the israel electric corporation ltd. organization, …

184
Appendix A1 SPECIFICATION SR-152 A1 - 1 THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION QUALITY CONTROL UNIT Q - APP - 02 4 03/ 2011 PAGE 1 FROM 6 Spec. No. Rev. Status Volume APPENDICES FOR CONTRACTS / ORDERS TITLE QUALITY REQUIREMENTS SUB TITLE QUALITY REQUIREMENTS 1. GENERAL 1.1 In addition to the provisions of the General Conditions Annexure "A" and without derogating from the generality there, the Quality Requirements as specified in this document constitute an integral part of the Contract between the Purchaser and the Contractor. Implementing these requirements shall not constitute any base/reason, for the Contractor to change the Contract schedule and/or price. 1.2 The Contractor shall make all the necessary arrangements and prepare all the required and necessary means to enable IEC's Quality Control Unit Representative (see clause 2) to review, observe, audit, inspect, test and survey the Work - at any facilities where Work or any part thereof is performed, including those of Contractor and Sub- Contractors, without any additional cost to the Purchaser or any change in the Contract schedule. 1.3 The Contractor shall nominate, as part of the execution of the Contract a quality engineer or a quality specialist to control and manage the quality requirements of the Contract. This person shall have the authority and responsibility with respect to all quality requirements of the Contract (including notifying the Purchaser about inspections, tests, etc.) and shall serve as Purchaser's liaison for quality matters. 1.4 The Contractor shall be responsible that all of the Contract’s quality requirements are known, accepted and performed by its Sub- Contractors. Special attention should be given to Contractor's procurement control and its Sub- Contractor's design control, process and manufacturing control, purchasing control, nonconforming material/events control and inspection notification. Upon Purchaser's request Contractor shall submit un-priced copies of purchase orders pertaining to the Work/Contact. PREPARED BY CHECKED BY APPROVED BY B. Ben-Akiva Q.C. UNIT QUALITY ENGINEERING Y. Shubinsky Q.C. Dept. - North MANAGER R. Bandel Q.C. UNIT MANAGER DATE AND SIGNATURE: 06/03/2011 DATE AND SIGNATURE: 06/03/2011 DATE AND SIGNATURE: 06/03/2011

Upload: others

Post on 16-Oct-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 1

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT Q - APP - 02

4 03/ 2011

PAGE 1 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS

TITLE

QUALITY REQUIREMENTS

SUB TITLE

QUALITY REQUIREMENTS

1. GENERAL

1.1 In addition to the provisions of the General Conditions – Annexure "A" and without derogating from the generality there, the Quality Requirements as specified in this document constitute an integral part of the Contract between the Purchaser and the Contractor. Implementing these requirements shall not constitute any base/reason, for the Contractor to change the Contract schedule and/or price.

1.2 The Contractor shall make all the necessary arrangements and prepare all the

required and necessary means to enable IEC's Quality Control Unit Representative (see clause 2) to review, observe, audit, inspect, test and survey the Work - at any facilities where Work or any part thereof is performed, including those of Contractor and Sub- Contractors, without any additional cost to the Purchaser or any change in the Contract schedule.

1.3 The Contractor shall nominate, as part of the execution of the Contract a

quality engineer or a quality specialist to control and manage the quality requirements of the Contract. This person shall have the authority and responsibility with respect to all quality requirements of the Contract (including notifying the Purchaser about inspections, tests, etc.) and shall serve as Purchaser's liaison for quality matters.

1.4 The Contractor shall be responsible that all of the Contract’s quality

requirements are known, accepted and performed by its Sub- Contractors. Special attention should be given to Contractor's procurement control and its Sub- Contractor's design control, process and manufacturing control, purchasing control, nonconforming material/events control and inspection notification. Upon Purchaser's request Contractor shall submit un-priced copies of purchase orders pertaining to the Work/Contact.

PREPARED BY CHECKED BY APPROVED BY

B. Ben-Akiva Q.C. UNIT QUALITY

ENGINEERING

Y. Shubinsky Q.C. Dept. - North

MANAGER

R. Bandel Q.C. UNIT MANAGER

DATE AND SIGNATURE : 06/03/2011

DATE AND SIGNATURE : 06/03/2011

DATE AND SIGNATURE :

06/03/2011

Page 2: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 2

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT Q - APP - 02

4 03/ 2011

PAGE 2 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS

TITLE

QUALITY REQUIREMENTS

SUB TITLE

2. DEFINITIONS, CLASSIFICATIONS AND ABBREVIATIONS.

2.1. CORRECTIVE ACTION (CA) – As defined in ISO 9000:2005.

2.2. QUALITY PLAN (QP) - Plan, prepared by the Contractor especially for the Contract, in accordance with ISO 10005 which covers all Contract stages.

2.3. INSPECTION AND TEST PLAN (ITP) – a plan, specifying all the inspections and tests for the Work throughout all Contract stages (from its initialing through design, in process inspection, type tests, product qualification, first article inspection, final inspection/s and test/s, packing, transportation and supply to the Purchaser, erection - including Site Acceptance Test and commissioning). ITP shall also specify Witness and Hold Points.

2.4. WITNESS POINT (WP) - a planned visit of the QCUR for purposes indicated in clause 1.2 for specific point of the ITP or Quality Plan.

2.5. HOLD POINT (HP) – the same as WP but with the distinction that the Contractor is not permitted to proceed with its planned activities without having received Purchaser’s written approval.

2.6. NON CONFORMANCE (NC) - deviation from any specified Contract requirement/s and/or from any quality characteristic of the Work.

2.7. NON CONFORMANCE REPORT (NCR) - a report, on Contractor’s numbered serial form, describing the details of a Non conformance, from its detection through disposition and corrective action(s).

2.8. QUALITY CHARACTERISTIC – Any identifiable property of the Work (i.e. physical ,chemical, functional, visual, technical, environmental, economical, statistical, legal etc.)

2.9. WORK - Scope of the Contract and the means to execute it.

2.10. QCUR - the Purchaser's Quality Control Unit Representative and/or any authorized representative of it.

2.11. SPECIAL PROCESS - Irreversible manufacturing processes or processes which require special or specific tools.

Page 3: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 3

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT Q - APP - 02

4 03/ 2011

PAGE 3 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS TITLE

QUALITY REQUIREMENTS

SUB TITLE

3. QUALITY PLAN AND INSPECTION AND TEST PLAN

3.1 The Contractor shall prepare QP and ITP for all stages of the Contract. These plans shall be submitted to the Purchaser for approval within fourteen (14) days of initialing of the Contract by the parties. Contractor shall not amend, change or alter any part of the QP and/or ITP without the prior written approval of the Purchaser. Note: ITP shall conform to Exhibit 'A' attached hereto or any other form approved by the Purchaser.

3.2 Contractor shall not commence work prior to receiving Purchaser’s written approval to the QP and ITP.

4. DOCUMENTATION

4.1 The Contractor shall submit to the Purchaser for review, along with the QP and ITP, its quality and manufacturing/operations procedures that pertain to the Work execution. The Purchaser has the right to receive explanations with respect thereto. Contractor shall provide Purchaser with all amendments and/or updates of documentation.

4.2 Special documents such as process procedures and inspection/test procedures written specifically for the Contract shall be submitted to the Purchaser, for review, comment and approval in accordance with Contract until the date agreed in there, but not less than twenty-one (21) days prior to its use.

4.3 The Contractor shall submit to the Purchaser, for review, comment and approval (as required by the Contract) all the process qualifications and the employees certifications for special processes which pertain to the Work and are relevant to the Contract execution.

4.4 Supplying Work which is not manufactured by the Contractor (under Contract terms) and which he has no control over the manufacturing process, shall not derogate from Contractors responsibility to supply the Purchaser with the documentation and quality records as indicated in Articles 4 and 7

Page 4: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 4

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT Q - APP - 02

4 03/ 2011

PAGE 4 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS

TITLE

QUALITY REQUIREMENTS

SUB TITLE

5. INSPECTIONS AND TESTS

5.1 The Contractor shall have available all test and inspection equipment and/or any other means, required in Purchaser’s opinion, for the execution of Work and ITP.

5.2 If Contractor uses the services of a Sub - Contractor to carry out any test/inspection required by the Work, only inspection companies certified to EN 45004 (level A or C) are acceptable.

5.2.1 Type test, Routine Test and Sample test shall be carried out according to Contract requirements.

5.3 Any other qualification test (for mechanical equipment) shall be carried out in the presence of the QCUR, followed by all quality records. The serial manufacturing shall commence only after 1st Article/piece test have successfully carried out witnessed by the Purchaser's QCUR.

6. INSPECTION NOTIFICATION

6.1. The Contractor shall indicate each inspection/test and notify the Purchaser of it in advance. An ITP schedule (on a GANT form) shall be prepared by the Contractor, within six (6) weeks after initialing of the Contract. Indications of inspection/test dates may in any event not be less than six (6) weeks in advance. Both inspection/test notification and ITP schedule shall be reported to the Purchaser's Project Management. In addition to the above ITP schedule, Contractor shall submit to Purchaser a final notice of planned tests/inspections not less than twenty-two (22) Israeli working days in advance.

6.2. Should Contractor fails to notify the Purchaser of a planned inspection/test, as required, or in the event Contractor carries out a test/inspection without the required presence of the QCUR, Purchaser shall have the option of demanding that Contractor re-perform the test/inspection in the presence of QCUR at a time convenient to Purchaser and at no additional cost..

7. QUALITY RECORDS

7.1. The Quality Records stipulated in this clause shall be, either in Hebrew, in dual/multi-language form with English, in English only, or if not available translated to English by Contractor.

7.2. Contractor shall submit to the Purchaser copy of the quality records documenting the inspections, tests or other quality operations of the Work, as indicated in the ITP, QP and the Contract. All quality records of skipped or missed WP and/or HP shall be submitted to Purchaser immediately after their generation.

Page 5: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 5

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT

Q - APP - 02 4

03/ 2011 PAGE 5 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS

TITLE

QUALITY REQUIREMENTS

SUB TITLE

7.3. All Test and Inspection Certificates/ Reports of materials, operations and or inspection/test, purchased or carried out for the Work and/or required by the applicable Standards, shall be submitted to the Purchaser immediately following their generation. These Certificates/Reports shall be original, in accordance with EN 10204:2004-3.1, containing actual measured values, signed and attested by Contractor. For any other document type, Contractor has to get Purchaser permission in advance.

7.4. Contractor shall make available to Purchaser upon its request, for review and comment, at Purchaser’s premises or other mutually agreed place (in Israel), the quality records of any - Type test, Routine test, Qualification test, First Article Inspection/Test, Process qualification, Special process and/or any other inspection/test/examination required by Purchaser, after initialing of the Contract, to evaluate the Work (at all stages) regardless of the QP and the ITP.

7.5. Submission of the documents and quality records, regarding the Equipment to which the documents relate, to Purchaser, as specified in Articles 4 and 7, shall be a condition, precedent to shipment by Contractor and payment by Purchaser.

7.6. Quality records of inspections/tests and/or of process control and process evaluation pertaining to a Work such as shelf item, standard Equipment and/ or already completed Equipment to be supplied to Purchaser between 30 to 120 days after execution of the Contract, shall be immediately submitted to the Purchaser or at least 60 days prior to packing for shipment, respectively.

8. HANDLING OF NONCONFORMANCES AND CORRECTIVE

ACTIONS

8.1. It is Purchaser's policy to reject Work and/or Goods that do not conform to all contractual requirements, unless acceptance is in the best interests of Purchaser. Acceptance of nonconforming Work or Goods is the sole prerogative of Purchaser.

8.2. It is the Contractor’s obligation to report to Purchaser about any nonconforming item/event which pertain to the Work and are relevant to Contract execution.

8.3. If the Contractor fails to report about a non conformance on time, Purchaser may request Contractor to dismantle the nonconforming Work (to witness the NC) with no additional cost. The documentation and quality records concerning this NC shall be immediately submitted to the Purchaser.

8.4. Each NC should be followed by corrective action/s (CA). A NC which is not followed by CA shall be rejected.

8.5. Deviating from 8.4 can cause stoppage of the Work and its rejection till the proper CA is taken by the Contractor.

Page 6: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A1 SPECIFICATION SR-152

A1 - 6

THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, QUALITY AND SAFETY DIVISION

QUALITY CONTROL UNIT Q - APP - 02

4 03/ 2011

PAGE 6 FROM 6

Spec. No. Rev.

Status Volume

APPENDICES FOR CONTRACTS / ORDERS

TITLE

QUALITY REQUIREMENTS

SUB TITLE

EXHIBIT A I&T Plan FORM

CONTRACTOR'S: NAME, I&T PLAN TITLE, THE PRODUCT INSPECTED/TESTED, and DOCUMENT IDENTITY & APPROVAL.

PURCHASER'S: NAME AND PROJECT''S NAME AND LOCATION.

No.

THE

INSPECTION OR

TEST

APPLICABLE DCUMENTS

WP/HP OR

OTHER

INSPECTED / TESTED BY

THE REPORT /

CERTIFICATE AND

ITS REF. STD/ PROCEDURE

REMARKS SUB- CONT./ SUPP

CONTR- ACTOR

PURCH-

ASER

OTHER

APPROVAL BY THE CONTRACTOR'S QUALITY ASSURANCE/CONTROL

NOMENCLATURE:

Page 7: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 1

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 1 of 7

DATE: (09/03/07) Revised: June 2012

SPECIFICATION FOR PAINTING ON GALVANIZED SURFACES Appendix 1.BY WET or ELECTROSTATIC POWDER PAINTING

1. SCOPE

This specification covers the requirements for painting of steel surfaces hot

dipped or electrolytically galvanized.

Galvanized steel shall be protected by paint (duplex system) except for

threaded items such as nuts and bolts which will be chromated according to

the instructions of the laboratory of materials.

Painting on galvanized surfaces may be problematic and a test patch is

recommended in order to assure a proper adhesion of the primer on the

prepared surface.

In each project it's recommended to enable a patch test before the work.

The project manager will choose the painting system according to the

environment and to the kind of galvanized layer.

2. SURFACE PREPARATION

2.1. On hot dip Galvanized items

2.1.1. Solvent cleaning

Cleaning all surfaces from dirt, dust, oil, grease using a

suitable solvent to SSPC SP-1.

Approved “Chemitaas” products: “Ardox 6-551”, BC-70 or

similar products of other manufacturers.

Page 8: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 2

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 2 of 7

DATE: (09/03/07) Revised: June 2012

2.1.2. Surface treatment

By one of the following methods:

A. Brush-off blast cleaning

According to SSPC-SP-7 specification.

Will be performed only by authorized workers.

Authorization shall be granted after ability to perform

roughening of the zinc coating and remove no more

than 10 microns of the zinc layer. The zinc layer

thickness shall be examined before and after blasting.

B. Chemical treatment

Submerging the item in a phosphating bath type “ZINC-

PHOSPHATE” conforming to BS. 3189-1991standard.

2.2 On electrolytically galvanized items

2.2.1 Solvent cleaning

According to par. 2.1.1.

2.2.2 Surface treatment By one of the following methods:

A. Mechanical

The surface shall be roughened to a degree suitable

for the specified paint system.

Approved surface cleaning media are listed in par. 7.4.

B. Chemical treatment according to par. 2.1.2B.

Page 9: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 3

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 3 of 7

DATE: (09/03/07) Revised: June 2012

3. PAINTING

ENVIRONMENT SUBSTRATE PAINTING SYSTEM THICKNESS

MICRON REMARKS

3.1 Internal location

or external in a

dry environment

3.1.1 Hot dip

galvanizing

zinc layer

thickness

over 80

micron

3.1.1.1 Liquid paints

Epoxy polyamide

modified special for

galvanizes surfaces / two

component aliphatic

polyurethane.

40

50

See par. 4.1 for

approved

manufactures and

products see par.

6.1 and 6.2 remarks

Total 90

3.1.1.2 3.1.1.2

Electrostatic

power painting

with pure

polyester

powder

Total

60

60

See par. 4.2 for

approved

manufacturers and

products.

See par. 5 technical

requirements.

3.1.2

Electrolyticaly

galvanizing

20-40 micron

zinc layer

thickness

3.1.2.1 Liquid paints

Epoxy

polyamide

modified

special for

galvanized

surfaces

70

See par. 4.1 for

approved

manufactures and

products

Two component

aliphatic polyurethane.

50 See par. 6.1, 6.2

Remarks.

Total 120

` 3.1.2.2 Electrostatic

powder

painting with

pure polyester

powder

80 See par. 4.2 for

approved

manufactures and

products.

See par. 5 technical

requirements. Total 80

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 4 of 7

DATE: (09/03/07) Revised: June 2012

Page 10: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 4

ENVIRONMENT SUBSTRATE PAINTING SYSTEM THICKNESS

MICRON REMARKS

3.2 External

location marine

or industrial

fume

environment

3.2.1 Hot dip

galvanizing

zinc layer

thickness

over 80

micron

3.2.1.1 Liquid paint

epoxy

polyamide

modified special

for galvanized

surfaces

70 See par. 4.1 for

approved

manufactures and

products.

Two component

Aliphatic

Polyurethane

50

See par. 6.1 and 6.2

Remarks

3.2.1.2 Electrostatic

powder painting

Prime: Epoxy powder.

Top: pure polyester

powder

Total

60

60

120

See par. 4.2 for

approved

manufacturer.

See par. 5 technical

requirements.

External location

marine or industrial

fume environment

3.2.2

Electrolitically

galvanizing 20-

40 micron zinc

layer thickness

3.2.2.1 Epoxy

polyamide

modified special

for galvanized

surfaces.

Two component

aliphatic

polyurethane

Total

100

50

150

See par. 4 for

approved

manufacturers and

products.

3.2.2.2 Electrostatic

powder painting

Prime: Epoxy powder.

Top: pure polyester

powder

Total

60

60

120

See par. 4.2 for

approved

manufacturers.

See par. 5 technical

requirements.

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 5 of 7

DATE: (09/03/07) Revised: June 2012

4. Paint manufactures and products approved

Page 11: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 5

4.1 Wet painting procedure above galvanized surface

Top Primer Manufacturer

Tamaglass PU

(Aliphatic)

Epitamarin Uniseal

brown

code – 842-xx

or

Epogal

code – 644-xx

Tambour

Unicryl Epoxy Primer 524 Nirlat

Carboline 134 Rust Bond Penetrating

Primer Carboline

ACROLOM 218 Duraplate 235 Sherwin williams

Amercoat 450 S Amercoat TC 71 Ameron

Sigmadur 520

Sigmacover 522

Or

Sigmacover 280

Sigma

Interthane 990 Interguard 269 International

Vigor PU 239 Vigor EP 201C Freitag

4.2 Electrostatic powder painting

Remarks Product name Manufacturer

185-xxx Polyester powder Shamir Tambour

series 7000 Polyester powder Unilac Nirlat - Univercol

Polyester powder David Powders

Page 12: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 6

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 6 of 7

DATE: (09/03/07) Revised: June 2012

5. Technical Requirement for electrostatic powder painting

Laboratory tests will be carried out on panels measuring 100 x 150 x 0.7 mm.

5.1 Thickness of Coating

At least 80 Microns. The test to be according to SSPC-PA1/1982.

5.2 Adhesion

Pull-off according to ASTM D 4541-85. Test dolly 20 mm. Using Acrylic

Adhesive (DP-805, Scotch-weld or equivalent). Minimum 1000 psi.

5.3 Hardness

Hardness of coating to scratching: 4000 gr. According to ISO R 1518.

5.4 Impact

According to ASTM D-2794: 25 Kg/cm. Will not be every cracking of the

coating, nor any detachment from the substrate.

5.5 Extensibility

ISO-1520-Erichsen Cupping: 6 mm without cracks or detachments.

5.6 Permeability

A coated panel will be partially submerged in pressure cooker containing

distilled water to a level of at least 25 mm. Cooking at least for two hours

after the appearance of steam.

After cooling of the cooker and the panel, the coating should be

examined: no bubbles should appear on the surface. (They are acceptable

only near the edges).

5.7 Resistance to Salt Spray Fog:

Three panels will be placed in al salt water chamber for 1000 hours after

being cross-cut in the center of the plate with an X, 50-70 mm long. After

drying for 24 hours at room temperature, adhesion to the cross-cut will be

examined.

Spread of rust along the lines and separation of the coating must not

exceed 2 mm. There must be no bubbles or rust spots on the surface

remote from the cut and the edges of the plate.

Page 13: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A2 SPECIFICATION SR-152

A1 - 7

THE ISRAEL ELECRIC CORPORATION

GENERATION DIVISION

CHIEF CHEMIST DEPT.

SPEC/PROCEDURE: CL-716/1600/99

ISSUE – 5

PAGE No. 7 of 7

DATE: (09/03/07) Revised: June 2012

6. Quality assurance

Is based on the authorization of the process and manufacturer that shall be granted

after ability to supply panels that will conform the requirements specified in par.5.

During the fabrication only thickness off the coating will be checked. There are not

permitted measurements under the specified thickness in par.5.1.

REMARKS

1. Damaged hot dip galvanized surfaces must be repaired by applying at least

two coats of organic zinc rich coatings to give a minimum dry film thickness

of 60 micron.

Approved products:

“Z.R.C” – I.E.C - distributor carmel handasa catalog no. 3560067

“ZINGA” - distributor m.b.l catalog no. 3560067

ZINC-GLAD 5 - distributor Chemital catalog no.3560067

GLAVITE 90 E - distributor tambour catalog no.3560067

2. In the painting system will be involved only paints from the same manufacturer

3. Every two successive coats must be colour contrasted.

4. I.E.C. will approve only paint products that permit over coating with the

paints specified in par 4.1.1. The result of adhesion test performed after over

coating according to Israeli Standard 785/27 will be at least level 1.

5. Surface profile producing media recommended: non-woven abrasive

wheels and discs such as: 3 M Scotch-Brite clean strip discs and wheels.

Coated abrasive discs (sending pads) as: Flap wheels such as: Grind 0

Flex Wheels from Merit Corporation

Needle guns consisting of a bundle of wire “needles” which can impact

the surface.

Prepared: Approved:

Y. Casapu

Dr. E. Sutskover

Revised by Shay Litani (June 2012)

Page 14: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 1

TYPE TEST REPORTS

Table 1 – Circuit Breaker type ________

Description IEC 62271-100

1 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Dielectric Tests at minimum pressure: 6.2

1.1. Power frequency voltage withstand test: 6.2.6.1

1.1.1. Option 1: Power frequency (50 Hz) voltage

withstand test, 1 min., wet conditions:

1.1.1.1. To earth (kV r.m.s.) 325

1.1.1.2. Across open CB (kV r.m.s.) 375

1.1.2. Option 2: Switching impulse voltage test

(250/2500 μs), wet conditions:

1.1.3. To earth (kV r.m.s.) 504

1.1.4. Across open CB (kV r.m.s.) 582

1.2. Power frequency voltage withstand test at

atmospheric pressure, and 60 sec/continuous: IECo

Spec.

1.2.1. To earth (kV r.m.s. / kV r.m.s.)

1.2.2. Across open CB (kV r.m.s. / kV r.m.s.)

1.3. Lightning impulse voltage withstand test: 6.2.6.2

1.3.1. To earth (kV peak) 750

1.3.2. Across open CB (kV peak) 860

1.4. Partial discharge test: 6.2.9

1.4.1. P.D. level at 1.2xUm/√3 kV (pC) <5

1.4.2. Free from p.d. up to (kV r.m.s.):

1.5. Voltage test as condition check (if applicable) 6.2.11

1 Additional standards IEC 62271-203, IEC 62271-300, IEC 62271-310, 62271-1, 62271-110, IEC/IEEE 62271-37-082, CENELEC EN 50052

Page 15: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 2

Description IEC 62271-100

1 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1.6. RIV test at 1.1xUm/3 kV (V) 6.3 <2500

2. Temperature rise test 6.5

2.1. Contacts (0C) 55

2.2. Connections (0C) 65

2.3. Accessible enclosure (0C) 30

2.4. Auxiliary and control equipment ((0C) 6.5.5

3. Measurement of resistance of main circuit R () 6.4

4. Mechanical and Environmental tests: 6.101 Class M2

4.1. Functional test:

4.1.1. At minimum supply voltage (CO cycles) 500

4.1.2. At rated supply voltage (CO cycles) 500

4.1.3. At maximum supply voltage (CO cycles) 500

4.1.4. At rated supply voltage (O-0.3s-CO-C cycles) 250

4.2. Endurance test (five times the test series provided

in clause ‎4.1) 10000

4.3. Environmental test:

4.3.1. Operation test at high temperature (C) +50

4.3.2. Operation test at low temperature -5

5. Electrical endurance testing IEC 62271-

310

6. Short time withstand current and peak withstand

current tests 6.6

6.1. Short time withstands current (kA) 50

6.2. Duration of short-circuit (sec) 1

6.3. Rated peak withstand current (kA peak) 125

Page 16: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 3

Description IEC 62271-100

1 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

7. Verification of the protection: 6.7

7.1. Verification of the IP coding 6.7.1 IP 65

7.2. Mechanical impact test 6.7.2 IK 10

8. Tightness tests 6.8

9. Electromagnetic compatibility (EMC) tests: 6.9

9.1. Emission tests 6.9.1

9.2. Immunity tests 6.9.2

9.3. Ripple on d.c. input power port immunity test 6.9.3.1

9.4. Voltage dips, short interruptions and voltage

variation on d.c. input power port immunity tests 6.9.3.2

10. Additional tests on auxiliary and control circuits: 6.10

10.1. Functional tests 6.10.2

10.2. Electrical continuity of earthed metallic parts test 6.10.3

10.3. Verification of the operational characteristics of

auxiliary contacts 6.10.4

10.4. Environmental tests 6.10.5

11. Verification of making and breaking capacities -

short-circuit tests 6.102 to

6.106

11.1. Test-duty T10 (10%) (kA r.m.s.) 6.106.1 5

11.2. Test-duty T30 (30%) (kA r.m.s.) 6.106.2 15

11.3. Test-duty T60 (60%) (kA r.m.s.) 6.106.3 30

11.4. Test duty T100s (100% sym):

11.4.1. Test duty T100s(a) (making test) (kA peak) 6.106.4 125

11.4.2. Test duty T100s(b) (breaking test) (kA r.m.s) 6.106.4 50

11.5. Test duty T100a (100% asym) (kA r.m.s) 6.106.5

11.6. Critical current test (if applicable) 6.106.7

Page 17: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 4

Description IEC 62271-100

1 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

11.7. Single-phase and double earth fault test (if

applicable) 6.106.8

12. Short line fault test 6.109

12.1. Test duty L90 (kA r.m.s.) 45

12.2. Test duty L75 (kA r.m.s.) 37.5

12.3. Test duty L60 (kA r.m.s.) (if applicable) 30

13. Out of phase making and breaking tests: 6.110

13.1. Test duty OP1 (30%) (kA) 3.75

13.2. Test duty OP2 (100%) (kA) 12.5

14.

Capacitive current switching tests for class C2

IEEE

C37 06 Table 14

14.1. Line charging breaking current (A) 63

14.2. Cable charging breaking current (A) 1000

14.3. Capacitor bank current switching test (A) 1000

14.3.1. Rated single capacitor bank breaking current (A) 1000

14.3.2. Rated back-to-back capacitor bank breaking

current (A)

14.3.3. Rated back-to-back capacitor bank inrush making

current (kA/Hz) 20/4300

15. Small inductive current switching tests IEC 62271-

110

15.1. Rated small inductive breaking current (A)

16. Sound test

IEC 62271-

37-

082/2012

Page 18: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 5

Table 2 – Disconnector type ________, Low Speed Earthing switch type ________ and High Speed Earthing switch type ________

Description IEC 62271-102

2 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Dielectric Tests at minimum pressure: 6.2

1.1. Power frequency voltage withstand test: 6.2.6.1

1.1.1. Option 1: Power frequency (50 Hz) voltage

withstand test, 1 min., wet conditions:

1.1.1.1. To earth (kV r.m.s.) 325

1.1.1.2. Between contacts (kV r.m.s.) 375

1.1.2. Option 2: Switching impulse voltage test

(250/2500 μs), wet conditions:

1.1.3. To earth (kV r.m.s.) 504

1.1.4. Between contacts (kV r.m.s.) 582

1.2. Power frequency voltage withstand test at

atmospheric pressure, and 60 sec/continuous: IECo

Spec.

1.2.1. To earth (kV r.m.s. / kV r.m.s.)

1.2.2. Between contacts (kV r.m.s. / kV r.m.s.)

1.3. Lightning impulse voltage withstand test: 6.2.6.2

1.3.1. To earth (kV peak) 750

1.3.2. Between contacts (kV peak) 860

1.4. Dielectric test on insulated earthing switches (kV

r.m.s.) 6.2.10 2

1.5. Partial discharge test: 6.2.9

1.5.1. P.D. level at 1.2xUm/√3 kV (pC) <5

1.5.2. Free from p.d. up to (kV r.m.s.):

2 Additional standards IEC 62271-203, IEC 62271-1

Page 19: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 6

Description IEC 62271-102

2 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1.6. Voltage test as condition check (if applicable) 6.2.11

1.7. RIV test at 1.1xUm/3 kV (V) 6.3 <2500

2. Temperature rise test 6.5

2.1. Contacts (0C) 55

2.2. Connections (0C) 65

2.3. Accessible enclosure (0C) 30

2.4. Auxiliary and control equipment ((0C) 6.5.5

3. Measurement of resistance of main circuit R () 6.4

4. Short time withstand current and peak withstand

current tests 6.6

4.1. Short time withstands current (kA) 50

4.2. Duration of short-circuit (sec) 1

4.3. Rated peak withstand current (kA peak) 125

5. Short-circuit making test for high speed earthing

switches class E1 6.101 2 op.

