this page has been left blank intentionally
TRANSCRIPT
Greenville Water Greenville, South Carolina
Technical Specifications
For the
Lake Keowee Intake to Adkins Water Plant Raw Water System Improvements
CIP #184
BC Project #154828
Final Design Submittal
May 2021
TECHNICAL SPECIFICATIONS
FOR
CIP #184
Lake Keowee to Adkins WTP Raw Water Improvements
Prepared for:
Greenville Water
407 West Broad Street
Greenville, South Carolina 29601
Plans Prepared by:
Brown and Caldwell
250 Berryhill Road, Suite 104
Columbia, South Carolina 29210
803.873.9701
The Standard Technical Specifications (“specifications”) and Construction Details (“details”) bound into this
booklet have been reviewed by the above (“Engineer”) and have been found to be in conformance and consistent
with the construction illustrated in the design drawings (“plans”) prepared for this utility construction project.
Discrepancies found between the plans and the specifications of the details shall be communicated to the
Engineer for interpretation.
Lake Keowee to Adkins WTP Raw Water System Table of Contents
154828 01 11 00 - i
Lake Keowee to Adkins WTP Raw Water System
FOR GREENVILLE WATER
LIST OF TECHNICAL SPECIFICATION SECTIONS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 11 80 Environmental Conditions
01 12 16 Work Sequence
01 12 50 Measurement and Payment
01 14 19 Use of Site
01 32 16 Construction Progress Scheduling
01 32 23 Survey and Layout Information
01 32 33 Photographic Documentation
01 33 00 Submittal Procedures
01 35 43 Environmental Procedures
01 40 00 Quality Requirements
01 42 19 Reference Standards
01 45 20 Equipment and System Performance and Operational Testing
01 45 29 Testing Laboratory Services
01 51 00 Temporary Utilities
01 66 00 Product Storage and Handling Requirements
01 73 23 Bracing and Anchoring
01 73 29 Cutting and Patching
01 75 00 System Testing
01 78 23 Operating and Maintenance Data
01 78 39 Project Record Documents
01 91 00 Commissioning
01 99 90 Reference Forms
DIVISION 03 – CONCRETE
03 11 00 Concrete Forming
03 20 00 Concrete Reinforcing
03 30 00 Cast-In-Place Concrete
03 48 11 Precast Concrete Vaults
03 60 00 Grouting
DIVISION 05 – METALS
05 05 13.13 Zinc Coating
05 05 20 Anchor Bolts
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Lake Keowee to Adkins WTP Raw Water System Table of Contents
154828 01 11 00 - ii
07 91 26 Joint Fillers
07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 31 20 Floor Access Doors
DIVISION 09 - COATINGS
09 90 00 Painting and Coating
DIVISION 10 – SPECIALTIES
10 14 00 Signage
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing
31 23 00 Excavation and Fill
31 23 16 Rock Removal
31 23 19 Dewatering
31 25 00 Erosion, Sedimentation and Dust Control
31 41 00 Shoring
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving
DIVISION 33 – UTILITIES
33 05 31 Ductile Iron Pipe
33 05 32 Lined and Coated Steel Pipe
DIVISION 40 – PROCESS INTEGRATION
40 05 01 Piping Systems
40 05 06.16 Piping Connections
40 05 07 Hangers and Supports for Process Piping
40 05 57.13 Manual Actuators
40 05 64 Butterfly Valves
40 05 78.13 Air Vacuum Valves for Water Service
APPENDIX
S&ME, Inc. Geotechnical Engineering Report
Revised Subsurface Exploration Report, Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&M Project No. 1569-20-028
November 19, 2020
DIVISION 01
GENERAL REQUIREMENTS
Section Title
01 11 00 SUMMARY OF WORK
01 11 80 ENVIRONMENTAL CONDITIONS
01 12 16 WORK SEQUENCE
01 20 00 MEASUREMENT AND PAYMENT
01 14 19 USE OF SITE
01 32 16 CONSTRUCTION PROGRESS SCHEDULE
01 32 23 SURVEY AND LAYOUT DATA
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 35 43 ENVIRONMENTAL PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 19 REFERENCE STANDARDS
01 45 20 EQUIPMENT AND SYSTEM PERFORMANCE AND OPERATIONAL
TESTING
01 45 29 TESTING LABORATORY SERVICES
01 51 00 TEMPORARY UTILITIES
01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS
01 73 23 BRACING AND ANCHORING
01 73 29 CUTTING AND PATCHING
01 75 00 SYSTEM TESTING
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 39 PROJECT RECORD DOCUMENTS
01 91 00 COMMISSIONING
01 99 90 REFERENCE FORMS
Lake Keowee to Adkins WTP Raw Water System Summary of Work
154828 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 SUMMARY
A. The work covered under this contract will be performed at the site of Greenville Water’s
Witty Adkins Water Treatment Plant (Adkins WTP) intake structure, and along the access
road and raw water main easement.
1.02 DESCRIPTION OF OWNER'S PROJECT
A. Greenville water has identified the need to replace two 48” PCCP raw water lines running
from the raw water pump station to the gate to the pump station access road. At two
locations, fittings, valves, vaults, piping and other appurtenances will be installed to
provide interconnections between the parallel raw water mains. The purpose of this
project is to mitigate the risk of failure of the existing PCCP lines, and increasing capacity
by replacing them with 54” ductile iron or steel pipe. The interconnections serve to
maintain maximum available capacity in the event one of the parallel mains is out of
operation.
1.03 CONTRACTS
A. The project will be performed under a single contract.
1.04 WORK OF THIS CONTRACT
A. Removal of both existing 48” PCCP and replace with new 54” ductile iron or steel pipe
from the pump station up to the first gate to the pump station.
1. Approximately 200 feet of each pipeline will be installed beneath the bridge
connecting the pump station and land. The new raw water mains will be connected to
the piping immediately inside the pump station.
a. The contractor shall develop means/methods for installing the new raw water
mains under the bridge and submit to the Owner and Engineer for review and
approval.
b. Examples of methods that may be considered include:
1) Example Method 1: Floating or barging sections in via water and lifting them
into place using the access points on the bridge deck and holding in place
while the supports are set and the joints welded, or
2) Example Method 2: Installing the joints of pipe from land. The contractor will
utilize the circular void in the bridge abutment left from the removed 48”
PCCP to insert sections of new pipe (similar OD) into place in saddles. The
access points in the bridge deck will be utilized to access and stabilize the
pipe as it’s being moved into place and welded together.
c. The contractor is not bound to one of the examples provided above and will
consider other means/methods for completing this portion of the work.
2. The remaining pipe will be along the existing pipeline and will require the complete
removal of the existing 48” PCCP and replacement with a new 54” ductile iron or
steel pipe generally in the same trench. Construction of only one raw water main will
Lake Keowee to Adkins WTP Raw Water System Summary of Work
154828 01 11 00 - 2
be done at a time to ensure the operation of the raw water system through the other
parallel main.
B. Installation of two interconnections along the raw water pipeline. One interconnection will
be located near the first gate for the pump station and the second one will be located at
the beginning of the cross-country portion of the pipeline.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Environmental Conditions
154828 01 11 80 1
SECTION 01 11 80
ENVIRONMENTAL CONDITIONS
PART 1 GENERAL
1.01 ENVIRONMENTAL CONDITIONS
A. This section describes the environmental conditions which have been observed at the
site of the work and which may reasonably be anticipated throughout the life of the
project.
1.02 CLIMATE CONDITIONS
A. The site of the work is at elevations between 800 and 900 feet above mean sea level.
B. Climate conditions are described as follows:
Description JAN FEB MAR APR MAY JUN
Average Max.
Temperature (ºF) 49.9 53.1 61.6 71.7 79.1 85.6
Average Min.
Temperature (ºF) 31.2 33.7 39.8 48.5 57.9 67.0
Average Total
Precipitation (in) 4.11 4.01 4.61 3.61 3.79 4.62
Description JUL AUG SEP OCT NOV DEC
Average Max.
Temperature (ºF) 88.8 87.9 81.1 71.4 61.7 51.7
Average Min.
Temperature (ºF) 70.4 69.4 61.8 50.7 41.7 34.0
Average Total
Precipitation (in) 4.9 4.66 4.32 3.78 4.15 4.21
South Carolina State Climate Office
1.03 ADDITIONAL CONDITIONS
A. Additional conditions which may be applicable are specified in other sections.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Work Sequence
154828 01 12 16 - 1
SECTION 01 12 16
WORK SEQUENCE
PART 1 GENERAL
1.01 CONTINUITY OF PLANT OPERATIONS
1.02 The existing raw water pump station is currently operation and available to Greenville water
to pump water from lake Keowee to the Adkins WTP. Temporary shutdown of portions of the
pump station may be necessary during construction of the raw water lines and
interconnections. The contractor shall coordinate the work with Greenville Water to provide
as little interference with normal operation as possible.
1.03 SUBMITTAL
A. In accordance with Section 01 33 00, the Contractor shall submit a detailed outage plan
and time schedule for operations which will make it necessary to remove a pipeline,
electrical circuit, equipment, or structure from service. The schedule shall be coordinated
with the construction schedule specified in the General Conditions of the Contract
Documents and shall meet the restrictions and conditions specified in this section. The
detailed plan shall describe the Contractor's method for bypassing, the length of time
required to complete said operation, and equipment which the Contractor shall provide in
order to bypass.
B. The Contractor shall observe the following restrictions:
1. Systems or individual equipment items shall be isolated, dewatered,
decommissioned, deenergized, or depressurized in accordance with the detailed
outage plan and schedule.
2. The Construction Manager shall be notified in writing at least one week in advance of
the planned operation.
1.04 PRECONSTRUCTION MEETING
A. Owner will schedule meeting after Contract time starts to run.
B. Attendance Required: Owner, Engineer, and Contractor.
C. Agenda:
1. Execution of Owner-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of Subcontractors, list of products, schedule of values, and
progress schedule.
5. Designation of personnel representing parties in Contract, Engineer, independent
testing firm.
6. Procedures and processing of field decisions, submittals, and substitutions,
applications for payments, proposal requests, Change Orders, and Contract closeout
procedures.
7. Scheduling.
Lake Keowee to Adkins WTP Raw Water System Work Sequence
154828 01 12 16 - 2
D. Engineer will record minutes and distribute copies within two days after meeting to
participants, with two (2) copies to Engineer, Owner, Contractor, and those affected by
decisions made.
1.05 SEQUENCE AND SCHEDULE OF CONSTRUCTION
A. The construction schedule required in Section 01 32 16 shall provide for the following
recommended sequence. The following is general in nature, without specific details,
means and methods. Variances to this sequence may be made in coordination with the
Owner and Engineer.
1. Install all Silt Fencing and additional sediment and erosion control measures as
deemed necessary.
2. Conduct field verification of the location, size, depth, configuration, and other
pertinent information that may impact design parameters.
3. Review connection details with the design engineer and owner and submit shop
drawings.
4. Submit detailed installation plan for raw water lines beneath access bridge.
5. Coordinate for the shut down of raw water pumps associated with the first raw water
line to be replaced.
6. Dewater the first existing raw water line.
7. Install first new raw water line to the access gate, to include valve vaults for future
interconnection.
8. Test new piping as specified in the Contract Documents.
9. Place first new raw water main in service.
10. Repeat steps 5 through 9 for the second raw water main and connect to the first
interconnection at the pump station access road gate.
11. Submit plan for shut down of raw water pumps/mains for installation of second
interconnection.
12. Install the second interconnection.
13. Return to normal operation with all interconnection valves open.
14. Perform final site grading, restoration, seeding and paving.
15. Submit as-built information.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 1
SECTION 01 12 50
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 DESCRIPTION
A. Measurements of the completed work shall be in accordance with, and by instruments
and devices calibrated to United States Standard Measures and the units of
measurement for payment, and the limits thereof, shall be made as shown on the Plans,
Specifications and General Specifications.
B. Each item for which payment will be made is listed in the Bid Schedule. Work specified or
shown on the Drawings for which the Bid Schedule does not provide a separate lump
sum or unit price, or which is incidental, is not separately paid. Costs for such work are
compensated in the prices bid for other work items.
C. The Bid Amounts for each Bid Item will be used for comparative bid analysis. The Bid
amounts will also form the basis of monthly progress payments. Bid items are not
intended to be exclusive descriptions of work categories and the Contractor shall
determine and include in its pricing all materials, labor, and equipment necessary to
complete each Bid Item (work phase) as shown and specified.
1.02 METHODS OF MEASUREMENT
A. Measure quantities in accordance with standard industry practice, and as specified
herein.
B. Units of measurement are indicated on the Bid Schedule for each unit price item of work.
Payment shall be made by multiplying the quantities measured by the unit price bid for
the item of work. The costs for performing each item of work shall be included in the
price bid for the item in which the work is required.
C. Payments for lump sum items will be made in accordance with a well-balanced, detailed
apportionment of the lump sum, prepared by the Contractor and approved by the
Engineer.
D. Measurements of allowance-based items shall be on the basis of allowable documented
costs, as specified herein, for labor, equipment, materials and services, and subcontracts
as submitted by the Contractor in the form of time-cards, and invoices.
1.03 REJECTED, EXCESS, AND WASTED MATERIAL
A. The following quantities will not be included for payment:
1. Quantities of material wasted or disposed of in a manner not called for under the
Contract or as a consequence of the construction method used to perform the work.
2. Rejected loads of material, including material rejected after it has been placed by
reasons of the failure of the Contractor to comply with the provisions of the Contract.
3. Material not unloaded from the transporting vehicle.
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 2
4. Material placed outside the lines indicated on the Drawings or established by the
Engineer.
5. Material not incorporated into the final Work.
6. Material remaining on hand after completion of the Work.
1.04 MOBILIZATION AND DEMOBILIZATION
A. MEASUREMENT
1. Measurement for this item shall be based on satisfactory progress of mobilization
and demobilization of the general contractor and any subcontractors.
B. PAYMENT
1. Payment for mobilization and demobilization will be made at the lump sum price
named. This price shall constitute full payment for mobilization and demobilization,
complete as specified. The lump sum price for mobilization and demobilization shall
include all costs for obtaining all bonds, permits, and licenses; location and
procurement of a staging area/storage yard; moving onto and off of the site of all
equipment; furnishing and erecting construction facilities; cleanup; and all
preparatory work as required for the proper performance and completion of the
project, including all work items not identified in a separate bid item. The Total Price
for mobilization and demobilization shall not exceed 5 percent of the total bid price
and payment of 66% of this line item shall be made for mobilization and 34% for
demobilization.
1.05 CLEARING AND GRUBBING
A. No separate payment shall be made for clearing and grubbing. The costs for such work
shall be included in other bid items.
1.06 CLEAN-UP AND TESTING
A. No separate payment shall be made for clean-up and testing, the costs of which shall be
included in the item to which it pertains.
1.07 EROSION, SEDIMENTATION AND DUST CONTROL
A. MEASUREMENT
1. Measurement for this item will be based on the percentage of work necessary to
implement temporary and permanent erosion and sedimentation control measures.
B. PAYMENT
1. Payment will be made at the lump sum price submitted on the Bid Schedule.
Payment shall be full compensation for all labor, materials, and equipment required
to implement and maintain erosion and sedimentation control measures as specified
and on the drawings. This bid price shall constitute full payment for such measures
including, but not limited to, grassing, silt fencing, rip rap, stone check dams,
sediment tubes, watering for dust control and other measures stipulated.
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 3
1.08 DEWATER RAW WATER MAINS
A. MEASUREMENT
1. Measurement for this item will be based on the percentage of work necessary to
dewater the existing raw water mains.
B. PAYMENT
1. Payment will be made at the lump sum price submitted on the Bid Schedule.
Payment shall be full compensation for all labor, materials, and equipment required
to dewater the raw water mains during construction. This bid price shall constitute
full payment for such measures including, but not limited to, dewatering, filtering of
water, and routing water to nearby storm drain.
1.09 TRENCH DEWATERING, EXCAVATION AND BACKFILL
A. No separate payment shall be made for trench excavation and backfill, the costs of which
shall be included in the bid item to which it pertains. No separate payment shall be made
for any unique method or technique required for the Contractor to complete the work in
accordance with the Contract Documents or federal, state and local regulations, permits,
laws and requirements.
B. No separate payment shall be made for trench sheeting, shoring and bracing, the costs
of which shall be included in the bid item to which it pertains. No additional
compensation shall be made for completion of all planning, design, engineering fees as
well as furnishing, constructing, removal, and disposal of such temporary and/or
permanent sheeting, shoring, and bracing as required under the provisions of any
permits, laws, regulations and in accordance with the requirements of OSHA.
C. No separate payment will be made for bedding, initial backfill and subsequent backfill.
No separate payment will be made for the trench foundation prepared as indicated in
Section 31 23 00 and on the Drawings, except for trench stabilization. The costs for
bedding, foundation, initial backfill and subsequent backfill shall be included in the item
bid for the associated pipeline.
D. No separate payment shall be made for designing, furnishing, installing, operating,
monitoring, maintaining, and removing temporary dewatering and drainage systems as
required to lower and control water levels to at least 2 feet below the lowest level of the
excavation to permit construction in the dry. Contractor shall obtain and pay for all
permits required for temporary dewatering and drainage systems.
1.10 ROCK EXCAVATION
A. No separate payment shall be made for rock excavation, the costs of which shall be
included in the item to which it pertains.
1.11 DUCTILE IRON RAW WATER MAIN
A. MEASUREMENT
1. Ductile Iron raw water mains shall be measured in linear feet to the nearest whole
number, along a horizontal plane along the centerline alignment, without deduction
for fittings or intermediate structures.
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 4
B. PAYMENT
1. Installation of new pipe of the size indicated by open-cut trench method, complete as
specified, including but not limited to utility potholing, all site clearing, existing
improvement protection, excavation, joint and pipe restraints, bedding foundation
support materials, thrust blocks, backfill, compaction, dewatering, warning/tracer
tapes and wires, filter fabrics, approved support of existing utilities, removal and
disposal of existing pipes and structures (other than allowed for in the Demolition of
Existing Raw Water Mains bid item), removal and disposal of trench spoils, old pipes
and old structures required to be removed, surface restoration in the trench repair
area prior to final paving, cleanup, testing of new pipe, and all labor, equipment,
materials and incidentals required for the work. No separate payment will be made
for modifying the original horizontal or vertical alignment to avoid existing utilities,
mains or services not shown, except where authorized for additional pipe and/or
fittings.
1.12 DEMOLITION OF EXISTING RAW WATER MAINS
A. MEASUREMENT
1. Measurement for this item will be based on the percentage of work necessary to
demolish the existing raw water mains and any necessary appurtenances.
B. PAYMENT
1. Payment will be made at the lump sum price submitted on the Bid Schedule.
Payment shall be full compensation for all labor, materials, and equipment required
to remove and dispose of the existing raw water mains and appurtenances as
specified and on the drawings. This bid price shall constitute full payment for such
measures including, but not limited to, removal and disposal of piping, air valves,
manholes, and other appurtenances necessary.
1.13 SITE IMPROVEMENTS
A. No separate payment shall be made for demolition, the costs of which shall be included
in the item to which it pertains.
1.14 FITTINGS
A. MEASUREMENT
1. Fittings will be measured based on the number of fittings, regardless of bend angle,
installed with restraint. Fittings associated with the interconnections will be paid for
under the Interconnection bid item.
B. PAYMENT
1. Payment for fittings will be made at the authorized quantity installed, at the unit price
indicated in the Bid. No separate payment shall be made for fitting restraint, to
include thrust blocking, retainer glands or harnessing at the fitting.
1.15 VALVES
A. No separate payment shall be made for valves, the costs of which shall be included in
the Interconnection bid item.
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 5
1.16 AIR RELEASE VALVE
A. MEASUREMENT:
1. Air release valves shall be measured based on the number installed complete in
place.
B. PAYMENT:
1. Payment for air release valves shall be made based on the authorized quantity at the
unit price indicated in the Bid. The bid price shall constitute full payment for the air
valve, piping, tapping saddle, fittings, vault, box, stone, and all related items as called
for on the drawings and in the specifications.
1.17 REMOVE AND REPLACE PAVEMENT
A. MEASUREMENT:
1. Asphalt and/or concrete pavement removal and replacement includes all work
necessary to remove existing paving, providing and compacting select backfill,
replacing the pavement, providing traffic control and providing temporary measures
for maintaining traffic. Measurement shall be based on square yards, to the nearest
one-tenth, at the type of pavement specified.
B. PAYMENT:
1. Payment to remove and replace pavement will be made for the quantity authorized at
the type indicated, in square yards, at the unit price indicated in the Bid. No
additional payment will be made for repairing damaged pavement adjacent to the
saw cut.
1.18 RESURFACE ASPHALT PAVEMENT
A. MEASUREMENT:
1. Asphalt pavement resurfacing will be measured on the basis of square yardage, to
the nearest whole number, in accordance with the limits for resurfacing directed by
the Engineer.
B. PAYMENT:
1. Payment for resurface asphalt pavement will be made at the authorized quantity,
measured in square yards, at the unit price indicated in the Bid. The bid price shall
constitute full payment for milling, removal of asphalt, new asphalt surface, striping,
and other necessary appurtenances.
1.19 CONNECT NEW RAW WATER MAIN AT INTAKE PUMP STATION
A. MEASUREMENT:
1. Connection of new raw water main at the intake pump station shall be measured
based on each connection installed.
B. PAYMENT:
1. Payment for connection of new raw water main at the intake pump station shall be
made at the authorized quantity at the bid price indicated on the Bid. Each
connection shall include evaluating the interior of the existing 48” steel pipe at the
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 6
pump station wall, fabricating steel pipe and connection ring, welding connections,
and all related items as called for on the drawings and specifications.
1.20 INTERCONNECTION SITE 1
A. MEASUREMENT:
1. Measurement for Interconnection Site 1 will be based on a proportioned percentage
of work necessary to complete the work as outlined in the Contractor’s Schedule of
Values.
B. PAYMENT:
1. Payment for Interconnection Site 1 shall be made at the lump sum price indicated on
the Bid. The Interconnection Site 1 shall include dismantling existing 48” PCCP raw
water, installing new piping, fittings, valves, vaults, thrust restraint, couplings,
restraints, wall penetrations, grouting, and all related items as called for on the
drawings and specifications. Connections to the new 54” DI or steel pipe and to the
existing 48” PCCP are included in this bid item.
1.21 INTERCONNECTION SITE 2
A. MEASUREMENT:
1. Measurement for Interconnection Site 2 will be based on a proportioned percentage
of work necessary to complete the work as outlined in the Contractor’s Schedule of
Values.
B. PAYMENT:
1. Payment for Interconnection Site 2 shall be made at the lump sum price indicated on
the Bid. The Interconnection Site 2 shall include removing portions of the existing
54” DI raw water, installing new piping, fittings, valves, vaults, thrust restraint,
couplings, restraints, wall penetrations, grouting, and all related items as called for
on the drawings and specifications. Connections to the new 54” DI or steel pipe and
to the existing 54” DI pipe are included in this bid item.
1.22 54” STEEL RAW WATER MAIN (UNDER BRIDGE FROM STA. 0+00 TO STA. 1+90, INCLUDING
SUPPORTS, ETC.)
A. MEASUREMENT:
1. Raw water mains underneath the bridge shall be measured in linear feet to the
nearest whole number, along a horizontal plane along the centerline alignment,
without deduction for fittings or intermediate structures. The contractor shall develop
means/methods for installing the new raw water mains under the bridge and submit
to the Owner and Engineer for review and approval. This bid item is intended for
compensation of the mains, regardless of the method utilized by the Contractor.
Reference Section 01 11 00, paragraph 1.04.A.
B. PAYMENT:
1. Installation of new pipe of the size indicated by necessary method, complete as
specified, including but not limited to protecting existing facilities (including electrical
conduits), providing crane and barge support equipment, excavation, joint and pipe
restraints, support materials, backfill, compaction, trench dewatering, transition to
Lake Keowee to Adkins WTP Raw Water System Measurement & Payment
154828 01 12 50 - 7
downstream DI or steel piping, surface restoration, cleanup, testing of new pipe, and
all labor, equipment, materials, and incidentals required for the work.
1.23 EMERGENCY PCCP PIPE REPAIR KIT
A. MEASUREMENT
1. Emergency PCCP Pipe Repair Kit shall be measured based on the number prepared
and delivered to the Adkins WTP or other location as directed by the Owner.
B. PAYMENT
1. Payment for Emergency PCCP Repair Kit shall be all costs associated with the
fabrication and delivery of 48-inch ductile iron pipe and fittings to repair a future
failure of the 48-inch PCCP raw water main between the intake pump station and the
water treatment plant. The repair kit shall be custom sized to fit the existing 48-inch
PCCP pipe, based on the dimensions taken and fittings prepared for Interconnections
1 and 2. The repair kit shall be suitable for a repair length of up to 20 feet and will
include sleeves/adaptors to connect to the existing PCCP main at 2 points.
1.24 CONTINGENCY ALLOWANCE
A. The Contractor shall include in the bid total, the amount shown for continency allowance
shown on the Bid.
B. Should the cost of the allowance be greater or less than the amount shown, the Contract
will be adjusted as needed, in accordance with provisions in the Contract Documents.
C. The contingency allowance is intended to provide adequate budget to cover items not
precisely determined by the Owner and unforeseeable conditions prior to bid. The
Contractor shall include the amount specified by the Owner in the bid to be used by the
Owner for items not specifically identified in the Contract Documents. The Owner will
specifically authorize any items to be covered under the Contingency Allowance. The
Contractor shall invoice items authorized for payment under the Contingency Allowance
with his monthly pay applications. The amount invoiced will be deducted from the lump
sum amount.
1.25 ALTERNATE BID ITEM A1 – 54” STEEL RAW WATER MAIN AND FITTINGS
A. Description: This alternate bid item is to provide steel pipe in lieu of ductile iron pipe and
fittings from Station 1+90 to Interconnection 1. If accepted, the unit price will replace the
bid items for A-10 and A-12 (ductile iron pipe and fittings). Measurement and payment
will be based on the linear feet to the nearest whole number, as outlined for ductile iron
raw water mains. Any fittings shall be included in this bid item, regardless of the quantity
provided.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Use of Site
154828 01 14 19 - 1
SECTION 01 14 19
USE OF SITE
PART 1 GENERAL
1.01 SUMMARY
A. The Owner's operating personnel will be responsible for operating the existing pump
stations throughout the execution of this contract. Equipment presently installed in the
pump stations must be available to Owner’s personnel at all times for use, maintenance,
and repair. If it is necessary in the course of operating the pump stations, for the
Contractor to move his equipment, materials, or any material included in the work, he
shall do so promptly and place that equipment or material in an area which does not
interfere with the pump station operation. The Contractor shall not adjust or operate
serviceable or functioning equipment or systems except as specifically required by this
contract. All lighting associated with the existing pump station shall stay in service until
the new station and associated lighting is brought online.
B. The Contractor shall schedule and conduct his work to minimize necessary shutdowns
and interference with normal system operations and maintenance.
C. The Contractor shall notify the Construction Manager, in accordance with Section 01 12
16, 1 week in advance of the time it is necessary to take out of service any existing tank,
pipeline, channel, electrical circuit, equipment or structure. The Contractor shall be
responsible for providing whatever temporary piping, pumping, power, and control
facilities as are required to maintain continuous pumping operation except as otherwise
specified. The integrity of existing station utilities shall be maintained by the Contractor at
all times.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Construction Progress Schedule
154828 01 32 16 - 1
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1 GENERAL
1.01 SCOPE
A. This section specifies reports and schedules for planning and monitoring the progress of
the work.
1.02 DESCRIPTION
A. The Contractor shall provide a graphic construction schedule indicating the various
subdivisions of the work and the dates of commencing and finishing each. The schedule
shall show the time allowed for testing and for other procedures which must be
completed prior to the work being put into operation. The schedule will take into account
the time of completion and the specific dates as specified in the Contract Documents
and the work sequence described in Section 01 12 16.
1.03 SUBMITTAL PROCEDURES
A. Within 20 days after the date of the Notice to Proceed, the Contractor shall submit in
accordance with Section 01 33 00, a construction schedule conforming to paragraph
1.02 Description. The format submitted shall be PDF.
B. Within 7 calendar days after receipt of the submittal, the Construction Manager shall
review the submitted schedule and return one copy of the marked up original to the
Contractor. If the Construction Manager finds that the submitted schedule does not
comply with specified requirements, the corrective revisions will be noted on the
submittal copy returned to the Contractor.
1.04 SCHEDULE REVISIONS
A. Revisions to the accepted construction schedule may be made only with the written
approval of the Contractor and Owner. A change affecting the contract value of any
activity, the completion time, and specific dates as specified in the Contract Documents
and sequencing (Section 01 12 16) may be made only in accordance with applicable
provisions of the General Conditions of the Contract Documents.
1.05 PROJECT STATUS UPDATE
A. Project status review and update shall be provided each month as specified in the
General Conditions of the Contract Documents.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Survey and Layout Data
154828 01 32 23 - 1
SECTION 01 32 23
SURVEY AND LAYOUT DATA
PART 1 GENERAL
1.01 SURVEY AND LAYOUT
A. The Owner will establish reference benchmarks and baselines as specified.
B. From the information provided, the Contractor shall develop and make such additional
surveys as are needed for construction, such as control lines, slope stakes, batter
boards, stakes for pipe locations and other working points, lines, and elevations.
C. Survey work shall be performed under the supervision of a licensed land surveyor or
registered civil engineer. Contractor shall reestablish reference benchmarks and survey
control monuments destroyed by his operations at no cost to the Owner.
D. Submit copy of an as-built survey sealed and signed by Land Surveyor certifying
elevations and locations of the Work are in conformance with Contract Documents.
E. Maintain complete and accurate log of control and survey work as Work progresses.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Photographic Documentation
154828 01 32 33 - 1
SECTION 01 32 33
PHOTOGRAPHIC DOCUMENTATION
PART 1 GENERAL
1.01 PRECONSTRUCTION PHOTOGRAPHS AND VIDEO
A. The Contractor shall provide preconstruction photographs and video prior to
commencement of work on the site. The photographs shall be digital, and shall indicate
the date on the image. The file name shall indicate the date and location where the
photograph was taken. Before construction may start, preconstruction photos shall be
submitted, in accordance with Section 01 33 00, to the Engineer on a CD or DVD.
B. Preconstruction photographs shall be taken at locations to be designated by the Owner/
Engineer. The photographer shall be equipped to photograph either interior or exterior
exposures. Photographs shall be taken to document the existing condition of the area
where work is to be performed; and may be used to support or dispel claims by property
owners upon completion of the work.
1.02 CONSTRUCTION PHOTOGRAPHS
A. The Contractor shall provide construction photographs showing the progress of the work.
The photographs shall be taken of such subjects as may be directed, and shall indicate
on the front of each image the date. The file name will include the date, job title and brief
description of the photograph including the location where the photograph was taken.
1.03 REQUIRED NUMBER OF PHOTOGRAPHS
A. For the work of this contract, photographs shall be provided as needed to document
existing conditions, as well as the post-construction condition.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Submittal Procedures
154828 01 33 00 - 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.01 SUBMITTALS
A. Submittals covered by these requirements include manufacturers' information, shop
drawings, test procedures, test results, samples, requests for substitutions, and
miscellaneous work-related submittals. Submittals shall also include, but not be limited
to, all mechanical, electrical and electronic equipment and systems, materials,
reinforcing steel, fabricated items, and piping and conduit details. The Contractor shall
furnish all drawings, specifications, descriptive data, certificates, samples, tests,
methods, schedules, and manufacturer's installation and other instructions as
specifically required in the contract documents to demonstrate fully that the materials
and equipment to be furnished and the methods of work comply with the provisions and
intent of the contract documents.
1.02 CONTRACTOR'S RESPONSIBILITIES
A. General:
1. The Contractor shall be responsible for the accuracy and completeness of the
information contained in each submittal and shall assure that the material,
equipment or method of work shall be as described in the submittal. The Contractor
shall verify that all features of all products conform to the specified requirements.
Submittal documents shall be clearly edited to indicate only those items, models, or
series of equipment, which are being submitted for review. All extraneous materials
shall be crossed out or otherwise obliterated. The Contractor shall ensure that there
is no conflict with other submittals and notify the Construction Manager in each case
where his submittal may affect the work of another contractor or the Owner. The
Contractor shall coordinate submittals among his subcontractors and suppliers
including those submittals complying with unit responsibility requirements specified
in paragraph 43 05 11-1.02 Unit Responsibility and applicable technical sections.
2. The Contractor shall coordinate submittals with the work so that work will not be
delayed. He shall coordinate and schedule different categories of submittals, so that
one will not be delayed for lack of coordination with another. No extension of time will
be allowed because of failure to properly schedule submittals. The Contractor shall
not proceed with work related to a submittal until the submittal process is complete.
This requires that submittals for review and comment shall be returned to the
Contractor stamped "No Exceptions Taken" or "Make Corrections Noted."
3. The Contractor shall certify on each submittal document that he has reviewed the
submittal, verified field conditions, and complied with the contract documents.
4. The Contractor may authorize in writing a material or equipment supplier to deal
directly with the Construction Manager or with the Owner with regard to a submittal.
These dealings shall be limited to contract interpretations to clarify and expedite the
work.
1.03 CATEGORIES OF SUBMITTALS
A. General:
Lake Keowee to Adkins WTP Raw Water System Submittal Procedures
154828 01 33 00 - 2
a. Submittals fall into three general categories; Action Submittals - Action
Submittals require review and response by the Engineer before the Contractor
proceeds with incorporating the equipment, materials, or procedure addressed in
a submittal into the work. Review comments for Action Submittals, and the
subsequent actions of the Contractor based on the review comments, shall
conform to REVIEW ACTION requirements specified in this section.
b. Informational Submittals- Informational Submittals are examined to verify that
the information has been furnished as specified. If the information has not been
furnished as specified the submittal will be returned marked “MAKE
CORRECTIONS NOTED” and any deficiencies will be noted. If the information has
been furnished as specified the submittal will be returned marked “RECEIPT
ACKNOWLEDGED”. CSI’s informational submittals are similar to what BC formerly
called PRODUCT DATA. Note: BC Testing Requirements can be either Action or
Information Submittals.
c. Closeout Submittals – Closeout Submittals consist of documentation that is not
available for review at the time Action Submittals are submitted for review or
documentation that is typically generated or furnished following incorporation of
the equipment, materials, or procedure into the work. Closeout submittals
include project record documents, O&M submittals, spare parts inventory listing,
spare parts, extra stock materials, special tools and other materials or
components that are furnished separate from the installed and completed work.
Closeout Submittals require review and response by the Engineer. Closeout
Submittal requirements are not satisfied until they have been reviewed and
returned marked “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.
2. At the beginning of work, the Construction Manager will furnish the Contractor lists of
those submittals specified in the project manual. Two separate lists will be provided:
submittals for review and comment and product data (submittals) for information
only.
B. Submittals for review and comment:
1. All submittals except where specified to be submitted as product data for information
only shall be submitted by the Contractor to the Construction Manager for review and
comment.
C. Submittals (product data) for information only:
1. Where specified, the Contractor shall furnish submittals (product data) to the
Construction Manager for Information only. Submittal requirements for operation and
maintenance manuals, which are included in this category, are specified in Section
01 78 23.
1.04 TRANSMITTAL PROCEDURE
A. General:
1. Unless otherwise specified, submittals regarding material and equipment shall be
accompanied by Transmittal Form 01 33 00-A specified in Section 01 99 90.
Submittals for operation and maintenance manuals, information and data shall be
accompanied by Transmittal Form 01 78 23-A specified in Section 01 99 90. A
separate form shall be used for each specific item, class of material, equipment, and
items specified in separate, discrete sections, for which the submittal is required.
Submittal documents common to more than one piece of equipment shall be
Lake Keowee to Adkins WTP Raw Water System Submittal Procedures
154828 01 33 00 - 3
identified with all the appropriate equipment numbers. Submittals for various items
shall be made with a single form when the items taken together constitute a
manufacturer's package or are so functionally related that expediency indicates
checking or review of the group or package as a whole.
2. A unique number, sequentially assigned, shall be noted on the transmittal form
accompanying each item submitted. Original submittal numbers shall have the
following format: "XXX"; where "XXX" is the sequential number assigned by the
Contractor. Resubmittals shall have the following format: "XXX-Y"; where "XXX" is the
originally assigned submittal number and "Y" is a sequential letter assigned for
resubmittals, i.e., A, B, or C being the 1st, 2nd, and 3rd resubmittals, respectively.
Submittal 25B, for example, is the second resubmittal of submittal 25.
B. Deviation from contract:
1. If the Contractor proposes to provide material, equipment, or method of work which
deviates from the project manual, he shall indicate so under "deviations" on the
transmittal form accompanying the submittal copies.
C. Submittal completeness:
1. Submittals which do not have all the information required to be submitted, including
deviations, are not acceptable and will be returned without review.
1.05 REVIEW PROCEDURE
A. General:
1. Submittals are specified for those features and characteristics of materials,
equipment, and methods of operation which can be selected based on the
Contractor's judgment of their conformance to the specified requirements. Other
features and characteristics are specified in a manner which enables the Contractor
to determine acceptable options without submittals. The review procedure is based
on the Contractor's guarantee that all features and characteristics not requiring
submittals conform as specified. Review shall not extend to means, methods,
techniques, sequences or procedures of construction, or to verifying quantities,
dimensions, weights or gages, or fabrication processes (except where specifically
indicated or required by the project manual) or to safety precautions or programs
incident thereto. Review of a separate item, as such, will not indicate approval of the
assembly in which the item functions.
2. When the contract documents require a submittal, the Contractor shall submit the
specified information as follows:
a. Digital copy of all submitted information plus one reproducible hard copy original
of all information shall be transmitted with submittals for review and comment.
b. Unless otherwise specified, digital copies of all submitted information shall be
transmitted with submittals (Product Data) for information only.
B. Submittals for review and comment:
1. Unless otherwise specified, within 35 calendar days after receipt of a submittal for
review and comment, the Construction Manager shall review the submittal and return
digital copy of the marked-up reproducible original noted in 1 above. The
reproducible original will be retained by the Construction Manager. The returned
submittal shall indicate one of the following actions:
Lake Keowee to Adkins WTP Raw Water System Submittal Procedures
154828 01 33 00 - 4
a. If the review indicates that the material, equipment or work method complies
with the project manual, submittal copies will be marked "NO EXCEPTIONS
TAKEN." In this event, the Contractor may begin to implement the work method or
incorporate the material or equipment covered by the submittal.
b. If the review indicates limited corrections are required, copies will be marked
"MAKE CORRECTIONS NOTED." The Contractor may begin implementing the work
method or incorporating the material and equipment covered by the submittal in
accordance with the noted corrections. Where submittal information will be
incorporated in O&M data, a corrected copy shall be provided.
c. If the review reveals that the submittal is insufficient or contains incorrect data,
copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the
Contractor shall not undertake work covered by this submittal until it has been
revised, resubmitted and returned marked either "NO EXCEPTIONS TAKEN" or
"MAKE CORRECTIONS NOTED."
d. If the review indicates that the material, equipment, or work method does not
comply with the project manual, copies of the submittal will be marked
"REJECTED - SEE REMARKS." Submittals with deviations which have not been
identified clearly may be rejected. Except at his own risk, the Contractor shall not
undertake the work covered by such submittals until a new submittal is made
and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS
NOTED."
C. Submittals (product data) for information only:
1. Such information is not subject to submittal review procedures and shall be provided
as part of the work under this contract and its acceptability determined under normal
inspection procedures.
1.06 EFFECT OF REVIEW OF CONTRACTOR'S SUBMITTALS:
A. General:
1. Review of contract drawings, methods of work, or information regarding materials or
equipment the Contractor proposes to provide, shall not relieve the Contractor of his
responsibility for errors therein and shall not be regarded as an assumption of risks
or liability by the Construction Manager or the Owner, or by any officer or employee
thereof, and the Contractor shall have no claim under the contract on account of the
failure, or partial failure, of the method of work, material, or equipment so reviewed.
A mark of "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED" shall mean
that the Owner has no objection to the Contractor, upon his own responsibility, using
the plan or method of work proposed, or providing the materials or equipment
proposed.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Environmental Procedures
154828 01 35 43-1
SECTION 01 35 43
ENVIRONMENTAL PROCEDURES
PART 1 GENERAL
1.01 SITE MAINTENANCE
A. The Contractor shall keep the work site clean and free from rubbish and debris. Materials
and equipment shall be removed from the site when they are no longer necessary. Upon
completion of the work and before final acceptance, the work site shall be cleared of
equipment, unused materials, and rubbish to present a clean and neat appearance.
1.02 TEMPORARY DAMS
A. Except in time of emergency, earth dams are not acceptable at catch basin openings,
local depressions, or elsewhere. Temporary dams of sand bags, asphaltic concrete, or
other acceptable material will be permitted when necessary to protect the work, provided
their use does not create a hazard or nuisance to the public. Such dams shall be
removed from the site as soon as they are no longer necessary.
1.03 AIR POLLUTION CONTROL
A. The Contractor shall not discharge smoke, dust, and other contaminants into the
atmosphere that violate the regulations of any legally constituted authority. He shall also
abate dust nuisance by cleaning, sweeping, and sprinkling with water, or other means as
necessary. The use of water, in amounts which result in mud on public streets, is not
acceptable as a substitute for sweeping or other methods.
1.04 NOISE CONTROL
A. Between 7:30 p.m. and 7:00 a.m., noise from Contractor's operations shall not exceed
limits established by applicable laws or regulations and in no event shall exceed 86 dBA
at a distance of 50 feet from the noise source.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 1
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 DESCRIPTION:
A. This Section specifies administrative and procedural requirements for quality control
services, field inspections and field testing of civil and structural constructs required for
this project. Contractor is responsible for the quality assurance and quality control of
their respective work.
1.02 DEFINITIONS:
A. Quality Control System (QCS): The quality control, assurance, and inspection system
established and carried out to ensure compliance with the Plans and Specifications.
B. QCS Supervisor: That person in responsible charge of the work occurring, as designated
by the Contractor in the QCS Plan.
C. QCS Inspector: Responsible, certified personnel inspecting the various constructs at
specified milestones and during the project overall and designated by the Construction
Manager. The Special Inspector is part of the QCS Inspector team.
D. Factory Test: Tests made on various materials, products and component parts prior to
shipment to the job site.
E. Field Tests: Tests and analyses made at or in the vicinity of the job site in connection with
the actual construction.
F. Certified Inspection Report: Reports signed by approved inspectors attesting that the
items inspected meet the specification requirements other than any exceptions included
in the report
G. Certificate of Compliance: Certificate from the manufacturer of the material or equipment
identifying said manufacturer, product and referenced standard, and shall be signed by a
designated officer of the manufacturer.
H. Standard Compliance: Condition whereby specified materials or equipment must
conform to the standards of organizations such as the American National Standard
Institute (ANSI), American Society for Testing and Materials (ASTM), Underwriters
Laboratories (UL) or similar organization.
I. Quality Assurance: The day-to-day, in-process supervisory observations of work and
materials conducted by the Contractor to assure that the proper methods and materials
are being used and installed by tradesmen.
J. Source Quality Control: The in-process testing and inspections conducted by the QCS
Inspector(s) to verify that the materials, equipment, workmanship and shop
manufactured constructs are in compliance with the Contract Documents, applicable
Codes and standards.
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 2
K. Field Quality Control: The testing and inspections conducted by the QCS Inspector(s) in
the field during and at the completion of each construct to verify that the in-process and
completed construction is in compliance with the Contract Documents, applicable Codes
and standards.
1.03 REFERENCES:
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization, or if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued,
or replaced.
Reference Title
ASTM C102 Practice for Laboratories Engaged in the Testing of Building Sealants.
ASTM C802 Practice for Conducting an Inter-Laboratory Test Program to Determine the Precision
of Test Methods for Construction.
ASTM C1093 Practice for Accreditation of Testing Agencies for Unit Masonry.
ASTM D3740 Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of Soil and
Rock as Used in Engineering Design and Construction.
ASTM D4561 Practice for Quality Control Systems for an Inspection and testing Agency for
Bituminous Paving Materials.
ASTM E329 Practice for Use in the Evaluation of Inspection and Testing Agencies as Used in
Construction.
IBC 2003 International Building Code, locally amended
1.04 CONTRACTOR’S RESPONSIBILITIES:
A. Monitor quality assurance over suppliers, manufacturers, products, services, site
conditions, and workmanship, to produce work of specified quality.
B. Coordinate with, schedule specified inspections by, and provide normal and customary
assistance to the QCS Inspectors.
C. Comply fully with manufacturers’ instructions, including each step in sequence.
D. Should manufacturers’ instructions conflict with Contract Documents, request
clarification before proceeding from Construction Manager.
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 3
E. Comply with specified standards as a minimum quality for the work except when more
stringent tolerances, codes, or specified requirements indicate higher standards or more
precise workmanship.
F. Perform work by persons qualified to produce workmanship of specified quality.
1.05 REGULATORY REQUIREMENTS:
A. General:
1. Comply with all Federal, State, and local Codes as referenced herein. Such
regulations apply to activities including, but not limited to, sitework and zoning,
building practices and quality, on and offsite disposal, safety, sanitation, nuisance,
and environmental quality.
B. Special Inspection:
1. Special Inspection shall be performed by the Special Inspector under contract with
the Construction Manager in conformance with the IBC. Special Inspection is in
addition to, but not replacing, other inspections and quality control requirements
herein. Where sampling and testing required herein conforms to Special Inspection
standards, such sampling and testing need not be duplicated.
C. Structural Observation:
1. Engineer shall make visual inspections of the work to assess general conformance
with the Contract Documents at significant construction stages and at completion of
the structural system. The QCS shall include a preliminary set of Structural
Observations and what items are expected to be observed. Contractor shall request
this preliminary set from Engineer through Construction Manager and submit as part
of their QCS submittal.
2. The following structural milestones shall be considered significant construction
stages:
a. Structure fill and deep foundations including piling.
b. Foundations prepared for concrete placement, including grade beams, pile caps,
strip, matt and pad footings, and monolithic slabs on grade.
c. Preparation of concrete, water-retaining walls prior to placement of concrete.
d. Completion of bearing walls prior to cover-up with non structural elements,
including concrete, masonry, cold formed steel, and lumber.
e. Roof and floor framing, including framed and sheathed systems, slabs, and
composite systems.
f. Completion of lateral force resisting system elements not included in the above
categories including moment connections, bracing, diaphragms, or other.
g. Completion of structural system after all significant architectural, mechanical,
plumbing, heating/ventilation equipment, electrical, and finish elements are
installed.
1.06 FIELD SAMPLE PROCEDURES:
A. When field samples are specified in a unit of work, construct each field sample to include
work of all trades required to complete the field sample prior to starting related field
work. Field samples may be incorporated into the project after acceptance by
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 4
Construction Manager. Remove unacceptable field samples when directed by
Construction Manager. Acceptable samples represent a quality level for the work.
1.07 CONTRACTOR DESIGNED STRUCTURAL SYSTEMS:
A. Design Engineering:
1. Contractor shall employ and pay for engineering services from a Professional
Engineer registered in the State of South Carolina for structural design of Contractor
designed structural systems including but not limited to temporary shoring and
bracing, formwork support, interior structural wall and ceiling systems, and support
systems for fire sprinkler, plumbing, mechanical, and electrical systems and
equipment
B. Tests And Inspections Of Contractor Designed Structural Systems:
1. Contractor shall pay for preliminary testing of concrete, grout, and mortar mix designs
where required by Code or the submittal process prior to start of such work.
Contractor shall pay for required shop and site inspection of Contractor designed
structural systems where required by Code or these specifications, to the extent such
testing and inspection exceeds that required for the structural system on the
drawings and in these specifications.
1.08 MANUFACTURERS’ FIELD SERVICES AND REPORTS:
A. When specified in individual specification sections, product suppliers or manufacturers
shall provide qualified staff personnel to observe site conditions, conditions of surfaces
and installation, quality of workmanship, start-up of equipment, test, adjust, and balance
of equipment as applicable, and to provide instructions when necessary. Contractor shall
submit qualifications of observer to Construction Manager 30 days in advance of
required observations. QCS Inspector shall record observations and site decisions or
instructions given to applicators or installers that are supplemental or contrary to
manufacturers’ written instructions.
1.09 JOB SITE CONDITIONS:
A. Schedule to ensure all preparatory work has been accomplished prior to proceeding with
current work. Proceeding with the work constitutes acceptance of conditions. Allow
adequate time for materials susceptible to temperature and humidity to “stabilize” prior
to installation. Establish and maintain environmental conditions (i.e., temperature,
humidity, lighting) as recommended by the various material manufacturers for the
duration of the work.
1.10 SUBMITTALS:
A. The following information shall be provided in accordance with Section 01 33 00 :
1. A copy of this specification section, with addendum updates included, and all
referenced and applicable sections, with addendum updates included, with each
paragraph check-marked to indicate specification compliance or marked to indicate
requested deviations from specification requirements. Check marks (✓) shall denote
full compliance with a paragraph as a whole. If deviations from the specifications are
indicated, and therefore requested by the Contractor, each deviation shall be
underlined and denoted by a number in the margin to the right of the identified
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 5
paragraph, referenced to a detailed written explanation of the reasons for requesting
the deviation. The ENGINEER shall be the final authority for determining acceptability
of requested deviations. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Failure to
include a copy of the marked-up specification sections, along with justification(s) for
any requested deviations to the specification requirements, with the submittal shall
be sufficient cause for rejection of the entire submittal with no further consideration.
2. Written description of Contractor’s proposed QCS plan in sufficient detail to illustrate
understanding and approach. The QCS plan and submittal shall include a log showing
anticipated inspections, Special Inspections, and source and field Quality Assurance
procedures. Preliminary submittal of the QCS plan may be made prior to commencing
field work. The preliminary submittal will illustrate the project’s initial three (3)
month’s work, and be followed one month later by a final QCS plan submittal.
3. Contractor’s proposed QCS Supervisor, qualifications, and if requested, references.
4. Preliminary structural observation set as described in paragraph 1.05.C Structural
Observation.
5. Complete structural system information describing Contractor designed structural
systems, including sealed calculations, shop and erection drawings, product
literature for the various components, ICBO Evaluation Reports for structural
components, and a discussion of risk issues associated with the proposed system
which could adversely impact overall project completion.
6. If requested by the Construction Manager during the work, manufacturer’s field
services and reports. If not so requested, treat same as Product Data.
PART 2 PRODUCTS
2.01 SOURCE QUALITY CONTROL:
A. Contractor Responsibilities:
1. Provide source quality control according to the reviewed and accepted QCS plan and
paragraph 1.04 herein. Coordinate with Construction Manager to facilitate the work
of the Testing Laboratory specified in Section 01 45 29 and Special Inspector.
Provide ready access to sampling and inspection locations and incidental labor
customary in such sampling and inspections. Timely prepare and submit submittals,
and revise as indicated by review comments. Comply with technical requirements in
each specification Section that applies to the work.
B. Construction Manager Responsibilities:
1. Review Contractor’s tracking of QCS activities at monthly meetings. Facilitate
completion of submittal review per Section 01 33 00. Assist Contractor to ensure
that Special Inspection occurs where and when specified.
C. Acceptance Criteria:
1. Acceptable characteristics and quality of a particular item or construct is defined in
that item’s or construct’s specification Section.
2.02 PRODUCT DATA
A. The following product data shall be provided in accordance with Section 01 33 00.
Lake Keowee to Adkins WTP Raw Water System Quality Requirements
154828 01 40 00 - 6
1. Manufacturers’ field services and reports unless requested by Construction Manager
to be submitted for review.
2. Special Inspection reports, unless otherwise directed in each technical specification
Section.
PART 3 EXECUTION
3.01 FIELD QUALITY CONTROL:
A. Field quality control responsibilities of the Contractor and Construction Manager are
substantially the same as described in paragraph 2.01, with the exception that this work
occurs primarily on the jobsite as the work progresses, and Special Inspection will occur
more often than at the source.
B. Acceptable characteristics and quality of a particular item or construct is defined in that
item’s or construct’s specification Section.
3.02 REGULATORY COMPLIANCE – SPECIAL INSPECTIONS:
A. The following types of work require Special Inspection according to Chapter 17 of the IBC
and each system’s specification Section:
1. Structure Fill.
2. Deep foundations including piling.
3. Structural concrete and reinforcing.
4. Anchor bolts and post-installed anchor systems.
5. Masonry systems, complete.
6. Structural steel and aluminum including connections.
7. Cold formed structural steel including connections.
8. Steel deck and wood sheathing.
9. Structural lumber including sawn and manufactured including connections.
10. All components of the lateral force resisting system not included in the above.
B. Section 01 45 29 describes Testing Laboratory sampling, testing and reporting, much of
which is conforming to Special Inspection requirements, and need not be replicated.
C. Contractor designed structural systems are subject to the same Special Inspection
requirements as all other work.
3.03 CORRECTION OF DEFECTIVE WORK:
A. Remove and replace defective, rejected, and condemned work at Contractor’s expense
until such work meets the requirements of Contract Documents.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 1
SECTION 01 42 19
REFERENCE STANDARDS
PART 1 GENERAL
1.01 ABBREVIATOINS
A. Wherever used in the project manual, the following abbreviations will have the meanings
listed:
Abbreviation Meaning
AA Aluminum Association Incorporated
P.O. Box 753
Waldorf, MD 20604
AAMA American Architectural Manufacturers Association
1540 East Dundee Road, Suite 310
Palatine, IL 60067
AASHTO American Association of State Highway and Transportation Officials
444 North Capitol Street, N.W., Suite 249
Washington, DC 20001
ABMA American Bearing Manufacturers Association
1200 19th Street N.W., Suite 300
Washington, DC 20036
ACI American Concrete Institute
22400 West Seven Mile Road
P.O. Box 19150, Redford Station
Detroit, MI 48219
AEIC Association of Edison Illuminating Companies
600 North 18th Street
P.O. Box 2641
Birmingham, AL 35291
AGMA American Gear Manufacturer's Association, Inc.
1500 King Street, Suite 201
Alexandria, VA 22314
AISC
American Institute of Steel Construction
One East Wacker Drive, Suite 3100
Chicago, IL 60601
AISI American Iron and Steel Institute
1101 Seventeenth Street, NW, Suite 1300
Washington, DC 20036
AMCA Air Movement and Control Association, Inc.
30 West University Drive
Arlington Heights, IL 60004
ANSI American National Standards Institute
11 West 42nd Street, 13th Floor
New York, NY 10036
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 2
Abbreviation Meaning
API American Petroleum Institute
1220 "L" Street N.W.
Washington, DC 20005
ARI Air-Conditioning and Refrigeration Institute
4301 North Fairfax Drive, Suite 425
Arlington, VA 22203
ASCE American Society of Civil Engineers
United Engineering Center
345 East 47th Street
New York, NY 10017
ASCII American Standard Code for Information Interchange
United States of America Standards Institute
10 East 40th Street
New York, NY 10016
ASHRAE American Society of Heating, Refrigeration and Air Conditioning
Engineers, Inc.
1791 Tullie Circle, NE
Atlanta, GA 30329
ASME American Society of Mechanical Engineers
345 East 47th Street
New York, NY 10017
ASTM American Society for Testing and Materials
100 Barr Harbor Drive
West Conshohocken, PA 19428
AWS American Welding Society
550 NW LeJeune Road
P.O. Box 351040
Miami, FL 33135
AWWA American Water Works Association
6666 West Quincy Avenue
Denver, CO 80235
BOCA Building Officials and Code Administrators, International, Inc.
4051 West Flossmoor Road
Country Club Hills, IL 60478
CMAA Crane Manufacturers Association of America, Inc.
(Formerly called: Overhead Electrical Crane Institute) (OECI)
8720 Red Oak Boulevard, Suite 201
Charlotte, NC 28217
CRSI Concrete Reinforcing Steel Institute
933 N Plum Grove Road
Schaumburg, IL 60173
CSA Canadian Standards Association
178 Rexdale Boulevard
Rexdale, Ontario, M9W IR3, Canada
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 3
Abbreviation Meaning
DEMA Diesel Engine Manufacturer's Association
30200 Detroit Road
Cleveland, OH 44145
DHI Door and Hardware Institute
14170 Newbrook Drive
Chantilly, VA 22021
EEI Edison Electric Institute
90 Park Avenue
New York, NY 10016
EIA Electronic Industries Association
Order from:
Global Engineering Documents
18201 McDurmott West
Irvine, CA 92714
EJMA Expansion Joint Manufacturers Association
25 North Broadway
Tarrytown, NY 10591
FEDSPEC Federal Specifications
General Services Administration
Specification and Consumer Information
Distribution Branch
Washington Navy Yard, Bldg. 197
Washington, DC 20407
FEDSTDS
(see FEDSPECS)
Federal Standards
FM Factory Mutual Engineering and Research Corporation
1151 Boston-Providence Turnpike
P.O. Box 9102
Norwood, MA 02062
HEI Heat Exchange Institute
1300 Sumner Avenue
Cleveland, OH 44115
HI Hydraulic Institute
9 Sylvan Way, Suite 180
Parsippany, NJ 07054
IAPMO International Association of Plumbing and Mechanical Officials
20001 Walnut Drive S
Walnut, CA 91789
ICBO International Conference of Building Officials
5360 Workman Mill Road
Whittier, CA 90601
ICEA
Insulated Cable Engineers Association
P.O. Box 440
South Yarmouth, MA 02664
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 4
Abbreviation Meaning
IEEE Institute of Electrical and Electronics Engineers
445 Hoes Lane
P.O. Box 1331
Piscataway, NJ 08855
IES Illuminating Engineering Society of North America
120 Wall Street
New York, NY 10017
ISA Instrument Society of America
67 Alexander Drive
P.O. Box 12277
Research Triangle Park, NC 27709
JIC Joint Industrial Council
7901 West Park Drive
McLean, VA 22101
MFMA Metal Framing Manufacturers Association
401 N. Michigan Avenue
Chicago, IL 60611
MILSPEC Military Specifications
Naval Publications and Forms Center
5801 Tabor Avenue
Philadelphia, PA 19120
MSS Manufacturers Standardization Society of the Valve & Fittings Industry,
Inc.
127 Park Street, N.E.
Vienna, VA 22180
NAAMM National Association of Architectural Metal Manufacturers
11 South La Salle Street, Suite 1400
Chicago, IL 60603
NACE National Association of Corrosion Engineers
1440 South Creek Drive
Houston, TX 77084
NBC National Building Code
Published by BOCA
NEC National Electric Code
National Fire Protection Association
One Batterymarch Park
P.O. Box 9101
Quincy, MA 02269
NEMA National Electrical Manufacturer's Association
2101 L Street, NW, Suite 300
Washington, DC 20037
NESC National Electric Safety Code
American National Standards Institute
1430 Broadway
New York, NY 10018
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 5
Abbreviation Meaning
NFPA National Fire Protection Association
One Batterymarch Park
P.O. Box 9101
Quincy, MA 02269
NSF National Sanitation Foundation
3475 Plymouth Road
P.O. Box 130140
Ann Arbor, MI 48113
OSHA Occupational Safety and Health Act
U.S. Department of Labor
Occupational and Health Administration
San Francisco Regional Office
450 Golden Gate Avenue, Box 36017
San Francisco, CA 94102
PCI Precast/Prestressed Concrete Institute
175 West Jackson Blvd., Suite 1859
Chicago, IL 60604
PPIC The Plumbing & Piping Industry Council, Inc.
510 Shatto Place, Suite 402
Los Angeles, CA 90020
RMA Rubber Manufacturers Association
1400 K Street NW, Suite 900
Washington, DC 20005
SAE Society of Automotive Engineers, Inc.
400 Commonwealth Drive
Warrendale, PA 15096
SAMA Scientific Apparatus Makers Association
One Thomas Circle
Washington, DC 20005
SBC Standard Building Code
Published by SBCCI
SBCCI Southern Building Code Congress International Inc.
900 Montclair Road
Birmingham, AL 35213
SCDHEC South Carolina Department of Health and Environmental Control
2600 Bull Street
Columbia, SC 29201
SCDOT South Carolina Department of Transportation
P.O. Box 191
Columbia, SC 29201
SDI Steel Door Institute
30200 Detroit Road
Cleveland, OH 44145
SMACNA Sheet Metal and Air Conditioning Contractors National Association, Inc.
P.O. Box 221230
Chantilly, VA 22021
Lake Keowee to Adkins WTP Raw Water System Reference Standards
154828 01 42 19 - 6
Abbreviation Meaning
SPI Society of the Plastics Industry, Inc.
1275 K Street NW, Suite 400
Washington, DC 20005
SSPC Society for Protective Coatings
40 24th Street, 6th Floor
Pittsburgh, PA 15222
SSPWC Standard Specifications for Public Works Construction
Building News, Inc.
3055 Overland Avenue
Los Angeles, CA 90034
TPI Truss Plate Institute
583 D'Onofrio Drive, Suite 200
Madison, WI 53719
UBC Uniform Building Code
Published by ICBO
UL Underwriters Laboratories Inc.
333 Pfingsten Road
Northbrook, IL 60062
UMC Uniform Mechanical Code
Published by ICBO
UPC Uniform Plumbing Code
Published by IAPMO
USBR Bureau of Reclamation
U.S. Department of Interior
Engineering and Research Center
Denver Federal Center, Building 67
Denver, CO 80225
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 1
SECTION 01 45 20
EQUIPMENT AND SYSTEM PERFORMANCE AND OPERATIONAL TESTING
PART 1 GENERAL
1.01 DESCRIPTION
A. This section contains requirements for the Contractor's performance in documenting
testing work required under this contract. In addition, this section contains requirements
the for the Contractor's performance during installed performance testing of all
mechanical, electrical, instrumentation, and HVAC equipment and systems, including
structures for watertight construction, provided under this contract and all equipment
furnished by the Owner. This section supplements but does not supersede specific
testing requirements found elsewhere in this project manual.
1.02 QUALITY ASSURANCE
A. Contractor's Quality Assurance Manager:
1. The Contractor shall appoint a Quality Assurance Manager to manage, coordinate,
and supervise the Contractor's quality assurance program. The Quality Assurance
Manager shall have at least 5 years of total experience, or experience on at least five
separate projects, in managing the startup commissioning of mechanical, electrical,
instrumentation, HVAC, and piping systems. The quality assurance program shall
include:
a. A testing plan setting forth the sequence in which all testing work required under
this project manual will be implemented.
b. A documentation program to record the results of all equipment and system
tests.
c. An installed performance testing program for all mechanical, electrical,
instrumentation, and HVAC equipment and systems installed under this contract.
d. A calibration program for all instruments, meters, monitors, gages, and
thermometers installed under this contract.
e. A calibration program for all instruments, gages, meters, and thermometers used
for determining the performance of equipment and systems installed under this
contract.
f. A testing schedule conforming to the requirements specified in
paragraph 2.02 Testing Schedule.
2. For the purposes of this section, a system shall include all items of equipment,
devices and appurtenances connected in such a fashion as their operation or
function complements, protects or controls the operation or function of the others.
The Quality Assurance Manager shall coordinate the activities of all subcontractors
and suppliers to implement the requirements of this section.
B. Calibration:
1. All test equipment (gages, meters, thermometers, analysis instruments, and other
equipment) used for calibrating or verifying the performance of equipment installed
under this contract shall be calibrated to within plus or minus 2 percent of actual
value at full scale. Test equipment employed for individual test runs shall be selected
so that expected values as indicated by the detailed performance specifications will
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 2
fall between 60 and 85 percent of full scale. Pressure gages shall be calibrated in
accordance with ANSI/ASME B40.1. Thermometers shall be calibrated in accordance
with ASTM E77 and shall be furnished with a certified calibration curve.
2. Liquid flow meters, including all open channel flow meters and all meters installed in
pipelines with diameters greater than 2 inches shall be calibrated in situ using either
the total count or dye dilution methods. Flow meter calibration work shall be
performed by individuals skilled in the techniques to be employed. Calibration tests
for flow metering systems shall be performed over a range of not less than
10 percent to at least 75 percent of system full scale. At least five confirmed valid
data points shall be obtained within this range. Confirmed data points shall be
validated by not less than three test runs with results which agree within plus or
minus 2 percent.
C. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
ANSI/ASME B40.1 Gauges Pressure Indicating Dial Type—Elastic Element
ASTM E77 Method for Verification and Calibration of Liquid-in-Glass
Thermometers
ASHRAE 41.8 Standard Methods of Measurement of Flow of Gas
Dye Dilution Calibration Method Flow Measurements in Sanitary Sewers By Dye Dilution, Turner
Designs Mountain View, California,
Flow Measurement in Sewer Lines by the Dye Dilution Method,
Journal of the Water Pollution Control Federation, Vol. 55,
Number 5, May, 1983, pg. 531
Flow Measurement in Open Channels and Closed Conduits, Vol
1, U.S. Department of Commerce, National Bureau of Stan-
dards, pg. 361
Techniques of Water-Resources Investigations of the United
States Geological Survey, Chapter 16, Measurement of
Discharge Using Tracers
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 3
1.03 SUBMITTALS
A. Submittal material, to be submitted in accordance with Section 01 33 00, shall consist of
the following:
1. A complete description of the Contractor's plan for documenting the results from the
test program in conformance with the requirements of
paragraph 2.02 Documentation Plans, including:
a. Proposed plan for documenting the calibration of all test instruments.
b. Proposed plan for calibration of all instrument systems, including flow meters and
all temperature, pressure, weight, and analysis systems.
c. Sample forms for documenting the results of field pressure and performance
tests.
2. The credentials and certification of the testing laboratory proposed by the Contractor
for calibration of all test equipment.
3. Preoperational check-out procedures, reviewed and approved by the respective
equipment manufacturers.
4. Detailed testing plans, setting forth step-by-step descriptions of the procedures
proposed by the Contractor for the systematic testing of all equipment and systems
installed under this contract.
5. A schedule and subsequent updates, presenting the Contractor's plan for testing the
equipment and systems installed under this contract.
6. A schedule establishing the expected time period (calendar dates) when the
Contractor plans to commence operational testing of the completed systems, along
with a description of the temporary systems and installations planned to allow
operational testing to take place.
7. A summary of the Quality Assurance Manager's qualifications, showing conformance
to paragraph 1.02 Contractor’s Quality Assurance Manager requirements.
PART 2 PRODUCTS
2.01 GENERAL
A. The Contractor shall prepare test plans and documentation plans as specified in the
following paragraphs. The Construction Manager will not witness any test work for the
purpose of acceptance until all test documentation and calibration plans and the
specified system or equipment test plans have been submitted and accepted.
2.02 DOCUMENTATION
A. Documentation Plans:
1. The Contractor shall develop a records keeping system to document compliance with
the requirements of this Section. Calibration documentation shall include
identification (by make, manufacturer, model, and serial number) of all test
equipment, date of original calibration, subsequent calibrations, calibration method,
and test laboratory.
2. Equipment and system documentation shall include date of test, equipment number
or system name, nature of test, test objectives, test results, test instruments
employed for the test and signature spaces for the Construction manager's witness
and the Contractor's quality assurance manager. A separate file shall be established
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 4
for each system and item of equipment. These files shall include the following
information as a minimum:
a. Metallurgical tests
b. Factory performance tests
c. Accelerometer recordings made during shipment
d. Field calibration tests1
e. Field pressure tests1
f. Field performance tests1
g. Field operational tests1
3. Section 01 99 90 contains samples showing the format and level of detail required
for the documentation forms. The Contractor is advised that these are samples only
and are not specific to this project nor to any item of equipment or system to be
installed under this contract. The Contractor shall develop test documentation forms
specific to each item of equipment and system installed under this contract.
Acceptable documentation forms for all systems and items of equipment shall be
produced for review by the Construction Manager as a condition precedent to the
Contractor's receipt of progress payments in excess of 50 percent of the contract
amount. Once the Construction Manager has reviewed and taken no exception to the
forms proposed by the Contractor, the Contractor shall produce sufficient forms, at
his expense, to provide documentation of all testing work to be conducted as a part
of this contract.
B. Test Plans:
1. The Contractor shall develop test plans detailing the coordinated, sequential testing
of each item of equipment and system installed under this contract. Each test plan
shall be specific to the item of equipment or system to be tested. Test plans shall
identify by specific equipment or tag number each device or control station to be
manipulated or observed during the test procedure and the specific results to be
observed or obtained. Test plans shall also be specific as to support systems
required to complete the test work, temporary systems required during the test work,
subcontractors' and manufacturers' representatives to be present and expected test
duration. As a minimum, the test plans shall include the following features:
a. Step-by-step proving procedure for all control and electrical circuits by imposing
low voltage currents and using appropriate indicators to affirm that the circuit is
properly identified and connected to the proper device.
b. Calibration of all analysis instruments and control sensors.
c. Performance testing of each individual item of mechanical, electrical, and
instrumentation equipment. Performance tests shall be selected to duplicate the
operating conditions described in the project manual.
d. System tests designed to duplicate, as closely as possible, operating conditions
described in the project manual.
2. Test plans shall contain a complete description of the procedures to be employed to
achieve the desired test environment.
3. As a condition precedent to receiving progress payments in excess of 75 percent of
the contract amount, or in any event, progress payments due to the Contractor eight
1Each of these tests is required even though not specifically noted in detailed specification section.
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 5
weeks in advance of the date the Contractor wishes to begin any testing work
(whichever occurs earliest in the project schedule), the Contractor shall have
submitted all test plans required for the systematic field performance and
operational tests for all equipment and systems installed under this contract. Once
the Construction Manager has reviewed and taken no exception to the Contractor's
test plans, the Contractor shall reproduce the plans in sufficient number for the
Contractor's purposes and an additional ten copies for delivery to the Construction
Manager. No test work shall begin until the Contractor has delivered the specified
number of final test plans to the Construction Manager.
C. Testing Schedule:
1. The Contractor shall produce a testing schedule setting forth the sequence
contemplated for performing the test work. The schedule shall be in bar chart form,
plotted against calendar time, shall detail the equipment and systems to be tested,
and shall be coordinated with the Contractor's construction schedule specified in
Section 01 32 16. The schedule shall show the contemplated start date, duration of
the test and completion of each test. The test schedule shall be submitted no later
than 4 weeks in advance of the date testing is to begin. The Construction Manager
will not witness any testing work for the purpose of acceptance until the Contractor
has submitted a schedule to which the Construction Manager takes no exception.
The test schedule shall be updated weekly, showing actual dates of test work,
indicating systems and equipment testing completed satisfactorily and meeting the
requirements of this project manual.
2.03 SYSTEM AND EQUIPMENT PERFORMANCE TESTS
A. Each item of mechanical, electrical, instrumentation, and HVAC equipment installed
under this contract shall be tested to demonstrate compliance with the performance
requirements of this project manual. Each electrical, instrumentation, mechanical,
piping, and HVAC system installed or modified under this contract shall be tested in
accordance with the requirements of this project manual.
2.04 OPERATIONAL TESTS
A. Once all equipment and systems have been tested individually, the Contractor shall fill all
systems except wastewater, scum sludge and other wastewater derived systems with the
intended process fluids. Wastewater-derived process systems shall be filled with water.
After filling operations have been completed, the Contractor shall operate all systems for
a continuous period of not less than five days, simulating actual operating conditions to
the greatest extent possible. The Contractor shall install temporary connections,
bulkheads and make other provisions to recirculate process fluids or otherwise simulate
anticipated operating conditions. During the operational testing period, the Contractor's
Quality Assurance Manager and testing team shall monitor the characteristics of each
machine and system and report any unusual conditions to the Construction Manager.
2.05 PRODUCT DATA
A. Product data, to be provided in accordance with Section 01 33 00, shall be the original
and three copies of all records produced during the testing program.
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 6
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor's quality control manager shall organize teams made up of qualified
representatives of equipment suppliers, subcontractors, the Contractor's independent
testing laboratory, and others, as appropriate, to efficiently and expeditiously calibrate
and test the equipment and systems installed and constructed under this contract. The
objective of the testing program shall be to demonstrate, to the Construction Manager's
complete satisfaction, that the structures, systems, and equipment constructed and
installed under this contract meet all performance requirements and the facility is ready
for the commissioning process to commence. In addition, the testing program shall
produce baseline operating conditions for the Owner to use in a preventive maintenance
program.
3.02 CALIBRATION OF FIXED INSTRUMENTS
A. Calibration of analysis instruments, sensors, gages, and meters installed under this
contract shall proceed on a system-by-system basis. No equipment or system
performance acceptance tests shall be performed until instruments, gages, and meters
to be installed in that particular system have been calibrated and the calibration work
has been witnessed by the Construction Manager.
B. All analysis instruments, sensors, gages, and meters used for performance testing shall
be subject to recalibration to confirm accuracy after completion, but prior to acceptance
of each performance test. All analysis instruments, sensors, gages, and meters installed
under this contract shall be subject to recalibration as a condition precedent to
commissioning under the provisions of Section 01 91 00.
3.03 PERFORMANCE TESTS
A. General:
1. Performance tests shall consist of the following:
a. Pressure and/or leakage tests.
b. Electrical testing as specified in Division 26.
c. Wiring and piping, individual component, loop, loop commissioning and tuning
testing as described in Division 40.
d. Preoperational checkout for all mechanical and HVAC equipment. Preoperational
check-out procedures shall be reviewed and approved by the respective
equipment manufacturers.
e. Initial operation tests of all mechanical, electrical, HVAC, and instrumentation
equipment and systems to demonstrate compliance with the performance
requirements of this project manual.
