the world bank for official use only report no. 53308-in · 2016. 7. 13. · document of the world...
TRANSCRIPT
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No. 53308-IN
PROJECT PAPER
ON A
PROPOSED ADDITIONAL FINANCING (LOAN)
IN THE AMOUNT OF US$ 50.7 MILLION
TO THE
REPUBLIC OF INDIA
FOR THE
TAMIL NADU ROAD SECTOR PROJECT
March 4, 2010
Sustainable Development Department
India Country Management Unit
South Asia Region
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective December 31, 2009)
Currency Unit = Indian Rupees (Rs)
Rs 46.5362 = US$ 1.0
US$ 1.0 = US$ 0.021489
FISCAL YEAR
April 1 – March 31
ABBREVIATIONS AND ACRONYMS
AG Accountant General
BOT Built Operate and Transfer
CAS Country Assistance Strategy
CQS Selection based on Consultants Qualification
DC Direct Contracting
EIRR Economic Internal Rate of Return
EMP Environmental Management Plan
FBS Fixed Budget Selection
FIRR Financial Internal Rate of Return
FMR Financial Management Report
FY Financial Year
GL Guidelines
HDM-4 Highway Development & Management Model-4
IBRD International Bank for Reconstruction & Development
ICB International Competitive Bidding
LIB Limited International Bidding
M&E Monitoring & Evaluation
NCB National Competitive Bidding
NGO Non-Government Organization
NPV Net Present Value
PDO Project Development Objective
PMU Project Management Unit
PPP Public Private Partnership
QBS Quality Based Selection
QCBS Quality & Cost Based Selection
QPR Quarterly Progress Report
RAP Resettlement Action Plan
SOE Statement of Expenditure
SSS Single Source Selection
TNRSP Tamil Nadu Road Sector Project
VOC Vehicle Operating Costs
Vice President : Isabel M. Guerrero
Country Director : N. Roberto Zagha
Sector Director : John Henry Stein
Sector Manager : Michel Audigé
Task Leader : Pratap Tvgssshrk
TABLE OF CONTENTS
Page
PROJECT PAPER DATA SHEET ............................................................................................ (i)
A. INTRODUCTION............................................................................................................. 1
B. BACKGROUND AND RATIONALE FOR ADDITIONAL FINANCING IN THE
AMOUNT OF US$ 50.7 MILLION 1
C. PROPOSED CHANGES .................................................................................................. 3
D. CONSISTENCY WITH CAS .......................................................................................... 7
E. ECONOMIC ANALYSIS OF COST OVERRUN ......................................................... 7
F. EXPECTED OUTCOMES .............................................................................................. 7
G. BENEFITS AND RISKS .................................................................................................. 7
H. FINANCIAL TERMS AND CONDITIONS FOR THE ADDITIONAL
FINANCING ..................................................................................................................... 8
ANNEX 1: REVISED ESTIMATED PROJECT COSTS
ANNEX 2: DISBURSEMENT SCHEDULE
ANNEX 3: ANALYSIS OF REASONS FOR COST OVERRUN
ANNEX 4: SCHEDULE FOR COMPLETION OF ACTIVITIES
ANNEX 5: SUMMARY OF THE REVISED ECONOMIC ANALYSIS
ANNEX 6: GOVERNANCE & ACCOUNTABILITY ACTION PLAN
ANNEX 7: CATEGORY-WISE ALLOCATION OF LOAN
i
PROJECT PAPER DATA SHEET
Date: March 4, 2010
Country: India
Project Name: Tamil Nadu Road Sector Project
– Additional Financing
Project ID: P118981
Team Leader: Pratap Tvgssshrk
Sector Director/Manager: John Henry Stein/
Michel Audigé
Country Director: N. Roberto Zagha
Environmental Category: A
Borrower: India
Responsible agency: Government of Tamil Nadu
Revised estimated disbursements (Bank FY/US$ m)
FY 2004 2005 2006 2007 2008 2009 2010 2011 2012
Annual 7.29 36.81 46.79 61.19 97.50 113.10 107.72 23.00 13.70
Cumulative 7.29 44.1 90.89 152.08 249.58 362.68 470.40 493.40 507.10
Current closing date: March 31, 2010
Does the restructured or scaled-up project require any exceptions from Bank
policies?
Have these been approved by Bank management? Not applicable
Is approval for any policy exception sought from the Board?
○ Yes No
○ Yes No
○ Yes No
Revised project development objectives/outcomes: [Not applicable]
Does the scaled-up or restructured project trigger any new safeguard policies? No
For Additional Financing
[X] Loan [ ] Credit [] Grant
For Loans/Credits/Grants:
Total Bank financing (US$ m): 50.7
Proposed terms: IBRD Flexible Loan with variable spread and final maturity of 25 years
including a grace period of 5 years
Financing Plan (US$ m)
Source Local Foreign Total
Borrower
IBRD
Total
6.40
40.15
46.55
0
10.55
10.55
6.40
50.70
57.10
1
A. INTRODUCTION
1. This Project Paper seeks the approval of the Executive Directors to provide an additional loan in
an amount of US$ 50.7 million to Tamil Nadu Road Sector Project, India (Project ID: P050649, Loan
Number: 4706-IN). The proposed additional loan would help finance the costs associated with cost
overrun as discussed in paragraph 6 below. There would be no changes to the original design and ongoing
activities of the Project.
