technical assistance consultant’s reporteca economic consulting associates (uk) edelman edelman...
TRANSCRIPT
Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Project Number: 44004-012 December 2014
Socialist Republic of Viet Nam: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (Financed by the Technical Assistance Special Fund)
Prepared by PricewaterhouseCoopers Private Limited
Hyderabad, Telangana, India
For the National Power Transmission Corporation and the Asian Development Bank
Advisory-GRID-Energy
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) Final Report
3 December 2014
PricewaterhouseCoopers Private Limited, Plot no. 77/A, 8-624/A/1, 3rd Floor, Road No. 10, Banjara Hills, Hyderabad 500 034, T: +91 (40) 4424 6000, F: +91 (40) 4424 6300, www.pwc.com/in
Ms. Daniela Schmidt
Senior Project Officer (Energy)
Asian Development Bank
Units 701-706, Sun Red River Building
23 Phan Chu Trinh Street, Hanoi
Vietnam
3 December 2014
Our Reference: ADB/NPT-TCB/007
Your Reference: Consultant Services Contract No. 107364-S52267 dated 10 January 2014 for TA-7668 VIE:
Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building
(44004-012)
Dear Daniela
Subject: Submission of the Final Report
During Feb’14-Jul’14, we studied prevailing external and internal regulations/guidelines, understood
organisation structure and roles of various entities/departments, mapped current processes, reviewed
technologies/tools used and studied framework/status of information exchange among entities/departments.
We submitted the findings of our study in form of inception report (21 April 2014), revised inception report (21
May 2014) and mid-term report (21 June 2014). Subsequently, we conducted a workshop (2 July 2014) to
discuss the findings and potential recommendations in each module.
As agreed with ADB and EVNNPT, we have submitted the recommendation report (21 July 2014) covering:
1. Investment planning : 7 recommendations
2. Project management : 6 recommendations
3. Transmission pricing : 4 recommendations
4. Public relations : 7 recommendations
EVNNPT provided its comments and suggestions on recommendations in August 2014 which were discussed
with ADB and PwC on 10 September and 15 September 2014. Based on these discussions, EVNNPT accepted
most of the recommendations (except three) and agreed in principle to implement them. The Memorandum of
Understanding (MoU) signed between ADB and EVNNPT is enclosed at Appendix 7 -.
Subsequently, we submitted the Draft Final Report on 3 November 2014 covering following:
1. Part-A: Updated Mid-term Report;
2. Part-B: Recommendation Report; and
3. Part-C: Approach Notes / Proposals / Training Materials (in accordance with the recommendation
report).
Note: In addition, Appendices are common to all three parts.
We understand that ADB and NPT are fine with the Draft Final Report as we did not receive any comments /
suggestions until 30 November 2014. Hence, we have finalised the Draft Final Report as the Final Report.
We trust this is in line with your expectations.
Best wishes,
Charudatta Palekar
T: +91 (40) 4424 6000
F: +91 (40) 4424 6300
M: +91 986 613 8089 (India)
M: +84 164 302 6242 (Vietnam)
Disclaimer
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 4
Disclaimer
This document has been prepared solely for Asian Development Bank (ADB), being the express addressee to
this document. PwC does not accept or assume any liability, responsibility or duty of care for any use of or
reliance on this document by anyone, other than (i) ADB, to the extent agreed in the relevant contract for the
matter to which this document relates (if any), or (ii) as expressly agreed by PwC in writing in advance.
This publication (and any extract from it) may not be copied, paraphrased, reproduced, or distributed in any
manner or form, whether by photocopying, electronically, by internet, within another document or otherwise,
without the prior written permission of PwC. Further, any quotation, citation, or attribution of this publication,
or any extract from it, is strictly prohibited without PwC’s prior written permission.
© 2014 PricewaterhouseCoopers Private Limited. All rights reserved. In this document, “PwC” refers to
PricewaterhouseCoopers Private Limited (a limited liability company in India), which is a member firm of
PricewaterhouseCoopers International Limited (PwCIL), each member firm of which is a separate legal entity.
List of abbreviation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 5
List of abbreviation
Abbreviations
AD Administration Department
ADB Asian Development Bank
ASEC ASEAN Development and Management Consulting Limited
BIDV Bank for Investment and Development of Vietnam
BOOT Build, Own, Operate and Transfer
CAPEX Capital Expenditure
CBN Central Bank of Nigeria
CDTA Capacity Development Technical Assistance
CEO Chief Executive Officer
CERC Central Electricity Regulatory Commission
CIF Cost, Insurance and Freight
CLPC Commune Level Peoples Committee (Level 1 Administrative Unit)
CMD Construction Management Department
CPD Corporate Planning Department
CPMB Central Power Projects Management Board
CSR Corporate Social Responsibility
DBFOT Design, Build, Finance, Operate and Transfer
DGE Directorate General of Energy
DLA Draft Loan Agreement
DLPC District Level Peoples Committee (Level 2 Administrative Unit)
DoNRE Department of Natural Resources and Environment
DoP Delegation of Powers
DSCR Debt Service Coverage Ratio
DTD Detailed Technical Design
E&F Economic & Finance
E&S Environmental & Social
ECA Economic Consulting Associates (UK)
Edelman Edelman India Private Limited
EIAR Environmental Impact Assessment Report
EPTC Electric Power Trading Company
ERAV Electricity Regulatory Authority of Vietnam
ERP Enterprise Resource Planning
EVN Vietnam Electricity
EVNNPT / NPT
National Power Transmission Corporation
F&A Finance & Accounting
FIMS Financial Information Management System
FS Feasibility Study
GIS Gas Insulated Sub-station
GoV Government of Vietnam (The Socialist Republic of Vietnam)
HCMC Ho Chi Minh City
ICD International Cooperation Department
IMD Investment Management Department
INR Indian Rupee
IRR Internal Rate of Return
IT Information Technology
JICA Japan International Co-operation Agency
kV kilo Volt
List of abbreviation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 6
MoF Ministry of Finance (Government of Vietnam)
MoIT Ministry of Industry and Trade (Government of Vietnam)
MoJ Ministry of Justice (Government of Vietnam)
MoM Minutes of Meeting
MoNRE Ministry of Natural Resources and Environment (Government of Vietnam)
MPI Ministry of Planning and Investment (Government of Vietnam)
NGCP National Grid Company of Philippines
NLDC National Load Despatch Centre
NPMB Northern Power Projects Management Board
NPV Net Present Value
O&I Operation & Investment
O&M Operation & Maintenance
ODA Official Development Assistance
OFC Optical Fibre Cable
OICB Other International Commercial Banks
OPEX Operating Expenditure
PAP Project Affected Persons
PCC Power Construction Company
PhP Philippine Peso
PI Profitability Index
PLPC Provincial Level Peoples Committee (Level 3 Administrative Unit)
PMB Power Projects Management Board
PMB Projects Management Board
PPE Personal Protective Equipment
PPP Public Private Partnership
PR Public Relations
PTC Power Transmission Company (subsidiary of EVNNPT)
PTC1 Power Transmission Company No. 1 (subsidiary of EVNNPT having head office in Hanoi)
PTC2 Power Transmission Company No. 2 (subsidiary of EVNNPT having head office in Danang)
PTC3 Power Transmission Company No. 3 (subsidiary of EVNNPT having head office in Nha Trang)
PTC4 Power Transmission Company No. 4 (subsidiary of EVNNPT having head office in HCMC)
PwC PricewaterhouseCoopers Private Limited
R&M Repair and Maintenance
R&R Rehabilitation & Resettlement
RoE Return on Equity
RoW Right of Way
SBV State Bank of Vietnam
SEA Social Impact Assessment
SFR Self-Financing Ratio
SLC Subordinate Local Company
SMO System and Market Operator
SPMB Southern Power Projects Management Board
TA Technical Assistance
TC Transmission Charge
TNB Tenaga Nasional Berhad
TPTR Total Power Transmission Revenue
USD United States Dollar
VAS Vietnam Accounting Standards
VND Vietnamese Dong
VP Vice President
Document control information
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 7
Document control information
Authors:
Name of Expert
Produced by Charudatta P Palekar, Hitesh Chaniyara, Padam Prakash, Vivek Sengupta, Do Thi Minh Hien
Supported by Ravi Kiran Kuchi, Sai Dheeksha Charan, Sandeep Kumar Mohanty, Vu Thi Diu, Trinh Thu Hien, Smita Joshi, Anwesha Chatterjee, Smera Chawla
Verified by Kameswara Rao, Executive Director, PwC
Distribution List:
Recipient Title / Designation No. of hard copies
Asian Development Bank Ms. Daniela Schmidt, Senior Project Officer (Energy)
1
National Power Transmission Corporation
Mr. Vu Tran Nguyen, Vice President (Economics & Finance)
5
Executive summary
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 8
Executive summary
Context of the TA
Power consumption in Vietnam has increased nearly fivefold since 2000 as Vietnam underwent a period of
strong economic growth. During 2008-12, EVNNPT's line length grew at 8.2% p.a. and capacity of transformers
increased at 15.8% p.a. In such fast growing power sector, the role of the transmission system has expanded
beyond the role of simply linking generation to the load centres. With the growing complexity and size of
transmission system, it is imperative to have a strong investment planning, agile project management to
minimise time and cost overruns, proactive and bidirectional public relations and recovery of full cost of service
with adequate returns to invest in new projects. The overview of the Vietnam power sector is presented at
Appendix 1 -. The organization structure of EVNNPT and its subsidiaries is illustrates at Appendix 2 -.
In February 2014, ADB has appointed PwC (in association with Edelman India and ASEC Vietnam) to provide
technical assistance (TA 7668-VIE) to EVNNPT for targeted capacity building. The main objective of the TA is
to support EVNNPT in emerging into a modern transmission company that can meet the challenges of a
growing network. The TA has focussed on four key areas viz. investment planning, project management,
transmission pricing and public relations and examined current status, identified key issues, recommended
improvements and imparted trainings. Detailed work plans of TA experts are enclosed in Appendix 3 -.
Approach & methodology
When examining the four different focus areas, we have looked at five dimensions of the organisation viz.
strategy (regulations), structure, processes, people, and technology. We have adopted our proprietary approach
“TRANSFORM” to deliver this engagement. The four phases namely Assess, Design, Construct and Implement
fit the phasing requirements of the engagement.
We had commenced the engagement with a kick-off meeting on 24 February 2014. From February to June, TA
team had held more than 50 meetings with all departments in the corporate office of EVNNPT, relevant
departments of NPMB, CPMB, SPMB, PTC1, PTC2, PTC4, ERAV, ECA and PECC1. Based on interactions and
documents made available to us, we have studied prevailing external and internal regulations/guidelines,
understood organisation structure and roles of various entities/departments, mapped current processes,
assessed current staffing and their capabilities, reviewed technologies/tools used and studied framework/status
of information exchange among entities/departments. Our findings were discussed in the workshop held on 2
July 2014.
In July 2014, we submitted the Recommendation Report outlining agreed recommendations and
implementation requirements. Subsequently, these recommendations were discussed in details with EVNNPT
and ADB. Based on the discussions, ADB and EVNNPT signed a Memorandum of Understanding (MoU) to
undertake implementation of agreed recommendations within stipulated time. Since then, PwC has been
supporting EVNNPT in implementing these recommendations.
Analysis and outcome
During February-July 2014, the TA consultants have studied prevailing external and internal regulations/
guidelines, understood organization structure and roles of various entities/ departments, mapped current
processes, reviewed technologies/ tools used and studied framework/ status of information exchange among
entities/ departments. The TA consultants also carried out a perceptions audit to do a qualitative study of
perceptions about EVNNPT among stakeholders. The TA consultants have submitted the findings of their entire
Executive summary
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 9
study in the form of an inception report (21 April 2014), revised inception report (21 May 2014) and mid-term
report (21 June 2014). The TA consultants conducted workshop (2 July 2014) to discuss the findings and
potential recommendations.
As discussed and agreed with ADB and EVNNPT, the TA consultants have submitted the recommendation
report (21 July 2014) covering 24 recommendations:
Module Number of recommendations
Investment planning 7
Project management 6
Transmission pricing 4
Public relations 7
Total: 24
EVNNPT has provided its comments and suggestions on recommendations in August 2014 which were
discussed with ADB and TA consultants on 10 September and 15 September 2014.
Based on these discussions, EVNNPT has accepted most of the recommendations (except three) and agreed in
principle to implement them as described in the recommendation report. The Memorandum of Understanding
(MoU) has been signed between ADB and EVNNPT which captures description of recommendations, timelines,
responsibilities and implementation strategy. The document is enclosed at Appendix 7 -.
Subsequently, we submitted the Draft Final Report on 3 November 2014.
We understand that ADB and NPT are fine with the Draft Final Report as we did not receive any comments /
suggestions until 30 November 2014. Hence, we have finalised the Draft Final Report as the Final Report.
Summary of recommendations and current status
The recommendations identified in each focus area and their implementation status are summarized below:
Investment planning
Recommendation Deliverable Status
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#3: Strategy for risk management against foreign exchange variation
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#4: Prioritization of the investment projects
Report (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial
Project Model and Corporate Model (MS Excel); Note on Models (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Executive summary
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 10
Recommendation Deliverable Status
model
Recommendation#6: Develop alternate modes of project funding
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#7: Process improvement in the investment planning process
Report (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Project management
Recommendation Deliverable Status
Recommendation#1: Standardization of designs, specifications and layouts
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Approach Note (MS Word)
English version included in this report
Vietnamese version NOT to be submitted as agreed with ADB
Recommendation#3: Develop a project risk management strategy
Strategy Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement
Not Applicable No deliverable as agreed with ADB/NPT
Recommendation#5: Merger of FS & DTD phases
Approach Note (MS Word)
English version included in this report
Vietnamese version NOT to be submitted as agreed with ADB
Recommendation#6: Develop a strong and focused project management unit
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Transmission pricing
Recommendation Deliverable Status
Recommendation#1: Conduct training on principles of regulatory economics and international practices
Classroom Training and Training Material (MS Power Point)
Training conducted on 7 October 2014
English and Vietnamese versions of training material shared during the training session
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#2: Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations
Proposal (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#3: Develop and implement integrated transmission pricing model (TPM) for compilation of data and calculation of revenue & charge
Pricing Model (MS Excel)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#4: Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of
Procedure (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Executive summary
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 11
Recommendation Deliverable Status information needed for transmission pricing
Public relations
Recommendation Deliverable Status
Recommendation#1: Plan, set-up and operationalise a dedicated PR department within EVNNPT and its subsidiaries
Proposal (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#2: Develop a Crisis Communications Manual
Manual (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#3: Develop uniform key messages for EVNNPT through a workshop
Workshop and Key Messages (MS Word)
Workshop conducted on 15 October 2014
English version of workshop outcome note included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#4: Leverage the social media for EVNNPT’s PR work
Approach Note (MS Word)
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#5: Plan, set-up and operationalise a dedicated CSR department within EVNNPT
Proposal (MS Word)
English version included in this report
Vietnamese version NOT to be submitted as agreed with ADB
Recommendation#6: Impart training to EVNNPT spokespersons on media handling skills
Classroom training and Training material (MS Power Point)
Training conducted on 14 October 2014
English and Vietnamese versions of training material shared during the training session
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Recommendation#7: Conduct a workshop on the fundamentals of effective public relations
Workshop and Training material (MS Power Point)
Training conducted on 13 October 2014
English and Vietnamese versions of training material shared during the workshop
English version included in this report
Vietnamese version to be submitted by 5 November 2014
Table of Contents
Private and Confidential
Table of contents
Part-A: Updated Mid-term Report 19
Investment planning 20
Strategy 20
Structure 21
Processes 25
People 39
Technology 39
Summary of key observations 42
Project management 45
Strategy 45
Structure 47
Processes 50
People 65
Technology 65
Summary of key observations 66
Transmission pricing 69
Strategy 69
Structure 82
Processes 82
People 89
Technology 90
Summary of key observations 91
Public relations 98
Strategy 98
Structure 101
Processes 110
People 115
Technology 116
Analysis of perceptions audit 120
Summary of key observations 123
Part-B: Recommendation Report 128
Investment planning 129
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment
planning and revised delegation of powers 129
Recommendation#2: Utilisation of funds generated through accelerated depreciation 131
Table of Contents
Private and Confidential
Recommendation#3: Strategy for risk management against foreign exchange variation 133
Recommendation#4: Prioritization of the investment projects 135
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model 136
Recommendation#6: Develop alternate modes of project funding 138
Recommendation#7: Process improvement in the investment planning process 140
Project management 143
Recommendation#1: Standardization of designs, specifications and layouts 143
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts 145
Recommendation#3: Develop a project risk management strategy 148
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement 152
Recommendation#5: Merger of FS & DTD phases 154
Recommendation#6: Develop a strong and focused project management unit 156
Transmission pricing 158
Recommendation#1: Conduct training on principles of regulatory economics and international practices 158
Recommendation#2: Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations 159
Recommendation#3: Develop and implement integrated transmission pricing model (TPM) for compilation of data and calculation of revenue & charge 161
Recommendation#4: Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of information needed for transmission pricing 162
Public relations 165
Recommendation#1: Plan, set-up and operationalise a dedicated PR department within EVNNPT and its
subsidiaries 165
Recommendation#2: Develop a Crisis Communications Manual 167
Recommendation#3: Develop uniform key messages for EVNNPT through a workshop 169
Recommendation#4: Leverage the social media for EVNNPT’s PR work 170
Recommendation#5: Plan, set-up and operationalise a dedicated CSR department within EVNNPT 171
Recommendation#6: Impart training to EVNNPT spokespersons on media handling skills 173
Recommendation#7: Conduct a workshop on the fundamentals of effective public relations 174
Part-C: Approach Notes / Proposals / Training Materials (in accordance with the Recommendation Report)177
Part-C (i): Investment planning 178
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers 179
Overview 179
Key issues with existing delegation of powers 179
Select global practices 180
Suggested solution 182
Conclusion 184
Table of Contents
Private and Confidential
Recommendation#2: Utilisation of funds generated through accelerated depreciation 185
Overview 185
Select global practices 188
Possible solutions 190
Conclusion 193
Recommendation#3: Strategy for risk management against foreign exchange variation 194
Overview 194
Possible foreign exchange fluctuation hedging options 195
Select global practices 200
Recovery of hedging cost 201
Implementation challenges 202
Implementation road map 203
Conclusion 204
Recommendation#4: Prioritization of the investment projects 205
Overview 205
Existing practice 205
Key issues 206
Select global practices 208
Proposed framework for prioritization 211
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment
projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model 216
Project model & Corporate model 216
Description - Project model 216
Description - Corporate model 223
Recommendation#6: Develop alternate modes of project funding 228
Background 228
Alternate modes of financing 228
Recommendation#7: Process improvement in the investment planning process 242
Overview 242
Existing practice 242
Select global practices 244
Key issues based on the comparison with other transmission utilities 247
Proposed recommendations for the investment planning process 248
Conclusion 252
Part-C (ii): Project management 253
Recommendation#1: Standardization of designs, specifications and layouts 254
Table of Contents
Private and Confidential
Requirement of standardization of designs 254
Key aspects of standardization 255
Current status of standardization in EVNNPT 261
Approach for standardization of designs 261
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts 264
Drivers for Turnkey execution 264
Key aspects of turnkey contracts and separate supply and erection contracts 265
Part-turnkey 266
Pre-requisites of turnkey mode of execution 267
Framework for designing turnkey contracts 267
Key aspects in turnkey procurement 269
Recommendation#3: Develop a project risk management strategy 272
Project risk management 272
Risk response strategies 273
Organization framework 274
Risk management matrix for a transmission project 275
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement 279
Recommendation#5: Merger of FS & DTD phases 280
Drivers for the recommendation 280
Current process 280
Proposed process 281
Implementation support 282
Recommendation#6: Develop a strong and focused project management unit 287
Requirement of a Project Management Unit 287
PMU at PMB/PTC level 288
PMU at EVNNPT level 289
Part-C (iii): Transmission pricing 294
Recommendation#1: Conduct training on principles of regulatory economics and international practices 295
Summary 295
List of participants 295
Recommendation#2: Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations 296
Context 296
Issue#1: Inadequate Return on Equity 296
Issue#2: Depreciation charging methodology 300
Issue#3: Treatment of foreign exchange rate variation 303
Issue#4: Lack of proper cost norms 306
Table of Contents
Private and Confidential
Issue#5: True-up (adjustment) mechanism 309
Issue#6: Penalty framework for failed service quality 312
Issue#7: Structure of transmission charge 316
Issue#8: Transmission charge sharing mechanism 318
Issue#9: Impairment of regulatory independence 320
Recommendation#3: Develop and implement integrated transmission pricing model (TPM) for compilation of
data and calculation of revenue & charge 323
Recommendation#4: Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of information needed for transmission pricing 324
Context 324
Provision#1: Streamlining the process of data preparation, collection, compilation and validation 324
Provision#2: Designing standard formats for furnishing all the relevant data in MS Excel formats 328
Provision#3: Defining data reconciliation and dispute resolution procedure 330
Part-C (iv): Public relations 331
Recommendation#1: Plan, set-up and operationalise a dedicated PR department within EVNNPT and its subsidiaries 332
Context 332
Benefits of an independent PR department 333
Approach 334
Other prominent functions of an independent PR department 339
Model structure in Vietnam 340
Model structure in India 341
European Union Prescription 344
Indicative timelines 344
Recommendation#2: Develop a Crisis Communications Manual 345
Introduction 345
Strategy 345
Indicative timeline 349
Recommendation#3: Develop uniform key messages for EVNNPT through a workshop 350
Summary 350
List of participants 350
Introduction 351
Structure 351
Outcome and feedback 354
Slogans shared by EVNNPT 354
Recommendation#4: Leverage the social media for EVNNPT’s PR work 360
Context 360
Recommendations 360
Table of Contents
Private and Confidential
Strategy 361 Content Opportunities 362
Tactics 363
Indicative timeline 364
Recommendation#5: Plan, set-up and operationalise a dedicated CSR department within EVNNPT 365
Context 365
Benefits of a robust CSR programme 365
How EVNNPT can profit from organised CSR work at project sites 366
Approach 367
CSR Activities 369
Measurement of CSR Programme 369
Indicative timeline 369
Recommendation#6: Impart training to EVNNPT spokespersons on media handling skills 370
Summary 370
List of participants 370
Tips for dealing with the media 371
Ten Commandments of media interaction 372
Body Language Do’s 373
Body Language Don’ts 374
Outcome and feedback 374
Recommendation#7: Conduct a workshop on the fundamentals of effective public relations 376
Summary 376
List of participants 376
Exercise#1: EVNNPT's real press release (Task: To edit and comment) 378
Exercise#2: To prepare a communication plan for an EVNNPT project 379
Appendix 1 - Overview of Vietnam power sector 380
Industry structure 380
Demand-Supply scenario 382
Transmission & Distribution network 383
Retail tariffs 384
Power sector reforms & development of market structure 385
Overview of EVNNPT's performance and plan 385
Appendix 2 - Organisation structure of EVNNPT and its subsidiaries 387
Organisation structure - EVNNPT Head Office 387
Organisation structure - NPMB 389
Organisation structure - PTC1 390
Organisation structure - other PMBs and PTCs 392
Table of Contents
Private and Confidential
Appendix 3 - Work plans of TA Experts 393
Investment planning 393
Project management 394
Transmission pricing 395
Public relations 396
Appendix 4 - Questionnaires for perceptions audit 397
To EVN officials and public officials 397
To media 397
To affected people 397
Appendix 5 - Summary of laws / decisions / decrees / circulars 398
Relevant to investment planning 398
Relevant to project management 410
Relevant to transmission pricing 419
Relevant to public relations 428
Appendix 6 - Detailed process charts for investment planning 435
Process Chart 1: First stage approval 435
Process Chart 2: Approval of FS 436
Process Chart 3: Approval of DTD 438
Process Chart 4: Process for procuring loans from DCB 439
Process Chart 5: Process for procuring loans from OICB 440
Process Chart 6: Process for procuring loans from ODA 441
Appendix 7 - MoU signed between ADB and EVNNPT 445
Appendix 8 - Project level and corporate level financial model for EVNNPT (IP Reco#5) 454
Appendix 9 - Training on principles of regulatory economics and international practices (TP Reco#1) 455
Appendix 10 - Integrated transmission pricing model (TPM) (TP Reco#3) 456
Appendix 11 - Training to EVNNPT spokespersons on media handling skills (PR Reco#6) 457
Appendix 12 - Workshop on the fundamentals of effective public relations (PR Reco#7) 458
Appendix 13 - EVNNPT feedback on three workshops / trainings on public relations 459
Part-A: Updated Mid-term Report
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 19
Part-A: Updated Mid-term Report
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 20
Investment planning
Strategy
We have reviewed the relevant laws/decisions/decrees/regulations/ circulars for the Investment Planning
function (Brief provided in Appendix 5 -). The table below summarizes our observations on the relevant laws/
decisions/ degrees/ regulations/ circulars:
Particulars PwC analysis and observations
Decision No. 1368/QD-EVNNPT, 2013
The majority of the powers from selection of consultants, approval to feasibility report, detailed technical design and subsequent modifications; for investment value even below 1000 billion VND lies with the President & CEO of EVNNPT. The investments with ticket sizes above 1000 billion VND requires approval from Management Board of EVNNPT for key processes such as approval of selection of consultants, approval of feasibility report/ detailed technical design and approval of unexpected works.
There is practically no financial/ administrative powers provided to PTC/ PMB/ vice presidents of various departments in EVNNPT.
There needs to be some decentralization of authority to the departments of EVNNPT/PTCs/ PMBs especially for projects of small value and critical nature. The PTCs and PMBs are responsible for identification of investment needs and execution of capital projects. In absence of such delegation of powers, projects of smaller ticket size and critical nature may be delayed. Such a centralized delegation of powers also lead to higher transaction costs in case of smaller projects which may not be beneficial for the company.
Empowering PMB and PTC will also allow the departments under EVNNPT and the President & CEO (NPT) to focus on investments of higher value and strategic nature.
We have compared the delegation of the power in EVNNPT with the delegation of powers for one of the world’s largest transmission companies, i.e. Power Grid Corporation of India Limited (POWERGRID) in India. We observed that the delegation of powers is decentralised in POWERGRID for small projects for quicker implementation. Hence, there could be some level of decentralization of all approvals which can be handled by the PTCs/ PMBs.
Decision No. 445 issued in 1994
The Decision No. 445 issued in 1994 provides for the assumptions and methodology for preparation of financial model to carry out the economic analysis of the proposed investment projects.
The assumption and methodology provided in the circular are outdated and of little relevance considering the current industry structure of Vietnam power sector and market dynamics. The norms for the determination of transmission charges, depreciation, O&M expenses, transmission charges, etc. are not in line with the norms prescribed by ERAV and the figures provided in the audited financial statements.
The prescribed outputs of the financial model are not adequate to provide the proper evaluation of the investment proposals. The circular should be updated in accordance with the latest norms prescribed by ERAV and with the latest industry structure of the Vietnam power sector.
No regulation/ guideline for identification of funding source for a proposed project
There is no prescribed guideline/ regulation for identification of funding sources for a proposed project. In the existing framework, it is the responsibility of CPD in EVNNPT. The CPD identifies the funding sources for a proposed project in consultation of F&A department. We believe that there is no robust framework under which the funding sources are
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 21
Particulars PwC analysis and observations
identified/ allocated by the CPD.
While selecting the funding source, the CPD is not preparing any detailed financial model to analyse that which source is beneficial and is aligned to the overall future cash flows of EVNNPT in future.
There should be a regulation/ guideline to mandate a detailed corporate financial model to assess the impact of selection of funding sources for each project on the overall cash flow of the EVNNPT. It is important to have such a guideline/ framework considering the following facts:
o There is a significant mismatch in the depreciable life of assets (8-12 years) allowed by ERAV for the recovery of transmission charges and the repayment tenure of loan (25-30 years)
o No equity infusion by the equity shareholders to finance the self-funding requirement
o No return on equity allowed by ERAV to finance the investment projects, and
o There is no certainty in the existing regime that the upward revaluation of assets will be considered by ERAV for the determination of transmission charges.
In the above-mentioned scenario, the entire loan portfolio should be balanced with short term, medium term and long term repayment options. It should be worked out with the help of a detailed financial model/ tool considering various scenarios.
No regulation/ guideline for the utilisation of funds generated through the depreciation allowed by ERAV - diversion of funds for capital projects
At present, there is no governing regulation/ guideline for the utilisation of funds generated through the depreciation allowed by ERAV as a part of the transmission charges
In the absence of the regulation/ guideline, the fund generated through the deprecation allowed by ERAV is being used to fund the capital investment requirements
In the absence of the equity infusion by the shareholders and inadequate allowance of return on equity, the EVNNPT is investing the depreciation fund to meet the self-funding ratio. This fund should ideally be utilised to repay the loan amount
No regulation/ framework for risk management in respect of foreign exchange variation- huge cost associated with foreign currency funding for capital projects
A significant portion of the total capital investment requirement is being met the foreign currency funds, i.e., ODA loans or loan from other International Commercial Banks. On the other hand, there is no framework available with EVNNPT under which it can hedge its foreign currency risk for repayment of loan and payment of interest charges.
The total loss from allocated exchange rate differences (as on Dec’12) is around 2013 billion VND (96 million USD). It is a significant amount. There should be regulation/ framework which should provide for mandatory hedging against the foreign currency debt service obligations.
Structure
The existing investment planning process has significant oversight from EVNNPT Management Board, EVN
and MoIT. The investment planning process is a pan organization process within the EVNNPT and requires
inputs from a number of departments and the subsidiary companies - PTCs and PMBs.
There are four departments within EVNNPT that have a critical role in the entire investment planning process,
which includes:
Corporate Planning Department (CPD);
Investment Management Department (IMD);
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 22
Finance & Accounting Department (F&AD); and
International Cooperation Department (ICD).
In addition to the above mentioned departments of EVNNPT, other departments such as technical department,
procurement department, safety department and subsidiaries such as PMB and PTCs which are wholly owned
subsidiaries of EVNNPT, also have a critical role in the investment planning process.
The broad roles and responsibilities along with the organization structure of the four departments, PTC and
PMB from an investment planning perspective are summarized below.
Entity Department Officers involved Specific role in Investment Planning
NPT CPD Director (reporting to President & CEO, EVNNPT)
Deputy Directors
Experts
The CPD is responsible for overall transmission network planning based on inputs from the PTCs/ PMBs. It is responsible to provide inputs to the Master Plan and Five Year Transmission Plan. It also prepares the Annual Implementation Plan. It also identifies the sources of funds for various investment projects.
NPT F&A Chief Accountant (reporting to VP - Economics & Finance)
Deputy Directors
Experts
The role of the F&A department is to arrange funds for the approved projects based on the decision of the CPD in respect of identification of the sources of fund. The department is primarily responsible for the following activities in respect of investment planning function:
To raise funds for projects from pre-approved sources. However, in respect of the projects identified to be financed by the ODAs (such as ADB and World Bank)), it will work in association with ICD;
Representing EVNNPT as the signatory in loan agreements (domestic banks and international commercial banks such as HSBC);
Manage disbursement of funds; and
Repayments of loans and payment of interest
It is also responsible for the accounting of the expenses of the projects.
NPT IMD Director (reporting to VP (Operations & Investment)
Deputy Directors
Experts
The primary role of the department is to review the feasibility study reports and technical designs prepared by the external consultants in respect of the proposed investment projects.
The roles and responsibilities are divided into the following two parts:
Technical review of the proposed investment projects; and
Cost estimation & financial analysis of the proposed investment projects.
NPT ICD Director (reporting to President & CEO and three VPs)
Deputy Directors
Experts
The main function of ICD is to manage and oversee activities in respect of arranging funds from ODA- multilateral or bilateral funding sources. The department works in coordination of the F&A department to discharge its functions pertaining to procurement of ODA loans.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 23
Entity Department Officers involved Specific role in Investment Planning It is also responsible for international cooperation and managing and developing the foreign relations of EVNNPT.
NPT Technical Department
Director (reporting to VP Operations & Investment)
Director (Technical)
Deputy Director
Experts
The Technical Department is responsible for conducting technical studies (load flow, short circuit, stability etc.) and reviewing investment proposal from O&M point of view.
PMB Planning Department
Experts directly reporting to Director (PMB)
The role of planning department of PMB in investment planning process includes:
Providing inputs to CPD for the preparation of Master Plan and Five year Transmission Plan
Developing annual implementation plan; and
Providing support to ICD in form of preparation of necessary documentation for procuring funds from ODAs.
PMB F&A Experts directly reporting to Director (PMB)
The broad roles and responsibilities of F&A department of PMB is as under:
To carry out the disbursement function in coordination with the F&A department of the EVNNPT
Making payments to vendors and contractors (within stipulated limits); and
Accounting of the project related expenses.
PMB Evaluation Department
Experts directly reporting to Director (PMB)
The Evaluation Department of PMB is responsible for the following:
Preparation of the Feasibility Study (FS) for the proposed investment projects in compliance with all related regulations / guidelines from a technical and financial perspective so as to ensure that the project gets approval of the management. However, the FS is actually prepared by the external consultant hired by PMB; and
Submitting projects to EVNNPT for approval and onwards submission to MoIT.
The table below summarizes our observations on the existing structure:
Observation PwC analysis and observations
CPD is responsible
for identifying the
funding sources for
capital projects
while F&A
department is
responsible for
raising funds from
domestic
commercial banks
or international
Identification of funding sources for capital projects is the responsibility of the
CPD in EVNNPT while the actual fund raising is coordinated by F&A department
(or ICD with help of F&A in case of ODA funds). Both the activities have a lot of
commonalities.
F&A Department is directly involved in fund raising activities and has better
market intelligence. The department also has better visibility on the overall
financial health of the company and may be in a better position to decide the
optimum funding source for the company.
In most of the transmission companies in developing/ developed countries, the
F&A department is responsible for identification of sources of funds since this
department in most cases is better equipped for the job.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 24
Observation PwC analysis and observations
commercial banks.
Segregation of the
functions of F&A
department on the
basis of finance and
accounting activities
At present, the functions of F&A department are segregated on the basis of works
relating to projects (based on the source of funds) and operations.
In the existing structure, the Deputy Director#1 is responsible for the finance and
accounting activities for investment and construction of the projects funded by
the domestic source of funds and the Deputy Director#2 is responsible for the
finance and accounting activities for the operations irrespective of the source of
funds and for the investment and construction of the projects funded by ODAs.
The finance and accounting functions while in many countries/ companies are
regarded as similar functions but in reality they varied.
The roles & responsibility of F&A department should be on the basis of the three
broad functions of the department - finance, accounts and budget. The finance
function should primarily include economists and management graduates, the
accounting functions should have qualified accountants and the budgeting
function should ideally include mix of chartered accountants and cost
accountants.
F&A reports to the
VP (Finance and
Economics) which
also manages the
material handling
department
The finance and accounts is regarded as the critical non-core function in a
transmission company (core activities are investments and operations).
Experience in similar developing countries such as India, Nigeria, etc. indicates
F&A should have a separate reporting structure which should be independent of
non-related activities such as material handling.
In EVNNPT, the responsibility of the VP (Finance & Economics) is more critical
considering the following fact:
o NPT is in the transition phase;
o There is a shortage of fund to invest in the capital projects; and
o The ERAV is not allowing adequate return on equity to fund the
equity portion of the capital requirements.
Considering the importance of the finance and accounting functions in the
EVNNPT, the VP (Finance and Economics) should not be burdened with any
additional responsibility such as material handling department. In fact material
handling department has more similarity to areas such as investments/ projects
rather than F&A.
However, we will carry out a detailed study to analyse the work load on the Vice
President (Finance and Economics) with regard to functions related to material
handling department.
De-centralisation of
the key tasks/
activities such as
development of the
feasibility study and
detailed technical
design
The IMD, CMD, technical department, etc. are not directly involved in the
preparation of feasibility study and detailed technical design of the projects.
These departments are only responsible for reviewing, monitoring and issuance
of guidelines, establishing standards and design standards, etc. However, the
primary responsibility of preparation of feasibility study and detailed technical
design is with the respective PMBs and PTCs.
In other words, there is no centralised dedicated team to prepare the feasibility
study and detailed technical design of the capital projects. There are separate
teams located at each PMBs/PTCs. The centralised dedicated team would have
assisted the EVNNPT to reduce the efforts and duplicity of the man power.
We compared it with the process followed by POWERGRID in India. We
observed that the preparation of feasibility report / detailed project report
including cost estimates and project investment proposal for each and every
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 25
Observation PwC analysis and observations
investment project are centralised at the corporate levels. The feasibility report
and detailed project report for the proposed transmission scheme consists of all
descriptions, technical details and cost estimation are prepared by the Cost
Engineering Department of POWERGRID at head quarter. The detailed
investment proposal is prepared by Corporate Planning Department of
POWERGRID, head quartered at the corporate office.
Processes
The investment planning process can be defined as the process of identification of capital projects, designing
the project structure, securing investment approval and tie up of resources (importantly financial resources).
The investment planning process is a crucial activity in a capital intensive industry such as power transmission.
The financial and human resource available would be limited and hence a transparent investment planning
process ensures selection of viable, critical and priority projects.
The investment planning process in EVNNPT can be divided into three stages:
Planning stage;
Approval stage; and
Funds identification and tie-up stage.
The exhibit below shows the macro level view of the investment planning process:
Planning stage
The planning process is the stage in which the projects are identified and a first level of approval is secured to
reflect that the projects are planned.
•Planned Investment (A) - Investment part of the Master Plan and Transmission Plan
•Unplanned Investment (B) - Investments based on critical need and not part of the macro plan
Planning
•All Investment (C) - All investments identified have to be approved for implementation
Approval
•Domestic Funding (D) - Funding from Domestic Banks
•International COmmercial Banks (E) - Funcing from OICB (US$)
•International Commercial Banks (F) - Funding from ODA (US$)
Identification& tie-up of funds
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 26
We observed that the entire framework of long term investment planning in EVNNPT is based on four levels of
plans. Our understanding of the planning process in given below:
The process for planning of an individual project will depend on the fact that whether the project is included in
the Annual Implementation Plan or not. The processes under each case are briefed below:
Projects included in the Annual Implementation Plan: Typically, the projects included in the
Annual Implementation Plan are related to long term planned investments to evacuate power from
upcoming power generation capacities, system strengthening to cater to growing demand and network
improvements to enhance quality and reliability of the supply. The entire planning process is described
below:
Master Plan
•It is a 10 years plan for the entire power sector. It is prepared by Institute of Energy (IE) and Directorate Generate of Energy (DGE) - both entities subordinated to MoIT. The Master Plan prepared by IE & DGE is reviewed by MoIT. The MoIT submits the draft Master Plan to Prime Master for approval. It is finally approved by Prime Minister.
• . The IE and DGE hold workshops to take inputs and discuss the master plan with various stakeholders including EVNNPT
Five year transmission plan
•It is an operation and business development plan for EVNNPT and forms part of the five year plan of EVN. It covers a period of 5 years
•The five year plan is based on 10 years master plan. This five year plan is for the entire EVN. It also covers the five year plan for the transmission sector prepared by EVNNPT and generation plan prepared by the generation corporations. The distribution sector is also covered at high level (total investment value but no list of projects). It is approved by MoIT
Five year rolling investment plan
•The five year plan will not change for the next 5 years but a five year rolling transmission investment plan is prepared by EVNNPT every year.
•The five year rolling transmission investment plan is a grid investment plan with a view to the next four years - the current year with four year perspective. This is to support the MoIT for monitoring of grid.
•It is approved by MoIT
Annual implementation
plan
•Apart from the five year rolling transmission investment plan, the EVNNPT also prepares an annual implementation plan.
•The five year rolling transmission investment plan is based on 10 years master plan, whereas the Annual Implementation Plan based on the capacity of the subsidiaries and departments.
•The annual implementation plan does not go to MoIT for approval. It is approved by the EVN.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 27
Projects not included in Annual Implementation Plan: On the other hand, critical projects
related to system strengthening and augmentation to the existing network to address network
overloading/ congestion issues/ voltage problems/ system inadequacy are projects not included in the
Annual Implementation Plan. These projects are identified on need basis by PTCs who are responsible
for operations of transmission infrastructure. The detailed planning process for the projects not
included in the Annual Implementation Plan is shown in Appendix 6 -. The summary of the process is
given below:
NPT
DGE[Preparation of 10 years Master Plan]
CPD [Preparation of five year transmission plan
]
EVN[Approval of five year transmission plan]
MOIT[Approval of five year transmission plan]
(1) President & CEO (NPT) (2) Management Board (NPT)
[Approval of five year transmission plan]
EVN[Preparation of rolling five year transmission
plan]
(1) President & CEO (NPT) (2) Management Board (NPT)
[Approval of rolling five year transmission plan]
MOIT[Approval of rolling five year transmission plan]
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 28
The above mentioned process is known as “first stage approval” in the EVNNPT. At present, the first stage
approval of the proposed investment is required for each project irrespective of the size and nature of the
project. It is pertinent to mention that the first stage approval is also accorded for the projects which are
included in the Annual Implementation Plan.
Approval and funds identification & tie-up stage
The stages in the process of approval and funds identification & tie for the investment proposals are
summarised in the table given below:
Stages Approval process
First stage
approval
The first stage approval of the proposed investment is required for each project
irrespective of the size and nature of the project. It is pertinent to mention that the
first stage approval is also required for the projects which are included in the
Annual Implementation Plan.
It requires the approval of MoIT.
Approval of
feasibility study
(FS)
The FS is prepared by the PMBs/ PTCs (as the case may be) and submitted to the
IMD in EVNNPT for review. The IMD will review the FS with inputs from a variety
of departments in EVNNPT such as CPD, Technical department, safety
department, IT department and F&A department. The FS comprises of the
technical studies, impact assessment studies and financial and economic analysis.
NPT
PTC [Identification of proposed investment and preparation of Investment Proposal and
submission to IMD (NPT)
IMD[Validation and review of Investment
Proposal by IMD based on inputs from Technical Department]
President & CEO (NPT) [Approval of Investment Proposal]
Management Board (NPT)[Approval of Investment Proposal]
VP (Operations & Investments)[Approval of Investment Proposal]
MOIT[Approval of Investment Proposal]
3 levels of approval
within NPT
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 29
Stages Approval process
After the review, the FS is submitted to President & CEO and Management
Board for review and approval
In case the project cost is more than 1,500 billion VND or the project is to be
funded by the ODAs, the approval of MoIT will be required
Approval of
detailed
technical design
Once the FS is approved by MoIT/ Management Board (NPT)/ President & CEO
(NPT), as the case may be, the detailed technical design (DTD) is prepared by an
external consultant (typically could be same consultant involved in preparation of
feasibility study).
The DTD is prepared with the inputs from all the relevant departments of PMB
and is submitted to IMD for the seeking approval from competent authority.
The DTD is submitted to the President & CEO and Management Board for review
and further submission to MoIT for the approval.
The MoIT review the DTD through an independent external consultant appointed
by it.
Fund
identification
and tie up of
funds
In case of funding from Other International Commercial Banks (OICB) and Official
Development Assistance (ODA), the funding proposal will go to MoIT, Ministry of
Finance, and Ministry of Justice for approval.
First stage approval
It has been already discussed in the previous section.
Approval of Feasibility Study (FS)
Generally, PTCs / PMBs hire an external consultant to prepare the Feasibility Study (FS) report. The feasibility
study typically includes the following components:
Technical studies:
o Line route survey,
o Load flow studies (system calculations),
o Basic design (PMB/PTC use standard designs and specifications prepared and approved by
EVNNPT),
o Fire prevention aspects,
o Telecommunication aspects, and
o Technical issues
Impact assessment studies:
o Environment Impact Assessment, and
o Social Impact Assessment and Resettlement (generally, consultant, with the help of PMB, goes
to commune to investigate social issues such as potential impact on land owners. This study is
done to minimise land needs and adverse impact on local people.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 30
Financial and economic:
o Financial analysis such as NPV, IRR, Benefit-to-Cost ratio
o Total investment cost
The detailed process for the approval of FS is provided as Appendix 6 -. The summary of the process is shown
below:
Approval of Detailed Technical Design (DTD)
Once the Feasibility Study (FS) report is approved by MoIT/ Management Board (NPT)/ President & CEO
(NPT), as the case may be, the Detailed Technical Design (DTD) is prepared by an external consultant, typically
could be same consultant involved in preparation of feasibility study. The DTD is prepared with the inputs from
all relevant departments of PMB and is submitted to IMD under the EVNNPT, for the approval from competent
authority. The DTD is also reviewed by the independent external consultant appointed by the MoIT in the
process of approval.
The detailed process for the approval of the DTD is provided in Appendix 6 -. The summary of the process is
provided below:
NPT
PTC /PPMB[Preparation of Feasibility Study (FS)
report]
IMD[Detailed review by IMD – technical
review, cost estimates, financial analysis with support from other departments]
Management Board[FS Approval]
President & CEO (NPT)[FS Approval]
MOIT[FS Approval]
If project cost > 800 billion VND and < 1500 billion VND and funding via domestic banks/ oversees commercial banks.
If project cost < 800 billion VND and project is funded using debt from domestic banks
If project cost > 1500 billion VND or the project is funded via Oversees Development Banks
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 31
Funds identification and tie-up stage
Currently there are three broad sources of funding the projects in EVNNPT: funding from ODAs, funding from
domestic commercial banks (DCB) and funding from other international commercial banks (OICB) such as
HSBC and Standard Chartered (commercial banks with head offices outside Vietnam and raise funds/ lend in
dollar currency).
In each case the process is varied and follows a different approval process. In case of funds raised from DCB and
OICB, the F&A department (NPT) is the nodal agency responsible for the entire process. However in case ODA
loans which are sovereign loans taken by EVNNPT, the Ministry of Finance (MoF) and Ministry of Planning and
Investment (MPI) are responsible for coordinating all activities at the Ministerial level related to ODA fund
raising. The activities at the company level are coordinated by ICD.
Domestic commercial banks (DCB)
The overall process is coordinated by the F&A Department (NPT). It acts as the representative of EVNNPT with
the domestic commercial banks. The identification of sources of funds for individual projects is however led by
CPD in consultation with the F&A Department (NPT). The detailed process for procuring loans from DCB is
provided in Appendix 6 -. The summary of the process is provided below:
NPT
PTC /PPMB[Preparation of Detailed Technical
Design (DTD)]
IMD[Detailed review of DTD by IMD with
support from other departments]
Management Board[DTD Approval]
President & CEO (NPT)[DTD Approval]
MOIT[Reviews DTD through an independent
consultant and provides approval]
IMD[Issues the Implementation Decision to
PTC/ PPMB]
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 32
Other International Commercial Banks (OICB)
The overall process for procurement of fund from OICB is coordinated by the F&A Department (NPT) who
would act as the representative of EVNNPT before the OICB. The identification of sources of funds for
individual project is however led by CPD in consultation with the F&A Department (NPT).
The difference, compared to the process followed in case of domestic commercial banks, is that in case of OICB,
the Ministries of the Government of Vietnam are also involved in the entire process since the loans requires
Government guarantee. The detailed process for procuring loans from OICB is provided in Appendix 6 -. The
summary of the process is provided below:
NPT
CPD[Identification of sources of funds by CPD
in consultation with F&A department]
F&A[Invites offers from various domestic
commercial banks and negotiates]
Management Board[Loan approval]
President & CEO (NPT)[Loan approval]
PTC/ PPMB[Withdrawal of funds by Implementing
agency]
If project cost > 500 billion VND
If loan < 500 billion VND
F&A[Invites offers from various domestic
commercial banks and negotiates]
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 33
Official Development Assistance (ODA)
The Prime Minister has the authority to approve the list of the projects to be funded with the ODA funds. The
primary responsibility of mobilization of ODA funds across sectors is with Ministry of Planning and Investment
in coordination with other Ministries such as Ministry of Finance.
All ODA loans are provided to the Government of Vietnam which is further extended on a mark-up on the
interest rate of EVNNPT. The detailed process for procuring loans from ODA is provided in Appendix 6 -. The
summary of the process is provided below:
NPTCPD
[Identification of sources of funds by CPD in consultation with F&A department]
F&A[Invites offers from various OICBs and
negotiates]
EVN[Loan approval]
Management Board[Submit the loan proposal to EVN for
approval]
OICB[Prepares the draft loan agreement and
submit to MOIT for approval]
F&A[Execution of loan agreement with OICB]
MOIT, MOF and MOJ[Negotiate the loan offer with OICB]
MOF[Issue of Government Guarantee]
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 34
Select global practices
We have studied the planning and investment approval processes in the following two transmission companies
- One of the world’s largest transmission company -POWERGRID in India, and ElectraNet, one of the
Transmission Network Service Providers (TNSPs) in Australia]. Total 8 TNSPs are there in Australia.
At this stage we have analysed the entire investment planning process in two stages:
Planning phase; and
Detailed Design and Implementation Approval Phase.
POWERGRID (India) - Planning phase
There are three stages during the planning process:
NPT
ICD[It discusses with the ODAs to finalise
terms & conditions for project selection]
CPD[It identifies the projects based on the
finalised terms & conditions and submits to President & CEO and Management Board]
ICD[It prepare the Project Outline (PO) and
submits to President & CEO and Management Board]
MOIT[Forwards the PO to MOF, MOFA, MOJ &
SBV for approval]
The Prime Minister[After approval of MOF, MOFA, MOJ, SBV & MPI, it is submitted to Prime Minister]
EVN[Reviews and submits the PO to MOIT]
ICD[It prepares the project documents]
The President[After approval of the Prime Minster, it is
approved by the President of Vietnam]
MOIT & Other Ministries[It is submitted for approval to MOIT, MPI,
MOF, MOJ]
The Prime Minister[Negotiation Team formed by the PM comprises of MOIT, MOF & SBV to
negotiate jointly with ODA]
EVN[NPT submits to EVN for approval]
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 35
Any non-planned activities which are necessary for transmission capacity addition or system strengthening are
included in the network plan on a rolling basis (with quarterly revisions, if needed) as per the latest data
available for the major inputs to the plan.
The MoP is involved only at one point as mentioned above. The decision of the EC is finally approved by the
MoP. It is pertinent to mention that the approval of MoIT (counterpart to MOP in India) is required for four
times in the entire planning and approval process.
POWERGRID (India) - Detailed design and implementation approval phase
There are four stages in this phase:
Advance preliminary expense: After the project is being allocated to POWERGRID by the EC, the
first step is approval of advance expenses to be spent at the project site. It is estimated by the corporate
planning department of POWERGRID. These expenses are approved as per the delegation of powers
and are primarily to be used in various preparatory activities (viz. surveys, soil investigation, wind
National Electricity Plan
•It is prepared by the Central Electricity Authority establised by the Ministry of Power (MoP) •The National Electricity Plan is prepared for a short-term framework of five years while
giving a 15 year perspective •The National Electricity Plan is prepared by CEA in two volumes namely, Generation
(Volume I) and Transmission (Volume II). •It is prepared on the basis of the year-wise forecasts of electricity demand for each state,
union territory, region and all India in detail for a period of 15 years
Network Plan
•It is prepared by the POWERGRID and is divided into two parts- technical plan and commercial plan
•The technical plan is approved by the Regional Standing Committees for Power System Planning (SCPSP), consisting of CEA, POWERGRID, State Transmission Utilities (STUs) of the constituent States, Regional Power Committee (RPC) of the concerned region and representatives of generating companies in the region.
•The commercial plan (broad level cost estimates) is approved by the RPCs consisting of generating companies, POWERGRID, STUs, distribution utilities, and State Load Dispatch Centres (SLDCs) of the particular region
Review by EC for selection of project to
implement via competitive bidding
route
•An Empowered Committee (EC) has been constituted by the MoP, with representatives from the MoP, CERC, planning commission, POWERGRID, CEA and two (2) experts from the field of power sector nominated by MoP.
•The EC, based on the network plan, identifies key projects to be implemented under competitive bidding route (through private player participation). The remaining projects are awarded to POWERGRID on nomination basis.
•The decisions of the EC are then approved by the Ministry of Power (MoP)
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 36
analysis, rainfall data, local statutory and environmental clearances etc.) for the preparation of detailed
project report (DPR).
Preparation of feasibility report (FR)/ detailed project report (DPR) including cost
estimates: The DPR for the proposed transmission scheme consisting of all descriptions, technical
details and cost estimation is prepared by the cost engineering department of POWERGRID. The DPR
is prepared in coordination with other departments of POWERGRID like corporate planning, finance,
contracts & procurement, and engineering etc. in a time-period of around 8-10 weeks. In case the
estimated project cost is more than 10 billion INR (167 million USD / 3540 billion VND), POWERGRID
is required to take the technical approval for such project from CEA. The DPR is approved by either
Chairman (projects of value less than 50 million INR / 0.83 million USD) or by Board of Directors
(projects of value more than 50 million INR / 0.83 million USD / 17.6 billion VND) or by Board of
Directors (projects of value more than 50 million INR / 0.83 million USD / 17.6 billion VND). However,
the approval from CEA is required in case the project cost is more than 10 billion INR / 167 million
USD / 3540 billion VND).
Preparation of project investment proposal: Based on the detailed cost estimates in the DPR,
the corporate planning department of POWERGRID prepares the detailed investment proposal. In case
the estimated project cost is more than 10 billion INR (167 million USD / 3540 billion VND), third-
party agency is appointed by the POWERGRID for the financial appraisal of the project. The
preparation of investment proposal takes around 1 month. The investment proposal is sent to the Board
of Directors for approval.
Project financing: The capital structure for any project (debt equity ratio) is a part of the DPR.
However, the sources of financing for any particular transmission scheme/project are not defined on a
project-specific basis in POWERGRID. Based on the planned transmission schemes, ongoing works
and milestones achieved, a financing proposal on company-wide basis is prepared by the corporate
planning department.
ElectraNet (Australia) - Planning phase
The planning in ElectraNet in Australia is summarised below:
Annual implementation plan- The annual plan is the finalised list of annual investments approved by AEMO based on the five year plan submitted by TNSP
Five year plan -Each TNSP prepares a five year plan based on load forecast/generation plans/ inputs from TNDP and public consultations.
Transmission Network Development Plan (TNDP) -Australian Energy Market Operator (AEMO) prepares the 20 years TNDP to serve as guiding document for Transmission
Network Service Providers (TNSP)
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 37
ElectraNet (Australia) - Detailed design and implementation approval phase
Based on the comparison with POWERGRID (India) and ElectraNet (Australia), the table below summarizes
our observations on the investment planning process of EVNNPT:
Observation PwC analysis and observations
No approval for
annual
implementation
plan by MoIT
The annual implementation plan is prepared by the CPD in EVNNPT keeping
in view the availability of resources and capabilities of the subsidiaries and
departments of EVNNPT.
It is submitted to the President & CEO and management board of EVNNPT for
approval. The management board issues as resolution in this regard. After the
approval of management board, the annual implementation plan is submitted
to EVN for approval
The annual implementation plan does not go to MoIT for approval. As the
annual implementation plan is not approved by the MoIT, all the projects-
planned (forming part of the annual implementation plan) or non-planned
investment (not forming part of the annual implementation plan) are
submitted to the MoIT for the first stage approval
We analysed the planning process of the Indian transmission sector and
observed that once the project is allocated to POWERGRID by EC, there is no
requirement for going back to the MoP for the approval of each and every
individual projects. However, the approval of CEA (under the Ministry of
Power) is required in case the project cost is more than 167 million USD /
3540 billion VND.
Centralised
approval with MoIT
for first stage
approval
The first stage approval is simply an approval of the investment proposal
before the preparation of FS. Under the current process of approvals, there is
no distinction between critical projects and non-critical projects and projects
with smaller/ larger ticket size.
There could be some level of decentralization of the approvals for an
investment proposal which can be delegated to the EVNNPT. Such projects
could be critical in nature and of smaller ticket size.
In the entire
investment Each project will go to MoIT for approval for at least three times (four times in
Identification and tie up of funds- The commercial services department is responsible for identification and raising of funds for the proposed investment
Project assessment conclusion report- Finally collating all the discussions and consultations, the asset management department prepares project assessment conclusion report. It is submitted for
regulatory approval
Project assessment draft report- The asset management department summarizes comments, conducts economic viability analysis and submits it again for public consultation.
Project specific consultation report- The asset management department prepares the project specification consultation report and send it for public comments
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 38
Observation PwC analysis and observations
planning process,
the approval of
MoIT is required
for at least three/
four (in case of
ODA/ OICB funded
projects) times.
case of ODA/ OICB funded projects) during the entire planning process.
The multiple rounds of approval while ensures greater oversight but may lead
to significant delays in implementing critical projects.
On the other hand, if compared with Indian transmission planning process, we
observed that there is no role of the MoP in the approval of individual projects.
Once the project is allocated to POWERGRID, there is no direct role of the
MoP in the planning process. All the approvals in respect of the feasibility
study, detailed project report, financing tie up are to be provided internally by
the authorities in the POWERGRID. However, the approval of CEA is required
in case the project cost is more than 167 million USD / 3540 billion VND.
DTD is reviewed by
the external
consultant on
behalf of MoIT in
all cases
irrespective of the
size and
importance of
project.
MoIT appoints an independent consultant to review the DTD which is
submitted to MoIT by EVN.
The entire process from hiring an external consultant, review and submission
of report is time consuming and is associated with costs and efforts. This level
of detailed review process may be required in case of technically complex
investment programme or projects of higher ticket size.
In case of smaller projects which are standard system strengthening /
replacement projects, hiring an external consultant may not be the efficient /
cost effective measure.
At the planning
stage, no
prioritization of
projects is done
based on financial
parameters
There is no tool/ system/ process/ regulation in place based on which the
decision in respect of prioritization of projects can be made. All projects which
are technically feasible are considered to be eligible for the implementation.
Considering the limited funds/ budgets in EVNNPT, the prioritization is
essential to determine which projects have to be immediately implemented
and which projects can be delayed.
The financial evaluation framework for selection of project should be more
robust. A more effective framework for cost benefit analysis should be
introduced.
Based on the various discussions held with various stakeholders, we observed
that the commercials of the projects are not discussed at the planning stage.
The cost estimation is determined at the time of approval of FS. On the other
hand, in the Indian transmission planning, the commercials (broad level
project cost) are also determined and approved at the time of the approval of
network plan.
In Australia, there is a well-established framework - RIT Test which ensures
selection of efficient projects.
In case of fund
raising from OICB,
MOF, MoIT and
MOJ are involved
for each and every
project
In case of borrowing from OICB, the involvement of so many ministries such
as MoF, MoIT and MoJ for each and every project may lead to delays in the
execution of the critical projects.
We also observed that no funding proposal has been rejected by MoF, MoIT
and MoJ in the recent past. Therefore, the process for involving the MoF,
MoIT and MoJ can be restricted to only high value projects. For the low value
projects a procedure similar to raising funds from domestic banks may be
adopted. However, broad level guidelines for OICB loan may be notified by the
MoF, MoIT and MoJ in respect of hedging against the foreign currency
variation.
Lack of self-
funding for the
The depreciation period is lower than the loan repayment period as elaborated
in the earlier point. This allows some surplus revenue for EVNNPT initially
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 39
Observation PwC analysis and observations
proposed
investments and
innovative options
for meeting the
self-funding
requirements
due to the difference in accelerated depreciation and loan repayment.
EVNNPT currently is forced to utilize this surplus to fund its equity
contribution in capital expenditure due the following reasons:
- No equity infusion by the equity shareholders
- No adequate return on equity is allowed in the tariff order to
generate retained earning which can be used for self-financing
- No possibilities to raise fresh equity from capital markets to fund
its investment
Such a practice may be dangerous in long run. It’s against the basic finance
principles. It may lead to debt trap situation in future.
There is no innovative self-financing options being explored such as sweat
equity, PPP on Design, Build, Finance, Operate and Transfer (DBFOT),
Build Own Operate Transfer (BOOT), etc.
People
Some of our observations pertaining to people issues during the discussions with various departments are
summarised below.
Shortage of staff across various departments in EVNNPT: In various discussions, we observed that
there is a shortage in staff across multiple departments. However, the shortage in manpower can only
be estimated if we can get the inputs on department wise strength and expected number to perform the
job optimally.
No clerical staff: We observed that the departments in EVNNPT are not supported by the clerical staff.
Our experience in similar organizations (where information technology penetration is limited) indicates
that especially in case of F&A department where data and transactions are huge, clerical staff can be
leveraged. However the experience and qualification of such clerical staff needs to be carefully outlined
so that they are tech-savvy.
Technology
The EVNNPT currently does not use any integrated technological systems such as Enterprise Resource
Planning (ERP). The EVNNPT have an in house IT team to support the requirements of the organization as and
when required. The various departments and subsidiaries under EVNNPT use standalone IT packages and tools
(most of them locally developed) to meet their requirements. Some of the tools and packages being used during
the investment planning process are summarized in the table below:
Key software tools / MS Excel models / system used:
Name of software tools / MS Excel models / system
Brief description / features / functionalities
PwC analysis and observations
PSSE (Siemens) The tool is used to simulate the network and conduct load flow, short circuit and stability studies
Standalone system used by the technical
department of EVNNPT
Tool seems to be adequate for the current
requirements
MS Excel based
model
The models used to assess the financial and economic
Tool is currently used by IMD
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 40
Name of software tools / MS Excel models / system
Brief description / features / functionalities
PwC analysis and observations
feasibility of the proposed investments are outdated and computing only few key parameters.
The tool is not adequate and needs
significant improvement to correctly assess
the financial and economic feasibility of the
project (our detailed observations are
provided in the later part of the section.
E-office tool Tracking and managing investment process The tool provides the timelines for each activity or approval, across various levels and is capable of track the location of the document pending for approval.
Tool is currently used by IMD
The table below summarizes some of our observations pertaining to technology/ tools issues during the
discussions with various departments.
Areas PwC analysis and observations
ICD lacks a tool to
monitor the progress
of the capital
projects
ICD is dealing with all the foreign banks and ODAs for arranging funds for the
capital expenditure. It needs to submit the progress updates to the banks
related to the projects funded by them but it does not have any tool or
mechanism or database to effectively monitor the progress of the capital
projects executed by PMBs/ PTCs.
Due to this, ICD spends significant time in preparing various reports and
tracking the project status based on manual inputs from various departments.
The ICD should have a system like ERP to expedite their functioning.
No robust tool for
financial and
economic appraisal
of projects
The financial model being used by EVNNPT for the financial and economic
appraisals of projects is outdated. It is not adequate to evaluate an investment
proposal on all the economic and financial parameters. The model calculates
some key financial metrics such as NPV and IRR but is not flexible to offer a
variety of views for different stakeholders.
We have reviewed the financial model in detail and provided our comments in
the later part of the section.
No integrated
investment
management and
appraisal system
At present, there is no integrated investment management and appraisal
system in place. Such a system would enhance the efficiency, lead to a lower
lead time, greater transparency and accountability.
In absence of an integrated investment management and appraisal system,
the adherence of each and every circular/decree/decision which has an impact
on the investment planning process needs to be externally monitored. In an IT
enabled tool, such conditions can be programmed in so that no deviations are
possible.
An integrated investment management and appraisal system will reduce such
manual inputs/ efforts from the department. Such a tool is often accompanied
with MIS view which reduces effort on report writing.
No tool for assisting
CPD/ F&A in
In the existing framework, it is the responsibility of CPD in EVNNPT to
identify the funding source for the projects. The CPD identifies the funding
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 41
Areas PwC analysis and observations
identification of the
funding source for
the projects
sources for a proposed project in consultation of F&A department. While
selecting the funding source, the CPD is not preparing any detailed financial
model/ tool to analyse that which source is beneficial and is aligned to the
overall future cash flows of EVNNPT in future.
There should be a detailed corporate financial model to assess the impact of
selection of funding sources for each project on the overall cash flow of the
EVNNPT. The entire loan portfolio should be balanced with short term,
medium term and long term repayment options. It should be worked out with
the help of a detailed financial model/ tool considering various scenarios.
As mentioned above, we have reviewed the financial model, which is being used by EVNNPT to carry out the
financial and economic appraisals of the investment projects. Our observations in respect of the financial model
are given below:
Particulars PwC analysis and observations
Revenue
projections
In the financial model, the transmission projects are evaluated on the financial
and economical parameters. For the projection of revenue stream of a
transmission project, the financial model has considered the purchase and sale
of power, which is not relevant for a transmission project in the current industry
structure.
It should have considered the transmission charges determined by ERAV for the
projection of revenue. The reason explained by the Power Engineering
Construction Company (PECC), a consultant of EVNNPT (who prepared the
financial model) was that they are following the Decision No. 445, which is quite
old and at that point in time, the business was not segregated into generation,
transmission and distribution segment. After the Decision No. 445, no
additional circular was issued in this regard. Therefore, the method followed by
PECC is based on the Decision No. 445.
There is need to update the Decision No. 445 and revise the financial model for
evaluating the investment proposals
Assumption for
determination of
transmission
charges
In respect of determination of transmission charges, the consultant has
considered that 20-25% of the retail electricity price (REP) will be the
transmission charges. In the current situation, the transmission charges are
quite low in compare to the percentage assumed in the financial model. At
present, the ERAV provides a separate tariff for transmission business, which
should be considered as a part of revenue assumption for the financial model
In this regard, the consultant explained that as per the Decision No. 445, the
generation tariff is required to be assumed as 50% of the retail electricity price
(REP), transmission charges as 20-25% of the REP and distribution charges as
30-25% of the REP. It is completely irrelevant in the current context.
Transmission loss In the financial model, the transmission loss is considered to be 0.3%, which is
quite low in compare to the actual transmission loss, i.e., 2.59%. The output of
the financial model will not provide a true and fair view.
O&M expenses The O&M expenses projected in the financial model is based on the percentage
prescribed in the Decision No. 445, which is not line with the norms prescribed
by ERAV for the determination of the transmission charges and also with the
actual O&M expenses.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 42
Particulars PwC analysis and observations
Depreciation The rate of depreciation is different from the rates used in the financial
statement and prescribed by ERAV for the determination of the transmission
charges. The output of the financial model will not provide a true and fair view.
No equity
component
In the financial model, the equity component or self-funding ratio is considered
to be zero. It will provide incorrect IRR and NPV.
Discounting rate The discounting rate used in the financial model is not the weighted average
cost of capital. The discounting rate is 8.1% based on the Decision No. 445. The
output of the financial model will not provide a true and fair view.
Summary of key observations
In the following section, we have summarised our key preliminary observations identified till date:
1. Centralised governance structure: The existing delegation of powers provides a highly centralised
governance structure. The majority of the powers for selection of consultants, approval of feasibility
study report, technical design and subsequent modifications lie with the President & CEO and the
Management Board of the EVNNPT. There are practically no financial/administrative powers provided
to PTC/ PMB/ departments in EVNNPT.
2. Outdated circulars: The Decision No. 445 issued in 1994 provides for the assumptions and
methodology for preparation of financial model to carry out the economic analysis of the proposed
investment projects. The assumption and methodology provided in the circular are outdated and of no
relevance considering the current structure of Vietnam power sector. The norms for the determination
of transmission charges, depreciation, O&M expenses, etc. are not in line with the norms prescribed by
ERAV and figures available in the audited financial statements.
3. Lack of appropriate policy framework/ regulations/ guidelines: We observed that there is a
lack of the policy framework/ regulations/ guidelines in respect of the following:
a. No regulation/ guideline for identification of funding source for a proposed project - There is
not regulation/ guideline to mandate a detailed corporate financial model to assess the impact
of selection of funding sources for each project on the overall cash flow of the EVNNPT. It is
important to have such a guideline/ framework considering the following facts:
i. There is a significant mismatch in the depreciable life of assets (8-12 years) allowed by
ERAV for the recovery of transmission charges and the repayment tenure of loan (25-
30 years)
ii. No equity infusion by the equity shareholders to finance the self- funding requirement
iii. No return on equity allowed by ERAV to finance the investment projects
iv. There is no certainty in the existing regime that the upward revaluation of assets will be
considered by ERAV for the determination of transmission charges and
v. In the above-mentioned scenario, the entire loan portfolio should be balanced with
short term, medium term and long term repayment options. It should be worked out
with the help of a detailed financial model/ tool considering various scenarios.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 43
b. No regulation/ guideline for the utilisation of funds generated through the depreciation allowed
by ERAV - In the absence of the regulation/ guideline, the fund generated through the
deprecation allowed by ERAV is being used to fund the capital investment requirements. This
fund should ideally be utilised to repay the loan amount.
c. No regulation/ policy framework for risk management in respect of foreign exchange variation-
A significant portion of the total capital investment requirement is being met the foreign
currency funds, which is open to foreign currency variation risk. On the other hand, there is no
framework available with EVNNPT under which it can hedge its foreign currency risk for
repayment of loan and payment of interest charges.
4. Functional structure of F&A department: At present, the functions of F&A department are
segregated on the basis of works relating to projects (based on the source of funds) and operations. The
finance and accounting functions while in many countries/ companies are regarded as similar functions
but are actually very varied. The roles & responsibility of F&A department should be on the basis of the
broad functions- finance/budgeting and accounting.
5. De-centralisation of the key tasks/ activities such as development of the feasibility study
and detailed technical design: There is no centralised dedicated team to prepare the feasibility
study and detailed technical design of the capital projects. There are separate teams located at each
PMBs/ PTCs. The centralised dedicated team would have assisted the EVNNPT to reduce the efforts
and duplicity of the man power.
6. Long investment planning process due to multiple approvals: There is a requirement for
rationalisation of the process in respect of investment planning due to the following reasons:
a. No approval for annual implementation plan by MoIT - Since the annual
implementation plan is not approved by the MoIT, all the projects are submitted to the MoIT
for the first stage approval. We analysed the planning process of the Indian transmission sector
and observed that once the project is allocated to POWERGRID, there is no requirement for
going back to the MoP for the approval of each and every individual projects.
b. Centralised approval with MoIT for first stage approval - The first stage approval is
basically an approval of the investment proposal before the preparation of FS. Under the
current process of approvals, all the investment proposals require the approval the MoIT. There
could be some level of decentralization of the approvals for an investment proposal which can
be delegated to the EVNNPT.
c. In the entire investment planning process, the approval of MoIT is required for at
least three/ four (in case of ODA/ OICB funded projects) times - Each project will go
to MoIT for approval for at least three times (four times in case of ODA/ OICB funded projects)
during the entire planning process. The multiple rounds of approval while ensures greater
oversight but may lead to significant delays in implementing critical projects. On the other
hand, if compared with Indian transmission planning process, we observed that there is no role
of MoP in the approval of individual projects. Once the project is allocated to POWERGRID,
there is no direct role of the MoP in the planning process. All the approvals in respect of the
feasibility study, detailed project report, financing tie up are to be provided internally by the
authorities in the POWERGRID.
d. DTD is reviewed by the external consultant on behalf of MoIT in all cases
irrespective of the size and importance of project - The entire process from hiring an
external consultant, review and submission of report is time consuming and is associated with
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 44
costs and efforts. This level of detailed review process may be required in case of technically
complex investment programme or projects of higher ticket size. In case of smaller projects
which are standard system strengthening / replacement projects, hiring an external consultant
may not be the efficient / cost effective measure.
e. In case of fund raising from OICB, MOF, MoIT and MOJ are involved for each and
every project - In case of borrowing from OICB, the involvement of so many ministries such
as MoF, MoIT and MoJ for each and every project may lead to delays in the execution of the
critical projects.
7. No prioritization of projects: There is no tool/ system/ process/ regulation in place based on which
the decision in respect of prioritization of projects can be made. All projects which are technically
feasible are considered to be eligible for the implementation. However, with limited funds/ budget,
prioritization is essential to determine which projects have to be immediately implemented and which
projects can be delayed.
8. Lack of self-funding for the proposed investments and innovative options for meeting the
self-funding requirements: There is no innovative self-financing options being explored such as
sweat equity, PPP on Design, Build, Finance, Operate and Transfer (DBFOT), Build Own Operate
Transfer (BOOT), etc. in EVNNPT. It is currently forced to utilize this surplus to fund its equity
contribution in capital expenditure. Such a practice may be dangerous in long run. It's against the basic
finance principles. It may lead to debt trap situation in future.
9. No robust tool for financial and economic appraisal of projects: The financial model being
used by EVNNPT for the financial and economic appraisals of projects is outdated. It is not adequate to
evaluate an investment proposal on all the economic and financial parameters. The model calculates
some key financial metrics such as NPV and IRR but is not flexible to offer a variety of views for
different stakeholders.
10. No integrated investment management and appraisal system: At present, there are no
integrated investment management and appraisal system in place. Such a system would enhance the
efficiency, lead to a lower lead time, greater transparency and accountability. In absence of an
integrated investment management and appraisal system, the adherence of each and every
circular/decree/decision which has an impact on the investment planning process needs to be
externally monitored. In an IT enabled tool, such conditions can be programmed in so that no
deviations are possible.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 45
Project management
Strategy
Key decrees
We have reviewed decrees relevant to project management. (Brief provided in Appendix 5 -). There is no change
in our understanding regarding the three Decrees, viz. Decree No. 12/2009/ND-CP, Decree No. 69/2008/ND-
CP and Decree No. 15/2013/ND-CP (Summary repeated for reference).
Regulation Summary
Decree No. 12/2009/ND-CP Applicable to all construction activities in infrastructure sectors
Details about various categories of infrastructure projects depending
on nature, size, source of funding etc. and mentions roles,
responsibilities and authorities of different “investment deciders” in
various stages of projects including formulation, funding, evaluation
and approval of feasibility studies, techno-economic studies,
monitoring of implementation.
Decree No. 69/2009/ND-CP Regulations on land use planning, land recovery, compensation,
support and resettlement, land prices, land allocation and lease, land
use rights and ownership of houses and other assets attached to land,
and land use duration extension
Decree No. 15/2013/ND-CP Regulations on quality management of construction works in survey,
design, construction execution and acceptance of construction works;
on safety management, handling of incidents during construction
execution, exploitation and use of construction works; and on
warranty of construction works
We have mentioned that the Decree No. 106/2005/ND-CP and Amendment Decree No. 81/2009/ND-CP have
expired on 15 April 2014. This is being replaced by Decree No. 14/2014/ND-CP. However, a brief comparison of
changes in both the decrees is provided below:
Regulation Summary
Decree No. 106/2005/ND-
CP and Amendment Decree
No. 81/2009/ND-CP
Safety corridors of transmission lines, electric field intensity limits,
safe distances and other clearances defined which are applicable for
both construction and operation phases
Different types of compensation and resettlement supports for trees,
fields, land inside safety corridors for different voltage levels defined
Replaced by Decree No. 14/2014/ND-CP
Decree No. 14/2014/ND-CP No change in majority of clearances and electric field intensity limits.
Certain clearances added to bring in more detail, e.g.: Safe distance
for electric discharge at 110 kV as 4 meters, Time period for fast
growing trees mentioned as 3 months etc.
There is more emphasis on safety aspects with articles on employee
training, frequency, contents etc. Also, responsibilities of different
ministries viz. Industry &trade, Science & technology, Construction in
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 46
Regulation Summary
terms of safety are detailed.
Better structured compensation clauses. One addition is that the
compensation/support for perennial crop land, production forest land
in a transmission line’s safety corridor is entitled to maximum 30% of
level of compensation for similar land acquisition
We have also reviewed the Law on bidding- Law No. 43/2013/QH13 dated 26 November 2013 has come into
effect recently (1 July’2014). It elaborates on all relevant aspects of procurement process- to provide advisory
services, non-advisory services, goods, construction and installation for investment projects of state-owned
enterprises. The law elaborated different types of bidding methods & processes, scheduled time lines for key
activities, eligibility criteria, selection process, types of contracts, responsibilities of various stakeholders etc.
The scheduled timelines, key activities, bidding methods and processes are in line with general international
practices.
New Land Law and changes in land acquisition
There are no major procedural changes in the process of land recovery (acquisition) in the old and new land law
(effective from 1 July 2014). However, some key differences that can have an impact on power transmission
projects are highlighted below:
Parameter New Land Law Old Land Law along
with relevant decrees
New Land database and
Information system
Articles 120 to 124 talk of land information
system, development and management of a
national land data base, online services and
identifies responsibilities of different ministries
in these tasks. When implemented, this will
help in a structured land recovery process
which benefits all stakeholders.
No such articles
Planning of land use 17 articles of Chapter 4 dedicated to different
aspects of master plan for 10 years and its
dependent annual plans- formulation, time
periods, responsibility of different authorities,
consultancy services for formulation, appraisal
of plans, adjustment of plans, publicity etc.
Land use planning is
mentioned in the law and
detailed in Decree No
69/2009/ND-CP there is
no master plan concept in
the old law.
Land pricing &
Compensation for land
recovery
Article 113 mandates Government to develop
Land price for every 5 years for different
regions, land types and amend them in case of
more than 20% fluctuation in market price
Article 74(2) mentions compensation will be
decided by Provincial People’s Committee at
the time of the recovery decision
Depending on the land
price brackets of Decree
188/2004/ND-CP,
amendment Decree 123/
2007 /ND-CP. Provincial
People’s committees have
power to provide
variation up to 20% on
both maximum &
minimum prices
Compensation for non-
agricultural land, with a
long remaining use
Entitled to higher compensation as per article
80(1) which states that in case equivalent land
cannot be provided, the land users shall be
Equal compensation for
all cases irrespective of
remaining land use term
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 47
Parameter New Land Law Old Land Law along
with relevant decrees
period at the time of the
recovery
compensated with money calculated based on
remaining land use term. Government is yet to
provide a detailed decree.
in the current regime
Time limit to pay
compensation
Article 93 (1) mentions compensation to be
paid once & directly to land owners within 30
days of land recovery.
No time limit mentioned
in either Law or decrees
Investors fail to use land
for 12 consecutive
months post allocation
Article 64 (i) provides extension of land use
term for another 24 months if investors pay the
total land use levy or land rental for the delayed
period. In case of further delay (except force
majeure cases), the land will be recovered by
the state
There is no provision of
extension for additional
24 months.
Also, the Government is yet to provide decrees for implementation provisions of various articles of the New
Land Law.
We understand that the land acquisition process along with subsequent R&R activities, designing compensation
plan etc. are time consuming. Many organizations are present and interactions between various departments
are increasing total time required for land acquisition. Although, it is required that entire site/ corridor
clearance should be obtained before start of construction; it is not being put in practice because of long time
required to get site clearance for all tower locations of a given line. We have requested for scheduled and actual
timelines for a sample transmission line and substation packages to understand the quantum of delay and
reasons thereof. We are yet to receive this information which will help us understand current practices for
project planning and monitoring. We made a visit to other PMBs and PTCs and have incorporated the
additional inputs in this report.
Structure
The key departments involved in the project management function and their respective roles are mentioned in
below.
Entity Department Officers involved Specific role in project management
NPT CPD Director (reporting to
President & CEO,
EVNNPT)
Deputy Directors
Experts
Obtains approval of FS consultants selected in
bidding process from appropriate authority
Review of fund requirement for a project and
provide inputs for FS approval
Approves detailed technical design (DTD)
consultants selected in bidding process
Approval of Procurement plan
Progress reporting to authorities as required
NPT CMD Director (reporting to
VP - Construction)
Deputy Directors
Experts
Obtains approval of EIAR from DoNRE
Approval of Project implementation plan
Progress reporting to authorities as required
Issues warnings to contractor when their
performance is affected by delays
Conducts adhoc site testing & inspection
NPT IMD Director (reporting to Co-ordinates with all relevant departments for
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 48
Entity Department Officers involved Specific role in project management
VP - Operations &
Investment)
Deputy Directors
Experts
tracking the project progress throughout its life
cycle
Obtains first stage approval from MoIT for PTC
projects
Maintains all contracts
Obtain FS approval from competent authority
Progress reporting to authorities as required
NPT International
Cooperation
Department
Director (reports to
President & CEO and
three VPs)
Deputy Directors
Experts
Progress monitoring and reporting to ODAs for
ODA funded projects
NPT F&A Chief Accountant
reporting to VP(E&F)
Deputy Directors
Experts
Processing of invoices of different consultants
and contractors as and when required
NPT Technical
Department Director (reporting to
VP Operations &
Investment)
Director (Technical)
Deputy Director
(Investment &
System calculation)
Experts
Review and approval of DTD
NPT Procurement
Department
Director (reports to
President & CEO)
Deputy Directors
Experts
Obtain Approval of procurement plan, bidding
documents from competent authority
PMB Materials
Department
Deputy Director
(reports to Director
PMB)
Experts
Review equipment drawings, designs with
support from Technical Department
Signs contracts for procurement of materials
from domestic and international vendors
Gives the sign-off to F&A Department of PMB
on payment processing of equipment suppliers
PMB Planning
Department
Experts directly
reporting to Director
(PMB)
Receipt of project allocation letter from IMD
(NPT) and intimates Procurement department
for consultant for preliminary cost estimation
Preparation of procurement plan (in
consultation with technical department,
procurement department, materials
department, resettlement department, etc.)
Signing contracts for civil works and
procurement of consulting/design services from
consultants
Support in processing of bills of contractors /
vendors
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 49
Entity Department Officers involved Specific role in project management
Consolidation of all weekly progress reports
received from various contractors/vendors
Support to technical department in project
progress monitoring
PMB Technical
Department
Deputy Director
(reports to Director
PMB)
Experts
Prepare Project Implementation Plan (PIP)
Monitor quality with regular testing and
inspection
Review of construction drawings, designs
Monthly progress monitoring against PIP
Impose penalty on contractors repeatedly
failing to meet schedules/ performance
standards
PMB F&A
Department
Experts directly
reporting to Director
(PMB)
Process payment of contractors / vendors and
either pay directly to contractor (if amount <
100 billion VND) or forward payment document
to F&A Department of EVNNPT
PMB Evaluation
Department
Experts directly
reporting to Director
(PMB)
Reviews Feasibility Study prepared by FS
consultants (in consultation with relevant
department and sometimes with help of other
consultants) and sends to IMD (NPT) for
approval (Second stage approval)
Reviews detailed technical design prepared by
DTD consultants (in consultation with relevant
department and sometimes with help of other
consultants) and sends to IMD (NPT) for
approval
PMB Procurement
Department
Experts directly
reporting to Director
(PMB)
Selection of consultant for preliminary cost
estimation on nomination basis (single source)
Selection of FS & DTD consultants, supply &
erection contractors through competitive
bidding process
Provide inputs in preparation of Procurement
Plan
Review of bidding documents prepared by DTD
consultants and submit to EVNNPT for
approval
Conduct bidding process (NIT, pre-bid, bid
receipt, evaluation etc.) with support from other
departments when required
Contract negotiations with support of Technical
Department
PMB Resettlement
Department
Deputy Director
(reports to Director
PMB)
Experts
In-charge of assigning the site clearances / land
acquisition - ensuring that the clear site is made
available to the contractor
Addressing resettlement issues
Processing compensations and making
payments
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 50
Entity Department Officers involved Specific role in project management
Responsible for construction coordination with
local authority to ensure the resettlement
happens
PTC Materials
Department
Deputy Director
(reports to Director
PTC)
Experts
Plan requirements of augmentation/ repair of
failed equipment and compile list of material
and equipment needed
Manage, supply equipment and material,
transfer, dispose equipment and material
PTC Planning
Department
Not Available Develops plan on construction investment
Involved in bid evaluation process
Lead in negotiation, and signing contracts
Monitors implementation progress of projects
PTC Technical
Department Deputy Director
(reports to Director
PTC)
Experts
Monitor, direct and inspect working status and
technical quality of equipment, substations and
transmission line
Support Material department in planning and
compiling requirements for related equipment
and materials
Monitor quality, inspect work for related
equipment and materials
Involved in procurement of new equipment &
materials and also in their regular maintenance
PTC F&A
Department
Not Available Process payment of contractors / vendors and
either pay directly to contractor (if amount < 30
billion VND) or forward payment document to
F&A Department of EVNNPT
PTC Construction
Investment
Department
Not Available Implement construction investment projects
from investment preparation till
commissioning.
Interact with consultants in procurement and
preparing cost estimates
Apart from these, multiple boards/ councils/ teams are created with a specific objective at different stages of
project life cycle.
Our observation on procurement process in PTCs is that there is no separate Procurement department and
Planning & Technical departments are performing this process which may be impacting the work load on these
departments.
Processes
The processes till issue of project approval letter are covered in the “Investment Management” section. Further,
it may be noted that this section focuses primarily on the PMBs/PTCs roles in the project management
function. Various sub-processes in project management function of typical projects of EVNNPT are grouped
into key processes as explained below:
Feasibility Study (FS),Detailed Technical Design (DTD) and Workshop Design (WD)
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 51
Procurement; and
Project execution.
Feasibility Study (FS), Detailed Technical Design (DTD) and Workshop Design (WD)
The key processes at this stage for PTC and PMB are explained in Process Chart 1 and Process Chart 2 below.
These processes are elaborated under Investment Planning module with focus on role of IMD and other
corporate departments. They are repeated here (with focus on role of PMB/ PTC departments) to provide a
complete overview of a project life cycle from inception to commissioning. Some processes mentioned concisely
in the diagram and certain salient points are elaborated below:
The projects approved in annual implementation plan are allocated to a particular PMB depending on
geographic location and/or the number of projects being currently handled (to ensure equitable
distribution of work among PMBs). Further, the key criteria to select PMB or PTC for a specific project
is - if project is to be completed in shortest
possible time with minimal impact of power
supply, such projects are awarded to PTC (as
PTC can better co-ordinate with NLDC and
execute this in shortest possible time). So,
generally, minor augmentation or
strengthening works that require minimum
outage of the system are allotted to respective
PTCs. (e.g.: replacement of failed equipment -
transformers, circuit breakers, insulators;
extension of bays in a substation, civil works
etc.). The project allocation letter with list of
projects, tasks/responsibilities, milestones is
provided to respective PMB/PTC.
FS covers basic project design and detailed cost
estimates which may be different from
preliminary cost estimates. DTD covers the
detailed project design and detailed revised cost
estimates i.e. at current price levels. DTD consultants prepare the detailed designs and specifications.
WD is based on approved DTD and takes care of any changes needed at manufacturing/construction
stage (no cost estimates prepared / revised at this stage). In case DTD/WD is not required for certain
projects, the requisite drawings are prepared at FS stage only.
There are multiple approvals needed for a project and first stage approval from MoIT is needed for only
PTC projects since they are not part of the master plan and is not needed for PMB projects which are
already a part of the master plan. The second stage approval (FS approval) is a mandatory step for all
the projects. Further, the three steps process elaborated in Decree No. 12/2009/ND-CP corresponds to
FS, DTD and WD stages post project allotment. Decision to apply one, two or three step process rests
with the project owner depending upon the size and complexity - If Project value < 15 billion VND,
single step process is followed and for others, three step process is followed.
PTC hires the consultant for preliminary cost estimation along with a brief technical study to assess
value of the project, generally, on a nomination basis without competitive bidding because value of such
Typical components covered under FS:
System calculations like short circuit studies,
dynamic and transient stability studies
Line route survey with three options and suggest
optimal route
Tower spotting, layout and Estimate bill of
quantities of equipment and material needed
Basic design (standard designs and specifications
are prepared and approved by EVNNPT)
Total investment cost and financial analysis such
as NPV, IRR, Benefit-to-Cost ratio
Environment Impact Assessment (EIA) and
Social Impact Assessment and Resettlement to
minimise land needs and adverse impact on local
people and environment.
Other aspects like Fire prevention,
Telecommunication etc.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 52
consultancy contract is too low. (Procurement can be done on nomination basis if the value is less than
3 billion VND).
After procuring first stage approval based on tentative cost estimates PTC conducts a bidding process to
hire an FS consultant. PMB hires an FS consultant when the project allocation letter is received.
As mentioned above in many cases, DTD consultant is generally hired as WD consultant on nomination
basis. However, if the project is large or complex, they may be different consultants. Further, it has
been mandated recently (post 1 July 2014) that selection of all consultants is to be done through
competitive bidding process.
PECCs are in general hired as FS or DTD consultants since other private consultancy firms are not
technically and financially qualified and do not possess qualification certificate from the Government. If
the capability of these private firms increases in future, their chances of selection can increase. A
supervisory consultant can also be hired to monitor the project execution.
DTD consultants prepare the detailed designs and specifications based on the standard designs for
tower and foundation, switching schemes, standard technical specifications already available for all
equipment and materials with EVNNPT. Land acquisition process starts immediately after the approval
of FS. The process is already explained in this report.
Key issues
Long-time taken for approvals: Requirement of approvals from board of directors of EVNNPT or
top management of EVN or MoIT for every consultant’s appointment with virtually no power at PMB/
PTC level. Further, every project report (FS/DTD) has to be approved by MoIT which is increasing the
project time lines.
Standardisation of designs, specifications and layouts: There are standardised specifications
for some of substation equipment (as per IEC) and ratings of equipment for different voltage levels are
standardised (e.g.: transformers at 220 kV level - 250/125 MVA; 500 kV - 150/200/300 MVA).
However, many substation equipment and transmission tower designs are not standardised. FS/DTD
consultants select appropriate design depending upon the requirement. Further, substation layouts are
prepared based on site conditions and availability of land.
Procurement
The key processes in this stage for PTC and PMB are explained in Process Chart 3 and Process Chart 4
respectively. Some of the processes mentioned concisely in the diagram are elaborated below:
Law on bidding (Law No. 43/2013/QH13) regulates various procurement related processes (viz.
procurement plan preparation, tender documents, bid submission, opening & evaluation) along with
timelines for review and approval at various stages. This law has replaced Law on Tendering - Law No.
61/2005/QH11.
Ideally, procurement plan is to be prepared based on approved DTD. However, in most cases, it is
prepared based on approved FS since it is very detailed and provides 70-80% of details required for
preparing the procurement plan. It is revised after finalization of DTD. Key contents of procurement
plan are details like name and price of bidding package, funding sources, form and method of selection
of contractors, timelines for execution etc. The tender plan is submitted by PMBs/PTCs and evaluated
& approved by EVNNPT.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 53
Selection of bidder in open bidding has following steps - (a) Prepare for selection of bidder; (b) organize
selection of bidder; (c) Assess the bid dossiers and negotiate contract; (d) Submit, evaluate, approve
and publicise result of bidder selection; (e) Finalize and sign contract. In all these steps, relevant
outcomes have to be submitted by PMBs/PTCs for evaluation and approvals by EVNNPT. For special
cases, contractor can be appointed on a single source basis.
Turnkey contracts are not awarded in Vietnam for various reasons including capability issues of
contractors. Hence all the projects are split into multiple supply and erection contracts (refer Table
below). Although, this has increased competition among bidders, this resulted in issues like increased
coordination efforts and increased responsibilities for concerned EVNNPT officials.
Typical list of packages in EVNNPT's project management:
# Typical packages in transmission line projects
Typical packages in sub-station projects
1. Consultant for preliminary cost estimates Consultant for preliminary cost estimates
2. FS consultant FS consultant
3. DTD consultant DTD consultant
4. Resettlement / site clearance Resettlement / site clearance
5. Topographical survey Topographical survey
6. Mines survey Mines survey
7. Tower steel supply HV Equipment and material supply
8. Conductor supply LV equipment supply
9. Insulator supply Control equipment supply
10. Cable supply Installation/erection
11. OPGW supply Testing and calibration
12. Installation/erection and tower foundation SCADA
13. Insurance of asset Insurance of asset
14. Audit service Audit service
Note: The packages listed in italics are not common between line project and sub-station project
The common bid evaluation method is a “minimum technical score” with lowest price quote. This is
also used for selection of FS/DTD consultants.
In case of PMBs, the bid evaluation is performed by “Team of Bid Evaluators” which is headed by
Deputy Director or Head of Procurement Department of corresponding PMB. Other members of team
include experts from technical department (depending upon the technicality/speciality of the project),
officers from F&A department and DTD consultants. Each member of the team independently evaluates
the bid and provides formal comments.
PMB invites the successful bidder to negotiate the contract within 10 days of completion of bid
evaluation. During contract negotiation, Technical department of PMB supports Procurement
department in reviewing and finalising progress reporting milestones, environment impact and
mitigation plan, safety plan, quality control plan, detailed milestone for each item, site handover plan,
design and drawings etc.
Key issues
It was mentioned that there is long lead time in procurement of equipment, material and services. This
may be due to multiple layers of decision making and heavily centralized decision making process. For
example, Procurement Plan for each project is submitted individually for approval rather than clubbing
of multiple projects.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 54
Although, we have asked for scheduled and actual timelines of various procurement packages, we could
not get any information. Hence, we presume that such information systems are not available with
PMBs.
In the current piece-meal execution, the design consultants are responsible for basic and detailed
designs and multiple contractors are responsible for execution of different contracts. There are multiple
issues with this kind of execution:
o Each contractor will be responsible for its own supply/design / erection package and
coordination of multiple vendors has been a challenging task for the EVNNPT. The degree of
complexity in coordination increases with number of vendors/ contractors involvement.
o A delay in execution in one of the packages leads to concomitant delays in the entire project.
o Further, in the current structure, the design consultants will not be responsible for deficiencies
in construction /erection activities and erection /supply contractors will not be responsible for
design deficiencies and finding out the responsibility of any defect lies with EVNNPT which
decreases the accountability on the part of contractors/ consultants.
Project execution
The key processes in this stage are explained in Process Chart 5 below. The diagram is self-explanatory and all
key points are covered. We do not have sufficient information for a project execution under PTC. However,
considering that PMBs deal with bulk of the projects and PTCs generally execute small value upgrade and
retrofit projects, the project execution activities of PTCs will be a sub-set of the PMBs activities.
Approval of vendor / contractor drawings: Vendor submits equipment drawings based on DTD
drawings (wherever applicable) for approval of Materials Departments of PMB or PTC as applicable.
Possible strategy for procurement packaging: One of the possible way-outs is to execute a
turnkey contract for the entire project and if need be, excluding high value components such as
transformer, reactor, conductor etc. (following 80-20 rule). These high value items can be centrally
procured. This will ensure single point responsibility for contract execution and also reduce the
coordination efforts of the EVNNPT. Further, when design and construction activities are done by the
same contractor/ consortium, chances of early rectification of design issues are high and there will be a
decrease in construction and design risks. In certain cases, some construction related activities can
start even before completion of design activities which will reduce the overall project life cycle. In one
of the leading transmission utilities in the world, we have noticed that similar methodology is being
followed with centralized procurement for transformer, reactor, conductor, insulator and cable
packages; regional or site level procurement for small value contracts. Key advantages in this mode
are:
Single point responsibility for contract execution and avoid the coordination issues
Chances of early rectification of design issues and a decrease in construction and design risks
Reduction in project time through simultaneous design and construction related activities
Potential approach to vendor capacity development: Vendor capacity development activities
can be undertaken by allocating certain percentage of projects which are not very crucial to the new
vendors. In the same utility mentioned above, the company takes up vendor development programme
from time to time for specific item / equipment depending on the importance of project.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 55
Erection contractor submits construction drawings based on DTD drawings (wherever applicable) for
approval of Technical Department of PMB or Planning Department of PTC, as applicable.
Construction: The contractor can start the execution after PMB issues order for "construction start".
Contractor provides a list of supervisors to be posted on site to PMB and also agrees with PMBs about
methods of construction and system of quality control.
Quality Inspection & Testing: As mentioned earlier, a testing and quality plan for applicable
equipment/ packages is decided during contract negotiations. Generally quality inspection tests are
performed by Contractors and PMBs’ officials visit such tests occasionally (decided on a case-to-case
basis).
In case of domestic vendors, the suppliers are expected to perform requisite tests and then request the
PMB officials for inspection. The concerned officials conduct the performance acceptance testing as per
the quality plan and signs MoM of testing acceptance. Also, Supply contractor have to provide valid
type test certificates. In case of foreign vendors, PMB may or may not conduct site visits depending on
costs of visits.
In case of construction site visits, PMB officials are informed by contractor at pre-agreed stages of
construction and concerned officials perform the required inspection/ testing and certify the
construction activity.
Progress Monitoring: Different departments of EVNNPT and PMB/PTC monitor projects at
different frequencies. Contractors hired by PMB are responsible for executing different contracts. All
weekly progress reports from various contractors/vendors are consolidated by the planning department
of PMB. Every month, technical department of PMB verifies the actual progress vis-à-vis project
implementation plan. In case of slippages, PMB reminds and follows-up the contractors to expedite the
work. In case of repeated violation, penalty is imposed as per the provisions of the contract.
CMD is responsible for overall monitoring of all construction projects carried out by all PMBs/ PTCs
and ensuring compliance with the overall technical, environmental and social and R&R
framework/guidelines. CMD also conducts ad hoc visits at construction project sites to validate the
actual progress / quality with respect to reported progress / quality. If CMD finds any issues in progress
or quality of the project, it reports the same to PMB /Supervisors to address the issue. CMD also
periodically reports project progress to Vice Presidents / President& CEO/ Management Board by itself
or as inputs to the general progress reports prepared by CPD. Further, ICD also collects data from
PMBs or CMD to submit status reports to the ODAs for ODA funded projects.
We have requested for templates of progress review, testing & commissioning reports, delay in
arranging inspection, escalation reports on various issues from Technical Department and Planning
Departments so as to gain insights in to the issues in project management of EVNNPT.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 56
Payments to contractors: The key steps for processing of payments in PTC and PMB projects are
explained in Process Chart 6 and Process Chart 7 below. The diagram is self-explanatory and all key
points are covered. Payment milestones are linked to completion of certain activities /works/ supply
and vary from contract to contract. They are proposed by Contractor and revised or accepted by
concerned PMB/PTC departments. We are informed that the payment process for domestically funded
projects requires one-two weeks (i.e. from receipt of a “completed invoice” to disbursement); in this,
F&A department at PMB/PTC takes 2-3 days to process the completed invoices.
In one of the leading transmission utilities, we have observed that a web-based inspection
management system is being used. The salient features of the system are:
Registration Main contractor (turnkey contractor) can register its name as user by providing all
requisite details. All sub-vendors should be pre-approved by the utility
Raising a call: Only a main contractor can raise inspection calls (on behalf of even the sub-
vendors) by quoting details like Letter of Award No and other details
Tracking a call: After raising a call, each inspection call is given a unique 10 digit call-ID by the
system for further processing/ monitoring of call status. The call will be allotted to a particular
executive and the contractor can contact him/her.
