towards factors affecting delays in construction projects: a … · 2017-06-20 · manage delay...

17
Dynamic Research Journals (DRJ) Journal of Economics and Finance (DRJ-JEF) Volume 2 ~ Issue 1 (January, 2017) pp: 12-28 www.dynamicresearchjournals.org www.dynamicresearchjournals.org 12 | Page Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe 1 Thabani Nyoni and 2 Wellington G. Bonga 1 Corresponding Author:T Nyoni - [email protected] Received 20 January, 2017; Accepted 25 January, 2017; Published 31 January, 2017 © The author(s) 2017. Published with open access at www.dynamicresearchjournals.org Abstract: -The problem of delays in the construction sector is a global phenomenon and the construction sector in Zimbabwe is no exception. This research seeks to empirically investigate the factors affecting construction delays in Zimbabwe. A questionnaire survey was used for data collection. The research employed heterogeneous sampling to select target population and one-hundred and twenty (120) questionnaires were completed and analyzed. Using a simple ordinal scale, based on a 5-point Likert Scale, professionals, contractors and consultants expressed their views on the relative importance of forty-six (46) pre-selected factors on construction project delays. Data was analyzed using the Relative Importance Index (RII). The results show that delay in progress payment by owner, difficulties in financing the project and change orders are amongst the twenty-seven (27) most important factors causing delay in construction projects in Zimbabwe. The study recommends attention to be made to the identified delay factors, paying particular attention to the twenty-seven (27) most ranked factors. Keywords: - Client Related Factors, Construction Projects, Delay, Equipment Related Factors, Owner Related Factors, Relative Importance Index, Zimbabwe. JEL Codes: C02, L11, L23, L25, L52, L74, L87, L91, M11, O31. I. INTRODUCTION Delays in construction projects are problems faced in the entire world (Bangash, 2016) and Zimbabwe is not an exception. Construction delay can be defined as the time overrun either beyond the contract date or beyond the date that the parties agreed upon for delivery (Assaf & Al-Hejji, 2006). In the same line of argument, Awari et al (2016) defined delay as the time overrun & cost overrun either beyond completion date specified in a contract or beyond the date that the parties agree upon for delivery of a project. According to Zack (2003) delay is an act or event which extends required time to perform or complete work of the contract and manifests itself as additional days of work. In the same line of argument, Mohamad (2010) agitates that delay is an act or event that extends the time to complete or perform an act under the contract. Delay, as described by Aibinu & Jagboro (2002) is a situation where the contractor and the project owner jointly or severally contribute to the non-completion of the project within agreed contract period. Alkhathani (2004) states that delay can be defined as extra time required to finish a given construction project beyond its original planned duration, whether compensated for or not. However, for the purposes of this research, the study adopts the definition of delay given by Assaf & Al-Hejji (2006). Delay in projects is counted as a common problem in construction projects (Sullivan & Harris, 1986). Delay apparently means loss of income according to and for the owner or client. In case of contractor, delay implies higher costs due to longer work time, labour cost increase and higher fabrication costs. While on-time completion of construction project is a signal of project efficiency and success as argued by Mansfield et al (1994), Anees & Sabarinathan (2016) and Al Hammadi & Nawab (2016), there are many unpredictable factors resulting from various sources affecting construction projects. Although there is no consensus on the factors affecting construction delay, it is generally understood that construction delay is the most critical problem causing failure to deliver the project in time, within a stipulated budget constraint, and expected quality. In Zimbabwe, just like in any developing country, the construction sector is a key barometer of economic performance; therefore it is vital to take control of the factors affecting construction project delay.

Upload: others

Post on 02-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Dynamic Research Journals (DRJ)

Journal of Economics and Finance (DRJ-JEF)

Volume 2 ~ Issue 1 (January, 2017) pp: 12-28

www.dynamicresearchjournals.org

www.dynamicresearchjournals.org 12 | P a g e

Towards Factors Affecting Delays in Construction Projects: A

Case of Zimbabwe

1Thabani Nyoni and 2Wellington G. Bonga

1 Corresponding Author:T Nyoni - [email protected]

Received 20 January, 2017; Accepted 25 January, 2017; Published 31 January, 2017 © The author(s) 2017. Published with open access at www.dynamicresearchjournals.org

Abstract: -The problem of delays in the construction sector is a global phenomenon and the construction sector

in Zimbabwe is no exception. This research seeks to empirically investigate the factors affecting construction

delays in Zimbabwe. A questionnaire survey was used for data collection. The research employed heterogeneous

sampling to select target population and one-hundred and twenty (120) questionnaires were completed and

analyzed. Using a simple ordinal scale, based on a 5-point Likert Scale, professionals, contractors and

consultants expressed their views on the relative importance of forty-six (46) pre-selected factors on construction

project delays. Data was analyzed using the Relative Importance Index (RII). The results show that delay in

progress payment by owner, difficulties in financing the project and change orders are amongst the twenty-seven

(27) most important factors causing delay in construction projects in Zimbabwe. The study recommends attention

to be made to the identified delay factors, paying particular attention to the twenty-seven (27) most ranked factors.

Keywords: - Client Related Factors, Construction Projects, Delay, Equipment Related Factors, Owner Related

Factors, Relative Importance Index, Zimbabwe.

JEL Codes: C02, L11, L23, L25, L52, L74, L87, L91, M11, O31.

I. INTRODUCTION Delays in construction projects are problems faced in the entire world (Bangash, 2016) and Zimbabwe is not an exception. Construction delay can be defined as the time overrun either beyond the contract date or beyond the date that the parties agreed upon for delivery (Assaf & Al-Hejji, 2006). In the same line of argument, Awari et al (2016) defined delay as the time overrun & cost overrun either beyond completion date specified in a contract or beyond the date that the parties agree upon for delivery of a project. According to Zack (2003) delay is an act or event which extends required time to perform or complete work of the contract and manifests itself as additional days of work. In the same line of argument, Mohamad (2010) agitates that delay is an act or event that extends the time to complete or perform an act under the contract. Delay, as described by Aibinu & Jagboro (2002) is a situation where the contractor and the project owner jointly or severally contribute to the non-completion of the project within agreed contract period. Alkhathani (2004) states that delay can be defined as extra time required to finish a given construction project beyond its original planned duration, whether compensated for or not. However, for the purposes of this research, the study adopts the definition of delay given by Assaf & Al-Hejji (2006). Delay in projects is counted as a common problem in construction projects (Sullivan & Harris, 1986). Delay apparently means loss of income according to and for the owner or client. In case of contractor, delay implies higher costs due to longer work time, labour cost increase and higher fabrication costs. While on-time completion of construction project is a signal of project efficiency and success as argued by Mansfield et al (1994), Anees & Sabarinathan (2016) and Al Hammadi & Nawab (2016), there are many unpredictable factors resulting from various sources affecting construction projects. Although there is no consensus on the factors affecting construction delay, it is generally understood that construction delay is the most critical problem causing failure to deliver the project in time, within a stipulated budget constraint, and expected quality. In Zimbabwe, just like in any developing country, the construction sector is a key barometer of economic performance; therefore it is vital to take control of the factors affecting construction project delay.