2. In general, performance tests for any individual system shall be performed in the
order listed above. The order may be altered only on the specific written authorization
of the Construction Manager after receipt of a written request, complete with justifi-
cation of the need for the change in sequence.
B. Pressure And Leakage Tests:
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 7
1. Pressure and leakage tests shall be conducted in accordance with applicable
portions of Divisions 3 and 40. All acceptance tests shall be witnessed by the
Construction Manager. Evidence of successful completion of the pressure and
leakage tests shall be the Construction Manager's signature on the test forms
prepared by the Contractor.
C. Functional Checkout:
1. Prior to energization (in the case of electrical systems and equipment), all circuits
shall be rung out and tested for continuity and shielding in accordance with the
procedures required in Division 26.
D. Component Calibration And Loop Testing:
1. Prior to energization (in the case of instrumentation system and equipment), all loops
and associated instruments shall be calibrated and tested in accordance with the
procedures required in Division 40.
E. Electrical Resistance:
1. Electrical resistance testing shall be in accordance with Division 26.
F. Preoperational Tests:
1. Preoperational tests shall include the following:
a. Alignment of equipment using reverse dial indicator method.
b. Pre-operation lubrication.
c. Tests per the manufacturers' recommendations for prestart preparation and
preoperational check-out procedures.
G. Functional Tests:
1. General: Once all affected equipment has been subjected to the required
preoperational check-out procedures and the Construction Manager has witnessed
and has not found deficiencies in that portion of the work, individual items of
equipment and systems may be started and operated under simulated operating
conditions to determine as nearly as possible whether the equipment and systems
meet the requirements of these specifications. If available, plant effluent may be
employed for the testing of all liquid systems except gaseous, oil, or chemical
systems. If not available, potable water shall be employed as the test medium. Test
media for these systems shall either be the intended fluid or a compatible substitute.
The equipment shall be operated a sufficient period of time to determine machine
operating characteristics, including noise, temperatures and vibration; to observe
performance characteristics; and to permit initial adjustment of operating controls.
When testing requires the availability of auxiliary systems such as looped piping,
electrical power, compressed air, control air, or instrumentation which have not yet
been placed in service, the Contractor shall provide acceptable substitute sources,
capable of meeting the requirements of the machine, device, or system at no
additional cost to the Owner. Disposal methods for test media shall be subject to
review by the Construction Manager. During the functional test period, the Contractor
shall obtain baseline operating data on all equipment with motors greater than 1
horsepower to include amperage, bearing temperatures, and vibration. The baseline
data shall be collected for the Owner to enter in a preventive maintenance system.
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 8
a. Test results shall be within the tolerances set forth in the detailed specification
sections of this project manual. If no tolerances have been specified, test results
shall conform to tolerances established by recognized industry practice. Where,
in the case of an otherwise satisfactory functional test, any doubt, dispute, or
difference should arise between the Construction Manager and the Contractor
regarding the test results or the methods or equipment used in the performance
of such test, then the Construction Manager may order the test to be repeated. If
the repeat test, using such modified methods or equipment as the Construction
Manager may require, confirms the previous test, then all costs in connection
with the repeat test will be paid by the Owner. Otherwise, the costs shall be borne
by the Contractor. Where the results of any functional test fail to comply with the
contract requirements for such test, then such repeat tests as may be necessary
to achieve the contract requirements shall be made by the Contractor at his
expense.
b. The Contractor shall provide, at no expense to the Owner, all power, fuel,
compressed air supplies, water, and chemicals, all labor, temporary piping,
heating, ventilating, and air conditioning for any areas where permanent facilities
are not complete and operable at the time of functional tests, and all other items
and work required to complete the functional tests. Temporary facilities shall be
maintained until permanent systems are in service.
2. Retesting: If under test, any portion of the work should fail to fulfill the contract
requirements and is adjusted, altered, renewed, or replaced, tests on that portion
when so adjusted, altered, removed, or replaced, together with all other portions of
the work as are affected thereby, shall, unless otherwise directed by the Construction
Manager, be repeated within reasonable time and in accordance with the specified
conditions. The Contractor shall pay to the Owner all reasonable expenses incurred
by the Owner, including the costs of the Construction Manager, as a result of
repeating such tests.
3. Post-test Inspection: Once functional testing has been completed, all machines shall
be rechecked for proper alignment and realigned, as required. All equipment shall be
checked for loose connections, unusual movement, or other indications of improper
operating characteristics. Any deficiencies shall be corrected to the satisfaction of
the Construction Manager. All machines or devices which exhibit unusual or
unacceptable operating characteristics shall be disassembled and inspected. Any
defects found during the course of the inspection shall be repaired or the specific
part or entire equipment item shall be replaced to the complete satisfaction of the
Construction Manager at no cost to the Owner.
3.04 OPERATIONAL TESTS
A. The Contractor shall provide system operation testing. After completion of all
performance testing and certification by the Construction Manager that all equipment
complies with the requirements of the specifications, the Contractor shall fill all process
units and process systems, except those employing domestic water, oil, air, or chemicals,
with intended process fluids. All domestic water, oil, air, and chemical systems shall be
filled with the specified fluid.
B. Upon completion of the filling operations, the Contractor shall circulate intended process
fluids through the completed facility for a period of not less than 48 hours, during which
all parts of the system shall be operated as a complete facility at various loading
conditions, as directed by the Construction Manager. The operational testing period shall
Lake Keowee to Adkins WTP Raw Water System Equipment And System Performance and Operational Testing
154828 01 45 20 - 9
commence after this initial period of variable operation. Should the operational testing
period be halted for any reason related to the facilities constructed or the equipment
furnished under this contract, or the Contractor's temporary testing systems, the
operational testing program shall be repeated until the specified continuous period has
been accomplished without interruption. All process units shall be brought to full
operating conditions, including temperature, pressure, and flow.
C. As-built documents specified in Section 01 78 39 of facilities involved shall be accepted
and ready for turnover to the Owner at the time of operational testing.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 1
SECTION 01 45 29
TESTING LABORATORY SERVICES
PART 1 GENERAL
1.01 DESCRIPTION:
A. This Section specifies Quality Control testing and reporting performed by the Testing
Laboratory. Construction Manager shall select a qualified Testing Laboratory and
contract for the services specified herein, except as specifically noted where Contractor
may elect to utilize Testing Laboratory to fulfill submittal requirements. Such an
arrangement does not relieve the Contractor from their responsibility to provide the
completed project as specified, and to perform Quality Assurance according to the QCS
as reviewed and accepted.
1.02 REFERENCES:
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ASTM A880 Criteria for Use in Evaluation of Testing Laboratories and Organizations for
Examination and Inspection of Steel, Stainless Steel, and Related Alloys
ASTM C802 Conducting an Inter-laboratory Test Program to Determine the Precision of Test
Methods for Construction Materials
ASTM C1021 Laboratories Engaged in the Testing of Building Sealants
ASTM Cl077 Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and
Criteria for Laboratory Evaluation
ASTM D3666 Specification for Minimum Requirements for Agencies Testing and Inspecting Road
and Paving Materials
ASTM D3740 Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of
Soil and Rock as Used in Engineering Design and Construction
ASTM D4561 Quality Control Systems for Organizations Producing and Applying Bituminous Paving
Materials
ASTM E4
Force Verification of Testing Machines
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 2
Reference Title
ASTM E329
Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
ASTM E543
Agencies Performing Nondestructive Testing
ASTM E994 Calibration and Testing Laboratory Accreditation Systems General Requirements for
Operation and Recognition.
1.03 TESTING LABORATORY QUALIFICATIONS:
A. Testing Laboratory shall satisfy the following qualifications:
1. Recommended Requirements for Independent Laboratory Qualification, published by
American Council of Independent Laboratories.
2. Conform to the requirements of ASTM E329 in particular, and other reference
standards as generally pertain to this project.
3. Authorized to operate in the State of South Carolina, with personnel and equipment
based sufficiently close to the project to allow short-notice site access for sampling
and testing.
4. Acceptable to Greenville Water, Construction Manager, and local building authorities.
1.04 TESTING LABORATORY RESPONSIBILITIES:
A. Testing Laboratory shall provide qualified personnel at the site and cooperate with
Construction Manager and Contractor in performance of the following services:
1. Perform specified independent inspection, sampling, and testing of products in
accordance with specified standards, to determine compliance with requirements of
Contract Documents.
2. Provide sampling equipment and personnel, deliver samples to the testing
laboratory, record field measurements, and cure samples as required by Contract
Documents.
3. Perform Building Department required tests and inspections, including Special
Inspection as specified in Section 01 40 00.
4. Timely prepare and deliver reports summarizing results of tests and inspections.
5. Attend pre-construction conferences and, if requested, a limited number of progress
meetings where Quality Control, testing, and inspection issues require discussion.
6. When directed by the Construction Manager or requested by the Contractor, provide
special and additional tests and inspections to verify material compliance with
requirements of Contract Documents.
a. Construction Manager shall pay for special tests and inspections where work
conforms to the Contract Document requirements.
b. Contractor shall pay for additional tests and inspections where work fails to
comply with Contract Document requirements (re-inspection) and for costs
associated with cancelled or short-notice re-scheduling of requested sampling,
testing, and inspection. Testing Laboratory work requested by Contractor to fulfill
submittal requirements shall also be considered additional tests.
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 3
1.05 CONTRACTOR RESPONSIBILITIES:
A. Contractor shall deliver adequate samples of materials proposed to be used and which
require testing to the Testing Laboratory. Contractor shall cooperate with Testing
Laboratory personnel, and provide access to the work and to manufacturer’s facilities.
Contractor shall provide incidental labor and facilities to provide access to work to be
tested, to obtain and handle samples at the site or at source of products to be tested, to
facilitate tests and inspections, storage and curing of test samples.
B. Contractor shall notify Testing Laboratory and Construction Manager 24 hours prior to
expected time for operations requiring inspection, sampling and testing services.
1.06 TEST AND INSPECTION REPORTS:
A. Report Contents:
1. At a minimum, Test and Inspection Reports shall include the following:
a. Project name and date of report.
b. Testing Laboratory name, address, telephone number, name of laboratory field
sampling personnel, lab testing personnel, or QCS Inspector as applicable.
c. Date, time, and location of sampling, testing, and inspecting.
d. Ambient temperature and weather conditions at the site or shop and curing
conditions of samples.
e. Product identification and referenced specification Section number.
f. Type of sample, test, and inspection and industry standard for sampling and
testing.
g. Results of sample, test, and inspection.
h. Evaluation of compliance with requirements in Contract Documents.
i. Certified Inspection Reports shall specifically indicate the qualification of the
inspector to render judgment and certify said inspection.
j. When requested by Construction Manager, interpretation of test results.
B. Distribution of Test and Inspection Reports:
1. Test and Inspection reports shall be submitted to the Construction Manager for
distribution as Product Data described in Section 01 33 00. Test reports shall be
submitted not more than two days after completion of required tests. Inspection
reports shall be submitted immediately if deficiencies or significant irregularities are
noted, and in no case less than two working days after said inspection. Provide
electronic copies of all reports.
1.07 SUBMITTALS:
A. The following information shall be provided in accordance with Section 01 33 00:
1. A copy of this specification section, with addendum updates included, and all
referenced and applicable sections, with addendum updates included, with each
paragraph check-marked to indicate specification compliance or marked to indicate
requested deviations from specification requirements. Check marks (✓) shall denote
full compliance with a paragraph as a whole. If deviations from the specifications are
indicated, and therefore requested by the Contractor, each deviation shall be
underlined and denoted by a number in the margin to the right of the identified
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 4
paragraph, referenced to a detailed written explanation of the reasons for requesting
the deviation. The Engineer shall be the final authority for determining acceptability
of requested deviations. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Failure to
include a copy of the marked-up specification sections, along with justification(s) for
any requested deviations to the specification requirements, with the submittal shall
be sufficient cause for rejection of the entire submittal with no further consideration.
2. Documentation of conformance with Testing Laboratory Qualifications as specified in
paragraph 1.03 herein.
3. Form 01 45 29 described in paragraph 3.03 by both Testing Laboratory and
Contractor.
1.08 LIMITS ON TESTING LABORATORY AUTHORITY:
A. Testing Laboratory may not release, revoke, alter, or enlarge on requirements of Contract
Documents. Testing Laboratory may not approve or accept any portion of the work, nor
assume any duties of Contractor. Testing Laboratory has no authority to stop the work
PART 2 PRODUCTS
2.01 SOURCE QUALITY CONTROL
A. General:
1. Source quality control is defined in Section 01 40 00. This Section provides general
guidelines as to the sampling, tests, and inspections required of products and
manufactures prior to delivery to the project site, and should be considered a
minimum. Additional information and requirements are provided in each technical
specification Section and those requirements shall control over this Section when in
conflict. Absence of a test, inspection or requirement listed herein from a subsequent
specification Section does not relieve the Testing Laboratory or the Contractor from
their respective responsibilities specified in this Section.
B. Reference Standards In Other Sections:
1. Codes, standards, and other references called out below, but which are not listed in
paragraph 1.02 are described in other specification Sections and not repeated
herein.
C. Fill Materials:
1. Imported Fill Materials: Testing Laboratory may conduct additional testing on behalf
of Contractor to prepare required submittals specified in Section 31 23 00.
2. Type C Fill Material: Testing Laboratory shall conduct required testing to verify on-site
materials proposed for fill conforms to specification Section 31 23 00. Contractor
shall pay Testing Laboratory for such sampling and testing. Sampling and testing
shall determine Liquid Limit, Plasticity Index, optimum moisture content and density
relationship, and other data as required for proper use of this material.
D. Paving Materials:
1. Provide sampling and testing requested by Construction Manager or additional
testing as requested by Contractor to verify materials proposed for use conform to
specification Section 31 23 00.
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 5
E. Concrete Reinforcing:
1. Provide sampling and testing requested by Construction Manager or additional
testing as requested by Contractor to verify materials proposed for use conform to
specification Section 03 30 00 and 03 41 00.
F. Cast-In-Place Concrete:
1. Provide sampling and testing requested by Construction Manager or additional
testing as requested by Contractor to verify materials proposed for use conform to
specification Section 03 30 00. At Contractor’s expense, Testing Laboratory may
assist Contractor in formulating concrete mix designs, testing and reporting same,
and providing the services of a Professional Engineer to review and seal the mix
design.
G. Precast Concrete:
1. Precast Yard Inspection: Source quality inspection is not required for PCI Certified
facilities unless otherwise directed by the Building Official.
2. Non PCI Certified Facilities: Provide Special Inspection conforming to CBC Chapter 17
and PCI recommendations for all facets of operation including reinforcing,
prestressing, concrete placing, finishing, and curing, form release and handling.
3. Vaults, Manholes, And Non-Structural Precast Concrete Items: Precast yard
inspection is not required unless so directed by the Construction Manager due to
quality concerns or lack of experience by the manufacturer. Such inspection and
testing shall be paid for by the Contractor, and conform to this Section’s
requirements and Section 03 41 00.
PART 3 EXECUTION
3.01 FIELD QUALITY CONTROL
A. General:
1. Field quality control is defined in Section 01 40 00. This Section provides general
guidelines as to the sampling, tests, and inspections required of work in progress or
completed in the field, and should be considered a minimum. Additional information
and requirements are provided in each technical specification Section and those
requirements shall control over this Section when in conflict. Absence of a test,
inspection or requirement listed herein from a subsequent specification Section does
not relieve the Testing Laboratory or the Contractor from their respective
responsibilities specified in this Section.
B. Reference Standards In Other Sections:
1. Codes, standards, and other references called out below, but which are not listed in
paragraph 1.02 are described in other specification sections and not repeated
herein.
C. Fill:
1. Subgrade Preparation And Compaction: Verify depth of scarification, moisture
content within optimal limits for compaction, and degree of compaction specified in
Section 31 23 00. Frequency of testing shall generally conform to 25 foot maximum
spacing for strip footings, each isolated pad footing, every 900 square feet for slabs
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 6
and mat foundations, or as directed by the Construction Manager in light of actual
geometry and conditions extent.
2. Structure Fill: Verify material provided, lift thickness, and compaction density.
Frequency of sampling and testing shall be the same as for Subgrade Preparation
and Compaction.
3. Structure Backfill: Verify material provided, lift thickness, and compaction density.
Frequency of sampling and testing shall be as directed by the Construction Manager
but not less than every 2 feet vertical (lifts) and every 1600 square feet of filled area.
4. Other Fill Materials: Verify material used, lift thickness, and compaction density.
Frequency of sampling and testing shall be as directed by the Construction Manager.
D. Paving:
1. Earthwork and Base Aggregate: Provide sampling and testing same as Fill described
above, and specified in Section 31 23 00. Frequency shall conform to Asphalt
Concrete Pavement, below.
2. Asphalt Concrete Pavement: Sample and test pavement thickness and installation
per CALTRANS Standard Specifications. Thickness verification shall be made at a
frequency not to exceed 1600 square feet of roadway or parking zones or as directed
by the Construction Manager.
3. Sitework Concrete at Pavement: Sitework concrete at pavement consists of curbs,
gutters, monolithic curb/sidewalk, inlet structures, catch basins, and other concrete
construction in contact with paving or necessary for a complete paving job but not
associated with buildings, process structures, or structural work controlled by the
CBC. Testing Laboratory shall conduct sampling and testing the same as specified for
cast-in-place concrete in Section 03 30 00, except strength cylinder testing shall
occur at one-half the frequency (placing rate) as for structural concrete.
E. Concrete Reinforcing:
1. Provide Special Inspection for all structural reinforcing in concrete and masonry per
CBC Section 1701.5 Item 4.
2. Provide Special Inspection for mechanical reinforcing connectors and splicing
systems as required by that product’s ICBO Evaluation Report, or equivalent.
F. Cast-In-Place Concrete:
1. Sample the first daily truck load of ready mixed concrete and every 50 cubic yards
thereafter, complying with ASTM C172.
2. Perform one slump test for the first daily truck load of ready mixed concrete and
every 50 cubic yards thereafter or as requested by Construction Manager if
consistency is in question, complying with ASTM C143.
3. Perform one air content test for each set of compressive strength specimens,
complying with ASTM C31.
4. Fabricate compressive strength specimens, complying with ASTM C39.
5. Make one set of 6 of compressive strength specimens for each day of structural
concrete placing or each 100 cubic yards or fraction thereof for each class of
concrete.
6. Test two specimens after curing 7 days, two specimens after curing 28 days, and
retain two specimens for later testing if required.
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 7
7. Comply with ACI 350 Section 5.6 (ACI 318 for non-water retaining structures) for
evaluation and acceptance of concrete.
G. Precast Concrete:
1. Site Inspection Of Precast Concrete Structural Assemblies: Visually inspect precast
plank, beam, hollowcore, or other precast systems after units are set in place,
mechanically anchored, reinforcing and details completed but prior to placing
concrete or grout which would prevent such inspection. Verify precast pieces conform
to expected geometry, bearing conditions and camber.
2. Completion Of Precast Concrete Structural Assemblies: Inspect reinforcing,
placement of concrete or grout fill as specified for those materials.
H. Anchor Bolts And Anchors:
1. Special Inspections: Provide Special Inspection for wedge anchors, undercut anchors,
adhesive anchors, epoxy anchors, and all other anchoring systems installed in
hardened concrete and masonry as required by that product’s ICBO Evaluation
Report, or equivalent.
2. Site Inspection Of Structural Anchor Bolts: Visually inspect all structural anchor bolts
for grade, diameter, embedment, geometry or type (“J” bolt or hex-head), quantity
and general location. Contractor shall assume all responsibility for detailed
dimensions locating each individual bolt, each bolt group in total, and locations of
bolts within each group (template).
I. Grout:
1. Site Inspection Of Masonry Grouting: See Masonry section of this specification.
2. Cementitious Grout For Structural Bearing: Visually inspect all column baseplates,
and grouted zone between structural struts/beams and their supporting wall
elements. Determine complete fill beneath baseplate by tapping with hammer and
noting hollow reports. Verify grout conforms to specification by observing empty bags,
which Contractor shall leave visible adjacent to area used until inspection complete.
3. Epoxy Grout For Equipment Bases: Provide inspection conforming to specification
Section 43 05 13 and its reference standards, details on the Drawings, and the
requirements of the epoxy grout manufacturer.
3.02 EVALUATION AND CORRECTION :
A. Evaluation:
1. Satisfactory completion of work will be judged on results of laboratory, shop, and site
tests and inspections.
B. Corrections:
1. If results of tests and inspections indicate work is below requirements of Contract
Documents, that portion of work is defective and shall be repaired or replaced by the
Contractor at no additional expense to the Owner by methods specified in each
material or system’s Section. Corrective action shall continue until such work meets
the requirements of the Contract Documents.
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 8
3.03 SCHEDULE OF INSPECTIONS AND TESTS:
A. Form 01 45 29 below shall be used to coordinate sampling and testing provided by
Testing Laboratory, Construction Manager, Contractor, and other parties, if any. Testing
Laboratory shall fill out Form 01 45 29 with anticipated inspections, sampling, and
testing, submit for review by Construction Manager and for information to Contractor,
and revise as directed. After receipt of Testing Laboratory’s Form 01 45 29 submittal,
Contractor shall submit Form 01 45 29 to identify sampling and testing requested for
submittal preparation, and with an allowance for additional inspections. Such allowance
shall not be less than five percent (5%) of the anticipated Field Quality Control budget for
the Testing Laboratory, but shall not contractually commit Contractor to such
expenditure, unless additional inspections requested and then only to their extent.
Lake Keowee to Adkins WTP Raw Water System Testing Laboratory Services
154828 01 45 29 - 1
FORM 01 45 29
ANTICIPATED SAMPLING, TESTING, AND INSPECTIONS BY TESTING
LABORATORY AND CONTRACTOR
Prepared by : ________ Testing Laboratory ________ Contractor (check one).
Electronic version available upon request. Expand each cell as necessary to provide a complete scope description.
Specification Section Source Quality Control Field Quality Control
31 23 00 – Excavation and
Fill
32 12 16 – Asphalt Paving
03 20 00 – Concrete
Reinforcing
03 30 00 – Cast-in-Place
Concrete
03 40 00 – Precast Concrete
03 60 00 – Grouting
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Temporary Utilities
154828 01 51 00 - 1
SECTION 01 51 00
TEMPORARY UTILITIES
PART 1 GENERAL
1.01 OFFICE
A. The Contractor is not required to maintain an office at the site of the work.
1.02 POWER
A. The Contractor shall provide power for construction at the project sites. He shall make
arrangements with the electrical utility and with the Owner for power takeoff points,
voltage and phasing requirements, transformers and metering and shall pay the costs
and fees arising therefrom. The Contractor shall provide the special connections required
for his work.
1.03 TELEPHONE
A. The Contractor shall provide telephone service at his construction site office. Mobile
telephone service is acceptable as a substitute for telephone service if the mobile
telephone will be on site at all times during completion of work.
1.04 SANITARY FACILITIES
A. The Contractor shall provide toilet and washup facilities for his work force at the site of
work. The facilities shall comply with applicable laws, ordinances, and regulations
pertaining to the public health and sanitation of dwellings and camps.
1.05 WATER
A. The Contractor shall coordinate for and pay for water as needed for flushing and testing
of the proposed pipelines and pump station.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Product Storage and Handling Requirements
154828 01 66 00 - 1
SECTION 01 66 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 GENERAL
1.01 DAMAGE
A. Equipment, products and materials shall be shipped, handled, stored, and installed in
ways which will prevent damage to the items. Damaged items will not be permitted as
part of the work except in cases of minor damage that have been satisfactorily repaired
and are acceptable to the Construction Manager.
1.02 PIPE
A. Pipe and appurtenances shall be handled, stored, and installed as recommended by the
manufacturer. Pipes with paint, tape coatings, linings or the like shall be stored to protect
the coating or lining from physical damage or other deterioration. Pipes shipped with
interior bracing shall have the bracing removed only when recommended by the pipe
manufacturer.
PART 2 EQUIPMENT
2.01 PACKAGE AND MARKING:
A. All equipment shall be protected against damage from moisture, dust, handling, or other
cause during transport from manufacturer's premises to site. Each item or package shall
be marked with the number unique to the specification reference covering the item.
B. Stiffeners shall be used where necessary to maintain shapes and to give rigidity. Parts of
equipment shall be delivered in assembled or subassembled units where possible.
2.02 IDENTIFICATION:
A. Each item of equipment and valve shall have permanently affixed to it a label or tag with
its equipment or valve number designated in this contract. Marker shall be of stainless
steel. Location of label will be easily visible.
2.03 SHIPPING:
A. Bearing housings, vents and other types of openings shall be wrapped or otherwise
sealed to prevent contamination by grit and dirt.
B. Damage shall be corrected to conform to the requirements of the contract before the
assembly is incorporated into the work. The Contractor shall bear the costs arising out of
dismantling, inspection, repair and reassembly.
2.04 FACTORY APPLIED COATINGS:
A. Unless otherwise specified, each item of equipment shall be shipped to the site of the
work with the manufacturer's shop applied epoxy prime coating as specified in Section
09 90 00 . The prime coating shall be applied over clean dry surfaces in accordance with
the coating manufacturer's recommendations. The prime coating will serve as a base for
Lake Keowee to Adkins WTP Raw Water System Product Storage and Handling Requirements
154828 01 66 00 - 2
field-applied finish coats. Electrical equipment and materials shall be painted by
manufacturer as specified in Section 09 90 00-3.03 Electrical and Instrumentation
Equipment and Materials.
2.05 STORAGE:
A. During the interval between the delivery of equipment to the site and installation, all
equipment, unless otherwise specified, shall be stored in an enclosed space affording
protection from weather, dust and mechanical damage and providing favorable
temperature, humidity and ventilation conditions to ensure against equipment
deterioration. Manufacturer's recommendations shall be adhered to in addition to these
requirements.
B. Equipment and materials to be located outdoors may be stored outdoors if protected
against moisture condensation. Equipment shall be stored at least 6 inches above
ground. Temporary power shall be provided to energize space heaters or other heat
sources for control of moisture condensation. Space heaters or other heat sources shall
be energized without disturbing the sealed enclosure.
2.06 PROTECTION OF EQUIPMENT AFTER INSTALLATION:
A. After installation, all equipment shall be protected from damage from, including but not
limited to, dust, abrasive particles, debris and dirt generated by the placement, chipping,
sandblasting, cutting, finishing and grinding of new or existing concrete, terrazzo and
metal; and from the fumes, particulate matter, and splatter from welding, brazing and
painting of new or existing piping and equipment. As a minimum, vacuum cleaning,
blowers with filters, protective shieldings, and other dust suppression methods will be
required at all times to adequately protect all equipment. During concreting, including
finishing, all equipment that may be affected by cement dust must be completely
covered. During painting operations, all grease fittings and similar openings shall be
covered to prevent the entry of paint. Electrical switchgear, unit substation, and motor
load centers shall not be installed until after all concrete work and sandblasting in those
areas have been completed and accepted and the ventilation systems installed.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 1
SECTION 01 73 23
BRACING AND ANCHORING
PART 1 GENERAL
1.01 SUMMARY
A. Scope
1. This section specifies the minimum structural requirements for the design,
anchorage and bracing of architectural/mechanical/electrical components,
equipment, and systems, and nonbuilding structures. Design of supports,
attachments and bracing for all parts or elements of the architectural, mechanical,
and electrical systems shall be provided in accordance with this section. The
requirements of this section shall apply to the design of the structural elements and
features of equipment and to platforms/walkways that are provided with equipment
or nonbuilding structures.
2. This section applies to nonstructural components that are permanently attached to
structures, and nonbuilding structures as defined below in paragraph 1.01
Definitions and ASCE 7-10. Note that equipment is defined as a nonstructural
component and tanks are defined as a non-building structure.
3. Design shall be in accordance with the criteria listed within this section and shall
conform to the provisions of the design codes listed within this section. Engineering
design is not required for attachments, anchorage, or bracing detailed on the
drawings or where the size of attachments, anchorage, or bracing is defined in the
technical specification sections.
4. The following nonstructural components are exempt from the seismic design loading
requirements of this section.
a. Components in Seismic Design Category A.
b. Architectural components in Seismic Design Category B other than parapets
supported by bearing walls or shear walls provided that the component
importance factor, Ip, is equal to 1.0.
c. Mechanical and electrical components in Seismic Design Category B.
d. Mechanical and electrical components in Seismic Design Category C provided
that the component importance factor, Ip, is equal to 1.0.
e. Mechanical and electrical components in Seismic Design Categories D, E or F
where the component importance factor, Ip, is equal to 1.0 and both of the
following conditions apply:
1) Flexible connections between the components and associated, piping and
conduit are provided, and
2) Components are mounted at 4 feet or less above a floor level and weigh 400
lb or less (4-foot criteria applies to the mounting support elevation relative to
the floor).
f. Mechanical and electrical components in Seismic Design Categories D, E or F
where the component importance factor, Ip, is equal to 1.0 and both of the
following conditions apply:
1) Flexible connections between the components and associated, piping and
conduit are provided, and
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 2
2) The components weigh 20 lb or less or, for distribution systems, weighing 5
lb/ft or less.
B. Definitions:
1. Structures: The structural elements of a building that resist gravity, seismic, wind,
and other types of loads. Structural components include columns, posts, beams,
girders, joists, bracing, floor or roof sheathing, slabs or decking, load-bearing walls,
and foundations.
2. Nonstructural Components: The nonstructural portions of a building include every
part of the building and all its contents, except the structural portions, that carry
gravity loads and that may also be required to resist the effects of wind, snow,
impact, temperature and seismic loads. Nonstructural components include, but are
not limited to, ceilings, partitions, windows, equipment, piping, furnishings, lights, etc.
3. Non-building Structures: All self-supporting structures that carry gravity loads and
that may also be required to resist the effects of wind, snow, impact, temperature
and seismic loads. Non-building structures include, but are not limited to, pipe racks,
storage racks, stacks, tanks, vessels and structural towers that support tanks and
vessels.
1.02 QUALITY ASSURANCE
A. Quality Control by Design-Builder or Design-Builder’s Representative:
1. Special Inspection of nonstructural components and non-building structures, and
their anchorages shall be performed by the Special Inspector under contract with the
Design-Builder or Design-Builder’s Representative and in conformance with IBC
Chapter 17. Special Inspector(s) and laboratory shall be acceptable to the Design-
Builder or Design-Builder’s Representative in their sole discretion. Special Inspection
is in addition to, but not replacing, other inspections and quality control requirements
herein. Where sampling and testing required herein conforms to Special Inspection
standards, such sampling and testing need not be duplicated.
B. References:
1. Where a referenced document contains references to other standards, those
documents are included as references under this section as if referenced directly.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization, or if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued, or replaced. When conflicting requirements occur, the most
stringent requirements will govern the design.
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 3
Reference Title
AAMA American Architectural Manufacturer’s Association
ACI 318 Building Code Requirements for Structural Concrete
ACI 350 Code Requirements for Environmental Engineering Concrete Structures
AISC 341 Seismic Provisions for Structural Steel Buildings
ACI 360 Specification for Structural Steel Buildings
ASCE 7 Minimum Design Loads for Buildings and Other Structures
ASTM C635 Standard Specification for the Manufacture, Performance and Testing of Metal
Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings
ASTM C636 Standard Practice for Installation for Metal Ceiling Suspension Systems for Acoustical
Tile and Lay-in Panel Ceilings
AWS D1.1 Structural Welding Code – Steel
AWS D1.2 Structural Welding Code - Aluminum
AWS D1.2 Structural Welding Code – Stainless Steel
IBC International Building Code with local amendments
NFPA-13 Standard for the Installation of Sprinkler Systems
OSHA U.S. Dept. of Labor, Occupational Safety and Health Administration
SMACNA Seismic Restraint Manual Guidelines for Mechanical Systems
1.03 SUBMITTALS
A. For structural elements of nonstructural components and non-building structures
required to be designed per this specification section, drawings and design calculations
shall be stamped by a South Carolina licensed professional engineer qualified to perform
structural engineering.
B. Submit drawings and calculations no less than four weeks in advance of the installation
of any component to be anchored to the structure or installation of any structural
member to which the component will be attached.
1. The following submittals shall be provided in accordance with Section 01 33 00:
a. List of all nonstructural components and non-building structures requiring wind
and seismic design and anchorage.
b. Shop drawings showing details of complete wind and seismic bracing and
anchorage attachment assemblies including connection hardware, and
embedment into concrete.
c. Shop drawings showing plans, elevations, sections and details of equipment
support structures and non-building structures, including anchor bolts, structural
members, platforms, stairs, ladders, and related attachments.
d. Identify all interface points with supporting structures or foundations, as well as
the size, location, and grip of all required attachments and anchor bolts. Clearly
indicate who will be providing each type of attachment/anchor bolt. Equipment
vendor shall design anchor bolts, including embedment into concrete, and submit
stamped calculations.
e. Calculations for all supports, bracing, and attachments shall clearly indicate the
design criteria applied in the design calculations. Concrete embedment
calculations shall be coordinated with thickness and strength of concrete
members. Submit a tabulation of the magnitude of unfactored (service level)
equipment loads at each support point, broken down by type of loading (dead,
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 4
live, wind, seismic, etc.). Indicate impact factors applied to these loads in the
design calculations.
f. Product Data: Manufacturer’s certificates of compliance with the seismic force
requirements of this section.
1.04 DESIGN CODES
A. The following standard codes have application at this site for:
Buildings/Structures: International Building Code 2012 and ASCE 7-10
Reinforced concrete: ACI 350-06 for Concrete Liquid Containing Tanks, ACI 318-11 for all other
reinforced concrete
Structural steel: AISC 360-10 and AISC 341-10
Welding: AWS Welding Codes, Latest Edition
Occupational health and safety
requirements:
U.S. Dept. of Labor, Occupational Safety and Health Administration
(OSHA)
Note: When conflicting requirements occur, the most stringent requirements will govern the design.
1.05 DESIGN LOADS
A. All nonstructural components and non-building structures shall be designed for the
following loads. Wind and snow loads shall not be applied to nonstructural components
and non-building structures that are located inside buildings.
1. Dead Loads:
a. An additional allowance will also be added for piping and conduit when supported
and hung from the underside of equipment and platforms.
b. Typical allowance for partition, piping and conduit unless noted otherwise: 20 psf
2. Uniform Live Loads:
Equipment Area: 150 psf or equipment plus 50 psf
Columns: No column live load reduction allowed
Stairs and landings: 100 psf
Maintenance Area Floor Loading 150 psf
Office and Control Floor Loading: 50 psf
Grating, Checkered Plates and Hatches Same loadings as adjacent floor areas
Truck Traffic Areas 250 psf or H-20 loading
Tank Roof 100 psf
3. Snow Loads:
Code: IBC 2012 & ASCE 7-10
Ground Snow Load (pg) 0 psf
Exposure: NA
Importance Factor (I): NA
Minimum Roof Snow Load: NA
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 5
4. Wind Loads:
Code: IBC 2012 & ASCE 7-10
Basic Wind Speed (3-second gust): 148 mph
Exposure: C
Topographic Factor (Kzt) 1.0
Note:
1. All exterior nonstructural components and nonbuilding structures, unless located in a pit or basin, shall be designed to
withstand the design wind loads without consideration of shielding effects by other structures.
5. Seismic Loads:
Code: IBC 2012 & ASCE 7-10
0.2 Sec. Mapped Spectral Response, SS: 0.312 g
1.0 Sec. Mapped Spectral Response, S1: 0.120 g
Site Class: D
0.2 Sec. Design Spectral Response, SDS: 0.323 g
1.0 Sec. Design Spectral Response, SD1: 0.186 g
Importance Factor (I): 1.25 (Wastewater Treatment facilities are
Occupancy Category III)
Component Importance Factor (Ip): 1.0, except Ip=1.5 for fire protection sprinkler
systems or components containing hazardous
materials
Seismic Design Category C
Notes:
1. Seismic loads shall be calculated on the basis of the governing building code. The structure dead load shall include
equipment operating loads.
2. Individual members shall be checked for seismic and full member live load acting simultaneously, except that flooded
equipment loads (infrequent occurrence) need not be combined with seismic loads. Equipment operating loads shall
be combined with seismic loads.
6. Impact Loads:
a. Impact loads shall be considered in the design of support systems.
b. The following impact load factors shall be used unless recommendations of the
equipment manufacturer will cause a more severe load case.
Rotating machinery: 20% of moving load
Reciprocating machinery: 50% of moving load
Monorail Hoists:
• Vertical 25% of lifted load
• Longitudinal 10% of lifted load
Hangers supporting floors and platforms: 33% of live and dead load
7. Temperature:
a. The effects of temperature shall be included in design where nonstructural
components and non-building structures are exposed to differential climatic
conditions. See paragraph 1.07 for temperature extremes.
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 6
1.06 LOAD COMBINATIONS
A. All nonstructural components and non-building structures shall be designed to withstand
the load combinations as specified in the governing building code. Where the exclusion
of live load or impact load would cause a more severe load condition for the member
under investigation, then the load shall be ignored when evaluating that member.
1.07 DESIGN CONSIDERATIONS
A. All nonstructural components and non-building structures shall be designed for the
following conditions:
1. Climatic Conditions:
Maximum design temperature: 110 degrees Fahrenheit
Minimum design temperature: 15 degrees Fahrenheit
2. Operating Conditions (Tanks):
Operating temperature: 140 degrees Fahrenheit
Maximum temperature differential: 125 degrees Fahrenheit
1.08 COLUMN BASE FIXITY
A. Column bases shall be designed as pinned connections. No moments shall be assumed
to be transferred to the foundations.
B. Where significant shear loads (greater than 5,000 lb. per anchor bolt) are transferred at
column base plates, the equipment vendor shall provide a shear key.
1.09 DEFLECTIONS
A. Maximum beam deflections as a fraction of span for walkways and platforms shall be
L/240 for total load and L/360 for live load. Maximum total load deflection for
equipment supports shall be L/450.
PART 2 PRODUCTS
2.01 GENERAL
A. Materials shall be in conformance with information shown on the drawings and in other
technical specification sections. See individual component and equipment specifications
for additional requirements.
PART 3 EXECUTION
3.01 GENERAL
A. Attachments and braces shall be made in such a manner that the component force is
transferred to the lateral force-resisting system of the structure. Attachment
requirements and size and number of braces shall be based on the calculations
submitted by the Supplier/Subcontractor.
Lake Keowee to Adkins WTP Raw Water System Bracing and Anchoring
154828 01 73 23 - 7
B. All anchorage of equipment is specified to be made by cast-in anchor bolts in concrete
elements unless specifically noted otherwise on the drawings or other specification
sections. Supplier/Subcontractor shall be responsible for any remedial work or
strengthening of concrete elements because of superimposed seismic loading if anchor
bolts are improperly installed or omitted due to lack of submittal review or improper
placement for any reason, at no additional cost to the Owner or Design-Builder or Design-
Builder’s Representative.
C. Anchor bolts shall be provided and installed by the Supplier/Subcontractor in accordance
with Section 05 05 20. Size of anchor bolts and embedment of anchor bolts shall be
based on the calculations submitted by the Supplier/Subcontractor.
D. Details of and calculations for all anchorages shall be submitted and accepted in
accordance with paragraph 1.03 prior to placement of concrete or erection of other
structural supporting members. Submittals received after structural supports are in place
will be rejected if proposed anchorage method would create an overstressed condition of
the supporting member. The Supplier/Subcontractor shall be responsible for revisions to
the anchorages and/or strengthening of the structural support so that there is no
overstressed condition at no additional cost to the Owner or Design-Builder or Design-
Builder’s Representative.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Cutting and Patching
154828 01 73 29 - 1
SECTION 01 73 29
CUTTING AND PATCHING
PART 1 GENERAL
1.01 STRUCTURES
A. The Contractor shall take all precautions necessary to protect the integrity and
usefulness of all existing facilities. If necessary, the Contractor may, with the approval of
the Owner, remove such existing structures, including curbs, gutters, pipelines and utility
poles as may be necessary for the performance of the work, and shall rebuild the
structures thus removed in as good a condition as found with the requirements specified.
He shall also repair existing structures which may be damaged as a result of the work
under this contract.
1.02 ROADS AND STREETS
A. Unless otherwise specified, roads and streets in which the surface is removed, broken, or
damaged, or in which the ground has caved or settled during the work under this
contract, shall be resurfaced and brought to the original grade and section. Roadways
used by the Contractor shall be cleaned and repaired. Before resurfacing material is
placed, edges of pavements shall be trimmed back far enough to provide clean, solid,
vertical faces, and shall be free of loose material. All paved surfaces shall be cut with a
pavement saw. Rough cuts are not allowed. Repair work shall conform to the paving
specifications.
1.03 CULTIVATED AREAS AND OTHER SURFACE IMPROVEMENTS
A. Cultivated or planted areas and other surface improvements which are damaged by
actions of the Contractor shall be restored as nearly as possible to their original
condition. Restoration shall take place within 1 week or sooner as directed by the
Construction Manager.
B. Existing guard posts, barricades, and fences shall be protected and replaced if damaged.
1.04 PROTECTION OF EXISTING INSTALLATIONS
A. The Contractor shall protect all existing operating facilities and structures from damages.
However, if damage occurs, the Contractor shall immediately correct or replace existing
equipment, controls, systems, structures, or facilities which are damaged in any way as a
result of his operations.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 1
SECTION 01 75 00
SYSTEM TESTING
PART 1 GENERAL
1.01 DESCRIPTION
A. This section contains requirements for the Contractor's performance in documenting
testing work required under the contract.
B. In addition, this section contains requirements for the Contractor's performance during
installed performance testing of all piping, mechanical, electrical, and instrumentation
systems provided under the contract.
C. This section supplements, but does not supersede, specific testing requirements found
elsewhere in these Specifications and as required by the manufacturers.
D. The Contractor is made aware that each system requires specific performance and
operational tests.
1.02 QUALITY ASSURANCE
A. Contractor's Quality Assurance Manager:
1. The Contractor shall appoint an operations engineer or equally qualified operations
specialist as Quality Assurance Manager to manage, coordinate, and supervise the
Contractor's quality assurance program.
2. The Quality Assurance Manager shall have at least five (5) years of total experience,
or experience on at least five (5) separate projects, managing the startup
commissioning of mechanical, electrical, instrumentation, and piping systems.
3. The Quality Assurance Manager role is intended to be filled on an as-needed basis as
specified and not intended to be a full-time job site representative. The Quality
Assurance Manager role can be filled by resident Project Superintendent provided
that the minimum specified qualifications are met.
B. Quality Assurance Program:
1. The quality assurance program shall be developed by the Contractor and shall
include:
a. A testing plan setting forth the sequence in which all testing work required under
this Specification will be implemented;
b. A documentation program to record the results of all equipment and system
tests;
c. An installed performance testing program for all mechanical, electrical,
instrumentation equipment and systems installed under the contract;
d. A calibration program for all instruments, meters, monitors, gauges, and
thermometers installed under the contract;
e. A calibration program for all instruments, gauges, meters, and thermometers
used for determining the performance of equipment and systems installed under
the contract; and
f. A testing schedule conforming to the requirements specified in Part 2.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 2
2. For the purposes of this section, a system shall include all items of equipment,
devices, and appurtenances connected in such a fashion as their operation or
function complements, protects, or controls the operation or function of the
equipment.
3. The Quality Assurance Manager shall coordinate the activities of the Contractor and
all subcontractors and suppliers to implement the requirements of this section.
C. Calibration:
1. All test equipment (gauges, meters, thermometers, analysis instruments, and other
equipment) used for calibrating or verifying the performance of equipment installed
under the contract shall be calibrated to within plus or minus 2 percent of actual
value at full scale.
2. Test equipment employed for individual test runs shall be selected so that expected
values as indicated by the detailed performance specifications will fall between 60
and 85 percent of full scale.
3. Pressure gauges shall be calibrated in accordance with ANSI/ASME B40.1.
4. Thermometers shall be calibrated in accordance with ASTM E77 and shall be
furnished with a certified calibration curve.
5. Liquid flow meters, including all open channel flow meters and all meters installed in
pipelines with diameters greater than two (2) inches shall be calibrated in situ using
either the total count or dye dilution methods as referenced in 01 75 00-1.02 D,
below.
6. Gas flow meters installed in piping systems with diameters greater than six (6) inches
shall be calibrated in situ using the pitot tube velocity averaging method as
referenced in 01 75 00-1.02 D, below.
7. Flow meter calibration work shall be performed by individuals skilled in the
techniques to be employed.
8. Calibration tests for flow metering systems shall be performed over a range of not
less than 10 percent to at least 75 percent of system full scale.
9. At least five (5) confirmed valid data points shall be obtained within this range.
10. Confirmed data points shall be validated by not less than three (3) test runs with
results which agree within plus or minus 2 percent.
D. References:
1. This section contains references to the documents set out in the chart below. They
are a part of this section as specified and modified. In case of a conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, whether or not the document has been superseded by a version with a later
date, discontinued or replaced.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 3
Reference Title
ANSI/ASME B40.1 Gauges Pressure Indicating Dial Type—Elastic Element
ASTM E77 Method for Verification and Calibration of Liquid-in-Glass Thermometers
ASHRAE 41.8 Standard Methods of Measurement of Flow of Gas
Dye Dilution Calibration
Method
Flow Measurements in Sanitary Sewers by Dye Dilution, Turner Designs
Mountain View, California
Flow Measurement in Sewer Lines by the Dye Dilution Method, Journal
of the Water Pollution Control Federation, Vol. 55, Number 5, May,
1983, pg. 531
Flow Measurement in Open Channels and Closed Conduits, Vol 1, U.S.
Department of Commerce, National Bureau of Standards, pg. 361
Techniques of Water-Resources Investigations of the United States
Geological Survey, Chapter 16, Measurement of Discharge Using
Tracers
1.03 SUBMITTALS
A. Submittal material, to be submitted in accordance with Section 01 33 00 prior to the
commencement of testing, shall consist of the following:
1. A complete description of the Contractor's plan for documenting the results from the
test program in conformance with the requirements of paragraph 01 75 00-2.02 A,
including:
a. Proposed plan for documenting the calibration of all test instruments
b. Proposed plan for calibration of all instrument systems, including flow meters and
all temperature, pressure, weight, and analysis systems
c. Sample forms for documenting the results of field pressure and performance
tests
B. The credentials and certification of the testing laboratory proposed by the Contractor for
calibration of all test equipment.
C. Preoperational check-out procedures, reviewed and approved by the respective
equipment manufacturers.
D. Detailed testing plans, setting forth step-by-step descriptions of the procedures proposed
by the Contractor for the systematic testing of all equipment and systems installed under
the contract.
E. A schedule and subsequent updates, presenting the Contractor's plan for testing the
equipment and systems installed under the contract.
F. A schedule establishing the expected time period (calendar dates) when the Contractor
plans to commence operational testing of the completed systems, along with a
description of the temporary systems and installations planned to allow operational
testing to take place.
G. A summary of the Contractor's Quality Assurance Manager's qualifications, showing
conformance to paragraph 01 75 00-1.02 A requirements.
H. Quality assurance program documentation.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 4
PART 2 PRODUCTS
2.01 GENERAL
A. The Contractor shall prepare test plans and documentation plans as specified in the
following paragraphs.
B. The Engineer will not witness any test work for the purpose of acceptance until all test
documentation and calibration plans and the specified system or equipment test plans
have been submitted and accepted.
2.02 DOCUMENTATION
A. Documentation Plans:
1. The Contractor shall develop a records keeping system to document compliance with
the requirements of this Section. Calibration documentation shall include
identification (by make, manufacturer, model, and serial number) of all test
equipment, date of original calibration, subsequent calibrations, calibration method,
and test laboratory.
2. Equipment and system documentation shall include date of test, equipment number
or system name, nature of test, test objectives, test results, test instruments
employed for the test and signature spaces for the Engineer's witness and the
Contractor's quality assurance manager. A separate file shall be established for each
system and item of equipment. These files shall include the following information as
a minimum:
a. Metallurgical tests
b. Factory performance tests
c. Accelerometer and temperature recordings made during shipment
d. Field calibration tests
e. Field pressure tests
f. Field performance tests
g. Field operational tests
3. Section 01 99 90 contains samples showing the format and level of detail required
for the documentation forms. The Contractor is advised that these are samples only
and are not specific to this project or to any item of equipment or system to be
installed under the contract.
4. The Contractor shall develop test documentation forms specific to each item of
equipment and system installed under the contract. Acceptable documentation
forms for all systems and items of equipment shall be produced for review by the
Engineer.
5. Once the Engineer has reviewed and taken no exception to the forms proposed by
the Contractor, the Contractor shall produce sufficient forms, at his expense, to
provide documentation of all testing work to be conducted as a part of the contract.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 5
B. Test Plans:
1. The Contractor shall develop test plans detailing the coordinated, sequential testing
of each item of equipment and system installed under the contract. Each test plan
shall be specific to the item of equipment or system to be tested. Test plans shall
identify by specific equipment or tag number each device or control station to be
manipulated or observed during the test procedure and the specific results to be
observed or obtained. Test plans shall also be specific as to support systems
required to complete the test work, temporary systems required during the test work,
subcontractors' and manufacturers' representatives to be present and expected test
duration. As a minimum, the test plans shall include the following features:
a. Step-by-step proving procedure for all control and electrical circuits by imposing
low voltage currents and using appropriate indicators to affirm that the circuit is
properly identified and connected to the proper device;
b. Calibration of all analysis instruments and control sensors;
c. Performance testing of each individual item of piping, mechanical, electrical, and
instrumentation equipment. Performance tests shall be selected to duplicate the
operating conditions described in the project manual;
d. System tests designed to duplicate, as closely as possible, operating conditions
described in the project manual; and
e. Shoring, bracing, pipe restraint, and other devices necessary to successfully
complete the testing.
2. Test plans shall contain a complete description of the procedures to be employed to
achieve the desired test environment.
C. Testing Schedule:
1. The Contractor shall produce a testing schedule setting forth the sequence
contemplated for performing the test work. The schedule shall be in bar chart form,
plotted against calendar time, shall detail the equipment and systems to be tested,
and shall be coordinated with the Contractor's construction schedule. The schedule
shall show the contemplated start date, duration of the test and completion of each
test.
2. The test schedule shall be submitted no later than four (4) weeks in advance of the
date testing is to begin. The Engineer will not witness any testing work for the
purpose of acceptance until the Contractor has submitted a schedule to which the
Engineer takes no exception.
3. The test schedule shall be updated weekly, showing actual dates of test work,
indicating systems and equipment testing completed satisfactorily and meeting the
requirements of these Specifications.
PART 3 EXECUTION
3.01 GENERAL
A. The Quality Assurance Manager shall organize teams made up of qualified
representatives of the Contractor, equipment suppliers, subcontractors, the Contractor's
independent testing laboratory, and others, as appropriate, to efficiently and
expeditiously calibrate and test the equipment and systems installed and constructed
under the contract.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 6
B. The objective of the testing program shall be to demonstrate that the structures,
systems, and equipment constructed and installed under this contract meet all
performance requirements and the facility is ready for the commissioning process to
commence. In addition, the testing program shall produce baseline operating conditions
for the Owner to use in a preventive maintenance program.
3.02 CALIBRATION OF FIXED INSTRUMENTS
A. Calibration of analysis instruments, sensors, gauges, and meters installed under this
contract shall proceed on a system-by-system basis. No equipment or system
performance acceptance tests shall be performed until instruments, gauges, and meters
to be installed in that particular system have been calibrated and the calibration work
has been witnessed by the Engineer.
B. All analysis instruments, sensors, gauges, and meters used for performance testing shall
be subject to recalibration to confirm accuracy after completion, but prior to acceptance
of each performance test. All analysis instruments, sensors, gauges, and meters
installed under the contract shall be subject to recalibration as a condition precedent to
commissioning.
3.03 SYSTEM AND EQUIPMENT PERFORMANCE TESTS
A. General:
1. Each item of mechanical, electrical, and instrumentation equipment installed under
the contract shall be tested to demonstrate compliance with the performance
requirements of this project manual. Each electrical, instrumentation, mechanical,
and piping system installed or modified under this contract shall be tested in
accordance with the requirements of these Specifications.
2. Performance testing of the force mains (EQ influent and drain piping) will include
individual testing of each pipe material as described in Part 1. Once all performance
testing for each pipe material has been successfully completed, the force mains will
be plugged, filled and pressurized. The force mains will be pressurized so that no
portion of the force mains experience pressure in excess of its rated operating
pressure and held for three (3) hours, with no visible leaks or pressure drops, or the
lesser of that allowed for any of the individual pipe materials.
3. Operational tests may not proceed for any equipment or system without successful
completion of the respective performance testing.
4. Performance tests shall consist of the following:
a. Pressure and/or leakage tests
b. Electrical testing as specified in Division 26
c. Wiring and piping, individual component, loop, loop commissioning and tuning
testing
d. Preoperational checkout for all mechanical equipment. Preoperational check-out
procedures shall be reviewed and approved by the respective equipment
manufacturers
e. Initial operation tests of all mechanical, electrical, and instrumentation
equipment and systems to demonstrate compliance with the performance
requirements of this project manual.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 7
5. In general, performance tests for any individual system shall be performed in the
order listed above. The order may be altered only on the specific written
authorization of the Engineer after receipt of a written request, complete with
justification of the need for the change in sequence.
B. Pressure and Leakage Tests:
1. Pressure and leakage tests shall be conducted in accordance with applicable
portions of Divisions 03 and 40. Evidence of successful completion of the pressure
and leakage tests shall be documented on the appropriate test forms prepared by
the Contractor.
C. Functional Checkout:
1. Prior to energization (in the case of electrical systems and equipment), all circuits
shall be rung out and tested for continuity and shielding in accordance with the
procedures required in Division 26.
D. Component Calibration and Loop Testing:
1. Prior to energization (in the case of instrumentation system and equipment), all loops
and associated instruments shall be calibrated and tested.
E. Electrical Resistance:
1. Electrical resistance testing shall be in accordance with Division 26.
F. Preoperational Tests:
1. Preoperational tests shall include the following:
a. Alignment of equipment, using reverse dial indicator method;
b. Pre-operation lubrication; and
c. Tests per the manufacturers' recommendations for prestart preparation and
preoperational check-out procedures.
G. Functional Tests:
1. General:
a. Once all affected equipment has been subjected to the required preoperational
check-out procedures and the Engineer has witnessed and has not found
deficiencies in that portion of the work, individual items of equipment and
systems may be started and operated under simulated operating conditions to
determine as nearly as possible whether the equipment and systems meet the
requirements of these specifications.
b. Potable or raw water may be used for the testing of all liquid systems except
gaseous, oil, or chemical systems. Test media for gaseous, oil, or chemical
systems shall either be the intended fluid or a compatible substitute.
c. The equipment shall be operated a sufficient period of time to determine
machine operating characteristics, including noise, temperatures and vibration;
to observe performance characteristics; and to permit initial adjustment of
operating controls.
d. When testing requires the availability of auxiliary systems such as looped piping,
electrical power, control air, or instrumentation which have not yet been placed in
service, the Contractor shall provide acceptable substitute sources, capable of
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 8
meeting the requirements of the machine, device, or system at no additional cost
to the Owner.
e. Disposal methods for test media shall be subject to review by the Engineer.
f. During the functional test period, the Contractor shall obtain baseline operating
data on all equipment with motors greater than 1 horsepower to include
amperage, bearing temperatures, and vibration. The baseline data shall be
collected for the Owner to enter in a preventive maintenance system.
g. Test results shall be within the tolerances set forth in the applicable sections of
these Specifications. If no tolerances have been specified, test results shall
conform to tolerances established by recognized industry practice. Where, in the
case of an otherwise satisfactory functional test, any doubt, dispute, or difference
should arise between the Engineer and the Contractor regarding the test results
or the methods or equipment used in the performance of such test, then the
Owner may order the test to be repeated.
h. If the repeat test, using such modified methods or equipment as the Owner may
require, confirms the previous test, then all costs in connection with the repeat
test will be paid by the Owner. Otherwise, the costs shall be borne by the
Contractor. Where the results of any functional test fail to comply with the
contract requirements for such test, then such repeat tests as may be necessary
to achieve the contract requirements shall be made by the Contractor at his
expense.
i. The Contractor shall provide, at no expense to the Owner, all power, fuel,
compressed air supplies, water, and chemicals, all labor, temporary piping,
heating, ventilating, and air conditioning for any areas where permanent facilities
are not complete and operable at the time of functional tests, and all other items
and work required to complete the functional tests. Temporary facilities shall be
maintained until permanent systems are in service.
2. Retesting:
a. If under test, any portion of the work should fail to fulfill the contract
requirements and is adjusted, altered, renewed, or replaced, tests on that portion
when so adjusted, altered, removed, or replaced, together with all other portions
of the work as are affected thereby, shall, unless otherwise directed by the
Engineer, be repeated within reasonable time and in accordance with the
specified conditions.
b. The Contractor shall pay to the Owner all reasonable expenses incurred by the
Owner, including the costs of the Engineer, as a result of repeating such tests.
3. Post-Test Inspection:
a. Once functional testing has been completed, all machines shall be rechecked for
proper alignment and realigned, as required.
b. All equipment shall be checked for loose connections, unusual movement, or
other indications of improper operating characteristics. Any deficiencies shall be
corrected to the satisfaction of the Engineer.
c. All machines or devices which exhibit unusual or unacceptable operating
characteristics shall be disassembled and inspected.
d. Any defects found during the course of the inspection shall be repaired or the
specific part or entire equipment item shall be replaced to the complete
satisfaction of the Engineer at no cost to the Owner.
Lake Keowee to Adkins WTP Raw Water System System Testing
154828 01 75 00 - 9
3.04 OPERATIONAL TESTS
A. Once all equipment and systems have been tested successfully individually, the
Contractor shall fill all with the intended process fluids. After filling operations have been
completed and prior to start-up and commissioning, the Contractor shall operate all
systems for a continuous period of not less than 72 hours, simulating actual operating
conditions to the greatest extent possible.
B. The Contractor shall install temporary connections, bulkheads and make other provisions
to recirculate process fluids or otherwise simulate anticipated operating conditions.
C. During the operational testing period, the Contractor's Quality Assurance Manager and
testing team shall monitor the characteristics of each machine and system and report
any unusual conditions to the Engineer. This test will include operation under various
loading conditions, as directed by the Engineer.
D. The operational testing period shall commence after this initial period of variable
operation. Should the operational testing period be halted for any reason related to the
facilities constructed or the equipment furnished under this contract, or the Contractor's
temporary testing systems, the operational testing program shall be repeated until the
specified continuous period has been accomplished without interruption. All process
units shall be brought to full operating conditions, including temperature, pressure, and
flow.
E. All costs for water, fuel, power, and chemicals required during this operational test shall
be borne by the Contractor. Process systems and units shall mean all materials and
equipment provided in this contract.
F. A detailed description of the operational test shall be included in the testing plan.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Operation and Maintenance Data
154828 01 78 23 - 1
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 GENERAL
1.01 SCOPE
A. Operation and maintenance (O&M) instructions shall be provided in accordance with this
section and as required in the technical sections of this project manual. O&M information
shall be provided for each maintainable piece of equipment, equipment assembly or
subassembly, and material provided or modified under this contract.
B. O&M instructions must be submitted and accepted before on-site training may start.
1.02 TYPES OF INFORMATION REQUIRED
A. General:
1. O&M information shall contain the names, addresses, and telephone numbers of the
manufacturer, the nearest representative of the manufacturer, and the nearest
supplier of the manufacturer's equipment and parts. In addition, one or more of the
following items of information shall be provided as applicable.
B. Operating Instructions:
1. Specific instructions, procedures, and illustrations shall be provided for the following
phases of operations:
a. Safety Precautions: List personnel hazards for equipment and list safety
precautions for all operating conditions.
b. Operator Prestart: Provide requirements to set up and prepare each system for
use.
c. Start-Up, Shutdown, And Postshutdown Procedures: Provide a control sequence
for each of these operations.
d. Normal Operations: Provide control diagrams with data to explain operation and
control of systems and specific equipment.
e. Emergency Operations: Provide emergency procedures for equipment
malfunctions to permit a short period of continued operation or to shut down the
equipment to prevent further damage to systems and equipment. Include
emergency shutdown instructions for fire, explosion, spills, or other foreseeable
contingencies. Provide guidance on emergency operations of all utility systems
including valve locations and portions of systems controlled.
f. Operator Service Requirements: Provide instructions for services to be performed
by the operator such as lubrication, adjustments, and inspection.
g. Environmental Conditions: Provide a list of environmental conditions
(temperature, humidity, and other relevant data) which are best suited for each
product or piece of equipment and describe conditions under which equipment
should not be allowed to run.
C. Preventive Maintenance:
1. The following information shall be provided for preventive and scheduled
maintenance to minimize corrective maintenance and repair:
Lake Keowee to Adkins WTP Raw Water System Operation and Maintenance Data
154828 01 78 23 - 2
a. Lubrication Data: Provide lubrication data, other than instructions for lubrication
in accordance with paragraph 1.02 Operator Service Requirements.
1) A table showing recommended lubricants for specific temperature ranges
and applications;
2) Charts with a schematic diagram of the equipment showing lubrication
points, recommended types and grades of lubricants, and capacities; and
3) A lubrication schedule showing service interval frequency.
b. Preventive Maintenance Plan And Schedule: Provide manufacturer's schedule for
routine preventive maintenance, inspections, tests, and adjustments required to
ensure proper and economical operation and to minimize corrective maintenance
and repair. Provide manufacturer's projection of preventive maintenance man-
hours on a daily, weekly, monthly, and annual basis including craft requirements
by type of craft.
D. Corrective Maintenance:
1. Manufacturer's recommendations shall be provided on procedures and instructions
for correcting problems and making repairs.
a. Troubleshooting Guides And Diagnostic Techniques: Provide step-by-step
procedures to promptly isolate the cause of typical malfunctions. Describe clearly
why the checkout is performed and what conditions are to be sought. Identify
tests or inspections and test equipment required to determine whether parts and
equipment may be reused or require replacement.
b. Wiring Diagrams And Control Diagrams: Wiring diagrams and control diagrams
shall be point-to-point drawings of wiring and control circuits including factory-
field interfaces. Provide a complete and accurate depiction of the actual job-
specific wiring and control work. On diagrams, number electrical and electronic
wiring and pneumatic control tubing and the terminals for each type identically to
actual installation numbering.
c. Maintenance And Repair Procedures: Provide instructions and list tools required
to restore product or equipment to proper condition or operating standards.
d. Removal And Replacement Instructions: Provide step-by-step procedures and list
required tools and supplies for removal, replacement, disassembly, and assembly
of components, assemblies, subassemblies, accessories, and attachments.
Provide tolerances, dimensions, settings, and adjustments required. Instructions
shall include a combination of test and illustrations.
e. Spare Parts And Supply Lists: Provide lists of spare parts and supplies required
for maintenance and repair to ensure continued service or operation without
unreasonably delays. Special consideration is required for facilities at remote
locations. List spare parts and supplies that have a long lead time to obtain.
f. Corrective Maintenance Manhours: Provide manufacturer's projection of
corrective maintenance man-hours including craft requirements by type of craft.
Corrective maintenance that requires participation of the equipment
manufacturer shall be identified and tabulated separately.
E. Appendices:
1. The following information shall be provided; include information not specified in the
preceding paragraphs but pertinent to the maintenance or operation of the product
or equipment.
Lake Keowee to Adkins WTP Raw Water System Operation and Maintenance Data
154828 01 78 23 - 3
a. Parts Identification: Provide identification and coverage for all parts of each
component, assembly, subassembly, and accessory of the end items subject to
replacement. Include special hardware requirements, such as requirement to use
high-strength bolts and nuts. Identify parts by make, model, serial number, and
source of supply to allow reordering without further identification. Provide clear
and legible illustrations, drawings, and exploded views to enable easy
identification of the items. When illustrations omit the part numbers and
description, both the illustrations and separate listing shall show the index,
reference, or key number which will cross-reference the illustrated part to the
listed part. Parts shown in the listings shall be grouped by components,
assemblies, and subassemblies.
b. Warranty Information: List and explain the various warranties and include the
servicing and technical precautions prescribed by the manufacturers or contract
documents to keep warranties in force.
c. Personnel Training Requirements: Provide information available from the
manufacturers to use in training designated personnel to operate and maintain
the equipment and systems properly.
d. Testing Equipment And Special Tool Information: Provide information on test
equipment required to perform specified tests and on special tools needed for
the operation, maintenance, and repair of components.
1.03 TRANSMITTAL PROCEDURE
A. Unless otherwise specified, O&M manuals, information, and data shall be transmitted in
accordance with Section 01 33 00 accompanied by Transmittal Form 01 78 23-A and
Equipment Record Forms 01 78 23-B and/or 01 78 23-C, as appropriate, all as specified
in Section 01 99 90. The transmittal form shall be used as a checklist to ensure the
manual is complete. Only complete sets of O&M instructions will be reviewed for
acceptance.
B. 5 copies of the specified O&M information shall be provided. For ease of identification,
each manufacturer's brochure and manual shall be appropriately labeled with the
equipment name and equipment number as it appears in the project manual. The
information shall be organized in the binders in numerical order by the equipment
numbers assigned in the project manual. The binders shall be provided with a table of
contents and tab sheets to permit easy location of desired information. Binders shall be
heavy-duty 3-ring style, which are suitable for bookshelf storage.
C. If manufacturers' standard brochures and manuals are used to describe O&M
procedures, such brochures and manuals shall be modified to reflect only the model or
series of equipment used on this project. Extraneous material shall be crossed out neatly
or otherwise annotated or eliminated.
1.04 PAYMENT
A. Acceptable O&M information for the project must be delivered to the Construction
Manager prior to the project being 65 percent complete. Progress payments for work in
excess of 65 percent completion will not be made until the specified acceptable O&M
information has been delivered to the Construction Manager.
Lake Keowee to Adkins WTP Raw Water System Operation and Maintenance Data
154828 01 78 23 - 4
1.05 FIELD CHANGES
A. Following the acceptable installation and operation of an equipment item, the item's
instructions and procedures shall be modified and supplemented by the Contractor to
reflect any field changes or information requiring field data.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Project Record Documents
154828 01 78 39 - 1
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
PART 1 GENERAL
1.01 DRAWINGS
A. Record drawings refer to those documents maintained and annotated by the Contractor
during construction and are defined as
1. a neatly and legibly marked set of contract drawings showing the final location of
piping, equipment, electrical conduits, outlet boxes and cables;
2. additional documents such as schedules, lists, drawings, and electrical and
instrumentation diagrams included in the specifications; and
3. Contractor layout and installation drawings.
B. Unless otherwise specified, record drawings shall be full size and maintained in a clean,
dry, and legible condition. Record documents shall not be used for construction purposes
and shall be available for review by the Construction Manager during normal working
hours at the Contractor's field office. At the completion of the work, prior to final
payment, all record drawings shall be submitted to the Construction Manager.
C. Marking of the drawings shall be kept current and shall be done at the time the material
and equipment are installed. Annotations to the record documents shall be made with an
erasable colored pencil conforming to the following color code:
1. Additions - Red
2. Deletions - Green
3. Comments - Blue
4. Dimensions - Graphite*
*Legibly mark to record actual depths, horizontal and vertical location of underground raceways, cables, and
appurtenances referenced to permanent surface improvements.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Commissioning
154828 01 91 00 - 1
SECTION 01 91 00
COMMISSIONING
PART 1 GENERAL
1.01 DESCRIPTION:
A. This section contains requirements for the Contractor's performance during the
commissioning of the structures, equipment and systems constructed and installed
during the course of this contract. All commissioning work, as described in this section,
shall be performed by the Contractor.
1.02 QUALITY ASSURANCE
A. Cleanup:
1. Following completion of the operational testing period, the Contractor shall remove,
clean, and replace all permanent and temporary filters and strainers in all pipeline
systems; replace all HVAC filters; dewater and clean all sumps; and dewater all
process units for final inspection as a condition precedent to commissioning.
B. Commissioning Team:
1. The Contractor shall assemble a commissioning team under the direction of an
individual duly authorized to commit the Contractor's personnel and resources to
respond to requests for assistance on the part of the Construction Manager or,
through the Construction Manager, the Owner. The commissioning team shall consist
of representatives of the Contractor's mechanical, electrical, and instrumentation
subcontractors, and others as appropriate. The commissioning team shall be
available at the site of the work during normal working hours (8 hours a day, 5 days a
week, Saturdays, Sundays, and legal holidays excepted) and shall be available within
2 hours' notice at all other times upon notice by telephone. The commissioning team
shall at all times be equipped and ready to provide for emergency repairs, adjust-
ments, and corrections to the equipment and systems installed and modified as a
part of this contract.
1.03 SUBMITTALS
A. The following information shall be submitted to the Construction Manager in accordance
with the provisions of Section 01 33 00:
1. Detailed plans for commissioning each process unit and each system constructed or
modified as a part of the work performed under this contract.
2. The Contractor's plan for providing a commissioning team conforming to the
requirements of paragraph 1.02 Commissioning Team during the commissioning
period. The plan shall be complete with a daytime staffing plan and names,
qualifications, and telephone numbers of those assigned to off-hour standby duty.
Lake Keowee to Adkins WTP Raw Water System Commissioning
154828 01 91 00 - 2
PART 2 PRODUCTS
2.01 SUMMARY
A. Working with representatives of the Owner and the Construction Manager, the Contractor
shall develop and produce a detailed, written plan for the startup and initial operation,
under actual operating conditions, of the equipment and systems installed and
constructed under this contract. The document, after acceptance by the Construction
Manager, shall serve as the guidance manual for the commissioning process.
PART 3 EXECUTION
3.01 SUMMARY
A. After completion of the equipment and system performance and operational testing,
where required, and agreement on the part of the Construction Manager that the
systems did meet all test requirements, commissioning will begin. The commissioning
period for each modified or new unit process system shall be four (4) weeks. The
Contractor shall remove all temporary piping, bulkheads, controls and other alterations to
the permanent systems that may have been needed during the performance and
operational testing and shall perform the tasks necessary to make the improvements
constructed under this contract fully operational. The Construction Manager shall confirm
in writing the date(s) that the system is ready for commissioning and on which actual
commissioning activities commence. Activities conducted prior to such written
confirmation shall not constitute commissioning.
B. The Owner's operation and maintenance personnel will be responsible for operation of
the systems to be commissioned. The portion of the work to be commissioned shall be
fully operational, performing all functions for which it was designed.
C. The Contractor shall be available at all times during commissioning periods to provide
immediate assistance in case of failure of any portion of the system being constructed.
At the end of the commissioning period and when all corrections required by the
Construction Manager to assure a reliable and completely operational facility are
complete, the Construction Manager shall issue a completion certificate. Each system
shall have been issued a completion certificate as a condition precedent to the final
acceptance of the work of this contract.
D. During the commissioning period, the Owner shall be responsible for all normal
operational costs and the Contractor shall bear the costs of all necessary repairs or
replacements, including labor and materials, required to keep the portion of the plant
being commissioned, operational.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 1
SECTION 01 99 90
REFERENCE FORMS
PART 1 FORMS
1.01 DESCRIPTION
A. The forms listed below and included in this section are referenced from other sections of
the project manual:
Form No. Title
01 33 00-A Submittal Transmittal Form
01 45 20-A Equipment Test Report Form
01 78 23-A Operation and Maintenance Transmittal Form
01 78 23-B Equipment Record Form
01 78 23-C Equipment Record Form
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 2
01 33 00-A. SUBMITTAL TRANSMITTAL FORM
Submittal Transmittal
Submittal Description: Submittal No:1 Spec Section:
Routing Sent Received
Owner: Contractor/CM
Project: CM/Engineer
Engineer/CM
Contractor: CM/Contractor
We are sending you:
Attached
Under separate cover via _________
Submittals for review and comment
Product data for information only
Remarks:
Item Copies Date Section No. Description Review
actiona
Reviewer
initials
Review comments
attached
aNote: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected
Attach additional sheets if necessary.
Contractor
Certify either a or b:
a. We have verified that the material or equipment contained in this submittal meets all the requirements,
including coordination with all related work, specified (no exceptions).
b. We have verified that the material or equipment contained in this submittal meets all the requirements
specified except for the attached deviations.
No. Deviation
Certified by:
Contractor's Signature:
1See Section 01 33 00-1.04. A, Transmittal Procedure.
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 3
01 45 20-A. EQUIPMENT TEST REPORT FORM
NOTE: This example equipment test report is provided for the benefit of the Contractor and is not specific to any piece of
equipment to be installed as a part of this project. The example is furnished as a means of illustrating the level of detail
required for the preparation of equipment test report forms for this project.
