TERM OF REFERENCE DESIGN FOR LIQUID TERMINAL LUBUK GAUNG REFINERY PLANT 1. Topographic Survey and Investigation of Existing Area a. Survey of Mater Layout Drainage Existing Plant (Flow Direction, channel dimension, bottom drainage elevation) b. Topographic Survey of existing boundary c. Topographic Survey of detailed situation d. Topographic Survey of existing elevation e. Soil Investigation Test (deep boring and sondir). f. Collecting secondary data (wind, rain, tides, etc) g. All related technical data and documentation for [permit process (IMB, etc) h. Cut and Fill recommendation i. Shore Protection recommendation j. Land Improvement recommendation 2. Engineering, Design and Specification (C/M/E) a. Site Plan b. Sectional View c. Overall Design Basis d. Detail section and Drawing e. Outline Technical Specification (M/C/E) f. Schematic Design and arrangements for whole plant 3. Design Development (C/M/E) a. Design (Drawing, detail and Specification) – Architecture Design; layout, sectional view, elevation, layout of switch board, motor points, cable support system, lighting scheme, typical layout detail and finishing scheme. b. Mechanical, Electrical & Civil Design (Specification and Calculation), All mechanical and electrical Design Outside Battery Limit (OSBL) Connection to Generator, Tank Farm to Main Office

Upload: kerehore007

Post on 14-Dec-2015

215 views

Category:

Documents


2 download

DESCRIPTION

Sample of Term Reference

TRANSCRIPT

Page 1: Term of Reference-liquid Terminal

TERM OF REFERENCEDESIGN FOR LIQUID TERMINAL

LUBUK GAUNG REFINERY PLANT

1. Topographic Survey and Investigation of Existing Area a. Survey of Mater Layout Drainage Existing Plant (Flow Direction, channel

dimension, bottom drainage elevation)b. Topographic Survey of existing boundaryc. Topographic Survey of detailed situationd. Topographic Survey of existing elevatione. Soil Investigation Test (deep boring and sondir).f. Collecting secondary data (wind, rain, tides, etc)g. All related technical data and documentation for [permit process (IMB, etc)h. Cut and Fill recommendationi. Shore Protection recommendationj. Land Improvement recommendation

2. Engineering, Design and Specification (C/M/E) a. Site Planb. Sectional Viewc. Overall Design Basisd. Detail section and Drawinge. Outline Technical Specification (M/C/E)f. Schematic Design and arrangements for whole plant

3. Design Development (C/M/E) a. Design (Drawing, detail and Specification) – Architecture Design; layout,

sectional view, elevation, layout of switch board, motor points, cable support system, lighting scheme, typical layout detail and finishing scheme.

b. Mechanical, Electrical & Civil Design (Specification and Calculation), All mechanical and electrical Design Outside Battery Limit (OSBL) Connection to Generator, Tank Farm to Main Office

c. Detail Design Report including Design Report, Drawing, Technical Specification and Budget Estimate for each utility above:

i. Main Office (C/M/E)ii. Road Access/System for whole plant

iii. Overall Pipe Rack Structuresiv. Drainage system for whole areav. All infrastructures work for whole area

vi. Tank Farm (C/M/E)vii. Weight Bridge (C/M/E)

viii. Pump House and Compressor (C/M/E)ix. Unloading and Laboratory (C/M/E)x. Generator and Transformer Building (C/M/E)

xi. Water tank with 500 lt capacity – 2 nos.xii. Pump Room Building and Fire Fighting system (C/M/E)

xiii. Boiler Warehouse (C/M/E) and Boiler itself

Page 2: Term of Reference-liquid Terminal

xiv. Coal and Cangkang Building (C/M/E)xv. Clean Water Storage tank – 500 lt. capacity

xvi. Workshop Building (C/M/E).

Compilation of all drawings and documents including design development and construction stage complete with detail design and administration documents.

4. FINAL DESIGN PRODUCTa. Hardcopy and softcopy:

i. Design Reports, Design drawing and detail drawing in A2 / A1 format for construction (softcopy (MS-Word, MS-Excel, PDF or CAD and Hardcopy)

ii. Technical Specification document (C/M/E)iii. Bill of Quantity (include unit price for all equipment material and labour,

unit rate analysis)iv. All design calculation – original file from engineering soft ware or

spreadsheet.v. Schedule for each Building and overall schedule.

vi. Method of Workb. Prepare product Catalogue and Operation Procedure Document (Manual

Installation, Operation and Maintenance for Equipment.c. Preparation Data for Permit. Prepare data (C/M/E) for Construction Permit.