the alice water cooling systems
DESCRIPTION
The ALICE water cooling systems. A.Tauro. Outline. ALICE cooling organization Overview of the ALICE water cooling systems Main problems found during the commissioning of the detectors TPC ITS Solutions adopted case by case Conclusions. ALICE cooling organization. Cooling coordinator: - PowerPoint PPT PresentationTRANSCRIPT
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
1
The ALICE water cooling systems
A.TauroA.Tauro
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
2
Outline
• ALICE cooling organization• Overview of the ALICE water cooling systems• Main problems found during the commissioning of the
detectors– TPC– ITS
• Solutions adopted case by case• Conclusions
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
3
ALICE cooling organizationALICE cooling organization
CoolingcoordinatorCooling
coordinator
Detector exptsDetector expts
Detector expts
TCTC
TS-CV/DC
• Cooling coordinator:– Provides the interface between the
cooling experts/TS-CV/external companies and the technical coordination (TC)
– Responsible for the installation and testing of cooling services
– Follows the commissioning stages
• Sub-detector cooling experts:– Provide technical specifications
– Perform prototyping and/or mock-up tests
– Commission the final system
• TS-CV/DC:– In charge of the fabrication, installation,
operation and commissioning of the cooling plants
Cooling plantCooling plantCooling plant
Cooling servicesCooling servicesCooling services
CERN techs or ext comp
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
4
Updates and reviewsUpdates and reviews
• Regular status updates:– Installation -> weekly planning meetings
– Commissioning -> daily commissioning meetings
– Technical board and technical forum
• Cooling reviews dedicated to each sub-detector aiming at discussing:– Detector protection and safety (interlocks, HW protections, relief valves,
…)
– Cooling performances
– In case of problems -> engineering change requests (re-routing of lines, cooling plant modifications)
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
5
Example: ALICE TB June ‘08Example: ALICE TB June ‘08
PLANT DCS INTERLOCK REMARKS
TPC FEE Some faulty heaters → reparation in June
OKP → Plant
Plant → LV (to be tested)
Cavitation in some lines
TPC RRTank release valve
must be replaced
Need to integrate conductivity measurement
P → TPC FEE plant (to be checked)
Low efficiency
FMD OK OK (same as TPC)P → Plant
Plant → LV, HV-
TOF
Need calibration of chilled water valve
Tank level transmitter replacement
OKPlant → LV (to be tested)
Overpressure is not an issue
PHOS FEE OK NOP → DSS → Plant (will be installed in June)
Detector T=30°C
No safety devices
PHOS CRY OK OK NOImprove line insulation
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
6
Example: ALICE TF Oct ‘07Example: ALICE TF Oct ‘07
Pressure test Water cleaning Remarks
TRD Jan 07: 10 SRs Sep 07: 6 SRsUpper sectors after TPC to IP
HMPID Feb 07 Filter cleaned
TOF Aug 07: 4/6 crates, 1/6 FEE Fittings/pipes required
TPCJan-Aug 07: C side,
MNF
Jun 07: A sideOnly MNF missing
Pressure test/cleaning was repeated after rerouting
PHOS-EMCAL
Aug 07Pressure test for PHOS crystal pipe not done
SDD+SSD Apr 07Jun 07
MNF: Sep-Oct 07Fine mesh filter (50um)
SPD Apr 07 Jun 07 -
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
7
The ALICE experiment
forward muonspectrometer
Central detectors
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
8
The L3 magnet in 2006…
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
9
ALICE front viewALICE front view
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
10
…and how it looks like now
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
11
Location of the cooling plants Location of the cooling plants in the UX25 cavernin the UX25 cavern
TOF, EMC, CPV, PHOS
TRD
TPCHMPID
SSD & SDDSPD
PHOS
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
12
Services through the L3 door
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
13
Installation of pipes in the Installation of pipes in the ALICE cavernALICE cavern
Installation: 1 and ½ year, 7 teams, ~20’000 mt of pipes (40% stainless steel), ~3700 press fittings
Test: about 500 over-pressure tests (~3’400hrs in total)
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
14
ALICE cooling plantsALICE cooling plants
Cooling plants:• 7 units (5 water, 2 evaporative). Most of them are shared between detectors• 5 produced by TS/CV-DC, 2 outsourced (Italy, Russia)• PHOS is the only -25°C, all the others work at +16,+18°C• Leakless operation• First unit (SPD) delivered beginning 2006, last one (PHOS) beginning 2008• Total value of cooling plants >1MCHF
0 50 100 150
Power removed[kW]
Flow[m3/h]
SPD
HMPID
SSD, SDD
TPC, FEEC, Res. Rod
TRD, TPC Screen
TOF, EMC, PHOS, CPV
C4F10 water
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
15
ΔP return
ΔP supply
ΔPdetector
Ppump
Ptank
h
Pin < PatmPout
Jose Direito TS/CV/DC, 13.05.2008
The leakless operationThe leakless operation
It works only if Pin < Patm
Not all the loop is under-pressure!!!
