COST ESTIMATION & CLEARANCES FOR 3x660 MW TPP
Preliminary cost Estimate for 3x 660 MW TPP COST ( Crore ) % Cost
100 Preliminary investigation & survey 2.5 0.04%
200 Civil Works 800 .0 11.40%
300 Mechanical Works 5367.4 76.46%
401 Main Plant 3900 55.56%
401 Steam generator with associated auxiliaries 2500 35.61%
401 Turbo generator with associated auxiliaries 1400 19.94%
402 Coal handling Plant 480 6.84%
403 Ash Handling Plant 260 3.70%
404 Water System 540 7.69%
404 Sea Water Intake including intake piping and
outfall 200 2.85%
404 Water treatment plant( Desalination & DM) 180 2.56%
404 Cooling tower including pumps 160 2.28%
405 LP & CW piping including valves, specialities and
fittings 65 0.93%
406 Air conditioning system and ventilation system 20 0.28%
407 Fire protection system 60 0.85%
408 Cranes/ Hoisting Equipments 10 0.14%
409 Compressed air System 13 0.19%
410 Miscellaneous Equipments, tanks, Piping,
Insulation etc 19.4 0.28%
411 Sub Total 5367.4 76.46%
GRAND TOTAL MECHANICAL 5367.4 76.46%
500 Electrical Works 350 4.99%
501 Electrical cost AS PER ROW 300 4.27%
505
Cost of transmission line & plant instrument & control
Lumpsum 200 2.85%
600 Total works Cost ( Prelims+ civil + mech+ elec+ C& I)
7019.9 100.00%
700 EPC Project Cost 7019.9 100.00%
Supply Of Main Plant Equipment System 3900 43%
Supercritical Boiler Including Auxiliaries 2500
Supercritical STG & Auxiliaries 1400
Supply of BOP Equipment System 2317.4 26%
Other mechanical Equipment System 1467.4
Electrical Equipment System and C&I 850
Engineering & Project management 351 4%
Erection & commissioning 352 4%
Civil Works 800 9%
Total 7720.5 86%