How many documents do you need
• A survey showed that we had 1000 + documents that governed the building of roads and railways
• The content was a mixed bag of odds and ends• Clarity and easy use • Can one make some saving in this?
![Page 3: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/3.jpg)
3
How Trafikverket is looking at the documents
General requirements
National regulations
Technical requirements and specifications
Advice
![Page 4: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/4.jpg)
4
General requirements
National regulations
Technical requirements and specifications
Advice
HandbooksInformation
In every project and in every stage of the process
Designers, contractors, project leaders
Several
Work done by the Transport Agency
A lot is going on…
![Page 5: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/5.jpg)
5
What areas?
1. Planning
2. Bridge and Tunnels
3. Power
4. Roads and Rail-substructure
5. Rail - superstructure
6. Signal
7. Traffic management
8. Tele
9. Road and rail – geometric design
10. Documentation
![Page 6: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/6.jpg)
6
Who is doing the work?
Trafikverkets expert group
Project manager for each area
TRAFIKVERKET CONSULTANTS
Consultants project manager
Steering comitte @ Trafikverket Project coordinator
Client board of directors
![Page 7: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/7.jpg)
7
Area 4: Roads and Rail - substructure
• Pavement design• Geotechnical engineering• Railway substructure• Dewatering and drainage• Road equipment
• Started out with approx. 50 different documents• Goal is set at 2 – 6 documents
![Page 8: TMALL 0143 Presentation engelsk v 1.0 1000 to 30 Tomas Winnerholt](https://reader035.vdocuments.site/reader035/viewer/2022062517/56649f335503460f94c4f1ec/html5/thumbnails/8.jpg)
8
Area 4 has reached half way
• We have made a first rough cut and divided everything into – National requirements– Requirements/Specifications– Advice– Handbook/Information
• Structural work on the documents is beeing done– Table of content– Definitions
• Good and useful discussions • Should work equally good regardless of B, DB or DBOM type of
projects