B. BACKGROUND AND RATIONALE FOR ADDITIONAL FINANCING IN THE
AMOUNT OF US$ 50.7 MILLION
Project Data and Performance
2. Tamil Nadu Road Sector Project was declared effective on October 31, 2003, with a loan amount
of US$ 348 million. Key project data and performance are summarized below:
Key Project Data Project Performance
Loan Amount: US$ 348 million Development Objectives: Satisfactory
Effectiveness date: October 31, 2003 Implementation Progress: Satisfactory
Closing date: March 31, 2010 Environmental Safeguards: Satisfactory
Project Age: 73 months Social Safeguards: Satisfactory
Loan Disbursed: US$ 314.73 million (90.44%) Risk Flags: None
3. The Project Development Objective (PDO) is to improve the quality and sustainability of the core
road network of Tamil Nadu. This objective is to be achieved through implementation of the following
three project components:
a) Road Upgrading Component consisting of widening and strengthening of about 750 km of
existing state highways to two lane roads
b) Road Maintenance and Safety Works Component consisting of periodic maintenance works
covering about 2000 km of state roads
c) Institutional Strengthening and Policy Development Component consisting of implementation
of Institutional Strengthening Action Plan, strengthening of road maintenance planning and
implementation, road safety, training, equipment, and pre-investment studies
4. The Project impact is monitored through improvements in key performance indicators relating to:
(a) rate of accident fatalities; (b) road network condition; (c) annual maintenance expenditures; and (d)
implementation of institutional strengthening action plan. Achievement of the PDO is satisfactory based
on the performance indicators agreed at appraisal. Three indicators out of six have exceeded the end-of-
project targets. These indicators are (a) reduction in road accident fatalities, (b) adequacy of resources
allocated to road maintenance, and (c) reduction of travel time. Implementation of the institutional
strengthening action plan, the fourth indicator, has been moderately satisfactory. The fifth indicator,
percentage of core road network in poor condition, has not yet met the end-of-project target. The sixth
indicator (i.e. actual economic rate of return of civil works financed under the project) will be calculated
at the end of the project.
The project implementation is satisfactory. The implementation progress by component is:
2
a) Road upgrading: The overall progress of works in five contracts which are under implementation is
about 89%. For one contract [i.e construction of Tsunami Bridge], procurement of works has been
completed. For the remaining one contract [i.e 4 km-long Kumbakonam Bypass], bids are expected to be
invited shortly.
b) Road maintenance and safety works: 849 km of roads have been improved. Works on 117 km of roads
are in progress. For improvement of about 300 km of roads on performance-based maintenance contracts,
bidding documents are being prepared. For another 113 km of roads, which have been studied for
development on PPP basis but were found to be unviable for toll-based BOT operations due to low FIRR
values, bidding documents are being prepared for maintenance.
c) Institutional Strengthening and Policy Development: Activities have focused on the institutional
framework of the Highways Department and on capacity building. Activities in the component are now
concentrating on providing tools to strengthen the operational capacity of the Highways Department.
These include Road Management System (RMS), Integrated Human Resource, Project and Financial
Management System (P&FMS), Geographic Information System (GIS), Road Accident Data
Management System (RADMS).
5. All legal covenants are in compliance.
Causes of the Cost Overrun
6. The project has experienced significant cost overrun. The cost overrun is primarily due to (a)
increased costs of the upgrading works due to increase in the prices of construction materials and delays
in execution of contracts, (b) appreciation of Indian Rupee vis-a-vis the US Dollar, and (c) addition of a
Tsunami affected bridge for which amendment to the Loan Agreement was carried out. Detailed analysis
of the reasons for cost overrun is presented in Annexure 3. The table below presents the breakdown of the
increase in costs.
(in million US $)
Item Amount of increase % of total increase
Upgrading works 41.5 73
Savings/overrun in all other items (-) 8.4 (-) 14.8
Exchange rate fluctuation 23.8 41.8
Total 56.9 100
a) Due to unprecedented hike in international oil prices, the prices of oil-based materials have
escalated. The prices of other road construction materials have also skyrocketed due to higher
transportation charges. Delays in execution of contracts and vast number of road works being undertaken
in the country also contributed to the increase in prices of key input materials. These have resulted into
requirement of more than expected „price contingencies/escalation‟. The bids for three civil works
contracts were received in October 2003 and agreements signed in October 2004/February 2005. This has
also resulted in escalation of cost of these contracts even though the bid prices do not vary with respect to
the base costs estimated at the time appraisal.
b) The other primary reason for cost overrun is appreciation of Indian Rupee. At the time of
appraisal of project, the exchange rate was 1 US$ = Rs. 48. During the course of the project, Indian Rupee
has appreciated to the level of about 1 US$ = Rs. 39. About US $ 23.8 million have already been spent
because of appreciation of Indian Rupee.
c) The Loan Agreement was amended in May 2005 to support the reconstruction and rehabilitation
of all roads and structures damaged and affected by the 26 December 2004 Tsunami that struck the coast
3
of Tamil Nadu. A bridge affected by the Tsunami is added to the scope of work for which procurement is
in process. Estimated Bank financing required for this bridge is about US $ 3.73 million.
Rationale for Additional Financing
7. The causes of the cost overrun were mostly outside the control of the Government of Tamil Nadu.
The additional loan will allow for completion of the works and services in the project. Without additional
finance, the PDO would not be achieved and the indicators related to reduction in core road network in
poor condition and implementation of institutional strengthening action plan would be compromised.
C. PROPOSED CHANGES
8. There are no changes in the PDO, design, and scope. There are no complimentary changes
applicable to the financial management and disbursement arrangements. The changes applicable to the
institutional arrangement and implementation mechanism are presented in paragraphs 13 and 20. Two of
the upgrading contracts (i.e. Tsunami Bridge and Kumbakonam Bypass) and periodic maintenance works,
which are presently at the stage of procurement, cannot be completed within the Loan Closing Date. To
complete these works in the project, extension to the Loan Closing Date by two years i.e. up to 31 March
2012 would be necessary. This would also allow for implementation of a Highways Department wide
Integrated Human Resource, Project and Financial Management System (P&FMS) and Geographic
Information System (GIS) which are presently at the stage of procurement. Revised estimated project
costs and disbursement schedule are presented in Annexes 1 and 2.
