temporary or semi-permanent single core ...25th international conference on electricity distribution...

5
25 th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n° 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE CORE POWER CABLES: A NEW WAY TO SAFE AND RELIABLE YET FAST INSTALLATION Theo BRUIJNSE Jan DIKKEN Power Chain Solutions Power Chain Solutions – NL – NL [email protected] [email protected] ABSTRACT The subject addressed in this paper is the installation of single core power cables for temporary or semi-permanent connections in electrical grids. These connections are used more and more by (mainly) TSOs and DSOs worldwide during maintenance or repair work (e.g. after a power outage) In many cases the above cables are not installed appropriately. By carrying out a study on the subject as well as by questioning the parties involved more information about relevant aspects was gathered prior to the development of an all new purpose designed cable block: the ’temporary site cleat’. INTRODUCTION When it comes to the installation of single core power cables for temporary or semi-permanent connections in electrical grids various methods are being used. Depending on the situation the cables can, for example, be laid on the ground, in the ground or in an embankment, installed on a ladder or hooked up on a wall. Whichever method is used the safety in case of a short- circuit must always be guaranteed. Additional measures are required when cables are placed on the ground or above. The focus in this paper lies on the current practice and possible issues that go with the latter method (installation of the cables on or above the ground) followed by the introduction of a means to deal with those possible issues: the temporary site cleat. TEMPORARY INSTALLATION OF SINGLE CORE POWER CABLES Current practice The question is whether single core power cables for temporary or semi-permanent connections in electrical grids are usually installed correctly and SAFELY. In many cases the answer to this question is negative. Due to the character of the above-mentioned connections and/or the urgency of the installation work involved the applicable standards and regulations are often not or only partially met. It should also be noted that during installation easily obtainable but less suitable materials like (universal) single cable cleats together with pine beams (see Fig. 1) are frequently used. Fig. 1: Cable securing with single cleats & pine beam Moreover … a) Is a pine beam in the above configuration short- circuit proof (even at the highest possible short- circuit currents)? see: www.youtube.com/watch?v=A6B4Zm5Ie8U b) Do the fixings offer sufficient support in order to prevent the cables from being damaged (especially during a short-circuit)? c) Will a short installation time be feasible at all (with so many loose components)? d) Can an optimum spacing of the cables be ensured (beam by beam)? e) To what extend is the installation method sustainable (with limited or no reuse of materials)? Discussion @ a): In order to answer this question some insight into the electromagnetic forces (both magnitude and direction) on the conductors during a short circuit is helpful.

Upload: others

Post on 22-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TEMPORARY OR SEMI-PERMANENT SINGLE CORE ...25th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE

25th International Conference on Electricity Distribution Madrid, 3-6 June 2019

Paper n° 1528

CIRED 2019 1/5

TEMPORARY OR SEMI-PERMANENT SINGLE CORE POWER CABLES:A NEW WAY TO SAFE AND RELIABLE YET FAST INSTALLATION

Theo BRUIJNSE Jan DIKKENPower Chain Solutions Power Chain Solutions

– NL – [email protected] [email protected]

ABSTRACTThe subject addressed in this paper is the installation ofsingle core power cables for temporary or semi-permanentconnections in electrical grids. These connections are usedmore and more by (mainly) TSOs and DSOs worldwideduring maintenance or repair work (e.g. after a poweroutage)In many cases the above cables are not installedappropriately. By carrying out a study on the subject aswell as by questioning the parties involved moreinformation about relevant aspects was gathered prior tothe development of an all new purpose designed cableblock: the ’temporary site cleat’.

INTRODUCTIONWhen it comes to the installation of single core powercables for temporary or semi-permanent connections inelectrical grids various methods are being used.Depending on the situation the cables can, for example, belaid on the ground, in the ground or in an embankment,installed on a ladder or hooked up on a wall.Whichever method is used the safety in case of a short-circuit must always be guaranteed. Additional measuresare required when cables are placed on the ground orabove.The focus in this paper lies on the current practice andpossible issues that go with the latter method (installationof the cables on or above the ground) followed by theintroduction of a means to deal with those possible issues:the temporary site cleat.