5.1. Short time withstands current (kA) 50

5.2. Rated peak withstand current (kA peak) 125

6. Operating and Mechanical and Environmental

tests for class M2 Disconnectors and class M1

Earthing Switches

6.102

6.1. Functional test:

6.1.1. At rated supply voltage (CO cycles) 900

6.1.2. At minimum supply voltage (CO cycles) 50

6.1.3. At maximum supply voltage (CO cycles) 50

6.2. Endurance tests:

6.2.1. Disconnectors: (ten times the test series provided 10000

Page 20: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 7

Description IEC 62271-102

2 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

in clause ‎6.1)

6.2.2. Earthing switches: (two times the test series

provided in clause ‎6.1) 2000

6.3. Operation at temperature limits: 6.104

6.3.1. Operation test at high temperature (C) +50

6.3.1.1. At minimum supply voltage (CO cycles) 3

6.3.1.2. At maximum supply voltage (CO cycles) 3

6.3.2. Operation test at low temperature (C) -5

6.3.2.1. At minimum supply voltage (CO cycles) 3

6.3.2.2. At maximum supply voltage (CO cycles) 3

7. Bus transfer current switching test-making and

breaking test at minimum gas pressure 6.106

7.1. Rated bus transfer current (A) 1600

7.2. Rated bus transfer voltage (kV r.m.s.) 10

7.3. Number of make-break operating cycles 100

8. Induced current switching test for each type of

earthing switches: 6.107

8.1. HSES class B

8.1.1. Electromagnetically coupling

Rated current/Rated voltage (A/kV) 80/2

8.1.2. Electrostatically coupling

Rated current/Rated voltage (A/kV) 3/9

8.2. LSES class A

8.2.1. Electromagnetically coupling

Rated current/Rated voltage (A/kV) 50/1

8.2.2. Electrostatically coupling 0.4/3

Page 21: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 8

Description IEC 62271-102

2 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

Rated current/Rated voltage (A/kV)

8.3. Number of make-break operating cycles for

electrostatically induced current 10

8.4. Number of make-break operating cycles for

electromagnetically induced current 10

9. Bus charging switching test

6.108 and

Annex. F

9.1. Bus charging current (A) 0.25

9.2. Test duty 1 – number of make and break

operations for standard/fast Disconnectors 50/200

9.3. Test duty 2 – number of make and break

operations for standard/fast Disconnectors 50/200

9.4. Test duty 3 – number of make and break

operations for standard/fast Disconnectors 50/50

Page 22: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 9

Table 3 – Current transformer type ________

Description IEC 61869-2

3 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Type Tests 7.2

1.1. Temperature rise test 7.2.2

1.1.1. Connections (0C) 65

1.1.2. Windings (0C) 65

1.1.3. Accessible enclosure (0C) 30

1.2. Dielectric tests at minimum gas pressure:

1.2.1. Lightning impulse voltage withstand test to earth

on primary windings (kV peak): 7.2.3 750

1.2.2. Power frequency voltage withstand test on

primary windings (kV): IEC

62271-203 325

1.3. Electromagnetic Compatibility test 7.2.5

1.3.1. RIV test 7.2.5.1

1.3.2. Immunity test 7.2.5.1

1.4. Tests for accuracy 7.2.6

1.4.1. Ratio error and phase displacement of measuring

CT's 7.2.6.201

1.4.2. Instruments security factor (FS) 7.2.6.202

1.4.3. Test for composite error 7.2.6.203

1.5. Verification of the degree of protection by

enclosures 7.2.7

1.6. Enclosure tightness test at ambient temperature 7.2.8

1.7. Pressure test for the enclosure

7.2.9 IEC 62271-203

6.103

3 Additional standards IEC 62271-203, 62271-1, 61869-1

Page 23: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 10

Description IEC 61869-2

3 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1.8. Short-time current test 7.2.201

1.8.1. Rated short-time thermal current (kA r.m.s.) 50

1.8.2. Duration of short-circuit (sec) 1

1.8.3. Rated dynamic current (kA peak) 125

1.9. Magnetization curves for each core type

IECo

Spec.

2. Special tests 7.4

2.1. Chopped impulse voltage withstand test on

primary terminals 7.4.1

2.2.

Transmitted overvoltage test (kV peak) 7.4.4

Impulse

type B

< 1.6

2.3.

Internal arc fault test

7.4.6 IEC

62271-203 6.105

and Annex B

50kA

/0.5sec

2.4. Enclosure tightness test at low and high

temperature 7.4.7

2.5. Gas dew point test 7.4.8

3. Sample tests 7.5

3.1. Instruments security factor (FS)

Page 24: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 11

Table 4 – Voltage transformer type ________

Description IEC 61869-3

4 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Type Tests 7.2

1.1. Temperature rise test 7.2.2

1.1.1. Connections (0C) 65

1.1.2. Windings (0C) 65

1.1.3. Accessible enclosure (0C) 30

1.2. Dielectric tests at minimum gas pressure:

1.2.1. Lightning impulse voltage withstand test to earth

on primary windings (kV peak): 7.2.3.2 750

1.2.2. Switching impulse withstand voltage test

(kV peak) 7.2.3.3

1.2.3. Power frequency voltage withstand test on

primary windings (kV r.m.s.) IEC

62271-203 325

1.3. Electromagnetic Compatibility test 7.2.5

1.3.1. RIV test 7.2.5.1

1.4. Tests for accuracy: 7.2.6

1.4.1. Tests for accuracy for measuring VT's 7.2.6.301

1.4.2. Tests for accuracy for protective VT's 7.2.6.302

1.5. Verification of the degree of protection by

enclosures 7.2.7

1.6. Enclosure tightness test at ambient temperature 7.2.8

1.7. Pressure test for the enclosure

7.2.9 IEC

62271-203

6.103

1.8. Short-circuit withstand capability test: 7.2.301

4 Additional standards IEC 61869-1, 62271-203, 62271-1, ANSI C5713

Page 25: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 12

Description IEC 61869-3

4 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1.8.1. Rated short-time thermal current (kA r.m.s.) 50

1.8.2. Duration of short-circuit (sec) 1

1.9. Magnetization curves for each core

IECo

Spec.

2. Special tests 7.4

2.1. Chopped impulse voltage withstand test on

primary terminals 7.4.1

2.2.

Transmitted overvoltage test (kV peak) 7.4.4

Impulse

type B

< 1.6

2.3.

Internal arc fault test

7.4.6 IEC

62271-203 6.105

and Annex B

50kA

/0.5sec

2.4. Enclosure tightness test at low and high

temperature 7.4.7

2.5. Gas dew point test 7.4.8

3. Other tests

3.1. Discharge withstand capability

IECo

Spec.

3.2. Ferroresonance test (if applicable)

IECo

Spec.

3.3. Impedance and excitation measurements

IEEE

C57 13

cl. 8/3

Page 26: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 13

Table 5 – Surge Arrester type ________

Description IEC 60099-4

5 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Type Tests

1.1. Dielectric Tests at minimum SF6 pressure: 11.8.2

1.1.1. Lightning impulse withstand voltage test (kV

peak) 750

1.1.2. Power frequency withstand voltage test for 1 min

(kV r.m.s.) 325

1.1.3. Withstand test on active part of GIS arrester (if

applicable) (kV r.m.s)

1.1.4. Power frequency withstand voltage test at

atmospheric pressure and at 60 sec/continuous

(kV r.m.s./kV r.m.s.)

IECo

Spec.

1.1.5.

Partial discharge test:

8.8 and

IEC

62271-

203

1.1.5.1. P.d. level at 1.2 U/3 (pC) <5

1.1.5.2. Free from p.d. up to (kV)

1.2. Residual voltage test: 8.3

1.2.1. Steep current impulse residual voltage test 8.3.1

1.2.2. Lightning impulse residual voltage test 8.3.2

1.2.3. Switching impulse residual voltage test 8.3.2

1.3. Long duration current impulse withstand test 8.4.2

1.4. Operating duty test 8.5 and

5 Additional standards IEC 62271-203, CENELEC EN50052.

Page 27: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 14

Description IEC 60099-4

5 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

11.8.5

1.4.1. Switching surge operating duty test

1.5. Power frequency voltage versus time curve 6.10

1.6. Short circuit test 11.8.7

1.7. Current distribution test (if applicable)

6.6 and

9.1e

Page 28: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 15

Table 6 – Busbar ducts

Description IEC 62271-203

6 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Dielectric tests at minimum gas pressure: 6.2

1.1. Power frequency voltage withstand test to earth

(kV r.m.s.) 6.2.6.1 325

1.2. Power frequency voltage withstand test at

atmospheric pressure, and 60 sec/continuous

(kV r.m.s./kV r.m.s.)

IECo

Spec.

1.3. Lightning impulse voltage withstand test to earth

(kV peak) 6.2.6.2 750

1.4. Partial discharge test: 6.2.9

1.4.1. P.D. level at 1.2xUm/√3 kV (pC) <5

1.4.2. Free from p.d. up to (kV r.m.s.):

2. Temperature rise test at I=4000A 6.5

2.1. Connections (0C) 65

2.2. Contacts (0C) 55

2.3. Accessible enclosure (0C) 30

3. Measurement of resistance of main circuit R () 6.4

4. Short time withstand current and peak withstand

current tests: 6.6

4.1. Rated short-time withstand current (kA r.m.s.) 50

4.2. Duration of short-circuit (sec) 1

4.3. Rated peak withstand current (kA peak) 125

5. Internal arc test: 6.105

5.1. Short circuit current (kA) 50

6 Additional standards IEC 62271-1

Page 29: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 16

Description IEC 62271-203

6 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

5.2. Arc duration (sec) 0.5

Page 30: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 17

Table 6 – SF6/Air Bushings type ________ with composite insulator

Description IEC 61462

7 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Design tests: 7

1.1. Tests on interfaces and connections and fittings 7.2

1.1.1. Reference dry power frequency flashover test 7.2.2 Uref

1.1.2. Thermal mechanical pre-stress test 7.2.3 >0.5xSML

1.1.3. Water immersion pre-stress test 7.2.4 42h

1.1.4. Verification test 7.2.5

1.1.4.1. Visual examination 7.2.5.1

1.1.4.2. Steep front impulse test (kV peak) 7.2.5.2

1.1.4.3. Dry power frequency test (kV peak) 7.2.5.3

80%Uref

30min

1.1.4.4. Internal pressure test 7.2.5.4 0.25xSIP

1.2. Tests on shed and housing material 7.3 and

IEC 62217

cl.9.3

1.2.1. Hardness test

1.2.2. Accelerated weathering test

1.2.3. Tracking and erosion test

1.2.4. Flammability test

1.3. Tests on tube material 9.4

1.3.1. Dye penetration test

1.3.2. Water diffusion test

2. Mechanical type tests 8 and

Table B1

2.1. Mechanical type tests 8.4.1

7 Additional standard IEC 62271-203, 60137, 62073, 61462, 60815, 62217, 62039, 61109

Page 31: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 18

Description IEC 61462

7 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

2.2. Cantilever bending test 8.4.2

3. Type tests according to: IEC 60137

3.1. Dielectric tests:

3.1.1. Wet power frequency voltage withstand test (kV

r.m.s.) 8.1 325

3.1.2. Power frequency voltage withstand test at

atmospheric pressure and 60 sec/continuous for

gas insulated bushing

(kV r.m.s./kV r.m.s.)

IECo

Spec.

3.1.3. Dry lightning impulse voltage withstand test (kV

peak) 8.3 750

3.1.4. Chopped lightning impulse voltage withstand test

(if applicable) (kV peak)

3.1.5. Partial discharge test: 9.4

Table 9

3.1.5.1. P.D. level at 1.05xUr/√3 kV (pC) <5

3.1.5.2. P.D. level at 1.5xUr/√3 kV (pC) <10

3.1.5.3. Free from p.d. up to (kV r.m.s.):

3.1.6. RIV test at 1.05xUr/3 kV (V) IEC

62271-203

cl.6.3 <2500

3.1.7. Tan measurement and capacitance

(if applicable) 9.1

3.1.8. Test on tap insulation (kV r.m.s.) 9.5 2

3.2. Thermal stability test 8.5

3.3. Temperature rise test: 8.7

3.3.1. Contacts (0C) 65

Page 32: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 19

Description IEC 61462

7 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

3.3.2. Terminals (0C) 65

3.3.3. Accessible enclosure (0C) 30

3.4. Thermal short time current withstand test: 8.8

3.4.1. Rated thermal short-time current (kA r.m.s.) 50

3.4.2. Duration of short-circuit (sec) 1

3.4.3. Rated peak withstand current (kA peak) 125

3.5. Cantilever load withstand test on mounted

bushing according to:

8.9 and

IECo

Spec.

3.5.1. Testing load for 1 min. (N) 4700

3.6. Tightness test (if applicable) 8.10

3.7. Internal pressure test (if applicable) 8.11

3.8. External pressure test (if applicable) 8.12

3.9. Verification of dimensions 8.13

3.10. Measurement of wettability class of insulator

surfaces IEC 62073

3.11. Seismic qualification test Moderate

level

4. Other special type tests

4.1. Accelerated aging test

4.2. Pollution test

4.3. Power arc test

4.4. Tests on insulating materials: IEC 62039

4.4.1. Tests on housing materials

4.4.2. Tests on core materials

4.4.3. Tests on structural materials

Page 33: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 20

Table 7 – Support insulators and partitions

Description IEC 62271-1

8 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Dielectric tests at minimum SF6 pressure: 6.2

1.1. Power frequency voltage withstand test to earth

(kV r.m.s.) 6.2 325

1.2. Power frequency voltage withstand test at

atmospheric pressure, and 60 sec/continuous

(kV r.m.s./kV r.m.s.)

IECo

Spec.

1.3. Lightning impulse voltage withstand test to earth

(kV peak) 6.2 750

1.4. Partial discharge test: 6.2.9

1.4.1. P.D. level at 1.2xUm/√3 kV (pC) <5

1.4.2. Free from p.d. up to (kV r.m.s.):

2. Pressure test on partitions up to bursting IEC 62271-203

cl.6.104

3. Thermal performance IEC 62271-203

cl.6.106.2

4. Tightness test for partitions IEC 62271-203

cl.6.106.3

8 Additional standards IEC 62271-203

Page 34: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 21

Table 8 – Cable connection enclosure

Description IEC 62271-203

9 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Dielectric tests: 6.2

1.1. Power frequency voltage withstand test to earth

(kV r.m.s.) 6.2 325

1.2. Power frequency voltage withstand test at

atmospheric pressure, and 60 sec/continuous

(kV r.m.s./kV r.m.s.)

IECo

Spec.

1.3. Lightning impulse voltage withstand test to earth

(kV peak) 6.2 750

1.4. Partial discharge test: 6.2.9

1.4.1. P.D. level at 1.2xUm/√3 kV (pC) <5

1.4.2. Free from p.d. up to (kV r.m.s.):

2. Temperature rise test: 8.7

2.1. Connections (0C) 65

2.2. Accessible enclosure (0C) 30

3. Measurement of resistance of main circuit R () 6.4

4. Short time withstand current and peak withstand

current tests: 6.6

4.1. Rated short-time withstand current (kA r.m.s.) 50

4.2. Duration of short-circuit (sec) 1

4.3. Rated peak withstand current (kA peak) 125

9 Additional standards IEC 62271-1, 62271-209

Page 35: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 22

Table 9 – Other tests

Description IEC 62271-203

10 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

1. Proof test for each type of enclosure

(see CENELEC 50052,50064,50069) 6.103

1.1. Destructive pressure test for: 6.103.2

1.1.1. Cast aluminium and composite aluminium

enclosures 5p

11

1.1.2. Welded aluminium and welded steel enclosures 2.3 ×𝜎𝑡𝜎𝑎

𝑝12

1.2. Non-destructive pressure test 6.103.2

2. Electrical and mechanical life tests to

demonstrate life performance of bellows, elbows

or expansion joints

IEEE

C37.122

3. Gas tightness tests on each type of enclosures 6.8

4. Short time current test on earthing circuits 6.6.102

5. Corrosion test on earthing circuits 6.107

6. Corrosion test on enclosures 6.108

7. Control Cubicle and auxiliary circuits

7.1. Dielectric tests on auxiliary and control circuits: 6.2.10

7.1.1. Impulse voltage withstand test (kV peak) IEC 60694 5

7.1.2. Power frequency voltage withstand test 1 min.

(kV peak) 6.2.10 2

7.2. Temperature rise on auxiliary and control

equipment 6.5.5

10

Additional standards: IEC 62271-1, IEC 62271-207, 60068-2, 61000-4,60094, IEEE C37.122, CENELEC 50052, 50064, 50069 11

p – design pressure of enclosure 12

σt – permissible design stress at test temperature, σa – permissible design stress at design temperature

Page 36: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 23

Description IEC 62271-203

10 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

7.3. Measurements of the resistance of auxiliary

contacts class 1 6.4.2

7.4. Other tests on auxiliary and control circuits: 6.10

7.4.1. Functional tests

7.4.2. Electrical continuity of earthed metallic parts

7.4.3. Verification of operational characteristics of

auxiliary contacts

7.4.4. Environmental tests:

7.4.4.1. Cold test

7.4.4.2. Dry heat test

7.4.4.3. Damp heat, steady state test

7.4.4.4. Cyclic humidity test

7.4.4.5. Vibration response and seismic tests

7.4.4.6. Other environmental tests IEC

60068-2

7.5. Verification of IP coding IEC 60529

7.5.1. CB cubicle, LCC IP54

7.5.2. Motor drive IP40

7.5.3. Protection of LCC indicated by additional letter class D

7.5.4. Protection of LCC equipment against mechanical

impact

IEC

62262

IK10

7.6. The digital interfaces based on IEC 61850 shall

be tested according to: IEC

62271-3

8. EMC tests for secondary system in case

electronic components are included, for normal

EMC severity class

6.9

Page 37: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A3 SPECIFICATION SR-152

A3 - 24

Description IEC 62271-203

10 Test

Plant

Date of

Test

Test report Remarks

Clause Value No. Value

8.1. Electrical fast transient/burst test (kV) 2

8.2. Oscillatory wave immunity test (kV) 2.5

8.3. Electrostatic discharge test ESD on electronic

equipment

8.4. Ripple on d.c. input power port immunity test

8.5. Voltage dips, short interruptions and voltage

variations on input power port immunity tests

8.6. Control equipment including microprocessors IEC

61000-4

8.7. Other tests (if applicable)

9. Seismic qualification for earth horizontal

acceleration

IEC

62271-207

IEEE 693

moderate

level

9.1. For GIS equipment

9.2. For LCC equipment

10. Cross cut test of painting ISO 2409 Grad 0

10.1. LCC enclosures

10.2. GIS enclosures

10.3. Support structures of GIS

10.4. Other metallic parts

11. SF6 gas certification

12. Welding and pressure testing performed on the

pressure vessels (if applicable)

CENELEC 50064,

50069

Page 38: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A4 SPECIFICATION SR-152

A4 – 1

On-Site HV test program for 170 kV GIS for MOBILE Substation

1. AC voltage test for GIS with voltage transformers connected at frequency

range between 80 and 300 Hz according to IEC 62271-203. The tests will be

performed with frequency turned SF6 insulated test equipment directly

flanged to the GIS.

1.1 For GIS manufactured for rated voltage 245 kV.

Each phase should be tested similar to the following sequence:

Gradual voltage increase up to U=270 kVrms for 3 min conditioning,

Gradual voltage increase up to test voltage Utest=376 kVrms for 1 min,

Voltage decrease to 170 kVrms for PD measurements.

1.2 For GIS manufactured for rated voltage 170 kV.

Each phase should be tested similar to the following sequence:

Gradual voltage increase up to U =220 kVrms for 3 min conditioning,

Gradual voltage increase up to test voltage Utest=270 kVrms for 1 min,

Voltage decrease to 155 kVrms for PD measurements.

Secondary windings of the voltage transformers have to be disconnected and

any ferro-resonance security circuit must be disconnected. Secondary

windings of the current transformers must be short-circuited and earthed.

During the HV test a partial discharge (PD) measurements should be

performed using UHF measuring method.

Page 39: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A4 SPECIFICATION SR-152

A4 – 2

2. AC Test Equipment

Frequency turned resonant test system from HIGHVOLT:

Rated voltage kV 680 Minimum voltage kV 68 Rated current A 1.5 Frequency range Hz 50 - 300 Duty cycle at rated power 15 min ON - 1 day OFF Min. load capacitance3) nF 0.4 Max. load capacitance nF 14.12 PD noise level pC 5 Mains supply at stiff grid 3NPE (3 phases + neutral (no protection

earth) V 230/400 Hz 50/60 A 63 kVA 43 Quality factor of complete test circuit ≥ 50 Operating conditions:

Ambient temperature °C 5 … 40

Daily mean temperature °C ≤ 25 Max. relative humidity % 90 (no condensation) Height above sea level m ≤ 1000 (at higher altitude with

reduced voltage) Ambient temperature for storage and transportation

°C -10 … 50 (no condensation)

Maximum shock loading in all directions 2 g Flange type Siemens 8DQ1 400 kV type.

Page 40: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A4 SPECIFICATION SR-152

A4 – 3

Page 41: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A4 SPECIFICATION SR-152

A4 – 4

The following test equipment is used for UHF and acoustic PD

measurements:

Hewlett Packard Model 8560E Spectrum Analyzer,

Partial discharge tester type PDS 100 from DOBLE,

Miteq Model AM-4A-000110-N UHF Amplifier,

Ultrasonic detector "ultraprobe 2000" from UE Systems Inc.

Dr. Vladimir Brandenbursky

Page 42: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A5 SPECIFICATION SR-152

A5 – 1

List of minimum control, fault signals and alarms

1. Three potential free contacts for each signal are required.

2. For each type of bay:

2.1. DC supply MCB tripped + NO volt.

2.2. AC supply MCB tripped + NO volt.

2.3. Voltage transformer MCB tripped (one alarm for each MCB)

2.4. Circuit breaker operation blocked by SF6 low pressure.

2.5. Low pressure warning alarm SF6 gas density monitoring for each gas

compartment.

2.6. Low pressure danger alarm SF6 gas density monitoring for each gas

compartment.

2.7. Pole discrepancy TRIP1, TRIP2

2.8. O-C-O LOCK (only for line bay)

2.9. Repeat anomaly detection.

2.10. MCB of disconnector and earthing switches open

2.11. Manual CLOSE order.

2.12. Manual OPEN order.

2.13. Bay in local mode

2.14. Circuit breaker CLOSE command

Page 43: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

File num. 95

Date: 04/5/17

Senior Vice President for

Planning, Development and Technology

Transmission Planning, Reliability and Equipment

System Reliability & H.V. Equipment Dept.

CYBER REQUIREMENTS

1. The document contains two main subjects:

1.1. Security information of the equipment designing and manufacturing.

1.2. Network and security safeguards of the equipment.

2. The supplier shall agree1 to three documents attached to his proposal as follows :

1 In case of requirements that cannot be fulfilled, it shall be explicitly indicated by supplier.

2 © - Compulsory requirements.

3. Network and security safeguards:

The supplier that will stand the requirements of tender first stage (threshold conditions and compulsory

requirements),

would be requested to answer to additional cyber security questions at the secondary stage.

No. FILE NAME:

2.1

NDA - ©2

2.2

General requirements - ©2

2.3

Security of project (environment)

Publication Team Date

Prepared

Y. Cohen 25/4/17

D. Visan 4/5/17

Checked M. Cheausu 25/4/17

Approved

Dr. H. Ben-Haim 25/4/17

D. Berger 27/4/17

A.Aspurtas 4/517

Page 44: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

File num. 96

Date: 04/5/17

Senior Vice President for

Planning, Development and Technology

Transmission Planning, Reliability and Equipment

System Reliability & H.V. Equipment Dept.

NON-DISCLOSURE AGREEMENT

AND PRELIMINARY CYBER REQUIREMENTS

1. NDA :

No parts of all the technological and management information in the specification may be reproduced, stored

in retrieval system or transmitted in any form or by any means electronic, mechanical, photocopying recording

or otherwise, without the prior written permission of the RELIABILITY & H.V. EQUIPMENT

DEPARTMENT Israel Electric Corporation (I.E.Co.)

2. PRELIMINARY CYBER REQUIREMENTS :

The supplier shall confirms the following requirements :

2.1. Security plan – attached to proposal .

2.2. Willingness to perform security plan assessment by I.E.Co. representatives .

3. SIGNATURE:

3.1. Company name: ______________

3.2. Company’s representative name : ______________

3.3. Date: ______________

3.4. Sign: ______________

Page 45: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

ISRAEL ELECTRIC CORPORATION (IEC)

CUSTOMERS DIVISION

TRANSMISSION & SUBSTATIONS

TENDER'S FIRST STAGE CYBER SECURITY GENERAL REQUIREMENTS

VERSION: 20-04-2017

STATUS: FINAL

APPROVED BY: ARYE ASPORTAS

Page 46: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 2 of 10

Table of Contents 1. General 3

2. Topology & Secured Network Architecture 3

3. Hardening & Configuration Management 5

4. Additional Security Measures 6 4.1 Hardware Configuration & Device control 6 4.2 Detection of Unauthorized Software and Unauthorized Modifications to Software 6 4.3 Database Protection 6 4.4 Anti-Malware Detection & Prevention System 7 4.5 Software Updates, Security Patches & Signature Updates 7

5. Identification, Authentication & Authorization 7 5.1 General 7 5.2 Default generic accounts 7 5.3 User Authentication 7 5.4 Access Security Management 8 5.5 Appropriate Use Banner 8 5.6 Password Policy 8 5.7 Authorization & Separation of Privileges 8

6. Contractor’s Maintenance 8

7. Monitoring, Indication & Control 8

8. Application Security 9 8.1 General 9 8.2 Free of “Electronic Self-Help” Enabled Software 9 8.3 Obligation for Notification of Security Vulnerabilities in Contractor-Provided

Software 9

9. System Test 10

Page 47: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 3 of 10

1. General

1) All system plans based on the principles in this document is subject to the approval of the IEC’S

Regulator. The contractor shall undertake to comply with any provisions of any annex which will be

added to this document. Deviations shall be permitted only with the approval of the regulator.

2) The Contractor must base its security considerations and requirements on the requirements of the

standards declared by IEC.

3) The Contractor must comply with IEC’s Information Security policies and procedures.

4) All security functions required by this Specification must be implemented in a non-interfering manner,

such that authorized and legitimate use of the system is not hampered, nor is the ability to perform

required functions impeded by the security features.

5) All equipment, servers, workstations, software and systems proposed and ultimately supplied with

these component systems shall be considered Critical Cyber Assets for the purposes of the system

and this contract.

6) All systems, networks, and equipment, as well as the equipment that defines the security perimeter

shall be treated and configured as Critical Cyber Assets.

7) All systems and equipment should follow international cyber security standards like “NERC CIP

standards”, “IEEE Standard Cyber Security Requirements for Substation Automation, Protection, and

Control Systems” etc.

8) All network and security equipment\ software designed for the purchased system, must be approved

by IEC.

9) Detailed Requirements for cyber security, hardware and system

configuration will be provided in the technical coordination phase.

2. Topology & Secured Network Architecture

1) The Contractor will not connect the system (or equipment, systems, and other items peripheral to

the main system) to the internet.

2) Each of the systems/equipment supplied, by the selected Contractor, shall include clearly defined

electronic security perimeters within which all associated system devices reside.

3) The primary access points through this perimeter shall be IEC-provided Firewalls.

4) Where technically feasible, communications shall be designed so that the most privileged application

shall initiate communications.

5) The Contractor shall provide documents and drawings depicting the electronic security perimeters, all

interconnected system components within the electronic security perimeter(s), all access points

through the electronic security perimeter(s), and all assets deployed or configured for controlling and

monitoring access to the defined access points.

Page 48: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 4 of 10

6) The Contractor shall limit required port access to a minimum and provide a list of all required ports,

services and addresses requiring access through any and all Firewalls that support normal, emergency

and ongoing maintenance functions.

7) This will include ports and services required for basic operating system functions.

8) As directed by IEC, the Contractor shall provide assistance to IEC in helping to determine the minimum

required access permissions for the firewalls that allow a functional, yet secure, operation of the

system, including normal, emergency and required ongoing maintenance actions.

9) The Corporate network shall not have direct query or access capability to any data stores or processes

within the system.

10) The system network shall be divided into segments. The location of the various components will be

determined by criteria such as their functionality, use, geographic location, belonging to a particular

system, Belonging to a particular environment (Production/test/developments etc...), the protocols

needed for their operation etc. It should be emphasized that any function/criteria, as mentioned

above, must be placed in a separate segment.

11) No communication shall be allowed between different segments, except for operational needs

(such as synchronization between components).