9. Financing Plan
Revised financing plan (in US $ million)
Source Parent Project Additional financing Total
IBRD 348 50.7 398.7
Government of India /
Borrower 102 6.4 108.4
Total 450 57.1 507.1
The revised category-wise loan allocation is presented at Annexure 7.
10. Implementation Schedule - To complete all the works and services in the project, extension to
the Loan Closing Date by two years i.e. up to 31 March 2012 would be necessary. The expected schedule
for completion of works/activities is presented at Annexure 4.
11. Disbursement Arrangements - Disbursements under the project will follow the SOE method
which is well established (reimbursement with full documentation and against SOE). Expenditures on
Land Acquisition, utility shifting and operating costs will be continued to be financed by the project from
Government of Tamil Nadu‟s own funds and will not be reimbursed by the Bank.
12. Financial Management – There are no changes in the implementation arrangements and the
consequently the accounting & reporting units remain unchanged and the existing project‟s financial
management arrangements, which are considered adequate, will account for and report on the additional
financing also. The existing financial management for the project is fully mainstreamed and uses country
systems for budget and accounting (Accountant General‟s accounting systems). For the purpose of
FMR/QPR a separate (excel based) system has been established at the PMU which helps generate
contract/package and activity-wise financial progress and the aggregate expenditure information in the
two systems (AG and excel) is reconciled on a monthly basis. The finance staff is also from the state
4
finance and accounts service in the PMU and divisional accountants in the 6 divisions. The project has
submitted the audit report for the year 2008-09 in a timely manner and there are no significant
accountability issues or ineligible expenditures identified in the external audit report. There is an in-house
internal audit wing in the PMU which carries out a 100% check of all expenditures on the up-gradation
component and audit of a sample of maintenance works is carried out by the internal audit wing of
Highways dept. There were issues relating to payments of variations orders beyond 15% and equipment
advance against hypothecated assets which were identified by internal audit – these have since been
satisfactorily resolved by the project management and there are no major unaddressed issues identified in
internal audit. The project also has a practice of obtaining independent confirmation (from the Bank) of
the Bank guarantees furnished by the contractors to confirm authenticity. The external audit for the
additional financing will also be carried out by Comptroller and Auditor General, who is the auditor for
the existing project also, as per the existing terms of reference. There would be one consolidated audit
report for both the existing project and the additional financing with a segregation of the claims under the
original and additional financing. The following audit reports will be monitored in the Audit Reports
Compliance System (ARCS):
Implementing Agency Audit
Auditors Audit Due Date
GOTN Highways Dept PMU Project financial
statements with SOE
CAG 6 months after the end of each
fiscal year (March 31st)
DEA/GOI Designated account CAG 6 months after the end of each
fiscal year (March 31st)
13. Procurement – Even though the additional financing is needed mostly to meet the cost overrun,
about 30 contracts (Works, Goods and Services) will be issued during the period of additional financing
(April 1, 2010 to March 31, 2012). Procurement of the activities financed by this additional loan will be
as per the World Bank Procurement/Consultant Guidelines of May 2004, revised October 2006. The
PMU is well equipped to handle the procurement proposed under the project and most of the officials
involved in procurement have undergone the training in Bank funded procurement. The Highways
Department has earlier handled many Bank-financed projects and is fully aware of the Bank procurement
procedures. Despite this, the delays in decision-making process are a major cause of concern. Based on
these factors, it is considered as “Medium-Risk” implementing agency. Though some other projects in
Tamil Nadu have experienced lack of competition in the bidding process for Civil Works, TNRSP has not
faced this problem in the past probably because of nature of the Works (viz. roads) and also size of the
contracts (relatively larger). Moreover, most of the civil works contracts are already awarded.
a) Procurement Methods: The details are given in the following table:
Category Method of
Procurement
Threshold (US$ Equivalent) for
parent loan
Proposed threshold (US$ Equivalent)
for additional loan
Civil Works
ICB >10,000,000 >10,000,000
NCB Up to 10,000,000 Up to 10,000,000
Shopping Up to 50,000 Up to 50,000
DC Not applicable As per para 3.6 of Guidelines
BOT Contract As per para 3.13(a) of GL As per para 3.13(a) of GL
Force Account As per para 3.8 of GL As per para 3.8 of GL
Goods and
Non-consultant
services
ICB >200,000 >1,000,000
LIB Not applicable As per para 3.2 of GL
NCB Up to 200,000 Up to 1,000,000
Shopping Up to 30,000 Up to 30,000
5
Category Method of
Procurement
Threshold (US$ Equivalent) for
parent loan
Proposed threshold (US$ Equivalent)
for additional loan
DC As per para 3.7 of GL As per para 3.6 of GL
Consultants‟
Services
CQS/LCS Not applicable Up to 100,000, as per para 3.6-3.7
SSS As per para 3.8-3.11 of GL As per para 3.9-3.12 of GL
Individuals As per para 5.1-5.4 of GL As per para 5.2 to 5.4 of GL
FBS As per para 3.1 and 3.5 of GL As per para 3.1 and 3.5 of GL
QBS Not applicable As per para 3.1 and 3.2 of GL
QCBS For remaining cases For remaining cases
Shortlist
Shortlist may comprise national
consultants only <200,000
Shortlist may comprise national
consultants only <500,000
b) Bank‟s Review: The frequency of supervision missions will be one every 6 months and the
Designated Procurement Specialist (DPS) will be part of the implementation supervision missions. The
Bank will prior review all the Works contracts above US$ 5 Million in value (against US$ 3 Million for
parent loan), Goods as well as non-consultancy services contracts above US$ 1 Million in value (against
US$ 500,000 for parent loan), and Consultancy services contracts above US$ 200,000 for firms (no
change) and US$ 50,000 for individuals (no change). In addition, all consultancy contracts to be issued on
single-source basis exceeding US$ 50,000 in value to consultancy firms shall be subject to prior review.
