team steady supply

21
TEAM STEADY SUPPLY ERIC VANDENBURG, SPENCER HOMAN, TREVOR LARSON and NIK URLAUB Team website: http://seniordesign.engr.uidaho.edu/2010-2011/microgrid/ 1

Upload: lynsey

Post on 23-Feb-2016

34 views

Category:

Documents


0 download

DESCRIPTION

ERIC VANDENBURG, SPENCER HOMAN, TREVOR LARSON and NIK URLAUB Team website: http://seniordesign.engr.uidaho.edu/2010-2011/microgrid /. TEAM STEADY SUPPLY. Table of contents:. Background Problem Definition Uninterruptible Power Supply (UPS) Current Design Design specifications - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: TEAM STEADY SUPPLY

1

TEAM STEADY SUPPLY

ERIC VANDENBURG, SPENCER HOMAN, TREVOR LARSON and NIK URLAUB

Team website: http://seniordesign.engr.uidaho.edu/2010-2011/microgrid/

Page 2: TEAM STEADY SUPPLY

2

Table of contents: Background Problem Definition Uninterruptible Power Supply (UPS) Current Design Design specifications Load information Proposed Design # 1 Constraints Proposed Design # 2 Ideas Design Tradeoffs Budget Schedule

Page 3: TEAM STEADY SUPPLY

3

Background: Advanced Electric Ship Demonstrator (AESD)

also known as “Sea Jet” 1/4 scale model, Length: 133 feet, Weight:

239,000 lbs, Location: Bayview, Idaho AESD is used for a variety of different tests and

experiments (eg. Acoustic data collection, Hull modification, Motor types)

Propulsion System is powered by 720 12V@40A/Hr Batteries

Auxiliary System is powered by 4 UPS Shore power, Diesel Engine used for charging

Page 4: TEAM STEADY SUPPLY

4

Problem Definition: This is a Feasibility Study with the following

objectives: Replace the Four Uninterrupted Power Supplies

(UPS) Provide Uninterrupted Power Flow to Every Auxiliary

Load. Increase the Duration of Battery Run Time (Increase

Quiet Mode Run time) Decrease Charge Time for Batteries (Decrease Time Between Quiet Mode Runs) Decrease Acoustic Contamination

Page 5: TEAM STEADY SUPPLY

5

What is an uninterruptible power supply (UPS):

PROSUPS provide a Load with power at all timesDuring connection to Shore/Diesel Generator, Load is powered and battery is charging.During Quiet Mode Runs the Battery supplies the Load with power

CONS UPS are not designed to run on the internal batteries for extended timeUPS are not designed to charge quickly UPS are not designed to minimize acoustics (Inverters)

4 UPS = 4 Inverters = Loud

SHORT QUIET MODE RUNS

LONG CHARGE TIME

ACOUSTIC CONTAMINATION

Page 6: TEAM STEADY SUPPLY

6

Current Design:

Page 7: TEAM STEADY SUPPLY

7

Design specifications: Remove the (4) uninterruptible power supplies

(UPS) causing unwanted acoustics. Continuous power supply to the loads at all times. Draw power from a common bus. Batteries capable of providing power for more than

45 minutes.

Page 8: TEAM STEADY SUPPLY

8

Design process: Brainstormed/researched DC microgrids Obtained load profiles from NAVSEA Calculated power consumed by the

auxiliary power system Determined the number of batteries

needed

Page 9: TEAM STEADY SUPPLY

9

Load information:With Onboard Data Acquisition System (ODAS) equipment off:• UPS #1 – 6.0A• UPS #2 – 13.9A• UPS #3 – 2.0A• UPS #4 – 3.3AWith ODAS equipment on:• UPS #1 – 17.4A• UPS #2 – 18.5A• UPS #3 – 7.3A• UPS #4 – 3.3AUPS #4 has weak batteries causing ODAS configuration not

to be utilized for this unit.

Page 10: TEAM STEADY SUPPLY

10

Design Schematic# 1

Page 11: TEAM STEADY SUPPLY

11

Design Schematic # 1

Page 12: TEAM STEADY SUPPLY

12

Design #1 Calculations

Page 13: TEAM STEADY SUPPLY

13

Design Schematic # 2Auxiliary System ties into Propulsion System

Auxiliary load is roughly a 12% increase to the connecting string

Vital Loads have power at all times

Looking into DC switchboards to connect to multiple strings to divide load

Page 14: TEAM STEADY SUPPLY

14

Design #2 Calculations

Page 15: TEAM STEADY SUPPLY

15

Constraints: Space: Current UPS dimensions

approximately 4*(4ft. by 2ft. by 2ft.). Battery dimensions approximately 24*(12 in. by 6 in. by 4 in.) SPACE not a problem.

Cost: Design #2 will be cheaper based on less materials and components.

Page 16: TEAM STEADY SUPPLY

16

Options Considered Current Lead-Acid Batteries (12V @

40A/Hr) Lithium-Ion Batteries (36.8V @ 50A/Hr) Fuel cells (not feasible)

• Size needed for storage• cost

Back up battery bank for Design # 2 Types of Inverters, most cost effective and

easy to implement

Page 17: TEAM STEADY SUPPLY

17

Design Tradeoffs

Page 18: TEAM STEADY SUPPLY

18

Project Learning Gained knowledge of DC microgrids A better understanding of one-line

diagrams Basic battery bank design Site visit

The operations and uses of the AESD

Page 19: TEAM STEADY SUPPLY

19

Budget: Site Visit: $70.00 Expo Poster: $20.00 Total: $90.00

Page 20: TEAM STEADY SUPPLY

20

Schedule: Start of Semester: January 10, 2011 Detailed Design Review: February 15,2011 Snapshot Day: March 8, 2011 Expo: April 29, 2011 Logbooks Due: May 5, 2011 Final Report: May 5, 2011

Page 21: TEAM STEADY SUPPLY

21

Questions: