the proposed alloystream manganese project at metalloys,...
TRANSCRIPT
AlloyStream Manganese Plant - Background Information Document © Cymbian Enviro – Social Consulting Services August 2007 1
The proposed AlloyStream Manganese Project at
Metalloys, Samancor Meyerton Works.
Reference Number: GAUT 002/07-08/N0553
Aim of the Project The proponent applying for the Environmental Impact Assessment (EIA) authorisation is Samancor
Manganese (Pty) Ltd (Metalloys). Samancor Manganese (Pty) Ltd in conjunction with Exxaro Resources (Pty) Ltd have formed a joint venture (AlloyStream Manganese Joint Venture) in order to construct and
operate an AlloyStreamTM technology furnace to produce manganese alloy commercially.
The AlloyStream Manganese Plant will be an 8.5 MVA gas / induction furnace that will produce
manganese alloy. In terms of the National Environmental Management Act (No 107 of 1998) Regulation
No. R. 386 & 387 (21 April 2006) and through consultation with the Gauteng Department of Agriculture, Conservation and Environment (GDACE) the project requires an Environmental Impact Assessment (EIA)
to obtain environmental authorisation.
Cymbian Enviro-Social Consulting Services have been appointed as the independent
environmental consultant, to manage the Environmental Authorisation Process. This
process includes the consultation with parties
that may be affected by, or have an interest,
in the project.
Purpose of this document:
� Provide Background Information regarding
the project.
� Provide an outline of the process being
followed in conducting the Environmental
Impact Assessment (EIA) Procedure.
� Inform members of the public of their
rights and responsibilities regarding participation in certain parts of the EIA
Procedure.
� Inform the public of the objective evidence surrounding the perceived impacts of the
proposed project.
� Assist the public to formulate their
comments in a manner that will ensure
that they can be afforded due attention in certain parts of the EIA procedure.
Kindly complete the attached form and return
it to the relevant Cymbian Enviro-Social Consulting Services representative before the
30th September 2007:
Cymbian Enviro-Social Consulting
Services
Konrad Kruger
P.O. Box 1676, Cresta, 2118 Johannesburg, South Africa
Tel : (011) 678 6680 Fax : 086 656 3883
E-mail : [email protected]
Background Information
Location
Metalloys, Samancor Meyerton Works, is located near the town of Meyerton in the Vaal
Triangle, approximately 70km south of the
Johannesburg Central Business District.
The proposed AlloyStream Manganese Plant
will be located within the Samancor Meyerton
Works, immediately west of the R59. The plant could be located on either Portion 4, 15,
63 or 74 of the farm Kookfontein 545 IQ and
can be reached from the R551, off the R59.
The Samancor Meyerton Works falls within the
jurisdiction of the Midvaal Local Municipality, which forms part of the greater Sedibeng
District Municipality. For the location of Samancor Meyerton Works, including the
alternative furnace locations, refer to Figure 2.
Existing Land Use
The current land use of the Samancor
Meyerton Works is heavy industrial.
Surrounding Land Uses
The land use surrounding Samancor Meyerton Works is industrial, agricultural and residential.
Alternative Locations
As part of the Scoping and EIA investigations five site alternatives are being investigated for
the proposed plant. Please refer to Figure 2 for a locality map of the different site
alternatives.
AlloyStream Manganese Plant - Background Information Document © Cymbian Enviro – Social Consulting Services August 2007 2
What does the project entail?
The project will entail the construction and operation of the AlloyStream Manganese Plant
and will comprise of:
� Raw Materials Handling equipment.
� An 8.5 MVA gas / induction furnace.
� A delivery system, including:
o Metal & Slag handling.
o Off-Gas handling system.
o Secondary dust and fume handling
system.
� Service equipment, such as:
o Cooling water system.
o Electrical supply system.
o Control system.
Process overview
The AlloyStream Manganese Plant utilises the AlloyStream™ pyro-metallurgical technology to
produce manganese alloy from manganese ore fines. AlloyStream is not competing with the
existing manganese alloy smelting technology,
but rather complements these plants. It is expected to make a notable contribution towards
the improved utilisation of South Africa’s mineral wealth by allowing the beneficiation of ores that
previously had limited use in traditional smelting technologies.
The feed materials for the AlloyStream process
comprise of ore, coal and flux. The feed material is fed to the furnace similar to the
method used by the established manganese alloy submerged arc furnace industry. The main
difference between AlloyStream and other technologies is that AlloyStream can process
previously unused resources.