Witness & Waiver: Witnessing requirement by the company’s representative is then either
waived off or the call is forwarded to the concerned regional inspection office for further action.
The waiver may be provided considering the available resources, criticality of the equipment and
project time schedule etc. In case of waiver, the turn-key contractor is supposed to witness the tests
and submit the results to the company for review and acceptance.
Blocking the call: Inspection call can be blocked if the information provided is found to be
inaccurate or incomplete or it is not closed within specified schedule. The calls can be reopened
only with proper explanation and confirmation that it shall not occur again in future.
Message Board: Messages are put on system on case to case basis for communicating to all
concerned. It is expected that the concerned inspection engineers / Contractors shall refer the
Message Board on regular basis and take the necessary action accordingly.
Other global practices for inspection management
Level of inspection: During post bid discussions, various supply equipment/ items are categorized in
different levels based on their criticality. Different levels of items require different involvement of
inspection by the company.
Process inspection: In a normal inspection process (product inspection), customer witnesses the
inspection in each offered lot or waives off witnessing in some intermittent lots. The acceptance or
rejection of offered lot depends on the inspection during final acceptance tests. However, in case of
process-inspection, the processes involved in various phases of manufacturing and testing are
inspected and efforts are made to enhance the process capabilities. It is expected that the final product
shall have built-in quality with better processes in place. This is in line towards achieving “Zero Product
Inspection”. Further, for improving quality during transportation, storage, erection and commissioning
activities during implementation of projects, Quality Audit on implementation of Field Quality Plans is
also carried out.
To initiate the process-inspection, process based MQPs are finalized with concerned manufacturer and
regular process-inspections are carried out at their manufacturer works to review the processes and to
optimize the inspection requirement.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 57
In case of ODA funded projects, process is to be completed in 51 days as per the regulations. However,
the actual time taken seems to be longer as whole process runs through several steps.
NPMB clarified that milestones are proposed by the contractors and reviewed/ accepted by PMB.
Number of milestones varies from contract to contract. PMB reviews the milestones, negotiates the
same and finalises for implementation monitoring. Payment is linked with the achievement of specific
milestone.
Commissioning activities & Contract closure: An acceptance board is constituted for each
project with representatives from all the
stakeholders. Testing of system is performed by
testing contractors and site engineers of PMB
witness/monitors the testing process. The
Acceptance Board holds meetings with site
engineers and offers comments on the different
parameters of testing performed. These
comments have to be resolved by the site
engineers working in tandem with the
contractors (if required). Acceptance board
issues approval of Project after all the
outstanding issues are resolved. PMB sends
report/ minutes of meeting to LDC (A0-NLDC/
A1-RLDC) for information and hands over to PTC
for operation.
Acceptance Board consists of
Vice President (Construction) - Head of Board
Director of PMB - Vice Head of Board
Member from EPTC
Company in-charge of fire prevention
PTC (operator of the project)
LDC
Representatives of all the contractors
Member from EVNNPT
PMB - officers from technical, materials and
safety departments
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 58
Process Chart 1: Feasibility Study and Detailed Technical Design - PTC Projects
Feasibility Study & DTD – PTC Projects
NPT/ EVN & Ministries & DeptsPTCConsultants
FS consultants prepare implementation plan , basic
design, and other aspects required for an investment project proposal
Second stage approvalApproval of Feasibility study by EVN/ MoIT/ NPT board depending on value
through IMD
Construction investment dept reviews all inputs of FS by itself or with help of other
departments and submits to NPT
Consultant prepares tentative project cost estimates
First stage approval (Technical feasibility) by MoIT
through IMD of NPT
Planning dept reviews with help of Construction investment dept and sends for
approval
Land recovery process ( Rarely
required)
Requirement of project identified by
PTC
Procurement process for selection of FS Consultants
Is project urgent/ critical/
small valueNo
DTD Consultants to prepare detailed technical design
Approval of detailed design by Technical Dept of NPT;
Procurement process for selection of
equipment /erection contractor
Construction investment dept reviews with inputs from other
departments / other consultants
Procurement process for selection of DTD Consultants (Rarely required)
Procurement plan with package prices, schedule, funding source, bidding parameters by Planning dept
Yes
Approval of Procurement plan through CPD of NPT
Procurement process for selection of Cost Estimates Consultants
DTD Consultants to prepare bidding documents
Planning Department reviews and forwards for
approval
Approval of bid documents through
Procurement Dept of NPT
Is project urgent/ critical/
small valueNo
Planning Department prepares bid documents&
forwards for approval
Yes
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 59
Process Chart 2: Feasibility Study and Detailed Technical Design - PMB Projects
Feasibility Study and Detailed Technical Design- PMB Projects
NPT/ EVN & Ministries & DeptsPMBConsultants
FS consultants prepare implementation plan , basic design,
conduct route survey ,system studies, EIA , SIA, resettlement issues & an
investment project proposal
Second stage approvalApproval of EIAR by DoNRE through CMD
Approval of Feasibility study by EVN/ MoIT/ NPT board depending on value through IMD
Evaluation dept reviews all inputs of FS by itself or with help of other consultants and submits to NPT
Land Acquisition / recovery process
Project allotment letter to PMB Procurement process for selection of FS
Consultants
Is project urgent/ critical/
small valueNo
DTD Consultants to prepare detailed technical design
Approval of detailed design by Technical Dept of NPT;
bid documents by Procurement Dept of NPT
Evaluation dept reviews with inputs from other departments /
other consultants
Procurement process for selection of DTD Consultants
Procurement process for selection of
equipment /erection contractor
Procurement plan with package prices, schedule, funding source, bidding parameters by Planning dept
Approval of Procurement plan through CPD of NPT
DTD Consultants to prepare bidding documents
Procurement Department reviews and forwards for
approval
Approval of bid documents through
Procurement Dept of NPT
Is project urgent/ critical/
small valueNo
Procurement Department prepares bid documents&
forwards for approval
Yes
Yes
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 60
Process Chart 3: Procurement process - PTC projects
Procurement process - PTC Projects
NPT/ EVN & Ministries & DeptsPTCConsultants/ Contractors
Bid process (NIT, pre-bid, receipt of bids, evaluation) by Planning Dept and submits for Director’s approval
Is project ODA funded?
Post Director’s approval , Planning dept seeks approval from NPT board/ President & CEO
YesAuthority submits for ODA approval; Post ODA,
approval of bidder & bid process
Planning dept calls for Contract negotiations with successful bidder and signs contract ( Director)
No
IMD (NPT) maintains all contracts
Approval of FS consultants by President & CEO/ NPT board
through CPD
Planning dept calls for bids from FS consultants for feasibility study
Planning dept selects consultant for tentative project cost estimation on
single source basis ( nomination basis)
Project requirement finalized by PTC
Planning dept selects DTD consultants for feasibility study ( mostly FS consultants) or follows similar bidding process for selection
Approval of DTD consultants through CPD by competent authority
Selection of Cost Estimate Consultants
Selection of FS Consultants
Selection of DTD Consultants ( rarely required)
First stage approval from MoIT
Second stage approval from MoIT/NPT
Preparation & review of initial estimates
Preparation & review of FS
Selection of Supply /Erection Contractors
Approval on bid documents & DTD( as
applicable)
Preparation & review of bid documents& DTD (as applicable)
Panel of Consultants pre-selected
Consultants submit bids
Planning dept evaluates and selects successful bidder; sends for approval
Bidders submit bids
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 61
Process Chart 4: Procurement process - PMB projects
Procurement process – PMB Projects
NPT/ EVN & Ministries & DeptsPMBConsultants/ Contractors
Bid process(NIT, pre-bid, receipt of bids, evaluation) by Procurement Dept(supported by Technical Dept and submits for Director’s approval
Is project ODA funded?
Post Director’s approval , Procurement dept seeks approval from Authority (NPT board/ President & CEO)
YesAuthority submits for ODA approval; Post ODA,
approval of bidder & bid process
Procurement dept (supported by Technical Dept) calls for Contract negotiations with successful bidder and signs contract ( Director)
IMD (NPT) maintains all contracts
Approval of FS consultants by President & CEO/ NPT board
through CPD
Planning dept calls for bids from FS consultants for feasibility study
Procurement dept selects DTD consultants for feasibility study ( mostly FS consultants) or follows similar bidding process for selection
Approval of DTD consultants through CPD by competent authority
Selection of FS Consultants
Selection of DTD Consultants
Project allotment letter
Second stage approval from MoIT/NPT
Preparation & review of FS
Selection of Supply /Erection Contractors Approval on bid
documents & DTD( as applicable)
Preparation & review of bid documents& DTD
Consultants submit bids
Planning dept evaluates and selects successful bidder; sends for approval
Bidders submit bids
No
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 62
Process Chart 5: Project execution - PMB projects
Project execution- PMB Projects
NPTPMBContractor/ Supplier
Material& Technical depts review& approve equipment and construction drawings respectively with support of consultants
Post approval, supplier starts manufacturing of equipment, Contractor starts construction
activities as per schedule
Technical Dept monitors quality regular testing and inspection
Supplier prepares equipment drawings. Contractor prepares Construction drawings
CMD conducts adhoc testing & Inspection on quality and reports findings to supervisor consultants/PMB and senior management
Contractor to take necessary remedial measures based on inputs and achieve
completion of milestones
CMD directly or via Technical dept issues upto 3 formal warnings; If un- resolved, penalty
measures based on type & severity of issue
Payment Process
Completion of all Project activities, install , commission the equipment and obtain sign-
off from concerned departments
Acceptance board constituted. Different tests conducted as per regulations, contract and approval of
commissioning given
Supply/ Erection Contract executed
Technical dept prepares project implementation plan (PIP) and gets reviewed by Director (approval from CMD-NPT)
On site work commenced by contractor
Project team set up – 1 expert from Technical dept for monitoring, 1-2 site engineers for site level progress &
Select supervision consultants( if required)
Weekly, Monthly and Periodic Progress reports to CMD/ IMD/ ICD/ CPD etc as required; CMD
primarily monitors from NPT
Planning dept monitors weekly progress & Technical dept monitors
monthly progress.
In case of delay and repeat issues in performance , Technical dept can
impose penalty.
Report to LDC(Ao, A1) about commissioning of project
Hand over project to respective PTC and costs verified by an auditor
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 63
Process Chart 6: Payment process for Domestic & ODA funded projects - PTC
Payment processes for Domestic and ODA funded projects- PTC
NPT/ ODAPTCContractor/ Supplier
Contractor raises invoices after successful completion of milestone
Officials from Planning, Technical Depts and legal representative verify the bill and send to F&A Dept for
payment
Is payment > prescribed limits of PTC?
Proposal reviewed at different levels in F&A Dept of NPT and approved after getting any clarifications as required
No
Yes
Document for fund disbursement certified by F&A dept and sent to bank
Bank electronically pays to contractor
Domestic funded Projects
ODA funded ProjectsContractor raises invoices after successful
completion of milestone
Document for fund disbursement certified by F&A dept and sent to bank designated by ODA; Bank
sends it to NPT
Bank electronically pays to contractor
Officials from Planning, Technical Depts and legal representative verify the bill and send to F&A Dept for
payment
F&A of NPT reviews and sends to bank which notifies MoF and also ODA head
office for payment
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 64
Process Chart 7: Payment process for Domestic & ODA funded projects - PMB
Payment processes for Domestic and ODA funded projects-PMB
NPT/ ODAPMBContractor/ Supplier
Contractor raises invoices after successful completion of milestone
Officials from Planning, Technical Depts and legal representative verify the bill and send to F&A Dept for
payment
Is payment > prescribed limits of PMB?
Proposal reviewed at different levels in F&A Dept of NPT and approved after getting any clarifications as required
No
Yes
Document for fund disbursement certified by F&A dept and sent to bank
Bank electronically pays to contractor
Domestic funded Projects
ODA funded ProjectsContractor raises invoices after successful
completion of milestone
Document for fund disbursement certified by F&A dept and sent to bank designated by ODA; Bank
sends it to NPT
Bank electronically pays to contractor
Officials from Planning, Technical Depts and legal representative verify the bill and send to F&A Dept for
payment
F&A of NPT reviews and sends to bank which notifies MoF and also ODA head
office for payment
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 65
People
A staff manual with roles and responsibilities at different levels and clear job description helps brings in clarity
to the officials and guides the new employees to assimilate into the organization with relative ease. In our
interactions, we have been provided with staff manual from International Cooperation Department only. Most
of the other departments mentioned that there are no staff manuals and this is a significant issue that can
hamper the employees from performing optimally.
It is estimated that around 200 projects are executed every year that are spread across geography of Vietnam in
different terrains. To execute these projects within stipulated timelines, EVNNPT and its subsidiaries require
qualified staff at corporate and field levels across the hierarchy. In our interaction, multiple departments have
mentioned shortage in staff vis-à-vis number of projects being executed hampering their quality of the work
and slippage in deadlines. Although, the number of staff in different departments/ subsidiaries is provided, we
could not estimate the requisite number of staff required to perform the tasks optimally as the inputs are not
available.
Technology
Different departments of EVNNPT and their subsidiaries use stand-alone IT tools with different forms/ report
templates for project monitoring. For example, PTC uses Microsoft Project, Microsoft Excel, Contracts
management application, FIMS for project management. However, lack of comprehensive project monitoring
tool as well as disparate methodologies prevailing in different entities/departments is hindering effective
project monitoring by the top management. The proposed project management software is intended to resolve
the gap. However, preliminary stakeholder interaction suggests that the software may be more of a project
information repository and status reporting tool rather than project monitoring and management tool
We could not garner business blue print/ manual of the proposed project management software in spite of
repeated requests and hence our understanding of this aspect is limited to our interactions with IT department
of EVNNPT and the same has already been presented in this report.
NPT or its subsidiaries do not have any integrated project management system and some departments in
EVNNPT are using stand-alone packages/software developed by IT department of EVNNPT along with MS
office tools like MS Excel and MS Project for project progress monitoring. In our interactions with multiple
departments, need for a project monitoring tool has been highlighted repeatedly for various reasons. This lack
of visibility at corporate level / senior management level is hindering effective project monitoring causing
severe delays in project execution. To cater to this need, EVNNPT is now in the process of developing "Project
Management Software" which is being developed by EVNNPT's IT Department with the help of a consultant.
After the successful roll-out of this software, it is expected that the authorized users at different locations/
departments viz. site execution teams at PMBs, PTCs as well as key departments at EVNNPT (viz. CMD, IMD,
CPD, Procurement department, Materials Department, F&A department etc.) can both update their activities in
various projects and know about the status of different projects through internet.
An investment project management module is only expected to be complete by the year-end considering the
urgency for the same. Other modules of the software are expected to be developed in a phased manner. Main
functions of the investment project management software as follows:
Management of project information
o Project information: Name, project type, start time, scheduled finish time, fund source, owner
o Information on tender packages
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 66
o Information on consultants, contractors
o Information on decisions for projects
Management of progress
o Progress management over project phases from investment project report until payment
o Challenges faced and solutions being adopted (if any) during project implementation
o Visual display of actual progress and scheduled progress (Gantt diagram or any similar model)
Reporting system
o Filter information in different ways (by project type, fund source, finish time, implementation
contractor, owner, a time period, actual implementation level, delay etc.)
o Produce reports with different templates to meet the requirements of CPD, CMD, IMD, F&A
Department etc.
Key software tools / MS Excel models / system used:
Name of software
tools / MS Excel
models / system
Brief description / features /
functionalities
PwC analysis and observations
Project
Management
Software
Web-based online application
developed using "SharePoint"
technology
Developed by an external
software development
company named Harmony
Software Technologies JSC
It will be installed in a central
server of EVNNPT and will be
accessed by all PMBs and PTCs
through internet
Seven modules: Project
management, Project
planning, Investment
preparation, Investment
implementation, Investment
completion, Searching,
Administration
We have been provided a brief overview of
the software by IT department. We have
requested for a detailed demonstration of
various functionalities and also for the
process manual being used for
development of the software. We are yet to
receive EVNNPT’s response on the same.
Prima facie, software appears to be more
of a project information repository and
status reporting tool rather than project
monitoring and management tool
Software is under development and it
needs review and refinement by various
stakeholders/users to make it more
effective
Software is currently in Vietnamese and it
is planned to be made available in English
to users
Summary of key observations
In the following section, we have summarised our key preliminary observations identified during inception /
process review phase:
1. Resource constraint and lack of focus in managing projects: It is estimated that around 200
projects are executed every year that are spread across geography of Vietnam in different terrains. To
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 67
execute these projects within stipulated timelines, EVNNPT and its subsidiaries require qualified staff
at corporate and field levels across the hierarchy. In our interaction, multiple departments have
mentioned shortage in staff vis-à-vis number of projects being executed hampering their quality of the
work and slippage in deadlines. The number of staff currently in different departments/ subsidiaries
and the expected number of staff required to perform the tasks optimally are not available currently.
There is a need for organization level resource requirement study to assess the requirement at different
positions and check under-utilization /over utilization of personnel in different departments. This will
also help in clearly identifying roles and responsibilities for different positions in EVNNPT and its
subsidiaries (preparation of staff manuals wherever required). Although different departments are
performing the activities in line with the tasks delegated, no integrated project- management is in
place.
2. Long lead time: It is mentioned that there is long lead time in procurement of equipment, material
and services. This is due to multiple layers of decision making and heavily centralized decision making
process. There is a recent change in the investment proposal approval requirement and now all the
project documents in FS & DTD stages should be approved by MoIT which is significantly increasing
the lead time. There is a significant time spent for review of documents at each stage (PMB/ EVNNPT/
EVN/ MoIT). An estimate for different steps in a typical project (based on our interactions) is given
below:
Sl.
No.
Key Activity Time duration from project allotment (in months)
Minimum Maximum
1. Project Allocation letter 0 0
2. FS consultant hired 6 8
3. FS approved 12 24
4. Hiring of DTD consultant & approval 30 42
5. Supply /erection contractor selection 37 50
6. Procurement plan, bidding documents, contractor selection approval (for ODA projects)
40 56
7. Commissioning of project 60 96
3. Delay in land acquisition (recovery) and R&R: The land acquisition process along with
subsequent R&R activities, designing compensation plan etc. are cumbersome and time consuming due
to the prevailing regulatory scenario in the country. Many organizations are present and interactions
between various departments seem to increase total time required for land acquisition. Further, it is
required that entire site/ corridor clearance should be obtained before start of construction; it is not
being put in practice because of long time required to get site clearance for all tower locations of a given
line.
New Land Law has come into effect on 1 July’14. Although there are some changes there is no mention
of reducing the organizations involved in the process.
4. Limited capabilities of local contractors and consultants: It has also been mentioned that the
financial, technical and project management capabilities of existing contractors/ vendors and design
consultants are limited and none of the existing contractors / bidders could meet the desired
qualification criteria for turnkey contracts. Hence, all the projects have to be split into small erection
and supply packages which are resulting in complex coordination issues for EVNNPT. It has been
observed that there is very less participation from international bidders. Further, the FS and DTD
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 68
consultants are generally PECCs and private players are not selected because they do not meet financial
and technical criteria and do not have Government Certificate.
5. Lack of proper tool to monitor and manage projects: Different departments of EVNNPT and
their subsidiaries use stand-alone IT tools with different forms/ report templates for project
monitoring. For example, PTC uses Microsoft Project, Microsoft Excel, Contracts management
application, FIMS for project management. However, lack of comprehensive project monitoring tool as
well as disparate methodologies prevailing in different entities/departments is hindering effective
project monitoring by the top management. The proposed project management software is intended to
resolve the gap. However, preliminary stakeholder interaction suggests that the software may be more
of a project information repository and status reporting tool rather than project monitoring and
management tool. In spite of repeated requests, we could not get the manual related to this tool and
hence we have only limited understanding of the tool which has been presented in the report.
6. Standardization: There are standardised specifications for some of substation equipment (as per
IEC) and ratings of equipment for different voltage levels have been standardised However, many
substation equipment and transmission tower designs are not standardised. FS/DTD consultants select
appropriate design depending upon the requirement. Further, substation layouts are prepared based on
site conditions and availability of land.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 69
Transmission pricing
Strategy
The MoIT and MoF have promulgated regulations which guide the process and method of determining the
transmission charge payable to the EVNNPT by the users of the transmission system. The primary regulation
that governs the determination of transmission charge is Circular No. 14/2010/TT-BCT dated 15 April 2010
(amended by Circular No. 3/2012/TT-BCT dated 19 January 2012). It sets out the detailed methodology for
calculating the transmission charge along with procedures and timelines to be followed for the submission,
calculation, review and approval of the transmission revenue and charge by stakeholders namely EVNNPT,
EVN, EPTC, NLDC, ERAV and payers of transmission charge.
This section briefly captures some of the key observations on the existing laws/decisions/decrees/regulations in
Vietnam (Brief provided in Appendix 5 -) and presents select global practices followed with respect to such
specific areas in South East Asian countries such as India, Malaysia and Philippines. It aims at providing an
indication towards the recommendations to be made.
Circular No. 14/2010/TT-BCT dated 15 April 2010 on method of elaboration, procedures for formulation, promulgation and management of power transmission charge
Based on our understanding of the above regulations, key areas of concern are listed below and
select global practices addressing those areas have also been presented.
True up mechanism:
The regulation specifies true-up / adjustment mechanism as part of transmission charge determination
methodology, but in reality, ERAV has not yet undertaken any such adjustment in determining the
transmission charge in the past, to take care of variation between approved tariff and actual expenses during
the previous year.
The formula for transmission charge of year N = Permitted capital cost + Permitted O&M expenses + Difference
between transmission costs and revenues of year N-1
Select global practices
For effectively truing up the costs allowed for previous years, the regulation should firstly define what the
controllable and uncontrollable cost parameters are. Based on such categorisation alone there can be a scientific
approach to allowance or disallowance of true and reasonable costs. This will also send a clear signal to the
utility about being prudent and efficient in their capital and operating expenditure.
In India
The Central Electricity Regulatory Commission (CERC), in its regulation named CERC (Terms and Conditions
of Tariff) Regulations, 2014 has defined controllable and uncontrollable factors as below.
The ‘controllable factors’ shall include but shall not be limited to the following:
1. Variation in capital expenditure on account of time and/ or cost over-runs on account of land
acquisition issues;
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 70
2. Efficiency in the implementation of the project not involving approved changes in scope, change in
statutory levies or force majeure events; and
3. Delay in execution of the project on account of contractor, supplier or agency of the transmission
licensee.
The ‘uncontrollable factors’ shall include but shall not be limited to the following:
1. Force majeure events; and
2. Change in Law.
The below example from the tariff order of the Northern Region System Strengthening Scheme-V of Power Grid
Corporation of India (POWERGRID) shows the disallowance of controllable cost items by the CERC. This
assessment sends clear indication to the licensee (here, POWERGRID) that expenditure which is controllable
and not prudent will not be allowed as a pass through.
As per the investment approval, the project was scheduled to be commissioned within 36 months from the date
of investment approval i.e. by 01.07.2009. The transmission asset was put under commercial operation on
01.01.2011, after a delay of 18 months. The transmission licensee had submitted, that the progress of work of
bus reactor at Bhiwadi sub-station was hampered mainly due to poor mobilization of supply and erection by the
contractor. Upon scrutiny of the reasons and relevant documents, the CERC was not convinced that the
construction activity around Bhiwadi could delay the commissioning of the transmission asset. Therefore in the
absence of any justifiable documentary evidence, the CERC was unable to accept the claims made by the
licensee. They were also of the view that the beneficiaries should not be burdened with the cost of time over-run
and accordingly impact on cost of the delay of 18 months was disallowed as a pass through.
Details of disallowed Interest During Construction (IDC) and Incidental Expenditure During Construction
(IEDC) are as follows:
As per Management Certificate submitted vide affidavit dated 06.12.2013 (million INR) Particular IDC IEDC
Expenditure up to 31.12.2010 13.284 3.605
Total IDC and IEDC claimed 13.284 3.605
Details of IDC & IEDC Disallowed for 18 months
Disallowed IDC and IEDC for 18 months 4.428 1.202
Total allowed 8.856 2.403
The true up process is undertaken once in 5 years at the end of the MYT control period by CERC for the
National Transmission utility (PGCIL) in India, based on the defined controllable and uncontrollable
parameters vis-à-vis the actual performance of the utility. These defined parameters set a clear standard of
performance to the utility, which will be allowed to enjoy incentive on efficient performance and will be
penalised for inefficiencies.
In Philippines
The Energy Regulatory Commission of Philippines in its Rules for setting Transmission Wheeling Rate, 2009
has defined the various guiding principles for determination of transmission revenue and wheeling rate. The
method followed is a Revenue Cap method, and is based on the below price control formula.
MARt = [MARt-1 x {1 + CWIt - X}] - Kt - RBRt
Where:
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 71
MARt-1 = Maximum allowed revenue for Regulatory Year t-1, where Regulatory Year t commences on 1
January 2004, MARt-1 equals PhP 24,591 million;
CWIt = Change in Weighted Index for Regulatory Year t;
X = A productivity or efficiency factor for Regulatory Year t. X equals 0 (zero) for each Regulatory Year
occurring during the First Regulatory Period;
Kt = Correction Factor to adjust for over or under recovery of revenue in Regulatory Year t-1. Where
Regulatory Year t commences on 1 January 2004, Kt equals 0 (zero); and
RBRt = A portion of the net income derived, during the 12 month period ending on 30 September in
Regulatory Year t-1, from each related business engaged in by the regulated entity, which business
utilizes assets that form part of the regulatory asset base, being a portion that is determined by the ERC
pursuant to Section 20 of the EPIRA and that may vary as between such businesses but which, for each
such business, does not exceed 50% of the net income that is so derived from that business.
The Kt approved by the Commission in its order dated December 2, 2013 on Maximum Allowable revenue for
FY 2013 of National Grid Company of Philippines (NGCP) was (1811.45) million PhP. The over/under-recovery
is calculated based on the actual amount billed to consumer along with the net payments receivable by NGCP as
a network service provider or system operator over the previous year less the maximum allowable revenue for
the previous year.
In Malaysia
The Energy Commission of Malaysia - Suruhanjaya Tenaga in its regulation namely Electricity Tariff Regulatory
Implementation Guidelines 2012, for the bundled utility TNB, provides the formula for Revenue Requirement
as follows.
AAR = Return on regulated assets (Return * RAB) + Forecast annual depreciation + Forecast annual operating
costs + Forecast annual tax payments + Efficiency carryover amount
The Efficiency carryover amounts will be determined based on the base incentive and the efficiency carryover
scheme. Base Incentive enables the business entities to retain any variances between actual operating and
capital expenditure amounts relative to forecasts within the regulatory term. This will encourage the pursuit of
efficiencies in both operating and capital expenditures, as reductions in any expenditure as a result of
efficiencies will result in higher return for shareholders.
Also, the efficiency carryover scheme provides the business entities a continuous and sustained incentive to
pursue cost efficiencies during every year of the Regulatory Term. This is important as under the base incentive
regime, the business entities incentive to pursue efficiencies weaken as they approach the end of the Regulatory
Term. This is because cost efficiencies will result in a lower cost base for the subsequent Regulatory Term and
the time to retain efficiencies during the current Regulatory Term reduces with every passing year of the
Regulatory term. This is done by adding 50% of the Cost Efficiency Amount to the annual revenue requirement
projected for the next Regulatory Term in a phased manner.
It can be seen that the methods followed on Philippines and Malaysia are efficiency-based revenue correction
mechanism where all cost parameters are open for being efficiently managed.
Penalty for failed service quality:
The above regulation lays down the procedure for calculating penalty for failed service quality, where EVNNPT
is fined for failing to guarantee quality of service in cases where outages of transmission lines and transformers
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 72
of the transmission system in the year exceeds regulated limits for each voltage level, except for incidents
caused by force majeure or problems not caused by EVNNPT. But even this guideline is merely on paper and is
not actually implemented. The cause for seems to be inadequate data availability as well as lack of clearly
defined quality parameters for assessing performance.
Information required and not accurately or fully captured as well as penalty norms which are not clearly
defined are:
1. Time of outage of transmission line or transformer
2. Number of outages of transmission line or transformer
3. Penalty norms for outage of transmission line at 110 kV, 220kV, 500kV
4. Penalty norms for outage of transformer at 110kV, 220kV, 500kV
Also the mechanism for penalising EVNNPT for any such failure is by deducting the penalty amount from the
welfare fund which is created for all staff members. This approach seems to be penalising all staff members who
might not be in any way related to the process of managing the service quality of the transmission system.
Select global practices
Specification of operating norms and performance parameters is essential to measure efficient performance of
the transmission system. To develop a suitable mechanism of incentive and disincentive is important to drive
the performance of the licensee. The approach followed usually for specifying operation norms is based on
historical data analysis and consideration of efficiencies, technological advantage, vintage etc. The performance
norms are also designed to be practical and implementable allowing the utility a fair chance to achieve the set
standards.
In India
The Tariff Policy, 2006 has set a principle for specifying operational norms. It provides that, “Suitable
performance norms of operations together with incentives and disincentives would need to be evolved along
with appropriate arrangement for sharing the gains of efficient operations with the consumers. This is essential
to encourage better operating performance. The norms should be efficient, relatable to past performance,
capable of achievement and progressively reflecting increased efficiencies and may also take into consideration
the latest technological advancements, fuel, vintage of equipment, nature of operations, level of service to be
provided to consumers etc. Continued and proven inefficiency must be controlled and penalized.’
For example the norms specified by CERC in its regulation named CERC (Terms and Conditions of Tariff)
Regulations, 2014 are as below.
Norms of operation for transmission system: The Normative Annual Transmission System Availability Factor
(NATAF) shall be as under:
1. For recovery of Annual Fixed Charges:
a. AC system: 98%;
b. HVDC bi-pole links and HVDC back-to-back stations: 95%.
2. For incentive consideration:
a. AC system: 98.50%;
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 73
b. HVDC bi-pole links and HVDC back-to-back stations: 96%.
For new HVDC stations, NATAF shall be considered as 95% for first three years of operations for the purpose of
incentive. Provided further that no incentive shall be payable for availability beyond 99.75%.
For AC system, two trippings per year shall be allowed. After two trippings in a year, additional 12 hours outage
shall be considered in addition to the actual outage.
In case of outage of a transmission element affecting evacuation of power from a generating station, outage
hour shall be multiplied by a factor of 2.
Further the penalty or incentive as applicable is adjusted in the Annual revenue requirement of the utility thus
allowing it higher recovery for better performance or lower recovery for failed service quality. This approach
ensures that the people responsible to ensure service quality will be directly answerable to the management and
also will not penalise staff members who are not responsible to maintain the service quality of the transmission
system.
In Malaysia
The Energy Commission of Malaysia - Suruhanjaya Tenaga in its regulation namely Electricity Tariff Regulatory
Implementation Guidelines 2012, for the bundled utility TNB, clearly lays down the Incentive framework for
operational performance. The regulation provides as under;
“The Commission considers it prudent and indeed part of its overall design of a holistic incentive-based
regulatory system to set standards and incentives to improve operating performance. This is because the
Commission does not want cost and financial efficiencies to be achieved at the expense of lowering
operational performance.
The Commission considers that operational performance primarily consists of network performance and
customer service. Therefore the Commission will consider establishing standards, benchmarks and incentives
(and disincentives) for network performance and customer service (where relevant) for the TNB business
entities.”
The Commission proposes to adopt the following criteria in setting the operational performance indicators:
relates closely to the business activities of the TNB business entities;
highly valued by electricity customers;
can be objectively measured; and
can be independently audited.
The Commission proposes that each of the TNB business entities recommend a list of 3 operational
performance indicators and demonstrate that they comply with the criteria as outlined above. For example, the
Commission notes that:
Circuit and plant availability, supply interruption and losses are common indicators adopted for the
electricity transmission businesses in Australia, UK and Singapore. In addition power quality indicators
(voltage dip incidents) have been used in Singapore for electricity transmission.”
The Commission for setting performance targets has in its draft recommendations adopted a model
where an upper bound and a lower bound target for each performance indicator will be set. The
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 74
Commission will review at least 3 years of historical data in setting both the lower bound and upper
bound performance targets.
Return on Equity:
The regulation allows for recovery of return on equity as part of the permitted capital cost, as a means to plough
back into further investment activities. But the same is not being mandatorily allowed as part of transmission
charge by the ERAV. Also, regulation does not specify fixed % of equity as return on equity (profit) because of
which EVNNPT is unable to assess absolute amount of RoE in a particular year impacting its ability to plan self-
financing for its upcoming investments.
Total permitted capital costs of year N = Total depreciation costs + Total long-term loan interest expenses +
Eligible power transmission profit of year N (RoE).
Select global practices
Regulated utilities are allowed to recover their cost to do business and earn a return on invested capital. This
return can be ploughed back into the business to enable further investment for improving performance
efficiency. The rate of return on equity is fixed such that it will not only attract investment and generate
sufficient resources for further growth in the sector but also to take care of the consumers’ interest. The
interests of the consumers are taken care of in the real sense only when quality power is made available
throughout the year. This could be achieved only through large capacity additions which in turn will require
huge investment. Further a higher investment in the form of equity also helps the utility in negotiating and
availing debt at competitive terms and conditions.
In India
Section 61 (d) of the Electricity Act, 2003 provides that the Regulatory Commission, while specifying the terms
and conditions for the determination of tariff, shall be guided by the principle of ‘safeguarding of consumers
interest and at the same time, recovery of cost of electricity in a reasonable manner’.
Para 5(3)(a) of the Tariff Policy stipulates that: ‘Balance needs to be maintained between the interests of
consumers and the need for investments while laying down rate of return. Return should attract investments at
par with, if not in preference to, other sectors so that the electricity sector is able to create adequate capacity.
The rate of return should be such that it allows generation of reasonable surplus for growth of the sector’.
The Central Electricity Regulatory Commission (CERC) of India, in its regulation named CERC (Terms and
Conditions of Tariff) Regulations, 2014 has provided that, Return on equity shall be computed at the base rate
of 15.50% for transmission systems.
In Malaysia and Philippines
Regulators in Malaysia and Philippines allow reasonable and fair return (termed as weighted average cost of
capital or WACC) on the regulatory asset base (RAB).
Structure of the transmission charges:
Currently the transmission charges payable by payer i in year N (TCi) is calculated by employing the following
formula.
Total transmission cost = Capacity-linked transmission charge + Energy-linked transmission charge + Total
adjustment for year N-1
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 75
The ratio of capacity and energy volume components in the power transmission charge is regulated by ERAV
each year, with α + β = 1; regulated α = 0 currently. This means that the transmission charge is only energy
based and not capacity based.
This may not the ideal way to recover transmission revenue, as the system is built to cater to the maximum
available generation capacity and thus should entail recovery from long term (committed) customers on
capacity basis as well. Also if the recovery is only energy based, there is no certainty to revenue recovery, as the
actual energy transmitted may vary from the projected energy to be transmitted.
Select global practices
The standard method of recovering transmission cost from long term customers is based on the system
capacity. Only for short term transactions, the transmission charge is based on the energy transacted. The
rational being that the entire revenue requirement for a transmission system comprises of fixed cost
components and thus do not vary with the volume of energy transacted. Hence irrespective of the volume of
energy transacted, this cost has to be fully recovered by the transmission licensee.
In India
The recoverable transmission charges from the long term customers are always denominated as
Charge/MW/time unit for e.g. 100,000 INR/MW/month.
In Philippines
The transmission charge is levied on contracted capacity in kW.
Cost norms:
It is also seen that the cost norms set as the basis for calculating the material costs and major repair costs
(which are components of the transmission revenue) are outdated and there is no mechanism to adjust these
existing cost norms to reflect inflation, technological advancement or substitution between capital and variable
costs. Further, since the list of cost norms is outdated, it also does not contain certain cost items which today
form part of the overall cost list.
The cost norms used by EVNNPT are the ones that were developed by EVN in 2006. Many cost items like
environment impact assessment study, engineering / management software, fire prevision systems, propaganda
systems, telecommunication systems etc. are completely missing in the list.
Select global practices
The usual practice should be one where the cost norms are reviewed and revised in a timely fashion to be
reflective of price movement in the current market. This is of utmost importance to be able to allow the utility to
correctly gauge impending costs and recover rightful revenue through tariff. Further changes in terms of
additions/ deletions to this list are necessary to be able to incorporate any new elements or do away with
redundancy.
In India
For regulated transmission licensees, the CERC has defined the consolidated O&M norms covering employee
costs, repair and maintenance costs and administrative and general costs. These norms are defined in terms of:
For transmission lines: INR/route km/year for each conductor configuration, tower configuration and
voltage level; and
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 76
For sub-stations: INR/bay/year for each voltage level (separate norms for HVDC systems).
In addition to O&M norms, regulations also define norms for working capital, auxiliary consumption in sub-
stations, initial spares to be capitalised (with total project cost), etc.
Transmission pricing methodology:
On the overall method adopted for pricing transmission service, it is observed that the current methodology
followed is nationally uniform, flat energy-based charge (also called the postage stamp method) where no
distinction is made between the transactions with regard to the power flow path, distance of power flow,
direction of power flow, supply or delivery points, the time when it takes place etc. Though this methodology is
reasonable in the existing context, further development of the transmission network, electricity markets and
competition will call for a more efficient pricing mechanism.
Select global practices
An efficient transmission pricing regulation should ensure following factors:
Reasonable revenue to the transmission system owners to enable repayment of loans, payment of
interest, return on equity, reimbursement of O&M cost, contingencies, etc.;
Encourage investment in the network and determine optimal location of generation and demand;
Transmission constraints and congestion in the network are properly assessed and addressed;
Proper accounting and allocation of transmission losses; and
Rational sharing of transmission charges and losses among the users.
For developing new mechanism for transmission pricing, ADB has already hired consultants under TA 8203-
VIE who are supporting ERAV in this area.
In India
Since 2011, India has moved from regional postage stamp methodology to simplified nodal pricing (called as the
Point of Connection (PoC) methodology). PoC methodology is used for computation and sharing of the Inter
State Transmission System (ISTS) Charges and Losses among Designated ISTS Customers (DICs) which
depends on quantum of the power flow and location of the node (injection/drawal) in the grid and is sensitive
to distance and direction. Charges would be computed for each node of DICs based on hybrid method. The
hybrid method employs both the average participation method as well as the marginal participation method.
Therefore the existing tariff norms may have to be reviewed by keeping in view the developments in the sector,
current and perceived challenges in the sector and duly recognizing the need for sustainable market
development. Though it is important to maintain regulatory certainty in tariff approach, the tariff should reflect
the changing market conditions as well.
Circular No. 203/2009/TT-BTC dated 20 October 2009 - Guiding the regime of management, use and depreciation of fixed assets
Based on our understanding of the above regulations, key areas of concern are listed below and
select global practices addressing those areas have also been presented.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 77
Depreciation:
The regulation allows for depreciation on re-valued asset base. In this case depreciation is allowed on assets
which have already been fully depreciated once, and thus amounts to abnormal recovery through double
charging of the depreciation. The same also is not in line with the repayment schedule of loans taken.
For e.g. useful life of transmission lines is typically 25-30 years, but for tariff purpose it is taken as 10 years. If
revaluation is allowed, depreciation is charged on the re-valued base for say, another 10 years. This in effect
leads to double recovery of the depreciation for such assets.
The second area of concern is for assets which are not re-valued. The typical life of any fixed asset is considered
to be between 8-12 years while the loan repayment tenure varies between 12-30 years. On the completion of the
life of the asset there will be no revenue (in terms of depreciation payment) to repay the loans for which
repayment of principal component for another 0-18 years is outstanding.
Select global practices
Depreciation is a major component of annual fixed cost (~ 30% in India, ~ 57% in Vietnam) and it is accepted
understanding that the depreciation represents service to capital subscribed and is considered as available cash
flow for repayment of loan (i.e. principal component).
In India
Para 5.8.2 of the National Electricity Policy, provides that “depreciation reserve is created so as to fully meet the
debt service obligation”. The regulatory meaning of depreciation is that there should be enough cash flow
available to meet the repayment obligations of the transmission licensee during the average long term loan
repayment tenure. For example, as per the CERC, the depreciation rate has been considered based on
normative repayment period of 12 years to repay the normative loan (70% of the capital cost). Residual
depreciation payment is spread over the balance life of the asset.
The norms specified by CERC in its tariff regulations, 2014 are as below:
1. Useful life of AC and DC sub-station - 25 years; Transmission line (including HVAC & HVDC) - 35
years; Communication system - 15 years.
2. The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the
Commission. In case of multiple elements of transmission system, weighted average life of the
transmission system shall be applied. Depreciation shall be chargeable from the first year of
commercial operation. In case of commercial operation of the asset for part of the year,
depreciation shall be charged on pro rata basis.
3. The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to
maximum of 90% of the capital cost of the asset.
4. Depreciation shall be calculated annually based on Straight Line Method and at rates specified.
5. Provided that the remaining depreciable value as on 31st March of the year closing after a period of
12 years from the effective date of commercial operation of the station shall be spread over the
balance useful life of the assets.
6. The transmission license, shall submit the details of proposed capital expenditure during the fag
end of the project (five years before the useful life) along with justification and proposed life
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 78
extension. The Commission based on prudence check of such submissions shall approve the
depreciation on capital expenditure during the fag end of the project.
7. In case of de-capitalization of assets in respect of transmission system or element thereof, the
cumulative depreciation shall be adjusted by taking into account the depreciation recovered in tariff
by the de-capitalized asset during its useful services.
Hence depreciation rates are prescribed is such a manner as to allow repayment of the debt component
during the average long term loan tenure and in general practice depreciation is not permitted on revalued
asset base.
In Malaysia
The Energy Commission of Malaysia - Suruhanjaya Tenaga in its regulation namely Electricity Tariff Regulatory
Implementation Guidelines 2012, for the bundled utility TNB, clearly lays down the norms to be followed in
calculating depreciation. The relevant extract from the regulation is as follows:
“Annual depreciation will be based on the efficient economic life of assets. In determining the efficient
economic life for various asset classes (such as transformers, poles, sub stations, switchgear etc.), the
Commission will benchmark with other utilities to ensure that the useful life assumptions are consistent with
best practice. The Commission will also consider obtaining an independent engineering estimate of useful life
for the various asset categories.”
Hence the efficient economic life of the asset is to be based on best practices/engineering estimates.
In Philippines
Depreciation is calculated using the straight line method based on either of the following:
RegDepnj,t = ORCj,t / RegLj,t or ODRCj,t / RemLj,t
Where:
ORCj,t = the optimised replacement cost
RegLj,t = the Regulatory Life of Asset Category
(Is when the economic life of an asset is taken to expire when the costs of maintenance and repair of
that asset exceed the efficient replacement cost)
ODRCj,t = the optimised depreciated replacement cost
RemLj,t = (RegLj,t - Agej,t); and
Agej,t = the weighted average age of the assets
This approach ensures that the asset is fully depreciated at the time its replacement becomes imperative.
The Decision No. 69/2013/QD-TTg of the Prime Minister dated 19 November 2013 - Regulates mechanism for changing of average retail power price.
Based on our understanding of the above regulations, key areas of concern are listed below and
select global practices addressing those areas have also been presented.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 79
TC adjustment mechanism:
Article 4 of the regulation lays down the mechanism for adjustment of electricity retail price. This regulation is
relevant as it has an indirect bearing on the allowable transmission charge, which forms a part of the electricity
retail price.
In case the mechanism of true-up was being systematically followed, the justly allowable cost/ revenue would
have been adjusted to arrive at the true transmission charge. The range specified in this regulation causes
unwarranted reductions in the transmission charge which is not based on the intended regulations specified in
Circular 14.
It is also observed that at present, electricity prices are subsidised for specific categories of consumers by the
Government, but no direct financial support in the form of subsidy is provided to EVN by the Government.
Select global practices
It may not be prudent to link recovery of the transmission revenue through tariff to the allowable recovery of
retail tariff. Based on the various fixed cost parameters, legitimate costs to the utility should be allowed. Only
when the normative and prudent costs are recovered, the transmission licensee will be able to operate more
efficiently. Allowing a sudden increase in transmission tariff may lead to tariff shock, so a separate mechanism
should be designed to allow the remainder of the justified increase in the costs within say, next three years.
The Electricity Law dated 3 December 2004 (amended by Law No. 24/2012/QH13 dated 20 November 2012) - Rules and regulations by which all entities that operate in the electricity sector shall abide by
Based on our understanding of the above regulations, key areas of concern are listed below and
select global practices addressing those areas have also been presented.
Regulatory independence - Article 31 of the Law stipulates guidelines for determination of electricity prices and
associated charges and the bodies who are responsible for its verification and approval. It identifies the
regulating body as a separate entity to that of the concerned ministry namely MoIT. But as on today the ERAV
is an integral part of the Ministry and does not wield any decision making of its own. The lack of an
independent regulating body might cause the price determination process to be driven by factors other than as
stipulated in Circular 14.
Select global practices
The very purpose of a regulator is to be able to undertake an independent evaluation of the tariff petition. The
Regulatory Commission is responsible to balance out the interests of both the transmission licensee as well as
the consumer. It is bound to function without any political influences.
In India
The Central Electricity Regulatory Commission (CERC) and the State Electricity Regulatory Commissions
(SERCs) are independent quasi-judicial regulatory bodies that are promulgated under the Electricity Act 2003.
They are separate legal entities and are not part of the Ministry of Energy / Power. This separation is very
crucial to ensure least amount of direct political influence as well as to ensure independent fulfilment of their
powers and duties.
In Thailand
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 80
The Energy Regulatory Commission of Thailand (ERC) is appointed by the King of Thailand as the independent
regulatory agency. State-owned utility, EGAT files the transmission pricing petition directly to ERC.
In Malaysia
The Malaysian Government established the Energy Commission (Suruhanjaya Tenaga) as autonomous body
under the Energy Commission Act 2001. Integrated utility, TNB files the transmission pricing petition directly
to Energy Commission of Malaysia.
In Philippines
Enactment of the Republic Act No. 9136, otherwise known as the Electric Power Industry Reform Act (EPIRA)
of 2001 saw the creation of the Energy Regulatory Commission (ERC) which is a purely independent regulatory
body performing the combined quasi-judicial, quasi-legislative and administrative functions in the electric
industry. The TRANSCO must directly submit to the ERC, its proposal for the maximum transmission wheeling
rates that may be charged by it for the relevant year.
Practice followed in Vietnam
The following table captures the various capital costs and operating costs which form the basis for arriving at
the Total Power Transmission Revenue of the EVNNPT. The contribution of each of these items towards the
TPTR and their treatment is as follows.
Sr. No.
Cost element PwC analysis and observations
A Capital cost items
1. Depreciation Asset life considered is too short causing excess revenue recovery through depreciation
Mismatch in depreciation and loan repayment structure
Assets re-valued once initial life term is over and allowed another full term for depreciation
Full depreciation allowed on revaluated assets causing over recovery through depreciation
ERAV having no control over investment approvals has limited or no control over this cost element
2. Interest charges There is no standard stipulated for the debt:equity ratio. But the attempt is to move towards a 70:30 scenario
3. Return on equity There is no standard norm for allowing RoE
For 2013, no RoE was approved, but the attempt is to move towards a 4%-6% rate of return
RoE is very essential to enable self-financing of projects
Equity base taken by ERAV, for the purpose of allowing RoE, includes increase in equity on account of revaluation of assets. In other countries (including India), RoE is not permitted on such additional equity from revaluation
B Operating cost items
4. Material costs NPT, being relatively new entity, lacks historical cost data which are needed for framing norms
Cost norm used to setting material costs are based on norms issued by EVN in 2006
These norms do not reflect the trends in the current prices, nor is the list comprehensive covering all relevant items
5. Salary costs Salaries are determined in accordance with MOLISA regulations and ERAV / EVNNPT has very little control over it
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 81
Sr. No.
Cost element PwC analysis and observations
Salaries are linked to labour productivity (kWh/employee/year) which may not be a fair indicator of performance. As this rate can vary with reduction in labour size it does not necessarily translate to increased productivity
Salary increase is constrained at (0.8 x productivity growth + 0.3 x profit growth); In FY13, it was calculated at (0.8 x productivity growth) since profit allowed was nil
6. Major repairs costs
NPT, being relatively new entity, lacks historical cost data which are needed for framing norms
Cost norm used to setting major repair costs are based on norms issued by EVN in 2006
These norms do not reflect the trends in the current prices, nor is the list comprehensive covering all relevant items
Allowed costs of major repairs is capped at 0.8% x asset value in year N-3; Basis for this provision needs to be re-evaluated
7. Outsourced service costs
No standard methodology adopted for appraising these costs, they are taken as per the audited accounts of previous year adjusted for the present year
8. Other expenses in cash
There is no hedging done to safeguard against foreign exchange losses
NPT can recover its realised foreign exchange losses
Part of the accumulated losses has been allowed to be recovered whereas balance is carried forward over future years to avoid tariff spike
The capital cost items comprise about 75-80% of the total revenue requirement, but ERAV has no control over
the approval of investments which may lead to allowing costs of unnecessary or inefficient investments. In
addition, there are several areas in the regulations as well and their interpretation which need considerable
thought and improvisation. These changes are imminent and will ensure better performance of the utility and
will also be an indicator of the direction in which the electricity market and overall power sector is heading to.
Comparison of Transmission costs as per the petition submitted by EVN for 2013 vis-à-vis costs as per the
audited financial statements (VAS) of EVNNPT throws light on the variations in the actual costs versus the
quantum passed onto consumers as part of the TPTR.
Comparison of Transmission costs as per the EVN petition vis-à-vis costs as per audited
financial statements (VAS) of EVNNPT for 2013 (million VND)
Particulars As per petition As per Audited accounts (VAS)
Capital costs
Depreciation 4,914,304.00 49.2% 5,885,723.03 62.3%
Interest 1,816,054.00 18.2% 1,305,140.12 13.8%
Profit (RoE) 120,341.00 1.2% 134,998.89 1.4%
Capital cost Total 6,850,699.00 68.6% 7,325,862.04 77.5%
Operating costs
Salary 1,247,079.00 12.5% 1,239,093.95 13.1%
Major Repairs 331,212.00 3.3% 277,242.19 2.9%
Materials 135,114.00 1.4% 148,496.39 1.6%
Outsourced Services 149,659.00 1.5% 146,068.53 1.5%
Other (incl. forex loss) 1,284,128.00 12.8% 312,780.65 3.3%
Operating cost Total 3,147,192.00 31.4% 2,123,681.71 22.5%
Total cost 9,997,891.00 100% 9,449,543.75 100% Note: Excludes interest income and unrealised forex loss
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 82
The above table clearly reflects the variances in the various cost components as incurred by EVNNPT and as
claimed in the TPTR petition. Huge variance is observed in Depreciation as well as under the other costs head
which includes forex losses. Depreciation on revalued assets has not been included in the calculation of TPTR
for FY13 which is why the total depreciation value is lower than that as stated in the annual audited accounts.
Similarly the other costs which includes forex losses of previous years to be recovered over a term of 5 years is
included in the cost for FY13 in the TPTR calculation as against such expenses stated in the annual audited
accounts.
Structure
Following are the key departments involved in the transmission pricing process:
1. Corporate Planning Department (CPD): Responsible for preparation of the transmission
pricing petition and submission to EVN for approval. CPD takes support from other departments
for procuring the relevant information to develop the petition.
2. Finance and Accounting Department (F&AD): This department is responsible for
supporting the CPD in the transmission tariff determination process by providing necessary
financial information based on the method of calculation stipulated in Circular 14
3. Technical Department (TD): The Technical Department is responsible to provide support to
CPD in the preparation of transmission pricing petition by providing technical information relevant
for calculation the penalty for failed service quality.
4. Organisation, Personnel & Labour Department (OPLD): This department provides
information about employees and associated expenses and cash expenses to the F&AD.
5. Power Transmission Company 1 (PTC1): The Planning Department and F&A Departments
are responsible for providing information to EVNNPT upon request.
The overall alignment of departments for undertaking the process of preparation of the transmission pricing
petition appears to be reasonable. However given an understanding on the nature of data / information to be
submitted by each department to CPD and the average time taken by CPD for preparation and submission of
the petition, it would be useful to determine internal timelines to be followed for submission of data by various
departments to CPD.
Also information to calculate failed service quality is not being provided by the TD, as relevant data is not
adequately captured and the standards of performance to determine penalty has also not yet been decided. This
is a key aspect that drives performance of the transmission licensee and it should be a mandatory requirement
to undertake determination of service quality. An incentive mechanism parallel to the existing penalty
mechanism might help in motivating the licensee towards recording of relevant information. The ERAV as the
regulator of the sector should also promulgate relevant regulations that stipulate the required service quality,
the measure of penalty for various points of system failure etc.
Processes
The transmission pricing function consists of three key processes namely (a) Submission of petition; (b)
Approval of petition; and (c) Billing & payment. Sub-processes (a) and (b) are divided in to two parts viz.
procedure for determination of total power transmission revenue and procedure for determination of
transmission charge. In addition, the process stipulated for determining penalty for failure to maintain service
quality is also detailed owing to its importance, but is not currently being followed by EVNNPT.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 83
Procedure for determination of Total Power Transmission Revenue (TPTR)
The process to be followed for submission, review and approval of the Total Power Transmission Revenue
(TPTR) is as below:
1. Step 1: The National Power Transmission Corporation (NPT) prepares the appraisal document of
Total Power Transmission Revenue for year N and submits it to the Vietnam Electricity (EVN) for
consensus.
2. Step 2: EVN undertakes a preliminary scrutiny of the submission made and incorporate
alterations that it deems fit. It then forwards the document to the Electricity Regulatory Authority
of Vietnam (ERAV) for assessment and final approval in writing before the fifteenth day of every
May (of the year N). In case of necessity, the ERAV can utilize consultants for assessment of the
submissions for total transmission revenue of the EVNNPT.
3. Step 3 (a): Based on the assessment of the ERAV if the submission is not eligible in accordance
with the Article 17 of the Circular No. 14 (as amended), the submission is remanded back to the
EVNNPT for revision;
4. Step 3 (b): The EVNNPT then supplements and finalizes the document within five (05) days upon
receiving the request of the ERAV and resubmits the same.
5. Step 4: Based on the assessment of the ERAV if the submission is eligible then, before the tenth
day of every June (year N) the final written approval authorizing the permitted Total Power
Transmission Revenue of year N of the EVNNPT is issued.
NPT EVN
1. Submission of appraisal doc
of Total Power Transmission Revenue for year N
ERAV
3a. Submission Not eligible, remand back
to NPT
3b. Supplement and finalize
the submission
Assessment of the (revised)
submission
Assessment of the submission
(alteration possible)
2. Forward for final assessment
and approval in writing
Consultant
4. Submission eligible
Written approval of the permitted Total Power Transmission Revenue of year N of
NPT
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 84
Documents to be submitted for approval of Total Power Transmission Revenue
The following submissions along with detailed assessment of the Total Power Transmission Revenue for year N
are submitted by the EVNNPT for approval.
1. Petition of Total Power Transmission Revenue of year N from EVNNPT.
2. Explanations and calculation sheets of Total Power Transmission Revenue of year N, including:
a. Analysis and assessment of the implementation of the assigned targets for power output, the
rate of transmission loss, faults of transmission line and transformers at various voltage levels;
b. The actual revenue and expenses incurred as at March 31st of year N;
c. Assessment of the profit, equity and financial indicators such as the ratio of return on equity,
debt equity ratio, self-financing ratio as at 31 December of year N-1;
d. Explanations and calculations of total capital expenses including calculation of depreciation
costs, long-term loan interest expenses, Equity as at the end of year N-1 and estimated equity
by end of year N and estimation of profit for year N;
e. Explanation and calculations of total permitted operating cost of year N including calculation of
material costs, salary costs, costs of repairs and overhaul, cost of outsourcing services and other
monetary costs of year N;
f. Explanation and calculation sheets of the difference in transmission cost and revenue of year
N-1; report on increase/decrease of the difference between transmission cost and revenue.
3. Supporting documents include:
a. List of investment projects which have been completed and put into operation until the report
time and estimated in year N in accordance with the National Power Development Master Plan
and approved annual grid expansion plan of the National Power Transmission Corporation;
b. List of items and values of fixed transmission assets which have been increased, decreased as of
December 31st of year N-1 and until March 31st of year N and estimated amount by month for
year N. For the assets which have not been put into operation, there shall be details of the
networks and other assets which include values of the assets;
c. Summary table indicating the change of regular labour in the payroll of the EVNNPT and
relevant units in year N-1 and schedule of this item for year N;
d. Summary of standby materials available and supplemented in year N-1 and expected in year N;
e. List of major repair items of fixed asset of year N-1 and estimated list of year N;
f. Financial Statement of year N-1: balance sheets, report on production and business results,
report on cash flows and financial disclosures;
4. Cost norms for expense items used in the documents approved by relevant authorities.
Key timelines specified for this procedure and actual adherence:
Activity As per Circular Actual (last cycle)
Submission of TPTR doc to EVN by EVNNPT Not defined 1 Nov’13
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 85
Activity As per Circular Actual (last cycle) Submission of TPTR doc to ERAV by EVN 15 May 14 Jan’14
Issuance of decision by ERAV 10 Jun 19 Mar’14
Procedure for determination of Transmission Charge (TC)
The process to be followed for submission, review and approval of the Transmission Charge (TC) to be in force
between July 1st of year N and June 30th of the following year, for each unit subject to pay transmission charge
is depicted below. The latest transmission charge petition dated 14th January 2014, filed by EVN to ERAV
indicates the change in the tariff cycle hence forth to be from 1st January to 31st December of any given year.
Also, as of now, EVNNPT computes transmission charge just dividing total revenue (in VND) by output energy
(in kWh) and does not follow the below mentioned elaborate process due to lack of adequate data.
1. Step 1: Before the fifth day of every January (year N), payers of transmission charge are
responsible for sending data of actual maximum capacity and actual delivered energy at each
delivery points of year N-1 to the EVNNPT.
2. Step 2: Before the first day of every April (year N), payers of transmission charges are responsible
for preparing and sending the forecast of energy delivery and total maximum capacity at all delivery
points of year N to the EVNNPT.
3. Step 3: The EVNNPT is responsible for consolidating and calculating the forecast of total energy
delivery and total maximum capacity of each unit subject to pay transmission charge and sending
the forecast results to the System and Market Operator for its comments.
In case a payer of transmission charge fails to send the forecast data, the EVNNPT can use the data
of year N-1 as the basis for calculating transmission charge for year N.
4. Step 4: Before the first day of every June (year N), the System and Market Operator is responsible
for sending its comments in writing on the forecast of energy delivery and total maximum capacity
of year N of each unit subject to pay transmission charge to the EVNNPT, to enable it to form the
basis for calculating price and transmission charge of year N for each such unit.
5. Step 5: Before the fifteenth day of every June (year N), the EVNNPT is responsible for determining
the transmission charge to be applied between July 1st of year N and June 30th of the following
year (N+1) for each unit subject to pay transmission charge (based on the approved transmission
revenue of year N and adjustment amount of year N-1), and submit the same to the EVN for
consensus.
6. Step 6: EVN upon scrutiny of the submission will forward the same to the ERAV for final scrutiny
and approval.
7. Step 7 (a): Based on the assessment of the ERAV if the submission is not eligible in accordance
with Article 19 of the Circular No. 14/2010/TT-BCT (as amended), the submission is remanded
back to the EVNNPT for revision.
8. Step 7 (b): The EVNNPT then supplements and finalizes the document within five (05) days upon
receiving the request of the ERAV and resubmits the same.
9. Step 8: Based on the assessment of the ERAV if the submission is eligible then the final written
approval authorizing the permitted Transmission charge of year N to be applied between July 1st of
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 86
year N and June 30th of the following year, for each unit subject to pay transmission charge to the
EVNNPT is issued.
NPTEVN
5. Submission of calculation of
transmission chargefor year N
ERAV
7a. Submission Not eligible, remand back
to NPT
7b. Supplement and finalize
the submission
Assessment of the submission
6. Forward for final assessment
and approval in writing
8. Submission eligible
Approval of the transmission charge (July 1st of year N and June 30th of the following year) for each payer of transmission
charges
Payers of Transmission
charge
1. Data on max capacity and actual delivered energy (N-1)
2. Forecast on max capacity and delivered energy (N)
SMO3. Consolidation and submission
of forecast of energy delivery and total maximum capacity of each payer of TC
4. Comments on the forecast of energy delivery
and total maximum capacity of year N
Documents to be submitted for approval of Transmission Charge
The following submissions along with detailed analysis and assessment are submitted by the EVNNPT for
approval of the Transmission Charge for year N:
1. A petition requesting for approval of transmission charge.
2. Explanation and calculation sheets of transmission charge of each unit subject to pay transmission
charge, including:
a. Capacity transmission charge, energy transmission charge;
b. Total maximum delivery capacity, total forecasted energy output of each unit subject to pay
transmission charge at all delivery points of year N;
c. Total adjusted amount of transmission cost of the unit subject to pay transmission charge in
year N-1 (detailed calculation sheets).
3. Supporting documents, including:
a. Forecasted energy output and total maximum capacity of year N of each unit subject to pay
transmission charge prepared by the System and Market Operator;
b. Data of total actual maximum capacity and actual energy delivery at each delivery point of year
N-1 of each unit subject to pay transmission charge.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 87
Key timelines specified for this procedure and actual adherence:
Activity As per Circular Actual (last cycle)
TC payers to send actual for (N-1) to EVNNPT 5 Jan Not in practice
TC payers to send MW / MWh forecasts (N) to EVNNPT 1 Apr Not in practice
SMO to send comments to EVNNPT on MW/MWh 1 Jun Not in practice
NPT to determine TC 15 Jun 1 Nov’13
NPT to finalise TC In 5 days NA
In practice the above two processes (viz. determination of total power transmission revenue and determination
of transmission charge) are not undertaken separately but as a single submission and ERAV issues a
consolidated decision (tariff order) covering both components.
It is observed that, in the process of filing the TPTR and TC petition the EVNNPT submits the petition to EVN
which then forwards the revised petition to ERAV for scrutiny and approval. This process of submitting the
petition to EVN in the process of tariff determination is not ideal and compromises the independence of
EVNNPT. EVN to balance out the interests of the transmission and distribution utility undertakes reduction of
some of the cost components in a non-scientific manner. Thus it seems redundant and non-beneficial to submit
the petition to EVN for approval before forwarding it to ERAV for approval. This existing mechanism might also
lead to inflating of the cost components by the EVNNPT to provide some buffer in the event of reduction by
EVN, thus making the entire regulatory process not accurate and counterproductive.
Procedure for Billing and Payment of Transmission Charge
The process to be followed for billing by the EVNNPT and payment by the users of transmission system is as
follows. However, in practice, this process is not being strictly followed. As per the current practice, EPTC pays
transmission charges to EVNNPT and distribution companies are not paying the transmission charges to
EPTC/NPT.
The Electric Power Trading Company (EPTC) is responsible for paying the total power transmission charge to
EVNNPT. Payers of power transmission charge are responsible for paying transmission charges to EPTC.
1. Step 1: Prior to the 10th day of each month (month T), the EVNNPT is responsible for sending to
the EPTC, the documentation for payment of transmission charges for the previous month (month
T-1 of each payer of transmission charge and total monthly transmission charge of month T-1 of all
payers).
In case any mistakes are detected or the document is incomplete, within ten (10) days from the date
of receipt of such payment documents, the EPTC must notify the EVNNPT in writing for
rectification of mistake or addition of missing information.
2. Step 2: Prior to the 15th day of each month (month T), the EPTC is responsible for making
advance payment of transmission charge of month T-1 to EVNNPT of an amount equal to 50% of
the total transmission charge defined in the payment documents of month T-1.
3. Step 3: Prior to 20th day of each month (month T), the EVNNPT sends bills for total transmission
charge of month T-1 to the EPTC (in attachment with complete payment documents in case of
additions or rectification).
4. Step 4: Prior to 5th day of next month (T+1), the EPTC needs to make payment of the outstanding
transmission charge of month T-1 to EVNNPT as per issued bills.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 88
Where data in the bills are different from the data notified by EVNNPT, the EPTC is responsible for
paying the value billed by EVNNPT. Payment for the difference is agreed by both parties in their
contract.
NPT
Payers of Transmission charge
(power companies, bulk users)
Electric Power Trading Company
(EPTC)
1. Documentation for payment of transmission charge for the
previous month (T-1)Payment of
monthly transmission
charge
2. Advance payment of 50% for month T-1
3. Invoice for payment oftotal transmission charge
for the month of T-1
4. Payment of balance amount for month T-1
At this point in time, only the distribution utilities pay transmission charges and generators are not liable to pay
any charges. This charging principle has to be relooked at. A change in the billing and payment process is
suggested from 2014 onwards. It is indicated that EPTC might request and receive money from EVN to make
payment to EVNNPT and then undertake a settlement with EVN for the same.
In India the EPTC does not have any role in the billing and payment cycle between the transmission utility and
its customers. The long term beneficiaries of the system like the distribution utilities pay their monthly dues to
the transmission utility based on long term capacity charges determined and in turn recovers the same from the
retail tariff it charges to its consumers. The short term consumers of the system pay as per usage in terms of
energy.
Procedure for actualisation of penalty for failed service quality
The process to be followed by EVNNPT for reporting statistics on incidents of faults/outages in the
transmission lines and transformers, to the Operator of the power network and the national electricity market is
as follows:
1. Step 1: Prior to first day of October, each year (year N), the EVNNPT must report statistics of to
the Operator of the power network and the national electricity market, on incidents of transmission
lines (power failure time ti and length of troubled line Li,N for each incident) and incidents of
transformers (power failure time ti and total MVA capacity of the troubled transformer Si,N for
each incident) of the transmission grid from September 1st in N-1 to 31st August of year N.
2. Step 2: Prior to first day of November each year (year N), the Operator of the power network and
the national electricity market is responsible for examining and authenticating the statistical report
on incidents of transmission lines and transformers and submits a report on the same to ERAV.
3. Step 3: Operator of the power network and the national electricity market also send a copy of the
report to EVNNPT to have a basis for calculating penalties for failed service quality in year N.
4. Step 4: Prior to first day of December each year (year N), the EVNNPT is responsible for providing
justification of statistics to ERAV on incidents of transmission lines and transformers from 1
September of year N-1 to 31 August of year N.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 89
5. Step 5: EVNNPT is required to calculate penalties for failed service quality of year N and submit
them to EVN for review.
6. Step 6: Post review, EVN will submit the final penalty calculations to ERAV for approval.
NPT SMO1. Report statistics
on incidents of system failure
ERAV
4. Providing valid justification for
the statistics
Examination & Authentication of the
statistical report
2. Report the statistics
3. Send final copy to have a basis for calculation
of penalty for year N
EVN
5. Submission of final penalty
calculations
6. Submission of penalty calculation for final approval
In practice the above process relating to calculation of penalty for failed service quality is not being undertaken
by EVNNPT as specified by the regulations. The above is an illustration of the process laid down in the
regulation. This is a key aspect that drives performance of the transmission licensee and it should be a
mandatory requirement to undertake determination of service quality. An incentive mechanism parallel to the
existing penalty mechanism might help in motivating the licensee towards recording of relevant information.
The ERAV as the regulator of the sector should promulgate relevant regulations that stipulate the required
service quality standards, the measure of penalty for various points of system failure etc.
People
CPD does not have adequate manpower with necessary skills to undertake the task of preparing the
transmission charge petition. As of now, 2 staff members have been assigned the task of preparing the
transmission charge petition. There is also the need for enhancing understanding on regulatory & tariff
economics among staff. Because of the non-allocation of sufficient staff with necessary skills the quality of the
petition has significant scope for improvement. The same is the case with the MS Excel based formats which
accompanies the petition.
Department / Entity No. of staff assigned Designation of staff
CPD (NPT) 2 1 - Deputy Director Business Operations 1 - Expert
Finance (NPT) No specific staff assigned -
Technical (NPT) No specific staff assigned -
Organisation, Personnel & Labour (NPT)
3 1 - Deputy Director 2 - Experts
PTCs No specific staff assigned -
PMBs Not involved in the process -
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 90
Technology
The review of existing data sources, IT tools, information etc. has shed light on the method of filing of the
transmission pricing petition by the EVNNPT. Based on the information studied so far, the EVNNPT files single
petition for approval of total power transmission revenue and transmission charge. The petition which is a
written submission to EVN/ERAV is accompanied by MS Excel formats supporting the calculations made.
Key software tools / MS Excel models / system used
Name of software tools / MS Excel models / system
Brief description / features / functionalities
PwC analysis and observations
MS Excel Formats Workbook containing detailed calculations of the various financial and other parameters supporting the determination of the transmission revenue and charge. For the future years it also captures scenarios based on target SFR and target DSCR.
Based on a thorough assessment it can be said that the formats are not as comprehensive and easy to understand as it ought to be in terms of capturing information about all major annual revenue components involved in the determination of the transmission charge and inter-linkages among components.
o For example: details about asset wise major repairs or information on outsourced expenses are not detailed.
Some discrepancies have also been identified in calculations in the formats, for which detailed clarification from the F&AD and OPLD is still awaited.
Select global practices
In India, the regulatory commissions design the standard formats in MS Excel that the licensees have to
populate with relevant information and submit along with the written petition. This method ensures that the
Regulator gets all the relevant information and in the detail that it seeks. This enables through prudence check
as well as clear case for allowance or disallowance depending on the expenditure proposed.
Key information / data received from various departments/entities:
Description of information / data Source department and entity
PwC analysis and observations
Financing cost - Total long-term loan interests and charges for borrowing capital defined in accordance with loan agreements for transmission assets.
F&A Department, EVNNPT
The data is being provided to the CPD but further detailed break up of each cost item should be given. Scrutiny of costs in terms of them being justly incurred, details on time and cost overruns etc. should be the basis for allowing or disallowing cost rather than total disallowance of RoE or other components to keep the charge within a desirable limit
On assessment of data provided by other departments to CPD, it was gathered that
Depreciation cost - Determined according to the life time and method of depreciation of fixed assets stipulated in Circular No. 203/2009/TT-BTC dated 20 October 2009 of the MoF guiding the management, use and depreciation of fixed assets and the subsequent replacement
F&A Department, EVNNPT
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 91
Description of information / data Source
department and entity
PwC analysis and observations
Eligible profit - Determined based on the average equity capital of the present (N) and previous year (N-1) multiplied by the Return on Equity rate
F&A Department, EVNNPT
there was no issue with regards to quality and availability of data. It was also observed that the basis for computing some data needed immediate updating. For example: the cost list used by EVNNPT for assessment of various cost items is very outdated and is lacking with new additions. This needs immediate attention as it definitely will cause skewed assessment of cost parameters
Estimation of the Operations & Maintenance costs
F&A Department, EVNNPT
Data for calculation of the penalty for failed service quality
Technical Department, EVNNPT
As of now, no penalty is being calculated as the relevant information is not being provided by the Technical Department.
Information on maximum transmission capacity and actual energy received at each delivery point of the previous year and forecast for the current year is provided to CPD by the payers of transmission charge
Payers of transmission charge
As of now historic information validated by the NLDC is used for forecasting maximum transmission capacity and actual energy received at each delivery point for the current year.
The quality of data provided by other departments to CPD is adequate as long as information being provided is
historic data which lacks ambiguity. The challenge arises when the data to be provided is futuristic and that
which involves forecasting. Different departments have been following different methods to arrive at such data,
for example - CPI, future growth rates, forecasted volume of work after commissioning of asset, forecasted data
on line and sub-station outages etc. Hence multiple departments have different values of the same parameter.
Even though these differences are reconciled by the departments through a meeting, a better approach would
be to standardise the approach to be followed by all departments for calculation of such parameters. This would
not only bring clarity but would also ensure ease of calculations and avoid corrections.
Summary of key observations
In the following section, we have summarised our key observations:
Strategy related
Inadequate recovery of expenses and negligible Return on Equity
1. The cost coverage in FY13 is 1.01 times
and RoE allowed was zero, which
impairs generation of adequate
internal resources which are needed
for self (equity) funding of future
projects. This seems inadequate as
compared to 15.5% post tax returns in
India. In 2014, allowed RoE was just
1% converting to a post-tax RoE of
0.75%.
0.2
9%
0.5
9%
4.0
0%
0.2
9%
0.0
0%
1.0
0%
0%
2%
4%
6%
8%
10%
2012 2013 2014
RoE (Proposed) RoE (Approved)
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 92
2. Even Self Financing Ratio (SFR) and
DSCR were not favourable during
2009-11, although they improved in
2012 due to revaluation of assets
(increase of 15,277 billion VND in
asset value). Regulation stipulates,
RoE should be allowed to achieve
SFR>25% & DSCR>1.5.
3. NPT is eligible to claims RoE in its
transmission charge petition, but it
may or may not be allowed by the
ERAV in the final tariff order. The
concept of including RoE as an element in the overall estimation of transmission revenue is to allow
a viable return to the utility beyond the actual costs incurred. For the current year (FY14) tariff,
ERAV has approved a 1% RoE to be recovered through transmission charge.
4. The current transmission charge recovers a very negligible rate of return on equity typically causing
the retained earnings of the EVNNPT to be zero. Without retained earnings, the EVNNPT would
find it difficult to undertake self-financing of projects. As per the requirement of domestic banks in
respect of funding of any investment project, the debt:equity ratio should be around 60:40 to
80:20. EVNNPT through revaluation of assets is attempting to project a higher equity composition
in its capital structure.
5. There is no support from the Government to EVNNPT by way of grant or subsidy. There is no
equity infusion in the EVNNPT from the parent company (EVN) to meet its fund requirement for
funding capital expenditure. A book adjustment in the equity head is done when at the end of the
financial year there is some profit booked and a portion of that is required to be transferred to the
parent company (EVN). This transferred amount is adjusted against the increase in equity fund.
True-up (adjustment) mechanism
1. The formula for calculating total transmission revenue allows for adjustment true-up of cost and
revenue of year N-1 to be considered in year N. But this provision is merely on paper and ERAV has
not undertaken adjustment of such past expenses and costs till date. Further, regulation does not
specify controllable and uncontrollable expense items, which would be good indicators to EVNNPT
to be prudent and efficient in expenses. Thus there is no mechanism which enforces the need to be
prudent and efficient in incurring capex and opex as well as adjustment for over/under recovery of
revenue. Timely true-up will help EVNNPT recover justifiable revenue and retain efficiency gain
(positive difference between allowed cost and actual cost).
2. The mechanism of allowance and disallowance of cost items should be based on the principles of
controllable and uncontrollable costs rather than arbitrary judgement based on the final retail tariff
to be imposed. On one hand, elements like RoE are completely disallowed and on the other hand,
over-recovery through depreciation on re-valued asset is allowed. This imbalanced approach will
not give the utility any incentive to improve its functioning efficiency and may create financial
imbalances in the future.
3. Further even such adjustments would not guarantee full true-up of justifiable increase in costs.
Decision No. 69/2013/QD-TTg dated 19 November 2013, lays down certain range of increase in
average electricity selling price due to similar adjustments in the retail electricity selling price and
the process for its approval. An increase in average electricity selling prices by 10% or more calls for
9.82%
18.04%
9.40% 10.56%
1.47
1.90 2.36
1.58
0.0
0.5
1.0
1.5
2.0
2.5
0%
5%
10%
15%
20%
25%
30%
2012 2013 2014
SFR (Proposed) SFR (Actual)
DSCR (Proposed) DSCR (Actual)
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 93
the EVN to seek approval from the Prime Minister. This decision might have a direct impact on the
increase allowed in the transmission charge.
Depreciation charge
1. Depreciation is a major component of revenue (~62% in Vietnam, ~30% in India). Investments
drive the depreciation costs; ERAV, which has very limited or no control over EVNNPT investment
approvals, seems to have no control over this cost item. Regulation allows for depreciation on
revaluation reserve, although it was not allowed by EVN / ERAV while approving the revenue
requirement for 2014. As per audited VAS 2012, ~ 2,000 billion VND (95 million USD) was
recognised. Such approach may result in mismatch between depreciation revenue and loan
repayment as average asset life is 8-12 years but loan repayment tenure varies 12-30 years. First 12
years if the depreciation revenue is greater than Loan (principal) repayment then this generates
surplus cash, which seems to be deployed in capital projects as ‘equity’. After 12 years the loan
repayment continues but no depreciation revenue is accrued, which will affect the loan repayment
capacity of EVNNPT. A study of future depreciation revenue v/s loan repayments is crucial to
ascertain the impact of this mismatch.
Composition of transmission charge
1. As per the regulation, the TC is currently a completely “energy-based charge”. It is pertinent to note
that any transmission system is built to cater to the maximum demand and evacuate available
generation and thus should entail full recovery irrespective of actual energy flow. In case of
“energy-based charge”, there is no certainty to recover full approved revenue, as the actual energy
transmitted may vary from the projected energy. Setting positive value of ‘α’ will reduce revenue
recovery risk to EVNNPT.
Loss due to forex variation
1. At present, EVNNPT does not have hedging against the risk of foreign exchange fluctuations which
causes huge losses to EVNNPT. As per the balance sheet of EVNNPT, there is no loss in past years
despite the fact that EVNNPT is not allowed to recover RoE. The reason being that EVNNPT is not
charging the entire foreign exchange fluctuation loss/ expenses in one year. They are allowed to
carry forward the loss/ expenses over the next 5 years. Due to the flexibility allowed to EVNNPT in
respect of not showing the forex fluctuation losses/ expenses in one year, they are able to show
profit in their financial statement and are paying income tax on this book profit. This is a further
erosion of funds which is not available in reality.
2. Forex loss is a real loss and must be allowed to be claimed in respective year’s revenue. ERAV
allows recovery of only realised forex loss but not the unrealised forex loss. There is no clear
mechanism/timelines for recovery of accumulated forex loss. Total loss from allocated exchange
rate differences (as on December 2012) was around 2,013 billion VND (96 million USD). This was
proposed to be liquidated in equal instalments in 2013, 2014 and 2015 (i.e. 671 billion VND per
annum). However, in 2014, ERAV has allowed only 241 billion VND of forex loss. EVNNPT
currently does not have any hedging mechanism against the risk of forex loss. If EVNNPT opts for
any such mechanism in future, the cost of procuring such instrument(s) shall be allowed in the
revenue requirement.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 94
Penalty for failed service quality
1. Regulation specifies mechanism of imposing penalty for failed service quality but it is not in
practice. This is because of inadequate data about outages and lack of penalty norms. For example -
Timing of outage and restoration of lines and transformers with precise reasons. Penalty norms for
outage of line and transformers at 110 kV, 220kV, 500Kv need to be clearly defined. Further
penalty is levied through deduction of equivalent from the EVNNPT’s Welfare Fund. Welfare Fund
has been created to take care of employee welfare needs such as bonus, social benefits to
employees, recreation and entertainment, etc. This approach seems to be penalizing all staff
members who might not be in any way related to the process of managing the service quality.
Regulation does not also provide for any specific incentive in case of efficient performance by
EVNNPT.
Cost norms
1. Cost norms are the basis for calculating the material costs and major repair costs (which are
components of the operating costs in the total transmission revenue). The cost norms currently
used by EVNNPT were developed by EVN in 2006. There is no mechanism to adjust existing cost
norms to reflect inflation, technological improvement etc. Further, it also does not contain certain
cost items which today form part of the overall cost. For example: EIA study, engineering /
management software, fire prevention systems, propaganda systems, communication systems etc.
Cost of major repairs is capped at 0.8% of asset value in Year N-3, which needs review. Once norms
are implemented, EVNNPT should be allowed to retain any savings on account of difference
between allowed cost (normative) and actual cost (audited). Scientifically developed norms will
drive reduction in operating costs.
Transmission pricing methodology
1. The current methodology followed is nationally uniform, flat energy-based charge. It does not
reflect power flow path, distance, direction, delivery points, time of usage. Though this
methodology appears to be reasonable in the current context, it may not be adequate in light of;
a. Massive growth of the transmission network in coming years
b. Emergence of wholesale and retail competitive electricity markets
c. Probable private sector participation
2. An efficient yet simple methodology will help promote market development.
Process related
Delay in filing of the transmission tariff petition
1. It was derived that there have been time lags at EVN’s end and/or at EVAR/MoIT end in processing
of the petition for transmission charge submitted by EVNNPT. Such delays may cause unnecessary
complexity in terms of delayed recovery of new charge by EVNNPT and would trigger adjustment
in the next cycle. Delay in notification of retail prices impacts transmission price finalisation.
2. There have been instances when the Government has decided to postpone the processing of the
petition for the electricity retail charge to the next year instead of the current year based on
prevailing macro-economic environment. For example, MoIT Decision No. 38/2012/TT-BCT dated
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 95
20 December 2012 (retail electricity tariff effective December 2012) was issued after a gap of almost
22 months from the Prime Minister's Decision No. 268/QD-TTg dated 23 February 2011 (retail
electricity tariff effective February 2011). This approach causes undue strain to EVNNPT as it would
be unable to recover any additional costs incurred/ to be incurred in the current year.
3. The process of filing TPTR and TC should be synchronised in the regulations. The process of
payment of transmission charges is currently not as stipulated in the regulation; this provision
should be updated in the regulation as per the revised practice proposed.
Powers of EVN in transmission pricing determination process
1. It has been observed that EVNNPT does not have full autonomy to determine its revenue
requirement; it has to be channelled through EVN. It seems EVN significantly modifies
revenue/price proposed by EVNNPT before its submission to ERAV. In 2014, EVN curtailed
EVNNPT’s proposed revenue by 22% and allowed only 1% RoE (instead of 4% as proposed by
EVNNPT). It appears ERAV also does not have powers to review investments proposed by
EVNNPT.
2. The table below captures the disallowance of revenue and expenses by EVN for 2014.
Item Power transmission tariff in 2014 (petitioned by EVNNPT)
Power transmission tariff in 2014 (reviewed by EVN)
Disallowance in %
Million VND
Power transmission output (Million kWh)
123,345 122,200 0.9%
Power transmission tariff 109.9 86.4 21.4%
Revenue 13,556,849 10,552,297 22.2%
Expenses 12,670,971 10,342,306 18.4%
Materials 166,133 140,148 15.6%
Salary and social insurance 1,390,407 1,356,838 2.4%
Depreciation of fixed assets (excl. revaluation of fixed assets)
6,506,645 6,004,235 7.7%
Outsourced services 202,188 50,360 75.1%
Major repair expenses 381,060 381,060 0.0%
Cash expenses 2,486,621 2,387,101 4.0%
Increases and impairments in electricity price
1,537,917 22,564 98.5%
Profit from power production and trading (1% of state capital)
885,878 220,000 75.2%
EVN made considerable changes in the numbers submitted by EVNNPT. Overall reduction was to the tune of
22% in the revenues and 18% in the total expenses. Major reductions were made in RoE and Forex loss
allowance.
Limited autonomy to EVNNPT and ERAV
1. It has been observed that EVNNPT does not have full authority to determine its revenue
requirement; it has to be channelled through EVN. EVN can exercise powers to curtail the revenue
requirement as it deems fit and submit the same to MoIT / ERAV for review and approval. Hence
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 96
there exists dependency of EVNNPT on EVN and the Government to seek revision in the
transmission charge.
2. Further, ERAV being integral part of MoIT lacks autonomy while approving the transmission
revenue and charge. ERAV does not have any specific powers to review proposed investments as
part of the transmission pricing calculation. Instead, the five-year network development plan and
annual investment plan as approved by MoIT and EVN are used to calculate the costs of
investments in the coming year.
3. As per Decision No. 69/2013/QD-TTg, ERAV shall mandatorily seek approval of MoIT for all
increases in retail tariff beyond 7% (w.r.t. prevailing prices).
Structure related
Coordination between concerned departments
1. Given the nature of data to be submitted by each department to CPD and the average time taken by
CPD for preparation and submission of the petition, internal timelines should be followed for
submission of data by various departments to CPD. It appears the information to calculate failed
service quality is not being captured. Also, the standards / norms have not been defined yet. An
incentive mechanism might help motivate EVNNPT employees towards accurate recording of
relevant information and computation of penalty.
Technology related
Scope for improvement in petition for transmission charge
1. It is also observed that the transmission revenue/charge petition filed by the EVNNPT does not
provide sufficient details (data, analysis, justification etc.) on the various expenses (both, actual and
planned), on the basis of which a sound decision for allowing or disallowing such expenses can be
made. There are no scientifically determined norms for computing materials costs and major repair
costs. ERAV is unable to implement penalty provisions on failure to meet quality standards in
absence of adequate data on incidents and norms.
2. Further, petition uses rudimentary MS Excel workbook for computation of costs and it is difficult to
understand the data flows, inter-linkages and analysis. The petition should also be supported by a
more detailed calculation (MS Excel model) which provides historic information as well as
projections for the future. This will enable a trend to emerge and will be useful in assessing if the
expenses are in line with the regulations and what can be justly allowed. For e.g. further details on
item wise repairs and maintenance expenses, details on outsourced expenses etc.
3. There is also ambiguity about the tariff cycle, which according to regulation is from 1 July of a given
year to the 3o June of next year. But there have been several orders which have called for extension
of tariff from 1 January of a given year. Also the latest transmission charge petition dated 14
January 2014, filed by EVN to ERAV indicates the change in the tariff cycle hence forth to be from 1
January to 31 December of any given year. This calls for a revision in the Regulation which specifies
cut off dates by which EVNNPT/ EVN have to review and submit the TPTR/ TC petition to ERAV
for final approval.
4. There is scope for strengthening the existing framework of EVNNPT even though it is a state owned
enterprise. Areas of improvement include the regulations guiding the filing of petition for
transmission charge and its approval process, classification of costs as controllable and
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 97
uncontrollable elements allowing for better recovery of justifiable expenses of EVNNPT,
comprehensive and accurate data to support the expense claims etc. Also, EVNNPT as well as
ERAV should be allowed to operate with certain level of independence while undertaking the
activity of submitting and approving the transmission charge petition.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 98
Public relations
Strategy
We have reviewed the relevant laws/decisions/decrees/regulations/ circulars for the Public relations function
(Brief provided in Appendix 5 -). The table below summarizes our observations on the relevant laws/ decisions/
degrees/ regulations/ circulars:
Regulations Objectives PwC analysis and observations
Regulation on Communication of EVNNPT, 2011
The regulation lays down that EVNNPT
has to ensure communication of
information to partners, customers of
EVNNPT and social community
NPT communicates with media,
directly. But PMB takes the active role
in the case of addressing the people
being affected by the project - who are
one of the most important
stakeholders
Thus those who are directly impacted
by EVNNPT projects do not have any
direct interaction with EVNNPT
directly on issues like land
acquisition, but are dealt with by PMB
Mentions ‘ad-hoc’ requirements,
indicating the need for crisis
communication or issue-based
communication
Though the need for crisis
communication is mentioned, no
definite plan or process appears to be
mandated or documented
The ad-hoc situation confuses the
prioritisation of issues
The regulation lays out the need for
fulltime communication staff at
EVNNPT
For PTCs, one fulltime staff and one
part time staff
PMBs one full time staff is
recommended
There is no full time head for the
communication team at EVNNPT
The Deputy Director No. 2 and three
experts from the Administration
Department look after
communication
For PTC, there are two part time staff
from the Administration Department
For PMBs too, there are no full time
staff. Communication is handled on a
case by case by whoever is a part of
the project and is assigned the task by
the management
The regulation lays down the staff
should have professional capacity and
knowledge of communication and have
the ability to work independently
The communication staff which are
currently carrying out the PR work
are not professionally trained. They
are mostly people from operations
who have earlier done some
communications work
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 99
Regulations Objectives PwC analysis and observations
The communication team shall have
responsibility to review contents,
organize editorial works, posts
information into News site; website and
means of mass media
Subsidiaries shall prepare press releases
on important events of itself and report
to Administration Department
Other departments. need to coordinate
with Administration Department in
term of information, event to
coordinate in implementation of
communication task
The consultant’s interviews with the
Administration Department show
that the other departments of
EVNNPT do not understand the role
of communication. Also they do not
appreciate or actively cooperate with
communication team in
communication activities
The communications team in the
Administration Department tends to
ignore many tasks assigned to it in the
annual plan
The Administration Department shall
work in coordination with press
agencies to organize working teams to
meet with EVNNPT’s subsidiaries to
collect material, take video, take photos
communication on press publications,
on channels of radio and TV stations
The 2014 communication plan of
EVNNPT reduced the number of
targeted online channels from six to
two
The two that have been retained are
the Party's website and the
Government Portal. The other four
are top prestigious online newspapers
in Vietnam
Meet with responsible people of the
press agencies, radio agencies to
implement procedures of news posting
and TV and radio broadcasting
The communication team from the
Administration Department does not
engage with the media on a regular
basis
The above is evident from the
perceptions audit of the media
The Administration Department shall
organise and advise on communication
to EVNNPT’s leaders to interact with
press agencies.
All requests for interviews, shall be
addressed by the Administration
Department. Other departments and
subsidiaries have the responsibility to
coordinate with the Administration
Department on dealing with media
The Administration Department
coordinates with all media and
organises press meets with EVNNPT’s
spokespersons
All requests for interviews are routed
through the Administration
Department
Decision No. 1428/QD-EVNNPT and amendment
It lays out the functions and
responsibilities of the various
departments of EVNNPT
The role and relevance of these
departments with regard to
communication have been outlined in
the section on Structure
Other relevant regulations:
Regulation PwC analysis and observations
Decision No. 1208/QD- Objective: To develop the roadmap for the power sector in line with the
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 100
Regulation PwC analysis and observations
TTg
National Master Plan
national socio-economic development strategy, ensuring adequate supply
of electricity for the national economy & social life
- To apply market mechanism
- To preserve the monopoly of the state in transmission
- To step up rural electrification
Communication related: The Decision states that communication is
necessary
- For people to understand about co-contributions of both
Government and People in power development in rural and
mountainous areas
- To raise awareness about market mechanism (needs, tariff,
investment etc.)
- For people to reasonably use power resources to protect the
environment
- To raise awareness about the Law relating to using power
economically and efficiently
- To support land acquisition activities and call for investment
in power projects
The Decision can be considered as a background and basic reference
document for EVNNPT, as a subsidiary in the power sector, to follow and
then develop its own strategy
Land Law No.
13/2003/QH11
Land management and
use
The land law prescribes land management and use.
The State is the sole owner of the land. It gives land use rights to the
citizens and withdraws this right for a greater purpose like development
Compensation and Land Acquisition are the two issues that EVNNPT
faces in project implementation. The process of land acquisition can be
much smoother if EVNNPT pays enough attention to communication
strategies with regard to stakeholders, especially the affected people
The objectives and messaging in this law can form the key messages for
stakeholders with regards to land acquisition and compensation
Decree 15/2013/ND-CP
Quality Management of
Construction Works
This decree gives regulations regarding the quality management in
survey, design, construction execution and acceptance of construction
works; on safety management, handling of incidents during construction
execution, exploitation and on warranty of construction works
There is an emphasis on crisis communication. The Decree mentions
- The process of communication of crisis, from commune level
to higher levels
- Within 24 hours investors have to send a written report
about the crisis to District Committee, Provincial Committee,
Ministry of Construction and to relevant bodies in case of
death of people
Despite the emphasis on the need for crisis communication, there does
not appear to be any crisis communication plan in place
As a company with many projects where mishaps can occur, EVNNPT
should consider this Decree as a basic guide for crisis communication
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 101
Structure
The companies and key departments involved in the public relations:
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
ERAV Mr. Tran Tue Quang MoIT
EVN
NPT
EPTC
Generating
Companies
Distribution
Companies
Reviews transmission price
proposals and seeks approval of
Minister / Vice Minister of
MoIT
Interacts with EVNNPT on two
key matters: (i) review and
approval of transmission price
petition; (ii) review and
approval of EVNNPT's
investment plan (both the
documents are submitted after
review by EVN)
Can initiate Suo-Motu revision
of electricity price (in case
utility fails to submit the tariff
proposal on time or does not
submit the proposal at all)
No consultation with public,
discoms and generating
companies yet during the
process of determination of
transmission tariff
EVN PR Cao Quang Quynh -
Acting Deputy
Director
Nguyen Van Binh -
Deputy Director
Bui Viet Ha - Expert
Nguyen Thi Thai Ha -
Expert
Dinh Ngan Ha -
Expert
Do Hoang Ha - Expert
Tran Tri Trung -
Expert
Nguyen Quynh Anh -
Expert
Nguyen Thi Diem
Huong - Expert
Nguyen Hoang Anh -
Expert
Nguyen Bich Lien -
Expert
EVN employees
All subsidiaries of
EVN
All departments
of EVNNPT
Local people at
project sites
Local Authorities
Media
MoIT
ERAV
Dictates strategy to all
subsidiaries, based on which
they develop communication
plans
Communication relating to
major issues and pressing
matters of the subsidiaries are
controlled by this department
NPT Administ Mr. Bui Duy Hung EVN Instructs, plans and
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 102
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
ration -
for
communi
cation
Director
Vu Quang Huy -
Expert
Le Xuan Hoan -
Expert
Tran Anh Son - Expert
MoIT
ERAV
NPT employees
Affected people
(for proposed
transmission
corridor and
substations) and
local people
where there are
transmission lines
and substations
Leaders at all
levels (communes
to provinces)
where projects
are implemented
Media
implements all the
communication related tasks
for EVNNPT, PMBs and PTCs
Manages
o Internal
Communication
(website,
newsletters,
quarterly
magazines)
o External
Communication
(publicity, mass
event management,
media relations)
Promote the image of EVNNPT
in public and to provide
information to the stakeholders
NPT Inspectio
n
Hoang Van Luoc -
Deputy Director
Local Authorities
Government
bodies
Regulators
Residents
Land owners
Inspection, monitoring and
compliance during construction
phase
Working with local authorities
to prepare the plans for safety,
protection & prevention of theft
of power
Encourage people living around
the transmission lines to sign a
commitment not to violate
safety corridor for transmission
lines
Raising people’s awareness
about the protection of
transmission lines
Carrying out CSR activities,
such as building houses, giving
students & poor families gifts
on special occasions; &
organising events
Issues/crisis management
during project construction and
operation
NPT Legal Dinh The Minh -
Deputy Director
Government
regulator
Other EVNNPT
departments
Arbitrators
Acts as the key contact point to
manage internal regulations to
ensure consistent application
throughout EVNNPT, reports to
the Management Board on six-
month and annual basis its
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 103
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
findings of review of internal
management regulations to
ensure compliance with existing
regulations on management
issued by EVN
Pronounce list of internal
management regulations that
are no longer valid.
Update, review and codify latest
regulations
Disseminate legal regulations,
internal management
regulations to EVN’s staff
NPT Construc
tion
Manage
ment
Hoang Van Tuyen -
Deputy Director Affected people
(for proposed
transmission
corridor and
substations) and
local people
where there are
transmission lines
and substations
Domestic funding
agencies
International
funding agencies
MoNRE/ DoNRE
Contractors
Workmen
Land acquisition, resettlement,
compensation, and
environment issues around
construction
Follows the government’s
master compensation plan,
consisting of size of land, unit
price and resettlement plan,
employment opportunities,
support for poor households
and ethnic minorities etc.
Works with the Voice of
Vietnam (VoV) and Vietnam
Television (VTV) to carry out
communication activities,
including those relating to
environmental and social
issues, while PTCs work with
provincial broadcasting stations
NPT Technical Tran The Khanh -
Expert
Domestic and
international
technical partners
Employees
Other EVNNPT
divisions
People living near
transmission
corridor
Workmen
Disseminates information on
environmental issues based on
documents from MoNRE and
EVN
All documents relating to
environment operation are sent
to the Technical Department for
review
All 7 subsidiaries of EVNNPT
prepare reports on environment
protection and send them to the
Technical Department which
prepares an overall report on
the issue
If PTCs do not understand the
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 104
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
guiding documents, they can
call the Technical Department
to ask or they can send a
written feedback as well. In case
the Technical or Construction
Management Departments
cannot answer, they ask
MoNRE to get answers for PTCs
Northern Power Projects Management Board (NPMB)
No full time staff for
communication
Local people
District
Resettlement
Council and other
local authorities
International
Funding Agencies
MoNRE
DoNRE
Employees
Workmen
Works closely with local
authorities (the District
Resettlement Council) to
publicize project information,
such as project policy, acquired
land area, and compensation
Prepare an Environment
Impact Assessment Report for
domestically funded projects
NPMB Resettle
ment
Mr. Do Duc Manh
Mr Vu Thanh Ha
Local people at
project sites
Provincial
People’s
Committee (PPC)
International
Funding Agencies
Resettlement activities are the
responsibility of the PPC,
NPMB gets involved where
necessary, like deciding on how
many and which households are
necessary to be displaced for a
particular project
PPCs are responsible for
announcements for land
acquisition; and can decide on
acquiring paddy land less than
10 hectares without the
approval of the Prime Minister
of Vietnam
Compensation plan is
developed
Indigenous people are paid
higher compensation price and
more employment
opportunities where alternate
cultivable land is not available
The authorities also support
such people in setting up small
businesses
NPMB Assessment Department
Mr. Nguyen Huu
Chanh
Affected people
MoNRE
Domestic
Funding Agencies
Sends written documents to
relevant communes and
commune residents. If
commune people agree with the
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 105
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
contents of the documents then
the commune can send
feedback to PMB about the
agreement on behalf of its
people.
