MEGAPROJECT Case Study
Basic Project Information
Case compiled by: ....Jonas Wennström...........................Contact details: [email protected]............................
Project Title Norra länken (the Northern Link)
Location Northern part of Stockholm cite centre, Sweden
Purpose The purpose of the project is to create a new link for the E20 motorway from the E4 motorway “Essingeleden” in north west to Värtan in the north east. This will improve the accessibility for Lidingö and open up for new urban developments in “Norra Djurgårdsstaden”. Norra Länken is also a prerequisite for the development of “Norra Stationsområdet” in the western parts. When finished, it will relieve the traffic load in the city centre [ME].
Scope The project includes the original plan of “Norra länken” with a connection only between Norrtull-Värtan but also the extension of the project to include the overdecking for “Norra Stationsområdet”. The project consists of rock and concrete tunnels and traffic facilities in connection to the tunnels.
Contractual Framework Mixed between design, design-build and build contracts. In total it is planned to consist of 62 contracts [STATN] [STAE].
Relevant Physical Dimensions
The length of the main tunnels will be 5 km of which 1 km was constructed twenty years ago. In total it will be11 km of road tunnels, of which 9 km is rock tunnels and 2 is concrete tunnels.
SECTION 1 - BASIC PROJECT INFORMATION
TEST VERSIONONLY
Stakeholder Category Case-Study Comments (e.g. maturity, previous experiences of stakeholders, skills, influence on project)
Internal
Supply-Side Client Swedish Transport Administration (STA)Financiers Värtan - Norrtull
75 %: the Swedish government via the STA.25 %: Stockholm Municipality.
Norrtull – Tomteboda80 %: Stockholm Municipality. 20 %: STA
Sponsors EU funding TEN-T subsidy: €56,15 millionClient’s Customers The public and the road usersClient’s Owners Swedish state.Other internal supply-side categories ( please specify)
Category Case-Study
Demand Side) Principal Contractor STA is responsible for procurement of design, construction and operation contracts [STAFAQ]
First Tier Contractors Design: Sweco, Grontmij, WSP, Bravida Mixed between design, design-build and build contracts
Build: Svevia, Hochtief, Bilfinger Berger, Skanska, Züblin-Pihl, PEAB, Veidekke and OdenIn total, the project is planned to consist of 44+18=62 contracts
Second Tier Consultants
Not known.
Professional Services ProvidersOther internal supply-side categories ( please specify)
Category Case-Study
MEGAPROJECT Stakeholder Identification (Internal)
SECTION 2 - PROJECT STAKEHOLDERS
TEST VERSIONONLY
Stakeholder Category Case-Study Comments (e.g. maturity, previous experiences of stakeholders, skills, influence on project)
External
Public Regulatory Agencies • Supreme Administrative Court of Sweden• County Administrative Boards of Sweden• Miljödomstolen
Local Government Stockholm Municipality and Solna MunicipalityNational Government Swedish GovernmentOther internal supply-side categories ( please specify)
Category Case-study
Private Local residents Albano, Vasastan, Östermalm,Roslagstull, Gärdet, HjorthagenLocal Landowners N/AEnvironmentalists “Förbundet för Ekoparken”ConservationistsArchaeologistsOther External Private stakeholders (please specify)
Category Case studyKTH, Värtan harbour
MEGAPROJECT Stakeholder Identification (External)
SECTION 2 - PROJECT STAKEHOLDERS
TEST VERSIONONLY
SECTION 2 -PROJECT STAKEHOLDERS
MEGAPROJECT Stakeholder Relationship Maps
Key: - Project Actor
- Project Relationship
?
Description of relationship
STA (client)
Ministry of
Finance
Swedish parliame
nt
Swedish governm
ent
Finances 75 %Finances 25%
Stockholm
Municipality
Contracts with
WSP
Design
GrontmijRamböll
Build/”Design Build”
Svevia HochtiefSkanskaPEAB Veidekke
Bilfinger-Berger
Züblin-Pihl
Road users
Subcontractors
Subconsultants
MEEC
Supreme
Administrative
Court of Sweden
County Administ
rative Boards
of Sweden
Bravida
62 contracts
Public
Public participationEnvironmentalis
ts
Operation
TEST VERSIONONLY
SECTION 2 - PROJECT STAKEHOLDERS
MEGAPROJECT External Stakeholder Attitude Analysis
External Stakeholder External Stakeholder’s Attitude to this Project
External Stakeholder’s Influence on project
Impact of Project on External Stakeholder
“Förbundet för Ekoparken”Negative
Concerned of the urban national park, Nationalstadsparken. Appealed against construction in 1997 and 2002. Won in court 1997 which halted the construction ten years and changed construction method.
