the smoothing and realignment of the lhc...3 sector78 of the lhc is very unstable has to be surveyed...

22
COULD THE LASER TRACKER AT401 REPLACE DIGITAL LEVELLING AND “ECARTOMETRY” FOR THE SMOOTHING AND REALIGNMENT OF THE LHC ? D. Missiaen, M. Duquenne DOMINIQUE MISSIAEN, CERN SWITZERLAND MATHIEU DUQUENNE, INSA, STRASBOURG, FRANCE

Upload: others

Post on 18-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

COULD THE LASER TRACKER AT401 REPLACE

DIGITAL LEVELLING AND “ECARTOMETRY” FOR

THE SMOOTHING AND REALIGNMENT OF THE

LHC ?

D. Missiaen, M. Duquenne

DOMINIQUE MISSIAEN, CERN SWITZERLAND

MATHIEU DUQUENNE, INSA, STRASBOURG, FRANCE

Page 2: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

2

Introduction

Measuring the sector 78 of LHC using standard and

CERN specific instruments

The AT401

Studies and simulations

Measuring with the AT401

Comparisons

Benefits

Conclusions

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Outlook

Page 3: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

3

Sector78 of the LHC is very unstable

Has to be surveyed and re-aligned very often

LHC is critical as much in vertical as in Horizontal (it was not the case for the LEP

Circular vacuum chamber

Fragile interconnections

It was foreseen during last Winter Technical Stop to make a survey in V and H

CERN is always looking for a sensor to measure remotely the LHC components from a survey train

HEXAGON/LEICA claims that AT401 is a good digital level

Then it was decided to make a measurement of the same area using the AT401

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Introduction

Page 4: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

4

Direct levelling with DNA03 and additional ones with

NA2

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Standard measurements (Vertical)

Page 5: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

5

Ecartometry with offsets with respect to a stretched

wire

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Standard measurements (Horizontal)

Page 6: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

6

A new Boson compatible with the HIGGS described in the standard model discovered at CERN by both ATLAS and CMS : announcement of July, 4th 2012

125 Gev

Still a lot of caracteristics to study

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

HIGGS boson

Page 7: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

7

Hybrid between a total station and a laser tracker

Main parameters

Distances up to 160 m

Heating time 3h

Measurement time < 2s

No measurements under 2m

Accuracy at 2 s (from manufacturer) :

+/-10 mm at 80 m

Angles : ~3 dmgon

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

The AT401

Page 8: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

8

Case 1: one station in front of every quadrupole

measuring one half-cell (53 m) on each side

Case 2 : one station in front of every two

quadrupoles measuring two half-cells (106 m) on

each side

Case 3 : one station in front of every quadrupole

measuring two half-cells (106 m) on each side

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Simulations of measurement sequences

Case Radial

(mm at 1s)

Longitudinal

(mm at 1 s)

Vertical

(mm at 1 s)

1 0.43 0.05 0.02

2 0.27 0.03 0.06

3 0.07 0.02 0.03

Page 9: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

9

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

The AT401 campaign

55 positions of the AT401

~50 points per station

Length : 2500m

Measurements done with Face I and Face II

~7500 observations

Initialisation of the instrument at 10 m

Page 10: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

10

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

The AT401 campaign

Bad closure of round of angles > Differences

between FACE I and II

-0.004

-0.003

-0.002

-0.001

0

0.001

0.002

0.003

0.004

0 500 1000 1500 2000Eca

rt e

n g

on

Nombre de points

-0.0035

-0.0025

-0.0015

-0.0005

0.0005

0.0015

0 500 1000 1500 2000

Eca

rt e

n g

on

Nombre de points

For H angles

For V angles

The origin was probably due to overheating of the

AT401

Page 11: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

11

Two calculations were done

with measurements at a max distance of 53 m

will all measurements

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data processing with LGC

Observations meas < 53 m All meas

R.m.s average R.m.s average

H angle

(dmgon)

0.6 0 1.5 0

V angle

(dmgon)

2.8 1.6 5.2 3.8

Distances

(mm)

0.11 0.00 0.05 0.00

Page 12: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

12

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with LGC (cont’d)

H Measurements with AT401 are closer to the nominal

mainly because they are equivalent to a wire of

200m

Magnets with important deviations are the same

Page 13: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

13

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with LGC (cont’d)

V Measurements with AT401

Page 14: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

14

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with LGC (cont’d)

Difference between Altitudes AT401 and H direct levelling for each position of the instrument

A similar test in an other area gave almost the same results

-1

-0.5

0

0.5

1

1.5

2

2.5

3

3.5

-150 -100 -50 0 50 100 150

Dh[mm]

Cumulative distance [m]

Page 15: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

15

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with LGC (cont’d)

Modelisation of the error

y = 0,0002x2 + 0,0062x - 0,0234 R² = 0,9933

-1

-0.5

0

0.5

1

1.5

2

2.5

3

3.5

-150 -100 -50 0 50 100 150

Ecart en mm

Distance en m

Courbe moyenne

Poly. (Courbe moyenne)

Observations meas < 53 m All meas

R.m.s average R.m.s average

V angle

(dmgon)

1.7 -0.6 2.6 -1.2

Page 16: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

16

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with LGC (cont’d)

after modelisation

Page 17: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

17

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with Plane

The relative position of the magnets is more important for

the beam than the absolute one

The deviations w.r.t a smooth curve, much more significant,

were calculated with PLANE (window, threshold)

Length of the window

offset

The idea is to run PLANE with the data of :

AT401

Levelling and ecartometry

And to compare the distances to the smooth curve

Page 18: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

18

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with Plane (cont’d)

In horizontal

Ecartometry

AT401 : all measurements

AT401 : measurements at a max distance of 53 m

Very gaussian

85% of the deviations

are with 0.1 mm

2 points are further

than 0.3 mm

No major difference

between short and long

distances measurements

Page 19: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

19

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with Plane (cont’d)

In vertical

Direct levelling

AT401 : all measurements (with and without modelisation)

AT401 : measurements at a max distance of 53 m (with and without modelisation)

Page 20: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

20

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Data post processing with Plane (cont’d)

80% of differences are within

0.1mm

2 points are outside the 0.3mm

No major difference between short

and long distance measurements

Modelisation influences only long

distance meas.

Page 21: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

21

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Other benefits of AT401

Longitudinal position

Radial deformation of dipoles

Sensor for a train ?

Stability to be solve

Targeting

Orientation of targets

robot

-0.0008

-0.0006

-0.0004

-0.0002

0

0.0002

0.0004

0.0006

0.0008

22250 22300 22350 22400 22450 22500 22550 22600 22650 22700

Devia

tion [

m]

Cumulative Distance [m]

Radial deformation of long dipoles

Page 22: THE SMOOTHING AND REALIGNMENT OF THE LHC...3 Sector78 of the LHC is very unstable Has to be surveyed and re-aligned very often LHC is critical as much in vertical as in Horizontal

22

AT401 measurements for smoothing the LHC

Quicker than standard ones

In horizontal

better global shape

almost as accurate as the ecartometry for relative position

In Vertical

Pb of vertical angles which are not in the specifications

Not possible to use it as a level for a long traverse

For relative positioning, almost as accurate as digital levelling

I would use it for H measurements but NOT for V ones until the vertical angles problem is solved

IWAA2012, 10-14 Sep. 2012, FNAL, Batavia D. Missiaen

Conclusions