tender for dg - chikhli(g.c.) industrial areaproviding lbm...

184
MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION TENDER DOCUMENT TENDER FOR Name of Work : DG - CHIKHLI(G.C.) INDUSTRIAL AREA...Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internal road G-H-I & Construction of WBM road for partial length with Strengthning , 50 mm thick semi grout with 20 mm thick PSS to Pentakali Jackwell road at Chikhali Growth Centre

Upload: duongkhanh

Post on 27-Jun-2019

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

TENDER DOCUMENT

TENDER FOR

Name of Work : DG - CHIKHLI(G.C.) INDUSTRIAL AREA...ProvidingLBM ,50 mm th. DBM with 25 mmth. SDBC to MIDCinternal road G-H-I & Construction of WBM road forpartial length with Strengthning , 50 mm thick semigrout with 20 mm thick PSS to Pentakali Jackwell road atChikhali Growth Centre

Page 2: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

Short Tender Notice1 1 1

Detailed Tender Notice2 2 5

DIRECTIONS FOR FILLING THE TENDER3 6 6

SCOPE OF WORK4 7 7

CLAUSE FOR RECOVERY OF ADDITONAL SECURITY DEPOSIT5 8 8

CLAUSE FOR RECOVCERY OF LABOUR CESS6 9 9

COMMON CONDITIONS AND ADDITIONAL CONTRACT CONDITIONS7 10 16

SPECIAL CONDITION FOR ROYALTY PAYMENT8 17 17

DECLARATION9 18 18

CLAUSE FOR REIMBURSEMENT OF TAXES/DUTIES10 19 19

PRICE VARIATION CLAUSE11 20 25

Value Added Tax (VAT) Act and Contract Labour, Income Tax Clause12 26 26

INSURANCE Clause of Work13 27 27

QUALITY AUDIT CLAUSE14 28 28

STANDARD CEMENT CONSUMPTION STATEMENT15 29 33

CEMENT VARIATION CLAUSE16 34 34

ADDITIONAL CLAUSE FOR WORKS COSTING MORE THAN RS.50 LAKHS17 35 35

Certificate From Contractor18 36 36

List of Defects Required to be observed and Rectified by the Contractor during the Defect Liability Period19 37 39

MAINTENANCE GUARANTEE CLAUSE DURING DEFECT LIABILITY PERIOD.20 40 40

Additional Contract Condition21 41 41

ANNEXURE – ‘A’ Joint Venture for works costing less than Rs.300 Lakhs22 42 43

ANNEXURE – ‘B’ Joint Venture for works costing less than Rs.300 Lakhs23 44 48

FORM - A24 49 50

B-1 Tender Form25 51 73

Schedule A26 74 76

Schedule B27 77 88

• Note : The Amendment’s details for any Tender document are displayed immediately after that document. Thelist of all such Amendments is available at the end of the document.

Item Wise Specification28 89

Index

Sr.No.

Particulars PageFrom

PageTo

Work Name : DG - CHIKHLI(G.C.) INDUSTRIAL AREA...Providing LBM ,50 mm th. DBM with 25 mmth. SDBC toMIDC internal road G-H-I & Construction of WBM road for partial length with Strengthning , 50 mmthick semi grout with 20 mm thick PSS to Pentakali Jackwell road at Chikhali Growth Centre

Page 3: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

(A Government of Maharashtra Undertaking)

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

E tenders are invited for the work “Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internalroad G-H-I & Construction of WBM road for partial length with Strengthning , 50 mm thick semi grout with 20mm thick PSS to Pentakali Jackwell road at Chikhali Growth Centre” having estimated cost of Rs.1,28,50,998.00 from the contractor registered with PWD, Govt, of Maharashtra, CPWD, MES, Railways, CIDCO,MJP in appropriate class.

The blank tender forms are available on E Tendering module on MIDC's website ,<www.midcindia.org>. The

Tenderers are requested to download the entire tender document from MIDC's website. The last date of

submission of E Tender documents duly filled in shall be 22/09/2015 upto 11:00 Hrs. and shall be opened on

the same day if possible. For further details please see detail tender notice on MIDC's website.

Right to reject any or all tenders without assigning any reason there of is kept reserved by the competentauthority.

--------------NOTICE ENDS HERE--------------

TENDER NOTICE NO. 06 / 2015-2016

Chief Engineer

Zone Nagpur

Page 1 Executive EngineerContractor

Page 4: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

DETAILED TENDER NOTICE NO. 06

E tenders are invited from eligible contractors for the following work. The details of tender are givenbelow.An amount given below towards Earnest Money Deposit (EMD) & cost of blank tender & applicationsupport amount should be paid online and online payment for errection of Asphalt plant with in 30 Km (ifApplicable).Scanned copy of D.D. towards Performance Security if applicable as per Performance SecurityClause shall be uploaded at the appropriate location in Envelope No. 2.The tender will be considered only if the enclosures are in proper order.The EMD will be forfeited in case, afterthe acceptance of the tender, the contractor refuses to pay the Security Deposit as noted below, within thespecified time limit. Otherwise it will be refunded. The work is to be completed within the stipulated time asnoted below.

1. Name of Work

DG - CHIKHLI(G.C.) INDUSTRIAL AREA...Providing LBM ,50mm th. DBM with 25 mmth. SDBC to MIDC internal roadG-H-I & Construction of WBM road for partial length withStrengthning , 50 mm thick semi grout with 20 mm thickPSS to Pentakali Jackwell road at Chikhali Growth Centre

2. Rs 1,28,50,998.00Estimated Cost

Earnest Money Deposit3.

Pay Rs 1,00,000.00 online

4. Application Support Amount

Rs. 1000/- pay online (Non-refundable)

5. Security Deposit

Pay Initial security deposit Rs 3,85,600.00 or 3.00% of tenderedcost whichever is higher. S. D. in the form of BG will be acceptedwhen amount of S.D. is more than Rs.50,000

Rs 8,99,600.00 or 7.00% of tendered cost whichever is higher tobe deducted through bills.

Cost of Blank Tender Form6.Rs 7,000.00 pay online (Non Refundable)

Not Required,Rs 0Deposit for Asphalt Plant7.

Demand Draft of Nationalized Bank / Scheduled Bank/ Bankapproved by Government of Maharashtra towardsPerformance Security if applicable as per PerformanceSecurity Clause payable at Khamgaon in favour of ExecutiveEngineer, MIDC, Division, Akola

Performance Security8.

Time Period9.6 Months Including monsoon

10. Availability of blank tender form24/08/2015 To 22/09/2015 (to be downloaded from the MIDC Etendering site www.midcindia.org).

Page 2 Executive EngineerContractor

Page 5: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

11. Queries of contractorWill be received by E tendering upto 09/09/2015 06:00 PM

12. Reply to queries & MIDC clarificationWill be published on the website on 15/09/2015 06:00 PM

Last date of submission of Tender13.22/09/2015 upto 11:00 AM hrs. @ MIDC website.

Date of opening of PQ & tender

Place of Tender Opening14.

22/09/2015 02:00 PM hrs. (if possible)

MIDC, Circle Office, Amravati

15. Class of registerationIV

16. Eligibility

Contractor having registration in IV & Above class with PWDGovt. of Maharashtra & MES, Railways, CPWD, MJP &CIDCO. Experience certificate of satisfactory completedatleast one single similar type of work consisting of LBM /DM / DBM/ AC / SDBC or any combination costing not lessthan Rs. 64.26 Lakhs in Govt. / Semi Govt. / Local Bodiesduring last 5 financial years should be attached in envelopeno.-1 only, ohterwise, 2nd envelope will not be opened. Thetnderer shall also comply with the conditions stated underthe clause of "Ädditional Contract Conditions" & shall submitthe certified document threeof in envelope no.-1

Compensation17.Rs 3,000.00 per day for delay in work execution/ completionof work.

Validity of offer18.180 days from the date of opening of the tender. (Fromopening of First Envelope)

1. Important Note: A. The information regarding the tender & PQ form (if applicable) & the facility todownload it, will be available on MIDC E tendering portal on website www.midcindia.org. The downloaded &duly completed tender form shall be submitted online (by eligible contractors only) without making anychange in the script of tender document. If after submission of tender, it is noticed that the tender script ismodified in any manner whatsoever, the tender will be summarily rejected. Contractors may upload theirqueries before expiry of query period. The replies to the queries received before the due date, will bepublished on the website along with MIDC clarification (if any) which should be downloaded by the tenderer.The document of reply to the queries of the contractor and MIDC clarification (if any) will form part & parcel ofthe tender document & the clarifications given in the document will supercede the provisions of the tender.After the tender is accepted & offer letter is issued to the contractor, agreement shall be executed with thecontractor on the tender copy prepared/printed by MIDC

B. Contractor must pay online:- a. EMD amount. b. Cost of Blank tender form. c. Application support amount. d. Deposit for erection of asphalt machinery within 30 Kms (if applicable) in absence of certificate and location plan uploaded at appropriate place.

2. The tenderer shall upload scanned copy / copies,of the following documents at appropriate place

Page 3 Executive EngineerContractor

Page 6: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Zone Nagpur

Chief Engineer

2. The tenderer shall upload scanned copy / copies,of the following documents at appropriate place

Envelope No.1 shall contain (i.e. in 1(a) and 1(b)):

(i) Certificate and location plan of Asphalt plant within 30 Kms. (If applicable) (In absence of Certificate andlocation plan of Asphalt plant pay the deposit online.) (ii) Attested copy of valid Registration Certificate in appropriate class issued by PWD (GoM)/ CIDCO/ Railways/MJP/ MES/ CPWD. (iii) Professional Tax Registration Certificate for employees in E category for tenders without PQ and both i.e.'E' & 'R' category for tenders where PQ is applicable. (iv) Registration Certification with Sales Tax Deptt. under VAT Act 2002, of Govt. of Maharashtra. (v) Certified copy of PAN card. (In case of Joint Venture PAN Card of the Lead Partner) (vi) Experience certificate for single similar work during last 5 financial years executed in Govt. Deptt. semiGovt. / Local bodies such as MIDC/ CIDCO/ MJP local bodies etc. as specified elsewhere OR PQ form dulycompleted with supporting documents and specified therein (if applicable). The updation of value work will bedone at 10% per annum (Compound) by multiplying the values with applicable factor i.e. 1.1,1.21,1.33,1.46 &1.61 as the case may be. (vii) Reply to queries of the contractor and MIDC clarification (if any). (viii) If tenderer desires to form JV, the notarized MOU of JV shall be uploaded as per format enclosed (ifapplicable). (ix) In case of final asphalting work i.e. BM/AC/DBA/SDBC/PSS works included in composite work or singlework, if the asphalt work costs Rs.100 lakhs and above, the details of plant and machinery as per form No. 'A'of PQ form. (x) The photo copies duly attested, of the above certificates will have to be uploaded in Envelope No.1.Original shall be produced in the office of for verification on the day of opening of the tender as mentionedelsewhere. (xi) Service tax Registration.

Envelope No.2 shall contain : (i) Price Bid (ii) Scanned copy of D.D. towards Performance Security if applicable as per Performance Security Clause shallbe uploaded at the appropriate location.

Important Conditions -1. The Submission of tender shall be done in the manner prescribed by MIDC only.2. If the contents of Envelope No.1(a) and 1 (b) are not found as per the requirements of MIDC, theEnvelope No.2 will not be opened at all & the tender shall be summarily rejected.3. Tenderer should digitally sign wherever required.4. The tenderer shall be bound to keep open the offer upto 180 Days from the date of opening of thetender. (i.e. from opening of First Envelope of tender)5. The acceptance of the tender rests with the competent authority which does not bind itself to accept thelowest tender & reserves the right to reject any or all tenders without assigning any reason thereof.6. The notes & conditions stipulated in this notice & elsewhere in the tender shall form the part of theagreement.7. If it is found that the information submitted is misleading/ false or if it is found that certain information ishidden, then the contractor will be disqualified during any stage of tender process & even after opening oftender.8. If any tenderer discloses/try to discloses in any manner whatsoever his offer in any other place thanenvelope No.2, his tender will be summerarily rejected.

Page 4 Executive EngineerContractor

Page 7: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Zone Nagpur

Page 5 Executive EngineerContractor

Page 8: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

DIRECTIONS FOR FILLING THE TENDER

1. The tenderer should quote the percentage/rate in words & in figures.

1. The tenderer should carefully note the unit for each item. No change in this unit is to be made. In case ofany doubt, the tenderer should get the matter clarified from the concerned Executive Engineer well inadvance so that the submission is made before the specified date & time.

2. All works proposed to be executed by contract shall be notified in a form of invitation to tender put up on a boardhung up in the office of the Exe. Engineer & signed by Exe. Engineer. This form will state the work to be carried out,the date for submitting & opening tenders, the time allowed for carrying out the work, the amount of earnest moneyto be deposited with tender, the amount of security deposit to be deposited by the successful tenderer & thepercentage, if any, to be deducted from bills. It will also state whether a refund of quarry fees, royalties, octroi &ground rents will be granted. Copies of the specifications, designs, drawings, estimated & scheduled rates & anyother documents required in connection with the work shall be signed by the Exe. Engineer for the purpose ofidentification & shall also be open for inspection by contractors at the office of Exe. Engineer during office hours.

Where the works are proposed to be executed according to the specification recommended by a contractor & approved

by a competent authority on behalf of MIDC such specifications, designs & drawings shall form part of the accepted tender.

1. The tenderer shall fill up the printed form, stating at what percentage above/below the rates specified in Schedule B(Memorandum showing items of work be carried out) he is willing to undertake the work. Only one rate or suchpercentage on all the Estimated rates/Scheduled rates shall be entered. Tenders, which propose any alteration inthe specifications in the said form of invitation to tender, or in the time allowed for carrying out the work, or whichcontain any other conditions, will be liable to rejection.

2. No receipt for any payment alleged to have been made by a contractor in regard to any matter relating to thistender or the contract shall be valid & binding on MIDC unless it is signed by the Exe. Engineer.

3. The Memorandum of work to be tendered for & the Schedule of Materials to be supplied by MIDC & their rates shallbe filled in & completed by office of Exe. Engineer before the tender form is uploaded.

4. All the work shall be measured net by standard measure & according to the rules & customs of MIDC withoutreference to any local custom.

5. The contractor is allowed to change his bid till last date of time of the submission of the tender. Only the last bid willbe saved in the system which will be considered for evaluation if the contractor is found eligible for opening of pricebid.

Page 6 Executive EngineerContractor

Page 9: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

SCOPE OF WORK

Name Of Work :- Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internal road G-H-I &Construction of WBM road for partial length with Strengthning , 50 mm thick semi grout with 20 mm thick PSS toPentakali Jackwell road at Chikhali Growth Centre

MIDC has developed Chikhali Growth Centre on 201.99 hectors of land situated on Chikhali- Jalanaroad about 3.00 kms. away from Chikhali town in district Buldhana. In this area, 183 plots have been carved out, outof which 138 Nos. of plots have been allotted to the various entrepreneurs, About 19 units are in production and 9units are under construction. MIDC has also established water supply scheme of 2.00 MLD capacity and raw water islifted from Pentakli Dam which is 24 KM. away from Chikhali G.C. The entire area is developed, the infrastructurefacilities such as asphalted roads, water treatment plant of 2.00 MLD capacity with 500 m3 capacity ESR, water

supply distribution network, street lights etc. are provided in this area.Following works are included in the tender.

1) Strengthening of old WBM road (approch road to Pentakli Jackwell)2) Providing 50mm th. semigrout with 25mm th. PSS to

Pentakli Jacewell road.3) Providing LBM 50mm DBM with 25 mm SDBC to MIDC internal road G-H-I.4) Construction of WBM road for partial length with strengthening.

All materials such as murum, metal, pipes,asphalt etc. shall be tested in Govt. laboratories. The tests shall be carriedout as per direction of Engineer-in-charge & relevant latest I.S. practices. The frequency of each test as mentioned inthe specification may be varied by Executive Engineer in charge of the work.. Charges for the testing shall be borneby the contractor. No extra payment for the same will be made by the department.

Any damaged to property such as power / Telephone. lines etc. during execution of work shall berectified or compensation will have to be paid by the contractor at his own risk and cost.During execution period of the work, contractor has to make necessary arrangement for diverting thetraffic at his risk and cost for which no any additional payment will be made. The contractor has to obtain thenecessary permissions from local authorities/land owners, engate necessary full time manpower and providenecessary road furniture for traffic diversion.

Page 7 Executive EngineerContractor

Page 10: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Govt of Maharashtra Undertaking)

CLAUSE FOR RECOVERY OF ADDITONAL SECURITY DEPOSIT A) Clause for Recovery of Additional Security Deposit in case tenders ACCEPTED more than 15% below :The tenderer shall note that, in case the tender is quoted and accepted more than 15% below then theadditionalsecurity deposit shall be recovered in the form of cash / DD, as the case may be, at the time of execution ofagreement .The recovery of additional security deposit shall be as detailed below:

Sr.No.

Offer received below Additional securitydeposit to berecovered

1) For offer between 15.01% upto20% below

1% of estimated cost.

2) For offer between 20.01% upto25% below

2% of estimated cost

3) For offer more than 25.01%below

3% of estimated cost

B) Clause for Recovery of security deposit for quantities Exceeding 125% and Extra Item Rate List (EIRL):

It shall also be noted that security deposit for the quantities exceeding 125% of tendered quantities and/orEIRL shall also be deducted at the % to be recovered through bills (i.e. in cash) as mentioned in the tender text.

C) Refund of above Security deposit:

The security deposit so recovered in above events shall be refunded after satisfactory completion of defectliability period.

Page 8 Executive EngineerContractor

Page 11: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

CLAUSE FOR RECOVERY OF LABOUR CESS

The Govt. of Maharashtra vide its decision dated 17/06/2010 has decided to recover Labour cess on allthe construction works undertaken by Govt., Public sector undertaking and Municipal Corporation, MunicipalCouncils, Gram Panchayat etc.

The contractors are therefore requested to note that labour cess at 1% of the cost of construction (excludingland cost) arrived at after deducting amount of compensation if any paid to the workers or their relatives underworkers compensation Act 1923 will be recovered from them. The recovery of labour cess at 1% shall be made fromthe payment due for each bill to be paid to the contractor.

Page 9 Executive EngineerContractor

Page 12: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

COMMON CONDITIONS & ADDITIONAL CONTRACT CONDITIONS

1. COMMON CONDITIONS: Extra charges for any item of work shall not be allowed unless the work to which it is related is clearly withinthe spirit & meaning of the specification or unless such works are ordered in writing by the Engr-in-charge & are claimed for in thespecified manner before the commencement of work. The contractor shall at his own expense make all necessary provisions for housing,water supply, electricity & sanitary arrangements for his employees at site of works as required. He shall pay directly to the concernedauthorities all rates, taxes, royalties & other charges. He shall also comply with all requirements of health department of the concernedauthorities.

2. MATERIALS: Unless otherwise specifically provided for either in the item or in the specifications or in the Schedule 'A' for Supply ofMaterials by MIDC, all items in the tender are inclusive of costs of material required for the execution of the items. Materials not stipulatedto be supplied by MIDC, shall be brought by the contractor at his cost. The quality, type & make of materials used in the work shall be asper samples got previously approved from Engineer-in-charge, as mentioned in the detailed specification All rejected material shall beremoved by the contractor from site of work immediately failing which the same will be got removed by MIDC at his cost.

3. WORKS: The lining out of all works shall be marked by the contractor on site with permanent pillars as directed. The necessary levelswill be given by MIDC. The contractor must however, provide the necessary labour & material for making out the ground & keeping allreferences, levels & lining props sealed in cement concrete & execute the work in accordance with those levels for which he will beresponsible throughout the whole period of contract. The few bench mark pillars to be connected with MIDC benchmark shall beconstructed by the contractor at the site of work as directed for reference of various levels in connection with work. The line out if requiredto be carried out more than one time, the same shall be done by the contractor without extra cost.

4. CARTING: The contractor shall convey pipes, specials & other sundry materials required for the Execution of the work at his owncost.The contractor shall provide diversion to the affected existing road, if required, as directed by Engineer-in-charge at his own cost

5. GENERAL: The contractor shall be deemed to be thoroughly conversant with the local condition such as the availability of allconstruction materials, skilled & unskilled labour & to have based his rates accordingly for this work. He shall be deemed to have carefullystudied all the specifications & drawings & followed them before the submission of his tender.

6. In case of any discrepancy between the type of working drawings on one hand & the wording of the corresponding item & specificationsthereof as per the contract, the later will be deciding for the purpose of actual execution of items. However, the Exe. Engineer's decisionshould be obtained in the matter before hand. For a composite item, if any higher specification are to be adopted for any component as aresult than specified in the item & specification therefore, extra rate will be payable on approvaNo major deviation involving substantialextra outlay will be made without the prior approval of the Superintending Engineer.

7. Work progress register will be maintained by MIDC on site &/or in the Divisional office &/or Sub division under it. The contractor willsign all instruction issued by Exe. Engineer or his representative/ his superior officers & comply with them. For this purpose the contractoror his authorised representative shall attend the site or said office daily for receiving instructions.

8. i) Metered water supply will be made available to the contractor from MIDC pipeline if available & water consumed will be charged atthe prevailing industrial rate or near by industrial area or in that area subject to change as decided by MIDC from time to time. Theconnection, metering etc. shall be taken by the contractor at his cost. In case of water supply to CETP and CHWTSDF will be provided atdomestic rate applicable in that area during construction and operation period.

ii) For taking water supply connection separate agreement for water supply connection is necessary to be executed with MIDC and the termsand conditions of this agreement will prevail until water supply connection is in force.

9. It willbe the contractor's responsibility to inspect & investigate the work site thoroughly so as to arrive at the rates quoted in the tender.In

Page 10 Executive EngineerContractor

Page 13: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

this regard necessary information available with MIDC Will be given to him without any guarantee about it's foolproofness.

10. Contractor has to clear road land width/plot which includes cutting trees less than 30 Cms. In girth with permission from concernedcompetent authority, cleaning brush wood, loose stones, vegetation, bushes, stumps & mole hills without any extra cost. The contractor shallprovide diversion to the affected existing road, if required as directed by Engineer-in-charge at his own cost.

11. The contractor shall engage an authorised all time person on this work capable of engaging & guiding the work & understanding allspecifications. He will take orders as willbe issued by the Exe.Engineer, or his authorised representative & shall be responsible for carryingthem out. The person shall not be changed without prior intimation to the Exe. Engineer & his representative on the work site.

12. The contractor will take all precautions during the execution of work so as not to cause any damage to any property/ adjacent properties& shall be responsible to make good any damaged property as directed by the Exe. Engineer till his satisfaction.

13. All installations such as electric cable, water pipeline, telephone lines, OFC, Sewer main manhole, natural drainage, gas/ fuile pipelines,CD works, strom water draines etc coming in the way shall be looked after carefully. The protections and support against any damages,which otherwise willhave to made good by contractor at his cost. In case any permission is required from Concerned authority for handlingthese lines, the contractor will co-ordinate with such authority. All safety precautions shall be taken from traffic flow point of view.

14. Contractor should specifically indicate the metal & murum quarries from which he proposes to bring the material for completing thework.

15. Where the proper measurement of work, it is necessary to have an initial set of levels taken,the same as recorded in the authorised fieldbook by the Exe. Engineer or his authorized representative & willbe signed by the contractor who willbe entitled to have a true copy of thesame on demand. Any failure on the part of the contractor to get such levels before starting the work will render him liable to accept thedecision of the Exe. Engineer as to the basis of taking measurements. Likewise the contractor will not cover any work which will render itssubsequent measurement difficult or impossible, without first getting the same jointly measured by himself & the authorised representativeof the Exe. Engineer. The record of such measurements on to Department's side willbe signed by the contractor & he willbe entitled to havea true copy of the same on demand.

16. All work before being finally taken over by MIDC will be entire liability of the contractor for guardingmaintaining & making good anydamage of any magnitude. Interim payments made for such work will not alter this position. The handing over by the contractor & takingover by the Exe. Engineer, or his authorised representative, will be always in writing, of which copies will go the Exe. Engineer, hisauthorised representative & the contractor. It is, however understood that before taking over such work, MIDC will not put it to its regularuse distinct from casual/incidental one.

17. Orders issued by the Superintending Engineer of MIDC by whatever designation he may be knownfrom time to time regarding theconduct of the work shall be binding on the contractor.

18. The tendered rates for supply of materials are for delivery of materials properly stacked in regular heaps or otherwise as directed forfacility of measurement before use. In case of road materials, the same shall be stacked by the road side as directed. Materials shall not betacked at places where they are likely to be damaged or lost. The contractor shall have no claim for any loss on this account. If such materialhas been paid for& is subsequently lost before use in the work, the contractor shall make good the loss.

19. No material shall be removed from the road land, except for excavation of gutters, or any other adjoining land unless permitted in writingsubject to such conditions as the Exe. Engineer may specifyThe contractor is liable for the damages/compensation arising out of disregard ofthis condition.

20. The orders of collection & utilisation of materials shall be decided by Exe.Engineer/his authorised representative so as to ensure orderlywork.

21. For the items so indicated, no materials shall be used without first having been measured by regular stacks. The whole of the quantity ofa particular material required for a sizable section of the work shall be first collected before it can be measured & used. The same materialshall either be collected separately or the collection shall not be started at all unless the material collected in the section under reference has

Page 11 Executive EngineerContractor

Page 14: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

shall either be collected separately or the collection shall not be started at all unless the material collected in the section under reference hasbeen all used.

22. The contractor will have to construct a shed for storing controlled & valuable materials issued to him under Schedule 'A' of theagreement, at work site, having double locking arrangement.The material shall be taken for use in the presence of the departmental person.No material will be allowed to be removed from site of work.

23. Under no circumstances shall any contractor be entitled to claim enhanced rates for any items in this contract.

24. The contractor shall study all the plans, specifications & other terms & conditions of the contract carefully before tendering & shall alsoinspect the site & get self acquainted with nature of work & local conditions regarding the availability of labour, material, source &sufficiency of water supply required for the execution of the work & site conditions, rivers, nallas, topography etc existing roads, means ofcommunication & access to site of work etc.

25. The contractor shall submit, within one month from the date of work order of MIDC, designs & drawings to the Exe.Engineer. Aftergetting the letter of approval of design from Exe.Engineer, the contractor shall at his own expense clear the site & take up theprovisional & final setting & carryout the work under the supervision of his responsible representative & shall provide necessary material,labour, tools, instruments etc required for the same. The line & setting out shall be done most accurately & it shall be the full responsibilityof the contractor for correctness of the position, level, dimensions, alignment etc of all parts of the work & if any time during the execution,any error appears/arises, the same shall be rectified by the contractor at his own cost. The checking of any setting out/line/level by theEngineer shall not in any way absolve the contractor of his own responsibility for the correctness thereof. The contractor shall protect &preserve all benchmark, site rails etc used for setting out of the work.

26. The contractor shall, if necessary, construct temporary roads & maintain these in proper condition till the completion of work at hisown cost. If necessary, he shall also at his own cost, make necessary arrangement for acquisition of land for construction of suchtemporary road or for any other purpose in connection with the execution of work.

27. The contractor shall comply with all proper & legal orders & direction of the local/public authority/ municipality & abide by their rules& regulations & pay all such fees & charges which he may be liable to. No reimbursement of such fees & charges will be made by MIDC.

28. The contractor shall inform the Engineer-in-charge in writing when any portion of the work is ready for inspection giving himsufficient notice to enable him to inspect the same without regarding the further r progress of work. The work shall not be considered tohave been completed inaccordance with terms of contract until the Engineer-in-charge shall have certified in writing to that effect

29. If contractor desires to use any design/material/process covered by letter "Patent" or "Copy Right", it shall be responsibility of thecontractor to observe all legal formalities for the use of the same

30. In the event of there being reasonable doubt as to the quality of workmanship & material used in the construction, the Engineer-in-chargemay order to the contractor to satisfy MIDC by carrying out suitable test of structure or part thereof. In the manner as prescribed in Clauseon Page 53 of the Indian Std. Code for practice for PCC & RCC for general building construction & as per Std.Spcf. of Deptt. As may beapproved by the Engineer-in- charge regarding the sufficiency wherever necessary at his own cost to the entire satisfaction of the Exe.Engineer

31. All the laboratory equipment required for the field test of materials, concrete, steel shall be arranged by contractor at his own cost

32. The contractor shall take all precautions, due care against damage by floods, rains, storms,out break of fire & accidents. Nocompensation willbe allowed to the contractor for his plants/materials lost, damaged by way of the above cause or other causes which isin charge of the contractor.

33. Safety of materials & recoveries: The contractor shall use the materials supplied to him by the department at free of cost or as mentionedin the Schedule ‘A’ very properly & economically. The contractor shall be responsible for proper handling & safe custody of the materialsso issued to him. The materials remaining unused after the completion of the work shall be returned by the contractor at the Department. Thedepartment will accept only such materials as are in perfect conditions. If any of the materials issued to the contractor free of cost there of

Page 12 Executive EngineerContractor

Page 15: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

department will accept only such materials as are in perfect conditions. If any of the materials issued to the contractor free of cost there ofshall be recovered from the contractor at double the rate at which it was purchased by the department, or the market rate prevailing at thetime whichever is higher. The contractor shall maintain a day to day account of materials issued to him by the department & shall produce itto the Engineer-in-charge when demanded.

34. Road Crossings: Any work at the road crossing shall be restricted only to half the width of the road, leaving the other half open fortraffic. Second half is taken up only after the first half is completed & made upto the original surface, serviceable with the permission ofEngineer-in-charge. All roads shall be reinstated by the contractor without any extra cost after proper consolidation, watering, cutting etc.Guarding barricading shall be provided by the contractor for 24 hrs. a day. The work of road crossing shall be planned well in advance &shall be carried out within the minimum possible time thereby causing least disturbance to traffic. No road sha ll remain excavated for morethan 24 hrs. Where the roads are very narrow such that traffic cannot be allowed in the second half when the work in first half is in progress,the contractor shall provide necessary diversions & maintain the same at his cost till such time as the work is in progress & the road isopened to traffic.

35. Interpretation: Singular & Plural 'Work' imparting the singular number shall include the plural number also & vice versa where thecontext requires.

36. Removal of Contractor's Employees: The contractor shall employ in & about the execution of the works only such persons as are careful,skilled, competent & experienced in their several trades & shall, on the direction of the Engineer-in-charge forthwith cease to employ in &about the execution of the works. Any person who in the opinion of the MIDC or En-Engineer-in-charge, misconduct himself, or isincompetent or negligent in the proper performance of his duties or whose continued employment is undesirable for any reason, suchpersons shall not be again employed upon the works without the written permission of the MIDC/Engineer-in-charge

37. Access to site of work: The provisions of clauses & conditions of this contract shall also apply to all premises, work shops, factories,plants, quarries & all other places from where materials, manufactured articles & machineries are being obtained or stored for the works.The MIDC/Engineer-in-charge or their representative & other subordinates shall be furnished with such information, assistance & facility bythe contractor as is required to make a complete & detailed investigation/inspection/supervision of the said goods.

38. Inspection of Works & Materials:

All materials & each part of details of the work shall be subject at all times, to inspection by the MIDC/Engineer-in-charge or theirrepresentative or other authorized subordinateswho shall be furnished with reasonable facilities & assistance by the contractor forascertaining whether or not the work as performed or the materials used are in accordance with the requirements & intent of the plans &specifications.

The contractor shall also inform the Engineer-in-charge in writing, when any portion is readyfor inspection giving him at least 24 hrs.advance intimation to enable him to inspect the same without regarding further progress of the work.

Any work done or materials used without supervision or inspection by the MIDC/Engineer-in-charge or is representative, is liable to beordered to be removed & replaced at the contractor's expense.

39. Testing of Materials & Works: All materials before being incorporated in the work shall be inspected. After satisfactory necessary testsas per prevalent standards shall be approved by the Engineer-in-charge. The testing shall be done in the Government approvedlab or anylaboratory approved by MIDC & the testing charges shall be borne by the contractor himself only.

Any work in which such materials are used prior to inspection & when necessary, testing & without approval or written permission of theEngineer-in-charge shall be considered as unauthorized, defective & not acceptable.

The testing of materials & works where necessary shall be carried out in accordance with the latest standards Methods of Bureau of IndianStandards Institution current on the date fixed for opening of the tender. If no such standard exists for a particular test, the standard methodas laid down by the British Standard Institution or by American Association of State Highway Officials or the American Society or othersuitable organization for testing of materials, will be used at the discretion of the Engineer-in-charge. He may also adopt any other suitable

Page 13 Executive EngineerContractor

Page 16: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

method at his discretion.

The contractor shall furnish such facilities instruments, machinery, equipment, labour and material as the Engineer-in-charge may require forcollecting & forwarding sample or for ascertaining the quantity, quantity or weight of materials used and if so directed shall not make usedof or incorporate in the work of any materials represented by the said sample until the required test are made and the materials accepted.

The contractor shall establish a laboratory at site where routine testing of materials of concrete, asphalt etccan be done to the requirements asper work at his cost. The daily test report register should be maintained at site/ lab and shall be produced as and when required.

The cost of collection of sample including transportations as well as of the testing shall be borne by the contractor for the followings.

i) The collection & supply of the samples & carrying out of such tests is provided for or clearly intended in the contract, willbe carried outin the laboratories approved by the Engineer-in-charge.

ii) The collection & supply of the samples & the carrying out of such tests if not provided for or clearly intended in the contract but ontesting, the material is found defective & has to be rejected. The defective material should be removed from site within 24 hours & report ofthe same should be given to Engineer-in-charge.

40. Unauthorized & Defective Works: No work shall be done without lines, levels, grades, lengths & other dimensions having been givenor approved by the Engineer-in-charge or when authorized by him or by his representative or other authorized subordinates. Any work doneby the contractor prior to the approval of the contract, work done contrary to or regardless of the instructions of the Engineer-in-charge,work done beyond the lines shown on the plans or as given, or any extra work done without authority willbe considered as unauthorized &willnot be paid for under the provisions of this contract. Work so done shall be ordered to be removed or replace at the contractor's expense.All works & materials which do not conform to the requirements of the contract whether on account of poor workmanship, defectivematerials, unsuitable equipments & plans, carelessness or any other causes, shall be considered as defective.

The Engineer-in-charge shall have the power to order removal or replacement of all unauthorized/defective materials/works which in hisopinion should be removed or replaced all defects, be removed, replaced or corrected as may be directed by the Engineer-in-charge.

41. Night Work: Subject to any provisions to the contrary contained in the contract, no work shall be carried out between the hours of sun set& sunrise without the written permission of the Engineer-in-charge except when the work is unavoidable or absolutely necessary,for savinglife or property or for the safety of the work, in which case, the contractor shall immediately inform the Engineer-in-charge or hisrepresentative, provided always that the provision of this clause shall not be applicable in the case of any work which it is customary to carryout by double or rotary shifts in which case sufficient advance notice shall be given of the intention of work at night to the Engineer-in-charge. After making all requisite arrangements & managementof areas, materials & equipments,required under any emergency etc.Overtime to supervisory staff of the MIDC, in such cases shall have to be however borne by the contractor.

The contractor shall also carry on work between sunset & sunrise if so required by the Engineer-in-charge, subject to obtaining approval inwriting, for expediting the progress on the works or for any other reasons of technical safety.

Whenever any work is required to be carried out at night in the interest of structural safety or any other reason with express approval of theEngineer-in-charge or his representativeauthorized to supervise, adequate lighting & other arrangement shall be made in advance by thecontractor for proper execution & supervision of the such work. The contractor shall not be however entitled to any extra payments for nightwork. Before such work to be carried, the contractor should also inform to local Police Station in writing.

42. Explosive and inflammable Materials: The MIDC does not anticipate use of any explosive or any inflammable material on this work,however, in the event, explosive of inflammable materials are used for the execution of the works, the contractor shall at his own expense,obtain such license or license as may be required for storing and using explosives and or inflammable materials and locate, construct andmaintain magazines if such area is required for storage in accordance with relevant Government rules in force. Such magazine shall clearlymarked dangerous – explosive in the original language and devnagriand shall be in the care of competent watchman all the time. All theseshall be done under intimation and after getting concurrence Engineer-in-charge.

The contactor shall exercise utmost care while using explosives and or inflammable material not to endanger life or property and shall be

Page 14 Executive EngineerContractor

Page 17: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

The contactor shall exercise utmost care while using explosives and or inflammable material not to endanger life or property and shall besolely responsible for any and all damages resulting from their storage and use, and shall indemnify absolutely MIDC and its office andemployees against any claim and liability arising out of any accident or any violation and or any law, rules, orders etc.

43. Care, Maintenance and repair of works:-

a) From the commencement until the time, the works are completed and finally accepted and handed over to the MIDC, the contractor shalltake full responsibility for care and maintenance thereof including care of all temporary works to the satisfaction of the Engineer-in-chargeand in case any damage the Deterioration loss or injury shall happen to the works or to any part there of or to any temporary work, fromstorms, fire, rains, accidents or any case whatsoever other than earthquake, volcanic eruption or other convulsionof nature or act of God,War, Invasion, act of foreign enemies, hostilities (whether war be declared or not) Civil war, rebellion, revolution, insurrection or military orinsured power, shall at his own cost maintain, repair and make good the same so that till the time of final acceptance, the works shall be ingood order and condition and in conformity in every respects with the requirements of the contract and the instructions of the Engineer-in-charge.

b) If the contractor fails to comply with the requirements mentioned in Sub Clause 1 above, the Engineer-in-charge will immediately askhim to comply with the same within prescribed period.In the event of contractor failing to comply with these instructions, the Engineer-in-charge will immediately proceed to take care of the same viz. maintain or repair as required at the cost of the contractor. The clauseregarding defect liability period is given separately.

44. Compliance of Laws: The contractor shall keep himself fully informed of all acts, laws of the Central & state Governments, all local byelaws, ordinances, rules & regulations & all orders & decrees of bodies/tribunals having any jurisdiction/authority which in any manner effectthose engaged or employed on the work or which in way effect the conduct of the works. He shall at all time observe & comply with all suchlaws, ordinances, rules, regulations, orders & decrees & shall give all notices & pay out of his own money, say fees or charges to which hemay be liable.

He shall protect & indemnify the MIDC & its officers & employees against any claim or liability arising from or based on the violation ofany such laws, ordinances, regulations orders, or decrees whether by himself or by his employees

45. Treasure Trove: In the event of the discovery by the contractor or his employees during the progress of the works of any treasure, coins,antiquities, fossils, minerals or other articles or things of value or interest, whether geological, archeological or any other such treasure orother things shall be deemed to be the absolute property of MIDC.

The contractor shall take all reasonable precautions to prevent his workmen or another persons from removing such things as above & shallimmediately upon discovery thereof & before removal, acquaint the Engineer-in-charge of such discovery &carry out his orders as to thedisposal of the same which will be at the contractors expense.

46. Patented Devices, Materials & Processes: Whenever the contractor desires to use any design, device, drawing information's, materials, orprocess covered by a patent of copyright,he shall procure the rights for such use by suitable legal agreement with the patentee or owner at hisown expenses & a copy of the agreement shall be filed with the Engineer-in-charge.

The contractor shall indemnify the MIDC from & against all claims, proceedings, damages, costs & expenses which may be brought ormade against the MIDC or to which they may be put by reason of the contract infringing or being held to have infringed any patent rights orcopyright in relation to any design, device drawing, materials or process at anytime during the prosecution or after the completion of thework & in the event of any injunction being obtained against the use of the same, the contractor shall replace the same with other materialsdesign, drawing, device, process etc. which do not infringe any such patent right or copy right, to the infringe any such patent right or copyright, to the satisfaction of the Engineer-in-charge.

47. Trespass: The contractor shall at all times be responsible for any damages due to trespass committed by his agents & work people incarrying out the work, unless authorized by the Engineer-in-charge in writing in which case,all repair work shall be done by the contractor at

Page 15 Executive EngineerContractor

Page 18: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

his own cost to restore the original condition.

48. Indemnity: The MIDC shall on behalf of the contractor shall indemnify their officers, employees etc against all actions, suits, claims &demands of any character brought in respect of any matter or thing done or omitted to be done by the contractor in the excavation of or inconnection with the works of this contract & against any loss or damage to MIDC his workman/labourers in consequence, for any action orsuit being brought against the contractor for anything done or omitted to be done in the execution of the works of the contract orcompensation to be paid by contractor to his workman/labourers in consequence of accidents causing damage or loss of life of hisworkman/labourers etc. All such payments made by the MIDC shall be recovered from the contractor from his dues out standing, or remainsto be paid or that which becomes payable.

The MIDC shall not be liable to the contractor for damages or losses or delays resulting, from work by third parties or by injunction or otherrestraining orders obtained by third parties.

49. Police Protection: If police is asked for by the contractor for special protection of his camp of work, the MIDC may arrange for suchprotection so far as possible with the authorities concerned and full cost of such protection shall be debited to the contractor and recoverfrom his bills without any extra claim

50. Permits, Licenses, Priorities, Certificates etc: The contractor shall make his own arrangements at his own cost, if required.

a.To obtain permits, licenses, quota certificates, foreign exchange etc for any materials or items of work etc if required by him.

b.To obtain rail & other priorities for transport of his plant, tools equipments, stores, machinery materials, labour staff etc.

c.To arrange with civil supply authorities for release of controlled goods if so, for his labour & staff.

The MIDC will not undertake to arrange for these but will not undertake to arrange for these but will render reasonable help within itscompetence without accepting any responsibility for delay if any.

51. Field Book: Whichever payments is based on levels, all sets of levels such as initial, intermediate & final shall be taken & recorded bythe Engr-in-charge or his representative in the presence of Contractor or his authorised representative. Contractor shall attend the site forchecking these levels & signing in token of acceptance thereof. If Contractor fails to attend the site on the day or for any reason fails to signthe documents in which these levels are recorded,they shall be final & binding on the contractor

52. Levels shown on the drawings: Whichever payment is based on the levels, all sets of levels such as initial, intermediate & final shall betaken & recorded by the Engr-in-charge or his representative in the presence of contractor or his authorised representative.Advanceintimation of day & time when the levels would be taken will be given by MIDC to the contractor/ his authorised representative.Contractorshall attend the site for checking these levels & signing in token of acceptance thereof.If contractor fails to attend the site on the day or forany reason fails to sign the documents in which these levels are recorded, they shall be final & binding on the contractor

53. Sign Boards:Necessary sign boards, danger flags & lamps during night time to mark the closure of the road shall be provided by thecontractor at his cost.A chowkidar is essential to be appointed by the contractor to keep light & watch the materials lying on site,intactthrough the night. Contractor is responsible for the accidents if above care in not taken properly. He will have to pay compensation for thesame.

Page 16 Executive EngineerContractor

Page 19: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

Special Condition for Royalty Payment

Clause regarding recovery of royalty charges through the bills of contractor towards Minor Minerals such as murum, excavation,

sand, metal etc. work done by the contractor

1) It shall be noted by the contractor that the amount of royalty charges towards the minor minerals(Excavation, murum, metal, sand etc.) consumed/used by the contractor for the work will be deducted from his billsand will be paid to the concerned Revenue Deptt. by MIDC.2) The contractor shall obtain above types of minor minerals from Govt. approved quarries or from the privateland after obtaining legal permission from the concerned authorities. However, in case the contractor brings thematerial from unauthorized quarries or in illegal manner, he shall be fully responsible for any legal action taken bythe Revenue or any Govt. authorities against him for such unauthorized or illegal act, even thoughthe royaltycharges are recovered from his bills and paid to be Revenue Department. He shall also indemnify MIDCofficers from any legal action so taken by the Govt. authorities for default on his part.3) The contractor shall give an undertaking on court fee stamp of Rs.100/- for indemnifying MIDC officersfrom any legal action taken by Govt. as detailed above.

Page 17 Executive EngineerContractor

Page 20: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

DECLARATION

I/We hereby declare that in the forma­tion of our Company, either by way of partnership or consultant, no

MIDC ex-employee has been on the enrollment of the Company.

It is further to certify that the ex-employee of the MIDC, who has joined the Company, has completed 2

years from his date of resignation from MIDC or from the date of retirement from MIDC.

Date :

Place : Signature of Contractor

Page 18 Executive EngineerContractor

Page 21: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

CLAUSE FOR REIMBURSEMENT OF TAXES/DUTIES

While submitting the tender, the contractor shall consider the prevailing taxes & duties on the dateof submission. In case there is statutory increase in the taxes/duties, the contractor shall submitdocumentary evidence for the payment of the same. On verification of the documents, the reimbursementwill be made if there is increase. In case there is reduction in the statutory taxes/duties, deduction will beeffected. It may also be noted that this clause is not applicable if there is increase in the octroi duringexecution of the work.

=======================================

Page 19 Executive EngineerContractor

Page 22: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

ACCOMPANIMENT TO THE GOVERNMENT RESOLUTION

PUBLIC WORKS DEPARTMENT NO. CAT/06/04/148 DT 16.5.2005

PRICE VARIATION CLAUSE

1. If during the operative period of the contract as defined in condition (i) below,there shall be any variation in theConsumer Price Index (New Series) for Industrial workers for MUMBAI Centre as per the Labour Gazette publishedby the Commissioner of Labour, Govt.of Maharashtra &/or in the Wholesale Price Index for all commoditiesprepared by the Office of Economic Adviser, Ministry of Industry, Govt. of India, or in the price of petrol/oil &lubricants & major construction materials like bitumen, cement, steel, various types of metal pipes etc, then subjectto the other conditions mentioned below, price adjustment on account of

i) Labour component

ii) Material component

iii) Petrol, oil & lubricant components

iv) Bitumen component

v) HYSD & mild steel component

vi) Cement component

vii) CI & DI pipes component

calculated as per the formula hereinafter appearing, shall be made. Apart from these, no other adjustment shall bemade to the contract price for any reason whatsoever. Component percentage as given below are as of the total costof work put to tender. Total of labour, material & POL components shall be 100 & other components shall be as peractual's,i) Labour component (Kl) [!LG] 35 %ii) Material component (K2) [!MG] 60 %iii) Petrol, Oil & Lubricant components (K3) [!PG] 5 %iv) Bitumen componentv) HYSD & mild steel componentvi) Cement componentvii) CI & DI pipes component

Note: if cement, steel, bitumen, CI & DI pipes are supplied on Schedule-A, then respective component shall not be

considered. Also, if particular component is not relevant, same shall be deleted.

1) Formula for Labour components :

V1 = 0.85 P x K1 x L1-L0

Page 20 Executive EngineerContractor

Page 23: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

100 L0

Where

V1= Amount of price variation in Rupees to be allowed for labour component P= Cost of work done during the

quarter under consideration minus the cost of cement, HYSD & mild steel, bitumen, CI & DI pipes calculated at the

basic star rates as applicable for the tender, consumed during the quarter under consideration. Star rates:

K1= Percentage of LABOUR component as indicated above.

L0= Basic Consumer Price Index for MUMBAI centre shall be average consumer price index for the quarter

preceding the month in which the last date prescribed for receipt of tender falls.

L1= Average Consumer Price Index for MUMBAI centre for the quarter under consideration.

2) Formula for Materials components :

V2 = 0.85 P x K2 x M1 -M0

100 M0

Where

V2= Amount of price variation in Rupees to be allowed for material component P= Same as worked out for labour

component K2= Percentage of Material component as indicated above.

M0= Basic Wholesale Price Index shall be average wholesale price index for the quarter preceding the month in

which the last date prescribed for receipt of tender falls.

M1= Average Wholesale Price Index for the quarter under consideration.

3) Formula for petrol, oil & lubricant components :

V3 = 0.85 P x K3 x P1-P0

100 P0

Where

Page 21 Executive EngineerContractor

Page 24: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

V3= Amount of price variation in Rupees to be allowed for POL component

P= Same as worked out for labour component

K3= Percentage of petrol, oil & lubricant component as indicated above.

P0= Average Price of HSD at MUMBAI, during the quarter preceding the month in which the last date prescribed for

receipt of tender falls.

P1= Average Price of HSD at MUMBAI, during the quarter under consideration.

4) Formula for Bitumen Component:

V4 = QB (B1 - B0)Where

V4= Amount of price variation in Rupees to be allowed for bitumen component

QB= Quantity of bitumen (Grade ) in Metric Tonnes used in the

permanent works & approved enabling works during the quarter under consideration.

B1= Current, average ex-refinery price per metric tonne of bitu

men (Grade ) under consideration including taxes (octroi,

excise, sales tax/VAT etc) during the quarter under consideration.

B0= Basic rate of bitumen in Rupees per metric tonne as considered for working out value of P or average ex-

refinery price in Rupees per metric tonne including taxes (octroi, excise, sales tax/VAT) of bitumen for the grade of

bitumen under consideration during prevailing quarter preceding the month in which the last date prescribed for

receipt of tender falls whichever is higher.

5) Formula for HYSD & mild steel component: V5 = SO x (SI1 - SI0) x T

SI0

Where

V5= Amount of price variation in Rupees to be allowed for HYSD/ mild steel component SO= Basic rate of

Page 22 Executive EngineerContractor

Page 25: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

V5= Amount of price variation in Rupees to be allowed for HYSD/ mild steel component SO= Basic rate ofHYSD/mild steel in rupees per metric tonne as considered for working outvalue of P. SI1= Average Steel Index asper RBI Bulletin during the quarter under considerationSI0= Average of Steel Index as per RBI Bulletin for thequarter preceding the month in which the last date prescribed for receipt of tender falls. T= Tonnage of steel used inthe permanent works for the quarter under consideration.

6) Formula for cement component :V6 = CO x (CI1 - CI0) x T

CI0

Where

V6= Amount of price escalation in Rupees to be allowed for cement component CO= Basic rate of cement inrupees per metric tonne as considered for working out value of P. CI1= Average Cement Index published in the RBIBulletin for the quarter under consideration. CI0= Average of Cement Index published in the RBI Bulletin for thequarter preceding the month in which the last date prescribed for receipt of tender falls. T= Tonnage of cement usedin the permanent works for the quarter under consideration.