Hagastaden (association consisting of municipalities institutions)
Positive Development of “Norra Stationsområdet”
Opens the possibility to build “Norra stationsområdet” and expansion of Karolinska Institutet
Svenska vägföreningen (Road association)
Positive
TEST VERSIONONLY
MEGAPROJECT Project ManagementProject Organisation
Client Project Team Size & Structure
Contractor Project Team Size and Structure
800 people at maximum [STAA]
Sub-Contractor Project Team Involvement
Project Tools and TechniquesPlease √ if present, x if absent , leave blank if unknown
Life-Cycle Costing Approaches □
Stakeholder Involvement □Y[VV05]
Building Information Modelling (BIM) □Y[BIM]
Project Management Software □Y
Relationship Management Tools □
Project Knowledge Management Tools □
Lessons Learnt Transfers □
Team Building Tools □
Competency framework □Other Tools and Techniques or More InformationFor the design procurements , requirement of all drawings should be presented in 3D based on experiences from the Southern Link project [3DP] .
SECTION 3 - PROJECT MANAGEMENT
TEST VERSIONONLY
Risk Management Processes Present (describe below) □Not Present □ No Information □
HR Management Processes Present (describe below) □Not Present □ No Information □
Procurement Management Processes Present (describe below) □Not Present □ No Information □
Integration Management Processes Present (describe below) □Not Present □ No Information □
Scope Management Processes Present (describe below) □Not Present □ No Information □
Time Management Processes Present (describe below) □Not Present □ No Information □
Cost Management Processes Present (describe below) □Not Present □ No Information □
Quality management Processes Present (describe below) □Not Present □ No Information □
Communications Management Processes
Present (describe below) □Not Present □ No Information □
Project Processes
SECTION 3 - PROJECT MANAGEMENT
TEST VERSIONONLY
MEGAPROJECT Project Performance
Aspects of Performance Concerned with Doing the Project Right
Original Targets and changes to targets
Actual Achievements Against Targets
Performance relating to time If only the project in its current form is considered, the tunnels between Norrtull and Värtan should be open for traffic in 2015 [STAFAQ]. Norrtull to Tomteboda is planned for 2015 and 2017. Railway tunnel for Värtabanan in 2019 [STATN]. Procurements of all contracts have been planned in[VV05] .
In current form, no major construction delays have been reported. Some delays have been reported in the early stages. However, in 2010 was the project on, or ahead of schedule [IN10] . A breakthrough of finishing a continuous tunnel was accomplished in November 2011 [IN]. Procurement plans and written contracts have been mostly followed [STAE].
Performance relating to cost Original stretch between Norrtull and Värtan: 11 billion SEK [STAA]“Norra stationsområdet “ added in 2010: 5,6 billion SEK [STATN]
To be done
Performance related to
achieving specificationOverdecking of the E4 motorway for the development of “Norra stationsområdet” was added in 2010. Included was also widening of roads to add extra capacity and a tunnel for Värtabanan.
Contracts written in 2010. Construction has begun.
SECTION 4 - PROJECT PERFORMANCE
TEST VERSIONONLY
Aspects of Performance Concerned with Doing the Right Project
Stakeholder or Stakeholder Grouping
Original Aims of Project Involvement and Changes to these
Aims
Achievement of these Aims
SECTION 4 - PROJECT PERFORMANCE
TEST VERSIONONLY
MEGAPROJECT Project Environment
Legal and Regulatory Environment
Legal and Regulatory Project Environment (regionally, nationally and Europe wide)
In Sweden are road constructions regulated by the “Road Act”. This law specify , for example, how the formal planning process should be accomplished, land owner rights, right of way and responsibilities [RA].Plan & bygglagen regulates planning and zoning of land developments for municipalities.The Environmental Code include laws regarding planning, EIA’s, public participation.Included are also laws regulating national parks, which in this case the tunnel between Norrtull and Värtan will mostly go under. [EC]
Specific Legal and Regulatory events impacting on the project
In 2009, the government gave acceptance to construct the concrete tunnel near Bellevue park with a more traditional method. This by changing a paragraph in the Environmental Code for allowance of temporary works in national parks. This was estimated to reduce the cost with around 1 billion SEK [BV09].