ΔPdetector vs flow must be knownΔPreturn should be calculated
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
16
The TPC cooling
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
17
Temperature uniformity across Temperature uniformity across the TPC volumethe TPC volume
• Ne/CO2 is a ‘cold’ gas, with a steep dependence of drift velocity on temperature
• Uniformity of the temperature field must be extremely good (ΔT ≤ 0.1 K)
• 18x2 trapezoidal read-out chambers each one consuming 720W
• Complex system of heat screens and cooling circuits
• Heat screens:– outer radius toward the TRD– inner radius shielding from the ITS
services– readout chamber bodies shielding
from the FEE heat dissipation– FEE towards the outside
• Cooling circuits:– resistive potential dividers– front-end electronics
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
18
Front end electronics cooling Front end electronics cooling pipespipes
• 0.5 mm copper tubes connected to 3 mm Si-tubes, without clamp or bracket
• Connection tested to withstand > 2 bar overpressure. But…
… it could happen that the pipes are not properly plugged after an intervention for which they have to be disconnected
-> what happen if one hose become disconnected ?
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
19
Test with dummy sectorTest with dummy sector• Test with dummy sector done in 2007 in the UX25 cavern• Demonstrates that if a Si-pipe bunches-off there is a leak inside the chamber• The plant takes 40s from the leak before stopping the water circulation• -> P sensors installed on each chamber input line• Continuous monitoring of pressures to verify underpressure operation• Exceeding the threshold would immediately trigger an ALARM and stop circulation
40 s
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
20
““Cavitation” problemCavitation” problem• For some sectors it has been observed ad
audible noise coming from the pipes• These sectors exhibited a Pout < 50 mbar• “Cavitation”, potentially dangerous
condition. Increase of the flow resistance due to bi-phase liquid
Pthreshold
• Increasing the tank pressure solves the problem but then makes the startup impossible
• Startup: need to kick up the pressure in order to get rid of the air in the pipe
• Solution: switch from startup tank pressure (e.g. 350 mbar) to running mode (e.g. 500 mbar)
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
21
Routing of cooling lines
pressure sensor threshold
Siphons in linesSiphons in lines• In some sectors there was no flow• The reason was the presence of
important siphons in the lines• These lines have been re-routed
sectors with new routing
• After re-routing of these lines the problem was solved
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
22
New lines installed
Re-routing of TPC linesRe-routing of TPC lines
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
23
ROC temperaturesROC temperatures
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
24
Skirt temperaturesSkirt temperatures
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
25
The laser system is used for precise position inter-calibration for the readout chambers and allows online monitoring of temperature and space-charge distortions, both of the order of a few mm
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
26
The ITS cooling
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
27
Layout of the ITSLayout of the ITS
• Only SPD uses C4F10 coolant
– low material budget, long-term stability against corrosion, chemical compatibility, minimal temperature gradients, cooling duct temperature above the dew point
• SDD and SSD share the same (water) cooling plant
• ITS uses stainless steel pipes
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
28
SPD commissioningSPD commissioning• Extensive (2 years) pre-commissioning
in the lab– In normal operation, if a sudden failure of the