7) Formula for CI/DI pipe Component: V7 = QD x (D1 - D0)

Where

V7= Amount of price escalation in Rupees to be allowed for CI/DI pipe component D0= Pig iron basic price inRupees per tonne considered for working out value of P. D1= Average pig iron price in Rupees per tonne during thequarter under consideration (Published by IISCO). QD= Tonnage of CI/DI pipes used in the works during the quarterunder consideration.

The following conditions shall prevail:

b) The operative period of the contract shall mean the period commencing from the date of the work order issued tothe contractor & ending on the date on which the time allowed for the completion of work specified in the contractfor work expires, taking into considering the extension of time, if any, for completion of the work granted byEngineer under the relevant clauses of the Conditions of Contract in cases other than those where such extension isnecessitated on account of default of the contractor. The decision of Engineer as regards the Operative Period of thecontract shall be final & binding on the contractor. Where any compensation for liquidated damages is levied on thecontractor on account of delay in completion or inadequate progress under the relevant contract provisions, the priceadjustment amount for the balance of work from the date of levy of such compensation shall be worked out bypegging the indices L1, M1, C1, P1, B1, SI1, CI1 to levels corresponding to the date from which such compensationis levied. ii) This price variation clause shall be applicable to all contracts in B1 & B2 forms but shall not apply topiece works. The price variation shall be determined during each quarter as per formula given above in this clause.iii) Price variation under this clause shall not be payable for the extra items required to be executed during thecompletion of the work & also on the excess quantities of items payable under the provision of Clause 14/41 of thecontract form B1 & B2. Since the rates payable for the extra items or the extra quantities under Clause 14/41 are tobe fixed as per the current DSR or as mutually agreed to yearly revision till completion of such work. In other words,when the completion/execution of extra items as well as extra quantities under Clause 14/41 of the Contract Form B1& B2 extends beyond the operative date of the DSR, then rates payable for the same beyond that date shall be revised

Page 23 Executive EngineerContractor

Page 26: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

& B2 extends beyond the operative date of the DSR, then rates payable for the same beyond that date shall be revisedwith reference to the current DSR prevalent at that time on year to year basis or revised in accordance with mutualagreement thereon, as provided for in the contract, whichever is less. iv) This clause is operative both ways ie.if theprice variation as calculated above is on the plus side, payment on account of the price variation shall be allowed tothe contractor & if it is on the negative side, MIDC shall be entitled to recover the same from the contractor & theamount shall be deductible from any amounts due & payable under the contract. v) To the extent that fullcompensation for any rise or fall in costs to the contractor is not entirely covered by the provisions of this or otherclauses in the contract, the unit rate & price included in the contract shall be deemed to include amount to cover thecontingency of such other actual rise or fall in costs.

vi) Calculation for working out escalation payment on account of material, labour & POL will be restricted to 2digits only.

Where V5= Amount of price variation in Rupees to be allowed for HYSD/ mild steel component SO= Basic rate ofHYSD/mild steel in rupees per metric tonne as considered for working out value of P. SI1= Average Steel Index asper RBI Bulletin during the quarter under consideration. SI0= Average of Steel Index as per RBI Bulletin for thequarter preceding the month in which the last date prescribed for receipt of tender falls. T= Tonnage of steel used inthe permanent works for the quarter under consideration.

8) Formula for CI/DI pipe Component: V7 = QD x (D1 - D0)

Where V7= Amount of price escalation in Rupees to be allowed for CI/DI pipe component D0= Pig iron basic pricein Rupees per tonne considered for working out value of P. D1= Average pig iron price in Rupees per tonne duringthe quarter under consideration (Published by IISCO).

QD= Tonnage of CI/DI pipes used in the works during the quarter under consideration.

The following conditions shall prevail: b) The operative period of the contract shall mean the period commencingfrom the date of the work order issued to the contractor & ending on the date on which the time allowed for thecompletion of work specified in the contract for work expires, taking into considering the extension of time, if any,for completion of the work granted by Engineer under the relevant clauses of the Conditions of Contract in casesother than those where such extension is necessitated on account of default of the contractor. The decision ofEngineer as regards the Operative Period of the contract shall be final & binding on the contractor. Where anycompensation for liquidated damages is levied on the contractor on account of delay in completion or inadequateprogress under the relevant contract provisions, the price adjustment amount for the balance of work from the date oflevy of such compensation shall be worked out by pegging the indices L1, M1, C1, P1, B1, SI1, CI1 to levelscorresponding to the date from which such compensation is levied.

ii) This price variation clause shall be applicable to all contracts in B1 & B2 forms but shall not apply to piece works.

Page 24 Executive EngineerContractor

Page 27: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

The price variation shall be determined during each quarter as per formula given above in this clause.

iii) Price variation under this clause shall not be payable for the extra items required to be executed during thecompletion of the work & also on the excess quantities of items payable under the provision of Clause 14/41 of thecontract form B1 & B2. Since the rates payable for the extra items or the extra quantities under Clause 14/41 are tobe fixed as per the current DSR or as mutually agreed to yearly revision till completion of such work. In other words,when the completion/execution of extra items as well as extra quantities under Clause 14/41 of the Contract Form B1& B2 extends beyond the operative date of the DSR, then rates payable for the same beyond that date shall be revisedwith reference to the current DSR prevalent at that time on year to year basis or revised in accordance with mutualagreement thereon, as provided for in the contract, whichever is less. iv) This clause is operative both ways ie.if theprice variation as calculated above is on the plus side, payment on account of the price variation shall be allowed tothe contractor & if it is on the negative side, MIDC shall be entitled to recover the same from the contractor & theamount shall be deductible from any amounts due & payable under the contract.

v) To the extent that full compensation for any rise or fall in costs to the contractor is not entirely covered by theprovisions of this or other clauses in the contract, the unit rate & price included in the contract shall be deemed toinclude amount to cover the contingency of such other actual rise or fall in costs.

vi) Calculation for working out escalation payment on account of material, labour & POL will be restricted to 2digits only.

Page 25 Executive EngineerContractor

Page 28: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA STATE COMMISSIONER OF SALES TAX

NOTIFICATION NO.VAT-1505/CR-123/TAXATION-1 DT.1.4.2005

MAHARASHTRA VALUE ADDED TAX ACT-2002

1. The tendered rates shall be inclusive of all taxes, rates & cesses & shall also be inclusive of the tax leviable in respect of VATunder the provision of the Maharashtra Value Added Tax Act-2002.

2. The contractors who submit the tenders should necessarily be a Registered Dealer under the MaharashtraValue Added Tax Act, 2002.

3. The contractor shall submit the Registration Certificate as a registered dealer under the above said Act atthe time of submission of tender/at the time of issuing the work order.

4. MIDC will deduct this tax at source at 2% (for registered contractors) & 4% (in other case) of the value ofthe work done as per Section 31 of Maharashtra VAT Act, 2002 & Notification No.VAT-1505/CR-123/TAXATION-1 DT.1.4.2005. TDS certificate to this effect will be issued by MI DC.

REGISTRATION UNDER CONTRACT LABOUR ACT -1970

While submitting the tender, the tenderer should note that he should produce the certified xerox copy ofRegistration in prescribed form issued by Labour Commissioner under Contract Labour Act, 1970, as an employer,as much as they are directly employing the workers for execution of the contract works awarded to them by MI DC& comply with the provision of the Act. After acceptance of tender by MIDC the contractor has to give intimationabout work order & get this particular work registered within a period of 15 days from the date of issue of work orderfrom labour commissioner under Contract Labour Act, 1970 failing which no permission will be granted to continuefurther work under the agreement.

DEDUCTION OF INCOME TAX

The Income Tax including surcharges or percentage in force from time to time or at the rate as intimated bythe competent Income Tax authority shall be deducted from bill amount whether measured bill, advance payment orsecured advance.

VAT will be deducted 5% instead of 4%

Amendments

Page 26 Executive EngineerContractor

Page 29: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION(A Government of Maharashtra Undertaking)

INSURANCE OF WORK

The contractor shall take out necessary Insurance Policy/Policies immediately after issuing work order and produce acopy of same prior to payment of first RA bill so as to pro­vide adequate insurance cover for exe­cution of theawardedcontract work for total contract value & complete con­tract period including defect liability period asstipulated in thetenderpaper and upto the period for which the extension of time limit is granted from the "Directorateof Insurance,MaharashtraState, Mumbai" only. Its postal address for correspon­dence is "264, MHADA, 1st floor,Opp Kalanagar,Bandra (E), Mumbai-400 051". Tel.26438690 / 26438746 & Fax:26438461. Similarly, all workmenappointed to complete the contract work are required to be insured under Workmen's Compensa­tion InsurancePolicy. Insurance Policy /Policies taken out from any other com­pany will not be accepted. If any con­tractor haseffected insurance with any Insurance Company, the same will not be accepted.

Page 27 Executive EngineerContractor

Page 30: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

QUALITY AUDIT CLAUSE

The contractor shall note that, following exercise of Quality Audit of the work shall be carried out by the nominated

authority from MIDC.

1. The quality audit of the work shall be exercised by authority nominated by MIDC at a stage when 80% of the workis completed or at stage as decided by MIDC.

2. The contractor should remain present (alongwith all test re­ports & necessary documents for the works) at site whenquality audit of the work is being exercised.

3. Final Bill will be released for payment only after complia­nce of the points/remarks raised by the quality auditor withproper reasoning to the competent authority & only after re­ceipt of clearance of nominated authority.

4. The contractor has to make all necessary rectifications, al­terations to the work executed, as suggested by thequality auditor without any extra cost. If the contractor fails to do so, or does not intend to do so, then the probableamount required for the rectifi­cation shall be withheld from the bills & other dues payable to the contractor. Thecontractor shall be liable to pay suitable compensation as decided by the Superintending Engineer.

Page 28 Executive EngineerContractor

Page 31: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION( A Govt. of Maharashtra Undertaking)

STANDARD CEMENT CONSUMPTION STATEMENT

Item of Work Rate of CementConsumption inbags.

Remarks

A] Cement Concrete (Nominal Mix)

Lower Limit Upper Limit

1:5:10 (M-5) 2.60/m3 2.35 2.85

1:4:8 (M-7.5) 3.10/m3 2.80 3.40

1:3:6 (M-10) 4.10/m3 3.80 4.40

1:2:4 (M-15) 6.20/m3 5.90 6.50

1:1&frac12;:3 (M-20) 8.20/m3 7.90 8.50

1: 1: 2 (M-25) 8.70/m3 8.40 9.00

B] Cement Concrete (Design Mix) Minimum cementconsumption forDesign Mix

M-15 5.80/m3 The grater value of either theminimum cement contentspecified or cementconsumption as per design mixwill prevail during execution ofwork.

M-20 6.60/m3

M-25 6.60/m3

M-30 7.00/m3

M-35 7.50m3

M-40 8.00/m3

C] Brick Masonry II Class with 30% mortar

CM - 1:8 1.05/m3

CM - 1:6 1.40/m3

CM - 1:5 1.70/m3

CM - 1:4 2.10/m3

D] 115 mm thick Brick Masonry II Class

CM - 1:3 0.28/m2

E] Brick Masonry I Class withoutpointing with 25% mortar

CM - 1:6 1.15/m3

CM - 1:5 1.40/m3

CM - 1:4 1.70/m3

F] UCR Masonry without pointing with 35% mortar

CM - 1:6 1.70/m3

CM - 1:5 2.00/m3

CM - 1:4 2.50/m3

G] UCR Masonry without pointing with 45% to 50% mortar

CM - 1:6 2.15/m3

CM - 1:5 2.60/m3

CM - 1:4 3.10/m3

H] Laterite Stone Masonry with 18% mortar

CM - 1:6 0.85/m3

CM - 1:5 1.00/m3

CM - 1:4 1.30/m3

I] Cement Plaster with Cement mortar 1:3 (neeru finish)

6 mm 0.07/m2

12 mm 0.13/m2

20 mm 0.20/m2

25 mm 0.23/m2

40 mm 0.40/m2

J] Cement Plaster with Cement mortar 1:4 (without neeru finish)

6 mm 0.06/m2

12 mm 0.11/m2

20 mm 0.17/m2

25 mm 0.22/m2

40 mm 0.34/m2

K] Coursed Rubble masonry with pointing 30% mortar

1:6 CM 1.70/m3

1:5 CM 2.00/m3

1:4 CM 2.50/ m3

L] Sand Faced plaster CM 1:3

12 MM 0.20/m2

20 MM 0.23/m2

25 MM 0.25/m2

M] Cement plaster without neeru finish CM 1:3

6 MM 0.07/m2

12 MM 0.13/m2

20 MM 0.20/m2

25 MM 0.25/m2

N] Cement plaster with neeru finish CM 1:4

6 MM 0.06/m2

12 MM 0.10/m2

20 MM 0.17/m2

25 MM 0.22/m2

O] Decorative texture plaster

CM 1:4 0.15/m2

P] Neat Cement Finish over green surface

1.5 mm Thick 0.04/m2

Q] Wet on wet finish CM 1:3

12 MM 1.05/m2

R] Pointing with Cement Mortar 1:3

Brick Masonry 0.03/m2

Stone Masonry 0.05/m2

S] Paving and Flooring

Shahabad / Tandur / Kotta / KaddapaChequred tiles / plain cement tiles /marble / mosaic / granite CM 1:4 bedand with pointing 1:3

0.19/m2

Skirting & Daddo 0.30/m2

Shahabad / Tandur / Kadappa CM 1:6 0.14/m2

White / coloured glazed tiles 0.28/m2

Granite stone facing plaster CM 1:3 0.20/m2

Ceramic tiles 0.22/m2

IPS flooring 40 mm 0.30/m2

T] Colgrout Masonry with 45 % mortar

Cement 1:3 sand mortar 3.54/m3

U] Gunniting CM 1:3

25 MM 0.28/m2

40 MM 0.45/m2

50 MM 0.55/m2

V] Water proofing

Box type water proofing 0.80/m2

Water proofing by injection grouting 1.00/m2

Water proofing on terrace slab 0.50/m2

Page 29 Executive EngineerContractor

Page 32: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Item of Work Rate of CementConsumption inbags.

Remarks

A] Cement Concrete (Nominal Mix)

Lower Limit Upper Limit

1:5:10 (M-5) 2.60/m3 2.35 2.85

1:4:8 (M-7.5) 3.10/m3 2.80 3.40

1:3:6 (M-10) 4.10/m3 3.80 4.40

1:2:4 (M-15) 6.20/m3 5.90 6.50

1:1&frac12;:3 (M-20) 8.20/m3 7.90 8.50

1: 1: 2 (M-25) 8.70/m3 8.40 9.00

B] Cement Concrete (Design Mix) Minimumcementconsumption forDesign Mix

M-15 5.80/m3 The grater value of either theminimum cement contentspecified or cementconsumption as per design mixwill prevail during execution ofwork.

M-20 6.60/m3

M-25 6.60/m3

M-30 7.00/m3

M-35 7.50m3

M-40 8.00/m3

C] Brick Masonry II Class with 30% mortar

CM - 1:8 1.05/m3

CM - 1:6 1.40/m3

CM - 1:5 1.70/m3

CM - 1:4 2.10/m3

D] 115 mm thick Brick Masonry II Class

CM - 1:3 0.28/m2

E] Brick Masonry I Class withoutpointing with 25% mortar

CM - 1:6 1.15/m3

CM - 1:5 1.40/m3

CM - 1:4 1.70/m3

F] UCR Masonry without pointing with 35% mortar

CM - 1:6 1.70/m3

CM - 1:5 2.00/m3

CM - 1:4 2.50/m3

G] UCR Masonry without pointing with 45% to 50% mortar

CM - 1:6 2.15/m3

CM - 1:5 2.60/m3

CM - 1:4 3.10/m3

H] Laterite Stone Masonry with 18% mortar

CM - 1:6 0.85/m3

CM - 1:5 1.00/m3

CM - 1:4 1.30/m3

I] Cement Plaster with Cement mortar 1:3 (neeru finish)

6 mm 0.07/m2

12 mm 0.13/m2

20 mm 0.20/m2

25 mm 0.23/m2

40 mm 0.40/m2

J] Cement Plaster with Cement mortar 1:4 (without neeru finish)

6 mm 0.06/m2

12 mm 0.11/m2

20 mm 0.17/m2

25 mm 0.22/m2

40 mm 0.34/m2

K] Coursed Rubble masonry with pointing 30% mortar

1:6 CM 1.70/m3

1:5 CM 2.00/m3

1:4 CM 2.50/ m3

L] Sand Faced plaster CM 1:3

12 MM 0.20/m2

20 MM 0.23/m2

25 MM 0.25/m2

M] Cement plaster without neeru finish CM 1:3

6 MM 0.07/m2

12 MM 0.13/m2

20 MM 0.20/m2

25 MM 0.25/m2

N] Cement plaster with neeru finish CM 1:4

6 MM 0.06/m2

12 MM 0.10/m2

20 MM 0.17/m2

25 MM 0.22/m2

O] Decorative texture plaster

CM 1:4 0.15/m2

P] Neat Cement Finish over green surface

1.5 mm Thick 0.04/m2

Q] Wet on wet finish CM 1:3

12 MM 1.05/m2

R] Pointing with Cement Mortar 1:3

Brick Masonry 0.03/m2

Stone Masonry 0.05/m2

S] Paving and Flooring

Shahabad / Tandur / Kotta / KaddapaChequred tiles / plain cement tiles /marble / mosaic / granite CM 1:4 bedand with pointing 1:3

0.19/m2

Skirting & Daddo 0.30/m2

Shahabad / Tandur / Kadappa CM 1:6 0.14/m2

White / coloured glazed tiles 0.28/m2

Granite stone facing plaster CM 1:3 0.20/m2

Ceramic tiles 0.22/m2

IPS flooring 40 mm 0.30/m2

T] Colgrout Masonry with 45 % mortar

Cement 1:3 sand mortar 3.54/m3

U] Gunniting CM 1:3

25 MM 0.28/m2

40 MM 0.45/m2

50 MM 0.55/m2

V] Water proofing

Box type water proofing 0.80/m2

Water proofing by injection grouting 1.00/m2

Water proofing on terrace slab 0.50/m2

Page 30 Executive EngineerContractor

Page 33: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Item of Work Rate of CementConsumption inbags.

Remarks

A] Cement Concrete (Nominal Mix)

Lower Limit Upper Limit

1:5:10 (M-5) 2.60/m3 2.35 2.85

1:4:8 (M-7.5) 3.10/m3 2.80 3.40

1:3:6 (M-10) 4.10/m3 3.80 4.40

1:2:4 (M-15) 6.20/m3 5.90 6.50

1:1&frac12;:3 (M-20) 8.20/m3 7.90 8.50

1: 1: 2 (M-25) 8.70/m3 8.40 9.00

B] Cement Concrete (Design Mix) Minimumcementconsumption forDesign Mix

M-15 5.80/m3 The grater value of either theminimum cement contentspecified or cementconsumption as per design mixwill prevail during executionof work.

M-20 6.60/m3

M-25 6.60/m3

M-30 7.00/m3

M-35 7.50m3

M-40 8.00/m3

C] Brick Masonry II Class with 30% mortar

CM - 1:8 1.05/m3

CM - 1:6 1.40/m3

CM - 1:5 1.70/m3

CM - 1:4 2.10/m3

D] 115 mm thick Brick Masonry II Class

CM - 1:3 0.28/m2

E] Brick Masonry I Class withoutpointing with 25% mortar

CM - 1:6 1.15/m3

CM - 1:5 1.40/m3

CM - 1:4 1.70/m3

F] UCR Masonry without pointing with 35% mortar

CM - 1:6 1.70/m3

CM - 1:5 2.00/m3

CM - 1:4 2.50/m3

G] UCR Masonry without pointing with 45% to 50% mortar

CM - 1:6 2.15/m3

CM - 1:5 2.60/m3

CM - 1:4 3.10/m3

H] Laterite Stone Masonry with 18% mortar

CM - 1:6 0.85/m3

CM - 1:5 1.00/m3

CM - 1:4 1.30/m3

I] Cement Plaster with Cement mortar 1:3 (neeru finish)

6 mm 0.07/m2

12 mm 0.13/m2

20 mm 0.20/m2

25 mm 0.23/m2

40 mm 0.40/m2

J] Cement Plaster with Cement mortar 1:4 (without neeru finish)

6 mm 0.06/m2

12 mm 0.11/m2

20 mm 0.17/m2

25 mm 0.22/m2

40 mm 0.34/m2

K] Coursed Rubble masonry with pointing 30% mortar

1:6 CM 1.70/m3

1:5 CM 2.00/m3

1:4 CM 2.50/ m3

L] Sand Faced plaster CM 1:3

12 MM 0.20/m2

20 MM 0.23/m2

25 MM 0.25/m2

M] Cement plaster without neeru finish CM 1:3

6 MM 0.07/m2

12 MM 0.13/m2

20 MM 0.20/m2

25 MM 0.25/m2

N] Cement plaster with neeru finish CM 1:4

6 MM 0.06/m2

12 MM 0.10/m2

20 MM 0.17/m2

25 MM 0.22/m2

O] Decorative texture plaster

CM 1:4 0.15/m2

P] Neat Cement Finish over green surface

1.5 mm Thick 0.04/m2

Q] Wet on wet finish CM 1:3

12 MM 1.05/m2

R] Pointing with Cement Mortar 1:3

Brick Masonry 0.03/m2

Stone Masonry 0.05/m2

S] Paving and Flooring

Shahabad / Tandur / Kotta / KaddapaChequred tiles / plain cement tiles /marble / mosaic / granite CM 1:4 bedand with pointing 1:3

0.19/m2

Skirting & Daddo 0.30/m2

Shahabad / Tandur / Kadappa CM 1:6 0.14/m2

White / coloured glazed tiles 0.28/m2

Granite stone facing plaster CM 1:3 0.20/m2

Ceramic tiles 0.22/m2

IPS flooring 40 mm 0.30/m2

T] Colgrout Masonry with 45 % mortar

Cement 1:3 sand mortar 3.54/m3

U] Gunniting CM 1:3

25 MM 0.28/m2

40 MM 0.45/m2

50 MM 0.55/m2

V] Water proofing

Box type water proofing 0.80/m2

Water proofing by injection grouting 1.00/m2

Water proofing on terrace slab 0.50/m2

Page 31 Executive EngineerContractor

Page 34: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Item of Work Rate of CementConsumption inbags.

Remarks

A] Cement Concrete (Nominal Mix)

Lower Limit Upper Limit

1:5:10 (M-5) 2.60/m3 2.35 2.85

1:4:8 (M-7.5) 3.10/m3 2.80 3.40

1:3:6 (M-10) 4.10/m3 3.80 4.40

1:2:4 (M-15) 6.20/m3 5.90 6.50

1:1&frac12;:3 (M-20) 8.20/m3 7.90 8.50

1: 1: 2 (M-25) 8.70/m3 8.40 9.00

B] Cement Concrete (Design Mix) Minimumcementconsumption forDesign Mix

M-15 5.80/m3 The grater value of either theminimum cement contentspecified or cementconsumption as per designmix will prevail duringexecution of work.

M-20 6.60/m3

M-25 6.60/m3

M-30 7.00/m3

M-35 7.50m3

M-40 8.00/m3

C] Brick Masonry II Class with 30% mortar

CM - 1:8 1.05/m3

CM - 1:6 1.40/m3

CM - 1:5 1.70/m3

CM - 1:4 2.10/m3

D] 115 mm thick Brick Masonry II Class

CM - 1:3 0.28/m2

E] Brick Masonry I Class withoutpointing with 25% mortar

CM - 1:6 1.15/m3

CM - 1:5 1.40/m3

CM - 1:4 1.70/m3

F] UCR Masonry without pointing with 35% mortar

CM - 1:6 1.70/m3

CM - 1:5 2.00/m3

CM - 1:4 2.50/m3

G] UCR Masonry without pointing with 45% to 50% mortar

CM - 1:6 2.15/m3

CM - 1:5 2.60/m3

CM - 1:4 3.10/m3

H] Laterite Stone Masonry with 18% mortar

CM - 1:6 0.85/m3

CM - 1:5 1.00/m3

CM - 1:4 1.30/m3

I] Cement Plaster with Cement mortar 1:3 (neeru finish)

6 mm 0.07/m2

12 mm 0.13/m2

20 mm 0.20/m2

25 mm 0.23/m2

40 mm 0.40/m2

J] Cement Plaster with Cement mortar 1:4 (without neeru finish)

6 mm 0.06/m2

12 mm 0.11/m2

20 mm 0.17/m2

25 mm 0.22/m2

40 mm 0.34/m2

K] Coursed Rubble masonry with pointing 30% mortar

1:6 CM 1.70/m3

1:5 CM 2.00/m3

1:4 CM 2.50/ m3

L] Sand Faced plaster CM 1:3

12 MM 0.20/m2

20 MM 0.23/m2

25 MM 0.25/m2

M] Cement plaster without neeru finish CM 1:3

6 MM 0.07/m2

12 MM 0.13/m2

20 MM 0.20/m2

25 MM 0.25/m2

N] Cement plaster with neeru finish CM 1:4

6 MM 0.06/m2

12 MM 0.10/m2

20 MM 0.17/m2

25 MM 0.22/m2

O] Decorative texture plaster

CM 1:4 0.15/m2

P] Neat Cement Finish over green surface

1.5 mm Thick 0.04/m2

Q] Wet on wet finish CM 1:3

12 MM 1.05/m2

R] Pointing with Cement Mortar 1:3

Brick Masonry 0.03/m2

Stone Masonry 0.05/m2

S] Paving and Flooring

Shahabad / Tandur / Kotta / KaddapaChequred tiles / plain cement tiles /marble / mosaic / granite CM 1:4 bedand with pointing 1:3

0.19/m2

Skirting & Daddo 0.30/m2

Shahabad / Tandur / Kadappa CM 1:6 0.14/m2

White / coloured glazed tiles 0.28/m2

Granite stone facing plaster CM 1:3 0.20/m2

Ceramic tiles 0.22/m2

IPS flooring 40 mm 0.30/m2

T] Colgrout Masonry with 45 % mortar

Cement 1:3 sand mortar 3.54/m3

U] Gunniting CM 1:3

25 MM 0.28/m2

40 MM 0.45/m2

50 MM 0.55/m2

V] Water proofing

Box type water proofing 0.80/m2

Water proofing by injection grouting 1.00/m2

Water proofing on terrace slab 0.50/m2Page 32 Executive EngineerContractor

Page 35: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Item of Work Rate of CementConsumption inbags.

Remarks

A] Cement Concrete (Nominal Mix)

Lower Limit Upper Limit

1:5:10 (M-5) 2.60/m3 2.35 2.85

1:4:8 (M-7.5) 3.10/m3 2.80 3.40

1:3:6 (M-10) 4.10/m3 3.80 4.40

1:2:4 (M-15) 6.20/m3 5.90 6.50

1:1&frac12;:3 (M-20) 8.20/m3 7.90 8.50

1: 1: 2 (M-25) 8.70/m3 8.40 9.00

B] Cement Concrete (Design Mix) Minimumcementconsumption forDesign Mix

M-15 5.80/m3 The grater value of either theminimum cement contentspecified or cementconsumption as per designmix will prevail duringexecution of work.

M-20 6.60/m3

M-25 6.60/m3

M-30 7.00/m3

M-35 7.50m3

M-40 8.00/m3

C] Brick Masonry II Class with 30% mortar

CM - 1:8 1.05/m3

CM - 1:6 1.40/m3

CM - 1:5 1.70/m3

CM - 1:4 2.10/m3

D] 115 mm thick Brick Masonry II Class

CM - 1:3 0.28/m2

E] Brick Masonry I Class withoutpointing with 25% mortar

CM - 1:6 1.15/m3

CM - 1:5 1.40/m3

CM - 1:4 1.70/m3

F] UCR Masonry without pointing with 35% mortar

CM - 1:6 1.70/m3

CM - 1:5 2.00/m3

CM - 1:4 2.50/m3

G] UCR Masonry without pointing with 45% to 50% mortar

CM - 1:6 2.15/m3

CM - 1:5 2.60/m3

CM - 1:4 3.10/m3

H] Laterite Stone Masonry with 18% mortar

CM - 1:6 0.85/m3

CM - 1:5 1.00/m3

CM - 1:4 1.30/m3

I] Cement Plaster with Cement mortar 1:3 (neeru finish)

6 mm 0.07/m2

12 mm 0.13/m2

20 mm 0.20/m2

25 mm 0.23/m2

40 mm 0.40/m2

J] Cement Plaster with Cement mortar 1:4 (without neeru finish)

6 mm 0.06/m2

12 mm 0.11/m2

20 mm 0.17/m2

25 mm 0.22/m2

40 mm 0.34/m2

K] Coursed Rubble masonry with pointing 30% mortar

1:6 CM 1.70/m3

1:5 CM 2.00/m3

1:4 CM 2.50/ m3

L] Sand Faced plaster CM 1:3

12 MM 0.20/m2

20 MM 0.23/m2

25 MM 0.25/m2

M] Cement plaster without neeru finish CM 1:3

6 MM 0.07/m2

12 MM 0.13/m2

20 MM 0.20/m2

25 MM 0.25/m2

N] Cement plaster with neeru finish CM 1:4

6 MM 0.06/m2

12 MM 0.10/m2

20 MM 0.17/m2

25 MM 0.22/m2

O] Decorative texture plaster

CM 1:4 0.15/m2

P] Neat Cement Finish over green surface

1.5 mm Thick 0.04/m2

Q] Wet on wet finish CM 1:3

12 MM 1.05/m2

R] Pointing with Cement Mortar 1:3

Brick Masonry 0.03/m2

Stone Masonry 0.05/m2

S] Paving and Flooring

Shahabad / Tandur / Kotta / KaddapaChequred tiles / plain cement tiles /marble / mosaic / granite CM 1:4 bedand with pointing 1:3

0.19/m2

Skirting & Daddo 0.30/m2

Shahabad / Tandur / Kadappa CM 1:6 0.14/m2

White / coloured glazed tiles 0.28/m2

Granite stone facing plaster CM 1:3 0.20/m2

Ceramic tiles 0.22/m2

IPS flooring 40 mm 0.30/m2

T] Colgrout Masonry with 45 % mortar

Cement 1:3 sand mortar 3.54/m3

U] Gunniting CM 1:3

25 MM 0.28/m2

40 MM 0.45/m2

50 MM 0.55/m2

V] Water proofing

Box type water proofing 0.80/m2

Water proofing by injection grouting 1.00/m2

Water proofing on terrace slab 0.50/m2

Page 33 Executive EngineerContractor

Page 36: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION ( A Govt. of Maharashtra Undertaking)

CEMENT VARIATION CLAUSE

The rates in Schudule are based on the above stated rates of cement consumption. The permissible variation in the cement consumptionshall be as given under Item No.1 above. For rest of the item permissible variation shall be + 5% of figures give above. If the actualconsuption on any work is below these limits, reduced rates shall be paid (considering double the prevailing market rate) for any item ofwork on which less cement has been used below limit of -5%. If consumption goes beyond the limit of +5% the same shall not be paid.It may be noted that when specifically ordered out to adopt richer mix than specified in the tender, the excess cement soconsumed above the specified mix in the tender, the same will be paid at prevailing market rate. However, for cement saveddue to adoption of poorer mix when so specifically directed by the department, a reduced rate will be paid (as per prevailingmarket rate).For excess/less cement use on work as per cement variation clause the standarad consumption for cement shall be as pertable given above.

Page 34 Executive EngineerContractor

Page 37: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

ADDITIONAL CLAUSE FOR WORKS COSTING MORE THAN Rs.50 LAKHS

Contractor should construct a site office of area specified elsewhere in the tender at the work site for use of MIDC Engineers & other

staff with 1 table, 6 chairs, 1 steel cupboard,1 fan etc without any claim for reimbursement.

The possession of the office would be in charge of Deputy Engineer. After the com­pletion of work, contractor would be

re­quested to dismantle the site office con­structed for the temporary use & take back all the materials in the office such as

tables, chairs, cupboard, fans etc.

If in case no such office is constructed by the contractor within a period of one month from the date of work order, an

amount of Rs.2 Lakhs shall be deducted from 1st RA Bill, which shall be kept in deposit till the office is constructed.

Page 35 Executive EngineerContractor

Page 38: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

CERTIFICATE

I/We hereby certify that the rates have been quoted by me/us after:

a) I/We have fully acquainted myself/ ourselves with site conditions &b) I/We have fully read, understood & accepted all terms, conditions, specifications & requirementsmentioned in these tender documents.

Stamped & dated

Signature of the

Contractor

Page 36 Executive EngineerContractor

Page 39: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION ( A Govt. of Maharashtra Undertaking)

List of Defects Required to be observed and Rectified by the Contractor during the Defect Liability Period

For WBM Road, CD works & Asphalting Works

1. Sinkiing of embankment, side shoulders, forming depressions, forming boils etc.

2. Developing pot holes, ruts, boils, wavy surface.3. Sinking of road at CD Works, forming depressions/ bumps.4. Underpining at CD works.5. Developing longitudinal cracks.6. Side shoulders not devleoped and compacted to level of asphalted road surface.7. Damage of NP2/NP3 Class pipes and pipe joints of CD works.8. Damge of UCR masonry.9. Sinking of cushioning over CD works pipes.10. Peeling out of pointing of UCR masonary.11. Developing horizontal and vertical cracks to UCR masonry, coping, concrete and plaster.12. Any other defect crititical or logical defect informed by Engineer-in-charge.

For Building :-

1. Sinking of foundaton.2. Crack in plaster by side of column/ beams etc.3. sinking of floor/ developing of cracks in floor, wavy tiles etc.4. Leakages through roof slab, chajja, masonary joints etc.5. Leakages in & through toilet block, joints of all pipes, fittings etc.6. Leakages/ Dampness through roof/ walls.7. Damage to roofing materials like AC sheets.8. Bulging of door frames, door suhtters, warping of frames/ shutter.9. Improper functioning of tower bolts, hand rails, hinges, handles, other fixtures.10. Damage to Aluminium window frame and shutter.11. Leakages through water pipes and sanitory pipes.12. Peeling of plaster / paint.13. Leakages through structrual glazing due to improper fixing of panels.

Page 37 Executive EngineerContractor

Page 40: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

14. Any other defect critical or logical defect informed by Engineer-in-charge.

For Electrical Works:

1. Cables getting damaged/ over heated.2. Burning of switches.3. Damage of switchgears/ earthing etc.4. Damage or improper functioning of pumps.5. Wall bracket swings due to breeze.6. Cables getting damaged due to inadequate cover/ protection (improper laying of cable.)7. Painting peeled off/ faded.8. Improper functioning of lamps and included fixtures.9. Any other defects critical or logical defect informed by Engineer-in-charge.10. Water retaining strucutures

i) Hydraulic test not as per norms.

ii) Lekages through floor, side walls, through joints of pipes and concrete and inlet/ outlet connection.

1. Pipelines:

i) Painting peeled offf/ faded.ii) Tilting of supports.iii) Leakages through pipe joints.iv) Leakages through joints of specials.v) Gaps between pipes and supports.vi) Failure of specials, Sluice Valves, Air Valves supplied and erected.vii) Hydraulic test not as per norms.

1. Sewers:

Page 38 Executive EngineerContractor

Page 41: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

i) Sinking of line.

ii) Cracking of pipes for want of bedding.

iii) Leakages through joints.

iv) Chember height not at least 0.6 m above ground.

v) Hyraulic test not as per norms.

vi) Sinking of supports.

vii) Peeling of plaster provided for manhole chember.

1. ESR/ GSR/ Collection sumps:

i) Lekages through floor, side walls, through joints of pipes and concrete.

ii) Plaster peeling off.

iii) Verticle cracks in walls.

iv) Level indicator properly working.

v) Lightening conductor provided whether in good conditions.

vi) Hydraulic test not as per norms.

Note:

i. Any other defect over and above those mentioned above or any defect as an when pointed out by the\Engineer-in-charge will have to be attended satisfactorily by the contractor at his own cost during the defect liabilityperiod.

ii. Out of the above mentioned defects, the defects relevent to the work executed under this contract shallonly be observed.

Page 39 Executive EngineerContractor

Page 42: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

Maintenance Guarantee Clause during Defect Liability Period .

1. The contractor willhave to guarantee the work executed under the agreement for a period of 3 Year from the date of completion of thework. During this period of 3 Year , the contractor will have to make good all damages caused to the works done by him under thisagreement, to the full satisfac­tion of Engineer-in-charge, without charging any extra cost. The repairs to defects due to bad workmanshipshall be done.

2. The contractor willhave to maintain the work done by him under this agreement in good condition during the defect liability period. Thelist of defects to be observed and rectified is attached separately in the tender document.

3. The contractor will have to carry out the repairs within 8 days from the date of intimation by MIDC about the damages.

4. If during the guarantee period, the company/contractor's firm gets dissolved or some new partners are introduced, then the responsibilityto maintain the work done under this agree­ment during the defect liability period will have to be borne by the new Company/Contractor'sfirm.

5. For enforcing this guarantee, 10.00 % Security Deposit of esti­mated cost or tendered cost whichever is higher, shall be recovered fromthe contractor as under:

a) 3.00 % initial security deposit in the form of DD/BG at the time of issue of work order.

b) 7.00 % to be recovered through RA bills.

Out of this 10.00 %, the initial security deposit of 3.00 % in the form of BG/DD will be released alongwith the final bill. However,

remaining 7.00 % recovered through RA Bills shall be released after completion of defect liability period or after 3 Year from the date of

completion of work.

Before releasing such security deposit after 3 Year or after the defect liability period, the Executive Engineer along with the representative

of the contractor shall in­spect the work & if the work is found to be satisfactory then only 7.00 % security deposit shall be released.

6. Considering the guarantee offered by the contractor, the contractor is requested to thoroughly inspect & study the site conditions beforequoting for this work. No extra claim on this account will be entertained later.7. If certain works are neglected by the contractor, the same shall be carried out by the department at the risk & cost of the contractor. Thecost of the same shall be recovered from the amount balance with MIDC.8. Before starting the work, the contractor will have to give in writing,guarantee on stamp paper of Rs.100/- for free maintenance of workdone by him for the period of 3 Year from the date of completion of work.9. This Maintenance Guarantee Clause supersedes all clauses regarding security deposit mentioned elsewhere in this tender.

Page 40 Executive EngineerContractor

Page 43: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Maharashtra Industrial Development Corporation(A Govt. of Maharashtra Undertaking)

Contractor having registration in IV & Above class with PWD Govt. of Maharashtra & MES, Railways, CPWD,MJP & CIDCO. Experience certificate of satisfactory completed atleast one single similar type of work consistingof LBM / DM / DBM/ AC / SDBC or any combination costing not less than Rs. 64.26 Lakhs in Govt. / Semi Govt. /Local Bodies during last 5 financial years should be attached in envelope no.-1 only, ohterwise, 2nd envelope willnot be opened. The tnderer shall also comply with the conditions stated under the clause of "Ädditional Contract

Conditions" & shall submit the certified document threeof in envelope no.-1

Page 41 Executive EngineerContractor

Page 44: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Annexure – ACONDITIONS FOR JOINT VENTURE LESS THAN 300 LAKHS

1) If the application is made by Joint Venture Consortia of two or more contractors of any class may combine and tender for a work costingto the amount up to which each individual contractor of the higher of the two limits, if they are of different categories, are empowered totender as per the original registration provided that …

i) The application shall be signed by all JV Partners so as to be legally binding on all JV Partners.

ii) The combination is of the contractors as a whole and not individual partners.

iii) The main contractor shall furnish the notarised joint venture MoU along with other joint venture partner on Rs.100 stamp paper alongwith PQ form in envelope No.1 only without which they shall not be qualified.

2) The notarized JV MoU / Agreement should give details as under

a) Particulars of the Firm.

b) Profit sharing ratio.

c) Principal place of business.

d) Details of the Lead Member of the Joint Venture Consortia.

e) Details of the Bank Account Operations.

f) Details of the authorized representative of all the Joint Venture Consortia members etc.

g) The JV constituting agreement shall be irrevocable till the completion of work.

h) The JV constituting agreement should cover clauses pertaining to liabilities arising out of the work, if any and liquidation thereof.

i) Whereas the share of the lead member should not be less than 51% and the share of all the Joint Venture Firm shall be 100%

j) One of the Partners shall be nominated as being in-charge and this authorization shall be evidenced by submitting a power of attorneysigned by legally authorized signatories of the Partners.

k) The Partner in-charge shall be authorized to incur liabilities and receive instructions for and on behalf of any and all Partners of theJoint Venture Consortia and entire execution of the contract including payment shall be done exclusively with the partner in-charge.

l) All Partners of the Joint Venture Consortia shall be liable jointly and separately for execution of the contract in accordance withcontract terms and a relevant statement to this effect shall be included in the authorization mentioned under (j) above.

3) The notarized JV MoU so submitted along with the Tender shall be considered as a Legal Document for establishing the Joint VentureConsortia.

4) The information pertaining to class of Registration, Work experience and / or Plant & Machinery of JV partner in the respective formsduly signed by the Partner shall be submitted with the tender in envelope No.1.

5) The financial norms shall have to be satisfied by the lead partner of joint venture firm in respect of bid capacity, as per Form ‘F’

6) In case of Joint Venture consortia the sponsoring firm has to submit complete information and identify the lead firm. It would benecessary for the Joint Venture Consortia to establish to the satisfaction of the MIDC that the venture has made practical, workable and

Page 42 Executive EngineerContractor

Page 45: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

necessary for the Joint Venture Consortia to establish to the satisfaction of the MIDC that the venture has made practical, workable andlegally enforceable agreements amongst the parties, that responsibilities etc., assigned are capable in their individual capacity to dischargethem competently and satisfactorily and also that, the lead firm has necessary skill and capacity to lead and responsibility and involvementfor the entire period of execution as well as a leading role in control and direction on the resources of the entire Joint Venture Consortia.

7) The % share of other partners (other than lead partner) should not be more than his limit of eligibility to quote for works divided by theestimated cost of work put to tender i.e. when such a percentage is applied to the cost of the work, his share of cost should not exceed hisown eligibility limit of tendering for works.

8) Machineries owned by each partner & hired can be clubbed together

9) When contractors submit the PQ forms in individual capacity satisfying the required norms and the same contractor submits the P.Q.form as a joint venture partner, the P.Q. form in individual capacity shall only be considered. P.Q. form and tender submitted in J.V.capacity shall be rejected outright.

10) All joint venture partners shall be fully responsible for the satisfactory completion of work.

Page 43 Executive EngineerContractor

Page 46: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

ANNEXURE – ‘B’ Joint Venture for works costing less than Rs.300 Lakhs

MEMORANDUM OF UNDERSTANDING FOR JOINT VENTURE AGREEMENT FOR “______________________________________________________________________”

DEED OF PARTNERSHIP (JOINT VENTURE OF _____________ AND ________________)

This Memorandum of Understanding for Joint Venture Agreement made and entered into aton his ______ day of _______ 20___ by and between :

1) ………………………………………………

AND

2) ………………………………………………

DEFINATIONS :-

In this deed, the following words and expression shall have meanings set out below :

“The Joint Venture” ( “JV” for short) shall mean “_______________________ (JV)” and“___________________” Joint Venture collectively acting in collaborations for the purpose ofthis agreement.

“ Apex Co-ordination Body (ACB) shall mean the body comprising Director of the Parties tothe Joint Venture”

“The Owner” shall mean

………………………………………………………

………………………………………………………

“The Works” shall mean the ………………………………………………………......

……………………………………………………………….

“ The Contract ” shall mean the contract entered into or to be entered into between the “JointVenture” and “The Owner” for the works.

Page 44 Executive EngineerContractor

Page 47: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

JOINT VENTURE (JV)

(whereas the Parties hereto declare that, they agree and undertake to form a Joint Venturefor the purpose of Execution of the works, as an integrated Joint Venture. The JV shall becalled as “ JOINT VENTURE ” for short) Provided that the Parties are not under this agreemententering into any permanent Partnership or Joint Venture to tender or undertake any contractother than the subject works. Nothing herein contained shall be considered to construe theParties or Partners to constitute either Party the agent of the other.

WITNESSES

WHEREAS the Executive Engineer, ……………………………………. herein after referred asthe Executive Engineer, have invited tenders for the work of“…………………………………………………………………………….. hereinafter referred as“The Works”

Whereas PARTY NO. I and PARTY NO. II wish to execute the Contract, if awarded as per theterms of this indenture. Now, therefore this Deed of Partnership witnesses as follows :-

1) That, these recitals are and shall be deemed to have been part and parcel of thepresent MOU for JV.

2) That, this MOU shall come into force from the date of this MOU i.e. the day of_____________ the year ______________

3) That, the operation of this MOU for JV firm concerns and is confined to “the works”only.

4) That, the name of the Joint Venture firm shall be “_________________)

5) That, PARTY NO. I and PARTY NO. II shall jointly execute the works according to allterms and conditions as stated in the relevant instructions contained in the Bid Documents /Contract as an integrated JV styled as “_______________________________)

That, this MOU for JV shall regulate the relations between the parties and shall includewithout being limited to them the following conditions.

a)M/s. ___________________________ shall be the lead Company Incharge of the JointVenture for all intents and purpose.

b) The parties hereto shall jointly and severally liable to MIDC for all acts, deeds and thingspertaining to the Contract. The Contract for the works shall be signed by Shri.

Page 45 Executive EngineerContractor

Page 48: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

pertaining to the Contract. The Contract for the works shall be signed by Shri._______________________ as a General Power of Attorney Holder.

c)That the Director of one of the parties of the JV, ________________ shall be the leadPartner of the JV firm and shall have the Power to Control and Manage the Affairs of the JV.

d)That, on behalf of the Joint Venture Lead Partner, _______________ have the Authority toincur liabilities, receive instructions and payments, sign and execute the Contract for and onbehalf of the Joint Venture. All payments made under the contract shall be made into the JointVenture’s bank account.

e) One or two Bank accounts shall be opened in the name of JV to be operated by the JointSignatory by representative of both the Partner of Joint Venture.

f) That each of the parties to the JV agrees and undertake to place at the disposal of the JVbenefits of its individual experience, technical knowledge and skill and shall in all respectsbear its share of the responsibility including the provision of information, advice and otherassistance required in connection with the works. The share and the participation of thepartners in the JV shall broadly be as follows :-

Name of Contractor Share of Percentage

1)

2)

Total 100%

And all rights, interests, liabilities, obligations, works experience and risks (and all net profit ornet losses) arising out of the contract shall be shared or borne by the Parties in proportion tothese share. Each of the parties shall furnish its proportionate share in any bonds,guarantees, sureties required for the works as well as its proportionate share in workingcapital and other financial requirements, all in accordance with the decisions of the ApexCoordinating body.

g) Any loan/advances shall be shared by the PARTY NO. I and PARTY NO. II in the ratio of________________ respectively.

h) All funds, finance or working capital required for carrying out and executing, the works orcontract shall be procured and utilized by the parties are mutually agreed by them and theyshall be liable and responsible for the same. Initial Capital of the JV firm shall be Rs.

Page 46 Executive EngineerContractor

Page 49: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

_______________.

i) The execution of the work on the site will be managed by a Project Manager. The ProjectManager shall be authorized to represent the JV on site in respect of matters arising out orunder the contract.

j) The PARTY NO. I and PARTY NO. II shall be jointly and severally liable towards the ownerfor the execution of the contract commitment in accordance with contract conditions.

k) The JV shall be registered with the Registrar of Firms / Company, Maharashtra State.Prior written approval of MIDC shall be obtained before any changes are proposed to be madein this Joint Venture Agreement, once it is registered with the Registrar of firms / Company,Maharashtra State.

l) This Joint Venture Agreement shall not be dissolved till the completion of the defect liabilityperiod as stipulated in the Tender Document conditions of the works and till all the liabilitiesthereof are liquidated.

m) That, questions relating to validity and interpretation of this deed shall be governed by thelaws of India. Any disputes in interpretation of any conditions mentioned herein shall bereferred to Arbitrator by mutual consent of the parties to the JV and such proceedings shall begoverned by the Indian Arbitration and Conciliation act, 1996. The award of the Arbitratorshall be final and binding on the parties, hereto, neither the obligations of each party hereto toperform the contract nor the execution of works shall stop during the course of thesearbitration proceedings or as a result thereof.

n)That, no party to the JV has the right to assign any benefit, obligation or liability under theagreement to any third party without obtaining the written consent of the other partner andMIDC.

·· Bank account (s) in the name of the Joint Venture firm may be opened with anyNationalized / Scheduled Bank / Banks approved by GoM and the representatives ofboth partners are authorized to operate upon such accounts jointly.

p) That, the parties to the JV shall be responsible to maintain or cause to maintain properBooks of Accounts in respect of the business of the JV firm and the same shall be closed at

Page 47 Executive EngineerContractor

Page 50: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Books of Accounts in respect of the business of the JV firm and the same shall be closed atthe end of the every financial year.

q) That the financial year of the firm shall be the year ended on the 31 st day of March everyyear.

r) That upon closure of the books of account, balance sheet and profit and loss account, as tothe state of affairs of the firm, as at the end of the financial year and as to the profit or lossmade, or incurred by the firm for the year ended on that date respectively, shall be preparedand the same shall be subject to audit by a Chartered Accountant.

LEGAL JURISDICTION

All matters pertaining to or emanating from this JV agreement involving the owner shall besubject to jurisdiction or High Court of Judicature, at ...………..

NOTICE AND CORRESPONDANCE

All correspondence and notices to the JV shall be sent to the following address :

IN WITNESS WHERE TO the parties have caused their duly authorized representative to signbelow :

Signed for and on behalf of signed for and on behalf of

Witness

1.

2.