12) There shall be a dedicated management segment for managing components out of band.

13) Shutting down management workstations at the end of a working day will not have adverse effect

on the operation of the systems.

14) A local management will be allowed only in a case of an operational malfunction, in which remotely

management is not possible.

15) Management connection shall be through a separation of communication (physical or logical) from

the production communication, such as a different NIC, a different port, a different protocol etc. The

management communication shall be encrypted for any component in the critical Infrastructure.

16) A communication control, in white list format, shall be implemented between the different segments,

including the management segment.

17) The control level shall be at least by the ‘Stateful inspection’ method.

18) Hubs shall not be used for communication purposes.

19) For permanent communication monitoring, a TAP shall be used. For temporary communication

monitoring, Span Port shall be used.

20) Only wired communication is allowed and wireless communication to the system components shall be

blocked (Such as WIFI, Bluetooth etc.).

21) In components which support time synchronization, the synchronization shall be from a centralized

Time source within the critical Infrastructure.

22) File & Print sharing services, within the critical Infrastructure, will be operated only from a dedicated

& centralized server.

23) Shares shall not be created on the end users workstations.

24) Network Connectivity:

Page 49: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 5 of 10

a) In general, only outbound link should be established.

b) The outbound information shall be routed only to its destination system using a FireWall.

c) The connectivity will be operated by a hardware that executes only one way transfer in a

physical manner.

d) If inbound and outbound connectivity is needed, a double one way connectivity (without a

closure option inside the system/network). The inbound and outbound connectivity will be set as

defined above.

e) Where applicable, and/or requested by IEC, the Contractor shall propose additional network

security architectures, including “DMZ” networks and associated systems, to provide external

users access to data without impacting the performance, reliability or security of the system or

its component systems.

f) Where DMZ networks are proposed, the network configurations shall be implemented to

maximize the security of the system networks, while facilitating access to data resources located

in the DMZ.

g) Well-defined rules outlining required and authorized traffic must be implemented at all access

points.

h) Management of access control devices must be permitted only from a highly restricted subset of

management devices.

i) The contractor will provide a document describing each port used in each unit.

25) NAC (Network Access Control) shall be used for detection & prevention of any network component

that is not authorized or compliance.

3. Hardening & Configuration Management

1) All components in the critical Infrastructure will be dedicated for it.

2) A static IP address shall be assigned for every component. The IP addresses pools will be defined by

IEC.

3) The contractor shall provide a listing of services required for any computer system running the

system applications or required to interface the system applications.

a) The listing shall include all ports and services required for normal operation as well as any other

ports and services required for emergency operation.

b) The listing shall also include an explanation or cross reference to justify why each service is

necessary for operation.

4) All applications, utilities, system services, scripts, configuration files, databases, user accounts and

all other software not required for operation of the system shall be removed prior to commissioning.

5) All access permissions implemented during system development, factory test and site test shall be

documented and reviewed for removal prior to system commissioning.

6) The Contractor shall submit to IEC a written certification attesting that all access privileges have

been scrubbed.

Page 50: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 6 of 10

7) All components shall be hardened in a way that will minimize cyber-attacks or surface cyber-attacks

and will expose the minimum ports and functionality needed for them to run. Hardening procedures

shall follow well-known hardening standards, such as NIST, the vendor’s best practices etc.

8) Any optional back-door shall be removed (Such as hard coded passwords etc).

9) The Contractor shall also perform hardening according IEC policy.

10) The Contractor shall document and submit documentation that the foregoing has been completed.

11) Error/Informative messages, displayed to the user, should not expose sensitive information, such as

versions, manufacturers, identifications of devices in the critical infrastructure etc.

12) Unsecured channels (for remote access or file transfer) shall be disabled, like TELNET, unsecured

RDP, FTP etc.

13) All security mechanisms within the controllers shall be operated and running.

14) Access for controller configuration will be made from a dedicated permitted workstation within the

critical infrastructure.

15) Source code deletion – The logical functionality, source code, shall not reside in the controller itself.

Only the final executable files shall reside on the controller.

4. Additional Security Measures

4.1 Hardware Configuration & Device control

1) The system shall support Device Control and DLP mechanism according to IEC policy. This

mechanism shall be implemented on all servers and workstations in order to prevent the use of

unauthorized removable media.

2) This mechanism shall be installed and running throughout the development, test, commissioning and

acceptance of the system to ensure that their performance impact is known and tested.

4.2 Detection of Unauthorized Software and Unauthorized Modifications

to Software

1) The system shall support Application Control\Whitelisting mechanism according to IEC policy. This

mechanism shall be implemented on all servers and workstations.

2) This mechanism shall be installed and running throughout the development, test, commissioning and

acceptance of the system to ensure that their performance impact is known and tested.

4.3 Database Protection

1) The system shall support Database Protection mechanism according to IEC policy.

2) This mechanism shall be installed and running throughout the development, test, commissioning and

acceptance of the system to ensure that their performance impact is known and tested.

Page 51: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 7 of 10

4.4 Anti-Malware Detection & Prevention System

1) The system shall support Anti-Malware Detection & Prevention mechanism according IEC policy. This

mechanism shall be implemented on all servers and workstations.

2) This mechanism shall be installed and running throughout the development, test, commissioning and

acceptance of the system to ensure that their performance impact is known and tested.

4.5 Software Updates, Security Patches & Signature Updates

1) All updates to the operating system and application software addressing cyber security shall be

installed as specified in Software Maintenance, prior to installation on the production systems.

2) All security patches and upgrades to the operating systems, databases, third-party products and

upgrades provided by Contractor and application software shall be tested and certified by the

Contractor.

3) Critical security updates/patches shall be installed on all components in the critical infrastructure

(Hardware/Software/Firmware), including on virtual components.

4) Security updates/patches shall be accepted from the vendor according a process which will

guarantee their integrity and source (for example – updates/patches shall be digitally signed).

5) The frequency of signatures update will be determined according IEC policy.

6) The contractor shall undertake to provide updates/fixes to security gaps that found on all life-cycle of

the system (from the development, test, acceptance and operational use).

7) In any case that technical or operational reason does not enable to implement a solution to any

security gaps the contractor must implemented compensating controls to these security gaps.

5. Identification, Authentication & Authorization

5.1 General

1) Identification, Authentication and Authorization procedures will be implemented according to IEC

policy.

2) A well-known encryption & hashing methods shall be used during data in rest and data in transit, in

order to protect authentication credentials.

5.2 Default generic accounts

1) The contractor shall remove all generic accounts, guest accounts, development accounts,

maintenance accounts, and default accounts provided by hardware, operating system, database,

application program, and other contractors.

5.3 User Authentication

1) The system must support a centralized account management method to enforce access

authentication and accountability of user activity, and to minimize the risk of unauthorized access.

2) User Authentication, for any environment (test, development, production, management, etc.) shall

be accomplished using at least two out of three authentication methods:

a) Something you know

Page 52: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 8 of 10

b) Something you have

c) Something you are

3) User credentials must not be transmitted in clear text.

5.4 Access Security Management

1) The cyber security controls shall be applied across all system’s applications and services and security

shall be managed as a single service for all component systems.

5.5 Appropriate Use Banner

1) Users accessing the system through interactive or maintenance access shall be presented with an

“Appropriate Use Banner”, the contents of which will be provided by IEC.

5.6 Password Policy

1) IEC’s Password policy shall be implemented in all systems and Password characters shall be hidden

or stared during typing.

2) Password characters shall be hidden or stared during typing

5.7 Authorization & Separation of Privileges

1) Operating System Administrative users shall have the authority to assign and define the different

classes of users and their default class for login.

2) Permissions to the system will be based on the ‘least privileged’ and ‘Need to know’ concepts,

including for accounts used for services or application purposes.

6. Contractor’s Maintenance

1) Remote maintenance connectivity, for the contractor, shall be approved first by the IEC’s regulator.

2) The maintenance connectivity mechanism shall be implemented by IEC.

7. Monitoring, Indication & Control

1) The system shall support Monitoring, Indication & Control mechanism according IEC policy.

2) IEC will work with the contractor to document and analyze the process for determining “normal”

network traffic, including all heartbeat signals.

3) Event logs shall be created on all components (Applications, Operating Systems, Network Devices

and Security Devices etc.)

4) A centralized IEC's SIEM system shall monitor all components, devices, servers and workstations in

the infrastructure. The monitoring shall be in active or passive mode according to IEC requirements.

Page 53: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 9 of 10

8. Application Security

8.1 General

1) The system code development shall be according IEC policy and international standards.

8.2 Free of “Electronic Self-Help” Enabled Software

1) The contractor must state that any software proposed does not contain embedded faults or back-

door mechanisms that could allow the contractor, or any other party, to remotely disable some or all

of the functions of the software, to affect their performance, or in any way to degrade its operation

(so-called “electronic self-help” in the terms of the Uniform Computer Information Transactions Act).

2) The software shall not contain any mechanism that automatically disables some or all of its functions

or degrades their operation on a certain date or upon the occurrence of a specific event.

8.3 Obligation for Notification of Security Vulnerabilities in Contractor-

Provided Software

1) The contractor shall inform IEC in a secure manner the discovery of an error in or a property of any

software resident on the system that makes the system vulnerable to cyber-intrusion.

2) The contractor shall have a patch management and update process.

3) The contractor shall provide details on their patch management and update process during project

implementation shortly after Contract award.

4) Post-contract award, Contractor shall provide notification of known vulnerabilities affecting

Contractor-supplied or required OS, application, and third-party software within the 48-hour period

after public disclosure.

5) Post-contract award, Contractor shall provide notification of patch(s) affecting security as identified

in the patch management process.

6) The contractor shall apply, test, and validate the appropriate updates and/or workarounds on a

baseline reference system before distribution.

7) The contractor shall diligently work to correct the error or modify the property to close the

vulnerability, and shall make the correction fully tested and available to IEC at no cost and must be

corrected to IEC’s satisfaction.

8) This obligation for notification and the closure of security-related vulnerabilities shall remain during

warranty and as long as a Service Agreement is in place.

9) After warranty, but without a Service Agreement, Contractor shall notify IEC of security-related

vulnerabilities.

10) Closure of security-related vulnerabilities in the absence of a Service Agreement will be handled on

an individual contract basis.

11) The contractor shall provide IEC with a process to submit problem reports to be included in the

system security process.

12) Submitted reports shall be reviewed and an initial action plan generated within 48 hours of submittal.

Page 54: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Customers Division Cyber Security Department

Page 10 of 10

13) The contractor shall protect problem reports of a security nature from public disclosure and when

notifying other customers shall not release any information to indicate that IEC identified the

problem.

14) The contractor shall verify and provide documentation that all services are patched to current status.

9. System Test

1) Cyber vulnerability assessment and penetration test shall be performed on FAT and SAT according to

IEC policy.

Page 55: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

WBS

1

1.1 INTRODUCTION

1.1.1

1.1.1.1

The supplier declares, in appendix A, that he adheres to the requirements

included in this document .Please attaché here a general statement regarding

your ability to meet the security requirements includes in this ducument

1.1.1.2

I.E.Co. representatives will conduct a survey with satisfactory results at supplier

premises prior to project kickoff or during other early stage, in coordination with

the supplier security entities.

1.1.2

1.1.3

REQUIRED

Attach file

SECURITY OF PROJECT PERFORMED BY VENDOR ABROAD

COMMENTSREQUIRED

PROJECT SYSTEM SECURITY STANDARD SPECIFICATION

Information' - This document regards information as any data and/or technical material and/or personal and/or technological and/or commercial

of I.E.Co. and/or its affiliates; including that handed to I.E.Co. by third party, as long as it hasn't become public according to I.E.Co. permission;

and any data pertaining I.E.Co. business or its customers' business, given to the supplier and/or to supplier employees and/or became their

possession during their work, by heart, in writing, in electronic media or any other way, including any product, idea, plan or document. Any

technological and managerial information in the project are included in the above 'information' definition.

OFFERED

This document sets security requirements the purpose of which is to ensure the proper management of security in development or upgrade of a

project for I.E.Co. (henceforth: the requirements). The body performing this development/upgrade will be called henceforth: the supplier.

Compliance of supplier to the requirements set forth in this document will be accomplished when:

Yes/No

The security requirements are as follows:

Page 56: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

2 SUPPLIER STRUCTURE, POLICY AND PROCEDURES

2.1

The supplier shall present security policy or alternatively shall refer specifically, in

its quality control policy, that refer to the paragraph requirements. Please attaché

here a security policy or quality control policy.

2.1.1 Managing the protection of I.E.Co. hardware and software assets,

2.1.1.1 Supplier organizational structure which supports the security issue;

2.1.1.2The commitment of supplier management to fulfill the requirements of this

document.

2.2 The supplier is required to nominate a manager to the project security.

2.3Supplier shall present procedures supporting the implementation of the

requirements included in this document. Please attaché here the procedures

2.4

Supplier shall present an appropriate organizational structure which supports the

above procedures (par. 2.2) and their enforcement on its employees and third

party/affiliates; including presentment of evidential documents such as minutes-

of-meetings, verification of training etc.) Please attaché here the organizational

structure and the job function..

2.5

Supplier shall prepare a security plan for the project. The plan shall include

implementation of the requirements in this document and detailed reference

regarding the following subjects: risk management and vulnerability scans and

their remedies/treatment; prohibiting access to the project information including

industrial espionage; and possible advanced security measures exercised by

supplier in the project.

All the requirements included in this document apply to any place in which the

project or part of it is performed, including third parties.

The security plan shall be handed to I.E.Co. for approval prior to project design

and shall be a pre-requisite to project development.Please attaché here a

security plan for the project.

3 PROJECT SECURITY IMPLEMENTATION

3.1

I.E.Co. representative will supervise the implementation of project security

throughout its phases, beginning with design, development, through factory

erection, FAT, till disassembly for shipping, packing and marking for delivery

(henceforth: project period). The supplier shall be responsible for the integrity

and completeness of the system throughout the transportation from supplier

premises to I.E.Co. project site.

3.2

I.E.Co. representative will install and operate logical security tools on the project

system, in collaboration with the supplier, including hardening. As an extra

security measure, I.E.Co. representative may be granted full control on the

security tools in the project system.

3.3The supplier agrees to accept the directives of I.E.Co. representative per par. 3.2

above throughout the project period.

3.4

In collaboration with supplier, I.E.Co. representative will be entitled to conduct

inspections, for the purpose of reviewing the implementation of the security

requirement at the supplier premises. Supplier shall cooperate and grant the

needed assistance in fulfillment of this audit.

3.5

In the framework of security activity, I.E.Co. representative will be allowed, with

prior supplier consent, to copy the project system portable media (such as hard

disks) for further security checks and/or to install security tools intended to

register/capture the project configuration for future verification and vulnerability

analysis.

4 PHSICAL SECURITY

4.1

Supplier shall allocate a separate secured and controlled physical working

environment for the project (henceforth: the secured area). All the elements of

the project, including all scope of delivery and project ancillary equipment in

supplier premises, such as test equipment, must reside in the secured area

throughout the project period, including the stages of packing and storing for

dispatch.

4.2The secured area walls shall be rigid construction. The secured area shall have

four walls, ceiling and floor. Please attaché here the secured area drawing.

4.3

The entrance doors to the secured area shall be metal made and equipped with

electromagnetic locks. The locks shall be approved beforehand in writing by

I.E.Co.. The entrance to the secured area shall be controlled according to the

following conditions:

4.3.1

Identification via biometric or encrypted proximity card, in a reputed standard

approved by I.E.Co. beforehand. Please attaché here a general description of

your access control system.

4.3.2

The entrance control shall be in the supplier internal network and shall not be

connected to any external network or Internet. Please attaché here a general

description/ drawing of your internal network.

4.3.3

Entitlement to give entrance permits shall be granted only to a supplier employee,

whom I.E.Co. will approve beforehand. The supplier shall prepare a procedure

for entrance permits, which will include a process for granting reasonable permits

to authorized personnel. Please attaché here a general description for your

entrance permits procedures including new permits and the termination of void

permits.

REQUIRED OFFERED

Yes/No

OFFERED

Attach file

Yes/No

Attach file

Attach file

Attach file

Yes/No

Yes/No

Yes/No

Attach file

Attach file

Attach file

Yes/No

OFFERED

Yes/No

Yes/No

Yes/No

Yes/No

REQUIRED

REQUIRED

Attach file

Yes/No

Page 57: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

4.3.4

The entrance control system shall enable entry of authorized personnel only. It

shall alarm on unauthorized access attempts, on attempts to neutralize the

control system, and any illegal attempt to enter the secured area through its

doors.

4.3.5The entrance control system shall alarm on 'bothered' door whenever the

secured area door is left open for a period longer than one minute.

4.3.6The entrance control system shall provide reports and facilitate forensic features

namely. full interrogation of events at least ninety days back.

4.4 The secured area shall not be identified as an I.E.Co. project.

4.5

CCTV cameras shall be installed in the secured area to cover the whole area.

The cameras shall photo and record 24 hours. The records shall be stored and

available for at least 90 days back. The recording computer and records shall

reside in a place which may be accessed by security personnel only Please

attaché here a general description for your CCTV permits procedures and a

drawing of your CCTV location regarding the secured area .

4.6

Physical intrusion detection system shall be installed in the secured area. It shall

cover the whole area and all apertures. The intrusion detection system shall

adhere to reputed standards; include local horn; and connection to security

center as per par.4.7. The intrusion detection system shall include at least two

communication channels (cellular and wire) which enable messaging

alarms/faults. The intrusion detection system center/concentrator shall reside in

a place which may be accessed by security personnel only. Please attaché here

a general description for your physical intrusion detection system permits

procedures and a drawing of your physical intrusion detection system location

regarding the secured area

4.7

The entrance control system, the intrusion detection system and the CCTV shall

be connected to security center which is active around the clock. The security

center shall be able to send a force which will reach the secured area within

maximum period of 10 minutes from receipt of alarm or other security message.

4.8

I.E.Co. will be authorized to watch, under prior coordination with supplier, the

information depicted above, on the security systems - in order to examine

security events.

4.9

The supplier undertakes to inform I.E.Co. of any intrusion to its premises even

though nothing has been stolen, immediately upon occurrence. The supplier

shall be responsible to inform I.E.Co. security entities via I.E.Co. central security;

available 24 hours including weekends and holydays, on phone number

97235678045 (multi-line). Example events are: theft of data/information,

intrusion, lost of laptop/external memory etc.

5 SUPPLIER EMPLOYEES

5.1Supplier shall manage records on employees who are involved in any stage of an

I.E.Co. project.

5.2

Supplier shall submit to I.E.Co. the records of every employee designated to

work on I.E.Co. critical project – for a security compliance check, to be performed

by I.E.Co. prior to any access of the worker to any stage of the project. The

supplier shall not employ anyone on the I.E.Co. project at its premises or at

subcontractor/third party premises, unless I.E.Co. has given in writing its approval.

5.3

The supplier undertakes to inform I.E.Co. promptly of any change in the status of

any employee (including third party/subcontractor) who is working on any stage of

an I.E.Co. project. Examples are: criminal conduct, termination of employment,

prolonged private staying abroad without reasonable cause etc.

5.4

The supplier shall submit a copy of the records to I.E.Co. prior to employment of

the person on I.E.Co. project. It is emphasized that a person shall not be allowed

to work or enter the secured area unless prior written consent from I.E.Co..

5.5

The supplier undertakes to monitor the permits and privileges of its employees in

a manner which grants access to the secured area and/or to I.E.Co. information

and/or to handling I.E.Co. project items – only to authorized personnel. In this

context the supplier undertakes to promptly remove the permits and privileges of

any person who ceased for any reason to work on any stage of I.E.Co. project.

5.6The supplier undertakes to sign up each and every authorized worker on the Non

Disclosure Agreement (NDA), appendix 2 of this document.

6 HANDLING I.E.Co. DATA

6.1

A dedicated and secured hard disk shall be allocated by supplier to I.E.Co.

project data. The network on which this data resides shall meet the following

requirements: Please attaché here a general description/ drawing of your

internal network

6.1.1 Disconnected from Internet

OFFERED

OFFERED

REQUIRED

REQUIRED

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Attach file

Attach file

Yes/No

Yes/No

Yes/No

Attach file

Attach file

Yes/No

Page 58: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

6.1.2

Identification to access the data shall be done via complex password with at least

six characters comprising special character and alphanumeric. Password

change shall be enforced once every ninety days. Last six passwords shall not

be allowed. Access shall be locked upon three erroneous trials.

6.1.3The supplier shall monitor for authorized access to I.E.Co. data, and proper audit

trail and logging of this activity.

6.1.4 The supplier shall record and audit all data retrievals.

6.1.5

The supplier shall backup I.E.Co. data and verify that the backup files are

separated from the general premises backup system – namely, I.E.Co. backup

shall be done in a secured network. Please attaché here a general description/

drawing of your backup system network segmentation

6.2 Access to I.E.Co. data shall be granted only to security authorized persons.

6.3Access rights to I.E.Co. data shall be periodically verified (at least once a month).

This activity shall be recorded.

6.4

The supplier shall manage, and present upon request, records of all I.E.Co. data

owned at its premises – including data/information developed by supplier for

I.E.Co.; including physical and electronic/computerized.The records shall also

include dates of receipt and dates of handling.

6.5

Security of records – The supplier shall centrally manage I.E.Co. data, which is

stored on I.E.Co. physical items/entities, at the secured area or at other secured

area conforming to the above security requirements. Regarding this clause, data

is any material pertaining I.E.Co. and the services given by supplier to I.E.Co.

critical systems, which is stored at supplier premises or at subcontractors / third

parties. The supplier shall store the data in locked metal cabinets or vaults.

Access to the stored data physical location shall be granted only to I.E.Co. and

supplier authorized personnel.Please attaché here a general description.

6.6

Cleaning of the secured area shall be done only in the presence of authorized

personnel. The entry and/or work of visitors, maintenance personnel, cleaners

etc. to the secured area shall be personally accompanied by supplier

employee(s) throughout their presence in the secured area.

6.7The door of the office/place in which the cabinet/vault is located shall be locked

upon leaving of the last authorized person.

6.8Duplication and coping of the material shall be done only by authorized person.

Surplus copies shall be promptly discarded via shredding.

6.9

The supplier shall not forward I.E.Co. information to third party unless given in

advance written consent from I.E.Co.. The information shall be transferred in

encrypted manner.

6.10

If I.E.Co. classified information/data needs to be processed on an external

computing machine such as a laptop (henceforth: laptop), the following directives

shall apply: Please attaché here a general description of your security policy

regarding this issue.

6.10.1The laptop shall be connected only to the secured network of the supplier per

par. 6.1

6.10.2

The laptop shall not be connected to any other network, including wireless. This

directive shall be enforced by physical and logical disconnection of the

connection capability.

6.10.3Supplier shall enforce its security policy, including antivirus updates, on these

laptops.

6.10.4

The hard disc of the laptop and any other device which storing I.E.Co. classified

material, shall be encrypted. The encryption tool shall be approved in advance

by I.E.Co. security bodies.

6.10.5Laptops shall not be left unattended in a parking car or other vehicle, including

trunk /luggage compartment.

6.10.6I.E.Co. data shall not be allowed to be taken to workers residence via laptop or

any other mean.

7 PROTECTION OF THE PROJECT COMPUTERIZED ITEMS

7.1

The project shall be developed in an isolated network (henceforth: the secured

network). The secured network shall not be connected to internet or any external

network. The data may be stored on the secured network. The Manufacturer

may offer alternatives to this chapter that will protect I.E. Co.'s information at

Manufacturer's network. The I.E.Co. will not undertake to approve/commit this

alternative Please attaché here a general description/ drawing of your network

7.2

The secured network configuration shall be planned in advance with I.E.Co.

collaboration. The command and control on the secured network components

shall be solely in the hands of the supplier, not by any third party.

OFFERED

Yes/No

Yes/No

Yes/No

Attach file

REQUIRED

Yes/No

Attach file

Yes/No

Yes/No

Yes/No

Attach file

Yes/No

Yes/No

Yes/No

Yes/No

Attach file

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 59: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

7.3The secured network configuration shall be preserved throughout the project.

Any configuration change shall have prior written I.E.Co. approval.

7.4

The supplier shall monitor and control the secured network and its configuration

continuously. As a minimum the supplier shall control the users, password policy

– change, complexity, configuration of security devices, updated antivirus,

communication security and prevention of attempt to connect unauthorized

devices. The supplier shall own documented procedures for this activity.

7.5

The test equipment used during all phases of the project shall conform to the

following requirements: Please attaché here a general description/ drawing of

your network

7.5.1The test equipment shall be connected to the secured network only, and comply

the secured network requirements.

7.5.2

In case the test equipment had been used in other projects, the supplier shall fully

reset the equipment, uninstall and erase all tools and files which where used by

the previous projects, perform antivirus check, neutralize all access from external

devices, perform hardening according to joint I.E.Co.-supplier procedures; and

prevent execution of any files which are not legal part of I.E.Co. project.

7.6

On any security event in the secured network such as intrusion, virus,

unidentified device or any exception from the network routine activity/behavior –

the supplier undertakes to promptly inform I.E.Co. security bodies, via I.E.Co.

security report center; the availability of which is 24 hours, including weekends

and holidays, phone number 972768642555 (multi line), Email

[email protected]. The message must be by phone and the mail should

serve as a backup only.

8 TERMINATION OF PROJECT AT THE FACILITY, PACKING AND DELIVERY

8.1Upon termination of the project at supplier premises the following actions shall be

performed, in the presence and with supervision of I.E.Co. representative:

8.2 Disassembly of project items and preparation to delivery.

8.3

I.E.Co. representative shall put a unique sticker on each case (namely items

which unite to a case such as PC, controller etc.). The sticker will be supplied by

I.E.Co. security department. The sticker shall be placed in a manner which

disables the opening of the case from any side unless damaging the sticker.

8.4 The delivery list shall indicate every device which had been marked with a sticker.

8.5During the entire packing and delivery phases the project equipment shall be

placed in the secured area.

8.6

Upon receipt of delivery in Israel, the cases shall be opened in the presence of

I.E.Co. representative, and all listed stickers shall be checked for integrity. In

case any of the above requirements is violated, an immediate notification to

I.E.Co. security center shall be made.

8.7

Supplier shall return to I.E.Co. all the information stored at its premises regarding

I.E.Co. project, except for technical documentation which has been decided by

I.E.Co. and supplier to remain in the hands of the supplier for maintenance. All

security requirements shall apply regarding this information as long as it is being

held at supplier premises, even though the project period is over.

9 CORRESPONDENCE AND EXCHANGE OF INFORMATION

9.1

All correspondence between I.E.Co. and the supplier regarding the critical

system, such as operation, maintenance, configuration, reports etc; and

particularly configurations of security measures – shall be done via encrypted

media. The encryption of the media shall be done by reputed standard and

proven technology which conforms to the networking/communication and security

infrastructure at I.E.Co.. General guidelines for this issue are: data encryption,

authentication of data source, integrity of data, ratification upon receipt and

sending of data Please attaché here a general description/ drawing of your

solution.

9.2Validity – these requirements shall be valid for all phases of the contract,

beginning with kickoff, through installations and operation.

10 SUPPLIER EMPLOYEE CONDUCT AT I.E.Co. SITES

10.2Supplier personnel shall coordinate all site visits with the power plant personnel

and will be escorted during their visits.

10.3 Connecting portable computers to the system

10.3.1Supplier support personnel shall comply with I.E.Co. site's general policy and

rules of data security.

10.3.2

Any requirement for the connection of an external computer to the system shall

be previously coordinated with the I.E.Co. site data security manager and the

system manager.

OFFERED

OFFERED

Yes/No

Yes/No

Yes/No

OFFERED

Yes/No

Yes/No

Yes/No

Yes/No

Attach file

Yes/No

Yes/No

REQUIRED

REQUIRED

Yes/No

Yes/No

Yes/No

REQUIRED

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 60: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

10.3.3

The external computer shall have an updated version of security safeguard

programs for online protection, detection, cleaning and logging of executed

actions to protect from viruses, vandals, worms etc.

10.3.4

Prior to the connection of the external computer to the system, supplier personnel

shall hand-in the computer to the data security manager in the power plant for

thorough checkup of the computer. Only after this checkup is completed, may

the external computer be connected to the system.

10.3.5

If after the checkup, the external computer has been exposed to external data

(other than the System's network, internet, external data transfer such as via Disk

On-Key etc.), the computer shall be handed-in again to the data security

manager in The power plant for checkup of the newly added files.

Yes/No

Yes/No

Yes/No

Page 61: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 1

Of:

13

Page:

1

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

DOCUMENT: Electrical Standard Specification.

SUBJECT: Control Cubicles –

Electrical Wiring Requirements.

