thomas jefferson national accelerator facility page 1 latifa elouadrhiri assistant project manager...

44
Thomas Jefferson National Accelerator Facility Page 1 Latifa Elouadrhiri Assistant Project Manager Hall B SVT Technical Review Jefferson Lab January 19-20, 2012 CLAS12 – Silicon Vertex Tracker Project Summary WBS 1.4.2.2.1.1

Upload: noel-flynn

Post on 28-Dec-2015

218 views

Category:

Documents


3 download

TRANSCRIPT

Thomas Jefferson National Accelerator Facility

Page 1

Latifa ElouadrhiriAssistant Project Manager

Hall B

SVT Technical ReviewJefferson Lab

January 19-20, 2012

CLAS12 – Silicon Vertex Tracker Project Summary

WBS 1.4.2.2.1.1

Thomas Jefferson National Accelerator Facility

Page 2

Charge 1

Are the individual elements of the detector well-designed and will they work well together as a system? Do the designs incorporate known good practice in preparing such detectors?

YES

Thomas Jefferson National Accelerator Facility

Page 3

Response to Charge 1Summary - Main Components Procurement

Sensors:Awarded to Hamamatsu Corporation on December 3, 2010Hamamatsu Recent Experience:

• CMS - Largest silicon detector ever built with 200 m² sensor area, ~20,000 silicon strip sensors with <0.01% defective strip

• ATLAS - ~17,000 single-sided micro strip sensors

• First Article Sensors received and checked by FNAL/MSU/Jlab• First Article Sensors meet or exceed specifications

FSSR2:All ASICs received (650 chips), 360 chips tested, SVT requires 264 chips

HFCB:Purchase awarded to Compunetics for 10 units on Dec. 2010

First article 5 HFCB delivered in August

First article tested and design changes have been implemented

Thomas Jefferson National Accelerator Facility

Page 4

Summary – Fabrication Plan

Design of individual elements completed and optimized to reduce risks:

Sensors – Opted for single-sided instead of double-sided

• Higher yield• Higher reliability

• Similar in design to proven sensors in other experiments

CMS, CDF and D0

– Manufactured by Hamamatsu Corporation • Recommended by other labs and reviewers as best in the world

•Extensive experience at world class facilities

• First Article Sensors received and checked by FNAL/MSU/JLab• First Article Sensors meet or exceed specifications

Thomas Jefferson National Accelerator Facility

Page 5

Summary – Fabrication Plan

Design of individual elements completed and optimized to reduce risks:

ASIC FSSR2–FSSR2 - Successful engineering run for BTeV–Well evaluated–Close versions (FPIX) in use at other facilities (BNL)– Performed multiple levels of testing

• Prior to dicing• After dicing• After assembly• After installation

All ASICs received (650 chips), 360 chips tested, SVT requires 264 chips.

Thomas Jefferson National Accelerator Facility

Page 6

Summary – Fabrication Plan

Design of individual elements completed and optimized to reduce risks:

HFCB– Guided by designs done at CDF and D0– Designed with 3 mil trace/spacing, allowed larger group

of vendors – Researched for the best quality parts– Reviewed the design with experts in the field:

Brian Eng (JLab), Peter Bonneau (JLab), Amrit Yegneswaran (JLab), Sasha Voronin (MSU), Tim Schmitt (Compunetics),Jacoub Kurnot (Compunetics)

Electrical grade module test completed and design changes

implemented

Thomas Jefferson National Accelerator Facility

Page 7

Summary – Fabrication Plan

Fabrication plan developed and optimized to reduce risks•Module components

– Carbon fiber, Rohacell — standard materials– First electrical grade module has been fabricated– Mechanical grade module will be fabricated

•Slow Controls and DAQ–Software

Plan to use existing software LabView/Epics/CODA–Hardware

Plan to use, wherever possible, “off-the shelf” electronics•For reliability and dependability

Electronics developed for other Halls, Hall D•With an eye to standardization

Thomas Jefferson National Accelerator Facility

Page 8

CHARGE 2

Are the test measurements, both performed to date and planned, appropriate to predict the performance of the system? Will the performance provide adequate margin for operation under the expected conditions following the 12 GeV upgrade? Are plans for handling the expected radiation damage well-developed and adequate to the task?

