Infor LN: v10.3 - v10.4 Miscellaneous Project EnhancementsRollout trainingCampus Course Code: 02_0021040_EEN0477_ELN
July 2014
Henk Otjens
2Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Topics• Cost and Service Items • Budget Adjustment addition• External Scheduling Interface additions• Optional pegging of project based warehouse orders• Multi-currency• New orders for Contracts• Cost Forecasting• Workflow for project cost• Cash Forecast (Financials)
3Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Topics covered in other presentations• Estimating
• Surcharges
• Requests for Quotation
• Cost Peg Audit History• Revenue Recognition• Contract Invoicing
4Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Cost and Service items• It was not possible to use items of type Cost and Service in:
• Estimating
• Budgeting
• Requirements Planning
• These type of items could be used as contract deliverables or as cost added in Procurement and costed to Project. So there could be costs while there was no budget. That made budget control difficult.
• We now allow these item types in the domains mentioned. The items will always be part of cost type Material but in Requirements Planning only for PRP Purchase Orders
• Note: Project specific Cost or Service items were and are not possible!
5Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Budget Adjustment• The Budget Adjustment is an option for change management but it was
possible to make changes to budget adjustments themselves.• We extend change management support by introducing:
• Final status (= Freeze)
• Last Modified Time and Login
6Copyright © 2014. Infor. All Rights Reserved. www.infor.com
External Scheduling Interface• Purpose:
• The Content, Quality and Performance of Interface to be extended
• Why?• To better make use of the scheduling options of external tools
• Relevant Changes:• Use of Calendar is optional at Export
• Introduce Calendar and Duration on Activity
• Improve Milestone Handling
• Allow link to lower levels of the activity structure
• Allow multiple projects to be imported/exported
• Made XML data more generic
7Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Calendar Export optional• Why?• Calendars are not always relevant and XML files will be smaller • While testing any issues in the calendar setup can be avoided• Note:
If on next export calendar is relevant after all than export should be Regenerate
8Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Calendar and Duration• It has been made possible to capture a calendar and the duration for the
leaf nodes of the activity structure• On higher levels the duration will be calculated• Advantages are that:
• Calendar can be part of export to external scheduling tool
• Duration can be part of export
• Both can be imported from external scheduling tool
• Note:For LN itself the calendar and duration is only informational as are the constraints
9Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Improve Milestone Handling• Allow Milestones on other levels of the activity structure than the top• For milestones dependent on activities (or other milestones) set Parent
Activity• Independent milestones still will be displayed on top of the Gantt
10Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Connection Node• Sometimes different parts of a project are handled by different
organizational elements• Therefore it is possible to link several external projects to one LN project• An option is available to select lower level of activity structure to be used
as top in the external scheduling package
11Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Example
• LN Project
• Multiple external projects
12Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Multiple Projects for Im-/Export• One-by-one import or export is very labor intensive• Therefore it is possible to select multiple projects that need to be exported
or imported• Selection stored for re-use
13Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Pegging and PRP Warehouse Order• In LN 10.3 for PRP Warehouse Orders pegging was only possible for
mandatory pegged items. Pegging the project cost can be useful for project warehouse orders that otherwise would not be pegged
• If an item is not pegged, an option is available on the PRP Warehouse Order to have the order pegged
• The Warehouse Order line, PIT and commitments will be created pegged or not, based on the Pegging flag (Y/N) on the PRP Warehouse Order
14Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Multi Currency• Purpose:
• Capability to use original rate when booked in a period where rate changes have occurred
• Procedure:• In case of multiple functional currencies have option for separate amounts/rates by
currency on:• Sundry Cost Entry
• Interim Results
• Note: This is only if the multiple functional currencies parameter is enabled as part of Companies (tcemm1170m000)
15Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Allow New orders for Contracts• More flexibility was requested on inactive contract lines• New Contract Parameters whether to allow new orders:
• While contract line is Free
• While contract deliverables have been shipped
• The first option allows to better handle situations in the startup phase• The second option allows to handle situations where additional items or
services need to be handled after the key contract deliverables have finalized
16Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Cost Forecast• The Cost Forecast sessions by Cost Object have been extended with
Approval option• The Global Approving session (tpppc4200m000) allows to approve the
Cost Forecast for a wider range selection of projects• Only Approved Cost Forecasts will be considered for
• Cost Control (Monitoring)
• Interim Results (Revenue Recognition)
• Program Cost Ledger (BI)
• Note: Existing customers should after migration to LN 10.4 approve existing cost forecasts
17Copyright © 2014. Infor. All Rights Reserved. www.infor.com
• Approval mechanism in LN is basic and not suited if multiple persons are involved
• ION Workflow has extensive capabilities
• Support on approval for:• Material
• Subcontracting
• Sundry Cost
• Interim Results
Additional ION Workflow Support
18Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Workflow Status of Document Interaction with ION
Infor LN Workflow ‘Authorization’
Draft(not effective)
Pending(not effective)
Approved(effective)
Rejected(not effective)
Submit
19Copyright © 2014. Infor. All Rights Reserved. www.infor.com
• Issue• Only Installments were considered
for the Cash Forecast in Financials
• More types considered like• Advances
• Deliverables
• Fees and Penalties
• Time & Materials / Cost Reimbursement
Cash Forecast (Financials)
20Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Miscellaneous Topics• Contract and Contract Line selection added• Options to create Project from Contract Line and Deliverable• The Bid option in Estimating has been added to the Customer 360• The Bids session has been reorganized• The Elements session has been restructured
• Editable Grid
• Multiple sessions revisited to merge tabs and eliminate clicks• Hide OBS options if Activity Types are not used• Hide Plan (as part of activity) if not in use
21Copyright © 2014. Infor. All Rights Reserved. www.infor.com
Topics• Cost and Service Items • Budget Adjustment addition• External Scheduling Interface additions• Optional pegging of project based warehouse orders• Multi Currency• New orders for Contracts• Cost Forecasting• Workflow for project cost• Cash Forecast (Financials)