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 13 | P a g e

Overview of the Economy and the Construction Industry of Zimbabwe Zimbabwe, once touted as the Jewel of Africa at Independence in 1980, has over the years acquired a reputation as the sick man of the Southern Africa region, with disastrous economic policies, political instability and a peculiar inability to get itself out of often self-inflicted difficulties (Bayai & Nyangara, 2013). Over the past years, the economic environment in Zimbabwe has faced a myriad of challenges following the inception of the multicurrency economy (dollarization) in 2009 (Gondo et al, 2016). Zimbabwe’s economy is contracting, with critics blaming policy inconsistency and toxic prescriptions such as the Economic Empowerment policy compelling foreign investors to cede at least 51% shareholding to locals (Ndebele, 2016). Financial and liquidity crises have characterized the Zimbabwean economy for the past five years as companies find it difficult to recover from the decade long hyperinflationary economic environment that forced the government to demonetize the local Zimbabwean dollar and adopted a wide range of foreign currencies chief amongst them being the United States dollar (Gondo et al, 2016). Zimbabwe’s economy is regressing due to stagnation, low productivity and deflation (Ndebele, 2016). The construction industry in Zimbabwe has not been spared by the fragile economic environment prevalent in Zimbabwe. There is a French dictum which says: “When the construction industry prospers everything prospers”. This dictum is arguably relevant in the Zimbabwean scenario in the sense that the construction industry in Zimbabwe has a lot of significance to the achievement of national socio-economic development goals enshrined in Zimbabwe’s current (October 2013-December 2018) economic blue-print, ZimAsset (Zimbabwe Agenda for Sustainable Socio-Economic Transformation) and these include the construction of housing, schools, hospitals, roads, power systems, irrigation and agriculture systems, urban and rural water supply and sanitation systems as well as maintenance and repair of existing infrastructure. It is indisputably true, as argued by Khan et al (2014), that the construction sector is positively related to success of any economy. Actually, Attar et al (2012) noted that construction is a key sector of the national economy for all countries around the world, as traditionally it takes up a big portion in the nation’s total employment and its significant contribution to a nation’s revenue as a whole. In the 1990s, construction as an industry employed about 100 000 people; in 2011, only 30 000 workers had jobs in this industry, indicating a decline of about 60% in employment capacity (Zimbabwean Independent, 2011). In Zimbabwe, the construction industry has the potential to account for at least 20% of the country’s annual GDP (Bulawayo24News, 2011; World Bank, 2012). According to ZimStat (2014), the construction industry contributed approximately 3% to Gross Domestic Product (GDP) for the year 2014. ZimAsset growth projections show that the construction sector is expected to grow as high as 15% (of GDP) by 2018. Zimbabwe, as noted by the Zimbabwean Independent (2011), would require approximately $15 billion for infrastructure development between 2011 and 2016. The construction industry is an important sector of the Zimbabwean economy as already emphasized by Chigara & Moyo (2014) and Nyoni & Bonga (2016). Through its backward and forward linkages, the construction industry provides means of production for other industries or commodities to be consumed. Khan et al (2014), notes that the construction sector plays a significant role in producing wealth and providing a better quality of life to the nation that is essential for development of the nation. However, the construction sector’s success depends on meeting certain objectives within stipulated time and budget constraints. This can only happen if construction projects are executed in time, without delay.

Knowledge gap According to Assaf & Hazmi (2006), construction delays play a key role in in any project success. Thus, according to Al-Khali & Al-Ghafly (1999), investigation is required into the problem of delays in order to better manage delay situations and mitigate the consequences of such delay. This study apparently fills a gap in knowledge of factors affecting delay of construction projects in Zimbabwe. Understanding of such factors may help construction project managers and policy makers to find out the main causes and their significance, in order to not only minimize and avoid the impact of delays in construction projects; but also develop new intervention strategies aimed at curbing delays and improving construction business performance in terms of sustainability, productivity, value addition to clients, profitability and competitiveness. It is envisioned that the result of the study will also assist construction firms to reduce the high incidence of delays in the completion of projects and thereby increase efficiency in the use of resources.

Purpose of the study The time required to complete construction projects is often more than specified time in Contract (Al Hammadi & Nawab, 2016). It is very rare to see that a construction project is completed on time (Baldwin & Manthel, 1971; Arditi et al, 1985; Assaf et al, 1995; Vidogah & Ndekugri, 1997; Shashid et al, 2015). In Zimbabwe, delays are one of the biggest problems in construction firms. Delays have an adverse impact on project

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 14 | P a g e

success in terms of time, cost, quality and safety (Association of Project Managers, 2006; Arditi & Pattanakitchamroon, 2006). The effects of construction delays, however, are not confined to construction companies, but can influence the overall economy of a developing country like Zimbabwe, where the construction industry is a driver of economic growth as argued by Nyoni & Bonga (2016). The most serious consequence of construction delay is that it sends bad signals to foreign investors thereby slowing down the national progress. There is need to conduct a detailed empirical investigation and identification of delay factors and then select the right actions to counter these delay factors within cost and maintain quality (Baldwin & Manthel, 1971; Arditi et al, 1985; Ireland, 1986; Sullivan & Harris, 1986; Assaf et al, 1995; Vidogah & Ndekugri, 1997; Al-Momani, 2000). Against this background, this research serves the purpose of empirically investigating the factors affecting construction delay in Zimbabwe.

Research questions 1) What are the factors affecting delays in construction sector? 2) What are the main factors affecting delay in the construction sector in Zimbabwe? 3) What is the impact of each pre-selected factor? 4) What is the relative rank in terms of importance of each pre-selected factor?

Research Framework The study, in order to attain its objectives, has proposed a framework which links construction project delay to various categories of the impacting factors as displayed in Figure 1 below:

Figure 1: Conceptual Framework

Source: Author’s design

Organisation of the study The study comprises of eight (8) sections and these are introduction, difficulties faced by the construction industry in Zimbabwe, literature review, materials and methods, data presentation and interpretation, results and discussion, recommendations and conclusion; in their chronological order

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 15 | P a g e

II. DIFFICULTIES FACED BY THE CONSTRUCTION INDUSTRY IN ZIMBABWE Construction industries in all countries face many difficulties and challenges (Gale & Fellows, 1990; Ofori, 1990). However, in developing countries (like Zimbabwe), these difficulties and challenges sit alongside the general situation of socio-economic stress, chronic resource shortages and a general inability to deal with key issues (Ofori, 2000). UNIDO (1993) argues that construction is one of the first industries to feel the effects of an economic recession. In Zimbabwe the construction sector has been mostly affected during the period leading to the 2008 hyperinflationary era. During that period, the construction sector was barely exposed to various financial and business risks that made the development of the sector difficult. The construction sector in Zimbabwe is characterized by perennial finance related problems such as high cost of financing and difficulty in getting loans. Employers in the construction sector continue to lament over high costs of production. This has been worsened by the current liquidity crisis coupled by both political uprising and gross macroeconomic mismanagement. Mhlanga (2016) noted that the cash crises, high rental costs, and lack of funding are threatening the survival of Small to Medium Enterprises (SMEs) in the country. Zimbabwe, as noted by Mpofu (2016), is in the grip of a serious cash crunch, which has worsened gradually since December 2015 due to dwindling exports and weakening regional currencies. More so, construction activity in Zimbabwe draws mostly on unskilled labour. Chigara & Moyo (2014) and Nyoni & Bonga (2016) found that lack of experienced labour is also a common problem in the construction sector in Zimbabwe. Moavenzadeh (1978) posits that although labour is abundant in developing countries (like Zimbabwe) there tends to be a shortage of skilled labour. Lack of highly skilled and trained workers in the construction industry in Zimbabwe could be attributed to high capital flight experienced in the country owing to economic-hardships. This has seen more workers crossing borders in search of greener pastures (Nyoni & Bonga, 2016). Furthermore, the construction sector in Zimbabwe also faces difficulties in terms of fraudulent practices and the inability to adopt best practices. In fact, Zimbabwe has suffered a lot due to corruption and nepotism in all sectors of the economy. However, corruption and nepotism in the construction sector distort the competitive nature of the industry as there will be no level ground with other innocent stakeholders. It is also unfortunate to note that the construction industry in Zimbabwe is still a very dangerous industry in which to work. According to ZimStats (2013), the Building and Construction industry experienced 119 332 incidences of injuries and 307 fatalities in 2013 alone. Delay in construction projects is considered one of the most common problems causing a multitude negative effect on the project and its participating parties (Awari et al, 2016). In the same line of argument, Divya and Ramya (2015) agitate that construction delay is considered to be one of the most recurring problems in the construction industry and it has an adverse effect on project success in terms of cost, time, quality and safety. Delay is one of the most prominent and recurring difficulties faced in the construction sector in Zimbabwe. Frequent and lengthy delay of construction projects has almost become a normal way of doing business in Zimbabwe.