City Of Sample
Example Water Treatment Plant
Stage IV Expansion Project
ABC Construction Company, Inc., General Contractor
XYZ Engineering, Inc., Construction Manager
Equipment Test Report
• Equipment Name: Sludge Pump 2
• Equipment Number: P25202
• Specification Ref: 11390
• Location: East Sedimentation Basin Gallery
Contractor Construction Manager
Verified Date Verified Date
A. Preoperational Checklist
1. Mechanical
a. Lubrication
b. Alignment
c. Anchor bolts
d. Seal water system operational
e. Equipment rotates freely
f. Safety guards
g. Valves operational
h. Hopper purge systems operational
i. Sedimentation tank/hopper clean
j. O&M manual information complete
k. Manufacturer's installation certificate complete
2. Electrical (circuit ring-out and high-pot tests)
a. Circuits:
1) Power to MCC 5
2) Control to HOA
3) Indicators at MCC:
a) Red (running)
b) Green (power)
c) Amber (auto)
4) Indicators at local control panel
b. Wiring labels complete
c. Nameplates:
1) MCC
2) Control station
3) Control panel
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 4
Contractor Construction Manager
Verified Date Verified Date
d. Equipment bumped for rotation
3. Piping Systems
a. Cleaned and flushed:
1) Suction
2) Discharge
b. Pressure tests
c. Temporary piping screens in place
4. Instrumentation and Controls
a. Flowmeter FE2502F calibration
1) Calibration Report No.
b. Flow recorder FR2502G calibrated against
transmitter
c. VFD speed indicator calibrated against
independent reference
d. Discharge overpressure shutdown switch
calibration
e. Simulate discharge overpressure Shutdown
B. Functional Tests
1. Mechanical
a. Motor operation temperature satisfactory
b. Pump operating temperature satisfactory
c. Unusual noise, etc?
d. Pump operation: 75 gpm/50 psig
(1) Measurement:
(a) Flow:
(b) Pressure:
(c) Test gage number:
e. Alignment hot
f. Dowelled in
g. Remarks:
2. Electrical
a. Local switch function:
1) Runs in HAND
2) No control power in OFF
3) Timer control in AUTO
b. Overpressure protection switch PS2502C
functional in both HAND and AUTO
c. Overpressure protection switch PS2502C set at
75 psig
d. PLC 2500 set at 24-hour cycle, 25 min ON
C. Operational Test
1. 48-hour continuous test. Pump cycles as specified,
indicators functional, controls functional, pump
maintains capacity, overpressure protection remains
functional, hour meter functional
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 5
RECOMMENDED FOR BENEFICIAL OCCUPANCY:
Construction Manager Date
ACCEPTED FOR BENEFICIAL OCCUPANCY
Owner's Representative Date
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 6
01 78 23-A. OPERATION AND MAINTENANCE TRANSMITTAL FORM
Date: Submittal No:2
To: Contract No:
Spec. Section:
Submittal Description:
Attention: From:
Checklist Contractor Construction Manager
Satisfactory N/A Accept Deficient
1. Table of contents
2. Equipment record forms
3. Manufacturer information
4. Vendor information
5. Safety precautions
6. Operator prestart
7. Start-up, shutdown, and postshutdown procedures
8. Normal operations
9. Emergency operations
10. Operator service requirements
11. Environmental conditions
12. Lubrication data
13. Preventive maintenance plan and schedule
14. Troubleshooting guides and diagnostic techniques
15. Wiring diagrams and control diagrams
16. Maintenance and repair procedures
17. Removal and replacement instructions
18. Spare parts and supply list
19. Corrective maintenance man-hours
20. Parts identification
21. Warranty information
22. Personnel training requirements
23. Testing equipment and special tool information
Remarks:
Contractor's Signature :
2 See Section 01 33 00-1.04.A, Transmittal Procedure.
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 7
01 78 23-B. EQUIPMENT RECORD FORM
Equip Descrip Equip Loc
Equip No. Shop Dwg No. Date Inst Cost
Mfgr Mfgr Contact
Mfgr Address Phone
Vendor Vendor Contact
Vendor Address Phone
Maintenance Requirements D W M Q S A Hours
Lubricants: Recommended:
Alternative:
Misc. Notes:
Recommended Spare Parts Electrical Nameplate Data
Part No Quan Part Name Cost Equip
Make
Serial No. Id No.
Model No. Frame No.
Hp V Amp Hz
Ph Rpm Sf Duty
Code Insl. Cl Des Type
Nema Des C Amb Temp Rise Rating
Misc.
Mechanical Nameplate Data
Equip
Make
Serial No. Id No.
Model No. Frame No.
Hp Rpm Cap Size
Tdh Imp Sz Belt No. Cfm
Psi Assy No. Case No.
Misc
Lake Keowee to Adkins WTP Raw Water System Reference Forms
154828 01 99 90 - 8
01 78 23-C. EQUIPMENT RECORD FORM
Equip Descrip Equip Loc
Equip No. Shop Dwg No. Date Inst Cost
Mfgr Mfgr Contact
Mfgr Address Phone
Vendor Vendor Contact
Vendor Address Phone
Maintenance Requirements D W M Q S A Hours
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 9
09 90 00-A COATING SYSTEM INSPECTION CHECKLIST
Project Name
Owner Coating System Manufacturer (CSM)
General Contractor (GC) Coating System Applicator (CSA)
Area or Structure Location within Structure
Coating System (eg E-1) Coating Type (eg Epoxy, etc.)
Coating System Inspection Checklist
Step Description Name Signature Date
1 Completion of cleaning and substrate
decontamination prior to abrasive blast
cleaning.
GC QC
CSM QC
CSA QC
2 Installation of protective enclosure of structure
or area and protection of adjacent surfaces or
structures that are not to be coated.
GC QC
CSM QC
CSA QC
3 Completion of ambient condition control in
structure or building area and acceptance of
ventilation methods in structure or Area.
GC QC
CSM QC
CSA QC
4 Completion of Surface Preparation for
Substrates to Be Coated.
GC QC
CSM QC
CSA QC
5 Completion of Primer Application. GC QC
CSM QC
CSA QC
6 Completion of Concrete Repairs If Required
and Related Surface Preparation Rework Prior
to Coating System Application.
GC QC
CSM QC
CSA QC
7 Completion of Concrete Filler/ Surface
Application to Concrete.
GC QC
CSM QC
CSA QC
8 Completion of First Finish Coat Application and
of Detail Treatment at Transitions or
Terminations.
GC QC
CSM QC
CSA QC
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 10
Coating System Inspection Checklist
Step Description Name Signature Date
9 Completion of Second Finish Coat Application
and of Detail Treatment at Transitions and
Terminations.
GC QC
CSM QC
CSA QC
10 Completion of Full and Proper Cure of Coating
System.
GC QC
CSM QC
CSA QC
11 Completion of Testing of Cured Coating System
including Adhesion, Holiday (Continuity) Testing
and Dry Film Thickness.
GC QC
CSM QC
CSA QC
12 Completion of Localized Repairs to Coating
System Following Testing.
GC QC
CSM QC
CSA QC
13 Final Acceptance of Coating System
Installation Including Final Clean-Up Complying
with Specification Requirements and the
CSM's Quality Requirements.
GC QC
CSM QC
CSA QC
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 11
26 05 00-E. MEDIUM VOLTAGE MOTOR STARTER TEST FORM
Equipment No.:
Location:
Room Temperature:
The protective devices shall be set in accordance with the specification before the tests are
performed.
1. Measure contact resistance (micro-ohms)
Phase: A B C
Contacts shall be replaced if resistance exceeds 50 micro-ohms.
2. Perform an insulation resistance test (1000 volts DC for 1 minute).
Phase A B C
Pole to ground megohms
Across open pole megohms
Pole to pole AB BC CA megohms
3. Perform minimum pickup voltage tests on trip and close coils.
4. Motor RTDs shall be tested by using a hot oil bath. The temperature at which
the sensor trips shall be recorded for each RTD.
5. The Contactor shall be tripped by operation of each protective device.
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 12
26 05 00-F. MEDIUM VOLTAGE SWITCHGEAR TEST FORM
Equipment No.:
Location:
Room Temperature:
The protective devices shall be set in accordance with the specification before the tests are
performed.
1. Measure contact resistance (micro-ohms).
Phase: A B C
Contacts shall be replaced if resistance exceeds 50 micro-ohms.
2. Perform an insulation resistance test (1000 volts DC for 1 minute).
Phase A B C
Pole to ground megohms
Across open pole megohms
Pole to pole AB BC CA megohms
3. Perform minimum pickup voltage tests on trip and close coils.
4. Verify the instrument transformer ratios. Check the transformer’s polarity
electrically.
5. The Contactor shall be tripped by operation of each protective device.
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 13
26 05 00-I. MEDIUM VOLTAGE LOAD INTERRUPTER SWITCH TEST FORM
Equipment Number:
Location:
Date:
1. Measure switch blade resistance (micro-ohms).
Phase: A B C
Contacts shall be replaced if resistance exceeds 50 micro-ohms.
2. Perform an insulation resistance test (1000 volts DC for 1 minute).
Phase A B C
Pole to ground megohms
Across open pole megohms
Pole to pole AB BC CA megohms
The results shall be recorded and signed. A copy shall be given to the Construction Manager in
accordance with paragraph 26 05 00-2.06 Product Data.
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 14
26 05 00-J. LIQUID-FILLED TRANSFORMER TEST FORM
Equipment Number:
Location:
Date/Weather Conditions:
A. Perform the "Insulation-Resistance Test" and "Dielectric Absorption Test" using Form 26
05 00-C, Dry Transformer Test Data Form.
B. Perform an applied voltage (low frequency dielectric) test in accordance with ANSI
C57.12.90, paragraph 10.5, Applied Voltage Test. Applied voltage levels shall be
75 percent of recommended factory test levels or recommended test levels of ANSI
C57.12.00, Table 5.
C. Insulating oil shall be sampled and shall be laboratory tested for the following:
1. Dielectric strength.
2. Acid neutralization.
3. Interfacial tension.
4. Color.
5. Power factor.
D. Perform a turns ratio test between the windings for all tap positions.
E. The temperature and pressure switches shall be tested using a hot oil bath and air
pump.
F. The results shall be recorded and signed by the Contractor and Construction Manager. A
copy shall be given to the Construction Manager in accordance with paragraph 26 05
00-2.06 Product Data. Any readings which are abnormal to ANSI industry standards
shall be reported to the Construction Manager.
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 15
26 05 00-L. NEUTRAL GROUNDING RESISTOR TEST
Equipment No.:
Location:
The pickup and time delay setting on the ground fault relay shall be set in accordance with
Section 26 05 74.
1. The transformer neutral insulation resistance shall be measured with and
without the grounding resistor connected to insure no parallel ground paths
exist.
2. The protective relay pickup current shall be determined by injecting test current
into the current sensor. The pickup current should be within 10 percent of the
dial setting. Record the dial setting and actual pickup tie.
3. The relay timing shall be tested by injecting 150 and 300 percent of pickup
current into the current sensor. The relay timing shall be in accordance with the
manufacturer's published time-current characteristic curves. Record the relay
timing at 150 and 300 percent of pickup current.
4. The circuit interrupting device shall be operated by operating the relay.
The results shall be recorded and signed by the Contractor and Construction Manager. A copy
shall be given to the Construction Manager in accordance with paragraph 26 05 00-2.06 Product Data.
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 16
40 61 13-A. LOOP WIRING AND INSULATION RESISTANCE TEST DATA FORM
Loop No.:
List all wiring associated with a loop in table below. Make applicable measurements as indicated after
disconnecting wiring.
Wire No. Panel Tie Field TB
Continuity Resistancea Insulation Resistanceb
Cond./
Cond. Cond./ Shield
Shield/ Gnd.
Shield/ Cond.
Cond./ Gnd.
Shield/ Shield
A -- (A/SH)
B (A/B) --
C (A/C) --
D (A/D) --
etc.
NOTES:
a. Continuity Test. Connect ohmmeter leads between wires A and B and jumper opposite ends together. Record resistance in table. Repeat procedure between A and C, A and D, etc. Any deviation of +2 ohms between any reading and the average of a particular run indicates a poor conductor, and corrective action shall be taken before continuing with the loop test.
b. Insulation Test. Connect one end of a 500 volt megger to the panel ground bus and the other sequentially to each completely disconnected wire and shield. Test the insulation resistance and record each reading.
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 17
40 61 13-B. CONTROL CIRCUIT PIPING LEAK TEST FORM
Loop No.:
List tubing associated with loop in table below. Make applicable measurements after isolating any air
consuming pilots from circuit.
Tube No.
Tubing Equivalent Length of 1/4-Inch
Coppera Test Period (seconds) Permitted Pressure
Drop (psi)b Measured Pressure
Drop (psi)
A
B
C
D
etc.
NOTES:
a. Convert actual tubing and air motor volume to equivalent 1/4-inch copper tubing.
b. Pressure drop shall not exceed 1 psi per hundred feet 1/4-inch tubing per 5 seconds.
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 18
40 61 13-C. CONTROLLER CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No.:
Input: Process Variable (PV) Scale:
Output: Output Scale:
PV Scale Calibration
% of Range Input Expected Reading Actual Reading % Deviation
0
50
100
% Deviation Allowed:
Connect output to PV for following tests:
Set Point (SP) Indicator Accuracy Output Meter Accuracy Controller Accuracy
SP PV
Reading Expected % Dev.
Actual Reading
Expected Reading
Actual % Dev.
OUTPUT OUTPUT % Dev.
(0%)
(50%)
(100%)
% Deviation Allowed: % Deviation Allowed: % Deviation Allowed:
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 19
40 61 13-D. PANEL INDICATOR CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No.:
Input:
Scale: Range:
PV Scale Calibration
% of Range Input Expected Reading Actual Reading % Deviation
0
50
100
% Deviation Allowed:
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 20
40 61 13-E. RECORDER CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No.:
Input: Chart: ______________________________
Scale: Range: _____________________________
% of Range Input Expected Reading Actual Reading % Deviation
0
50
100
% Deviation Allowed:
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 21
40 61 13-F. SIGNAL TRIP CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No.:
Input:
Scale: Range:
Set Point(s):
After setting set point(s), run signal input through entire range and calculate deadband.
Incr. Input Decr. Input Calc. Required
Set Point Trip Point Trip Point Deadband Deadband
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 22
40 61 13-G. FIELD SWITCH CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No:
Input:
Range:
Set Point(s):
Simulate process variable (flow, pressure, temperature, etc.) and set desired set point(s). Run through
entire range of switch and calculate deadband.
Incr. Input Decr. Input Calc. Required
Set Point Trip Point Trip Point Deadband Deadband
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 23
40 61 13-H. TRANSMITTER CALIBRATION TEST DATA FORM
Tag No. and Description:
Make & Model No.: Serial No.:
Input:
Output:
Range: Scale:
Simulate process variable (flow, pressure, temperature, etc.) and measure output with appropriate
meter.
% of Range Input Expected Reading Actual Reading % Deviation
0
50
100
% Deviation Allowed:
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 24
40 61 13-I. MISCELLANEOUS INSTRUMENT CALIBRATION TEST DATA FORM
(For instruments not covered by any of the preceding test forms, the Contractor shall create a form
containing all necessary information and calibration procedures.)
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 25
40 61 13-J. INDIVIDUAL LOOP TEST DATA FORM
Loop No.:
Description: (Give complete description of loop's function using tag numbers where appropriate.)
P&ID No.: (Attach copy of P&ID.)
a. Wiring tested:
(Attach test form 40 61 13-A)
b. Instrumentation tubing/piping tested:
(Attach test form 40 61 13-B)
c. Instruments calibrated:
(Attach test forms 40 61 13-C through I)
d. List step-by-step procedures for testing loop parameters. Test loop with instruments,
including transmitters and control valves, connected and functioning. If it is not possible
to produce a real process variable, then a simulated signal may be used with the
Construction Manager's approval.
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
Mauldin Rd Wet Weather PS Reference Forms
149439 01 99 90 - 27
40 61 13-K. LOOP COMMISSIONING TEST DATA FORM
Loop No.:
a. Loop tested:
(Attach test form 40 61 13-J)
b. Controlled or connected equipment tests confirmed:
c. Give complete description of loop's interface with process.
d. With associated equipment and process in operation, provide annotated chart trace of
loop response to changes in set points for verification of performance. This chart should
demonstrate 1/4-amplitude damping as output adjusts to set point change. Show set
points, starting and finishing times on chart, as well as any other pertinent data.
Connect 2-pen recorder to process variable (PV) and to controller output. Use
1 inch/second chart speed.
Pen 1 - PV - Connections:
Pen 2 - Output - Connections:
CERTIFIED Date
Contractor's Representative
WITNESSED Date
Owner's Representative
DIVISION 03
CONCRETE
Section Title
03 11 00 CONCRETE FORMING
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 48 11 PRECAST CONCRETE VAULTS
03 60 00 GROUTING
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 1
SECTION 03 11 00
CONCRETE FORMING
PART 1 GENERAL
1.01 DESCRIPTION
A. Formwork requirements for concrete construction.
1.02 QUALITY ASSURANCE
A. References:
1. The references listed below are part of this section. Where a referenced document
cites other standards, such standards are included as references under this section
as if referenced directly. In the event of conflict, the requirements of this section shall
prevail.
Reference Title
ACI 117 Tolerances for Concrete Construction and Materials
ACI 301 Specifications for Structural Concrete
ACI 318 Building Code Requirements for Structural Concrete
National Institute of
Standards - PS1
Construction and Industrial Plywood
B. Design – General:
1. Provide design of formwork, shoring and reshoring systems by the Contractor’s
Professional Engineer currently registered in the State of South Carolina.
2. Design, engineering, and construction of formwork, shoring, and reshoring systems is
the responsibility of the Contractor.
3. Develop a procedure and schedule for removal of shores (and installation of
reshores).
4. Structural record calculations, signed and sealed by the Contractor’s Engineer, are
required to prove that all portions of the structure, in combination with the remaining
forming and shoring systems, have sufficient strength to safely support their own
weight plus the loads placed thereon.
5. When developing procedures, schedules, and structural calculations; consider the
structural system that exists, effects of imposed loads, and the strength of concrete
at each stage of construction.
C. Design Criteria:
1. Design formwork in accordance with ACI 301 and ACI 318 for building structures and
ACI 350 and 350.5 for environmental structures to provide concrete finishes as
specified in Section 033000.
2. Design systems for full height of wet concrete pressure.
3. Design formwork to limit maximum deflection of form facing materials, as reflected in
concrete surfaces exposed to view, to 1/240 of span.
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 2
1.03 SUBMITTALS
A. Action Submittals:
1. Procedures: Section 01 33 00.
2. Manufacturer's product data with installation instructions:
a. Form materials.
b. Form ties (with waterstops).
c. Form release compound.
d. Void forms.
B. Informational Submittals:
1. Procedures: Section 01 33 00.
2. Letter of certification:
a. Stating that formwork has been designed in accordance with this specification
and referenced documents, sealed and stamped by the Contractor’s registered
design Engineer.
PART 2 PRODUCTS
2.01 FORMS
A. Wood Forms:
1. Provide new and unused exterior grade plywood panels manufactured in accordance
with American Plywood Association (APA) and bearing the trademark of that group.
a. Forms for concrete surfaces exposed to view: use APA High Density Overlay (HDO)
Plyform Class I Exterior 48" X 96" X 3/4".
b. Forms for other concrete surfaces: use APA Douglas Fir B-B Plyform Class I
Exterior 48” X 96” X 3/4-inch.
2. When approved, plywood may be reused.
B. Metal Forms:
1. Do not use aluminum. Provide forms free of rust and straight without dents to provide
members of uniform thickness.
2.02 FORM TIES
A. Commercially fabricated for use in form construction. Fabricated so that ends or end
fasteners can be removed without causing spalling at surfaces of the concrete. Cone on
ends shall be 3/4 inch to 1 inch diameter. Provide embedded portion of tie not less than
1 1/2 inch from face of concrete after cone ends have been removed. Provide ties with
integral waterstops at water-retaining and below grade structures.
B. Tapered through-bolts may be used when approved. Use 1-inch minimum diameter at the
smallest end. Fill tapered tie holes after cleaning to produce watertight construction. Use
a mechanical waterstop plug near the center of the wall and fill each side with non-shrink
cement grout. Mechanical waterstop plug shall be Greenstreak Group, Inc. “X-Plug”; or
equal.
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 3
2.03 FORM RELEASE COMPOUND
A. Coat form surfaces in contact with concrete using a non-staining, non-residual, water
based, bond-breaking form coating. [Use NSF approved form release agents in potable
water containment structures.]
PART 3 EXECUTION
3.01 PREPARATION
A. Cover surface of forms with form release compound prior to form installation in
accordance with manufacturer’s recommendations.
B. Do not permit excess form coating material to stand in puddles on forms or hardened
concrete surfaces against which fresh concrete is to be placed.
C. Clean surfaces of forms, reinforcing steel and other embedded items of accumulated
mortar, grout, or other foregn materials from previous concreting or construction
activities before concrete is placed.
3.02 FORMWORK CONSTRUCTION
A. Form vertical surfaces of cast-in-place concrete including sides of footings.
B. Construct and place forms so that the resulting concrete will be of the shape, lines,
dimensions, and appearance indicated on the Drawings. Brace or tie forms together to
maintain position and shape under the load of freshly-placed concrete.
C. Tighten forms to prevent leakage.
D. Provide temporary openings(windows) at base of column and wall forms and at other
points where necessary to facilitate cleaning and observation immediately before
concrete is placed.
E. Provide temporary openings to limit height of free fall of concrete and to limit the lateral
movement of concrete during placement. Openings are required in wall placements
greater than 20 feet in height, spaced no more than 8 feet on center measured
horizontally and vertically.
F. Place a 3/4-inch chamfer strip at exposed to view corners of formed surfaces.
G. At construction joints,overlap hardened concrete surface by at least 1 inch. Brace forms
against hardened concrete to prevent movement, offsets, or loss of mortar at
construction joint and to maintain a true surface. Where possible, locate juncture of built-
in-place forms at architectural lines, control joints, or at other inconspicuous lines.
H. [Where circular sections are formed using flat faced materials, use flat form lengths not
exceeding 2 feet wide and the resulting deflection angles at the joints is not greater than
3-1/2 degrees.
I. Construct wood forms for openings to facilitate loosening. Anchor forms so that
movement of any part of the formwork system is prevented during concrete placement.
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 4
J. At platforms constructed to move equipment over in-place reinforcment, provid beams,
struts, and/or legs, supported directly on formwork or other structural members without
resting on reinforcing steel.
K. Provide a positive means of adjustment (wedges or jacks) at shores and struts to take up
settlement during concrete placement. Brace forms against lateral deflection. Fasten in-
place wedges and shims used for final adjustment of forms prior to concrete placement.
L. Place tapered through-bolt form ties with the larger end on the side of the structure in
contact with liquid.
3.03 TOLERANCES
A. Install formwork with tolerances in accordance with ACI 117 and the following (the more
stringent requirement controls):
1. Install formwork in accordance with manufacturer’s written instructions.
2. Vertical surface tolerance from plumb; walls, columns, piers, and risers:
1/2 inch for entire height
1/4 inch in any 10 feet of height
3. Vertical surface tolerance from plumb; exposed wall corners, end columns, control-
joint grooves, and other exposed to view vertical lines:
1/2 inch for entire height
1/4 inch in any 20 feet of height
4. Horizontal variation from level or from grade; top of slabs, slab soffits, ceilings, and
beam soffits, measured before removal of supporting shores:
3/4 inch for entire length
3/8 inch for any bay or 20 foot length
1/4 inch in any 10 feet of length
5. Horizontal variation from level or from grade; exposed lintels, sills, parapets,
horizontal grooves, and other exposed-to-view horizontal lines:
1/2 inch for entire length
1/4 inch in any 20 feet of length.
6. Plan position variation; columns, walls, and partitions:
3/4 inch for entire length
3/8 inch for any bay or 20 foot length
7. Plan location and size; sleeves, floor openings, walls, wall openings, beams, and
columns:
1/2 inch
8. Cross sectional dimensions; columns and beams and thickness of slabs and walls:
3/8 inch
9. Plan dimensions; footings and foundations:
minus 1/2 inch
+ 2 inches
10. Misplacement or eccentricity; footings and foundations:
2 percent of footing width in direction of misplacement
not more than 2 inches
11. Thickness; footings and foundations:
minus 5 percent
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 5
no limit on the maximum increase except that which may interfere with other
construction.
12. Step variance in flight of stairs:
Rise 1/16 inch
Tread from level 1/8 inch
B. Use control points and benchmarks for reference purposes to check tolerances.
Establish and maintain reference points in an undisturbed condition until final
completion and acceptance of the work.
C. Regardless of tolerances listed, no portion of a structure shall extend beyond the legal
boundary of work site.
D. Camber formwork to compensate for anticipated deflections in formwork under wet load
of concrete. Adjust camber to maintain above specified tolerances in hardened concrete
after forms and shoring are removed.
3.04 REMOVAL OF FORMS
A. Do not impose construction loads or remove shoring from any part of the structure until
that portion of the structure in combination with remaining forming and shoring systems
has sufficient strength to safely support its weight and loads placed thereon.
B. If forms are loosened and not removed, proceed same day with wet curing operations to
soak surfaces of concrete where forms are loosened. When wet curing is not practical or
not planned, loosen, remove, and start approved curing proceedures on the same day.
C. When required for concrete curing in hot weather, required for repair of surface defects,
or when required for finishing at an early age; remove forms as soon as concrete has
hardened sufficiently to resist damage from removal operations or lack of support.
D. Remove top forms on sloping surfaces as soon as concrete has attained sufficient
stiffness to prevent sagging. Make repairs or finishing treatment on such sloping
surfaces immediately after form removal.
E. Remove wood forms for wall openings as soon as this can be accomplished without
damage to concrete.
F. Remove formwork from columns, walls, sides of beams, and other parts not supporting
weight of concrete as soon as concrete has hardened sufficiently to resist damage from
removal.
G. When shores and supports are so arranged such that non-load-carrying form facing
material can be removed without loosening or disturbing other shores and supports,
facing material may be removed when concrete has sufficiently hardened to resist
damage from removal.
H. In all cases, proceed with curing same day as form removal.
I. Where no reshoring is planned, forms and shoring used to support weight of concrete
shall be left in place until concrete has attained its specified 28-day compressive
strength.
Lake Keowee to Adkins WTP Raw Water System Concrete Forming
154828 03 11 00 - 6
3.05 RESHORING
A. Do not impose construction loads or remove shoring from any part of the structure until
that portion of the structure, in combination with remaining forming and shoring systems,
has sufficient strength to safely support its weight and loads placed thereon.
B. While reshoring is underway, no superimposed dead or live loads are permitted on the
new construction.
C. During reshoring, do not subject concrete in structural members to combined dead and
construction loads in excess of loads that the structural members can adequately
support.
D. Place reshores as soon as practicable after stripping operations are complete, but in no
case later than the end of working day on which stripping occurs.
E. Place reshores to carry their required loads without overstressing.
F. Where a reshoring procedure is planned, supporting formwork may be removed when
concrete has reached the concrete strength specified by the formwork engineer’s
structural calculations and verified by field cured test cylinders or other approved
method.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 1
SECTION 03 20 00
CONCRETE REINFORCING
PART 1 GENERAL
1.01 DESCRIPTION
A. Section includes: Reinforcing steel for use in reinforced concrete.
1.02 REFERENCES:
A. The references listed below are a part of this section. Where a referenced document
contains references to other standards, those documents are included as references
under this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of this
section shall prevail.
Reference Title
ACI 117 Specification for Tolerances for Concrete Construction and Materials
ACI 315 Details and Detailing of Concrete Reinforcement
ACI 318 Building Code Requirements For Structural Concrete
ACI SP-66 ACI Detailing Manual
ASTM A615 Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706 Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A775 Epoxy-Coated Steel Reinforcing Bars
ASTM A884 Epoxy-Coated Steel Wire and Welded Wire Reinforcement
ASTM A1064 Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for
Concrete
AWS D1.4 Structural Welding Code - Reinforcing Steel
CRSI-PRB Placing Reinforcing Bars
CRSI-MSP Manual of Standard Practice
FEDSPEC QQ-W-461H Wire, Steel, Carbon (Round, Bare, and Coated)
1.03 SUBMITTALS
A. Action Submittals
1. Procedures: Section 01 33 00.
2. A copy of this specification section with each paragraph check-marked to indicate
specification compliance or marked to indicate requested deviations from
specification requirements.
3. Check-marks (✓) shall denote full compliance with a paragraph as a whole.
Deviations shall be underlined and denoted by a number in the margin to the right of
the identified paragraph. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Include a
detailed, written justification for each deviation. Failure to include a copy of the
marked-up specification sections, along with justification(s) for any requested
deviations to the specification requirements, with the submittal shall be sufficient
cause for rejection of the entire submittal with no further consideration.
4. Mill certificates for all reinforcing.
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 2
5. Manufacturer and type of proprietary reinforcing steel splices. Submit a current ICC
Report and manufacturer’s literature that contains instructions and
recommendations for each type of coupler used.
6. Qualifications of welding operators, welding processes and procedures.
7. Reinforcing steel shop drawings showing reinforcing steel bar quantities, sizes,
spacing, dimensions, configurations, locations, mark numbers, lap splice lengths and
locations, concrete cover and reinforcing steel supports. Reinforcing steel shop
drawings shall be of sufficient detail to permit installation of reinforcing steel without
reference to the contract drawings. Shop drawings shall not be prepared by
reproducing the plans and details indicated on the contract drawings but shall
consist of completely redrawn plans and details as necessary to indicate complete
fabrication and installation of reinforcing steel, including large scale drawings at
joints detailing bar placement in congested areas. Placement drawings shall be in
accordance with ACI 318. Reinforcing details shall be in accordance with ACI SP-66.
1.04 DELIVERY, STORAGE AND HANDLING
A. Ship reinforcing steel to the jobsite with attached plastic or metal tags having permanent
mark numbers which match the shop drawing mark numbers. All reinforcing shall be
supported and stored above ground. Use only plastic tags secured to the reinforcing steel
bars with nylon or plastic tags for epoxy coated reinforcing steel bars.
PART 2 PRODUCTS
2.01 BAR REINFORCEMENT
A. Reinforcing steel bars shall be deformed billet steel in conformance with ASTM A615,
Grade 60. Bars to be welded shall be deformed billet steel conforming to ASTM A706.
Where specified, reinforcing steel shall be epoxy-coated in conformance with ASTM
A775.
2.02 WIRE FABRIC
A. Wire fabric shall be welded steel mesh conforming to ASTM A1064.
2.03 WIRE AND PLAIN BARS
A. Wire used as reinforcement and bars used as spiral reinforcement in structures shall be
cold drawn steel conforming to ASTM A1064.
2.04 SMOOTH DOWEL BARS
A. Smooth dowel bars shall conform to ASTM A615, Grade 60, with a metal end cap at the
greased or sliding end to allow longitudinal movement.
2.05 EPOXY COATED BARS
A. Epoxy coated bars shall conform to ASTM A775 and ASTM A884.
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 3
2.06 EPOXY COATED REINFORCING STEEL BAR PATCHING MATERIAL
A. Epoxy coated reinforcing steel bar patching material shall be compatible with coating
material, inert in concrete, obtained from manufacturer of the epoxy resin used to coat
the reinforcing steel bars and meet the requirements of ASTM A775.
2.07 REINFORCING STEEL MECHANICAL SPLICES
A. Reinforcing steel mechanical splices shall be a positive connecting threaded type
mechanical splice system manufactured by Erico, Inc., Dayton Superior, Williams Form
Engineering Company, or approved equal.
B. Type 1 mechanical splices shall develop in tension or compression a strength of not less
than 125 percent of the ASTM specified minimum yield strength of the reinforcement
and shall meet all other ACI 318 requirements. Type 1 mechanical splices are typical
except for locations noted below where Type 2 mechanical splices are required.
2.08 TIE WIRE
A. The wire shall be minimum 16 gage annealed steel conforming to FEDSPEC QQ-W-461H.
2.09 BAR SUPPORTS
A. Bar supports coming into contact with forms shall be CRSI Class 1 plastic protected or
Class 2 stainless steel protected and shall be located in accordance with CRSI-MSP and
placed in accordance with CRSI-PRB.
B. Provide manufactured concrete block supports with embedded tie wires (wire dobies) for
footing and slabs on grade. Do not use brick, broken concrete masonry units, spalls,
rocks, construction debris, or similar material for supporting reinforcing steel.
C. Provide stainless steel or plastic protected plain steel supports for other work.
2.10 FABRICATION:
A. Fabricate reinforcing steel bars in accordance with ACI 318 and the following tolerances:
1. Sheared lengths: +/-1 inch.
2. Overall dimensions of stirrups, ties, and spirals: +/-1/2 inch.
3. All other bends: +0 inch, -1/2 inch
4. Minimum diameter of bends of reinforcing steel bars: Per ACI 318.
PART 3 EXECUTION
3.01 PLACEMENT TOLERANCE
A. Reinforcing steel placement tolerance shall conform to the requirements of ACI 117, ACI
318, and the following:
1. Reinforcing steel bar clear distance to formed surfaces shall be within +/-1/4 inch of
specified clearance and minimum spacing between bars shall be a maximum of
1/4 inch less than specified.
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 4
2. Reinforcing steel top bars in slabs and beams shall be placed +/-3/8 inch of
specified depth in members 8 inches deep or less and +/-1/2 inch of specified depth
in members greater than 8 inches deep.
3. Reinforcing steel spacing shall be placed within +/- one bar diameter or +/- 1 inch,
whichever is greater.
4. The minimum clear distance between reinforcing steel bars shall be equal to the
greater of 1 inch or the reinforcing steel bar diameter for beams, walls and slabs, and
the greater of 1 1/2 inches or 1.5 times the reinforcing steel bar diameter for
columns.
5. Beam and slab reinforcing steel bars shall be threaded through column vertical
reinforcing steel bars without displacing the column reinforcing steel bars and still
maintain clear distances for beam and slab reinforcing steel bars.
3.02 CONCRETE COVER
A. Unless specified otherwise on the Drawings, reinforcing steel bar cover shall conform to
the following:
1. Reinforcing steel bar cover shall be 3 inches for concrete cast against earth.
2. Reinforcing steel bar cover shall be 2 inches for reinforcing steel bars for formed
concrete surfaces exposed to earth and weather.
3. Reinforcing steel bar cover shall be 2 inches for any formed surfaces exposed to or
above any liquid.
4. Reinforcing steel bar cover shall be 1 ½ inches for reinforcing not in the above
categories unless noted otherwise on the design drawings.
3.03 SPLICING
A. Reinforcing steel splicing shall conform to the following:
1. Use Class B splice lengths in accordance with ACI 318 for all reinforcing steel bars
unless shown otherwise on the drawings.
2. For welded wire fabric the splice lap length measured between the outermost cross
wires of each fabric sheet shall not be less than one spacing of cross wires plus 2
inches, nor less than 1.5 times the development length nor less than 6 inches.
3. Splices of reinforcement steel bars not specifically indicated or specified shall be
subject to the approval of the Owner’s Representative. Mechanical proprietary splice
connections may be used when approved by the Owner’s Representative or as
indicated on the drawings per manufacturer’s instructions.
4. Welding of reinforcing steel bars is not allowed unless approved by the Owner’s
Representative.
3.04 CLEANING
A. Reinforcing steel bars at time of concrete placement shall be free of mud, oil, loose rust,
or other materials that may affect or reduce bond. Reinforcing steel bars with rust, mill
scale or a combination of both may be accepted without cleaning or brushing provided
dimensions and weights including heights of deformation on a cleaned sample are not
less than required by applicable ASTM standards.
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 5
3.05 PLACEMENT
A. Reinforcing steel bar placement shall conform to the following:
1. Uncoated reinforcing steel bars shall be supported and fastened together to prevent
displacement by construction loads or concrete placement. For concrete placed on
ground, furnish concrete block supports or metal bar supports with non-metallic
bottom plates. For concrete placed against forms furnish plastic or plastic coated
metal chairs, runners, bolsters, spacers and hangers for the reinforcing steel bar
support. Only tips in contact with the forms require a plastic coating.
2. Fasten coated reinforcing steel bars together to prevent displacement. Use plastic or
nylon ties to hold the coated reinforcing steel bars rigidly in place. Support coated
reinforcing steel bars with plastic or plastic coated chairs, runners, bolsters, spacers
and supports as required.
3. Support reinforcing steel bars over cardboard void forms by means of concrete
supports which will not puncture or damage the void forms nor impair the strength of
the concrete member.
4. Where parallel horizontal reinforcement in beams is indicated to be placed in two or
more layers, reinforcing steel bars in the upper layers shall be placed directly over
the reinforcing steel bars in the bottom layer with the clear distance between each
layer to be 2 inches unless otherwise noted on the Drawings. Place spacer
reinforcing steel bars at a maximum of 3’-0” on center to maintain the minimum
clear spacing between layers.
5. Extend reinforcement to within 2 inches of formed edges and 3 inches of the
concrete perimeter when concrete is placed against earth.
6. Reinforcing steel bars shall not be bent after embedding in hardened concrete unless
approved by the Owner’s Representative.
7. Tack welding or bending reinforcing steel bars by means of heat is prohibited.
8. Where required by the contract documents, reinforcing steel bars shall be embedded
into the hardened concrete utilizing an adhesive anchoring system specifically
manufactured for that application. Installation shall be per the manufacturer’s
written instructions.
9. Bars with kinks or with bends not shown shall not be used.
10. Heating or welding bars shall be performed in accordance with AWS D1.4 and shall
only be permitted where specified or approved by the Owner’s Representative. Bars
shall not be welded at the bend.
3.06 REPAIR OF EPOXY COATING
A. Epoxy coating damage need not be repaired in cases where the damaged area is 0.1
square inch or smaller. Repair all damaged areas larger than 0.1 square inch in
conformance with ASTM A775.
3.07 FIELD QUALITY CONTROL
A. Field quality control shall include the following:
1. Notify the Owner’s Representative whenever the specified clearances between the
reinforcing steel bars cannot be met. The concrete shall not be placed until the
Contractor submits a solution to the congestion problem and it has been approved by
the Owner’s Representative.
Lake Keowee to Adkins WTP Raw Water System Concrete Reinforcing
154828 03 20 00 - 6
2. The reinforcing steel bars may be moved as necessary to avoid other reinforcing steel
bars, conduits or other embedded items provided the tolerance does not exceed that
specified in this section. The Engineer’s approval of the modified reinforcing steel
arrangement is required where the specified tolerance is exceeded. No cutting of the
reinforcing steel bars shall be done without written approval of the Owner’s
Representative.
3. An independent laboratory will be employed to review and approve reinforcing steel
bar placement for correct materials, fabrication, sizes, locations, spacing, concrete
cover, and splicing.
4. Coated reinforcing steel bars will be inspected on the jobsite for handling defects,
coating abrasion, coating thickness and continuity of coating. The Owner’s
Representative may defer final inspection of the coated reinforcing steel bars until
bar erection and handling is complete. Repair coated areas as directed by the
Owner’s Representative and completed prior to concrete placement.
5. An independent laboratory shall be employed to review and approve Contractor
welding procedures and qualify welders in accordance with AWS D1.4. The laboratory
shall visually inspect each weld for visible defects and conduct non-destructive field
testing (radiographic or magnetic particle) on not less than one sample for each 10
welds. If a defective weld is found, the previous 5 welds by the same welder shall
also be tested.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 1
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Cast-in-place concrete, which consists of providing material, mixing,
transporting equipment, and labor for the proportioning, mixing, transporting, placing,
consolidating, finishing, curing, and protection of concrete in the structure.
1.02 RELATED SECTIONS
A. This section contains specific references to the following related specification sections.
Additional related sections may apply that are not specifically listed below.
1. Section 03 60 00 Grouting
2. Section 07 91 26 Joint Fillers
3. Section 07 92 00 Joint Sealants
4. Section 09 90 00 Painting and Coating
1.03 REFERENCES:
A. The references listed below are a part of this section. Where a referenced document
contains references to other standards, those documents are included as references
under this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of this
section shall prevail.
Reference Title
ACI 117 Tolerances for Concrete Construction and Materials
ACI 211.1 Selecting Proportions for Normal, Heavy Weight and Mass Concrete
ACI 301 Specifications for Structural Concrete
ACI 305.1 Specification for Hot Weather Concreting
ACI 306.1 Standard Specification for Cold Weather Concreting
ACI 214R Guide to Evaluation of Strength Test Results in Concrete
ACI 318 Building Code Requirements for Structural Concrete
ACI 350 Code Requirements for Environmental Engineering Concrete Structures
ACI 350.1 Tightness Testing of Environmental Engineering Concrete Containment Structures
ACI 503.7 Crack Repair by Epoxy Injection
ASTM C31 Making and Curing Concrete Test Specimens in the Field
ASTM C33 Concrete Aggregates
ASTM C39 Compressive Strength of Cylindrical Concrete Specimens
ASTM C42 Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C94 Ready-Mixed Concrete
ASTM C117 Materials Finer Than 75-m (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C131 Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the
Los Angeles Machine
ASTM C136 Sieve Analysis of Fine and Coarse Aggregates
ASTM C143 Slump of Hydraulic Cement Concrete
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 2
Reference Title
ASTM C150 Portland Cement
ASTM C157 Length Change of Hardened Cement Mortar and Concrete
ASTM C172 Sampling Freshly Mixed Concrete
ASTM C192 Making and Curing Concrete Test Specimens in the Laboratory
ASTM C231 Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260 Air-Entraining Admixtures for Concrete
ASTM C309 Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C494 Chemical Admixtures for Concrete
ASTM C595 Blended Hydraulic Cements
ASTM C618 Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C881 Epoxy-Resin-Base Bonding Systems for Concrete
ASTM C989 Slag Cement for use in Concrete and Mortars
ASTM C1059 Latex Agents for Bonding Fresh to Hardened Concrete
ASTM C1260 Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C1315 Liquid Membrane-Forming Compounds for Curing and Sealing Concrete
ASTM C1567 Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate
ASTM C1602 Mixing Water Used in the Production of Hydraulic Cement Concrete
ASTM D75 Sampling Aggregates
ASTM D2419 Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate
ASTM E329 Agencies Engaged in Construction Inspection and/or Testing
ASTM E1643 Standard Practice for Selection, Design, Installation and Inspection of Water Vapor
Retarders Used in Contact with Earth or Granular Fill under Concrete Slabs.
ASTM E1745 Standard Specification for Plastic Water Vapor Retarders Used in Contact with Soil or
Granular Fill under Concrete Slabs.
CRD-C572 U.S. Corps of Engineer’s Specifications for Polyvinylchloride Waterstop
IBC International Building Code with local amendments
1.04 SUBMITTALS
A. Action Submittals:
1. Procedures: Section 01 33 00.
2. A copy of this specification section with each paragraph check-marked to indicate
specification compliance or marked to indicate requested deviations from
specification requirements.
3. Check-marks (✓) denote full compliance with a paragraph as a whole. Deviations
shall be underlined and denoted by a number in the margin to the right of the
identified paragraph. The remaining portions of the paragraph not underlined signify
compliance with the specification. Include a detailed, written justification for each
deviation. Failure to include a copy of this marked-up specification section, along with
justification(s) for requested deviations, with the submittal, is cause for rejection of
the entire submittal with no further consideration.
4. Each proposed mix design showing:
a. Expected strength at 7 and 28-days
b. Slump, before and after introduction of high-range water-reducing admixture
c. Water/cement ratio
d. Weights and test results of the ingredients
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 3
e. Aggregate gradation
f. Test results of mix design prepared by an independent testing laboratory
g. Shrinkage test results for liquid containing structures
h. Other physical properties necessary to review each mix design for conformance
with these specifications
5. Mix designs proposed shall be sealed by a Professional Engineer registered in the
state where the project is located.
6. Product literature and technical data for aggregates, cement, and pozzolan.
7. Product literature, technical data, and dosage of proposed admixtures including, but
not limited to, air entraining, water reducing, retarding, shrinkage reducing, etc.
8. Anticipated average delivery time from batch plant to site. If this time exceeds the
limit specified in Part 3, include proposed method to extend set time without
deleterious effects on final product. Owner’s Representative reserves the right to
accept or reject such proposed methods.
9. Lift Drawings: Submit shop drawings for concrete placements on the project before
on-site construction begins. The drawings shall be organized by structure and
submitted as a complete set for the Engineer’s review. The drawings shall be drawn
to scale and show dimensions, forming details, and placement volumes. Show
location of construction joints, details of surface preparation, scheduled finish,
embedments, penetrations, openings, keyways, blockouts, bulkheads, etc. The
drawings shall clearly show the placement sequence and will be accompanied by a
schedule that shows the schedule dates for forming, placement, and stripping for
each section of concrete placed within each structure.
10. Curing program description in sufficient detail to demonstrate that the Contractor will
provide acceptable strength, finish, and crack control within the completed structure.
11. Product literature and technical data for waterstops, curing and sealing compounds,
bonding compounds, surface hardeners, and epoxy and chemical grout for crack
injection.
12. Sample panels to demonstrate formed wall surface finishes as specified in Part 3.
13. Samples of concrete floor and slab finishes as specified in Part 3.
14. Concrete delivery truck tickets showing the information listed in ASTM C94,
section 14.
1.05 QUALITY ASSURANCE
A. Quality Control By Owner:
1. Special Inspection of concrete work shall be performed by the Special Inspector
under contract with the Owner and in conformance with the IBC Chapter 17. Special
Inspection of concrete is in addition to, not replacing, other inspections and quality
control requirements specified herein. Where sampling and testing specified herein
conforms to Special Inspection standards, such sampling and testing need not be
duplicated.
2. All structural concrete work shall receive Special Inspection in accordance with IBC
Chapter 17. Structural concrete includes elements which resist code-defined loads
and whose failure would impact life safety. Non-structural site work concrete does
not require Special Inspection. Anchor bolts and anchors installed in hardened
concrete require Special Inspection.
3. Refer to Section 01 45 00 Quality Control, for Owner provided testing.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 4
B. Quality Control By Contractor:
1. Where required to demonstrate conformance with the specified requirements for
cast-in-place concrete, the Contractor shall provide the services of an independent
testing laboratory which complies with the requirements of ASTM E329. The testing
laboratory shall sample and test concrete materials as specified in this section. Costs
of testing laboratory services shall be borne by the Contractor.
C. Basis For Quality:
1. Cast-in-place concrete shall conform to the requirements of ACI 301, except as
modified herein.
PART 2 PRODUCTS
2.01 MATERIALS
A. Cement:
1. Portland cement shall be ASTM C150, Type II or Type V, low alkali, containing less
than 0.60 percent alkalis. In addition to standard requirements, cement shall satisfy
optional chemical and physical requirements of ASTM C150, Tables 2 and 4,
respectively.
2. If low alkali cement is not available, aggregates shall show an expansion of less than
0.1% when tested in accordance with ASTM C1260 or ASTM C1567 concrete mix test
results shall be submitted verifying that the aggregates are not reactive per the
criteria in this standard. ASTM C1260 and ASTM C1567 results shall be no older
than 1 year.
3. Portland-pozzolan cement shall be ASTM C595, Type IP (MS), interground, low alkali.
4. Use cementitious materials that are of the same brand and type and from the same
plant of manufacture as the cementitious materials used in the concrete represented
by the submitted field test records or used in the trial mixtures. See Change of
Materials paragraph below.
B. Ground granulated blast-furnace slag (GGBFS), if used in conjunction with portland
cement, shall be per ASTM C989.
C. Aggregates:
1. General:
a. Except as modified herein, fine and coarse aggregates shall conform to ASTM
C33. Fine and coarse aggregates are regarded as separate ingredients.
Aggregates shall be non-reactive and washed before use.
b. Check aggregates for alkali-silica reactive constituents per ASTM C1260.
Aggregate shall have less than 0.1% expansion when tested in accordance with
ASTM C1260. Aggregates having 0.1% or greater expansion may still be
satisfactory provided ASTM C1567 concrete mix test results are submitted and
show an expansion of less than 0.1% at 16 days. Test results shall be no older
than 1 year.
c. Tests for size and grading of fine and coarse aggregates shall be in accordance
with ASTM C136. Combined aggregates shall be well and uniformly graded from
coarse to fine sizes to produce a concrete that has optimum workability and
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 5
consolidation characteristics. Establish the final combined aggregate gradation
during mix design.
d. Aggregates used in the project production concrete shall be obtained from the
same sources and have the same size ranges as the aggregates used in the
concrete represented by the submitted historical data or trial mixtures. See
Change of Materials paragraph below.
2. Fine Aggregate:
a. Fine aggregate shall be hard, dense, durable particles of either sand or crushed
stone regularly graded from coarse to fine. Gradation shall conform to ASTM C33.
For classes of concrete which will be used in liquid retaining structures, fine
aggregate shall not exceed 40 percent by weight of combined aggregate total,
except for concrete with coarse aggregate of less than maximum size 1/2 inch.
b. Variations from the specified gradations in individual tests will be acceptable if
the average of three consecutive tests is within the specified limits and the
variation is within the permissible variation listed below:
U.S. standard sieve size Permissible variation in individual tests, percent
30 and coarser 2
50 and finer 0.5
c. Other tests shall be in accordance with the following specifications:
Test Test method Requirements
Amount of material ASTM C117 3 percent passing No. 200 sieve maximum by weight
Sand equivalent ASTM D2419 Minimum 70 percent
3. Coarse Aggregate:
a. Coarse aggregate shall be hard, dense and durable gravel or crushed rock free
from injurious amounts of soft and friable particles, alkali, and organic matter.
Other deleterious substances shall not exceed the limits listed in ASTM C33,
Table 3 for Class Designation 5S. Gradation of each coarse aggregate size
specified shall conform to ASTM C33, Table 2.
b. Variations from the specified gradations will be acceptable in individual tests if
the average of three consecutive tests is within the specified limits.
D. Pozzolan:
1. Pozzolan shall be Class F fly ash conforming to ASTM C618. Class C fly ash is not
allowed. Pozzolan supplied during the life of the project shall have been formed at
the same single source. See Change of Materials paragraph below.
2. The pozzolan color shall not substantially alter the resulting concrete from the normal
gray color and appearance.
3. Use pozzolan materials that are of the same brand and type and from the same plant
of manufacture as the materials used in the concrete represented by the submitted
field test records or used in the trial mixtures.
E. Admixtures:
1. General:
a. Admixtures shall be compatible with the concrete and with each other. Calcium
chloride or admixtures containing calcium chloride are not acceptable. Use
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 6
admixtures in accordance with the manufacturer's recommendations and add
separately to the concrete mix. Water reducing retarders and admixtures shall
reduce the water required by at least 11 percent for a given concrete consistency
and shall comply with the water/cement ratio standards of ACI 211.1. Retarder
dosage shall result in set time consistent with requirements specified in Part 3.
2. Water Reducing Admixtures:
a. Conform to ASTM C494, Type A. Acceptable products include: BASF
“MasterPozzolith 322”; SIKA Chemical Corp. “Plastocrete 161”; Euclid Chemical
Co. “Eucon WR 91”; or approved equal.
3. Water Reducing and Retarding Admixtures:
a. Conform to ASTM C494, Type D. Acceptable products include: BASF
“MasterPozzolith 80”; Sika Chemical Corp. “Plastiment”; Euclid Chemical Co.
“Eucon Retarder 75”; or approved equal.
4. High Range Water Reducing (Superplasticizing) Admixtures:
a. Conform to ASTM C494, Type F. Acceptable products include: BASF
“MasterGlenium” Series; Sika Chemical Corp. “Viscocrete 2100” or “Viscocrete
2110” (Hot Weather) or “Viscocrete 6100” (Cold Weather); Euclid Chemical Co.
“Eucon 37”; W.R. Grace “ADVA 195”; or approved equal.
5. High Range Water Reducing And Retarding Admixtures:
a. Conform to ASTM C494, Type G. Acceptable products include: W.R. Grace
“Daracem 100”; Sika Chemical Corp. “Sikaplast 200” ; Euclid Chemical Co.
“Eucon 537”; or approved equal.
6. Air Entraining Agent:
a. Conform to ASTM C260 and produce air entrained concrete as specified in the
Mix Proportioning table below. Acceptable products include: Sika Chemical Corp.
“AEA-15”; Euclid Chemical Co. “AEA-92”; or approved equal.
7. Shrinkage Reducing Admixture:
a. Select admixture for compatibility with air entrainment admixture and other
ingredients in the concrete mix. Acceptable products include: BASF “Tetraguard
AS20”; Grace “Eclipse 4500”; or spproved equal.
F. Water:
1. For washing aggregate, mixing, and for curing shall be free from oil and deleterious
amounts of acids, alkalis, and organic materials; comply with the requirements of
ASTM C1602. Additionally, water used for curing shall not contain an amount of
impurities sufficient to discolor the concrete.
G. Change of Materials:
1. After each concrete mix design is approved, no changes of any sort or source will be
allowed without prior written approval from the Engineer. When brand, type, size, or
source of cementitious materials, aggregates, water, ice, or admixtures are proposed
to be changed, new field data, data from new trial mixtures, or evidence that
indicates that the change will not affect adversely the relevant properties of the
concrete shall be submitted for approval by the Engineer before use in concrete.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 7
2.02 CONCRETE CHARACTERISTICS
A. Mix Proportioning:
1. Concrete shall be normal weight concrete composed of cement, pozzolan,
admixtures, aggregates, and water; proportioned and mixed to produce a workable,
strong, dense, and impermeable concrete. It is acceptable to substitute interground
Portland-pozzolan cement conforming to ASTM C595, containing the specified
amount of pozzolan in lieu of Portland cement and pozzolan. Water-cementitious
material (w/cm) ratio is based on the combined contents of cement and pozzolan.
2. Provide concrete mix designs in accordance with the following guidlines:
Concrete
class
Minimuma
28-day
compressive
strength, psi
ASTM coarse
aggregate
size
Maximum
water-
cementitious
materials
(w/cm) ratio
Minimum
cementitious
materials
content
(pounds/CY)
Pozzolan,
percent by
weight of
cementitious
materials
Air content
(percent)
Slump
rangef
(inches)
B 3000 57 or 67 0.45 560 15-20d 4-6 3-5
C-1 4500 57 or 67 0.40 560 15-20 4-6 3-5
C-2 5000 57 or 67 0.42 560 15-20d 4-6 3-5
D-1 4000 8 0.42 600 15-20d 4-6 3-5
Ec 2000 57 -- - 15-20d Not Required 4-8
a Determine compressive strength at the end of 28 days based on test cylinders made and tested in accordance with
ASTM C39.
b Compressive strength of Class A concrete may be determined at 56 days.
c Concrete encasement for electrical conduit shall contain 3 pounds of red oxide per sack of cement.
d Pozzolan use is optional for this class of concrete.
e Minimum 28-day compressive strength shall be 500 psi and maximum 28-day compressive strength shall be 1,000 psi.
f Slump before addition of high range water reducing admixture (superplasticizer). Maximum slump after addition of high
range water reducing admixture shall be 8”.
B. Use:
1. Provide concrete by class for the uses listed below.
Concrete class Type of use
B Non-structural concrete (sidewalks,
curbs, pavers, etc.)
C-1 Typical cast-in-place structural concrete
C-2 Precast concrete
D-1 Topping concrete (Precast Concrete
Topping)
Ea Pipe bedding and encasement, electrical
conduit encasement (duct banks) and
concrete fill
a Contractor’s option to use the same concrete mix for pipe encasement as the concrete slab above.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 8
C. Control Tests:
1. General:
a. Select and adjust proportions of ingredients in accordance with ACI 211.1.
Verification of mix characteristics for submittal may be achieved using either the
Trial Mix Design method or Field Experience Data method. Do not place concrete
prior to submittal and acceptance of proposed mix.
2. Trial Mix Design:
a. Mixes verified by this method shall have the samples produced for testing,
manufactured at the batch plant which will supply concrete to the project, using
materials proposed for the Work and material combinations listed above. Testing,
data, and reporting shall conform to ACI 318 and the following:
1) Required compressive strength used as the basis for selecting concrete
proportions (f’cr) shall be the specified concrete strength (f’c) + 1000 psi for
specified concrete strengths less than 3,000 psi and f’c + 1200 psi for
specified concrete strengths between 3000 psi and 5000 psi.
2) Make at least three different trial mixtures for each class of concrete
qualified by the Trial Mix Design. Each trial mixture shall have a different
w/cm ratio or different cementitious materials content that will produce a
range of compressive strengths encompassing f’cr.
3) Design trial mixtures to produce a slump within ¾ inch of the maximum
specified and an air content within 0.5 percent of the maximum specified.
4) For each w/cm ratio or cementitious materials content, cast and cure at
least twelve standard test cylinders in accordance with ASTM C192. Four
cylinders from each batch tested at age 7-days, 14-days, and 28-days or as
required to comply with ACI 318.
5) From results of the cylinder tests, plot a curve showing the relationship
between w/cm ratio and compressive strength.
6) From the curve of w/cm ratio versus compressive strength, select the w/cm
ratio that will produce f’cr. This is the maximum w/cm ratio to be used
unless a lower w/cm ratio is specified above.
3. Field Experience Data:
a. When sufficient test data for a particular mix design is available which is identical
or substantially similar to that proposed for use, Contractor may substitute use of
this data in lieu of a trial mix design. Field data, reports, and analysis shall
conform to ACI 318, except as modified herein.
1) Historical mix design proportions for which data are submitted may vary
from the specified mix within the following limits:
a) f’c as specified or up to 500 psi above
b) w/cm ratio as specified or lower
c) pozzolan content within 5 percent of that specified
d) maximum coarse aggregate size may not vary smaller, but gradation
of coarse aggregate may vary
e) slump after introduction of admixtures +0/-1 inch.
b. Use of historical Field Experience Data does not allow modification of the project
mix specifications herein without review and acceptance by the Engineer.
4. Shrinkage:
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 9
a. Liquid containing structures using Class C-1 concrete mix are intended to be
watertight. Provide test results for Class C-1 concrete mix meeting the following
requirement: drying shrinkage limit of 0.032 percent in the laboratory at 35-days
(7-days moist cure and 28-days drying) as tested in accordance with ASTM C157
and the following modifications:
1) Wet cure specimens for a period of 7-days (including the period of time the
specimens are in the mold). Wet cure may be achieved either through
storage in a moist cabinet or room in accordance with ASTM C 511, or
through storage in lime saturated water.
2) Slump of concrete for testing shall match job requirements and need not be
limited to restrictions as stated in ASTM C 157 section 8.4.
3) Report results in accordance with ASTM C 157 at 0, 7, 14 & 28-days of
drying.
b. Concrete shall not be placed in the field prior to acceptance of the concrete mix.
To meet the drying shrinkage limit, it is recommended that a shrinkage reducing
admixture be considered for use in concrete for liquid containing structures.
2.03 WATERSTOPS
A. Polyvinyl Chloride (PVC):
1. Manufacture PVC waterstops from virgin polyvinyl chloride conforming to the Corps of
Engineers Specification No. CRD-C572. Use 6-inch flat center/ribbed sides/0.375
inch thick less waterstops in construction joints. Acceptable products include:
Greenstreak Group, Inc. “Model 679”; Vinylex Waterstops and Accessories “Model
R638”; or approved equal. Use 9 inch center-bulb/ribbed sides/0.375 inch thick
waterstops in expansion joints. Acceptable products include: Greenstreak Group, Inc.
“Model 696”; Vinylex Waterstops and Accessories Model “RLB938”; or approved
equal.
2. Use molded crosses, tees, and other shapes for changes of direction, intersections,
and transitions or cut and splice as recommended by the manufacturer.
B. Expanding (Hydrophilic) Waterstops:
1. Expanding waterstops shall be bentonite-free and made from unvulcanized rubber.
Acceptable products include: Adeka Corporation “Ultra Seal MC-2010MN”;
Greenstreak Group, Inc. “Hydrotite CJ-1020-2K”; or approved equal. These are
allowable for use only where indicated on the drawings or accepted in writing by the
Engineer. Provide adhesive approved by the waterstop manufacturer plus concrete
nails and fender washers to secure waterstop material in-place during concrete
placement. The waterstop MUST be placed between two mats or curtains of steel
reinforcement.
2. For limited cover applications or where only one mat or curtain of reinforcement is
present, use Adeka Corporation “Ultra Seal KBA-1510FP”or approved equal.
C. Injected Tube Waterstops:
1. Chemical grout injection tube system, use De Neef Construction Chemicals “Injecto
System” or approved equal.
2.04 SEALANTS AND JOINT FILLERS
A. Sealants and preformed joint fillers are specified in Sections 07 92 00 and 07 91 26.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 10
2.05 BONDING COMPOUNDS
A. Not exposed to water after placement: Polyvinyl Acetate.
B. Exposed to water after placement: Latex emulsion or epoxy adhesive.
C. Apply bonding compounds in accordance with the manufacturer’s instructions.
2.06 EPOXY FOR CRACK INJECTION
A. Use a two-component, moisture insensitive, high modulus, injection grade, 100 percent
solids, epoxy-resin blend. Consistency as required to achieve complete penetration into
cracks. Material shall conform to ASTM C881 Type 1 Grade 1. Acceptable products
include: Sika Corporation “Sikadur 52”; Adhesives Technology Corporation “Crackbond
SLV302”; or approved equal.
B. Use epoxy injection for structural crack repairs except as noted below for non-structural
cracks in liquid-containing concrete structures. The Engineer shall determine whether a
crack is classified as structural or non-structural.
2.07 CHEMICAL GROUT FOR CRACK INJECTION
A. Use hydrophobic polyurethane grout at the Engineer's discretion as an alternative for
sealing non-structural cracks in concrete structures intended to be watertight. Acceptable
products include: DeNeef Construction Chemicals "Hydro Active Cut" and “Flex SLV PURe”
or Sika Corporation “SikaFix HH Plus” and “SikaFix HH LV”; or approved equal.
2.08 RETARDANT
A. Retardant for exposing aggregate for unformed surfaces in construction joints shall be
Sika Corporation“Rugasol-S”; W.R. Grace “Top-Cast”; or approved equal.
B. Apply retardant in accordance with manufacturer’s instructions sufficient to assure
a minimum penetration of 1/4 inch.
2.09 SURFACE HARDENER
A. Moderate Duty Hardener:
1. Use a premixed, non-colored, and non-metallic hardener. Acceptable products
include: BASF “MasterTop 100”; or approved equal.
2. Apply hardener in accordance with manufacturer’s instructions, in an amount of at
least 0.75 pounds per square foot for commercial, light duty traffic and 1.25 pounds
per square foot for heavy duty traffic and process spaces. Product and/or application
procedure shall be coordinated with air content of concrete being placed.
B. Heavy Duty Hardener:
1. Use an emery aggregate dry shake applied during slab finishing. Acceptable products
include: L&M Construction Chemicals “Emeryplate FF”; or approved equal.
2. Apply in accordance with manufacturer’s recommendations at a minimum rate of 1.5
pounds per square foot; adjust for the specific floor traffic and use anticipated.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 11
Product and/or application procedure shall be coordinated with air content of
concrete being placed.
C. Hardener For Existing Concrete:
1. Use an alkaline siliconate solution to harden, densify, and seal the surface.
Acceptable products include: L&M Construction Chemicals “Seal Hard”; or approved
equal.
2.10 CURING AND SEALING COMPOUNDS
A. Acceptable products include: BASF “MasterKure CC 250SB”; Dayton Superior “Cure &
Seal 25% J22UV”; or approved equal, conforming to ASTM C309 and ASTM C1315.
B. Compound shall be clear and applied in accordance with the manufacturer’s instructions.
C. Curing and sealing compound shall be certified compliant with final finish system if
applicable.
2.11 VAPOR RETARDER
A. Permeance: Maximum 0.3 perm when tested in accordance with ASTM E96, Procedure A.
B. ASTM E1745 Class A; 6 mil thick clear polyethylene film; type recommended for below
grade application. Furnish joint tape recommended by manufacturer.
PART 3 EXECUTION
3.01 GENERAL
A. Use only truck-mixed, ready-mixed concrete conforming to ASTM C94. Proportion
materials by weighing.
B. Introduce pozzolan into the mixer with cement and other components of the concrete mix;
do not introduce pozzolan into a wet mixer ahead of other materials or with mixing water.
C. Introduce water at the time of charging the mixer; additional water may be introduced
within 45 minutes from charging the mixer, provided the specified w/c ration and slump is
not exceeded and the maximum total water per the approved mix design is not exceeded.
D. Arrange with the testing laboratory for inspection as required to comply with these
specifications.
E. Deliver concrete to the site and complete discharge within 90 minutes after introduction
of water to the mixture. Extension of allowable time beyond this limit requires a Contractor
proposed remedial action plan to be reviewed and accepted by the Owner’s
Representative.
3.02 CONVEYING AND PLACING CONCRETE
A. Convey concrete from the mixer to the forms in accordance with ACI 301. Remove
concrete that has segregated in conveying from the site of the work.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 12
B. Placing Concrete:
1. General:
a. Place concrete in accordance with ACI 301. Do not permit concrete to drop freely
more than 4-ft.
b. Install vapor retarder under interior slabs on grade in accordance with ASTM
E1643. Lap joints minimum 6" and seal watertight by taping edges and ends.
c. Repair vapor retarder damaged during placement of concrete reinforcing. Repair
with vapor retarder material; lap over damaged areas minimum 6" and seal
watertight.
2. Placing Concrete By Pumping:
a. Concrete placed by pumping is at Contractor’s discretion and shall not be the
cause to change or relax specified mix design characteristics. Concrete shall
possess the specified characteristics at the point of placement.
b. Measure slump at the hose discharge, except as follows: Initial slump testing in
each placement shall occur at both the pumping unit inlet hopper and hose
discharge. Slump loss in pumping, measured between the inlet hopper and the
hose discharge, shall not exceed 1 inch. After these criteria have been satisfied,
slump may be measured at the inlet hopper with allowable slump increased by
the earlier measured difference, not to exceed 1 inch.
c. Before starting each pumping operation, prime the pump and line with a cement
slurry to lubricate the system. Waste cement slurry outside the forms. Equip hose
tip with a safety chain for recovery in case of hose blowout during pumping. Hose
or accessories shall not remain in the freshly placed concrete.
d. Use tremie placing techniques and equipment for pump placed concrete. Pump
discharge system shall remain full of concrete from pump to discharge point at
all times. Concrete pumping shall not occur until Owner’s Representative has
verified equipment including the tremie plug. Should the discharge line become
open, with zones empty of concrete, cease pumping and re-primed with tremie
plug installed before continuing.
3. Placing Concrete In Hot Weather:
a. In temperatures above 80 degrees F, place concrete in accordance with
ACI 305.1.
4. Placing Concrete In Cold Weather:
a. In temperatures below 45 degrees F, place concrete in accordance with
ACI 306.1.
3.03 CONSOLIDATING CONCRETE:
A. Consolidate concrete in accordance with ACI 301. If evidence of inadequate consolidation
is observed, concrete placement will be suspended until Contractor provides a revised
plan to achieve proper consolidation.
3.04 CURING AND SEALING
A. General:
1. Cure concrete using water, a clear membrane curing compound, or by a combination
of both methods. Coordinate repairs or treatment of concrete surfaces so that
interruption of curing will not be necessary.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 13
2. Maintain concrete surface temperature between 50 degrees F and 80 degrees F for
at least 5 days. Cure concrete in hot weather (above 80 degrees F) in accordance
with ACI 305.1. Cure concrete in cold weather (below 45 degrees F) in accordance
with ACI 306.1.
B. Water Curing:
1. Keep concrete continuously wet for a minimum of 10-days after placement.
Absorptive mats or fabric may be used to retain moisture during the curing period.
2. Use water curing in hot weather for liquid containment structures. Cover forms and
keep moist. Loosen forms as soon as possible without damage to the concrete, and
make provisions for curing water to run down inside them. During form removal, take
care to provide continuously wet cover to newly exposed surfaces.
C. Curing Compound:
1. When curing compound is allowed, apply it as soon as the concrete has set
sufficiently so as not to be marred by the application or apply it immediately following
form removal for vertical and other formed surfaces. Preparation of surfaces,
application procedures, and installation precautions shall follow manufacturer’s
instructions. For liquid containing structures, apply curing compound at twice the
manufacturer’s recommended dosage rate, applied in two coats perpendicular to
each other.
2. Do not use curing compound on concrete surfaces to be coated, waterproofed,
moisture-proofed, tiled, roofed, or where other coverings are to be bonded In these
cases, use water curing unless the curing compound is first removed or is compatible
with the final finish covering.
3.05 PROTECTION
A. Protect concrete from injurious action by sun, rain, flowing water, frost, and mechanical
means.
B. Loading green concrete is not permitted. Green concrete is defined as concrete with less
than 100 percent of the specified strength.
C. Backfill shall not be placed against concrete walls until the concrete has reached the
specified strength, connecting slabs and beams have been cast and have also reached
the specified strength, and watertightness testing and repairs have been completed for
liquid containing strutures to the satisfaction of the Owner’s Representative.
D. Arrangements for covering, insulating, heating, and protecting concrete in cold weather
shall be in accordance with ACI 306.1.
3.06 CONSTRUCTION JOINTS
A. General:
1. Place concrete in each unit of construction continuously. Before new concrete is
placed on or against concrete which has set, retighten forms and clean foreign
matter from the surface of the set concrete. Provide waterstops as specified.
B. Construction:
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 14
1. Form construction joints by producing a rough surface of exposed aggregates using a
surface retardant; include joints between the slab and topping concrete. The limit of
the treated surfaces shall be 1 inch away from the joint edges. Within 24 hours after
placing, remove retarded surface mortar either by high pressure water jetting or stiff
brushing or combination of both so as to expose coarse aggregate. A rough surface of
exposed aggregate may also be produced by sandblasting followed by high pressure
water jetting. Sandblasting, if used, shall remove 1/4 inch of laitance film and expose
coarse aggregate to ensure adequate bond and watertightness at the construction
joints.
C. Locations:
1. Provide construction joint locations as follows:
a. Cast walls exceeding 50 feet in length in panels not to exceed 30 feet in length.
Cast adjoining panels only after 5-days have elapsed. Joints are not allowed
within the lesser of 10 feet or 25 percent of the wall length from a corner unless
specifically detailed thus on the drawings.
b. Locate joints in beams or girders at or near the quarter point between supports.
c. Make joints in the members of a floor system at or near the quarterpoint of the
span.
d. Make joints in walls and columns at the underside of floors, slabs, beams or
girders and at the tops of footings or floor slabs.
e. Cast slab panels in checkerboard patterns not to exceed 40 feet in length and
not to exceed 900 square feet in area, with maximum 1 ½ to 1 ratio of side
lengths. Minimum lapsed time between placing adjacent panels shall be 3-days.
The requirements for size of slab panel is waived if joints are located on the
Drawings.
2. Vertical construction joints shall have edges grooved or beveled at faces exposed to
view including interior faces of basins and tanks. Seal grooves subjected to wetting
or weather with joint sealant.
3. Continue reinforcing steel and any welded wire reinforcement through construction
joints. Beams, girders, and floor slabs shall not be constructed over columns or walls
until at least one day has elapsed to allow for initial shrinkage in the column or wall.
No joint will be allowed between a slab and a beam or girder unless otherwise shown.
Joints shall be perpendicular to the main reinforcement. Provide waterstops in
construction joints as specified.
3.07 INSERTS AND EMBEDMENTS
A. Inserts:
1. Where pipes, castings, or conduits are to pass through structures, position in forms
before placing concrete; or where shown on Drawings or approved by the Owner’s
Representative, provide openings in the concrete for subsequent insertion of such
pipes, castings, or conduits. Provided waterstops and a slight flare in the form to
facilitate grouting and permit the escape of entrained air during grouting.
2. Provide additional reinforcement around openings. Use non-shrink grout to infill
around inserts.
3. Place horizontal conduits and pipes, in slabs and beams, between the top and
bottom layers of reinforcement. Spacing and size limitations shall conform to
ACI 318.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 15
4. Conduits and pipes shall not run directly beneath a column or base plate.
5. Position conduit, pipe, dowels, and other ferrous items such that there will be a
minimum of 2-inches clearance between said item and concrete reinforcement.
Welding inserts to reinforcement is not permitted.
6. The outside diameter of conduit or pipe shall not exceed one-fourth the slab or beam
thickness.
B. Embedments:
1. Gate frames, gate thimbles, special castings, channels, grating frames, or other
miscellaneous metal parts to be embedded in concrete shall be secured in the forms
prior to concrete placement.
2. Embed anchor bolts and inserts in concrete as shown. Provide inserts, anchors, or
other bolts necessary for the attachment of piping, valves, metal parts, and
equipment.
3. Provide nailing blocks, plugs, strips, and the like necessary for the attachment of
trim, finish, and similar work. Voids in sleeves, inserts, and anchor slots shall be filled
temporarily with readily removable material to prevent entry of concrete. Do not use
continuouse anchor slots or strips in concrete intended to be watertight.
4. Positon operators or sleeves for gate or valve stems to clear reinforcing steel,
conduit, and other embedments, and to align accurately with equipment.
3.08 EXPANSION JOINTS
A. Expansion joints shall be as shown. Do not extend reinforcement or other embedded
metal items through expansion joints. Provide waterstops where indicated.
3.09 WATERSTOPS
A. Waterstops shall conform to ACI 301. Tie waterstops in position prior to placement of
concrete to prevent movement and deformation.
B. Provide waterstops in construction and expansion joints as follows:
1. Joints in parts of structures exposed to ground or water on one side and occupied by
non-submerged equipment or by personnel on the other.
2. Wall and slab joints of tanks and channels subject to water pressure.
3. Waterstops shall be provided for the full height of the walls.
4. Provide at other locations shown on the Drawings.
C. Field splices shall be at straight sections using heat fused welded, butt splices only.
Lapping of splices or joining by means other than heat fused welding is not allowed.
D. Install hydrophilic waterstops according to manuacturer’s recommendations. Surfaces of
concrete shall be prepared level/plumb and to the smoothness required by manufacturer.
Grind surface as necessary. Provide bonding adhesive and concrete nails with fender
washers to hold waterstop in position during concrete placment.
