the rtds simulation and analysis on csg operation characters of csg_the rtd… · the rtds...
TRANSCRIPT
THE RTDS SIMULATION AND ANALYSIS ON CSG OPERATION
CHARACTERS
Mengjun Liao, Weiqiang Han, Qi Guo, Yunwen Guo
Electrical Power Research Institute, China Southern Power Grid, Guangzhou, P.R.China 510000
Abstracts: Nuozhadu and Xiluodu DC transmission system in operation makes the AC/DC hybrid scale of CSG
enlarge to eight AC and seven DC transmission systems, which increases the complexity of AC/DC hybrid
transmission system operation. It’s indicates that the paralleled complex-circuit AC/DC hybrid transmission
system of CSG cannot be simulated accurately and cannot be analysed on some deeper problems by only using the
electro-mechanical transient simulation tools. This paper constructs the RTDS simulation platform of CSG above
220kV grid with 8 HVDC system, based on the closed loop connection and FDNE (Frequency Dependent
Network Equivalent), which recurs the electro-magnetic transient and response of (U)HVDC control and
protection system. At last the security risk assessment of multi-HVDCs commutation failures is present by this
simulation platform in some extreme AC fault.
Key words: Hybrid AC&DC power system, Real-time simulation, Interaction of AC&DC, Multi-HVDCs
commutation failure
1. Overview
China southern power grid (CSG) has institute
“eight HVDC and eight AC” pattern in the “West to
East” Power Transmission Project, while Nuozhadu
HVDC project and Xiluodu HVDC project are
operating in 2013. It operates one of the most
sophisticated and technologically advanced in the
world featuring long distance, extra high voltage and
hybrid AC&DC operation. Multi-HVDC projects
centre in the load area lead to complex interaction
between HVDC system and AC system, such as a
key issue of multi-HVDC commutation failure.
Considering a key factor of nonlinearity of HVDC
transmission system in the hybrid AC&DC operation,
traditional TSA (Transient Stability Analysis) may be
hard to simulate accurately in the electro-magnetic
transience of interaction between HVDC and AC
system and the response of control and protection
system. Therefore, this paper indicates to build a
real-time simulation platform of CSG to solve the
analysis issues of hybrid AC&DC operation. At last,
investigation about security risk of multi-HVDCs
commutation failure is present.
2. Feasibility and Challenge of Large Scale
Real-Time Simulation
2.1 Real-Time Simulation (RTS)
RTDS, RT-LAB, HYPERSIM and ADPSS are
typical RTS tools around the world. At the beginning
of being designed, they are used to verify actual
power system Control and Protection (C&P) devices
with hardware-in-loop (HIL) technology instead of
the traditional dynamic analog test. As an
Electro-Magnetic Transient (EMT) algorithm, RTS
simulates the real power system instant by building
the power model with high order differential
equation and partial differential equation. It is able to
respond nonlinearity of power electronic accurately.
Therefore, RTS presents significant advantages of
accurate simulation for HVDC and HIL technology
in hybrid AC&DC operation comparing with
TSA.[1]~[4]
2.2 Challenge of Hybrid AC&DC Operation
Real-Time Simulation
In hybrid AC&DC operation simulation, two
key issues below must be considered seriously: one is
the accurate modelling of HVDC transmission
system, including power electronic nonlinearity as
well as C&P response of HVDC. The other is
characteristic of large scale AC system. As
mentioned before, RTS presents significant
advantages of accurate simulation for HVDC and
HIL technology in hybrid AC&DC operation
comparing with TSA. However, the simulation scale
of RTS is limited to maintain the solution in real-time
which ensures HIL requirement strictly. Taking
Real-Time Digital Simulator (RTDS) as example,
there are specific limitations of node, component and
variable as well as interface channel number in each
unit of RTDS.
In the earlier investigation of power system, the
key issues of system stability concentrated upon the
generators electromechanical transient process to
judge whether two groups of coherent generators
would lose the synchronization during disturbance.
