tim burkhalter burns & mcdonnell 1 - cbia · tim burkhalter burns & mcdonnell 1 ... tim...
TRANSCRIPT
6/5/2014
Tim Burkhalter Burns & McDonnell 1
Onsite Power Generation
IS IT A GOOD DECISION FOR MY PLANT?
Presented by:
Kurt Koenig, Burns & McDonnell
Lee Hoffman, Pullman & Comley
Combined Heat and Power (CHP): The on-site simultaneous generation of two forms of energy from a single fuel/energy source
OVERVIEW
MARKET APPLICATIONS
TYPICAL TECHNOLOGIES
PROJECT DEVELOPMENT APPROACH
ECONOMICS
START TODAY
RESOURCES
6/5/2014
Tim Burkhalter Burns & McDonnell 2
“BEHIND THE FENCE”
COLLEGE CAMPUS
HOSPITALS
MILITARY BASES
MANUFACTURING FACILITIES
RESEARCH FACILITIES
DATA CENTERS
INDUSTRIAL
COMMERCIAL
WHERE CHP?
IS CHP A GOOD DECISION FOR MY PLANT?
EFFICIENCY
Coal Plant = 30-40%
Combined Cycle Plant = 40-50%
CHP (overall electrical/thermal) = 70-90%
RELIABILITY
EMISSIONS REDUCTION
UTILITY COST SAVINGS
ECONOMICS / LCCA
6/5/2014
Tim Burkhalter Burns & McDonnell 3
CHP CONFIGURATIONS
Bottoming Cycle
Generate Electricity
Local Use Export/Sale
Drive a Steam Turbine
Condensing Back Pressure
Generate Steam
Boiler HRSG
Waste Heat from Process
Furnaces Kilns Exothermic Reactions
Topping Cycle
Utilize Energy Space
Heating/DHW Process Needs
Cooling
Create Useful Energy
Steam Hot
Water Chilled Water
Capture Waste Heat
Flue Gas Jacket Cooling
Extraction Steam
Generate Electricity Combustion
Turbine Recip
Engine Boiler +Steam
Turbine
TRADITIONAL CONCEPT
Fossil Plant (coal)
Combined Cycle
Plant
Nuclear Plant
Hydro
Wind
Utility Owned
Factory/Process Facility
College Campus
Hospital
Mixed Use Development
High Rise
Casino
City
Privately Owned
6/5/2014
Tim Burkhalter Burns & McDonnell 4
CHP CONCEPT
HTTP://WWW.C2ES.ORG/TECHNOLOGY/FACTSHEET/COGENERATIONCHP
CHP RELIABILITY
MAINTAIN POWER THROUGH UTILITY OUTAGE LOW COST FOR BLACK START CAPABILITY MAINTAIN THERMAL GENERATION FUEL DIVERSITY CLIENT SPECIFIC
Research Needs
Emergency Response
Natural Disasters
6/5/2014
Tim Burkhalter Burns & McDonnell 5
CHP EMISSIONS
AVERAGE US GRID
80% EFFICIENT BOILERS
25MW GAS TURBINE UNFIRED HRSG
VS
*Results from EPA emissions estimating tool
MARKET APPLICATIONS
Type MW Heat/Power Ratio
Universities 5-30 High
Hospitals 2-10 Medium
Industrial/Manufacturing 5-60+ Medium-High
Government/Military 5-60 Low-Medium
District Energy Systems 5-50 Medium-High
Mixed Use Developments 3-10 Low
6/5/2014
Tim Burkhalter Burns & McDonnell 6
MARKET POTENTIAL MARKET POTENTIAL
6/5/2014
Tim Burkhalter Burns & McDonnell 7
MARKET POTENTIAL OPPORTUNITY FOR CHP IN U.S.
Source: ICF Report The Opportunity for CHP in the United States
6/5/2014
Tim Burkhalter Burns & McDonnell 8
TYPICAL TECHNOLOGIES &
TECHNOLOGY SELECTION
TURBINES
HRSG’S
RECIPROCATING ENGINES
STEAM TURBINES
TYPICAL TECHNOLOGIES
GAS TURBINES (4-50MW)
Solar, Siemens, GE (aero’s) HRSG’S (5,000-350,000 LBS/H)
Rentech, Cleaver Brooks RECIPROCATING ENGINES (2-18MW)
GE Jenbacher, Wartsilla STEAM TURBINES (2-50MW)
Siemens, Elliot, GE, TurboSteam
6/5/2014
Tim Burkhalter Burns & McDonnell 9
HEAT RECOVERY POTENTIAL (RULES OF THUMB) GAS FIRED RECIPROCATING ENGINES
1.2 lbs/h of 100psig sat steam per kw
2.5-3.0 MMBtu of hot water per MW (jacket water and exhaust in series) GAS TURBINES
Unfired ~ 4.0-6.0 lbs/h of 100psig sat steam per Kw
Fired to 1600F ~ 2 x unfired capacity
TYPICAL TECHNOLOGIES
TYPICALLY A BALANCE BETWEEN SUMMER THERMAL LOAD AND WINTER ELECTRIC LOAD
If summer thermal load is small - limits prime mover size (cooling a possibility?)
