(to be published in the gazette of india, part-ii, and...
TRANSCRIPT
APPLICATION FOR
ENVIRONMENTAL
CLEARANCE
UNDER SECTION 7.2 OF EIA
NOTIFICATION SEPT’ 06) OF
GHONSA EXPN. OC WANI NORTH AREA, WCL.
(For Enhancement in production capacity from 0.45 MTPA to O.60
MTPA within the existing land of 128.79 ha)
FORM – I, TOR, ADDENDUM
EIA/EMP,COMPLIANCE OF EARLIER EC
DECEMBER - 2012 Prepared by :-
ENVIRONMENT DEPARTMENT
CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED
KASTURBA NAGAR, JARIPATKA
NAGPUR - 440014
SUBMISSION
This Environmental impact assessment (EIA)/
Environmental Management Plan (EMP) has
been prepared for expansion in production
capacity of existing mine from the sanctioned
capacity of 0.45 MTPA to 0.60 MTPA without
increase of land area u/s 7.2 of EIA Notification,
2006. The copy of the EC has been enclosed as
Annexure – I.
The Public Consultation/ Public Hearing as per
EIA Notification, 2006 has been completed on
09.08.2011.The minutes of the said Public
Hearing is attached as Annexure – III.
CONTENTS
SL.NO CHAPTER
NO.
PARTICULARS PAGE NO.
1. Duly filled in Form – 1 for
enhancement of capacity
F -1 to F
2 Draft Terms of Reference TOR – 1
3. Executive Summary ES – 1 to ES - 25
4. Addendum EIA/EMP
Chapter - I Introduction
Chapter - II Project Profile
Chapter - III Description of
Environment
Chapter - IV Anticipated
Environmental
Impacts & Mitigation
Measures
Chapter - V Environmental
Monitoring
Programme
Chapter - VI Additional Studies
Chapter - VII Project Benefits
Chapter - VIII Environmental Cost
Benefit Analysis
Chapter - IX Environmental
Management Plan
LIST OF PLATES
SL.NO PLATENO. PARTICULARS
1. I Location plan of mine.
2 II Index plan covering Core Zone & Buffer
Zone Showing Main Drainage
3. II A Land Use Cover map of Core & Buffer
Zone using Satellite data
4. III Index Plan Showing features within the
Core & Buffer Zone
5. IV Index Plan Showing features within 3 km
of the Core Zone
6. V Quarry & Surface layout Plan showing
Surafce Contours and Floor Contours.
7. VA Geological Plan of Wardha Valley
Coalfield with Special Reference to
Ghonsa OC
8. V B Surface Plan of Ghonsa Block
9. VI Existing Cross – Sections Plan -
Longitudinal & Transverse
10. VII Post Mining Land Use Plan
11. VIII Post Mining Sections - Longitudinal &
Transverse
12. IX Plan Showing Base- Line AQMS covering
Core & Buffer Zone
LIST OF ANNEXURES
SL.NO Annexure –
No.
PARTICULARS
1. I EC issued by MOEF vide letter dated
29.02.2012 (A – I/1 to A-I/5).
2. II Duly filled in proforma for environmental
Appraisal of Mining Project
(A – II/1 to A-II/42).
3. III Minutes of the Public Hearing held on
09.08.2011(A – III/1 to A-III/10).
4. IV Copy of the Authenticated list of Flora &
Fauna (A – V/1 to A-V/27).
5. V Environmental Statement 2011-12
(A – VI/1 to A-VI/19).
6. VI Compliance of EC dated 29.02.2012.
APPLICATION FOR
ENVIRONMENTAL CLEARANCE
(AS PER SECTION 7.2 OF EIA NOTIFICATION SEPT’ 06)
OF
GHONSA EXPN. OPENCAST PROJECT WANI NORTH AREA, WCL
(Increase in Production from 0.45 MTPA to 0.60MTPA)
(Within the same Mine Lease Area of 128.79 ha)
FORM – 1 &
TERMS OF REFERENCE
DECEMBER– 2012
Prepared by :-
ENVIRONMENT DEPARTMENT
CMPDI, RI – IV, JARIPATKA
NAGPUR - 440014
GHONSA EXPANSION OC PROJECT OF WCL (I) Basic Information
SN. Item Details
1 Name of the project/s. Ghonsa Expansion OC Project
2 S.No. in the schedule. 1(a)
3 Proposed
capacity/area/lenght/tonnage to
be handled/command area/lease
area/number of wells to be drilled.
Operating OC mine proposed for
Expansion in Mine production capacity
from 0.45 to 0.60 MTPA within the same
lease area.
4 New/Expansion/Modernization. Expansion production capacity only
5 Existing Capacity/Area etc. Production Capacity – 0.45 MTPA
Mine Lease Area – 128.79 ha
6 Category of Project i.e. ‘A’ or ‘B’. “A”
7 Does it attract the general
condition? If yes, please specify.
No
8 Does it attract the specific
condition? If yes, please specify.
No
9 Location
Plot/Survey/Khasra No. Details shown in enclosed Plate I
Village Near Kumbharkhani Village
Tehsil Wani
District Yavatmal
State Maharashtra
10 Nearest railway station/airport along
with distance in kms.
Wani Railway Station- 24 kms
Nagpur Airport – 170 kms
11 Nearest Town, City, District
Headquarters along with distance in
kms.
Wani Tahsil Town is 20 km and Yavatmal
Town the District HQ is 125 km.
12 Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given).
Village Panchayat – Kumbharkhani
Tahsil – Wani,
District – Yavatmal
Maharashtra State
13 Name of the applicant. K.Chakraborty
14 Registered Address As given below
15 Address for correspondance:
Name K.Chakraborty
Designation (Owner/Partner/CEO) General Manager(Environment)
Address Environment Department,
Coal Estate, 9th Floor, Civil Lines
Nagpur (M.S.)
Pin Code 440 001
E-mail [email protected]
Telephone No. 0712 - 2510151
Fax No. 0712 – 2510151
16 Details of Alternative Sites examined,
if any. Location of these sites should
be shown on a topo sheet.
Not Applicable
17 Interlinked Projects. Not Applicable
18 Whether seperate application of
interlinked project has been
submitted?
Not Applicable
19 If yes, date of submission. ----
20 If no, reason. -----
21 Whether the proposal involves
approval/clearance under: if yes,
details of the same and their status to
be given.
a) The Forest (Conservation) Act,
1980?
b) The Wildlife (Protection) Act, 1972?
c) The C.R.Z. Notification, 1991?
No
No
No
22 Whether there is any Government
Order/Policy relevant/relating to the
site?
No
23 Forest land involved (hectares). No
24 Whether there is any litigation
pending against the project and/or
land in which the project is propose
to be set up?
a) Name of the Court
b) Case No.
c) Orders/directions of the Court, if
any and its relevance with the
proposed project.
No
(I) Activity
1. Construction, operation or decommissioning of the Project involving actions, which will
cause physical changes in the locality (topography, land use, changes in water bodies,
etc.)
Sl.
No.
Information/
Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities /rates,
wherever possible) with source of information data
1.1 Permanent or
temporary
change in land
use, land cover
or topography
including
increase in
intensity of land
use (with respect
to local land
use plan)
Yes Proposed mine is an expansion of existing Ghonsa OC mine interms of production capacity only.
The total land involved in this project is 128.79 ha.The environment clearance has already been taken in existing Ghonsa OC mine vide letter dated 29.02.2012.
Break up is given below.
Sl. No.
Particulars Land already acquired in existing Ghonsa OC mine
Total
1. Agricultural Land
128.79 ha 128.79 ha
2. Waste Land (Govt. Land)
-
3. Forest Land
-
TOTAL 128.79 ha 128.79 ha
The entire land is covered black cotton soil and is generally used for growing mainly the cash crop like cotton , sugarcane, chillies etc. apart from standard agricultural products like rice, wheat and jawar .
Till date, out of 69 land holdings, 55 have been provided with employment and 3 have been given Moetary Compensation in lieu of Employment. Changes of total Land Use during Mining:
Sl. Agri- Waste Forest including
No. culture (Govt) Zudpi Jungle TOTAL
Land Land
1. Excavation 38.05 - -- 38.05
2. Ext. OB Dump 29.35 -- - 29.35
3. Infrastructure 10.00 - - 10.00
4. Blasting Zone 35.39 --- - 35.39
5. Embankment 15.00 - - 15.00
6. Clony 1.00 - - 1.00
Total 128.79 -- --- 128.79
-------------------------------------------------------------------------------------------------
1.2 Clearance of
existing land,
vegetation
and buildings?
Yes Land for the proposed opencast mine has been partly
acquired and balance will be acquired under relevant
acts as follows: -
Sl.no Land Particulars CBA
Act,1957
(ha)
Forest
Act,
1957
(ha)
Total
Land
(ha)
1. Agricultural land 128.79 128.79
2. Waste Land ---
3. Forest Land
Total 128.79 --- 128.79
1.3 Creation of new
land uses?
Yes The creation of new land usage will be as under:
(Spread through the entire life of the mine)
The creation of new land usage will be as under:
(Spread through the entire life of the mine)
(a) Excavation Area .. 38.05 ha
(b) External OB Dump Area .. 29.35 ha
(c) Embankment Area -- 15.00 ha
(d) Infrastructure .. 10.00 ha
(e) Blasting zone and -- 35.39 ha
Rationalization area
(f) Colony -- 1.00 ha
-----------------------
128.79 ha 1.4 Pre-construction
investigations e.g.
bore holes, soil
testing?
Yes 24 boreholes (RB and MWKK series) were drilled in 1.35 km2
quarry area. Total meterage is 1259.35. Borehole density is 18.
1.5 Construction Work No The mine is already in operation and necessary facilities have
been constructed. 1.6 Demolition works?
No No structure to be dismantled.
1.7 Temporary sites
used for
construction works
or housing of
construction
workers?
No Initially temporary structures will be made essentially to meet the
enabling needs of Construction manpower & machinery
deployed.
1.8 Above ground
buildings, structures
or earthworks
including linear
structures, cut and
fill or excavations
Yes The details of various construction works to be
undertaken in the proposed site have been given in the
sanctioned PR and also at item no 1.5 above.
Excavation – 38.05 ha
Embankment – 15.00 ha
External OB Dump – 29.35 ha 1.9 Underground works
including mining or
tunneling?
No Not applicable
1.10 Reclamation works?
Yes Solid Waste Management (Proposed)
i) OB in External dump – 7.37 Mm3
Including Embankment
ii) OB in Internal dump – 1.17 Mm3
The post-mining scenario can be summarized as below :
( Area in ha )
____________________________________________________________________
Sl. Particulars Plantation Void Public Use Undisturbed/ Total
No Unplanted
___________________________________________________________________
1. External 29.35 - - - 29.35
OB Dump
2. Excavation 4.00 34.05 - -- 38.05
3. Infrastructure - - 10.00 - 10.00
4. Blasting Zone 10.00 - - 25.39 35.39
Including
Rationalization
6. Colony --- - 1.00 -- 1.00 Plain land plantation
8. Embankment 15.00 - - - 15.00
Total 58.35 34.05 11.00 25.39 128.79
1.11 Dredging?
No --
1.12 Offshore
structures?
No
----
1.13 Production and
manufacturing
processes?
Yes Open Cast mining with Shovel - Dumper Combination method.
1.14 Facilities for storage
of goods or
materials?
Yes Coal produced from opencast mine shall be stored
on surface at designated coal stock yard duly
provided with fire fighting & dust suppression system.
The goods & materials shall be stored in designated
store.
Explosives shall be stored in magazine(4x10t) as
approved by Controller of Explosives.
1.15 Facilities for treat-
ment or disposal
of solid waste or
liquid effluents?
Yes Solid Waste –
Sl.
NO
Particulars Disposal of Solid Wastes(In Mm3)
External OB
Dump
Internal Dump
in Decoaled
Void
Total
1. Solid
Waste
(Over
burden)
7.37 1.17 8.54
Liquid Effluent –
a) Mine Pumped Out Water – Initial sedimentation in
the mine sump provided at the floor of the seam
and then treatment in Sedimentation Pond on
surface.
b) Workshop Effluent – In designated Effluent Treatment
Plant with Zero Discharge.
c ) Domestic Effluent – Treatment in septic tank and
Soak pit provided with residential unit.
1.16 Facilities for long
term housing of
operational
workers?
Yes Fifty numbers of Hutments have already been constructed
against approved PR of south quarry.
1.17 New road, rail or
sea traffic during
construction or
operation?
Yes Already constructed as it is an operating mine.
i) Haul Road - has been provided and maintained
by Hiring agency.
ii) Service Road – 0.50 km.
iii) Approach Road for Mine – 0.50 km.
1.18
New road, rail, air
waterborne or
other transport
infrastructure
including new or
altered routes and
stations, ports,
airports etc?
No
1.19 Closure or
diversion of existing
transport routes or
infrastructure
leading to changes
in traffic
movements?
No
1.20 New or diverted
transmission lines
or pipelines?
No
1.21 Impoundment,
damming,
culverting,
realignment or
other changes to
the hydrology of
watercourses or
aquifers?
Yes Construction of Embankment around the quarry.
Hydro geological Set-up :
Mine induced effect would be distinctly noticed within a
distance of 300 m from the mine edge in the down-dip
side at quarry depth of 46 m. as envisaged in the CGWA
Report prepared earlier for quarry depth of 46 m.
However, the effect will be limited / negligible in the up-
dip side of the incrop zone due to shallow depth..
1.22 Stream crossings? No
-
1.23 Abstraction or
transfers of water
form ground or
surface waters?
Yes Ground Water –
Due to excavation strata seepage water gets
accumulated at the floor of the coal seam in the sump
having capacity to deal with peak rainfall. In order to
maintain the working faces dry for coal production this
water is pumped out daily.
Surface Water –
No abstraction from surface water course, treated mine
water and sub-soil water will be used for Industrial and
Domestic use. However, it is suggested in the RPR that the
source of water may be ascertained after carrying out
hydro-geological investigation in respect of quality and
quantity of water.
1.24 Changes in water
bodies or the land
surface affecting
drainage or run-
off?
No
1.25
Transport of
personnel or
materials for
construction,
operation or de-
commissioning?
No
The mine is already in operation; the personnel are
using their own transport.
Decommissioning is not envisaged in near future as
the mine is proposed for expansion with life of 18
years.
1.26 Long-term
dismantling or
decommissioning
or restoration
works?
No Not envisaged at present.
1.27 Ongoing activity
during
decommissioning
which could
have an impact
on the
environment?
No Not envisaged at present.
1.28 Influx of people
to an area in
either temporarily
or permanently?
No Temporary Influx – 500 (Approximately).
1.29 Introduction of
alien species? No Not applicable
1.30 Loss of native
species or genetic
diversity?
No Not applicable
1.31 Any other
actions?
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply):
Sl.No.
Information/checklist
confirmation
Yes/No
Details thereof (with approximate quantities
/rates, wherever possible) with source of
information data
2.1 Land especially
undeveloped or
agricultural land (ha)
Yes Tenancy/Agricultural land –232.50 ha.
2.2 Water (expected
source & competing
users) unit: KLD
Yes Source – Mine Pumped out Water
i)Consumption at site - 50 KLD.
ii)Consumption in colony - 80 KLD.
2.3 Minerals (MT) Coal 1.73 Million Tonnes
2.4 Construction material
– stone, aggregates,
sand / soil
(expected source) –
( MT)
No Mine is already in operation.
2.5 Forests and timber
(source – MT)
No Not applicable
2.6 Energy including
electricity and fuels
(source, competing
users) Unit: fuel (MT),
energy (MW)
Yes Electricity –
Source – MAHAGENCO
Consumption – 2.52 MKWH/ANNUM
Diesel
Source – Area Store
Consumption – 5500 liters /day
2.7 Any other natural
resources (use
appropriate standard
units)
No Not applicable
3. Use, storage, transport, handling or production of substances or materials, which could
be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.
Sl.
No.
Information/Checklist confirmation
Yes/No
Details thereof
(with approximate
quantities/rates,
wherever possible) with
source of information
data
3.1 Use of substances or materials, which are
hazardous (as per MSIHC rules) to human
health or the environment (flora, fauna, and
water supplies)
No Not applicable
3.2 Changes in occurrence of disease or affect
disease vectors (e.g. insect or water borne
diseases)
No Not applicable
3.3 Affect the welfare of people e.g. by
changing living conditions?
No Not applicable
3.4 Vulnerable groups of people who could be
affected by the project e.g. hospital patients,
children, the elderly etc.,
No Not applicable
3.5 Any other causes No Not applicable
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
Sl.No.
Information/Checklist confirmation
Yes/No
Details thereof (with
approximate
quantities/rates,
wherever possible) with
source of information
data
4.1 Spoil, overburden or mine wastes Yes A total quantity of 8.54
million m3 solid waste will
be generated during
the opencast mining
operation.
4.2 Municipal waste (domestic and or
commercial wastes)
Yes Domestic – Recycling for
manures
(Approx. 100 kg/day)
4.3 Hazardous wastes (as per Hazardous
Waste
Management Rules)
Yes ETP Sludge- Secured
land fill
Used Oil- Through
approved recyclers.
4.4 Other industrial process wastes
No ---
4.5 Surplus product
No ---
4.6 Sewage sludge or other sludge from
effluent treatment
Yes Will be treated and
disposed as per Consent
Conditions.
4.7 Construction or demolition wastes Yes Wastes :
During
construction-
Insignificant
Demolition - Not
envisaged at
Present
4.8 Redundant machinery or equipment Yes By auction through
authorized agencies.
4.9 Contaminated soils or other materials Yes Through biological
reclamation by growing
trees (native species).
4.10 Agricultural wastes No ---
4.11 Other solid wastes
No ---
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.No
.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data.
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes Operation of Heavy Earth
Moving Machines (HEMMs).
The quantum of gases viz. SO2,
NO2 and CO in ambient
environment is being measured
through ambient air quality
monitoring in the mine activity
area every fortnight as per
Environment Protection
Amendment Rule, 2000;
In fulfillment of the requirement
of Environment Clearance
conditions.
5.2 Emissions from production
processes
Yes Dust particles including coal
dust.
The quantum of Dust (SPM &
RPM) in the ambient
environment is being measured
through ambient air quality
monitoring in the mine activity
area every fortnight as per
Environment Protection
Amendment Rule, 2000.
5.3 Emissions from materials
handling including storage or
transport
Yes Dust particles including coal
dust.
The quantum of Dust (SPM &
RPM) in the ambient
environment is being measured
through ambient air quality
monitoring in the mine activity
area every fortnight as per
Environment Protection
Amendment Rule, 2000.
5.4 Emissions from construction
activities including plant and
equipment
Yes Insignificant
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
No ---
5.6 Emissions from incineration of
waste
No ---
5.7 Emissions from burning of waste
in open air (e.g. slash materials,
construction debris)
No ----
5.8 Emissions from any other
sources
No ---
6.Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No
.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data with
source of information data
6.1 From operation of equipment
e.g. engines, ventilation plant,
crushers
Yes Generation of Noise and
Vibration will be due to the
following operations.
i) Operation of HEMMs /
Machineries.
ii) Blasting Operations
The vibration level will be measured
through Vibrometer.
The quantum of noise in ambient
environment is being measured
through ambient noise quality
monitoring in the mine activity area
every fortnight as per Environment
Protection Amendment Rule, 2000.
6.2 From industrial or similar
processes
No
6.3 From construction or
demolition
Yes Insignificant
6.4 From blasting or piling
Yes Blasting –
Is being carried out as per permission
from DGMS and will be maintained
within the permissible limits specified
by DGMS.
6.5 From construction or
operational traffic
Yes Construction: Insignificant
Operational – through movement of
coal transportation trucks and
dumpers.
Noise level is being monitored every
fortnight as per Environment
Protection Amendment Rule, 2000.
6.6 From lighting or cooling systems
No ---
6.7 From any other sources No ---
7. Risks of contamination of land or water from releases of pollutants into the ground
or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No
.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No Used Oil – will be disposed off through
approved Recyclers.
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and
place of discharge)
Yes Mine Pumped Out Water –
Excess Treated mine pumped out
water is proposed to be discharged
into local nullah.
Quality parameters will be monitored
every fortnight.
Domestic sewage
Domestic Sewage will be treated in
individual Septic Tank and Soak Pit
provided with each residential unit.
Workshop Effluent –
Effluent will be treated in Effluent
Treatment Plant with Zero Discharge.
Quality parameters will be monitored
every fortnight.
7.3 By deposition of pollutants
emitted to air into the land or
into water
Yes Fugitive emission into air from OB
dumps, transportation roads.
Quantum of fugitive emission in
ambient environment will be
monitored every quarter (Except
Monsoon).
7.4 From any other sources
No ---
7.5 Is there a risk of long term build
up of pollutants in the
environment from these
sources?
No ---
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment
S.No
.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
8.1 From explosions, spillages, fires
etc from storage, handling,
use or production of
hazardous substances
No
8.2 From any other causes
Yes Due to –
1) Land Sliding in OB Dump and mine
Pit –
2) Mine Inundation
3) Blasting
8.3 Could the project be affected
by natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburst etc)?
No ----
9. Factors which should be considered (such as consequential development) which
could lead to environmental effects or the potential for cumulative impacts with
other existing or planned activities in the locality
9.1 Lead to development of
supporting.
lities, ancillary development or
development
stimulated by the project
which could have impact on
the environment e.g.:
• Supporting infrastructure
(roads, power supply, waste
or waste water treatment,
etc.)
• housing development
• extractive industries
• supply industries
• other
Yes For Eco – development activities in the
areas surrounding the project it is
proposed to develop a green belt by
plantation, biological reclamation of
OB dumps, water shed development,
etc. These activities will help in
reduction of dust and noise pollution
and will also supplement the shortage
of water in nearby villages in future.
The social impact will mainly be due
to the acquisition of the tenancy land,
required for this project. The project is
expected to form a nucleus for further
industrialization/development and
urbanization of the study area. There
would be development in the
secondary and tertiary sectors to
support the project activities.
It is proposed to organize
entrepreneurship motivation camps
for willing EPAPs for different self-
employment options. This will be in
addition to the compensation being
paid to the land-loosers as per the
Company’s policy.
9.2 Lead to after-use of the site,
which could have an impact
on the environment
Yes
The degraded land is proposed to be
biologically reclaimed which will
improve the green cover in the area.
9.3 Set a precedent for later
developments
Yes Activities detailed out in previous
paragraph above do culminate in
conjunction with local setup has set
precedence of economic
development leading to over all
socio-economic growth of the area.
9.4 Have cumulative effects due
to proximity to other existing
or planned projects with
similar effects
Yes New Opencast Mine: Coal occurs in
layers and for large distances.
Associated mining activities with such
closely located centers along with
other relocated sectors etc. Would
have accumulative impact.
III ) Environmental Sensitivity
S.No
.
Areas Name/
Identity
Aerial distance (within 10 km.)
Proposed project location boundary
1 Areas protected under
international conventions,
national or local legislation for
their ecological, landscape,
cultural or other related value
No ---
2 Areas which are important or
sensitive for ecological
reasons - Wetlands,
watercourses or other water
bodies, coastal zone,
biospheres, mountains, forests
No -
3 Areas used by protected,
important or sensitive species
of flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration
No
---
4 Inland, coastal, marine or
underground waters
No ---
5 State, National boundaries No ----
6 Routes or facilities used by the
public for access
to recreation or other tourist,
pilgrim areas
No ----
7 Defence installations
No ---
8 Densely populated or built-up
area
No ---
9 Areas occupied by sensitive
man-made land uses
(hospitals, schools, places of
worship, community facilities)
Yes Limited to the Project Township
10 Areas containing important,
high quality or scarce resources
(ground water resources,
surface resources, forestry,
agriculture, fisheries, tourism,
minerals)
Yes Ground water – Yes
Surface water- Canal, Viderbha river
Forestry - No
Agricultural – Yes
Fisheries - Yes
Minerals – Coal
11 Areas already subjected to
pollution or environmental
damage. (those where existing
legal environmental standards
are exceeded)
No ---
12 Areas susceptible to natural
hazard which could cause
the project to present
environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding
or extreme or adverse
climatic conditions)
No ---
PROPOSED
TERMS OF REFERENCE
OF
GHONSA OPENCAST PROJECT EXPN. FOR
(Grant of EC u/s 7.2 of EIA Notification, 2006)
PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
Based on the information furnished in Form – I, the Terms of Reference (TORs) for grant of EC u/s
7.2 of EIA/Notification, 2006 for expansion in production capacity only within the acquired land
area is as under :
i) The proposed project under consideration is Ghonsa Opencast Mine located in Wani
Tahsil,; Dist Yevatmal; State Maharashtra as shown in the plan (Pate – I) and fall under
the administrative control of Wani North Area of Western Coalfields Limited.
ii) The study area comprises 10 km (radius) zone around the mine lease as shown in the
enclosed plan (Pate – II)
iii) Initially the Project has been accorded Environmental Clearance for 0.30 Mty with 128.00 ha of
land vide MOEF's letter no. J-11015/27/2004 - IA.II(M) dated 13.01.2005. Subsequently the
enhancement in capacity up to 0.45 MTPA vide MOEF's letter no. J-11015/165/2009-IA.II(M)
dated 29.02.2012. Now the project is being proposed fr further enhancement in capacity up to
0.60 MTPA within the already acquired mining area of 128.79 ha.
iv) An addendum EIA/EMP for detailed environmental impact assessment due to proposed
enhancement along with control measures is attached.
v) The Public Hearing for the project covering the future expansion also has already been
completed on 09.08.2011.
I hereby given undertaking that the data and information given in the
application and enclosures are true to the best of my knowledge and belief
and I am aware that if any part of the data and information submitted is found
to be false or misleading at any stage, the project will be rejected and
clearance give, if any to the project will be revoked at our risk and cost.
Date:
Place: Nagpur
Signature of the applicant
With Name and Full Address
(Project Proponent / Authorised Signatory)
EXECUTIVE SUMMARY
OF
EIA/EMP
FOR
GHONSA EXPN. OC
WANI NORTH AREA,
WCL
(0.60 MTPA)
EXECUTIVE SUMMARY 1.0 INTRODUCTION
Ghonsa Block is located in Wani Taluqa of Yavatmal District of Maharashtra State
and is named after nearby Ghonsa village. An underground project adjacent to
proposed Ghonsa OCP in the same geological Block had been approved as
“Kumbharkhani Underground” on Dec.’98 for a capital of Rs.56.890 Crores for a target
production of 0.36 Mty. The U/G mine has produced about 0.28Mt in the year 2007-08. It
has been contemplated to work this Block by opening an opencast project of about
0.45 Mt annual capacity to meet the increasing demand of non-coking coal . A Project
Report of Ghonsa Opencast Project was prepared by CMPDI RI-IV in March 2001. In this
PR (capacity-0.45Mty) the Ghonsa OCP Block was divided in three quarries namely North
quarry, Central quarry and South quarry. The proposed quarriable area was bounded by
State high way No.233 in North, Vidharbha river in West and South and incrop of Seam-I
in East. The quarriable area is separated by underground project by the barrier of State
highway No.233 passing over the property. It was proposed to work these quarries by
departmental HEMM. This PR was not yielding the requisite IRR for approval. However, an
annexure was enclosed in this PR indicating economics of working in South quarry only,
by total hiring of HEMM. The total Hiring option for south quarry only was yielding 49.45%
IRR at 85% production capacity.
The WCL Board in its 167th Meeting, held on 9.10.2001 approved the total hiring option for
South quarry only, for an initial capital of Rs.6.99 crores and for an annual targeted
capacity of 0.30 Mty.
The environmental clearance for this project was obtained from MOEF in January 2005.
Subsequently, a RPR for Ghonsa OC expansion with a rated capacity of 0.45 MTPA with
293.65 ha has been prepared and approved by WCL Board.
Based on above referred RPR, the Form – 1 was submitted to MOEF through MOC vide
letter no. 43011/29/2009- CPAM dated 28.05.2009. It was discussed in the Expert Appraisal
Committee of MOEF on 24.06.2009 and Terms of Reference (TOR) has been issued by
MOEF vide its letter no, J- 11015/165/2009 –IA.II (M) dated 08.07.2009.
As directed by MOEF vide aforesaid TOR, Public Hearing document was prepared and
submitted to Maharashtra Pollution Control Board for conduction of PH as per EIA
Notification, 2006. The Public Hearing was successfully conducted by MPCB on
09.08.2011. Based on the suggestions made in the Public Hearing, the final EIA/EMP was
prepared submitted to MOEF for obtaining Environmental Clearance as per EIA
Notification, 2006.The Environmental Clearance for Phase – I of the project within the
existing land was accorded by MOEF vide its letter no. J – 11015/165/2009-IA.II(M)
dated 29.02.2012.
Now it is envisaged that the mine within the sanctioned land area can produce beyond
the sanctioned capacity of 0.45 MTPA. Therefore, this proposal has been prepared for
obtaining Environmental Clearance u/s 7.2 of EIA Notification, 2006 for Ghonsa OC Expn.
for a peak capacity of 0.60 MTPA within the already sanctioned land area of 128.79 ha.
2.0 MARKETABILITY & JUSTIFICATION
The deficit of coal from WCL is likely to touch 6.55 Mt in 2011-12 even when future
projects are approved, so there will be no difficulty in marketing of coal hence the
project is justified to bridge the gap.
3.0 PROJECT SITE INFORMATION
Ghonsa block covering an area of 2.8 sq. km forms part of Ghonsa/Kumbharkhani rift
basin coalfield and falls in Wani Taluqa of Yavatmal Distt. of Maharashtra State. Ghonsa
village at the north-west corner of the block is connected by S.H. NO.233 from Wani
town which in turn is connected with NH-7 to Hyderabad via Pandharkawada. The
distance of Ghonsa village from Wani town is about 20 km. The project area may be
approached from Wani-Patan main road via. Rasa- Kumbharkhani fair weather road
having distance of about 3 km from Rasa Junction. Nearest railway station to Ghonsa
Block is Wani in Majri-Rajur Branch of Central Railway. A railway line from Wani to
Mukutbandh passes about 10 km away at Pitur flag station from project area.
Ghonsa block exhibits gently undulating topography sloping towards Vidharbha River
flowing in the middle of the block. The elevation varies from 229.08m to 240.44m. The
main drainage of the area is controlled by Vidharbha River which flows in south-westerly
direction passing through central and Southern property and finally meets with
Penganga River. A few small seasonal nullahs passing through the property drain into
Vidharbha River during rainy season. HFL of Virdharba River is recorded in 1990 as 237.15
m.
4.0 COAL QUALITY
There are following two seams present in the block :-
Seam Depth Range
(m)
Thickness
Range (m)
UHV
(kcal/kg)
GCV
(kcal/kg)
Min. Max. Min. Max. Min. Max. Min. Max.
Seam II 14.30 63.35 2.12 6.30 3707 5036 4678 5463
Seam I 14.45 80.80 1.00 3.50 3377 4064 4486 4952
Seam quality details estimated for 0.05m dilution at each contact point for Seam-I and
Seam-II combined together have been given in Table below
5 cm
dilution
at each
contact
point
Parameters South Quarry
Moisture % 6.36
Ash % 32.59
UHV(kcal/kg) 3525
GCV(kcal/kg) 4563
Grade E
5.0 PRODUCTION CAPACITY OF MINE
The peak capacity of the mine is 0.60 MTPA.
6.0 SEAM CHARACTERISTICS & MINE PROFILE
Sl. PARTICULARS South Quarry
1 Area of the Quarry
(a) On floor (Ha.) 27.68
(b) On surface (Ha.) 38.05
2. Depth (m)
(a) Initial 13
(b) Final 46
3. Gradient of Seam 1 in 12.0 to 1 in 10.5
4. Effective thickness of seam (m)
(a) Seam-I 1.00 to 3.50
(b) Seam-II 2.12 to 5.40
5. .Strike length (m) 955
6. Width on surface (m):
(a) Maximum 510
(b) Minimum 180
7. Mineable reserves (Mt) 1.73
8. Total OB incl. Access Trench
(Mm3)
8.54
9. Average S.R. m3/t. 4.94
6.1 SELECTION OF MINING METHOD
Considering this production from two seams with less reserve in a limited strike length,
deployment of dragline would not prove to be effective and economical. Hence, only
shovel-dumper combination with incline slicing method is recommended.
7.0 COAL HANDLING ARRANGEMENT
A small coal handling plant is proposed near the access trench of South Quarry to
handle the entire production from mine. The CHP will have facilities like crushing, ground
stocking, weighing etc. Mode of despatch of coal from CHP will be on road to
MAHAGENCO & other miscellaneous consumers.
8.0 LAND REQUIREMENT & REHABILITATION
The break up of the type of land required and Proposed land use during mining for
Ghonsa OC project is as follows :
Sl.
No
Particulars (Type of
Land)
Land to
be
acquired
Sl.
No
Land Use – During
Mining Land (in
ha)
1. Agricultural land 128.79 1. Excavation area 38.05
2. Government Land - 2. External OB Dump 29.35
3. Forest Land - 3. Infrastructure 10.00
Sub Total (1+2+3) 128.79 4. Blasting zone &
rationalization
35.39
5. Embankment 15.00
6. Colony outside ML
area
1.00
Grand Total 128.79 Total 128.79
9.0 MINING SCHEDULE AND EQUIPMENT REQUIREMENT
It is envisaged in this option of the project report that removal of overburden and
extraction of coal are proposed to be done by hiring/outsourcing of HEMM. The scope of
work by hiring/outsourcing of HEMM shall include blast hole drilling, earth work
excavation, loading, transportation, dumping, dozing, construction of haul road, leveling
at dumping sites, water spraying and land reclamation etc. as per guidelines of the
project authorities highlighted in this project report or otherwise to suit the local
conditions.
10.0 MINE FACILITIES
10.1 WORKSHOP & UNIT STORES
All HEMM deployed in this mine will be hired and their maintenance will be contractor’s
responsibilities. Hence, there is no provision of any unit excavation workshop in the report.
One small and independent unit stores has been provided at convenient location to
cater the routine needs of consumables, spares, POLs etc. This will depend on
Regional/Central stores for major spares. Unit store lay out drawing is not given in this
project.
10.2 POWER SUPPLY
The estimated maximum demand of mine loads of Ghonsa OC Mine works out to 1034
kVA. A new 33 kV /3.3 kV substation is already installed to cater the need of power
requirement of Kumbharkhani mine. This substation is receiving power at 33 kV from Wani
MSEDCL substation by a 20 km long 33 kV overhead line. It is proposed to extend this
33kV feeder for a length of 2 km, upto Ghonsa OCM and a 2 X 1 MVA, 33 kV /3.3 kV
substation will be installed.
11.0 SAFETY & CONSERVATION
This report has been drawn in conformity with the prevailing statutory provisions
applicable for safety in Opencast Mines. Proposed quarry area is mostly below HFL of
Vidhabha river hence, flood protection embankment with top RL 6 m above HFL would
be constructed around quarry area. Special precaution should be taken while deploying
workers in the mine. Before employing any labour to the mine proper vocation training
should be imparted and recommendations of VIII Safety Conference should be strictly
followed. Terms and conditions shall be fixed by management for deployment of labours
by leaser of HEMM as well as machineries.
12.0 MINE CLOSURE PLANNING
The proposed Ghonsa OC expansion mine has been planned upto 46 m depth and it is
most likely that this will be extended further in dip side in future. Although no statutory
guidelines exist on financial provisioning for mine closure activities as yet, financial
provision of Rs.6.00 laks/ha has been provided throughout the mine life in order to
undertake mine closure activities. Closure cost may be reviewed under the changing
circumstances and new legislative requirements.
13.0 ENVIRONMENTAL IMPACT ASSESSMENT & ENVIRONMENTAL POLLUTION CONTROL
MEASURES:-
Baseline Environmental Scenario :-
Baseline data on environmental quality for winter season are collected for 90 days during
the period from 01st December`09 to 28th February`2010. The study carried out during the
said period is reported below.
APPROACH METHODOLOGY
Micrometeorological data generation
A meteorology station has been set up at Core zone and micrometeorological
parameters like wind velocity, wind direction, temperature, relative humidity, cloud cover
etc. are recorded on hourly basis for 90 days from 01st December`09 to 28th
Februarty`2010 representing winter season. Daily rainfall also has been recorded and
reported.
Ambient air quality monitoring
Ambient air quality was monitored at 6 locations i.e. one in core zone and the remaining
five in buffer zone. A total of 24 samples (24-hrly) for SPM & RPM and 72 samples (8-hrly)
for SO2 and NOx samples were collected from each location during the study period and
analyzed.
Water quality monitoring
Representative water samples 6 nos. namely Mine discharge, Project site (W1 & W2),
Handpump, Ghonsa basti (W3), Handpump, Pratara village (W4), Vidharbha river U/s
(W5) and Vidharbha river D/s (W6) were collected, preserved and transported to R&C
Environmental Engg. Laboratory, Chennai and analyzed as per standard methods.
Noise levels recording
Noise levels were recorded by using CYGNET Integrated sound level meter (100X) from six
ambient air quality locations during day time and night time at an interval of four hours
for one day.
Soil quality monitoring
Soil samples from three locations namely one in Dump soil, Corzone (S1), Agri.Land,
Corezone village (S2) and Barren land,Corezone (S3) were collected at depths of 30, 60
and 100 cms and analysed for various physico-chemical and fertility parameters.
DATA ANALYSIS AND RESULTS
Micrometeorology
The wind velocity readings were ranging from <0.4 – 14.2 km/hr. Predominant winds were
from North-East (NE) and East North-east (ENE) directions. The maximum temperature
recorded was 25.5C and the minimum was 11.0C. The mean relative humidity was
found to 63.6% and no rainfall was recorded during the study period.
Air quality
Core zone
SPM and RPM values are ranging from 165 - 246 g/m3 and 68 g/m3 to 125 g/m3
respectively. SO2 and NOx values are varying between 7.2 to 11.6 g/m3 and 8.9 to
15.2 g/m3 respectively. All the values are found to be well within the Standards for
Coalmines stipulated by Ministry of Environment & Forests (MoEF).
Buffer zone
SPM and RPM values are ranging from 108 g/m3 to 179 g/m3 and 32 g/m3 to 87 g/m3
respectively. SO2 and NOx values are varying between 5.4 – 10.6 and 6.9 – 13.0 g/m3
respectively. All RPM, SO2and NOx values are well within the CPCB norms.
Water quality
The water samples (6 Nos.) collected from different water sources ie. Wastewater,
Surface & ground water etc. are analyzed as per procedures outlined in IS : 2488 / IS :
3025 / AWWA / APHA.
At all locations, oil and grease, phenolic compounds, cyanides, sulphides and
insecticides are found to be absent and all heavy metal values except Iron are found to
be below the detectable limit.
In general, water quality at six locations is found to be within the prescribed limits.
Noise levels
Mean Leq noise levels at day time and night time are ranging from 47.4 to 60.4 dB(A) and
40.1 to 51.7 dB(A) respectively in the study area. While comparing with IS: 4954 -1986
norms for acceptable outdoor noise levels in residential area (55 dB(A)) in respect of
buffer zone and Industrial area (75 dB(A)) in respect of core zone.
Soil quality
The soil quality of the project area appears to be good and would support vegetation after
suitable reclamation / modification.
CONCLUSIONS
The following conclusions are drawn based on the baseline data collected at core and
buffer zone area.
i) Ambient air quality parameters viz., RPM, SO2 and NOx are well within the CPCB
norms for industrial, Commercial, Residential and other areas.
ii) The quality of mine water treated effluent is good. Further, the ground and surface
water quality is also good and is well within the norms of IS : 10500-1991 and IS :
2296 – 1982 respectively. Therefore, the mixing of mine effluent will not have
adverse effect on surface Most of the noise levels recorded are generally less than
65 dB(A) and are well within the acceptable outdoor noise levels in residential
areas in respect of buffer zone and Industrial area in respect of core zone as per
the norms of IS: 4954 - 1986.
iii) The soil quality in the project area appears to be good and would support
vegetation after suitable reclamation measures.
AIR POLLUTION IMPACT ASSESSMENT
The impact assessment has been carried out dealing with the following points:
(a) Phase-wise inventory of air pollution emission sources
(b) Impact assessment
a. Phase-wise inventory of air pollution emission sources
The pollution sources are obvious and to assess the impact, the project life is divided into
following time frames:
Operation phase
Post-operational stage
The activities associated with these time frames and having impact on the ambient air
quality along with the pollutants are enumerated in the following sections:
Operational phase
During this phase, activities necessary for mining of coal, its handling and transport are
taken up. Such activities having impact on ambient air quality are detailed below:
(i) Drilling : Dust
(ii) Blasting of coal and
overburden
: Dust and noxious gases
(iii) Handling of coal : Dust and noxious gases
(iv) Overburden handling : Dust and noxious gases
(v) Dump formation (internal) : Dust and exhaust fumes from
dumpers and dust till the
development of green cover
(vi) Movement of vehicles : Dust and noxious fumes
Post-operational stage
During this stage of the project, the activities related to the closure of mine are to be
carried out. Preparation of mine closure plan shall be carried out during the period four
to five years before the closure of the mine. Some of the activities for the closure are:
Modifications in physical and biological reclamation of backfilled area Salvaging and
shifting operation of HEMMs and other equipment Clearing of coal and other materials,
restoration of infrastructure area & colony area to the extent possible and necessary if
not useful for other projects Management of hydrology and hydrogeology.
Redeployment of workforce, etc, arrangement & implementation of post-operation
monitoring mainly keeping watch, vigil, etc.
The activities having impact on the ambient air quality are enumerated below:
(i) Movement of HEMMs for physical
reclamation of backfilled area
: Dust and obnoxious
fumes
(ii) Movement of vehicles for shifting and
salvaging operation of HEMMs and other
equipment
: Dust and obnoxious
fumes
(iii) Movement of vehicles for clearing of coal
and other materials
: Dust and obnoxious
gases
b. Impact assessment
The mining and its related activities create ambient air pollution. The impact of mining on
ambient air quality is highlighted in the following paragraphs:
The ambient air quality is influenced due to the presence of RPM, SPM, SO2, NOx, etc.,
which are generated due to various activities like drilling, blasting and handling related
to the project. Further, the ambient air quality is affected marginally to a varying degree
due to the mining activities of other nearby opencast and underground coalmines of the
same coalfield. The concentration of pollutants may vary depending upon the various
micro-meteorological parameters and the seasons of a year.
The baseline ambient air quality has been generated surrounding the proposed site of
Ghonsa Expansion OC and the details have been given in the previous paragrph. It is
seen that the ambient air quality parameters are well within the permissible limits which
establishes the fact that adverse impact on ambient air quality due to coal mining
activities are insignificant.
Now, with the start of the proposed expansion project, there is likelihood of addition of
pollution to the existing concentration level of different attributes of ambient air. Efforts
will be made by implementation of proper abatement measures so as to maintain the
sinking capacity of ambient air to absorb the additional load, if any, thereby maintaining
the quality of ambient air to the pre – mining level to the extent possible.
Now in order to assess the likely contribution of pollution due to proposed enhanced
mining activities, as directed Numerical Modeling (ISCST – 3) has been done and the
details have been given in Chapter – IV. It can be seen that the likely level of ambient
pollutant at the peak production capacity (0.60 MTPA) of the mine will remain well within
the permissible limits. In addition, air quality data of mine activity area of nearby OCPs
have been considered to prove the fact that an operating mine with the production
capacity much more than that of proposed project, generates pollution load, even in
dry season, well below the limit values, so the pollution load from proposed project will
be much less. The details of data in respect of Pimpalgaon OCP (1.25 MTPA), Ukni OCP
(2.20 MTPA) and Junad OCP (0.60 MTPA) for the period of quarter ending June 2010 to
June 2011 are given in Chapter - IV. It can be seen from the data that even in the worst
season, the ambient air quality parameters are within the permissible limits.
NOISE QUALITY
In order to assess the existing ambient noise level in the surrounding of proposed project
site corresponding to pre-mining scenario, baseline noise level data has been
generated & details are given in Chapter – III along with the regular ambient noise level
monitoring data of the existing mine. All the values are well within the permissible limit.
Proposed mine would be associated with following activities that may generate noise
during operation :
(a) Drilling
(b) Blasting
(c) Shovel operation
(d) Dozing
(e) Movement of dumper
(f) Operation of CHP / Workshop
The following are some of the important activities responsible for high noise level
generation, with their expected noise levels :
All mining activities i.e. drilling, blasting, shoveling, dozing and dumping are associated
with high noise level [about 100 dB(A)].
Operation of most HEMMs produce high noise level. The noise level are in range of 80 –
100 dB(A). Noise level have been found to be related to engine capacity. Crusher –
General noise level due to crusher ranges from 90 dB(A) – 105 dB(A). Some of noisy
equipment produce noise whose level is around 120 dB(A).
The average sound pressure level of some of the HEMM associated with mining operation
which are responsible for high noise level generation are as follows :
EQUIPMENT NOISE LEVEL
[dB(A)]
Dozer 98
Dumper 92
Power shovel 93
Drilling machine 96
ACCEPTABLE INDUSTRIAL NOISE LEVEL
As per Env. (Protection) Amendment Rules, 2000 the ambient air quality standards in
respect of noise in industrial, commercial, residential and silence zones area as follows:
Sl.
No.
Category of
area
Limits [dB(A)]
Day time (6.00 AM to 10.00 PM )
Night time (10.00 PM to 6.00 AM )
1. Industrial 75 70
2. Commercial 65 55
3. Residential 55 45
4. Silence zone 50 40
Assessment of the degree of noise to which a workplace noise is harmful, is done by
comparing the values measured at workplace to the permissible limit adopted by
statutory bodies like DGMS.
The Director General of Mines Safety vide their circular no. DG (Tech.)/18 of 1975 has
prescribed the permissible limit for noise level as 90 dB(A) , for the workers engaged in
mining occupation likely to be exposed to in an 8 hour shift period with unprotected ear.
Whereas, the following table shows the maximum permissible noise exposure levels, as
per American Standards, for the industrial workers.
Exposure time
(Hrs./day)
Noise level
[dB(A)]
8 90
6 92
4 95
3 97
2 100
1.5 102
1 105
0.5 108
0.25 or less 115
EXPOSURE TO PULSE OR IMPACT NOISE
SHOULD NOT EXCEED 140 dB(A)
Now to assess the likely contribution from proposed project, the ambient noise level of
operating mines of the same area has been taken into consideration. It is observed that
noise level recorded near CHP & Near Manager’s Office (mine activity area & major
source of noise in opencast mines) of Pimpalgaon OCP(1.50 MTPA), Ukni OCP(2.20
MTPA) & Junad OCP (0.60 MTPA) respectively are well within the permissible limit. The
peak capacity of proposed Ghonsa OC Expn. Is only 0.45 MTPA, which is much less than
the operating OC mines in the neighbourhood. Hence, it is anticipated that with the
control measures in place the level of ambient noise will remain well within the
permissible limits.
Air and Noise Pollution Control Measures:-
a) To reduce air pollution due to dust produced during various mining and allied
activities, adequate water spraying has been envisaged at strategic points so that
dust will not get airborne. All haul roads, service roads, coal transportation roads shall
be metalled.
b) Proper blasting techniques by designing a suitable blasting pattern after actual field
observation would be followed to minimize adverse effects of ground vibration and
noise.
c) Development of green belt around infrastructure, colony, along roads and in vacant
land would be undertaken for arresting dust and noise propagation. Moreover,
green belt has been proposed against Antargaon Khurd and Goigaon village for
arresting air, noise pollution.
d) Proper maintenance of all HEMM and other P&M will be undertaken so as to reduce
the harmful exhaust and noise.
e) Regular cleaning of transportation roads will be carried out. It is further proposed to
carry coal by covered trucks.
f) Personal protective gears will be given to workmen exposed to dusty and noisy work
environment.
It has also been proposed to carry out regular ambient air quality monitoring in order to
ascertain the exact level of various pollutants which will help in organizing the control
measures accordingly. Ambient noise level will also be monitored and adequate
measures will be taken for reducing the intensity of noise and its propagations.
Water Quality:-
Impact Assessment on Water:- Identification of the sources of water pollution
Likely sources of water pollution from this project along with the type of pollutants are as
follows:
(i) Sanitary (domestic) wastewater : Suspended solids and BOD.
(ii) Industrial wastewater from
workshop
: Suspended solids, oil & grease;
(iii) Wastewater from mine : Suspended solids of coal, clay
and oil;
(iv) Surface run-off passing through
coal stockpiles
: Suspended solids;
(v) Storm water from leasehold area
and built-up area
: Suspended solids.
Impact assessment
Mining and its related activities may create water quality problems. The impact of mining
at the project on both surface and ground water sources has been assessed and given
below:
(a) Surface water sources
Deterioration of water quality and pollution of water bodies due to discharge of mine
effluent, if not treated. Change in relief pattern due to mining may cause flooding,
siltation, choking and pollution. Mitigatory measures would involve provision of (i) garland
drains on periphery to prevent surface run-off from entering into the quarry , (ii) catch
drain around the dumps for avoiding siltation and (iii) sedimentation ponds for reducing
the pollution of surface water bodies.
Possible overflow of water from nearby rivers/nallahs must be safeguarded by stone
pitching and strengthening the embankment along the side of the water course
In order to assess the existing quality of surface as well as ground water quality
surrounding the proposed project site, water samples both from ground water as well as
surface water have been collected & analyzed. The detailed report has been discussed
in Chapter – III. It is seen from the data that water quality in both ground and surface
water samples are well within the permissible limits. It can thus be concluded that effluent
from existing mines operating in the vicinity of the proposed project has not affected the
natural water quality adversely as the existing mining operations are being carried out
with adequate control measures.
Further, to assess the likely quality mine pumped out water as well as the quality of
effluent from the proposed Workshop effluent treatment plant, the mine water discharge
quality of existing Operating opencast projects lying in the immediate vicinity of the
same area which are being monitored regularly as per Env. (Protection) Amendment
Rule , 2000 have been considered . The results indicate that even in untreated condition
mine pumped out water does not contain any pollution load. The details of quality
monitoring data in respect of mine pumped out water for Pimpalgaon OC, Ukni OC,
Junad OC for the period of quarter ending June 2010 to June 2011 are given in detail in
Chapter – IV.
(b) GROUNDWATER RESOURCES IN THE AREA :
Groundwater recharge
Rainfall is the main recharge source for groundwater. The study area receives an
average annual rainfall of 1100 mm. Additionally, groundwater is also being recharged
from other sources such as return flow from irrigation and mine pumped out (waste)
water thrown on land/natural drains, minor irrigation reservoir and canals etc. The
replenishable groundwater recharge has been computed by rainfall-infiltration method
in the absence of long term water table fluctuation data of different formations in the
area. The rainfall infiltration factor for semiconsolidated sandstones (Gondwanas) and
Basalts / Vindhyans has been considered to be 12% and 7% respectively (GEC report-
1997) by critical review of all the ground factors responsible for rainfall -recharge to
groundwater. While computation of groundwater recharge, the hilly area with > 20%
slope amounting to about 17 sq. km. has been discarded from the study area of 314 sq.
km. The groundwater recharge computation as per GEC -1997 norms is as under :-
a) Recharge from rainfall : 23.73 MCM
i) Kamthis/Barakar (15.68 Sq.Km) - 2.07 MCM
ii) Basalts/Vindhyans (281.32Sq.Km) - 21.66 MCM
b) Recharge from other sources : 0.86 MCM
i) Irrigation return flow - 0.37 MCM
ii) Return flow from mine pumped
out (waste) water - 0..25 MCM
iii) Recharge from minor irrigation - 0.24 MCM
tank and canals
c) Gross groundwater recharge (a+b) : 24.59 MCM
Groundwater draft :
The groundwater withdrawal is generally for domestic, industry and irrigation requirement
and is quantified as under.
The land use details of the buffer zone are as follows :
a) Irrigated agriculture area - 258 ha.
b) Un-irrigated agriculture area - 19961 ha.
c) Cultivable waste land - 1640 ha.
d) Not available for cultivation - 2666 ha.
e) Forest area - 5762 ha.
f) Uninhabited - 3175 ha
----------------
Total 33462 ha.
The groundwater draft for domestic & irrigation use is computed as under :
Sl No. Purpose No./Area Water
consumption per
capita
Total qty. of
withdrawal (MCM)
1.
a) Domestic
(Human Population)
b) Domestic (Animals)
53840
Nos.
38540
Nos.
70 Lit/day
20 Lit/day
1.38
0.28
2.
Irrigation (for 120 days)
258 ha.
40000 Lit/ha/day
1.24
Total : 2.90
In addition to the above, the working Kumbarkhani UG mine in the study area is also
pumping out groundwater continuously to keep the working faces dry for effective
extraction of coal. An estimate has been made on the water pumped out from this mine
and it comes to 1.24 MCM annually.
Thus, the total groundwater withdrawal in the area amount to 4.14 MCM
Groundwater balance :
i) Gross groundwater recharge : 24.59 MCM
ii) Natural discharge to drains & other
losses (10% of item (i) ) : 2.46 MCM
iii) Net annual groundwater availability : 22.13MCM
iv) Allocation/ projection upto next
25 years for domestic & industrial use : 1.75 MCM
v) Annual groundwater draft for all uses : 4.14 MCM
vi) Groundwater balance (Item iii-iv & v) : 16.24 MCM
Groundwater stage of development :
Coal mining is the only industrial activity in the area. Besides this, groundwater utilisation is
mainly for domestic and irrigation use. The level/stage of groundwater development
computation in the present study is around 18.70% which can be categorized as "Safe"
with less than 70% value. As per CGWB report on Yeotmal district of Maharashtra, the
stage of development in Wani Tehsil Block in which Ghonsa OCM is located is 5.95 % and
classified as "Safe"category.
Water Pollution Control Measures:-
a) Domestic Effluent :
The effluent from residential houses and service buildings are proposed to be treated in a
suitable sewage treatment disposal plant.
b) Mine Discharge :
Water collected near workings will first be allowed to settle in sumps. Sufficiently large
sumpage has been proposed to eliminate the discharge of suspended solids on the
surface along with mine water. It will then be passed through a sedimentation pond.
The final discharge has been proposed to be utilized for various purposes like water
spraying, watering of plants, HEMM washing etc. It is proposed to put the water in a
closed water circuit for its recycling and reuse. The balance treated water then can be
used for supplementing the shortage of water in the nearby villages. It has, therefore,
been proposed to regularly monitor the quality of mine water discharge and if any
undesirable element is found in the sample, it will be treated properly.
c) Effluent from Workshop, etc. :
Entire effluent from workshop will be passed through a settling tank with oil & grease trap
arrangements. Clear water thus collected will be recycled on the closed water circuit
for its reuse.
19.0 Rehabilitation & Resettlement:-
Rehabilitation:-
In the approved PR in South quarry was only 129 ha. Till date 128.79 ha land has been
acquired for South quarry. There is no village falling in the proposed land of the project as
such no resettlement of house oustees is involved in this project.
COMPENSATION & REHABILITATION
Payment of compensation for land losers has been estimated as per compensation
package of R&R policy of CIL.
Till date, out of 69 land holdings, 55 have been provided with employment and 3 have
been given Moetary Compensation in lieu of Employment.
14.0 ENVIRONMENTAL MONITORING –
The environmental monitoring programme at present will be carried as per details
given below:
S
N
Items Parameters Frequency No. of
Stations
1 Ambient
Air Quality
Monitoring
SPM, RPM, SO2,
Nox, CO & Fugitive
dust
Every Fortnight as per
EPA, Rule 2000
4
2 Water
Quality
Monitoring
1) 4 Parameters
viz. p H, Total
Suspended Solids
Every Fortnight
2
(TSS), Chemical
Oxygen Demand
(COD) & Oil and
Grease.
2) 35 Parameters
Once in a Year
3 Noise
Quality
Monitoring
Noise Levels Every Fortnight 2
4 Environme
ntal
Statement
Annual
5 Ground
Water
Level
Monitoring
& Quality
Water Level &
Quality
Parameters.
Water Level –
Quarterly.
Water Quality – Yearly.
In Buffer
Zone
Villages.
6 Complian
ce Report
of EC
Conditions
All conditions both
Specific & General
1st June &
1st December
Not
Applicabl
e
15.0 PUBLIC CONSULTATION
As per the conditions given in the Terms of Reference issued by MOEF vide its letter-dated
08.07.2009, Public Hearing has been successfully conducted as per the provision given in
the EIA Notification, 2006 by MPCB on 09.08.2011. The details have been discussed in
Chapter – VI.
16.0 PROJECT BENEFITS
The benefits of the project can be summarized as below:-
- The physical infrastructure in the area has already been improved substantially by
following ways:-
Development of road thereby improving the communication.
Improvement in Power, Telephone (including Mobile) facility.
Improvement in Health Care facility & Educational facility.
Improvement in Market / Trade & Business.
- The social infrastructure by way of cultural mixing of people of other states with local
community glorifying “UNITY IN DIVERSITY”.
- Substantial employment in the project & indirect employment for business & trading,
contractor, transportation, vehicle contractor, nursery development.
17.0 MONITORING ORGANISATION
Close monitoring of the environment and implementation of various protective measures
discussed in the report forms an important part of EMP. In the earlier chapters the causes
of various pollutions along with the preventive and mitigating measures have been
discussed. In this chapter description of the administrative aspects of ensuring that
mitigative measures are implemented and their effectiveness monitored, after approval
of the EIA is being discussed.
MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of the
various measures suggested, a multi-disciplinary approach is essential.
(a) WCL headquarter acts as an apex body which supervises the activities relating to
environment at project level through the General Manager.
(b) Chief General Manager of the area coordinates the activities of various disciplines in
the area to render all necessary assistance at the implementing level i.e. the Project.
Area Nodal Officer (Environment) monitors all aspects of environment on behalf of the
Chief General Manager. He also takes suitable steps for generation of environment data
along with its analysis and interpretations.
As far as plantation is concerned horticulturist with suitable backup staff shall be
provided in the area for undertaking the plantation jobs including raising of a nursery.
Plantation will have to be done on a large area. Therefore, it may be desired that an
outside agency may have to be employed for this purpose. The horticulturist along with
the supervisor shall only monitor and guide the agency for selection of site, treatment of
soil, selection of species etc.
(c) Sub Area Manager is responsible for mechanical reclamation of the area. He is also
responsible for biological reclamation with the assistance of CGM's office.