Power system researches usually reduce the AC
system scales in real-time simulation by equivalent
models. Dynamic equivalence of coherent generator
groups and network equivalence are two of the most
common methods. However, as an increasing of
system capacity and power electronic application,
new challenge arises in real-time simulation of
hybrid AC&DC system. One is the major factor of
power system stability turns to HVDC
electro-magnetic transience gradually from
generators electromechanical transient. Traditional
dynamic equivalence based on fundamental
frequency may lose the interaction characteristic of
high frequency. On the other hands, fast increasing of
AC system scales make dynamic equivalence more
difficulty than before.[5]~[6]
Some references present a new technology of
Frequency Dependent Network Equivalence (FDNE)
as an accurate solution of real-time simulation for
large scale power system. A wide-band multi-port
equivalence will be used to instead of less critical
power grid so that the simulation scales would be
decreased but a wide-band electro-magnetic
transience would be reserved in the simulation. In
this way, hybrid AC&DC power system is able to be
modelled in RTS [7~[9].
Considering advantages of RTS and FDNE
technology, this paper has build a real-time
simulation platform with whole transmission network
above 220kV based on RTDS. Some important C&P
devices of HVDC transmission projects and Special
System Protection (SSP) are HIL in the RTS
platform.
3. The RTS Platform with Whole Transmission
Network of CSG above 220kV
The RTS platform with whole transmission
network above 220kV is shown as Figure.1. It
includes eight HVDC transmission systems and their
C&P systems. Two sets of C&P systems are HIL and
the rest are used digital models in RTDS. Certainly,
other C&P systems can be switched as HIL
depending on different investigating objective. The
AC system models are separated into two parts. One
is electro-magnetic transient simulation model of full
power system surrounding the converter stations and
the “West to East” Power Transmission Project. The
other part is an equivalence of less important power
system using FDNE technology. By this way, it
decreases the simulation scales but maintains a high
simulation accuracy of hybrid AC&DC system.
HVDC Digital model
HVDC C&P model
HVDC C&P DeviceClosed-loop
BUS
Equivalence simulation Grid
using FDNE
Full EMT simulation Grid
HVDC SYSTEM AC SYSTEM
Fig. 1 Schematic diagram of the CSG RTS platform with whole
transmission network above 220kV
3.1 HIL of HVDC C&P System
HVDC transmission system modelling is the
most important section in the RTS platform. Power
electronics are full electro-magnetic transient
simulation models in RTDS, such as valve, converter
transformer, filters and so on. The parameters refer to
actual project. Set of C&P devices, including Station
Controller, Pole Controller, Pole Protection and so on,
are HIL with the specific GT interface cards. The
analogs of voltage and current as well as status of
breakers are sending to C&P devices by GT output
interface cards. After C&P system calculation,
references of alpha angle and orders of breakers
would be returned to the RTDS model for HVDC
operation.
Fig. 2 schematic diagram of HIL of HVDC C&P system
3.2 HIL of Special System Protection
In order to verify the C&P response of actual
power grid, some SSPs are necessary in the RTS
platform. Out-off-step separator, a system special
protection, is considered to be closed-in-the-loop,
which is used to separate power system into two
disconnected power grid to prevent instability of two
groups of coherent generators during disturbance.
Considering where oscillation between coherent
generators centres in the AC transmission lines due to
the multi-HVDCs commutation failure, out-off-step
separator of stations between Guangxi power grid
and Guangdong power grid are HIL in the RTS
platform.
3.3 Comparison of Simulation Result and PMU
Record
These years, there are some post-disturbances
in the multi-HVDCs infeed power grid leading to
multi-HVDCs commutation failures. With
comparison of simulation result and PMU record in
actual case, the RTDS simulation platform is proved
to be effective and high accuracy.
Figure 3.1 to 3.3 show a post-disturbance
simulation of “2012.8.11” failure. In this case, single
phase short-circuit was located on the T-line from
Zengcheng to Suidong Ⅱ which leaded to five
HVDCs commutation failure. Firstly, it is necessary
to adjust power flow and HVDC to meet the
operation before post-disturbance in the CSG RTS
platform with whole transmission network above
220kV. Then set a single phase short-circuit where it
was in “2012.8.11” failure. In this case, C&P systems
of YG UHVDC, TG HVDC and GG2 HVDC are
HIL in the RTS platform.
