tlalocnet ear-1338091 annual report · tlalocnet 2014-2015 annual report 1 tlalocnet ear-1338091...

11
TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report covers TLALOCNet project (EAR-1338091) “MRI: TLALOCNet - Development of a continuous GPS-MET array in Mexico for atmospheric, climatic, and seismotectonic research in the Americas” activities for the time period from September 1, 2014 to August 31, 2015. TLALOCNet is a collaborative project with multiple institutional PIs, under a single award from the National Science Foundation to UNAVCO on August 16, 2013. The project is directed by M. Meghan Miller, as PI, with Glen Mattioli, Enrique Cabral, Chuck DeMets, and Yolande Serra acting as Co-PIs. Glen Mattioli is acting as Project Director in his role as Director of Geodetic Infrastructure at UNAVCO; Karl Feaux is the Project Lead in his role as the GPS Operations Manager for the PBO, and John Galetzka is the Project Manager. Figure 1. TLALOCNet operating and planned stations: 14 installed NSF cGPS-Met stations (yellow dots) and 11 planned stations (red dots), which remain to be installed. Data from 13 UNAM contribution stations (green dots) will be included in the TLALOCNet archives. Other NSF-funded stations, from COCONet (orange dots) and the PBO El-Major Cucapah Earthquake (blue dots) projects also are shown on this map.

Upload: others

Post on 31-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

1

TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report covers TLALOCNet project (EAR-1338091) “MRI: TLALOCNet - Development of a continuous GPS-MET array in Mexico for atmospheric, climatic, and seismotectonic research in the Americas” activities for the time period from September 1, 2014 to August 31, 2015. TLALOCNet is a collaborative project with multiple institutional PIs, under a single award from the National Science Foundation to UNAVCO on August 16, 2013. The project is directed by M. Meghan Miller, as PI, with Glen Mattioli, Enrique Cabral, Chuck DeMets, and Yolande Serra acting as Co-PIs. Glen Mattioli is acting as Project Director in his role as Director of Geodetic Infrastructure at UNAVCO; Karl Feaux is the Project Lead in his role as the GPS Operations Manager for the PBO, and John Galetzka is the Project Manager.

Figure 1. TLALOCNet operating and planned stations: 14 installed NSF cGPS-Met stations (yellow dots) and 11 planned stations (red dots), which remain to be installed. Data from 13 UNAM contribution stations (green dots) will be included in the TLALOCNet archives. Other NSF-funded stations, from COCONet (orange dots) and the PBO El-Major Cucapah Earthquake (blue dots) projects also are shown on this map.

Page 2: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

2

To date, UNAVCO engineering personnel have retrofitted 4 existing stations and installed 10 new stations (Table 1) for a total of 14 completed stations to date. Another retrofitted station—PZUL—will be rejected as a TLALOCNet station because of deteriorating security and cellular data communications at the site. At least 8 additional stations will be installed by December 1st, 2015, and any remaining stations, including GUAX, should be installed and online by March 1st, 2016, which will bring the final total to 25 at the close of construction. Site Code Site Name Status

Latitude Longitude

USMX UNISIERRA, Moctezuma

Operational 29.82165 -109.68105

TNHM UNAM Geology, Hermosillo

Operational 29.081501 -110.970732

TNCU UACJ, Cuauhtemoc

Operational 28.450378 -106.794057

TNAM Central Universidad de las Valles, Ameca, former AMEC

Operational 20.535604 -103.966937

TNMS Mascota, former MASC

Operational 20.534774 -104.796761

TNCM Chamela Biological Station

Operational 19.498162 -105.044621

TNMR Maruata, former MMIG

Operational 18.288518 -103.345448

TNAT Acatlan, former OxNet station OXAC

Operational 18.130115 -98.041092

TNNX Nochixtlan, Magdalena Zahuatlán, near former OXNC

Operational 17.407534 -97.223888

TNPJ Pijijiapan Seismic Station PCIG

Operational 15.704550 -93.218903

TNBA Bahia de los Angles

Operational 28.971933 -113.547295

YESX Yecora Operational 28.378418 -108.919587

TNPP Puerto Penasco

Operational 31.335473 -113.631682

Page 3: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

3

TNTB Topolobampo Operational 25.605938 -109.052736

PZUL Telmex tower near Cruz de Loreto

Find alternative site. Logging GPS and MET data, but telemetry cannot be established due to changes with local cellular data provider.