In case there are
disagreements, PMB organises
direct meetings. In this
meeting, PMB listens to and
answers all the queries of the
commune people. MoMs are
developed and signature
obtained from all participants
All EIA reports prepared by
external consulting agencies are
approved by the Assessment
Department
Social Impact Assessment (SIA)
and Impact on Indigenous
Peoples reports are required for
internationally funded projects,
whereas for projects funded
domestically, preparation of
Indigenous Peoples reports is
not mandatory
NPMB Planning Department
Mr. Vu Xuan An Affected people
MoNRE
International
Funding Agencies
Hires external consulting
agencies which prepare EIAs
that are approved by the
Assessment Department
For internationally funded
projects, there are two EIA
reports: one, as per the laws of
Vietnam is prepared by the
Assessment Department of
PMB and the other, following
the donor’s regulations is
prepared by external consulting
agency hired by the Planning
Department
The Social Impact Assessment
(SIA) is also done by the
Planning Department as
required by donors
There is a special plan for
addressing the indigenous
people called the Ethnic
Minorities Development Plan
(EMDP)
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 106
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
CPMB No full time staff for communication
Local people
District
Resettlement
Council and other
local authorities
International
Funding Agencies
MoNRE
DoNRE
Employees
Workmen
There is no dedicated
department for PR. Each
department communicates with
external parties as required
In matters relating to
compensation & resettlement,
the task belongs to the
Resettlement Department.
The Technical department
communicates about
construction work and progress
of project
The Administration
Department communicates
about social issues (i.e. the
benefits and importance of a
project)
The Appraisal Department
communicates about the
environmental issues
The Resettlement Department
prepares a project
communication document that
contains information about the
scope of the project, the kind of
impact, the time to start
construction and the
completion timeline
The Appraisal Department
conducts the Environment and
Social Impact Assessment (EIA
& SIA / ESIA) studies. These
are mandatory and are
prepared by external
consultants
For ODA funded projects, the
report is evaluated by CPMB
and, after review, is submitted
to the donor. For domestically
funded projects, the report is
evaluated by CPMB and
submitted to the environment
authorities in the government
Social Impact Assessment (SIA)
study is not undertaken
separately but is a part of the
Environment and Social Impact
Experts, during the process of
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 107
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
working out compensation
rates, interact with the local
people and communicate about
the project
The Resettlement Department
prepares weekly, monthly,
annual plans on resettlement
issues, including those related
to communication
SPMB Nguyễn Thế Mỹ -
Manager of
Procurement
Department
Dương Anh Tuấn -
Manager of
Resettlement
Department
Trần Thị Tuyết
Lan - Deputy
Manager of
Appraisal
Department
Lê Thị Thanh
Nhàn - Expert of
Appraisal
Department
Phạm Văn Tranh -
Expert of
Resettlement
Department
Lưu Nguyễn
Hương Lan -
Expert in-charge
of Environment,
Resettlement
Department
Nguyễn Bích Ngọc
- Expert from
Procurement
Department
Local people
District
Resettlement
Council and other
local authorities
International
Funding Agencies
MoNRE
DoNRE
Employees
Workmen
SPMB visits the province,
district and commune to
communicate about the project
after investment in a project is
approved
The District Resettlement
Committee prepares the list of
affected people, rate schedule
for compensation and is made
available to the public for
comments
These comments are taken into
account and adjustments are
duly made
SPMB coordinates as a member
of the Resettlement Committee
and seeks resolution of complex
problems
Reports major problem if any to
EVNNPT and seeks advice and
conveys the council to the
Resettlement Committee. It is
then communicated to the
public
Does not communicate directly
with the commune officials
Everything is routed through
the Resettlement Committee
SPMB has a manual for
communication. The ISO
Manual on Resettlement &
Compensation covers “public
communication”. Crisis
communication is covered in
the manual
The rules, process, etc. for EIA
and Social IA are similar to
NPMB
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 108
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
SPMB Communicates internally
with employees through emails
and internal website
Power
Transmis
sion
Company
1 (PTC1)
Le The Huy -
Deputy Director
Nguyen Manhjj
Hung - Expert
Power generation
companies
Power
distribution
companies
Other customers
Local people
around
transmission
corridors and
substations
Local authorities
Promoting PTC1’s image by
providing information about
PTC1. Raising awareness about
role and importance of
transmission lines so that the
public understands the need to
safeguard transmission lines’
corridors
Power Transmission Company 2 (PTC2)
Trần Thanh Phong - Deputy Director -chairman of the meeting
Nguyễn Tiến Dũng - Deputy Director
Nguyễn Hải - Manager of Investment & Construction Department
Lê Hữu Hùng - Manager of Technical Department
Nguyễn Thanh Hải - Deputy Manager of Finance & Accounting Department
Đoàn Hữu Thanh - Deputy Manager of Planning Department
Phan Hồng Phương - Deputy Manager of Administration Department
Phan Anh - Deputy Manager of Inspection & Legal Department
Trương Thế Phong - Deputy Manager of Technical Safety - Labour Safety Department
Power generation
companies
Power
distribution
companies
Other customers
Local people
around
transmission
corridors and
substations
Local authorities
The expert in-charge of
communication has experience
in journalism and is a member
of the Vietnam Journalists
Association, and is a technical
staff
The focus of communication is
on protection of safety corridors
Land acquisition is not critical
for PTC2 as the projects are in
remote areas
There is no official regulation
mandating the use of social
media. But the staff does use
social media like Facebook to
communicate on projects
PTC does provide special help
to indigenous peoples primarily
in the recruitment of workers;
alongside support for workers
from such background when
their families face difficulties
There is the intranet and the
internal website for internal
communication where
information is posted regularly.
It also carries personal
information like birthday
celebrations, etc. Employees
post ideas about work on the
intranet and internal website
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 109
Entity Depart-
ment
Officers involved Stakeholders Specific role in public
relations
Lê Quốc Thắng - Expert from Administration Department
Trần Thị Hương - Expert from Planning Department
Nguyễn Anh Tuấn - Expert from Technical Department
Nguyễn Thị Thuỳ Trang - Expert from Finance & Accounting Department
Power Transmission Company 4 (PTC4)
Trần Thái Dũng - Manager of Planning Department
Nguyễn Phương Nam - Deputy Manager of Planning Department
Hà Công Minh - Manager of Load Dispatch Department
Phan Thái Bình - Manager of IT Department
Võ Thanh Cường - Manager of Investment & Construction Department
Dương Thất Đúng - Deputy Manager of Finance & Accounting Department.
Dương Văn Tâm - Deputy Manager of Personnel & Labour Department.
Mr. Đạt - Expert of Technical Department.
Power generation
companies
Power
distribution
companies
Other customers
Local people
around
transmission
corridors and
substations
Local authorities
The Deputy Director
Technical is responsible for
communication. The
Manager of the Safety
Department reports to him
Technical staff are assigned
the task of communication
since they have experience
and good knowledge of
safety. They do not have
specialised communication
skills
Communication on land
acquisition is handled by
the concerned Resettlement
Committee. Sometimes, a
member of the PTC4
Management Board is a
member of the
Resettlement Committee
Construction and O&M personnel also communicate with local people
Some members of trade
union and youth union also
help in communication.
The trade unions maintain
a safety officers’ network
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 110
Processes
The diagram represents the process of communication between EVN, EVNNPT, its subsidiaries and
stakeholders.
The Administration Department of EVNNPT is responsible for strategy, planning and implementation of all
communication related tasks for EVNNPT, PMBs and PTCs. Any communication with the media is through the
Administration Department.
Local authorities play the key role in communicating with the affected people for land acquisition, with PMBs
liaising with them. Thus the communication with affected people for is only through PMBs and EVNNPT plays
more of indirect observational role. EVNNPT gets involved only when there is a crisis. The people affected by
transmission projects around the region are mostly not aware of EVNNPT. They only know about PMB which
directly interacts with them.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 111
The PPC informs the DC about land acquisition and the DC informs the commune, which include leaders from a
cluster of villages. The village leaders then communicate the plan to the villagers and other ethnic minorities/
indigenous peoples. The village leaders usually communicate the issue in the local language of the indigenous
peoples, announcing through loud speakers or through one and one meetings with these people:
The tariff revision process is an internal exercise that involves only EVNNPT, EVN, ERAV and MoIT. Neither
EVNNPT’s petition for tariff revision is shared with any stakeholders, nor are the comments of stakeholders
invited before finalisation of the new tariffs.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 112
Select global practices
Aspect Thailand India
About the transmission sector
Electricity Generating Authority of Thailand (EGAT) owns most of the country’s power production units and is responsible for the country’s transmission system
There are two distributing utilities in the Thai electricity system, namely the Metropolitan Electricity Authority (MEA) and the Provincial Electricity Authority (PEA)
India is one of the few countries where the Transmission Sector has been opened up for private participation & this has attracted significant interest from private players
Private participation is mainly in BOO (Build Own Operate) format and is small & growing
Power Grid Corporation of India (POWERGRID), the government-owned Central Transmission Utility (CTU), is responsible for wheeling power of central generating utilities and inter-state mega independent power producers
State Transmission Utilities (STUs: managed by respective state governments) are responsible for wheeling of power from state generating units and state level independent power producers
As per the Electricity Act, 2003 the functions of the Central Transmission Utility are:
o Undertake transmission of energy through the inter-state transmission system
o Discharge all functions of planning & co-ordination for inter-state transmission system
o Ensure development of an efficient, coordinated and economical system
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 113
Aspect Thailand India
of inter-state transmission lines for smooth flow of electricity from generating stations to load centres
o Ensure integrated operation of the regional grids through RLDCs (Regional Load Despatch Centres)
Similarly, the State Transmission Utilities are responsible for the development of transmission networks at the state level
For communication on land acquisition
EGAT informs the owner or possessor of the property concerned in writing about the proposed acquisition
The owner or possessor of the property may make a submission to the EGAT Board, giving reasons why it would be inappropriate to acquire his land. The Board is obliged to give its decision on the petition within 30 days from the date of receipt of the request
A meeting is called by EGAT to explain the salient features of the transmission project as well as to listen to the points raised by the people whose land is to be acquired
There are cases in which citizens have voiced the need to have a joint action committee to study the impact of an EGAT project. The committee comprises external consultants, experts and leaders of the affected community. It undertakes an impact assessment study and submits its report to the public and the government.
Finally, high ranking officials from EGAT are expected to meet the residents in person, listen to their point of view and seek their cooperation
An initial environment and social assessment is conducted to study the impact of the land loss
Over and above the mandatory requirements of the land acquisition law, POWERGRID is committed to assessment of probable impacts associated with land acquisition through its social assessment and management process which includes a socio-economic survey of the proposed substation sites
The socio-economic survey assesses both adverse and positive impacts of the project on aspects such as the natural resource base, developmental potential of the area, economy of the affected area, social structure, norms and traditions.
The socio-economic survey also includes a complete household census recording members, property with legal rights and resources which are in possession or in use
Appropriate methods such as participatory rural appraisal and questionnaires are utilized.
Public is informed about the project at every stage of execution. During the survey, the site officials, along with consultants, meet people and inform them about the RoW requirement / land acquisition details.
The Environmental and Social Policy and Procedures (ESPP) spells out its commitment to ensure total transparency through a well-defined public consultation process as well as dissemination of relevant information about the project at every stage of its implementation.
It is also ensured that such consultations are based on the principle/concept of “Free, Prior Informed Consultation”.
The site selection by POWERGRID is planned on the basis of avoiding irrigated land, homestead land/houses, religious structures, cultural property or public infrastructure
POWERGRID aim to locate sub-stations on government/waste land as far as possible
For communication on resettlement
Under section 30 of the EGAT Act, EGAT decides on the compensation value and pays fair compensation to
In India land acquisition, resettlement and compensation are governed by the brand new Right to Fair Compensation and Transparency
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 114
Aspect Thailand India
& compensation
the owner or possessor of the property or another holder of a right for the following cases:
Use of land to set up posts for transmission or distribution lines
Use of land to set up sub-stations or other accessories
Use of land which is declared as electric line laying zone
In cases the compensation amount is not agreed upon between the owner/possessor or rightful holder of the property and EGAT, or
If the owner or possessor/ rightful holder of the property could not be found
EGAT deposits such compensation to the Court/ the Deposit Office, or deposits it in the Government Savings Bank in the name of the owner/possessor/ rightful holder of the property
If there is any interest accrued on such deposit, it is also vested to the owner/ possessor/ rightful holder of the property
in Land Acquisition, Rehabilitation and Resettlement Act, 1913 which came into effect on January 1, 2014
This new land law replaces the old colonial-era law, the 1894 Land Acquisition Act, which was seen as one-sided and weighted against land owners and land users.
The new law notably makes “fair compensation and transparency” in land acquisition a right of the people
It makes up for the earlier absence of a national law to provide for rehabilitation & resettlement (R&R) and also compensation for loss of livelihood of those affected and displaced. The old law did not do this and R&R suffered badly
POWERGRID assess the social impact of land acquisition based on the socio-economic survey and design compensation packages in consultation with the people.
The mode / technique of public consultation involves public meetings, informal small group meetings, information brochures and pamphlets, operating field offices, local planning visits and site visits by staff, response to public enquires, press releases inviting comments, project coordination committees, ombudsman or representative and public displays
For communication with affected people
EGAT's corporate plan explicitly requires public participation and seeks public acceptance of the development project
EGAT's objectives in public consultation include seeking the opinion of the public and understanding their needs, assessing the objections of the communities living in the operational area, and disseminating accurate information about the project
EGAT’s operations have always been closely related to rural communities and their livelihood from the construction survey to the construction of power plants and transmission lines as well the electricity generating activities. It is EGAT’s policy to become part of the community wherever they operate
POWERGRID involves affected people from inception stage to operation and maintenance
They consult affected people in issues of RoW, land acquisition or loss of livelihood
POWERGRID organises meetings with the Project Affected Persons (PAPs) in order to evolve the Rehabilitation Action Plan (RAP)
Meetings with the State authorities, PAFs and well-reputed persons in the area are also consulted during the preparation and implementation of the RAP
The company guarantee entitlements and compensation to affected people as per its R&R policy
For communicating with public officials
Local communities, leaders, and government and non-governmental groups are canvassed and requested for recommendations
Several public meetings are held at each of the project sites to discuss
Public hearings are mandatory step in the process of environmental clearance for most infrastructural projects in India. This provides a legal space for public officials and people of an area to come face-to-face with the project proponent and the government and express
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 115
Aspect Thailand India
concerns, mitigation measures and seek resolutions
Alternatives to the projects are discussed with the local communities, as appropriate for each site and as detailed in the project specific environmental executive summaries
their concerns
For communication with indigenous peoples
EGAT continues to monitor positive as well as negative developmental outcomes of its projects, after the completion of the power plants and transmission line projects, by promoting the establishment of local cooperatives and providing assistance funds for people affected by its operations. Such social investment has made significant improvement of the well-being of local people
POWERGRID pays special attention to marginalized and vulnerable groups and secure their inclusion in overall public participation.
Their Rehabilitation Action Plan (RAP) is designed to offset the trauma of economic and cultural disruption to these communities and to develop and implement programs which are meaningful and workable such that they do not become worse off economically than before
People
1. EVN has supervisory control over EVNNPT’s communication activities. In EVNNPT,
communication is undertaken by various departments and subsidiaries. EVNNPT does not have a
separate communication or PR department. While communication is formally the responsibility of
the Administration Department, its leadership maintains several other responsibilities
simultaneously and communication is one of them.
2. The Deputy Director#2 of the Administration Department is part-time in-charge of communication
in EVNNPT. The communication team of EVNNPT has three experts who do full- time PR work.
The expert who plays the key role in the department, and often acts independently, is a power
system engineer by training and has over 15 years’ of experience. But he has no professional
qualification in PR or communication and has worked in this field only since 2012. The senior
management apprehends that a communication expert may not understand the operational
processes or issues. Therefore it does not make professional qualification and experience a pre-
requisite for those assigned communication roles. EVNNPT communication officials do attend brief
training programs, but those do not appear to be comprehensive.
3. For EVNNPT, the communication team does both planning and implementation. For the
subsidiaries of EVNNPT, the team makes only the master plan and develops strategy.
Implementation is carried out by the subsidiaries themselves through officials that do
communication work in addition to their other work.
4. In NPMB, too, there is no full-time expert dedicated to communication. Communication is handled
on case by case basis by a management appointee based on his or her project responsibilities. The
Deputy Director-Technical serves as spokesperson and is in-charge of making all announcements.
NPMB implements communication strategies laid down by EVNNPT and EVN.
5. In PTC1, the Administration Department handles communication. There is a team of two people
that works part time in communication. One of them is the Deputy Director and the other is an
expert who is a business graduate and does not possess any professional qualification in PR. This
individual has been in the current position for just over a year. He handles both internal and
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 116
external communication. Items of internal news are sent from subsidiaries and then edited and
published on the company website. For carrying out external communication, he coordinates with
the Inspection Department of PTC. He makes the plans and is also responsible for the execution of
the activities mentioned therein. The communication expert has also developed a 5-year
communication strategy with inputs of the local offices. The strategy is yet to be approved. The plan
is submitted to his supervisor in the Administration Department. From there, it goes to the PTC1
Deputy Director and then to EVNNPT for final approval.
6. For PTC2, the Deputy Director is in-charge of communication. There is one full-time expert in the
team in-charge of communication. The team prepares the material for communication. There are
experts who are in-charge of communication. The expert has no professional communication
qualification, but is a technical staff. He has experience in journalism and is a member of the
Vietnam Journalists Association.
7. In the case of PTC4, there is no dedicated staff for PR. But there are many experts who do
communication work. They are from the Safety Department and are experts responsible for
ensuring safety. The Deputy Director (Technical) is responsible for communication. The Manager
of the Safety Department reports to him.
8. Experts are assigned the task of communication. These are technical staff. They have experience
and good knowledge of safety. They meet basic requirements. They do not have specialized
communication skills.
9. Workers employed in construction and O&M also communicate with local people.
10. Some members of trade union and youth union are also helping in communication. The trade
unions maintain a safety officers’ network. They receive training in the form of short term courses
in communication.
11. The PMB officials sometimes find themselves ill equipped to communicate directly with certain
stakeholder groups. For instance, during interaction with the ethnic minorities, the major
challenges faced are language barrier, low education and differences in customs/cultures. PMB has
to depend heavily on the communes for communication.
12. At CPMB there is neither any dedicated department for PR nor is any person in-charge of
communication. Each department communicates with external parties if it has to. In the case of
Compensation & Resettlement, the task belongs to the Resettlement Department. Technical
department communicates about construction work and progress of project. The Administration
Department communicates about social issues (i.e. the benefits and importance of a project). The
Appraisal Department communicates about the environmental issues. No guidance has ever been
received from EVNNPT or EVN on communication. All communication activities are linked to
projects. If need be, the Deputy Director in-charge of a project communicates with EVNNPT or
EVN.
Technology
Key communication plans being followed:
Major plans used Topics Prescribed Tasks PwC analysis and observations
EVN Communication Plan for 2014
Communication work of the subsidiaries of EVN
Develop detailed
communication plan of
Each subsidiary
develops a
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 117
Major plans used Topics Prescribed Tasks PwC analysis and observations
the Group, defining the
communication theme
for each quarter
Provide written
guidance to unit
members on performing
communication
activities driven by
content
communication plan
based on the strategy
provided by EVN and
then submits it to EVN
for approval
EVN then supervises all
communication
activities through
monthly reports (from
the subsidiaries) to
ensure everything is on
track
Media management and orientation
Manage information
flow to media
organisations
EVN is not active in
regular media
engagement regarding
announcement of new
projects etc.
Media sees EVN as
monopolist and
unresponsive
Community Relations Issuing the Regulation
on organizing
community relations
activities and
management model of
community relations
work within the Group
EVN has recently started
communicating with
stakeholders, especially
the ordinary public, to
publicise EVN’s
activities and to secure
support for EVN’s work.
They are now using the
slogan “Light up trust”,
which stems from the
thought that its purpose
now is to win back trust
from stakeholders
NPT Propagation Plan 2014
Propagate the role, position, importance and achievements of EVNNPT and its subsidiaries
Coordinate with local
and central media
agencies to update news
of EVNNPT
Writing articles on
electronic portal of
EVNNPT
Power Transmission
Newsletter
Organize charitable
activities
Media engagement is a
major part of EVNNPT’s
communication work
Articles about
EVNNPT’s projects,
events, business etc. are
posted on the electronic
portal, i.e. the website of
EVNNPT
Newsletters are sent
internally within
EVNNPT and its
subsidiaries. Thus, while
the Plan requires
EVNNPT to use the
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 118
Major plans used Topics Prescribed Tasks PwC analysis and observations
Power Transmission
Newsletter to
communicate with all
stakeholders, in fact the
newsletter is consumed
internally
NPT organises various
CSR activities through
the workers union and
youth union
Internal propagation Writing articles on the
website, newsletter of
every units, newsletter
of Transmission and
electronic portal of
EVNNPT
Use of websites,
newsletters and
magazines for internal
communication is
common
Propagate the protection of power grid safety corridors
Distribute brochures
Hang posters, paintings
Write articles, reports
Disseminate
information in the mass
media about the
incidents where there
was a threat to life and
property
Through organizations,
schools
Other forms suitable for
specific units
NPT does not directly
deal with the people
affected by transmission
projects
PTC is in-charge of
direct interaction
PTC disseminates
information through
posters, fliers about the
protection of safety
corridor. However these
are localised and not all
of the people are aware
of this activity
Propagate site clearance compensation
Dialogues and meeting
Coordinate with media
agencies to submit
articles, reportage and
propaganda
Site clearance and
compensation again is
not directly handled by
EVNNPT.
The PPC prepares the
compensation plan and
sends it to PMB for
budgeting
Media is not used
optimally for
communication with
regard to site clearance
Engaging with media for communication
To perform activities in
coordination with press
agencies to organize
working teams to meet
with EVNNPT’s
subsidiaries to collect
One of the objectives of
communication work of
EVNNPT is to
communicate about
EVNNPT with entire
society and this is also
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 119
Major plans used Topics Prescribed Tasks PwC analysis and observations
material, take video,
take photos,
communication on
press publications, on
channels of radio and
TV stations
mentioned in the plans
of 2013 and 2014 but in
fact, since its
establishment (about 5
years so far) EVNNPT is
rarely reported in the
mass media
The interviews with
media and MoIT shows
that EVNNPT does not
work well with the
media and its target
audiences exclude mass
public as it mentions in
both Regulation and
Communications Plans
Besides, the number of
newspapers (both online
and print) used in
EVNNPT
communication work is
quite limited
The EVNNPT communication plan for 2013 (analysed here vis-à-vis 2014 plan)
There has been no change in terms of objectives, target audiences and
communication tools to be used
However, there are differences as listed below:
o The 2014 plan identifies clearly the activities to be performed by
EVNNPT and its subsidiaries. The target media are identified
o Newspapers: The 2013 plan selects six online channels for
communication (including the Party’s website, the Government
Portal, Prestigious online newspapers like Dantri, VnExpress,
Vietnamnet, and the Power sector’s websites) while the 2014 keeps
only two channels as targets the Party’s website and the Government
Portal
o In term of print newspapers, the 2013 and 2014 plans keep the same
number of newspapers. Four newspapers (Nhan dan (People),
Vietnam News Agency, Lao dong (Labour), Hanoimoi (New Hanoi))
are same and two are different
o In 2013 plan, the Power Magazine and Industry & Trade newspaper
were selected but in 2014 plan they are replaced by Dau tu
(Investment) and Nguoi dai bieu nhan dan (People’s representatives)
newspapers
o The 2014 plan mentions the cooperation with other communication
institutions like the Centre for Power Information, Energy Magazine,
and Power and Life Magazine, whereas, the 2013 did not have this.
PTC1 Communication Implementation Plan 2014
Communication with local authorities: Provincial Peoples Committee, District
Sending out official
letters, fliers according
to form
PMB send s official
letters to PPC and DC on
land acquisition and
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 120
Major plans used Topics Prescribed Tasks PwC analysis and observations
Councils etc. Report on status of
violation cases of
transmission line
corridor
Working directly with
People Committee /
Steering Committee at
provincial level
work closely with them
to ensure smoother
process.
Reporting of status of
cases of violation of
transmission line
corridor is yet to be
explored
Communication with Affected People
Use Panels, posters at
Public places (CPC,
schools, cultural houses
etc.)
Provide tapes or articles
to broadcast on
loudspeaker system to
CPC (Hamlets/Mountain
villages)
The communication with
affected people is
localized
In some areas PTC
addresses the people, in
some other areas it does
not
This is evident from the
perceptions audit, where
many affected people
were not aware of any
briefings on land
acquisition as well as
protection of the safety
corridors
Communication with individuals on protection of safety corridor
Sign agreements with
farmers living near the
transmission line
Sending out official
letters, fliers according
to form, and signing of
commitment by owners,
household heads and
individuals having
property in or near the
corridor
PTC is carrying out the
requisite tasks under the
supervision of and in
coordination with
EVNNPT
However, from
interactions with
individuals, it appears
that there is inadequate
communication on land
acquisition or briefing
on the safety of the
transmission corridors
Analysis of perceptions audit
A perceptions audit was undertaken to gauge and analyse the perception of the stakeholders about EVNNPT
and its subsidiaries. This was qualitative study insofar as it did not use a “statistically significant” sample size.
In other words, it was a dipstick study designated to gauge their perceptions about EVNNPT and its activities
and the satisfaction quotient on the communication process that it follows. Representatives from four major
stakeholder groups were chosen. These people were administered questionnaires specific to their group. The
interview was conducted over a period of three weeks in Hanoi as well as at an EVNNPT project site at Hoa
Binh. Representatives of the following stakeholder groups were quizzed:
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 121
Negative
20%
Positive
33%
Neutral
27%
Never Heard
of 20%
Media;
General public;
Public officials; and
EVN officials.
The feedback was analysed and used to map the satisfaction quotient. The questionnaire used is attached in
Appendix 4 -.
Response
The responses of fifteen people have been collated and analysed.
The media respondents comprised senior to top
level representatives of both print and electronic
media. These media persons were very responsive
and were more willing to share their views than
some of the other stakeholders groups. Around
40% of the respondents were from the media.
The general public also responded well. Around
27% of the respondents comprised general public
who conveyed their perceptions on the
organisation. The general public included the
affected people whose land had been acquired and
who had been compensated and rehabilitated.
People living around the safety corridors and
substations and representatives of ethnic minorities/ indigenous peoples were also part of this group.
Public officials and EVN officials were less forthcoming with their responses. They were either sceptical about
the exercise or hesitant about commenting on their internal systems.
Outcome
General perception
The general perception about EVNNPT as an organisation was mapped.
The group of respondents that had a positive perception about EVNNPT
was the largest, followed by those who had a neutral perception. However
those who had a positive perception about EVNNPT were not more than
33% of the total number of people quizzed. In contrast, 40% of the
respondents had a negative perception, or had not heard of EVNNPT.
Conclusion: EVNNPT has a long way to go before it could be said that it
enjoys a positive reputation among the majority of the stakeholders.
27%
40%
20%
13%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
GeneralPublic
Media PublicOfficials
EVN
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 122
Communicatio
n 25% No
communicat
ion 75%
Part of EVN
NPT is a subsidiary of EVN and EVN is added as a prefix to EVNNPT and the
names of all its subsidiaries. To understand whether EVNNPT is viewed as an
autonomous organisation, respondents were questioned as to whether they
saw EVNNPT as an entity distinct from EVN. It was found that EVNNPT was
seen as a part of EVN by all respondents who were aware of both
organisations.
Conclusion: It is unmistakable that EVNNPT’s image and reputation are
intertwined with those of EVN.
Perception on communication/information flow to different stakeholder groups
The stakeholders were asked on their satisfaction quotient
with EVNNPT in terms of information flow and
communication on various issues. The issues included land
acquisition, resettlement, inviolability of the transmission
corridors and communicating with the indigenous peoples/
ethnic minorities. Nearly half of the respondents did not
warm up to EVNNPT’s communication efforts. 53% believe
the communication process is good and adequate. More
than 20% perceive the efforts as inadequate.
Conclusion: Taking all stakeholder groups into account,
EVNNPTs communication score leaves a lot to be desired.
Communication with the general public
The general public was questioned if they received information about issues
through loud speakers, leaflets and so on, as was claimed by the EVNNPT
officials. No more than one fourth of the respondents conceded that there
was some form of communication. The bulk of the respondents said there
was no intimation on any of the issues.
Conclusion: EVNNPT needs to communicate a lot more than it is now
doing with the general public.
Feedback on the CSR activities undertaken by EVNNPT
NPT was rated on the basis of the CSR work that they undertake for the
affected people. Most of the respondents thought that the CSR work was
inadequate and were unhappy about it. A major part of the respondent group
was not aware of the initiatives undertaken by EVNNPT.
Conclusion: EVNNPT has to do much more on CSR. Additionally they
should make stakeholders aware of such CSR work as they are doing.
Independen
t Entity
0%
Part of
EVN 100%
20%
33%
27%
20%
0%
5%
10%
15%
20%
25%
30%
35%
Good Adequate Poor NoResponse
Happy,
37%
Unhappy, 38%
Not Awar
e, 25%
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 123
Communicat
e 40%
No communicati
on 20%
No comments 40%
Perception of the general public on Rehabilitation and Compensation
The questionnaire sought feedback from the affected people on
rehabilitation and compensation. Most of the people quizzed
were unhappy about the rehabilitation, as they had to
surrender their homestead and relocate. Some people were
happy as their new home was better. The compensation
offered evoked mixed feelings: the respondents were both
happy and unhappy.
Conclusion: Land acquisition remains a very sensitive issue.
Communication about the imperatives of maintaining safety in and around the transmission corridor
The general public was asked about being briefed on the need to ensure
safety around the transmission corridor. 40% said that there was
communication on this issue. An equal number of respondents had no
comments to offer. The remaining 20% said that there is no
communication on the subject.
Conclusion: The communication on transmission corridor inviolability,
such as it is, is localised and inadequate.
Summary of key observations
Strategy related issues
1. Communication or PR so far has not been a priority or focus area for the EVNNPT leadership. The
need for PR is recognized though not adequately. It is critical for the leadership to recognise the
efficacy of PR /communication as an essential strategic tool for achieving business objectives.
Focus on communication is an absolute necessity. There is a clear need for EVNNPT, and all its
departments and subsidiaries, to regard communication as a vital function that is central to the
running of the organization. At this time, all departments and subsidiaries do not have
communication as an important activity. Most departments appear to see communication as
primarily the responsibility of the Administration Department.
2. A key perception issue that EVNNPT faces is the view that EVN - the parent company - is a
monopolistic organization, which is not responsive. EVNNPT and all its subsidiaries are bound to
have the EVN as prefix to their names in all public communication. For example, it is EVNNPT and
EVNNPT NPMB. This prefix and the resultant association with EVN affects the image of the
concerned organization.
3. Common citizens sometimes compare EVN with the telecommunication companies. Competition in
the telecom sector makes the telecommunication companies more responsive to public opinion.
38%
50%
63%
50%
0%
10%
20%
30%
40%
50%
60%
70%
Rehabilitation Compensation
Happy Not Happy
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 124
EVN has ventured into some areas that are not its core competency. This has affected its
reputation.
4. Crisis communication strategy is also an issue with EVNNPT. While EVNNPT officials are aware of
the possibility of accidents and breakdowns being caused by the breaching of the safety corridor for
transmission lines, and are also aware of the possibility of a land acquisition dispute getting out of
hand, not enough attention appears to be paid to crisis preparedness from a communication
perspective. This is a dichotomy because there is near unanimity among EVNNPT officials that land
acquisition is a highly sensitive issue, which severely affects EVNNPT’s reputation and also hurts its
business because, as one official informed us, as much 80 per cent of all projects are delayed -
mostly on account of site clearance and compensation issues. Many in EVNNPT do not feel that it is
directly responsible for communication relating to land acquisition. Such communication is seen as
either EVN’s responsibility or that of PMB and the local authorities. It is a fact that PMB and EVN
works with local authorities on communicating with the local people before the commencement of a
project. One EVNNPT expert said that when the peasants are aggrieved they blame EVN or PMB-
not EVNNPT. And once the lines are up, many village people associate the transmission lines with
the distribution companies - again not EVNNPT. However, another expert said many of the
residents in the interiors of the country do associate EVNNPT with the transmission lines and
harbour positive feelings about EVNNPT.
5. There is a need to pay greater attention to messaging. This will lead to consistency in
communication and adoption of more talk points for EVNNPT and its various subordinate units
and subsidiaries.
6. The EVNNPT communication plan does not pay attention to the need for ensuring environmental
norms are followed and/or highlighting the environmental norms that are being followed. A formal
social impact assessment is not always undertaken except where it is mandatory as part of the
norms of the donor organization financing a particular project.
7. The EVN and EVNNPT communication plan does not seem to reflect the goals and priorities set by
the National Master Plan for Power.
8. The budget for communication (for manpower, for equipment and tools, and for activities) appears
to be insufficient. At least the staff thinks it so.
9. Social impact assessment reporting is not mandatory as per Vietnamese regulations. It is
undertaken as per regulation of the donor agency. According to Vietnamese policy, the criterion for
SIA is only compensation; whereas donors’ regulations also consider gender, development of
indigenous peoples and vulnerable households. The differences in regulations create confusion and
so there is a need to harmonize the policies.
10. For projects funded domestically, preparation of reports for Indigenous Peoples reports is also not
a requirement at the initial stage.
Structure related issues
1. Neither EVNNPT nor any of its subsidiaries has a dedicated PR department. There is also a
shortage of qualified communications staff.
2. Last year, EVNNPT proposed to have a separate communications department. This proposal is yet
to be approved by EVN. EVN maintains that it would like all its subsidiaries to have separate
communication department. The distribution companies tend to have their own communication /
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 125
PR departments. This is attributed by some to the fact that these subsidiaries have a long history
(and so have evolved over time) and have optimal direct customer interface. For EVNNPT
executives handling communication, there is too much to do, too many issues to address and too
little time for them to be able to do justice to the tasks.
3. NPT focuses a lot on CSR. But the impact is only on a few people and is inadequate to alter
perceptions about EVN and EVNNPT if that is the objective. From the point of view of EVNNPT,
these activities are not seen as “CSR” because of the simple reason that the concept of CSR is not
widely or adequately understood. Tariff cross-subsidy and providing breaks to those living in areas
affected by natural calamities are seen by some in EVN as CSR activities. There is no department in
EVNNPT that is in-charge of CSR. Activities relating to CSR are carried out by different
departments, mainly by the Workers Union and the Youth Union and also by the Administration
Department in the subsidiaries. Which department will undertake any particular CSR activity
depends on the specific context of the activity.
4. NPMB is responsible for land acquisition and compensation. So the affected people do not know
about EVNNPT. They know of only NPMB.
5. The transmission pricing petition is reviewed by EVN, which changes the content based on
expenses, return on equity etc. which has significant impact on ultimate transmission price,
financial viability and independence of EVNNPT. Thus, it would be better if EVNNPT is made
independent of EVN in this matter and it is able to directly petition ERAV.
People related issues
1. Lack of professionally qualified personnel manning PR positions is an issue. Thus, human
resources need to be improved both in terms of quality (professional qualifications and experience)
and quantity. There is an apprehension in a section of the leadership that a professionally trained
person may not have any knowledge or experience of operational matters. But such misgivings are
unfounded. Such a person can be extensively briefed on operational matters.
2. NPT is aware of the worth of training—both of those who carry out communication functions as
well as those who are only periodically called to play the communicator’s role. However, the
training programmes, such as they are, are grossly inadequate and are no substitute for recruiting
professionally qualified personnel. EVN organises two training courses every year. The first is for
the communication staff of EVN and all subsidiaries, and the second is for spokesman training for
the top leaders (including directors, vice directors, managers’ in-charge of communication and
other authorised spokespersons). Besides, the subsidiaries may have their own training courses.
There is a need to impart training in soft skills, writing, logistics in communication activities, and
IT, including a wider and deeper use of the Net and New Media.
3. The communication plans do not identify the spokespersons. However, EVNNPT and its
subsidiaries have their own designated spokespersons which are normally vice president or vice
director. While there are training programmes for these spokespersons, it would be useful to have
such training programmes also for lower levels of the officials.
4. The PMB officials sometimes find themselves ill equipped to communicate directly with certain
stakeholder groups, say ethnic minorities due to language barrier, low education and differences in
customs/cultures. PMB has to depend heavily on the communes for communication.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 126
Process related issues
1. Frequent changes in the staff doing PR work dilute the commitment that executives have towards
their job.
2. The stakeholders are not listed, far less prioritized.
3. There is no use of third party advocacy (content/ research/statement). Highlighting of positive
aspects (propagation) is better accepted when done by a third party. Otherwise, it runs the risk of
being taken less seriously because it is perceived as no more than “propaganda”, the term widely
used to describe communication work.
4. It would be useful to put in place a system for receiving and assessing feedback from stakeholders.
Little stress is placed on systematic feedback and two-way communication between EVNNPT and
stakeholders.
5. There is a need to introduce measurement in the plans.
6. For domestically funded projects, the focus is on compensation. It is important to have a separate
resettlement plan also.
Perception related issues
1. The positive perception about EVNNPT is apparently overridden by negative and neutral feelings.
One of the reasons for this is that EVNNPT is perceived as being a part of EVN, which is perceived
as a monopolist and unresponsive.
2. A major chunk of the stakeholders think that EVNNPT does not communicate with them on issues
like land acquisition, resettlement and compensation.
3. The communication/ briefing on maintaining safety around transmission corridor is also
inadequate.
4. Most people think that the CSR activities that EVNNPT undertakes are inadequate. A lot of people
are even unaware of the fact that they undertake CSR work. It would be useful if EVNNPT develops
a plan and strategy for CSR activities and also involves media for visibility.
5. Most of those who are affected by EVNNPT projects are not happy with the rehabilitation and
resettlement initiatives. Even on compensation, opinion is equally divided with as much as one half
of the affected people being unhappy with what they have received.
Technology related issues
1. NPT is not active on social media. Platforms like Facebook are very popular in the country, but this
popularity is not being leveraged by EVNNPT. It would be useful to leverage the high education
level of common people and the high internet penetration.
2. There is no evidence that the electronic media is being used to its fullest advantage by EVNNPT.
Training of EVNNPT spokespersons on how best to handle the electronic media would be helpful.
The other aspect of this would be to work with the producers of electronic media channels to
produce programming content that would highlight the key messages of EVNNPT in the most
palatable and persuasive manner.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 127
3. Though the agenda of the department is to use mass media along with the company website and
direct communication, there appears to be insufficient use of local mass media (publications,
televisions) for disseminating information.
Part-B: Recommendation Report
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 128
Part-B: Recommendation Report
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 129
Investment planning
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Overview
Title Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Dimension Strategy
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft approach note along with the revised delegation of powers pertaining to the investment planning: Four weeks from signing of MoU between ADB and EVNNPT
Presentation to EVNNPT: One week from the finalisation of the approach note
Rationale
1. The Decision No. 1368/QD-EVNNPT, 2013 governs the delegation of powers for undertaking
investment decision in EVNNPT. The existing framework is about more centralisation in decision
making to the President & CEO or Management Board of EVNNPT. There is a requirement of
decentralization of powers in respect of investment planning due to the following reasons:
a. The majority of the powers from selection of consultants, approval to feasibility report,
detailed technical design and subsequent modifications; for investment value even below
800 billion VND lies with the President & CEO of EVNNPT. The Investments with ticket
sizes above 800 billion VND require approval from Management Board of EVNNPT;
b. There is practically no financial/ administrative powers provided to PTCs/ PMBs/ vice
presidents of EVNNPT;
c. The PTCs and PMBs are responsible for identification of investment needs and execution
of capital projects. In absence of such delegation of powers, projects of smaller ticket size
and critical nature may be delayed. Such a centralized delegation of powers also lead to
higher transaction costs in case of smaller projects which may not be beneficial for the
company;
d. Empowering PMBs and PTCs will also allow the departments under EVNNPT and the
President & CEO of EVNNPT to focus on investments of higher value and strategic nature;
and
e. It will empower PTCs/ PMBs to undertake financial and administrative decisions quickly
based on the ground realities which will also ensure greater accountability from the
PTC/PMB employees.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 130
2. The proposed approach note shall assist EVNNPT and MoIT to understand, assess and refine the
existing Delegation of Powers in line with the widely accepted industry practices which could be
rolled out in a short time period.
3. The revised Delegation of Powers to be provided in the proposed approach note shall reduce the
time required for planning and approval of the investment projects of small and critical in nature.
Description
1. The approach note shall contain the following:
a. Brief of the existing delegation of powers as per Decision No. 1368/QD-EVNNPT, 2013;
b. Key issues with the existing delegation of powers in context of investment planning and
approval. This section shall also highlight experiences in other countries;
c. Framework for clearly outlining the parameters based on which upcoming projects can be
segregated into different clusters. It shall also identify the clusters where the financial and
administrative powers may be decentralised to PTCs/PMBs/departments of EVNNPT;
d. Revised delegation of power;
e. Key benefits of the revised delegation of powers especially in respect of the issues
highlighted above; and
f. Roadmap for implementation of revised delegation of power. This section shall also
highlight key challenges in implementation and our suggestion (in any) to overcome these
challenges in an efficient manner.
Implementation steps
1. PwC will submit the draft approach note to EVNNPT for discussions and inputs. If required, PwC
will conduct detailed discussions and presentation to ADB/ EVNNPT team on the salient features
of the revised delegation of power, benefits arising out of it and manner of implementation for
discussion with MoIT.
2. PwC will revise the draft approach note after incorporating the comments and suggestions from
EVNNPT/ ADB and submit the final approach note to EVNNPT.
3. NPT will discuss the approach note with EVN and MoIT for their approval; and MoIT in
consultation with EVNNPT and other stakeholders formulate a new circular notifying the new
delegation of powers.
Pre-requisites for implementation
1. The approval of EVN and MoIT will be required for the implementation of the revised delegation of
power.
2. The implementation of revised delegation of powers shall be a policy level change and all related
circulars/ decisions/ decrees which refers/relies on the Decision No. 1368/QD-EVNNPT, 2013
needs to be revised to reflect the changes in the delegation of power.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 131
Potential barriers in implementation
1. The decentralization of powers especially pertaining to financial decisions is often encountered
with resistance from the top levels of management.
2. The staff on positions where the additional financial and administrative powers will be conferred
upon may not be mentally ready to assume additional responsibility due to legacy issues. Thus
Change Management becomes imperative in this case.
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Overview
Title Utilisation of funds generated through accelerated depreciation
Dimension Strategy
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft approach note: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. At present, there is no governing regulation/ guideline for the utilisation of funds generated
through the depreciation allowed by ERAV as a part of the transmission charges. In the absence of
the regulation/ guideline, the fund generated through the deprecation is being used to fund the
capital investment requirements. This fund should ideally be utilised to repay the loan amount. It is
important to have a guideline/ framework for the utilisation of depreciation funds considering the
following facts:
a. There is a significant mismatch in the depreciable life of assets (8-12 years) allowed by
ERAV for the recovery of transmission charges and the repayment tenure of loan (25-30
years);
b. The actual useful life of the fixed assets is significantly different from the useful life
considered for the determination of depreciation by ERAV;
c. No equity infusion by the equity shareholders to finance the self-funding requirement;
d. No return on equity allowed by ERAV to finance the investment projects; and
e. There is no certainty in the existing regime that the upward revaluation of assets will be
considered by ERAV for the determination of depreciation forming part of the
transmission charges.
2. The approach note will provide a platform to discuss the importance of allowance of return on
equity for the financial sustainability of the EVNNPT on long-term basis. It will assist the
management of EVNNPT, EVN and MoIT to understand the long-term consequences of
inappropriate utilisation of the depreciation fund.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 132
Description
1. The approach note shall contain the followings:
a. Brief of the existing arrangement for utilisation of depreciation funds;
b. Need for monitoring the utilisation of depreciation funds. It will highlight the potential
risk issues which may arise due to the existing arrangement in future;
c. Comparison of the following two methodologies for funding the capital investment
projects:
i. Continue with the existing arrangement to fund the capital projects by charging the
accelerated depreciation fund; and
ii. Increase the return on equity for funding the capital investment requirement.
d. Comparison with the global industry practice for the utilisation of depreciation fund. We
will also provide the comparison of the depreciation rates across asset classes being
allowed/ charged in other countries for transmission assets;
e. Benchmark the return on equity being allowed under similar regulated framework in other
countries for power transmission sector;
f. Propose a framework to establish adequate return on equity to fund the capital investment
requirement without any significant increase in the transmission charges. In other words,
the approach note shall propose that the accelerated depreciation will be replaced with
adequate return on equity without having any significant impact on the consumer prices;
and
g. Highlight key challenges in implementation and our suggestion (in any) to overcome these
challenges in an efficient manner.
Implementation steps
1. PwC will submit the draft approach note to EVNNPT for discussions and inputs. If required, PwC
will conduct detailed discussions and presentation to ADB/ EVNNPT team on the salient features
of the approach note, benefits arising out of it and manner of implementation for discussion with
MoIT.
2. PwC will revise the draft approach note after incorporating the comments and suggestions from
EVNNPT/ ADB and submit the final approach note to EVNNPT.
3. NPT and ADB will discuss the approach note with EVN and MoIT for their approval.
4. NPT, MoIT and ADB will conduct discussions on the approach note with MoF (if required) for
review and implementation.
5. After the approval of MoIT and MoF, ERAV will formulate and issue required decisions/circulars
on the new depreciation rates and return on equity to be allowed for transmission investments.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 133
Pre-requisites for implementation
1. Prior to implementation, a clear understanding is required among various stakeholders- EVNNPT,
EVN, ERAV, MoIT, and MoF that the change in the methodology is essential for the long-term
financial sustainability of the EVNNPT and it will not have any significant impact on tariff.
2. The actual implementation will require change in the regulatory policy/ decision/ circular for the
determination of depreciation.
Potential barriers in implementation
1. The implementation will require approval from various stakeholders such as management of
EVNNPT, EVN, ERAV, MoIT and MoF. Obtaining approval from various stakeholders might be a
potential barrier in the implementation of the recommendation.
2. The increase in return on equity might face resistance from public. The public might misinterpret
the increase in return on equity with the increase in profitability. An appropriate communication
strategy will be required to convey the fact that there is no increase in overall tariff along with the
reason of increasing the return on equity.
Recommendation#3: Strategy for risk management against foreign exchange variation
Overview
Title Strategy for risk management against foreign exchange variation
Dimension Strategy
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft approach note: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. A significant portion of the total capital investment requirement is being met by the foreign
currency funds, i.e., ODA or loan from other International Commercial Banks. On the other hand,
there is no framework available with EVNNPT under which it can hedge its foreign currency
variation for repayment of loan and payment of interest charges. There have been significant losses
in the past on account of foreign exchange variation. The approach note shall propose hedging
structure and principles to reduce such losses in future.
2. Due to the flexibility allowed to EVNNPT in respect of not showing the forex fluctuation losses/
expenses in one year, they are able to show profit in their financial statement and are paying
income tax on this book profit causing further erosion of funds which in reality does not exist. The
approach note shall also discuss in depth such anomaly and propose changes with an objective to
optimise the cash flow of the EVNNPT.
Description
1. The approach note shall include the following components:
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 134
a. Risks arising of the un-hedged foreign exchange exposure;
b. Framework existing in other countries to manage foreign exchange exposure;
c. Hedging process that may be adopted by EVNNPT;
d. Possible instruments and markets for hedging;
e. Organizational requirements to manage the hedging process; and
f. Highlight the changes required in the existing framework.
Implementation steps
1. PwC will submit the draft approach note to EVNNPT for review and inputs.
2. PwC will revise the draft approach note after incorporating the comments and suggestions from
EVNNPT and submit the final approach note to EVNNPT.
3. NPT and ADB will discuss the approach note with EVN and MoIT for their approval.
4. NPT, MoIT and ADB will conduct discussions on the approach note with MoF (if required) for
review and implementation.
5. After the approval of MoIT and MoF, the MoF will formulate and issue required decisions/circulars
in respect of establishment of framework for risk management against foreign exchange variation.
Pre-requisites for implementation
1. It is pertinent for the EVNNPT, EVN, MoIT and MOF to understand the need for establishment of
the hedging mechanism.
2. NPT would need a small team of professionals with good exposure to hedging process.
3. The historical movements of VND vis-à-vis USD is an important parameter in ascertaining the cost
of hedging. In case the VND has been very fluctuating currency, the cost of hedging may actually
outstretch the benefits of hedging. Hence it is pertinent to assess the potential cost of hedging
through discussions with multinational/ global banks.
4. Hedging is dependent on the liquidity of the currency in global market and hence it would be ideal
to understand the liquidity scenario through discussions with various multinational/ global banks
with large trading desk.
5. The cost of hedging needs to be treated as a cost of financing and has to be a pass through
component in the tariff. Thus the transmission pricing framework would also need to be revised to
incorporate this.
Potential barriers in implementation
1. The liquidity position, i.e., demand-supply scenario of VND vis-à-vis free market currencies such as
USD and Euro is an important aspect in the establishment of hedging mechanism. In case the
demand for VND is very low compared to the supply, the hedging might be difficult.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 135
2. The implementation will require the approval from various stakeholders such as management of
EVNNPT, EVN, ERAV, MoIT and MoF. Obtaining approval from various stakeholders might be a
potential barrier in the implementation of the recommendation.
Recommendation#4: Prioritization of the investment projects
Overview
Title Prioritization of the investment projects
Dimension Process
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft report: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. At present, there is no tool/ system/ process/ regulation in place based on which the decision in
respect of prioritization of projects can be made. All projects which are technically feasible are
considered to be eligible for the implementation.
2. Considering the limited funds/ budgets in EVNNPT, the prioritization is essential to determine
which projects have to be immediately implemented and which projects can be delayed.
3. There is a requirement of a robust framework to assist EVNNPT in undertaking investment
decision particularly in respect of prioritization of projects which will be based on the technical
importance (reliability) and the commercial and financial viability of the project.
4. The evaluation framework for selection of project shall be more robust and effective to carry out a
cost benefit analysis of the proposed capital investment.
Description
1. The framework shall identify key technical, commercial and financial parameters to be considered
for prioritisation of the investment projects along with typical cut-off and qualification levels.
2. The framework shall also highlight the importance/ weightage of each of the parameters (technical,
commercial and financial) so as to enable informed decision making from EVNNPT.
3. It shall also outline the process to be adopted while prioritization of the proposed investment
projects.
Implementation steps
1. PwC will submit the draft framework to invite suggestions from EVNNPT.
2. PwC will revise the draft approach note after incorporating the comments and suggestions from
EVNNPT and submit the final approach note to EVNNPT.
3. NPT will discuss the framework with EVN and MoIT for their approval.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 136
4. After the approval of EVN and MoIT, the MoIT will formulate and issue required
decisions/circulars in respect of establishment of framework for prioritisation of the investment
projects.
5. PwC will also help the staff to get acquainted with the mechanism of project prioritisation by
providing training in this regard.
Pre-requisites for implementation
1. The existing evaluation framework followed by various departments, PTC and PMB needs to be
scrutinized in depth to ensure that no critical parameter is left out.
2. If any integrated IT/ MIS tool is being developed, this framework should also be incorporated into
the integrated IT/ MIS tool. However, in this case staff will require training to get them familiarised
with the basic level IT system knowledge.
Potential barriers in implementation
1. This entire exercise of prioritising the projects will make some of the projects as low priority; there
might be resistance from the offices/ teams who are sponsors of the projects.
2. There is a possibility that at the time of evaluation of proposed capital investment projects using
this framework, a project of strategic nature such as cross border transmission project may get
rejected. Hence the rejected projects should be reviewed by a dedicated committee to ascertain if
the project can be delayed.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Overview
Title Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Dimension Technology
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft financial models: Eight weeks from signing of MoU between ADB and EVNNPT
Rationale
1. The existing financial model being used by EVNNPT for the financial and economic appraisal of
projects is outdated. It is not adequate to evaluate an investment proposal on all the economic and
financial parameters. The model calculates some key financial metrics such as NPV and IRR but is
not flexible to offer a variety of views for different stakeholders. This model is based on the
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 137
assumptions and guidelines provided in the Decision No. 445, which is quite outdated and doesn’t
fit in the present context.
2. The project financial model shall facilitate EVNNPT in taking prudent and informed decisions on
capital investments which are really required from commercial point of view. The project financial
model shall bring about standardization and transparency in investment decisions. It shall provide
credible information to various stakeholders such banks/ financial institutes/ donors to enable
them in taking a prudent decisions on the tenure and amount of the loans.
3. In the existing framework, it is the responsibility of CPD in EVNNPT to identify the funding source
for the projects. The CPD identifies the funding sources for a proposed project in consultation of
F&A department. While selecting the funding source, the CPD does not prepare any detailed
financial model/ tool to analyse that which source is beneficial and is aligned to the overall future
cash flows of EVNNPT in future.
4. There should be a detailed corporate financial model to assess the impact of selection of funding
sources for each project on the overall cash flow of the EVNNPT. The entire loan portfolio should
be balanced with short-term, medium-term and long-term repayment options. It should be worked
out with the help of a detailed financial model/ tool considering various scenarios.
Description
1. Both the financial models (project financial model and corporate financial model) shall be
developed using MS Excel spreadsheets which shall have inputs sheets, working / calculations
sheets and output sheet. The output sheets will be determined in consultation with EVNNPT.
2. The financial models shall have self-checks and balances to identify any error.
3. The financial models shall provide facility of scenario analysis by adjusting specific inputs
parameters. The financial models shall provide scenarios for various key leverage ratios such as
debt service coverage ratio, interest coverage ratio, debt/equity ratio under different funding
models for the project.
4. The financial models shall incorporate prevailing statutory guidelines of EVN, EVNNPT, MoIT and
MOF.
5. Various aspects of the project financial model such as transmission losses, depreciation, O&M costs
and discounting rates shall be aligned to the transmission pricing principles/ regulatory guidelines/
actuals so that the model would be a true reflection of future expectations.
6. The corporate financial model shall take in inputs from the existing annual financial statements,
individual project financial models, loan repayment schedule, future capital investment plan,
funding options, projection of transmission pricing, etc.
7. PwC shall also prepare operating guidelines for both the financial models and make a presentation
thereof to the users in EVNNPT.
Implementation steps
1. PwC will submit the draft financial models along with the operating guidelines to EVNNPT for their
comments and suggestions. If required, PwC will also make a presentation to EVNNPT in respect of
the key features of the financial models and benefits of the financial models.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 138
2. PwC will revise the draft financial model after incorporating the comments and suggestions from
EVNNPT and submit the final financial model to EVNNPT; and
3. PwC will also conduct training for identified EVNNPT staff.
Pre-requisites for implementation
1. The users shall need to have basic understanding of MS Excel and finance parameters including
description and use of key financial ratios.
2. The new appraisal and fund identification process may now entail greater analysis prior to decision
making and hence staff will have to invest more time and effort to get accustomed to the new
process/ financial models.
3. The Decision No. 445, 1994 shall also need to be revised in lines with the new industry structure
and regulatory regime in place.
Potential barriers in implementation
1. The existing financial model based on the Decision No. 445, 1994 is being used by EVNNPT/ EVN
for a long time. Therefore, the change in the financial models might be resisted from the users/
staff from EVNNPT.
Recommendation#6: Develop alternate modes of project funding
Overview
Title Develop alternate modes of project funding
Dimension Process
Category Long-term (18-36 months)
Timelines (indicative)
Submission of draft approach note: Four weeks from signing of MoU between ADB and EVNNPT
Presentation to EVNNPT: One week from the finalisation of the approach note
Rationale
1. At present, EVNNPT is facing challenges to fund its capital expenditure requirement due to the
following reasons:
a. No equity infusion by the equity shareholders;
b. No adequate return on equity is allowed in the tariff order to generate retained earning
which can be used for self-financing; and
c. No possibilities to raise fresh equity from capital markets to fund its investment.
2. NPT currently is forced to utilize the surplus depreciation fund to finance its equity contribution in
capital expenditure. The depreciation period is lower than the loan repayment period as elaborated
in the earlier section. This allows some surplus revenue for EVNNPT to invest into the capital
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 139
projects. However, such a practice may be dangerous in long run. It’s against the basic finance
principles. It may lead to debt trap situation in future.
3. There appears to be no innovative self- financing options such as sweat equity, Public Private
Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT), Build Own Operate
Transfer (BOOT) like used in India, Brazil, etc. These alternative routes of financing projects shall
reduce the financing and execution burden on EVNNPT.
4. Most of the financing routes are implemented through competitive bidding process and hence
would lead to higher efficiency in terms of project development and may also lead to lower prices.
5. Implementing such routes of financing will significantly enhance the financing and execution
bandwidth of EVNNPT and company can focus on strategic projects.
Description
1. The approach note shall detail out select experience of other countries in implementing alternate
modes of financing.
2. The approach note shall identify practical modes of financing that may be adopted by EVNNPT to
execute projects. It shall highlight the following:
a. Brief of the alternative options;
b. Name of countries where these options have been implemented;
c. Benefits and weaknesses of the alternative routes;
d. Implementation challenges; and
e. Implementation roadmap.
3. The approach note shall also indicate possible entry routes such as tariff based bidding, bidding
based on requirement of capital subsidy/grant, bidding based on technical experience, nomination
etc.
Implementation steps
1. PwC will submit the draft approach note to EVNNPT for discussions and inputs. If required, PwC
will conduct detailed discussions and presentation for ADB/ EVNNPT team on the salient features
of the approach note, benefits arising out of it and manner of implementation for discussion with
MoIT.
2. PwC will revise the draft approach note after incorporating the comments and suggestions from
EVNNPT/ ADB and submit the final approach note to EVNNPT.
3. NPT and ADB will discuss the approach note with EVN and MoIT for their approval.
4. NPT, MoIT and ADB will conduct discussions on the approach note with MoF (if required) for its
review and implementation.
5. After the approval of MoIT and MoF, MoIT may initiate preparation of guidelines and standard
transaction (or bidding) documents along with issuance of necessary circulars/ decrees/ decisions.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 140
Pre-requisites for implementation
1. The alternative financing options might require a policy and legal framework in place to get them
implemented. It will require preparation of standard bidding documents, guidelines for selection of
private players and also appointment of a nodal agency/ department to take care of alternate
financing routes.
2. Prior to implementation, a clear understanding is required among various stakeholders- EVNNPT,
EVN, ERAV, MoIT, Ministry of Justice and MoF that the alternative financing options are essential
for the long-term financial sustainability and efficient functioning of the EVNNPT.
3. Support shall be required from IDAs to fund the complete process of preparation of guidelines and
bidding documents.
Potential barriers in implementation
1. Implementing alternative routes of financing is a key strategic change and requires convincing the
highest levels of Government which may, sometimes, be difficult and time consuming.
2. Often the sponsoring company (in this case EVNNPT) is too engrossed on carving out its role in the
entire process due to which the primary objective is lost during the process.
3. Alternate routes of financing are often looked upon as a radical shift in the policy, and they may be
met with opposition at early stages.
Recommendation#7: Process improvement in the investment planning process
Overview
Title Process improvement in the investment planning process
Dimension Process
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft report on process improvement: Eight weeks from signing of MoU between ADB and EVNNPT
Rationale
1. There is a requirement of re-engineering of investment planning process due to the following
reasons:
a. The investment planning process in EVNNPT requires a period of 24 months to 36 months,
whereas in other countries the time taken is 6-8 months;
b. All projects, planned/ unplanned go to MoIT for first stage approval because the annual
implementation plan is not approved by MoIT. It results into significant delay;
c. Under the current process of approvals, there is no distinction between critical projects vs
non-critical projects and small projects v/s large projects;
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 141
d. The multiple rounds of approval from MoIT (3-4 times) while ensures greater oversight but
may lead to significant delays in implementing critical projects;
e. The detailed technical design for all projects, irrespective of the size and importance, are
screened by external consultants on behalf of MoIT. This is a time consuming process. In
case of smaller projects which are standard system strengthening / replacement projects, it
may be cost and time effective to rely on the evaluation of technical department in
EVNNPT; and
f. In case of fund raising from ODAs/OICB, various MOF, MoIT and MOJ are involved for
each and every project. In case of ODAs, the approvals from prime minister and president
are also required. It results into significant delay.
2. Considering the huge capital investment plan, there is a need of a long-term IT enabled business
process improvement initiatives which will bring in greater efficiency, transparency and control.
Description
1. The report shall:
a. Contain the complete activity level details of the existing process along with key process
related information such as lead time, inputs/ outputs/ mode of implementation;
b. Highlight the key issues/redundancies at the activity level. It shall help identifying the key
lacunas in the existing process including in depth analysis of the lead time, approvals,
input/output, mode of implementation etc.;
c. Benchmark the process on broad level with the processes followed in other countries; and
d. Suggest the re-engineered process for investment planning.
2. The report shall outline the restructured process intended to achieve two key objectives:
a. Reducing the lead time by cutting out the unnecessary redundancies in the process; and
b. Reducing costs through leveraging strengths in internal departments for projects of lower
ticket size.
Implementation steps
1. PwC will submit the draft report to EVNNPT for discussions and inputs. If required, PwC will
conduct detailed discussions and presentation for ADB/ EVNNPT team on the proposed re-
engineered process, benefits arising out of it and manner of implementation for discussion with
MoIT.
2. PwC will revise the draft report after incorporating the comments and suggestions from EVNNPT/
ADB and submit the final approach note to EVNNPT.
3. NPT and ADB will discuss the report with EVN and MoIT for their approval.
4. After the approval of MoIT, EVNNPT may initiate preparation of relevant Circulars/Decisions/
Decrees to implement/ operationalise the process improvement initiatives for the submission to
MoIT for approval.
Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 142
Pre-requisites for implementation
1. It will require a policy level change at MoIT level, therefore it is pertinent for the EVNNPT, EVN,
and MoIT to understand the need of re-engineering of the investment planning process.
2. The implementation of re-engineered investment planning process will require changes in all the
related circulars/ decisions/ decrees which refer to investment planning process.
Potential barriers in implementation
1. Similar to organization change, process change initiatives may entail significant change
management effort. It is often seen that staff and management are resistant to any process change
which may disturb the inertia of the organization.
2. The implementation will require the approval from various stakeholders such as management of
EVNNPT, EVN, and MoIT. Obtaining approval from various stakeholders might be a potential
barrier in the implementation of the recommendation.
3. Process change is often a long and tedious process and hence continuous involvement of dynamic
champions at every point is desirable.
4. Process change often fails due to initial difficulties faced by the staff. They often move back to the
original way of doing things. It is a slow process but highly beneficial in long run.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 143
Project management
Recommendation#1: Standardization of designs, specifications and layouts
Overview
Title Standardization of designs, specifications and layouts
Dimension Strategy
Category Long-term (18-36 months)
Timelines (indicative)
Submission of draft approach: Four weeks from signing of MoU between ADB and EVNNPT
Discussion & submission of final approach: Two weeks after submission of draft approach
Rationale
1. Standardization of designs, specifications and layouts will reduce engineering design and detailed
engineering time and hence reduces project development period (pre project preparatory
activities):
a. Standardization of equipment design and technical specifications offer multiple benefits;
b. Type tests, unlike routine tests, are done on first prototype of an equipment to confirm
that the equipment meets design specifications and are not repeated on every unit
manufactured or fabricated. Hence, if equipment design is standardised, type testing can
be avoided since a type test certificate can be accepted for an agreed validity period (say 5
years for a transformer). This will help in reduction of project time. In case of towers, its
testing is generally a time consuming process and it will further increase in case of
different wind zones / voltage levels. Also, any failure of testing will delay the process
further;
c. Design standardization will help increase the pace of concomitant activities. For example,
Standardization of tower design will hasten up the tower foundation design since the tower
designs are available beforehand. Further, steel procurement can also start without waiting
for design finalization;
d. Standardization reduces requirement of spares (For example tower parts can be used
interchangeably); and
e. Increased acquaintance with standard designs for field supervisors as well as construction
contractors will help them speed up different activities.
2. Standardization of design and technical specifications for different power equipment is followed in
multiple developed and developing countries of Europe and Asia.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 144
Description
1. Our approach will identify various equipment whose design needs to be standardised and standard
technical specifications need to be developed along with possible parameters that affect them:
a. Design of transmission line towers and Specifications: The design of transmission line
towers (including foundation design) will be impacted by wind conditions, number of
turnings in the surveyed route (types of angle towers), various crossings, proposed voltage
level, soil conditions and resistivity. For example, in India, there are generally two types of
towers- Suspension and angle towers and angle towers are further classified depending on
angle of turn or crossing. The different tower foundations need to be standardised based
on soil conditions, tower type, height and structure;
b. Design of transmission line equipment and Specifications: Key transmission line
equipment consists of conductors and insulators. Number of sub-conductors in one phase/
circuit along with conductor type can be pre-determined (e.g.: ACSR twin moose, ACSR
Bersimis, AAAC conductor etc.) depending on line length, voltage level, climatic conditions
etc. Similarly, type of insulators viz. suspension, double suspension, tension strings etc.
and material for insulation (porcelain or glass or polymer) can be standardised depending
on voltage level and climatic conditions;
c. Design of substation switching schemes and layouts: Different switching schemes may be
adopted for different voltage levels. For example, in India it’s a common practice to adopt
different switching schemes for different voltage levels- One & Half breaker scheme or
Double Main and Transfer bus bar scheme at 400 kV level and Double Main & Transfer
scheme or Double Main with breaker by pass scheme at 220 kV level. Further, based on
the switching schemes, the substation layouts may be standardised; and
d. Design and Specifications of Substation equipment: Standardisation in design of
substation equipment like power transformer, reactor, current transformer, potential
transformer, surge arrestor, bus bars, relays, circuit breakers, insulators, fittings and
accessories clamps and connectors, substation structures with beams and columns, control
room layout, wiring and cable connectors, fire protection system can reduce the time
during execution. All these equipment and layout design drawings can be standardised to
the extent possible to avoid repetitive design process. Also, standardizing technical
specifications for this equipment will help avoid repetitive testing and approval process.
2. We will discuss and finalize with EVNNPT about the extent of standardization possible in
transmission lines and substations and will prepare an approach as follows:
a. Process to be followed for standardization; and
b. Roles and responsibilities of the team involved in the standardization and frequency of
team meetings.
Implementation steps
1. We will prepare an approach on standardization to EVNNPT.
2. We will discuss the approach with relevant teams/ departments/ subsidiaries of EVNNPT and
finalize it.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 145
Pre-requisites for implementation
1. None.
Potential barriers in implementation
1. This is an ongoing process and based on implementation experience additional equipment and
materials design /specifications may have to be standardised or removed from the standardization
list. Experience need to be reviewed with the feedback from PMB/PTC and contractors.
2. Continuous monitoring and support is needed from top management.
3. Concerned teams/ departments/ subsidiaries of EVNNPT should be convinced of the need and
benefits of standardization.
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Overview
Title Adoption of full/part turnkey (supply cum erection) contracts
Dimension Process
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft approach: Four weeks from signing of MoU between ADB and EVNNPT
Discussion & Submission of final approach: Two weeks after submission of draft approach
Rationale
While executing the individual supply and erection contracts, the organization faces following issues:
1. Lack of single point responsibility: Each contractor will be responsible for its own supply/design /
erection package and coordination of multiple vendors has been a challenging task for the
EVNNPT. Degree of complexity in coordination increases with number of vendors/ contractors.
2. Completion risk with EVNNPT: The PMB Deputy Directors carry the responsibility and risk of
timely execution of projects while coordinating with multiple vendors, contractors and consultants.
Design consultants will not be responsible for deficiencies in construction /erection activities and
vice-versa; Finding out the responsibility of any defect lies with EVNNPT which decreases the
accountability on the part of contractors/ consultants.
3. Difficulty in matching of procurement & erection schedules: Matching of schedule of procurement
of equipment/ material with the requirement at site for erection contractors is a challenging task.
The supply of equipment to erection contractor can be delayed due to reasons like delay in
procurement by the concerned department, delay in transport of equipment from stores, diversion
of material to any other site due to an emergency etc. and this leads to delay in project execution.
On the contrary, if the equipment lies idle in stores of EVNNPT, and there is a delay on part of
erection contractor mobilization, it leads to quicker expiry of guarantee periods which is also a loss
to EVNNPT.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 146
4. Probable low response from contractors: The erection contracts are limited to only electrical and
civil erection works and hence the value of such contracts will be low. This will not be commercially
interesting option for established contractor. This leads to sub-optimal response rate from
established and reputed contractors.
The turnkey or part-turnkey execution can be used to resolve these issues.
Description
1. Single Point Responsibility: In Turnkey execution, all the activities from detailed engineering,
procurement of stipulated equipment and materials, arranging for testing and inspection,
interactions with various sub-vendors, timely erection, testing & commissioning will be the
responsibility of the main turnkey contractor.
2. Reduction of workload & risk of EVNNPT: This will reduce significantly the risk and thus work load
of EVNNPT since the coordination efforts will be reduced and the supply-cum-erection contractor
will bear major responsibility of timely execution of contracts. Also, the above mentioned issues like
wastage of guarantee period while the equipment lies idle in store, possibility of disputes with
erection contractors for delay in providing equipment/ materials etc. will be addressed.
3. Value addition by EVNNPT: EVNNPT can enhance value by timely interventions, monitoring and
focus on enhancing quality of the execution by any procedural changes and new initiatives.
4. Packaging Concept in turnkey projects: A transmission system project should be divided into
clearly defined packages in such a way that the packages can be executed without any coordination
and interfacing issues and at same time attract competitive bids. So, Package list is prepared based
on cost of the package, location, availability of equipment and/or materials, completion schedule
etc. In Indian 400 kV transmission lines, it has been observed that foundations, tower supply &
erection, conductor & stringing and insulators constitute about 15-20 %, 35-40%, 40-45%, 5-7%
respectively of total cost. As separation of supply of towers and related works like foundations,
erection & stringing leads to interfacing and coordination issues, conductor and insulator packages
are separately bid out depending on value and all other associated supply and erection works of
transmission line are bid out as single package. Similarly, in case of substations supply and
installation of transformer and reactor packages are separately bid out where as all supply -cum
erection including civil works are bid out as a turnkey package. So, some of the possible packaging
concepts that can be considered for turnkey execution are:
a. In case of multiple lines and substations of a project, transformer, reactor, conductor and
insulators can be centrally procured as they are high value items and procurement of
remaining line equipment can be clubbed with the erection contract(s) of lines;
b. In case of a single substation package, the entire substation can be awarded to a single
contractor including transformer or reactor;
c. In case of a single transmission line package, both conductor and insulator packages can
be included in the single supply-cum-erection contract; and
d. In case of long transmission lines that need urgent execution, the total line supply-cum -
erection packages can be split according to distance and awarded to two or more
contractors.
5. Reduced Time & Cost over runs: A properly planned turnkey project will reduce time and cost over
runs since the main contractor can plan certain design and execution activities in parallel and can
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 147
match its procurement schedule of required equipment with overall erection schedule. A timely
execution of project will avoid additional costs like interest during construction that would have
been incurred if there is delay in projects due to mismatch in schedules of erection and supply
contractors.
Implementation steps
1. We will prepare an approach which will contain the following:
a. Identify the real barriers for turnkey execution of contracts as per EVNNPT and suggest
approach to overcome the barriers; and
b. Possible supply cum erection packages viz. supply-cum-erection package of transmission
towers including foundation and stringing, supply packages of conductor and insulator,
supply-cum-installation packages for transformer and reactor, supply-cum-erection
package of substation.
2. We will discuss the approach with relevant teams/ departments/ subsidiaries of EVNNPT and
finalize the responsibilities for development of standard bidding documents for turnkey projects,
changes in procurement policy and procedures and delegation of powers.
Pre-requisites for implementation
1. Changes in procurement policy, procedures and packaging policies or norms in EVNNPT to
incorporate turnkey execution model.
2. Appropriate qualifying requirements with criteria on technical and financial capabilities of bidders,
similar past experience, clear conditions for joint venture /consortium of supply and erection
contractors.
3. Technical specifications have to be defined for different equipment and a list of approved sub-
vendors/ suppliers is made available so that time for testing can be reduced. Standardization of
designs and specifications will not only help in reducing the time for pre-construction activities but
also reduce the chance of disputes in future.
4. Adequate time is to be given for bid submission since contractors need time for tying up with
various supply vendors. Also, appropriate type of bid process (single-stage or two-stage) has to be
chosen depending on nature and complexity of projects.
5. Comprehensive bid documents with clear scope of contractor, identification of responsibilities of
contractors and EVNNPT, proper price variation indexing, adequately defined payment milestones,
guaranteed performance & technical parameters, penalties for delay or faulty equipment, issue
escalation and dispute redressal mechanism etc.
6. Effective project monitoring system / tool for timely interventions by EVNNPT.
7. Efficient payment mechanism to contractors for completed milestones.
8. Vendor capacity development initiatives are needed since this will be a new regime for contractors
as well. Also, vendor development initiatives are needed to develop domestic vendors’ capabilities
as turnkey contractors (reserving a certain percentage of packages that meet certain criteria to new
contractors).
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 148
Potential barriers in implementation
1. Continuous monitoring and support is needed from top management and sustained interest to be
inculcated in concerned team members. Concerned teams/ departments/ subsidiaries of EVNNPT
should be convinced of the need and benefits of standardization.
2. Any delay in meeting prerequisites or non-implementation of pre-requisites may result in a delayed
project execution and which may set a bad precedent even for future efforts on implementation of
the turnkey regime.
3. Capabilities of contractors/ vendors in understanding and adapting to the turnkey regime.
Recommendation#3: Develop a project risk management strategy
Overview
Title Develop a project risk management strategy
Dimension Process
Category Short term (0-6 months)
Timelines (indicative)
Submission of draft risk management strategy: Three weeks from signing of MoU between ADB and EVNNPT
Discussion & submission of final strategy: Two weeks after submission of draft approach
Rationale
1. Every project faces risks. Risk is an uncertain event or condition which, if occurs, has negative
effect on the envisaged project outputs and results in issues like time over run, cost over-run, poor
quality execution resulting in increased O&M or poor system availability etc.
2. Risk assessment is an integral part of effective project management. Identifying risks and
incorporating possible mitigation measures in the project planning phase will help in smooth
execution.
Type of Risks Can be mitigated Cannot be mitigated
Can be envisaged
Risk mitigation measures using qualitative or quantitative tools (prioritize based on impact and possibility)
Force majeure conditions; Risks to be absorbed by respective parties
Unknown risks No mitigation possible (Prepare a contingency plan based on past experiences)
Description
1. An integrated Project Risk Management Plan has to be prepared along with detailed design/
Project feasibility study. This should identify all possible risks, their probability of occurrence,
impact on project outcomes viz. technical performance, cost, completion schedule, execution,
safety, security and environment impact. This plan also addresses the extent of risk carried by all
the stakeholders and whether risk can be transferred between stakeholders so that the stakeholder
who is most capable to manage a risk will bear the particular risk. Also, adequate risk-return
balance has to be maintained among stakeholders.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 149
2. The risk management plan addresses risks in all phases of the project - viz., design, approvals,
financing, contractual, procurement, construction, completion and have mitigation strategies for
various risks.
3. The risk management strategy provides a holistic view of risks, challenges and potential problems
and builds processes that help mitigate the risks and reduce the “risk premium costs”. This also
gives a clear picture of project risks and strengths to the top management.
4. Project risk management helps the top management and monitoring teams/ authorities to validate
and communicate project progress and risks, evaluate and quantify project processes against
benchmarks and ensure project accountability and stakeholder management.
5. A sample risk management strategy is defined below. Only a sample set of risks are identified and
detailed risk management strategy will be developed subsequently.
Implementation steps
1. We will develop a risk management strategy and finalize it based on discussion with concerned
team/departments. This will be a dynamic and living document, and has to be updated and
modified in the light of the experiences gained with implementation of projects.
Pre-requisites for implementation
1. None.
Potential barriers in implementation
1. Support from top management needed in making it a mandatory practice in project planning
phase.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 150
Sample Risk Management Strategy
Risk Description Probability of occurrence
Potential impact
Risk score
Risk mitigation strategies
Design Risks
Wrong design Wrong design of equipment, unsuitable technical specifications for equipment, inappropriate design scheme or layout etc.
Low High Standardization of designs and technical specifications will reduce the need for designing equipment or formulating specifications for every project.
XXXX
Bidding Risks
Time over run Time over run in bid document preparation, conduct of bid process, contract negotiations etc.
Medium High Could be reduced by efficient project management coupled with strong knowledgeable project team. Seeking proactive bidder co-operation will reduce time overruns
XXXXX
Commercial Risks
Increase in costs of materials
Construction cost estimate may change due to changes in underlying cost of materials
Medium High The risk is less for short duration projects. However, in case of longer duration projects, the risk is high as steel, copper, aluminium, labour costs can increase which impacts tower parts, conductor, civil foundation and erection services etc. Price variation clauses with proper indexing will result in contractor not padding up the bid. However any profit or loss due to increase or decrease in costs has to be borne by EVNNPT.
XXXXX
Financing Risks
Increase in interest costs, forex risk
Construction cost estimates may change because of increase in interest rates and forex rate (in case of foreign loan)
Low Medium The risk is less for short duration projects. However, in case of longer duration projects, the risk is high. The risk can be mitigated by hedging the loan value with the financial institution
XXXXX
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 151
Risk Description Probability of occurrence
Potential impact
Risk score
Risk mitigation strategies
Construction Risks
Delay in construction Construction activity delayed due to issues like Right of way clearance, land acquisition issues, delay in mobilization of labour, climatic conditions
High High Following stipulated procedures for acquiring Right of way and regular communication to general public at various phase of project Also, selecting experienced contractors and monitoring the project performance regularly by concerned EVNNPT officials will lessen the probability of occurrence of these events
Commissioning Risks
Delay in testing Delay in testing and commissioning due to reasons
xxxx xxxx xxxxxxx
XXXXX
There are many other risks like delay in approval, force majeure conditions, accidents, government regulation etc. which will be elaborated subsequently
Notes:
Probability of occurrence
Potential impact Overall score Risk
Low Low 1 Low Risk
Low Medium 2
Low High 3 Moderate Risk
Medium Medium 4
Medium High 6 High Risk
High High 9
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 152
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement
Overview
Title Developing IT tools for project monitoring, inspection and online procurement
Dimension Technology
Category Long term (18 months- 36 months)
Timelines (indicative)
Not Applicable (To be performed by EVNNPT)
Rationale
1. NPT or its subsidiaries do not have any integrated Project management system and some
departments in EVNNPT are using stand-alone packages/software developed by IT department of
EVNNPT along with MS office tools like MS Excel and MS Project for project progress monitoring.
In our interactions with multiple departments, need for a project monitoring tool has been
highlighted repeatedly for various reasons. This lack of visibility at corporate level / senior
management level is hindering effective project monitoring causing severe delays in project
execution.
2. NPT is now in the process of developing "Project Management Software" which is being developed
by EVNNPT's IT Department with the help of a consultant/contractor. However, stakeholder
interaction suggests that the software is more of a project information repository and status
reporting tool rather than project monitoring and management tool.
3. NPT or its subsidiaries do not currently have any online procurement system or inspection
management systems which can reduce the time taken for these processes, increase transparency
and streamline the process further.
4. An inspection management system will help in increasing the efficiency of the inspection process as
it will help both vendors and EVNNPT employees to plan their schedule well ahead and all call log
details can be easily retrieved by management for monitoring the loading of employees and success
rate of various calls which determines the vendor efficiency.
Description
1. Key features of the “Project Management Software” being developed by EVNNPT:
a. Web-based online application developed using "SharePoint" technology;
b. Developed by an external software development company named Harmony Software
Technologies JSC;
c. It will be installed in a central server of EVNNPT and will be accessed by all PMBs and
PTCs through internet; and
d. Seven modules: Project management, project planning, investment preparation,
investment implementation, investment completion, searching, administration.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 153
2. Ideally project management software for a transmission project should capture all the activities and
their dependencies, scheduling with timelines; estimate resourcing requirements for various
activities, monitor all the outputs; provide complete visibility to top management about physical
progress of project, funding and financing status and different issues hindering the project progress
w.r.t. schedule.
3. The software should be able to perform a scenario analysis considering at least best and worst case
scenarios. For example, what will be the delay in completion schedule if detailed engineering design
phase gets delayed by say, “x” days and what will be the increase in project cost (due to Interest
During Construction). Similarly, what will be impact on project cost due to change in interest rates,
foreign currency variation risk etc.?
4. Inspection management system:
a. The inspection management system will provide opportunity for contractors to register
themselves with the relevant work order details and log-in calls for inspection by EVNNPT
officials; and
b. Post successful completion of inspection, the contractors will provide a summary of
reports which are duly signed by the inspecting officer and the equipment’s acceptance is
provided for contractor.
5. An online procurement system should allow vendors/contractors to register themselves, apply for
bids, get notified of the amendments, pre-bid meeting etc.; upload technical, financial bids in the
system securely and access the final results of the bidding process.
Implementation steps
1. NPT needs to undertake a holistic review of its IT infrastructure, decide on requirement of an
integrated IT solution or disparate IT tools (for online procurement, inspection management
system, project management software) and prepare an IT strategy.
2. Since it is a long term process and there is a need for exhaustive study of prevailing IT tools and
there is ongoing project management software under development, there are no short term
measures.
Pre-requisites for implementation
1. Basic computer knowledge for the employees involved in operation of the systems as well as
availability of IT infrastructure (computers, internet connection, Local Area Network, routers etc.).
2. Selection of a competent IT vendor who understands the requirements clearly and can design the
IT tools accordingly.
Potential barriers in implementation
1. Reluctance of employees (if any) in adopting the systems.
2. Any glitches in implementation or delay in implementation may result in loss of interest of
employees.
3. Support needed from top management in ensuring that the employees adopt these IT tools and that
the teething problems, if any, are addressed speedily.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 154
Recommendation#5: Merger of FS & DTD phases
Overview
Title Merger of FS & DTD phases
Dimension Process
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft approach: Four weeks from signing of MoU between ADB and EVNNPT
Discussion & submission of final approach: Two weeks after submission of draft approach
Rationale
1. On an average, it takes around three years from project allotment letter to approval of Detailed
Technical Design (DTD) which is definitely very high and needs to be reduced for speedy
implementation of projects. This long time for design activities is due to heavily centralized
decision making process viz. no power with PMBs/ PTCs in approval and multiple rounds of
approval from MoIT; design verification by MoIT consultants; lack of standardization in technical
specifications and bid documents etc.
2. Among other things, merger of Feasibility Study (FS) and DTD phases can reduce this time
significantly.
3. Preparation of a part of detailed technical design, preparation of construction/ working drawings
should be the responsibility of supply cum erection contractor.
Description
1. In the current process, typical components covered under FS are:
a. System calculations like short circuit studies, dynamic and transient stability studies;
b. Line route survey with three options and suggest optimal route;
c. Tower spotting, layout and Estimate bill of quantities of equipment and material needed;
d. Basic design (standard designs and specifications are prepared and approved by
EVNNPT);
e. Total investment cost and financial analysis such as NPV, IRR, Benefit-to-Cost ratio;
f. Environment Impact Assessment (EIA) and Social Impact Assessment (SIA) and
Resettlement to minimise land needs and adverse impact on local people and
environment; and
g. Other aspects like fire prevention, telecommunication etc.
2. After FS approval, DTD consultants are selected and they prepare the detailed engineering/
technical designs and specifications along with bidding documents.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 155
3. In our suggested process, Feasibility Report or Detailed project report of a transmission line will
include the following:
a. Design, Technical Specifications and Construction standards for foundations, towers,
cables and insulators;
b. Quantities/numbers of different types of tower structures/poles, length of cables,
conductors etc., indicated as the BOQ schedule;
c. Project Packaging to attract suitable competition facilitating cost effective procurement.
The size & scope of the different packages depends on magnitude & location of project;
d. Cost estimation as per BOQ prepared of the various system elements (such as cables,
conductors, transformers, switchgears, capacitors, lightning arrestors and insulators, the
control and communication system, engineering and project management, supervision
and contingencies);
e. Project Implementation plan and schedule for the Project taking into account, system
constraints and other relevant factors;
f. Financial Analysis including proposed capital structure for the project;
g. Statutory and environmental clearances for project, if procured at this stage;
h. System operation requirements, based on applicable laws and grid code;
i. Operation and Maintenance Plan include facilities such as protection, communication,
measurement, telemetry and interface equipment etc.; and
j. Bid documents.
4. The final detailed technical design and further working/construction drawings vendor/suppliers
drawings will be prepared by the selected contractor.
5. In case, design and drawings are standardised and a list of pre-approved vendors is provided, the
contractor can start the procurement process without type tests and submit the construction
drawings to the EVNNPT.
Implementation steps
1. PwC will develop an approach with process before and after merger of FS & DTD phases. We expect
to receive written feedback or comments on the note and finalize it based on feedback.
Pre-requisites for implementation
1. No specific pre-requisites, but standardization of design and technical specifications will help in the
new process.
Potential barriers in implementation
1. Approval needed from top management of EVNNPT and MoIT as well which can delay the process.
2. Changes in regulations/ decrees may be a long drawn process.
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 156
Recommendation#6: Develop a strong and focused project management unit
Overview
Title Develop a strong and focused project management unit
Dimension Structure
Category Medium term (6-18 months)
Timelines (indicative)
Submission of draft approach: Four weeks from signing of MoU between ADB and EVNNPT
Discussion & submission of final approach: Two weeks after submission of draft approach
Rationale
1. There is a significant growth in the transmission network of Vietnam since 2008 as lines increased
by 40% & substation capacity increased by 62%. Further, EVNNPT is planning to augment its
transmission assets significantly during 2016-30:
a. 500 kV system - ~9500km lines, 71000 MVA transformer capacity
b. 220 kV system - ~16000 km lines,135000 MVA transformer capacity
2. At present, EVNNPT is facing issues in project completion in terms of time and cost overruns. The
factors contributing to the delay are a combination of uncontrollable and controllable reasons such
as delays in land acquisition, resistance from general public, lack of proper monitoring
methodology (IT tool), long time for various approvals and pre-construction activities etc.
3. Among other things, lack of an effective and integrated project management to ensure effective
monitoring and quick resolution of issues seems to be a critical gap.
Description
1. A dedicated PMU would efficiently coordinate with other stakeholders to ensure timely completion
of projects; in-turn optimises the project cost and effectively manages quality of projects.
2. The tentative roles of PMU can be:
a. Managing shared resources across different departments of EVNNPT and its subsidiaries;
b. Identifying and developing project management methodology, best practices;
c. Developing and managing project policies, procedures, templates and coordinating
communication between different departments, vendors/contractors;
d. Exception report to top management on various delays in project execution; and
e. Monitoring the quality management of projects.
3. Detailed Master Network: Preparation of this network for each project for completion of the project
on schedule will be a key role of PMU. The network should incorporate all the activities involved
and the time for completion of each activity. Methods such as Critical Part Method (CPM), Program
Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 157
Evaluation & Review Technique (PERT) can be adopted by the PMO for planning and scheduling
the master network. For example, steps in CPM method are:
a. Activity identification: Identify activities in different phases of the project from inception
to commissioning;
b. Activity precedence identification: Identify the dependent activities i.e. activities that
cannot start until the completion of another activity (say, Bill of quantities and costing of
projects cannot start until the completion of survey activity or Notice inviting tender
cannot be floated till approval of bid documents);
c. Network construction: The master network can be prepared using tools like Gantt chart,
MS project. Subsequently, time, cost and resource implications of a various activities in the
plan are decided; and
d. Critical path: Critical path determines the shortest possible time to complete the project. It
is the sequence of activities that add up to the longest overall duration. PMU can prepare a
detailed list of activities with help of concerned departments with their early and latest
start and finish times. Dependencies between different activities are already identified.
This will help in identification of critical path.
4. The contractor is also required to prepare a detailed network schedule of activities for completion
of work within time frame. After approval of EVNNPT, the PMU can check this based on the master
network prepared.
5. Project monitoring is to be regularly carried out by this PMU through review meetings and status
report is to be put up to the management. The monitoring parameters include financial as well as
physical progress parameters. In the review meetings various issues impeding project progress
have to be discussed and resolved.
Implementation steps
1. We will develop an approach identifying PMU cell members along with their responsibilities,
timelines for meeting. We will also interact with EVNNPT to understand whether a separate PMU
cell is beneficial or existing organization and manpower can be utilized or not.
2. We will finalize the approach based on inputs from EVNNPT officials.
Pre-requisites for implementation
1. Availability of Project management tools (IT tools) and corresponding infrastructure.
2. Adequate resource allocation and availability of skilled personnel who can effectively utilize the IT
tools.
Potential barriers in implementation
1. Lack of proper IT tools and hardware.
2. Lack of adequate and skilled resources.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 158
Transmission pricing
Recommendation#1: Conduct training on principles of regulatory economics and international practices
Overview
Title Conduct training on principles of regulatory economics and international practices
Dimension People
Category Short-term (0-6 months)
Timelines (indicative)
Submission of training material: Two weeks from signing of MoU between ADB and EVNNPT
Conduct the training: Two weeks from submission of training material
Rationale
1. To fully be able to appreciate all the suggested modifications to regulations and processes, it is
necessary that all relevant staff is conversant with primary principles of regulatory economics.
2. The understanding of practices and principles applied in other countries to compute transmission
revenue and charge and handle associated issues will enable the staff to be more open to change as
well as understand the long standing benefits to such modifications.
3. Successful implementation of any recommended modifications depends largely on the skills and
competency levels of the stakeholders.
Description
1. PwC will develop suitable training material in form of MS Power Point and MS Word. The material
shall also include select international practices and case studies.
2. PwC will keep in mind framework and issues specific to Vietnam while developing the training
material.
Implementation steps
1. PwC will submit the training material to EVNNPT.
2. PwC will conduct the training for EVNNPT team and seek feedback of participants after training.
Pre-requisites for implementation
1. Identified participants of the training shall have basic understanding of technical and financial
aspects of transmission sector.
Potential barriers in implementation
1. No specific barriers identified.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 159
Recommendation#2: Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations
Overview
Title Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations
Dimension Strategy
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft proposal: Two weeks from signing of MoU between ADB and EVNNPT
Discussion on draft proposal: Two weeks from submission of draft proposal
Submission of revised draft proposal: Two weeks from discussion on draft proposal with EVNNPT
Rationale
1. At present Circular No. 14 & 3 ("regulations") guide the overall process for determination of Total
Power Transmission Revenue (TPTR) and Transmission Charge (TC) along with procedure to be
followed for submission of the application (petition) by EVNNPT, review by EVN and approval by
ERAV. The current methodology followed is nationally uniform, flat energy-based charge. It does
not reflect power flow path, distance, direction, delivery points, and time of usage. Though this
methodology appears to be reasonable in the current context, it may not be adequate in light of
massive growth of the transmission network in coming years, emergence of wholesale and retail
competitive electricity markets, probable private sector participation and other reasons.
2. The proposal to modify the existing regulations shall help EVNNPT put forth important
modifications in the regulations regarding principles of computing revenue and charge along with
rationale. The underlying objectives of modifications are to reflect fair economic principles, current
market environment, prevailing principles of financial accounting and at the same time ensure
balancing of interests of various stakeholders (viz. EVNNPT, EVN, ERAV, Government). The
proposal shall be in line with the prudent global practices. Some of the areas of improvement are
described below:
a. Depreciation: Circular No. 203/2009 deals with treatment of depreciation on assets. As
per this regulation, full depreciation is allowable on a revalued asset considering useful life
between 8-12 years. This in essence allows over-recovery of depreciation as the commonly
accepted useful life of transmission lines is 30-40 years and substations is 25-35 years;
b. Return on Equity: Circular No. 14 & 3 allows Return on Equity, as part of the permitted
capital cost, to cover the cash (equity) costs of new investments. But it does not specify
specific % of RoE, leaving it completely at the discretion of the ERAV. For example, ERAV
has allowed only 1% pre-tax RoE in 2014;
c. Charge structure: Circular No. 14 & 3 deal with the structure of the transmission
charge. The proportion of the total revenue linked with capacity (α) and energy (β) is
regulated by ERAV each year, with α + β = 1. Currently, α is set at zero. It is obvious that
any transmission system is built to cater to the maximum demand and evacuate available
generation and thus should entail full recovery of revenue irrespective of actual energy
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 160
flow. In case of “energy-based charge”, there is no certainty to recover full approved
revenue, as the actual energy transmitted may vary from the projected energy;
d. Prudence check of opex and capex: For the true-up (adjustment) of expenses,
regulation does not specify controllable and uncontrollable expense items for the purpose
of allowing/disallowing expense in excess of approved expense. There is no clear
mechanism which enforces the prudency and efficiency in incurring capital and
operational expenses;
e. Treatment of forex loss: Forex loss is a real loss and must be allowed to be claimed in
respective year’s revenue. ERAV has been allowing recovery of only realised forex loss but
not the unrealised forex loss. Also, there is no clear mechanism/timelines for recovery of
accumulated forex loss; and
f. Penalty for failure service quality: The regulation does not specify penalty norms for
outage of line and transformers at different voltage level. In addition, penalty is levied
through deduction of equivalent amount from the EVNNPT’s Welfare Fund. This approach
seems to be penalizing all staff members who might not be in any way related to the
process of managing the service quality. Further, regulation does not have provision for
any specific incentive to employees involved in maintaining service quality.
3. The existing regulation mandates review of application by EVN before its submission to ERAV. It
seems EVN significantly modifies revenue/price proposed by EVNNPT before its submission to
ERAV. For example: In 2014, EVN curtailed EVNNPT’s proposed revenue by 22%, expenses by 18%
and allowed RoE of 1% in place of 4-6%. This mechanism compromises the interest of EVNNPT as
well as undermines the role of ERAV.
Description
1. The draft proposal shall be prepared in MS Word and shall include analysis of key provisions,
associated issues, review of select global practices, proposed modifications, rationale for the
modifications and its implications on EVNNPT.
Implementation steps
1. PwC will submit the draft proposal to EVNNPT for their comments and suggestions.
2. PwC will discuss the draft proposal with EVNNPT.
3. PwC will submit the revised draft proposal to EVNNPT after incorporating their comments and
suggestions.
Pre-requisites for implementation
1. NPT shall seek authorisation from management board of EVNNPT and EVN to submit such
proposal to ERAV.
2. NPT shall provide necessary data to PwC to analyse various components of revenue, expenses and
penalty.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 161
Potential barriers in implementation
1. EVN may not permit EVNNPT to submit this proposal to ERAV.
Recommendation#3: Develop and implement integrated transmission pricing model (TPM) for compilation of data and calculation of revenue & charge
Overview
Title Develop and implement integrated transmission pricing model (TPM) for compilation of data and calculation of revenue & charge
Dimension Technology
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft TPM: Four weeks from signing of MoU between ADB and EVNNPT
Discussion on draft TPM: One week from submission of draft TPM
Submission of final TPM: One week from discussion on draft TPM with EVNNPT
Conduct the training: One week from submission of final TPM
Rationale
1. The present spreadsheets used by EVNNPT for determining the transmission revenue and charge
are rudimentary and fragmented. It does not capture all the elements needed for determining the
transmission charge in sufficient detail. It also lacks provisions to incorporate some of the
components that have been specified in the transmission pricing computation methodology in
Circular No. 14/2010 and Circular No. 3/2012. For example: It does not capture truing-up
(adjustment) to take care of legitimate differences between approved revenue and expenses and
actual revenue and expenses of the last year.
2. The proposed transmission pricing model (TPM) covering computation of Total Power
Transmission Revenue (TPTR) and Transmission Charge (TC) shall help EVNNPT improve
compliance with the relevant circulars and decisions by providing for all components specified in
Circular No. 14 & 3.
3. The TPM shall streamline the process of data compilation and calculation of TPTR and TC and
provides an integrated view of inputs, calculations and outputs.
4. The TPM shall provide credible and key information to the management enabling them to take
prudent decisions on requirement of transmission revenue and charges. It will clearly demonstrate
the revenue gap (if any) that will emerge if recovery of prudent costs are not allowed.
5. Use of such model is prevalent in several transmission utilities globally such as POWERGRID
(India).
Description
1. The TPM will be developed using single MS Excel workbook as a platform. The design of the TPM
will be user-friendly, easy to operate, flexible and aesthetically appealing. We will follow PwC's
standard guidelines to create such a model.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 162
2. The TPM will have a set of input sheets, a set of calculation sheets and a set of output sheets - all of
which will have dynamic linkage to reflect the impact of any manual change across the model.
3. The TPM will also facilitate scenario analysis by adjusting specific input variables or expected
output parameters. For example to achieve a desired DSCR what is the revenue realisation that is
necessary. These key parameters will be agreed upon in consultation with EVNNPT.
4. The TPM will derive all its inputs from the data collection formats that all relevant departments in
EVNNPT shall use to capture and share relevant information.
Implementation steps
1. PwC will submit the draft TPM to EVNNPT for their comments and suggestions.
2. PwC will discuss the draft TPM with EVNNPT.
3. PwC will submit the final TPM to EVNNPT after incorporating their comments and suggestions.
4. PwC will conduct training for EVNNPT team on how to operate and maintain the TPM.
Pre-requisites for implementation
1. Users shall have basic understanding of MS Excel, technical and financial parameters used in
determining TPTR and TC.
2. After a pre-defined transition (overlapping) period, users shall not be permitted to use legacy
spreadsheets in parallel to new TPM.
3. The Circular No. 14 & 3 should ideally be revised so as to take care of specific issues related to
pricing principles and process.
Potential barriers in implementation
1. NPT may face resistance to adopt the new TPM in place of legacy spreadsheets.
2. Notification of any revisions in the existing circulars and decisions may require updating of the
TPM.
Recommendation#4: Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of information needed for transmission pricing
Overview
Title Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of information needed for transmission pricing
Dimension Process and Structure
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft TPP: Four weeks from signing of MoU between ADB and EVNNPT
Discussion on draft TPP: One week from submission of draft TPP
Submission of final TPP: One week from discussion on draft TPP with EVNNPT
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 163
Rationale
1. Circular No. 14 & 3 deal with the procedure for data collection, review and filing of the application
(petition) for review and approval of Total Power Transmission Revenue and Transmission Charge
by EVN and ERAV. The proposed transmission pricing procedure (TPP), with an underlying
objective of streamlining and standardising the entire process, shall help EVNNPT improve its
compliance to the relevant circulars and decisions.
2. The TPP shall streamline the process of preparation, collection, compilation and validation of
various information and data needed for transmission pricing. At present even though there are no
considerable delays on the part of any department in filing information, there is no standard
procedure and timeline being followed.