Cancels: EPD-3/99 Rev. F Rev. -

Applicable:

09/2004

Date:

09/2004

Page 62: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 2

פרויקט:

CONTROL CUBICLES - ELECTRICAL WIRING REQUIREMENTSנושא:

סוג מסמך:

עקרון תכנון תזכיר תכנוני

מפרט נייר עמדה

חישובים

שימת מחשבר תקן / נוהל

02 01 - הוצאה מס' 09/2004 תאריך:

חתימה שם חתימה שם חתימה שם ר. ושלר הכין

א. רוזנברג בדק ג. סנטו תואם תואם מ. זיידמן תואם א. פינץ תואם אלצ'הד"ר ל. אישר

אישרר הפצה אל ה"ה:

שם

שם שם שם

לידיעתך לידיעתך לידיעתך לידיעתך

X א. כהנא X ב. ציטרינל X ג. רגף X ל. אלצ'ה

X מ. אלקלעי X ל. ברגר X א. כהן X א. רוזנברג

X ג. סנטו X ז. קאופמן X ג. שטיינברג X א. פינץ

X מאירי. ב X י. סיליקי X ל. וורטמן X מ. זיידמן

X ש. אופק X י. שרושי X ד. אליעזר X ר. ושלר

X ה. לנדאו X א. רובינשטיין X ר. קליין X א. פינרו

X א. שחף X ד. פרץ X ב. זוניס X נ. קרידרמן

X תיק X י. סוסקין X א. פישמן X ל. פלינר

X א. לזר X מ. דוידוב X ס. הראל

X א. אלכסנדרוב X ג. גראוס X א. דימיטריו

חברת החשמל לישראל בע"מ חטיבת פרויקטים הנדסיים

אגף תכנון הנדסי המגזר החשמלי

מספר המסמך:

The Israel Electric Corporation Ltd.

Engineering Projects Group

Engineering Division

Electrical Sector

מספר הנוהל:EPD-A.03

הוצאה:01

דף:2

מתוך:13

Page 63: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 3

Of:

13

Page:

3

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03 CONTENT: PAGE

1. GENERAL 4

2. WIRING MATERIALS AND REQUIREMENTS 4

3. TERMINAL BLOCKS 6

4. ARRANGEMENT OF WIRING 8

5. TERMINATIONS 10

6. MISCELLANEOUS 11

7. WIRING TESTS 12

8. APPENDIX 1 – INTERNAL WIRING COLOR CODING 13

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 64: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 4

Of:

13

Page:

4

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

1. GENERAL.

1.1 This standard applies in the implementation of control , protection ,

supervisory, instrumentation and measuring circuits included in

control systems, protection systems, switchgears, MCC's, control

panels and other electrical cubicles of Power Stations and Substations.

1.2 All Control Cubicles shall conform to this Standard Specification ,

except where overruled by specific requirements of the Project

Specification.

1.3 This Standard shall also be read in conjunction with Standard

EPD-5/2002 Rev.F: " CONTROL CUBICLES REQUIREMENTS "

( or EPD –A.05 , to be issued in the future ) .

2. WIRING MATERIALS AND REQUIREMENTS.

2.1 WIRING MATERIALS.

2.1.1 The Israeli or European manufacturers shall use stranded copper

conductors having halogen free insulation.

The wire shall be type HO7Z-K for 750V rated voltage, according

to Standards CENELEC HD 22.1 and HD 22.9.

2.1.2 The American manufacturers shall use stranded copper switchboard

wire , 90ºC maximum operating temperature Heat – Resistant SIS

Insulation , according to National Electrical Code ( NFPA 70-1996 ) ,

table 310-13 , having 600V rated insulation .

2.1.3 Connections between fixed and hinged panels shall be made with stranded

( extra-flexible) switchboard wire , having the same insulation as specified

above .

2.2 CONTROL WIRING SIZE

2.2.1 For control circuits having a control voltage of 220 VDC or

230 VAC , wires sized 1.5 sq.mm ( No. 16 AWG ) shall be used . 2.2.2 For control and supervisory circuits in which the current is less than

0.2 A , wires sized 1.0 sq.mm ( No. 18 AWG ), shall be used .

2.2.3 For control and supervisory circuits of European manufactured

Control Systems (DCS) , in which the current is less than 0.2 A ,

wires sized 0.5 sq.mm ( No. 20 AWG ) can be used.

Cancels: EPD-3/99 Rev.F Rev. 01

Applicable:

09/2004

Date:

09/2004

HOLD

Page 65: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 5

Of:

13

Page:

5

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

2.3 POWER WIRING SIZE .

2.3.1 This standard refers to the following power circuits :

a. Primary and secondary connections of control transformers.

b. Incoming power circuits.

2.3.2 The wiring of the above devices shall be made with similar wires as

defined in paragraph 2.1.

The size of the wire shall be correlated with the control transformer primary and secondary currents , with the incoming power circuits

current and with the circuit protection .

2.4 CURRENT TRANSFORMER WIRING SIZE. Current Transformer Circuits wiring shall be made with similar wires

as defined in paragraph 2.1.

The minimum wire size shall be 2.5 sq.mm (No. 14AWG). 2.5 INSTRUMENT WIRING SIZING (Low Level Signal Wiring).

2.5.1 Shielded instrumentation cable shall be used on all low level

signal

wiring.

Unless otherwise specified in the Project Specification , the

Contractor shall use twisted-pair No. 18 AWG , Class B stranded-

tinned copper-wire , with minimum use 300V insulation over each

conductor, aluminized mylar tape ( with stranded-tinned copper

drain wire) over both conductors , and an overall jacket . 2.5.2 If apparatus cannot accept conductors of sizes specified above

than the maximum size of conductors accepted by these

apparatus, can be used . 2.5.3 For Low Level Signal Wiring of European manufactured Control

Systems (DCS) , shielded wires sized 0.5 sq.mm ( No. 20 AWG ),

similar to those used for control wiring can be used , according to

the manufacturer standard.

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 66: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 6

Of:

13

Page:

6

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

3. TERMINAL BLOCKS .

3.1 REQUIREMENTS FOR ISRAELI OR EUROPEAN

MANUFACTURERS . 3.1.1 The terminals shall comply with IEC 60947-7-1 , July 2002

Standard .

3.1.2 Type of terminals: screw type terminals. 3.1.3 The housing shall be made of thermosetting or thermoplastic

materials having the following characteristics :

a. Tracking resistance …….. CTI : 600

b. Continuous service temperature ……. 100 ºC

c. Inflammability class………………… UL94-VO

d. Halogen and asbestos free

e. Good tropical and termite resistance

f. Contamination class ………………… 3

3.1.4 The metal parts ( clamping parts and current carrying parts ) shall

be made of copper alloy to eliminate corrosion .

The screw clamping method shall be vibration resistant. 3.1.5 Mounting rail ……………………………… TS 32 3.1.6 Rated Voltage ……………………………… 800 V

3.1.7 Approved terminal blocks Manufacturers : Phoenix or Wiedmuller ,

as follows :

Phoenix Weidmuller a. Control and Instrumentation wiring

up to 1.5 sq.mm ( No. 16 AWG ) … UK 2.5 N WDU 2.5 N

b. Control and Power wiring

up to 6.0 sq.mm ( No. 10 AWG )…. UK 6N WDU 6N

c. Power wiring

Up to 10 sq.mm ( No. 4 AWG ) …. UK 16N WDU 16N

d. Curent transformer circuits * ……. UGSK/S WTQ 6/1

*: Three (3) terminals shall be used for each current transformer.

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 67: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 7

Of:

13

Page:

7

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

3.1.8 The insulation material of terminal blocks shall not be adversely

affected by abnormal heat and fire .

Compliance to this requirement shall be checked by the needle flame

test, according to Standard IEC 60695-2-2.

3.1.9 Performance Requirements.

3.1.9.1 Temperature Rise.

The terminal blocks shall be tested in accordance with Standard

IEC 60947-1-1, item 8.4.5. The temperature rise of terminals shall not exceed 45ºC.

3.1.9.2 Rated Short-time Withstand Capability. The terminal blocks shall be capable of withstanding for 1 sec. the

rated short-time withstanding current which corresponds to

120A/mm² of its rated cross-section , according to Standard

IEC 60947-1-1, item 8.4.6.

3.1.10 For European manufactured equipment Maxi-Termi-Point

terminals, according to DIN/VDE 0815 Standard can be used .

3.2 REQUIREMENTS FOR AMERICAN MANUFACTURERS. 3.2.1 The terminals shall comply with the NEMA Standard Publication

No. ICS 4 /2000 and shall be UL approved. 3.2.2 Molded thermoset phenolic base – rated 150°C. 3.2.3 Suitable for connection of copper conductors.

3.2.4 Washer head screw contacts.

3.2.5 The metal parts ( clamping parts and current carrying parts ) shall

be made of copper alloy to eliminate corrosion .

3.2.6 Rated insulation voltage :

-- For control and instrumentation circuits less than 120V :

Ui = 300 V

-- For control and instrumentation circuits above120V :

Ui = 600 V

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 68: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 8

Of:

13

Page:

8

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

3.2.7 The following terminal blocks are accepted : a. For control circuits 120 V and above :

Series 1500 or Series 1600, Marathon Special Products

Co. or Catalogue No. 2B112 Buchanan. b. For control circuits less than 120 V and instrumentation :

Series 300 Marathon Special Products Co., or Type

CR151B – General Electric.

4. ARRANGEMENT OF WIRING.

4.1 Wire and wire groups extending from terminal blocks to instruments or

devices on cubicles , or from one cubicle to another , shall be installed

in halogen free ducts or troughs and packed in neatly formed bundles

securely clamped or tied together and supported from the cubicle

framework.

Plastic cable ties ( Halogen free or EPR ) shall be used to bundle wires

outside of ducts or troughs .

No more than 30 wires shall be bundled together in wire hinge loops. 4.2 When wiring is installed in wire ducts or troughs , the edges of the

cut-outs troughs which the wires pass shall be provided with suitable

protection of the insulation from cuts or nicks . 4.3 Shielded instrument cables carrying low level signals shall be in

separate bundles or wire-ways . 4.4 Drain wires and shield tapes shall be fully insulated and terminated at

terminal blocks .

Grounding of shielded wires shall be as defined in the Project

Specification or drawings.

4.5 Wire extensions from wire-ways or bundles to instruments shall be

neatly formed, attached and secured to the cubicles with wire cleats .

Bends in the wiring shall be carefully made in such a manner that the

insulation or cover is not damaged . Care shall be used in removing insulation from the wire , so that the

wire will not be cut or nicked .

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 69: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 9

Of:

13

Page:

9

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

4.6 All wiring shall be installed exactly as shown on the wiring diagrams. 4.7 The maximum number of conductors connected to any one terminal

point on a terminal block shall be two ( 2 ) .

4.8 Spare contacts from each device ( circuit breaker , auxiliary relay ,

control switch, etc ) shall be wired to terminal blocks , as per specific

Project Specification requirements.

4.9 Both ends of each wire shall be tagged with appropriate plastic

markers.

Mylar wire markers such as Brady Type SLFW or similar as agreed

upon, should be used.

4.10 Internal wiring color coding shall be according to Appendix 1 of this

standard specification. 4.11 The wires marking shall be made as follows :

-- The terminal block end of each wire will be tagged with the

terminal number.

-- The instrument or device end of the wire will be tagged with the

respective instrument or device designation and terminal number,

according to the wiring diagram.

4.12 All internal wiring of control circuits will preferable be terminated

by the Contractor at the terminal blocks , rather than between

devices within the cubicle . 4.13 All the alarm circuits should be connected to adjacent terminal block

points , to facilitate Purchaser's field wiring . 4.14 In bench-board type control cubicles applications, switches, lights

and other instruments shall be loop wired.

Sufficient wire length shall be included in the loop to permit complete

removal of all connected devices through the face of the bench-board,

to permit maintenance of the device from the front of the cubicle,

without disconnecting any wires . 4.15 Wiring shall be routed in such a manner that it will not prevent blank

cubicle ( spare ( from being used for the addition of future

equipment.

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 70: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 10

Of:

13

Page:

10

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

5. TERMINATIONS. 5.1 Compression type ( solder-less) lugs or ferrules shall be applied on the

ends of all stranded wires for connection to terminal blocks or to

instruments.

For connection to screw type terminals , isolated fork type terminal

lugs should be used . The lugs should be tin plated to resist corrosion. 5.2 The wire insulation shall be removed for the lug application without

nicking the conductor.

The wire shall be firmly inserted into the lug and crimped with the

specified tool , recommended by the lug manufacturer .

Devices having compression clamps, push-on, etc type terminals will

be wired accordingly.

5.3 All solder and push-on type connections shall have snug fittings

insulated sleeves which cover the entire lug and extend 1/4 inch

(6mm) over the insulation.

5.4 Terminal blocks shall be provided for terminating all wiring entering

and leaving the cubicles, except the leads from thermocouples and

other temperature detecting devices , and devices connected with

prefabricated cables, that may be field run directly to the terminals in

the instrument cases.

5.5 Thermocouple extension wire and other solid wire terminations shall

be made without the use of lugs.

5.6 The arrangement of terminal blocks for Purchaser's connections shall

permit convenient cable installation.

Cable supports shall be provided for Purchaser's wiring.

Wiring troughs shall be provided in areas requiring a high density of

such cables.

Routing paths of all such cables shall be shown on Contractor's cubicle

wiring diagrams.

Adhesive-backed wire bundle grips are not accepted for supporting

wire extensions.

5.7 Terminal blocks shall be arranged with terminals in vertical or

horizontal rows.

Terminal blocks shall have each point identified indelibly.

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 71: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 11

Of:

13

Page:

11

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03 One side of the terminal blocks shall be left free for Purchaser's connections. All jumpers between terminals shall be made on the internal wiring

side .

Terminals associated with individual items of equipment shall be

grouped together for convenient cable connections .

5.8 The terminal blocks shall not be mounted closer than 7 inches

( 180 mm ) from the control cubicle walls and at least 10 inches

( 250 mm ) from the cable entrance .

Central line distance between terminal blocks shall be a minimum

of 8 inches ( 200 mm ) . Where terminal blocks for Purchaser's connections are mounted on

vertical wire-ways , the inside area of said wire-ways shall be reserved

exclusively for Purchaser's incoming cables . 5.9 All incoming power terminals shall be clearly identified in a manner

distinctly different from all other terminations , for safety in

maintenance. It is recommended to group the terminals as follows : 5.9.1 Power

5.9.2 Control AC / DC ( 120 V/ 220 V) 5.9.3 Control DC circuits 24 VDC , 48 VDC , 60 VDC

5.9.4 Instrumentation

5.10 Where bottom cable entry is used , the vertical wire-ways shall be

located over floor openings , to allow Purchaser's cable to have a clear

run directly to the terminal blocks .

6. MISCELLANEOUS .

If any component is not available at the time of shipment , Contractor

shall provide wooden templates complete with accurate terminal arrangement and all wiring terminated . The plate shall closely resemble the configuration of the missing

component , so that the cubicle wiring can be bundled and identified

for easy substitution of the missing device in field .

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 72: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 12

Of:

13

Page:

12

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03 Where cubicles are shipped in sections for connecting together in field, the

wiring between sections shall be factory made, to be connected in field.

Identically tagged terminal blocks shall be provided on each side of

the shipping unit.

Jumpers shall be provided for convenient connection in field.

7. WIRING TESTS .

The wiring shall be capable of withstanding a one (1 ) minute field

test at 1500 VAC , all parts to ground ( except the wiring for electronic equipment ) .

The factory tests shall demonstrate freedom from grounds and accuracy of

the wiring.

Point-to-point continuity tests and electrical insulation tests shall be factory

made.

Megger or other high voltage tests shall not be applied to any coaxial

shielded or solid-state components.

Cancels: EPD-3/99 Rev. F Rev. 01

Applicable:

09/2004

Date:

09/2004

Page 73: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A7 SPECIFICATION SR-152

A7 - 13

Of:

13

Page:

13

Control Cubicles –

Electrical Wiring Requirements.

STANDARD No.

EPD-A.03

8. APPENDIX 1 – INTERNAL WIRING COLOR CODING

The following color coding is required for the internal wiring of control

cubicles :

8.1 AC CIRCUITS. 8.1.1 Protective earth : Yellow - Green ( mandatory )

8.1.2 Neutral : Blue

8.2 AC POWER CIRCUITS. 8.2.1 One ( 1 ) phase : Brown

8.2.2 Three ( 3 ) phase :

-- Phase L1 : Brown ( preferred ) , or

Brown + L1 marking / sleeve

-- Phase L2 : Brown – Orange ( brown with one orange

strip on the whole wire length -preferred ) ,

or

Brown + L2 marking / sleeve

-- Phase L3 : Brown – Black ( brown with one black strip on the whole wire length- preferred) ,

or

Brown + L3 marking / sleeve

8.3 DC POWER CIRCUITS.

8.3.1 ( + ) : Brown

8.3.2 ( - ) : Blue 8.4 CONTROL CIRCUITS. : Grey ( preferred ) , or Black .

- FINAL -

Cancel: EPD-3/99 Rev. F Rev.

01

Applicable:

09/2004

Date:

09/2004

Page 74: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A8 SPECIFICATION SR-152

A8 - 1

Static calculation of stresses on silicon rubber SF6/air bushing

Calculation of safety factor

SF6/air bushing type ..........................................................................

SF6/air bushing dimensions and weight acc. to attached drawing ......

Height of SF6/air bushing .................................................................. m

Weight of SF6/air bushing .................................................................. kg

Maximum Mechanical Load of insulator............................................. kNm

Rated static terminal load on X, Y and Z directions

(including tensile force and weight due to connected conductors) ..... 2700 N

Short circuit terminal load

(short circuit current acc. to Specification) ......................................... 4000 N

Wind velocity on SF6/air bushing and connected conductors ............. 44 m/sec

Height of mounting of SF6/air bushing (will be considered in calculation of seismic load) .............................. m

Earthquake load characteristics:

Horizontal earthquake accelerations ................................................. 0.25 g

Vertical earthquake accelerations......................................................

Frequency .........................................................................................

Damping of critical damping ..............................................................

Horizontal acceleration response ......................................................

Vertical acceleration response ..........................................................

1) Condition 11 – Routinely expected loads

(Design pressure 100%, Mass 100%, Rated terminal load 100%, Wind pressure

30%)

Bending moment on bottom insulator:

by design pressure (X/Y direction) ..................................................... kNm / kNm

by rated terminal load (X/Y direction) ................................................ kNm / kNm

by wind pressure (X/Y direction) ........................................................ kNm / kNm

TOTAL: kNm / kNm

Safety factor for insulator:

MML/TOTAL bending moment on bottom insulator) .......................... kNm / kNm

Vertical forces on bottom insulator:

by design pressure (Z direction) ........................................................ N

by rated terminal load (Z direction) .................................................... N

by weight (Z direction) ....................................................................... N

TOTAL: N

1 Please add the calculation of each required value of bending moment

Page 75: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A8 SPECIFICATION SR-152

A8 - 2

Condition 2 – Rarely occurring loads (Alt. 1)

(Design pressure 100%, Mass 100%, Rated terminal load 50%, Wind pressure

100%, Short circuit load 100%)

Bending moment on bottom insulator:

by design pressure (X/Y direction) ..................................................... kNm / kNm

by rated terminal load (X/Y direction) ................................................ kNm / kNm

by wind pressure (X/Y direction) ........................................................ kNm / kNm

by short circuit load (X/Y direction) .................................................... kNm / kNm

TOTAL: kNm / kNm

Safety factor for insulator:

MML/TOTAL bending moment on bottom insulator) .......................... kNm / kNm

Vertical forces on bottom insulator:

by design pressure (Z direction) ........................................................ N

by rated terminal load (Z direction) .................................................... N

by weight (Z direction) ....................................................................... N

TOTAL: N

2) Condition 3 – Rarely occurring loads (Alt. 2)

(Design pressure 100%, Mass 100%, Rated terminal load 70%, Wind pressure

10%, Seismic load 100%)

Bending moment on bottom insulator:

by design pressure (X/Y direction) ..................................................... kNm / kNm

by rated terminal load (X/Y direction) ................................................ kNm / kNm

by wind pressure (X/Y direction) ........................................................ kNm / kNm

by seismic load (X/Y direction) .......................................................... kNm / kNm

TOTAL: kNm / kNm

Safety factor for insulator:

MML/TOTAL bending moment on bottom insulator) .......................... kNm / kNm

Vertical forces on bottom insulator:

by design pressure (Z direction) ........................................................ N

by rated terminal load (Z direction) .................................................... N

by seismic load (Z direction) ..............................................................

by weight (Z direction) ....................................................................... N

TOTAL: N

Page 76: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A8 SPECIFICATION SR-152

A8 - 3

3) Total Loading and Safety factors

Total bending moment

Required/Offered safety factor

Vertical forces on

Z directions

(N)

on X

directions (Nm)

on Y directions

(Nm)

on X directions

on Y directions

1. Condition 1

1.1 Bottom section of insulator

2.1 /...... 2.1 /......

2. Condition 2

2.1 Bottom section of insulator

1.5 /...... 1.5 /......

3. Condition 3

3.1 Bottom section of insulator

1.2 /...... 1.2 /......

Page 77: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A9 SPECIFICATION SR-152

A9- 1

Main anti-corrosion coatings in GIS

No Components Material

Anti-corrosion coatings

Remarks Galvanizing Painting

Zn coating by hot dip process

Zn plating by metallization

Zn plating by electrolytic

process

Primer coat Intermediate coat

Finish coat Total paint / color

(µm) (µm) (µm) (µm) (µm) (µm) (µm) 1 Enclosure

1.1 Outdoor sections 1.2 Indoor sections

1.3 Internal surface 2 Expansion bellows 3 Housings

3.1 Circuit breakers

3.2 Disconnectors

3.3 Earthing switches 4 LCC

5 Support frame

5.1 Outdoor sections

5.2 Indoor sections 6 Bolts and nuts 7 Operating links

Page 78: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B1 SPECIFICATION SR-152

App B1/1

1.1

1.2

1.2.1

Type 1-H.V. Type 2-L.V.

1.2.3 p1-p2 p1-p2 =

1.2.4 s/p1 > s/p1 =

1.2.5 c > c =

1.2.6 α = α =

1.2.7 Da < Da =

1.2.8 SCD SCD =

1.2.9 RUSCD RUSCD =

1.2.10 ka = ka =

1.2.11 kad = kad =

1.2.12 Corrected USCD = Corrected USCD =

1.2.13 L L =

1.2.14 CF= L/A < CF= L/A =

1.2.15 l1/d1 < l1/d1 =

1.2.16 l2/d2 < l2/d2 =

1.2.17 tc ≥ tc ≥ N.A.

composite (polymer)

15 mm

Alternating sheds

Figure 1

Requirements for Alternating sheds type, Composite Insulator designed for

Type 1- H.V. (161 kV) and Type 2- L.V. (24 kV) bushings:

REQUIRED OFFERED

composite (polymer) parametersparameters1.2.2

0.9

corrected USCD=RUSCD∙Ka∙Kad

L_total=(u_max/√3)∙corrected USCD

300

31 mm/kV

53.7 mm/kV

45 mm

10˚-15 ˚

6

4

4

4

1

according to clause 2.3.10 below

BUSHINGS REQUIREMENTS

Page 79: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B1 SPECIFICATION SR-152

App B1/2

2.1

2.2

2.2.1

Type 1-H.V. Type 2-L.V.

2.2.3 s/p > s/p =

2.2.4 c > c =

2.2.5 α = α =

2.2.6 Da < Da =

2.2.7 SCD SCD =

2.2.8 RUSCD RUSCD =

2.2.9 ka = ka =

2.2.10 kad = kad =

2.2.11 Corrected USCD = Corrected USCD =

2.2.12 L L =

2.2.13 CF= L/A < CF= L/A =

2.2.14 l/d < l/d =

2.2.15 tc ≥ tc ≥ N.A.

2.2.2 parameters composite (polymer) parameters

1

according to clause 2.3.10 below

4.5

4.5

6

300

31 mm/kV

53.7 mm/kV

0.75

45 mm

10˚-15 ˚

Requirements for Non-Alternating (Uniform) sheds type, Composite

Insulator designed for Type 1- H.V. (161 kV) and Type 2- L.V. (24 kV)

bushings:

REQUIRED OFFERED

composite (polymer)

Non-Alternating (Uniform) sheds

Figure 2

corrected USCD=RUSCD∙Ka∙Kad

L_total=(u_max/√3)∙corrected USCD

Page 80: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B1 SPECIFICATION SR-152

App B1/3

2.3

2.3.1

2.3.2

2.3.3

2.3.4

2.3.5

2.3.6

2.3.7

2.3.8

2.3.9

2.3.10

2.3.11

2.3.12

2.3.13

2.3.14

2.3.15

2.3.16 tc

The thickness of the SIR (silicone rubber) Envelope of bushing in its

connection zones with the bushing upper metal part (Head) and with the

bushing bottom metal part (Bottom Flange) at least 6 (mm)

Kad

Diameter factor

Kad = 1, for Da < 300 mm

Kad = 0.0005 Da + 0.85, for Da ≥ 300 mm

Corrected

USCD

Corrected reference unified specific creepage distance

corrected USCD=RUSCD∙Ka∙Kad

L Total nominal creepage distance - L_total=(u_max/√3)∙corrected USCD

SCD Specific Creepage Distance according to SPS class (e)

RUSCDReference Unified Specific Creepage Distance according to SPS class (e)

RUSCD=SCD∙√3

CF=L/ACreepage factor is a global check of the overall density of creepage

distance.

l/d

The highest ratio found on any section, for example on the underside of a

cap and pin insulator.

l - The part of the creepage distance measured between the above two

points.

d - The straight air distance between two points on the insulating part or

between a point on the insulating part and another on a metal part.

A Arcing distance of the insulator.

Ka Altitude factor - Ka = 1, for altitudes up to 1000 m

c The minimum distance between adjacent sheds of the same diameter.

α Shed angle.

Da Average diameter – Da = (Ds1+Ds2+2Dt)/4

Terms, definitions and abbreviations

Parameter Description

s/pSpacing versus shed overhang is ratio of the vertical distance between

two similar points.

p1-p2 Shed overhang distance.

Page 81: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B1 SPECIFICATION SR-152

App B1/4

3

Figure 3

Thickness of the SIR (silicone rubber)

Page 82: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/1

THE ISRAEL ELECTRIC CORPORATION LTD. PLANNING DEVELOPMENT AND TECHNOLOGY DIVISION RELIABILITY AND H.V. EQUIPMENT DEPARTMENT

SR-152

___________________________________________________

RELIABILITY, MAINTAINABILITY and SAFETY

REQUIREMENTS

OF

30MVA 161/24-36kV MOBILE SUBSTATION

VERSION A VERSION B

Name Date Signature Name Date Signature

PREPARED M. BEN-YEHUDA 24.5.17

CHECKED M. CHAUSHU

APPROVED DR. H. BEN HAIM

Page 83: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/2

RELIABILITY, MAINTAINABILITY, SAFETY (RMS)

1. Reliability

The Contractor shall present the reliability tasks and methods which he used to improve

the design for reliability, and to evaluate the MTTF/MTBF of the Mobile Substation and its

main components.

The Contractor shall provide expected values for the relevant parameters of the Mobile

Substation (see Table 1).

2. Failure Analysis

From his Failure Reporting Analysis and Corrective Action System (FRACAS), Contractor

shall present a failure report and the analysis of the failures which occurred during the

service life of similar Mobile Substations manufactured by him. The report should include

the withdrawn conclusion and the corrective actions subsequently undertaken.

3. Maintainability

Contractor shall present his maintainability tasks and methods which are he used to

improve the design for maintainability and to decrease and determine the following

parameters for the main maintenance activities (see Table 2):

(1) Duration of maintenance activities.

(2) Man power and man hours needed for maintenance.

4. Critical Accessories and Spare Parts

Contractor shall present the methods he used to identify the critical accessories and spare

parts, and submit his recommendation list for these items. Critical items shall be identified

in accordance with Task 208 of MIL-STD-785.

5. Failure Mode and Effect Analysis (FMEA)

The Contractor shall submit an FMEA report aimed to identify potential design

weaknesses. This report should be prepared in according with MIL-STD-1629, or IEC-

60812. The analysis will include compensating provisions and inputs to the maintenance

plan.

Page 84: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/3

6. RAM Data

6.1 Contractor Declaration

Contractor shall declare the following RAM parameters for his all Items of Mobile

Substations. Contractor shall build a table for each Item with Its detailed components as

per the following tables for:

Table 1.1: RAM DATA FOR ITEM 1: 170 kV SF6 GIS

Where:

MTTF : Mean Time To Failure. EOL : Expected Operating Life. MTTR : Mean Time To Repair. MTTPM: Mean Time To (perform) Preventive Maintenance. MTBPM: Mean Time Between Preventive Maintenance.