According to Awari et al (2016), companies would be able to avoid or minimize these delays if major contributing factors were identified and planned for in a timely manner. Assessing delays, as argued by Al-Khali & Al-Ghafly (1999), can provide insights for early planning to control these factors and improve project performance.

In the same line of argument, Agu & Ibe (2016) agitate that delay factors are very crucial within a construction project and it is vital that all stakeholders must have certain knowledge regarding this issue in order for the project to be completed effectively and satisfactorily. Therefore, the study seeks to investigate the delay factors affecting construction projects in Zimbabwe in order to help industry practitioners reach their intended goals with greater efficiency.

III. LITERATURE REVIEW

Construction industry involves several complex issues all of which are invariably of great importance to the parties of the construction contract. These issues concern entitlement to recover costs of delay or the necessity to prolong the project with the consequential entitlement to recovery costs for adjustments to the contract schedules. Questions arise as to the causes of delay and assigning of fault often evolves into disputes and litigation (Bolton, 1990). Today, many stakeholders in construction are becoming increasingly concerned about the duration of construction projects because of increasing interest rates, inflation and commercial pressures (Nkado, 1995) and its potential to result in negative consequences such as disputes and claims leading to arbitration or litigation

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 16 | P a g e

Related Studies Baldwin et al (1971) examined the subject of delays and concluded that weather, labour supply and subcontractors’ scheduling were the three major causes of delay. Assaf et al (1995) investigated delay in construction and identified fifty-six (56) causes of delay that were grouped into nine (9) major categories. Their study found that the finance category ranked highest whilst the environment category ranked lowest. Chan and Kumaraswamy (1997) conducted a survey in Hong Kong construction projects to evaluate the relative importance of 83 delay factors and found five main delay factors: poor risk management and supervision, unforeseen site conditions, slow decision making, client-initiated variations and work variations. Assaf and Al-Hejji (2006) conducted a survey on time performance of different types of construction projects to determine the causes of delay and their importance to each of the project participants (owners, contractors and consultants). The authors identified seventy-three (73) causes of delay and found out that only twenty-six (26) of these factors were most important. Aigbavboa et al (2014) looked at construction project delay in Zambia and found out that delay in payments and difficulties in financing projects by the contractor among others were the major causes of construction delays. Bangash (2016) analyzed the causes of delays in construction projects in Pakistan and found that efficient communication between parties and management skills are critical items in contractor related factors. Anees and Sabarinathan (2016) studied delay factors in the Indian building construction and concluded that the most important factors were delay in payments, shortage of equipment and ineffective planning and scheduling. Zewdu (2016) examined construction projects delays and their antidotes for the Ethiopian construction sector and revealed low level application of techniques and software packages for project planning and time control.

IV. MATERIALS AND METHODS The study used a qualitative approach and data was gathered using a questionnaire approach. The questionnaire was built around factors affecting delay in construction projects drawn from previous studies and is comprised of both structured and unstructured questions. To ensure validity of the questionnaire, a pilot study has been undertaken. The pilot study was specifically done to check clarity and appropriateness of questions, check the range of responses and finally check the efficiency with which the questionnaire will be completed by the respondents. Hand delivery and emailing of questions to various stakeholders in the construction industry was done to aid the study in answering its research questions. The target population of 120 respondents was selected using heterogeneous sampling.

Data Analysis Approach The Relative Importance Index (RII) was used herein to determine respondents’ perceptions of the relative importance of the pre-selected delay factors. The RII index was computed based on Nyoni & Bonga (2016) approach;

Where n1, n2, n3, n4, and n5 are the number of respondents who selected: (1) very weak, (2) weak, (3) fair, (4) strong and (5) very strong. The RII technique aids in finding the contribution a particular variable makes to the prediction of a criterion variable both by itself and in combination with other predictor variables (Johnson & Breton, 2004), thus making it suitable for this research.

Questionnaire Discussion The design philosophy of the questionnaire was based on the fact that the questions had to be simple, clear and understandable for the respondents and at the same time be easily interpreted by the researcher. Factors affecting delay were derived from both empirical and theoretical literature reviewed. The questionnaire had three parts that allowed the study to extract relevant and useful information to answer research questions. Section A had 46 pre-selected, closed-ended (structured) questions; these are the factors which were identified from literature review and categorized into 12 groups namely Owner, Contractor, Consultant, Client, Labour, Design team, Contract, Material, Contractual relations, Equipment, Project and External related. The questions in this section were measured using a simple ordinal scale based on a 5-point Likert scale comprising of ratings from 1 to 5; 1 indicates the least impact while 5 indicates the greatest impact. The respondents were asked to tell the extent to which a particular factor affected delay in their organization. Section B had four open-ended (un-structured)

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 17 | P a g e

questions which were designed in a special way so as to capture “other” factors or the so-called omitted variables, the ones that were not identified by the researcher but still exist to affect delay. Section C had the demographics of the respondents such as age, sex, education, work experience and profession, whose primary purpose was to describe the respondents to effectively ensure reliability and strengthen research results.

Demographics A total of 120 questionnaires were completed and analyzed. The respondents’ construction industry work experience ranges from less than a year to up to more than fifteen years; while respondents’ education ranges from O’ Level up to Postgraduate Level and their ages range from at least 21 up to more than 55 years. The respondents were made up of 29 contractors (approximately 24.2%), 23 consultants (approximately 19.2%) and 68 professionals (approximately 56.7%). The demographics served the main purpose of strengthening the research results; for example, responses differed according to the work experience and therefore the researcher had to consider responses from experienced respondents as more reliable since they have seen it all. The demographics of the respondents who took part in this study show that they had relevant technical experience to provide valid assessments of the factors presented in the questionnaire.

V. DATA PRESENTATION AND INTERPRETATION Table 1: Descriptive Statistics

Group of factors No. of

factors

No. of

factors with

RII > 50%

Mean

RII

Standard

deviation

Minimum

RII

Maximum

RII

Range

[Max-Min]

Owner related 6 6 69.2 9.6 59.3 79.9 20.6

Contractor related 6 2 45.2 18.3 19.8 74.7 54.9

Consultant related 5 3 44.2 18.4 17.1 61.5 44.4

Client related 2 2 69.1 2.3 67.4 70.7 3.4

Labour related 4 2 44.9 19.9 17.5 62.7 45.2

Design team related 7 3 38.5 23.6 10.1 70.4 60.3

Contract related 2 1 51.7 16.4 40.1 63.3 23.2

Material related 3 1 45.7 12.5 31.8 55.9 24.1

Contractual relations related

3 3 55.3 3.1 51.7 57.4 5.7

Equipment related 2 2 68.8 7.5 63.5 74.1 10.6

Project related 3 2 53.0 18.6 32.8 69.4 36.6

External related 3 0 34.8 20.4 11.2 47.1 35.9

Overall - - 51.7 14.2 35.2 65.6 30.4

Table 1 above shows various statistic measures of the Relative Importance Index. The Design team related category which consisted of 7 factors, had the highest number of factors whilst the Client related, Contract related and Equipment related categories, had only 2 factors each; being the least number of factors per category. The Owner related and the Contractor related categories had 6 factors each whilst the Material related, Contractual relations related, Project related and External related categories had 3 factors each. The Consultant related category had 5 factors whilst the Labour related category had 4 factors. In the Owner related group, the number of factors with RII › 50% were 6, while the Consultant related, Design team related and Contractual relations related groups each had 3 factors that had RII › 50%. The Contractor related, Client related, Labour related, Equipment related and Project related categories, each had 2 factors that scored above 50%. The Contract related and Materials related groups, each had only 1 factor that scored above 50%. All the factors that fell under the External related category scored below 50%. Based on mean RII, Owner related factors; whose average RII is 69.2%, are the most critical factors amongst the 12 categories, followed by Client related and Equipment related factors with average RIIs of 69.1% and 68.8% respectively. The External related factors have an average RII of 34.8% showing that they are the least important in terms of their overall effect on delay in construction projects in Zimbabwe. The overall mean RII is approximately 52%, which implies that all the factors are important; regardless of individual factor rankings. Hence all the factors ought to be addressed, although greater effort should be directed to the most ranked factors. The standard deviation satisfies the basic criterion for a measure of variation. The more variation there is in the observed values, the larger the standard deviation in question. The table above shows that there is more variation amongst the External related factors whose standard deviation is 20.4% while Client related factors exhibit the least variation, with standard deviation of 2.3%. The table above also shows the minimum RII, maximum RII and