3. The TPP shall ensure timely, complete and credible information to be used in the TPM. At present
there are standalone MS Excel sheets that are being used by individual departments to capture
necessary data. This causes disparities in the way data is provided to CPD to be incorporated into
the transmission revenue and charge calculation spreadsheet being presently used.
4. Several transmission utilities across the globe (e.g. POWERGRID) use such standard procedures.
Description
1. The TPP will be developed using single MS Word file. The design of the TPP will be user-friendly,
easy to read & comprehend and aesthetically appealing. We will follow PwC's standard guidelines to
create such models.
2. The TPP will define the detailed process flow along with responsibilities (department level /
individual level) and time frame, taking into cognisance the cut-off dates as specified in the Circular
No. 14 & 3 and other relevant regulations. It will assign responsibilities for data preparation,
submission, collection, compilation and validation. It will also factor in time for prudence check of
such data by CPD and seeking revised/additional data (if needed) before finalisation of the petition.
3. The TPP will contain the standard formats for furnishing all the relevant data in MS Excel formats
in a single workbook. These formats will enable accurate and detailed data collection from all
relevant departments of EVNNPT. It will clearly mention the nature of data and the level of detailed
break up of such data required.
4. The formats will be designed in such a way to allow easy transitioning into maintaining regulatory
accounts in the future.
5. The TPP will also define the data reconciliation and dispute resolution procedure to take care of
issues such as mismatch in same parameter used by two different departments.
Implementation steps
1. PwC will submit the draft TPP to EVNNPT for their comments and suggestions.
2. PwC will discuss the draft TPP with EVNNPT.
3. PwC will submit the final TPP to EVNNPT after incorporating their comments and suggestions.
Transmission pricing
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 164
Pre-requisites for implementation
1. Users shall have basic understanding of MS Word and MS Excel.
2. The Circular No. 14 & 3 should ideally be revised so as to take care of specific issues related to
pricing principles and process.
Potential barriers in implementation
1. NPT may face resistance to adopt the new TPP.
2. Notification of any revisions in the existing circulars and decisions may require updating of the
TPP.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 165
Public relations
Recommendation#1: Plan, set-up and operationalise a dedicated PR department within EVNNPT and its subsidiaries
Overview
Title Plan, set-up and operationalize a dedicated PR department within EVNNPT and its subsidiaries
Dimension Strategy and Structure
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft proposal: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. The communication activities of EVNNPT are inadequate as compared to current needs. So far,
communication or PR has not been a focus or priority area for EVNNPT. Our Perceptions Audit
revealed that EVNNPT needs to communicate very much more with all its stakeholders, including
the ordinary public and those affected by its projects, than what it does now.
2. There is a clear need for PR or communication to be a critical function for EVNNPT in order to
achieve its business objectives. This can be accomplished by a separate department that is
adequately staffed as well as fully empowered and is led full-time by a senior executive who is part
of the leadership team.
3. The PR department should be the central point for strategy, planning and implementation of all
communication initiatives and external stakeholder engagement undertaken by EVNNPT through
its own departments and/or its subsidiaries. It will drive all PR/communication work, including
message development, in EVNNPT and its subsidiaries.
4. A separate PR department will work towards positioning EVNNPT as an independent entity
functionally separate from EVN. Currently, in communication matters, EVNNPT is under the
influence of EVN and many stakeholders are often unaware of EVNNPT’s role and responsibility.
EVN gets the credit for EVNNPT’s role and EVN’s negative attributes (“unresponsive” and
“monopolistic”) often get transferred to EVNNPT in the perception of the ordinary people. While
an independent PR department would function autonomously, it would still keep EVN informed
and updated and would not work at cross purposes with EVN’s PR department.
5. A separate PR department will help EVNNPT break free of the present mode of insufficient
communication and reach out directly, intensively and regularly to the media, the community and
other stakeholders.
6. A full-fledged PR department that actively fulfils all its responsibilities will ensure that, from a
communications perspective, EVNNPT does not keep its subsidiaries at an arm’s length and
distance itself from their work.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 166
7. Such a department will also ensure that EVNNPT drives communication relating to such vital areas
as land acquisition, resettlement and compensation as well as transmission corridor protection,
working in partnership with public officials (local authorities).
Description
1. Communication requirements are central to its functioning for an organisation like EVNNPT.
Therefore, the proposed PR department should be fully empowered. It should be led by a senior
executive who reports directly to the CEO. The CEO should take personal interest in the running of
the communications function. This will ensure primacy for the communications function.
2. The proposed PR department in EVNNPT should directly supervise and lead the work of the PR
departments to be set up in the subsidiaries.
3. This department should work towards creating a separate brand identity for EVNNPT.
4. The proposed communications department of EVNNPT should be adequately staffed and
sufficiently funded so that, in terms of both manpower and budget, the department can fulfil all its
responsibilities.
Implementation steps
1. The consultants will prepare and submit a draft proposal to EVNNPT outlining the need for a
dedicated PR department in EVNNPT and its subsidiaries. It will also outline the steps involved in
setting up such departments. The consultant will invite comments and suggestions from EVNNPT.
2. The consultants will submit the final proposal after modifying the draft proposal on the basis of
EVNNPT’s comments and suggestions.
3. The consultants will support EVNNPT in implementing activities needed to immediately kick start
the process of giving due importance to the PR function. These have been detailed later in this
document as separate recommendations and include the following:
a. An Effective Communications Workshop to optimise the job worthiness of the existing
staff handling communication;
b. A Message Development Workshop for the leadership team of EVNNPT; and
c. A Media Training Workshop for Spokespersons.
Pre-requisites for implementation
1. Full support from the top leadership of EVNNPT.
2. Full support from the EVN leadership.
Potential barriers in implementation
1. Possible reservations in sections of the top leadership team about the need for according primacy to
PR and providing the wherewithal to do so.
2. Reluctance on the part of EVN to let go of its total control over EVNNPT’s PR work.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 167
3. Absence of skilled staff and qualified personnel to implement the PR plans of EVNNPT.
4. Budgetary support is insufficient at this time. A full-fledged PR department will require a
significant financial commitment on both manpower and resources as well as on implementation of
PR activities.
Recommendation#2: Develop a Crisis Communications Manual
Overview
Title Develop a Crisis Communications Manual
Dimension Strategy and Process
Category Short-term (0-6 months)
Timelines (indicative)
Submission of draft approach note: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. Crisis communication strategy is an issue with EVNNPT. The probability of having a crisis is high
due to disputes relating to land acquisition. There is a strong likelihood of an incident or a minor
crisis turning into a major situation that threatens to get out of hand.
2. There can also be a crisis arising out of accidents and breakdowns caused by the breaching of the
safety corridor for transmission lines.
3. The potential consequences of a crisis include:
a. Loss of reputation;
b. Loss of stakeholder confidence or support;
c. Loss of public approval;
d. Loss of Government /political leadership approval;
e. Loss of employee commitment;
f. Project delay;
g. Financial loss; and
h. Lawsuits.
4. There is near unanimity among EVNNPT officials that land is a highly sensitive issue and projects
get routinely delayed due to disputes. Yet, not enough attention appears to be paid to crisis
preparedness from a communications perspective. This is possibly because land acquisition related
communication is not yet seen to be the direct responsibility of EVNNPT.
5. However, this situation will change once EVNNPT drives PR relating to land acquisition and, on the
whole, has a full-fledged and a highly proactive PR programme.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 168
6. Seamless communication of a high order is critical during a crisis. But smooth handling can come
only from preparedness. Thus, crisis preparedness will have to be central to EVNNPT’s PR
programme.
Description
1. There are two aspects to crisis communications - crisis preparedness and the actual handling of a
crisis situation. An organisation can successfully handle a crisis situation only if it is fully prepared
for such an exigency. Therefore, organisations such as EVNNPT that are particularly vulnerable to
crisis must have crisis preparedness as an integral part of their communications programme
because the danger of project delays due to a crisis, and along with that a loss of reputation, cannot
be overemphasised.
2. Crisis preparedness means having a crisis manual or a crisis plan in place. At a basic level, this
document lists who will do what in the event of a crisis. On a more complex plane, it anticipates
every potential situation and lists ways and means of ensuring that there are no surprises, no
fumbling and no false steps. It lists the steps to be taken in meeting a crisis situation head-on in
order to defuse it quickly with minimal loss of reputation and the least possible delay (and the
consequent financial loss).
Implementation steps
1. Consultants shall prepare and submit an introductory Approach Note on Crisis Preparedness to
EVNNPT for its comments and suggestions.
2. Consultants will finalise and submit the introductory Approach Note after incorporating the
feedback from EVNNPT.
Pre-requisites for implementation
1. NPT must fully acknowledge the role of communication in its functioning and in its efforts to attain
its business objectives. EVNNPT must set-up a separate PR department that shall drive the
communication efforts of the entire organisation, including its subsidiaries.
2. NPT must appreciate that effective PR is vital for anticipating and containing crisis situations.
Potential barriers in implementation
1. NPT’s reluctance to set-up a separate vertical for PR in itself and in its subsidiaries.
2. Delays caused due to any other reason in setting up a separate PR department.
3. NPT continuing to down play both crisis and crisis communications.
4. NPT continuing to not playing a leading and proactive role in communication relating to such
issues as land acquisition.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 169
Recommendation#3: Develop uniform key messages for EVNNPT through a workshop
Overview
Title Develop uniform key messages for EVNNPT through a workshop
Dimension Strategy
Category Short-term (0-6 months)
Timelines (indicative)
Preparation for the workshop: Three weeks from signing of MoU between ADB and EVNNPT
Conduct the workshop: One day
Rationale
1. It is imperative for every organisation, division, and brand or business initiative to have a set of two
to four all-encompassing key messages. These key messages must form the bedrock of the
spokespersons' statements. Regardless of whatever else they may say, they must deliver these
messages--either verbatim or by paraphrasing them.
2. Articulated repeatedly and consistently, these key messages will help audiences /stakeholders know
exactly what the organisation, division, brand, or business initiative stands for just the way the
spokespersons want them to—nothing more, nothing less.
3. The key messages must stand the test of time in the medium-term. But they are not permanent.
They must be re-viewed after a reasonable length of time for re-validation or revision.
4. Since, EVNNPT does not appear to have any key messages; it cannot carry out effective
communication without them. The key messages will provide a base or an underpinning to all other
PR statements or messages delivered by EVNNPT. They will reinforce EVNNPT’s PR, including the
delivery of all other messages.
5. It is, therefore, necessary for EVNNPT to forthwith develop a set of key messages for itself.
Description
1. The key messages will not be foisted by the consultants on EVNNPT. Instead, the development of a
set of key messages will be facilitated by us through a Message Development Workshop.
2. The participants in the proposed workshop will be the entire leadership team of EVNNPT.
3. In the workshop, the participants shall engage in a brainstorming session moderated by a senior
consultant. This brainstorming session shall be neither open-ended nor freewheeling. There shall
be a structure to it and the moderator shall ensure that the discussion remains within the ambit of
that structure. The participants shall indulge in honest soul-searching as they examine facts and
perceptions, both positive and negative, about their organisation. At the end of the session, they
shall distil the all-important two or three key messages.
Implementation steps
1. The consultants shall submit the proposal for the Message Development Workshop to EVNNPT
and request the participation of the entire leadership team on the designated day.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 170
2. NPT shall confirm the date, time and venue of the workshop as well as the participation of the
entire leadership team.
3. The consultants shall do preparatory work in terms of preparing the workshop document and
workbook.
4. The workshop shall be held on the designated day. It shall be conducted by a senior consultant.
5. The consultants shall finalise the workshop document and circulate it among the participants.
Pre-requisites for implementation
1. Participation by the entire leadership team of EVNNPT by committing time for the workshop.
Potential barriers in implementation
1. The belief that EVNNPT does not need to have a separate identity and key messages of its own.
2. Delegation of the task of developing messages, through participation in the message development
session, to officials other than the leadership.
Recommendation#4: Leverage the social media for EVNNPT’s PR work
Overview
Title Leverage the social media for EVNNPT’s PR work
Dimension Technology
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft approach note: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. According to one estimate, Internet penetration in Vietnam is 34%, which is more than the global
average. Internet access is available in every commune in the rural areas of the country.
2. It has been reported that over 8.5 million Vietnamese people use social networking.
3. It has been seen that platforms like Facebook are very popular in the country.
4. However, EVNNPT is not active in the social media arena.
5. While social media may not be the best option for reaching out to target audiences in rural areas
(direct communication with opinion leaders may be the best way to reach out to audiences in
matters of land acquisition), it is certainly a credible and effective way to spread the message.
6. Social media is also an effective means of receiving feedback from target audiences.
7. It is important to leverage social media platforms to reach out to various stakeholders and engage
with them on a continuous basis.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 171
Description
1. NPT is active on online media but does not actively engage in social media platforms like Facebook,
Twitter and online blogs.
2. Information, pictures and videos about various proactive initiatives of EVNNPT can be posted on
these platforms and these stories can reach a greater mass of people in real time.
3. NPT does not have a credible two way communication process yet. Social media is an effective way
to have two-way communications with various stakeholders. EVNNPT can connect with members
of various stakeholder groups and receive communication from them.
4. Other tools like online blogs can also be designed to purvey information and receive comments
from stakeholders.
5. Social media can be the best platform to reach out to the informed public who spend a lot of their
time on it.
Implementation steps
1. Consultants shall prepare and submit an introductory Approach Note on Leveraging Social Media
to EVNNPT for its comments and suggestions.
2. Consultants will finalise and submit the introductory Approach Note after incorporating the
feedback from EVNNPT.
Pre-requisites for implementation
1. Preparation and implementation of an Approach Note on leveraging social media pre-supposes an
acknowledgement by EVNNPT’s leadership that social media will be an effective tool for the
organisation to use.
Potential barriers in implementation
1. Social media and networking is a 24/7 pursuit and needs constant monitoring of the Internet and
continuous engagement and interaction.
2. In the absence of a dedicated staff, both monitoring and real-time or near real-time engagement
may be hindered.
3. Constant content creation is challenging job and EVNNPT will need to keep a long list of content in
the pipeline.
4. NPT must also be prepared to receive criticism, and sometimes unpleasantly worded criticism,
through social media. Such criticism will have to be dealt with in a mature and sensitive manner.
Recommendation#5: Plan, set-up and operationalise a dedicated CSR department within EVNNPT
Overview
Title Plan, set-up and operationalise a dedicated CSR department within EVNNPT
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 172
Dimension Strategy and Structure
Category Medium-term (6-18 months)
Timelines (indicative)
Submission of draft proposal: Four weeks from signing of MoU between ADB and EVNNPT
Rationale
1. NPT focuses on a lot of corporate social responsibility (CSR) initiatives, but the impact is
inadequate to alter perceptions about EVNNPT in the public domain.
2. Organised and focused CSR activities will contribute significantly in EVNNPT’s effort to gain
goodwill of not only those who are directly affected by its projects, but also those who might be
affected by them at a future date.
3. Our Perceptions Audit revealed that most stakeholders feel that the quantum of CSR activity that
EVNNPT undertakes is unsatisfactory. Additionally, a significant chunk of the respondents were
not aware of the CSR activities undertaken by EVNNPT.
4. Currently there is no department in EVNNPT that is in-charge of CSR Activities related to CSR are
carried out by different departments and different unions.
5. Overall, the CSR effort appears to be somewhat disjointed and in need of focus.
Description
1. CSR activities should be dealt with strategically, with innovation, focus and the utmost priority.
2. A separate CSR function in EVNNPT will help bring focus and give direction to CSR activities,
especially with regard to engagement with the communities at the project sites.
3. It will also ensure that such initiatives get optimum publicity mileage for EVNNPT.
4. The overall purpose of CSR activities will be to help improve, in a sustainable manner, the quality
of life of the communities affected by EVNNPT projects, both at the construction stage and at
operation & maintenance stage.
5. The overall objective will be to win trust and gain goodwill for EVNNPT.
Implementation steps
1. Consultants shall prepare and submit a draft introductory Approach Note on CSR to EVNNPT for
its comments and suggestions.
2. Consultants will finalise and submit the introductory Approach Note after incorporating the
feedback from EVNNPT.
Pre-requisites for implementation
1. The preparation and implementation of the proposal on CSR presupposes an agreement on the part
of EVNNPT that organised CSR activities are worth pursuing.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 173
2. It also presupposes that EVNNPT will make available the wherewithal (staff and budgetary
resources) to carry out meaningful CSR activities.
Potential barriers in implementation
1. CSR as a concept is relatively unknown in the country. It is not widely or sufficiently understood.
CSR is often confused with charity or giving jobs to the jobless. Sometimes, tariff cross-subsidy or
giving breaks to those affected by natural calamities are confused with CSR.
2. This insufficient understanding may pose to be a challenge.
Recommendation#6: Impart training to EVNNPT spokespersons on media handling skills
Overview
Title Impart training to EVNNPT spokespersons on media handling skills
Dimension People
Category Short-term (0-6 months)
Timelines (indicative)
Preparation for the workshop: Two weeks from signing of MoU between ADB and EVNNPT
Conduct the workshop: One day
Rationale
1. Once EVNNPT sets up a separate PR department and it begins to implement a planned
communications programme, it will be important for it to speak to the media in an organised
manner on a regular basis.
2. Equally, EVNNPT will have to respond to media queries and other overtures from the media.
3. In either case, EVNNPT spokespersons will have to give interviews to the media or make press
statements.
4. It is important for EVNNPT spokespersons to understand how the media functions, how it is
structured and how news is reported in the media. This will help them understand how the mind of
a media-person works.
5. It is equally important for them to know how to handle questions from the media in order to
control the flow of information in a manner that furthers the communications objectives of the
EVNNPT.
Description
1. It is difficult to have a commanding position in a media interaction if the media and the journalist
are mysterious and forbidding entities.
2. When they cease to be a mystery, the spokesperson is better placed to handle the interaction in
such a manner that he is able to tell the media only what he wants to tell.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 174
3. It also helps him to know the difference between print and electronic and Net-based media and the
different ways of handling them.
4. Finally, it is critical for the spokesperson to know the dos and don’ts of handling the media.
Implementation steps
1. The consultants shall submit the proposal for the workshop on “Media Handling Skills” to EVNNPT
and request the participation of designated spokespersons and potential spokespersons on the
agreed day.
2. NPT shall confirm the date, time and venue of the workshop as well as the participation of an
agreed minimum number of senior executives.
3. The consultants shall do preparatory work in terms of preparing the workshop presentation and
hand-outs as well as arranging for a camera crew and other technical support.
4. The workshop shall be held on the designated day.
Pre-requisites for implementation
1. The workshop can be held only if EVNNPT accepts the consultants’ recommendation about setting
up a separate PR department and to adopt a highly proactive PR programme.
2. The workshop can be held only if EVNNPT feels that its spokespersons and potential spokespersons
will gain from undergoing training in media handling skills.
Potential barriers in implementation
1. NPT does not accept the consultants’ recommendation about setting up a PR department and
adopting an aggressive media strategy.
2. NPT feels that there is nothing significant to be gained by its spokespersons and potential
spokespersons from a media training workshop.
Recommendation#7: Conduct a workshop on the fundamentals of effective public relations
Overview
Title Conduct a workshop on the fundamentals of effective public relations
Dimension People
Category Short-term (0-6 months)
Timelines (indicative)
Preparation for the workshop: Two weeks from signing of MoU between ADB and EVNNPT
Conduct the workshop: One day
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 175
Rationale
1. Once EVNNPT accepts the consultants’ recommendation on adopting an organised and highly
proactive PR programme, it will need human resources that have basic familiarity with effective
communication and what it can achieve.
2. The functional as well as supervisory staff who will man the newly set-up PR department will gain
immensely from knowing the fundamentals of effective communication. This is with regard to
those who do not have any formal training or even experience of PR.
3. A PR primer or an introduction to communication will add immense value to those who will be
expected to take up PR work immediately.
Description
1. It would help those who are beginners in professional PR to be exposed to definitions of common
PR terms and activities; the tools of PR; the fundamentals of media relations; and the basics of PR
writing.
2. They would also gain from being told about communication management, media monitoring, the
value of PR plans and the way to make one.
3. It would also help them to know the difference between print and electronic and Net-based media
and the different ways of handling them.
4. Finally, it is important for them to learn about non-media PR activities.
Implementation steps
1. The consultants shall submit the proposal for the workshop on the “Fundamentals of effective PR”
to EVNNPT and request the participation of communication executives or those likely to be
deputed to work in the proposed new PR department.
2. NPT shall confirm the date, time and venue of the workshop as well as the participation of an
agreed minimum number of executives.
3. The consultants shall do preparatory work in terms of preparing the workshop presentation and
hand-outs.
4. The workshop shall be held on the designated day.
Pre-requisites for implementation
1. The workshop can be held only if EVNNPT accepts the consultants’ recommendation about setting
up a separate PR department and to adopt a highly proactive PR programme.
2. The workshop can be held only if EVNNPT feels that its personnel will gain from senior and veteran
professionals taking them through the rudiments of effective PR.
Potential barriers in implementation
1. NPT does not accept the consultants’ recommendation about setting up a PR department and
adopting a proactive PR strategy.
Public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 176
2. NPT feels that there is nothing significant to be gained by its personnel attending such a workshop.
Part-C: Approach Notes / Proposals / Training Materials (in accordance with the Recommendation Report)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 177
Part-C: Approach Notes / Proposals / Training Materials (in accordance with the Recommendation Report)
Part-C (i): Investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 178
Part-C (i): Investment planning
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 179
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Overview
NPT is currently owned by EVN and ultimately by Government of Vietnam. The Government being the majority
of shareholder as well as stakeholder in the power sector which has large scale implications on public should
maintain a certain degree of control on investment decisions of the Company. However, in the fast paced
business environment, decentralisation is the key to having effective management and responding better to the
changing business requirements. Hence, it is imperative to strike a balance between the keeping effective
control over the management of the company as well as delegating powers lower down the order to effective
performance.
Decision No. 1368/QD-EVNNPT, 2013 governs the delegation of powers for undertaking investment decision in
EVNNPT. The existing framework is about more centralisation in decision making to President & CEO or
Management Board of EVNNPT. This decision is in fact an amendment of the original Decision No. 496/QD-
NPT dated 16 June 2010. A brief reading of the changes suggests that the new decision has brought about more
centralisation in decision making to the President & CEO or Management Board.
This decision is important not only from a process efficiency perspective but also from a governance
perspective. The authority for investment decision and implementation in EVNNPT is based on the value of the
investment proposed. The investment is categorised into three broad categories (based on its value) which
includes:
1. Investment value less than 500 billion VND;
2. Investment value from 500 billion VND (in some cases it is 800 billion) to 1000 billion VND;
3. Investment value from 1000 billion VND to 50% of the total asset value.
Key issues with existing delegation of powers
The existing framework is about more centralisation in decision making to the President & CEO or
Management Board of EVNNPT. There is a requirement of decentralization of powers in respect of investment
planning due to the following reasons:
1. The majority of the powers from selection of consultants, approval to feasibility report, detailed
technical design and subsequent modifications; for investment value below 800 billion VND lies with
the President & CEO of EVNNPT. The Investments with ticket sizes above 800 billion VND require
approval from Management Board of EVNNPT;
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 180
2. The PMBs operating in different regions have different investment and quality needs and it becomes
difficult under a centralised model to expedite the decision making process;
3. There are some investment requirements which require immediate execution. Such projects under
regular channels lead to delay and may lead to significant opportunity loss. There is practically no
financial/ administrative powers provided to PTCs/ PMBs/ vice presidents of EVNNPT; and
4. The PTCs and PMBs are responsible for identification of investment needs and execution of capital
projects. In absence of such delegation of powers, projects of smaller ticket size and critical nature may
be delayed. Such a centralized delegation of powers also lead to higher transaction costs in case of
smaller projects which may not be beneficial for the company.
The concept note is focussed on reviewing delegation of power in similar developing countries and proposes a
framework based on which the existing circular may be amended to achieve higher levels of efficiency and
centralisation in authority.
The proposed framework suggested in the concept note will be associated with the following benefits:
1. Efficient manner of empowering PMBs and PTCs without losing control of top management, will allow
the core departments under EVNNPT along with the President & CEO and Management Board of
EVNNPT to focus on investments of higher value and strategic nature; and
2. Ensuring a greater accountability of the PTCs/ PMBs along with adequate powers to undertake
financial and administrative decisions quickly based on the ground realities;
Select global practices
India
POWERGRID is one the leading power transmission companies in the world. The company operates over one
hundred thousand circuit kilometres of transmission lines and has impeccable performance record achieving an
availability of 99.9% consistently. POWERGRID features in the top 25o power utilities in the world and is
ranked among the top five in terms of growth.
As a top performing and profit making company, POWERGRID is bestowed with special status of “Navratna
Company” and is eligible for enhanced delegation of powers including:
1. Board of Directors (BoD) have full powers to make capital expenditure without any approval from the
Government;
2. BoD has authority to enter into mergers and acquisitions/ disposals; and
3. BoD has the full power to enter into joint ventures amounting to 15% of the net worth of the company
(ceiling limit of VND 3.47 trillion in a single project).
POWERGRID follows a simple delegation of authority. The delegation of authority is summarized in the table
below:
Powers Position (Approving authority - Approval of indent of items to be purchased)
Up to VND 0.347 billion Manager
Up to VND 1.735 billion Chief Manager
Up to VND 3.47 billion Deputy General Manager
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 181
Powers Position (Approving authority - Approval of indent of items to be purchased)
Up to VND 10.410 billion General Manager (head of work-stream within a single department)
Up to VND 52 billion Executive Directors
Up to VND 69.40 billion (Works contract) / Up to VND 1.735 billion (Consulting contract)
Chairman and Managing Director (CMD)
VND 69.40 billion to 260 billion (Works contract)
The same powers is also delegated two Committee of Directors (i) Committee for Works contract and (ii) Committee for Consulting contracts
Over VND 260 billion Board of Directors
South Africa
Eskom is the Government owned vertically integrated utility of South Africa. The company controls majority of
the power assets in the country. Eskom with its significant asset base is stated as one of the well performing
vertically integrated utility companies in the world.
The company is divided into generation, transmission and distribution divisions and each division has
autonomous functions. Eskom Delegation of Authority (DOA) forms a part of the procurement framework and
is reviewed and published from time to time. The DOA and its subsequent amendments are approved by Board
of Directors of Eskom.
In this DOP, the Eskom Board of Directors has assigned the powers for procurement/ disposal of goods and
services to chief executive, finance director, group executives and divisional executives, and further delegated to
other appointed general and senior managers, procurement managers and / or to tender committees. It covers
the power in respect of approval of the purchase, disposal and/or leasing of assets, goods and services for and
on behalf of Eskom.
The powers delegated to various authorities are given below:
Procurement Managers
Eskom divisions and regions (based on geography) have designated procurement managers (PM). The PMs are
trained in the powers/ responsibilities and process of procurement. The PMs are responsible for judiciously
expedite any procurement which comes up from the end users through a SAP based system. The PM is also
responsible to monitor the turnaround time, consolidation of requests to achieve better economies,
optimization in savings, liaising with the end users and quality assurance. The procurement approval powers of
PMs are summarized in the table below:
Contractual value Process of approval
Contract value < = R 1 million (VND 1.925 billion)
1. The buyer/ user of the product recommends the proposed purchase
2. The PM seconds / approves the purchase
Senior Managers
A Senior Manager is a position designated three positions below the Chief Executive of Eskom (Chief Executive
Eskom manages all the transmission related activities). General Managers followed by Senior Managers report
to Divisional Executive Transmission, who reports to Chief Executive). A procurement approval, approved by
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 182
PM but exceeding the value of R 1 million (VND 1.925 billion) but lower than R 5 million (VND 9.625 billion)
can be approved by a Senior Manager and above. The powers are summarized below:
Contractual value Process of approval
Contract value > R 1 million (VND 1.925 billion) and Contract value <= R 5 million (VND 9.625 billion)
1. The buyer/ user of the product recommends the proposed purchase
2. The PM seconds / approves the purchase
3. Senior Manager approves the purchase
Tender Committee
All the procurement exceeding the delegations applicable to Senior Manager is delegated by the Chief
Commercial Officer or the Group Commercial Executive Committee to the tender committee. The Chief
Commercial Officer, by the powers vested by Board of Directors, can set out the financial limit for the tender
committee and the Chairman of tender committee.
Contractual value Process of approval
Contract value > R 5 million (VND 9.625 billion) and Contract value <= Limit set out by Chief Commercial Officer
1. The buyer/ user of the product recommends the proposed purchase
2. The PM seconds / approves the purchase
3. Tender committee approval for the project
Executive Committee (EXCO)
All tenders which exceed in value/ term with the limits defined by Chief Commercial Officer for tender
committee comes to Executive Committee. EXCO is the body to which the Chief Executive has delegated
procurement authority and EXCO may also in turn delegate part of its powers to EXCO Procurement Sub-
committee (EXCOPS) to approve procurement/ disposal of goods and services which exceed the expenditure
limits of Procurement/ Tender Committee delegations. Generally strategic and high value investment approvals
comes the EXCO committee. The EXCO comprises of Group Executive (Commercial and Technology). The
delegation of power is as below:
Contractual value Process of approval
Contract value > Limit set out by Chief Commercial Officer
1. The buyer/ user of the product recommends the proposed purchase
2. The PM seconds / approves the purchase
3. EXCO committee approval for the project
Suggested solution
Decentralization of powers
Our review into the leading practices with select power transmission companies, indicate that financial and
administrative powers are delegated to individual employee level. This system is aimed at not only improving
the efficiency of decision making but also increase accountability.
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 183
Setting up financial limits
As a first step towards effective decentralization of powers, is to conduct a historical study to set financial
powers at individual levels. The process of setting the financial limits would have to done through focused
group discussions including representatives from PTC, PMB, Board of Directors and representatives from EVN
and MOIT.
The financial limits should further be ratified by Board of Directors of EVNNPT. The financial limits and
ceilings should be subject to periodic review by a Board appointed committee. The results of the review should
be represented to the Board of Directors (NPT) for consideration and ceiling limits may be altered depending of
the decision of the Board of Directors.
Guiding principle
The guiding principle for decentralization of authority should be “need and efficiency based.” As the PTCs/
PMBs clearly have better local knowledge of the investment requirements of the system, hence the lowest level
of decentralization may be PTC and PMB. This implies that within specified limits, PTC/ PMB should be able to
have complete control over the investment which implies origination, packaging, tending, and selection of
suppliers/contractors/service providers, quality monitoring and payments.
Broadly the delegation of power may be rationalized as below:
Contract value Authority of power
Projects valued less than VND 200 billion and project is critical and immediate in nature
PMB and PTC/ Vice President equivalent [Complete autonomy to PMB/ PTC management to approve, raise funds, select consultant / contractors and manage quality]
Projects valued between VND 200 billion to VND 500 billion
Regional tender committees [should comprise of representatives from PMB, PTC, EVNNPT Corporate and other representatives. Chairman of the Committee should be Vice President (Operations & Investment), EVNNPT.
Projects valued between VND 500 billion to VND 1000 billion
President & CEO should have power to approve investment valued between VND 500 billion to VND 1 trillion. However, before the project comes to President & CEO, it should be approved by the Regional tender committee.
Projects valued between VND 1000 billion to VND 2000 billion
NPT Tender Committee [The Board of Directors should appoint a EVNNPT Tender Committee as an authorized representative of the BOD in terms of complete financial powers. The Committee should include members of the BOD of EVNNPT, executive members such as Vice President (Operations & Investment) and President & CEO (NPT).
Projects above VND 2000 billion Board of Directors or management board
Maintaining controls
The revised delegation of power will bestow greater financial powers with the employees of EVNNPT and its
divisions. The increase in decentralisation will also likely to give rise to the number of commercial transactions
during the year and hence it becomes imperative to also monitor and manage the risk pertaining to delegation
of powers.
Formation of Risk Management Committee
The management board of EVNNPT may look to form a Risk Management Committee (RMC). The RMC may
comprise of executive members such as Vice President (Finance and Economics) and Vice President
(Construction) along with select members of the Board.
Recommendation#1: Decentralisation in decision making and approval process pertaining to investment planning and revised delegation of powers
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 184
The Risk Management Committee may conduct annual risk review of the contracts executed during the year by
all levels under the revised delegation of powers policy.
The findings of the RMC should be reported to the Board of Directors and MOIT for review.
Formation of DOP Review Committee
The management board of EVNNPT may form a DOP Review Committee which should conduct an annual
review of the changing business requirements and the ceiling limits in the existing Delegation of Power. The
DOP Review Committee should henceforth submit its review report and recommendations to the Board of
Directors of EVNNPT for further perusal and the BOD may revise the ceiling limit for investments based on the
recommendations of the committee.
Conclusion
1. Providing autonomy to the employees and empowering them with greater responsibility and powers is
seen to bear significant fruit. Leading companies around the world follow a decentralized model for
investment approval.
2. The exact limit / ceiling for investment approval should depend on the existing business environment,
historical trend of contract sizes and future requirements. The setting up of financial limits should be
done through a consultative process and the views of the individual stakeholders should be considered.
3. Training and business intelligence: It is imperative in the changing business environment to train the
employees from PTC/ PMB and above to make then procurement specialist. The procurement specialist
will bring in the technical and market knowledge and insights into packaging, contracting, tendering
and negotiations. The procurement specialist may be selected from the existing manpower available
with the company but they should be provided with effective training.
4. Delegation of powers should not be used to simply break down larger contracts into smaller
components or for undue advantage/ favours. This is where the role of Risk Management Committee
becomes crucial to review the use of the DOP during the year and whether the use has been within the
intended framework and objectives.
5. NPT should respond quickly to the needs of the business and tend to survive well. Maintaining a
balance between decentralization of authority and effective controls over the process is paramount to
ensuring smooth functioning. In the current business context, there should be focus to reduce the
construction period by using technological developments and modern project management techniques.
In certain Latin American countries, transmission lines of hundreds of kilometres are being constructed
in less than a year’s time. In such a scenario, it is unreasonable to have project identification to
approval period of more than one year, and in fact effort should be concentrated to reduce the time
further.
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 185
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Overview
NPT operates under a regulated regime, which implies that the transmission pricing is set by an independent
electricity regulator (ERAV) based on certain upfront prescribed norms.
In Vietnam, the transmission pricing norms are issued by MOIT and MOF vide circular number 14/2010/TT-
BCT dated 15 April 2010 (amended by Circular No. 3/2012/TT-BCT dated 19 January 2012). This circular
clearly outlines the procedure and timelines to be followed for submission, calculation, review and approval of
transmission pricing. The circular also provides for the method of determination of transmission pricing, as
mentioned below:
Annual transmission revenue for the year = permitted capital cost + permitted O&M expenses +
revenue deficit / (Surplus) in the previous year
The most significant component of the transmission revenue is permitted capital cost which is summation of
depreciation costs + interest on long term loans + eligible transmission profit.
The depreciation cost, which is essentially a non-cash item, in above formula of permitted capital costs, is
meant as a surrogate for principal repayment of the debt employed. This mechanism of using allowable
depreciation cost for principal repayment is practiced in a majority of developing and developed countries such
as India, Germany, Italy and Nigeria.
The Dilemma
In other countries, where depreciation cost forms a part of transmission pricing, the depreciation rates used for
the purpose of determination of transmission charges are calculated on the basis of the economic useful life of
the assets. However, In Vietnam, EVNNPT is allowed depreciation on the assets at accelerated rates. The useful
life of the fixed assets for the purpose of the determination of depreciation is pegged at 8-12 years in Vietnam
which is significantly low compared to the economic useful life of transmission assets which is 25-35 years.
The use of proceeds from depreciation should be used for the repayment of the loan in line with global practice.
However, contrary to the depreciation period of 10 years, the tenure of repayment of majority of term loans is
between 20 to 25 years. Hence, there is a mismatch between the recovery of revenue in form of depreciation
and the actual repayment of loan. This leads to generation of surplus fund in the initial 8-12 years period due to
accelerated depreciation. This surplus depreciation fund is invested into the capital investment projects since
there is a lack of equity funding. The reasons for lack of equity funding are given below:
1. No fresh equity infusion from shareholders: There have been no fresh equity infusion from the EVN
(shareholder) or government (the ultimate shareholder) of EVNNPT to invest in capital expenditure
projects.
2. Lack of adequate Return on Equity invested: No RoE is being allowed to EVNNPT on the equity
employed. Although EVNNPT is claiming a return on equity at the rate of 4%-6% rate of return, which
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 186
is not being allowed to EVNNPT. However, the return claimed by EVNNPT is significantly lower
compared to the required rate of return on equity. Ideally, the return on equity should be higher than
return on debt.
In the absence of fresh infusion of equity and negligible return on equity, EVNNPT is left with only one option
which is utilising the surplus depreciation funds to meet the equity infusion obligations. This may lead to fund
deficit situation for EVNNPT.
NPT had already faced a fund deficit scenario in the past. In FY 11, such a situation occurred because the
repayment tenure of bonds was 5 years, against the recovery period of 10 years through the depreciation. Due to
the mismatch in depreciation period and tenure of loan, the EVNNPT faced a fund deficit situation in FY11.
EVN (the holding company of EVNNPT) had to support EVNNPT to meet the fund deficit incurred due the
significant repayment of bonds (1,250 billion VND) in a year. The mismatch in depreciation period and tenure
of loan may lead to significant financial risk (fund deficit scenario) in future for EVNNPT as discussed in the
next section.
The future risk
If a single capital project is being analysed, it can be observed that the entire cost will be recovered in first 8-12
years, whereas the loan (raised for constructing the capital project) will be required to be paid till 2oth or 25th
year. As mentioned above, the surplus depreciation funds recovered during first 8-12 years are being invested in
long term capital projects in the same year. Therefore, there will be no recovery against the repayment of loan
during the period starting from 13th year to 20th or 25th (as the case may be) of the project lifecycle. EVNNPT
has to rely on the depreciation allowed on other capital projects which are still operating under first 8-12 years
of their lifecycle. In case the future capital investment requirement goes down after 10-15 years, which seems to
be a logical assumption, the depreciation allowed on other capital projects will also goes down. In such a
situation, there will be cash deficit situation for repay the long term loan obligations. This is not a healthy
practice to be adopted. EVNNPT may land up a debt trap scenario, where the company would have to borrow in
order to fund its debt repayment.
In order to illustrate the gravity of the risk, we have conducted a short cash flow assessment for EVNNPT using
a suitable example.
For the purpose of above-mentioned cash flow assessment, we have considered certain assumptions as
mentioned below:
1. The balance of fixed assets as on 31st Dec 2012 is VND 47 trillion (as per the audited accounts of
EVNNPT - December 2012);
2. The assets are depreciable over a period of 10 years (average of 8-12 years considered by ERAV for the
purpose of determination of transmission charges);
3. The Debt to Equity ratio for the project is 90:10 (close to the existing gearing ratio);
4. The Debt borrowed is to be repaid in 20 equal instalments;
5. The capital investment expenditure for 2013, 2014 and 2015 has been taken from the tariff petition
prepared by EVNNPT. Post 2015, it has been considered on the basis of discussion with various
departments of EVNNPT (till 2020) and on the basis of an assumption that after 10-12 years, the
capital investment requirement might go down. The rationale behind a reducing trajectory of
investments is that as the infrastructure in Vietnam grows, a certain level of saturation will be reached
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 187
post which new investments would be lower. The capital investment over the next 30 years is
summarized in the graph below:
The cash flow graph below clearly indicates that in case the existing scenario persists, i.e. the surplus
depreciation fund being funnelled towards meeting equity commitments with minimal ROE, EVNNPT will not
be able to meet its future cash requirements.
Sound financial principles state that funds from depreciation fund should be utilised to meet the debt
repayment obligation. Equity as a source of fund should be either from available free reserves/ fresh equity
infusion.
In this concept note, there is a comparison of the depreciation rates (or useful life of assets) considered for the
determination of tariff and allowed return on equity across various countries. The concept note also provides
for suitable alternatives keeping in mind the impact on final consumer tariff.
-
2
4
6
8
10
12
14
16
18
20
Capital Investment (in VND Trillion)
-
5
10
15
20
Depreciation vs repayment of loans (VND trillion)
Total Repayment Total Depreciation
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 188
Select global practices
Depreciation
Depreciation represents “Return of Capital” which implies that capital invested in assets are returned back to
the investors over the useful life of the assets while return on equity and interest expenses represent “Return on
Capital”. It is an accepted understanding that the depreciation represents service to capital subscribed and is
considered as available cash flow for repayment of loan (i.e. principal component).
Accelerated depreciation
According to the discussion paper on depreciation norms issued by CERC (Central Electricity Regulatory
Commission, India), nearly 97 percent of the utilities around the world apply a straight-line recovery method
for the purpose of tariff determination, and only a small percentage of them use the accelerated depreciation
methodology.
Upon careful review of the depreciation norms used for the purpose of accounting, tariff determination and
taxation policies, it has been observed that accelerated depreciation around the world is typically adopted for
the purpose of taxation (where the Government intends to attract investors) and hence for tax saving purposes
and not for tariff or accounting purpose. Typically, accelerated depreciation has been used to promote eco-
friendly technologies such as wind, solar, geothermal projects. In USA, the qualified solar energy property
follows the Modified Accelerated Cost Recovery System [MACRS] - 5-year depreciation schedule using a 200
percent declining balance method. Similarly in Netherlands the wind energy projects are allowed accelerated
depreciation. In India accelerated depreciation is used for tax computation only for wind and solar power
projects.
Depreciation for the purpose of tariff determination
In a majority of countries across the globe, normal straight line depreciation rates are used for the purposes of
tariff determination. A comparison of the average depreciation rates for transmission assets for a few countries
is given below:
Country Depreciation rates
POWERGRID, India Transmission lines and towers (35 years life): 5.28% (for first 12 years) and 1.16% (for next 23 years). Substation (25 years life): 5.28% (for first 12 years) and 2.05% (for next 13 years) The residual value is pegged at 10%
National Grid, United Kingdom
The regulator, Ofgem has launched a new price control regulation called as RIIO (Revenue = Incentives+ Innovation+ Outputs). Depreciation rates for assets existing pre RIIO is 5% and depreciation rates for new assets is 2.22%
Australia Transmission substations (40 years): 2.50% of the asset value and Transmission lines (45 years): 2.22% of the asset life
Transmission Company of Nigeria (TCN), Nigeria
Plant and machinery (35 years): 2.8%, Land and buildings (50 years): 2.00%, Furniture and fittings (15 years): 6.67%, Motor vehicles (5 years): 20%
South Africa (NERSA) Depreciation rates is linked to actual service life of the assets based on the historical depreciation charged by the company
The above table indicates that across the globe the life of transmission assets is more than 25-35 years and in
some cases (in developed countries) as high as 50 years. The use of normal depreciation rates for the purpose of
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 189
tariff computation represents the true useful / service life of the assets over which the assets are put to use and
thereby generate revenues.
It can be concluded that the depreciation rates or useful life of assets considered in Vietnam are considerably
higher compared to other countries.
Return on equity
Under a cost plus regime, where the prices are regulated by external independent electricity regulator, the tariff
/ price setting principles allows the power sector companies a reasonable return on the equity invested. This
reasonable return on equity invested depends on a number of factors such as inflation in the country, currency
fluctuations, risk of the industry in that country and return expectations of the investors in similar business.
The return on equity truly represents the profit the company is able to generate during a year and this profit can
then be ploughed back in form of equity for further investments.
In Vietnam, as per the existing circular on transmission, the regulation allows for recovery of reasonable return
on equity as part of the permitted capital cost. However the return on equity is not mandatorily allowed as part
of transmission charge by the ERAV. Additionally, the regulation also does not specify the quantum of return on
equity which will be allowed in subsequent years. In absence of specific guideline on the quantum of return on
equity (ROE) to be allowed, EVNNPT is not allowed to recover an adequate amount of ROE in a particular year.
This impacts the Company’s ability to plan self-financing for its upcoming investments.
Country Allowed ROE Typical cost of debt
Vietnam 1% 11%
India 15.50% (after tax) 11%-13.5%
Germany 9.29% 3.54%
Canada 8.76% 5.32%
Montenegro 10.90% 6.81%
US 10.57% 3%
Nigeria 25.00% 17%
Croatia 4.91% 4.01%
Kosovo 6.10%
Macedonia 8.53% 2.33%
Turkey 9.93% (WACC) Source: Bloomberg, CERC and ECRB Report (2013) and Comparable companies (India)
The most notable conclusion that one can draw from the above table is that the cost of equity in all the countries
(except Vietnam) is higher compared to the cost of debt. The degree of premium may vary but equity in all cases
carries a higher premium compared to debt.
In case of EVNNPT, the allowance of reasonable return on the equity will benefit the company immensely.
Some of the key benefits are summarized below:
1. Cash generated from the ROE may serve as a long term source of fund for meeting the equity
commitments of the Company; and
2. Reasonable ROE will also help EVNNPT to improve its gearing ratio. Currently the Company borrows
over 90% of the asset value which is good for the company but in future, over leveraged companies find
hard to raise capital especially at times of global economic turmoil.
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 190
Possible solutions
There can be two possible solutions:
1. Continue with existing arrangement and allowance of depreciation on revaluation of assets; and
2. Allowance of reasonable Return on Equity (ROE) with normal depreciation.
Continue with existing arrangement and allowance of depreciation on revaluation of assets
Accordingly to the VAS, EVNNPT has the flexibility to revalue their fixed assets. EVNNPT is also eligible to
charge additional depreciation on the revalued amount. The pricing regulation allows for depreciation on the
revalued assets which have already been fully depreciated once. EVNNPT can use this method of recovering
additional depreciation on revalued fixed assets for meeting its equity funding requirement. The additional
depreciation to be charged in the annual revenue requirements of EVNNPT may be used to repay the residual
loan.
Considering these facts, EVNNPT can continue with existing arrangement and rely upon the additional
depreciation allowed on revaluation of assets
For the purpose of analysis, it has been assumed that the fixed assets will be revalued after every 10 years.
Hence in FY29 and FY39 (i.e. with a gap of 10 years), the assets based will increase with the revalued amount of
VND 60 trillion for FY29 and VND 70 trillion for FY39. It will reset the depreciation curve over the repayment
curve. However, this mechanism will have a significant impact on the tariff.
The graph below indicates the use of revaluation of assets to fund the repayment of loan:
However, there is not much clarity on the allowance of depreciation on the revalued value in the existing pricing
regulation. It is not certain that how much depreciation will be allowed in the revalued fixed assets. This option
is also not based on a prudent pricing principle because this in effect leads to double recovery of the
depreciation for such assets, i.e. 200% of asset value is recovered over 20 years. It might not be feasible to
charge depreciation on revalued assets considering the fact the awareness in public will increase in future.
-
5
10
15
20
25
Depreciation vs repayment of loans (VND trillion)
Total Repayment Total Depreciation
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 191
The net increase in annual revenue requirement of transmission tariff is shown in the graph below:
Allowance of reasonable Return on Equity (ROE) with normal depreciation
The previous scenario discussed above leads to higher transmission revenue requirements which will be
difficult to find acceptability among ERAV and other stakeholders.
It is observed that accelerated depreciation as a tool is not widely acceptable for the purpose of tariff
determination and use of excess cash generated from accelerated depreciation may lead to future debt trap.
Therefore, alternative options are required to be evaluated. Another option can be claiming return of equity
instead of claiming the accelerated depreciation. This approach is followed globally in the power sector.
There is a provision of allowing return on equity in the circular for determination of transmission pricing.
However the rate of return is not prescribed in the circular but as discussed above typically it is higher than
return on debt. In case of EVNNPT, the return on equity should be 13% which is 2% over and above the typical
domestic cost of debt.
The proceeds from return on equity can be used up for meeting the equity funding requirements. This will also
ensure widening of the net worth and improve the credit worthiness of the EVNNPT.
The graph below indicates the scenario an ROE of 13% is allowed by ERAV and EVNNPT claims a depreciation
rate of 5% (rather than 10%).
-
1
2
3
4
5
6
7
8
Increase in transmission ARR (VND trillion)
The Net Present Value of the net increase in Annual Revenue Requirement (ARR) for
EVNNPT is VND 9.48 trillion till FY42 (using a discounting rate of 10%).
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 192
It is evident that in such a scenario, the depreciation generated would be able to cater to the repayment
requirement. The ROE would allow the company to generate additional funds which may be used to fund
EVNNPT’s equity commitment
The net impact on the transmission annual revenue requirement is summarized in the graph below:
The above illustration clearly indicates that not only Scenario 3 beneficial for EVNNPT in reducing its future
risk but also beneficial for the consumers in long run. Moreover this is also in line with accepted norms in
similar developing and developed countries.
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Depreciation vs repayment of loans (VND trillion)
Repayment Depreciation ROE
(8)
(6)
(4)
(2)
-
2
4
6
8
10
Net increase/ (decrease) in ARR in VND Trillion
Increase/ (Decrease) in ARR
Net Present Value for net increase in Annual Revenue Requirement (ARR) for EVNNPT is -
VND 13.76 trillion till FY42 (using a discounting rate of 10%).
Recommendation#2: Utilisation of funds generated through accelerated depreciation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 193
Conclusion
Sound financial and cash management principles are essential pillars of the reform process for electricity
industry. Similar to banking industry, infrastructure companies deal with significant quantum of cash and it is
essential to match the quantum and timing of assets and liabilities. In case of a regulated industry, it is
pertinent to have in place pricing regulations which inherently promote such behaviour among companies.
In case of EVNNPT the timing and quantum mismatch between funds generated from depreciation and
liabilities from debt repayment may lead to significant cash flow risk, as evident in FY11. Once the investment
quantum plateaus with the passage of time and transmission infrastructure reaching a certain level of maturity
similar to developed countries this risk will most likely peak.
The concept note discussed the global practices followed in similar developing or developed nations pertaining
to ROE and Depreciation rates. In most countries, the depreciation rates are linked to the useful life of the
assets while ROE is typically higher than the cost of debt. These two criteria form the basic building blocks of
regulatory pricing mechanism.
With an aim to reduce the perceived risk on future cash flows owing to existing practice, it is advisable that
EVNNPT should focus on the allowance of the return on equity instead of accelerated depreciation. In this
option, the depreciation rates can be lowered to match the loan amortization schedule while a reasonable ROE
is allowed which can be funnelled to meet the equity commitments. This approach will in fact lead to a lower
tariff and benefit the consumers in long run as well as help the EVNNPT to operate efficiently. This is also in
line with the regulatory environment prevalent in most countries. Such a practice will also help EVNNPT
manage cash better.
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 194
Recommendation#3: Strategy for risk management against foreign exchange variation
Overview
A foreign exchange risk arises when a financial transaction is denominated in a currency other than the base
currency of a country. The risk is that there may be an adverse movement in the exchange rate of the
denomination currency in relation to the base currency before the date when the transaction is completed. This
means that a company might have to pay more than they signed the contract for. This is known as currency
fluctuation risk. It affects the value of the firm’s operating cash flows, profit and loss statements, and
competitive position, hence market share and stock price.
NPT has raised a significant amount of loan in foreign currency from the international banks or ODAs. As on
December 2012, the outstanding loan amount was 31.32 trillion VND out of which 74% was in foreign currency,
precisely 59% in USD (US Dollar), 5% in EUR (Euro) and 10% in JPY (Japanese Yen). The following graph
shows the variation of VND against USD, JPY and EUR historically (in VND).
As evident from above, all the three currencies have appreciated against the VND during last 10 years, especially
USD in which there has been no depression in any given year and EVNNPT has the maximum foreign loan
amount i.e. 59% in USD. Due to this, there have been significant foreign exchange fluctuation losses in the past.
In FY 2012, the realised foreign exchange loss was 195.67 billion VND and the unrealised foreign exchange loss
is 743.93 billion VND.
NPT is suffering huge financial losses due to foreign exchange fluctuation. Further, it is not able to recover the
foreign exchange fluctuation losses in the transmission pricing. There is no clear mechanism/timelines for
recovery of accumulated foreign exchange fluctuation losses prescribed by the ERAV. At present, ERAV allows
recovery of only realised forex losses but not the unrealised forex losses. The total accumulated loss on account
0
1
1
2
2
3
3
0
100
200
300
400
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
VN
D i
n '
00
ag
ain
st
JP
Y
VN
D i
n '
00
ag
ain
st
US
D/
EU
R
JPY EUR USD
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 195
of allocated foreign exchange fluctuation, as on December 2012, was around 2.01 trillion VND (96 million
USD). This was proposed to be recovered in three equal instalments in 2013, 2014 and 2015 (i.e. 671 billion
VND per annum). However, in 2014, ERAV has allowed only 241 billion VND of forex loss. This is deteriorating
the financial position of EVNNPT.
Based on the existing accounting framework in Vietnam, EVNNPT has flexibility in respect of not showing the
foreign exchange fluctuation losses/ expenses in one year. Due to this, they are able to show profit in their
financial statement and are paying income tax on this book profit which in reality does not exist. It is causing
further erosion of funds. This financial practice will have negative impact on the financial health of the
EVNNPT.
Based on the above facts, it can be concluded that the magnitude of impact on account of foreign exchange
fluctuation is quite significant in past. In future also, there is a high probability of increase in foreign exchange
losses due to the trend of USD appreciating against the VND. EVNNPT might have to pay an incremental
amount to repay the outstanding foreign currency loan. It is pertinent to mention that the tenure of the foreign
currency loan in EVNNPT varies between 20 to 30 years, which is significantly high in compare to other
countries.
At present EVNNPT does not hedge its risks on account of foreign currency fluctuation. However, the exact
reason for not hedging the foreign currency fluctuation risk has not been identified due to the fact that the
consultant did not get an opportunity to meet the Ministry of Finance and State Bank of Vietnam to understand
the existing framework in Vietnam and reasons for not hedging the foreign currency fluctuation risk by the
government enterprises. It might be because of non-availability of an appropriate hedging framework or
mechanism against the risk of foreign exchange fluctuation or hedging instruments in Vietnam.
Considering the huge foreign currency fluctuation risk, EVNNPT is in acute need to have a regulatory
framework that allows hedging against foreign currency fluctuation risk. It should be allowed to recover the
hedging cost in the transmission pricing. This concept note discusses about the various hedging options
available for foreign currency fluctuation risk globally along with the experiences across various other countries.
It broadly covers the existing options for foreign currency fluctuation hedging available in Vietnam. It will also
provide a strategy which can be followed by EVNNPT while hedging against foreign currency fluctuation risk.
Possible foreign exchange fluctuation hedging options
The foreign exchange fluctuation hedging refers to the activities to reduce or eliminate the exposure to foreign
exchange fluctuation arising from transactions or existing assets and liabilities denominated in foreign
currencies. It is basically a process of risk management with an objective to bring about certainty on cost of
foreign exchange fluctuation. It is done purely to manage the risk and not for the profit.
Globally, there are two methods that are being used to manage foreign exchange fluctuation risk:
1. Natural hedging; and
2. Financial hedging.
Natural hedging
The natural hedging means reducing the difference between receipts and payments in a given foreign currency.
The firms/ companies involved in international trade often attempt to ‘match’ the currency denomination of
their receipts and payments in order to limit foreign exchange exposure. Similarly, this principle is employed by
firms by taking on foreign currency assets or liabilities to net out existing exposures.
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 196
Similar to the technique of matching, multinational firms often use a strategy called ‘leading and lagging’. This
strategy essentially involves a parent company bringing forward or delaying payments or receipts of foreign
currency with its subsidiaries to offset the currency risks associated with other foreign currency transactions.
This strategy is one of managing cash flows across the consolidated group by the parent company.
Unfortunately, the option of natural hedging is not available with EVNNPT because the preliminary
requirement for opting natural hedging is that there should be some receipts and payments or assets and
liabilities in a given foreign currency. In case of EVNNPT, it has only payments and liabilities in USD - no assets
and receipts in USD, hence it cannot go with natural hedging option.
Financial hedging
The other method involves buying foreign exchange hedging instruments that are typically sold by banks and
foreign exchange brokers. The various options available for financial hedging are as follows:
Foreign exchange forward contracts
The forward contract is a contract between two parties, which allow a firm/ company to set the exchange rate at
which it will buy or sell a given quantity of foreign currency in the future (on either a fixed date or during a fixed
period of time). The firm/ company can use foreign exchange forward contracts to sell or purchase foreign
currencies at a future date and a given exchange rate. Since the forward rate would be agreed upon entering the
contract, subsequent exchange rate movements become irrelevant. The settlement takes place at the time and
the exchange rate mentioned in the contract, regardless of any fluctuations of the exchange rate on the foreign
exchange market.
They are flexible instruments that can easily match future transaction exposures (generally up to one year). The
forward contracts are easy to use and carry no purchase price - which makes them very popular.
Strengths associated with the option
The benefits associated with foreign exchange forwards are as follows:
1. There is no initial outlay required;
Fin
an
cia
l h
edg
ing
in
stru
men
ts Foreign exchange forward
contracts
Foreign exchange future contracts
Foreign exchange option contracts
Foreign exchange swaps Currency Swaps
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 197
2. While foreign exchange futures are standardised in amount and maturity, the foreign exchange
forwards can be tailored to suit an individual firm’s needs. The forward contracts are easy to use and
are flexible in terms of the contract amount and maturity;
3. The company is protected against unfavourable exchange rate fluctuations;
4. The cost of hedging is known upfront, hence it helps companies manage their profit margins and plan
cash flows. The budgeting and costing are accurate;
5. The forward contracts are cheaper than options and swaps, and easier to manage internally; and
6. It is easy to acquire a forward contract.
Weaknesses associated with the option
The weaknesses associated with this option are as follows:
1. Once a firm/ company has covered a transaction with a forward foreign exchange contract, it cannot
take advantage of preferential exchange rate movements;
2. All parties are exposed to counterparty default risk - It is an agreement between two parties, therefore
there is a risk of not making required delivery or payment by the other party; and
3. These contracts are not marketable, they can’t be sold to another party when they are no longer
required and are binding.
Foreign exchange future contracts
A foreign currency future contract is the contract specifying a standard volume of a particular currency to be
exchanged on a specific settlement date. A foreign exchange future contract is similar to the forward contract
but is more liquid because it is traded in an organized exchange i.e. the futures market. The depreciation of a
currency can be hedged by selling futures and appreciation can be hedged by buying futures. The important
differences between the foreign exchange future contracts and foreign exchange forward contracts instruments
are as follows:
1. The forward contracts are traded over-the-counter (OTC), means directly between counterparties, while
futures are exchange-traded instruments settled with a central counterparty;
2. The forward contracts are private agreements between two parties and are not as rigid in their stated
terms and conditions, while futures are less flexible; and
3. The specific details concerning settlement and delivery are quite distinct. For forward contracts,
settlement of the contract occurs at the end of the contract. Future contracts are marked-to-market
daily, which means that daily changes are settled day by day until the end of the contract. Furthermore,
settlement for future contracts can occur over a range of dates. Forward contracts, on the other hand,
only possess one settlement date.
The future contracts require a small initial outlay (a proportion of the value of the future) with which significant
amounts of money can be gained or lost with the actual price fluctuations.
Strengths associated with the option
The future contracts offer the following advantages:
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 198
1. There is a central market for futures. Since future contracts are traded on a central market, this
increases the liquidity. There are many market participants and one may easily buy or sell futures;
2. The company is protected against unfavourable exchange rate fluctuations;
3. A firm/ company who has taken a position in the futures market can easily make an opposite
transaction and close its position; and
4. Leverage is another key advantage of future contracts. This feature is brought about by the margin
system, where a trader takes on a large position with only a small initial deposit. Leverage allows the
trader to hedge big amounts with much smaller outlays.
Weaknesses associated with the option
The weaknesses associated with this option are as follows:
1. Standardized features: As mentioned earlier, the future contracts have standardized features with
respect to some characteristics like contract size, expiry date etc. It does not provide for flexibility in
terms and conditions of the contract;
2. Initial and daily variation margins: This is a unique feature of the futures contract. A firm/ company/
trader who wish to take a position in the futures market must first pay an initial margin or deposit. This
deposit will be returned when the trader closes his or her position. The initial and daily variation
margins can cause cash flow burden on small firm/ company/ trader; and
3. The markets for futures in many currencies either do not exist, or are relatively illiquid.
Foreign exchange option contracts
The firm/ company can hedge against foreign currency risk by purchasing a currency option- put or call. A
contract that grants the holder the right, but not the obligation, to buy or sell currency at a specified exchange
rate during a specified period of time is called foreign exchange option. For this right, a premium is paid to the
broker, which will vary depending on the number of contracts purchased. There are two types of foreign
exchange option contracts:
1. Call option contracts- A contract or agreement that gives a firm/ company the right (but not the
obligation) to buy a foreign currency at a specified price within a specific time period; and
2. Put option contracts-A contract or agreement giving the holder the right, but not the obligation, to sell a
specified amount of foreign currency at a specified price within a specified time. This is the opposite of
a call option, which gives the holder the right to buy a foreign currency.
The foreign exchange option contracts allow firm/ company to benefit from favourable movements in exchange
rates at the cost of upfront premium. For example, a company has purchased an option giving it the right to
purchase USD at an exchange rate of 21,500 USD/VND six months from now. In case, the exchange rate is
21,000 USD/VND at that time, the company won’t exercise its right to purchase the USD at 21,500 USD/ VND.
In case, the exchange rate is 22,000 USD/VND, then the company will exercise its right to purchase U.S. dollars
at a rate of 21,500 USD/VND.
The option contracts are also called as Exercise Price or Strike Price contracts. The fixed nature of the exercise
price reduces the uncertainty of exchange rate changes and limits the losses of open currency positions. The
foreign exchange option contract is particularly suited as a hedging tool for contingent cash flows, as is the case
in bidding processes.
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 199
Strengths associated with the option
The foreign exchange option contracts offer the following advantages:
1. Risk is limited for the buyer of options contract, i.e., it will at the most lose the contracts premium;
2. The company is protected against unfavourable exchange rate fluctuations; and
3. Helps to lock-in the price but without the compulsion to honour the contract, especially to benefit from
favourable price movements.
Weaknesses associated with the option
The weaknesses associated with foreign exchange option contracts are as follows:
1. As the foreign exchange option contracts are much more flexible compared to foreign exchange
forwards or futures, they are more expensive;
2. Not too easy to operate. It will require a team with specific skill set to deal in foreign exchange option
contracts; and
3. The perceived complexity of currency options and the fact that most of them carry a purchase price has
limited their use across various countries, in particular smaller or medium sized companies.
Foreign currency swaps
The foreign currency swaps means a contract in which the simultaneous selling and buying (or buying and
selling) of a foreign currency takes place. It helps firms to match receipts and payments in a foreign currency.
For example, if a company receives a US$250,000 payment today and knows it will have to make a payment of
US$250,000 in 45 days, it could enter into a swap arrangement whereby it sells US$250,000 today (for VND)
and commits to purchase the same amount of U.S. dollars in 45 days at an exchange rate that is pre-
determined. Entering into a swap allows the company to have access to the VND equivalent of US$250,000 for
the next 45 days. It also eliminates foreign exchange exposure during this period. However, the company now
has a contractual commitment to purchase U.S. dollars in 45 days and will need to pay for these with VND at
that time.
A foreign exchange swap consists of two legs:
1. a spot foreign exchange transaction; and
2. a forward foreign exchange transaction.
These two legs are executed simultaneously for the same quantity, and therefore offset each other.
As the foreign exchange swap contracts are simply a combination of a “spot” transaction and a forward contract,
there are no significant direct costs associated with the purchase of swaps (some collateral may need to be
posted).
Strengths associated with the option
The swap contracts offer the following advantages:
1. Customised transactions, perfectly suiting hedging needs;
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 200
2. Provides a choice to set the currency which the firm/ company requires;
3. Not very expensive; and
4. Very long time period hedge possible. Beneficial for long term contract.
Weaknesses associated with the option
The weaknesses associated with this option are as follows:
1. The disadvantage of a currency swap for the parties is that if one of them does not fulfil its obligations,
the other party leaves exposed;
2. There are credit risk issues that tend to be more complex than other types of transactions; and
3. Time consuming process due to the long negotiations process.
Select global practices
The foreign currency fluctuation hedging options used in other countries are listed in the table given below:
Country Forwards and futures Options Currency Swaps
Bangladesh √ √ √
China √ √ √
Hong Kong √ √ √
India √ √ √
Indonesia √ √ √
Malaysia √ √ ×
Philippine √ √ √
Singapore √ √ √
Sri Lanka √ √ ×
Chile √ √ √
Colombia √ √ √
Costa Rica √ × √
Mexico √ √ √
Uruguay √ × ×
Croatia √ × ×
Czech republic √ √ ×
Israel √ √ √
Poland √ √ √
Romania √ √ ×
Russia √ √ √
South Africa √ √ √
Turkey √ √ ×
Australia √ √ √
Japan √ √ √
Thailand √ √ √ Source: HSBC’s Emerging Markets Currency Guide 2012 and public domain information
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 201
Recovery of hedging cost
There is a cost associated with the hedging options, known as hedging cost. In general, the cost of hedging is
lower that foreign exchange fluctuation losses. The cost of hedging in the foreign exchange fluctuation losses
should be allowed by ERAV to EVNNPT while determining the transmission pricing. However, there is no
clarity in the transmission pricing regulation issued by ERAV. It is allowed in various countries, for example in
India, Nigeria, etc.
In India, the Central Electricity Regulatory Commission (CERC) provides for allowance for the cost of hedging
in its regulations. It is also pertinent to note that there is a provision for the allowance of foreign currency
fluctuation losses in case the transmission licensee is not able to hedge the foreign exchange risks.
The article 50 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,
2014 states that:
1. The generating company or the transmission licensee, as the case may be, may hedge foreign
exchange exposure in respect of the interest on foreign currency loan and repayment of foreign loan
acquired for the generating station or the transmission system, in part or in full in the discretion of
the generating company or the transmission licensee.
2. As and when the petitioner enters into any hedging based on its approved hedging policy, the
petitioner should communicate to the beneficiaries concerned about its hedging decision within thirty
days of entering into such hedging transaction(s).
3. Every generating company and transmission licensee shall recover the cost of hedging of foreign
exchange rate variation corresponding to the normative foreign debt, in the relevant year on year-to-
year basis as expense in the period in which it arises and extra VND liability corresponding to such
foreign exchange rate variation shall not be allowed against the hedged foreign debt.
4. To the extent the generating company or the transmission licensee is not able to hedge the foreign
exchange exposure, the extra VND liability towards interest payment and loan repayment
corresponding to the normative foreign currency loan in the relevant year shall be permissible
provided it is not attributable to the generating company or the transmission licensee or its suppliers
or contractors.
5. Every generating company and the transmission licensee shall recover the cost of hedging and
foreign exchange rate variation on year-to-year basis as income or expense in the period in which it
arises”
In Nigeria, the Nigerian Electricity Regulatory Commission also provides for allowing the foreign exchange
fluctuation risks in the transmission charges. The multi-year tariff order for the period 1 June 2012 to 31 May
2017 issued by the Nigerian Electricity Regulatory Commission states that:
“The foreign exchange risk is accommodated in the MYTO model on a bi-annual basis during the minor
reviews. In addition, although this risk is regularly adjusted during the minor reviews, investors have
informed the Commission that the official CBN rates are not always accessible to them and that they are often
charged a commission by their bankers for purchasing foreign exchange. NERC therefore recommends a 1%
premium above CBN rates to cover these additional costs. The exchange rate adopted is assumed to increase
steadily over the years. This is also subject to review bi-annually”.
Considering the above facts, the hedging cost should also be allowed by ERAV to EVNNPT while determining
the transmission pricing.
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 202
Implementation challenges
The implementation challenges for establishing a framework for foreign currency fluctuation hedging in
EVNNPT are as follows:
1. The establishment of hedging mechanism in EVNNPT will require approval from various stakeholders such as EVN, ERAV, MoIT and MoF. Obtaining approval from various stakeholders might be a potential barrier in the implementation of the recommendation;
2. No team of professionals with good exposure to hedging process in EVNNPT;
3. There is no clarity on the recovery of hedging cost in the transmission pricing. The cost of hedging
needs to be treated as a cost of financing and has to be a pass through component in the tariff;
4. If the cost of hedging is too high in Vietnam, it may actually outstretch the benefits of hedging;
5. Availability of hedging instruments in Vietnam is another important aspect for establishing the hedging
mechanism in EVNNPT. In the absence of the discussion with MoF and SBV, it is difficult to assess the
availability of hedging instruments in Vietnam; and
6. The liquidity position, i.e., demand-supply scenario of VND vis-à-vis free market currencies such as
USD and Euro is another important aspect in the establishment of hedging mechanism. In case the
demand for VND is very low compared to the supply, the hedging might be difficult.
Present status of foreign currency fluctuation hedging in Vietnam
In Vietnam, the foreign currency transactions are mainly governed by Decree 160 dated 28 December 2006.
The SBV announces a daily USD-VND official exchange rate. This is partly based on the average rate of
interbank transactions of the previous day. The SBV regulations set a trading band for USD-VND transactions
in the spot market. This trading band was last narrowed on 11 February 2011 from +/-3% down to +/-1%
around the official rate.
The forwards, swaps and options instruments are available in Vietnam. However, they remained to be a small
part of the foreign exchange market in Vietnam. They have accounted for only 10% of total foreign exchange
trading turnover.
The forward segment of the Vietnam foreign exchange market has been characterized by several unfavourable
features, such as:
1. Low trading volumes;
2. The sale-purchase structure of forward trading has been clearly lopsided by commercial banks. The
value of forward sales made by commercial banks represented around 75-85 percent of total forward
trading;
3. While quoting for the forward VND/USD rate, the banks have to work with highly prescriptive
guidelines. As per a report “VIETNAM’S EXCHANGE RATE POLICY AND IMPLICATIONS FOR ITS
FOREIGN EXCHANGE MARKET, 1986-2009”, it has been observed that out of 29 foreign exchange
dealers who were interviewed, 27 indicated that regulations had become a barrier to forward trading;
and
4. The banks are often relatively slow and cautious in responding to requests for forward quotations.
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 203
The currency options were first introduced by Eximbank into Vietnam’s forex market in 2003. However,
trading in this form of derivative products has yet to establish.
Implementation road map
The road-map for establishing a foreign exchange hedging mechanism in EVNNPT is as mentioned below:
The hedging strategy or detailed policy of EVNNPT should provide for the following:
1. The processes and controls in respect of hedging such as:
a. When should foreign exchange exposure be hedged?
b. What tools and instruments can be used under what circumstances?
c. Who is responsible for managing foreign exchange exposure?
2. Monitoring controls over the limits and hedging process;
3. Reporting requirements for hedging on regular basis;
4. Process to determine fair value of the derivative instruments;
5. Operational framework for hedging mechanism; and
6. Determining the accounting policy and disclosures.
•There should be policy/ decree/ regulation/ decision issued by the Government on foreign exchange fluctuation hedging mechanism applicable to power sector
•The policy guidelines should prescribe for heding the foreign exchange transactions entered into by EVNNPT and recovery of cost by ERAV
Policy framework
•Under the broad policy issued by the Government, the EVNNPT has to draft its hedging stratergy/ detailed policy. It should be approved by its management board.
•This detailed policy document should provide for processes and controls in repsect of hedging mechanism
Hedging strategy
•The implementation of hedging framework may require to establish a new team with an experience of hedging
•The hedging activity can be outsourced for the initial period
Organisation structuring
•The hedging mechanism will only be successful, if the hedging cost is being allowed to be recovered in the transmission pricing.
•The benefits from hedging should also be passed on the consumers
Regulatory approval
Recommendation#3: Strategy for risk management against foreign exchange variation
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 204
Once the EVNNPT decides for establishing the foreign exchange fluctuation hedging mechanism, it has to
deploy resources in managing it. A separate team with experience in hedging will be required under the finance
department. The operation framework to be followed by EVNNPT can be as follows:
Conclusion
The approach note discussed about the significance of foreign exchange fluctuation hedging for EVNNPT and
also the various options/ instruments used globally along with associated benefits and weakness. Although
EVNNPT will face challenges in establishing the hedging practices in Vietnam but it will be beneficial for
EVNNPT considering the huge dependence on foreign currency loans and the long term repayment tenure of
these foreign currency loans. EVNNPT should establish a foreign exchange fluctuation hedging mechanism to
minimise its foreign exchange fluctuation losses.
As an immediate step, EVNNPT should approach to ERAV for allowance of foreign exchange fluctuation
hedging expenses and foreign exchange fluctuation losses in the transmission tariff. Since Vietnam is a
developing economy, it is presently exposed to significant quantum of foreign loans, MoIT should develop a less
regulated market to encourage foreign exchange fluctuation hedging mechanism.
Determination of
exposure
•As a first step, EVNNPT should identify and measure the foreign exchange exposures in respect of repayment of foreign currency loan and payment of interest.
Analysis of forex
market
•After identifying and measuring the foriegn exchange exposures, EVNNPT needs to develop a forecast on the market trends to analyze the trend of the foreign exchange market in vietnam The period for forecasts should be typically 6 months. Based on the analysis, EVNNPT should estimate the foreign exchange risk and impact of it on the probability of EVNNPT
Setting up limits
•Based on identified foreign exchange exposures and estimated foreign exchange risk, EVNNPT has to set its limits for handling foreign exchange exposure. The remaining should be hedged by the EVNNPT through the selection of an appropriate hedging instrument
Selection of hedging instrument
•Based on the identified limits for hedging, EVNNPT needs to select an appropriate hedging instrument taking into consideration the hedging strategy approved by the management board and a robust cost benefit analysis.
Monitoring of losses
•NPT should also monitor the foreign exchange hedging transactions to identify the areas which need to be strenghtened in future. It should analyse the entire process of the transaction in case any loss has been incurred to EVNNPT after entering into a hedging transaction.
Reporting and review
•NPT should place an appropriate reporting and review process for periodic update to the management board. The reports should include status on unhedged forex transactions, details of the transactions entered by EVNNPT for hedging, profit or loss for each transaction, outcome of the monitoring report, and foreign currency trends in Vietnam.
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 205
Recommendation#4: Prioritization of the investment projects
Overview
In a State owned transmission utility, the obligation of the utility is to serve all customers and available
demand. Capital investments are suggested to maintain or enhance system reliability required to serve the
forecasted demand. The transmission planning focusses on selection of least cost alternative with aim to
achieve the desired reliability and meet the load requirements. The transmission planning is treated as a
sequential activity to generation planning since adding generation capacity is more expensive compared to
adding transmission capacity.
The essence behind traditional approach of transmission investment selection is as follows:
1. To meet the reliability requirements of the system;
2. To meet the growing load requirements; and
3. Selection of an expansion plan with least associated cost.
Existing practice
NPT which is the nodal company responsible for planning, development, operations and maintenance of
transmission assets in Vietnam, is also responsible for identification of transmission investment requirements,
appraisal of the projects and selection of projects for execution. The final decision on execution depends on a
number of other state participants- EVN, MoIT, etc. However, EVNNPT remains the key body to undertake
various feasibility analyses to ascertain the viability of each of the projects.
The present system of identification, investment appraisal and implementation of transmission projects in
Vietnam is not at par with the globally accepted investment evaluation framework.
The existing practice at EVNNPT is that any project identified and which are technically feasible are eligible
projects. The projects are screened for to ascertain the financial feasibility (as a part of the Feasibility Study) but
financial viability is not considered as a NO-GO criteria.
The first stage is project identification. The projects are identified and dovetailed with generation plan. The
identified projects are mostly approved as a part of the Master/ Five year plans/ annual implementation plan.
Once the projects are broadly identified as a part of the sector plan and approved by competent authorities,
EVNNPT is responsible for undertaking the feasibility study and preparation of technical design of the project.
All the projects would necessarily have to undergo the feasibility study, which is the primarily appraisal stage.
The feasibility study of the projects has to be approved by MOIT before the Detailed Technical Design is being
commenced.
Investment appraisal process
The investment appraisal process is divided into two parts:
1. Feasibility study; and
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 206
2. Detailed technical design.
Feasibility Study
At present, all identified projects undergo a detailed feasibility study in which certain economic, financial,
technical parameters are assessed and finally approved by MoIT. Once the feasibility stage is cleared
successfully, the projects are considered for next stage evaluation, i.e. approval of detailed technical design.
There are no scoring and weightage given to those parameters being evaluated during the approval of feasibility
study.
A select list of parameters considered as a part of the feasibility study:
1. Technical
a. System calculations: such as power flow studies, short circuit studies, dynamic and transient
stability studies
b. Line route survey: Line route survey is accompanied with three options and suggest optimal
route
c. Tower spotting, layout and estimate bill of quantities of equipment and material needed
d. Basic design (standard designs and specifications are prepared and approved by EVNNPT)
2. Financial
a. Total investment cost and financial analysis such as NPV, IRR, Benefit-to-Cost ratio
3. Others
a. Environment Impact Assessment (EIA) and Social Impact Assessment (SIA) and resettlement
to minimize land needs and adverse impact on local people and environment.
b. Other aspects like fire prevention, telecommunication etc.
Detailed Technical Design
The second stage of process which involves approval of detailed technical design of the transmission system is
known as Detailed Technical Design (DTD). The DTD is not mandatory for all projects and augmentation/ up
gradation projects associated with existing transmission substations and lines (also labelled as ‘Urgent and
Critical’) do not require an a detailed technical design. The detailed technical design is actually the phase in
which complete technical specifications for the project is finalised and approved by the appropriate authority.
Similar to the FS, the DTD is also sent up to EVN, MOIT, etc. for approval and once the approval is secured, the
project is considered as ready for implementation.
Key issues
1. There are several key issues in the transmission investment planning and investment appraisal process:
Upon careful examination of FS of select projects, it was seen that there is no scoring of the projects.
There is only a comparison with the standard criteria. The scoring will help EVNNPT to identify the
projects which are not low in terms of scores. In a situation, where EVNNPT has very limited resources,
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 207
the scoring will enable EVNNPT to select the projects based on the scores within a portfolio of number
of projects;
2. All the parameters mentioned in the evaluation are considered equally important. Practically, there are
some parameters which may be extremely critical for the benefit of the country, while some other
parameters may not be as important as others. There should be a mechanism to differentiate among the
parameters based on its criticality and importance. The projects with higher score should be
implemented first over other projects;
3. The financial and economic analysis of the projects is based on the Decision no 445, issued in 1994. It
provides for the assumptions and methodology for preparation of financial model to carry out the
financial and economic analysis of the proposed investment projects. The assumption and methodology
provided in the circular are outdated and are of no relevance considering the current structure of
Vietnam power sector. The norms for the determination of transmission charges, depreciation, O&M
expenses, etc. are not in line with the norms prescribed by ERAV and provided in the audited financial
statements;
4. It is evident that EVNNPT lacks funds to finance its capital requirements. In such a condition, there
should be a tool/ system/ process/ regulation in place based on which the decision in respect of
prioritization of future projects can be made. Considering the limited funds/ budgets in EVNNPT, the
prioritization is essential to determine which projects have to be immediately implemented and which
projects can be delayed;
5. In EVNNPT, the projects are selected on the basis of least cost transmission project to cater to selected
load and generation centres. It is now being challenged. There are a number of alternate options
available such as selection of projects based on benefits rather than cost/ public interests; and
6. In Vietnam, the transmission planning follows the distribution and generation planning. In Countries
with rapid power sector reforms such as US have their transmission planning leading the generation
and load growth. EVNNPT also needs to enter into a dynamic transmission sector planning.
With such issues in the investment planning and investment appraisal process, EVNNPT needs to revise the
framework used currently. A more comprehensive and structured framework for the project evaluation and
prioritization is needed.
There is a requirement of a robust framework to assist EVNNPT in undertaking investment decision
particularly in respect of prioritization of projects which should be based on an appropriate weightage of
technical importance (reliability) and the commercial and financial viability of the project.
A prioritization framework should consider the organisational goal while evaluating the projects. It should
evaluate the projects on various parameters such as technical, economic, financial and organizational
capabilities. The parameters should be weighted such that the critical parameters impacting significantly the
organisational goal and national benefit are identified distinctly. The most critical projects identified should be
considered for implementation first. The EVNNPT framework does not satisfy many of these criteria, therefore
there is a need for revision of the framework.
According to the G20 Investment and Infrastructure Working Group and the G20 Development Working
Group, June 2014, “Simply raising spending on infrastructure will not provide the allocative and distributional
efficiency required to enhance economic growth and job creation over the long-term. It is therefore critical to
achieving the international community’s growth, job creation and poverty alleviation goals that governments
allocate scarce resources available for investment where they will have the greatest impact”.
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 208
It is essential to have well-defined, transparent and clear criteria to prioritize projects so that their selection is
objective and free of any influence.
The Concept Paper looks at the global practices with relation to selection and prioritization of transmission
investments and proposes a comprehensive selection and prioritization criteria which may be followed by
EVNNPT in Vietnam.
Select global practices
Romania
Romanian TSO (TransElectrica - fully independent from the production and supply companies) is responsible
for transmission planning and development in Romania. TSO prepares a comprehensive ten year transmission
sector development which is updated once in every two years. Unlike in Vietnam, in Romania, the transmission
development plans are approved by an independent regulatory commission.
TSO conducts a complete set of studies including load flow analysis, security analysis, probabilistic analysis,
short circuit and dynamic calculations. The investment planning and appraisal consists of technical and
economic criteria which are summarized below:
1. Technical criteria
a. Planning with a n-1 reliability criteria and a n-2 reliability criteria to design transmission
capacity for nuclear power plants;
b. Static and dynamic stability; and
c. Technical criteria to design the reactive power compensation installations.
2. Economic criteria
a. Payback period (is the most important criteria to prioritize projects);
b. Reduction of loss of load costs;
c. Reduction of losses and costs;
d. Reduction of re-dispatching costs;
e. Reduction of congestion costs; and
f. Benefit from telecommunication lines, and any other benefits.
TSO does not conduct risk estimations.
Ireland
EIRGRID is the national power transmission company in Republic of Ireland. The entire transmission planning
stage comprises of six phases. The six phase of the transmission planning in EIRGRID is summarized below:
Top level engagement
This is the stakeholder consultation stage where concerns of various groups are addressed and the importance of grid development is communicated. There are two advisory forums- National and Regional Advisory Forums.
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 209
Preliminary phase: technical basis of the project
The technical need for the project is clearly documented. The scope of the project is identified and defined in this phase. The scope is constantly challenged during the process to ascertain the importance and technical viability of the project.
Information gathering phase
The objectives of the information gathering phase are:
1. Preparation of the study area and rationale for the project;
2. To identify environmental and other constraints within the study area and prepare an environmental
and constraint map;
3. To identify potential route corridors/site locations (Potential Indicative Corridor/ Sites);
4. To present key messages regarding the project to the public and stakeholders; and
5. To obtain initial public/stakeholder input regarding the project.
Evaluation phase
During this phase, the various alternatives of corridors and sites are evaluated. The objectives of this phase are summarized below:
1. Carry out a multi-criteria evaluation of identified corridors/sites which includes identification of
selection criteria (which could be different for different projects) and evaluation of corridors;
2. Conduct comparative evaluation of alternatives;
3. Shortlist the identified indicative corridors/sites;
4. To identify an emerging preferred corridor/site (among alternative select the best one);
5. To identify a potentially feasible route within identified corridors;
6. To continue to present key messages to public/stakeholders; and
7. To obtain ongoing public/stakeholder input regarding project.
Route conformation phase
During this phase, the route is confirmed, landowners are identified and complete evaluation is done for the emerged preferred corridor. It includes:
1. Identify and engage with landowners on the route/site;
2. Continue to present key messages to public/stakeholders; and
3. Move from information gathering to information giving.
Environmental Impact Assessment and Application phase
This is the final stage where complete planning application along with proposal is prepared. At this stage comprehensive environmental impact assessment is also conducted and communicated to the stakeholders.
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 210
India
POWERGRID is the inter-state transmission company which owns and operates almost all the inter-state
transmission assets in India. The transmission planning process of POWERGRID comprises of two broad steps:
Planning phase
The planning stage commences with identification of the project to be implemented in near to long term. The
planning phase comprises of the following three steps:
1. National Electricity Plan;
2. Network Plan; and
3. Identification of the projects by Empowered Committee to be implemented through competitive
bidding route.
Detailed design and implementation phase
This is the primarily stage where complete feasibility of the project is ascertained, investment proposal is
prepared and financing for the project is identified. The key steps in this phase are:
1. Approval of advance Preliminary Expense;
2. Feasibility Report (FR)/ Detailed Project Report (DPR) including Cost Estimates;
3. Project investment proposal; and
4. Finalization of project financing options.
It is the key appraisal stage for the project. At this stage the project is either accepted/ rejected / alternatives are
evaluated. An unviable project will not pass the feasibility stage. The projects are evaluated on the basis of the
following framework:
1. Technical: the technical evaluation will cover the evaluation of the following:
a. Broad route and alternate route identification for the project;
b. Bill of quantity (BOQ) for the project; and
c. Design, technical specifications and construction standards for foundations, towers, cables and
insulators.
2. Techno-commercial: It will cover the evaluation of the following:
a. Project packaging to attract suitable competition facilitating cost effective procurement;
b. Cost estimation as per BOQ prepared of the various system elements (such as cables,
conductors, transformers, switchgears, capacitors, lightning arrestors and insulators, the
control and communication system, engineering and project management, supervision and
contingencies);
c. Project implementation plan and schedule for the project taking into account, system
constraints and other relevant factors;
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 211
d. Operation and maintenance plan including facilities such as protection, communication,
measurement, telemetry and interface equipment etc.;
e. Statutory and environmental clearances for project; and
f. System operation requirements, based on applicable laws and grid code.
3. Financial: It will be focused on carrying out detailed financial analysis including proposed capital
structure for the project.
The prioritization of the projects in India is very dynamic, where the central power planning agency ((namely
Central Electricity Authority) reviews the progress of the planned generation capacity to be added, increase in
load and the progress of the transmission lines proposed to be carrying that additional load.
Proposed framework for prioritization
At present, the resources available with EVNNPT are limited. It would often have conflicting projects exceeding
the available resources. In such a scenario, EVNNPT would have to select from these conflicting projects based
on the prioritization of the projects. There is need of framework based on which the prioritization of the
projects can be performed.
Overall Approach
NPT may follow the following six steps framework for prioritization of the projects:
Steps Description
Identify the critical parameters for
the evaluation of the project
Identify the parameters based on which the projects are to be evaluated.
The parameters will be divided into three parts:
Technical parameters
Economic parameters
Organizational parameters
Assign weights to the parameters
based on their criticality
While assigning weights, EVNNPT should keep in mind the
organizational and Company’s goal. The parameters which are of utmost
national importance should be given more weights than others.
Keep a minimum qualifying criteria
for each parameter
There should be minimum qualifying criteria for each parameter. The
project should fulfil the minimum qualifying criteria for each parameter
and any of the projects scoring below that level should be eliminated.
Assign a weightage to all the
parameters and determine the
weightage average score for all the
projects
Based on the assigned weightage for each parameter, a weighted average
score should be determined for all the projects which pass the qualifying
criteria
Weighted Average Score = (Score on each
parameter*Weights of each parameter) / Sum (Weights of
each parameter)
Rank the projects based on the
weighted average score
Rank all the projects in a decreasing order to create a prioritized list.
Implement the top ranked projects
for which funds are available
Based on the available funds, EVNNPT should select the top ranked
projects that should be implemented for national benefit and to achieve
the organizational growth
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 212
Identify the critical parameters for the evaluation of the project
Based on the practices followed globally for the selection of the transmission projects, the following technical
and economic parameters can be considered for the selection of the transmission projects.
Technical parameters
The key technical criteria would include:
1. N-1 reliability criterion: The network complaint with (n-1) criterion means the network will be able
to withstand a single system element (e.g. transmission line, transformer, generating unit, etc.) outage
and meets the following requirements:
a. No breach of the limiting values for network operation variables (operation voltage, frequency)
that may endanger the security of the power system or lead to an unacceptable strain on
equipment, damage, destruction or an inadmissible reduction in the life of equipment;
b. No inadmissible overloading of components may take place;
c. The voltages and frequency are satisfactory for consumers and generating units;
d. Interruptions of supply are avoided (with the use of redundancies temporarily available in
lower voltage networks and in the installations of transmission system users);
e. Secondary tripping through activation of further protection devices on equipment not directly
affected by the disturbance cannot involve the risk of spreading the disturbance;
f. There is no need to change or, if necessary, interrupt power transfers; and
g. The loss of generating unit stability is avoided.
2. Short-circuit criterion: The facilities and devices connected to the network must be designed to
operate according to given current limits. Short circuit analysis provides the value of the maximum
current expected to flow during short circuit at specific node of the network. Network elements
(conductors, breakers, transformers) should be able to withstand such fault current without any
permanent damage to the element. The system design should guarantee that:
a. Short circuit currents will not exceed the capacity of devices/ switchgear installed on that node,
b. A sufficient short-circuit power value is available for fault clearance by the electrical protection
system.
c. In the short circuit analysis, the short circuit current for the line should be less than the limit
specified
3. Stability criterion: In the stability criterion, the objective should be to check the stability (state of
synchronism among generators) of the grid when fault occurs on any element or there is sudden
tripping of generator(s) or sharp reduction in the load. Stability calculations have to determine the time
value of short-circuit duration (critical clearance time-Tc) for which stability is to be ensured ((i.e.
generators must not go out of synchronism till such time after the transient), in order to estimate
stability margin. Critical clearance time should be calculated for the lines which are part of corridors of
important power transit. Steady-state scenarios for stability calculations should be determined.
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 213
4. Load Flow Analysis: Load flow studies should be conducted to ensure that electrical power transfer
from generators to consumers through the grid system is stable, reliable and economic and do not
violate network loading and bus voltage limits. There should be standards for the load flow in the
transmission lines and the projects to be scored on the basis of the transmission load they are planned
for. The load flowing through each line of the network should be recorded and the overloading of lines
should also be recorded. One possible recording template could be:
Planning scenario
Node Voltage (kV) Overloaded branch
Overloading (% Imax or Sr)
Description of the analysed scenario
Name of nodes with voltages outside of permitted range
Absolute value of voltage which is out of range
Name of branch which is overloaded
Amount of overloading in percentage of maximum current or rated power
5. Line Survey: The transmission line survey should include the following:
a. Line route based upon topo sheets and theodolite survey;
b. Soil resistivity as this will give necessary data for induced currents and on that PTCC clearance
is to be obtained;
c. Crossing details e.g. river roads, telephone lines and forest etc.; and
d. Angle points so as to know the line route.
6. Environmental Impact Analysis: In this, the environmental impact of the project and the
measures envisaged to prevent damage to environment should be evaluated together with the cost
implication. The two important aspects to consider in this case are:
a. Forest clearing along the transmission line; and
b. Compensatory afforestation plan.
Organizational and management parameters
The organizational and management parameters will include the following:
1. Implementation plan: The project should also be given a score on the feasibility of the implementation
plan;
2. State of preparedness: There should a minimum benchmark set for the following to evaluate project:
a. Mode of implementation;
b. Infrastructural Back-up; and
c. Studies and investigations conducted.
Economic parameters
The economic parameters will cover the following:
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 214
1. Need for the project: The need (business / social / others) for the project should be clearly defined
and the project should be scored on how critical is the need right now. The scoring criteria can be a
LIKERT scale rating and the scoring can be 1 to 5 based on the criticality. The LIKERT scale rating is
used to evaluate relative degree of positive or negative response typically to a questionnaire, such as a
LIKERT scale can be very high, high, moderate, low and very low;
2. Cost benefit analysis: Cost effectiveness analysis should be undertaken to determine whether
projected investment in the proposed project is consistent with overall national and sectorial objectives
and represents the best means of achieving the intended benefits;
3. Financial cost of transmission: For the purpose of appraisal, the capital cost and the operating
costs should be worked out at market prices. Cash flow should be prepared for the projected cost and
the flow of energy in each year covering entire economic life of the project. The costs and the units
transmitted should be discounted at a pre-determined rate of discount as may be specified by the
Government to workout unit cost of transmission;
4. Economic cost of transmission: The objective of the economic analysis of transmission project
should be to determine the cost of transmission at their true economic cost- actual resources cost as the
financial cost of transmission might not reflect the true cost of power on account of distortions inherent
in the market prices. While working out the economic cost of transmission, both the costs and power
transmitted have to be valued at their true economic resources cost. Ellis process involves removal of
taxes and duties from the costs as they are not the costs to the society. Similarly, the subsidies are also
not allowed as they are only transfer payments. The foreign exchange being scarce, there is certain
amount of premium on it. All the imported items such as plant and machinery have to be valued at CIF
prices. Apart from adjustment in the costs, the economic analysis also covers the impact of the
proposed project on the power system. As a result of the proposed project becoming operative, there
may be some improvement in reliability of the system. It should also consider the associated
environment and social cost;
5. Sensitivity analysis: The project plan should be prepared on the basis of, as far as possible, realistic
assumption of demand supply gap, capital cost estimates, gestation period, operating cost estimates,
production build-up, turnover, economic life, etc. However, the project is in the nature of a venture
which means exposure to chance and some of the assumptions/estimates may go wrong. Experience
shows that in several areas assumptions have often gone wrong. It is, therefore, necessary to carry out
sensitivity analysis to indicate the project's financial viability when there is changes in the estimates of
key parameters such as capital costs particularly the foreign exchange component, operating cost etc.
The extent of changes in the key parameters should be based on the past experience relating to the
sector. If the costs are very sensitive to the changes in the independent variable, the plan is not robust
enough. If the plan is not robust, it should be scored low for the implementation;
6. Profitability index: The profitability index (PI) is defined as the ratio between expected annual
benefit from candidate project and the annuity of its expected costs. In case the profitability of the
project is over one (1) then it is economically viable. The expected benefits and costs should be
determined as follows:
a. The expected benefits: The expected benefits should be the weighted average of the
followings:
i. Benefit due to reduction of expected annual undelivered electricity costs;
ii. Benefit due to annual losses reduction;
iii. Benefit due to reduction of annual re-dispatching costs; and
Recommendation#4: Prioritization of the investment projects
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 215
iv. Benefit due to annual congestion costs reduction.
b. Expected costs of transmission project: The expected costs in the transmission project
should be:
i. Investment costs;
ii. Operation and maintenance costs; and
iii. System costs.
Assign weights to the parameters based on their criticality
The assignment of weights would depend on the strategic priority of the stakeholders in the sector. The weights
should be assigned to the framework through a consultative process including key stakeholders. The process of
weightage definition should be through brainstorming session between representatives all key departments.
However, assignment of weightage should be a time bound activity and the team responsible should present the
findings to the Board within specific time period. During this process, the minimum cut-off values for select
parameters may also be defined.
The values could be decided by EVNNPT Board and then sent to MOIT for approval.
The proposed investment evaluation framework for prioritization of projects has been proposed to look at
transmission sector as an area leading power sector reforms. Growth in power transmission is required for the
development and growth of power markets. Hence, the planning and evaluation criteria for selection of
transmission investments, to be set up within limited resources are of paramount importance.
The framework proposed is robust and a number of key elements of the framework is being discussed and
implemented in developing countries such as India and China. The basic framework for the project evaluation
has been defined however before operationalizing the key weightages for each of the parameter along with
minimum cut-off criteria should be defined by EVNNPT.
The evaluation framework can be further automated which will ensure a higher degree of transparency and
controls. Finally, parameters and process definition is only part of the work done but the true success lies in
actual implementation. Hence it is imperative that the evaluation framework is used impartially.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 216
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Project model & Corporate model
Refer Appendix 8 - for the MS Excel based Project Model and Corporate Model
Description - Project model
Overview
Financial model is a standard tool widely used by investors, financial institutions and external evaluators to
assess the viability of a project. The leading public sector utilities around the world post the sector reform
process have widely adopted financial modelling as a basic and important phase of the investment appraisal
process.
NPT also uses financial models to assess the financial and economic viability of the projects based on the
assumptions and guidelines in the Decision No. 445. However, the financial models in use are outdated. It is
not adequate to evaluate an investment proposal on all the economic and financial parameters. The model
calculates some key financial metrics such as NPV and IRR but is not flexible to offer a variety of views for
different stakeholders.
Based on our observations and review of the existing financial model and our expertise in developing similar
models for public utilities, private investors and multilateral financial institutions, we have prepared a robust
financial model for appraising a project.
The project model is prepared to assess the financial and economic viability of an investment proposal as a
standalone project. Some of the key features of the financial model are as below:
1. The capital investment proposal including inflow of debt and equity has been calculated quarterly to
bring in more accuracy to the financial model;
2. Units of currency are primarily in VND million;
3. Segregation of input, output and working sections in the model to ease operation and updating;
4. Flexible and robust time and date functions so that the same model can be reused multiple times; and
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 217
5. Calculating multiple ratios from view point of investors/ financial institutions/ and regulators.
This note is focused on a providing a complete brief about the financial model which would be useful for the
EVNNPT to operate and subsequently update the financial model. The entire note is divided into three sections,
similar to the financial model i.e. Assumptions/ Input, Working area and Output section.
The standard modus operandi for using financial models is that all users should have the flexibility to update
Assumptions/ Input area and review the Output section but the Working area should be managed only by a
dedicated team from Finance/ IMD Department.
Feeding in the right input
The financial model has a dedicated input area where the key assumptions pertaining to the project needs to be
fed in. The input area is marked distinctively with Yellow colour, marking off cells where the inputs should be
fed in. The rest of the section / values in the sheet are primarily either fixed values/ preliminary calculations.
Assumptions
The table below clearly indicates the major assumptions in the financial model and manner in which individual
values should be incorporated.
Reference Description Input values
Input sheet Line 6-17
The table in the associated line numbers indicates the mapping of each month (represented by month numbers) to each quarter (represented by quarter numbers).
The values should not change except if there is a change in the convention of the financial year for EVNNPT.
Input sheet Line 19-22
The lines are general time related input and should not change
Input sheet Cell D26
The input represents date on which the financial and cost are being evaluated. In most cases the date should be the current date when the model is being customized for a project.