Inside the furnace the ore, coal and flux is
heated. Carbon from the coal reacts with the iron and manganese oxides to form the
manganese alloy. The gangue in the feed
material melts to form liquid slag. Metal and
slag is tapped from the furnace while gas and
dust is continuously extracted and cleaned with
an off-gas bag filter.
Heat for this high temperature process is
supplied as a combination of electrical energy and chemical energy. Process gasses are
combusted inside the furnace to optimise energy
utilisation and to ensure that product gas from
the process has the minimum impact on the
environment.
Process to be followed
In terms of Government Notice Regulation 387
of the Environmental Impact Assessment (EIA)
Regulations (2006), promulgated in terms of Section 24(5) of the National Environmental
Management Act (No. 107 of 1998), the
proposed development is subject to a Scoping
and EIA Procedure, which entails the following:
� Public Participation Process as described in
Regulation 56 of the EIA Regulations, 2006;
� Identification of potential environmental
impacts;
� Compilation of a Scoping Report in
accordance with Regulation 29 of the EIA
Regulations, 2006;
� Compilation of an Environmental Impact
Assessment Report in accordance with
Regulation 32 of the EIA Regulations,
2006;
� Undertaking of Specialist Studies Report in
accordance with Regulation 33 of the EIA
Regulations, 2006; and
� The compilation of an Environmental
Management Plan (EMP) in accordance
with Regulation 34 of the EIA Regulations,
2006.
The final EIA report will include details on all specialist studies undertaken. This report will
provide sufficient information to facilitate
decision-making by the designated Authority.
Process flow diagram of the furnace is shown in Figure 1.
AlloyStream Manganese Plant - Background Information Document © Cymbian Enviro – Social Consulting Services August 2007 3
Authority Pre-consultation
A pre-consultation meeting will be arranged with all relevant authorities. The purpose of the
meeting will be to communicate the nature of the project, and obtain guidance from
Authorities in terms of the project process and
deliverables.
Stakeholder Engagement Initiation Phase
During this phase stakeholder engagement activities will commence. This will include the
compilation of necessary Background
Information Documents (BID’s), advertisements,
site notices, and notification letters.
The issues raised during this phase will be collated into a stakeholder database and an
issues report will be generated.
Scoping Phase
The Scoping Phase brings together the issues
received during stakeholder engagement, and the planning phases of the Environment Impact
Assessment. During this phase all issues and comments identified are evaluated, and the
“Scope” of further studies is determined.
The Scoping Report will describe the stakeholder engagement process and will have the Issues
Report attached for review by the Authorities. In addition, the Scoping Report will:
� Describe the proposed development and
reasonable alternatives;
� Describe the property on which the activity
is proposed to take place;
� Describe the environment (at a screening
level) that may be affected by the activity
and the manner in which the physical,
biological, social, economic and cultural
aspects of the environment that may be affected by the proposed activity;
� Identify all legislation and guidelines that
have been considered in the preparation of the Scoping Report;
� Describe the environmental issues and
potential impacts that have been identified;
� Indicate the methodology that will be
adopted in assessing the potential impacts that have been identified, including any
specialist studies or specialised processes
that will be undertaken;
� Detail the stakeholder engagement
process; and
� Include all proof of stakeholder
engagement.
A draft copy of the Scoping Report will be made available for stakeholder review, prior to
finalisation and submission of the report.
Environmental Impact Assessment
The EIA Report will include:
� A detailed description of the proposed
development;
� A description of the need and desirability
of the proposed development and the
identified potential alternatives to the
proposed activity;
� A description of the environment that may
be affected by the activity and the manner
in which physical, biological, social, economic and cultural aspects of the
environment may be affected by the proposed development;
� A summary of the findings of the specialist
studies;
� A summary of the methodology used in
determining the significance of potential
impacts;
� A detailed assessment of all identified
potential impacts, including a comparative
assessment of identified land use and
development alternatives;
� Identified mitigation measures;
� Copies of all specialist reports will be appended to the EIA report; and
� Any further information that will assist in
decision making by the Authorities.
Specialist Studies
The following specialist studies have been
identified thus far:
� Traffic impact assessment;
� Air quality impact assessment;
� Health risk assessment;
� Technical Review; and
� Noise Impact Assessment.