Fig. 3.1 The comparison of simulation result and PMU record –
YG HVDC power, voltage and current
Fig. 3.2 The comparison of simulation result and PMU record –
TG HVDC power
Fig. 3.3 The comparison of simulation result and PMU record –
power of AC transmission line
Table 1 shows the detailed difference of HVDC
commutation failure between simulation and actual
record. According to the simulation result and PMU
record, commutation failure of three HVDC projects
during post-disturbance present approximately same
response in power loss and recovery. Then, prony
method is taken to analyse the system oscillation
frequency and damping. The difference of oscillation
between simulation and actual record are shown as
Table 2.
Table 1 The detailed difference of HVDC
commutation failure
HVDC
PROJECT
Minimun power Recovery time
Simulation Record Simulation Record
YG UHVDC 0MW 0MW 177ms 158ms
TG HVDC 0MW 280MW 132ms 142ms
GG2 HVDC 1600MW 1800MW 58ms 22ms
Table 2 The detailed difference of oscillation
Transmission Line Oscillation Frequency Damping
Simulation Record Simulation Record
Wuzhou – Luodong I 0.37 Hz 0.36 Hz 6.6% 11.5%
Hezhou – Luodong I 0.36 Hz 0.37 Hz 6.5% 12.5%
Guilin - Xianlingshan I 0.37 Hz 0.36 Hz 7.3% 11.6%
4. Power system security risk of multi-HVDCs
commutation failure
As it shows above, short-circuit fault in
multi-infeed power system may lead to
multi-HVDCs commutation failure. As if this fault is
not able to be clear in time, multi-HVDCs
commutation failure will last longer and system
disturbance becomes more critical. Even, it will
cause system instability and damage.
In order to investigate the power system security
risk of multi-HVDCs commutation failure, this
section simulates largest load and power generation
of strict operation in RTS platform and sets a series
of faults about single phase short-circuit and
mid-breaker failure located in important 500kV
substations of Guangdong power grid.
The main electrical connection of 500kV
substation is shown as figure 4. Two transmission
lines or transformers are connecting to the electrical
buses of substation by three breakers. If a
short-circuit fault locates in LINE 2, breaker 5021
and 5022 will be open to clear the fault. However, if
the mid-breaker 5022 doesn’t open as well as
expected, the Breaker Failure Protection will be
active after a delay to open breaker 5021 and 5023.
At the same time, the relevant breakers of the other
side of LINE 2 and LINE 5 will be open, too. In this
situation, two transmission lines would be power off.
LINE 1 LINE 2 LINE 3
LINE 4 LINE 5 LINE 6
Short-circuit fault
#1 Bus
#2 Bus
5021
5022
5023
A
5011 5031
5012
5013
5032
5033
Fig. 4 The main electrical connection of 500kV substation
Take Beijiao 500kV substation as example.
According to the main electrical connection of Huad
substation, if a short-circuit fault and mid-breaker
failure locate in Beijiao-Zengcheng I transmission
line, Breaker Failure Protection acts after 300ms and
cut-off Beijiao-Zengcheng I transmission line and #1
transformer. As Figure 5 and Table 3 shown below,
eight HVDC projects present commutation failure at
the same time during this disturbance. The minimum
power of four HVDC projects reach 0 MW and all
HVDC projects take more than 344 micro-second to
be recovery. Because of the long-time multi-HVDCs
commutation failure, system becomes instable and
out-off-step oscillation is located in the AC
transmission lines of Guangdong section. As Figure 6
shown, about 3 seconds after the short-circuit fault,
Special System Protection acts and cut off the AC
transmission lines. Power grid is separated into two
disconnected parts.
Besides, system instability will be caused by a
short-circuit fault and mid-breaker failure in another
nine substations of Huadu, Suidong and so on.