3.10 MODIFICATION OF EXISTING CONCRETE
A. General:
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 16
1. Verify structural dimensions related to or controlled by previously constructed or
existing structures prior to concrete work.
B. Cutting or Coring Concrete:
1. Saw cut concrete to a depth of 1 inch to form straight outlines of concrete areas to
be removed. Where reinforcement is exposed due to saw cutting or core drilling and
no new material is to be placed on the cut surface, provide a protective epoxy coating
to the entire cut surface.
2. Coat surfaces of oversized openings with an epoxy bonding compound prior to re-
finishing with profiling mortar to the required opening size.
3. Grind existing joint edges to create a chamfer matching those used on adjacent
construction.
4. Investigate concrete to be drilled, cored, or sawcut to determine location of
reinforcing steel. Locate penetrations to clear existing reinforcing steel. Where not
possible to avoid reinforcing steel, consult the Engineer as to acceptability of cutting
reinforcing steel and provide new reinforcing systems as directed.
5. Locating methods include chipping to expose reinforcing steel, ground penetrating
radar, X-ray, or magnetic flux devices. Locates of existing reinforcing shall be by the
Contractor.
C. Joining New Concrete To Existing:
1. Existing concrete surfaces to be joined with new concrete shall be cleaned and
roughened by abrasive blasting, bush hammering, or other method to achieve ¼-inch
amplitude surface. Remove existing metalwork, embeds, or other interfering items.
Coat existing surface with epoxy bonding compound prior to placement of new
concrete.
D. Post-Installed Anchors and Dowels:
1. Use non-destructive methods for locating reinforcement prior to drilling operations.
For anchor and dowel locations that interfere with reinforcement, attempt to relocate
to avoid drilling through the reinforcement if possible.
2. For situations that do not allow relocation, cutting of reinforcement for installation is
subject to the following:
a. Prior to drilling through reinforcement, the Contractor shall consult the Owner’s
Representative or Engineer.
b. Drill holes with a hammer drill and carbide bit (core drilled holes are not allowed),
followed by brushing and air-cleaning with oil-free compressed air.
c. Holes drilled through reinforcement must be in compliance with adhesive anchor
assumptions for roughened hole surface typical of a hammer drill and carbide bit.
No smooth hole surfaces are allowed.
d. Do not cut slab rebar within 24 inches of a supporting wall, column, or an
opening in the slab.
e. No cutting of rebar is allowed in the middle third of slab spans for anchors with
diameters equal to or greater than 3/4 inch.
f. Maximum of two rebar may be cut in any 10 foot width of slab.
g. Maximum of two rebar may be cut within any 10 foot width of concrete wall.
h. Maximum of one rebar may be cut within any 8 foot width of CMU wall.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 17
3. For anchors that cannot be moved and that conflict with the above requirements,
consult Engineer for direction. It is not acceptable to cut reinforcement in beams,
columns, precast members, or stairs.
4. Use a pre-manufactured, self-mixing, injectable, two-component, epoxy adhesive, as
per Section 03 60 00. Follow manufacturer’s recommendations and ICC Evaluation
Report for installation.
E. Waterstops:
1. Where a waterstop between new and existing concrete is required, install either a
hydrophilic waterstop or a retrofit waterstop as indicated.
3.11 FORMED SURFACE FINISHES
A. Repair Of Surface Defects:
1. Repair surface defects, including tie holes, minor honeycombing, or otherwise
defective concrete in accordance with ACI 301. Clean areas to be repaired. Cut and
chip out honeycombed or otherwise defective areas to solid concrete, to a depth of at
least 1-inch. If defective area includes exposed reinforcing steel, correct by removing
concrete a minimum of 1-inch beyond the reinforcing. Make edges of the cut
perpendicular to the surface of the concrete in a neat rectangular patern.
2. Joints shall be grooved to a radius or bevel of ¾-inch depth.
3. Finish patches on exposed surfaces to match and blend with adjoining work. Cure
patches as specified for the concrete. Protect finished surfaces from stains and
abrasions.
B. Formed Surface Finishes:
1. Finish A - Grout Rubbed Finish
a. After repair of surface defects, apply a grout rubbed finish in accordance with
ACI 301 except that all form fins and other protrusions shall be completely
removed. Lightly sandblast surfaces prior to sacking. Sandblasting shall occur
after the specified curing period.
b. Add a PVA bonding compound to the mix water used in sacking mortar; as
recommended by the manufacturer.
c. Provide Finish A at uncoated surfaces of stair wells, interior surfaces of
equipment rooms, galleries, tunnels, operations areas, exposed channels and
tanks from 1 foot below minimum water surfaces and up, and at permanently
exposed vertical and sloped surfaces such as pipe chases.
d. Do not provide Finish A at concrete surfaces receiving a coating.
2. Finish B - Smooth Surface Finish
a. Initial surface preparation is the same as Finish A; repair surface defects and
remove all form fins.
b. Provide Finish B at surfaces to be coated. See Section 09 90 00 for additional
concrete surface preparation, including filling of bug holes, and coating
requirements.
3. Finish C - Rough Form Finish
a. Repair surface defects and imperfections greater than 3/8 inch in any
dimension. Remove form fins and protrusions down to less than 3/8 inch
projection.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 18
b. Provide Finish C or smoother, for interior surfaces of wet wells, tanks, and
channels; from 1 foot below minimum water surface and down.
c. Also apply Finish C to unoccupied interior areas not otherwise specified.
4. Finish D – Unfinished Surface
a. Repair surface defects and otherwise leave the surfaces as they come from the
forms, except plug tie holes and repair or remove defects greater than 1/2 inch
in any dimension.
C. Sample Of Formed Surface Finish A:
1. Provide a sample concrete panel, minimum 4 feet by 4 feet; representative of formed
surface Finish A. The panel shall be representative of the workmanship and finish
required, including repair of defects, filling of tie holes, sandblasting, and rubbing.
2. The sample shall be approved by the Owner’s Representative prior to the start of
production work. The sample shall be on display at the job site, and finished surfaces
shall match sample.
3.12 SLAB FINISHES
A. General:
1. The finishes specified herein include surface finishes, treatments and toppings for
floors and slabs. Do not use dry cement on new concrete surfaces to absorb excess
moisture. Round edges to a radius of 1/2 inch.
2. Slope floors to drain uniformly within a room or space. Unless otherwise specified,
slope shall be a minimum of 1/8 inch per foot toward nearest drain. Restrict use of
floor drains with only locally depressed slabs to locations specifically noted.
3. Immediately after final finish is applied, the surface shall be cured and protected as
specified in Curing, Sealing, and Protection paragraphs above.
4. Where finish is not specified, floor slabs shall receive a Steel Trowel Finish.
B. Float Finish:
1. Perform floating with a hand or power-driven float in accordance with ACI 301. Begin
floating when the bleed water sheen has disappeared and the surface has stiffened
sufficiently. Float as required to meet tolerance requirements of ACI 117 for a
conventional surface.
2. Floating shall close cracks and checks plus compact and smooth the surface. Refloat
the slab to a uniform texture.
3. Applly float finish to surfaces of channels, tank bottom slabs, tops of footings, and
surfaces to receive insulation or roofing.
C. Steel Trowel Finish:
1. Float the concrete surface as indicated above and then trowel in accordance with
ACI 301.
2. Provide Steel Trowel Finish on floors and walking surfaces unless specified
otherwise.
D. Broom Finish:
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 19
1. Float the concrete surface as indicated above, then immediately give the concrete a
coarse transverse scored texture by drawing a broom or burlap belt across the
surface in accordance with ACI 301.
2. Provide a Broom Finish for walks, top of tank walls, slabs-on-grade exposed to
atmosphere, and where otherwise indicated.
3.13 TOPPING CONCRETE
A. Subfloor Finish:
1. Slabs to receive a topping concrete, topping grout, or tile; shall be float finished to
required elevations. Immediately following the final finishing, either:
a. treat slab with a retardant and abrasive blast to create expose aggregate with ¼
inch amplitude, or
b. create the ¼ inch amplitude roughened surface by raking the freshly floated
surface using a standard garden rake.
2. Immediately after finishing, proceed with required curing and protection of the slab
as stated above.
B. Topping Concrete or Grout:
1. Remove dirt, laitance, and loose aggregate. Keep cleaned base slab saturated
surface dry for a period of 24 hours prior to the application of topping. Remove
excess water.
2. Apply and scrub a neat cement grout into the surface of the base slab using a stiff
broom. The cement grout shall not be allowed to dry and shall be spread within 15
minutes ahead of the topping placement.
3. The topping shall then be placed, compacted, and floated. Test surface with a
straight edge to detect and correct high and low spots to a tolerance of 1/8 inch in
10 feet.
4. Incorporate float finish, surface hardener, steel trowel finish, etc as specified.
3.14 RELATED SURFACES
A. Stair Treads:
1. Construct stair treads with a nonskid nosing as specified in Section 05 50 00.
2. Treads shall have a Float Finish followed by a Steel Trowel Finish with a slope of
1/8 inch toward the front.
B. Finishing of Unformed Surfaces:
1. Adjacent Unformed Surfaces:
a. Tops of walls, buttresses, horizontal offsets, and similar unformed surfaces
occurring adjacent to formed surfaces shall be struck smooth after concrete is
placed and shall be Float Finished to a texture reasonably consistent with that of
the adjacent formed surface.
b. Continue final treatment of formed surface uniformly across the top of the
unformed surface.
2. Pavements and Sidewalks:
a. The surface of the concrete shall be screeded to grade and sloped to drain. After
screeding, the surface shall be Float Finished followed by a Broom Finish.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 20
b. Round edges and expansion joints to a radius of 1/2 inch. Control joints shall be
grooved or sawcut to a minimum depth of 1/4 the slab thickness.
3.15 FIELD SAMPLING AND TESTS
A. General:
1. Field sampling and tests shall be performed by an independent testing laboratory.
Samples of aggregates and concrete will be obtained at such times to represent the
quality of the materials and work throughout the project.
2. The laboratory shall provide necessary labor, materials and facilities for sampling
aggregate and for casting, handling, and initially storing the concrete samples at the
work site.
3. The minimum number of samples and tests are specified in Testing paragraph below.
B. Sampling:
1. Aggregates:
a. General:
1) Sample fine and coarse aggregates in accordance with ASTM D75 not less
than 30 days prior to the use of such aggregates in the work.
2) Take samples at the discharge gates of the bins feeding the weigh hopper.
Repeat sampling when the source of material is changed or when
unacceptable deficiencies or variations from the specified requirements of
materials are found.
3) Aggregate samples shall be tagged and their sources idenified.
b. Coarse Aggregate:
1) Take a sample weighing between 50 and 60 pounds after the batch plant is
brought up to full operation.
2) Take samples to obtain a uniform cross section, accurately representing the
materials on the belt or in the bins for sieve analysis.
c. Fine Aggregate:
1) Take samples as specified for coarse aggregate.
2) Take samples of sand when the sand is moist for sieve analysis and specific
gravity tests.
2. Concrete:
a. Take samples of plastic concrete in accordance with ASTM C172.
b. Take samples at the hopper of mixing equipment or transit mix truck, except as
noted in the Placing Concrete by Pumping subparagraph of the Conveying and
Placing article above.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 21
C. Testing:
1. Aggregate:
a. A minimum of one test of coarse aggregate per 400 cubic yards of concrete used
and a minimum of one test of fine aggregate per 200 cubic yards of concrete
used shall be made to confirm continuing conformance with specifications for
gradation, cleanliness and sand equivalent.
b. A maximum of one test per day of each aggregate is required.
c. Repeat of the entire concrete mix design test program is required before source
changes will be accepted.
2. Concrete:
a. Strength Tests:
1) The strengths specified for the design mix shall be verified by the
independent testing laboratory during placement of the concrete.
Verification shall be accomplished by testing standard cylinders of
concrete samples taken at the job site. Cylinders shall be 4 by 8 inch or 6
x 12 inch.
2) Concrete samples shall represent the concrete placed in the forms. One
set of six standard 6 x 12 inch (or nine 4 x 8 inch) cylinders shall be cast
of each class of concrete for each 50 cubic yards or less, or for each
5,000 square feet of slab or wall surface area placed per day. Provide
additional cylinders when an error in batching is suspected. Each set of
cylinders are cast from material taken from a single load of concrete.
3) Casting, handling and curing of cylinders shall be in accordance with
ASTM C31. For the first 24 hours after casting, keep cylinders moist in a
storage box constructed and located so that its interior air temperature
will be between 60 and 80 degrees F. At the end of 24 hours, the testing
laboratory will transport the cylinders to their laboratory.
4) Testing of specimens for compressive strength shall be in accordance
with ASTM C39. Each test shall consist of two 6 x 12 inch (or three 4 x 8
inch) test cylinders from each group of six (or nine) specimens. Test at
the end of 7 days and at the end of 28 days. The remaining cylinders
shall be tested at the end of 56 days if the 28-day strength reports below
specification.
5) A strength test shall consist of the average strength of two 6 x 12 inch (or
three 4 x 8). If one cylinder shows evidence of low strength due to
improper sampling, casting, handling, or curing, the result of the
remaining cylinders may be used if approved by the Owner’s
Representative.
6) The average of any three consecutive 28-day strength test results of the
cylinders representing each class of concrete for each structure shall be
equal to or greater than the specified strength. Not more than 10
percent of the individual strength test results shall have values less than
the specified 28-day strength for the total job concrete. No individual
strength test result shall be less than the specified strength by more than
500 pounds per square inch.
7) Provide certified reports of the test results directly to the Owner’s
Representative and the Engineer. Test reports shall include sufficient
information to identify the mix used, the stationing or location of the
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 22
concrete placement, and the quantity placed. Slump, water/cement ratio,
air content, temperature of concrete, and ambient temperature shall be
noted.
8) The 28-day strength test results shall be evaluated in accordance with
ACI 214R. Quality control charts showing field test results shall be
included with the test results for each class of concrete in each major
structure. Charts shall be prepared in accordance with ACI 214R. Quality
control charts shall be maintained throughout the entire project and shall
be available for the Owner’s Representative’s inspection at any time.
9) If the 28-day test results fall below the specified compressive strength for
the class of concrete required for any portion of the work, adjustment in
the proportions, water content, or both, shall be made as necessary at
the Contractor’s expense. Report changes and adjustments in writing to
the Owner’s Representative.
10) If compressive test results indicate concrete in place may not meet
structural requirements, tests shall be made to determine if the structure
or portion thereof is structurally sound. Tests may include, but not be
limited to, cores in accordance with ASTM C42 and any other analyses or
load tests acceptable to the Engineer. Costs of such tests and/or anlysis
shall be borne by the Contractor.
b. Tests for Consistency of Concrete:
1) Measure slump in accordance with ASTM C143. Take samples for slump
determination from concrete during placement. Tests shall be made at
the beginning of concrete placement operation, whenever test cylinders
are cast, and at subsequent intervals to ensure that the specification
requirements are met.
2) For pumped concrete, measure slump in accordance with the Placing
Concrete by Pumping subparagraph of the Conveying and Placing article
above.
3) When high range water reducer is added at the site, slump tests shall be
taken before and after addition of the admixture.
c. Tests for Temperature and Air Content:
1) Temperature tests shall be made at frequent intervals during hot or cold
weather conditions until satisfactory temperature control is established.
Perform temperature tests whenever test cylinders are cast.
2) Measure air content in accordance with ASTM C231 whenever test
cylinders are cast. For pumped concrete, measure air content in
accordance with the Placing Concrete by Pumping subparagraph of the
Conveying and Placing article above.
D. Final Laboratory Report:
1. The testing laboratory shall provid a final report at the completion of all concreting.
This report shall summarize the findings concerning concrete used in the project and
provide totals of concrete used by class and structure.
2. Include final quality control charts for compressive strength tests for classes of
concrete specified in each major structure. Also include the concrete batch plant’s
coefficient of variation and standard deviation results for each class of concrete.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 23
3.16 REPAIR OF DAMAGED AND CRACKED CONCRETE:
A. Acceptance Of Concrete:
1. Completed cast-in-place concrete work shall conform to the applicable requirements
of ACI 301 and the Contract Documents. Concrete work that fails to meet these
requirements shall be repaired, as approved by the Engineer, to bring the concrete
into compliance. Repair methods shall be in accordance with ACI standards,
including ACI 503.7, and are subject to the approval of the Engineer.
2. Concrete that cannot be brought into compliance by approved repair methods will be
rejected. Remove and replace rejected concrete work.
3. The cost of repairs and replacement of defective concrete shall be borne by the
Contractor.
B. Repair Methods:
1. Damaged/defective concrete or concrete with crack widths exceeding 0.004 inches
at liquid-containing and conveying structures or crack widths exceeding 0.006 inches
for other structures shall be repaired by one of the following methods (only the
Engineer may determine that a defect or crack does not require repair):
a. Perform watertightness testing and repair as needed to meet leakage criteria in
this specification even when liquid-containing and conveying structures meet the
crack width criteria defined above.
b. Damaged or defective concrete includes surface defects, honeycomb, rock
pockets, indentations greater than 3/16 inch, spalls, chips, air bubbles greater
than 1/2 inch diameter, pinholes, bugholes, embedded debris, lift lines, sand
lines, bleed lines, leakage from form joints, fins, projections, form popouts,
texture irregularities, and stains or other color variation that cannot be removed
by cleaning.
1) Damaged or defective concrete is repaired according to procedures
outlined above under finish requirements, Repair of Surface Defects.
2. Crack Repair Method 1:
a. Fill the joint or crack by drilling holes to the affected area (following the product
manufacturer’s details), install injection ports, and force epoxy or chemical grout
(expanding urethane) into the joint under pressure.
b. Material type and repair proceedures shall be approved by Engineer.
c. After injection and curing; ports, sealing mix, and surface shall be cleaned and
worked to match the adjacent specified finish.
3. Crack Repair Method 2:
a. Fill cracks with low viscosity epoxy, applied by pouring/flooding crack zone until
cracks are filled. Prepare surface, install, and cure according to manufacturer’s
recommendations.
b. At a minimum, prepare surface to be clean and dry with no visible detrimental
material in cracks to be filled. Conform to temperature limitations of epoxy. Clean
and refinish to match adjacent surfaces.
4. Crack Repair Method 3:
a. Cut a bevel groove 3/8 to 1/2 inch in width and depth, use backer rod or tape,
and fill with sealant in accordance with manufacturer’s instructions.
b. This repair method is only used where approved by Engineer.
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 24
c. Groove and sealant shall be applied on wet or hydrostatic pressure side of
surface.
C. Repair Method Use:
1. Repair Method 1: For cracks in walls, surfaces sloped 1:1 or greater, beams,
columns, structural slabs, overhead surfaces, and liquid retaining surfaces. Need for
repair depends upon crack width, location, and leakage.
2. Epoxy grout is used for repair of structural cracks and chemical grout (expanding
urethane) for repair of non-structural cracks at liquid-containing structures. The
Engineer shall determine whether a crack is classified as structural or non-structural.
3. Repair Method 2: Utilized in lieu of Method 1 for slabs when approved by Owner’s
Representative. Final finish shall match adjacent surfaces.
4. Repair Method 3: Limited to dry-surface slabs, walls subject to less than three feet of
liquid pressure, or as approved by Engineer. Repair Method 3 is not an equivalent
repair method to Repair Methods 1 or 2, which shall be considered the standards.
3.17 WATERTIGHTNESS TESTING AND REPAIR
A. Liquid Containing Concrete Tanks And Channels:
1. Watertightness testing shall comply with ACI 350.1 and the following requirements:
2. Concrete tanks, basins, reservoirs and channels which have walls or slabs subjected
to hydrostatic pressure shall be tested for watertightness. The tests shall be made
after the structure is complete and the concrete has achieved its specified 28-day
strength, but prior to application of waterproof coating or backfill.
3. Filling of the tank for watertightness testing shall not exceed a rate of 4 feet/hour. Fill
with water to the maximum operating water surface. Keep water at this level for at
least 72 hours prior to start of test.
4. Testing includes visual inspection of the dry sides of all walls, wall base construction
joint at top of the slab, and the soffit of elevated slabs for evidence of leakage. Damp
spots, leakage, or seepage revealed by the test, including those caused by shrinkage
of concrete, honeycombed areas, construction joints, or other sources shall be
repaired by Repair Method 1 (see Repair Methods paragraph in the Repair of
Damaged Concrete and Cracking article above).
5. Damp spots are defined as areas from which water that can be picked up on dry
hand and smeared across the dry concrete surface.
6. Re-test tanks or channels which have been repaired to check the suitability of
repairs.
7. Provide water required for testing and re-testing and dispose of in an approved
manner.
8. After repair of visual leakage, liquid containing or conveying concrete structures
supported on soil must also meet maximum leakage criteria into the soil through
their base slab or mat foundation as follows:
Structure Type Tightness Criterion
Containment structures fully lined prior to hydrostatic test No measurable loss
Cylindrical water and wastewater storage tanks and
reservoirs other than digesters
0.025 percent per
day
Lake Keowee to Adkins WTP Raw Water System Cast-in-Place Concrete
154828 03 30 00 - 25
Digesters 0.050 percent per
day (surcharged
hydrostatic test)
Rectangular basins and tanks 0.050 percent per
day
Concrete paved reservoirs and channels 0.10 percent per
day
Note: All damp spots and/or leakage through walls, wall-to-slab joints, and elevated slabs shall first be
repaired as described above. Leakage into soil equal to or less than the values shown in the table
above is permitted only through base slabs on soil or mat foundations.
9. Record volume loss by measuring the vertical distance from the water surface to a
fixed point on the tank above the water surface. Account for evaporation from open
surfaces.
10. If the drop in water surface during the 24-hour test period exceeds the values given
in the table above, exclusive of evaporation, the leakage is considered excessive and
shall be remedied.
3.18 CLEANUP
A. Upon completion of the work and prior to final inspection, clean all concrete surfaces as
follows: Sweep with a broom to remove loose dirt, then mop and/or flush with clean water.
Scrub by hand or machine as required to remove and blend stains or discolored areas .
B. Clean floors that have curing and sealing compound as stated above, followed by the final
application of curing and sealing compound.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 1
SECTION 03 48 11
PRECAST CONCRETE VAULTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Factory design and manufacture of precast concrete vault sections and accessories.
B. Quality assurance and control.
C. Field installation of vaults.
D. Waterproofing of vaults.
E. Installation of frames, hatches, and fall protection.
F. Ladders and safety devices.
1.02 RELATED SECTIONS
A. Section 03 11 00 - Concrete Forming
B. Section 03 20 00 - Concrete Reinforcement
C. Section 03 30 00 - Cast-In-Place Concrete
1.03 REFERENCES
Reference Title
ASTM C150 Portland Cement
ASTM C207 Hydrated Lime for Masonry Purposes
ASTM C478 Precast Reinforced Manhole Sections
ASTM C913 Precast Concrete, Water, and Wastewater Structures
ACI 301 Specifications for Structural Concrete Buildings
ACI 315 Details and Detailing of Concrete Reinforcement
ACI 315R Manual of Engineering and Placing Drawings for Reinforced Concrete Structures
ACI 318 Building Code Requirements for Structural Concrete
CRSI 63 Recommended Practice for Placing Reinforcing Bars
1.04 DESIGN
A. All vaults shall be designed by a licensed professional engineer registered in the State of
South Carolina, and engaged by the manufacturer. All dead loads, live loads, flotation,
erection, temperature and anchorage stresses shall be considered.
B. The calculations and drawings shall be prepared in a neat and legible manner, sealed by
the licensed Professional Engineer performing the calculations.
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 2
C. The sealed calculations shall include a summary page to list all design loads, material
specifications, and design criterion used in the calculations.
D. For design, groundwater shall be assumed at the top of the vault and the design shall
provide for a 1.5 percent factor of safety against floatation.
E. Vaults shall be designed for H-20 wheel load on top slab, hatches, and surcharge loading
at grade around all sides of the vault.
1.05 SUBMITTALS
A. Submit evidence that shows current PCI, NPCA, and/or SCDOT certification.
B. Submit shop drawings of wall sections and bases proposed for this project, include joint
design and related details for field assembly as applicable.
C. Submit certification of conformance with Contract Documents and ASTM C478 or C913
as applicable.
D. Submit catalog cut and installation details for cast iron manhole covers, aluminum
hatches with fall protection grates, and ladders with safety devices
E. Submit catalog cut for waterproofing system used on exterior surfaces.
F. Under a separate submittal, provide two file copies of calculations for each vault
indicating all loads and load combinations. Other than the summary page, calculations
will not be reviewed; calculations will not be returned to Contractor.
1.06 QUALITY ASSURANCE
A. Manufacturer shall be a PCI, NPCA, and/or SCDOT-certified plant for production of
precast vaults as specified herein.
B. Aggregate used in producing concrete shall be from SCDOT approved sources.
1.07 QUALITY CONTROL INSPECTION
A. The quality of all materials, the process of manufacture and the finished sections shall
be subject to inspection by Engineer. Such inspection may be made at the place of
manufacture and/or at the Site after delivery.
B. All sections shall be inspected for general appearance, dimensions, soundness, etc. The
surface shall be dense, close-textured and free of honeycomb, cracks, roughness,
exposure of reinforcement, damaged joints, or other irregularities.
C. All sections which have been damaged after delivery will be rejected, or if already
installed, shall be repaired or removed and replaced entirely at Contractor’s expense.
D. Rejected sections shall be tagged as such, segregated from other sections, and removed
from the Site.
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 3
PART 2 PRODUCTS
2.01 CONCRETE
A. Minimum 28-Day Compressive Strength - 4500 psi.
2.02 REINFORCEMENT
A. Reference Section 03 20 00.
2.03 PRECAST OR CAST-IN-PLACE CONCRETE BASES
A. Design and manufacture of precast concrete bases shall conform to the requirements of
this section and ASTM C478 or C913 as applicable. Cast-in-place concrete bases shall
conform to Section 03 11 00 and Section 03 30 00.
B. Bases shall conform to the dimensions indicated on the Drawings or as required by
design. The horizontal joint at the top of the base shall be compatible with that of the
precast wall section.
C. Sumps shall be where shown on the Drawings. Walking surfaces shall be sloped to the
sump, have a non-slip broom finish, and be sealed with a penetrating concrete sealer.
Minimum concrete fill thickness at sumps shall be two inches.
2.04 PRECAST CONCRETE WALLS
A. Design and manufacture of precast concrete walls shall conform to the requirements of
this section and ASTM C478 or C913 as applicable.
B. All tongue-and-groove joints in the precast wall, including the joint at the top of the base,
shall be made up using gaskets.
C. The precast sections shall be provided with a special groove to receive and hold the
gasket in position during joint assembly.
D. After joint assembly, the gap between sections shall be packed on the inside and outside
with “Masterflow 713” by Master Builder; “Five Star Grout” by U.S. Grout Corp.; or equal,
and shall be troweled smooth so that no projections remain on the inside. There shall be
concrete to concrete bearing between the various sections. The gasket shall not support
the weight of the section.
2.05 PRECAST CONCRETE SLAB TOPS
A. Precast reinforced concrete slab tops shall be manufactured in accordance with ASTM
C478 or C913 as applicable. Openings and frames shall be provided for hatches where
shown on the Drawings. Slab tops shall be set in a full bed of mortar.
B. Slab tops shall be crowned or sloped to drain, minimum 1/4 inch per foot.
C. Concrete slab tops shall receive a non-slip broom finish and a penetrating concrete
sealer per Section 03 30 00.
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 4
2.06 PIPE SEALS
A. Where polyethylene, plastic or PVC pipe is utilized, connections between vault and pipes
shall be made with flexible rubber sleeves with stainless steel straps and bolts. Provide
an elastomeric waterstop gasket where sleeve sizes are not commercially available.
B. The annular space around the pipe wall or sleeve shall be packed with “Masterflow 713”
by Master Builders, “Five Star Grout” by U.S. Grout Corp.; or equal. Before the grout has
set, Contractor shall recheck invert elevations of the pipe.
C. For steel or ductile iron pipe, provide a pipe sleeve sized to accept the pipe plus a
modular mechanical seal such as Link Seal or equal.
2.07 HATCHES
A. Hatches shall be of the size and type shown on the Drawings and as described in Section
08 31 20 – Floor Access Doors.
1. Aluminum single leaf, watertight gasketed floor hatch. Floor hatch shall be furnished
with flush stainless steel hinges, aluminum stiffeners, and lockable slam latch.
Hatches shall have extended aluminum frame to match concrete thickness with
continuous anchor and shall be constructed of 1/4 inch minimum aluminum
diamond pattern plate design.
2. Hatches shall be provided with an auto-lock, hold-open device and torsion spring
assembly. All hardware, including all parts of the latch and lifting mechanism
assemblies, hold-open arms and guides, and all brackets, hinges, pins and fasteners
shall be stainless steel or bronze.
3. The hatches shall be designed for an H-20 wheel load. A 1-inch drain coupling shall
be provided in hatch frame. Contractor to extend drain to exterior of structure or to
sump pit at vaults intended to remain dry.
4. At all hatches, provide a hinged aluminum grate fall-through protection system.
5. Aluminum hatches shall be Bilco “PCM” or as manufactured by Washington
Aluminum Company or equal.
2.08 LADDER
A. Where shown on Drawings, provide ladder rungs made of cast iron or polypropylene with
steel reinforcement. Rungs shall be either cast in place or drilled and adhesive grouted in
the shop. Rungs are equally spaced at a maximum 12-inch spacing from the top of the
base slab to the top of the top slab.
B. Install ladder rungs so that the distance from the rungs to the finished wall is 7 inches.
C. Provide stainless steel ladder access safety post by Bilco, U.S.F. Fabrications, or equal.
2.09 OPENINGS AND INSERTS
A. All openings required in the concrete shall be reinforced with additional diagonal bars
tied to each layer of wall or slab reinforcement.
B. Any required pipe sleeves, inserts, and wall openings shall be coordinated with
mechanical requirements prior to casting the units.
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 5
2.10 WATERPROOFING
A. Around the exterior of all wall joints, apply the “Bituthene” primer and membrane
waterproofing system by W.R. Grace Company, or equal.
B. Exterior wall surfaces shall be waterproofed using manufacturer’s standard two-coat
system, specifically designed to waterproof the exterior of concrete surfaces in a below-
grade submerged condition.
C. For the top slab and above-grade exposed side walls, the concrete shall be sealed with
two coats of a penetrating concrete slab sealer.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that subgrade elevations for vault base is correct, excavation is dewatered, and
subgrade is pre-compacted.
B. Verify that rejected units have been removed from Site.
3.02 PREPARATION
A. Provide foundation mat of run-of-crusher stone to support base. Mat shall be 6 inches
minimum depth and shall bear on sound undisturbed earth; excavate and remove
subgrade material as necessary to reach sound subgrade.
B. Stone foundation mat shall be a minimum of 1 foot greater than the footprint of the vault
base, and shall be compacted to a uniform, level surface.
3.03 INSTALLATION
A. Vault shall be accurately located and uniformly supported on the foundation mat in a
level position.
B. Install wall sections in properly oriented position; follow manufacturer’s instructions for
joining together each section using the gaskets. Pack joints with grout.
C. Units shall be laid-up plumb and level.
D. Contractor is responsible for the integrity of all materials and protection against flotation
during the installation and backfilling process.
3.04 COATINGS
A. All exterior below-grade wall joints shall be sealed using a membrane waterproofing
system. Next, all below-grade wall surfaces shall be waterproofed, applied per
manufacturer’s instructions.
B. After installation is complete, the cover slab and interior walking surfaces shall be sealed
as specified above.
Lake Keowee to Adkins WTP Raw Water System Precast Concrete Vaults
154828 03 48 11 - 6
3.05 BACKFILLING
A. Backfill using well compacted structural fill material, being careful to not damage exterior
waterproof coating while providing full support under connecting pipes using compacted
bedding material.
B. During the one year warranty period, all visible leaks shall be sealed in an approved
manner.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Grouting
154828 03 60 00 - 1
SECTION 03 60 00
GROUTING
PART 1 GENERAL
1.01 DESCRIPTION
A. Section includes: Grout for column base plates, other structural supports, equipment
bases, surface repair and uses other than masonry. Grout for masonry is specified in
Section 04 20 00.
1.02 RELATED SECTIONS
A. This section contains specific references to the following related sections. Additional
related sections may apply that are not specifically listed below.
1. Section 43 05 13 Rigid Equipment Mounts
1.03 REFERENCES:
A. The references listed below are a part of this section. Where a referenced document
contains references to other standards, those documents are included as references
under this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of this
section shall prevail.
Reference Title
ASTM C230 Flow Table for Use in Tests of Hydraulic Cement
ASTM C307 Standard Test Method for Tensile Strength of Chemical-Resistant
Mortar, Grouts, and Monolithic Surfacings
ASTM C531 Standard Test Method for Linear Shrinkage and Coefficient of Thermal
Expansion of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings,
and Polymer Concretes
ASTM C579 Standard Test Methods for Compressive Strength of Chemical-Resistant
Mortars, Grouts, Monolithic Surfacings and Polymer Concretes
ASTM C882 Standard Test Method for Bond Strength of Epoxy-Resin Systems Used
with Concrete by Slant Shear
ASTM C942 Standard Test Method for Compressive Strength of Grouts for
Preplaced-Aggregate Concrete in the Laboratory
ASTM C1107 Packaged Dry, Hydraulic-Cement Grout (Non-shrink)
ASTM C1181 Standard Test Methods for Compressive Creep of Chemical-Resistant
Polymer Machinery Grouts
ASTM E329 Agencies Engaged in Construction Inspection, Testing, or Special
Inspection
COE CRD-C611 Flow of Grout for Preplaced Aggregate Concrete
COE CRD-C621 Non-shrink Grout
IBC International Building Code
Lake Keowee to Adkins WTP Raw Water System Grouting
154828 03 60 00 - 2
1.04 SUBMITTALS
A. Action Submittals
1. Procedure: Section 01 33 00:
2. A copy of this specification section with each paragraph check-marked to indicate
specification compliance or marked to indicate requested deviations from
specification requirements.
3. Check-marks (✓) shall denote full compliance with a paragraph as a whole.
Deviations shall be underlined and denoted by a number in the margin to the right of
the identified paragraph. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Include a
detailed, written justification for each deviation. Failure to include a copy of the
marked-up specification sections, along with justification(s) for any requested
deviations to the specification requirements, with the submittal shall be sufficient
cause for rejection of the entire submittal with no further consideration.
4. Complete product literature and installation instructions for the following:
Cementitious non-shrink grout, epoxy grout, adhesive for dowel and anchor setting,
and concrete repair mortar products to be used on the project.
5. Current ICC Evaluation Service reports for adhesives used for dowel and anchor
setting.
6. Installer certification in accordance with ACI/CRSI Adhesive Anchor Installer
Certification Program for installers of horizontal or upwardly inclined adhesive
anchors.
1.05 QUALITY ASSURANCE
A. Quality Control by Owner
1. The Owner will provide the services of a qualified Special Inspector in accordance
with Section 01 45 29.
2. Adhesive anchors installed in horizontal or upwardly inclined orientations to resist
sustained tension loads shall be continuously inspected during installation by a
Special Inspector.
a. The Special Inspector shall furnish a report to the Engineer, Owner’s
Representative and Building Official that the work covered by the report has been
performed and that the materials used and the installation procedures used
conform with the approved Project Manual and the Manufacturer’s Printed
Installation Instructions (MPII).
B. Quality Control by Contractor
1. Provide the services of an independent testing laboratory which complies with the
requirements of ASTM E329 if a product other than those listed below is proposed
and test data is not available from the supplier to demonstrate equivalence to the
specified grout. The testing laboratory shall sample and test the proposed grout
materials. Costs of testing laboratory services shall be borne by the Contractor.
C. Certifications
1. Installer certification shall be in accordance with ACI/CRSI Adhesive Anchor Installer
Certification Program for installers of horizontal or upwardly inclined adhesive
anchors.
Lake Keowee to Adkins WTP Raw Water System Grouting
154828 03 60 00 - 3
PART 2 PRODUCTS
2.01 CEMENTITIOUS NON-SHRINK GROUT
A. Cementitious non-shrink non-metallic aggregate grout shall be:
1. BASF, Masterflow 928
2. Euclid Chemical Company, Hi-Flow Grout
3. Five Star Products, Inc., Five Star Grout
4. Sika Corporation, SikaGrout 212
5. Approved Equal
2.02 EPOXY GROUT FOR EQUIPMENT MOUNTING:
A. Epoxy grout for equipment mounting shall be a non-cementitious, resin based, multi-
component formulation. Epoxy grout shall be flowable, with shrinkage minimized to
achieve minimum 98% effective bearing area. Epoxy grout shall be:
1. BASF, Masterflow 648
2. Euclid Chemical Company, E3-G
3. Sika Corporation, Sikadur 42
4. Approved Equal.
2.03 ADHESIVE FOR DOWEL AND ANCHOR SETTING
A. Adhesive for setting dowels and anchoring connection/base plate bolts shall be an
injectable two-component epoxy adhesive. Adhesive shall be approved for the intended
use per the product ICC Report. Adhesive shall be:
1. Hilti, HIT-RE 500-SD
2. Simpson Strong Tie, SET XP Anchoring Adhesive
3. Approved Equal (equivalent product must have ICC approval for use in cracked
concrete in areas with high seismic risk).
2.04 CONCRETE REPAIR MORTAR
A. Horizontal Applications: Repair mortars shall be:
1. BASF, MasterEmaco S 466CI
2. Sika Corporation, SikaTop 111 Plus
3. Approved Equal
B. Vertical and Overhead Applications: Repair mortars shall be:
1. BASF, MasterEmaco 1500HCR Vertical Overhead
2. Sika Corporation, SikaTop 123 Plus
3. Approved Equal
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine and accept existing conditions before beginning work.
Lake Keowee to Adkins WTP Raw Water System Grouting
154828 03 60 00 - 4
3.02 CEMENTITIOUS NONSHRINK GROUT
A. Non-shrink, cementitious, nonmetallic aggregate grout shall be used for column base
plates, structural bearing plates, and all locations where the general term “non-shrink
grout” is indicated on the Drawings. Use of this grout to support the bearing surfaces of
machinery shall be as specified in Section 43 05 13 or as detailed on the Drawings for
specific locations or pieces of equipment. If guidance is not provided in locations noted
above, use of non-shrink grout for equipment mounting shall be limited to equipment
less than 25 horsepower or 750 pounds. Grout shall be placed and cured in accordance
with the manufacturer's instructions.
B. Non-shrink cementitious grout shall not be used as a surface patch or topping. Non-
shrink cementitious grout must be used in confined applications only.
3.03 EPOXY GROUT FOR EQUIPMENT MOUNTING
A. Prepare concrete surfaces of equipment pads as indicated in details on the Drawings
and as required by the epoxy grout manufacturer. Epoxy grout for equipment mounting
shall be placed and cured in accordance with the requirements of Section 43 05 13,
details on the Drawings, and in conformance with manufacturer’s recommendations.
3.04 CONCRETE REPAIR MORTAR
A. Concrete repair materials and procedures shall be submitted for review to the Owner’s
Representative and shall be accepted prior to commencement of the repair work.
B. Follow all manufacturer's instructions, including those for minimum and maximum
application thickness, surface preparation and curing. Add aggregate as required per
manufacturer's recommendations. Any deviations from the manufacturer's instructions
shall be submitted for review to the Owner’s Representative and shall be accepted prior
to commencement of the work.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Zinc Coatings
154828 05 05 13.13 - 1
SECTION 05 05 13.13
ZINC COATINGS
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies both hot-dip zinc coating and mechanical zinc coating.
Electroplated corrosion protection is not an acceptable substitute for mechanical zinc
coating.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ASTM A123 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A143 Safeguarding Against Embrittlement of Hot-Dip Galvanized Structural
Steel Products and Procedure for Detecting Embrittlement
ASTM A153 Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A384 Safeguarding Against Warpage and Distortion During Hot-Dip
Galvanizing of Steel Assemblies
ASTM A385 Providing High-Quality Zinc Coatings (Hot-Dip)
ASTM A780 Repair of Damaged Hot-Dip Galvanized Coatings
ASTM B695 Coatings of Zinc Mechanically Deposited on Iron and Steel
MILSPEC DOD-P-21035 Paint, High Zinc Dust Content, Galvanizing Repair
1.03 SUBMITTALS
A. The following information shall be provided in accordance with Section 01 33 00:
1. Zinc dust-zinc oxide coating manufacturer's product data showing conformance to
the specified product.
2. Manufacturer's recommendation for application of zinc dust-zinc oxide coating.
Lake Keowee to Adkins WTP Raw Water System Zinc Coatings
154828 05 05 13.13 - 2
3. Coating applicator's Certificate of Compliance that the hot-dip galvanized coating
meets or exceeds the specified requirements of ASTM A123 or A153, as applicable.
PART 2 PRODUCTS
2.01 MATERIALS
A. Zinc Coating:
1. Hop-dip zinc coating material shall be as specified in ASTM A123 and A153, as
applicable. Mechanical zinc coating shall be as specified in ASTM B695.
B. Zinc Dust-Zinc Oxide Coating:
1. Zinc dust-zinc oxide coating shall conform to MILSPEC DOD-P-21035. Coating shall
be as manufactured by Z.R.C. Chemical Products Co., Galvicon Co., or equal.
2.02 FABRICATION REQUIREMENTS
A. Fabrication practices for products to be galvanized shall be in accordance with applicable
portions of ASTM A143, A384 and A385.
PART 3 EXECUTION
3.01 APPLICATION
A. Steel members, fabrications and assemblies shall be galvanized after fabrication in
accordance with ASTM A123.
B. Structural steel connection bolts, screws, nuts, washers shall be hot-dip galvanized per
ASTM A153.
3.02 COATING REQUIREMENTS
A. Hot-dip coating weight shall conform to paragraph 5.1 of ASTM A123 or Table 1 of ASTM
A153, as appropriate.
B. Mechanically applied coating thickness shall be Class 50 as specified in ASTM B695.
3.03 REPAIR OF DEFECTIVE GALVANIZED COATING
A. Where zinc coating has been damaged after installation, substrate surface shall be first
cleaned and then repaired with zinc dust-zinc oxide coating in accordance with ASTM
A780. Application shall be as recommended by the zinc dust-zinc oxide coating
manufacturer. Coating shall consist of multiple coats to dry film thickness of 8 mils.
B. Items not physically damaged, but which have insufficient or deteriorating zinc coatings,
and items damaged in shipment or prior to installation, shall be removed from the
project site for repair by the hot-dip zinc coating method.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 1
SECTION 05 05 20
ANCHOR BOLTS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Bolts and all-thread rods used to attach structural elements and
equipment to concrete. Included are cast-in-place and post-installed anchors (adhesive
systems and wedge type expansion anchors), nuts and washers.
B. Cast-in-place and post-installed anchors shall be Type 316 stainless steel unless noted
otherwise.
1.01 RELATED SECTIONS
A. This section contains specific references to the following related sections. Additional
related sections may apply that are not specifically listed below.
1. Section 03 60 00 Grouting
1.02 REFERENCES
A. The references listed below are a part of this section. Where a referenced document
contains references to other standards, those documents are included as references
under this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of this
section shall prevail.
Reference Title
ACI 318 Building Code Requirements for Structural Concrete
ASTM A193 Alloy-Steel and Stainless Steel Bolting for High Temperature or High
Pressure Service and Other Special Purpose Applications
ASTM A194 Carbon and Alloy Steel Nuts for Bolts for High Pressure or High Temperature
Service, or Both
ASTM A320 Alloy-Steel and Stainless Steel Bolting for Low-Temperature Service
ASTM A563 Carbon and Alloy Steel Nuts
ASTM F593 Stainless Steel Bolts, Hex Cap Screws, and Studs
ASTM F594 Stainless Steel Nuts
ASTM F844 Washers, Steel, Plain (Flat), Unhardened for General Use
ASTM F1554 Anchor Bolts, Steel, 36, 55, 105-ksi Yield Strength
IBC International Building Code with local amendments
1.03 SUBMITTALS
A. Action Submittals
1. Procedures: Section 01 33 00.
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 2
2. A copy of this specification section with each paragraph check-marked to indicate
specification compliance or marked to indicate requested deviations from
specification requirements.
3. Check-marks (✓) shall denote full compliance with a paragraph as a whole.
Deviations shall be underlined and denoted by a number in the margin to the right of
the identified paragraph. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Include a
detailed, written justification for each deviation. Failure to include a copy of the
marked-up specification sections, along with justification(s) for any requested
deviations to the specification requirements, with the submittal shall be sufficient
cause for rejection of the entire submittal with no further consideration.
4. Anchor bolt placement plans.
5. Anchor bolt, nut, and washer material information, including material certifications.
6. Record copy of design calculations and details showing the required diameter,
length, embedment, edge distance, confinement, anchor reinforcement, anchor bolt
sleeves, connection redesign, and other conditions, stamped and signed by a
Professional Engineer currently registered in the state of South Carolina.
7. Product Data:
a. ICC Evaluation Service Reports for post-installed adhesive type anchors and
expansion (wedge type) anchors when allowed. Products shall be ICC approved
for use in cracked concrete in high seismic areas (Seismic Design Category D, E
and F).
b. Product data indicating load capacity charts/calculations.
c. Chemical resistance.
d. Temperature limitations.
e. Manufacturers written installation instructions.
8. Installer certification for horizontal or upwardly inclined adhesive anchors in
accordance with ACI/CRSI Adhesive Anchor Installer Certification Program.
1.04 QUALITY ASSURANCE
A. Quality Assurance By Owner
1. Special inspection of anchor bolts shall be performed by the Special Inspector under
contract with the Owner and in accordance with IBC Chapter 17.
2. Adhesive anchors installed in horizontal or upwardly inclined orientations to resist
sustained tension loads shall be continuously inspected during installation by a
Special Inspector.
3. The Special Inspector shall furnish a report to the Engineer, Owner’s Representative,
and Building Official that the work covered by the report has been performed and
that the materials used and the installation procedures used conform with the
approved Project Manual and the Manufacturer’s Printed Installation Instructions
(MPII).
B. Certifications
1. Installer certification shall be in accordance with ACI/CRSI Adhesive Anchor Installer
Certification Program for installers of horizontal or upwardly inclined adhesive
anchors.
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 3
PART 2 PRODUCTS
2.01 GENERAL
A. Anchor bolt holes in equipment support frames shall not exceed the bolt diameters by
more than 1/4 inch. Minimum anchor bolt diameter shall be 1/2 inch. Anchor bolts for
equipment mounting and vibration isolation systems shall be provided as specified.
B. Tapered washers shall be provided where mating surface is not square with the nut.
C. Anchor bolts shall be cast-in-place anchors unless post-installed anchors are specified or
shown on the Drawings. Substitution of post-installed anchors will not be permitted
unless specifically requested by the Contractor and approved by the Engineer.
2.02 PERFORMANCE/DESIGN CRITERIA
A. Anchor bolts for equipment shall be designed by the equipment manufacturer to include
equipment operational loads combined with seismic and wind forces when applicable.
Design criteria provided in Section 01 73 24.
2.03 MATERIALS
A. Anchor bolt materials shall be as specified in the following table:
Material Specification
Stainless Steel Anchor Bolts ASTM A193 or A320, Type 316
Stainless Steel Threaded Rods ASTM F593, Type 316
Stainless Steel Nuts and Washers ASTM A194 Heavy Hex Nuts and Washers, Type 316
ASTM F594 Heavy Hex Nuts at Adhesive Anchors, Type 316
Carbon Steel Anchor Bolts ASTM F1554, Grade 36, Hot Dip Galvanized
High-Strength Carbon Steel Anchor Bolts ASTM F1554, Grade 55, Weldable per Supplementary
Requirement S1, Hot Dip Galvanized
Carbon Steel Nuts and Washers ASTM A563 and F844, Heavy Hex, Hot-Dip Galvanized
Concrete Adhesive Anchors
Hilti “HIT-RE 500-SD”, Simpson “SET-XP”, or approved equal,
with Type 316 Stainless Steel threaded rods
Masonry Adhesive Anchors Hilti "HIT-HY 70", Simpson “SET”, or approved equal, with Type
316 Stainless Steel threaded rods
Masonry Expansion (wedge) Anchors* Hilti "KWIK BOLT 3", or approved equal, Type 316 Stainless
Steel
Concrete Expansion (wedge) Anchors * Hilti “KWIK BOLT TZ”, or approved equal, Type 316 Stainless
Steel
*Post installed anchors shall always be an adhesive type anchor system except where noted otherwise or
when Contractor makes a request for a specific application and Engineer approves.
2.04 STAINLESS STEEL FASTENER LUBRICANT (ANTI-SEIZING)
A. Anti-seizing Lubricant for Stainless Steel Threaded Connections:
1. Formulated to resist washout.
2. Acceptable manufacturers are Bostik, Saf-T-Eze, or equal.
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 4
2.05 ANCHOR BOLT SLEEVES
A. Provide anchor bolt sleeves as shown on design drawings and as required by equipment
manufacturer’s design.
1. Provide high density polyethylene plastic sleeves of single unit construction with
deformed sidewalls such that the concrete and grout lock in place.
2. The top of the sleeve shall be self-threading to provide adjustment of the threaded
anchor bolt projection.
3. Acceptable manufacturers are Contec, Wilson, or equal.
PART 3 EXECUTION
3.01 GENERAL
A. Anchor bolts shall be cast-in-place anchors unless post-installed anchors are specified or
shown on the Drawings.
B. Grouting of anchor bolts using plastic sleeves with non-shrink or epoxy grout, where
specified, shall be in accordance with Section 03 60 00.
C. The threaded end of anchor bolts and all-thread rods shall be long enough to project
through the entire depth of the nut and if too long, shall be cut off at ½-inch beyond top
of nut and ground smooth.
3.02 CAST-IN-PLACE ANCHOR BOLTS
A. Anchor bolts to be embedded in concrete shall be placed accurately and held in correct
position using templates while the concrete is placed.
B. After anchor bolts have been embedded, their threads shall be protected by grease and
the nuts run on.
3.03 ADHESIVE ANCHOR BOLTS
A. Note that adhesive anchors shall not be substituted for cast-in-place anchor bolts unless
the adhesive anchors have been specified or shown on the Drawings, or approval has
been obtained from the Engineer that substitution of adhesive anchors is acceptable for
the specific use and location. Use of adhesive anchors shall be subject to the following
conditions:
1. Limit to locations where intermittent or continuous exposure to the following is
extremely unlikely:
a. Acid concentrations higher than 10 percent
b. Chlorine gas
c. Machine or diesel oils
2. Limit to applications where exposure to the following is extremely unlikely:
a. Fire
b. Concrete or rod temperature above 120 degrees F
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 5
3. Overhead applications (such as pipe supports) shall not be allowed unless approved
by the Engineer and installation is by an Installer specially certified for overhead
applications.
4. Approval from Engineer for specific application and from supplier of equipment to be
anchored, if applicable.
5. Anchor diameter and material shall be per Contract Documents or equipment
manufacturer’s specifications. Anchor shall be threaded or deformed the full length
of embedment and shall be free of rust, scale, grease, and oils.
6. Embedment depth shall be as specified or as required by the equipment
manufacturer.
7. Follow the anchor system manufacturer’s installation instructions.
8. Holes shall have rough surfaces created by using a hammer drill with carbide bit.
Core drilled holes are not allowed.
9. Holes shall be blown clean with oil-free compressed air and be free of dust or
standing water prior to installation. Follow additional requirements of the adhesive
manufacturer.
10. Concrete and air temperature shall be compatible with curing requirements of
adhesives per adhesive manufacturer’s instructions. Anchors shall not be placed in
concrete when the temperature is below 25 degrees F.
11. Anchors shall be left undisturbed and unloaded for full adhesive curing period, which
is based on temperature of the concrete.
3.04 EXPANSION ANCHORS
A. Expansion (wedge type) anchors shall not be substituted for cast-in-place anchor bolts or
adhesive anchors unless approved by the Engineer for a specific application. Use of
expansion anchors shall be subject to conditions 4 through 9 as specified above for
adhesive anchors. Expansion anchors shall not be used in a submerged condition or in
mounting of equipment subject to vibration or cyclic motion.
3.05 REINFORCING STEEL CONFLICTS WITH POST-INSTALLED ANCHOR INSTALLATION
A. When reinforcing steel is encountered in the drill path, slant drill to clear obstruction and
provide beveled washer to match angle of anchor. Drill shall not be slanted more than 10
degrees.
B. Where slanting the drill does not resolve the conflict, notify the Owner’s Representative
and resolve the conflict to the satisfaction of the Owner’s Representative in consultation
with the Engineer.
C. Abandoned post-installed anchor holes shall be cleaned and filled with non-shrink grout
and struck off flush with adjacent surface.
D. The costs of determining and executing the resolution shall be borne by the Contractor.
The determination and execution of the resolution shall not result in additional cost to
the Owner.
E. Reinforcing steel in masonry shall not be damaged.
Lake Keowee to Adkins WTP Raw Water System Anchor Bolts
154828 05 05 20 - 6
F. In order to avoid or resolve a conflict, locate embedded reinforcing steel using non-
destructive methods and/or redesign the attachment.
1. Redesign shall be done by the Contractor’s Professional Engineer currently registered
in the state of South Carolina.
2. Calculations and details for redesign shall be submitted.
END OF SECTION
DIVISION 07
THERMAL AND MOISTURE PROTECTION
Section Title
07 91 26 JOINT FILLERS
07 92 00 JOINT SEALANTS
Lake Keowee to Adkins WTP Raw Water System Joint Fillers
154828 07 91 26 - 1
SECTION 07 91 26
JOINT FILLERS
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies preformed joint fillers.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
ASTM D994 Preformed Expansion Joint Filler for Concrete (Bituminous Type)
ASTM D1752 Preformed Sponge Rubber and Cork Expansion Joint Fillers for Concrete Paving and
Structural Construction
PART 2 PRODUCTS
2.01 PREFORMED ASPHALT FIBERBOARD
A. Preformed asphalt fiberboard joint filler shall be in accordance with ASTM D994 and
shall be 1/2 inch thick unless otherwise specified.
2.02 PREFORMED RESIN-BONDED CORK
A. Preformed resin-bonded cork joint filler shall be in accordance with ASTM D1752, Type II.
Cork joint filler thickness shall match the specified joint width.
2.03 PRODUCT DATA
A. The following information shall be provided in accordance with Section 01 33 00:
1. Manufacturer's recommendations for handling and installation of the material.
Lake Keowee to Adkins WTP Raw Water System Joint Fillers
154828 07 91 26 - 2
PART 3 EXECUTION
3.01 GENERAL
A. Preformed joint fillers shall be placed into position before the concrete is poured. Where
it is necessary for the filler to be fixed to existing concrete or other building materials, a
suitable adhesive recommended by the filler manufacturer shall be used. Filler surfaces
shall be clean and dry prior to the placement of the concrete.
3.02 PREFORMED ASPHALT FIBERBOARD
A. Preformed asphalt fiberboard joint fillers shall be used for expansion joints in concrete
sidewalks, curbs, and roadways.
3.03 PREFORMED RESIN-BONDED CORK
A. Preformed resin-bonded cork joint filler shall be used for expansion joints in concrete
structures. The expansion joint shall be sealed with backer rod and sealant as specified
in Section 07 92 00.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Joint Sealants
154828 07 92 00 - 1
SECTION 07 92 00
JOINT SEALANTS
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies joint sealants.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
FEDSPEC TT-S-00230C Sealing Compound: Elastomeric Type, Single Component
FEDSPEC TT-S-00227E Sealing Compound: Elastomeric Type, Multi-Component
PART 2 PRODUCTS
2.01 POLYURETHANE SEALANT
A. Acceptable Products:
1. Acceptable products shall be Sikaflex by Sika Chemical Corporation, Vulkem by
Mameco International, U-Seal Joint Sealant by Burke Company, or Rubber Calk by
Products Research and Chemical Corporation.
B. General:
1. Polyurethane sealants shall conform to FEDSPEC TT-S-0230C for one-component
systems and FEDSPEC TT-S-00227E for two-component systems. Polyurethane
sealant shall be one of the following two types.
a. Self-Leveling:
1) Self-leveling polyurethane sealant shall be Type I, Class A as specified by the
FEDSPECs referenced above.
b. Nonsag:
Lake Keowee to Adkins WTP Raw Water System Joint Sealants
154828 07 92 00 - 2
1) Nonsag polyurethane sealant shall be Type II, Class A as specified by the
FEDSPECs referenced above.
C. Primer:
1. Primer shall be as recommended by the sealant manufacturer.
D. Backer Rod or Backer Tape:
1. Backer rod shall be open cell polyethylene or polyurethane foam. Rod shall be
cylindrical unless otherwise specified. Backer tape shall be polyethylene or
polyurethane with adhesive on one side.
2.02 MASTIC SEALANT
A. General:
1. Mastic joint sealant shall consist of a blend of refined asphalts, resins and
plasticizing compounds, reinforced with fiber. Sealant shall be compatible with joint
fillers and shall be pressure grade.
B. Primer:
1. Primer shall be as recommended by the mastic sealant manufacturer.
2.03 PRODUCT DATA
A. The following information shall be provided in accordance with Section 01 33 00:
1. Manufacturer's product data showing conformance to the specified products.
2. Manufacturer's recommendations for storage, handling and application of sealants
and primers.
PART 3 EXECUTION
3.01 GENERAL
A. Sealants and primers shall be applied according to the sealant manufacturer's
recommendations. Polyurethane sealants shall be used on all expansion joints and
specified construction joints.
B. Joints and spaces to be sealed shall be clean, dry and free of dust, loose mortar,
concrete and plaster. Additional preparation of joints and spaces shall be provided in
accordance with manufacturer's recommendations. Primer shall be applied only to the
surfaces that will be covered by the sealant.
3.02 POLYURETHANE SEALANTS
A. General:
1. Nonsag polyurethane sealants shall be used on vertical joints. Self-leveling
polyurethane sealants shall be used on horizontal joints.
B. Joint Dimensions:
1. Unless otherwise specified, joints and spaces to be filled shall be constructed to the
following criteria. Joints and spaces shall have a minimum width of 1/4 inch and a
Lake Keowee to Adkins WTP Raw Water System Joint Sealants
154828 07 92 00 - 3
maximum width of 1 inch. The depth of the sealant shall be one-half the width of the
joint, but in no case less than 1/4 inch deep. Sealant depth shall be measured at the
point of smallest cross section. When joints exceed the depth requirements, backing
rod shall be inserted to provide the joint depth specified. If the joint sealant depth is
within the specified tolerances, backer tape shall be placed in the bottom of the joint.
3.03 MASTIC SEALANT
A. Joint Dimensions:
1. Joints to be sealed shall be 2 inches deep, 1 inch wide at the top, and 3/4 inch wide
at the base.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Floor Access Doors
154828 08 31 20 - 1
SECTION 08 31 20
FLOOR ACCESS DOORS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Factory-fabricated single or double leaf aluminum floor access doors
and frames with water drainage. Include telescoping ladder safety post, and fall
protection grating system.
1.02 REFERENCES
A. The references listed below are a part of this section. Where a referenced document
contains references to other standards, those documents are included as references
under this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of this
section shall prevail.
Reference Title
ASTM B221 Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
ASTM B632 Aluminum-Alloy Rolled Tread Plate
ASTM A240 Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for
Pressure Vessels and for General Applications
ASTM F593 Stainless Steel Bolts, Hex Cap Screws, and Studs
ASTM F594 Stainless Steel Nuts
AASHTO American Association of State Highway and Transportation Officials
OSHA U.S. Dept. of Labor, Occupational Safety and Health Administration
1.03 SUBMITTALS
A. Action Submittals:
1. Procedures: Section 01 33 00.
2. A copy of this specification section with each paragraph check-marked to indicate
specification compliance or marked to indicate requested deviations from
specification requirements.
3. Check-marks (✓) shall denote full compliance with a paragraph as a whole.
Deviations shall be underlined and denoted by a number in the margin to the right of
the identified paragraph. The remaining portions of the paragraph not underlined will
signify compliance on the part of the Contractor with the specifications. Include a
detailed, written justification for each deviation. Failure to include a copy of the
marked-up specification sections, along with justification(s) for any requested
deviations to the specification requirements, with the submittal shall be sufficient
cause for rejection of the entire submittal with no further consideration.
4. Statement of experience for both manufacturer and installer.
5. Fabrication drawings showing layouts, connections to structure, and anchoring
details.
Lake Keowee to Adkins WTP Raw Water System Floor Access Doors
154828 08 31 20 - 2
6. Erection and installation drawings showing construction details, reinforcement,
anchorage, and installation with relation to the building construction.
7. Drain pipe layout from the drain coupling to the discharge point.
B. Informational Submittals:
1. Manufacturer's product data showing conformance to the specification.
2. Structural calculations for the floor access door design provided by the manufacturer
and sealed by a registered professional engineer registered in the State of South
Carolina.
3. Instructions for the storage, handling, installation, and operation.
4. Manufacturer’s warranty.
1.04 QUALITY ASSURANCE
A. Manufacturer: Minimum of 5 years’ experience manufacturing similar products.
B. Installer: Minimum of 2 years’ experience installing similar products.
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver materials in manufacturer’s original packaging, stored in a dry, protected, well-
vented area. Inspect product upon receipt and report damage to carrier and
manufacturer.
1.06 SPECIAL WARRANTY
A. Materials shall be free of defects in material and workmanship for a period of 5 years
from the date of purchase. Should a part fail to function in normal use within this period,
manufacturer shall furnish a new part at no charge.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. The following manufacturers are acceptable. The manufacturer’s standard product may
require modification to conform to specified requirements.
1. The Bilco Company.
2. Babcock Davis.
3. Halliday Products.
4. East Jordan Iron Works (EJ).
5. Approved Equal.
2.02 PERFORMANCE/DESIGN CRITERIA
A. Door leafs shall be reinforced to support a minimum live load of 300 psf or AASHTO
H-20 wheel load with a maximum deflection of 1/150th of the span. See Floor Access
Door Schedule at the end of this section, which indicates loading criteria required at each
location.
Lake Keowee to Adkins WTP Raw Water System Floor Access Doors
154828 08 31 20 - 3
B. Nominal opening sizes and hinge opening side shall be as noted on the Drawings and in
the Floor Access Door Schedule.
2.03 MATERIALS
A. Access doors, single or double leaf: 1/4 inch minimum aluminum with diamond tread
pattern; ASTM B632, 6061-T6.
B. Channel frame shall be 1/4 inch minimum extruded aluminum with bent down anchor
tabs around the perimeter: ASTM B221, 6061-T6.
C. Hardware: ASTM A240 Type 316 stainless steel throughout.
D. Fasteners:
1. Bolts: ASTM F593
2. Nuts: ASTM F594
2.04 COMPONENTS/ FEATURES
A. Manufacturer shall provide the required number and size of compression spring
operators enclosed in telescopic tubes to provide, smooth, easy, and controlled door leaf
operation throughout the entire arc of opening; and to act as a check in retarding
downward motion of the cover when closing.
B. Spring tubes shall be constructed of a reinforced nylon 6/6-based engineered composite
material. The upper tube shall prevent accumulation of moisture, grit, and debris inside
the lower tube assembly. The lower tube shall interlock with a flanged support shoe
fastened to a formed 1/4 inch gusset support plate.
C. Door leafs shall be equipped with a hold-open arm which automatically locks the door in
the open position. A removable exterior turn/lift handle with a spring loaded ball detent
shall be provided to open the door and the latch release shall be protected by a flush,
gasketed, removable screw plug. A stainless steel snap lock with fixed handle shall be
mounted on the underside of the door.
D. Provide heavy forged aluminum hinges with 1/4 inch minimum diameter stainless steel
pins.
1. Hinges must operate in such a manner to prevent the door leafs from protruding into
the channel frame.
2. Design hinges specifically for horizontal installation.
3. Hinges shall be through-bolted to the cover with tamperproof stainless steel lock
bolts and through-bolted to the frame with stainless steel bolts and locknuts.
E. A continuous ethylene propylene diene monomer (EPDM) gasket shall be mechanically
attached to the aluminum frame to create a barrier around the entire perimeter of the
cover and significantly reduce the amount of dirt and debris that may enter the channel
frame.
F. A 1.5 inch drain coupling shall be provided.
Lake Keowee to Adkins WTP Raw Water System Floor Access Doors
154828 08 31 20 - 4
G. Provide telescoping ladder safety posts for easy, safe ladder access through the access
door openings.
1. Material: Stainless steel.
2. Telescoping post to be permanently mounted to the top two rungs of fixed ladders.
3. Post must automatically lock in the fully raised position to provide the user with a
firm and steady hand-hold.
4. Post to have release lever that allows the post to be easily lowered to its retracted
position.
H. Provide a fall protection grating system where indicated in the Floor Access Door
Schedule. Manufacturer shall install the grating system when the door is fabricated.
1. Design Criteria: Meet OSHA 29 CFR 1910.23 requirements for fall protection.
2. Grating panel material: Aluminum with powder coat paint finish.
3. Grating panel color: High visibility OSHA safety yellow or orange.
4. Grating panel shall lock automatically in the full open position.
5. Grating panel shall lift open in the opposite direction as the door(s).
6. Hold open feature: Stainless steel hold open device shall be provided to lock the
cover in the fully open 90 degree position.
7. Lift mechanism and hardware: Stainless steel lifting mechanisms as specified above
for all fall protection panels that weigh over 50 pounds.
8. Grating openings: Reinforced with easy-open aluminum covers for removal of
instrumentation below access doors.
2.05 FINISHES
A. Door and frame: Mill finish aluminum with heavy bituminous coating where in contact
with concrete.
B. Telescopic safety post: aluminum or stainless steel.
C. Springs: Electro-coated acrylic finish.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine substrates and openings for compliance with requirements for installation
tolerances and other conditions affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 INSTALLATION
A. Installation shall conform to the manufacturer’s recommendations.
B. Frame shall be accurately cast in place and securely anchored to concrete. Installation of
access doors after concrete is placed is not allowed.
Lake Keowee to Adkins WTP Raw Water System Floor Access Doors
154828 08 31 20 - 5
C. Set frame level, plumb and in proper alignment with adjacent work.
D. Contractor shall field route a 1.5 inch Schedule 80 PVC drain pipe from the 1.5 inch
drain coupling on all access doors to the water or floor level below. Place drain pipe clear
of the access area below the door and as approved by the Owner’s Representative.
3.03 REPAIR/RESTORATION
A. Repair finishes damaged during installation.
B. Remove and replace doors that are warped, bowed, or otherwise damaged.
3.04 ADJUSTING
A. Adjust doors and hardware after installation for proper operation.
3.05 CLEANING
A. Clean exposed surfaces using methods acceptable to the manufacturer that will not
damage finish.
3.06 FLOOR ACCESS DOOR SCHEDULE
Floor Access Doors
Mark Location Clear Opening
Size 1
Leafs Loading Fall
Protection
Grating
Comments
H-01 Interconnect Site 2 2’-6” x 4’-0” Double H-20 Yes Drain channel to sump.
Note:
1. Clear opening is defined as the dimensions such that objects can pass through the floor access door. Lifting and other
hardware shall be outside of the opening dimensions.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 1
SECTION 09 90 00
PAINTING AND COATING
TABLE OF CONTENTS
PART 1 GENERAL ......................................................................................................................................... 3
1.01 DESCRIPTION ............................................................................................................................... 3
A. Scope: ...................................................................................................................................... 3
B. Definitions: .............................................................................................................................. 3
1.02 QUALITY ASSURANCE .................................................................................................................. 5
A. References: ............................................................................................................................. 5
B. Standardization: ...................................................................................................................... 7
C. Quality Control Requirements: ............................................................................................... 7
D. Inspection at Hold Points: ...................................................................................................... 8
1.03 DELIVERY AND STORAGE ............................................................................................................ 9
A. General: ................................................................................................................................... 9
1.04 SUBMITTALS: ................................................................................................................................ 9
A. General: ................................................................................................................................... 9
1.05 RESPONSIBILITIES OF THE CTR ............................................................................................... 11
A. General: ................................................................................................................................ 11
B. Coating System Installation Training: ................................................................................. 11
C. Coating System Inspection: ................................................................................................. 11
D. Final Report: ......................................................................................................................... 12
PART 2 PRODUCTS .................................................................................................................................... 12
2.01 MATERIALS ................................................................................................................................ 12
A. General: ................................................................................................................................ 12
Material Requirements for Coating Systems: All of U.S. Except California .................... 12
2.02 PRODUCT DATA ......................................................................................................................... 13
A. General: ................................................................................................................................ 13
PART 3 EXECUTION ................................................................................................................................... 13
3.01 COATINGS .................................................................................................................................. 13
A. General: ................................................................................................................................ 13
B. Shop and Field Coats: .......................................................................................................... 14
C. Application Location Requirements: ................................................................................... 14
3.02 PREPARATION ........................................................................................................................... 15
A. General: ................................................................................................................................ 15
B. Blast Cleaning: ..................................................................................................................... 15
C. Solvent Cleaning: ................................................................................................................. 16
D. Metallic Surfaces: ................................................................................................................ 16
E. Concrete Surfaces: .............................................................................................................. 17
F. Masonry Surfaces: ............................................................................................................... 18
G. Fiberglass Reinforced Plastic (FRP) Surfaces: ................................................................... 18
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 2
3.03 APPLICATION ............................................................................................................................. 18
A. Workmanship: ...................................................................................................................... 18
B. Coating Properties, Mixing and Thinning: ........................................................................... 19
C. Atmospheric Conditions: ..................................................................................................... 19
D. Concrete Substrate Temperatures and Detail Treatment: ................................................ 19
E. Protection of Coated Surfaces: ........................................................................................... 20
F. Method of Coating Application: ........................................................................................... 20
G. Film Thickness and Continuity: ........................................................................................... 20
H. Special Requirements: ........................................................................................................ 21
I. Electrical and Instrumentation Equipment and Materials: ............................................... 21
J. Soluble Salt Contamination of Metallic Substrates: .......................................................... 21
3.04 CLEANUP ................................................................................................................................... 22
A. General: ................................................................................................................................ 22
3.05 COATING SYSTEM SPECIFICATION SHEETS (COATSPEC) ....................................................... 22
A. General: ................................................................................................................................ 22
Table A Coating Specification Sheets ............................................................................... 22
Coating System Specification Sheets (COATSPEC) .......................................................... 23
A. Coating System Identification: E-1 ............................................................................. 23
B. Coating System Identification: E-2 ............................................................................. 23
C. Coating System Identification: EU-1 ........................................................................... 24
D. Coating System Identification: M-1 ............................................................................ 25
3.06 COATING SYSTEMS SCHEDULE (FINISH SCHEDULE) ............................................................. 25
A. General: ................................................................................................................................ 25
Coating Systems Schedule (Finish Schedule) .................................................................. 26
A. General: All Surfaces not Specified by Area or Structure ......................................... 26
3.07 INSPECTION AND TESTING BY OWNER ................................................................................... 26
A. General: ................................................................................................................................ 26
3.08 FINAL INSPECTION .................................................................................................................... 27
A. General ................................................................................................................................. 27
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 3
SECTION 09 90 00
PAINTING AND COATING
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This Section specifies coating systems, surface preparations, and application
requirements for coating systems.
B. Definitions:
1. Specific coating terminology used in this Section is in accordance with definitions
contained in ASTM D16, ASTM D3960, and the following definitions.
a. Definitions:
1) Abrasive: Material used for blast cleaning, such as sand, grit or shot.
2) Abrasive Blast Cleaning: Cleaning/surface preparation by abrasive propelled
at high speed.
3) Anchor Pattern: Profile or texture of prepared surface(s).
4) ANSI: American National Standards Institute.
5) Bug Holes: Small cavities, usually not exceeding 15 mm in diameter, resulting
from entrapment of air bubbles in the surface of formed concrete during
placement and compaction.
6) Coating/Paint/Lining Thickness: The total thickness of primer, intermediate
and/or finish coats.
7) Coating System Applicator (CSA): A generic reference to the specialty
subcontractor or subcontractors retained by the Contractor to install the
coating systems specified in this Section.
8) Coating System Manufacturer (CSM): Refers to the acceptable coating
system manufacturer, abbreviated as the CSM.
9) Coating System Manufacturer’s Technical Representative(s) (CTR): Refers to
the technical representative(s) of the acceptable Coating System
Manufacturer and is abbreviated as CTR.
10) Dew point: Temperature of a given air/water vapor mixture at which
condensation starts.
11) Dry Film Thickness (DFT): Depth of cured film, usually expressed in mils
(0.001 inch). Use this definition as opposed to existing definition.
12) Drying Time: Time interval between application and curing of material.
13) Dry to Recoat: Time interval between application of material and ability to
receive next coat.
14) Dry to Touch: Time interval between application of material and ability to
touch lightly without damage.
15) Feather Edging: Reducing the thickness of the edge of paint.
16) Feathering: Operation of tapering off the edge of a point with a comparatively
dry brush.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 4
17) Field Coat: The application or the completion of application of the coating
system after installation of the surface at the site of the work.
18) Hold Point: A defined point, specified in this Section, at which work shall be
halted for inspection.
19) Holiday: a discontinuity, skip, or void in coating or coating system film that
exposes the substrate.
20) Honeycomb: Segregated condition of hardened concrete due to non-
consolidation.
21) ICRI: International Concrete Repair Institute.
