the eurisol multi-mw target unit: radiological protection and radiation safety issues

23
THE EURISOL MULTI-MW TARGET UNIT: RADIOLOGICAL PROTECTION AND RADIATION SAFETY ISSUES Y. Romanets 1 , R. Luis 1 ,J. Bermudez 3 , J.C. David 5 , D. Ene 5 , I. F. Goncalves 1 , Y. Kadi 2 , C. Kharoua 2 , F. Negoita 4 , R. Rocca 2 , L. Tecchio 3 , P. Vaz 1 1 ITN - Estrada Nacional 10, 2686-953, Sacavém, Portugal 2 CERN- CH-1211, Genève 23, Switzerland 3 INFN-LNL - Viale dell'Università, 2 - 35020 Legnaro (PD), Italy 4 NIPNE - Str. Atomistilor no.407, P.O.BOX MG-6, Bucharest - Magurele, Romania 5 CEA - Saclay, DSM/IRFU/SPHN, F-91191 Gif-sur-Yvette, France SATIF-10, CERN 2-4 June 2010

Upload: angelica-figueroa

Post on 30-Dec-2015

24 views

Category:

Documents


0 download

DESCRIPTION

The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues. Y. Romanets 1 , R. Luis 1 ,J . Bermudez 3 , J.C. David 5 , D. Ene 5 , I. F. Goncalves 1 , Y. Kadi 2 , C. Kharoua 2 , F. Negoita 4 , R. Rocca 2 , L. Tecchio 3 , P. Vaz 1 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

THE EURISOL MULTI-MW TARGET UNIT:RADIOLOGICAL PROTECTION AND RADIATION SAFETY ISSUES

Y. Romanets1, R. Luis1,J. Bermudez3, J.C. David5, D. Ene5, I. F. Goncalves1, Y. Kadi2, C. Kharoua2, F. Negoita4, R. Rocca2, L. Tecchio3, P. Vaz1

1ITN - Estrada Nacional 10, 2686-953, Sacavém, Portugal 2CERN- CH-1211, Genève 23, Switzerland

3INFN-LNL - Viale dell'Università, 2 - 35020 Legnaro (PD), Italy4NIPNE - Str. Atomistilor no.407, P.O.BOX MG-6, Bucharest - Magurele, Romania

5CEA - Saclay, DSM/IRFU/SPHN, F-91191 Gif-sur-Yvette, France

SATIF-10, CERN 2-4 June 2010

Page 2: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Outline

The EURISOL Project Facility layout

Multi-MW Target Station

Geometry used on the simulations

Calculation results

Conclusions

Page 3: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

EURISOL-DS European Isotope Separation On-Line Radioactive Ion Beam Facility

The main objectives of the EURISOL Design Study were:

to show the reliability of the next-generation European ISOL Radioactive Ion Beam (RIB) facility as well as the consistence of it’s key elements: driver accelerator, target/ion-source assembly, mass-selection system and instrumentation;

to find the possible cross-interest of the scientific and research areas with other actual European projects and existing laboratory infrastructures;

to come out with the key technologies and the engineering solutions which need to evolve in order to progress on such kind of projects;

Page 4: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

THE EURISOL FACILITY4 MW Proton Accelerator

(1GeV, up to 4mA)Multi MW Target Station

Mass SeparatorPost Accelerator

Page 5: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

General layout of the Multi MW Target Station

Page 6: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Facility layout including support maintenance spaces

Proton Beam

Page 7: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

A

C

B

General view of the facility (implemented (FLUKA) geometry): A – Cut (Plane) perpendicular to the beam, include fission target handling room, RIB extraction elements, fission target end spallation target area. Cut on the point of the beam collision(z=0 cm); B – Zoom of the fission targets and spallation target area; C – Zoom of the fission targets and spallation target areas. Plane parallel to the beam (x=0 cm).

Proton beam

1 m

1 m 1.2 m

Page 8: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

RESULTS

Page 9: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Spallation Target and Fission Targets areasNeutron and photon flux (n*cm-2

*mA-2), FLUKA performed calculationsNeutron flux

Plane z=0

Plane x=0

Photon flux

Plane z=0

Plane x=0

7 m

8 m

10 m

Page 10: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Fission Targets Handling RoomNeutron and photon flux (n*cm-2

*mA-2), FLUKA performed calculations

Plane z=0cm

13 m

14 m

Neutron fluxPhoton flux

A B

Particle flux distribution in the Fission Target Handling Room during operation of the facility. Particle fluxes due leaks through the fission products extraction tubes: A – Photon flux distribution; B – Neutron flux distribution;

(n*c

m-2

*mA-2

)

(n*c

m-2

*mA-2

)

Page 11: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Fission Targets Handling Room(FLUKA performed calculations)

Plane z=0cmPrompt irradiation

4MW (1GeV*4mA) proton beam

0 day (shutdown time) cooling time

Dose‐E

Q (

Sv*h

‐1)

Dose‐E

Q (

Sv*h

‐1)

Activity (Ci*g‐1), 0 day (shutdown time) cooling time

13 m

14 m

Page 12: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Dose Equivalent after ShutdownDose‐EQ (Sv*h‐1)

Plane x=2cm (-1cm:1cm)Plane z=0.8 cm (-0.5cm:0.3cm)0 day (shutdown time) cooling

time

Page 13: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Spallation Target and Fission TargetsNeutron flux (n*cm-2

*mA-2), FLUKA performed calculations

Plane x=0cmPlane z=0cm

1 m

1 m 1.2 m

Page 14: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Activities after Shutdown (decay contribution after 200 days of irradiation (4MW power proton beam))

Activity (Ci*g‐1) Plane x=2cm (-1cm:1cm)Plane z=0.8 cm (-0.5cm:0.3cm)

0 day (shutdown time) cooling time

1 year cooling time

Page 15: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Mercury Loop Trolley

Neutron flux (n/cm2/mA)

prompt irradiation, 1MW (1GeV*1mA) proton

beam

2.5 m

5 m

2.5 m

2.5 m

Page 16: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Mercury Loop TrolleyActivities after Shutdown

0 day (shutdown time) cooling time

1 year cooling time

Activity (Ci*g‐1)

Page 17: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Dose‐E

Q (

Sv*h

‐1)

Dose‐E

Q (

Sv*h

‐1)

Mercury Loop TrolleyDose Equivalent

Prompt irradiation, 4MW (1GeV*4mA) proton beam

Page 18: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Extraction Tubes

Page 19: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Extraction Tubes

Page 20: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Extraction Tubes

Page 21: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

CONCLUSIONS

Activation – the key parameter for: Future maintenance of the facility and each sector of it Evaluation of the facility waste production (Type and quantity)

Geometry – needs particular attention on this case because: Main element of the system, extraction tubes, are the source of the

direct neutron leak Due to the necessity of exchanging/replacing various elements of the

system from time to time and to the requirements of the high safety level, the geometry becomes more complicated

Dose - determination of this value is fundamental for: Decision on choice of the access type for the different parts/sectors of the

facility Shielding requirements Conditioning/restrictions on the operation and maintenance of the facility

Project supported by the European Commission under the FP6 “Research Infrastructure Action- Structuring the European Research Area” EURISOL-DS Project Contract no. 515768 RIDS. Part of the work has also been supported by the Portuguese Foundation for the Science and Technology (FCT) in the framework of the projects CERN/FP/83586/2008 and POCI/FP/81951/2007

Page 22: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010

Thank you

Page 23: The EURISOL Multi-MW Target Unit: Radiological protection and radiation safety issues

SATIF-10, CERN 2-4 June 2010