MTTPM

(Hrs)

MTBPM

(Yrs)

MTTR

(Hrs)

EOL

(Yrs)

MTTF

(Yrs)

Component

GIS bus-ducts

GIS circuit breaker

GIS circuit breaker OM

GIS disconnector switches

GIS disconnector OM

GIS earthing switches

GIS earthing switches OM

GIS combined disconnector and earthing switches (if applicable)

GIS combined disconnector and earthing switches OM (if applicable)

GIS current transformer

GIS voltage transformer

SF6 air bushing

Digital Control

Monitoring System

Page 85: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/4

Table 1.2: RAM DATA FOR ITEM 2 - POWER TRANSFORMERS

MTTPM (Hrs)

MTBPM (Yrs)

MTTR (Hrs)

EOL (Yrs)

MTTF (Yrs)

ITEM

Three Phase Power Transformer

Oil Air Bushing

Bushing Current Transformers

On Load Tap Changer

Tap Changer Motor Drive

Voltage Regulator

Tap-Changer Position Indicator

Fan Motor

Fans

Oil Level Indicator

Pressure Relief Valve

Oil pointer thermometer for local measurement

Winding pointer thermometer for local measurement

Supervision equipment alternative 1

Supervision equipment alternative 2

Buchholtz Relay

Protective Relay for OLTC

Active Parts

Table 1.3: RAM DATA FOR ITEM 5: DC SUPPLY

Table 1.4: RAM DATA FOR ITEMS 6 and 7: 36 kV SF6 GIS

MTTPM

(Hrs)

MTBPM

(Yrs)

MTTR

(Hrs)

EOL

(Yrs)

MTTF

(Yrs)

Component

Battery compartments

Battery charger

MTTPM

(Hrs)

MTBPM

(Yrs)

MTTR

(Hrs)

EOL

(Yrs)

MTTF

(Yrs)

Component

GIS bus-ducts

GIS circuit breaker

GIS circuit breaker OM

GIS disconnector switches

GIS disconnector OM

Page 86: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/5

Table 1.5: RAM DATA FOR ITEM 8: PETERSEN COIL

MTTPM (Hrs)

MTBPM (Yrs)

MTTR (Hrs)

EOL (Yrs)

MTTF (Yrs)

ITEM

Three Phase Power Transformer

Oil Air Bushing

Current Transformers

Operating mechanism

Cooling system

Oil Level Indicator

Oil pointer thermometer

Adjustable Thermal monitor

Buchholtz Relay

Table 1.5: RAM DATA FOR ITEM 9: CAPACITOR BANK

GIS earthing switches

GIS earthing switches OM

GIS combined disconnector and earthing switches (if applicable)

GIS combined disconnector and earthing switches OM (if applicable)

GIS current transformer

GIS voltage transformer

Cables connection

Digital control system

Monitoring system

MTTPM

(Hrs)

MTBPM

(Yrs)

MTTR

(Hrs)

EOL

(Yrs)

MTTF

(Yrs)

Component

Automatic Resonance Controller

Current Injection Unit

Capacitor unit

Damping reactor

Disconnector

Earthing switch

Current transformer for unbalance protection

Support insulator

Page 87: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/6

Table 1.6: RAM DATA FOR OTHER COMPONENTS

Table 2: Main Maintenance Activities Data

Maintenance Activity Mean Time (Hrs)

Man Power

Man-Hours

Where:

Mean Time = Mean time to perform a main maintenance activity Man Power = Number of required workers for performing a main maintenance activity Man Hours = Number of workers X time duration of main maintenance activity

6.2 Field Demonstrated RAM Data

In Addition to the RAM data mentioned above, Contractor shall submit also the following

information:

6.2.1Quantities of similar Mobile Substation installed in all locations, each year since

1990.

MTTPM

(Hrs)

MTBPM

(Yrs)

MTTR

(Hrs)

EOL

(Yrs)

MTTF

(Yrs)

Component

Automatic Resonance Controller

Current Injection Unit

Differential Protection relay

Overcurrent Protection relay

Lock Out relay

Breaker Failure Protection (BFP)

Earth Fault (Wattmetric) Protection

Load shedding

Fire protection system

Security Alarm system

HV cables

LV cables

Control and Measuring (shield) cables

Page 88: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/7

6.2.2 Similar transformer failure information like:

(1) Number of failure each year.

(2) Description of failures.

(3) Root causes classification.

(4) Mean times to repair/replace in the field (MTTR).

Table 3: Field Demonstrated RAM Data for Mobile Substation Model No. _______________

Field RAM Data

2007 2008 2009 2010 2012 2013 2014 2015 2016 2017

Total number of installed Mobile Substations

Total No. of repairs/replaces for any reason

Failures due to wrong design

Failures due to faulty production

Failures due to bad use/handling

Random failures

Mean Time To Repair/Replace

Total accumulated operating time (Mobile Substations x Years) for _____ KV, _____ MVA

Mobile Substation, from 2007 to 2017 is ______ [Mobile Substation x years].

Please arrange the above mentioned information in the following table:

Page 89: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/8

Unreliability Demonstration Procedure

7. General

Since there are only a few Mobile Substations according to Annexure C in this tender, it is

not practical to apply a standard – classic reliability demonstration plan (i.e. IEC-60605, or

IEC-61124). This fact is due to the long calendar test time expected in such a

demonstration. For this reason an “unreliability demonstration” was designed for this

tender, and I.E.C will prepare a UDP, based on the following principals.

In the UDP the UPPER limit for the MTBF, rather than the lower limit, will be calculated

from demonstration results, with given confidence level. Thus, this test will verify if the

demonstrated MTBF is WORSE than a certain value (close to the required MTBF).

The purchased MOBILE SUBSTATION will be participating in an Unreliability

Demonstration Procedure (UDP) after their installation, in order to verify in case they do

not comply with their specified reliability (Failure Rate/MTBF). The UDP will be started

right after the installation, and operation of the MOBILE SUBSTATION, and will be

performed by I.E.C crew. Final parameters for the UDP will be discussed at contract

phase.

7.1 Reliability Requirements

The maximum acceptable failures rate, or minimum MTBFs are as follows:

(1) 0.01/Yr for Major failures (MTBF, = 100 Yrs).

(2) 0/04/Yr for Minor failures (MTBF, = 25 Yrs).

7.2 Plan Parameters

(1)Test Time

The Test Time is the operating time summation of all tested units. It is measured in

Units*Years and depended on agreed contractor risks. In the further it was calculated for

contractor risks only. The more of units the less of years (calendar time) since the Test

Time it is fixed. In case of a failure, the faulty MOBILE SUBSTATION will be repaired and

replaced as soon as possible otherwise; the calendar time will be lengthening, to keep

Test Time to agreed Units*Years demonstration.

Page 90: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/9

(2) Maximum Number of Failures

Using equations: (1), and (2) in the following Par. 7.3, the maximum number of failures

allowable is determined to be as follows:

- 1 minor failure.

- 0 (zero) major failures.

Description Minor Failures Major Failures

Test Time*Units [Unit*Years] Ta=15 Ta=15

calendar time of test [years] t=1.5 t=1.5

Reject if faults number are r = 2 1

Probability of rejection 0.122 0.139

U [Yrs] with CL=80% 28 142

Where:

r - Number of relevant failures.

- Contractor’s risk.

U - Upper limit for the MTBF

CL - Confidence level

7.3 Rational

If the number of occurring failures in t years is X, and the maximum failures allowed in that

period is k, then the probability of not passing the demonstration is, when there will be

more than k failures in t years. The probability is actually identical to Contractor’s risk ().

This risk is given by the following Poisson distribution formula:

k

0i

-t/i

i!

e)t/-1kPX

(

(1)

Where is the required MTBF.

The upper limit for the MTBF, U, may be calculated by using the chi-square distribution:

,2r)2CL(2U

t2

(2)

Page 91: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/10

7.4 Failure Policy and Consideration

(1) I.E.C will implement a Failure Reporting, and Analysis System.

(2) All kinds of failures will be registered by the Failure Detector, in a Failure Report Form

(FRF) including those occurring during the Warranty Period. However, only the

relevant ones will be considered and counted for Accept/Reject criterion. The FRF will

include all failure information.

(3) In case of Systematic Failure the manufacturer will repair all the MOBILE

SUBSTATION, and perform a Corrective Action (preventive measures) to all the

MOBILE SUBSTATION including which already installed, to I.E.C satisfaction. In this

case, the Failure Review Board (as detailed in aragraph 7.5) may decide, depends

upon the failure severity, to reset the accumulated test time, and to restart the RFD

from the beginning,

(4) In all other failures (Minor or Major failures) the time test measurement will be

resumed after the repair.

(5) Parts replacement due to and during preventive maintenance action will not be

considered as a failure.

7.5 Failure Review Board

The FRF will be presented to a Failure Review Board (FRB) for reviewing, discussing and

deciding. The FRB will be headed by an I.E.Co engineer, and composed of I.E.Co and

Contractor members. Only the FRB is entitled to decide any decision about a failure

(classification, repair, corrective action, etc.) after failure analysis and investigation. The

conclusions of the FRB discussion will be registered in a Reliability Demonstration

Logbook (RDL).

7.6 Penalties

(1) After and only after expiration of the Warranty Period even in the course of the UPD,

I.E.Co. will assume full responsibility for all repair/replace costs. Anyway, during

Warranty Period the Contractor will assume full responsibility for all repair/replace

costs.

(2) If the UDP is terminated in “Accept” decision, responsibility remains as stated in the

previous paragraph (para. 1).

Page 92: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/11

(3) If the UDP is terminated in “Reject” decision due to Major Failures, The Contractor will

retroactively assume responsibility for all repair/replace cost and will extend his

Warranty for Major Failures only to additional period of ten (10) years.

(4) If the UDP is terminated in “Reject” decision due to Minor Failures, The Contractor will

retroactively assume responsibility for all repair/replace cost and will extend his

Warranty for Minor Failures only to additional period of ten (10) years.

8. Terms and Definitions

(1) Failure

A failure is any event where a MOBILE SUBSTATION stops functioning, or functions

outside of its specification limits, and requires a repair/replacement. The failures can

be divided into two groups, Relevant and Non-relevant failures.

(2) Non Relevant Failure

A Non Relevant Failure is a failure that was caused by one of the following events:

Incorrect installation, or not in accordance with Contractor’s instruction.

Misuse, or not in accordance with Contractor’s instruction.

Caused by test equipment.

External cause, “Force Major” etc. (i.e. lightning).

Secondary Failure.

(3) Relevant Failure

A Relevant Failure is a failure that could happen in real life, and was not defined as

“Non Relevant”. Also, a Relevant Failure is a failure that causes a MOBILE

SUBSTATION malfunction or undesirable operation (Including repair/replace, and

logistic times).

(4) Systematic Failure

A Systematic Failure is a Relevant Failure that happens two times or more, and

therefore it required a Corrective Action. A systematic failure can be eliminated only by

a modification of the design, manufacturing process, or operational procedures. A

systematic failure can be induced at will by simulating the failure cause, and it is called

also Reproducible Failure (Systematic Failures group is sub group contained in

Relevant Failures group).

(5) Random Failure

A Random Failure is a failure that its root cause is of a “random nature”, and cannot be

defined as “Systematic Failure”.

Page 93: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/12

(6)Major Failure

A “Major Failure” is a failure that causes a forced MOBILE SUBSTATION stop

functioning.

(7)Minor Failure

A “Minor Failure” is a failure that causes a MOBILE SUBSTATION functions outside of

its specification and may generate undesirable action (Including repair/replace, and

logistic times).

(8) Secondary Failure

A “Secondary Failure” is a failure that was caused by another failure.

(9) Test Time

“Test Time” is the cumulative summation of operating time of all MOBILE

SUBSTATION participating in this demonstration.

(10)Failure Review Board

A Failure Review Board (FRB) is the body entitled to decide about failure matters. The

main task of the FRB is to analyze the failures, and especially to decide as to failure

classification, and Corrective Actions. The FRB made up from Contractor and I.E.Co.

representatives.

(11)Failure Rate

The failure rate, of a MOBILE SUBSTATION is the number of failures per operating

time unit.

(12)MTBF

MTBF is the mean operating time between failures of a MOBILE SUBSTATION. MTBF

= 1/.

Reliability

Reliability is a design characteristic defining the ability of a MOBILE SUBSTATION to

perform satisfactorily. Therefore, the MOBILE SUBSTATION reliability is the probability

that the MOBILE SUBSTATION will perform without failures, for a pre-defined period of

time, when used under stated conditions (in I.E.Co.’s customer site). MTBF is a

reliability parameter.

(13)Life Length

The life length of a MOBILE SUBSTATION is the time until the accumulated repair cost

sum up to the half of the price of a new one.

(14) Maintenance

Page 94: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B2 SPECIFICATION SR-152

App B2/13

Maintenance is any action taken by technical staff to:

Restore a faulty item to its operable condition after a failure, or:

Preserve the operable, or safety condition of a good item, or:

Test the operable condition of an item.

(15)Preventive Maintenance

Preventive Maintenance (PM) is the maintenance actions carried out on a good unit, at

predetermined intervals, or in accordance with prescribed criteria, and intended to

reduce the MOBILE SUBSTATION probability of a future failure, or degradation of the

functioning of the item.

(16)MTTR

MTTR is the mean time required to perform a repair (including checks) or replace of a

MOBILE SUBSTATION.

(17)Maintainability

Maintainability is a design characteristic defining the ability of a MOBILE SUBSTATION

to be restored quickly to its operable condition after a failure. Therefore, a MOBILE

SUBSTATION maintainability is the probability that a failed MOBILE SUBSTATION is

restored to its functioning condition, within specified period of time, under stated

condition, using stated procedures (defined by the Contractor), and resources (defined

by the I.E.Co.). MTTR is a maintainability parameter.

(18)I.E.Co.

Israel Electric Corporation.

(19)IEC

International Electrotechnical Commission.

Page 95: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Israel Electric Corp. Ltd. חברת החשמל לישראל בע"מ Power and Energy Group חטיבת הייצור והאנרגיה

Generation Division אגף הייצור Chief Chemist Department י הכימאי מחלקת הראש

50מפרט מס:

24/01/2016בתוקף מתאריך: מפרט טכני לכימיקלים וחומרים

הנושא : INSULATING OIL 7מתוך 1דף מס'

שם המפרט:

MINERAL INSULATING OIL

SUPPLIED FOR/WITHIN ELECTRICAL

EQUIPMENT

שם תאריך חתימה

24/01/2016 מדאר תמירון גריסרו מריוס

הוכן ע"י

04/02/2016 ד"ר ויקטור מרקו

אושר ע"י

Page 96: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

1. Scope

This specification covers new (unused) mineral insulating inhibited oil of petroleum origin, as

delivered, for use in Israel Electric Corporation as an insulating and cooling medium in new

and existing power and distribution electrical apparatus, such as transformers, regulators, circuit

breakers, switchgear and similar equipment. It also applies to oil delivered to Israel Electric

Corporation in new electric equipment and along with new electric equipment.

2. Reference Documents

IEC 60296:2012, Unused mineral insulating oils for transformers and switchgear

IEC 60156, Insulating liquids-Determination of the breakdown voltage at power frequency-Test method

IEC 60247, Measurement of relative permittivity, dielectric dissipation factor and d.c. resistivity of

insulating fluids

IEC 60422, Supervision and maintenance guide for mineral insulating oils in electrical equipment

IEC 60475, Method of sampling liquid dielectrics

IEC 60628, Gassing of insulating liquids under electrical stress and ionization

IEC 60666, Detection and determination of specified anti-oxidant additives in insulating oils

IEC 60814, Insulating liquids – Oil-impregnated paper and pressboard – Determination of water by

automatic coulometric Karl Fischer titration

IEC 61125, Unused hydrocarbon based insulating liquids – Test methods for evaluating the oxidation

stability

IEC 61198, Mineral insulating oils – Methods for the determination of 2-furfural and related

compounds

IEC 61619, Insulating liquids – Contamination by polychlorinated biphenyls (PCBs) – Method of

determination by capillary column gas chromatography

IEC 61620, Insulating liquids-Determination of the dielectric dissipation factor by measurement of the

conductance and capacitance – Test method

IEC 61868, Mineral insulating oils – Determination of kinematic viscosity at very low temperatures

IEC 62021-1, Insulating liquids-Determination of acidity – Part 1: Automatic potentiometric titration

ISO 2719, Determination of flash point – Pensky-Martens closed cup method

ISO 3016, Petroleum products – Determination of pour point

ISO 3104, Petroleum products – Transparent and opaque liquids – Determination of kinematic viscosity

and calculation of dynamic viscosity

ISO 3675, Crude petroleum and liquid petroleum products – Laboratory determination of density –

Hydrometer method

ISO 6295, Petroleum products – Mineral oils – Determination of interfacial tension of oil against water

– Ring method

ISO 12185, Crude petroleum and petroleum products – Determination of density – Oscillating U-tube

method

ISO 14596, Petroleum products – Determination of sulfur content – Wavelength-dispersive X-ray

fluorescence spectrometry

DIN 51353, Detection of corrosive sulfur – Silver strip

BS 2000, Part 346, Determination of polycyclic aromatics in lubricant base oil and asphaltene free

petroleum fractions – Dimethylsulfoxide refractive method

ISO/IEC 17025:2005, General requirements for the competence of testing and calibration laboratories

Page 97: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

3. Property Requirements for Insulating Oil (information shall be provided by the oil supplier) 3.1 M i n e r a l insulating oil as delivered by the supplier shall meet all the requirements of

IEC60296:2012 Unused mineral insulating oils for transformers and switchgear for inhibited oils.

3.2 Use of re-refined oil is allowed if it complies with all the properties listed in that standard.

TABLE A

Name of oil manufacturer:

Type of oil:

Property Test method Limits Supplier data

Unused Inhibited Mineral Insulating Oil Property Requirements

Test

No. Function

1 Viscosity at 40 °C ISO 3104 Max. 12 mm²/s

2 Viscosity at -30 °C ISO 3104 Max. 1 800 mm²/s

3 Pour point ISO 3016 Max. -40 °C

4 Water content IEC 60814 Max. 30 mg/kg

a/40 mg/kg

b

5 Breakdown voltage IEC 60156 Min. 30 kV/70 kV

c

6 Density at 20 °C ISO 3675 or ISO

12185 Max. 0.895 g/ml

7 DDF at 90 °C IEC 60247 or IEC

61620 Max. 0.005

8 Particles (counting, sizing) IEC 60970 See

d

Refining/stability

9 Appearance - Clear, free from sediment and

suspended matter

10 Acidity IEC 62021-1 Max. 0.01 mg KOH/g

11 Interfacial tension EN 14210 or

ASTM D971 Min. 40 mN/m

12 Total sulphur content IP 373 or ISO

14596 See

d

13 Corrosive sulfur DIN 51353 Not corrosive

14 Potentially corrosive sulphur IEC 62535 Not corrosive

15 DBDS IEC 62697-1 Non-detectable (<5 mg/kg)

16 Anti-oxidant Inhibitors IEC 60666 0.08-0.40%

17 Metal passivator additives IEC 60666 Non-detectable (<0.05 mg/kg)

18 Other additives - See

e

19 2-Furfural content IEC 61198 Non-detectable (<0.05 mg/kg)

20 Stray gassing 6.22 of IEC 60296 See

d

21 FTIR – fingerprint or other

method agreed between

IECo and supplier.

- See

d(please add relevant documents)

Performance

22 Oxidation stability IEC 61125:1992

(method C) Test

duration: 500 h

23 Total acidity f

1.9.4 of IEC

61125:1992 Max. 1.2 mg KOH/g

24 Sludge f

1.9.1 of IEC

61125:1992 Max. 0.8%

25 DDF at 90 °C f

1.9.6 of IEC

61125:1992 Max. 0.500

26 Gassing tendency IEC 60628:1985,

Method A See

d

Page 98: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

a For bulk supply.

b For delivery in drums. c After laboratory treatment. d Results must be provided. e The supplier shall declare the generic type of all additives, and their concentrations in the case of antioxidant additives. f To be performed at the end of oxidation stability test. g The values should be without temperature correction. h A different value could be agreed between supplier and user depending upon local circumstances. i Shall be similar to the value before first filling (Unused Inhibited Mineral Insulating Oil Property Requirements). j By vacuum extraction.

Test

No.

Property Test method Limits Supplier data

Health, safety and

environment

27 Flash point ISO 2719 Min. 135 °C

28 PCA content IP 346 Max. 3%

29 PCB content (mg/kg) IEC 61619 Not detectable (< 2 total)

Requirements for Mineral Insulating Oils after Filling in New Electrical Equipment

Property Highest voltage for equipment kV

<72.5 72.5 to 170 >170

30 Appearance Clear, free from sediment and suspended matter

31 Colour (on scale given in

ISO 2049)

Max. 2.0 Max. 2.0 Max. 2.0

32 Breakdown voltage (kV) >55 >60 >60

33 Water content (mg/kg) g 20 h <10 <10

34 Acidity (mg KOH/g) Max. 0.03 Max. 0.03 Max. 0.03

35 Dielectric dissipation

factor at 90°C and 40 Hz

to 60 Hz

Max.0.015 Max.0.015 Max.0.015

36 Resistivity at 90°C

(GΩm)

Min.60 Min.60 Min.60

37 Oxidation stability i As specified in IEC 60296

38 Interfacial tension

(mN/m)

Min.35 Min.35 Min.35

39 Total PCB content

(mg/kg) i

Not detectable (< 2 total)

40 Particles (counting,

sizing)

- Should be made as a baseline for future comparison

41 Inhibitor content i -

42 Total gas content –

according IEC 61181 j

- <1% <0.5%

43 DGA according to IEC

61181 j

-

44 FTIR - fingerprint i -

Page 99: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

3.3 Tests required at various stages in complete process for power transformers commissioning (>72.5KV):

TABLE B

Stage description TEST No. Test certificate by

1 i Bidder acceptance 1-29 Pre-approved laboratories (see

clause 7.2)

2 C.O.T. from oil supplier after order

confirmationa.

3-5,8,9,11,14-17,21,29 Pre-approved laboratories (see

clause 7.2)

3 Incoming inspection. 4,11,21 Accredited/approved Lab h

4 Afterf first filling, before electrical

testing at manufacturer site.

30-36,38-41,43,44 Accredited/approved Lab h

5 Afterf electrical testing at

manufacturer site.

43,19 Accredited/approved Lab h

6 Testing of oil before transformer delivery to purchaser, according to one of the following scenarios:

6.1 Filled with dry gasb and Partially

assembled.

1-19,21,22d Pre-approved laboratories (see

clause 7.2)

6.2 Afterf transformer was filled with oil

and fully assembledc.

17,30-44 (for test No. 37

seed)

Pre-approved laboratories (see

clause 7.2)

6.3 Afterf transformer was partially filled with oil and Partially assembledc:

6.3.1 Tests for main Transformer. 17,30-41 (for test No. 37

seed), 44

Pre-approved laboratories (see

clause 7.2)

6.3.2 Tests for separated oil. 44 (same as 6.3.1 oil) Pre-approved laboratories (see

clause 7.2)

7 i Testing of oil according to the destination of the transformer according to one of the following

scenariose:

7.1 Storage:

7.1.1 With option 6.1 afterf D.P. test, full

assembly and full with oil according

to manufacturer instructions.

32-35,38,40,43,44 Accredited/approved Lab h

7.1.2 With option 6.2 4,5,8,11,43 – After one

year

Accredited/approved Lab h

7.1.3 With option 6.3 and after f full

assembly and full with oil according

to manufacturer instructions

32,33,35,38,41-44 Accredited/approved Lab h

7.2 Purchaser station:

7.2.1 g Before energizing and after f full

assembly and full with oil according

to manufacturer instructions.

30-36,38,40,41,43,44 Pre-approved laboratories (see

clause 7.2)

7.2.2 Storage:

7.2.2.1 With option 6.1 afterf D.P. test, full

assembly and full with oil according

to manufacturer instructions.

32-35,38,40,43,44 Accredited/approved Lab h

7.2.2.2 With option 6.2 4,5,8,11,43 – After one

year

Accredited/approved Lab h

7.2.2.3 With option 6.3 and after f fully

assembled according to

manufacturer instructions

32,33,35,38,41-44 – Accredited/approved Lab h

a For 20 ton batch for each order or as agreed between supplier and purchaser. b Dew point < -60˚C c The oil will not be treated and/or circulated before energizing at purchaser site d The result should not postpone delivery. e According to commercial annexures (if it's include in manufacturer warranty/responsibility). f Sample shall be taken between 24 – 48 hours. g Each transformer have to perform 7.2.1 tests before energizing at purchaser station. h Labs that shall be agreed between purchaser and supplier. i The oil tests reports provided for current stage shall include also the reports of the oil tests performed between the

previous stage and the current stage.

Page 100: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Note: The oil will be tested in storage up to 5 years according to paragraph 6.2 and limits therein. The

transformer oil will be tested also during operation within the warranty period once every 3 months

according to routine tests specified by IEC60422. Any excess of trends and limits will be a clause to contact

the transformer supplier and find out the cause for it.

3.4 Test at stages in complete process for distribution and small transformers (<72.5KV), one certificate is

enough for a group of 20 supplied transformers.

TABLE C

Stage description TEST No. Test certificate by

1d Bidder acceptance 1-29 Pre-approved laboratories

(see clause 7.2)

2 C.O.T. from oil

supplier after order

confirmationa.

3-5,8,9,11,14-17,21,29 Pre-approved laboratories

(see clause 7.2)

3 Incoming inspection. 4,11,21 Accredited/approved Lab c

4d Afterb electrical

testing at

manufacturer site.

30-36,38-41,43,44 Pre-approved laboratories

(see clause 7.2)

a For 20 ton for each order or as agreed between supplier and purchaser. b Sample shall be taken between 24 – 48 hours. c Labs that shall be agreed between purchaser and supplier. d The oil tests reports provided for current stage shall include also the reports of the oil tests performed between the

previous stage and the current stage.

4. Specific requirements for special applications

For transformers with higher operating temperatures or designed for extended service life, Israel

Electric Corporation may require the oil (catalog Nº 5236327) to comply with restricted limits after

oxidation test according to IEC 61125:1992 (Method C). Specific requirements oils are in generally

more robust to aging and can prolong the transformer life.

- Total acidity: max. 0.3 mg KOH/g;

- Sludge: max. 0.05 %;

- DDF at 90 °C: max. 0.050;

- Total sulphur content: max. 0.05% (before oxidation test).

5. Identification and general delivery requirements for separate oil

5.1 Oil shall be delivered in bulk, tank containers or packed in steel drums. These shall

be clean and suitable for this purpose to avoid any contamination. Israel Electric

Corporation catalog numbers (for the oils that comply with General Specification):

847103 (drums), 3177771 (bulk).

5.2 Oil drums shall be new and free of any internal coating.

5.3 Oil drums and sample containers shall carry at least the following markings:

• manufacturer's designation;

• classification;

• oil quantity.

5.4 Marking shall be accomplished by labeling or stenciling.

5.5 Paint type and/or sticker shall be water and oil proof.

Page 101: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

5.6 Each oil delivery shall be accompanied by a document from the supplier specifying at

least: manufacturer's designation, oil classification and compliance certificate.

5.7 Israel Electric Corporation is free to send at any time an oil sample to any of the pre-

approved laboratories of 7.2, to check if the oil values of a specific delivery meet the initial specification. If any contradiction is found between the actual measurements and the certificate values, the oil can be returned to the supplier after further clarification.

6. Sampling

Sampling for any purpose, shall be carried out only in accordance with the procedure described in

IEC 60475.

7. Testing and certification

7.1 Potential suppliers shall include in their proposals:

• The table in sub-clause 3.2 including the type and concentration of any additive in

the oil;

• The original manufacturer's technical specification of the oil;

• The list of the laboratories measuring each parameter in the table in sub-clause

3.2. must be acceptable to Israel Electric Corporation;

• Certification of the quality assurance system of the oil manufacturer's production

line. The certifying organization must be known and accepted by Israel Electric

Corporation;

• Safety Data Sheet (SDS) of the oil.

7.2 Pre-approved laboratories for transformer oil testing shall include the following independent

laboratories:

• Doble Engineering Company - www.doble.com

• LABELEC, Electricidade de Portugal (EDP) – www.edp.pt

• EIMV - Electroinstitute Milan Vidmar (EIMV) - www.eimv.si

• SEA MARCONI TECHNOLOGIES S.a.s.-www.seamarconi.com

• LABORELEC - www.laborelec.com

• Siemens AG - www.energy.siemens.com/hq/en/services/power-transmission-

distribution/transformer-test-laboratory/

7.3 Approved products-see Appendix A.

Page 102: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix A- Approved Insulating Oil Sources and Types

This document lists the insulating oil sources and types approved for Israel

Electric use, as of 24.01.2016.

Oils that comply with equipment under 72.5KV

1. Apar Industries Ltd. - POWEROIL TO 1020 - 60 UX

2. Savita Oil Technologies Ltd. – TRANSOL GEX

3. Nynas Naphthenics AB - Nytro Lyra X

4. Shell Deutschland Oil GmbH – Shell Diala S3 ZX-I

5. Shell Deutschland Oil GmbH – Shell Diala S4 ZX-I

6. Petro-Canada Europe Lubricants Ltd. – Luminol Tri

7. Nynas Naphthenics AB – Nytro Gemini X

8. Ergon Refining, Inc. – Hyvolt III

Oils that comply with equipment over 72.5KV

1. Nynas Naphthenics AB - Nytro Lyra X

2. Shell Deutschland Oil GmbH – Shell Diala S3 ZX-I

3. Shell Deutschland Oil GmbH – Shell Diala S4 ZX-I

4. Petro-Canada Europe Lubricants Ltd. – Luminol TRi

5. Nynas Naphthenics AB – Nytro Gemini X

6. Ergon Refining, Inc. – Hyvolt III

7. Savita Oil Technologies Ltd. – TRANSOL GEX

In one transformer will be only one approved oil manufacturer. No mixing

of oils is allowed in one transformer even from approved oil supplier

Page 103: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

:מפרטשם הSELF INDICATING ORANGE SILICA GEL

FOR USE AS DESICCANT IN TRANSFORMER

AIR DEHYDRATORS

חברת החשמל לישראל בע"מ חטיבת ייצור והולכה

אגף הייצור מחלקת הכימאי הראשי

Israel Electric Corp. Ltd.