20.064000 -105.507600

GUAX Isla Guadalupe Javier Gonzalez working on permission to visit island; GUAX VSAT burning in at TNBA since February 2015.

28.88 -118.29

17 Pena Colorada Mine, PENA

Find alternative site nearby? Site may be unstable. 19.390500 -104.101300

18 Purificacion Find alternative site in Coalcoman, Michoacan. Security situation has degraded.

19.664998 -104.636944

19 Infiernillo Get permission to build. 18.271536 -101.95597

20 Marquelia, OXMA

Ready to build in dry season. 16.710369 -98.611593

21 El Camaron, OXEC

Find alternative site to avoid costly VSAT telemetry. 16.520100 -96.054900

22 Galeras, OXTU

Ready to build in dry season only. 16.152516 -97.652251

23 Guevara, OXGU

Find alternative site to avoid costly VSAT telemetry. 16.631600 -96.910900

24 Putla, OXP2 Find alternative site due to landslide and erosion threat.

16.993163 -97.932754

25 Isla Maria Madre

Move site to different part of Mexico. VSAT not possible according to local contacts.

21.62 -106.56

Table 1. TLALOCNet cGNSS-Met station status (NSF-funded). The TLALOCNet project also involves a cost-share component from the Universidad Nacional Autónoma de Mexico (UNAM). UNAM is responsible for providing daily GPS data files to the UNAVCO archive for 13 stations. To date, UNAM has contributed data from 10 of the 13 stations shown in Table 2. The final three stations are expected to be operational in late 2015 to early 2016, during the final year of this three-year award. Site Code Site Name Status

Latitude Longitude

OXUM

Puerto Angel Operational 15.665317° -96.491614°

OXPE Puerto Escondido

Operational 15.888700° -97.075300°

OXTH Tehuantepec Operational 16.286300° -95.240800°

UTON Tonantzintla Operational 19.033500° -98.316200°

Page 4: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

4

UCOE Coeneo Operational 19.813200° -101.69440°

UTEO Teoloyucan In-Progress 19.741300° -99.188600°

UAGU Aguascalientes Operational 21.918500° -102.31500°

UXAL Xalapa Operational 19.516400° -96.924800°

TNMO Morelia Operational 19.648800° -101.22780°

UIGF Ciudad Universitaria

In-Progress 19.327000° -99.176000°

UJUR Juriquilla In-Progress 20.704200° -100.44700°

TNAL Altzomoni Operational 19.120300° -98.654200°

UGEO Guadalajara Operational 20.693900° -103.35000°

Table 2. TLALOCNet contributing stations from Universidad Nacional Autónoma de Mexico. PROJECT STAKEHOLDERS The project stakeholders include the following institutional, atmospheric, solid earth, ionospheric, and data center stakeholders: Institutional stakeholders • National Science Foundation (USA) • UNAVCO (USA) • Instituto de Geofísica, UNAM (México) • Servicio Sismologico Nacional, UNAM (México) • Centro de Ciencias de la Atmósfera, UNAM (México) • Conacyt (México) • Universidad de Guadalajara (México) • Instituto de Geología, UNAM (México) • Centro de Geociencias, UNAM (México) • Universidad Autónoma de Ciudad Juárez (México) • Conagua / Servicio Meteorologico Nacional (México) • Universidad de Sonora (México) Atmospheric Stakeholders • David Adams, UNAM • John Braun, University Center for Atmospheric Research • Carlos Minjarez, Department of Physics, Universidad de Sonora • Arthur Douglas, Creighton University • Christopher Castro, University of Arizona

Page 5: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

5

• David Gochis, NCAR • Seth Gutman, NOAA • Kirk L. Holub, NOAA • E. Robert Kursinski, University of Arizona • Rajul Pandya, UCAR • Luis Farfan-Molina, CICESE • Chris Watts, University of Sonora • Marek Zreda, University of Arizona Solid Earth Stakeholders • Rick Bennett, University of Arizona • Mike Brudzinski, University of Miami-Ohio • Vladimir Kostoglodov, UNAM • Javier Gonzalez, CICESE • Jorge Zavala, Servicio Mareográfico Nacional, UNAM • Carlos Valdés, Servicio Sismológico Nacional, UNAM • Rocco Malservisi, University of South Florida • Osvaldo Sanchez-Zamora, UNAM • Diego Melgar, University of California-Berkeley • Shannon Graham, University of Wisconsin-Madison • Christina Plattner, Ludwig Maximilians University-Munich, Germany • Mario Rebolledo-Vieyra, Centro de Investigacion Cientifica de Yucatan, A.C. • Estaban Vazquez, Universidad de Sinoloa • Andrea Walpersdorf, LGIT, University Joseph Fourier – Grenoble, France • Marco Guzman-Speziale, Centro de Geosciencias, UNAM • Alejandro Gonzalez, University of California-San Diego Ionospheric Stakeholders • Roman Pérez, UNAM • Tim Fuller-Rowell, CIRES, University of Colorado, SWPC, NOAA

