the do’s and don’ts of government construction contracts joseph c. kovars, esq. ober|kaler 100...

74
The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 [email protected] | 410.347.7343 Barbara G. Werther, Esq. Ober|Kaler 1401 H Street, N.W. Washington, DC 2005 [email protected] | 202.326.5015 Or David Letterman’s Top Ten Traps for the Unwary www.ober.com

Upload: claud-owen

Post on 26-Dec-2015

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

The Do’s and Don’ts of Government Construction Contracts

Joseph C. Kovars, Esq.Ober|Kaler

100 Light StreetBaltimore, MD 21202

[email protected] | 410.347.7343

Barbara G. Werther, Esq.Ober|Kaler

1401 H Street, N.W.Washington, DC 2005

[email protected] | 202.326.5015

Or David Letterman’s Top Ten Traps for the Unwary

www.ober.com

Page 2: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Top Ten Traps

1. Authority to bind the Government

2. Funding of contract—Anti-Deficiency Act

3. Recognizing constructive changes

4. Notice requirements

5. Bilateral modification releases

6. Documentation: letter in/letter out

7. Updating schedules

8. Cure notices/show cause

9. Claim certification

10. False claims 2

Page 3: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Federal Acquisition Regulation (FAR)

Provides uniform policies and procedures for acquisitions by Federal Gov’t agencies

Parts 1-51 are policies and instructions

Part 52 is standard form clauses

Part 53 is forms

FAR clauses apply to the extent they are incorporated into the contract, either full text or by reference.

The Christian Doctrine

3

Page 4: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Procurement Methods for Construction

Sealed bidding – FAR Part 14

Only used where price is sole basis for award

Contracting by Negotiation – FAR Part 15

Used when factors other than price are considered

Used for “Best Value” procurements

“Negotiation” is a term of art – its not a real negotiation!

4

Page 5: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Sealed Bidding

Invitation for Bid (IFB) is used

Bids are publicly opened

Award goes to lowest price, responsive bid by a responsible bidder

“Responsive” bid means complies in every respect with the requirements of the IFB (FAR 14.404-2)

“Responsible” bidder refers to financial resources, integrity, organization and skills, ability to meet schedule, and past performance (FAR Part 9.1)

Firm, fixed-price contract results.5

Page 6: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contracting By Negotiation

Request for Proposals is used (RFP)

Tradeoff between price and other factors (Best Value)

Evaluation factors and significant sub-factors must be clearly stated (Section M of RFP)

Must state whether all other factors are more important, less important or equally important as price

Separate technical and price proposals submitted (separate volumes)

6

Page 7: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contracting By Negotiation - 2

Technical evaluation by technical team

Price evaluation by price team

Technical & price kept separate until final selection decision

Oral presentations can be used

Can typically award on basis of initial proposals without “discussions”

Or can hold “discussions”, followed by BAFO

7

Page 8: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contracting By Negotiation - 3

If discussions are held with one offeror, must hold discussions with all within competitive range

Discussions must indicate deficiencies, significant weaknesses and adverse past performance information

Exceptions may be taken, but are risky

Additional features and enhancements may be offered

8

Page 9: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contracting By Negotiation - 3

Debriefing of unsuccessful offerors available on request

When to protest?

What’s the likelihood of winning a protest?

9

Page 10: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Funding – Anti-Deficiency Act

Procurements are funded through appropriations.

The appropriation is listed on the contract form; should be checked.

Anti-Deficiency Act prohibits: Making or authorizing an expenditure or creating or authorizing an obligation in excess of the amount available in the appropriation or fund unless authorized by law. (31 U.S.C. s. 1341(a)(1)(B))

10

Page 11: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Funding – Anti-Deficiency Act

Anti-Deficiency Act -- Government’s representatives cannot make any payment or a commitment to make payment for work unless there are sufficient funds “in the bank” (in the appropriation) to cover the cost in full.

What does this mean in terms of the multiyear construction project?

11

Page 12: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Funding – Anti-Deficiency Act

Limitation of Funds clause (FAR 52.232-22) - Monitor costs and notify at 75%. Right to stop work.