The date is entered in a mm-dd-yyyy format
Input sheet Cell D30-31/ 35-36/ 40-43/ 50-52/ 56-58/ 62-64/ 70-75/ 79-84
The user needs to enter the value of the project components in VND million. The prices should ideally represent the current prices (i.e. on the Base Date in Cell D26)
The absolute cost needs to be plugged against each of the corresponding investment item.
Input sheet Cell D90-96/ E90-96/ D99-105
The cells indicate the general details of the project such as line length and number of bays.
The user needs to enter the project details in the requisite cells based on the units written in corresponding cells. The cells E90-96 are options in a drop down box and hence the user just needs to select the right input.
Input sheet Line 117-119/ 121-123/ 125-129/ 131
The line represents how the investment (in terms of actual cash outflows) is phased over the entire construction period. The total for each line item should be exactly equal to 100%.
The user needs to enter the percentage of money spent during each quarter compared to the total cost of the item.
Input sheet Cell C135
The cell represents how much debt would be required as a percentage of the total capital cost.
The user needs to enter the percentage of debt to the total project cost.
Input sheet The cell represents of the total equity to be The user needs to enter the
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 218
Reference Description Input values C137 invested in the project, the amount of equity to be
invested upfront before the debt comes in. percentage of the total equity which will be invested upfront before the debt inflow.
Input sheet C138
The cell represent the return on equity to be allowed by the regulator for the project
The user needs to input the expected return on equity for the particular project based on regulatory guidelines.
Input sheet C139
The cell represents the interest rate on working capital loans.
The user needs to enter the expected interest rate for working capital loans based on prevailing market scenario.
Input sheet C140
The cell represents the WACC/ threshold rate over which the project would be viable for both debt and equity holders.
The user needs to enter the WACC/ minimum hurdle rate over which the project would be viable for the investors and banks. General formula is Debt/total project cost * (interest rate) * (1-tax rate) + equity/ total project cost * (cost of equity).
Input sheet D144-147
The proportion of the total debt to be financed by the corresponding debt item. The total for all debts should be 100%.
The user needs to enter the percentage of total debt to be financed through each loan source.
Input sheet D151/164/177/190
The cells represent the currency in which borrowing happens.
The options are available in a drop down menu and the user has to simply select the currency of the loan. The options are provided in the params sheet and model team can revise the same if a new currency type is required.
Input sheet D152/165/178/191
The cells represent the type of debt whether it is linked to LIBOR, Vietnam’s domestic interest rate or at fixed rate.
The options are available in a drop down menu and the user has to simply select the type of loan.
Input sheet D153/166/179/192
The cell represents the interest rate. Depending on the type of loan, the interest rate may change.
The user needs to enter the interest rate based on the prevailing market conditions.
Input sheet D154/167/180/193
The cells get activated only if hedging switch is on and represent the cost of hedging. This is the premium over the interest rate for full hedge.
In case the cell gets activated, i.e. text will appear asking to input the “Hedging cost” the user needs to enter the cost of hedging in percentage. This percentage will be added to the interest rate.
Input sheet D156/169/182/195
The cells are the switch for hedging and indicate if the hedging is being done for the loan or not.
The options are available in a drop down menu and the user has to simply select the option to hedge or not.
Input sheet D158/171/184/197
The cells represent the moratorium period i.e. period after the COD post which the repayment of loan begins.
The user needs to enter the moratorium period in months.
Input sheet The lines represent the loan repayment schedule The user needs to input the
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 219
Reference Description Input values
D161/174/187/200 i.e. the percentage of the total loan to be repaid during that year. The total of each line should be equal to 100%
repayment scheduled for the loan based on tentative loan conditions.
Input sheet Line 205-206/209-210/ 213
The lines represent the forecast of macro-economic parameters. Lines 205-206 represent the exchange rate forecast between VND USD and VND Euro. Lines 209-210 represent the interest rates especially LIBOR and Vietnam base rate projections. Line 213 represents the inflation rate projections for Vietnam.
The user needs to enter the forecast for macro-economic parameters based on management’s view/ taking inputs from economists.
Input sheet D217-219/ 221-223/ 225-229
The cells represent the portion of the total cost for each item of the transmission project which is dependent on inflation. For example only 50% of the total conductor cost is subject to inflation.
The user needs to input portion the capital cost for the particular item which would depend on inflation and the cost may rise with time.
Input sheet D234-236 and D239-241
The cells (234-236) represent the base year cost for employee costs, administrative and general expenses and repair and maintenance costs. The cells 239-241 represent the escalation rate for the corresponding employee costs, administrative and general expenses and repair and maintenance costs.
The user needs to enter the estimate for base year for employee costs, administrative and general expenses and repair and maintenance costs and the expected annual escalation rate for the same.
Input sheet D245-248
The cells represent information for computation of tax. Cell D 245 indicates the tax holiday which may be applicable for transmission investments. Cell D246 indicates the corporate tax rate. Cell D 247 represents the VAT rate. Cell D 248 represents the years for which losses can be carried over for tax computation.
The user needs to enter the tax related inputs based on the actual guidance from tax department.
Input sheet D253-258 and E253-258
The cells represent the life of the assets and the residual value at the end of the life. These two values are used to calculate the depreciation rates.
The user needs to enter the life of the particular type of asset and the corresponding residual life for the project.
Input sheet Line 261-263
Line 261 represents transmission losses for the particular line. Line 262 represents the forecast for electricity bought (i.e. electricity input to the line measured at the starting point of the line). Line 263 represents the forecast for the price at which electricity is bought by EVNNPT.
The user needs to enter the transmission line losses, quantum of electricity to be bought and the price at which the electricity will be bought.
Input sheet D266-267
The cells represent the current assets. Cell D266 indicates the receivable days (expressed in months). Cell D267 indicates the inventory for spares expressed as a percentage of the fixed assets.
The user needs to input the months of receivables and inventory that the project would need to maintain as a percentage of the total asset base.
Input sheet D270-271
The cells represent the current liabilities. Cell D 270 represents the O&M expense payable days (expressed in months). Cell D 271 represents the power purchase payable days (expressed in months).
The user needs to input the months of payables for O&M expenses and for power purchase.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 220
Error checking
A user need to be careful while plugging in the input values while there are specific checks at certain sections to
indicate an erroneous entry. The colour coding for error checking is mostly incorporated in Column A. The
colour coding is simple; Green represents correct values while Red represents wrong value.
The description of error checking is provided in the table below:
Reference Error checking
Input sheet Line 117-119/ 121-123/ 125-129/ 131
The phasing of investments (%age) is used to show how has the total investment spread over the construction period. The total phasing for a single item (such as Conductors or Insulators or Civil) cannot exceed or be below 100% except for items where there are no investments at all.
Input sheet Line 161/174/187/200
The line items represent the repayment schedule as %age of the total debt. The total repayment scheduled cannot be less than or exceed 100%.
Input sheet Cell D148
The Cells D144-147 represents the proportion of the total debt being financed by corresponding debt item. Cell D148 represents the total of sum of individual loan as a percentage of the total debt. This cell should have a value of 100%.
Feeding in the right input
The sheets “Quarter_computations” and “Annual_computations” are the calculation sheets. These sheets
should only be changed by experienced modellers in charge of maintaining the financial model.
The sheet “Quarter_computations” calculates the phasing of the investments in quarters from the date of the
estimation, expected debt and equity inflow and calculation of IDC and interest. Some of the key elements of
the sheet are summarized in the table below:
Reference Description
Quarter_computation Line 74-90
The cost of the project will increase from the date of estimation/ modelling to the actual implementation. This section forecasts the nominal cost of the project. The section uses the base cost and the inflation values along with dependence of each project component (denoted in the Input sheet: Line 217-229) on the inflation to calculate the nominal value of the project.
Quarter_computation Line 115-117
Complete equity phasing for the project which is calculated from the project phasing, debt to equity ratio and upfront equity commitment.
Quarter_computation Line 120-171
In these lines the complete debt schedule for the project is computed. The debt schedule includes debt inflow, repayment, interest calculations (including IDC) and forex fluctuations.
The sheet “Annual_computations” focusses on calculation of depreciation, O&M expenses, taxes, working
capital requirements and annual revenue requirement for the particular project. The table below summarizes
the important sections of the working sheet.
Reference Description
Annual_computation Line 28-72
The depreciation for each asset type is calculated in the lines from 28-72. The calculation depends on the depreciation rates and investment made.
Annual_computation Line 75-81
The O&M expenses are calculated in the lines from 75-81. The calculation uses the base year estimation for employee, administrative and general and repair and
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 221
Reference Description maintenance expenses and the expected annual escalation rates for the same.
Annual_computation Line 83-96
The lines from 83-96 has the complete tax calculations including tax holiday, carry forward of losses and corporate tax and VAT payable.
Annual_computation Line 99-116
This section includes the calculation of the transmission pricing for the particular project using the Cost + ROE principle.
Annual_computation Line 122-130
These lines contain the calculations of the working capital requirements including forecast of current asset and current liabilities.
The sheet “Financial statements” is simply a summary of all items into the financial statements i.e. P&L,
Balance Sheet and Cash Flow Statement. The sheet also includes calculation of Free Cash Flow to the Project
and Free Cash Flow to equity holders to calculate the IRR and NPV.
Decoding the output
Iterations and how to run the model once the inputs are changed (Button on the output sheet)
There are certain sections in the model which have iterative calculation which implies that the some values have
circular dependence. In order to remove the circular dependence, we have used a macro which will be activated
pressing the button “Press the button to execute” on sheet “Key output.”
Hence every time an input is updated the user has to press this button to calculate the results.
Transmission pricing
The lines from D05 to H08 summarize the transmission pricing and details are summarized in the table below:
Reference Description
Key output D05 to H05
The line indicates the power buying rate
Key output D06 to H06
The line indicates the power selling rate
Key output D07 to H07
The line indicates the transmission price per kWh
Key output D08 to H08
The line indicates the annual revenue requirement for EVNNPT for this particular project including the costs and the profit margin in VND million.
Financial statements
The cells from D11 to H76 contain the detailed financial statements for the first five years of operations. The
years for which the user intends to see the results can be changed by change the cells D04 to H04.
The cells D15-H15, D19-H19, D23-H23, D29-H29 and D33-H33 calculate the key profitability ratios for the
project for the corresponding years. The profitability ratios are key values to indicate the profitability of the
project in terms of the pricing and cost structure.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 222
Ratio analysis
The cells from M 06 to Q 18 summarize the key ratios for the project. Each of the ratios indicate a different
aspect of the project and the table below shall help deciphering the ratios:
Ratio Description
Debt to equity ratio This is the standard leverage ratio to indicate how much the project is levered. A high leverage is generally good for the project since it indicates lower business risk for the equity holders and improved equity cash flows. However too high leverage also increases the financing risk for the project and the project may not be able to sustain the debt service requirements.
DSCR (Debt Service Coverage Ratio)
This ratio is defined as the ratio of Net Income to the total debt service requirements (i.e. repayment + interest). The DSCR is an important ratio which is evaluated by the banks/ lenders of the project and typical DSCR requirements is over 1.2 (however it may vary depending on the bank/ financial institution).
Interest coverage ratio (ICR)
This ratio is defined as the ratio of Net Income to the total interest payments. The Interest coverage is also an important ratio which is evaluated by the banks/ lenders of the project. The ICR is used to see if the project is able to meet the interest on loans.
Current ratio The current ratio is a measure of the liquidity of the project. It is used to assess if the project generates enough cash to meet its short term obligations. Typically a current ratio of over 1.5 is acceptable. A current ratio of less than 1 indicates that the company may likely enter to a cash strap scenario in future.
Acid test Similar to the current ratio, acid test is also a measure to assess the liquidity scenario of the project without considering the inventory (since a company typically cannot sell its inventory to generate cash). An acid test of less than 1 indicates that the company may likely enter to a cash strap scenario in future.
Days of receivables The approximate time it takes for the project to receive the payments from its customers.
Asset turnover Asset turnover depicts how profitably the assets are employed in the business. Typically in case of capital intensive industry such as power transmission asset turnover is lower compared to a low capital intensive industry such as retail/ electricity distribution. This ratio can be used to also evaluate competing projects. However a general approach is to determine the historical asset turnover and select project which match or exceed the benchmark ratio.
Degree of operating leverage (DOL)
DOL is a type of leverage ratio summarizing the effect of operating leverage on a company's earnings before interest and taxes (EBIT). Operating leverage involves using a large proportion of fixed costs to variable costs in the operations of the firm. The higher the degree of operating leverage, the more volatile the EBIT figure will be relative to a given change in sales (amount of power received and sold), all other things remaining the same. In a transmission business typically the degree of operating leverage is very low.
Days of payables The approximate time it takes for the project to pay the payments it owes to its suppliers.
Returns
The returns which are the final set of output parameters are the most important ones in any project appraisal.
The key ratios are summarized in the table below:
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 223
Parameter Description
IRR to project The IRR to the project is the rate of discount at which the NPV to the project is zero. A project is said to be feasible only if the IRR to the project is greater than WACC. However on occasions IRR function doesn’t work since when the cash flow changes sign for more than once during the life of the project. At times of comparing two projects with different lives, IRR is not the right function to use. Hence NPV is treated as a better ratio for evaluation.
NPV to the project The NPV to the project is the value the project will generate considering an opportunity cost equal to the WACC of the project. A project is said to be feasible for equity and debt holders only if the NPV to the project is greater than 0.
IRR to the equity holders
The IRR to the equity holders is the rate of discount at which the NPV to the equity holders is zero. A project is feasible for equity investors only if the IRR to equity holders is greater than Cost of Equity.
NPV to the equity holders
The NPV to the equity holders is the value the project will generate for equity investors considering an opportunity cost equal to the cost of equity for the project. (In this case we have used ROE as a substitute for Cost of Equity). A project is said to be feasible for equity holders only if the NPV to the equity holders is greater than 0.
Payback period The Payback period is the years taken to recover the total investment from the date of commercial operations or COD.
This financial model is built to be simple yet scalable. However it is important that the modification to the
formulas and the working sheets should only be managed by professional modellers, typically from the Finance
and Accounts/ IMD Department. It is important that customization for individual projects should be kept a
minimum. The actual selection framework/ various hurdle rates would dependent on EVNNPT’s management
keeping in view the existing industry trend and acceptable benchmarks for lenders and investors.
Description - Corporate model
Overview
The objective of the corporate model is to assess the financial and economic viability of an investment proposal
vis-à-vis with the complete business scenario of the firm. Some of the key features of the corporate model are as
below:
1. The entire model is built using annual calculations for simplicity;
2. Units of currency are primarily in VND million;
3. Segregation of input, output and working sections in the model to ease operation and updating;
4. Flexible and robust time and date functions so that the same model can be reused multiple times; and
5. Calculating multiple ratios from view point of investors/ financial institutions/ and regulators.
This note is focused on a providing a complete brief about the financial model which would be useful for the
EVNNPT to operate and subsequently update the financial model. The entire note is divided into three sections,
similar to the financial model i.e. Assumptions/ Input, Working area and Output section.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 224
The standard modus operandi for using financial models is that all users should have the flexibility to update
Assumptions/ Input area and review the Output section but the Working area should be managed only by a
dedicated team from Finance Department.
Feeding in the right input
The financial model has a dedicated input area where the key assumptions pertaining to the firm needs to be
fed in. The input area is marked distinctively with Yellow colour, marking off cells where the inputs should be
fed in. The rest of the section / values in the sheet are primarily either fixed values/ preliminary calculations.
Assumptions
The table below clearly indicates the major assumptions in the financial model and manner in which individual
values should be incorporated.
Reference Description
Input sheet Cell D4
This is the base financial year from which the projections are being calculated. In most scenarios, this will the immediately preceding financial year.
Input sheet Cell D9-14
The closing gross fixed asset in the base financial year as per audited financial statements.
Input sheet Cell D17-22
The cumulative depreciation in the base financial year as per audited financial statements.
Input sheet D25
The CWIP in the base financial year as per audited statements.
Input sheet Line 27
This is the capitalization schedule of the CWIP outstanding in the base financial year.
Input sheet Cell D47 - 48
The break-up of loans outstanding in the base financial year as per the audited statements.
Input sheet Cell D51-52
The assumption for repayment of the outstanding loan (in the base financial year)/ old loans (only)
Input sheet Cell D55-56
The assumption for weighted average interest cost for old loans (outstanding in the base financial year).
Input sheet Cell D61-80
The section is the input for the project cost. Each new project can be input into a fresh line.
Input sheet Cell D84-H103
The break-up of the investments plans (by each project wise) into the asset categories.
Input sheet Cell D106-H125
This section requires the user to input the year wise phasing of each of the project which forms a part of the investment plan.
Input sheet Cell D129-148
This section requires the user to enter the project wise debt assumptions.
Input sheet Cell D153-155
This section requires the user to input the operational assumptions for the firm in terms of energy to be bought/ sold and transmission losses.
Input sheet Cell D159/163/165/168/171
These cells represent various cost elements for the business. In this space, the user has to enter the base data of these costs as on base financial year (as per audited accounts).
Input sheet Cell D184-186
This section contains the tax assumptions.
Input sheet Cell D190-211
These cells represent the balance sheet scenario as per the base financial year. The user has to enter the data as per the accounts and update the model.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 225
Working area
The sheet “Calculations” contains the entire calculations which have been used to generate the specific outputs.
Some of the key elements of the sheet are summarized in the table below:
Reference Description
Calculations Line 06-89
The section represents the complete capital phasing of the investment plan for the company. The investment plan is multiplied with the phasing to generate the fixed asset schedule for the company.
Calculations Line 91-114
This section focuses on the depreciation schedule where each type of asset, its value and depreciation rates are used to prepare the required forecast.
Calculations Line 116-273
This section represents the complete debt schedule for the firm. The debt schedule is divided into three parts - Existing loan in domestic currency, existing loan in foreign currency and future loans.
Calculations Line 275-280
This section focusses on calculating the O&M expenses.
Calculations Line 290-301
This section contains the detailed calculation of taxes.
Calculations Line 359-370
This section calculates the current assets and liabilities using historical trend.
Calculations Line 379-392
This section calculates the transmission pricing in the given scenario.
Decoding the output
Iterations flag
There are certain sections in the model which have iterative calculation which implies that the some values have
circular dependence. In order to remove the circular dependence, we have used a flag concept. In the cell D05 of
the Input Sheet, there is a flag. This flag should be turned on to false and then back to true every time the model
is to be revised/ updated.
Transmission pricing
The lines from D05 to H08 summarize the transmission pricing and details are summarized in the table below:
Reference Description
Key output Line 07
The line indicates the power buying rate
Key output Line 08
The line indicates the quantum of power bought
Key output Line 10
The line indicates the power selling rate
Key output Line 11
The line indicates the quantum of power sold in million units.
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 226
Ratio analysis
Ratio analysis using the forecasted the financial statements, may be used to evaluate various financial, risk and
operating aspects of the firm. The ratio analysis also serves as a decision tool which allows management to
undertake a conscious decision.
The Lines 16 to 33 summarize the key ratios for the firm and each of the ratios indicates a different aspect of the
firms’ business and the table below shall help deciphering the ratios:
Ratio Description
Debt to equity ratio
This is the standard leverage ratio to indicate how much the firm is levered. A high leverage is generally good for the firm since it indicates lower business risk for the equity holders and improved equity cash flows. However too high leverage also increases the financing risk for the firm and the firm may not be able to sustain the debt service requirements.
DSCR (Debt Service Coverage Ratio)
This ratio is defined as the ratio of Net Income to the total debt service requirements (i.e. repayment + interest). The DSCR is an important ratio which is evaluated by the banks/ lenders of the firm and typical DSCR requirements is over 1.2 (however it may vary depending on the bank/ financial institution).
Interest coverage ratio (ICR)
This ratio is defined as the ratio of Net Income to the total interest payments. The Interest coverage is also an important ratio which is evaluated by the banks/ lenders of the firm. The ICR is used to see if the firm is able to meet the interest on loans.
Current ratio The current ratio is a measure of the liquidity of the firm. It is used to assess if the firm generates enough cash to meet its short term obligations. Typically a current ratio of over 1.5 is acceptable. A current ratio of less than 1 indicates that the company may likely enter to a cash strap scenario in future.
Acid test Similar to the current ratio, acid test is also a measure to assess the liquidity scenario of the firm without considering the inventory (since a company typically cannot sell its inventory to generate cash). An acid test of less than 1 indicates that the company may likely enter to a cash strap scenario in future.
Days of receivables
The approximate time it takes for the firm to receive the payments from its customers.
Asset turnover Asset turnover depicts how profitably the assets are employed in the business. Typically in case of capital intensive industry such as power transmission asset turnover is lower compared to a low capital intensive industry such as retail/ electricity distribution.
Degree of operating leverage (DOL)
DOL is a type of leverage ratio summarizing the effect of operating leverage on a company's earnings before interest and taxes (EBIT). Operating leverage involves using a large proportion of fixed costs to variable costs in the operations of the firm. The higher the degree of operating leverage, the more volatile the EBIT figure will be relative to a given change in sales (amount of power received and sold), all other things remaining the same. In a transmission business typically the degree of operating leverage is very low.
Days of payables The approximate time it takes for the firm to pay the payments it owes to its suppliers.
Returns
The returns which are the final set of output parameters are the most important ones in any appraisal process.
The key ratios are summarized in the table below:
Parameter Description
Recommendation#5: Develop and implement (i) project financial models to assist in appraisal of investment projects and (ii) corporate level model to assist in fund identification along with necessary operating booklet for the use of financial model
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 227
Parameter Description
NPV to the firm The NPV to the firm is the value the firm will generate considering an opportunity cost equal to the WACC of the firm. The business is said to be feasible for equity and debt holders only if the NPV to the firm is greater than 0.
NPV to the equity holders
The NPV to the equity holders is the value the firm will generate for equity investors considering an opportunity cost equal to the cost of equity for the firm. (In this case we have used ROE as a substitute for Cost of Equity). The business is said to be feasible for equity holders only if the NPV to the equity holders is greater than 0.
The primary use of the corporate model is for visualizing the cash flow scenario of the company under various
debt scenarios for a particular year. The model can also be used to assess if the firm would be able to service the
debt obligations. Both project model and corporate model are complementary and should be used in tandem for
decision making. The models are also designed to provide insight into the cost and pricing structure.
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 228
Recommendation#6: Develop alternate modes of project funding
Background
As per the National Master Plan for power development in Vietnam for the year 2011-2020 period with the
vision to 2030, there will be a huge investment requirement for EVNNPT. The total physical investment plan
envisaged according to the Master Plan is shown in the table below:
Item Unit 2011 - 2015 2016 - 2020 2021 - 2025 2026 - 2030
500 kV substations MVA 17,100 26,750 24,400 20,400
220 kV substations MVA 35,863 39,063 42,775 53,250
500 kV lines Km 3,833 4,539 2,234 2,724
220 kV lines Km 10,637 5,305 5,552 5,020 Source: Master Plan VII (for 2011-2020 and with a vision 2030)
The total investment in the grid will be 210.4 trillion VND during the period 2011 - 2020 and 494 trillion during
the period the 2021 - 2030.
NPT is largely dependent on the long term loans from ODAs (ADB, World Bank, etc.) and other International
Banks (e.g. Citibank, BNP Paribas) to fund their capital investment requirement. Based on our study, it seems
that EVNNPT is facing challenges to arrange the equity portion to fund its capital expenditure requirement due
to the following reasons:
1. No equity infusion by the equity shareholders; and
2. No adequate return on equity is allowed in the tariff order to generate retained earning which can be
used for self-financing.
In the given situation, EVNNPT is forced to utilize the surplus depreciation fund to finance its equity
contribution for capital expenditure. The depreciation period allowed by the Regulator is lower than the loan
repayment period. This provides some surplus cash to EVNNPT to invest into the capital projects. However,
such a practice may deteriorate the financial position of EVNNPT in long run. It is against the basic finance
principles. It may lead to debt trap situation in future.
Considering the above facts, EVNNPT is required to evaluate alternative modes of financing to fund the equity
portion to finance the huge capital investment requirement. The purpose of the concept note is to discuss the
various equity financing options available with EVNNPT along with their benefits and implementation
challenges.
Alternate modes of financing
The alternative modes of equity financing available with EVNNPT to fund the capital investment requirement
are as follows:
1. Raising fresh equity from capital markets to fund its investment;
2. Lease financing; and
3. Public private partnership.
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 229
Raising fresh equity from capital markets to fund its investment
The capital projects are generally financed by debt and equity. The equity portion comes from retained earnings
or fresh infusion of equity. In case of EVNNPT, it is not allowed to recover any return on its equity therefore
there are no retained earnings available with EVNNPT. It has also been observed that no equity is being infused
from the shareholders or from the government. In the given scenario, an alternative option may be raising fresh
equity from capital markets. The pre-requisite for raising fresh equity from capital markets is that the company
should be listed in the stock exchange.
Benefits associated with the option
It will reduce the burden from the government budget and will help EVNNPT to meet the huge capital
investment requirements.
Experience of other countries
Australia: Many of the transmission networks in Australia are owned by public listed entities, the shares of
which are traded in the financial markets.
Spain: The electricity transmission sector in Spain is monopolized by Red Eléctrica de España (REE), a public-
listed company, which is the sole transmission agent and operator of the Spanish electricity system. The Red
Eléctrica de España is a public listed company which owns all the transmission assets. The shares of the
company have been quoted in the four Spanish Stock Exchange Markets since 7 July 1999.
India: The Central Transmission Utility in India, i.e., POWERGRID is a public listed company with National
Stock Exchange (NSE) and Bombay Stock Exchange (BSE) in India. The shares are traded in the capital
markets.
Implementation challenges
The option of raising fresh equity from the capital markets might not be feasible for EVNNPT because of the
following reasons:
1. NPT is a 100% government subsidiary company therefore the listing of shares in the stock exchange for
EVNNPT will not possible in the existing framework. The disinvestment of equity by the government
might not be feasible in Vietnam;
2. Tapping the capital market is feasible only for those companies which have achieved significant scale of
operations and have profitable operations. There should be a proven good financial track record for the
company to raise equity from the capital market. EVNNPT is a loss making company. It will be difficult
for EVNNPT to attract the investors; and
3. As EVNNPT is not allowed to recover any return on equity from the consumers; hence it will not be able
to distribute any dividend to its shareholders.
Considering the above-mentioned facts, it can be concluded that the option of raising fresh equity from capital
markets to fund its investment might not feasible in Vietnam.
Lease financing
The lease financing can be another mode of financing for setting up a transmission asset. Under a lease, the
developer (lessee) typically leases the fixed assets with an explicit intent to eventually own it and makes
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 230
periodic payment to the lessor in lieu of using the fixed assets. At the end of the term of the lease, the developer
has a buyout option usually at a - bargain purchase price that is fixed in advance at the time the lease is
established. In other words, the lessee pays for essentially the full cost of fixed assets over the lease period,
based on the intent to own the assets.
Experience of other countries
The lease financing has been used by few state owned power companies in India to finance their fixed assets.
Benefits associated with the option
The lease financing is advantageous in the following manners:
1. The developer can finance 100% of the equipment using lease financing, which is not possible in case of
bank financing;
2. Lease financing can also be made available for long term such as 20 years, whereas it is almost
impossible to get loan from local banks for such a long tenure;
3. Assets and capital equipment can be paid from the revenue earned;
4. Rates can be as competitive, or even better, as compared to bank funding rates because of the security
provided by the asset;
5. During recession, leasing is particularly well positioned to help businesses when most have low taxable
profits; and
6. Depending on the situation, companies may benefit from tax advantages.
Implementation challenges
The lease financing option might not be feasible for EVNNPT because of the following reasons:
1. The depreciation can be generally allowed to the lessor. The benefit of depreciation will not be available
to the EVNNPT. As mentioned above, the EVNNPT is largely dependent on the surplus depreciation
fund to finance its equity contribution in capital expenditure. It will be very difficult to fund its capital
investment requirements other than those funded by lease financing;
2. There is no certainty regarding the allowance of the lease charges from the Regulator as a part of the
transmission charges;
3. There might be additional expenses such as indirect taxes associated with the lease payment; and
4. There must be a market for lease financing in Vietnam. Considering the poor financial position of
EVNNPT, the bank may hesitate to offer the lease financing options to EVNNPT.
The EVNNPT may evaluate the lease financing option subject to the offers available to EVNNPT by local or
international banks in Vietnam.
Public private partnership (PPP)
In a public private partnership (PPP), a venture of government service and private business is funded and
operated by a partnership of government and one or more private sector companies. Generally in a PPP, the
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 231
public partner is (not necessarily) expected to take care of the government clearances and land acquisition and
the private partner is expected to bring with them the technical expertise and financing sources for the
development of the asset.
As per the Asian Development Bank, “the term “Public Private Partnership” describes a range of possible
relationships among public and private entities in the context of infrastructure and other services (Public
Private Partnership Handbook, ADB),”
A company like EVNNPT, which is facing constraints on investment and other resources, should recognize the
importance of private participation in investment in infrastructure to help them meeting their investment
requirements. Globally, governments are increasingly turning to the private sector as an alternative additional
source of funding to meet the funding gap.
Benefits associated with the option
The benefits associated with the option are discussed below:
1. It will supplement limited resources and capacities of EVNNPT to meet the huge capital investment
requirement;
2. It will help EVNNPT to bring in private sector technology and innovation which will enable EVNNPT to
provide better public services through improved operational efficiency;
3. It can a win-win scenario for both EVNNPT and private sector by:
a. Providing incentive to the private sector to deliver projects on time and within budgets, and
b. Imposing budgetary certainty on EVNNPT by setting present and the future costs of
transmission projects over time
4. It will assist EVNNPT in extracting long-term value-for-money through appropriate risk transfer to the
private sector over the life of the project - from design/ construction to operations/ maintenance
5. It will help in developing local private sector capabilities through joint ownership with large
international firms, as well as sub-contracting opportunities for local firms in areas such as civil works,
electrical works, facilities management, security services, cleaning services, maintenance services, etc.,
and
6. It will provide support to economy of the country by creating more infrastructure base as well as giving
a boost to its business and industry associated with infrastructure development (such as construction,
equipment, support services, etc.) at competitive costs.
Various options under PPP
There are many variants of PPP structure which have been used by different agencies around the world and can
vary from simple management/operating contracts to full divestments. These PPP models primarily differ on
four key characteristics:
1. Ownership of project asset;
2. Responsibility of capital investment;
3. Duration of the contract/concession; and
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 232
4. Assumption and involvement of risks.
Based on the above parameters, there can be following PPP models:
1. Service contracts;
2. Asset transfer models;
3. Perpetual ownership of the assets; and
4. Joint Ventures.
Service contracts
Under this PPP model, i.e., service contracts, the government (public authority) hires a private company or
entity to carry out one or more specified tasks or services for a stipulated period of time. The public entity still
remains the primary provider of the infrastructure service and contracts out only portions of its operation to the
private partner. The private partner is bound to perform the service at the mutually agreed cost wherein it has
to meet performance standards set by the public sector. In several cases, the responsibility to incur capital
expenditure is also assigned to the private players.
Under the service contract, the government pays the private partner a predetermined fee for the service, which
may be based on a one-time fee, unit cost, or other basis. In order to increase contractor’s profit there is a need
to reduce operating costs and increase operational efficiency, while meeting required service standards.
The Governments generally use competitive bidding procedures to award service contracts, which tend to work
well given the limited period and narrowly defined nature of these contracts.
The associated strengths and weakness of this PPP structure has been presented below:
Strengths Weakness
Performance can be monitored easily These contracts don’t provide ownership right to the private parties, hence the private parties face problem to raise finance to incur capital expenditure (if required under the service contract). It reduces the effectiveness of contractor may be compromised
Brings substantial impact on the system operation and improves efficiency
The private party is to be selected through competitive bidding procedures. There must be sufficient bidders available in the market to compete for the bid otherwise the basic purpose will be defeated. The contract values are generally low in service contracts, there only local players will participate in the bidding.
Serves as an instrument for technology transfer and managerial capacity
Asset transfer models
This PPP model is also known as concessional contract model. In this model, the private party (also called
concessionaire) undertakes the capital investments and operates the facility for a fixed period of time (also
called concession period) after which the ownership of the assets reverts back to the public sector.
Under this PPP model, the private entity brings the capital required to build the new facility/ assets. The private
operator owns the assets for a period set by concessional contract. The period should be sufficient to allow the
private player to recover investment costs through user charges. The public sector entity agrees to purchase the
output produced by the facility. At the end of the contract, the public sector entity assumes the ownership of the
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 233
facility/ assets. The public sector entity can also opt to contract the operation responsibility to the private party,
or award a new contract to a new private party post the end of the contract.
There can be different types under this PPP model:
1. Build Operate Transfer (BOT): It is a form of project financing, wherein a private entity receives a
concession from the public sector entity to finance, design, construct, and operate a facility stated in the
concession contract. Due to the long-term nature of the arrangement, the costs are usually recovered
during the concession period;
2. Build Own Operate Transfer (BOOT): A BOOT structure differs from BOT in that the private
party owns the works till the end of the concession period. During the concession period the private
company owns and operates the facility with the prime goal to recover the costs of investment and
maintenance while complying with the operation standards. The specific characteristics of BOOT make
it suitable for infrastructure projects like highways, roads mass transit, railway transport and power
projects and as such they have political importance for the social welfare but are not attractive for other
types of private investments;
3. Build Rent Operate Transfer (BROT) or Build Lease Operate Transfer (BLOT): The Build
Rent Operate Transfer (BROT) or Build Lease Operate Transfer (BLOT) is a public-private partnership
(PPP) project model in which a private party designs, finances and builds a facility and lease/ rent the
facility to the public sector entity. The private party operates the facility for the duration of the lease
and then transfers ownership to the public sector entity; and
4. Design-Build-Finance-Operate-Transfer (DBFOT): The Design-Build-Finance-Operate-
Transfer is a project delivery method very similar to BOOT. The private party assumes the risk of
design, construction and financing till the end of the contract period. It also assumes the responsibility
for maintenance and operation and transfer the facility or asset to the public sector entity at the end of
the contract period. This model is extensively used in specific infrastructure projects such as toll roads
and power sector.
The associated strengths and weakness of this PPP structure has been presented below:
Strengths Weakness
Effective way to attract private finance required to fund new construction or rehabilitate existing facilities
Concession contracts are complex in nature
Provides incentives to the operator to achieve improved levels of efficiency
Concessions provide only limited competition given the limited number of qualified operators for a major infrastructure network
Transfer of the full package of operating and financing responsibilities enables the concessionaire to prioritize and innovate
These contracts don’t provide ownership right to the private parties, hence the private parties face problem to raise finance to incur capital expenditure. It reduces the effectiveness of contractor may be compromised
It can supplement limited resources and capacities of public sector entities. It helps to bring in private sector technology and innovation which will enable public sector entity to provide better public services through improved operational efficiency
Non completion of the project within the stipulated timelines would result in creation of stranded infrastructure. It happened in India
The responsibility and risk are shared between the private party and public sector entity. The responsibility
sharing matrix is given below:
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 234
Responsibilities Private party Public sector entity
Design and engineering The private party bears the entire responsibility of design and engineering.
Fund raising The entire responsibility of fund raising and optimal capital structure rests with the private party
The public sector entity provides the necessary support to private party to achieve the financial closure.
Project development The entire project development risks are borne by the private party
The public sector entity provides the support to private party in respect of achieving the statutory clearances and land acquisition
Operations The operations and operations related risks are also primarily borne by the private party. However concessions may be granted for certain events related to third party performance.
Public sector entity though does not carry any risk during this stages but do carries the responsibility of third party monitoring of activities
Off-take risks The public sector entity will be liable to purchase the services produced by the private player from the facility
Transfer of assets Public Entity has explicit and implicit contingent liabilities that may arise due to loan guarantees, default of a sub-sovereign loan or acquisition of the asset at a terminal value post expiration of the contract/concession.
Perpetual ownership of the assets
In this PPP model, the private sector remains responsible for design, construction and operation of an
infrastructure facility. In this model, the private sector builds, owns and operates a facility, and sells the
product/service to its users or beneficiaries- essentially the public entity. This is the most common form of
private participation in the power sector in many countries.
The public sector’s main advantages lie in the relief from bearing the costs of design and construction, the
transfer of certain risks to the private sector and the promise of better project design, construction and
operation.
There can be three main types under this form:
1. Build-Own-Operate type of arrangements (Build Own Operate, Build Own Operate
Maintain and Design Build Finance Own Operate, etc.): it is a public-private partnership (PPP)
model in which a private party builds, owns and operates some facility or structure, the output of which
is being sold to public sector entity. Although the government doesn't provide direct funding in this
model, it may offer other financial incentives such as tax-exempt status. The developer owns and
operates the facility independently. In a BOO/ BOOM, DBFOO project ownership of the project
remains usually with the private party. Therefore the private party gets the benefits of any residual
value of the project. This framework is used when the physical life of the project coincides with the
concession period;
2. Private Finance Initiative (a more recent innovation): The private finance initiative (PFI) is a
way of creating "public-private partnerships" (PPPs) by funding public infrastructure projects with
private capital. It has been developed initially by the governments of Australia and the United
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 235
Kingdom, and used extensively there and in Spain. PFI can be used simply to place a great amount of
debt 'off-balance-sheet'. The key features of this PPP model are as follows:
a. In this model, a public sector entity signs a contract with a private sector consortium,
technically known as a Special Purpose Vehicle (SPV). This consortium is typically formed for
the specific purpose of providing the PFI. It is owned by a number of private sector investors,
usually including a construction company and a service provider, and often a bank as well;
b. PFI contracts are typically for 25-30 years (depending on the type of project); although
contracts less than 20 years or more than 40 years exist, they are considerably less common.
During the period of the contract the consortium (of the private parties) will provide certain
services, which were previously provided by the public sector;
c. The consortium is paid for the work over the course of the contract on a "no service no fee"
performance basis;
d. The public authority will design an "output specification" which is a document setting out what
the consortium is expected to achieve. If the consortium fails to meet any of the agreed
standards it should lose an element of its payment until standards improve. If standards do not
improve after an agreed period, the public sector authority is usually entitled to terminate the
contract, compensate the consortium where appropriate, and take ownership of the project;
and
e. Termination procedures are highly complex, as most projects are not able to secure private
financing without assurances that the debt financing of the project will be repaid in the case of
termination. In most termination cases the public sector entity is required to repay the debt
and take ownership of the project. In practice, termination is considered a last resort only.
3. Divestiture by license or sale: In this PPP model, the ownership of the facility/ assets is transferred
with the private developer. The private player is provided with the authorisation or license to build,
own and construct the facility/ assets. The ownership of the facility may be 100% or 51% with private
parties depending on the nature of divestment scheme. The public sector entity will not have any
control over the assets. It is more common in Indian power distribution sector. However, it has not
been very successful in power transmission sector. In Nigeria, the divestment happened for all the
public sector entities operating in generation and distribution sector but not for the transmission
sector.
The associated strengths and weakness of the PPP structure has been presented below:
Strengths Weakness
Effective way to attract private entity Default in payment to the private entity would result in uncertain revenues for the project
Provides incentives to the operator to achieve improved levels of efficiency
The private player will face implementation problems in respect of getting statutory clearances and land acquisition
It can supplement limited resources and capacities of public sector entities. It helps to bring in private sector technology and innovation
The responsibility and risk are shared between the private party and public sector entity. The responsibility
sharing matrix is given below:
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 236
Responsibilities Private party Public sector entity
Design and engineering The private party bears the entire responsibility of design and engineering.
Fund raising The responsibility of actual fund raising and optimal capital structure rests with the private party
Project development The entire project development risks are borne by the private party
.
Operations The operations and operations related risks are primarily borne by the private party. However concessions may be granted for certain events related to third party performance.
Off-take risks The off-take risks are mostly shared by both private party and public sector entity depending on the arrangement, otherwise the public sector entity should purchase the service or output produced by the facility or assets.
Joint Ventures
Joint ventures serves as an alternatives to full privatization in which the facility/ asset is co-owned and
operated by the public sector entity and private operators.
In joint venture arrangement, the responsibilities to build and finance the facility/ asset are with the private
party and responsibilities in respect of operations are shared between the public sector entity and private party.
The main responsibility assigned to the public sector entity is to getting statutory clearances and land
acquisitions. Depending on the JV agreement, the public sector entity might require to bring the equity portion
to the extent of its share in the joint venture. The selection of JV partner is done through the competitive bid
process.
Under a joint venture there are two options for contribution of the public and private entity-the public and
private sector partners can either form a new company or assume joint ownership of an existing company
through a sale of shares to one or several private investors.
The associated strengths and weakness of the PPP structure has been presented below:
Strengths Weakness
Real partnerships of the public and private sectors that match the advantages of the private sector with the social concerns and local knowledge of the public sector.
Government’s dual roles as owner and regulator can lead to conflict of interest.
There is always an effort towards increasing the efficiency as the stakes of both government and private entity is involved
Joint ventures also have a tendency to be directly negotiated or to follow a less formal procurement
Experience of other countries
The PPP experiences in other countries are discussed below:
India
Transmission sector in India has been primarily considered as a regulated business. Private sector involvement
in transmission sector of India began with Ministry of Power putting in place a framework for promoting
private sector participation, allowing private players to develop transmission infrastructure though a Joint
venture route and under a tariff based competitive bidding framework.
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 237
In 2006, Ministry of Power came out with a set of guidelines to promote private sector participation and
selection of developers under a competitive bidding framework and notified a set of standard bidding
documents in 2008 for tariff based competitive bidding to ensure transparency and level playing field among all
interested bidders.
A numbers of transmission project have been awarded to private players under the PPP framework in India.
The various PPP models operational in India are as follow:
1. Joint Venture route: In Joint venture route, the models currently adopted in India successfully
entail 26% of the equity investment in the project to be by the public sector company, while the balance
74% is brought in by the JV partner- private party. Joint Venture route has been successfully tried by
the Central Transmission Utility (POWERGRID) for 5 projects and one state transmission utility for 4
projects till date. Post January, 2012 this route is no more available and is completely replaced by the
competitive bidding routes described in succeeding paras.
2. Independent Power Transmission Company (IPTC) or tariff based competitive bidding
route or BOOM route: The IPTC route is based on the guidelines issued by Ministry of Power. The
project is identified by the selection committee (comprises of Central Electricity Authority- a
government appointed authority and Central Transmission Utility- POWERGRID) to be implemented
through this route. The private party is selected through an international bid process under a tariff
based competitive bidding framework. The project is awarded on a build own operate maintain
(BOOM) basis to the bidder selected through a tariff based competitive selection basis, with bidders
quoting for the transmission charges that they would charge for the Project. This framework has
successfully adopted for 16 inter-state transmission projects till date with close to 9 projects on the
anvil. Additionally, many States have also adopted this IPTC model for inter-state transmission
projects. Some of the early projects were marked with highly aggressive bidding by new entrants, which
have now been rationalized.
3. Viability Gap Funding (VGF) or BOOT route: The VGF route is based on the asset transfer model
of PPP. In this route, the state comes out with an upfront annual annuity for the project, while the
selection of the private developer is based on the amount of additional premium (viability gap, to be
provided to the private developer from the state) or concession (in case the annuity set upfront by the
procurer is more than the required, there might be reimbursements to the developer for implementing
the project). Till date, two projects have been awarded by State Transmission Utilities, while many
other states are currently in the process of selecting developers based on this framework. This route
takes a long lead time for securing pre-bidding approvals from Government of India and commitment
of funds for viability gap funding. Industry participants too exhibit lesser enthusiasm in this route.
Chile
Chile has a successful history of PPPs. The Chile’s electricity sector is organised around four distinct electrical
systems. Out of the four, the two more prominent ones are SIC (Sistema Interconectado Central) and SING
(Sistema Interconectado Norte Grande), which together constitute ~99% of the country’s demand. The
transmission ownership in the SIC region is dominated by TRANSELEC (which manages ~50% of the region’s
transmission capacity), while in the SING region, the transmission ownership is distributed among numerous
owners (each controlling between 10-20% of the capacity, adding up to 75% of the total regional capacity).
All assets in the sector are 100% privately owned in the country, with large scale privatisation starting in the
1980s. The transmission companies’ assets were constructed through concessions granted by the Chilean
government. The Chilean Electricity Law requires such companies to operate their assets on an open access
basis.
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 238
Philippines
The government of Philippines has been promoting private investment in public projects in sectors like power,
transport, infrastructure etc. The Philippine BOT Law (Republic Act No. 7718) and its Implementing Rules &
Regulation provides tax exemptions and other benefits to the private companies contributing to the
development of the country. The country has seen PPP initiatives worth USD 19.5 billion.
In the transmission sector, the National Transmission Corporation (TransCo) is a government agency created
under Republic Act No. 9136, otherwise known as the Electric Power Industry Reform Act (EPIRA) of 2001.
Since March 1, 2003, TransCo operated and managed the power transmission system that links power plants to
the electric distribution utilities nationwide. The law mandated the privatization of TransCo through an
outright sale or management concession agreement.
Following a public bidding conducted in December 2007, the TransCo concession was awarded to the National
Grid Corporation of the Philippines (NGCP), which eventually secured a congressional franchise to operate the
transmission network through Republic Act No. 9511.
On January 15, 2009, the TransCo turned over the management and operation of its nationwide transmission
system to NGCP. The ownership of all transmission assets remains with TransCo. The NGCP operating under a
50-year franchisee has the right to operate, maintain, expand and further strengthen the country’s power
transmission system.
Brazil
More than 50% of the transmission infrastructure in Brazil is owned by Eletrobras Group (a mixed capital
company, which has the Federal Government as the largest investor).
Till 1999, Brazil had two independent sub-systems, viz., the South-Southeast-Center West and the North-
Northeast. These are now inter-connected, allowing for continuous and permanent exchange of energy between
the regions and which provides more flexible, secure and economic operation of the National Interconnected
System (Sistema Interligado Nacional, SIN).
Under the new electric model in the country, a private agency, viz., the National System Operator (Operador
Nacional do Sistema Elétrico - ONS), is responsible for the supervision of this National Interconnected System.
In 1999, ANEEL (Brazilian Electricity Regulatory Authority) started offering transmission concessions
(comprising transmission lines & substations) through public auctions. ANEEL runs these auction processes on
an international competitive basis, in which public / private, national / international, and individual firms /
consortium participate. The Concessionaire is selected on the basis of lowest annual revenue bid over a
concession period of 30 years (based on revenue cap regulation).
Implementation challenges
The implementation challenges for a PPP option are mentioned below:
1. In some cases, the development, bidding and ongoing costs in PPP projects are likely to be greater than
for traditional government procurement processes. In such cases, the government should assess
whether the greater costs involved are justified. There should be methods in place for analysing these
costs and looking at value for money;
2. In PPP framework, some projects may be easier to finance than others. If there is proven technology
involved and/ or the extent of the private sectors obligations and liability is clearly identifiable, the
financing under PPP framework will be smooth;
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 239
3. Finding a balance between the public and the private interest: In a public Private partnership, conflicts
of interest can arise due to the fact that the basic motive of both the parties to enter into the partnership
is different. The private partner is profit centric and the public partner is customer centric. In such
cases it is very important that the contracts are comprehensive and have taken into account the interest
of both the parties;
4. Allocations of risks and responsibilities: The PPP contracts should clearly distinguish the rights and
obligations of the private party and public sector entities. There should be clear demarcation of the
risks and responsibilities between the private and public sector entity;
5. Maintaining transparency during the procurement process: This is the most common challenge rising
in a PPP framework. The private parties will participate in the process only if the process carried out by
the public sector entity to select the bidder is transparent and genuine; and
6. Establishing the policy landscape enabling PPP: The pre-requisite for implementing a PPP framework
is that there should be appropriate policy landscape to support the PPP initiatives. Establishing PPP
framework in a country where there is no supporting policy landscape will be very challenging.
Implementation road map
It is pertinent to mention that there is a policy framework in Vietnam for implementation of PPP framework.
The decree no 108/ 2009/ ND-CP dated 27 Nov 2009 provides for investment domains, conditions, order,
procedures and incentives; and rights and obligations of parties in respect of the projects to be implemented
under the PPP framework such as build-operate-transfer, build-transfer-operate and build-transfer contracts.
The investment domains covered under the decree also include the power plants and power transmission lines.
The decree recognises the following three PPP models:
1. Build-operate-transfer (BOT) contract- It means a contract signed between a competent state agency
and an investor to build and operate an infrastructure facility in a specified duration. Upon the
expiration of this duration, the investor shall transfer without compensation such facility to the
Vietnamese State.
2. Build-transfer-operate (BTO) contract- It means a contract signed between a competent state agency
and an investor to build an infrastructure facility. After completely building this infrastructure facility,
the investor shall transfer it to the Vietnamese State. The Government will grant the investor the right
to operate that facility for a specified duration to recover investment capital and earn profits.
3. Build-transfer (BT) contract- It means a contract signed between a competent state agency and an
investor to build an infrastructure facility. After completely building this infrastructure facility, the
investor shall transfer it to the Vietnamese State. The Government will create conditions for the
investor to implement other projects for recovering investment capital and earning profits or shall
make payments to the investor as agreed in the BT contract.
The decree covers the following:
1. State agencies competent to sign and perform project contracts;
2. Raising of capital sources for project implementation by the investors or project enterprises;
3. Use of state capital for project implementation;
4. Setting up Inter-branch working parties to assist in project negotiation and implementation;
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 240
5. Drawing up and announcement of lists of projects to be implemented through the PPP framework;
6. Selection of investors for negotiating project contracts and signing of project contracts and related
contracts;
7. Contents of a project contract- transfer of rights and obligations under project contracts, modification
and supplementation of project contracts, term of a project contract, termination of project contracts,
application of foreign laws governing project contracts and related contracts, Security for the project
contract performance obligation, etc.;
8. Procedures for granting investment certificates and implementing projects;
9. Transfer of project works including general regulations on transfer of project works, finalization and
transfer of BOT works, and transfer of BT and BTO works;
10. Investment incentives and supports for investors and project enterprises; and
11. Tasks and powers of the various stakeholders.
The decree provides for the broad guiding parameters for investment/ project to be implemented through BOT,
BTO and BT in various sectors such as roads, road bridges, road tunnels and ferry landings; railways, railway
bridges and railway tunnels; airports, seaports and river ports; clean water supply systems; water drainage
systems; and wastewater and waste collection and treatment systems; power plants and power transmission
lines; other infrastructure facilities as decided by the Prime Minister.
Based on these broad guiding parameters, a specific standard bidding guidelines (covering the bidding
framework) and standard bidding documents (comprising of request for qualifications, request for proposals,
contracts, etc.) should be prepared for power sector in Vietnam. Most of the implementation challenges
mentioned above can be mitigated if the proposed standard bidding guidelines provide for the following:
1. Transparent bidding framework including the basis of bidding such as whether it will be competitive
tariff based bidding or viability gap funding basis or technical/ financial strength basis;
2. A robust mechanism of selection of projects to be executed through the PPP mode. There should be a
cost-benefit analysis to be carried out before proposing the project for implementation through PPP
mode;
3. An obligation for the public sector entity to support the private players in getting the statutory
clearances, achieving the financial closure and acquisition of land;
4. A balance between the interest of public sector entity and the private player. It should focus on
incentives based on performance or out-put to the private parties; and
5. An appropriately balanced risk and return framework for public sector entity and private party.
Considering the above-mentioned facts, it is recommended that the EVNNPT should evaluate the PPP option
for implementing its capital projects. It will supplement the limited resource requirement and limited capacities
of EVNNPT to meet the huge capital investment requirement. It will help EVNNPT to bring in private sector
technology and innovation which will enable EVNNPT to provide better public services through improved
operational efficiency.
As the guiding framework is already in place in Vietnam, it will be very smooth for EVNNPT to implement its
capital projects under the PPP framework. However, it will require a specific standard bidding guidelines and
Recommendation#6: Develop alternate modes of project funding
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 241
bidding documents for the power sector. The Ministry of Industry & Trade should develop a power sector
specific standard bidding guidelines and standard bidding documents.
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 242
Recommendation#7: Process improvement in the investment planning process
Overview
NPT has been set up as a company to develop, operate and maintain the transmission infrastructure in
Vietnam. The efficiency of transmission companies around the world is governed by their ability to effectively
plan and develop the infrastructure within a time schedule. The focus of EVNNPT should be on the following
parameters:
1. Effective investment planning;
2. Efficient approval process; and
3. Timely implementation and execution of capital projects.
Our concept note focusses on enhancement of effective and efficient investment planning and approval process
in EVNNPT. The investment planning process can be defined as the process of identification of capital projects,
designing the project structure, securing investment approval and tie up resources (importantly financial
resources). The investment planning process is a crucial activity in a capital intensive industry such as power
transmission. The financial and human resource available would be limited and hence a transparent investment
planning process ensures selection of viable, critical and priority projects.
Existing practice
The investment planning process in EVNNPT can be divided into three stages:
1. Planning stage;
2. Approval stage; and
3. Funds identification and tie-up stage.
The concept note only focusses on the planning and approval stage. The fund identification and tie up (not
covered under this concept note) requires strategic changes rather than process changes. These strategic
changes are discussed in “Concept note on alternative modes of financing.”
Planning stage
At this stage, the transmission projects are identified and a first level approval is secured before the projects are
included as a part of the long term transmission plan. The planning stage comprises of five levels of investment
plans. The five plans (in terms of hierarchy of planning) are discussed below:
1. Master Plan: The planning stage begins with ten year sector plan known as “Master Plan. It is
prepared by Institute of Energy (IE) and Directorate Generate of Energy (DGE) - both entities
subordinated to MoIT. The Master Plan prepared by IE & DGE is reviewed by MoIT. The MoIT submits
the draft Master Plan to Prime Master for approval. It is finally approved by Prime Minister. The
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 243
IE and DGE hold workshops to take inputs and discuss the master plan with various stakeholders
including EVNNPT.
2. Five year transmission plan: The five year transmission plan is a part of the five year business plan
for EVN (which is the holding company for EVNNPT and also manages power generation and
distribution). This five year plan is for the entire EVN. It also covers the five year plan for the
transmission sector prepared by EVNNPT and generation plan prepared by the generation corporations
and a high level plan for power distribution. It is approved by MoIT.
3. Five year rolling transmission plan: The above-mentioned five year plan will not change for the
next 5 years but a five year rolling transmission investment plan is prepared by EVNNPT every year.
The five year rolling transmission investment plan is a grid investment plan with a view to the next four
years - the current year with four year perspective. This is to support the MoIT for monitoring of grid.
It is approved by MoIT.
4. Annual implementation plan: Apart from the five year rolling transmission investment plan, the
EVNNPT also prepares an annual implementation plan. The five year rolling transmission investment
plan is based on 10 years master plan, whereas the Annual Implementation Plan based on the capacity
of the subsidiaries and departments. The annual implementation plan does not go to MoIT for
approval. It is approved by the EVN.
The process for planning of an individual project will depend on the fact that whether the project is included in
the Annual Implementation Plan or not. The
processes under each case are briefed below:
1. Projects not included in Annual
Implementation Plan: The critical
projects related to system
strengthening and augmentation to the
existing network to address network
overloading/ congestion issues/
voltage problems/ system inadequacy
are projects not included in the Annual
Implementation Plan. These projects
are identified on need basis by PTCs
who are responsible for operations of
transmission infrastructure. The
summary of the process is given in the
adjacent exhibit. Each such project
requires an approval from MoIT,
which is known as “first stage
approval”.
2. Projects included in the Annual
Implementation Plan: The projects
included in the Annual
Implementation Plan are related to
long term planned investments to
evacuate power from upcoming power
generation capacities, system
strengthening to cater to growing
NPT
PTC
[Identification of proposed investment and
preparation of Investment Proposal and
submission to IMD (NPT)
IMD
[Validation and review of Investment
Proposal by IMD based on inputs from
Technical Department]
President & CEO (NPT)
[Approval of Investment Proposal]
Management Board (NPT)
[Approval of Investment Proposal]
VP (Operations & Investments)
[Approval of Investment Proposal]
MOIT
[Approval of Investment Proposal]
3 levels of
approval
within
EVNNPT
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 244
demand and network improvements to enhance quality and reliability of the supply. These projects
should not go to MoIT for approval as these projects are already part of Annual Implementation Plan.
However, each of the projects goes to MoIT for approval as a part of existing practice.
At present, the first stage approval of the proposed investment is required for each project irrespective of the
size and nature of the project.
Approval stage
There are broadly three levels of approvals (not including the approval for fund identification and tie up), which
are summarized below:
First stage approval - Reviewed by MoIT
The first stage approval of the proposed investment is required for each project irrespective of the size and
nature of the project. As mentioned above, the first stage approval is also required for the projects which are
included in the annual implementation plan.
Approval of feasibility study- Reviewed by MoIT for the projects more than 1500 billion VND
The FS is prepared by the PMBs/ PTCs and submitted to the IMD in EVNNPT for review. The IMD will review
the FS with inputs from a variety of departments in EVNNPT such as CPD, Technical department, safety
department, IT department and F&A department. The FS comprises of the technical studies, impact assessment
studies and financial and economic analysis. After the review, the FS is submitted to President & CEO and
Management Board for review and approval. In case the project cost is more than 1,500 billion VND or the
project is to be funded by the ODAs, the approval of MoIT will be required
Approval of detailed technical design
Once the FS is approved by MoIT/ Management Board (NPT)/ President & CEO (NPT), as the case may be, the
detailed technical design (DTD) is prepared by an external consultant (typically could be same consultant
involved in preparation of feasibility study).
The DTD is prepared with the inputs from all the relevant departments of PMB and is submitted to IMD for the
seeking approval from competent authority. The DTD is submitted to the President & CEO and Management
Board for review and further submission to MoIT for the approval. The MoIT review the DTD through an
independent external consultant appointed by it.
Select global practices
India
Planning phase
There are three stages during the planning process:
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 245
Any non-planned activities which are necessary for transmission capacity addition or system strengthening are
included in the network plan on a rolling basis (with quarterly revisions, if needed) as per the latest data
available for the major inputs to the plan.
The MoP is involved only at one point as mentioned above. The decision of the EC is finally approved by the
MoP. It is pertinent to mention that the approval of MoIT (counterpart to MOP in India) is required for four
times in the entire planning and approval process.
Detailed design and implementation approval phase
There are four stages in this phase:
1. Advance preliminary expense: After the project is being allocated to POWERGRID by the EC, the
first step is approval of advance expenses to be spent at the project site. It is estimated by the corporate
planning department of POWERGRID. These expenses are approved as per the delegation of powers
and are primarily to be used in various preparatory activities (viz. surveys, soil investigation, wind
National Electricity Plan
•It is prepared by the Central Electricity Authority establised by the Ministry of Power (MoP) •The National Electricity Plan is prepared for a short-term framework of five years while
giving a 15 year perspective •The National Electricity Plan is prepared by CEA in two volumes namely, Generation
(Volume I) and Transmission (Volume II). •It is prepared on the basis of the year-wise forecasts of electricity demand for each state,
union territory, region and all India in detail for a period of 15 years
Network Plan
•It is prepared by the POWERGRID and is divided into two parts- technical plan and commercial plan
•The technical plan is approved by the Regional Standing Committees for Power System Planning (SCPSP), consisting of CEA, POWERGRID, State Transmission Utilities (STUs) of the constituent States, Regional Power Committee (RPC) of the concerned region and representatives of generating companies in the region.
•The commercial plan (broad level cost estimates) is approved by the RPCs consisting of generating companies, POWERGRID, STUs, distribution utilities, and State Load Dispatch Centres (SLDCs) of the particular region
Review by EC for selection of project to
implement via competitive bidding
route
•An Empowered Committee (EC) has been constituted by the MoP, with representatives from the MoP, CERC, planning commission, POWERGRID, CEA and two (2) experts from the field of power sector nominated by MoP.
•The EC, based on the network plan, identifies key projects to be implemented under competitive bidding route (through private player participation). The remaining projects are awarded to POWERGRID on nomination basis.
•The decisions of the EC are then approved by the Ministry of Power (MoP)
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 246
analysis, rainfall data, local statutory and environmental clearances etc.) for the preparation of detailed
project report (DPR).
2. Preparation of feasibility report (FR)/ detailed project report (DPR) including cost
estimates: The DPR for the proposed transmission scheme consisting of all descriptions, technical
details and cost estimation is prepared by the cost engineering department of POWERGRID. The DPR
is prepared in coordination with other departments of POWERGRID like corporate planning, finance,
contracts & procurement, and engineering etc. in a time-period of around 8-10 weeks. In case the
estimated project cost is more than INR 1,000 Crore (USD 167 million), the POWERGRID is required
to take the technical approval for such project from CEA. The DPR is approved by either Chairman
(projects of value less than INR 5 Crore/ USD 0.83 million) or by Board of Directors (projects of value
more than INR 5 Crore/ USD 0.83 million). However, the approval from CEA is required in case the
project cost is more than INR 1,000 Crore/ USD 167 million).
3. Preparation of project investment proposal: Based on the detailed cost estimates in the DPR,
the corporate planning department of POWERGRID prepares the detailed investment proposal. In
case, the project cost is more than INR 1,000 Crore (USD 167 million), a third-part is appointed by the
POWERGRID for the financial appraisal of the project. The preparation of investment proposal takes
around 1 month. The investment proposal is sent to the Board of Directors for approval.
4. Project financing: The capital structure for any project (debt equity ratio) is a part of the DPR.
However, the sources of financing for any particular transmission scheme/project are not defined on a
project-specific basis in POWERGRID. Based on the planned transmission schemes, ongoing works
and milestones achieved, a financing proposal on company-wide basis is prepared by the corporate
planning department.
ElectraNet (Australia) - Planning phase
ElectraNet is the leading power transmission utility in Australia. The processes followed adopted by ElectraNet
is highly optimized and ensures higher efficiency. The planning in ElectraNet in Australia is summarised below:
Annual implementation plan- The annual plan is the finalised list of annual investments approved by AEMO based on the five year plan submitted by TNSP
Five year plan -Each TNSP prepares a five year plan based on load forecast/generation plans/ inputs from TNDP and public consultations.
Transmission Network Development Plan (TNDP) -Australian Energy Market Operator (AEMO) prepares the 20 years TNDP to serve as guiding document for Transmission Network Service Providers
(TNSP)
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 247
Detailed design and implementation approval phase
Key issues based on the comparison with other transmission utilities
The process being followed by EVNNPT for investment planning and approval is a prolonged process requiring
multiple levels of approvals. The company including PTC/ PMB and its employees do not have much power and
almost all approvals are granted at the highest level, irrespective of the complexity, size and criticality of the
projects.
The key issues in the existing planning process are summarized below:
1. First stage of approval from MOIT for all projects:
a. The annual implementation plan does not go to MoIT for approval. As the annual
implementation plan is not approved by the MoIT, all the projects- planned (forming part of
the annual implementation plan) or non-planned investment (not forming part of the annual
implementation plan) is submitted to the MoIT for the first stage approval;
b. The first stage approval is simply an approval of the investment proposal before the
preparation of FS. Under the current process of approvals, there is no distinction between
critical projects and non-critical projects and projects with smaller/ larger ticket size; and
c. In comparison to the planning process of POWERGRID, it can be observed that once the
project is allocated to POWERGRID by EC, there is no requirement for going back to the MoP
for the approval of each and every individual projects. However, the approval of CEA is
required in case the project cost is more than USD 167 million.
2. At-least three-four iterations of approvals from MOIT:
a. Each project will go to MoIT for approval for at least three times (four times in case of ODA/
OICB funded projects) during the entire planning process.
Identification and tie up of funds- The commercial services department is responsible for identification and raising of funds for the proposed investment
Project assessment conclusion report- Finally collating all the discussions and consultations, the asset management department prepares project assessment conclusion report. It is submitted for
regulatory approval
Project assessment draft report- The asset management department summarizes comments, conducts economic viability analysis and submits it again for public consultation.
Project specific consultation report- The asset management department prepares the project specification consultation report and send it for public comments
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 248
b. The multiple rounds of approval while ensures greater oversight may lead to significant delays
in implementing critical projects which is not in lines with the globally leading practice.
c. On the other hand, if compared with POWERGRID, it can be observed that there is no role of
the MoP in the approval of individual projects. Once the project is allocated to POWERGRID,
there is no direct role of the MoP in the planning process. All the approvals in respect of the
feasibility study, detailed project report, financing tie up are to be provided internally by the
authorities in the POWERGRID. However, the approval of CEA is required in case the project
cost is more than USD 167 million.
3. DTD is reviewed by the external consultant on behalf of MoIT in all cases irrespective of
the size and importance of project:
a. MoIT appoints an independent consultant to review the DTD which is submitted to MoIT by
EVN;
b. The entire process from hiring an external consultant, review and submission of report is time
consuming and is associated with costs and efforts. This level of detailed review process may be
required in case of technically complex investment programme or projects of higher ticket size;
and
c. In case of smaller projects which are standard system strengthening / replacement projects,
hiring an external consultant may not be the efficient / cost effective measure.
4. At the planning stage, no prioritization of projects is done based on financial
parameters:
a. Based on the various discussions held with various stakeholders, it was observed that the
commercials of the projects are not discussed at the planning stage. The cost estimation is
determined at the time of approval of FS;
b. On the other hand, in POWERGRID, the commercials (broad level project cost) are also
determined and approved at the time of the approval of network plan. In Australia, there is a
well-established framework under which the projects are evaluated on commercial parameters
at the planning stage; and
c. The financial evaluation framework for selection of project should be more robust. A more
effective framework for cost benefit analysis should be introduced. This has been proposed and
discussed in a separate concept note.
Proposed recommendations for the investment planning process
In developed countries such as Australia, the UK and the USA the market comprises of multiple competing
transmissions service providers and these countries also allow for merchant transmission lines. This inherent
difference compared to developing countries such as India, South Africa and Vietnam where the transmission
sector is primarily dominated by single government owned utility leads to limited competition in developing
countries. In markets where the competition is less, some degree of monitoring is required. Most countries
seek to empower the employees but in turn warrant greater accountability from them. This is
the central theme while proposing the recommendations in this concept note. It is also noteworthy to mention
that recommendations in this concept note needs to be looked at and reviewed in conjunction with the
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 249
recommendation on “Delegation of Powers.” Both recommendations in isolation would defeat the purpose
intended.
The key elements set out in our set of recommendations include:
1. Minimum changes to the existing process to ensure quicker and smooth adoption while aiming to
achieve the desired objectives;
2. Reducing the number of approvals required to reduce the lead time from concept to operation without
impacting the controls in the process; and
3. Empowering EVNNPT as a company to undertake independent decisions which benefits the company
and its users (generators, distributers and ultimate consumers).
Planning process
In the planning stage there are four levels of plans which are prepared. It can be reduced to three levels. The
Five Year Rolling Transmission Plan is an overlap of the Annual Implementation Plan and Five
Year Transmission Plan.
The second change proposed is the approval of Annual Implementation Plan (AIP). It is proposed that the AIP
should be approved by MoIT. Once the AIP is approved, the projects included in the AIP should not again go to
MoIT for approval.
The new planning framework would be as following:
Approval process
The existing approval stage is complicated and requires multiple rounds of approval from MOIT which is the
highest body in power sector within the country. Approvals for Feasibility Study and Detailed Technical Design
are also sought from MOIT which requires a considerable lead time. The recommendation in respect of
approval process is focused on proposing minimal process change but ensuring quicker approval process.
Some key changes proposed are summarized below:
1. No first stage approval: The first level approval process on investment proposal which requires
approval from MOIT is premature. The key information required to prepare a comprehensive proposal
is only available post the FS and DTD studies. In cases the projects are not viable either commercially/
Master Plan (approved by Prime Minister)
Five year transmission plan (approved by MoIT)
Annual Implementation plan (approved by MoIT)
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 250
technically but in existing framework one approval is still sought. The first stage approval may be
replaced with a “Preliminary go-ahead” stage which should not go beyond the Board of Directors of
EVNNPT. This level of approval should only be sought for projects not included in the Annual
Implementation Plan.
a. Projects above VND 1000 billion - Preliminary go-ahead from Board of Directors of EVNNPT
b. Projects up to VND 1000 billion - Preliminary go-ahead from President & CEO of EVNNPT
c. Projects up to VND 500 billion - Head of PMB/ PTC / Vice Presidents of EVNNPT
2. Merger of FA and DTD and Approval of FS and DTD within EVNNPT: The FS and DTD go up
to MOIT for approval, separately which is a time consuming process. On the other hand, it is proposed
that MOIT in discussion with EVN may propose broad guidelines / criteria based on which EVNNPT
management can decide on the FS and DTD. The project exceeding defined financial and technical
threshold should go to MoIT for approval. It is also proposed that FS and DTD can be merged together.
A separate concept note is being submitted by the consultant in this regard. The external consultants
appointed by MoIT are not required for all projects but only projects which exceed a defined financial
and technical threshold of complexity can be reviewed by MoIT through an external consultant.
Based on the annual implementation plan, PTC/ PPMB prepares a preliminary proposal/ rationale
The preliminary proposal will be submitted to relevant authority for preliminary go ahead
PTC/ PMB's head/ VP/ Presidents & CEO/ BoD (as the case may be) will provide the approval as per the delegation of power
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 251
3. New stage of investment proposal: An investment proposal should be prepared for all projects
taking into consideration the key output from FS and DTD. The investment proposal should be
submitted to relevant authority for approval along with the complete FS and DTD (merged) reports.
The Investment Proposal should be prepared by the IMD department. The projects exceeding a defined
financial threshold can be submitted with MoIT for approval.
After the preliminary go ahead, the PTC/ PMB will prepare combined FS and DTD (in case the suggestion in respect of merger is accepted by EVNNPT), otherwise FS and DTD will be
approved separately as per the existing process
The combined FS and DTD prepared by PTC/ PMB, as the case may be, submitted to IMD department in EVNNPT.
The IMD will review the combined FS & DTD with inputs from a variety of departments in EVNNPT such as CPD, Technical department, safety department, IT department and F&A
department.
After review the combined FS & DTD will be submitted to relevant authorities within EVNNPT for the projects which are within a defined financial and technical threshold
For the projects exceding a defined financial and technical threshold, the proposal will be submitted to MoIT for approval
After the approval of FS and DTD, the IMD will prepare an investment proposal
In case the project cost is within the defined financial thresold, the investment proposal will be submitted to the relevant authority based on delegation of power with in EVNNPT
In case the project cost iexcceds the defined financial thresold, the investment proposal will be submitted to MoIT for approval
After the approval of investment proposal, BoD of EVNNPT will issue a final project implementation approval for the execution of project
Recommendation#7: Process improvement in the investment planning process
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 252
Conclusion
The existing investment planning process is a prolonged one requiring multiple levels of approval from the
highest body (MOIT). There are advantages of repetitive approvals but the disadvantages are more over
whelming. Such a process reduces the accountability of the employees who are real workforce on ground.
In comparison in India which is a similar developing country, Ministry of Power has delegated the entire
investment decision making process to the Board of Directors of POWERGRID (which is the national
transmission company in India) even though the quantum of investments being managed by POWERGRID is
far greater.
In Australia too, similar to India, the entire investment planning process is managed by the transmission
company while the only external approving body is the independent regulator while Government has no role in
the entire process.
Considering the above facts, a new process has been proposed. The new proposed process is based on the
existing stages of the investment planning process. However, delegation of power in respect of decision making
is of indicative nature. It should be finalized based on a consultative process with all the stakeholders. The
approval of MOIT (which is the highest body in power sector) is only required once or for the projects which
exceeds a defined financial and technical threshold.
The new process will empower employees within EVNNPT and also enhance their accountability. MOIT each
year may appoint an audit committee to review the project approval process being followed within EVNNPT.
The entire process will reduce the lead time and cost.
The aim is that finally the entire investment planning process should be managed by EVNNPT alone without
requirement of external approvals.
Part-C (ii): Project management
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 253
Part-C (ii): Project management
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 254
Recommendation#1: Standardization of designs, specifications and layouts
Requirement of standardization of designs
Standardization of designs, drawings and specification of transmission line systems is one of global practice
followed by leading transmission utilities to reduce costs and time required for execution of transmission
projects. In Vietnam, it was observed that the high project preparatory period is one of the key reasons for delay
in the project implementation and hence a reduction in this time will help in speedy implementation of
projects. Use of standardized designs, specifications and layouts will reduce engineering design efforts as well
as time for detailed engineering and consequently reduce project development period i.e. pre project
preparatory activities. Standardization of design and technical specifications for different power equipment is
already followed in multiple developed and developing countries of Europe and Asia. There are multiple
benefits of standardization.
1. Faster project execution: Standardization avoids repetitive work and hence leads to reduction in
time taken for all activities related to design, approvals, engineering activities, specification
preparation, type tests etc. This will also result in reducing the work load of officials who can contribute
in innovation, risk management and better project monitoring.
2. Saving in costs: Since repetitive inspection tests are avoided, this will lead to monetary savings for
the organization as well as supplier/ sub-vendors. Also, suppliers can quickly manufacture the
equipment because of familiarity. Suppliers also do not require costlier resources for design activities
and can employ junior resources since all the key aspects are standardized.
3. Better utilization of spares: Availability of standardized equipment will reduce the requirement of
inventory in central stores or regional stores. This will also impact working capital requirement during
operation and quick availability of spares leading to shorter downtime of transmission lines and
substations.
Standardization can positively impact timelines in
multiple stages of transmission project:
1. Design & Engineering: As mentioned
above, designs, specifications and drawings
for different equipment will be readily
available post standardization and hence
there will be significant work reduction for
PMBs/PTCs. Time required for specification
preparation, engineering drawings review
and approvals will be reduced significantly
post standardization of such equipment
designs. Even the chances of errors on part
of manufacturers will reduce because of
standardization.
2. Bid process: Standardization of designs&
technical specifications coupled with
Standardization
Design & Engineeri
ng
Bid process
Project Execution
Inspection & testing
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 255
standard clauses of bid documents will reduce the bid process duration significantly. Further, since the
suppliers, vendors and contractors are already aware of these standardization (and no deviations
permitted), the bid evaluation time will also reduce.
3. Project execution: Increased acquaintance with standard designs for field supervisors as well as
construction contractors will help them speed up different activities. Also, it impacts pace of
concomitant activities. For example, standardization of tower design will hasten up the tower
foundation design since the tower designs are available beforehand. Steel procurement can also start
without waiting for design finalization.
Standardization increases interchangeability. For example, tower parts for one project can be used for
other in case of any change in schedules.
4. Inspection and testing: Type tests, unlike routine tests, are done on first prototype of an equipment
to confirm that the equipment meets design specifications and are not repeated on every unit
manufactured or fabricated. In case of transmission towers, its testing is generally a time consuming
process and it will further increase in case of different wind zones/ voltage levels. Also, any failure of
testing will delay the process further. Further, availability of test beds to perform the testing may also
be an issue.
Hence, if equipment design is standardized, type testing can be avoided since a type test certificate can
be accepted for an agreed validity period (say 5 years for a transformer). This will help in reduction of
project time.
Standardization will also result in multiple benefits in operation as there will be less requirement of
maintenance of spares inventory since they will be interchangeable. Also, operation personnel will be familiar
with the design and operation and can easily trouble shoot issues because of familiarity.
Key aspects of standardization
Prior to standardization of various equipment design and specifications, it is essential to standardize operating
voltage level, basic insulation level and estimate short circuit levels at different voltage levels of the system. All
these parameters impact ratings of various protections and metering equipment in transmission lines and
substations and hence have to be finalized before standardization. The key design parameters that need to be
standardized in substation and transmission equipment and layouts are elaborated below. However, these are
indicative in nature. The exact scope and parameters that need to be standardized have to be decided by
EVNNPT with the help of technical consultants (as required).
Substation design & equipment
Standardization of design, layout and equipment reduces project design time, project preparatory period and
construction period considerably. Following paragraphs explain the scope for standardization of designs,
equipment specifications and layouts for a High Voltage substation/switchyard:
Substation switching scheme and layout: There are a variety of switching schemes for various HV and
EHV substations and it is desirable to standardize a switching scheme for different voltage levels based on cost
and reliability considerations. For example, in India the central transmission utility mostly follows one and half
breaker scheme for 400 kV substations and Double Main and Transfer bus scheme for 220 kV substations. The
switching scheme helps in standardizing bill of materials for key equipment like circuit breakers, insulators,
current and voltage transformers and their electrical connections, cabling requirements etc.
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 256
Further, layouts of substation can be standardized by standardizing on a typical layout of substation based on
statutory clearances required to be maintained, bay size & width, bus size and type of material, equipment
interconnecting level, bus level, span length etc. for a particular voltage level (say 500kV).
Once the substation/switchyard layouts are standardized, individual equipment structures can also
standardized. Standardized designs of beams and columns can be used for structures, further equipment
foundations designs can be also defined, if required.
Standardized of layouts and designs can be extended to substation control room buildings. The control
buildings designs can be standardized for a substation of each voltage level.
Transformers & reactors: We suggest standardizing specifications of power transformers viz. MVA ratings
for different voltage levels along with other parameters like % impedance, acceptable loss level at no load and
full load, number of windings, voltage regulation, vector group, tap changer ranges, electrical clearances,
bushing parameters, insulation levels, cooling requirements at various loadings, material for core, tank,
windings, transformer oil parameters, auxiliary fittings & accessories (e.g.: Buchholz, pressure relief valves, oil
& winding temperature indicators). A range of values for most of these parameters are available in the IEC
standards which are already adopted by EVNNPT and EVNNPT may choose optimum parameters based on
recommendations of technical consultants.
Similarly, we suggest that MVAR ratings & other parameters of bus reactors and line reactors used in high
voltage substations (500 kV and 220 kV) may also be standardised. The ratings of bus reactors have to be
determined by factors like required voltage regulation, short circuit-fault level in the system etc.
Circuit breakers: Key design parameters of circuit breakers to be standardised is the capability to withstand
short circuit current (generally in kilo Amperes/second) along with other parameters viz. insulating & medium
for arc-extinguishing (e.g.: SF6, oil), value of pre-insertion resistor, operating duty cycle, operating mechanism
(hydraulic or spring), capabilities of clearing faults (in kilo Amps) etc.
Lightning Arrestors: Key parameters to standardise for lightning arrestors or surge arrestors are type of
arrester for a particular voltage level. Generally Metal Oxide Varistor (MOV) arrestors are being used at high
voltage level. The other key ratings like rated arrester voltage, nominal discharge current, energy handling
capability, maximum continuous operating voltage etc. will need to be provided for a particular voltage class.
Current transformer and Capacitor Voltage Transformer: The rated currents and ratios, burden,
number of secondary cores (protection or metering), accuracy class for protection core (magnetising current
and knee point voltage) and accuracy class for metering core etc. have to be standardized for different voltage
levels
Protection schemes: There are three major components to be protected in the transmission system-
transmission line, bus bars and power transformers. Different types of protection schemes exist for detecting
different faults in these three areas. Generally line protection will have Main 1 and Main2 protection having
distance protection/differential protection and back up protection. Bus bar differential protection can be
distributed or centralised type and transformer protection will be differential type along with over current,
Restricted Earth Fault, back up earth fault, over flux and instrument relay protection mounted on transformer
body. These protection schemes need to be standardised for the sake of overall protection coordination. Even,
type of protection relay - numerical, static or electro-mechanical needs to be standardised
Communication equipment: Transmission system requires communication channels between substations
for speech, control and protection. The communication can be through Power line carrier communication
(PLCC) or through Optical Ground Wire (OPGW). The communication mode and different aspects of the same
may be standardised.
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 257
Standardization of Tower Design
It is desirable that the designs of transmission towers are standardised to the extent possible. The
standardization needs to be taken on various design parameters. As we understand from our numerous
meetings and discussions held with concerned EVNNPT engineers and managers, the height, weight and tower
configuration is decided depending on a complex interplay of multiple parameters and further some of these
parameters are again inter-dependent. Key parameters that impact standardization of tower design are
elaborated below:
Clearances
As per our understanding based on the discussions with EVNNPT engineers and managers, the total height of
tower is a sum of minimum permissible ground clearance,
maximum sag of lower most conductor, vertical spacing
between conductors and vertical clearance between ground
wire and top conductor. Following parameters have scope
for standardization.
1. Maximum sag of lowermost conductor: The
size and type of conductor, wind and climatic
conditions and span length determine the
conductor sag and tensions. Span i.e. horizontal
distance between two consecutive towers depends
on economic considerations and has to be
standardized for different voltage levels in
different terrains for different towers. Maximum
sag for conductor span occurs at the maximum
temperature and still-wind conditions.
2. Spacing of conductors: Length of the insulator, diameter of the conductors and maximum sag at the
centre of span, impact spacing of conductors and should be standardized.
Wind pressure
The loading on towers due to wind is a major component on total loading on towers. It should be noted that the
wind speed increases with height and is less at ground level because of friction. The aerodynamic forces on the
exposed surfaces may cause the effective loading in a direction different than wind direction and hence need to
be calculated properly.
As shown, Vietnam is divided into five wind regions depending on wind pressure.
They are further sub-divided into two regions on the basis of strong or weak
hurricane winds. While designing standard towers, it may be noted that
standardizing for all wind regions may not be necessary. The tower standardised for
higher wind speeds (say wind region III) will be used for areas under lower wind
speeds (wind region I & II). Area covered in a particular wind region, requirement
of transmission towers in that particular region should be considered to determine
whether standardization is, at all, necessary for that particular wind zone.
Wind region
Pressure (daN/ mtr2)
I 65
II 95
III 125
IV 155
V 185
Various Clearanaces
Wind pressure
Angle of deviation
Conductor, configuration
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 258
Angle of deviation & crossings
The transmission line route will not be entirely on a flat terrain in a straight line and encounter varying angles
and ground heights in its route. Towers have to be standardized based on the angle of turn. A range of values
may be specified and a particular standardised design should be able to withstand the tensions and loading for
that particular range. Generally, tangent suspension towers are mostly used as long as the route is a flat terrain.
Angle towers (tension towers) can be sub-classified into different types depending on the requirement. The
tension towers for various angles of turn (15, 30, 45, 60 etc.) and suspension towers needs to be standardized
for different wind zones as mentioned above
Special towers need to be designed for crossing of river, highway, railway lines etc. However, standardization of
the same may or may not be needed depending on the number of such towers. Sometimes, tower and leg
extensions are required to provide sufficient clearance over ground or while crossing power lines, railway lines,
highways and uneven ground etc. Even these extensions can be standardised to ensure easy availability and
inter-changeability.
Conductors and their configuration
The type of conductor required is designed and selected based on various technical factors -power transfer
capacity required, thermal capacity of conductor, voltage level of power transfer and other electrical and
mechanical properties. Most commonly used conductors in high voltage power transfer are Aluminium Core
and steel reinforced (ACSR). Different types of conductors are available - bersimis, moose, panther, dog, wolf,
zebra etc. depending on number of aluminium and steel strands in a sub-conductor and diameter of each
strand. Many recent developments have come to enhance power supply, reduce loss, weight etc. which led to
newer types of alloys being used (e.g.: AAAC- All Aluminium Alloy conductor).We suggest to standardise type of
conductor, sub-conductors per phase and its configuration for different voltage levels and type of circuits
(single circuit, double circuit).
Other line related equipment
Tower material: The base width of the towers of different voltage can be standardised. Steel is the major
component of tower structure. Grade of steel and mix of mild steel and high tensile steel, member size has to be
standardised.
Tower parts: Other tower parts include bolts, nuts, clamps, connectors, fittings, washers, joints, different
plates, step bolts, anti-climbing devices, bird guards etc. Standards for most of the equipment are available in
IEC and other general standards along with process and method of connections. However, choosing a certain
standard for different equipment or method of connection has to be done by EVNNPT. For example,
dimensions of bolts like bolt diameter, hole diameter, spacing, edge distance can be standardized. Also, method
of fitting of bolts and nuts can be specified. Similarly, thickness of washer and type of washers can be
standardized.
Insulators: We suggest standardizing type of insulators to be used at different voltage levels based on
creepage distance, material of insulator (porcelain, glass, polymer), mechanical strength of insulators, shape
(disc or rod) and requirements of hard ware fittings.
Following are details of standardization carried out on power transmission systems by Indian Central Power
Utility. We are providing various design parameters, specifications, layouts etc. for different equipment at 400
kV level.
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 259
Standardization by Indian Central Transmission Utility - Power Grid
Corporation of India Limited (POWERGRID)
The most common extra high voltage transmission level prevailing in India is 400 kV. POWERGRID has
standardised various tower design parameters, layouts, specifications of equipment for this voltage level
to reduce time and costs involved in repeated design and approvals. Some of the key design parameters
are presented below:
Wind zones: India is divided into six wind zones of different wind speeds -meter/second (m/s) - 33, 39,
44, 47, 50 and 55. In view of overall economy and time, the standardization has been done for wind zones
of 44 m/s and 50 m/s for all type of towers. The standard towers for wind zone of 44 m/s is also utilized
for wind zones of 33 m/s and 39 m/s and that of wind zone of 50 m/s is adopted for wind zone of 47 m/s.
No standardisation is done for wind zone of 55 m/s, since this wind zone is confined to very small area of
the country.
Angle of deviation: Classification of towers depending on the angle of deviation in route
Angle (degrees)
Single circuit
Double circuit
Uses
0-2 A DA/ P Tangent towers for straight run of the transmission line.
2-15 B DB/ Q Also used as sectionalising towers without any angle
15-20 C DC/ R Also used as transposition tower without any angle
30-60 D DD/ S Terminal towers near gantry or as anchoring tower before major river crossing, power line crossing, railway crossings
Tower & Leg extensions: All towers are designed so that they can be provided with standard tower
extensions of +3, +6 +9 and + 25 meters. These extensions are used to provide sufficient clearance over
ground or while crossing power lines, railway lines, highways, other towers, uneven ground etc. Standard
leg extensions are designed for 1.5, 2.5 and 3.5 meters for uneven ground (say hill slopes) to avoid or
reduce costs of benching /revetment.
Conductors: POWERGRID standardised usage of ACSR moose conductor for its 400 kV transmission
lines. Either twin or quad bundled conductors are used depending on quantum of power transfer.
Different parameters for conductor including strands of Aluminum & steel, wire diameter, overall
diameter and drawings for wooden drum of conductors are standardised.
Insulators: The standardization of insulators depends on parameters like creepage distance, electro-
mechanical strength of insulator and size of the insulators (i.e. diameter, length etc.). Generally
composite rod or disc type insulators are used in POWERGRID and the material and all types of
drawings for 220, 400 and 765 kV voltage levels are standardized. Example:
Composite rod insulator -For 400 kV Twin moose conductors
Type of Insulator
String
Size of Core dia x
Nominal length)
(mm)
Minimum
Creepage
Distance(mm)
Units
per
String
Unit’s Electro-
mechanical
strength (kN)
Mechanical Strength
of String along with
Fittings (kN)
Single ‘I’ Suspension 20 x 3335 13020 1 x 1 120 120
Single Tension 24 x 3910 13020 2 x 1 160 2 x 160
Double Tension 24 x 3910 13020 2 x 1 160 2 x 160
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 260
Source: POWERGRID website
Standardization by Indian Central Transmission Utility - Power Grid
Corporation of India Limited (POWERGRID)
Other tower parts: All clamps, connectors, bolts, washers, angles etc. have been standardised. For
example, POWERGRID is using electro-galvanised spring washers under all nuts of tower with a
minimum thickness of 3mm. commonly used diameter of bolts are 12, 16 and 20 mm.
Switching Scheme of substations: The electrical switching layouts are standardized and following
are most commonly used. One and a half breaker scheme at 400 kV switchyard and Double Main and
Transfer bus scheme at 220 kV level have been standardised.
Transformer & reactors: For 400/220 kV substations, 315 MVA 3 phase auto transformers are used
till recently. However, 500 MVA rating transformers are being used in areas expected to have high load
growth. Similarly, MVAR ratings of bus and line reactors at 400 kV level are either 50 MVAR or 80
MVAR.
Protection schemes: POWERGRID uses Numerical distance protection schemes of two different
makes as Main-I and Main-II protection. Differential protection relay, Restricted Earth Fault Protection
relay, Backup impedance protection relays are used in case of reactors and transformers. Also, Over-flux
Protection, Direction Over current and earth fault protection are used additionally in case of
transformers. Key settings of these relays like operating time etc. are standardised. POWERGRID has
switched to numerical relays in all its protection schemes.
Circuit Breakers: SF6 circuit breakers with a short circuit rating of40 kA/sec are commonly used in 400
kV switchyards
Surge Arrestors: The insulation level for different equipment is designed to withstand lighting impulse
and switching surge levels for 400 kV system as follows:
Equipment Lightning impulse (kVp) Switching surge (kVp)
Power transformer +1300 +1050
Instrument Transformer +1425 +1050
Reactor +1300 +1050
CB/Isolator Phase to ground +1425 +1050
Across open contacts +1425 (-/+240) + 900 (-/+345)
Substation Civil works: POWERGRID has developed standard drawings for all the civil works
including control room building, fire-fighting system, foundations, and township works etc. which will be
issued during the bidding phase. All the required site specific variations will be incorporated and released
to contractor as per work schedule.
Battery & Battery Charger: In a 400 kV substation, the standard requirement of DC System is two(2)
float-cum- boost chargers and two(2) battery sets for each of 220V and 48 V systems.
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 261
Current status of standardization in EVNNPT
As we understand, EVNNPT has already initiated the process of standardization of designs, specifications and
drawings of substation equipment. Technical Department of EVNNPT is leading the initiative for the
standardization of designs, specifications and drawings. Currently, few of the substation equipment
specifications are being standardized. However, the process of standardization needs to be expedited further by
formalizing the responsibility and process of the same. We suggest forming a high level committee of overseeing
and advising the standardization process carried out by technical department. The committee will be able to
drive the standardization initiative in EVNNPT.
Standardization of transmission line towers and other transmission line equipment is not on agenda of
EVNNPT. It needs to be included. As explained above, it will help EVNNPT in saving costs and time in
transmission project execution. Here is the approach we suggest to facilitate the standardization initiative
within EVN EVNNPT and its 7 subsidiaries.
Approach for standardization of designs
A high level committee of deputy directors from Technical, Materials and Procurement departments from
EVNNPT and Technical departments of PMBs and PTCs may be formed for the purpose of standardizing
various equipment and designs. This committee will be headed by Director of Technical department, EVNNPT.
Secretarial support will be provided by the Technical department of EVNNPT.
Objective
The objective of this committee is to standardize designs, drawings, layouts and technical specifications of
various equipment, materials, electrical and civil structures, processes in manufacturing, construction and
commissioning etc. To start with, the committee may focus on standardization of designs, drawings and
specifications of equipment and materials in substations and lines.
Key activities
Key steps to be followed for such standardization are as follows:
1. List out all the equipment, materials in the transmission line and substation along with specifications
and designs available and being used by EVNNPT;
2. Identify key equipment, material e.g.: power transformer, reactors, circuit breaker, conductor,
insulator, surge arrestor, wave trap, tower parts that consume significant time in engineering;
3. Conduct bid process for selection of consultant(s) who will prepare standard designs, drawings and
layouts for selected equipment within stipulated timelines;
Director, technical dept, EVNNPT
One Dy director, Technical dept,
EVNNPT
Dy director, Materials dept,
EVNNPT
Dy director, Procurement dept,
EVNNPT
One Dy Director from techncial
dept of each PMB
One Dy Director from techncial
dept of each PTC
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 262
4. Review the designs, drawings and layouts prepared by consultants and finalise the same by conducting
internal discussions (among EVNNPT and PMBs/PTCs) as well as interaction with consultant(s); and
5. Obtain approvals from concerned authorities for standardization of designs, drawings and
specifications.
Further, to incentivize the process of standardization and idea generation internally in the organization, the
working committee may seek ideas regarding standardization of design or specification of particular equipment,
material or from internal experts in different departments of EVNNPT and subsidiaries. A monetary incentive
may be provided for those designs which have been adopted after evaluation. The new ideas generated through
this initiative can be evaluated and develop further by following the steps mentioned above under “Key
Activities”.
Scope of work for Consultant(s)
Experienced Consultant(s) has to be hired for
standardization of designs, layouts etc. The
consultant(s) are mandated to study the historical
designs, decide various parameters impacting design
and then prepare standardized designs, drawings, and
layouts. For example, in case of transmission tower
designs, the scope of consultants will be
1. Decide parameters impacting design- e.g.:
clearances, angle of turn, wind zone,
temperature etc.;
2. Study past designs of different towers in similar conditions in Vietnam or similar countries;
3. Check for historical performance in terms of number of outages, faults & reasons, maintenance
requirements etc. and if these reasons are attributable to any design parameters; and
4. Finalize tower designs for existing combination of parameters that are mostly required.
Monitoring
There should be a time-bound plan for standardizing design and specifications of key equipment and materials
that should be monitored by the working committee in its quarterly review meetings and report to the top
management
Post standardization review
Standardization of designs, specification of different equipment and materials etc. needs to be reviewed once in
a year (as decided by EVNNPT for different equipment) based on operational performance, new technological
innovations, change in system conditions etc.
Also, it may be noted that even after standardization of key parameters in technical specifications of various
equipment/ materials, there will be other parameters which have to be finally provided by the vendor/
equipment manufacturer which should stipulate to relevant band of values provided in that particular IEC and
other standards. In some transmission projects, it may happen that some minor variations need to be
considered from standard specifications due to site specific issues or regional climatic vagaries. In this case,
Decide parameters
impacting design
Study previous designs and
layouts
Historical performance
Prepare standard designs, layouts
Recommendation#1: Standardization of designs, specifications and layouts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 263
only the particular deviations need to be approved from the relevant authority rather than entire design (after
duly considering the impact of such deviations on operational performance, reliability and costs).
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 264
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Drivers for Turnkey execution
EVNNPT has been awarding multiple and separate supply and erection contracts for the execution of power
transmission projects in Vietnam. Currently, following are the general list of packages associated with a
transmission line and substation projects.
# Typical packages in transmission line projects
Typical packages in sub-station projects
1. Consultant for preliminary cost estimates Consultant for preliminary cost estimates
2. FS consultant FS consultant
3. DTD consultant DTD consultant
4. Resettlement / site clearance Resettlement / site clearance
5. Topographical survey Topographical survey
6. Mines survey Mines survey
7. Tower steel supply HV Equipment and material supply
8. Conductor supply LV equipment supply
9. Insulator supply Control equipment supply
10. Cable supply Installation/erection
11. OPGW supply Testing and calibration
12. Installation/erection and tower foundation(multiple contractors)
SCADA
13. Insurance of asset Insurance of asset
14. Audit service Audit service
Note: The packages listed in italics are not common between line project and sub-station project
Following are the typical issues faced by an organization while executing multiple /separate supply and erection
contracts:
Lack of single point responsibility
Each contractor will be responsible for its own supply /design /erection packages and coordination of multiple
contractors will be a challenging task for the owner i.e. EVNNPT. Degree of complexity in coordination
increases with number of vendors /contractors. Further, in case of any issues in operation, identification of the
responsible party for the issue becomes the responsibility of the owner. This may prove time consuming if the
issue /defect cannot be attributed to a single vendor and the resultant delay impacts the performance of the
system. In the case of contracts executed by EVNNPT, the entire responsibility of resolving various
coordination issues lie with itself and hence it is vulnerable to all the above mentioned risks.
Difficulty in matching of procurement & erection schedules
Matching of schedule of procurement of equipment /material with the requirement at site for erection
contractors is a challenging task. The supply of equipment to erection contractor can be delayed due to reasons
like delay in procurement by the concerned department, delay in transport of equipment from stores, diversion
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 265
of material to any other site due to an emergency etc. and this leads to delay in project execution. On the
contrary, if the equipment lies idle in stores, and there is a delay on part of erection contractor mobilization, it
leads to quicker expiry of guarantee periods. In case of EVNNPT also, there are multiple contractors,
consultants working on the different packages of project and there is strong possibility of occurrence of the
above mentioned mismatches. Further, PMB’s Deputy Directors carry the responsibility of timely execution of
projects.
Probable low response from contractors
The value of multiple supply and erection contracts is generally low. We understand that even there are
packages for construction of only 20 km line as well. The value of such contracts will be low and will not be
commercially viable for established contractors leading to lesser number of responses for bids and hence less
competition.
Key aspects of turnkey contracts and separate supply and erection contracts
A brief comparison of key aspects of Turnkey and separate Supply & Erection contracts is presented below and
are subsequently elaborated.
Parameter Separate Supply & Erection Contracts
Turnkey Contract
Project responsibility Owner is responsible to identify the concerned party for a particular issue. Completion risk with owner
Turnkey contractor has single point responsibility to resolve all issues. Completion risk with contractor
Bid process Less time for evaluation for a package, but number of packages
More time for evaluation of package, Bid evaluation will become easier with standardization
Coordination Tasks Complex Simpler
Time and cost over runs Chances are high Lesser probability
Owners participation Limited participation in routine stages of project execution and monitoring. Can be mitigated by appointing an Owner’s Engineer
Considerable participation in almost every stage of project
Project Responsibility: In turnkey execution, all the activities from detailed engineering, procurement of
equipment and materials, arranging for testing and inspection, interactions with various sub-vendors, timely
erection, testing & commissioning will be the responsibility of the main turnkey contractor. In case of separate
supply & erection contracts, owner needs to interact with multiple contractors and consultants for different
packages. Further, during operation of the project, if any issue arises, then it would be the responsibility of the
owner to identify the concerned contractor, consultant for such defect. It would become complex if multiple
contractors and consultants are involved in a project.
Bid process: In case of multiple supply and erection contracts, the total time and efforts of owner for running
the bid process will be higher as compared to a single bid process in case of turnkey execution. Although, the
time and efforts required for that single bid process may be higher as compared to a single supply or erection
package because of detailed techno-commercial eligibility and qualification criteria in a turnkey project.
From the owner’s perspective, in a turnkey situation it is often difficult to effectively compare the various design
proposals submitted by contractors. The designs will probably not be uniform because there are usually many
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 266
different methods of satisfying the owner’s general needs and performance specifications. Partly, this issue can
be resolved by standardizing the basic designs and parameters, releasing a list of pre-approved sub-vendors etc.