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 18 | P a g e

range of RII (a measure of spread) for each group of factors. Overall variability is shown by standard deviation of approximately 14% and a RII range of approximately 30%.

The distribution of the factors affecting delay in construction projects in Zimbabwe is shown below: Figure 2: The 5-Number summary showing the distribution of the RII

Figure 2 above is a Box & Whisker Plot showing how the RII is distributed for the various pre-selected factors affecting construction delays. It is also important to note that the overall mean RII is greater than 50%, indicating that on average, all the ranked factors are generally important and should be equally addressed. The minimum RII is 10.1% and the maximum RII is 79.9% as shown above. However, it follows that the factor that scored the maximum RII (that is: delay in progress payment by owner) is the most critical one as ranked by the respondents while the one that scored the minimum RII (that is; delay in producing design documents) bears relatively lesser importance although it still exist to affect construction delays. Q1 is 38.85, Q2 (the median) is 55.2 and Q3 is 62.85. Since [(Q3 – Q2) ‹ (Q2 – Q1)], i.e 7.65<16.35, it implies that the distribution of the RII is negatively skewed. Data check is done to check outliers. The results are shown in Table 2 below;

Table 2: Calculation of Outlier Boundaries Formula Workings Statistics

Interquartile Range (IQR) Q3-Q1 62.85-38.85 24

Outlier (lower boundary) Q1-1.5*IQR 38.85-1.5*24 2.85

Outlier (upper boundary) Q3+1.5*IQR 62.85+1.5*24 98.85

Table 2 above any RII that lies below the lower boundary (2.85) and above the upper boundary (98.85) as calculated is an outlier. Therefore, the research has found no outliers in the RII statistics, since the minimum is 10.1% and the maximum is 79.9% and both lie between the outlier boundaries. This implies that the research results are all considered for policy conclusions as they show synonymous characteristics.

VI. RESULTS AND DISCUSION The analysis of the results was based on the RII index of the identified factors. The RII indices identify the relative importance attached to the factors by the respondents. The overall factors were classified under 12 categories as follows: Owner related (6), Contractor related (6), Consultant related (5), Client related (2), Labour related (4), Design team related (7), Contract related (2), Material related (3), Contractual relations related (3), Equipment related (2), Project related (3) and External related (3). However, 19 factors were of little concern to the respondents and this indicates that such factors rarely affect delay in construction projects in Zimbabwe. The RII indices for such factors fall below 50% (or 0.5) and these are delay in materials delivery, poor site management, unforeseen ground conditions, weather conditions, insufficient data collection & survey before design, inadequate labour supply, inadequate planning, mistakes & discrepancies in contract documents, rework due to errors during construction, quality assurance/control, legal disputes between parties, late procurement of

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 19 | P a g e

materials, mistakes & discrepancies in design documents, inadequate construction materials, personal conflicts among workers, preparation & approval of drawings, misunderstanding of owner’s requirements by design engineer, changes in government regulations and delay in producing design documents Below is a discussion of the 27 most important factors affecting delay in construction projects in Zimbabwe:

Owner related category

Table 3: RII ranking of owner related factors Factors affecting delay RII Rank

Delay in progress payment by owner 79.9 1

Delay in revising and approving design documents by owner 77.3 2

Delay in approving shop drawings and sample materials 76.5 3

Suspension of work by owner 61.7 4

Unavailability of incentives for contractor for finishing ahead of schedule 60.6 5

Conflicts over joint ownership of project 59.3 6

Delay in progress payment by owner: This factor ranked 1st both in the Owner related category and in

the overall ranking, with an RII index of 79.9%. This indicates that delay in progress payment by owner is an important determinant of delay in construction projects in Zimbabwe. The results are consistent with the findings of Assaf etal (1995), Assaf and Al-Hejji (2006), Awari et al (2016) and Al-Hammadi and Nawab (2016). Delay in revising & approving design documents by owner: This factor indicates that delay from owner in revising and approving design documents can lead to the delay in project completion. This factor ranked 2nd both in the Owner related category and overall ranking, with an RII index of 77.3%. This is consistent with the findings of Al-Hammadi and Nawab (2016). Delay in approving shop drawings and sample materials: The results also show that this is an important issue that leads to delay in completion of construction projects. This factor ranked 3rd in both the Owner related and overall ranking, with an RII index of 76.5%. This is also similar to the findings of Al-Hammadi and Nawab (2016). Suspension of work by owner: In Zimbabwe, some construction projects have been suspended by owners for various reasons including disputes and misunderstandings on both financial and contractual issues with other stakeholders. This factor ranked 4th in the Owner related category and ranked 13th in the overall ranking, with an RII index of 61.7%. The results are consistent with the findings of Al-Hammadi and Nawab (2016). Unavailability of incentives for contractor for finishing ahead of schedule: This factor ranked 5th in the Owner related category and ranked 15th in the overall ranking with an RII index of 60.6%. In Zimbabwe, incentives for contractors for finishing ahead of schedule are rare thing to come by. However, it is important to note that such incentives play a significant role in motivating contractors to work extra-hard. Conflicts over joint ownership of project: This was also found to be an important factor that also exists to affect delay. This factor ranked 6th in the Owner related category and ranked 16th in the overall ranking, with an RII of 59.3%. Some construction projects in Zimbabwe are so large that they are usually run by both players in the private and public sector, through the so-called Public-Private Partnerships. However, some conflicts erupt over certain issues and this causes delay and total abandonment of projects in some extreme cases.

Contractor related category

Table 4: RII ranking of contractor related factors Factors affecting delay RII Rank

Difficulties in financing the project 74.7 1

Poor qualifications of contractor’s technical staff 51.3 2

Poor site management 48.8 3

Inadequate planning 41.4 4

Rework due to errors during construction 35.1 5

Inadequate construction methods 19.8 6

Difficulties in financing the project: This factor ranked 1st in the Contractor related category and

ranked 4th in the overall ranking, with an RII index of 74.7%.This is consistent with the findings of Baldwin et al (1971), Assaf et al (1995), Frimpong et al (2003), Aigbavboa et al (2014) and Al-Hammadi and Nawab (2016). In Zimbabwe, most contractors are now facing problems in financing construction projects at their disposal. This could be attributed to the current liquidity crisis and the general economic instability that is in the country.

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 20 | P a g e

Poor qualifications of contractor’s technical staff: This research also found out that poor qualifications of contractor’s technical staff is another important factor that leads to delay in construction projects in Zimbabwe. This factor ranked 2nd in the Contractor related category and ranked 27th in the overall ranking, with an RII index of 51.3%. The results are similar to the findings of Bangash (2016). The findings are acceptable because Zimbabwe has witnessed large numbers of experts resorting to work and stay abroad due to economic hardships in Zimbabwe. This, among other reasons, has left contractors with no option, but to make use of the available technical staff, most of whom lack both the necessary professional qualifications and hands-on experience.

