ground
• Fire Lift Required
• Bsmt & Tower Stairs Require Pressurization
High-Rise Bldg w/ Refuge Floor
• > 30 storeys above ground
• > 9 meters below ground
• Fire Lift Required
• Evacuation Lift may be required
• Bsmt Stairs, Tower Stairs, and Refuge Require Pressurization
High-Rise Bldg w/ Fire Floor Isolation
• Same physical features as High-Rise
• In addition to standard High-Rise smoke mgmt, two floors above and below the fire floor are pressurized.
Typical Floor Plan (No Fire Floor Isolation)
Pressurized Floor (Fire Floor Isolation)
Typical Floor Plan (Fire Floor Isolation)
Code & Standard System Sizing Method Recommendation and Test Requirements
Document NFPA 92 - 2012 Qatar Civil Defense - FSS
System Sizing Method Recommendation
SFPE TR 82-4 Designing Stair Pressurization Systems (Similar to British Standard Method) ASHRAE Chapter 52 – Fire and Smoke Management
None Provided
System Test Requirement
Maintain pressure differential across closed doors when (1) 3* Stairway Doors are
open, or (2) Lifts parked with doors
open.
None Provided
* The number of open stairway doors is determined by the local fire authority and is not NFPA prescribed.
Calculation – ASHRAE 52
QSP = 0.839 * Asb * (Delta-Psb)1/2 + 0.452 * AOD * (Delta-Psb)1/2
QSP = Fan Flow Rate for Pressurization of Stairway to Required Static Pressure (m3/s)
HS = Total Height of Stairway
Asb = Total Flow Area between Stairway and Building (m2) - walls and closed doors
AOD = Flow Area through Open Doors (m2)
Delta -Psb = Primary Pressure Difference between Stairway & Building (Pa)
Calculations – Industry Leakage Data
ASHRAE HANDBOOK 2007 Chapter 52
• Field tests have repeatedly shown that ‘LOOSE’ wall construction should be utilized for system sizing in the region.
Calculations – Industry Leakage Data S
ele
ct D
oo
rs a
s A
pp
rop
ria
te f
or
the
Pro
ject
(B
lue
Bo
x C
an
Be
Ign
ore
d)
Calculations – Industry Leakage Data
Important Note: If a stairway has a door with double-leafs, BOTH leaves of the door must be open for testing and it
only counts as One Door Open.
Calculations – Industry Leakage Data
Data from a Tamura and Shaw Study, 1976
Typical System Layout
Air Injection Points
• Single point injection OK for lifts to approx. 40 storeys
• Single point
injection OK for stairways of approx. 15 to 20 storeys, but will not satisfy Bsmt Stairways
Recommended System Layout
Air Injection Points
• Inject air to Lift Shafts at top, bottom, and approximately every 40 storeys
• Inject air to
stairways at top and approximately every 15-20 storeys
• Inject air to all basement stairways
Lessons Learned (Page 1 of 5)
• Pressurization systems to be sized based on
ASHRAE 52 methodology with ‘loose’ leakage rates
and appropriate safety factors.
• Stack effect is negligible based on field test results and
may generally be discounted in system sizing
calculation.
• Wind effects are negligible based on field testing and
may generally be discounted in system sizing
calculation unless stairways or lift shafts are located
against an exterior wall.
Lessons Learned (Page 2 of 5)
• Pressurization system intakes and reliefs should not be
directly exposed to wind pressure and need to have
tightly sealing dampers. Either condition may allow
humid outside air to enter a stairway or shaft and
could result in mould issues.
• Masonry shafts are not appropriate as air plenums for
pressurization systems; excessive leakage and
excessive friction loss.
• For towers taller than 40 storeys single point air
injection at the top of the building is generally
insufficient for pressurizing lift shafts.
Lessons Learned (Page 3 of 5)
• Pressurization system fans should be equipped with
VFDs for the setting of fan maximum speed.
• Pressurization systems should be equipped with
adjustable pressure relief dampers to prevent system
over-pressurization of stairways. Pressure sensor
control may have excessive response time.
• Basement stairs should be equipped with stand-alone
pressurization systems and not combined with tower
pressurization systems.
Lessons Learned (Page 4 of 5)
• Pressurization system fans should be equipped with
VFDs for the setting of fan maximum speed.
• Pressurization systems should be equipped with
adjustable pressure relief dampers to prevent system
over-pressurization of stairways. Pressure sensor
control may have excessive response time.
• Basement stairs should be equipped with stand-alone
pressurization systems and not combined with tower
pressurization systems.
• For towers taller than 15 - 20 storeys single point air
injection at the top of the building is generally
insufficient for pressurizing stairways.
Lessons Learned (Page 5 of 5)
• Construction schedules should prioritize early
completion of pressurization systems and the execution
of pressurization system testing. (Failure to validate
the systems early could result in extensive delays
to the approval for occupancy for the project.)