cooling were to occur, the temperature at the module would increase at a rate of 1 °C/s
– Continuous monitoring and a fast, reliable safety interlock on each module are therefore mandatory
• DCS and interlocks also tested in the lab
• Problems encountered in real installation
– Low or zero flow in some loops. Due to different pipe layout with respect to lab
– Still some liquid back into compressor. Heaters added
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
29
The SSD cooling
Two thin (40 μm wall thickness) phynox tubes
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
30
The SSD FEE chips
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
31
50um filter150um filter
Cleaning of the lines. June ‘07Cleaning of the lines. June ‘07• In June 2007, before connecting the ITS to the cooling plant the pipes were cleaned by
circulating water• Found metal chips, dust particles which could have damaged the detector• Water circulation continued for several days• Filters of different mesh replaced at every time• -> lesson learnt: use extreme care during pipe installation. Plug them before connecting the
detector
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
32
Water leak. July ‘07Water leak. July ‘07• In July 2007, after 2 days of run with the nominal flow, a water leak was detected inside the
ITS barrel (probably due to an open in the SDD region)• Mylar foil acted as drain, water level not high enough to reach ladders• In order to be leak proof, it was then decided to allow to work only in sub-atmospheric region
inside the detector• As for the TPC, pressure sensors were introduced in order to read the pressures at the
detector
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
33
Problems and solutionsProblems and solutions
• When lowering the tank pressure to be underpressure at the detector, the “cavitation” problem appeared– Solution: 1) re-routing of some lines, 2) changing the inner pipe diameter
• Given the different routing of the lines, the flows amongst the loops were not equalized– Solution (SDD): upgrade the plant with flowmeters and pressure regulators– Solution (SSD): install balancing valves on input-output lines
• SSD and SDD have different flows and different ΔPdetector -> each one found an optimum value for Ptank and Ppump– Solution: install back-pressure regulators (SSD) + input pressure regulator (SSD) to decouple as much as possible the two systems
• The loops were difficult to drain– Solution: install bypass into cooling plant and manual valves in each line
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
34
Add 3 lines 16/18 till here
Add 2 lines 16/18 till here
Add 5 lines 16/18
Add 3+2 lines 16/18
Add 5 lines 16/18
The new lines
Cost: 50KCHF
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
35
N2 and Compressed air supply
LD
VEA-4
QR-7
N2 @ 6 bar
Flow
can be a
djuste
d a
t the flo
wm
eter
PS3
VEA-5
QP - 1
VEA-1
Boitier Orange
PS2
SSD supply manifold
SDD supply manifold
SSD 4-ladder groups:8 outlets x 2 x 0.96L/min
= 15.36 L/min
SSD 5-ladder groups:8 outlets x 2 x 1.2L/min
= 19.2 L/min
Chilled water
HT
R -
S28
500
W
HT
R -
S21
TT
S21
VP- S28i
500
W
TT
S28H
TR
-S
18
500
W
HT
R -
S11
TT
S11
VP- S18i
500
W
TT
S18
VP- S21i
QR-1
RWA
VMA-S
MSSD exchangerSDD exchanger
FOA-1
SDD 2-ladder groups:8 outlets @ (2 x 0.6L/min) = 9.6L/min
250
W
250
W
HT
R -
D18
HT
R -
D11
TT
D11
VP- D18i
TT
D18
VP- D11i
SDD end-ladders of 2-ladder groups:
8 outlets @ (2 x 1.2L/min) = 19.2 L/min
500
W
500
W
HT
R -
D28
HT
R -
D21
TT
D21
VP- D28i
TT
D28
VP- D21i
SDD 4-ladder groups:5 outlets @ (2 x 1.2L/min) = 12L/min
500
W
500
W
HT
R -
D38
HT
R -
D31
TT
D31
VP- D38i
TT
D38
VP- D31i
SDD end-ladders of 4-ladder groups:
5 outlets @ (2 x 2.4L/min) = 24L/min
100
0 W
100
0 W
HT
R -
D48
HT
R -
D41
TT
D41
VP- D48i
TT
D48
VP- D41i
CA- 1
LW1
TTD
183.02.01
CERN/TS/CV/DC
LHC - Fluids - EXPERIMENTAL HALL
SSD+SDD cooling plant : P&I diagram (with upgrades) Version 5
M. Santos2008-Jan-10
LHCF222???