22) Incompatibility: Inability of a coating to perform well over another coating
because of bleeding, poor bonding, or lifting of old coating; inability of a
coating to perform well on a substrate.
23) Laitance: A layer of weak, non-durable concrete containing cement fines that
is brought to the surface through bleed water because of concrete finishing
and/or over-finishing.
24) Mil: 0.001 inch.
25) NACE: National Association of Corrosion Engineers.
26) Overspray: Dry spray, particularly such paint that failed to strike the intended
surface.
27) Pinhole: A small diameter discontinuity in a coating or coating system film
that is typically created by outgassing of air from a void in a concrete
substrate resulting in exposure of the substrate or a void between coats.
28) Pot Life: Time interval after mixing of components during which the coating
can be satisfactorily applied.
29) Resurfacer/Resurfacing Material: A layer of cementitious and/or resin-base
material used to fill or otherwise restore surface continuity to worn or
damaged concrete surfaces.
30) Shelf Life: Maximum storage time for which a material may be stored without
losing its usefulness.
31) Shop Coat: One or more coats applied in a shop or plant prior to shipment to
the site of the work, where the field or finishing coat is applied.
32) Spreading Rate: Area covered by a unit volume of paint at a specific
thickness.
33) SSPC: The Society for Protective Coatings.
34) Stripe Coat: A separate coat of paint applied to all weld seems, pits,
nuts/bolts/washers and edges by brush. This coat shall not be applied until
any previous coat(s) have cured and, once applied, shall be allowed to cure
prior to the application of the subsequent coat(s).
35) Surface Saturated Dry (SSD): Refers to concrete surface condition where the
surface is saturated (damp) without the presence of standing water.
36) Tie Coat: An intermediate coat used to bond different types of paint coats.
Coatings used to improve the adhesion of a succeeding coat.
37) Touch-Up Painting: The application of paint on areas of painted surfaces to
repair marks, scratches, and areas where the coating has deteriorated to
restore the coating film to an unbroken condition.
38) TPC: Technical Practice Committee.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 5
39) Volatile Organic Compound (VOC) Content: The portion of the coating that is a
compound of carbon, is photochemically reactive, and evaporates during
drying or curing, expressed in grams per liter (g/l) or pounds per gallon
(lb/gal).
40) Immersion: Refers to a service condition in which the substrate is below the
waterline or submerged in water or wastewater at least intermittently if not
constantly.
41) Weld Splatter: Beads of metal scattered near seam during welding.
42) Wet Film Thickness (WFT): The primer or coating film’s thickness immediately
following application. Wet film thickness is measured in mils or thousandths
of an inch (0.001 inch) and is abbreviated WFT.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued, or replaced.
Reference Title
ANSI/ASC 29.4
Exhaust Systems
Abrasive Blasting Operations – Ventilation and Safe Practice
ANSI/NSF 61 Drinking Water System Components Health Effects
ANSI B74.18 Grading of Certain Abrasive Grain on Coated Abrasive Material
ASTM D16 Standard Terminology for Paint, Related Coatings, Materials, and Applications
ASTM D2200
(SSPC-VIS1)
Pictorial Surface Preparation Standards for Painting Steel Surfaces
ASTM D3960 Standard Practice for Determining Volatile Organic Compound (VOC) Content of Paints and
Related Coatings
ASTM D4262 Standard Test Method for pH of Chemically Cleaned or Etched Concrete Surfaces
ASTM D4263 Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method
ASTM D4414 Standard Practice for Measurement of Wet Film Thickness by Notch Gages
ASTM D4417 Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel
ASTM D4541 Standard Test Methods for Pull-Off Strength of Coatings On Metal Substrates Using
Portable Adhesion Testers
ASTM D4787 Standard Practice for Continuity Verification of Liquid or Sheet Linings Applied to Concrete
Substrates
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 6
Reference Title
ASTM D5162 Standard Practice for Discontinuity (Holiday) Testing of Nonconductive Protective Coating
on Metallic Substrates
ASTM D7234 Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using
Portable Adhesion Testers.
ASTM E337 Standard Test Method for Measuring Humidity With a Psychrometer
ASTM F1869 Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor
Using Anhydrous Calcium Chloride
FS 595b Federal Standard Colors
ICRI 03732 Guideline for Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings,
and Polymer Overlays
NACE Publication 6D-163 A Manual for Painter Safety
NACE Publication 6F-163 Surface Preparation of Steel or Concrete Tank/Interiors
NACE Publication 6G-164 A Surface Preparation Abrasives for Industrial Maintenance Painting
NACE Standards January 1988 Edition of the National Association of Corrosion Engineers, TPC.
NACE Standard RP0188 Standard Recommended Practice – Discontinuity (Holiday) Testing of New Protective
Coatings on Conductive Substrates
NACE Standard RP0288 Standard Recommended Practice, Inspection of Linings on Steel and Concrete
NACE Standard RP0892 Standard Recommended Practice, Linings Over Concrete in Immersion Service
NACE Publication TPC2 Coatings and Linings for Immersion Service
NAPF 500-03 Surface Preparation Standard for Ductile Iron Pipe and Fittings in Exposed Locations
Receiving Special External Coatings and/or Special Internal Linings
NAPF 500-03-04 Abrasive Blast Cleaning for Ductile Iron Pipe
NAPF 500-03-05 Abrasive Blast Cleaning for Cast Ductile Iron Fittings
OSHA 1910.144 Safety Color Code for Marking Physical Hazards
OSHA 1915.35 Standards – 29CFR - Painting
SSPC Paint Application Specification No. 1.
SSPC-AB 1 Mineral and Slag Abrasives
SSPC-PA 1 Shop, Field, and Maintenance Painting of Steel
SSPC-PA 2 Measurement of Dry Coating Thickness with Magnetic Gages
SSPC-PA 9 Measurement of Dry Coating Thickness on Cementitious Substrates Using Ultrasonic
Gages
SSPC-PA Guide 1 Guide for Illumination of Industrial Painting Project
SSPC-PA Guide 3 A Guide to Safety in Paint Application
SSPC-PA Guide 6 Guide for Containing Debris Generated During Paint Removal Operations
SSPC-PA Guide 11 Guide for Coating Concrete
SSPC SP1 Solvent Cleaning
SSPC SP2 Hand Tool Cleaning
SSPC SP3 Power Tool Cleaning
SSPC SP5 White Metal Blast Cleaning
SSPC SP6 Commercial Blast Cleaning
SSPC SP7 Brush-Off Blast Cleaning
SSPC SP10 Near-White Blast Cleaning
SSPC SP11 Power Tool Cleaning to Bare Metal
SSPC SP12 Surface Preparation and Cleaning of Steel and Other Hard Materials by High and Ultra-High
Pressure Water Jetting Prior to Recoating
SSPC SP13 Surface Preparation of Concrete
SSPC-TR2 Wet Abrasive Blast Cleaning
SSPC-TU-3 Overcoating
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 7
Reference Title
SSPC-TU-4 Field Methods for Retrieval and Analysis of Soluble Salts on Substrates.
SSPC V2 Systems and Specifications: Steel Structures Painting Manual, Volume 2
SSPC-VIS 1 Visual Standard for Abrasive Blast Cleaned Steel
SSPC-VIS 3 Visual Standard for Power and Hand – Tool Cleaned Steel
SSPC-VIS 4 Visual Standards (Waterjetting)
SSPC-VIS 5 Visual Standards (Wet Abrasive Blast Cleaning)
WPCF Manual of Practice No.
17
Paints and Protective Coatings for Wastewater Treatment Facilities. Guide and Paint
Application Specifications.
B. Standardization:
1. Materials and supplies provided shall be the standard products of CSMs. Materials in
each coating system shall be the products of a single CSM.
2. The standard products of CSMs other than those specified may be acceptable when
it is demonstrated to the Construction Manager that they are equal in composition,
durability, usefulness, and convenience for the purpose intended. Requests for
consideration of CSMs other than those specified in this Section will be considered,
provided the following minimum conditions are met. Such requests are not a
substitution for submittals after the alternative CSMs have been considered and
accepted.
a. The proposed coating system shall use an equal or greater number of separate
coats to achieve the required total dry film thickness.
b. The proposed coating system shall use coatings of the same generic type as that
specified including curing agent type.
c. Requests for consideration of products from CSMs other than those specified in
this Section shall include information listed in paragraph 1.04, demonstrating
that the proposed CSM’s product is equal to the specified coating system.
d. The Contractor and the proposed alternative CSM shall provide a list of
references for the proposed product where the coating of the same generic type
has been applied. The reference list shall include the project name, city, state,
owner, phone number of owner; coating system reference and number from this
Section 09 90 00; type of facility in which it was used, generic type, and year
coating was applied.
C. Quality Control Requirements:
1. The Contractor is responsible for the workmanship and quality of the coating system
installation. Inspections by the Construction Manager or the CTR will not relieve or
limit the Contractor’s responsibilities.
2. The Contractor’s methods shall conform to requirements of this specification and the
standards referenced in this Section. Changes in the coating system installation
requirements will be allowed only with the written acceptance of the Construction
Manager before work commences.
3. Only personnel who are trained by the CTR specifically for this contract or who are
approved by the CSM specifically for this contract shall be allowed to perform the
coating system installation specified in this Section.
4. Contaminated, outdated, diluted materials, and/or materials from previously opened
containers shall not be used.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 8
5. For repairs, the Contractor shall provide the same products, or products
recommended by the CSM, as used for the original coating.
6. The Contractor shall identify the points of access for inspection by the Owner or the
Construction Manager. The Contractor shall provide ventilation, ingress and egress,
and other means necessary for the Construction Manager’s personnel to access
safely the work areas.
7. The Contractor shall conduct the work so that the coating system is installed as
specified and shall inspect the work continually to ensure that the coating system is
installed as specified. Coating system work that does not conform to the
specifications or is otherwise not acceptable shall be corrected as specified.
8. The Contractor shall complete the Coating System Inspection Checklist, Form
09 90 00-A, included in Section 01 99 90, for coating system installations. Follow the
sequential steps required for proper coating system installation as specified and as
listed in the Coating System Inspection Checklist. For each portion of the work, install
the coating system and complete sign-offs as specified prior to proceeding with the
next step. After completing each step as indicated on the Coating System Inspection
Checklist, the Contractor shall sign the checklist indicating that the work has been
installed and inspected as specified.
9. The Contractor shall provide written daily reports that present, in summary form, test
data, work progress, surfaces covered, ambient conditions, quality control inspection
test findings, and other information pertinent to the coating system installation.
D. Inspection at Hold Points:
1. The Contractor shall conduct inspections at Hold Points during the coating system
installation and record the results from those inspections on Form 09 90 00-A. The
Contractor shall coordinate such Hold Points with the Construction Manager such
that the Construction Manager may observe Contractor’s inspections on a scheduled
basis. The Contractor shall provide the Construction Manager a minimum of two (2)
hours of notice prior to conducting Hold Point Inspections. The Hold Points shall be
as follows:
a. Environment and Site Conditions. Prior to commencing an activity associated with
coating system installation, the Contractor shall measure, record, and confirm
acceptability of ambient air temperature and humidity as well as other conditions
such as proper protective measures for surfaces not to be coated and safety
requirements for personnel. The acceptability of the weather and/or
environmental conditions within the structure shall be determined by the
requirements specified by the CSM of the coating system being used.
b. Conditions Prior to Surface Preparation. Prior to commencing surface
preparation, the Contractor shall observe, record, and confirm that oil, grease,
and/or soluble salts have been eliminated from the surface.
c. Monitoring of Surface Preparation. Spot checking of degree of cleanliness,
surface profile, and surface pH testing, where applicable. In addition, the
compressed air used for surface preparation or blow down cleaning shall be
checked to confirm it is free from oil and moisture.
d. Post Surface Preparation – Upon completion of the surface preparation, the
Contractor shall measure and inspect for proper degree of cleanliness and
surface profile as specified in this Section 09 90 00 and in the CSM’s written
instructions.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 9
e. Monitoring of Coatings Application – The Contractor shall inspect, measure, and
record the wet film thickness and general film quality (visual inspection) for lack
of runs, sags, pinholes, holidays, etc. as the application work proceeds.
f. Post Application Inspection – The Contractor shall identify defects in application
work including pinholes, holidays, excessive runs or sags, inadequate or
excessive film thickness and other problems as may be observed.
g. Post Cure Evaluation – The Contractor shall measure and inspect the overall dry
film thickness. The Contractor shall conduct a DFT survey, as well as perform
adhesion testing, holiday detection, or cure testing as required based on the type
of project and the specific requirements in this Section 09 90 00 and/or in the
CSM’s written instructions.
h. Follow-up to Corrective Actions and Final Inspection. The Contractor shall
measure and reinspect corrective coating work performed to repair defects
identified at prior Hold Points. This activity also includes final visual inspection
along with follow-up tests such as holiday detection, adhesion tests, and DFT
surveys.
1.03 DELIVERY AND STORAGE
A. General:
1. Materials shall be delivered to the job site in their original, unopened containers.
Each container shall be properly labeled. Materials shall be handled and stored to
prevent damage to or loss of label.
2. Labels on material containers shall show the following information:
a. Name or title of product.
b. CSM's batch number.
c. CSM's name.
d. Generic type of material.
e. Application and mixing instructions.
f. Hazardous material identification label.
g. Shelf life expiration date.
3. Materials shall be stored in enclosed structures and shall be protected from weather
and excessive heat or cold in accordance with the CSM’s recommendations.
Flammable materials shall be stored in accordance with state and local
requirements.
4. Containers shall be clearly marked indicating personnel safety hazards associated
with the use of or exposure to the materials.
5. Material Safety Data Sheets (MSDS) for each material shall be provided to the
Construction Manager.
6. The Contractor shall store and dispose of hazardous waste according to federal, state
and local requirements. This requirement specifically addresses waste solvents and
coatings.
1.04 SUBMITTALS:
A. General:
1. Provide in accordance with Section 01 33 00:
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 10
a. A copy of this specification section, with addendum updates included, and
referenced and applicable sections, with addendum updates included, with each
paragraph check-marked (✓) to indicate specification compliance or marked to
indicate requested deviations from specification requirements or those parts
which are to be provided by the Contractor or others. Check marks shall denote
full compliance with a paragraph as a whole. If deviations from the specifications
are indicated, and therefore requested by the Contractor, each deviation shall be
underlined and denoted by a number in the margin to the right of the identified
paragraph, referenced to a detailed written explanation of the reasons for
requesting the deviation. The Construction Manager shall be the final authority
for determining acceptability of requested deviations. The remaining portions of
the paragraph not underlined shall signify compliance on the part of the
Contractor with the specifications. Failure to include a copy of the marked-up
specification sections, along with justification(s) for requested deviations to the
specification requirements shall be cause for rejection of the entire submittal and
no further submittal material will be reviewed.
b. CSM’s current printed recommendations and product data sheets for coating
systems including:
1) Volatile organic compound (VOC) data.
2) Surface preparation recommendations.
3) Primer type, where required.
4) Maximum dry and wet-mil thickness per coat.
5) Minimum and maximum curing time between coats, including atmospheric
conditions for each.
6) Curing time before submergence in liquid.
7) Thinner to be used with each coating.
8) Ventilation requirements.
9) Minimum atmospheric conditions during which the paint shall be applied.
10) Allowable application methods.
11) Maximum allowable moisture content.
12) Maximum shelf life.
c. Affidavits signed and sealed by an officer of the CSM’s corporation, attesting to
full compliance of each coating system component with current and promulgated
federal, state, and local air pollution control regulations and requirements.
d. Material Safety Data Sheets (MSDS) for materials to be delivered to the job site,
including coating system materials, solvents, and abrasive blast media.
e. List of cleaning and thinner solutions allowed by the CSMs.
f. Storage requirements including temperature, humidity, and ventilation for
Coating System Materials as recommended by the CSMs.
g. CSM's detailed, written instructions for coating system treatment and graphic
details for coating system terminations in the structures to be coated including
pipe penetrations, metal embedments, gate frames, and other terminations to be
determined from the contract drawings. This information shall also include detail
treatment for coating system at joints in concrete.
h. The Contractor and CSA shall provide a minimum of five project references each
including contact name, address, and telephone number where similar coating
work has been performed by their companies in the past five years.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 11
1.05 RESPONSIBILITIES OF THE CTR
A. General:
1. The Contractor shall retain or obtain the services of the CTR to be on site to perform
the Contractor and/or CSA application training and to routinely inspect and verify in
writing that the application personnel have successfully performed surface
preparation, filler/surface application, coating system application, and Quality Control
Inspection in accordance with this Section 09 90 00 and to warrantable level of
quality. This must include checking the required degree of cleanliness, surface pH for
concrete substrates, surface profile of substrates, proper mixing of coating materials,
application (including checking the wet and dry film thickness of the coating
systems), proper cure of the coating systems, and proper treatment of coating
systems at terminations, transitions, and joints and cracks in substrates. Refer to
paragraph 1.05 (B) Coating System Installation Training. for further details on these
CTR requirements. This inspection is in addition to the inspection performed by the
Contractor in accordance with this Section 09 90 00.
B. Coating System Installation Training:
1. Provide a minimum of 8 hours of classroom and off site training for application and
supervisory personnel (both the Contractor's and CSA’s). Provide training to a
minimum of two supervisory personnel from the CSA and one supervisor from the
Contractor. Alternatively, the CTR shall provide a written letter from the CSM stating
that the application personnel (listed by name) who shall perform coating work are
approved by the CSM without further or additional training.
2. One CTR can provide training for up to fourteen application personnel and three
supervisory personnel at one time. The training shall include the following as a
minimum:
a. A detailed explanation of mixing, application, curing, and termination details.
b. Hands-on demonstration of how to mix and apply the coating systems.
c. A detailed explanation of the ambient condition requirements (temperature and
humidity) and surface preparation requirements for application of the coating
system as well as a detailed explanation of re-coat times, cure times, and related
ambient condition requirements.
d. When training is performed, the CTR shall provide a written letter stating that
training was satisfactorily completed by the personnel listed by name in the
letter.
C. Coating System Inspection:
1. While on site to routinely inspect and verify, the CTR shall perform the following
activities to confirm acceptability and conformance with the specifications:
a. Inspect ambient conditions during various coating system installation at hold
points for conformance with the specified requirements.
b. Inspect the surface preparation of the substrates where the coating system will
terminate or will be applied for conformance to the specified application criteria.
c. Inspect preparation and application of coating detail treatment (for example,
terminations at joints, metal embedments in concrete, etc.).
d. Inspect application of the filler/surface materials for concrete and masonry
substrates.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 12
e. Inspect application of the primers and finish coats including wet and dry film
thickness of the coatings.
f. Inspect coating systems for cure.
g. Review adhesion testing of the cured coating systems for conformance to
specified criteria.
h. Review coating system continuity testing for conformance to specified criteria.
i. Inspect and record representative localized repairs made to discontinuities
identified via continuity testing.
j. Conduct a final review of completed coating system installation for conformance
to the specifications.
k. Prepare and submit a site visit report following each site visit that documents the
acceptability of the coating work in accordance with the CSM’s
Recommendations.
D. Final Report:
1. Upon completion of coating work for the project, the CTR shall prepare a final report.
That report shall summarize daily test data, observations, drawings, and photographs
in a report to be submitted in accordance with paragraph 2.02. Include substrate
conditions, ambient conditions, and application procedures, observed during the
CTR's site visits. Include a statement that the completed work was performed in
accordance with the requirements of this Section 09 90 00 and the CSM’s
recommendations.
PART 2 PRODUCTS
2.01 MATERIALS
A. General:
1. Notwithstanding the listing of product names in this Section 09 90 00, the Contractor
shall provide affidavits, signed and sealed by an officer of the CSM’s corporation,
attesting to full compliance of each coating system component with current and
promulgated federal, state, and local air pollution control regulations and
requirements. No coatings shall be applied to a surface until the specified affidavits
have been submitted and have been reviewed and accepted. Failure to comply with
this requirement shall be cause for rejection and removal of such materials from the
site.
2. The following list specifies the material requirements for coating systems. Coating
systems are categorized by generic name followed by an identifying abbreviation. If
an abbreviation has a suffix number, it is for identifying subgroups within the coating
system. Coating Systems E-5 and E-6 shall be NSF 61 certified.
Material Requirements for Coating Systems: All of U.S. Except California
Coating System CSM First Coat(s) Finish Coat(s)
Epoxy Coatings
E-1 PPG PMC Amerlock 2/400 Series Amerlock 2/400 Series
Carboline Carboguard 890 Carboguard 890
International
Paint/ICI *
Devran 224 HS Devran 224
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 13
Material Requirements for Coating Systems: All of U.S. Except California
Coating System CSM First Coat(s) Finish Coat(s)
Sherwin Williams Macropoxy 646 Macropoxy 646
Tnemec Series V69 Series V69
E-2 PPG PMC Amerlock 2/400 Series Amerlock 2/400 Series
Carboline Carboguard 890 Carboguard 890
International
Paint/ICI
Bar-Rust 236 Bar-Rust 236
Sherwin Williams Sea Guard 6000 Epoxy N11-400 Sea Guard 6000 Epoxy N11-
400
Tnemec Series V27 or V69 Series V69
Epoxy Polyurethane
Primer Coat(s) Intermediate Coat(s)
EU-1 PPG PMC Amercoat Amercoat 385 Amercoat 450H
Carboline Carbozinc 859 Carboguard 890 Carbothane 134 VOC
International
Paint/ICI
Cathacoat 313 Devran 233 or 224HS Devthane 379
Sherwin Williams Zinc Clad IV Macropoxy 646 Hi Solids Polyurethane
Tnemec Series 90-97 Series V69 Series 1075
Miscellaneous
M-1 Carboline Carbowrap Priming Paste Tape A, B, or C (temp.
dependent)
Denso Denso Paste Densyl Tape
Trenton Waxtape Primer #1 Wax Tape
*See CSM’s Product Data Sheets for acceptable thinners for VOC compliance or do not thin.
2.02 PRODUCT DATA
A. General:
1. Prior to application of coatings, submit letter(s) from the CTR(s) identifying the
application personnel who have satisfactorily completed training as specified in
paragraph 1.05 or a letter from the CSM stating that personnel who shall perform the
work are approved by the CSM without need for further or additional training.
2. Submit reports specified in paragraph 1.02 Quality Control Requirements and 1.05
Coating System Inspection when the work is underway.
3. Submit the Coating System Inspection Checklists, using Form 09 90 00-A, included in
Section 01 99 90, for the coating work.
4. CTR final report in accordance with paragraph 1.05 Final Report.
PART 3 EXECUTION
3.01 COATINGS
A. General:
1. Coating products shall not be used until the Construction Manager has accepted the
affidavits specified in paragraphs 1.04 and 2.01, the Construction Manager has
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 14
inspected the materials, and the CTR has trained the Contractor and CSA in the
surface preparation, mixing and application of each coating system.
2. Erect and maintain protective enclosures as stipulated per SSPC-Guide 6 Guide for
Containing Debris Generated During Paint Removal Operations.
B. Shop and Field Coats:
1. Shop Applied Prime Coat: Except as otherwise specified, prime coats may be shop-
applied or field-applied. Shop-applied primer shall be compatible with the specified
coating system and shall be applied at the minimum dry film thickness
recommended by the CSM. Data sheets identifying the shop primer used shall be
provided to the on-site coating application personnel. Adhesion tests shall be
performed on the shop primer as specified in paragraph 3.01 Adhesion Confirmation.
Damaged, deteriorated and poorly applied shop coatings that do not meet the
requirements of this Section 09 90 00 shall be removed and the surfaces recoated.
If the shop primer coat meets the requirements of this Section 09 90 00, the field
coating may consist of touching up the shop prime coat and then applying the finish
coats to achieve the specified film thickness and continuity.
2. Field Coats: Field coats shall consist of one or more prime coats and one or more
finish coats to build up the coating to the specified dry film thickness. Unless
otherwise specified, finish coats shall not be applied until other work in the area is
complete and until previous coats have been inspected.
3. Adhesion Confirmation: The Contractor shall perform an adhesion test after proper
cure in accordance with ASTM D3359 to demonstrate that (1) the shop applied prime
coat adheres to the substrate, and (2) the specified field coatings adhere to the shop
coat. Test results showing an adhesion rating of 5A on immersed surfaces and 4A or
better on other surfaces shall be considered acceptable for coatings 5 mils or more
in thickness (Method A). Test results showing an adhesion rating of 5B on immersed
surfaces and 4B or better on other surfaces shall be considered acceptable for
coating thicknesses less than 5 mils.
C. Application Location Requirements:
1. Equipment, Nonimmersed: Items of equipment, or parts of equipment that are not
immersed in service, shall be shop primed and then finish coated in the field after
installation with the specified or acceptable color. If the shop primer requires
topcoating within a specified period, the equipment shall be finish coated in the shop
and then touch-up painted after installation. If equipment removal and reinstallation
is required for the project, touch-up coating work shall be performed in the field
following installation.
2. Equipment, Immersed: Items of equipment, or parts and surfaces of equipment that
are immersed when in service, with the exception of pumps and valves, shall have
surface preparation and coating work performed in the field. Coating systems applied
to immersed equipment shall be pinhole free.
3. Steel Water Tanks: The interior surfaces of steel water tanks or reservoirs shall have
surface preparation and coating work performed in the field.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 15
3.02 PREPARATION
A. General:
1. Surface preparations for each type of surface shall be in accordance with the specific
requirements of each coating specification sheet (COATSPEC) and the following. In
the event of a conflict, the COATSPEC sheets shall take precedence.
2. Surfaces to be coated shall be clean and dry. Before applying coating or surface
treatments, oil, grease, dirt, rust, loose mill scale, old weathered coatings, and other
foreign substances shall be removed. Oil and grease shall be removed before
mechanical cleaning is started. Where mechanical cleaning is accomplished by blast
cleaning, the abrasive used shall be washed, graded and free from contaminants
that might interfere with the adhesion of the coatings. The air used for blast cleaning
shall be sufficiently free of oil and moisture so as not to cause detrimental
contamination of the surfaces to be coated.
3. Where deemed necessary by the Owner’s representative, a NACE International
certified coatings inspector, provided by the Owner, will inspect and approve surfaces
to be coated before application of a coating. Surface defects identified by the
inspector shall be corrected by the Contractor at no additional cost to the Owner.
4. Cleaning and painting shall be scheduled so that dust and spray from the cleaning
process shall not fall on wet, newly coated surfaces. Hardware, hardware
accessories, nameplates, data tags, machined surfaces, sprinkler heads, electrical
fixtures, and similar uncoated items which are in contact with coated surfaces shall
be removed or masked prior to surface preparation and painting operations.
Following completion of coating, removed items shall be reinstalled. Equipment
adjacent to walls shall be disconnected and moved to permit cleaning and painting of
equipment and walls and, following painting, shall be replaced and reconnected.
B. Blast Cleaning:
1. When abrasive blast cleaning is required to achieve the specified surface preparation
the following requirements for blast cleaning materials and equipment shall be met:
a. Used or spent blast abrasive shall not be reused on this project.
b. The compressed air used for blast cleaning shall be filtered and shall contain no
condensed water and no oil. Moisture traps shall be cleaned at least once every
four hours or more frequently as required to prevent moisture from entering the
supply air to the abrasive blasting equipment.
c. Oil separators shall be installed just downstream of compressor discharge valves
and at the discharge of the blast pot discharges. These shall be checked on the
same frequency as the moisture traps as defined above.
d. Regulators, gauges, filters, and separators shall be in use on compressor air lines
to blasting nozzles times during this work.
e. An air dryer or desiccant filter drying unit shall be installed which dries the
compressed air prior to blast pot connections. This dryer shall be used and
maintained for the duration of surface preparation work.
f. The abrasive blast nozzles used shall be of the venturi or other high velocity type
supplied with a minimum of 100 psig air pressure and sufficient volume to obtain
the blast cleaning production rates and cleanliness/specified.
g. The Contractor shall provide ventilation for airborne particulate evacuation
(meeting pertinent safety standards) to optimize visibility for both blast cleaning
and inspection of the substrate during surface preparation work.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 16
h. If, between final surface preparation work and coating system application,
contamination of prepared and cleaned metallic substrates occurs, or if the
prepared substrates' appearance darkens or changes color, recleaning by water
blasting, reblasting and abrasive blast cleaning shall be required until the
specified degree of cleanliness is reclaimed.
i. The Contractor is responsible for dust control and for protection of mechanical,
electrical, and other equipment adjacent to and surrounding the work area.
C. Solvent Cleaning:
1. Any solvent wash, solvent wipe, or cleaner used, including but not limited to those
used for surface preparation in accordance with SSPC SP-1 Solvent Cleaning and
shall be of the emulsifying type which emits no more than 340 g/l VOCs for AIM
regions, 250 g/l for CARB regions and 100 g/l for SCAQMD regions, contains no
phosphates, is biodegradable, removes no zinc, and is compatible with the specified
primer.
2. Clean white cloths and clean fluids shall be used in solvent cleaning.
D. Metallic Surfaces:
1. Metallic surfaces shall be prepared in accordance with applicable portions of surface
preparation specifications of the Society for Protective Coatings (SSPC) specified for
each coating system. See Coat Spec for each coating system in this Section
09 90 00. The profile depth of the surface to be coated shall be in accordance with
the COATSPEC requirements in this Section measured by Method C of ASTM D4417.
Blast particle size shall be selected by the Contractor to produce the specified
surface profile. The solvent in solvent cleaning operations shall be as recommended
by the CSM.
2. Preparation of metallic surfaces shall be based upon comparison with SSPC-VIS1-89
(ASTM D2200), and as described in the Coat Spec for each coating system. If dry
abrasive blast cleaning is selected and to facilitate inspection, the Contractor shall,
on the first day of cleaning operations, abrasive blast metal panels to the standards
specified. Plates shall measure a minimum of 8-1/2 inches by 11 inches. Panels
meeting the requirements of the specifications shall be initialed by the Contractor
and the Construction Manager and coated with a clear non-yellowing finish. One of
these panels shall be prepared for each type of abrasive blasting and shall be used
as the comparison standard throughout the project.
3. Blast cleaning requirements for steel, ductile iron and stainless steel substrates are
as follows:
a. Steel piping shall be prepared in accordance with SSPC SP-6 (Commercial Blast
Cleaning) and primed before installation. Ductile iron piping surfaces including
fittings shall be prepared in accordance with NAPF 500-03, NAPF 500-03-04, and
NAPF 500-03-05.
b. Stainless steel surfaces shall be abrasive blast cleaned to leave a clean uniform
appearance with a minimum surface profile of 1.5 to 2.5 mils that is uniform.
c. Remove traces of grit, dust, dirt, rust scale, friable material, loose corrosion
products or embedded abrasive from substrate by vacuum cleaning prior to
coating application.
d. Care must be taken to prevent contamination of the surface after blasting from
worker’s fingerprints, deleterious substances on workers’ clothing, or from
atmospheric conditions.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 17
e. Ambient environmental conditions in the enclosure must be constantly monitored
and maintained to ensure the degree of cleanliness is held and no “rust back”
occurs prior to coating material application.
E. Concrete Surfaces:
1. Inspection of concrete surfaces prior to surface preparation and surface preparation
of concrete surfaces shall be performed in accordance with SSPC-SP13 (also called
NACE 6).
2. Prepare substrate cracks, areas requiring resurfacing and perform detail treatment
including but not limited to, terminating edges, per CSM recommendations. This shall
precede surface preparation for degree of cleanliness and profile.
3. The surface profile for prepared concrete surfaces to be coated shall be evaluated by
comparing the profile of the prepared concrete with the profile of graded abrasive
paper, as described in ANSI B74.18 or by comparing the profile with the ICRI 03732
(surface profile replicas). Surface profile requirements shall be in accordance with
the Coat Spec requirements and the CSM’s recommendations.
4. Surface cleanliness of prepared concrete substrates shall be inspected after
cleaning, preparation, and/or drying, but prior to making repairs or applying a coat in
the coating system. If concrete surfaces are repaired, they shall be reinspected for
surface cleanliness prior to application of the coating system.
5. Surface preparation of concrete substrates shall be accomplished using methods
such as dry abrasive blast cleaning, high, or ultra high-pressure water blast cleaning
in accordance with SSPC-SP-13. The selected cleaning method shall produce the
requirements set forth below.
a. A clean substrate that is free of calcium sulfate, loose coarse or fine aggregate,
laitance, loose hydrated cement paste, and otherwise deleterious substances
shall be achieved. Blast cleaning and other means necessary shall be used to
open up air voids or bugholes to expose their complete perimeter. Leaving
shelled over, hidden air voids beneath the exposed concrete surface is not
acceptable. Concrete substrate must be dry prior to the application of
filler/surface or coating system materials.
b. Acceptable surface preparation must produce a concrete surface with a
minimum pH of 8.0 to be confirmed by surface pH testing. If after surface
preparation, the surface pH remains below 8.0, perform additional water
blasting, cleaning, or abrasive blast cleaning until additional pH testing indicates
an acceptable pH level.
c. Following inspection by the Contractor of the concrete surface preparation,
thoroughly vacuum clean concrete surfaces to be coated to remove loose dirt,
and spent abrasive (if dry blast cleaning is used) leaving a dust free, sound
concrete substrate. Debris produced by blast cleaning shall be removed from the
structures to be coated and disposed of legally off site by the Contractor.
6. Should abrasive blast cleaning or high or ultrahigh pressure water blasting not
remove degraded concrete, chipping or other abrading tools shall be used to remove
the deteriorated concrete until a sound, clean substrate is achieved which is free of
calcium sulfate, loose coarse or fine aggregate, laitance, loose hydrated cement
paste, and otherwise deleterious substances. Concrete substrates must be dry prior
to the application of filler/surfacers or coating system materials.
7. Surface cleanliness of prepared concrete substrates shall be inspected after
cleaning, preparation, and/or drying, but prior to application of coating materials. If
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 18
concrete surfaces are repaired, they shall be reinspected for surface cleanliness and
required surface profile prior to application of the coating system.
8. Moisture content of concrete to be coated shall be tested in accordance with ASTM
D4263, Standard Test Method for Indicating Moisture in Concrete by the Plastic
Sheet Method and ASTM F 1869, Standard Test Method for Measuring Moisture
Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride. The
ASTM D4263 plastic sheet test shall be conducted at least once for every 500 sq. ft.
of surface area to be coated. The presence of any moisture on plastic sheet following
test period constitutes a non-acceptable test. For concrete surfaces to be coated
which are on the negative or back side of concrete walls or structures exposed to
soils (back filled) or immersed and waterproofed, perform calcium chloride tests in
accordance with ASTM F-1869 once for each 500 sq. ft. of surface area to be coated.
Comply with CSM’s written recommendations regarding acceptance/non-acceptance
of moisture vapor emissions.
F. Masonry Surfaces:
1. Prepare masonry surfaces such as Concrete Masonry Units (CMU) to remove chalk,
loose dirt, dried mortar splatter, dust, peeling, or loose existing coatings, or otherwise
deleterious substances to leave a clean, sound substrate.
2. Be certain masonry surfaces are dry prior to coating application. If pressure washing
or low-pressure water blast cleaning is used for preparation, allow the masonry to dry
for at least 5 days under dry weather conditions or when the minimum ambient
temperature is 70 degrees F prior to coating application work.
G. Fiberglass Reinforced Plastic (FRP) Surfaces:
1. Prepare FRP surfaces by sanding to establish uniform surface roughness and to
remove gloss from the resin in the FRP. Next, vacuum clean to remove loose FRP
dust, dirt, and other materials. Next, solvent clean using clean white rags and allow
solvent to evaporate completely before application of coating materials.
3.03 APPLICATION
A. Workmanship:
1. Coated surfaces shall be free from runs, drips, ridges, waves, laps, and brush marks.
Coats shall be applied to produce an even film of uniform thickness completely
coating corners and crevices.
2. The Contractor's equipment shall be designed for application of the materials
specified. Compressors shall have suitable traps and filters to remove water and oils
from the air. A paper blotter test shall be performed by the Contractor when
requested by the Construction Manager to determine if the air is sufficiently free of
oil and moisture so as not to produce deteriorating effects on the coating system.
The amount of oil and moisture in spray air shall be less than the amount
recommended by the CSM. Spray equipment shall be equipped with mechanical
agitators, pressure gages, and pressure regulators, and spray nozzles of the proper
sizes.
3. Each coat of coating material shall be applied evenly and sharply cut to line. Care
shall be exercised to avoid overspraying or spattering paint on surfaces not to be
coated. Glass, hardware, floors, roofs, and other adjacent areas and installations
shall be protected by taping, drop cloths, or other suitable measures.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 19
4. Coating applications method shall be conventional or airless spray, brush or roller, or
trowel as recommended by CSM.
5. Allow each coat to cure or dry thoroughly, according to CSM’s printed instructions,
prior to recoating.
6. Vary color for each successive coat for coating systems when possible.
7. When coating complex steel shapes, prior to overall coating system application,
stripe coat welds, edges of structural steel shapes, metal cut-outs, pits in steel
surfaces, or rough surfaces with the primer coat. This involves applying a separate
coat using brushes or rollers to ensure proper coverage. Stripe coat via spray
application is not permitted.
B. Coating Properties, Mixing and Thinning:
1. Coatings, when applied, shall provide a satisfactory film and smooth even surface.
Glossy undercoats shall be lightly sanded to provide a surface suitable for the proper
application and adhesion of subsequent coats. Coating materials shall be thoroughly
stirred, strained, and kept at a uniform consistency during application. Coatings
consisting of two or more components shall be mixed in accordance with the CSM’s
instructions. Where necessary to suit the conditions of the surface, temperature,
weather and method of application, the coating may be thinned as recommended by
the CSM immediately prior to use. The volatile organic content (VOC) of the coating as
applied shall comply with prevailing air pollution control regulations. Unless otherwise
specified, coatings shall not be reduced more than necessary to obtain the proper
application characteristics. Thinner shall be as recommended by the CSM.
C. Atmospheric Conditions:
1. Coatings shall be applied only to surfaces that are dry, and only under conditions of
evaporation rather than condensation. Coatings systems shall not be applied during
rainy, misty weather, or to surfaces upon which there is frost or moisture
condensation. During damp weather, when the temperature of the surface to be
coated is within 10 degrees F of the dew point, forced dehumidification equipment
may be used to maintain a temperature of minimum 40 degrees F and 10 degrees F
above the dew point for the surfaces to be coated, the coated surface, and the
atmosphere in contact with the surface. These conditions shall be maintained for a
period of at least 8 hours or as recommended by the CSM. Where conditions causing
condensation are severe, dehumidification equipment, fans, and/or heaters shall be
used inside enclosed areas to maintain the required atmospheric and surface
temperature requirements for proper coating application and cure.
D. Concrete Substrate Temperatures and Detail Treatment:
1. When the surface temperatures of the concrete substrates to be coated are rising or
when these substrates are in direct sunlight, outgassing of air from the concrete may
result in bubbling, pinhole formations, and/or blistering in the coating system. The
application of the filler/surface and the coating system will only be allowed during
periods of falling temperature. This will require that application of the filler/surface
and coating system shall only occur during the cooler evening hours. Contractor shall
include any cost for working outside of normal hours in the bid.
2. Should bubbles, pinholes, or discontinuities form in the applied coating system
material, they shall be repaired as recommended by the CSM. Should pinholes
develop in the filler/surfacer material or in the first coat of the coating material, the
pinholes shall be repaired in accordance with the CSM’s recommendations prior to
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 20
application of the next coat of material. Whenever pinholes occur, the air void behind
or beneath the pinhole shall be opened up completely and then completely filled with
the specified filler/surfacer material. Next, the coated area around the pinhole repair
shall be abraded and the coating reapplied over that area.
3. Perform application detail work per CSM’s current written recommendations and/or
drawings.
E. Protection of Coated Surfaces:
1. Items that have been coated shall not be handled, worked on, or otherwise
disturbed, until the coating is completely dry and hard. After delivery at the site, and
upon permanent erection or installation, shop-coated metalwork shall be recoated or
retouched with specified coating when it is necessary to maintain the integrity of the
film.
F. Method of Coating Application:
1. Where two or more coats are required, alternate coats shall contain sufficient
compatible color additive to act as indicator of coverage, or the alternate coats shall
be of contrasting colors. Color additives shall not contain lead, or lead compounds,
which may be destroyed or affected by hydrogen sulfide or other corrosive gas,
and/or chromium.
2. Mechanical equipment, on which the equipment manufacturer's coating is
acceptable, shall be touch-up primed and coated with two coats of the specified
coating system to match the color scheduled. Electrical and instrumentation
equipment specified in Divisions 26 and 40 shall be coated as specified in
paragraph 3.03 Electrical and Instrumentation Equipment and Materials.
3. Coatings shall not be applied to a surface until it has been prepared as specified. The
primer or first coat shall be applied by brush to ferrous surfaces that are not blast-
cleaned. Coats for blast-cleaned ferrous surfaces and subsequent coats for nonblast-
cleaned ferrous surfaces may be either brush or spray applied. After the prime coat is
dry, pinholes and holidays shall be marked, repaired in accordance with CSM's
recommendations and retested before succeeding coats are applied. Unless
otherwise specified, coats for concrete and masonry shall be brushed, rolled, or
troweled.
G. Film Thickness and Continuity:
1. WFT of the first coat of the coating system and subsequent coats shall be verified by
the Contractor, following application of each coat.
2. The surface area covered per gallon of coating for various types of surfaces shall not
exceed those recommended by the CSM. The first coat, referred to as the prime coat,
on metal surfaces refers to the first full paint coat and not to solvent wash, grease
emulsifiers or other pretreatment applications. Coatings shall be applied to the
thickness specified, and in accordance with these specifications. Unless otherwise
specified, the average total thickness (dry) of a completed protective coating system
on exposed metal surfaces shall be not less than 1.25 mils per coat. The minimum
thickness at any point shall not deviate more than 25 percent from the required
average. Unless otherwise specified, no less than two coats shall be applied.
3. In testing for continuity of coating about welds, projections (such as bolts and nuts),
and crevices, the Construction Manager shall determine the minimum conductivity
for smooth areas of like coating where the dry-mil thickness has been accepted. This
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 21
conductivity shall be the minimum required for these rough or irregular areas.
Pinholes and holidays shall be recoated to the required coverage.
4. The ability to obtain specified film thickness is generally compromised when brush or
roller application methods are used and, therefore, more coats may need to be
applied to achieve the specified dry film thickness.
5. For concrete substrates, the Contractor shall apply a complete skim coat of the
specified filler/surfacer material over the entire substrate prior to application of the
coating system. This material shall be applied such that all open air voids and
bugholes in the concrete substrate are completely filled prior to coating application.
H. Special Requirements:
1. Before erection, the Contractor shall apply all but the final finish coat to interior
surfaces of roof plates, roof rafters and supports, pipe hangers, piping in contact with
hangers, and contact surfaces that are inaccessible after assembly. The final coat
shall be applied after erection. Structural friction connections and high tensile bolts
and nuts shall be coated after erection. Areas damaged during erection shall be
hand-cleaned or power-tool cleaned and recoated with primer coat prior to the
application of subsequent coats. Touch-up of surfaces shall be performed after
installation. Surfaces to be coated shall be clean and dry at the time of application.
Except for those to be filled with grout, the underside of equipment bases and
supports that have not been galvanized shall be coated with at least two coats of
primer specified for system E-2 prior to setting the equipment in place. Provide
coating system terminations at leading edges and transitions to other substrates in
accordance with the CSM’s recommendations or detail drawings.
I. Electrical and Instrumentation Equipment and Materials:
1. Electrical and instrumentation equipment and materials shall be coated by the
equipment manufacturer as specified below.
a. Finish: Electrical equipment shall be treated with zinc phosphate, bonderized or
otherwise given a rust-preventive treatment. Equipment shall be primed, coated
with enamel, and baked. Minimum dry film thickness shall be 3 mils.
1) Unless otherwise specified, instrumentation panels shall be coated with
system E-1 for indoor mounting and system EU-1 for outdoor mounting.
2) Before final acceptance, the Contractor shall touch up scratches on
equipment with identical color coating. Finish shall be smooth, free of runs,
and match existing finish. Prior to touching up scratches, Contractor shall fill
them with an appropriate filler material approved by the CSM.
b. Color: Exterior color of electrical equipment shall be FS 26463 (ANSI/NSF 61)
light gray. Interior shall be painted FS 27880 white. Nonmetallic electrical
enclosures and equipment shall be the equipment manufacturer's standard grey
color.
1) Exterior color of instrumentation panels and cabinets mounted indoors shall
be FS 26463 light gray; unless otherwise specified, exterior color for cabinets
mounted outdoors shall be FS 27722, white. Cabinet interiors shall be FS
27880, white.
J. Soluble Salt Contamination of Metallic Substrates:
1. Contractor shall test in accordance with SSPC-TU-4 metallic substrates to be coated
that have been exposed to seawater or coastal air or to industrial fallout of
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 22
particulate or other sources of soluble chlorides (such as wastewater exposure). If
testing indicates detrimental levels of soluble salts, those in excess of 25 ppm, the
Contractor shall clean and prepare these surfaces to remove the soluble salts.
3.04 CLEANUP
A. General:
1. Upon completion of coating, the Contractor shall remove surplus materials, protective
coverings, and accumulated rubbish, and thoroughly clean surfaces and repair
overspray or other coating-related damage.
3.05 COATING SYSTEM SPECIFICATION SHEETS (COATSPEC)
A. General:
1. Coating systems for different types of surfaces and general service conditions for
which these systems are normally applied are specified on the following COATSPEC
sheets. Surfaces shall be coated in accordance with the COATSPEC to the system
thickness specified. Coating systems shall be as specified in paragraph 3.06. In case
of conflict between the schedule and the COATSPECS, the requirements of the
schedule shall prevail.
2. Coating Specification Sheets included in Table A are included this paragraph 3.05.
Table A Coating Specification Sheets
Coating System ID Coating Material Surface Service Condition
E-1 Epoxy Metal Interior; exterior, covered, not exposed to direct
sunlight, non-corrosive exposure.
E-2 Epoxy Metal Immersed, nonpotable; non-immersed,
moderately corrosive environment, color
required.
EU-1 Zinc-epoxy-polyurethane
system
Ferrous Metal Exterior, exposed to direct sunlight, moderately
corrosive non-immersed.
M-1 Petrolatum based mastic
or wax based wrapping
tapes
Metal Below grade (buried) or where little to no surface
preparation can be performed on piping or
structural steel.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 23
Coating System Specification Sheets (COATSPEC)
A. Coating System Identification: E-1
1. Coating Material: Epoxy
2. Surface: Metal
3. Service Condition: Interior; exterior, covered, not exposed to direct sunlight, non-corrosive exposure.
4. Surface Preparation:
a. General: Shop primed surfaces which are to be incorporated in the work shall be prepared
in the field by cleaning surfaces in accordance with SSPC SP-2 (Hand Tool
Cleaning). Damaged shop coated areas shall be cleaned in accordance with SSPC
SP-5 (White Metal Blast Cleaning) to achieve a uniform surface profile of 2.0 to 2.5
mils and spot primed with the primer specified. Shop epoxy primed surfaces shall
require light abrasive and vacuum cleaning blasting prior to receiving finish coats.
b. Ferrous Metal: Bare ferrous metal surfaces shall be prepared in accordance with SSPC SP-6
(Commercial Blast Cleaning) to achieve a uniform, surface profile of 2.0 to 2.5
mils.
Ferrous metal with rust bleeding shall be cleaned in accordance with SSPC SP-1
(Solvent Cleaning). Areas of rust penetration shall be spot blasted to SSPC SP-10
(Near White Blast) (to achieve the 2.0- to 2.5-mil surface profile) and spot primed
with the specified primer. For ductile iron surfaces, refer to the requirements in
paragraph 3.02 Metallic Surfaces.
c. Nonferrous and
Galvanized Metal:
Nonferrous and galvanized metal shall be prepared in accordance with SSPC SP-7
(Brush-off Blast Cleaning) to achieve uniform, minimum surface profile 1.0 to 1.5
mils.
5. Application: Field
a. General: Prime coat may be thinned and applied as recommended by the CSM, provided
the coating as applied complies with prevailing air pollution control regulations.
b. Ferrous Metal: Prime coats shall be an epoxy primer compatible with the specified finish coats
and applied in accordance with the written instructions of the CSM.
c. Nonferrous and
Galvanized Metal:
Nonferrous and galvanized metal shall be cleaned prior to the application of the
prime coat in accordance with SSPC SP-1 (Solvent Cleaning).
6. System Thickness: 10 mils dry film.
7. Coatings:
a. Primer: One coat at CSM's recommended dry film thickness.
b. Finish: One or more coats at CSM's recommended dry film thickness per coat to achieve
the specified system thickness.
B. Coating System Identification: E-2
1. Coating Material: Epoxy
2. Surface: Metal
3. Service Condition: Immersed, nonpotable; non-immersed, moderately corrosive environment, color
required.
4. Surface Preparation:
a. Ferrous Metal: Ferrous metal surfaces shall be prepared in accordance with SSPC SP-5 (White
Metal Blast Cleaning) to achieve a uniform surface profile of 2.0 to 2.5 mils.
Damaged shop coating shall be cleaned in accordance with SSPC SP-5 (White
Metal Blast Cleaning) and vacuum cleaning and spot primed with the primer
specified. Shop epoxy primed surfaces shall require light abrasive blasting or
abrading prior to receiving finish coats if the maximum recoat time for the primer
has been exceeded. This cleaning must produce a uniform 1.0- to 1.5-mil profile in
the intact shop primer. For ductile iron surfaces, refer to the requirements in
paragraph 3.02 Metallic Surfaces.
b. Nonferrous and
Galvanized Metal:
Nonferrous and galvanized metal shall be prepared in accordance with SSPC SP-7
(Brush-off Blast Cleaning) to achieve a uniform surface profile of 1.0 to 1.5 mils.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 24
Coating System Specification Sheets (COATSPEC) Galvanized steel with this E-2 coating system shall not be used in immersion
service in wastewater.
5. Application: Field
a. General: Prime coat may be thinned and applied as recommended by the CSM, provided
the coating as applied complies with prevailing air pollution control regulations.
b. Ferrous Metal: Prime coat shall be an epoxy primer compatible with the specified finish coats.
c. Nonferrous and
Galvanized Metal:
Nonferrous and galvanized metal, non-immersed, shall be coated prior to the
application of the prime coat with a grease emulsifying agent in accordance with
the CSM's written instructions. Nonferrous metal to be immersed shall not be
painted. Galvanized metal shall not be immersed even if it is painted.
6. System Thickness: 16 mils dry film.
7. Coatings:
a. Primer: One coat at CSM's recommended dry film thickness.
b. Finish: Two or more coats at CSM's recommended dry film thickness per coat to the
specified system thickness.
C. Coating System Identification: EU-1
1. Coating Material: Zinc-Epoxy-Polyurethane System
2. Surface: Ferrous Metal
3. Service Condition: Exterior, exposed to direct sunlight, moderately corrosive, non-immersed.
4. Surface Preparation:
a. General: Shop primed surfaces which are to be incorporated in the work shall be prepared
in the field by cleaning surfaces in accordance with SSPC SP-2 (Hand Tool
Cleaning). Damaged shop coated areas shall be cleaned in accordance with SSPC
SP-3 (Power Tool Cleaning) and recoated with the primer specified.
b. Ferrous Metal: Bare ferrous metal surfaces shall be prepared in accordance with SSPC SP-6
(Commercial Blast Cleaning) 2.5 – 3.0. Ductile iron surfaces to be coated shall be
abrasive blast cleaned in accordance with paragraph 3.02 Metallic Surfaces.
Ferrous metal with rust bleeding shall be cleaned in accordance with SSPC-SP-11
(Power Tool Cleaning to Bare Metal). Areas of rust penetration shall be spot
blasted to SSPC SP-10 (Near White Blast) and spot primed with the specified
primer.
c. Galvanized Metal: Damaged galvanized steel areas with exposed ferrous metal and/or rusted shall
be cleaned in accordance with SSPC SP-5 (White Metal Blast Cleaning) or Power
Tool Cleaned to Bare Metal in accordance with SSPC-SP-11 to achieve a uniform
1.0- to 1.5-mil profile and spot primed with the primer specified.
Nonferrous and galvanized metal shall be prepared in accordance with SSPC SP-7
(Brush-off Blast Cleaning) to impart a 1.0- to 2.0-mil profile to the galvanized steel
surfaces. Where this cannot be performed, prepare by abrading in accordance with
SSPC-SP-3, Power Tool Cleaning to impart a 1.0- to 1.5-mil profile uniformly to the
galvanized steel surfaces.
For EU-1 over galvanized steel, delete the zinc rich primer.
5. Application: Field
a. General: Prime coat may be thinned and applied as recommended by the CSM, provided
the coating as applied complies with prevailing air pollution control regulations.
b. Ferrous Metal: Prime coats shall be a zinc rich epoxy or polyurethane primer compatible for use
with urethane finish coats and applied in accordance with written instructions of
the CSM or in the case of CARB or SCAQMD applications, prime with specified
primer that is not zinc rich. In these cases, only a two-coat system is applied.
6. System Thickness: 3 to 4 mils of zinc rich primer, one intermediate or primer epoxy coat at 5 to 6 mils
and one finish coat of polyurethane at 2 to 3 mils DFT.
7. Coatings:
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 25
Coating System Specification Sheets (COATSPEC)
a. Primer: One coat at CSM's recommended dry film thickness.
b. Intermediate: One coat at CSM’s recommended dry film thickness.
c. Finish: One coat at CSM's recommended dry film thickness per coat to meet the specified
system thickness.
D. Coating System Identification: M-1
1. Coating Material: Petrolatum based mastic or wax based wrapping tapes.
2. Surfaces: Metal
3. Service Condition: Below grade (buried) or where little to no surface preparation can be performed on
piping or structural steel.
4. Surface Preparation: Remove loose scale, rust, dirt, excessive moisture, or frost from the surface in
accordance with SSPC SP-2 (Hand Tool Cleaning).
5. Application: All surfaces shall be hand rubbed or brushed with a priming paste recommended
by the CSM. Sharp projections such as threads, irregular contours, or badly pitted
areas shall receive a liberal amount of priming paste to ensure maximum
protection of metal throughout.
On irregular shaped surfaces, i.e., nuts, bolts, flanges, valves, etc., the Contractor
shall use either of the following systems recommended by the CSM.
A. Apply recommended mastic by hand in sufficient quantity to build an
even contour over entire surface. The Contractor shall pay particular attention to
ensure that folds and air pockets within the mastic layer are thoroughly pressed
out prior to subsequent application of tape.
OR:
B. An extra layer of tape shall be cut and carefully molded around sharp
projections, nuts, bolts, etc., before final application of tape, in order to meet
specified system thickness.
Tape shall be spirally wrapped with a 55 percent overlap and sufficient tension
and pressure to provide continuous adhesion without stretching the tape. Edges of
tape must be continuously smoothed and sealed by hand during wrapping. On
vertical application, contractor shall begin at bottom and proceed upward creating
a weatherboard overlap.
6. System Thickness: Smooth contours shall have a minimum thickness of 50 mils while nuts, bolts, and
sharp projections shall be 100 mils.
7. Tape: Number and types of tape wraps shall be in accordance with the CSM's written
instructions.
3.06 COATING SYSTEMS SCHEDULE (FINISH SCHEDULE)
A. General:
1. Specific coating systems, colors, and finishes for rooms, galleries, piping, equipment,
and other items that are coated or have other architectural finishes are specified in
the following coating system schedule. Unless otherwise specified in the coating
system schedule, the word "interior" shall mean the inside of a building or structure,
and the word "exterior" shall mean outside exposure to weather elements.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 26
Coating Systems Schedule (Finish Schedule)
Location/Surface Coating System Identification
A. General: All Surfaces not Specified by Area or Structure
1. Equipment and Metal Appurtenances
a. Equipment, non immersed, unless otherwise specified
1) Indoors E-1
2) Outdoors EU-1
b. Equipment, immersed, unless otherwise specified E-2
c. Existing equipment
1) Not damaged nor modified by work in this contract Uncoated
2) Damaged, exposed, or modified by work in this
contract
a) Indoors E-1 (see paragraph 3.02 )
b) Outdoors EU-1 without primer (see
paragraph 3.02)
d. Electrical switchgear panels, unit substations, motor
control centers, power transformers, distribution
centers, and relay panels; indoors and outdoors
See paragraph 3.03 Electrical
and Instrumentation
Equipment and Materials
e. Instrumentation panels, graphic indicating panels,
indicating and transmitting field panels, unless
otherwise specified
1) Indoors See paragraph 3.03 Electrical
and Instrumentation
Equipment and Materials
2) Outdoors See paragraph 3.03 Electrical
and Instrumentation
Equipment and Materials
Note: Owner will select color from coating manufacturer’s list of EPA approved colors for potable water.
3.07 INSPECTION AND TESTING BY OWNER
A. General:
1. Inspection by the Owner or others does not limit the Contractor’s or CSA’s
responsibilities for quality workmanship or quality control as specified or as required
by the CSM’s instructions. Inspection by the Owner is in addition to any inspection
required to be performed by the Contractor.
2. The Owner may perform, or contract with an inspection agency to perform, quality
control inspection and testing of the coating work covered by this Section 09 90 00.
These inspections may include the following:
a. Inspect materials upon receipt to ensure that are supplied by the CSM.
b. Inspect to verify that specified storage conditions for the coating system
materials, solvents and abrasives are provided.
c. Inspect and record findings for the degree of cleanliness of substrates.
d. Inspect and record the pH of concrete and metal substrates.
e. Inspect and record substrate profile (anchor pattern)
f. Measure and record ambient air and substrate temperature.
g. Measure and record relative humidity.
h. Check for the presence of substrate moisture in the concrete.
Lake Keowee to Adkins WTP Raw Water System Painting and Coating
154828 09 90 00 - 27
i. Inspect to verify that correct mixing of coating system materials is performed in
accordance with CSM’s instructions.
j. Inspect, confirm, and record that the "pot life" of coating system materials is not
exceeded during installation. Inspect to verify that recoat limitations for coating
materials are not exceeded.
k. Perform adhesion testing.
l. Measure and record the thickness of the coating system.
m. Inspect to verify proper curing of the coating system in accordance with the
CSM's instructions.
n. Perform holiday or continuity testing for coatings that will be immersed or
coatings that will be exposed to aggressively corrosive conditions.
3.08 FINAL INSPECTION
A. General
1. Contractor shall conduct a final inspection to determine whether coating system work
meets the requirements of the specifications.
2. The Construction Manager will subsequently conduct a final inspection with the
Contractor to determine the work is in conformance with requirements of the
contract documents.
3. Any rework required shall be marked. Such areas shall be recleaned and repaired as
specified at no additional cost to the Owner.
Lake Keowee to Adkins WTP Raw Water System Signage
154828 10 14 00 - 1
SECTION 10 14 00
SIGNAGE
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies informational and accident prevention signs.
1.02 OPERATING AND DESIGN REQUIREMENTS
A. General:
1. Accident prevention signs shall conform as to design with OSHA Section 1910.145 of
Subpart J, Part 1910, Chapter XVII, Title 29 of the Code of Federal Regulations. Exit
signs shall conform with Section 1910.37(g) of the OSHA Safety and Health Standard
for General Industry, Article 10, Section 10.113 of the Uniform Fire Code, and where
applicable with local fire regulations.
B. Design Requirements:
1. Size:
a. Sign size shall be as follows:
1) 36 inch x 18 inch
2) 14 inch x 20 inch
3) 10 inch x 14 inch
4) 7 inch x 10 inch
2. Type:
a. The sign type shall be as follows:
Type Message
IV DANGER--KEEP OUT
VI DANGER--CONFINED SPACE ENTRY
PART 2 PRODUCTS
2.01 GENERAL
A. Sign lettering shall be single stroke and shall contrast in color with the background. For
those messages for which there are international symbols, the international symbols
shall be used. Chain mounted signs shall have lettering on both sides.
2.02 MATERIALS
A. Signs shall be 0.100-inch thick fiberglass with embedded fadeproof legends.
Lake Keowee to Adkins WTP Raw Water System Signage
154828 10 14 00 - 2
PART 3 EXECUTION
3.01 GENERAL
A. Signs shall be distributed, at each pump station, as follows:
Location Number Size Message Mount
Interconnect Site 2 1 3 IV Hatch
Interconnect Site 2 1 2 VI Hatch
END OF SECTION
DIVISION 31
EARTHWORK
Section Title
31 10 00 SITE CLEARING
31 23 00 EXCAVATION AND FILL
31 23 16 ROCK REMOVAL
31 23 19 DEWATERING
31 25 00 EROSION, SEDIMENTATION AND DUST CONTROL
31 41 00 SHORING
Lake Keowee to WTP Raw Water System Site Clearing
154828 31 10 00 - 1
SECTION 31 10 00
SITE CLEARING
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope: This section specifies site preparation which consists of clearing, grubbing and
demolition.
B. Existing Conditions: The Contractor shall determine the actual condition of the site as it
affects this portion of work.
C. Protection: Site preparation shall not damage structures, landscaping or vegetation
adjacent to the site. The Contractor shall repair, or replace any damaged property.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
3.01 PREPARATION
A. Coordinate with plant staff not less than five (5) working days before performing Work.
3.02 CLEARING AND GRUBBING
A. Unless otherwise specified, the Contractor shall remove obstructions such as brush,
trees, logs, stumps, roots, heavy sod, vegetation, rock, stones larger than 6 inches in any
dimension, broken or old concrete and pavement, debris, and structures where the
completion of the work require their removal.
B. Remove stumps, main root ball, root system, surface rock, and pavements to depth of
12" below proposed subgrade elevation.
C. Material that is removed and is not to be incorporated in the work shall be disposed of
off the site.
3.03 DEMOLITION AND REMOVAL
A. Structures: Demolition and removal of structures consist of removal of abandoned
superstructures, foundation walls, footings, slabs and any other structures. Excavations
caused by existing foundations shall be cleared of waste, debris and loose soil, and
refilled as specified.
B. Drain manholes and poke holes in manhole floors and walls prior to filling. When
adjacent sewer lines are not to be filled, place temporary plugs in each line connecting to
manhole, in preparation for filling manhole.
Lake Keowee to WTP Raw Water System Site Clearing
154828 31 10 00 - 2
C. Pavement: When portions of asphalt pavements and concrete pads are to be removed
and later construction is to be connected, edges shall be saw cut, on a neat line at right
angles to the curb face.
D. Salvage: The Owner has the right to salvage any items scheduled for removal. The
Contractor shall notify the Construction Manager 5 days prior to any salvage or
demolition work to determine the disposition of items to be removed. The Construction
Manager will mark items to be salvaged. Such items shall be properly disconnected,
removed from their foundations, cleaned, and stored at a location on the plant site as
specified. The following items have been identified for salvage:
1. Air release valves
3.04 UTILITY INTERFERENCE
A. Where existing utilities interfere with the prosecution of the work, the Contractor shall
relocate them in accordance with the General Conditions of the Contract Documents.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 1
SECTION 31 23 00
EXCAVATION AND FILL
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies earthwork which consists of excavation, filling, grading, and
disposal of excess material.
B. Definitions:
1. Compaction: The degree of compaction is specified as percent compaction.
Maximum or relative densities refer to dry soil densities obtainable at optimum
moisture content.
2. Excavation Slope: Excavation slope shall be defined as an inclined surface formed by
removing material from below existing grade.
3. Embankment Slope: Embankment slope shall be defined as an inclined surface
formed by placement of material above existing grade.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, whether or not the document has been superseded by a version with a later
date, discontinued or replaced.
Reference Title
ASTM C136 Standard Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D1556 Test Method for Density of Soil in Place by the Sand-Cone Method
ASTM D1557 Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate
Mixtures Using 10-lb (4.5-kg) Rammer and 18-in. (457-mm) Drop
ASTM D2419 Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate
ASTM D3017 Test Method for Moisture Content of Soil and Soil- Aggregate in Place by
Nuclear Methods (Shallow Depth)
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 2
B. Tests:
1. The Construction Manager will take samples and perform moisture content,
gradation, compaction, and density tests during placement of backfill materials to
check compliance with these specifications. The Contractor shall remove surface
material at locations designated by the Construction Manager and provide such
assistance as necessary for sampling and testing. The Construction Manager may
direct the Contractor to construct inspection trenches in compacted or consolidated
backfill to determine that the Contractor has complied with these specifications.
Payment for inspection trenches shall be as specified in the General Conditions of
the Contract Documents .
2. Tests will be made by the Construction Manager in accordance with the following:
Test Standard Procedure
Moisture content ASTM D3017
Gradation ASTM C136
Density in-place ASTM D1556
Moisture-density relationships ASTM D1557
1.03 SUBMITTALS
A. Samples of fill materials to be used shall be submitted 2 weeks in advance of use.
Samples shall consist of 0.5 cubic feet of each type of material.
PART 2 PRODUCTS
2.01 FILL MATERIALS
A. Type A:
1. Type A material shall be a clean gravel-sand mixture free from organic matter and
shall conform to the following gradation:
U.S. standard sieve size Percent by weight passing
3/4 inch 100
3/8 inch 70-100
No. 4 55-100
No. 10 35-95
No. 20 20-80
No. 40 0-55
No. 100 0-2
B. Type B:
1. Type B material shall be a select granular material free from organic matter and of
such size and gradation that the specified compaction can be readily attained.
Material shall have a sand equivalent value determined in accordance with ASTM
D2419 of not less than 20 and shall conform to the following gradation:
U.S. standard sieve size Percent by weight passing
3 inch 100
No. 4 35-100
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 3
No. 30 20-100
2. The coefficient of uniformity shall be 3 or greater.
3. The material may be an imported quarry waste, clean natural sand or gravel, select
trench excavation or a mixture thereof.
C. Type C:
1. Type C material shall be unclassified material which is free from peat, wood, roots,
bark, debris, garbage, rubbish or other extraneous material. The maximum size of
stone shall not exceed 6 inches. If the material excavated from the site meets these
requirements, it may be classified as Type C.
D. Type D:
1. Type D material shall be free-draining granular material or commonly known as #57
stone and shall conform to the following gradation:
U.S. standard sieve size Percent by weight passing
1 – ½ inch 100
1 – inch 90-100
1/2 – inch 25-60
No.4 0-10
No. 8 0-5
E. Type F:
1. Type F material shall be crushed rock and shall conform to the following gradation:
U.S. standard sieve size Percent by weight passing
1-1/2 inch 87-100
3/4 inch 45-90
No. 4 20-50
No. 30 6-29
No. 200 0-12
2. Type F material shall be composed of hard, durable, sound pieces having a specific
gravity of not less than 2.65.
PART 3 EXECUTION
3.01 GENERAL
A. Control of Water:
1. The Contractor shall keep excavations reasonably free from water during
construction. The static water level shall be drawn down a minimum of 2 feet below
the bottom of excavations to maintain the undisturbed state of natural soils and
allow the placement of any fill to the specified density. Disposal of water shall not
damage property or create a public nuisance. The Contractor shall have on hand
pumping equipment and machinery in good working condition for emergencies and
shall have workmen available for its operation. Dewatering systems shall operate
continuously until backfill has been completed to 1 foot above the normal static
groundwater level.
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 4
2. Groundwater shall be controlled to prevent softening of the bottom of excavations, or
formation of "quick" conditions. Dewatering systems shall not remove natural soils.
The Contractor shall control surface runoff to prevent entry or collection of water in
excavations.
3. Release of groundwater to its static level shall be controlled to prevent disturbance of
the natural foundation soils or compacted fill and to prevent flotation or movement of
structures or pipelines.
B. Overexcavation:
1. Where the undisturbed condition of natural soils is inadequate for support of the
planned construction, the Construction Manager will direct the Contractor to
overexcavate to adequate supporting soils. The excavated space shall be filled to the
specified elevation with backfill. The overexcavated space under footings may be
filled with concrete. The quantity and placement of such material will be paid for as
extra work.
C. Surplus Material:
1. Unless otherwise specified, surplus excavated material shall be disposed of off site in
accordance with applicable ordinances and environmental requirements.
2. If the quantity of surplus material is specified, the quantity specified is approximate.
The Contractor shall satisfy himself that there is sufficient material available for the
completion of the embankments before disposing of any material inside or outside
the site. Shortage of material, caused by premature disposal of any material by the
Contractor, shall be replaced by the Contractor.
3. Material shall not be stockpiled to a depth greater than 5 feet above finished grade
within 25 feet of any excavation or structure except for those areas designated to be
preconsolidated. For these areas, the depth of stockpiled material shall be as
specified. The Contractor shall maintain stability of the soil adjacent to any
excavation.
D. Borrow Material:
1. If the quantity of acceptable material from excavation is not sufficient to construct
the embankments required by the work, the quantity of material needed to complete
the embankments shall consist of imported borrow conforming to specified
requirements.
E. Hauling:
1. When hauling is done over highways or city streets, the loads shall be trimmed and
the vehicle shelf areas shall be cleaned after each loading. The loads shall be
watered after trimming to eliminate dust.
F. Finish Grading:
1. Finished surfaces shall be smooth, compacted and free from irregularities. The
degree of finish shall be that normally obtainable with a blade-grader.
2. Finished grade shall be as specified by the contours plus or minus 0.10 foot except
where a local change in elevation is required to match sidewalks, curbs, manholes
and catch basins, or to ensure proper drainage. Allowance for topsoil and grass
cover, and subbase and pavement thickness shall be made so that the specified
thickness of topsoil can be applied to attain the finished grade.
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 5
3. When the work is an intermediate stage of completion, the lines and grades shall be
as specified plus or minus 0.5 foot to provide adequate drainage.
4. If the soil is to be cultivated or straw is to be incorporated into the surface, rocks
larger than 2-1/2 inches in maximum dimension, roots and other debris on the
surface of the slope shall be removed and disposed of prior to cultivation or
placement of straw.
G. Control Of Erosion:
1. The Contractor shall maintain earthwork surfaces true and smooth and protected
from erosion. Where erosion occurs, the Contractor shall provide fill or shall excavate
as necessary to return earthwork surfaces to the grade and finish specified.
3.02 CLASSIFICATION OF FILL
A. Fill material shall be placed in horizontal layers and compacted with power-operated
tampers, rollers, idlers, or vibratory equipment. Material type, maximum layer depth,
relative compaction, and general application are specified in Table A. Unless otherwise
specified, fill classes shall be used where specified in Table A under general application.
Table A, Fill Classifications
Fill class Material
type
Maximum
uncompressed layer
depth, inches
Minimum relative
compaction, percent
General application
A1 A 8 95 Bedding for pipe, initial pipeline backfill; slabs
on grade
B1 B 8 95 Structure and subsequent pipeline backfill
B2 B 8 90 Site fill
C1 C 8 90-95 Subsequent pipeline backfill; compaction as
specified
C2 C 8 90 Site fill, embankments and dikes
D1 D - 95 Bedding for pipe, initial and subsequent tank
and pipeline backfill
F1a F 12 95 Structure and pipeline bedding, initial and
subsequent pipeline backfill
a. Material shall not be used for bedding or initial backfill for plastic pipe.
3.03 EARTHWORK FOR STRUCTURES
A. Structure Excavation:
1. The bottom shall not be more than 0.15 foot above or below the lines and grades
specified. If the elevation of structure excavation is not specified, the excavation shall
be not more than 0.15 foot above or below the elevation specified for fill material
below the structure. Slopes shall vary no more than 0.5 foot from specified grade
unless the excavation is in rock where the maximum variation shall be 2 feet.
2. Should the excavation be carried below the lines and grades specified on the
drawings or should the bottom of the excavation be disturbed because of the
Contractor's operations and require overexcavation and backfill, the Contractor shall
refill such excavated space to the proper elevation in accordance with the procedure
specified for backfill. The cost of such work shall be borne by the Contractor.
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 6
3. Unless otherwise specified, excavations shall extend a sufficient distance from walls
and footings to allow for placing and removal of forms, installation of services, and
for inspection, except where concrete is specified to be placed directly against
excavated surfaces.
B. Foundation Treatment:
1. Rock foundations for concrete or masonry footings shall be excavated to sound
material. The rock shall be roughly leveled or cut to steps and shall be roughened.
Seams in the rock shall be grouted under pressure as directed by the Construction
Manager and paid for as extra work.
2. When footings are to be supported on piles, excavations shall be completed to the
bottom of the footings before any piles are drilled or driven therein. When swell or
subsidence results from driving piles, the Contractor shall excavate, or backfill the
footing area to the grade of the bottom of the footing with suitable material as
specified. If material under footings is such that it would mix into the concrete during
footing placement or would not support the weight of the fluid concrete, the
Contractor shall replace the material with suitable material, install soffit forms or
otherwise provide a suitable platform on which to cast the footing as directed by the
Construction Manager. This shall be paid for as extra work.
3. Whenever any structure excavation is substantially completed to grade, the
Contractor shall notify the Construction Manager who will make an inspection of the
foundation. No concrete or masonry shall be placed until the foundation has been
inspected by the Construction Manager. The Contractor shall, if directed by the
Construction Manager, dig test pits and make test borings and foundation bearing
tests. If the material tested is undisturbed soil, the cost thereof will be paid for as
extra work. If the material tested is backfill material, the cost thereof will be paid as
specified in the General Conditions of the Contract Documents.
C. Structure Backfill:
1. Unless otherwise specified, structure backfill shall be Class B1.
2. After completion of construction below the elevation of the final grade, and prior to
backfilling, forms shall be removed and the excavation shall be cleaned of debris.
3. Structure backfill shall not be placed until the subgrade portions of the structure
have been inspected by the Construction Manager. No backfill material shall be
deposited against concrete structures until the concrete has developed a strength of
not less than 2500 pounds per square inch in compression, or until the concrete has
been in place for 28 days, whichever occurs first.
4. Backfill material shall be placed in uniform layers and shall be brought up uniformly
on all sides of the structure. When compaction is done by ponding and jetting,
thickness of uncompacted layers shall not exceed 4 feet.
5. Compaction of structure backfill may be performed by ponding and jetting if the
backfill material is of such character that it will be self-draining when compacted and
that foundation materials will not be damaged by the applied water and no damage
from hydrostatic pressure will result to the structure. Ponding and jetting shall not be
used within 4 feet of finished grade and shall be performed in such a manner that
water will not be impounded.
6. Unless otherwise specified, backfill around and above pipelines within the excavation
line of any structure shall be the same as that specified for structures.
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 7
3.04 EARTHWORK FOR PIPELINES AND CONDUITS
A. General:
1. Earthwork for pipelines and conduits is specified in Table A; in the standard details;
and in the following paragraphs.
B. Pipeline Excavation:
1. The bottom of the trench shall be carried to the specified lines and grades with
proper allowance for pipe thickness and for bedding as specified.
C. Pipeline Backfill:
1. Bedding: The Contractor shall not proceed with backfill placement in excavated areas
until the subgrade has been inspected by the Construction Manager. All pipe shall
have a minimum thickness of bedding material below the barrel of the pipe as
specified. Bedding material shall be placed in the bottom of the trench, leveled and
compacted. Bell holes shall be excavated at each pipe joint to permit proper
inspection and uniform bearing of pipe on bedding material.
a. After the pipe has been laid to alignment and grade, unless otherwise specified,
additional bedding material shall be placed in layers the full width of the trench
and compacted up to the specified level. Bedding shall be placed simultaneously
on both sides of the pipe, keeping the level of backfill the same on each side. The
material shall be carefully placed and compacted around the pipe to ensure that
the pipe barrel is completely supported and that no voids or uncompacted areas
are left beneath the pipe. Contractor shall use particular care in placing material
on the underside of the pipe to prevent lateral movement during backfilling.
2. Initial Backfill: After pipe has been properly bedded, Contractor shall place and
compact initial backfill as specified. Initial backfill, where specified below the
springline of the pipe, shall be placed and compacted in accordance with
paragraph 3.04 Pipeline Backfill for additional bedding material.
3. Subsequent Backfill:
a. General: Backfill material, placement and compaction above the pipe zone shall
be as specified. Backfill above the pipe zone shall not commence until pipe zone
backfill has been inspected and accepted by the Construction Manager.
b. Improved Areas: Unless otherwise specified, select granular backfill (Class B1,
C1, D1, or F1 shall be used under all paved and unpaved roadways and paved
and unpaved roadway shoulders, roadway embankments, and in all public right-
of-ways and easements. The trench shall be backfilled to an elevation which will
permit the placement of the specified surface or paving. Paving shall be as
specified in Section 32 12 16. Other surfaces shall be restored, including
compaction, to the condition existing prior to construction including restoration of
yard areas.
c. Unimproved Areas: Class C1 backfill shall be used for all trenches in pastureland,
cultivated land, undeveloped land, and for other unimproved areas where
specified. Class C1 backfill shall not be used in any public right-of-way. Trench
excavation which meets the requirements of Type C material may be used. The
Contractor shall maximize the use of fine-grained materials (e.g., sand, silty sand,
sandy silt) as Class C1 backfill.
1) For Class C1 backfill, the trench above the pipe zone shall be backfilled to
within 12 inches of original ground surface. The top 12 inches of soil shall be
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 8
removed and stored in such a manner that it will not become mixed with
unsatisfactory soils. After the trench has been backfilled, the stored topsoil
shall be replaced at a uniform depth in its original area compacted to its
original condition. The Contractor shall leave the backfilled trench neatly
mounded not more than 6 inches above existing grade for the full width of
the Class C1 backfill area.
3.05 EARTHWORK FOR EMBANKMENTS
A. Foundation Preparation:
1. The surface of the foundation shall not contain standing water and shall be free of
loose material, foreign objects and rocks greater than 6 inches in maximum
dimension. Immediately prior to placement of embankment fill material, the
foundation surface shall be thoroughly moistened, scarified to a depth of 6 inches,
moisture conditioned again as necessary and recompacted to 95 percent relative
compaction. After the preparation has been completed, the Contractor shall promptly
place and compact the first lift of embankment on the foundation to prevent damage
to the surface. If the foundation surface is damaged, the Contractor shall repair the
surface to the specified condition. In any areas where materials become soft or
yielding, such materials shall be removed, disposed of, and replaced with specified
material. The surface of the embankment shall be maintained to permit travel of
construction equipment. Ruts in the surface of any layer shall be filled and leveled
before compacting.
B. Embankment Fill:
1. Rocks, broken concrete, or other solid materials, which are larger than 4 inches in
greatest dimension, shall not be placed in embankment areas where piles are to be
placed or driven.
2. Fill material having a sand equivalent value less than 10 shall be placed in the lower
portions of embankments and shall not be placed within 2.5 feet of finished grade.
3. When the embankment material consists of large, rocky material, or hard lumps,
such as hardpan or cemented gravel which cannot be broken readily, such material
shall be well distributed throughout the embankment. Sufficient earth or other fine
material shall be placed around the larger material as it is deposited so as to fill the
interstices and produce a dense, compact embankment.
4. Unless otherwise specified, the embankment shall be raised to form an
approximately horizontal plane extending transversely to the final slopes. The
embankment shall be crowned at all times during construction so that water will
drain readily off the embankment.
5. The temporary differential elevation between any two adjoining zones of the
embankment due to construction operations shall not exceed 24 inches.
6. If the compacted surface of any layer of material is too smooth to bond properly with
the succeeding layer, the surface shall be scarified. If required, the surface shall be
sprinkled or otherwise moisture conditioned before the succeeding lift is placed. Any
surface crust formed on a layer of fill material that has been dumped and spread
shall be broken up by harrowing and, if required, the full depth of the affected layer
shall be moisture conditioned immediately prior to rolling.
C. Key Construction:
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 9
1. Where specified, a key shall be excavated along the length of the toe of fill slopes.
The exposed soils along the key and under fill areas shall be disced and/or scarified
to a depth of at least 12 inches, moisture conditioned to within 3 percent of optimum
moisture content, and compacted to at least 90 percent of maximum dry density.
D. Embankment Tolerances:
1. General: Embankment slopes within 4 feet of shoulder grade shall vary less than 0.5
foot from the designated slope. Slopes beyond 4 feet from shoulder grade shall vary
less than 1 foot from the designated slope. Measurements for variance shall be
made perpendicular to the slope. Slopes which are 6 to 1 or flatter shall vary less
than 0.2 foot from the designated slope.
a. If embankments are constructed of rock greater than 12 inches in diameter, the
slopes more than 4 feet below shoulder grade may vary up to 2 feet from the
designated slope.
2. Roadway Embankment Tolerances: The excavated surface shall be less than 0.08
foot above or below the grades specified after deducting for the roadway pavement
thickness.
a. Vertical alignment tolerances permitted on the roadway surface shall not exceed
plus or minus 0.30 feet from the vertical alignment specified, with the provision
that within the tolerance range local surface irregularities shall not exceed 0.15
feet as measured by the gap between the roadway surface and a 10-foot
straightedge placed on any flat graded surface. On vertical curves, the same
standards will apply except that an additional gap allowance will be made for the
road surface curvature over the 10-foot length of the straightedge.
b. Horizontal alignment tolerances permitted shall not exceed plus or minus 1 foot
providing the departure is relatively uniform over any specific length of the
roadway.
c. Roadway median strips shall be graded to drain and shall not vary more than 0.1
foot from the specified grade.
3.06 SUBGRADE FOR PAVEMENT
A. The prepared subgrade shall be scarified to a depth of at least 12 inches and
recompacted to at least 95 percent of the maximum density.
B. Proof roll areas to receive pavement to identify areas of soft yielding soils.
1. Use loaded tandem-axle pneumatic tired dump truck or large smooth drum roller.
2. Load equipment to maximum 50 tons gross weight and make a minimum of four
passes with two passes perpendicular to the others.
3.07 SITE FILL
A. Unless otherwise specified, site fill shall be Class C2 fill. If the existing slope in an area to
be filled is greater than 5:1, the Contractor shall bench the area prior to filling.
3.08 GROUTING RIPRAP
A. When riprap is properly positioned, stones shall be flushed with water to remove fines,
and cement grout as specified in Section 03 60 00 shall be applied. Stones shall be wet
prior to and during grout application. Grout shall be applied in two courses using baffles
Lake Keowee to Adkins WTP Raw Water System Excavation and Fill
154828 31 23 00 - 10
and diverting equipment. The first course shall completely penetrate the stone voids and
shall be applied with the aid of poles or rods to loosen the tight pockets of stone. The
second course shall be applied as soon as the first course has jelled. The second course
shall be broomed uphill during application, and the entire surface shall be rebroomed to
eliminate runs and fill voids.
B. After grouting is complete, no load shall be permitted on the grouted surface for 24
hours. The grouted surface shall be protected from damage until curing is complete. The
grout shall be cured as specified in Sections 03 30 00-3.05 and 3.06.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Rock Removal
154828 31 23 16 - 1
SECTION 31 23 16
ROCK REMOVAL
PART 1 GENERAL
1.01 DESCRIPTION
A. Removal of subsurface rock encountered during excavation, utilizing mechanical or
blasting methods.
1.02 RELATED SECTIONS
A. Section 01560, Environmental Controls
B. Section 02100, Site Preparation
C. Section 02200, Earthwork
1.03 REFERENCES
A. NFPA 495 – EXPLOSIVE MATERIALS CODE, 2001 EDITION
1.04 DEFINITIONS
A. Rock, in the opinion of the Engineer, cannot be excavated except by drilling, blasting,
“jack hammering” or “hoe ramming” and includes sound solid masses, layers and ledges
of consolidated and indurated rock or mineral matter of such hardness, durability and/or
texture that it is not rippable or cannot be excavated with normal earth excavation
equipment such as a Caterpillar 320 series excavator, or equal. Rock exceeds
moderately hard rock hardness, as defined in, as defined in as defined in “Subsurface
Manual for Design and Construction of Buildings," 1976, published by the American
Society of Civil Engineers. These definitions are summarized in the following:
1. ROCK HARDNESS CRITERIA
a. Very Hard - Cannot be scratched with knife or sharp pick. Breaking of hand
specimen requires several hard blows of geologist's pick.
b. Hard - Can be scratched with knife or pick only with difficulty. Hard blow of
hammer required to detach hand specimen.
c. Moderately - Can be scratched with knife or pick. Gouges or grooves to ¼ inch
deep can be excavated by hard blow of point of a geologist's pick. Hand
specimens can be detached by moderate blow.
d. Medium - Can be grooved or gouged 1/16 inch deep by firm pressure on knife or
pick point. Can be excavated in small chips to pieces about 1 inch maximum size
by hard blows of the point of a geologist's pick.
e. Soft - Can be gouged or grooved readily with knife or pick point. Can be
excavated in chips to pieces several inches in size by moderate blows of pick
point. Small thin pieces can be broken by finger pressure.
f. Very Soft - Can be carved with knife. Can be excavated readily with point of pick.
Pieces 1 inch or more in thickness can be broken with finger pressure. Can be
scratched readily by fingernail.
Lake Keowee to Adkins WTP Raw Water System Rock Removal
154828 31 23 16 - 2
1.03 QUALIFICATIONS
A. Explosives – Retain company, firm, subcontractor or individual specializing in explosives
for disintegration of rock, with five year documented experience.
1.04 REGULATORY REQUIREMENTS
A. Conform to applicable State and local codes for explosive disintegration of rock and to
NFPA 495 for handling explosive materials.
B. Obtain permits from authorities having jurisdiction before explosives are brought to site
or drilling is started.
1.05 SCHEDULING
A. Schedule blasting work to be completed between the hours of 9 a.m. and 5 p.m. Monday
through Friday, excluding holidays.
B. Schedule work to minimize disruption of vehicular traffic in nearby public thoroughfares.
C. Coordinate schedule with local police and fire departments, including owners of nearby
existing facilities.
1.06 SUBMITTALS
A. Seismic Survey Firm – Retain Company specializing in seismic surveys with five years
documented experience. Submit name and qualifications. Submit blasting monitoring
reports to the Engineer.
B. Explosives – Retain company, firm, subcontractor or individual specializing in explosives
for disintegration of rock, with five year documented experience. Submit name and
qualifications.
C. Measurement Sketches – Submit plan and profile sketches from surveys showing
stationing and rock encountered as agreed to by the Engineer. For payment to be made,
certified measurement sketches must be provided by the Contractor. Logs alone from
the drilling and blasting firm are NOT adequate to verify payment.
1.07 BLASTING SURVEY
A. Where blasting is approved by Engineer, pre-blasting and post-blasting surveys shall be
conducted on and reported for all major structures within the influence range of any
blasting operations or within a minimum of 1,000 feet, whichever is greater, from any
blast site. The surveys shall consist of a visual inspection and recording by notes and
photographs of structures, to include specifically cracks or other structural damage
previously sustained. Pre-blast surveys shall be conducted by a qualified technician
approved by the Owner. The preconstruction survey will not damage equipment or
facilities. A copy of all notes and photographs shall be submitted to the Contractor prior
to the beginning of blasting operations and prior to final payment. The records so
obtained shall be retained in the Contractor’s file for at least 1 year after completion of
the Contract. In the event of any damage claim, a report shall be prepared by the
Lake Keowee to Adkins WTP Raw Water System Rock Removal
154828 31 23 16 - 3
Contractor on the particular structure involved to include those notes and photographs
and submitted to the Engineer.
B. Costs for blasting surveys shall be paid directly by the Contractor.
C. The Contractor shall make all necessary contacts with property owners for the blasting
surveys, and shall be responsible for all communications with the owners.
PART 2 PRODUCTS
2.01 MATERIALS
A. Explosives – Type recommended by explosives firm.
B. Delay Device – Type recommended by explosives firm.
C. Blast Mat Materials – Type recommended by explosives firm.
PART 3 EXECUTION
1.01 EXAMINATION
A. Verify site condition and location of nearby buildings, structures and other facilities,
recording irregularities, which exist prior to work of this Section.
B. Verify locations of nearby underground utilities and structures.
1.02 PREPARATION
A. Identify required lines, levels, contours, and datum; establish quantity of rock to be
removed to meet project requirements.
B. Conduct survey and document conditions of buildings and structures near locations of
rock removal, and prior to blasting, photograph existing conditions identifying existing
irregularities. Provide a minimum of two (2) copies of pre-blast survey reports to
ENGINEER prior to any blasting.
1.03 ROCK REMOVAL – MECHANICAL METHOD
A. Excavate and remove rock by mechanical method at locations required by the Contract
Documents and when trimming bottom or sides of excavation is necessary to meet
project requirements.
B. Drill holes and utilize expansive tools, wedges, and/or mechanical disintegration
compound, as appropriate, to fracture rock.
C. Cut away rock at bottom of excavation to form level bearing surface for foundations of
buildings and structures.
D. Remove shaled layers to provide sound and unshattered base.
Lake Keowee to Adkins WTP Raw Water System Rock Removal
154828 31 23 16 - 4
E. In utility trenches, trim rock to 6 inches below bottom of installed pipe and 12 inches
wider than outside diameter of installed pipe.
1.04 ROCK REMOVAL – BLASTING METHOD
A. If blasting method is utilized for rock disintegration, notify the ENGINEER and execute as
follows:
1. Advise owners of adjacent buildings, structures and utilities in writing, prior to
executing seismographic survey. Explain planned blasting and seismic operations.
Allow sufficient time for owners to implement their own protective measures.
2. Obtain a seismic survey prior to rock excavation to determine maximum charges that
can be used at different locations in area of excavation without damaging adjacent
properties of other work.
3. Prior to blasting, allow time for ENGINEER to take site measurements of rock
quantities to be removed.
4. Adequately cover blast area to prevent flyrock. Blast mats or overburden soil are
acceptable, but no off-site soil may be imported to be used as overburden.
5. Notify police and fire departments of blasting time schedule.
6. Provide seismographic monitoring during all blasting operations when within SCDOT
Highway rights-of-way and within 100 feet of existing buildings.
7. Disintegrate rock and remove from excavation.
8. Cut away at excavation bottom to form level bearing surface for foundation of
buildings and structures and bedding of utility mains.
9. Remove fractured layers to provide a sound and unshattered base prior to pipe
installation.
10. In utility trenches, trim rock to 6 inches below bottom of installed pipe and 12 inches
wider than outside diameter of installed pipe.
11. In addition to observing all laws, regulations, and ordinances relating to transporting
storage and handling of explosives, conform to any further requirement with the
Engineer may deem appropriate.
1.05 DISPOSAL AND REPLACEMENT OF ROCK
A. Trench excavation, consisting of rock exceeding 50 pounds in weight, and smaller
fragments when directed by the Engineer, shall not be used for backfilling. Approved
borrow to supply any deficiency of trench backfill shall be provided by the Contractor
without additional payment.
B. The Contractor shall remove and dispose of all pieces of rock which are not suitable for
use in other parts of the work. Rock disposed of by hauling away to spoil areas is to be
replaced and approved surplus excavation obtained elsewhere on the site, insofar as it is
available. Any deficiency in the backfill material shall be made up with acceptable
material from outside sources as approved by the Engineer.
C. Fragments of rock may not be used in backfilling pipe. Backfilling trench is further
specified under Section 31 23 00. Nesting of rock fragments will not be permitted and
will be removed as directed by the Engineer.
Lake Keowee to Adkins WTP Raw Water System Rock Removal
154828 31 23 16 - 5
D. If rock below grade is shattered by blasting caused by holes drilled too deep, or too heavy
charges of explosives, or any other circumstance due to blasting; and if, in the opinion of
the Engineer, the shattered rock is unfit for use on the job, the rock shall be removed and
the excavation refilled with crushed stone at the expense of the Contractor.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Dewatering and Drainage
154828 31 23 19 - 1
SECTION 31 23 19
DEWATERING AND DRAINAGE
PART 1 GENERAL
1.01 SUMMARY
A. The Contractor shall design, furnish, operate, and remove temporary dewatering systems
to lower and control water to maintain stable, undisturbed subgrades.
B. Dewatering includes but is not limited to the lowering of the water table, the lowering of
the hydrostatic pressure, preventing surface water from entering the excavation during
construction, preventing ground water from entering the excavation during construction,
installation of recharging systems and/or disposing of discharge water, and installing and
monitoring observation wells and settlement markers. Common dewatering methods
include sump pumping, deep wells, well points or combinations thereof.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00:
1. Qualifications of Dewatering Specialist
a. List of at least five successful dewatering projects. Contact information shall
include names, current addresses, and telephone numbers of the Owner or
persons who were in charge of representing the Owner of those five construction
projects during the time of the dewatering.
b. Contractor shall submit qualifications of specialist's or firm's South Carolina
Registered Professional Engineer who shall stamp and seal shop drawings of
dewatering plan. Contractor shall submit qualifications of specialist's or firm's
field representative who shall oversee the installation, operation and
maintenance of the dewatering system.
2. Dewatering Plan
a. Shop drawings and calculations stamped and signed by a South Carolina
Registered Professional Engineer. Drawings shall indicate the locations and sizes
of berms, dikes, ditches, all deep wells, observation wells, sand and gravel filters,
piezometers, settlement points, well points, sumps, recharge systems, and
discharge lines, including their relation to sedimentation ponds.
b. Dewatering plan shall also include a description of the capacities of the pumps,
prime movers, and standby equipment. The plan shall also include a detailed
description of the sequence of dewatering activities, maintenance requirements
and system removal procedures and a list of all applicable laws, regulations,
rules, and codes to which dewatering design conforms.
3. Dewatering System Monitoring Reports
a. Contractor shall submit to Engineer observation well data, daily piezometric levels
shall be identified by date, time, well number, and system (subsystem if multiple
pumps are used) pumping rate. Piezometric levels shall be reported in feet of
drawdown and groundwater elevation.
Lake Keowee to Adkins WTP Raw Water System Dewatering and Drainage
154828 31 23 19 - 2
b. Contractor shall submit to Engineer dewatering well data, suspended material
test results shall be identified by date, time, well number, well pumping rate (if
monitored) and system (subsystem if multiple pumps are used) pumping rate.
4. Modified Dewatering Plan
a. A modified dewatering plan shall be submitted to the Engineer within 24 hours, if
open pumping from sumps and ditches results in boils, loss of fines, softening of
the ground or instability of the slopes.
1.03 QUALITY ASSURANCE
A. Contractor shall prepare dewatering design including calculations and drawings under
the direction of a South Carolina Registered Professional Engineer. All dewatering design
drawings, calculations, and details shall be stamped and signed by a South Carolina
Registered Professional Engineer.
B. When the use of well points, deep wells, recharge systems, or equal systems are required
to design the groundwater control, the Contractor shall employ the services of a
dewatering specialist that has the following qualifications:
1. A minimum of 10 years’ experience in the design and construction of well points,
deep wells, recharge systems, or equal systems.
2. Have completed at least five successful dewatering projects of equal size and
complexity and with equal systems.
3. Retains the services of a South Carolina Registered Professional Engineer with a
minimum of 10 years’ experience in the design of well points, deep wells, recharge
systems, or equal systems.
4. Retain the services of a field representative having a minimum of 5 years’ experience
in the design and installation of well points, deep wells, recharge systems, or equal
systems.
C. The Contractor shall notify the Engineer immediately if any settlement or movement is
detected of survey points on structures adjacent to excavations being dewatered. If
settlement or movement is deemed to be related to the dewatering, discontinue
dewatering and submit a modified dewatering plan to the Engineer within 24 hours. Do
not continue dewatering until the modified dewatering plan has been approved.
Implement the approved modified plan and repair any damage incurred to the adjacent
structures at no additional cost to the Owner.
D. If the dewatering system does not maintain the groundwater level so as to maintain the
specified subgrade condition and density requirements, notify the Engineer and modify
system to perform as specified at no additional cost to the Owner.
E. The Contractor shall obtain and comply with permits, laws, regulations, rules and codes
required.
1.04 SITE CONDITIONS
A. The project geotechnical report (s) include existing geotechnical data of the site,
including boring logs, laboratory and field test results. Locations of the borings shall be
as indicated on the drawings.
Lake Keowee to Adkins WTP Raw Water System Dewatering and Drainage
154828 31 23 19 - 3
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.01 DEWATERING
A. Contractor shall design, furnish, install, and maintain dewatering system in accordance
with approved dewatering plan. Contractor shall follow guidelines recommended by
S&ME, Inc. in their Geotechnical Engineering Report dated November 19, 2020. Locate
dewatering system components so that they do not interfere with construction under this
or other contracts. Dewatering program shall be conducted in such a manner as to
prevent undermining or disturbing foundations of existing structures or of work ongoing
or previously completed.
B. Contractor shall not begin excavation until the dewatering system is fully operational and
the excavation may proceed without disturbance to the final subgrade. Dewatering
should continue until backfilling of excavation reaches a level above original groundwater
level. Dewatering shall continue uninterrupted until the structures, pipes, and
appurtenances to be built there have been completed such that they will not be floated
or otherwise damaged by an increase in groundwater elevation.
C. Contractor shall discontinue open pumping from sumps and ditches, if such pumping is
resulting in boils, loss of fines, softening of the ground, or instability of the slopes. The
dewatering plan will be modified and submitted to the Engineer within 24 hours at no
additional cost to the Owner. Where subgrade materials are unable to meet the
subgrade density requirements due to improper dewatering techniques, remove and
replace the materials in accordance with Section 31 23 00 at no additional cost to the
Owner.
3.02 DEWATERING DISCHARGE
A. Contractor shall install sand and gravel filters in conjunction with well points and deep
wells to prevent the migration of fines from the existing soil during the dewatering
operation. Water from the dewatering operation shall be transported without
interference to other work, damage to existing pavement, other surfaces or property.
Pumped water shall be discharged to a sedimentation pond or drainage system as
indicated or specified. Contractor to install and maintain erosion/sedimentation control
devices at the point of discharge as indicated or specified and as part of the overall
dewatering plan. Do not discharge water from dewatering operations directly into any
live or intermittent stream, channel, wetlands, surface water or any storm sewer. Water
from dewatering operations shall be treated by filtration, settling basins, or other
approved method to reduce the amount of sediment contained in the water to allowable
levels. Under no circumstances shall water from dewatering systems be discharged into
sanitary sewer systems. Engineer reserves the right to sample the discharge water at any
time to ensure environmental laws and permits are being adhered to.
B. Contractor shall not pump water found to be contaminated with oil or other hazardous
material into indicated or specified sedimentation ponds or drainage systems without
treatment.
Lake Keowee to Adkins WTP Raw Water System Dewatering and Drainage
154828 31 23 19 - 4
3.03 MONITORING DEVICES AND RECORDS
A. Contractor shall install, maintain and take measurements at least once a day and three
times a day for 3 days after dewatering startup or during failure of dewatering system,
from observation wells during the period of time that the dewatering system is in
operation. Contractor shall extend observation wells below the earth retention system
and install them around the perimeter of the excavation. Observation wells shall not be
spaced more than 100 feet apart around the perimeter of the excavation. Observation
wells shall be installed midway between, multiple stage well point systems and/or deep
well shafts. Contractor shall modify the dewatering system in order to maintain the
specified water level.
B. Contractor shall install, maintain and take measurements from the geotechnical
instruments, including settlement markers (reference points on surrounding structures)
and piezometers, as part of the overall dewatering plan. Settlement markers shall be
placed on all structures within a distance equal to twice the depth of the excavation, from
the closest edge of the excavation. Settlement survey measurements shall be taken and
reported to 0.001 feet.
3.04 REMOVAL OF DEWATERING SYSTEM
A. Contractor shall not remove the dewatering system without written approval from the
Engineer. Contractor shall backfill and compact sumps or ditches with screened gravel
or crushed rock in accordance with Section 31 23 00.
B. Contractor shall remove well points and deep wells. Well holes shall be abandoned in
accordance with local and state regulations.
C. If an equal system has been used, Contractor shall remove and backfill in accordance
with approved dewatering plan.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 1
SECTION 31 25 00
EROSION, SEDIMENTATION AND DUST CONTROL
PART 1 GENERAL
1.01 SUMMARY
A. The work shall consist of control measures as required by local regulations, permits
obtained by the Owner and by the Engineer, as specified herein and shown on the
Drawings, during the life of the contract to control erosion, sedimentation, and dust.
B. Establish, construct, and maintain erosion and sediment control measures. Siltation
control devices shall be installed in the appropriate locations before construction begins.
The erosion control structures shall be maintained until temporary ground cover is
established to stop all sediment and erosion. All fines imposed for improper erosion and
sedimentation and control shall be paid by the Contractor responsible for the work.
C. Temporary erosion and pollution control shall include construction work off-site where
such work is necessary as a result of borrow pit operations, haul roads or equipment
storage sites.
D. In addition to permits obtained by the Owner, the Contractor shall acquire any additional
necessary land disturbance permits from the local regulatory agency prior to
commencing work. The Contractor shall be responsible for submitting sufficient
documents such that approval can be acquired.
E. Install temporary erosion and sediment controls that will ensure the stormwater, other
water, and drainage from job site areas which will be stripped or modified of its naturally
existing or artificially established stabilization or protection against erosion shall pass
through some type of filter system before being discharged and that these areas shall be
kept sufficiently moist to control dust.
F. The Contractor shall implement the practices set in the Stormwater Pollution Prevention
Plan (SWPPP) submitted as a part of the Notice of Intent (NOI) for Stormwater Discharges
from Large and Small Construction Activities, NPDES General Permit SCR100000 and
the South Carolina Department of Health and Environmental Control’s (SCDHEC) “Storm
Water Management BMP Handbook.”
1.02 SUBMITTALS
A. The Contractor shall submit a written plan for controlling erosion, sedimentation and
dust. The plan shall conform to the requirements of any permits obtained from local
regulatory agencies. The written plan shall be submitted in accordance with Section 01
33 00 and include at a minimum:
1. Schedule of erosion and sedimentation control activities.
2. Plan for maintenance of sedimentation control structures.
3. List of products and seeding species.
4. Plan for dust control.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 2
1.03 SLOPE PROTECTION AND EROSION CONTROL
A. Whenever steeper slopes or abrupt changes in grade are required, a diversion or berm
ditch shall be constructed at the top of the slope to cause the surface water to flow along
the diversion to a controlled down slope. The diversion shall be protected against
erosion with mulch and hay bales, and paved inverts where needed.
B. Silt barriers shall be constructed around all inlets and maintained throughout
construction. Sediment accumulated behind silt barriers shall be removed when the
ponding capacity is reduced by one-half.
1.04 SILTATION FENCES
A. Siltation fences shall be installed in the locations as indicated on the Drawings. Siltation
fences shall be installed prior to clearing operations. Siltation fences shall be kept in
good repair and maintained throughout construction. Sediment shall be removed when
the ponding capacity is reduced by one-half.
B. Siltation fences shall be constructed around all inlets to the stormwater system. They
shall be repaired and maintained throughout construction. Sediment shall be removed
before the ponding capacity is reduced by one-half.
1.05 DUST CONTROL
A. The Contractor shall exercise precautionary measures to minimize dust emissions, which
will include, but shall not be limited to, periodic sprinkling or wetting of the site. The
Contractor has the option of using a dust palliative. The Contractor must comply with all
local regulations.
PART 2 PRODUCTS
2.01 MATERIALS
A. Silt Fence
1. Silt fence shall be nylon reinforced polyester netting with fabric weight in excess of
4.0 ounces per yard and having a built-in cord running throughout the top edge of the
fabric. Silt fence fabric shall be equal to Mirafi 100X, inert to chemicals commonly
found in soil, and resistant to mildew, rot, insects, and rodent attack.
2. Reinforcing mesh shall be ½ inch galvanized steel
3. Posts shall be steel 48-inch long (min), 50,000 psi min yield. Standard “T” section
with a nominal face width of 1.38” and nominal “T” length of 1.48”. Weigh 1.25
pounds/foot. Have a soil stabilization plate with a minimum cross section area of 17
square inches attached to steel posts. Painted with a water based, baked enamel
paint.
B. Filter Fabric
1. Filter fabric shall conform to the requirements of Section 804.11 of the SCDOT
Specification for Highway Construction.
C. Sediment Tubes
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 3
1. Sediment tubes shall consist of compacted geotextiles, curled excelsior wood,
natural coconut fiber or hardwood mulch. Straw, pine needle and leaf mulch-filled
sediment tubes are not permitted. The outer netting shall consist of seamless, high-
density polyethylene photodegradable materials treated with ultraviolet stabilizers or
with seamless high-density polyethylene non-degradable materials.
2. The sediment tube diameter shall range between 18and 24 inches.
3. Where installed within the SCDOT highway right-of-way, the selected sediment tube
shall be listed on the SCDOT approved products list.
D. Turf Reinforcement Mats
1. Turf reinforcement mats shall be a three-dimensional stable net structure with
sufficient thickness, void space and strength to capture and retain soil I to allow for
the development of root growth and vegetation within the matrix. All components of
the turf reinforcement mat shall be 100-percent synthetic and resistant to biological,
chemical and ultraviolet degradation. The materials shall be designed to reduce soil
erosion and assist in the growth, establishment, and protection of vegetation for a
period exceeding 5 years.
2. The product shall be selected to meet the slope characteristics and design flow
velocity of the application.
E. Netting
1. Netting shall be ½ inch galvanized steel, chicken wire mesh. Netting stakes shall be
either steel rods not smaller than ½ inch diameter or shall be either fir, southern pine
or hemlock.
F. Filter Stone
1. Filter stone shall be Number 57 stone for all silt fence toed in trenches and Number
4 surge stone for all truck cleaning pads at all job site haul road entrances.
G. Check Dam Material
1. Silt check dam material shall be coarse, angular, clean-washed crushed stone,
gravel, or rock ranging in size from 12” D50 Riprap (DHEC) meeting the requirements
of SCDOT Class A or Class B erosion control stone.
H. Riprap
1. Riprap shall consist of clean field stone or rough quarry stone, resistant to
weathering by wind or water, varying in weight from 25 to 250 pounds. Sixty percent
of the riprap shall weigh a minimum of 100 pounds each and no more than 5 percent
of the riprap shall weigh less than 50 pounds each. Riprap thickness shall be 1½
times the diameter of the largest stones used. The specific gravity of the individual
stones should be at least 2.5.
PART 3 EXECUTION
3.01 GENERAL
A. The implementation of all erosion and sedimentation control devices shall be done in
accordance with permits obtained, local regulations and the SCDHEC “Storm Water
Management BMP Handbook.”
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 4
B. The controls shown on the Drawings are to be considered the minimum requirements.
The Contractor shall be responsible for providing any additional control measures
necessary to avoid soil erosion, sedimentation and storm water pollution.
C. Temporary construction exits shall be maintained in a condition that will prevent tracking
or flow of mud out of the work area or onto public roads.
3.02 SILT FENCING
A. Silt fencing shall be installed as shown on the Drawings, and as required to prevent
migration of sediment.
B. The silt fence shall be installed to leave 10 feet between the silt fence and the creek or
wetland.
C. A trench shall be excavated approximately 8 inches wide and 8 inches deep when
placing fabric by hand. Twelve inches of geotextile fabric shall be placed into the 6-inch
deep trench, extending the remaining 8 inches towards the upslope side of the trench.
The trench shall be backfilled with soil or gravel and compacted.
D. Twelve inches of fabric shall be buried into the ground when pneumatically installing silt
fence with a slicing method.
E. Posts shall be installed to a minimum depth of 24 inches, with a minimum of 1 to 2
inches above the fabric, and no more than 3 feet of the post above the ground.
F. The fabric shall be attached to the steel posts using heavy-duty plastic ties that are
evenly spaced and placed in a manner to prevent sagging or tearing of the fabric. In call
cases, ties should be affixed in no less than four places.
G. The fabric shall be installed a minimum of 24 inches above the ground. When
necessary, the height of the fence above ground may be greater than 24 inches.
H. In tidal areas, extra silt fence height may be required. The post height will be twice the
exposed post height. Post spacing will remain the same and extra height fabric will be 4,
5, or 6 feet tall.
I. Locate silt fence checks every 100 feet maximum and at low points.
J. The fence shall be installed perpendicular to the direction of flow and place the fence the
proper distance from the toe of steep slopes to provide sediment storage and access for
maintenance and cleanout.
K. The Contractor shall inspect the silt fencing every 7 calendar days and within 24 hours
after each rainfall event that produces ½ inch or more of precipitation. Check for
sediment buildup and fence integrity. Check where runoff has eroded a channel beneath
the fence, or where the fence has sagged or collapsed by fence overtopping.
1. If the fence fabric tears, begins to decompose, or in any way becomes ineffective,
replace the section of fence immediately.
2. Remove sediment accumulated along the fence when it reaches one-third the height
of the fence, especially if heavy rains are expected.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 5
3. Remove trapped sediment from the site or stabilize it on site.
4. Remove silt fence within 30 days after final stabilization is achieved or after
temporary best management practices (BMPs) are no longer needed.
5. Permanently stabilize disturbed areas resulting from fence removal.
L. Accumulated silt and debris shall be removed by the Contractor from behind the face of
the silt fence as needed to provide proper silt fence operation. Clogged or damaged
fabric shall be immediately replaced at no additional cost.
3.03 SEDIMENT TUBES
A. Sediment tubes shall be installed along contours, in drainage conveyance swales, and
around inlets to help reduce the effects of soil erosion by energy dissipation and
retaining sediment.
B. Sediment tubes shall be located in the area specified on the drawings, and installed in
accordance with the details and manufacturer’s recommendations. The tube shall be
installed so that 20 percent of the tube diameter is buried and there are no gaps
between the bottom of the tube and top of the ground. When the length of the area to be
crossed requires multiple tubes, they shall be installed to allow a minimum of 6-inch
overlap.
C. Tubes shall be securely anchored in place by wood stakes or steel posts, a minimum of
48 inches in length placed on 2-foot centers. Stakes shall be connected to the mesh on
the downstream side and driven to extend 12 inches above the tube.
3.04 TURF REINFORCEMENT MATS
A. The Contractor shall grade and compact the areas to be protected with turf
reinforcement mats (TRM) as indicated on the plans. Large rocks, soil clods, vegetation
and other sharp objects that could keep the TRM from close contact with the subgrade
shall be removed. The top 2 inches of soil, which shall be the seedbed, shall be
loosened. Apply seeding in accordance with the seeding schedule. Do not apply mulch
in areas that are to be covered with TRMs.
B. The Contractor shall install the TRM in accordance with the manufacturer’s
recommendations and the following:
1. The TRM shall extend two to three feet over the crest of the slope and be anchored in
a terminal anchor trench a minimum of 12 inches deep by 6 inches wide. Anchor the
trench at 1-foot spacings and backfill with compact soils. The TRM shall be unrolled
along the placement area and loosely laid (not stretched) in such a manner that it will
conform to the surface irregularities when material is placed on or against it. The
TRM may be folded and overlapped to permit proper placement in the designated
area. Secure TRM to ground surface using U-shaped minimum eight gauge wire
staples driven flush into the soil. All anchors should be between 8 and 18 inches
long and have sufficient anchoring strength to restrain the TRM in its installed
location.
2. The TRM shall be joined by overlapping a minimum of 18 inches (unless otherwise
specified), and secured against the underlying foundation material. Securing pins,
approved and provided by the TRM manufacturer, shall be placed along the edge of
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 6
the panel or roll material to adequately hold it in place during installation. The
upstream or up-slope TRM shall overlap the abutting down-slope TRM. At vertical
laps, securing pins shall be inserted through both layers along a line through
approximately the midpoint of the overlap. At horizontal laps and across slope laps,
securing pins shall be inserted through the bottom layer only. Securing pins shall be
placed along a line approximately 2 inches in from edge of the placed TRM at
intervals not to exceed 12 inches unless otherwise specified. Additional pins shall be
installed as necessary and where appropriate to prevent any undue slippage or
movement of the TRM. The use of securing pins will be held to the minimum
necessary. Pins are to be left in place unless otherwise specified.
3. Should the TRM be torn or punctured, or the overlaps or sewn joint disturbed, as
evidenced by visible fabric damage, subgrade pumping, intrusion, or grade distortion,
the backfill around the damaged or displaced area shall be removed and restored to
the original approved condition. The repair shall consist of a patch of the same type
of TRM being used, overlaying the existing TRM. When the TRM seams are required
to be sewed, the overlay patch shall extend a minimum of 1 foot beyond the edge of
any damaged area and joined by sewing as required for the original TRM except that
the sewing shall be a minimum of 6 inches from the edge of the damaged fabric.
TRM panels joined by overlap shall have the patch extend a minimum of two foot
from the edge of any damaged area.
3.05 STABILIZED CONSTRUCTION ENTRANCES
A. Construction Specifications
1. Clear the entrance/exit area of all vegetation, roots, and other objectionable
material.
2. Grade the road foundation so that the entrance/exit will have a cross slope.
3. Place stone to the dimensions, grade, and elevation shown on plans.
4. Temporary construction entrance/exit shall be constructed using washed stone 2 to
3 inches in size.
5. Construction of temporary construction entrance/exit shall utilize filter fabrics.
B. Maintenance Guidelines
1. Maintain the gravel pad in a condition to prevent mud or sediment from leaving the
construction site. This may require periodic topdressing with 2-inch stone.
Contractor shall immediately remove mud and all objectionable materials spilled,
washed, or tracked onto any road.
3.06 GRASS LINED CHANNEL
A. Construction Specifications
1. Excavate the channel and shape it to an even cross-section as shown. When staking,
indicate a 0.2-foot overcut around the channel perimeter for silting and bulking.
2. Grade soil away from channel so that surface water may enter freely.
3. Apply lime, fertilizer, and seed to the channel and adjoining areas in accordance with
the vegetation plan.
4. Spread straw mulch at the rate of 100 lb/ 1000 ft2.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 7
5. Start laying the jute fiber netting from the top of the upstream end of the channel and
unroll it down grade. Do not stretch netting.
6. Bury the upslope end and staple the net every 12 inches across the top end, every 3
feet around the edges and across the net so that the straw is held closely against the
soil. Do not stretch the netting when stapling.
7. Netting strips should be joined together along the sides with a 3-inch overlap and
stapled together.
8. To join ends of strips, insert the new roll of net in a trench as with upslope end and
overlap it 18 inches with the previously laid upper roll. Turn under 6 inches of the
18-inch overlap and staple every 12 inches across the end.
B. Maintenance Guidelines
1. During the establishment period, check grass-lined channels weekly and after every
rainfall. After grass is established, check the channel weekly and after every heavy
rainfall event. Immediately make repairs. It is particularly important to check the
channel outlet and all road crossings for bank stability and evidence of piping or
scour holes. Remove all significant sediment accumulations to maintain the
designed carrying capacity. Keep the grass in a healthy, vigorous condition at all
times, since it is the primary erosion protection for the channel.
3.07 ROCK CHECK DAMS
A. Construction Specifications
1. Check dams shall be placed at the locations shown on the Drawings. The check
dams shall be field fit into the existing ditch and placed such that the top is below the
ditch to prevent flooding of adjacent areas.
2. Place stone to the lines and dimensions shown in the plan on a filter fabric
foundation.
3. Keep the center stone section at least 9 inches below natural ground level where the
dam abuts the channel banks.
4. Extend stone at least 1.5 feet beyond the ditch banks to keep overflow water from
undercutting the dam as it re-enters the channel.
5. Protect the channel downstream from the lowest check dam, considering that water
will flow over and around the dam.
6. Make sure that the channel reach above the most upstream dam is stable.
7. Ensure that channel appurtenances, such as culvert entrances below check dams,
are not subject to damage or blockage from displaced stones.
B. Maintenance
1. Inspect check dams and channels for erosion damage weekly and after each runoff
event.
2. Anticipate submergence and deposition above the check dam and erosion from high
flows around the edges of the dam. Correct all damage immediately. If significant
erosion occurs between dams, install a protective riprap liner in that portion of the
channel.
3. Remove sediment accumulated behind the dams as needed to prevent damage to
channel vegetation, allow the channel to drain through the stone check dam, and
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 8
prevent large flows from carrying sediment over the dam. Add stones to dams as
needed to maintain design height and cross section.
4. Upon stabilization of the disturbed areas, the check dams shall be removed, and the
remaining sediment cleaned out of the ditch. The Contractor shall reshape the ditch
to its existing shape or blend into the adjacent ditch section. The Contractor shall
properly seed the ditch and protect with matting.
3.08 TREE PRESERVATION AND PROTECTION
A. Construction Specifications
1. Place barriers to prevent the approach of equipment within the drop line of trees to
be retained.
2. Do not nail boards to trees during building operations.
3. Do not cut tree roots inside the tree drip line.
4. Do not place equipment, construction materials, topsoil, or fill dirt within the limit of
the drop line of trees to be saved.
5. If a tree marked for preservation is damaged, remove it and replace it with a tree of
the same or similar species, 2-inch caliper or larger, from balled and burlapped
nursery stock when activity in the area is complete.
6. During final site cleanup, remove barriers around trees.
B. Maintenance
1. In the event that damage to protected trees occur, repair any damage to the crown,
trunk, or root system immediately.
a. Repair roots by cutting off the damaged areas and painting them with tree paint.
Spread peat moss or moist topsoil over exposed roots.
b. Repair damage to bark by trimming around the damaged area. Taper the cut to
provide drainage, and paint with tree paint.
c. Cut off all damaged tree limbs above the tree collar at the trunk or main branch.
Use three separate cuts to avoid peeling bark from healthy areas of the tree.
3.09 OUTLET PROTECTION
A. Construction Specifications
1. Ensure that the subgrade for the filter and riprap follows the required lines and
grades shown in the plan. Compact any fill required in the subgrade to the density of
the surrounding undisturbed material. Low areas in the subgrade on undisturbed soil
may also be filled by increasing the riprap thickness.
2. Excavate below channel outlet and widen channel to the required riprap thickness for
each apron. Foundation to be cut to zero grade and smoothed.
3. The riprap and gravel filter must conform to the specified grading limits shown on the
plans.
4. Filter fabric, when used, must meet design requirements and be properly protected
from punching or tearing during installation. Place filter fabric on bottom and sides of
prepared foundation. Repair any damage by removing the riprap and placing another
piece of filter fabric over the damaged area. All connecting joints should overlap a
minimum of 1 foot. If the damage is extensive, replace the entire filter fabric.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 9
5. Riprap may be placed by equipment, but take care to avoid damaging the filter fabric.
6. The minimum thickness of the riprap should be 1.5 times the maximum stone
diameter.
7. Riprap may be field stone or rough quarry stone. It should be hard, angular, highly
weather-resistant, and well graded Class B erosion control stone.
8. Place riprap on zero grade, top of riprap to be level with existing outlet, no overfall at
ends. Set the top of the riprap at the downstream end level with the receiving area or
slightly below it.
9. Ensure that the apron is properly aligned with the receiving stream and preferably
straight throughout its length. If a curve is needed to fit site conditions, place it in the
upper section of the apron.
10. Immediately after construction, stabilize all disturbed areas with vegetation as
specified on the seeding schedule in the Drawings.
B. Maintenance
1. Inspect riprap outlet structures weekly and after heavy rains to see if any erosion
around or below the riprap has taken place or if stones have been dislodged.
Immediately make all needed repairs to prevent further damage.
3.10 TEMPORARY SEDIMENT TRAP
A. Construction Specifications
1. Clear, grub, and strip the area under the embankment of all vegetation and root mat.
Remove all surface soil containing high amounts of organic matter and stockpile or
dispose of it properly. Haul all objectionable material to the designated disposal
area.
2. Ensure that fill material for the embankment is free of roots, woody vegetation,
organic matter, and other objectionable material. Place the fill in lifts not to exceed 9
inches and machine compact it. Overfill the embankment 6 inches to allow for
settlement. Fill shall be Class C2. The existing grade shall be scarified to a depth of
at least 24 inches and recompacted to at least 95 percent of the Standard Proctor
(ASTM D698) maximum dry density. Fill material shall be placed in loose layers not
to exceed 9 inches in thickness. At optimum moisture content ± 2 percent, the fill
shall be compacted to 95 percent Standard Proctor (ASTM D698) maximum dry
density.
3. Construct the outlet section in the embankment. Protect the connection between the
riprap and the soil from piping by using filter fabric or a keyway cutoff trench between
the riprap structure and the soil.
a. Place the filter fabric between the riprap and soil. Extend the fabric across the
spillway foundation and sides to the top of the dam; or
b. Excavate a keyway trench along the centerline of the spillway foundation
extending up the sides to the height of the dam. The trench should be at least 2
feet deep and 2 feet wide with 1:1 slopes.
4. Clear the pond area below the elevation of the crest of the spillway to facilitate
sediment cleanout.
5. All cut and fill slopes should be 2:1 or flatter.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 10
6. Ensure that the stone (drainage) section of the embankment has a minimum bottom
width of 3 feet and maximum side slopes of 1:1 that extend to the bottom of the
spillway section.
7. Construct the minimum finished stone spillway bottom width, as shown on the plans,
with 2:1 side slopes extending to the top of the over filled embankment. Keep the
thickness of the sides of the spillway outlet structure at a minimum of 21 inches.
The weir must be level and constructed to grade to assure design capacity.
8. Material used in the stone section should be a well-graded mixture of stone with a
d50 size of 9 inches (Class B erosion control stone is recommended) and a maximum
stone size of 14 inches. The stone may be machine placed and the smaller stones
worked into the voids of the larger stones. The stone should be hard, angular, and
highly weather-resistant.
9. Ensure that the stone spillway outlet section extends downstream past the toe of the
embankment until stable conditions are reached and outlet velocity is acceptable for
the receiving stream. Keep the edges of the stone outlet section flush with the
surrounding ground and shape the center to confine the outflow stream.
10. Direct emergency bypass to natural, stable areas. Locate bypass outlets so that flow
will not damage the embankment.
11. Stabilize the embankment and all disturbed areas above the sediment pool and
downstream from the trap immediately after construction.
12. Show the distance from the top of the spillway to the sediment cleanout level (one-
half the design depth) on the plans and mark it in the field.
B. Maintenance
1. Inspect temporary sediment traps weekly and after each period of significant rainfall.
Remove sediment and restore the trap to its original dimensions when the sediment
has accumulated to one-half the design depth of the trap. Place the sediment that is
removed in the designated disposal area or incorporated into site grading.
2. Check the structure for damage from erosion or piping. Periodically check the depth
of the spillway to ensure it is a minimum of 1.5 feet below the low point of the
embankment. Immediately fill any settlement of the embankment to slightly above
design grade. Any riprap displaced from the spillway must be replaced immediately.
3. After all sediment-producing areas have been permanently stabilized, remove the
structure and all unstable sediment. Smooth the area to blend with the adjoining
areas and stabilize properly.
3.11 STREAM PROTECTION
A. A temporary ford or structure shall be installed across streams and water courses for
short-term use by construction vehicles and heavy equipment to provide a means to
cross streams and water courses without moving sediment into streams, damaging
stream bed or channel or causing flooding.
B. Land disturbing activity in connection with construction of pipelines in, on, over or under
a natural water course shall minimize the extent and duration of disruption of the stream
channel.
Lake Keowee to Adkins WTP Raw Water System Erosion, Sedimentation, and Dust Control
154828 31 25 00 - 11
3.12 PROVISIONS FOR EROSION CONTROL DURING CONSTRUCTION
A. The Contractor shall inspect all erosion and sedimentation control measures at least
once a week and within 24 hours after any storm event of greater than one-half inch of
rain per 24-hour period or more frequently if required by state or federal law. The person
performing this monitoring shall have certification approved by the Owner. The
Contractor shall maintain inspection and maintenance records in compliance with the
Owner’s erosion and sediment control policies and procedures. Copies of all inspection
and maintenance records will be transmitted to the Owner for filing on a weekly basis.
B. The Contractor shall implement erosion control measures around all areas to be
disturbed prior to disturbing ground in the area, to the satisfaction of the Engineer.
C. The Contractor shall take sufficient precautions during construction to eliminate run-off
of polluting substances such as silt, clay, wastes, fuels, oils, and bitumen into water
supplies and surface waters. Special precautions shall be taken in the use of
construction equipment to conduct operations in a manner that reduces erosion.
D. The temporary drainage ditches, silt fences, and other erosion and sediment control
features shall be maintained at all locations.
E. Disposal of drainage from the site shall be at a location approved by the Engineer.
Drainage shall not be disposed of until silt and other sedimentary materials have been
removed. Particular care shall be taken to prevent the discharge of unsuitable drainage
to a water supply or surface water body.
F. As a minimum, the following shall apply:
1. Approved silt fencing shall be provided at points where drainage from the work site
leaves the site, to reduce the sediment content of the water. Sufficient silt fence
shall be provided such that all flow will filter through the straw or silt fence. Other
methods, which reduce the sediment content to an equal or greater degree, may be
used as approved by the Engineer.
2. Drainage leaving the site shall flow to water courses in a manner that controls
erosion.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Shoring
154828 31 41 00 - 1
SECTION 31 41 00
SHORING
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies requirements for sheeting, shoring, and bracing of trenches
greater than 4 feet in depth.
B. Design Requirements:
1. The Contractor shall design sheeting, shoring, and bracing in accordance with
Article 6 of OSHA and the South Carolina State Labor Code. The standards of design
referred to in the Labor Code shall be those of CAL/OSHA.
2. Horizontal strutting below the barrel of a pipe and the use of pipe as support are not
acceptable.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
OSHA OSHA Excavation Standard – Subpart P
PART 2 PRODUCTS
2.01 GENERAL
A. The Contractor shall submit as product data to the Owner information required by
Subpart P of the OSHA Excavation Standard. Information shall be provided in accordance
with Section 01 33 00 of this project manual.
Lake Keowee to Adkins WTP Raw Water System Shoring
154828 31 41 00 - 2
PART 3 EXECUTION
3.01 GENERAL
A. The construction of sheeting, shoring, and bracing shall not disturb the state of soil
adjacent to the trench and below the excavation bottom.
B. Design sheeting and shoring to be left in place as part of the completed Work, cut off
minimum 18" below finished subgrade, or design sheeting and shoring to be removed at
completion of excavation work.
3.02 SEQUENCE
A. Trench excavation shall not be started until the design for trench support has been
accepted by the Owner.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Asphalt Paving
154828 32 12 16 - 1
SECTION 32 12 16
ASPHALT PAVING
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies paving consisting of aggregate base, asphaltic concrete, and
associated materials.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
ASTM D1557 Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate
Mixtures Using 10-lb (4.5-kg) Rammer and 18-in (457-mm) Drop
B. Testing:
1. Testing will be conducted by the Construction Manager to determine compliance with
the specified degree of compaction and moisture content.
1.03 WEATHER LIMITATIONS
Apply prime and tack coats only when ambient temperature is above 50 degrees F, and when
temperature has not been below 35 degrees F for 12 hours immediately prior to application. Do not
apply during rainy weather or when base is wet or contains an excess of moisture.
Construct asphalt concrete surface course only when atmospheric temperature is above
40 degrees F, and base is dry. Base course may be placed when air temperature is above 30 degrees
F, and is rising.
Weather limitations specified within the South Carolina Department of Transportation Standard
Specifications shall govern when in conflict with the limitations listed above.
Lake Keowee to Adkins WTP Raw Water System Asphalt Paving
154828 32 12 16 - 2
1.04 SUBMITTALS
Submittals shall be made in accordance with Section 01 33 00, not less than 10 days prior to
application of pavement, and include the following data:
A. Certificates signed by the producer stating that the materials supplied comply with these
Specifications.
B. The design mix and test data for each course.
PART 2 PRODUCTS
2.01 MATERIALS
A. Aggregate Base:
1. Shall conform to the requirements of Section 305 of the South Carolina Department
of Transportation Standard Specifications.
B. Liquid Asphalt:
1. Liquid asphalt for tack coats and treatment of aggregate base shall be Grade MC
250 and shall comply with South Carolina Department of Transportation Standard
Specifications.
C. Hot Mix Asphalt Aggregate Base Course:
1. Shall conform to the requirements of Section 310 of the South Carolina Department
of Transportation Standard Specifications.
D. Hot Mix Asphalt Binder Course:
1. Shall conform to the requirements of Section 402, Type B, of the South Carolina
Department of Transportation Standard Specifications.
E. Hot Mix Asphalt Surface Course:
1. Shall conform to the requirements of Section 403, Type B or C (per drawings), of the
South Carolina Department of Transportation Standard Specifications.
F. Other Surfaces:
1. When roadways or private driveways of non-specified materials (brick, stone, etc.) are
damaged during construction, they shall be repaired, to the extent at which they were
damaged, with similar or original materials.
PART 3 EXECUTION
3.01 GENERAL
A. Construction shall conform to the details, dimensions and grades specified. Maximum
variations in finished grade of paving shall be plus or minus 0.05 feet.
3.02 AGGREGATE BASE PLACEMENT
A. Subgrade:
Lake Keowee to Adkins WTP Raw Water System Asphalt Paving
154828 32 12 16 - 3
1. Areas to be paved shall be graded and compacted in accordance with Section 31 23
00-3.06.
2. Where specified, the subgrade shall be treated with lime utilizing 5 percent
(dry weight) hydrated lime.
B. Aggregate Base:
1. Placing of aggregate base shall comply with South Carolina Department of
Transportation Standard Specifications. Relative compaction shall be a minimum of
95 percent as determined using methods set forth in ASTM D1557.
C. Treated Aggregate Base:
1. Where specified, the aggregate base shall be given a penetration treatment with
liquid asphalt as specified and in conformance with South Carolina Department of
Transportation Standard Specifications.
3.03 ASPHALT CONCRETE PAVEMENT
A. Asphalt Concrete:
1. Placement of asphalt concrete pavement shall comply with South Carolina
Department of Transportation Standard Specifications. Berms shall be shaped and
compacted with an extrusion machine.
B. Tack Coat:
1. tack coat shall be applied to all vertical surfaces of existing pavement; to curbs,
gutters, and construction joints against which asphalt concrete will be placed; to
pavements to be surfaced; and where specified at the approximate rate of
0.05 gallons per square yard. Application shall comply with South Carolina
Department of Transportation Standard Specifications. Immediately prior to placing
asphalt concrete, additional tack coat shall be applied to areas where the tack coat
has been damaged.
2. Immediately prior to construction of asphalt concrete berms, a continuous tack coat
shall be applied to the pavement surface. Application of the tack coat shall not cause
a slip or weakened plane between the two joined surfaces.
C. Traffic Line Painting:
1. Traffic lines shall be painted on pavement surfaces where specified. Surfaces are to
be free of contaminants that may interfere with adhesion. Thinning and coverage
shall be as recommended by the manufacturer, but coverage shall not exceed
400 square feet per gallon. Traffic lines shall be of uniform width with the edges
straight and even. Traffic shall be restricted from the area until the paint has dried.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 1
SECTION 33 05 31
DUCTILE IRON PIPE
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies ductile iron pipe, ductile fittings and gaskets.
2. All ductile iron pipe shall be domestically manufactured in the United States. Pipe
shall be cast, cleaned, lined, fabricated, tested, and certified at a USA manufacturing
facility.
B. Definition:
1. Where cast iron pipe is specified, the term and symbol shall mean ductile iron pipe.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ANSI A21.14 Ductile-Iron Fittings 3 In. Through 24 In., for Gas
ANSI A21.52 Ductile-Iron Pipe, Centrifugally Cast, in Metal Molds or Sand Lined Molds for Gas
ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings Class 25, 125, 250, and 800
ANSI B16.5 Pipe Flanges and Flanged Fittings
ASTM A716 Ductile-Iron Culvert Pipe
ASTM C150 Portland Cement
AWWA C104
(ANSI A21.4)
Cement-Mortar Lining for Ductile- Iron and Gray-Iron Pipe and Fittings for Water
AWWA C110
(ANSI A21.10)
Ductile-Iron and Gray-Iron Fittings, 3 In. Through 48 In., for Water and Other Liquids
AWWA C111
(ANSI A21.11)
Rubber-Gasket Joints for Ductile- Iron and Gray-Iron Pressure Pipe and Fittings
AWWA C115
(ANSI A21.15)
Flanged Ductile-Iron and Gray-Iron Pipe With Threaded Flanges
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 2
Reference Title
AWWA C150
(ANSI A21.50)
Thickness Design of Ductile-Iron Pipe
AWWA C151
(ANSI A21.51)
Ductile-Iron Pipe, Centrifugally Cast, in Metal Molds or Sand-Lined Molds, for Water or
Other Liquids
AWWA C153
(ANSI A21.53)
Ductile-Iron Compact Fittings, 3 In. Through 12 In. for Water and Other Liquids
AWWA C600 Installation of Ductile-Iron Water Mains and Their Appurtenances
AWWA C606 Grooved and Shouldered Type Joints
PART 2 PRODUCTS
2.01 GENERAL
A. Pipe design, materials and manufacture shall comply with the following documents:
Item Document
Thickness design AWWA C150
Manufacturing requirements
• Water or other liquid AWWA C151
Gravity service pipe ASTM A716
Joints
• Rubber gasket AWWA C111
• Threaded flange AWWA C115
Fittings
• Water or other liquid AWWA C110/AWWA C153
Cement mortar lining AWWA C104
2.02 PIPE
A. Ductile Iron Pipe shall conform to AWWA C150/ANSI A21.50, AWWA C151/ANSI
21.51 and ASTM A746.
B. Flanged pipe shall be minimum Class 53. Flanges shall be furnished by the pipe
manufacturer. Sizes will be as shown on the Drawings.
C. Ductile Iron Pipe shall be furnished in nominal lengths of 18 to 20 feet. When on
piers, ductile iron pipe shall be furnished in exact lengths of 20-feet.
D. Pipe sizes will be as shown on the Drawings and shall have a minimum pressure
rating as indicated in the following table:
Pipe Sizes (inches) Pressure Class (psi)
4 - 12 350
14 – 20 250
24 200
30 - 54 150
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 3
2.03 WELDED-ON OUTLETS
A. Welded-on outlets may be used in lieu of the tees shown on the plans. All welded-on
outlets shall be rated for a working pressure of 250 psi and shall have a minimum safety
factor of 2.0; except that 36” welded-on outlets for 54”-64” parent pipe diameters shall
be rated at 200-psi. Welded-on outlets may be provided as a radial (tee) outlet, a
tangential outlet, or a lateral outlet. Parent pipe and branch pipe shall meet hydrostatic
test requirements in accordance with AWWA C151, section 51-9, prior to fabrication.
B. All joints on welded-on branch outlets shall be provided in accordance with the latest
revision of ANSI/AWWA C111/A21.11 and/or ANSI/AWWA C115/A21.15, as applicable.
All outlets shall be fabricated from centrifugally cast ductile iron pipe designed in
accordance with ANSI/AWWA C150/A21.50 and manufactured in accordance with
ANSI/AWWA C151/A21.51.
C. All welds must be produced using 55% nickel iron welding rod or wire. Carbon steel
electrodes will not be acceptable. Both branch and parent outlet pipe shall be class 53.
After fabrication each outlet pipe shall be air tested to 15 psi to ensure weld integrity. A
soap and water solution shall be applied during the testing procedure to inspect the weld
for leakage. Any welds that show air seepage shall be refabricated and retested.
D. The type of pipe end for the branch outlet shall be as specified or indicated on the
drawings. The maximum size and laying length of the welded-on branch outlet shall be
recommended by the pipe manufacturer and acceptable to the Engineer for the field
conditions and connecting pipe or valve. Pipe embedment material and trench backfill
shall be placed and compacted under and around each side of the outlet to hold the pipe
in proper position and alignment during subsequent pipe jointing, embedment, and
backfilling operations.
2.04 HYDROSTATIC TESTING
A. All pipe 4”-24” shall be tested per AWWA standards to 500 psi. All pipe, 30”-inches and
larger, shall be subject to a factory hydrostatic test of at least 500 psi for a period of not
less than 10 seconds after which time the pressure is to be elevated to a peak pressure
that induces a stress in the pipe wall equivalent to 75% of the minimum specified yield of
ductile iron (42,000 psi) as calculated by the following formula:
p = 2fs t
D
Where: p = peak hydrostatic pressure
fs = stress in pipe wall during hydrostatic test, which shall be 0.75 times
the minimum yield strength of the ductile iron in tension, i.e.: 42,000 psi
t = nominal wall thickness, in.
D = outside diameter, in.
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 4
Factory Hydrostatic Test Pressures for Ductile Iron Pipe
(30in and Larger)
Pressure Class 150 200 250 300 350
Pipe Size / Outside
Diamter
“t”
(in)
Test
Press.
(psi.)
“t”
(in)
Test
Press.
(psi.)
“t”
(in)
Test
Press.
(psi.)
“t”
(in)
Test
Press.
(psi.)
“t”
(in)
Test
Press.
(psi.)
30” / 32.00 0.34 669 0.38 748 0.42 827 0.45 886 0.49 965
36” / 38.30 0.38 625 0.42 691 0.47 773 0.51 839 0.56 921
42” / 44.50 0.41 580 0.47 665 0.52 736 0.57 807 0.63 892
48” / 50.80 0.46 570 0.52 645 0.58 719 0.64 794 0.70 868
54” / 57.60 0.51 558 0.58 635 0.65 711 0.72 788 0.79 865
60” / 61.60 0.54 552 0.61 624 0.68 695 0.76 777 0.83 849
64” / 65.70 0.56 537 0.64 614 0.72 691 0.80 767 0.87 835
2.05 GASKETS
A. Unless otherwise specified, gasket material shall be standard styrene butadiene
copolymer (SBR). Gaskets shall, in addition, comply with AWWA C111 for push-on and
mechanical joints and with AWWA C606 for grooved end joints.
2.06 FITTINGS
A. Unless otherwise specified, fittings shall conform to AWWA C110 and AWWA C153. Ends
shall be flanged, restrained mechanical joint, restrained push-on, or grooved to suit the
conditions specified. Long-radius elbows shall be provided where specified.
2.07 JOINTS
A. Unrestrained Joints:
1. Push-On Joints: Unrestrained joints, where specified, shall be the rubber ring
compression, push-on type joint suitable for buried service. Unrestrained joints shall
be the Fastite Joint as manufactured by American Cast Iron Pipe Company, the Tyton
Joint as manufactured by U.S. Pipe, or equal. This joint is not permitted on fittings or
specials, unless otherwise specified. Unless otherwise specified, joints shall have an
allowable deflection up to 5 degrees at specified pressures. Joint assembly and field
cut joints shall be made in strict conformance with AWWA C600 and manufacturer's
recommendations.
2. Mechanical Joints: Where specified, mechanical joints for above or below ground
service shall meet the requirements of ANSI/AWWA A21.10/C110 and ANSI/AWWA
A21.11/C111. Gaskets and bolts and nuts shall comply with paragraphs 2.03 and
2.05 Bolts and Nuts, respectively.
B. Restrained Joints:
1. General: Unless otherwise specified, restrained joints are required for all exposed
and buried piping. Unless otherwise specified, restrained joints shall be flanged or
grooved end for exposed service and restrained push-on for buried service.
2. Push-On Joints: Restrained push-on joints shall be as specified in paragraph 2.05.
3. Restrained joints shall be Amarillo Fast-Grip gasket, Flex-Ring, Field Flex-Ring, Lok-
Ring, Barracuda orange gasket, US Pipe Red Field Lok gaskets, TR Flex, Ebba
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 5
Megalug or equal. Restrained joint gaskets shall be colored, non-black. The color
shall be consistent throughout the entire cross section of the gasket and not be
attained by surface coating; the color shall be inherent within the rubber. Gaskets
shall meet applicable requirements of AWWA/ANSI C111/A21.11 and shall be
ANSI/NSF Standard 61 certified. Restrained gaskets shall be manufactured in the
United States.
4. Restrained joints shall be capable of being deflected after full assembly. Joint
assembly shall be in strict conformance with AWWA C600 and manufacturer's
recommendations. No field cuts of restrained pipe are permitted without prior
approval of the Construction Manager.
5. Flange Assemblies: Unless otherwise specified, flanges shall be ductile iron and shall
be threaded-on flanges conforming to ANSI/AWWA A21.15/C115 or cast-on flanges
conforming to ANSI/AWWA A21.10/C110. Flanges shall be adequate for 250 psi
working pressure. Bolt circle and bolt holes shall match those of ANSI B16.1, Class
125 flanges and ANSI B16.5, Class 150 flanges. Where specified, flanges shall be
threaded-on or cast-on flanges conforming to ANSI B16.1, Class 250.
a. Unless otherwise specified, bolts and nuts for flange assemblies shall conform
with Section 40 05 06.16-2.01 Bolts. Gaskets shall be as specified in Section 40
05 06.16-2.01 Gaskets.
6. Mechanical Joints: Where specified, restrained mechanical joints shall be the positive
restraint type.
a. Locked mechanical hydrant tees, bends and adapters are an acceptable
substitute for anchoring fire hydrants and valves to the pipe main.
C. Ball And Socket Flexible Joint Pipe: Ball and socket flexible joint pipe shall be the boltless
type and shall allow a maximum joint deflection of 15 degrees. Each joint shall be
provided with a retainer lock to prevent rotation after assembly. Joints shall be the Flex-
Lok Joint as manufactured by American Cast Iron Pipe Company, USIflex as
manufactured by U.S. Pipe, or equal.
D. Bolts and Nuts: Corrosion-resistant bolts and nuts for use with ductile iron joints shall be
high-strength, low-alloy steel as specified in ANSI/AWWA C111/A21.11.
2.08 PIPE COATING
A. Unless otherwise specified, pipe and fittings shall be coated with asphaltic material as
specified in AWWA C151.
B. Exposed pipe and fittings shall be coated with Tnemec Series 69 Hi-Build Epoxoline II, or
equal, installed in accordance with manufacturer’s recommended coating procedure.
Exposed pipe and fittings susceptible to direct sunlight shall receive an additional
Tnemec Series 1075, or equal, finish coat installed in accordance with manufacturer’s
recommended coating procedure.
C. Polyethylene Encasement- If required and noted per plans, polyethylene encasement for
use with ductile iron pipe and fittings shall be VBio and meet all the requirements for
ANSI/AWWA C105/A21.5, Polyethylene Encasement for Ductile Iron Pipe Systems.
Polyethylene encasement for use with ductile iron pipe systems shall consist of three
layers of co-extruded linear low-density polyethylene (LLDPE), fused into a single
thickness of not less than eight mils.
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 6
D. The inside surface of the polyethylene wrap to be in contact with the pipe exterior shall
be infused with a blend of anti-microbial biocide to mitigate microbiologically influenced
corrosion and a volatile corrosion inhibitor to control galvanic corrosion. Ductile iron pipe
and the polyethylene encasement used to protect it shall be installed in accordance with
AWWA C600 and ANSI/AWWA C105/A21.5 and in accordance with all recommendations
and practices of the AWWA M41, Manual of Water Supply Practices.
2.09 INTERIOR LINING
A. Cement Mortar Lining: Where specified, interior surfaces of pipe and fittings shall be
cement mortar lined in accordance with AWWA C104. Cement shall be ASTM C150, Type
II or V, low alkali, containing less than 0.60 percent alkalies.
2.10 PRODUCT DATA
A. The following information shall be provided in accordance with Section 01 33 00:
1. Shop drawings.
2. Alignment drawings.
3. Certifications specified in the following documents:
a. ANSI A21.14, paragraph 14-4.2
b. ANSI A21.52, paragraph 52-4.2
c. ASTM A716, paragraph 4.2
d. AWWA C110, paragraph 10-5.3
e. AWWA C111, paragraph 11-7.1
f. AWWA C115, paragraph 15-4.2
g. AWWA C151, paragraph 51-5.2
h. AWWA C153, paragraph 53-6.3
i. AWWA C606, paragraph 4.1.1.1
PART 3 EXECUTION
3.01 INSTALLATION
A. General:
1. Piping runs specified on the drawings shall be followed as closely as possible.
Proposed deviations shall be submitted in accordance with Section 01 33 00.
2. Pipe shall be installed in accordance with AWWA C600.
3. Connections to existing structures and manholes shall be made so that the finished
work will conform as nearly as practicable to the requirements specified for the new
manholes, including necessary concrete work, cutting and shaping. Concrete mortar
shaping within any structure and manhole shall be as specified.
B. Insulating Sections:
1. Where a metallic nonferrous pipe or appurtenance is connected to ferrous pipe or
appurtenance, an insulating section shall be provided as specified in Section 40 05
06.16-3.05.
C. Anchorage:
Lake Keowee to Adkins WTP Raw Water System Ductile Iron Pipe
154828 33 05 31 - 7
1. Anchorage shall be provided as specified. Calculations and drawings for proposed
alternative anchorage shall be submitted in accordance with Section 01 33 00.
3.02 ACCEPTANCE TESTING
A. Hydrostatic pressure tests shall be conducted in accordance with Section 4 of AWWA
C600 except that test pressures and allowable leakage shall be as listed in Section 40
05 01.
B. The Contractor shall conduct the tests in the presence of the Construction Manager.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 1
SECTION 33 05 32
LINED AND COATED STEEL PIPE
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies cement mortar lined and coated steel pipe and fittings.
B. Design Requirements:
1. See 2.01.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
API STD 1104 Welding Pipelines and Related Facilities
ASME Section IX Boiler and Pressure Vessel Code; Welding and Brazing Qualifications
ASTM A36/A36M Structural Steel
ASTM A139 Specification for Electric-Fusion (Arc)-Welded Steel Pipe (NPS 4 and Over)
ASTM A283/A283M Low and Intermediate Tensile Strength Carbon Steel Plates, Shapes, and Bars
ASTM A570/A570M Hot-Rolled Carbon Steel Sheet and Strip, Structural Quality
ASTM E165 Method for Liquid Penetrant Examination
ASTM E709 Guide for Magnetic Particle Examination
ASME Section V Nondestructive Testing Examination
ASME Section VII Rules for Construction of Pressure Vessels – Division 1
ASME Section IX Welding and Brazing Qualifications
AWS D1.1 Structural Welding Code – Steel
AWWA C200 Steel Water Pipe 6 Inches and Larger
AWWA C205 Cement-Mortar Protective Lining and Coating for Steel Water Pipe--4 in. and
Larger--Shop Applied
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 2
Reference Title
AWWA C206 Field Welding of Steel Water Pipe
AWWA C207 Steel Pipe Flanges for Waterworks Service--Sizes 4 in. through 144 in.
AWWA C208 Dimensions for Steel Water Pipe Fittings
AWWA C210 Liquid-Epoxy Coatings and Linings for Steel Water Pipe and Fittings
AWWA C222 Polyethylene Coating and Linings for Steel Water Pipe and Fittings
AWWA C604 Installation of Buried Steel Water Pipe – 4 in. (100 mm) and Larger
AWWA C651 Disinfecting Water Mains
AWWA M11 Steel Pipe--A Guide for Design and Installation
B. Testing:
1. Factory testing shall conform to the requirements of AWWA C200, except that at the
manufacturer's option, fittings and specials not made from hydrotested cylinders may
be checked by the dye-penetrant method or magnetic particle or ultrasonic testing.