Availability of Funds clause (FAR 52.232-19) – “Funds are not presently available for performance beyond ______. . .” Implied right to stop work.

What happens when the Government runs out of money and there is no new appropriation?

12

Page 13: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

FAR 52.243-4 CHANGES (JUNE 2007)

(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes --

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the Government-furnished property or services; or

(4) Directing acceleration in the performance of the work.

13

Page 14: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating (1) the date, circumstances, and source of the order and (2) that the Contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.

14

Page 15: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.

15

Page 16: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

(e) The Contractor must assert its right to an adjustment under this clause within 30 days after (1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.

(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.

16

Page 17: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

The contractor is required to perform the changed work as directed and make claim under the Disputes Clause if not paid. (Constructive change or dispute over unilateral amount granted). FAR 52.233-1(i)

Permissible scope of changes

Drawings and specifications

Method or manner of performance

GFM/GFP

Directed acceleration

Time of performance (nights, weekends)

Place of performance

17

Page 18: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

Types of Changes» Formal» Constructive

Formal/Express Changes

Directed change or CCD – unilateral from Government

Bilateral – supplemental modification to contract Accord and satisfaction Reservation of rights

Who may initiate? Either party

18

Page 19: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

Constructive Changes:

Conduct by C.O. or authorized representative which has the effect of causing the Contractor to perform work different from that set forth in the contract,

Even when not described or acknowledged as a change.

19

Page 20: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

Elements of a Change

Direction to do something different from existing contract

Within the general scope of the contract

Issued by C.O. (or duly authorized representative)

20

Page 21: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

What does “within the general scope” of the contract mean? No exact formula

99.99% of every change you will ever see.

Prohibition on issuing changes outside the general scope because significantly different work should be put out for bid.

Changes beyond general scope are “cardinal changes.”

21

Page 22: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes

Cardinal change

1965, Wunderlich Constructing Co. v. U.S., Court of Claims says changes beyond the general scope of the contract are “cardinal changes”

The number of changes, in and of itself, is not necessarily a cardinal change

More of the same kind of work (i.e., more asbestos abatement) not a cardinal change

Direction to build an airstrip when the contract was for the terminal probably is a cardinal change

22

Page 23: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Authority

Who has authority to issue changes to the Contract? (FAR 1.603-3(a))

Only the C.O. (or authorized representative) has authority to bind the Government and modify the contract

Who is the C.O. ?

What is authority of COTR?, ROICC?, etc.

23

Page 24: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Authority

The Government is not legally bound by unauthorized acts or acts of unauthorized agents

Apparent Authority is NOT AVAILABLE AGAINST THE GOVERNMENT.

Contractor’s duty to assure authority behind direction.

Don’t be a “Volunteer.”

24

Page 25: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Authority

When is the Government bound by unauthorized actions?

Implied Authority/Course of Conduct

Ratification

Equitable Estoppel

25

Page 26: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Authority

Who does not have authority?

Inspectors

Contract administrators

Getting confirmation:

If you are “directed” by a Government representative, send a letter to the C.O. and ask the C.O. if you are to comply with the directive, i.e., have the C.O. ratify the “directive.”

26

Page 27: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Constructive Changes

What is a constructive change?

(Subsection (b) of the changes clause)

(1)A directive to the Contractor

(2)Requiring the Contractor to perform additional or changed work

(3)Contractor relied on the Government direction and incurred increased cost, added time

(4)Notice given

27

Page 28: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Types of Constructive Changes

1. Interpretation of specifications and drawings

Ambiguity in the specifications/drawings Patent vs. latent

The ambiguity is latent

The contractor’s interpretation is reasonable

The Government has a different interpretation and tells the contractor to perform in accordance with the Government’s interpretation

The contractor incurs additional costs by complying with Government’s interpretation

28

Page 29: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes - Types of Constructive Changes

2. Inconsistencies between drawings and specifications

FAR 52.236-21:

If only in specifications, or only in drawings, treat as if mentioned in both places

In case of difference, specifications govern over drawings

If the discrepancy is patent, duty to inquire pre-bid

If the discrepancy is latent, give notice, segregate costs

29

Page 30: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

3. Defective Specification

The Government warrants the adequacy of its specifications

Must be a design specification (implied warranty on Government under Spearin)

