the role of energy savings in solving the current
TRANSCRIPT
Load shedding schedules
Stage Type Reduction obtained by interrupting supply -
load shedding
Reduction obtained by instructing reduction -
curtailment (pre-agreed)
Stage 070-100 MW
Unscheduled(pre-agreed)
Ad hoc Load offered by customers under the immediate curtailment option
(min 25% for 2 hrs)
Stage 1800-1300 MW
Scheduled / Notified
Shed 5% of national non-curtailment load at peak
Curtail 10% of normal demand within 2h of notification
Stage 21600-2100 MW
Scheduled / Notified
Shed 10% of national non-curtailment load at peak
Stage 33200-4400 MW
Scheduled / Notified
Shed 20% of national non-curtailment load at peak
Curtail 20% of normal demand within 2hrs of notification
Stage 4 Unscheduled(instructed)
Shed >20% of national non-curtailment load at peak
As instructed by the National System Operator at the time.
Research has been undertaken into the market potential for energy savings per technology
Technology Resid Comm Indus Total
Efficient Lighting 939 115 116 1,170Solar Water Heating 3,713 3,713
Domestic Cooking Conversion
2,144 2,144
Infra red heating 766 766Heat Pumps 960 224 569 1,753Showerheads & Restrictors
240 160 400
Load Management 9 200 209Heating, Ventilation & (HVAC)
14 70 84
Agricultural Initiatives 144 144Efficient Compressed Air 1,255 1,255Motor Efficiency 408 408Variable Speed Drivers 417 417Fan / Pumps 530 530
TOTAL 8,762 666 3,565 12,933
• The market’s total potential is the estimated maximum amount of demand savings that can be achieved in each technology class.
• The market potential was estimated in a recent research study conducted by EEDSM.
• In setting targets, the market penetration in any of the technology classes did not exceed 50% of the research finding’s maximum market potential.
• The above conservative target settings approach allows for market estimation accuracy, customer own projects and supply chain constraints.
EEDSM track record : verified average weekday energy savings impact for June 2006
Average Weekday Total and DSM Impact (MW): June 2006
-
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.000
:00
01:3
0
03:0
0
04:3
0
06:0
0
07:3
0
09:0
0
10:3
0
12:0
0
13:3
0
15:0
0
16:3
0
18:0
0
19:3
0
21:0
0
22:3
0
Time
MW
Total Impact DSM Impact
700
500
EEDSM efforts have displaced the equivalent capacity of a full power station
IDM cumulative performance over time (Measured and Verified savings provided for annual report 2013/14)
90 162 43
2 1082
1999 23
71 2725 30
72 3531 39
41
126
285
1004
2656
4343 49
06
6240
7590
9417
1078
0
0
2000
4000
6000
8000
10000
12000
2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14
EE has permanency / longevity - once implemented, the energy efficient solution is in place for the duration of the technology life.
Power Alert and supporting communication initiatives demonstrate justifiable, measureable and strategically timed energy savings
Power Alert, for which energy savings and as a result behaviour change impact can be measured, demonstrates that significant reach is required to translate into meaningful behaviour change.
Power Alert and its supporting campaigns deliver proven savings, cost effectively at times that are critical to the power system – but, requires CONTINUED focus and spend
October 2014 8
3.51
million people273 MW & 1,644MWh (June 2014)
Aware Motivational IntentionsRelevanceRelevanceKnowledge Behavior
Energy savings
Targeted messaging
Fresh creative
Frequency (high)
1
2
3
Critical inputs2 Ongoing refinement to sustain participation
Note 1. The measured MW impact suggests for every 100 people reached, ~8 responds by changing behaviour saving energy. This compares very well with international benchmarks for effecting positive behaviour change.
It has however consistently delivered demand and energy savings, strategically timed at very competitive costs compared to the available alternatives
9
Through the Power Alert, South Africans have contributed to keeping the lights on
Impa
ct –
MW
redu
ctio
n
Since its introduction in 2006, the Power Alert has consistently kept the South African public informed about the electricity supply situation and have effectively reduced the peak demand during weekday evenings by between 150 to 350 MWs (delivering as much as 450MWs peak demand reduction on occasion)
Average impact of Power Alert signals: April 20 – Dec 2014
64
143221
350
Demand Response
900MW reductionContracted for current DMP
Up to 2500MW reduction potential = DRAPP
Payment of a fixed rate for load reduction at fixed predetermined times.
