TCUSD New K-5 Construction
PROJECT UPDATENOVEMBER 4, 2015
1
![Page 2: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/2.jpg)
TCUSD New K-5 Construction
• PROJECT PROCESS• CONCEPTUAL COST ESTIMATE• DESIGN UPDATE• BUILDING STRUCTURE & EXTERIOR FINISH
OPTIONS• INTERIOR/EXTERIOR FINISHES
2
![Page 3: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/3.jpg)
+
The Preconstruction Process
![Page 4: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/4.jpg)
+
The Preconstruction Process
![Page 5: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/5.jpg)
+
The Preconstruction Process
![Page 6: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/6.jpg)
+
The Preconstruction Process
![Page 7: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/7.jpg)
+
D
ETA
ILLESS
TIME
The Preconstruction Process
MORE ESTIMATE
DESIGN
Programming
Schematic Design
Design Development
ConstructionDocuments Permitting
![Page 8: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/8.jpg)
+
MORE
D
ETA
ILLESS
ESTIMATE
DESIGN
Programming
Schematic Design
Design Development
ConstructionDocuments Permitting
TIME
Programming Estimate
SD Estimate
DD Estimate
CD Estimate
Permitted Documents
Design slows to react to milestone estimate
The Preconstruction Process
![Page 9: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/9.jpg)
+
D
ETA
ILLESS
TIME
The Preconstruction Process
MORE ESTIMATE
DESIGN
Programming
Schematic Design
Design Development
ConstructionDocuments Permitting
![Page 10: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/10.jpg)
+
The Preconstruction Process
![Page 11: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/11.jpg)
+
The Preconstruction Process
![Page 12: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/12.jpg)
+
The Preconstruction Process
![Page 13: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/13.jpg)
+
The Preconstruction Process
![Page 14: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/14.jpg)
+
The Preconstruction Process
![Page 15: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/15.jpg)
+
The Preconstruction Process
GMP #1Demolition and
Abatement
GMP #2Sitework and
Building
![Page 16: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/16.jpg)
Design Update• Emc2 prepared Design Development Drawings
o CORE updating Estimateo Emc2 reviewed design & systems with District Staff
• CORE presenting Abatement and Demolition GMPo Work to take place November / December
• Construction Drawings Planned to be Completed around end of November
• Construction GMP in January• Construction to start February with Completion
December 2016
16
![Page 17: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/17.jpg)
o Circulation• Parking Alternates, Reuse Existing Paving
(under new paving)o Utilities
• Reviewing Existing Water Sourceo Grades / Drainage
• Surface Flow / Stepped Buildings
17
![Page 18: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/18.jpg)
o Current Building Area = 62,880o 36 Classroom Spaces
• 24 Typical Classrooms (Classroom Wings)
• 4 Typical Classrooms at Building Center
• 4 NLI classrooms + 1 HLI Classroom
• 1 Music Room (at Platform)• 2 Special Needs Rooms
o 6 Future Classrooms Planned for at end of classroom wings
18
![Page 19: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/19.jpg)
Enlarged Core & MPR
19
![Page 20: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/20.jpg)
Typical Classroom Wing
20
![Page 21: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/21.jpg)
o Materials & Finishes• Wood Framed Building Structure• Masonry Veneer with Prefinished Metal Wall Panels• Single Ply Roofing• Aluminum Windows• Hollow Metal (Steel Doors and Frames)
21
![Page 22: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/22.jpg)
22
![Page 23: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/23.jpg)
o New Buildings integrating with Jr. High & High School Buildings (Unity of District)• Materials• Colors• Design Features
Continuity in Design
23
![Page 24: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/24.jpg)
Structure & Exterior Options
• Base Bid: Wood Studs with EIFS $14,524,024
Exterior Skin Analysis• Option 1: Wood Studs with masonry + $270,000
veneer to 9 feet & metalpanels above
• Option 2: Wood studs with Fiber ($53,000)Cement Board Siding
Structural Framing Analysis• Option 1a: Concrete Masonry Unit (CMU) + $945,000
Painted exterior walls, metal studinterior walls, wood roof structure
• Option 1b: Concrete Masonry Units (CMU) at + $255,000interior corridor walls (furring onnon-corridor sides)
• Option 2: Concrete Masonry Units (CMU) + $1,705,000Painted exterior walls, metal studinterior walls, wood roof at center,steel roof structure at wings
24
![Page 25: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/25.jpg)
Base Bid- EIFS
25
![Page 26: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/26.jpg)
Exterior Finish Option 1-Masonry Veneer & Metal
Panels
Masonry Veneer
Metal Panels
26
![Page 27: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/27.jpg)
Structural Framing Option – Painted CMU
27
![Page 28: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/28.jpg)
Interior Floor Finishes
28
![Page 29: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/29.jpg)
Interior Floor Finishes
29
![Page 30: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/30.jpg)
Interior Floor Finishes
30
![Page 31: TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4, 2015 1](https://reader035.vdocuments.site/reader035/viewer/2022070415/5697bfac1a28abf838c9bc2d/html5/thumbnails/31.jpg)
Interior Floor Finishes
31