Regional Data Center Stakeholders • Bertha Márquez-Azúa, University of Guadalajara • Fran Boler, UNAVCO, Regional Data Center Liaison

OPERATIONS SUMMARY The major milestones for this reporting period (9/1/14 to 8/31/15) were the reconnaissance and the receipt of permits at twenty sites as well as the full execution of a Memorandum of Understanding between UNAVCO and UNAM. This MOU defines UNAM as the permit holder for all TLALOCNet sites, but gives UNAVCO personnel the authorization to work at these locations. Continued progress toward station installation occurred along with other preparation for final installations. There was only one required maintenance visit in the last year; no cases of vandalism occurred at any of the TLALOCNet stations.

Page 6: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

6

Other project operational highlights include:

• Started “Donation-to-UNAM #2” paperwork and shipping process of remaining heavy and expendable equipment in October 2014—delivered to UNAM in May 2015.

• Hired a Mexican contract worker, Luis Salazar Tlaczani, to assist UNAVCO with station installation and maintenance.

• Completed the installation of the Regional Data Center at the University of Guadalajara. • Completed installations of stations TNCM, TNMR, TNAT, TNNX, TNPJ, TNTB, TNPP,

TNBA, YESX, TNAM, TNMS, and PZUL. • Completed the network monitoring tools to assist managers and engineers in station

maintenance. On-going and other future work includes:

• Eight stations are scheduled for installation by December 1, 2015. • Remaining 3 stations will be installed by March 1, 2016. • Maximize the number of stations providing high-rate data (1 Hz) streams in real-time (<1

s latency). • Add meteorological instruments to all contributing stations. • Completion of the TLALOCNet webpage and initiation of live website.

Site and Schedule Changes A teleconference was conducted on October 17th, 2014 between the PIs, TLALOCNet project lead, and project manager to provide a project status report and decide on several site relocations. Two proposed sites In Guerrero (OXTP and PAPA) and one in Michoacan (CALC) were found unsuitable by John Galetzka, and after discussion, the PIs decided to shift those sites to locations in northwest Mexico (Topolobampo, Puerto Penasco, and GUAX). There were delays in the arrival of equipment donation #2 at UNAM before Easter 2015. The delays caused the schedule for these installations to be pushed back until fall 2015, when the weather is more agreeable for fieldwork. We anticipate that additional installations will resume in September 2015, and at least eight additional stations will be operational by December 1st, 2015. Any remaining proposed sites, including GUAX, should be installed and online by March 1st, 2016, which will bring the construction phase of TLALOCNet to a close. Regional Data Center For three days in early December 2014 in Boulder, UNAVCO Geodetic Data Services staff trained future COCONet and TLALOCNet Regional Data Center (RDC) operators in a GSAC and Dataworks software. In February 2015, UNAVCO staff delivered the TLALOCNet Regional Data Center system to U.S. Embassy in Mexico City using the Department of State diplomatic pouch service. The system consists of a virtual machine (VM) that has been provisioned with the Linux operating system and systems software including web server, web application server, ftp server, Java, Perl, Python, Dataworks, and MySQL, plus the GSAC database, GSAC software, and required synchronization scripts. The TLALOCNet RDC system now resides and is successfully operating at the University of Guadalajara.