Specifications contain errors, omissions, inconsistencies

Contractor entitled to costs of attempting to comply and for performing corrective work

Changes - Types of Constructive Changes

30

Page 31: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com31

Page 32: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

3. Defective Specification

The Government warrants the adequacy of its specifications

Must be a design specification (implied warranty on Government under Spearin)

Specifications contain errors, omissions, inconsistencies

Contractor entitled to costs of attempting to comply and for performing corrective work

Changes - Types of Constructive Changes

32

Page 33: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Risk of Specification Problems

Design Specifications – Government owns risk

Performance Specifications – Contractor owns risk

Mixed Specifications – It depends (analyze in detail)

Changes - Types of Constructive Changes

33

Page 34: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com34

Page 35: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Changes – Types of Constructive Changes

Risk of Specification Problems (cont’d)

Design-Build Contracting

Building Information Modeling (BIM)

35

Page 36: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

BIM

36

Page 37: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

4. Inspection and Testing

Government over-inspection

Improper or incompetent rejection

Government directs a change in testing method or frequency

More stringent testing procedure than that set forth in contract

Interference by Government in unreasonable inspecting during performance

Changes - Types of Constructive Changes

37

Page 38: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

5. Changes In The Method And Manner Of Performance

Where C.O. insists on a change in the contractor’s method and manner of performance of the work

Contractor can recover the difference in cost between its method and Government’s method

Example – change in planned sequence

Changes - Types of Constructive Changes

38

Page 39: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

6. Constructive Acceleration

When Government effectively requires the contractor to finish earlier than planned

Changes - Types of Constructive Changes

39

Page 40: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

7. Duties of Cooperation, Not to Hinder

NTP issued, but contractor not permitted to construct road to worksite

Work on railroad tracks can only be performed with Owner’s flagmen and at night, but no flagmen work at night

C.O. withheld design fix from contractor and charged contractor LDs for not finishing “on time”

Changes - Types of Constructive Changes

40

Page 41: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

8. Cumulative Impact

Combined impact of a large number of changes

Ripple effect

Note: Low rate of success in cases. Measurement of damages is “amorphous.”

Be careful when signing modifications

Bell BCI v. United States (Fed. Cir. 2009)

Changes - Types of Constructive Changes

41

Page 42: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Notice Requirements

Notice must be timely

Notice must be in writing

Notice must be sent to the C.O.

Notice must set forth the nature of the claim

Constructive changes– notice relates back 20 days, as to costs incurred

No time limit for defective specifications

Changes

42

Page 43: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Exceptions to Strict Notice Requirements(1) Where the Government knew about the basis of the claim* Actual knowledge can be shown from Government records* Presence of Government personnel on jobsite* Acts of Government in working with contractor to address issue* Meetings

(2) Where the Government considers the claim on the merits without complaining about lack of notice

(3) Where the Government is not prejudiced by the lack of notice

* Government has burden of proving it was prejudiced

* Prejudice occurs if Government cannot mitigate expense or elect any one of available options

Changes

43

Page 44: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contractor Duty to Proceed The Contractor must perform the changed work

– C.O. can terminate contract for default if contractor does not proceed

– Disputes Clause: Contractor can submit its claim Equitable Adjustment

Price:– Bruce Construction v. U.S., 324 F.2d 516 (Ct. Cl. 1963) – “keep [a]

contractor whole when the Government modifies the contract.”– “Actual, reasonable cost” ordinarily incurred because of the change » Actual cost plus reasonable OH + P

– May include costs incurred for affected work areas not changed Time

If the change order implicates work on the critical path, additional time may be required

The Request for Equitable adjustment (REA)

Changes

44

Page 45: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Delays & Suspension

Types of delays

Excusable, Compensable, Unexcused

Special Cases: –Sovereign vs. contractual acts;–Subcontractors & suppliers;–Bankruptcy & financial inability (unless

Government caused)

Compensable Special Case:–Differing Site Conditions

45

Page 46: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Concurrent delays – burden on claiming party to untangle

Net effect : excusable delay; no damages recoverable by either party

Requires two delays on critical path

Highly fact intensive

The “Hurry Up and Wait” problem

Delays & Acceleration

46

Page 47: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Notice requirements:

10 days. Prejudice rule.