ORGANISATION FOR ENVIRONMENT MANAGEMENT
SN Measures/Actions Agency
1. Environmental Control 1 Chief General Manager, Wani North Area
2 Nodal Officer, (Environment), Wani North
Area
3 Sub Area Manager, Ghonsa Expn. OC.
4 Staff Officer (Civil), Wani North Area
5 Environmental Cell (WCL H.Q.)
2. Environmental
Monitoring
1 Chief General Manager, Wani North Area
2 Staff Officer (Civil), Wani North Area
3 Nodal Officer (Environment), Wani North
Area
4 Sub Area Manager, Ghonsa Expn. OC
5 Environment Cell of WCL Headquarters
6 Environmental Laboratory of CMPDI, RI-IV
3. Reclamation 1 Sub Area Manager, Ghonsa Expn. OC
2 Nodal Officer (Environment), Wani North
Area
3 Environmental Supervisor
4 Horticulturist
************
ENVIRONMENT IMPACT
ASSESSMENT
&
ENVIRONMENTAL
MANAGEMENT PLAN FOR
ENVIRONMENTAL CLEARANCE
(AS PER EIA NOTIFICATION SEPT’ 06)
OF
GHONSA EXPN. OC WANI NORTH AREA, WCL.
(FOR Enhancement in production capacity from 0.45 MTPA to O.60
MTPA within the already acquired land Area of 128.79 ha)
DECEMBER - 2012
Prepared by :-
ENVIRONMENT DEPARTMENT
CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED
KASTURBA NAGAR, JARIPATKA
NAGPUR - 440014
CHAPTER – I
INTRODUCTION
1.0 INTRODUCTION
Ghonsa Block is located in Wani Taluqa of Yavatmal District of Maharashtra State
and is named after nearby Ghonsa village. An underground project adjacent to
proposed Ghonsa OCP in the same geological Block had been approved as
“Kumbharkhani Underground” on Dec.’98 for a capital of Rs.56.890 Crores for a target
production of 0.36 Mty. The U/G mine has produced about 0.28Mt in the year 2007-08. It
has been contemplated to work this Block by opening an opencast project of about
0.45 Mt annual capacity to meet the increasing demand of non-coking coal . A Project
Report of Ghonsa Opencast Project was prepared by CMPDI RI-IV in March 2001. In this
PR (capacity-0.45Mty) the Ghonsa OCP Block was divided in three quarries namely North
quarry, Central quarry and South quarry. The proposed quarriable area was bounded by
State high way No.233 in North, Vidharbha river in West and South and incrop of Seam-I
in East. The quarriable area is separated by underground project by the barrier of State
highway No.233 passing over the property. It was proposed to work these quarries by
departmental HEMM. This PR was not yielding the requisite IRR for approval. However, an
annexure was enclosed in this PR indicating economics of working in South quarry only,
by total hiring of HEMM. The total Hiring option for south quarry only was yielding 49.45%
IRR at 85% production capacity.
The WCL Board in its 167th Meeting, held on 9.10.2001 approved the total hiring option for
South quarry only, for an initial capital of Rs.6.99 crores and for an annual targeted
capacity of 0.30 Mty.
The environmental clearance for this project was obtained from MOEF in January 2005.
Subsequently, a RPR for Ghonsa OC expansion with a rated capacity of 0.45 MTPA with
293.65 ha has been prepared and approved by WCL Board.
Based on above referred RPR, the Form – 1 was submitted to MOEF through MOC vide
letter no. 43011/29/2009- CPAM dated 28.05.2009. It was discussed in the Expert Appraisal
Committee of MOEF on 24.06.2009 and Terms of Reference (TOR) has been issued by
MOEF vide its letter no, J- 11015/165/2009 –IA.II (M) dated 08.07.2009.
As directed by MOEF vide aforesaid TOR, Public Hearing document was prepared and
submitted to Maharashtra Pollution Control Board for conduction of PH as per EIA
Notification, 2006. The Public Hearing was successfully conducted by MPCB on
09.08.2011. Based on the suggestions made in the Public Hearing, the final EIA/EMP was
prepared submitted to MOEF for obtaining Environmental Clearance as per EIA
Notification, 2006.The Environmental Clearance for Phase – I of the project within the
existing land was accorded by MOEF vide its letter no. J – 11015/165/2009-IA.II(M)
dated 29.02.2012.
Now it is envisaged that the mine within the sanctioned land area can produce beyond
the sanctioned capacity of 0.45 MTPA. Therefore, this proposal has been prepared for
obtaining Environmental Clearance u/s 7.2 of EIA Notification, 2006 for Ghonsa OC Expn.
for a peak capacity of 0.60 MTPA within the already sanctioned land area of 128.79 ha.
1.1 LOCATION
Ghonsa Block covering an area of 2.80 sq. k.m. forms part of Ghonsa / Kumbharkhani
rift basin coalfield and falls in Wani Taluq of Yavatmal Distt. of Maharashtra
State. The area is bounded by latitudes 19o57'11" and 19o58'35" N and longitudes 78 deg
49'30" and 78 deg 50’25" E, and is covered by Survey of India Topo Sheet No. 561/13
shown in Plate No.I.
1.1.1 AREA OF THE PROJECT IN SQ. KMS.
The area of the proposed mine is 2.80 km2 including the land already acquired for
Ghonsa South Quarry. The present proposal for enhancement in production capacity
has been envisaged in already acquired land of 128.79 ha.
1.2 ACCESSIBILITY AND COMMUNICATION
Ghonsa Block is an interior under-developed region of Yavatmal District. Ghonsa village
at the north-west corner of the Block is connected by S.H. NO.233 from Wani town which
in turn is connected with NH-7 to Hyderabad via Pandharkawada. The distance of
Ghonsa village from Wani town is about 20 km. The project area may be approached
from Wani-Patan main road via. Rasa- Kumbharkhani fair weather road having distance
of about 3 k.m. from Rasa Junction.
Nearest railway station to Ghonsa Block is Wani in Majri-Rajur Branch of Central Railway.
A railway line from Wani to Mukutbandh passes about 10 km away at Pitur flag station
from project area.
1.3 CLIMATE AND RAINFALL DATA
Ghonsa Block has extreme climate with maximum temperature of 48OC during summer
months and about 10OC during winter. The average rainfall is about 800-1200mm. The
bulk of rainfall takes place during wet months, i.e, July, August and September. The
maximum rainfall in a day or 24 hours is of 249.4mm, recorded in Chandrapur on
14/08/1959. The direction of the wind is mainly N-S, N-W and SE-NE.
1.4 TOPOGRAPHY WITH DRAINAGE PATTERN OF AREA
Ghonsa Block exhibits gently undulating topography sloping towards Vidharbha River
flowing in the middle of the Block (Plate-II). The elevation varies from 229.08 to 240.44m.
The main drainage of the area is controlled by Vidharbha River which flows in south-
westerly direction passing through Central and Southern property and finally meets with
Penganga River. A few small seasonal nullahs passing through the property drain into
Vidharbha River during rainy season. HFL of Virdharba river is recorded in 1990 as 237.15
m.
1.5 SOURCES OF DATA
This report has been formulated using various data from the following sources:
SN Type of Data Sources
1 Mining and economic parameters and
other miscellaneous data
CMPDIL and Wani North Area,
WCL.
2 Environmental data including
meteorological data, air quality, dust fall
rate, water quality and noise level data.
Environmental-data generation
of Wani North Area of WCL,
Maharashtra carried out by
CMPDI.
3 Socio-economic study & Land
use/cover mapping buffer zone.
Base line Socio - Economic
survey.
4 Flora and fauna Survey Report prepared by the
competent authority in this field.
5 Surface hydrology and hydrogeology CMPDIL, RI- IV, Nagpur.
6 Meteorological data Environmental-data generation
of Wani North Area of WCL,
Maharashtra carried out by
CMPDI.
7 Land use/cover mapping core zone. As per State Govt. Record, data
supplied by the concerned
WCL area office.
To Nainp
ur
To U
mer
khed To Al la pal li
To
Adil a
bad
To Pusad
To Acha lp ur
2 9,00 ,0 00 29 ,5 0,00 0 30,0 0,00 0 30 ,50,0 00
10,5 0,00 0
1 1,00 ,0 00
1 1,50 ,0 00
1 2,00 ,000
12,5 0,00 0
1 3,00 ,0 00
1 2,50 ,0 00
12 ,0 0,00 0
1 1,50 ,0 00
11,0 0,00 0
10 ,5 0,00 0
2 9,00 ,000 2 9,50,0 0030 ,00,0 00 3 0,50 ,0 00
13 ,0 0,00 0
Gondia
To G
ondia
ToAgod a
Wun
na
Andh
ari River
Gh orajh ari T ank
Ramte k Tan k
Be mbla
Wagh
ori
Ardn
Arna R.
Ardn
Nag Nadi
Can
nal
Kanha
n River
Vaida
rbha R. P en
gan ga
Kuni River
Ward
ha Rive
r
Penc
h R
iver
NAGPUR AREA
G.M.OFFICE
G.M.OFFICE
UMRER AREA
G.M.OFFICE
G.M.OFFICE
WANI NORTH AREA
MAJRI AREA
WANI AREA
G.M.OFFICE
BALLARPUR
AREA
PENCH AREAG.M.OFF ICE
G.M.OF FICE
N
PATHAKHERA AREA
Junn arde o
Umreth
Kh irs adoh
CHHINDWARA
Sin gho ri
Mun ga wa ni
SEONI
P au nar
Amarwara Bak hari
Kara boh
Ta miaRa mpur
Shah pur
Nimpa ni Bh atora
GHORADONGRI
L in ga
L awagh ogri
Bhoina
Ka niwa ra
Gop algan j
Sau nsar
Pa ndh urna
Ch ik hal i
Mul tai
Pa tta
Warud
Masod
BETUL
Gura khar
Atne r
Morsi
J ala lk hera
Katol
Kond ha li
T ale gao nTivsa
Nan dg aon
AMRAVATI
Ch and ur
Dattapu r
Pu lg aon
De oli
WARDHA
Sai lu
S ind i
Sao ner
Kh apa
Pind kap ar
Ch an il
Ra mako na
NAGPUR
Umred
Pa un i
Samu drap ur
Jam
Alipur
Wad ki
Karan ji
P and ha rkawada
Yav atmal
Ner
Darwha
Dig ras
Ja vat
Gh ugu s
Bori
Ra jur
Waro ra
Kha rsin gi
Ch imu r
Shan karp urBh is i
Tem pa
Na gbh ir
Sind ewahi
Bh an dara
T umsa r
Go regh at
Piparwah i
Kh awasa
Ramtek
Kam ptee
Mo uda
Bu ttib ori
Wa ni
Bad nera
Gud gaon
Bh awra
Narkh er
Se oni Ch apara
Amla
Ash ti
Madh eri
Bal l arshah
Arvi
Hin ga ngh at
Gadc han dur
Sasti
Rajura
CHANDRAPUR
CHANDRAPUR AREA
Kalmes hwar
G.M.OFFICE
Ma nikga rh
G.M.OFFICESala iy a
Te kad han a
Ch en kab ori
Ra nipurKa lme sura
Sh ega on
KANHAN AREA
G.M.OFFICE
Ka nh an
Wardha
R iver
LOCATION PLAN OF W.C.L. AREASSCALE :-
0 1 0Km. 20Km.
M A H A R A S H T R A
M A D H Y A P R A D E S H
A. P.
Pa rasia
Jo dmoh a
Sa rni
WCL AREAS
MADHYA PRADESH
• Pathakheda
• Pench
• Kanhan
MAHARASHTRA
• Nagpur• Umrer
• Wani• Wani North
• Majri• Chandrapur
• Ballarpur
INCLINE MINEBHANDEWADA
CHINCHALA O/C
PRPR
GR
PISGAON BLOCK
GR
GR
Index Sheets
5511L
5512L
569I
5613I
561M
554P
553P
5515L
16L
55
WAGHDHORA
CHIKALGAON O/C
PR
GR
AREA
2500m1500m500m
1000m0m 2000m 3000m
3500m
WANI BLOCK
MANDAR
BLOCK
GR
CHAPTER-II
PROJECT PROFILE
2.0 BACKGROUND/INTRODUCTION
Directorate of Geology & Mining (Govt. of Maharashtra) commenced Regional
Exploration in Ghonsa-Kumbharkhani rift basin in July 1982, and drilled 84 boreholes (RB
series) in this area. D.G.M(M.S) proved about 8 km. of strike extension of coal seam in NW-
SE direction.
This Block was surveyed by CMPDI in dry season of 1990, and prepared a geological
report entitled “Geological assessment of Ghonsa Block, May 1991”, RI–IV Nagpur.
Based on this geological report, opencast department of RI-IV prepared a project report
entitled “Ghonsa Opencast Project Report “ in September,1990.
It may be noted that in Dec. 1992 MECL drilled 14 (MGN series) more boreholes for
structure proving in Ghonsa dip extension area and published a report as “Geological
report on exploration for coal Ghonsa dip extension Block” Dec. 1992.
To prove the existence of coal Seam in the rise side as well as dip side to plan
Kumbharkhani U.G project, additional 12 boreholes (MWKK series) were drilled by MECL.
MECL subsequently prepared a geological report entitled “ Geological note on
exploration for coal, Kumbharkhani Underground Block, Aug. 1998”. Drilling was
continued to establish the further continuity of coal seam in NW of Ghonsa Dip Extn. And
Kumbharkhani Blocks and GR for Ghonsa (NW) Extn. Block was submitted in
November,1999.
2.2 DIFFERENT GEOLOGICAL REPORTS PREPARED AT DIFFERENT PERIOD FOR THE BLOCKS
UNDER REFERENCE
a) Geological Assessment of ‘Ghonsa’ Block, Wardha Valley Coalfield, CMPDI,
March,1988.
b) Geological Report on Exploration for Coal ‘Ghonsa Dip Extn.’ Block, Wardha
Valley Coalfield, MECL, December,1992.
c) Geological Report on Exploration for Coal ‘Kumbharkhani UG Block, , Wardha
Valley Coalfield, MECL, August,1998.
d) Geological Report on Exploration for Coal ‘Ghonsa(NW) Extn.’ Block, , Wardha
Valley Coalfield, MECL, November,1999.
2.2.1 BLOCK BOUNDARIES / AREA OF THE BLOCK
The area of the mining Block is 1.35 km2.
2.2.2 The mining Block has opencast potentiality.
2.3 EXPLORATION STATUS
2.3.1 Number of Boreholes and Meterage drilled by the various Agencies and period of
drilling thereof, in the Block Area 24 boreholes (RB and MWKK series) were drilled in
1.35 km2 quarry area. Total meterage is 1259.35. Borehole density is 18.
2.3.2 SURVEYING
Survey in the Block was initiated from the boreholes RB-40 and RB-37 drilled by DGM
(MS) & Triangulation Station T2 . The Coordinate of these reference points carried from
boreholes RB-46 and RB-48 in the Ghonsa Block are as follows :-
Station North East
1. Borehole RB-37 10,78,206. 8556 29, 82, 814. 4607
2. Borehole RB-40 10,77,680.1808 29,83,414.3071
3. Triagulation Station T-2 10,78,214.3991 29,82,881.8980
Prior to this, the boreholes RB-46 & RB-48 falling in the Ghonsa Block were connected in
the National Grid (Conformal Conic Projection) with reference to the base line pillar of
Rajur Colliery. The difference of grid bearing of boreholes RB-46 to RB-48 is taken into
account for conversion of Co-ordinates into National Grid as shown below :-
1. Bearing of RB-46 to RB-48 in National Grid : 174 O 49 Min. 12 Sec.
2. Bearing of RB-46 to RB- 48 in Local Grid : 175 O 16 Min. 15 Sec.
3. Difference in National Grid & Local Grid : 00 O 27 Min. 03 Sec.
bearing
Subsequently all the boreholes of the MWKK series were connected to National Grid by
triangulation method. All the old boreholes falling within the Kumbharkhani (UG) Block
are transferred from the CMPDIL report “ (Geological Assessment Report - Ghonsa
updip part”) and were in accordance with the “Geological Report for Exploration for
coal, Ghonsa Dip Extension Block”. The reduced level were carried from borehole No.RB-
37, value of which 237.57 m.
2.3.3 NUMBER OF BOREHOLES ANALYSED BAND BY BAND AND SEAM OVERALL PROXIMATE
AND ULTIMATE ANALYSIS
Coal Analysis
a) Band by Band Analysis - 20
b) Overall Analysis - 18
c) Ultimate Analysis - 3
d) Total Sulphur and Sulphur distribution - 5
e) Ash Fusion Temp. Range - 2
2.4 RELIABILITY OF DATA AND DEGREE OF CONFIDENCE
1. Since borehole details of RB series boreholes except RL and FRLs are not available,
the thickness range of different formations and coal seam have been given based
on MWKK series boreholes only.
2. The main purpose for drilling MWKK series boreholes was to ascertain 15 m hard
cover line and to carry out physico-mechanical tests of strata. As such, only band
by band analysis of coal samples were carried out.
3. All the faults are considered to be normal gravity fault and assumed to have 60o
dip. These faults are considered as pre-kamthi and hence projected upto floor of
Kamthi/Lameta formatioin.
4. The subcrops of seam have been drawn at the base of Lameta/Kamthi formation
based on the available sub-surface data and hence it has its own limitations.
2.5 GEOLOGY AND STRUCTURE OF BLOCK AREA
2.5.1 GEOLOGICAL SUCCESSION / REGIONAL GEOLOGY
Regional Geological sequence, Wardha Valley Coalfield Age Formation Lithology
Recent to Sub recent Detrital
mantle
Black cotton soil, sandy soil, Kankar etc.
Eocene Deccan Trap Basalts
UNCONFORMITY
Cretaceous Lametas Cherty Limestone, Silicified sandstone
UNCONFORMITY
Upper Kamthi Red, brown, medium to coarse grained sandstone
Permian-Lower
Triassic
Variegated clay and shale bands.
UNCONFORMITY
Middle Permian Motur Medium to fine grained variegated sandstones,
Variegated clays and shales.
Age Formation Lithology
Lower Permian Barakar Predominantly grey to white, medium to coarse
Grained sandstone with minor shales,
Carbonaceous shales and coal seam
Upper Carboniferos Talchir Greenish to grey coloured sandstone, siltstones
and shales
Lower Permian
UNCONFORMITY
Precambrian Sullavai
sandstone,
Pakhai
Limestone
White to light brown quartzitic sandstones,
Conglomerates. Grey, bluish or pinkish limestones
and cherts.
UNCONFORMITY
Archaean Metamorphic Quartizites, granite, Gneisses, Schists. Etc.
Geology of the Block
The lithological formations of the Block are given in thickness wise in followingtable:-
Age Formatio
n
Lithology Thickness Range in Metres
North Quarry South
Quarry
Central
Quarry.
Min Max Min Max Min Max
Recent
to Sub
Recent
Soil/
Weather
ed
Zone
Black cotton soil,
sandy soil
Nil
(R.B.
54)
9.00
(MWKK
– 9)
Nil(R.
B.38,
39,
etc)
14.0
0(M
KK-
1)
Nil
(RB-
20,
37)
14.0
(MWK
2,3)
Cretace
ous
Lametas Fine to medium
grained dull white
celcareous
sandstone
Chocolate
coloured clay,
reddish and grey
shale, limestone,
siltstone.
Nil
(R.B-
21,22)
18.30
(R.B.-
16)
Nil
(MW
KK-
1,12)
12.2
0
(R.B.
-38)
Nil
(MWK
-2)
23.8
(RB-
20)
Unconformity
Upper
Permian
to
Lower
Triassic
Kamthi Fine to coarse
grained, pinkish,
brown ferruginous
sandstone,pink, grey
sandy shale
Nil(R.B
21,22,2
5)
17.44
(MWKK
-6)
Nil
(R.B.-
38,
39)
22.7
4
(MW
KK-
1)
Nil
(RB-
19,
20,
37)
17.0
(MWK
-2)
Unconformity
Upper
permian
to
middle
permian
Moturs Medium grained red
to pink sandstone,
veriegated shale.
Nil 18.30
(R.B.-
21)*
Nil
Nil
Nil
11.0
(MWK
-
5)
Nil
53.
75 (RB
-20)
Lower
permian
Barakars Medium to coarse
grained and gritty
grey sandstone,
grey shale, sandy
shale, elternate
sandstone and
shale carb, shale
and coal
17.66
(MWKK
-9)
80.65
(R.B.-
16)
14.38
(MW
KK-4)
67.1
0
(R.B.
-63)
Upper
carbonif
erous to
lower
permian
Talchirs Talchirs Greenish
shale
Not
encou
ntered
- Not
enco
unter
ed
-
Not
Encou
ntere
d
Not
Encou
ntere
d
* Moturs met in borehole R.B-21 which is in North Quarry.
FORMATIONS
BARAKAR FORMATION :-
It is coal bearing formation. The Barakar Formation which overlies Talchirs conformably
are not found exposed and is represented by grey to whitish feldspathic sandstone
variates, shale, carbonaceous shale and two coal seams as encountered in boreholes.
MOTUR FORMATION :
Motur formation conformably overlies the Barakars. It is characterised by brick-red,
purple, brown, chocolate brown and greyish clays with Occasional sandstone bands,
and siltstone, etc. The transition zone between Moturs and Barakar is generally marked
by grey clay and siltstones. Motur in Ghonsa Dip Extension is found intersected in 13
boreholes. Howerver in quarry area only B.H. RB-21 has encountered Moturs.
KAMTHI FORMATION:-
The Kamthi Formation is also not exposed in the area. Subsurface data show the
presence of Kamthi in this Block and is represented by reddish brown sandstone and
variegated clays.
LAMETA FORMATION :
Lameta Formation overlies the Kamthis with an unconformity. This is mostly represented
by Limestone/claystone.
SOIL
The soil in the area is mostly sandy and clayey associated with Kankar.
STRUCTURAL SETTING WITHIN THE PROJECT AREA
The Gondwana sedimentation in Wardha Valley Coalfield has taken place in NW-SE
trending rift basins separated by Vindhyans. Ghonsa Block is located in the Ghonsa-
Kumbharkhani rift basin. The area under report is covered by thick blanket of soil and
Kamthi formation. The geological structure, therefore, is mainly based on the data
obtained from the boreholes. The interpreted structure of the area under report is
presented in the form of floor contours of coal seams at 10 m. interval.
DIP AND STRIKE
In general, the beds have NW-SE strike with minor swing in the region north of borehole
MWKK-6 to MWKK-7 & R.B- 16 where it gradually becomes NNW-SSE. The beds generally
dip 1 in 9.5 due south west to SSW with minor variation. Generally dip becomes gentler
towards the subcrop region and towards northern part. In the south-eastern part and in
the west central part the dip is slightly steeper.
NO. OF FAULTS AND THEIR CHARACTERISTIC & FEATURES
Block is affected by total 5 faults of which two minor faults F4-F4 and F5-F5 occur in
proposed quarry area. Fault F4-F4 traverses in SE-NW direction in the South Eastern part
of the Block in between MWKK-11 and MGN-2 & RB-33 and MGN-5. The throw of the fault
ranges between 2 m. and 5 m. within the Block. The dip of the fault is assumed to be 60o
due south west. The other fault F5-F5 is NE-SW throwing towards NW. The throw of this
fault is 10 m. This fault is evidenced by the absence of coal seams in B.H. R.B-3 and RB-45.
Fault F4-F4 defines the southern boundary of the Block.
2.5 COAL SEAM & QUALITY
The occurrence of two coal seams designated as Seam-II & I has been proved by drilling
in Ghonsa OC Block. The depth of occurrence (floor) thickness range and parting is
given for the Block in table below.
DEPTH RANGE, THICKNESS RANGE AND PARTING IN
GHONSA BLOCK
Seam/Parting Depth Range (floor)
(m)
Thickness Range
(m)
Min. Max. Min. Max.
Seam-II 14.30 63.35 2.12 6.30
(R.B. 39) (R.B. 21) (MWKK-2) (R.B. 16)
Parting 12.30 (R.B. 22) to 17.67 (MWKK-12)
Seam-I 14.45 80.80 1.00 3.50
(R.B.-40) (R.B.-21) (R.B.-63) (R.B.-41)
Parting 6.95 m (R.B. 48) to 8.41 (R.B. 4)
Local Seam 24.05 86.35 0.20 1.10
(R.B. 42) (R.B. 44) (R.B. 54) (R.B. 46)
The opencast Block is divided as North quarry, South quarry and Central quarry. The
depth, thickness, parting range quarrywise is as follows
QUARRYWISE DEPTH, THICKNESS & PARTING RANGE
Quarry Sea
m
Depth Range(Floor) Thickness (m) Parting
Min. Max. Min. Max. Min. Max.
North II 18.45
(R.B 17)
63.35
(R.B. 21)
3.57
(MWKK-6)
6.30
(R.B. 16)
12.30
(R.B. 22)
17.42
(MWKK-6)
I 30.25
MWKK-9
80.80
(R.B. 21)
1.12
(MWKK-6)
2.93
(R.B. 16)
South II 14.30 (R.B.
39)
28.32
(MWKK-1)
2.12
(MWKK-1)
5.40
(R.B. 38)
15.87
(R.B. 41)
17.67
(MWKK-12)
I 14.45
(R.B. 40)
47.75
(MWKK-1)
1.00
(R.B. 63)
3.50
(R.B. 41)
Central II 12.75
(RB- 19)
26.91
(RB-20)
2.68
(MWKK-2)
3.80
(R.B. 19)
15.00 17.77
I 16.50
(MWKK- 5)
46.70
(RB20)
1.40
(MWKK-3)
2.50
(MWKK-5)
SEAM-II
The coal seam-II has been intersected in total 18 boreholes of North, South and Central
quarries. The seam is devoid of obvious dirt band (Ash+Moisture > 75%). The details of
dirt band and effective thickness is given in Annexure-III. The seam is workable
throughout the Block.
ROOF & FLOOR STRATA
The immediate roof of the seam is mostly sandstone at places it is sandy shale. The
immediate floor of the seam is mostly shaly sandstone to sandstone intercalations.
SEAM-I
Coal seam-I has been intersected in total 24 boreholes of North , South and Central
quarries. The seam contains 1 number of obvious dirt band of 0.13 to 0.27 m in
thickness. The details of dirt bands are given in Annexure-IV. The seam thickness near
borehole MWKK-6 and R.B-63 is 1.12 m & 1.00 m respectively.
ROOF & FLOOR
The immediate roof of the seam is mostly sandstone occasionally shale to arnaceous
sandstone. The floor is predominantly sandstone/ & shaly sandstone.
PARTING BETWEEN SEAM-II & SEAM-I
The thickness of parting between Seam-II to Seam –I ranges between 12.30 m to 17.77
m. and is composed of sandstone, grey shale, alternate shale and sandstone, clay and
carb shale.
QUALITY
PROXIMATE ANALYSIS DATA - SEAM-II
The quality of boreholes falling within quarriable area is available as equilibriated
calculated or determined at laboratory at 60% R.H & 40oC basis and is given below
PROXIMATE ANALYSIS OF SEAM-II
Particul
a-rs
SOUTH QUARRY NO. OF B.H
CONSIDERED
Min. Max. S-Q
Moistur
e %
4.79
(MWKK-12)
8.3 (R.B.
41)
5
Ash% 22.7
(R.B. 38)
32.84
(MWKK-12)
5
V.M% 26.2
(R.B 38)
26.2
(RB-38)
1
F.C% 26.2
(R.B. 38)
26.2
(RB-38)
1
UHV
k.Cal/k
g
3707
(MWKK-12)
4650
(R.B. 38)
5
Grade E D 5
G.CV
k.Cal/k
g
4768 5241 8
SPECIAL TESTS – SEAM-II
(1) TOTAL SULPHUR AND DISTRIBUTION OF SULPHUR.
B.H.
Name
Depth of
Seam(m)
Total S% Distribution of Sulphur
Pyritic % Sulpha
te
Organic
%
NORTH QUARRY
R.B. 21 58.85 63.35 3.14 1.58 0.87 0.69
R.B. 22 54.90 59.00 2.67 1.35 0.67 0.65
R.B. 27 29.30 35.36 3.35 1.84 0.77 0.74
SOUTH QUARRY
R.B. 38 14.30 19.70 1.87 1.35 0.29 0.23
CENTRAL QUARRY
RB-20 57.00 62.80 2.09 - - -
(2) ULTIMATE ANALYSIS
B.H.
Name
Depth of
Seam(m)
Ultimate analysis on 60% RH at 40oC basis
From To Carbon
%
Hydroge
n
Nitrogen
%
Sulphur
%
NORTH QUARRY
R.B. 22 54.90 59.00 49.21 2.93 1.05 2.67
R.B.
33
28.30 31.80 48.68 2.78 1.05 2.13
SOUTH QUARRY
R.B.
38
14.30 19.70 52.83 2.83 1.16 1.87
CENTRAL QUARRY
- - - NIL - - -
(3) ASH FUSION TEMPERATURE
The ash fusion Temperature range of coal seam have been determined by CSL, Nagpur,
the results are as follows
B.H.NO
.
Depth of Seam
(m)
Ash Fusion Temperature
Range(OC)
Remarks
From To Initial
Deform
ation
Temp
Hemisph
erical
Temp
Flow
Temp
R.B. 22 54.90 59.00 1260 1400 Over
1400
North Quarry
R.B. 33 28.30 31.80 1200 Over
1400
Over
1400
B.H in the vicinity of
quarriable area of South
Quarry
OVERALL QUALITY OF SEAM-II (UNDILUTED)
Following Table shows the range of U.H.V 3707 to 5036 k.Cal/kg. However, the
quarrywise weighted UHV is as follows :
Quarry M% Ash% UHV
(k.Cal/kg)
GCV
(k.Cal/kg)
Grade
South 7.2 25.62 4364 5089 D
PROXIMATE ANALYSIS DATA - SEAM-I
The quality of boreholes falling within quarriable area (North , South and Central) is
available as equilibriated or determined at laboratory at 60% RH & 40oC basis and is
given below :-
PROXIMATE ANALYSIS SEAM-I
Partic
ulars
SOUTH QUARRY NO.OF BH
CONSIDERED
Min. Max. S-Q
Moist
ure %
3.64
(MWKK-12)
7.7
(R.B. 41)
7
Ash% 25.13
(R.B-41)
37.1
(R.B. 40)
7
V.M% 24.8
(R.B. 38)
- 1
F.C% 34.1
(R.B. 38)
- 1
UHV
(k.Cal
/kg)
2911
(R.B-40)
4374
(R.B.-41)
7
Grad
e
F D 7
G.CV
(k.Cal
/kg)
4147 5073 7
SPECIAL TESTS
(1) TOTAL SULPHUR AND DISTRIBUTION OF SULPHUR
B.H. NO. Depth of
Seam(m)
Total S% Distirbution of Sulphur %
From To Pyritic Sulpha
te
Organic
NORTH QUARRY
R.B. 21 78.70 80.80 2.63 1.59 0.57 0.47
R.B. 22 71.30 73.30 3.17 1.86 0.80 0.51
R.B. 27 50.30 52.50 3.02 2.12 0.89 0.01
SOUTH QUARRY
R.B. 38 36.60 39.23 1.14 0.94 0.15 0.05
CENTRAL QUARRY
R.B. 37 33.10 35.20 0.70 - - -
(2) ULTIMATE ANALYSIS
B.H.
NO.
Depth of Seam
(m)
Ultimate analysis on 60% RH & 40oC basis
From To Carbon
%
Hydrog
en
Nitrogen Sulphur %
NORTH QUARRY
R.B. 22 71.30 73.30 44.89 2.41 0.88 3.17
SOUTH QUARRY
R.B. 38 36.60 39.23 44.05 2.62 1.00 1.14
CENTRAL QUARRY
- No data -
(3) ASH FUSION TEMPERATURE
Ash fusion temperature is available for only 1 borehole i.e. R.B.-22 in North Quarry.
B.H.
Name
Depth of Seam
(m)
Ash Fusion Temperature Range
From To Initial Deformation
Temp (oC)
Hemispheri
cal Temp
(oC)
Flow
Temp
(oC)
R.B. 22 71.30 73.30 1300 Over 1300 Over
1400
OVERALL QUALITY OF SEAM-I (UNDILUTED)
Following Table shows the range of UHV for Seam-I for different quarries, The overall
weidhted U.H.V. for different quarries are as follows :
Quarry M% Ash% UHV
(k.Cal/kg)
GCV
(k.Cal/kg)
Grade
South 5.89 34.13 3377 4486 E
Quarrywise quality of Seam-II & Seam-I combined
Dilution Parameters South Quarry
Undilute
d
Moisture % 6.41
Ash % 30.88
UHV(k.Cal/kg) 3754
GCV(k.Cal/kg) 4717
Grade E
Grade F
5 cm
dilution
at each
contact
point
Moisture % 6.36
Ash % 32.59
UHV(k.Cal/kg) 3525
GCV(k.Cal/kg) 4563
Grade E
2.6 HYDRO-GEOLOGICAL INFORMATION
2.7.1 HYDRO-GEOLOGICAL DETAILS
Ghonsa Block is the western most extension of the coal belt in Wardha Valley and it
falls under the administrative jurisdiction of Yeotmal district, Maharashtra. This Block is
situated in the Penganga basin and is mostly drained by the south easterly flowing
perennial Vidharbha river which is one of the major tributaries of Penganga river.
2.7.2 HYDROGEOLOGICAL REGIME
The proposed mine area is mostly covered by Lameta/Kamthi formations which are
concealed by black cotton soil layer of limited thickness. However, the surrounding
area (buffer zone) is occupied by Deccan Trap formation. Ground water occurs in the
area under both confined and unconfined conditions.
Unconfined acquifer, in general, extends down to a depth of about 25 m below
ground level (bgl) and is taped by dug wells for domestic and agricultural use. Depth
to water table in the area varies from 1.0 m to 7.0 m bgl in post monsoon period
while it attains deepest level ranging from 3.0 to 10.0 m bgl in pre-monsoon season.
Water table fluctuation between the two extreme seasons varies between 2 and 5 m.
Normally, water table has configuration similar to that of topography but with
reduced relief. The ground water flow direction has been inferred to be south –
easterly with hydraulic gradient of 1.8 x 10 –3 (regional average) which may represent
Ghonsa Block as well. The yield of dug wells in Kamthis is from 100 m3/day to 350
m3/day. The specific capacity varies from 90 to 165 litres per minute/metre of
drawdown.
In respect of confined/semi-confined aquifer in Kamthi/Barakars, the tubewells
constructed have registered an yield of 2 LPS to 10 LPS (regional values).
The water is generally alkaline in nature with pH value ranging from 7.5 to 8.4 and it is
also of good quality with electrical conductivity values less than 750 micromhs/cm.
Further, the proposed mine area may be in the discharge zone in view of facts like
shallow to moderate depth of water levels, low order water fluctuations etc.
2.7.3 GROUND WATER PREDICTIONS
In the absence of site specific parameters, the following acquifer parameters which
are established at Rajur and Baranj Blocks have been presumed for quantification of
anticipated ground water inflow to the quarry at the stage/time of 5 years after target
production (quarry depth approximately 50 m. mine expansion rate of 5 m/day i.e.
1.95 Mm3/year OB removal).
1. Hydraulic conductivity :
Kamthis : 5 m/day
Barakars : 1.7 m/day
2. Specific yield : 0.03
3. Storage co-efficient : 0.005
4. General water level : 5 to 6 m. bgl
5. Saturated thickness:
Kamthis : 10 m.
Barakars : 24 m.
6. Transmissivity :
Kamthis : 50 m2/day
Barakars : 41 m2/day
By utilizing the above parameters, the anticipated ground water inflow into the
quarry has been worked to be around 40 LPS at the time of 5 years after target
production (coal- 2.25 Mt & OB 11.64 Mm3).
2.7 GEOLOGICAL RESERVES
BRIEF METHODOLOGY ADOPTED FOR RESERVE ESTIMATION
Boundaries:
The Block boundaries considered for reserve purpose as under.
North - Subcrop of Seam-I and Block boundary as shown in the Seam Folio plan :
Seam-I
South – Fault F4-F4
West - Block boundary & Wani Patan Road.
East - Fault F5-F5
NORMS AND ASSUMPTIONS
(1) Reserves have been calculated on the basis of In-band thickness. The carb shale
bands and obvious dirt band included in seam is given in Annexures III & IV of
Seam-II & Seam-I.
(2) A deduction of 10% from the gross reserves has been made to arrive at the net-in-
situ geological reserves of coal to give allowance for likely geological uncertainties
such as unidentified faults, local wash outs, swings and rolls, etc.
(3) The area has been divided into 2 sectors, viz. East of East Bank of Vidarbha river and
West of East Bank Vidarbha river or beyond river to Block boundary.
Geological Reserves
Net geological reserves (Mt) for the Block is as follows :
Seam Area East of Vidarbha
river to Subcrop of
Seam
Area West of East Bank of
river to Block boundary
Total Mt
Seam-II 8.556 Mt 3.662 Mt 12.218 Mt
Seam-I 6.042 Mt 2.238 Mt 8.280 Mt
Total 14.598 Mt 5.900 Mt 20.498 Mt
It may be noted here that Net Geological Reserves of Ghonsa Geological report of
CMPDI May ,1991 are 13.419Mt , in addition Net Geological reserves of Sector ‘A’ of
MECL Geological report of Ghonsa Dip Extn. Block Dec,1992 and N-W part of SH No. 233
reserves have been considered to arrive about 20.498 Mt of Geological Net reserves.(i.e.
13.419 + 5.501 + 1.578 = 20.498)
Out of total 14.60 Mt net geological reserves above Vidarbha river only 7.83 Mt net
Geological reservs ( 7.05 Mt. extractable reserves ) have been considered for OC
mining. Details of Blocked reserves are given below :-
Sl.No. PARTICULAR RESERVE BLOCKED (MT)
1. Between Quarry floor and River ( because of
flood protection Embankment)
5.42
2. Due to S.H. No.233 1.25
3. Due to Kumbharkhani Village 0.10
Total 6.77
PIT FORMULATION STRATEGY
As described earlier only two workable coal seams viz; Seams-II & I have been
encountered in Ghonsa Block. The thickness of these seams in quarriable area viaries
from 2.38-6.30m. and 1.35-3.15 m respectively These seam generally contains 1-2 Nos. of
thin carb-shale bands.
However, in few boreholes, grey shale band has also been found to have developed
within this seam. The parting between these two seams varies from 13.96 m to 17.77 m.
2.9 MINEABLE RESERVES:
The net geological reserves available in the Block is 20.50 Mt out of which only 1.73 Mt is
available for quarrying within the limit of the present expansion proposal.
2.10 TARGET OUTPUT & MINE LIFE:
The proposed peak output of mine is 0.60 MTPA of ROM Coal.
2.11 METHOD OF MINING
GEO-MINING CHARACTERISTICS
DETAILS OF SEQUENCE OF COAL SEAM AND PARTING
Name of coal
seam/parting
Thickness of coal
seam/parting (m)
SEAM II 2.12 to 6.30
PARTING 12.30
SEAM I 1.00 to 3.50
MINE PARAMETERS
Sl. PARTICULARS South Quarry
1 Area of the Quarry
(a) On floor (Ha.) 27.68
(b) On surface (Ha.) 38.05
2. Depth (m)
(a) Initial 13
(b) Final 46
3. Gradient of Seam 1 in 12.0 to 1 in 10.5
4. Effective thickness of seam (m)
(a) Seam-I 1.00 to 3.50
(b) Seam-II 2.12 to 5.40
5. .Strike length (m) 955
6. Width on surface (m):
(a) Maximum 510
(b) Minimum 180
7. Mineable reserves (Mt) 1.73
8. Total OB incl. Access Trench
(Mm3)
8.54
9. Average S.R. m3/t. 4.94
CHOICE OF TECHNOLOGY:
The shovel dumper combination has been proposed in this mine. As the total mineable
reserves are only 1.73 Mt, application of dragline and surface miner have been ruled out.
Moreover, the application of dragline or surface miner will not be economically viable in
the prevailing geo-mining conditions. The thin seam thickness (2m to 4m) of seam-I and
seam-II calls for smaller size HEMM. Shovel-Dumper combination is very flexible and most
adopted technology in WCL. The mine at present is being worked through total out –
sourcing option and will continue to be worked with the same. The proposed
enhancement in production capacity will be achieved without addition of any any
resources interms of machine and/men. The list of equipments in place at the mine is as
given below:-
Sl.No. Name/Type of Machine with Capacity Nos.
1. Front End Loader – 2.00 Cum 3
Front End Loader – 1.75 Cum 1
2. Tipper – 12.00 Cum 9
Tipper – 10.00 Cum 5
3. Drill – 160 mm 1
Drill – 150 mm 1
4. Dozer – 165 HP 1
Dozer – 150 HP 2
5. Grader – 145 HP 1
6. Water Sprinkler – 8000 Litres 1
MINING SYSTEM & SYSTEM PARAMETERS
Slope of quarry batter has been kept as 37 degree in rise side of quarry whereas the
dipside batter angle is proposed 40 degree. Slope of the working benches would be
kept at 70 degree. Haul Road would be constructed with help of motor grader and
dozer on the floor of Quarry at the gradient of 1 in 16.
WIDTH OF WORKING & NON-WORKING BENCHES
For overburden keeping the bench height of 10 m, the width of working and non-
working benches have been kept as 30 m and 20 m respectively. For coal, bench
height would depend upon the thickness of seam, bench width for coal for working
and non-working benches would also be kept as 30 m and 20m respectively.
HEIGHT OF BENCHES
The height of benches in overburden has been kept as 10m while in coal seam, height of
bench has been kept same as thickness of coal seam i.e. 2m & 4m.
All effort has been made to maximise the backfilling while preparing the calendar
programme of the mine.
EQUIPMENT SCHEDULE
It is envisaged in the PR that total excavation (Top OB, Parting and coal) would be done
by Hiring of HEMM. No departmental HEMM is proposed for mining purpose.
DRILLING & BLASTING
The degree of fragmentation in opencast mine has to be optimised so that total cost of
drilling, blasting, excavating, transport and crushing as a total system is minimised.
In order to reduce the excessive vibrations at nearby village, surface structures, river,
road, etc. and also to achieve satisfactory blasting results, an optimised control
blasting system depending upon rock formations using combination of delays and
relays will have to be evolved. It is further recommended that at the time of actual
execution, proper study on ground vibration should be made with scientific methods.
The amount of top soil is about about 6.50 Mm3 out of the total OB of 38.65 Mm3.
Controlled blasting is to be done near Kumbharkhani Village to avoid fly rock and
ground vibration as distance between village and South Quarry is approx. 100 m. For
storage of explosive 3 magazines having 3 t capacities each have been proposed in the
PR.
2.12 COAL QUALITY
INTRODUCTION
The Occurrence of two coal seams designated as Seam-II & I have been proved by
drilling in Ghonsa OC Block. The depth, thickness range and parting for the Block is given
in table below.
Seam/Parting Depth Range (floor) (m) Thickness Range (m)
Min. Max. Min. Max.
Seam-II 14.30 (R.B. 39) 63.35 (R.B.
21)
2.12 (MWKK-2) 6.30 (R.B. 16)
Parting 12.30 (R.B. 22 to 17.67 (MWKK-12)
Seam-I 14.45 (R.B.-
40)
80.80 (R.B.-
21)
1.00 (R.B.-63) 3.50 (R.B.-41)
Parting 6.95 m (R.B. 48) to 8.41 (R.B. 4)
Local Seam 24.05 (R.B. 42) 86.35 (R.B.
44)
0.20 (R.B. 54) 1.10 (R.B. 46)
Local seam has not been considered in this project report as it is very thin & impersistent.
QUALITY ANALYSIS
The Quality of seams with & without contamination is given below :-
Dilution Parameters South Quarry
Undiluted Moisture % 6.41
Ash % 30.88
UHV(kcal/kg) 3754
GCV(kcal/kg) 4717
Grade E
5 cm dilution at each
contact point
Moisture % 6.36
Ash % 32.59
UHV(kcal/kg) 3525
GCV(kcal/kg) 4563
Grade E
2.13 WORKSHOP, STORES & MAGAZINE
BRIEF TEXT
All HEMM deployed in this mine will be hired and their maintenance will be contractor’s
responsibilities. Hence, there is no provision of any unit excavation workshop in the report.
E & M workshop facilities have been provided to carry out the maintenance and repair
of the CHP equipment, pumps, electrical etc. of the mine. This E & M workshop will be
supported by Regional/Central workshop for major repairs and parts manufacture,
because it is essentially a pithead maintenance workshop.
UNIT STORES: -
One small and independent unit stores has been provided at convenient location to
cater the routine needs of consumables, spares, POLs etc. This will depend on
Regional/Central stores for major spares. Unit store lay out drawing is not given in this
project.
2.14 SAFETY & CONSERVATION
DEGREE OF GASSINESS
Proposed degree of gassiness of seams are Degree-I.
INUNDATION
Vidharbha river is flowing in the dip side of the project and quarry area is under HFL
hence there is possibility of danger of innundation from surface water. However,
necessary embankment 6 m above HFL (237.15 m) of the river has been proposed and its
alignment is shown in Quarry & Surface Layout Plan.
DUST SUPPRESSION
For suppression of dust hiring charges for water sprinkling has been included in the
RPR. Suppression of mine dust may be done by using package bond & dust bond,
for methodology of application DGMS Circular No.8 of 1997 may be referred.
FIRE AND SPONTANEOUS HEATING
(1) Wild or herbaccous plants shall be removed from the mine.
(2) No person shall deposit heated material or ashes on any opencast working. Also no
person shall light a fire or permit a fire to be lighted in any OC working except by the
permission in writing of the Manager and only for a special purpose specified therein.
(3) No coal shall be left exposed more than its incubation period to avoid fire in
seam due to spontaneous heating.
SLOPE STABILITY
It is suggested that following action may be taken to deal with slope stability problem.
i) Vulnerable area may be identified and marked on quarry plan.
ii) Observation of actual alignment of fault plans, its throw, joints, etc. may be recorded
during the process of exploitation.
iii) Water drainage system may be properly implemented.
iv) Regular monitoring of tension cracks, horizontal and vertical movement of strata in
critical area may be done.
HAUL ROAD MAINTENANCE
Haul road would be prepared & maintained by hiring agency as per the existing
guidelines.
BLASTING
Special precautions have to be taken while performing blasting operations near
Kumbhar khani village, State highway No. 233 and Rasa Kumbhar khani road.
CONSERVATION OF COAL
Optimum exploitation of coal has to be done by controlled blasting method near
Kumbharkhani village without shifting the village. Quarry limits are finalised in such a
way to exploit maximum possible coal without rehabilitation of adopting adequate
safety distance from said villages. Although for calculation of mineable coal reserves
10% mining losses has been taken into account, but in practice all efforts would be
made to minimise the losses. Separate excavator is provided for mining coal. OB
benches would be kept sufficiently advanced to avoid mixing of coal & OB. Maximum
backfilling is proposed in mine.
Surface dumps are planned upto a maximum height of 45 m considering availability of
non coal bearing area and lithology of OB material. The height of dump may be
increased after scientific study to reduce requirement of land for OB dumping.
ADDITIONAL PERMISSION / RELAXATIONS REQUIRED FROM DGMS
SAFETY ASPECTS FOR OUTSOURCING/HIRING OF HEMM (TOTAL HIRING & PARTIAL
HIRING OPTION)
Special precaution should be taken while employing contractual labours in the mine.
Before employing those in the mine proper vocational training should be imparted and
recommendations of VIII Safety Conference should be strictly followed. Terms and
conditions shall be fixed by management for deployment of contractual labours as well
as machineries. Some of the major aspects are as follows:
A) For persons :
i) Records in Form-B & Form-E shall be maintained.
ii) Records of VTC driving licence of operators shall be kept by Operators and readily
available for inspection by management
iii) Salaries shall be distributed in front of management representative
iv) No person shall be employed unless person holds VTC certificate and Management
is informed.
v) Adequate supervision shall be maintained by competent person.
B) For Machineries :
i) All the machineries to be deployed in mines should be passed by the
management.
ii) RTO certificate photo copies of all vehicles shall be submitted to management.
iii) Daily welding, monitoring, inspection shall be done by contractor's mechanic as
directed by management.
iv) Machine manufacturers should be asked to give risk analysis.
C) General :
i) No person/vehicle shall be deployed at any place other than authorised place.
ii) All employees of contractors should obey lawful instruction of mine management.
iii) Risk Management Plan by contractor of tipper/pay loader
iv) Trained Manpower
v) Restricted traffic & traffic control planning.
2.15 ENVIRONMENT IMPACT
AIR QUALITY
Dust is likely to be generated due to coal transportation, wind erosion of OB dumps, and
coal handling.
WATER QUALITY
Mine pumped out water, after sedimentation, will be utilized within mine premises and
balance will be used for supplementing any shortage of water in the affected villages.
Moreover, analysis of water pumped out from existing mines around the proposed
project shows that even untreated water meets the acceptable limits, as such quality of
water pumped out from the proposed project not likely to have any significant pollution
load even in untreated condition.
GROUND WATER RESOURCE
Due to proposed project, it is anticipated that the effect on ground water regime will be
pronounced upto around 500 m from mine edge and effect will be pronounced in the
down-dip side and milder in the up-dip side. But this effect will be temporary in nature
and once the project is over, after 2 – 3 rains, the regime will regain its almost original
status.
NOISE IMPACT
Existing noise level at the mine site (wrt pre-mining level) is likely to increase but will be
duly controlled ( to keep well within acceptable limit ) by developing green belt around
CHP, workshop, and along roads, around colony, etc.
FLORA AND FAUNA
No changes in the diversity of species or number of any species of animal are
anticipated.
LAND USE
Regarding land use during mining, in addition to excavation of quarry for coal,
overburden dump will be created along with development of other mine related
infrastructures. Overburden dump is proposed to be technically and biologically
reclaimed along with Quarry (backfilled portion) and sufficient greenery will be
developed. As such no significant change in present land use pattern is anticipated.
CLOSURE ACTION PLAN
In case of Ghonsa OC, the mine is being planned upto a specific depth in order to
achieve economic viability.
Closure planning is a whole-of-life exercise that begins at the start of a mine and
continues till post closure. The dynamic nature of closure planning requires regular and
critical review to reflect changing circumstances as a result of any operational change,
new regulation, and new technology and remain flexible enough to cope with
unexpected events.
Following steps have to be undertaken in relation to Mine Closure Planning:
(a) Prior to the surface demolition/restoration a surface audit should be undertaken on
all surface structures, spoil heaps, lagoons, etc. to assess whether there are any
hazardous materials that could cause problems viz; explosives, chemicals, etc. A
list of surface assets should be prepared and made available to potential
purchasers, prospective purchasers could be invited and asked to submit sealed
bids. This would ensure that the sale of assets give better financial gain.
(b) In order to identify potential impact necessary hydrogeological studies into post-
mining groundwater recharge has to be done. The void of the mine can be
proposed as a water resource to be utilised for aquaculture. The option of further
deepening even after exhausting reserves upto proposed PR limits has been kept
open in this project report.
(c) As a detailed component of the Closure Plan, a Decommissioning Plan is to be
developed towards the final stages preferably 5 years prior to tentative closure of
mine. Once established it may be updated annually.
FINANCIAL ASPECT
The proposed Ghonsa OC mine has been planned upto 46 depth and it is most likely that
this will be extended further in future. Although no statutory guidelines exist on financial
provisioning for mine closure activities as yet, financial provision of Rs.6.00 lakhs/ha has
been provided throughout the mine life in order to undertake mine closure activities (for
plantation in slope of dumps & quarry, for protection of mine boundary and
continuation of monitoring programme and control of contaminated effluents). Closure
cost may be reviewed under the changing circumstances and new legislative
requirements.
2.16 SOCIO-ECONOMIC STATUS
128.79 ha of land has already been acquired. All the land losers have been suitably
compensated as per CIL’s R&R Policy. Till date, out of 69 land holdings, 55 have been
provided with employment and 3 have been given Monetary Compensation in lieu of
Employment.
ENVIRONMENT MANAGEMENT
AIR QUALITY MANAGEMENT
Ambient Air Quality will be controlled by black topping of roads, water spraying on
roads, biological reclamation of OB dumps, green belt around CHP, OB dump, and
along coal transportation roads on both sides etc.
WATER QUALITY
Mine pumped out water, after sedimentation, will be utilized within mine premises and
balance will be used for supplementing any shortage of water in the affected villages.
Moreover, analysis of water pumped out from existing mines around the proposed
project shows that even untreated water meets the acceptable limits, as such quality of
water pumped out from the proposed project is not likely to have any significant
pollution load even in untreated condition.
Effluent from workshop will be treated in ETP & thereafter recycled. Similarly, water from
CHP, after sedimentation will be recycled. For domestic effluent, adequate sewage
disposal arrangement has been proposed.
NOISE MANAGEMENT
The workers exposed to high noise level will be provided with earplugs. Provision of
enclosed booths at the worksite to protect worker from noisy environment will be made.
FLORA AND FAUNA MANAGEMENT
Adequate plantation has been proposed with native species to maintain the diversity
and also to attract the fauna.
LAND RESOURCE MANAGEMENT
Regarding land use during mining, in addition to excavation of quarry for coal,
overburden dump will be created along with development of other mine related
infrastructures. Overburden dump is proposed to be technically and biologically
reclaimed along with Quarry ( backfilled portion ) and sufficient greenery will be
developed.
ENVIRONMENT MANAGEMENT SYSTEM
To have a close watch on the environmental condition and implementation of the
various measures suggested, a multi- disciplinary approach is essential. At present WCL
headquarter acts as apex body which supervises the activities relating to environment at
project level through the General Manager. General Manager of the area coordinates
the activities of various disciplines in the area to render all necessary assistance at the
implementing level i.e. the project . Area Nodal Officer (Environment) monitors all
aspects of environment on behalf of the General Manager. He also takes suitable steps
for generation of environment data alongwith its analysis and interpretations.
As far as plantation is concerned horticulturist with suitable backup staff is provided in the
area for undertaking the plantation jobs including raising of a nursery.
Sub-Area Manager is responsible for mechanical reclamation of the area. He is also
responsible for biological reclamation with the assistance of GM’s office.
CHAPTER-III
DESCRIPTION OF ENVIRONMENT
3.0 Introduction
As explained in previous chapter, Ghonsa OC has just started operation and is being
proposed for expansion in production capacity as well as enhancement of lease area. In
order to assess the existing environmental scenario w.r.t. proposed expansion project and
as directed in the Terms of Reference issued by MOEF, the base line environmental data
has been generated covering the core & the buffer zone of the proposed project during
winter season of 2009-10. These data has been generated during 1st December 2009 to
28th February, 2010 in respect of socio – economic profile, ambient air, ground & surface
water quality, ambient noise level, flora & fauna and the same have been described in
detail in subsequent paragraphs.
3.1 SOCIO-ECONOMIC PROFILE:
Introduction:
For the purpose of understanding the socio-economic profile, studies have been
undertaken with respect of population, literacy, income classification, occupational
structure, land use and other civic amenities like transport facilities, health care etc.
These studies have been undertaken both in
(i) Core Zone, and
(ii) Buffer Zone.
Core Zone:
The core zone consists of the leasehold area where mining & allied activities take place.
There is no village in the core zone. Buffer zone is the area covered by a circle of 10 km
radius around the core zone. It has 33 numbers of villages.
APPROACH METHODOLOGY
The study of socio-economic environment is a part of Environment Impact Assessment
(EIA). A family’s socioeconomic status is based on family income, parental education
level, parental education level, parental occupation and social status in the community.
The study includes demographic structure of the area (Core zone and Buffer zone 15
Kms. radius from mine lease area), housing, education, health and medical services,
occupation, water supply, sanitation, communication, transportation, prevailing disease
pattern as well as features of aesthetic significance such as temples, historical
monuments scenic beauty etc., as per 2001 census. This would help in visualizing and
predicting the likely impact depending upon the nature and magnitude of the project.
In order to validate the census report, house hold survey was made to collect the data of
250 house holds falling within core and buffer zone by floating questionnaire to residence
and local people of different villages (respondents selected on basis of socio-economic
condition), village head (Sarapanch / Police patil).
The occupational health status data is collected across the spectrum of male and
female population, for the different age groups. The data has been also collected from
the mine Hospital / local Doctor.
The basic amenities as per the census and the information from the residents of the
surveyed villages are described in the following sub-sections.
SOCIO- ECONOMICS DATA
The data collected for baseline study as per district census includes:
a) Number and names of Villages falling within the study area,
b) Social Profile, c) Economic, d) Infrastructure Facilities and
e) Occupational Health
The above information would help in predicting and evaluating likely impacts of the
socio-economic environment due to proposed mining activities.
Description of study area
The study area comprises of the following Districts and Tahesils of Maharashtra state:
District Tahsil
Code No. Name Code No. Name
14 Yavatmal
0014 Maregaon
0015 Zari-Jamini
0016 Wani
NUMBER & NAMES OF VILLAGES FALLING WITHIN THE STUDY AREA
There are no villages within the distance of 500m from the mine lease area and in the
core zone of the project.
There are 33 villages within the study area (Buffer zone).
SOCIAL PROFILE
Total population:
The data on total population with breakup including, male – female & SC - ST is given in
subsequent paragraphs and tables. There are 33 villages in the study with 6569
households. Total population of the area is 29,085, with 51.04 % male and 48.96% female
population. The percentage of scheduled caste population is 6.16, with 51.48 % male
and 48.52% female population. The scheduled tribe is 32.25, with 50.72 % male and
49.28% female population.
The religions which occurs in Yavatmal district are Buddhists, Christians, Hindus, Jains and
Muslims. Christians are more numerous in urban area.
The largest three scheduled castes present in the district are Mahar, Mang and Bhambi.
Ther other casts present are Kunbi, Mali, Banjara, Andh, Gond, Pardhans and Kolam.
Major languages which are spoken in Yavatmal district are Banjari, Gondi, Gujrathi, Hindi,
Kolami, Marathi, Sindhi, and Telugu. Marthi is the principal language and is the mother
tounge of the population.
The population of Gondi and Kolami speakers are higher and rural areas while the the
proportions of Gujrathi. Hindi.Sindi and Urdu speakers are higher in urban areas. Telugu
spearkers are fairly distributes over rural and urban areas.
Literacy level:
The literacy level of both male and female is given in table 2.2. The literacy rate is 60.92%.
Out of this35.54% is male and 25.38% is female. The illiteracy rate is 39.08%. with 39.67%
male and 60.33% female population.
Average House holds size:
The average house hold size is given in table in subsequent pages. It varies from 4.0 to 7.0
persons per family.
ECONOMIC
Occupational structure:
The percentage of total workers is 56.90 with male workers 52.95% and female workers
47.05%.
The percentage of non-workers is 43.10 with male workers 48.52% and female workers
51.48%.
i) Main workers are 80.43%, with male workers 57.30% and female workers 42.70%.
ii) Marginal workers are 19.57%, with male workers 35.04% and female workers 64.96%.
Land use Pattern:
The crops grown in the area are following types. These are of single types crops.
Kharif crops:
Jowar, cotton, groundnut and rice are the important kharif crops.
Rabi crops:
Wheat and gram are the important crops grown in the rabbi season. Sesame and linseed
(jawas) are also grown besides these.
Irrigated crops:-
Sugarcane, bananas, oranges, grapes, and betel-leaves are some important irrigated
crops.