If winter electric load is small – limits prime mover size (export?) TYPICALLY NO ELECTRIC EXPORT LIMITING FACTOR MAY CHANGE SEASONALLY HOURLY MODEL IS A MUST!
TYPICAL TECHNOLOGIES
6/5/2014
Tim Burkhalter Burns & McDonnell 10
TECHNOLOGY SELECTION DISPATCH
OTHER KEY SELECTION CRITERIA
ELECTRICAL EFFICIENCY VS STEAM PRODUCTION TURN DOWN EMISSIONS PROFILES (SCR?) NOISE STARTS/STOPS SPACE REQUIRED DUCT FIRING CAPACITY INLET COOLING GAS PRESSURE
6/5/2014
Tim Burkhalter Burns & McDonnell 11
STAGE 1 - QUALIFICATIONS
STAGE 2 – LEVEL 1 FEASIBILITY ANALYSIS
STAGE 3 – LEVEL 2 FEASIBILITY ANALYSIS
STAGE 4 – PROCUREMENT
PROJECT DEVELOPMENT
APPROACH DEVELOPMENT APPROACH
STAGE 1 - QUALIFICATION TIMELINE 1-7 Days KEY INPUTS Spark Spread Min/Max/Annual Loads Current Utility Operations Goals/Key Drivers DELIVERABLES Potential Annual Savings Calculation Go/No-Go Recommendation Level I Proposal
6/5/2014
Tim Burkhalter Burns & McDonnell 12
DEVELOPMENT APPROACH
STAGE 2 – LEVEL 1 FEASIBILITY ANALYSIS
TIMELINE 4-8 Weeks
KEY INPUTS Rate Structures or Assumptions Thermal and Electric Load Profiles (prefer hourly) Current Asset Condition/Performance Growth Assumptions Financial Parameters Understanding of current operations/Permits Base Case Definition
DELIVERABLES Hourly Dispatch Model (3-6 Cases) Conceptual Layouts Heat Balance/Flow Diagrams/One-lines(MV) Permitting Hurdles Cost Estimate +/-40% LCCA, IRR, Payback Configuration Recommendation Level 2 Proposal
DEVELOPMENT APPROACH
STAGE 3 – LEVEL 2 FEASIBILITY ANALYSIS
TIMELINE 8-12 Weeks
KEY INPUTS Detailed Rate Structures and Procurement Strategies Historic Hourly Loads Capital Replacement Plan, Deferred Maintenance, Other O&M Costs Growth Assumptions Financial Parameters, Financing Options Detailed Interviews with Operations Staff Current Permits
DELIVERABLES Hourly Dispatch Model (1-2 Cases) 15% Design Documents (Heat Balance/PID’s/One-lines/Plans and Sections) Multidiscipline Cost Estimate +/-20% LCCA, IRR, Payback Sensitivity Analysis (Rates, Load, Capital, etc.) Delivery Method Analysis/Discussion Recommendation
6/5/2014
Tim Burkhalter Burns & McDonnell 13
FULL LCCA/PRO FORMA
Hourly Compensated Dispatch Model Detailed Rate Information/Escalation Load Growth Forecasts Avoided Costs Value for REC’s/Carbon Detailed Capital Cost Maintenance Costs Value for lost revenue Sensitivity/Risk Analysis
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
$16.00
$18.00
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
An
nu
al
Co
st
/ S
avin
gs
($M
illio
ns)
Maintenance Capital Energy Savings
0.0
0.2
0.4
0.6
0.8
1.0
1.2
-
200
400
600
800
1,000
1,200
-$25 -$15 -$5 $5 $15 $25 $35 $45 $55 $65 $75 $85
Exceed
an
ce P
rob
ab
ilit
y
Fre
qu
en
cy
Option 2 NPV Savings vs. Base Case (Millions)
DEVELOPMENT APPROACH
STAGE 4 - PROCUREMENT DEVELOP BID PACKAGE PROCEED WITH DESIGN ONLY DESIGN-BUILD DESIGN-BUILD-OWN-OPERATE PROGRAM MANAGER/OWNERS ENGINEER COMMISSIONING
6/5/2014
Tim Burkhalter Burns & McDonnell 14
PROJECT COSTS
TURBINE AND RECIP - $1500 TO $5000/KW
Existing Site?
Load available?