Boards believe in contemporaneous records.

Right to early completion – conceptually accepted, but difficult to prove.

Schedule must be realistic and relied upon

Delays & Acceleration

47

Page 48: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Proving Delay Claims

Sophistication of Boards and Court of Claims for delay claims

CPM schedule is normal basis of proof

Some cases even say hard to imagine proving claim without CPM analysis

Sophisticated in review/analysis of CPM presentations TIA/Windows Impacted as planned, Collapsed as built,

Delays & Acceleration

48

Page 49: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Important to use contemporaneous schedules and updates.

Have solid schedule as early as possible

Update it accurately and honestly.

Will have to live with project schedule for claims purposes

If Government restricts updates, create shadow schedule

Delays & Acceleration

49

Page 50: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Acceleration

Well recognized doctrine

Actual and constructive

Constructive – effect of requiring acceleration

Delays & Acceleration

50

Page 51: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Terminations for Default – FAR 52.249-10

Draconian – a “forfeiture” - disfavored

High standard of proof

Default termination is discretionary with C.O.

Improper default termination is converted to a T for C

High stakes – a dispute is “winner take all”

Terminations

51

Page 52: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Terminations for Default (cont.)

If default sticks, the government recovers its re-procurement costs from the defaulted contractor

And, any other rights available to the Government, such as LDs

Burden of proof is on the Government to show, by a preponderance of the evidence, that the default termination was proper.

Terminations

52

Page 53: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Grounds for Default Termination

A. Failure to complete the work within the time for the contract or any extension.

B. “Failure to make progress”

C. Repudiation by the contractor

D. Contractor’s failure to perform its obligations under the contract

E. Failure to provide adequate assurances that performance will proceed

F. Failure to continue performance during a dispute

Terminations

53

Page 54: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Cure Notice (or Show Cause) FAR 49.402-3(e)

Required in supply contracts

Not required in construction contracts

But, Government often issues cure notice

Take this very seriously

Provide adequate assurances

Terminations

54

Page 55: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Contract Disputes Act

Basic statute governing claims

Established claims process and forums for disputes

Initiation of claim – submitted to CO, request Final Decision

Definition of “claim” written assertion,

matter of right,

payment of sum certain

Claims and Disputes

55

Page 56: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Must be Certified if over $100,000

Final Decision is prerequisite to appeal/litigation Final Decision must be provided in 60 days

Unless it isn’t – can specify a longer period (usually 60 more)

May consider claim as deemed denied” if not timely issued

Interest from date of certification

Claims and Disputes

56

Page 57: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Certification Requirement

Classic trap for unwary

Made by authorized person who can bind the company

“Claim made in good faith”

“Supporting data are accurate and complete to the best of my knowledge and belief”

“Amount requested accurately reflects the adjustment for which the contractor believes the Government to be liable”

Claims and Disputes

57

Page 58: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Under penalty of perjury

False Claims Act liability – criminal and civil, company and personal

Subcontractor issues – want subcontractor to certify to you

Even if the sub does so, need to do due diligence independently,

Can’t rely blindly on sub certification.

Pass thru agreements-- need to remain liable to sub for what sub is claiming.

Claims and Disputes

58

Page 59: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Claims and Disputes

Appealing Contractor Performance Evaluation Todd Construction v. U. S., 656 F.3d 1306 (Fed. Cir. 2011)

Pre-Todd Rule: Unsatisfactory performance evaluations not appealable.

Post-Todd contractor may appeal UNSAT because it is a claim “relating to the performance under the contract.”

To obtain judicial review, must comply with CDA claim certification requirements.

59

Page 60: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Field overhead

Can recover as percentage adder to direct costs, or as extended, time-related cost.

Not both, and only consistent with general treatment.

This generally means go with percentage markup.