The land use pattern of the study area (10 km radius) is given as below:
i) Forest land is 15.56%,
ii) Irrigated land is 2.58%,
iii) Un-irrigated land is 70.03%,
iv) Waste land is 4.78% and
v) Uncultivated land is 7.05%.
INFRASTRUCTURE FACILITIES
The houses are made of Bricks or earthen walls with cement or earthen flooring. The roofs
are tiled, sheets and of terrace roof. The grouping of the houses as per the wall material
shows the level of prosperity in the village.
Most of the houses are without toilet facilities of their own and they use the open land in
the village for the purpose. There are no public toilets.
The migration from the villages during the past is not much. The migration is to the nearest
town is for employment / study purpose or for labour work due to the lack of
employment in the village.
Drinking water (Tap/Well/Hand pumps) is available within the village or within the range
of 5Km distance. The quality of water is reasonably well. The difficulty arises in summer
season.
The villages are connected with Electric lines but power is intermittently supplied as in all
rural areas of the state.
The fuel for cooking purpose is L.P.G, kerosene/ coal or firewood.
Most of the villages are connected with tar / mud roads with state transport facilities.
Motor cycles, Cycles are used for traveling purposes. Bullock carts / Tractors are used for
carrying materials.
The house-to-house sample survey registers the data generally in tune with the census
figures. It also further updates the data particularly in respect of literacy, persons on jobs,
Toilet facilities, housing standards, medical facilities, item of source of cooking energy,
vehicles in villages etc.
OCCUPATIONAL HEALTH SURVEY
An occupational health risk is a leading cause of morbidity and mortality. The
occupational risk factors account for a number of morbid conditions, including back
pain, hearing loss, chronic obstructive lung disease, asthma, injuries, cancer, leukemia
etc.
OCCUPATIONAL HEALTH HAZARDS:
It is observed during the survey that, the habitation is away from the mining site. Therefore
there will be a minimum effect of mining activities on the locals.
Coal dust has been a serious hazard in mining, causing coal workers’ pneumoconiosis or
‘black lung’ and chronic obstructive pulmonary disease. The risk can be largely
controlled by dust suppression and respiratory protection.
The risk of tropical diseases such as malaria and dengue fever is substantial during the
rainy season. Eradication of mosquitoes and improved sanitation will controlled these
hazards effectively.
It is observed during the survey that malaria, dysentery / diarrhea and skin disorders are
common among all the sex / ages.
OCCURANCE OF HISTORICAL/ARCHAEOLOGICAL SITES
Wani is tahsil headquarter situated on the bank of Nirguda river. The famous temple of
Shir Ranganarh swami is in this town. Thousands of pilgrims visit the temple from Falguna
vadi to Chitra Sud 15. Wani is an important center of trade in cattle and bullocks. There
are coal mines near Wani. The place is well connected with important places in the
district by state roadways and also by Rail.
The project is having a Hospital at Township with Bed facilities. There is no Medical facility
available in the villages on regular basis except for intermittent visiting Doctors (Once a
week or so).
PUBLIC AWARENESS AND OPINION ABOUT THE PROJECT
Most of the respondents are aware about the project. 75% respondents have favorable
opinion, 20% have unfavorable opinion and 5% have not given any opinion.
The respondents were asked to opine about the project. They expected job
opportunities, improvement in educational, transport, medical and Increase in housing
facilities.
Unfavorable opinion can be attributed to increase in environmental pollution, crimes
and increase in the cost of commodities.
3.2 BASE LINE ENVIRONMENTAL QUALITY:
A preliminary air quality assessment plan has been completed with two objectives:
i) To evaluate the general air quality conditions in the study area during existing condition
and to provide basis for study of long-term trend of pollutant concentration when the
project will operate.
ii) To provide data for the subsequent development of air pollution prevention and
control programs during the life of the project.
Existing air quality assessment scheme has been split into following four phases:
- Inventory of emission sources;
- Micro meteorological data;
- Collection of air quality data;
- Analysis and interpretation of data.
Inventory of Emission Sources
a) Mining Activities
i) Handling of Coal;
ii) Coal Stock;
iii) Coal Transportation Roads;
b) Non-mining activities
i) Road Traffic;
ii) Other industries
iii) Urban activities.
3.2.1 SCOPE AND METHODOLOGY
Preamble
The scope of the study and the present report covers the detailed characterisation of the
existing environmental status in the study area for major environmental components viz.
micrometeorology, ambient air quality, water/waste water quality, noise level and soil
quality.
Micrometeorology
As a part of this study, micrometeorology and microclimatic parameters were recorded by
installing a meteorological station at core-zone. Data of wind velocity, wind direction,
ambient temperature, relative humidity and cloud cover were recorded at hourly intervals
in a day throughout the study period. Further rainfall also has been recorded and reported.
Wind velocity and wind direction were recorded using cup anemometer and wind vane
respectively. Ambient temperature was noted by wet and dry bulb thermometer.
Relative humidity was measured from hygrometer and a self-recording rain gauge was
used for rainfall data collection. Cloud cover data has been collected by visual
inspection.
Ambient air quality
To assess the ambient air quality status, monitoring stations were identified on the basis of
meteorology in the upwind and downwind direction as well as to represent the cross
sectional scenario of the project site. Based on the production activities, the parameters
chosen for assessment of air quality are Suspended Particulate Matter (SPM), Respirable
Particulate Matter (RPM), Sulphur dioxide (SO2) and Oxides of Nitrogen (NOx).
Calibrated Respirable Dust sampler (with an average flow of 1.2 - 1.4 m3/min.) was used for
monitoring of SPM & RPM and a tapping provided in the hopper of the same sampler was
utilised for sampling of SO2 and NOx with proper flow controller (1 LPM).
A field laboratory for the purpose of calibration of equipment and standardisation of
analytical procedures was also established. SPM & RPM were monitored on 24- hourly basis
and gaseous pollutants on 8 hourly basis for 2 days in a week for 12 weeks as per the
guidelines of CPCB / MOEF. Collected samples are analysed on the day of sample
collection with the following procedure.
SPM & RPM
Ambient air laden with suspended particulates enters the Respirable Dust Sampler (RDS)
through the inlet pipe of sampler by means of high flow rate blower (1.2 to 1.4 m3/min). As
the air passes through the cyclone, coarse, non-respirable dust (size > 10 microns) is
separated from the air stream by centrifugal forces acting on the solid particles. These
separated particles fall through the cyclone’s conical hopper and collect in the sampling
bottle placed at bottom. The fine dust forming the respirable fraction (size <10 microns) of
the Total Suspended Particulates passes through the cyclone and is carried by the air
stream to the Glass Microfibre Filter Paper. The Respirable Particulate Matter (RPM) is
retained by the filter and the carrier air exhausted from the system through the blower. The
mass concentration (µg/m3) of Suspended Particulate Matter (non-respirable dust and
respirable dust) and Respirable Particulate Matter in the ambient air is computed by
measuring the mass of collected particulates and the volume of air sampled.
NO2 (Jacob & Hocheiser modified method)
Ambient air is bubbled at the rate of 0.5-1.0 l/min in an Impinger containing a solution of
Sodium Hydroxide and Sodium Arsenate. The resultant Nitrite Ion is reacted with
Phosphoric acid, Sulphanilamide and N-ethylene di-amine di-hydro chloride to form a
coloured complex. The absorbance is measured in a Spectrophotometer at a wavelength
of 540 nm. The concentration of NO2 is then calculated by using standard graph.
SO2 (Modified West & Gaeke Spectrophotometer method)
Ambient air is bubbled at the rate of 0.5 -1.0 l/min in an Impinger containing a scrubbing
solution of Sodium-Tetra Chloro Mercurate. The resultant compex is reacted with P-
Rosaniline and Formaldehyde to form coloured Para-Rosaniline methyl sulphuric acid.
The absorbance of the solution is measured in a Spectrophotometer at a wavelength of
560nm. The SO2 is then calculated from standard graph.
Water quality
Water samples were collected and analyzed as per procedures outlined in IS-2488/ IS-
3025 / AWWA / APHA. Sterilized bottles were used for collection of water sample for
bacteriological analysis, stored in icebox and transported to the laboratory for the
analysis. Parameters like pH, Temperature, Dissolved Oxygen, Residual Chlorine,
Conductivity, Free Ammonia, Total Hardness, Calcium Hardness and Magnesium
Hardness were analyzed in the field while collecting the samples. MPN index of Coliforms
are determined in the laboratory as per standard methods.
Noise levels
Ambient noise level measurements in four co-ordinal directions were carried out using
CYGNET with windscreen during daytime as well as nighttime.
Noise measurements were made at 1.5 m above ground and about 3m away from walls,
buildings or other sound reflecting sources. The readings were taken at an interval of one
minute for 30 minutes and mean Leq. values has been reported. Ambient noise levels are
compared with Air quality standards in respect of noise for residential area.
Soil quality
To assess the baseline soil quality, soil samples were collected from identified locations in
core & buffer zones using augers at depths 30, 60 and 100 cms. The samples were analyzed
for chemical parameters like pH, EC, N, P, K and engineering parameters like textural class,
bulk density, liquid limit, field capacity, wilting coefficient and available water storage
capacity.
3.2.2 MICROMETEOROLOGICAL STATUS
Rationale behind sampling
Meteorological parameters are important factors in the study of air pollution. The
transport and diffusion of the pollutants in the atmosphere are governed by
meteorological factors. Factors like wind velocity, wind direction and atmospheric-
stability are known as primary / basic meteorological parameters since the dispersion
and diffusion of pollutants depend mainly on these factors. Factors like ambient
temperature, humidity, rainfall, atmospheric pressure, etc., are known as secondary
meteorological parameters as these factors control the dispersion of the pollutants
indirectly by affecting the primary factors. Thus, to assess the air pollution impact it
becomes essential to collect the above-mentioned meteorological parameters in the
project area.
Micrometeorological and microclimatic parameters were recorded by installing a
meteorology station in core-zone as it represents the prevailing micrometeorological
aspects of the study area. During the study period, hourly reading of wind velocity, wind
direction, temperature, humidity, cloud cover etc., were recorded and reported. Further
daily rainfall has been recorded and reported.
Data presentation & analysis
The micrometeorological data thus collected has been processed and analyzed as per
standard procedures.
Data Presentation
The seasonal wind distribution is given in the Table below along with the abstract of
micrometeorology data.
Data Analysis
Meteorological data collected during the study reveal the following status:
Meteorology status
Meteorology station : Corezone
Climatic conditions Winter season
(01st Dec.09 – 28th Feb.10)
Predominant wind direction (from) NE / ENE
Calm condition (%) 25.83
Predominant prevailing wind range
(Kmph) 5 -11
Wind speed (m/sec)
i) Minimum 0.4
ii) Maximum 14.5
Temperature (°C)
i) Minimum 11.0
ii) Maximum 25.5
Relative humidity (%) (Mean) 63.5
Total rainfall (cm) -
Seasonal wind distribution data.
Season : Winter 2009-10
Location : Corezone
Wind
Direction
Wind Velocity, Kmph (% Duration)
< 1.0 1 – 5 5 – 11 11 – 19
N
25.83
1.67 1.20 -
NNE 4.21 1.99 0.56
NE 13.29 4.82 0.14
ENE 11.30 4.58 0.09
E 2.92 1.53 0.05
ESE 3.43 1.62 0.05
SE 3.19 1.67 -
SSE 2.22 0.37 -
S 0.51 0.28 -
SSW 0.88 0.42 -
SW 0.88 0.37 -
WSW 1.02 0.19 -
W 0.42 0.00 -
WNW 1.06 0.32 -
NW 3.75 1.67 -
NNW 0.88 0.56 0.09
Season 25.83 51.62 21.58 0.97
3.3 AMBIENT AIR QUALITY STATUS
Preamble
The principle objective of the ambient air quality monitoring is to assess the existing levels of
air pollutants as well as the regional background concentration in and around the project
area. Air pollution forms an important and critical factor to study the environmental issues in
the mining areas. Air quality has to be frequently monitored to know the extent of pollution
due to mining and allied activities. The ambient air quality monitoring was carried out at six
stations.
The monitoring stations were identified on the basis of meteorology in the upwind and
downwind direction as well as to represent the cross sectional scenario of the project site.
The monitoring network was designed based on the available meteorological and
climatologically norms of predominant wind direction and wind speed of the study region.
The parameters selected for analyzing the air quality status are Suspended Particulate
Matter (SPM), Respirable Particulate Matter (RPM), Sulphur dioxide (SO2) and Nitrogen
oxides (NOx). As per the existing norms, air quality monitoring was carried out on 24 hourly
basis for SPM & RPM and 8 hourly basis for SO2 and NOx samples for two days in a week for
twelve weeks in the season.
Details of Ambient air quality-monitoring stations
(Location & Bearing)
SI.
No. Location Name Location Code
Direction
(from Site)
Distance
(Km)
1. Core-zone A1 - -
2. Ghonsa village A2 NW 0.8
3. Phulora A3 NE 1.6
4. Salgaon A4 SE 1.9
5. Kalampad village A5 SW 2.4
6. Dahegaon village A6 WNW 1.6
Rationale behind sampling
(i) Core zone (A1): The location is selected to assess the air quality due to active mining
and to know the increase in pollution levels due to mining operation through post project
monitoring.
(ii) Ghonsa village (A2): This location is situated at 0.8 km distance from the proposed
project site towards NW direction. The location is selected to assess pollution level in the
nearby mining area.
(iii) Phulora village (A3): This location is situated about 1.6 km distance from site towards NE
direction and it was selected for air quality monitoring to assess baseline status in the
upwind direction of the study area.
(iv) Salgaon village (A4): This location is situated about 1.9 km distance from site towards SE
direction and it was selected for air quality monitoring to assess baseline status in the
nearby mining area.
(v) Kalampad village (A5): This location is situated at 2.4 km distance from the mine
towards SW direction. The data will help to know the extent of pollution, if any, due to
mining operations in nearby area and to assess baseline status in the downwind direction.
(vi) Dahegaon village (A6): This location is situated at 1.6 km distance from the mine
towards WNW direction. The data will help to know the extent of pollution, if any, due to
mining operations in nearby area and to assess baseline status in the downwind direction.
Data Presentation
The ambient air quality data are given in the paragraphs & tables below: -
Data Analysis
Core zone
SPM and RPM values are ranging from 165 - 246 g/m3 and 68 g/m3 to 125 g/m3
respectively. SO2 and NOx values are varying between 7.2 to 11.6 g/m3 and 8.9 to 15.2
g/m3 respectively. All the values are found to be well within the Standards for Coalmines
stipulated by Ministry of Environment & Forests (MoEF).
Buffer zone
SPM and RPM values are ranging from 108 g/m3 to 179 g/m3 and 32 g/m3 to 87 g/m3
respectively. SO2 and NOx values are varying between 5.4 – 10.6 and 6.9 – 13.0 g/m3
respectively. All RPM, SO2and NOx values are well within the CPCB norms.
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Corezone
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs 14 - 22 Hrs 22 - 06 Hrs
SO2 NOx SO2 NOx SO2 NOx
I 03/04.12.2009 204 103 8.0 10.3 9.2 11.7 7.6 9.8
04/05.12.2009 196 98 7.7 9.8 8.8 11.2 7.2 9.5
II 09/10.12.2009 218 109 8.3 10.6 9.6 12.3 7.9 10.2
10/11.12.2009 233 117 8.6 10.8 9.8 12.5 8.0 10.3
III 14/15.12.2009 228 115 8.4 10.5 9.5 12.2 7.8 10.0
15/16.12.2009 214 108 8.1 10.2 9.3 11.8 7.5 9.7
IV 24/25.12.2009 246 125 9.0 11.5 10.2 13.6 8.4 10.8
25/26.12.2009 220 112 8.8 11.2 10.0 13.1 8.2 10.5
V 31/01.01.2010 182 82 9.9 10.6 9.8 13.1 9.2 10.8
01/02.01.2010 165 76 10.8 9.6 11.2 13.1 9.4 11.3
VI 05/06.01.2010 178 80 11.3 9.9 11.6 12.8 10.3 11.9
06/07.01.2010 180 80 10.8 10.1 11.3 13.8 10.2 10.8
VII 11/12.01.2010 192 88 10.6 11.8 10.8 14.3 9.5 10.6
12/13.01.2010 174 78 9.5 10.8 10.4 12.9 8.9 10.9
VIII 17/18.01.2010 185 70 10.6 11.4 10.8 14.2 9.1 10.9
18/19.01.2010 180 72 9.6 11.9 10.3 14 8.4 10.4
IX 27/28.01.2010 172 78 9.5 12.3 10.1 13.9 8.6 11.1
28/29.01.2010 170 68 10.1 12.8 10.5 14.1 9.1 10.8
X 02/03.02.2010 214 74 10.2 9.6 11.5 14.8 9.6 10.4
03/04.02.2010 212 72 10.6 8.9 10.8 13.1 9 11.5
XI 10/11.02.2010 186 68 9.6 10.1 10.4 13.9 8.4 10.8
11/12.02.2010 205 75 9.5 10.6 10.4 15.2 8.4 11.8
XII 22/23.02.2010 186 68 10.1 10.9 10.6 12.8 9.5 11.9
23/24.02.2010 202 80 10.4 10.8 10.9 14.8 9.2 11.3
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Ghonsa village
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs 14 - 22 Hrs 22 - 06 Hrs
SO2 NOx SO2 NOx SO
2 NOx
I 03/04.12.2009 125 63 7.6 9.6 8.7 11.0 7.4 9.2
04/05.12.2009 110 58 7.3 9.2 8.5 10.6 7.1 8.8
II 09/10.12.2009 108 55 8.0 10.2 8.9 11.8 7.8 9.7
10/11.12.2009 132 67 8.2 10.4 9.0 12.0 8.0 9.9
III 14/15.12.2009 140 72 8.3 10.2 9.2 11.7 8.1 9.6
15/16.12.2009 126 64 7.9 9.8 8.8 11.3 7.6 9.3
IV 24/25.12.2009 134 69 8.7 11.2 9.5 12.5 8.3 10.8
25/26.12.2009 147 75 8.4 10.9 9.3 12.0 8.2 10.2
V 31/01.01.2010 124 36 6.8 9.2 7.1 9.6 5.7 6.9
01/02.01.2010 135 42 6.4 8.9 6.8 9.1 5.6 7.1
VI 05/06.01.2010 122 35 6.1 9.1 6.6 10.2 5.4 7.6
06/07.01.2010 138 42 6.4 9.4 6.8 10.6 5.6 7.6
VII 11/12.01.2010 110 32 6.7 8.9 6.8 11.1 6.1 7.4
12/13.01.2010 124 37 6.5 8.4 7.1 9.4 5.9 6.9
VIII 17/18.01.2010 136 41 6.3 8.6 6.8 8.9 5.7 7.2
18/19.01.2010 144 45 6.9 9.6 7.6 9.5 6.1 7.5
IX 27/28.01.2010 134 40 7.4 10.3 7.9 10.6 6.1 8.1
28/29.01.2010 117 34 7.2 9.6 7.5 9.9 5.9 7.5
X 02/03.02.2010 146 46 7.0 9.4 7.4 10.2 5.8 7.1
03/04.02.2010 125 37 6.4 8.8 6.9 9.5 5.7 7.6
XI 10/11.02.2010 152 48 6.3 9.6 6.6 9.9 5.4 7.5
11/12.02.2010 134 41 6.4 9.6 6.8 10.1 5.6 7.5
XII 22/23.02.2010 126 38 6.7 10.6 7.1 10.8 6 8.9
23/24.02.2010 118 35 7.3 11.6 7.6 11.9 6.3 9.5
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Phulora village
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs 14 - 22 Hrs 22 - 06
Hrs
SO2 NOx SO2 NOx SO2 NOx
I 03/04.12.2009 136 70 7.8 9.8 8.5 11.4 7.5 9.5
04/05.12.2009 124 64 7.5 9.4 8.8 10.9 7.2 9.2
II 09/10.12.2009 115 58 8.2 10.4 9.3 12.2 7.8 10.2
10/11.12.2009 147 74 8.4 10.7 9.5 12.5 8.0 10.4
III 14/15.12.2009 154 78 8.5 10.5 9.7 12.0 8.2 10.3
15/16.12.2009 138 72 8.0 9.9 9.2 11.7 7.6 9.6
IV 24/25.12.2009 143 73 8.8 11.4 10.1 12.8 8.4 11.2
25/26.12.2009 159 80 8.5 11.1 9.8 12.6 8.2 10.8
V 31/01.01.2010 129 41 7.9 10.3 8.2 10.7 6.8 8.0
01/02.01.2010 140 47 7.5 10 7.9 10.2 6.7 8.2
VI 05/06.01.2010 127 40 7.2 10.2 7.7 11.3 6.5 8.7
06/07.01.2010 143 47 7.5 10.5 7.9 11.7 6.7 8.7
VII 11/12.01.2010 115 37 7.8 10 7.9 12.2 7.2 8.5
12/13.01.2010 129 42 7.6 9.5 8.2 10.5 7 8.0
VIII 17/18.01.2010 141 46 7.4 9.7 7.9 10 6.8 8.3
18/19.01.2010 149 50 8.0 10.7 8.7 10.6 7.2 8.6
IX 27/28.01.2010 139 45 8.5 11.4 9 11.7 7.2 9.2
28/29.01.2010 122 39 8.3 10.7 8.6 11 7 8.6
X 02/03.02.2010 151 51 8.1 10.5 8.5 11.3 6.9 8.2
03/04.02.2010 130 42 7.5 9.9 8 10.6 6.8 8.7
XI 10/11.02.2010 157 53 7.4 10.7 7.7 11 6.5 8.6
11/12.02.2010 139 46 7.5 10.7 7.9 11.2 6.7 8.6
XII 22/23.02.2010 131 43 7.8 11.7 8.2 11.9 7.1 10.0
23/24.02.2010 123 40 8.4 12.7 8.7 13 7.4 10.6
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Salgaon village
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs 14 - 22 Hrs 22 - 06
Hrs
SO2 NOx SO2 NOx SO2 NOx
I 03/04.12.2009 160 77 6.9 8.9 7.9 10.7 6.8 8.8
04/05.12.2009 154 70 6.7 8.6 8.2 10.3 6.7 8.5
II 09/10.12.2009 172 75 7.4 9.6 8.7 11.6 7.4 9.4
10/11.12.2009 164 86 7.6 9.9 8.8 11.9 7.6 9.7
III 14/15.12.2009 174 85 7.8 9.7 9.1 11.4 7.8 9.6
15/16.12.2009 164 87 7.3 9 8.6 11.1 7.3 8.8
IV 24/25.12.2009 160 76 7.9 10.6 9.3 12.2 7.9 10.5
25/26.12.2009 166 81 7.7 10.3 9.1 12 7.7 10.1
V 31/01.01.2010 164 75 7.3 9.7 7.8 10.3 6.4 7.5
01/02.01.2010 150 71 6.9 9.4 7.5 9.8 6.3 7.7
VI 05/06.01.2010 162 76 6.6 9.6 7.3 10.9 6.1 8.2
06/07.01.2010 156 84 6.9 9.9 7.5 11.3 6.3 8.2
VII 11/12.01.2010 168 79 7.2 9.4 7.5 11.8 6.8 8.0
12/13.01.2010 172 86 7.0 8.9 7.8 10.1 6.6 7.5
VIII 17/18.01.2010 164 82 6.8 9.1 7.5 9.6 6.4 7.8
18/19.01.2010 166 79 7.4 10.1 8.3 10.2 6.8 8.1
IX 27/28.01.2010 162 78 7.9 10.8 8.6 11.3 6.8 8.7
28/29.01.2010 155 74 7.7 10.1 8.2 10.6 6.6 8.1
X 02/03.02.2010 166 77 7.5 9.9 8.1 10.9 6.5 7.7
03/04.02.2010 164 78 6.9 9.3 7.6 10.2 6.4 8.2
XI 10/11.02.2010 156 71 6.8 10.1 7.3 10.6 6.1 8.1
11/12.02.2010 167 76 6.9 10.1 7.5 10.8 6.3 8.1
XII 22/23.02.2010 164 79 7.2 11.1 7.8 11.5 6.7 9.5
23/24.02.2010 166 76 7.8 12.1 8.3 12.6 7.0 10.1
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Kalmpad village
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs 14 - 22 Hrs 22 - 06 Hrs
SO2 NOx SO2 NOx SO2 NOx
I 03/04.12.2009 164 61 8.2 9.6 9.1 10.5 7.8 8.4
04/05.12.2009 174 63 8.0 9.2 9.4 10.6 7.5 8.1
II 09/10.12.2009 179 64 8.5 10.1 9.9 11.0 8.2 8.8
10/11.12.2009 169 62 8.8 10.4 10.1 11.4 8.4 9.0
III 14/15.12.2009 154 55 8.9 10.2 10.3 11.6 8.5 9.1
15/16.12.2009 144 55 8.2 9.6 9.9 10.8 8.1 8.7
IV 24/25.12.2009 139 52 9.2 11.0 10.6 11.2 8.9 9.5
25/26.12.2009 149 54 8.9 10.7 10.4 11.2 8.6 9.2
V 31/01.01.2010 159 58 7.5 9.1 8.2 9.5 6.6 8.3
01/02.01.2010 124 46 7.1 8.8 7.9 9.0 6.5 8.5
VI 05/06.01.2010 129 45 6.8 9 7.7 10.1 6.3 9.0
06/07.01.2010 142 48 7.1 9.3 7.9 10.5 6.5 9.0
VII 11/12.01.2010 148 52 7.4 8.8 7.9 11.0 7 8.8
12/13.01.2010 133 47 7.2 8.3 8.2 9.3 6.8 8.3
VIII 17/18.01.2010 163 68 7.0 8.5 7.9 8.8 6.6 8.6
18/19.01.2010 158 54 7.6 9.5 8.7 9.4 7 8.9
IX 27/28.01.2010 177 62 8.1 10.2 9 10.5 7 9.5
28/29.01.2010 165 60 7.9 9.5 8.6 9.8 6.8 8.9
X 02/03.02.2010 152 54 7.7 9.3 8.5 10.1 6.7 8.5
03/04.02.2010 141 52 7.1 8.7 8 9.4 6.6 9.0
XI 10/11.02.2010 126 48 7.0 9.5 7.7 9.8 6.3 8.9
11/12.02.2010 130 52 7.1 9.5 7.9 10.0 6.5 8.9
XII 22/23.02.2010 141 56 7.4 10.5 8.2 10.7 6.9 10.3
23/24.02.2010 127 48 8.0 11.5 8.7 11.8 7.2 10.9
AIR QUALITY DATA OF SPM, RPM & CO
Project : Ghonsa OCP
Season
: Winter`2009-10
Location : Dahegaon
Unit: µg/m
3
WEEK DATE SPM
(24 Hrly) RPM
(24 Hrly)
06 - 14 Hrs
14 - 22 Hrs 22 - 06 Hrs
SO
2 NOx SO2 NOx SO2 NOx
I 03/04.12.2009 145 70 8.3 10.8 10.0 12.1 7.2 8.4
04/05.12.2009 129 67 8.6 11.3 9.9 11.9 7.4 8.9
II 09/10.12.2009 125 65 8.6 11.1 10.2 12.0 6.9 8.4
10/11.12.2009 122 63 8.7 11.0 10.6 11.6 6.6 8.5
III 14/15.12.2009 137 71 8.0 10.6 9.8 11.2 6.8 8.5
15/16.12.2009 131 68 7.7 9.9 10.1 10.6 7.0 8.3
IV 24/25.12.2009 139 72 7.3 10.2 9.1 10.4 7.1 8.7
25/26.12.2009 142 74 7.1 10.0 8.6 9.8 6.6 8.5
V 31/01.01.2010 153 55 6.8 9.3 8.2 9.7 6.8 8.0
01/02.01.2010 162 59 8.0 10.3 8.7 10.1 6.5 7.7
VI 05/06.01.2010 159 58 7.7 9.6 8.2 8.9 6.3 7.5
06/07.01.2010 155 54 7.9 10.3 7.7 8.4 6.1 7.9
VII 11/12.01.2010 163 61 7.5 9.4 7.1 7.8 6.1 7.8
12/13.01.2010 141 47 7.1 8.9 7.4 8.4 6.4 8.1
VIII 17/18.01.2010 151 56 6.5 8.1 7.5 8.3 6.5 7.5
18/19.01.2010 145 51 6.7 8.0 7.8 8.8 6.1 7.0
IX 27/28.01.2010 169 60 7.7 8.6 8.1 9.2 7.5 9.7
28/29.01.2010 175 59 8.0 8.9 7.9 9.5 7.3 9.3
X 02/03.02.2010 167 57 8.6 9.5 8.5 11.5 8.1 9.4
03/04.02.2010 163 55 8.3 9.1 8.2 10.6 7.3 9.5
XI 10/11.02.2010 157 53 8.1 8.7 8.4 11 7.1 9.1
11/12.02.2010 155 51 7.7 8.5 7.7 9.3 6.9 8.7
XII 22/23.02.2010 159 54 7.3 8.1 7.4 8.9 6.4 8.9
23/24.02.2010 153 46 7.4 8.2 7.5 9.3 6.7 8.5
Existing Ambient Air Quality :
i) Air Quality: The ambient air quality of existing Ghonsa OC mine is being monitored as
per Env. Protection Amendment Rule, 2000 at following locations.
1.
2.
Ghonsa village
Kumbarkhani Guest house
/Colony
-
--
WNGOA-1
WNGOA-2
The methodology of ambient air quality monitoring is as given below: -
SPM:
The twenty-four hourly air samples are collected with high volume respirable dust
sampler. Ambient air laden with suspended particulates enters the respirable dust
sampler through the inlet pipe of sampler by means of a high flow rate blower (1.1 to 1.5
m3/min.). As the air passes through the cyclone, coarse, non-respirable dust (size >10
microns) is separated from the air stream by centrifugal forces acting on the solid
particles. These separated particles fall through the cyclone's conical hopper and
collect in the sampling bottle place at bottom. The fine dust forming the respirable
fraction (size<10 microns) of the total suspended particulates passes through the cyclone
and is carried by the air stream to the Glass Micro Fibre Filter Paper. The respirable dust
(RPM) is retained by the filter and the carrier air exhausted from the system through the
blower. The mass concentration (micro gm/m3) of suspended particulate matter (non-
respirable dust and respirable dust) and respirable particulate matter in the ambient air is
computed by measuring the mass of collected particulates and the volume of air
sampled.
NOx :
Determination of oxides of Nitrogen is based on the procedure of "Jacobs and
Hochheiser method". In this method the air sample is collected 24 hourly in the field and
analysed in the laboratory using spectronic 20 D+ Spectrophotometer. Nitrogen oxides
as Nitrogen di-oxide are collected by bubbling air through a Sodium hydroxide solution
to form a stable solution of Sodium nitrite. The nitrite ion produced during sampling is
determined colorimetrically (with the help of Spectrophotometer, measuring absorbence
at 540 nm) by reacting the exposed absorbing reagent with Phosphoric acid,
Sulphanilamide and N (1 – naphthyl) ethylenediamine dihydrochloride. The interference
of Sulphur di-oxide is eliminated by converting it to Sulphuric acid with Hydrogen
peroxide before anlysis. Value of Nox in air sample, below 6 micro gm/m3 has been
reported as BDL.
SO2 :
Determination of SO2 is based on the procedure of West and Gaeke method. Sulphur di-
oxide from the air stream is absorbed in a Sodium tetrachloromercurate solution to form
a stable solution of Dichlorosulphitomercurate. The amount of Sulphur dioxide is then
estimated by the colour produced when P-Rosaniline hydrochloride is added to the
solution. The colour is estimated by a reading of absorbance at 560 mm in the
Spectrophotometer. Value of SO2 in air sample, below 6 micro gm/m3 has been
reported as BDL.
The Ambient Air Quality is being monitored at the above locations as per Environment
Protection Amendment Rule – 2000. The recorded values during quarter ending June
2010 to June 2011 have been given below and all parameters have been found to be
well below the permissible limit.
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2011 06.04.11 - 07.04.11 185 36 < 6 < 6 MAY 2011 22.05.11 - 23.05.11 185 81 < 6 < 6 JUN. 2011 07.06.11 - 08.06.11 96 45 < 6 < 6 JUN. 2011 22.06.11 - 23.06.11 69 32 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2011 06.04.11 - 07.04.11 138 38 < 6 < 6 APR. 2011 22.04.11 - 23.04.11 156 35 < 6 < 6 MAY 2011 08.05.11 - 09.05.11 173 65 < 6 < 6 MAY 2011 22.05.11 - 23.05.11 141 36 < 6 < 6 JUN. 2011 07.06.11 - 08.06.11 140 40 < 6 < 6 JUN. 2011 22.06.11 - 23.06.11 44 20 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2011 19.01.11 - 20.01.11 64 32 < 6 < 6 FEB. 2011 20.02.11 - 21.02.11 85 38 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house : WNGOA-2 ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2011 20.01.11 - 21.01.11 171 84 < 6 < 6 FEB. 2011 05.02.11 - 06.02.11 190 85 < 6 < 6 FEB. 2011 20.02.11 - 21.02.11 80 21 < 6 < 6 MAR. 2011 05.03.11 - 06.03.11 189 64 < 6 < 6 MAR. 2011 26.03.11 - 27.03.11 124 43 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2010
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2010 22.10.10 - 23.10.10 73 33 < 6 < 6 NOV. 2010 20.11.10 - 21.11.10 37 24 < 6 < 6 DEC. 2010 25.12.10 - 26.12.10 60 28 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2010 22.10.10 - 23.10.10 40 15 < 6 < 6 NOV. 2010 20.11.10 - 21.11.10 35 12 < 6 < 6 DEC. 2010 25.12.10 - 26.12.10 164 60 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2010
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2010 05.04.10 - 06.04.10 182 37 < 6 < 6 APR. 2010 22.04.10 - 23.04.10 90 38 < 6 < 6 MAY 2010 07.05.10 - 08.05.10 155 59 < 6 < 6 MAY 2010 22.05.10 - 23.05.10 187 81 < 6 < 6 JUN. 2010 07.06.10 - 08.06.10 115 53 < 6 < 6 JUN. 2010 22.06.10 - 23.06.10 155 60 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2010 05.04.10 - 06.04.10 96 42 < 6 < 6 APR. 2010 22.04.10 - 23.04.10 179 83 < 6 < 6 MAY 2010 08.05.10 - 09.05.10 177 81 < 6 < 6 JUN. 2010 07.06.10 - 08.06.10 152 69 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
From the above paragraphs it can be concluded that the contribution of mining
activities at the site under consideration is insignificant so far as ambient Air Quality is
concerned which is further corroborated by the fact that the baseline scenario in and
around the mine site is also quite satisfactory w.r.t. the permissible limits.
3.4 BASE LINE WATER QUALITY STATUS
Rationale behind sampling
Any adverse impact or pollution consequence of water will have serious effect on the
environment. Hence, it becomes important to assess the water quality periodically in the
mining area. Thus, to assess the water quality, six locations are identified and samples (6
Nos.) were collected and analysed for physico-chemical and heavy metal parameters.
Bacterial examination was also carried out to find out the Coliform contamination (if any)
at water sources. The water quality assessment has been made from the following
monitoring stations).
Mine discharge during Dec.09 - W1
Mine discharge during Jan.10 - W2
Handpump, Ghonsa Basti - W3
Handpump, Phulora village - W4
Vidharbha river U/s. - W5
Vidharbha river D/s - W6
Data presentation & analysis
The detailed water quality data generated are given below
Waste water quality status
Source pH
Suspended
Solids (mg/l) BOD (mg/l) COD (mg/l)
Min. Max. Min. Max. Min Max. Min. Max.
Mine
discharge
6.84 6.94 3 8 - - 21 24
GSR 422E
Norms 5.5-9.0 100 30 250
Water quality status
Source pH
Turbidity
(NTU)
TDS
(mg/l)
Total
Hardness
(mg/l)
Iron
(mg/l)
Chloride
(mg/l)
Sulphate
(mg/l)
Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. Min. Max.
Ground
Water 6.65 7.02 6 7 624 908 245 538 0.06 0.08 128 166 32 51
IS
105000
Norms
6.5-8.5 10 500-2000 300-600 0.3-1.0 250-1000 200-1000
Surface water quality status
Source pH
Colour
(Hazen
Units )
TDS
(mg/l)
Iron
(mg/l)
Chloride
(mg/l)
Sulphate
(mg/l) Fluoride
(mg/l)
Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. Min. Max.
River 7.11 7.55 30 32 628 658 0.10 0.12 148 164 40 42 0.10 –
0.12
IS:2296-
1982 6.5-8.5 300 1500 50 600 400 1.5
Summary
At all locations, Oil and grease, phenolic compounds, cyanides, sulphides and insecticides
are found to be absent and all heavy metal values except Iron and Zinc are found to be
below the detectable limit. In general, the water quality at all six locations are found to be
well within the prescribed norms of GSR: 422E, IS: 10500 - 1991 and IS: 2296 - 1982.
WATER QUALITY DATA Location : Mine discharge (W1) Date of sampling : 29.12.2009
S. No
Parameter Unit Result
General Standards for discharge of Effluents
into Inland Surface water GSR 422(E)
1. Colour & Odour Pt-Co 8 & Odourless -
2. Total Suspended Solids Mg/l 3 100
3. Particle size of suspended solids Shall pass
850 micron ISI sieve
100% are passing through 850 micron
ISI sieve
Shall pass 850 micron ISI sieve
4. Total Dissolved solids mg/l 682 -
5. pH - 6.94 5.5-9.0
6. Temperature oC 28.0 5°C above water
temperature
7. Oil & Grease mg/l Nil 10
8. Total residual chlorine mg/l Nil 1.0
9. Ammonical Nitrogen (as N) mg/l 0.10 50
10. Kjeldahl nitrogen mg/l 0.20 100
11. Free ammonia (as NH3) mg/l Nil 5.0
12. BOD - 3 Days at 27oC mg/l - 30
13. COD mg/l 21 250
14. Arsenic (as As) mg/l <0.01 0.2
15. Mercury (as Hg) mg/l <0.001 0.01
16. Lead (as Pb) mg/l <0.01 0.01
17. Cadmium (as Cd) mg/l <0.01 2
18. Hexavalent Chromium (as Cr6+) mg/l <0.001 0.10
19. Total Chromium mg/l <0.001 2.0
20. Copper (as Cu) mg/l <0.001 3
21. Zinc (as Zn) mg/l <0.01 5
22. Selenium (as Se) mg/l <0.01 0.05
23. Nickel (as Ni) mg/l <0.01 3
24. Boron (as B) mg/l <0.01 -
25. Percent Sodium mg/l 18.97 -
26. Residual Sodium Carbonate mg/l Nil -
27. Cyanides (as CN) mg/l Nil 0.2
28. Chloride (as Cl) mg/l 65 -
29. Fluorides (as F) mg/l 0.12 2
30. Dissolved Phosphates (as PO4) mg/l 0.07 5.0
31. Sulphates (as SO4) mg/l 10 -
32. Sulphides (as S) mg/l Nil 2
33. Phenols (as C6H5OH) mg/l Nil 1.0
34. Bio-assay test
90%survival of fish after 96 hours in
100% effluent
100%survival of fish after 96 hours in
100% effluent
90%survival of fish after 96 hours in 100%
effluent
35. Manganese (as mn) mg/l Nil 2.0
36. Iron (as Fe +2) mg/l 0.03 3.0
37. Vanadium (as V) mg/l Nil 0.2
38. Nitrate Nitrogen mg/l 0.28 10
WATER QUALITY DATA Location : Mine discharge (W2) Date of sampling : 23.01.2010
S. No
Parameter Unit Result
General Standards for discharge of Effluents
into Inland Surface water GSR 422(E)
1. Colour & Odour Pt-Co 10 & Odourless -
2. Total Suspended Solids Mg/l 8 100
3. Particle size of suspended solids Shall pass
850 micron ISI sieve
100% are passing through 850 micron
ISI sieve
Shall pass 850 micron ISI sieve
4. Total Dissolved solids mg/l 710 -
5. pH - 6.84 5.5-9.0
6. Temperature oC 28.5 5°C above water
temperature
7. Oil & Grease mg/l Nil 10
8. Total residual chlorine mg/l Nil 1.0
9. Ammonical Nitrogen (as N) mg/l 0.18 50
10. Kjeldahl nitrogen mg/l 0.36 100
11. Free ammonia (as NH3) mg/l Nil 5.0
12. BOD - 3 Days at 27oC mg/l - 30
13. COD mg/l 24 250
14. Arsenic (as As) mg/l <0.01 0.2
15. Mercury (as Hg) mg/l <0.001 0.01
16. Lead (as Pb) mg/l <0.01 0.01
17. Cadmium (as Cd) mg/l <0.01 2
18. Hexavalent Chromium (as Cr6+) mg/l <0.001 0.10
19. Total Chromium mg/l <0.001 2.0
20. Copper (as Cu) mg/l <0.001 3
21. Zinc (as Zn) mg/l <0.01 5
22. Selenium (as Se) mg/l <0.01 0.05
23. Nickel (as Ni) mg/l <0.01 3
24. Boron (as B) mg/l <0.01 -
25. Percent Sodium mg/l 21.26 -
26. Residual Sodium Carbonate mg/l Nil -
27. Cyanides (as CN) mg/l Nil 0.2
28. Chloride (as Cl) mg/l 74 -
29. Fluorides (as F) mg/l 0.11 2
30. Dissolved Phosphates (as PO4) mg/l 0.08 5.0
31. Sulphates (as SO4) mg/l 14 -
32. Sulphides (as S) mg/l Nil 2
33. Phenols (as C6H5OH) mg/l Nil 1.0
34. Bio-assay test
90%survival of fish after 96 hours in
100% effluent
100%survival of fish after 96 hours in
100% effluent
90%survival of fish after 96 hours in 100%
effluent
35. Manganese (as mn) mg/l Nil 2.0
36. Iron (as Fe +2) mg/l 0.04 3.0
37. Vanadium (as V) mg/l Nil 0.2
38. Nitrate Nitrogen mg/l 0.46 10
WATER QUALITY DATA
Location : Handpump, Ghonsa Basti (W3) Date of sampling : 29.12.2009
Sl. No.
Parameter Unit Result IS: 10500-1991
Norms
1 pH - 6.65 6.5 – 8.5
2 Colour Hazen Units <5 10
3 Temperature oC 28.5 -
4 Turbidity NTU 7 10
5 Total suspended solids mg/l Nil -
6 Total dissolved solids mg/l 908 500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 4.4 -
9 BOD - 3 days at 27oC mg/l - -
10 COD mg/l 18 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil 0.2
13 Chloride (as CI) mg/l 166 250
14 Flouride (as F) mg/l Nil 1.0
15 Sulphate (as SO4) mg/l 51 200
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l Nil 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.001
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 0.05
22 Selenium (as Se) mg/l <0.01 0.01
22 Arsenic (as As) mg/l <0.01 0.05
23 Barium (as Ba) mg/l <0.01 -
24 Cadmium mg/l <0.01 0.01
25 Nickel (as Ni) mg/l <0.01 -
26 Boron (as B) mg/l <0.01 -
27 Mercury (as Hg) mg/l <0.001 0.001
28 Silver (as Ag) mg/l <0.01 -
29 Lead (as Pb) mg/l <0.01 0.05
30 Zinc (as Pb) mg/l <0.01 5
31 Alkalinity to phenolphthalein mg/l Nil -
32 Alkalinity to methyl orange mg/l 420 200
33 Iron (as Fe) mg/l 0.08 0.3
34 Total Hardness mg/l 538 300
35 Calcium (as Ca) mg/l 39 75
36 Magnesium (as Mg) mg/l 106 30
37 Total Nitrogen (as N) mg/l Nil -
38 Percent sodium % 22.10 -
39 Coliform organisms MPN/100ml -2- Absent
40 Sodium (as Na) mg/l 72
41 Potassium (as K) mg/l 14
WATER QUALITY DATA Location : Handpump, Phulora village (W4) Date of sampling : 29.12.2009
Sl. No.
Parameter Unit Result IS: 10500-1991
Norms
1 pH - 7.02 6.5 – 8.5
2 Colour Hazen Units <5 10
3 Temperature oC 28.0 -
4 Turbidity NTU 6 10
5 Total suspended solids mg/l Nil -
6 Total dissolved solids mg/l 624 500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 4.1 -
9 BOD - 3 days at 27oC mg/l - -
10 COD mg/l 14 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil 0.2
13 Chloride (as CI) mg/l 128 250
14 Flouride (as F) mg/l Nil 1.0
15 Sulphate (as SO4) mg/l 32 200
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l Nil 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.001
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 0.05
22 Selenium (as Se) mg/l <0.01 0.01
22 Arsenic (as As) mg/l <0.01 0.05
23 Barium (as Ba) mg/l <0.01 -
24 Cadmium mg/l <0.01 0.01
25 Nickel (as Ni) mg/l <0.01 -
26 Boron (as B) mg/l <0.01 -
27 Mercury (as Hg) mg/l <0.001 0.001
28 Silver (as Ag) mg/l <0.01 -
29 Lead (as Pb) mg/l <0.01 0.05
30 Zinc (as Pb) mg/l <0.01 5
31 Alkalinity to phenolphthalein mg/l Nil -
32 Alkalinity to methyl orange mg/l 268 200
33 Iron (as Fe) mg/l 0.06 0.3
34 Total Hardness mg/l 245 300
35 Calcium (as Ca) mg/l 68 75
36 Magnesium (as Mg) mg/l 18 30
37 Total Nitrogen (as N) mg/l Nil -
38 Percent sodium % 39.10 -
39 Coliform organisms MPN/100ml -0- Absent
40 Sodium,(as Na) mg/l 78
41 Potassium (as K) mg/l 16
WATER QUALITY DATA
Location : Vidharbha river U/s (W5) Sampling Date : 29.12.2009
Sl. No. Parameter Unit Result IS:2296-1982 Tolerance limits for Inand Surface
water (Class C)
1 pH - 7.11 6.5 – 8.5
2 Colour Hazen Units 30 300
3 Temperature oC 29.0 -
4 Turbidity NTU 40 -
5 Total suspended solids mg/l 22 -
6 Total dissolved solids mg/l 628 1500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.1 4.0
9 BOD - 3 days, 27oC mg/l - 3.0
10 COD mg/l 16 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil -
13 Chloride (as CI) mg/l 148 600
14 Flouride (as F) mg/l 0.10 1.5
15 Sulphate (as SO4) mg/l 40 400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l <0.01 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.005
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 1.5
22 Selenium (as Se) mg/l <0.01 0.05
22 Arsenic (as As) mg/l <0.01 0.2
23 Barium (as Ba) mg/l <0.01 -
24 Cadmium mg/l <0.01 0.01
25 Nickel (as Ni) mg/l <0.01 -
26 Boron (as B) mg/l <0.01 -
27 Mercury (as Hg) mg/l <0.001 -
28 Silver (as Ag) mg/l <0.01 -
29 Lead (as Pb) mg/l <0.01 0.1
30 Zinc (as Pb) mg/l 0.04 15
31 Alkalinity to phenolphthalein
mg/l Nil -
32 Alkalinity to methyl orange mg/l 212 -
33 Iron (as Fe) mg/l 0.10 50
35 Calcium (as Ca) mg/l 64 -
36 Magnesium (as Mg) mg/l 26 -
37 Total Nitrogen (as N) mg/l 0.44 -
38 Percent sodium % 31.96 -
39 Coliform organisms MPN/100ml <1100 5000
40 Sodium (as Na) mg/l 62 -
41 Potassium (as K) mg/l 16 -
WATER QUALITY DATA
Location : Vidharbha river U/s(W5) Sampling Date : 29.12.2009
Sl. No. Parameter Unit Result IS:2296-1982 Tolerance limits for Inand Surface
water (Class C)
1 pH - 7.55 6.5 – 8.5
2 Colour Hazen Units 32 300
3 Temperature oC 29.0 -
4 Turbidity NTU 44 -
5 Total suspended solids mg/l 28 -
6 Total dissolved solids mg/l 658 1500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.0 4.0
9 BOD - 3 days, 27oC mg/l - 3.0
10 COD mg/l 18 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil -
13 Chloride (as CI) mg/l 164 600
14 Flouride (as F) mg/l 0.12 1.5
15 Sulphate (as SO4) mg/l 42 400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l <0.01 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.005
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 1.5
22 Selenium (as Se) mg/l <0.01 0.05
22 Arsenic (as As) mg/l <0.01 0.2
23 Barium (as Ba) mg/l <0.01 -
24 Cadmium mg/l <0.01 0.01
25 Nickel (as Ni) mg/l <0.01 -
26 Boron (as B) mg/l <0.01 -
27 Mercury (as Hg) mg/l <0.001 -
28 Silver (as Ag) mg/l <0.01 -
29 Lead (as Pb) mg/l <0.01 0.1
30 Zinc (as Pb) mg/l 0.04 15
31 Alkalinity to phenolphthalein
mg/l Nil -
32 Alkalinity to methyl orange mg/l 232 -
33 Iron (as Fe) mg/l 0.12 50
35 Calcium (as Ca) mg/l 62 -
36 Magnesium (as Mg) mg/l 24 -
37 Total Nitrogen (as N) mg/l 0.44 -
38 Percent sodium % 38.56 -
39 Coliform organisms MPN/100ml <1100 5000
40 Sodium (as Na) mg/l 62 -
41 Potassium (as K) mg/l 16 -
Existing Water Quality: -
In order to assess the quality of mine pumped out water, monitoring of the same is
being regularly carried out every fortnight as per Environment Protection Rule – 2000. As
there is no pumping of water from the mine, water analysis could not be done.
However, just adjacent to the subject OC mine, there is an operating UG mine namely
Kumbharkahni UG and analysis of mine pumped out water is regularly being carried
out in the said mine. Therefore, the results of Kumbharkhani UG mine pumped out
water has been considered here as reference. The results of analysis of mine pumped
out water from existing Ghonsa OC carried out during quarter ending June 2010 to
June , 2011 have been given below and results show that values of all the parameters
are well below the permissible limits.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : KUMBARKHANI UG
Name of the Location : Mine water discharge - WNKUW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2011 06.04.11 8.06 80 160 BDL
APR. 2011 22.04.11 7.49 72 120 BDL
MAY 2011 08.05.11 7.35 90 230 BDL
MAY 2011 23.05.11 7.64 88 200 BDL
JUN. 2011 07.06.11 7.32 80 150 BDL
JUN. 2011 19.06.11 7.38 98 240 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : KUMBARKHANI UG
Name of the Location : Mine water discharge - WNKUW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2011 06.01.11 7.47 80 200 BDL
JAN. 2011 19.01.11 7.89 90 240 BDL
FEB. 2011 05.02.11 7.74 86 210 BDL
FEB. 2011 20.02.11 8.10 60 160 BDL
MAR. 2011 05.03.11 7.67 86 180 BDL
MAR. 2011 26.03.11 7.28 94 220 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2010
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : KUMBARKHANI UG
Name of the Location : Mine water discharge - WNKUW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2010 06.10.10 7.24 96 200 BDL
NOV. 2010 09.11.10 7.98 90 180 BDL
NOV. 2010 20.11.10 7.80 92 190 BDL
DEC. 2010 06.12.10 7.34 64 80 BDL
DEC. 2010 25.12.10 7.15 66 90 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2010
NAME OF THE AREA : WANI NORTH DATE : 23.10.10
NAME OF THE PROJECT : KUMBARKHANI UG
1. Name of the Location : Mine water discharge - WNKUW-1
Sl. No.
Parameters Analysis Results Standards for discharge
Part A, Schedule VI
1 pH 7.38 5.5 – 9.0
2 Temperature (0C) 28.9 Te<Ts+50C
3 Colour (Hz) 5 *
4 Odour Unobjectionable Unobjectionable
5 Turbidity (NTU) 18 *
6 Conductivity (µs/cm) 704 *
7 Total Suspended Solids (mg/l) 82 100
8 Oil & Grease (mg/l) BDL 10
9 Dissolved Oxygen (mg/l) 4.0 *
10 C.O.D. (mg/l) 160 250
11 B.O.D. 3 days at 270C (mg/l) 8 30
12 Total Residual Chorine (mg/l) BDL 1 (Max.)
13 Ammonical Nitrogen (mg/l) 0.28 50
14 Total kjeldahl Nitrogen (mg/l) 3.3 100
15 Free Ammonia (mg/l) BDL 5.0
16 Arsenic (mg/l) BDL 0.2
17 Lead (mg/l) BDL 0.1
18 Hexavalent Chromium (mg/l) BDL 0.1
19 Total Chromium (mg/l) BDL 2
20 Copper (mg/l) BDL 3
21 Zinc (mg/l) 0.19 5
22 Selenium (mg/l) BDL 0.05
23 Nickel (mg/l) BDL 3
24 Fluoride (mg/l) 0.4 2
25 Dissolved Phosphate (mg/l) 0.38 5
26 Sulphide (mg/l) BDL 2
27 Iron (mg/l) 0.1 3
28 Manganese (mg/l) BDL 2
29 Vanadium (mg/l) BDL 0.2
30 Nitrate Nitrogen (mg/l) 3.2 10
31 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2010
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : KUMBARKHANI UG
Name of the Location : Mine water discharge - WNKUW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2010 05.04.10 8.36 76 120 BDL
APR. 2010 22.04.10 8.49 84 160 BDL
MAY 2010 08.05.10 8.09 94 200 BDL
MAY 2010 22.05.10 7.66 90 180 BDL
JUN. 2010 07.06.10 7.45 98 240 BDL
JUN. 2010 22.06.10 7.48 96 220 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
3.5 HYDROGEOLOGY:
INTRODUCTION
The Ghonsa opencast mine with annual target capacity of 0.45 Mt and mine life of 18
years lies in Wardha Valley Coalfield in Yeotmal district of Maharashtra and is at a
distance of about 20 km south-west of Wani township. The Ghonsa-Kumbarkhani rift
basin in Wardha Valley Coalfield comprises of two of coal seams i.e. Seam-I and Seam-
II separated by a thick sandstone parting of about 15 m (average). This mine is planned
to exploit coal from both coal seams (Seam I & II) with mineable reserve of 7.05 Mt. The
total mine lease area of 293.65 Ha. lies in the Penganga river sub-basin (Plate - II) which
controls the master drainage of this area. The mine area has gentle undulating
topography with ground slope towards south and south-east.
Coal mining is either by underground or opencast method. Both these mining methods
create dis-equilibrium in environmental scenario of the area and disturbs the
groundwater conditions in particular. In view of this, Environmental Management Plan
(EMP) and its clearance are pre-requisites for any kind of mining projects. As a part of
EMP, pre-mining hydrogeological scenario/parameters are to be established as datum
lines and these parameters are to be monitored periodically during active and post-
mining stages to assess the impact on groundwater regime/environment due to the
mining activity and also to suggest suitable remedial measures to minimize the impact.
In order to take up the above task, it is essential to know about the hydrogeological
regime of the Ghonsa OCM area. Hydrogeological regime of a geomorphic region is
mostly controlled by three major aspects namely i) Topography ii) Geology and iii)
Climate besides the groundwater and associated phenomena such as the mode of
occurrence and movement of water, the direction and velocity of water flow, the rate
and magnitude of fluid potential fluctuation, the quantity of water present in the
formations i.e. conduit and storage functions of aquifers, the groundwater reserve, the
recharge-discharge process, the infiltration phenomena, the interaction surface and
groundwater, the type and change of chemical quality of waters in space and time etc.
Generally, changes to hydrogeological regime occur temporarily at different phases of
mining activity are as below :
a) The pre-mining phase represents a system that has evolved over a long period which
is relatively unchanging set of hydrological and hydro-geochemical constituents
existed.
b) The active mining phase represents a period of continued disruption and dis-
equilibrium of total hydrogeological regime.
c) The reclamation phase represents a period in which the hydrological and hydro-
chemical system starts to adjust to the newly created conditions of reclamation.
d) The post-mining phase represents a period in which the system has to a major extent,
adjusted to the post-mining conditions so that the rate of change in the groundwater
system is small relative to phase 2 and 3.
The following hydrogeological regime has been projected from the limited available
data and may represent the existing hydrogeological set-up of Ghonsa OCM area.
GEOLOGY OF THE AREA :
The formations within the Ghonsa OC mine area mainly belong to the Gondwanas The
geological cross- sections prepared at the central part of the quarry almost
perpendicular to the strike reveals that two coal seams occur in Barakar formation which
is overlain by Kamthis/Lametas and sandy clay soil layer at the top. The following
sequence of rock formations are encountered in the quarriable area.
Stratigraphic sequence in Ghonsa block
Age Formation Lithology
Thickness
(m)
Min. Max.
Recent to Sub-
recent
Soil/Weat
hered
zone
Black cotton soil, sandy
soil
Nil 14.0
Cretaceous Lametas Fine to medium grained,
dull white, calcareous
sandstone, chocolate
coloured clay, reddish
and grey shale,
limestone, siltstone
Nil 12.20
------------------------------------------Unconformity-----------------------------------
Upper Permian
to Lower
Triassic
Kamthis Fine to coarse grained,
pinkish, brown,
ferruginous sandstone,
pink, grey sandy
shale/clay
Nil 22.74
Upper Permian
to Middle
Permian
Moturs* Variegated shale/clay
with medium grained, red
to pink sandstone bands,
Nil Nil
Lower Permian Barakars Medium to coarse
grained, gritty, grey
sandstone, grey shale,
sandy shale, alternate
sandstone and shale,
carb. shale and coal
14.38 67.10
* Moturs are absent in the quarriable area. However they are encountered in down dip
side of proposed quarry.
Strike & Dip
In general the beds have NW-SE strike with minor swing in the northern sector where it is
gradually becomes NNW-SSE. The beds generally dip l in 9.5 due south-west to SSW with
minor variation. Generally dip becomes gentler towards the subcrop region and towards
northern part and in the remaining area the dip is slightly steeper.
Faults.
5 Nos of faults traverse in the block area out of which two minor faults occur in the
proposed quarry area.
The buffer zone area is occupied by mostly Basalts (70%) in the western part and the
remaining area is occupied by Vindhyans (25%) and Kamthis/Barakars (5%) - (Plate - V)
under the soil cover of limited thickness.
HYDROGEOLOGICAL SET-UP :
Aquifers :
Generally sandstone horizons serve as aquifers and shale/clay acts as aquicludes in
Gondwanas where as weathered / secondary porous zones are aquifers in Basalts &
Vindhyans. The various hydrogeological units developed in the study area are in the
following table.
Sl.
No.
Type of
Aquifer
Depth
range (m)
Core zone Buffer zone
1. Unconfined 0 - 20.0 Soil
zone/weathered
Lametas
/Kamthis
Weathered Basalts
& Vindhyans
2. Semiconfined/
confined
Beyond
25
Kamthis and
Barakars
Inter trappeans,
vesicular and
fractured / jointed
Basalts, limestone
and sandstone of
Vindhyans and
also sandstone of
Gondwanas.
