the bjørnafjorden crossing · replacement within design life. complexity and costs related not...

40
The Bjørnafjorden crossing Floating bridge – Concept development and selection process Øyvind Kongsvik Nedrebø Anette Fjeld Svein Erik Jacobsen

Upload: others

Post on 30-Dec-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

The Bjørnafjorden crossingFloating bridge – Concept development and selection process

Øyvind Kongsvik Nedrebø Anette Fjeld Svein Erik Jacobsen

Page 2: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

E39 Stavanger – BergenNew highway

Stavanger

Bergen

Bjørnafjorden

Page 3: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Floating bridge, rev.: 2012

Subsea rock, Flua: -32 m

Page 4: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

2016:

Page 5: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

2016: NOT OK!

17.03.2017

Page 6: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

1: Moved bridge east at north end (away from Flua)

Old, 2016

New, 2017

Page 7: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

2: Changed from concrete to steel for pontoons

Page 8: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

2017: New floating bridge design

K7

K8

End-anchored floating bridge

Side-anchored floating bridge

Page 9: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

How to reach the required and convincing level clarity regarding which bridge candidate should be taken forward to FEED phase? Run additional conceptual design phase based onthe following:

a) Two teams work in parallel on four alternatives (K11…K14).

b) The two teams to be separated. No exchange of information between the teams are allowed.

c) The results reported to be based on extensive analysis work. The design documentation produced shall cover all major aspectsgoverning for the design.

d) Independant verification work to be carried out by DNV GL in parallel.

A challenging assignment! However, NPRA expectation:The two teams will be capable of reaching the same conclusionregarding which bridge alternative to select for FEED.

28.10.2019

Page 10: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Four alternatives nominated: K11, K12, K13, K14subject to assessment in new concept study phase (Nov. 2018 – Aug. 2019)

K7 →

Alternative K11: Arch-shaped floating bridge supported

only at each end, i.e. equivalent to K7.

Alternative K12: Arch-shaped floating bridge supported at

each end similar to K11, but in addition equipped with a mooring system.

Alternative K13: Straight side-anchored bridge similar to K8.

Alternative K14: Side-anchored bridge similar to K8.

However, straight part of bridge limited to the cable-stayed bridge. Floating bridge part to have curved geometry.

K8 →

Page 11: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

1. The project setup of both teams

2. Proposed base cases from both teams

3. The different selection methods for both teams

4. Insight to one technical challenge; parametric exitation

5. Concluding remarks to our recommendation of K12

CONSULTANTS PART OF THE PRESENTATION

Page 12: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

WORK COLLABORATIONNORCONSULT – OLAV OLSEN

HEYERDAHL ARKITEKTER AS

Page 13: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

PROJECT ORGANISATION

COST AND UNCERTAINTY ANALYSES

K12

K13

K14

K11

PMCOMP. REPR.

E

N

V

L

O

A

D

S

A

N

A

L

Y

S

I

S

D

E

S

I

G

N

G

E

O

M

A

I

N

T

E

N

A

N

C

E

A

R

C

H

I

T

E

C

T

U

R

E

C

O

N

S

T

R

U

C

T

I

O

N

C

O

N

C

E

P

T

G

R

O

U

P

CAD/BIM

OTHER PLANNING

DISCIPLINES

SUPPORT

Page 14: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -
Page 15: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -
Page 16: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

BASE CASES

K11: End-anchored K12: End-anchored with mooring

K13: Side-anchored K14: Side-anchored without

expansion joint

Page 17: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Base cases

Page 18: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

QUANTITATIVE CONCEPT RANKING

COST ROBUSTNESS SUSTAINABILITY

+ AESTETHICS: Weighted value of monumental buildingadditional cost (1 billion)

Page 19: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

CONCEPT DEVELOPMENT AND SELECTIONCOST MODEL

> Cost model connected to the concept definition model

> Bottom-up cost estimatecovering approx. 90% ofconstruction cost

> Consistant across thedifferent concepts

> Tool for working with themost important costelements

> Shows if proposed conceptalterations actually reducescosts and/or uncertainty

Page 20: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

CONCEPT DEVELOPMENT AND SELECTIONROBUSTNESS CRITERION

> Over 100 events og risk elements were identified through workshops, interviews and a questionnaire. 21 of these where classified as concept specific and significant.

> Probability and consequence was estimated in a separate risk workshop (2 rounds) and the expected value of the risk element is calculated.

> Other risk elements (project general) was not evaluated and will be an addition to all concepts.

Page 21: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

CONCEPT DEVELOPMENT AND SELECTIONRISK WORKSHOP INFLUENCE

12%

6%

Ship impact

Consequence cost distribution workshop 1:

Consequence cost distribution workshop 2:

Ship impact

Page 22: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

VISUAL IMPACT

Page 23: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

QUALITATIVE CONCEPT RANKING

K11 K12

Pros: - Known technology, built before (in a smaller scale)

- Simple system, easy to calculate response from loads, ductile behavior

- Known eigenperiods which are difficult to move

- Larger capacity for unknown overloading due to stronger bridge girder

- Installation of complete assembled floating bridge, less work in Bjørnafjorden

- Less maintenance, few “wearing parts”

- Redundant system with double horizontal load-carrying system.