In case of single source contract to individuals, the qualifications, experience, terms of reference and
terms of employment shall be subject to prior review. All contracts below the prior review threshold will
be subject to periodic post review on a sample basis.
c) Procurement Risk: The following table lists major procurement related risks and the mitigation
plan. The risk ratings have been decided based on both the probability of occurrence of various risk
factors as well as their likely impact. Based on the risk factors, the overall residual procurement risk
rating for the project is proposed as “Substantial”.
Risk Factor Initial
Risk
Mitigation Measure Completion
Date
Residual Risk
F&C risk
(including
collusion and
outside
interference) in
contracting process
High • Measures to improve competition such as
appropriate packaging, realistic post
qualification criteria, market-linked cost
estimate etc.
• Increased disclosure, improvement in
complaint handling, documentation, etc.
• Monitoring of indicators of F&C in the
procurement process and initiate appropriate
action if such indicators are noticed
Ongoing
Ongoing
Ongoing
Substantial
Inefficiencies and
delays in
procurement
process
High • Cutting down the internal delays in decision
making by closer scrutiny of the procurement
progress
• Using e-mail for communication with the
Bank and forwarding complete information to
the Bank in one go
Ongoing
Ongoing
Substantial
Overall Risk High Substantial
6
d) Other Procurement Provisions: All other procurement provisions applicable to parent loan will
also be applicable to additional loan.
14. Environmental Safeguards – The environmental safeguard policies developed for the parent
project will also apply to the additional loan. The environmental issues in the project included
unavoidable tree cutting, road upgrading and widening adjacent to eco-sensitive coastal zone, unavoidable
removal and shifting of community assets from the corridor of impact and temporary construction related
impacts. These impacts have been, by and large, addressed through effective management as detailed in
the Environmental Management Plan (EMP) and Environment and Resettlement Management Plan
(ERMP). The key features of EMP include sound environmental management of temporary impacts
during construction phase; extensive tree plantation efforts jointly organized with Tamil Nadu Forest
Department; compliance with Ministry of Environment and Forests (MOEF) regulatory clearance
conditions stipulated for the road packages adjacent to sensitive coastal zone; and environmental
enhancements for cultural and community assets, and incidental spaces along the project corridors.
Integration of environmental enhancement measures along the project corridors, in addition to project
EMPs, has paid good results and built community goodwill. The progress of these measures in all the
upgrading roads except TNRSP - 01 is about 90%, and in TNRSP - 01, the progress is about 55%. The
specific value addition includes restoration/protection of 108 roadside ponds, enhancement of 155 cultural
/ community properties and improvement of about 70 incidental spaces contributing to road safety,
common space for community use, and better landscaping. The successful implementation of
enhancement measures highlights the need for enhancing the community assets along the project corridor
through EMPs. As part of the project, the Highways Department will commission a specific study to
document good practices and lessons learnt in implementing the project EMPs. EMP implementation
progress is in line with construction progress and implementation is satisfactory. However, the EMP
implementation progress of about 55% in TNRSP 01 is slow compared to that of other contract packages
of the project. The Highways Department will continue to critically monitor the progress of EMPs. For
implementation of EMPs, the current structure of Environmental Management Unit with one
Environmental Engineer and one Forest officer will continue. The consolidated Environmental
Assessment Report has been published on November 12, 2009.
15. Social Safeguards – The magnitude of private land acquisition and resettlement impacts in the
project is one of the largest for the State Highway projects of this nature (432 hectares, 11,155 land
owners and 1085 displaced families). The implementation of Resettlement Action Plan for mitigation of
these impacts has been largely completed (about 97%). The land acquisition and resettlement impacts in
the two upgrading contracts, which are currently in procurement stage, are very limited and award of
these contracts is linked to the satisfactory completion of pre-identified actions in the implementation of
RAP. The overall land acquisition and resettlement implementation is proceeding satisfactorily except
that there is one unresolved issue. This issue relates to pending payments to NGOs and M&E consultants
where some of the payments have been disallowed by the Highways Department. The Highways
Department held a meeting with NGOs/M&E consultants on this issue during the recent Bank mission in
November, 2009 wherein the Highways Department has clarified that it will provide a statement on the
status of payments and disallowances, and any outstanding eligible payments will be released
immediately. The Highways Department, accordingly, have prepared a statement on payments made and
outstanding and shared that with consultants on 6 January 2010. As per the statement prepared by the
Highways Department, there are no outstanding eligible payments. As regards disallowances, the
Highways Department clarified that they are not in a position to revisit and the NGOs and M&E
consultants can resort to the remedial measures as available in the contract.
7
D. CONSISTENCY WITH CAS
16. The project is consistent with the November 2008 CAS (for the period FY 2009 – 2012) which is
organized around three pillars: rapid and inclusive growth, sustainable development, and service delivery,
with a cross-cutting focus on improving the effectiveness of public spending and achieving results. The
project will help in removing infrastructure and skills constraints to growth in both urban and rural areas.