YES

Thomas Jefferson National Accelerator Facility

Page 9

Response to Charge 2

Good performance of the detector predicted by measurements performed on sensors and electrical module.

• Levels of electronic noise and radiation dose small and manageble• First electrical grade module works well.

• Measured S/N of ~10 with realistic lengths of HV and LV cable

• Threshold dominated by electromagnetic background

• Electronic noise small in comparison to EM background

• GEMC simulation shows that radiation level over 15 years of running

at 50% duty cycle on Carbon target to be 2.5 Mrads– ASICs designed to handle 5 MRads

Thomas Jefferson National Accelerator Facility

Page 10

Rates and Radiation

Total Rate ~22 MHz• Dominated by photons

Electronic Noise ~0.6 KHzDose 2.5 MRads over 15 years of operation at 50% duty cycle

Thomas Jefferson National Accelerator Facility

Page 11

Charge 3

Are plans for the assembly, quality control, and acceptance testing at various sites well developed and appropriate for production of a detector of this scale?

YES

Thomas Jefferson National Accelerator Facility

Page 12

Response to Charge 3

Summary – Assembly Plan

•Assembly plan developed and optimized to reduce risks–Modules

•Module design based on CDF and D0

•JLab will develop, in consultation with FNAL and MSU, specifications, designs and procedures for module assembly and testing

•Module components will be tested at JLab, MSU & Fermi,

• Planned to be assembled and tested at FNAL with strong MSU participation

•FNAL and MSU have extensive experience assembling such modules

•Detector integration plan–Clean room and Infrastructure ready at JLab for testing and assembly–Installation procedures well thought out

Thomas Jefferson National Accelerator Facility

Page 13

QA/QC - Overview• Managed under the JLab QA/QC Plan (and 12 GeV Upgrade Supplemental

QA/QC Plan), in conjunction with Value Engineering– All components must comply with specifications provided to vendor before

being accepted • Comprehensive QA/QC document addresses:

– Sensors– Hybrid Flex Circuit Boards (HFCB)– FSSR2 ASICs– Modules– Support & Cooling System

– Commissioning– Risk Mitigation– Safety

‒ Engineered Safety Controls‒ Administrative Safety Controls ‒ Test Stand Safety‒ Electrical Safety Compliance

Thomas Jefferson National Accelerator Facility

Page 14

Quality Assurance

• Protocols provided for situations that might compromise the detector

• Assemble and rework will be carried out in a class 10,000 clean room

• ESD protection requirements specified in NASA STD-8739.7 will be followed

• All equipment will be grounded• Grounded static dissipative mats will be used• Electronic travelers will be used for test activities• Test results are documented in the electronic

logbook

Thomas Jefferson National Accelerator Facility

Page 15

Quality Control

• Individual components will be tested prior to assembly– Silicon sensors, readout chips, PCBs, cabling …

• Complete modules will be tested prior to detector assembly

• Entire detector will be tested after assembly– On a region by region basis – and as complete detector

• Detector will be tested after installation

Thomas Jefferson National Accelerator Facility

Page 16

Value Engineering

One silicon sensor size • Design minimizes number of masks needed• Three mask designs for SVT• All SVT detector modules are identical

All detector modules are identical– Lower number of spares needed – Interchangeability between regions

Use of previously designed readout chips • Performance already evaluated

Use of Jefferson Lab developed CODA for data acquisition software

Use of Jefferson Lab developed monitoring software

Thomas Jefferson National Accelerator Facility

Page 17

Risk Mitigation

Custom fixture to prevent shipping damage

Alignment markers on support structure for installation

Fiducial marks for silicon component alignment

Standard single-sided, 320 µm silicon sensors

FSSR2 readout ASICs – Already evaluated

Thomas Jefferson National Accelerator Facility

Page 18

Risk Mitigation

Hybrid Flexible Circuit Board and instrumentation designs– Based on CDF and D0 designs

Minimal number of sensor types

Wherever possible– Industry-designed boards and electronics– “Off-the-shelf” board components

Thomas Jefferson National Accelerator Facility

Page 19

Charge 4

Is the cooling system design ready for first-article manufacture, and is it well-integrated into the design of the detector? Assess the design maturity for services and cable routing, including bias, data links, cooling services, support/mounting points, ability to provide servicing over the life of the detector, and ability to repair/replace a damaged module.