Page 7: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

7

Table 3. TLALOCNet Status: Tasks completed in during this reporting period. In-Country Independent Contractor Luis Salazar was hired by UNAVCO as an independent contractor in May 2014 to perform various tasks related to GNSS station reconnaissance, permitting, installation, maintenance, and other activities in support of the NSF-funded TLALOCNet project. Luis has proven himself an invaluable team member, and always accompanies and assists UNAVCO field engineers, while they are working in Mexico. SCIENTIFIC EFFORTS: ACTIVITIES, SUBMITTED MANUSCRIPTS AND ABSTRACTS Kirk Holub from NOAA has agreed to process in real-time GPS PWV from TLALOCNet and other real-time stations in Mexico. The 2015 North American monsoon, which is currently underway, will be observed using the seven new TLALOCNet stations in northwestern Mexico, and those of several other stakeholder institutions. We anticipate that these observations and the GPS-derived PW products will provide an unprecedented data set for the academic atmospheric science community and other TLALOCNet stakeholders. Submitted and Published Manuscripts and Abstracts Misra, V., C. Wang, Y. Serra, K. Karnauskas, E. M. Ellinor, J. Sheinbaum, P. Chang, S. –K. Lee, B. Rosenheim, B. Kirtman, D. Enfield, E. D. Maloney, A. Kumar, G. Poveda, R. Fu, J. Jouanno, S. Berthet, A. Mishra, M. Bourassa, J. Candela, and J. Ochoa, 2015: The Intra-Americas Sea: Challenges and Opportunities to Understand North American Climate Variability and Predictability. Bull. Am. Meteorol. Soc., Submitted, 2015.

Serra, Y., D. K. Adams, C. Minjarez, C. Castro, J. Moker, A. Arellano, A. Quintanar, L. Alatorre, A. Granados, E. Vazquez and K. Holum, 2015: The North American Monsoon GPS Transect Experiment 2013. Bull. Am. Meteorol. Soc., Submitted, 2015.

Graham, S., C. DeMets, E. Cabral-Cano, V. Kostoglodov, B. Rousset, A. Walpersdorf, N. Cotte, C. Lasserre, R. McCaffrey, L. Salazar-Tlaczani. Slow slip history for the Mexico subduction zone: 2005 through 2011. Pure and Applied Geophysics, Submitted, 2015.

Baptiste, R., C. Lasserre, N. Cubas, S. Graham, M. Radiguet, C. DeMets, A. Socquet, M.

Cumulative Since Previous Report

Details From Current Year

Stations Installed New / Refurbished

10 new 4 refurbished

8 new 3 refurbished New: TNCM, TNMR, TNAT,

TNNX, TNPJ, TNTB, TNPP, TNBA Refurbished: YESX, TNAM, TNMS, PZUL (will be relocated)

Maintenance Visits

2 1 Troubleshoot TNPP

Page 8: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

8

Campillo, V. Kostoglodov, E. Cabral-Cano, N. Cotte, A. Walpersdorf. Lateral Variations of Interseismic Coupling along the Mexican Subduction Interface: Relationships with Long Term Morphology and Fault Zone Mechanical Properties. Pure and Applied Geophysics, Submitted, 2015.

Cabral-Cano, E., D. Solano-Rojas, T. Oliver-Cabrera, S. Wdowinski, E. Chaussard, L. Salazar-Tlaczani, F. Cigna, C. DeMets, J. Pacheco-Martínez, 2015. Satellite geodesy tools for ground subsidence and associated shallow faulting hazard assessment in central Mexico. International Association of Hydrological Sciences, Publication Series, Submitted, 2015.

Cabral-Cano, E., D. Solano Rojas, T. Oliver-Cabrera, S. Wdowinski, E. Chaussard, L. Salazar-Tlaczani, F. Cigna, C. DeMets, J. Pacheco, 2015. Subsidence and associated shallow faulting hazard assessment in central Mexico using InSAR and GPS. Fringe 2015 workshop. Advances in the Science and Applications of SAR Interferometry. ESA ESRIN, March 2015, Frascati (Rome), Italy.

Cabral-Cano, E., D. Solano Rojas, T. Oliver-Cabrera, L. Salazar-Tlaczani, S. Wdowinski, C. DeMets, J. Pacheco, 2014. Subsidence and associated shallow faulting hazard assessment in central Mexico using InSAR and GPS. Abstract G41A-0471 presented at 2014 Fall Meeting, AGU, San Francisco, Calif., 15 -19 Dec. 2014.

Galetzka, J., E. Cabral, L. Salazar-Tlaczani, D. Adams, Y. Serra, G. Mattioli, M. Miller, 2014. Development of the TLALOCNet GPS-Met Network in Northwestern Mexico: Supporting Continuous Water Vapor Observations of the North American Monsoon. Abstract A33A-3156 presented at 2014 Fall Meeting, AGU, San Francisco, Calif., 15 -19 Dec. 2014.

Cotte, N. and E. Cabral, 2014. Slow Slip Events and degree of coupling along the Mexican subduction zone in Guerrero and Oaxaca areas: role of the slab geometry and its lateral variations, spatio-temporal evolution, slip budget, determined from cGPS time series inversion using PCAIM code. Abstract S53C-4517 presented at 2014 Fall Meeting, AGU, San Francisco, Calif., 15 -19 Dec. 2014.