Consultant related category

Table 5: RII ranking of consultant related factors Factors affecting delay RII Rank

Waiting time for approval of tests and inspections 61.5 1

Inadequate experience of consultant 56.3 2

Poor contract management 52.6 3

Quality assurance/control 33.7 4

Preparation & approval of drawings 17.1 5

Waiting time for approval of tests and inspections: This factor ranked 1st in the Consultant related

category and ranked 14th in the overall ranking, with an RII index of 61.5%. The results are similar the findings of Odeh and Battaineh (2002). Some projects in Zimbabwe have been delayed due to the long time taken by consultants in approving tests and inspections. Inadequate experience of consultant: Inexperienced consultants are a barrier to project-on-time completion as supported by the findings of Anees and Sabarinathan (2016). This factor ranked 2nd in the Consultant related category and ranked 20th in the overall ranking, with an RII index of 56.3%. Poor contract management: This research also found that poor contract management is now becoming a prominent problem in Zimbabwe’s construction sector. Poor contract management ranked 3rd in the Consultant related category and ranked 25th in the overall ranking, with an RII index of 52.6%. This is consistent with the findings of Odeh and Battaineh (2002) and Frimpong et al (2003).

Client related category

Table 6: RII ranking of client related factors Factors affecting delay RII Rank

Finance and payment of completed work 70.7 1

Unrealistically imposed contract duration 67.4 2

Finance and payment of completed work: Delay in finance and payment of completed work

consequently leads to delay in the overall project as also found by Assaf et al (1995) and Odeh and Battaineh (2002). This has been worsened by financial instability in the country, characterized by the current liquidity crisis. Finance and payment of completed work ranked 1st in the Client category and ranked 6th in the overall ranking, with an RII index of 70.7%. Unrealistically imposed contract duration: This factor ranked 2nd in the Client related category and ranked 9th in the overall ranking, with an RII index of 67.4%. The results indicate that some clients in the construction sector have a tendency of imposing unrealistic contract durations. This is similar to the findings of Odeh and Battaineh (2002) and Al-Hammadi and Nawab (2016).

Labour related category

Table 7: RII ranking of labour related factors Factors affecting delay RII Rank

Lack of experienced workers 62.7 1

Lack of well-educated and trained workers 55.8 2

Inadequate labour supply 43.4 3

Personal conflicts among workers 17.5 4

Lack of experienced workers: Lack of experienced labour has a negative impact on delay. Experience

is very important in the sense that it improves both the intellectual and physical abilities of work force which

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 21 | P a g e

consequently saves both time and resources. This factor ranked 1st in the Labour related category and ranked 12th in the overall ranking, with an RII index of 62.7%. Lack of well-educated and trained workers: While labour supply (in general) is currently not a problem in Zimbabwe, the results of this study show that well-educated and trained labour in construction trades is becoming a problem that now needs to be addressed. Nyoni & Bonga (2016) note that, lack of highly skilled and trained workers in the construction industry in Zimbabwe could be attributed to high capital flight experienced in the country owing to economic-hardships. This factor ranked 2nd in the Labour related category and ranked 22nd in the overall ranking, with an RII index of 55.8%.

Design team related category

Table 8: RII ranking of design-team related factors Factors affecting delay RII Rank

Non-use of advanced modern engineering design software 70.4 1

Inadequate design team experience 55.6 2

Complexity of project design 54.8 3

Insufficient data collection and survey before design 43.7 4

Mistakes & discrepancies in design documents 21.2 5

Misunderstanding of owner’s requirements by design engineer 13.5 6

Delays in producing design documents 10.1 7

Non-use of advanced modern engineering design software: This factor ranked 1st in the Design team

related category and ranked 7th in the overall ranking, with an RII index of 70.4%. This result is supported by Anees and Sabarinathan (2016). Most construction companies in Zimbabwe are not yet using advanced modern engineering design softwares. However, such softwares improve efficiency despite the fact that they are expensive to acquire. Inadequate design team experience: his factor ranked 2nd in the Design team related category and ranked 23rd in the overall ranking, with an RII index of 55.6%. Lack of experience has a negative influence on both project duration and productivity. This result is consistent with the findings of Anees and Sabarinathan (2016). Complexity of project design: This is another factor that has also been found to exist and affect delay as supported by the findings of Anees and Sabarinathan (2016). This factor ranked 3rd in the Design team related category and ranked 24th in the overall ranking, with an RII index of 54.8%. Complexity of project design can be a difficult issue, especially in large construction projects.

Contract related category

Table 9: RII ranking of contract related factors Factors affecting delay RII Rank

Change orders 63.3 1

Mistakes and discrepancies in contract documents 40.1 2

Change orders: While changes suggested by both the owner and client before the project

implementation may not have significant impact on project completion, however during the project; implementation-changes in the requirements by the owner or client significantly influence contract especially in terms of completion of project. Normally such change orders result in extended contract durations. This factor ranked 1st in the Contract category and ranked 11th in the overall ranking, with an RII index of 63.3%. The results are similar to the findings of Al-Hammadi and Nawab (2016). Material related category

Table 10: RII ranking of material related factors Factors affecting delay RII Rank

Shortage of materials 55.9 1

Delay in materials delivery 49.4 2

Late procurement of materials 31.8 3

Shortage of materials: The results show that this is an important factor that affects delay in construction

projects in Zimbabwe. This factor ranked 1st in the Materials related category and ranked 21st in the overall ranking

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 22 | P a g e

with an RII index of 55.9%. This is supported by Odeh and Battaineh (2002), Awari et al (2016) and Anees and Sabarinathan (2016). The results are acceptable because in Zimbabwe some construction projects nearly come to a halt due to material shortages. This has been made worse due to the current liquidity crisis that has made it difficult for contractors to procure materials in time and in right quantities. On the other hand, materials suppliers are reluctant to supply materials on credit because contractors will normally pay suppliers only when they themselves are paid.

Contractual relations related category

Table 11: RII ranking of contractual relations related factors Factors affecting delay RII Rank

Poor professional management 57.4 1

Legal disputes 56.7 2

Insufficient communication between parties 51.7 3

Poor professional management: This factor ranked 1st in the Contractual relations category and ranked 17th in the overall ranking with an RII index of 57.4%. In this category, this is the most important factor in the delay of construction projects. It is, however, important to note that professionalism is an integral part of construction management and has a significant bearing on project duration. Legal disputes: The results show that this is an important factor that affects delay in construction projects in Zimbabwe. This factor ranked 2nd in the Contractual relations category and ranked 19th in the overall ranking with an RII index of 56.7%. Conditions incorporated in construction contracts, not only, explain and amplify the basic obligations of parties to the contract, but also, provide the administrative mechanisms for ensuring that the correct procedures are followed. However, in Zimbabwe, some parties are not very familiar with the conditions of contract resulting in breaches causing delay. In Zimbabwe, the approval and execution of construction projects, especially those that are government-funded, is characterized by both complicated regulations and bureaucracy. Owners, contractors and consultants have to follow certain enacted procedures to ensure successful completion of the projects.

Insufficient communication between parties: In construction sector, just like in any other sector;

communication is very important. This factor ranked 3rd in the Contractual relations category and ranked 26th in the overall ranking. In Zimbabwe, contractors usually complain over insufficient communication especially from consultants with regards to instructions, as a result delay becomes inevitable in their projects. The results are consistent with the findings of Chan and Kumaraswamy (1997), Odeh and Battaineh (2002), Al-Hammadi and Nawab (2016) and Bangash (2016).