YES

Thomas Jefferson National Accelerator Facility

Page 20

Response to Charge 4

• FEA calculations performed• First mockup done of cold plate completed• Cable routing cooling services layout developed.

Thomas Jefferson National Accelerator Facility

Page 21

Module Temperature Distribution

Heat Output : 2W

Coolant: WaterCoolant temperature: 15oC

Flow rate: 3 LPM(Twater ~0.6oC)

Nitrogen Purge at 20oC

Heat Sink Material : Copper

Peak Temperature on sensor: ~22oC

Peak Temperature on chip: ~24oC

24oC 22oC 21oC

Thomas Jefferson National Accelerator Facility

Page 22

Cold Plate Prototype

Copper Inserts with fins

Cooling Channel

Cold Plate is in two parts --

One part with cooling channel machined in it

Second part with slots machined to accommodate inserts

Adhesive used – 3M DP 190

Thomas Jefferson National Accelerator Facility

Page 23

Prototype Thermal Experiment

• Heat output- 3W

• Water temperature – 15.5 C (at inlet)

• Flow rate: 2.6 LPM

• Temperature measured adjacent to resistor – 25.7 C

• Temperature measured on stave support – 17.4 C

Thomas Jefferson National Accelerator Facility

Page 24

Summary and Path Forward• QA/QC developed for each component

– Specification, assembly, and test procedures documented

• All components have been tested individually and in full chain and meet our physics specifications

• Assembly plan and acceptance testing at FNAL and JLab have been developed and documented

• Path Forward– Give the go ahead to Hamamatsu for sensor production

– Production of the HFCB with the new design changes

– Complete design of the fixtures and tooling for module production at FNAL

– Build mechanical grade module

– Start SVT module production

Thomas Jefferson National Accelerator Facility

Page 25

THANK YOU!

Thomas Jefferson National Accelerator Facility

Page 26

Appendix

Thomas Jefferson National Accelerator Facility

Page 27

Sensors: QA

• Information to be supplied by the vendor for each sensor:– ID # engraved in the area provided on the sensor– Sensor ID numbers listed for each wafer – Traceability data: relative yield of a batch, start and end

dates of processing, and wafer numbers– Test results for each sensor

Thomas Jefferson National Accelerator Facility

Page 28

Sensors: QC

Tests to be done by the vendor for each sensor: •Sensor leakage current <10 nA/cm2

•Inter-strip, backplane, and total capacitance ‒1.2 pF/cm, 0.2 pF/cm, 1.4 pF/cm

•Depletion voltage between 40 V – 100 V•Resistance: Interstrip, polybias resistors, Al strip

‒>1 GΩ, 1.5 MΩ, <20 Ω/cm

Thomas Jefferson National Accelerator Facility

Page 29

Sensors: Risk Mitigation

Opted for single-sided instead of double-sided• Higher yield• Higher reliability

Similar in design to proven sensors in other experiments• CMS, CDF, and D0

Manufactured by Hamamatsu Corporation • Recommended by other labs and reviewers as best in

the world•Extensive experience at world class facilities

Thomas Jefferson National Accelerator Facility

Page 30

HFCB: QA• Design Phase

– Develop prototype design– Fabricate hybrid test board – Develop software to test circuit

• Vendor

– Evaluates design files– Made change suggestions– Submitted changes for approval prior to

manufacturing• Post manufacturing

– Vendor performs electrical test on all circuits for shorts and opens, rejecting all that do not pass

– Vendor sends only HFCBs that meet specifications

Thomas Jefferson National Accelerator Facility

Page 31

HFCB: QC

• Prior to population– Circuits are visually inspected using microscopes

and video capture– Circuits are tested by manufacturer for plane shorts

and voltage drop• Post component population, prior to ASIC mounting

and bonding– Circuit is power tested

• Post ASIC mounting and Bonding– Chip functionality testing

‒ Chip register test‒ Threshold scan

Thomas Jefferson National Accelerator Facility

Page 32

HFCB Installation: QC

• After installation on module– Functionality test

‒ Performed after every bonding step for 1st Article modules‒ After final sensor bonding step for production modules