Generation & Transmission Group

Generation Division

Chief Chemist Dpt.

מפרט טכני לכימיקלים וחומרים דומים

804 : מפרטמס'

25.05.2012 :בתוקף מתאריך

DESICCANTS הנושא: 3מתוך 1 דף מס'

חתימה תאריך שם 25.05.2012 איליה פרומין הוכן ע"י

נבדק ע"י

25.05.2012 דר' ו' מרקו אושר ע"י

Page 104: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

SELF-INDICATING ORANGE SILICA GEL HEAVY METAL FREE

FOR USE AS DESICCANT IN TRANSFORMER AIR DEHYDRATORS -מחלקת הכימאי הראשי

3מתוך 2עמוד 25.05.2012.בתוקף מתאריך:

1. Scope

This specification covers self-indicating Orange Silica Gel with non-hazardous

humidity indicator, for use in Israel Electric as dehydrating agent for transformer

air drying equipment (Israel Electric catalogue No 5001635).

The silica gel shall contain an indicator changing a color from orange into green or

white (colorless) during the process of moisture adsorption.

The products shall not contain any material that has been regenerated.

2. Technical requirements

2.1 The material shall consist of silica gel in beaded form and free from

extraneous matter. The bead size of 90% of it should be 2-6 mm.

2.2 The product shall conform to the technical requirements given in Table 1.

2.3 Suppliers shall submit with their proposals:

a technical specification of the product, containing at least, the data

required in the Israel Electric spec N° 804;

Safety Data Sheet (SDS).

2.4 The regeneration conditions of silica gel shall be specified by the supplier in

Table 2.

3 . Packaging

3.1 The desiccant shall be filled into strong, sound clean, dry and transparent

packages (to determine the color of the product). Each package shall contain 1.2 kg

of desiccant, and it shall be hermeticaly sealed after filling. The packages shall be air

tight and capable of being easily opened (e.g. transparent plastic bags, which cannot

be torn).

3.2 The bagged desiccant shall be packaged in leakproof and air tight containers.

The containers shall be approximately full and shall hold an agreed quantity of bags

per container.

3.3 Each package and each container (both internal and external) shall be legibly

and durably marked with at least the following details:

- The material designation

- Manufactures name

- Distinctive lot or batch number

- Quantity of contents

- Date of manufacture

Page 105: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

SELF-INDICATING ORANGE SILICA GEL HEAVY METAL FREE

FOR USE AS DESICCANT IN TRANSFORMER AIR DEHYDRATORS -מחלקת הכימאי הראשי

3מתוך 3עמוד 25.05.2012.בתוקף מתאריך:

Table 1. Property Requirements for Silica Gel

Properties Limits Supplier's Data

1. Chemical composition:

-SiO2

-humidity indicator

93 wt.% min

5% max

2. Apparent density, kg/l, min 0.7

3. New material moisture (100°C, 4h),

% by weight, max 2.0

4. Bead size:

-larger than 6 mm, wt%, max

-smaller than 2mm, wt%, max

5.0

5.0

5. Water vapor adsorption capacity, %, min

at relative humidity (RH) of air:

20%

40%

80%

10.0

20.0

33.0

6. Colour change indication range (start to

end), adsorption at 20%RH ± 7.5%RH,

@ 20°C, weight%

6-14

Table 2. Regeneration conditions (shall be filled by supplier)

Parameter Insert all data

in this column

1. Maximum temperature at which the

material properties are preserved, C

2. Recommended temperature or temperature

range for material regeneration, C

3. Recommended time for drying 1 kg of

white/colourless material in a layer 2.5 cm

high, by forced air at the recommended

temperature, to reach 2% moisture, minutes

Page 106: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B5 SPECIFICATION SR-152

App B5/1

TESTS ON SITE

1. Verification of shock detectors,

2. Verification of general mounting.

3. Verification of oil tightness at a pressure of 0.2 bar,

4. Verification of voltage ratio and checking of voltage vector relationship,

5. Measurement of winding resistance,

6. Verification of no-load losses and exciting current,

7. Verification of transformer insulation resistance,

8. Verification of capacitance and dielectric dissipation factor,

9. Verification of oil dielectric breakdown voltage,

10. Verification of auxiliary circuits insulation resistance,

11. Testing of automatic and manual operations of OLTC and Voltage Regulator,

12. Verification of correct wiring,

13. Testing of auxiliary circuits: automatic and manual operation, alarm and tripping,

14. Adjustment of thermic and time relays,

15. Verification of thermostats (adjustment and operation),

16. Verification of protections,

17. Verification of bushing current transformers,

18. Verification of valves and flaps position,

19. Verification of oil levels and silicagel air dryers,

20. Sweep Frequency Response Analysis (SFRA) test.

Page 107: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B6 SPECIFICATION SR-152

File: APPENDIX B6-COATING FOR ALUMINUM CABINET.docx

Page 1 of 5

.Israel Electric Corp. Ltd חברת החשמל לישראל בע"מ

Generation & Transmission Group חטיבת ייצור והולכה

Dpt. Chemist Chief - Generation Division מחלקת הכימאי הראשי -אגף הייצור [email protected] 04-8183362 - למלם דודא וציפויים עבצ

[email protected] 8183158-04 - ליטני שי 8185706-04פקס: 10.2.2016

217-000260-2015

Specification for coating galvanized tin or aluminum cabinets

by Liquid or powder coating

General

The specification deals with painting cabinets for control or electricity made of

galvanized or aluminum.

The coating application will be "wet" or powder coating (electrostatic).

Painting over galvanized surface requires an early experiment to ensure adherence to

substrate.

All the coating materials shall be of a single manufacturer.

Each layer shall be in different shade.

The coating application shall be engineering quality as outlined in SSPC standard PA-1,

and in accordance with the manufacturer's instructions on the product pages. The finished

product shall have a uniform appearance and lacks liquidity, wrinkles or other defects,

has a uniform thickness in proportion to demand. The coating layers will firmly glue to

the substrate. The final color determined by the customer.

Shay Litani Elmalem David Dr. Marcu Victor

Page 108: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B6 SPECIFICATION SR-152

File: APPENDIX B6-COATING FOR ALUMINUM CABINET.docx

Page 2 of 5

contents

1. Surface preparation for painting on Zinc ......................................................................... 3

1.1. On Hot Deep Galvanized surface ........................................................................ 3

1.2. On electrolytic Galvanized surface ..................................................................... 3

1.3. Galvanize Local repair ........................................................................................ 3

2. Coating application .......................................................................................................... 4

2.1. Galvanized or aluminum cabinets coating – 2 layers............................................... 4

2.2. Strip Coating ............................................................................................................ 4

3. Approved Coating Products ............................................................................................. 5

3.1. Approved Liquid Coating ........................................................................................ 5

3.2. Approved Powder Coating ....................................................................................... 5

4. Quality assurance ............................................................................................................. 5

Page 109: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B6 SPECIFICATION SR-152

File: APPENDIX B6-COATING FOR ALUMINUM CABINET.docx

Page 3 of 5

1. Surface preparation for painting on Zinc

1.1. On Hot Deep Galvanized surface

1.1.1 Solvent Cleaning

The surface shall be cleaned without any dirt, oil, grease or any foreign matter according

to standard "SOLVENT CLEANING SSPC SP-1".

1.1.2 Surface preparation according to one of the following methods:

A. Brush-Off Blast Cleaning according to SSPC SP-7

Depreciation more than 10 microns of thickness of the galvanization is not allowed.

B. Chemical treatment

Phosphate washing (BS-3189).

1.2. On electrolytic Galvanized surface

1.2.1 Solvent cleaning according to 1 .1.1.

1.2.2 Surface treatment in one of the following methods:

A. Roughening the surface with mechanical tool according to the requirements in the

spec and according to the TDS, with minimal damage to the zinc.

B. Chemical treatment – according 1.1.2 B

1.3. Galvanize Local repair

Local galvanize damage shall be repair to 60 micron minimum (possible with 2

layers) with one of the following approved products (Israel):

Product distributor

Z.R.C "Carmel Handasa" ZINGA "m.b.l"

ZINC-GLAD 5 "Nirlat " GALVITE 90 E "Tambour"

Page 110: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B6 SPECIFICATION SR-152

File: APPENDIX B6-COATING FOR ALUMINUM CABINET.docx

Page 4 of 5

2. Coating application

All materials shall be made by the same manufacturer.

Each layer shall be in different color (shade).

Approved Products for liquid coating – see table 3.1

Approved Products for powder coating – see table 3.2

2.1. Galvanized or aluminum cabinets coating – 2 layers

Offered

By MFR

Remarks DFT

[µ] Coating System # Hot Deep or

Electrolytic #

- - -

70

50

Liquid coating:

Primer: polyamide epoxy

Top: Polyurethane 2.1.1.1

Hot Deep

70 µ 2.1.1

120 Total:

- - -

70

50

Powder coating:

Primer: phenolic epoxy

Top: pure polyester 2.1.1.2

120 Total:

- - -

100

50

Liquid coating:

Primer: polyamide epoxy

Top: Polyurethane 2.1.2.1

Electrolytic

20-40 µ 2.1.2

150 Total:

- - -

70

50

Powder coating:

Primer: phenolic epoxy

Top: pure polyester 2.1.2.2

120 Total:

Surface

preparation

according to

coating

manufacturer.

Roughness

required!

50

50

Liquid coating:

Primer: polyamide epoxy

Top: Polyurethane 2.1.3.1 Aluminum 2.1.3

100 Total:

Surface

preparation

according to

coating

manufacturer.

80 Powder coating:

Top: pure polyester 2.1.3.2

80 Total:

2.2. Strip Coating

Before or after spraying each coat of a paint system, all areas as corners, edges, welds,

small brackets, bolts, nuts, difficult-to-reach-areas… shall be stripe-painted by brush to

ensure that these areas have at least the minimum specified film thickness.

Page 111: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B6 SPECIFICATION SR-152

File: APPENDIX B6-COATING FOR ALUMINUM CABINET.docx

Page 5 of 5

3. Approved Coating Products

3.1. Approved Liquid Coating

Top Primer Manufacturer Supplyer

(Israel)

Tamaglass PU

(Aliphatic)

Epitamarin Uniseal brown

code 842-xx

or

Epogal code 644-xx

Tambour Tambour

Interthane 990 Interguard 269 International

Unicryl Epoxy HB 55 Nirlat

Amercoat 450 S Amercoat TC 71 Ameron

Acrolom 218 Duraplate 235 Sherwin williams Nirlat

Sigmadur 520

Sigmacover 522

Or

Sigmacover 280

Sigma

Carboline 134 Rust Bond Penetrating

Primer Carboline

55210/55610 15570/15300 Hempel

3.2. Approved Powder Coating

Code Product Manufacturer

182-xxx Or 192-xxx

186-xxx Epoxy Powder

Pure Polyester powder Tambour

Series 9000

Series 7000 Epoxy Powder

Pure Polyester powder Nirlat / Univercol

4. Quality assurance

The contractor is responsible to perform a quality control plan, document and to report

the results of the product testing.

Minimum Report:

Surface preparation before application (hold point) – roughness and cleanliness.

DFT – Dry Film Thickness of each layer (ISO 19840).

Adhesion test according to ISO 16276 (X-Cut test ( . Minimum level "1" required.

The Israel Electric Company may perform the continuity test standard NACE 188 (Wet

Sponge) Discontinuities shell be corrected by the contractor and his responsibility.

There may be additional checks according to the supervisor decision.

Page 112: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B7 SPECIFICATION SR-152

File: APPENDIX B7-COATING FOR POWER TRANSFORMER.docx Page 1 of 4

.Israel Electric Corp. Ltd חברת החשמל לישראל בע"מ

Generation & Transmission Group חטיבת ייצור והולכה

Dpt. Chemist Chief - Generation Division מחלקת הכימאי הראשי -הייצור גף א

Paints and coatings 04-8183362 - למלם דודא [email protected]

Fax :8185706-04 8183158-04 - ליטני שי [email protected]

2009-217-141707

24.11.2015 20.9.2015

Specification for Coating Requirements of Power Transformers

and/or Arc Suppression Coil

The coating system shall supply protection against atmospheric corrosion for periods at least 15 year

without need for maintenance, for the transformer and its attached elements.

Remark: in that coating spec "transformer" means "Transformer and/or Arc Suppression Coil".

Transformers shall be positioned in various environmental conditions. Some may be positioned in

deserts and exposed to strong and direct sun radiation; other may be positioned in a polluted-marine

environment classified as C5-M by ISO 12944-5. All coating systems shall be complying with

ISO 12944-5 C5-M as minimum requirements.

Paints shall be applied in shop in the frame of SSPC – PA1. Field painting is not permitted.

Internal surfaces shall be paint/coating protected as a routine procedure of the manufacturer, and can be

proved to be successful by documents.

The oil, coating layers, insulating materials, and all other components of the transformer must not

chemically react and must not interfere with each other, in order to keep the properties of each one,

under the operating temperature conditions.

In case of lack of experience in antiskid painting on the cover – the manufacturer may suggest an

antiskid solution that was composed by the paint manufacturer.

Cover coating shall be thicker and include tested antiskid solutions (Similar to MIL PRF24667B).

Only coating systems for which the manufacturer has previous successful experience shall be suggested.

All coating layers shall be by the same single paint manufacture.

The outer top-layer shade shall be RAL 7038. Internal shade (where applicable) shall be fair.

The transformer manufacturer is responsible for the paint and coating application quality.

The final product shall be good looking, homogeneous, free from leaks and shall have a good adhesion

to the transformer matrix.

Standards use in this specification: ISO 12944-5 Paints and varnishes -- Corrosion protection of steel structures by

protective paint systems -- Part 5: Protective paint systems

SSPC – PA1 Shop, Field, and Maintenance Painting of Steel

MIL PRF24667B PERFORMANCE SPECIFICATION: COATING SYSTEM, NON-

SKID, FOR ROLL, SPRAY, OR SELF-ADHERING APPLICATIONS

SSPC PA-2 or ISO 19840 Procedure for Determining Conformance to Dry Coating Thickness

Requirements

ISO 16276 "Paints and varnishes – Cross cut test"

Page 113: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B7 SPECIFICATION SR-152

File: APPENDIX B7-COATING FOR POWER TRANSFORMER.docx Page 2 of 4

The coating technical information shall be coordinated with the paints manufacturer and shall include at

least:

Coating procedure description

Surface preparation procedures

Description of application procedures

Required surface roughness

Special treatment of problematic areas (cover, thin edges, radiators, strip coats etc.)

Materials

Manufacturer name and address.

Generic classification of coating system.

The full commercial paints name, technical datasheets of the paints and materials.

Quality control

Quality reports and environmental conditions during application shall be given to the tank,

radiators and other elements separately.

List of Parameters to be measured and measuring standards (thickness, adhesion and their

scattering are mandatory).

Tests required:

Dry Film Thickness (DFT) shall be measured according to SSPC PA-2 or ISO 19840 (the

supplier has to declare which standard he uses as a routine).

Adhesion test shall be according to ISO 16276 "Paints and varnishes – Cross cut test"

(or ASTM D-3359), Level 1 required.

Previous experience:

Names and addresses of two (2) customers. Dates of application, project description.

Maintenance repairing instructions: for damages during shipment or erection or operation of all

painting systems.

Page 114: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B7 SPECIFICATION SR-152

File: APPENDIX B7-COATING FOR POWER TRANSFORMER.docx Page 3 of 4

Principal Options for Protective Coating

The supplier shall suggest a coating system for the approval of Israel Electric Corp. Ltd.

Such approval will include checking the suggested coating system to its purpose as well as

compliance with all requirements of the current document.

The supplier shall declare which option he uses for protection (see options A-D):

Option A

A Duplex system- Hot deep galvanized and painted (Information to be delivered by the

manufacturer):

Galvanizing transformers is routine at the manufacturer's (indicate two customers)

Galvanizing shall be according to "ASTM-A 153/2003 Std spec. for Zinc coating (Hot-Dip)

on iron and steel" or by an international or regional accepted standard.

The metal shall be suitable for galvanizing

Surface preparation according to galvanizer's procedures

Zinc thickness: 75 microns (minimum)

Surface preparation for painting (without passivation).

Paint system with 2 layers of 120 micron minimum thicknesses, except cover having 220

microns (minimum) and antiskid requirements.

Option B

Painted fused sprayed Zinc (equal to IEC's Spec. CL-100):

(Information to be delivered by the manufacturer)

Submission of method and workers audition certificates

Two customers' addresses with 5 years experience

Surface preparation for Zinc spraying

Zinc thickness of 100 microns (minimum) + coating: primer 70 micron and topcoat 50

microns, except cover having 220 microns of paint (minimum) and an antiskid requirement.

Option C

A 3 layer system Zinc-rich/ Epoxy/ Polyurethane

Zinc-rich base is the routine for the manufacturer (indicate two customers)

Zinc-rich shall be stated according to ASTM-D 520

Description of Surface preparation.

Total Thickness of 250 micron (minimum, with base layer thickness of 70 microns) , except

cover having 350 microns(minimum) and an antiskid requirements.

Page 115: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B7 SPECIFICATION SR-152

File: APPENDIX B7-COATING FOR POWER TRANSFORMER.docx Page 4 of 4

Option D

A 3 layer system Epoxy/ Epoxy/ Polyurethane

Epoxy/Epoxy/Polyurethane is the routine for the manufacturer (indicate two customers)

Description of Surface preparation.

Total Thickness of 350 micron (minimum, with base layer thickness of 70 microns), except

cover having 450 microns (minimum) and an antiskid requirements.

Internal

Transformer manufacturer declaration that internal coating is a routine process

(indicate two satisfied customers).

Paint manufacturer declaration for compliance with mineral transformer oil.

Shay Litani Dr. Ehud Sutskover

Page 116: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B8 SPECIFICATION SR-152

App B8/1

Report of

Sound Pressure/Intensity Level Measurement

and Sound Power Calculation

Page 117: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B8 SPECIFICATION SR-152

App B8/2

Table No. 1: The Averaged Sound Pressure/Intensity Level, measured at a

distance of 2 meters:

- Frequency range 1610,000Hz - The cooling system operated

Eq

uip

me

nt

Op

era

tion

Transformer operating conditions

Energized at: - Rated voltage

- No load

- Rated freq.

Energized at: - Impedance voltage

- Rated current

- Rated freq.

Not energized

Tap position

So

un

d p

ressu

re/in

ten

sity leve

ls a

t 1

/3 o

cta

ve

ba

nd f

requ

ency (

dB

/Hz)

16

20

25

31.5

40

50

63

80

100

125

160

200

250

316

400

500

630

800

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

10000

Overall Sound Pressure/Intensity Level, dBA weighted

Page 118: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B8 SPECIFICATION SR-152

App B8/3

Table No. 2: The Averaged Sound Pressure/Intensity Level, measured at a distance of 1.0 meters:

- Frequency range 1610,000Hz - The cooling system not operated

Eq

uip

me

nt

Op

era

tion

Transformer operating conditions

Energized at: - Rated voltage

- No load

- Rated freq.

Energized at: - Impedance voltage

- Rated current

- Rated freq.

Tap position

So

un

d p

ressu

re/in

ten

sity leve

ls a

t 1

/3 o

cta

ve

ba

nd f

requ

ency (

dB

/Hz)

16

20

25

31.5

40

50

63

80

100

125

160

200

250

316

400

500

630

800

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

10000

Overall Sound Pressure/Intensity Level, dBA weighted

Page 119: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B8 SPECIFICATION SR-152

App B8/4

Table No. 3: The Calculated Sound Power Level:

- Frequency range 1610,000Hz

- The cooling system operated/not operated

Eq

uip

me

nt

Op

era

tion

Transformer operating conditions

Energized at:

- Rated voltage

- No load

- Rated freq.

Energized at:

- Impedance voltage

- Rated current

- Rated freq.

Energized at:

- Rated voltage

- Rated current

- Rated freq.

Not energized

Cooling system

operated Not

operated operated

Not operated

operated Not

operated operated

Tap position

So

un

d p

ow

er

leve

ls a

t 1/3

octa

ve

ba

nd f

requ

ency (

dB

/Hz)

16

20

25

31.5

40

50

63

80

100

125

160

200

250

316

400

500

630

800

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

10000

Overall Sound Power Level, dBA weighted

Page 120: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B8 SPECIFICATION SR-152

App B8/5

Page 121: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B9 SPECIFICATION SR-152

App B9/1

CONTRACTOR’S TECHNICAL PERFORMANCE GUARANTEES

When during testing it is shown that the losses exceed the guaranteed level plus

tolerances on the principal, minimum and maximum taps as stated in this

Specification, the Contractor shall pay the I.E.Co. liquidated damages as follows:

1. For each transformer unit that the losses exceed the guaranteed level plus

tolerances on the principal, minimum and maximum taps, the Contractor shall

pay for each kW of losses in excess of the declared values (subcl. 10.3.21.4)

, without tolerances, liquidated damages as prescribed hereunder:

1.1. No-load losses - US$ 6050

1.2. Short-circuit losses - US$ 1850

1.3. Auxiliary power - US$ 2800

The liquidated damages are a genuine estimate of the direct damages foreseen

and are not to be regarded as penalty. They shall be calculated separately for

each type of losses indicated above and shall be cumulative.

2. For each type of transformer delivered according to this Specification the

average tolerances of no-load and short-circuit losses shall not exceed zero.

For each one percent which the average tolerance exceeds the guaranteed

value the Contractor will pay the I.E.Co. a compensation of one percent of the

Contract value.

The reference temperature for the losses considered in the calculation of the

above indicated damages shall be the standard reference temperature.

The calculation of exceeded losses will be performed separately for each type of

transformer and separately for no-load and short-circuit losses as well as for the

losses on the principal, minimum and maximum transformer taps.

Page 122: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B10 SPECIFICATION SR-152

The Israel Electric Corporation Ltd.

PROCEDURE

FOR

HANDLING OF NON-CONFORMANCES

Page 123: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B10 SPECIFICATION SR-152

App B10/2

It is the obligation of the Contactor to inform Israel Electric Corp. Ltd. (I.E.Co.) about

any deviation from the contract technical specifications, which occurs on any

action/item of the contract realization, such as design, raw materials, manufacturing

testing and inspection and so on. The deviations will be classified into the following

three (3) non conformance levels:

1. NON CONFORMANCE LEVELS

1.1. Non conformance (NC) of Level 1:

1.1.1. NC which do not affect the compliance to the contract technical specifications and the contract value.

1.1.2. NC which leads to slight modification into the contract technical specifications, but has certainly no effects on performance, neither on the short term nor on the long term, as well as not on the contract value.

1.2. Non-conformance of Level 2:

1.2.1. NC which do not affect the contract value but leads to modification of one or more the contract technical specifications, which has slight effects on secondary performances.

1.2.2. Scrapping parts with influence on the delivery time.

1.3. Non-conformance of Level 3:

1.3.1. Any other NC which is not included in the previous levels (For instance such a NC which can affect even uncertainly mandatory requirement or contract value).

Page 124: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B10 SPECIFICATION SR-152

App B10/3

HANDLING OF NON CONFORMANCE

Contractor reporting duty according to each non conformance levels below:

1.4. Level 1: No duty of notification.

1.5. Level 2: Duty of notification.

Within one (1) week the Non Conformity Report will be delivered to I.E.Co. Project Manager.

A Corrective Action (CA) Report is required, including the influence on time schedule, or other relevant contract issue, if any.

I.E.Co. has the right to send their remarks to the reports, including discuss the NC level classification.

1.6. Level 3: Duty of notification and approval by IECo necessary.

1. The Contactor shall stop the manufacturing immediately.

2. The Contactor will deliver a NC Report to I.E.Co. Project Manager within one (1) week.

3. When the disposition is to repair a detailed repair procedure must be presented to I.E.Co for approval immediately upon its issuing including a CA.

4. I.E.Co. will send its approval or rejection for the disposition within one (1) week. Any and only supplementary day will not be accounted as contactor delay.

5. Only after I.E.Co.’s approval the Contractor can resume manufacturing.

6. The NC equipment may be rejected in case of unsuitable implementation of the repair procedure and/or the CA taken.

7. Successful completion of the repair procedure and the CA should be reported to I.E.Co.

Page 125: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B11 SPECIFICATION SR-152

App B11/1

DESIGN REVIEW FOR TRANSFORMER ENGINEERING

1. Winding Design

Arrangement of Windings

Type of Winding (layered , continuous Disc, etc.)

Conductor configuration in each winding including conductor size

and insulation thickness

Regulating Winding location, design construction and tap lead exits

Leakage flux considerations

Fiber optics Temperature Probe location and calculations

2. Insulation design

Shielding in Winding

Clearances

Dielectric strength versus design margins

3. Short Circuit Design

Calculated stresses in windings compared to maximum design

allowed stresses

Calculated forces on members

Winding processing and compression during drying operations and

final clamping

4. Transient Voltage Distribution

Impulse

Switching

5. Core Design

Geometry, step lap, etc.