Prime Mover
Supporting Infrastructure/Distribution BACK PRESSURE STEAM TURBINE – $450 -$650/KW
Condensing turbine adds cost – condenser, towers, piping, water treatment, etc. MAINTENANCE COSTS – OEM VS THIRD PARTY
ECONOMICS
($1.7)
$2.9
$18.0
$2.1 $1.5
$0.0 $5.9
($15.2)($1.4)
($0.2)
($25.0)
($20.0)
($15.0)
($10.0)
($5.0)
$0.0
$5.0
$10.0
$15.0
Purchased
Electricity -
Energy
Purchased
Electricity -
Demand
Purchased
Electricity -
Standby
Purchased
Electricity -
Generation
Capacity
Natural
Gas
Non Fuel
O&M
Initial Capital
Thru 2016
Capital
After 2016
Cumulative
With
Current GHG
Policies
NP
V,2
01
3 $
MM
Incremental Cost Of Utility Service, NPV 2013$MM
Option 7 vs. Option 2, Expected Value
Savings, decrease in costIncrease in costEnding incremental present value
STATE INCENTIVES
CEFIA/Green Bank CHP Program
PROBABLY BEST BET FOR CHP IN CONNECTICUT
CEFIA is seeking proposals for grants, loans, loan enhancements or power purchase incentives Incentives vary based on technology and efficiency – cap is $450/kw REQUEST FOR PROPOSALS
Issued July 9, 2013 Applications available at www.energizect.com/chp Responses to RFPs due no later than February 27, 2015 at 5 pm ELIGIBLE APPLICANTS Almost anybody—except single family homeowners: For-profit companies Not-for-profit entities Municipalities State and federal agencies Colleges and Universities School districts Not-for-profit and for-profit affordable housing companies Public housing agencies
6/5/2014
Tim Burkhalter Burns & McDonnell 15
STATE INCENTIVES
CEFIA/Green Bank CHP Program
FOCUS
Focus is on projects that have large electrical and thermal loads Hospitals, POTWs, colleges and schools, manufacturing facilities and multi-family housing/hotels are all good bets CRITERIA FOR APPLICATIONS
Must be in development phase. NO construction Past grant winners, and LREC/ZREC winners are not eligible Systems must be 5 MW or less Systems must be commercially available CHP systems Located in UI or CL&P service territory Generate electricity for on-site use, but excess may be sold on the wholesale market The Financial Assistance Agreement must be taken “as is.”
STATE INCENTIVES
CEFIA/Green Bank C-PACE Program
“SQUARE PEG” – BUT OCCASIONALLY THERE IS A SQUARE HOLE
Commercial Property-Assessed Clean Energy Program Developed for energy efficiency projects, but can be used for CHP CRITERIA FOR PARTICIPATION
Must demonstrate energy savings sufficient to justify repayment Must be a permanent structure Must be in a municipality that has agreed to the C-PACE program Renewable CHP projects are best bets CHP projects that are peak shavers can be eligible
6/5/2014
Tim Burkhalter Burns & McDonnell 16
STATE INCENTIVES
CEFIA/Green Bank C-PACE Program Geographic Scope
Source: www.energizect.com
STATE INCENTIVES
CEFIA/Green Bank C-PACE Program -- How it works:
Source: CEFIA
6/5/2014
Tim Burkhalter Burns & McDonnell 17
FEDERAL INCENTIVES
NOT AS ROBUST AS STATE INCENTIVES, BUT AVAILABLE
BUSINESS ENERGY INVESTMENT TAX CREDIT FEDERAL LOAN GUARANTEES FOR ADVANCED FOSSIL ENERGY PROJECTS BUSINESS AND INDUSTRY GUARANTEED LOANS MODIFIED ACCELERATED COST-RECOVERY SYSTEM
SIMPLE METHOD
SPARK SPREAD = ELECTRIC COST ($/MMBTU) – GAS COST ($/MMBTU)
BREAKPOINT ~ 11-12 Gas Cost = $5/MMBtu Electric Cost = $0.10/kWh * 293 = $29.3/MMBtu Delta = 24.3 Gas Cost = $6/MMBtu Electric Cost = $0.06/kWh * 293 = $17.5/MMBtu Delta = 11.5
SPARK SPREAD
6/5/2014
Tim Burkhalter Burns & McDonnell 18
SPARK SPREAD SPARK SPREAD
Operating Cost to Generate
CHP Fuel Costs, $/kWh $0.0588
Thermal Credit, $/kWh ($0.0292)
Incremental O&M, $/kWh $0.0090
Operating Costs to Generate Power, $/kWh $0.0386
Capital Charge, $/kWh $0.0333
Total Costs to Generate Power, $/kWh $0.0719
Current Average Electricity Price, $/kWh $0.0800
Spark Spread, $/kWh** $0.0081
SPARK SPREAD – BETTER METHOD – EPA CHP
6/5/2014
Tim Burkhalter Burns & McDonnell 19
PUBLIC RESOURCES
DOE CLEAN ENERGY APPLICATION CENTERS
http://www1.eere.energy.gov/manufacturing/distributedenergy/ceacs.html EPA CHP EMISSIONS CALCULATOR
http://www.epa.gov/chp/basic/calculator.html EPA SPARK SPREAD ESTIMATOR EPA CATALOG OF CHP TECHNOLOGIES EPA CHP PROJECT DEVELOPMENT HANDBOOK
http://www.epa.gov/chp/
ANALYSIS TOOLS
COMBINED HEAT & POWER TURBINE SELECTION GUIDE HOURLY DISPATCH MODELS PERFORMANCE MODELS
Excel
Gatecycle CASE STUDIES
6/5/2014
Tim Burkhalter Burns & McDonnell 20
Questions?
Kurt Koenig [email protected]
919-900-1864
Lee Hoffman [email protected]
860-424-4315