In the buffer zone, Moturs comparising mostly clay with thin bands of sandstone are not
recoginsed as aquifers and they act as separating media thereby considerably reducing
the scope of Barakars as potential aquifers though they are mostly arenacous in nature.
Due to the Basalt caping, the groundwater potential of the semiconfined aquifer in
general may considerably reduce further.
Groundwater levels :
About 40 open wells/piezometers in and around Ghonsa OC project were inventoried by
CMPDI, RI-IV and fixed them as observation wells. The water levels are being monitored
from from May’06 to Jan’11 and furnished in annexure-III. The location of dug
wells/piezometers is shown in plate-IV.
However, depth to water table in unconfined aquifer in general varies from 3.90 to 14.0
m bgl in pre-monsoon season while it is from 1.90 m to 10.10 m bgl in post-monsoon
period in the year 2010. Water table fluctuation in general is from 1.0 m to 5.80 m
between the two extreme seasons. The water table configuration is mostly similar to that
of topography but with reduced relief. The groundwater flow direction in the core zone is
towards south westerly while it has south-easterly trend in the buffer zone with local
variations. Deep water levels and large zone of fluctuation are indicative of recharge
zone and are observed mostly in the Basalts occurring in western part of the study area.
a. Pre-monsoon : Core Zone – 4.98 to 8.99 m
Buffer Zone – 3.90 to 14.00m
b. Post-monsoon : Core Zone 2.80 to 6.60 m
Buffer Zone – 1.90 to 10.10m
Groundwater Survey and Development Agency (GSDA), Government of Maharashtra
has been monitoring groundwater levels in this area by establishing permanent
observation wells. The pre-monsoon and post-monsoon historical groundwater level
data of the period 1993 to 2002 (10 years) has been collected for four observation wells
falling in and around the study area and furnished in the following table.
Water level data from permanent observation wells of Groundwater Survey and
Development Agency for the period 1993-2002.
(Value in m bgl)
Yea
r
Rasa
(Wani Tahsil)
Nawargaon
(Maregaon
Tehsil)
Bopapur
(Jhari Jamini
Tehsil)
Borgaon Bandi
(Jhari Jamini
Tehsil)
Pre Pos
t
Fluc
t Pre
Pos
t
Flu
ct Pre Post
Fluc
t Pre Post Fluct
199
3
6.6
0
4.3
0 2.30 -- -- -- 6.40 3.60 2.80 7.90 3.85 4.05
199
4
6.0
0
3.9
0 2.10
10.0
0
8.5
0
1.5
0 5.80 2.80 3.00 5.70 4.95 0.75
199
5
5.8
0
2.2
0 3.60 9.80
8.1
0
1.7
0 5.70 2.70 3.00 7.00 5.90 1.10
199
6
6.5
0
2.6
0 3.90
10.6
0
7.7
5
2.8
5 4.90 2.40 2.50 7.75 5.70 2.05
199
7
7.2
0
2.7
0 4.50
10.1
0
8.8
0
1.3
0 6.30 2.20 4.10 8.50 6.10 2.40
199
8
6.8
0
2.1
5 4.65 9.35
8.0
0
1.3
5 5.80 1.90 3.90 7.80 6.40 1.40
199
9
5.6
0
2.7
0 2.90 9.15
8.6
0
0.5
5 4.60 1.70 2.90 7.45 5.15 2.30
200
0
7.0
0
1.2
5 5.75 9.45
8.4
5
1.0
0 5.30 2.55 2.75 7.50 -- --
200
1
7.0
5
2.1
0 4.95 9.55
7.9
5
1.6
0 6.40 2.35 405 7.75 6.30 1.45
200
2
7.7
5
2.5
0 5.25 9.20
8.0
0
1.2
0 6.40 2.60 3.80 8.40 6.35 2.05
Ave
rag
e
6.6
3
2.6
4 3.99 9.69
8.2
4
1.4
5 5.76 2.48 3.28 7.58 5.63 1.95
The above data reveals that the pre-monsoon water level vary from 4.6 m to 10.60 m bgl
with an average of 7.42 m bgl and the post-monsoon water levels range from 1.25 m to
8.80 m bgl with an average of 4.75 m bgl. The fluctuation in water levels between the
two extreme seasons varies from 0.55 m to 5.75 m with an average of 2.67 m.
Water level trend :
Hydrographs of two permanent observation wells fixed by CMPDI, Regional Institute-IV
are presented below to assess the water level trends in pre-monsoon and post-monsoon
seasons.
The water level trend of well No (WN-63) situated in the core zone (at village
Ghonsa) of ghonsa OC mine about 1 km W of existing Ghonsa OC and well no WN-62
situated at Phulora village and about 2.5 km N of Ghonsa OC, indicate there is no
impact on water table as given in the following figure.
HYDROGRAPH OF OBSERVATION WELLS (WN-62/WN63) AT
VILLAGAE PHULORA/GHONSA/ IN BUFFER ZONE OF
GHONSA OCM, WANI NORTH AREA0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
May
'06
Aug
'06
Nov
'06
Jan'07
May
'07
Aug
'07
Nov
'07
Jan'08
May
'08
Aug
'08
Nov
'08
Jan'09
May
'09
Aug
'09
Nov
'09
Jan'10
May
'10
Aug
'10
Nov
'10
Jan'11
TIME IN MONTHS
DT
W (
m b
gl)
General aquifer parameters :
No detailed hydrogeological investigations were carried out at Ghonsa OC mine area.
However, the aquifer parameters evaluated by CMPDI at the nearby Rajur Colliery area
have been considered and attributed for the study area. The projected hydraulic
parameters of the aquifers in Kamthis & Barakar formations are as follows :
Hydraulic conductivity -
Kamthis - 2.4 m/day
Barakars (upper) - 1.0 m/day
Storage coefficient - 5 x 10-3
Specific yield - 0.03
The tubewells constructed in Gondwanas have registered moderate yield ranging from 2
LPS to 10 LPS. However, the borewells in Basalts and Vindhyans in general recorded low
yield varying from negligible to 3.0 LPS with some exceptions of moderate yield due to
secondary porosity and favourable physical setting. It can be inferred that the hydraulic
conductivity of these formations is poor. The specific yield of unconfined aquifer in
Basalts & Vindhyans has been considered around 0.03 (GEC-1997).
GROUNDWATER RESOURCES IN THE AREA :
Groundwater recharge
Rainfall is the main recharge source for groundwater. The study area receives an
average annual rainfall of 1100 mm. Additionally, groundwater is also being recharged
from other sources such as return flow from irrigation and mine pumped out (waste)
water thrown on land/natural drains, minor irrigation reservoir and canals etc. The
replenishable groundwater recharge has been computed by rainfall-infiltration method
in the absence of long term water table fluctuation data of different formations in the
area. The rainfall infiltration factor for semiconsolidated sandstones (Gondwanas) and
Basalts / Vindhyans has been considered to be 12% and 7% respectively (GEC report-
1997) by critical review of all the ground factors responsible for rainfall -recharge to
groundwater. While computation of groundwater recharge, the hilly area with > 20%
slope amounting to about 17 sq. km. has been discarded from the study area of 314 sq.
km. The groundwater recharge computation as per GEC -1997 norms is as under :-
a) Recharge from rainfall : 23.73 MCM
i) Kamthis/Barakar (15.68 Sq.Km) - 2.07 MCM
ii) Basalts/Vindhyans (281.32Sq.Km) - 21.66 MCM
b) Recharge from other sources : 0.86 MCM
i) Irrigation return flow - 0.37 MCM
ii) Return flow from mine pumped
out (waste) water - 0..25 MCM
iii) Recharge from minor irrigation - 0.24 MCM
tank and canals
c) Gross groundwater recharge (a+b) : 24.59 MCM
Groundwater draft :
The groundwater withdrawal is generally for domestic, industry and irrigation requirement
and is quantified as under.
The land use details of the buffer zone are as follows :
a) Irrigated agriculture area - 258 ha.
b) Un-irrigated agriculture area - 19961 ha.
c) Cultivable waste land - 1640 ha.
d) Not available for cultivation - 2666 ha.
e) Forest area - 5762 ha.
f) Uninhabited - 3175 ha
-----------
Total 33462 ha.
The groundwater draft for domestic & irrigation use is computed as under :
Sl No. Purpose No./Area Water
consumption
per capita
Total qty. of
withdrawal (MCM)
1.
a) Domestic
(Human Population)
b) Domestic (Animals)
53840
Nos.
38540
Nos.
70 Lit/day
20 Lit/day
1.43
0.28
2.
Irrigation (for 120 days)
258 ha.
40000
Lit/ha/day
1.24
Total : 2.95
In addition to the above, the working Kumbarkhani UG mine in the study area is also
pumping out groundwater continuously to keep the working faces dry for effective
extraction of coal. An estimate has been made on the water pumped out from this mine
and it comes to 1.24 MCM annually.
Thus, the total groundwater withdrawal in the area amount to 4.19 MCM
Groundwater balance :
i) Gross groundwater recharge : 24.59 MCM
ii) Natural discharge to drains & other
losses (10% of item (i) ) : 2.45 MCM
iii) Net annual groundwater availability : 22.14MCM
iv) Allocation/ projection upto next
25 years for domestic & industrial use : 2.19 MCM
v) Annual groundwater draft for all uses: 4.19 MCM
vi) Groundwater balance (Item iii-iv & v): 15.76 MCM
Groundwater stage of development :
Coal mining is the only industrial activity in the area. Besides this, groundwater utilisation is
mainly for domestic and irrigation use. The level/stage of groundwater development
computation in the present study is around 18.92 %, which can be categorized as "Safe"
with less than 70% value. As per CGWB report on Yeotmal district of Maharashtra, the
stage of development in Wani Tehsil Block in which Ghonsa OCM is located is 5.95 % and
classified as "Safe" category and the same is attached in subsequent pages.
Dynamic & Static resources :
The dynamic and static reserves for the core and buffer zones are estimated by utilising
the aquifer parameter mentioned at the head of 3.4. The opencast mine acts as large
diameter well/ sink wherein all the aquifers overline the working seam would converted in
to unconfined state and the inflow to the mine is contributed from the saturated
overburden formation i.e. multiple aquifer system However the unconfined aquifer is the
most affected in opencast mining area.
The average mine depth of 51 m is considered as exploitable depth for static reserve
estimation in core zone with an area of 2.93 ha. The pre-monsoon water level is around 9
m bgl. with an average fluctuation of 4.0 m.
Whereas for the buffer zone with an area of 295.72 Sq.km. (297.00-2.93), the floor of
unconfined aquifer (50 m) has been considered as extractable depth. The pre-monsoon
water level (average) is about 7.5 m and water table fluctuation is around 2.67 m. The
dynamic & static resources estimated for core and buffer zones are as below :
Estimated Dynamic & Static resources for core and buffer zones
Zone Dynamic reserve Static reserve
Area
(Sq.km)
Water
level
Flu.(m)
Sy Potential
MCM
Area
(Sq.km)
Extractable
thick. of
aquifer
below
Fluc. zone
(m)
Sy Potential MCM
Core 2.93 4.00 0.03 0.35 2.93 21 0.03 1.85
Buffer 294.07 2.67 0.03 23.55 294.07 12.5 0.03 110.28
Total 23.9 112.13
Note : The Ghonsa OCM area is in the recharge area of Penganga river sub-basin.
WATER QUALITY :
Generally, the water quality is mostly alkaline in nature with pH value of 7.9 to 8.5 of
potable quality with low concentration of total dissolved solids (TDS) are to the tune of
236 mg/l to 556 mg/l. (average around 400 mg/lt). The quality of mine discharge from
proposed mine is expected to be with in thresh-holed limits as inferred from the quality of
mine However, monitoring is continuously being done as per Environment Protection
(Amendment Rule, 2000) and in case, any undesirable element noticed, immediate
corrective action will be taken. The quality of ground water in the area is given in
subsequent pages.
Therefore, it can be concluded that the impact on mine water is insignificant so far as the
increase in production is concerned for the last four years. For the balance period of the
project/mine life with the enhanced coal production, scenario is not likely to change
GROUND WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH
Sr. No
Test Parameters
Standard ( IS : 10500 : 1993 )
WN-23,Wahegao
n 15.01.09
WN-58A, Borda
16.01.09
Desirable limit
Permissible limit
1 Apparent Colour ( Hz Unit )
10 5 5 25
2 Odour unobjectionable unobjectionable unobjectionable -
3 Taste Agreeable Agreeable Agreeable -
4 Turbidity NTU 1.8 5.4 5 10
5 pH Value 7.54 at 28.5oC 8.10 at 30.5
oC 6.5 to 8.5 No relaxation
6 Total Hardness as CaCO3 mg/l
600.67 305.67 300 600
7 Iron (as Fe) mg/l 0.03 0.05 0.3 1.0
8 Chlorides (as Cl) mg/l 151.99 25.05 250 1000
9 Residual Chlorine mg/l Nil Nil 0.2 -
10 Fluoride (as F) mg/l 0.2 0.5 1.0 1.5
11 TDS mg/l 1164.11 598.84 500 2000
12 Calcium (as Ca) mg/l 180.20 99.89 75 200
13 Magnesium (as Mg) mg/l 36.57 13.62 30 100
14 Copper as(Cu) mg/l < 0.01 < 0.01 0.05 1.5
15 Manganese as (Mn) mg/l < 0.05 < 0.05 0.1 0.3
16 Sulphate (as SO4) mg/l 83.23 22.83 200 400
17 Nitrates (as NO3) mg/l 254.79 50.52 45 100
18 Mercury as (Hg) mg/l 0.03 0.38 0.001 No relaxation
19 Cadmium as (Cd) mg/l < 0.01 < 0.01 0.01 No relaxation
20 Selenium as (Se) mg/l < 0.01 < 0.01 0.01 No relaxation
21 Arsenic as (As) mg/l 0.005 0.001 0.05 No relaxation
22 Cyanide as (CN) mg/l < 0.01 < 0.01 0.05 No relaxation
23 Lead as (Pb) mg/l 0.02 0.03 0.05 No relaxation
24 Zinc as (Zn) mg/l < 0.1 < 0.1 5 15
25 Chromium as (Cr +6
) mg/l < 0.03 0.033 0.05 No relaxation
26 Aluminum as (Al) mg/l 0.02 0.02 0.03 0.2
27 Boron as (B) mg/l 0.08 0.01 1 5
28 Mineral oil mg/l Absent Absent 0.01 0.03
29 Pesticides mg/l Absent Absent Absent 0.001
30 Total Alkalinity mg/l 300.37 252.14 200 600
31 Phenolic Compunds mg/l < 0.001 < 0.001 0.001 0.002
32 Total Coliform (MPN/100 ml)
Absent > 16 Nil 10
33 E.Cond. at 250C µs/cm 1850 856 - -
GROUND WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH
Sr. No
Test Parameters
Analysis Results
Sampling Code, Location & Sample collection date Standard ( IS : 10500 : 1993 )
WN-63, Ghonsa 16.01.09
WN-64A, Sonegaon 16.01.09
WN-67, Dahegaon 16.01.09
Desirable limit Permissible
limit
1 Apparent Colour ( Hz Unit )
3 1 1 5 25
2 Odour unobjectionable
unobjectionable unobjectionable unobjectionable -
3 Taste Agreeable Agreeable Agreeable Agreeable -
4 Turbidity NTU 2.7 1.6 2.1 5 10
5 pH Value 8.08 at 30.5oC 7.97 at 30.5
oC 8.12 at 30.5
oC 6.5 to 8.5 No relaxation
6 Total Hardness as CaCO3 mg/l
525.43 483.48 559.41 300 600
7 Iron (as Fe) mg/l 0.03 0.008 0.0073 0.3 1.0
8 Chlorides (as Cl) mg/l 105.21 76.17 210.43 250 1000
9 Residual Chlorine mg/l Nil Nil Nil 0.2 -
10 Fluoride (as F) mg/l 0.3 0.5 0.4 1.0 1.5
11 TDS mg/l 945.59 777.21 1500.49 500 2000
12 Calcium (as Ca) mg/l 119.87 95.89 87.90 75 200
13 Magnesium (as Mg) mg/l 54.97 59.35 82.70 30 100
14 Copper as(Cu) mg/l < 0.01 < 0.01 < 0.01 0.05 1.5
15 Manganese as (Mn) mg/l < 0.05 < 0.05 < 0.05 0.1
16 Sulphate (as SO4) mg/l 37.24 30.67 81.56 200 400
17 Nitrates (as NO3) mg/l 128.13 158.88 232.1 45 100
18 Mercury as (Hg) mg/l 0.08 < 0.001 0.007 0.001 No relaxation
19 Cadmium as (Cd) mg/l < 0.01 < 0.01 < 0.01 0.01 No relaxation
20 Selenium as (Se) mg/l < 0.01 < 0.01 < 0.01 0.01 No relaxation
21 Arsenic as (As) mg/l 0.001 0.002 0.002 0.05 No relaxation
22 Cyanide as (CN) mg/l < 0.01 < 0.01 < 0.01 0.05 No relaxation
23 Lead as (Pb) mg/l 0.02 0.03 0.04 0.05 No relaxation
24 Zinc as (Zn) mg/l < 0.1 < 0.1 < 0.1 5 15
25 Chromium as (Cr +6
) mg/l < 0.03 < 0.03 < 0.03 0.05 No relaxation
26 Aluminum as (Al) mg/l 0.08 0.04 0.32 0.03 0.2
27 Boron as (B) mg/l 0.05 0.02 0.16 1 5
28 Mineral oil mg/l Absent Absent Absent 0.01 0.03
29 Pesticides mg/l Absent Absent Absent Absent 0.001
30 Total Alkalinity mg/l 339.83 265.29 350.78 200 600
31 Phenolic Compunds mg/l < 0.001 < 0.001 < 0.001 0.001 0.002
32 Total Coliform (MPN/100 ml)
2 > 16 > 16 Nil 10
33 E.Cond. at 250C µs/cm 1550 1340 2420 - -
GROUND WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH
Sr. No
Test Parameters
Analysis Results
Sampling Code, Location & Sample collection date Standard ( IS : 10500 : 1993 )
WN-71, Kolampod 17.01.09
WN-74, Wirkund 17.01.09
WN-75, Rasa 17.01.09
Desirable limit Permissible
limit
1 Apparent Colour ( Hz Unit )
5 10 5 5 25
2 Odour unobjectionable
unobjectionable unobjectionable unobjectionable -
3 Taste Agreeable Agreeable Agreeable Agreeable -
4 Turbidity NTU 3.3 58 3.3 5 10
5 pH Value 7.92 at 30.5oC 7.84 at 30.5
oC 8.12 at 30.5
oC 6.5 to 8.5 No relaxation
6 Total Hardness as CaCO3 mg/l
299.68 319.65 515.44 300 600
7 Iron (as Fe) mg/l 0.03 0.02 0.01 0.3 1.0
8 Chlorides (as Cl) mg/l 7.01 31.06 90.18 250 1000
9 Residual Chlorine mg/l Nil Nil Nil 0.2 -
10 Fluoride (as F) mg/l 0.5 0.6 0.1 1.0 1.5
11 TDS mg/l 442.4 595.73 1475.6 500 2000
12 Calcium (as Ca) mg/l 68.73 83.11 119.87 75 200
13 Magnesium (as Mg) mg/l 31.13 27.24 52.54 30 100
14 Copper as(Cu) mg/l < 0.01 < 0.01 < 0.01 0.05 1.5
15 Manganese as (Mn) mg/l < 0.05 < 0.05 < 0.05 0.1 0.3
16 Sulphate (as SO4) mg/l 9.59 40.23 114.16 200 400
17 Nitrates (as NO3) mg/l 5.27 45.76 254.79 45 100
18 Mercury as (Hg) mg/l 0.13 0.02 0.02 0.001 No relaxation
19 Cadmium as (Cd) mg/l < 0.01 < 0.01 < 0.01 0.01 No relaxation
20 Selenium as (Se) mg/l < 0.01 < 0.01 < 0.01 0.01 No relaxation
21 Arsenic as (As) mg/l 0.003 0.001 0.003 0.05 No relaxation
22 Cyanide as (CN) mg/l < 0.01 < 0.01 < 0.01 0.05 No relaxation
23 Lead as (Pb) mg/l 0.01 < 0.01 0.02 0.05 No relaxation
24 Zinc as (Zn) mg/l < 0.1 < 0.1 < 0.1 5 15
25 Chromium as (Cr +6
) mg/l < 0.03 < 0.03 < 0.03 0.05 No relaxation
26 Aluminum as (Al) mg/l 0.04 0.04 0.04 0.03 0.2
27 Boron as (B) mg/l 0.01 0.02 0.18 1 5
28 Mineral oil mg/l Absent Absent Absent 0.01 0.03
29 Pesticides mg/l Absent Absent Absent Absent 0.001
30 Total Alkalinity mg/l 342.01 241.16 352.99 200 600
31 Phenolic Compunds mg/l < 0.001 < 0.001 < 0.001 0.001 0.002
32 Total Coliform (MPN/100 ml)
2 > 16 > 16 Nil 10
33 E.Cond. at 250C µs/cm 632 840 2380 - -
GROUND WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH
Sr. No
Test Parameters
Standard ( IS : 10500 : 1993 )
WN-83A, Pilkiwadhona
17.01.09
WN-86, Susri 16.01.09
Desirable limit Permissible
limit
1 Apparent Colour ( Hz Unit )
3 3 5 25
2 Odour unobjectionable
unobjectionable unobjectionable -
3 Taste Agreeable Agreeable Agreeable -
4 Turbidity NTU 4.8 2.6 5 10
5 pH Value 7.85 at 30.5oC 7.89 at 30.5
oC 6.5 to 8.5 No relaxation
6 Total Hardness as CaCO3 mg/l
759.19 313.66 300 600
7 Iron (as Fe) mg/l 0.01 0.1 0.3 1.0
8 Chlorides (as Cl) mg/l 248.52 23.05 250 1000
9 Residual Chlorine mg/l Nil Nil 0.2 -
10 Fluoride (as F) mg/l 0.7 0.2 1.0 1.5
11 TDS mg/l 1310.73 526.33 500 2000
12 Calcium (as Ca) mg/l 167.82 85.51 75 200
13 Magnesium (as Mg) mg/l 82.7 24.32 30 100
14 Copper as(Cu) mg/l < 0.01 < 0.01 0.05 1.5
15 Manganese as (Mn) mg/l < 0.05 < 0.05 0.1 0.3
16 Sulphate (as SO4) mg/l 108.72 26.09 200 400
17 Nitrates (as NO3) mg/l 338.26 57.84 45 100
18 Mercury as (Hg) mg/l 0.01 0.04 0.001 No relaxation
19 Cadmium as (Cd) mg/l < 0.01 < 0.01 0.01 No relaxation
20 Selenium as (Se) mg/l < 0.01 < 0.01 0.01 No relaxation
21 Arsenic as (As) mg/l 0.002 0.001 0.05 No relaxation
22 Cyanide as (CN) mg/l < 0.01 < 0.01 0.05 No relaxation
23 Lead as (Pb) mg/l < 0.01 0.03 0.05
24 Zinc as (Zn) mg/l < 0.1 < 0.1 5 15
25 Chromium as (Cr +6
) mg/l < 0.03 < 0.03 0.05 No relaxation
26 Aluminum as (Al) mg/l 0.05 0.05 0.03 0.2
27 Boron as (B) mg/l 0.14 0.02 1 5
28 Mineral oil mg/l Absent Absent 0.01 0.03
29 Pesticides mg/l Absent Absent Absent 0.001
30 Total Alkalinity mg/l 210.48 241.16 200 600
31 Phenolic Compunds mg/l < 0.001 < 0.001 0.001 0.002
32 Total Coliform (MPN/100 ml)
> 16 Absent Nil 10
33 E.Cond. at 250C µs/cm 2260 731 - -
,
MINE DRAINAGE/PUMPING :
The semiconsolidated Gondwanas are mostly stratified formations. The permeable beds
(Sandstone horizons) act as individual hydrogeological units and develop multi-aquifer
system. As such under these circumstances, the groundwater flow/velocity along the
bedding planes is higher than across the plane. It is imperative that horizontal hydraulic
conductivity is many folds higher than the vertical hydraulic conductivity.
The opencast mine acts as large diameter well/sink resulted in by cutting /extraction of
different aquifer zones/formations overlying the working coal seam. As soon as
depression / pit is created due to mine cut, the initial discharge is generally heavy due to
concentration of flow to that region thereby creating depletion/draw down in water
levels in the surrounding area and the inflow stabilises due to partial desaturation. With
increase in depth of incision, the semiconfined aquifer would also be exposed
/punctured thereby the total system would be converted into water table condition and
a cone of depression would be formed by the gravity drainage from different aquifer
zones. In opencast mining, the unconfined aquifer is the most affected and the
semiconfined aquifer is least affected. The mine effluent & influence is directly
proportional to the mine area and depth.
The groundwater inflow computation has been done by utilising the above mentioned
aquifer and mine parameters. The classic Theis equation has been modified by
introducing mine expansion rate and the groundwater inflow to the Ghonsa OC mine
has been estimated to be around 3500 m3/day (1.28 MCM annually ) at the final quarry
depth of 76 m.
The operating Kumbarkhani UG mine in the buffer zone area is continuously pumping
groundwater to the tune of 1.1 MCM annually as part of mine management.
RADIUS OF MINE INFLUENCE AREA :
In the opencast mines, the different aquifers overlying the working coal seam would be
contributing groundwater to the mine by gravity drainage since they are
exposed/removed at the mine. The anticipated groundwater inflow to the mine is to the
tune of 3500 m3/day at the final quarry depth of 76 m. As such due to this
pumping/gravity drainage, cone of depression would be formed. The shape and extent
of the cone would depend on mainly hydraulic conductivity and specific yield of
aquifers, mine depth & area etc.
Generally steep drawdown cone would be formed in poor potential aquifers thereby the
influence area is to small distance and reverse is established in respect of aquifers with
high hydraulic conductivity. The radius of mine influence area has been estimated for
Ghonsa OCM by using Sichardt formula based on the above mentioned aquifer and
mine parameters and works out to about 600 m at final mine depth of 76 m. It may be
appropriate to mention here that the presence of prominent boundaries/faults and also
interfringing of sandstone and shale beds may restrict the propogation of drawdown
cone.
Mine induced effect would be distinctly noticed within a distance of 300 m from the
mine edge in the down-dip side and becomes milder/ insignificant thereafter. However
the effect is limited/negligible in the up-dip side of the incrop zone due to shallow mine
depth & area and further mine development is towards dip-side only.
3.6 BASE LINE AMBIENT NOISE LEVEL STATUS
Rationale Behind Sampling
To know the background ambient noise level at the operating Ghonsa OCP and its
surrounding environment, 6 locations (one in core zone and five in buffer zone) were
identified for baseline study.
The noise level monitoring stations are given below.
AMBIENT NOISE LEVEL MONITORING STATIONS
SI.No. Location Name Location
Code
1. Core-zone N1
2. Ghonsa village N2
3. Phulora N3
4. Salgaon N4
5. Kalampad village N5
6. Dahegaon village N6
Data presentation & analysis
The generated noise level data are given in subsequent pages and the abstract is
furnished in Table below.
Noise level status
S.No. Zone
Leq. Noise level
(mean)(dB (A)) Noise level
Standards
Daytime Nighttime Daytime Nighttime
1. Core zone 60.8 51.7 75 70
2. Buffer zone 47.4 – 52.6 40.1 – 42.6 55 45
Mean Leq noise levels at day time and night time are ranging from 47.4 to 60.4 dB(A) and
40.1 to 51.7 dB(A) respectively in the study area. While comparing with IS: 4954 -1986
norms for acceptable outdoor noise levels in residential area, these values are found to
be within the limits.
Summary
While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels in residential
area, the Leq values are found to be within the limits.
NOISE LEVEL DATA
Project : Ghonsa OCP
Season : Winter `09-10
S.NO. Location name Daytime Leq. Nighttime Leq.
1 Core-zone (N1) 60.4 51.7
2 Ghonsa village(N2) 52.6 40.8
3 Phulora (N3) 49.3 42.6
4 Salgaon (N4) 48.5 41.3
5 Kalampad village (N5) 47.8 40.6
6 Dahegaon village (N6) 47.4 40.1
3.7 BASE LINE Soil Quality:
In order to assess the quality of soil in the surrounding area covering both core zone and
buffer zone analysis of soil sample at three locations have been carried out as given
below:-
Rationale behind sampling
Soil characteristics, erosion aspects, soil fertility etc., have direct bearing on the
environment. Knowledge of soil parameters is essential for the planning and
implementation of a-forestation. Further, major mining activities affect the soil regime of the
surrounding areas directly or indirectly. Hence, it becomes important to study the soil
characteristics.
By keeping the above aspects in view, three locations are selected in the study area.
Locations are selected in such a way that different type of soils for supporting different
species of vegetation are covered. The soil quality monitoring stations are furnished below
and are shown in Fig. I.
Dump soil, Corezone - S1
Agri.Land, Corezone village - S2
Barren land, Corezone - S3
Data presentation & analysis
The soil quality data collected are given in below.
Soil quality status
S.No. Parameters Range of Concentration
1 pH 6.40-7.63
2. Organic Carbon (%) 0.60 – 1.20
3. Potassium (mg/kg) 0.501 – 159
4. Nitrogen (mg/kg) 0.476 - 249
5. Available magnesium (mg/kg) 0.304 – 1.70
6. Texture Class Clay Loam
Summary
The soil quality in the project area appears to be good and would support after suitable
reclamation measures. SOIL QUALITY DATA
Location : Dump soil, Core Zone (S1) Sampling Date : 20.12.2009
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-100
1. pH 6.40 6.44 6.50
2. Electrical conductivity (m-mhos/cm at 20C) 0.070 0.65 0.079
3. Nitrogen,mg/kg 0.482 0.476 0.489
4. Phosphorus, mg/kg 0.081 0.077 0.088
5. Potassium, mg/kg 0.510 0.501 0.523
6. Total Magnesium, mg/kg 0.312 0.304 0.326
7. Organic carbon (%) 1.20 1.14 1.19
8. Grain size distribution
Sand(%)
Silt (%)
Clay (%)
11.65
52.18
36.17
14.03
49.68
36.29
13.57
48.88
37.55
9. Textural class Clayey silt
10. Bulk density (g/cc) 1.19 1.25 1.32
11. Liquid limit (%) 15.68 14.96 15.80
12. Plastic limit (%) 11.66 11.08 11.26
13. Infiltration rate (cm/hr) - 2.4 -
14. Field capacity (%) 9.9 10.4 10.5
15. Wilting co-efficient (%) 0.8 0.9 0.9
16. Available water storage capacity (%) 9.1 9.5 9.6
SOIL QUALITY DATA Location : Agri. Land, Corezone (S2) Sampling Date : 20.12.2009
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-100
1. pH 7.53 7.59 7.63
2. Electrical conductivity (m-mhos/cm at 20C) 0.34 0.38 0.36
3. Nitrogen, mg/kg 242 249 245
4. Phosphorus, mg/kg 31.4 32.8 34.9
5. Potassium, mg/kg 152 159 155
6. Total Magnesium, mg/kg 1.4 1.7 1.5
7. Organic carbon (%) 1.12 1.15 1.19
8. Grain size distribution
Sand (%)
Silt (%)
Clay (%)
23
25
52
20
24
56
18
23
59
9. Textural class Clay Loam
10. Bulk density (g/cc) 1.15 1.19 1.15
11. Liquid limit (%) 22.8 23.4 25.1
12. Plastic limit (%) 11.8 12.1 12.0
13. Infiltration rate (cm/hr) 2.7
14. Field capacity (%) 5.9 6.1 6.3
15. Wilting co-efficient (%) 0.6 0.5 0.4
16. Available water storage capacity (%) 5.3 5.4 5.6
SOIL QUALITY DATA
Location : Barren Land, Corezone (S3) Sampling Date : 20.12.2009
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-100
1. pH 7.26 7.31 7.35
2. Electrical conductivity (m-mhos/cm at 20C) 0.52 0.53 0.57
3. Nitrogen, mg/kg 156 162 168
4. Phosphorus, mg/kg 12.1 12.8 13.1
5. Potassium, mg/kg 72 76 81
6. Total magnesium, mg/kg 1.22 1.27 1.25
7. Organic carbon (%) 0.62 0.64 0.60
8. Grain size distribution
Sand (%)
Silt (%)
Clay (%)
26
30
44
28
26
96
31
24
45
9. Textural class Clay Loam
10. Bulk density (g/cc) 0.87 0.89 0.93
11. Liquid limit (%) 16.8 17.5 17.7
12. Plastic limit (%) 14.5 14.8 15.0
13. Infiltration rate (cm/hr) - 3.8 -
14. Field capacity (%) 5.9 6.1 6.3
15. Wilting co-efficient (%) 0.6 0.5 0.5
16. Available water storage capacity (%) 5.3 5.6 5.8
3.8 Flora & Fauna
A. INTRODUCTION
An Environmental Impact Assessment (EIA) study was conducted to generate baseline
data of flora and fauna for Ghonsa (OC) Mine Area during winter months. The project is
situated in Wani North area of Western Coalfields Limited (WCL) in Maharashtra State.
Topographically the areas are encompassed by undulating terrain of flat ridges with
fragments of natural vegetation, which is characterized by tropical dry deciduous forest
type. Mean annual temperatures are recorded between 250c to 400c. Average annual
precipitation is recorded from 800 to1200mm mostly during south west monsoon period.
Generally the soils are sandy loam but predominantly sandy brown at slopes of hilly
terrain.
OBJECTIVE(S):
To generate baseline data on flora and fauna in core and buffer zone of the project.
To assess environmental impacts and potential damages to terrestrial flora, fauna and
aquatic bodies
To suggest environment mitigation measures and conservation plan for the biodiversity of
core and buffer zones.
B. METHODOLOGY:
The survey of flora and fauna was undertaken in core and buffer zones areas during
winter months. The survey team consist Prof. M. Venkayya, Dept. of Botany and Dr. P.S.
Raja Sekhar, Associate professor, Dept. of Environmental Sciences, Andhra University,
Visakhapatnam and VRDS consultancy members Sri .M. D.Salve and Mr. M. Shankar.
The team members conduct field visits with in 15 km range of core zone and buffer zone
areas and covered the villages viz. Gawarala, Nawargaon, Wegaon, Saganpur, Raipur,
Zamkola, Kosara, Palloni, Mendholi, Pattarpur and Hiwardhara. The study aspects
covered by the EIA team under the following subtitles:
FLORA
1. Agriculture crops
2. Commercial crops
3. Plantations done by the WCL/Forest Department
4. Natural vegetation /Forest type
5. Grassland vegetation
6. Endangered species
7. Endemic species
8. Aquatic flora
FAUNA
1. Total listing of faunal elements
2. Endangered species (as per Indian wildlife act)
3. Endemic species
4. Migratory species
5. Migratory corridors or Paths
6. Breeding and spawning grounds
7. Aquatic fauna.
Floral analysis of the study areas of terrestrial origin was carried out based on physical
verification of natural patches selected randomly and plant species associations of the
core and buffer zones. The plant species were identified neither in the field it self based
on their morphological features and reproductive materials. The unknown collected
plant species identity was confirmed with the known herbarium collections of the dept.
of Botany, Andhra University, Visakhapatnam.
The agriculture activities in relation to cropping patterns and seasonal crop varieties
cultivated i.e. vegetables, cereals and pulses were assessed through field survey of the
village crop lands, secondary information gathered from local inhabitants and personal
interviews with the village level revenue officials. All these observations of core and
buffer zone areas were noted on data sheets and are presented in tabular formats.
Fauna was recorded neither from direct observations viz. pug marks, skeletal remains,
animal droppings nor indirect evidences of gathered information by interviewing the
local villagers about the presence or absence of the important wild life fauna.
Avian fauna (bird’s species) was observed through binoculars of focal length 8 x12X and
species identification has been done from ornithological notes and pictorial descriptions
of various authors. The status assessment of faunal elements was determined based on
their frequency of occurrence and as per the scheduled references of the Indian wildlife
(Protection) Act, 1972
TERRESTRIAL FLORA
Terrestrial flora of the region was classified in to natural vegetation of forest origin, agro-
ecosystems of agriculture crop varieties, cash crops of commercial importance, and
agro-forestry plantations raised by the Western Coal Fields and Forest department in the
vicinity of mining project areas.
Agricultural Crops
To a greater extent two times in a year the crops are cultivated during the south west
monsoon months of July to October (Kharif) and winter months of November to January
(Rabi). The cropping pattern is greatly varied from mixed crops in low lands to mono
crop varieties of dry land areas. The crop varieties, which are cultivated in core and
buffer zones of the project, are presented in Tables below.
Commercial Crops
Commercial crops like pulses and oil seeds are cultivated in the crop lands of the project
areas along with traditional crop varieties during the post-monsoon period of November,
December and January for subsistence income generation and livelihood of local
communities. The list of commercial crops grown in core and buffer zone of the project
are presented in Tables below.
Plantations/Agro forestry species:
The following Agro forestry species are raised at farm lands, in cultivable waste lands of
the village outskirts, on the banks of non-perennial streams, rivulets and at road side
vacant areas. The agro forestry species of Core zone and Buffer zones are listed in Tables
below.
Natural Vegetation / Forest Types
The natural vegetation is classified as dry deciduous forest of trees, shrubs and
herbaceous communities. The flora of the region succeeded in to three layer
stratification of top storey of canopy layer, middle storey and lower story of ground level.
Natural vegetation was found to be in degraded status in the mining areas of core zone
with grassy slopes and discontinuous dry deciduous thickets of xerophytes. A systematic
list of plant species of the core and buffer Zones is presented in Table below.
Flora of Core Zone:
List of Agricultural crops in Core zone
Crop variety Family name Botanical name Local/Trade name
Vegetables Amaranthacea Abelmoschus esculentus Bhendi
Cucurbiataceae Coccinia indica Kundru
Solanaceae Capsicum annum Mirchi
Solanum melongena Brinjal
List of Cash (commercial) crops in Core Zone
Crop variety Family name Botanical name Local /Trade name
Not Applicable Na Na Na
List of Agro forestry species of Core Zone
Family name Botanical name Local/Trade name
Anacardiaceae Mangifera indica Amba/Mango
Caesalpinaceae Tamarindus indica Iimli/Tamarind Tree
Cemarubiaceae Ailanthus excelsa Maharukh
Euphorniaceae Phyllanthus emblica Awla/Indian goose berry
Pongamia pinnata Karanj/Beech tree
Graminae Bambusa arundinaceae Bamboo
Meliaceaea Azadirachta indica Neem
Mimosaceae Acacia catechu Khair
A.auaculiformis Babool
Albizia lebeck Shirish
Myrtaceae Syzygium cumini Amrud
Rhamnaceae Zyzyphus jujube Bhor
List of Natural (vegetation) Flora Core Zone Area
Canopy /Upper layer – Tree flora
Family name Botanical name Local/Trade name
Anacardiaceae Semecarpus anacardium Bibba
Annonaceae Annona squamosa Sitaphal
Caesalpinaceae Bahunia racemosa Apta
Cassia fistula Bahawa
Tamarindus indica Chunch
Cemarubiaceae Ailanthus excelsa Maharukh
Combretaceae Anogiessus latifolia Dhawda
Ebenaceae Diospyros melanoxylon Tendu
Euphorbiaceae Phyllanthus emblica Awla
Fabaceae Butea monosperma Palas
Dalbergia paniculata Dhobin
D. sisso Sisam
Erythrina variegate Kasai
Pongamia pinnata Karanj
Pterocorpus marsupium Bija
Graminae Bambusa arundinaceae Katang bamboo
Lecythidaceae Careya arborea Kunbhi
Lytheraceae Lagerstroemia parviflora Lendia/lenda
Meliaceae Azadirachta indica Neem
Mimosaceae Acacia araculiformis Babul
A. catechu Khair
A.nilotica Babul
Albizzia lebbeck Sirish
Cassia siamea Kashid
Leucaena leucocephala Subabul
Moraceae Ficus bengalensis Vad
F.religiosa Pipal
Moringaceae Moringa critifolia Aal
Myrtaceae Syzygium cumini Jamun
Palmae Borassus flabellifer Sindhi
Rhamnaceae Zizyphus mauritiana Ber
Rutaceae Chloroxylon swietenia Behura
Sapindaceae Schleichera oleosa Kusumb
Sterculiaceae Sterculia urnes Karaj
Tiliaceae Grewia tilifolia Dhaman
Verbenaceae Tectona grandis Sagwan
Middle layer – Tress & Climbers
Family name Botanical name Local/ Trade name
Celastraceae Maytenus emarginata Bharati
Combretaceae Calycopteris floribunda Gilibuli
Combretum ovilifolium Piwarvel
Convolvulaceae Argyria nervosa Rakath vel
Ipomoea quiomequit Ganesh vel
I. eriocarpa Boota
I.palmata Ghiabato
Euphorbiaceae Ricinus communis Arandi
Fabaceae Abrus precartorious Gunj
Flocourtiaceae Flacourtia indica Kakai
Minispermaceae Cocculus hirsutus Vasan vel
Periplocaceae Cryptolepis buchanani Dhdhi
Rhamnaceae Ventilago denticulate Lokhandi
Zizypus juzuba Bhor
Z.oenoplia Eroni
Tiliaceae Grewia hirsute Gaturli
Verbenaceae Lantana camara Raimunia
Vitex nigunda Nirgundi
Ground layer – Shrubs & Herbs
Family name Botanical name Local/ Trade name
Acanthaceae Andropogon pumilus Diwartan
Barleria prionitis Katekoranti
Amaranrhus spinosus Kate chawli
Asclepidaceae Hygrophylla sculli Na
Compositae Tridax procumbens Kamarmodi
Parthenium hysterophorus Gajar gawat
Spilanthus acmella Na
E.nummularis Na
Merremia emarginata Undir khani
Euphorbiaceae Euphorbia hirta Dhudhi
Fabaceae Alyscicarpus monilifer Na
Desmodium dichotomum Na
I.cordifolia Na
Tephrosia hamiltonii Divali
Lavendula bipinnata Na
Leucas biflora Na
Malvaceae Hibiscus lobatus Na
H.ovalifolius Na
Sida acuta Na
Mimosaceae Mimosa pudica Lajavanti
Myrtaceae Rotala tenuis Na
Nyctaginaceae Boerhavia diffusa Na
Rananculaceae Cleome viscose Pivili tilwan
Rubiaceae Borreria articularis Na
Physalis minima Na
Zygophylaceae Tribulus terrestris Goakru
Grass Lands:
No prominent grass land ecosystem has been found in the Core zone area. However the
grasslands are mixed with natural vegetation of low lands and in cultivated fields. The
grasses and sedges of core zone are listed in Table below.
List of Grasses and Sedges of Core Zone
Family name Botanical name Local /Trade name
Cyperaceae Kyllina tenufolia Na
Graminae Aristida hystrix Na
Chloris barbata Na
Dactylocte aegyptiaca Na
Digitaria ternate Na
Eragrastiella bifaria Na
Eragrastis ciliaris Na
Eragrastis ciliaris Na
Endangered Flora: No endangered plant species in Core zone.
List of Endangered Flora of Core Zone
Family name Botanical name Local /Trade name
Not Applicable Na Na
Endemic Flora: No endemic plant species have been found in Core zone.
List of Endemic Flora of Core Zone
Family name Botanical name Local /Trade name
Not Applicable Na Na
Aquatic Flora:
No perennial aquatic bodies are present in the Core zone. The following aquatic flora
observed in the village ditches and small ponds.
Aquatic plants of Core zone of Project areas
Family name Botanical name Local/Trade name
Not Applicable Na Na
Flora of Buffer Zone
List of Agricultural crops in Buffer Zone
Crop variety Family name Botanical name Local/Trade name
Cereals Poaceae Zey mays Makkha/Maize
Triticum aestivum Wheat
Pulses Fabacea Cajanus cajan Arhar/Tuar
Cicer arietinum Channa
Phaseolus mungo Mung
Phaseolus aconitifolius Moth
Vegetables Amaranthacea Abelmoschus esculentus Bhendi
Cucurbiataceae Coccinia indica Kundru
Solanaceae Capsicum annum Mirchi
Lycopersicon lycopersicum Tomato
Solanum melongena Brinjal
List of Cash (commercial) crops in Buffer Zone
Crop variety Family name Botanical name Local /Trade name
Pulses Fabacea Cajanus cajan Tuar
Phaseolus mungo Mung
Dolichos lablab Sem
Solanacea Lycopersicon lycopersicum Tomato
Linaceae Linum usitatissimum Alsi/Linseed
List of Agro forestry species in Buffer Zone
Family name Botanical name Local/Trade name
Anacardiaceae Mangifera indica Amba/Mango
Caesalpinaceae Tamarindus indica Iimli/Tamarind Tree
Cemarubiaceae Ailanthus excelsa Maharukh
Combretaceae Terminalia arjuna Arjun
Euphorniaceae Phyllanthus emblica Awla/Indian goose
berry
Fabaceae Dalbergia sisso Shesam/Rose wood
Pongamia pinnata Karanj/Beech tree
Graminae Bambusa arundinaceae Bamboo
Meliaceaea Azadirachta indica Neem
Mimosaceae Acacia catechu Khair
A.auaculiformis Babool
Albizia lebeck Shirish
Myrtaceae Syzygium cumini Amrud
Rhamnaceae Zyzyphus jujube Bhor
Verbenaceae Tectona grandis Sagwan
List of Flora (Natural Vegetation) of Buffer Zone
(a) Canopy /Upper layer – Tree flora
Family name Botanical name Local/Trade name
Anacardiaceae Semecarpus anacardium Bibba
Annonaceae Annona squamosa Sitaphal
Caesalpinaceae Bahunia racemosa Apta
Cassia fistula Bahawa
Hardwickia binnata Anjan
Parkinsonia aculeate Vedi-babul
Tamarindus indica Chunch
Cemarubiaceae Ailanthus excelsa Maharukh
Combretaceae Anogiessus latifolia Dhawda
Terminalia alata Ain
T. arjuna Arjun/Kahu
T. chebula Hirda
Ebenaceae Diospyros melanoxylon Tendu
Euphorbiaceae Phyllanthus emblica Awla
Fabaceae Butea monosperma Palas
Dalbergia paniculata Dhobin
D. sisso Sisam
Erythrina variegate Kasai
Pongamia pinnata Karanj
Pterocorpus marsupium Bija
Graminae Bambusa arundinaceae Katang bamboo
Lecythidaceae Careya arborea Kunbhi
Leeaceae Leea crispa Kuram
Lytheraceae Lagerstroemia parviflora Lendia/lenda
Meliaceae Azadirachta indica Neem
Mimosaceae Acacia araculiformis Babul
A. catechu Khair
A.nilotica Babul
Albizzia lebbeck Sirish
A.odoratisima Shinchuva
A. procera Pandra
Cassia siamea Kashid
Leucaena leucocephala Subabul
Moraceae Ficus bengalensis Vad
F.racemosa Umber
F.religiosa Pipal
Moringaceae Moringa critifolia Aal
Myrtaceae Syzygium cumini Jamun
Eugenia jambolana Jambhul
Palmae Borassus flabellifer Sindhi
Rhamnaceae Zizyphus mauritiana Ber
Rutaceae Chloroxylon swietenia Behura
Sapindaceae Schleichera oleosa Kusumb
Sterculiaceae Sterculia urnes Karaj
Waltheria americana Safed bendi
Tiliaceae Grewia tilifolia Dhaman
Verbenaceae Tectona grandis Sagwan
(b) Middle layer – Tress & Climbers
Family name Botanical name Local/ Trade name
Asclepidaceae Damia extensa Utaranvel
Celastraceae Maytenus emarginata Bharati
Combretaceae Calycopteris floribunda Gilibuli
Combretum ovilifolium Piwarvel
Convolvulaceae Argyria nervosa Rakath vel
Cuscuta reflexa Amar vel
Ipomoea quiomequit Ganesh vel
I. eriocarpa Boota
I.palmata Ghiabato
I.absucura Dopateluta
Discoreaceae Dioscorea bulbifera Akas vel
Euphorbiaceae Kirganelia reticulate Pitundi
Securengia virosa Dhani
Fabaceae Abrus precartorious Gunj
Butea superba Palas vel
Flocourtiaceae Flacourtia indica Kakai
Minispermaceae Cocculus hirsutus Vasan vel
Nyctaginaceae Nyctanthus arbortristis Kharasi
Periplocaceae Cryptolepis buchanani Dhdhi
Rhamnaceae Ventilago denticulate Lokhandi
Zizypus juzuba Bhor
Z.oenoplia Eroni
Z.glaberrima Ghoti
Tiliaceae Grewia hirsute Gaturli
Verbenaceae Lantana camara Raimunia
Vitex nigunda Nirgundi
(d) Ground layer – Shrubs & Herbs
Family name Botanical name Local/ Trade name
Acanthaceae Andropogon pumilus Diwartan
Barleria prionitis Katekoranti
Amaranthaceae Achyranthus aspera Chirchitta
Amaranrhus spinosus Kate chawli
Caesalpinaceae Cassia absus Kan kuti
Compositae Tridax procumbens Kamarmodi
Parthenium hysterophorus Gajar gawat
Spilanthus acmella Na
Convolvulaceae Evolvulus alsinoides Na
E.nummularis Na
Merremia emarginata Undir khani
Euphorbiaceae Euphorbia hirta Dhudhi
E.rosea Na
Fabaceae Alyscicarpus monilifer Na
Indigofera linifolia Na
I.cordifolia Na
Tephrosia hamiltonii Divali
Labiateae Hyptis suaveolens Na
Ocimum sanctum Tulsi
Ocimum bassilicum Rantulsi
Leucas biflora Na
Liliaceae Gloriosa superba Khadyanag
Malvaceae Hibiscus lobatus Na
H.ovalifolius Na
Sida acuta Na
Martinaceae Martynia annua Waghnakhi
Mimosaceae Mimosa pudica Lajavanti
Myrtaceae Rotala tenuis Na
Nyctaginaceae Boerhavia diffusa Na
Oxalidaceae Oxalis corniculata Tipani
Rananculaceae Cleome viscose Pivili tilwan
Rubiaceae Borreria articularis Na
Solanaceae Datura metal Kala dhotra
Physalis minima Na
Zygophylaceae Tribulus terrestris Goakru
Grass Lands:
No prominent grass land ecosystem has been found in the core zone area. However the
grasslands are mixed with natural vegetation of low lands and in cultivated fields. The
grasses and sedges of Buffer zone are listed in Table below.
List of Grasses and Sedges of Buffer Zone
Family name Botanical name Local /Trade name
Cyperaceae Kyllina tenufolia Na
Scleria annularis Na
Graminae Apluda mutica Phulkia
Aristida hystrix Na
Chloris barbata Na
Cymbapogon martini Tikhadi
Dactylocte aegyptiaca Na
Digitaria ternate Na
Eleusine indica Na
Eragrastiella bifaria Na
Eragrastis ciliaris Na
Endangered Flora: No endangered plant species in Core zone.
List of Endangered Flora of Buffer Zone
Family name Botanical name Local /Trade name
Not Applicable Na Na
Endemic Flora: No endemic plant species have been found in Core zone.
List of Endemic Flora of Buffer Zone
Family name Botanical name Local /Trade name
Not Applicable Na Na
Aquatic Flora:
No perennial aquatic bodies are present in the Core zone. The following aquatic flora
observed in the village ditches and small ponds.
Aquatic plants of Buffer zone
Family name Botanical name Local/Trade name
Convolvulaceae Ipomoea aquatica Water spinach
Gentianaceae Nymphoides indica Floating Leaf
Nelumbonaceae Nelumbo nucifera Lotus
TERRESTRIAL FAUNA
Fauna of Core Zone
Faunal diversity is very negligible in project areas of the core zone as the habitat conditions
are not being suitable for the distribution of important wildlife fauna. The Check lists of faunal
groups of the Core zone are presented in Table below.
Checklist of Terrestrial Fauna of Core zone
(a) Mammals
Zoological name Common name Status in Wildlife(Protection) Act
Rousettus leschenaulti Indian Fulvous Fruit- Bat Schedule-V, Section 3
Mus booduga Indian Field Mouse Schedule-V, Section, 5
Mus rattus rattus Common House Rat Schedule-V, Section, 6
Bandicota bengalensis Bandicoot Rat Schedule-V, Section, 6
Herpestes edwardsi Indian Grey Mongoose Schedule-IV, Section, 6A
(b) Birds
Zoological name Common name Status in Wildlife(Protection) Act
Bubulcus ibis Cattle egret Schedule-IV, Section,11
Ardeola grayii Indian pond heron Schedule-IV, Section,11
Milvus migrans Black kite Schedule-IV, Section,11
Streptopelia chinensis Spotted dove Schedule-IV, Section,11
Alcedo atthis Small blue kingfisher Schedule-IV, Section,11
Halcyon smyrensis White-breasted
kingfisher
Schedule-IV, Section,11
Merops orientalis Small bee-eater Schedule-IV, Section,11
Acridotheres tristis Common myna Schedule-IV, Section,11
Sturnus contra Asian pied starling Schedule-IV, Section,11
Venellus indicus Red-wattled lapwing Schedule-IV, Section,11
Chardrius dubius Little ringed flover Schedule-IV, Section,11
Psittakula krameri Rose ringed parakeet Schedule-IV, Section,11
Pyccnonotus cafer Red-vented bulbul Schedule-IV, Section,11
Coracias benghalensis Indian roller Schedule-IV, Section,11
Turdoides caudatus Common babbler Schedule-IV, Section,11
Centropus sinensis Crow pheasant Schedule-IV, Section,11
Dicrurrus adsimilis Black Drango Schedule-IV, Section,11
Carvus splendens House crow Schedule—V, Section,1
Passer domesticus House sparrow Schedule-IV, Section,11
(c) Reptiles
Zoological name Common name Status in Wild life(Protection) Act
Not Applicable Na Na
(d) Amphibians
Zoological name Common name Status in wildlife (Protection) Act
Not Applicable Na Na
(e) Butter flies
Zoological name Common name Status in wildlife(Protection) Act
Not Applicable Na Na
Endangered Species (as per Wildlife (Protection) Act: No Endangered fauna was
recorded in Core Zone.
Checklist of Endangered species of Core zone
Zoological name Common name Status in Wild life(Protection) Act
Not Applicable Na Na
Endemic Species of the Project areas: No endemic species were observed in Core Zone
Checklist of Endemic species of Core zone
Zoological name Common name Status in Wild life (Protection) Act
Not Applicable Na Na
Migratory species of the Project areas: No migratory fauna was observed in Core Zone
Table 2.4a: Checklist of Migratory species of Core zone
Zoological name Common name Status in Wild life (Protection) Act
Not Applicable Na Na
Migratory corridors and Flight paths: No Migratory Corridors and Flight paths were
present in Core Zone.
Table 2.5a: Migratory corridors of Core zone
Name of the area Location Protected status
Not Applicable Na Na
Breeding and Spawning grounds: No breeding and spawning grounds were earmarked
for the wildlife fauna in Core zone.
Breeding and spawning grounds of Core zone
Name of the area Location Protected status
Not Applicable Na Na
Aquatic Fauna:
Aquatic fauna belong to Fin-fish (Fishes), Shell- fish (Mollusc) and Crustaceans Prawns) of
non-commercial species. The checklist of aquatic fauna of Core Zone is presented in
Table below
Checklist of Aquatic fauna of Core Zone
(a) Fishes:
Zoological name Common name Status in Wild life(Protection)Act
Clarias batrachus Magur Not Applicable
Mugil cephalous Mullet Not Applicable
Catla catla Catla Not Applicable
(b) Crustaceans
Zoological name Common name Status in Wild life(Protection) Act
Macrobrachium rosenbergi Freshwater Prawn Not Applicable
(c) Mollusc
Zoological name Common name Status in Wild life(Protection) Act
Littorina sp. Common snail Not Applicable
Fauna of Buffer Zone:
The buffer zone areas of the project are providing with suitable habitats for the
distribution of wildlife fauna like mammals. The bird’s fauna is conspicuous in the buffer
zone areas. The fauna of the buffer zone areas are listed in Table below.
Checklist of Terrestrial Fauna of Buffer zone
(a) Mammals
Zoological name Common name Status in Wildlife(Protection) Act
Rousettus leschenaulti Indian Fulvous Fruit- bat Schedule-V, Section 3
Presbytis entellus The Common Langur Schedule-II, Part-I,Section,4A
Mus booduga Indian Field Mouse Schedule-V, Section, 5
Mus rattus rattus Common House Rat Schedule-V, Section, 6
Bandicota bengalensis Bandicoot Rat Schedule-V, Section, 6
Herpestes edwardsi Indian Grey Mongoose Schedule-IV, Section, 6A
Lepus nigricollis nigricollis Black napped Hare Schedule-IV, Section, 3A
Felis chaus Jungle Cat Schedule-II,Part-II,Section,2C
Vulpes bengalensis Indian Fox Schedule-II, Part-I,Section,1B
Canis aureus Jackal Schedule-II,Part-I,Section,2B
(b) Birds
Zoological name Common name Status in Wildlife(Protection) Act
Egretta alba Larger egret Schedule-IV, Section,11
Bubulcus ibis Cattle egret Schedule-IV, Section,11
Ardeola grayii Indian pond heron Schedule-IV, Section,11
Milvus migrans Black kite Schedule-IV, Section,11
Haliastur Indus Brahminy kite Schedule-IV, Section,11
Streptopelia chinensis Spotted dove Schedule-IV, Section,11
Alcedo atthis Small blue kingfisher Schedule-IV, Section,11
Halcyon smyrensis White-breasted
kingfisher
Schedule-IV, Section,11
Merops orientalis Small bee-eater Schedule-IV, Section,11
Dinopium benghalensis Common wood
pecker
Schedule-IV, Section,11
Acridotheres tristis Common myna Schedule-IV, Section,11
Upupa epops Common hoopoe Schedule-IV, Section,11
Sturnus contra Asian pied starling Schedule-IV, Section,11
Dendrocitta vagabond Indian tree pie Schedule-IV, Section,11
Venellus indicus Red-wattled lapwing Schedule-IV, Section,11
Chardrius dubius Little ringed flover Schedule-IV, Section,11
Psittakula krameri Rose ringed parakeet Schedule-IV, Section,11
Pyccnonotus cafer Red-vented bulbul Schedule-IV, Section,11
Coracias benghalensis Indian roller Schedule-IV, Section,11
Turdoides caudatus Common babbler Schedule-IV, Section,11
Centropus sinensis Crow pheasant Schedule-IV, Section,11
Dicrurrus adsimilis Black Drango Schedule-IV, Section,11
Carvus macrorhynchos Jungle crow Schedule-IV, Section,1
Carvus splendens House crow Schedule—V, Section,1
Passer domesticus House sparrow Schedule-IV, Section,11
Ploceus philippinus Baya weaver Schedule-IV, Section,11
(c) Reptiles
Zoological name Common name Status in Wildlife (Protection)
Act
Varanus benghalensis Indian monitor lizard Schedule-II, Part-II
Enhydris enhydris Smooth water snake Schedule-IV, Section,12
Natrix piscator Olive keel back snake Schedule-IV, Section,12
(d) Amphibians
Zoological name Common name Status in Wildlife(Protection) Act
Euphlyctis hexadactyla Common frog Schedule-IV, section,13
Bufo melanostictus Common toad Schedule-IV, section,13
(e) Butter flies
Zoological name Common name Status in Wild life (Protection)
Act
Danaus genutia Striped tiger Schedule-IV, Section,18
Antheria mylita Moth Schedule-IV, Section,18
Endangered Species (as per Wildlife (Protection) Act: No Endangered fauna was
recorded in Buffer Zone.