Induction level

Cooling ducts

Material

Core grounding

Page 126: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APEENDIX B11 SPECIFICATION SR-152

App B11/2

Leakage flux heating

6. Load Tap Changer

Voltage per step

Current per step

BIL

Contact life and maintenance requirements

Lead clearances And routing outside of winding

Tap changer must be operated at less than 80% of its current

rating to extend maintenance interval requirements

7. Cooling

Calculated winding and oil rises

Hot spot rises in each winding

Oil flow

Tap leads

Overload calculations

8. Tank Design and Oil Preservation System

Welding procedure

Gasket design

Radiator bank supports

Shielding

Core & Coil support

Access to equipment for maintenance, i.e. Bushings, core ground ,

cts

Valves

9. Test Program

functional test of all control circuits in factory to verify wiring

10. Preparation for Shipment, Field Installation and Field Processing

11. General Arrangement Drawing and Wiring Schematics Drawings

Page 127: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C1 SPECIFICATION SR-152

App C1/1

COMMANDS

No voltage object field 1 Line Diagram

1 161 TRIP CB 170KV GIS Q0

2 161 CLOSE CB 170KV GIS Q0

3 161 OPEN IL LINE 170KV GIS Q1

4 161 CLOSE IL LINE 170KV GIS Q1

5 161 OPEN IL LINE EARTH 170KV GIS Q8

6 161 CLOSE IL LINE EARTH 170KV GIS Q8

7 161 OPEN IL EARTH PETERSEN NEUTRAL SWGR NQ0

8 161 CLOSE IL EARTH PETERSEN NEUTRAL SWGR NQ0

9 161 MAN TAP CHANGER TRAFO TR1

10 161 AUTO TAP CHANGER TRAFO TR1

11 161 RAISE TAP CHANGER POS TRAFO TR1

12 161 LOWER TAP CHANGER POS TRAFO TR1

13 36/24KV TRIP CB INFEED 1Q0

14 36/24KV CLOSE CB INFEED 1Q0

15 36/24KV OPEN IL BB INFEED 1Q1

16 36/24KV CLOSE IL BB INFEED 1Q1

17 36/24KV TRIP CB COUPLER 2Q0

18 36/24KV CLOSE CB COUPLER 2Q0

19 36/24KV TRIP CB CAPACITOR 3Q0

20 36/24KV CLOSE CB CAPACITOR 3Q0

21 36/24KV TRIP CB FEEDER 1 4Q0

22 36/24KV CLOSE CB FEEDER 1 4Q0

23 36/24KV TRIP CB FEEDER 2 5Q0

24 36/24KV CLOSE CB FEEDER 2 5Q0

25 36/24KV TRIP CB FEEDER 3 6Q0

26 36/24KV CLOSE CB FEEDER 3 6Q0

27 36/24KV TRIP CB FEEDER 4 7Q0

28 36/24KV CLOSE CB FEEDER 4 7Q0

29 36/24KV IN RECLOSING RELAY BB HT

30 36/24KV OUT RECLOSING RELAY BB HT

31 IN LOAD SHED RELAY MOBILE

32 OUT LOAD SHED RELAY MOBILE

33 STEP 50.1 HZ MOBILE

34 VOLT REG SET1 TRAFO MOB

35 VOLT REG SET2 TRAFO MOB

36 VOLT REG SET3 TRAFO MOB

Page 128: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C2 SPECIFICATION SR-152

App C2/1

INDICATIONS

No voltage object field One Line Diagram

1 161 TRIP CB TRAFO MOB Q0

2 161 CLOSE CB TRAFO MOB Q0

3 161 OPEN IL LINE TRAFO MOB Q1

4 161 CLOSE IL LINE TRAFO MOB Q1

5 161 OPEN IL LINE EARTH TRAFO MOB Q8

6 161 CLOSE IL LINE EARTH TRAFO MOB Q8

7 161 OPEN IL EARTH CB TRAFO MOB Q51

8 161 CLOSE IL EARTH CB TRAFO MOB Q51

9 161 OPEN NEUTRAL SWGR CB TRAFO MOB NQ0

10 161 CLOSE NEUTRAL SWGR CB TRAFO MOB NQ0

11 161 MAN TAP CHANGER TRAFO MOB P7

12 161 AUTO TAP CHANGER TRAFO MOB P7

13 161 LINE VOLT EXIST LINE T1

14 36/24 TRIP CB TRAFO MOB 1Q0

15 36/24 CLOSE CB TRAFO MOB 1Q0

16 36/24 OPEN IL BB TRAFO MOB 1Q1

17 36/24 CLOSE IL BB TRAFO MOB 1Q1

18 36/24 TRIP CB COUPLER 2Q0

19 36/24 CLOSE CB COUPLER 2Q0

20 36/24 TRIP CB CAPACITOR 3Q0

21 36/24 CLOSE CB CAPACITOR 3Q0

22 36/24 TRIP CB FEEDER 1 4Q0

23 36/24 CLOSE CB FEEDER 1 4Q0

24 36/24 TRIP CB FEEDER 2 5Q0

25 36/24 CLOSE CB FEEDER 2 5Q0

26 36/24 TRIP CB FEEDER 3 6Q0

27 36/24 CLOSE CB FEEDER 3 6Q0

28 36/24 TRIP CB FEEDER 4 7Q0

29 36/24 CLOSE CB FEEDER 4 7Q0

30 36/24 OPEN IL EARTH LINE TRAFO MOB 1Q8

31 36/24 CLOSE IL EARTH LINE TRAFO MOB 1Q8

32 36/24 TRIP IL EARTH LINE COUPLER 2Q8

33 36/24 CLOSE IL EARTH LINE COUPLER 2Q8

34 36/24 TRIP IL EARTH LINE CAPACITOR 3Q8

35 36/24 CLOSE IL EARTH LINE CAPACITOR 3Q8

36 36/24 TRIP IL EARTH LINE FEEDER 1 4Q8

37 36/24 CLOSE IL EARTH LINE FEEDER 1 4Q8

38 36/24 TRIP IL EARTH LINE FEEDER 2 5Q8

39 36/24 CLOSE IL EARTH LINE FEEDER 2 5Q8

40 36/24 TRIP IL EARTH LINE FEEDER 3 6Q8

41 36/24 CLOSE IL EARTH LINE FEEDER 3 6Q8

42 36/24 TRIP IL EARTH LINE FEEDER 4 7Q8

43 36/24 CLOSE IL EARTH LINE FEEDER 4 7Q8

44 36/24 OUT RECLOSING RELAY BB HT

45 OUT LOAD SHED RELAY MOBILE

46 STEP 50.1 HZ MOBILE

47 VOLT REG SET1 TRAFO MOB

48 VOLT REG SET2 TRAFO MOB

49 VOLT REG SET3 TRAFO MOB

Page 129: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C2 SPECIFICATION SR-152

App C2/2

No voltage object field One Line Diagram

50 TAP CHANGER MODE TRAFO MOB

51 BCD TAP POSITION TRAFO MOB

52 BCD TAP POSITION TRAFO MOB

53 BCD TAP POSITION TRAFO MOB

54 BCD TAP POSITION TRAFO MOB

55 BCD TAP POSITION TRAFO MOB

56 BCD TAP POSITION TRAFO MOB

Page 130: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C3 SPECIFICATION SR-152

App C3/1

ALARMS

Alarms from Main Distributions

1 380VAC NO VOLTAGE AL

2 380VAC FUSE AL

3 60V DC FUSE AL

4 60V DC SEVERE AL(O.V, U.V & RIPPLE)

5 60V DC LEAKAGE AL

6 380VAC/60VDC CHARGER FAIL

7 48 VDC FUSE AL

8 60/48V CONVERTER FAIL

9 230 VAC UPS FUSE AL

10 60VDC/230VAC INVERTER FAIL

Alarms from 161kV

11 LOCAL (161kV) AL

12 LINE VOLTAGE TRANSFORMER FUSE AL

13 SF6 & GENERAL AL

14 C.B OPERATION LOCK AL

15 C.B CLOSE LOCK AL

16 C.B AL

Alarms from Transformer

15 LOCK OUT RELAY 1 AL

16 LOCK OUT RELAY 2 AL

17 BUCHOLTZ TRIP AL

18 BUCHOLTZ AL

19 TEMP AL

20 OIL LEVEL AL

21 TAP CH AL

22 FANS & FUSE AL

23 TRANS. PROTECTION FAIL

24 VOLTAGE REGULATOR FAIL

25 TEMPERATURE MONITOR FAIL

Alarms from 36/24kV

26 LOCAL (36/24kV) AL

27 SF6 FAIL

28 SPRING FAILURE(C.B)

29 BREAKER FAILURE PROTECTION TRIP

30 BREAKER FAILURE PROTECTION BLOCK

31 C.B ALARM

32 CAPCITOR BANK ALARM

33 INFEED C.B. AL

34 PT AL

Page 131: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C3 SPECIFICATION SR-152

App C3/2

Neutral Regime Alarms

35 PETERSON COIL ALARM

36 PETERSON COIL LOCK

37 LOSS OF EARTHING SYSTEM

38 LOCAL (Neutral Switchgear)

General Alarms

39 MV CONTROL & PROTECTION RELAYS COMMUNICATION

40 STATION ALARM

41 LOAD SHEDDING ALARM

42 PROTECTION RELAY, PS FAILURE & FUSE AL

43 MEASURING AND TRANSDUCER AC FUSE ALARM

44 AIR CONDITIONING SYSTEM ALARM

45 FIRE ALARM

46 FIRE SYSTEM FAILURE ALARM

SPARE

47 SPARE

48 SPARE

49 SPARE

50 SPARE

51 SPARE

52 SPARE

53 SPARE

54 SPARE

55 SPARE

56 SPARE

57 SPARE

58 SPARE

59 SPARE

60 SPARE

Page 132: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C4 SPECIFICATION SR-152

App C4/1

MEASURING

No. Transducer Measurement Voltage Output Location

1

3 Phase 3 Wire

Watt/VAR Transducer

Bi-directional Active Power

161 4-12-20mA

Cubicle 4.1 Control Cubicle

Bi-directional Reactive Power

161 4-12-20mA

2 3 Phase Current

Transducer

Current L1 161 4-20 mA

Cubicle 4.1 Control Cubicle

Current L2 161 4-20 mA

Current L3 161 4-20 mA

3 3 Phase Voltage

Transducer

Phase L1 161 4-20 mA

Cubicle 4.1 Control Cubicle

Phase L2 161 4-20 mA

Phase L3 161 4-20 mA

4 1 Phase Current Transducer

Current L2-Cub Q2

36/24kV 4-20 mA MV SWGR Q2

Current L2-Cub Q4

36/24kV 4-20 mA MV SWGR Q4

Current L2-Cub Q5

36/24kV 4-20 mA MV SWGR Q5

Current L2-Cub Q6

36/24kV 4-20 mA MV SWGR Q6

Current L2-Cub Q7

36/24kV 4-20 mA MV SWGR Q7

5

3 Phase Voltage

Transducer

Phase L1 36/24kV 4-20 mA

MV SWGR PT

Phase L2 36/24kV 4-20 mA

Phase L3 36/24kV 4-20 mA

6

Phase to Phase Voltage Transducer L1-L3

36/24kV 4-20 mA

MV SWGR PT

7 3 Phase 3 Wire VAR Transducer

Bi-directional Reactive Power

36/24kV 4-12-20mA MV SWGR Q3

8 Transformer Temp Monitor 0-150 Degrees

Trafo 4-20 mA

Cubicle 4.2 Transformer Protection Cubicle

9 Peterson Coil Voltage 0-115 V

Peterson Coil 0-115 V

Peterson Control Cabinet

10 60VDC Voltage Monitor 0-70 V

60VDC 4-20 mA Cubicle 4.3 60VDC Main Distribution

Page 133: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX C5 SPECIFICATION SR-152

App C5/1

TRANSDUCERS

No. Description

1 All the transducers shall have a standard output signal of direct current 4-20mA. In case of bi-directional energy flow the output signal shall be 4-n-20mA, n is linear with the zero point.

2 The transducer outputs shall be linearly proportional to the measured value over its entire range.

3 The transducers shall be designed for an external load of 0750 for each output.

4 The transducers will be externally powered from a 230 V.A.C. The power supply shall be galvanically isolated from all input-output circuits. The variations of supply voltage can be -15%÷+10%.

5 The voltage input circuits for 161 kV applications shall continuously withstand 1.2 times the rated voltage and for 1 sec. double the rated voltage.

6 The voltage input circuits for 2436 kV application shall withstand 1.9 times the rated voltage for 8 hours (28,800 sec.).

7 The current input circuits shall continuously withstand double the rated current and for 1 sec. 40 times the rated current.

8 The transducers shall be within 0.1% of full scale typical accuracy and within

0.2% of full scale in the worst case.

9 The transducers shall have a standard calibration adjustment of 20% of the

rated value and a zero adjustment of 10%.

10 Screw terminals and spaces between connections shall be dimensioned so that voltage and current conductors with cross-sectional areas of 4 mm2 can be connected.

11 ONE PHASE CURRENT TRANSDUCER input: 0-6A, 50Hz, output: 4-20mA, aux. supply 230VAC.

12

3 PHASE, 3 WIRE WATT/VAR TRANSDUCER WATT+VAR transducer 3 phases 3 wires unbalance load, input: VT=161KV/115V L-L, CT=400/5A, 50Hz, output: 4-12-20mA, -45-0-45 MW+MVAR, accuracy 0.1%, aux. supply 230VAC.

13 3 PHASE CURRENT TRANSDUCER Input: 0-6A, 50Hz, output: 4-20mA, aux. supply 230VAC. Quantity:5

14 ONE PHASE VOLTAGE TRANSDUCER (PHASE TO PHASE) Voltage transducer 1 phase, input: 0-(110)x1.2V, 50Hz, output: 4-20mA, aux. supply 230VAC.

15

3 PHASE VOLTAGE TRANSDUCER Voltage transducer 3 phases, input: 0-(115)x1.2/√3V, 50Hz, output: 4-20mA, aux. supply 230VAC. Quantity:2 Voltage transducer 3 phases, input: 0-(110)x1.2/√3V, 50Hz, output: 4-20mA, aux. supply 230VAC.

16

3 PHASE, 3 WIRE WATT/VAR TRANSDUCER WATT+VAR transducer 3 phases 3 wires unbalance load, input: VT=24KV/110V L-L, CT=400/5A, 50Hz, output: 4-12-20mA, -10-0-10 MW+MVAR, accuracy 0.1%, aux. supply 230VAC.

17 Types of equipment approved by IECo:

i. ACT-4I-3P, ACT-4V-3P, WVT-3 ( conlab) ii. 3CCFJ5, 3VCFJ5, 3WDGJ5 + 3RDGJ5 ( GEC)

Page 134: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/1

THE ISRAEL ELECTRIC CORPORATION LTD.

ENGINEERING PLANNING DIVISION

SUBSTATION PLANNING SECTOR

APPENDIX D1

Protection Functions

AUGUST 2016

Page 135: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/2

TRANSFORMER PROTECTION

Page 136: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/3

1. MV control and protection units

1.1. I/O

The minimum number and type of required inputs and outputs of the

MVCPU 24/36KV are according to the following table:

REQUIRED

quantity\type Comments Description

4 Accuracy ± 0.5% of the reading

CTs input (IR,IS,IT,I0) 0-5A

4 Accuracy ± 0.5% of the reading

VTs input (VR,VS,VT open delta 0-110V)

1 Accuracy ± 0.5% of the reading

VT input (0-110V Petersen Coil)

24 Infeed bay Binary input at least

24 Coupler bay

24 Capacitor bay

24 Line bay (feeder)

6 Infeed bay Command outputs at least

4 Coupler bay

4 Capacitor bay

4 Line bay (feeder)

2 Infeed bay NO + NC watchdog outputs

2 Coupler bay

2 Capacitor bay

2 Line bay (feeder)

12 Infeed bay NO relay output

12 Coupler bay

Page 137: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/4

REQUIRED

12 Capacitor bay

12 Line bay (feeder)

2 Infeed bay NC relay output at least

2 Coupler bay

2 Capacitor bay

2 Line bay (feeder)

6 Infeed bay Change-over relay output

4 Coupler bay

4 Capacitor bay

4 Line bay (feeder)

10/100 base + redundant 100 base

LAN Ethernet communication redundant ports at least

RJ45 or at least USB2 Front Communication ports

Communication ports

fail contact and indication on the

relay through local HMI screen or LED

for each

Power supply indications

128 configurable events Event recorder at least

10 Fault reports at least

479 Snapshot events at least

16 Data logger channels at least

16 Remote devices at least

32 GOOSE output GOOSE messages at least

64 GOOSE digital input

16 GOOSE Analog input

Table 1 I/O of MVCP Unit 24/36KV

Page 138: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/5

1.2. Protection functions

MVCPU 24/36KV protection functions allocation shall be as follows (for

details see Appendix D4):

Name Of Protection Function

Overcurrent Feeder

Residual Overcurrent

Directional Earth-fault (Wattmetric)

Auto-reclosure : Cycle 1, Cycle 2, Close time

Breaker Failure

SOTF - Switch On To Fault

Overcurrent Coupler

Residual Overcurrent

Breaker Failure

SOTF - Switch On To Fault

Overcurrent Infeed

Residual Overcurrent

Breaker Failure

SOTF - Switch On To Fault

Overcurrent Capacitor Bank

Residual Overcurrent

Breaker Failure

SOTF - Switch On To Fault

Directional Earth-fault (Wattmetric)

Over-voltage

Under-voltage

Table 2 Protection Functions 24/36KV

Page 139: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/6

1.2.1. Directional Earth Fault (Wattmetric) protection (32N) The Wattmetric protection has a 0° characteristic angle.

Maximum sensitivity is obtained when the measured current

is in phase with the polarizing voltage. For other phase

angles, the relay operates when:.

Figure 1 : Dir. Earth Fault (Wattmetric) protection (32N) characteristic angle.

Page 140: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/7

1.2.2. BREAKER FAILURE PROTECTION

When the BFP selector-switch of a bay is in the "block"

position, the BFP function of the bay will be blocked.

The following table represent the BFP logic for MV sections

substation

Legend :

- BFP of a bay operated.

- Trip command to the bay's circuit breaker .

- No operation.

HV BB2

Trafo Hv Bay

All the BB2 L 7Q0 L 6Q0 L 5Q0

CapB 4Q0 Inf 3Q0

Coup 2Q0

MV 24KV BB1

x x x x x x BFP Coup 2Q0

x x x x x BFP x Inf 3Q0

x x x BFP x x CapB 4Q0

x x BFP x x x L 5Q0

x BFP x x x x L 6Q0

BFP x x x x x L 7Q0

LEGEND 1

BFP

X

Page 141: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/8

Earthing State

Two different methods of earthing system are used, including a

Petersen coil and an earthing switch:

1. The Petersen coil and the earthing switch are connected

directly to the neutral point.

DRAWING 2

Page 142: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/9

Protection Enabled

PC>V02 VOLTAGE RAISE

PC CLOSED

EIS AND ES CLOSED

Leakage 1 0 0

Wattmetric OR Leakage

Leakage 0 0 0

Wattmetric 1 1 0

No Protection enabled 0 1 0

Leakage 1 0 1

Leakage 0 0 1

Leakage 1 1 1

Leakage 0 1 1

Leakage COMMS FAIL

Wattmetric AND Leakage 1 0 0

Wattmetric AND

Leakage

Leakage 0 0 0

Wattmetric AND Leakage 1 1 0

Leakage 0 1 0

Wattmetric AND Leakage 1 0 1

Leakage 0 0 1

Wattmetric AND Leakage 1 1 1

Leakage 0 1 1

Leakage COMMS FAIL

Table 3 Wattmetric and/or leakage fuctionality, Resistor "ON"

Page 143: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/10

Protection Enabled

PC>V02 VOLTAGE RAISE

Unacceptable

Leakage 0 1 Wattmetric OR Leakage Leakage 1 1

Leakage 0 1

Wattmetric OR Leakage

Wattmetric AND Leakage 1 1

Protection Enabled

PC>V02 VOLTAGE RAISE

Loss of system earthing

Leakage 0 1 Wattmetric OR Leakage Leakage 1 1

Leakage 0 1

Wattmetric OR Leakage

Wattmetric AND Leakage 1 1

Table 4 Leakage and/or Wattmetric Protection Functionality considering

and "loss of earthing" states.

Page 144: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/11

1.3. Load shedding

The under frequency functions for the three priority levels are defined as follows

Frequency level Relay functionality

Priority 1 Under-frequency 1 Frequency Rate of change 1

Priority 2 Under-frequency 2 Frequency Rate of Change 2 Analog level Comparator 1 Analog level Comparator 2

Priority 3 Under-frequency 3 Frequency Rate of Change 3

Table 5 Frequency protection functinality for the three priority levels

Page 145: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/12

The minimum number and type of required inputs and outputs of the

frequency relay are according to the following table:

REQUIRED

quantity\type Comments Description

2 Accuracy ± 0.5% of the reading from BB1-2

VTs input (VR,VS,VT open delta 0-110V)

12 Binary input at least

10 Outputs to control center at least

2 NO + NC watchdog outputs

2 Change-over relay output

10/100 base + redundant 100 base

LAN Ethernet communication ports

RJ45 or at least USB2 Front Communication ports

Communication ports

fail contact and indication on the

relay through local HMI screen or LED

for each

Power supply indications

128 configurable events Event recorder at least

10 Fault reports at least

479 Snapshot events at least

16 Data logger channels at least

16 Remote devices at least

32 GOOSE output GOOSE messages at least

32 GOOSE digital input

16 GOOSE Analog input

Table 6 I/O OF FREQUENCY RELAY

Page 146: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/13

1.3.1. Feeder Restoration

The under-frequency relay logic (T12, T13, T14 Time Shift

between the Priorities).

TIMER Settings Location

Radial logic

T12 (Time between the command

coming from the NCC and the start

of the Restoration of P3)

80 s UF logic

T13 (Time between the Restoration

of P3 and the P2)

50 s UF logic

T14 (Time between the Restoration

of P2 and the P1)

10 s UF logic

Table 7 Time shifts between the priorities

Page 147: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D1 SPECIFICATION SR-152

App D1/14

1.4. MV Capacitor Bank Switching

Typical connection of a MV Capacitor Bank is as in the following scheme:

Figure 2 Modular Capacitor Bank

Figure 3 Capacitor Bank CB Close permission

Page 148: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/1

THE ISRAEL ELECTRIC CORPORATION LTD.

ENGINEERING PLANNING DIVISION

SUBSTATION PLANNING SECTOR

APPENDIX D2

Time Synchronization

AUGUST 2016

Page 149: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/2

1. TIME-SYNCHRONIZATION

1.1. General description

IEC's (Israel electric company) specifications for digital relays and digital

systems for substations include requirements for time-synchronization, by a

GPS system, located in the substation.

Two methods of time-synchronization for digital relays and digital systems are

possible (see Drawing TS-1):

1. Direct synchronization link between a digital relay or system and a

GPS system in the substation.

2. Time synchronization of digital relays and systems through the LAN

(Local Area Network) of the central control system of the substation.

1.2. General requirements

For both methods, the IEC had made a set of the following minimum

requirements:

1. The time resolution in the log (event/fault recorder) of the time-

synchronized relays/systems will be 1 (one) millisecond or a fraction of a

millisecond.

2. The time difference between the log of time-synchronized digital

relays/systems in a given substation (∆T1), will not be more than 5 (five)

millisecond.

3. The time difference between the log of digital relays which comprise one

organic system (e.g. decentralized fault-recorder, protection or control

system) (∆T2), will not be more than 1 (one) millisecond (see Drawing TS-

2).

4. The time difference between the log of a REFERENCE GPS system, and

the log of each of the time-synchronized digital relays/systems in the

substation (∆T3), will not be more than 10 (ten) millisecond (see Drawing

TS-3).

Page 150: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/3

1.3. Method of testing

(Drawing TS-3).

A GPS system with an internal log and a discrete input will serve as a

REFERENCE GPS.

One pulse at a time will be sent to a discrete input of each of the tested relays

or systems (time-synchronized in method 1 or 2, as described above) and to

the REFERENCE GPS from a single source in the substation.

The registrations in the logs of the tested relays or systems will be compared

with the registrations in the log of the REFERENCE GPS.

The average ∆T1, ∆T2, ∆T3 are calculated according to the log results of at

least 10 (ten) sequential impulses. Relays or systems will be qualified if their

average ∆T1, ∆T2, ∆T3 is within the acceptable range (as indicated above).

A log reading that will deviate more than 50% of the acceptable ∆T1, ∆T2, and

∆T3 will disqualify the relay or system.

Page 151: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/4

Page 152: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/5

Page 153: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D2 SPECIFICATION SR-152

App D2/6

Page 154: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/1

THE ISRAEL ELECTRIC CORPORATION LTD.

ENGINEERING PLANNING DIVISION

SUBSTATION PLANNING SECTOR

APPENDIX D3

Frequency Relay

AUGUST 2016

Page 155: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/2

1. ELECTRICAL DESIGN REQUIREMENTS

1.2 The frequency relay required, shall have the functions stated in

the Technical Specification subclause 21.3.10.4.

1.3 (Optional) – Possibility to receive voltage data created by a non-

conventional c.t. v.t., i.e. Rogovsky coil, connection to process

bus by which Manufacturer is to be indicated. Reference list of

existing systems is to be submitted.

1.4 The frequency relay shall be proven in operation and shall

operate satisfactorily under the environmental conditions stated

previously.

The relay shall be stable against vibrations.

1.5 The relay shall in general be insensitive to harmonics, frequency

variations, D.C. components in the fault currents and induced

high transient voltages, and EMC & RFI.

1.6 The relay shall continue its proper operation in the case of

inadvertent grounding of one point in the DC supply circuits or

any other point at the terminal board.

1.6 The relay auxiliary supply voltages are to be continuously

supervised, with a fault indication provided upon detection of a

fault condition.

Page 156: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/3

2. GENERAL REQUIREMENTS FOR FREQUENCY RELAYS.

2.1 The frequency relay shall be connected to the secondary side of

the high voltage transformer.

2.2 The frequency relay shall be capable of detecting the following

situations: over-frequency, under-frequency, frequency rate of

change and three phase under-voltage.

2.3 The relay shall have at least 3 protection stages in addition to a

recovery function.

2.4 Each protection stage shall be applicable for load shedding upon

under-frequency and frequency rate of change. The stage shall

be able to act alone upon each condition or as a combination of

under-frequency and frequency rate of change. The stage shall

include 4 separate adjustable timers. In addition, each protection

stage shall be able to be activated by 3 phase under-voltage.

2.5 When the stage times out the relay produces a trip signal. The

trip signal can be linked to the desired output contact. The

contact mode shall be programmable between normal mode

(i.e., drops out when under-frequency and frequency rate of

change condition is no longer present) and latched mode (i.e.,

drops out only upon pickup of recovery function).

2.6 The relay shall have programmable low voltage blocking. Low

voltage condition shall set an output contact.

2.7 The relay shall have an external control input to block all three

stages.

2.8 The recovery function after frequency load shedding shall pick

up upon reaching a set over-frequency or activated via external

recovery input. The recovery function shall include 3 separate

adjustable timers for closing the circuit breaker of the three

loads.

2.9 The recovery function after under-voltage load shedding shall

pick up upon reaching a set over-voltage or activated via

Page 157: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/4

external recovery input. The recovery function shall include 3

separate adjustable timers for closing the circuit breaker of the

three loads.

3 Self-Monitoring, Testing and Supervision

3.1 The relay's auxiliary supply voltage shall be continuously

supervised.

3.2 The digital frequency relays shall perform continuous self-

monitoring and self-testing of the frequency relay hardware and

software with fault diagnostic display. Upon detection of a

hardware fault, the relay shall block itself and issue an alarm.

3.2.1 In the event that a software fault is detected, the micro-

processor shall reset and restart. If the fault is not eliminated by

restarting, the relay operation is to be blocked.

4 Human-Machine Interface

4.1 The Human Machine Interface (HMI) shall be made possible

using a Serial interface for communication with a portable PC

terminal. HMI, also via push buttons and LCD, is preferred but

not compulsory

4.2 The HMI operating language shall be English.

4.3 The HMI facilities shall be used for relay setting (from portable

PC only), for reading of events, for reading of primary system

data and for diagnostic purposes.

4.4 Memory shall be provided to store two settings, which can be

selected by an external signal. Alteration of setting data shall be

protected by means of a code-word.

4.5 The frequency relay shall be equipped with alarm and trip front-

plate signals which are user selectable (at least 8 alarms).

Page 158: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/5

4.6 The relay settings and configurations shall be made possible by

the use of a PC with the appropriate user interface program. The

user interface program shall be in English and be included in the

scope of supply. A minimum of ten (10) copies/licenses shall be

offered.

4.7 In addition to the relay port for the portable PC, the relay shall be

equipped with a second port for sub-station communication,

according to Standard IEC-61850.

5 Algorithms and Software

5.1 The Contractor shall submit a comprehensive description of the

signal processing methods used to make relaying decisions.

This description shall include:

- Sampling rate.

- Digital filtering methods.

- Calculation accuracy.

5.2 The Contractor is required to submit a comprehensive

description of the software implemented in the microprocessor

including overall relaying flow-chart and type of input-output

control.

6 User’s Applicable Logic Software.

The digital relay is to consist of logic software capable for the

use of the Purchaser. This software is to have the following

characteristics:

6.1 Inputs to the Software:

a) Binary electrical inputs to the relay.

b) Internal binary variables created by the frequency relay.

c) Analog values measured by the relay or calculated by the

relay.

d) Binary output of other parts of the user’s software.

Page 159: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/6

6.2 Output of the Software:

a) Output contacts of the relay, including trips and close

contacts.

b) Inputs to the frequency relay (which are also activated by

external electrical inputs to the relay).

c) L.E.D.’s alarms on the front of the relay.

d) Other inputs segments of the user’s software.

6.3 Software Logic

The input to the software is to be processed by combination of

logical gate timers and flip-flops.

Each of the binary inputs and outputs of the logic components

can be inverted.

6.4 The processing of the additional user’s software is not to affect

proper operation of the frequency relay.

6.5 The repetition rate of the software (i.e. the numbers it runs per

cycle) is to be selectable.

6.6 The Bidder is to supply data regarding the C.P.U. loading vs. the

user’s logic size in use.

6.7 Alarm notification is to appear in case the user’s logic size is

subjecting the proper operation of the frequency relay.

Page 160: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/7

SUMMARY OF DATA FOR FREQUENCY RELAY FOR LOAD SHEDDING

Name of Bidder: _____________________________

REQUIRED OFFERED

7. FREQUENCY RELAY

7.1 General Technical Data

7.1.1 Relay type

7.1.2 Voltage Measuring Circuits

7.1.2.1 Number of analog voltage (number)

Preferred

Minimum 3 phase

1 phase to phase

7.1.2.2 Rated voltage (phase to phase) (v) 115 ©

7.1.2.3 Rated frequency (Hz) 50 ©

7.1.2.4 Burden (VA) ≤ 0.5 ©

7.1.2.5 Maximum conditions voltage (phase to phase)

(V) > 2 x 115 ©

7.1.2.6 Maximum voltage during 1 sec (V)

7.1.2.7 Requirements of cables of voltage circuits

(Screened, cross – section)

7.1.3 Auxiliary DC Supply

7.1.3.1 Auxiliary DC voltage (V) 60VDC+15%-

10%

7.1.3.2 Power consumption quiescent (W) < 30

7.1.3.3 Power consumption picked-up (W) < 40

7.1.4 Command Relays

7.1.4.1 Number of trip contacts (No.) ≥ 3 ©

7.1.4.2 Number of close contacts (No.) ≥ 3 ©

7.1.4.3 Make and carry capacity for 0.5 sec

L/R > 10ms (A) 30A

7.1.4.4 Break switching capacity L/R >40 ms (A) ≥ 0.5 A ©

At 220 VDC

7.1.4.5 Switching voltage (V) 60V DC ©

7.1.4.6 Permissible continuous current (A) ≥ 10 A

7.1.5 Signal Relays

7.1.5.1 Number of signal contact (No.) ≥ 8 ©

7.1.5.2 Make and carry capacity for 0.5 sec

L/R > 10ms (A) 15 A

7.1.5.3 Break switching capacity L/R>40ms (A)

At 220V DC ≥ 0.2 A

Page 161: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/8

REQUIRED OFFERED

7.1.5.4 Switching voltage (V) 60V DC ©

7.1.5.5 Permissible continuous current (A) ≥ 5 A

7.1.6 Binary Inputs 60VDC+15%-

10%

7.1.6.1 Number of binary inputs (No.) ≥ 8

7.1.6.2 Input signal voltage 60V dc Yes ©

Can the binary inputs also function using

60V DC signal voltage Yes

7.1.6.3 Current consumption ≤ 20 mA

7.2 Frequency and Voltage Module

7.2.1 Total of frequency stages 4 ©

7.2.2 First three tripping stages to be set by under-

frequency and/or rate of change of frequency

Yes ©

7.2.3 Setting range of under frequency elements 40-55 Hz

7.2.4 Fourth stage to be a recovery function set by

over-frequency

Yes ©

7.2.5 Setting range of over frequency recovery

function

45-60 Hz

7.2.6 Are frequency function and rate of change

frequency function independent?