E. ECONOMIC ANALYSIS OF COST OVERRUN
17. Revised economic analysis has been carried out for the upgrading roads because in these works
there are cost overruns. At the time of appraisal of the parent project, economic analysis was carried out
for 743 km of upgrading roads and the overall EIRR for these roads was 30.2% with an NPV, discounted
at 12%, of Rs 26,233 million. For carrying out revised economic analysis, four homogenous/typical
stretches in TNRSP 01 and two each in all the other roads have been considered. Revised economic
analysis has been carried out using the Highway Development and Management Model (HDM-4). The
analysis is done considering a period of 25 years including construction period. Vehicle Operating Costs
(VOC) and value of time have been considered in the analysis. Updated vehicle parameters and unit costs
have been used in the analysis. In all sections, the NPV discounted at 12% is positive confirming the
economic justification of the project even though the cost of civil works increased significantly. The
EIRR for all the sections is between 15.6% and 49.6%. Some of the sections have higher EIRR than at
appraisal. The sections in TNRSP 02 stretch have higher EIRR than all other stretches due to higher
traffic volumes and relatively less increase in construction costs. Comparatively low EIRRs of sections in
TNRSP 03 and TNRSP 04 are due to the combination of high increase in construction costs and lower
traffic volumes. The results of the sensitivity analysis considering 20 percent decrease in benefits show
the economic justification of the project even though the benefits are decreased significantly. The EIRR
for all the sections in such situation also is more than 12%. Annexure 5 presents details of analysis carried
out.
F. EXPECTED OUTCOMES
18. The expected outcome is to improve the quality and sustainability of the core road network of
Tamil Nadu. The outcome is on track and the additional loan will help ensure that it is ultimately
achieved.
G. BENEFITS AND RISKS
19. The project is aimed at improving the quality and sustainability of the core road network of Tamil
Nadu. With successful implementation of road upgrading, and road maintenance and safety works
components, the quality of the core road network would be improved. Implementation of the Integrated
Human Resource, Project and Financial Management System (P&FMS) and Geographic Information
System (GIS), which are presently at the stage of procurement and operationalization of Road
Management System and Road Accident Data Base Management System, would enhance the
management capabilities of the Highways Department. Functional re-organization of the Highways
Department, which has been finalized and awaiting approval of the Government of Tamil Nadu, will also
be completed.
20. There are no additional risks associated with this additional Loan. However, a Governance and
Accountability Action Plan [enclosed at Annexure 6], which will be applicable to the activities financed
by this additional loan, has been prepared by the Highways Department together with the Bank and its
implementation will be reviewed during project implementation support missions.
8
H. FINANCIAL TERMS AND CONDITIONS FOR THE ADDITIONAL LOAN
21. The additional financing loan would IBRD Flexible Loan with variable spread and final maturity
of 25 years including a grace period of 5 years. The Front End Fee for the additional financing would be
0.25%. The additional financing will be processed as an amendment of the original Loan Agreement
under the original General Conditions rather than as a new Loan. This is in compliance with the
understanding between Legal and OPCIL that if an additional financing involves no new activities but
just cost overruns, a simple amendment would be acceptable.
22. There are no effectiveness conditions.
9
Annex 1
REVISED ESTIMATED PROJECT COSTS
Project Cost By Component Local Foreign Total
US$ million US$ million US$ million
1. Road Upgrading Component 255.95 99.54 355.49
2. Road Maintenance and Safety Works Component 94.75 10.53 105.28
3. Institutional Strengthening and Policy Development 13.03 5.85 18.88
Project Costs 363.73 115.92 479.65
Exchange rate fluctuation* 23.80 - 23.80
Total Project Costs 387.53 115.92 503.45
Front-end Fee - 3.61 3.61
Total Financing Required 387.53 119.53 507.06
Project Cost By Category Local Foreign Total
US$ million US$ million US$ million
1. Goods 3.48 1.06 4.54
2. Works 327.71 102.51 430.22
3. Services 32.54 12.35 44.89
Project Costs 363.73 115.92 479.65
Exchange rate fluctuation* 23.80 - 23.80
Total Project Costs 387.53 115.92 503.45
Front-end Fee - 3.61 3.61
Total Financing Required 387.53 119.53 507.06
Note: * Effect of exchange rate fluctuation is shown separately. This amount is consumed in road upgrading component and road
maintenance and safety works component against works.
10
Annex 2
DISBURSEMENT SCHEDULE
Years Ending June 30
US$ Million 2004
(actual)
2005
(actual)
2006
(actual)
2007
(actual)
2008
(actual)
2009
(actual)
2010 2011 2012 Total
Parent Project
Total Financing
Required
Project Cost
Investment cost 3.11 36.11 46.09 60.49 96.80 112.4 87.32 442.32
Recurrent Cost 0.7 0.7 0.7 0.7 0.7 0.7 0.0 4.20
Total Project
Cost
Front-end fee 3.48 0.00 0.00 0.00 0.00 0.00 0.00 3.48
Total Financing 7.29 36.81 46.79 61.19 97.50 113.10 87.32 450.00
Financing
IBRD 4.99 26.61 37.89 42.09 77.00 88.70 70.72 348.00
Government 2.30 10.20 8.90 19.10 20.50 24.40 16.60 102.00
Others 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Project
Financing
7.29 36.81 46.79 61.19 97.50 113.10 87.32 450.00
Additional
Financing
Total Financing
Required
Project Cost
Investment cost 20.27 23.00 13.70 56.97
Recurrent Cost 0.00 0.00 0.00 0.00
Total Project
cost
20.27 23.00 13.70 56.97
Front-end fee 0.13 0.00 0.00 0.13
Total Financing 20.40 23.00 13.70 57.10
Financing
IBRD 18.00 20.00 12.70 50.7
Government 2.40 3.00 1.00 6.40
Others 0.00 0.00 0.00 0.00
Total Project
Financing
20.40 23.00 13.70 57.10
11
Annex 3
ANALYSIS OF REASONS FOR COST OVERRUN
1. Due to unprecedented hike in international oil prices, the prices of oil-based materials have
escalated. The prices of other road construction materials have also skyrocketed due to higher
transportation charges. Delays in execution of contracts and vast number of road works being undertaken
in the country also contributed to the increase in prices of key input materials. These have resulted into
requirement of more than expected „price contingencies/escalation‟. Some of the price increases during
the course of the project are as follows:
234% increase in the cost of bitumen from Rs. 10660 per MT to Rs. 35670 per MT
193% increase in the cost of steel from Rs. 19500 per MT to Rs. 57200 per MT
Material Unit Current
Price
(in Rs.)