Page 48 Executive EngineerContractor

Page 51: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Maharashtra Industrial Develement Corporation(A Govt. of Maharashtra Undertaking)

FORM - A

Sr.No. Name of Equipment No. of units

1 Hot mix plant (capacity) DM-50

2 Sensor Paver 2 Nos.

3 Vibratory Roller. (30 MT) 2 Nos.

N

ote: 1) In case of hired plant and machinery, the copy of agreement shall be furnished along with documents ofownership in the name of person from whom machinery is hired.

2) In case, if the contractor do not possess - Hot mix asphalt plant with in 30 Km radius from site of work, then anundertaking on stamp paper of Rs.100 duly notarized shall be submitted by the contractor along with PQ form in envelopeNo. 1 for assurance towards erection of hot mix asphalt plant within 30 Km from the site of work not later than one monthfrom the date of work order, and separate DD of Rs.5,00,000/- as guarantee shall be submitted along with PQ form inenvelope No.1. Once the contractor erects the hot mix plant, within 30 Km radius from site of work, the amount of Rs.5.00lacs will be refunded.

Page 49 Executive EngineerContractor

Page 52: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

N

N

Page 50 Executive EngineerContractor

Page 53: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

(A Government of Maharashtra Undertaking)

FORM B-1

PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS

General Rules and Directions for the Guidance of contractors.

1.All works proposed to be executed by contract shall be notified in a form of invitation to tender pasted on a boardhung up in the office of the Executive Engineer, MIDC, Division, Akola and signed by the Executive Engineer,MIDC Dn.

This form will state the work to be carried out as well as the date for submitting and opening tenders, and the timeallowed for carrying out the work, also the amount of earnest money to be deposited with the tender and the amountof security deposit to be deposited by the successful tenderer, and the percentage, if any, to be deducted from bills. Itwill also state whether a refund of quarry fees, royalties, dues and ground rents will be granted. Copies of thespecifications, designs and drawings, estimated rates, scheduled rates and any other documents required inconnection with the work shall be signed by the Executive Engineer for the purpose of identification and shall also beopen for inspection by contractors at the office of the Executive Engineer during office hours.

Where the works are proposed to be executed according to the specifications recommended by a contractor andapproved by a competent authority on behalf of MIDC such specifications with designs and drawings shall form partof the accepted tender.

2. In the event of the tender being submitted by a firm, it must be signed separately by each partner thereof, and inthe event of the absence of any partner, it shall be signed on his behalf by a person holding a power of attorneyauthorising him to do so.

3. Receipts for payments made on account of any work, when executed by a firm, should also be signed by all thepartners except where the contractors are described in their tender as a firm, in which case the receipt shall be signedin the name of the firm's one of the partners, or by some other person having authority to give official receipts for thefirm.

4. Any person who submits a tender shall fill up the usual printed form stating at what percentage above or below therates specified in Schedule 'B' (memorandum showing items of work. to be carried out) he is willing to undertake thework. Only one rate or such percentage on all the estimated rates/ scheduled rates shall be named. Tenders whichpropose any alterations in the works specified in the said form of invitation to tender, or in the time allowed forcarrying out the work, or which contain any other conditions, of any sort will be liable for rejection. No printed formof tender shall include a tender for more than one works but if contractor who wish to tender for two or more works,they shall submit separate tender for each work.

5. The Superintending/ Executive Engineer or his duly authorised Assistant shall open tenders in the presence of

Page 51 Executive EngineerContractor

Page 54: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

contractors who have submitted tenders or their representatives who may be present at the time, and he will enter theamounts of the several tenders in a comparative statement in a suitable form. In the event of a tender being accepted,the contractor shall, for the purpose of identification, sign copies of the specifications and other documentsmentioned in Rule 1. In the event of tender being rejected. the Divisional/ Competent officer shall authorise theScheduled Bank concerned to refund the amount of earnest money deposited to the contractor making the tender, onhis giving a receipt for the return of the money.

6. The officer competent to dispose of the: tenders shall have the right of rejecting all or any of the tender withoutassigning any reason thereof.

7. No receipt for any payment alleged to have been made by a contractor in regard to any matter relating to thistender or the contract shall be valid and binding on MIDC unless it is signed by the Executive Engineer.

8. The memorandum of work to be tendered for and the schedule of materials to be supplied by MIDC and their ratesshall be filled in and completed by the office of the Executive Engineer, before the tender form is uploaded. If a formwhich has not been so filled in and completed, contractor shall request the said office through query to have this donebefore he completes and submits his tender.

9. All works shall be measured net by standard measure and according to the rules and customs of MIDC and theirrates shall be without reference to any local custom.

10. Under no circumstances shall any contractor be entitled to claim enhanced rates for any items in this contract.

11. The measurements of work will be taken according to the usual methods in use in MIDC and no proposals toadopt alternative methods will be accepted. The Executive Engineer's decision as to what is the usual method in usein the MIDC will be final.

12. The contractor shall comply with the provision of the Apprentices Act 1961 and the rules and orders issuedthere under from time to time. If he fails to do so, his failure will be a breach of the contract and the SuperintendingEngineer, may in his discretion, cancel the contract. The contractor shall also be liable, for any pecuniary liabilityarising on account of any violation by him of the provisions of the Act.

Page 52 Executive EngineerContractor

Page 55: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

========================================================================

MEMORANDUM

a Name of work Providing LBM ,50 mm th. DBM with 25 mmth.SDBC to MIDC internal road G-H-I & Constructionof WBM road for partial length with Strengthning , 50mm thick semi grout with 20 mm thick PSS toPentakali Jackwell road at Chikhali Growth Centre

b Estimated Cost Rs. 1,28,50,998.00

c E.M.D. Rs. 1,00,000.00 by DD / RTGS of Nationalized

Bank / Scheduled Bank/ Bank approved byGovernment of Maharashtra payable at in favour ofExecutive Engineer, MIDC, Division, Akola

d Security Deposit Initial SD Rs. 3,85,600.00 or 3.00 % of tendered cost

whichever is higher by DD / RTGS of NationalizedBank / Scheduled Bank/ Bank approved byGovernment of Maharashtra. S. D. inform of BG willbe accepted when amount of S.D. is more thanRs.50,000/-

Rs.8,99,600.00 or 7.00 % of tendered costwhichever is higher through RA bills.

Total SD Rs. 12,85,200.00 or 10.00 % of tendered costwhichever is higher.

e Percentage, if any, to be deductedfrom bills so as to make up the totalamount required as security deposit

7 %

f Compensation for non-completion ofwork in time/slow progress of work,for every day the work is carried out atdisproportionately slow rate

Rs. 3000 per day

g Time allowed for the work from thedate of written order to commence thework.

6 Months Including monsoon

Page 53 Executive EngineerContractor

Page 56: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

I/We hereby tender for the execution of above stated work for Maharashtra Industrial Development Corporation(hereinafter referred to as MIDC) at (in figures) _____________________________________ percentabove/below. (in words) ________________________________________________ _percent above/below. Theestimated rates entered in Schedule B (memorandum showing items of work to be carried out) & in accordance withall specifications, designs, drawings, instructions & rules, terms & conditions of contract as hereinabove &hereinafter included in these documents & agree that when materials are provided by the MIDC, such material & therates to be paid for them shall be as provided in Schedule A hereto. Should this tender be accepted, I/We herebyagree to abide by & fulfill all the terms & conditions of contract annexed hereto & in default thereof to forfeit & payto MIDC the sums of money mentioned in the said conditions. Demand Draft No. _________________dated_____/ / _____from the bank ________________in respect of the sum of Rs.(in figures) _____________ &(in words) _______________________________________________________ is herewith forwarded, towards thecost of blank tender form, which is non-refundable.Demand Draft No. dated / / from thebank___________________________in respect of the sum of Rs.(in figures) _____________________ & (in words)________________________________ _____________________________________________ is herewithforwarded, representing the earnest money, full value of which is to be absolutely forfeited to MIDC should I/We donot deposit the full amount of security deposit specified in the above memorandum, in accordance with Clause I(A)of the Contract Conditions; otherwise the said earnest money shall be refunded to us.

Signature of witness: Signature of the contractor.

Address: Address:

Occupation:

Date: Date:

The above tender is hereby accepted by me on behalf of the MIDC______ at % above/ below the estimated cost.

Place: Executive EngineerDate:

Maharashtra Industrial Development Corporation

Page 54 Executive EngineerContractor

Page 57: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

CONDITION OF CONTRACT

CLAUSE 1; Securiy deposit: The person(s) whose tender may be accepted (hereinafter called the contractor, whichexpression shall unless excluded by or repugnant to the context include his heirs, executors, administrators &assigns) shall A) within 10 days (which may be extended by the Suptd. Engineer concerned upto 15 days if theSuperintending Engineer thinks fit to do so) of the receipt by him of the notification of the acceptance of his tender,deposit with the Exe. Engineer in cash to the Exe. Engineer (if deposited for more than 12months) of sum sufficientwhich will make up the full security deposit specified in the tender or B) Permit MIDC at the time of making anypayment to him for work done under the contract to deduct such as will amount (*% of all money so payable)suchdeductions to be held by MIDC by way of Security deposits) provided always that in the event of the contractordepositing a lump sum by way of security deposit as contemplated at (A) above, then & in such case, if the sum sodeposited shall not amount to 10.00 % of the total estimated cost of the work, it shall be lawful for MIDC at the timeof making any payment to the contractor for work done under the contract to make up the full amount of 10.00 % bydeducting a sufficient sum from every such payment at last aforesaid until the full amount of the security deposit ismade up. All compensation or other sums of money payable by the contractor to MIDC under the terms of hiscontract may be deducted from or paid by the sale of sufficient part of his security deposit or from interest arisingthere from or from any sums which may be due or may become due by MIDC to the contractor under any othercontract or transaction of any nature, on any account whatsoever & in the event of his Security deposit being reducedby reasons of any such deductions or sale as aforesaid, the contractor shall, within 10 days thereafter, make good incash as aforesaid any sum(s) which may have been deducted from (* or raised by sale of his security deposit) or anypart thereof.

If the amount of security deposit to be paid in a lump sum within the period specified at (A) above is not paidthe tender/contract already accepted shall be considered as cancelled & legal steps taken against the contractor forrecovery of the amount.

* [NOTE: This will be the same percentage as that in the tender at (f)]

CLAUSE 2; Compensation for delay: The time allowed for carrying out the work as entered in the tender shall bestrictly observed by the contractor & shall be reckoned from the date on which the order to commence work is givento the contractor. The work shall throughout the stipulated period of the contract be proceeded with, with all duediligence (time being deemed to be of the essence of the contract on the part of the contractor). In the event of thecontractor failing to comply with this condition he shall be liable to pay as compensation an amount of Rs. 3000 perday or such amount upto 1% as Suptd. Engineer (whose decision in writing shall be final) may decide, of the amountof the estimated cost of the whole work as shown by the tender for each day that the work remainsuncommenced /unfinished, after the proper date. And further to ensure good progress during the execution of thework, the contractor shall be bound, in all the cases in which the time allowed for any work exceeds 1 month tocomplete:

25% of the work in 25 % of the time

50% of the work in 50% of the time

75% of the work in 75% of the time

Page 55 Executive EngineerContractor

Page 58: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

100% of the work in 100% of the time

Note: The quantity of work to be done within a particular time to be specified above shall be fixed by the officercompetent to accept the contracts after taking into consideration the circumstances of each case and inserted in theblank space kept for the purpose & abide by the programme of detailed progress laid down by the Exe. Engineer.

In the event of contractor failing to comply with this condition, he shall be liable to pay as compensation an amountof Rs. 3000 per day or such amount upto 1% as Suptd. Engineer (whose decision in writing shall be final) maydecide of said estimated cost of the whole work for every day that the due quantity of work remains incomplete,provided always that the total amount of compensation to be paid under the provisions of this clause shall not exceed10% of the estimated cost of the work as shown in the tender.

CLAUSE 3: In any case in which under any clause(s) of this contract, the contractor shall have rendered himselfliable to pay compensation amounting to the whole of this security deposit (whether paid in one sum or deducted byinstallments) or in case of the abandonment of work owing to serious illness or death of the contractor or any othercause the Exe. Engineer on behalf of MIDC shall have power to adopt any of the following courses, as he may deembest suited to the interest of MIDC:-

Action when whole of security deposit is forfeited.

a) To rescind the contract (of which rescission notice in writing to the contractor under the hand of the Exe.Engineer shall be conclusive evidence) & in that case the security deposit of the contractor shall stand forfeited & beabsolutely at the disposal of MIDC.

b) To carry out the work or any part of the work departmentally debiting the contractor with the cost of the work,expenditure incurred on the tools & plants, & charges on additional supervisory staff including the cost of workcharged establishment employed for getting the unexecuted part of the work completed & crediting him with thevalue of the work done departmentally in all respects in the same manner & at the same rates as if it had been carriedout by the contractor under the terms of his contract. The certificate of Exe. Engineer, as to the cost & other alliedexpenses so incurred & as to the value of the work so done departmentally shall be final & conclusive against thecontractor.

c) To order that the work of the contractor be measured up & to take such part thereof as shall be unexecuted out ofhis hands & to give it to another contractor to complete in which case all expenses incurred on advertisement forfixing a new contracting agency additional supervisory staff including the cost of work charged establishment & costof the work executed by the new contract agency will be debited to the contractor & the value of the work done orexecuted through the new contractor shall be credited to the contractor in all respects & in the same manner & at thesame rates as if it had been carried out by the contractor under the terms of his contract. The certificate of the Exe.Engineer as to all the cost of the work & other expenses incurred as aforesaid for or in getting the unexecuted workdone by the new contract & as to the value of work so done shall be final & conclusive against the contractor.

In case the contract shall be rescinded under clause:

a) above, the contractor shall not be entitled to recover or be paid any sum for any work therefor, actually performed

Page 56 Executive EngineerContractor

Page 59: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

by him under this contract unless & until the Exe. Engineer shall have certified in writing the performance of suchwork & the amount payable to him in respect thereof, & he shall only be entitled to be paid the amount so certified.In the event of either of the courses referred to in clauses

b) or c) being adopted & the cost of the work executed departmentally or through a new contractor & other alliedexpenses exceeding the value of such work credited to the contractors, the amount of excess shall be deducted fromany money due to the contractor by MIDC under the contract or otherwise howsoever or from his security deposit orthe sale proceed thereof provided. However, the contractor shall have no claim against MIDC even if certified valueof the work done departmentally or through a new contractor, exceeds the certified cost of such work & alliedexpenses, provided always that whichever of the three courses mentioned in clause a), b) or c) is adopted by the Exe.Engineer the contractor shall have no claim to compensation for any loss sustained by him by reason of his havingpurchased or procured any materials, or entered into any engagements or made any advances on account of or with aview to the execution of the work or the performance of the contract.

The certificate of the Executive Engineer as to all cost of the work done by the new contractor and as to thevalue of the work so done and shall be final and conclusive against the contractor.

CLAUSE 4; Action when the progress of any particular portion of the work is unsatisfactory: If the progress of anyparticular portion of the work is unsatisfactory the Exe. Engineer shall, notwithstanding that the general progress ofthe work is in accordance with the conditions mentioned in Clause 2, be entitled to take action under Clause 3(b)after giving the contractor 10 days notice in writing. The contractor will have no claim for compensation, for any losssustained by him owing to such action.

CLAUSE 5; Contractor shall remain liable to pay compensation if action not taken under Clauses 3 & 4. Power totake possession of or require removal of, or sell contractor's plant: In any case in which any of the powers conferredupon the Exe. Engineer by Clauses 3 & 4 hereof shall have become exercisable & the same shall not have beenexercised, the non exercise thereof shall not constitute a waiver of any of the conditions hereof & such powers shallnotwithstanding be exercisable in the event of any future case of default by the contractor for which under any clause(s) hereof he is declared liable to pay compensation amounting to the whole of his security deposit & the liability ofthe contractor for past & future compensation shall remain unaffected. In the event of the Exe. Engineer taking actionunder sub-clause a) or c) of Clause 3: he may, if he so desires, take possession of all or any tools, plant, materials &stores, in or upon the works or the site thereof or belonging to the contractor, or procured by him & intended to beused for the execution of the work or any part thereof, paying or allowing for the same in account at the contractrates, or in the case of contract rates not being applicable at current market rates, to be certified by the Exe. Engineerwhose certificate thereof shall be final. In the alternative the Exe. Engineer may, after giving notice in writing to thecontractor or his clerk of the works, foreman or other authorised agent, require him to remove such tools, plant,materials or stores from the premises within a time to be specified in such notice; & in the event of the contractorfailing to comply with any such requisition, the Exe. Engineer may remove them at the contractor's expense or sellthem by auction or private sale on account of the contractor & at his risk in all respects & the certificateof the Exe. Engineer as to the expense of any such removal, & the amount of the proceeds & expense of any suchsale shall be final & conclusive against the contractor.

CLAUSE 6; Extension of time: If the contractor shall desire an extension of the time for completion of the work onthe ground of his having been unavoidably hindered in its execution or on any other ground, he shall apply in writing

Page 57 Executive EngineerContractor

Page 60: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the ground of his having been unavoidably hindered in its execution or on any other ground, he shall apply in writingto the Exe. Engineer before the expiration of the period stipulated in the tender or before the expiration of 30 daysfrom the date on which he was hindered as aforesaid or on which the case for asking for extension occurred, which,is earlier ever & the Exe. Engineer may, if, in his opinion, there are reasonable grounds for granting an extension,grant such extension as he thinks necessary or proper. The decision of the Exe. Engineer in this matter shall be final.

CLAUSE 7; Final certificate: On completion of the work, the contractor shall be furnished with a certificate by theExe. Engineer (hereinafter called the Engineer-in-charge) of such completion, but no such certificate shall be givennor shall the work be considered to be complete until the contractor shall have removed from the premises on whichthe work shall have been executed all scaffolding, surplus materials & rubbish, & shall have cleaned off the dirt fromall woodwork, doors, windows, walls, floor or other parts of any buildings, in or upon which the work has beenexecuted, or of which he may have had possession for the purpose of executing the work, nor until the works shallhave been measured by the Engineer-in-charge or where the measurements have been taken by his subordinates untilthey have received the approval of the Engineer-in-charge, the said measurements being binding & conclusiveagainst the contractor. If the contractor shall fail to comply with the requirements of this clause as to the removal ofscaffolding, surplus materials & rubbish, & cleaning off dirt on/before the date fixed for the completion of the work,the Engineer-in-charge may, at the expense of the contractor, remove such scaffolding, surplus materials & rubbish& dispose of the same as he thinks fit & clean off such dirt as aforesaid & the contractor shall forthwith pay theamount of all expense so incurred, but shall have no claim in respect of any such scaffolding or surplus materials asaforesaid except for any sum actually realised by the sale thereof.

CLAUSE 8; Payments on intermediate certificates to be regarded as advances: No payment shall be made for anywork, estimated to cost less than rupees one thousand till after the whole of the work shall have been completed & acertificate of completion given. But in the case of works estimated to cost more than rupees one thousand, thecontractor shall, on submitting a monthly bill therefor, be entitled to receive payment proportionate to the part of thework then approved & passed by the Engineer-in-charge, whose certificate of such approval & passing of the sum sopayable shall be final & conclusive against the contractor. All such intermediate payments shall be regarded aspayments by way of advance against the final payments only & not as payments for work actually done &completed, & shall not preclude the Engineer-in-charge from requiring any bad, unsound, imperfect or unskillfulwork to be removed or taken away & reconstructed or re-erected, nor shall any such payment be considered as anadmission of the date performance of the contract or any part thereof in any respect or the accruing of any claim, norshall it conclude, determine, or affect in any other way the powers of the Engineer-in-charge as to the final settlement& adjustment of accounts or otherwise, or in any other way vary or affect the contract. The final bill shall besubmitted by the contractor within one month of the date fixed for the completion of the work, otherwise, theEngineer-in-charge's certificate of the measurements & of the total amount payable for the work shall be final &binding on all parties.

CLAUSE 9; Payment at reduced rates on account of items of work not accepted as completed to be at the discretionof Engineer-in-charge: The rates for several items of works estimated to cost more than Rs.1000/- agreed to within,shall be valid only when the item concerned is accepted as having been completed fully in accordance with thesanctioned specifications. In cases where the items of work are not accepted as so completed the Engineer-in-chargemay make payment on account of such items at such reduced rates as he may consider reasonable in the preparationof final or on account bills.

CLAUSE 10; Bills to be submitted monthly: A bill shall be submitted by the contractor each month on or before thePage 58 Executive EngineerContractor

Page 61: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

of final or on account bills.

CLAUSE 10; Bills to be submitted monthly: A bill shall be submitted by the contractor each month on or before thedate fixed by the Engineer-in-charge for all work executed in the previous month, & the Engineer-in-charge shalltake or cause to be taken the requisite measurement for the purpose of having the same verified, & the claim, so faras it is admissible, shall be adjusted, if possible, within ten days from the presentation of the bill. If the contractordoes not submit the bill within the time fixed as aforesaid, the Engineer-in-charge may depute a subordinate tomeasure up the said work in the presence of the contractor or his duly authorised agent whose counter signature tothe measurement list shall be sufficient warrant, & the Engineer-in-charge may prepare a bill from such list whichshall be binding on the contractor in all respects.

CLAUSE 11; Bills to be on printed forms: The contractor shall submit all bills on the printed forms to be had onapplication at the office of the Engineer-in-charge. The charges to be made in the bills shall always be entered at therates specified in the tender or in the case of any extra work ordered in pursuance of these conditions, & notmentioned or provided for in the tender, at the rate herein after provided for such work.

CLAUSE 12; Stores supplied by MIDC: If the specification or estimate of the work provides for the use of anyspecial description of materials to be supplied from the store of MIDC or if it is required that the contractor shall usecertain stores to be provided by the Engineer-in-charge (such material & stores, & the prices to be charged thereforeas hereinafter mentioned being so far as practicable for the convenience of the contractor but not so as in any way tocontrol the meaning or effect of this contract specified in the schedule or memorandum hereto annexed) thecontractor shall be supplied with such materials & stores as may be required from time to time to be used by him forthe purpose of the contract only, & the value of the full quantity of the materials & stores so supplied shall be set offor deducted from any sums then due, or thereafter to become due to the contractor under the contract, or otherwise,or from the security deposit, or the proceeds of sale thereof; of the security deposit is held in Government securities,the same of a sufficient portion thereof shall in that case be sold for the purpose. All materials supplied to thecontractor shall remain the absolute property of MIDC, & shall on no account be removed from the site of work, &shall at all times be open to inspection by the Engineer-in-charge. Any such materials unused & in perfectly goodcondition at the time of completion or termination of the contract shall be returned to MIDC store, if the Engineer-in-charge so requires by a notice in writing given under his hand, but the contractor shall not be entitled to return anysuch material except with consent of the Engineer-in-charge & he shall have no claim for compensation on accountof any such material supplied to him as aforesaid but remaining unused by him or for any wastage in or damage toany such materials.

CLAUSE 13; Works to be executed in accordance with specifications, drawings, orders etc.: The contractor shallexecute the whole & every part of the work in most substantial & workmanlike manner, both as regards materials &in every other respect in strict accordance with specifications. The contractor shall also conform exactly, fully &faithfully to the designs, drawings & instructions in writing relating to the work signed by the Exe. Engineer-in-charge & lodged in the office to which the contractor shall be entitled to have access for the purpose of inspection atsuch office, or on the site of work during the office hours. The contractor will be entitled to receive 3 sets of contractdrawings & working drawings as well as one certified copy of the accepted tender along with the work order free ofcost. Further copies of the contract drawings & working drawings if required by him shall be supplied at the rate ofRs.100 per No. of contract drawings & Rs.100 per No. of drawings except where otherwise specified.

CLAUSE 14; Alterations in specifications & designs not to invalidate contracts: The Engineer-in-charge shall have

Page 59 Executive EngineerContractor

Page 62: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

power to make any alterations in, or addition to, the original specifications, drawings, designs & instructions thatmay appear him to be necessary or advisable during the progress of work, & the contractor shall be bound to carryout the work in accordance with any instructions in this connection which may be given to him in writing signed bythe Engineer-in-charge & such alteration shall not invalidate the contract; & any additional work which thecontractor may be directed to do in the manner above specified as part of the work shall be carried out by thecontractor on the same conditions in all respects on which he agreed to do the main work & at the same rates as arespecified in the tender for the main work.

Rates for works not entered in estimate, for schedule of rates of the district: And if the additional & altered workincludes any class of work for which no rate is specified in this contract; then such class of work shall be carried outat the rates entered in the Schedule of Rates of the Division or at the rates mutually agreed upon between theEngineer-in-charge & the contractor, whichever are lower. If the additional or altered work, for which no rate isentered in the Schedule of Rates of the Division, is ordered to be carried out before the rates are agreed upon them,the contractor shall, within seven days of the date of receipt by him of the order to carry out the work, inform theEngineer-in-charge of the rate which he intends to charge for such class of work & if the Engineer-in-charge does notagree to this rate, he shall By Notice in writing be at liberty to cancel his order to carry out such class of work, &arrange to carry it out in such manner as he may consider advisable provided always that if the contractor shallcommence work or incur any expenditure in regard thereto before the rates shall have been determined as lastlyhereinbefore mentioned, then in such case he shall only be entitled to be paid in respect of the work carried out orexpenditure incurred by him prior to the date of the determination of the rate as aforesaid according to such rate(s) asshall be fixed by the Engineer-in-charge. In the event of the dispute, the decision of the Suptd. Engineer of the circlewill be final.

Where, however, the work is to be executed according to the designs, drawings & specifications recommended bythe contractor & accepted by the competent authority the alterations above referred to shall be within the scope ofsuch designs, drawings & specifications appended to the tender.

Extensions of time in consequence of additions or alterations: The time limit for the completion of the work shall beextended in the proportions that the increase in its cost occasioned by alterations/additions bears to the cost of theoriginal contract work & the certificate of the Engineer-in-charge as to such proportions shall be conclusive.

CLAUSE 15; No claim to any payment or compensation for alteration in, or restriction of work:

1. If at any time after execution of the contract documents the Engineer shall for any reason whatsoever (other thandefault on the part of the contractor for which MIDC is entitled to rescind the contract) desire that the whole or anypart of the work specified in the tender should be suspended for any period or that the whole or part of the workshould not be carried out at all he shall give to the contractor a notice in writing of such desire & upon the receipt ofsuch notice the contractor shall forth required after having the regard of the appropriate stage at which the workshould be stopped or suspended so as to cause any damage or injury to the work already done or endanger the safetythereon provided that the decision of the Engineer as to the stage at which the work or any part of it could be or couldhave been safely stopped or suspended shall be final & conclusive against the contractor. The contractor shall haveno claim to any payment or compensation whatsoever by reason of or in pursuance of any notice as aforesaid onaccount of any suspension, stoppage or curtailment except to the extent specified here in after.

Page 60 Executive EngineerContractor

Page 63: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

2. Where the total suspension of work ordered as aforesaid continued for continuous period exceeding 90 days, thecontractor shall be at liberty to withdraw from the contractual obligations under the contract so far as it pertains tothe unexecuted part of the work by giving 10 days prior notice in writing to the Engineer within 30 days of the expiryof the said period of 90 days of such intention are requiring the Engineer to record the final measurement of the workalready done & to pay the final bill. Upon giving such notice, the contractor shall be deemed to have been dischargedfrom his obligation to complete the remaining unexecuted work under this contract. On receipt of such notice theEngineer shall proceed to complete the measurement & make such payment as may be finally due to the contractorwithin a period of 90 days from receipt of such notice in respect of the work already done by the contractor. Suchpayment shall not in any manner prejudice the right of the contractor to any further compensation under theremaining provisions of this clause.

3. Where the Engineer requires the contractor to suspend the work for a period in excess of 30 days at any time or60 days in the aggregate, the contractor shall be entitled to apply to the Engineer within 30 days of resumption ofwork after such suspension for payment of compensation to the extent of pecuniary loss suffered by him in respect ofworking machinery rendered idle on the site or on account of his having had to pay the salary/wages of a labourengaged by him during the said period of suspension provided always that the contractor shall not be entitled to anyclaim in respect of any such working machinery, salary/wages for the first 30 days whether consecutive or in theaggregate of such suspension or in respect of any suspension where so ever occasioned by unsatisfactory work or anyother default on his part. The decision of the Engineer in this regard shall be final & conclusive against thecontractor.

4. In the event of.

i) Any total stoppage of work on notice from the Engineer under sub-clause(1) in that behalf.

ii) Withdrawal by the contractor from the contractual obligation to complete the remaining unexecuted work undersub-clause (2) on account of continued suspension of work for a period exceeding 90 days, iii) Curtailment in thequantity of item(s) originally tendered on account of any alteration, omission or substitutions in the specifications,drawings, designs or instructions under Clause 14(1) where such curtailment exceeds 25% in quantity & the value ofthe quantity curtailed beyond 25% at the rates for the item specified in the tender is more than Rs.5000/-. It shallbe open to the contractor, within 90 days from the service of... i) The notice of stoppage of work or; ii) Othernotice of withdrawal from the contractual obligations under the contract on account of the continued suspension ofwork or;

iii) Notice under Clause 15(i) resulting in such curtailment to produce to the Engineer satisfactory documentaryevidence of that he had purchased or agreed to purchase material for use in the contracted work before receipt by himof the notice of stoppage, suspension or curtailment & require MIDC to take over on payment such material at therates determined by the Engineer. Provided, however, that such rates shall in no case exceed the rates at which thesame were acquired by the contractor. The MIDC shall thereafter take over the material so offered, provided thequantities, offered, are not in excess of the requirements of the unexecuted work as specified in the accepted tenderand are of quality and specifications approved by the Engineer.

CLAUSE 15(A); No claim to compensation on account of loss due to delay in supply of material by MIDC: Thecontractor shall not be entitled to claim any compensation from MIDC for the loss suffered by him on account of

Page 61 Executive EngineerContractor

Page 64: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

delay by MIDC in the supply of materials entered in Schedule 'A' where such delay is caused by:

i) Difficulties relating to the supply of railway wagons.ii) Force majeure.iii) Act of God.iv) Act of enemies of the state or any other reasonable cause beyond the control of MIDC.

In the case of delay in the supply of materials MIDC shall grant such extension of time for the completion of theworks as shall appear to the Exe. Engineer to be reasonable in accordance with the circumstances of the case. Thedecision of the Exe. Engineer as to the extension of time shall be accepted as final by the contractor.

CLAUSE 15 (B); Time limit for unforeseen claims: Under no circumstances whatever shall the contractor be entitledto any compensation from MIDC on any account unless the contractors shall have submitted a claim in writing to theEngineer-in-charge within one month of the cause of such claim occurring.

CLAUSE 16; Action & compensation payable in case of bad work: If any time before the security deposit or any partthereof is refunded to the contractor it shall appear to the Engineer-in-charge or his subordinate in charge of thework, that any work has been executed with unsound, imperfect or unskillful workmanship or with materials ofinferior quality or that materials / articles provided by him for the execution of the work are unsound, or of a qualityinferior to that contracted for, or are otherwise not in accordance with the contract, it shall be lawful for the Engineer-in-charge to intimate this fact in writing to the contractor & then not with standing the fact that the work, materialsor articles complained of may have been inadvertently passed, certified & paid for, the contractor shall be bound toforthwith rectify, or remove & reconstruct the work so specified in whole or in part, as the case may require or if sorequired, shall remove the materials or articles so specified & provided other proper & suitable materials or articles athis own charge & cost & in the event of his failing to do so within a period to be specified by the Engineer-in-chargein the written intimation aforesaid, the contractor shall be liable to pay compensation at the rate of one percent on theamount of the estimate for every day not exceeding 10 days, during which the failure so continues & in the case ofany failure the Engineer-in-charge may rectify or remove & re-execute the work or remove & replace the materialsor articles complained of as the case may be at the risk & expense in all respects of the contractor. Should theEngineer-in-charge consider that any such inferior work or materials as described above may be accepted or madeuse of, it shall be within his discretion to accept the same at such reduced rates as he may fix therefore.

CLAUSE 17; Work to be open to inspection. Contractor or responsible agent to be present: All works under or incourse of execution or executed in pursuance of the contract shall at all times be open to the inspection & supervisionof the Engineer-in-charge & his subordinates, & the contractor shall at all times during the usual working hours, & atall other times at which reasonable notice of the intention of the Engineer-in-charge or his subordinate to visit thework shall have been given to the contractor, either himself be present to receive orders & instructions, or have aresponsible agent duly accredited in writing present for that purpose. Orders given to the contractor's duly authorisedagent shall be considered to have the same force & effect as if they had been given to the contractor himself.

CLAUSE 18; Notice to be given before work is covered up: The contractor shall give not less than five day's noticein writing to the Engineer-in-charge or his subordinate in-charge of the work before covering up or otherwise placingbeyond the reach of measurement any work in order that the same may be measured & correct dimensions thereoftaken before the same is so covered up or placed beyond the reach of measurement, & shall not cover up or place

Page 62 Executive EngineerContractor

Page 65: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

taken before the same is so covered up or placed beyond the reach of measurement, & shall not cover up or placebeyond the reach of measurement any work without the consent in writing of the Engineer-in-charge or hissubordinate in-charge of the work & if any work shall be covered up or placed beyond the reach of measurementwithout such notice having been given or consent obtained, the same shall be uncovered at the contractor's expense,& in default thereof no payment or allowance shall be made for such work or for the materials with which the samewas executed.

CLAUSE 19; Contractor liable for damage done & for imperfections: If during the period of 3 Year from the dateof completion as certified by the Engineer-in-charge pursuant to Clause-7 of the contract or 3 Year aftercommissioning the work, whichever is earlier in the opinion of the Exe. Engineer, the said work is defective in anymanner whatsoever, the contractor shall forthwith on receipt of notice in that behalf from the Exe. Engineer, dulycommence execution & completely carry out at his cost in every respect all the work that may be necessary forrectifying & setting right the defects specified therein including dismantling & reconstruction of unsafe portionsstrictly in accordance with & in the manner prescribed & under the supervision of the Exe. Engineer. In the event ofthe contractor failing or neglecting to commence execution of the said rectification work within the period prescribedtherefore in the said notice &/or to complete the same as aforesaid as required by the said notice, the Exe. Engineerget the same executed & carried out departmentally or by any other agency at the risk on account & at the cost ofcontractor. The contractor shall forthwith on demand pay to the MIDC the amount of such costs, charges & expensessustained or incurred by the MIDC of which the certificate of the Exe. Engineer shall be final & binding on thecontractor. Such costs, charges & expenses shall be deemed to be arrears of land revenue & in the event of thecontractor failing or neglecting to pay the same on demand as aforesaid without prejudice to any other rights &remedies of the MIDC the same may be recovered from the contractor as arrears of land revenue. The MIDC shallalso be entitled to deduct the same from any amount which may then be payable or which may thereafter becomepayable by the MIDC to the contractor either in respect of the said work or any other work whatsoever or from theamount of security deposit retained by MIDC (of which the certificate of the Engineer-in-charge shall be final) fromany sums that may then be due or may thereafter become due to the contractor; or from his security deposit or theproceeds of sale thereof, or of a sufficient portion thereof.

CLAUSE 20 Contractor to supply plant, ladders, scaffoldings etc.: The contractor shall supply at his own cost allmaterials (except such special materials, if any, as may, in accordance with the contract, be supplied from the MIDCstores) plant, tools, appliances, implements, ladders, cordage, tackles, scaffolding, & temporary works requisite orproper for the proper execution of the work, whether, in the original, altered or substituted form, & whether includedin the specifications, or other documents forming part of the contract or referred to in these conditions or not &which may be necessary for the purpose of satisfying or complying with the requirements of the Engineer-in-chargeas to any matter as to which under these conditions he is entitled to be satisfied, or which is entitled to requiretogether with carriage therefore, to & from the work.

Contractor is liable for damages arising from non-provisions of lights, fencing etc.

The contractor shall also supply without charge the requisite number of persons with the means & materialsnecessary for the purpose of setting out works, &, counting, weighing & assisting the measurement or examination atany time & from time to time of the work or the materials. Failing this the same may be provided by the Engineer-in-charge at the expense of the contractor & the expenses may be deducted from any money due to the contractor underthe contract or from his security deposit or the proceeds of sale thereof, or of a sufficient portion thereof. The

Page 63 Executive EngineerContractor

Page 66: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the contract or from his security deposit or the proceeds of sale thereof, or of a sufficient portion thereof. Thecontractor shall provide all necessary fencing & lights required to protect the public from accident, & shall also bebound to bear expenses of defense of every suit, action or other legal proceedings, that may be brought by anypersons for injury sustained owing to neglect of the above precautions, & to pay any damages & costs which may beawarded in any such suit, action or proceedings to any such person, or which may with the consent of the contractorbe paid for compromising any claim by any such person.

CLAUSE 21: The contractor shall provide suitable scaffolds & working platforms, gangways & stairways, & shallcomply with the following regulations in connections therewith.

a) Suitable scaffolds shall be provided for workmen for all work that cannot be safely done from a ladder or byother means

.b) A scaffold shall not be constructed, taken down, or substantially altered, except i)Under the supervision of a competent & responsible person; &

ii) as far as possible by competent workers possessing adequate experience in this kind of work.

c) All scaffolds & appliances connected therewith & all ladders shall :-

i) be of sound materials;

ii) be of adequate strength having regard to the loads & strains to which they will be subjected; &

iii) be maintained in proper condition

d) Scaffolds shall be so constructed that no part thereof can be displaced in consequence of normal use.

e) Scaffolds shall not be overloaded & so far as practicable the load shall be evenly distributed.

f) Before installing lifting gear on scaffolds special precautions shall be taken to ensure the strength & stabilityof the scaffolds.

g) Scaffolds shall be periodically inspected by a competent person.

h) Before allowing a scaffold to be used by his workmen the contractor shall, whether the scaffold has beenerected by his workmen or not, take steps to ensure that it complies fully with the regulations herein specified.

i) Working platforms, gangways & stairways shall :-

i) be so constructed that no part thereof can sag unduly or unequally.

ii) be so constructed & maintained, having regard to the prevailing conditions as to reduce as far as practicable risksof persons tripping or slipping; &

iii) be kept free from any unnecessary obstructions,

Page 64 Executive EngineerContractor

Page 67: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

iii) be kept free from any unnecessary obstructions,

j) In the case of working platforms, gangways, working places & stairways at a height exceeding eight feet.

i) every working platform & every gangway shall be closely boarded unless other adequate measure are taken toensure safety.

ii) every working platform & gangway shall have adequate width; &

iii) every working platform, gangway, working place & stairway shall be suitably fenced.

k) Every opening in the floor of a building or in a working platform shall, except for the time & to the extentrequired to allow the access of persons or the transport of shifting of material, be provided with suitable means toprevent the fall of persons or material.

l) When persons are employed on a roof where there is a danger of falling from a height exceeding six feetsuitable precautions shall be taken to prevent fall of persons or material,

m) Suitable precautions shall be taken to prevent persons being struck by articles which might fall from scaffoldsor other working places,

n) Safe means of access shall be provided to all working platforms & other working places.

CLAUSE 22: The contractor shall comply with the following regulations as regards hoisting appliances to be used byhim:a) Hoisting machines & tackles, including their attachments, anchorages & support shall:-

i) be of good mechanical construction, sound material & adequate strength & free from patent defect; &

ii) be kept in good repair & in good working order.

b) Every rope used in hoisting/lowering materials or as a means of suspension shall be of suitable quality, adequatestrength & free from patent defect.

c) Hoisting machines & tackle shall be examined & adequately tested after erection on the site & before use & bere-examined in position at intervals to be prescribed by the MIDC.

d) Every chain, ring, hook, shackle, swivel & pulley block used in hoisting/lowering materials or as a means ofsuspension shall be periodically examined.e) Every crane driver/hoisting appliance operator shall be properly qualified.

f) No person who is below the age of 18 years shall be in control of any hoisting machine including any scaffold orgive signals to the operator.

g) In the case of every hoisting machine & of every chain, ring, hook, shackle, swivel & pulley block used inhoisting/ lowering/ as a means of suspension the safe working load shall be ascertained by adequate means.

Page 65 Executive EngineerContractor

Page 68: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

h) Every hoisting machine & all gears referred to in the preceding regulation shall be plainly marked with thesafe working load.

i) In the case of a hoisting machine having a variable safe working load each safe working load & the conditionsunder which it is applicable shall be clearly indicated. j) No part of any hoisting machine or of any gear referredto in regulation (g) above shall be loaded beyond the safe working load except for the purpose of testing.

k) Motors, gearings, transmissions, electric wiring & other dangerous parts of hoisting appliance shall be providedwith efficient safeguards.

l) Hoisting appliances shall be provided with such means as will reduce to a minimum the risk of the accidentaldescent of the load.

m) Adequate precautions shall be taken to reduce to a minimum the risk of any part of a suspended load becomingaccidentally displaced.

CLAUSE 23: Measure for prevention of fire: The contractor shall not set fire to any standing jungle, trees,brushwood or grass without written permit from the Exe. Engineer.When such permit is given, & also in all caseswhen destroying cut or dug up trees, brushwood, grass etc. by fire, the contractor shall take necessary measures toprevent such fire spreading to or otherwise damaging surrounding property. The contractor shall make his ownarrangements for drinking water for the labour employed by him.

CLAUSE 24: Liability of contractor for any damage done in or outside work area: Compensation for all damagedone intentionally or unintentionally by contractor's labour whether in or beyond the limits of MIDC propertyincluding any damage caused by the spreading of fire mentioned in Clause 22 shall be estimated by the Engineer-in-charge or such other officer as he may appoint & the estimates of the Engineer-in-charge subject to the decision ofthe Suptd. Engineer on appeal shall be final & the contractor shall be bound to pay the amount of the assessedcompensation on demand failing which the same will be recovered from the contractor as damages in the mannerprescribed in Clause 1 or deducted by the Engineer-in-charge from any sums that may be due or become due fromMIDC to the contractor under this contract or otherwise.

The contractor shall bear the expenses of defending any action or other legal proceedings that may be brought by anypersons for injury sustained by him owing to neglect of precautions to prevent the spread of fire & he shall pay anydamages & cost that may be awarded by the court in consequence.

CLAUSE 25: Employment of female labour: The employment of female labourers on works in the neighbourhood ofsoldier's barracks should be avoided as far as possible.

CLAUSE 26: Work on Sundays: No work shall be done on a Sunday without the sanction in writing of the Engineer-in-charge.

CLAUSE 27: Work not to be sublet. Contract may be rescinded & security deposit forfeited for subletting it withoutapproval or for bribing a public officer or if contractor becomes insolvent: The contract shall not be assigned/subletwithout the written approval of the Engineer-in-charge. And if the contractor shall assign or sublet his contract, orattempt so to do or become insolvent or commence any proceeding to get himself adjudicated an insolvent or make

Page 66 Executive EngineerContractor

Page 69: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

any composition with his creditors, or attempt so to do or if any bribe, gratuity, gift, loan, perquisite, reward oradvantage, pecuniary or otherwise, shall either directly or indirectly be given, promised or offered by the contractor,or any of his servants or agents to any public officer or person in the employ of MIDC in any way relating to hisoffice or employment, or if any such officer or person shall become in any way directly or indirectly interested in thecontract, the Engineer-in-charge may thereupon by notice in writing rescind the contract, & the security deposit ofthe contractor shall thereupon stand forfeited & be absolutely at the disposal of MIDC & the same consequencesshall ensue as if the contract had been rescinded under Clause 3 hereof & in addition the contractor shall not beentitled to recover or be paid for any work therefore actually performed under the contract.

CLAUSE 28: Sum payable by way of compensation to be considered as reasonable compensation without referenceto actual loss: All sums payable by a contractor by way of compensation under any of these conditions shall beconsidered as a reasonable compensation to be applied to the use of MIDC without reference to the actual loss ordamage sustained, & whether any damage has or has not been sustained.

CLAUSE 29: Changes in the constitution of firm to be notified: In the case of tender by partners, any change in theconstitution of a firm shall be forthwith notified by the contractor to the Engineer-in-charge for his information.

CLAUSE 30: Works to be under direction of Suptd.Engineer: All works to be executed under the contract shall beexecuted under the direction & subject to the approval in all respects of the Superintending Engineer of the Circle forthe time being, who shall be entitled to direct at what point(s) & in what manner they are to be commenced, & fromtime to time carried on.

CLAUSE 31: Decision of Superintending Engineer to be final:Except where otherwise specified in the contract & subject to the powers delegated to him by MIDC under the Coderules then in force, the decision of the Suptd. Engineer of the Circle for the time being shall be final, conclusive &binding on all parties to the contract upon all questions relating to the meaning of the specifications, designs,drawings & instructions hereinbefore mentioned & as to the quality of workmanship, or materials used on the work,or as to any other question, claim, right, matter or thing whatsoever, if any way arising out of, or relating to thecontract, designs, drawings, specifications, estimates, instructions, orders or other conditions, or otherwise,concerning the works or the execution, or failure to execute the same, whether arising during the progress of work, orafter the completion or abandonment thereof.

CLAUSE 32: Stores of European/American manufacture to be obtained from MIDC: The contractor shall obtainfrom the MIDC's store all stores & articles of European or American manufacture which may be required for thework, or any part thereof or in making up any articles required therefor or in connection therewith unless he hasobtained permission in writing from the Engineer-in-charge to obtain such stores & articles elsewhere. The value ofsuch stores & articles as may be supplied to the contractor by the Engineer-in-charge will be debited to the contractorin his account at the rates shown in the Schedule in Form 'A' attached to the contract & if they are not entered in thesaid Schedule, they shall be debited to him at cost price which for the purposes of this contract shall include the costof carriage & all other expenses whatsoever, which shall have been incurred in obtaining delivery of the same at thestores aforesaid.

CLAUSE 33: Lump sums in estimates: When the estimate on which a tender is made, includes lump sums in respectof parts of the work, the contractor shall be entitled to payment in respect of the items of work involved or the part of

Page 67 Executive EngineerContractor

Page 70: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the work in question at the same rates as are payable under this contract for each items, or if the part of the work inquestion is not in the opinion of the Engineer-in-charge capable of measurement, the Engineer-in-charge may at hisdiscretion pay the lump amount entered in the estimate, & the certificate in writing of the Engineer-in-charge shall befinal & conclusive against the contractor with regard to any sum(s) payable to him under the provision of this clause.

CLAUSE 34: Action where no specification exists: In the case of any class of work for which there is no suchspecification as is mentioned in Rule 1 such work shall be carried out in accordance with the Divisional specification,& in the event of there being no Divisional specification, then in such case the work shall be carried out in allrespects in accordance with the instructions & requirements of the Engineer-in-charge.

CLAUSE 35: Definition of work: The expression "work(s)" where used in these conditions, shall, unless there besomething in the subject or context repugnant to such construction, be construed to mean the work(s) contracted to beexecuted under or in virtue of the contract, whether temporary or permanent & whether original, altered, substitutedor additional.

CLAUSE 36: Contractor's percentage whether applied to net or gross amounts of bill: The percentage referred to inthe tender shall be deducted from/added to the gross amount of the bill before deducting the value of any stockissued.

CLAUSE 37: Payment of quarry fees & royalties: All quarry fees, royalties, octroi, duties & ground rent for stackingmaterials, if any, should be paid by the contractor, as specified elsewhere in tender.

CLAUSE 38: Compensation under the Workmen's Compensation Act: The contractor shall be responsible for &shall pay any compensation to his workmen payable under the Workmen's Compensation Act, 1923 (VIII of 1923),hereinafter called the said Act) for injuries caused to the workmen. If such compensation is paid by MIDC asprincipal under sub-section (1) of section 12 of the said Act on behalf of the contractor, it shall be recoverable byMIDC from the contractor under sub-section (2) of the said section. Such compensation shall be recovered in themanner laid down in Clause 1 above.

CLAUSE 39: The contractor shall be responsible for & shall pay the expenses of providing medical aid to anyworkman who may suffer a bodily injury as a result of an accident. If such, expenses are incurred by MIDC the sameshall be recoverable from the contractor forthwith & be deducted without prejudice to any other remedy of MIDCfrom any amount due or that may become due to the contractor.

CLAUSE 40: The contractor shall provide all necessary personal safety equipment & first aid apparatus available forthe use of the persons employed on the site, shall maintain the same conditions suitable for immediate use at any time& shall comply with the following regulations in connection herewith :-

a) The workers shall be required to use the equipment so provided by the contractor & the contractor shall takeadequate steps to ensure proper use of the equipment by those concerned.

b) When work is carried on in proximity to any place where there is a risk of drowning, all necessary equipmentshall be provided & kept ready for use & all necessary steps shall be taken for the prompt rescue of any person indanger.

Page 68 Executive EngineerContractor

Page 71: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

c) Adequate provision shall be made for prompt first aid treatment of all injuries likely to be sustained during thecourse of the work.

CLAUSE 41: Claim for Quantities entered in the Tender or Estimate:

1.Quantities in respect of the several items shown in the tender are approximate & no revision in the tendered rateshall be permitted in respect of any of the items so long as, subject to any special provision contained in thespecifications prescribing different percentage of permissible variation, the quantity of the item does not exceed thetender quantity by more than 25% & so long as the value of the excess quantity beyond this limit at the rate of theitem specified in the tender is not more than Rs.5,000/-.

2.The contractor shall, if ordered in writing by the Engineer to do so, carry out any quantities in excess of the limitmentioned above in sub-clause (1) hereof, on the same conditions as & in accordance with the specifications in thetender & at the rates (i) derived from the rates entered in the current Schedule of Rates & in absence of suchrates, (ii) at the rate prevailing in the market. The said rate being increased/decreased as the case may be, by thepercentage which the total tendered amount bears to the estimated cost of the work as put to tender based onSchedule of Rates applicable to the year in which the tender was invited. For the purpose of operation of this clause,this cost shall be taken to be worked out from the DSR prevailing at the time at the acceptance of tender.