PART 2 PRODUCTS
2.01 PIPE MATERIALS
A. Steel shall conform to the requirements of ASTM A570, Grade 30 or 33, or ASTM A283,
Grade C or D, ASTM A139, Grade C, D, or E, with a maximum carbon content of 0.25%,
or ASTM A36.
B. Steel shall be of domestic orgin.
C. Unless otherwise shown on the drawings, the minimum steel cylinder thickness shall be
not less than the diameter divided by 240. The diameter specified for pipe and fittings
shall be the nominal inside diameter after lining.
D. Pipe shall be designed for 150 psi working pressure with an additional 100 psi allowance
for transient. Pipe design shall be in accordance with AWWA M11. Design stress shall be
limited to 50% of the minimum yield strength at working pressure and 75% at the greater
of working pressure plus transient allowance, or test pressure.
E. Pipe shall be designed for the cover conditions as shown on the plans. The design shall
be in accordance with AWWA M11. Modulus of soil reaction (E’) values to be used for
design shall be taken from the following table:
Depth of Cover E’
2 to 10 feet 1000 psi
10 to 15 feet 1200 psi
15 to 20 feet 1300 psi
F. The allowable design deflection shall be 3% of the pipe nominal inside diameter.
2.02 PIPE MANUFACTURE
A. Pipe shall be straight or spiral seam in accordance with AWWA C200.
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 3
B. Complete pipe manufacturing shall be performed at a single pipe producing facility.
Partial production at one facility and the completion at another will not be acceptable.
C. Pipe shall be designed for the cover conditions as shown on the plans. The design shall
be in accordance with AWWA M11.
D. Pipe is to be furnished principally in 40 to 50 ft. nominal laying lengths with special
lengths, field trim pieces and closure pieces as required by plan and profile for location
of elbows, tees, reducers, other in-line fittings, and closures.
E.
2.03 JOINTS
A. Joints shall conform to the requirements set forth under AWWA C200. Welded joints shall
be lap welded in accordance with AWWA C206. Flanges where specified shall be steel
plate flanges conforming to AWWA C207.
2.04 FITTINGS AND APPURTENANCES
A. Fittings and appurtenances shall conform to AWWA C208 and shall be designed in
accordance with AWWA M11, except that ends of the fittings may be longer.
B. Pipe material used in fittings shall be of an equivalent material and the same minimum
thickness as the pipe. The minimum radius of elbows shall be 2.5 times the pipe outside
diameter and the maximum miter angle on each section of an elbow shall not exceed 11
1/4 degrees. If an elbow radius is less than 2.5 x pipe diameter, stresses shall be
checked per AWWA M11 and wall thickness or yield strength increased, as necessary.
C. Fittings shall be equal in pressure design strength and shall have lining and coating as
specified for the pipe to which it connects. Fabricate specials and fittings from
hydrostatically tested pipe, wherever practical. All butt and fillet welds made after
hydrostatic testing of straight pipe shall be magnetic particle examined in accordance
with ASTM E709. Acceptance criteria shall be in accordance with ASME Code, Section
VIII, Division 1, Appendix 6.
2.05 PIPE LINING AND COATING
A. Unless specified otherwise, pipe lining and coating shall be cement mortar in
conformance with AWWA C205. Fittings and specials larger than 24 inches, not
fabricated from centrifugally lined straight sections, shall require 2 x 4 x 13 gage self-
furring wire mesh reinforcement for hand applied lining.
B. Straight pipe shall be coated with polyurethane, 25 mils minimum DFT, conforming to
ANSI/AWWA C222. Fittings and special sections, the pipe shall receive one of the
following protective coatings:
1. Liquid epoxy, 16 mils minimum DFT, conforming to ANSI/AWWA C210.
2. Polyurethane, 25 mils minimum DFT, conforming to ANSI/AWWA C222.
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 4
2.06 JOINTS
A. The joint shall be a field-welded lap joint conforming to the requirements of ANSI/AWWA
C200, welded on either the inside or outside in accordance with the requirements of
ANSI/AWWA C206. The standard bell shall provide for a minimum lap of 1-inch or three
times the thickness of the belled pipe, whichever is greater, and other dimensional
requirements of ANSI/AWWA C200 and ANSI/AWWA C206. The design maximum
deflection shall be 1-inch.
B. Mechanical Couplings:
1. Mechanical couplings shall be sleeve type couplings conforming to ANSI/AWWA
C219, or split-sleeve-type couplings conforming to AWWA C227.
2. Where restrained joints are required, ANSI/AWWA C219 mechanical couplings shall
be harnessed for the maximum pressure (test pressure or transient pressure) in
accordance with AWWA M11.
3. Pipe ends for mechanical couplings shall conform to ANSI/AWWA C200 and
ANSI/AWWA C219 or ANSI/AWWA C227, as applicable. Harness lugs or rings and
pipe ends shall be coated with epoxy conforming to ANSI/AWWA C210. The inside
lining shall be continuous to the end of the pipe.
C. Where indicated, joints shall be full penetration butt-weld to maintain consistent a
outside diameter.
D. Flanges
1. Flanges shall be in accordance with ANSI/AWWA C207, Class D, E or F.
2. Shop lining shall be continuous to the end of the pipe. Shop coating shall be
continuous to the base of the back of the attached flange. Flange face, back and
edge shall be shop coated with a soluble rust preventive compound.
E. Flanges, bolts, nuts, and gaskets shall be in accordance with ANSI/AWWA C207. Bolts
shall extend a minimum of three threads past the nut.
2.07 PRODUCT DATA
A. The following information shall be provided in accordance with Section 01 33 00:
1. An Affidavit of Compliance with AWWA C200.
2. Layout schedule.
PART 3 EXECUTION
3.01 PIPE LAYING
A. General:
1. Pipe shall be provided in accordance with AWWA M11. Welded joints shall be in
accordance with AWWA C206.
2. Sleeve-type mechanical pipe couplings shall be provided in accordance with AWWA
M11 and Section 40 05 06.16 of this project manual.
3. Mechanical joints shall be provided and assembled in accordance with the
manufacturer's instructions.
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 5
4. The contractor shall install all required piping and accessories in accordance with
ANSI/AWWA C604, and shall handle, store and assemble pipe in accordance with the
manufacturer’s recommendations. Pipe installation as specified in this section
supplements AWWA M11.
B. Rubber Gasket Joints (NOT USED)
C. Lap field welded joints
1. Wire brush exposed surfaces of pipe ends. The plain end shall extend into the
expanded bell to provide the minimum overlap stated above at any location around
the joint circumference. Prior to welding, the joint gap shall be fit around the full
circumference until it is in accordance with the requirements of ANSI/AWWA C206,
and tacked in place.
2. Certified welders shall provide a single full fillet weld (thickness of the thinnest
member plus any gap) on the inside or outside surface of the joint.The exterior
surface of the joint shall be protected by applying one or more layers of heat-shrink
material in accordance with heat-shrink sleeve manufacturer’s recommendations
and ANSI/AWWA C216. Weld After Backfill (WAB) is an acceptable method of pipe
installation. The joint must be fully coated and the pipe must be completely
backfilled to at least 12” over the top of the pipe prior to welding on the inside.
3. The interior joint space shall be mortared in accordance with ANSI/AWWA C205.
D. Sleeve and Mechanical Joints:
1. Sleeve and mechanical joints when buried shall be concrete encased.
E. Flanged joints:
1. Bolt holes of flanges shall straddle the field top centerline of the pipe.
2. Assemble flanged joints in accordance with ANSI/AWWA C604.
3. Execute care when tightening joints to prevent undue strain upon valves, pumps and
other equipment.
4. If flanges leak under pressure testing, loosen or remove the nuts and bolts, reset or
replace the gasket, reinstall or re tighten the bolts and nuts, and retest the joints.
Joints shall be watertight.
3.02 BURIED PIPING
A. Inspect each pipe and fitting before lowering it into the trench. Inspect the lining and
coating. Patch damaged areas in the field with material similar to the original.
B. Clean ends of pipe thoroughly. Remove foreign matter and dirt from inside of pipe and
keep clean during and after laying.
C. Handle pipe in a manner to avoid any damage to the pipe. Do not drop or roll pipe into
trenches under any circumstances.
D. Grade the bottom of the trench and place a 4-inch minimum layer of select or scarified
material under the pipe. Before laying each section of pipe, check the grade and correct
any irregularities found. The trench bottom shall form a uniform bearing and support for
the pipe.
Lake Keowee to Adkins WTP Raw Water System Lined and Coated Steel Pipe
154828 33 05 32 - 6
E. At the location of each joint, dig a bell (joint) hole in the bottom of the trench and at the
sides to permit assembly, coating and visual inspection of the entire joint.
F. Keep the trench in a dewatered condition during pipe laying and application of joint
coating.
G. Close the ends of the pipe when the pipe laying is not in progress. Do not permit trench
water, animals, or foreign objects to enter the pipe.
H. The pipe shall be embedded in a compacted soil envelope that will yield the values
required in section 2.01.E
3.03 EXPOSED PIPING
A. All piping and fittings shall be installed true to alignment and rigidly supported thrust
anchors shall be provided where required. Any damage to the linings shall be repaired to
the satisfaction of the engineer before the pipe is installed.
B. Each length of pipe shall be cleaned out before installation.
C. Sleeves shall be installed for all pipes passing through floors or walls as shown on the
drawings.
D. Concrete inserts for hangers and supports shall be furnished and installed in the
concrete as it is placed. The inserts shall be in accordance with the requirements of the
piping layout and joining method and their location shall be verified from approved piping
layout drawings and structural drawings.
E. Except as otherwise shown on the drawings, either lap welded, butt welded, sleeve type
coupling or flange joints may be used. Prior to approval of joining method, layouts for
hangers and supports shall be submitted to the engineer for approval.
F. Flanged joints shall be made with bolts with one nut each, studs with a nut on each end,
or studs with one nut each where the flange is tapped.
G. The exterior surface of the pipe and fittings shall receive a prime coat of paint consistent
with any required final coat. The steel surface shall be prepared in accordance with the
paint manufacturer’s requirements.
3.04 TESTING
A. Hydrostatic testing shall be conducted in accordance with Section 4 of AWWA C604 and
a test pressure of 150 psi. Unless otherwise specified, allowable leakage shall be as
specified in Section 40 05 01.
END OF SECTION
DIVISION 40
PROCESS INTEGRATION
Section Title
40 05 01 PIPING SYSTEMS
40 05 06.16 PIPING CONNECTIONS
40 05 07 HANGERS AND SUPPORTS FOR PROCESS PIPING
40 05 57.13 MANUAL ACTUATORS
40 05 64 BUTTERFLY VALVES
40 05 78.23 AIR VACUUM VALVES FOR PROCESS SERVICE
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 1
SECTION 40 05 01
PIPING SYSTEMS
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies systems of process piping and general requirements for piping
systems. Detailed specifications for the components listed on the Piping System
Specification Sheets are found in other sections of Division 40. This section shall be
used in conjunction with those sections.
B. Definitions:
1. Pressure terms used in Section 40 05 01 and elsewhere in Division 40 are defined
as follows:
a. Maximum: The greatest continuous pressure at which the piping system
operates.
b. Test: The hydrostatic pressure used to determine system acceptance.
1.02 QUALITY ASSURANCE
A. References:
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
AASHTO M36/M36M Metallic (Zinc or Aluminum) Coated Corrugated Steel Culverts and Under-
drains
ANSI A13.1 Scheme for the Identification of Piping Systems
ANSI B1.20.1 Pipe Threads, General Purpose (Inch)
ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings Class 25, 125, 250, and 800
ANSI B16.3 Malleable Iron Threaded Fittings Class 150 and 300
ANSI B16.5 Pipe Flanges and Flanged Fittings
ANSI B16.9 Factory-Made Wrought Steel Buttwelding Fittings
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 2
Reference Title
ANSI B16.11 Forged Steel Fittings, Socket Welding and Threaded
ANSI B16.12 Cast Iron Threaded Drainage Fittings
ANSI B16.22 Wrought Copper and Copper Alloy Solder Joint Pressure Fittings
ANSI B16.26 Cast Copper Alloy Fittings for Flared Copper Tubes
ANSI B31.1 Power Piping
ANSI B31.3 Chemical Plant and Petroleum Refinery Piping
ASME Section IX Boiler and Pressure Vessel Code; Welding and Brazing Qualifications
ASTM A47 Malleable Iron Castings
ASTM A53 Pipe, Steel, Black and Hot Dipped, Zinc-Coated Welded and Seamless
ASTM A74 Cast Iron Soil Pipe and Fittings
ASTM A105/A105M Forgings, Carbon Steel, for Piping Components
ASTM A106 Seamless Carbon Steel Pipe for High-Temperature Service
ASTM A126 Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe
Fittings
ASTM A197 Cupola Malleable Iron
ASTM A234/A234M Pipe Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and
Elevated Temperatures
ASTM A312/A312M Seamless and Welded Austenitic Stainless Steel Pipe
ASTM A403/A403M Wrought Austenitic Stainless Steel Piping Fittings
ASTM A536 Ductile Iron Castings
ASTM A570/A570M Hot-Rolled Carbon Steel Sheet and Strip, Structural Quality
ASTM B88 Seamless Copper Water Tube
ASTM C76 Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe
ASTM C296 Asbestos-Cement Pressure Pipe
ASTM C443-REV A Standard Specification for Joints for Circular Concrete Sewer and Culvert
Pipe, Using Rubber Gaskets
ASTM C564 Rubber Gaskets for Cast Iron Soil Pipe and Fittings
ASTM D1248 Polyethylene Plastics Molding and Extrusion Materials
ASTM D1784 Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl
Chloride) (CPVC) Compounds
ASTM D1785 Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120
ASTM D2241 Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR)
ASTM D2513 Thermoplastic Gas Pressure Pipe, Tubing, and Fittings
ASTM D2665 Poly (Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings
ASTM D2996 Filament-Wound Reinforced Thermosetting Resin Pipe
ASTM D3034 Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe
and Fittings
ASTM D3261 Butt Fusion Polyethylene (PE) Plastic Fittings for Polyethylene (PE) Plastic
Pipe and Tubing
ASTM D4174 Cleaning, Flushing, and Purification of Petroleum Fluid Hydraulic Systems
ASTM D4101 Propylene Plastic Injection and Extrusion Materials
ASTM F441 Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80
AWWA C105 Polyethylene Encasement for Ductile-Iron Piping for Water and Other Liquids
AWWA C110 Ductile-Iron and Gray-Iron Fittings, 3 Inch Through 48 Inch, for Water and
Other Liquids
AWWA C111 Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and
Fittings
AWWA C115 Flanged Ductile-Iron and Gray-Iron Pipe with Threaded Flanges
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 3
Reference Title
AWWA C151 Ductile-Iron Pipe, Centrifugally Cast in Metal Molds or Sand-Lined Molds, for
Water or Other Liquids
AWWA C200 Steel Water Pipe 6 Inches and Larger
AWWA C205 Cement-Mortar Protective Lining and Coating for Steel Water Pipe--4 In. and
Larger--Shop Applied
AWWA C206 Field Welding of Steel Water Pipe
AWWA C207 Steel Pipe Flanges for Waterworks Services--Sizes 4 In. through 144 In.
AWWA C208 Dimensions for Fabricated Steel Water Pipe Fittings
AWWA C209 Cold-Applied Tape Coating for Special Sections, Connections, and Fittings
for Steel Water Pipelines
AWWA C210 Liquid Epoxy Coating Systems for the Interior and Exterior of Steel Water
Pipe
AWWA C214 Tape Coating Systems for the Exterior of Steel Water Pipelines
AWWA C301 Prestressed Concrete Pressure Pipe, Steel Cylinder Type, for Water and
Other Liquids
AWWA C303 Reinforced Concrete Pressure Pipe--Steel Cylinder Type, Pretensioned, for
Water and Other Liquids
AWWA C600 Installation of Ductile-Iron Water Mains and Their Appurtenances
AWWA C651 Disinfecting Water Mains
AWWA C900 Polyvinyl Chloride (PVC) Pressure Pipe, 4 Inches Through 12 Inches, for
Water
AWWA M11 Steel Pipe--A Guide for Design and Installation
CISPI 301 Specification Data for Hubless Cast Iron Sanitary System with No-Hub Pipe
and Fittings
FEDSPEC L-C-530B(1) Coating, Pipe, Thermoplastic Resin or Thermosetting Epoxy
MIL-H-13528B Hydrochloric Acid, Inhibited, Rust Removing
MIL-STD-810C Environmental Test Methods
SAE J1227 Assessing Cleanliness of Hydraulic Fluid Power Components and Systems
UPC Uniform Plumbing Code
B. Fittings and Coupling Compatibility:
1. To assure uniformity and compatibility of piping components, fittings and couplings
for grooved end piping systems shall be furnished by the same manufacturers.
PART 2 PRODUCTS
2.01 PIPING MATERIALS
A. Unless otherwise specified, piping materials, including pipe, gaskets, fittings, connection
and joint assemblies, linings and coatings, shall be selected from those listed on the
piping system specification sheets. Piping materials shall conform to detailed
specifications for each type of pipe and piping appurtenance specified in other sections
of Division 40.
2.02 PIPING IDENTIFICATION
A. Plastic Tracer Tape:
1. Tracer tape shall be 6 inches wide, colored the same as the background colors as
specified in Table A, paragraph 3.06, and made of inert plastic material suitable for
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 4
direct burial. Tape shall be capable of stretching to twice its original length and shall
be as manufactured by Allen Systems, W. H. Brady Co., Seton Name Plate
Corporation, Marking Services Inc., or equal.
2. Two messages shall be printed on the tape. The first message shall read "CAUTION
CAUTION CAUTION PIPE BURIED BELOW" with bold letters approximately 2 inches
high. The blank shall be filled with the particular system fluid such as water.
2.03 VALVES
A. Valves of the same size and service shall be provided by a single valve manufacturer.
Packing shall be non-asbestos material. Actual length of valves shall be within 1/16 inch
(plus or minus) of the manufacturer's specified length. Flanges shall meet the
requirement of ANSI B16.5. Push-on and mechanical joints shall meet the requirements
of AWWA C111. Valve operators are specified in Sections 40 05 57.13.
2.04 PRODUCT DATA
A. Product data on piping materials shall be provided in accordance with Section 01 33 00
where specified.
B. Piping layout drawings shall be transmitted to the Construction Manager a minimum of 2
weeks prior to construction. Drawings shall be original layouts by the Contractor;
photocopies of contract drawings are not acceptable.
PART 3 EXECUTION
3.01 INSTALLATION
A. Location:
1. Piping shall be provided as specified except for adjustments to avoid architectural
and structural features and shall be coordinated with electrical construction.
B. Piping Sizes:
1. Where the size of piping is not specified, the Contractor shall provide piping of the
sizes required by UPC. Unless specified otherwise, small piping (less than 1 inch in
diameter) required for services not described by UPC shall be 1/2 inch.
C. Pipe Support, Anchorage and Seismic Bracing:
1. General: Piping shall be supported by anchor brackets, guides, saddles or hangers.
Acceptable types of supports, guides, saddles, hangers and structure attachments
for general pipe support, expansion/ contraction and for seismic bracing, as well as
anchorage details, are shown on the drawings. Minimum spacing shall be as
specified for supports and for seismic bracing. Where a specific type of support or
anchorage is indicated on the drawings, then only that type shall be used there.
Piping shall be vertically supported by anchor brackets, guides, saddles or hangers
and shall be seismically braced where indicated to resist lateral load. Supports shall
be provided on each run at each change of direction. Pipe supports shall be hot-dip
or mechanically galvanized. Unless otherwise specified, existing pipes and supports
shall not be used to support new piping.
2. Piping Connections to Machines: Piping at machine connections shall be aligned in
all planes to permit insertion of bolts at bolted connections or coupling screwed
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 5
connections without using jacks, come-a-longs or other mechanical means to align
field piping with the connections at the machines. Bolts shall not be forced into
mating flange bolt holes and shall be capable being withdrawn using finger pressure
alone. The use of ‘dutchmen’ mitered sections or similar specials to achieve the
required alignment with machine connections is strictly prohibited.
D. Anchorage for Buried Piping:
1. All plugs, caps, tees and bends in buried pressure piping systems shall be anchored
by means of reaction backing or restrained joints as specified.
E. Bedding and Backfill:
1. Bedding and backfill for buried piping shall be as specified.
F. Equipment Connection Fittings
1. Where shown, equipment connection fittings as specified in Section 40 05 06.16
shall be provided between field piping systems and equipment inlet and outlet
connections.
G. Flexibility
1. Unless otherwise specified, piping passing from concrete to earth shall be provided
with two pipe couplings or flexible joints as specified in Section 40 05 06.16.
3.02 PIPING IDENTIFICATION
A. Plastic Tracer Tape:
1. A single line of tape as specified in paragraph 2.02 Plastic Tracer Tape shall be
provided 2.5 feet above the centerline of buried PVC pipe. For PVC pipelines buried 8
feet or greater below finished grade, contractor shall provide a second line of tape 12
inches below finished grade, above and parallel to each buried pipe. Tape shall be
spread flat with message side up before backfilling.
3.03 VALVE IDENTIFICATION
A. Stainless steel tags bearing the specified valve number stamped in 1/4-inch high letters
shall be installed on valve flanges in a position visible from floor level. Flangeless valves
8 inches in diameter and larger shall have tags attached to the valve body by self-tapping
corrosion resistant metal screws. Flangeless valves 6 inches in diameter and smaller
shall have tags attached to the valve stem by stainless steel wire. Wire shall be 0.063
inch minimum.
3.04 TESTING
A. General:
1. Upon completion of piping, but prior to application of insulation on exposed piping,
the Contractor shall test the piping systems. Pressures, media and test durations
shall be as specified in the PIPESPEC. Equipment which may be damaged by the
specified test conditions shall be isolated. Testing shall be performed using
calibrated test gages and calibrated volumetric measuring equipment to determine
leakage rates. Each test gage shall be selected so that the specified test pressure
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 6
falls within the upper half of the gage's range. Unless otherwise specified, the
Contractor shall notify the Construction Manager 24 hours prior to each test.
2. Unless otherwise specified, testing, as specified herein, shall include existing piping
systems which connect with new pipe systems. Existing pipe shall be tested to the
nearest existing valve. Any piping which fails the test shall be repaired. Repair of
existing piping will be considered and paid for as extra work.
B. Liquid Systems:
1. Leakage shall be zero at the specified test pressure throughout the specified
duration for the following systems: exposed piping, buried insulated piping, and
buried or exposed piping carrying liquid. Unless otherwise specified, leakage from
other buried liquid piping systems shall be less than 0.02 gallon per hour per inch
diameter per 100 feet of buried piping.
C. Drains:
1. Drain systems, other than pumped drain systems, shall be tested in accordance with
UPC.
3.05 CLEANING AND FLUSHING
A. General:
1. Piping systems shall be cleaned following completion of testing and prior to
connection to operating, control, regulating or instrumentation equipment. The
Contractor may, at his option, clean and test sections of buried or exposed piping
systems. Use of this procedure, however, will not waive the requirement for a full
pressure test of the completed system. Unless specified otherwise, piping 24 inches
in diameter and smaller shall first be cleaned by pulling a tightly fitting cleaning ball
or swab through the system. Piping larger than 24 inches in diameter may be
cleaned manually or with a cleaning ball or swab.
B. Temporary Screens:
1. Upon completion of the cleaning, the Contractor shall connect the piping systems to
related process equipment. Temporary screens, provided with locator tabs which
remain visible from the outside when the screens are in place, shall be inserted in
pipelines at the suction of pumps and compressors in accordance with the following
table:
Equipment Suction or Piping Size, Inches Maximum Screen Opening, Inches
0 –1 1/16
1-1/4 – 3 1/4
3-1/2 – 6 1/2
Over 6 1
2. The Contractor shall maintain the screens during testing, initial start-up, and initial
operating phases of the commissioning process. In special cases, screens may be
removed as required for performance tests. The Contractor shall remove the
temporary screens and make the final piping connections after the screens have
remained clean for at least 24 consecutive hours of operation. Systems handling
solids are exempted.
Lake Keowee to Adkins WTP Raw Water System Piping Systems
154828 40 05 01 - 7
C. Liquid Systems:
1. After completion of cleaning, liquid systems, unless otherwise specified, shall be
flushed with clean water. With temporary screens in place, the liquid shall be
circulated through the piping system using connected equipment for a minimum
period of 15 minutes and until no debris is collected on the screens.
D. Potable Water Systems:
1. Potable water piping systems shall be flushed and disinfected in accordance with
AWWA C651.
3.06 PIPING SPECIFICATION SHEETS (PIPESPEC)
A. Piping and valves for groupings of similar plant processes or types of service lines are
specified on individual piping specification sheets (PIPESPECS). Piping services are
grouped according to the chemical and physical properties of the fluid conveyed and/or
by the temperature or pressure requirements. Each grouping of services (PIPESPEC) is
identified by a piping system number. Piping services specified in the PIPESPECS and on
the drawings are alphabetically arranged by designated service symbols as shown in
Table A. Table A also indicates the system number, fluid category, and pipe marker
background color of each service.
B. Ductile Iron Pipe – see Section 33 05 31.
C. Lined and Coated Steel Pipe – see Section 33 05 32
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 1
SECTION 40 05 06.16
PIPING CONNECTIONS
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies the following methods of connecting metallic piping: flanges,
threading, mechanical couplings, equipment connection fittings, dielectric unions, and
welding.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ANSI Bl.1 Unified Inch Screw Threads (UN and UNR Thread Form)
ANSI Bl.20.1 Pipe Threads, General Purpose (Inch)
ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings
ANSI B16.5 Pipe Flanges and Flanged Fittings
ANSI B18.2.1 Square and Hex Bolts and Screws Inch Series
ANSI B18.2.2 Square and Hex Nuts (Inch Series)
ANSI B31.1 Power Piping
ANSI B31.3 Chemical Plant and Petroleum Refinery Piping
ASME Section IX Boiler and Pressure Vessel Code; Welding and Brazing Procedures,
Welders, Brazers, and Welding and Brazing Operators Qualifications
ASTM B98 Copper-Silicon Alloy Rod, Bar and Shapes
ASTM F37 Standard Test Methods for Sealability of Gasket Materials
ASTM F104 Standard Classification System for Nonmetallic Gasket Materials
ASTM F152 Standard Test Methods for Tension Testing of Nonmetallic Gasket
Materials
ASTM F593
Stainless Steel Bolts, Hex Cap Screws, and Studs
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 2
Reference Title
AWWA C111
Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings
AWWA C206
Field Welding of Steel Water Pipe
AWWA C207 Steel Pipe Flanges for Waterworks Service-Size 4 in. through 144 in.
AWWA C219 Bolted, Sleeve-Type Couplings for Plain-End Pipe
AWWA C550 Protective Epoxy Coatings for Valves and Hydrants
AWWA C606 Grooved and Shouldered Joints
AWWA M11 Steel Pipe-A Guide for Design and Installation
NSF 61 Drinking Water System Components - Health Effects
1.03 SUBMITTALS
A. In addition to the material listed in the detailed specification, the following submittals
shall be provided in accordance with Section 01 33 00:
1. For Equipment Connection Fittings used in pumping applications submit thrust rod
stretch calculations in accordance with paragraph 2.02 Equipment Connection
Fittings. and dimensional layout data.
PART 2 PRODUCTS
2.01 FLANGE ASSEMBLIES
A. Flanges:
1. General: Flanges shall either be flat flanges or convoluted ring flanges as specified in
the following paragraphs.
2. Flat Flanges: Cast iron flanges shall be faced in accordance with ANSI B16.1. Where
companion flanges are used, the flanges on pipe shall be refaced to be flush with the
companion flange face. Class 150 and Class 300 forged steel flanges shall be raised
face conforming to ANSI B16.5. Lightweight slip-on flanges shall be plain face
conforming to AWWA C207, Class B and ANSI B16.5. Unless otherwise specified,
steel flanges shall be ANSI B16.5, Class 150 or AWWA C207, Class D. Class E AWWA
flanges shall be provided where test pressure exceeds 175 psi. Plain faced flanges
shall not be bolted to raised face flanges.
3. Convoluted Ring Flanges: Convoluted ring flanges shall be ductile iron, forged steel or
cast stainless steel, designed to bear on hubs welded to the pipe and shall be as
manufactured by Improved Piping Products. The Construction Manager knows of no
equal. The flange joints shall be rated for not less than 150 percent of the test
pressures listed in Section 40 05 01 and shall conform to the requirements of ANSI
B 16.5 and AWWA C207. The flange manufacturer shall be prepared to demonstrate,
by certified pressure test that the flanges will meet these requirements.
B. Gaskets:
1. Gasket material shall be as specified in paragraph 2.03.
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 3
2. Gaskets for plain faced flanges shall be the full face type. Thickness shall be 1/16
inch for pipe 10 inches and less in diameter and 1/8 inch for pipe 12 inches and
larger in diameter. Unless otherwise specified, gaskets for raised face flanges shall
match the raised face and shall be 1/16 inch thick for pipe 3-1/2 inches and less in
diameter and 1/8 inch thick for pipe 4 inches and larger.
C. Bolts:
1. Flange assembly bolts shall be ANSI B18.2.1 standard square or hexagon head bolts
with ANSI B18.2.2 standard hexagon nuts. Threads shall be ANSI Bl.1, standard
coarse thread series; bolts shall be Class 2A, nuts shall be Class 2B. Bolt length shall
conform to ANSI B16.5.
2. Unless otherwise specified, bolts shall be carbon steel machined bolts with hot
pressed hexagon nuts. Bolts for submerged service shall be made of Type 316
stainless steel in conformance with ASTM F593, marking F593F. Nuts for submerged
service shall be made of copper-silicon alloy bronze conforming to ASTM B98, alloy
C65100, designation H04 or alloy C65500, designation H04. Bolts and nuts for
buried service shall be made of noncorrosive high-strength, low-alloy steel having the
characteristics specified in ANSI/AWWA C111/A21, regardless of any other
protective coating. Where washers are required, they shall be of the same material
as the associated bolts.
2.02 MECHANICAL COUPLINGS
A. Sleeve-Type Couplings:
1. Unless otherwise specified, sleeve-type mechanical pipe couplings shall be Smith-
Blair Type 411, Dresser Style 38, or equal, with the stop removed from the middle
ring. Reducing couplings shall be Smith-Blair Type 415, Dresser Style 62, or equal.
Sleeve-type flanged coupling adapters shall be Smith-Blair Type 913, Dresser Style
128, or equal. Insulating couplings shall be Smith-Blair Type 416, Dresser Style 39,
or equal.
2. Bolts for submerged service shall be made of Type 316 stainless steel in
conformance with ASTM F593, markingF593F. Nuts for submerged service shall be
made of copper-silicon alloy bronze conforming to ASTM B98, alloy C65100,
designation H04, or alloy C65500, designation H04. Bolts and nuts for buried service
shall be made of noncorrosive high-strength, low-alloy steel having the characteristics
specified in ANSI/AWWA C111/A21, regardless of any other protective coating.
Where washers are required, they shall be of the same material as the associated
bolts.
3. Gaskets shall be as specified in paragraph 2.03 and AWWA C111.
B. Plain End Couplings:
1. Plain end pipe couplings for pipe sizes 6 inches and smaller shall be Gustin-Bacon
200, Victaulic Style 99, or equal for Schedule 80 pipe and Gustin-Bacon 205,
Victaulic Style 90, or equal for lighter weight pipe. Plain end couplings for pipe sizes
8 inches and larger shall be Gustin-Bacon 200, Victaulic Style 99, or equal. Unless
otherwise specified, bolts and nuts shall comply with AWWA C606.
2. Gaskets shall be as specified in paragraph 2.03 and AWWA C606.
C. Grooved End Couplings:
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 4
1. Grooved end flexible-type couplings shall be Gustin-Bacon 100, Victaulic Style 77, or
equal. Grooved end rigid-type couplings shall be Gustin-Bacon 120 Rigi-Grip, Victaulic
Style 07 Zero-Flex, or equal. Flexible-type couplings shall be used for all piping
greater than 12 inches in diameter; for pipe 12 inches in diameter and less in rack-
mounted tunnel piping applications; and for grooved joints adjacent to pump or
blower suction and discharge where grooved couplings are used for noise and
vibration control. All other applications for piping 12 inches in diameter and less shall
utilize rigid-type couplings. Grooved end flanged coupling adapters shall be either
Gustin-Bacon 154, Victaulic Style 741, or equal. Snap-joint grooved end couplings
shall be Gustin-Bacon 115, Victaulic Style 78, or equal. Cut grooves are not permitted
on fabricated or lightwall pipe.
2. Unless otherwise specified, bolts and nuts shall comply with AWWA C606. Bolts for
submerged service shall be Type 316 stainless steel in conformance with ASTM
F593, marking F593F. Nuts for submerged service shall be made of copper-silicon
alloy bronze conforming to ASTM B98, alloy C65100, designation H04 or alloy
C65500, designation H04. Bolts and nuts for buried service shall be made of
noncorrosive high-strength, low-alloy steel having the characteristics specified in
ANSI/AWWA C111/A21, regardless of any other protective coating. Where washers
are required, they shall be of the same material as the associated bolts.
3. Gaskets shall be as specified in paragraph 2.03 and AWWA C 606.
D. Equipment Connection Fittings
1. Equipment connection fittings shall provide both lateral and angular misalignment
adjustment between equipment connection flanges and the connection to field
piping systems by providing individually adjustable flexible joints at each connection.
In addition, equipment connection fittings shall provide full pressure thrust restraint
between the field piping connection and equipment connection flanges.
2. Equipment connection fittings shall consist of two flanged coupling adapters, a plain
end section of pipe and thrust restraint rods and associated fittings designed to
transmit thrust without transmitting shear to the thrust restraint rods and without
compromising provisions for accommodating angular and parallel misalignment.
Materials and features shall conform to the requirements established in this
paragraph. Standard “dismantling joints” incorporate only one flanged coupling
adapter and are not acceptable substitutes. Equipment connection fittings shall be
Romac ECF Series, or Baker Coupling Company, Los Angeles or equal, modified as
specified to provide the required features.
3. Equipment connection fittings shall each consist of a single sleeve of plain end piping
conforming to the requirements of the specified piping system of sufficient length to
span the gap between the connection at the equipment and the connection at the
field piping with gasketed flange adapters at each end. Thrust restraint shall be
provided by means of all threaded rod spanning between flanges and male rod nuts
and female washers that are rounded to provide a ball-joint type self aligning feature.
All threaded restraint rod shall project through flange and mating flange coupling
adapter bolt holes or through holes in restraint lug plates that extend above the
flanges and are secured to the flanges with a minimum of two flange bolts. Where
the all threaded rods project through flange bolt holes, ball joint type nut and washer
combinations and lock washers shall be provided at each face, each end. Where
restraint lug plates are employed, ball joint type nuts and washers shall be provided
only on the outside faces of the plates and the nuts shall have a self locking feature
that prevents nut movement due to vibration or other operational or environmental
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 5
causes. Double nutting with non-locking nuts shall not be an acceptable method of
providing the self locking feature. Thrust rod diameter and material shall be selected
to provide sufficient freedom of movement through all bolt holes to allow unrestricted
maximum adjustment of equipment connection fittings to accommodate piping
misalignment without transmitting any shear to the thrust rods and also to permit full
development of thrust restraint at all thrust rod tension take-ups. Design of
equipment connection fittings shall conform to AWWA C219.
4. Thrust rods, restraint lug plates, nuts, washers and lock washers shall be Type 316
stainless steel, all selected to develop full rated piping system pressure thrust forces.
Equipment connection fittings for pump applications shall have thrust rod number
and diameter selected such that thrust rod stretch under piping system operating
pressure does not exceed 2 mils. Calculations shall be submitted. Dry film
molybdenum di-sulfide anti-galling compound shall be factory applied to ends of
thrust rods, covering all threads subject to nut travel and tightening. Gaskets shall be
as specified in paragraph 2.03. Flange gaskets shall be full face type. Follower
gaskets shall be compression wedge type.
5. Sleeves shall be carbon steel or as specified for the specific piping system. Pressure
rating of flange adapters shall equal or exceed the pressure rating of mating flanges.
All metal portions of equipment connection fittings, with the exception of 316
stainless steel components, shall be coated and lined with fusion bonded epoxy
conforming to AWWA C550 and NSF 61.
E. Dismantling Joints:
1. Dismantling joints may be used as takedown couplings in accordance with paragraph
3.03. Dismantling joints shall fully restrained double flange fittings consisting of a
flange coupling adapter and flanged spool piece that allows for longitudinal
adjustment. Thrust restraint shall be provided by means of all threaded rod spanning
between flanges and secured to the flanges with a minimum of two flange bolts.
Design of equipment connection fittings shall conform to AWWA C219. Sleeves shall
be carbon steel or as specified for the specific piping system. Pressure rating of
flange adapters shall equal or exceed the pressure rating of mating flanges. All metal
portions of equipment connection fittings, with the exception of 316 stainless steel
components, shall be coated and lined with fusion bonded epoxy conforming to
AWWA C550 and NSF 61. Dismantling joints shall be Romac DJ-400, Smith Blair
975, or Crane-Viking Johnson Dismantling Joint.
F. Sleeve Band Couplings:
1. Sleeve band couplings shall be Victaulic Depend-O-Lock. Unless otherwise noted,
couplings for liquid service shall be Model F x F Type 2 fully restrained, shouldered
high deflection couplings with standard width band. Couplings shall comply with
AWWA C-219. Couplings for use with air systems shall be Airmaster restrained
Depend-O-Lock couplings in conformance with AWWA C-606. Sleeve band couplings
are acceptable wherever sleeve type couplings are used (paragraph 2.02 Sleeve
Type Coupling).
G. Flexijoint:
1. Where specified Flexijoint couplings shall be Flanged Romac Flexijoint couplings. The
Flexijoint is a flexible, ductile iron joint that can accommodate expansion,
contraction, rotation and bending and is rated at 350 psi working pressure. The joint
can accommodate 15 to 20 degree deflection depending on size. Body shall be
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 6
ductile iron, lock rings Type 410 stainless steel, and ring gasket, casing, ball and
cover shall be EPDM molded watertight construction. All metal portions of Flexijoint
coupling including the stainless steel lock rings shall be coated and lined with fusion
bonded epoxy conforming to AWWA C550 and NSF 61. For buried installations, install
with polyethylene baggy cover in accordance with the manufacturer’s instructions.
2.03 GASKETS
A. Gaskets designated in Section 40 05 01 shall be as follows:
1. EPDM: ethylene-propylene-diene-terpolymer.
2. Neoprene: neoprene.
3. Nitrile: nitrile (Buna N).
4. Compressed gasketing consisting of organic fibers (Kevlar) and neoprene binder;
ASTM F104 (F712400), 2500 psi (ASTM F152), 0.2 ML/HR LEAKAGE FUEL A (ASTM
F37).
5. Compressed gasketing consisting of organic fibers (Kevlar) and SBR binder; ASTM
F104 (F712400), 2500 PSI (ASTM F152), 0.1 ml/hr leakage Fuel A (ASTM F37).
6. Gylon gasketing, Garlock Style 3500, 2000 psi (ASTM F152), 0.22 ml/hr Fuel A
(ASTM F37).
7. Gylon gasketing, Garlock Style 3510, 2000 psi (ASTM F152), 0.04 ml/hr Fuel A
(ASTM F37).
8. Gylon gasketing, Garlock Style 3504, 2000 psi (ASTM F152), 0.12 ml/hr Fuel A
(ASTM F37).
9. TFE: noncreeping tetrafluoroethylene (TFE) with insert filler.
10. PTFE bonded EPDM: PTFE bonded to EPDM in full-face gasket having concentric-
convex molded rings; Garlock Stress Saver 370 or equal.
2.04 THREAD
A. Pipe thread dimensions and size limits shall conform to ANSI Bl.20.1.
2.05 DIELECTRIC UNIONS
A. Dielectric unions shall be EPCO, Capitol Manufacturing, or equal.
2.06 COATINGS
A. Unless otherwise specified, flange assemblies and mechanical type couplings for buried
installation shall be field coated with System M-1 as specified in Section 09 90 00.
2.07 PRODUCT DATA
A. In accordance with Section 01 33 00, the Contractor shall provide for each welder, a
welder qualification certificate indicating the welder is certified for pipe welding in
accordance with ASME Boiler and Pressure Vessel, Section IX. Each welder's certificate
shall be provided to the Construction Manager prior to that welder working on the job.
Lake Keowee to Adkins WTP Raw Water System Piping Connections
154828 40 05 06.16 - 7
PART 3 EXECUTION
3.01 PIPE CUTTING, THREADING AND JOINTING
A. Pipe cutting, threading and jointing shall conform to the requirements of ANSI B31.1.
3.02 PIPE WELDING
A. Pipe shall be welded by ASME-certified welders using shielded metal arc, gas shielded
arc or submerged arc welding methods. Welds shall be made in accordance with the
requirements of ANSI B31.1 for piping Systems 8, 26, and 28 specified in Section 40 05
01. Welds shall be made in accordance with the requirements of ANSI B31.3 for piping
System 20 specified in Section 40 05 01.
B. Welds for piping systems not specified above shall be made in accordance with AWWA
C206.
3.03 TAKEDOWN COUPLINGS
A. Takedown couplings shall be screw unions, flanged or grooved end mechanical coupling
type joints and shall be provided as specified. Flanged or grooved end joints shall be
employed on pipelines 2-1/2 inches in diameter and larger. Where piping passes through
walls, takedown couplings shall be provided within 3 feet of the wall, unless specified
otherwise.
B. A union or flanged connection shall be provided within 2 feet of each threaded end valve.
3.04 FLEXIBILITY
A. Unless otherwise specified, piping passing from concrete to earth shall be provided with
two pipe couplings or flexible joints (or a single Flexijoint) as specified on the buried pipe
within 2 feet of the structure for 2-inch through 6-inch diameter pipe; within 3 feet of the
structure for 8-inch through 24-inch diameter pipe; and within one and one-half pipe
diameters of the structure for larger pipe. Where required for resistance to pressure,
mechanical couplings shall be restrained in accordance with Chapter 13 of AWWA M11,
including Tables 13-4, 13-5 and 13-5A, and Figure 13-20.
3.05 DIELECTRIC CONNECTIONS
A. Where a copper pipe is connected to steel or cast iron pipe, an insulating section of
rubber or plastic pipe shall be provided. The insulating section shall have a minimum
length of 12 pipe diameters. Dielectric unions as specified in paragraph 2.05 may be
used instead of the specified insulating sections. Where copper pipe is supported from
hangers, it shall be insulated from the hangers, or copper-plated hangers shall be used.
3.06 EQUIPMENT CONNECTION FITTINGS
A. Where shown, equipment connection fittings shall be provided between field piping
systems and equipment inlet and outlet connections.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 1
SECTION 40 05 07
HANGERS AND SUPPORTS FOR PROCESS PIPING
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies hangers and supports for all piping systems specified in
Section 40 05 01. This section does not include pipe supports for fire sprinkler
systems, pipe anchors, guides or seismic restraints.
B. Operating Conditions:
1. The hangers and supports specified in this section are provided to resist pipe loads
occurring primarily in the downward (gravity) direction. For the purpose of pipe
hanger and support selection, this section establishes pipe support classifications
based on the operating temperatures of the piping contents. Pipe support
classifications are as follows:
a. Hot Systems
1) A - 1. 120 degrees F to 450 degrees F
2) A - 2. 451 degrees F to 750 degrees F
3) A - 3. Over 750 degrees F
b. Ambient Systems
1) B. 60 degrees F to 119 degrees F
c. Cold Systems
1) C - 1. 33 degrees F to 59 degrees F
2) C - 2. -20 degrees F to 32 degrees F
C. Hanger and Support Selection:
1. The Contractor shall select pipe hangers and supports as specified in the project
manual. Selections shall be based upon the pipe support classifications specified in
this section, and any special requirements which may be specified in the project
manual.
2. The Contractor shall review the piping layout in relation to the surrounding structure
and adjacent piping and equipment before selecting the type of support to be used at
each hanger point.
3. Hangers and supports shall withstand all static and specified dynamic conditions of
loading to which the piping and associated equipment may be subjected. As a
minimum, consideration shall be given to the following conditions:
a. Weights of pipe, valves, fittings, insulating materials, suspended hanger
components, and normal fluid contents.
b. Weight of hydrostatic test fluid or cleaning fluid if normal operating fluid contents
are lighter.
c. Reaction forces due to the operation of safety or relief valves.
d. Wind, snow or ice loadings on outdoor piping.
4. Hangers and supports shall be sized to fit the outside diameter of pipe, tubing, or,
where specified, the outside diameter of insulation.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 2
5. Where negligible movement occurs at hanger locations, rod hangers shall be used for
suspended lines, wherever practical. For piping supported from below, bases,
brackets or structural cross members shall be used.
6. Hangers for the suspension of size 2 1/2 inches and larger pipe and tubing shall be
capable of vertical hanger component adjustment under load.
7. The supporting systems shall provide for and control the free or intended movement
of the piping including its movement in relation to that of connected equipment.
8. Where there is horizontal movement at a suspended type hanger location, hanger
components shall be selected to allow for swing. The vertical angle of the hanger rod
shall not, at any time, exceed 4 degrees.
9. There shall be no contact between a pipe and hanger or support component of
dissimilar metals. Prevent contact between dissimilar metals when supporting copper
tubing by use of copper-plated, rubber, plastic or vinyl coated, or stainless steel
hanger and support components.
10. Unless otherwise specified, existing pipes and supports shall not be used to support
new piping.
11. Unless otherwise specified, pipe support components shall not be attached to
pressure vessels.
12. Stock hanger and support components shall be used wherever practical.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
AISC Manual of Steel Construction American Institute of Steel Construction, Manual of Steel
Construction, Allowable Stress Design - 9th Ed.
FEDSPEC WW-H-171e-78 Hangers and Supports, Pipe
MFMA-2-91 Metal Framing Standards Publication
MSS SP-69-91 Pipe Hangers and Supports - Selection and Application
MSS SP-58-93 Pipe Hangers and Supports - Materials, Design and Manufacture
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 3
PART 2 PRODUCTS
2.01 ACCEPTABLE PRODUCTS
A. Standard pipe supports and components shall be manufactured by B-Line, Carpenter &
Patterson, Kin-Line, Grinnell, Michigan, Pipe Shields Incorporated, Standon, Superstrut,
Unistrut, or equal. Pipe support components shall conform to the requirements of MSS
SP-69 and FEDSPEC WW-H-171e. Pipe support materials shall conform to the
requirements of MSS SP-58. Metal framing system components shall conform to the
metal framing manufacturers' Association Standard MFMA-2.
2.02 MATERIALS
A. General:
1. Unless otherwise specified, pipe hangers and supports, structural attachments,
fittings and accessories shall be hot-dip or mechanically galvanized after fabrication.
Nuts, bolts and washers may be zinc-plated except for those subject to moisture or
corrosive atmosphere, as specified in Section 26 05 00-1.05 Corrosive Areas, which
shall be type 304 stainless steel.
B. Pipe Hangers and Supports:
1. Type 1 - Clevis Pipe Hanger: Clevis hangers shall be carbon steel with configuration
and components equivalent to MSS and FEDSPEC Type 1.
a. Steel pipe (insulated) - shall be B-Line B3100, Grinnell Fig. 260, or equal, with
insulation shield.
b. Steel pipe (uninsulated) - shall be B-Line B3100, Grinnell Fig. 260, or equal.
c. Cast and ductile iron pipe - shall be B-Line B3102, Grinnell Fig. 590, or equal.
d. Copper pipe (uninsulated) - shall be B-Line B3104 CT, Grinnell Fig. CT-65, or
equal.
e. Copper pipe (insulated) - shall be B-Line B3100, Grinnell Fig. 260, or equal, with
insulation shield.
f. Plastic pipe - shall be B-Line B3100 C, Carpenter & Patterson Fig. 100PVC, or
equal.
2. Type 2 - "J" Pipe Hanger: Hangers shall be carbon steel with configuration and
components equivalent to MSS Type 5.
a. Steel pipe - shall be B-Line B3690, Grinnell Fig. 67, Michigan model 418, or
equal.
b. Copper and plastic pipe - shall be Michigan model 419, Unistrut J 1205N series,
or equal.
3. Type 3 - Double Bolt Pipe Clamp: Pipe clamp shall be carbon steel, with configuration
and components equivalent to MSS and FEDSPEC Type 3.
a. Steel pipe (insulated) - shall be B-Line B3144, Grinnell Fig. 295, or equal, with
insulation shield. Insulation shield is optional for hot and ambient systems.
b. Steel pipe (uninsulated) - shall be B-Line B3144, Grinnell Fig. 295, or equal.
c. Copper pipe (insulated only) - shall be B-Line B3144, Grinnell Fig. 295, or equal,
with insulation shield.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 4
4. Type 4 - Adjustable Roller Hanger: Rollers shall be cast iron, yoke and cross bolt shall
be carbon steel. Configuration and components shall be equivalent to MSS Type 43
and FEDSPEC Type 44.
a. Steel pipe (insulated) - shall be B-Line B3110, Grinnell Fig. 181, or equal, with
insulation shield.
b. Steel pipe (uninsulated) - shall be B-Line B3110, Grinnell Fig. 181, or equal.
c. Copper pipe (insulated only) - shall be B-Line B3110, Grinnell Fig. 181, or equal,
with insulation shield.
d. Plastic pipe - shall be B-Line B3110, Grinnell Fig. 181, or equal.
5. Type 5 - Single Pipe Roll: Rollers and sockets shall be cast iron, cross rod shall be
steel. Configuration and components shall be equivalent to MSS Type 41 and
FEDSPEC Type 42.
a. Steel pipe (insulated) - shall be B-Line B3114, Grinnell Fig. 171, or equal, with
insulation shield.
b. Steel pipe (uninsulated) - shall be B-Line B3114, Grinnell Fig. 171, or equal.
c. Plastic pipe - shall be B-Line B3114, Grinnell Fig. 171, or equal.
6. Type 6 - Framing Channel Pipe Clamp: Pipe clamps shall be steel with galvanized
finish and material thickness as listed below:
a. Steel pipe (uninsulated) - Pipe size 3/8 inch and 1/2 inch shall be 16 gage;
3/4 inch through 1 1/4 inches shall be 14 gage; 1 1/2 inches through 3 inches
shall be 12 gage; 3 1/2 inches through 5 inches shall be 11 gage; 6 and
8 inches shall be 10 gage; Michigan model 431, Powerstrut PS 1100, Unistrut P
1109 series, or equal.
b. Steel pipe (insulated) - Pipe clamp shall be as described in paragraph 2.02 Steel
Pipe (Uninsulated) with insulation shield.
c. Copper (uninsulated) and plastic pipe - Pipe size 3/8 inch and 1 inch shall be 16
gage; 1-1/4 inches and 1-1/2 inches shall be 14 gage; 2 inches through 3 inches
shall be 12 gage; 4 inches shall be 11 gage; clamp shall be copper-plated, plastic
coated or lined with dielectric material; Michigan model 432, Powerstrut PS
1200, Unistrut P 2024C and P 2024PC series, or equal.
d. Copper pipe (insulated) - Pipe clamp shall be as described in
paragraph 2.02 Steel Pipe (Uninsulated) with insulation shield.
7. Type 7 - U-BOLT: U-bolts shall be carbon steel with configuration equivalent to MSS
and FEDSPEC Type 24.
a. Steel pipe (uninsulated) - shall be Grinnell Fig. 137, B-Line B3188, or equal.
b. Steel pipe (insulated) - shall be Grinnell Fig. 137, B-Line B3188, or equal, with
insulation shield.
c. Cast and ductile iron pipe - shall be Grinnell Fig. 137, B-Line B3188, or equal.
d. Copper pipe (uninsulated) - shall be Carpenter & Patterson Fig. 222 CT, B-Line
B3501 CT, Grinnell Fig. 137C, or equal.
e. Copper pipe (insulated) - shall be Grinnell Fig. 137, B-Line B3188, or equal, with
insulation shield.
f. Plastic pipe - shall be Grinnell Fig. 137C, Michigan model 151, B-Line B3188 C,
or equal.
8. Type 8 - Adjustable Pipe Roll Support: Rollers and sockets shall be cast iron, cross
rod and support rods shall be carbon steel.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 5
a. Steel pipe (insulated) - shall be B-Line B3122, Grinnell Fig. 177, or equal, with
insulation shield.
b. Steel pipe (uninsulated) - shall be B-Line B3122, Grinnell Fig. 177, or equal.
c. Copper pipe (insulated only) - shall be B-Line B3122, Grinnell Fig. 177, or equal,
with insulation shield.
d. Plastic pipe - shall be B-Line B3122, Grinnell Fig. 177, or equal.
9. Type 9 - Welded Pipe Stanchion: Minimum material thickness shall be standard
schedule carbon steel pipe, cut to match contour of the pipe elbow. Use of this
support shall be limited to ambient systems only.
10. Type 10 - Pipe Stanchion Saddle: Saddles and yokes shall be carbon steel and
comply with MSS Type 37 and FEDSPEC Type 38.
a. Steel pipe (insulated) - shall be Carpenter & Patterson Fig. 125, B-Line B3090, or
equal, with insulation shield.
b. Steel pipe (uninsulated) - shall be Carpenter & Patterson Fig. 125, B-Line B3090,
or equal.
c. Cast and ductile iron pipe - shall be Carpenter & Patterson Fig. 125, B-Line
B3090 NS, or equal.
d. Flanged ductile iron pipe – shall be Standon S96 or equal.
e. Copper pipe (uninsulated) - shall be Carpenter & Patterson Fig. 125, B-Line
B3090, or equal, with insulation shield or lined with dielectric material.
f. Copper pipe (insulated) - shall be Carpenter & Patterson Fig. 125, B-Line B3090,
or equal, with insulation shield.
g. Plastic pipe - shall be Carpenter & Patterson Fig. 125, B-Line B3090, or equal.
11. Type 11 - Offset Pipe Clamp: Pipe clamp shall be carbon steel with configuration and
components as specified and shall be of standard design manufactured by a pipe
hanger component manufacturer.
a. Steel pipe (insulated) - shall be B-Line B3148, Grinnell Fig. 103, or equal, with
insulation shield.
b. Steel pipe (uninsulated) - shall be B-Line B3148, Grinnell Fig. 103, or equal.
c. Cast and ductile iron pipe - shall be B-Line B3148 NS, Grinnell Fig. 103, or equal.
d. Copper pipe (insulated) - shall be B-Line B3148, Grinnell Fig. 103, or equal, with
insulation shield.
e. Copper pipe (uninsulated) - shall be B-Line B3148, Grinnell Fig. 103, or equal,
lined with dielectric material.
f. Plastic pipe - shall be B-Line B3148, Grinnell Fig. 103, or equal.
g. Vertical pipe support applications shall be as specified above except that
insulation shields shall not be used for insulated pipe.
12. Type 12 - Riser Clamp: Riser clamp shall be carbon steel with configuration and
components equivalent to MSS and FEDSPEC Type 8.
a. Steel pipe (insulated) - shall be B-Line B3373, Grinnell Fig. 261, or equal.
b. Steel pipe (uninsulated) - shall be B-Line B3373, Grinnell Fig. 261, or equal.
c. Cast and ductile iron pipe - shall be B-Line B3373, Grinnell Fig. 261, or equal.
d. Copper pipe (insulated) - shall be B-Line B3373 CT, Grinnell Fig. CT-121,
Michigan model 511, or equal.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 6
e. Copper pipe (uninsulated) - shall be B-Line B3373 CT, Grinnell Fig. CT-121,
Michigan model 511, or equal.
f. Plastic pipe - shall be B-Line B3373, Grinnell Fig. 261c, or equal.
13. Type 13 - Framing Channel Pipe Strap: Pipe strap shall be carbon steel, with
configuration equivalent to MSS Type 26.
a. Steel pipe (uninsulated) - shall be Superstrut No. C-708-U, Powerstrut PS 3126,
Kin-Line No. 477, or equal.
b. Steel pipe (insulated) - shall be Superstrut No. C-708-U, Powerstrut PS 3126, Kin-
Line No. 477, or equal, with insulation shield.
c. Copper pipe (uninsulated) - shall be Superstrut No. C-708-U, Powerstrut PS 3126,
Kin-Line No. 477, or equal, with insulation shield or lined with dielectric material.
d. Copper pipe (insulated) - shall be Superstrut No. C-708-U, Powerstrut PS 3126,
Kin-Line No. 477, or equal, with insulation shield.
e. Plastic pipe - shall be Superstrut No. C-708-U, Powerstrut PS 3126, Kin-Line No.
477, or equal.
C. Rack and Trapeze Supports:
1. General: Unless otherwise specified, trapeze and pipe rack components shall have a
minimum steel thickness of 12 gage, with a maximum deflection 1/240 of the span.
2. Type 20 - Trapeze Pipe Support: Trapeze pipe support cross members shall be
framing channel as specified in paragraph 2.02 Framing Channel. Flat plate fittings
shall be 1 5/8-inch square carbon steel of standard design manufactured by framing
channel manufacturer, Unistrut P2471, B-Line B202-2, or equal.
3. Type 21 - Pipe Rack Support: Post and cross members shall be framing channel as
specified in paragraph 2.02 Framing Channel. Pipe rack fittings shall be carbon steel,
of standard design manufactured by framing channel manufacturer. 90-degree
fittings shall be gusseted Unistrut P2484, B-Line B844, or equal. Post base fittings
shall be as specified in paragraph 2.02 Type E – Framing Channel Post Base.
D. Structural Attachments:
1. Type A - Malleable Iron Concrete Insert: Concrete inserts shall be malleable iron and
comply with MSS and FEDSPEC Type 18. Grinnell Fig. 282, Carpenter & Patterson
Fig. 108, or equal.
2. Type B - Side Beam Bracket: Bracket shall be malleable iron and comply with MSS
Type 34 and FEDSPEC Type 35. Grinnell Fig. 202, B-Line B3062, or equal.
3. Type C - Malleable Beam Clamp With Extension Piece: Clamp and extension piece
shall be malleable iron, tie rod shall be steel. Beam clamp shall comply with MSS and
FEDSPEC Type 30. Grinnell Fig. 218 with Fig. 157 extension piece, B-Line B3054, or
equal.
4. Type D - Steel Beam Clamp With Eye Nut: Beam clamp and eye nut shall be forged
steel. Configuration and components shall comply with MSS and FEDSPEC Type 28.
Grinnell Fig. 292, Carpenter & Patterson Fig. 297, or equal.
5. Type E - Framing Channel Post Base: Post bases shall be carbon steel, of standard
design manufactured by framing channel manufacturer. Single channel: Unistrut
P2072A, B-Line B280, or equal. Double channel: Unistrut P2073A, B-Line B281, or
equal.
6. Type F - Welded Beam Attachment: Beam attachment shall be carbon steel and
comply with MSS and FEDSPEC Type 22. B-Line B3083, Grinnell Fig. 66, or equal.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 7
7. Type G - Welded Steel Bracket: Bracket shall be carbon steel and comply with MSS
Type 32 and FEDSPEC Type 33 for medium welded bracket. Heavy welded bracket
shall comply with MSS Type 33 and FEDSPEC Type 34.
8. Type H - Cast Iron Bracket: Bracket shall be cast iron, Carpenter & Patterson Fig. 340,
or equal.
9. Type J - Adjustable Beam Attachment: Beam attachment shall be carbon steel,
Carpenter & Patterson Fig. 151, B-Line B3082, or equal.
10. Type K - Double Channel Bracket: Wall channel shall be single channel framing
channel as specified in paragraph 2.02 Framing Channel. Cantilever bracket shall be
a carbon steel double framing channel assembly, Unistrut P2542 through P2546, B-
Line B297-12 through B297-36, or equal.
11. Type L - Single Channel Bracket: Wall channel shall be single channel framing
channel as specified in paragraph 2.02 Framing Channel. Cantilever bracket shall be
a carbon steel single framing channel assembly, Unistrut P2231 through P2234, B-
Line B198-6, B198-12, B196-18 and B196-24, or equal.
12. Type M - Wall Mounted Channel: Wall channel shall be single channel framing
channel as specified in paragraph 2.02 Framing Channel.
13. Type N - Pipe Stanchion Floor Attachment: Baseplate shall be carbon steel with 1/2
inch minimum thickness. Anchor bolt holes shall be 1/16 inch larger than the anchor
bolt diameter. The space between the baseplate and the floor shall be filled with
nonshrink grout.
E. Accessories:
1. Hanger Rods: Rods shall be carbon steel, threaded on both ends or continuous
threaded and sized as specified.
2. Weldless Eye Nut: Eye nut shall be forged steel and shall comply with MSS and
FEDSPEC Type 17. Eye nut shall be Grinnell Fig. 290, B-Line B3200, or equal.
3. Welded Eye Rod: Eye rod shall be carbon steel with eye welded closed. Inside
diameter of eye shall accommodate a bolt diameter 1/8 inch larger than the rod
diameter. Eye rod shall be Grinnell Fig. 278, B-Line B3211, or equal.
4. Turnbuckle: Turnbuckle shall be forged steel and shall comply with MSS and
FEDSPEC Type 13. Turnbuckle shall be Grinnell Fig. 230, B-Line B3202, or equal.
5. Framing Channel: Framing channel shall be 1 5/8 inches square, roll formed, 12-
gage carbon steel. Channel shall have a continuous slot along one side with in-turned
clamping ridges. Single channel: Unistrut P1000, B-Line B22, or equal. Double
channel: Unistrut P1001, B-Line B22A, or equal. Triple channel: Unistrut P1004A, B-
Line B22X, or equal.
2.03 PRODUCT DATA
A. Hanger and support locations and components shall be indicated on the piping layout
drawings required by Section 40 05 01-2.04.
PART 3 EXECUTION
3.01 HANGER AND SUPPORT LOCATIONS
A. The Contractor shall locate hangers and supports as near as possible to concentrated
loads such as valves, flanges, etc. Locate hangers, supports and accessories within the
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 8
maximum span lengths specified in the project manual to support continuous pipeline
runs unaffected by concentrated loads.
B. At least one hanger or support shall be located within 2 feet from a pipe change in
direction.
C. The Contractor shall locate hangers and supports to ensure that connections to
equipment, tanks, etc., are substantially free from loads transmitted by the piping.
D. Where piping is connected to equipment, a valve, piping assembly, etc., that will require
removal for maintenance, the piping shall be supported in such a manner that temporary
supports shall not be necessary for this procedure.
E. Pipe shall not have pockets formed in the span due to sagging of the pipe between
supports caused by the weight of the pipe, medium in the pipe, insulation, valves and
fittings.
3.02 INSTALLATION
A. Welded and bolted attachments to the building structural steel shall be in accordance
with the requirements of the AISC Manual of Steel Construction. Unless otherwise
specified, there shall be no drilling or burning of holes in the building structural steel.
B. Hanger components shall not be used for purposes other than for which they were
designed. They shall not be used for rigging and erection purposes.
C. The Contractor shall install items to be embedded before concrete is poured. Fasten
embedded items securely to prevent movement when concrete is poured.
D. Embedded anchor bolts shall be used instead of concrete inserts for support installations
in areas below water surface or normally subject to submerging.
E. The Contractor shall install thermal pipe hanger shields on insulated piping at required
locations during hanger and support installation. Butt joint connections to pipe insulation
shall be made at the time of insulation installation in accordance with the manufacturer's
recommendations.
F. Hanger and support components in contact with plastic pipe shall be free of burrs and
sharp edges.
G. Rollers shall roll freely without binding.
H. Finished floor beneath Type N structural attachments and framing channel post bases
shall be roughed prior to grouting. Grout between base plate and floor shall be free of
voids and foreign material.
I. Baseplates shall be cut and drilled to specified dimensions prior to welding stanchions or
other attachments and prior to setting anchor bolts.
J. Plastic or rubber end caps shall be provided at the exposed ends of all framing channels
that are located up to 7 feet above the floor.
Lake Keowee to Adkins WTP Raw Water System Hangers and Supports for Process Piping
154828 40 05 07 - 9
3.03 ADJUSTMENTS
A. The Contractor shall adjust hangers and supports to obtain required pipe slope and
elevation. Shims made of material that is compatible with the piping material may be
used. Stanchions shall be adjusted prior to grouting their baseplates.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Manual Actuators
154828 40 05 57.13 - 1
SECTION 40 05 57.13
MANUAL ACTUATORS
PART 1 GENERAL
1.01 DESCRIPTION
A. This section specifies manual operators for valves and gates, and operator
appurtenances.
1.02 REFERENCES
1. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains
references to other standards, those documents are included as references under
this section as if referenced directly. In the event of conflict between the
requirements of this section and those of the listed documents, the requirements of
this section shall prevail.
2. Unless otherwise specified, references to documents shall mean the documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective
date of the Agreement if there were no Bids). If referenced documents have been
discontinued by the issuing organization, references to those documents shall mean
the replacement documents issued or otherwise identified by that organization or, if
there are no replacement documents, the last version of the document before it was
discontinued. Where document dates are given in the following listing, references to
those documents shall mean the specific document version associated with that
date, regardless of whether the document has been superseded by a version with a
later date, discontinued or replaced.
Reference Title
AWWA C500 Gate Valves 3 through 48 inch NPS, for Water and Sewage Systems
PART 2 PRODUCTS
2.01 GENERAL
A. Except as specified in valve and gate specification sections, manual operators shall be as
specified herein. Operators shall be mounted on the valve or gate and provided as a unit.
Each valve body or operator shall have cast thereon the word "OPEN," an arrow indicating
the direction to open, and flow direction arrows.
2.02 OPERATORS
A. General:
1. Manual operators shall have operating torques less than 80 foot-pounds. Unless
specified otherwise, each manual operator shall be provided with an operating wheel.
Unless specified otherwise, the direction of rotation of the operator shall be
counterclockwise for opening.
B. Wrench Nuts:
Lake Keowee to Adkins WTP Raw Water System Manual Actuators
154828 40 05 57.13 - 2
1. Wrench nuts shall comply with Section 3.15 of AWWA C500. A minimum of two
operating keys, but no less than one key per every ten valves, shall be provided for
operation of the wrench nut operated valves.
C. Chain Wheels:
1. Chain wheels shall be ductile iron. Operating chains shall be galvanized.
2.03 OPERATOR APPURTENANCES
A. Valve Boxes:
1. Valve boxes shall be cast iron and shall have suitable base castings to fit properly
over the bonnets of their respective valves and heavy top sections with stay-put
covers. Covers shall be hot-dip galvanized.
B. Floor Boxes:
1. Floor boxes shall be hot-dip galvanized. Where the operating nut is in the concrete
slab, the floor box shall be bronze bushed. Where the operating nut is below slab, the
opening in the bottom of the box shall be sufficient for passage of the operating key.
C. Adjustable Shaft Valve Boxes:
1. Adjustable shaft valve boxes shall be concrete or cast iron Brooks No. 3RT, Christie
G5, Empire 7-1/2 valve extension box, or equal. Box covers on water lines shall be
impressed with the letter "W." Gas line covers shall be impressed with the letter "G."
2.04 PRODUCT DATA
A. Manufacturer's catalog information and other data confirming conformance to design
and material requirements shall be provided in accordance with Section 01 33 00.
PART 3 EXECUTION
3.01 GENERAL
A. Installation shall be as specified herein. Valve operators shall be located so that they are
readily accessible for operation and maintenance. Valve operators shall be mounted for
unobstructed access, but mounting shall not obstruct walkways. Valve operators shall
not be mounted where shock or vibration will impair their operation. Support systems
shall not be attached to handrails, process piping, or mechanical equipment.
3.02 OPERATORS
A. General:
1. Valves and gates shall be provided with manual operators, unless specified
otherwise. Where possible, manual operators shall be located between 48 inches
and 60 inches above the floor or a permanent work platform.
B. Wrench Nuts:
1. Wrench nuts shall be provided on buried valves, on valves which are to be operated
through floor boxes, and where specified. Extended wrench nuts shall be provided if
necessary so that the nut will be within 6 inches of the valve box cover.
Lake Keowee to Adkins WTP Raw Water System Manual Actuators
154828 40 05 57.13 - 3
C. Chain Wheels:
1. Unless otherwise specified, valves with centerlines more than 7 feet, 6 inches above
the specified operating level shall be provided with chain wheels and operating
chains. Chain wheel operated valves shall be provided with a chain guide. Operating
chains shall be looped to extend within 4 feet of the specified operating level below
the valve. For plug-type valves 8 inches and larger, the operator shall be provided
with a hammer blow wheel. Hooks shall be provided for chain storage where the
chain may hang in a walkway.
3.03 OPERATOR APPURTENANCES
A. Valve Boxes:
1. Valve boxes extending to finished surfaces shall be provided for buried valves.
B. Floor Boxes:
1. Floor boxes shall be provided for wrench operation of valves located below concrete
slabs. Each floor box and cover shall be of the depth required for installation in the
slab.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Butterfly Valves
154828 40 05 64 - 1
SECTION 40 05 64
BUTTERFLY VALVES
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies butterfly valves for water service.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings Class 25, 125, 250
and 800
ANSI B16.5 Pipe Flanges and Flanged Fittings
ASTM A48 Gray Iron Castings
ASTM A108 Steel Bars, Carbon, Cold-Finished, Standard Quality
ASTM A126 Gray Iron Castings for Valves, Flanges, and Pipe Fittings
ASTM A216/A216M Steel Castings, Carbon, Suitable for Fusion Welding, for High
Temperature Service
ASTM A276 Stainless and Heat-Resisting Steel Bars and Shapes
ASTM A436 Austenitic Gray Iron Castings
ASTM A536 Ductile Iron Castings
AWWA C504 Rubber-Seated Butterfly Valves
PART 2 PRODUCTS
2.01 MATERIALS
A. Size 30 Through 72 Inches: Valves from 30 through 72 inches in size shall be
constructed of the following materials unless otherwise specified:
Lake Keowee to Adkins WTP Raw Water System Butterfly Valves
154828 40 05 64 - 2
Component Material
Shaft Stainless steel, ASTM A276, Type 304
Disc Ductile iron, ASTM A536, or cast iron, ASTM A48, Class 40
Seat mating surface Stainless steel, ASTM A276, Type 304, mounted in body or on
disc edge
Seat sealing surface Neoprene, EPDM or Buna N
Body Cast iron, ASTM A126, Class B
2.02 MANUFACTURE
A. General:
1. Valves shall be the stub or through shaft design. Wafer type valves are not
acceptable for buried service. Unless otherwise specified, valve flange drilling shall
be per ANSI B16.1, Class 125.
B. Valves shall be designed in accordance with AWWA C504. Shafts shall be turned, ground
and polished. Shaft dimensions and operator torque shall be chosen for the pressure
specified in Section 40 05 01 and Class B as specified in AWWA C504. When carbon
steel shafts and stainless steel journals are used, static seals shall be provided to isolate
the interior of the disc and the shaft from the process fluid.
C. Valves, size 3 through 72 inches, shall have seats that are vulcanized, bonded,
mechanically secured, or clamped to the body or disc.
D. Vavles, size 30 through 72 inches, valve seats shall be field adjustable and field
replaceable. Discs for valves shall be of the flow-through Type with a 360-degree seating
design.
2.03 MANUAL OPERATORS
A. General:
1. Manual operators shall be designed in accordance with AWWA C504 and shall have
a disc position indicator designating the opened and closed position of the valve.
2. Manual operators shall be of the traveling nut, rack and pinion, or worm gear type.
Operators shall be equipped with adjustable mechanical stop-limiting devices to
prevent overtravel of the disc in the open and closed positions and shall be self-
locking and designed to hold the valve in any intermediate position between full open
and full closed. Valve operator components shall withstand an input torque of 300 ft-
lbs at the extreme operator positions without damage.
3. Operator for buried service shall include an AWWA operating nut and shall be
gasketed and grease packed for submerged operation at water pressures to 10 psig.
Operators for exposed service shall include a handwheel and be gasketed for
weatherproof service.
2.04 PRODUCT DATA
A. Affidavits of compliance with AWWA C504 valves shall be provided in accordance with
Section 01 33 00.
B. Acceptable manufacturers include Dezurik, Milliken, Mueller, and Golden Anderson.
Lake Keowee to Adkins WTP Raw Water System Butterfly Valves
154828 40 05 64 - 3
PART 3 EXECUTION
3.01 INSTALLATION
A. Valves shall be installed in accordance with the manufacturer's recommendations.
END OF SECTION
Lake Keowee to Adkins WTP Raw Water System Air/Vacuum Valves for Water Service
154828 40 05 78.13 - 1
SECTION 40 05 78.13
AIR/VACUUM VALVES FOR WATER SERVICE
PART 1 GENERAL
1.01 DESCRIPTION
A. Scope:
1. This section specifies air release valves, air and vacuum valves, and combination air
valves for clean water service, pumping, and storage applications.
B. Types:
1. Air Release Valves: Air release valves (ARV) shall have a small venting orifice to vent
the accumulation of air and other gases with the line or system under pressure. Size
and capacity shall be as specified.
2. Air and Vacuum Valves: Air and vacuum valves (AVV) shall have a large venting orifice
to permit the release of air as the line is filling or relieve the vacuum as the line is
draining or is under negative pressure. Size and capacity
3. Combination Air Valves: Combination air valves (CAV) shall have operating features of
both the air and vacuum valve and the air release valve. They include both single-
and dual-body construction. Size and capacity shall be as specified.