Equipment related category

Table 12: RII ranking of equipment related factors Factors affecting delay RII Rank

Lack of technologically advanced equipment 74.1 1

Lack of adequate equipment 63.5 2

Lack of technologically advanced equipment: Nyoni & Bonga (2016) noted that most construction

companies in Zimbabwe use old and outdated machinery. This factor ranked 1st in the Equipment related category and ranked 5th in the overall ranking, with an RII index of 74.1%. The results are supported by Anees and Sabarinathan (2016). While construction in Zimbabwe is still highly labour intensive, it is important to note that technologically advanced equipments not only save time but also improve productivity.

Lack of adequate equipment: The results show that this is an important factor that affects delay in construction projects in Zimbabwe. This factor ranked 2nd in the Equipment category and ranked 10th in the overall ranking, with an RII of 63.5%. This is consistent with the findings of Odeh and Battaineh (2002), Anees and Sabarinathan (2016) and Awari et al (2016). Without adequate equipment construction delay is inevitable. Most contractors in Zimbabwe do not own equipment themselves, where equipment is required; contractors normally hire. However, this makes the whole process even more difficult because sometimes such equipment could be in use somewhere at the time when it is needed. In such cases, contractors are forced to wait for such equipment until it is available for hiring.

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 23 | P a g e

Project related category Table 13: RII ranking of project related factors

Factors affecting delay RII Rank

Original contract is too short 69.4 1

Type of project bidding and award (negotiation, lowest bidder) 56.9 2

Ineffective delay penalties 32.8 3

Original contract is too short: This factor ranked 1st in the Project related category and ranked 8th in

the overall ranking, with an RII index of 69.4%. It is important to note that while all the parties may want the project to be finished quickly, the completion date should be specified objectively rather than subjectively. This means that specified project duration ought to be realistic. Type of project bidding and award (negotiation, lowest bidder): This factor ranked 2nd in the Project related category and ranked 18th in overall ranking, with an RII index of 56.9%. This is consistent with the findings of Assaf and Al-Hejji (2006). Traditionally, contractor selection has been based solely on the prices offered by the bidders. However, in Zimbabwe; nowadays, when it comes to selecting a contractor, many owners do not consider the price as the single selection criterion. This implies that contractor selection is no longer a straightforward procedure performed by merely sorting the bids based on the offered price but rather a complicated process where owners now also consider a combination of several factors such as price, reputation of the bidders, history of previous projects, major construction quality indicators, prepared drawings, suggested construction methods among other things. This is why, as argued by Zavadskas et al (2010) and Huang (2011), there rarely exists a bidder that can dominate the rest of the competitors in all of the relevant criteria. This implies that owners may occasionally fail to select the best contractor as the final winner of the bid. As a result, delay in construction projects in Zimbabwe becomes literally inevitable.

Other factors that were also found to exist and affect delay as derived from un-structured questions: Frequent equipment breakdowns: This another delay causing factor in construction projects in Zimbabwe. The results are supported by Odeh and Battaineh (2006) and Anees and Sabarinathan (2016). Heavy machinery like bulldozers and cranes have a very high probability of breaking down especially after years in service. Most equipment used in the construction sector in Zimbabwe is very old and outdated. Some machinery has turned out to be unreliable even after several repairs but contractors continue to use such machinery. This increases incidences of break-downs during construction, thereby causing delay. Low productivity and efficiency of capital (plant and equipment): Since most machinery that is being used in construction sector in Zimbabwe is very old and outdated, efficiency and productivity are always compromised and this causes delay in project completion. Low productivity of labour: This is another factor that has also been found to exist and affect delay in construction projects in Zimbabwe. This result is similar to the findings of Anees and Sabarinathan (2016). Low productivity of labour has a direct negative influence on project completion. Injuries and fatalities during construction: This study also revealed that this is an important issue in the construction sector in Zimbabwe. In construction projects in Zimbabwe, injuries are more common than fatalities. However, all of these issues cause delay in project completion. The results are supported by the findings of Anees and Sabarinathan (2016). The overall ranking of the 46 pre-selected factors is summarized in the table below:

Table 14: Overall ranking of factors affecting delay Factors affecting delay Category RII

index

Within

Rank

Overall

Rank

Delay in progress payment by owner Owner related 79.9 1 1

Delay in revising & approving design documents by owner Owner related 77.3 2 2

Delay in approving shop drawings & sample materials Owner related 76.5 3 3

Difficulties in financing the project Contractor related 74.7 1 4

Lack of technologically advanced equipment Equipment related 74.1 1 5

Finance & payment of completed work Client related 70.7 1 6

Non-use of advanced modern engineering design software Design team related 70.4 1 7

Original contract is too short Project related 69.4 1 8

Unrealistically imposed contract duration Client related 67.4 2 9

Lack of adequate equipment Equipment related 63.5 2 10

Change orders Contract related 63.3 1 11

Lack of experienced workers Labour related 62.7 1 12

Suspension of work by owner Owner related 61.7 4 13

Waiting time for approval of tests and inspections Consultant related 61.5 1 14

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 24 | P a g e

Unavailability of incentives for contractor for finishing ahead of schedule

Owner related 60.6 5 15

Conflicts over joint ownership of projects Owner related 59.3 6 16

Poor professional management Contractual relations related 57.4 1 17

Type of project bidding & award (negotiation, lowest bidder) Project related 56.9 2 18

Legal disputes Contractual relations related 56.7 2 19

Inadequate experience of consultant Consultant related 56.3 2 20

Shortage of materials Materials related 55.9 1 21

Lack of well-educated & trained workers Labour related 55.8 2 22

Inadequate design team experience Design team related 55.6 2 23

Complexity of project design Design team related 54.8 3 24

Poor contract management Consultant related 52.6 3 25

Insufficient communication between parties Contractual relations related 51.7 3 26

Poor qualifications of contractor’s technical staff Contractor related 51.3 2 27

Delay in materials delivery Materials related 49.4 2 28

Poor site management Contractor related 48.8 3 29

Unforeseen ground conditions External related 47.1 1 30

Weather conditions External related 46.1 2 31

Insufficient data collection & survey before design Design team related 43.7 4 32

Inadequate labour supply Labour related 43.4 3 33

Inadequate planning Contractor related 41.4 4 34

Mistakes & discrepancies in contract documents Contract related 40.1 2 35

Rework due to errors during construction Contractor related 35.1 5 36

Quality assurance/control Consultant related 33.7 4 37

Ineffective delay penalties Project related 32.8 3 38

Late procurement of materials Materials related 31.8 3 39

Mistakes & discrepancies in design documents Design team related 21.2 5 40

Inadequate construction materials Contractor related 19.8 6 41

Personal conflicts among workers Labour related 17.5 4 42

Preparation & approval of drawings Consultant related 17.1 5 43

Misunderstanding of owner’s requirements by design engineer Design team related 13.5 6 44

Changes in government regulations External related 11.2 3 45

Delay in producing design documents Design team related 10.1 7 46

VII. RECOMMENDATIONS The research recommends the following:

1) Construction companies should take steps to entice and train youth in carpentry, masonry and other trades. Incentives in form of allowances and Best Worker of the Year Awards should be provided to try and retain experienced and well-trained workforce and at the same time create competition among workers.

2) The flaws in the design documents should be timely addressed before or during implementation phases to avoid mistakes and discrepancies in design documents. The approval of revised drawing, sample materials or design documents should be timely undertaken as sometimes the owner may be too busy with his or her other projects and may not be able to spare time for a specific project. The consultant should focus on timely delivery of the design or engineering documents (approvals) as well as timely inspections and should have close liaison with client and contractor for timely submission of the required engineering documents to avoid delays in producing design documents. The client should be devoted and sincere with his or her project for timely approval of the shop drawings and other documents sent to him or her by the consultant or contractor.

3) Main contractors should avoid their tendency of subletting the contracts (to subcontractors who usually happen to be incapable of completing construction projects in time), or otherwise technically sound, financially strong subcontractor should be preferred. It is also recommended however, that government should also provide affordable loan facilities to players (clients, contractors and owners) in the construction sector to boost their capacity to meet their financial obligations.