Checklist of Endangered species of Buffer zone
Zoological name Common name Status in Wild life (Protection)
Act
Not Applicable Na Na
Endemic Species of the Project areas: No endemic species were observed in Buffer Zone
Checklist of Endemic species of Buffer zone
Zoological name Common name Status in Wild life (Protection) Act
Not Applicable Na Na
Migratory species of the Project areas: No migratory fauna observed in Buffer Zone
Checklist of Migratory species of Buffer zone
Zoological name Common name Status in Wild life(Protection) Act
Not Applicable Na Na
Migratory corridors and Flight paths: No migratory corridors and Flight paths were
observed in Buffer Zone.
Migratory corridors of Buffer zone
Name of the area Location Protected status
Not Applicable Na Na
Breeding and Spawning grounds: No breeding and spawning grounds were earmarked
for the wildlife fauna in Buffer zone.
Breeding and spawning grounds of Buffer zone
Name of the area Location Protected status
Not Applicable Na Na
Aquatic Fauna:
Aquatic faunal groups are of Fin- fish (Fishes) and Shell- fish (Mollusc) and Crustaceans
(Prawns) of non-commercial species.
Checklist of Aquatic Fauna of Buffer Zone
(a) Fishes:
Zoological name Common name Status in Wild life(Protection) Act
Channa punctatus Spotted murrel Not Applicable
Clarias batrachus Magur Not Applicable
Mugil cephalous Mullet Not Applicable
Labeo rohita Rohu Not Applicable
Labeo gonious Minor carp Not Applicable
Catla catla Catla Not Applicable
(b) Crustaceans
Zoological name Common name Status in Wild life(Protection) Act
Macrobrachium rosenbergi Freshwater Prawn Not Applicable
Macrobrachium
malcolmsoni
Small Prawn Not Applicable
(c) Mollusc
Zoological name Common name Status in Wild life(Protection) Act
Planoxis sulcatus Ground snail Not Applicable
Littorina sp. Common snail Not Applicable
EIA - Summary Statement
SURVEY REPORT ON GENERATION OF BASE LINE DATA FOR FLORA AND FAUNA OF GHONSA
(OC) MINE OF WESTERN COAL FIELDS LTD.
I. Indicate aerial distance from the periphery of core zone and buffer zone areas of the
following (up to 15km):
S.No Geographical features Name Aerial distance from 15 (km)
Core Zone Buffer Zone
1 National Park /Sanctuary Not
Applicable
None None
2. Biosphere reserve/Tiger/Elephant
Reserve/any other Reserve
Not
Applicable
None None
3. Forest Type (RF/PF/Unclassified) Not
Applicable
None None
4. Habitat for Migratory Birds Not
Applicable
None None
5. Corridor for animals of schedule
1& II of wildlife (protection)
Act,1972
Not
Applicable
None None
6 Archeological sites Notified /Others Not
Applicable
None None
II A. Description of Flora in the Core and Buffer Zones
A. Flora Core Zone Buffer Zone
1.Agricultural crops Table given above Table given above
2.Commercial crops Table given above Table given above
3.Plantations/Agro forestry Table given above Table given above
4.Natural vegetation/Forest
type
No forest areas
(Table given above)
No forest areas (Table
given above)
5. Grass lands No grass lands
(Table given above)
No grass lands
(Table given above)
6.Endangered species None of the species found None of the species found
7. Endemic species None of the species found None of the specie found
8. Others (specify) No prominent aquatic
bodies are present
No prominent aquatic
bodies are present
II B. Description of Fauna in the Core and Buffer Zones
B. Fauna Core Zone Buffer Zone
1.Endangered species None None
2. Endemic Species Not present Not present
3.Migratory species None None
4. Details of Aquatic fauna. No prominent aquatic
bodies
No prominent aquatic
bodies
PROF. M.VENKAIAH, M.SC.P.HD DR.P.S.RAJA SEKHAR, M.SC.PH.D
Professor (Botanist) Associate Professor (Zoologist)
DEPT. OF BOTANY DEPT. OF ENVIRONMENTAL SCIENCES
ANDHRA UNIVERSITY ANDHRA UNIVERSITY
Visakhapatnam-53 003, A.P Visakhapatnam-530 003, A.P
CHAPTER – IV
ANTICIPATED ENVIRONMENTAL IMPACTS
&
MITIGATION MEASURES
4.1 AIR POLLUTION IMPACT ASSESSMENT
The impact assessment has been carried out dealing with the following points:
(a) Phase-wise inventory of air pollution emission sources
(b) Impact assessment
a. Phase-wise inventory of air pollution emission sources
The pollution sources are obvious and to assess the impact, the project life is divided into
following time frames:
Operation phase
Post-operational stage
The activities associated with these time frames and having impact on the ambient air
quality along with the pollutants are enumerated in the following sections:
Operational phase
During this phase, activities necessary for mining of coal, its handling and transport are
taken up. Such activities having impact on ambient air quality are detailed below:
(i) Drilling : Dust
(ii) Blasting of coal and
overburden
: Dust and noxious gases
(iii) Handling of coal : Dust and noxious gases
(iv) Overburden handling : Dust and noxious gases
(v) Dump formation (internal) : Dust and exhaust fumes from
dumpers and dust till the
development of green cover
(vi) Movement of vehicles : Dust and noxious fumes
Post-operational stage
During this stage of the project, the activities related to the closure of mine are to be
carried out. Preparation of mine closure plan shall be carried out during the period four
to five years before the closure of the mine. Some of the activities for the closure are:
Modifications in physical and biological reclamation of backfilled area Salvaging and
shifting operation of HEMMs and other equipment Clearing of coal and other materials,
restoration of infrastructure area & colony area to the extent possible and necessary if
not useful for other projects Management of hydrology and hydrogeology.
Redeployment of workforce, etc, arrangement & implementation of post-operation
monitoring mainly keeping watch, vigil, etc.
The activities having impact on the ambient air quality are enumerated below:
(i) Movement of HEMMs for physical
reclamation of backfilled area
: Dust and obnoxious
fumes
(ii) Movement of vehicles for shifting and
salvaging operation of HEMMs and other
equipment
: Dust and obnoxious
fumes
(iii) Movement of vehicles for clearing of coal
and other materials
: Dust and obnoxious
gases
b. Impact assessment
The mining and its related activities create ambient air pollution. The impact of mining on
ambient air quality are highlighted in the following paragraphs:
The ambient air quality is influenced due to the presence of RPM, SPM, SO2, NOx, etc.,
which are generated due to various activities like drilling, blasting and handling related
to the project. Further, the ambient air quality is affected marginally to a varying degree
due to the mining activities of other nearby opencast and underground coalmines of the
same coalfield. The concentration of pollutants may vary depending upon the various
micro-meteorological parameters and the seasons of a year.
The baseline ambient air quality will be generated surrounding the proposed site of
Ghonsa Expansion OC but now to assess the present ambient air quality scenario
corresponding to the pre-mining status of the proposed project, the baseline data
generated in the surrounding of the existing project (having mostly common area) along
with the regular environmental monitoring data generated in & around the existing
project have been described in the previous chapter. It is seen that the ambient air
quality parameters are well within the permissible limits which establishes the fact that
adverse impact on ambient air quality due to coal mining activities are insignificant.
Now, with the start of the proposed expansion project, there is likelihood of addition of
pollution to the existing concentration level of different attributes of ambient air. Efforts
will be made by implementation of proper abatement measures so as to maintain the
sinking capacity of ambient air to absorb the additional load, if any, thereby maintaining
the quality of ambient air to the pre – mining level to the extent possible.
Now in order to assess the likely contribution of pollution due to proposed mining
activities, air quality data of mine activity area of nearby OCPs have been considered to
prove the fact that an operating mine with the production capacity much more than
that of proposed project, generates pollution load, even in dry season, well below the
limit values, so the pollution load from proposed project will be much less. The details of
data in respect of Pimpalgaon OCP (1.25 MTPA), Ukni OCP (2.20 MTPA) and Junad OCP
(0.60 MTPA) for the period of quarter ending June 2008 to June 2011 are given in
subsequent pages. It can be seen from the data that even in the worst season, the
ambient air quality parameters are within the permissible limits in these mines which are
operating at much higher scale than the mine under consideration.
From the above data it is seen that, the ambient air quality parameters in and around
the existing OC projects located in the same area having much higher scale of
operation are all well within the permissible limits. As these OCPs are having higher scale
of operation compared to that of proposed project, therefore, it can be concluded that
the ambient air quality parameters in & around the proposed project during actual
mining operations with all control measures in place, will also remain well within the
permissible limits.
As it is an established fact that the impact on the ambient air will be mainly due to
proposed coal production leading to enhanced coal handling resulting out of increased
drilling and blasting. Therefore, to assess the anticipated impact due to proposed coal
production, Impact Prediction through numerical modeling ISCST – 3 has been done and
the resultant incremental values have been arrived at. The exercise in the case of Base
line data has been done and it is seen from the data that all the values of SPM & RPM
are well within the permissible limits. There is sufficient sinking capacity available and as
such is not anticipated to reach anywhere near to the permissible limit value even after
achieving the peak production capacity of 0.60 MTPA which has been corroborated by
the numerical modeling results. The details are given in subsequent pages.
From the above table, it can be inferred that even after achieving the peak production
capacity of 0.60 MTPA, the resultant increase in the level of SPM & RPM will be well within
the control. Thus the ambient air quality in and around the mine site will remain well
within the permissible limits with the proposed pollution control measures in place during
actual implementation.
Efforts will be made by implementation of proper abatement measures so as to maintain
the sinking capacity of ambient air to absorb the additional load, if any, thereby
maintaining the quality of ambient air to the pre – mining level to the extent possible.
So the ambient air quality will have no harmful effect on human being, flora and fauna,
soil quality, surface structures and aesthetic value of the surrounding environment as
suitable mitigatory measures will be taken to make the operation eco-friendly.
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2012
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village
: WNGOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
APR. 2012 06.04.12 - 07.04.12 186 82 4 3 APR. 2012 21.04.12 - 22.04.12 143 43 3 2 MAY. 2012 07.05.12 - 08.05.12 126 68 2 1 MAY. 2012 22.05.12 - 23.05.12 176 38 4 3 JUN. 2012 07.06.12 - 08.06.12 137 43 4 4 JUN. 2012 21.06.12 - 22.06.12 195 66 3 2
PERMISSIBLE LIMIT 200 100 80 80
2. Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
APR. 2012 06.04.12 - 07.04.12 162 64 4 3 APR. 2012 21.04.12 - 22.04.12 181 58 2 1 MAY. 2012 07.05.12 - 08.05.12 146 15 4 3 MAY. 2012 21.05.12 - 22.05.12 175 43 3 2 JUN. 2012 07.06.12 - 08.06.12 160 65 4 3 JUN. 2012 21.06.12 - 22.06.12 60 15 3 2
PERMISSIBLE LIMIT 200 100 80 80
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2012
NAME OF THE AREA : WANI NORTH Q.E. : MARCH.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN. 2012 20.01.12 - 21.01.12 140 70 3 2 FEB. 2012 06.02.12 - 07.02.12 129 57 2 2 FEB. 2012 21.02.12 - 22.02.12 75 23 2 1 MAR. 2012 05.03.12 - 06.03.12 106 12 2 2 MAR. 2012 22.03.12 - 23.03.12 184 58 3 3
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN. 2012 20.01.12 - 21.01.12 85 42 2 2 FEB. 2012 06.02.12 - 07.02.12 187 91 4 3 FEB. 2012 21.02.12 - 22.02.12 112 33 3 2 MAR. 2012 04.03.12 - 05.03.12 175 63 4 3 MAR. 2012 22.03.12 - 23.03.12 187 89 4 3
PERMISSIBLE LIMIT 200 100 80 80
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : PIMPALGAON OCP
1. SAM Office : WNPOA-1
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 06.04.09 - 07.04.09 187 90 < 6 < 6
APR. 2009 20.04.09 - 21.04.09 262 125 < 6 < 6
MAY 2009 05.05.09 - 06.05.09 359 177 < 6 < 6
MAY 2009 20.05.09 - 21.05.09 246 112 < 6 < 6
JUN. 2009 04.06.09 - 05.06.09 278 94 < 6 < 6
JUN. 2009 19.06.09 - 20.06.09 397 131 < 6 < 6
TLV as per Env.(Protection) Amendment Rule
2000 600 300 120 120
2. Pragati Nagar – Water filter plant
: WNPOA-2
( 24 hourly values in μg/m3) Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 06.04.09 - 07.04.09 190 80 < 6 < 6
APR. 2009 20.04.09 - 21.04.09 65 21 < 6 < 6
MAY 2009 06.05.09 - 07.05.09 172 82 < 6 < 6
MAY 2009 19.05.09 - 20.05.09 136 56 < 6 < 6
JUN. 2009 05.06.09 - 06.06.09 188 86 < 6 < 6
JUN. 2009 19.06.09 - 20.06.09 153 53 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Workshop : WNPOA--3 ( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 06.04.09 - 07.04.09 360 136 < 6 < 6
APR. 2009 20.04.09 - 21.04.09 496 171 < 6 < 6
MAY 2009 05.05.09 - 06.05.09 409 189 < 6 < 6
MAY 2009 19.05.09 - 20.05.09 399 131 < 6 < 6
JUN. 2009 05.06.09 - 06.06.09 453 192 < 6 < 6
JUN. 2009 19.06.09 - 20.06.09 329 114 < 6 < 6
TLV as per Env.(Protection) Amendment Rule
2000 600 300 120 120
4. Borgaon village
: WNPOA--4
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 196 89 < 6 < 6
APR. 2009 19.04.09 - 20.04.09 191 88 < 6 < 6
MAY 2009 05.05.09 - 06.05.09 176 69 < 6 < 6
MAY 2009 18.05.09 - 19.05.09 115 51 < 6 < 6
JUN. 2009 04.06.09 - 05.06.09 175 78 < 6 < 6
JUN. 2009 18.06.09 - 19.06.09 103 45 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one (P impa lg a on OC - S AM Offic e)
186
308
187262
359246 278
397
0
200
400
600
AP R . AP R . MAY MAY JUN. JUN.Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM
MAY 2009 19.05.09 - 20.05.09 1342
2. CHP ( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM
JUN. 2009 05.06.09 - 06.06.09 2299
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : UKNI OCP
1. Workshop Premises : WNUOA-1
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 332 104 < 6 < 6 MAY 2009 04.05.09 - 05.05.09 310 143 < 6 < 6 MAY 2009 18.05.09 - 19.05.09 339 133 < 6 < 6 JUN. 2009 04.06.09 - 05.06.09 412 184 < 6 < 6 JUN. 2009 18.06.09 - 19.06.09 302 131 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNUOA--2
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 196 82 < 6 < 6 APR. 2009 19.04.09 - 20.04.09 83 33 < 6 < 6 MAY 2009 04.05.09 - 05.05.09 162 57 < 6 < 6 MAY 2009 18.05.09 - 19.05.09 147 64 < 6 < 6 JUN. 2009 06.06.09 - 07.06.09 146 63 < 6 < 6 JUN. 2009 19.06.09 - 20.06.09 147 53 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni) : WNUOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 04.04.09 - 05.04.09 380 146 < 6 < 6 JUN. 2009 04.06.09 - 05.06.09 425 192 < 6 < 6 JUN. 2009 18.06.09 - 19.06.09 388 183 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Pimpri Village
: WNUOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 06.04.09 - 07.04.09 192 84 < 6 < 6 APR. 2009 20.04.09 - 21.04.09 137 39 < 6 < 6 MAY 2009 06.05.09 - 07.05.09 190 78 < 6 < 6 MAY 2009 20.05.09 - 21.05.09 188 83 < 6 < 6 JUN. 2009 06.06.09 - 07.06.09 154 60 < 6 < 6 JUN. 2009 20.06.09 - 21.06.09 183 61 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one ( Ukni OC - Workshop P remises)
267314332 310 339
412302
0
200
400
600
AP R . AP R . MAY MAY JUN. JUN.
Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2009 18.04.09 - 19.04.09 565
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2009 18.04.09 - 19.04.09 639
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : JUNAD OCP
1. SAM office : WNJOA--1 ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 291 88 < 6 < 6 APR. 2009 19.04.09 - 20.04.09 258 123 < 6 < 6 MAY 2009 05.05.09 - 06.05.09 337 115 < 6 < 6 MAY 2009 18.05.09 - 19.05.09 219 91 < 6 < 6 JUN. 2009 05.06.09 - 06.06.09 320 159 < 6 < 6 JUN. 2009 18.06.09 - 19.06.09 297 72 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNJOA--2
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 196 82 < 6 < 6 APR. 2009 19.04.09 - 20.04.09 83 33 < 6 < 6 MAY 2009 04.05.09 - 05.05.09 162 57 < 6 < 6 MAY 2009 18.05.09 - 19.05.09 147 64 < 6 < 6 JUN. 2009 06.06.09 - 07.06.09 146 63 < 6 < 6 JUN. 2009 19.06.09 - 20.06.09 147 53 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNJOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 04.04.09 - 05.04.09 380 146 < 6 < 6 JUN. 2009 04.06.09 - 05.06.09 425 192 < 6 < 6 JUN. 2009 18.06.09 - 19.06.09 388 183 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNJOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2009 05.04.09 - 06.04.09 196 89 < 6 < 6 APR. 2009 19.04.09 - 20.04.09 191 88 < 6 < 6 MAY 2009 05.05.09 - 06.05.09 176 69 < 6 < 6 MAY 2009 18.05.09 - 19.05.09 115 51 < 6 < 6 JUN. 2009 04.06.09 - 05.06.09 175 78 < 6 < 6 JUN. 2009 18.06.09 - 19.06.09 103 45 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one ( J una d OC - S AM Offic e)
265 269 256291 258337
219320 297
0
200
400
600
AP R . AP R . MAY MAY JUN. JUN.
Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Security Post ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
MAY 2009 19.05.09 - 20.05.09 553
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : PIMPALGAON OCP
1. SAM Office
: WNPOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 06.01.09 - 07.01.09 198 60 < 6 < 6 JAN. 2009 19.01.09 - 20.01.09 392 151 < 6 < 6 FEB. 2009 08.02.09 - 09.02.09 285 114 < 6 < 6 FEB. 2009 19.02.09 - 20.02.09 248 83 < 6 < 6 MAR. 2009 03.03.09 - 04.03.09 450 196 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Pragati Nagar – Water filter plant
: WNPOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 06.01.09 - 07.01.09 177 55 < 6 < 6 JAN. 2009 19.01.09 - 20.01.09 140 62 < 6 < 6 FEB. 2009 09.02.09 - 10.02.09 178 76 < 6 < 6 FEB. 2009 19.02.09 - 20.02.09 179 73 < 6 < 6 MAR. 2009 04.03.09 - 05.03.09 179 79 < 6 < 6 MAR. 2009 18.03.09 - 19.03.09 191 82 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Workshop
: WNPOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 18.01.09 - 19.01.09 400 169 < 6 < 6 FEB. 2009 09.02.09 - 10.02.09 243 59 < 6 < 6 FEB. 2009 20.02.09 - 21.02.09 338 153 < 6 < 6 MAR. 2009 02.03.09 - 03.03.09 367 142 < 6 < 6 MAR. 2009 19.03.09 - 20.03.09 373 138 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNPOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 08.01.09 - 09.01.09 191 67 < 6 < 6 JAN. 2009 18.01.09 - 19.01.09 131 45 < 6 < 6 FEB. 2009 10.02.09 - 11.02.09 170 65 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 151 72 < 6 < 6 MAR. 2009 03.03.09 - 04.03.09 95 41 < 6 < 6 MAR. 2009 19.03.09 - 20.03.09 189 84 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one (P impa lg a on OC - S AM Offic e)
195115
198
392285 248
450
0
200
400
600
JAN. JAN. F E B . F E B . MAR . MAR .
Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
MAR. 2009 18.03.09 - 19.03.09 2110
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
MAR. 2009 19.03.09 - 20.03.09 977
CO MONITORING DATA ( All values are given in μg/m
3)
Sl.
No. Monitoring Location Monitoring Date
Observed
Value
NAAQ
Standards (1
hour)
1.
SAM office
09.02.09 < 114.3 10000
2.
Pragati Nagar
09.02.09 < 114.3 4000
3.
Workshop
09.02.09 < 114.3 10000
4.
Borgaon village
10.02.09 < 114.3 4000
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : UKNI OCP
1. Workshop Premises : WNUOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 17.01.09 - 18.01.09 476 192 < 6 < 6 FEB. 2009 10.02.09 - 11.02.09 247 53 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 401 138 < 6 < 6 MAR. 2009 03.03.09 - 04.03.09 389 132 < 6 < 6 MAR. 2009 17.03.09 - 18.03.09 168 80 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNUOA--2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
FEB. 2009 10.02.09 - 11.02.09 181 77 <6 <6 MAR. 2009 17.03.09 - 18.03.09 167 72 <6 <6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNUOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 06.01.09 - 07.01.09 125 41 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 284 72 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Pimpri Village
: WNUOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 06.01.09 - 07.01.09 196 87 < 6 < 6 JAN. 2009 18.01.09 - 19.01.09 171 63 < 6 < 6 FEB. 2009 09.02.09 - 10.02.09 171 66 < 6 < 6 FEB. 2009 19.02.09 - 20.02.09 186 92 < 6 < 6 MAR. 2009 04.03.09 - 05.03.09 169 67 < 6 < 6 MAR. 2009 19.03.09 - 20.03.09 127 22 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one ( Ukni OC - Workshop P remises)
247 283476
247
401 389
1680
200
400
600
JAN. JAN. F E B . F E B . MAR . MAR .
Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
FEB. 2009 10.02.09 - 11.02.09 241
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
MAR. 2009 18.03.09 - 19.03.09 702
CO MONITORING DATA ( All values are given in μg/m
3)
Sl.
No. Monitoring Location Monitoring Date
Observed
Value
NAAQ
Standards (1
hour)
1.
Workshop premises
10.02.09 < 114.3 10000
2.
Bhalar township
10.02.09 < 114.3 4000
3.
Near substation
10.02.09 < 114.3 10000
4.
Pimpri village
10.02.09 114.3 4000
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : JUNAD OCP
1. SAM office
: WNJOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 08.01.09 - 09.01.09 120 44 < 6 < 6 JAN. 2009 18.01.09 - 19.01.09 277 119 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 324 94 < 6 < 6 MAR. 2009 03.03.09 - 04.03.09 259 88 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNJOA--2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
FEB. 2009 10.02.09 - 11.02.09 181 77 <6 <6 MAR. 2009 17.03.09 - 18.03.09 167 72 <6 <6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNJOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 06.01.09 - 07.01.09 125 41 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 284 72 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNJOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JAN. 2009 08.01.09 - 09.01.09 191 67 < 6 < 6 JAN. 2009 18.01.09 - 19.01.09 131 45 < 6 < 6 FEB. 2009 10.02.09 - 11.02.09 170 65 < 6 < 6 FEB. 2009 18.02.09 - 19.02.09 151 72 < 6 < 6 MAR. 2009 03.03.09 - 04.03.09 95 41 < 6 < 6 MAR. 2009 19.03.09 - 20.03.09 189 84 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one ( J una d OC - S AM Offic e)
203 198 209 202 238120
277324
259
0
200
400
600
JAN. JAN. F E B . F E B . MAR . MAR .
Y ear-2008
Y ear-2009
FUGITIVE DUST MONITORING DATA
1. Security Post ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
MAR. 2009 18.03.09 - 19.03.09 743
CO MONITORING DATA ( All values are given in μg/m
3)
Sl.
No. Monitoring Location Monitoring Date
Observed
Value
NAAQ
Standards (1
hour)
1.
SAM office
10.02.09 < 114.3 10000
2.
Bhalar township
10.02.09 < 114.3 4000
3.
Near substation
10.02.09 < 114.3 10000
4.
Borgaon village
10.02.09 < 114.3 4000
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : PIMPALGAON OCP
1. SAM Office
: WNPOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 19.10.08 - 20.10.08 160 39 < 6 < 6 NOV. 2008 05.11.08 - 06.11.08 397 189 < 6 < 6 DEC. 2008 04.12.08 - 05.12.08 303 128 < 6 < 6 DEC. 2008 21.12.08 - 22.12.08 249 64 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Pragati Nagar – Water filter plant
: WNPOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 145 36 < 6 < 6 OCT. 2008 19.10.08 - 20.10.08 78 25 < 6 < 6 NOV. 2008 06.11.08 - 07.11.08 184 83 < 6 < 6 NOV. 2008 20.11.08 - 21.11.08 107 35 < 6 < 6 DEC. 2008 04.12.08 - 05.12.08 143 46 < 6 < 6 DEC. 2008 21.12.08 - 22.12.08 159 76 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Workshop
: WNPOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 19.10.08 - 20.10.08 178 74 < 6 < 6 NOV. 2008 20.11.08 - 21.11.08 219 63 <6 <6 DEC. 2008 21.12.08 - 22.12.08 395 174 <6 <6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNPOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 152 51 < 6 < 6 NOV. 2008 05.11.08 - 06.11.08 187 87 < 6 < 6 NOV. 2008 21.11.08 - 22.11.08 56 18 < 6 < 6 DEC. 2008 03.12.08 - 04.12.08 188 83 < 6 < 6 DEC. 2008 20.12.08 - 21.12.08 178 88 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one (P impa lg a on OC - S AM Offic e)
81 72
276
160
397
303
249
0
200
400
600
OCT. OC T. NOV. NOV. DE C . DE C .Y ear-2007
Y ear-2008
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
OCT. 2008 18.10.08 - 19.10.08 370
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
OCT. 2008 19.10.08 - 20.10.08 461
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : UKNI OCP
1. Workshop Premises : WNUOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 18.10.08 - 19.10.08 158 79 <6 <6 NOV. 2008 20.11.08 - 21.11.08 166 80 <6 <6 DEC. 2008 20.12.08 - 21.12.08 438 218 <6 <6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNUOA--2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 93 21 <6 <6 DEC. 2008 03.12.08 - 04.12.08 116 30 <6 <6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNUOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
NOV. 2008 05.11.08 - 06.11.08 212 99 < 6 < 6 DEC. 2008 03.12.08 - 04.12.08 182 50 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Pimpri Village
: WNUOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 162 48 < 6 < 6 OCT. 2008 20.10.08 - 21.10.08 181 81 < 6 < 6 NOV. 2008 06.11.08 - 07.11.08 196 95 < 6 < 6 NOV. 2008 21.11.08 - 22.11.08 194 61 < 6 < 6 DEC. 2008 04.12.08 - 05.12.08 141 58 < 6 < 6 DEC. 2008 22.12.08 - 23.12.08 184 70 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore zone ( Ukni OC - Works hop P remis es )
71
229212182
0
200
400
600
OC T . OC T . NOV. NOV. DE C . DE C .
Y ear-2007
Y ear-2008
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
NOV. 2008 04.11.08 - 05.11.08 1772
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
NOV. 2008 04.11.08 - 05.11.08 945
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : JUNAD OCP
1. SAM office
: WNJOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 18.10.08 - 19.10.08 171 58 < 6 < 6 NOV. 2008 20.11.08 - 21.11.08 144 69 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNJOA--2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 93 21 <6 <6 DEC. 2008 03.12.08 - 04.12.08 116 30 <6 <6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNJOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
NOV. 2008 05.11.08 - 06.11.08 212 99 < 6 < 6 DEC. 2008 03.12.08 - 04.12.08 182 50 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNJOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2008 14.10.08 - 15.10.08 152 51 < 6 < 6 NOV. 2008 05.11.08 - 06.11.08 187 87 < 6 < 6 NOV. 2008 21.11.08 - 22.11.08 56 18 < 6 < 6 DEC. 2008 03.12.08 - 04.12.08 188 83 < 6 < 6 DEC. 2008 20.12.08 - 21.12.08 178 88 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in C ore z one ( J una d OC - S AM Offic e)
91
251
499
171144
0
200
400
600
OCT. OC T. NOV. NOV. DE C . DE C .
Y ear-2007
Y ear-2008
FUGITIVE DUST MONITORING DATA
1. Security Post ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
OCT. 2008 18.10.08 - 19.10.08 158
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : PIMPALGAON OCP
1. SAM Office
: WNPOA-1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 21.04.08 - 22.04.08 186 85 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 308 151 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Pragati Nagar – Water filter plant
: WNPOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 06.04.08 - 07.04.08 159 54 < 6 < 6 APR. 2008 20.04.08 - 21.04.08 149 58 < 6 < 6 MAY 2008 08.05.08 - 09.05.08 141 61 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 185 88 < 6 < 6 JUN. 2008 05.06.08 - 06.06.08 188 86 < 6 < 6 JUN. 2008 20.06.08 - 21.06.08 44 20 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Workshop
: WNPOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 21.04.08 - 22.04.08 274 112 < 6 < 6 JUN. 2008 06.06.08 - 07.06.08 335 122 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNPOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 20.04.08 - 21.04.08 78 29 < 6 < 6 MAY 2008 07.05.08 - 08.05.08 146 64 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 121 41 < 6 < 6 JUN. 2008 05.06.08 - 06.06.08 192 82 < 6 < 6 JUN. 2008 19.06.08 - 20.06.08 65 32 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2008 06.04.08 - 07.04.08 460
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2008 20.04.08 - 21.04.08 428
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : UKNI OCP
1. Workshop Premises : WNUOA-1
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
MAY 2008 07.05.08 - 08.05.08 267 114 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 314 115 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township
: WNUOA--2
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 05.04.08 - 06.04.08 185 83 < 6 < 6 APR. 2008 19.04.08 - 20.04.08 135 56 < 6 < 6 MAY 2008 07.05.08 - 08.05.08 153 65 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 191 87 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 188 88 < 6 < 6 JUN. 2008 19.06.08 - 20.06.08 77 29 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni)
: WNUOA--3
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 19.04.08 - 20.04.08 260 99 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 271 130 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Pimpri Village
: WNUOA--4
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 06.04.08 - 07.04.08 98 48 < 6 < 6 APR. 2008 21.04.08 - 22.04.08 113 38 < 6 < 6 MAY 2008 08.05.08 - 09.05.08 106 47 < 6 < 6 MAY 2008 22.05.08 - 23.05.08 183 81 < 6 < 6 JUN. 2008 05.06.08 - 06.06.08 194 82 < 6 < 6 JUN. 2008 19.06.08 - 20.06.08 74 27 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
FUGITIVE DUST MONITORING DATA
1. Weigh Bridge ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2008 05.04.08 - 06.04.08 343
2. CHP ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM
APR. 2008 20.04.08 - 21.04.08 1076
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : JUNAD OCP
1. SAM office : WNJOA--1 ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 05.04.08 - 06.04.08 265 131 < 6 < 6 MAY 2008 07.05.08 - 08.05.08 269 127 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 256 99 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bhalar Township : WNJOA--2
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 05.04.08 - 06.04.08 185 83 < 6 < 6 APR. 2008 19.04.08 - 20.04.08 135 56 < 6 < 6 MAY 2008 07.05.08 - 08.05.08 153 65 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 191 87 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 188 88 < 6 < 6 JUN. 2008 19.06.08 - 20.06.08 77 29 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
3. Near Substation (Ukni) : WNJOA--3 ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 19.04.08 - 20.04.08 260 99 < 6 < 6 JUN. 2008 04.06.08 - 05.06.08 271 130 < 6 < 6
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Borgaon village
: WNJOA--4
( 24 hourly values in μg/m3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2008 20.04.08 - 21.04.08 78 29 < 6 < 6 MAY 2008 07.05.08 - 08.05.08 146 64 < 6 < 6 MAY 2008 21.05.08 - 22.05.08 121 41 < 6 < 6 JUN. 2008 05.06.08 - 06.06.08 192 82 < 6 < 6 JUN. 2008 19.06.08 - 20.06.08 65 32 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
FUGITIVE DUST MONITORING DATA
1. Security Post ( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM APR. 2008 06.04.08 - 07.04.08 255
AIR POLLUTION CONTROL MEASURES
Since Ghonsa Expansion OC is a proposed mine, the environmental monitoring data
generation will be done after the mine starts on regular basis as per the Env (Protection)
Amendment Rule published Vide Gazette of dated 25.9.2000. In addition to data
generation, following abatement measures will be taken in order to suppress the dust
and noxious gases generation to the maximum possible extent.
4.2.1 Drilling Operations
In order to reduce dust generated by drilling operation wet drilling will be done.
4.2.2 Blasting Operation
In order to minimize the generation of dust during blasting, the following measures will be
adopted:
(a) Blast holes will be properly placed/spaced/positioned.
(b) Blast will be properly designed in respect of hole-spacing. Hole placing and blast
design are looked into as a fresh case every time, by a competent Blasting Officer
who takes into consideration the actual geo-mining conditions of the site.
(c) Blasting will be done between shifts or during the rest interval when the minimum
number of persons is present around the blast area. In order to quickly disperse the
dust generated in blasting operations, blasting is avoided when there is wind.
Blasting is avoided in the mornings and during cloudy situations.
(d) Adaptation of Controlled Blasting Technique as permitted by DGMS.
4.2.3 Loading & Transport
The loosened overburden material as well as coal, as far as possible will be wetted first
with help of water spray arrangements before the start of loading operations.
Movement of vehicles and HEMM on haul roads, particularly when they are un -
metalled, is another major source of dust generation. To minimize dust generation due to
this operation, the following abatement measures will be taken.
(a) All long-life haul roads and service roads will be properly constructed and
metalled. Unmetalled roads will be kept free of ruts, potholes etc.
(b) All haul-roads will be regularly sprayed with water. Water sprinklers will be regularly
used in the project.
(c) Overloading of vehicles will be avoided.
(d) Covering of loaded trucks by tarpauline.
(e) Regular cleaning of transportation roads.
(f) Adequate green belt will be developed all along the coal transportation road on
both sides.
All the above-mentioned control measures will be continued during the entire life of the
project.
4.2.4 OB Dumps
On the dump slopes and top surface, plantation of grass and trees will be done in
phases. The job of plantation will be taken up from the revenue budget of the mine.
4.2.5 Ambient Air Quality Monitoring
The ambient air quality monitoring will be carried out on regular basis as per the Env
(Protection) Amendment Rule, 2000 so as to ascertain the likely load of various air
pollutants and thereby suitably modifying the various control measures.
4.2.6 Plantation to Check Air Pollution
Plantation has been under taken in the mine area as mitigatives measure against air
pollution, noise pollution and to increase the aesthetic value. The plantation will be
developed at suitable places like overburden dump, along the road sides, unused land
etc to arrest as well as reduce the rate of dispersion of dust generated due to various
mining operations viz. quarrying, coal and OB transportation, OB dumping, CHP
operation. Species to be planted (recommended by Forest Department) in the area are
as follow.
a) Ornamental trees viz Gulmohar, Eucalyptus and fruit trees like Mango, Guava, Jamun
and medicinal plant like Neem etc. will be planted in colony area, schools, dispensary,
community buildings, play ground etc.
b) Ornamental shady trees will be planted e.g. around colony along roads, haul roads,
and around industrial buildings etc.
c) The fast growing varieties of trees like Eucalyptus act as sound barriers where as
ornamental shady trees e.g. Subabul, Kikar and karanj will add to the aesthetic look of
the area.
d) The Species to be planted on OB dumps etc are: Gravalia, Robusia, Punis, Vanetis,
Semal, Karanj, Babul, etc
4.3 WATER QUALITY
Impact Assessment on Water:- Identification of the sources of water pollution
Likely sources of water pollution from this project along with the type of pollutants are as
follows:
(i) Sanitary (domestic) wastewater : Suspended solids and BOD.
(ii) Industrial wastewater from
workshop
: Suspended solids, oil & grease;
(iii) Wastewater from mine : Suspended solids of coal, clay
and oil;
(iv) Surface run-off passing through
coal stockpiles
: Suspended solids;
(v) Storm water from leasehold area
and built-up area
: Suspended solids.
Impact assessment
Mining and its related activities may create water quality problems. The impact of mining
at the project on both surface and ground water sources has been assessed and given
below:
(a) Surface water sources
Deterioration of water quality and pollution of water bodies due to discharge of mine
effluent, if not treated. Change in relief pattern due to mining may cause flooding,
siltation, choking and pollution. Mitigatory measures would involve provision of (i) garland
drains on periphery to prevent surface run-off from entering into the quarry , (ii) catch
drain around the dumps for avoiding siltation and (iii) sedimentation ponds for reducing
the pollution of surface water bodies.
Possible overflow of water from nearby rivers/nallahs must be safeguarded by stone
pitching and strengthening the embankment along the side of the water course
In order to assess the existing quality of surface as well as ground water quality
surrounding the proposed project site, water samples both from ground water as well as
surface water have been collected & analyzed. The detailed report has been discussed
in Chapter – III. It is seen from the data that water quality in both ground and surface
water samples are well within the permissible limits. It can thus be concluded that effluent
from existing mines operating in the vicinity of the proposed project has not affected the
natural water quality adversely as the existing mining operations are being carried out
with adequate control measures.
Further, to assess the likely quality mine pumped out water as well as the quality of
effluent from the proposed Workshop effluent treatment plant, the mine water discharge
quality of existing Operating opencast projects lying in the immediate vicinity of the
same area which are being monitored regularly as per Env. (Protection) Amendment
Rule , 2000 have been considered . The results indicate that even in untreated condition
mine pumped out water does not contain any pollution load. The details of quality
monitoring data in respect of mine pumped out water for Pimpalgaon OC, Ukni OC,
Junad OC for the period of quarter ending June 2008 to June 2011 are given in
subsequent pages.
As such, in the proposed Ghonsa Expansion OCP, similar quality of mine effluent can be
expected because of same hydro geological set up.
However, due care will be taken to treat the mine water discharge by sedimentation for
the proposed project. Effluents from workshop are proposed to be treated in ETP and
moreover water will be mostly recycled in Workshop & CHP. As such, possibility of
adverse impact on natural watercourses after mixing is very remote.
Garland drain around the OB dump & coal dump will be made to avoid siltation of
natural water course.
As indicated earlier, this is already an operating mine, the quality of mine pumped out
water is being monitored once in every fortnight. The proposed expansion is envisaged
within the acquired land and as such there is no change in the hydrogeological set –
up.The base line data generated at surface watercourses and at the ground water in
the villages in the buffer zone have revealed that all parameters are well within the
permissible limits.
Based on the data collected at similar coal mine, it can be concluded that the impact
due to proposed mining operation, the adverse impacts on water both surface as well as
ground water will be insignificant.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : Mine water discharge - WNPOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 06.04.09 8.5 50 70 BDL
APR. 2009 20.04.09 8.2 40 60 BDL
MAY 2009 06.05.09 8.3 24 40 BDL
MAY 2009 19.05.09 8.1 56 80 BDL
JUN. 2009 06.06.09 8.2 36 60 BDL
JUN. 2009 19.06.09 8.3 44 50 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
Name of the Location : ETP water discharge - WNPOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 06.04.09 8.3 48 80 BDL
APR. 2009 20.04.09 8.5 46 70 BDL
MAY 2009 06.05.09 7.8 28 50 BDL
MAY 2009 19.05.09 8.4 54 90 BDL
JUN. 2009 06.06.09 8.1 66 120 BDL
JUN. 2009 19.06.09 8.3 74 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location : Mine water discharge - WNUOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 05.04.09 8.3 58 100 BDL
APR. 2009 19.04.09 8.1 32 70 BDL
MAY 2009 06.05.09 8.0 26 40 BDL
MAY 2009 18.05.09 8.2 28 48 BDL
JUN. 2009 05.06.09 8.1 48 80 BDL
JUN. 2009 19.06.09 8.2 52 90 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNUOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 05.04.09 8.3 46 80 BDL
APR. 2009 19.04.09 8.0 38 60 BDL
MAY 2009 06.05.09 8.4 24 40 BDL
MAY 2009 18.05.09 8.2 46 80 BDL
JUN. 2009 05.06.09 8.1 54 120 2.0
JUN. 2009 19.06.09 8.3 66 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
3. Name of the Location : DETP water discharge - WNUOW-3
Month Date of Sample Analysis Results
collection TSS (mg/l)
BOD (3 days 27oC) mg/l
APR. 2009 05.04.09 64 18
APR. 2009 19.04.09 40 12
MAY 2009 04.05.09 44 12
MAY 2009 18.05.09 42 10
JUN. 2009 05.06.09 58 18
JUN. 2009 19.06.09 54 16
TLV as per Env.(Protection)
Amendment rule 2000 100 30
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Mine water discharge - WNJOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 05.04.09 8.5 50 80 BDL
APR. 2009 19.04.09 8.4 36 50 BDL
MAY 2009 06.05.09 8.3 38 70 BDL
MAY 2009 18.05.09 8.4 34 60 BDL
JUN. 2009 06.06.09 8.2 40 60 BDL
JUN. 2009 19.06.09 8.1 60 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNJOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2009 05.04.09 8.1 52 100 BDL
APR. 2009 19.04.09 8.3 70 140 2.4
MAY 2009 06.05.09 8.5 60 90 BDL
MAY 2009 18.05.09 8.3 38 60 BDL
JUN. 2009 06.06.09 8.2 48 80 BDL
JUN. 2009 19.06.09 8.4 66 110 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : Mine water discharge - WNPOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 07.01.09 8.1 66 80 BDL
JAN. 2009 18.01.09 7.5 80 160 BDL
FEB. 2009 09.02.09 8.4 44 50 BDL
FEB. 2009 19.02.09 7.6 80 140 BDL
MAR. 2009 04.03.09 8.4 46 60 BDL
MAR. 2009 18.03.09 8.0 84 150 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
Name of the Location : ETP water discharge - WNPOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 07.01.09 8.2 42 60 BDL
JAN. 2009 18.01.09 7.6 60 80 BDL
FEB. 2009 09.02.09 8.0 60 100 1.6
FEB. 2009 19.02.09 7.8 28 40 BDL
MAR. 2009 04.03.09 7.8 76 140 2.8
MAR. 2009 18.03.09 7.4 44 80 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location : Mine water discharge - WNUOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 11.01.09 8.1 46 50 BDL
JAN. 2009 18.01.09 7.2 72 140 BDL
FEB. 2009 10.02.09 8.0 52 60 BDL
FEB. 2009 18.02.09 7.6 46 80 BDL
MAR. 2009 03.03.09 7.8 40 60 BDL
MAR. 2009 17.03.09 7.7 22 40 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNUOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 11.01.09 8.3 34 40 BDL
JAN. 2009 18.01.09 7.3 40 60 BDL
FEB. 2009 10.02.09 8.1 76 200 3.6
FEB. 2009 18.02.09 7.8 52 80 BDL
MAR. 2009 03.03.09 7.8 34 90 1.6
MAR. 2009 17.03.09 8.2 42 60 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
3. Name of the Location : DETP water discharge - WNUOW-3
Month Date of Sample Analysis Results
collection TSS (mg/l)
BOD (3 days 27oC) mg/l
JAN. 2009 08.01.09 50 14
JAN. 2009 17.01.09 44 12
FEB. 2009 10.02.09 60 18
FEB. 2009 18.02.09 50 12
MAR. 2009 03.03.09 54 16
MAR. 2009 17.03.09 48 16
TLV as per Env.(Protection)
Amendment rule 2000 100 30
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Mine water discharge - WNJOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 08.01.09 8.6 54 80 BDL
JAN. 2009 18.01.09 8.1 80 180 BDL
FEB. 2009 10.02.09 8.1 54 80 BDL
FEB. 2009 18.02.09 8.2 38 60 BDL
MAR. 2009 03.03.09 8.5 50 80 BDL
MAR. 2009 18.03.09 8.4 62 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNJOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN. 2009 08.01.09 8.5 44 60 BDL
JAN. 2009 18.01.09 7.9 84 140 BDL
FEB. 2009 10.02.09 8.2 44 40 BDL
FEB. 2009 18.02.09 8.1 32 60 BDL
MAR. 2009 03.03.09 8.3 58 100 BDL
MAR. 2009 18.03.09 8.4 54 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : Mine water discharge - WNPOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 7.1 44 60 BDL
OCT. 2008 19.10.08 6.7 28 40 BDL
NOV. 2008 06.11.08 7.5 68 120 BDL
DEC. 2008 04.12.08 7.3 66 120 BDL
DEC. 2008 20.12.08 7.3 98 160 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
Name of the Location : ETP water discharge - WNPOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 7.3 34 40 BDL
OCT. 2008 19.10.08 6.6 64 120 BDL
NOV. 2008 06.11.08 7.6 42 60 BDL
DEC. 2008 04.12.08 7.3 40 60 BDL
DEC. 2008 20.12.08 7.3 56 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH DATE : 19.11.08
NAME OF THE PROJECT : PIMPALGAON OCP
1. Name of the Location Mine water discharge - WNPOW-1
Sl. No.
Parameters Analysis Results
Standards for discharge
Part A, Schedule VI
1 pH 7.5 5.5 – 9.0
2 Temperature (0C) 28.2 Te<Ts+50C
3 Colour (Hz) Acceptable *
4 Odour Unobject. Unobjectionable
5 Turbidity (NTU) 5 *
6 Conductivity (µs/cm) 1970 *
7 Total Suspended Solids (mg/l) 74 100
8 Total Dissolved Solids (mg/l) 1380 *
9 Oil & Grease (mg/l) BDL 10
10 Dissolved Oxygen (mg/l) 4.1 *
11 C.O.D. (mg/l) 180 250
12 B.O.D. 3 days at 270C (mg/l) 6 30
13 Total Residual Chorine (mg/l) BDL 1 (Max.)
14 Ammonical Nitrogen (mg/l) BDL 50
15 Total kjeldahl Nitrogen (mg/l) 2.6 100
16 Free Ammonia (mg/l) BDL 5.0
17 Arsenic (mg/l) BDL 0.2
18 Lead (mg/l) BDL 0.1
19 Hexavalent Chromium (mg/l) BDL 0.1
20 Total Chromium (mg/l) BDL 2
21 Copper (mg/l) BDL 3
22 Zinc (mg/l) 0.22 5
23 Selenium (mg/l) BDL 0.05
24 Nickel (mg/l) BDL 3
25 Fluoride (mg/l) 0.42 2
26 Dissolved Phosphate (mg/l) BDL 5
27 Sulphide (mg/l) BDL 2
28 Iron (mg/l) 0.1 3
29 Manganese (mg/l) 1.9 2
30 Nitrate Nitrogen (mg/l) 2.6 10
31 Sulphate (mg/l) 300 *
32 Chloride (mg/l) 180 *
33 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH DATE : 19.11.08
NAME OF THE PROJECT : PIMPALGAON OCP
1. Name of the Location Workshop (ETP) water discharge WNPOW-2
Sl. No.
Parameters Analysis Results
Standards for discharge
Part A, Schedule VI
1 pH 7.5 5.5 – 9.0
2 Temperature (0C) 28.4 Te<Ts+50C
3 Colour (Hz) Acceptable *
4 Odour Unobject. Unobjectionable
5 Turbidity (NTU) 10 *
6 Conductivity (µs/cm) 3450 *
7 Total Suspended Solids (mg/l) 98 100
8 Total Dissolved Solids (mg/l) 2416 *
9 Oil & Grease (mg/l) BDL 10
10 Dissolved Oxygen (mg/l) 3.8 *
11 C.O.D. (mg/l) 240 250
12 B.O.D. 3 days at 270C (mg/l) 10 30
13 Total Residual Chorine (mg/l) BDL 1 (Max.)
14 Ammonical Nitrogen (mg/l) BDL 50
15 Total kjeldahl Nitrogen (mg/l) 2.5 100
16 Free Ammonia (mg/l) BDL 5.0
17 Arsenic (mg/l) BDL 0.2
18 Lead (mg/l) BDL 0.1
19 Hexavalent Chromium (mg/l) BDL 0.1
20 Total Chromium (mg/l) BDL 2
21 Copper (mg/l) BDL 3
22 Zinc (mg/l) 0.18 5
23 Selenium (mg/l) BDL 0.05
24 Nickel (mg/l) BDL 3
25 Fluoride (mg/l) 0.51 2
26 Dissolved Phosphate (mg/l) BDL 5
27 Sulphide (mg/l) BDL 2
28 Iron (mg/l) 0.04 3
29 Manganese (mg/l) BDL 2
30 Nitrate Nitrogen (mg/l) 3.2 10
31 Sulphate (mg/l) 580 *
32 Chloride (mg/l) 494 *
33 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location : Mine water discharge - WNUOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 6.9 36 40 BDL
OCT. 2008 18.10.08 6.9 28 40 BDL
NOV. 2008 05.11.08 7.6 44 80 BDL
DEC. 2008 03.12.08 7.2 44 80 BDL
DEC. 2008 20.12.08 7.3 36 60 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNUOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 7.2 38 50 BDL
OCT. 2008 18.10.08 6.5 32 60 BDL
NOV. 2008 05.11.08 7.7 48 60 BDL
DEC. 2008 03.12.08 6.7 50 100 BDL
DEC. 2008 20.12.08 7.4 62 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
3. Name of the Location : DETP water discharge - WNUOW-3
Month Date of Sample Analysis Results
collection TSS (mg/l)
BOD (3 days 27oC) mg/l
OCT. 2008 14.10.08 44 14
OCT. 2008 18.10.08 40 14
NOV. 2008 05.11.08 46 15
NOV. 2008 20.11.08 48 16
DEC. 2008 03.12.08 44 16
DEC. 2008 20.12.08 56 17
TLV as per Env.(Protection)
Amendment rule 2000 100 30
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH DATE : 20.11.08
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location Mine water discharge - WNUOW-1
Sl. No.
Parameters Analysis Results
Standards for discharge
Part A, Schedule VI
1 pH 7.3 5.5 – 9.0
2 Temperature (0C) 28.4 Te<Ts+50C
3 Colour (Hz) Acceptable *
4 Odour Unobject. Unobjectionable
5 Turbidity (NTU) 4 *
6 Conductivity (µs/cm) 2230 *
7 Total Suspended Solids (mg/l) 62 100
8 Total Dissolved Solids (mg/l) 1560 *
9 Oil & Grease (mg/l) BDL 10
10 Dissolved Oxygen (mg/l) 4.1 *
11 C.O.D. (mg/l) 100 250
12 B.O.D. 3 days at 270C (mg/l) < 5 30
13 Total Residual Chorine (mg/l) BDL 1 (Max.)
14 Ammonical Nitrogen (mg/l) BDL 50
15 Total kjeldahl Nitrogen (mg/l) 3.1 100
16 Free Ammonia (mg/l) BDL 5.0
17 Arsenic (mg/l) BDL 0.2
18 Lead (mg/l) BDL 0.1
19 Hexavalent Chromium (mg/l) BDL 0.1
20 Total Chromium (mg/l) BDL 2
21 Copper (mg/l) BDL 3
22 Zinc (mg/l) 0.2 5
23 Selenium (mg/l) BDL 0.05
24 Nickel (mg/l) BDL 3
25 Fluoride (mg/l) 0.37 2
26 Dissolved Phosphate (mg/l) 0.02 5
27 Sulphide (mg/l) BDL 2
28 Iron (mg/l) 0.08 3
29 Manganese (mg/l) BDL 2
30 Nitrate Nitrogen (mg/l) 2.6 10
31 Sulphate (mg/l) 550 *
32 Chloride (mg/l) 210 *
33 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH DATE : 20.11.08
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location Workshop (ETP) water discharge WNUOW-2
Sl. No.
Parameters Analysis Results
Standards for discharge
Part A, Schedule VI
1 pH 7.7 5.5 – 9.0
2 Temperature (0C) 28.3 Te<Ts+50C
3 Colour (Hz) Acceptable *
4 Odour Unobject. Unobjectionable
5 Turbidity (NTU) 3 *
6 Conductivity (µs/cm) 890 *
7 Total Suspended Solids (mg/l) 56 100
8 Total Dissolved Solids (mg/l) 534 *
9 Oil & Grease (mg/l) BDL 10
10 Dissolved Oxygen (mg/l) 4.3 *
11 C.O.D. (mg/l) 80 250
12 B.O.D. 3 days at 270C (mg/l) < 5 30
13 Total Residual Chorine (mg/l) BDL 1 (Max.)
14 Ammonical Nitrogen (mg/l) BDL 50
15 Total kjeldahl Nitrogen (mg/l) 3.0 100
16 Free Ammonia (mg/l) BDL 5.0
17 Arsenic (mg/l) BDL 0.2
18 Lead (mg/l) BDL 0.1
19 Hexavalent Chromium (mg/l) BDL 0.1
20 Total Chromium (mg/l) BDL 2
21 Copper (mg/l) BDL 3
22 Zinc (mg/l) 0.13 5
23 Selenium (mg/l) BDL 0.05
24 Nickel (mg/l) BDL 3
25 Fluoride (mg/l) 0.38 2
26 Dissolved Phosphate (mg/l) 0.02 5
27 Sulphide (mg/l) BDL 2
28 Iron (mg/l) BDL 3
29 Manganese (mg/l) BDL 2
30 Nitrate Nitrogen (mg/l) 2.1 10
31 Sulphate (mg/l) 160 *
32 Chloride (mg/l) 42 *
33 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Mine water discharge - WNJOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 7.1 42 60 BDL
OCT. 2008 19.10.08 6.9 34 60 BDL
NOV. 2008 05.11.08 7.6 54 80 BDL
DEC. 2008 05.12.08 7.4 50 80 BDL
DEC. 2008 20.12.08 7.6 34 50 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNJOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
OCT. 2008 14.10.08 6.9 48 80 BDL
OCT. 2008 18.10.08 7.3 38 60 BDL
NOV. 2008 05.11.08 7.7 44 40 BDL
DEC. 2008 05.12.08 7.5 44 60 BDL
DEC. 2008 20.12.08 7.5 64 100 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH DATE : 19.11.08
NAME OF THE PROJECT : JUNAD OCP
1. Name of the Location Mine water discharge - WNJOW-1
Sl. No.
Parameters Analysis Results
Standards for discharge
Part A, Schedule VI
1 pH 6.9 5.5 – 9.0
2 Temperature (0C) 28.1 Te<Ts+50C
3 Colour (Hz) Acceptable *
4 Odour Unobject. Unobjectionable
5 Turbidity (NTU) 14 *
6 Conductivity (µs/cm) 900 *
7 Total Suspended Solids (mg/l) 98 100
8 Total Dissolved Solids (mg/l) 540 *
9 Oil & Grease (mg/l) BDL 10
10 Dissolved Oxygen (mg/l) 3.9 *
11 C.O.D. (mg/l) 160 250
12 B.O.D. 3 days at 270C (mg/l) 6 30
13 Total Residual Chorine (mg/l) BDL 1 (Max.)
14 Ammonical Nitrogen (mg/l) BDL 50
15 Total kjeldahl Nitrogen (mg/l) 2.8 100
16 Free Ammonia (mg/l) BDL 5.0
17 Arsenic (mg/l) BDL 0.2
18 Lead (mg/l) BDL 0.1
19 Hexavalent Chromium (mg/l) BDL 0.1
20 Total Chromium (mg/l) BDL 2
21 Copper (mg/l) BDL 3
22 Zinc (mg/l) 0.18 5
23 Selenium (mg/l) BDL 0.05
24 Nickel (mg/l) BDL 3
25 Fluoride (mg/l) 0.34 2
26 Dissolved Phosphate (mg/l) 0.02 5
27 Sulphide (mg/l) BDL 2
28 Iron (mg/l) 0.1 3
29 Manganese (mg/l) BDL 2
30 Nitrate Nitrogen (mg/l) 1.9 10
31 Sulphate (mg/l) 150 *
32 Chloride (mg/l) 50 *
33 Phenolics Compounds (mg/l) BDL 1 1. BDL - Below Detectable Level, 2. * - Limit not specified.
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : Mine water discharge - WNPOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 06.04.08 7.31 40 60 BDL
APR. 2008 21.04.08 7.50 32 70 BDL
MAY 2008 08.05.08 7.80 20 45 BDL
MAY 2008 22.05.08 7.59 30 50 BDL
JUN. 2008 04.06.08 7.15 45 80 BDL
JUN. 2008 20.06.08 7.09 50 88 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
Name of the Location : ETP water discharge - WNPOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 06.04.08 7.13 65 110 BDL
MAY 2008 08.05.08 7.90 40 75 BDL
MAY 2008 22.05.08 7.53 50 90 BDL
JUN. 2008 04.06.08 7.60 58 100 BDL
JUN. 2008 20.06.08 7.46 45 80 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : UKNI OCP
1. Name of the Location : Mine water discharge - WNUOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 05.04.08 7.33 50 70 BDL
APR. 2008 20.04.08 7.40 35 55 BDL
MAY 2008 07.05.08 7.60 18 25 BDL
MAY 2008 22.05.08 7.47 30 50 BDL
JUN. 2008 04.06.08 6.90 48 60 BDL
JUN. 2008 20.06.08 7.10 55 75 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNUOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 05.04.08 7.38 50 75 BDL
APR. 2008 20.04.08 7.48 38 50 BDL
MAY 2008 07.05.08 8.12 20 38 BDL
MAY 2008 22.05.08 7.15 60 90 BDL
JUN. 2008 04.06.08 7.40 40 70 BDL
JUN. 2008 20.06.08 7.23 48 60 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
3. Name of the Location : DETP water discharge - WNUOW-3
Month Date of Sample Analysis Results
collection TSS (mg/l)
BOD (3 days 27oC) mg/l
APR. 2008 05.04.08 40 12
APR. 2008 20.04.08 38 10
MAY 2008 08.05.08 54 14
MAY 2008 22.05.08 24 8
JUN. 2008 04.06.08 70 18
JUN. 2008 20.06.08 48 12
TLV as per Env.(Protection)
Amendment rule 2000 100 30
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Mine water discharge - WNJOW-1
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 05.04.08 7.63 25 48 BDL
APR. 2008 21.04.08 7.68 40 65 BDL
MAY 2008 07.05.08 7.80 20 45 BDL
MAY 2008 22.05.08 7.58 35 55 BDL
JUN. 2008 04.06.08 7.48 38 60 BDL
JUN. 2008 20.06.08 7.52 30 50 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
2. Name of the Location : Workshop (ETP) water discharge - WNJOW-2
Month Date of Sample Analysis Results
collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APR. 2008 05.04.08 7.60 45 90 BDL
APR. 2008 21.04.08 7.56 58 100 BDL
MAY 2008 07.05.08 7.90 50 95 BDL
MAY 2008 22.05.08 7.70 40 75 BDL
JUN. 2008 04.06.08 7.57 60 110 BDL
JUN. 2008 20.06.08 7.49 68 130 BDL
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
(BDL - Below Detectable Level- Value < 1.0 mg/l)
4.3.1 WATER POLLUTION CONTROL MEASURES
Salient controls measures have been taken are as follows:
i) Industrial Effluent
The wastewater from workshop and CHP, which normally remain laden with oil and
grease, suspended and dissolved solids etc. will be treated in the Effluent Treatment Plant
(ETP). Clear water coming out from the treatment plant will be taken into the closed
water circuit and recycled for its reuse. All parameter of ETP waste discharge will be
monitored regularly as per Env. (Protection) Amendment Rule, 2000.
ii) Mine Water
Most of the suspended particles will be settled in the sump and the supernatant water
will be pumped out. This water will be passed through sedimentation pond on surface,
before being discharged in to natural drain.
iii) Surface Run-off
Adequate numbers of vegetation will be grown on the top surface and slopes of the
dumps in order to arrest the erosion of soil and it also reduces surface run-off, which helps
averting siltation of natural watercourses.