Price in
Base year
[Sep 2003]
(in Rs.)
Percentage
increase of
current price
over base
price
Maximum during
the construction
Percentage
increase over
base price Price
(in Rs.)
Period
Bitumen MT 22777 10660 113.67 35670 Dec-08 234.62
Bitumen
Emulsion MT 26542 11636 128.10 26542 Jun-09 128.10
Cement MT 4400 2660 65.41 5200 Feb-08 95.49
Steel MT 32000 19500 64.10 57200 Jul-08 193.33
Diesel Liter 34.40 22.66 51.81 35.51 Oct-06 56.71
2. The bids for three civil works contracts were received in October 2003 and agreements signed in
October 2004/February 2005 as shown in the table below. This has also resulted in escalation of cost of
these contracts even though the bid prices do not vary with respect to the base costs estimated at the time
of appraisal.
Contract Bids invited on Bids opened on Agreement signed on
TNRSP 01 7-Jul-03 15-Oct-03 8-Oct-04
TNRSP 02 16-Jul-03 14-Oct-03 4-Feb-05
TNRSP 03 16-Jul-03 14-Oct-03 4-Feb-05
TNRSP 04 16-Jul-03 14-Oct-03
TNRSP 04 - Second
invitation 17-Feb-05 12-May-05 13-Nov-05
3. There are variations in the upgrading civil works contracts. The primary reasons for the variations
are (a) huge time difference between the preparation of Detailed Project Report in year 1999 to start of
construction of works in year 2005, (b) damages done to the existing pavements because of the Tsunami
that struck the coast of Tamil Nadu on 26 December 2004, and (c) deficiencies in the bills of quantities.
However, some of the contracts have positive and others have negative cumulative variations. Therefore,
as a whole, there is no contribution of variations to the cost overrun. The cost overrun in upgrading
contracts is about US $ 41.5 million. The details are shown in the table below:
12
(in million US
$)
Contract
/ Item Category
At appraisal stage As of now for completion of works
Base
cost
Physical contingen
cies
Price contingen
cies
Total
cost
Bank
Share
Original contract
price
Variati
ons Escalation
Total
cost
Bank Share
required
TNRSP
01 1 (a) 138.54 10.39 11.17 160.10 128.08 127.44 -20.83 31.17 137.77 110.22
TNRSP
02 1 (a) 42.71 3.20 3.44 49.35 39.48 41.41 12.06 15.38 68.85 55.08
TNRSP
03 1 (a) 25.83 1.94 2.08 29.85 23.88 29.88 11.43 11.46 52.77 42.22
TNRSP
04 1 (a) 23.96 1.80 1.93 27.69 22.15 24.85 7.70 9.38 41.92 33.54
TNRSP
05 – 1 1 (a)
9.27 0.70 0.75 10.72 8.58
7.35 0.00 0.65 8.01 6.41
TNRSP
05 – 2 1 (a) 4.70 0.00 0.50 5.20 4.16
Tsunami
Bridge 1 (a)
4.17 0.00 0.50 4.67 3.73
Total
240.31 18.03 19.37 277.71 222.17 239.80 10.36 69.03 319.19 255.35
Difference with respect to the estimates at the stage of appraisal -0.51 -7.67 49.66 41.48 33.18
4. As can be seen from the above, the primary factor contributing to the increase in total cost is the
escalation due to increase in prices of input materials. In escalation/price contingencies, the contribution
of cement, steel, bitumen, oil and lubricants, and other materials including aggregates are 8.5%, 4.2%,
32.3%, 12.9% and 42.1% respectively.
5. The Loan Agreement was amended in May 2005 to support the reconstruction and rehabilitation
of all roads and structures damaged and affected by the 26 December 2004 Tsunami that struck the coast
of Tamil Nadu. A bridge affected by the Tsunami is added to the scope of work for which procurement is
in process. Estimated Bank financing required for this bridge is about US $ 3.73 million, which is
included in the above calculations.
6. The other primary reason for cost overrun is appreciation of Indian Rupee. At the time of
appraisal of project, the exchange rate was 1 US$ = Rs. 48. During the course of the project, Indian Rupee
has appreciated to the level of about 1 US$ = Rs. 39. The average exchange rate of Indian Rupee versus
US $ in different months during the project duration is as under:
13
About US $ 23.8 million have already been spent because of appreciation of Indian Rupee. The
details of expenditure made up to 31 July 2009 in various currencies and corresponding disbursements are
presented below.