3.Claims arising out of reduction in the tender quantity of any item beyond 25% will be governed by theprovision of Clause 15 only, when the amount of such reduction beyond 25% at the rate of the itemspecified in the tender is more than Rs.5,000/-.(The clause is not applicable to extra items)

4. The clause is not applicable to extra items.

5.There is no change in the item rate if the excess is more than 25% of the tendered quantity but the valueof excess work at the tendered rate does not exceed Rs.5000/-

6.The quantities to be paid at tendered rate shall include

a) Tendered quantity plus

b) 25% excess of the tendered quantity or the excess quantity of the value of Rs.5000/- at the tenderedrates, whichever is more.

CLAUSE 42: Employment of famine affected labour: The contractor shall employ any famine, affected, convict orother labour of a particular kind or class if ordered in writing to do so by the Engineer-in-charge.

CLAUSE 43: Claim for compensation for delay in starting the work: No compensation shall be allowed for any delaycaused in the starting of the work on account of acquisition of land or, in the case of clearance works, on account ofany delay in according sanction to estimates.

CLAUSE 44: Claim for compensation for delay in the execution of work: No compensation shall be allowed for anydelay in the execution of the work on account of water standing in borrow pits or compartments. The rates areinclusive for hard or cracked soil, excavation in mud, sub-soil water or water standing in borrow pits & no claim for

Page 69 Executive EngineerContractor

Page 72: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

delay in the execution of the work on account of water standing in borrow pits or compartments. The rates areinclusive for hard or cracked soil, excavation in mud, sub-soil water or water standing in borrow pits & no claim foran extra rate shall be entertained, unless otherwise expressly specified.

CLAUSE 45: Entering upon or commencing any portion of work: The contractor shall not enter upon or commenceany portion of work except with the written authority & instructions of the Engineer-in-charge or of his subordinate-in-charge of the work. Failing such authority the contractor shall have no claim to ask for measurements of orpayment for work.

CLAUSE 46: Minimum age of persons employed, the employment of donkeys &/or other animals & the payment offair wages:

i) No contractor shall employ any person who is under the age of 18 years.

ii) No contractor shall employ donkeys or other animals with breaching of string or thin rope. The breaching must beatleast three inches wide & should be of tape (Nawar).

iii) No animal suffering from sores, lameness or emaciation or which is immature shall be employed on the work.

iv) The Engineer-in-charge or his agent is authorised to remove from the work any person/ animal found workingwhich does not satisfy these conditions & no responsibility shall be accepted by MIDC for any delay caused in thecompletion of work by such removal.

v) The contractor shall pay fair & reasonable wages to the workmen employed by him in the contract undertaken byhim. In the event of any dispute arising between the contractor & his workmen on the grounds that the wages paidare not fair & reasonable the dispute shall be referred without delay to the Exe. Engineer, who shall decide the same.The decision of the Exe. Engineer shall be conclusive & binding on the contractor but such decision shall not in anyway affect the conditions in the contract regarding the payment to be made by MIDC at the sanctioned tender rates.

vi) The contractor shall provide drinking water facilities to the workers. Similar amenities shall be provided to theworkers engaged on large work in urban areas.

CLAUSE 47: Method of payment: Payment to contractors shall be made by cheques drawn on any bank within theDivision convenient to them, provided the amount exceeds Rs.10. Amounts not exceeding Rs.10 will be paid in cash.

CLAUSE 48: Acceptance of conditions compulsory before tendering for work: Any contractor who does not acceptthese conditions shall not be allowed to tender for works.

CLAUSE 49: Employment of scarcity labour: If Government declares a state of scarcity or famine to exist in anyvillage situated within 10 miles of work, the contractor shall employ upon such parts of the work, as are suitable forunskilled labour, any person certified to him by the Exe. Engineer or be any person to whom the Exe. Engineer mayhave delegated this duty in writing to be in need of relief & shall be bound to pay to such persons wages not belowthe minimum which the Government may have fixed in this behalf. Any dispute which may arise in connection withthe implementation of this clause shall be decided by the Exe. Engineer whose decision shall be final & binding onthe contractor.

Page 70 Executive EngineerContractor

Page 73: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

CLAUSE 50: The prices quoted by the contractor shall not in any case exceed the control price if any fixed byGovernment or reasonable price which is permissible for him to charge a private purchaser for the same class &description of goods under the provisions of Hoarding & Profiteering Prevention Ordinance, 1943 as amended formtime to time. If the price quoted exceeds the controlled price or the price permissible under Hoarding & ProfiteeringPrevention Ordinance the contractor will specifically mention this fact in his tender along with the reasons forquoting such higher price. The purchaser at his discretion will in such case exercise the right of revising the price atany stage so as to conform with the controlled price on the permissible under the Hoarding & Profiteering PreventionOrdinance. This discretion will be exercised without prejudice to any other action that may be taken against thecontractor.

CLAUSE 51: The rates to be quoted by the contractor must be inclusive of sales tax/VAT, LBT etc. no extrapayment on this account will be made to the contractor.

CLAUSE 52: The contractor should as far as possible obtain his requirement of labour, skilled & unskilled from thenearest Employment Exchange.

CLAUSE 53: The provision regarding contractor's labours provisioning the Contract Labour (Regulation &Abolition) Act, 1970 with the Maharashtra Contract Labour (Regulation & Abolition) Rule, 1971 shall be binding onthe contractors. If the provision in the said Act contradicts with any of the provisions regarding Contractor's laboursin any of the clauses in this tender, the provisions in the Contract Labour (Regulation & Abolition) Act, 1970 withthe Maharashtra Labour (Regulation & Abolition) Rules, 1971 shall prevail.

CLAUSE 54: The contractor shall comply with the provisions of the Apprentices Act, 1961 & the rules & the ordersissued under these from time to time. If he/they fails to do so, the failure will be a breach of the contract & theSuperintending Engineer, may in his discretion, cancel the contract. The contractor shall be liable to him/them, of theprovisions of the Act.

CLAUSE 55: Supply of materials etc. by the contractors: The contractors are to provide every article (with theexceptions noted in Schedule 'A' attached) which may be necessary & requisite for the due & proper execution of theseveral works included in contract according to the true indent & measuring of the drawings & specifications takentogether which are to be signed by Exe. Engineer, MIDC, (hereinafter called the Exe. Engineer) & by the contractor(s) whether the same may or may not have been prescribed in the specifications or shown on the drawings providedhowever that the same are reasonable & obviously to be informed therefor. In case of any discrepancy between thedrawing & the specification the Exe. Engineer, shall decide which of the two is to be followed.

CLAUSE 56: Execution of work: The contractor shall set out the whole of the work as per approved drawings &details supplied to him & as per the instruction given during the execution of work by the Engineer-in-charge or hisagent, & shall rectify any errors, which may be found therein & shall provide all necessary labour & materials for thepurpose. The contractor shall also provide plants, labour & materials (with the exceptions noted in Schedule attachedwhich may be necessary & requisite for the works). The materials & workmanship are to be the best of theirrespective jobs. The contractor shall have the work in all respects clean & perfect at the completion thereof.

CLAUSE 57: Drawings & Specifications: Atleast 6 copies of the drawings & specifications submitted by theContractor & approved & signed by the Superintending Engineer shall be furnished by the Contractors to the MIDC

Page 71 Executive EngineerContractor

Page 74: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

& copies there of shall be kept on binding. Contractor's agent who is to be constantly kept on the ground by the Exe.Engineer, MIDC, under Schedule 'A' of the contract will supply plain MS rounds &/or TOR steel depending upon theavailability. As such, designs based on exclusive use Tor steel shall not be accepted.

CLAUSE 58: Control over works: The Exe. Engineer or his duly authorised representative have at all times access tothe works which are to be entirely under his control. He may require the Contractors to dismiss person in theContractor's employment upon the works if such person in his opinion is incompetent or misconducts himself & thecontractor shall forthwith comply with every such requirements.

CLAUSE 59: Materials left at site: All works & materials brought & left upon the site of the work either by thecontractor or by his orders for the purpose of forming part of the work are to be considered to be property of theMIDC, & the same shall not be removed or carried away by the Contractor or any other person, without the specialleave or consent in writing of the Exe. Engineer, but the MIDC shall not in any way be answerable for any loss ordamage which may happen to or in respect of any such work or materials on account of the same being lost or stolenor injured or damaged by weather or otherwise.

CLAUSE 60: Removal & substitution of materials: The Exe. Engineer, shall have full power to order the removalfrom the premises of the materials which in his opinion are not in accordance with the specifications & may employother persons to remove the same without having to be answerable or accountable for any loss or damage that may be

caused to such materials. The Exe. Engineer, shall also have full power to order other proper material to besubstituted & in case of default the Exe. Engineer, may cause the same to be supplied & all cost which be incurred insuch removal & substitution shall be borne by the contractor.

CLAUSE 61: Action in case of improper materials & workmanship: If in the opinion of the Exe. Engineer, any workor any part thereof is executed with improper materials or defective workmanship, the contractor shall when requiredby the Exe. Engineer, forthwith re-execute the same & substitute proper material & workmanship & in case ofdefault by the contractor in so doing within a week from the date of the requisition, the Exe. Engineer, shall have fullpower to employ other persons to re-execute the work & cost there of shall be borne by the contractor.

CLAUSE 62: Action & compensation payable in case of backlog/delay: If at any time before security deposit isrefunded to the Contractor, it shall appear to the Exe. Engineer or his subordinate in-charge of the work, that anyworks have been executed with unsound, imperfect or unskillful workmanship or with materials or articles providedby him for the execution of the work are unsound, or of a quality inferior to that contracted, it shall be lawful for theEngineer-in-charge to intimate this fact in writing to the Contractor & then not with standing the fact that the work,materials or articles complained or any have been inadvertently passed, certified & paid for, the contractor shall bebound to forthwith rectify or remove or reconstruct the work so specified in whole or in part, as the case may require,or if so required, shall remove the materials or articles so specified & provide other proper & suitable materials orarticles at his own charge & cost. In the event of his failing to do so within in the limit aforesaid, the Contractor shallbe liable, to pay compensation at the rate of 1 % on the amount of the estimated cost for every day not exceeding 10days, during which the failure so continues & in the event of any such failures as aforesaid the Engineer-in-chargemay rectify or remove & re-execute the work or remove & replace the material/articles complained of, as the casemay be, at the risk & expenses in all respects of the Contractor. Should the Engineer-in-charge consider that any suchinferior work or materials as described above is not acceptable, then it will be straight way rejected.

Page 72 Executive EngineerContractor

Page 75: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

CLAUSE 63: Performance & guarantee of the work or plant completed by the contractor: The contractor shall makegood & repair defects in materials & workmanship & performance etc. revealed in the finished work or the plantcompleted by him, for a period of 3 Year from the date of which final completion certificate, is issued by theEngineer-in-charge. The decision of the Engineer-in-charge as to the necessity of repairs shall be binding on thecontractor. If the contractor fails to maintain & keep in proper condition the work completed by him or if the planterected by him falls in performance of guarantee furnished by the contractor over the stipulated period ofmaintenance or performance, then the Engineer-in-charge shall be entitled to carry out the necessary repairs,departmentally or through another agency at the cost of contractor. The decision of Engineer-in-charge regarding theamount of the expenses incurred in carrying out the repairs shall be final & binding on the contractor. The Engineer-in-charge shall be entitled to forfeit the whole or any part of the security deposit towards the expenses incurred byhim in repairing the work completed by the contractor.

CLAUSE 64: Responsibility of contractor for damage or fire etc.: From the commencement of the work to thecompletion of the same, the work shall be under the Contractor's charge. The contractor shall be held responsible forany damage done to the same by fire or any other cause & they shall be liable to make good all such damages & tocarry out any repairs which may be rendered necessary to the same by fire or other causes & they are to hold theMIDC harmless from any claims for injuries to persons or structural damage, damage to property happening fromany neglect or default or want of proper care or misconduct on the part of the Contractor or any of their employeeduring the execution of the work.

CLAUSE 65: Execution of work included in the contract: The Exe. Engineer shall have full power to send workmenon the premises to execute fittings & other works not included in the Contract & for which the Contractors shallafford every reasonable facility during ordinary working hours, provided that such operations shall be carried on insuch a manner as not to impede the progress of the work included in the contract. The contractor shall not howeverbe responsible for any damage which may happen to or be occasioned in the execution of any such fittings or otherworks.

Page 73 Executive EngineerContractor

Page 76: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Maharashtra Industrial Development Corporation

Schedule A

Name Of Work : Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internal road G-H-I &Construction of WBM road for partial length with Strengthning , 50 mm thick semigrout with 20 mm thick PSS to Pentakali Jackwell road at Chikhali Growth Centre

Schedule showing (approx) the material to be issued to the contractor for works to be executed on thiscontract, & the rate at which they are to be charged.

Sr. No. Particulars Quantity

Rate at which theMaterial is to becharged to the

contractor with unit

Place ofDelivery

Unit

NILNIL NIL NIL NILNIL

TERMS & CONDITIONS FOR ISSUE OF MATERIAL UNDER SCHEDULE 'A'

1.Materials required in excess of the quantity may or may not be supplied by the Deptt.If not supplied, the contractor should make his own arrangements to provide the same,for which no extra claims will be entertained.

2.All materials remaining unused after the completion of the works should be returnedto the Department at the Departmental Store. For the materials remaining unused &not returned, recovery will be effective at twice the issue rate of the materials or theprevailing market rate at the time of completion of work, whichever is higher.

3.Considerable delay is likely to occur in getting the materials required to be conveyedby rail, whether such materials are to be supplied by the MIDC or by the contractorhimself. The contractor, therefore, should submit indent for his requirement sufficientlyin advance to allow for the period usually taken for supply of such material.

No responsibility can be accepted for such delays in regard to supply of these materials.Every assistance will be given to obtain the supplies as quickly as possible.

4.Contractor should check the materials before they are issued to him. Any complaintafter the material is accepted by him will not be entertained.

5.The contractor should make his own arrangements for storing, the material issued tohim, by constructing a pucca shed which should be leak proof & should protect againstmoist climates.

Page 74 Executive EngineerContractor

Page 77: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

moist climates.

6.All other materials not included in the above schedule will have to be procured by thecontractors from the open market at his own cost.

7.The contractor shall maintain a regular account of consumption of the material issuedto him by the Department, either at cost or free of cost & shall be produced when askedfor.

8.All conveyance charges including loading & unloading operations for bringing thematerials issued from the place of delivery to the site of work should be borne by thecontractor.

9.Weight of MS rounds that will be issued under Schedule 'A' will be computed on thebasis of following table.

Dia of Bar in mm. Weight in Kg/RM length

of bar

6 0.22

8 0.39

10 0.62

12 0.89

16 1.58

18 2.00

20 2.46

22 2.92

25 3.85

28 4.83

32 6.31

36 7.99

40 9.87

In case of dispute or delegations in diameters, computation of weights shall be made at

Page 75 Executive EngineerContractor

Page 78: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

a rate of 0.785 Kg/Sq.cm. of cross sectional area.

10.The issue of steel from the stores stipulated in Schedule 'A' shall be on the basis of

lengths of MS rounds measured in metric system to the nearest 10mm. length. The

surplus steel after completion of work shall also be taken back & measured on the same

basis. The MS rounds returned to the departmental store shall be in the form of cut

pieces of whole lengths remaining unutilised & will be accepted as such. Pieces of length

one metre & above shall accepted. The percentage waste in the form of pieces of length

below one metre shall not be more than 1% of the tonnage actually used in work. Any

additional loss beyond 1% stipulated above, shall be treated as used in an unauthorized

& wasteful manner, & recovery at double the issue rate or market rate, whichever is

more, shall be effected for such wasteful use of steel.

Page 76 Executive EngineerContractor

Page 79: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Schedule B

Maharashtra Industrial Development Corporation

Name Of Work : Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internal road G-H-I &Construction of WBM road for partial length with Strengthning , 50 mm thick semi groutwith 20 mm thick PSS to Pentakali Jackwell road at Chikhali Growth Centre

Name Of Sub Estimate : Providing LBM ,50 mm th. DBM with 25 mm th. SDBC to internal road G-H-IAmount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

22,995.00SquareMeter

5.004,599.00

Cleaning the old / fresh asphaltsurface with wire brushes, bristlesbrushes and gunny bags to receiveasphalt treatment.

1 Rupees FiveOnly

16,36,910.00CubicMeter

7,117.00230.00 Providing and laying Lean Mix BM(LBM) using VG 30 grade asphalt forfilling pot-holes and improvement ofexisting road surface whereverrequired including material, heatingasphalt, remixing it with stone metalin hot mix paver transporting andlaying, rolling and finishing etc.complete using metal grading as perTable No 500-4 of specification ofroad & bridges published by IRC etc.complete. (using asphalt @ 3.5% byweight of mix including tack coat overWBM surface With all leads ofasphalt and metal & rolling withvibratory roller etc

2 Rupees SevenThousand OneHundredSeventeen Only

Page 77 Executive EngineerContractor

Page 80: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

21,61,530.00SquareMeter

470.004,599.00

Providing and laying hot mix hot laidDense Bituminous Mcadam as per jobmix formula having 50 mmcompacted thickness with minimumbitumen content of 4.5% of theweight of the total mix of VG-30grade on prepared surface withspecified graded crushed aggregatesfor base/binding course includingloading of aggregates with front endloader, heating of binder, aggregatesand filler in hot mix plant,transportation the mix material bytippers and laying the mixed materialwith sensor pavers finisher to therequired level and grade, rolling byvibratory roller to achieve the desireddensity including all material, labour,machinery with all leads and lifts,lighting, guarding barricading andmaintenance of diversion if necessaryetc. complte. (including cost ofbitumen emulsion tack coat of 25kg /100 Sq. m.)

3 Rupees FourHundredSeventy Only

11,54,349.00SquareMeter

251.004,599.00

Providing and laying hot mixed hotlaid Semi Dense BituminousConcrete(SDBC) 25 mm thick usingVG 30grade asphalt / CRMB / PMBwith5.50% of asphalt by total weight ofmix including supplying of allmaterials, heating and mixingbitumen and chips, laying semi densebituminous concrete by hydrostaticpaver with sensor control includingtack coat by using VG 10 gradeasphalt at 5 kg/10m2 or emulsiongrade bitumen, conforming IS: 8887dose 2.50 kg / 10 m2 finishing,compaction with smooth wheeledtandem vibratory roller with all labourand materials .Including all leads ofmaterials etc. complete

4 Rupees TwoHundred FiftyOne Only

Page 78 Executive EngineerContractor

Page 81: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

2,36,300.00CubicMeter

425.00556.00 Earthwork in embankment withapproved material having field soakCBR not less than 8 and laboratorysoak CBR not less than 12 obtainedby the Contractor from his borrowareas including all lifts and leadsincluding laying in layers of 20cm to30cm for power roller and 45cm to60cm for vibratory compactor,breaking clods, and dressing to therequired lines, curves and sectionincluding payment of royalty chargesto the Govt. of Maharashtra. (Leadshall be certified by Dy. Engr.) a) For lead 20 km(Lead shown below only for thepurpose of estimate)

5 Rupees FourHundredTwenty FiveOnly

5,004.00CubicMeter

9.00556.00 Watering to OMC (16 kg to 24 kg ofwater per Cu.M.) The earth work inembankment in 20 cm to 30 cmlayers. (95% proctor density)

6 Rupees NineOnly

7,784.00SquareMeter

14.00556.00 Consolidation with proper ramming /rolling in layers the earthwork in embankment . (95% proctordensity)

7 RupeesFourteen Only

52,24,872.00Total Amount Rs :

Name Of Sub Estimate : Construction of WBM road for partial length & Strengthning to Pentakali Jackwellroad

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

53,580.00SquareMeter

6.008,930.00

Clearing jungle including uprooting,removing trunk vegetation, grass,bushes, trees up to 30 cm girth andremoval of rubbish up to a distance of50 m and stacking neatly outside theperiphery of the area cleared.

1 Rupees SixOnly

Page 79 Executive EngineerContractor

Page 82: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

1,10,500.00CubicMeter

85.001,300.00

Open excavation for road works, sidegutters water retaining structures andlarge excavated areas not involvingmanual lift of materials such as waterreservoir, foundation, dam seats andallied works in soils of all sorts, sandgravel, soft and hard murum andboulders not exceeding 0.03 Cu.M. insize, to required grade, camber andside slopes and conveying theexcavated material with all lifts andupto a lead of 100 m from outside theedge of excavated area, spreadingthe same on embankment or stackingas directed.

2 Rupees EightyFive Only

1,04,650.00CubicMeter

115.00910.00 Conveying material obtained fromroad cutting including all lifts, andbeyond initial lead, laying in layers of20cms to 30cms, in case ofpower roller and 45cms to 60cms incase of vibratory compactor,breaking clods, dressing to therequired lines, curves, grade andsection for formation of roads,including leveling, disposing offsurplus material in desired manner asdirected by Engineer-in-chargeetc. complete including taxes ,Royalty if any beyond 100 m initiallead. (Disposal or reuse location asshown on drawing)a) Lead up to 5 km.

3 Rupees OneHundred FifteenOnly

Page 80 Executive EngineerContractor

Page 83: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

10,03,000.00CubicMeter

425.002,360.00

Earthwork in embankment withapproved material having field soakCBR not less than 8 and laboratorysoak CBR not less than 12 obtainedby the Contractor from his borrowareas including all lifts and leadsincluding laying in layers of 20cm to30cm for power roller and 45cm to60cm for vibratory compactor,breaking clods, and dressing to therequired lines, curves and sectionincluding payment of royalty chargesto the Govt. of Maharashtra. (Leadshall be certified by Dy. Engr.)c) Any Lead (from 10 to 20 km)

4 Rupees FourHundredTwenty FiveOnly

18,315.00CubicMeter

9.002,035.00

Watering to OMC (16 kg to 24 kg ofwater per Cu.M.) The earth work inembankment in 20 cm to 30 cmlayers. (95% proctor density)

5 Rupees NineOnly

28,490.00CubicMeter

14.002,035.00

Consolidation with proper ramming /rolling in layers the earth work inembankment . (95% proctor density)b) With vibratory roller in 45 to 60cm layers

6 RupeesFourteen Only

2,35,200.00CubicMeter

1,050.00224.00 Supplying 50 mm to 75 mm trapstone oversize metal at the roadside including, conveying andstacking etc. complete including alltaxes and royalty and lead up to 20km.

7 Rupees OneThousand FiftyOnly

9,03,900.00CubicMeter

1,150.00786.00 Supplying 40 mm trap stone metalat the roadside including conveyingand stacking complete including alltaxes and royalty. Lead up to 20 kmcomplete.

8 Rupees OneThousand OneHundred FiftyOnly

Page 81 Executive EngineerContractor

Page 84: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

3,03,920.00CubicMeter

1,160.00262.00 Providing trap / stone / granite stonemetal at the work site as directed instacks of minimum size of 3 x 2 x 1m or as directed in stacks of highersizes than the minimum tipulatedabove Including all loading /unloading operation and conveyanceto the site of work lead up to 10 km.including all taxes and royaltycharges.d) Standard size 25 mm (Crushedaggregate)

9 Rupees OneThousand OneHundred SixtyOnly

1,13,408.00SquareMeter

16.007,088.00

Picking the old WBM surface up to adepth of 75 mm and re-sectioning,barreling and bringing the surface toproper camber, alignment, gradient,including providing V groove at theperiphery of road surface.

10 Rupees SixteenOnly

69,960.00CubicMeter

55.001,272.00

Spreading in compact layers oversizeand size metal to the requiredcamber and gradient.

11 Rupees FiftyFive Only

10,400.00CubicMeter

32.00325.00 Spreading hard murum, or blindagecollected in roadside stack over thetop of soling or oversize metal or sizemetal including evening it into top ofcrevices (Road side stacks of murumwill be measured including voidswithout deducting allowance forcompaction, separately and paid forunder relevant item of embankmentof road whichever is applicable.)

12 Rupees ThirtyTwo Only

10,080.00SquareMeter

6.001,680.00

Watering over sub-grade consistingof soling and / or oversize metal.

13 Rupees SixOnly

21,840.00SquareMeter

13.001,680.00

Consolidation over sub-gradeconsisting of soling and / or oversizemetal and hard murum by 8-10 tonneroller until proper interlockingetc. completeb) With 30 tonne vibratory roller

14 RupeesThirteen Only

Page 82 Executive EngineerContractor

Page 85: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

1,26,000.00SquareMeter

16.007,875.00

Watering over size metal andblindage during consolidation by 8-10 tonne roller over final surface ofsize metal and blindage untilproper interlocking etc. complete.

b) With 30 MT vibratoryroller/compactor

15 Rupees SixteenOnly

76,800.00SquareMeter

320.00240.00 Providing dry rubble pitching usingsufficiently large face stones ofapproved quality for an averagedepth of 225 mm including providingone header in one Sq.M. of pitchingarea complete, including all leads.a) Quarry rubble pitching

16 Rupees ThreeHundredTwenty Only

16,800.00SquareMeter

70.00240.00 Providing cement pointing for stonework using cement mortar 1:3proportion.

a) Flush Pointing

17 RupeesSeventy Only

7,830.00CubicMeter

145.0054.00 Excavation in trenches, pits, pipelines, foundations, column footings,walls etc. in earth’s soils of all types,gravel, sand, soft & hard murum, andboulders up to 0.03 cum. sizeincluding removing the excavatedmaterial upto a distance of 50 Mbeyond the edge of excavationincluding the initial lift of 1.5 M,stacking or spreading as directed,bailing of sub-soil water if anypreparing base for foundation etc.,and back filing the excavated pit ortrench using the excavated materialin layers including watering andramming as required or as directedby Engineer-In-charge, including alllabour and materials complete.

18 Rupees OneHundred FourtyFive Only

Page 83 Executive EngineerContractor

Page 86: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

5,850.00CubicMeter

325.0018.00 Excavation for trenches, pits,pipelines, foundations, columnfootings, walls etc. in soft rock andboulders between 0.03 TO 0.30 Cu.M.in size for a depth upto 1.5 Mincluding removing the excavatedmaterials upto a distance of 50 Mbeyond the edges of trenches / pitsetc. breaking the boulders into 225mm size rubble including stacking thesame (rubble as well as soft rock)and / or spreading as directed, bailingout water if any, preparing the bedfor foundations & necessary backfilling the excavated pit / trench asdirected by Engineer-in-charge alllabour and materials complete.

19 Rupees ThreeHundredTwenty FiveOnly

19,700.00Meter1,970.0010.00 Providing at the site of work andlowering, laying and jointing RCC NP2class pipes conforming to IS:458-1988 in prepared trenches ingrade and level, including hoisting,making rubber ring / collar joints incement mortar 1:1, including cost ofcollar / rubber ring, jointing materiallike cement, sand etc. and hydraulictesting of the pipes at factory as wellas on site as per the stipulation inrelevant IS code etc. complete.b) 600 mm diaRCC NP2 class

20 Rupees OneThousand NineHundredSeventy Only

41,150.00Meter4,115.0010.00 C ) 900 mm dia RCC NP2 class21 Rupees FourThousand OneHundred FifteenOnly

4,800.00CubicMeter

4,800.001.00 Providing and laying in position plaincement concrete using granite orblack trap graded metal includingmixing in a mechanically operatedmixer, dewatering, compacting,curing as required complete for alllifts up to a + 5 m. above or belowthe ground level where concrete isproposed, includingcentering/shuttering using ordinaryPortland cement.c) In 1:2:4 proportion.

22 Rupees FourThousand EightHundred Only

Page 84 Executive EngineerContractor

Page 87: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

56,800.00CubicMeter

7,100.008.00 Providing and laying in positionCement Concrete for RCC work usinggranite / black trap metal includingmixing in mechanically operatedmixers, compacting by mechanical ormanual means as may be requiredand directed by Engineer-In-Charge,including steel or plywood shuttering,centring, formwork dewatering, for allelements in foundation, plinths, ofbuilding works, where reinforcedcement concrete is proposed to beused upto +/-5 m from the averageground level including all labour andmaterial complete, finishing thesurface with 1:3 cement mortar. etccomplete.c) In 1:1.5:3 proportion by volume.

23 Rupees SevenThousand OneHundred Only

40,380.00MetricTonne

67,300.000.60 Providing and fixing in positionreinforcement of all dia for RCC piles,pile caps, footings, foundations,slabs, columns, beams, canopies,staircase, newels, chajjas, lintelspardis, copings, fins, arches etc. asper detailed designs, drawings andschedules including cutting, bending,hooking the bars, binding with wiresor tack welding and supporting asrequired at all locations and height alllabour and materials testing etc.complete.b ) Tor steel bars

24 Rupees SixtySevenThousand ThreeHundred Only

33,83,353.00Total Amount Rs :

Name Of Sub Estimate : Providing 50 mm thick semi grout with 20 mm thick PSS to Pentakali Jackwell roadAmount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

1,26,000.00SquareMeter

16.007,875.00

Picking the old WBM surface up to adepth of 75 mm and re-sectioning,barreling and bringing the surface toproper camber, alignment, gradient,including providing V groove at theperiphery of road surface.

1 Rupees SixteenOnly

Page 85 Executive EngineerContractor

Page 88: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

4,11,800.00CubicMeter

1,160.00355.00 Providing trap / stone / granite stonemetal at the work site as directed instacks of minimum size of 3 x 2 x 1m or as directed in stacks of highersizes than the minimum tipulatedabove Including all loading /unloading operation and conveyanceto the site of work lead up to 20 km.including all taxes and royaltycharges.a) Standard size 40 mm (HandBroken)

2 Rupees OneThousand OneHundred SixtyOnly

1,38,040.00CubicMeter

1,160.00119.00 d) Standard size 25 mm (Crushedaggregate)

3 Rupees OneThousand OneHundred SixtyOnly

1,34,470.00CubicMeter

1,130.00119.00 f) 12 mm size (crushed aggregate)4 Rupees OneThousand OneHundred ThirtyOnly

27,278.00CubicMeter

46.00593.00 Spreading metal on road surfacefrom 40 mm to 10 mm standard sizeand spreading evenly to requiredcamber and gradient with lead up to100 m from stacks.

5 Rupees FourtySix Only

47,250.00SquareMeter

6.007,875.00

Watering over sub-grade consistingof soling and / or oversize metal.

6 Rupees SixOnly

1,06,312.50SquareMeter

13.507,875.00

Rolling with 8 / 10 tonne vibratoryroller over 40 to 25 mm standard sizemetal to finish the surface to requiredcamber and gradient until properinterlocking.a) 8-10 tonne power roller

7 RupeesThirteen AndPaisa Fifty Only

12,43,715.00MetricTonne

56,532.5022.00 Supplying and stacking at works siteas directed 30 / 40, 60 / 70 and 80 /100 penetration grade asphalt in bulkconforming to IS:73-1992. For alllead of asphaltc) VG 10

8 Rupees FiftySix ThousandFive HundredThirty Two AndPaisa Fifty Only

4,840.00MetricTonne

220.0022.00 Heating asphalt to its boiling pointand evenly spreading it over roadsurface for grout treatment / tackcoats / seal coats.a ) Bulk asphalt

9 Rupees TwoHundredTwenty Only

Page 86 Executive EngineerContractor

Page 89: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Amount And Rate In (Rs)

Sr.No Item DescriptionQuantity Rate Unit AmountRate In Words

59,062.50SquareMeter

7.507,875.00

Rolling with 8 / 10 tonne vibratoryroller on the grouted surface.

10 Rupees SevenAnd Paisa FiftyOnly

15,92,325.00SquareMeter

202.207,875.00

Providing and laying 20 mm. thickpremix seal surfacing with all leads asdirected, preparing and cleaning thebase, heating aggregates at 0.27m3per 10m2 of aggregates of specifiedsize, mixing with heated asphalt 60 /70 grade / CRMB / PMB 22 kg. per10m2 in a hot mix plant andspreading over the surface to betreated after applying tack coat using80 / 100 grade asphalt dose 5kg/10m2 or bituminous emulsiongrade conforming to IS: 8887 dose2.50 kg / 10 m2, laying the mix sealsurfacing with hydrostatic paver withsensor control & compaction to thedesire level etc. complete.

A) By using penetration grade asphaltfor tack coat.

a)  Using VG 30 grade

11 Rupees TwoHundred TwoAnd PaisaTwenty Only

3,33,625.00CubicMeter

425.00785.00 Earthwork in embankment withapproved material having field soakCBR not less than 8 and laboratorysoak CBR not less than 12 obtainedby the Contractor from his borrowareas including all lifts and leadsincluding laying in layers of 20cm to30cm for power roller and 45cm to60cm for vibratory compactor,breaking clods, and dressing to therequired lines, curves and sectionincluding payment of royalty chargesto the Govt. of Maharashtra. (Leadshall be certified by Dy. Engr.)

c) Any Lead (from 10 to 20 km)

12 Rupees FourHundredTwenty FiveOnly

7,065.00CubicMeter

9.00785.00 Watering to OMC (16 kg to 24 kg ofwater per Cu.M.) The earth work inembankment in 20 cm to 30 cmlayers. (95% proctor density)

13 Rupees NineOnly

Page 87 Executive EngineerContractor

Page 90: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

10,990.00CubicMeter

14.00785.00 Consolidation with proper ramming /rolling in layers the earth work inembankment . (95% proctor density)b) With vibratory roller in 45 to 60cm layers

14 RupeesFourteen Only

42,42,773.00Total Amount Rs :

Schedule B -- Summary

Description Amount In RsSr.No.

Providing LBM ,50 mm th. DBM with 25 mm th. SDBC to internal road G-H-I 52,24,872.001

Construction of WBM road for partial length & Strengthning to Pentakali Jackwell road 33,83,353.002

Providing 50 mm thick semi grout with 20 mm thick PSS to Pentakali Jackwell road 42,42,773.003

Total

Say

1,28,50,998.00

1,28,50,998.00

Page 88 Executive EngineerContractor

Page 91: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

List of Amended Documents

Sr. No. Document Name

1 Value Added Tax (VAT) Act and Contract Labour, Income Tax Clause

Page 89 Executive EngineerContractor

Page 92: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

                                   MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

                                                                Item Specification

Work Name: Providing LBM ,50 mm th. DBM with 25 mmth. SDBC to MIDC internal road G-H-I &

Construction of WBM road for partial length with Strengthning , 50 mm thick semi grout with 20 mm

thick PSS to Pentakali Jackwell road at Chikhali Growth Centre

Sub Estimate: Providing LBM ,50 mm th. DBM with 25 mm th. SDBC to internal road G-H-I

1     Cleaning the old / fresh asphalt surface with wire brushes, bristles brushes and gunny bags to

receive asphalt treatment.

Specification:

 General : The item provides cleaning the old or fresh asphalt surface with wire bristle brush and

with gunny bags before applying new asphalt treatment.

 Equipment : The equipment such as small pick wire bristle brushes and gunny bags shall be

used for cleaning.

 Cleaning : Prior to the application of the binder, all dust, dirt, caked mud, animal dung, loose and

foreign material etc. shall be removed 30 cm on either side, beyond the full width to be treated, by

means of mechanical sweepers and blowers, if available or other wise with wire brushes, small

picks, brooms etc. the material so removed shall be disposed off as directed by the Engineer-in-

charge. The prepared surface shall be closed to traffic and maintained fully clean till the binder is

applied.

 Item to Include : The item includes all labour, equipment etc. required for cleaning the old or

fresh asphalt road surface as per above specifications.

 Mode of Measurement and Payment : The area of old or fresh asphalt road thus cleaned as per

the above specifications shall be measured in sqm. The contract rate shall be per sqm of asphalt

road cleaned. 2     Providing and laying Lean Mix BM (LBM) using VG 30 grade asphalt for filling pot-holes andimprovement of existing road surface wherever required including material, heating asphalt,remixing it with stone metal in hot mix paver transporting and laying, rolling and finishing etc.complete using metal grading as per Table No 500-4 of specification of road & bridges publishedby IRC etc. complete. (using asphalt @ 3.5% by weight of mix including tack coat over WBMsurface With all leads of asphalt and metal & rolling with vibratory roller etc Specification:

 General : The item pertains to providing and laying lean mix BM for filling potholes and

improvement of existing road surface.

 Materials : Binder shall be as specified and shall conform to IS : 73 and stone chipping shall

conform to grading as the Table below unless otherwise specified or directed by the Engineer-in-

Charge. The quantities of materials shall be as specified in Table below. Proper

Page 93: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

record will be kept to ensure that the daily out-turn of work is correlated with the quantity of

bitumen. Materials required per cum of compacted lean asphalt mix shall be as under :- Approx.

25 mm size metal 0.72 cum.

20 mm size metal 0.24 cum.

12 mm size metal 0.24 cum.

Asphalt Minimum 3.5% of total weight. Solvent 4 kg.

Rate of asphalt application for tack coat shall be 5 Kg./10 m2 The asphalt shall be evenly spread

over the surface at the rate specified. It will be further evened up by oil immersed brushes with

long handles to cover the entire surface with the asphalt.

Mixing : The mixing of stone and asphalt shall be done into power driven mixer or any other

suitable mixing machine, approved by the Engineer-in-Charge. Mixing shall be done till all the

aggregates are thoroughly coated. The required quantity of chips for each batch of mix shall be put

in the mixer through automatic arrangements provided through suitable measuring boxes of 3 Cum

capacity and the required quantity of asphalt will be added properly.

Laying : The premix so prepared shall be transported and laid on the road surface by means of

paving and finishing machine. The carpet shall be so laid as to give desired compacted thickness.

Before starting laying, tack coat shall be provided at 5 Kg/10 m2 to the cleaned old surface. The

conveyance of premix from mixing plant to site of laying will not be paid extra. All the depression

etc. noticed while the rolling is in progress shall be made good by adding premixed chips and

rolled again. The final surface so obtained shall be as specified by the Engineer-in-Charge. 60/70

penetration grade asphalt shall be used for tack coat only.

 Rolling :

i) The premix after laying properly on the road shall be rolled with 8 to 10 tonne roller. All

depressions etc. shall be made good by adding premix chips while rolling is in progress as

mentioned under laying above.

ii) The wheels of roller shall be wetted while rolling the premix.

iii) The road may be opened to traffic after 48 hrs.

 Special Requirements :

1. Test : Extraction test for the correct use of bitumen at the rate specified shall be done by the

contractor at his own cost from the mix prepared for laying selected at random by the Engineer-in-

Charge or his representative at least 4 times a day. If the rate  of bitumen specified varies, more

frequent tests are to be carried out. If the bitumen is less than that specified, worked out from

average of tests in a day, reduced rate will be paid. If however, the bitumen is found to be more, no

extra payment shall be made since the contractor is supposed to use exact quantity of bitumen as

specified.

2. Analysis of each type of aggregate as specified shall be made. If the material do not run

uniform, more frequent test shall be carried out.

3. Arrangement for carrying out these two tests shall be made by the contractor at of the work at

his own cost to exercise proper control over the preparation of aggregate and bitumen. The

tests should be carried out in the presence of the Engineer-incharge.

4. Compact mix density shall have equal to or greater than 95 of laboratory specimen grade in the

Page 94: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

given proportion.

5. In order to check the average thickness, trial area shall be laid with a known weight of material

in order to determine the area covered per tonne and daily check shall be made on the average

obtained with the assessed daily tonnage laid.

6. The item covers filling pot holes on the existing asphalt surface to make true to slope and

gradient of the surrounding road surface.

Mode of Measurement and Payment :

The actual consolidated volume of lean Mix/Bituminous Macadam shall be paid for. The rate shall

be for one cubic meter of compacted L.B.M. as per specification. Trial will be taken to check up the

percentage reduction in volume after consolidation to determine the actual quantity for payment.

For calculation, average depth of the pot holes and its area will be measured. No payment for tack

coat is payable as it is included in the item itself. 3     Providing and laying hot mix hot laid Dense Bituminous Mcadam as per job mix formulahaving 50 mm compacted thickness with minimum bitumen content of 4.5% of the weight of thetotal mix of VG-30 grade on prepared surface with specified graded crushed aggregates forbase/binding course including loading of aggregates with front end loader, heating of binder,aggregates and filler in hot mix plant, transportation the mix material by tippers and laying themixed material with sensor pavers finisher to the required level and grade, rolling by vibratory rollerto achieve the desired density including all material, labour, machinery with all leads and lifts,lighting, guarding barricading and maintenance of diversion if necessary etc. complte. (includingcost of bitumen emulsion tack coat of 25kg / 100 Sq. m.) Specification:

Specification  :-

This clause specifies the construction of Dense Graed Bituminous Macadam, (DBM), foruse mainly, but not exclusively, in base/binder and profile corrective course. And profile corrective courses, DBM is also intended for use as road base material. This work shallconsist of construction in a single or multiple layers of DBM on a previously prepared base or sub-base. The thickness of a single layer shall be 50mm to 100 mm.507.2 MaterialBitumen:       The bitumen shall be paving bitumen of penetration grade complying with IndianStandard Specifications for Paving Bitumen IS :79 and of penetration indicated in Table 500 10 fordense bitumen macadam. Or this bitumen as modified by one of the methods specified in clause521 or as otherwise specified in the contract. Guidance on the selection of as appropriate grade ofbitumen is given  in the manual of Construction and supervision of bituminous works.Coarse aggregates: The coarse aggregates shall consist of crushed rock, crushed gravel or otherhard material retained on the 2.36 mm sieve. They shall be clean, hard, durable, of cubical shapefree from dust and soft or friable matter organic or other delicious substances where thecontractors selected source of aggregates have poor affinity for bitumen as  a condition for theapproval of the sources, the bitumen shall be treated with an approved anti stripping agent as perthe manufactures recommendations without additional payment. Before approval of the source, theaggregate shall be tested for stripping the aggregates shall satisfy the physical requirementsspecified in table 5008 for dense bituminous macadam.            Where crushed gravel is proposed for use as aggregate, not less than 90% by weight ofthe crushed material retained on the 4.75 mm sieve shall have at least two fractured faces.507.2.3 :- Fine aggregates: Fine aggregates shall consist of crushed or naturally occurring

Page 95: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

mineral material or a combination of the two passing the 2.36 mm sieve and retained on the 75micron sieve. They shall be clean, hard durable dry and fre from dust and soft or friable matterorganic or other deleterious matter.            The fine aggregate shall have a san equivalent value of not less than 50 when tested inaccordance with the requirement of IS 2720 ( part 37)             The plasticity index of the fraction passing the 0.425 mm sleeve shall not exceed 4 whentested in accordance with IS 2720 (Part 5)Table 500-8 Physical requirements for coarse aggregate for Dense graged BituminousMacadam

Notes: 1         IS 2386 Part 1                                   5          IS 2386 Part 5            2          IS 2386 Part 1                                   6          IS 2386 Part 3                        (the elongation test to be done only on non flaky aggregates in the sample.)                        3          IS 2386 Part 4*                                 7          IS 6241            4          IS 2386 Part 4*                                 8          AASITTOT 283***            *          Aggregate may satisfy requirements of either of these two tests.            **        The water sensitivity test is only required if the minimum retained coating in thestripping test Is less than 95%.            507.2.4           Filler:            Filler shall consist of finely divide mineral matter such as rockdust hydrated lime or cement approved by the Engineer.                        The filler shall be graded within the limits indicated in Table 500-9.Table 500-9 Grading requirements for mineral filler

The filler shall be free from organic impurities and have plasticity index not greater     than 4. Theplasticity Index requirement shall not apply if filler is cement or lime. When the coarse aggregate isgravel 2 per cent. By weight of total aggregate shall be Portland cement or hydrated lime and the

Property Test Specification

Cleanliness(dust) Grain size analysis Max 5% passing 0.075mm

sieve

Particle shape Flakiness and Elongation

Index (combined)

Max 3%

Strength Los Angles Abrasion value

aggregate Impact value

Max 3%

Max3%

Durability Soundness

Sodium sulphate

Magnesium Sulphate

Max3%

Max3%

Water absorption stripping Water absorption Max3%

Stripping Coating and stripping of

Bitumen aggregate Mixtures

Minimum retained

Coating 95%

Water sensitivity Retained Tensite strength Max 8%

IS Sleve(mm) Cumulative per cent passing by weight of

total aggregate

0.6 100

0.3 95-100

0.075 85-100

Page 96: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

percentage of fine aggregate reduced accordingly. Cement or hydrated lime is not required whenthe limestone aggregate used. Where the aggregates fail to meet the requirements of the watersensitivity test in table 500-8 then 2 percent by total weight of aggregate of hydrated lime shall beaggaed without additional cost.507.2.5           Aggregate grading and binder content :           When tested in accordance with IS:2386 Part 1 ( wet sieving method) the combined grading of the coarse and fine aggregates andadded filler for the particulate mixture shall fall within the limits shown in Table 500-10 for densebituminous macadam grading 1 or 2 as specified in the contract the type and quantity of bitumenand appropriate thicknes are also indicated for each mixture type.Table 500-10 Composition of Dense garaged bituminous macadam pavement lavers

Notes:  1.       The combined aggregate grading shall not vary from the low limit on one sieve to thehigh limit on the adjacent sieve.            2.         Determined by marshal method507.3  Mixture Design507.3.1           Requirement for the mixture :    A part from conformity with the grading andquality requirements for individual ingredients the mixture shall meet the requirements set out inTable 500-11Table 500-11 Requirements for dense graded bituminous macadam

Grading 1 2

Nominal aggregate size 40mm 25mm

Layer thickness 80-100 mm 50-75 mm

Is sieve(mm) Cumulative % by weight of total aggregate passing

45 100

37.5 95-100 100

26.5 6-93 90-100

19 - 71-95

13.2 55-75 56-80

9.5 - -

4.75 38-54 38-54

2.36 28-42 28-42

118 - -

0.6 - -

0.3 7-21 7-21

0.15 - -

0.075 2-8 2-8

Bitumen content % by

Mass of totatl mix2

Min4.0 Min 4.5

Bitumen grade (pen) 65 or 90 65 or 90

Minimum Stability (KN at 60 C )

Minimum flow (mm)

9.0

2

Page 97: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

The requirements for minimum per cent voids in mineral aggregate (VMA) are set out in Table 500-12Table 500-12 Minimum percent voids in mineral aggregate (VMA)

Notes 1.         The nominal maximum particle size is one sixe larger than the first sieve to                         retained more than 10 percent            2.         Interpolate minimum voids in the mineral aggregate (VMA) for design air                         voids values between thing listed. 507.3.2           Binder content :      The binder content shall be optimizes to achieve therequirements of the mixture set out in table 500-11and the traffic volume specified in thecounteract. The marshal method For determining the optimum binder content shall be adopted as described in. The asphaltInstitute manual MS-2 replacing the aggregates retained on the 26.5 mm sieve by theaggregates passing the 26.5 m sieve retained on the 22.4 mm sieve where approved bythe Engineer.            Where 40 mm dense bituminous macadam mixture is specified the modifiedmarshal method described in MS-2 shall be used. This method requires modifiedequipment and procedures particularly the minimum stability values in Table 500-11 shallbe multiplied by 2.25 and the minimum flow shall be 3mm.507.3.3 Hob mix Formula :           The contractor shall inform the Engineer  in writing atleast 20 days before the start of the work of the jobs mix formula proposed for use in theworks, and shall give the flowing details.1)        Source and location of all materials2)        Proportions of all material expressed as follows where each is applicable            a) Binder type and percentage by weight of total mixture            b) coarse aggregate/Fine aggregate/Mineral filler as percentage by weight of total             aggregate including mineral filler .