Catch drains of suitable size will be provided around periphery of the OB dump as well as
soil dumps to arrest site and sediment flows from the respective dump sites. In case of OB
benches in the quarry, cross drainage will be provided which will carry silt and sediments
into main sump made at the floor of the seam which will accumulate all the silts and act
as first stage settling pond. The water will then be pumped out through pumps on to the
surface and discharged in to surface settling tank/sedimentation pond. The clear water
from the surface sedimentation tank will be used for watering the mine area, roads and
green belt development. The catch drains mentioned above will be regularly desilted
and maintained properly. In addition, garland drains will also be provided around the
periphery of the excavated area, which will carry surface run off and the drains will be
regularly desilted before onset of monsoon. These drains will allow accumulation of silt
materials and sufficient retention time for settling of silt materials.
The domestic sewage disposal arrangement will be provided in the township.
Regular water quality/effluent quality monitoring will be carried out so as to ascertain the
likely load of pollutants and thereby suitably modifying the control measures.
4.3.2 IMPACT OF MINING ON WATER REGIME :
The mining activity creates dis-equilibrium in environmental scenario of the area and
disturbs the groundwater conditions/regime in particular. The impact on water regime
due to mining activity can be broadly classified as under.
i) Impact on topography & soil
ii) Impact on surface water and quality
iii) Impact on groundwater & quality
A brief description / out-line on these aspects are given below :
Impact on topography & soil:
A local change in ground topography will be created at Ghonsa OCM due to mining
operations such as open pit, embankments, dumps of overburden and coal etc. As a
result, there would be marginal change in the drainage and surface run-off. During these
courses, soil is more susceptible for changes due to erosion, leaching
phenomena/process etc. Further the fine dust particles of coal & overburden may
adversely affect the porosity of soils.
Within the core zone area, cracks and loosening of soil would be resulted in due to mine
and associated activities such as drilling, blasting etc thereby physical/texural changes
would occur in soil/formations. This mine induced process increases the rate of infiltration
and recharge. The studies carried out in Wardha Valley Coalfield have established that
rainfall-infiltration rates have been increased by 100% (doubled) in the core zone area of
opencast mines thereby increasing the scope of groundwater recharge. So also the
back filled area may be a good media for high groundwater recharge due to high
induced permeability. Further, the void proposed to be left out would store substantial
quantity of rain water which can be utilised for domestic & agriculture use and also for
recharging the groundwater source. It may be appropriate to high light the fact that
temporary groundwater loss/deficit created during active mining stage would be
compensated by these different means in the post mining stage so that the initial
groundwater levels are regained to normalcy at the earliest for the utility of the area.
Impact on surface water & quality:
As mentioned earlier, there would be minor change in the ground topography and
infiltration capacity/rate of soil/formation due to mining operations resulting in some local
change in drainage pattern and surface run-off in core zone. It is established that high
infiltration zone would serve as good media for high groundwater recharge and reduces
the surface run-off considerably in the core zone. In view of this, the mine has to handle
more water in the monsoon period besides the additional contribution from the surface
run-off from the catchment area. As such the surface run-off contribution to the natural
drains from the mining area would be minimum thereby drastic change is expected in
hydrologic regime of the river system.
The surface run-off from the dumps of overburden material and coal and mine water
discharge/effluent are laden with suspended particles of coal and other associated
materials. These waters are collected by foot drains with stoppage arrangement and
passed through sedimentation tank/pond. This treated water will be utilised for mine site
requirement and the surplus would be utilised to supplement the water shortage for
domestic and agriculture use of villages if required or discharged onto land
surface/natural drains the surface run-off from the mine area will be free from suspended
particles and its mixings may not induce any change in the surface water quality which is
well is within the thresh-hold limits. So also the groundwater quality in the area
satisfactory/good and its mixing with surface water may not affect the quality adversely.
Impact on groundwater & its quality:
Mining is associated with groundwater problems, particularly when it is below water
table. The impact of mining on groundwater is dependent mainly on mine and aquifer
parameters, groundwater recharge-discharge process etc. In the opencast mining, the
unconfined aquifer gets affected more whereas the semiconfined aquifers are least
affected due to continuous gravity drainage and conventional sump pumping or
advance dewatering schemes for efficient and safe working. As such, during this
exercise, basically the water level is to be depressed/depleted below the working seam
depth in which case large scale mine water pumping can not avoided.
Consequently the mine dewatering would drain out some area around the mine with
decline in groundwater levels. However, these mine induced effects are temporary.
Further, the mine effluent would contaminate the other resources of water if discharged
untreated. However, the water quality monitoring would be undertaken in the
stipulated interval during the mining of Ghonsa OCM.
Groundwater inflow and mine influence area have been estimated and the
groundwater monitoring would be undertaken as corrective measure to avoid adverse
effects. The mine discharge after passing through sedimentation pond / tank would be
discharged onto land/natural drains with earthen check dam so that the groundwater
gets additional recharge by the return flow. The artificial recharge by water conservation
structures in mine influence area proper may not be a viable solution because of the
reason that recharged water would drain to the mine at a faster rate due to the steep
hydraulic gradients resulted in during mining activity. As mentioned earlier the mine
impact may be for temporary period during mine life and the area would regain the
normalcy/benefits in many ways by appropriate reclamation measures during post-
mining period. However, the water shortage in the proposed Ghonsa mine influence
area would be supplemented from the treated mine water discharge for both domestic
& irrigation use of affected villages if any.
FIG-1 HYDROGRAPH OF OBSERVATION WELL AT
RASA(WN-75)
0
1
2
3
4
5
6
7
8
9
May'06
Aug'06
Nov'06
Jan'07
JUN'07
Aug'07
Nov'07
Jan'08
JUN'08
Aug'08
Nov'08
Jan'09
PERIOD ( MONTHS)
DEP
TH T
O W
ATE
R(m
bgl
)
-700m-
0
100
200
300
400
500
RADIUS OF INFLUENCE - 700 m IN GHONSA
OCP (RPR)
Final Depth
4.3.2 Remedial measures to control ground water depletion
The following methodology and remedial measures will be taken to minimize the mine-
induced impact on ground water levels and also adverse effects in the area.
(i) Artificial recharge to ground water system at the periphery of the anticipated
influence area by local stagnation in low lying areas/drains by providing low height
dams/bunds or by injection of mine water discharge. Surface water through
tubewells /percolation structures.
(ii) The water shortage in the villages, if any, in the influence area can be
supplemented by supply of water from outside source or from the mine water after
treatment.
While reclamation of the mined area, void at the deepest portion of the pit has to be
left. This residual pit void would initially serve as access for future expansion and
subsequently it could be backfilled.
Regular well water monitoring in nearby villages will be carried out quarterly as per
MOEF’s guidelines.
4.4 NOISE QUALITY
In order to assess the existing ambient noise level in the surrounding of proposed project
site corresponding to pre-mining scenario, baseline noise level data has been
generated & details are given in Chapter – III along with the regular ambient noise level
monitoring data of the existing mine. All the values are well within the permissible limit.
Proposed mine would be associated with following activities that may generate noise
during operation :
(a) Drilling
(b) Blasting
(c) Shovel operation
(d) Dozing
(e) Movement of dumper
(f) Operation of CHP / Workshop
The following are some of the important activities responsible for high noise level
generation, with their expected noise levels :
All mining activities i.e. drilling, blasting, shoveling, dozing and dumping are associated
with high noise level [about 100 dB(A)].
Operation of most HEMMs produce high noise level. The noise level are in range of 80 –
100 dB(A). Noise level have been found to be related to engine capacity. Crusher –
General noise level due to crusher ranges from 90 dB(A) – 105 dB(A). Some of noisy
equipment produce noise whose level is around 120 dB(A).
The average sound pressure level of some of the HEMM associated with mining operation
which are responsible for high noise level generation are as follows :
EQUIPMENT NOISE LEVEL
[dB(A)]
Dozer 98
Dumper 92
Power shovel 93
Drilling machine 96
ACCEPTABLE INDUSTRIAL NOISE LEVEL
As per Env. (Protection) Amendment Rules, 2000 the ambient air quality standards in
respect of noise in industrial, commercial, residential and silence zones area as follows:
Sl.
No.
Category of
area
Limits [dB(A)]
Day time (6.00 AM to 10.00 PM
)
Night time (10.00 PM to 6.00 AM
)
1. Industrial 75 70
2. Commercial 65 55
3. Residential 55 45
4. Silence zone 50 40
Assessment of the degree of noise to which a workplace noise is harmful, is done by
comparing the values measured at workplace to the permissible limit adopted by
statutory bodies like DGMS.
The Director General of Mines Safety vide their circular no. DG (Tech.)/18 of 1975 has
prescribed the permissible limit for noise level as 90 dB(A) , for the workers engaged in
mining occupation likely to be exposed to in an 8 hour shift period with unprotected ear.
Whereas, the following table shows the maximum permissible noise exposure levels, as
per American Standards, for the industrial workers.
Exposure time
(Hrs./day)
Noise level
[dB(A)]
8 90
6 92
4 95
3 97
2 100
1.5 102
1 105
0.5 108
0.25 or less 115
EXPOSURE TO PULSE OR IMPACT NOISE
SHOULD NOT EXCEED 140 dB(A)
Now to assess the likely contribution from proposed project, the ambient noise level of
operating mines of the same area has been taken into consideration. It is observed that
noise level recorded near CHP & Near Manager’s Office (mine activity area & major
source of noise in opencast mines) of Pimpalgaon OCP(1.50 MTPA), Ukni OCP(2.20
MTPA) & Junad OCP (0.60 MTPA) respectively are well within the permissible limit. The
data from Quarter Ending June 2008 to June 2011 are given in subsequent pages.
With the opening of the proposed Ghonsa Expansion OCP , the expected noise level in
the mine activity area will be much less as compared to Pimpalgaon OCP, Ukni OCP &
Junad OCP as the scale of operation will be less. Hence the impact on noise will be
insignificant.
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : CHP - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 63.9 57.3
APR. 2009 18.04.09 65.7 60.8
MAY 2009 06.05.09 64.8 58.2
MAY 2009 18.05.09 62.9 56.4
JUN. 2009 05.06.09 63.8 57.9
JUN. 2009 19.06.09 66.2 61.7
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Pragati Nagar) - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 50.1 40.7
APR. 2009 18.04.09 51.4 41.9
MAY 2009 06.05.09 52.3 42.4
MAY 2009 18.05.09 49.8 40.9
JUN. 2009 05.06.09 50.0 41.3
JUN. 2009 19.06.09 51.5 42.2
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : UKNI OCP
Name of the Location : CHP WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 66.6 59.3
APR. 2009 18.04.09 68.1 61.2
MAY 2009 06.05.09 65.1 58.4
MAY 2009 18.05.09 67.4 59.9
JUN. 2009 05.06.09 65.8 58.9
JUN. 2009 19.06.09 67.3 60.6
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 52.2 42.9
APR. 2009 18.04.09 50.6 41.2
MAY 2009 06.05.09 52.3 43.0
MAY 2009 18.05.09 51.6 41.8
JUN. 2009 05.06.09 50.4 40.9
JUN. 2009 19.06.09 51.7 42.2
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : JUNAD OCP 5
Name of the Location : Near Manager Office - WNJON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 60.1 55.9
APR. 2009 18.04.09 62.6 57.3
MAY 2009 06.05.09 65.6 58.7
MAY 2009 18.05.09 63.4 56.5
JUN. 2009 06.06.09 62.8 55.4
JUN. 2009 19.06.09 64.3 57.6
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNJON-2
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2009 05.04.09 52.2 42.9
APR. 2009 18.04.09 50.6 41.2
MAY 2009 06.05.09 52.3 43.0
MAY 2009 18.05.09 51.6 41.8
JUN. 2009 05.06.09 50.4 40.9
JUN. 2009 19.06.09 51.7 42.2
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : CHP - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 64.9 58.4
JAN. 2009 18.01.09 63.5 59.0
FEB. 2009 09.02.09 65.2 57.4
FEB. 2009 19.02.09 67.3 58.9
MAR. 2009 04.03.09 66.3 56.4
MAR. 2009 18.03.09 67.4 57.5
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Pragati Nagar) - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 50.7 38.6
JAN. 2009 18.01.09 51.6 41.2
FEB. 2009 09.02.09 53.1 40.4
FEB. 2009 19.02.09 52.3 41.8
MAR. 2009 04.03.09 53.2 42.7
MAR. 2009 18.03.09 52.4 41.9
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : UKNI OCP
Name of the Location : CHP WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 66.7 59.4
JAN. 2009 18.01.09 64.5 57.4
FEB. 2009 10.02.09 65.8 58.2
FEB. 2009 18.02.09 67.3 59.7
MAR. 2009 03.03.09 65.9 58.1
MAR. 2009 17.03.09 67.4 56.5
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 51.6 40.1
JAN. 2009 18.01.09 52.0 41.6
FEB. 2009 10.02.09 53.2 42.3
FEB. 2009 18.02.09 51.8 41.7
MAR. 2009 03.03.09 53.7 43.9
MAR. 2009 17.03.09 52.8 42.6
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2009
NAME OF THE AREA : WANI NORTH Q.E. : MAR.
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Near Manager Office - WNJON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 62.3 56.3
JAN. 2009 18.01.09 61.7 52.3
FEB. 2009 10.02.09 56.3 50.4
FEB. 2009 18.02.09 55.1 49.8
MAR. 2009 03.03.09 56.8 50.9
MAR. 2009 18.03.09 53.4 48.5
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNJON-2
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
JAN. 2009 08.01.09 51.6 40.1
JAN. 2009 18.01.09 52.0 41.6
FEB. 2009 10.02.09 53.2 42.3
FEB. 2009 18.02.09 51.8 41.7
MAR. 2009 03.03.09 53.7 43.9
MAR. 2009 17.03.09 52.8 42.6
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : CHP - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 66.2 57.3
OCT. 2008 19.10.08 68.1 57.9
NOV. 2008 06.11.08 67.2 58.3
NOV. 2008 19.11.08 66.9 56.6
DEC. 2008 04.12.08 65.3 57.1
DEC. 2008 21.12.08 66.9 56.8
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Pragati Nagar) - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 53.1 42.8
OCT. 2008 19.10.08 51.9 41.8
NOV. 2008 06.11.08 52.8 43.1
NOV. 2008 19.11.08 52.4 42.4
DEC. 2008 04.12.08 52.6 41.9
DEC. 2008 21.12.08 53.4 42.4
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : UKNI OCP
Name of the Location : CHP WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 69.2 58.3
OCT. 2008 18.10.08 66.2 57.1
NOV. 2008 05.11.08 65.9 58.2
NOV. 2008 19.11.08 68.1 56.9
DEC. 2008 03.12.08 66.9 57.1
DEC. 2008 20.12.08 67.3 56.7
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 53.2 41.9
OCT. 2008 18.10.08 52.3 42.1
NOV. 2008 05.11.08 53.8 41.6
NOV. 2008 19.11.08 52.3 42.8
DEC. 2008 03.12.08 53.6 43.6
DEC. 2008 20.12.08 53.1 42.1
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Near Manager Office - WNJON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 51.3 48.2
OCT. 2008 19.10.08 55.1 50.0
NOV. 2008 05.11.08 53.6 51.1
NOV. 2008 19.11.08 55.6 50.3
DEC. 2008 05.12.08 54.8 49.2
DEC. 2008 20.12.08 55.3 48.3
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNJON-2
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
OCT. 2008 14.10.08 53.2 41.9
OCT. 2008 18.10.08 52.3 42.1
NOV. 2008 05.11.08 53.8 41.6
NOV. 2008 19.11.08 52.3 42.8
DEC. 2008 03.12.08 53.6 43.6
DEC. 2008 20.12.08 53.1 42.1
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : PIMPALGAON OCP
Name of the Location : CHP - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 06.04.08 66.0 59.0
APR. 2008 20.04.08 67.4 62.3
MAY 2008 08.05.08 72.0 67.4
MAY 2008 22.05.08 68.0 63.5
JUN. 2008 04.06.08 71.0 66.7
JUN. 2008 20.06.08 69.5 60.8
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Pragati Nagar) - WNPON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 06.04.08 53.1 42.6
APR. 2008 20.04.08 52.0 43.1
MAY 2008 08.05.08 53.4 42.0
MAY 2008 22.05.08 51.5 40.9
JUN. 2008 04.06.08 52.0 41.6
JUN. 2008 20.06.08 50.8 39.5
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : UKNI OCP
Name of the Location : CHP WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 05.04.08 65.3 57.2
APR. 2008 20.04.08 70.4 65.0
MAY 2008 07.05.08 71.8 66.8
MAY 2008 22.05.08 68.0 60.9
JUN. 2008 04.06.08 70.0 64.5
JUN. 2008 20.06.08 72.1 65.0
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNUON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 05.04.08 53.1 42.7
APR. 2008 20.04.08 51.3 43.0
MAY 2008 07.05.08 53.0 42.9
MAY 2008 22.05.08 51.0 41.2
JUN. 2008 04.06.08 52.0 40.8
JUN. 2008 20.06.08 49.8 39.9
Permissible Limit 55 45
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2008
NAME OF THE AREA : WANI NORTH Q.E. : JUNE
NAME OF THE PROJECT : JUNAD OCP
Name of the Location : Near Manager Office - WNJON-1
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 05.04.08 57.4 53.7
APR. 2008 20.04.08 62.8 56.7
MAY 2008 07.05.08 65.6 58.6
MAY 2008 22.05.08 62.0 55.9
JUN. 2008 04.06.08 64.5 58.0
JUN. 2008 20.06.08 59.0 55.5
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony (Bhalar) WNJON-2
Month Date of Data Noise Level in dB(A) Remarks
collection Day Time Night Time
APR. 2008 05.04.08 53.1 42.7
APR. 2008 20.04.08 51.3 43.0
MAY 2008 07.05.08 53.0 42.9
MAY 2008 22.05.08 51.0 41.2
JUN. 2008 04.06.08 52.0 40.8
JUN. 2008 20.06.08 49.8 39.9
Permissible Limit 55 45
4.4.1 NOISE POLLUTION CONTROL MEASURES
Monitoring of the noise control will be carried out on regular basis as per the Env
(Protection) Amendment Rule 2000. While planning for an effective noise attenuation
measures, the concept of source, path and receiver has been considered.
(A) Noise Control at Source
There are two areas where the noise generation can be checked at source.
(i) Proper Design
Since the generation of noise can be reduced by reducing the vibration amplitude, the
area of vibrating part and frequency of vibration will be taken care that all loose
contact between metal parts avoided.
Shock absorbing pads will be fixed in the foundation of vibrating equipment / machines.
In case of aerodynamic noise producing sources, mufflers will be provided with the
machines.
(ii) Proper Maintenance
All machines and equipment will be properly maintained. Sound muffler system and
bearing lubricating system etc. of equipment will be kept in proper condition.
Noise control in Transmission Path
The measures are to be taken for control of noise along the transmission path have been
put in following two categories:
(i) Air borne path
(ii) Ground borne path
(i) Air Borne Path
The control in air – borne path has been planned in a number of ways as:
(a) The crusher house, screen house etc., which are source of high level noise
generation are to be enclosed.
(b) Planting of furrows of trees along the thick foliage around the compound and wall
of CHP, workshop and other industrial buildings. This will reduce the spread of noise.
It can be also used as an acoustic enclosure to reduce ambient noise.
(ii) Ground Borne Path
It has been proposed to provide vibration isolators in the form of vibration absorbing
pads placed at the base of vibrating equipment.
(C) Noise Control at Receiver End
Even after adopting above measures, if desired noise level is not achieved at receiver
end, in that case, following measures are suggested:
(a) The workers exposed to high noise level are provided with earplugs.
(b) Provision of enclosed booths at the worksite to protect worker from noisy
environment.
Control Of Ground Vibration
The adverse impacts due to ground vibration occurs because of blasting operations
carried out in the mine. In the proposed Ghonsa Expansion OC blasting will be carried
out as per the provisions of the Statute and only after taking due permission from
Directorate General Of Mines Safety (DGMS). The blasting pattern including spacing of
holes, burden, charge per blast/delay etc. will be duly approved by DGMS and then only
it will be practiced in the mine during actual mining operations. The blasting will be
carried out under the direct supervision of a Blasting Officer and records of every blast
will be monitored and maintained. In case of blasting near the habitation, separate
blasting pattern will be designed and tested so as to avoid/ minimize any adverse
impact of blasting/ ground vibration on the nearby structures. The approval for such type
of Controlled blasting will be obtained from DGMS and will be implemented accordingly.
4.5 During Mining Land Use Pattern:-
The proposed land use pattern during mining operation at proposed Ghonsa Expansion
OCP is as follows:-
LAND USE DURING MININGSL.
NO.
PARTICULARS AGRICULTURAL
LAND (ha)
WASTE
LAND (ha)
FOREST
LAND (ha)
TOTAL
1 EXCAVATION AREA 38.05 - -- 38.05
2 EXT. OB DUMP 29.35 --- - 29.35
3 INFRASTRUCTURE 10.00 - - 10.00
4 BLASTING ZONE 35.39 -- - 35.39
5 EMBANKMENT 15.00 - - 15.00
6 COLONY OUTSIDE
ML AREA
1.00 --- --- 1.00
TOTAL 128.79 ---- ---- 128.79
4.5.1 Solid Waste Management:-
During quarrying operation, OB is initially removed and kept as external dump. Coal
production starts once the coal seam is touched. Once the lowest and economically
mineable coal seam is exhausted, a void / decoaled area is created. The OB generated
from advancing benches is then backfilled in this decoaled area as an internal dump.
With the ongoing process of mining operation, the external dump and internal dump are
technically reclaimed.
Backfilling of Quarry Void:
It has been proposed to work the quarries by Horizontal Slicing Method i.e. conventional
benching system with shovel-dumper combination. This system is being widely used in the
opencast mines of Wardha Valley Coalfield. As explained in Chapter – II, there is only
one quarry in the project having a surface area of 38.05 ha with initial depth of 13 m and
final depth of 46m. The gradient is flat (1 in 12.0 to 1 in 10.5) and as such, the quarry is
being worked by dividing the same into two parts so as to maximize the backfilling. It is
envisaged that part of the overburden will be simultaneously backfilled in the quarry itself
after advancing the face to a safe working distance. The backfilling of quarry void will
start from 4th year of quarry operation.
The detailed break-up of overburden management are as follows:-
S.N. Head Overburden (Mm3)
1 External OB Dump 7.37
2 Internal Dumping 1.17
TOTAL 8.54
4.6.2 Post Mining Land Use Pattern:-
The post-mining land use pattern at Ghonsa Expansion OCP will be as follows:-
POST MINING SCENARIO (AREA FIGS IN ha)
SL. NO.
PARTICULARS PLANTATION VOID PUBLIC USE UNDISTURBED/ UNPLANTED
TOTAL
1 EXTERNAL OB DUMP
29.35 - - - 29.35
2 EXCAVATED AREA 4.00 34.05 - --- 38.05
3 INFRASTRUCTURE - - 10.00 - 10.00
4 BLASTING ZONE INCLUDING
RATIONALISATION
AREA
10.00 - - 25.39 35.39
5 EMBANKMENT 15.00 - - - 15.00
6 COLONY 1.00
TOTAL 58.35 34.05 11.00 25.39 128.79
4.6.3 Plantation Programme:-
The job of plantation will be taken up from the revenue budget of the mine.
Proposed Width of Green Belt:-
a) Along the roads, 1000 saplings per km of road length in two rows on both sides of
the road creating 3.0 m wide green belt on either side.
b) Around colony and infrastructure @ 2500 saplings per ha in 3 rows of plantation all
around the available suitable spaces will be done keeping the width of green belt
as 5.0 m.
c) In vacant land, @ 2500 saplings per ha in 2 m X 3 m grid in order to develop green
patches.
Species to be Planted:- Native Species.
4.6.4 PROGRESSIVE & FINAL MINE CLOSURE PLAN
Mine closure plan.
Although, the mining activities may last a few decades, but they are liable to leave a
long lasting impacts on the landscape, ecology and on local inhabitants. The objective
of mine closure plan is aimed at restoration/reclamation of disturbed area, which should
be acceptable to local community as well as regulatory authority.
Mine closure is not something that happens at the end of a mine's life rather mine closure
is an ongoing series of activities starting from the planning stage of a mine and ending
with a suitably restored site that can be returned to the community. The mine closure is
planned in two phases:
a) The first phase/progressive site-specific closure plan includes the various activities to
be implemented over the life of the mine. The required timetable for these is given in
detail in the EMP/Project Report itself. The required fund – Capital and Revenue, is
also given under different heads in the EMP/Project Report.
b) This plan may undergo and incorporate changes depending upon the actual site
condition during implementation, legal & social requirements in future, availability of
additional coal reserves, etc. As such a detailed closure plan will be prepared
before the actual closure time of the mine. This plan is the culmination of the
activities given under progressive plan.
Major activities under mine closure plan
The mine closure plan includes the following major activities.
1.1 Environmental Aspects
1.2 Social Aspects
1.3 Safety & Technical Aspects
Environmental Aspects.
Reclamation of dumps.
During quarrying operation, OB is initially removed and kept as external dump. Coal
production starts once the coal seam is touched. Once the lowest and economically
mineable coal seam is exhausted, a void / decoaled area is created. The OB generated
from advancing benches is then backfilled in this decoaled area as an internal dump.
With the ongoing process of mining operation, the external dump and internal dump are
technically reclaimed.
Backfilling of Quarry Void:
It has been proposed to work the quarries by Horizontal Slicing Method i.e. conventional
benching system with shovel-dumper combination. This system is being widely used in the
opencast mines of Wardha Valley Coalfield. The backfilling of quarry void will start from
4th year of quarry operation.
The detailed break-up of overburden management are as follows:-
S.N. Head Overburden (Mm3)
1 External OB Dump 7.37
2 Internal Dumping 1.17
TOTAL 8.54
Post Mining Land Use Pattern:-
The post-mining land use pattern at Ghonsa Expansion OCP will be as follows:-
POST MINING SCENARIO (AREA FIGS IN ha)
SL. NO.
PARTICULARS PLANTATION VOID PUBLIC USE UNDISTURBED/ UNPLANTED
TOTAL
1 EXTERNAL OB DUMP
29.35 - - - 29.35
2 EXCAVATED AREA 4.00 34.05 - --- 38.05
3 INFRASTRUCTURE - - 10.00 - 10.00
4 BLASTING ZONE INCLUDING
RATIONALISATION
AREA
10.00 - - 25.39 35.39
5 EMBANKMENT 15.00 - - - 15.00
6 COLONY 1.00
TOTAL 58.35 34.05 11.00 25.39 128.79
Hydrogeological Considerations
The local drainage of the region is controlled by Vidharbha River. The discharge of the
mine water after treatment will first meet the local nullah and ultimately discharge into
Vidharbha River. The surface run-off from external OB dumps will be guided through
sedimentation ponds and garland drains to the surface watercourse. These structures will
remain even after the closure of the mine as it will prevent eroded material from
reaching the main drainage / watercourse of the region.
In the reclaimed area, the permeability of water is usually higher and receives about 40%
of rainfall as recharge. Due to this, the impact on rise side of the mine gets reduced and
with time and after cessation of mining it even improves the ground water system.
The final void provides access for future expansion of the mine.
Bio-diversity issues:
The reclaimed and afforested external dump covering 29.35 ha along with 80.00 ha of
backfilled area, 35 ha of embankment and 55.00 ha of plain land will be made into a
habitat for the fauna. This composite habitat for faunal spp based upon prey predator
relationships, after complete reclamation will support populations of insect, bird spp,
small herbivores and other predatory species dependent upon these spp, in the food
chain.
Social Aspects:
Mining operation has affected the families and landowners in the mine take area
directly. The project affected persons and families will be given adequate compensation
as per Company's norms.
Safety & Technical aspects
It includes demolition, dismantling, disposal & alternative use of surface structures like
workshops, power line foundations, offices, residential colonies etc.
Utilisation of existing surface infrastructure:
In this project, the surface structures will be utilized by the future extension of mine.
Management of Hazardous waste:
The waste oil and oil filters collected during routine maintenance of HEMMS comprise
hazardous material generated during the life of mine. These will be regularly collected
and auctioned to authorized recyclers and as such no hazardous material will be left at
site after the closure of the mine.
Management & Use of void:
The quarry void will provide access for the future extension of the mine.
Survey records & maps:
Survey records of working showing the infrastructures, last working position, dump etc. will
be maintained. A copy of the closure plan giving details of all the safety precautions
taken along with maps etc. will be submitted to the Directorate General of Mines Safety.
Fencing around void for mine closure:
At the time of final closure of mine a permanent fencing will be erected around the void
periphery. The physical details of the fencing are:
Height : 1.5 m
RCC Posts : 1.8 m high placed at 3 m apart.
Wire : Parallel lines & 2 cross lines of barbed wire.
Fund provision for mine closure:
For the effective closure of the mine, various activities are to be continued after the end
of mining operation viz. land reclamation, afforestation, protective boundary/fencing,
continuation of all monitoring programmes, control of all contaminated effluents,
securing of all petroleum products, chemicals & waste etc.
Conclusion:
It can be seen from the points mentioned above that the activities required for mine
closure are already covered in the EMP/PR of the mine. These activities are not a one-
time activity to be undertaken at the end of life of mine. Most of the activities are carried
out regularly over the total life span of the mine.
The project under consideration is in all likelihood get further extended towards dip which
will give an additional lease of life to the project. As such, the actual closure plan can be
finalized only at the end of expansion project.
Financial provisions as per the Ministry of Coal Guidelines dated 24/08/2009 for the
project under consideration within the limits specified has been made in the report to
undertake mine closure activities.
Note on creation of a Corpus Fund:
The purpose of a Corpus fund is to make available the required fund for the various
activities of mine closure at the time of actual closure of the mine. In Proposed Ghonsa
Expansion OC Project the fund required for various activities for mine closure has already
been provided in EMP/PR. These are provided in the approved PR of the project.
The fund provisions indicated above takes care of all the requirements of mine closure
and has the commitment of the highest authority of the Company.
Conclusion:
It can be seen from the points mentioned above that the activities required for mine
closure are already covered in the EMP/PR of the mine. These activities are not a one-
time activity to be undertaken at the end of life of mine. Most of the activities are carried
out regularly over the total life span of the mine.
The project under consideration is in all likelihood get further extended towards dip which
will give an additional lease of life to the project. As such, the actual closure plan can be
finalized only at the end of expansion project.
Although no statutory guidelines exist on financial provisioning for mine closure activities
as yet, but financial provisions as foreseen on date for the project under consideration
within the limits specified has been made in the report to undertake mine closure
activities.
4.7 Occupational Health Issues
WCL has full fledged medical set up in all areas to check up and monitor all the
occupational diseases endangering the health of its preciuos workforce. The periodical
medical examination for all workman is compulsory as per Statute.It is carried out once in
every five years for each and every worker and proper records are maintained and
submitted to Directorate General of Mines Safety as it is a statutory requirement.
In case of workers, above 50 years of age and employed in underground mine, this
periodical medical examination is carried out every two and half years interval. In
Pathakhera Area, under whose administrative control, the mine under consideration is
being worked is no exception. All the statutory obligations under the occupational
health are strictly followed.
Present set up of Occupational Health Services At WCL:
WCL is having occupational health committee at the corporate (HQ) level as well as at
the unit (Area /Project level).
At corporate level, the committee consists of the following: -
Chief General Manager (Safety)
Chief of Medical Services
Periodical Medical Examination (PME) Incharge of HQ.
The committee scrutinizes the report of the area every quarter.
At Unit level, the committee consists of the following: -
General Manager (Operations)
Area Medical Officer
Area Safety Officer
Periodical Medical Examination (PME) Incharge of Area.
The above committee takes the review at area level every month. There are 11 hospitals
having PME Centres in the hospitals. The PME Centres are well equipped with Spirometry
(Lung Function test), Audiometry (for testing hearing impairment) along with the facilities
for X – Ray & other bio – chemical tests.
The details are as follows: -
Periodical Medical Examination (PME) Centres – 11
(Occupational Health Centres)
Nos. of Doctors engaged in
Periodical Medical Examination - 11
Nos. of Doctors trained in
Periodical Medical Examination - 22
Nos. of X – Ray machines (300 mA) - 9
Nos. of X – Ray machines (500 mA) - 2
Nos. of ILO film Tests - 10
Nos. of Audiometer units - 7
(4 units are under process of procurement)
Nos. of Spirometer units - 8
(3 units are under process of procurement)
Nos. of Pathology Labs - 11
Nos. of X – Ray technicians - 14
Nos. of Laboratory Technicians - 22
All the PME Centres are fully computerised.
As per the Statute / Mines Act, 1952, all the workers are examined every five years and
the disease profile is maintained in PME Centres in different colour codes as given below:
-
Yellow Card – Hypertension
Green Card – Diabetes
Red Card - Ischaemic Heart Disease
Workers exposed to high decibel machineries i.e. more than 90 decibels and are found
to have developed hearing impairment, are subjected to repeated audiometric tests.
In suitable cases, as per the recommendation of the Apex Medical Board, the change of
job is also suggested and implemented accordingly.
In addition, the Welfare Board of WCL time to time makes visits to different area hospitals
& PME Centres so as take stock of the ground realities.
CHAPTER- V
ENVIRONMENTAL MONITORING PROGRAMME
5.0 ENVIRONMENTAL MONITORING –
The environmental monitoring programme will be carried out as per details given
below: -
S
N
Items Parameters Frequency No. of
Stations
1 Ambient
Air Quality
Monitoring
SPM, RPM, SO2,
Nox, CO & Fugitive
dust
Every Fortnight as per
EPA, Rule 2000
4
2 Water
Quality
Monitoring
1) 4 Parameters
viz. p H, Total
Suspended Solids
(TSS), Chemical
Oxygen Demand
(COD) & Oil and
Grease.
2) 35 Parameters
Every Fortnight
Once in a Year
2
3 Noise
Quality
Monitoring
Noise Levels Every Fortnight 2
4 Environme
ntal
Statement
Annual
5 Ground
Water
Level
Monitoring
& Quality
Water Level &
Quality
Parameters.
Water Level –
Quarterly.
Water Quality – Yearly.
In Buffer
Zone
Villages.
6 Complian
ce Report
of EC
Conditions
All conditions both
Specific & General
1st June &
1st December
Not
Applicabl
e
CHAPTER- VI
ADDITIONAL STUDIES
6.0 INTRODUCTION:
Mining is a hazardous industry. There is risk to life and property associated with various
mining and allied activities of the project. As such a detailed study has been carried out
covering identification and assessment of risk, and recommendation of measures to
prevent damage to life and property against such risks. They are discussed below.
6.1 PUBLIC CONSULTATION
As directed in the TOR, Public Consultation as per EIA Notification, 2006 has been
conducted by Maharashtra Pollution Control Board. For this purpose, Draft EIA/EMP
document as per the generic structure and with due compliance of all the conditions
issued in TOR dated 08.07.2009 (Copy enclosed as Annexure – I) was prepared and
submitted to Regional Officer, MPCB Regional Office, Nagpur.
The Public Hearing was conducted twice on 21.07.2010 and 22.12.2010 but in both
occasions PH could not be completed. The same was successfully completed on
09.08.2011. After conduction of Public Hearing by MPCB as per procedure laid down in
EIA Notification, 2006 and receipt of the recommendations from MPCB, this final EIA.EMP
has been prepared for submission to MOEF for obtaining EC. The detailed Minutes of
Meeting along with questions raised and replies given as received from MPCB, Nagpur is
attached herewith as Annexure – III.
The replies to the queries raised during the Public Hearing are already incorporated in
the said minutes and given below:-
S.N. COMMENTS / SUGGESTIONS OF
PARTICIPANTS WCL’s REPLY
1 Shri. Vijay Raju Jivane, Grampanchayat
Member, Ghonsa stated that at
present WCL authorities do not have
specific information about the names
of farmers and their family members
whose land is to be acquired for the
expansion project. WCL authorities
should explain in the public hearing
about the method adopted for land
acquisition. He stressed that
compensation for land should be given
according to market rates. He asked
about rehabilitation policy of Coal
India Ltd. He demanded for one
employment per 2 acre of land
acquired and the rate should be equal
Shri. Sachin Patil, (WCL) replied that land
is acquired under Land Acquisition Act or
Coal Bearing Act of Central Government.
Under this Act the cost of land is decided
by State Authority as per market value.
He further said that as per RR policy of
Coal India Ltd., employment is given to
the land looser having land of 2 acres or
above. In case of those who opted for
one time compensation in lieu of
employment, are given Rs. 5 lakhs per
acre of land.
to rate decided by State Government
plus additional Rs. 5 lakhs per acre. 2. Shri. Dilip Kakde, Zilha Parishad, stated
that the public hearing for this
expansion project was cancelled
before due to non-fulfillment of
commitments made by WCL authorities
and same commitments especially
about employments are still not fulfilled.
He complained that heavy dust
generation takes place due to mining
and transportation activities and water
sprinklers are not operated regularly.
He alleged that WCL authorities always
give their assurance for developmental
works but never fulfill it. He informed
that one handicap person Shri. Anil
Raut, whose land was acquired, is still
waiting for the employment since
many years.
He registered his oppose for the public
hearing and requested people to
support him. He stated that rainwater
will enter into Ghonsa village and thus
will affect the agricultural land of the
village. WCL authorities should give
assurance regarding this. He alleged
that coal carrying trucks were not
covered by tarpaulin which leads to
spillage of coal. The Air Quality
Monitoring Machine is not operated for
24 hours as per norms and appealed
that the air monitoring machine should
be operated at his house to know the
air quality. He further stated that
proceedings of the previous public
hearing were not made available to
Zilha Parishad. He alleged that mine
discharge water is released into river
without any treatment. He requested
Chairman for considering above issues
and not to give permission for
expansion of coalmine.
Shri. Ramteke (WCL) briefed the present
status of works done by WCL as
committed during the previous public
hearing. He stated that road from
Mukutban to Ghonsa is repaired and the
expenditure incurred for the same is Rs. 22
lakhs. A total compensation of Rs. 1.77
lakhs were paid to the affected farmers.
For controlling air pollution, new eight
water sprinklers are provided on internal
roads and are in operation.
He further stated that no overloading of
trucks is allowed from the coalmine. If
found, they have stopped and allowed
only after taking permitted load and that
too covered with tarpaulin. The rainwater
harvesting scheme was introduced into
nearby villages for conservation of water.
Total Rs. 40 lakhs was spent towards
developmental works in nearby villages
by WCL. Mine water is not being
discharged directly into river. Three
numbers of check dams has been
erected. A drain of 150 meter has been
cleaned and culvert has been erected
into river. Sedimentation tank is provided
for the removal of solids from mine
discharge.
3. Shri. Dilip Kakde stated that the
information given by WCL authorities is
not acceptable by them. The
untreated black water is released into
river due to which animals and people
are suffering. He alleged that video
recording can be done for one day.
Shri. Sachin Patil (WCL) replied that
proposal for giving employment to Shri.
Anil Daulat Raut has been forwarded to
the WCL Head Quarter as a special case.
Delay is taking place but Shri. Raut will
definitely get a job in WCL.
He demanded that Government
officials should verify whether WCL has
undertaken these works or not.
4. Shri. Kakde stated that CMD, WCL has
committed that Shri. Anil Raut will get
employment within 8 days, but till date
no employment has been given. He
asked that how long back . Raut was
acquired?
Shri. R.N. Panda (WCL) replied that there
is no provision for employment to
Handicapped person in WCL. However,
Shri. Raut will be given employment as a
special case.
Chairman Shri. Rajendra Deshmukh
stated that if the . Raut was acquired,
he is entitled for the employment in
WCL. Hence, he should get the
employment as early as possible.
5. Shri. Vasudev Vidhate stated that WCL
authority always give formal replies to
the questions asked during public
hearing. They should give specific
answers to the questions. There is policy
of Central and State Government
regarding employment to
handicapped persons and since WCL is
in , they should follow the said policy.
Throughout the country, there is
reservation to the handicapped
persons for employment. On the day
WCL acquired. Raut, he became
eligible for the employment in WCL. His
income source i.e. land was taken
away from him and employment is not
provided. He requested Chairman to
instruct WCL authority to act on this
issue of employment to Shri. Raut first
and then conduct the public hearing.
Shri. Sharma (WCL) replied that CMD,
WCL has already taken note of this case.
6. Shri. Vidhate objected that WCL
authority is not giving proper answer.
He demanded reply from responsible
officer who have authority for taking
decision in this regard.
Chairman Shri. Deshmukh stated that
although this issue is not related with
environment, it is concerned with
livelihood of people and can’t be
neglected. He directed Shri. H.S. Khare,
CGM, WCL, Wani North Area to reply
this issue.
Shri. H.S. Khare (CGM) replied that in this
case land compensation has been given
and if the person is physically not fit for
employment, monitory compensation
can be given. Shri. Raut refused to
accept the monitory compensation. He
informed that proposal of employment to
Shri. Raut has been forwarded to HQ with
strong recommendation and CMD has
committed to give him employment. He
assured that Shri. Raut will get
employment.
Shri. Kakde stated that CMD assured
before six months that Shri. Raut will get
employment within 8 days. He asked
that there is provision of employment to
physically handicapped persons in
State and Central Government
polieies, then how WCL authorities can
deny the proposal of Shri. Raut.
7. Shri. Kakde alleged that the road is not
completely repaired. Although, WCL
authorities are claiming that Rs. 22 lakhs
have been spent on repairing of the
roads, all ditches were not filled.
Chairman Shri. Deshmukh instructed
WCL authorities not to give false
assurance and information. He further
instructed to initiate concrete actions
like water sprinklers on road edges
should be in working condition and
operated regularly. Funds allotted for
specific works should be utilized
properly.
Shri. Ramteke (WCL) replied that as water
pump was stolen, due to which water
sprinkling was affected and assured the
regular water sprinkling on the roads.
8. Shri. Vasudev Vidhate alleged that
MPCB do not have right to conduct
public hearing, because public hearing
should be conducted within 45 days
from receipt of application and MPCB
is failed on this ground and thus new
agency has to conduct the public
hearing.He further stated that if people
want to lodge complaint against such
issues, they have to go to , because
National Green Tribunal is located
there. He requested that a Bench of
National Green Tribunal should be
made available at for peoples ease.
He further said that there are about 45
(existing and proposed) mines in this
region. When any land acquisition is
proposed for any mine or industry, it
should be discussed in detail with land
owners (i.e. farmers) of that area giving
them detailed information in respect of
lease of land. The land owners should
be taken into confidence before land
acquisition. Further, dump is not
allowed to dump within 500 meters
from the river bank or road.
Shri. N.G. Nihul, Regional Officer, MPCB,
Chandrapur stated that generally such
things didn’t happen. But still people can
send their say in this regard to Ministry of
Environment & Forest, if anybody’s written
objection is not reflected in the minutes.
He stated that EIA report published in
English and Environmental issues
mentioned in it are not understood by
the people. He demanded that under
such situation, one facilitator should be
appointed either by Government or by
industry to provide information
mentioned in EIA report to the people.
He stated that notice for public hearing
is being published in newspapers by
MPCB with an appeal to people for
submitting views, questions, objections
etc. regarding the proposed project
and accordingly he had submitted his
letter during previous public hearing to
the Chairman. However, the details of
same letter were not mentioned in the
proceedings of that public hearing by
MPCB. He informed that the said
project will get Environmental
Clearance by MoEF. He stated that
due to such issues people didn’t have
faith in MPCB.
9. Shri. Dinkar Pawde, President, Wani
Town BJP stated that due to this project
about 21 villages are getting affected.
There is already issue of increase in air
and water pollution. He informed that
residents of Kumbharkhani village are
present. Chairman and members of
public hearing panel can ask these
people whether they are getting justice
or not.
He stated that WCL is getting benefited
by Rs. 2100 crores and State
Government is benefited by Rs. 700
crores from this project. Four more
projects are coming in this area in
future, due to which company will be
benefited by Rs. 5000 crores. Thus, he
demanded that WCL should spend at
least Rs. 6 crores for pollution control
and environmental protection.
He further stated that local WCL
officers are favorable for the
development of villages and pollution
control and are co-operative with the
villagers, whereas officers of HQ of WCL
do not co-operate with the people. He
gave an example that WCL authorities
send the proposal of repairing of Wani
Shri. R.N. Panda, Project Officer, GOCP
(WCL) replied that WCL authorities had
already committed in Gramsabha that
there will be no damage to the houses as
will conduct controlled blasting. Still if
some damages are observed then the
proper action will be initiated for
controlling the effects of blasting.
Shri. H.S. Khare, CGM, WNA (WCL) replied
that there is provision of closing of blast
area by net, which will be implemented.
– Ghonsa road to HQ people’s
demand, whereas it was refused by
their Head Office. He further said that
WCL authorities assured us for use of
low power explosives blasting. Still the
houses in Kumbharkhani village got
cracks in the walls due to vibrations.
10.
Shri. Pawde informed that the Divisional
Commissioner conducted meeting at
Wani and instructed that the work of
Wani – Ghonsa road should be
undertaken collectively by WCL, coal
washeries of this region and concerned
Government authority. He demanded
urgent attention towards this issue
because this work is not yet started.
Shri. Pawde stated that due to blasting,
cracks are taking place to the houses.
In such situation it is difficult to live in
village. He said that nearly 50 lakhs
tone coal is being transported from
Wani Taluka every year to other power
projects of . People are interested in
giving land for the projects because
they are becoming wealthy. He
demanded price of Rs. 15 lakhs per
acre of land and demanded
compensation against the damages
occurred due to blasting in
Kumbharkhani and other villages.
Shri. Ramteke (WCL) replied that Divisional
Commissioner, had conducted the
meeting in this regard with authorities of
WCL, PWD & MPCB. During the said
meeting, Hon’ble Commissioner directed
that Mukutban – Ghonsa road will be
constructed for long life. This work will be
done under PPP model and PWD will
make the work plan and will take initiative
for this work as it is the Government body.
Shri. Ramteke informed that WCL didn’t
receive any letter from PWD in this regard.
Shri. R.N. Panda (WCL) replied that he will
assess the details about damages
occurred due to blasting and will initiate
proper action in this regard at the earliest.
He informed that WCL authorities are
waiting for the proposal from PWD
regarding construction of road.
11. Smt. Manda Chiwane, Sarpanch,
Grampanchayat, Borda stated that
Borda village has not received any
fund. The village does not have basic
facilities like drinking water and road.
Drinking water is contaminated with
minerals.
Shri. Ramteke (WCL) replied that due to
encroachments adequate land for
construction of road is not available in the
village. Water table is at low level in the
village. He informed that work of
submersible pump / tube well is awarded
and soon will be completed.
12. Shri. Ganesh Paigan, Deputy Sarpanch,
Borda said that clearing of
encroachment is internal matter of
village administration and it will be
cleared once the work starts. He
added that several times villagers had
submitted letter for tube well. But, no
fund has been provided for the same.
Shri. Bhalla, Deputy GM (Civil), WNA
(WCL) stated that for tarring, work order
has been already issued & work will start
as soon as the encroachment is removed.
Shri. Ramteke (WCL) stated that machines
for the construction work of road are not
able to go on site due to limited space.
On which, Chairman Shri. Deshmukh
stated that this work can be done
manually also without using heavy
machines.
13. Shri. Mendale stated that WCL should
make proper arrangement for drinking
water. He demanded for provision of
tube well in the village.
Shri. R.N. Panda (WCL) replied that
submersible pump will be installed this
year. Provision will be made for this from
the CSR fund.
14. Shri. Vasudev Vidhate demanded
justifiable reply regarding blasting and
safety zone from the persons who
prepared draft EIA. He said that this
project is adjoining to the Rasa village,
Ghonsa village and . Thus these two
villages and river are prone to the
damages due to blasting.
Chairman Shri. Deshmukh instructed
WCL authorities to explain details of
safety zone.
Shri. Sachin Patil (WCL) stated that safety
zone is of 500 meters from mine boundary.
15. Shri. Vidhate stated that OB dump is at
10 meters away from Zilha Parishad
School, which should be 500 meter
away i.e. out side the safety zone. Thus
the mining Act is violated. If the project
commences, there is danger to the life
of people of this region. He stated that
plan should be made in such way that
water should not enter into village
even if the flow of river is changed. He
asked that whether the rules regarding
embankment, which are going to lay,
will be followed or not.
Shri. Sachin Patil (WCL) stated that mine
plan is approved from DGMS and 500
meter distance is mandatory. He stated
that strict compliance of these criteria is
observed. He further said that the
embankment will be made according to
rules of DGMS.
16. Shri. N.G. Nihul, R.O., MPCB asked that
whether all work is being undertaken
according to rules / permission of
DGMS or not.
Shri. H.S. Khare, CGM, WNA (WCL) replied
that under Mines Act, work is being done
as per DGMS permission. If DGMS
authorities desires, they can impose
specific conditions.
17. Shri. Vidhate objected on mine plan
submitted by WCL officers and
questioned that how to know whether
this plan is correct or not. If the plan is
incorrect and mine work start as per
the incorrect plan, it may cause threat
and damage to people and
environment. So actual details
regarding specific area defined for
mining, roads, agricultural land, houses
etc. should be shown in the plan and
Shri. Sachin Patil (WCL) stated that DGMS
gives permission only after taking all the
things into consideration, which are
shown on the CMPDI plan.
made available to the people.
18. Shri. Vidhate asked to show road on
the mining plan.
Shri. R.N. Panda (WCL) showed the details
in the map and he stated that public
road is parallel to the mine boundary.
19. Shri. Vidhate asked for post monitoring
reports should be made available to
Grampanchayats by MPCB. He asked
that whether road and mine boundary
will be merged after the commissioning
of mine. He said that distance of school
from Ghonsa mine is mere 10 meters.
Shri. R.P. Singh (WCL) stated that the mine
boundary cannot be changed without
the permission of DGMS.
Shri. R.N. Panda (WCL) stated that
Ghonsa village is at a distance of 600
meter from mining area.
Shri. Meshram, Deputy Sarpanch,
Sonegaon demanded for proper
arrangement regarding drinking water
supply from WCL. He said that
Sonegaon village is located on the
bank of river, due to which village is
under threat of flood. He added that
Grampanchayat already sent proposal
for school & passenger shed to WCL.
But, response is not received from WCL.
He alleged that students of
Kumbharkhani village can’t go to
school because Kumbharkhani –
Ghonsa road is closed, due to which
villagers face lot of problems.
Chairman Shri. Deshmukh stated that
WCL authorities should provide proper
road to the villagers and instructed to
do this work at the earliest. He directed
Shri. Khare (WCL) to give time bound
commitment regarding this.
Shri. H.S. Khare (WCL) stated that
previously there was kachha road and 20
meter wide road was developed. He
committed that the repairing of road will
be undertaken within 3 weeks period.
6.2 INUNDATION
Vidharbha river is flowing in the dip side of the project and quarry area is under HFL
hence there is possibility of danger of innundation from surface water. However,
necessary embankment 6 m above HFL (237.15 m) of the river has been proposed and its
alignment is shown in Quarry & Surface Layout Plan around the three Quarries. The
financial provision of pitching of embankment has been kept in Appendix A.8.1.
Suitable diversion of nallah flowing over the property has also been proposed.
DUST SUPPRESSION
For suppression of dust hiring charges for water sprinkling has been included in the
RPR. Suppression of mine dust may be done by using package bond & dust bond,
for methodology of application DGMS Circular No.8 of 1997 may be referred.
FIRE AND SPONTANEOUS HEATING
(1) Wild or herbaccous plants shall be removed from the mine.
(2) No person shall deposit heated material or ashes on any opencast working. Also no
person shall light a fire or permit a fire to be lighted in any OC working except by the
permission in writing of the Manager and only for a special purpose specified therein.
(3) No coal shall be left exposed more than its incubation period to avoid fire in
seam due to spontaneous heating.
SLOPE STABILITY
It is suggested that following action may be taken to deal with slope stability problem.
i) Vulnerable area may be identified and marked on quarry plan.
ii) Observation of actual alignment of fault plans, its throw, joints, etc. may be recorded
during the process of exploitation.
iii) Water drainage system may be properly implemented.
iv) Regular monitoring of tension cracks, horizontal and vertical movement of strata in
critical area may be done.
HAUL ROAD MAINTENANCE
Haul road would be prepared & maintained by Hiring agency as per the existing
guidelines.
BLASTING
Special precautions has to be taken while performing blasting operations near Kumbhar
khani village, State highway No. 233 and Rasa Kumbhar khani road.
CONSERVATION OF COAL
Optimum exploitation of coal has to be done by controlled blasting method near
Kumbharkhani village without shifting the village. Quarry limits are finalised in such a
way to exploit maximum possible coal without rehabilitation of adopting adequate
safety distance from said villages. Although for calculation of mineable coal reserves
10% mining losses has been taken into account, but in practice all efforts would be
made to minimise the losses. Separate excavator is provided for mining coal. OB
benches would be kept sufficiently advanced to avoid mixing of coal & OB. Maximum
backfilling is proposed in mine.
Surface dumps are planned upto a maximum height of 45 m considering availability of
non coal bearing area and lithology of OB material. The height of dump may be
increased after scientific study to reduce requirement of land for OB dumping.
SCIENTIFIC STUDIES
Provision for scientific studies regarding Slope stability & Hydro-geological study have
been made in this PR
ADDITIONAL PERMISSION / RELAXATIONS REQUIRED FROM DGMS
SAFETY ASPECTS FOR OUTSOURCING/HIRING OF HEMM (TOTAL HIRING & PARTIAL
HIRING OPTION)
Special precaution should be taken while employing contractual labours in the mine.
Before employing them to the mine proper vocational training should be imparted and
recommendations of VIII Safety Conference should be strictly followed. Terms and
conditions shall be fixed by management for deployment of contractual labours as well
as machineries. Some of the major aspects are as follows :
A) For persons :
i) Records in Form-B & Form-E shall be maintained.
ii) Records of VTC driving licence of operators shall be kept by Operators and readily
available for inspection by management
iii) Salaries shall be distributed in front of management representative
iv) No person shall be employed unless person holds VTC certificate and Management is
informed.
v) Adequate supervision shall be maintained by competent person.
B) For Machineries :
i) All the machineries to be deployed in mines should be passed by the management.
ii) RTO certificate photo copies of all vehicles shall be submitted to management.
iii) Daily welding, ,monitoring, inspection shall be done by contractor's mechanic as
directed by management.
iv) Machine manufacturers should be asked to give risk analysis.
C) General :
i) No person/vehicle shall be deployed at any place other than authorised place.
ii) All employees of contractors should obey lawful instruction of mine management.
iii) Risk Management Plan by contractor of tipper/pay loader
iv) Trained Manpower
v) Restricted traffic & traffic control planning.
OTHER MEASURES:
Other measures have also been recommended for avoiding risk in mine operation. They
are discussed below;
(A) Provision of proper illumination in quarry, O.B. dumps area, along roads, in workshop
& other work area.
(B) Communication system - Efficient communication system (based on VHF system)
have been provided for the project. This will allow proper communication link between
various work centers and helps in avoiding accidents.
(C) Maintenance facilities - The project will employ a large number of HEMMs for
quarrying and transportation of local and OB. Ill - maintained HEMMs may prove to be
the source of grave risk. A well-equipped workshop will be provided for scheduled
maintenance of HEMMs to avoid their failures.
(D) Training - Coal industry has set up a number of training institutes for imparting training
to its employees. These training raise the safety awareness among workers and train
them to carry out their assignments safely.
(E) Medical aid - The project has provided for well equipped hospital and qualified
doctors. They can attend to medical emergencies arising out of accidents.
CONCLUSIONS:
Following conclusions may be drawn from the above discussion:
(a) Coal mining is associated with a number of hazards.
(b) These hazards can be identified and assessed, which has been done for this project.
(c) Preventive measures against identified risks have been provided in this report
(d) With adoption of such protective measures, the operation of the mine would be safe.
6.3 IMPACT ON SOCIO-ECONOMIC
The activities listed under the two phases of this proposed project are likely to affect the
environment to varying degrees. The environment is a very complex system and so many
factors are interlinked and interdependent of each other, that any prediction
concerning the impact on the environment as a whole may not always be very precise.
So relevant aspects of environment are isolated as parameters and the impact due to
various activities on the parameters has been identified as project activities.
6.3.1 Socio-economic Impact
A) Population Growth and Migration
The opening of this project will be having an impact on the people inhabiting
surrounding the project area. There will be migration of people from outside due to more
job opportunities in the project area. Thus, the population in this area is likely to increase.
B) Resettlement & Rehabilitation.
There is no village falling over the core zone of the project. As such, there is no
resettlement of house oustees involved in this project.
C) Transport and Communication
The provision of metalled approach road to the place of work and other places of public
interests like shopping, education, medical services etc. is going to improve the existing
transport & communication network.
D) Health
At present, Wani North Area is having a full-fledged Regional Hospital. All the medical
emergencies are attended by the medical professionals of this hospital. In case of major
problems, the matter is generally referred to Chandrapur which is only 36 Kms away. As
such, in the Buffer Zone, health care facilities can be taken as satisfactory. With the
opening of this project, the facilities created in the project are likely to be extended for
neighboring population also.
The occupational health hazard associated with coal mining is the Coal Miners’ Lung
Disease (Pneumoconiosis). The disease is caused by the prolonged inhalation of coal
dust particles below 3 Micron size. The disease is detected by Chest X-Rays done during
periodical medical examination among the coal mine workers. However, this disease
has been detected among the underground mine workers only. As such, this
occupational disease is not expected to affect the workers of the proposed opencast
project.