Recovering Costs from the Government

60

Page 61: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Unabsorbed home office overhead – Eichleay Formula

So many restrictions that generally not worth the trouble any longer

Among other things, requires essentially complete standby situation, and showing impracticable to take on replacement work

Recovering Costs from the Government

61

Page 62: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

False Statements Act, 18 U.S.C. 1001

False Claims Act, 3729 (a)(1) and (a)(2)

(a)(1) imposes contractor liability for knowingly presenting, or causing to be presented, false claims

(a)(2) imposes contractor liability knowingly using false records or statements to obtain payment for false claims.

Numerous Other Fraud/Falsification Statutes & Penalties

62

Page 63: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

MAIN ELEMENTS:

A claim for payment submitted to the Government

Falsity (claim itself or records supporting)

Knowing conduct

63

Page 64: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

CLAIMS:

Requests for progress payments

Request for final payment

Requests for Equitable Adjustments and Claims

Statements Regarding the Quality of the Work

64

Page 65: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

FALSITY:

Does the Contractor’s Conduct Comport With Its Contractual, Regulatory, and Statutory Obligations Invoice misrepresenting quantity installed

Invoice seeking payment for non-conforming work

False certification of payment of Davis Bacon Act wages– Payment and/or proper classification of workers

REA’s with factual misrepresentations.

65

Page 66: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

Knowing Conduct:

Did Contractor have: actual knowledge of the falsity,

deliberately ignore the truth or falsity of the information, or

act in reckless disregard of the truth or falsity of the information

Did the Government have prior knowledge of the facts allegedly constituting a false claim?

66

Page 67: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

OTHER EXAMPLES:

False certifications of compliance with the contract requirements Representations of timely payment to

subcontractors

Billing amounts not intending to pay subs

Seeking or obtaining payment for work the Contractor knows does not conform to the contract requirements

Inflated quantities in an invoice

67

Page 68: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

False Claims

Daewoo v. United States

Forfeiture of affirmative claim due to fraud

$65 M claim became $50 M adverse judgment

Affirmed on appeal

Numerous mistakes -- Unclear consequences

68

Page 69: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Ethics/Compliance

BASIC ELEMENTS: Written code of business ethics and code of conduct

Internal audit of company policies, procedures and controls

Mechanism for anonymous reporting of violations

Compliance/ethics education program for employees

Enforce disciplinary actions for violations

Cooperation with government investigations

69

Page 70: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Mandatory Disclosure Rule (FAR 52.203-13)

• Contractor shall timely disclose in writing to OIG and CO, when credible evidence that the Contractor has:• Committed a violation of Federal criminal law (fraud, bribery,

gratuities, conflict of interest);

• Committed a violation of the civil False Claims Act; or

• Obtained a significant overpayment from the Government.

• Duty continues for 3 years following final payment.

• Failure to make required disclosure is grounds for debarment. FAR 3.1003

Ethics/Compliance

70

Page 71: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Ethics and Conduct Requirements

FAR 52.203-13 requires Contractors (except commercial item contracts and small businesses:

Have a written code of ethics and conduct;

Exercise due diligence to prevent and detect criminal conduct

Encourage ethical conduct and promote a culture of ethical compliance

Implement “ongoing business ethics awareness and compliance program”

71

Page 72: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Ethics/Compliance

Procurement Integrity Act and FAR 52.203-14 require Contractors to “exercise due diligence” to ensure that no employee gains an unfair competitive advantage by possessing:

Proprietary information obtained from a government official without permission, or

Source selection information that is not available to all competitors.

In the event of an OCI or PCI, Contractor must disclose to the Government.

72

Page 73: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Ethics/Compliance

Strategy to Mitigate OCI/PCI Risks: Develop a comprehensive plan that includes detection,

mitigation and removal of conflicts of interest. Screen employees and acquisition targets for OCI and

PCI risks and avoid acquiring/hiring them, if possible. Assign a senior ranking individual as compliance officer

for the firm Assess OCI and PCI risks periodically Prepare OCI and PCI disclosures when necessary.

73

Page 74: The Do’s and Don’ts of Government Construction Contracts Joseph C. Kovars, Esq. Ober|Kaler 100 Light Street Baltimore, MD 21202 jckovars@ober.com | 410.347.7343

www.ober.com

Questions?