Yes

7.2.7 Number of independent under frequency

functions (number of stages)

≥ 3 ©

7.2.8 Number of independent rate of change of

frequency function

≥ 1 ©

7.2.9 Number of independent timers for first under

frequency function

3 ©

7.2.10 Number of independent timers for second under

frequency function

2 ©

7.2.11 Number of independent timers for third under

frequency function

1 ©

7.2.12 Number of independent timers for rate of change

of frequency function

≥ 3 ©

7.2.13 Rate of change of frequency can be

independently assigned to each tripping stage

Yes ©

7.2.14 Total of voltage stages 4

7.2.15 First three tripping stages to be set by under- voltage Yes

7.2.16 Setting range of under voltage elements (p.u.) 0.6-0.95

7.2.17 Fourth stage to be a recovery function set by over-

voltage

Yes

7.2.18 Setting range of over voltage recovery function (p.u.) 0.9-1.3

7.2.19 Number of independent under voltage functions

(number of stages)

≥ 3

7.2.20 Number of independent timers for first under voltage

function

1

7.2.21 Number of independent timers for second under

voltage function

1

Page 162: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/9

REQUIRED OFFERED

7.2.22 Number of independent timers for third under voltage

function

1

7.2.23 Can the recovery function after frequency/rate of

change of frequency load shedding be initiated by an

external contact?

Yes ©

7.2.24 Can the recovery function after voltage load shedding

be initiated by a separate external contact?

Yes

7.2.25 Can the frequency/rate of change of frequency load

shedding function be blocked by an external contact?

(yes/no)

Yes ©

7.2.26 Can the voltage load shedding function be blocked by

a separate external contact? (yes/no)

Yes

7.2.27 Trip contact can be programmed to drop outs when

under- frequency or voltage condition is no longer

present (according to 2.5)

Yes ©

7.2.28 Trip contacts can be programmed to remain latched,

i.e. drops out only upon pickup of recovery function

Yes ©

7.2.29 Programmable low voltage blocking for frequency

/rate of change of frequency load shedding function

Yes ©

7.2.30 Setting range for low voltage blocking (p.u.) for

frequency and rate of change of frequency load

shedding

0.0-0.6

7.2.31 Programmable low voltage blocking for voltage load

shedding function

Yes

7.2.32 Setting range for low voltage blocking (p.u.) for

voltage load shedding

0.0-0.6

7.2.33 Programmable three phase voltage plausibility

blocking (i.e. prevents voltage load shedding due to 3

phase faults)

Yes

7.2.34 Can the relay perform all the under-frequency and

rate of change of frequency load shedding functions

as depicted in drawing STR-1002-1

Yes ©

7.2.35 Can the relay perform all the under-frequency, rate of

change of frequency and voltage load shedding

functions as depicted in drawing STR-1002-2

Yes

7.2.36 Number of independent timers (of type pulse after on

delay) for 3 tripping stages of frequency load

shedding

7.2.37 Number of independent timers (of type pulse after on

delay) for 3 tripping stages of voltage load shedding

3

7.3 Supervision function

Page 163: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/10

REQUIRED OFFERED

7.3.1 AC voltage (PT-MCB)

Block operation in case of MCB failure(yes/no) ..............

Yes

7.3.2 DC supply (yes/no) Yes

7.4 Self -Monitoring and Testing © 7.4.1 Software supervision 7.4.1.1 By watchdog hardware time (yes/no) 7.4.1.2 By other means 7.4.2 Memory checksum test a. During power up (yes/no) b. During service (yes/no) c. Frequency of self-test during service 7.4.3 A/D Accuracy test © a. During power up (yes/no) Yes b. During normal operation

(continuously/ periodically)

7.5 Human-Machine Interface 7.5.1 Standard PC connected to relay with possibility to

perform the following function during normal

operation

Yes ©

7.5.1.1 Relay parameter setting (yes/no) Yes © 7.5.1.2 Reading of data from relay, memory and storing: Yes © a. on PC RAM (yes/no) b. on PC Hard disk or floppy disk (yes/no) 7.5.1.3 Reading and storing of currently measured data

(yes/no) .............................................................................

7.5.2 LED on relay front 7.5.2.1 Number of LEDs 8 7.5.2.2 Can LED be programmed for each alarm (yes/no) Yes 7.5.3 The user interface program shall be in English and be

included in the Scope of Supply of the Contract

Yes ©

7.5.4 A minimum of ten copies /licenses of the user

interface program shall be offered

10

7.5.5 Push buttons and LCD

Relay shall be equipped with push buttons and LCD

for parameters setting and reading of measured data

Yes

7.6 COMMUNICATION 7.6.1 Serial port communication © 7.6.1.1 Number of serial ports 7.6.1.2 Type of port 7.6.1.3 Communication speeds (Baud) 7.6.1.4 Data transfer interface connection transmission

distance (m)

7.6.1.5 Communication through serial port to operator

interface:

a). By portable PC (yes/no) b). Type of connection RS232,RJ45 7.6.2 Communication for substation communication 7.6.2.1 According to IEC-61850 7.6.2.2 Type of port 7.6.2.3 Communication speed

Page 164: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/11

REQUIRED OFFERED

7.6.2.4 Data transfer interface connection transmission

disconnector

7.6.1.6 Communication through optical port to operator

interface

7.6.1.7 Optical connection (type, standard) 7.7 Algorithm and Software 7.7.1 Description of signal processing and algorithm as

required in clause 6

Indicate Document number

7.7.2 Type of analog filtering and transfer characteristic 7.7.3 Sampling rate of A/D converter 7.7.4 Type of digital filtering 7.7.5 Supplier shall keep the Purchaser informed on new

hardware/software development improvements and

shall offer them on a special rate/free of charge

(yes/no)

yes ©

7.8 User’s Applicable Logic Software 7.8.1 The user’s software is based on programming

language (indicate)

7.8.2 Number of user’s software segments, available 8 7.8.3 Type of logical gates available (indicate) function

complete

component

7.8.4 Number of logical gates available in each segment 16 7.8.5 Total number of logical gates available 128 7.8.6 Number of timers available in each segment 2 7.8.7 Total number of timers available 16 7.8.8 Time range of the timer, and time step (indicate) 0.001 msec

1000 sec/

0.001 sec

7.8.9 Number of flip-flop available in each segments 4 7.8.10 Total number of flip-flop available 32 7.8.11 C.P.U. loading Vs. size of user’s software (add

graphs)

Page 165: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/12

Page 166: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D3 SPECIFICATION SR-152

Name of Bidder: ____________________________________

App D3/13

Page 167: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D4 SPECIFICATION SR-152

App D4/1

THE ISRAEL ELECTRIC CORPORATION LTD.

ENGINEERING PLANNING DIVISION

SUBSTATION PLANNING SECTOR

APPENDIX D4

MV Bay Protection Functions

AUGUST 2016

Page 168: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D4 SPECIFICATION SR-152

App D4/2

CAPACITOR BANK

FUNCTION BLOCK FUNCTION INITIATE FUNCTION

* LOR Operates PHASE TOC LOW 1

(I>)

ACCORDING TO Appendix D1 TABLES No. 3,4 * LOR Operates NEUTRAL TOC 1

(I0>)

32N HIGH 1

ACCORDING TO Appendix D1 TABLES No. 3,4

(WATT GND FLT HIGH)

(BFP BLK)' (from selector)

AND Q1 LINE BFP INITIATE

AND

(I> TRIP OR I0> TRIP

OR UNBALANCE TRIP)

PHASE OV 1

(over voltage)

PH UV 1

(under voltage)

In the PLC the delay will be set to 5 min (300000 ms)

PH OV 2

(NORMAL VOLTAGE)

(permit to close)

UNBALANCE AL

(IAC)

* LOR Operates UNBALANCE TRIP

(IAC)

Page 169: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D4 SPECIFICATION SR-152

App D4/3

COUPLER

FUNCTION BLOCK FUNCTION INITIATE FUNCTION

None

PHASE TOC LOW 1

(I>)

None PH IOC HIGH 1

(I>>)

Q0 OPEN PH TOC HIGH 1

2 sec after CB close (in PLC) (SOTF)

(BFP BLK)' (from selector)

None AND Q1 LINE BFP INITIATE

AND

(I>/I>> TRIP)

(*including trip from SOTF)

Page 170: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D4 SPECIFICATION SR-152

App D4/4

INFEED

FUNCTION BLOCK FUNCTION INITIATE FUNCTION

None

PHASE TOC LOW 1 (I>)

PH IOC HIGH 1

None

(I>>) None

NEUTRAL TOC 1

(I0>)

Q0 OPEN PH TOC HIGH 1

2 sec after CB close (in PLC) (SOTF)

ACCORDING TO

"LOSS OF EARTHING" LOGIC

Initiation timer in the PLC will be set to 15 min

Loss Of Earthing

(BFP BLK)' (from selector) None AND Q1 LINE BFP INITIATE

AND (I>/I>> TRIP OR I0> TRIP)

(*including trip from SOTF)

Page 171: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

APPENDIX D4 SPECIFICATION SR-152

App D4/5

LINE FEEDER FUNCTION BLOCK FUNCTION INITIATE FUNCTION

PHASE TOC LOW 1

(I>)

AR BLK AFTER 2 SHOT

AR BLOCK

PH IOC HIGH 1

AR BLK AFTER 1 SHOT

(I>>)

AR LOCKOUT (end of AR operation)

ACCORDING TO Appendix D1 TABLES No. 3,4

NEUTRAL TOC 1

(I0>)

AR BLK AFTER 2 SHOT

AR BLOCK NEUTRAL IOC1

AR BLK AFTER 1 SHOT (I0>>)

AR LOCKOUT (end of AR operation)

ACCORDING TO Appendix D1 TABLES No. 3,4

AR IN PROG

Q0 OPEN PH TOC HIGH 1

2 sec after CB close (in PLC) (SOTF)

32N HIGH 1

ACCORDING TO Appendix D1 TABLE No.4

(WATT GND FLT HIGH)

SOTF TRIP,LOCAL,L.S. TRIP

BFP TRIP RECEIVE,BFP TRIP SEND

AR Selector

Dispatch Center AR

CB Not Ready

(BFP BLK)' (from selector)

AND Q1 LINE BFP INITIATE

AND

(I>/I>> TRIP OR I0>/I0>> TRIP)

(*including trip from SOTF)

Page 172: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 1 of 7

App TR031/1

1. Documents to be submitted during proposal stage

1.1. Drawings and parts list of the proposed semitrailer including all accessories and required

devices.

1.2. Submit details and catalog pages for the proposed transportation items including: axles,

suspension, etc... Please specify: manufacturer's name, model and characteristic

dimensions.

1.3. Submit operating instructions for the semitrailer and the included equipment in Hebrew

or English.

1.4. An agreement with a certified vehicle laboratory in ISAREL which is recognized by the

ministry of Transport in ISRAEL.

2. Requirements from the winning supplier

2.1. The semitrailer will be supplied with all documents required by law. Valid certificate,

signed by the Ministry of Transport and the Israel Police.

2.2. The semitrailer will be supplied in a ready to operate condition with al devices required

by law.

2.3. Two operation and maintenance manuals in Hebrew will be supplied for each for semi –

trailer.

2.4. Training for operation and transport of the semitrailer will be provided. Up to 10 drivers

will participate in the training.

3. Service

3.1. The supplier commits to provide spare parts supply, assemblies, and repair service for a

period of at least five years from the delivery date of the semi – trailer.

3.2. Supply of spare parts will be performed within 7 working days.

3.3. Supply of assemblies will be performed within 21 working days.

3.4. Service and repairs during the warranty period and thereafter will be performed within

48 hours from the time the service call, not including Saturdays and holidays.

3.5. Supplier undertakes to maintain and provide spare parts for the semi – trailer.

Page 173: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 2 of 7

App TR031/2

4. Technical Requirements for all semitrailers

4.1. The semitrailers shall comply with international highway regulations and its design data

shall be approved by Israeli Ministry of Transport.

4.2. The semitrailers shall be able to travel safely with all the equipment installed, at a

maximum permissible speed by the traffic regulations in Israel without police escort.

4.3. Maximum dimensions of the semitrailers shall not exceed:

4.3.1. Width- 3.4 (m).

4.3.2. Height- 4.8 (m).

4.4. The semitrailers shall be equipped with axles type ROR or equivalent.

4.5. The load distribution on all excels shall be according to Israeli authorities requirements.

4.6. The Manufacturer shall take into account in design of semitrailers the stresses.

4.7. The semitrailers shall be provided with hydraulic or pneumatic suspension to permit

lifting and lowering the entire semitrailer platform. The suspension shall be

interconnected and isolated also by means of appropriate valves.

4.8. 15m turning radius shall be ensured with all semitrailer wheels by means of steering

wheel.

4.9. The semitrailers shall include special means which will enable the connection of the

semitrailer to the ground.

4.10. Semitrailers braking system shall be in accordance with international regulations and

shall be approved by Israeli Ministry of Transport.

4.11. Semitrailers electrical system shall be in accordance with international regulations and

shall be approved by Israeli Ministry of Transport.

4.12. The necessary documents for approval by competent authorities shall include with all

above required data.

4.13. The semitrailers shall be tested in accordance with international regulation and

standards.

4.14. All necessary authorizations, documents, approvals by competent Israeli authorities

shall be obtained by Contractor before the semitrailer is built. All costs in connection

with these approvals shall be bear by Contractor.

4.15. Boxes for labor safety equipment, fire protection equipment and maintenance tools shall

be provided on one of the semitrailers.

4.16. A system of personnel crossovers, access platforms and/or decking's, staircases and

ladders provided with railings shall be included.

4.17. Removable covering to protect the wheels against sun radiation shall be provided.

4.18. The nameplate with maximum speed shall be added on each semitrailer. All nameplates

of semitrailers shall be in English and Hebrew.

Page 174: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 3 of 7

App TR031/3

4.19. A device for measuring and recording the amplitude of vibration during transport shall

be mounted on each semitrailer. Indicate type. An alarm shall be given in driver cabin in

case of higher amplitude of vibration.

4.20. A list of spare parts for each semitrailer shall be provided.

4.21. Instruction book shall be provided in English and Hebrew.

4.22. Hydro pneumatic jacks for the full lifting of the semitrailer during storage and operation

will be provided. Jacks shall be installed between the axles.

4.23. Plates for load dispersion will be provided and installed in suitable and accessible

storage locations.

4.24. There will be exact matching with the electric and pneumatic equipment existing in the

trucks.

4.25. Made by known European company, Radial tubeless tires will be supplied. The tires

will be imported to Israel in irregular imports and will be existing in the Israeli market.

4.26. A central grease unit will be provided which will allow greasing of all the necessary

places in the semi – trailer.

4.27. Braking system with electronic command including ABS.

4.28. If a diesel fuel tank having a volume of 1000 liters or above will be supplied, the

semitrailer will be provided with ADR approval for transportation of hazardous

materials.

4.29. All equipment will be installed on the semitrailer will be new and unused. All installed

parts will be original and new.

4.30. The semitrailers will be provided with all the devices needed according to the laws of

transportation in Israel.

4.31. The supplier is responsible for the repair or replacement of any part included the

semitrailer that has any flaw in the material and / or workmanship.

4.32. All controls, operation levers, and switches will be clearly marked in Hebrew. Signs

will be legible and durable in the weather conditions existing in country.

4.33. All lights would be LED type.

4.34. Lighting will be installed in the upper rear of the semitrailers.

4.35. The semitrailers (except of the multi axels semitrailer) shall be provided with two (2)

pairs parking legs.

4.36. The semitrailers (except of the multi axels semitrailer) diameter of king pin shall be 2

inch.

4.37. Two (2) wheels shall be provided as spares. Easy and safety lifting machine would be

supply for each spare wheel.

Page 175: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 4 of 7

App TR031/4

5. Technical Requirements for the multi axels semitrailer

This semitrailer shall include among other things:

5.1.1. Three (3) pairs parking legs.

5.1.2. One (1) muted 6HP Diesel engines for steering-wheel, leveling feet's and pistons

with an electric starter, manually backup, with an additional fuel tank volume of 20

liters and a battery charger to charge at storage time The engine will be light and

small as possible and allow carrying by one person.

5.1.3. All system pipes will provide with fast connections.

5.1.4. The tires will be manufactured by YANMAR or recognized as equivalent.

5.1.5. Air brakes on all wheels with emergency break-away feature.

5.1.6. Chock blocks for rear wheels.

5.1.7. Heavy-duty pneumatic screws jack for leveling and removing the load from the

tires.

5.1.8. Fifth wheel plate and king pin for use with universal rocking type coupler suitable

for 90 degree turning.

5.1.9. Front vertical supports for semitrailer with two speed adjustments.

5.1.10. Fender over all wheels.

5.1.11. Flexible cable with separable plug for connecting the semitrailer light circuit to

the towing unit.

5.1.12. Hose and fitting for connecting the brake system of the semitrailer to the towing

unit.

5.1.13. “VOLVO FH500” or "MAN TGX480" trucks shall be used for towing the

semitrailer.

5.1.14. Mud flaps at the rear of the semitrailer.

5.1.15. Metallic cable trays shall be provided for H.V. and L.V. cables, under each

semitrailer floor.

5.1.16. Removable cover for H.C. cables shall be provided.

5.1.17. Blocking devices for stationary.

5.1.18. Six (6) wheels shall be provided as spares. Easy and safety lifting machine

would be supply for each spare wheel.

5.1.19. The diameter of king pin shall be 3.5 inch.

5.1.20. Towing eyes at rear of the semitrailer.

5.1.21. Lighting at the top rear of supported.

5.1.22. Tires air pressure saving system.

5.1.23. Massive, waterproof, Self-drive remote control + lifting the leveling cylinders.

The remote will work wirelessly and wired (with 10 meter cable length). Storage

box with lock permeable waterproof will provide for the remote. The remote will be

provided with two 120-volt battery and charger.

Page 176: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 5 of 7

App TR031/5

5.1.24. Operating position to perform self-driving action + level of the leveling

cylinders will be installed on the trailer.

5.1.25. The support legs will be hydraulic and manually.

5.1.26. LED strip with flashing orange lights will be installing at the rear of the

semitrailer.

6. Painting and marking:

6.1. Surface Preparation

6.1.1. Solvent Cleaning – SSPC SP-1

6.1.2. Abrasive Cleaning – Sa-2½ (ISO 8501-1), Profile 50-75 micron.

6.1.3. Welds Grinding - NACE RPO 178, level C

6.2. Coating Application

6.2.1. Top Color: Traffic orange RAL 2009

6.2.2. Every layer shall be different color.

6.2.3. Strip Coating on top of all sharp edges (with the same prime coat).

6.2.4. Prime Coat – Epoxy mastic 70 micron (Include missed coat).

6.2.5. Intermediate coat – HB Epoxy – 100 micron.

6.2.6. Top coat – Aliphatic Polyurethane – 60 micron. Total DFT = 230 micron.

6.3. Quality

6.3.1. All the trailers will be mounted with 3M Diamond Grade Conspicuity Marking

around the platform.

6.3.2. The Contractor shall provide for each semitrailer, painting certificate.

The painting certificate shall include at least:

6.3.2.1. Identification number of the equipment.

6.3.2.2. Testing code.

6.3.2.3. Prime intermediate and top coat (description and type of paint).

6.3.2.4. Thickness of coats and measuring instruments (SSPC PA-2).

6.3.2.5. Test results of "Pull off Test" as per ASTM D-4541, Minimum 5 MPa.

The test can be done on test panels. A detailed report is needed.

6.4. All the trailers will be mounted with 3M Diamond Grade Conspicuity Marking around

them platform

Page 177: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 6 of 7

App TR031/6

Datasheet

To fill by offering subject Company Name proposers

Address company proposing

Name of the company representative

Phone number of the company's representative

Email address of the company's representative

Equipment manufacturer name

Equipment manufacturing country

semitrailer manufacturer name

semitrailer manufacturing country

Requirements for all semitrailers:

Length:

Wide:

Height:

Weight:

dimensions of the each semitrailer

Semitrailers axles type

Load distribution on each excel

Axels model

Turning radius of each semitrailer

Type of measuring and recording amplitude of vibration

device

Tires size

Tires manufacturer

Volume of the diesel fuel tank

Amount of each trailer axles

king pin diameter

Amount of spare wheels

Requirements for multi axels semitrailer:

king pin diameter

Amount of spare wheels

engines for steering-wheel:

HP-

fuel tank volume-

weight-

Page 178: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Organization and Logistics Division Logistics and Property Department

Nationwide transport

Tel: 076-8636010, Fax: 04-8183574

Date :26/12/2016

Specification: TR-031

Edition : 1

Technical Specifications for the purchase of semitrailers for

transformer mobile station

Page 7 of 7

App TR031/7

Tires size

Tires manufacturer

Degree turning Fifth wheel plate and king pin

Amount of spare wheels

Page 179: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

1 Prepare By: Ilan Akons

Design requirements for the protection of electrical

equipment from Electric Field Interferences (EFI)

1. Enclosure / control cubicles / control boxes - requirements against EFI

1.1. Background

1.1.1. Codes description for shielded enclosure reducing the effect of Electro-

Magnetic Interferences (EMI) to external radiation sources shall be

according to IEC-61000-5-7.

1.1.2. Test Performance shall be according to IEC-61000-5-7 cl. 7.9. cl. 5 (table 1).

1.1.3. General Test Approach shall be according to IEC-61000-5-7 cl. 6

1.1.4. The shield designators A through F define the demonstrated shielding

performance for each of the frequency bands of table 1. The format of the

code for the enclosure/cubicle shield shall use the format: EMABCDEF (see

table 1).

The shielding performance indicated by the designator is the minimum value

that is provided by the enclosure for the stated frequency band.

Table 1 – Electro-Magnetic field shield code designators

Frequency

band

Shield

designator

Shield

performance

dB

Shield

designator

value

10 kHz -100 kHz A Untested x

100 kHz - 1 MHz B <10 0

1 MHz - 30 MHz C ≥10 1

30 MHz - 1 GHz D ≥20 2

1 GHz - 10 GHz E ≥30 3

10 GHz - 40 GHz F ≥40 4

≥50 5

≥60 6

≥80 7

≥90 8

≥100 9

Page 180: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

2 Prepare By: Ilan Akons

1st example, an enclosure with a demonstrated shield effectiveness of at

least 50 dB over the frequency range from 100 kHz to 1 GHz, but which

was not tested at other frequencies, would be designated as: EMx555xx

2nd

example, an enclosure has a demonstrated shield effectiveness of 40

dB over the frequency range from 10 kHz to 30 MHz, and a shield

effectiveness of 50 dB for the frequency range from 30 MHz to 10 GHz,

shall be specified as: EM44455x

1.1.5. The enclosure / control cubicle should be made of a highly-conductive

material such as steel or aluminum of sufficient thickness and incorporate

various penetrations for access, power, communications, ventilation, so that

the equipment in cubicle will continue to function during and after an event of

a pulse of 50000 [V/m] electric field.

1.1.6. The manufacturer can protect the inner equipment with several shielded layer

to protect various equipment with different isolated levels. Any variance from

this isolation level should be accompanied by technical data showing that

equipment can tolerate such fields.

1.1.7. For outdoor enclosure / control cubicle type the shield code shall be at least:

EM4677xx

1.1.8. For indoor enclosure / control cubicle type the shield code shall be defined

with respect to the building/structure/shelter attenuation shielding

effectiveness.

1.2. Technical Requirements

1.2.1. Environmental Protection - Cubicle's environmental protection degree

shall be at least - IP54

1.2.2. Shield - Cubicle's shield degree shall be EM4677xx according to IEC-

61000-5-7 clause 5 (table 1)

1.2.3. Material - The cubicle should be made of a highly-conductive material

(such as steel or aluminum of sufficient thickness) and incorporate various

penetrations for access, power, communications, ventilation, so that the

equipment in the LV Container will continue to function during and after

an event of a pulse of 50,000 [V/m] electric field.

1.2.4. Equipment Isolation - The equipment in the cubicle shall be isolated from

outside interferences even against a 50,000 [V/m] electric field pulse hit

the cubicle.

Page 181: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

3 Prepare By: Ilan Akons

1.2.5. Equipment Protection - The manufacturer may protect the inner

equipment with several shield layers to protect various equipment with

different isolated levels. Any variance from this isolation level should be

accompanied by technical data showing that equipment can tolerate such

fields.

1.2.6. Access – Access doors, including personnel doors, shall provide sufficient

electric field isolation so as not to compromise the overall Shield

Specification of the low voltage (LV) container above.

The manufacturer doors design shall rely and meet MIL-STD-188-125-1

cl. 5.4.2 (see figure 2).

1.2.7. Air Intake/Exhaust – any outside air intake or exhaust shall be through a

Waveguide Below Cutoff or other shielded means that provides sufficient

electric field isolation so as not to compromise the overall Shield

Specification of the LV Container above.

The manufacturer design shall rely and meet MIL-STD-188-125-1 cl.

5.5.3 (see figure 4).

1.2.8. Power – The power supply feed into the LV Container shall be through an

filter that limits conducted emissions to below 5 [V]. Any level of

isolation that results in greater than 5 [V] conducted emissions should be

accompanied by technical data demonstrating the level of tolerance above

5 [V].

1.2.9. Sensors & Conductors - Sensor and actuator conductors should travel

through an appropriate filter and/or penetration closet that provides

sufficient electric field isolation so as not to compromise the overall shield

specification of the LV container above.

The manufacturer design shall rely and meet MIL-STD-188-125-1 cl.

5.4.2.2 (see figure 3).

1.2.10. DC charger and battery cabinet - The LV container shall provide for the

inclusion of a battery cabinet and appropriate battery charging equipment.

Any external access hatches to the battery cabinet shall be designed to

provide sufficient electric field isolation so as not to compromise the

overall shield specification of the LV container above.

The manufacturer design shall rely and meet MIL-STD-188-125-1 cl.

5.4.2.2 (see figure 3).

1.2.11. Other Penetrations - Other penetrations may be required to maintain the

required level of RF isolation from the electric field pulse. No

penetrations shall be placed into the design that compromises the isolation

performance of the LV container. All penetrations, no matter what

purpose or function, shall be engineered to maintain the Shield

Specification of the LV container above.

The manufacturer design will be according to MIL-STD-188-125-1 and

other sub-clauses mentioned previously.

Page 182: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

4 Prepare By: Ilan Akons

1.2.12. Wiring - All metallic wiring connections from / to the cubicle shall be

done with shielded cables. Connections of cables will be through metallic

connectors only.

1.2.13. Cable wiring shall comply with IECo. Standard EPD-A.03 (see Appendix

A8).

1.2.14. Communication cables - Communications cables shall be of fiber optic

design wherever feasible (see requirements in Section #4).

1.2.15. Other Connections - Fiber-optic connections shall be done according to

manufacturer instructions.

2. Cable requirements

Wire cables shall be protected from exterior electric fields whichcould harm them.

For new flexible cables, their shielding performance shall comply with table 2

requirements.

The table is based on the figure from the MIL-STD_188-125-1, Appendix A, figure A-5.

Frequency range Minimum Shielding conductive fabric

Attenuation [DB]

10 [kHz] - 100 [kHz] 50

100 [kHz] - 1 [MHz] 70

1 [MHz] - 10 [MHz] 85

10 [MHz] - 100 [MHz] 90

100 [MHz] - 1 [GHz] 90

1 [GHz] - 5 [GHz] 85

Table 2: shielding performance

Figure 2: Examples of shielded cables with wiring

Page 183: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

5 Prepare By: Ilan Akons

Figure 2 (Cont.): Examples of shielded cables with wiring

3. Grounding Strap requirements

3.1. Grounding, unless otherwise specified, shall consist of a copper strap of at

least 35mm in width and at least 0.6mm in thickness, and be of the shortest

practical length subject to technical, physical, and environmental factors.

3.2. Grounding straps shall be attached to the grounding gird/mat through

soldering exothermic bonding or other non-mechanical means.

3.3. Grounding Straps shall be placed so that shielded cables, conduits and other

conductive cabling can be grounded at each end as a minimum.

4. Cable connections between external equipment and control cubicle

The sub clauses herein relate to cables wiring between VT's, CT's, sensors etc. and the

control cubicle.

Communications cables shall be fiber optic wherever feasible, otherwise:

4.1. All cables shall be of the shielded type and the sheath shall be earthed at

both ends.

4.2. Cables can be installed in standard galvanized rigid steel conduits, or

electrical metallic tubing, or ducts, with water tight joints, both ends shall be

earthed, to enlarge the RF attenuation.

Page 184: THE ISRAEL ELECTRIC CORPORATION LTD. ORGANIZATION, …

Appendix Y1 Design requirements to protect electric equipment

6 Prepare By: Ilan Akons

5. Wires to control cubicle

Low-voltage power supply wires and communication cables permanently installed in

RJ45 and/or USB ports shall be installed inside shielded conduit or braid shields. The

manufacturer design of the metallic conduit and the braid shields shall rely and meet

the attenuation requirements shown in table 2.

Both conduit and braid shields ends shall be earthed.

6. Connection of external shielded cable to cubicle

The shielding of the connection of wires entering the metallic cubicle shall not be

inside the cubicle but from outside, see figure no. 3

Figure 3: Example of optimal bonding of a shielded cable to the enclosure by a

compression fitting providing a 360-degree bond