Bank financed eligible expenditure made Disbursed in $
(excluding Special
Account) in various currencies in equivalent INR (approx. at Rs 48, 40, 80 per $, AUS
$, and #)
$ 6,022,357 289,073,119 6,022,357
AUS $ 85,588 3,423,535 648,731
# 266,708 21,336,608 482,165
INR 12,152,797,000 12,152,797,000 276,349,665
Total 12,466,630,262 283,502,917
14
Annex 4
SCHEDULE FOR COMPLETION OF ACTIVITIES
Activity/Contract Ongoing / to be
procured
Expected date of
completion
TNRSP 01 upgrading works contract Ongoing March 2010
TNRSP 02 upgrading works contract (except Vettar Bridge and
Bridge No.s 31 and 32)
Vettar Bridge
Bridge No.s 31 and 32
Ongoing
Ongoing
Ongoing
March 2010
June 2010
December 2010
TNRSP 03 upgrading works contract Ongoing Substantially
Completed
TNRSP 04 upgrading works contract Ongoing March 2010
TNRSP 05 upgrading works contract – Ramanad bypass Ongoing July 2010
Third and fourth year maintenance works Ongoing July 2010
Kumbakonam Bypass upgrading works contract to be procured July 2011
Tsunami Bridge upgrading works contract to be procured December 2011
Performance based maintenance contracts – first year
-second year
to be procured April 2011
December 2011
Minor road safety improvement works to be procured December 2010
Project and Financial Management System to be procured August 2011
Geographic Information System to be procured August 2011
Transaction advisory services for feasibility study of PPP roads to be procured March 2011
Pre-investment studies to be procured December 2010
Equipment for implementation of RADMS to be procured December 2010
Equipment for data collection for GIS to be procured December 2010
15
Annex 5
SUMMARY OF THE REVISED ECONOMIC ANALYSIS
1. Revised economic analysis has been carried out for the upgrading roads because in these works
there are cost overruns. The following table presents the variation in costs in the upgrading contracts.
Contract
/ Road
Stretch
Initial costs (Rs million) Revised Costs (Rs million) Variation
in total
cost (%) Base
cost
Physical
contingencies
Price
contingencies
Total
cost
Contract
price Variations Escalation
Total
cost
TNRSP
01 6650 499 536 7685 6117 (-) 1000 1496 6613 (-) 13.9
TNRSP
02 2050 154 165 2369 1988 579 738 3305 39.5
TNRSP
03 1240 93 100 1433 1434 549 550 2533 76.8
TNRSP
04 1150 86 93 1329 1193 370 450 2013 51.4
The decrease in cost of TNRSP 01 road stretch is due to deletion of six Road Over Bridges, which were
entrusted to the contractor for TNRSP 02. The decrease in cost is also due to deletion of road works in
about 13.6 km length of the stretch.
2. Traffic counts were carried out in year 2008 and these are presented vis-à-vis the corresponding
figures in the year 2003 in the following table.
Contract / Road
Stretch
Traffic volume in PCUs in the year
2003 2008
TNRSP 01 3450 6104
TNRSP 02 6148 11586
TNRSP 03 2414 4486
TNRSP 04 1087 2221
3. At the time of appraisal of the parent project, economic analysis was carried out for 743 km of
upgrading roads and the overall EIRR for these roads was 30.2% with an NPV, discounted at 12%, of Rs
26,233 million. For carrying out revised economic analysis, four homogenous/typical stretches in TNRSP
01 and two each in all the other roads have been considered. The following table presents the lengths and
unit costs of these homogenous sections.
Contract /
Road Stretch
Homogenous /
typical section
Length of
homogenous section
(km)
Unit cost in 2003
(Rs million)
Revised Unit cost
(Rs million)
TNRSP 01
1 24.7 5.0 6.3
2 27.8 12.5 16.5
3 28.6 11.6 15.38
4 27.0 10.6 14.13
TNRSP 02 1 17.6 14.2 20
2 30.3 15.3 20.3
TNRSP 03 1 31.5 15.0 24.0
2 23.5 13.6 23.6
16
TNRSP 04 1 29.2 11.7 17.8
2 38.5 10.6 16.2
4. The following traffic growth rates are used in the analysis. These assumed growth rates are based
on the overall growth of economy and is consistent with those used in the initial economic analysis.
Vehicle type Traffic growth rates (% per year)
TNRSP01 TNSRP02 TNSRP03 TNSRP04
Car 8.5 8.5 10 9
Bus 5 5 5.5 5
Light Commercial Vehicle 6 5.5 6.5 5.5
Multi Axle Vehicle 6.5 6.5 8 7
Heavy Commercial Vehicle 5 4.5 6 5
Auto 7.5 7.5 7.5 8.5
Tractor 5 5 1 5
Two Wheeler 9 9 8 9
5. Revised economic analysis has been carried out using the Highway Development and
Management Model (HDM-4). The analysis is done considering a period of 25 years including
construction period. Vehicle Operating Costs (VOC) and value of time have been considered in the
analysis. Updated vehicle parameters and unit costs have been used in the analysis. In year 2008, the price
of fuel has increased substantially and it is not true representative, instead of 2008 fuel prices, fuel prices
in 2009 have been used in the analysis. The following table presents the results of the revised economic
analysis.
Contract /
Road stretch Homogenous /
typical section
Results of revised economic analysis NPV based on
original costs and
traffic in year 2003 EIRR (%) NPV (Rs million)
TNRSP 01
1 27.8 333 308
2 46.6 1231 1185
3 43.9 635 648
4 33.4 512 512
TNRSP 02 1 49.6 3164 3044
2 46.8 5404 5189
TNRSP 03 1 20.2 532 76
2 19.5 368 74
TNRSP 04 1 15.6 77 46
2 18.7 167 176
6. In all sections, the NPV discounted at 12% is positive confirming the economic justification of
the project even though the cost of civil works increased significantly. The EIRR for all the above
sections is more than 12%. Some of the sections have higher EIRR than at appraisal, which was 30.2%.