DM
QR - 5QR - 3VP- 1
OT1
PP
QR - 2
TT1
PT 2
FT1
CT1
VTA - 1QR - 4
UV
UV
PR - S2PR - S1
VTA - D1 VTA - D2 VTA - D3 VTA - D4
8 + 8 = 16 returns from SSD
SSD return manifolds
VP
-S
21r
VP
-S
11r
VP
-D
3141
r
VP
-D
1121
r
SDD return manifolds
8 + 5= 13 returns from SDD
QR-S1 V-D1 V-D2
VMA-DM
TTWin
PI 2
VR- 1 PT1
PI1
PPV-1VEA-2
PPV-2VEA-3
DG
PS1
LT
N2 for tank flushing
N2 for membrane
70L/h tap water
VP- 2
PPV-3 VP- 3
PI3
PT3
QP - 3FOA-2V-1
VP- S11i
FT
D1
FT
D2
FT
D3
FT
D4
FT
S2
FT
S1
FT
D11A
FT
D11C
FT
D18A
FT
D18CFT
D21A
FT
D21C
FT
D28A
FT
D28C
FT
D31A
FT
D31C
FT
D38A
FT
D38C
FT
D41A
FT
D41C
FT
D48A
FT
D48C
PR
-D11
A
PR
-D11C
PR
-D18
A
PR
-D18C
PR
-D21
A
PR
-D21C
PR
-D28
A
PR
-D28
C
PR
-D31
A
PR
-D31C
PR
-D38
A
PR
-D38C
PR
-D41
A
PR
-D41C
PR
-D48
A
PR
-D48
C
VP- D3141r
“D” concerne SDD “r” concerne
le retour
Nomenclature des vannes retour
4 chiffres: composition des 2 vannes
d’injection (i) correpondantes a ce retour:VP-D31i et VP-D41i
QR
–S
11iA
QR
–S
11iC
QR
–S
18iA
QR
–S
18iC
QR
–S
21iA
QR
–S
21iC
QR
–S
28iA
QR
–S
28i
C
QR
-D
1121r
A
QR
-D
1121
rC
QR
-D
314
1rA
QR
-D
3141r
C
QR
–S
11rA
QR
–S
11r
C
QR
–S
21rA
QR
–S
21r
C
QR-S2
PIS1
PIS2
PPV-4
TTS
Corrosion monitoringQR - CORRin
QR - CORRout
QR - DrainSDD
QR - DrainSSD
VEA-6
The SSD-SDD plant upgrade
Cost of the upgrade: 150KCHF
By-passes for Circuit Draining
Two actuated valves on the common returns with remote positioning control to decouple return pressure from the SDD
Pressure regulator for the SSD
Manual valves on all SSD returns and supplies
5 enlarged return valves+ forks for the 18mm OD SDD pipes
Pressure regulators for SDDFlowmeters for SDD
30/10/2008 Engineering Forum on Cooling for the LHC Detectors
36
Conclusions
• The ALICE cooling organization has been described. The cooling coordinator acting as a reference for all the cooling matters
• The leakless operation is effective only if Pin<Patm and it doesn’t guarantee that there are no leaks
• P sensors are fundamental in leakless systems. They should be part of the design of the cooling system
• It is fundamental to measure ΔPdetector vs flow and to have a good estimate of ΔPreturn. Piping inside the detector must be robust
• An optimized routing of the lines is crucial to minimize the impedance and to avoid siphons. Max care must be taken in the cleaning procedures
• Test test test is always the key