Maximum flow (mm)

Compaction level (Number of blow)

Percent air voids

Percent voids in mineral aggregate (VMA)

Percent voids filled with bitumen(VEB)

4

75 blows on each of two faces of specimens

3-6

See table 500-12 below

Nominal Maximum

particle size(mm)

Minimum VMA percent related to Design air voids percent

3.0 4.0 5.0

9.5 14.0 15.0 16.0

12.5 13.0 14.0 15.0

19.0 12.0 13.0 14.0

25.0 11.0 12.0 13.0

37.5 10.0 11.0 12.0

Page 98: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

3)        A single definite percentage passing each sever for the mixed aggregate4)        The individual grading of the individual aggregate fractions and the proportion  of             each in the combined grading.5)        The results of test enumerated in Table 500-11 as obtained by the contractor.6)        Where the mixer is a bates mixer the individual weight of each type of aggregate             and binder per batch.7)        Test results of physical characteristics of aggregate to be used.8)        Mixing temperature and compacting temperature.While establishing the job mix formula the Contractor shall ensure that it is based on  acorrect and truly representative sample of the materials that will actually be used in thework and that the mixture and its different ingredients satisfy the physical and strengthrequirements of these specifications.Approval of the job mix formula shall be based on independent testing by the Engineer forwhich samples of all ingredients of the mix shall be furnished by the Contractor as requiredby the Engineer.The approved job mix formula shall remain effective unless and until arevised bob mixformula is approved should a change in the source of materials be proposed a new hobmix formula shall be forwarded to the Engineer for approval before the placing of thematerial.507.3.4.          Plant trials permissible variation in job mix formula:Once the laboratory job mix formula is approved the contractor shall carry out plant trials atthe mixer to establish that the plant can be setting to produce as uniform mix conforming tothe approved job mix formula. The permissible variations of the individual percentages ofthe various ingredients in the actual mix from the job mix formula to be used shall be withinthe limits as specified in Table 500-13 . These variations are intended to apply to individualspecimens taken for quality control test in accordance with section 900.Table 500-13 Permissible variations from the job mix formula

Description Permissible variation

Base/binder course Wearing course

Aggregate passing19 mm

sieve or larger

+ 8% +    7%

Aggregate passing 13.2 mm

9.5 mm

+ 7% +    6%

Aggregate passing 4.75mm + 6% + 5%

Aggregate passing 2.36 mm

1.18 mm 0.6mm

+ 5% + 4%

Aggregate passing 0.3 mm

0.15 mm

+ 4% +  3%

Aggregate passing 0.075 + 2% +   1.5%

Page 99: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Once the plant trials have demonstrated the capability of the plant and the trails areapproved the laying opration may commence over the period of the first month ofproduction for laying on the works the Engineer shall require additional testing of theproduct to establish the reliability and consistency of the plant.507.3.5 Laying trials :-        Once the plant trials have bee successfully completed andapproved the contractor shall carry out laying trials to demonstrate that the proposed mixcan be successfully laid and compacted all in acc ordance with clause 501. The laying trialshall be carried out on as suitable area which is not to form part of the works, unlessspecifically approved in writing by the Engineer. The area of the laying trials shall be aminimum of 100 sqm of construction similar to that of the project road and it shall be in allrespects, particularly compaction the same as the project construction on which thebituminous material is to be laid.             The Contractor shall previously inform the Engineer  of the proposed method forlaying and compacting the material. The plant trials shall then establish if the proposedlaying plant compaction plant and methodology is capable of producing satisfactory results.The density of the finished paving layer shall be detrained by taking cores ano sooner than24 hours after laying or by other approved method.            Once the laying trials have been approved the same plant and methodology shallbe applied to the laying of the material on the project and noe variation of either shall beacceptable unless approved in writhing by the Engineer who may at his diseretion reuirefurther laying trials.507.4 Construction Operations507.4.1           Weather and seasonal limitations : The provisions of clause 501.5.1 shallapply.507.4.2           Preparation of base :-        The base on which Dense Graded bituminousmaterial Is to be laid shall be prepared in accordance with clauses 501 and 902 asappropriate or as directed by the by the Engineer. The surface3 shall be thoroughly sweptclean by  amechanical boroom and the dust removed by  compressed air. In locatonswhere mechanical broom cannot acces other approved methods shall be used as  directedby the Engineer,507.4.3           :-  Geosynthetics : Where geosynthetics are specified in the contract thisshall be in accordance with the requirements stared in clause 70-3.507.4.4 :- Stress absorbing layer : Where a stress absorbing layres is specified in thecontract, this shall be applied in accordance with the requirements of Clue 522.507.4.5 :- Prime coat :-      Where the material on which the dense bituminous macadamis to be laid is other than a bitumen bound layer, a prime coat shall be applied, asspecified, in accordance with the provisions of clause 502, or  as directed by the Engineer.507.4.6:- Tack coat :          Where the material on which the dense bituminous macadam

Binder content + 0.3% +   0.3%

Mixing temperature + 100 C + 100 C

Page 100: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

is to be placed is a bitumen bound surface a tack coal shall be applied as specified, inaccordance with the provisions of clause 503 or as directed by the Engineer.507.4.7 Mixing and transportation of the mixture : The provisions as specified inclauses 501.0 and 501.4 shall apply.507.4.8 Spreading : The provisions of clauses 501.5.3 and 501.5.4 shall apply.507.4.9 Rolling : The general provisions of clauses 501.6 and 501.7 shall apply  asmodified by the approved laying trials . The compaction process shall be carried out by thesame plant, and using the same method as approved in the laying trials which may bevaried only with the express approval of the Engineer in writing. 507.5 Opening to traffic:The newly laid surface shall  not be open to traffic for at least 24 hrs. after laying andcompletion of compaction without the express approval of the Engineer in writing.507.6 Surface  finish and quality control of work :The surface  finish of the completed construction shall conform to the requirements ofclause 902. All materials and workmanship shall comply with the provisions set out insection 900 of this specification.507.7 Arrangements for Traffic:During the period of construction arrangement,  for traffic shall be made in accordance withthe provisions of Clause 112.Mode of Measurement and Payment  :-Item shall be measured as finished work as square metres of sealing surface laid andcompacted of 50 mm thickness of specified type. The contract rate shall be per sqm of thework done as per above specifications. vibratory roller instead of ordinary roller. 4     Providing and laying hot mixed hot laid Semi Dense BituminousConcrete (SDBC) 25 mm thickusingVG 30 grade asphalt / CRMB / PMBwith 5.50% of asphalt by total weight of mix includingsupplying of all materials, heating and mixing bitumen and chips, laying semi dense bituminousconcrete by hydrostatic paver with sensor control including tack coat by using VG 10 grade asphaltat 5 kg/10m2 or emulsion grade bitumen, conforming IS: 8887 dose 2.50 kg / 10 m2 finishing,compaction with smooth wheeled tandem vibratory roller with all labour and materials .Including allleads of materials etc. complete Specification: General : The item consist of providing and laying hot mixed hot laid semi dense bituminousconcrete 25 mm thick with 5.5% of asphalt by total weight of mix.Materials :Bitumen : Bitumen shall be of penetration grade 60/70 conforming to IS:73.Coarse Aggregate : This shall be crushed or broken form hard stones obtained from approvedquarry. These shall be clean, strong, durable of fairly cubical shape and free from disintegratedsoft, friable thin elongated or laminated pieces. These shall also be free from dirt organic,deleterious and any other foreign matter and adherent coatings. The coarse aggregates shallsatisfy the physical requirements laid down below.Fine Aggregates : The fine aggregates shall be the fraction passing 2.80 mm sieve and retained on90 micron sieve, consisting of crusher run screenings, natural sand or a mixture of both. Theseshall be clean hot, durable, uncoated dry, and free from any injurious, soft or flaky pieces and

Page 101: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

organic or deleterious substances. The aggregates shall also be free from sulphates, chlorides andother materials (i.e. product of decomposition), which may be liable to break down during drying orsubsequently when exposed to weather.4Grading for Aggregates (Mixture of Coarse Aggregates and Fine Aggregates) : In order to satisfythe design requirements for the semi dense asphalt concrete mix laid down described below, themix shall contain coarse aggregates and fine aggregates in suitable proportion. True andrepresentative samples of the aggregate likely and proposed to be used on the specific job shall betested in design laboratory and a proper blend of the individual aggregates normally available shallbe worked out so that the gradation of the final composition shall satisfy the limits laid down inTable below.TableCOMPOSITION OF SEMI DENSE BITUMINOUSCONCRETE PAVEMENT LAYERS

Notes : 1. The combined aggregate grading shall not vary from thelow limit on one sieve to the high limit on the adjacent sieve.2.Determined by the Marshall method.*Only in exceptional circumstances. 80/100 penetration grade may be used, as approved by theEngineer.Table

Grading 1

Nominal aggregate size 10 mm

Layer Thickness 25-30 mm

IS Sieve1 (mm) Cumulative % by weight of total

aggregate passing

45

37.5

26.5

19

13.2 100

9.5 90-100

4.75 35-51

2.36 24-39

1.18 15-30

0.6 --

0.3 9-19

0.15 --

0.075 3-8

Bitumen content % by Min 5.5

mass of total mix2

Bitumen grade (pen) 65*

Page 102: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

REQUIREMENTS FOR SEMI DENSE BITUMINOUS PAVEMENTLAYERS

TablePHYSICAL REQUIREMENTS FOR COARSE AGGREGATE FORBITUMINOUS CONCRETE PAVEMENT LAYERS

*Aggregate may satisfy requirements of either of the tests.**The water sensitivity test is only required if the minimum retained coating in the stripping test isless than 95%.The requirements for minimum per cent voids in mineral aggregate (VMA)are set out in Table VMA TablePERMISSIBLE VARIATIONS FROM THE JOB MIX FORMULA

Minimum stability (kN at 60° C) 8.2

Minimum flow (mm) 2

Maximum flow (mm) 4

Compaction level (Number of blows) 75 blows on each of the two

faces of the specimen

Per cent air voids 3-5

Per cent voids in mineral aggregate (VMA) See Table

Per cent voids filled with bitumen (VFB) 65-78

Property Test Specification

Cleanliness (dust) Grain size analysis1 Max 5%passing0.075 mmsieve

Particle shape Flakiness and Elongation Index Max 30%(Combined)2

Strength* Los Angeles Abrasion Value3 Max 35%Aggregate Impact Value4 Max 27%

Polishing Polished Stone Value5 Min 55Durability Soundness6

Sodium Sulphate Max 12%Magnesium Sulphate Max 18%

Water Absorption Water absorption7 Max 2%

Stripping Coating and Stripping of Bitumen MinimumRetained

Aggregate Mixtures9 Coating 95%Water Sensitivity** Retained Tensile Strength8 Min 80%Notes : 1. IS: 2386 Part I 6. IS: 2386 Part 5            2 IS:2386Part I 7. IS: 2386 Part 3(the elongation test to be done only on non-flaky aggregates in the sample)

3. IS: 2386 Part 4* 8. AASHTOT283**

4. IS: 2386 Part 4* 9. IS: 62415. BS: 812 Part 114

Page 103: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

TableMINIMUM PER CENT VOIDS IN MINERAL AGGREGATE (VMA)

Notes : 1. The nominal maximum particle size is one size larger than the firstsieve to retain more than 10 per cent.2.Interpolate minimum voids in the mineral aggregate (VMA) for design air voids values betweenthose listed.Bitumen Content : The bitumen content shall be determined in an approved Govt. Laboratory asdirected by the Engineer-in- Charge by the Marshall design method, so as to obtain the followingstandards of compaction and strength using 75 blows on each end of the specimen forcompaction.For the purpose of tendering, the contractor shall base his rate on the assumption that the bitumencontent of the mixture shall be 5.5% by weight of the total mix assuming 111.50 kg of bitumen percum of total mix compacted to 100% density in Marshall mould. If the actual quantity of bitumenrequired to be used as a result of the laboratory test is found different from the quantity of bitumenthat is assumed above, necessary adjustment in the cost of extra/short bitumen used shall bemade on the basis of issue rate of bitumen including storage charges plus 2.5% for handlingcharges from the assumed basisof 111.50 kg of bitumen per cum. of total mix compacted to 100% density in Marshall mould.Immersion : Compression test to measure the loss in Marshall stability due to effect of water on themix shall be conducted and if the index of retained stability is less than 75, the mix shall berejected or the aggregate shall be processed by approved method to increase the index to a

Sr.Description

Permissible VariationsBase/binder WearingNo.Course Course

1Aggregate passing19 mm sieve orlarger

+ 8% + 7%

2 Aggregate passing13.2 mm, 9.5 mm + 7% + 6%

3 Aggregate passing4.75 mm + 6% + 5%

4Aggregate passing2.36 mm, 1.18 mm,0.6

+ 5% + 4%

mm

5 Aggregate passing0.3 mm, 0.15 mm + 4% + 3%

6 Aggregate passing0.075 mm + 2% + 1.5%

7 Binder content + 0.3% + 0.3%8 Mixing temperature + 10° C + 10° C

NominalMaximum Minimum VMA, Per cent

Particle Size1 Related to Design Air Voids, Per cent2(mm) 3.0 4.0 5.09.5 14.0 15.0 16.012.5 13.0 14.0 15.019.0 12.0 13.0 14.025.0 11.0 12.0 13.037.5 10.0 11.0 12.0

Page 104: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

minimum of 75.Design Mix :Requirement of Mix : Apart from conformity with the grading and quality requirements of individualingredients, the mix shall meet the requirements set forth in Table below.TableREQUIREMENTS FOR DENSE GRADED BITUMINOUS MACADAM

The requirements for minimum per cent voids in mineral aggregate (VMA)are set out as under -Binder Content : The binder content shall be so decided as to achieve the design requirements ofthe. Marshall method for arriving at the binder content shall be adopted.Job Mix Formula : The contractor shall intimate to the Engineer-in-Charge in writing, at least 20days before the startof the work, the job mix formula proposed to be used for the work and shall give the followingdetails :a.Source and location of all materials.b.Proportions of all materials expressed as follows where

c.A single definite percentage passing each sieve for the mixed aggregate.d.The results of test enumerated in Table shall be obtained by the Contractor.e.Test results of physical characteristics of aggregates to be used.f.Mixing and compacting temperature.While working out the job mix formula, the Contractor shall ensure that it is based on a correct andtruly representative sample of the materials that will be used actually in the work and that the mixand its ingredients satisfy the physical and strength requirements of these specifications.Approval of the job mix formula shall be based on independent testing by the Engineer-in-Chargefor which samples of all ingredients of the mix shall be furnished by the Contractor as required.The approved job mix formula shall remain effective unless and until modified by the Engineer-in-Charge. Should a change in the source of materials be proposed, a new job mix formula shall beestablished and got approved from the Engineer-in- Charge before actually using the mix andmaterials.Construction Operations :Weather and Seasonal Limitations : The work of laying shall not be taken up during rainy or foggyweather, when the base course is damp or wet, or during dust storm or when the atmospherictemperature in shade is 100C or less.Preparation of Base : The base on which semi dense bituminous concrete is to be laid shall beprepared, shaped and conditioned to the specified levels, grade and cross fall (camber) inaccordance with specifications or as directed by the Engineer-in-Charge.The surface shall be thoroughly swept, clean, free from dust and foreign matter using mechanical

Minimum stability (kN at 60° C) 9.0Minimum flow (mm) 2Maximum flow (mm) 4Compaction level (Number of blows) 75 blows on each of the two

faces of the specimenPer cent air voids 3-6Per cent voids in mineral aggregate (VMA) See TablePer cent voids filled with bitumen (VFB) 65-75

each is applicable.Binder - as percentage by weight of total

mix.Coarse aggregate - as percentage by weight of total

aggregateFine aggregate - including mineral filler

Page 105: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

broom and dust removed by mechanical means or blown off by compressed air. In portions wheremechanical means cannot reach, other approved method shall be used as directed by theEngineer-in-Charge.Tack Coat : The tack coat at 5 kg/10 m2 shall be applied over the base preparatory to laying ofsemidence Bituminous Concrete.The tack coat shall consist of application of single coat of bitumen to a existing road surfacepreparatory to another bituminous construction over it.Preparation of Mix : Hot mix plant of adequate capacity and capable of producing a proper anduniform quality mix shall be used for preparing the mix. The plant may be either a batch type orcontinuous or drum mix type.The Plant shall have the following essential features:A.General : a.The Plant shall have coordinated set of essential units capable of producing uniform mix as perthe job mix formula.b.Cold aggregate feed system with minimum 3 bins having belt conveyor arrangement for initialproportioning of aggregate from each bin in the required quantities.c.Dryer unit with burner capable of heating the aggregate to the required temperature without anyvisible unburnt fuel or carbon residue on the aggregate and to reduce the moisture content of theaggregate to the specified minimum.d.The plant shall be fitted with suitable type of thermometer at appropriate locations so as toindicate or record/register the temperature of heated aggregate, bitumen and mix.e.Bitumen storage unit capable of heating, measuring/metering and spraying of bitumen atspecified temperature with automatic synchronization of bitumen and aggregate feed in therequired proportion.f.A filler system suitable to receive bagged or bulk supply of filler material and its incorporation tothe mix in the correct quantity/percentage.g.A suitable built-in dust control system for the dryer to contain/recycle permissible quantity of finesinto the mix. It should be capable of preventing the exhaust of fine dust into atmosphere forenvironmental control.h.The plant should have centralized control panel/cabin capable of presenting,controlling/synchronizing all operations starting from feeding of cold aggregates to the discharge ofthe hot mix to ensure proper quality of mix. It should have indicators for any malfunctioning in theoperation.B.For Batch Type Plant :a.Gradation control unit having vibratory screens for accurate sizing of hot aggregate and storingthem in separate bins.b.Proper arrangement for accurate weighing of each size of hot aggregate from the control panelbefore mixing.C.For Continuous Type Plant :a.Gradation control unit having vibratory screens for accurate sizing of hot aggregate and storingthem in separate bins.b.There should be appropriate arrangement for regulating and volumetric control of the flow of hotaggregate from each bin to achieve the required proportioning.D.For Drum Mix Plant :a.It is prerequisite that only properly screened graded materials are fed to the bins. If required avibratory screening unit should be installed at the plant site to ensure the same.b.Belt conveyors below each bin and main gathering conveyor should have variable speed drivemotors. There should be electronic load sensors on the main conveyor for measuring the flow ofaggregates.MANUFACTURING AND ROLLING TEMPERATURESBitumen Bitumen Aggregate Mixed Rolling LayingPeutratia Mixing Mixing (°C) Material (°C) (°C) (°C)

Page 106: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

The temperature of both the aggregates and the bitumen at the time of mixing shall be inaccordance with the job mix formula and strictly controlled. All overheated and carbonizedmixtures, which form or show indication of excess moisture, will be rejected.Any truck/tipper causing excessive segregation of material by its spring suspension or othercontributing factor or that show undue delays shall be removed from the work until such conditionsare corrected.Spreading : The mix transported from the hot mix plant to the site shall be spread by means of selfpropelled mechanical paver with suitable screeds capable of spreading, tamping and finishing themix to specified grade, lines and cross section.The paver finisher shall have the following essential features:a)Loading hoppers and suitable distributing mechanism.b)All drive having hydrostatic drive/control.c)The machine shall have a hydraulically extendible screed for appropriate width requirement.d)The screed shall have tamping and vibrating arrangement for initial compaction to the layer as itis spread without rutting or otherwise marring the surface. It shall have adjustable amplitude andfrequency.e)The paver shall be equipped with necessary control mechanism so as to ensure that the finishedsurface is free from surface blemishes.f)The paver shall be fitted with electronic sensing device for automatic thickness leveling andprofile control within the specified tolerances.g)The screed shall have the internal heating arrangement.h)The paver shall be capable of laying either 2.5 to 4.0 m width or 4.0 m to 7.0 m width asspecified in the contract.However, in restricted locations and in narrow width where the available equipment cannot beoperated the Engineer-in-Charge may permit manual laying of the mix.The temperature of mix at the time of laying shall be in the range of 115° C - 130° C.Mixes with a temperature of less that 155° C shall not be loaded into paver finisher.Longitudinal joints and edges shall be constructed true to the delineating lines parallel to thecenterline of the road. Longitudinal and transverse joints shall be offset by at least 250 mm fromthose in the lower courses and the joint on the top most layer shall be allowed to fall within thewheel path. All transverse joints shall be cut vertically to the full thickness of the previously laid mixwith pneumatic cutter and the surface painted with hot bitumen before placing fresh material.Longitudinal joints shall be preferably hot joints. Cold longitudinal joints shall be properly heatedwith joint heater to attain a suitable temperature of about 80° C before laying of any material. Anoverlapping of 150 mm may be allowed for making the joint.Rolling : After spreading the mix by paver, it shall be thoroughly compacted by rolling with a set ofrollers moving at speed not more than 5 km/hr, immediately following close to the paver. Generallythe initial or breakdown rolling shall be done with 8-10 tonne static weight smooth wheeled roller.The intermediate rolling shall be done with 8 to 10 tonne staticweight vibratory roller or with a smooth wheeled pneumatic tyre roller of 15 to 30 tonne weighthaving a tyre pressure of 7 kg/cm2. The finish rolling shall be done with 8 to 10 tonne weighttandem roller. The exact pattern of rolling shall be established after trial compaction as approvedby the Engineer- in-Charge. Any displacement occurring as a result of reversing of the direction ofa roller or from any other cause shall be corrected at once as specified and/or removed and madegood. The rollers shall not be permitted to stand on pavement which has not been fully compactedand where temperature is still more than 70° C.Necessary precaution shall be taken to prevent dropping of oil, grease, petrol or other foreignmatter on the pavement either when the rollers are operating or standing.The roller wheels shall be kept moist to prevent the mix from adhering to wheels. But in no case

(°C)35 160-170 160-175 170 Max. 100 Min. 130 Min.65 150-165 150-170 165 Max. 90 Min. 125 Min.90 140-160 140-165 155 Max. 80 Min. 115 Min.

Page 107: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

shall fuel/lubricating oil be used for this purpose nor excessive water poured on the wheels. Rollingshall commence longitudinally from edge and proceed towards the center, except that on portionshaving unidirectional cross fall/super elevation, it shall progress from the lower to upper edgeparallel to the center line of the pavement. The roller shall proceed on the fresh material with rearor fixed wheel loading so as to minimize the pushing of the mix and each pass of the roller shalloverlap the preceding one by half the width of the rear wheel. Rolling shall be continued till thedensity achieved is at least 98% of that of laboratory Marshall Specimen compacted as defined inTable 23.3.1 and all roller marks are eliminated. Patching of an area that has been rolled will notbe permitted. Rolling operations shall be completed in all respects before the temperature of themix falls below 100° C.Opening to Traffic : Traffic may be allowed after completion of the final rolling when the mix hascooled down to the surrounding temperature.Surface Finish and Quality Control : General : All works performed shall conform to the lines, grades, cross sections and dimensionsshown on the drawings or as directed by the Engineer-in-Charge, subject to the permittedtolerances described herein after.Surface Level : The surface level tolerances shall be as per Table below. Provided however, thatthe negative tolerance for wearing course shall not be permitted in conjunction with the positivetolerance for base course, if the thickness of the former is thereby reduced by more than 6 mm forflexible pavement and 5 mm for concrete pavements.

For checking complains with the below requirement for base course measurement of surface levelshall be taken on a grid of point place at 6.25m longitudinally and 3.5m transversely. For any 10consecutive measurements longitudinally or transversely, not more than one measurement shallbe permitted to exceed the tolerance as above, this one measurement being not in excess of 5 mmabove the permitted tolerance.For checking the compliance with the above requirement for bituminous wearing courses andconcrete pavements, measurements of the surface levels shall be taken on a grid of points spacedat 6.25m along the length and 0.5m from the edges and at the center of the pavement. In anylength of pavement, compliance shall be deemed to be met for the final road surface, only if thetolerance is satisfied for any point on the surface.TableSurface Regularity of Pavement Course : The longitudinal profile shall be checked with a 3-meterlong straight edge/moving straight-edge as directed by Engineer-in-Charge at the middle of each

1Base course for flexible

pavement

a) Bituminous course

b) Other than bituminous

i) Machine laid

ii) Manual laid

+ 6 mm

+ 10 mm

+ 15 mm

2Wearing course for flexible

pavement

a)Machine laid

b)Manual laid

+ 6 mm

+ 10 mm

3Cement concrete

pavement 

+ 5 mm- 6 mm

Page 108: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

traffic lane along a line parallel to the center line of the road.The maximum permitted number of surface irregularities shall be as per Table below :Table

*Category of each section of road as described in Contract.The maximum allowable difference between the road surface and underside of 3m straight-edgewhen placed parallel with, or at right angles to the center line of the road at points decided by theEngineer-in-Charge shall be :

21.5.4Rectification : Where the surface regularity of various pavement courses fall outside thespecified the Contractor shall be liable to rectify these in the manner described below and to thesatisfaction of the Engineer-in-Charge.a)Water Bound Macadam / Wet Mix Macadam (Sub Base/ Base) : Where the surface is high orlow, the top 75 mm shall be scarified, reshaped with added material as necessary and re-compacted.b)Bituminous Constructions : For bituminous constructions other than wearing course, where thesurface is low, the deficiency shall be corrected by adding fresh material overall suitable tack coatif needed and re-compacting to specifications Where the surface is high, the full depth of the layersshall be remove and replaced with fresh material and compacted to specifications.For wearing course where the surface is high or low, the full depth of the layer shall be removedand replaced with fresh material and compacted to specifications. In all cases where the removaland replacement of the bituminous layer is involved, the area treated shall not be less than 5 m inlength and not less than 3.5 m in width.Quality Control Tests during ConstructionThe material supplied and the works carried out by the Contractor shall conform to thespecifications prescribed in the preceding Clauses.For ensuring the requisite quality of construction, the materials and works shall be subjected toquality control tests, as described hereinafter. The testing frequencies set forth are the desirable

Surfaces ofCarriageways &Paved Shoulders

Surfaces of Lay-bys,service areas and allbituminous base courses

Irregularity 4 mm 7 mm 4 mm 7 mm

Length(m) 300 75 300 75 300 75 300 75

NationalHighways/Expressways

20 9 2 1 40 18 4 2

RoadsofLowerCategory*

40 18 4 2 60 27 6 3

For pavement surface 3 mm(bituminous and cementconcrete)For bituminous base course 6 mmFor granular sub base/basecourse 8 mm

For sub base under concretepavement 10 mm

Page 109: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

minimum and the Engineer-in-Charge shall have the full authority to carry out additional tests asfrequently as he may deem necessary, to satisfy himself that the materials and works comply withthe appropriate specifications. However, the number of tests recommended in Tables may be reduced at the discretion of the Engineer-in-Charge if it is felt that consistency in the quality of materials can still be maintained with thereduced number of tests.Acceptance Criteria for the tests on density and Marshall stability shall be subject to the conditionthat the mean value is not less than specified values plus:[ 1.65 – {1.65 / (No. of Samples)0.5} ] times the standard deviation.TableCONTROL TESTS FOR BITUMINOUS WORKS, AND THEIRMINIMUM FREQUENCY

Sr. Type ofConstruction Test Frequency (Min).

No.

1.Prime Coat/TackCoat/Fog Spray

(i) Quality of binder

Number ofsamples per lotand tests as perIS:73,IS:217 andIS:8887 asapplicable.

(ii) Binder temperaturefor application

At regular closeintervals

(iii) Rate of spread ofBinder

One test per500m2 and notless than twotests per day.

2.SealCoat/SurfaceDressing

(i) Quality of binderSame asmentioned underSerial No.1

(ii) Aggregate ImpactValue/Los Angeles

One test per 50m3 ofaggregate

Abrasion Value

(iii) Flakiness Indexand -do-

Elongation Index(iv) Stripping value of Initially one set of 3

aggregates representative specimens(Immersion Tray for each source of supply.Test) Subsequently when

warranted by changes inthe quality of aggregates

(v) Water absorptionof -do-

aggregates

(vi) Water sensitivityof Initially one set of 3

mix representative specimens

Page 110: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

for each source of supply.Subsequently whenwarranted by changes inthe quality of aggregates(if required)

(vii) Grading of One test per 25 m3 ofaggregates aggregate

(viii)Soundness Initially, one determination(Magnesium and by each method for each

Sodium Sulphate)source ofsupply,then aswarrantedby changein thequality oftheaggregates.

(ix) Polished stone value As required

(x) Temperature ofAt regularcloseintervals

binder at application

(xi) Rate of spread ofOne testper 500 m2of

materialswork, and,not lessthantwo testsper day

(xii) Percentage ofWhengravel isused, one

fractured faces test per 50m3 ofaggregate

3.Open-grantedPremix

(i) Quality of binderSame asmentionedunder

Surfacing/Close- Serial No.1

gradedPremixSurfacing

Page 111: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

(ii) Aggregate ImpactSame asmentionedunder

Value/Los Angeles Serial No.2Abrasion Value

(iii) Flakiness Index and -do-Elongation Index

(iv) Stripping valueSame asmentionedunderSerial No.2

(v) Water absorption ofSame asmentionedunder

aggregates Serial No.2

(vi) Water sensitivity ofSame asmentionedunder

mix Serial No.2

(vii) Grading ofSame asmentionedunder

aggregates Serial No.2

(viii)SoundnessSame asmentionedunder

(Magnesium and Serial No.2

SodiumSulphate)

(ix) Polishedstone value As required

(x) Temperature of

At regularcloseintervals

binder atapplication

(xi) Bindercontent

One testper 500 m3andnot lessthan twotests perday

(xii) Rate of spread ofRegularcontrolthrough

Page 112: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

mixedmaterials

checks oflayerthickness

(xiii)Percentage ofSame asmentionedunder

fracturedfaces Serial No.2

4. Bituminous Macadam (i) Quality ofbinder

Same asmentionedunderSerial No.1

(ii) AggregateImpact

Same asmentionedunder

Value/LosAngeles Serial No.2

AbrasionValue

(iii) FlakinessIndex and

Same asmentionedunder

ElongationIndex Serial No.2

(iv) Strippingvalue

Same asmentionedunderSerial No.2

(v)Watersensitivityof

-do-

mix

(vi) Grading ofTwo testsper day perplant

aggregates both on theindividualconstituents andmixedaggregatesfrom thedryer

(vii) Water absorption of Same as inSerial No.2

aggregates

(viii)SoundnessSame asmentionedunder

Page 113: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

(Magnesium and Serial No.2

SodiumSulphate)

(ix) Percentageof

Same asmentionedunder

fracturedfaces Serial No.2

(x) Bindercontent and

Periodic,subject to

aggregategrading

minimum oftwo testsperday perplant

(xi) Control ofAt regularcloseintervals

temperature ofbinder andaggregateformixing andof themix at thetime oflaying androlling

(xii) Rate of spread ofRegularcontrolthrough

mixedmaterials

checks oflayerthickness

(xiii)Density ofOne testper 250 m2of area

compacted layer

5. Bituminous (i) Quality of binderSame asmentionedunder

Penetration Serial No.1Macadam/Built-upSpray-Grout

(ii) Aggregate ImpactOne testper 200 m3of

Page 114: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Value/Los Angeles aggregateAbrasion Value

(iii) Flakiness Index and -do-Elongation Index

(iv) Stripping valueSame asmentionedunderSerial No.2

(v) Water absorption of Same asSerial No.2

aggregates

(vi) Water sensitivity of Same asSerial No.2

mix(vii) Aggregate grading

(viii)SoundnessSame asmentionedunder

(Magnesium and Serial No.2Sodium Sulphate)

(ix) Percentage ofSame asmentionedunder

fractured faces Serial No.2

(x) Temperature ofAt regularcloseintervals

binder at application

(xi) Rate of spread ofSame asmentionedunder

binder Serial No.2

6. Dense Bituminous (i) Quality of binderSame asmentionedunder

Macadam/Semi Dense Serial No.1Bituminous Concrete/Bituminous Concrete

(ii) Aggregate ImpactSame asmentionedunder

Value/Los Angeles Serial No.2Abrasion Value

(iii) Flakiness Index and -do-Elongation Index

(iv) Stripping ValueSame asmentionedunder

Page 115: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

5     Earthwork in embankment with approved material having field soak CBR not less than 8 andlaboratory soak CBR not less than 12 obtained by the Contractor from his borrow areas includingall lifts and leads including laying in layers of 20cm to 30cm for power roller and 45cm to 60cm forvibratory compactor, breaking clods, and dressing to the required lines, curves and section

Serial No.2

(v) SoundnessSame asmentionedunder

(Magnesium and Serial No.2Sodium Sulphate)

(vi) Water absorption of As in SerialNo.2

aggregates(vii) Sand equivalent test As required(viii)Plasiticity Index As required

(ix) Polished stone valueAsrequired,for SemiDenseBituminousConcrete/BituminousConcrete

(x) Percentage of Same as mentionedunder

fractured faces Serial No.2(xi) Mix grading One set of tests on

individualconstituents andmixed aggregatefrom thedryer for each 400tonnesof mix subject to aminimum of two testsperplant per day

(xii) Stability of Mix For each 400 tonnesof mixproduced, a set of 3Marshall specimensto beprepared and testedforstability, flow value,

Page 116: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

including payment of royalty charges to the Govt. of Maharashtra. (Lead shall be certified by Dy.Engr.) a) For lead 20 km (Lead shown below only for the purpose of estimate) Specification:

General : The work provides setting out and preparing the ground and formation embankment for

the road with approved quality materials obtained from the contractor’s borrow areas, laying in

layers, of 20 cm to 30 cm to the required density, lines, curves, grades and cross section and

dimensions shown on the plan or as directed by the Engineer-in- Charge with due allowance for

shrinkage for compaction.

Material : All the useful and acceptable materials of approved quality obtained from the

contractor’s borrow areas shall be used for the embankment work. The borrow areas shall be got

approved prior to bringing material to site of work from the Engineer-in-Charge. All the useful and

approved material obtained from contractor’s borrow areas as directed shall be used for the

embankment work. Approved quality murum or a mixture of sand, murum, gravel, small boulders

or rubble as approved shall be used. Black cotton soil, shadu or shrinkable soils shall not be used.

Murum having laboratory dry density of less than 1.65 gm/cc shall be rejected. For embankments

upto 3 m in height, murum with laboratory dry density of less than 1.65 gm/ cc shall not be used.

Only the tested materials approved by the Engineer-in-Charge shall be used for the embankment.

Rejected materials shall not be brought to the work site. The perishable materials such as stumps,

pieces of wood, roots, rubbish, etc. shall be removed from the embankment material. The material

required for embankment shall be obtained by the contractor from the approved quarries by the

Engineer-in-Charge: - All lifts and specified leads involved in conveying the material to site shall be

included in the rate. The payment of taxes, duties, octroi and royalty as per rules and regulations

levied by the Govt. shall have to be paid by the contractor. The Contractor shall be responsible

regarding any claims if any, that may be made by private owners. The payment of royalty charges

is to be born by the contractor and no reimbursement from MIDC is admissible.

 Setting Out : Alignment of the road shall be set out as shown in the drawing or as directed to true

lines, curves, and grades. Profiles shall be set out with stout poles to mark the center and edges of

the formation width with the top levels of formation clearly marked by paint or cut and the slopes

with string and pegs at every 30 meters on straight portions and 10m or less on curves or as

directed by the Engineer-in-Charge. The toe line shall be marked with pick marks.  Longitudinal

and cross-section levels shall be taken recorded and signed by the contractor or his authorized

representative and also by the Engineer-in-charge. All the materials and labour required for this

item shall be supplied by the contractor and profiles, B.M.s etc. shall be put up by the contractor.

The cost of these operations is included in the rate of this item. Profiles, pegs, benchmarks and

other marks shall be maintained without any disturbance till the completion of the work, and as

directed by the Engineer-in-charge.

 Equipment: Pickaxes, crowbars, phawras, and Ghamelas maybe used for carrying out work

manually. The scrapers, dozers, graders, shovels, dumpers, trucks, trolleys, etc. may be used for

executing work using mechanical equipments. Three wheels, 8 tones Power Roller giving a

pressure required to obtain the specified density may be used for compaction. Bullock carts with

Page 117: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

water tanks or mechanically driven water tankers may be used for watering. The contractor shall

submit the list of equipments available with him and intended to be used on the work and shall got

approved for their use from the Engineer-incharge.

Construction Methods :

Diversions : If diversions, barricading and signals for day and night are necessary, they shall be

provided without any extra cost.

 Preparing the Ground for Laying Bank : Before any material is laid for the embankment the

ground shall be cleared of all rubbish, removing bushes, etc., and the holes, if any, filled up. When

the embankment is to be laid on hillsides or slopes, the existing slopes shall be ploughed deeply. If

the cross slopes are steeper than 1 in 3, steps with reverse slope shall be cut into the slopes to

give proper hold and seating to the bank as directed by the Engineer-in-Charge. On surfaces flatter

than 1 in 15, no special surface treatment such as cutting steps shall be necessary. The top 15 cm

of soil shall be scarified and watered as directed and compacted to the same density as specified

for the embankment before any  material is laid for the Bank-work. When the embankment is to be

placed over an existing road, which is within 15 cm of the finished formation, the road or other hard

surface shall be scarified to a minimum depth of 15 cm for which payment shall be made

separately under relevant item of road excavation. The rate for embankment includes all the

operations for preparing the bed for laying the embankment material.

Laying the Bank : Embankment material shall be placed in successive horizontal layers of 20 cm

to 30 cm thickness extending to the full width of the embankment including the slopes at the level

of the particular location and 30 cm more on both sides to allow compaction of the full specified

section. The extra loose stuff at the edges shall be trimmed after completion of the embankment

work without extra cost leaving the correct section fully compacted. Keeping width of the bank

initially less and widening it later by dumping loose earth on the slopes shall not be permitted as

the additional width and slopes may remain loose and uncompacted and may not have been

compacted as earlier carried out work. Similar procedure to extend the embankment by dumping

the material longitudinally shall also not be allowed. When boulders, broken stones, and similar

hard materials are mixed up with the embankment materials, care shall be taken to see that they

are distributed uniformly in to the embankment and that no hollows are left near them. No stone or

hard material shall project above the top of any layer. Each layer of embankment shall be watered,

leveled and compacted as specified, before the succeeding layer is placed. The surface of the

embankment shall, at all times during construction, be maintained at such a cross fall to shed

water and prevent ponding. If bridges and culverts on the road are not completed in advance of

embankment work, a length of 15 m bank shall be left on each side of the structure and these

lengths shall dealt  with later for  placing the embankment work. The contractor shall construct

temporary diversion road till the work of culverts and bridges are completed and all type of traffic is

allowed to be passed on these bridges and culverts. The camber stipulated shall be provided in the

embankment only and shall not be adjusted in metalling.

Protection : Proper care shall be taken to ensure that the method of operation and compaction of

the bank-work does not cause damage or undue strain to any structural element. Embankment

over and around bridges or culverts shall be of approved materials and carefully placed and

Page 118: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

compacted. The contractor shall take all precautions necessary for the protection of the bank-work

by diversions of streams, local surface drainage, rain water, etc. likely to damage the bank. Any

damage to  the embankment-work due to no protection or inadequate protection shall be made

good by the contractor at his own cost. Conveyance of materials shall not cause obstruction or

nuisance to the nearby property owners and traffic.

Finishing : The embankment shall be finished and dressed smooth and even in conformity with

the alignment, levels, cross-sections and dimensions shown on the drawing with due  allowances

for shrinkage. On curves, sections shall be provided with super elevation and increased widths as

shown on the plans or directed by the Engineer-in- Charge. All damages caused by rain, flood or

any other reasons shall be made good in the finishing operations without any extra cost by the

contractor. The road land width shall be cleared.

 Maintenance : The contractor shall be responsible for maintaining the work satisfactorily at his

own cost till the completion of the defect liability period as specified in the contract  agreement.

 Test :

(a) Tests shall be made to determine the required density of the material to be used by the Proctor

Density Method before starting the work.

(b) The required number of CBR tests and plasticity index tests shall be carried out as directed by

the Engineer-in-Charge.

 Item to include :

1) Setting out alignment including necessary labour and materiel and maintaining it as long as

required and directed by the engineer-in- charge of the work.

2) Preparing the ground for laying the embankment.

3) Providing and maintaining diversions.

4) Obtaining the embankment materials including all lifts and leads as specified under this item and

laying embankment in layers, tests and payment of Royalties, fees, ocrtoi etc., if any. The cost of

testing of material is included in the item of embankment.

5) Protecting and maintaining the embankment.

6) Finishing the embankment

7) All labours, materials, use of equipments, machinery, tools, survey instruments and plant

necessary for completing the work satisfactorily.

8) Watering to OMC and compaction is not included in the scope of this item and shall be paid

separately under relevant items incorporated in this tender.

Mode of Measurement and Payment :

The quantities shall be  worked out by cross sectional measurement using leveling instruments.

The contract rate shall be per cum of the finished embankment-work, watered and compacted

(watering to OMC and compaction shall be paid separately). The measurement of the sections

shall be limited to the dimensions shown on the drawings or those ordered by the Engineers in

Charge in writing. The dimensions shall be recorded up to two decimals. The sectional areas shall

be worked out up to two decimals. The quantity shall be worked out up to two decimals of a cum.

by average area method. The volume of embankment thus calculated shall be reduced by 16% for

the purpose of payment when the measurements are taken for running bills if watering and

Page 119: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

compaction has not done and by 1% in final measurements. The final quantity to be paid for under

this item shall be the total quantity of embankment-work reduced by 1 per cent. 6     Watering to OMC (16 kg to 24 kg of water per Cu.M.) The earth work in embankment in 20 cmto 30 cm layers. (95% proctor density) Specification:

 General : The item provides watering the layers of 20 to 30 cm of embankment laid.

 Material and Equipment : Water to be used shall be free of harmful elements, which may cause

heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall make his

own arrangements for getting adequate quantity of acceptable water. The water tankers shall be

used, without any additional payment.

Watering : When the murum of the 20 to 30 cm layer in embankment road contains less than the

optimum moisture, water shall be added to the material in the embankment layers of the road to

bring the moisture, uniformly up to requirement. If the material contains more than the required

moisture, it shall be allowed to dry until the moisture is reduced to the required extent. If due to wet

weather etc. the moisture contents of the soil cannot be reduced to the appropriate amount by

exposure, the compaction shall be suspended till suitable conditions prevail without contractor’s

claiming any compensation.

 Item to Include : All material, equipment machinery labour, taxes etc. shall be included in the

rate.

Mode of Measurement and Payment : The measurement shall be taken on Cum. basis of the

embankment of the road watered. 7     Consolidation with proper ramming / rolling in layers the earth work in embankment . (95%proctor density) Specification:

a)With 8-10 tonne roller in 20 to 30cm layers

 General : The item provides consolidation of the earthwork in embankment in 20 to 30 cm layers

for 8 to 10 tonnes roller and 40 to 50 cm layers for vibratory rollers. This item is to be  executed

after laying the earthwork in embankment in the layers of 20 to 30 cm and the layer is watered.

 Equipment : The ramming rods and 8-10 tone ordinary or vibratory roller as directed shall be

used.

 Consolidation : When a loose layer is leveled manually or mechanically with camber provided

and moistened or dried to a uniform and required moisture content suitable for maximum

compaction, it shall be compacted by power rollers, vibratory rollers or heavy hauling or dozing

equipment to give the specified 95% of the standard proctor density. If on testing, the density is

found to be less than 95% of the standard density the contractor shall do additional compaction

necessary to get the specified density after adding water if required. When the specified density is

imperative, the work shall be removed and redone by the contractor at his own cost to give the

specified density. Proper sequence of all component operations shall be maintained to give

Page 120: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

individual progress. For compaction of embankment the road roller shall move longitudinally and

rolling shall be done from edges to centre. The camber shall be provided in the cutting and shall

not be adjusted in metalling. Care shall be taken for getting good compaction behind abutments,

returns and wing walls, etc. Cutting/ Bank-work in areas not accessible to rollers such as those

adjoining bridges, culverts and other works, shall be carried out independently of the main

embankment and shall have the layers placed in 10 cm to 15 cm. thickness and each layer shall

be moistened and thoroughly compacted with mechanical or manual tampers. Embankment shall

be brought up simultaneously in equal layers on each side and compacted carefully to avoid

unequal pressure, etc The compaction of the embankment shall be done by moving road roller

longitudinally from edges to centre.

Item to Include : The item includes only the compaction of each layer by 8-10 tonne roller or

vibratory roller. All labour and equipment required to execute the item as per above specification

shall be included in the item. If specified vibratory compactors shall be used.

Mode of Measurement and Payment :

The measurement shall be taken of the earthwork for embankment of road in Cum. upto two

decimals. The contract rate shall be for a unit of One Cubic meter of the finished bank work. Sub Estimate: Construction of WBM road for partial length & Strengthning to Pentakali Jackwellroad 1     Clearing jungle including uprooting, removing trunk vegetation, grass, bushes, trees up to 30cm girth and removal of rubbish up to a distance of 50 m and stacking neatly outside the peripheryof the area cleared. Specification:  General : The item provides clearing of jungle, including cutting small trees, vegetation, andbushes and stacking them out side the cleared area. Clearing of Jungle : The land area required for cleaning shall be cleared of all trees have a girthof 30 cm and less, brushwood, loose stones, vegetation, bushes, stumps and all otherobjectionable materials. The roots of trees shall be removed to a depth of 30 cm below the groundformation and the excavations filled up with excavated materials in 15 to 20 cm layers andcompacted. Brushwood, stumps, vegetation, etc., shall be cut flush with the ground. All thematerials cleared shall be the property of MIDC. Useful materials shall be arranged in convenientstacks along side of cleared boundary or as directed at places within a lead of 50 metres andhanded over to the MIDC. Unsuitable materials shall be burnt or otherwise disposed off by thecontractor at his own cost as directed by the Engineer without causing any nuisance,inconvenience or damage to the work, property or people in the vicinity. If the material is disposedoff outside the cleared land, necessary permissions from the private land owners shall be taken bythe contractor and royalty etc. if any should be paid by him without claiming compensation. In allcases, the materials shall be disposed off in a neat manner. Item to Include : Item includes all labour, tools and equipment for cutting of trees cleaning of siteand disposing of the material as per above specifications.  Mode of Measurement and Payment : The area of the jungle cleared shall be measured in sqmupto two decimal places. The linear dimensions shall be measured correct to 1 cm. The payment

Page 121: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

shall be made after completing the work in one installment at the contract rate per sqm. 2     Open excavation for road works, side gutters water retaining structures and large excavatedareas not involving manual lift of materials such as water reservoir, foundation, dam seats andallied works in soils of all sorts, sand gravel, soft and hard murum and boulders not exceeding 0.03Cu.M. in size, to required grade, camber and side slopes and conveying the excavated materialwith all lifts and upto a lead of 100 m from outside the edge of excavated area, spreading the sameon embankment or stacking as directed. Specification:  General : This item refers to the bulk excavation, in soils of all sorts, sand, gravel soft and hardmurum and boulders below 0.03 cum size. The excavation shall be for large areas like dam seats,water retaining structures, side gutters, large excavation areas, road works etc. when contractorutilizes excavation machinery like bulldozers, shovels, JCBs and tippers and dumpers fortransportation etc.  Site Preparation : Normally the site as directed by the Engineer-in- charge, on which theconstruction, as per the drawings, is to be started shall be first cleaned and cleared of allobstructions. The loose stones, bushes, rubbish, brushwood, trees along with roots, etc. shall beremoved. The material shall be stacked or disposed off as directed. All the material shall be theproperty of MIDC. After clearing the site, the alignment or center lines or points shall be given bythe Engineer-in- charge. The contractor shall establish the reference marks, benchmark pillars inmasonry with 100 x 100 mm M.S. plate fixed at top. The top of M.S. Plate will represent benchmark connected to GTS. The contractor shall maintain bench mark pillars till completion of worketc., and the widths for excavations shall be clearly marked by the contractor as directed, true toline, curve, level and slope. The contractor shall provide all labour and marking material such aswooden/steel pegs, white lime powder, oil paint, or any other suitable marking material at his owncost and he shall be fully responsible for the correctness of the line, curve and levels and slopes.  Excavation : Before commencement of the excavation the levels shall be taken at x-section withintervals of not exceeding 10 m in respect of plain ground and not exceeding 5 m in respect ofsloping grounds. The interval along x-section shall be as directed by the Engineer -in-charge. Thelevels shall be recorded in the field book and shall be signed by the Engineer-in-charge and theauthorized representative of the contractor in token of acceptance. The contractor shall excavateand remove all the material from the marked area of excavation by using labour, machinery andequipments most suitable for excavation of large quantities in wet or dry condition.  Foundation Preparation : In this classified strata, the foundation road works, gutters, forreservoirs and dam seat, may be provided. Also the foundations for rafts, embedments of pipelinesfor water supply or drainage or gas may be laid in this type of classified soil. The foundation shallbe cleared of all loose material and shall be dressed by chiseling to the smooth surface to thecorrect line and level. The levels of such excavated level when strata changes and or foundationshall be taken and recorded adopting practice as mentioned earlier. The contractor shall notexcavate below the line shown in the drawing or as directed. No foundation of any sort shall be laidunless the Engineer - in-charge approves/passes the foundation and record the dimensions andelevations and types of soils of the foundation pit, trench excavated.  Shoring and Strutting : The cost of shoring and strutting shall not be paid separately unlessprovided in the contract. The type and designing of shoring shall be decided by the contractor, andshall get approved from the Engineer in Charge. Pay Slopes : Pay slopes may be stipulatedaccording to which excavation shall be carried out and paid for. 

Page 122: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Disposal of Excavated Material : All the material obtained from clearing the site or fromexcavation shall be the absolute property of MIDC. All materials obtained from clearing the site andexcavation shall be disposed off or spread or stacked within a lead of 100 meters beyond theexcavated area as directed by the Engineer in Charge. Materials suitable for back-filling or otheruse shall be stacked at a convenient place within a lead of 100 meters as directed for refilling orreuse. No excavated material shall be kept within 1.5 m distance from the outer top edge to avoidthe falling of the stuff in the pit or trench. surplus materials shall be used for levelling the groundaround as directed within a lead of 100 meters. If the surplus materials are required to beconveyed and used or stacked beyond 100 meters contractor shall be paid for extra lead or theextra conveyance as per the terms of contract.  Dewatering : It is the responsibility of the contractor to remove the water accumulated in the pit ortrench, from sub-soil water or from rains or from any other natural source, by manually or bypumping out as required. Unless provided for in the contract separately, no payment shall be madefor bailing out the water. The contractor may be required to provide temporary bunds, or providebypass arrangements to avoid entering of water in the excavation at his own cost. The drainedwater shall be properly disposed off, so as not to cause any damages to the excavated area nor tothe surrounding structures. The contractor shall keep the excavated area dry for measurementsand for laying of foundation mortar or concrete.  Side Slips and Blows : Even after sufficient care of sides, slips or blows occur, they shall beremoved at contractor’s cost.  Backfilling : After excavation is completed, measurements recorded by the Engineer-in-chargeand the foundation raft after construction of masonry/structure or the pipeline is laid, all the shoringshall have to be removed. The backfilling of the pit or trench to the original level or as shown in thedrawing or as directed shall be made from the selected excavated material stacked separately forthat purpose. The material shall be laid in layers of 15 to 20 cm in thickness, watered and thenrammed properly. The backfilling shall only be done after receiving orders from the Engineer-in-charge and without damaging the foundation raft or the pipeline etc.  Protective Measures : All the excavated pits, trenches etc. shall be properly protected from anyaccidents by providing strong fencing around. At night red lantern and watchman shall be kept inproper position to indicate the danger zone. It is the responsibility of the contractor to take theadequate protective measures and safety of the excavation, people and workmen and surroundingproperties and will have to bear t he damages if caused. All the cost of protective measures shallbe included in the item rate.  Item to Include : The item includes all lifts and lead upto 100 m beyond the edge of excavation.The use heavy earth excavating and moving machinery including the fuel, oil, maintenance andrepairs, all taxes and depreciation are included in the item rate. The lead beyond 100m shall bepaid extra under Item No.Gen/A/9.  Mode of Measurement and Payment : The measurements of the original ground profiles atselected locations shall be taken after clearing the site. The measurements of the final excavatedprofile shall be taken if the excavation is less or more as directed by the Engineer - in-charge orshall be measured as per drawings. Excess excavation shall be recorded but shall be paid to thelimited quantity as explained above. The quantity shall be measured in cubic meters and paid atthe rate as per the contract agreement. Deductions for voids shall be made @ 40% if quantity paidon stack measurements. The size of stacks shall be 3.0 m X 2.0 m X 1.0 m size preferably. 3     Conveying material obtained from road cutting including all lifts, and beyond initial lead, layingin layers of 20cms to 30cms, in case of power roller and 45cms to 60cms in case of vibratory

Page 123: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

compactor, breaking clods, dressing to the required lines, curves, grade and section for formationof roads, including leveling, disposing off surplus material in desired manner as directed byEngineer-in-charge etc. complete including taxes , Royalty if any beyond 100 m initial lead.(Disposal or reuse location as shown on drawing) a) Lead up to 5 km. Specification:

General : The work provides conveying the material obtained from road cutting, and laying the

selected material for formation of the road, laying them in 20 to 30 cm layers, breaking clods

dressing to the required lines, curves, grades, cross section etc. (disposing the surplus material as

directed by the Engineer-in-Charge). The obtained excavated material shall have the CBR value

more than 8 if it is used for embankment and the max. dry density shall not be less than 1.75

gm/cc.