Political Environment
Political Project Environment
Specific Political Events impacting on the project
SECTION 5 - PROJECT ENVIRONMENT
TEST VERSIONONLY
MEGAPROJECT Project Environment
Economic Environment
Economic Project Environment
2007 -2008 – Economic boom, difficulties to find labour2008-2009 global recession
Specific Economic Events impacting on the project
SECTION 5 - PROJECT ENVIRONMENT
TEST VERSIONONLY
Eve
nts
in
pro
ject
Eve
nts
in
e
nvi
ron
me
nt
MEGAPROJECT Project Key Events and Activities TimelineTIME
SECTION 6 - PROJECT TIMELINE
60’s
Ring road discussions
1991
Completion of Karlberg -
Norrtull
Aug 1996
Start of
rock tunnel construction
Project halt
Jan 1997
2007
Events before current development
2008 2009 2010
Current development
20062005
Design & Procure.
NL11 : Skanska
2011
NL12 : PEAB
NL22 : BBNL31 : Züblin
NL33 : Veidekke
NL34 : Veidekke
NL35 : Hochtief & Oden
Political acceptance
NL51 : Hochtief & Oden
NL41 : PEAB
NL62 : Veidekke
NL52 : Skanska
N66 : TE AB
N67 : Bravida
N68 : Bravida
N69 : Läckeby
N72 : Bravida
Working tunnels
Appeal against project rejected, full
project legally accepted
Change in the ”Environmental Code” regarding temporary
works in National Parks
Extension of project with”Norra stationsområdet”
Breakthrough in tunnel boring
Contracting
Hard to find labour [REF?] Economic recession
TEST VERSIONONLY
References•[STAFAQ] Trafikverket: Frågor och svar. http://www.trafikverket.se/Privat/Projekt/Stockholm/E20-norra-lanken/Fragor-och-svar/•[ME] Genomslaget klart - asfalteringen börjar http://www.me.se/Tidning/Branschnytt/20111/Nomvember/Genomslaget-klart---asfalteringen-borjar/•[IN] Genomslag för Norra Länken. Infrastrukturnyheter. http://www.infrastrukturnyheter.se/2011/12/genomslag-i-norra-l-nken•[3D] ”Väg- och vattenbyggaren”. Volume 4. 2006•[BIM] Trafikverket. Stefan Engdahl.•[VV05]. Norrtullsområdet. Vägverket. 2005.•[GA] Startklart för Norra länken, Svenska Dagbladet 6 april 2006•[BV09] Byggare kan börja gräva för Norra länken. 2009. http://www.byggvarlden.se/nyheter/byggprojekt/article87866.ece•[RA] The Road Act SFS 1971:948. http://www.notisum.se/rnp/sls/lag/19710948.htm•[EC] The Environmental Code 1998:808•[STATN] http://www.trafikverket.se/Privat/Projekt/Stockholm/E20-norra-lanken/Delprojekt-i-Norra-lanken/Tomteboda--Karlberg/•[STAE] Entreprenader, tecknade kontrakt. http://www.trafikverket.se/Privat/Projekt/Stockholm/E20-norra-lanken/Om-projektet/Entreprenader-Tecknade-kontrakt/•[STAA] http://www.trafikverket.se/Privat/Projekt/Stockholm/E20-norra-lanken/Om-projektet/•[3DP] 3D-projektering – framtiden i vägbyggnadssektorn? . Rasmus Regnstrand. Master thesis. 2011.•[IN10] Snabbt driv i Norra länken. Infrastrukturnyheter. http://www.infrastrukturnyheter.se/2010/02/snabbt-driv-i-norra-lanken