4) The clients and owners should have a proper orientation with contractors, planners, designers and consultant engineers to minimize the changes in the scope of project. Suspension of work, by owners or any other party should be reasonable and justified; otherwise it will result in a mere wastage of time.

5) The client should conduct weekly meetings or monitoring visits with contractor and consultant on regular basis to expedite the pace of work according to the planed schedule (targets) in order have proper liaison with all stakeholders and also avoid disputes between the parties involved. All parties involved are

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 25 | P a g e

encouraged to engage proper and effective communication ways such as meetings and monitoring visits to enhance proper coordination.

6) There is always a chance of conflict in construction projects hence a centralized decision making system is recommendable for timely decision making.

7) If the contractor completes the project within time, they should be given an incentive in form of Cash Award or guaranteed (repeated) Future Business Award. However, it is also recommended that clients should desist from imposing unrealistic contract durations.

8) Contractors should rely on suitable, adequate, well repaired as well as modern, technologically advanced equipment and softwares.

9) If the project is complex in nature it must be made sure that the designers selected for it are suitable for it. The project management team and the owners must make sure that design contracts are awarded to experienced design firms who are capable of completing the design of the project on their own. It should also be made sure that consultants are well experienced and capable of tackling the project timeously.

10) An up-to-date schedule of material supply should be provided by the contractors and should contain the time required to supply materials and the availability of the required materials in time to avoid both delay of materials delivery and shortage of materials.

11) Finally, it is also recommended that construction companies should make sure they engage in exposure monitoring and risk assessment as an occupational health and safety management strategy to avoid injuries and fatalities at work. Construction companies should also make sure that occupational health and safety programmes are an integral part of the general safety and health strategy. Consistent medical surveillance is recommendable to ensure fitness and suitability of workers for certain construction jobs.

VIII. CONCLUSION This study identifies the causes of delay in construction projects in Zimbabwe. A questionnaire survey was used to collect data from the selected population of research. The study fills a gap in knowledge of factors affecting delay in construction projects in Zimbabwe, which can be used by project managers and policy makers in developing new intervention strategies aimed at curbing delays and improving construction business performance in Zimbabwe. While all factors identified in this research should be addressed, greater effort should be directed to the twenty-seven (27) most ranked factors.

REFERENCES

[1] Z.K. Bangash, Analyzing delays in construction projects for Peshawar: Contractor perception, Journal of Emerging Trends in

Applied Engineering, 1(1), 2016, 13-18. [2] S.A. Assaf and S. Al-Hejji, Causes of delays in large construction projects, International Journal of Project Management, 24,

2006, 349-357. [3] S.G. Awari, M. Jamgade and U. Patil, Identifying the causes of delay in construction industry in Mumbai region, International

Journal of Modern Trends in Engineering and Research, 2(7), 2016, 541-543. [4] J.G. Zack, Schedule delay analysis: is there agreement?, Proc. Conf. on Project Management, Project Management Institute, College of Performance, New Orleans, 2003. [5] M.R.B. Mohamad, The factors and effects of delays in government construction projects: case study in Kuantan, University of

Malaysia [6] A. Aibinu and G. Jagboro, The effects of construction delays on project delivery in Nigerian construction industry, International

Journal of Project Management, 20(8), 2002, 593-599. [7] M.M. Alkhathani, Examination of the correlation of critical success and delay factors in construction projects in the kingdom of Saudi Arabia, University of Pittsburgh, 2004 [8] A. Sullivan and F.C Harris, Delay on large construction projects, International Journal of Operations and Production Management,

6 (1), 1986, 25-33. [9] N.R. Mansfield, O.O. Ugwu and T. Doran, Causes of delay and cost overrun in Nigeria construction projects, International Journal

of Project Management, 12 (4), 1994, 254-260. [10] M.K. Anees and S. Sabarinathan, Ranking of delay factors in the Indian Building Construction, International Journal On

Engineering Technology and Sciences, III (VI), 2016, 39-50. [11] S. Al Hammadi and M.S. Nawab, Study of delay factors in construction projects, International Advanced Research Journal in

Science, Engineering and Technology, 3(4), 2016, 87-92. [12] I. Bayai and D. Nyangara, An analysis of determinants of private investment in Zimbabwe for the period 2009-2011, International

Journal of Economics and Management Sciences, 2(5), 2013, 11-42. [13] K. Gondo, S.N. Gore and K. Sithole, Role of the psychological contract in employee retention for local authorities in Zimbabwe, Journal of Research in Business and Management, 4(8), 2016, 30-36. [14] H. Ndebele, Mugabe appeals to SA to increase investment in Zimbabwe, Zimbabwe Independent, 4th November, 2016. [15] Zimbabwe Agenda for Sustainable Socio-Economic Transformation [ZimAsset], Towards and empowered society and a growing economy (October 2013-December 2018), Government of Zimbabwe, Harare, 2013.

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 26 | P a g e

[16] R.A. Khan, M.S. Liew and Z.B. Ghazali, Malaysian construction sector and Malaysian Vision 2020: Developed Nation Status, Proc. 2nd World Conf. on Business, Economics and Management (WCBEM 2013), Elsevier Ltd, Social and Behavioral Sciences, 109, 2014, 507-513. [17] A.A. Attar, A.K. Gupta and D.B. Desai, A study of various factors affecting labor productivity and methods to improve it, IOSR

Journal of Mechanical and Civil Engineering, 2012, 11-14. [18] Zimbawean Independent, Chinese ‘grab’ construction projects-Murray and Roberts boss cries foul, http://www.theindependent.co.zw/12/10/2016/zim-mall-project-lawful/, 2011, Accessed 13 December 2016. [19] Bulawayo24News, Construction industry on the road to recovery, http://bulawayo24.com/index-id-business-sc-local-byo-10417-article-construction-industry-on-the-road-to-recovery.html, 2011, Accessed 13 December 2016. [20] World Bank, Dealing with construction permits in Zimbabwe, http://www.doingbusiness.org/data , 2012, Accessed 13 December 2016. [21] Zimbabwe National Statistics Agency [ZimStats], National Accounts Report (2009-2014), Government of Zimbabwe, Harare,

2014. [22] T. Chigara and T. Moyo, Factor affecting labour productivity on building projects in Zimbabwe, International Journal of

Architecture, Engineering and Construction, 3(1), 2014, 57-65. [23] T. Nyoni and W.G. Bonga, An Empirical Investigation of Factors Affecting Construction Sector Labour Productivity in Zimbabwe, International Journal of Business and Management Invention, 5(8), 2016, 68-79. [24] S. Assaf and M. Hazmi, Causes of delay in large construction projects, Journal of Management in Engineering, 11(2), 2006, 45-50. [25] M.I. Al-Khalil and M.A. Al-Ghafly, Delay in Public Utility Projects in Saudi Arabia, International Journal of Project Management,

17(2), 1999, 101-106. [26] J.R. Baldwin and J.M. Manthel, Causes of delay in construction industry, Journal of Construction Division, 7, 1971, 177-187. [27] D. Arditi, G.T. Akan and S. Gurdamar, Reasons for delays in public projects in Turkey, Construction Management and Economics,

3(2), 1985, 171-181. [28] S.A. Assaf, M. Al-Khalil and M. Al-Hazmi, Causes of delays in large building construction projects, Journal of Management in

Engineering II(2) 1995, 45-50. [29] W. Vidogah and I. Ndekugri, Improving management of claims-contractors’ perspective, Journal of Management in Engineering,

