tech tidbits-3 mud delivery

2
Tech Tidbits, vol. 3 Evaluating bid tenders includes verification that the equipment bid will be able to complete the drilling program specified, i.e. well depth, lengths of each casing string, specified mud delivery and conditioning, etc. However, sometimes the capabilities as identified by manufacturer and model number may not reflect the operating capacities as installed. The following are two case studies to illustrate this situation. 1. Mud delivery Specifications in the inquiry required 1,000 gpm at 4,500 psi. The contractor equipment list showed two mud pumps which the vendor data sheets show as capable of delivering approximately 430 gpm at 4,670 psi each. No problem, right? After contracting the rig, during acceptance it was discovered these mud pumps were fitted with 1,000 hp motors. In order to deliver the nameplate specifications, a 1,600 hp driver is required. The contractor replaced the installed motors with larger ones capable of delivering the mud needed for the program. Recognizing this as part of the acceptance allowed execution of the drilling program as designed. There are several reasons why this "mismatch" could have occurred. 1. Some contractors choose to install lower horsepower electric motors than the maximum input power rating for a specific mud pump if the anticipated service conditions will permit (e.g. high circulation rate, low standpipe pressure), thus saving the incremental cost of the more powerful motor. 2. Another reason for the lower horsepower drivers could be improved pump service life (increased engineering factor of safety). 3. In certain cases, equipment availability may be an issue, and lower powered motors are selected simply to more expeditiously get back to work. Once installed, they remain in service until the next replacement cycle. 2. Hoisting and braking

Upload: wholenumber

Post on 12-Nov-2015

212 views

Category:

Documents


0 download

DESCRIPTION

Evaluating bid tenders includes verification that the equipment bid will be able to complete the drilling program specified, i.e. well depth, lengths of each casing string, specified mud delivery and conditioning, etc. However, sometimes the capabilities as identified by manufacturer and model number may not reflect the operating capacities as installed. The following are two case studies to illustrate this situation.

TRANSCRIPT

  • Tech Tidbits, vol. 3

    Evaluating bid tenders includes verification that the equipment bid will be able to complete the drilling

    program specified, i.e. well depth, lengths of each casing string, specified mud delivery and

    conditioning, etc. However, sometimes the capabilities as identified by manufacturer and model

    number may not reflect the operating capacities as installed. The following are two case studies to

    illustrate this situation.

    1. Mud delivery

    Specifications in the inquiry required 1,000 gpm at 4,500 psi. The

    contractor equipment list showed two mud pumps which the vendor data sheets show as capable of

    delivering approximately 430 gpm at 4,670 psi each. No problem, right?

    After contracting the rig, during acceptance it was discovered these mud pumps were fitted with 1,000

    hp motors. In order to deliver the nameplate specifications, a 1,600 hp driver is required. The

    contractor replaced the installed motors with larger ones capable of delivering the mud needed for the

    program. Recognizing this as part of the acceptance allowed execution of the drilling program as

    designed.

    There are several reasons why this "mismatch" could have occurred.

    1. Some contractors choose to install lower horsepower electric motors than the maximum input

    power rating for a specific mud pump if the anticipated service conditions will permit (e.g. high

    circulation rate, low standpipe pressure), thus saving the incremental cost of the more

    powerful motor.

    2. Another reason for the lower horsepower drivers could be improved pump service life

    (increased engineering factor of safety).

    3. In certain cases, equipment availability may be an issue, and lower powered motors are

    selected simply to more expeditiously get back to work. Once installed, they remain in service

    until the next replacement cycle.

    2. Hoisting and braking

  • Acceptance of one rig resulted in recognizing that the eddy

    current brake recommended by the drawworks manufacturer was not installed, but one of a lower

    capacity. Discussions with both the drawworks and eddy current brake manufacturers suggested the

    possibility that the braking capacity was adequate, but only if the controls were configured and

    installed to utilize the drawworks motors as regenerative brakes. The rig could not confirm the

    controls configuration.

    A drawworks braking capacity test was designed and conducted, confirming sufficiency of this capacity

    as installed.

    Both cases illustrate the importance of careful assessment and acceptance of rig equipment to ensure

    performance requirements will be achieved. Procedures that do not require checking the matching of

    system components could result in hiring a rig that is not suitable for the program you have designed.