Environmental Management Plan (EMP)
The EMP will contain the following information:
� Information on the proposed management or mitigation measures that will be
undertaken to address the environmental impacts that have been identified in the
EIA Report, including environmental impacts or objectives of:
o Planning and design;
o Pre-construction and construction
activities;
o Operation or undertaking of the
activity;
o Rehabilitation of the environment; and
o Closure, where relevant.
AlloyStream Manganese Plant - Background Information Document © Cymbian Enviro – Social Consulting Services August 2007 4
� A detailed description of the aspects of the
activity;
� An identification of the persons who will be
responsible for the implementation of the EMP;
� Where appropriate, time periods within
which the measures in the EMP must be
implemented; and
� Proposed mechanisms for monitoring
compliance with the EMP and reporting
thereon.
Stakeholder Review prior to Submission
Once completed, the draft report including the
environmental impact assessment and management programme, will be made available
at public places for stakeholder review. Comments from stakeholders will be utilised to
finalise the report for submission to Authorities.
Submission and Decision-making
The report will be finalised and submitted to the
various Authorities for decision-making. Their decision will be provided in a written Record of
Decision (ROD). Once the ROD has been received, an advertisement will be placed in a
local newspaper, notifying the public of the ROD and where it will be available to view.
Relevant Authorities
The authorities responsible for administering and
implementation of the above legislation are:
� The Gauteng Department of Agriculture,
Conservation and Environment;
� The Midvaal Local Municipality
� The Sedibeng District Municipality
� Department Environmental Affairs and
Tourism; and
� The Department of Water Affairs and
Forestry.
How can you get involved?
� Register as an Interested and Affected
Party by completing the attached
comment response form;
� Propose ideas to solve problems that arise
during the consultation process;
� Voice your concerns about proposals and
their potential impact; and
� Assist with information that will contribute
to a thorough study.
The Roles and Responsibilities of the Stakeholder
Registered stakeholders have the right to bring to the attention of the competent authority any issues that they believe may be of significance to the consideration of the application. The rights of stakeholder are qualified by certain obligations, namely: 1. Stakeholders must ensure that their comments are submitted within the timeframes that have been approved by
the GDACE, or within any extension of a timeframe agreed by the applicant or Environmental Assessment Practitioner (EAP);
2. A copy of comments submitted directly to the competent authority must be served on the applicant or EAP; and 3. Any direct business, financial, personal or other interest that they might have in the approval or refusal of the
application must be disclosed. The roles of stakeholders in a public participation process usually include one or more of the following:
• Assisting in the identification and prioritisation of issues that need to be investigated; • Making suggestions on alternatives and means of preventing, minimising and managing negative impacts and
enhancing project benefits; • Assisting in or commenting on the development of mutually acceptable criteria for the evaluation of decision
options; • Contributing information on public needs, values and expectations; • Contributing local and traditional knowledge; and
• Verifying that their issues have been considered. In order to participate effectively, stakeholders should: • Become involved in the process as early as possible; • Register as a stakeholder; • Advise the EAP of other stakeholders who should be consulted; • Contribute towards the design of the public participation process (including timeframes) to ensure that it is
acceptable to all stakeholders; • Follow the process once it has been accepted; • Read the material provided and actively seek to understand the issues involved;
• Give timeous responses to correspondence; • Be respectful and courteous towards other stakeholders; • Refrain from making subjective, unfounded or ill-informed statements; and • Recognise that the process is confined to issues that are directly relevant to the application.
Figure 2: Location of the proposed Alternative AlloyStream Manganese Project Sites
REGISTRATION / COMMENT FORM
PROJECT REFERENCE NO: ESC 167
AlloyStream Manganese Plant - EIA
PLEASE COMPLETE AND RETURN THIS FORM SO THAT WE HAVE YOUR COMPLETE
CONTACT DETAILS
Closing date for comments: 30th September 2007
PARTICULARS OF STAKEHOLDER Name
Postal
Address
Post code:
Street
Address:
Post code
Tel: E-Mail
Cell: Fax
Language Preference
COMMENTS DATE:
If you are aware of any people who should be contacted in this process, please
provide their details here:
Please add additional pages if required.
Return to: Konrad Kruger
Cymbian Enviro – Social Consulting Services
PO Box 1676
Cresta
2118
Tel : (011) 678 6680
Fax : (086) 656 3883
Email : [email protected]