13(5), 1997, 33-44. [30] A. Shashid, H. Ahmad, N. Ahmad, M.N Shafique and N Amjad, Analysis of performance key factors affecting residential construction projects in Pakistan, Arabian Journal of Business and Management Review (Nigerian Chapter), 3(10), 2015, 9-14. [31] Association of Project Managers, APM body of knowledge, 5th Edition (London, APM, 2006) [32] D. Arditi and T. Pattanakitchamroon, Selecting a delay analysis method in resolving construction claims, International Journal of

Project Management, 24, 2006, 145-155. [33] V. Ireland, A comparison of Australia and US building performance for high-rise buildings, School of Building Studies, University

of Technology, Sydney, 1986. [34] A.H. Al-Momani, Construction delay: a quantitative analysis, International Journal of Project Management, 18(1), 2000, 51-59. [35] A.W. Gale and R.F. Fellows, Challenge and Innovation: the challenge to the construction industry, Construction Management and

Economics, 8, 1990, 431-436. [36] G. Ofori, The construction industry: Aspects of its Economics and Management, Singapore University Press, Singapore, 1990. [37] G. Ofori, Challenges of construction industries in developing countries: lessons from various countries, Proc. of the 2nd CIBT G29

Conf. on Construction in developing countries: challenges facing the construction industry in developing countries, Gaborone, Botswana, 2000, 40-50. [38] United Nations Industrial Development Organisation [UNIDO], Prospects for the development of the construction industry in developing countries, Proc. Conf. ID/WG.528/5, Vienna, 1993 [39] F. Mhlanga, Cash Crises threatens SMEs, Zimbabwe Independent, 4th November, 2016. [40] B. Mpofu, Chiwenga takes bond notes to the barracks, Zimbabwe Independent, 4th November, 2016. [41] F. Moavenzadeh, Construction industry in developing countries, World Development, 6(1), 1978, 97-116. [42] Zimbabwe National Statistics Agency [ZimStats], National Health Profile Report of 2013, Government of Zimbabwe, Harare,

2013. [43] R. Divya and S. Ramya, Cause, Effects and Minimization of Delays in Construction Projects, Proc. Conf. on the Research in

Communication, Computation, Electrical Science and Structures (NCRACCESS-2015), 2015, 47-53. [44] N.N. Agu and B.O. Ibe, Assessment of factors causing delay on building construction projects in Enugu, Nigeria, International

Journal of Innovative Science, Engineering and Technology, 3(6), 2016, 544-558. [45] J. Bolton, Types of claims-Construction and disruption claims, Course Manual (Portman Inter-Continental, London, 1990). [46] R.N. Nkado, Construction-Time Influencing Factors: the Contractors’ Perspective, http://www.misronet.com/articles.html Accessed 13 December 2016. [47] J.R. Baldwin, J.M. Manthel, H. Rothbart and R.B. Harris, Causes of delay in the construction industry in the South-Eastern United States, Journal of Management in Engineering, 31(2), 1971, 51-81. [48] D.W. Chan and M.M. Kumaraswamy, A comparative study of causes of time overruns in Hong Kong construction projects, International Journal of Project Management, 5(1), 1997, 55-63. [49] C.O. Aigbavboa, W.D. Thwala and M.J. Mukuka, Construction project delays in Lusaka, Zambia: Causes and Effects, Journal of

Economics and Behavioral Studies, 6(11), 2014, 848-857. [50] Z.T. Zewdu, Construction Projects Delay and Their Antidotes: The Case of Ethiopian Construction Sector, International Journal

of Business and Economics Research, 5(4), 2016, 113-122. [51] J.W. Johnson and J.M. Breton, History and use of the Relative Importance Indices in Organizational Research, Organizational

Research Methods, 7, 2004, 238-257. [52] Y. Frimpong, J. Oluwoye and L. Crawford, Causes of delay and cost overruns in construction groundwater projects in developing countries: Ghana as a case study, International Journal of Project Management, 12(5), 2003, 321-326. [53] A.M. Odeh and H.T. Battaineh, Causes of construction delay: Traditional contracts, International Journal of Project Management,

20(1), 2002, 67-73.

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 27 | P a g e

[54] E.K. Zavadskas, T. Vilutiene, Z. Turskis and J. Taruosaitiene, Contractor selection for construction works by applying SAW-G and TOPSIS grey techniques, Journal of Business Economics and Management, II(1), 2010, 34-55. [55] X. Huang, Analysis of the selection of project contractor in the construction management process, International Journal of Business

and Management, 6(3), 2011, 184-189.

Appendix QUESTIONNAIRE

Section A: Closed-ended questions Please indicate to what extent each of the following factors affects delay at your organisation (by ticking in the box below 1/2/3/4/5).

Data Measurement Key: 1-Very Weak; 2-Weak; 3-Fair; 4-Strong; 5-Very Strong

Number Factors affecting delay 1 2 3 4 5

Project related

1 Original contract is too short

2 Legal disputes between various parties

3 Type of project bidding and award (negotiation, lowest bidder)

Owner related

4 Change orders by owner during construction

5 Delay in revising and approving design documents by owner

6 Delay in approving shop drawings and sample materials

7 Suspension of work by owner

8 Conflicts over joint ownership of project

9 Delay in progress payment by owner

Contractor related

10 Poor site management

11 Inadequate construction methods

12 Inadequate planning

13 Difficulties in financing the project

14 Rework due to errors during construction

15 Poor qualifications of contractor’s technical staff

Consultant related

16 Poor contract management

17 Preparation and approval of drawings

18 Quality assurance/control

19 Waiting time for approval of tests and inspections

20 Inadequate experience of consultant

Design team related

21 Mistakes and discrepancies in design documents

22 Delays in producing design documents

23 Complexity of project design

24 Insufficient data collection and survey before design

25 Misunderstanding of owner’s requirements by design engineer

26 Inadequate design team experience

27 Non-use of advanced modern engineering design software

Client related

28 Finance and payment of completed work

29 Unrealistically imposed contract duration

External related

30 Weather conditions

31 Changes in government regulations

32 Unforeseen ground conditions

Labour related

33 Lack of experienced workers

34 Lack of well-educated and trained workers

35 Personal conflicts among workers

36 Inadequate labour supply

Equipment related

37 Lack adequate equipment

38 Lack of technologically advanced equipment

Towards Factors Affecting Delays in Construction Projects: A Case of Zimbabwe

www.dynamicresearchjournals.org 28 | P a g e

Material related

39 Shortage of materials

40 Delay in materials delivery

41 Late procurement of materials

Contract related

42 Change orders

43 Mistakes and discrepancies in contract documents

Contractual relations related

44 Poor professional management

45 Legal disputes

46 Insufficient communication between parties

Section B: Open-ended questions 1) How would you define delay in construction industry? ............ .............. ............ ........... ......... ........ ....... ........ ...... ....... ........ ......

...... .................................................................................................................................................................... 2) What are the factors affecting delay at this construction company? ............... ............................. .................... .................... .......... .....

....................................................................................................................................................................................................................

....................................................................................................................................................................................................................

.................................................................................................................................................................................................................... 3) Amongst the factors you mentioned above, which ones are the most important and why?.. .......... ........ ...... ........ ......... ....... ....... ....

....................................................................................................................................................................................................................

....................................................................................................................................................................................................................

.............................................................................................................................................. 4) Given the responses you provided above, how can construction delay be minimized or

avoided?.........................................................................................................................................................................................................................................................................................................................................................................................................................

Section C: Demographics Please tick the applicable

Sex:..................................Male/Female; Age:………………...……18-25/26-35/36-50/above 50 Education:…………….…O’ Level/ A’ Level/ Diploma/ Degree/ Post Graduate Work Experience:.......................student/0-5 years/6-10 years/10-15 years/above 15 years You are allowed to tick more than one profession

Profession: � Carpenter � Builder/Bricklayer � Earth-moving & Construction equipment Operator � Electrician � Engineer � Painter � Tiler � Plumber � Foreman/Supervisor � Manager � Other (specify)…………………………………………..