team no. 43 ove the bridge - smooth the line
DESCRIPTION
Team No. 43 Ove the Bridge - Smooth the LineTRANSCRIPT
A simple arch structure, easy to build using
the maximum of locally sourced materials.
The bridge will provide access across the river
for foot traffic, bicycles and animals. The
bridge can be constructed at minimal cost, in
a short period of time by low levels of un-
skilled labour. It is a harmonious solutionskilled labour. It is a harmonious solution
that fits in with the local landscape, culture
and environment.
Bridge Deck Support
Saddle Detail 1Bridge Deck Support
Saddle Detail 2
Pedestrians,
cyclists
or
animals
Cables for stabilizing the
bridge deck..
The bridge is principally
composed of bamboo, using
rapidly renewable material
which can be locally sourced.
The bamboo must be dried
and treated with a
preservative solution to
provide a long structural
service life. The use of low
Materials & Labour Requirements (Estimated)
Main Structure Bamboo 300M linear
Woven bamboo for decking 700M linear
Steel Cables 130M linear
Steel Saddles 70 No.
150mm Diameter Steel Pipe 8M
Natural Twine/Rope for handrail 130m
Concrete pad abutments with cast-in steel
tubes to accept bamboo girders.
Connections to be grouted after insertion.
service life. The use of low
carbon materials may also
provide scope for embedded
carbon offsetting, credits for
which could be sold to
finance construction
Natural Twine/Rope for handrail 130m
Mortar 100kg(dry)
Concrete abutments 6M3
Aggregate Locally sourced
Bamboo Reinforcement for
abutments 20M Linear
Labourers (peak) 40 Persons
Construction Duration 4 Weeks
4 51
2
6 7
Plan showing old and
new bridges.
Section showing bridge deck.
Scale: 1:25 at A3
3
Notes about
the section:
8
Detail: Bamboo weave
is added after stage 6 to
create deck.
the section:
Width of the
deck is about
1.6m wide.
Headroom is
estimated to
be 2m.
Construction sequence:
1 & 2 – Arches
Connect bamboo to bamboo by steel bar and seal with
mortar. Jointed bamboo poles are stacked in layers with
pinning bolts. Pinned segments are filled with mortar tocreate deck. pinning bolts. Pinned segments are filled with mortar to
enhance compressive strength. Arches are formed to a
curve to create bridge shape.
3 – Dead-End Blocks & Abutments
Prepare bricks from local mud and sand. Stack the
bricks to form the formwork of the concrete dead-ends.
Insert steel pipe to accept bridge arches.
Masnory retaining wall to improve the abutments
stability and durability if necessary.
4 – Erection of arches
Prepare bamboo scaffoldings for the erection. Position
the arches within the abutment pipes. Grout joints with
mortar.
5 & 6 – Bracings and cables
Section showing new bridge and old bridge. The old bridge keeps its function
during the erection of the new bridge. The new bridge is higher than the old
bridge deck to reduce the risk of flood damage. Bamboo reinforced concrete
abutments are used to anchor and support the arch structure. A gravity retaining
wall is considered to cope with the steep nature slope and the additional loading
from the concrete block foundation of the bridge.
Sources: Based on example bridges by Jorg
Stamm and the IT Transport/DFID publication:
“Footbridges: A manual for Construction at
Community and District Level”
5 & 6 – Bracings and cables
Install bamboo bracing and then cable from the arches
down to the deck of the bridge.
7 & 8 – Deck and railing
Tie the bamboo weave to edges of bamboo deck rails
with ropes. Install the stabilizing cables.
Scale: 1:250 at A3