- Largest potential for- and flexibility in designing a robust solution.

- Mooring reduces the response and increases design life compared to K11. Possible to increase design life further with small amount of

additional steel. - Fibre rope mooring gives favorable interaction

with bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases

- Installation of complete assembled floating bridge, less work in Bjørnafjorden, simple mooring hook-up

- Few and manageable anchor locations - No joints and bearings

Cons: - Lack of redundancy - Uncertain wind load as turbulence

spectra are normally not applied to structures with long eigenperiods

- Large, concentrated forces at landfalls

- Requires larger clearance between tower legs

- Mooring needs replacement within design life. Complexity and costs related to this operation not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Limited experience with taut mooring on these water depths

Rank: 2 1

Reason: Most simple Most robust

K13 K14

Pros: - Redundancy in mooring - Fibre rope mooring gives favorable

interaction with bridge girder. - Linear behavior of mooring without risk

of successive mooring line failure for known load cases.

- Simplest production. - Potential for moving landfall north onto

the bank outside Gulholmane and obtaining a shorter bridge.

- Redundancy in mooring - Fibre rope mooring gives favorable interaction with

bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases.

- No joints and bearings

Cons: - Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Many and some unfavorable anchor positions.

- Limited experience with taut mooring on these water depths

- Great number of work operations performed on the fjord.

- Monotonic driving experience - Maintenance of joints and bearings - Noise from joints

- Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides - Some unfavorable anchor positions. - Limited experience with taut mooring on these

water depths - Great number of work operations performed on the

fjord.

Rank: 4 3

Reason: Most complex Compromise

K11 K12

Pros: - Known technology, built before (in a smaller scale)

- Simple system, easy to calculate response from loads, ductile behavior

- Known eigenperiods which are difficult to move

- Larger capacity for unknown overloading due to stronger bridge girder

- Installation of complete assembled floating bridge, less work in Bjørnafjorden

- Less maintenance, few “wearing parts”

- Redundant system with double horizontal load-carrying system.

- Largest potential for- and flexibility in designing a robust solution.

- Mooring reduces the response and increases design life compared to K11. Possible to increase design life further with small amount of

additional steel. - Fibre rope mooring gives favorable interaction

with bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases

- Installation of complete assembled floating bridge, less work in Bjørnafjorden, simple mooring hook-up

- Few and manageable anchor locations - No joints and bearings

Cons: - Lack of redundancy - Uncertain wind load as turbulence

spectra are normally not applied to structures with long eigenperiods

- Large, concentrated forces at landfalls

- Requires larger clearance between tower legs

- Mooring needs replacement within design life. Complexity and costs related to this operation not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Limited experience with taut mooring on these water depths

Rank: 2 1

Reason: Most simple Most robust

K13 K14

Pros: - Redundancy in mooring - Fibre rope mooring gives favorable

interaction with bridge girder. - Linear behavior of mooring without risk

of successive mooring line failure for known load cases.

- Simplest production. - Potential for moving landfall north onto

the bank outside Gulholmane and obtaining a shorter bridge.

- Redundancy in mooring - Fibre rope mooring gives favorable interaction with

bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases.

- No joints and bearings

Cons: - Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Many and some unfavorable anchor positions.

- Limited experience with taut mooring on these water depths

- Great number of work operations performed on the fjord.

- Monotonic driving experience - Maintenance of joints and bearings - Noise from joints

- Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides - Some unfavorable anchor positions. - Limited experience with taut mooring on these

water depths - Great number of work operations performed on the

fjord.

Rank: 4 3

Reason: Most complex Compromise

K11 K12

Pros: - Known technology, built before (in a smaller scale)

- Simple system, easy to calculate response from loads, ductile behavior

- Known eigenperiods which are difficult to move

- Larger capacity for unknown overloading due to stronger bridge girder

- Installation of complete assembled floating bridge, less work in Bjørnafjorden

- Less maintenance, few “wearing parts”

- Redundant system with double horizontal load-carrying system.

- Largest potential for- and flexibility in designing a robust solution.

- Mooring reduces the response and increases design life compared to K11. Possible to increase design life further with small amount of

additional steel. - Fibre rope mooring gives favorable interaction

with bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases

- Installation of complete assembled floating bridge, less work in Bjørnafjorden, simple mooring hook-up

- Few and manageable anchor locations - No joints and bearings

Cons: - Lack of redundancy - Uncertain wind load as turbulence

spectra are normally not applied to structures with long eigenperiods

- Large, concentrated forces at landfalls

- Requires larger clearance between tower legs

- Mooring needs replacement within design life. Complexity and costs related to this operation not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Limited experience with taut mooring on these water depths

Rank: 2 1

Reason: Most simple Most robust

K13 K14

Pros: - Redundancy in mooring - Fibre rope mooring gives favorable

interaction with bridge girder. - Linear behavior of mooring without risk

of successive mooring line failure for known load cases.