Demand Market Participation (DMP) programme; Demand Response Aggregated Pilot (DRAPP) programme
DMPSize: Customers with 20-80MW demand reduction potentialMarket focus: Industrial
DRAPPSize: Customers with <10MW demand reduction potentialMarket focus: Small industrial and commercial
Multiple fixed rate per MWhR800/MWh – R1000/MWh.
Requires update
The IDM programme produces benefits at all levels of the economy and society…
Developmental contributions
Education and training
1,778
The IDM programme initiated a cultural and behavioural change amongst South Africans
85
33
The number of teachers reached via workshops since 2004
The number of learners receiving ESCO Development Programme Certificates
The number of building energy auditors certified through the Building Energy Auditors Training programme (BEAT)
Access to lighting
62 million The number of CFLs replaced since inception
Access to hot water
382,542 The number of SWH installed since inception
19,354The number of heat pumps installed since inception
Industrial Commercial / Agricultural
Residential
ESCO
PerformanceContracting
Standard Offer / SOP FLEX
Standard Product / Aggregated SPP
Residential Mass Roll-out
SWH / HP Rebate
Other Mass Rollout
IDM solutions sector coverageTECHNOLOGYKEY:
PRIORITY 1PRIORITY 2Priority 3
Industrial Process Optimisation, Fans Compressed Air, Shower Heads, Lighting
Process Optimisation, Lighting Heat Pumps, HVAC etc.
Energy SolutionsDemand
Solutions
Lighting, Hot Water Systems, Solar , Process Optimisation, Renewables
Lighting, Shower Heads, Industrial Heat Pumps
HP & LP Solar Water Heaters, Heat Pumps
CFL Sustainability and Fill-ins
“Mixed bag” of technologies
12
As national priority, multiple roleplayers are now promoting and participating in EEDSM initiatives
12 I Tax incentive + SANEDI and the dti
12 L Tax incentive + SANEDI and the DoE
Private Sector Energy Efficiency (PSEE) Initiative
+ National Business Initiaitive
Industrial Energy Efficiency Programme +
National Cleaner Production centre (NCPC)
Solar Water Heating (SWH) rebate +
Department of Energy
AfD Green Loan and Technical Assistance
Facility
Green Energy Efficiency Fund + IDC and kfW
DR and EEDSM + Department of Energy IPP
Procurement Office
Distributed and/or own generation increasingly part of the energy solution
Solar PV developments
The unofficial IRP 2013 update suggested that 22.5 GW solar PV from rooftop installations may be possible by 2030.
“Other” alternatives (incl. gas and cogen)
Note 1. Source: spheralsolar.com; Note 2. Fully indexed price in 2013 Rands; 15
Technology advancements and price trends are empowering the “Prosumer”
Capacity installed (kWp) – Feb 2015PV capacity that has been voluntarily reported and registered
National 25.8MW(excluding REIPPPP)
R2/kWh 3.10 1.85 0.99
BW 1 BW 2 BW 3
Price trends
Large scale Solar PV trends reported by the REIPPPP has shown a 68% drop in price from bid window (BW) 1 to bid window 3 (i.e. three consecutive years):
- 68%
Cellular major MTN South Africa has approved two gas-powered generation developments for its Doornfontein (1 MW) and Newlands (6 MW) sites, in Gauteng, based on the success of its 2 MW trigeneration plant at its Roodepoort headquarters.MTN will expand this methane-powered plant by another 5 MW within the next two years, which will meet all its baseload heating, cooling and electricity requirements of its head offices.
“MTN reduces power-price exposure with innovative self-generation schemes”3
Note 3. http://www.engineeringnews.co.za/article/mtn-reduces-power-price-exposure-with-innovative-self-generation-schemes-2014-09-26-1
EXAMPLE
Global(capacity cost):
$1/watt 1784 1.30 0.70
year 1953 2012 2015
- 99.9%International and local
Demand side levers: Funding and MW savings shortfall
16
Funding Shortfall
2013/14 2014/15 2015/16 2016/17 2017/18 TotalRequired Funding (Rm) 5,684 4,972 2,614 2,763 4,456 20,489 - Demand Response 1,168 688 752 797 844 4,249 - Base IDM 2,941 2,709 1,862 1,966 3,612 13,090 - RMR (not in NERSA submission) 1,575 1,575 0 0 0 3,150
NERSA Approved (Rm) 2,623 1,641 819 712 1,244 7,039 - Demand Response 1,168 688 0 0 0 1,856 - Base IDM 1,455 953 819 712 1,244 5,183
Shortfall (Rm) 3,061 3,331 1,795 2,051 3,212 13,450 - Demand Response 0 0 752 797 844 2,393 - Base IDM 1,486 1,756 1,043 1,254 2,368 7,907 - RMR 1,575 1,575 0 0 0 3,150
MW Shortfall
2013/14 2014/15 2015/16 2016/17 2017/18 TotalRequired MW Savings 1,270 2,168 2,629 2,861 3,322 3,322 - Demand Response 512 752 992 992 992 992 - Base IDM 458 816 1,037 1,269 1,730 1,730 - RMR 300 600 600 600 600 600
NERSA Approved (MW) 891 1,425 860 1,056 1,471 1,471 - Demand Response 512 752 0 0 0 0 - Base IDM 379 673 860 1,056 1,471 1,471 - RMR 0 0 0 0 0 0
Shortfall (MW) 379 743 1,769 1,805 1,851 1,851 - Demand Response 0 0 992 992 992 992 - Base IDM 79 143 177 213 259 259 - RMR 300 600 600 600 600 600
• The reduction of funding allocation to IDM requires delivery of 85% of the submitted demand savings target (MW), with only 40% of the applied for funding being approved.