TEMPORARY INSTALLATION OF SINGLECORE POWER CABLESCurrent practiceThe question is whether single core power cables fortemporary or semi-permanent connections in electricalgrids are usually installed correctly and SAFELY. In manycases the answer to this question is negative.Due to the character of the above-mentioned connectionsand/or the urgency of the installation work involved theapplicable standards and regulations are often not or onlypartially met.

It should also be noted that during installation easilyobtainable but less suitable materials like (universal)single cable cleats together with pine beams (see Fig. 1)are frequently used.

Fig. 1: Cable securing with single cleats & pine beam

Moreover …

a) Is a pine beam in the above configuration short-circuit proof (even at the highest possible short-circuit currents)? see:www.youtube.com/watch?v=A6B4Zm5Ie8U

b) Do the fixings offer sufficient support in order toprevent the cables from being damaged (especiallyduring a short-circuit)?

c) Will a short installation time be feasible at all (withso many loose components)?

d) Can an optimum spacing of the cables be ensured(beam by beam)?

e) To what extend is the installation method sustainable(with limited or no reuse of materials)?

Discussion@ a):In order to answer this question some insight into theelectromagnetic forces (both magnitude and direction) onthe conductors during a short circuit is helpful.

Page 2: TEMPORARY OR SEMI-PERMANENT SINGLE CORE ...25th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE

25th International Conference on Electricity Distribution Madrid, 3-6 June 2019

Paper n° 1528

CIRED 2019 2/5

To calculate the magnitude of the short-circuit forces onthe conductors of three single core cables in flat formation[1-3] the following formulas are applicable:

It appears that the forces on the outer conductors and themiddle conductor are not exactly the same (due to thedifferent relative positions of the cables to one another).The calculation example below for three single core powercables in flat formation shows that the short-circuit forcesshould not be underestimated:

maximal short-circuit current:isc = 40 kA rms 1 s => ip = κ∙√2∙isc = 1,8∙√2∙40 = 102 kA

centre to centre conductor distance: d = 120 mm = 0,12 m

To determine the direction of the short-circuit forces on theconductors the theory of the Lorentz force comes into play.It explains that this direction depends on the sign of thecurrent flow through the conductors: currents in samedirections attract whereas currents in opposite directionsrepel. For a 3 phase short-circuit Fig. 2 describes thedirection of the short-circuit forces on the conductors:perpendicular to and in the plane of the cables; theinteraction between any two phase conductors at variousinstants is given below the current-time graph.

maximal force on outer conductors: Fco = = = 14 kN/m

Fig. 2: Direction of the short-circuit forces on the conductors during a 3 phase short-circuit

Page 3: TEMPORARY OR SEMI-PERMANENT SINGLE CORE ...25th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE

25th International Conference on Electricity Distribution Madrid, 3-6 June 2019

Paper n° 1528

CIRED 2019 3/5

Although the forces are oscillating the cables will onlyfollow the first impulse caused by the peak value of theirrespective short-circuit currents. The inertia of the cables(easily 5 kg/m or more) simply prevents them from beingswapped around with a relative high frequency.

@ b):When single cable cleats are used it concerns mostly auniversal type for fixing various cables of differentdiameters (see Fig. 2). However, for single core cables thesupport of this type of cleat is not perfect.

Fig. 2: Single cable cleat / universal type

For a three-phase connection based on single core cablesin flat formation the universal single cable cleat is lesssuitable due to the limited side support in the case of ashort-circuit (as can be seen in Fig. 2). This will lead tohigh mechanical stress on the cable which may result inpossible damage. In particular EPR rubber insulated cablesare at risk although damage to cables with XLPE insulationcannot be ruled out either [4].A universal single cable cleat is ’range taking’ andtherefore designed to secure a range of cables with variousdiameters. In order to cope with this range the ’two-bowprinciple’ is used: the cable is clamped between two(circular) curved surfaces with a diameter equal to thelargest diameter of the range.For multicore cables a ’2-bow cable cleat’ has provenadequate (as long as the applied clamping force does notbecome too high in order to avoid excessive surfacepressures). This is due to the fact that possible three-phaseshort-circuit forces are absorbed within the cablesthemselves.The latter does not apply to single core cables however. Incase of three single core cables in flat formation accordingto Fig. 1 a possible short-circuit will result in short-circuitforces on the conductors perpendicular to and in the planeof the cables as discussed above. These forces are bestdealt with through cable cleats which offer maximumsupport in the same direction (see Fig. 3).In order to calculate the ’beam spacing’ (and hence thenumber of beams for a given length of cable) the maximumallowable surface pressure on the insulation - viaprojection of a conductor in the direction of itscorresponding (peak) short-circuit force - is normally oneof the determining factors (although often overlooked).