In separate supply & erection contracts, though it takes significant time to conduct multiple bid processes for
various vendors and contractors for individual works, it is considerably easy to select the prospective bidder as
the comparison would generally be in monetary terms. The design is prepared by a separate consultant hired by
the owner.
Coordination: In case of separate supply & erection contracts, the owner should constantly coordinate with
multiple contractors and consultants to execute the project as per the timelines. This significantly increases the
workload on the executing authority as well as places the completion risk in its domain. At times of variation, it
becomes difficult for the owner to identify every contractor and vendor responsible for the specified work.
Further, any mismatch in the completion schedule of a package can lead to concomitant delays and other losses.
For example, in case of any delay in erection contract and the corresponding material equipment has already
been successfully delivered, the available guarantee period of such equipment will reduce without actual usage.
Turnkey execution will significantly reduce the risk and work load of the owner, since the coordination efforts
will be reduced and the turnkey contractor will bear major responsibility of timely execution of contracts. Also,
issues like wastage of guarantee period while the equipment lies idle in store, possibility of disputes with
erection contractors for delay in providing equipment/ materials etc. will be greatly reduced from the owner’s
perspective.
Further, in turnkey mode, the contractor’s control over design and construction planning allows it to use
innovative designs, familiar construction methods and timely procurement of equipment etc. resulting in better
project execution.
Time & Cost over runs: A properly planned turnkey project will reduce time and cost over-runs since the
main contractor can plan certain design and execution activities in parallel and can match its procurement
schedule of required equipment with overall erection schedule. A timely execution of project will avoid
additional costs like interest during construction that would have been incurred in case of delay. Further, the
owner can reduce the risk of cost escalation on raw materials in case of contractors default.
In separate supply & erection contracts, the contractor’s decreased control over the design of the project may
result in increased overall costs. Since design is prepared by an individual contractor, manufactured by other
vendor and erected by some other contractor, the erection contractor would not be in a position to order
necessary materials for subsequent phases ahead of time, perhaps increasing the cost. These expenses will all
result in increased project costs.
Owner’s participation: In turnkey execution the owner will have very limited or negligible participation in
the project execution and project management controls. This is generally mitigated by employing an owner’s
engineer to monitor the progress and quality of the work. This would help to retain owner’s interest on
specifications and quality of the project.
In separate supply and erection contracts, the owner will have significant participation in every stage of the
project. But due to its increased responsibility to maintain timelines and procurement schedules, owner will not
have greater focus on the quality of the work.
Part-turnkey
A variant of the turnkey execution is part turnkey or limited turnkey execution. This can be achieved by splitting
the responsibility on mutually exclusive activities of a project to individual parties. For example, in case of
multiple lines and substations of a project, transformer, reactor, conductor and insulators can be centrally
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 267
procured by the owner as they are high value items and supplied to the contractor at site. Central bulk
procurement would help in achieving cost effectiveness and also easier operation due to replicability of spares
and increased awareness among O&M. personnel. The procurement of remaining line equipment can be
clubbed with the erection contract(s) of lines as in case of turnkey execution.
Pre-requisites of turnkey mode of execution
Certain pre-requisites have to be satisfied before implementing turnkey mode of project execution to ensure
timely and effective project implementation.
1. Appropriate qualifying requirements with criteria on technical and financial capabilities of bidders,
similar past experience, clear conditions for joint venture /consortium of supply and erection
contractors;
2. Technical specifications have to be standardised for different equipment and a list of approved sub-
vendors/ suppliers should be made available so that time for testing can be reduced. Standardization of
designs and specifications will not only help in reducing the time for pre-construction activities but also
reduce the chance of disputes in future;
3. Comprehensive bid documents with clear scope of contractor, identification of responsibilities of
contractors and EVNNPT, proper price variation indexing, adequately defined payment milestones,
guaranteed performance & technical parameters, penalties for delay or faulty equipment, issue
escalation and dispute redressal mechanism etc.;
4. An effective project management tool (software) for constant updates on status of projects;
5. Prompt payment mechanism to contractors for completed milestones; and
6. Vendor capacity development initiatives are needed since this will be a new regime for contractors as
well. Also, vendor development initiatives are needed to develop domestic vendors’ capabilities as
turnkey contractors (reserving a certain percentage of packages that meet certain criteria to new
contractors).
Framework for designing turnkey contracts
Since turnkey mode is not prevalent in EVNNPT for domestic procurement, following steps are required to
institutionalize it.
Policy level changes
•Identify laws, decrees, decisions on procurement that get impacted
•Propose changes and pursue for approval
Development of detailed documents & procedures
•Develop working level documents/ procedures
•Multiple iterations and consultations with PMBs, PTCs and stakeholders
Pilot implementation & institutionalization
•Identify pilot projects for turnkey implementation
•Institutionalize the changes and seek improvement based on experience
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 268
1. Policy level changes
a. Identification of decrees, decisions that need to be updated: All the laws, decrees on bidding
and prevailing procurement process, delegation of power have to be studied and changes
required for implementing turnkey mode are to be suggested;
b. Discussion with EVNNPT, PMBs, PTCs and other stakeholders and submit to EVN/ MOIT/
concerned authority for approval;
2. Development of detailed documents and procedures
a. Post approval of policy changes, preparation of procedures and documents e.g.: draft Standard
bidding document (SBD) for different modes of procurement;
b. Discussion with key departments involved in Procurement function EVNNPT, PMBs, PTCs and
other stakeholders;
c. Incorporate the agreed inputs and submit to EVN/MOIT/concerned authority for approval;
3. Pilot implementation & institutionalization
a. Identification of pilot projects for execution in turnkey framework;
b. Institutionalize the changes and seek improvement based on experience.
To facilitate the entire process, a high level committee of Deputy Directors and experts has to be formed from
all key departments in Procurement function in EVNNPT and PMBs - procurement, materials, finance &
accounts, evaluation etc. This committee will be headed by Director of Procurement department, EVNNPT.
Secretarial support will be provided by the Procurement department of EVNNPT. Composition of the
committee is as follows:
Objective: The objective of this committee is to facilitate the process of development of policies, procedures
and standard bidding documents for the effective implementation of turnkey mode of procurement in EVNNPT
Role of Consultant(s): The committee can hire consultant(s) for assisting it in the above steps.
Monitoring: There should be a time-bound plan for identifying changes required in the existing policy regime,
development of policies, procedures and SBD, stakeholder consultations and obtaining approvals. The progress
should be monitored by the committee in its quarterly review meetings and report to the top management
Director, Procurement,
EVNNPT
Dy director, Procurement,
EVNNPT
Dy director, Materials, EVNNPT
Dy director, F&A, EVNNPT
Dy director, Technical, EVNNPT
One senior expert each from
Procurement & Evaluation of each
PMB
1 1 1 1 6
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 269
Post implementation review: After successful pilot implementation and incorporating any changes in the
documents, a particular number of projects should be identified for turnkey mode of procurement every year.
Since turnkey projects are generally of significant value, they have to be executed by PMBs and not PTCs
Further, a dedicated cell in procurement department of the respective PMB may be created with sufficient
number of experts for executing the project in turnkey mode.
The committee will review the progress of turnkey mode of implementation once in a year (or as decided by
EVNNPT) to suggest changes in clauses, procedures for optimal implementation of turnkey regime.
Key aspects in turnkey procurement
Following are the key aspects to be considered for developing and implementing a turnkey procurement regime
in EVNNPT.
1. Packaging concept;
2. Qualification criteria;
3. Design & Engineering;
4. Role of supervisory consultant;
5. Risk allocation;
6. Contract management; and
7. Quality control.
Packaging concept
A transmission system project should be divided into clearly defined packages in such a way that the packages
can be executed without any coordination and interfacing issues and at same time attract competitive bids. So, a
package list has to be prepared based on cost of the package, location, availability of equipment and/or
materials, completion schedule etc.
So, we suggest the possible packaging concepts that can be considered for turnkey execution:
1. Route alignment, detailed survey and soil investigation packages;
2. In case of a single substation package, the entire substation (including transformer/reactor) may be
awarded to a single contractor including supply and erection of the same. In case of multiple
substations, transformers and reactors can be centrally procured and rest of the supply and erection
works can be awarded in turnkey mode;
3. In case of a single transmission line package, both conductor and insulator packages can be included in
the single supply-cum-erection contract. Further, in case of transmission line packages, a minimum
route length (say 100 km) can be awarded as a single package rather than multiple small packages; and
4. In case of long transmission lines that need urgent execution, the supply-cum -erection packages for
parts & erection along with conductors and insulators can be split according to distance and awarded to
two or more contractors.
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 270
EVNNPT has been contracting even small stretches of transmission lines (say 20 km) through separate erection
contracts; this can be executed in a different way, like combining the construction of a new line and renovation
of the existing line in one package (or) increasing the minimum route length that can be awarded to a single
player for a package. This would increase the estimated cost of the package, which may encourage more
established players to enter the sector as well as reduce the efforts of EVNNPT in procurement, approvals and
coordination.
Qualification criteria
Generally, qualification criteria for selecting a turnkey contractor include:
1. Basic criteria: Legal status of companies and other compliances to Acts& Rules in the country;
2. Technical capability: Relevant past technical experience in similar projects, say, supply of particular
equipment and the quantity of such equipment, value of erection services, O&M experience etc. in
particular period; Also, non-performance of contracts in the past years and pending litigation history
are checked. Generally, relevant client citations are asked as proof;
3. Financial capability: Historical financial performance is evaluated using parameters like annual
turnover, net worth, internal cash accrual. Audited financial statements are generally required as proof;
4. In some cases, experience of key personnel in relevant areas is also required;
5. Also, where applicable, conditions for Joint Venture /consortium participation in bids are mentioned;
EVNNPT should also develop criteria using similar criteria for the turnkey projects.
Design & Engineering
The design parameters, standard drawings & technical specifications, guaranteed technical particulars for all
key equipment and materials in the particular project package should be mentioned upfront in the bid
documents. The technical parameters are generally based mainly on output specifications. Further, a list of pre-
approved sub-vendors for different equipment is also part of the bid documents. The underlying principle of all
the designs & drawings is to balance two counteracting principles of standardization as well as providing
flexibility to contractors for innovation. The review and approval processes for working designs and drawings
are also to be provided in the document. Also, all testing and inspection processes & procedures along with
standards to be adopted for the fabrication, manufacturing, assembling, construction, erection and
commissioning have to be detailed as part of the document.
Role of supervisory consultant
EVNNPT/ PMBs can appoint a supervisory consultant to monitor the performance of the turnkey contractor in
project implementation. The Engineer shall be responsible for the enforcement and proper administration of
the contract and shall, with due care and diligence, carry out:
1. Review of designs and providing comments in line with owner’s requirements;
2. Attend testing & inspection of design, manufacturing, erection and commissioning of various
equipment/ material of projects;
3. Supervision of erection and construction activities in line with prescribed standards;
4. Attend testing and commissioning of the equipment; and
Recommendation#2: Adoption of full/part turnkey (supply cum erection) contracts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 271
5. Assist in resolution of disputes (if any).
Risk allocation
As an underlying principle, risks should be allocated to the parties that are best suited to manage them. Project
risks should, therefore, be assigned to the turnkey contractor to the extent it is capable of managing them.
Appropriate allocation of risks and responsibilities would increase the scope of innovation leading to
efficiencies in costs and services. For example, the commercial and technical risks relating to construction,
operation and maintenance can be allocated to the contractor whereas, all direct and indirect political risks can
be assigned to the EVNNPT.
Contract management
Variation: The variations in a turnkey contract include variation in quantity of supply items, increase in the
scope of services and subsequent time extension or increase in contract value. The provisions for variations
should include the owner’s right to vary the works, the contractor’s right to refuse a variation, contractor-
proposed variations, the procedure for variations and rules about disputed variations. The purpose of the
variation provisions is to ensure that the contractor is paid a reasonable fee for any changes in the design and
construction of equipment/ materials and the owner has its right to change the same subject to mutually agreed
rates and time extension.
Termination: A contract may be closed on completion of all supply and fabrication, erection, installation and
successful commissioning of equipment and materials in the scope of work of contractor. However, the contract
should provide for conditions for contractual termination by owner as well as contractor, e.g.: owner’s non-
payment or prolonged suspension of works and contractor’s insolvency or breach of performance. Generally, a
certain cure period is allowed for rectifying the breaches before issuing termination notice.
Payment: Timely payment to main contractor on fulfilment of particular payment milestone is essential in
turnkey contracts since the payments to sub-contractors and vendors are generally linked back-to-back to it.
EVNNPT already has experience in ODA funded turnkey contracts and hence can develop a timely payment
mechanism for domestically funded engagements.
Monitoring: An information system with monitoring responsibilities and responsible point of contacts for
different activities from contractor and turnkey contractor, escalation matrix for different issues need to be
agreed upfront between main contractor and owner so as to avoid unnecessary disputes during execution.
Defect liability: A turnkey contract framework generally specifies defect liability period for the performance
of equipment and materials from the date of issue of the completion certificate. During this period, the
contractor shall, at its own cost and initiative, correct, repair and/or rectify any and all defects and/or
imperfections in the design, fabrication, erection and installation of equipment/ materials. This effectively
transfers the task of defect identification and its resolution from the owner to the main contractor. In case the
contractor fails to resolve the issue with in stipulated timelines, it will be liable for pre-decided penalties.
Quality Control
Reduced efforts in coordination will help in focusing on quality control for project managers. They will be
enhancing quality control of the equipment/ materials and construction processes. Enhanced quality control
does not necessarily mean only attending all types of tests and increased inspections by EVNNPT officials. The
focus of quality control will be on crucial type tests, manufacturing of key equipment, monitoring processes and
ensuring that the transmission system operates within stipulated quality, security and reliability parameters.
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 272
Recommendation#3: Develop a project risk management strategy
Project risk management
Risk is an uncertain event or condition which, if occurs, has a negative effect1 on the envisaged project outputs
and results in issues like time over run, cost over-run, poor quality execution resulting in increased O&M or
poor system availability etc. The power transmission projects, like other infrastructure projects face various
risks in different stages of the life cycle. A risk management plan/ matrix/ strategy should address these risks in
all phases of the project viz., design, approvals, financing, procurement, construction, completion and have
mitigation strategies for various risks.
Benefits of an effective risk management framework
1. Formulation of a realistic project plan in terms of both cost estimates and time estimates;
2. Minimization of risks for a party and /or allocation of risks to the party best able to handle them;
3. Clear contractual terms and conditions and lesser scope of disputes;
4. Effective contingency plans and risk mitigation options;
5. Better financial modelling of projects due to more statistical information of historical risks; and
6. More rational project decisions and risk appetite based on prevailing macro-economic conditions.
Key steps of risk management are identification, assessment, risk allocation and designing response strategies:
1. Risk identification: All possible risks have to be identified at the system studies/ design phase of the
transmission project. Generally, risks are identified based on historic experiences in similar projects.
Since many power transmission projects were already executed and in operation for a long time,
identification of risks in the country’s context is an easier job. As an illustrative example, we have
identified various project risks for a typical power transmission project till commissioning based on our
understanding and multiple interactions with EVNNPT officials later in this approach note.
2. Risk assessment: The degree of likelihood of various risks and possible consequences in case of
occurrence can be assessed using quantitative techniques and qualitative techniques.
a. Quantitative techniques utilize historic data to assess the probability and calculate the impact
of a risk occurrence in terms of either time or money. Various statistical tools and methods are
available to perform complex analysis and ascertain the risks in an objective manner
b. Qualitative techniques are predominantly used to list the likely risk sources and their
consequences, particularly in case of unavailability of historical data. We also suggest adopting
a similar approach in case of risk management matrix for EVNNPT due to lack of data.
Gradually, an information system can be built to accumulate all information of project, e.g.:
scheduled dates of different activities in project, actual dates and reasons for delay (i.e. risks),
cost over-runs, contract variations, changes in scope etc. However, to start with the project risk
1 Positive risks or opportunities are not analysed in this note.
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 273
management matrix has been prepared by providing a subjective risk assessment methodology
i.e. a ratings assigned to both probability and impact of occurrence of risk and calculating an
overall rating for that risk.
3. Risk Allocation: The ideal principle of risk allocation in projects is that all risks should be borne by
the party best able to assess, and manage them or the party with access to hedging options or lowest
costs of bearing the risks. In the sample risk management matrix developed, we have identified the risk
bearer in the current regime.
4. Risk response strategies: Risk response strategies have to be designed for all the identified risks.
Possible strategies are identified in the next section.
Risk response strategies
An appropriate response to any occurrence of all envisaged risks should be
available beforehand. Different risk response strategies are mentioned
below:
Avoidance
This strategy can be adopted in the design phase of the transmission
project if the costs of risks are prohibitive. For example, avoiding high risk
construction approaches or activities, adopting a familiar approach
instead of an untested one, or avoiding an unfamiliar subcontractor may
be examples of avoidance. If it’s known that it involves significantly high
costs for construction/erection of transmission towers in a rainy season in a particular area, then construction/
erection activity can be planned in such a way to increase the activity prior to that season by increasing
resources or revising the construction plan etc.
Transfer
This strategy does not eliminate risk, but only transfers the responsibility of the particular risk to another party.
Risk transfer nearly always involves payment of a risk premium to the party taking on the risk. It includes the
use of different kinds of insurances (Equipment & material delay in supply or damages during different phases,
life & injury risk for officers and labour etc.), performance bonds, warranties, and guarantees. Typically, in case
of a turnkey contract the risk of delays on account of coordination of various schedules of suppliers/ sub-
vendors and erection contractor is transferred to the main contractor from the utility as opposed to the case of
having separate design, supply and erection contractors.
Mitigation
Mitigation of risks means to reduce the probability and/or consequences of an adverse risk event to an
acceptable threshold. Mitigation costs should be appropriate, given the likely probability of the risk and its
consequences. For example, during a transmission line implementation, it is realized that a delay in erection is
a possibility due to a delay in pre-construction activities. In this case, if increasing resources can reduce the
erection time, then a cost-benefit analysis can be performed for increasing costs due to deployment of more
resources vis-à-vis decrease in loss of revenue due to timely completion and revenue.
Acceptance
Avoidance Transfer
Mitigation Acceptance
Risk responses
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 274
Risk acceptance is important for cases where the costs of avoiding, mitigating or transferring the risks to
another party are very high compared to benefits. Active acceptance may include developing a contingency plan
to execute, should the risk occur- the most usual one is to establish a contingency allowance, or reserve,
including amounts of time, money, or resources to account for the risk. The allowance should be determined by
the impacts, computed at an acceptable level of risk exposure, for the risks that have been accepted. Generally
force majeure events and acts of God etc. fall under this category.
Organization framework
We suggest that the planning department of PMB or PTC, as the case may be, undertake the additional
responsibility of preparing and maintaining of risk management matrix and analysis. In case a PMU is set up,
the responsibility of preparing the same can be passed on to it. The risk management matrix should be a
mandatory part of Feasibility Report for every medium and large size-projects over certain value of project costs
(say above 5 billion VND). The threshold value of project cost can be suitably decided by EVNNPT. Any
unforeseen risk faced during a project execution and corresponding risk response strategy adopted has to be
referred by the concerned site personnel (with any suggestion for response) to the concerned Planning
departments/ PMU. Further, a master risk management matrix for all projects executed in a year has to be
summarized by Planning department /PMU (as applicable) along with different risk mitigation measures
adopted. This will act as a reference for future projects.
In this note, we covered risk management of project from conceptualization till commissioning (operational
risks not covered) from the view point of EVNNPT based on our understanding of various project issues faced
by EVNNPT. Since, there is no historical data available to perform a quantitative analysis of risks, we followed a
qualitative approach. Risks are grouped under different heads - design, bidding, construction etc. and their
probability of occurrence and impact is rated in three categories - Low, Medium and High. Finally, an overall
risk rating is provided with product of ratings in both occurrence and impacts of risks. Also, parties bearing the
risk currently and risk response strategies for different risks are provided. Preparing a risk management matrix
before start of the project will act as a preventive measure and help to reduce issues leading to poor quality,
delayed execution and cost over-runs.
Please note that the risk management matrix is a live document that needs to be updated periodically based on
changing base conditions, external & internal factors in various aspects viz., operational, financial, commercial,
legal, regulatory impacting the project.
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 275
Risk management matrix for a transmission project
Risk Description Probability of Occurrence
Potential Impact
Risk borne by
Overall risk rating
Risk Response Strategies
Design Risk
Wrong Design Wrong Design Equipment, Unsuitable technical specifications for equipment
Low High EVNNPT Standardization of designs and technical specifications will reduce the need for designing equipment or formulating specifications for every project. Further, careful scrutiny of concerned EVNNPT departments and hiring of experienced consultants for standardization will reduce the probability of occurrence This risk is transferred to turnkey contractor in case of turnkey mode.
Design Delay Delay in preparation of working designs due to issue with design consultants (non-performance, lack of resources etc.)
Medium Low EVNNPT Standardization will reduce the probability of occurrence. Turnkey mode of execution will reduce the impact as the same can be covered by faster execution by the turnkey contractor
Inappropriate design scheme or layout
Mismatch of designs with site Conditions
Medium Medium EVNNPT Turnkey mode of execution will reduce the impact as the turnkey contractor will be responsible for final working drawings, supply and erection activities.
Bidding Risks
Time over run Time over run in bid process- Preparation of documents, Conduct of bid process and bid evaluation, negotiations etc.
Medium Low EVNNPT This risk cannot be transferred and has to be borne by EVNNPT. However, chance of risk occurrence can be reduced by efficient project management (regular monitoring by PMU is a way to reduce the risk).
Wrong evaluation of bids
Evaluating specifications of same equipment manufactured by different companies
High High EVNNPT Standardization of specifications will reduce the probability of occurrence. However, impact cannot be reduced
Construction Risk
Planning Risk Inappropriate planning of activities Low High EVNNPT Identifying activity timelines as per actual conditions and proper monitoring of timelines. A PMU can perform the project planning using modern techniques like
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 276
Risk Description Probability of Occurrence
Potential Impact
Risk borne by
Overall risk rating
Risk Response Strategies
Critical Path method (CPM) where precedent and successor activities are identified along with linkages, early and late start time, early and late finish times, slack times etc.
Delay in construction
Lack of proper monitoring and slippages by contractor due to variety of reasons like non-performance of erection contractor, delay in supply of equipment, transport, site conditions, lack of access to site, Right of Way issues etc.
Medium High Erection Contractor & EVNNPT (sharing of risk depends on Liquidated Damages & Performance security clauses vis-à-vis lost revenue of EVNNNPT)
Rigorous monitoring of projects with a project management tool by dedicated staff (PMU) and good documentation practices will identify issues and parties responsible for delay. This helps the issue at site to reach the concerned authority for corrective action immediately. Further, segregation of risks and risk allocation upfront with clear contractual terms and conditions will give clear understanding to both contractor and EVNNPT. A standard bidding document for different modes of contract execution will help reduce the risk. Clauses on Penalties for delay and liquidated damages will act as disincentive for contractors
Increase in cost of raw materials
Cost estimate of materials may change due to inflation, market conditions, currency risk etc.
Medium High Supplier The risk is less for short duration projects. However, in case of longer duration projects, the risk is high as steel, copper, aluminium, labour costs can increase which impacts tower parts, conductor, civil foundation and erection services etc. If the contract does not have clauses on Price variation (i.e. proper indexing with international indices), it will result in high bid quotes. But, in case of price indexing clauses, any profit or loss due to increase or decrease in costs may have to be borne by EVNNPT.
Changes in scope Variations in the design, specifications, quantities of equipment/ materials required during construction
Medium Medium Erection Contractor & EVNNPT (sharing of risk depends
Standardization of specifications will reduce the scope for change in designs and specifications. Probability of scope variation is high in a transmission line erection project rather than any supply of
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 277
Risk Description Probability of Occurrence
Potential Impact
Risk borne by
Overall risk rating
Risk Response Strategies
on contractual terms)
equipment or substation projects. Correct preliminary and detailed surveys will reduce the probability of occurrence.
Delay in inspection and testing
Delay in testing and commissioning Low Low Supplier & EVNNPT (sharing of risk depends on Liquidated Damages & Performance security clauses vis-à-vis lost revenue of EVNNNPT)
This risk can be mitigated by developing an information system through which inspection calls can be logged by the vendors and their completion time, reasons for delay can be monitored. A PMU can monitor the system and pursue for early and successful completion of inspection. An incentive and penalty mechanism may be devised with good ratings for vendors with punctual calls and successful completion and habitual offenders can be penalised monetarily and in severe cases, blacklisted from participating in future bids
Payment Risk Delayed payments to contractors, resulting in contractors delaying/ stopping the work.
Low High EVNNPT Payment mechanism should be clearly mentioned and followed. The requisite documents for payment release should be specified. Regular monitoring by PMU will reduce the chance of occurrence
Financing Risk
Delay in Financial Closure
Tying-up financials required for the construction of the project
Low Medium EVNNPT Better credit ratings should be maintained with the banks by prompt payment of instalments.
Increase in interest costs, forex risk
Construction cost estimates may change because of increase in interest rates and forex rate (in case of foreign loan)
High High EVNNPT The risk is relatively less for short duration projects. However, in case of longer duration projects, the risk is high. The forex risk can be mitigated by hedging the foreign component of loan value with a financial institution after doing a cost-benefit analysis
Other Risks
Land Recovery & Right of way
Delay in land acquisition and right of way due to resistance from public on account of multiple
High High EVNNPT Most of the activities of Land acquisition fall outside the purview of EVNNPT and is monitored by the Government Act. Recent Land Law has better
Recommendation#3: Develop a project risk management strategy
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 278
Risk Description Probability of Occurrence
Potential Impact
Risk borne by
Overall risk rating
Risk Response Strategies
reasons compensation norms. The project execution authorities should follow the norms and regulations and interact with People Councils and committees and follow the prescribed approach (notices, wide publicity, sufficient notice period, prompt deposit of compensation etc.)
Delay in approvals
Delay in receiving approvals for each stage of project from the higher authorities
High Medium EVNNPT Optimization of process by merging certain steps (e.g.: FS & DTD phases) and also devolution of powers to subsidiaries
Force Majeure & other disturbances
Occurrence of an unexpected events or act of God; Labour disputes or any strife
- High Erection Contractor, Supplier & EVNNPT (sharing of risk depends on contractual terms)
- Clear and detailed clauses on force-majeure conditions, consequential termination as well as financial obligations of both the parties should be in the bid document/ contract
Delay due to Disputes
Any legal disputes delaying the contract execution
Low High - Unambiguous dispute resolution mechanism should be available in the contract documents. Generally conciliation, mediation, arbitration and court of law are ways for settling disputes in that order.
Index:
Probability of Occurrence Potential Impact Risk rating Low Low/Medium Low Medium Low Low High Medium Medium Medium High Low Medium High High High Medium/High
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 279
Recommendation#4: Developing IT tools for project monitoring, inspection and online procurement
No deliverable as agreed with ADB/NPT.
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 280
Recommendation#5: Merger of FS & DTD phases
Drivers for the recommendation
While reviewing and discussing the existing project planning processes with various departments of EVNNPT
and its subsidiaries, it was observed that, on an average, it takes around three years from issue of project
allotment letter to approval of Detailed Technical Design (DTD) in case of EVNNPT transmission projects
which is high and needs to be reduced for speedy implementation of projects. There are multiple factors
contributing for this delay- heavily centralized decision making process with PMBs/ PTCs having no powers of
approval and requiring multiple rounds of approval from MoIT; lack of standardization in technical
specifications and bid documents etc. The merger of Feasibility Study (FS) and Detailed Technical Design
(DTD) phases, in addition to our other recommendations will reduce this time significantly. This has been
suggested based on similar international practice followed by leading international transmission utilities. It
may be noted that the focus of this note is only on merger of activities of FS and DTD phases at PMB/PTC level.
Overall optimization of planning process is covered in another approach note of investment planning.
Current process
The FS is prepared by the PMBs/ PTCs (as the case may be) and submitted to the IMD in EVNNPT for review.
The FS comprises of the technical studies, impact assessment studies and financial and economic analysis. The
current process in FS & DTD phases in projects executed by PMB and PTC are provided in Figure 1 and Figure 3
respectively. In the FS phase, following components are covered:
1. Line route survey with three options and suggest optimal route
2. Tower spotting, layout and Estimate bill of quantities of equipment and material needed
3. Basic design of equipment
4. Total investment cost and financial analysis such as NPV, IRR, Benefit-to-Cost ratio
5. Environment Impact Assessment (EIA) and Social Impact Assessment and Resettlement to minimise
land needs and adverse impact on local people and environment.
6. Other aspects like Fire prevention, Telecommunication etc.
After FS approval, DTD consultants are selected and they prepare the detailed engineering/ technical designs
and specifications along with bidding documents. Only the urgent and critical projects or small augmentation
projects will not require DTD. We suggest merging both the phases into a single phase and leaving the detailed
working designs / construction design drawings to the selected contractor, as part of his responsibility.
In our approach note related to investment planning on “Process Improvement”, we have already shared
international practices/activities involved in planning phase of couple of utilities.
The relevant process highlights of the feasibility study process of POWERGRID, Indian Central Transmission
Utility and Inter-state Transmission Licensee, (which owns majority of inter-state lines) is provided below for a
quick reference:
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 281
Proposed process
We are proposing the revised process, considering similar global project planning practices followed. Following
tasks will be included in our proposed process for Feasibility Report and Detailed Technical Design.
1. Line route survey for the finalized system with three options and suggest optimal route;
2. Design, technical specifications and construction standards for foundations, towers, cables and
insulators, conductors, transformers, reactors, circuit breakers and other key equipment of the project.
Availability of standardised designs, specifications and drawings will significantly reduce the time
required for this step;
3. Quantities/numbers of different types of tower structures, poles, insulators, length of cables&
conductors, circuit breakers, isolators etc. indicated as the Bill of quantities (BOQ) schedule;
4. Cost estimation as per BOQ prepared of the various system elements (such as cables, conductors,
transformers, switchgears, capacitors, lightning arrestors and insulators, the control and
communication system, engineering and project management, supervision and contingencies);
5. Financial analysis for assessing financial viability of project and proposed capital structure for the
project (type of funding-domestic or foreign, amount, equity etc.);
6. Project packaging to attract suitable competition facilitating cost effective procurement. The size &
scope of the different packages depends on magnitude & location of project. If turnkey or part turnkey
procurement with suitable norms for packages along with a list of pre-approved vendors for different
equipment is adopted, time and cost for procurement can be optimized with good competition. The
standardised designs along with project implementation plan and schedule for the project considering
possible contingencies;
7. Statutory and environmental clearances required for project and the progress of the same. At least
preliminary applications should have been made by this stage; and
POWERGRID allots projects for execution, post approval of the allocation of transmission system by
empowered committee. Following steps are being followed, once project is allotted for execution.
1. A route survey is conducted and a techno-commercially & environmentally optimal route
alignment is chosen
2. A detailed project report is prepared consisting of all descriptions, technical details and cost
estimations. It will be prepared by the cost engineering department in coordination with
corporate planning, finance, contracts & procurement, and engineering etc.
3. The Chairman or Board of Directors of POWERGRID or the Central Electricity Authority (CEA)
will be the approving authority for technical portion depending on cost of the project. Similarly
investment proposal will be approved either by BOD or Ministry of Power depending on cost of
the project.
4. Post requisite approvals, the bid documents for packages will be released for the purpose of
tendering which will have basic standard designs, specifications, qualification criteria etc.
5. The detailed engineering of layout designs, equipment designs and tower drawings will be
completed by the contractor and approval obtained from POWERGRID.
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 282
8. System operation requirements, based on applicable laws and grid code. Operation and Maintenance
plan include facilities such as protection, communication, measurement, telemetry and interface
equipment etc.
The consultants will also prepare bid documents after their submission of packaging plan, BOQ and cost
estimates. The revised process post-merger of FS & DTD phases for PMB and PTC projects is presented in
Figure 2 and Figure 4 respectively
Implementation support
To facilitate the merger of these two phases, a high level committee of Vice President and Directors has to be
formed from all key departments involved in planning function in EVNNPT- CPD, IMD, F&A, Technical and
Procurement along with Directors of all PMBs and PTCs. This committee will be headed by Vice President
(Operation & Investment), EVNNPT. Secretarial support will be provided by CPD of EVNNPT. Suggested
composition of the committee is as follows:
Objective of the committee: To design a process that merges current FS &DTD phases thereby reducing the
time taken for iterative approvals.
Timelines: The committee should work in a time bound manner with a target date of achieving its objective
(say an year). The committee should meet at least once in two months till the objective is achieved.
Steps/Activities: The Committee members can form a working group in their respective departments/
subsidiaries to gather inputs on the merger of these two phases. These inputs can be debated in the bi-monthly
meetings and a final process flow has with responsibilities of each department along with work flow to be
designed. The above suggested process can be taken as a guideline and the committee may discuss and finalize
the detailed aspects. Also, the requisite changes in the policy level documents may be identified (decrees, etc.)
and consequential changes may be put up for approval of concerned authorities.
The final process may be sent to President& CEO, Management Board of EVNNPT and subsequently to
concerned authorities of EVN, MOIT for approval.
Vice President (Operation & Investment),
EVNNPT
Director, CPD,
EVNNPT
Director, F&A,
EVNNPT
Director, IMD,
EVNNPT
Director, Technical, EVNNPT
Director, Procurement,
EVNNPT
Directors of PMBs and
PTCs
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 283
Feasibility Study and Detailed Technical Design- PMB Projects
NPT/ EVN & Ministries & DeptsPMBConsultants
FS consultants prepare implementation plan , basic design,
conduct route survey ,system studies, EIA , SIA, resettlement issues & an
investment project proposal
Second stage approvalApproval of EIAR by DoNRE through CMD
Approval of Feasibility study by EVN/ MoIT/ NPT board depending on value through IMD
Evaluation dept reviews all inputs of FS by itself or with help of other consultants and submits to NPT
Land Acquisition / recovery process
Project allotment letter to PMB Procurement process for selection of FS
Consultants
Is project urgent/ critical/
small valueNo
DTD Consultants to prepare detailed technical design
Approval of detailed design by Technical Dept of NPT;
bid documents by Procurement Dept of NPT
Evaluation dept reviews with inputs from other departments /
other consultants
Procurement process for selection of DTD Consultants
Procurement process for selection of
equipment /erection contractor
Procurement plan with package prices, schedule, funding source, bidding parameters by Planning dept
Approval of Procurement plan through CPD of NPT
DTD Consultants to prepare bidding documents
Procurement Department reviews and forwards for
approval
Approval of bid documents through
Procurement Dept of NPT
Is project urgent/ critical/
small valueNo
Procurement Department prepares bid documents&
forwards for approval
Yes
Yes
Figure 1: Current FS & DTD processes in PMB projects
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 284
Proposed merging of Feasibility Study(FS) and Detailed Technical Design(DTD) - PMB Projects
NPT/ EVN & Ministries & DeptsPMBConsultants
FS-cum-DTD consultants prepare ( as required) Implementation plan
Line Route survey and optimal route
EIA , SIA, resettlement issues
Detailed design ( possible after standardization of drawings& designs)
Feasibility report with detailed cost estimates, financial analysis
Procurement plan (packaging)* , bid documents along technical specification
*Procurement plan and bid documents by planning dept of PMB in case of urgent works
Approvals EIAR by DoNRE through CMD
Procurement plan through CPD of NPT
Design by Technical Dept of NPT
Bid documents by Procurement Dept of NPT
All parts of FS by EVN/ MoIT/ NPT board depending on value through IMD
Evaluation dept reviews all inputs of FS by itself or with help of other consultants/departments and submits to NPT for final
approval
Land Acquisition / recovery process( ( as
required)
Project allotment letter to PMB
Procurement process for selection of equipment /
erection contractor
Planning dept calls for bids
Planning dept evaluates and selects successful bidder; sends for approval
Consultants submit bids
Approval of consultants by President & CEO/ NPT board through CPD
Figure 2: Proposed Process flow for PMB projects post-merger of FS&DTD phases
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 285
Feasibility Study & DTD – PTC Projects
NPT/ EVN & Ministries & DeptsPTCConsultants
FS consultants prepare implementation plan , basic
design, and other aspects required for an investment project proposal
Second stage approvalApproval of Feasibility study by EVN/ MoIT/ NPT board depending on value
through IMD
Construction investment dept reviews all inputs of FS by itself or with help of other
departments and submits to NPT
Consultant prepares tentative project cost estimates
First stage approval (Technical feasibility) by MoIT
through IMD of NPT
Planning dept reviews with help of Construction investment dept and sends for
approval
Land recovery process ( Rarely
required)
Requirement of project identified by
PTC
Procurement process for selection of FS Consultants
Is project urgent/ critical/
small valueNo
DTD Consultants to prepare detailed technical design
Approval of detailed design by Technical Dept of NPT;
Procurement process for selection of
equipment /erection contractor
Construction investment dept reviews with inputs from other
departments / other consultants
Procurement process for selection of DTD Consultants (Rarely required)
Procurement plan with package prices, schedule, funding source, bidding parameters by Planning dept
Yes
Approval of Procurement plan through CPD of NPT
Procurement process for selection of Cost Estimates Consultants
DTD Consultants to prepare bidding documents
Planning Department reviews and forwards for
approval
Approval of bid documents through
Procurement Dept of NPT
Is project urgent/ critical/
small valueNo
Planning Department prepares bid documents&
forwards for approval
Yes
Figure 3: Current FS & DTD processes in PTC projects
Recommendation#5: Merger of FS & DTD phases
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 286
Proposed merging of Feasibility Study(FS) and Detailed Technical Design(DTD) - PMB Projects
NPT/ EVN & Ministries & DeptsPMBConsultants
FS-cum-DTD consultants prepare ( as required) Implementation plan
Line Route survey and optimal route
EIA , SIA, resettlement issues
Detailed design ( possible after standardization of drawings& designs)
Feasibility report with detailed cost estimates, financial analysis
Procurement plan (packaging)* , bid documents along technical specification
*Procurement plan and bid documents by planning dept of PMB in case of urgent works
Approvals EIAR by DoNRE through CMD
Procurement plan through CPD of NPT
Design by Technical Dept of NPT
Bid documents by Procurement Dept of NPT
All parts of FS by EVN/ MoIT/ NPT board depending on value through IMD
Evaluation dept reviews all inputs of FS by itself or with help of other consultants/departments and submits to NPT for final
approval
Land Acquisition / recovery process( ( as
required)
Project allotment letter to PMB
Procurement process for selection of equipment /
erection contractor
Planning dept calls for bids
Planning dept evaluates and selects successful bidder; sends for approval
Consultants submit bids
Approval of consultants by President & CEO/ NPT board through CPD
Figure 4: Proposed Process flow for PTC projects post-merger of FS&DTD
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 287
Recommendation#6: Develop a strong and focused project management unit
Requirement of a Project Management Unit
There is a significant growth in the transmission network of Vietnam since 2008 as lines increased by 40% &
substation capacity increased by 62%. Further, EVNNPT is planning to augment its transmission assets
significantly during 2016-30, viz. ~9,500km lines & 71,000 MVA transformation capacity @500 kV level and
~16,000 km lines &135,000 MVA @220 kV level. It is imperative that, to attain this level of system
strengthening in given time frame and estimated budget, timely completion of various activities of different
projects is mandatory. However, currently, many controllable and uncontrollable factors like delay in land
acquisition, resistance from general public, lack of proper monitoring methodology (IT tool), long time for
various approvals and pre-construction activities are delaying project execution of transmission projects of
EVNNPT resulting in time and cost overruns.
In the current organization structures of EVNNPT and its subsidiaries, there is no focus on project management
across the different activities of project life cycle. We also faced considerable difficulties in collecting historic or
current data of various project management aspects, in particular regarding actual and schedules dates of
various activities, reasons for delays, time and cost over-runs of project etc. There may be a significant gap in
historic project data management. We felt the need for establishing a Project Management Unit (PMU) at
EVNNPT level.
As per our interactions with officials of EVNNPT and its subsidiaries, we have designed a structure that utilizes
existing organizational resources as well as provide flexibility to hire new resources, if required. Our suggested
structure for PMU is briefly mentioned below.
Figure 5: Overall structure of PMU
Director (CMD) will be the head of the PMU. A new Deputy Director with at least two experts as Project
Management Officers (PMOs) will be performing the designated roles of PMU structure at EVNNPT level. A
new Deputy Director is required since the current three deputy directors reporting to Director (CMD) and the
associated experts are already overloaded with their current responsibilities (viz. approval of DoNRE, testing &
inspection etc.). Further, all the Deputy Directors of all PMBs/PTCs will be assisted by at least one PMO for
performing the designated roles of PMU structure at PMB/PTC level. The number of PMOs can be decided
depending on number of construction projects to be monitored and the envisaged work load. Manpower
requirement of PMOs can be managed either by identifying existing experts with lighter work load, or by
recruiting new employees at a junior level.
Director (CMD) PMU head, EVNNPT
PMU, EVNNPT
PMU, NPMB
PMU, CPMB
PMU, SPMB
PMU, PTC1
PMU, PTC2
PMU, PTC3
PMU, PTC4
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 288
PMU officials are expected to interact with concerned officials, vendors, contractors, consultants to understand
the issues in detail and present viewpoints of the parties concerned in review meetings to top management.
Figure 6: Interactions of PMU
The roles and responsibilities of PMU officials are segregated into corporate and regional levels, viz. EVNNPT
and PMB/PTC.
PMU at PMB/PTC level
Directors of all the PMBs/ PTCs have to identify at least one official at expert level for each deputy director of
the PMB/PTC. Number of required PMOs assisting a Deputy Director will be decided by the Director PMB/PTC
depending on the number of projects to be monitored.
Roles and responsibilities of officers at various designations in the PMU structure are defined below:
Designation Activities
Project Management Officers, PMB/PTC
The roles and responsibilities of PMO at PMB/PTC are mentioned below. The number of PMOs at PMB/PTC will be decided by the Director of that particular PMB/PTC depending on the workload (i.e. number of projects being monitored)
Project Management Unit (PMU)
EVNNPT
CPD, IMD, CMD, Technical,Materials, Procurement etc
PMBs/ PTCs
Technical, Materials, Resettlement, Planning, Procurement, F&A, Evaluation etc
Design consultants, different suppliers,
contractors, vendors
Others
Other approving authorities (e.g.:
ministries & concerned depts, People councils)
Director of PMB / PTC
Deputy Director - 1
At least an expert dedicated as PMO
Existing Experts
Deputy Director - 2
At least an expert dedicated as PMO
Existing Experts
Deputy Director - 3
At least an expert dedicated as PMO
Existing Experts
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 289
Designation Activities
Prepare requisite plans (detailed project plan, procurement plan, resourcing requirements etc.). While designing project plan, modern techniques like Critical Path method (CPM), Program Evaluation Review technique (PERT) charts can be adopted
Prepare risk management matrix of different projects
Monitor procurement process for selection of consultants, contractors, vendors and highlight delays
Monitor work progress of Design and FS consultants, EIAR consultants
Monitoring of various activities in project execution vis-à-vis agreed detailed schedule (L2 network) and identify delays along with reasons for the delays.
Interact with concerned F&A departments regarding payment of invoices and expedite completed invoices; educate contractors and site engineers on various standard forms and requisite proofs to enable speedy processing of bills
Prepare evaluation report consolidating various steps in project along with reasons for deviation from original schedule and costs. This will act as historical data for future projects
Deputy Director PMU, Nodal officer at PMB/PTC
Consolidate report from PMO(s) and follow up with concerned parties to resolve the issues.
Provide monthly consolidated project highlights and major issues report to Director, CMD with a copy to concerned Director of PMB/PTC
Director, PMB/PTC Guidance to concerned deputy director and support in resolving issues with contractors
PMU at EVNNPT level
Organization structure
Roles and responsibilities of officers at various designations in the PMU structure are defined below:
Designation Activities
Project Management Officers, EVNNPT
Follow-up to ensure speedy turnaround time for various approvals in a prompt manner (project plan, procurement plan, EIAR, Feasibility Study etc.)
Monitor status of land recovery and Right of way issues.
Developing procedures, templates for information gathering from different
Director of CMD (also Head - PMU)
Deputy Directors - 1, 2, 3 and
associated experts
New Deputy Director - 4 (for
PMU)
PMO#1 PMO#2
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 290
Designation Activities
departments
Identify common pain areas in project execution and prepare an action plan beforehand that can be applicable across different projects
Identifying good project management methodologies based on experience and document the same as best practices for approval of concerned authorities
Assist Deputy Director, PMU, EVNNPT in delivering any of his/her responsibilities
Deputy Director#4, PMU, EVNNPT
Consolidate inputs from PMUs of various PMBs/PTCs and present an exception summary report to top management in review meetings
Follow up with other relevant departments (Procurement, Technical, Finance & Accounts, Administration etc.) in EVNNPT for resolving any issues in a project
Organize an yearly meeting /conference with various contractors, consultants and sub-vendors to understand the key concerns and submit the findings to the top management
Director (CMD), EVNNPT
Take direct action or direct concerned officials to resolve issues highlighted in exception report
Report to concerned authorities in case of any issues impacting projects that are outside his/her authority.
Tools & methodologies
PMB/PTC and EVNNPT officials are already conversant with preparing project plans using Microsoft Project
(MS Project). A typical project plan for a transmission project using MS Project is provided subsequently in
Figure 7: Sample Project plan of EVNNPT. Preparation of detailed project plan for all projects is a key role of
PMU. To start with, PMU officials can use MS Project to prepare the plan which should incorporate all the
activities involved and the time for completion of each activity. PMU officials can use methods like Critical Part
Method (CPM), Program Evaluation & Review Technique (PERT) for planning and scheduling. For example,
steps in CPM method are
1. Activity identification: Identify activities in different phases of the project from inception to
commissioning;
2. Activity precedence identification: Identify the dependent activities i.e. activities that cannot start until
the completion of another activity (say, Bill of quantities and costing of projects cannot start until the
completion of survey activity or Notice inviting tender cannot be floated till approval of bid
documents);
3. Network construction: The detailed project plan can be prepared using MS project. Subsequently, time,
cost and resource implications of a various activities in the plan are decided; and
4. Critical Path: Critical path determines the shortest possible time to complete the project. It is the
sequence of activities that add up to the longest overall duration. PMU can prepare a detailed list of
activities with help of concerned departments with their early and latest start and finish times.
Dependencies between different activities are already identified. This will help in identification of
critical path.
The contractor is also required to prepare a detailed schedule of activities for completion of work within time
frame for approval of EVNNPT. The actual execution timelines of different activities will be regularly monitored
against this schedule.
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 291
Monitoring frequency: PMOs will be monitoring weekly/ bi-weekly / monthly progress of pre award and
post award activities of projects, as decided at the start based on criticality of project. Progress monitoring
reports regarding status of projects will be shared as summary reports to top management.
Reports: Various status reports need to be generated by the PMU officials for the purpose of project status
reporting to top management. The templates of such reports need to be developed and standardized by the
PMU officials. Templates and reports with common interest parameters cost, budget, loading of resources that
need to be monitored can be standardised for all the common packages like civil and electrical erection works of
transmission lines, supply of conductor, insulators, transformers and reactors. MS Project has capabilities to
track scheduled and actual values of timelines of different activities, budget spent, loading of resources etc.
Since EVNNPT officials are already conversant with MS Project, these reports may be developed using the same
tool. PMOs at PMB/PTC will generate these reports for their respective PMB/PTC and these will be
consolidated by PMOs at EVNNPT and circulated to the top management in various review meetings.
Information sources: The preliminary source of information for project status monitoring will be the
“Project management software” being developed/ implemented. Till the time it is not developed or there are
areas where software does not provide information, PMOs/experts will interact with concerned departments
and obtain information. Standard templates for accessing information will be prepared by PMOs for gathering
information from departments where it is not available in the software. Information can be accessed by via e-
mail from all the concerned officials. PMU officials can also visit project sites in case of necessity.
Implementation support from EVNNPT: An internal circular has to be issued mandating prompt and
accurate response (to the extent possible) from all the concerned departments and officials to the queries and
information sought by PMU officials. A list of nodal persons from these departments and all contact details will
also be mentioned in the circular along with the list of PMU officials and their contact details. PMU officials
may be provided separate computer with an internet connection.
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 292
Figure 7: Sample Project plan of EVNNPT
Recommendation#6: Develop a strong and focused project management unit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 293
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 294
Part-C (iii): Transmission pricing
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 295
Recommendation#1: Conduct training on principles of regulatory economics and international practices
Summary
Title of the training: Training on principles of regulatory economics and international practices
Date & Time: 07 October 2014, 9.00 am - 12.00 noon
Venue: Seminar Room, Fifth Floor, EVNNPT, 18 Tran Nguyen Han, Hanoi
No. of participants: 4
Training material: Refer Appendix 9 -
List of participants
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 296
Recommendation#2: Support EVNNPT in drafting a proposal to ERAV for specific modifications in the existing transmission pricing regulations
Context
The Ministry of Investment & Trade (MoIT) and Ministry of Finance (MoF) have promulgated regulations
which guide the process and method of determining the transmission charge payable to the EVNNPT by the
users of the transmission system. The primary regulation that governs the determination of transmission
charge is Circular No. 14/2010/TT-BCT dated 15 April 2010 (amended by Circular No. 3/2012/TT-BCT dated 19
January 2012). It sets out the detailed methodology for calculating the transmission revenue and charge along
with procedures and timelines to be followed for the submission, calculation, review and approval of the
transmission revenue and charge by stakeholders namely EVNNPT, EVN, EPTC, NLDC, ERAV and payers of
transmission charge.
NPT is facing certain financial and procedural bottlenecks due to specific provisions of the prevailing
regulations. Also, EVNNPT is unable to comply with certain provisions of the regulations due to ambiguity in
the said provisions of the regulations or certain internal difficulties. Hence, EVNNPT has decided to identify
such provisions, evaluate its impact on EVNNPT’s performance, compare them with global practices and
propose appropriate amendments for consideration by ERAV / MoIT.
In this context, the following section captures some of the key provisions of the existing regulations (including
laws, decisions, decrees) governing the transmission pricing framework in Vietnam and presents a case for their
review and amendment. Such analysis is supported by select global practices followed in South East Asian
countries such as India, Malaysia and Philippines. It aims at providing an indication towards the
recommendations to be made. Key issues are as discussed below.
Issue#1: Inadequate Return on Equity
Return on Equity (RoE) as the name suggests is the regulated return allowed to the investors/ equity holders of
the regulated entity. The rate is determined by the regulator after taking into consideration a multitude of
factors namely the prevailing market risk premium and beta value as well as the normative Debt:Equity ratio.
Alternatively some regulators allow Return on the Regulatory Asset Base (comprising of equity and debt), while
not allowing interest on debt (long-term loans) separately.
Description of the existing provisions
Circular No. 14/2010/TT-BCT recognizes the need to allow a return to the EVNNPT in its estimation of total
revenue requirement and provides for profit from power transmission as part of the capital cost. The formula
for determining the Total Capital Cost is provided as follows.
1. Total transmission capital cost in year N (NTTCAPC ) is determined by the following equation:
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 297
NLVDHKHTTCAP LNCCCNNN
Where:
NKHC : Total depreciation cost of fixed assets in year N (VND)
NLVDHC : Total long term-loan interest charge and associated fees for loan taking, to be paid in year N
for transmission assets (VND)
LNN: Allowable profit from power transmission in year N (VND)
2. Further the allowable profit for year N (LNN) is determined by the following equation:
LNN = VCSH,N × ROEN
Where:
VCSH,N: Average of equity as of December 31st of year N-1 and estimated equity as of December 31st of
year N (VND)
ROEN: Rate of return on the EVNNPT’s equity (%), to be determined to ensure financial criteria for
investment and development of transmission network, including Self Financing Ratio (SFR) and Debt
Service Coverage Ratio (DSCR) which should gradually increase to reach 25% and 1.5 times
respectively.
Even though the provision exists in the regulation, the same is not being mandatorily allowed as part of
transmission charge by the ERAV. Also, the regulation does not specify a fixed % of equity as return on equity
(profit) because of which EVNNPT is unable to assess absolute amount of RoE in a particular year, impacting its
ability to plan self-financing (equity infusion) for new investments.
Rationale for proposed amendments
The proposed amendments suggested above are based on two factors:
1. The shortcomings in the existing regulations (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below:
a. Regulation allows RoE, as part of the permitted capital cost, to cover the cash (equity) costs of
new investments, but it does not specify the % of RoE. This ambiguity leaves the provision open
for manipulation and allowed or disallowed as deemed fit.
b. ERAV has been allowing very low RoE to EVNNPT in the past. Even in 2014 the allowed RoE
was only 1% which means a post-tax RoE of 0.75%. This is a very low % by any market standard
return and will not satisfy any cash needs of the utility nor satisfy requirements of the investors
and bankers.
c. Even Self Financing Ratio (SFR) and Debt Service Coverage Ratio (DSCR) were not favourable
during the period between 2009 and 2011. Subsequently, there was an improvement in these
parameters in 2012, but the same was due to significant increase in asset base due to
revaluation of assets (increase of 15,277 billion VND in asset value).
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 298
2. A clear understanding of the importance of allowance of RoE, backed by provisions made by
comparable economies in the region. Presented below is a comparison of the approach followed by
India, Philippines and Malaysia on the provision of Return on Equity/ Regulatory Asset base.
India Philippines Malaysia
Fixed post-tax rate of 15.5%
Additional 0.5% for timely completion of the project
Mandatorily included in ARR
Income tax on RoE is allowed separately
Return = WACC x RAB
Asset revaluation undertaken prior to each RP
Asset revaluation done based on optimised depreciated replacement cost
WACC is with pre-tax cost of debt
WACC = reE/V + rdD/V
Return = WACC x RAB
Return is based on a benchmark efficient WACC
If the utility is able to structure capital requirements such that the actual cost of capital is lower than the regulated WACC, the financial benefit is retained by the business
WACC under IBR (FY2014-2017) is 7.5%
The above practice followed by comparable economies in terms of maturity of the transmission industry, throws
light on the approach followed by all three regulators to provide for a regulated assured return. While in India
the regulator allows a stipulated return on equity and interest expense on long-term loan capital separately, the
regulators in Philippines and Malaysia allow for a composite return on the regulated asset base covering equity
and long-term loan capital.
Description of proposed amendments
Regulated utilities should be allowed to recover their cost to do business and earn a return on invested capital
(both, equity and debt). This return can be ploughed back into the business to enable further investment for
meeting demand growth and improving quality of service. The rate of return on equity should be fixed such that
it will not only attract investment and generate sufficient resources for further growth in the sector but also to
take care of the consumers’ interest.
The following pointers need to be considered while arriving at the % RoE.
1. Regulation calls for RoE to be such a % which will gradually achieve a SFR >= 25% and DSCR >= 1.5;
2. ERAV may undertake a study of appropriate return to be allowed based on market risk premium, beta
and D:E ratio;
3. Increasing equity base through asset revaluation is a notional adjustment and does not amount to real
flow of funds. Hence allowing RoE will ensure available funds to plough back in new projects; and
4. Some of the approaches available for ERAV to undertake the assessment of RoE are; i) Dividend
Growth Model/ Discounted Cash Flow Model; ii) Price/Earning Ratio Method; iii) Risk Premium
Approach; and iv) Capital Asset Pricing Model (CAPM).
Based on the above consideration, the ERAV may determine a fixed % of RoE (either pre-tax or post-tax), which
shall be mandatorily allowed to form part of the ARR of EVNNPT. Making such a provision is essential for the
financial health and credibility of EVNNPT. This will also provide credibility to the EVNNPT to secure sufficient
funds at reasonable interest rates from bankers for future investments.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 299
The estimated potential impact of allowance of fixed RoE on EVNNPT’s profit and revenue for the year 2014 is
shown in the following chart. The chart depicts the revenue (in billion VND), profit (in billion VND) and the %
increase in revenue for year 2014 under five scenarios as compared to the revenue figures for the year 2013. The
five scenarios considered are 1) 0% RoE (last year); 2) 1% RoE (current year); 3) 4% RoE (as asked by EVNNPT
in its petition); 4) 10% RoE (interim scenario); and 5) 16% RoE (potentially desirable).
The two graphs indicate the growth in revenue as well as in the DSCR and SFR due to inclusion of various % of
RoE as part of the total transmission revenue requirement. It can be seen that a desired SFR of 25% can be
achieved only at a ROE of higher than 10%.
27% 29%
35%
49%
62%
0%
10%
20%
30%
40%
50%
60%
70%
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Scenario-1(RoE=0%)
Scenario-2(RoE=1%)
Scenario-3(RoE=4%)
Scenario-4(RoE=10%)
Scenario-5(RoE=16%)
% I
nc
re
as
e
Bil
lio
n V
ND
Growth in Revenue and Profit under five RoE scenarios
Revenue (billion VND) Profit (billion VND) % increase in Revenue
1.74 1.78
1.90
2.13
2.36
13.9% 14.9%
18.0%
24.3%
30.6%
0%
5%
10%
15%
20%
25%
30%
35%
-
0.50
1.00
1.50
2.00
2.50
Scenario-1(RoE=0%)
Scenario-2(RoE=1%)
Scenario-3(RoE=4%)
Scenario-4(RoE=10%)
Scenario-5(RoE=16%)
%
No
. o
f ti
me
s
Change in DSCR and SFR under five RoE scenarios
DSCR SFR
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 300
Issue#2: Depreciation charging methodology
It is accepted in regulatory regime that the depreciation represents service to capital subscribed and normally
considered a cash flow available for repayment of long-term loan. There should be enough cash flow available to
meet the repayment obligations of the transmission licensee during such time as average loan repayment
tenure.
Description of the existing provisions
Circular No. 14/2010/TT-BCT lays down the below formula for determining the Total Capital Cost for EVNNPT
of which deprecation on fixed assets is an integral part.
1. Total transmission capital cost in year N (NTTCAPC ) is determined by the following equation:
NLVDHKHTTCAP LNCCCNNN
Where:
NKHC : Total depreciation cost of fixed assets in year N (VND)
NLVDHC : Total long-term loan interest charge and associated fees for loan taking, to be paid in year N
for transmission assets (VND)
LNN: Allowable profit from power transmission in year N (VND)
Total depreciation of fixed assets in year N (NKHC ) is determined in accordance with the provisions on duration
of use and depreciation method for fixed assets as specified in Circular No. 203/2009/TT-BTC dated 20
October 2009 of the Ministry of Finance which provides guidelines on the management, utilization and
depreciation of fixed assets and any subsequent additions or revisions thereof.
For transmission assets, the time for depreciation is different from what is specified in Circular No.
203/2009/TT-BTC, the EVNNPT shall develop a regime for depreciation of those assets and submit to the EVN
for consideration; the EVNNPT shall also submit that document to the ERAV for adoption before submitting to
the Ministry of Finance for issuance.
Rationale for proposed amendments
The proposed modifications suggested as above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below:
Summary: MoIT / ERAV may determine a fixed % of RoE, which shall be mandatorily allowed
to form part of the Annual Revenue Requirement of EVNNPT. If allowed RoE is post-tax,
income tax on RoE should be allowed separately.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 301
a. The regulation allows for depreciation on re-valued asset base. In such cases depreciation is
allowed on assets which have already been fully depreciated once, thus amounting to double
charging of depreciation.
For example: useful (technical) life of transmission lines is typically 25-35 years, but for tariff
purpose it is taken as 10 years. If revaluation is allowed, depreciation is charged on the re-
valued base for say another 10 years. This in effect leads to double recovery of the depreciation
for the same asset.
b. The depreciation charging mechanism is also not in line with the repayment schedule of long-
term loans (debt) taken. For assets which are not re-valued, the typical life is considered to be
between 8-12 years while the loan repayment tenure varies between 12-30 years. On the
completion of the life of the asset, there remains no revenue (in terms of recovery through
depreciation) to repay the loans for which repayment of principal component for another 0-18
years is outstanding.
2. Provisions made by comparable economies in the region, on depreciation charging mechanisms are
presented below.
India Philippines Malaysia
Cash flow available to meet the repayment obligations
Useful life Line - 35 years Sub-station - 25 years
Straight line method and at specified rates for first 12 years; remaining depreciation spread equally over balance life
Depreciation rates for regulatory (tariff) purpose are different from those used for book keeping purpose
Depreciation calculated on straight line basis
Depreciation = Replacement cost/Regulatory life
Replacement cost = optimised depreciated asset value; hence no excess depreciation
Economic life of asset expires when cost of O&M > replacement cost
Regulatory life = weighted average of economic life of specific asset category
Depreciation calculated on straight line basis
Commission to benchmark economic life determination with global best practices
To also obtain Independent engineering estimate for useful life estimation
The above approaches followed clearly illustrates that depreciation is definitely linked to debt repayment (asset
replacement cost) ensuring adequate cash flow for repayment of debt. Further, the useful life of asset used for
regulatory purpose should be linked with technical / economic life of the asset and shall be determined based
on engineering estimates and expert opinions. It is also pertinent to note that the depreciation rates for
regulatory (tariff) purpose could be different from those used for book keeping purpose as the objectives of both
the computations are different. The following table shows framework for computing depreciation for
transmission line assets in India:
Purpose Life (years)
Depreciation method
Depreciation Rates (per annum)
Salvage value (% of gross asset value)
Regulatory (as per CERC tariff regulations 2014)
35 SLM (two slopes) 0-12 years: 5.28% 13-35 years: 1.158%
10%
Book keeping (as per Companies act 2013)
40 SLM (single slope) 0-40 years: 2.38% 5%
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 302
For example: If the gross value of the transmission line asset is 100 INR, utility can charge depreciation as
per following: (i) First 12 years: 100*5.28% = 5.28 INR per year (Total deprecation for first 12 years = 63.36
INR); (ii) 13-35 years: Balance depreciation for last 23 (=35-12) years = 100 - 10%*100 (salvage value) -
63.36 = 26.64 INR; Depreciation rate for last 23 years = 26.64 / 23 = 1.158%
Description of proposed amendments
Depreciation is a major component of annual fixed charge (62% in Vietnam as per the financial statements VAS
2013). It needs to be determined in a scientific manner based on such methodology which on one hand allows
for servicing of debt during the entire loan tenure while on the other does not lead to excess cash generation
beyond requirement burdening the customers. Thus linking depreciation rate to the average long term loan
repayment period is the key to ensuring availability of adequate cash for principal repayment and then passing
on the benefit of lower charge to customers post loan repayment tenure.
Factors to be taken into consideration while designing the depreciation rates:
1. Determination of useful (economic) life of various categories of transmission assets based on
independent engineering estimates and industry standards;
2. Average long-term loan tenure applicable to EVNNPT;
3. Normative Debt:Equity ratio prevalent for similar regulated businesses in Vietnam;
4. Reduction in interest burden caused due to repayment of debt at given rates;
5. Reduced transmission charge to consumers due to reduced depreciation charge over the balance useful
life of the asset;
6. The remaining depreciable value (if any) to be spread over the remaining life of the asset; and
7. To disallow depreciation on revalued asset base considering, the benefit of increased RoE (as proposed
in earlier section).
The above approach will ensure that the burden of debt repayment of the utility is provided for while allowing
the benefit of lower charge to customers once loan repayment if completed.
The estimated potential impact of depreciation methodology on EVNNPT’s profit and revenue for the year 2013
to 2015 (as estimated in the petition document) is shown in the following chart. It can be seen that depreciation
allowed is in excess of requirement for principle repayment. From the depreciation values provided, the rate of
depreciation allowed lies between 5.8% and 6.6%, whereas the ideal rate keeping in mind the requirement for
principle repayment would lie between 3.2% and 3.8% approximately.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 303
59%
5%
10%
26%
Proportion of debt in foreign and local currency (Dec'12)
USD
EUR
JPY
VND
Issue#3: Treatment of foreign exchange rate variation
Loss on account of foreign exchange rate variation is a real loss and must be allowed to be claimed in respective
year’s revenue. For EVNNPT, there is no clear mechanism/timelines for recovery of accumulated foreign
exchange loss. In addition, EVNNPT is not using any hedging mechanism to minimise the risk of foreign
exchange rate variation.
Hedging of and/or compensating for foreign exchange rate variation is important for utilities like EVNNPT
whose foreign debt exposure is significant. As on 31
December 2012, EVNNPT’s debt in foreign currencies (USD,
EUR & JPY) was close to 74% of total debt. Utilities usually
hedge the foreign exchange exposure in respect of the interest
on foreign currency loan and repayment of foreign loan, in
part or full at their discretion. Such a safeguard is considered
proactive by the regulator and such costs related to hedging
are allowed as pass through in the transmission charge. On
the other hand, any unhedged positions not only entail high
risk for the utility but will also burden the customers, if the
full loss so suffered is passed on to consumers through
increased transmission charge.
Description of the existing provisions
Circular No. 14/2010/TT-BCT mentions in passing the inclusion of variation in foreign exchange rates on its
long-term loans under the calculation of ‘other monetary costs’, as follows.
“The total of other monetary costs in year N (NKC ) includes such expenditures as: per diem; expenditures for
workshops and conferences, and for receiving guests; expenditures for training; expenditures for buying
reactive power; expenditures for scientific research, studies, and innovative initiatives; expenditures for
meals during shift work; expenditures for the militia, watchmen, flood control, and firefighting; expenditures
4,914
3,248 3,309 3,402
1,666
3,198
4,382
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
2013 2014 2015
Bil
lio
n V
ND
Excess depreciation proposed for the years 2013-15
Depreciation
Loan PrincipleRepayment
ExcessDepreciation
6,507
7,784
Summary: MoIT / ERAV may undertake the exercise of re-determining the deprecation
charging rates by linking it to the loan repayment tenure the useful (economic) life of the
asset thus preventing excessive recovery of depreciation.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 304
for protective clothes, working clothes, labor safety, industrial and environmental sanitation; expenditures
for drinking water during working hours, in-kind compensation for night shifts, and compensation for toxic,
harmful and hazardous works; expenditures for emergency care in case of accidents in work, normal
medicine and rehabilitation for workers; expenditures associating to recruitment; losses accounted into
expenditures; tax expenses; land rental; short term interests due in the given year (including interest charges
of short term loans for obtaining working capital needed for transmission operations); and discrepancies
between effective foreign exchange rates of long term loans due in the given year and other
monetary expenditures in year N.”
The existing regulations have no specific provisions laid down for mitigation of such losses through hedging
etc., even though such losses have been significant in nature and have impacted the profitability of EVNNPT.
Rationale for proposed amendments
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below.
a. There is no hedging undertaken to safeguard against foreign exchange currency movement and
subsequent losses. Total loss (as on December 2012) was around 2,013 billion VND (96 million
USD).
b. As per the prevailing regulations, ERAV allows recovery of only realised foreign exchange loss
(incurred in the current year) in respective year’s revenue but not the unrealised foreign
exchange loss (anticipated to be incurred in future years). But without taking necessary steps to
safeguard against such losses, the customer of the utility is unduly burdened
c. Part of the accumulated losses has been allowed to be recovered whereas balance is carried
forward over future years to avoid tariff shock to customers. It was proposed to liquidate the
accumulated loss of 2,013 billion VND in equal instalments in 2013, 2014 and 2015 (i.e. 671
billion VND per annum). However, in 2014, ERAV has allowed only 241 billion VND of foreign
exchange loss. There is no clear mechanism/timelines for recovery of accumulated foreign
exchange loss.
2. Provisions made by comparable economies in the region, on treatment of foreign exchange rate
variation are presented below:
India Philippines Malaysia
Transmission licensee hedges foreign exchange exposure
Licensee to communicate to the beneficiaries about its hedging decision within 30 days
Licensee to recover cost of hedging corresponding to the normative foreign debt, in the relevant year
To the extent there is no hedge for the foreign exchange exposure, the
Licensee to request for change in MAR if:
o A major prescribed change in the PhP/$US exchange rate of + 15% occurs
o The PhP/$US exchange rate for a Quarter is > 120% of the PhP/$US exchange rate for that Quarter which is approved for the capital expenditure
Not specified
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 305
India Philippines Malaysia
extra rupee liability, shall be permissible
program
Revaluation of RAB before every regulatory period implicitly considers foreign exchange rate variation
From the above table, it can be seen that both India and Philippines have regulations that govern the treatment
and minimisation of foreign exchange rate variation exposure and subsequent treatment of cost / loss.
Description of proposed amendments
NPT shall exploring possibility of hedging against foreign exchange rate variation and adopt the following
suggestions:
1. Exploring possibility of hedging against the risk of foreign exchange fluctuations, through appropriate
instruments.
2. Cost of hedging for hedged foreign debt and currency liability for un-hedged foreign debt shall be
allowed to be recovered in the respective years.
3. If quantum of such exposure exceeds a certain set limit, then a maximum time frame in years to be
stipulated for such recovery.
4. Such expense / loss should be reflected in the books of accounts, as their exclusion will lead to further
erosion of funds as tax on unavailable profit.
To demonstrate the impact of reduction in realised exchange rate differences on profit for the year 2014, four scenarios have been presented here, where Scenario 1 assume a reduction of 10%, Scenario 2 a reduction of 30%, Scenario 3 a reduction of 50% and Scenario 4 a reduction of 70% in the realised exchange rate differences estimated for the year 2014 (as per the tariff application). The estimated additional profit availability due to anticipated reduction in realised forex losses under four scenarios is shown in the following chart:
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 306
It can be seen from the above chart that there is direct benefit of hedging against foreign exchange rate
variation to EVNNPT reflected through an increase in profit.
Issue#4: Lack of proper cost norms
Normative operating cost norms to calculate the Operating & Maintenance (O&M) expenses are absolutely
necessary to enable the utility to adhere to efficient standards of incurring such expenses. These norms will set a
clear benchmark beyond which any costs if incurred will be deemed inefficient and may not be allowed as pass
through in the transmission charge.
Description of the existing provisions
Circular No. 14/2010/TT-BCT stipulates the methodology for estimation of Costs of materials and Cost of major
repairs as two of the five components for estimating the total Operation and Maintenance (O&M) cost.
1. The formula laid down for calculating the total material cost is divided into the material cost of three
components namely, i) transmission lines, ii) sub-stations and iii) transformers. For example:
a. The total materials cost for transmission lines in year N (ĐD
NVLC ) is determined by the following
equation:
Where:
886 886 886 886 886
5 16 26 36
700
750
800
850
900
950
Actuals Scenario 1 (10%reduction)
Scenario 2 (30%reduction)
Scenario 3 (50%reduction)
Scenario 4 (70%reduction)
Bil
lio
n V
ND
Estimated additional profit available due to anticipated reduction
in realised forex losses through forex hedging
Profit Additional profit
NK
Đd i
NC
ĐBhhid
ĐD
VLhid
ĐD
VL ĐGLCN
500
110,,,,
Summary: EVNNPT shall explore possibility of hedging against foreign exchange rate
variation. The MoIT/ ERAV shall provide for pass-through of such costs in the regulation to
be included as part of total revenue requirement
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 307
hidL ,, : Total length of transmission lines type d, at voltage level i, under topographic
conditions h and operated in year N (km)
hid
ĐD
VLĐG,,
: Material unit cost for 1 km of transmission lines type d, at
voltage level i, under topographic conditions h (đ/km)
d: Indicators for type of lines including: single-circuit overhead line (D), double-circuit
overhead line (K), one-circuit underground cable (NĐ), two-circuit underground cable
(NK)
i: Indicators of voltage level including 110 kV, 220kV, 500 kV
h: Indicators of topographic conditions including: the plain (DB), the midland and
mountains (TD), high mountains and thick forests (NC).
b. Similarly the regulation lays down formulas for calculating the material cost of sub-stations and
transformers. Under each formula, the total cost is calculated based on the normative per unit
cost for various voltage levels and topographic conditions.
2. The formula laid down for calculating the total cost of major repairs is divided into the major repairs
cost of four components namely, i) transmission lines, ii) sub-stations, iii) transformers and iv)
auxiliary and servicing structures. For example:
a. The total cost for major repairs of transmission lines in year N (ĐD
SCLNC ) is determined by the
following equation:
Where:
hidL ,, : Total length of transmission lines type d, at voltage level i, under topographic
conditions h and given major repairs in year N (km)
hid
ĐD
SCLĐG,,
: Unit cost of major repairs for each km of transmission lines type
d, at voltage level i, under topographic conditions h (VND/km)
d: Indicators for type of lines including: single-circuit overhead line (D), double-circuit
overhead line (K), one-circuit underground cable (ND), two-circuit underground cable
(NK)
i: Indicators of voltage level including 110 kV, 220kV, 500 kV
h: Indicators of topographic conditions including: the plain (ĐB), the midland and
mountains (TD), high mountains and thick forests (NC)
b. Similarly the regulation lays down formulas for calculating the major repairs cost of sub-
stations, transformers and auxiliary and servicing structures. And under each formula the total
NK
Dd i
NC
ĐBhhid
ĐD
SCLhid
ĐD
SCL ĐGLCN
500
110,,,,
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 308
cost is calculated based on the normative per unit cost for various voltage levels and
topographic conditions.
Both these above mentioned cost estimations rely on underlying unit cost norms determined by EVNNPT for
voltage levels and topographic conditions. It is seen that the current cost norms set as the basis for calculating
the material costs and major repair costs (which are components of the transmission revenue) are outdated and
there is no mechanism to adjust these existing cost norms to reflect inflation, technological advancement or
substitution between capital and variable costs. Further, since the list of cost norms is outdated, it also does not
contain certain cost items (e.g., EIA study, engineering / management software, etc.) which today form part of
the overall cost list.
Rationale for proposed amendments
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below.
a. Cost norms are the basis for calculating the material costs and major repair costs (which are
components of the operating costs in the total transmission revenue);
b. The cost norms currently used by EVNNPT were developed by EVN in 2006
i. There is no mechanism to adjust existing cost norms to reflect inflation, technological
improvement etc.;
ii. Further, it also does not contain certain cost items which today form part of the overall
cost;
For example: EIA study, engineering / management software, fire prevention systems,
propaganda systems, communication systems etc.
c. Cost of major repairs is capped at 0.8% of asset value in Year N-3;
d. Once norms are implemented, EVNNPT should be allowed to retain any savings on account of
difference between allowed cost (normative) and actual cost (audited) provided quality of
service parameters are adhered too.
2. Provisions made by comparable economies in the region, on designing normative cost standards are
presented below:
India Philippines Malaysia
For regulated transmission licensees, the CERC has defined the consolidated O&M norms covering employee costs, repair and maintenance costs and administrative and general costs. These norms are defined in terms of:
For lines: INR/route km/year for each conductor configuration and tower configuration
For sub-stations: INR/bay/year for each voltage level
Separate norms for HVDC systems
Not specified Not specified
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 309
India Philippines Malaysia
In addition to O&M norms, regulations also define norms for working capital, auxiliary power consumption in sub-stations, initial spares (inventories) to be capitalised (along with the total project cost), etc.
Description of proposed amendments
NPT is expected to review its cost norms and revise them based on the following pointers:
1. The usual practice should be one where the cost norms are reviewed and revised in a timely fashion to
be reflective of price movement in the current market. This is of utmost importance to be able to allow
the utility to correctly gauge impending costs and recover rightful revenue through tariff.
2. Further changes in terms of additions/ deletions to this list are necessary to be able to incorporate any
new elements or do away with redundancy.
3. Scientifically developed norms will drive reduction in operating costs.
Issue#5: True-up (adjustment) mechanism
The process of truing-up (adjustment) is an inherent component of any mature regulation. It is a control
mechanism that helps in adjusting the over/ under recoveries of efficient costs by the transmission licensee
resulting from differences between forecast/approved values and actual/legitimate values. Such differences
may arise on account of controllable factors and uncontrollable factors.
True-up of revenue / cost requires one or the other kind of revenue / cost control mechanisms in place. For
example: defining controllable and uncontrollable cost parameters putting an overall revenue cap etc. This
mechanism is a clear indicator to the licensee of the expected prudent levels of certain costs that it may plan
and incur.
Description of the existing provisions
Circular No. 14/2010/TT-BCT specifies true-up / adjustment mechanism as part of transmission charge
determination methodology as follows:
Annual permitted total transmission revenue of year N (NTTG ) includes: permitted capital cost (
NTTCAPC ),
permitted operation and maintenance cost (NTTOMC ) and adjusted transmission revenue for year N-1 (
1NCL ), which is determined by employing the following formula:
1 NOMCAPTT CLCCGNTTNTTN
Summary: EVNNPT in conjuncture with EVN shall develop updated cost norms with all
relevant cost components covered
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 310
Where:
NTTCAPC : Permitted transmission capital cost for year N of the National Power Transmission
Corporation (VND)
NTTOMC : Total permitted operation and maintenance cost of year N of the National Power
Transmission Corporation (VND)
CLN-1: The difference between transmission costs and revenues of year N-1 which is
adjusted in the permitted total transmission revenue of year N (VND), determined in
accordance with the method prescribed in Clause 9 Article 1 of this Circular”
Chapter III of the above regulation lays down the principle of calculating the transmission revenue adjustment
of year N-1 to be adjusted in year N, and also lays down the responsibility for maintaining records and reporting
on differences between transmission cost and revenue.
Even though the regulation has made a provision to make such corrections, ERAV has not yet undertaken any
such adjustment in determining the transmission charge in the past, to take care of variation between approved
tariff and actual expenses during the previous year.
Rationale for proposed amendments
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below:
a. Regulation specifies revenue true-up (adjustment) mechanism but not in practice;
b. Variations between approved expenses/revenues and actual expenses/revenues during the
previous years have not been adjusted by ERAV till date;
c. Further, regulation does not specify controllable and uncontrollable expense items, which
would be good indicators to EVNNPT to be prudent and efficient in expenses;
d. Thus there is no mechanism which enforces the need to be prudent and efficient in incurring
capex and opex as well as adjustment for over/under recovery of revenue; and
e. Timely true-up will help EVNNPT recover justifiable revenue and retain efficiency gain
(positive difference between allowed cost and actual cost).
2. Provisions made by comparable economies in the region, on true-up (adjustment) are presented below:
India Philippines Malaysia
CERC Tariff Regulations 2014 define controllable / uncontrollable factors
o Controllable - Capex variation due to time over-run and cost over-run, project implementation
TWRG 2009 stipulate a correction factor in determining revenue requirement
Correction factor - Adjustment for over/under recovery of revenue in year t-1
ECM Tariff Regulations 2012 stipulate an Efficiency Carryover Amount as part of total revenue requirement
ECA = Base Incentive + Efficiency Carryover
o BI - Retention of
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 311
India Philippines Malaysia
efficiency, delay in execution on account of contractor/supplier
o Uncontrollable - Force majeure, change in law
Calculated based on actual amount billed to customer plus net receivable by utility less max. allowable revenue for year t-1
variances in actual Opex & Capex relative to forecasts within the regulatory term
o EC - 50% of cost efficiency amount achieved in last regulatory term
The below example from the tariff order of the Northern Region System Strengthening Scheme-V of
Power Grid Corporation of India (POWERGRID) shows the disallowance of controllable cost items by
the CERC. This assessment sends clear indication to the transmission licensee (here, POWERGRID)
that expenditure which is controllable and not prudent will not be allowed as a pass-through.
As per the investment approval, the project was scheduled to be commissioned within 36 months from
the date of investment approval i.e. by 01.07.2009. The transmission asset was put under commercial
operation on 01.01.2011, after a delay of 18 months. Upon scrutiny of the reasons and relevant
documents, the CERC was not convinced by the reasoning given by the utility. Therefore in the absence
of any justifiable documentary evidence, the cost of time over-run i.e. impact on cost of the delay of 18
months was disallowed as a pass through.
Details of disallowed Interest During Construction (IDC) and Incidental Expenditure During
Construction (IEDC) are as follows:
As per Management Certificate submitted vide affidavit dated 06.12.2013 (INR million)
Particular IDC IEDC
Expenditure up to 31.12.2010 13.284 3.605
Total IDC and IEDC claimed 13.284 3.605
Details of IDC & IEDC Disallowed for 18 months
Disallowed IDC and IEDC for 18 months 4.428 1.202
Total allowed 8.856 2.403
Description of proposed amendments
NPT has already made a provision for adjusting its over/under recoveries in the previous year, in the total
revenue requirement of the current year. The next step would be to widen the scope of this adjustment in such a
manner that it also inculcates efficiency in the operations of EVNNPT. The below pointers indicate the benefit
of undertaking a true-up process:
1. Undertaking a true-up on a timely basis is an absolute necessity to ensure that neither the licensee nor
the customer is being burdened by disallowance of prudent costs or through allowing inefficiencies to
be passed on through transmission charge.
2. Defining controllable and un-controllable parameters sets clear standards of performance to the
licensee, which will be allowed to enjoy incentive for efficiency and will be penalised for inefficiencies.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 312
3. The mechanism of truing-up of cost items should be based on the principles of controllable and
uncontrollable costs rather than on arbitrary judgement based on the level of final retail tariff to be
imposed. Based on such categorisation alone there can be a scientific approach to allowance or
disallowance of true and reasonable costs.
4. This will also send a clear signal to the utility about being prudent and efficient in their capital and
operating expenditure.
5. On one hand, elements like RoE are completely disallowed and on the other hand, over-recovery
through depreciation on re-valued asset is allowed. This imbalanced approach will not give the utility
any incentive to improve its functioning efficiency and may create financial strain in the future.
MoIT / ERAV may review the regulations governing truing up, cost control mechanisms of contemporaries and
design its own regulations which best fits EVNNPT and the energy regime in Vietnam.
Issue#6: Penalty framework for failed service quality
Suitable performance norms of operations together with incentives and dis-incentive mechanism is key to
ensure that the licensee has a clear understanding of the expectation from it in terms of performance standards.
Alongside the above, there is a need to be design an appropriate arrangement for sharing the gains of efficient
operations with the consumers. The norms should be efficient, relatable to past performance, achievable,
progressively reflecting increased efficiencies and may also take into consideration the latest technological
advancements, fuel, vintage of equipment, nature of operations, level of service to be provided to customers etc.
Continued and proven inefficiency must be controlled and penalized.
Description of the existing provisions
Circular No. 14/2010/TT-BCT lays down the procedure for calculating penalty for failed service quality, where
EVNNPT is fined for failing to guarantee quality of service in cases where outages of transmission lines and
transformers of the transmission system in the year exceeds regulated limits for each voltage level, except for
incidents caused by force majeure or problems not caused by EVNNPT. The total amount of penalties due to
failure to ensure the transmission service quality every year (year N) RN of the EVNNPTC is determined by the
following equations:
NN TLN RRR
CtLrBtLrAtLrRl
k
kNkL
m
j
jNjL
n
i
iNiLLNNNN
1
,
1
,
1
, 500220110
GtSrEtSrDtSrRl
k
kNkT
m
j
jNjT
n
i
iNiTTNNNN
1
,
1
,
1
, 500220110
Where:
Summary: MoIT/ ERAV may establish controllable and uncontrollable cost parameters and
ensure that the provision for true-up made in the existing regulation is enforced in a timely
manner. EVNNPT should be allowed to retain the efficiency gains (i.e. positive difference
between approved costs and actual costs). Further, regulation should lay down clear
instructions with regard to timelines and process of filing information by EVNNPT.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 313
NLR : The amount of penalty due to failure to ensure the transmission service
quality because of blackouts in the transmission line system (VND)
NTR : The amount of penalty due to failure to ensure the transmission service
quality because of blackouts in transformers (VND)
NiL , ( NjL , , NkL , ): Total length of 110kV (220kV, 500kV) transmission lines under blackout
when event i (j, k) happens (km)
NiS , ( NjS , , NkS , ): Total installed capacity of high voltage transformers 110kV (220kV, 500kV)
under blackouts when event i (j, k) happens (MVA)
it ( jt , kt ): Duration of blackout on transmission lines or high voltage transformers
110kV (220kV, 500kV) when event i (j, k) happens (minutes)
n (m, l): Number of blackouts on transmission lines or high voltage transformers
110kV (220kV, 500kV) in year N (from 01 September year N-1 to 31 August
year N)
NLr 110 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts on transmission lines in year N calculated for each km of 110kV
transmission line in one minute [VND/(km*minute)], in accordance with the
following equation:
NTTL GXrN
110110
NLr 220 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts on transmission lines in year N calculated for each km of 220kV
transmission line in one minute [VND/(km*minute)], in accordance with the
following equation:
NTTL GXrN
220220
NLr 500 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts on transmission lines in year N calculated for each km of 500kV
transmission line in one minute [VND/(km*minute)], in accordance with the
following equation:
NTTL GXrN
500500
NTr 110 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts in transformers in year N calculated for each MVA capacity of
high voltage 110kV transformer in one minute [VND/(MVAminute)], in
accordance with the following equation:
NTTT GYrN
110110
NTr 220 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts in transformers in year N calculated for each MVA capacity of
high voltage 220kV transformer in one minute [VND/(MVAminute)], in
accordance with the following equation:
NTTT GYrN
220220
NTr 500 : Rate of penalty due to failure to ensure transmission service quality because
of blackouts in transformers in year N calculated for each MVA capacity of
high voltage 500kV transformer in one minute [VND/(MVAminute)], in
accordance with the following equation:
NTTT GYrN
500500
110X : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts on 110kV transmission lines [1/(kmminute)]
220X : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts on 220kV transmission lines [1/(kmminute)]
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 314
500X : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts on 500kV transmission lines [1/(kmminute)]
110Y : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts in 110kV transmission transformers [1/(MVAminute)]
220Y : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts in 220kV transmission transformers [1/(MVAminute)]
500Y : Coefficient of penalty due to failure to ensure transmission service quality
because of blackouts in 500kV transmission transformers [1/(MVAminute)]
A (B, C): Penalty norms for blackouts on 110kV (220kV, 500kV) transmission lines
D (E, G): Penalty norms for blackouts in 110kV (220kV, 500kV) transmission
transformers
Blackouts on transmission lines and transformers that are taken into account when determining penalties due
to failure to ensure the transmission service quality should be the events with the duration of more than or
equal to one minute. The duration of blackouts on transmission lines and in transmission transformers should
be in round figures and in the unit of minute.
The above guideline is merely on paper and is not actually implemented. The cause for it is the inadequate data
available as well as lack of clearly defined quality parameters for assessing performance.
Rationale for proposed amendments
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below:
a. Even though the provision for estimating the penalty for failed service quality has been made in
the regulation, it has not be implemented so far due to the fact that the information required to
be filed by the licensee not being accurately/ fully captured as well as lack of clearly defined
penalty norms as below:
i. Time of outage of transmission line or transformer
ii. Number of outages of transmission line or transformer
iii. Duration of outages of transmission line or transformer
iv. Rate of Penalty for outage of transmission line at 110 kV, 220 kV, 500 kV
v. Rate of Penalty for outage of transformer at 110 kV, 220 kV, 500 kV
b. Also the mechanism defined in the regulation for penalising EVNNPT for any such failure is by
deducting the penalty amount from the welfare fund which is created for all staff members.
This approach seems to be penalising all staff members who might not be in any way related to
the process of managing the service quality of the transmission system.
2. Provisions made by comparable economies in the region, on performance standards and associated
incentives / penalties are presented below:
India Philippines Malaysia
Tariff Policy 2006: Based on RTWR, the initial The Commission proposed
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 315
India Philippines Malaysia
Suitable performance norms together with incentives/penalties and appropriate sharing of gains of efficient operations with consumers are necessary
CERC Tariff Regulations 2014:
NATAF: o For recovery of
Annual Fixed Charges: 98% (AC); 95% (HVDC)
o For incentive consideration: 98.5% (AC); 96% (HVDC)
Total penalty/incentive is adjusted in the revenue requirement of the utility
reliability targets are set as - the mean value of the particular reliability performance for the last five (5) years where the upper and lower cut-off points shall be set at plus or minus one (±1) standard deviation from the mean value.
Reward/Penalty should not exceed:-
10% of the average monthly rate
3% of the ARR for that Regulatory Year
that each of the TNB business entities recommend 3 operational performance indicators and demonstrate that they comply
For example: the Commission notes that:
o circuit and plant availability, supply interruption and losses are common indicators adopted for the electricity transmission businesses in Australia, UK and Singapore
In addition, power quality indicators (voltage dip incidents) have been used in Singapore for electricity transmission
The above regulations clearly illustrate that standards of performance - Availability, Interruptions, Loss
levels etc. have been defined by each regulator and corresponding penalty and (or) incentive scheme is
also designed to ensure its implementation by licensee. The table below captures the Incentive earned
by the transmission utilities in India based on the set availability norms by Central ERC or State ERC:
Name of transmission utility (in India) Year Estimated incentive on account of System Availability > Target Availability (million INR)
Power Grid Corporation of India Limited 2013-14 1787.6
Maharashtra State Electricity Transmission Company Limited 2011-12 451.1
Tamil Nadu Transmission Corporation Limited 2013-14 234.4
Karnataka Power Transmission Corporation Limited 2011-12 143.9
Description of proposed amendments
The existing provisions in the regulation need to be made implementable by undertaking the below pointers:
1. Specification of standard operating norms and performance parameters is essential to measure efficient
performance of the licensee and to develop a suitable mechanism of incentive and disincentive are key
to drive performance.
2. The approach followed usually for specifying operation norms is based on historical data analysis and
consideration of efficiencies, technological advantage, vintage etc.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 316
3. The performance norms are also designed to be practical and implementable allowing the utility a fair
chance to achieve the set standards.
Issue#7: Structure of transmission charge
The structure of the transmission charge determines how the recovery of the total revenue requirement of the
transmission licensee takes place. The standard method of recovering transmission cost from long-term
customers is based on the system capacity. Only for short-term transactions, the transmission charge is based
on the energy transacted. The rational being that the entire revenue requirement for a transmission system
comprises of fixed cost components and thus do not vary with the volume of energy transacted. Hence
irrespective of the volume of energy transacted, this cost has to be fully recovered by the transmission licensee.
Description of the existing provisions
Article 7 of Circular No. 14/2010/TT-BCT lays down the method to calculate the annual transmission charge for
units subject to pay such charges as follows:
1. The annual transmission price ( iTTg) (VND/kWh) in year N for the unit i subject to transmission cost
payment is determined by the following equation:
Ni
i DB
GN
iTT
A
TCg
,
Where:
TCi: Transmission cost to be paid by the unit i subject to transmission cost payment in year N
(VND)
Ni
DB
GNA,
: Total estimated electrical energy to be received by the unit i at all receiving points in year N
2. The transmission charges payable by the ith unit subject to pay transmission charge in year N (TCi) is
calculated by employing the following formula:
1,, NiAPNi DCTCTCTCii
Where:
TCP,i: Part of transmission cost based on capacity (VND)
TCA,i: Part of transmission cost based on electrical energy (VND)
1, NiDC : Total adjusted amount of transmission cost for the unit subject to transmission cost payment
i for year (N-1) (VND)
Summary: MoIT / ERAV may undertake technical study of historic data on performance of
EVNNPT and design appropriate operating norms along with incentive/ disincentive
mechanism duly considering technological advancement, vintage of equipment etc. Initial
targets can be set at “relaxed” level.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 317
3. The parts of transmission cost based on the capacity and based on the electrical energy are respectively
determined by the following equations:
DB
Nin
i
DB
Ni
TT
P P
P
GTC N
i ,
1
,
Ni
N
i
DB
GNn
iNi
DB
GN
TT
A A
A
GTC
,
1,
Where:
DB
NiP, : Total maximum projected receiving capacity of the unit subject to transmission cost
payment i at receiving points in year N (MW)
n: Total number of units subject to transmission cost payment
, : Ratio of parts of capacity and electrical energy to transmission cost as annually
specified by the ERAV, with + = 1; and = 0 for year 2011.
This may not be the ideal way to recover transmission revenue, as the system is built to cater to the
maximum available generation capacity and thus should entail recovery from long-term (committed)
customers on capacity basis as well. Also if the recovery is only energy based, there is no certainty to
revenue recovery, as the actual energy transmitted may vary from the projected energy to be
transmitted.
Rationale for proposed amendments
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below:
a. Currently α is set at zero leading to the transmission charge being a completely “energy-based
charge”;
b. It is a known fact that any transmission system is built to cater to the maximum demand and
evacuate available generation and therefore should entail full recovery of the such capacity
charges irrespective of actual energy flow;
c. In case of “energy-based charge”, there is no certainty to recover full approved revenue, as the
actual energy transmitted may vary from the projected energy used to calculate the per unit
rate;
d. In the absence of the true up mechanism, this method of charging the transmission customers
becomes even more unreliable;
2. Provisions made by comparable economies in the region, on structure of the transmission charge are
presented below:
India Philippines Malaysia
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 318
India Philippines Malaysia
Based on capacity for long-term and medium-term customers (expressed in INR/MW/month)
Based on energy for short-term customers (expressed in INR/MWh)
Based on energy (expressed in PhP/kW/month)
Based on energy (expressed in sen/kWh)
Description of proposed amendments
MoIT / ERAV to review the exiting mechanism and determine the value of so as to derive the component of
transmission charge which will be based on the transmission capacity. The below key points may be taken note
of while determining this proportion:
1. It is not ideal to recover transmission revenue only on energy basis, as the system is built to cater to the
maximum available generation capacity and thus should entail recovery from long-term customers
(such as power distribution companies) on capacity basis.
2. The total available transmission capacity based on the capacity of all generating stations can be taken as
the basis for determining the capacity based transmission charge for long-term transmission
customers, while energy transacted can be taken as the basis for determining the transmission charge
for the short-term customers.
Issue#8: Transmission charge sharing mechanism
Sharing mechanism is the means by which the total revenue requirement of the Transmission utility is charged
to its customers. The sharing of transmission charges is based on the technical and commercial information
provided by various customers, the transmission licensees, and any other relevant entity, including the load
dispatch centres. Based on the method opted, relevant information is collected to assess the proportion of total
charges to be apportioned to various customers.
Description of the existing provisions
On the overall method adopted for pricing transmission service, it is observed that the current methodology
followed is nationally uniform, flat energy-based charge (also called the postage stamp method) where no
distinction is made between the transactions with regard to the power flow path, distance of power flow,
direction of power flow, supply or delivery points, the time when it takes place etc. Though this methodology is
reasonable in the existing context, further development of the transmission network, electricity markets and
competition will call for a more efficient pricing mechanism.
Rationale for proposed amendments
An efficient transmission pricing regulation should ensure following factors:
Summary: MoIT / ERAV based on existing regulations and information from EVNNPT to
determine the value of so as to charge transmission tariff based on both the transmission
capacity as well as energy transmitted.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 319
1. Reasonable revenue to the transmission system owners to enable repayment of loans, payment of
interest, return on equity, reimbursement of O&M cost, contingencies, etc.;
2. Encourage investment in the network and determine optimal location of generation and demand;
3. Transmission constraints and congestion in the network are properly assessed and addressed;
4. Proper accounting and allocation of transmission losses; and
5. Rational sharing of transmission charges and losses among the users.
The proposed modifications suggested above are based on two factors:
1. The shortcomings in the existing regulation (Circular No. 14/2010/TT-BCT dated 15 April 2010)
promulgated by the MoIT and its impact on the EVNNPT. Some of them have been highlighted below.
a. Nationally uniform, energy based flat charge being levied to customers of EVNNPT, where no
distinction is made between the transactions with regard to the power flow path, distance of
power flow, direction of power flow, supply or delivery points, the time when it takes place etc.
b. Methodology is reasonable in the existing context, development of the transmission network,
electricity markets and competition will call for a more efficient pricing mechanism.
2. Provisions made by comparable economies in the region, on transmission charge sharing mechanism
are presented below:
India Philippines Malaysia
Moved from regional postage stamp to simplified nodal pricing (PoC) reflecting usage, distance, direction and voltage level
Generators and demands pay different rates
Revised every three months
Nationally uniform, flat charge based on demand
Forecasted monthly usage of available transmission capacity is used to determine charge expressed in PhP/kW/month
Revised annually
Nationally uniform, flat charge based on energy
The tariff so determined is nationally uniform, flat energy-based charges expressed in sen/kWh
Revised annually
Note: Since 2011, India is using the simplified nodal pricing (Point of Connection methodology). PoC
methodology is used for computation and sharing of the Inter State Transmission System Charges and
Losses among Designated ISTS Customers (DICs) which depends on quantum of power flow and
location of the node (injection/drawal) in the grid and is sensitive to distance and direction. Charges
would be computed for each node of DICs based on hybrid method. The hybrid method employs both
the average participation method as well as the marginal participation method.
Description of proposed amendments
The existing method of pricing even though reasonable in the existing context needs to be reviewed as any
further development of the transmission network, electricity markets and competition will call for a more
efficient pricing mechanism.
ERAV is expected to assess various models available to determine appropriate transmission sharing mechanism
and adopt one which is best suited in Vietnamese context.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 320
Some of the methods that can be reviews by the ERAV are as below:
1. Rolled in Paradigm: Postage stamp, Contract Path Method, MW-Mile method
2. Incremental Transmission Pricing Paradigm: Long/Short Run Incremental/Marginal cost method
Issue#9: Impairment of regulatory independence
The very purpose of a regulator is to be able to undertake an independent evaluation of the tariff petition. The
Regulatory Commission is responsible to balance out the interests of both the transmission licensee as well as
the consumer. It is bound to function without any political influences.
Description of the existing provisions
Article 31 of the Electricity Law stipulates guidelines for determination of electricity prices and associated
charges and the bodies who are responsible for its verification and approval. It identifies the regulating body as
a separate entity to that of the concerned ministry namely MoIT. But as on today the ERAV is an integral part of
the Ministry and does not wield any decision making of its own. The lack of an independent regulating body
might cause the price determination process to be driven by factors other than as stipulated in Circular 14.
1. It has been observed that EVNNPT does not have full autonomy to determine its revenue requirement;
it has to be channelled through EVN. It seems EVN significantly modifies revenue/price proposed by
EVNNPT before its submission to ERAV. In 2014, EVN curtailed EVNNPT’s proposed revenue by 22%
and allowed only 1% RoE (instead of 4% as proposed by EVNNPT). It appears ERAV also does not have
powers to review investments proposed by EVNNPT.