Setting Out : For laying the material, the profile shall be set up with poles to mark the center and

edges of the formation, top levels.

Conveying : All lifts and leads in conveying the material to site shall be included in the rate as

specified. Contractor shall be responsible to see that the vehicles used for transporting the material

do not drop any of the contents on the road and thus cause nuisance to traffic. The contractor shall

be responsible for any damage or accident arising out of any such material. The contractor shall

remove such material at his expenses. The vehicle conveying the material shall not obstruct the

traffic. The contractor may use manpower scrapers, dozers, graders, shovels, dumpers, trucks,

trollies, etc. for conveying the material. The maintenance of all above equipments, any taxes,

insurance, depreciation etc. shall be deemed to be included in the item rate. No separate claim

shall be entertained. If the useful material available from the road cutting is not used and materials

obtained from other sources are used, by the contractor for his own convenience, such materials

shall be deemed to have been obtained from the road cutting to the extent to which useful

materials

were available for the banking and shall be paid for under this item.

Laying the Material : Conveyed material shall be placed in 20 cm to 30 cm thick layers,

consolidated by 8 to 10 tone road roller. The conveyed material shall be placed in layers 40 cm to

50 cm thick layers if compaction with vibratory compactor. The conveyed material shall be spread

for full width of embankment and compacted full section specified. The extra loose stuff at the

edges shall be trimmed later without extra cost, leaving the correct section fully compacted. The

watering every layer to O.M.C. and compaction of the same shall be paid of separately under

relevant item incorporated in the tender. The camber shall be provided while carrying out

embankment work and shall not be adjusted in metal ling (compaction shall be paid under relevant

item separately).

Disposal : The surplus material shall be conveyed and laid at the location as directed by the

Engineer-in-Charge. The cost of the disposing the surplus material at a given location as directed

is included in the rate.

Item to Include : Item includes, conveying the material from road cutting and laying the same in

layers or (disposing the material as directed), including lead as specified the transporting,

Page 124: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

machinery, labour for loading and unloading, all tools and equipment etc.

complete.

Mode of Measurement and Payment : The contract rate is per cum of the excavated material

conveyed and laid in layers. The quantity shall be worked out by cross sectional measurements

using leveling instruments. The measurements of the sections shall be limited to the dimensions

shown on the drawings or those ordered by the Engineer-in-Charge in writing. The dimensions

shall be recorded correct up to cm. The sectional areas shall be worked out correct upto two

places of decimals.

                                    

4     Earthwork in embankment with approved material having field soak CBR not less than 8 and

laboratory soak CBR not less than 12 obtained by the Contractor from his borrow areas including

all lifts and leads including laying in layers of 20cm to 30cm for power roller and 45cm to 60cm for

vibratory compactor, breaking clods, and dressing to the required lines, curves and section

including payment of royalty charges to the Govt. of Maharashtra. (Lead shall be certified by Dy.

Engr.) c) Any Lead (from 10 to 20 km)

Specification:

 General : The work provides setting out and preparing the ground and formation embankment for

the road with approved quality materials obtained from the contractor’s borrow areas, laying in

layers, of 20 cm to 30 cm to the required density, lines, curves, grades and cross section and

dimensions shown on the plan or as directed by the Engineer-in- Charge with due allowance for

shrinkage for compaction.

Material : All the useful and acceptable materials of approved quality obtained from the

contractor’s borrow areas shall be used for the embankment work. The borrow areas shall be got

approved prior to bringing material to site of work from the Engineer-in-Charge. All the useful and

approved material obtained from contractor’s borrow areas as directed shall be used for the

embankment work. Approved quality murum or a mixture of sand, murum, gravel, small boulders

or rubble as approved shall be used. Black cotton soil, shadu or shrinkable soils shall not be used.

Murum having laboratory dry density of less than 1.65 gm/cc shall be rejected. For embankments

upto 3 m in height, murum with laboratory dry density of less than 1.65 gm/ cc shall not be used.

Only the tested materials approved by the Engineer-in-Charge shall be used for the embankment.

Rejected materials shall not be brought to the work site. The perishable materials such as stumps,

pieces of wood, roots, rubbish, etc. shall be removed from the embankment material. The material

required for embankment shall be obtained by the contractor from the approved quarries by the

Engineer-in-Charge: - All lifts and specified leads involved in conveying the material to site shall be

included in the rate. The payment of taxes, duties, octroi and royalty as per rules and regulations

levied by the Govt. shall have to be paid by the contractor. The Contractor shall be responsible

regarding any claims if any, that may be made by private owners. The payment of royalty charges

is to be born by the contractor and no reimbursement from MIDC is admissible.

Setting Out : Alignment of the road shall be set out as shown in the drawing or as directed to true

lines, curves, and grades. Profiles shall be set out with stout poles to mark the center and edges of

Page 125: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the formation width with the top levels of formation clearly marked by paint or cut and the slopes

with string and pegs at every 30 meters on straight portions and 10m or less on curves or as

directed by the Engineer-in-Charge. The toe line shall be marked with pick marks.  Longitudinal

and cross-section levels shall be taken recorded and signed by the contractor or his authorized

representative and also by the Engineer-in-charge. All the materials and labour required for this

item shall be supplied by the contractor and profiles, B.M.s etc. shall be put up by the contractor.

The cost of these operations is included in the rate of this item. Profiles, pegs, benchmarks and

other marks shall be maintained without any disturbance till the completion of the work, and as

directed by the Engineer-in-charge.

Equipment: Pickaxes, crowbars, phawras, and Ghamelas maybe used for carrying out work

manually. The scrapers, dozers, graders, shovels, dumpers, trucks, trolleys, etc. may be used for

executing work using mechanical equipments. Three wheels, 8 tones Power Roller giving a

pressure required to obtain the specified density may be used for compaction. Bullock carts with

water tanks or mechanically driven water tankers may be used for watering. The contractor shall

submit the list of equipments available with him and intended to be used on the work and shall got

approved for their use from the Engineer-incharge.

 Construction Methods :

 Diversions : If diversions, barricading and signals for day and night are necessary, they shall be

provided without any extra cost.

 Preparing the Ground for Laying Bank : Before any material is laid for the embankment the

ground shall be cleared of all rubbish, removing bushes, etc., and the holes, if any, filled up. When

the embankment is to be laid on hillsides or slopes, the existing slopes shall be ploughed deeply. If

the cross slopes are steeper than 1 in 3, steps with reverse slope shall be cut into the slopes to

give proper hold and seating to the bank as directed by the Engineer-in-Charge. On surfaces flatter

than 1 in 15, no special surface treatment such as cutting steps shall be necessary. The top 15 cm

of soil shall be scarified and watered as directed and compacted to the same density as specified

for the embankment before any  material is laid for the Bank-work. When the embankment is to be

placed over an existing road, which is within 15 cm of the finished formation, the road or other hard

surface shall be scarified to a minimum depth of 15 cm for which payment shall be made

separately under relevant item of road excavation. The rate for embankment includes all the

operations for preparing the bed for laying the embankment material.

Laying the Bank : Embankment material shall be placed in successive horizontal layers of 20 cm

to 30 cm thickness extending to the full width of the embankment including the slopes at the level

of the particular location and 30 cm more on both sides to allow compaction of the full specified

section. The extra loose stuff at the edges shall be trimmed after completion of the embankment

work without extra cost leaving the correct section fully compacted. Keeping width of the bank

initially less and widening it later by dumping loose earth on the slopes shall not be permitted as

the additional width and slopes may remain loose and uncompacted and may not have been

compacted as earlier carried out work. Similar procedure to extend the embankment by dumping

the material longitudinally shall also not be allowed. When boulders, broken stones, and similar

hard materials are mixed up with the embankment materials, care shall be taken to see that they

Page 126: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

are distributed uniformly in to the embankment and that no hollows are left near them. No stone or

hard material shall project above the top of any layer. Each layer of embankment shall be watered,

leveled and compacted as specified, before the succeeding layer is placed. The surface of the

embankment shall, at all times during construction, be maintained at such a cross fall to shed

water and prevent ponding. If bridges and culverts on the road are not completed in advance of

embankment work, a length of 15 m bank shall be left on each side of the structure and these

lengths shall dealt  with later for  placing the embankment work. The contractor shall construct

temporary diversion road till the work of culverts and bridges are completed and all type of traffic is

allowed to be passed on these bridges and culverts. The camber stipulated shall be provided in the

embankment only and shall not be adjusted in metalling.

Protection : Proper care shall be taken to ensure that the method of operation and compaction of

the bank-work does not cause damage or undue strain to any structural element. Embankment

over and around bridges or culverts shall be of approved materials and carefully placed and

compacted. The contractor shall take all precautions necessary for the protection of the bank-work

by diversions of streams, local surface drainage, rain water, etc. likely to damage the bank. Any

damage to  the embankment-work due to no protection or inadequate protection shall be made

good by the contractor at his own cost. Conveyance of materials shall not cause obstruction or

nuisance to the nearby property owners and traffic.

Finishing : The embankment shall be finished and dressed smooth and even in conformity with

the alignment, levels, cross-sections and dimensions shown on the drawing with due  allowances

for shrinkage. On curves, sections shall be provided with super elevation and increased widths as

shown on the plans or directed by the Engineer-in- Charge. All damages caused by rain, flood or

any other reasons shall be made good in the finishing operations without any extra cost by the

contractor. The road land width shall be cleared.

Maintenance : The contractor shall be responsible for maintaining the work satisfactorily at his

own cost till the completion of the defect liability period as specified in the contract  agreement.

 Test :

(a) Tests shall be made to determine the required density of the material to be used by the Proctor

Density Method before starting the work.

(b) The required number of CBR tests and plasticity index tests shall be carried out as directed by

the Engineer-in-Charge.

 Item to include :

1) Setting out alignment including necessary labour and materiel and maintaining it as long as

required and directed by the engineer-in- charge of the work.

2) Preparing the ground for laying the embankment.

3) Providing and maintaining diversions.

4) Obtaining the embankment materials including all lifts and leads as specified under this item and

laying embankment in layers, tests and payment of Royalties, fees, ocrtoi etc., if any. The cost of

testing of material is included in the item of embankment.

5) Protecting and maintaining the embankment.

6) Finishing the embankment

Page 127: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

7) All labours, materials, use of equipments, machinery, tools, survey instruments and plant

necessary for completing the work satisfactorily.

8) Watering to OMC and compaction is not included in the scope of this item and shall be paid

separately under relevant items incorporated in this tender.

Mode of Measurement and Payment :

The quantities shall be  worked out by cross sectional measurement using leveling instruments.

The contract rate shall be per cum of the finished embankment-work, watered and compacted

(watering to OMC and compaction shall be paid separately). The measurement of the sections

shall be limited to the dimensions shown on the drawings or those ordered by the Engineers in

Charge in writing. The dimensions shall be recorded up to two decimals. The sectional areas shall

be worked out up to two decimals. The quantity shall be worked out up to two decimals of a cum.

by average area method. The volume of embankment thus calculated shall be reduced by 16% for

the purpose of payment when the measurements are taken for running bills if watering and

compaction has not done and by 1% in final measurements. The final quantity to be paid for under

this item shall be the total quantity of embankment-work reduced by 1 per cent. 5     Watering to OMC (16 kg to 24 kg of water per Cu.M.) The earth work in embankment in 20 cmto 30 cm layers. (95% proctor density) Specification:

 General : The item provides watering the layers of 20 to 30 cm of embankment laid.

 Material and Equipment : Water to be used shall be free of harmful elements, which may cause

heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall make his

own arrangements for getting adequate quantity of acceptable water. The water tankers shall be

used, without any additional payment.

 Watering : When the murum of the 20 to 30 cm layer in embankment road contains less than the

optimum moisture, water shall be added to the material in the embankment layers of the road to

bring the moisture, uniformly up to requirement. If the material contains more than the required

moisture, it shall be allowed to dry until the moisture is reduced to the required extent. If due to wet

weather etc. the moisture contents of the soil cannot be reduced to the appropriate amount by

exposure, the compaction shall be suspended till suitable conditions prevail without contractor’s

claiming any compensation.

 Item to Include : All material, equipment machinery labour, taxes etc. shall be included in the

rate.

 Mode of Measurement and Payment : The measurement shall be taken on Cum. basis of the

embankment of the road watered. 6     Consolidation with proper ramming / rolling in layers the earth work in embankment . (95%proctor density) b) With vibratory roller in 45 to 60 cm layers Specification:

a)With 8-10 tonne roller in 20 to 30cm layers

Page 128: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

 General : The item provides consolidation of the earthwork in embankment in 20 to 30 cm layers

for 8 to 10 tonnes roller and 40 to 50 cm layers for vibratory rollers. This item is to be  executed

after laying the earthwork in embankment in the layers of 20 to 30 cm and the layer is watered.

 Equipment : The ramming rods and 8-10 tone ordinary or vibratory roller as directed shall be

used.

 Consolidation : When a loose layer is leveled manually or mechanically with camber provided

and moistened or dried to a uniform and required moisture content suitable for maximum

compaction, it shall be compacted by power rollers, vibratory rollers or heavy hauling or dozing

equipment to give the specified 95% of the standard proctor density. If on testing, the density is

found to be less than 95% of the standard density the contractor shall do additional compaction

necessary to get the specified density after adding water if required. When the specified density is

imperative, the work shall be removed and redone by the contractor at his own cost to give the

specified density. Proper sequence of all component operations shall be maintained to give

individual progress. For compaction of embankment the road roller shall move longitudinally and

rolling shall be done from edges to centre. The camber shall be provided in the cutting and shall

not be adjusted in metalling. Care shall be taken for getting good compaction behind abutments,

returns and wing walls, etc. Cutting/ Bank-work in areas not accessible to rollers such as those

adjoining bridges, culverts and other works, shall be carried out independently of the main

embankment and shall have the layers placed in 10 cm to 15 cm. thickness and each layer shall

be moistened and thoroughly compacted with mechanical or manual tampers. Embankment shall

be brought up simultaneously in equal layers on each side and compacted carefully to avoid

unequal pressure, etc The compaction of the embankment shall be done by moving road roller

longitudinally from edges to centre.

 Item to Include : The item includes only the compaction of each layer by 8-10 tonne roller or

vibratory roller. All labour and equipment required to execute the item as per above specification

shall be included in the item. If specified vibratory compactors shall be used.

Mode of Measurement and Payment :

The measurement shall be taken of the earthwork for embankment of road in Cum. upto two

decimals. The contract rate shall be for a unit of One Cubic meter of the finished bank work. 7     Supplying 50 mm to 75 mm trap stone oversize metal at the road side including, conveyingand stacking etc. complete including all taxes and royalty and lead up to 20 km. Specification:

General : The item provides the supply of specified type of stone metal 50 mm to 75 mm oversize

at the roadside including obtaining the rubble from approved sources and quality and hand

breaking to size, conveying to the site of work, including all lifts and leads and stacking in regular

stacks as specified.

Material : Metal shall be obtained from the approved quarries as specified below :

Quarries : The contractor shall obtain the metal of the approved quality to the extent required for

Page 129: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the work from the approved and authorized quarries out of approved quality rubble. He shall,

however, obtain the necessary permissions from the competent authorities, pay royalties, duties

and if applicable octroi and be liable to pay compensation for any damage caused to the quarries

or the land or property and adjoining properties either deliberately or through negligence or

otherwise, or from waste of materials in obtaining the requisite quantity of rubble.

Blasting ; if required, shall be done with utmost care according to specification by obtaining

necessary permission for blasting operation from the competent authorities and the contractor

shall be fully responsible for any accidents and compensations resulting there from. Alternatively,

the contractor shall make his own arrangement for supply of hand broken metal approved by the

Engineer-in-Charge. The contractor shall be fully responsible for any and all compensations to be

paid as royalty, rents, octroi and duties or damages to properties and injuries to persons etc.,

caused in obtaining the metal. No claim on account of any obstruction caused in collection of

materials or

difficulties or action arising out of quarrying in private land shall be entertained and MIDC will

remain indemnified with regard to such action and payment. Quarrying shall be done only from

sound portions of approved quarries, the disintegrated and weathered portions shall be rejected.

The payment of royalty shall be made by the contractor and no reimbursement from MIDC is

admissible.

Metal :

Quality : The metal of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering. Their water absorption

shall be as low as possible but not more than 2 per cent. They shall generally be hand broken

metal.

The physical test on metal shall be conducted by Engineer-in- Charge. The cost of such testing

shall be inclusive in unit rate of Item.

Size : The shape of the stone metal shall be regular The stone shall be broken with the smallest

dimensions equal to the 50 mm thickness of oversize metal. The longest dimension shall not be

more than 75 mm. Before starting collection, the contractor shall get a sample conforming to the

required quality shape and size approved from the Engineer-in-Charge who will preserve it in his

site office for reference. The size of the metal shall be between 50 to 75 mm

Conveyance to Site : Materials shall be brought to site for construction. The contractor shall be

responsible to see that vehicles used for transporting materials do not drop any of the contents on

the road and shall not cause nuisance to traffic. The contractor shall also be responsible for any

damage or accident arising out of any such material falling on the road or elsewhere and shall

attend and settle to all complaints in this regard. The Engineer-in-Charge may order the removal of

such materials at the expenses of the contractor in case of negligence. Vehicles conveying or

depositing materials shall not obstruct traffic.  For all leads and lifts included in the rate for the item.

Stacking : The metal shall be stacked uniformly along the roadside or as directed in regular stacks

of 3 m X 2 m X 1 m unless other sizes are ordered by the Engineer-in-Charge. Stacking shall be

done only after the quality, shape and size of the metal are approved. The stacks shall be made

without appreciable hollows without making special efforts to hand-pack the material. The stacks

Page 130: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

shall be free of earth, rubbish, vegetation, inferior or oversize or undersize material. One stack in

each unit section may be of different length if necessary to make up the total quantity in that

particular section. Low and wide stacks with outer retaining walls and the center filled in loosely

shall not be permitted. The material shall be stacked entirely clear of the carriage way and as far

as possible beyond the side widths and the side drains, on even ground or in the absence of such

even ground the platforms prepared in advance for the purpose by the contractor at his cost. If no

such land is available, the width of the stack may be reduced and the stacks may be laid on the

side widths with the approval of the Engineer-in-Charge. Such stacks shall be protected from being

disturbed. Necessary precautions to provide barricading, signs and signals shall be taken, the

contractor being responsible for any accident, injury and compensation due to his negligence in

this respect. On hill roads material shall be stacked only at places where narrow width and stacked

on the side of the road as directed without interfering with free drainage. The Engineer-in-Charge

may, if required, get the stacks coming in the way of or obstructing the traffic, removed at the cost

of the contractor and the contractor shall not be entitled to claim for any loss or damage to the

materials on that account. The stacking operations shall be started at the point farthest from the

quarry and carried towards the nearest point. The stacks shall not be laid at such places where

they are likely to be damaged on account of the traffic, washing out by rains or floods or drainage,

slides of the banks or the slopes of cutting. The contractor without extra claims shall make any loss

on account of these

or such other reasons good. As far as possible the metal shall be stacked evenly on one side of

the

road only and in such quantities per unit length as will be required for that particular length or as

ordered by the Engineer-in-Charge.

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, octroi and duties, fees, rents, taxes etc. compensation due to

injuries to persons or damages to property in any way connected with the execution of this item

and for loss of materials due to improper stacking etc., and shall make good the losses without

extra claims. The contractor shall also be responsible for the blasting operations required for

obtaining the rubble.

Item to Include :

1)         Obtaining metal of approved quality, shape and size from quarry metal, boulder metal,

Laterite metal and making payment of royalties, taxes, fees, rents, octroi and duties etc.

2)         Conveying to roadside including  all lead and  lifts.

3)         Stacking.

Mode of Measurement and Payment : The contract rate shall be for one cubic meter of metal

supplied at site in stacks of approved size.  When the metal is specified to be stacked in stacks of

one uniform size, smallest stack may be chosen in the particular km or unit section and measured

for its length, breadth and depth. The cubic contents of this stack shall be multiplied by the number

of such stacks in the km or unit section to arrive at the quantity in the particular km or unit section. 

The Engineer-in-Charge may measure any other stacks also for verification. When the sizes of

stacks are not uniform, each stack shall be measured individually. The dimensions shall be

Page 131: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

measured correct to two places of decimal of a meter and quantity worked out correct to two

places of decimals of a cubic meter. If there is reason to believe that the stacks are very loose and

are having unduly large hollows and or materials not satisfying the specifications, the stacks may

be got opened and restacked properly after removing the inferior material as directed by the

Engineer- in-

Charge by the contractor at his cost. The measurements of such a stack shall then be taken and if

they are less than those of a normal heap, the quantity of the restacked stack shall be multiplied by

the no. of stacks to arrive at the quantity in the particular unit or length. No deduction shall be

made for voids. 8     Supplying 40 mm trap stone metal at the roadside including conveying and stacking completeincluding all taxes and royalty. Lead up to 20 km complete. Specification:

General : The item provides the supply of specified type of stone metal 40 mm size at the roadside

including obtaining the rubble from approved sources and hand breaking to size, conveying to the

site of work, including all lifts and leads and stacking in regular size as specified including making

payment for royalty and other taxes, octroi and duties etc.

Material : Metal shall be obtained from the approved quarries as specified below:

Quarries : The contractor shall obtain the metal of the approved quality to the extent required for

the work from the approved and authorized quarries. The contractor shall, however, obtain the

necessary permissions from the appropriate authorities, pay royalties and will be liable to pay

compensation for any damage caused to the quarries or the land or property either deliberately or

through negligence or otherwise, or from waste of materials in obtaining the requisite quantity of

rubble.  The contractor shall make his own arrangement for metal supply approved by the

Engineer-in-Charge. The contractor shall be fully responsible for any and all compensations to be

paid as royalty, rents, octroi & duties or any other statutory charges or damages to properties and

injuries to persons etc., caused in obtaining the metal. No claim on account of any obstruction

caused in collection of materials or difficulties or action arising out of quarrying in private land shall

be entertained and MIDC will remain indemnified with regard to such action and payment.

Quarrying shall be done only from sound portions of approved quarries, the disintegrated and

weathered portions being rejected.

1.2.2    Metal :

Quality : The metal of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering and scale. The water

absorption shall be as low as possible but not more than 2 per cent. It shall generally be hand

broken metal. The metal shall be cubical in nature and shall pass the desired sieve.  The physical

test on metal shall be conducted by approved laboratory in the presence Engineer-in-Charge or his

representative. The cost of such testing shall be inclusive in unit rate of item.

Size : The shape of the stone metal shall be cubical. The stone shall be broken with the smallest

dimensions equal to the 40 mm thickness of size metal.

Page 132: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Before starting collection, the contractor shall get a sample conforming to the required quality

shape and size approved by the Engineer-in-Charge who will preserve/keep it in his site office for

reference. The size of the metal shall be 40 mm.

Conveyance to Site : Materials shall be brought to site sufficiently in advance of construction. The

contractor shall be responsible to see that vehicles used for transporting materials do not drop any

of the contents on the road and thus cause nuisance to traffic. The contractor shall also be

responsible for any damage or accident arising out of any such material falling on the road or

elsewhere and shall attend to all complaints in this regard. The Engineer-in-Charge may order the

removal of such materials at the cost of the contractor in case of negligence/or any other reason.

Vehicles conveying materials shall not obstruct traffic.  For all leads and lifts included in the rate for

the item.

Stacking : The metal shall be stacked uniformly along the roadside or as directed in regular stacks

of 3 m X 2 m X 1 m unless stacks of other sizes are ordered by the Engineer-in-Charge. Stacking

shall be done only after the quality, shape and size of the metal are approved. The stacks shall be

made without appreciable hollows without making special efforts to hand-pack the material. The

stacks shall be free of earth, rubbish, vegetation and shall confirm size specified. One stack in

each unit section may be of different length if necessary to make up the total quantity in that

particular section. Low and wide stacks with outer retaining walls and the center filled in loosely

shall not be permitted. The material shall be stacked entirely clear of the carriage way and as far a

possible beyond the side widths and the side drains, on even ground or in the absence of such

even ground the platforms prepared in advance for the purpose by the contractor at his cost. If no

such land is available, the width of the stack may be reduced and the stacks may be laid on the

side widths with the approval of the Engineer-in-Charge. Such stacks shall be protected from being

disturbed. Necessary precautions such as barricading, signs and signals shall invariably be taken,

the contractor being responsible for any accident, injury and compensation due to his negligence in

this respect. On hill roads material shall be stacked only the side of the road as directed without

interfering with free drainage.  The Engineer-in-Charge, if required, get the stacks coming in the

way of or obstructing the traffic, removed at the cost of the contractor and the contractor shall not

be entitled to claim for any loss or damage to the materials on that account. The stacking

operations shall be started at the point farthest from the quarry and carried towards the nearest

point. The stacks shall not be laid at such places where they are likely to be damaged on account

of the traffic, washing out by rains or floods or drainage, slides of the banks or the slopes of

cutting. The contractor without extra claims shall make any loss on account of these or such other

reasons good.

As far as possible the metal shall be stacked evenly on one side of the road only and in such

quantities per unit length as will be required for that particular length or as ordered by the

Engineer-in-Charge.

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, octroi & duties, fees, rents, taxes etc. compensation due to

injuries to persons or damages to property in any way connected with the execution of this item

and for loss of materials due to improper stacking etc. And shall make good the losses without

Page 133: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

extra claims.  The contractor shall be also responsible for the blasting operations required for

obtaining the rubble.

Item to Include :

1)         Obtaining metal of approved quality, shape and size from quarry metal, boulder metal and

making payment of royalties, taxes, fees, rents, octroi & duties etc.

2)         Conveying to roadside including all lead and lifts.

3)         Stacking.

Mode of Measurement and Payment : The contract rate shall be for one cubic meter of metal

supplied at site in stacks of approved size.  When the metal is stacked in stacks of one uniform

size, smallest stack may be chosen in the particular km or unit section and measured for its length,

breadth and depth. The cubic contents of the stack shall be multiplied by the number of such

heaps in the km or unit section to arrive at the quantity in the particular km or unit section. The

Engineer-in-Charge may measure any other heaps also for verification.  When the sizes of stacks

are not uniform, each stack shall be measured individually. The dimensions shall be measured

correct to two places of decimal of a meter and quantity worked out correct to two places of

decimals of a cubic meter. If there is reason to believe that the stacks are very loose and are

having unduly large hollows and or materials not satisfying the specifications, the stacks may be

got opened and restacked properly  after removing the inferior material as directed by the

Engineer-in-Charge by the contractor at his cost. The measurements of such a stack shall then be

taken and if they are less than those of a normal stack, the quantity of the restacked stack shall be

multiplied by the no. of stacks to arrive at the quantity in the particular unit or length.  No deduction

shall be made for voids. Metal shall not be used until the full quantity is collected in km or particular

unit and measured. All stacks measured shall be marked with lime wash bands to distinguish them

to avoid double measurement.  If the material is found to be of inferior quality or of size not

satisfying the requirements, the same shall be rejected entirely.  All labour, materials etc. required

for measuring, restacking, checking, lime washing, etc., shall be at the cost of contractor.  The

contract rate shall be for one cubic meter of specified metal supplied at site in stacks of approved

size. 9     Providing trap / stone / granite stone metal at the work site as directed in stacks of minimumsize of 3 x 2 x 1 m or as directed in stacks of higher sizes than the minimum tipulated aboveIncluding all loading / unloading operation and conveyance to the site of work lead up to 10 km.including all taxes and royalty charges. d) Standard size 25 mm (Crushed aggregate) Specification:

General : The item provides supply of stone aggregate of the specified type and size at the site of

work, including obtaining the stones of the specified quality from approved sources, manually

breaking or crushing them in mechanical crushers, loading into conveyor and unloading at sit of

work conveying for all  leads and all lifts, stacking in regular heaps as specified.

Material : Stones of approved quality shall be used for hand broken or crushed aggregate.

Quality : The rubble of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering. The water absorption shall

Page 134: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

be as low as possible but not more than 2 per cent. They shall generally be broken rubble.

Stone Aggregate : The aggregates shall be obtained by crushing approved stones of specified

type in a mechanical crusher and shall be clean, strong, tough, dense, durable, close grained and

free from soft,  decayed and weathered portions and from coating of dust, dirt or other

objectionable matter. They shall preferably have good hydrophobic characteristics. The metal shall

generally satisfy the following physical requirements:-

Tests shall be carried out according to I.S.383-1970

Tests considered necessary shall be carried out in an approved laboratory.

Size of Metal shall be as under:-

Note :- Not more than 20% of any sample shall exceed in its greatest dimension standard size plus

25 mm. For 40 mm. Standard size, standard size plus 8 mm. For 25 mm, 20 mm and 12 mm

standard sizes and standard size plus 6 mm for 10 mm and 6 mm standard sizes plus 4 mm.  The

metal shall be roughly cubical in shape and of uniform size with sharp edges for interlocking.

Rounded, flaky thin, elongated metal shall not be accepted. Before collection, samples of the metal

shall be got approved for quality size and shape by the Engineer-in-Charge who will preserve them

in his site office for reference. They shall be completely dry at the time of use.

Conveyance : Materials shall be brought to site sufficiently in advance of construction. The

contractor shall be responsible to see that vehicles used for transporting materials do not drop any

of the contents on the road and thus cause nuisance to traffic. The contractor shall also be

responsible for any damage or accident arising out of any such material falling on the road or

elsewhere and shall attend to all complaints in this regard. The Engineer-in-Charge may order the

removal of such materials at the expenses of the contractor in case of neglect. Vehicles conveying

or disposing materials shall not obstruct traffic.  For all leads and lifts included in the rate for the

item.

Stacking : The material shall be stacked uniformly along the roadside or as directed in regular

stacks of minimum size 3m X 2m X 1 m unless other sizes are ordered by the Engineer-in-Charge,

stacking shall be done only after the quality, shape and size of the material are approved. The

stacks shall be made without appreciable hollows without making special efforts to hand-pack the

material. The stacks shall be free of earth, rubbish, vegetation, inferior or too much oversize or

undersize material. One stack in each unit section may be of different length if necessary to make

up the total quantity in that particular section. Low and wide stacks with outer retaining walls and

the center filled in loosely shall not be permitted. The material shall be stacked entirely clear of the

carriage way and as far a possible beyond the side widths and the side drains, on even ground or

in the absence of such even ground the platforms prepared in advance for the purpose by the

contractor at his cost. If no such land is available, the width of the stack may be reduced and the

stacks may be laid on the side widths with the approval of the Engineer-in-Charge. Such stacks

shall be protected from being disturbed. Necessary precautions such as barricading, signs and

signals shall invariably be taken, the contractor being responsible for any accident, injury and

compensation due to his negligence in this respect. On hill roads material shall be stacked only on

the side of the road as directed without interfering with free drainage. The Engineer-in-Charge

may, if required, get the stacks coming in the way of or obstructing the traffic, removed with the

Page 135: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

cost of the contractor and the contractor shall not be entitled to claim for any loss r damage to the

materials on that account. The stacking operations shall be started at the point farthest from the

quarry and carried towards the nearest point. The stacks shall not be laid at such places where

they are likely to be damaged on account of the traffic, washing out by rains or floods or drainage,

slides of the banks or the slopes of cutting. The contractor without extras claims shall make any

loss on account of these or such other reasons good. As far as possible the metal shall be stacked

evenly on one side of the road only and in such quantities per unit length as will be required for

that particular length or as ordered by the Engineer-in-Charge. Each size of aggregate shall be

stacked separately and entirely clear from the carriageway and where possible clear of the

shoulders also. They shall be stacked in such a manner as to prevent mixture, deterioration or

contamination

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, fees, rents, taxes, octroi, duties, etc. Compensation due to injuries

to persons or damages to property in any way connected with the execution of this item and for

loss of materials due to improper stacking etc. and shall make good the losses without extra

claims. The contractor shall also responsible for the blasting operations.

Item to Include :

1) Obtaining metal of approved quality, shape and size from  quarry metal, boulder metal, Laterite

metal and payment of royalties, taxes, octroi, duties, fees, rents, etc.

2) Conveying to roadside including  all lead and lifts.

3) Stacking.

Mode of Measurement and Payment :

The contract rate shall be for one cubic meter of material supplied at site in stacks of approved

size. When the material is stacked in stacks of one uniform size, smallest stack may be chosen in

the particular km or unit section and measured for its length, breadth and depth. The cubic

contents of this heap shall be multiplied by the number of such stacks in the km or unit section to

arrive at the quantity in the particular km or unit section. The Engineer-in-Charge may measure

any other stacks also for verification. When the sizes of stacks are not uniform, each stack shall be

measured individually. The dimensions shall be measured correct to two places of decimal of a

meter and quantity worked out correct to two places of decimals of a cubic meter. If there is reason

to believe that the stacks are very loose and are having unduly large hollows and or materials not

satisfying the specifications, the stacks may be got opened and restacked properly after removing

the inferior material as directed by the Engineer- in charge at the contractor’s cost. The

measurements of such a stack shall then be taken and if they are less than those of a normal

heap, the quantity of the restacked heap shall be multiplied by the no. of stacks to arrive at the

quantity in the particular unit or length. No deduction shall be made for voids. Material shall not be

used until the full quantity is collected in km or unit length and measured. All stacks measured shall

be marked with lime wash bands to distinguish them to avoid double measurement. If the material

is found to be of inferior quality or of size not satisfying the requirements, the same may be

rejected entirely. All labour, materials etc. required for measuring, restacking, checking, lime

washing, etc. shall be at the cost of contractor.

Page 136: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

10     Picking the old WBM surface up to a depth of 75 mm and re-sectioning, barreling andbringing the surface to proper camber, alignment, gradient, including providing V groove at theperiphery of road surface. Specification:

General : The item provides picking the old WBM road surface and resectioning of the road

surface.

 Road Diversion : while carrying out the picking operations, if the traffic cannot be allowed to pass

over the side shoulders, suitable diversions shall be provided and maintained till necessary by the

contractor at his risk and cost.

 Picking Operation : All the caked mud, slush animal droppings, vegetation and all other rubbish

accumulated on the road-surface shall be removed. Where the section of the road surface is good,

the road surface shall be picked lightly only to loosen the surface stones. Where the section is

uneven picking shall be done a little deeper to enable the sectioning to be done to the required

shape with the picked up material. The picking shall always be ahead of the spreading of metal

and compaction by about 100 metres. The edges of the picking shall be truly in a line or curve as

the case may be. This can be achieved by tying strings to nails driven on the road edges and

ranging for a sufficiently long length. The picked up surface shall be sectioned to the required

grade and camber, super elevation or transition section. Templates shall be used to obtain correct

and uniform camber, super elevation or transition section as the case may be The V groove shall

be provided on either side of the road edges as directed, so as to avoid sliding away metal spread.

The road surface may be watered by the contractor for easier picking without claiming, extra for

the same. The junction of the picked and non-picked surfaces shall be diagonal. 

Item to Include : The item includes all labour, materials, use of tools and equipment, etc. for

picking. It also includes watering, if required, sectioning, barreling, grading, diversions, including

barricading, warning signals, lights, etc., unless separately provided in the tender.

 Mode of Measurement and Payment : The areas picked shall be worked out in sq. metres. The

width shall be limited to the width specified or as ordered by the Engineer-in-Charge. The length

shall be measured along the centerline of the road. Increased width on curves shall be measured.

                                                                       

The Contract rate shall be for one sq. meter of surface picked and sectioned. 11     Spreading in compact layers oversize and size metal to the required camber and gradient. Specification:

 General : This item provides to the labour work for spreading the oversize or size metal and

spreading it for the road crust.

Material : The oversize and size metal shall be supplied and stacked by the contractor, or metal

obtained by breaking rubble broken and stacked by the contractor available from cutting or rubble

supplied by MIDC from other sources.

 Spreading Metal : Before commencement of spreading oversize metal it should be ensured that

Page 137: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

finished embankment/cutting is with proper camber and gradient. The metal shall be clean and

then spread evenly over the rolled rubble-soling surface or on any formation by giving a twisting

motion of the basket at the time of spreading. In order to ensure that the metal is spread to the

exact width on either sides, V groove is excavated. To ensure the correct thickness, the road area

shall be suitably marked so as to receive the contents of one stack for the specified thickness in

the area marked. The unevenness and undulations after the spreading shall be checked by

camber boards and line for the camber and grade at intervals of every 10 meters. The edge line

shall be ranged for a sufficiently long length to obtain straight lengths and on curves marking outer

and inner edges of curves. The sides of the metal shall be held by bunds of murum to prevent

metal from spreading if side widths are not provided at the time. These bunds shall be of such

depth as to support the metal. The junction of the existing road and the new construction shall be

diagonal in plan. Between the straight lengths and curves and at the meeting points of convex and

concave portions of reverse curves the change in the camber shall made very gradually as

directed by the Engineer-in-Charge. The thickness of spread oversize/size metal shall be uniform

through out width of road camber should not be adjusted by spreading oversize/size metal of

differential depths.

 Item to Include : Conveying the metal from the road side, stacks and spreading evenly to the

required depth, width and section. All labour tools and equipment required for the satisfactory

completion of the item.

 Mode of Measurement and Payment : The quantity spread shall be calculated by deducting the

quantity in balance on site from the total collection existing on the roadside before spreading is

started. The quantity on site shall be checked before spreading. The contract rate shall be for

spreading one cubic meter of metal from collected stacks as per direction of Engineer-in-Charge. 12     Spreading hard murum, or blindage collected in roadside stack over the top of soling oroversize metal or size metal including evening it into top of crevices (Road side stacks of murumwill be measured including voids without deducting allowance for compaction, separately and paidfor under relevant item of embankment of road whichever is applicable.) Specification:

 General : The item provides the labour for spreading hard murum or blindage from the roadside

stacks over soling/oversize metal/size metal.

 Material : The murum or blindage shall be confirming to the approved quality.

 Spreading Hard Murum : The hard murum or blindage shall be clean and without any foreign

material, granular and spread evenly over the rubble-soling or over the rolled oversize or size

metal surface by giving a twisting motion to the basket at the time of spreading. In order to ensure

the correct thickness, the road area shall be suitably marked so as to receive the contents of one

stack for the specified thickness in the area marked. The spread minimum shall be sweeped by

iron fork evenly to fill the crevices/interstics of the laid soling/metal surfaces. The unevenness and

undulations after the spreading of the murum shall be checked by using camber boards and line

for the camber and grade at intervals of every 10 meters. The edge line shall be ranged for a

sufficiently long length to obtain straight lengths and ,on curves marking inner and outer edge of

Page 138: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the curve In hand packed soling or rolled oversize metal the murum equivalent to 33% of cum.

quantity of rubble soling/oversize metal shall be spread. In respect of size metal the murum

equivalent to 16% of cum of size metal laid shall be spread over.

 Item to Include : Conveying the hard murum or blindage from the road side stacks and spreading

evenly to the required depth, width and section. All labour, tools and equipment and required for

the satisfactory completion of the item shall be provided by contractor.

Mode of Measurement and Payment : The quantity spread shall be calculated by deducting the

quantity in balance on site from the total collection existing on the roadside before spreading is

started. The quantity on site shall be checked before spreading. The contract rate shall be for

spreading one cubic meter of hard murum or blindage collected in stacks. 13     Watering over sub-grade consisting of soling and / or oversize metal. Specification:

 General : The item provides the watering over soling, oversize and size metal.

 Material and Equipment : Water to be used shall be free of harmful elements, which may cause

heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall make his

own arrangements for getting adequate quantity of acceptable water. Only just sufficient water as

is necessary shall be sprinkled uniformly with the help of water tanker and/or sprinkler over the

hard murum/blindage so as to obtain maximum compaction with the type of rolling adopted without

total crushing of the material. The water shall be used profusely small fillets shall be provided at

edges so that the water will not flow away. The roller shall move in water slurry which will penetrate

into crevices all voids in metal shall feet fill in and proper bond in the metal shall be formed.

 Item to Include : All clean water, material, machinery, equipment, labour, taxes etc. shall be

included in the rate.

 Mode of Measurement and Payment : The measurement shall be the area of road surface

watered in sqm upto two decimals. The payment shall be at the rate per sqm. 14     Consolidation over sub-grade consisting of soling and / or oversize metal and hard murum by8-10 tonne roller until proper interlocking etc. complete b) With 30 tonne vibratory roller Specification:

a) with 8 – 10 tonne roller

b) with vibratory compactors

 General : The item provides for full compacting/consolidating the

sub-grade with soling and/or oversize metal layers and hard murum

with 8-10 tonne roller/vibratory compactor as directed.

 Consolidating the Sub-Grade and the Soling : The sub-grade, of and

soling and/or oversize metal and murum layer shall be rolled after it is

dressed to the required grade, camber and section. The soling shall be

rolled dry with 8 to 10 tonne roller or vibratory roller 8 to 10 tonne to

refusal i.e. till the stones in the soling cease to move under the roller

Page 139: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

and no more compaction can be achieved. In case of unevenness, high

spots shall be knocked out and depressions filled by spalls and

recompacted fully. ‘V’ groove shall be cut along the edges and

compacted before starting rolling on subgrade to prevent spreading of

stones.

 Compaction of Oversize, Size Metal and Murum : The compaction

shall be done with a 8-10 tonne ordinary or vibratory roller of 8 to 10

tonne capacity as directed by Engineer-in-charge. The rolling shall

begin with the outside rear wheel of the roller covering equal parts of

shoulder and metal and the roller shall be run forward and backward

until the shoulder holds the metal firmly. The rolling shall then

progress from edges to the center in strips parallel to the centerline of

the road. Rolling shall be done by lapping uniformly each preceding

rear wheel track by one half width of the track and shall continue until

all the surface has been rolled by the rear wheels till the impression of

the rear wheels does not appear on road surface. Side fillets shall be

raised to avoid water flowing away. ‘V’ groove shall be excavated on

either edges before spreading the metal so that the metal will not move

beyond the edges.

On super elevations, the rolling shall be started at the inner edge and

carried towards the outer edge. In all cases, the correct cross sections

of the road as required at straight portions, super elevations and

transitions shall be obtained on final rolling. During and after rolling,

the sections, camber and grades shall be checked with camber boards

and straight edge and any defect set right at the time of rolling. Care

shall be taken to see that the rolling work is started and stopped

without jerks. The roller shall not be stopped in the working section

as far as possible. Rolling shall not normally be done in lengths of less

than 100 m. The stretch started on a particular day shall as far as

possible be completed on the same day. On completion of day’s work,

the roller shall be made to stand on the side width of the road and shall

be guarded by watchmen and conspicuous barricades, caution boards

and Red light shall be hung on to the roller so as to be visible from

both sides of the road.

 Dry Rolling of Oversize Metal : The layer of metal shall be rolled dry

first with 8-10 tonne roller or vibratory roller as may be specified i.e.

till the metal is completely interlocked and ceases to move under the

roller and no more compaction can be achieved. This state can be

judged by -

1) metal ceasing to move in front of the roller or,

2) crushing of the metal with further rolling or,

Page 140: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

3) loaded bullock cart leaving no indentation over the compacted

surface.

In case of uneven spots, high spots shall be lowered by removing

necessary metal pieces and depressions shall be filled by additional

metal and full compaction of these portions redone to confirm to the

correct section.

 Wet Rolling : The rolled surface shall then be watered freely

(Watering item shall be paid under item of watering separately) and

rolled again. Blindage shall then be spread as per requirement to a

uniform thickness of specified thickness as directed by the Engineerin-

Charge and further rolling done to pack the interstices with blindage

small fillets shall be provided on either edges of metal width.

Watering shall be done profusely as directed by Engineer-in-Charge

and the surface finally rolled to the satisfaction of the Engineer-in-

Charge. The road roller should move in thin slurry so that the slurry

penetrates in the crevices of metal leaving no voids and thick bond

between metal is developed.

 Item to Include : The item includes all the labour, machinery and

equipment for rolling over the sub-grade and the soling and gravel

including all cost of machinery, labour and all other charges involved.

Making good unevenness if any by cutting or adding is also included.

 Mode of Measurement and Payment : The contract rate shall be for

compacting one sqm area of the road surface of the full width of subgrade,

soling, oversize metal and murum blindage as shown in the

section including increased widths on curves, road crossings etc.

The area of the road compacted shall be measured in sqm. 15     Watering over size metal and blindage during consolidation by 8- 10 tonne roller over finalsurface of size metal and blindage until proper interlocking etc. complete. b) With 30 MT vibratoryroller/compactor Specification:

General : The item provides watering and compacting to the final surface of size metal and

blindage until proper interlocking.

Material and Equipment : Water to be used shall be free from harmful elements, which may

cause heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall

make his own arrangements for getting adequate quantity of acceptable water.  The water tankers

and 8-10 tonne 3 wheel road roller shall be used. If directed vibratory roller shall be used for proper

compaction.

Watering : Small fillets shall be constructed on either edges of metal width so that the water

sprinkled will not flow away. Only just sufficient water as is necessary shall be sprinkled uniformly

Page 141: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

with the help of water tanker and sprinkler over the size metal and blindage so as to obtain

maximum compaction with the type of rolling adopted without total crushing of the metal. The water

shall be used profusely. The roller shall move in plastic murum slurry which will penetrate into

crevices of in the metal making good bond between metal.

Compaction of Size Metal & Murum : The compaction shall be done with 8-10 tonne ordinary or

vibratory roller of 8 to 10 tonnes capacity as directed by the Engineer-in-Charge. The rolling shall

begin with the outside rear wheel of the roller covering equal parts of shoulder & metal & the roller

shall be run forward and backward, until the shoulder holds the metal firmly. The rolling shall then

progress from edges to the center in strips parallel to the centerline of the road. Rolling shall be

done by lapping uniformly each preceding rear wheel track by one half width of the track & shall

continue until all the surfaces has been rolled by the rear wheels till the impression of the rear

wheels does not appear. Side fillets shall be raised to avoid water flowing away. ‘V’ groove

excavated on either edges of metal width will avoid sliding metal beyond width of metal and edge

will remain in straight line. On super elevations, the rolling shall be started at the inner edge and

carried towards the outer edge. In all cases, the correct cross section of the road as required at

straight portions, super elevations and transitions shall be obtained on final rolling. During and after

rolling the sections and grades shall be checked with camber boards and straight edges and any

defect is set right at the time of rolling. Care shall be taken to see that the roller is moved or started

and stopped without jerks. The roller shall not be stopped in working section as far as possible.

Rolling shall not normally be done in lengths of less than 100 m. The stretch started on a particular

day shall as far as possible be completed on the same day. On completion of day’s work, the roller

shall be parked on the side width of the road and shall be guarded by the watchman and

conspicuous barricades. Red light shall be hanged on the roller so as to be visible from both sides

of the road.

Dry Rolling of Size Metal : The layer of metal shall be rolled dry first with 8-10 tonne roller/

vibratory compactor to refusal i.e. till the metal is completely interlocked and ceases to move under

the roller and no more compaction can be achieved. This state can be judged by,

i) Metal ceasing to move in the front of the roller.

ii) Crushing of the metal with further rolling or

iii) Loaded bullock cart leaving no identification over the compacted surface.

In case of uneven spots, high spots shall be lowered by removing necessary metal pieces and

depressions shall be filled by additional metal and full compaction of these portions redone to

confirm to the correct section.

Wet Rolling : Small murum fillets shall be constructed on either edges of the metal width. The

rolled surface shall then be watered freely and rolled again. Blindage shall then be spread to a

uniform thickness of specified thickness as directed by the Engineer-in-Charge and further rolling

done to pack the interstices with blindage. Watering shall be done profusely as directed by

Engineer-in-Charge and the surface finally rolled to the satisfaction of Engineer-in-Charge. The

fillets constructed on either edges of metal width will avoid the water flowing away. The roller shall

move in plastic murum slurry which will penetrate in the crevices in the metal and bond will be

developed in the metal.

Page 142: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Item to Include : all material, machinery equipment, labour, taxes etc. shall be included in the rate.

Mode of Measurement and Payment :

The measurement shall be taken of the area of road surface watered and compacted, in sqm upto

two decimals. The payment shall be at the rate per sqm. 16     Providing dry rubble pitching using sufficiently large face stones of approved quality for anaverage depth of 225 mm including providing one header in one Sq.M. of pitching area complete,including all leads. a) Quarry rubble pitching Specification:

General : The item provides for dry rubble stone pitching of 23 cm.

Thick for the road work.

 Material : The rubble stones for pitching shall be sound, hard and

durable and fairly regular in shape. The depth of the stones shall be

about equal to the specified thickness of 225 mm and stone shall

generally be not less than 10 liter in volume or the size as directed by

the Engineer-in-Charge. The smaller size stones required for packing

and wedging shall be brought to the site only to the required extent and

they shall not be used in two or more thickness as a substitute for the

stones of full thickness.

 Formation of Base : The slopes of the bank shall be made up with

murum and trimmed to the required slope and properly compacted

under the separate item. Profiles shall be put up with pegs and strings

at required intervals for the pitching to ensure that is done true to line,

curves, levels, thickness and slopes.

 Pitching: A masonry wall or a line of pinheads when necessary, shall

be provided at the toe to support the pitching. The lowest course of

pitching shall be started from the toe wall or the line of pin headers.