E) Literacy
With the development of this project, educational facilities will get a boost and facilities
developed in the surrounding of the project area are going to improve further which in
turn will improve the literacy of the rural areas also around this project.
F) Economic Impacts
Most of the people are non-workers. Remaining is engaged in Cultivation and
Agriculture. With the opening of the project the occupational structure of the area is
going to change further and many people are likely to be involved in the job of mining
and allied activities. Hence, income level of these people is likely to improve to
significant level.
Employment opportunities and Quality of life
Employment opportunities both direct & indirect in this project are likely to cause
migration from outside. Amenities like medical educational, recreational etc. will be
available to local people and their quality of life will definitely improve.
Land House Oustees & House Oustees
The provision of land in the approved PR in South quarry was only 129 ha. Till date 128.79
ha land has been acquired for South quarry. There is no house oustees involved in this
project.
STATUS OF LAND ACQUISITION
128.79 ha land has already been acquired for South quarry, which is now being worked
and the present proposal for expansion in production capacity is envisaged within this
acquired land only.
COMPENSATION & REHABILITATION
Till date, out of 69 land holdings, 55 have been provided with employment and 3 have
been given Moetary Compensation in lieu of Employment.
SOCIO-ECONOMIC MEASURES
Peripheral development:
As per the present practices in WCL coal mines, adequate steps are being taken for the
local villagers by providing various infrastructure and welfare facilities and giving
assistance in health care in Wani North Area of WCL, under which the proposed Ghonsa
Expansion OC project will come into operation.
The various development works like construction of Primary, School, Post office, Shopping
center, diversion of cart track for villagers, establishment of bank, diversion of irrigation
canal etc; have been completed, mainly for catering to the needs/socio-economic
upliftment of the neighbouring population.
It may be seen that the eco-development measures including welfare measures are
regularly undertaken and, in future, the welfare measures will continue to be taken
based on the assessment of the "felt needs" of the community around the project.
Development works done in nearby villages under different schemes of WCL
Year Works Done Amount
(Rs. Lakhs)
Scheme
2004-05 Construction of Bus shelter, toilet and Hand pump
at Ghonsa village
2.54 SC/ST works
2005-06 Construction of stage for Adarsh High School at
Ghonsa village
1.98 CSR works
2006-07 Construction of two rooms for school building and
Hand pump at Dahegaon village
4.29 CSR works
Construction of concrete road (Internal village
road) in Dahegaon village
4.71 CSR works
Construction of concrete road (Internal village
road) in Mohurli village
1.19 CSR works
2007-08 Making concrete pavement for internal road at
Rasa village
2.18 CSR works
Making concrete pavement for internal road at
Mohurli village
2.40 CSR works
Making concrete pavement for internal road at
Ghonsa village
3.07 CSR works
Making concrete pavement for internal road at
Sonegaon village
2.50 SC/ST works
2008-09 Construction of concrete road (Internal village
road) at Rasa village
3.00 CSR works
Construction of concrete road (Internal village
road) at Borda village
2.00 CSR works
Making concrete pavement for internal road at
Kumbharkhani village
3.00 SC/ST works
2009-10 Internal concrete road at Suknegaon village 2.05 CSR works
Internal concrete road at Ghonsa village 2.10 CSR works
Internal concrete road at Kumbharkhani village 2.20 CSR works
Road side drain at Kumbharkhani village 0.93 CSR works
Internal concrete road at Ejasari village 2.02 SC/ST works
Internal concrete road at Kumbharkhani village 1.98 SC/ST works
2010-11 Concrete road at Ghonsa market 4.00 CSR works
Making concrete pavement for internal road at
Sonegaon village
3.00 CSR works
WBM road at Borda village 3.00 CSR works
Community hall at Ijasan village 3.00 CSR works
One no. hand pump at Ghonsa village 0.60 CSR works
One no. hand pump at Sonegaon village 0.55 CSR works
2 nos. hand pump at Kumbharkhani village 1.20 CSR works
Distribution of School Bags at Rasa, Kumbharkhani
& Ghonsa village
0.42 CSR works
Arrangement of Health Camp & distribution of
Blanket at Rasa village
0.40 CSR works
Total 60.31
Year Works Amount
(Rs. Lakhs)
Scheme
2011-12 WBM road at Rasa village 3.00 CSR works
WBM road at Kumbharkhani village 3.00 CSR works
Supply of 10 nos. Solar Light at Ghonsa village 1.55 CSR works
Sanctioned
in 2010-11
Supply of Tree guard at Rasa village 1.73 CSR works
2011-12 Construction of cement concrete road at
Ghonsa village
3.00 CSR works
Supply of Tree guard at Ghonsa village 1.75 CSR works
Construction of borewell with submersible pump
at at Rasa village
6.50 CSR works
Construction of cement concrete road at Rasa
village
3.00 CSR works
Approach road from Rasa to Gotegaon village 6.00 CSR works
Construction of cement concrete road at
Kumbharkhani village
3.00 CSR works
Construction of underground drain at
Kumbharkhani village
2.50 CSR works
2 nos tubewell with submersible pump at
Kumbharkhani village
8.00 CSR works
Construction of tubewell with hand pumps at
Dahegaon village
0.70 CSR works
Construction of concrete road at Dahegaon
village
3.50 CSR works
Construction of concrete road at Sakra village 3.50 CSR works
Construction of community centre at Sakra
village
8.00 CSR works
Construction of concrete road at Sonegaon
village
4.00 CSR works
One no hand pump at Sonegaon village 0.70 CSR works
Construction of concrete road at Maregaon
(Korombi) village
3.50 CSR works
Arrangement of inter village volleyball
tournament at Ghonsa village
Total 66.93
CHAPTER – VII
PROJECT BENEFITS
7.0 PROJECT BENEFITS
The benefits of the project can be summarized as below:-
- The physical infrastructure in the area has already been improved substantially by
following ways:-
Development of road thereby improving the communication.
Improvement in Power, Telephone (including Mobile) facility.
Improvement in Health Care facility & Educational facility.
Improvement in Market / Trade & Business.
- The social infrastructure by way of cultural mixing of people of other states with local
community glorifying “UNITY IN DIVERSITY”.
- Substantial employment in the project & indirect employment for business & trading,
contractor, transportation, vehicle contractor, nursery development.
CHAPTER - VIII
ENVIRONMENTAL COST – BENEFIT ANALYSIS
Ministry of Environment & Forests while issuing TOR has not specifically indicated for
carrying out “Cost Benefit” Analysis, hence the same has not been carried out.
CHAPTER - IX
ENVIRONMENT MANAGEMENT PLAN
9.0 GENERAL
Close monitoring of the environment and implementation of various protective measures
discussed in the report forms an important part of EMP. In the earlier chapters the causes
of various pollutions along with the preventive and mitigating measures have been
discussed. In this chapter description of the administrative aspects of ensuring that
mitigative measures are implemented and their effectiveness monitored, after approval
of the EIA is being discussed.
9.1 MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of the
various measures suggested, a multi-disciplinary approach is essential.
(a) WCL headquarter acts as an apex body which supervises the activities relating to
environment at project level through the General Manager.
(b) Chief General Manager of the area coordinates the activities of various disciplines in
the area to render all necessary assistance at the implementing level i.e. the Project.
Area Nodal Officer (Environment) monitors all aspects of environment on behalf of the
General Manager. He also takes suitable steps for generation of environment data
along with its analysis and interpretations.
As far as plantation is concerned horticulturist with suitable backup staff shall be
provided in the area for undertaking the plantation jobs including raising of a nursery.
Plantation will have to be done on a large area. Therefore, it may be desired that an
outside agency may have to be employed for this purpose. The horticulturist along with
the supervisor shall only monitor and guide the agency for selection of site, treatment of
soil, selection of species etc.
(c) Sub Area Manager is responsible for mechanical reclamation of the area. He is also
responsible for biological reclamation with the assistance of CGM's office.
ORGANISATION FOR ENVIRONMENT MANAGEMENT
SN Measures/Actions Agency
1. Environmental Control 1 Chief General Manager, Wani North Area
2 Nodal Officer, (Environment), Wani North
Area
3 Sub Area Manager, Ghonsa Expansion OC.
4 Staff Officer (Civil), Wani North Area
5 Environmental Cell (WCL H.Q.)
2. Environmental
Monitoring
1 Chief General Manager, Wani North Area
2 Staff Officer (Civil), Wani North Area
3 Nodal Officer (Environment), Wani North
Area
4 Sub Area Manager, Ghonsa Expn. OC
5 Environment Cell of WCL Headquarters
6 Environmental Laboratory of CMPDI, RI-IV
3. Reclamation 1 Sub Area Manager, Ghonsa Expansion OC
2 Nodal Officer (Environment), Wani North
Area
3 Environmental Supervisor
4 Horticulturist
CHAPTER-X
DISCLOSURE OF CONSULTANTS ENGAGED
10.1 Name of Consultant
Central Mine Planning & Design Institute Limited. Briefly, it is called as ‘CMPDI’. It is an ISO
9001 Company.
Its registered corporate office is situated at Gondwana Place, Kanke Road, Ranchi –
834008, a capital city of Jharkhand State. It operates through seven strategically located
Regional Institutes over six states territories of India. Details of all seven Institutes including
its corporate office are given as in Table-10.1.
Table-10.1
SN Offices Addresses Tel/Fax
Postal E-Mail Website
1 Corporate Gondwan
a Place,
Kanke
Road,
Ranchi-
834008,
Jharkhand
c.in,
cmpdihq@cmp
di.co.in
http://www
.cmpdi.co.i
n
+916512230483,22301
16 /+916512231447,
2232249
2 Regional
Institute-I
West End,
GT Road,
asansole –
713301,
West
Bengal
- - +913412253504/
+913412250935
3 Regional
Institute-II
Koyla
Bhawan,
Koyla
Nagar,
Dhanbad-
826005,
Jharkhand
+913262230850,22307
89/ +913262265575
4 Regional
Institute-III
Gondwan
a Place,
Kanke
Road,
Ranchi-
834008,
Jharkhand
+916512231506/
+916512231501
5 Regional
Institute-IV
Kasturba
Nagar,
Jaripatka-
440014
http://www
.cmpdi.co.i
n
+917122642134/
+917122643231
6 Regional
Institute- V
SECL
Complex,
Seepat
Road,
Bilaspur,
Chhatisgar
h.
+917752246482/
+917752246481
7 Regional
Institute-VI
CWS
Colony,
P.O.
Jayant
Colliery,
Sidhi-
486890,
M.P.
+917805222329,
222172/
+917805222330
8 Regional
Institute-VII
Griha
Nirman
Bhawan,
Sachiwala
ya Marg,
Unit 3,
Bhubanesh
war-
751001,
Orissa
+916742394357,
2394760/
+916742395128
All the above Regional Institutes are dedicated to render services to seven subsidiaries of
the CIL AS follows:
Table-10.2
Sl. No. Institutes Dedicated to
1 Regional Institute-I Eastern Coalfields Ltd. (ECL)
2 Regional Institute-II Bharat Coking Coal Ltd. (BCCL)
3 Regional Institute-III Central Coalfields Ltd. (CCL)
4 Regional Institute-IV Western Coalfields Ltd. (WCL)
5 Regional Institute-V South Eastern Coalfields Ltd. (SECL)
6 Regional Institute-VI Northern Coalfields Ltd. (NCL)
7 Regional Institute-VII Mahanadi Coalfields Ltd. (MCL)
Hqrs. Ranchi is committed to render services to NEC & Non-CIL clients and specialized
assignments for both CIL & Non-CIL clients.
10.2 Brief Resume of the Consultants:
10.2.1 Establishment Background:
The company was formerly known as Coal Mines Authority Limited. And, the Central Mine
Planning & Design Institute Limited (herein after called as CMPDI) is a planning & design
division of Coal India Limited (herein after called as CIL) as per Memorandum of
Association of the company. The CIL is a holding company since November 01, 1975,
and the CMPDIL is one of its subsidiaries since then. It is under Ministry of Coal,
Government of India.
10.2.2 Strength & Resources
a) Manpower:
CMPDI has more than 800 multidisciplinary technical executive professionals who
combine innovation and initiative to deliver faster and effective solutions in planning,
implementation and management of projects.
b) Resources:
CMPDI is equipped with modern laboratory facilities for undertaking various analytical
works to supplement its services. It has well equipped network of six environmental
laboratories located in various coalfields to regularly monitor air, water and noise
parameters. The central unit at Ranchi is accredited with Central Pollution Board, New
Delhi. Besides its own strength, CMPDI has access to the vast resources with its principal,
CIL, India’s largest coal producer and a Nava Ratan Company.
10.2.3 Recognition:
CMPDI is recognized as preferred consultant by India and overseas clients, United Nation
agencies and international financial institutions and the company is registered with
World Bank
Asian Development Bank
African Development Bank
United Nations Development Programme
10.2.4 Main Functional Area:
The main functional area of the CMPDI is to provide adequate and up-to-date planning,
design and technological supports to the CIL and its coal producing subsidiaries to
enable them to produce the planned quantity of coal efficiently and economically with
due attention to safety, conservation, quality and environment. In addition to these,
CMPDI also provides necessary consultancy for clients outside the CIL in India and
abroad. The Quality Management System of CMPDI, Ranchi is certified under
international standard – ISO-2000 by BVQI (UK). Services covered under are as follows:
Consultancy in Mineral Exploration and Environmental Management.
Planning & Design in Mining, Civil & Architectural Engineering, Coal Preparation &
Utilization, Electrical & Mechanical Engineering, Mining Electronics, Geomatics
and Mine Construction.
Laboratory testing facilities for the above
Technical & Management Training in Mineral & Mining Sector
10.3 Nature of consultancy rendered:
CMPDI has been offering services in the fields enumerated in Table – 10.3
Table – 10.3
Sl. No. Services Offered
1 Exploration & Resource Evaluation
2 Mine Planning & Design Services
3 Infrastructures Engineering
4 Environmental Services
5 Beneficiation Services
6 Management Services
7 Specialized Services
8 Laboratory Services
9 ITC in Mining
10 Research & Development
10.3.1 Exploration & Resource Evaluation:
New generation exploration technology coupled with skilled manpower has made
CMPDI a twenty first century leader in mineral exploration, deposit modeling, resource
evaluation, resource management, mining geology, hydro-geological & geophysical
studies, engineering, geological investigations etc. Services rendered under this head are
described in brief in Table-12.3.1 hereinafter.
Table-10.3.1
Sl.No. Sub-heads of
Services
Services Rendered in
1 Geological
Support for
mining
Production support or mine development drilling and
prediction of faults and pinch / wash outs.
Delineation of roof / floor and dirt bands
2 Drilling Coring-Diamond rotary drills up to a capacity of 1280
m depth
Non-coring-Direct rotary and DTH drills for geophysical
logging, hydro-geological investigations, dewatering,
etc.
3 Deposit
modeling
Using geo-statistical and geological software packages
including MINEX and in-house developed CEMPGEODOC
and SASLINT software
4 Resource
Evaluation
Deposits of coal, lignite, manganese, iron ore (magnetite
and hematite), phosphorite, coal bed methane etc.
5 Resource
Management
Strategic planning for future exploration depending
upon market demand.
Updating of reserve / resource of individual blocks or
coalfields.
6 Hydro-
geological
studies
Systematic ground water investigations.
Mining hydro-geological studies
7 Geo-
engineering
works
Determination of strength properties of rocks and coal and
RQD (Rock Quality Designation) to assess strength
characteristics of strata
8 Master
planning for
assessment of
resource
potential with
respect to
CBM, globally
an emerging
environment
friendly
alternate
energy
source.
Creation of data packages of potential CBM blocks.
Resource evaluation of CBM / CMM / AMM.
Formulation of policy guidelines for harnessing CBM
resources.
Implementation of CIL-ONGC Consortium’s venture in
developing CBM in coalfields.
To provide quality services, CMPDI is effectively utilizing technology like remote sensing,
combination drilling (coring and non-coring), multi-probe geophysical borehole logging,
seismic refraction survey etc.
CMPDI has already undertaken over 500 integrated exploration projects in varying
geological and terrain conditions.
10.3.2 Mine Planning & Design Services:
CMPDI is a premier consultant in open pit and underground mine planning & design in
coal, lignite and other minerals. It has prepared more than 950 mining project reports
with individual capacity up to 35 Million ton per annum. CMPDI uses advance software
like MINEX for resource modeling; mine planning and scheduling of open cast and
underground mine projects. It has helped its subsidiaries to achieve unprecedented
growth from open cast mines in their organizations. Its experience in mechanized
underground mining technology spans exploitation of coal seams from 1.00 m to 20 m
thickness, at different gradients from flat to 750, with soft to extremely hard coal, liable to
spontaneous heating and gassiness and under varying roof strata conditions. Services
offered to be manifold and are enumerated briefly in Table-12.3.2.
Table-10.3.2
Sl. No. Services Offered
1 Master planning of coalfield
2 Perspective planning
3 Conceptual engineering studies
4 Techno-economic feasibility studies
5 Detailed project reports
6 Detailed engineering with working drawings
7 Mine ventilation & transport planning
8 Operational planning
9 Mining plans for mining lease
10 Mine capacity assessment
11 Performance analysis of equipment
12 Prediction of surface subsidence through numerical
modeling software
13 Geophysical logging, Seismic survey, Resistivity Survey.
10.3.3 Infrastructure Engineering:
CMPDI provides engineering logistic or support services for development of infrastructure.
It has developed multi-disciplinary engineering skills for implementing projects of various
complexities. In particular, it has offered complete planning & design services for
architectural planning, civil, structural, electrical and mechanical engineering in various
projects. A few of them are enumerated in Table-10.3.3.
Table – 10.3.3
Sl. No. Services Offered
1 Planning of large capacity, high speed bulk material
handling plants
2 Turnkey execution of coal handling plants
3 Planning of high voltage sub-stations
4 Planning of workshops of various types and capacities
5 Township planning including roads, water supply, water
supply system, drainage, Water / sewerage treatment plants
and detailed planning and design of all township
infrastructure
6 Site selection of pit head thermal power plants based on
remote sensing data
7 Rail corridor alignment through remote sensing
8 Techno-economic feasibility study of captive power plants
based on pulverized coal and FBC technology
10.3.4 Environmental Services:
CMPDI holds a position of eminence in the field of environmental planning, impact
assessment, management and environmental engineering in coal and other sectors. It is
the nodal agency for co-ordination and monitoring of ongoing environmental up-
gradation schemes sanctioned by Ministry of Coal and Mines under the head
“Environmental Measures and Subsidence Control”. It undertakes technical scrutiny of
new proposals, visits to project sites and disbursement of funds to the implementing
agencies.
A few of the new areas in which CMPDI has diversified are environmental and hydro-
geological studies for disposal of fly ash, development of air quality model, bio-treatment
of industrial effluents, carrying capacity base development planning, watershed
modeling and rain water harvesting. Services offered with respect to environmental
quality monitoring, engineering, management and planning are briefly given in Table-
10.3.4.
Table-10.3.4
Sl. No. Sub-heads of
Services
Services rendered
1 Environmental
Monitoring
Air quality
Water quality
Noise level
Soil quality
Micro-meteorological studies
Stack monitoring
2 Environmental
Engineering
Industrial/ Municipal effluent
treatment and recycling plants
Hazardous waste disposal site
engineering
Municipal effluent disposal site
engineering
3 Natural resource
management
Land use planning
Rain water harvesting
Watershed management plans
4 Regional planning Regional environment
management plans
Regional environment status plans
5 Environment
assessment plans
Environment assessment plans
6 Special studies Review of existing mining and
environment policies, legislations,
standards and mechanisms for
monitoring compliance,
institutional strengthening for
regulatory and counterpart
institutions.
Study of environmental problems
and action plan for restoration of
environmental quality.
Mine closure planning
10.3.5 Beneficiation Services:
CMPDI specializes in planning, design and construction of new washeries and
modification of existing washeries for coal and mineral beneficiation. Services with
respect to beneficiation offered to are given in Table-10.3.5.
Table-10.3.5
Sl. No. Services Offered to for
1 Planning of coal and mineral beneficiation plants
2 Preparation of feasibility / project reports including macro
level analysis, washability studies, environmental impact
assessment and techno-economic analysis.
3 Technical studies, performance evaluation and operation
and maintenance related consultancy for existing washeries.
10.3.6 Management Services:
Management services enumerated in Table-10.3.6 have been offered by CMPDI to
different organizations or bodies.
Table-10.3.6
SN Sub-heads of Services Services rendered for
1 Coal Investment
promotion Services
Assistance to Government of India in
identification and assessment of coal mining
properties for investments through private sector
participation.
2 Quality Management
Services
Consultancy for implementation, certification and
maintenance of ISO 9001 Quality Management
System and its industry specific translations, ISO
14001 Environment Management System and
OHSAS 18001 Occupational Health and Safety
Assurance System.
3 Human Resource
Services
Creating knowledge and skill based workforce,
CMPDI through its Staff Training College (STC)
imparts training to its clients’ personnel. Under
UNDP, CMPDI has trained professionals from
Nigeria, Sultanate of Oman and North Korea.
Through its STC it has organized training
programmes under five major categories such as
(i) Technical, (ii) Managerial, (iii) Computer
application, (iv) Quality Skills, (v) Quality System,
etc. It has also organized and conducted off-
campus training programmes with respect to
Quality System at various subsidiaries of CIL.
CMPDI diversified into management system consultancy in 1998. While continuing to
provide consultancy for ISO 9000 Quality Management System (QMS) and ISO 14000
Environmental Management System (EMS), it made forays into consultancy for ISO 17025
(Testing and calibrating laboratories) under consultancy scope as:
Creation of Management system
Providing training support
Implementation, certification and post certification support
10.3.7 Specialized Services:
With a view to catering to specific requirements of clients, CMPDI has been providing
field oriented specialized services to its clients. Descript services rendered under this
category have been remote sensing, terrestrial survey, blasting, ventilation design & gas
assessment in underground mines, energy audit and non-destructive testing. Main
services rendered are described in brief in Table-10.3.7.
Table-10.3.7
SN Sub-heads of Services Services rendered in
1 Geomatics Geomatic services in mining sector ranging fro
topographical survey, baseline data generation
and monitoring of land use / land cover for
environmental management, water resource survey
and coal mine fire mapping. It has also imparted
expertise services in the field of remote sensing
applications, terrain mapping, co-relation survey for
underground mines, GPS / GIS survey, cartography
and digital image processing.
2 Blasting Carrying out controlled blasting and ground
vibration study, vibration monitoring, fragmentation
improvement studies, random sampling & testing of
explosives and accessories and performance
evaluation of new explosives with sophisticated
testing equipment, in both coal and non-coal
sectors.
3 Non-destructive Testing
(NDT)
Services for non-destructive testing of components
of machinery, installations and other structural
elements have been provided at site during
periodic maintenance to avoid accidental failure.
4 Ventilation and Gas
Survey
CMPDI has been offering services for ventilation
monitoring, planning & design of ventilation system
including gas assessment and testing for
underground mines.
5 Energy Audit CMPDI is empanelled as an accredited energy
auditor with Govt. of West Bengal and Petroleum
Conservation Research Association (PCRA) under
Ministry of Petroleum and Natural Gas, Govt. of
India. Over 130 reports on electrical and diesel
energy conservation have been prepared.
6 Inspection services CMPDI has been rendering pre-dispatch third party
inspection services for plants and equipment at the
manufacturers’ workstations for materials procured
by its clients.
7 Captive power plants Reports on optimum utilization, conceptual notes
and tender documents
10.3.8 Laboratory Services:
CMPDI has well equipped laboratories for carrying out investigations and analysis for
geo-chemical, petrography coal washability and geo-mechanical properties.
For coal and lignite characterization, CMPDI has laboratories with highly skilled
manpower and state of art equipment. The data generated by these laboratories form
basis of characterization and grading of coal in exploration, mine feasibility reports,
washery design and down stream utilization. Brief description of Laboratory Services
rendered by CMPDI is given in Table-10.3.8.
Table-10.3.8
SN Sub-heads of Services Services rendered in
1 Geo-chemical
Laboratory
CMPDI has been rendering services like geo-
chemical analysis like proximate & ultimate analysis,
GCV determination of coal and lignite and other
special test through microprocessor based
automatic calorimeter and analyzer.
2 Petrographic Laboratory CMPDI has been carrying out evaluation for hydro
carbons, oil shales and coal bed methane for coal
coke and source rock through sophisticated
microscopes, identifying mineral phases in coal,
rocks and metal through X-Ray diffractometer, and
micro-area analysis and cleat studies for CBM
through Scanning Electron Microscope accredited
by International Committee for Coal and Organic
Petrology (ICCP).
3 Mining Laboratory CMPDI has been determining physico-mechanical
properties of rocks for design inputs for mine
planning and other technical services and
undertaking testing of roof supports and building
materials for design support systems for
underground workings.
4 Washery Laboratory CMPDI has been determining washability
characteristics of coarse, small and fine coal and
shattering & pulverized characteristics of coal for
assistance in planning and design of coal
beneficiation plants.
7 Captive power plants Reports on optimum utilization, conceptual notes
and tender documents
10.3.9 IT Services in Mining:
CMPDI has been gearing up itself fully to meet challenges of IT sector requisite for mining
industries as per IT implementation scheme with a view to revolutionizing mining industry
and mining operations in coming years. IT services provided by CMPDI have been
tabulated in Table-10.3.9.
Table-10.3.9
Sl. No. Services Offered to for
1 Mine communication and mine safety systems
2 Establishing internet and internet facilities
3 Real time fleet management system for large OC mines
using GIS & GPS.
4 Land information system using enterprise GIS.
10.3.10 R & D Services:
The Research & Development activities in coal and lignite are being administered
through the Scientific Advisory Committee (SSRC) with Secretary (Coal) as its Chairman.
The committee is entrusted with the task of planning, budgeting and overseeing the
implementation of R & D programme in coal and lignite sector and also for application
of research findings. And, CMPDI is the Nodal Agency to co-ordinate S & T / R & D
activities in coal and lignite sectors and assist SSRC in areas mentioned herein after.
CMPDI applied research and development in the field of mining, beneficiation,
utilization, environment, exploration, etc. serving as nodal agency for all S & T schemes
funded by Ministry of Coal and R & D schemes funded by R & D Board of CIL (constituted
in August 1995).
Field oriented research projects including transfer and absorption of new technology
concerning main areas of coal research have been as follows:
Production, productivity and safety.
Coal beneficiation and utilization.
Environment and Ecology.
********************************
ANNEXURE - II
PROFORMA FOR ENVIRONMENTAL APPRAISAL OF MINING
PROJECTS (MINING SECTOR PROJECTS)
Note1 :All information to be given in the form of Annex/s should be properly numbered
and form part of reply to this proforma.
Note 2: Please enter / in appropriate box where answer is Yes/No
Note 3: No abbreviation to be used – Not available or Not applicable should be clearly
mentioned.
Note 4: Core zone is the mining lease area.
Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all around the periphery
of the core zone and for ML area above 25 ha. an area 10 km all around the periphery of the
core zone.
Note 5: Adopt Scoping process in carrying out EIA study
Note 6: Please indicate source of data
1. General Information
(a) Name of the project : Ghonsa OC Expansion Project (0.60 MTPA)
Name of the proponent : M/s WESTERN COALFIELDS LIMITED
Mailing Address : C/O Chief General Manager
Wani North Area , WCL, Bhallar Township
Dist. Yavatmal ( M. S.)
E- mail : [email protected]
Telephone : 07239 – 241347
Fax No. : 07239 – 241357 (CGM Office)
(b) Objective of the project :
To meet the demand of power
coal
(c) Location of mine(s)
Village(s) Tehsil District State
Kumbharkhani &
Ghonsa
Wani Yavatmal Maharashtra
(d) Does the proposal relate to
(i) New mine : No
(ii) Expansion : Yes
Increase in ML area : Yes
Increase in annual production : Yes
(iii) Renewal of ML : No
(iv) Modernization : No
e) Site information
Geographical Location
Latitude : 190 57’11” to 190 58’35” N
Longitude : 780 49’30” to 780 50’ 25” E
Topo sheet no : 55 I /13
Total mining lease area (in ha) : 128.79
( Location Plan is enclosed as Plate- I)
(ii) Dominant nature of terrain :
Flat
Undulated : Yes , Gently undulating.
Hilly
2. Land usage of the mining lease area (in ha).
(a)Agrclt. Land : 128.79
(b) Waste land(Govt.land) : ---
(c) Forest /Zudpi Jungle : ---
(d) Surface water bodies : Nil
(e) Others (Specify) : Nil
Total : 128.79
3. Indicate the seismic zone in which ML area falls. In case of zone IV & V, details of
earth quakes in last 10 years. : Seismic zone no. - II
(a) Severity (Richter Scale) : Not applicable
(b) Impact i.e. Damage to
Life : No
Property : No
Existing mine : No
5. Township (outside mining lease) :
(a) Total area (in ha) : 1.00 ha
(b) No. of dwelling units : 50 Miners Quarters (Existing)
(c) Distance from mine site : 3 km
6. Distance of water bodies (in km)
Distance from River Bank* Other water bodies* Sea / Creek
/Lake / nalla etc. (specify)
Mining lease
boundary
Vidharbha river –
100 m
-
Ancillary facilities - -
[* from highest flood line/high tide line] -
7. For projects falling within the Coastal Regulation Zone (CRZ) : Not applicable
Whether the mineral to be mined is of rare nature and not available outside CRZ?
If yes, annex a scaled location map showing low tide line (LTL), high tide line (HTL) duly
demarcated by one of the authorized agencies*[*Director, Space Application Centre,
Ahmedabad: Centre for Earth Sciences Studies, Thiruvananthapuram: Institute of Remote
Sensing, Anna University, Chennai, Institute of Wetland Management & Ecological
designs, Kolkata, Naval Hydrographer’s Office, Dehradun: National Institute of
Oceanography, Panjim, Goa: and National Institute of Ocean Technology, Chennai]
boundary of mining lease area, diastance of ML area from LTL and HTL CRZ boundary
and CRZ classification of the project area as per the approved Coastal Zone
Management Plan, and settlements, sand dunes, mangroves, forest land/patches, turties
breeding and nesting sites etc., if any, in the project area.
8. Indicate aerial distance from the periphery of core zone/area from the periphery of the
buffer zone to the boundary of following (upto 10 km)
Given below ;-
a) BUFFER ZONE – It is the area within the radius of 10 km of mining lease area and the
details of features within buffer zone is as given below ;-
[*Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all around the
periphery of the core zone and for ML area above 25 ha. an area 10 km all around the
periphery of the core zone].
9. Description of flora & fauna separately in the core and buffer zones*
[*Consult the Wildlife(Protection) Act, 1972 as amended subsequently and list species
with (1) Common name (2) Scientific name and (3) under which schedule of the Wildlife
(Protection) Act the identified species fall. Get the list authenticated by an Expert in the
field/credible scientific institute/University/Chief Wildlife Warden office. Information to be
based on field survey].
Flora & Fauna Area
EIA - Summary Statement
SU REPORT ON GENERATION OF BASE LINE DATA FOR FLORA AND FAUNA OF DINESH (OC)
MINE OF WESTERN COAL FIELDS LTD.
I. Indicate aerial distance from the periphery of core zone and buffer zone areas of the following
(up to 15km):
S.No Geographical features Name Aerial distance from 15 (km)
Core Zone Buffer Zone
1 National Park /Sanctuary Not Applicable None None
2. Biosphere reserve/Tiger/Elephant
Reserve/any other Reserve
Not Applicable None None
3. Forest Type (RF/PF/Unclassified) Not Applicable None None
4. Habitat for Migratory Birds Not Applicable None None
5. Corridor for animals of schedule
1& II of wildlife (protection) Act,1972
Not Applicable None None
6 Archeological sites Notified /Others Not Applicable None None
II A. Description of Flora in the Core and Buffer Zones
A. Flora Core Zone
Buffer Zone
1.Agricultural crops Table in Chapter - III Table in Chapter - III
2.Commercial crops Table in Chapter - III Table in Chapter - III
3.Plantations/Agro forestry Table in Chapter - III Table in Chapter - III
4.Natural vegetation/Forest type No forest areas- Only Jhudpi
Jungle (Table in Chapter - III)
No forest areas
(Table in Chapter – III)
5. Grass lands No grass lands (Table in Chapter - III) No grass lands
(Table in Chapter - III)
6.Endangered species None of the species found None of the species found
7. Endemic species None of the species found None of the specie found
8. Others (specify) No prominent aquatic
bodies are present
No prominent aquatic
bodies are present
10. Details of mineral reserves (as per approved Mining Plan)
(Quantity in million tonnes )
(a) Proved : 14.60
(b) Indicated :
(b) Inferred :
(c) Mineable reserves : 1.73 Million Tonnes
11. Major geological formation/disturbances in the mining lease area
(a) Geological maps submitted : Yes
(b) Geological sections submitted : Yes
(c) Contour map submitted : Yes
(d) Whether the presence, if any noted of
(i) Faults
: Yes
(ii) Dykes
: No
(iii) Shear Zone
: No
(iv) Folds
: No
(v) Other weak zones : Yes, presence of sympathetic
faults and Minor slips can not be
ruled out.
(e) Source of data (Indicate) : Geological report & PR
prepared by CMPDI
12. Production of mineral(s) and life of mine
(a) Rated capacity of mine mineral wise (tonnes/annum) : 0.60 MTPA (Maximum
Achievable)
(b) Life of mine at proposed capacity (years) : 2 years
(c) Lease period (Years)
: Not applicable
(d) Date of expiry of lease (D/M/Y) : Not applicable
(e) Indicate in case of existing mines :
Date of opening of mine : 2008-09
ii) Production in the last 5 years
From year 08-09to year 10-11 in million tones. : As given below
2008-09 – 87883 te
2009-10- 300000 te
2010-11- 362760 te
2011-12 -- 450000 te
i) Projected production for the balance
Years : Maximum Achievable
0.60 MTPA
ii) Whether mining was suspended after : No
opening of the mine ?
If yes, details thereof including last production
figures and reason for the same.
(f) Whether plans & sections provided ? : Yes
13. Type and method of mining operations
Type
Method
Opencast Yes By
Mechnised
method
Manual Mechanised
Yes
Underground x X
Both x x
14. MINING DETAILS:-
Geo-mining Characteristics & Mine Profile
MINE PARAMETERS
The seam characteristics and the profile of the quarries are as given below in Table:
Sl. PARTICULARS South Quarry
1 Area of the Quarry
(a) On floor (Ha.) 27.68
(b) On surface (Ha.) 38.05
2. Depth (m)
(a) Initial 13
(b) Final 46
3. Gradient of Seam 1 in 12.0 to 1 in 10.5
4. Effective thickness of seam (m)
(a) Seam-I 1.00 to 3.50
(b) Seam-II 2.12 to 5.40
5. .Strike length (m) 955
6. Width on surface (m):
(a) Maximum 510
(b) Minimum 180
7. Mineable reserves (Mt) 1.73
8. Total OB incl. Access Trench
(Mm3)
8.54
9. Average S.R. m3/t. 4.94
CHOICE OF TECHNOLOGY:
The shovel dumper combination has been proposed in this mine. As the total mineable
reserves are only 1.73 Mt, application of dragline and surface miner have been ruled out.
Moreover, the application of dragline or surface miner will not be economically viable in
the prevailing geo-mining conditions. The thin seam thickness (2m to 4m) of seam-I and
seam-II calls for smaller size HEMM. Shovel-Dumper combination is very flexible and most
adopted technology in WCL.
Drilling & Blasting
The degree of fragmentation in opencast mine has to be optimised so that total cost of
drilling, blasting, excavating, transport and crushing as a total system is minimised.
Controlled blasting method has to be adopted. In order to keep the ground vibrations
within the permissible limit as per DGMS Circular No. 7 of 1997, to avoid flying of rock
fragments and also to achieve satisfactory blasting results, optimized drilling / blasting
parameters depending upon rock formation using combination of relays / delays will
have to be evolved. It is further recommended that at the time of actual execution,
proper study for controlled blasting and ground vibration is to be done with the help of
scientific body in order to evolve site specific charge distance relationship.
Powder factor of 3.0 m3/ kg & 5.0 t/kg for OB and coal has been considered in this report.
It is proposed that Site Mix explosive should be used to save charging time and avoid
creating extra Magazine capacity.
EQUIPMENT FOR OB & COAL:
It is envisaged in the PR that total excavation (Top OB, Parting and coal) would be done
by Hiring of HEMM. No departmental HEMM is proposed for mining purpose.
15. Mine details.
(a) Opencast mine :
(i) Stripping ratio (mineral in tones to over burden in m3 ) : 1 : 4.94
(ii) Ultimate working depth (in m bgl) : 46
(iii) Indicate present working depth in case of : 35
existing mine (in m bgl)
(iv) Thickness of top soil (in m)
Minimum : 5.00
Maximum : 10.00
Average : 7.50
iii) Thickness of overburden (in m)
Minimum : 13.00
Maximum : 46.00
Average : 29.50
iv) Mining Plan
Height and width of the
bench in
Overburden/waste.
: Bench height – 10 m
Width –
Working Bench- 30m
Non-working width-
20m
Height & width of the
bench in ore body / coal
seam
: Bench height – 5 m
Width –
Working Bench- 30m
Non-working width-
20m
Proposed inclination /
slope of the sides of the
opencast mine
(separately for
overburden , coal/ ore
and overall slope of the pit
sides ) both while
: Individual Bench
slope-
Coal - 700
OB ( hard strata ) -700
OB ( soft soil ) - 450
Overall slope –
rise side - 270 to 370
operating the mine as well
as at the time of closure
of the mine.
(while operating &
closure )
dip side-
while operating-180-
200
while closure - 400
The recommendation
of Slope stability study
being implemented.
Whether transverse
sections across the
opencast mine at the end
of fifth year and at the
end of the life of the mine
have been submitted
: Yes
(vii) Type of blasting, if any, to be adopted. : Controlled Blasting
(b) Underground : Not Applicable
(i) Seam/Ore body Min.Depth (m) Max. Depth (m) Avg.thicikness (m)
Rate of dip in degree Direction of dip.
Mode of entry into the mine
Shaft
Adit
Incline
Details of machinery
On surface
At face
For transportation
Others
Method of stopping (metalliferrous mines)
Open
Filled
Shrinkage
Caving
Combination of above
Others (specify)
Extraction method
Caving
Stowing
Partial Extraction
Subsidence
Predicted max. subsidence (in m)
Max. value of tensile strain (in mm/m)
Max. slope change (in mm/m)
Whether identified possible subsidence
Area (s) superimposed on Surface
Plan has been submitted ?
Major impacts on surface features like
Natural drainage pattern, houses, buildings,
Water bodies, roads, forests etc.
Salient features of subsidence management
(monitoring and control).
16. Surface drainage pattern at mine site.
(a) Whether the pre-mining surface drainage plan
submitted?
: Yes
(b) Do you propose any modification/diversion in
the existing natural drainage pattern at any
stage? If yes, when. Provide location map
existing natural drainage indicating contours,
dimensions of pattern proposed to be
diverted, direction of flow of water, proposed
route/changes, if any i.e. realignment of river
/ nallah / any other water body falling within
core zone and its impact.
: No major change-modification /
diversion in water body . Only
small diversions of seasonal
nullahs & diversion of irrigatinon
canal and there will not be
any adverse impact on existing
natural drainage pattern
17. Embankment and/or weir construction
(a) Do you propose, at any stage, construction of
(i) Embankment for protection against flood : Yes
(ii) Weir for water storage for the mine : No
(b) If so, provide details thereof.
( Quantum of OB proposed for embankment ) : Details in Chapter – II.
:
(b) Impact of embankment on HFL and settlement around : No impact
anticipated.
(d) Impact of weir on down stream users of water : Not Applicable.
18. Vehicular traffic density (outside the ML area)
Type of vehicles No. of vehicles per day
a) Existing -- Coal Tippers 91 trucks/day
Light vehicles Insignificant
(b) After the proposed activity -- Coal Tippers Approx. 180 /day
& Light vehicles
(c) Whether the existing road network is adequate ? : Yes
If no, provide details of alternative proposal ? : NA
* Considering maximum achievable capacity of 0.60 MTPA.
19. Loading, transportation and unloading of mineral and waste rocks on surface:
(a) Manual
(b) Tubs, mine cars, etc.
(c) Scraper, shovels, dumpers/trucks ------ Yes (Shovel & Dumper only)
(d) Conveyors (belt chain, etc)
(e) Others (specify)
20. Mineral(s) transportation outside the ML area
Qty.(in TPD) Percentage(%) Length (in km)
(a) Road 1818 100
(b) Rail -
(c) Conveyors
(d) Ropeway
(e) Water ways
(f) Pipeline
(g) Others (specify)
Total 1818 100%
25. Water requirement (m3/day)
Purpose Avg. Demand Peak Demand
Mine site 1. Mine operation/workshop 2. Land reclamation 3. Dust suppression 4. Drinking 5. Green Belt 6. Beneficiation 7. Washeries 8. Fire Service 9. Others (service buildings) 10 Losses B. Township Green Belt Domestic Other (specify)Welfare Losses
120 12
251
135 15
15
260
Total 383 425
26. Source of water supply*
S.No. Source m3/day
1. River (name)
2. Ground water
3. Mine water (sump/pit) 383
4. Other surface water bodies(specify) -
[*Annex a copy of sanction letter/permission from the concerned authority (Central Ground Water Authority in case of ground water abstraction is from notified area/State Ground Water Board in case of non-notified area/State Irrigation Department for surface water pumping) for drawing water]
27. Lean season flow in case of pumping from river/nalla (cumecs) : 0.01
28. Ground water potential of the study area
28.1 Ground water availability
(a) Range of water table (m bgl) (i) Pre-monsoon (April/May)
Core Zone : 4.98 - 8.99 m Buffer zone : 3.90 - 14.00 m
(ii) Post-monsoon (November)
Core zone : 2.80 - 6.6m Buffer zone : 1.90 - 10.10m
(b) Total annual replenishable recharge (million m3/ year)
By ground water table fluctuation method : 23.9 MCM By rainfall infiltration factor method : 24.59 MCM
( c) Annual draft excluding estimated draft through : 4.19 MCM
mine discharge (million m3/year)
(d) Estimated draft through mine discharge (million m3/year) : 1.24 MCM
(e) Net annual ground water availability (million m3/year) : 22.14 MCM
(f) Stage of ground water development in % : 18.92 %
28.2. Water demand – Competing users of the water source
S. No. Usage Present consumption Additional proposed
Total (m3/day)
Surface Ground Surface Ground Surface Ground
1. Domestic 4684 1500 6184
2. Irrigation 10033 - 10033
3. Industry -
4. Mining 3500 2500 6000
5. Others (Specify)
-
Total 18517 4000 22517
29. Water quality* : (a) Annex physico-chemical analysis of water at intake point : Enclosed
(b) In case of existing mine, annex report on quality of water : discharge i.e. complete physico-chemical analysis**
[*For non-discharging mines at least four ground water samples to be taken preferably from downstream direction of the mine in pre-monsoon and post-monsoon periods and analysed. For discharging mines six samples are to be analysed ]. ** All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter.
*** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’.
30. Impact on ground water regime/stream/lake/springs due to mine dewatering* (a) Radius of influence (in m)
: 500m (Final mine depth-200m)
[To be estimated based on analysis of pumping
test data and application of empirical formula]. (b) Whether saline water ingress will take place ? : NA (applicable to coastal areas) (c) Impact on stream/lake/springs
: NA
[*Provide a comprehensive hydro-geological assessment report. If the average mine dewatering is more than 100 m3/day and or going below water table in non-monsoon period. The report should be based on preferably latest one year pre-monsoon and post-monsoon baseline data covering information on ground water situation, aquifer characteristics, water level conditions (April – May and November), estimate of ground water resources, predicted impact of the project on ground water regime and detailed remedial/conservation measures such as artificial recharge of ground water etc. The report should be based on actual field inventory out of existing wells, at least 30 observation wells in the buffer zone with supplementary information from secondary sources (mention name). For estimation** of ground water resource (refer question No.28 above) be designated study area of the buffer zone may be sub-divided into command and non-command areas, watershed-wise (in case of hard rock/consolidated formations)/ block-wise/mandal-wise in case of alluvial/unconsolidated formations)].
[**For estimating ground water resources in the area follow the Ground Water Estimation Committee recommendations of 1997]
31. Waste Water Management
Mine (a) Daily average discharge (m3/day) from different sources
i. Mine water discharge during Lean period : 3500 Monsoon period : 6100
ii. Workshop : 10
iii. Domestic (mine site) : 12 iv. Beneficiation/Washeries : v. Coal Handling Plant : vi. Tailings pond :
vii. Others Total : 3522 m3/day (b) Waste water treatment plant/flow sheet : As given below for treatment process attached
The strata seepage water will get accumulated in main mine sump provided at the floor of the seam which will allow significant settlement of suspended particles. Thereafter, supernatant mine water will be pumped out on surface & be passed through sedimentation pond for second stage settlement.
For, Workshop Effluent Treatment, a Zero – Discharge Workshop Effluent Treatment Plant will be
set up and will be operated.
(c) Quantity of water recycled/reused/ to be recycled in
(i) Percentage : 20 % (ii) m3/day : 704
d) Point of final discharge : Local drainage
Final Point Quantity discharged (in m3/day)
Surface (i) Agricultural land (ii) Waste land (iii) Forest land (iv) Green belt
---
2. River/nallah 2818
3. Lake
4. Sea
5. Others (specify)
Total 2818
(e) Users of discharge water
(i) Human : (ii) Livestock : (iii) Irrigation : Irrigation. (iv) Industry (mine site ) : (v) Others (specify) :
(f) Details of the river/nalla,if final effluent is/will be discharged (cumecs) : (i) Average flow rate : 1.0
(ii) Lean season flow rate : (iii) Aquatic life : (iv) Analysis of river water 100 m : upstream and 100 m downstream of discharge point submitted.
Township : Combined Township
(a) Waste water generation from township (m3/day) : (b) Are you planning to provide sewage treatment plant ? : No
(c) Usage of treated water : NA
32. Attach water balance statement in the form of a flow diagram : In Chapter - III indicating source(s), consumption (Section-wise) and output
33. Ambient noise level leq dB(A) : Baseline noise level data is given in Chapter – III of
EIA/EMP. Details given below
TABLE
AMBIENT NOISE LEVEL MONITORING STATIONS
SI.No. Location Name Location
Code
1. Core-zone N1
2. Ghonsa village N2
3. Phulora N3
4. Salgaon N4
5. Kalampad village N5
6. Dahegaon village N6
Data presentation & analysis
The generated noise level data are given in subsequent pages and the abstract is
furnished in Table below.
Noise level status
S.No. Zone
Leq. Noise level
(mean)(dB (A)) Noise level
Standards
Daytime Nighttime Daytime Nighttime
1. Core zone 60.8 51.7 75 70
2. Buffer zone 47.4 – 52.6 40.1 – 42.6 55 45
Mean Leq noise levels at day time and night time are ranging from 47.4 to 60.4 dB(A) and
40.1 to 51.7 dB(A) respectively in the study area. While comparing with IS: 4954 -1986
norms for acceptable outdoor noise levels in residential area, these values are found to
be within the limits.
Summary
While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels in residential
area, the Leq values are found to be within the limits.
34. Solid Waste
(a) Top soil and Solid waste quantity and quality
Name
(Lump/fines/
slurry/
sludge/others )
Composition
Quantity
(m3/month)
Method of Disposal
Mining activity*
a. Top Soil
b. Over burden
c. Others
(Specify)
Clay, Alluvium,
Shale,
Sandstone,
Quantity year –
wise given in
chapter – IV.
Dumping on surface as
external OB dump ,quarry
backfilling & embankment
construction .
Effluent Treatment
Plant (Sludge)
Oil & Grease
Silt
Will be disposed off
through approved
Recyclers.
Secured Land-fill
TOTAL ..
[* Annex layout plan indicating the dump sites Attached]
(b) (i) Does waste(s) contain any hazardous/ : No
toxic substance/radioactive materials
or heavy metals ?
(ii) If yes, whether details and precautionary : Not applicable
measures provided ?
(c) Recovery and recycling possibilities : Not applicable
(d) Possible user(s) of the solid waste : Quarry backfilling.
embankment
Construction.Balance in
external OB dump.
(e) (i) Is the solid waste suitable for backfilling ? : Yes
(ii) If yes, when do you propose : From IVth year of operation.
to start backfilling
(in million m3)
Solid waste(s) Already
accumulated
(A)
To be
generated (B)
% age of A & B to be
backfilled
A B
Overburden As given below
Others (specify) NIL
Summary of Solid Waste –
Sl.
NO
Particulars Disposal of Solid Wastes(In Mm3)
External OB
Dump
Internal Dump in
Decoaled Void
Total
1. Solid Waste
(Over burden)
7.37 1.17 8.54
(f) In case waste is to be dumped on the ground, indicate :
(i) Associated environmental problems : Fugitive emission of dust by wind &
surface run off.
(ii) Number & type of waste dumps :
No.of external dumps
: 01
Max. projected height of dumps (in m) : 60
No.of terraces and height of each stage : Four terraces, each of 15 m
with berm of 6 m at + 15 m &
+ 45m level and transportation
bench of 20 m at + 30 m
level.
Overall slope of the dump (degree) : 28o
Proposed reclamation measures :
Development of grasses ,
legumes & plants. OB
dump will be first
technically reclaimed with
proper benches & slopes.
Then it will be taken up for
biological reclamation
(afforestation) in phases
along with embankment.
The year – wise Calendar
Programme is given
below:-
(iii) Section of the waste dump in relation to : Yes
the adjacent ground profile attached
This is a tentaive programme drawn with the consideration of the maximum achieavable
capacity of 0.60 MTPA and may undergo changes depending on the actual progress of
the mine as well as future expansion in strike direction with addition of two more quarries.
Post mining land use plan (Conceptual)
The post-mining land use pattern at Ghonsa Expansion OCP will be as follows:-
POST MINING SCENARIO (AREA FIGS IN ha)
SL. NO.
PARTICULARS PLANTATION VOID PUBLIC USE UNDISTURBED/ UNPLANTED
TOTAL
1 EXTERNAL OB DUMP
29.35 - - - 29.35
2 EXCAVATED AREA 4.00 34.05 - --- 38.05
3 INFRASTRUCTURE - - 10.00 - 10.00
4 BLASTING ZONE INCLUDING
RATIONALISATION
AREA
10.00 - - 25.39 35.39
5 EMBANKMENT 15.00 - - - 15.00
6 COLONY 1.00
TOTAL 58.35 34.05 11.00 25.39 128.79
35. Fuel/Energy requirements*
[*To be furnished for mines having ML area more than 25 ha or captive power
generation of 500 KVA and above].
(a) Total power requirement – 1034 kVA
(in kVA)
S.No Mine site Township Others (specify) Total
1 Present ---
2 Proposed 890 144 - 1034
Total 890 144 - 1034
(b) Source of power : - MAHAGENCO.
( Due approval from MAHAGENCO taken at area level for no. of mines
together).
S.No SEB/Grid* Captive
power
plant
DG sets
1. Present
As above
2. Proposed
Total
[*Annex a copy of the sanction letter from the concerned authority]
(c) Details of fuels : Deployment of HEMM proposed through partial hiring.
S.No. Fuel Daily consumption
(TPD)
Calorific
value
(Kcals/kg)
% Ash % Sulphur
1.
2.
3.
HSD
LSHS
Other
(Lub.)
Existing
4500
Proposed
5500
36. Storage of inflammable/explosive materials
S.No. Name Number of
Storages
Consumption
(in TPD)
Maximum Quantity at
any point of time.
1. Fuels Central
Storage
5500 Maximum storage for 3
days only.
2. Explosives Magazine 2500 kg Maximum storage for 3
days only.
37. Human Settlement
Core Zone Buffer Zone
Population* All details regarding socio –
economic have been given in
Chapter – III.
No. of villages Nil
Number of households Village-
wise
[*As per actual survey]
38. Rehabilitation & Resettlement ( R & R) Plan*
[*Provide a comprehensive rehabilitation plan, if more than 1000 people are likely to be
displaced, other-wise a summary plan]
a) Villages falling within the study area :
Villages
Number Name
Core Zone Nil NA
500 m from the blasting
site(s)
Buffer zone All details regarding socio –
economic details have
been given in Chapter – III.
Shown in Index Plan
(Plate – II))
Township site --- ---
(b) Details of village(s) in the core zone : Nil.
( c) Population to be displaced and/or Land oustees : Land Oustees – Yet to be
finalized.
Name of
village(s) falling
within
Number of oustees
Land (only) Homestead
(only)
Land and Homestead
(both)
Mining
Lease
Till date 69.
55 Employment
given. 3 have been
given Monetary
Compensation.
Nil As given in previous
Column.
Township
Site
Nil
(d) Whether R&R package has been finalized?
If yes, salient features of R & R plan for oustees : Not Applicable
(i) Site details where the people are proposed to
be resettled & facilities existing/to be created : Not Applicable
(ii) Funds earmarked for compensation package * : Not Applicable
(iii) Agency/Authority responsible for their resettlement : Not Applicable
(iv) Time of commencement of resettlement : Not Applicable
of Project Affected People (PAP)
(v) Period by which resettlement of PAP will : Not Applicable.
39. Lease-wise plantation details
(a) Lease area (in ha.) New mine Existing Mine
(i) Area broken up : 25.00 ha
(ii) To be broken up : 13.05 ha
(iii) Area not to be broken up : 90.74 ha
(b) Township area (in ha) 1.00 ha.
( c) Area afforested and proposed (in ha)
Afforested 3.50 ha ; Proposed –The proposed afforestation plan is given below.
On the dump slopes and top surface, plantation of grass and trees will be done in phases
and the details are as follows ;-
(d) No. and type of trees planted and proposed :
(i) Existing : 8750
a. When plantation was started? 2009-10
b.
No.of plant species planted
Number of saplings (per ha.)
Native species 2500
(ii) Proposed : 5000
No. of plant species to be
planted
Number of saplings (per ha)
Native species 2500
40. Environmental health and safety
(a) What major health and safety hazards
are anticipated?
No major health & safety hazards
anticipated. However, coal mining
activities are itself hazardous and as
such disaster management plan has
been worked out considering the
probable risks / hazards & their
mitigative measures have been given
in detail in Chapter – VI.
(b) What provisions have been made/proposed
to be made to conform to health and safety
requirement? :
Mine will be worked as per statute.
Dispensary, First aid center at the
mine level, full fledged hospital at
Area level to cater to the
needs of all employees. Emergency
Response Plan will be prepared and
mock rehearsal will be done
regularly.
( c) In case of an existing mine :
(i) Comprehensive report on health status : Periodical Medical Examination of all
workmen once in five years.
Mineralogical composition of RPM (dust) :
Free silica as SiO2 - 11.5
Chromium* (Total as well as Hexavalent) - Not applicable
Lead ** - Not applicable
[*Only for Chromite mines] [** Only for Base Metal mines]
(d) Information on radiation protection measures, if applicable : Not Applicable
41. Environmental Management Plan
Salient features of environmental protection measures.
S.No. Environmental issues* Already practiced, if
applicable
Proposed.
1. Air pollution Green belt development,
plantation at all suitable
vacant areas, OB dump,
Wet Drilling, water
spraying on
haul road & coal
transportation
road etc.
To be continued
2. Water pollution Sedimentation pond for
mine pumped out
water
Workshop Effluent Treatment
Plant for workshop effluent
3. Water conservation Earthen check dams
4. Noise pollution Providing personal
protective gears / ear
muffs & ear plugs,
maintenance of P&M,
green belt development
etc.
To be continued
5. Solid waste/Tailings Backfilling in decoaled
void, embankment
construction, external OB
dump & biological
reclamation thereafter.
Backfilling in decoaled void,
embankment construction,
external OB dump &
biological reclamation
thereafter.
6. Land degradation Technical & biological
reclamation
Technical & biological
reclamation
7. Erosion & Sediment Plantation on OB dump &
embankment, garland
drains around OB dump &
coal dump , green belt on
plain land.
8. Top soil Initiallty to be dumped at
earmarked site and thereafter
to be used concurrently
9. Ground vibration Controlled Blasting To be continued
10. Wildlife conservation Not Applicable Not Applicable
11. Forest protection Not Applicable
12. Others (specify) Social development works
in nearby villages.
To be continued as per the
CSR Policy of the Company (* As applicable)
42. Compliance with environmental safeguards (for existing units) :
(a) Status of the compliance of conditions of : Complied
environmental clearance issued by MOEF
if any, enclosed
(b) Status of the compliance of ‘ Consent to : Complied
operate’ issued by SPCB, if any, enclosed.
(c) Latest ‘environmental statement’ enclosed : Annexure – VI.
43. Scoping of EIA
Whether environmental impact assessment : Yes
of the project has been carried out by following
scoping process?
If yes, a copy of scoping of EIA annexed : Details given below.
IMPORTANT ENVIRONMENTAL ASPECTS (Scoping )
1. Forest land involved Yes
2. Wild life sanctuary ( 10 km. radius) None
3. Fragile Eco/ Bio- diversity system nearby (10
km. radius)
None
4. Coastal area nearby (10 km. radius) None
5. Environmental impact on the region. No adverse impact anticipated.
However the project will be
beneficial to the local people of
the region.
6. Impact on quality & quantity of ground
water specific to the project.
The detailed impact assessment
has been done and given in
Chapter – III & IV. Impact will be
insignificant.
7. Risk & Hazards involved due to the project Risk & hazards associated with
mining will be limited to mine
area only. However, the mine is
being worked and will continue
to be worked as per the
statute.
8. Env. Pollution control
measures
Environmental Pollution control
measures are being implemented
and will continue to be effectively
implemented & regular monitoring
will be done.
9. Rehabilitation & resettlement. There is no Resettlement of
house oustees involved in this
proposal.There is only
Rehabilitation of land oustees
involved due to acquisition of
additional tenancy land.
Entire Rehabilitation will be
carried out as per Company’s
Policy.
44. Mine closure
(a) Have you planned mine closure : Yes
(b) Submitted a conceptual mine : Yes
closure plan
(c) If yes, indicate estimated amount : As per MOC Guidelines – Aug,2009
for implementing the same (in Rs.lakhs)
Details of Progressive Mine Closure Plan is given below;-
PROGRESSIVE & FINAL MINE CLOSURE PLAN
Mine closure plan.
Although, the mining activities may last a few decades, but they are liable to leave a
long lasting impacts on the landscape, ecology and on local inhabitants. The objective
of mine closure plan is aimed at restoration/reclamation of disturbed area, which should
be acceptable to local community as well as regulatory authority.