The table below captures the disallowance of revenue and expenses by EVN for 2014:
Item Power transmission tariff in 2014 (petitioned by EVNNPT)
Power transmission tariff in 2014 (reviewed by EVN)
Dis-allowance in %
Million VND
Power transmission output (Million kWh)
123,345 122,200 0.9%
Power transmission tariff 109.9 86.4 21.4%
Revenue 13,556,849 10,552,297 22.2%
Expenses 12,670,971 10,342,306 18.4%
Materials 166,133 140,148 15.6%
Salary and social insurance 1,390,407 1,356,838 2.4%
Depreciation of fixed assets (excl. revaluation of fixed assets)
6,506,645 6,004,235 7.7%
Outsourced services 202,188 50,360 75.1%
Major repair expenses 381,060 381,060 0.0%
Cash expenses 2,486,621 2,387,101 4.0%
Increases and impairments in 1,537,917 22,564 98.5%
Summary: MoIT / ERAV may review the existing norms by keeping in view the developments
in the sector, current and perceived challenges in the sector and duly recognizing the need
for sustainable market development. Though it is important to maintain regulatory certainty
in tariff approach, the tariff should reflect the changing market conditions as well.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 321
Item Power transmission tariff in 2014 (petitioned by EVNNPT)
Power transmission tariff in 2014 (reviewed by EVN)
Dis-allowance in %
electricity price
Profit from power production and trading (1% of state capital)
885,878 220,000 75.2%
EVN made considerable changes in the numbers submitted by EVNNPT. Overall reduction was to the
tune of 22% in the revenues and 18% in the total expenses. Major reductions were made in RoE and
foreign exchange loss allowance.
2. Further, ERAV being integral part of MoIT lacks autonomy while approving the transmission revenue
and charge. ERAV does not have any specific powers to review proposed investments as part of the
transmission pricing calculation. Instead, the five-year network development plan and annual
investment plan as approved by MoIT and EVN are used to calculate the costs of investments in the
coming year.
3. As per Decision No. 69/2013/QD-TTg, ERAV shall mandatorily seek approval of MoIT for all increases
in retail tariff beyond 7% (w.r.t. prevailing prices).
Rationale for proposed amendments
1. Provisions made by comparable economies in the region, on regulatory independence and related
processes are presented below:
India Philippines Malaysia
As per the Electricity Act 2003, the Central ERC and State ERCs are independent quasi-judicial regulatory bodies
CERC/SERCs do not report to the Ministry of Energy / Power
Central and State Transmission utilities file the transmission pricing petition directly to CERC /SERC
Under Section 38 of EPIRA 2001, the Government created an independent, quasi-judicial regulatory body namely the Energy Regulatory Commission (ERC) of Philippines
Transmission utility (National Grid Corporation of the Philippines) files the transmission pricing petition directly to ERC
The Malaysian Government established the Energy Commission (Suruhanjaya Tenaga) as autonomous body under the Energy Commission Act 2001
Integrated utility, TNB files the transmission pricing petition directly to Energy Commission of Malaysia
The above Acts and provisions confer exclusive rights to the regulator and ensure (as far as possible) their
independent operations. Also the existing transmission utilities file their annual transmission petition directly
to respective regulators and not through the holding company, thus being able to fairly seek their share in the
overall retail tariff.
Description of proposed amendments
Based on the understanding of the existing regulations and processes followed by EVNNPT for filing the TPTR
petition to ERAV, the proposed changes may be reviewed:
1. ERAV to be independent of direct political influence (MoIT) and set up as an independent regulator.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 322
2. EVN to allow EVNNPT to directly exercise its powers as the transmission licensee and not be part of
EVNNPT’s TPTR petition filing process. This will ensure that EVN does not side-line the interests of
EVNNPT to ensure the overall compliance to be met for retail tariff setting.
Summary: ERAV and EVNNPT to be given sufficient independence to operate in their
respective capacities as the regulator and the transmission utility. This may be done by
incorporating relevant changes in the tariff filing process.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 323
Recommendation#3: Develop and implement integrated transmission pricing model (TPM) for compilation of data and calculation of revenue & charge
Refer Appendix 10 -
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 324
Recommendation#4: Prepare a transmission pricing procedure (TPP) for collection, compilation and validation of information needed for transmission pricing
Context
Circular No. 14 & 3 lay down the procedure for data collection, review and filing of the application (petition) for
review and approval of Total Power Transmission Revenue (TPTR) and Transmission Charge (TC) by EVN and
finally by ERAV. The proposed Transmission Pricing Procedure (TPP), with an underlying objective of
streamlining and standardising the entire process, shall help EVNNPT improve its compliance to the relevant
circulars and decisions.
Objective
1. The TPP shall help streamline the process of preparation, collection, compilation and validation of
various information and data needed for transmission pricing. At present, there is no standard
procedure and timeline being followed; and
2. The TPP shall help ensure timely collection and use of complete and credible information for the
Transmission Pricing Model (TPM).
In this context, the following section captures key provisions proposed to be followed during the preparation of
the TPTR / TC petition based on the data to be collected and compiled from various departments of the
EVNNPT.
Provision#1: Streamlining the process of data preparation, collection, compilation and validation
This section will clearly lay out the responsibilities at department level / individual level for submission, review
and validation of data along with prescribed time lines for enabling the CPD in the preparation of the TPTR /
TC petition.
Status of data to be submitted by various departments
The table below lists down all the data that is needed to be submitted to the Corporate Planning Department by
various other departments and presents the current status of data and formats used to provide such
information and necessary action to be taken.
Sl. No.
Description of data Responsible Department
Data presently being provided (Yes / No)
Status of formats available
(A) CAPITAL COST DATA
1. Depreciation F&AD No Format made
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 325
Sl. No.
Description of data Responsible Department
Data presently being provided (Yes / No)
Status of formats available
Opening GFA
Additions / Deductions during the year
Life of the asset
Annual depreciation rate
Not in the detail required.
available to capture necessary details.
2. Interest charges
Loan details including total loan and currency
Interest rate
Loan tenure and grace period
Outstanding loan at the start of year N
Principal and interest repayment
Residual value at the end of year N
F&AD/ PTC Yes Minimum adjustment in format required to include some details.
Format made available to capture necessary details.
3. Return on equity
Outstanding equity at the start of the year N
% RoE to be applied
F&AD Following a different approach to determine profit. Alternate method suggested.
No other detailed format required. Change in approach required.
(B) OPERATING COST DATA
4. Material costs
Opening material cost for year N
Additional quantity of material procured and cost norms for lines and transformers of various voltages and for different terrains
Adjustment factor and its basis
F&AD Yes But more details to be provided, with clarity on various adjustment factors considered and causes for exclusions.
Existing format is adequate.
5. Salary costs
Estimated staff and their levels
Labor productivity
Unit price salary for working staff and management
Provision for health and staff welfare
OPLD Yes Precise and non-conflicting information and index used to compute salary hikes to be provided.
Existing format is adequate, but consistency of data needed.
6. Major repairs costs
Total Tangible and Intangible fixed assets for the year N
F&A Yes Minimum adjustment required.
Existing format is adequate.
7. Outsourced service costs
Opening cost for year N
Additional quantity of material procured and cost norms for lines and transformers of various voltages and for different terrains
Adjustment factor and its basis
Increase beyond applicable cost norms and reasons thereof
F&AD Yes But more details to be provided, with clarity on various adjustment factors and causes for exclusions.
Existing format is adequate.
8. Other expenses in cash
Opening cost for year N
Additional quantity of material procured and cost norms for lines and transformers of various voltages
OPLD Yes But more details to be provided, with clarity on various adjustment factors and causes for
Existing format is adequate.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 326
Sl. No.
Description of data Responsible Department
Data presently being provided (Yes / No)
Status of formats available
and for different terrains
Adjustment factor and its basis
Increase beyond applicable cost norms and reasons thereof
exclusions.
(C) TECHNICAL DATA
9. Transmission lines and transformers outage record
Transmission line and transformer outage data including line length, voltage level, minute of outage
Penalty co-efficient applicable for various voltages
Penalty norms for various voltages
TD / PTC No Not at all provided. Need to first establish the value for penalty co-efficient and penalty norms for various voltage levels for lines and transformers. This should be based on technical studies undertaken by the utility.
Working Appendix 9 made available to capture necessary details.
(D) ACCOUNTING DATA
10. Actual cost and revenue information for previous year (N-1)
Actual costs incurred and revenue earned during year (N-1) based on audited financial statements.
Costs incurred due to force majeure causes
Costs incurred due to additional projects sanctioned by the government
Interest rate applicable(as per regulation) as carrying cost on under recovery
F&AD No Not at all provided. Can be easily sourced from prior period accounts statements.
Working Appendix 8 made available to capture necessary details.
Based on the above table the status of data and whether or not it is being adequately provided can be gauged. To
enable better capture of information pertaining to Depreciation, Interest on Long term loans, Penalty
calculation and Prior period cost and revenue adjustments, new formats have been designed and annexed along
with the Transmission pricing model. These formats will act as a common input form from where data will flow
into the pricing calculations.
It should be noted that the formats/ appendices which are part of the Transmission pricing model should be
used as a common format by all departments which need to submit information on the various cost item.
This will ensure that the CPD receives information from various departments in similar formats and can easily
collate, compile and incorporate the same into the model for arriving at the Transmission charge.
The figure below captures the seamless flow of data from various departments responsible for supplying such
information to CPD, leading to preparation and submission of the TPTR & TC petition.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 327
The table below lists down the staff responsible within each department to submit data to CPD. Further internal
time lines have been drawn to ensure that all the departments including CPD has sufficient time in preparing
the TPTR petition within the time lines defined by Circular 14.
Department Responsibility No. of staff
assigned
Designation of
staff
Time line to be adhered to
F&AD Submission of Financial data in prescribed formats.
2 (Suggested) 1 - Deputy Director
1 - Expert
5th March, year N
TD Submission of Technical data in prescribed formats.
2 (Suggested) 1 - Deputy Director
1 - Expert
5th March, year N
OPLD Submission of data on employee cost etc. in prescribed formats.
3 1 - Deputy Director
2 - Experts
5th March, year N
PTC Submission of necessary Financial and Technical data in prescribed formats.
2 (Suggested) 1 - Deputy Director
1 - Expert
5th March, year N
CPD Collection and compilation of all data submitted.
2 1 - Deputy Director
Business
Operations
1 - Expert
1 - Expert suggested
15th March, year N
Prudence and consistency check.
2 25th March, year N
Receipt and incorporation of any additional data sought from various departments.
2 5th April, year N
Complete preparation of the TPTR petition and submit it for internal approval.
3 (Suggested in overall)
5th May, year N
Make any recommended changes in the petition.
12th May, year N
NPT to submit the TPTR Petition to EVN for review before 15th May, year N
Transmission Pricing Petition
Financial data on financing cost,
depreciation, equity, operating costs
Technical data on failed service quality
due to outages
Need based information on
technical and financial aspects
Data on employee salaries, benefits
associated costs and cash expenses
Corporate Planning
Department
Finance & Accounting Department
Technical Department
PTCs (Planning and
F&A Departments)
Organization, Personnel &
Labour Department
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 328
The above table clearly assigns responsibility to each department as well as staff member for enabling the
preparation and timely submission of the TPTR petition to EVN in line with timelines specified.
Provision#2: Designing standard formats for furnishing all the relevant data in MS Excel formats
It is of utmost importance to have necessary formats which enable the capture of all relevant information under
all cost items. Such forms/ formats should be designed such that they are self-sufficient and capture all
necessary information. These formats will act as the input feed to all calculations and will help in determining
the Transmission charge.
Such formats enable the imminent transition towards maintaining regulatory accounts, which calls for separate
set of accounts be maintained for the regulatory process apart from that of books of accounts for accounting
purposes. The below two formats on Depreciation calculation and calculation of Interest on long term loans
have been designed keeping in mind the method of calculation to be employed and capture of relevant details
for future reference. These formats should be incorporated into the Transmission pricing model to form the
input sheets, from which relevant information flows.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 329
Format 1 - Format for Depreciation Calculation
Sr. No.
Year N Gross Block of Assets Annual rate of
depreciation (%)
Depreciation Name of Asset At the
beginning of the year (as
on 1 January of year N)
Additions from
investments during the
year N
Deductions / Adjustment during the
year N
Additions from
revaluation during the
year N
At the end of the year (as
on 31 December of
year N)
On the Assets at the
beginning of the year (as
on 1 January of year N)
Pro rata depreciation on additions
from investments during the
year N
Depreciation on revalued asset for the
year N
Total depreciation
for the year N
1. Land and Land rights
2. Buildings
3. Hydraulic works
4. Other civil works
5. Plant & machinery
6. Lines & cables Network
7. Vehicles
8. Furniture & Fixtures
9. Office equipment
10. Capital spares
TOTAL
Format 2 - Format for Principal Repayment and Interest Expense Calculations for Long-term Loans
Sr. No.
Counterparty Contract Value Interest %
Loan Periods (months) For year N Currency Amount Grace
period Loan
payment period
Time for principal payment
Outstanding at the start of the year
Principal Payment
Interest Payment Total (Principal
+ Interest)
Residual at the end of
the year Start Finish Basic
construction Business operation
1.
2.
3.
4.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 330
Provision#3: Defining data reconciliation and dispute resolution procedure
Data reconciliation is a key aspect of the responsibility assigned to CPD. Given that information is provided by
multiple departments, there is scope for varying information under the same head (for the same parameter) to
be provided to CPD. The very use of common formats being used by all departments will weed out possibility of
any calculation error to a certain extent.
In the even that there is still some discrepancy in the data submitted by different departments under the same
head, a quick reconciliation of such variation is necessary to ensure correctness. To ensure that such variations
be smoothened, CPD staff responsible for preparation of the TPTR petition shall call for one representative
from each department which provided such data to substantiate with sources, information so provided.
A total of 5 working days at the maximum can be set aside for such dispute resolution, as any further delay on
this count may adversely impact the adherence to timelines prescribed for final submission by EVNNPT. The
support of internal / external specialists can be sought for any clarification of complex nature.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 331
Part-C (iv): Public relations
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 332
Recommendation#1: Plan, set-up and operationalise a dedicated PR department within EVNNPT and its subsidiaries
Context
An extensive assessment of the public relations (PR) practices of EVNNPT and its subsidiaries was undertaken
by the visiting consultants. To conduct this assessment, detailed interviews were conducted with senior officials
and key officials responsible for communication across EVNNPT departments and select EVNNPT subsidiaries
based in Hanoi, Ho Chi Minh City and Danang. The consultants also studied relevant laws / decisions / decrees
/ regulations / circulars relating to the communication activities of EVNNPT. All available communication
plans of EVN, EVNNPT and its subsidiaries were also thoroughly examined. In addition, a Perceptions Audit
was carried out with select stakeholders to understand their assessment of EVNNPT and its subsidiaries. This
was a qualitative, dipstick study among key stakeholder groups to determine and analyse perceptions about
EVNNPT and its subsidiaries and the satisfaction quotient about the communication processes that these
organisations follow.
As per the findings of the Perceptions Audit:
1. NPT’s image and reputation are intertwined with those of EVN -which is seen widely as monopolistic
and unresponsive. Therefore, EVNNPT does not seem to have a strong independent brand identity.
2. NPT does not appear to enjoy a positive reputation amongst some of its stakeholders positive
reputation among a majority of the stakeholders The level of EVNNPT’s communication with the
general public appears to be inadequate
It is understood that a majority of EVNNPT’s projects get delayed -and mostly due to problems relating to site
clearance, compensation, land acquisition and rehabilitation. In addition, it is a constant challenge for EVNNPT
to maintain the inviolability of transmission corridors and ensure that breaches and accidents do not result in
unacceptably long disruptions in the uninterrupted supply of power.
It was found that EVNNPT and its subsidiaries do carry out a fair amount of communication work with regard
to their stakeholders. There is also some internal communication within the organisation and between its
subsidiaries. But the overall PR work is sporadic, disjointed and carried out on an ad hoc and tactical basis by
various departments and various executives. Much of the external stakeholder communication work is being
undertaken by EVNNPT’s General Affairs Department which has many other administrative duties. Most other
departments of EVNNPT think communication is the responsibility of the General Affairs Department. But the
General Affairs Department capacity is not equal to the task. The small PR team does not have the bandwidth to
do justice even to their limited responsibilities.
Despite the need for constant communication with stakeholders, there is no dedicated PR Department within
the organisation. In most of the subsidiaries, the part time staffs carry out the PR work. Among the executives
who handle PR work, in EVNNPT and its subsidiaries, there is an acute shortage of qualified, trained, or
experienced personnel in PR.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 333
The reason for this state of affairs is that PR is not seen as a strategic function or central to the working of
EVNNPT. It is essential to recognize that PR is critical for furthering the business objectives of EVNNPT. There
is a dire need for EVNNPT to have a fully empowered and adequately funded PR Department. Equally, there is
a need for EVNNPT to emerge from its self-imposed shell in PR. It must also not keep its subsidiaries at a
distance and maintain what is effectively an arm’s length relationship with them, especially in PR. It must
ensure that EVNNPT drives all communication relating to such vital areas as land clearance, land acquisition,
compensation, resettlement and rehabilitation of affected land-owners. It must also drive all communication
relating to the protection of transmission corridor.
The proposed dedicated PR department within EVNNPT will function as the central point for strategy, planning
and implementation of all communication initiatives and external stakeholder engagement undertaken by
EVNNPT through its own departments and/or its subsidiaries. It will drive all communication work, including
the development of Key Messages, in EVNNPT and its subsidiaries. Currently, the subsidiaries do PR work in
silos. There is no coordination or effort to take advantage of synergies. This lacuna can be addressed by having a
central PR department in EVNNPT and smaller PR departments for the subsidiaries - all working in concert. It
must reach out to its stakeholders much more than it does now. It must do so in a planned manner and in
concert with its subsidiaries.
This department would also spearhead the internal communication function within EVNNPT and its
subsidiaries alongside crisis communication, digital communication (including social media) and related
activities. It will act in tandem with local authorities and public officials whose interface with the ordinary
people will continue to be valued and leveraged to EVNNPT’s advantage.
Most importantly, given the organisational structure of EVNNPT vis-à-vis EVN, the proposed PR Department
would keep EVN informed and updated and would not work at cross purposes with EVN’s PR Department.
However, and this would be the critical difference from the current practice, EVNNPT’s PR Department would
be autonomous and would not take directions from EVN’s PR Department on strategy and major tactical
matters.
Benefits of an independent PR department
Above all, an internal PR Department at EVNNPT will understand the organisation as well as its business
objectives better and be best placed to drive communications. The PR Department will ensure that all
communication with stakeholder groups is in line with the company’s vision, mission and business objectives.
The major responsibility of the PR Department will be to interface with other stakeholder groups and build and
maintain positive relations with them. These stakeholder groups would include:
1. Government and relevant ministries;
2. Local authorities at all levels up to the province;
3. Ordinary people;
4. Influencers at all levels (including commune leaders);
5. International donors;
6. Business associates, including suppliers, contractors;
7. Generating companies, other power producers, distributing companies;
8. Consultants;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 334
9. Media; and
10. Employees.
Approach
The PR department should be headed by a member of the leadership team of EVNNPT and reports directly to
the President and CEO of EVNNPT. The chief executive should take a personal interest in the functioning of the
PR Department. This is because the CEO is the principal decision maker and chief spokesperson for the whole
organisation. When he drives policy in the organisation, it is only apt that he also gives direction to the
communication function. What the public relations department does must at all times be carefully coordinated
with the positions of the leadership team. Such senior level involvement will ensure that PR gets its due in
terms of organisational functioning and financial resources. The business goals of EVNNPT will be best served
by such an arrangement. Illustrated below is the four step process towards setting up and operationalising a PR
department:
Step-1: Defining the PR department’s objectives and scope
1. Define the PR Department’s role along with a clear statement of the team’s objectives and what specific
business need it will meet
2. List all the groups/departments that the PR Department will support and the level of support that will
be provided - both in EVNNPT and each subsidiary
3. Outline how the PR Department of EVNNPT will work with the smaller PR department in each
subsidiary
Step-2: Identifying deliverables and resource needs
1. Clearly outline the PR Department’s responsibilities & deliverables
2. List specific deliverables, frequency and timelines
3. Define the resources required based on the deliverables. These must be both human resources and
financial resources
Step-3: Determining team roles & responsibilities
1. Putting together the organisation chart and reporting structure
2. Outlining the roles and responsibilities of each executive
3. Determination of the skill set required in each executive
a. Professionally qualified PR professionals for, among other areas
i. strategy
Defining the PR Department’s objectives and
scope
Identifying deliverables and resource needs
Determining team roles &
responsibilities
Operationalising the new PR department
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 335
ii. routine work
iii. content for print, electronic media and Internet media
iv. media relations
v. community relations
vi. social media
b. Trainers (internal/external) to address training needs
4. Developing specific job descriptions for each of the members in the team
5. Developing clear measuring criteria in order to track performance of executives
Step-4: Operationalising the new PR department
Once the PR Department is officially launched, the following steps would need to be taken to operationalize it:
Stakeholder mapping
The first step would be to do stakeholder mapping: Develop databases of prominent members of all stakeholder
groups including, but not limited to the following Media
1. Media
2. Influencers
3. Those who are active on social media on issues of relevance
4. Leaders of the communes
5. Donor agencies
In Stakeholder Mapping, through a systematic process, we identify key members and opinion leaders within
each stakeholder group and assess their ability to influence the external environment on vital issues. This tool
provides an approach for greater strategic integration based on qualitative considerations. Our research seeks
to identify:
1. Important members of various stakeholder groups
2. Focus areas of various stakeholders groups and individuals
3. Likely friends, negative influencers or neutrals among these stakeholders
4. The greatest opportunities for engagement: for defensive or reactive purposes or for proactively seeking
opportunities for cooperation
Stakeholders are then plotted on a chart according to their ability to influence the external environment (Y-
axis) and the/organisation’s ability to engage with the stakeholder (X-axis). The result: a targeted list of
stakeholders that allows the organisation to prioritise engagement and track shifts over time.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 336
Preparing PR Plan
1. Prepare an annual PR Plan for EVNNPT and for each of the subsidiaries
2. A typical PR Plan has the following broad elements:
a. Situation analysis;
b. Business objectives;
c. PR objectives;
d. Target audiences;
e. Strategy;
f. Key messages;
g. Tactics; and
h. Activities.
These plans would be complete with timelines and tools for measurement.
1. Measurement is evaluating the effectiveness of a PR programme. There are different ways of
measurement. Broadly, these can be classified into the following categories:
2. Outputs: These look at Reach: for example, the number of news articles generated during the period
surveyed, their Advertisement Value Equivalent (the column centimetre cost of the editorial coverage
generated), their tonality (positive, negative, neutral), and whether they have carried the Key Messages
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 337
3. Outcomes: These look at Opinion: for example, the Perceptions Audit conducted among stakeholders
by the consultants - have the views of stakeholders changed at the end of the period under review, and
how have they changed
4. Business Results: These look at changes in Business Results: for example, the number of projects
delayed due to issues relating to site clearance and resettlement
Clearly, the first method is measurement of direct effectiveness and the third method is the measurement of
indirect effectiveness, while the second is in-between.
Thus, it is important to set measurable public relations objectives and link PR objectives to business and
organisational objectives.
Getting a clear understanding of an organisation’s business or performance goals is the PR Department’s first
step in setting measurable objectives for a communications programme. EVNNPT need to set objectives by:
1. Specifying a desired outcome like increase awareness, improved relationships, positive perception, etc.;
2. Directly specifying one or several target audiences and stakeholders;
3. Being measurable, both conceptually and practically; and
4. Including a time frame in which the objective is to be achieved.
Developing key messages
Key messages are at the heart of PR. Key Messages are core messages that EVNNPT’s target audiences will hear
and remember. Articulated repeatedly and consistently by spokespersons, either verbatim or paraphrased, Key
Messages will help the target audiences know exactly what EVNNPT stands for. They must form the bedrock of
the spokespersons’ statements. They will create meaning and headline the issues EVNNPT want to focus and
discuss. Key messages will allow EVNNPT to control communications and enhance relationships with the target
audiences.
The key messages and proof points should ideally:
1. reflect EVNNPT’s company strategy;
2. be credible and drive EVNNPT’s agenda;
3. reflect stakeholders’ understanding;
4. avoid negativity and enhance positive points;
5. use and enhance EVNNPT’s brand image; and
6. stand the test of time for a reasonable period.
As part of the deliverables in targeted capacity-building for this project, the consultants conducted a Key
Message Development Workshop for the leadership team of EVNNPT on October 15, 2014. Nearly a dozen of
the top managers of EVNNPT, including the Chairman of the Board of Management Members of the
Management Board, Heads of Department, and Vice Presidents, participated in the brainstorming session that
led to the finalization of the following key messages for EVNNPT:
1. By successfully covering the whole country with its state-of-the art transmission network, EVNNPT
provides the backbone of the national power system;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 338
2. By ensuring safe, stable and uninterrupted supply of power, EVNNPT plays a critical role in the social
and economic development of the country; and
3. NPT has a highly qualified, skilled, disciplined, devoted, responsible and humane workforce.
Developing media kit
A Media Kit would be a pre-requisite for a media relations programme or even a standalone media interaction.
The contents of it are meant for the use of the media person and her publication. Typically, a Media Kit for
EVNNPT or any of the subsidiaries would comprise the following:
1. A corporate profile or backgrounder on EVNNPT;
2. A corporate profile or backgrounder on the subsidiary;
3. Profiles of the leadership, including the spokespersons;
4. Pictures of the leadership;
5. Annual Report;
6. Material relevant to the media interaction where the Media Kit is given out: for example, if it is to be
given out at a press conference, then the news release meant for the event must be included;
7. Soft copies of all of the above;
Setting-up the processes
One of the early tasks of the newly set up PR Department would be to put in place processes, among others, for
the following:
1. Media Monitoring (in-house or outsourced) of the print, electronic and Internet-based media. What
appears in the media must be made available in the shortest possible time to a select mailing list of
recipients (within and outside the PR Department) at the head offices of EVNNPT and its subsidiaries;
2. Flow of information within EVNNPT (between the PR Department and the relevant departments) and
between EVNNPT and its subsidiaries - Internal Communication
3. Preparation, management and updation of lists (data-bases), including the following:
a. Media persons
b. Influencers
c. Government and public officials, including local authorities
d. Relevant executives within EVNNPT and subsidiaries
4. Stakeholder mapping is related to this activity.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 339
Other prominent functions of an independent PR department
Internal communication
NPT’s internal communication is limited, at this time, to the use of company websites, newsletters and
magazines. The information flow relating to PR between EVNNPT’s General Affairs Department and the
subsidiaries does not appear to be planned nor seamless or uniform. Internal communications - on a broader
level - can be extended to the staff members of EVNNPT and all its subsidiaries. This can include the exchange
of ideas and opinions, the development of professional relationships, updates and announcements. It can
empower them and spur them to perform optimally in their work. Structured internal communications
programmes can be put in place. Engaged employees accelerate business performance by going above and
beyond the call of duty, always looking for ways to create additional value for the business. They are focused on
value-creating behaviours during times of change or challenge. The proposed PR Department could develop
innovative campaigns for such employee engagement.
Two-Way Communication Models
Communication work that EVNNPT has been doing so far appears to be focused mostly on one way
communication. It is critical for EVNNPT to listen carefully to all stakeholders at all times. This is the only way
to understand the point of view of the stakeholders, especially those who are dissatisfied with anything that
EVNNPT or a subsidiary is doing or planning to do. This is particularly true of issues relating to land acquisition
or the maintenance and protection of transmission lines. Warning bells can ring early on and corrective action
can be taken before a potentially damaging situation spins out of control. Monitoring the local media is one
effective way of “listening”. Monitoring the social media and receiving feedback through social media constitute
another effective way. The social media platform is a very effective medium for two way communication. The
PR department needs to have trained and dedicated resources for handling social media engagement.
Crisis communication
NPT does not appear to have a crisis communication strategy in place for anticipating and combating crisis
situations that may arise during land acquisition for new projects and in securing the transmission corridor
from violators. There is need to develop a crisis manual that will anticipate all possible scenarios as well as plan
and prepare for mitigating the damage to reputation caused by those situations.
Corporate social responsibility
It is very important for companies in the infrastructure sector, especially those which have to deal with people
whose livelihood is land dependent, to undertake and / or promote socially beneficial activities and projects.
These activities and projects would be above and beyond the compensation, resettlement and rehabilitation
relating to land acquisition. Thus EVNNPT must have a comprehensive corporate social responsibility (CSR)
policy which is based on the needs of the communities which are being impacted (directly or indirectly) by its
projects. This CSR policy must be implemented by a CSR function either as a part of the PR Department or as a
separate department working in conjunction with the PR Department.
Priorities for the PR Department
1. Undertake a robust, proactive, multi-pronged PR campaign
2. Build an independent brand identity for EVNNPT
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 340
3. Take the lead and drive all communications relating to land acquisition and protection of transmission
corridor
4. Undertake an aggressive media outreach programme
5. Pay due regard to safeguard—whether of the environment or the rights and needs of indigenous peoples
and ethnic minorities
Model structure in Vietnam
We can refer to similar companies in other countries to study the structure and role of a PR Department.
We refer here to three companies: one in Vietnam and two in India - one in the private sector and the other in
the public sector.
FPT (The leading ICT company in Vietnam) - Communications Department
1. Structure: Communications Department is directly under the Management Board of FPT. It comprises
3 sub-departments which are PR, Branding and CSR.
2. Tasks: The PR sub-department implements communication activities for the whole FPT, including
communication support for all subsidiaries (investor relations included). Its main activities are media
relations, organising events, issuing press releases, writing PR articles, organising media interviews,
developing communication strategies (quarterly, yearly or ad-hoc)
The Branding sub-department’s function is to build and manage the brand, to participate in
sponsorship programmes to position the brand.
The CSR sub- department’s function is to focus on social sponsorship activities and to organize
contribution activities to support the staff of the company.
3. Workforce: 13 people, including 1 department head, 1 PR sub-department head and the rest are
executives.
The PR sub-department comprises 7 people, 1 based in Ho Chi Minh City and the other six in Hanoi. 1
is head, 1 is responsible for investor relations and the rest are in charge of subsidiaries.
Vietnam Airlines - The Division of Branding and Public Relations
1. Function: In Vietnam Airlines, PR is the responsibility of the Division of Branding and Public Relations.
This department is under the Department of Planning and Development with the function of
consultation for the Department Head on internal communication, corporate communication and
media relations in order to promote Vietnam Airlines’ image and to support sales following the
direction and development strategy of the organisation as a whole.
PR Tasks: To develop strategies, plans and implement strategic communication activities in Vietnam
and other key markets to build, protect and enhance Vietnam Airlines’ image in all networks;
a. To develop PR plans and implement communication activities to support sales, services and
product advertising in order to ensure general business productivity;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 341
b. To develop and implement plans for internal communication, media communication and crisis
communication;
c. To be the contact point in providing information to the media, both local and international;
d. To build and develop relationships of cooperation with media agencies, to organise media
related activities such as media conferences, media workshop, presentations, media field
trips/press tours, and to support the media in working with the other departments of the
organisation;
e. To be the contact point for Corporate Social Responsibility - CSR in the Sky Team; and
f. To write and edit content and speeches for the top leaders.
2. Structure: 5 sub-divisions (Planning, Design & Production, Advertising & Sponsorship, PR, and
Finance)
a. Number of staff: 23, including 1 Division Head and 3 vice-heads; and
b. Number of staff of PR sub-division: 4, including a vice-head and 3 executives.
3. Main activities: To cooperate with other departments to implement:
a. Media Relations;
b. Organising events;
c. Editing and publishing magazine for external audiences (partners, users, customers, etc.);
d. Editing and publishing in-flight magazine;
e. Internal communications;
f. Media monitoring;
g. Media analysis;
h. Crisis communications;
i. Community sponsorship; and
j. Direct non-commercial activities with customers.
Model structure in India
The company in the Indian private sector
The mentioned company is one of India’s largest integrated power sector companies. The Company together
with its subsidiaries and jointly controlled entities has an installed gross generation capacity of close to 10,000
MW in India and a presence in all the segments of the power sector.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 342
Organisation Chart of PR department
Roles and Responsibilities
1. Managing Director: As the chief executive, he/she is the key spokesperson for the company. He/she
is expected to be from a technical background and have a thorough understanding of both the
technological and commercial aspects of the business. He/she is expected to be knowledgeable and able
to tell audiences about his/her organisation in an interesting and compelling manner. He/she is
expected to be willing to meet the media whenever such meetings are called for and delivers the key
messages of the company unfailingly and consistently. He/she is the key decision maker on what issues
to comment on, which publication to talk to and what topics to speak on. Yet, on most PR related
issues, he/she is willing to be guided by the advice and recommendation of the PR Department.
2. Head - Corporate Communications: Runs the PR Department of the company and is responsible
for both internal and external communications and works directly with the Managing Director of the
company. This official ensures positive working relationships with key external stakeholders in a
manner that furthers the business interests of the company. The official also ensures that the
department delivers and executes an effective PR strategy along with a PR Plan to implement it.
Function of the position is to also ensure that an updated crisis manual is available to all relevant
executives and crisis drills are carried out at regular intervals. This official leads the engagement of the
PR department with various business heads and subsidiaries. Any content that is sent to the
stakeholders is reviewed and approved by this office.
3. Lead - Internal Communications: This position leads and coordinates the Employee Engagement
and Internal Communications Divisions, providing professional support to the organisation. This
function coordinates for news gathering across the business verticals and subsidiaries, identifying
internal issues and opportunities. He/She is also responsible for coordinating for the dissemination of
employee-related news to the media. He/She reports to the Head- Corporate Communication.
4. Lead - External Communications: This position coordinates the delivery of an integrated
communications and media service across all business verticals and subsidiaries. The official works
closely with the internal communication team to package newsworthy information for the media.
He/She produces all media collaterals and the monthly newsletter that is sent to various stakeholders.
He/She is the organisational point person for liaising with the PR agency hired by the firm for external
communications. As such, he/she is responsible for media relations, including all media events and
relationships with media persons. He/She is responsible for coordinating with various stakeholders
Managing Director
Head - Corporate Communications
Lead - Internal Communications
Lead - External Communications
Lead - Corporate Branding
Businesses: • - Generation • - Transmission • - Distribution • - Trading
Business Heads Subsidiaries Heads
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 343
outside the organisation. He/She collaborates with the digital team to align social media/blogging
content with wider digital objectives.
5. Lead - Corporate Branding: This position is responsible for the management and coordination of
all the activities under corporate marketing, including advertising. Thus, he/she is responsible for the
development of advertising campaign plans, coordination of the campaign development process;
briefing of campaigns to the subsidiaries and business units; execution of the campaigns; and the
monitoring and evaluation of those campaigns. He/She is also responsible for management and
coordination of brand initiatives such as participation in trade fairs and exhibitions.
The company in the Indian public sector
The Power Grid Corporation of India Limited (POWERGRID) is a state-owned electricity company.
POWERGRID carries about 50% of the total power generated in India on its transmission network.
POWERGRID operates throughout India. Its transmission network consists of roughly 101,886 circuit
kilometres and 170 EHVAC and HVDC substations, which provide total transformation capacity of 168,063
MVA. POWERGRID's inter-regional capacity is more than 32,000 MW. It has a subsidiary company, Power
System Operation Corporation Limited (POSOCO) which runs the five Regional Load Dispatch Centres and a
National Load Dispatch Centre. POWERGRID also operates a telecom business under the name POWERTEL.
Organisation Chart of PR department
Roles and Responsibilities
The PR Department of the company is headed by an executive of the level of General Manager. He reports
directly to an Executive Director, who is a member of the top leadership team of the organisation. The PR
Department oversees all aspects of internal and external communications across all stakeholders. The
department is manned by executives who have PR training and / or have experience of handling PR. Its key
responsibilities are as follows:
Chairman & Managing Director
Director - Personnel
General Manager - Public Relations & Communications
Chief Manager - Corporate Communications
Officer - Public Relations
Regional Heads Subsidiaries Heads
• - Northern • - Eastern • - Southern • - Western
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 344
1. Ensure that all positive initiatives of the company are highlighted through print/electronic/social
media;
2. Remove misinformation and allay misgivings in the public domain;
3. Develop and executive comprehensive PR plans in a timely manner. The plans must mention
ownership for all PR tasks, timelines and methods of measurement to ensure delivery;
4. Ensure there is a uniform set of messaging through the company to support its communications;
5. Ensure there is planned engagement with all stakeholders to convey the company’s perspective;
6. Ensure there are crisis communication plans in place for all possible scenarios.
European Union Prescription
The European Union (EU) has developed a "Grid Infrastructure Communication Toolkit” - a website that
outlines the elements essential for successful, inclusive project communication and multi-stakeholder dialogue
at the local level of any power grid development project in Europe.
The toolkit is designed along categories of communication and all factors involved in the context of
transmission projects. These include identification and engagement with the various Stakeholders involved, the
Project Stages, the Communication Channels, the Communication Formats and the Contents conveyed. Each of
these categories addresses the concerns of the different types of stakeholders along with addressing the needs of
the different project stages. These profiles are linked to one another showing how communication elements in
the context of transmission projects work together. The descriptions are accompanied by questions that will
help to identify the places where further, project-specific considerations are important. The toolkit also
provides several Practice Examples showing how different toolkit elements have proven to work in the
framework of real-life grid projects.
The toolkit can be accessed at http://www.grid-communications-toolkit.eu/. It would very useful to access this
material at the time of setting up the new department and adopt such practices as might be considered useful
and appropriate to the Vietnam context.
Indicative timelines
Month 1: Defining the PR
Department’s objectives and
scope
Month 2-5: Identifying
deliverables and resource needs
Month 6-8: Determining team roles &
responsibilities and appointing
staff
Month 9-13: Operationalising
the new PR department and
undertaking CSR activities
Month 14-18: Measure
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 345
Recommendation#2: Develop a Crisis Communications Manual
Introduction
The nature of EVNNPT’s business is such that there is always a likelihood of a crisis or a near-crisis situation.
Land is a sensitive issue in many parts of the world. Vietnam is no exception. Land acquisition for new projects
is not always a smooth operation. The number of EVNNPT projects that get delayed due to problems relating to
site clearance, land acquisition and resettlement is unacceptably high. Likewise, there are often issues that have
to do with the protection of transmission lines. Accidents and breakdowns are often caused by the breaching of
the safety corridor of transmission lines. Such crisis situations cause substantial financial loss to EVNNPT.
When there are project delays and power breakdowns, there is also loss of reputation and the loss of confidence
in EVNNPT of multiple stakeholders, including the ordinary public and the Government / political leadership.
Besides land and transmission corridor, there could be other causes of crisis for EVNNPT like, for instance fire
in an installation.
All of these make it absolutely imperative for the public relations team of EVNNPT to make crisis
communications a core competency. With effective crisis communications, a crisis is defused before it spins out
of control or causes substantial damage. Thus, delays due to land acquisition can be either eliminated or
significantly reduced. Likewise, the damage caused in the smooth functioning of transmission lines, and breaks
in the uninterrupted supply of power, can be limited to the bare minimum. Additionally, the proactive
communications that this would necessarily entail would contribute significantly in furthering the PR objectives
of EVNNPT.
So far, adequate attention does not appear to have been paid by EVNNPT to crisis communications. The reason
for this is perhaps that EVNNPT does not yet see communication related to land acquisition as its direct
responsibility. However, this will change once EVNNPT has an empowered PR Department with a full-fledged
PR programme that is multi-faceted and very proactive. Crisis communications would necessarily be an
important leg of such a PR programme.
The essential precondition for effective communications during crisis and pre-crisis situations is strategic and
tactical preparedness. It is critical for EVNNPT to have a Crisis Manual, copies of which should be available to
senior members of the PR departments in EVNNPT and its subsidiaries. If the Manual is stored online, then
these senior executives should have ready access to it. The following are the steps involved in crisis
preparedness, including the preparation of the Crisis Manual.
Strategy
We suggest the following four stage approach to the development of a crisis communication Manual for
EVNNPT.
Communications Audit
Analysis of the Audit report
Development of a Crisis
Communications Manual
Training
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 346
Communications Audit
The Communications Audit for Crisis will accomplish the following tasks:
1. Identify vulnerabilities in operations - weaknesses of EVNNPT that might cause a crisis situation
2. Identify image vulnerability - how any weakness or gap in public perceptions about EVNNPT may give
rise to a crisis situation
3. Identify the different kinds of crisis situations and the possible levels of risk. The following are some
obvious examples of the kinds of crisis situations:
a. A problem relating to site clearance and land acquisition;
b. A breakdown of transmission line;
c. A fire in an installation.
It would be important to identify all possible crisis scenarios, including those that are most unlikely to happen.
That would ensure preparedness for the worst cases as well as the least likely cases.
The communications audit will comprise of the following steps:
1. Evaluate systems currently in place for crisis communications. This would include evaluation of the
following:
a. Infrastructural and functional readiness. This would involve also surveying the physical
operations by making visits to on-site locations and critical off-site locations
b. Readiness and approach of the members of the leadership team at EVNNPT as well as in each
of the subsidiaries
2. Evaluate whether formal or informal crisis teams are in place in EVNNPT and in each subsidiary
3. Evaluate people-readiness and the skill set of executives likely to deal with crisis situations
4. Map and study current systems and protocols for internal and external communications in times of
crisis in both EVNNPT and its subsidiaries. The issues to be studied would include the following:
a. Internally, is it laid down who is to be informed and by whom and at which point, during pre-
crisis and crisis situations?
b. Externally, is it laid down who, among external (non-media) stakeholders is to be informed and
by whom and at what point during pre-crisis and crisis situations?
5. Is there a checklist of contacts in place with full contact details?
6. Is there a list of potential allies at vulnerable locations?
7. Evaluate existing protocols for media relations during pre-crisis and crisis situations. This would
include evaluation of the following:
a. Does EVNNPT and each subsidiary have in place a relevant media list a with full contact
details?
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 347
b. Are there are clear guidelines in place about proactively informing the media and reacting to
media queries?
c. Do EVNNPT and all subsidiaries have designated spokespersons and are they all media-
trained?
d. Are draft media statements and draft media releases in place?
e. Is there a list of potential allies in the media with their contact details?
8. Examine media coverage during past crisis situations to see whether there are any highlights or
patterns
9. Evaluate the hardware and equipment available to those handling PR at EVNNPT and its subsidiaries
10. Evaluate perceptions about EVNNPT among key stakeholders, especially the public, in vulnerable
locations where crisis situations may arise. This would include an evaluation of cultural and attitudinal
factors at play in crisis-prone regions
11. Collect and analyse information about crisis situations from the past. This will include analysis of media
coverage
12. Carry out a thorough analysis of the social media coverage of EVNNPT in general and previous
coverage, if any, of crisis situations
13. Conduct a review of the online presence (websites, etc.) of EVNNPT and its subsidiaries
Analysis of the Audit report
This exercise will consist of a gap analysis and a needs assessment. This means identifying the gaps between
current practices and best practices and then assessing what needs to be done to close those gaps.
Development of a Crisis Communications Manual
Comprising more than just Standard Operating Procedures, this document will have the following:
1. Definitions of crisis situations so that users of the manual might be able to identify them. By that token,
they also know when action is called for and when not. Degrees of crisis are also specified;
2. Step by step instructions on the course of action to be taken in the event of every kind of crisis;
3. Crisis Response Teams by office with names of executives and their contact numbers;
4. Duty assignment: who will do what in the event of different kinds of crisis and their powers of decision
making;
5. Crisis contact list within the organisation;
6. Checklists of who in the organisation is to be notified and at what stage. This includes notifying the top
management. For instance, some organisations divide crisis situations into three broad levels: A, B and
C levels. “A” Level crisis situations require that the top management be notified within two hours. “B”
Level crisis situations require that the top management be notified within 24 hours, while “C” Level
crisis situations require that the top management be notified after the crisis is over;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 348
7. Guidelines on alerting or notifying authorities outside the organization - who and at what stage. These
would include local authorities, regulators and government officials, etc.;
8. Guidelines on how exactly information is to be shared;
9. Methodology for maintaining records and keeping logs. The system would include logging calls from
stakeholders and communicating key points to relevant executives;
10. Specific instructions on what kind of crisis and what degree of crisis merit internal communications
(employee communications) and the manner of disseminating information within the organization and
obtaining feedback where required;
11. Guidelines on communications with the local community at crisis locations. These would spell out also
how to deal with village folk perturbed by any step taken by EVNNPT with regard to land acquisition or
transmission corridor. This would also list out common perceptions and region-wise peculiar cultural
and attitudinal factors and how to respond to all of these;
12. Region and area-wise list of allies and positive influencers who can be mobilized to help EVNNPT
respond to people’s concerns;
13. Complete guidelines on media relations - both proactive and reactive. These will comprise the
following:
a. Names of designated spokespersons;
b. Names of team leaders and members of crisis teams in EVNNPT, subsidiaries and their offices
with full contact details;
c. Names of special Crisis Media Unit in every organization (NPT and subsidiaries and their
branch offices) This would comprise one or more designated executives from the PR
Department who would be earmarked exclusively for media relations during a crisis;
d. Relevant media lists with contact details;
e. Names of media allies;
f. Names of third party influencers who could be persuaded to talk to the media and lend indirect
support;
g. Guidelines on responding to media queries;
h. Guidelines on proactively going to the media through statements, press releases, media
briefings, press conferences or electronic media appearances / interviews;
i. Template of holding statements for the media;
j. Template of proactive statements for the media;
k. Template of press releases for likely crisis situations and degrees thereof;
l. Draft Q’s and A’s and issues & responses document for use in answering questions from the
media. Whenever crisis occurs, these can be quickly modified and tailored to suit the needs of
the situation;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 349
m. Do’s and don’ts of dealing with the media during crisis situations: What spokespersons are
permitted to say and what they are not;
n. System for maintaining logs of media calls;
o. Special guidelines for monitoring the media, including the online media, during crisis
situations;
p. Guidelines on Social Media activities for crisis mitigation;
q. Guidelines on the use of the print publications, electronic media and online presence (websites,
etc.) of EVNNPT and its subsidiaries for crisis mitigation;
14. System for conducting post-mortem after a major crisis; and
15. Emergency summary cards for each office: These would list, in simple language, the immediate first
steps to be taken in the event of a crisis - even before the Crisis Teams get activated.
Training
Crisis preparedness would be incomplete without training and testing through mock drills. Training for crisis
preparedness would involve the following:
1. Media training for all spokespersons;
2. Extensive briefings of relevant executives at EVNNPT and subsidiaries and their offices outside head
office;
3. Mock drills or simulations of crisis situations followed by extensive analysis;
4. Follow-up action basis the above-mentioned analysis of mock drills.
The Crisis Communications Manual must be periodically reviewed and necessary revisions carried out. A year is
a reasonable period after which a review must be carried out.
Indicative timeline
Month 1: Communication
Audit
Month 2: Analysis of Audit Report
Month 3-5: Development of
Crisis Communications
Manual
Month 6: Training
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 350
Recommendation#3: Develop uniform key messages for EVNNPT through a workshop
Summary
Title of the workshop: Develop uniform key messages for EVNNPT
Date & Time: 15 October 2014, 7.30 am - 11.30 am
Venue: Meeting Room No. 202, Second Floor, EVNNPT, 18 Tran Nguyen Han, Hanoi
No. of participants: 11
Training material: --
List of participants
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 351
Introduction
From a communications or PR perspective, it is imperative for any organisation to have the following:
1. A limited number of authorised spokespersons.
2. The spokespersons say only that which is in alignment with the business and communications
objectives of the organisation.
3. The spokespersons sing from the same sheet - meaning there must be total alignment between what
they say individually. They must deliver the same key messages.
4. The spokespersons drive the agenda in every interaction with the target audience--the media or any
other audience.
Every organisation, every brand and even every business initiative must have its own set of key messages. Key
messages, articulated repeatedly and consistently, will help audiences know exactly what the organisation /
brand / business initiative stands for just the way the spokespersons want them to—nothing more, nothing less.
These key messages must form the bedrock of the spokespersons' communications. Regardless of whatever else
they may say, they must deliver these messages--either verbatim or by paraphrasing them. The key messages
must stand the test of time in the medium term. They must be reviewed after a reasonable length of time for re-
validation or revision.
When a spokesperson drives the agenda in a media interaction, he responds to media queries, but regardless of
whatever else he says, he also puts across the key messages. Not necessarily verbatim, but woven into the
narrative, as it were. The messages have to be conveyed with the aid of facts and statistics as well as illustrations
from the working of the organisation -- the on-the-ground situation.
Focused, timely and pro-active communication of well-defined and clear messages is of critical importance for
EVNNPT as it embarks on using effective PR as an essential and indispensable tool to achieve its business
objectives.
The key messages will provide a base or an underpinning to all other PR statements or messages delivered by
EVNNPT. They will reinforce EVNNPT’s PR, including the delivery of all other messages.
In the message development workshop, the senior management of the company will engage in a brainstorming
session moderated by the consultants. This brainstorming session will be neither open-ended nor freewheeling.
There is a structure to it and the consultants will ensures that the discussion remains within the ambit of that
structure.
The objective of the workshop is to come up with a set of key messages or communications themes.
Structure
On the following pages, we cover eight steps to arrive at the key messages. Please use them as worksheets. Your
inputs are vital, invaluable and the very basis of this workshop.
Step-1: Set business objectives
What do we want to accomplish through PR / communication?
1. Uninterrupted, safe and stable power transmission
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 352
2. Maintain efficiency
3. Maintain profitability
4. Serve society
5. Serve the national economy
Step-2: Identify target audiences
Who do we want to reach?
1. Government and relevant ministries
2. Local authorities, including provincial authorities
3. Ordinary people
4. International donors
5. Suppliers (including contractors)
6. Consultants
7. Media
Step-3: Analyse issues: facts
What are the salient things we want to say about EVNNPT? (Positive facts)
1. NPT provides and maintains the backbone of the power network in Vietnam
2. NPT plays a very important role in the social and economic development of the country
3. NPT is a state tool for governing the power market
4. NPT is the bridge connecting power producers and consumers
5. NPT has successfully covered the whole country with its transmission network
6. NPT ensures the supply of power - safely, stably, and continuously
7. NPT’s rate of power losses meets international standards
8. NPT provides a state-o-the -art transmission network
9. NPT has highly qualified, skilled, disciplined, and devoted human resources
Step-4: Analyse issues: facts
What are the questions we want answered? (Negative facts)
1. There are difficulties in site clearance
2. Transmission tariffs are low. Internationally, these are 10-12 % of retail prices to end users, in Vietnam
the corresponding figure is 5.5%
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 353
3. There are difficulties in transmission corridor protection
4. There are difficulties in forecasting & planning for power demand
5. There are difficulties in determining the development, planning and progress of power generation
6. There are difficulties in the mobilisation of funds for construction work
7. Low profitability
8. Reliability is not very high
9. Difficulties in implementation of government regulations & procedures on construction investment,
site clearance and tariffs
10. Difficulties in recruitment of staff in rural & mountain areas
11. Difficulties in the utilisation of linesmen who are older than 45
12. It is a difficult and dangerous job for the operational staff
Step-5: Analyse issues: perceptions
What are the impressions we want to create or reinforce? (Positive perceptions)
1. NPT and the national power transmission system play a very important role in the social & economic
development of the nation
2. NPT has a highly qualified, skilled, disciplined & devoted workforce
3. NPT owns a modern national power transmission system that meets international standards
4. NPT’s transmission power loss rates meet international standards
5. NPT keeps in mind (the need to) provide enough power for socio-economic development and people’s
lives
6. It is the responsibility of all of us to safely protect the national power transmission system
7. NPT tariffs are low (from the consumer’s point of view)
Step-6: Analyse issues: perceptions
What are impressions we want to dispel or remove? (Negative perceptions)
1. NPT projects are always delayed
2. High power transmission loss rates
3. EVN association: low productivity, high power tariff, low responsiveness (monopoly)
4. Low compensation
5. Transmission projects do not bring direct benefit to local people
6. Transmission lines have a harmful health impact
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 354
Step-7: Develop important messages
What are the principal messages? (Keywords suggested by Chairman)
1. Modern
2. Responsibility
3. Disciplined
4. Humane resources (aim for)
5. Important
Step-8: Develop key messages
What are the key messages?
1. By successfully covering the whole country with its state-of-the art transmission network, EVNNPT
provides the backbone of the national power system
2. By ensuring safe, stable and uninterrupted supply of power, EVNNPT plays a critical role in the social
and economic development of the country
3. NPT has a highly qualified, skilled, disciplined, devoted, responsible and humane workforce
Outcome and feedback
The workshop helped identify and develop the key messages for EVNNPT as outlined in the workshop content:
1. By successfully covering the whole country with its state-of-the art transmission network, EVNNPT
provides the backbone of the national power system;
2. By ensuring safe, stable and uninterrupted supply of power, EVNNPT plays a critical role in the social
and economic development of the country; and
3. EVNNPT has a highly qualified, skilled, disciplined, devoted, responsible and humane workforce.
Another prominent aspect of the workshop was that it was attended by the Chairman of the Management Board
for EVNNPT. Following this workshop, EVNNPT contacted the PR experts to judge and shortlist slogans from a
slogan competition organised by the Company. In addition to shortlisting the slogans, the PR experts also
provided additional recommendations for slogans to EVNNPT.
Slogans shared by EVNNPT
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 355
Sr. No.
Content Copywriter Agency
45 slogans from EVNNPT slogan creation contest
A EVNNPT
1. Soi sáng tương lai Light up the future
Phạm Văn Trường Ban TCCB & LĐ
B CÔNG TY TRUYỀN TẢI ĐIỆN 1
2. EVNNPT Truyền tải niềm tin (câu này trùng ý tưởng nhiều tác giả) EVNNPT - Trust Transmission
Trần Minh Tuấn BGĐ - Công Ty TTĐ1
3. Truyền tải vươn xa - thắp sáng mọi nhà Transmission toward further - light up all houses
Phạm Văn Cường Trạm 500kV Thường Tín-Công ty TTĐ 1
4. Truyền tải Quốc Gia - Không ngừng vươn xa National transmission - Never stop to reach further
Phạm Văn Cường Trạm 500kV Thường Tín-Công ty TTĐ 1
5. Truyền tải điện: Kết nối tương lai Power Transmission: Future Connection
Chu Xuân Khoát Trạm 500kV Thường Tín-Công ty TTĐ 1
6. Truyền tải điện quốc gia - Hạnh phúc cho mọi nhà! NATIONAL POWER TRANSMISSION - HAPPINESS TO EVERYONE!
Hoàng Văn Lược Phòng.TTBV&PC - Công ty TTĐ 1
7. EVNNPT Dong điên thăp sáng niêm tin EVNNPT Power light up the trust
Hồ Văn Hồng TTĐ Hoa Bình Công ty TTĐ 1
8. EVNNPT Thắp sáng tương lai EVNNPT Light up the future
Nguyễn Quốc Dân TTĐ Hoa Bình Công ty TTĐ 1
C CÔNG TY TRUYỀN TẢI ĐIỆN 2
9. Sức mạnh niềm tin vươn xa Nghiêm Xuân Hoàng Đội truyền tải điện Komplong
10. An toàn - Ổn định - Sáng tạo - Hiệu quả Safety - Stability - Innovation - Efficiency
Nguyễn Ngọc Phước Đội truyền tải điện ĐăkTô
11. An toàn - Liên tục - Hiệu quả Safety - Continuation - Efficiency
Phạm Công Long Đội truyền tải điện ĐăkTô
12. An toàn - Chất lượng - Hiệu quả Safety - Quality - Efficiency
Huỳnh Tấn Phú Đội truyền tải điện ĐăkTô
13. Truyền ánh sáng, tải niềm tin Transmit light, bring the trust
Nguyễn Thế Thành Truyền tải điện Qua ng Bình
14. Không chỉ là điện Not just power
Nguyễn Tấn Khôi Tra m biên áp 500 kV Qua ng Nga i
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 356
Sr. No.
Content Copywriter Agency
15. An toàn, tin cậy, chất lượng, hiệu quả Safety, reliability, quality, efficiency
Đặng Khánh Ly Tra m biên áp 220 kV Dung Quât
16. Kết nối năng lượng - Dẫn bước tiên phong Power connecting - To pioneering step
Nguyễn Thế Mạnh
17. EVNNPT gưi tro n niêm tin EVNNPT fully deliver the trust
Trân Khương Non Đô i Truyên ta i điên Sơn Hà
D CÔNG TY TRUYỀN TẢI ĐIỆN 3
Văn phòng Công ty
18. EVNNPT - Vững bước tiên phong, đồng hành phát triển. Pioneer of innovation, companion of development
Văn phong Công ty A. Phú CVP là nhóm trưởng
19. EVNNPT - An toàn - Hiện đại - Bền vững Safety - Modernity - Sustainability
Văn phong Công ty A. Phú CVP là nhóm trưởng
20. EVNNPT - Không giới hạn, Không khoảng cách NPT: No Limit - No Distance
Truyền tải điện Pleiku
21. Truyền sức mạnh - tải niềm tin Transmit the power, load belief
Đặng Đức Lý Giám đốc
22. Rạng ngời huyết mạch Việt Nam Vietnam arterial shine
Nguyễn Tuyên
Truyền tải điện ĐăkLăk
23. EVNNPT kết nối sức mạnh, toả sáng tương lai Connect the power, shining future
Trương Công Ân Phó Giám đốc
24. EVNNPT - Nối nguồn ánh sáng Connect the light source
Phan Thị Hiền
25. EVNNPT Truyền tải niềm tin- Thắp sáng tương lai Transmission beliefs - Lighting the future
Lê Thị Thoả
26. Ánh sáng của mọi nhà, năng lượng của mọi nơi Light of every houses, energy of everywhere
Nguyễn Tiến Dũng
27. EVNNPT - Kết nối điện năng, sẻ chia phát triển EVNNPT - Power connection, development share
Hoàng Văn An
Truyền tải điện Ninh Thuận - Cam Ranh
28. Tải đủ, truyền xa, quốc gia thịnh vượng. Efficient and far-reaching transmission makes a prosperous country
Trương Thị Bích Loan
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 357
Sr. No.
Content Copywriter Agency
Truyền tải điện Cao Nguyên
29. EVNNPT Đi cùng năm tháng thắp sáng tương lai EVNNPT Along the years light the future
Võ Ngọc Sơn
30. EVNNPT - Năng lượng để phát triển bền vững EVNNPT - Power for firm development
Đỗ Phi Hùng Phó Giám đốc
31. EVNNPT Kết nối nguồn năng lượng EVNNPT - Connecting electric power
Phan Đình Minh
Trạm biến áp 500kV Pleiku
32. EVNNPT Xuyên suốt mọi miền, nối liền dòng điện. Through everywhere, connecting electric current
Huỳnh Quang Thịnh
33. EVNNPT Chắp cánh cho dòng điện vươn xa. Winging for current's development
Đào Ngọc Sơn Chủ tịch CĐ
E CÔNG TY TRUYỀN TẢI ĐIỆN 4
34. Truyền tải nguồn sáng, kết nối tương lai Transmission of the light source, connected future
Nguyễn Tấn Danh Trưởng phiên trạm 220KV Cai Lậy
BAN QUẢN LÝ DỰ ÁN CÁC CÔNG TRÌNH ĐIỆN MIỀN BẮC
35. EVNNPT-Đưa điện đủ đến đời. EVNNPT- Transmitting power enough for life.
Đoàn Ngọc Hưng Trưởng Phòng Tổng hợp Ban Quản lý Dự án các công trình điện miền Bắc
36. EVNNPT-Truyền tải năng lượng Việt. EVNNPT-Transmitting Vietnam power.
Đoàn Ngọc Hưng CV. Phòng Tổng hợp Ban Quản lý Dự án các công trình điện miền Bắc
37. EVNNPT- Vì một Việt Nam tràn đầy năng lượng EVNNPT - For Vietnam full of power
Trần Thị Hạnh CV. Phòng Kỹ thuật Ban Quản lý Dự án các công trình điện miền Bắc
38. EVNNPT- Khơi nguồn sáng EVNNPT - Create light source
Trần Thị Hạnh CV. Phòng Kỹ thuật Ban Quản lý Dự án các công trình điện miền Bắc
39. EVNNPT- Một phần tất yếu của năng lượng Việt. EVNNPT- A part of Vietnam power.
Trần Thị Hiền CV. Phòng Tổng hợp Ban Quản lý Dự án các công trình điện miền Bắc
40. EVNNPT- Truyền tải điện - Truyền tải mạch sống Việt EVNNPT- Transmit power - Transmit Vietnam life source
Trần Thúy Ngân CV. Phòng Tổng hợp Ban Quản lý Dự án các công trình điện miền Bắc
BAN QLDA CÁC CÔNG TRÌNH ĐIỆN MIỀN TRUNG
41. Lưới điện vươn xa, nhà nhà hạnh phúc The further the power grid reaches, the more happiness it brings to us
Phan Thị Hằng Ban QLDA CCT Điện Miền Trung
42. Vượt qua thách thức, tháp sáng tương lai Overpassing challenge, lighting up future
Phong ĐT Ban QLDA CCT Điện Miền Trung
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 358
Sr. No.
Content Copywriter Agency
43. Có điện, có phát triển - Đủ điện, đủ tiện nghi
Hoàng Nam Ban QLDA CCT Điện Miền Trung
44. Lưới điện vươn xa - nước nhà tiến tới The power grid reach further - the nation reach higher
Hoàng Nam
BAN QLDA CÁC CÔNG TRÌNH ĐIỆN MIỀNNAM
45. EVNNPT: Truyền tải sức mạnh, truyền tải niềm tin EVNNPT: Transmit the power, Transmit the faith
Phạm Hữu Chương CV. Phòng Kỹ thuật Ban Quản lý Dự án các công trình điện miền Nam
9 slogan from creative agency
1. Truyền khát vọng, bật tương lai Transmit aspiration, gain future
2. NPT: Lan tỏa hạnh phúc, hội tụ niềm tin NPT: Share happiness, converge belief
3. NPT: Xây tầm cao mới, hướng tới tương lai NPT: Toward higher reach, toward future
4. Lan truyền văn minh, khởi nguồn khát vọng Spreading civilization, originating aspiration
5. NPT: Mang ánh sáng hạnh phúc đến muôn nhà NPT: Bring the light of happiness to all
6. NPT: Dòng chảy phồn vinh NPT: The flow of prosperity
7. Huyết mạch cuộc sống The vessel of life
8. An toàn trên từng đường dây Safety in each line
9. Tận tụy từ trái tim Dedication from the heart
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 359
Slogans shortlisted by the PR expert:
1. Sr. No. 1 & 8: Light up the future
2. Sr. No. 10: Safety - Stability - Innovation - Efficiency
3. Sr. No. 14: Not just power
4. Sr. No. 15: Safety, reliability, quality, efficiency
5. Sr. No. 19: Safety - Modernity - Sustainability
6. Sr. No. 28: Efficient and far-reaching transmission makes (for) a prosperous country
7. Sr. No. 42: Overpassing challenge, lighting up future
8. Sr. No. 44: Power grid reach further - nation reach higher
Selection from the slogans submitted by the creative agency:
1. Sr. No. 1: Transmit aspiration, gain future
2. Sr. No. 5: Bring the light of happiness to all
Additional slogans submitted by the PR experts:
1. Transmitting prosperity
2. Transmitting a better life
3. Overcoming challenges to light up the future
4. For a better life for all
5. We help build the nation
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 360
Recommendation#4: Leverage the social media for EVNNPT’s PR work
Context
Visiting consultants studied the public relations practices of EVNNPT and its subsidiaries by interacting with
the key officials responsible for communication alongside reviewing the available documentation on the
Company’s practices.
One of the findings of the study is that EVNNPT is not active in the social media arena though EVNNPT uses
online media. It primarily implies that EVNNPT and its subsidiaries do not actively engage in social media
platforms like Facebook, Twitter, YouTube and online blogs.
On reviewing the statistics for internet penetration & usage; and social media usage in Vietnam it is revealed
that the internet penetration in Vietnam, is nearly 40% -well above the global average of 33%. Internet is
available in every commune in even the rural areas of the country. A Vietnamese accesses the Internet on an
average 5.6 hours per day, 6.4 days per week. The average time of using the Internet is 4 hours and 37 minutes
per day. As many as 34% of mobile users access the Internet on mobiles, while the average time of mobiles
users accessing is 1 hour and 43 minutes per day.
Over 38% of the population uses social networking, with an average daily usage time of 2 hours and 23 minutes.
There are 20 million Facebook accounts in the country. Every 3 seconds a new Facebook account is created
indicating the popularity of Facebook and other similar platforms.
The explosive growth of social media across the world indicates social media to be a powerful PR tool.
Increasing number of participants in social media has resulted in increasing discussions on all possible topics of
interest - including those relevant for the various businesses. Social media is also a platform for activism and
anti-business discussion. It is important for companies and brands to be aware if they are being talked about
and then to influence such conversations to their advantage. Conversely, it is equally important for companies
and brands to join the conversation flow and spread positive messages about themselves and their business
initiatives. It follows then that if companies or brands are not on social media not only are they missing a huge
opportunity to influence public opinion, but are also laying themselves open to considerable damage by the
unhindered flow of negative messages.
It is worth mentioning that while social media allows unmediated and direct access to stakeholders, this
directness can hurt companies and brands badly when negative messages go viral in no time and, additionally,
get picked up by traditional media. Not surprisingly, organisations around the world are not only using social
media as an integral part of their multi-pronged PR programmes but are finding new and innovative ways of
doing so.
Recommendations
It is important therefore for EVNNPT - as it sets up an independent PR Department and adopts a robust,
vigorous and proactive PR programme, driving communication along multiple channels - to seek to leverage
social media as an indispensable PR tool. While social media may not be the best option for reaching out to
target audiences in rural areas (direct communication with opinion leaders may be the best way to reach out to
audiences in matters of land acquisition), it is certainly a credible and effective way to spread the message
alongside brand building. It is important to imaginatively utilise social media platforms to reach out to various
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 361
stakeholders and engage with them on a continuous basis. Thus, it is critical to develop a proactive, sustained
and inclusive social media engagement programme for EVNNPT that delivers on the following:
1. Helps build a separate brand identity for EVNNPT throughout the digital community;
2. Creates and reinforces positive perceptions about EVNNPT centering around the corporate Key
Messages;
3. Identifies potential crisis situations and addresses them through an effective response mix.
NPT’s Key Messages, as decided by its leadership team, are as follows:
1. By successfully covering the whole country with its state-of-the art transmission network, EVNNPT
provides the backbone of the national power system;
2. By ensuring safe, stable and uninterrupted supply of power, EVNNPT plays a critical role in the social
and economic development of the country;
3. NPT has a highly qualified, skilled, disciplined, devoted, responsible and humane workforce.
Strategy
Under this section we have detailed out a step by step strategy that is required to develop a plan for leveraging
social media
Listen
1. Track existing conversation on social platforms like Facebook, Twitter, Online blogs, by using relevant
keywords. These could include topics of interest for the brand, or issues of concern for the Company or
the industry;
2. Detailed tracking of all online conversation on defined topics or relevant issues.
Analyse
1. Use analytics to derive insights across various themes, topics, demographics related or relevant to
EVNNPT;
2. Need to understand positions and habits of regular social media users and influencers;
3. Analysing tonalities and trends of conversations on social media platforms.
Note: Social media measurement tools can be expensive. But free or low cost options are also readily available.
These include Google Alerts, Google Analytics, and Hootesuite.
Plan
Marrying insights gathered in Stage 2 with the business and PR objectives of EVNNPT, a detailed action plan
needs to be prepared. This action plan to include:
1. a proactive approach towards content dissemination - identifying topics, tonality and tools for
dissemination of content;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 362
2. a robust approach to mitigate reputational damage by responding to negatives in the quickest possible
time.
Create
1. Create content on various aspects of EVNNPT’s work;
2. Prepare ways to create content in almost real time to counter negatives;
3. Develop a list of influencers to carry positives, including key messages;
a. Third-parties;
b. Bloggers;
c. Focus groups.
Engage
1. Engage with bloggers and tweeters to post the information online;
2. Invite public to participate in the discussion;
3. Engage with third parties for content development and posting.
Execute
1. Create and publish content along with executing campaign ideas;
2. Amplifying key messages through relevant channels.
Measure
1. Devise and carry out measurement by generating reports around keywords, themes, topics and cull
insights that could be relevant to EVNNPT.
Content Opportunities
1. All press releases on new developments and initiatives at EVNNPT being disseminated among print
and electronic media journalists or being uploaded on the EVNNPT’s website should also be
disseminated on platforms like Facebook and Twitter. This might even be better than contributing to
clog the inbox of journalists. They can be reached on platforms they visit on a regular basis;
2. Information, pictures and videos about various proactive initiatives of EVNNPT can be posted on these
platforms and these stories can reached to a greater mass of people directly in real time;
3. The Perceptions Audit carried out by the consultants has revealed that the general public does not know
enough about the CSR activities of EVNNPT. These initiatives can be publicised on social platforms;
4. Links to online coverage received by EVNNPT press releases can be posted on social media;
5. Suggested topics for positive conversation online:
a. Information on EVNNPT’s transmission projects at Vietnam;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 363
i. Announcement of new projects;
ii. Information on the project management and progress;
iii. Completion of projects;
iv. Expansion of existing projects;
b. Richer content in terms of pictures, video, infographics with positive messaging about the
contribution of EVNNPT to the socio-economic development of the country;
c. Content relating to the Key Messages of EVNNPT can be posted;
d. Short videos on public safety can be posted;
e. Videos on success stories of EVNNPT in handling land acquisition;
f. Create content around the theme of EVNNPT building and maintaining the backbone of the
power sector in Vietnam and the theme EVNNPT helps transform the lives of people;
g. Highlight best practices undertaken by EVNNPT; and
h. Facts and infographics on the Vietnam power sector and on EVNNPT projects.
6. An awareness campaign on the inviolability of the transmission corridor can be prepared and
implemented through social media.
Tactics
Greater engagement with the online community can be achieved by the following tactics:
6. Create a Facebook page for EVNNPT for carrying branded content;
7. Create a Twitter handle for EVNNPT. Give viral reach to positive buzz, using influencers to amplify;
8. Monitor negative postings and put out own point of view, without getting into arguments with those
posting negative content;
9. Create a microsite titled “Humane EVNNPT”. This will host all content that will position EVNNPT as a
caring organisation that builds and maintains the backbone of the power sector in Vietnam;
10. Use YouTube as a personalised channel that will host all video based content;
11. Ross post industry information;
12. Post links to positive messages about EVNNPT, including re-tweets, cross-posting topics of relevance;
13. Express thanks by cross-posting and replying, “favouring” and following those who talk positively about
the brand;
14. As part of an Influencer Outreach Programme, build and maintain relationships with online influencers
who will serve as EVNNPT’s brand advocates and help convert their audience into brand advocates. An
independent third party perspective has a positive impact on the public. The content can be posted on
various platforms;
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 364
15. Develop small groups on social media who will discuss on industry issues like land acquisition and
project delays, giving full play to EVNNPT’s positions on contentious issues;
16. Create social media campaigns using positive case studies: instances where issues relating to land
acquisition or transmission corridor protection have been handled in a positive manner leading to high
levels of satisfaction among the affected people;
17. Use traditional media to amplify the positive postings on social media; and
18. Measure success using online monitoring tools and modify engagement plan accordingly.
Indicative timeline
Month 1-2: Listening
and Tracking
Month 3-5: Analysis
Month 6-8: Plan and
Create Plan
Month 9-11: Engage
Month 12-16: Execute
Month 17-18: Measure
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 365
Recommendation#5: Plan, set-up and operationalise a dedicated CSR department within EVNNPT
Context
An extensive assessment of the public relations (PR) practices of EVNNPT and its subsidiaries was undertaken
by the consultants. To conduct this assessment, detailed interviews were conducted with senior officials as well
as key officials responsible for communication across departments of EVNNPT and select subsidiaries based in
Hanoi, Ho Chi Minh City and Danang. The consultants also studied relevant laws / decisions / decrees /
regulations / circulars relating to the communication activities of EVNNPT. All available communication plans
of EVN, EVNNPT and its subsidiaries were also thoroughly examined. A Perceptions Audit was carried out. This
was a qualitative, dipstick study among key stakeholder groups to determine and analyse perceptions about
EVNNPT and its subsidiaries and the satisfaction quotient about the communication processes that these
organisations follow.
During the course of this study, it was found that EVNNPT undertakes many corporate social responsibility
(CSR) initiatives, though these are neither described nor seen as such. Furthermore, the impact of many of
these activities could be perceived to be inadequate to build positive perceptions about EVNNPT in the public
mind. Additionally, the Perceptions Audit revealed that most of the stakeholders feel the quantum of CSR
activity that EVNNPT undertakes was is unsatisfactory. A significant chunk of the respondents in the
Perception Audit were not aware of the CSR activities undertaken by EVNNPT. Currently, there is no
department or unit in EVNNPT that is in charge of CSR. Activities related to CSR are carried out by different
departments and different unions. Overall, the CSR effort appears to be somewhat disjointed and devoid of
focus with no net gain coming to EVNNPT out of them.
Benefits of a robust CSR programme
All over the world, companies and brands are moving CSR towards the centre of their overall business strategy.
In 2014, in the Trust Barometer global survey carried out by Edelman (the leading PR firm) it was found that
84% of the respondents believed a company can pursue its self-interest while also doing good work for society.
In its 2012 “goodpurpose” survey, Edelman found that 87% of the respondents believed business should place
at least equal weight on both business and society. In response to this groundswell of opinion in favour of
companies being socially more responsible, leading organisations and brands have been leveraging their
resources to tackle social and environmental challenges and make a positive difference on societal issues.
There are many names to this business response:
1. Citizenship: A company's responsibility to the communities in which it operates and to society at
large;
2. Sustainability: A business approach that creates long-term stakeholder value by embracing
opportunities and managing risks deriving from economic, environmental and social developments
stemming from the manner in which a company is run;
3. Philanthropy: A company’s donation of funds, time or talent without any expectation of direct
corporate gain - such as increases in revenue; and
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 366
4. Purpose: The strategic, emotional driving force behind an organisation / brand’s core value
proposition.
CSR enables a company to associate itself with a higher social good. It allows the company to differentiate itself
before a diverse set of stakeholders. It builds, protects and enhances reputation. It creates goodwill for the
company, especially in areas of operation and reduces risk by opening channels of communication.
CSR engages and inspires all categories of stakeholders, including customers and employees in an increasingly
connected world. It is a useful way to mobilise, unite and motivate all the people a business touches from
employees to customers. It goes beyond philanthropy or altruism. It is a strategy for profit and growth based on
improving people’s lives.
In India, the government has turned CSR from a voluntary activity to a mandated responsibility for all
companies having a certain threshold of size. Thus, CSR is no longer an act of charity or individual philanthropy
but a responsibility of corporates.
How EVNNPT can profit from organised CSR work at project sites
Organised and focused CSR activities will contribute significantly in EVNNPT’s effort to gain goodwill of not
only those who are directly affected by its projects, but also those who might be affected by them at a future
date. A robust CSR programme that meets the aspirations of the affected communities will lead to the
following:
1. Community’s licence to operate: A robust CSR programme will not only provide EVNNPT with the
people’s licence to operate, but also to retain the licence, creating and increasing the people’s trust in
EVNNPT
2. Enhanced corporate reputation: The benefits of goodwill, positive image and branding would
accrue to EVNNPT once it operates effective CSR programmes. This will allow EVNNPT to position
itself as a responsible corporate citizen
3. Reduced Resistance: Various stakeholders will see EVNNPT as a development partner fostering
growth at the national level and adopting socially beneficial initiatives at the local level rather than as
an entity that is only interested in acquiring land from those who are unwilling to part with it
4. Easier access to capital: International funding agencies prefer to work with companies that behave
responsibly on safeguard by fulfilling ethical, social, and environmental responsibilities and by
responding positively to the needs of ethnic minorities and indigenous peoples
It is very important for companies in the infrastructure sector, especially those which have to deal with people
whose livelihood is land dependent, to undertake and / or promote socially beneficial activities and projects.
These activities and projects would be above and beyond the compensation, resettlement and rehabilitation
relating to land acquisition.
Thus EVNNPT must have a comprehensive corporate social responsibility (CSR) policy which is based on the
needs of the communities which are being impacted (directly or indirectly) by its projects. The overall purpose
of the CSR activities would be to help improve, in a sustainable manner, the quality of life of the communities
touched by EVNNPT’s projects, both at the construction stage and at operation & maintenance stage. The
overall objective would be to win trust and gain goodwill for EVNNPT - and help build an independent brand
identity for it. All of this would go a long way to help EVNNPT further its business goals. If enough goodwill is
generated over time, project delays due to the resistance of local people may become history.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 367
This CSR policy must be planned and implemented by a CSR function either as a part of the proposed PR
Department or as a separate department working in conjunction with the PR Department.
Approach
Since, there is still strong reservations within the EVNNPT leadership about the advisability of having a formal
CSR function within the organisation, we recommend the following strategic approach to the creation of such a
function.
Build Vision and Support for CSR
The key objective here is influencing internal stakeholders of EVNNPT with the goal of creating a broad base of
support for CSR throughout the organisation. Key action steps might include:
1. Developing a clear CSR mandate for EVNNPT
2. Fostering organisational interest for CSR at EVNNPT
3. Building board, CEO and executive-level support and involvement
Once there is broad agreement on the advisability of setting up a separate and dedicated CSR function,
the following process of setting it may be followed:
Examine current scenario on CSR
The key objective here is assessing the whole picture on CSR or on initiatives that might be described as CSR
activities. Illustrative assessment actions might include:
1. Determining the Vietnam government’s position on CSR or activities that can be viewed as CSR;
2. Assessing CSR definition currently being used by EVNNPT;
3. Assessing the community and environment work being undertaken by EVNNPT;
4. Evaluating EVNNPT’s existing CSR policies, standards, values statements or business principles -such
as they are;
5. Understanding current commitments of EVNNPT on CSR or on activities that might be described as
CSR;
6. Identifying departments, functional areas, or cross functional initiatives involving CSR at EVNNPT and
its subsidiaries;
7. Evaluating relationships with various stakeholders in the context of CSR;
8. Examining evaluation, measurement and reporting processes related to CSR activities.
Build Vision and Support for CSR
Examine current scenario on CSR
Design a CSR Structure
Operationalising the new CSR function
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 368
Design a CSR Structure
The key objective here is engaging in a process to develop the most appropriate CSR structure for EVNNPT
considering its industry sector, mission, culture, business structure, geographic locations, risk areas and level of
commitment. Various steps for designing a CSR structure include:
1. Understanding the key drivers;
2. Identifying key community, environment, and related issues which are of relevance to the various
stakeholders of EVNNPT and its subsidiaries;
3. Identifying and evaluating all stakeholders of EVNNPT and its subsidiaries;
4. Identifying functions that support CSR efforts at EVNNPT;
5. Analysing company systems, culture & any impending changes;
6. Evaluating structural options inter-team, inter-department at EVNNPT and its subsidiaries;
7. Creating a structure for cross-functional interaction in EVNNPT and between EVNNPT and
subsidiaries. Such a structure would comprise a separate department within EVNNPT, or a separate
unit within the proposed PR Department of EVNNPT, and smaller units in the subsidiaries;
8. Developing a detailed staffing plan for the new CSR team; and
9. Developing a process for budget preparation and resource allocation.
Effectively, the above-mentioned steps would amount to the following:
1. Defining the CSR function’s objectives and scope;
2. Identifying deliverables and resource needs;
3. Determining team roles and responsibilities; and
4. Setting up the CSR department in EVNNPT and CSR units in the subsidiaries.
Operationalising the new CSR function
Once the CSR team is in place, the next step would be to operationalise the CSR function. This would comprise
the following basic steps:
1. Database preparation of key stakeholders relating to CSR;
2. Preparation of an annual plan for CSR - at the levels of EVNNPT as a whole and each subsidiary;
3. Setting up processes for implementation (directly by the team and / or indirectly through partners like
NGOs and self-help groups);
4. Setting-up processes for systematic use of employee resources (volunteers) and unions;
5. Setting-up processes for monitoring and measurement of impact; and
6. Setting-up processes for publicising the CSR work within the stakeholder groups, including the affected
people, public authorities and the media.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 369
CSR Activities
The CSR activities that EVNNPT could look at the level of the community at the project sites can broadly be
categorised under the following buckets:
1. Economic value creation in communities;
2. Educational initiatives;
3. Health & family welfare;
4. Environmental sustainability initiatives;
5. Protection of national heritage;
6. Employee engagement in value creation;
7. Empowering women from economically disadvantaged sections; and
8. Improving the lives of people from the ethnic minorities and indigenous peoples.
Measurement of CSR Programme
To measure the efficacy and success of the CSR programmes, the new CSR department could undertake the
following:
1. Monitor the positive outcomes of the initiative - in terms of making a positive impact on the
community;
2. Monitor the coverage received in the media and social media;
3. Perceptions Audit: Qualitative analysis of the perceptions of stakeholder groups about EVNNPT’s CSR
work.
Indicative timeline
Month 1-2: Build Vision and
Support for CSR
Month 3-5: Examine current scenario on CSR
Month 6-9: Design a CSR
Structure
Month 10-15: Operationalising
the new CSR function
Month 16-18: Measure
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 370
Recommendation#6: Impart training to EVNNPT spokespersons on media handling skills
Summary
Title of the workshop: Training to EVNNPT spokespersons on media handling skills
Date & Time: 14 October 2014, 2.00 pm - 5.00 pm
Venue: Meeting Room, Fifth Floor, EVNNPT, 18 Tran Nguyen Han, Hanoi
No. of participants: 17
Training material: Refer Appendix 11 -
List of participants
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 371
Tips for dealing with the media
We believe the press is becoming more intrusive in the rush to get stories. Often, businesses and organizations
get caught in crossfire of sloppy reporting, misleading information and inaccuracies.
The following common-sense “rules of engagement” for dealing with the media have been tested and proven in
our years of experience with the press:
1. Don’t lie. Ever.
2. You don’t have to answer every question you’re asked.
3. Think. Think before you answer anything. A corollary: Have a clear goal in mind before you answer
anything
4. Don’t lose your cool. If you do, the media won’t forget- it will show a video clip or photo of how you lost
your cool over and over and over.
5. If you’re wrong, admit it. If you’re happy, be it. If you’re hurt, show it.
6. Answer only the question that you want to answer it.
7. Assume everything is “on the record”.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 372
8. Stick to your story. Don’t improvise.
9. Don’t speak too much. Be concise and to-the-point. Often, less is more.
10. Always think of the future. Don’t burn your bridges with reporters.
Ten Commandments of media interaction
Cardinal rule: Be truthful
1. Be relevant
a. Talk from the point of view of your audience’s interest
b. Know your audience
c. Don’t use jargon
2. Be personal
a. Speak in personal terms, whenever possible, to enhance credibility
b. Use ‘I’, not the corporate “we”
c. Take personal responsibility
3. Be careful
a. If you do not want some statement quoted, do not make it
b. There is no such thing as “off the record” or “not for attribution”
c. “Off the cuff” statements run the danger of being headlines the next day
d. Statements made for “background” or briefing purposes are always subject to being quoted
e. If you happen to make an inaccurate statement, correct it immediately
4. Be organized
a. State the most important fact at the beginning
b. People are often too busy to read an article in entirety
c. Always keep your key message in mind
d. Use your voice and gestures for added emphasis
e. Back up your points with statistics and personal anecdotes
5. Be calm
a. Do not argue with a reported or lose your cool. You’ll never win the argument
b. Audiences and reporters will sense hostility
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 373
c. Be friendly, but not too talkative
d. Reporters deliberatively argue to elicit a response
6. Be positive
a. If a question contains negative language or words you don’t like, do not repeat the reporter’s
negative words
b. You run the risk of having the reporter’s negative language attributed to you. Instead, state the
answer in a positive manner
7. Be direct
a. If a reporter asks a direct question, he is generally entitled to a direct answer
b. Answer the questions, but then bridge to a key message
8. Be confident
a. Don’t speculate
b. Answer the reporter, but then bridge to a key message
9. Be open
a. If you cannot answer a question, never say “no comment”
b. Always give a valid reason for not being able to answer. For example, a legal case is “pending”
10. Be attentive
a. Listen to the question
b. Be sensitive to the reporter’s intent
c. If you miss the point of a question, you appear evasive
Body Language Do’s
1. First steps
a. Handshake
b. Smile
2. Getting acquainted
a. Eye contact
b. Listening head
c. Open gestures and Easy body movements
d. Leaning forward
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 374
3. Getting a word in edgeways
a. Speaking a little louder
b. Triple head nods
c. Verbal signal like ‘yes’, ‘well’, ‘but’
4. Be calm
a. Do not argue with a reported or lose your cool. You’ll never win the argument
b. Audiences and reporters will sense hostility
c. Be friendly, but not too talkative
d. Reporters deliberatively argue to elicit a response
Body Language Don’ts
1. Stare at the speaker - different from maintaining eye contact
2. Fold your arms - indicates withdrawal and a desire for self-protection
3. Tap or twitch your feet
4. Work while the speaker is talking to you
5. Pack up papers and folders before the meeting is over
6. Look at the watch
7. Lean back in your chair with your hands behind your head
8. Drum your fingers and bite your nails
9. Cover your mouth while you talk
10. Have your hands in the pocket
11. Overfriendliness
Outcome and feedback
The workshop was aimed at helping develop skillsets to clearly communicate with external audiences. Based on
an initial assessment of the workshop, it can be concluded that the group was able to understand and value the
training.
As part of the training, a mock interview was conducted as a training exercise to resemble a real media
interview as closely as possible. This was aimed at preparing the candidate in better engagement with media
and better presentation of their point of view.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 375
Mock interview - Transcript
1. Question#1: The most difficult step in transmission projects is site clearance. Some papers report that
the difficulty caused by affected people. Have you ever wondered that one of the reasons of anti-acts of
affected people is attitudes, behaviour and communication capacity of the power sector’s staff?
a. Answer: EVNNPT's transmission line projects are mainly served for national socio-economic
development and people's life purposes so there is no case of lack of support from people in the
site clearance. If there are any cases of lack of support, it may be caused by unclear explanation
from local authority. The resettlement is done by the local authority so EVNNPT have been
coordinating with the local authority to persuade the cases of lack of support.
2. Question#2: What is EVNNPT's role in communication with the people in the site clearance?
a. Answer: Communicate purpose, meaning of the projects; Introduce technical parameters to
ensure that people feel secure to support for EVNNPT's projects.
3. Question#3: As unofficial sources, there are some households facing with a lot of difficulties after the
resettlement and difficulty to have a stable daily life. What EVNNPT has to do in those cases?
a. Answer: EVNNPT is currently focusing to ensure progress of projects. Regarding to those cases
of households after the resettlement, we will actively coordinate with the local authority to
quickly ensure people's stale life because one of EVNNPT's project purposes is to serve for the
country and people.
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 376
Recommendation#7: Conduct a workshop on the fundamentals of effective public relations
Summary
Title of the workshop: Fundamentals of effective public relations
Date & Time: 13 October 2014, 7.30 am - 11.30 am 13 October 2014, 2.00 pm - 5.00 pm
Venue: Meeting Room, Fifth Floor, EVNNPT, 18 Tran Nguyen Han, Hanoi
No. of participants: 20
Training material: Refer Appendix 12 -
List of participants
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 377
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 378
Exercise#1: EVNNPT's real press release (Task: To edit and comment)
Insert Header Field
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 379
Exercise#2: To prepare a communication plan for an EVNNPT project
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 380
Appendix 1 - Overview of Vietnam power sector
Industry structure
The Vietnam Electricity (EVN), a state owned enterprise, reporting to Ministry of Industry and Trade, is the
largest buyer of electricity from the power plants and has a monopoly on transmission and distribution of
electricity. The EVN was has been a vertically integrated utility till the recent past. Although now separate
entities have been formed for generation (three entities), transmission (NPT), trading (EPTC) and distribution
(five entities), all these entities are either wholly-owned subsidiaries of EVN or EVN has a controlling stake in
these entities.
The power sector is under the jurisdiction and management of the Ministry of Industry and Trade (MoIT). The
Electricity Regulatory Authority of Vietnam (ERAV), under MoIT, is responsible for issuing license for
participants in electricity market, regulatory body in competitive power market, and regulating electricity tariff.
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 381
Government of Vietnam
(GoV)
Ministry of Industry and Trade
(MoIT)
Directorate General of Energy
(DGE)
Vietnam Electricity
(EVN)
National Load Despatch Centre
(NLDC)
Northern Regional Load Despatch
Centre
Central Regional Load Despatch
Centre
Southern Regional Load Despatch
Centre
Electric Power Trading Company
(EPTC)
National Power Transmission Corporation
(NPT)
Power Transmission Company No. 1
(PTC1), Hanoi
Northern Power Projects
Management Board
(NPMB), Hanoi
Power Transmission Company No. 2
(PTC2), Danang
Central Power Projects
Management Board
(CPMB), Danang
Power Transmission Company No. 3
(PTC3), Nha Trang
Southern Power Projects
Management Board
(SPMB), HCMC
Power Transmission Company No. 4
(PTC4), HCMC
Multiple Subordinated Local
Companies (applicable to all
four PTCs)
Power Companies (Discoms)
Northern Power Company, Hanoi
Central Power Company, Danang
Southern Power Company, HCMC
Hanoi Power Company, Hanoi
Ho Chi Minh City Power Company,
HCMC
Power Generating Companies
Power Generation Corporation 01
Power Generation Corporation 02
Power Generation Corporation 03
Independent Power Producers
BOT Power Projects
Electricity Regulatory Authority of Vietnam
(ERAV)
Ministry of Planning and Investment
(MPI)
Ministry of Finance
(MoF)
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 382
Demand-Supply scenario
Demand
Power consumption in Vietnam has increased nearly fivefold since 2000 as Vietnam underwent a period of
strong economic growth. Since opening up to foreign trade and investment, Vietnam has been growing faster
than most other Asian countries, reached CAGR of 13.5% in the period of 2000 - 2012. Industrial players and
households are major components in power consumption, representing 90% of total demand. It is forecasted
that domestic demand for electricity will double in the next 10 years (CAGR expected to be about 9.0%).
Source: Source: IEA, BMI, PwC Analysis
Supply
22,403
102,457
242,077
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
-
50,000
100,000
150,000
200,000
250,000
300,000
20
00
20
02
20
04
20
06
20
08
20
10
20
12
20
14
20
16
20
18
20
20
20
22
Electricity Net Consumption
Net Consumption (GWh) YOY Growth (%)
49%
14%
10%
6%
8%
6% 7%
Installed capacity by ownership in 2012
EVN
JSC with EVN'sstake
Petro Vietnam
Vinacomin
Foreign Developers
Other LocalDevelopers
Imported
52%
28%
19% 1%
Installed capacity by fuel source in 2012
Hydropower
Gas turbine
Coal fired
Oil fired
Others
79 93
100 112
122 135
148 161
90 100
109 119
130 144
158 173
-
20
40
60
80
100
120
140
160
180
200
2010 2011 2012e 2013f 2014f 2015f 2016f 2017f
Th
ou
sa
nd
s
Demand and Supply of Vietnam Electricity Industry (Million kWh)
Supply of electricity - BMI
Estimated demand of electricity
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 383
Demand-Supply imbalance
Vietnam has a history of power shortage and it is expected to continue to be an issue until 2020. Further,
hydropower, including imports from China and Laos, which makes up the bulk of Vietnam’s power generating
capacity, is susceptible to shortages during the dry season. Other factors that have resulted in a shortage of
power in Vietnam are the lack of funding, increasing cost of fuel and other inputs, difficulties in land
acquisition, investors' lack of capability and prolonged approval processes. In order to address this need, power
generation capacity will have to increase and diversify to other sources, both renewable and non-renewable.
Transmission & Distribution network
In 2012, the rural electrification rate in Vietnam was 96.8% and is expected to reach nearly 100% by 2020. The
transmission system has seen a steady growth both in terms of line length (km) and transformation capacity.
Growth in transmission system 2008 2009 2010 2011 2012
500 kV transmission lines (km) 3,455 3,758 4,243 4,328 4,847
220 kV transmission lines (km) 7,987 9,400 9,870 10,645 10,858
500 kV transformation capacity (MVA) 7,050 8,400 11,550 13,950 15,150
220 kV transformation capacity (MVA) 15,477 17,977 21,039 24,476 25,351 Ref: EVN EVNNPT presentation in May 2013
In addition to the transmission system, Vietnam’s power distribution system of about 115,659 km is comprised
of various 6kV, 10kV, 15kV, 22kV and 35kV lines with a total capacity of 3,662 MVA and 109,199 km of 220V
lines with a total capacity of 32,061 MVA. The T&D losses have also been consistently reducing from approx.
21% in 1995 to around 10% in 2011.
6,2
33
7,8
71
8,8
84
10
,010
10
,62
6
11,
57
6
12
,27
0
13
,512
15
,76
3
17
,52
1
20
,54
2
23
,52
7
26
,47
5
-
5,000
10,000
15,000
20,000
25,000
30,000
20
00
20
01
20
02
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Growth in Installed Generation Capacity (MW)
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 384
Source: EVN, PwC Analysis
Retail tariffs
Wholesale prices at which EVN sells electricity to distribution companies are determined by production costs
and retail prices. Therefore, distribution companies that have high retail prices will buy electricity at higher
prices than those with low retail prices. Retail prices at which distribution companies sell electricity to
consumers are set by the government for the whole country. Although retail prices have been adjusted almost
each year (at a CAGR of 7.7% p.a. during 2005-2014), currently retail prices still do not cover actual costs of
electricity. The flow chart below shows the broad process of approval of electricity price.
Source: EVN
3,539 3,657 4,243
5,012 5,272 6,010 6,258
6,863 7,445 7,401
7,985
9,597 10,060
15%
14% 14% 14%
13% 13%
12%
11% 11%
10% 10% 10% 10%
0%
2%
4%
6%
8%
10%
12%
14%
16%
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Electric Power Transmission & Distribution Loses (Million kWh)
Electric Power T&D Losses Electric Power T&D Losses (% of Output)
787 815 860 870 948
1058
1242
1361
1499 1533
0
200
400
600
800
1000
1200
1400
1600
1800
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14f
Average retail electricity tariff (VND / kWh)
EVN MOIT
MoF
Validate price
Prime Minister
Approve new price
End-users
Proposal for price change
Approve if retail price change <=10%
Retail price change >10%
Although price change decisions
shall be made by MOIT, price
change less than 10% is usually
approved if there is no special
judgment from the Government
CAGR = 7.7%
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 385
Power sector reforms & development of market structure
The Electricity Law notified in 2004 (effective from July 2005) is the first step taken by the Government of
Vietnam towards the power sector reforms as it set the objective to make the power sector more competitive
and increase investors’ confidence. In 2006, the Government of Vietnam has formally initiated the reforms by
bringing out a roadmap for establishing a competitive power market and restructuring the erstwhile state-
owned vertically integrated utility, Vietnam Electricity (EVN).
The power sector reform road map spans across a period of about 20 years and is planned to be implemented in
three successive market phases as indicated below:
Overview of EVNNPT's performance and plan
The following table summarises EVNNPT's operational and financial performance in the last two years and plan
for next two years:
Parameter Unit 2012
(Actual)
2013
(Estimate)
2014
(Proposed)
2015
(Proposed)
Transmission output Billion kWh 103.58 112.64 123.35 135.68
Losses % 2.33 2.75 2.18 2.00
Employees Nos. 7,202 7,085 7,461 7,848
Capex Million USD 375 629 736 903
Charter capital Million USD 342 1,057 1,057 1,057
RoE (proposed/approved) % 0.29/0.29 0.59/0 4.00/1.00 6.00/NA
Revenue
(proposed/approved)
Million USD 410/410 476/NA Op-1: 644/500
Op-2: 682/490
Op-1: 779/NA
Op-2: 836/NA
Price
(proposed/approved)
US
cents/kWh
0.40/0.40 0.42/0.40 Op-1: 0.52/0.41
Op-2: 0.55/0.41
Op-1: 0.57 /NA
Op-2: 0.62/NA
Self Financing Ratio (SFR) % - 9.82 Op-1: 18.04
Op-2: 23.07
Op-1: 23.60
Op-2: 30.02
1: Competitive Generation Market
(Up to 2014)
• Qualified electricity generation companies are able to sell electricity to the wholesale buyer (EPTC - Electricity Power Trade Company) through bilateral contracts and the spot market
• EPTC then sells electricity to EVN and EVN’s subsidiaries through wholesale contracts
• EPTC, NPTC (National Power Transmission Company) and NLDC (National Load Dispatch Centre) are still EVN’s subsidiaries
2.1: Pilot Competitive Wholesale Market
(2015-2016)
• Allowing the establishment of new wholesale buyers
• NPTC and NLDC become independent units in the Electricity market
• Power Generation Corporations (GENCO 1,2,3), EVN’s power plants (except large power plants which relate to national security) transform into state-owned IPPs
• Power Corporations and Power Companies (distribution units) are also retail sellers but must separate those two businesses
• Power corporations, Power companies, qualified retail sellers and large consumption clients can buy electricity from power plants and wholesale sellers (pilot wholesale market)
2.2: Competitive Wholesale Market
(2017-2022)
• Subsidiaries of Power Corporations (power companies) become independent units. They must separate their distribution business from retailing business
3.1: Pilot Competitive Retail Market (2022-
2024)
• Allowing the establishment of new retail sellers
• Retail sellers buy electricity from power generation units, wholesale sellers through bilateral contracts and spot market, then sell electricity to customers
• Retail departments in some power companies become independent retail sellers
• Some consumption clients are selected to participate in pilot competitive retail market
• Customers will be able to buy electricity from power generation units, wholesale sellers or retail sellers of their own free will through bilateral contracts or spot market
3.2: Competitive Retail Market (2024
onward)
• Retail departments in power companies must become independent retail sellers
Overview of Vietnam power sector
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 386
Parameter Unit 2012
(Actual)
2013
(Estimate)
2014
(Proposed)
2015
(Proposed)
Debt Service Coverage
Ratio (DSCR)
Times - 1.47 Op-1: 1.90
Op-2: 2.08
Opt-1: 2.23
Op-2: 2.50
Forex variation (allocated) Million USD 35 32 Op-1: 32
Op-2: 32
Op-1: 32
Op-2: 32
Revaluation depreciation
(allocated)
Million USD 732 - Op-1: 0
Op-2: 38
Op-1: 0
Op-2: 57
Op-1 (Option 1): Additional depreciation cost (generated from revaluation of assets) is included
Op-2 (Option 2): Additional depreciation cost (generated from revaluation of assets) is NOT included
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 387
Appendix 2 - Organisation structure of EVNNPT and its subsidiaries
Organisation structure - EVNNPT Head Office
Management Board
President & CEO
Vice President (Construction &
Investment)
Vice President (Technical)
Vice President (Economics & Finance)
General Department Internal Control
Department
General Affairs
(Administration)
Department
Procurement
Department
Information
Technology (IT)
Department
Corporate Planning
Department
Construction
Management
Department
International
Cooperation
Department
Organization and
Human Resources
Department
Technical Department Inspection Department
Finance & Accounting
Department Safety Department Legal Department
Investment
Management
Department
Materials Department
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 388
The organization structure depicted above and the designation wise staffing details is based on the discussions
held with various departments of EVNNPT:
Sr. No.
