third quarter meeting presentation temporary steam plant

32
Temporary Steam Plant Guidelines Presented by Jack Muscia Rental Business Development Manager Indeck Power Equipment Company

Upload: vominh

Post on 02-Jan-2017

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Third Quarter Meeting Presentation Temporary Steam Plant

Temporary Steam Plant Guidelines

Presented by Jack Muscia

Rental Business Development Manager Indeck Power Equipment Company

Page 2: Third Quarter Meeting Presentation Temporary Steam Plant

Are You Prepared for Possible Steam Interruptions?

•  Management expects 24/7 operations.

•  Do you have contingency plans in place?

•  Do you have temporary tie-ins installed?

•  Is the equipment provider located in Illinois?

Page 3: Third Quarter Meeting Presentation Temporary Steam Plant

Hospitals Require the Services with no Interruption…

•  Sterilization •  Humidification •  Heating •  Hot Water

Page 4: Third Quarter Meeting Presentation Temporary Steam Plant

Some of the Reasons for a Temporary Steam Plant are

Unplanned Outages

Planned Outages

Winter Loads

Delays Bringing

New Plant On-line

Page 5: Third Quarter Meeting Presentation Temporary Steam Plant

A Typical Unplanned Outage

•  Reason: Emergency Boiler Rental •  Capacity: (4) 70,000 PPH •  Type: Trailer-Mounted Boilers •  Design Pressure: 350 psi •  Burner: Low NOx

Page 6: Third Quarter Meeting Presentation Temporary Steam Plant

A Planned Outage Example

•  Reason: Continuous Operations •  Capacity: (4) 75,000 PPH •  Type: Trailer-Mounted Boilers •  Design Pressure:750psi/750F

Page 7: Third Quarter Meeting Presentation Temporary Steam Plant

Temporary Steam Plant Planning Stages

•  Capacity •  Operating pressure •  Steam temp

(saturated or superheat)

•  Fuel type

•  1 month •  3 month •  6 month •  12 month plus

•  Weekday vs. weekend

•  Winter vs. summer months

•  Holiday vs. non-holiday

Page 8: Third Quarter Meeting Presentation Temporary Steam Plant

Delivery Timing - Winter Shipment

(1) 60,000 PPH trailer-mounted watertube boiler being shipped for temporary process steam.

Page 9: Third Quarter Meeting Presentation Temporary Steam Plant

Next Steps in the Planning Stages

•  Boiler Placement •  treated feedwater •  Boiler chemicals •  Electrical & Fuel •  Steam •  Blow downs •  Instrument air

•  Varies with AQMD •  Permit to construct •  Permit to operate

•  Permit details: - timing - cost - source test - variances

Page 10: Third Quarter Meeting Presentation Temporary Steam Plant

Final Planning Stages

•  Review and implement a HAZOP procedure

•  Request descriptions and drawings from equipment supplier

•  Ideal to Implement a Master Agreement Program between Lessor & Lessee

Page 11: Third Quarter Meeting Presentation Temporary Steam Plant
Page 12: Third Quarter Meeting Presentation Temporary Steam Plant

•  Deaerators •  Feedwater Pumps •  Demineralizers, Water

Softeners, Chemical FS

•  Blowdown Tanks •  Diesel Generators •  Valves •  Controls

Planning Stages - Equipment Offerings

Page 13: Third Quarter Meeting Presentation Temporary Steam Plant

Auxiliary Equipment

Water Softeners

Deaerators Economizers

Page 14: Third Quarter Meeting Presentation Temporary Steam Plant

Planning Stages – Boiler Types

Page 15: Third Quarter Meeting Presentation Temporary Steam Plant

Complete Mobile Steam Plants

•  System Components: firetube boiler, feed system, water softener, and blowdown separator

•  Steam Flows: 8,625 PPH to 10,500 PPH (250/300 BHP)

•  Pressure: 15 psig to 250 psig

Page 16: Third Quarter Meeting Presentation Temporary Steam Plant

Mobile Boiler: Drawing

Page 17: Third Quarter Meeting Presentation Temporary Steam Plant

Saturated Watertube Trailers

•  Steam Flows: 24,000 PPH to 80,000 PPH

•  Pressure: 125 psig to 750 psig

Page 18: Third Quarter Meeting Presentation Temporary Steam Plant

20-40-60-75,000 PPH Watertube Boilers

Page 19: Third Quarter Meeting Presentation Temporary Steam Plant

40,000 PPH Rental Boiler: Drawing

Page 20: Third Quarter Meeting Presentation Temporary Steam Plant

Qualifying a Rental Boiler Company

How long have they been in business?

Types of boilers offered?

Where is service support out of?

Availability and when can they deliver?

Rental term / duration (price points)?

Page 21: Third Quarter Meeting Presentation Temporary Steam Plant

Qualifying a Rental Boiler Company

Ask for references?

What is condition of the rental boiler?

Do they offer ancillary equipment?

What’s required from Lessee to obtain a boiler rental?

Page 22: Third Quarter Meeting Presentation Temporary Steam Plant

What’s Required to Rent ?

Purchase Order

Signed Contract

& Insurance Certificate

Rental Monies

& Security Deposit

Boiler Rental

Page 23: Third Quarter Meeting Presentation Temporary Steam Plant

Lessee/Lessor Scope

Purchase Order: Lessee

Signed Lease Rental Agreement: Lessee / Lessor

Certificate of Insurance: Lessee

Tax exemption or resale certificates: Lessee

Freight arrangements / O & M manual: Lessor

Coordinate start-up service: Lessee / Lessor

Other installation and operating requirements: Lessee

Future: Implement a Master Rental Agreement between Lessee / Lessor

Page 24: Third Quarter Meeting Presentation Temporary Steam Plant

Common Questions

How long since the boiler was last inspected and tested?

When do rental charges begin and end?

What equipment and supplies are included in rental charges?

Do start up charges apply?

Certificates of Insurance?

Page 25: Third Quarter Meeting Presentation Temporary Steam Plant

Common Questions (continued)

Who provides the oil pump / tanks?

Who supplies the gas regulator?

Who provides the smokestacks / EPA ports?

Who pays the freight?

Who makes freight arrangements?

Page 26: Third Quarter Meeting Presentation Temporary Steam Plant

Common Questions (continued)

Who provides the hookup?

Who supplies the utilities?

What about feedwater treatment?

How should boilers be operated?

How about disconnecting?

How is boiler to be prepared for shipment?

Loading / unloading preparations?

Page 27: Third Quarter Meeting Presentation Temporary Steam Plant

Final Common Questions (continued)

Heat tracing and insulation?

What is shipped loose for field-installation?

Page 28: Third Quarter Meeting Presentation Temporary Steam Plant

Heat Tracing and Insulation

•  Drum heads – insulated

•  Feedwater piping – heat traced and insulated

•  Heat trace and insulation for economizer piping by Lessee

75,000 PPH Trailer-Mounted Watertube

Page 29: Third Quarter Meeting Presentation Temporary Steam Plant

Back Front Valves

What is on a Trailer-Mounted Boiler?

Page 30: Third Quarter Meeting Presentation Temporary Steam Plant

Top 4 Reasons for a Master Agreement Program

Minimize Down Time

Insurance Requirement

Timely Rental Process/Response

Successful Implementation & Execution

Page 31: Third Quarter Meeting Presentation Temporary Steam Plant

Temporary Steam Plant Guidelines

Questions & Answers

Jack Muscia [email protected]

1-800-4INDECK

Page 32: Third Quarter Meeting Presentation Temporary Steam Plant

Thank You!