Mine closure is not something that happens at the end of a mine's life rather mine closure
is an ongoing series of activities starting from the planning stage of a mine and ending
with a suitably restored site that can be returned to the community. The mine closure is
planned in two phases:
c) The first phase/progressive site-specific closure plan includes the various activities to
be implemented over the life of the mine. The required timetable for these is given in
detail in the EMP/Project Report itself. The required fund – Capital and Revenue, is
also given under different heads in the EMP/Project Report.
d) This plan may undergo and incorporate changes depending upon the actual site
condition during implementation, legal & social requirements in future, availability of
additional coal reserves, etc. As such a detailed closure plan will be prepared
before the actual closure time of the mine. This plan is the culmination of the
activities given under progressive plan.
Major activities under mine closure plan
The mine closure plan includes the following major activities.
Environmental Aspects
Social Aspects
Safety & Technical Aspects
Environmental Aspects.
Reclamation of dumps.
During quarrying operation, OB is initially removed and kept as external dump. Coal
production starts once the coal seam is touched. Once the lowest and economically
mineable coal seam is exhausted, a void / decoaled area is created. The OB generated
from advancing benches is then backfilled in this decoaled area as an internal dump.
With the ongoing process of mining operation, the external dump and internal dump are
technically reclaimed.
Backfilling of Quarry Void:
It has been proposed to work the quarries by Horizontal Slicing Method i.e. conventional
benching system with shovel-dumper combination. This system is being widely used in the
opencast mines of Wardha Valley Coalfield. The backfilling of quarry void will start from
4th year of quarry operation.
The detailed break-up of overburden management are as follows:-
S.N. Head Overburden (Mm3)
1 External OB Dump 7.37
2 Internal Dumping 1.17
TOTAL 8.54
Post Mining Land Use Pattern:-
The post-mining land use pattern at Ghonsa Expansion OCP will be as follows:-
POST MINING SCENARIO (AREA FIGS IN ha)
SL. NO.
PARTICULARS PLANTATION VOID PUBLIC USE UNDISTURBED/ UNPLANTED
TOTAL
1 EXTERNAL OB DUMP
29.35 - - - 29.35
2 EXCAVATED AREA 4.00 34.05 - --- 38.05
3 INFRASTRUCTURE - - 10.00 - 10.00
4 BLASTING ZONE INCLUDING
RATIONALISATION
AREA
10.00 - - 25.39 35.39
5 EMBANKMENT 15.00 - - - 15.00
6 COLONY 1.00
TOTAL 58.35 34.05 11.00 25.39 128.79
Hydrogeological Considerations
The local drainage of the region is controlled by Vidharbha River. The discharge of the
mine water after treatment will first meet the local nullah and ultimately discharge into
Vidharbha River. The surface run-off from external OB dumps will be guided through
sedimentation ponds and garland drains to the surface watercourse. These structures will
remain even after the closure of the mine as it will prevent eroded material from
reaching the main drainage / watercourse of the region.
In the reclaimed area, the permeability of water is usually higher and receives about 40%
of rainfall as recharge. Due to this, the impact on rise side of the mine gets reduced and
with time and after cessation of mining it even improves the ground water system.
The final void provides access for future expansion of the mine.
Bio-diversity issues:
The reclaimed and afforested external dump covering 29.35 ha along with 80.00 ha of
backfilled area, 35 ha of embankment and 55.00 ha of plain land will be made into a
habitat for the fauna. This composite habitat for faunal spp based upon prey predator
relationships, after complete reclamation will support populations of insect, bird spp,
small herbivores and other predatory species dependent upon these spp, in the food
chain.
Social Aspects:
Mining operation has affected the families and landowners in the mine take area
directly. The project affected persons and families will be given adequate compensation
as per Company's norms.
Safety & Technical aspects
It includes demolition, dismantling, disposal & alternative use of surface structures like
workshops, power line foundations, offices, residential colonies etc.
Utilisation of existing surface infrastructure:
In this project, the surface structures will be utilized by the future extension of mine.
Management of Hazardous waste:
The waste oil and oil filters collected during routine maintenance of HEMMS comprise
hazardous material generated during the life of mine. These will be regularly collected
and auctioned to authorized recyclers and as such no hazardous material will be left at
site after the closure of the mine.
Management & Use of void:
The quarry void will provide access for the future extension of the mine.
Survey records & maps:
Survey records of working showing the infrastructures, last working position, dump etc. will
be maintained. A copy of the closure plan giving details of all the safety precautions
taken along with maps etc. will be submitted to the Directorate General of Mines Safety.
Fencing around void for mine closure:
At the time of final closure of mine a permanent fencing will be erected around the void
periphery. The physical details of the fencing are:
Height : 1.5 m
RCC Posts : 1.8 m high placed at 3 m apart.
Wire : Parallel lines & 2 cross lines of barbed wire.
Fund provision for mine closure:
For the effective closure of the mine, various activities are to be continued after the end
of mining operation viz. land reclamation, afforestation, protective boundary/fencing,
continuation of all monitoring programmes, control of all contaminated effluents,
securing of all petroleum products, chemicals & waste etc.
Conclusion:
It can be seen from the points mentioned above that the activities required for mine
closure are already covered in the EMP/PR of the mine. These activities are not a one-
time activity to be undertaken at the end of life of mine. Most of the activities are carried
out regularly over the total life span of the mine.
The project under consideration is in all likelihood get further extended towards dip which
will give an additional lease of life to the project. As such, the actual closure plan can be
finalized only at the end of expansion project.
Financial provisions as per the Ministry of Coal Guidelines dated 24/08/2009 for the
project under consideration within the limits specified has been made in the report to
undertake mine closure activities.
Note on creation of a Corpus Fund:
The purpose of a Corpus fund is to make available the required fund for the various
activities of mine closure at the time of actual closure of the mine. In Proposed Ghonsa
Expansion OC Project the fund required for various activities for mine closure has already
been provided in EMP/PR. These are provided in the approved PR of the project.
The fund provisions indicated above takes care of all the requirements of mine closure
and has the commitment of the highest authority of the Company.
Conclusion:
It can be seen from the points mentioned above that the activities required for mine
closure are already covered in the EMP/PR of the mine. These activities are not a one-
time activity to be undertaken at the end of life of mine. Most of the activities are carried
out regularly over the total life span of the mine.
The project under consideration is in all likelihood get further extended towards dip which
will give an additional lease of life to the project. As such, the actual closure plan can be
finalized only at the end of expansion project.
Although no statutory guidelines exist on financial provisioning for mine closure activities
as yet, but financial provisions as foreseen on date for the project under consideration
within the limits specified has been made in the report to undertake mine closure
activities.
45. Capital cost of the project (in Rs. Lakh) : 699.00
(Based on latest estimate)
46. Cost of environmental protection measures : As shown below (in Rs. Lakh)
ENVIRONMENTAL COST PROJECTION
A provision of Rs. 9.00 lakhs has been made against environment protection and details
are as under :
Sl No. Particulars Amount ( Rs. Lakhs)
1 Environmental Monitoring 2.00
2 Plantation /Green belt
development/biological reclamation
5.00
3 Misc. Actvities/Maintenanace/
Statutory Fees etc.
2.00
TOTAL 9.00
b) In addition Rs. 3.0/t (every year) of coal under revenue head has been kept.
It is felt that the above provisions are adequate to handle the existing pollution load.
However, if need arises, necessary action along with provision of fund shall be
accordingly taken.
47. Amount earmarked for socio-economic : As per the CSR Policy of the Company
welfare measures for the nearby villages Details given in Chapter – VI.
other than R & R plans.
48. Public Hearing
a. Date of advertisement : 07.07.2011
b. Newspapers in which the advertisement appeared : The Hitavada &
Daily Lokmat(Marathi)
c. Date of public hearing (DD/MM/YY) : 09.08.2011
d. Public Hearing Panel chaired by & members present : Addl. District Magistrate
Yaavtmal & MPCB
Officials
e. No. of people attended the public hearing meeting : Panel Members &
and number of people from the lease area No. of villagers - 250
(approx.)
f. Summary/details of public hearing in tabular form :
As directed in the TOR, Public Consultation as per EIA Notification, 2006 has been
conducted by Maharashtra Pollution Control Board. For this purpose, Draft EIA/EMP
document as per the generic structure and with due compliance of all the conditions
issued in TOR dated 08.07.2009 (Copy enclosed as Annexure – I) was prepared and
submitted to Regional Officer, MPCB Regional Office, Nagpur.
The Public Hearing was conducted on 09.08.2011. After conduction of Public Hearing by
MPCB as per procedure laid down in EIA Notification, 2006 and receipt of the
recommendations from MPCB, this final EIA.EMP has been prepared for submission to
MOEF for obtaining EC. The Minutes of Meeting as received from MPCB, Nagpur is
attached herewith as Annexure – III.
S.N. COMMENTS / SUGGESTIONS OF
PARTICIPANTS WCL’s REPLY
1 Shri. Vijay Raju Jivane, Grampanchayat
Member, Ghonsa stated that at
present WCL authorities do not have
specific information about the names
of farmers and their family members
whose land is to be acquired for the
expansion project. WCL authorities
should explain in the public hearing
about the method adopted for land
acquisition. He stressed that
compensation for land should be given
according to market rates. He asked
about rehabilitation policy of Coal
India Ltd. He demanded for one
employment per 2 acre of land
acquired and the rate should be equal
to rate decided by State Government
plus additional Rs. 5 lakhs per acre.
Shri. Sachin Patil, (WCL) replied that land
is acquired under Land Acquisition Act or
Coal Bearing Act of Central Government.
Under this Act the cost of land is decided
by State Authority as per market value.
He further said that as per RR policy of
Coal India Ltd., employment is given to
the land looser having land of 2 acres or
above. In case of those who opted for
one time compensation in lieu of
employment, are given Rs. 5 lakhs per
acre of land.
2. Shri. Dilip Kakde, Zilha Parishad, stated
that the public hearing for this
expansion project was cancelled
before due to non-fulfillment of
commitments made by WCL authorities
and same commitments especially
about employments are still not fulfilled.
He complained that heavy dust
generation takes place due to mining
and transportation activities and water
sprinklers are not operated regularly.
He alleged that WCL authorities always
give their assurance for developmental
works but never fulfill it. He informed
that one handicap person Shri. Anil
Raut, whose land was acquired, is still
waiting for the employment since
many years.
He registered his oppose for the public
hearing and requested people to
support him. He stated that rainwater
will enter into Ghonsa village and thus
will affect the agricultural land of the
village. WCL authorities should give
assurance regarding this. He alleged
that coal carrying trucks were not
covered by tarpaulin which leads to
spillage of coal. The Air Quality
Monitoring Machine is not operated for
24 hours as per norms and appealed
Shri. Ramteke (WCL) briefed the present
status of works done by WCL as
committed during the previous public
hearing. He stated that road from
Mukutban to Ghonsa is repaired and the
expenditure incurred for the same is Rs. 22
lakhs. A total compensation of Rs. 1.77
lakhs were paid to the affected farmers.
For controlling air pollution, new eight
water sprinklers are provided on internal
roads and are in operation.
He further stated that no overloading of
trucks is allowed from the coalmine. If
found, they have stopped and allowed
only after taking permitted load and that
too covered with tarpaulin. The rainwater
harvesting scheme was introduced into
nearby villages for conservation of water.
Total Rs. 40 lakhs was spent towards
developmental works in nearby villages
by WCL. Mine water is not being
discharged directly into river. Three
numbers of check dams has been
erected. A drain of 150 meter has been
cleaned and culvert has been erected
into river. Sedimentation tank is provided
for the removal of solids from mine
discharge.
that the air monitoring machine should
be operated at his house to know the
air quality. He further stated that
proceedings of the previous public
hearing were not made available to
Zilha Parishad. He alleged that mine
discharge water is released into river
without any treatment. He requested
Chairman for considering above issues
and not to give permission for
expansion of coalmine.
3. Shri. Dilip Kakde stated that the
information given by WCL authorities is
not acceptable by them. The
untreated black water is released into
river due to which animals and people
are suffering. He alleged that video
recording can be done for one day.
He demanded that Government
officials should verify whether WCL has
undertaken these works or not.
Shri. Sachin Patil (WCL) replied that
proposal for giving employment to Shri.
Anil Daulat Raut has been forwarded to
the WCL Head Quarter as a special case.
Delay is taking place but Shri. Raut will
definitely get a job in WCL.
4. Shri. Kakde stated that CMD, WCL has
committed that Shri. Anil Raut will get
employment within 8 days, but till date
no employment has been given. He
asked that how long back . Raut was
acquired?
Shri. R.N. Panda (WCL) replied that there
is no provision for employment to
Handicapped person in WCL. However,
Shri. Raut will be given employment as a
special case.
Chairman Shri. Rajendra Deshmukh
stated that if the . Raut was acquired,
he is entitled for the employment in
WCL. Hence, he should get the
employment as early as possible.
5. Shri. Vasudev Vidhate stated that WCL
authority always give formal replies to
the questions asked during public
hearing. They should give specific
answers to the questions. There is policy
of Central and State Government
regarding employment to
handicapped persons and since WCL is
in , they should follow the said policy.
Throughout the country, there is
reservation to the handicapped
persons for employment. On the day
WCL acquired. Raut, he became
eligible for the employment in WCL. His
income source i.e. land was taken
away from him and employment is not
provided. He requested Chairman to
instruct WCL authority to act on this
issue of employment to Shri. Raut first
Shri. Sharma (WCL) replied that CMD,
WCL has already taken note of this case.
and then conduct the public hearing.
6. Shri. Vidhate objected that WCL
authority is not giving proper answer.
He demanded reply from responsible
officer who have authority for taking
decision in this regard.
Chairman Shri. Deshmukh stated that
although this issue is not related with
environment, it is concerned with
livelihood of people and can’t be
neglected. He directed Shri. H.S. Khare,
CGM, WCL, Wani North Area to reply
this issue.
Shri. H.S. Khare (CGM) replied that in this
case land compensation has been given
and if the person is physically not fit for
employment, monitory compensation
can be given. Shri. Raut refused to
accept the monitory compensation. He
informed that proposal of employment to
Shri. Raut has been forwarded to HQ with
strong recommendation and CMD has
committed to give him employment. He
assured that Shri. Raut will get
employment.
Shri. Kakde stated that CMD assured
before six months that Shri. Raut will get
employment within 8 days. He asked
that there is provision of employment to
physically handicapped persons in
State and Central Government
polieies, then how WCL authorities can
deny the proposal of Shri. Raut.
7. Shri. Kakde alleged that the road is not
completely repaired. Although, WCL
authorities are claiming that Rs. 22 lakhs
have been spent on repairing of the
roads, all ditches were not filled.
Chairman Shri. Deshmukh instructed
WCL authorities not to give false
assurance and information. He further
instructed to initiate concrete actions
like water sprinklers on road edges
should be in working condition and
operated regularly. Funds allotted for
specific works should be utilized
properly.
Shri. Ramteke (WCL) replied that as water
pump was stolen, due to which water
sprinkling was affected and assured the
regular water sprinkling on the roads.
8. Shri. Vasudev Vidhate alleged that
MPCB do not have right to conduct
public hearing, because public hearing
should be conducted within 45 days
from receipt of application and MPCB
is failed on this ground and thus new
agency has to conduct the public
hearing.He further stated that if people
want to lodge complaint against such
issues, they have to go to , because
National Green Tribunal is located
there. He requested that a Bench of
National Green Tribunal should be
made available at for peoples ease.
He further said that there are about 45
(existing and proposed) mines in this
Shri. N.G. Nihul, Regional Officer, MPCB,
Chandrapur stated that generally such
things didn’t happen. But still people can
send their say in this regard to Ministry of
Environment & Forest, if anybody’s written
objection is not reflected in the minutes.
region. When any land acquisition is
proposed for any mine or industry, it
should be discussed in detail with land
owners (i.e. farmers) of that area giving
them detailed information in respect of
lease of land. The land owners should
be taken into confidence before land
acquisition. Further, dump is not
allowed to dump within 500 meters
from the river bank or road.
He stated that EIA report published in
English and Environmental issues
mentioned in it are not understood by
the people. He demanded that under
such situation, one facilitator should be
appointed either by Government or by
industry to provide information
mentioned in EIA report to the people.
He stated that notice for public hearing
is being published in newspapers by
MPCB with an appeal to people for
submitting views, questions, objections
etc. regarding the proposed project
and accordingly he had submitted his
letter during previous public hearing to
the Chairman. However, the details of
same letter were not mentioned in the
proceedings of that public hearing by
MPCB. He informed that the said
project will get Environmental
Clearance by MoEF. He stated that
due to such issues people didn’t have
faith in MPCB.
9. Shri. Dinkar Pawde, President, Wani
Town BJP stated that due to this project
about 21 villages are getting affected.
There is already issue of increase in air
and water pollution. He informed that
residents of Kumbharkhani village are
present. Chairman and members of
public hearing panel can ask these
people whether they are getting justice
or not.
He stated that WCL is getting benefited
by Rs. 2100 crores and State
Government is benefited by Rs. 700
crores from this project. Four more
projects are coming in this area in
future, due to which company will be
benefited by Rs. 5000 crores. Thus, he
demanded that WCL should spend at
least Rs. 6 crores for pollution control
Shri. R.N. Panda, Project Officer, GOCP
(WCL) replied that WCL authorities had
already committed in Gramsabha that
there will be no damage to the houses as
will conduct controlled blasting. Still if
some damages are observed then the
proper action will be initiated for
controlling the effects of blasting.
Shri. H.S. Khare, CGM, WNA (WCL) replied
that there is provision of closing of blast
area by net, which will be implemented.
and environmental protection.
He further stated that local WCL
officers are favorable for the
development of villages and pollution
control and are co-operative with the
villagers, whereas officers of HQ of WCL
do not co-operate with the people. He
gave an example that WCL authorities
send the proposal of repairing of Wani
– Ghonsa road to HQ people’s
demand, whereas it was refused by
their Head Office. He further said that
WCL authorities assured us for use of
low power explosives blasting. Still the
houses in Kumbharkhani village got
cracks in the walls due to vibrations.
10.
Shri. Pawde informed that the Divisional
Commissioner conducted meeting at
Wani and instructed that the work of
Wani – Ghonsa road should be
undertaken collectively by WCL, coal
washeries of this region and concerned
Government authority. He demanded
urgent attention towards this issue
because this work is not yet started.
Shri. Pawde stated that due to blasting,
cracks are taking place to the houses.
In such situation it is difficult to live in
village. He said that nearly 50 lakhs
tone coal is being transported from
Wani Taluka every year to other power
projects of . People are interested in
giving land for the projects because
they are becoming wealthy. He
demanded price of Rs. 15 lakhs per
acre of land and demanded
compensation against the damages
occurred due to blasting in
Kumbharkhani and other villages.
Shri. Ramteke (WCL) replied that Divisional
Commissioner, had conducted the
meeting in this regard with authorities of
WCL, PWD & MPCB. During the said
meeting, Hon’ble Commissioner directed
that Mukutban – Ghonsa road will be
constructed for long life. This work will be
done under PPP model and PWD will
make the work plan and will take initiative
for this work as it is the Government body.
Shri. Ramteke informed that WCL didn’t
receive any letter from PWD in this regard.
Shri. R.N. Panda (WCL) replied that he will
assess the details about damages
occurred due to blasting and will initiate
proper action in this regard at the earliest.
He informed that WCL authorities are
waiting for the proposal from PWD
regarding construction of road.
11. Smt. Manda Chiwane, Sarpanch,
Grampanchayat, Borda stated that
Borda village has not received any
fund. The village does not have basic
facilities like drinking water and road.
Drinking water is contaminated with
minerals.
Shri. Ramteke (WCL) replied that due to
encroachments adequate land for
construction of road is not available in the
village. Water table is at low level in the
village. He informed that work of
submersible pump / tube well is awarded
and soon will be completed.
12. Shri. Ganesh Paigan, Deputy Sarpanch,
Borda said that clearing of
encroachment is internal matter of
village administration and it will be
cleared once the work starts. He
added that several times villagers had
submitted letter for tube well. But, no
fund has been provided for the same.
Shri. Bhalla, Deputy GM (Civil), WNA
(WCL) stated that for tarring, work order
has been already issued & work will start
as soon as the encroachment is removed.
Shri. Ramteke (WCL) stated that machines
for the construction work of road are not
able to go on site due to limited space.
On which, Chairman Shri. Deshmukh
stated that this work can be done
manually also without using heavy
machines.
13. Shri. Mendale stated that WCL should
make proper arrangement for drinking
water. He demanded for provision of
tube well in the village.
Shri. R.N. Panda (WCL) replied that
submersible pump will be installed this
year. Provision will be made for this from
the CSR fund.
14. Shri. Vasudev Vidhate demanded
justifiable reply regarding blasting and
safety zone from the persons who
prepared draft EIA. He said that this
project is adjoining to the Rasa village,
Ghonsa village and . Thus these two
villages and river are prone to the
damages due to blasting.
Chairman Shri. Deshmukh instructed
WCL authorities to explain details of
safety zone.
Shri. Sachin Patil (WCL) stated that safety
zone is of 500 meters from mine boundary.
15. Shri. Vidhate stated that OB dump is at
10 meters away from Zilha Parishad
School, which should be 500 meter
away i.e. out side the safety zone. Thus
the mining Act is violated. If the project
commences, there is danger to the life
of people of this region. He stated that
plan should be made in such way that
water should not enter into village
even if the flow of river is changed. He
asked that whether the rules regarding
embankment, which are going to lay,
will be followed or not.
Shri. Sachin Patil (WCL) stated that mine
plan is approved from DGMS and 500
meter distance is mandatory. He stated
that strict compliance of these criteria is
observed. He further said that the
embankment will be made according to
rules of DGMS.
16. Shri. N.G. Nihul, R.O., MPCB asked that
whether all work is being undertaken
according to rules / permission of
DGMS or not.
Shri. H.S. Khare, CGM, WNA (WCL) replied
that under Mines Act, work is being done
as per DGMS permission. If DGMS
authorities desires, they can impose
specific conditions.
17. Shri. Vidhate objected on mine plan
submitted by WCL officers and
questioned that how to know whether
this plan is correct or not. If the plan is
incorrect and mine work start as per
the incorrect plan, it may cause threat
Shri. Sachin Patil (WCL) stated that DGMS
gives permission only after taking all the
things into consideration, which are
shown on the CMPDI plan.
and damage to people and
environment. So actual details
regarding specific area defined for
mining, roads, agricultural land, houses
etc. should be shown in the plan and
made available to the people.
18. Shri. Vidhate asked to show road on
the mining plan.
Shri. R.N. Panda (WCL) showed the details
in the map and he stated that public
road is parallel to the mine boundary.
19. Shri. Vidhate asked for post monitoring
reports should be made available to
Grampanchayats by MPCB. He asked
that whether road and mine boundary
will be merged after the commissioning
of mine. He said that distance of school
from Ghonsa mine is mere 10 meters.
Shri. R.P. Singh (WCL) stated that the mine
boundary cannot be changed without
the permission of DGMS.
Shri. R.N. Panda (WCL) stated that
Ghonsa village is at a distance of 600
meter from mining area.
Shri. Meshram, Deputy Sarpanch,
Sonegaon demanded for proper
arrangement regarding drinking water
supply from WCL. He said that
Sonegaon village is located on the
bank of river, due to which village is
under threat of flood. He added that
Grampanchayat already sent proposal
for school & passenger shed to WCL.
But, response is not received from WCL.
He alleged that students of
Kumbharkhani village can’t go to
school because Kumbharkhani –
Ghonsa road is closed, due to which
villagers face lot of problems.
Chairman Shri. Deshmukh stated that
WCL authorities should provide proper
road to the villagers and instructed to
do this work at the earliest. He directed
Shri. Khare (WCL) to give time bound
commitment regarding this.
Shri. H.S. Khare (WCL) stated that
previously there was kachha road and 20
meter wide road was developed. He
committed that the repairing of road will
be undertaken within 3 weeks period.
49. Whether the following approvals*(wherever applicable) have been obtained ?
(i) Site clearance from MOEF : Not Applicable
(ii) Consent for Establishment’ from the : To be obtained for 0.60 MTPA
State Pollution Control Board.
(iii) NOC from Atomic Mineral Division : Not applicable
(iv) Mining plan approval from IBM/ : Not Applicable.
Ministry of Coal
(v) In case of existing mines, mining : Not Applicable
scheme approval from IBM
(vi) Forestry clearance under FCA, 1980 : Not Applicable
(vii) NOC from Chief Controller of : Existing Mine, already obtained.
Explosives
(viii) Commitment regarding availability/ : Not applicable as water
pumping of water from the concerned requirement will be met
authorities from mine pumped out water.
(ix) In case of ML area falling in notified areas : Not Applicable
of the Central Ground Water Authority
NOC from them.
[*Annex copies of approvals and number them]
50. Was / is there any court case relating : Not applicable
to the project or related activities ?
If so, provide details present status.
Verification: The data and information given in this proforma are true to the best of my
knowledge and belief.
Signature of the applicant*
with Full name & address
[*Owner or his authorized signatory]
Date:
Place:
Given under the seal of organization on
behalf of whom the applicant is signing.
Annexure - V
ENVIRONMENTAL STATEMENT
FOR THE YEAR APRIL, 2011 – MARCH, 2012
GHONSA OC MINE, WCL
CHAPTER - I
1.1 GENESIS
Vide Gazette Notification No. G.S.R.3289(E) dated 13th March,
1992, the Ministry of Environment & Forests, Govt. of India have made
provisions for Mandatory Environmental Statement as follows :
“Every person carrying on an industry, operation or process
requiring consent under Section 25 of the Water Act, 1974 or under Section 21 of the Air Act, 1982 or both or authorisation under the
Hazardous Water Rules, 1989 issued under the Environmental Protection Act, 1986 shall submit an Environmental Audit Report for the financial year ending 31st March in Form – V to the concerned State
Pollution Control Board on or before 30th September every year beginning 1993”.
In compliance with the above, the work of Environmental
Statement for Ghonsa Opencast Mine was entrusted with the Central
Mine Planning & Design Institute Limited by Western Coalfields Limited, Nagpur.
CHAPTER - II
SALIENT FEATURES OF THE PROJECT
1.
Name of the Project
GHONSA OC Mine
2.
Location
WCL, Wani-North Area, Distt : Yavatmal
State : Maharashtra
3.
Production
0.45 Mty
4.
Water Consumption
110.00 kl/day
5.
Raw Material Consumption :
(a)
(b)
Explosive
POL
2238.00 kg/day
4500.00 l/day
CHAPTER – III
BASIS FOR ENVIRONMENTAL STATEMENT
1.0 Water is not directly used during mining for coal production. It percolates into working area during mining operation. However, water is consumed for other
purposes; mainly for domestic supply, industrial supply. Part “B” of the proforma contains detailed break-up of water consumption.
2.0 Raw materials used in coal mining activities are explosives and POL for machines and automobiles, steel, timber, cement, etc.
3.0 Pollution discharged into water has been calculated on the basis of water analysis and identified water pollutants. The main pollutants in mine water
are suspended solids. The other sources of pollution in the effluent from various processes include oil and grease (from Workshop and CHP).
4.0 Ambient air quality is monitored to study the level of air pollution. CHP has been indicated as fugitive source in reports and mobile sources are HEMM
moving on haul road, blasting, exhaust from vehicles and HEMMs, loose materials of OB dumps and burning of coal.
5.0 Mining activity produces less quantity of hazardous waste; and it is shown in Part “D” of Form – V.
6.0 Solid waste produced from mining activities is overburden (OB) material. Recycling process of this material is normally done by suitably backfilling
the same in the extracted portion of the quarry. 7.0 The pollution abatement measures for the sake of Environmental Statement
are :
(i) Dust suppression by water spray; (ii) Afforestation; (iii) OB Dump Reclamation;
(iv) Water spraying to prevent burning of coal. 8.0 Items identical under Part “H” of the proforma are those items which the
Consultants have felt necessary which is also true for Part “I” in order to help Western Coalfields Limited to organise their abatement efforts for performing
mining activities without adversely affecting the environment.
CHAPTER – IV
FORM – V
PART - “A”
Sl. No.
Particulars
1. Name and address of the Mine Ghonsa OC Mine
(a) Place WCL, Wani North Area
(b) District Yavatmal
(c) Telephone No. C/o General Manager,
Wani North Area 07172-275215
(d) FAX No. -
2. Date of last Environmental
Statement Report submitted
30th September, 2011
PART - “B”
WATER & RAW MATERIALS CONSUMPTION
Table – (a)
Water consumption on Usage Pattern
Sl.
No. Particulars
1. Water Consumption (kl/day) :
(a) Process – Industrial :
(i) Dust suppression 60.00
(ii) Fire fighting 50.00
(iii) Workshop and others --
(iv) Green Belt --
(v) CHP Beneficiation --
(b) Domestic Purpose
(i) Domestic Use (service building)
--
(ii) Green Belt in Township
TOTAL 110.00 kl/day
Table – (b)
WATER CONSUMPTION AGAINST PRODUCTION (INCLUDING RECYCLED)
Name of the Product
Water Consumption
per unit of product (including recycled)
During the Previous
Financial Year 2011-12
During the Current
Financial Year 2012-13
COAL
102.66 l/t
of coal produced
110.00 l/t
of coal produced
RAW MATERIAL CONSUMPTION
Name of the
Raw Material
Name of the
Product
Consumption of Raw Material per Unit of Product
During the Previous
Financial Year 2011-12
During the Current
Financial Year 2012-13
Explosive
Coal
1.64 kg/t
1.83 kg/t
POL
Coal
3.30 l/t
3.66 l/t
PART - “C”
POLLUTION GENERATED
(Parameters specified in the consent issued)
1.
Pollutants
Quantity of Pollution
Generated
Percentage variation from
prescribed standards with reasons
(a)
Water
See Annexure I
Values of parameters are
within permissible limits.
(b)
Air
See Annexure I
Levels of air pollutants are
within permissible
limits.
PART - “D”
HAZARDOUS WASTE
(As specified under Hazardous Waste/ Management & Handling Rules, 1989)
1.
Hazardous Waste
Total Quantity (kg)
During the Previous Financial Year
(2011-12)
During the Current Financial Year
(2012-13)
(a)
From Process (Oil & Grease)
NIL
NIL
(b)
From Pollution Control Facilities
(Sludge from ETP)
0.72 MT
0.72 MT
PART - “E”
SOLID WASTES
Total Quantity
During the Previous Financial Year
(2011-12)
During the Current Financial Year
(2012-13)
(Provision)
(a)
From Process Overburden)
2.18 Mm3
3.00 Mm3
(b)
From Pollution
Control Facility
Nil
Nil
(c)
(i) Quantity recycled or re-utilised within the
unit dumped on quarry void
0.21 Mm3
3.00 Mm3
(ii) Sold
Nil
Nil
(iii) Disposed (as external dumps)
1.97 Mm3
Nil
Mm3 = Million Cubic Metre.
PART - “F”
PLEASE SPECIFY CHARACTERISTICS (IN TERMS OF CONCENTRATION &
QUANTUM) OF HAZARD AS WELL AS SOLID WASTES AND INDICATE DISPOSAL PRACTICE ADOPTED FOR BOTH THESE CATEGORIES OF WATER.
- The hazardous waste is being disposed through :
(i) The sludge from ETP through land fill arrangement;
(ii) Oil and grease is disposed of through authorized/registered recyclers/re-refiner.
Solid wastes in the mine are in the form of overburden material which comprises of sandstone, conglomerates, sandy and clayey shales. Out of total OB material, 1.97 Mm3 has been dumped externally and 0.21 Mm3
OB has been dumped into quarry voids.
PART – “G”
IMPACTS OF POLLUTION CONTROL MEASURES ON CONSERVATION OF
NATURAL RESOURCES AND CONSEQUENTLY ON COAL PRODUCTION.
The brief summary of Pollution Control Measures taken for this mine is
as under :
G.0 In order to carry out mining operations in an environmentally, friendly
and planned manner, the sources of pollution were identified and measures were suggested to keep them within permissible limits.
G.1 SOURCES OF AIR POLLUTION
The likely sources of air pollution are as under :
- Drilling operation; - Blasting operation; - Loading and transportation of Coal/OB;
- Wind Erosion of Coal Stock/OB Dumps; - Haul Road/Coal Transportation Roads;
- Exhaust from vehicular movement. G.1.1 Measures for Control of Air Pollution
For control of air pollution, measures suggested are :
- Regular use of dust extraction devices while drilling holes for
blasting;
- Regular water sprinkling on coal faces, benches, coal stocks, black
topped metal roads and haul roads; - Measures of reclaiming OB dumps (Biological Reclamation) and
backfilling of the voids to the maximum possible extent.
- Tree plantation along the periphery of the quarry, CHP, around other service buildings along the sides of permanent haul road and
open land;
- Regular cleaning of coal transportation road.
G.1.2 Implementation Status
- Water sprinkling is done on coal stock and before its transportation on coal faces, benches and haul roads;
- Regular water sprinkling is done before drilling and coal stock and roads
G.2 WATER POLLUTION
G.2.1 Sources of Water Pollution
The anticipated sources of water pollution are as under :
- TDS and TSS due to mining operation present in the mine water
(mainly coal particles);
- Oil and Grease from Workshop/CHP Effluent.
G.2.2 Water Pollution Control Measures
-The main pollutant responsible for water pollution is suspended solids. Sedimentation pond should be provided to take care of this pollutant.
G.2.3 Implementation Status Some portion of mine water is being tilized for dust suppression. The excess water is retained in the sump before discharged into surface body.
G.3 NOISE POLLUTION G.3.1 Sources of Noise Pollution
The sources of noise pollution are as under :
- Drilling Operation; - Blasting Operation; - Operation of Shovels and Dumpers;
- Workshop.
G.3.2 Noise Pollution Control Measures suggested
The measures for reduction of noise level as envisaged in the EMP are as under :
- Selection of mining equipments so as to keep noise level below 85 dB(A);
- Provision of Ear Mufflers for operators exposed for long duration of
time;
- Provision of green belt around Workshop, CHP and
other sensitive areas;
- Limitation of blasting operation between 12.00 Noon to 2.30 PM.
G.3.3 Implementation Status
- Mining equipment are kept in good condition to reduce noise level.
- Blasting operation is done during 12.00 Noon to 2.30 PM;
- Machines are kept in good conditions to reduce noise.
PART – “H”
ADDITIONAL INVESTMENT PROPOSAL FOR ENVIRONMENTAL PROTECTION IN THE AREA :
H.1 The project has incurred an expenditure on the followings in connection with environmental management in the area :
Sl.
No.
Particulars Amount
(Rs)
1. Water Cess Nil
2. Consent Fees 2,65,000.00
3. Air, Water, Noise Quality
Monitoring
Cost included with
Kumbharkhani UG
4. Others (JVS (MPCB), Sprinkling of
water)
80,000.00
H.2 Future Programme
The project has incurred an expenditure on the following in connection
with the environmental management in the area: - 8750 nos tree plantation will be done over 3.50 ha area.
Sl.
No.
Particulars Amount
(Rs)
1. Air Pollution Control Measures 12,00,000.00
2. Plantation 10,00,000.00
3. Water Cess 10,000.00
4. Consent Fees Valid up to 2013.
5. Air, Water, Noise Quality
Monitoring
Cost included with
Kumbharkhani UG
6. Others (JVS (MPCB), Sprinkling
of water)
1,00,000.00
PART - “I”
MISCELLANEOUS
ANY OTHER PARTICULARS IN RESPECT OF ENVIRONMENTAL PROTECTION &
ABATEMENT OF POLLUTION.
- Regular pollution control measures should be continued.
– oOo –
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : JUN.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2011 06.04.11 - 07.04.11 185 36 < 6 < 6 MAY 2011 22.05.11 - 23.05.11 185 81 < 6 < 6 JUN. 2011 07.06.11 - 08.06.11 96 45 < 6 < 6 JUN. 2011 22.06.11 - 23.06.11 69 32 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
APR. 2011 06.04.11 - 07.04.11 138 38 < 6 < 6 APR. 2011 22.04.11 - 23.04.11 156 35 < 6 < 6 MAY 2011 08.05.11 - 09.05.11 173 65 < 6 < 6 MAY 2011 22.05.11 - 23.05.11 141 36 < 6 < 6 JUN. 2011 07.06.11 - 08.06.11 140 40 < 6 < 6 JUN. 2011 22.06.11 - 23.06.11 44 20 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in Ghons a Village
18290
155 187115 155
185 185 96 690
200
400
600
AP R . AP R . MAY MAY JUN. JUN.Y ear-2010
Y ear-2011
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : SEP.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JUL. 2011 06.07.11 - 07.07.11 40 19 < 6 < 6 JUL. 2011 23.07.11 - 24.07.11 53 23 < 6 < 6 AUG. 2011 06.08.11 - 07.08.11 67 29 < 6 < 6 AUG. 2011 22.08.11 - 23.08.11 56 23 < 6 < 6 SEP. 2011 23.09.11 - 24.09.11 37 14 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
JUL. 2011 06.07.11 - 07.07.11 30 14 < 6 < 6 JUL. 2011 23.07.11 - 24.07.11 41 20 < 6 < 6 AUG. 2011 06.08.11 - 07.08.11 181 61 < 6 < 6 AUG. 2011 22.08.11 - 23.08.11 62 27 < 6 < 6 SEP. 2011 04.09.11 - 05.09.11 32 11 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in Ghons a Village
19 34 20 46 28 3744 53 67 56 370
200
400
600
Jul. J ul. Aug. Aug. S ep. S ep.Y ear-2010
Y ear-2011
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2011
NAME OF THE AREA : WANI NORTH Q.E. : DEC.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2011 21.10.11 - 22.10.11 50 13 < 6 < 6 NOV. 2011 21.11.11 - 22.11.11 143 37 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM RPM NOX SO2
OCT. 2011 09.10.11 - 10.10.11 81 36 < 6 < 6 OCT. 2011 21.10.11 - 22.10.11 176 38 < 6 < 6 NOV. 2011 05.11.11 - 06.11.11 71 28 < 6 < 6 NOV. 2011 21.11.11 - 22.11.11 182 82 < 6 < 6 DEC. 2011 23.12.11 - 24.12.11 84 34 < 6 < 6
PERMISSIBLE LIMIT 200 100 80 80
S P M L evel in Ghons a Village
73 37 6050 143
0
200
400
600
Oct. Oct. Nov. Nov. Dec . Dec .Y ear-2010
Y ear-2011
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2012
NAME OF THE AREA : WANI NORTH Q.E. : MARCH.
NAME OF THE PROJECT : GHONSA OC
1. Ghonsa Village : WNGOA--1
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN. 2012 20.01.12 - 21.01.12 140 70 3 2 FEB. 2012 06.02.12 - 07.02.12 129 57 2 2 FEB. 2012 21.02.12 - 22.02.12 75 23 2 1 MAR. 2012 05.03.12 - 06.03.12 106 12 2 2 MAR. 2012 22.03.12 - 23.03.12 184 58 3 3
PERMISSIBLE LIMIT 200 100 80 80
2. Kumbarkhani Colony / Guest house
: WNGOA-2
( 24 hourly values in μg/m
3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN. 2012 20.01.12 - 21.01.12 85 42 2 2 FEB. 2012 06.02.12 - 07.02.12 187 91 4 3 FEB. 2012 21.02.12 - 22.02.12 112 33 3 2 MAR. 2012 04.03.12 - 05.03.12 175 63 4 3 MAR. 2012 22.03.12 - 23.03.12 187 89 4 3
PERMISSIBLE LIMIT 200 100 80 80
SPM Level in Ghonsa Village
64 85
140 129 75 106184
0
200
400
600
JAN. JAN. FEB. FEB. MAR. MAR.Year-2011
Year-2012
CO MONITORING DATA ( All values are given in μg/m
3)
Sl.
No. Monitoring Location Monitoring Date
Observed
Value
NAAQ
Standards (1
hour)
1.
Ghonsa village
06.03.12 < 114.3 4000
2.
Kumbarkhani Colony
06.03.12 < 114.3 4000
Annexure - VI
Ghonsa OC (0.45 MTPA with 128.79 ha)
Compliance of EC Conditions
EC accorded vide letter no. J- 11015/165/2009- IA.II(M)
dated 29th
February, 2012.
SPECIFIC CONDITIONS
S.N. Conditions
Status of Compliance
i. No Washery shall be established within the ML without prior environmental clearances from this Ministry.
Noted. There is no such proposal at present nor envisaged in near future. However, the directive of Ministry shall be followed before taking up any such job.
i Top soil should be stacked properly with proper slope at earmarked site(s) of the two topsoil dumps shall not be kept active and shall be used within a year of its generation for reclamation and development of green belt.
Topsoil is being stacked separately as shown on the plan having height of 20.00 meters, covering an area of 7.00 ha. The top soil is being continuously re- used for reclamation purposes.
iii. The embankment constructed along the river boundary shall be of suitable dimensions and stabilized with plantation so as to withstand peak water flow and prevent mine inundation.
The embankment has been constructed along river boundary after taking due permission from Directorate General of Mines Safety (DGMS) and the height above the HFL is maintained as per the provisions of Coal Mines Regulation, 1957 and allied Technical Circulars issued by DGMS. The dimension and construction of embankment takes into account the peak water flow to prevent any danger to the mine from inundation due to inrush of surface water. Further, to increase the strength and stability of the embankment, plantation is also being taken up.
iv OB dumps should be stacked at the existing earmarked external OB dumpsite(s) only The ultimate slope of the dump shall not exceed 28 degree. Bamboo and other native species shall be planted on OB dumps for slope stability. Monitoring and management of the reclaimed dumpsites shall continue until the vegetation becomes self sustaining. Compliance status should be submitted to the Ministry of environment & Forest and its Regional Office at Bhopal on yearly basis..
There is only one external OB dump and the excavated OB is being stacked at the earmarked site only. The dump is still active as such plantation activities are yet to be taken up. The ultimate slope of the dump will be maintained.
v Catch drains and siltation ponds of
appropriate site should be constructed to arrest size and sediment flows from soil, OB and mineral dumps. The water so collected should be utilized for watering the mine area, roads, green belt development, etc. The drains should be regularly desilted and maintained properly. Garland drains (size, gradient & length) and sump capacity should be designed keeping 50% safety margin over and above the peak sudden rainfall and maximum discharge in the area adjoining the mines site, sump capacity should also provide adequate retention period to allow proper settling of silt material. Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation should be based on the rainfall data.
Catch drains around OB dump as well as around the quarry has been made which are desilted before onset of every monsoon. These catch drains arrest the flow of sediments and silt from the external OB dump. The size of the catch drains is adequate to arrest the flow of silt and sediments. In addition cross – drainage has been provided along the Overburden benches which carry all the silt and sediment. The water through cross drainage along OB benches & coal benches accumulate in the mine sump. The sump of adequate capacity, considering peak rainfall has been provided at the floor of the excavation which gives initial settlement of suspended particles. The water then is being pumped out on surface & led into surface sedimentation tank. The treated water is being utilized for dust suppression, watering of plants, washing of HEMM etc. In order to check run off & flow of silt from OB, dumps , as given in the condition above, proper garland drains/catch drains have been made around OB. Dump periphery these drains are desilted before onset of every monsoon, Moreover, cross drainages have been provided in the OB, benches to guide entire seepage water into the main mine sump made at the floor or the seam, the sump capacity is adequate enough to provided siltation of suspended silt material at the floor of the sump. As such, separate retaining wall is not required.
vi Crushers at the CHP of adequate capacity for the expansion project shall be operated with high efficiency bag filters, water sprinkling system shall be provided to check fugitive emissions from crushing operations, conveyor system, haulage road, transfer points etc.
At present, the ROM coal is being dispatched directly as such there is no crushing involved.
vii i Drills shall be wet operated. Complied.
Viii The project Authorities shall ensure that the main approach roads are black topped and are properly maintained. A – 3 – tier green belt comprising of mix of native species shall be developed all along major approach roads and major haul roads.
The main approach road has been black topped and is being maintained properly. Three tier plantation shall be developed as the configuration of the mine is likely to get changed with addition of two more quarries (the proposal has already been considered by EAC but held up due to Forest Clearance) and the detailed plan has been prepared and will be implemented.
Ix The capacity of trucks used for transportation shall minimum 25 T trucks and shall be mechanically covered.
At present, there is no mechanically closed truck commercially available for coal transportation in our country. The 20 T trucks are being used with covering of tarpaulin. The matter was taken up by WCL with leading truck manufacturers of the country viz. Tata Motors, Ashok Leyland, Asia Motor Works. Various designs were developed and tried in the field but all trials failed at site.
X Controlled blasting shall be practiced with use of delay detonators and only during daytime. The mitigative measures for control of ground vibrations and to arrest the fly rocks and boulders shall be implemented.
Controlled blasting is being practiced as per permission obtained from DGMS. All mitigative measures are being taken for control of ground vibration and to arrest fly rocks and boulders.
xi. A progressive afforestation plan shall be implemented which includes reclaimed external OB dump and embankment area, backfilled area, along ML boundary, along roads and infrastructure, embankment and within vacant land and in township located outside the lease by planting native species in consultation with the local DFO/Agricultural Department. The density of the tress shall be around 2500 plants/ha. Massive plantation shall be carried out in open spaces in and around the mine and avenue plantation along the main approach roads to the mine.
External OB dump is still active and as such biological reclamation is yet to be taken up. The backfilled area for this quarry will be further extended with the addition of two more quarries in the near future (in the 2nd Phase)for which proposal has already been submitted to MOEF (but held up due to forestry Clearance). All reclamation works as per the plan will be implemented.
Xii No ground water shall be used for the mining operations.
No ground water is being used for the mining operations.
xiii Regular monitoring of ground water level and quality should be carried out b establishing a network of existing wells and construction of new peizometers. The monitoring for quantity should be done four times a year in pre-monsoon (April/ May), monsoon (August) post-monsoon (November) & winter (January) seasons Data thus collected should be submitted to the Ministry of Environment & Forests and the Central Ground Water Board, Regional Office quarterly within one month of monitoring.
The monitoring of ground water level four times a year in pre-monsoon (April/ May), monsoon (August) post-monsoon (November) & winter (January) and quality once in year by establishing a network of existing wells is being done through CMPDIL and report are enclosed herewith.
Xiv The Company shall put up artificial groundwater recharge measures for augmentation of ground water resource in case monitoring indicates a decline in water table. Project Authorities should meet water requirement of nearby villages in case the village well go dry due to dewatering of the mine.
As per the monitoring results, till date no decline of water level has been observed. The water requirement of nearby villages, in case the village well goes dry due to dewatering of the mine, will be met.
xv For monitoring land use pattern and for post mining land use, a time series of land use maps, based on Satellite imagery(on a scale of 1:5000) of the Core and Buffer Zone, from the start of the project until end of mine life shall be prepared once in 3 years (for any one particular season which is consistent in the time series) and the report submitted to MOEF and its Regional Office at Bhopal.
For monitoring land use pattern, maps based on Satellite imagery has been prepared starting from March 2011 and the same time scale will be continued for every three years. The March 2011 Report has been annexed herewith. -
xvi A final mine closure plan along with details of Corpus fund shall be submitted to the Ministry 5 years before mine closure for approval, in case dip side extension project is not planned/implemented.
The present proposal is involving only one quarry (ML Area 128.79 ha)out of the total three quarries planned for the total project. The TOR for the Total project (involving 293.25 ha) has already been obtained and Public Hearing for the same has been completed. The EAC has also recommended the project for environmental clearance subject to submission of copy of Stage – I FC. The present proposal does not involve any forest land but the total project involving three quarries involve forest land. The Forest Clearance proposal is under process at Maharashtra State Govt. and as soon as Stage – I FC is received it will be submitted to MOEF for formal issuance of EC for the Extension Project. As such final closure is not envisaged in near future.
xvii The project authorities shall in consultation with the panchayat of the local villages identify socio – economic and welfare measures under CSR to be carried out over the balance life of the mine. A budgetary provision of Rs 5.00 per tonne of coal shall be earmarked for CSR activities. The budget and expenditure thereon village – wise and activity – wise for CSR shall be displayed on WCL website and also included a part of the Annual Plan.
The socio – economic developmental as well as welfare activities are being taken up under CSR through consultation with the neighbouring villages. The works done till date is appended herewith for ready reference. Similar works will be carried out during the balance life also. CIL has already framed a Corporate CSR Policy applicable to all its subsidiaries including WCL. As per the Policy, Rs 5.00 Per tone is earmarked for undertaking CSR activities within 15 km of the project.
xviii The Company shall have a well laid down Corporate Environmental Policy approved by the Board of Directors. The Environmental Policy shall prescribe for standard operating process/procedures to bring into focus any infringement/deviation/violation of the environmental norms/conditions. To provide for checks and balances, the Company should have a well laid out system of reporting on non – compliances/violations of environmental norms to the Board of Directors of the Company and/or shareholders or stakeholders at large.
Coal India Limited has framed its “Corporate Environmental Policy – 2012” applicable to its all Subsidiaries including WCL. A copy of the aforesaid Policy is annexed herewith.
GENERAL CONDITIONS :
S.N.
CONDITIONS. STATUS OF COMPLIANCE.
i No change in mining technology and working plan should be made without prior approval of the ministry of environment and forests.
Noted for compliance. No change in Mining Technology and Working Plan has been made.
ii No change in the calendar plan including excavation quantum of coal and wastes/OB dumps should be made.
Noted for compliance. For enhancing the sanctioned capacity from 0.45 MTPA to 0.60 MTPA, fresh application is submitted.
iii Four ambient air quality-monitoring stations shall be established in the core zone as well as buffer zone for PM 10 , PM2.5, SO2 & NOx monitoring, location of the ambient air quality stations shall be decided based on the meteorological date topographical feature. Environmentally & ecologically sensitive targets in consultation with the state pollution control board.
The monitoring has been started functioning from the 2005 as per the EC granted in 2005 and monitoring was being done for SPM, RPM,SO2 & NOx as per the condition given in the EC. The PM10, SO2 & NOx are already being monitored and Sampling Machine for PM 2.5 is being procured by CMPDIL This will also be started shortly.
iv Fugitive dust emissions from all the sources should be controlled regularly monitored and data recorded properly. Water spraying arrangement on haul roads, (loading & unloading) points should be provided and properly maintained.
Fugitive dust emissions from all sources are being effectively controlled through water spraying arrangement and are being maintained properly.
v Data on ambient air quality (PM 10,PM 2.5, SO2 and NOx) shall be be regularly submitted to this ministry including its Regional Office at Bhopal and the State pollution control board/central pollution control board once in six months.
Reports are being submitted to MOEF and its Regional Office at Bhopal and also to State Pollution Control Board on quarterly basis.
vi
Adequate measures should be taken for control of noise levels below the limit of 85 DB (A) in the work environment. Worker engaged in blasting and drilling operations of HEMM.CHP etc. should be provided with near plugs/muffs.
The major sources of noise pollution in this O/C mine are operation of HEMM. Fortnightly monitoring of noise level is being done. One Station has been been fixed viz (i) Near Manager Office. The noise levels during day-to-day operations are controlled as per statute. Workers engaged in operation of HEMM are provided with appropriate earplugs, earmuffs. Workers are given proper training as per statute & refresher training is also imparted at regular interval. Further, Periodical Medical Examination once in five years is also done on each workmen.
vii Industrial wastewater (workshop and wastewater from the mine) should be properly collected treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th may 1993 and 31st December
Strata seepage water carrying all the silt and sediments through the OB benches gets collected at the mine sump made at the floor of the seam. The sump has got adequate capacity which allows significant retention period for settling of suspended particles. This is the first
1993 or as amended from time to time. Oil grease trap should be installed before discharge of workshop effluents.
stage settlement/treatment. The supernatant water from the mine sump is then pumped out from the mine and fed into the surface sedimentation pond. The water discharged from sedimentation pond is then let off for natural discharge. The quality parameters are monitored every fortnight & all parameters are monitored once in a year. There is no organic load nor there is any toxic element. All the other physic – chemical parameters are well within the permissible limits. There is no workshop at the site and hence there is no discharge of effluent from workshop.
viii Vehicular emissions shall be kept under control and regularly monitored. Vehicles used for transporting the mineral shall be covered with tarpaulin and optimally loaded till the mechanically closed trucks introduced by the Company.
All vehicles of the Company as well as the hired vehicles are having PUC Certificate. Vehicles used for transporting the mineral are covered with tarpaulin and optimally loaded. At present, there is no mechanically closed truck commercially available for coal transportation in our country. The 20 T trucks are being used with covering of tarpaulin. The matter was taken up by WCL with leading truck manufacturers of the country viz. Tata Motors, Ashok Leyland, Asia Motor Works. Various designs were developed and tried in the field but all trials failed at site.
ix Environmental laboratory should be established with adequate number and type of pollution monitoring and analysis equipments in consultation with the state pollution control board.
Well-equipped and approved environment laboratory exists at Nagpur, which is run by CMPDIL who carries all the work of environmental monitoring for the projects of WCL.
x Personnel working in dusty areas should wear protective respiratory devices and they should also be provided with adequate training and information on necessary safety and health aspects. Occupational health surveillance programme of the workers should be under taken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed.
Workers engage in industry areas are provided with appropriate dust mask However safety measures are being taken. Health aspects are taken care through regular Periodical Medical examination. The workers are given regular training on safety and health aspects. As per statute, Periodical medical examination is carried out for each employee once in every 5 years to detect any diseases so that appropriate actions can be taken.
xi A separate environmental management cell with suitable qualified personnel should be set-up under the control of a Sr. Executive, who will report directly to the head of the company.
At project level, the Environmental management cell headed by Sub Area Manager/ General Manager (M) and is assisted directly by Project Nodal Officer (Env), Chief General Manager (M) heads the cell at Area level and is assisted by GM (Op) & Area Nodal Officer (Env), GM (Env) heads the environment department at HQ/corporate level with a multi-disciplinary team of qualified & experienced Engineers. Reporting directly to Director (Tech), Project & Planning.
xii The funds earmarked for environmental protection measures should kept in separate account and should not be diverted for other purposes. Year–wise expenditure should be reported to the Ministry and its Regional Office located at Bhopal.
Funds are not being used for any other purposes. The expenditure both under Capital & Revenue head for the current year as well as progressive is given. A record register showing expenditure statement work-wise related to environment protective measures are being maintained.
xiii The regional office of this Ministry located at Bhopal shall monitor compliance of the stipulated conditions. The project authorities should extend full cooperation to the office(s) of the Regional Office by furnishing the requisite data/information/monitoring reports.
Noted
xiv A copy of the clearance letter will be marked to concerned Panchayat/local NGO, if any, from whom and suggestion/representation has been received while processing the proposal.
Already been complied.
xv State pollution control Board should display a copy of the clearance letter at the Regional office, District Industry Center and Collector’s office/Tehsildar’s office for 30 days.
Not applicable.
xvi The project authorities should advertise at least in two local newspapers widely circulated around the project, one of which shall be in the vermicular language of the locality concerned within seven days of issue of the clearance letter informing that the project has been accorded environmental clearance and a copy of the clearance letter is available with the state Pollution Control Board and may also be seen at web site of the Ministry of Environment & Forests at http://envfor.nic.in. and the copy of the same should be forwarded to the Regional Office of the Ministry located at Bhopal.
This has already been complied and copies of advertisement submitted to MOEF along with our earlier six monthly compliance reports
^^^^^^^^^^^^^^^^^^^^
Development works done in nearby villages under different schemes of WCL
Year Works Done Amount
(Rs. Lakhs)
Scheme
2004-05 Construction of Bus shelter, toilet and Hand pump
at Ghonsa village
2.54 SC/ST works
2005-06 Construction of stage for Adarsh High School at
Ghonsa village
1.98 CSR works
2006-07 Construction of two rooms for school building and
Hand pump at Dahegaon village
4.29 CSR works
Construction of concrete road (Internal village
road) in Dahegaon village
4.71 CSR works
Construction of concrete road (Internal village
road) in Mohurli village
1.19 CSR works
2007-08 Making concrete pavement for internal road at
Rasa village
2.18 CSR works
Making concrete pavement for internal road at
Mohurli village
2.40 CSR works
Making concrete pavement for internal road at
Ghonsa village
3.07 CSR works
Making concrete pavement for internal road at
Sonegaon village
2.50 SC/ST works
2008-09 Construction of concrete road (Internal village
road) at Rasa village
3.00 CSR works
Construction of concrete road (Internal village
road) at Borda village
2.00 CSR works
Making concrete pavement for internal road at
Kumbharkhani village
3.00 SC/ST works
2009-10 Internal concrete road at Suknegaon village 2.05 CSR works
Internal concrete road at Ghonsa village 2.10 CSR works
Internal concrete road at Kumbharkhani village 2.20 CSR works
Road side drain at Kumbharkhani village 0.93 CSR works
Internal concrete road at Ejasari village 2.02 SC/ST works
Internal concrete road at Kumbharkhani village 1.98 SC/ST works
2010-11 Concrete road at Ghonsa market 4.00 CSR works
Making concrete pavement for internal road at
Sonegaon village
3.00 CSR works
WBM road at Borda village 3.00 CSR works
Community hall at Ijasan village 3.00 CSR works
One no. hand pump at Ghonsa village 0.60 CSR works
One no. hand pump at Sonegaon village 0.55 CSR works
2 nos. hand pump at Kumbharkhani village 1.20 CSR works
Distribution of School Bags at Rasa, Kumbharkhani
& Ghonsa village
0.42 CSR works
Arrangement of Health Camp & distribution of
Blanket at Rasa village
0.40 CSR works
Total 60.31
Year Works Amount
(Rs. Lakhs)
Scheme
2011-12 WBM road at Rasa village 3.00 CSR works
WBM road at Kumbharkhani village 3.00 CSR works
Supply of 10 nos. Solar Light at Ghonsa village 1.55 CSR works
Sanctioned
in 2010-11
Supply of Tree guard at Rasa village 1.73 CSR works
2011-12 Construction of cement concrete road at
Ghonsa village
3.00 CSR works
Supply of Tree guard at Ghonsa village 1.75 CSR works
Construction of borewell with submersible pump
at at Rasa village
6.50 CSR works
Construction of cement concrete road at Rasa
village
3.00 CSR works
Approach road from Rasa to Gotegaon village 6.00 CSR works
Construction of cement concrete road at
Kumbharkhani village
3.00 CSR works
Construction of underground drain at
Kumbharkhani village
2.50 CSR works
2 nos tubewell with submersible pump at
Kumbharkhani village
8.00 CSR works
Construction of tubewell with hand pumps at
Dahegaon village
0.70 CSR works
Construction of concrete road at Dahegaon
village
3.50 CSR works
Construction of concrete road at Shakra village 3.50 CSR works
Construction of community centre at Shakra
village
8.00 CSR works
Construction of concrete road at Sonegaon
village
4.00 CSR works
One no hand pump at Sonegaon village 0.70 CSR works
Construction of concrete road at Maregaon
(Korombi) village
3.50 CSR works
Arrangement of inter village volleyball
tournament at Ghonsa village
Total 66.93
Annexure - VII