Galetzka, J., K. Feaux, E. Cabral-Cano, L. Salazar-Tlaczani, C. DeMets, D. K. Adams, Y. L. Serra, G. S. Mattioli, M. Miller, 2014. La Red Gps-Met Tlalocnet En México: Desarrollo Inicial. Reunión Anual Unión Geofísica Mexicana, Puerto Vallarta, Jal., 2-7 Noviembre 2014. Resúmen SE11-1.

DATA SUMMARY UNAVCO currently archives standard 15 sec hourly data files from 14 UNAVCO-built GPS-Met stations, and 10 Mexican-contributed GPS-Met stations. Additionally, there are currently 7 TLALOCNet stations delivering high-rate, low-latency (1 Hz, < 2 s) data streams in real-time via the Networked Transport of RTCM via Internet Protocol (NTRIP); these RT-GPS stations are part of the UNAVCO RT network of >450 stations, which is managed through the proprietary PIVOT software package from Trimble Navigation, Inc.

Page 9: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

9

BUDGET AND SCHEDULE Including open commitments (project manager salary, travel to support remaining scope, and the purchase of remaining project hardware), the TLALOCNet expenditures through the end of June 2015 were $992,485. With a June 2015 project budget (through 22 months) of $1,087,637, the project is within a 10% cost variance. The delay in the first year hiring of the project manager has pushed the expected network completion of all stations to March 2016. The project is in a good position, however, to meet all installation goals in Year 3, within the proposed budget. UNAVCO engineering staff installed 3 cGNSS-Met stations in the first year and 11 stations in the second year of the TLALOCNet project. Because the project manager was not hired until the 8th month of the first year of the project, the original, overly optimistic, 2-year installation schedule has not been met. The project, however, remains appropriately under budget based on the number of stations installed to date and is in a good position to finish the installations in during the final year (9/1/15 to 8/31/16). UNAM installed 4 required cost-share stations in the first year and 7 more were completed in the second year of the project (Figure 2 and 3). All data from the UNAM contributing stations are delivered via daily ftp to the UNAVCO data archive. Additional project milestones, such as completion of the regional data center and the project web page, are shown in the detailed project schedule (Figure 4).

Figure 2. NSF-funded station installations (left). Figure 3. UNAM cost-share stations (right). FY2014 refers to the project period from Sept. 1, 2013 to August 31, 2014; FY2015 refers to the project period from Sept. 1, 2014 to August 31, 2015; FY2016 refers to the project period from Sept. 1, 2015 to August 31, 2016.

Page 10: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

10

Figure 4. TLALOCNet three-year project schedule (red vertical line is the current epoch).

TlalocNet-schedule 8/2/15, 11:01 AM

/Users/galetzka/Dropbox/TlalocNet (1)/Project-Management/Time/TlalocNet-schedule.oplx 1

Title Start Effort EndQtr 1 2012 Qtr 2 2012 Qtr 3 2012 Qtr 4 2012 Qtr 1 2013 Qtr 2 2013 Qtr 3 2013 Qtr 4 2013 Qtr 1 2014 Qtr 2 2014 Qtr 3 2014 Qtr 4 2014 Qtr 1 2015 Qtr 2 2015 Qtr 3 2015 Qtr 4 2015 Qtr 1 2016 Qtr 2 2016TLALOCNet

TLALOCNet Budget and Proposal SubmissionProject Funded by NSF

Pre-Project Kickoff TeleconferenceProject Kickoff Meeting - Boulder, CO

UNAVCO/UNAM Meeting in San FranciscoInternal BA Kickoff Meeting

Webpage DevelopmentMeeting to discuss overall web plan

Basic webpage online (1 pager w/map)Webpage with Project Management Elements

Webpage with Science Highlights

MOU Development Redo COCONet MOU

Complete UNAM - UNAVCO MOUComplete UNAVCO-UdeG MOU

Hire TLALOCNet Project ManagerProject Plan Completed

Procurement and PrepY1 Procurement - 7 systems

Y2 Procurement - 18 systemsPrep Equipment - 2 Upgrades, 2 New

Prep Equipment - 4 StationsPrep Equipment - 12 sets of DC systems

Non-UNAM VSAT testing and preparation for GUAX at San Clemente and TNBA

UNAM Engineer HiredContract Negotiated

Contract Signed

Regional Data Center CompletedMeeting with Berta Marquez and University of Guadalajara IT Dept