Department Director Deputy Directors
Experts Total
1. Construction Management Department 1 3 9 13
2. Corporate Planning Department 1 2 10 13
3. Finance & Accounting Department 1* 2 16 19
4. Administration Department 1 2 27 30
5. Information Technology Department 1 2 8 11
6. Inspection Department 1 1 6 8
7. Internal Control Department 1 1 1 3
8. International Cooperation Department 1 1 7 9
9. Investment Management Department 1 3 11 15
10. Legal Department 1 1 2 4
11. Materials Department 1 2 4 7
12. Organisation, Personnel & Labour Department 1 2 8 11
13. Procurement Department 1 3 7 11
14. Safety Department 1 1 2 4
15. Technical Department 1 3 20 24
TOTAL 15 29 138 182 * Chief Accountant
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 389
Organisation structure - NPMB
The mapping of departments with director and deputy directors within NPMB is shown below:
The reporting hierarchy within NPMB is shown below:
In terms of staffing, NPMB has one Director, three Deputy Directors, 130 Experts and 20 other staff. The
information on department-wise staffing is yet to be received from NPMB.
Director (NPMB)
Deputy Director#1
Materials Department
Deputy Director#2
Technical Department
Deputy Director#3
Resettlement Department
Direct reporting to Director (NPPMB)
Finance & Accounting Department
Planning Department
Procurement Department
Evaluation Department
Administration Department
Vice President (Construction),
EVNNPT
Director (NPPMB)
Deputy Director#1
Experts
Drivers & Support Staff
Deputy Director#2
Experts
Drivers & Support Staff
Deputy Director#3
Experts
Drivers & Support Staff
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 390
Organisation structure - PTC1
The functional departments, transmission companies, units directly under control of PTC1 and other business units (like workshop) within PTC1 are shown below:
Director Board
(PTC1)
Functional Departments
Administration Department
Planning Department
Organisation and Labour
Department
Technical Department
Safety Department
Finance & Accounting Department
Inspection & Legal Department
Materials Department
Construction Investment Department
Load Shedding Department
Information Department
Workshop Team
Testing Workshop
Repair and Maintenance
Workshop
Logistics and Mechanics Team
Transmission Companies
Ha Noi PTC
Hai Phong PTC
Quang Ninh PTC
Thai Nguyen PTC
Hoa Binh PTC
Tay Bac PTC
Ninh Binh PTC
Thanh Hoa PTC
Nghe An PTC
Ha Tinh PTC
Units under direct control
220kV Ha Dong Sub-station
220kV Chem Sub-station
220kV Mai Dong Sub-station
500kV Hoa Binh Sub-station
500kV Thuong Tin Sub-station
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 391
Director of PTC1 monitors four departments directly- Planning, F&A, Organisation & Labour and Construction
Investment. All other departments of PTC1 report directly to respective deputy director in-charge. The mapping
of departments/units with director and deputy directors within PTC1 is shown below:
In terms of staffing, PTC1 has one Director, three Deputy Directors, 2466 other staff (including Experts).
Director (PTC1)
Deputy Director#1
- Sub-stations
- Testing Workshop
- Repair and Maintenance Workshop
- Load Shedding Department
- Information Technology Department
-Technical Department (Sub-stations)
- Grid Development of Hanoi Area
Deputy Director#2
- Transmission lines
- Technical Department (Transmission lines)
- Safety Department
- Material Department
- Logitics and Mechanics Department
- Managing Flood Prevention Actions
Deputy Director#3
- Administration Department
- Inspection and Legal Department
- House constructions in all projects
Organisation structure of EVNNPT and its subsidiaries
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 392
Organisation structure - other PMBs and PTCs
PMBs
CPMB
Description Number Remarks
Total departments 8
Total staff 136
Director 1
Deputy Director 4
Experts 111 9 master degree, 95 bachelor degree, rest others
Drivers and support staff 20
Note:
One additional deputy director compared to NPMB/SPMB.
Average value of the projects under construction (ongoing) in CPMB area: 4 trillion VND
As per the current year mandate, they must start construction of 9 projects and must commission 9
projects
SPMB
Description Number Remarks
Total departments 8
Total staff 167 95% staff are experts and above having bachelor degree
Director 1
Deputy Director 3
Experts 143
Drivers and support staff 20
Note:
In a department: Max staff - 30; Min staff - 10
PTCs
PTC2, PTC3 and PTC4 have two deputy directors whereas only PTC1 has three deputy directors because
PTC1 manages very large geographic area and larger system
Number of departments (11) are same in all four PTCs
Total staff of PTC4 = 2044 (11 departments)
Work plans of TA Experts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 393
Appendix 3 - Work plans of TA Experts
Investment planning
Month (M) Activities/ tasks Time of Expert (person months)
M1-M2 Project inception and high level study of current practices
Project kick-off and inception visit
Agree on work plan and timelines
High level study of current processes, procedures, tools and
methodologies, roles of departments involved in investment
planning
Submission of Inception Report
0.90
M3-M4 Detailed study of current practices and high-level recommendations
Workshop, stakeholder consultation and agreement on key findings
Detailed study of existing tools, mechanisms, procedures and
strategies, roles and responsibilities
Collection/receipt of pending baseline data by means of detailed
interactions with various stakeholders
Comprehensive review of current practices and identification of gaps
Study of select global practices
Make high level recommendations
Submission of Mid Term Report
1.30
M5-M6 Final recommendations
Recommendations and solutions to improve existing tools,
mechanisms, procedures and strategies
Workshop, stakeholder consultation and agreement on key findings
Identify, review and propose strategies and solutions to improve
existing practices based on current review, select global practices
and stakeholder inputs on high level recommendations
Preparation of implementation plan
Submission of Draft Final Report
1.30
M7-M8 Implementation support
Workshop and stakeholder consultation on issues in implementation
Training and handholding
Receipt of comments from all stakeholders
Submission of Final Report
1.50
Total 5.00
Work plans of TA Experts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 394
Project management
Month (M) Activities/ tasks Time of expert (person months)
M1-M2 Project inception and high level study of current practices
Project kick-off and inception visit
Agree on work plan and timelines
High level study of current processes, procedures, tools and
methodologies, roles of departments involved in project management
Submission of Inception Report
0.90
M3-M4 Detailed study of current practices and high-level recommendations
Workshop, stakeholder consultation and agreement on key findings
Detailed study of existing tools, mechanisms, procedures and
strategies, roles and responsibilities
Collection/receipt of pending baseline data by means of detailed
interactions with various stakeholders
Comprehensive review of current practices and identification of gaps
Study of select global practices
Make high level recommendations
Submission of Mid Term Report
1.20
M5-M6 Final recommendations
Recommendations and solutions to improve existing tools,
mechanisms, procedures and strategies
Workshop, stakeholder consultation and agreement on key findings
Identify, review and propose strategies and solutions to improve
existing practices based on current review, select global practices and
stakeholder inputs on high level recommendations
Preparation of implementation plan
Submission of Draft Final Report
1.40
M7-M8 Implementation support
Workshop and stakeholder consultation on issues in implementation
Training and handholding
Receipt of comments from all stakeholders
Submission of Final Report
1.50
Total 5.00
Work plans of TA Experts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 395
Transmission pricing
Month (M) Activities/ tasks Time of expert (person months)
M1-M2 Project inception and high level study of current practices
Project kick-off and inception visit
Agree on work plan and timelines
High level study of current processes, procedures, tools and
methodologies, roles of departments involved in transmission
pricing
Submission of Inception Report
0.90
M3-M4 Detailed study of current practices and high-level recommendations
Workshop, stakeholder consultation and agreement on key findings
Detailed study of existing tools, mechanisms, procedures and
strategies, roles and responsibilities
Collection/receipt of pending baseline data by means of detailed
interactions with various stakeholders
Comprehensive review of current practices and identification of gaps
Study of select global practices
Make high level recommendations
Submission of Mid Term Report
1.10
M5-M6 Final recommendations
Recommendations and solutions to improve existing tools,
mechanisms, procedures and strategies
Workshop, stakeholder consultation and agreement on key findings
Identify, review and propose strategies and solutions to improve
existing practices based on current review, select global practices
and stakeholder inputs on high level recommendations
Preparation of implementation plan
Submission of Draft Final Report
1.40
M7-M8 Implementation support
Workshop and stakeholder consultation on issues in implementation
Training and handholding
Receipt of comments from all stakeholders
Submission of Final Report
1.60
Total 5.00
Work plans of TA Experts
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 396
Public relations
Month (M) Activities/ tasks Time of Expert
(person months)
International National
M1-M2 Project inception and high level study of current
practices
Project kick-off and inception visit
Agree on work plan and timelines
High level study of current processes, procedures, tools and
methodologies, roles of departments involved in public
relations
Submission of Inception Report
0.80 0.90
M3-M4 Detailed study of current practices and high-level
recommendations
Workshop, stakeholder consultation and agreement on key
findings
Detailed study of existing tools, mechanisms, procedures
and strategies, roles and responsibilities
Collection/receipt of pending baseline data by means of
detailed interactions with various stakeholders
Comprehensive review of current practices and
identification of gaps
Study of select global practices
Make high level recommendations
Submission of Mid Term Report
0.90 1.10
M5-M6 Final recommendations
Recommendations and solutions to improve existing tools,
mechanisms, procedures and strategies
Workshop, stakeholder consultation and agreement on key
findings
Identify, review and propose strategies and solutions to
improve existing practices based on current review, select
global practices and stakeholder inputs on high level
recommendations
Preparation of implementation plan
Submission of Draft Final Report
0.80 1.20
M7-M8 Implementation support
Workshop and stakeholder consultation on issues in
implementation
Training and handholding
Receipt of comments from all stakeholders
Submission of Final Report
1.50 1.80
Total 4.00 5.00
Questionnaires for perceptions audit
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 397
Appendix 4 - Questionnaires for perceptions audit
To EVN officials and public officials
1. What is your general perception or opinion about EVNNPT?
2. Do you see EVNNPT as a distinct entity or an extension of EVN or do you see it as a part of EVN?
3. How would you rate EVNNPT in terms of its communication and information flow with different
stakeholder groups, including the Ministry of Industry & Trade?
4. Do you think that the local people are communicated well on various issues? Are you happy with
the level of communication?
5. What do you think of the CSR activities of EVNNPT?
To media
1. What is your general perception or opinion about EVNNPT?
2. Do you see EVNNPT as a distinct entity or an extension of EVN or do you see it as a part of EVN?
3. What is your opinion of the information flow from EVNNPT? Is it regular and adequate? Is it
responsive when you contact EVNNPT? Is it easy to connect with the EVNNPT officials and receive
information?
4. What is your opinion about CSR that EVNNPT undertakes? Does EVNNPT do enough for ordinary
people in project areas (other than ensuring / paying compensation to people whose land is
acquired for the project)?
To affected people
1. Do you see EVNNPT as a distinct entity or an extension of EVN or do you see it as a part of EVN?
2. Are you unhappy about the land loss?
3. How do you compare your present home to the old one?
4. Are you satisfied with the compensation or not?
5. Are you communicated well through loudspeakers, leaflets etc. on various issues? Are you happy
with the level of communication?
6. Has your family been trained or guided about the need to protect transmission lines corridors?
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 398
Appendix 5 - Summary of laws / decisions / decrees / circulars
Relevant to investment planning
Decision No. 1368/QD-EVNNPT dated 18 October 2013
This is the most crucial Decision in the investment planning process. This Decision lays down the delegation of
powers for various activities/ decisions under the investment planning process. This decision is in fact an
amendment of the original Decision No. 496/QD-NPT dated 16 June 2010. A brief reading of the changes
suggests that the new Decision has brought about more centralisation in decision making to the President &
CEO or Management Board. This Decision is important not only from a process efficiency perspective but also
from a governance perspective.
Some of the salient features of the Decision are summarised below:
The authority for investment decision and implementation in EVNNPT is based on the value of the investment
proposed. The investment is categorised into three broad categories (based on its value) which includes:
1. Investment value less than 500 billion VND
2. Investment value from 500 billion VND to 1000 billion VND
3. Investment value from 1000 billion VND to 50% of the total asset value
The powers are judiciously divided for each activity under the investment planning process for each category of
projects.
Scope of work Authority of approval Investment value above 1000 billion VND and up to 50% of the total asset value
Investment value between 500 billion VND and 1000 billion VND
Investment value less than 500 billion VND
Selection of consultant at feasibility study stage
President & CEO President & CEO President & CEO
Approval of feasibility study
Management board President & CEO President & CEO
Selection of consultant at technical design stage
President & CEO President & CEO Projects Management Board / Power Transmission Company
Approval of technical design, estimation
President & CEO President & CEO Projects Management Board/Power Transmission Company
Approval of procurement plan
Management board President & CEO N.A.
Approval of invitation to bid, request for proposal
President & CEO President & CEO Projects Management Board/Power Transmission Company
Approval of DTGT President & CEO President & CEO Projects Management Board/Power Transmission Company
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 399
Scope of work Authority of approval Investment value above 1000 billion VND and up to 50% of the total asset value
Investment value between 500 billion VND and 1000 billion VND
Investment value less than 500 billion VND
Approval of contractor selection result
Management board President & CEO Projects Management Board/Power Transmission Company
Contract signing Projects Management Board
President & CEO Projects Management Board/Power Transmission Company
Selection of supervision consultant
President & CEO President & CEO President & CEO
Approval of working drawings - estimation
Projects Management Board/Power Transmission Company
Projects Management Board/Power Transmission Company
Projects Management Board/Power Transmission Company
Approval of unexpected contents: - Unexpected work items, revision of main technical solution or total investment stated in Decision on approval of project investment
Management board President & CEO President & CEO
Modification of technical design affecting main technical solutions stated in Decision on approval of technical design, or over provision value.
President & CEO President & CEO Projects Management Board/Power Transmission Company
Modification of technical design not affecting main technical design and not over provision value.
Projects Management Board/Power Transmission Company
Projects Management Board/Power Transmission Company
Projects Management Board/Power Transmission Company
Establishment of acceptance board
President & CEO President & CEO President & CEO
Approval of balancing of finished projects
Management board President & CEO President & CEO
Decree No. 38/2013/ND-CP dated 23 April 2013
This Decree is primarily pertaining to the management and utilization of the Official Development Assistance
(ODA) and concessional loans from various donor agencies. This Decree clearly outlines the following
important areas:
1. Basic principles for use of ODA funds
2. Priority areas for use of ODA funds
3. Process to be followed for ODA funding, use and monitoring
4. Roles of various state agencies
The salient features of this Decree is summarised in the table below:
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 400
Area Salient features
Basic principles for use of ODA funds
The ODA funds and concessional loans from donor agencies will be used by the Government in socio-economic development of the country. The ODA funds are managed centrally by the Government. The use of ODA funds shall be towards achieving the highest socio-economic effectiveness with sustainable manner. The guiding principles for use of such funds includes equality and fairness, capital absorption capacity, debt re-payment capability and the safety of public debts, in which prioritize to use concessional loans for programs and projects that can refund directly. The Government of Vietnam is also open to creating a favourable framework for use of ODA funds by private sector. In case there is some discrepancies among state laws and international treaties (with Government of Vietnam), the provisions of such international treaties shall take precedence.
Priority areas for use of ODA funds
The priority areas for use of ODA funds include:
Large transportation infrastructure
Urban infrastructure including power supply infrastructure
Energy Infrastructure with focus on renewable and new energy
Social development infrastructure
Science and high technology
Rural and agriculture development
Institutional strengthening and administrative reforms
Environment protection, climate change, natural resources protection etc.
Promote trade and investments
Support implementation of National target programmes
Other sectors under decision of Prime Minister
Process to be followed for ODA funding, use and monitoring
The ODA funding process from identification to utilization is defined under the Decree as a five step process:
Step 1: Formulation and approval of funding limits by the Prime Minister of
Vietnam
Step 2: Preparation, appraisal, approval of program or project documents by
EVNNPT (who will act as the Project Owners) under the aegis of MoIT
Step 3: Conclusion of International treaties on ODA and concessional loans
by the Prime Minister (in case of strategic projects) with support from
Ministry of Foreign Affairs, MoJ, MoIT and MPI or by MoIT in case of non-
strategic projects.
Step 4: Implementation of programs and projects under the management of
Project Management Unit formed by EVNNPT from internal team/ external
consultants
Step 5: Supervision and evaluation of programs and projects by Line
Agencies, PMU and MPI.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 401
Area Salient features Roles of various state agencies
There are various roles assigned to various key departments and ministries in the country for mobilization, use, supervision and evaluation of use of ODA funds/ concessional loans. The key players include:
State (Vietnam): Unified management of ODA funds, making decisions,
policies, master plans, issuing legal documents and executing macro level
management and utilization of ODA funds.
Ministry of Planning and Investment: Responsible for drafting and
submission of legal documents for management and utilization of ODA funds;
focal point agency for all management responsibilities including problem solving,
collating and providing the funding list to the Prime Minister; coordinating with
MoF for approval of domestic financial regime applicable to ODA funded projects,
planning disbursement and handling demand for adding capital in the annual
plans; managing supervision and evaluation activities and submitting periodic
reports.
Ministry of Finance: Coordinating with MPI and other agencies for
formulating strategies and plans for mobilization and utilization of ODA funds;
guidance on preparation of content involving conditions on using funds, financial
management of programs and projects; inputs to Prime Minister on conclusion of
international treaties; officially representing as the borrower on behalf of the
Government; execution of financial management programs; Specifying the
procedures for fund withdrawal and management of fund withdrawal; guiding on
implementation of policies on taxes and charges; allocating budget from the State
budget and other funding sources for payment of ODA; coordinating with the
State bank of Vietnam in defining and publishing the list of commercial banks
eligible to perform the external payment transactions related to ODA; collating
data on disbursement and full responsibility to arrange counterpart funds.
State Bank of Vietnam: Responsible for coordinating with relevant agencies to
conclude ODA funds under select multilateral institutions; coordinating with MoF
post execution of international treaties and monitor and report fund withdrawal
and payment.
Ministry of Justice: Appraising, negotiating and providing comments on the
draft International treaties; comments on the project/ program and regarding
need of international cooperation; appraising the program and PD on foreign
cooperation in legal sector and providing comments from legal aspects on the
draft resettlement framework policy
Ministry of Foreign Affairs: Representing Vietnam abroad to mobilize the
ODA funds; checking, proposing for negotiation, conclusion of the International
treaties on ODA; conducting external procedures on conclusion and
implementation of International treaties and coordinating with concerned
agencies in elaborating and implementing guidelines and directions for ODA
Office of Government: Assisting the Government and the Prime Minister in
leading, directing and operating the uniform state management on ODA;
providing opinions on contents in the course of preparing the programs and
projects and assisting the Government and the Prime Minister for checking and
urging implementation of this Decree
Ministers/ Ministerial level agencies/ Government Agencies:
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 402
Area Salient features Formulating Outlines of programs and projects and submitting them to
competent agencies; coordinating with the MoF and the SBA to conclude
international treaties; proposing to the Prime Minister for conclusion of specific
International treaties; executing the functions of state management of ODA and
concessional loans and ensuring transparency.
People’s Committee: Coordinating with MPI and other agencies for
formulating strategies and plans for mobilization and utilization of ODA funds;
formulating outline of programs and projects, coordinating with MoF and SBV to
conclude the international treaties; responsibility for directing and organizing
land acquisition, compensation and site clearances; ensuring publicity and
transparency and arrange funds for debt repayment in case of on lending
programs.
Decision No. 1485/QD-EVNNPT dated 11 December 2013
The Decision 1485 of 2013, issued by the President & CEO (NPT) is pertaining to the amendment of some
functions and responsibilities of various departments of EVNNPT. This Decision in addition to various
departments also refers to some amendment in roles and responsibilities of Corporate Planning Department
and International Cooperation Department, both of which have a significant role in the investment planning
process.
The detailed roles and responsibilities of CPD and ICD outlined under the Decision 1485 of 2013 are already
provided of this report.
Decision No. 1208/QD-TTg dated 21 July 2010
The Decision 1208 of 2010 from Prime Minister of Vietnam is the Master Plan for 2011-2020 with a
consideration of 2030. The Master Plan is broadly divided into two parts:
1. Part I: Deals with the vision, mission and targets for the energy sector in 2011-2020 with a macro
view of the vision till 2030; and
2. Part II: Deals with the responsibilities of Ministries and other Government Agencies.
Some of the key objectives/ targets set under the Master Plan are summarised below:
1. Invest in the transmission grid to achieve N-1 reliability standard;
2. Ensure the grid is developed in coherence with standards in neighbouring countries to enable
energy exchange between countries;
3. Promote development of GIS and underground substations where land availability is a constraint;
4. Should be able to handle 194- 210 billion kWh by 2015; 330- 362 billion kWh by 2020; and 695-
834 billion kWh by 2030 which would include 18400 MW of wind and hydro power by 2020 (since
variable energy sources such as wind and hydro require greater investment in transmission system
to build the required redundancy);
5. Invest in higher voltage lines i.e. 500 kV;
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 403
6. Higher use of multi circuit lines; and
7. Enable connectivity with other ASEAN countries and Great Mekong Sub-Region (GMS) countries.
The physical investment targets are summarized in the table in starting of this module.
In terms of responsibilities to various ministries, the following table summarises the responsibilities from an
investment planning perspective:
Ministries Responsibilities
Ministry of Industry and Trade
The key responsibilities of MoIT are:
Strictly monitor the electricity supply-demand, progress of
implementation of electricity source and grid projects in order to decide
and adjust the schedules of projects in the approved master plan or
consider and report to the Prime Minister;
Coordinate and urge investors and contractors to implement projects in
the Master Plan in a timely and efficient fashion
Publicize lists of projects in the approved plans and select investors for
Prime Minister’s approval
Formulate plans for raising capital for electricity development
Study and submit plans on Smart Grids
Complete the legal and infrastructure requirements to develop a
competitive market
Ministry of Planning and Investment
The key responsibilities of MPI are:
Formulate mechanisms and policies to attract foreign investment, ODA
capital and private investment capital; and
Prime responsibility, along with MoIT, to allocate adequate budget funds
for the formulation and publicity of the master plan.
Ministry of Finance The MoF will be responsible for formulating financial mechanisms and capital mechanisms for investment in the development of the electricity sector under the approved master plan.
State Bank of Vietnam The SBV will be responsible coordinating with all concerned ministries and sectors in formulating appropriate mechanisms and policies to enhance the capacity of banks to ensure adequate supply of funds for electricity projects under the approved master plan
Vietnam Electricity (EVN) The key responsibilities of EVN are:
Invest in, and put into operation the assigned electricity transmission
projects according to the approved schedules; and
Assign EVNNPT to invest in 500 kV and 220 kV network.
Provincial level People's Committees
The key responsibilities of Provincial level People’s Committees are:
Arrange land areas in their local land use planning for electricity
transmission grid works approved in this master plan
Assume the prime responsibility for, and closely coordinate with
investors in, ground clearance, compensation, population relocation and
resettlement for grid projects
Decree No. 108/2009/ND-CP dated 27 November 2009
This Decree provides for investment domains, conditions, order, procedures and incentives; and rights and
obligations of parties to build-operate-transfer, build-transfer-operate and build-transfer contracts. This decree
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 404
contains information about the State agencies competent to sign and perform project contracts, investment
domains, capital sources for project implementation, and use of state capital for project implementation.
The decree contains the process for drawing up and announcement of lists of projects (which includes the
approval of project proposals and feasibility study reports) and selection of investors for negotiating project
contracts.
Along with this, the other things highlighted in the decree are:
1. Project contract details;
2. Procedures for granting investment certificates and implementing projects;
3. General regulations on transfer of project works;
4. Finalization and transfer of BOT works;
5. Investment incentives and security for investors and project enterprises; and
6. State management of investment projects in the form of BOT, BTO or BT contract and
Implementation provisions.
Decree No. 24/2011/ND-CP dated 5 April 2011
Amendment of some articles of Decree 108/2009/ND-CP dated 27 November 2009 of the government on
investment under form of Build-operation-transfer, build-transfer-operation or build-transfer contract
(hereafter Decree 24/2011/ND-CP)
Circular No. 01/2014/TT-BKHDT dated 9 January 2014
This Circular provides guidelines for the Government's Decree No. 38/2013/ND-CP according to Clause 1
Article 70 of the Decree No. 38/2013/ND-CP. Decree No. 38/2013/ND-CP which deals with the management
and utilization of the Official Development Assistance (ODA) and concessional loans from various donor
agencies. The circular contains information about the donors of ODA and concessional loans, management and
use of non-project aid, compiling and approving funding lists and Regulations on the Prime Minister’s
competence to approve the funding list.
It gives the process for the preparation, assessment and approval of project documentation. It also lists down
the various conditions for management of project execution, Formulating & approving capital plans of projects
and Project supervision & evaluation. The circular also deals with the programs, projects, and non-project aid
that are established during the transition from the Government's Decree No. 131/2006/ND-CP dated
November 09, 2006 on ODA management to the Government's Decree No. 38/2013/ND-CP dated April 23,
2013.
Decision No. 106/QD-TTg dated 19 January 2012
The decision is regarding the approval of the scheme on orientations for attraction, management and use of
official development assistance and other preferential loans of donors during 2011-2015. The salient features of
the scheme are:
1. The 2011-2015 scheme consists of three parts:
a. Part I: Necessity, objectives and scope of the scheme.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 405
b. Part II: Evaluation of implementation of the contents of the scheme on orientations for
attraction and use of official development assistance during 2006-2010.
c. Part III: Attraction, management and use of ODA and other preferential loans of donors
during 2011-2015.
2. The plan of action for implementation of the 2011 -2015 scheme constitutes part of the scheme.
3. The Part II of the decision contains the evaluation of implementation of the contents of the scheme
which is based on the Results of implementation of the contents of the 2006-2010 ODA scheme
and the problems and constraints in the attraction and use of ODA. The evaluation evaluates the
causes of the problems in the scheme of 2006-2010
4. The Part III then places the context for the Attraction, management and use of ODA and other
preferential loans of donors during 2011-2015. The investment demand in the five-year socio-
economic development plan is estimated and guiding principles for improving the institutional and
legal environment are also outlined.
5. Lastly the action plan is outlined which is given as follows:
Group of solutions
Action Responsible agency
Coordinating agency
Deadline Indicator for monitoring
I. Improving policies and institutions
1. Elaboration and submission to the Prime Minister of a draft new decree to replace Decree No. 131/2006/ND-CP on ODA management and use
Ministry of Planning and Investment
Ministries of Finance, Foreign Affairs, and Justice. State Bank, Government Office and donors
Second quarter of 2012
A decree issued
2. Issuance according to competence of documents and circulars guiding the new decree replacing Decree No. 131/2006/ND-CP on ODA management and use
Ministries of Planning and Investment and Finance
Related agencies and donors
Second quarter of 2012
Guiding Documents and circulars issued
3. Based on the new decree replacing Decree No. 131/2006/ND-CP and circulars guiding this Decree, related agencies shall improve administrative procedures
Ministries of Planning and Investment, and Finance
Related agencies
Third quarter of 2012
Current administrative procedures reduced by 30%
4. Study and proposal to the Prime Minister for decision of the issuance of guidelines on
Ministry of Planning and Investment
Related agencies
Second quarter of 2012
Guidelines issued
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 406
Group of solutions
Action Responsible agency
Coordinating agency
Deadline Indicator for monitoring
allocation, management, implementation and supervision of disbursement of domestic capital allocated from the state budget for programs and projects funded with ODA or preferential loans, including priority policies for each. sector, field or difficulty-hit locality
II. Improving organization and management
1. Improvement of organizational structures of focal agencies at all levels in-charge of management and use of ODA and preferential loans
Ministry of Planning and Investment
Related agencies
Fourth quarter of 2012
Organization of these focal agencies improved
2. Improvement of effectiveness and efficiency of operation of the Government's ODA working party by upgrading this working party into a national steering committee for ODA headed by a government leader
Ministry of Planning and Investment And Government Office
Government's ODA working party
Second quarter of 2012
National Steering committee for ODA Established and operating
III. Enhancing partnership and improving aid effectiveness
I. Raising of quality of dialogs between the Government and donors by renovating agendas and contents of forums for development policy dialogs at national and sectoral levels, associating aid effectiveness with development effectiveness
Ministry of Planning and Investment And ministries and sectors
Related agencies and donors
2012-2015 Quality of Dialogs between the Government and donors raised
2. Enhancement of the role and raising of quality of operation of the Aid Effectiveness Forum by implementing the
Ministry of Planning and Investment
AEF Executive Committee, related Vietnamese agencies and donors
2012-2015 Aid quality and effectiveness improved, associating aid effectiveness with development
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 407
Group of solutions
Action Responsible agency
Coordinating agency
Deadline Indicator for monitoring
Busan Declaration in Vietnam and carrying out activities to improve aid effectiveness
effectiveness (plan on implementation of the Busan Declaration in Vietnam elaborated and approved; a new aid architecture with participation of ministries, sectors and localities and groups of partnerships in sectors and fields set up)
IV. Building capacity for management and use of ODA and preferential loans
1. Elaboration and implementation of medium-term plans on building capacity for management and use of ODA and preferential loans toward professionalism and sustainability
Ministry of Planning and Investment
Related agencies and donors
-Second and third quarters of 2012
Plans promulgated
2. Provision of basic training in policies, institutions, processes. procedures and operations of management and use of ODA and preferential loans for project managers at all levels and donors' officers
Ministry of Planning and Investment
Related agencies and donors
2012-2015 Officers directly managing the implementation of ODA and preferential loans and donors' officers provided with professional knowledge and skills
V. Improving tie implementation of programs and projects, speeding up disbursement
1. Periodical review of program and project preparation and implementation, proposal of solutions to speed up the signing and increasing disbursement rate
Ministry of Planning and Investment, other Ministries, sectors and localities
Agencies in-charge of state management of ODA and Preferential loans, project managers and donors
2012-2015 ODA and preferential loans signed and disbursement rate increasing year on year
2. Harmonization of processes and procedure between the Vietnamese Government and donors
Agencies in-charge of state management of ODA and preferential loans and managing agencies
Related agencies and donor
2012-2015 Differences in processes and procedures between the Vietnamese Government and donor narrowed a number of action to be taken in advance
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 408
Group of solutions
Action Responsible agency
Coordinating agency
Deadline Indicator for monitoring institutionalized; procedures for supplementing and amending international agreement on ODA and preferential loans in the course of implementation of program and project simplified
VI. Enhancing the monitoring, supervision and assessment
1. Enhancement of monitoring, supervision and evaluation
Ministry of Planning and Investment, General Statistics Office of Vietnam
Ministries, sectors, localities and donors
2012-2015 System of management information and data on ODA and preferential loans improved: national statistics on signed and disbursed ODA loans formed
2. Building of personnel capacity for monitoring, supervision and evaluation of management and use of ODA and preferential loans
Ministries of Planning and Investment, and Finance, and ministries, sectors and localities
Related agencies and donors
2012-2015 Training courses in institutions and skills of monitoring, supervision and evaluation organized
3. Elaboration and application of penalties to assure compliance with regulations on monitoring, supervision and evaluation of management and use of ODA and preferential loans
Ministry of Planning and Investment
Related agencies and donors
Second quarter of 2012
Penalties to assure Compliance with regulations on monitoring, supervision and evaluation elaborated and applied
4. Enhancement of community-based monitoring and supervision
Ministry of Planning and Investment
Related agencies and donors
Regularly Institutions and environment favourable for community participation in monitoring and supervision of effectiveness of ODA and preferential loans enhanced
VII. Information publicity and transparency
1. Coordination with donors in publicizing policies, prioritized sectors and areas,
Ministry of Planning and Investment
Related agencies and donors
2012-2015 Policies, prioritized sectors and areas. conditions for provision of ODA and preferential
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 409
Group of solutions
Action Responsible agency
Coordinating agency
Deadline Indicator for monitoring
conditions for provision of ODA and preferential loans of donors
loans of donors publicized
2. Updating of information on attraction, management and use of ODA and preferential loans in the mass media
Ministries of Planning and Investment, and Finance, ministries, sectors and localities
Related agencies and donors
2012-2015 Information on Attraction, management and use of ODA and preferential loans updated and provided in the mass media
VIII. Implementation of the scheme
1. Dissemination, thorough grasp and implementation of the scheme
Ministry of Planning and Investment
Related agencies and donors
Second quarter of 2012
Ministries, sectors, localities and donors guided in and thoroughly grasping the spirit, guiding principles and contents of the scheme; the action plan for the scheme implementation implemented
2. Monitoring and evaluation of the scheme implementation
Ministry of Planning and Investment, ministries, sectors and localities
Related agencies and donors
2011-2015 Biannual and annual reports on the scheme implementation and results of ministries, sectors and localities sent to the Ministry of Planning and Investment; periodical reports and reports on mid-term and final evaluation of the scheme implementation results of the Ministry of Planning and Investment submitted to the Prime Minister
Decision No. 553/QD-EVN dated 7 September 2011
Issuance of regulation on delegation of investment decision and investment implementation in Vietnam
Electricity.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 410
Relevant to project management
Decree No. 12/2009/ND-CP dated 12 February 2009 and amendment Decree No. 83/2009/ND-CP dated 15 October 2009
The Decree No. 12/2009/ND-CP dated 12 February 2009 is an over encompassing decree on all the
construction activities in various social and economic infrastructure sectors of Vietnam, viz., power industry, oil
and gas extraction, chemicals, fertilizer, machine manufacture, cement, metallurgy, mineral exploitation and
processing, all modes of transport sector, irrigation, housing, electronics, pharmaceutical, telecommunication,
health care, tourism, aquaculture, forestry and fishery product processing etc. The Decree details about various
categories of infrastructure projects depending on nature, size, source of funding etc. and mentions roles,
responsibilities and authorities of different “investment deciders” in various stages of projects including
formulation, funding, evaluation and approval of feasibility studies, techno-economic studies, monitoring of
implementation etc. The Decree also elaborates on capability conditions of organizations and individuals
engaged in various construction activities.
The formulation, evaluation and approval of investment projects on the construction of works funded with
ODAs shall comply with the corresponding laws of ODA.
Salient features
1. Project classified based on investment requirements and sector- Group A (> 1500 billion VND),
Group B (75-1500 billion VND) and Group C (<75 billion VND). Power projects fall under all the
three groups depending on investment size.
2. Involvement of state management in a project across different stages also depends upon funding
source of projects i.e., For a state-funded project, state manages the project across the life cycle
from identification of investment policies, project formulation, investment decision, designing,
estimation, contractor selection, construction, testing and operation. Whereas, for a private sector
project, investors shall decide on forms and contents of project management.
3. Formulation of Projects: Details of formulation of different construction projects in feasibility
reports with design plan, design drawings along with authorities for approval for different types of
projects and time limits are explained in this Decree. For example, in case of design drawings, there
are 3 different types of construction designs depending on the size and nature of a specific work.
a. One-step design: In this case, basic design (during formulation of project indicating major
technical specifications), technical design (post investment approval with further details)
and working drawing design (exhaustive design used in construction) steps are combined
into working-drawing design step;
b. Two-step design: Involves separate basic design and combining technical design and
working-drawing design; and
c. Three-step design: Involves separate basic design, technical design and Working-drawing
design. Power Transmission projects generally fall under this category.
4. Evaluation of Projects: Project evaluation authorities/ committees along with their composition
and evaluation methodology for different projects are explained.
5. Management of environment and labour safety: Steps to be taken for proper environment
management, labour safety during construction activities are described.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 411
6. Capabilities of organizations and individuals engaged in construction activities across different
levels are elaborated.
Amendment to Decree No. 83/2009/ND-CP dated 15 October 2009
1. Investment deciders shall allocate sufficient capital within 3 years, for group-C projects, or 5 years,
for group-B projects, depending on project implementation schedules.
2. Time limits set for agencies examining the project dossiers for different categories of projects and
in case of no opinion within stipulated timelines, a deemed agreement is assumed for the project
dossiers.
3. Amendments for clauses regarding adjustments in projects for which state’s contribution is more
than 30% and detailing type of public projects that can be set for architectural design competitions;
Expenses for such competitions will be considered part of project investment.
4. Ministry of Planning and Investment to guide capability conditions of organizations and
individuals for evaluating work construction investment projects.
Decree No. 14/2014/ND-CP dated 26 February 2014
The Government Decree No. 14/2014/ND-CP dated 26 February 2014 provides detailed stipulations on
implementation of some articles of the Electricity Law on power safety, including safety in power generation,
transmission and distribution along with safety norms during construction and operation of transmission line
for personnel as well as general public. The Decree also elucidates about compensation and assistance for
buildings, land and trees to be acquired in safety corridors of overhead electrical wires during construction and
operation as well.
Salient features
1. Norms for permitted working time vis-à-vis electric field intensity in and around substations
2. Different safety clearances for electricity discharge by voltage level for overhead power
transmission lines, underground cables and substations
3. Contents for Training programme on safety for workers
4. Technical parameters for material and insulation type used in power transmission
5. Procedures to be followed in operation and maintenance like tree cutting, periodicity, intimation to
owner or Commune People’s Committees
6. Compensation norms, authorities responsible for approving compensation amount for land,
households and other property which is being used for construction of transmission assets
Decree No. 15/2013/ND-CP dated 6 February 2013 and Circular No.10/2013/TT-BXD dated 25 July 2013
The Government Decree No. 15/2013/ND-CP dated 6 February 2013 provides regulations on quality
management of construction works in survey, design, construction execution and acceptance of construction
works; on safety management, handling of incidents during construction execution, exploitation and use of
construction works; and on warranty of construction works.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 412
Salient features
1. Nodal Agency: Ministry of Construction is nodal agency for the quality of construction works
across all sectors. Since, the construction of transmission lines falls under specialized category of
construction works and Ministry of Industry & Trade supports Ministry of Construction.
2. Project Classification: Projects classified into five different categories - building works,
industrial works (includes power sector projects), urban infrastructure projects, transport works,
works for agriculture and rural development.
3. Survey: Various tasks in construction survey along with responsibilities of Investor, Survey
Contractor and other organizations supporting in survey are mentioned.
4. Design: Various tasks in design (including drawings, specifications etc.) for works along with
responsibilities of Investor, Design Contractor are mentioned. Further, steps in appraisal and
approval of design including role of state authorities (Ministry of Construction, Ministry of
Industry & Trade, Departments of Construction and Industry & Trade) in verification of design
works are also detailed.
5. Construction Execution: Responsibilities of investors, Design Contractors, Construction
contractors, manufacturers and suppliers of materials & equipment used in construction works etc.
are elaborated. Safety management during construction and inspection responsibilities of different
ministries/ departments along with timelines for implementation of the same are elaborated.
Ministries of Construction and Industry & Trade along with the corresponding departments are
responsible for power transmission projects. Dispute resolution mechanism is also specified.
6. Warranty post Construction: Warranties (time lines) for different grade projects and
responsibilities of parties are specified.
7. Incident handling: Based on the damage to human life and property, incidents are graded into 4
levels- particularly serious level, level I, level II and level III. Provincial People’s Committees are
responsible for sending the reports on incidents to concerned Ministries. In case of any incident,
the Ministry of Construction along with Ministry of Industry & Trade (for power transmission) are
mandated to investigate it, prepare a report on causes and remedial measures being adopted.
Circular No.10/2013/TT-BXD dated 25 July 2013
This Circular elaborates regulations on inspection, assessment and approval of construction quality
management according to the Decree No. 15/2013/ND-CP, applicable to the building works (does not cover
power sector projects). The circular mentions the tasks of project management enterprise/ investor for
construction quality management (e.g.: selection and approval of sub-contractor, building schedule, quality
control etc.) under different kinds of contracts- Engineering-Procurement-Construction (EPC), Engineering-
Construction (EC), construction, Engineering-Procurement (EP), Procurement-Construction (PC) and under
different ownership models - BOT, BTO, BT, or PPP.
The circular details various steps of construction survey- objectives, survey plan and survey activity,
preparation of report, assessment and acceptance. Plans for controlling quality during construction process
along with such methods for different products and safety measures to be adopted during construction have
been mentioned. All steps similar to life cycle of construction project i.e., design, work plan, plan for controlling
quality, monitoring construction works’ quality & supervision, inspection, assessment are to be performed for
building construction also. The construction authorities affiliated to the Ministry of Industry and Trade will
inspect the building works in power lines in class I, II & III projects. After performing requisite tests on building
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 413
structures and providing reports, completion reports have to be prepared by the investors. Any disputes over
construction quality shall be settled either through - negotiation, hiring a third party consultant or courts.
People’s Level Committees of provinces have to send annual or unscheduled reports on the quality and quality
management of local building works to the Ministry of Construction before December 15 every year. Penal
measures in case of failure in meeting the set standards are also mentioned.
Circular No. 13/2013/TT-BXD dated 15 August 2013
This circular details the verification, appraisal and approval for technical design for works implementing three-
step design, construction drawings design for works implementing one-step or two-step design and other
designs which are carried out following fundamental design specified in Article 20 and Article 21 of the Decree
No. 15/2013/ND-CP, dated February 06, 2013, on quality management of construction works (hereinafter
abbreviated to Decree 15/2013/ND-CP).
In case of works does not fall under the five categories mentioned in Article 21 of Decree 15/2013/ND-CP,
investors will submit technical or construction drawings design (as applicable for one-step, two-step or three-
step design) following basic design to construction-specialized agencies at Central level (Ministries of
Construction, Industry and Trade etc.) and Provincial/Municipal level (e.g.: Departments of Construction,
Industry and Trade etc.) for verification. The verification can be done by agencies appointed by construction-
specialized agencies in case of non-state funded projects. Details of contents of such appraisal and verifications
reports are elaborated - e.g.: conformity about components, specifications of design dossiers compared with
regulations, gaps found etc. After verification, construction drawings are to be approved by Investor.
In case of any change in work construction design due to any reason, the verification, appraisal and re-approval
has to be done. A dossier of design verification of the works construction design includes a report for
verification of the works, approval of project decision, conditions on capability of survey contractors,
contractors for construction design, Drawings and design description, construction estimate of works etc.
Different time limits for verification of construction design for different projects is specified and time for
beginning the design verification of the construction-specialized agency is calculated from the date of receipt of
full and valid dossier. Investors will pay charges for the verification charges to the agencies in line with
provisions of the Ministry of Finance.
Decree No. 69/2008/ND-CP dated 13 August 2009
The Government Decree No. 69/2008/ND-CP dated 13 August 2009 provides regulations on land use planning,
land recovery, compensation, support and resettlement, land prices, land allocation and lease, land use rights
and ownership of houses and other assets attached to land, and land use duration extension.
The land use plan will be consolidated through a bottom-up approach in the People’s Committees at different
levels-Commune level, District level and Provincial Level. Provincial level People’s Committees coordinate with
different ministries (including Ministry of Industry & Trade) which propose their demands for land use in
different areas. Ministry of Natural Resources and Environment finalizes the land use plan and formulates
national-level land use plan and submits to Government for approval.
Salient features
1. Land Prices: In case of land use by equitized state enterprises who have been allocated land by
government (i.e. not through competitive bidding or auctioning), there is provision to re-determine
rates set by Provincial People’s committee in case the rates set are not close to actual market prices.
Principles for setting the annual land rent rates as well as lump sum rates are available in the
decree.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 414
2. Key Compensation principles:
a. Provincial level People’s committees assign compensation, support and resettlement tasks
to compensation organizations viz. District-level compensation, support and resettlement
councils, Land fund development organizations. The composition of such organizations
and funds for their expenses are elaborated in the Decree; and
b. Land recovered by the State shall be compensated with new land with the same use
purpose. If no land is available for compensation, compensation equal to the value of land
use rights calculated based on land prices at the time of land recovery decision will be paid.
In case land is compensated with new land or residential land or a house for resettlement,
any difference in value shall be paid / recovered in cash.
c. Provincial-level People's Committees shall, based on the practical conditions of localities,
prescribe the minimum resettlement quota and support levels. In case compensation
amount is less than the minimum resettlement quota, households and individuals
receiving residential land or houses for resettlement are entitled to the difference as
resettlement support.
d. Supports: Principles for life support, job support and other supports are referred in the
Decree. For example, in case of recovery of agricultural land, support for life stabilization
will be provided as follows:
Support* to land users who 30-70% agricultural land
>70% agricultural land
need not move out 6 months 12 months
have to move out 12 months 24 months
move out to areas with extreme difficulties
24 months 36 months
* cash equivalent to 30 kg of rice for a month at the average price at the time the support
3. Procedures for Land Recovery, Allocation and Lease: In case it is decided to auction land
use rights for a particular land, land shall be recovered and allocated to land fund development
organizations for clearing the ground and organizing the auction. Subsequently, natural resources
and environment agencies shall carry out procedures to issue certificates of land use rights (as
applicable) to the successful bidder in auction. In case, land is required to be recovered for a
project, following steps are followed. It may be noted that this is not an exhaustive process and
some steps have been simplified for the purpose of clarity.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 415
Investor to submit a dossier to local agency which submits to Provincial level People's Committee(PLPC)
Land recovery note (LRN) contains reasons for land recovery, area, location, approved detailed construction planning, relocation plan
Is identified Land under planning stage?
PLPC notifies land recovery (land recovery note) or authorize district-level People's Committee(DLPC) to notify land recovery after introducing an investment site.
No
Wait till issue of Land PlanYes
PLPC chairperson permits Investor to conduct survey and map project area after investment approval; prepare detailed construction planning for approval, recovering land and making a master plan on compensation, support & resettlement
LRN notified in local media, posted at head offices of Commune Level peoples’ Committees (CLPC) & public places in areas where land is to be recovered
PLPC chairperson directs DLPC /CLPC to perform following activities
DLPC to set up a council to make a compensation , support & resettlement plan , job training etc. If Land fund organizations exist, they may be assigned this task
CLPC to coordinate with the investor in preparing survey and also with local people
Investor formulates investment project proposal under applicable laws along with all details /plans on compensation , resettlement etc
Compensation, support & resettlement plan Details of land losers, land, compensation & support plan, resettlement arrangements , relocation etc
Min 20 days
NREAs submit land recovery dossiers to corresponding Level people Committees(LPCs)
LPCs decide to acquire land
Provincial/District NREAs submit compensation plans to corresponding LPCs for approval
5 days
Approval of LPCs on compensation plans
CGCO coordinates with CLPCs in publicizing the plan
3 days
Council on Compensation, support and resettlement pays compensation to the land losers
Land recovered from respective persons/ organizations
20 days
Land coercion by CGCO, CLPC etc in case land is failed to be handed over30 days
A
A
Compensation plan publicized similar to LRN
Comments received by Compensation & ground clearance organization(CGCO)
CGCO summarizes and sends to natural resources & environment agency (NREA)
Provincial/ District level NREAs coordinate with respective agencies and decide on land recovery
Process from Planning of Compensation to Land Recovery
Land Recovery Process
Decree No. 106/2005/ND-CP and Amendment Decree No. 81/2009/ND-CP
Decree No. 106/2005/ND-CP dated 17 August 2005 details and guides the implementation of articles of the
Electricity Law on protection of safety of high-voltage power grid works. This decree is supplemented by Decree
No. 81/2009/ND-CP dated 12 October 2009 which has amended certain articles (primarily regarding removal
of 66 kV voltage level and compensation and resettlement mechanism).Decree 106 mentions the safety
corridors (i.e. specific width depending on voltage level and along the length of line) and clearances (safety
corridors) required to be maintained for different voltage levels for protection of various assets and their users
viz. household, trees, crops in fields, railway transport, inland water ways, existing transmission wires & power
cables. The compensation & resettlement framework for tower footing and Right of Way of power transmission
lines provided in the decree is summarized below:
Project Relocation & Compensation
Compensation &
supports for houses
and facilities inside
power grid safety
corridors
For 220 kV & below transmission lines
No relocation required subject to electric field intensity being under stipulated
limits, maintaining safety clearances and following stipulated conditions (e.g.:
fire-proof roofs& walls, proper earthing of metal structure).
Compensation up to 70% of value of house (or as decided by PLPC) provided for
restricted usability and impact on daily life.
If the above stipulated safety criteria are not met, additional compensation to be
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 416
Project Relocation & Compensation
borne for meeting those conditions will also be provided to the PAP.
If these criteria cannot be met, then PAPs are entitled for relocation support
For 500 kV transmission lines
Relocation of all land users is mandatory if they lie inside safety corridors of
500 kV transmission lines. All compensation and support provided as per
relevant decree
Compensation or
support for land inside
power grid safety
corridors
If land lies in the safety corridor and is not subject to land recovery, users will
be entitled to compensation or support for restricted usability of their land.
Lump sum compensation or support will be decided by PLPC and paid from
investment project capital
Compensation or support not exceeding 80% of the compensation for recovery
of land (residential or combination of residential & other types) calculated on
the land area lying inside the corridor
Other salient points:
When land users have to relocate their houses from safety corridors and wish to change the use of
land of other types outside the safety corridors into residential land, local land management
agencies shall carry out procedures to propose competent authorities to permit the change of land
use purpose.
Compensation will be provided for tree felling /trimming whether they are inside or outside the
safety corridors if they exist before implementation notice.
However, we understand that both Decree No. 106/2005/ND-CP and Decree No. 81/2009/ND-CP are expiring
on 15 April 2014 and are awaiting inputs on valid decrees.
Decision No. 2414/QD-TTg dated 11 December 2013
The decision finalises the list and commissioning schedule of key generation and transmission projects during
2014-20 period. Criteria for generation and transmission projects to be treated as urgent are stated in this
decision.
1. Preparation for Project Investment: Investors can appoint domestic advisory contractor(s), in
line with Law on bidding, for preparation & verification of technical design, compensation and
resettlement, social-environment report, feasibility report and other support during
implementation of project. The pre-conditions for investors for starting a project are capital
mobilization plan (in-principle agreement on capital supply from credit institutions) and
satisfactory environmental standards. In case of urgent power transmission projects, the investors
are allowed to carry out previously a few of contents of survey, advisory for making technical design
during appraisal and approval of the investment project. In case investors are allowed to put
implementation of technical design into the scope of work of EPC bidding package, they will be
responsible for preparation of appraisal, approval of technical design; appraisal and approval of
design of construction drawings
2. Compensation and ground clearance: Investors can appoint suitable agencies for setting up
landmarks of corridors of lines as soon as the competent agencies have approved sub-projects on
compensation, ground clearance & resettlement and relevant PPCs have granted Right of way for
lines.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 417
3. Selection of contractors & contract price: Competent authorities will decide the bidders in
line with Decision No. 50/2012/QD-TTg dated 09 November 2012. In case of urgent projects with
similar technology/ parameters, contract can be negotiated directly with those having similar
experience in the last 5 years subject to some principles (e.g.: quality of equipment should not be
lower than quality of project already executed). Further, prices for imported equipment and
services are lump-sum and for domestic construction, instalment, it is adjusted w.r.t. changes in
exchange rate, labour unit price and prices of other inputs. Also, provisions for contract price
variation (increase or decrease) can be kept for change in scope, volume or quantity of work.
4. Funding arrangement: Foreign funding is allowed for investors as prescribed in Law on Public
Debt Management and the Government’s Decree No. 15/2011/ND-CP dated 16 February 2011. With
respect to domestic funding, State Bank of Vietnam can direct domestic commercial banks to
provide loans to investors. Credit institutions are allowed to provide loans exceeding 15% of own
capital for a customer and exceeding 25% of own capital for a group of concerned customers.
Further, domestic credit institutions are exempted from appraisal of economic and financial
efficiency for each power transmission project.
5. Responsibilities of Ministries: Ministry of Industry and Trade (MoIT) shall appraise, approve
supplementation of list, and correct the scale and progress of the transmission augmentation works
so that the system operates in synchronism with generation addition finalised in the Decision.
Relevant ministries shall support and, coordinate with MoIT in monitoring, inspecting, urging,
aiming to facilitate for investors in effective implementation of the urgent power projects; timely
resolution of issues under their competence, and escalation of issues if the same cannot be resolved.
PPCs shall support by allocating land, establish councils of compensation and ground clearance and
population relocation and resettlement.
Law No. 43/2013/QH13 regarding Law on bidding
1. Scope of law: Among other projects, this law regulates selection of bidders to provide advisory
services, non-advisory services, goods, construction and installation for investment projects of
state-owned enterprises (SOEs) in which SOEs investment is (a) 30% or more; (b) less than 30%
but total invested capital is more than 500 billion VND.
2. Types of bidding methods and processes: The law details different types and methods of bid
processes viz., open & limited bidding, domestic & international, Direct & competitive, single phase
& two phase, single dossier bag & two dossier bags etc. and mentions the cases in which particular
method/ type can be used.
Timelines applicable for key steps in selection of bidders are as below:
Sl. No.
Key Activity in procurement process Timeline
Domestic International
1. Time for appraisal and approval of Plan on tenderer selection
20 days for appraisal and 05 working days for approval after receiving report on appraisal
2. Time for appraisal and approval of bid dossiers after submission by bid solicitor
20 days for appraisal and 10 working days for approval after receiving report on appraisal
3. Time for issue of dossiers for submitting EOIs, invitation for pre-qualification, dossiers of requirements
03 working days from day of publishing such notices
4. Time for EOI /pre-qualification submission by tenderers 10 days from issue of bids
20 days from of issue of bids
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 418
Sl. No.
Key Activity in procurement process Timeline
Domestic International
5. Duration for preparing the bid dossiers by bidders At least 20 days At least 40 days
6. Duration for bid evaluation / assessment
dossiers of expression of interest / pre-qualification
dossier of proposals
bid dossiers
20 days 30 days* 45 days *
30 days 40 days* 60 days*
7. Duration for approving or giving the handling opinion on result of tenderer selection
10 days 10 days
* can be extended by another 20 days if required
1. Selection Process: The law provides articles on formulation of plan for selection of bidders with
project and package details, estimated price, capital sources, method and type of procurement,
duration of contract etc. The plan will be submitted to the competent authority by the investment
owner/ bid solicitor for their evaluation and approval. Generic steps for tenderer selection are
Prepare for tenderer selection; organize the tenderer selection; assess dossier of proposals and
negotiate contract; submit, evaluate, approve and publicize the result of tenderer selection; finalize
and sign contract. These steps vary according to the method and type of selection. Eligibility
conditions, value of bidding guarantee for different kinds of supply and services contracts along
with conditions for return of security are also provided.
2. Evaluation: Different methods to assess bidders for goods and construction are available- (a)
lowest price (all bidders who satisfied required technical criteria will be ranked in terms of their
quotes), (b) assessment price (all expenses converted on a same ground on technical, financial and
commercial elements for entire use life cycle of goods), (c) combination of both the lowest price and
assessment method. Advisory services packages are also evaluated similarly. After evaluation,
contract will be signed between successful bidder(s) and authority.
3. Contract: Different types of contracts depending upon contract payment- lump sum, fixed unit
price, modifiable unit price, time-based contract are prevailing in Vietnam. Also, list of contract
documents, contract performance guarantee, contract adjustments are elaborated in the law.
4. Responsibilities: Responsibilities of different parties in selection of tenderers, investors -
competent agencies, investment owner, bid solicitor, expert groups, evaluating organizations,
tenderers and investors are elaborated in the law. Further, responsibilities of different state
agencies like Ministries, Prime minister and peoples’ committees in managing & supervising bid
processes are mentioned.
5. Others: The law also talks of banned acts in bidding process and how to deal with violations in bid
process and resolution of protests and disputes in bidding process.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 419
Relevant to transmission pricing
Electricity Law No. 28/2004/QH11 dated 3 December 2004
This law dated 3 December 2004 as amended by Law No. 24/2012/QH13 dated 20 November 2012 is the
guiding principle which specifies broad rules and regulations by which all entities that operate in the electricity
sector abide by. These principles lay down the basis for development planning and investment of the electricity
sector; development and operation of the electricity markets; rights and obligations of organizations and
individuals undertaking various activities and users of electricity; protection of electrical equipment; electricity
saving and safety.
Salient features (relevant to transmission pricing)
Article 30 lays down the basis for determining and adjusting electricity price as follows:
1. The electricity price policies;
2. The socio-economic development conditions of the country, people’s incomes in each period;
3. The electricity supply-demand relationship;
4. The electricity production and business costs and reasonable profits of electricity units;
5. The electricity market development grades; and
6. The annual audited financial statement of the electricity unit.
Article 31 stipulates guidelines for adjustment of electricity prices and associated charges as follows:
1. The schedule of electricity retail price shall be worked out by the electricity retailing entity based on
the framework of average price, the mechanism of adjustment of price and structure of the retail
price prescribed by the Prime Minister, and in conformity with the level of development of the
electricity market.
2. The MoIT is primarily responsible, and coordinates with the MoF to elaborate the price framework
based on average price, mechanisms of adjustment of price and structure of the retail price table
and submit them to the Prime Minister for final decision. The adjustment of the electricity retail
price must be implemented publicly, transparently with respect to changes of component relating
to adjustment of such price. The State uses measures to stabilize the electricity sale price in
conformity with provisions of the Law on price.
3. The price of - electricity generation, electricity-wholesaling, transmission and auxiliary services for
electrical system; charges for regulating the system operations and charges for administration of
market transaction shall be elaborated by the concerned electricity units and appraised by the
electricity regulating agency before they are submitted to the Minister of Industry and Trade and
the Minister of Finance for approval.
4. The MoIT shall assume the prime responsibility for, and coordinate with the MoF to guide methods
to elaborate the range of electricity generation, electricity-wholesaling, transmission and auxiliary
services for electrical system; charges for regulating the system operations and charges for
administration of market transaction.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 420
Article 40 lays down the rights and obligations of the electricity-transmitting unit. The electricity-transmitting
units shall also have the following rights:
1. To elaborate and submit for approval the electricity transmission charges;
2. To be supplied with necessary information on electricity-transmitting activities.
Decree No. 137/2013/ND-CP dated 21 October 2013
The Decree No. 137/2013/ND-CP dated 21 October 2013 deals with the implementation aspect of various
clauses stipulates in the Electricity Law 2004;
Salient features (relevant to transmission pricing)
1. MoIT is responsible to regulate the method, formulation and review of power generation price
framework, power wholesale price framework, power transmission line charge, auxiliary service
price of power system, load dispatch and operation charge of power system, operation charge of
power market transaction after considering inputs received from the Ministry of Finance.
2. MoIT is responsible to approve:
a. Load dispatch and operation charge of power system, operation charge of power market
transaction after considering inputs received from the Ministry of Finance;
b. Power generation price framework, power wholesale price framework, power transmission
line charge, auxiliary service price of power system except for cases regulated in clause 22
of Article 1 of amended and supplemented law on electricity.
The above Decree clearly chalks out the roles and responsibility of MoIT in approving the pricing framework
and regulating the charges for all operations in the electricity sector.
Decision No. 69/2013/QD-TTg dated 19 November 2013
The Decision No. 69/2013/QD-TTg of the Prime Minister dated 19 November 2013 regulates mechanism for
changing of average retail power price;
Salient features (relevant to transmission pricing)
Article 4 lays down the mechanism for adjustment of electricity selling price as follows.
1. In a given financial year, average electricity selling price is considered for adjustment when the
basic input parameters change in comparison to the parameters which had been used to define the
basic average electricity selling price.
2. In case where the basic input parameters changed in comparison to the parameters used for
defining the basic average electricity selling price, which makes the basic average electricity selling
price.
a. lower than the current average selling price and within the defined price bracket, EVN
shall reduce the average selling price to the respective level and report to the MoIT and
MoF;
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 421
b. higher than current average selling price (after using power price stability fund) by 7% to
less than 10% and within the set price bracket, EVN will be entitled to adjust the increase
average power price at corresponding levels after reporting and receiving approval of the
MoIT;
c. higher than current average selling price (after using power price stability fund) by more
than or equal to 10% and not within the set price bracket, EVN will be entitled to adjust to
increase average power price at corresponding levels after reporting and receiving
approval of the MoIT. EVN will prepare a price proposal document, report to MoIT and
submit to MoF for review. Within 10 working days, MoF has responsibility to review and
send its comments to MoIT. Within next 10 working days, MoIT has responsibility to
consolidate and submit the appraisal opinion to the Prime Minister for consideration and
direction.
Article 5 lays down the responsibility of examination and supervision over adjustment of average electricity
selling price as follows.
1. The MoIT is responsible to examine and supervise over adjustment of average electricity selling
price. When necessary, the MoIT shall request in writing to the EVN for reducing or stopping any
increase of the average electricity selling price.
2. The MoF is also responsible to examine adjustment of the average electricity selling price;
participate in and coordinate with the MoIT in examining differences of rational and regular costs
in comparison to the figures calculated in the petition of electricity selling price after having figures
of settlement statements, audit reports etc.
3. The MoIT is also responsible to announce publicly the cost price of electricity production and
business at all stages, namely of generation, transmission, distribution and retail supply,
administration of auxiliary services of electrical system; the extent of loss or profit of the EVN and
costs which have not yet been included in the cost price of electricity production and business. The
EVN shall announce publicly the adjustment of average electricity retail price and reason thereof.
The above clauses shed light on the mechanism of retail selling price adjustment and its likely impact on the
transmission charge approved. A better understanding of the basis of cost adjustments (true-up process) will
help in bringing out any shortcomings in the existing mechanism of finalization of the transmission charge.
Circular No. 14/2010/TT-BCT dated 15 April 2010 and Circular No. 03/2012/TT-BCT dated 19 January 2012
The Circular No. 01/VBHN-BCT dated 6 September 2013 is a consolidated circular specifying the methodology
for process and procedures for formulation promulgation and management of the power transmission charge.
This circular was originally promulgated as Circular No: 14/2010/TT-BCT dated 15 April 2010 and later
amended through Circular No. 3 /2012/TT-BCT dated 19 January 2012.
This elaborates the methodology stipulated for determining the transmission charge and lays down the process
to be followed for submission/ filing of the transmission charge petition by the EVNNPT to the EVN for
consensus and further to MoIT and ERAV for final assessment and approval.
This provides the following principles and mechanism for allocation of transmission charges on the users of the
system.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 422
Transmission tariff calculating principle
The annual power transmission charge is applied as a unified price nationwide irrespective of distance of power
transmission and point of transfer and receipt.
Average transmission charge is determined annually under the principle of recovery of eligible costs and
profitability to operate the electricity transmission grid to achieve specified quality criteria and meet financial
requirements for investment and development of electricity transmission grid.
Average transmission charge of year N (NTTg )
Determined based on the permitted total transmission revenues of year N of the EVNNPT and total energy
output delivered by the EVNNPT to the units subject to pay transmission charge at the delivery points.
n
i
DB
GN
TT
TT
Ni
N
N
A
Gg
1,
Where:
NTTG:
Permitted total transmission revenues of year N of the National Power Transmission Corporation (VND);
Ni
DB
GNA, :
Total energy output expected to be delivered of the unit i at all delivery points in year N (kWh);
n: Number of units subject to pay transmission charge.
Annual permitted total transmission revenue of year N (NTTG ) includes: permitted capital cost (
NTTCAPC ),
permitted operation and maintenance cost (NTTOMC ) and adjusted transmission revenue for year N-1 (
1NCL )
1 NOMCAPTT CLCCGNTTNTTN
Where:
NTTCAPC:
Permitted transmission capital cost for year N of the EVNNPT (VND);
NTTOMC:
Total permitted operation and maintenance cost of year N of the EVNNPT (VND);
CLN-1: The difference between transmission costs and revenues of year N-1 which is adjusted in the permitted total transmission revenue of year N (VND).
Capital cost:
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 423
Total capital costs of transmission of year N ( ) is defined under the following formula:
=
Where:
: Total depreciation costs of fixed assets in year N (VND);
: Total long-term loan interest expenses and borrowing fees and payables in year N for transmission assets (VND);
LNN: Eligible power transmission profit of year N (VND).
Operations and Maintenance cost:
Total O&M costs of year N ( ) is defined under the following formula:
Where:
: Total material costs of year N (VND)
: Total salary costs of year N (VND)
: Total major repair costs of year N (VND)
: Total outsourced service costs of year N (VND)
: Total of other expenses in cash of year N (VND)
Cost and Revenue adjustment component:
The EVNNPT shall be responsible for setting up and maintaining the system of records to monitor cost items to
determine the difference between the cost and revenue of year N-1 to adjust in the permitted total transmission
revenue of year N.
The adjustment of transmission cost and revenue can only be done in the following cases:
Actual total revenue of year N-1 of the EVNNPT is different from the approved permitted total transmission
revenue of year N-1;
Actual rise in eligible costs of year N-1 (based on the financial statements) against the approved proposal of
transmission charge of year N-1 (including depreciation cost, long term interest, salary cost, overhaul cost,
outsourcing service cost, difference of exchange rate), except the arisen cost prescribed in the two cases
below;
Cost incurred for remedies of damages due to natural calamities and force majeure in year N-1;
Arisen cost for reasonable investments in transmission assets beyond the plan of year N-1 approved by the
State’s competent agencies.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 424
Transmission charge ( ) (VND/kWh) of year N chargeable to payer i of transmission charge
This charge is based on the following formula:
Where:
TCi: Transmission costs to be paid by payer i of transmission costs in year N (VND);
: Total forecast power delivery of payer of power transmission costs at all delivery points in year N;
The transmission charges payable by payer i of transmission costs in year N (TCi) is calculated by employing the
following formula.
1,, NiAPNi DCTCTCTCii
Where:
TCP,i: Capacity transmission charge (VND) TCA,i: Energy transmission charge (VND)
1, NiDC:
Total adjustment amount of transmission charge payable by payer i of transmission costs for year (N-1) (VND)
Components of electricity transmission costs by capacity and power volume are determined by the following
two formulas.
Where:
Total adjustment amount of transmission charge payable by the ith unit due to the difference between the actual
energy delivery output, actual maximum delivery capacity and the estimated energy delivery output and the
estimated maximum delivery capacity for year N-1 (DCi,N-1) is calculated by employing the following formula:
: Total forecast maximum delivery capacity of payer i of power transmission costs in delivery points in year N (MW)
n: Total number of payers of power transmission costs α, β: Ratio of capacity and energy volume components in the power transmission charge
regulated by ERAV each year, with α + β = 1; regulated α = 0 for the year 2011
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 425
n
i
DB
DB
n
i
TT
TT
n
i
DB
DB
n
i
TT
TT
NTTNNi
A
A
A
A
P
P
P
PGIDC
1
1-NGNi,
1-NGNi,
1
1-NGNi,
1-NGNi,
1
1-Ni,
1-Ni,
1
1-Ni,
1-Ni,
111, %1
Where:
Transmission costs of month j (TCij) of payer i of power transmission costs is defined by the following formula.
Where:
Principles of penalty for failed service quality
The EVNNPT is fined for failing to guarantee quality of service in cases where outages of transmission lines and
transformers of the transmission grid in the year exceeds regulated limits for each voltage level, except for
incidents caused by force majeure (natural disaster) or problems not caused by EVNNPT.
Mechanism of penalties is applied annually by deduction from welfare fund with an amount equal to the total
penalty for failure to guarantee transmission service quality and that amount is transferred to the development
reserve of EVNNPT.
The annual total amount of penalty for failed service quality (year N) RN of EVNNPT is defined by the following
formula:
1NTTG:
Total power transmission revenue of year (N-1) (VND)
DBP 1-Ni, : Total estimated maximum capacity of the ith unit subject to pay transmission charge at all delivery points in year (N-1) (MW)
TTP 1-Ni, : Total actual maximum capacity of the ith unit subject to pay transmission charge at all delivery points in year (N-1) (MW)
DBA 1-Ni, GN : Estimated energy delivery output of the ith unit subject to pay transmission charge in year (N-1) (MWh)
1-Ni,
TT
GNA:
Actual energy delivery output of the ith unit subject to pay transmission charge in year (N-1) (MWh)
1NI:
Average interest rate of deposit in VND, term of 12 months post-paid for corporate customers determined on the December 31st of year (N-1) of 4 commercial banks (Vietcombank, Vietinbank, BIDV, Agribank) plus 3.0%
: Total of actual delivery volume at delivery points of payer i of transmission costs in month j (kWh)
: Transmission tariff of year N for payer i of transmission costs (VND/kWh)
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 426
Where:
: The amount of penalty for failed transmission service quality due to outage of transmission lines (VND)
: The amount of penalty for failed transmission service quality due to outage of transformers (VND)
Li,N (Lj, N, Lk,N): Total length of 110 kV transmission line (220kV, 500kV) under outage when the incident i happened (j, k) (km)
Si,N (Sj,N,Sk,N): Total capacity of transformer of high voltage level of 110kV (220kV, 500kV) under outage when the incident i happened (j, k) (MVA)
ti (tj, tk): Time of outage of transmission line or transformer of high voltage level of 110kV (220kV, 500kV) when the incident i happened (j, k) (minute)
n (m, l): Number of outages of transmission line or transformer of high voltage level of 110kV (220kV, 500kV) in year N (from 01 September of year N-1 to 31 August of year N)
,
Penalty for failed service quality due to outage of transmission lines in year N for each km of 110 kV, 220 kV & 500 kV transmission line in a minute [VND/(km x minute)] is calculated by the following formula:
= X110 or (X220, X500, Y110, Y220, Y500) x GTT N
,
Penalty on failed transmission service quality due to outages of transformer in year N for each MVA of transformer, of voltage level 110 kV, 220 kV & 500 kV in a minute [VND/(MVA x minute)]
X110, X220, X500 Penalty ratio for failed transmission service due to outage of transmission line of 110 kV, 220 kV & 500 kV [1/(km x minute)]
Y110, Y220, Y500 Penalty ratio for failed transmission service due to outage of transformer of 110 kV, 220 kV & 500kV [1/(MVA x minute)]
A (B, C): Penalty norms for outage of transmission line at 110 kV (220kV, 500kV) D (E, G): Penalty norms for outage of transformer at 110kV (220kV, 500kV)
The total penalty for failed service quality in year N (RN) of EVNNPT for 0.1% incidence is (0.1% x ).
Incidents of failure of transmission line and transformers are taken into consideration when defining penalties
for failed service quality when the outage last for at least 1 minute.
Circular No. 203/2009/TT-BTC dated 20 October 2009
Article 4 deals with determination of historical costs of fixed assets:
The historical costs of fixed assets of enterprises may only be changed in the following cases:
1. Revaluation of fixed assets in the following cases:
a. Under decision of a competent state agency;
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 427
b. Reorganization of the enterprise, change of ownership of the enterprise, transformation of
the enterprise: separation, splitting, merger, consolidation, equitization, sale, contracting,
lease, transformation of limited liability company into joint-stock company and vice versa;
and
c. Use of assets for outward investment.
2. Upgrading of fixed assets.
3. Removal of one or a number of parts of the fixed asset which is/are managed according to the
standards of a tangible fixed asset.
Article 13 lists the various available methods of depreciation of fixed assets:
1. Straight line method;
2. Declining balance method; and
3. Units-of-production depreciation method.
Based on the ability to meet the conditions stipulated for each fixed asset depreciation method, enterprises are
allowed to select depreciation methods suitable for each kind of its fixed assets.
Straight line method: Fixed assets engaged in business activities may be depreciated according to the
straight line method.
Enterprises operating and gaining high economic efficiency are allowed to conduct rapid depreciation of their
fixed assets in order to quickly renew technologies. Fixed assets engaged in business activities and eligible for
rapid depreciation include machinery, equipment; measuring and experimental instruments: equipment and
means of transport; tools used for management: and working animals and gardens of perennial trees. When
conducting rapid depreciation, enterprises shall ensure that they get profits in their business. In case enterprise
conduct rapid depreciation over two times the prescribed frame of use life of fixed assets provided in Appendix
I to this Circular, the depreciation cost exceeding the rapid depreciation level (over two times) may not be
included in their reasonable expenses upon calculating enterprise income tax of the period.
Appendix I of the regulation presents the schedule of useful life of all asset categories, where on an average it
varies between 8-12 years.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 428
Relevant to public relations
Decision No. 1208/QD-TTg dated 21 July 2010
The objective of the plan is to develop the roadmap for power sector in conformity with the national socio-
economic development strategy, ensuring adequate supply of electricity for the national economy and social
life. The National Master Plan is focused on the following development viewpoints:
1. To develop the electricity sector in conformity with the national socio-economic development
strategy, ensuring adequate supply of electricity for the national economy and social life;
2. To effectively utilize domestic energy resources for electricity development in combination with the
rational import of electricity and fuel, diversification of primary energy sources for electricity
production, conservation of fuel and energy security for the future;
3. To incrementally improve the quality of electricity supplied to consumers of Vietnam;
4. To apply market mechanism for electricity sale prices with a view to encourage investment in the
development of the electricity sector;
5. To encourage electricity conservation;
6. To develop the power sector along with protecting natural resources and the eco-environment, and
ensuring national sustainable development;
7. To gradually create and develop a competitive electricity market, diversifying the modes of
investment and trading in power sector;
8. To preserve the monopoly of the state in the power transmission grid in order to ensure security of
the national energy system;
9. To develop the power sector on the basis of the rational and efficient use of primary energy
resources of each region; and
10. To further step up rural electrification and ensure adequate, uninterrupted and the safe supply of
electricity in all regions nationwide.
The National Master Plan addresses the various topics of interest to the industry sector. Since the government
is the decision maker with regards to EVN and EVNNPT, it would be a good idea to examine the government’s
agenda - as mentioned in the National Master Plan - from the perspective of EVN’s and EVNNPT’s
communications plans. Listed below are some of the initiatives that are relevant for it:
1. Focus on the overall power generation of the country with an efficient use of the domestic energy
resources in combination with the import of primary energy;
2. Giving priority to sustainable energy sources, including renewable energy sources for power
production;
3. Focus on rural electrification;
4. Stress on developing and strengthening regional power centres nationwide, ensuring reliable power
supply on site;
5. Focus on technology and innovation in the transmission sector;
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 429
6. Laying underground electricity grids incrementally in cities and towns to limit the impact on the
landscape and environment;
7. Reduction of electricity losses and building smart grids;
8. Interest in attracting foreign direct investment (FDI) in developing electricity projects.
Law No. 13/2003/QH11 dated 29 November 2013
The land law prescribes land management and use. The State is clearly defined as the sole owner of the land. As
such, it is described as having the right to recover and re-possess land as and when required to further the
larger public good. Below are some major highlights of the law:
Salient features
1. The State leases land in exchange of annual land rents from households and individuals. They rent
land for agricultural production, forestry, aquaculture, salt making etc.;
2. The State has the right to take back the land for the purposes of defence, security, national interest,
public interest and economic development;
3. The State will pay compensation, as decided by the Provincial/municipal People's Committees, and
sometimes open for bidding or as agreed between State and the lessee;
4. The state will notify at least 90 days before land recovery for agricultural land, and 180 days for
non-agricultural land;
5. Also, the state shall notify the person the reasons for recovery, time and plan for evacuation, the
overall schemes for compensations, ground clearance and resettlement;
6. In instances where people refuse to provide the land, the State will use coercive ways to recover the
land;
7. If there are no resettlement zones planned, the persons whose land is recovered will receive
compensation to purchase or lease residential areas under the State's ownership;
8. For safety protection corridors: If the land use affects the safety protection of works, the works
owners and land users will apply remedial measures; if remedies cannot be achieved, the State shall
recover the land and pay compensations according to the provisions of law.
Summary
1. The State clearly defines itself to be the sole owner of the land where it gives land use rights to the
citizens of Vietnam and withdraws the land for a greater purpose like development;
2. The State will communicate such an order giving notice of at least 90 days for agricultural land and
180 days for non-agricultural land along with the reason for the withdrawal along with the
compensation that will be provided and the resettlement policy.
Decree No. 15/2013/ND-CP dated 6 February 2013
This Decree provides regulations on the quality management of construction works in survey, design,
construction execution and acceptance of construction works; on safety management, handling of incidents
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 430
during construction execution, exploitation and use of construction works; and on warranty of construction
works. Listed below are the major points:
Salient features
1. The investing company has to undertake responsibilities for organizing the quality management in
the implementation process of works construction investment projects;
2. All construction activities should comply with the National technical codes;
3. In case the investing company is following an international standard, those have to be translated
into Vietnamese and ratified by the authority;
4. Construction survey has to be undertaken in compliance with the construction survey technical
plans;
5. The survey reports have to be prepared so that they satisfy requirements of survey tasks and
contracts;
6. The survey will validate if the quality of construction materials, products, equipment and
components is in accordance with the applied standards and national technical codes in
correspondence and the requirements of design;
7. Investors have to design dossiers with design tasks, basic designs, conditions of construction
contracts, and relevant regulations of the law and send them to competent authorities for
verification;
8. Investors have to provide the contractual party with sufficient information and documents related
to products and goods as stipulated by the regulations on the quality of products and goods and
other relevant regulations; follow the regulations on labels of products and goods;
9. Organizational structure and supervision work plan including the responsibilities, powers, tasks for
all positions of supervision, the quality control plan and procedure, the inspection and acceptance
procedure and the management of related documents and materials will also be prepared by the
investors;
10. Labourers involved in construction execution at sites must be eligible, healthy, trained on safety
and allocated adequate safety equipment as stipulated by regulations on labour safety;
11. Preparation and archives of completion dossiers of completed items, construction works by the
investor;
12. Stakeholders are responsible to hold negotiation for solutions in case of any disputes over the
quality of construction works;
13. Reporting of incidents should be immediate. Investors must briefly report to communal level
People’s Committees and Investors’ senior agencies within 24 hours after the incidents have
occurred;
14. Reporting of incidents:
a. For all types of incidents, if humans are hurt, Investors must also report to the Ministry of
Construction and other competent State authorities as stipulated in the relevant
regulations;
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 431
b. After the receipt of reports in writing or of information about the incidents, Provincial
People’s Committees are responsible for sending the reports on incidents to the Ministry of
Construction and Ministries managing specialized construction works in cases of incidents
of particularly serious level, and other incidents causing the loss of human life;
c. Involved parties must take photos, shoot films, collect evidences and take notes of incident
scenes in service of the State inspection of incident causes and preparation of incident
dossiers before dismantling and clearing incident scenes; and
d. Investors, owners or use managers of works shall take responsibilities for compiling
dossiers of incidents with contents.
Summary
1. National codes are of utmost importance and international quality codes has to be ratified by local
authorities;
2. A construction survey has to be undertaken to check if the work has complied with the technical
plans and has to be reported in accordance with the applied standards and national technical codes;
3. Investors have to design dossiers with design tasks, basic designs, conditions of construction
contracts, and relevant regulations of the law and send them to competent authorities for
verification; and
4. A special emphasis is laid for crisis communication. In case of an incident during construction, the
developer has to also report to the Ministry of Construction and other competent State authorities
in writing. They also need to click photos, shoot films, collect evidences and take notes of incident
scenes in service of the State inspection of incident causes and preparation of incident dossiers
before dismantling and clearing incident scenes.
NPT Regulation on Propaganda (communication), 2011
This regulation, issued by EVNNPT, describes in detail the communication responsibilities of EVNNPT. This is
keeping in view the current laws. This regulation is to be applied comprehensively in EVNNPT (head office and
subsidiaries).
Salient features
1. Vice Presidents, Deputy Directors of various departments, Managers of departments and Directors
of EVNNPT’s subsidiaries shall be responsible for implementing this regulation;
2. The regulation shall be applied comprehensively to EVNNPT head office and its subsidiaries;
3. In addition, this regulation outlines all of EVNNPT’s communication tools including power
transmission news, EVNNPT’s website, and mass media;
4. The regulation also outlines the communication put in place by EVNNPT so as to proactively create
an information channel with partners, consumers of EVNNPT and social community;
5. The aim is to create consistency in communication, messaging and information for the press:
6. The regulation governs all content for communication including (but not limited to):
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 432
a. Policies;
b. Guidelines relating to power activity;
c. Information on management and operation and construction investment activities of
EVNNPT and EVN;
d. Information on the implementation status of various projects;
e. Brand and image for social opinions, locals and partners;
f. EVN’s culture;
g. NPT and its subsidiaries’ behaviour rules;
h. Provide introduction of functions, tasks, model, organizational structure, and operation
activities;
i. Tradition, competition and operation;
j. Information on science-technology, environment, labour safety and sanitation;
k. Initiatives for technical innovation;
l. Operation rationalization with practical efficiency in EVNNPT and its subsidiaries’
business and operation;
7. The regulation defines the spokesperson for the various departments and subsidiaries;
8. There is also clear indication for the need for trained personnel for the communication function;
and
9. The regulation also mentions the need for “spokesperson and information supply in ad-hoc cases”
which implies the need for crisis communication and/or issue based communication.
Summary
1. Though the regulation clearly indicates the need for consistency in communication across all
mediums, there is no clear messaging developed along with the plans that clearly lay out the talk
points for EVNNPT and its various subordinate units and subsidiaries;
2. The regulation outlines the need for professionally trained staff which at present is lacking within
the system; and
3. There is mention of “spokesperson and information supply in ad-hoc cases” which appears to imply
issue based communication / crisis communication. However, there does not appear to be any
communication plan in place focused at anticipating issues/issue management and/or crisis
communication.
Decision No. 1428/QD-EVNNPT and amendment
This document lays out the functions and responsibilities of the various departments of EVNNPT.
In the table below, we have highlighted the functions of those departments whose work relates to
communication activities alongside the stakeholders that are being engaged with by that department.
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 433
Department Communication aspect of the function & responsibility
Stakeholders being engaged by the department
Administration Department
Consult to help EVNNPT’s leaders to direct, manage administration, reception, document filing, propaganda, public relations, traditional customs of EVNNPT; health care of EVNNPT. Help EVNNPT’s leaders to supervise and speed up functional departments and other units to implement assigned tasks.
Employees of EVNNPT
All stakeholders as this
department functions as
communications & PR
department of EVNNPT. These
include media, local
authorities, and affected people
in project areas
Corporate Planning Department
Consult to help EVNNPT’s leaders to direct, manage plan tasks; contract of transmission service supply and related works; transmission pricing and charging; statistic and analysis of business and operation and construction investment activities, undertake supervision, assessment of overall investment of EVNNPT.
Ministry of Industrial and
Trade
EVN
Other departments of EVNNPT
Financial investors
Business partners
Technical Department
Consult to help EVNNPT’s leaders to direct, manage operation management, technical management of transmission network, research and technical-technology-scientific breakthroughs, standardization, quality and environment management (in the field of operation management); technical safety and labour safety.
Domestic and international
technical partners
Officials looking at technical &
labour safety
Power transmission sector in
and outside Vietnam
Regulators of environmental
norms
Investment Management Department
Consult to help EVNNPT’s leaders to instruct, manage projects in the stage of investment preparation and investment implementation as delegation (approval of feasibility study, technical design-estimation) including:
Manage project implementation progress in
the above mentioned stage
Review, submit for approval of documents
related to feasibility study, technical design-
estimation
Management of construction investment
cost of EVNNPT
Departments of Corporate
Planning, Technical,
Information Technology,
International Cooperation,
Material, Construction
Management
Construction Management Department
Consult to help EVNNPT’s leaders to direct, operate construction progress, quality management, construction and erection contract management of construction investment projects and big repairs from the stage of construction preparation until completion and put into use and land acquisition compensation; Mange environment in construction investment field.
Departments of Corporate
Planning, Investment
Management, International
Cooperation, F&A,
Procurement, Material
Appointed and bidding
contractors
Regulators of environment
norms
Labour
Local authorities
People at project sites
Inspection Department
Consult to help EVNNPT’s leaders to manage direct, control inspection tasks; Settle claim,
Anti-corruption authorities
Summary of laws / decisions / decrees / circulars
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 434
Department Communication aspect of the function & responsibility
Stakeholders being engaged by the department
denouncement; anti-corruption, security, protection of the government, EVN, EVNNPT secrets; national defence.
Government legal authorities
Local authorities
People at project sites
Legal Department Consult the Management Board to manage and oversee activities of management of the implementation of legal regulations in EVNNPT, any legal issues related to its operations and protection of EVNNPT’s interests.
Government regulators
Corporate planning
department
International Cooperation Department
Consult the Management Board to manage and oversee activities of arranging foreign funding sources and ODA funding, multilateral or bilateral funding sources and international cooperation and foreign relations development of EVNNPT.
Departments of Corporate
Planning, Finance &
Accounting, Investment
Management, Construction
Management, Technical and
Procurement
Visa and Passport authorities
Foreign business partners
Foreign consultants
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 435
Appendix 6 - Detailed process charts for investment planning
Process Chart 1: First stage approval
Power Transmission Company
identifies the need of new transmission
system (line / sub-station / reactive
compensation etc.) based on own need (e.g.
reduce overloading) or based on inputs
received from Discom(s)
PTC prepares the investment proposal and
sends it to IMD after seeking approval of the
Director of the PTC
After taking inputs of the Technical
Department, IMD forwards the investment
proposal to VP (Operation & Investment)
Review and approval by VP (Operation &
Investment)
Review and approval by President & CEO
Review by Management Board
Whether the project is technically
feasible?
Submitted to MoIT for firs stage appoval
YES
Disapprove (NO-GO)
OR Ask for more information
NO
IMD issues the decision of first stage
approval to respective departments
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 436
Process Chart 2: Approval of FS
National Master Plan
(Current Plan VII: 2011-20)
Based on National Master Plan, NPT prepares Five-year Transmission Plan and
Annual Detailed Plan (both these plans are revised annually)
Based on the decision of the President & CEO, the
respective PPMB/PTC will initiate the project
PTC/ PPMB hires an external consultants to prepare a
Feasibility Study (FS)
Whether FS meets the
prescribed criteria? FS is submitted to IMD
PTC/PPMB seeks
additional
information
Yes
No
Review of the FS by IMD
Review of Technical
feasibilityCost estimation and
Financial Analysis
Review of design
and technical
parameters by IMD
Telecommunicati
on and IT review
by IT deptt
Review in respect of
O&M and fire
protection by
Technical Deptt etc.
Review of fund
requirement & project
planning by Corporate
Planning Department
Review of financial
& economical
analysis and cost
estimation by IMD
C
After the approval of the Annual Detailed Plan, President & CEO will decide that who will execute the
project depending on the location of the project and work load of each PPMB/ PTC. President & CEO
may decide to hold or stop the project
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 437
All the comments and review report will be compiled by the IMD
Reviewed proposal to
be submitted to
Management Board
FS will be submitted to MoIT
If not approved, it will go
back to IMD who will make
the suggested amendments
in the proposal through
meetings and consultative
process with various
departments
After the approval of MoIT, it will go to IMD for
issuance of Implementation Decision
C
IMD will issue the Implementation Decision to all
the concerned departments
Project is ODA or
domestic funded?
Project cost < 1500
billion VND
NPT
management
can approve
ODA funded
Ye
s
If project c
ost >= 1500 billio
n VND
Project cost < 1500
billion VND Domestic funded
In case the project is funded by domestic sources and project cost is < 800 billion VND,
President & CEO can decide otherwise it will be submitted to the Management Board
NPT
Management
Board can
approve
Ye
s
If project cost >= 1500 billion VND
NPT
Management
Board can
approve
Ye
s
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 438
Process Chart 3: Approval of DTD
After the issuance of Implementation Decision by IMD,
the PPMB/ PTC will prepare the Detail Technical Design
(DTD)
Review of the DTD by IMD
IMD will consult with all the relevant departments
After consulting with all the relevant departments, the
IMD will submit the DTD to President & CEO
President & CEO will submit the DTD to MoIT
After the comment from independent consultant, MoIT
will approve the DTD
MoIT will hire an independent consultant to review the
DTD
MoIT will send the approved DTD to President & CEO
President & CEO will issue a Implementation Decision
in respect of approval of DTD
In c
ase
the
ind
ep
en
de
nt c
on
su
ltan
t ha
s a
ny c
om
me
nts
, it will g
o b
ack to
NP
T fo
r am
en
dm
en
t/ mo
dific
atio
n
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 439
Process Chart 4: Process for procuring loans from DCB
For the investment projects, which are approved by the CPD and funds not identified for the project, F&A
Department is responsible to procure domestic loans
F&A Department will seek offers from the domestic banks
The domestic banks will submit their offers to F&A Department
F&A Department will negotiate the terms & conditions of offer with the domestic bank
After agreeing upon the rates of interest and other terms & conditions of the offered loan, F&A
Department will submit the loan proposal to President & CEO for approval
If loan amount >= 500 billion VND
YesNo
Approval of Management Board
neededApproval of President & CEO needed
After getting the approval of the Management Board of NPT or President & CEO, F&A Department may
sign loan agreement with the domestic bank
After signing the loan agreement, the disbursement function is delegated to the PPMB/ PTC
PPMB/ PTC will withdraw the fund as per the loan agreement
The obligation for interest and repayment of loan will be on F&A Department of NPT
During the process, F&A Department will have to submit the details to the bank in respect of economic
efficiency of the project such cash flow, NPV, loan repayment capacity, etc.
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 440
Process Chart 5: Process for procuring loans from OICB
Decision of CPD in respect of procuring loan for the investment project from Other International Commercial
Bank (OICB)
F&A Department will take offers from OICB based on the decision of CPD
F&A Department negotiate with OICB in respect of interest rates and other terms & conditions of loan
Based on the negotiation, the OICB will revise the offer
F&A Department will submit the negotiated offer to President & CEO for approval
NPT hires external consultant to prepare a
document (as per decree 15 and a circular
issued for providing format for applying for
guarantee). It is supported by details of
economic efficiency, benefits from projects,
capacity to repay loan etc.
MoF will issue the gaurantee
Based on negotiation, NPT will sign the loan agreement with OICB
President & CEO submits he offer to the Management Board for approval
Management Board submits an official letter and negotiated offer letter to EVN
EVN will issue its consent to loan proposal and submit it to MoIT for its approval
In parallel to the submission to MoIT by
EVN, NPT will apply to MoF for guarantee
After the issuance of consent letter by EVN (pending
approval of MoIT), the OICB will send the draft loan
agreement (DLA)
By this time, MOIT provides its approval to the proposal
submitted by EVN
MOIT submits the proposal to Ministry of Finance (MoF)
and Ministry of Justice (MoJ).
Based on the DLA, MoIT, MoF and MoJ will negotiate the
DLA. By this time, the report on Environment & Social
Impact Assessment must have approved by MoNR&E
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 441
Process Chart 6: Process for procuring loans from ODA
ICD discusses with ODAs to finalize terms & conditions for project selection
ICD reports NPT’s leaders regarding the amount, criteria for project selection based on which the CPD to
make a list based on the identified criteria
CPD submits the proposed list for consideration and approval to President & CEO
President & CEO submit the list of project to NPT’s Management Board for approval
After the approval of the Management Board, ICD prepares project outline (PO) for the approved projects
as per the regulation of Decree 38
The final version of PO is submitted to MPI (Ministry of Planning & Investment) for its approval- MPI
reviews the PO
NPT submits the PO to EVN for approval with a written request
After review and approval by EVN, it is submitted to MoIT for approval
After the approval of EVN, the PO request is submitted to MoIT for approval
MoIT reviews the PO
C
Any questions/
clarification?If yes, the NPT/EVN has to clarify and modify the PO
No
MPI sends the PO for comments from related ministries (MOF, MOFA, MOJ, SBV) and collects all the
comments and consolidate
Any questions/
clarification?If yes, the NPT/EVN has to clarify and modify the PO
PO is submitted to PM for approval
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 442
EVN reviews the project document and submits to MoIT for review and approval
MoIT, after its review, submits the project document to Ministry of Planning and Investment (MoPI),
Ministry of Finance (MoF) and Ministry of Justice (MoJ) for seeking their comments
Approval of the project document by MoPI, MoF and MoJ
After approval of PO from President, the NPT is required to prepare the project document. It is prepared
by PPMB and other concerned departments - CMD, ICD, IMD, F&A, etc. It is consolidated by ICD
The project document must contain the report on Environment Impact Assessment approved by Ministry
of Natural Resource & Environment, project details with project objective and its economic efficiency
NPT submits the project document to EVN
C
Any questions?If yes, the NPT has to clarify and modify the project document
C
Prime Minister submits it to President for approval
President approves the PO
After approval of project documents by various ministries, ODA will initiate the pre-evaluation of project
document
Depending on the loan source (BL/ML), SBV or MOF will submit its recommendation for establishment of negotiation team to the Prime Minister
Negotiation team will be formed by the PM
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 443
After the approval of PM,, MoF will sign loan agreement with ODA
After signing of loan agreement, the disbursement plan will be validated by MoF
MoF will sign the loan disbursement form as a part of approval
After the signing of loan withdrawl form, NPT can withdraw the fund
The loan agreement needs to be registered with SBV
MoF will appoint an On-Lending Agency (such as EVN Finance Corporation / any other commercial
bank) to monitor the loan disbursement and verify the expenses to get disbursements
NPT has to submit disbursement withdrawal form (as per the Circular no 86 of 2011on ODA loan
management) to On-Lending Agency
On-Lending Agency will escalate the loan withdrawal form to MoF for approval
C
Negotiation team generally comprises of MoF, MoIT and State Bank of Vietnam (SBV). The team
negotiate jointly with the funding agency/ donor
The results of negotiation are to be submitted to PM for approval
Detailed process charts for investment planning
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 444
After approval of project documents by various ministries, ODA will initiate the pre-evaluation of project
document
After pre-evaluation by ODA, NPT will initiate negotiation. Negotiation will be jointly done by MoF, MoIT
and State Bank of Vietnam (SBV)
After the completion of negotiation, MoF will sign loan agreement with ODA
After signing of loan agreement, the disbursement plan will be validated by MoF
MoF will sign the loan disbursement form as a part of approval
After the signing of loan withdrawl form, NPT can withdraw the fund
The loan agreement needs to be registered with SBV
MoF will appoint an On-Lending Agency (such as EVN Finance Corporation / any other commercial
bank) to monitor the loan disbursement and verify the expenses to get disbursements
NPT has to submit disbursement withdrawal form (as per the Circular no 86 of 2011on ODA loan
management) to On-Lending Agency
On-Lending Agency will escalate the loan withdrawal form to MoF for approval
C
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 445
Appendix 7 - MoU signed between ADB and EVNNPT
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 446
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 447
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 448
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 449
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 450
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 451
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 452
MoU signed between ADB and EVNNPT
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 453
Project level and corporate level financial model for EVNNPT (IP Reco#5)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 454
Appendix 8 - Project level and corporate level financial model for EVNNPT (IP Reco#5)
Training on principles of regulatory economics and international practices (TP Reco#1)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 455
Appendix 9 - Training on principles of regulatory economics and international practices (TP Reco#1)
Integrated transmission pricing model (TPM) (TP Reco#3)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 456
Appendix 10 - Integrated transmission pricing model (TPM) (TP Reco#3)
Training to EVNNPT spokespersons on media handling skills (PR Reco#6)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 457
Appendix 11 - Training to EVNNPT spokespersons on media handling skills (PR Reco#6)
Workshop on the fundamentals of effective public relations (PR Reco#7)
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 458
Appendix 12 - Workshop on the fundamentals of effective public relations (PR Reco#7)
EVNNPT feedback on three workshops / trainings on public relations
Private and Confidential
TA-7668 VIE: Increasing the Efficiency of the National Power Transmission Corporation through Targeted Capacity Building (44004-012) - Final Report
PwC 459
Appendix 13 - EVNNPT feedback on three workshops / trainings on public relations
1. Mr. Tran Quoc Lam (Vice President, EVNNPT): “The Media Handling Skill workshop is really useful
for my work. I appreciate what the consultants shared with us.”
2. Mr. Tran Minh Tuan (Vice Director, PTC1): “The workshop is helpful especially the hand-outs with
short and simple tips.”
3. Mr. Tran Minh Tuan (Vice Director, PTC1): “The Effective PR workshop is a good chance for both
leaders and executives as we can understand more the importance of PR/communication and support
each other in work.”
4. Mr. Nguyen Manh Hung (Expert, PTC1): “I’ve learnt a lot from the Effective PR workshop and the
knowledge that we shared is useful for my current job as a communication executive. The workshop
provided me with framework that would help me plan and implement communication work more
logically.”
5. Mr. Bui Duy Hung (Director, Admin Department, EVNNPT): “As the head of Admin Department and is
in-charge of communication work I find the workshop is necessary and important. The workshop
provided us a structure that we can apply in our communication work professionally.”
6. Mr. Le Xuan Hoan (Expert, Admin Department, EVNNPT): “I’m in charge of communication work at
EVNNPT but I’m not professionally trained so I often implement communication activities based on
my experience. The workshop helps me with structure and framework to better my work.”
Insert Header Field
Private and Confidential
© 2014 PricewaterhouseCoopers India Private Limited. All rights reserved. In this document, “PwC” refers to PricewaterhouseCoopers India Private Limited, which is a member firm of PricewaterhouseCoopers International Limited, each member firm of which is a separate legal entity.
PwC 460
Building relationships
Creating value