4. Air Valves for Vertical Turbine Pumps: Air valves for vertical turbine pumps (ATP) shall
consist of an air and vacuum valve with throttling device for sizes 3-inch and less,
and a dual body construction combination air valve mounted on top of a surge check
for sizes 4-inch and larger. Size and capacity shall be as specified.
1.02 REFERENCES
A. This section contains references to the following documents. They are a part of this
section as specified and modified. Where a referenced document contains references to
other standards, those documents are included as references under this section as if
referenced directly. In the event of conflict between the requirements of this section and
those of the listed documents, the requirements of this section shall prevail.
B. Unless otherwise specified, references to documents shall mean the documents in effect
at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). If referenced documents have been discontinued by
the issuing organization, references to those documents shall mean the replacement
documents issued or otherwise identified by that organization or, if there are no
replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents
shall mean the specific document version associated with that date, regardless of
whether the document has been superseded by a version with a later date, discontinued
or replaced.
Reference Title
ASTM A126 Gray Iron Castings for Valves, Flanges, and Pipe Fittings
ASTM A240 Heat-Resisting Chromium and Chromium Nickel Stainless Steel Plate, Sheet,
and Strip for Pressure Vessels
Lake Keowee to Adkins WTP Raw Water System Air/Vacuum Valves for Water Service
154828 40 05 78.13 - 2
1.03 SCHEDULE
Valve number Valve size, inches Type System press, PSI Capacity, CFFAM/SCFS
ARV 5+40 8 AVV 150
PART 2 PRODUCTS
2.01 ACCEPTABLE PRODUCTS
A. Air release and vacuum valves shall be APCO as manufactured by Valve and Primer
Corporation, Crispin as manufactured by Multiplex Manufacturing Company, or equal,
modified to provide the specified features and to meet the specified operating
conditions.
2.02 MATERIALS
Component Material
Body, cover Cast iron, ASTM A126, Grade B
Float Type 316 SS, ASTM A240
Seat Buna-N or Type 316 SS
Trim Type 316 SS, ASTM A240
A. Materials specified are considered the minimum acceptable for the purposes of
durability, strength, and resistance to erosion and corrosion. The Contractor may propose
alternative materials for the purpose of providing greater strength or to meet required
stress limitations. However, alternative materials must provide at least the same
qualities as those specified for the purpose.
2.03 CONSTRUCTION
A. Air release valves shall be float operated, compound lever type, except air release valves
less than 1-inch may be simple lever type.
B. Air and vacuum valves shall be designed to protect the float from direct contact of the
rushing air and water to prevent the float from closing prematurely in the valve. The seat
shall be fastened into the valve cover, and shall be easily removed if necessary. The float
shall be center or peripheral guided for positive shutoff into the seat.
C. Combination air valves, unless otherwise specified, shall be single-body construction in
sizes 1- through 6-inch and dual-body construction in sizes 8-inch and larger. Single-body
construction shall be designed to provide all functions within one housing. The body inlet
shall be baffled to protect the float and the large and small orifices shall be designed so
that during large orifice closure, the small air release orifice will open to allow small
amounts of air to escape. Dual-body construction shall combine one air and vacuum
valve and one air release valve with interconnecting piping and gate valve.
D. Air valves for vertical turbine pumps (sizes 3-inch and less) shall be designed and
constructed as specified for air and vacuum valves except the discharge orifice shall be
fitted with a throttling device to regulate and restrict air venting and establish a pressure
Lake Keowee to Adkins WTP Raw Water System Air/Vacuum Valves for Water Service
154828 40 05 78.13 - 3
loading on the rising column of water on pump start. Unless otherwise specified, air
valves, 4-inch and larger, shall be dual body combination air valves except the inlet shall
be fitted with a surge check to prevent water column entering the valve on pump start.
E. Valves shall be suitable for pressures up to 150 psi.
2.04 PRODUCT DATA
A. The following information shall be provided in accordance with Section 01 33 00:
1. Manufacturer's product data.
2. Applicable O&M instruction manuals per Section 01 78 23.
PART 3 EXECUTION
3.01 INSTALLATION
A. Air release and vacuum valves shall be installed in accordance with the manufacturer's
recommendations. Unless otherwise specified, isolation valves per Section 40 05 01
shall be provided below each air valve.
END OF SECTION
Appendix A - Geotechnical Engineering Report
S&ME, Inc. Geotechnical Engineering Report
Revised Subsurface Exploration Report, Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&M Project No. 1569-20-028
November 19, 2020
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
PREPARED FOR:
Brown and Caldwell
250 Berryhill Road, Suite 104
Columbia, South Carolina 29210
PREPARED BY:
S&ME, Inc.
48 Brookfield Oaks Drive, Suite F
Greenville, South Carolina 29607
November 19, 2020
S&ME, Inc. | 48 Brookfield Oaks Drive, Ste F | Greenville, SC 29607 | p 864.297.9944 | www.smeinc.com
November 19, 2020
Brown and Caldwell
250 Berryhill Road, Suite 104
Columbia, South Carolina 29210
Attention: Mr. Scott Adams, P.E.
Reference: Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
Dear Mr. Adams:
S&ME, Inc. has completed the first and second phases of the subsurface exploration services for the referenced
site in Pickens County, South Carolina. This work was performed in general accordance with S&ME Proposal No.
15-2000032, dated January 31, 2020 and with the Standard Subcontract for Professional Services between S&ME
and Brown and Caldwell, executed on March 30, 2020. A subsurface exploration report was previously provided
on June 12, 2020 for the first phase of work (borings B-1 through B-12). This report has been updated to address
the second phase of work (borings B-13 through B-17).
The purpose of this geotechnical study was to determine the general subsurface conditions at selected locations
along the proposed alignment and to evaluate those conditions with regard to the design and construction of the
proposed water line. This report presents our findings together with our conclusions and recommendations for
design and construction of the proposed pipeline.
We appreciate the opportunity to be of continued service to you on this project. If you have any questions
concerning the information presented or if we can be of further assistance, please contact us.
Sincerely,
S&ME, Inc.
Jordan Titus, P.E. David Swoap, P.E.
Project Engineer Principal Engineer
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 iii
Table of Contents
1.0 Project Information ........................................................................................................... 1
2.0 Exploration and Testing ................................................................................................... 1
2.1 Field Exploration ............................................................................................................................ 1
2.2 Laboratory Testing ......................................................................................................................... 2
3.0 Site Conditions .................................................................................................................. 2
3.1 Surface Features .............................................................................................................................. 2
3.2 Area Geology .................................................................................................................................. 5
3.3 Subsurface Conditions ................................................................................................................... 5
3.3.1 Surface Materials .............................................................................................................................. 5
3.3.2 Existing Fill....................................................................................................................................... 6
3.3.3 Alluvial Soils ..................................................................................................................................... 6
3.3.4 Residual & Possible Residual Soils ................................................................................................... 6
3.3.5 Subsurface Water .............................................................................................................................. 6
3.3.6 Laboratory Testing Discussion ......................................................................................................... 7
4.0 Conclusions and Recommendations ............................................................................. 7
4.1 Site Preparation ............................................................................................................................... 8
4.2 Excavation ....................................................................................................................................... 8
4.3 Dewatering/Surface Water Considerations ................................................................................ 9
4.4 Pipe Installation ............................................................................................................................ 10
4.4.1 Existing Fill and Alluvial Soils ....................................................................................................... 10
4.4.2 Uplift Forces .................................................................................................................................... 10
4.4.3 Pipe Bedding ................................................................................................................................... 10
4.5 Fill Placement and Compaction.................................................................................................. 11
4.5.1 Use of Excavated Soils as Fill .......................................................................................................... 11
4.5.2 Use of Off-Site Borrow Materials as Fill ......................................................................................... 11
4.5.3 Allowable Bearing Capacity for Site Structures ............................................................................. 11
5.0 Limitations of Report ..................................................................................................... 12
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 iv
Appendix
Boring Location Plan (Figures 1 and 2)
Legend to Soil Classification and Symbols
Boring Logs (B-1 through B-17)
Field Testing Procedures
Laboratory Test Results
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 1
1.0 Project Information
Our understanding of the project is based on the following:
• Email and telephone correspondence between Mr. Scott Adams, P.E. and Mr. Jordan Titus, P.E. with S&ME
between January 23 and June 8, 2020;
• Our review of the Figures_Combined_proposed borings, which was prepared by Brown and Caldwell and
provided by Mr. Adams as an attachment to the May 6, 2020 email;
• Our review of the ACAD 2020-28.dwg, which was provided as an attachment to the above referenced June
3 email;
• Email correspondence between Mr. Adams, Mr. Jay Mazzei, P.E. with Brown and Caldwell between
September 21 and October 17, 2020;
• A site meeting between Brown and Caldwell, Howard Engineering, Chao and Associates, and Greenville
Water on October 8, 2020;
• Site visits by Mr. Titus and Mr. Josh Gathro, E.I.T. with S&ME in May and October of 2020; and
• Our review of aerial images from Google EarthTM and the Pickens County GIS website.
Based on the information provided, we understand that Greenville Water plans to replace portions of a raw water
line from a pump station on Lake Keowee to the Adkins Water Treatment Plant in Pickens County, South Carolina.
The new water line will be constructed in two sections. The first section will be approximately 4,700-feet long and
be installed within an existing easement and will connect the water treatment plant to a connection point on
Cofferdam Road (Phase 1). We understand the new line will be installed between an existing 48-inch and 54-inch
raw water lines that currently supply the treatment plant. The new water line will primarily be installed at depths
ranging from approximately 10- to 15-feet below the existing ground surface in this first phase.
The second section will be approximately 1,800 feet long and will connect the pump station on Lake Keowee to a
connection point at the end of Wellhouse Crossing (Phase 2). The water line will run through an existing
causeway. We understand that an existing 48 inch raw water line will be removed and replaced in this section.
The new water line we primarily be installed at depths ranging from approximately 8- to 10- feet below the
existing ground surface in this phase (including approximately 4 feet of cover).
2.0 Exploration and Testing
2.1 Field Exploration
Our field exploration included site reconnaissances by a member of our geotechnical staff and the drilling of
twelve (17) soil test borings (labeled B-1 through B-17). Proposed boring locations were provided to us as
indicated on the Figures_Combined_proposed borings for Phase 1. Boring locations for Phase 1 were adjusted in
the field to avoid the existing water lines. Boring depths for Phase 1 were provided by Mr. Adams during a phone
conversation on May 12, 2020. Boring locations and depths for Phase 2 were chosen during the October 8, 2020
site meeting. The boring locations were established in the field using our hand-held GPS and are depicted on the
Boring Location Plan (Figures 1 and 2) in the Appendix.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 2
The Phase 1 borings were drilled with an ATV-mounted drill rig (CME 550 with an automatic hammer) and the
Phase 2 borings were drilled with a truck mounted drill rig (CME 55 with an automatic hammer). Hollow-stem
augers were used to advance all of the boreholes. Split-spoon samples and Standard Penetration Resistance (N)
values were generally obtained at 2.5-foot intervals in the upper 10 feet, and at 5-foot intervals thereafter. An
additional split-spoon sample was obtained at the boring termination depth (12 or 16 feet). After completion of
drilling, we measured the depth to subsurface water at the time of boring (TOB). We then backfilled some of the
boreholes with soil cuttings and installed a mechanical hole plug near the surface in each boring to help reduce
borehole settlement. Temporary standpipes (piezometers) were installed in 4 borings and 1 boring remained
open for stabilized water measurements. After a period of at least 24 hours, water levels were measured from the
open boring and piezometers. The piezometers were then removed and the boreholes were backfilled as
described above.
The drill rigs used on this project utilized an autohammer for conducting the Standard Penetration Tests. The N-
values presented on the Boring Logs have not been corrected for theoretical energy (see Field Testing Procedures
in the Appendix for additional discussion); however, our evaluation of the subsurface soils is based on the
corrected N-values.
2.2 Laboratory Testing
After completion of the field work, the split-spoon samples were transported to our laboratory where a
Geotechnical Professional visually and manually classified the soils in general accordance with the Unified Soil
Classification System (USCS). The results of the classifications and the field testing results are presented on the
individual Boring Logs in the Appendix, along with a Legend to Soil Classification and Symbols, and the Field
Testing Procedures. The boring locations and ground surface elevations shown on the Boring Logs and profile
were estimated from the provided ACAD 2020-28.dwg and Google EarthTM and should be considered
approximate.
Selected split-spoon samples in Phase 1 were subjected to laboratory index testing (moisture content, Atterberg
limits, and grain size distribution tests) to aid in the classification and evaluation of the soil’s engineering
properties. The Appendix contains the individual laboratory test reports, and the results are discussed in following
sections of this report.
Composite samples from eight different borings in Phase 1 were sent to Corrosion Testing Laboratories, Inc. for
corrosion series testing. The corrosion series test results will be reported by others.
3.0 Site Conditions
3.1 Surface Features
As previously mentioned, the Phase 1 water line will be installed between the Adkins Water Treatment Plant (WTP)
and a connection point on Cofferdam Road. The majority of the Phase 1 borings are within an existing easement
of the roadway. The ground surface along the easement is primarily grassed with some longer brush, with a tree
line on either side of the easement. Two creeks run perpendicular to the easement near borings B-5 and B-10 and
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 3
rip-rap was observed near the banks. The ground surface elevations typically slope gently along the easement.
However, more severe elevation changes occurred near the creek banks, with approximately 70 feet of
topographic relief occurring across the proposed alignment for the new water line.
The Phase 2 water line will be installed between the pump station on Lake Keowee and a connection point at the
end of Wellhouse Crossing. The two existing water lines are approximately 15 feet apart and generally run on
both sides of a paved asphalt drive that connects the pump station to Wellhouse Crossing. The water lines cross
an approximately 500 foot causeway that connect Wellhouse Crossing to the small island the pump station is
located on. The causeway is approximately 40 feet wide and the embankment face of each side is protected by
rip-rap. Our Phase 2 exploration was limited to the causeway and the connection point. The roadway slopes
gently down from the connection point at Wellhouse Crossing to the causeway. The causeway is relatively level
with elevations ranging from approximately 805 to 808 feet.
Our exploration and site visits for Phase 1 were made during relatively warm, overcast and rainy weather. The
ground surface was observed to be stable, but somewhat moist at the time of our original exploration, due to
rains in May of this year. Our exploration and site visits for Phase 2 were made during relatively cool and
somewhat rainy weather. The ground surface was stable during our exploration for phase 2. Photographs of the
site taken during our site visits are shown below.
Date
: 5/8
/2020
P
ho
tog
rap
her:
J. Tit
us
Location / Orientation Standing at western end of easement facing east.
Remarks Topography slopes relatively sharply towards the creek.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 4
Date
: 5/1
5/2
020
P
ho
tog
rap
her:
J. Tit
us
Location / Orientation Standing near boring B-8 facing east.
Remarks Topography slopes gently in this area.
Date
: 10/8
/2020
P
ho
tog
rap
her:
J. Tit
us
Location / Orientation Standing near boring B-14 facing west.
Remarks View of the existing Causeway.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 5
3.2 Area Geology
The subject property is in the Piedmont Physiographic Province of western South Carolina. Rocks of the Piedmont
occur in belts that extend across portions of the southeast and are primarily metamorphic gneiss and schist with
some granite intrusions. The bedrock in the Piedmont is covered with residual soil (weathered in-place) of varying
thickness, derived by chemical decomposition and physical weathering of the underlying rock. The resulting
residual soils consist predominately of micaceous sandy silts and silty sands which often grade to clayey silts and
silty clays with nearness to the ground surface. The thickness of the residual soils can vary from only a few feet to
over 100 feet.
The boundary between the residual soil and the underlying bedrock is not sharply defined. Generally, a transition
zone consisting of very hard soil to soft rock, appropriately classified as “partially weathered rock” (PWR), is found.
Within the transition zone, large boulders or lenses of relatively “fresh” rock which are generally much harder than
the surrounding material often exist. The irregular bedrock surface is basically a consequence of differential
weathering of the various minerals and joint patterns of the rock mass.
The natural geological profile of portions of the proposed alignment of the new water line have been disturbed by
past grading activities (primarily construction of the causeway and excavation and installation of the existing water
lines and other utilities) that resulted in the placement of fill. Please keep in mind fill soils can vary in composition
and consistency, and the engineering characteristics of these soils can be difficult to predict. Although there is no
specific correlation between the degree of compaction of existing fill and the results of standard penetration
testing, a qualitative assessment of existing fill can often be made based on visual observation of the fill materials
sampled in the borings and the general magnitude of the standard penetration test values.
Alluvial soils are typically present within and adjacent to former and existing drainage features. Typically, the
upper soils along streams and drainage features, and within geologic flood plain areas, are water-deposited
materials (termed alluvium) that have been eroded and transported from higher elevations upstream. These
alluvial soils are usually wet, soft, and compressible. Alluvium can vary from silts and clays to sand, gravel, and
cobbles, and can contain organic debris and mica.
3.3 Subsurface Conditions
The following is a brief and general description of subsurface conditions encountered along the proposed
alignment of the new water line. More detailed information is provided on the individual Boring Logs included in
the Appendix. Similar soils were grouped into strata on the logs. The strata contact lines represent approximate
boundaries between soil types; the actual transition between soil types in the field could be gradual in both the
horizontal and vertical directions.
3.3.1 Surface Materials
A 1- to 3-inch organic-laden layer of topsoil was initially encountered at the ground surface in each of the borings
within Phase 1 (B-1 through B-13) and boring B-17. In borings B-14 through B-16 a 2- to 3- inch thick layer of
asphalt was initially encountered. The asphalt in borings B-14 and B-16 was underlain by 2 and 1 inches of
crushed stone, respectively. Please note that surface materials will vary in type and thickness throughout the area
proposed for the new water line.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 6
3.3.2 Existing Fill
Existing fill was encountered beneath the surface materials in 14 of the 17 borings (B-1 through B-5, B-7 through
B-9, and B-12 through B-17) to depths of approximately 5½ to 16 feet below the existing ground surface. The fill
consisted primarily of sandy lean clay (USCS symbol CL), sandy silt (ML), and silty sand (SM), often with traces to
some rock fragments and occasionally mica. The fill appeared relatively free from debris and organic matter,
except for the borings performed in the causeway (borings B-15 and B-16). The causeway borings contained trace
roots, organic staining and an organic odor. The Standard Penetration Resistance (N) values recorded in the
existing fill ranged from 4 to 35 blows per foot (bpf). However, higher blow counts were likely amplified by rock
fragments. Typical N values in the fill ranged from 5 to 21 bpf, indicating a low to moderately high degree of
compaction. Borings B-2, B-3, B-5, B-15, and B-16 were terminated in fill at their planned termination depths of
12 or 16 feet.
It should be noted that existing fill soils often become wet due to rainwater runoff infiltrating these soils and
becoming perched above layers of more consistent residual soils. In addition, the upper residual soils near the
fill/residuum interface can be moist or wet as well. Based on the presence of the existing nearby underground
utilities, we expect additional fill will be encountered at various depths and locations throughout the proposed
alignment of the new water line.
3.3.3 Alluvial Soils
Alluvial soils (alluvium) were encountered in boring B-10 beneath the topsoil and extended approximately 8 feet
below the ground surface. The sampled alluvium was classified as clayey sand (SC), contained trace roots, and was
noted to have an organic odor. The recorded N-values varied from 2 to 3 bpf, indicating a very loose relative
density.
3.3.4 Residual & Possible Residual Soils
Residual soils (residuum) or possible residual soils were encountered beneath the fill in borings B-1, B-4, B-7, B-8,
B-9, B-12, B-13, B-14, and B-17, beneath the alluvium in boring B-10, and beneath the topsoil in borings B-6 and
B-11. In boring B-4, the boring encountered soils that exhibited characteristics of residual soil, however, the soils
also shared resemblance to the fill soils in the stratum above. Therefore, we classified these soils as “possible
residuum” on the Boring Log. Accordingly, the sampled “possible residuum” will also be referred to as “residuum”
throughout the remainder of this report. The residual soils were generally comprised of sandy silt (ML), silty sand
(SM), and elastic silt with sand (MH) with varying amounts mica. The N values recorded in the residual soils
ranged from 4 to 20 bpf, indicating a soft to very stiff consistency for the silt and clay and a very loose to medium
dense relative density for the sands. Borings B-1, B-4, B-6 through B-14, and B-17 terminated in residual soils at
the planned termination depths of 12, 16, or 25 feet.
3.3.5 Subsurface Water
In Phase 1, subsurface water was encountered in 3 of the borings (B-4, B-5, and B-10) at depths ranging from 4.1
feet (24-hour reading in B-10) to 12.6 feet (24-hour reading in boring B-4) below the surface. These depths
correspond to elevations that range from 830.1 to 857.1 feet, respectively, above mean sea level (MSL). In Phase
2, subsurface water was encountered in boring B-14 at a depth of 18 feet below the surface. Please note that
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 7
subsurface water levels will fluctuate during the year, due to such things as seasonal variations, fluctuations in the
creek levels, precipitation, and construction activity in the area.
3.3.6 Laboratory Testing Discussion
As previously discussed in Section 2.0 Exploration and Testing, select split-spoon samples in Phase 1 were
subjected to laboratory testing consisting of moisture content, Atterberg limits, and grain-size distribution (sieve
analysis). The individual test results are included on data sheets in the Appendix and are also summarized in the
table below.
Table 3-1 – Laboratory Test Results
Boring
No.
Sample
Depth
(ft)
USCS
Symbol
Moisture
Content
(%)
Percent
Finer
#200 (%)
LL (%)
PI (%)
B-4 13.5-15 SM 20.0 24.7 40 2
B-8 13.5-15 MH 55.9 73.7 62 9
B-10 3.5-5 SC 24.4 25.4 29 8
4.0 Conclusions and Recommendations
The following presents our geotechnical recommendations regarding construction of the new water line. When
reviewing this information, please remember that the easement and the causeway have been previously graded
and pipe lines have been installed in the same general area in the past. Our experience with sites such as this
indicates that unexpected conditions, such as deposits of unsuitable existing fill, could exist between and near our
borings. Therefore, field engineering evaluations during construction and installation are very important.
The boring data indicates the proposed alignment for the new water line is generally underlain by areas of low to
moderately high consistency existing fill and residual soils. In addition, low consistency alluvium was encountered
in one of the borings (B-10) near one of the creek crossings in Phase 1. Because of the fill and the alluvial soils,
low consistency and unsuitable soils could be encountered near or at the bottom of excavations along the
alignment. The excavation bottoms will need to be thoroughly evaluated for suitability as a working subgrade
and for purposes of pipe bedding. Any alluvial soils encountered during excavation to the pipe installation depth
will be of particular concern, as they are often wet, soft, and compressible. The existing fill soils containing
organics in the causeway boring (B-15 and B-16) are also of concern. Some undercutting and/or stabilization of
low consistency soils beneath the proposed water line should be expected and budgeted, especially near the
creek crossings and within the causeway.
Based on the conditions encountered in our borings, excavation to anticipated subgrade levels is not likely to
encounter PWR or auger refusal material. However, subsurface water was encountered in three of the borings
within Phase 1 following 24 hours from TOB, at depths ranging from only 4.1 to 12.6 feet below the existing
ground surface. These depths correspond to approximate elevations ranging from 830 to 857 feet. Thus, it is
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 8
likely that subsurface water will be encountered during excavation for the new water line near the creek crossings
in Phase 1. Subsurface water was encountered in boring B-14 at a depth of approximately 18 feet. Therefore,
excavations in Phase 2 are not anticipated to encounter subsurface water. However, it should be noted that the
subsurface water levels could have been influenced by rainwater water runoff infiltrating the fill and “perching”
above some of the more consistent or clayey soils.
Based on the boring data, the primary geotechnical considerations for this project are:
• Likelihood of encountering subsurface water during construction in Phase 1 and the need for temporary
dewatering near the creek crossings;
• Potential undercutting of low consistency fill or alluvial soils and stabilization beneath the finished
elevation of the new pipe, especially near the creek crossings and in the causeway; and
• Stability of exposed soils within the open excavation during installation of the new pipe.
Our conclusions and recommendations are based on the project information outlined previously and on the data
obtained from the field-testing program. If the geometry or proposed water line crossing locations or depths are
changed or significantly differ from those outlined, or if conditions are encountered during construction that differ
from those encountered by the soil test borings, S&ME requests the opportunity to review our recommendations
based on the new information and make any necessary changes. In addition, the development and construction
team must understand our recommendations are based on the premise that our representative will be on-site to
observe and document important elements of the construction, including those listed above. Our observations
and testing services can be a vital component in improving the performance and efficiency of the site work.
4.1 Site Preparation
Prior to excavation, stripping of the topsoil along the proposed alignment should be performed to help reduce
the potential of the soils from being mixed with organic materials. Pavement materials should also be removed,
where applicable.
4.2 Excavation
While specific installation depths of the new pipe section have not provided, we anticipate that the new section of
pipe will be installed via cut and cover techniques to depths of up to 15 feet deep in Phase 1 and 10 feet deep in
Phase 2. Based on the borings performed at the site, we anticipate the excavations to install the new pipe sections
will encounter existing fill soils, alluvial soils, and residuum. We anticipate these materials, as well as any newly
placed fill soils, can be excavated using traditional equipment such as heavy backhoes and tracked excavators.
PWR and auger refusal material were not encountered in the borings. However, it must be emphasized that rock
in a weathered, boulder, and mass form varies erratically in depth and location in the Piedmont Physiographic
Province. Such natural materials could be encountered within or below the residuum, beneath the fill, or below
the alluvium between or near the boring locations. If encountered, excavation of PWR will require a heavy tracked
excavator, possibly using a hoe ram attachment, and/or pneumatic tools. We anticipate that due to the proximity
of nearby utilities, blasting would not be permitted.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 9
Because the new water line will be installed between two existing underground utility lines and/or within a
causeway, we do not anticipate the excavations can be sloped back due to the potential damage that could occur
to the existing lines and causeway. Therefore, for the temporary excavation work for installing the new water line,
we expect a series of trench boxes, shoring and/or bracing will be needed to obtain a safe working environment
and preserve the integrity of the existing utility lines. Excavations should be shored in accordance with local, state,
and federal regulations, including OSHA (29 CFR Part 1926) excavation trench safety standards. The contractor is
solely responsible for site safety; this information is provided only as a service and under no circumstances should
we be assumed responsible for construction site safety.
Depending on the Contractor’s means and methods, the excavation work could require the installation of a
retaining system to accommodate the excavations near the existing utilities. If a retaining system is used, it could
consist of sheet piling, or soldier piles (possibly with struts and walers) and lagging. The retaining system will be
highly dependent upon the available working space. We would be happy to provide retaining system design
parameters, if requested.
4.3 Dewatering/Surface Water Considerations
As previously noted, subsurface water was encountered in three of the borings in Phase 1 at relatively shallow
depths. Based on the water levels observed and the expected pipe installation depths, we anticipate that
temporary dewatering measures will be required near the creek crossings in Phase 1.
The means and methods of dewatering and subsurface water control are typically left to the discretion of the
Contractor. However, temporary dewatering can normally be accomplished with temporary excavations and sump
pumps. Pumping from the sumps should be maintained such that the water level is drawn down to a minimum of
3 feet below the bottom of the excavations at all times during installation of the new water line. Pumping must be
maintained continuously from sumps, well points, or wells for any beneficial de-watering to be derived and a
back-up pump should be maintained on-site. Discontinuous pumping will result in softening of the subgrade
soils and the potential need for additional undercutting of bearing level soils.
Control of surface water along the proposed alignment will be very important for this project. Additional
rainwater runoff accumulating in the excavations will significantly increase the amount of dewatering. and could
soften and disturb the bearing materials. Therefore, we recommend that all surfaces at the top of the excavation
be adequately sloped to provide positive drainage as construction progresses. Berms and or french drains could
needed to help divert rainwater runoff depending on the amount of precipitation that occurs during construction.
The contractor should also be prepared to implement additional dewatering techniques should the need arise.
Erosion and sediment control measures such as pumping through silt bags, temporary sediment traps, etc., should
be incorporated into the construction plans.
It should be noted that subsurface water may be encountered at depths different than those measured in the soil
test borings. Water levels tend to fluctuate with seasonal and climatic variations, as well as with some types of
construction operations.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 10
4.4 Pipe Installation
4.4.1 Existing Fill and Alluvial Soils
Undercutting of low consistency existing fill and alluvial soils should be anticipated at the probable pipe bearing
elevations along certain parts of the proposed alignment (especially near creek crossing and along the causeway).
Complete removal of these soils may not be required; over-excavation and replacement with structural fill or
washed stone with the use of geotextiles could potentially reduce the amount of undercut required. The extent
and depth of undercutting should be determined in the field by the Geotechnical Engineer. However, we
anticipate approximately 2 to 3 feet of undercutting will be sufficient in most cases.
4.4.2 Uplift Forces
Uplift or buoyancy forces could be a factor if the pipe sections are installed below a stabilized subsurface water
level. Due to the presence of subsurface water in our borings, there is a potential for uplift loads, especially near
the existing creeks. If the uplift forces are approximately equal to or larger than the weight of the pipe (empty)
and overlying backfill, it will be necessary to anchor the pipe with either a screw or block anchor system. We
recommend a minimum factor of safety of 1.5 be provided against uplift.
4.4.3 Pipe Bedding
The bedding material for the pipes should comply with all requirements of the pipe manufacturer. In areas where
granular bedding is used, it should be placed in not more than 6-inch layers and compacted with hand operated
compactors. In excavations where subsurface water is encountered, we recommend that adequate temporary
dewatering measures be provided to help maintain stable subgrade conditions, as discussed in Section 4.3. It may
be necessary, depending on the actual subsurface conditions , that the excavation bottoms and sides be lined with
a needle punched non-woven filter fabric such as Mirafi 140N, or equivalent, and the granular backfill wrapped in
the fabric to help prevent the infiltration of soil fines into the granular material. Migration of fines into the gravel
bedding could result in softening of subgrade support, the creation of voids, and corresponding subsidence of
these soils. The fabric should be placed in areas where subsurface water is encountered during construction.
If practical, the pipe excavation bottoms should be carefully evaluated by a representative of the Geotechnical
Engineer prior to pipe installation. The evaluations should include shallow hand auger borings and dynamic cone
penetrometer (DCP) tests in the excavation bottoms, as well as probing. These evaluations will help assess
whether the pipe is directly underlain by suitable bearing material. If unsuitable materials are detected, they
should be undercut and replaced with crushed stone or stabilized prior to pipe installation. We anticipate the
stabilization will consist of installing filter fabric (Mirafi 140N or equivalent) and 18 to 36 inches of SCDOT No. 57
crushed stone underneath the pipe. Thicker layers of crushed stone (36 inches) will likely be necessary in areas
where the pipe is underlain by alluvial soils, while thinner layers could be suitable in areas where the pipe is
underlain by low consistency fill or residual soils. Due to the wet conditions near the creek crossings and alluvium
material encountered in one of the borings, some stabilization should be anticipated along the pipe alignment.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 11
4.5 Fill Placement and Compaction
After excavation, undercutting, and stabilization areas requiring fill placement should be raised to their design
subgrade configuration with soil free of deleterious materials, including rock fragments greater than 4 inches in
diameter. The fill should be uniformly spread in 6- to 8-inch-thick loose lifts and be compacted to at least 95
percent of the soil’s maximum dry density, as determined by a laboratory standard Proctor compaction test (ASTM
D-698). Hand-operated compaction equipment should be used directly along sides and above the pipe for an
adequate height to not damage the pipe. The Structural Engineer should determine the safe height. The
moisture content should be controlled at plus to minus 3 percent of optimum; however, a slight increase in
optimum moisture could be allowable if the minimum compacted density is achieved and subgrade is stable.
Closer moisture control could be needed for more silty soils.
Fill placement should be observed by a qualified Materials Technician working under the general direction of the
Geotechnical Engineer. In addition to this visual evaluation, the Technician should perform in-place field density
tests to confirm the required degree of compaction is attained.
4.5.1 Use of Excavated Soils as Fill
Most of the sampled fill and residuum appeared generally adaptable for use as well-compacted structural fill with
proper preparation, removal of organic matter and moisture conditioning. The alluvial soils can potentially be
used; however, they tend to be saturated and difficult to dry prior to placement. All of the excavated soils will
need to be carefully evaluated by a Geotechnical Professional prior to reuse.
The in-situ moisture content of the subsurface soils was generally above optimum for compaction at the time of
our exploration. However, the moisture content of these soils will fluctuate with prevailing weather conditions
prior to and at the time of grading. If any soils are stockpiled for future reuse, they should be protected from
precipitation with plastic sheeting, or at least somewhat compacted during placement and sloped to drain
rainwater runoff. As with any earthwork project, moisture adjustment (wetting or drying) could be required to
achieve the recommended degree of compaction.
4.5.2 Use of Off-Site Borrow Materials as Fill
Although we anticipate it is unlikely, imported fill could potentially be needed for grading purposes on this site.
The imported fill should consist of a clean, low plasticity soil, and be evaluated by a Geotechnical Professional
prior to hauling to the site. Preferably, the standard Proctor maximum dry density of imported soils should be at
least 100 pounds per cubic foot (pcf).
4.5.3 Allowable Bearing Capacity for Site Structures
Based on the boring data and assuming the recommendations provided in the sections above are properly
implemented, a uniform net maximum allowable bearing pressure of 2,000 pounds per square foot (psf) is
available for thrust restraints and other site structures when supported in residual soils or well-compacted fill.
Revised Subsurface Exploration Report
Lake Keowee to Adkins WTP Water Line
Pickens County, South Carolina
S&ME Project No. 1569-20-028
November 19, 2020 12
Due to the fill and alluvial material encountered during our exploration, bearing capacity evaluations are very
important for this site. All excavation bottoms for site structures should be evaluated by a representative of the
Geotechnical Engineer as discussed in Section 4.4.
Some excavations for thrust blocks could require undercutting to penetrate low consistency soils or any unsuitable
fill soils which went undetected during pipe bedding measures.
5.0 Limitations of Report
This report has been prepared in accordance with generally accepted geotechnical engineering practice for
specific application to this project. The conclusions and recommendations in this report are based on the
applicable standards of our practice in this geographic area at the time this report was prepared. No other
warranty, expressed or implied, is made.
We relied on project information given to us to develop our conclusions and recommendations. If project
information described in this report is not accurate, or if it changes during project development, we should be
notified of the changes so that we can modify our recommendations based on this additional information if
necessary.
Our conclusions and recommendations are based on limited data from a field exploration program. Subsurface
conditions can vary widely between explored areas. Some variations may not become evident until construction.
If conditions are encountered which appear different than those described in our report, we should be notified.
This report should not be construed to represent subsurface conditions for the entire water line alignment.
Unless specifically noted otherwise, our field exploration program did not include an assessment of regulatory
compliance, environmental conditions or pollutants, or presence of any biological materials (mold, fungi, bacteria).
If there is a concern about these items, other studies should be performed. S&ME can provide a proposal and
perform these services if requested.
Important Information About Your
Geotechnical Engineering ReportVariations in subsurface conditions can be a principal cause of construction delays, cost overruns and claims.The following information is provided to assist you in understanding and managing the risk of these variations.
Geotechnical Findings Are ProfessionalOpinionsGeotechnical engineers cannot specify materialproperties as other design engineers do.Geotechnical material properties have a far broaderrange on a given site than any manufacturedconstruction material, and some geotechnicalmaterial properties may change over time becauseof exposure to air and water, or human activity.
Site exploration identifies subsurface conditions atthe time of exploration and only at the points wheresubsurface tests are performed or samplesobtained. Geotechnical engineers review field andlaboratory data and then apply their judgment torender professional opinions about site subsurfaceconditions. Their recommendations rely upon theseprofessional opinions. Variations in the vertical andlateral extent of subsurface materials may beencountered during construction that significantlyimpact construction schedules, methods andmaterial volumes. While higher levels of subsurfaceexploration can mitigate the risk of encounteringunanticipated subsurface conditions, no level ofsubsurface exploration can eliminate this risk.
Scope of Geotechnical ServicesProfessional geotechnical engineering judgment isrequired to develop a geotechnical explorationscope to obtain information necessary to supportdesign and construction. A number of uniqueproject factors are considered in developing thescope of geotechnical services, such as theexploration objective; the location, type, size andweight of the proposed structure; proposed sitegrades and improvements; the constructionschedule and sequence; and the site geology.
Geotechnical engineers apply their experience withconstruction methods, subsurface conditions andexploration methods to develop the explorationscope. The scope of each exploration is uniquebased on available project and site information.Incomplete project information or constraints on thescope of exploration increases the risk of variationsin subsurface conditions not being identified andaddressed in the geotechnical report.
Services Are Performed for SpecificProjectsBecause the scope of each geotechnicalexploration is unique, each geotechnical report isunique. Subsurface conditions are explored andrecommendations are made for a specific project.Subsurface information and recommendations maynot be adequate for other uses. Changes in aproposed structure location, foundation loads,grades, schedule, etc. may require additionalgeotechnical exploration, analyses, andconsultation. The geotechnical engineer should beconsulted to determine if additional services arerequired in response to changes in proposedconstruction, location, loads, grades, schedule, etc.
Geo-Environmental IssuesThe equipment, techniques, and personnel used toperform a geo-environmental study differsignificantly from those used for a geotechnicalexploration. Indications of environmentalcontamination may be encountered incidental toperformance of a geotechnical exploration but gounrecognized. Determination of the presence, typeor extent of environmental contamination is beyondthe scope of a geotechnical exploration.
Geotechnical Recommendations Are NotFinalRecommendations are developed based on thegeotechnical engineer’s understanding of theproposed construction and professional opinion ofsite subsurface conditions. Observations and testsmust be performed during construction to confirmsubsurface conditions exposed by constructionexcavations are consistent with those assumed indevelopment of recommendations. It is advisableto retain the geotechnical engineer that performedthe exploration and developed the geotechnicalrecommendations to conduct tests andobservations during construction. This may reducethe risk that variations in subsurface conditions willnot be addressed as recommended in thegeotechnical report.
Portion obtained with permission from “Important Information About Your Geotechnical Engineering Report”, ASFE, 2004© S&ME, Inc. 2010
SCALE:
DATE:
PROJECT NUMBER
FIGURE NO.
1NOT TO SCALE
NOV 2020
1569-20-028
LAKE KEOWEE TO ADKINS WTP WATER LINEPICKENS COUNTY, SOUTH CAROLINA
PHASE 1 BORING LOCATION PLAN
LEGEND
Approximate Boring Location
B-12
B-11B-10
B-9 B-8
B-7
B-6
B-5
B-4
B-3B-2
B-1
NOTE: THE AERIAL PHOTOGRAPH FROM GOOGLE EARTH WAS MODIFIED BY S&ME. DRAWING IS FOR GENERAL INFORMATION ONLY AND SHOULD NOT BE
USED FOR THE MEASUREMENT OR ESTIMATION OF QUANTITIES OR DISTANCES.
B-13
SCALE:
DATE:
PROJECT NUMBER
FIGURE NO.
2NOT TO SCALE
NOV 2020
1569-20-028
LAKE KEOWEE TO ADKINS WTP WATER LINEPICKENS COUNTY, SOUTH CAROLINA
PHASE 2 BORING LOCATION PLAN
LEGEND
Approximate Boring Location
B-14
NOTE: THE AERIAL PHOTOGRAPH FROM GOOGLE EARTH WAS MODIFIED BY S&ME. DRAWING IS FOR GENERAL INFORMATION ONLY AND SHOULD NOT BE USED FOR THE MEASUREMENT OR ESTIMATION OF QUANTITIES OR DISTANCES.
B-15
B-17 B-16
Asphalt
Concrete
Topsoil
HC
LEGEND TO SOIL CLASSIFICATION AND SYMBOLS
Partially WeatheredRock
Cored Rock
(Shown in Water Level Column)
0 to 45 to 1011 to 3031 to 50Over 50
Silt (ML)
Clay (CL, CH)
Sandy Silt (ML)
Clayey Sand (SC)
Clayey Silt (MH)
Organic (OL, OH)
RELATIVE DENSITY
Very LooseLoose
Medium DenseDense
Very Dense
CONSTITUENT MODIFIERS
Trace: <5%Few: 5 to <15%
Little: 15 to <30%Some: 30 to <50%Mostly: 50 to 100%
- Total Length of Rock Recovered in the CoreBarrel Divided by the Total Length of the CoreRun Times 100%.
REC
RQD
TOB
(Shown in Graphic Log)
WATER LEVELS
CONSISTENCY OF COHESIVE SOILS
CONSISTENCY
STD. PENETRATIONRESISTANCEBLOWS/FOOT
Very SoftSoftFirmStiff
Very StiffHard
Very Hard
STD. PENETRATIONRESISTANCEBLOWS/FOOT
RELATIVE DENSITY OF COHESIONLESS SOILS
= Water Level At Termination of Boring
= Water Level Taken After 24 Hours
= Loss of Drilling Water
= Hole Cave
0 to 23 to 45 to 8
9 to 1516 to 3031 to 50Over 50
Fill
Sand (SW, SP)
Silty Sand (SM)
Sandy Clay (CL, CH)
Silty Clay (CL, CH)
Gravel (GW, GM, GP)
SOIL TYPES (USCS CLASSIFICATION)
Shelby Tube
Split Spoon
Rock Core
No Recovery
SAMPLER TYPES
(Shown in Samples Column)
TERMS
StandardPenetrationResistance
- Total Length of Sound Rock SegmentsRecovered that are Longer Than or Equal to 4"(mechanical breaks excluded) Divided by theTotal Length of the Core Run Times 100%.
- Termination of Boring
N.E. - Not Encountered
- The Number of Blows of 140 lb. Hammer Falling30 in. Required to Drive 1.4 in. I.D. Split SpoonSampler 1 Foot. As Specified in ASTM D-1586.
6
8
7
7
4
4
TOPSOIL - 2 inches
FILL: SANDY SILT (ML) - firm, red tan brown,fine to medium, trace large rock fragments inSS-1
- - - Slightly micaceous
RESIDUUM: SANDY SILT (ML) - soft, red tanbrown, fine to medium, some clay, slightlymicaceous to micaceous
Boring terminated at 16 feet
3
4
4
3
2
2
3
3
3
3
2
3
4
3
4
2
2
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
906.2
901.2
896.2
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-1
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 911.2 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825154°19'48"LAT.: 344944°23'24"
8
11
24
35
15
15
TOPSOIL - 2 inches
FILL: SILTY SAND (SM) - loose to mediumdense, red brown tan, fine to coarse, somelarge rock fragments
FILL: SILTY SAND (SM) - medium dense todense, white brown red, fine to coarse, somerock fragments, few large rock fragments
FILL: SANDY SILT (ML) - stiff, red brown tan,fine to coarse, few large rock fragments
Boring terminated at 16 feet
3
6
11
18
6
7
2
3
9
14
6
5
5
13
17
9
8
SS-1
SS-2
SS-3
SS-4
SS-6
SS-7
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
906.3
901.3
896.3
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-2
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 911.3 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825201°48'36"LAT.: 344943°13'12"
12
8
8
9
7
7
TOPSOIL - 3 inches
FILL: SANDY LEAN CLAY (CL) - stiff to firm,red brown tan, fine to coarse
FILL: SANDY SILT (ML) - firm, tan brown red,fine to medium, slightly micaceous, some clay
FILL: SILTY SAND (SM) - loose, tan brownred, fine to coarse, slightly micaceous
Boring terminated at 16 feet
5
4
4
4
3
3
4
3
3
3
3
7
4
4
5
4
4
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
896.7
891.7
886.7
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-3
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 901.7 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825206°53'24"LAT.: 344945°4'48"
8
11
9
11
7
6
TOPSOIL - 3 inches
FILL: SANDY LEAN CLAY (CL) - firm to stiff,red brown, fine to medium, moist
FILL: SILTY SAND (SM) - loose to mediumdense, red brown tan, fine to coarse, slightlymoist, trace rock fragments, slightly micaceous
POSSIBLE RESIDUUM: SILTY SAND (SM) -loose, brown red tan, medium to fine,micaceous
Boring terminated at 16 feet
4
5
4
6
3
3
3
4
4
5
2
4
6
5
5
4
3
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
864.7
859.7
854.7
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-4
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 869.7 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: NE at TOB, 12.6 ft at 24 hrs
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
Temporary piezometer installed on 5/21;
abandoned on 5/27.CAVE-IN DEPTH: N/A
LONG.: -825210°19'48"LAT.: 344946°55'12"
26
4
5
7
13
TOPSOIL - 2 inches
FILL: SILTY SAND (SM) - medium dense,white tan, fine to coarse, some large rockfragments
FILL: SILTY SAND (SM) - loose to mediumdense, white gray red, fine to coarse, slightlymicaceous, moist to very moist
Boring terminated at 12 feet
13
2
2
4
6
7
2
2
3
4
13
2
3
3
7
SS-1
SS-2
SS-3
SS-4
SS-5
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
836.5
831.5
5
10
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-5
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 841.5 ft
BORING DEPTH: 12.0 ft
WATER LEVEL: 9 ft at TOB, 11.4 ft at 24 hrs
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
Temporary piezometer installed on 5/21;
abandoned on 5/27.CAVE-IN DEPTH: N/A
LONG.: -825214°33'0"LAT.: 344949°4'12"
8
13
6
6
6
6
TOPSOIL - 2 inches
RESIDUUM: SANDY LEAN CLAY (CL) - firmto stiff, red brown, fine to medium, slightlymicaceous, slightly moist
SANDY SILT (ML) - firm, red brown tan, fine tomedium, slightly micaceous, slightly moist
Boring terminated at 16 feet
4
5
3
3
3
3
3
4
3
2
2
4
8
3
3
3
3
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
875.7
870.7
865.7
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-6
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 880.7 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825219°8'24"LAT.: 344951°19'12"
14
21
10
13
13
11
TOPSOIL - 2 inches
FILL: SANDY LEAN CLAY (CL) - stiff to verystiff, red brown, fine to medium, moist in SS-3and SS-4
RESIDUUM: SANDY SILT (ML) - stiff, redbrown tan, fine to coarse, slightly micaceous
Boring terminated at 16 feet
6
10
4
5
5
2
4
5
3
3
3
8
11
6
8
8
9
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
HC
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
871.6
866.6
861.6
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-7
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 876.6 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: NE at TOB; NE at 24 hrs
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: 12.6'
LONG.: -825225°1'48"LAT.: 344952°34'12"
5
5
9
15
4
5
TOPSOIL - 1 inch
FILL: SANDY LEAN CLAY (CL) - firm to stiff,brown red tan, fine to medium, trace rockfragments, moist
RESIDUUM: ELASTIC SILT WITH SAND(MH) - soft, red brown, fine to medium, moist,slightly micaceous
Boring terminated at 16 feet
3
2
4
6
2
2
2
2
4
3
2
3
5
9
2
3
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
878.5
873.5
868.5
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-8
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 883.5 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825230°52'12"LAT.: 344953°59'24"
5
6
7
8
5
5
TOPSOIL - 1 inch
FILL: SILTY SAND (SM) - loose, red browntan, fine to coarse, trace rock fragments
RESIDUUM: SANDY SILT (ML) - firm, red tanbrown, fine to coarse, trace rock fragments,layer of silty sand
Boring terminated at 16 feet
2
3
3
4
2
2
2
3
2
2
3
3
3
4
4
3
3
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
896.6
891.6
886.6
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-9
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 901.6 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825235°1'12"LAT.: 344953°37'48"
2
3
3
4
6
TOPSOIL - 2 inches
ALLUVIUM: CLAYEY SAND (SC) - very loose,gray, fine to coarse, trace roots, organic odor,wet
RESIDUUM: SILTY SAND (SM) - very looseto loose, brown red white, fine to coarse, tracerock fragments, slightly micaceous, wet
Boring terminated at 12 feet
1
1
2
2
3
WOH
1
1
2
2
1
2
1
2
3
SS-1
SS-2
SS-3
SS-4
SS-5
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
850.0
845.0
5
10
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-10
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 855.0 ft
BORING DEPTH: 12.0 ft
WATER LEVEL: 8 ft at TOB, 4.1 ft at 24 hrs
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
Temporary piezometer installed on 5/21;
abandoned on 5/27.CAVE-IN DEPTH: N/A
LONG.: -825239°28'12"LAT.: 344952°31'12"
7
7
6
4
8
7
TOPSOIL - 1 inch
RESIDUUM: SANDY SILT (ML) - firm to soft,brown red tan, fine to coarse
SILTY SAND (SM) - loose, brown tan, fine tocoarse
Boring terminated at 16 feet
3
3
3
2
3
3
2
3
2
2
2
4
4
3
2
5
4
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
890.3
885.3
880.3
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-11
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 895.3 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825243°46'48"LAT.: 344951°39'36"
4
5
6
4
7
6
TOPSOIL - 2 inches
FILL: SANDY SILT (ML) - soft to firm, tan redbrown, fine to coarse
RESIDUUM: SANDY SILT (ML) - soft to firm,brown tan red, fine to coarse, trace rockfragments
Boring terminated at 16 feet
2
2
3
2
3
3
1
2
2
2
3
2
3
3
2
4
3
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
902.9
897.9
892.9
5
10
15
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-12
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 5/21/20
DRILL RIG: CME 550
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 907.9 ft
BORING DEPTH: 16.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from ACAD 2020-28.dwg and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825244°48'0"LAT.: 344951°28'48"
5
5
6
6
9
14
20
TOPSOIL - 1 inch
FILL: SILTY SAND (SM) - loose, brown red,
fine to coarse, trace roots, slightly micaceous
RESIDUUM: SANDY SILT (ML) - firm to stiff,brown red white, fine to coarse, slightlymicaceous
SILTY SAND (SM) - medium dense, brownwhite, fine to coarse
Boring terminated at 25 feet
3
2
3
3
4
6
10
2
2
3
2
2
4
9
2
3
3
3
5
8
10
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
SS-7
HC
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
901.0
896.0
891.0
886.0
881.0
5
10
15
20
25
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-13
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 11/10/20
DRILL RIG: CME 55
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 906.0 ft
BORING DEPTH: 25.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from Google Earth and should be
considered approximate.
CAVE-IN DEPTH: 23'
LONG.: -825245°19'48"LAT.: 344951°30'36"
9
14
10
13
5
5
10
ASPHALT - 2 inches
CRUSHED STONE - 2 inches
FILL: SANDY LEAN CLAY (CL) - stiff, red brown tan, fine to coarse, large rock fragments in SS-1, some rock fragments in SS-2 and SS-3
RESIDUUM: SANDY SILT (ML) - stiff, redbrown, fine to medium
SANDY SILT (ML) - firm, black red brown, fineto medium, micaceous, slightly moist
SILTY SAND (SM) - loose, white red brown,fine to coarse, moist, few rock fragments
Boring terminated at 25 feet
4
7
5
6
2
2
5
3
5
5
4
2
2
2
5
7
5
7
3
3
5
SS-1
SS-2
SS-3
SS-4
SS-5
SS-6
SS-7
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
813.0
808.0
803.0
798.0
793.0
5
10
15
20
25
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-14
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 11/10/20
DRILL RIG: CME 55
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 818.0 ft
BORING DEPTH: 25.0 ft
WATER LEVEL: 18 ft at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from Google Earth and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825317°54'0"LAT.: 344933°50'60"
7
12
13
9
26
ASPHALT - 2 inches
FILL: SANDY LEAN CLAY (CL) - firm to stiff,red brown, fine to medium, trace roots in SS-3and SS-4, trace rock fragments, large rockfragment in SS-4.
FILL: SANDY LEAN CLAY (CL) - very stiff, redbrown, fine, trace roots, organic stain and odor
Boring terminated at 12 feet
4
6
6
4
4
3
5
4
3
3
3
6
7
5
22
SS-1
SS-2
SS-3
SS-4
SS-5
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
803.0
798.0
5
10
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-15
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 11/10/20
DRILL RIG: CME 55
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 808.0 ft
BORING DEPTH: 12.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from Google Earth and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825320°50'60"LAT.: 344933°54'0"
7
6
7
10
11
ASPHALT - 3 inches
CRUSHED STONE - 1 inch
FILL: SANDY LEAN CLAY (CL) - firm to stiff,red brown tan, fine to medium, trace roots,organic stain and odor in SS-4 and SS-5
Boring terminated at 12 feet
3
3
3
4
4
2
3
4
3
2
4
3
4
6
7
SS-1
SS-2
SS-3
SS-4
SS-5
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
800.0
795.0
5
10
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-16
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 11/10/20
DRILL RIG: CME 55
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 805.0 ft
BORING DEPTH: 12.0 ft
WATER LEVEL: Not Encountered at TOB
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from Google Earth and should be
considered approximate.
CAVE-IN DEPTH: N/A
LONG.: -825324°30'0"LAT.: 344935°7'12"
6
9
7
9
10
TOPSOIL - 1 inch
FILL: SANDY LEAN CLAY (CL) - firm to stiff,red brown, fine to medium, trace roots, tracerock fragments
RESIDUUM: SILTY SAND (SM) - loose, redbrown white, fine to coarse
Boring terminated at 12 feet
2
4
2
3
5
3
3
3
2
5
4
5
5
6
5
SS-1
SS-2
SS-3
SS-4
SS-5
GR
AP
HIC
LO
G
N V
AL
UE
DE
PT
H
(fe
et)
THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
BORING, SAMPLING AND PENETRATION TEST DATA IN GENERALACCORDANCE WITH ASTM D-1586.
STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
NOTES:
FINES %
10 20 30 40 50 60 70 80 90
PL LLNM
SPT N-Value (bpf)
804.0
799.0
5
10
2nd
6in
/ RE
C
3rd
6in
/ RQ
D
SA
MP
LE
TY
PE
SA
MP
LE
NO
.
1st 6
in /
RU
N #
BLOW COUNT/ CORE DATA
EL
EV
AT
ION
(fe
et)
WA
TE
R L
EV
EL
MATERIAL DESCRIPTION
BORING LOG B-17
1.
2.
3.
4.
Page 1 of 1
S&
ME
BO
RIN
G L
OG
- V
OG
TL
E
15
69
-20
-02
8 L
AK
E K
EO
WE
E W
AT
ER
LIN
E B
OR
ING
LO
GS
.GP
J
S&
ME
20
09
_0
9_
24
.GD
T
11
/18
/20
PROJECT: Lake Keowee to Adkins WTP Water LinePickens County, South Carolina
S&ME Project No. 1569-20-028
CLIENT: Brown & Caldwell
DATE DRILLED: 11/10/20
DRILL RIG: CME 55
DRILLER: Independence Drilling, Inc.
HAMMER TYPE: Automatic
SAMPLING METHOD: Split spoon
DRILLING METHOD: 2¼" H.S.A.
ELEVATION: 809.0 ft
BORING DEPTH: 12.0 ft
WATER LEVEL: Not Encountered at 24 hrs
LOGGED BY: J. Titus
NOTES: Elevations and coordinates were
estimated from Google Earth and should be
considered approximate.
Temporary piezometer installed on 11/10;
abandoned on 11/17.CAVE-IN DEPTH: N/A
LONG.: -825326°21'36"LAT.: 344935°9'36"
Field Testing Procedures
Soil Test Borings
The boring and sampling were conducted in accordance with ASTM D-1586-11 test method. Initially, the boring
was advanced by mechanically augering through the overburden soils. When necessary, a heavy drilling fluid is
used below the water table to stabilize the sides and bottom of the borehole. At regular intervals, soil samples
were obtained with a standard 1.4-inch I.D., 2-inch O.D., split-barrel or split-spoon sampler. The sampler was first
seated 6 inches to penetrate any loose cuttings and then driven an additional foot with blows of a 140-pound
hammer falling 30 inches. The number of hammer blows required to drive the sampler the final foot is designated
as the "Standard Penetration Resistance" or N-value. The penetration resistance, when properly evaluated, can be
correlated to consistency, relative density, strength and compressibility of the sampled soils.
When performing the Standard Penetration Test with a conventional safety hammer and cathead, a portion of the
energy of the falling weight is lost due to the resistance of the rope on the cathead. An automatic hammer is a
hydraulic/mechanical tool that raises and cleanly releases the weight when performing the Standard Penetration
Test, resulting in more of the energy of the falling weight being applied to the rods. The conventional rope and
cathead safety hammers delivers about 60% of the theoretical energy delivered by a 140-pound hammer free-
falling 30 inches. N-values obtained through the safety hammer and cathead are commonly termed N60.
Research conducted by Seed et al., 1984, has developed correlation factors for the use of hammers other than the
safety hammer and cathead. To correlate automatic hammer N-values (Nauto hammer) to N60 values, the equation is:
N60 = Nauto hammer * Ce, where Ce is 1.3 to 1.4 for the automatic hammers used on this project.
Water Level Readings
A water level reading is normally taken in conjunction with boring and is recorded on the Boring Logs following
termination of drilling. This reading indicates the approximate location of the hydrostatic water table at the time
of our field exploration. The groundwater table may be dependent upon the amount of precipitation at the site
during a particular period of time. Fluctuations in the water table should also be expected with variations in
surface run-off, evaporation, construction activity and other factors.
Occasionally the boreholes sides will cave, preventing the water level readings from being obtained or trapping
drilling water above the cave-in zone. In these instances, the hole cave-in depth (designated by HC) is measured
and recorded on the Boring Logs. Water level readings taken during the field operations do not provide
information on the long-term fluctuations of the water table. When this information is required, piezometers are
installed to prevent the boreholes from caving.
Oven ID. 13978 Calibration Date: 10/07/19
LABORATORY DETERMINATION OF
WATER CONTENT
B-10
Method: A (1%)
ft.
SS-2 3.5 - 5'
AASHTO T 265ASTM D 2216
Tare Wt. +
Dry Wt
Balance ID.
13.5 - 15' YM-1 94.06 254.81 228.03
Brown and Caldwell
S&ME Sample Date(s):
B (0.1%)
26.78
gramsgrams
D-4
Form No: TR-D2216-T265-1
Revision No. 1
Revision Date: 08/16/17
250 Berryhill Road, Suite 104 Columbia, SC 29210
Sampling Method: Split-spoon
Boring
No.
B-4
6/10/20
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
Brian Vaughan, P.E.
DateSignature
Group Leader
PositionTechnical Responsibility
Benjamin Kovaleski
ASTM D 2216: Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
Notes / Deviations / References
Test Date(s):
grams grams
20.0%
13942 Calibration Date: 9/10/19
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
SS-5
%
Percent
Moisture
6/04 - 6/05/20Project Name: Lake Keowee to Adkins WTP Water Line
Tare Wt.+
Wet Wt
Sample
Depth
Tare # Tare WeightSample
No.
Water
Weight
Sampled by:
Client Name:
Client Address:
285.66 247.44 38.22
59.13B-8
Certification Type / No. DateTechnician Name
5/21/20
Project #: 1569-20-028 Report Date: 6/10/20
90.55
SS-5 13.5 - 15' YM-2 90.97 255.88
24.4%
55.9%196.75
6/10/20
N
o
t
e
NICET Lab Level III / 117226
S&ME, Inc. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-4_B-8_B-10 (Moisture Content).xlsm
Page 1 of 2
Moisture Content
24.7%
2
o
Medium Sand 37.6%0.6%
Hard & Durable x
Angular
Weathered & Friable
Description of Sand & Gravel Particles: Rounded
Medium Sand
38
8.636
Coarse Sand
Gravel
Liquid Limit 40
5/21/20
Plastic Index
Position
37.1%
20.0%
Fine Sand
Group Leader
o x
Fine Sand
Silt & Clay
SIEVE ANALYSIS OF SOILS
Coarse Sand
Clay < 0.005 mm
0.6%
Colloids < 0.001 mm
Plastic Limit
6/10/20Brian Vaughan, P.E.
Notes / Deviations / References:
Technical Responsibility Signature Date
oSoft
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
0.0%
Specific Gravity 2.650 Cc = 0.003 Cu =
2.00 mm
< 2.00 mm and > 0.425 mm (#40)
Coarse Sand < 4.75 mm and >2.00 mm (#10)
Lake Keowee to Adkins WTP Water Line
250 Berryhill Road, Suite 104 Columbia, SC 29210
SILTY SAND (SM) - brown red tan, medium to fine, micaceous
Depth:Split-spoon
Project Name:
Boring #:
Medium Sand
Maximum Particle Size
Sample Date:
6/10/20
SS-5 13.5 - 15'
Sample Description:
Type:Sample #:
Project #:
Client Address:
Test Date(s):
Report Date:1569-20-028
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
6/04 - 6/10/20
Form No: TR-D422-WH-1Ga
Revision No. 1
< 75 mm and > 4.75 mm (#4) Silt < 0.075 and > 0.005 mmGravel
Brown and Caldwell
62gB-4 Log #:
Client Name:
Revision Date: 8/10/17
ASTM D 422
Cobbles < 300 mm (12") and > 75 mm (3")
37.1%
37.6%
Fine Sand < 0.425 mm and > 0.075 mm
3" 1.5" 1"3/4" 3/8" #4 #10 #20 #40 #60 #100 #200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.010.101.0010.00100.00
Per
cen
t P
ass
ing
(%
)
Millimeters
S&ME, Inc. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-4 SS-5 (13.5-15') Grain.xlsx
Page 1 of 1
A
B
C
D
E
F
N
LL
25
0.974
28
27
26 1.005
1.014
2.00
33.93
5.26 4.48
15
38.1%
23119
SILTY SAND (SM) - brown red tan, medium to fine, micaceous
Report Date:
Sample Date:
44.1%
11.71
Plastic Limit
38.2%
1.71
33.81
26.68 26.70 26.67
38.50
23
41.1%
11.24
39.86
36.20
5.16
31.93
38.0%
LL Apparatus 23158
12
10/7/2019
Liquid LimitPan #
Tare #: 11 13 14
Oven 13978
2/1/2020
29 1.018
1.009
N
20
21
22
N Factor
23
Factor
0.979
0.985
0.99
24
% Passing the #200 Sieve:
1.000
NP, Non-Plastic
Benjamin J. Kovaleski
Air Dried
6/10/20
Notes / Deviations / References:
24.7%
ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
SM
40
38
30 1.022
Liquid Limit
o
2
Group Symbol
Plastic Limit
One-point Method
15
26.79
4.62
42.56
Plastic Index
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
6/10/20Technical Responsibility Date
Ave. Average
Wet Preparation Dry Preparation
Technician Name Date
Multipoint Method
0.995
Tare Weight
32.10
27.62
Moisture Contents determined by
ASTM D 2216
3.66
# OF DROPS
% Moisture (D/E)*100 38.4%
30
Dry Soil Weight (C-A)
LL = F * FACTOR
9.52
Wet Soil Weight + A
Dry Soil Weight + A
Water Weight (B-C)
37.94
43.66
Lake Keowee to Adkins WTP Water Line Test Date: 6/09/20
S&ME ID #
10/15/2019
62g
Balance (0.01 g)
B-4 Log #:
Type:
5/21/20
9/10/2019 Grooving tool 13942
1569-20-028
Depth:SS-5 13.5 - 15'
o
S&ME ID # Cal Date:
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
Sample Description:
6/10/20
250 Berryhill Road, Suite 104 Columbia, SC 29210Client Address:
Client Name:
Cal Date: Type and Specification
Split-spoonSample #:
Boring #:
Type and Specification
Brown and Caldwell
AASHTO T 90x o
Revision Date: 7/26/17
Revision No. 1
Project #:
Project Name:
ASTM D 4318 AASHTO T 89
One Point Liquid Limit
LIQUID LIMIT, PLASTIC LIMIT,
& PLASTIC INDEX
Form No. TR-D4318-T89-90
15 20 25 30 35 40
30.0
35.0
40.0
45.0
50.0
10 100
% M
ois
ture
Co
nte
nt
# of Drops
S&ME, INC. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-4 SS-5 (13.5-15') PI.xlsx
Page 1 of 1
Moisture Content
73.7%
9
o
Medium Sand 20.9%0.2%
Hard & Durable x
Angular
Weathered & Friable
Description of Sand & Gravel Particles: Rounded
Medium Sand
53
8.636
Coarse Sand
Gravel
Liquid Limit 62
5/21/20
Plastic Index
Position
5.2%
55.9%
Fine Sand
Group Leader
o x
Fine Sand
Silt & Clay
SIEVE ANALYSIS OF SOILS
Coarse Sand
Clay < 0.005 mm
0.2%
Colloids < 0.001 mm
Plastic Limit
6/10/20Brian Vaughan, P.E.
Notes / Deviations / References:
Technical Responsibility Signature Date
oSoft
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
0.0%
Specific Gravity 2.650 Cc = 0.003 Cu =
2.00 mm
< 2.00 mm and > 0.425 mm (#40)
Coarse Sand < 4.75 mm and >2.00 mm (#10)
Lake Keowee to Adkins WTP Water Line
250 Berryhill Road, Suite 104 Columbia, SC 29210
ELASTIC SILT WITH SAND (MH) - red brown, fine, slightly micaceous
Depth:Split-spoon
Project Name:
Boring #:
Medium Sand
Maximum Particle Size
Sample Date:
6/10/20
SS-5 13.5 - 15'
Sample Description:
Type:Sample #:
Project #:
Client Address:
Test Date(s):
Report Date:1569-20-028
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
6/04 - 6/10/20
Form No: TR-D422-WH-1Ga
Revision No. 1
< 75 mm and > 4.75 mm (#4) Silt < 0.075 and > 0.005 mmGravel
Brown and Caldwell
62gB-8 Log #:
Client Name:
Revision Date: 8/10/17
ASTM D 422
Cobbles < 300 mm (12") and > 75 mm (3")
5.2%
20.9%
Fine Sand < 0.425 mm and > 0.075 mm
3" 1.5" 1"3/4" 3/8" #4 #10 #20 #40 #60 #100 #200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.010.101.0010.00100.00
Per
cen
t P
ass
ing
(%
)
Millimeters
S&ME, Inc. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-8 SS-5 (13.5-15') Grain.xlsx
Page 1 of 1
A
B
C
D
E
F
N
LL
25
0.974
28
27
26 1.005
1.014
2.17
33.06
4.05 3.96
10
53.3%
23119
ELASTIC SILT WITH SAND (MH) - red brown, fine, slightly micaceous
Report Date:
Sample Date:
64.4%
9.09
Plastic Limit
53.0%
2.10
32.82
27.78 26.27 26.84
36.44
26
61.7%
9.48
42.08
36.80
5.85
30.89
53.6%
LL Apparatus 23158
7
10/7/2019
Liquid LimitPan #
Tare #: 6 8 9
Oven 13978
2/1/2020
29 1.018
1.009
N
20
21
22
N Factor
23
Factor
0.979
0.985
0.99
24
% Passing the #200 Sieve:
1.000
NP, Non-Plastic
Benjamin J. Kovaleski
Air Dried
6/10/20
Notes / Deviations / References:
73.7%
ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
MH
62
53
30 1.022
Liquid Limit
o
9
Group Symbol
Plastic Limit
One-point Method
20
27.35
5.85
41.60
Plastic Index
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
6/10/20Technical Responsibility Date
Ave. Average
Wet Preparation Dry Preparation
Technician Name Date
Multipoint Method
0.995
Tare Weight
30.72
26.76
Moisture Contents determined by
ASTM D 2216
5.28
# OF DROPS
% Moisture (D/E)*100 58.5%
35
Dry Soil Weight (C-A)
LL = F * FACTOR
9.02
Wet Soil Weight + A
Dry Soil Weight + A
Water Weight (B-C)
35.75
42.29
Lake Keowee to Adkins WTP Water Line Test Date: 6/09/20
S&ME ID #
10/15/2019
62g
Balance (0.01 g)
B-8 Log #:
Type:
5/21/20
9/10/2019 Grooving tool 13942
1569-20-028
Depth:SS-5 13.5 - 15'
o
S&ME ID # Cal Date:
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
Sample Description:
6/10/20
250 Berryhill Road, Suite 104 Columbia, SC 29210Client Address:
Client Name:
Cal Date: Type and Specification
Split-spoonSample #:
Boring #:
Type and Specification
Brown and Caldwell
AASHTO T 90x o
Revision Date: 7/26/17
Revision No. 1
Project #:
Project Name:
ASTM D 4318 AASHTO T 89
One Point Liquid Limit
LIQUID LIMIT, PLASTIC LIMIT,
& PLASTIC INDEX
Form No. TR-D4318-T89-90
15 20 25 30 35 40
52.0
57.0
62.0
67.0
72.0
10 100
% M
ois
ture
Co
nte
nt
# of Drops
S&ME, INC. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-8 SS-5 (13.5-15') PI.xlsx
Page 1 of 1
32.4%
26.8%
Fine Sand < 0.425 mm and > 0.075 mm
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
6/04 - 6/10/20
Form No: TR-D422-WH-1Ga
Revision No. 1
< 75 mm and > 4.75 mm (#4) Silt < 0.075 and > 0.005 mmGravel
Brown and Caldwell
62gB-10 Log #:
Client Name:
Revision Date: 8/10/17
ASTM D 422
Cobbles < 300 mm (12") and > 75 mm (3")
Sample Date:
6/10/20
SS-2 3.5 - 5'
Sample Description:
Type:Sample #:
Project #:
Client Address:
Test Date(s):
Report Date:1569-20-028
19.0 mm
< 2.00 mm and > 0.425 mm (#40)
Coarse Sand < 4.75 mm and >2.00 mm (#10)
Lake Keowee to Adkins WTP Water Line
250 Berryhill Road, Suite 104 Columbia, SC 29210
CLAYEY SAND (SC) - gray, fine to medium with some gravel
Depth:Split-spoon
Project Name:
Boring #:
Medium Sand
Maximum Particle Size
13.0%
Specific Gravity 2.650 Cc = 0.003 Cu =
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
6/10/20Brian Vaughan, P.E.
Notes / Deviations / References:
Technical Responsibility Signature Date
oSoft
5/21/20
Plastic Index
Position
32.4%
24.4%
Fine Sand
Group Leader
o x
Fine Sand
Silt & Clay
SIEVE ANALYSIS OF SOILS
Coarse Sand
Clay < 0.005 mm
2.3%
Colloids < 0.001 mm
Plastic Limit
Moisture Content
25.4%
8
o
Medium Sand 26.8%2.3%
Hard & Durable x
Angular
Weathered & Friable
Description of Sand & Gravel Particles: Rounded
Medium Sand
21
8.636
Coarse Sand
Gravel
Liquid Limit 29
3" 1.5" 1"3/4" 3/8" #4 #10 #20 #40 #60 #100 #200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.010.101.0010.00100.00
Per
cen
t P
ass
ing
(%
)
Millimeters
S&ME, Inc. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-10 SS-2 (3.5-5') Grain.xlsx
Page 1 of 1
A
B
C
D
E
F
N
LL
25
LIQUID LIMIT, PLASTIC LIMIT,
& PLASTIC INDEX
Form No. TR-D4318-T89-90
One Point Liquid Limit
Revision Date: 7/26/17
Revision No. 1
Project #:
Project Name:
ASTM D 4318 AASHTO T 89
1569-20-028
Depth:SS-2 3.5 - 5'
o
S&ME ID # Cal Date:
S&ME, Inc. - Greenville 48 Brookfield Oaks Dr., Suite F Greenville, SC 29607
Sample Description:
6/10/20
250 Berryhill Road, Suite 104 Columbia, SC 29210Client Address:
Client Name:
Cal Date: Type and Specification
Split-spoonSample #:
Boring #:
Type and Specification
Brown and Caldwell
AASHTO T 90x o
Lake Keowee to Adkins WTP Water Line Test Date: 6/09/20
S&ME ID #
10/15/2019
62g
Balance (0.01 g)
B-10 Log #:
Type:
5/21/20
9/10/2019 Grooving tool 13942
Tare Weight
32.26
26.96
Moisture Contents determined by
ASTM D 2216
3.43
# OF DROPS
% Moisture (D/E)*100 26.9%
35
Dry Soil Weight (C-A)
LL = F * FACTOR
12.73
Wet Soil Weight + A
Dry Soil Weight + A
Water Weight (B-C)
40.41
39.63
Ave. Average
Wet Preparation Dry Preparation
Technician Name Date
Multipoint Method
0.995
Plastic Index
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
6/10/20Technical Responsibility Date
26.33
4.02
44.43
15
24
% Passing the #200 Sieve:
1.000
NP, Non-Plastic
Benjamin J. Kovaleski
Air Dried
6/10/20
Notes / Deviations / References:
25.4%
ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
SC
29
21
30 1.022
Liquid Limit
o
8
Group Symbol
Plastic Limit
One-point Method
29 1.018
1.009
N
20
21
22
N Factor
23
Factor
0.979
0.985
0.99
LL Apparatus 23158
2
10/7/2019
Liquid LimitPan #
Tare #: 1 3 4
Oven 13978
2/1/2020
26.70 26.50 25.91
36.32
25
28.9%
13.91
42.86
39.43
3.31
31.96
21.2%33.1%
9.99
Plastic Limit
21.1%
1.12
33.38
0.974
28
27
26 1.005
1.014
1.28
33.24
6.05 5.30
5
21.2%
23119
CLAYEY SAND (SC) - gray, fine to medium with some gravel
Report Date:
Sample Date:
15 20 25 30 35 40
19.0
24.0
29.0
34.0
39.0
10 100
% M
ois
ture
Co
nte
nt
# of Drops
S&ME, INC. - Corporate 3201 Spring Forest Road
Raleigh, NC. 27616
B-10 SS-2 (3.5-5') PI.xlsx
Page 1 of 1