UNAVCO Purchases Required HardwareMirror Archive Established

Full RDC Established

ReconnaissanceRecon: YESX, USMX

Recon: Hermosillo, CuauhtemocRecon: CHAM, PAPA, CALC, MMIG

Recon: OXNC, OXEC, OXGU, CHAM, CALC, PCIG, OXTU, OXMA, OXP2, OXAC, AMEC, MASC, PZUL, PURI, PENA, OXTPRecon: Infernillo, Canas, Paraiso

Recon: 7 alternative sites

ShippingDiplomatic Pouch #1 (5 sets of Trimble Rx and Ant plus Metpacks)

Overland delivery for USMX, YESX, TNHM, TNCUDiplomatic Pouch #2 (5 sets of Trimble Rx and Ant plus heavy tools)

Diplomatic Pouch #3 (5 sets of Trimble Rx and Ant plus Metpacks)Donation Shipment #1 (4 Stations)

Submit Donation Letter #2 to UNAMDiplomatic Pouch #4 (5 sets of Trimble Rx, Ant, Metpacks)

Donation Shipment #2 (12 Stations)Diplomatic Pouch #5 (5 sets of Trimble Rx and Ant plus Metpacks)

Diplomatic Pouch #6 (7 Metpacks and VSAT equipment)Overland importation of enclosures and other hardware for Topolobabmpo and Penasco

GUAX VSAT hardware arrives in San ClementeOverland importation GUAX VSAT from San Clemente to TNBA

Donation #2 available at UNAMDiplomatic Pouch for any remaining hardware

Overland importation of equipment for GUAX

Station InstallationsPermits Accepted for Hermosillo

Permit Accepted for CuauhtemocMoctezuma USMX, Hermosillo TNHM, Cuauhtemoc TNCU

Chamela, Ameca, Mascota, Maruata, recon Stations 24 25Nochixtlan, Acatlan, Pijijiapan; finalize Mascota

Yecora, Bahia de Los Angeles; maintain USMX (John, Adam, Luis)Puerto Penasco, Topolobampo (John, Adam, Luis)

TNBA VSAT deployment and testPena Colorada, Purification, Ciruelos, Infiernillo; finalize Ameca, Chamela, Maruata

Marquelia, Putla, Guevera, Camaron, GalerasMaria Madre, GUAX

MeetingsUGM - Puerto Vallarta

AGU - San FranciscoUGM - Puerto Vallarta

AGU - San Francisco

Data ProcessingProcessing Centers Invoice Received (Quarterly)

Processing Centers Paid (Quarterly)

Page 11: TLALOCNet EAR-1338091 Annual Report · TLALOCNet 2014-2015 Annual Report 1 TLALOCNet EAR-1338091 Annual Report September 1, 2014 - August 31, 2015 (FY2015) SUMMARY This annual report

TLALOCNet 2014-2015 Annual Report

11

EDUCATION, OUTREACH, AND COMMUNITY ENGAGEMENT In addition to our focus on logistics and station construction during the second year, the TLALOCNet project set up the Regional Data Center and PIs and UNAVCO staff reported about progress at two major geophysical conferences. On the occasion of the 30th anniversary of the devastating Mw 8.1 earthquake in Mexico, UNAVCO has been invited to participate at a symposium called "Sismo 85: Advances and challenges in seismology, engineering and risk management 30 years after the 1985 earthquake" at the Universidad Nacional Autonoma de Mexico (UNAM) campus in Mexico CIty. UNAVCO staff is working to provide speakers for sessions on networks and earthquakes and educational/outreach. Meetings and Conferences An invited talk about the initial development of TLALOCNet was given at the UGM annual meeting in Puerto Vallarta, Mexico in November 2014, and one poster was presented at Fall AGU in December 2015. As the project construction phase moves toward completion, we anticipate that a special session at AGU or GSA will be developed by the PIs to highlight new and upgraded TLALOCNet infrastructure (instruments and IT), data, data products, and analysis. PROJECT CONCERNS Additional time and effort to find and construct alternative sites: Adverse conditions at one operating station and six proposed stations required UNAVCO staff in close consultation with the PI team and our regional partners to select seven alternative sites. The conditions range from newly identified monument/geologic instability (two sites), required use of costly satellite telemetry (two sites), deteriorating security (one site), and restriction from using any form of telemetry (one site). Risk mitigation: We anticipate selecting and permitting seven alternative sites by November 1st, 2015, and having those stations operational by February 1st, 2016.