Fig. 3: Cable cleat with maximum support

@ c):To realize the configuration according to Fig. 1 some 20parts are needed (see Fig. 4).

Fig. 4: Single cleats, pine beam & fixing material

@ d):When workers are under stress of e.g. a power outage it isdifficult to maintain the optimum spacing beam after beam(see Fig. 5).

Fig. 5: Optimum spacing of single core cables in free air

Dg = conductor diameter

F = (peak) short-circuit force

B = width of the cable cleat

Page 4: TEMPORARY OR SEMI-PERMANENT SINGLE CORE ...25th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE

25th International Conference on Electricity Distribution Madrid, 3-6 June 2019

Paper n° 1528

CIRED 2019 4/5

@ e):With limited or no reuse of materials - as is often the casewith temporary connections - the installation of single corecables on pine beams is not very sustainable.

DEVELOPING A NEW SOLUTIONStudyBy carrying out a study on the subject as well as byquestioning the parties involved more information aboutrelevant aspects was gathered. The outcome of this studyserved as the basis for further development (see Table 1).After several prototypes a full-scale demo was built andsuccessfully tested in cooperation with one of the leadingDutch DSOs.

New solutionFinally an all-new purpose designed cable block will beintroduced:

the temporary site cleat …

CONCLUSIONSIn many cases single core power cables for temporary orsemi-permanent connections in electrical grids are notinstalled appropriately. Especially on and above theground additional measures are required for the cables tobe installed correctly and SAFELY. Easily obtainable butless suitable materials like (universal) single cable cleatstogether with pine beams are to be avoided. Without solidevidence to rule out the risk of the cables breaking looseor being damaged during a short-circuit and to be on theconservative side, utilities might consider the followingadaptation of their standard practice as: (a) whether toinclude a list of suitable materials for these specificconnections and (b) whether to include additionalrequirements for the way the cables should be installed(e.g. with regard to being short-circuit proof and themaximum cleat spacing) to cover for the above risks. Thetemporary site cleat will certainly contribute to the latter.

ACKNOWLEDGEMENTSThis paper has been written on the basis of an R&D projectand with input from, among others, the cable industry andvarious system operators in the EU. Without being specificthe authors would like to express gratitude to all partiesinvolved for their support.Thanks are given to Lou van der Sluis, professor emeritusin Electrical Power Systems, Delft University ofTechnology, the Netherlands, for reviewing this paper.

Table 1: What makes a good cable cleat?

Page 5: TEMPORARY OR SEMI-PERMANENT SINGLE CORE ...25th International Conference on Electricity Distribution Madrid, 3-6 June 2019 Paper n 1528 CIRED 2019 1/5 TEMPORARY OR SEMI-PERMANENT SINGLE

25th International Conference on Electricity Distribution Madrid, 3-6 June 2019

Paper n° 1528

CIRED 2019 5/5

REFERENCES[1] L. Heinhold, R. Stubbe, 1999, Kabel und Leitungen fürStarkstrom (5th edition), Publicis MCD Verlag, Erlangen,Germany, 387-405[2] IEC 60865-1, 2011-10, Short-circuit currents –Calculation of effects – Part 1: Definitions and calculationmethods (Edition 3.0), IEC, Geneva, Switzerland[3] IEC 61914, 2015-11, Cable cleats for electricalinstallations (Edition 2.0), IEC, Geneva, Switzerland[4] R. M. Eichhorn, 1981, “A critical comparison of XLPEand EPR for use as electrical insulation on undergroundpower cables”, IEEE Trans Elect. Insulation, vol. EI-6,472-475