The toe of the slope and the pitching laid course by course up the

slope. At least one header shall be provided per sqm area of pitching.

The stones for the pitching shall be used after merely knocking out

weak corners and edges with a mason’s hammer. The stones shall be

laid closely in position on the prepared bed and firmly set with the

even face on top. The pitching shall be laid to lines, levels, curves and

slopes as indicated in the plans or as ordered by the Engineer-Charge. Each stone shall cover the

full depth of pitching and shall be

perpendicular to the slopping bed. The stones shall be laid breaking

joints as far as possible. Additional murum bedding if required for

getting proper slope, shall be carried up simultaneously with each

course of pitching, watered, if necessary and rammed without any extra

cost.

Page 143: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

The interstices in the joints between adjacent stones shall be filled in

with spalls of the proper size and wedged in with hammers to ensure

tight packing. Such filling shall be carried out immediately after

placing larger stones and before the next upper layer is taken in hand.

 Item to Include: The item includes providing and laying dry rubble

pitching of the 225 mm thickness to lines, curves, slopes and levels

including preparing base, making up trimming and compacting the bed

in hand packing.

Labour, materials and use of tools and plant necessary for the

satisfactory completion of the work is included in the item.

Pitching without line level shall be rejected and corrected at the cost of

the contractor.

 Mode of Measurement and payment: The dimensions shall be

measured correct upto a cm. And the area worked out correct to the

second decimal of a sq. meter. The contract rate shall be for one sq.

metre of finished pitching. 17     Providing cement pointing for stone work using cement mortar 1:3 proportion. a) FlushPointing Specification:

 General : The item pertains to providing cement pointing for stone

work using cement mortar 1:3.

 Material :

Cement : As per item GenC/0.2.1.

Sand : As per item Gen/C0.2.2.

Water : As per item Gen/C/0.2.4

 Cement Mortar : Cement mortar of the specified proportion of 1:3

shall be prepared as per item Gen/E/0.2.

 Preparation of Surface : The joints shall be raked out properly. Dust

and loose mortar shall be brushed out. Efflorescence if any, shall be

removed by brushing and scraping. The surface shall then be

thoroughly washed with water, cleaned and kept wet before pointing is

commenced.

The joints shall be raked to such a depth that the minimum depth of the

new mortar measured from either the sunken surface of the finished

pointing or from the edge of the stone shall not be less than 12 mm.

 Scaffolding : For all exposed stonework or tile work, independent

double scaffolding having two sets if vertical supports shall be

provided. The supports shall be sound and strong tied together with

horizontal pieces over which planks shall be fixed.

Page 144: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

For all other stonework in building, single scaffolding shall be

permitted. In such cases, the inner end of the horizontal scaffolding

pole shall rest in a hole provided only in the header course for the

purpose. Only one header for each pole shall be left out. Such holes for

scaffolding shall, however, not be allowed in pillars/columns less than

one meter in width, or immediately near the skew backs of arches. The

holes left in masonry works for scaffolding purposes shall be filled and

made good before plastering.

Note : In case of special stonework, scaffolding shall be got approved

from Engineer-in-charge in advance.

 Application of Pointing and Finishing :

1. The mortar shall be pressed into the raked out joints, with a

pointing trowel, either flush, sunk or raised, according to the

type of pointing required. The mortar shall not spread over the

corner, edges of surface of the masonry. The pointing shall then

be finished with the proper tool, in the manner described below.

2. Flush Pointing : The mortar shall be pressed into the joints and

shall be finished off flush and level with edges of the stones,

tiles or stones so as to give a smooth appearance. The edges

shall be neatly trimmed with a trowel and straight edge.

3. Ruled Pointing : The joints shall be initially formed as for

flush pointing and then while the mortar is still green, a groove

of shape and size as shown in drawings or as instructed, shall

be formed by running a forming tool, straight along the centre

line of the joints. This operation shall be continued till a smooth

and hard surface is obtained. The vertical joints shall also be

finished in a similar way. The vertical lines shall make true

right angles at their junctions with the horizontal lines and shall

not project beyond the same.

4. Raised and Cut Pointing : Raised and cut pointing shall

project from the wall facing with its edges cut parallel so as to

have a uniformly raised band about 6 mm raised and width 10

mm more as directed.

5. The superfluous mortar shall then be cut off from the edges of

the lines and the surface of the masonry shall also be cleaned

off all mortar. The finish shall be such at the pointing is the

exact size and shape required and the edges are straight, neat

and clean.

6. The pointing lines shall be truly horizontal and vertical except

where the joints are slanting as in rubble random masonry.

Lines of joints from different directions should meet neatly at

Page 145: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

the junctions instead of crossing beyond.

 Curing : The pointing shall be kept wet for 7 days. During this period

it shall be suitably protected from all damages, and if pointing damages

the same shall be rectified by the contractor at his cost, as per above

mentioned procedure.

 Item to Include : The item includes providing all materials for

pointing in C.M. 1:3, including transportation, royalty for material, all

labour, tools and plants, machinery and equipments, staging,

scaffolding, bailing out water, curing, testing and construction as per

above specifications etc. complete.

Mode of Measurement and Payment : The pointing area shall be

measured in sqm as detailed below and shall be paid at the contract

rate per sqm.

1. Length and breadth shall be measured correct to a cm and its

area shall be calculated in m2 up to two places of decimal.

2. For jambs, soffits, sills etc. for opening not exceeding 0.5 m2

each in area, ends of joists, beams, posts, girders, steps etc. not

exceeding 0.5 m2 each in area and opening not exceeding 3 m2

each deduction and additions shall be made in the following

way, in case of pointing on external face only.

No deduction shall be made for ends of joist, beams, posts etc.

and opening not exceeding 0.5 m2 each, and no addition shall

be made for reveals, jambs, soffits, silts etc. of these openings.

Deduction for openings exceeding 0.5 m

2 but not exceeding 3

m2 each shall be made as follows and no additions shall be

made for reveals. Jambs, soffits, sills etc. for these openings.

When both the faces of wall are pointed with the different

pointing or if one face is plastered and other is pointed or

plastered, deduction shall be made from the plaster or pointing

on the side of frame of doors, windows, etc. on which the width

of reveal is less than that on the other side, but no deduction

shall be made from the other side.

Where width of reveals on both faces of wall are equal,

deduction of 50% of area of opening on each face shall be

made from area of pointing or plaster as the case may be (As

per IS: 1200).

When two faces of wall are pointed with different pointing or if

one face is plastered and other is pointed or plastered,

deduction shall be made from the plaster or pointing on the side

of frames for doors, windows etc. on which the width of reveal

Page 146: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

is less than that on other side, but no deduction shall be made

from other side.

For opening having door frame equal to or projecting beyond

thickness or wall, full deduction for opening shall be made

from each pointed face of wall.

3. In case of opening of area above 3 m2 each, deduction shall be

made for the openings, but jambs, reveals, soffits and sills shall

be measured. 18     Excavation in trenches, pits, pipe lines, foundations, column footings, walls etc. in earth’ssoils of all types, gravel, sand, soft & hard murum, and boulders up to 0.03 cum. size includingremoving the excavated material upto a distance of 50 M beyond the edge of excavation includingthe initial lift of 1.5 M, stacking or spreading as directed, bailing of sub-soil water if any preparingbase for foundation etc., and back filing the excavated pit or trench using the excavated material inlayers including watering and ramming as required or as directed by Engineer-In-charge, includingall labour and materials complete. Specification:  General : The item refers to the excavation, in earth, soils of all types,gravel, sand, soft and hardmurum and boulders up to 0.03 cum size.The excavation shall be for trenches, pits, pipe lines,foundations,column footings, walls etc. and may be in wet or dry, in earth, and similar other soft orloose material.   Site Preparation : The site as directed by the Engineer-in-charge, on which the construction, asper the drawings, is to be started shall be first cleaned and cleared of all obstructions. The loosestones, bushes, rubbish, brushwood, trees along with roots, etc. shall be removed. The materialshall be stacked or disposed off as directed. All the material shall be the property of MIDC. Afterclearing the site, the alignment or center lines or points shall be given by the Engineer-in-charge.The contractor shall establish the reference marks, benchmark pillars in masonry with M.S. Platetop of which shall be bench mark connected to GTS. The B.M. Pillars shall be maintainedundisturbed by the contractor etc. and the widths for excavations shall be clearly marked by thecontractor as directed, true to line, curve, level and slope. The contractor shall provide all labourand marking material such as wooden/steel pegs, white lime powder, oil paint, or any othersuitable marking material at his own cost and he shall be fully responsible for the correctness ofthe line, curve and levels and slopes.  Excavation : Before starting actual excavation work, contractor shall notify the Engineer-in-chargefor taking the necessary measurements of cross sectional levels along the alignment formeasurement purposes. The levels recorded in the field book shall be signed by the Engineer-in-charge and authorised representative of the contractor in token of acceptance. The contractor shallremove all the material from the marked area of excavation by using labour, tools and equipmentsmost suitable for excavation of soft material as enumerated in the item in wet or dry conditions.The excavation shall be true to line, curve, shape, level grade as per the drawings or as directed.The widths of excavations shall be as minimum to the widths required at the bottom and thevertical faces shall be as far as possible in plumb. Unless provided in the contract, no extrapayment shall be made for the excavation on side slopes for stability of slopes. Contractor shall befully responsible for the correctness of the excavation. Whenever the strata of different grade of

Page 147: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

soil not covered in this item is met, the excavation shall be stopped and the Engineer-in-chargeshall be notified to take the cross-sectional levels for taking the measurements and the same shallbe recorded and practise as mentioned above shall be adhered to. The extra excavation in depthor on sides shall not be paid and the contractor will have to fill the extra excavated depths in layersto bring the correct level by watering and ramming at his own cost.  Foundation Preparation : The foundation for column footing and for structural components suchas wall shall not be provided on soft strata covered under this item of excavation. The foundationsfor rafts, embedment of pipelines for water supply or drainage or gas may be laid on the foundationprepared on soft strata. The foundation level even if is confined within the soft layer, the final layerof excavation watered and brought to the required level and slope by ramming. The contractorshall not excavate below the line shown in the drawing or as directed. No foundation of any sortshall be laid unless the Engineerin- charge approves the strata on which foundations are to be laidand passes the depth of excavation to lay foundation and record the dimensions and elevationsand types soils of the foundation pit, trench excavated, and shall be recorded in the field bookadopting system already explained above.  Shoring and Strutting : The cost of shoring and strutting shall not be paid separately unlessprovided in the contract. The type and designing of shoring shall be decided by the contractor, andshall get approved from the Engineer in Charge. Pay Slopes : In lieu of shoring and strutting payslopes for excavation of trenches/pits shall be stipulated and paid accordingly.  Disposal of Excavated Material : All the material obtained from clearing the site or fromexcavation shall be the absolute property of MIDC. All materials obtained from clearing the site andexcavation shall be disposed off or spread or stacked within a lead of 50 meters beyond theexcavated area as directed by the Engineer in Charge. Materials suitable for back-filling or otheruse shall be stacked at a convenient place within a lead of 50 meters as directed for refilling orreuse. No excavated material shall be kept within 1.5 m distance from the outer top edge ofexcavation to avoid the falling of the stuff in the pit or trench. Surplus materials shall be used forlevelling the ground around as directed within a lead of 50 meters. If the surplus materials arerequired to be conveyed and used or stacked beyond 50 meters contractor shall be paid for extralead or the extra conveyance as per the terms of contract.  Dewatering : It is the responsibility of the contractor to remove the water accumulated in the pit ortrench, from sub-soil water or from rains or from any other natural source, by manually or bypumping out as required. Unless provided for in the contract separately, no payment shall be madefor bailing out the water. The contractor may be required to provide temporary bunds, or providebyepass arrangements to avoid entering of water in the excavation at his own cost. The drainedwater shall be properly disposed off, so as not to cause any damages to the excavated area nor tothe surrounding structures. The contractor shall keep the excavated area dry for measurementsand for laying of foundation mortar or concrete.  Side Slips and Blows : Even after sufficient care of sides, slips or blows occur, they shall beremoved at contractor’s cost.  Backfilling : After excavation is completed, measurementsrecorded by the Engineer-in-charge and the foundation raft masonry above is constructed or thepipeline is laid, all the shoring shall have to be removed. The backfilling of the pit or trench to theoriginal level or as shown in the drawing or as directed shall be made from the selected excavatedmaterial stacked separately for that purpose. The material shall be laid in layers of 15 to 20 cm inthickness, watered and then rammed properly. The backfilling shall only be done after receivingorders from the Engineer-in-charge and without damaging the foundation raft or the pipeline etc.  Protective Measures : All the excavated pits, trenches etc. shall be properly protected from any

Page 148: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

accidents by providing strong fencing around. At night red lantern and watchman shall be kept inproper position to indicate the danger zone. It is the responsibility of the contractor to take theadequate protective measures and safety of the excavation, people and workmen and surroundingproperties and will have to bear the damages if caused. All the cost of protective measures shallbe included in the item rate.  Item to Include : The rate for this item, as per the agreement includes all labour and tools forclearing the site, marking out the excavation line outs, shoring and strutting, excavation of pits ortrenches, bailing or pumping out water if not provided separately, removal of excavated materialand disposal of material as directed, refilling of pits or trenches, adequate protective measures etc.Contractor shall also make the necessary arrangements for taking measurements. The rate alsoincludes the cost of repairs due to excess excavations or slips. The item also includes payment ofthe damages if any, by the contractor. The disposal of the material is included within 50 m radiusfrom the edge of excavation. The lift for excavation of 1.5 m is covered by this item. The additionallifts shall be paid under Item No.Gen/A/2. The lead beyond 50 m shall be paid extra under ItemNo.Gen/A/9.  Mode of Measurement and Payment : The measurements of the original ground profiles atselected locations shall be taken after clearing the site. The measurements of the final excavatedprofile shall be taken if the excavation is less or more as directed by the Engineerin- charge orshall be measured as per drawings. Excess excavation shall be recorded but shall be paid to thelimited quantity as explained above. The quantity shall be measured in cubic meters and paid atthe rate as per the contract agreement. 19     Excavation for trenches, pits, pipelines, foundations, column footings, walls etc. in soft rockand boulders between 0.03 TO 0.30 Cu.M. in size for a depth upto 1.5 M including removing theexcavated materials upto a distance of 50 M beyond the edges of trenches / pits etc. breaking theboulders into 225 mm size rubble including stacking the same (rubble as well as soft rock) and / orspreading as directed, bailing out water if any, preparing the bed for foundations & necessary backfilling the excavated pit / trench as directed by Engineer-in-charge all labour and materialscomplete. Specification:  General : The item refers to the excavation, in soft rock and boulders between 0.03 and 0.30 cumsize. The excavation shall be for trenches, for pipelines, pits, foundations, column footings, wallsetc. and may be in wet or dry, in soft rock, and similar other material.  Site Preparation : As per Item No.Gen/A/1.2. Site preparation may not be required if the classifiedlayer lies below the item of excavation in soils classified as per Item No.Gen/A/1.  Excavation : As per Item No.Gen/A/1.3. The contractor shall excavate and remove all the materialfrom the marked area of excavation by using labour, tools and equipments most suitable forexcavation of soft rock in wet or dry condition.  Foundation Preparation : In this classified strata, the foundation for column footing and forstructural components such as wall may be provided. Also the foundations for rafts, embedment ofpipelines for water supply or drainage or gas may be laid in this type of classified soft rock. Thefoundation shall be cleared of all loose material and shall be dressed by chiselling to the correctline and level. The contractor shall not excavate below the line shown in the drawing or asdirected. No foundation of any sort shall be laid unless the Engineerin- charge approves/passesthe depth of excavation to lay foundation and record the dimensions and elevations and types soilsof the foundation pit, trench excavated. 

Page 149: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Shoring and Strutting : The cost of shoring and strutting shall not be paid separately unlessprovided in the contract. The type and designing of shoring shall be decided by the contractor, andshall get approved from the Engineer in Charge. Pay Slopes : In lieu of shoring and strutting payslopes for excavation may be stipulated according to which excavation has to be carried out andshall be paid.  Disposal of Excavated Material : The boulders obtained during the excavation shall be brokeninto the rubble of size of about 225 mm. This rubble shall be stacked in measurable hips and atlocations, as directed, within the initial lead of 50 m from the edges of excavation as directed. Therubble shall be disposed off by the contractor at his cost if it is not usable as certified by theEngineer-in-charge.  Dewatering : It is the responsibility of the contractor to remove the water accumulated in the pit ortrench, from sub-soil water or from rains or from any other natural source, by manually or bypumping out as required. Unless provided for in the contract separately, no payment shall be madefor bailing out the water. The contractor may be required to provide temporary bunds, or providebypass arrangements to avoid entering of water in the excavation at his own cost. The drainedwater shall be properly disposed off, so as not to cause any damages to the excavated area nor tothe surrounding structures. The contractor shall keep the excavated area dry for measurementsand for laying of foundation mortar or concrete.  Side Slips and Blows : Even after sufficient care of sides, slips or blows occur, they shall beremoved at contractor’s cost.  Backfilling : After excavation is completed, measurements recorded Maharashtra IndustrialDevelopment Corporation by the Engineer-in-charge and the foundation raft and masonry/structurethere on or the pipeline is laid, all the shoring shall have to be removed. The backfilling of the pit ortrench to the original level or as shown in the drawing or as directed shall be made from theselected excavated material stacked separately for that purpose. The material shall be laid inlayers of 15 to 20 cm in thickness, watered and then rammed properly. The backfilling shall only bedone after receiving orders from the Engineer-in-charge and without damaging the foundation raftor the pipeline etc.  Protective Measures : All the excavated pits, trenches etc. shall be properly protected from anyaccidents by providing strong fencing around. At night red lantern and watchman shall be kept inproper position to indicate the danger zone. It is the responsibility of the contractor to take theadequate protective measures and safety of the excavation, people and workmen and surroundingproperties and will have to bear the damages if caused. All the cost of protective measures shallbe included in the item rate.  Item to Include : As per Item No.Gen/A/1.11, but for soft rock classified material. The lift forexcavation upto 1.5 m is covered by this item. The additional lifts shall be paid under ItemNo.Gen/A/4. The lead beyond 50 m shall be paid extra under Item No.Gen/A/9. The item alsoinclude breaking boulders into rubble of 225 mm and stacking within lead of 50 m.  Mode of Measurement and Payment : The measurements of the original ground profiles atselected locations shall be taken after clearing the site. The measurements of the final excavatedprofile shall be taken if the excavation is less or more as directed by the Engineerin- charge orshall be measured as per drawings. Excess excavation shall be recorded but shall be paid to thelimited quantity as explained above. The quantity shall be measured in cubic meters and paid atthe rate as per the contract agreement. Deductions for voids shall be made @ 40% if quantity paidon stack measurements. The size of stacks shall be 3.0 m X 2.0 m X 1.0 m size preferably. 20     Providing at the site of work and lowering, laying and jointing RCC NP2 class pipes

Page 150: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

conforming to IS:458-1988 in prepared trenches in grade and level, including hoisting, makingrubber ring / collar joints in cement mortar 1:1, including cost of collar / rubber ring, jointing materiallike cement, sand etc. and hydraulic testing of the pipes at factory as well as on site as per thestipulation in relevant IS code etc. complete. b) 600 mm diaRCC NP2 class Specification:

j)  600 mm dia.

k)  900 mm dia.

Specification :-

General : The item covers to providing and laying & jointing of RCC pipes of NP2 class, including

the sealing rings, mortar filling and hydraulic testing. The excavation of trenches for laying of pipe

will be paid separate under relevant item included in this tender.

Material : RCC NP2 class pipes shall conform to IS : 458-1988. For ready reference and

comparison the particulars of the RCC Non-Pressure and Pressure pipes of different classes are

given here, though the item refers only for NP2 class pipe.

Cement Concrete Pipes (with and without Reinforcement)

The pipes shall be with or without reinforcement as required and shall be of the specified class.

These shall conform to IS : 458-1988. The reinforced cement concrete pipes shall be

manufactured by centrifugal (or spun) process and only reinforced is proposed for use NP2 by

providing temperature steel reinforcement. All pipes shall be true to shape, straight, perfectly

sound and free from cracks and flaws. The external and internal surface of the pipes shall be

smooth and hard. The

pipes shall be free from defects resulting from imperfect grading of the aggregate mixing or

molding. Concrete used for the manufacture of un-reinforced and reinforced concrete pipes and

collars shall not be leaner than M-15 grade C.C. The maximum size of aggregate should not

exceed one third of the thickness of the pipe or 20 mm whichever is less. The reinforcement in the

reinforced concrete pipes shall extend throughout the length of the pipe. The circumferential and

longitudinal reinforcements shall be adequate to withstand the specified hydrostatic pressure and

further bending stresses due to the weight of water when running full across a span equal to the

length of pipe plus three times its own weight.

Note 1 :- If steel wires are used as longitudinal reinforcement, the weight specified in col 7 shall be

modified by the factor 1265/1400.

Note 2 :- If mild steel is used for spiral reinforcement, the weight specified under col 8 shall be

increased to 1400/1265.

Laying & Jointing Cement Concrete Pipes And Specials :

Laying : Loading, transporting and unloading of concrete pipes shall be done with care. Handling

shall be such as to avoid impact. Gradual unloading by inclined plane upto 900 mm dia pipes and

by chain pulley block for pipes 1000 mm and above is recommended. All pipe sections and

connections shall be inspected carefully before being laid. Broken or defective pipes or

connections shall not be used and paid. Pipes shall be lowered into the trenches carefully.

Mechanical appliances shall be used. Pipes shall be laid true to line and grade as specified. Laying

Page 151: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

of pipe shall proceed upgrade of a slope. If the pipe have spigot and socket joints, the socket ends

shall face ascending gradient. In the case of pipes with joints to be made with loose collars, the

collars shall be slipped on before the next pipe is laid. Adequate and proper joints shall be

provided as directed. In case where foundation condition are unusual such as in the proximity of

trees, under existing or proposed tracks manholes etc. the pipe shall be encased all around in 15

cm thick cement concrete M15 grade or compacted sand or gravel. In cases where the natural

foundation is inadequate the pipes shall be laid either on concrete cradle supported on proper

foundations or on any other suitably designed structure. If concrete cradle bedding is used, the

depth of concrete below the bottom of the pipe shall be at least 1/4th of the internal diameter of the

pipe subject to the min. of 10 cm and a maximum of 30 cm. The concrete shall extend beyond both

the sides of the pipe at least to a distance of 1/4th of the outside diameter subject to minimum 10

cm and maximum 30 cm. The pipe shall be laid on this concrete bedding before setting of the

concrete . Pipes laid in trenches in earth shall be bedded evenly and firmly and as far up the

haunches of the pipe as to safely transmit the load expected from the backfill through the pipe to

the bed. This shall be done either

by excavating the bottom of the trench to fit the curve of the pipe or by compacting the earth under

around the curve of the pipe to form an even bed. Necessary provision shall be made for joints

wherever required. When the pipe is laid in a trench in rock, hard clay, shale or other hard material

the 15 cms depth below the pipe shall be excavated and refilled with an equalizing bed cushion of

15 cms thickness of granular approved granular soft murum, sand or compacted earth. In no case

the pipe shall be laid directly on such hard material. It should be ensured that the rock protrudes

shall be knocked off. When the pipes are laid completely above the ground the foundations shall

be made even and sufficiently compacted to support the pipeline without any material settlement.

Alternatively the pipeline shall be supported on rigid foundations at intervals as approved by the

Engineer-in-Charge. Suitable arrangements shall be made to retain the pipeline in the proper

alignment, such as by shaping the top of the supports to fit the lower part of the pipe. The distance

between the supports shall in no case exceed the length of the pipe. The pipe shall be supported

as far as possible close to the joints. In no case the joints shall come in the centre of the span.

Suitably designed anchor blocks at change of direction and grades for  pressure lines shall be

provided where required. The cost of bedding below pipes, concrete and/or murum supports

constructed, anchor blocks etc. is not included in the scope of item and shall be paid separately

under relevant items included in the tender Jointing : Joints shall generally be of rigid type. Where

specified flexible type joints may also be provided, an approval of Engineer-in- Charge. Rigid

Spigot & Socket Joint : The spigot of each pipe shall be slipped home well into the socket of the

pipe previously laid and adjusted in the correct position. The opening of the joint shall be filled with

stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) which shall be

rammed with caulking tool and finished at 45° tapper. After a day’s work any extraneous material

shall be removed from the inside of the pipe and the newly made joint shall be cured at least for 7

days. Rigid Collar Joint : The two adjoining pipes shall be butted against each other and adjusted

in correct position. The collar shall then be slipped over the joint, covering equally both the pipes.

The annular space shall be filled with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand)

Page 152: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

which shall be rammed with caulking tool and finished at 45° tapper. After a day’s work any

extraneous materials shall be

removed from the inside of the pipe and the newly made joint shall be cured at least for 7 days.

Flexible Spigot & Socket Joint : The joint is composed of specially  shaped spigot and socket ends

on the concrete pipes. A rubber ring shall be placed on the spigot, which shall be forced into the

socket of the pipe previously laid. This compresses the rubber ring as it rolls into the annular space

formed between the two surfaces of the spigot and the socket. Flexible Collar Joint : This shall be

made up of a loose collar, which covers two specially shaped pipe ends. Each end shall be fitted

with a rubber ring which when compressed between the spigot and the collar, seal the joint.

Internal Flush Joint : This joint shall generally be used for culvert pipe of 60 cm diameter and

above. The ends of the pipe are specially shaped to form a self-centering joint with an internal

jointing space 1.3 cm wide. The finished joint shall be flush with both inside and outside with the

pipe wall. The jointing space shall be filled with cement mortar 1:1 (1 cement : 1 fine sand) mixed

sufficiently dry to remain in position when forced with a trowel or rammer and finished at 45°

tapper. After day’s work any extraneous materials shall be removed from the inside of the pipe and

the newly made joint shall be cured at least for 7 days. External Flush Joint : This joint is suitable

for pipes which are too small for jointing from inside. This joint is composed of specially shaped

pipe ends. Each end shall be butted against each other and adjusted in correct position. The

jointing space shall then be filled with cement mortar 1:1 (1 cement : 1 fine sand) sufficiently dry

and finished off flush at 45° tapper. Great care shall be taken to ensure that the projecting ends

are not damaged as no repairs can be readily affected from inside the pipe. In all pressure

pipelines the recess at the end of the pipe line shall be filled with jute braiding dipped in hot

bitumen or other suitable approved compound. Pipes shall be so jointed that the bitumen ring of

one pipe shall set into the recess of the next pipe. The ring shall be thoroughly compressed by

jacking or by any other suitable method.

The number of pipes that shall be jacked together at a time shall depend on the diameter of the

pipes and the bearing capacity of the soil, for small pipes upto 25 cm diameter, six pipes can be

jacked together at a time. The quantity of jute and bitumen in the ring shall be just sufficient to

fill the recess in the pipe when presses hard by jacking or by any other suitable method. Before

and during jacking care shall be taken to see that there is no offset at the joint.

Testing : Smoke test shall be carried out from chamber to chamber at contractor’s cost.

Refilling of Trenches : In case where pipes are not bedded on concrete special care shall be

taken in refilling trenches, to prevent the displacement and subsequent settlement at the surface

resulting in uneven surface and dangers to foundations etc. The back filling materials shall be

packed by hand under and around the pipe and rammed with a shovel and light tamper. This

method of filling will be continued upto the top of pipe. The refilling shall rise evenly on both sides

of the pipe continued upto 60 cm above the top of pipe so as not to disturb the pipe. No tamping

shall be done within 15 cm of the top of pipe. The tamping shall become progressively heavier as

the depth of the backfill increases (item of excavation shall be paid under relevant item of

excavation of tender).

Item to Include : Item includes all labour, tools and equipment, all material, RCC pipes of NP2

Page 153: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

class of specified diameter and jointing material, etc. for laying, jointing and testing of pipes etc.

complete.  The item does not include the excavation of trenches, but includes refilling of trenches

after laying and jointing, after satisfactory testing.

Mode of Measurements and Payment : The length of pipes shall be measured in running metres

nearest to a cm as laid or fixed, from inside of one manhole to the inside of the other manhole. The

length shall be taken along the centre line of the pipes Excavation and cement concreting

wherever required shall be measured and paid separately under relevant items. The contract rate

shall be per running meter of the RCC NP2 pipe of specified diameter laid.The payment shall be

made in three stages as under:

1.         On providing and supplying pipes as per specifications - 70%

2.         On laying and jointing of pipes - 20%

3.         After satisfactory hydraulic testing of pipe line - 10% 21     C ) 900 mm dia RCC NP2 class Specification:

k)  900 mm dia.

Specification :-

General : The item covers to providing and laying & jointing of RCC pipes of NP2 class, including

the sealing rings, mortar filling and hydraulic testing. The excavation of trenches for laying of pipe

will be paid separate under relevant item included in this tender.

Material : RCC NP2 class pipes shall conform to IS : 458-1988. For ready reference and

comparison the particulars of the RCC Non-Pressure and Pressure pipes of different classes are

given here, though the item refers only for NP2 class pipe.

Cement Concrete Pipes (with and without Reinforcement)

The pipes shall be with or without reinforcement as required and shall be of the specified class.

These shall conform to IS : 458-1988. The reinforced cement concrete pipes shall be

manufactured by centrifugal (or spun) process and only reinforced is proposed for use NP2 by

providing temperature steel reinforcement. All pipes shall be true to shape, straight, perfectly

sound and free from cracks and flaws. The external and internal surface of the pipes shall be

smooth and hard. The

pipes shall be free from defects resulting from imperfect grading of the aggregate mixing or

molding. Concrete used for the manufacture of un-reinforced and reinforced concrete pipes and

collars shall not be leaner than M-15 grade C.C. The maximum size of aggregate should not

exceed one third of the thickness of the pipe or 20 mm whichever is less. The reinforcement in the

reinforced concrete pipes shall extend throughout the length of the pipe. The circumferential and

longitudinal reinforcements shall be adequate to withstand the specified hydrostatic pressure and

further bending stresses due to the weight of water when running full across a span equal to the

length of pipe plus three times its own weight.

Note 1 :- If steel wires are used as longitudinal reinforcement, the weight specified in col 7 shall be

Page 154: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

modified by the factor 1265/1400.

Note 2 :- If mild steel is used for spiral reinforcement, the weight specified under col 8 shall be

increased to 1400/1265.

Laying & Jointing Cement Concrete Pipes And Specials :

Laying : Loading, transporting and unloading of concrete pipes shall be done with care. Handling

shall be such as to avoid impact. Gradual unloading by inclined plane upto 900 mm dia pipes and

by chain pulley block for pipes 1000 mm and above is recommended. All pipe sections and

connections shall be inspected carefully before being laid. Broken or defective pipes or

connections shall not be used and paid. Pipes shall be lowered into the trenches carefully.

Mechanical appliances shall be used. Pipes shall be laid true to line and grade as specified. Laying

of pipe shall proceed upgrade of a slope. If the pipe have spigot and socket joints, the socket ends

shall face ascending gradient. In the case of pipes with joints to be made with loose collars, the

collars shall be slipped on before the next pipe is laid. Adequate and proper joints shall be

provided as directed. In case where foundation condition are unusual such as in the proximity of

trees, under existing or proposed tracks manholes etc. the pipe shall be encased all around in 15

cm thick cement concrete M15 grade or compacted sand or gravel. In cases where the natural

foundation is inadequate the pipes shall be laid either on concrete cradle supported on proper

foundations or on any other suitably designed structure. If concrete cradle bedding is used, the

depth of concrete below the bottom of the pipe shall be at least 1/4th of the internal diameter of the

pipe subject to the min. of 10 cm and a maximum of 30 cm. The concrete shall extend beyond both

the sides of the pipe at least to a distance of 1/4th of the outside diameter subject to minimum 10

cm and maximum 30 cm. The pipe shall be laid on this concrete bedding before setting of the

concrete . Pipes laid in trenches in earth shall be bedded evenly and firmly and as far up the

haunches of the pipe as to safely transmit the load expected from the backfill through the pipe to

the bed. This shall be done either

by excavating the bottom of the trench to fit the curve of the pipe or by compacting the earth under

around the curve of the pipe to form an even bed. Necessary provision shall be made for joints

wherever required. When the pipe is laid in a trench in rock, hard clay, shale or other hard material

the 15 cms depth below the pipe shall be excavated and refilled with an equalizing bed cushion of

15 cms thickness of granular approved granular soft murum, sand or compacted earth. In no case

the pipe shall be laid directly on such hard material. It should be ensured that the rock protrudes

shall be knocked off. When the pipes are laid completely above the ground the foundations shall

be made even and sufficiently compacted to support the pipeline without any material settlement.

Alternatively the pipeline shall be supported on rigid foundations at intervals as approved by the

Engineer-in-Charge. Suitable arrangements shall be made to retain the pipeline in the proper

alignment, such as by shaping the top of the supports to fit the lower part of the pipe. The distance

between the supports shall in no case exceed the length of the pipe. The pipe shall be supported

as far as possible close to the joints. In no case the joints shall come in the centre of the span.

Suitably designed anchor blocks at change of direction and grades for  pressure lines shall be

provided where required. The cost of bedding below pipes, concrete and/or murum supports

constructed, anchor blocks etc. is not included in the scope of item and shall be paid separately

Page 155: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

under relevant items included in the tender Jointing : Joints shall generally be of rigid type. Where

specified flexible type joints may also be provided, an approval of Engineer-in- Charge. Rigid

Spigot & Socket Joint : The spigot of each pipe shall be slipped home well into the socket of the

pipe previously laid and adjusted in the correct position. The opening of the joint shall be filled with

stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) which shall be

rammed with caulking tool and finished at 45° tapper. After a day’s work any extraneous material

shall be removed from the inside of the pipe and the newly made joint shall be cured at least for 7

days. Rigid Collar Joint : The two adjoining pipes shall be butted against each other and adjusted

in correct position. The collar shall then be slipped over the joint, covering equally both the pipes.

The annular space shall be filled with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand)

which shall be rammed with caulking tool and finished at 45° tapper. After a day’s work any

extraneous materials shall be

removed from the inside of the pipe and the newly made joint shall be cured at least for 7 days.

Flexible Spigot & Socket Joint : The joint is composed of specially  shaped spigot and socket ends

on the concrete pipes. A rubber ring shall be placed on the spigot, which shall be forced into the

socket of the pipe previously laid. This compresses the rubber ring as it rolls into the annular space

formed between the two surfaces of the spigot and the socket. Flexible Collar Joint : This shall be

made up of a loose collar, which covers two specially shaped pipe ends. Each end shall be fitted

with a rubber ring which when compressed between the spigot and the collar, seal the joint.

Internal Flush Joint : This joint shall generally be used for culvert pipe of 60 cm diameter and

above. The ends of the pipe are specially shaped to form a self-centering joint with an internal

jointing space 1.3 cm wide. The finished joint shall be flush with both inside and outside with the

pipe wall. The jointing space shall be filled with cement mortar 1:1 (1 cement : 1 fine sand) mixed

sufficiently dry to remain in position when forced with a trowel or rammer and finished at 45°

tapper. After day’s work any extraneous materials shall be removed from the inside of the pipe and

the newly made joint shall be cured at least for 7 days. External Flush Joint : This joint is suitable

for pipes which are too small for jointing from inside. This joint is composed of specially shaped

pipe ends. Each end shall be butted against each other and adjusted in correct position. The

jointing space shall then be filled with cement mortar 1:1 (1 cement : 1 fine sand) sufficiently dry

and finished off flush at 45° tapper. Great care shall be taken to ensure that the projecting ends

are not damaged as no repairs can be readily affected from inside the pipe. In all pressure

pipelines the recess at the end of the pipe line shall be filled with jute braiding dipped in hot

bitumen or other suitable approved compound. Pipes shall be so jointed that the bitumen ring of

one pipe shall set into the recess of the next pipe. The ring shall be thoroughly compressed by

jacking or by any other suitable method.

The number of pipes that shall be jacked together at a time shall depend on the diameter of the

pipes and the bearing capacity of the soil, for small pipes upto 25 cm diameter, six pipes can be

jacked together at a time. The quantity of jute and bitumen in the ring shall be just sufficient to

fill the recess in the pipe when presses hard by jacking or by any other suitable method. Before

and during jacking care shall be taken to see that there is no offset at the joint.

Testing : Smoke test shall be carried out from chamber to chamber at contractor’s cost.

Page 156: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Refilling of Trenches : In case where pipes are not bedded on concrete special care shall be

taken in refilling trenches, to prevent the displacement and subsequent settlement at the surface

resulting in uneven surface and dangers to foundations etc. The back filling materials shall be

packed by hand under and around the pipe and rammed with a shovel and light tamper. This

method of filling will be continued upto the top of pipe. The refilling shall rise evenly on both sides

of the pipe continued upto 60 cm above the top of pipe so as not to disturb the pipe. No tamping

shall be done within 15 cm of the top of pipe. The tamping shall become progressively heavier as

the depth of the backfill increases (item of excavation shall be paid under relevant item of

excavation of tender).

Item to Include : Item includes all labour, tools and equipment, all material, RCC pipes of NP2

class of specified diameter and jointing material, etc. for laying, jointing and testing of pipes etc.

complete.  The item does not include the excavation of trenches, but includes refilling of trenches

after laying and jointing, after satisfactory testing.

Mode of Measurements and Payment : The length of pipes shall be measured in running metres

nearest to a cm as laid or fixed, from inside of one manhole to the inside of the other manhole. The

length shall be taken along the centre line of the pipes Excavation and cement concreting

wherever required shall be measured and paid separately under relevant items. The contract rate

shall be per running meter of the RCC NP2 pipe of specified diameter laid.The payment shall be

made in three stages as under:

1.         On providing and supplying pipes as per specifications - 70%

2.         On laying and jointing of pipes - 20%

3.         After satisfactory hydraulic testing of pipe line - 10% 22     Providing and laying in position plain cement concrete using granite or black trap gradedmetal including mixing in a mechanically operated mixer, dewatering, compacting, curing asrequired complete for all lifts up to a + 5 m. above or below the ground level where concrete isproposed, including centering/shuttering using ordinary Portland cement. c) In 1:2:4 proportion. Specification:

General : The item pertains to providing and laying in position Plain Cement Concrete (PCC) of

specified proportion. The work includes providing all material, mixing, compacting, curing,

shuttering, dewatering etc. complete up to lift of ± 5 m.

Material:

Cement : Ordinary Portland Cement (OPC) as specified at item Gen/C/0.2.1.

Fine Aggregate (Sand) : specifications shall conform to item Gen/C/0.2.2.

Coarse Aggregate : specifications shall conform to item Gen/C/0.2.3. Grading and maximum size

of coarse aggregate shall be as specified in the drawing. Normally the maximum size should not

be more than 40 mm or 25 % of the minimum dimension of the member, whichever is less.

Water : specifications shall conform to item Gen/C/0.2.4.

Mix Proportion and Mixing : The mix proportion as specified on the drawing, separately for each

component shall be provided. For detailed specifications refer to item No.Gen/C/0.5. For mixing

without mechanical mixer, prior permission from the Engineer-in-charge shall be obtained.

Page 157: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Specifications for mixing shall conform to item Gen/C/0.7.

Formwork and Scaffolding : Formwork shall be provided for giving the desired shape and sizes

for the PCC as per the drawings. The specifications shall conform to item Gen/C/0.19.7. The

striping time also shall be as specified in the item. The scaffolding shall be normally provided of

steel tubes. The specifications for scaffolding also shall conform to item Gen/C/0.19.8.

Transportation, Placing and Compaction : Specifications shall conform to item Gen/C/0.8.

Field Tests : The appropriate field tests as directed by the Engineer-in charge shall be carried out

as explained in item Gen/C/0.15.

Inspection & Testing of Structure : As per the contract conditions inspection & testing of a

structure shall be carried out in accordance with item Gen/C/0.16

Finishing of Concrete : The finishing of concrete surface shall be as per item Gen/C/0.17.

Special Features : Special requirements such as Architectural shapes/ finishes, Expansion joints,

Construction joints, Water stops, grouting, etc. shall be provided as shown on drawing/s and as

directed by Engineer in Charge. For specifications for these the appropriate clauses of item

Gen/C/0 shall be referred.

Curing : As per item Gen/C/0.14.

Item to Include : This item for providing Plain Cement Concrete (PCC) with specified mix

proportion at specified locations with initial lift of + 5 m above or below ground level includes all

ingredients of concrete i.e. water, cement, fine and coarse aggregates, all transportation,

dewatering, tools and plants, all taxes, royalties, labour, formwork, testing, curing etc. complete.

Mode of Measurement and Payment : The measurements of the concrete laid shall be taken on

volumetric basis in cum. The openings shall be deducted. The unit rate of concrete will be per cum

of specified proportion 23     Providing and laying in position Cement Concrete for RCC work using granite / black trapmetal including mixing in mechanically operated mixers, compacting by mechanical or manualmeans as may be required and directed by Engineer-In-Charge, including steel or plywoodshuttering, centring, formwork dewatering, for all elements in foundation, plinths, of building works,where reinforced cement concrete is proposed to be used upto +/-5 m from the average groundlevel including all labour and material complete, finishing the surface with 1:3 cement mortar. etccomplete. c) In 1:1.5:3 proportion by volume. Specification:

c) In 1:1.5:3 proportion by volume

Specification :-

General : The item pertains to providing and laying in position Cement Concrete of specified

proportion or by in design mix grade for Reinforced concrete works in foundation or plinth. The

work includes providing all material, mixing, compacting, curing, shuttering, dewatering, etc.

complete upto lift of ± 5 m. Providing the reinforcement steel shall be carried out by item No.

Gen/C/0.2.5

Material : As per item Gen/C/0.2.

Mix Proportion and Mixing : As per item Gen/C/0.5. For providing Concrete of specified grade by

Page 158: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

designing the mix of concrete, please refer to specifications as per item Gen/C/0.4 and 0.5.

The design mix shall be got done from the approved laboratories and got approved by the

Engineer-in-charge.

Formwork and Scaffolding : As per item Gen/C/0.19.

Transportation, Placing and Compaction : Specifications shall conform to item Gen/C/0.8.

Field Tests : The appropriate field tests as directed by the Engineer-in charge shall be carried out

as explained in item Gen/C/0.15.

Inspection & Testing of Structure : As per the contract conditions inspection & testing of a

structure shall be carried out in accordance with item Gen/C/0.16

Finishing of Concrete : The finishing of concrete surface shall be as per item Gen/C/0.17.

Special Features : Special requirements such as Architectural shapes / finishes, Expansion joints,

Construction joints, Water stops, grouting, etc. shall be provided as shown on drawing/s. For

specifications for these the appropriate clauses of item Gen/C/0 shall be referred. 3.10 Curing :

As per item Gen/C/0.14.

Item to Include : This item for providing Cement Concrete with specified mix proportion or

specified grade, at specified locations with initial lift of ± 5 m above or below ground level includes

all ingredients of concrete i.e. water, cement, fine and coarse aggregates, all transportation,

dewatering, tools and plants, all taxes, loyalties, labour, formwork, testing, curing etc. complete.

The provision of reinforcement steel is not included in this item.

Mode of Measurement and Payment : The measurements of the concrete laid shall be taken on

volumetric basis in cum. The openings shall be deducted. The unit rate of concrete per cum of

specified proportion includes all the items.

Item No. 25 :-   Providing and fixing in position reinforcement of all dia for RCC piles, pile caps,

footings, foundations, slabs, columns, beams, canopies, staircase, newels, chajjas, lintels pardis,

copings, fins, arches etc. as per detailed designs, drawings and schedules including cutting,

bending,

hooking the bars, binding with wires or tack welding and supporting as required at all locations and

height all labour and materials and testing complete.

b) Tor Steel Bars

Specification :-

General : The item pertains to providing and fixing in position reinforcement of all dia for RCC

piles, pile caps, footings, foundations, slabs, columns, beams, canopies, staircase, newels,

chajjas, lintels pardis, copings, fins, arches etc..

Material : The reinforcement shall be of Mild Steel or Tor Steel bars as indicated on the drawings.

The material shall conform to item Gen/C/0.2.5.

Construction : Contractor shall provide the reinforcement bars of tor steel or mild steel of

specified dia. at locations in numbers or at spacing’s, as per detailed designs, drawings and

schedules including cutting, bending, hooking the bars, binding with wires or tack welding and

supporting as required at all locations and height. The work shall be carried out as specified in

Gen/C/0.2.5. The reinforcement shall be got checked by the Engineer-in-charge or his

representative before concreting. The contractor shall provide and fix in position any additional

Page 159: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

reinforcement, if directed, in addition to the reinforcement shown on drawing.

Item to Include : The item includes all the material of reinforcement bars, binding wires, welding

rods and labour and tools and equipment for cutting, bending welding, testing charges etc.

complete as per drawings and as directed by the Engineer-in-charge.

Mode of Measurement and Payment : The measurement of the reinforcement bars shall be

taken in metric tons 24     Providing and fixing in position reinforcement of all dia for RCC piles, pile caps, footings,foundations, slabs, columns, beams, canopies, staircase, newels, chajjas, lintels pardis, copings,fins, arches etc. as per detailed designs, drawings and schedules including cutting, bending,hooking the bars, binding with wires or tack welding and supporting as required at all locations andheight all labour and materials testing etc. complete. b ) Tor steel bars Specification:

b) Tor Steel Bars

Specification :-

General : The item pertains to providing and fixing in position reinforcement of all dia for RCC

piles, pile caps, footings, foundations, slabs, columns, beams, canopies, staircase, newels,

chajjas, lintels pardis, copings, fins, arches etc..

Material : The reinforcement shall be of Mild Steel or Tor Steel bars as indicated on the drawings.

The material shall conform to item Gen/C/0.2.5.

Construction : Contractor shall provide the reinforcement bars of tor steel or mild steel of

specified dia. at locations in numbers or at spacing’s, as per detailed designs, drawings and

schedules including cutting, bending, hooking the bars, binding with wires or tack welding and

supporting as required at all locations and height. The work shall be carried out as specified in

Gen/C/0.2.5. The reinforcement shall be got checked by the Engineer-in-charge or his

representative before concreting. The contractor shall provide and fix in position any additional

reinforcement, if directed, in addition to the reinforcement shown on drawing.

Item to Include : The item includes all the material of reinforcement bars, binding wires, welding

rods and labour and tools and equipment for cutting, bending welding, testing charges etc.

complete as per drawings and as directed by the Engineer-in-charge.

Mode of Measurement and Payment : The measurement of the reinforcement bars shall be

taken in metric tons Sub Estimate: Providing 50 mm thick semi grout with 20 mm thick PSS to Pentakali Jackwell road 1     Picking the old WBM surface up to a depth of 75 mm and re-sectioning, barreling and bringingthe surface to proper camber, alignment, gradient, including providing V groove at the periphery ofroad surface. Specification:

Page 160: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

7.1 General : The item provides picking the old WBM road surface and resectioning of the road

surface.

7.2 Road Diversion : while carrying out the picking operations, if the traffic cannot be allowed to

pass over the side shoulders, suitable diversions shall be provided and maintained till necessary

by the contractor at his risk and cost.

7.3 Picking Operation : All the caked mud, slush animal droppings, vegetation and all other

rubbish accumulated on the road-surface shall be removed. Where the section of the road surface

is good, the road surface shall be picked lightly only to loosen the surface stones. Where the

section is uneven picking shall be done a little deeper to enable the sectioning to be done to the

required shape with the picked up material. The picking shall always be ahead of the spreading of

metal and compaction by about 100 metres. The edges of the picking shall be truly in a line or

curve as the case may be. This can be achieved by tying strings to nails driven on the road edges

and ranging for a sufficiently long length. The picked up surface shall be sectioned to the required

grade and camber, super elevation or transition section. Templates shall be used to obtain correct

and uniform camber, super elevation or transition section as the case may be The V groove shall

be provided on either side of the road edges as directed, so as to avoid sliding away metal spread.

The road surface may be watered by the contractor for easier picking without claiming, extra for

the same. The junction of the picked and non-picked surfaces shall be diagonal.

7.4 Item to Include : The item includes all labour, materials, use of tools and equipment, etc. for

picking. It also includes watering, if required, sectioning, barreling, grading, diversions, including

barricading, warning signals, lights, etc., unless separately provided in the tender.

7.5 Mode of Measurement and Payment : The areas picked shall be worked out in sq. metres.

The width shall be limited to the width specified or as ordered by the Engineer-in-Charge. The

length shall be measured along the centerline of the road. Increased width on curves shall be

measured.                                                                       

The Contract rate shall be for one sq. meter of surface picked and sectioned. 2     Providing trap / stone / granite stone metal at the work site as directed in stacks of minimumsize of 3 x 2 x 1 m or as directed in stacks of higher sizes than the minimum tipulated aboveIncluding all loading / unloading operation and conveyance to the site of work lead up to 20 km.including all taxes and royalty charges. a) Standard size 40 mm (Hand Broken) Specification:

Specification :-

General : The item provides the supply of specified type of stone metal 40 mm size at the roadside

including obtaining the rubble from approved sources and hand breaking to size, conveying to the

site of work, including all lifts and leads and stacking in regular size as specified including making

payment for royalty and other taxes, octroi and duties etc.

Material : Metal shall be obtained from the approved quarries as specified below:

Quarries : The contractor shall obtain the metal of the approved quality to the extent required for

the work from the approved and authorized quarries. The contractor shall, however, obtain the

necessary permissions from the appropriate authorities, pay royalties and will be liable to pay

Page 161: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

compensation for any damage caused to the quarries or the land or property either deliberately or

through negligence or otherwise, or from waste of materials in obtaining the requisite quantity of

rubble.  The contractor shall make his own arrangement for metal supply approved by the

Engineer-in-Charge. The contractor shall be fully responsible for any and all compensations to be

paid as royalty, rents, octroi & duties or any other statutory charges or damages to properties and

injuries to persons etc., caused in obtaining the metal. No claim on account of any obstruction

caused in collection of materials or difficulties or action arising out of quarrying in private land shall

be entertained and MIDC will remain indemnified with regard to such action and payment.