The sections in TNRSP 02 stretch have higher EIRR than all other stretches due to higher traffic volumes
and relatively less increase in construction costs. Comparatively low EIRRs of sections in TNRSP 03 and
TNRSP 04 are due to the combination of high increase in construction costs and lower traffic volumes.
7. The first reason which explains the differences in the EIRR is the relative increase in construction
costs compared to the increase in VOCs and savings. VOCs have increased due to the price of inputs such
as fuel and lubricants which saw a major increase and also due to the general inflation for other inputs.
17
The second reason is that the roads deteriorated between the time the initial economic analysis was
carried out and the time the works were executed and roads were improved. This resulted in higher
savings on VOCs than estimated at appraisal, further confirming that the maintenance/improvement of the
roads was justified. The third reason is that the roads became operational later than expected at appraisal
and as a result the savings in the revised economic analysis are based on 2008 traffic volumes while they
were based on 2006/2007 traffic volumes in the initial economic analysis.
8. The following table presents the results of the sensitivity analysis. The sensitivity analysis
considered 20 percent decrease in benefits.
Contract / Road
stretch Homogenous /
typical section
Results of revised economic analysis
with 20% reduction in benefits
EIRR (%) NPV (Rs million)
TNRSP 01
1 24 254
2 40 963
3 37 494
4 28 398
TNRSP 02 1 44 2493
2 42 4251
TNRSP 03 1 18 523
2 17 301
TNRSP 04 1 13 29
2 16 90
9. The above results show the economic justification of the project even though the benefits are
decreased significantly. The EIRR for all the above sections is more than 12%. However, this sensitivity
is unlikely to happen (a) as traffic is expected to grow to accompany the current economic growth, (b)
there is little uncertainty on the cost of the works as all the contracts are nearing completion and the costs
have been updated to take into account the price escalation as well as variations, and (c) VOCs are
unlikely to be reduced in view of the past trend for the price of inputs such as fuel, lubricants, tires, and
salaries.
18
Annex 6
GOVERNANCE AND ACCOUNTABILITY ACTION PLAN
The following Governance and Accountability Action Plan (GAAP) has been prepared to
address key risks in the project as follows:
Delays in land acquisition/pre-construction activities
Collusion by contractors
Submission of fraudulent documents by bidders
Financial progress on project not commensurate with physical progress
Sub-standard quality of road design and/or road work.
Deterioration of assets created under project due to lack of commitment/resources to road
maintenance
Use of Project
Funds
Risk/level of risk Existing measures Proposed Measures Timeline
Upgrading
Works
Delays in Land
acquisition/Low
50% land
acquisition prior to
award of work
100% land to be acquired
prior to award of work
Faulty
designs/Moderate
Designs by reputed
international
consultants
Proof-check by independent
consultants
Due procurement
process not
followed/Low
Complaints handling
mechanism under Chief
Vigilance Officer to deal
with all complaints; Full
disclosure of all award
information
December 2009
Low number of bids
received/Low
Contractor workshops,
appropriate packaging, better
post-qualification criteria to
be employed
Continuous
Collusion by
contractors/Moderate
PIU to start maintaining
database of contractor
participation and contract
award information;
Information to be on website
within 5 days of contract
award
Starting
December 2009
19
Use of Project
Funds
Risk/level of risk Existing measures Proposed Measures Timeline
Upgrading
Works
Submission of fraudulent
documents by
bidder/Moderate
Reference checks to be
conducted for successful
bidder
Continuous
Financial progress not
commensurate with
physical progress/Low
PFMS being developed;
Disclosure of financial
progress reports on
website along with action
taken on external audit
reports, details of audit
notes pending by division
and cumulative payments
against major contracts
June 2010
Ineffective monitoring of
condition/Low
GIS based system along
with RMS will enhance
monitoring of condition
of network
December 2010
Maintenance
Contracts
Quality of work/Low Monitoring by
Highways
Department and
Project Management
Unit, checks by
Technical Examiner
Consultants
Will be performance
based maintenance
contracts; dedicated
quality control cell with
adequate resources under
the proposed Institutional
Development Study in the
TNRSP; empanelment of
a quality control panel
with retired engineers by
GoTN
December 2010
Compliance to
safeguards/Low
Dedicated social and
environmental officer to
monitor these in design
and bid documents
Asset
Management
Low sustainability of
assets created under
project/Low
User satisfaction surveys
and RMS to assess the
quality and percentage of
bad roads under CRN
Surveys at start
mid-point and
end of project
Poor information
disclosure hampers public
scrutiny and
accountability
Disclosure Policy to be
agreed upon; Website to
be in Tamil. Citizen
information boards to be
at all sites. Project
information to be
disseminated through the
departmental Highway
Bulletins as well.
By negotiations
and continuous
through project
implementation
20
Annex 7
CATEGORY-WISE ALLOCATION OF LOAN
S.
No.
Category Amount of the
Original Loan
Allocated
(Expressed in
Dollars)
Amount of the
Additional Loan
(Expressed in
Dollars)
% of Expenditures
to be Financed
1 Civil Works
(a) under Parts A. 1 and B of
the Project
309,170,000 45,453,250 80%
(b) under Part A.3 (c) of the
Project
3,100,000 60,000 90%
2 Goods 3,660,000 40,000 100% of foreign
expenditures, 100%
of local
expenditures (ex-
factory cost), and
80% of local
expenditures for
other items
procured locally
3 (a) Consultant's Services 19,450,000 5,020,000 90%
(b) NGO services and training
under Part A.3 (a) of the
Project
2,480,000 - 100%
4 Subprojects 6,660,000 - 100% of amount
paid by Tamil Nadu
5 Fee 3,480,000 126,750 Amount due under
Section 2.04 of this
Agreement
Total 348,000,000 50,700,000