– HFCB has pulse injection circuit for ASIC testing

Thomas Jefferson National Accelerator Facility

Page 33

HFCB: Risk Mitigation

• Risk– Complexity of design– Component reliability

• Mitigation – Guided by designs done at CDF and D0– Designed with 3 mil trace/spacing, allowed larger group

of vendors – Took the “next logical step” in design improvements – Researched for the best quality parts– Electrical grade module test

Thomas Jefferson National Accelerator Facility

Page 34

ASIC: QC

• FSSR2 configuration register and read-back– Data read back must be identical to written data

• FSSR2 registers’ mask load and read-back– Test mask configuration

• Threshold scan• Gain and noise measurement• Readout configuration test• Channel inefficiency• ADC operation

Thomas Jefferson National Accelerator Facility

Page 35

ASIC Risk Mitigation

• Risks– Available ASICs are only from BTeV engineering

run• Mitigation

– FSSR2 - Successful engineering run for BTeV– Perform multiple levels of testing

• Prior to dicing• After dicing• After assembly• After installation

– 650 chips in hand and 360 have been successfully tested

Thomas Jefferson National Accelerator Facility

Page 36

Backing Structure: QC / Risk Mitigation

• Visually inspect for: – de-lamination– loose carbon strands– general condition

• Measure with CMM dimensions– At least 20 points– copper heat sink flatness at 10 points with CMM

• Check – alignment holes for tolerances

• Risk Mitigation– Use of standard materials– Achievable tolerances

Thomas Jefferson National Accelerator Facility

Page 37

Module: QC / Risk Mitigation• Prior to assembly

• Visual inspection of the backing structure• Measure all dimensions of the backing structure

• Post Assembly• Dimensions of the module, flatness, straightness, etc.

will be measured and recorded using CMM• Positional accuracy of the sensors and HFCB will be

measured using an optical CMM• Check HV/LV• Measure leakage current

Risk Mitigation• Modules will be fabricated at FNAL, which has extensive

experience in fabricating and assembling similar modules

Thomas Jefferson National Accelerator Facility

Page 38

Barrel Assembly: QC / Risk Mitigation

• Cold plate will be compared to drawing specifications• Heat sink insert will be checked for compliance with

drawings and excess glue will be removed• Module support and conductor will be checked with a

CMM• Downstream support ring will be measured and

compared with the drawings

• Risk Mitigation– Cold plate prototyped– 1st Article tests

Thomas Jefferson National Accelerator Facility

Page 39

Detector Assembly: QA/QC/Risk Mitigation

• At manufacturer• All assembly components are inspected by the

manufacturer and must meet all drawing specifications

• Prior to detector assembly (of each sub-detector)• Visual inspection of the assembly components• Dimensions of the components, flatness,

straightness, etc. will be measured and recorded using CMM

• Positional accuracy of the sensors and HFCB will be measured using an optical CMM

• Risk mitigation• Cold plate and support structure were prototyped at

JLab and also compared to results from FEA

Thomas Jefferson National Accelerator Facility

Page 40

Slow Controls: QA/QC/Risk Mitigation• At the manufacturer

• All hardware functions fully tested

• At JLab after assembly and installation• Multiple automated LabView tests

‒ Test voltage, current, and trip setting

• Risk mitigation• Hardware purchased from known source for quality and

reliable products • Similar systems used previously in past Hall B systems

with great success

Thomas Jefferson National Accelerator Facility

Page 41

Data Acquisition: QA/QC/Risk Mitigation

• At the vendor– Electrical test performed on PCBs

• After assembly– Runs with laser source

• After installation– Runs with cosmic ray source– Burn-in test

• Risk mitigation– Use of “off-the-shelf” components/industry standards

Thomas Jefferson National Accelerator Facility

Page 42

Checkout after Installation

• Cables and electronics will be visually inspected

• Test– Continuity of signal cable connections– HV/LV power to front-end electronics– Slow controls procedures to adjust critical parameters

of the equipment

Thomas Jefferson National Accelerator Facility

Page 43

Commissioning

• Low voltage system will be checked with dummy loads

• Low voltage will be powered first, then high voltage, in appropriate steps

• Read/write tests will be performed on the ASIC registers

• Efficiency and tracking accuracy tests using cosmic rays will be performed

Thomas Jefferson National Accelerator Facility

Page 44

Summary

• Well developed general QA/QC plan

• QA/QC developed for each component

– Specification, assembly, and test procedures documented