• Over and above IDM core funding, R3.15bn will be required over the next 2 years to fund the RMR Programme to deliver savings in support of Keeping the lights on.
Expanding into social media
Our communication has necessarily expanded to include flash mobs, school programmes, social media - higher frequency, more platforms - more tv channels (linked to changing viewing patterns and pay for TV) and tools / apps.
Eskom Brand
46 696
70 356
Facebooklikes
Twitterfollowers
March 2015Facebook Fans/Twitter Followers
896 4566
Facebooklikes
Twitterfollowers
July 2013Facebook Fans/Twitter Followers
Experiments show consistent responsiveness to price
0%
10%
20%
30%
40%
50%
60%
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Peak
Red
uctio
n
Peak to Off-Peak Price Ratio
Enabling Tech
Price Only
Source: Brattle Group
Objective of Critical Peak Day Pricing
• Critical peak day pricing is a dynamic tariff that will contribute to Eskom's efforts to keep the lights on • by providing customers with pricing signals that enables customers to
respond to system constrained periods,• empowers customers to become active participants in demand response, and • encourages electricity savings.
• The objectives of introducing Critical Peak Pricing1 generally are:1. To provide a pricing signal that enables customers to respond to system
constrained periods and empowers customers to become active participants in demand response,
2. To manage a capacity shortfall, 3. To manage a shortfall in energy supply, 4. To encourage the efficient use of electricity,5. To improve the financial viability of the utility, 6. To lower total (demand and supply) energy costs, creating economy
efficiency 7. To improve customer service by allowing for informed customer decision
making21
1World Bank Dynamic Pricing Primer
Features of the Critical Peak Day tariff
22
• The CPD tariff assumes that the existing tariff structures (Miniflex, Ruraflex and Nightsave Small and Nightsave Rural) will not change, except on critical peak days, where:
• For a limited number of days per year (capped to 20 system constrained days per year):
• the customer will be charged higher energy prices during the critical peak hours of the day (6am to 10pm i.e. standard and peak periods)
• the remaining non-critical days of the year, the corresponding hours will have a lower/adjusted energy prices
• This tariff design feature:• provides a significantly stronger pricing signal that better reflects the
higher cost of generation during system constrained days• encourages customer to reduce, forgo, substitute or load shift electricity usage
during system constrained times, thereby avoiding potential load shedding• provides a direct price incentives for customers to benefit from the adjusted energy
rates for the remaining non-critical days, which is lower than normal tariff rates.• Ensures revenue neutrality (set at the level where the customer does not
change the consumption behavior patterns).
•
Pilot Findings and Results – definite load reduction and no signs of comeback load
230
50000
100000
150000
200000
250000
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Perc
enta
ge lo
ad r
espo
nse
[kW
]
7 days after 1 day after CPD 1 day before 7 days before
• Average of 27% load reduction in pilot customer responses.
• 7 days BEFORE and AFTER plus 1 day before and after the event – no signs of load shifting after the Critical Peak Day event.
• Agrees with customer survey: customers indicated they did no shifting, and reduced their electricity usage.
0
4 000
8 000
12 000
16 000
20 000
2004
/05
2005
/06
2006
/07
2007
/08
2008
/09
2009
/10
2010
/11
2011
/12
2012
/13
2013
/14
2014
/15
2015
/16
2016
/17
2017
/18
27 Million tons of Coal
24
Closing Thought:GWh 47,340 GWh. The electrical energy that has been
saved since inception of the IDM programme
Amount of coal ‘not burnt’
• There is a cost associated with every kWh of electricity that can not be supplied when electricity supply is constrained