Quarrying shall be done only from sound portions of approved quarries, the disintegrated and

weathered portions being rejected.

1.2.2    Metal :

Quality : The metal of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering and scale. The water

absorption shall be as low as possible but not more than 2 per cent. It shall generally be hand

broken metal. The metal shall be cubical in nature and shall pass the desired sieve.  The physical

test on metal shall be conducted by approved laboratory in the presence Engineer-in-Charge or his

representative. The cost of such testing shall be inclusive in unit rate of item.

Size : The shape of the stone metal shall be cubical. The stone shall be broken with the smallest

dimensions equal to the 40 mm thickness of size metal.

Before starting collection, the contractor shall get a sample conforming to the required quality

shape and size approved by the Engineer-in-Charge who will preserve/keep it in his site office for

reference. The size of the metal shall be 40 mm.

Conveyance to Site : Materials shall be brought to site sufficiently in advance of construction. The

contractor shall be responsible to see that vehicles used for transporting materials do not drop any

of the contents on the road and thus cause nuisance to traffic. The contractor shall also be

responsible for any damage or accident arising out of any such material falling on the road or

elsewhere and shall attend to all complaints in this regard. The Engineer-in-Charge may order the

removal of such materials at the cost of the contractor in case of negligence/or any other reason.

Vehicles conveying materials shall not obstruct traffic.  For all leads and lifts included in the rate for

the item.

Stacking : The metal shall be stacked uniformly along the roadside or as directed in regular stacks

of 3 m X 2 m X 1 m unless stacks of other sizes are ordered by the Engineer-in-Charge. Stacking

shall be done only after the quality, shape and size of the metal are approved. The stacks shall be

made without appreciable hollows without making special efforts to hand-pack the material. The

stacks shall be free of earth, rubbish, vegetation and shall confirm size specified. One stack in

each unit section may be of different length if necessary to make up the total quantity in that

particular section. Low and wide stacks with outer retaining walls and the center filled in loosely

shall not be permitted. The material shall be stacked entirely clear of the carriage way and as far a

possible beyond the side widths and the side drains, on even ground or in the absence of such

even ground the platforms prepared in advance for the purpose by the contractor at his cost. If no

such land is available, the width of the stack may be reduced and the stacks may be laid on the

Page 162: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

side widths with the approval of the Engineer-in-Charge. Such stacks shall be protected from being

disturbed. Necessary precautions such as barricading, signs and signals shall invariably be taken,

the contractor being responsible for any accident, injury and compensation due to his negligence in

this respect. On hill roads material shall be stacked only the side of the road as directed without

interfering with free drainage.  The Engineer-in-Charge, if required, get the stacks coming in the

way of or obstructing the traffic, removed at the cost of the contractor and the contractor shall not

be entitled to claim for any loss or damage to the materials on that account. The stacking

operations shall be started at the point farthest from the quarry and carried towards the nearest

point. The stacks shall not be laid at such places where they are likely to be damaged on account

of the traffic, washing out by rains or floods or drainage, slides of the banks or the slopes of

cutting. The contractor without extra claims shall make any loss on account of these or such other

reasons good.

As far as possible the metal shall be stacked evenly on one side of the road only and in such

quantities per unit length as will be required for that particular length or as ordered by the

Engineer-in-Charge.

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, octroi & duties, fees, rents, taxes etc. compensation due to

injuries to persons or damages to property in any way connected with the execution of this item

and for loss of materials due to improper stacking etc. And shall make good the losses without

extra claims.  The contractor shall be also responsible for the blasting operations required for

obtaining the rubble.

Item to Include :

1)         Obtaining metal of approved quality, shape and size from quarry metal, boulder metal and

making payment of royalties, taxes, fees, rents, octroi & duties etc.

2)         Conveying to roadside including all lead and lifts.

3)         Stacking.

Mode of Measurement and Payment : The contract rate shall be for one cubic meter of metal

supplied at site in stacks of approved size.  When the metal is stacked in stacks of one uniform

size, smallest stack may be chosen in the particular km or unit section and measured for its length,

breadth and depth. The cubic contents of the stack shall be multiplied by the number of such

heaps in the km or unit section to arrive at the quantity in the particular km or unit section. The

Engineer-in-Charge may measure any other heaps also for verification.  When the sizes of stacks

are not uniform, each stack shall be measured individually. The dimensions shall be measured

correct to two places of decimal of a meter and quantity worked out correct to two places of

decimals of a cubic meter. If there is reason to believe that the stacks are very loose and are

having unduly large hollows and or materials not satisfying the specifications, the stacks may be

got opened and restacked properly  after removing the inferior material as directed by the

Engineer-in-Charge by the contractor at his cost. The measurements of such a stack shall then be

taken and if they are less than those of a normal stack, the quantity of the restacked stack shall be

multiplied by the no. of stacks to arrive at the quantity in the particular unit or length.  No deduction

shall be made for voids. Metal shall not be used until the full quantity is collected in km or particular

Page 163: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

unit and measured. All stacks measured shall be marked with lime wash bands to distinguish them

to avoid double measurement.  If the material is found to be of inferior quality or of size not

satisfying the requirements, the same shall be rejected entirely.  All labour, materials etc. required

for measuring, restacking, checking, lime washing, etc., shall be at the cost of contractor.  The

contract rate shall be for one cubic meter of specified metal supplied at site in stacks of approved

size. 3     d) Standard size 25 mm (Crushed aggregate) Specification:

Specification

General : The item provides supply of stone aggregate of the specified type and size at the site of

work, including obtaining the stones of the specified quality from approved sources, manually

breaking or crushing them in mechanical crushers, loading into conveyor and unloading at sit of

work conveying for all  leads and all lifts, stacking in regular heaps as specified.

Material : Stones of approved quality shall be used for hand broken or crushed aggregate.

Quality : The rubble of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering. The water absorption shall

be as low as possible but not more than 2 per cent. They shall generally be broken rubble.

Stone Aggregate : The aggregates shall be obtained by crushing approved stones of specified

type in a mechanical crusher and shall be clean, strong, tough, dense, durable, close grained and

free from soft,  decayed and weathered portions and from coating of dust, dirt or other

objectionable matter. They shall preferably have good hydrophobic characteristics. The metal shall

generally satisfy the following physical requirements:-

Tests shall be carried out according to I.S.383-1970

Tests considered necessary shall be carried out in an approved laboratory.

Size of Metal shall be as under:-

Note :- Not more than 20% of any sample shall exceed in its greatest dimension standard size plus

25 mm. For 40 mm. Standard size, standard size plus 8 mm. For 25 mm, 20 mm and 12 mm

standard sizes and standard size plus 6 mm for 10 mm and 6 mm standard sizes plus 4 mm.  The

metal shall be roughly cubical in shape and of uniform size with sharp edges for interlocking.

Rounded, flaky thin, elongated metal shall not be accepted. Before collection, samples of the metal

shall be got approved for quality size and shape by the Engineer-in-Charge who will preserve them

in his site office for reference. They shall be completely dry at the time of use.

Conveyance : Materials shall be brought to site sufficiently in advance of construction. The

contractor shall be responsible to see that vehicles used for transporting materials do not drop any

of the contents on the road and thus cause nuisance to traffic. The contractor shall also be

responsible for any damage or accident arising out of any such material falling on the road or

elsewhere and shall attend to all complaints in this regard. The Engineer-in-Charge may order the

removal of such materials at the expenses of the contractor in case of neglect. Vehicles conveying

or disposing materials shall not obstruct traffic.  For all leads and lifts included in the rate for the

Page 164: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

item.

Stacking : The material shall be stacked uniformly along the roadside or as directed in regular

stacks of minimum size 3m X 2m X 1 m unless other sizes are ordered by the Engineer-in-Charge,

stacking shall be done only after the quality, shape and size of the material are approved. The

stacks shall be made without appreciable hollows without making special efforts to hand-pack the

material. The stacks shall be free of earth, rubbish, vegetation, inferior or too much oversize or

undersize material. One stack in each unit section may be of different length if necessary to make

up the total quantity in that particular section. Low and wide stacks with outer retaining walls and

the center filled in loosely shall not be permitted. The material shall be stacked entirely clear of the

carriage way and as far a possible beyond the side widths and the side drains, on even ground or

in the absence of such even ground the platforms prepared in advance for the purpose by the

contractor at his cost. If no such land is available, the width of the stack may be reduced and the

stacks may be laid on the side widths with the approval of the Engineer-in-Charge. Such stacks

shall be protected from being disturbed. Necessary precautions such as barricading, signs and

signals shall invariably be taken, the contractor being responsible for any accident, injury and

compensation due to his negligence in this respect. On hill roads material shall be stacked only on

the side of the road as directed without interfering with free drainage. The Engineer-in-Charge

may, if required, get the stacks coming in the way of or obstructing the traffic, removed with the

cost of the contractor and the contractor shall not be entitled to claim for any loss r damage to the

materials on that account. The stacking operations shall be started at the point farthest from the

quarry and carried towards the nearest point. The stacks shall not be laid at such places where

they are likely to be damaged on account of the traffic, washing out by rains or floods or drainage,

slides of the banks or the slopes of cutting. The contractor without extras claims shall make any

loss on account of these or such other reasons good. As far as possible the metal shall be stacked

evenly on one side of the road only and in such quantities per unit length as will be required for

that particular length or as ordered by the Engineer-in-Charge. Each size of aggregate shall be

stacked separately and entirely clear from the carriageway and where possible clear of the

shoulders also. They shall be stacked in such a manner as to prevent mixture, deterioration or

contamination

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, fees, rents, taxes, octroi, duties, etc. Compensation due to injuries

to persons or damages to property in any way connected with the execution of this item and for

loss of materials due to improper stacking etc. and shall make good the losses without extra

claims. The contractor shall also responsible for the blasting operations.

Item to Include :

1) Obtaining metal of approved quality, shape and size from  quarry metal, boulder metal, Laterite

metal and payment of royalties, taxes, octroi, duties, fees, rents, etc.

2) Conveying to roadside including  all lead and lifts.

3) Stacking.

Mode of Measurement and Payment :

The contract rate shall be for one cubic meter of material supplied at site in stacks of approved

Page 165: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

size. When the material is stacked in stacks of one uniform size, smallest stack may be chosen in

the particular km or unit section and measured for its length, breadth and depth. The cubic

contents of this heap shall be multiplied by the number of such stacks in the km or unit section to

arrive at the quantity in the particular km or unit section. The Engineer-in-Charge may measure

any other stacks also for verification. When the sizes of stacks are not uniform, each stack shall be

measured individually. The dimensions shall be measured correct to two places of decimal of a

meter and quantity worked out correct to two places of decimals of a cubic meter. If there is reason

to believe that the stacks are very loose and are having unduly large hollows and or materials not

satisfying the specifications, the stacks may be got opened and restacked properly after removing

the inferior material as directed by the Engineer- in charge at the contractor’s cost. The

measurements of such a stack shall then be taken and if they are less than those of a normal

heap, the quantity of the restacked heap shall be multiplied by the no. of stacks to arrive at the

quantity in the particular unit or length. No deduction shall be made for voids. Material shall not be

used until the full quantity is collected in km or unit length and measured. All stacks measured shall

be marked with lime wash bands to distinguish them to avoid double measurement. If the material

is found to be of inferior quality or of size not satisfying the requirements, the same may be

rejected entirely. All labour, materials etc. required for measuring, restacking, checking, lime

washing, etc. shall be at the cost of contractor. 4     f) 12 mm size (crushed aggregate) Specification:

Specification

General : The item provides supply of stone aggregate of the specified type and size at the site of

work, including obtaining the stones of the specified quality from approved sources, manually

breaking or crushing them in mechanical crushers, loading into conveyor and unloading at sit of

work conveying for all  leads and all lifts, stacking in regular heaps as specified.

Material : Stones of approved quality shall be used for hand broken or crushed aggregate.

Quality : The rubble of the trap stones shall be hard, tough, sound, durable, dense, clean, of close

texture and free from unsound material, cracks, decay and weathering. The water absorption shall

be as low as possible but not more than 2 per cent. They shall generally be broken rubble.

Stone Aggregate : The aggregates shall be obtained by crushing approved stones of specified

type in a mechanical crusher and shall be clean, strong, tough, dense, durable, close grained and

free from soft,  decayed and weathered portions and from coating of dust, dirt or other

objectionable matter. They shall preferably have good hydrophobic characteristics. The metal shall

generally satisfy the following physical requirements:-

Tests shall be carried out according to I.S.383-1970

Tests considered necessary shall be carried out in an approved laboratory.

Size of Metal shall be as under:-

Note :- Not more than 20% of any sample shall exceed in its greatest dimension standard size plus

25 mm. For 40 mm. Standard size, standard size plus 8 mm. For 25 mm, 20 mm and 12 mm

Page 166: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

standard sizes and standard size plus 6 mm for 10 mm and 6 mm standard sizes plus 4 mm.  The

metal shall be roughly cubical in shape and of uniform size with sharp edges for interlocking.

Rounded, flaky thin, elongated metal shall not be accepted. Before collection, samples of the metal

shall be got approved for quality size and shape by the Engineer-in-Charge who will preserve them

in his site office for reference. They shall be completely dry at the time of use.

Conveyance : Materials shall be brought to site sufficiently in advance of construction. The

contractor shall be responsible to see that vehicles used for transporting materials do not drop any

of the contents on the road and thus cause nuisance to traffic. The contractor shall also be

responsible for any damage or accident arising out of any such material falling on the road or

elsewhere and shall attend to all complaints in this regard. The Engineer-in-Charge may order the

removal of such materials at the expenses of the contractor in case of neglect. Vehicles conveying

or disposing materials shall not obstruct traffic.  For all leads and lifts included in the rate for the

item.

Stacking : The material shall be stacked uniformly along the roadside or as directed in regular

stacks of minimum size 3m X 2m X 1 m unless other sizes are ordered by the Engineer-in-Charge,

stacking shall be done only after the quality, shape and size of the material are approved. The

stacks shall be made without appreciable hollows without making special efforts to hand-pack the

material. The stacks shall be free of earth, rubbish, vegetation, inferior or too much oversize or

undersize material. One stack in each unit section may be of different length if necessary to make

up the total quantity in that particular section. Low and wide stacks with outer retaining walls and

the center filled in loosely shall not be permitted. The material shall be stacked entirely clear of the

carriage way and as far a possible beyond the side widths and the side drains, on even ground or

in the absence of such even ground the platforms prepared in advance for the purpose by the

contractor at his cost. If no such land is available, the width of the stack may be reduced and the

stacks may be laid on the side widths with the approval of the Engineer-in-Charge. Such stacks

shall be protected from being disturbed. Necessary precautions such as barricading, signs and

signals shall invariably be taken, the contractor being responsible for any accident, injury and

compensation due to his negligence in this respect. On hill roads material shall be stacked only on

the side of the road as directed without interfering with free drainage. The Engineer-in-Charge

may, if required, get the stacks coming in the way of or obstructing the traffic, removed with the

cost of the contractor and the contractor shall not be entitled to claim for any loss r damage to the

materials on that account. The stacking operations shall be started at the point farthest from the

quarry and carried towards the nearest point. The stacks shall not be laid at such places where

they are likely to be damaged on account of the traffic, washing out by rains or floods or drainage,

slides of the banks or the slopes of cutting. The contractor without extras claims shall make any

loss on account of these or such other reasons good. As far as possible the metal shall be stacked

evenly on one side of the road only and in such quantities per unit length as will be required for

that particular length or as ordered by the Engineer-in-Charge. Each size of aggregate shall be

stacked separately and entirely clear from the carriageway and where possible clear of the

shoulders also. They shall be stacked in such a manner as to prevent mixture, deterioration or

contamination

Page 167: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Special Points : The contractor shall be responsible for obtaining consent of owners of quarries

and lands, payment of royalties, fees, rents, taxes, octroi, duties, etc. Compensation due to injuries

to persons or damages to property in any way connected with the execution of this item and for

loss of materials due to improper stacking etc. and shall make good the losses without extra

claims. The contractor shall also responsible for the blasting operations.

Item to Include :

1) Obtaining metal of approved quality, shape and size from  quarry metal, boulder metal, Laterite

metal and payment of royalties, taxes, octroi, duties, fees, rents, etc.

2) Conveying to roadside including  all lead and lifts.

3) Stacking.

Mode of Measurement and Payment :

The contract rate shall be for one cubic meter of material supplied at site in stacks of approved

size. When the material is stacked in stacks of one uniform size, smallest stack may be chosen in

the particular km or unit section and measured for its length, breadth and depth. The cubic

contents of this heap shall be multiplied by the number of such stacks in the km or unit section to

arrive at the quantity in the particular km or unit section. The Engineer-in-Charge may measure

any other stacks also for verification. When the sizes of stacks are not uniform, each stack shall be

measured individually. The dimensions shall be measured correct to two places of decimal of a

meter and quantity worked out correct to two places of decimals of a cubic meter. If there is reason

to believe that the stacks are very loose and are having unduly large hollows and or materials not

satisfying the specifications, the stacks may be got opened and restacked properly after removing

the inferior material as directed by the Engineer- in charge at the contractor’s cost. The

measurements of such a stack shall then be taken and if they are less than those of a normal

heap, the quantity of the restacked heap shall be multiplied by the no. of stacks to arrive at the

quantity in the particular unit or length. No deduction shall be made for voids. Material shall not be

used until the full quantity is collected in km or unit length and measured. All stacks measured shall

be marked with lime wash bands to distinguish them to avoid double measurement. If the material

is found to be of inferior quality or of size not satisfying the requirements, the same may be

rejected entirely. All labour, materials etc. required for measuring, restacking, checking, lime

washing, etc. shall be at the cost of contractor. 5     Spreading metal on road surface from 40 mm to 10 mm standard size and spreading evenly torequired camber and gradient with lead up to 100 m from stacks. Specification:

11.1 General : The item covers to provide the labour for conveying the metal of standard size from

the roadside stacks and spreading it for the road sectioning.

11.2 Spreading Metal : The metal shall be screened if it contains grass, rubbish dust or other

deleterious foreign material. ‘V’ groove is excavated on either edges of metal width to avoid sliding

away spread metal during rolling. The groove will ensure clean straight/curve edge of road. The

metal shall be spread evenly over the rolled rubble soling surface or WBM surface or as directed

Page 168: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

by giving a twisting motion to the basket at the time of spreading. In order to ensure the correct

thickness, the road area shall be suitably marked so as to receive the contents of one stack for the

specified thickness in the area marked. The unevenness and undulations after the spreading shall

be rectified either by thinning the metal or adding it as required. The metal so spread shall be

checked by camber boards and line for the camber and grade at intervals of every 10 meters or so.

The edge line stakes shall be ranged for a sufficiently long length to obtain straight lengths and

uniform curves. The sides of the metal shall be held by bunds of murum to prevent metal from

spreading if side widths are not provided at the time. These bunds shall be of such depth as to

support the metal. The junction of the existing road and the new construction shall be diagonal in

plan. Between the straight lengths and curves and at the meeting points of convex and concave

portions of reverse curves the change in the camber shall made very gradually as directed by the

Engineer-in-Charge.

11.3 Item to Include : The item includes providing all labour, tools, and equipment for conveying

the metal from the roadside stacks and spreading even to the required depth, width and section.

The item includes all leads & lifts as directed by Engineer-in-Charge.

11.4 Mode of Measurement and Payment : The quantity of spreading of metal of the specified

size shall be arrived at by deducting the quantity in balance in stacks from the total collection

existing on the roadside before spreading is started. The quantity on site shall be checked before

spreading is started and after completion of spreading. The contract rate shall be for spreading one

cubic meter of metal as per direction of Engineer-in-Charge. 6     Watering over sub-grade consisting of soling and / or oversize metal. Specification:

9.1 General : The item provides the watering over soling, oversize and size metal.

9.2 Material and Equipment : Water to be used shall be free of harmful elements, which may

cause heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall

make his own arrangements for getting adequate quantity of acceptable water. Only just sufficient

water as is necessary shall be sprinkled uniformly with the help of water tanker and/or sprinkler

over the hard murum/blindage so as to obtain maximum compaction with the type of rolling

adopted without total crushing of the material. The water shall be used profusely small fillets shall

be provided at edges so that the water will not flow away. The roller shall move in water slurry

which will penetrate into crevices all voids in metal shall feet fill in and proper bond in the metal

shall be formed.

9.3 Item to Include : All clean water, material, machinery, equipment, labour, taxes etc. shall be

included in the rate.

9.4 Mode of Measurement and Payment : The measurement shall be the area of road surface

watered in sqm upto two decimals. The payment shall be at the rate per sqm. 7     Rolling with 8 / 10 tonne vibratory roller over 40 to 25 mm standard size metal to finish thesurface to required camber and gradient until proper interlocking. a) 8-10 tonne power roller Specification:

Page 169: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

General : After spreading 40 to 25 mm standard size metal laid to the required thickness,

grade and camber the same shall be uniformly compacted to the full width with 8 to 10

tonne roller. In portions having unidirectional cross fall/super elevation, rolling shall

commence from the lower edge and progress gradually towards the upper edge. The roller

should progress parallel to the centerline of the road, from edges uniformly overlapping

each preceding track by at least one third width until the entire surface has been rolled.

Alternate strips of the roller shall be terminated in stops at lead 1mt away from any

preceding stop. The rolling shall be continued till no impression of rear wheels appear. Any

displacement occurring as a result of reversing of the direction of the roller or from any

other cause shall be corrected at once as specified and/or removed and made good.

Required quantity of water shall be sprinkled over the aggregate to remove dust etc. if

required. All loose, segregated uneven or otherwise defective areas should be made good

to the full thickness of the layer and re-compacted. The

item shall be executed as per direction of Engineer-in-Charge.

13.2 Mode of Measurement and Payment : The measurement shall be in per sq. mtr of the

compacted layer of the finished metal surface. 8     Supplying and stacking at works site as directed 30 / 40, 60 / 70 and 80 / 100 penetrationgrade asphalt in bulk conforming to IS:73-1992. For all lead of asphalt c) VG 10 Specification: General : The item provides supplying and stacking at works site of

specified penetration grade asphalt in bulk

 1.2 Material : Asphalt or bitumen shall be straight run conforming to IS:

73 or industrial bitumen as per IS: 702 of suitable consistency

satisfying the requirement of physical properties as give in table below

                                          PHYSICAL PROPERTIES OF BITUMEN

Table

Sr.

NoCharacteristics Requirements

Method of

Test

Penetration at 250 C in

1/10 mm20 to 40

Softening point (R&B) 50 to 90 IS: 1205

Ductility at 270 C (Min.

is cms) 3 IS: 1208

Page 170: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

.

                                          PHYSICAL PROPERTIES OF BITUMENTable

                                          PHYSICAL PROPERTIES OF BITUMENTable

1.3 Conveyance and Stacking : The asphalt is to be carried from the

refineries in the bulk containers approved by the RTO and other

authorities. The transportation is entire responsibility of the contractor.

MIDC is not responsible for any loss or damage to asphalt or the

vehicle or to any accident, claims etc. The item shall be treated as

complete only after the asphalt is received at the work site. For

stacking the asphalt the contractor shall provide the necessary

containers of the required capacities.

1.4 Item to Include : Item includes loading of asphalt in bulk container at

the Mumbai Refinery, unloading in the bulk containers provided at the

work site, etc. complete, including all the labour, container vehicle its

Maharashtra Industrial Development Corporation

99

all costs such as fuel, insurance, paying of all taxes, claims, damages,

depreciation, labour etc., complete. The rate is excluding the

transportation, which shall be paid at the appropriate rate as per Item

No.Rd/F/3, for the specified distance from the Mumbai Refinery. The

contractor shall have to furnish original challan of the refinery

alongwith weighment slips in original before use and after use of

asphalt.

1.5 Mode of Measurement and Payment : The quantity of the asphalt/

bitumen, of specified penetration grade supplied and stacked at the

work site shall be measured in Metric tonne. The payments for the

Loss on heating

percent

(Maximum)

 1 IS: 1212

Solubility in CS2

percent

(Minimum)

 99 IS: 1216

Page 171: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

quantity stacked shall be at the contract rate per MT. The

transportation charges shall be paid as per the item Rd/F/3. 9     Heating asphalt to its boiling point and evenly spreading it over road surface for grouttreatment / tack coats / seal coats. a ) Bulk asphalt Specification:

General : The item provides the heating of asphalt supplied at the

work site under item no. Rd/F/1 and Rd/F/2 to its boiling point and

spreading the same over road surface for grout treatment / tack coats/

seal coats.

4.2 Preparation of Surface : Preparation of road surface shall be carried

out under appropriate separate item.

Prior to the application of the binder, all dust, dirt, caked murum,

animal dung, loose and foreign material etc. shall be removed 30 cm

on either side, beyond the full width to be treated, by means of

mechanical sweepers and blowers, if available or otherwise with wire

brushes, small picks, brooms etc. The material so removed shall be

disposed off as directed by the Engineer-in-charge.

For WBM surface, the interstices between the road metal shall be

exposed upto a depth of about 10 mm by means of wire brushes picks.

The surface shall then be brushed with soft brooms to remove all loose

aggregates. Finally the traces of fine dust, which gets accumulated

while brushing, shall be thoroughly removed from the surface by

blowing with gunny bags.

The prepared surface shall be closed to traffic and maintained fully

clean till the binder bitumen/asphalt is applied.

4.3 Heating and Applying Asphalt/Binder (Hot Bitumen) : The asphalt/

bitumen shall be heated in a boiler to a temperature for 30/40 grade &

60/70 grade up to 1770 C to 1910 C (3500 F to 3750 F) and for 80/100

Maharashtra Industrial Development Corporation

104

grade up to 163

0 C to 1770 C (3250 F to 3500 F) and the temperature

shall be maintained at the time of actual application. The use of a

thermometer being essential.

The binder shall be applied evenly to the clean dry surface by means of

a pressure sprayer at the rate specified. The binder shall be applied

longitudinally along the length of the road and never across it. The

edges of the binder surface shall be defined by wire or a rope stretched

in position.

Page 172: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Heating in cut out drums and pouring from perforated tins, cans and

such other methods shall not be permitted. Except in the case of petty

works and repairs with the specific approval of the Engineer-in-charge.

Excessive deposits of binder caused by stopping of the sprayer or

through leakage or any other reason shall be suitably corrected before

the stone chipping are sprayed.

4.4 Mode of Measurement and Payment : The quantity of asphalt heated

and applied shall be measured in Metric tonne and also the source of

asphalt shall be recorded whether from bulk supply or from drum

supply. In respect of bulk asphalt/bitumen carriers the same shall be

weighed before application of asphalt/bitumen and also after the

application of the asphalt/bitumen. The difference in these to weights

and/or the quantity worked out with reference to the rate of application

of the asphalt/bitumen and the area of actual application, whichever is

lower shall be payable. The weightment slips in original for the

weighment of asphalt at the approved weigh bridge before use and

after use of asphalt shall be submitted by the contractor.

The item rate shall be per Metric tonne of asphalt heated and applied. 10     Rolling with 8 / 10 tonne vibratory roller on the grouted surface. Specification:

14.1 General : The item provides rolling after grouting the surface.

14.2 Spreading and Rolling : After spreading the 10 mm metal aggregate over the grouted

surface, in specified quantities. The rolling shall be done over the grouted surface uniformly

compacted to full width with 8 to 10 tonne vibratory roller. In portions having unidirectional cross

fall/super elevation, rolling shall commence from the lower edge and progress gradually towards

the upper edge. The roller should progress parallel to the centerline of the road, from edges

uniformly overlapping each preceding track by at least one third width until the entire surface has

been rolled. Alternate strips of the roller shall be terminated in stops at lead 1mt away from any

preceding stop. The rolling shall be continued till no impression of rear wheels appear. Any

displacement occurring as a result of reversing of the direction of the roller or from any other cause

shall be corrected at once as specified and/or removed and made good. Required quantity of water

shall be sprinkled over the aggregate to remove dust etc. if required. All loose, segregated uneven

or otherwise defective areas should be made good to the full thickness of the layer and re-

compacted. The item shall be executed as per direction of Engineer-in-Charge.

14.3 Item to Include : All the labour, machinery, tools and plants required for rolling are included

in this item. The supply and spreading the metal over the grouted surface shall be paid under

relevant item.

14.4 Mode of Measurement and Payment : The contract rate shall be for compacting one sqm

area of the road of the full width after spreading 12 to 10 mm metal as shown in the section

Page 173: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

including increased widths on curves, road crossings etc. The area of the road compacted shall be

measured and paid in sqm. 11     Providing and laying 20 mm. thick premix seal surfacing with all leads as directed, preparingand cleaning the base, heating aggregates at 0.27m3 per 10m2 of aggregates of specified size,mixing with heated asphalt 60 / 70 grade / CRMB / PMB 22 kg. per 10m2 in a hot mix plant andspreading over the surface to be treated after applying tack coat using 80 / 100 grade asphalt dose5 kg/10m2 or bituminous emulsion grade conforming to IS: 8887 dose 2.50 kg / 10 m2, laying themix seal surfacing with hydrostatic paver with sensor control & compaction to the desire level etc.complete. A) By using penetration grade asphalt for tack coat. a)  Using VG 30 grade Specification:

Specification :-

22.1 General : This work shall consists of constructing a single layer of 20 mm thickness of premix

seal surfacing, on previously prepared bituminous base to the requirements of these specifications,

to serve as a sealing course.

22.2 Materials :

22.2.1 Bitumen :

The bitumen shall be paving bitumen of suitable penetration grade 60/70 as per Indian Standard

Specifications for “Paving Bitumen” IS: 73-1961.

22.2.2 Coarse Aggregates :     

The aggregates shall consist of crushed stone, crushed gravel/shingles or other stones. They shall

be clean, strong, durable and fairly cubical in shape and free from disintegrated pieces, organic or

other deleterious matter and adherent coating. The aggregate shall satisfy the physical

requirement as per Table below :

                                                           Property Test Specification

Cleanliness (dust)                  Grain size analysis1                                                                Max 5% passing

0.075mm sieve

Particle shape                       Flakiness and Elongation Index (Combined)2             Max 30%

Strength*                               Los Angeles Abrasion Value3                                          Max 40%

                                               Aggregate Impact Value3                                              Max 30%  Durability                                      Soundness4

                                                 Sodium Sulphate                                              Max 12%

                                              Magnesium Sulphate                                            Max 18%

Water Absorption                      Water absorption5                                                           Max 1%

Stripping                                   Coating and Stripping of Bitumen

                                                  Aggregate Mixtures6                                                    Minimum retained

coating 95%

Water Sensitivity7                                     Retained Tensile Strength8                                        Min 80%

Notes :

Notes : 1. IS: 2386 Part I        4. IS: 2386 Part 5

Page 174: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

2. IS: 2386 Part II       5. IS: 2386 Part 3

(the elongation test to be done only on non-flaky aggregates in the sample)

3. IS: 2386 Part 4*      6. IS: 6241

7. The water sensitivity test is only to be carried out if the minimum retained coating in the stripping

test is less than 95%

* Aggregate may satisfy requirements of either of the tests.

** Elongation index is wt. of Elongated particles divided by non flaky particles. The value of

Flakiness index and Elongation index so found are added for total Flakiness and Elongation

indexes.

If crushed gravel/shingle is used, all of the gravel/shingle pieces retained on 4.75 mm sieve shall

have at least one fractured face. The plasticity index of the fraction passing the 425-micron sieve

shall not exceed 4.0%.

22.2.3 Fine Aggregates :

Fine aggregates shall be the fraction passing 2.36 mm sieve and retained on 75 micron sieve,

consisting of crusher run screenings, natural sand or a mixture of both. These shall be clean, hard,

durable, uncoated, dry and free from any injurious, soft pieces and organic or other deleterious

substances.

22.2.4 Filler :

Filler shall consist of finely divided mineral matter such as rock dust, hydrated lime or cement as

approved by the Engineer-incharge. The filler shall be graded within the following limits as per

Table below:

             

The filler shall be free from organic impurities and have a plasticity index not greater than 4. The

plasticity index requirement shall not apply if filler is cement or lime.

22.3 Mix Design : As specified in the description of the items.

22.4 Construction Operation :

22.4.1 Weather and Seasonal Limitations : The work of laying shall not be taken up during rainy or

foggy weather, when the base course is damp or wet, or during dust storm or when the

atmospheric temperature in shade is 10°C or less.

22.4.2 Preparation of Base : The base on which premixed seal surface is to be laid shall be

prepared, shaped and conditioned to the specified levels, grade and cross fall (camber) in

accordance with specifications or as directed by the Engineerin- Charge. The surface shall be

thoroughly swept, clean, free from dust and foreign matter using mechanical broom and dust

removed by mechanical means or blown off by compressed air. In portions where mechanical

 Sieve percentage passing by weight 

 600 Micron  100

 300 Micron  95 - 100

 50 Micron  85  - 100

Page 175: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

means cannot reach, other approved method shall be used as directed by the Engineer-in-Charge.

22.4.3 Tack Coat : The tack coat shall be applied over the base preparatory at 3 Kg./10 Sqm.

22.4.4 Preparation of Mix : The aggregate gradation for MSS shall be as under:

Hot mix plant of adequate capacity and capable of producing a proper and uniform quality mix shall

be used for preparing the mix. The plant may be either a batch type or continuous or drum mix

type.

The Plant shall have the following essential features :

A. For Batch Type Plant :

a. Gradation control unit having vibratory screens for accurate sizing of hot aggregate and storing

them in separate bins.

b. Proper arrangement for accurate weighing of each size of hot aggregate from the control panel

before mixing.

B. For Continuous Type Plant :

a. Gradation control unit having vibratory screens for accurate sizing of hot aggregate and storing

them in separate bins.

b. There should be appropriate arrangement for regulating and volumetric control of the flow of hot

aggregate from each bin to achieve the required proportioning.

C. For Drum Mix Plant :

a. It is prerequisite that only properly screened graded materials are fed to the bins. A vibratory

screening unit should be installed at the plant site to ensure the same.

b. Belt conveyors below each bin and main gathering conveyor should have variable speed drive

motors. There should be electronic load sensors on the main conveyor for measuring the flow of

aggregates. The temperature of binder at the time of mixing shall be in the range of 150°C - 165°C

and that of aggregate in the range of 155°C - 170°C. provided also that at no time shall the

difference in temperature between the aggregate and binder exceeds 14° Centigrade. The

temperature of both the aggregates and the bitumen at the time of mixing shall be in accordance

with the job mix formula and strictly controlled. All overheated and carbonized mixtures, which form

or show indication of excess moisture, will be rejected. Any truck/tipper causing excessive

segregation of material by its spring suspension or other contributing factor or that show undue

 IS Sieve designation (mm)  Cumulative % by weight of total aggregates passing through  

 A Type  B Type

 13.20 ( mm )       --  100

 11.20 ( mm )  100   88 - 100

 5.60  ( mm ) 52 - 88  31 - 52

 2.80   ( mm )  14 - 38  5  - 25

 0.09    ( mm )  0  - 5  0  - 5

Page 176: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

delays shall be removed from the work until such conditions are corrected.

22.5 Item to Include : Item includes all material, machinery, plant, tools and equipment for

providing and laying hot mixed hot laid premixed bituminous seal surface.

Mode of Measurement and Payment :

Item shall be measured as finished work as square metres of sealing surface laid and compacted

of 20 mm thickness of specified type. The contract rate shall be per sqm of the work done as per

above specifications. vibratory roller instead of ordinary roller. 12     Earthwork in embankment with approved material having field soak CBR not less than 8 andlaboratory soak CBR not less than 12 obtained by the Contractor from his borrow areas includingall lifts and leads including laying in layers of 20cm to 30cm for power roller and 45cm to 60cm forvibratory compactor, breaking clods, and dressing to the required lines, curves and sectionincluding payment of royalty charges to the Govt. of Maharashtra. (Lead shall be certified by Dy.Engr.) c) Any Lead (from 10 to 20 km) Specification:

General : The work provides setting out and preparing the ground and

forming embankment for the road with approved material obtained

from MIDC borrow areas or pits, laying in layers, of 20 cm to 30 cm

for compaction by 8-10 road roller and 40 cm to 50 cm , if compacted

by vibratory compaction to achieve required density and lines, grades,

cross section and dimensions shown on the plan or as directed by the

Engineer-in-Charge with due allowance of shrinkage for compaction.

2.2 Material : All the useful and acceptable material obtained from MIDC

borrow areas with CBR not less than 8 as directed shall be used for the

embankment work. Approved soil, murum or a mixture of soil, sand,

murum, gravel, small boulders or rubble shall be used. Black cotton

soil, shadu or shrinkable soils shall not be used. Soils having

laboratory dry density of less than 1.75 gm/ cc shall be rejected. For

embankments more than 3 m in height, soil with laboratory dry density

of less than 1.52 gm/ cc shall not be used. Only the materials

considered suitable by the Engineer-in-Charge shall be used for the

embankment. Rejected materials shall not be brought to the work site.

The perishable material if any, such as stumps, pieces of wood, roots,

rubbish, etc. shall be removed from the approved material.

The material required for embankment shall be obtained in any of the

following ways provided the material is suitable in the opinion of the

Maharashtra Industrial Development Corporation

5

Engineer-in-Charge provide the CBR value of the excavated material

is more than 8.

1. From cuttings from nearby sections of the road as directed.

Page 177: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

2. From excavation for improving sight distance in nearby curves as

directed.

3. By widening any adjacent nalla or waterways if directed by

Engineer-in-charge.

4. By excavating cuts to lead water away from the road.

5. From wasteland outside the road land.

6. From humps above the general ground level within the road land.

7. From land acquired temporarily by the contractor if any, outside

the road land.

8. From borrow pits in Departmental land when permitted.

The contractor shall use the material in priorities specified by the

Engineer-in-Charge for obtaining the materials from different sources.

All lifts and leads involved in conveying the material to site shall be

included in the rate.

The material required for embankment from MIDC’s borrow areas,

will be made available to the contractor free of cost. The payment for

taxes, duties, octroi and royalty as appropriate levied by the Govt. shall

have to be made by the contractor. Borrow pits shall be excavated

according to directions of the Engineer-in-Charge. If the materials are

obtained from private lands in lieu of stipulated MIDC borrow areas,

for the sake of convenience of the contractor, he shall make his own

arrangements for payments of rents, compensation, taxes, duties, octroi

and royalty etc. and shall not be entitled for extra claims.

MIDC shall remain indemnified regarding any claims that may be

made by private owners in this respect. Roadside borrow pits if

permitted shall be dug according to the directions of the Engineer-incharge.

Maharashtra Industrial Development Corporation

6

2.3 Setting Out : Alignment of the road shall be set out as shown in the

drawing or as directed true to lines, curves, and grades. Profiles shall

be set out with stout poles to mark the center and edges of the

formation with the top levels of formation clearly marked by paint or

cut and the slopes with string and pegs at every 30 meters on straight

portions and 10 m or less on curves or as directed by the Engineer-in-

Charge. The toe line shall be marked with pick marks. Longitudinal

and cross-section levels shall be taken, recorded and signed by the

contractor or his authorized representative.

All the materials and labour required for this item shall be supplied by

the contractor and profiles, B.M.s etc. shall be put up by the contractor.

The cost of these operations is included in rate of this item.

Profiles, pegs, benchmarks and other marks shall be maintained

Page 178: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

without any disturbance as long as they are required, and directed by

the Engineer-in-charge.

2.4 Equipment : Pickaxes, crowbars, phawras, and Ghamelas maybe used

for manual work : Scrapers, dozers, graders, shovels, dumpers, trucks,

trolleys, etc. may be used for mechanical work, at the cost of the

contractor. Three wheels, 8 tones Power Roller giving a pressure

required to obtain the specified density may be state used for

compaction. Bullock carts with tanks or mechanically driven tankers

may be used for watering. The contractor shall submit the list of

equipments available with him and intended to be used on the work

and shall be got approved for their use from the Engineer-in-charge.

2.5 Construction Methods :

2.5.1 Diversions : If diversions, barricading and signals are

necessary, they shall be provided, without any extra cost.

2.5.2 Preparing the Ground for Laying Bank : Before any

material is laid for the bank the ground shall be cleared of all

Maharashtra Industrial Development Corporation

7

rubbish, removing bushes etc., and the holes, if any, filled up.

When the embankment is to be laid on hillsides or slopes, the

existing slopes shall be ploughed deeply.

If the cross slopes are steeper than 1 in 3, steps with reverse

slope state shall be cut into the slopes to give proper hold and

seating to the bank as directed by the Engineer-in-Charge. On

surfaces flatter than 1 in 15, no special surface treatment such

as cutting steps shall be necessary. The top 15 cm of soil shall

be scraped and watered to OMC as directed and compacted to

the same density as specified for the embankment before any

material is laid for the Bank-work. No extra payment shall be

paid for this activity.

When the embankment is to be placed over an existing road or

other hard surface, which is within 15 cm of the finished

formation, the road or other hard surface shall be scraped to a

minimum depth of 15 cm without extra cost.

The rate for embankment includes all the operations for

preparing the bed for laying the embankment material.

2.5.3 Laying the Bank : The material for embankment shall be

placed in successive horizontal layers of 20 cm to 30 cm

thickness extending to the full width of the embankment

including the slopes at the level of the particular layer and 30

cm more on both sides to allow compaction of the full specified

Page 179: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

section. The extra loose stuff at the edges shall be trimmed

later after completion of the bank work without extra cost

leaving the correct section fully compacted.

Keeping width of the bank initially less and widening it later by

dumping loose earth on the slopes shall not be permitted as the

additional width and slopes will not get homogenous to the

Maharashtra Industrial Development Corporation

8

earlier laid embankment and compaction of such embankment

may not be uniform. Similar procedure to extend the

embankment by dumping the material longitudinally shall also

not be allowed. When boulders, broken stones, and similar hard

materials are mixed up with the embankment materials, care

shall be taken to see that they are distributed uniformly in to the

bank, so that no hollows are left near them. No stone or hard

material shall project above the top of any layer. Each layer of

embankment shall be watered, to OMC leveled and compacted

as specified, before the succeeding layer is placed (watering

and consolidation shall be paid separately) under relevant

items. The surface of the embankment shall, at all times during

construction, be maintained at such a cross fall as will shed

water and prevent ponding. If bridges and culverts on the road

are not completed in advance of bank work, a length of 15 m to

30 m bank shall be left on either sides of the structure and these

lengths shall be dealt with later for placing the embankment

work. The camber as stipulated shall be provided in the

embankment only and shall not be adjusted in metalling.

2.6 Protection : Proper care shall be taken to ensure that the method of

operation and compaction of the bank-work does not cause damage or

undue strain to any structural element. Embankment over and around

bridges or culverts shall be of approved materials and carefully placed

and compacted. The contractor shall take all precautions necessary for

the protection of the bank-work by diversions of streams, local surface

drainage, rain water, etc. likely to damage the bank. Any damage to

the embankment-work in absence of proper protection or inadequate

protection shall be made good by the contractor at his own cost.

Conveyance of materials shall not cause obstruction or nuisance to the

nearby property owners and traffic.

2.7 Finishing : The embankment shall be finished and dressed smooth and

even in conformity with the alignment, levels, gradient cross-sections

Maharashtra Industrial Development Corporation

Page 180: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

9

and dimensions shown on the drawing are with due allowances for 1%

shrinkage. On curves, sections shall be provided with super elevation

and increased widths as shown on the plans or as directed by the

Engineer-in-Charge. All damages caused by rain, flood or any other

reasons shall be made good in the finishing operations without any

extra cost by the contractor. The road land width shall be cleared.

2.8 Maintenance : The contractor shall be responsible for maintaining the

embankment work satisfactorily at his own cost till the completion of

the defect liability period as specified in the contract agreement.

2.9 Test :

(a) Tests shall be carried to determine the required density of the

material to be used by the Proctor Density method before

starting and during the progress of the work. Tests shall be

carried out in approved laboratory/Govt. approved laboratory.

(b) Density tests shall be carried out for the embankment work

during the progress of the work. One set of three core samples

for every 1,000 sqm area of each layer of embankment work

shall be taken and tested. The average density shall not be less

than 95% of the standard proctor density. A deviation of 80 kg

per cum for fine and 160 kg per cum for coarse grained murum

shall be permitted in dry density in individual sample if the

average density reached up to 95% of standard proctor density

for each set.

(c) The required number of CBR tests and other tests shall be

carried out as directed by the Engineer-in-Charge.

2.10 Item to Include :

1) Setting out alignment including necessary labour and materiel

and maintaining it as long as required and directed by the

engineer-in- charge of the work.

Maharashtra Industrial Development Corporation

10

2) Preparing the ground for laying the embankment.

3) Providing and maintaining diversions if necessary

4) Obtaining the embankment materials including all lifts and

leads as specified under this item and laying in bank in layers,

tests and payment of Royalties, fees, octroi etc., if any. The cost

of testing of materials is included in the item of embankment.

5) Protecting and maintaining the bank.

6) Finishing the embankment

7) All labour materials, use of equipments, machinery, tools and

Page 181: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

plant necessary for completing the work satisfactorily.

Note :- Watering to OMC and compaction is not included in this item

and shall be paid separately, under relevant items.

2.11 Mode of Measurement and Payment : The quantities shall be

worked out by cross sectional measurements after watering and

consolidation using leveling instruments. The contract rate shall be per

cum of the finished bank-work, watered and compacted.

The measurement of the sections shall be limited to the dimensions

shown on the drawings or those ordered by the Engineers in Charge in

writing. The dimensions shall be recorded up to two decimals. The

sectional areas shall be worked out up to two decimals. The quantity

shall be worked out up to two decimals of a cum. by average area

method.

The volume of embankment thus calculated shall be reduced by 15%

for the purpose of payment when the measurements are taken for

running bills without watering and compaction and by 1% in final

measurements.

The final quantity to be paid for under this item shall be the total

quantity of embankment work reduced by 1 per cent. 13     Watering to OMC (16 kg to 24 kg of water per Cu.M.) The earth work in embankment in 20cm to 30 cm layers. (95% proctor density) Specification:

5.1 General : The item provides watering the layers of 20 to 30 cm of embankment laid.

5.2 Material and Equipment : Water to be used shall be free of harmful elements, which may

cause heavy efflorescence, etc. and approved by the Engineer-in-Charge. The contractor shall

make his own arrangements for getting adequate quantity of acceptable water. The water tankers

shall be used, without any additional payment.

5.3 Watering : When the murum of the 20 to 30 cm layer in embankment road contains less than

the optimum moisture, water shall be added to the material in the embankment layers of the road

to bring the moisture, uniformly up to requirement. If the material contains more than the required

moisture, it shall be allowed to dry until the moisture is reduced to the required extent. If due to wet

weather etc. the moisture contents of the soil cannot be reduced to the appropriate amount by

exposure, the compaction shall be suspended till suitable conditions prevail without contractor’s

claiming any compensation.

5.4 Item to Include : All material, equipment machinery labour, taxes etc. shall be included in the

rate.

5.5 Mode of Measurement and Payment : The measurement shall be taken on Cum. basis of the

embankment of the road watered. 14     Consolidation with proper ramming / rolling in layers the earth work in embankment . (95%

Page 182: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

proctor density) b) With vibratory roller in 45 to 60 cm layers Specification:

General : The item provides consolidation of the earthwork in

embankment in 20 to 30 cm layers for 8 to 10 tonnes roller and 40 to

50 cm layers for vibratory rollers. This item is to be executed after

laying the earthwork in embankment in the layers of 20 to 30 cm and

the layer is watered.

6.2 Equipment : The ramming rods and 8-10 tone ordinary or vibratory

roller as directed shall be used.

6.3 Consolidation : When a loose layer is leveled manually or

mechanically with camber provided and moistened or dried to a

uniform and required moisture content suitable for maximum

compaction, it shall be compacted by power rollers, vibratory rollers or

heavy hauling or dozing equipment to give the specified 95% of the

standard proctor density. If on testing, the density is found to be less

than 95% of the standard density the contractor shall do additional

compaction necessary to get the specified density after adding water if

required. When the specified density is imperative, the work shall be

removed and redone by the contractor at his own cost to give the

specified density.

Proper sequence of all component operations shall be maintained to

give individual progress.

For compaction of embankment the road roller shall move

longitudinally and rolling shall be done from edges to centre. The

camber shall be provided in the cutting and shall not be adjusted in

metalling.

Maharashtra Industrial Development Corporation

22

Care shall be taken for getting good compaction behind abutments,

returns and wing walls, etc.

Cutting/ Bank-work in areas not accessible to rollers such as those

adjoining bridges, culverts and other works, shall be carried out

independently of the main embankment and shall have the layers

placed in 10 cm to 15 cm. thickness and each layer shall be moistened

and thoroughly compacted with mechanical or manual tampers.

Embankment shall be brought up simultaneously in equal layers on

each side and compacted carefully to avoid unequal pressure, etc

The compaction of the embankment shall be done by moving road

roller longitudinally from edges to centre.

6.4 Item to Include : The item includes only the compaction of each layer

Page 183: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

by 8-10 tonne roller or vibratory roller. All labour and equipment

required to execute the item as per above specification shall be

included in the item. If specified vibratory compactors shall be used.

6.5 Mode of Measurement and Payment : The measurement shall be

taken of the earthwork for embankment of road in Cum. upto two

decimals. The contract rate shall be for a unit of One Cubic meter of

the finished bank work.

Page 184: TENDER FOR DG - CHIKHLI(G.C.) INDUSTRIAL AREAProviding LBM ...wms1.midcindia.org/seWMSUploadedfiles/DTP/1806/... · MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION 1 Short Tender Notice

Signed By

Organisation Unit

Signed Date

Sudhakar Radhuji Wagh

Government ofMaharashtra

21/08/2015

:

:

:

Page 90 Executive EngineerContractor