Fig. 5 Simulation result of HVDC power
HVDC Project
Minimum Power
of HVDC
(MW)
Recovery
XLD HVDC 0 400ms
NZD UHVDC 820 462ms
YG UHVDC 0 618ms
GG2 HVDC 422 517ms
GG1 HVDC 0 344ms
TG HVDC 234 548ms
SG HVDC 0 370ms
Fig. 6 Simulation result of AC transmission lines of
Guangdong section
5. Conclusion
CSG operates one of the most sophisticated and
technologically advanced in the world featuring long
distance, extra high voltage and hybrid AC&DC
operation. Multi-HVDC projects centre in the load
area lead to complex interaction between HVDC
system and AC system. Facing the difficulty and
challenge of simulation of hybrid AC&DC power
system, this paper investigates to build a real-time
simulation platform for the whole transmission
network of CSG above 220kV. With comparison of
simulation result and PMU record in actual case, the
RTDS simulation platform is proved to be effective
and high accuracy.
Another investigation of this paper is power
system security risk of multi-HVDCs commutation
failure. Multi-HVDCs commutation failure will last
longer, or even lead to system instability if
post-disturbances in the multi-HVDCs infeed power
grid does not be clear in time. A series of single
phase short-circuits and mid-breaker failures in
important 500kV substations of Guangdong power
grid have been simulated in the RTS platform.
According to the simulation result, single phase
short-circuits and mid-breaker failures in Beijiao and
other nine substations may cause system instability in
strict operation of largest load and power generation.
References
[1] KUFFEL R, GIESBRECHT J, MAGUIRE T, et al. RTDS-A
Fully Digital Power System Simulator Operation in Real
Time[C]// Proceedings of First International Conference on
Digital Power System Simulators (ICDS’95), 5−7 April 1995,
College Station, TX, USA: IEEE, 1995: 19−24.
[2] DUCHEN H, AGERKVIST M, KUFFEL R, et al. HVDC
Simulation and Control System Testing Using a Real-Time
Digital Simulator (RTDS) [C]// Proceedings of First
International Conference on Digital Power System
Simulators (ICDS’95), 5−7 April 1995, College Station, TX,
USA: IEEE, 1995: 213.
[3] KUFFEL R, WIERCKX R P, DUCHEN H, et al. Expanding
an Analogue HVDC Simulator's Modelling Capability Using
a Real-Time Digital simulator (RTDS) [C] // Proceedings of
First International Conference on Digital Power System
Simulators(ICDS’95), 5−7 April 1995, College Station, TX,
USA: IEEE, 1995: 199.
[4] ANAYA-LARA O, ACHA E. Modeling and Analysis of
Custom Power Systems by PSCAD/EMTDC [J]. IEEE Trans
on Power Delivery, 2002,17(1):266−272.
[5] HEFFERNAN M D,TURNER K S,ARRILLAGA J,et al.
Computation of AC-DC System Disturbances, Part I:
Interactive Coordination of Generator and Converter
Transient Models [J].IEEE Trans on Power Apparatus and
Systems,1981,100(11):4341−4348.
[6] ANDERSON G W J. Hybrid Simulation of AC-DC
Power Systems [D].New Zealand:University of Canterbury,
1995
[7] Y. Liang, X. Lin, A. M. Gole and M. Yu, “Improved
Coherency-Based Wide-Band Equivalents for Real-Time
Digital Simulators”, IEEE Trans. Power syst., vol.26, no.3,
pp.1410-1417, 2011.
[8] X. Lin, A. M. Gole, and M. Yu, “A wide-band
multi-port system equivalent for real-time digital power
system simulators,” IEEE Trans. Power Syst., vol.24, no.1,
pp.237-249, 2009.
[9] B. Gustavsen, A. Semlyen. Enforcing Passivity for
Admittance Matrices Approximated by Rational Functions
[J]. IEEE Trans. on Power System, 2001,16(1): 97-104.
[10] HAN, Weiqiang, LI Zhangying, GUO Qi, et al.
Research on the Feasibility and Mode of RTDS Analysis of
Power System Operation. [J]. Southern Power System
Technology, 2010, Vol.4, No.3, pp: 51-56.
[11] LIAO Mengjun, GUO Qi, GUO Yunwen, et al. Study on
risk of system transient instability by breaker refused [J].
Southern Power System Technology, 2014, Vol. 8(S2):
199-204.