- Simplest production. - Potential for moving landfall north onto

the bank outside Gulholmane and obtaining a shorter bridge.

- Redundancy in mooring - Fibre rope mooring gives favorable interaction with

bridge girder. - Linear behavior of mooring without risk of

successive mooring line failure for known load cases.

- No joints and bearings

Cons: - Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides

- Many and some unfavorable anchor positions.

- Limited experience with taut mooring on these water depths

- Great number of work operations performed on the fjord.

- Monotonic driving experience - Maintenance of joints and bearings - Noise from joints

- Mooring, part of main load-carrying system, needs replacement within design life. Complexity and costs related not sufficiently reflected.

- Challenging soil conditions, risk of underwater slides - Some unfavorable anchor positions. - Limited experience with taut mooring on these

water depths - Great number of work operations performed on the

fjord.

Rank: 4 3

Reason: Most complex Compromise

Page 24: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

• Milestones for development and selection- Initial phase: Establish base cases through:

▪ Experience form earlier phases▪ Initial analyses▪ Sensitivities▪ Possible showstoppers▪ Aestetic evaluation

- Development phase▪ Extensive analyses and design, including sensitivity analyses, ship impact, parametric excitation, comfort criterias, hydrodynamic effects etc.▪ Risk analyses▪ Cost estimates based on quantities

- Conclusive phase▪ Supplementary analyses▪ Conclusion on parametric excitation▪ Optimization▪ Risk reduction through continous risk analyses and risk mitigation▪ Updated cost estimated incl. Uncertainties▪ Aesthetics▪ Robustness

Conclusion: K12 is the preferred solution

Concept development and selection

Page 25: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Concept development and selectionAnalyses and special studies

Page 26: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Concept development and selectionAesthetics - Visual Impact

• Horizontal alignment• Landscape

• Vertical alignment• Pontoon, column, bridge deck, tower and cable stay shape/configuration• Walkway• Landscaping

Page 27: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Concept development and selectionCost estimates

Page 28: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Concept development and selectionRisk Analyses

Risk analyses are carried out as a work tool to:• Choose optimal bridge concept- Identification of risk elements- Comparisons of risk elements

between concepts- Comparisons of risk elements

to others• Outline areas/challenges for

further evaluation within theproject (mitigations)- Parametric excitation- Placing of anchors- Ship collosion

Page 29: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Concept development and selectionRanking –K12 superior tothe other alternatives

Page 30: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

ChallangesParametric excitation and response

Page 31: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

ChallangesParametric excitation and response

Page 32: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

ChallangesParametric excitation and response

Page 33: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

OON PROPOSAL: CONSERVATIVE DESIGN APPROACH

Page 34: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

OON PROPOSAL: CONSERVATIVE DESIGN APPROACH

Page 35: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

PARAMETRIC EXCITATIONCALCULATED RESPONSE

CALCULATED RESPONSE HAS A RETURN PERIOD OF APPROX. 700 MILL. YEARS

Page 36: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

© Dr.techn.Olav Olsen AS

- End-anchored bridge; known structure without joints or bearings

- Aestethically the best alternative with good horizontal and vertical alignment

- Mooring reduces response and increases robustness and capacity for skew loading

- Quantities, a key cost driver, have «converged», but optimizations are still possible

- Significant development in construction and installation methods

CONCLUSION: K12 IS A ROBUST AND COST-EFFECTIVE SOLUTION

Page 37: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

© Dr.techn.Olav Olsen AS

- Two completely independent assessments recommended the same floating bridge alternative, and DNV GL supports the conclusion.

- The recommendations are made on detailed information about the site conditions, given in the design basis prepared by NPRA.

- Uncertainties from previous phases, like parametric resonnance, has been adressed and handled in this project

CONCLUSION: K12 IS A ROBUST AND COST-EFFECTIVE SOLUTION

The NPRA has a solid basis for proceeding with the project

Page 38: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Summary on costs!Concepts considered for Bjørnafjorden

Illustration: Vianova/Baezeni/NPRA

Concept assessed 2015 - 2016: 42,8

Concept assessed 2015 - 2017: 22,9

2012: 14,5

2019: 15,8

Project cost: billions NOK (2019-kroner, incl. VAT)

Concept assessed 2015 - 2016: 27,6

Page 39: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Extra gain! ☺This lagoon saved from NPRA highway E39 ambition!

04.07.2017

Page 40: The Bjørnafjorden crossing · replacement within design life. Complexity and costs related not sufficiently reflected. - Challenging soil conditions, risk of underwater slides -

Thank you!